84th Congress, 1st Session   -      -           -    -      -   House Document No. 4, Vol. 2



     ANNUAL REPORT, DEPARTMENT OF THE ARMY
             Fiscal Year Ended June 30, 1954



                  ANNUAL REPORT OF THE

         CHIEF OF ENGINEERS
                                        U. S. ARMY

                      ON CIVIL WORKS ACTIVITIES


                                          1954
                                 IN TWO VOLUMES

                                           Vol. 2




                                         UNITED STATES
                                 GOVERNMENT PRINTING OFFICE

                                        WASHINGTON : 1954
                                                  CONTENTS

                                                                                                                                                  Page
NEw ENGLAND DIVISION..                   .    .   .   .   .      .    .      .   .   .   .       .       .   .   .       .   .    .       .         3
NORTH ATLANTIC DIVISION:
    New York, N. Y., district-............                                                                                                         87
    Philadelphia, Pa., district-.......-...-.........                                                                                             157
    Baltimore, Md., district.......                           ------------                                                                        195
    W ashington, D . C., district --                      --....
                                                           .........................                                                              243
    Norfolk, Va., district..      ..........                                                                                                      269
SOUTH ATLANTIC DIVISION:
    W ilmington, N . C., district.... .............................        ... . . . . . . . .                                                    297
    Charleston, S. C., district --................ . ....             ..............                                                              315
    Savannah, Ga., district..... . . . . . . . . . . . . . .. . . . . .                                                                           329
    Jacksonville, Fla., district ........            .              .               .           . .--                                             347
    M obile, Ala., district ......      .          .         .                      ---..... ..                                                   413
LOWER MISSISSIPPI VALLEY DIVISION:
    New Orleans, La., district..............                                                                                                      455
    Vicksburg, M iss., district.......      ......... .......-                                                           -        -               523
    M emphis, Tenn., district-........ ....           .......                        .       .       .       .       .       .        .           543
SOUTHWESTERN DIVISION:
    Galveston, Tex., district-.. .......              - - - - - - - -                    --                                                       551
    Fort Worth, Tex., districtL.................                        .          .        .                                                     603
    Albuquerque, N. M ex., district .......... ____........ .......... .              .   .   .                                                   629
    Little R ock, Ark., district ......... .....-....    ... . ........   ....... . . . . . . .                                                   643
    Tulsa, Okla., district .... ..     . ...                                                                                                      6...
                                                                                                                                                  671
UPPER MISSISSIPPI VALLEY DIVISION:
    St. Louis, M o., district .............................                                                                                       705
    Mississippi River between the Missouri River and Minneapolis, Minn.......                                                                     733
    Rock Island, Ill., district-..........            .          .        .      .   .                                                            747
    St. Paul, M inn., district ...-       ................. ....... .. .........   .   .                                                          761
MisSOURI RIVER DIVISION:
    Kansas City, Mo., district ..... ...........-                    ---   ------                                                                 793
    Omaha, Nebr., district.....................                                                                                                   825
    Garrison, N. Dak., district                   -------------------------------------                                                           849
    Fort Peck, Mont., district ............            .       .        .      .                                                                  857
OhIO RIVER DIVISION:
    O hio River............-------------............. ........-------------
                                                                      -- ------------ ---.....................                                    869
    Nashville, Tenn., district-----...---------------------------------                                                                           879
    Louisville, Ky., district-----........---------------------.                                                                                  911
    Huntington, W. Va., district...........-----------------------------------                                                                    949
    Pittsburgh, Pa., district.. ...........                 .        .......... ....    ___.........................                              983
GREAT LAKES DIVISION:
    Duluth, Minn., district ................-...................-                                 1031
    Milwaukee, Wis., district.............-                                                       1053
    Chicago, Ill., district-....----------......   .-----------------------------                 1115
    Detroit, Mich., district-----.....           ..          ----------------------------------   1151
    Buffalo, N. Y., district ......-                                                -     -        1185
    Survey of Northern and Northwestern lakes.-.. __............__.                  _____ ____.. 1239
SOUTH PACIFIC DIVISION:
    Los Angeles, Calif., district .............                                                                                              1249
    San Francisco, Calif. district-----..........  .....                                                                                    1301
                                                                                                                                 ..-----------------------------
    Sacramento, Calif., district ........------..........                                                                          _-        1349
                                                                                                                                              1
2                                                               CONTENTS

                                                                                                                                                   Page
NORTH PACIFIC DIVISION:
     Portland, Oreg., district ..                                      _                                                                          1407
                                                                                                                                                  1..-----------------
     Seattle, Wash., district.......                       .......             ...............--------------------------------       ..-------.    481
     Walla Walla, Wash., district                                ...... .......-----------------------------------                                1527
     Alaska district.........................                     ....         .......---------------------------------------------               1543
The Board of Engineers for Rivers and Harbors ........------------------------                                                                    1551
The Beach Erosion Board....----------------------------------------                                                                                557
California Debris Commission ...................                                .......-------------------------------------                      1561
Mississippi River Commission .                                      ...
                                                 --------............           ..               ..------------------------..-----...             1575
Waterways Experiment Station------------------------------...---                                                                                  1629
Permanent International Association of the Congresses of Navigation......--------                                                                 1631
Interoceanic Canal surveys.................................................................---------------------------------------...             1635
Investigations and supervision of projects under the Federal Water Power Act..                                                                    1637
Miscellaneous Civil Works..............                             ...----------------       ....-----------------------....
                                                                                                                 ..........................       1639
      IMPROVEMENT OF RIVERS AND HARBORS IN THE
                               NEW ENGLAND DIVISION

   The New England Division, an operating division with both
district and division functions, comprises all of New England ex-
cept western Vermont and small portions of Massachusetts and
Connecticut along their western boundaries, and includes small
portions of southeastern New York, all embraced in the drainage
basins tributary to Long Island Sound and the Atlantic Ocean east
of the New York-Connecticut State line. It also includes Fishers
Island, N. Y.
                                              IMPROVEMENTS

                     Navigation                                              Flood Control
1.   Corea Harbor, Maine................             4    33.   Merrimack River Basin, N. H.
2.   Northeast Harbor, Maine.......                  4            and Mass....................            56
3.   Penobscot River, Maine-....._                   5    34.   Franklin Falls Reservoir,
4.   Belfast Harbor, Maine..............             7            Merrimack River Basin,
                                                                   N. H ......... ....... .............    58
5.   Kennebec River, Maine ..........                8    35.   Edward McDowell Reservoir,
6.   Portland Harbor, Maine........-                10            Merrick River Basin, N. H..             59
7.   Cape Porpoise Harbor, Maine.                   12    36.   Blackwater Reservoir, Mer-
8.   Kennebunk River, Maine .....                   13            rimack River Basin, N. H....
9.   Isles of Shoals Harbor, Maine                     37.      Blackstone River Basin, Mass.
         and N. H-..........                         14            and R. I-...................... ....    62
10.   Newburyport Harbor, Mass                       15 38.      Thames River Basin, Conn,
11.   Gloucester Harbor and An-                                    R. I. and Mass................
         nisquam River, Mass.........                17 39.      Mansfield Hollow Reservoir,
12.   Boston Harbor, Mass................            19            Thames River Basin, Conn.               66
                                                        40.      Connecticut River Basin, Vt.,
13.   Dorchester Bay and Neponset                                  N. H., Mass., and Conn ......           67
         River, Mass .........................       23 41.      Victory Reservoir, Connect-
14.   Town River, Mass................               24            icut River Basin, Vt...........         71
15.   Hingham Harbor, Mass........                   25 42.      Union      Village          Reservoir,
16.   Plymouth Harbor, Mass............              26            Connecticut River Basin, Vt             71
17.   Cape Cod Canal, Mass..............             28 43.      Ball Mountain Reservoir,
18.   Pollock Rip Shoals, Nan-                                     Connecticut River Basin, Vt             73
         tucket Sound, Mass..............            31    44.   Surry Mountain Reservoir,
19.   Cross Rip Shoals, Nantucket                                  Connecticut River Basin,
         Sound, Mass ..................              :33            N. H........ ...... ..........         74
                                                     33 45.      Birch Hill Reservoir, Con-
20.   Cuttyhunk Harbor, Mass.....                                  necticut River Basin, Mass..            75
21.   Fall River Harbor, Mass.......-..              34 46.      Tully Reservoir, Connecticut
22.   Providence River and Harbor,                                 River Basin, Mass................       77
         R. I .................... .......... ....
                                                .    36 47.
                                                                 Knightville Reservoir, Con-
23.   Seekonk River, R. I.............               38            necticut River Basin, Mass_             78
24.   Pawcatuck River, R. I. and                        48.      Chicopee, Connecticut River
         Conn ........................ .........     39            Basin, Mass..................           79
25.   New London Harbor, Conn ....                   41 49.      West Springfield, Connecticut
26.   Thames River, Conn................             42            River Basin, Mass...............        81
27.   Connecticut            River        Below         50.      Winsted, Connecticut River
                                                                   Basin, Conn....................         82
         Hartford, Conn-............                 44 51.                                                83
                                                                 Inactive Projects.................
28.   Milford Harbor, Conn...........                46 52.      General Investigations ........       _   84
29.   Southport Harbor, Conn .......                 48 53.      Inspection of Completed Flood
30.   Norwalk Harbor, Conn.....-                     49            Control Works........................   84
31.   Stamford Harbor, Conn ..........               51 54.      Flood Control Work Under
32.   Inactive Projects......            ........    53            Special Authorization............       85
               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                      1. COREA HARBOR, MAINE
   Location. This harbor, locally known as Indian Harbor, lies at
the southeasterly extremity of the town of Gouldsboro and just
westerly of the entrance to Gouldsboro Bay, about 12 miles east of
Bar Harbor, Maine. (See U. S. Coast and Geodetic Survey Chart
No. 305.)
   Existing project. This provides for an anchorage basin 8 feet
deep at mean low water, 600 feet long in an east and west direc-
tion, and 400 feet wide in a north and south direction. The mean
tidal range is 10.5 feet and the extreme 12 feet.
   The cost of new work for the completed project was $31,707.
There is no approved estimate of cost for maintenance.
   The existing project was approved by the River and Harbor Act
of August 30, 1935. The latest published map is in the project
document (Rivers and Harbors Committee Document No. 27, 74th
Congress, 1st Session).
   Local cooperation.                         None required.
  Terminal facilities. There are 21 wharves, 15 of which are
small and cannot be approached by vessels at low tide. The
wharves are privately owned. Facilities are considered adequate
for present commerce.
   Operations and results during fiscal year.                                                            Maintenance dredg-
ing, by contract, to restore project depth in the 8-foot anchorage
basin was started on July 29, 1953, and completed on September
12, 1953. During this period 23,851 cubic yards of ordinary ma-
terial and 48.8 yards of boulders were removed at a cost of $57,318,
all maintenance funds.
   Condition at end of fiscal year.                                          The existing project was com-
pleted in 1938. The controlling depth at mean low water was 7
feet (1953).   The costs under the existing project have been
$90,869, of which $31,707 was for new work and $59,162 was for
maintenance.
                                             Cost and fnanial summary

                                                         Fiscal year ending June 30                                               Total to June
                                                                                                                            __   30, 1954, includ-
                                                                                                                                 ing fiscal years
                                      1950             1951                1952            1     1953               1954           prior to 1950
New work:                                                                                                                                    ,70
   Appropriated -     -         -    -     -       --.      . .             . . .
                                                                      . ---------..    .        . . .          .i----------_$31,707
   Cost .    .       ..-----.------------------------------..---........                   I..................                             31,707
Maintenance:
   Appropriated ..               ..      ......                              $1, 500            _$63, 531         -$5,     869             59,,162
   Cost -- - --      -       ;- ----                          --              1,031 1                   813          57,318                59,162


                              2. NORTHEAST HARBOR, MAINE
   Location. This harbor is a small cove, indenting the south
shore of Mount Desert Island, Maine. It lies just east of the en-
trance to Somes Sound, about 13 miles southwest of Bar Harbor.
 (See U.S. Coast and Geodetic Survey Charts Nos. 306 and 1202).
   Existing project. This provides for a channel and anchorage 10
feet deep between the 10-foot natural contour and proposed town
landing, and 7-foot anchorage areas contiguous to the existing
natural channel. The project depths refer to mean low water.
                RIVERS AND HARBORS-NEW ENGLAND DIVISION                                                               5
The mean tidal range is 10.3 and the spring range is 11.7 feet.
   The estimate of cost for new work (1954) is $160,000. The
latest (1950) approved estimate for annual cost of maintenance
is $1,500.
   The existing project was authorized by the River and Harbor
Act of March 2, 1945 (H. Doc. 132, 76th Cong., 1st sess.). The
latest published map is in the project document.
   Local cooperation. Local interests have fully compiled with all
requirements of local cooperation except for construction of a
public landing. Funds have been appropriated for this purpose
and the construction will be started as soon as the disposal area
on which the landing will be located has consolidated sufficiently to
bear the construction equipment.
   Terminal facilities. There are 14 privately owned landings, 2
of which are open to the public without charge, and one publicly
owned temporary landing.
   Operationsand results during fiscal year. Improvement dredg-
ing, by contract, hydraulic process, of a channel approximately
250 to 650 feet wide, 800 feet long and 10 feet deep at mean low
water; and two anchorage areas approximately 18 acres in total
extent and 7 feet deep at mean low water was completed. During
the period 166,880 cubic yards of ordinary material were removed.
Costs during the fiscal year were $133,449, all for new work.
   Condition at end of fiscal year. Construction of the existing
project, initiated in May 1954, was completed in June 1954. The
controlling depths at mean low water are as follows: 10 feet in
the 10-foot channel (1954) ; 7 feet in the northerly 7-foot anchor-
age (1954); 7 feet in the 7-foot southerly anchorage (1954).
Costs under the existing project have been $133,449, all for new
work.
                                               Cost and financial summrnr'!

                                                             Fiscal year ending June 30                  Total to June
                                                                                                        39,1954,includ-
                                                                                                        ing fiscal years
                                     1950                   1951         1952        1953    1954         prior to 1950

New work:
    Appropriated       ----------------------------------------------                       $150, 000          $150, 000
    Cost---------       ----------------------------------------------                       133,449            133, 449


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954.............................--------------.                  $9,852
    Unobligated balances available for succeeding fiscal year ending June 30,
    1955...........................----....................-----------......                                            9 ,852
    Estimated additional amount needed to be appropriated for completion
    of existing project .............................................................................................. 10 ,000

                                 3. PENOBSCOT RIVER, MAINE
  Location. This river drains a large number of lakes and small
streams in north central and eastern Maine and, after assuming
definite character as a stream, flows about 100 miles in a southerly
direction through the middle of the State, discharging into Pen-
obscot Bay, about 90 miles northeast of Portland, Maine. (See
U. S. Coast and Geodetic Survey Chart No. 311.)
  Previous projects. Adopted by the River and Harbor Act of
6                 REPORT OF CHIE'           OF' ENGINEERS. U. S. ARMY, 1954

July 11, 1870, and modified by the River and Harbor Acts of March
3, 1899, and July 11, 1947. For further details of'previous
projects, see page 1732 of Annual Report for 1915, page 48 of
Annual Report for 1938, and page 31 of Annual Report for 1949.
   Existing project. This provides for dredging to a depth of 22
feet between Winterport and Bucksport, about 16 miles below
Bangor; for straightening, widening, and deepening to 15 feet
the channel near Stearns Mill and near Crosbys Narrows from 3
to 4.5 miles below Bangor; and for deepening the harbor at Bangor
to 14 feet and widening it along the Bangor front, giving an addi-
tional width of from 100 to 300 feet for a length of about 2,000
feet. The project depths refer to mean low water, which is 3 feet
above extreme low tide. The mean range of tide at Bangor is 13.1
feet, and the extreme about 15 feet.
   The cost for new work for the completed project was $292,020
exclusive of amounts expended under previous projects. The
latest (1950) approved estimate for annual cost of maintenance
is $3,000.
   The existing project was authorized by the following river and
harbor acts:

       Acts                        Work authorized                                  Documents

July    5, 1884   Widening the channel at Bangor and Crosby's Nar-      S. Ex. Doc. 44, 48th Cong., 1st sess.,
                   rows.                                                  and Annual Report 1884, p. 475.
Aug. 11, 1888     Dredging between Winterport and Bucksport    -....    H. Ex. Doc. 133, 50th Cong., 1st
                                                                          sess., and Annual Report 1888,
                                                                          p. 425.
July 31, 1892     Widening the channel at Bangor.                 _ _
                                                         ___ ___ _.       . Ex. Doc. 37, 52d Cong., 1st ses.,
                                                                        11..H
                                                                          and Annual Report 1892, p. 553.
Mar.    2, 1907   Further widening of the harbor at Bangor   ..   ------H. Doc. 739, 59th Cong., 1st sess.
                                                                           (Contains the latest published
                                                                           map. Other maps are in H. Doe.
                                                                          652, 71st Cong., 3d sess.)



   Local cooperation. None required.
   Terminal facilities. The river front of Bangor has 12 wharves,
most of which are of the timber-crib stone-ballasted type. Exten-
sive improvements and alterations are in progress at all the oil
terminals to handle increased receipts of petroleum products.
Eleven of the wharves have physical connection with a railroad.
On the east side of the river at Brewer, opposite Bangor, there is
one water terminal, a coal handling plant having mechanical ap-
pliances and three petroleum products storage plants. The re-
.mainder of the terminals on the east side of the river are in poor
condition. At South Brewer there is a large pulp and paper plant
which has water connections, oil pumping and storage facilities.
There are a number of private wharves open to the public at
moderate charges. At Bucksport on the north side of the river
there are three important terminals, one a coal handling plant
and two used by a large paper manufacturing plant which has
terminal facilities for the receipt and storage of oil products and
pulpwood. The terminal facilities are considered adequate for
existing needs.:
   Operations and results during fiscal year. A condition survey,
by hired labor, to determine the extent of shoaling in the 22-foot
project channel in the vicinity of Frankfort Flats and Lawrence
                 RIVERS AND HARBORS-NEW ENGLAND DIVISION

Cove was completed at a cost of $1,939, all maintenance funds.
  Condition at end of fiscal year. The existing project was com-
pleted in 1913. The controlling depths at mean low water were
about 14 feet from IBucksport to Winterport (1937) ; channel op-
posite Lawrence Cove about 19 feet (1954) ; channel at Frankfort
Flats 22 feet (1954) ; thence 15 feet to Stearns Mill; thence 14
feet to Bangor, except for a shoal area in Bangor Harbor on the
Brewer side, where the least depth is 4.6 feet (1937). The costs
under the existing project have been $388,182, of which $292,020
was for new work and $96,162 was for maintenance.
                                          Cost and financial summary

                                                     Fiscal year ending June 30                          Total to June
                                                                                                        30,1954, includ
                                                                         11ing                              fiscal years
                                   1.9_50          1951             1952         1953   i    1954         prior to 1950
New work:
    Appropriated          ----------- ------------------------------------                  -----------             020
                                                                                                                $501,
   Cost ..-------------         --------------------- ---------------------------------                         1501, 020
Maintenance:
   Appropriated--------   - -------------------------------------------...                    $3, 100             97, 323
   Cost----------          ------------------------------------    ----------                  1,939              96,162

  I Includes   $209,000 for new work for previous projects.


                                 4. BELFAST HARBOR, MAINE
   Location. This harbor is located on the westerly side of Pen-
obscot Bay near its head and is about 25 miles north of Rockland
Harbor, which is near the mouth of Penobscot Bay. (See U. S.
Coast & Geodetic Chart No. 208.)
   Previous project. Adopted by River and Harbor Acts of May
20, 1826 and August 14, 1876. For further details'see page IX of
Annual Report for 1897.
   Existing project. This provides for dredging the main channel
to a depth of 15 feet for a minimum width of 220 feet and areas
on the east and west sides to 8 and 13 feet, respectively. The mean
range of tide is 9.7 feet.
   The cost of new work for the completed project was $39,561,
exclusive of amounts expended on previous projects.
   The existing project was authorized by the River and Harbor
Act approved September 19, 1890. The latest published map is in
project document (H. Ex. Doc. No. 81, 51st Cong., 1st sess.).
   Local cooperation. None required.
   Terminal facilities. There are nine wharves located on the
south side of the harbor below the highway bridge. Construction
consists mainly of pile and timber piers extending from timber or
stone bulkheads. A spur railroad track runs close to the back of
eight of the wharves. Six wharves are in good repair and three
are in poor condition. One wharf is used for receipt of fish and
one for tie up of towboats. The remaining seven are not pres-
ently used for waterborne commerce.           There are no publicly
owned wharves. The facilities are considered adequate for the
present needs of commerce.
   Operations and results during fiscal year. A condition survey,
by hired labor, to determine the extent of shoaling in the 15-foot
8               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

channel and the 8 and 13-foot areas was completed during the fis-
cal year at a cost of $1,147, all maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1897. The controlling depths in 1954 were 13 feet in the
15-foot area; 11 feet in the 13-foot area; and 3 to 8 feet in the 8-
foot area. The costs under the existing project have been $40,708,
of which $39,561 was for new work and $1,147 was for main-
tenance.
                                             Cost and financ ial
                                                               summnaryi


                                                                           dingal
                                                                         i...s . ying
                                                                                  ...            .    ..                  fisc includ-
                                                                                                                      30,1954,   y ars
                                      1950              1951              1952               1953          1954        prior to 1950
New Work:
   Appropriated-
   Cost   ---------------------
Maintenance:
                      ------     --   ----   --------                         ------
                                               -----------------------------------------------
                                                                                                 - -$61,                            561
                                                                                                                                '61, 561
   Appropriated        _._._ .                            .    ..-        _            -         -         $1, 500               1, 500
     Cost         _ .---------------------       ------------ ----------                   ------------      1, 147              1, 147

    ' Includes $22,000 for new work for previous projects.



                                      5. KENNEBEC RIVER, MAINE

   Location. Kennebec River drains a large number of lakes and
minor streams, and flows from Moosehead Lake about 150 miles in
a southerly direction and discharges into the Atlantic Ocean about
25 miles east of Portland. (See U. S. Coast and Geodetic Survey
Charts Nos. 288, 289, and 314.)
   Previous projects. The first project was adopted by the River
and Harbor Act of March 2, 1827. Modifications and additions
were authorized by River and Harbor Acts of August 30, 1852,
June 23, 1866, July 11, 1870, March 3, 1871, March 3, 1873, March
3, 1881, and August 11, 1888. For further details of previous
projects see page 1735 of Annual Report for 1915, and page 52 of
Annual Report for 1938.
   Existing project. This provides for a channel 27 feet deep and
not less than 500 feet wide, extending from the mouth to a point
about 0.6 mile above the bridge at Bath; thence to Gardiner a
channel not less than 150 feet wide, with a depth of 17 feet at
Beef Rock Shoal, at the foot of Swan Island, 18 feet deep through
rock at Lovejoy Narrows, near the head of Swan Island, decreas-
ing to 16 feet deep at Gardiner; a channel west of Swan Island
100 feet wide, 12 feet deep, except at the upper shoal, where the
depth was to be 15 feet; and a channel 125 feet wide and 11 feet
deep from Gardiner upstream to Augusta, at the head of naviga-
tion. The section of river included in the project is about 44
miles in length. The work includes dredging, rock excavation,
and two riprap training walls. The project depths refer to mean
low water. The mean tidal range is 8.4 feet at the mouth of the
river, 6.4 feet at Bath, 5.3 feet at Richmond, 5 feet at Gardiner,
and 4.1 feet at Augusta. The spring tides are about 1 foot greater
at the mouth and about 0.5 foot greater at Augusta.
                RIVERS AND HARBORS-NEW ENGLAND DIVISION                                                    9
   The estimate of cost for new work (1954) is $1,220,000, exclu-
sive of amounts expended under previous projects. The latest
(1950) approved estimate for annual cost of maintenance is
$8,000.
   The existing project was authorized by the following River and
Harbor Acts:

    Acts                          Work authorized                                   Documents
June 13, 1902   Channel between Augusta and Gardiner, Maine-.            H. Doc. 262, 56th Cong., 1st sess.'
Mar. 2, 1907    Channel below Gardiner, Maine ..-..-    .    ...-   _    H. Doc. 321, 59th Cong., 2d sess.'
Mar. 4, 1913    Channel west of Swan Island .   .---                     H. Doc. 746, 62d Cong., 2d sess.'
Oct. 17, 1940   27-foot channel from mouth to Bath-....   ............
                                                                  _      S. Doe. 55, 77th Cong., 1st sess.'


1 Contains the latest published maps.

   Recommended modification of project. In House Document
No. 2107, 64th Congress, 2d session, it was recommended that the
improvement and maintenance of the channel west of Swan Island,
near the town of Richmond, be abandoned.
   Local cooperation. None required.
   Terminal facilities. Wharves suitable for landing or loading
are located at Bath, Woolwich, Richmond, Randolph, Gardiner,
Hallowell, and Augusta. Of the 24 wharves located at Bath, 5 are
publicly owned and 19 privately owned, about one-third of which
are in poor repair and are little used. Rail connections are avail-
able at 19 of the wharves at Bath. Depths alongside range from 12
to 25 feet. At the other points named above there are 16 wharves
in usable condition. All but one are equipped with mechanism for
handling passengers and freight. Those open to the public on
equal terms are two at Hallowell and one each at Randolph and
Augusta. None is publicly owned. The facilities are considered
adequate for existing commerce.
   Operationsand results during fiscal year. Maintenance dredg-
ing, by Government hopper dredge Lyman, to restore project
depth of 27 feet in the channel from the mouth of the river to the
Carlton Bridge at Bath, was started on August 25, 1953, and com-
pleted on September 24, 1953. During the period 58,390 cubic
yards, pay place plus natural shoaling, of ordinary material were
removed at a cost of $57,620, all maintenance funds.
   Condition at end of fiscal year. The existing project is sub-
stantially complete. To complete the project, there remains the
dredging of the 27-foot channel from Bath Iron Works Corpora-
tion to 0.6 of a mile above the bridge at Bath. The controlling
depths at mean lowwater in the Kennebec River from the mouth to
Doubling Point are 27 feet (1953), with the exception of a shoal
area along the northerly limit of the channel northwest of North
Sugar Loaf Island, having a controlling depth of 19 feet; 26 feet
from Doubling Point, to the Bath Bridge (1953) ; 13 feet from
Abagadasset Point to the Gardiner-Randolph Bridge, thence 8 feet
to Augusta for the project channel widths (1942).        The costs
under the existing project have been $1,363,707, of which $1,090,-
529 was for new work and $273,178 was for maintenance.
10             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                      Cost and financial summary

                                             Fiscal year ending June 30                               Total to June
                                                                                                     30, 1954, includ-
                                                                                                     ing fiscal years
                               1950          1951         1952                   1953      1954       prior to 1950
New work:
   Appropriated--------           ----------------------                      ---.-
                                                                             -$1,                             599, 940
     Cost--.......-....                  _     -....     ..            .------              --.....         1,599,940
Maintenance:
     Appropriated--------
                        ........-       $30,000 ------        --- --------          $60   $57, 620            273,178
     Cost. ......    -.     -            27, 547
                               ---...........                    $72             2, 321    57, 620            273, 178


Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project............. ...............     $129, 471
                                                                       .......
1Includes $509,411 for new work for previous projects.

                            6. PORTLAND HARBOR, MAINE
   Location. This harbor is on the southwestern coast of Maine,
about 100 miles northeast of Boston, Mass. (See U. S. Coast and
Geodetic Survey Chart No. 325.)
   Previous projects. Adopted by joint resolution of June 5, 1868,
and River and Harbor Act of June 10, 1872. For further details
see page 1736 of Annual Report for 1915, and page 40 of Annual
Report for 1936.
   Existing project. This provides for an anchorage area 35 feet
deep at mean low water, approximately 170 acres in area, north-
west of House Island; an anchorage area off the eastern end of the
city, with a minimum depth of 30 feet; dredging a 35-foot channel
from the westerly side of the Maine State pier in the lower part of
the main harbor through its channel of approach to the sea; dredg-
ing to 35 feet the present 30-foot channel from the Maine State
pier to Portland Bridge for its full width, thence to Vaughan
Bridge for a width of 400 feet, thence to the Boston & Maine Rail-
road bridge for a width of 300 feet; dredging a 35-foot turning
basin easterly of Vaughan Bridge; and construction of stone
breakwater about 900 feet long from Spring Point to Spring Point
Light; for a channel 30 feet deep and 300 feet wide from the an-
chorage to the Grand Trunk Bridge at the mouth of Back Cove; for
rock excavation to give a depth of 14 feet between the Grand
Trunk and Tukey's Bridges, and a channel 12 feet deep and 300
feet wide thence to the head of Back Cove; for the removal of two
obstructing ledges in the main ship channel to a depth of 40 feet;
for a stone breakwater about 2,000 feet long on the southerly side
of the mouth of the inner harbor; and the maintenance of Soldier
Ledge Channel in Hussey Sound, Casco Bay, at a depth of 40 feet.
   The project depths refer to mean low water. The mean tidal
range is 8.9 feet, extreme 10.2 feet, though variations as great as
16 feet have been observed under storm conditions.
   The estimate of cost for new work (1954) is $5,003,000 exclu-
sive of amounts expended on previous projects. The latest (1950)
approved estimate for annual cost of maintenance is $40,000.
   The existing project was authorized by the following River and
Harbor Acts:
                   RIVERS AND HARBORS-NEW ENGLAND DIVISION                                                  11
       Acts                          Work authorized                                   Documents
July           Breakwater on southerly side of mouth of inner har-
         4, 1836                                                           H. Doc. 491, 23d Cong., 1st sess.
                bor.
June 23, 1866 Extension of breakwater.
June 3,1896 Dredging to 30 feet over greater part of inner harbor.         S. Doc. 271, 54th Cong., 1st sess.
Mar. 3,1905 Extension of 30-foot depth up Fore River to Boston
(Sundry civil)  & Maine R. R. bridge and in channel of approach
                to Back Cove.
July 25,1912       30-foot anchorage; 14 feet at entrance to Back Cove;    H. Doec. 489, 62d Cong., 2d sess.
                    restoration of 12-foot depth in Back Cove and 30-
                    foot depth in the approach as well as in lower part
                    of harbor.
Aug.    8,1917     35-foot depth in lower part of main harbor and the      H. Doec. 71, 65th Cong., 1st sess.
                    channel of approach, and removal of 2 obstructing
                    ledges in main channel.
Mar.    2, 1945    35-foot anchorage, approximately 170 acres in area      H. Doec. 560, 76th Cong., 3d sess.'
                    northwest of House Island.
       Do..._.     Maintenance of Soldier Ledge Channel in Hussey          H. Doc. 730, 79th Cong., 2d sess.
                    Sound, at depth of 40 feet.
July 24. 1946      Deepening 30-foot channel to 35 feet; 35-foot turning   H. Doec. 510, 79th Cong., 2d sess.'
                    basin easterly of Vaughan Bridge; breakwater at
                     Spring Point.

  ' Contains the latest published maps.

   Local cooperation. Fully complied with.
   Terminal facilities. There are 60 wharves in the harbor, of
which 48 are active and 12 inactive and in poor condition. Six of
the wharves are publicly owned, three by the United States Gov-
ernment, one by the State of Maine, one by the city of South Port-
land, and one by the city of Portland. Mechanical handling facili-
ties are available at 28 of the wharves. Railroad connections have
been made to 35 of them. The facilities are considered adequate
for the needs of existing commerce. For a further description of
terminal facilities see Port and Terminal Facilities of Northern
New England, 1941.
   Operations and results during fiscal year. A condition survey,
by hired labor, to determine the extent of shoaling in the 35-foot
project channel was completed during the fiscal year at a cost of
$3,505, all maintenance funds.
   Condition at end of fiscal year. The existing project was about
66 percent completed, the remaining portion consisting of the re-
moval to a depth of 40 feet at mean low water of a ledge located
about 0.5 mile southeast of Portland Head Light at the entrance to
Portland Harbor, dredging the 35-foot anchorage area northwest
of House Island and the dredging of the hard areas in the 35-foot
channel. The controlling depths at mean low water in the various
improved channels of Portland Harbor at the dates they were last
surveyed were: 34 feet in the north and easterly three quarters,
and 29 feet in the remaining quarter of the 35-foot channel from
the sea to abreast the State Pier, thence 33 feet in the northerly
half and 28 feet in the hard areas in the southerly half of the
channel to Portland Bridge; (1954), thence 35 feet in the center
half and 32 feet in the outer quarters to the Vaughan Bridge,
thence 29 feet through the north draw opening of the Vaughan
Bridge, thence 35 feet in the three northerly quarters and 31 feet
in the southerly quarter to the Boston and Maine railroad bridge
 (1954). The costs under the existing project have been $4,172,847,
of which $3,260,398 was for new work and $912,449 for main-
tenance.
12                  REPORT OF CHIEF OF ENGINEERS, U                                                        S.. ARMY. 1954


                                                         Cost and financial summary

                                                                Fiscal year ending June 30                                                 Total to June
                                                                                                                                    _ 30, 1954, includ-
                                                                                                                                      ing fiscal years
                                            1950               1951              1952                1953                1954              prior to 1950
New work:
     Appropriated--------                 $206, 000 -------------....---------                       $21,423              ..------------      1$3, 952, 833
   Cost----------------                     871,015          $166,316            $30,824      ------------------------                         13,952,833
Maintenance:
     Appropriated ..-.          _-.         175, 000         -10, 513            175, 000            -6, 903              $4, 300                 913, 243
     Cost ----------------                  117,918             46,569           160,930                7,167              3,505                  912,449

Other new work data:
    Appropriated for succeeding fiscal year ending June 30, 1955.................. $765, 000
    Unobligated balances avaliable for succeeding fiscal year ending June
    30, 1955.................................................................................---------------------------------------------........ 765,000
    Estimated additional amount needed to be appropriated for completion
    of existing project.........                                                                                                                   977, 602
  1 Includes $692,435 for new work for previous projects.

                                  7. CAPE PORPOISE HARBOR, MAINE
  Location. This harbor is located in the town of Kennebunkport
on the coast of Maine, 27 miles southwest of Portland, Maine, and
about the same distance northeast of Portsmouth, N. H. (See U. S.
Coast and Geodetic Survey Chart No. 1205).
  Existing project. This provides for the removal of ledge rock
in the entrance channel to deepen and straighten the outer portion
so as to give a depth of 18 feet for a width of 200 feet between
Goat and Folly Islands; a channel 16 feet deep over a width of 200
feet through the bar; a combined channel and anchorage between
the bar and the town wharf about 2,150 feet long, 600 feet wide
and 15 feet deep; a channel 100 feet wide and 6 feet deep from the
town wharf in Cape Porpoise Harbor to the head of Porpoise Cove.
All depths refer to mean low water. The mean range of tide is 8.7
feet and the spring range is 9.9 feet. The cost of new work for the
completed project was $175,037, exclusive of $20,000 contributed
by local interests. The latest (1950) approved estimate for annual
cost of maintenance is $1,800 for that portion of the project above
town wharf. There is no approved estimate of cost for mainte-
nance on that portion of the project below town wharf.
   The existing project was authorized by the following river and
harbor acts:
      Acts                                       Work authorized                                                          Documents
Mar. 3, 1899           Channel 200 feet wide and 16 feet deep at entrance,                                H. Doc. 160, 55th Cong., 3d sess.
                        and channel and anchorage 15 feet, 600 feet wide,
                        and about 3,000 feet long within the harbor.
Mar. 2, 1907           Excavation of ledge rock in outer entrance channel to                              H. Doc. 191, 59th Cong., 1st seas.
                        depth of 18 feet, 200 feet wide.
June 30,1948           Channel 100 feet wide and 6 feet deep from town                                    H. Doc. 555, 80th Cong., 2d seas.
                        wharf in Cape Porpoise Harbor to head of Porpoise                                  (Contains latest published map.)
                        Cove.


   Local cooperation. Fully complied with.
   Terminal facilities. Present terminal facilities consist of a
single wharf located on Bickfords Island. This wharf is an open
pile timber structure fronting on the dredged channel for a length
of about 180 feet, with depths alongside of about 6 to 10 feet at
                 RIVERS AND HARBORS-NEW ENGLAND DIVISION                                                                 13
mean low water. Auxiliary equipment consists of three landing
floats, one electrically operated hoist, and two small hand-operated
hoists for handling supplies to and from boats. This wharf is
owned by the town of Kennebunkport and is open to the public
without charge. This wharf is considered adequate for the needs
of the community.
   Operationsand results during fiscal year. A condition survey,
by hired labor, to determine the extent of shoaling in the 6-foot
channel and the 15-foot combined channel and anchorage was com-
pleted during the fiscal year at a cost of $668, all maintenance
funds.
   Condition at end of fiscal year. The existing project was com-
pleted in 1950. An entrance channel 200 feet wide and 16 feet
deep and an anchorage area about 3,000 feet long, 600 feet wide
and 15 feet deep at mean low water were secured in 1902. The
removal of ledges and straightening the outer portion of the chan-
nel for a width of about 190 feet with a depth of 18 feet at mean
low water was secured in 1908. The dredging of the 6-foot chan-
nel was completed in 1950. The controlling depths are: 18 feet in
the outer entrance channel (1942) ; 14 feet in the entrance chan-
nel (1954); 10 feet in the combined channel and anchorage,
 (1954) ; 6.0 feet in the 6-foot channel (1954). The costs under the
existing project have been $175,705, of which $175,037 was for
new work and $668 for maintenance. In addition, $20,000 was
expended from contributed funds.
                                          Cost and financial summary

                                                   Fiscal year ending June 30                                Total to June
                                                                                                   _ __     30, 1954, includ-
                                                                                                            ing fiscal years
                                   1950           1951            1952             1953            1954       prior to 1950

New work:
   Appropriated ....-..            $55, 000        $3, 600     -$2, 065 ------------------------                   1 $175, 037
   Cost____ --- __----              17, 429        39, 107 ----------------------                                   1'175, 037
M aintenance:
   Appropriated-------------                   .       ------------           ------------         -$332                  668
   Cost  ---------------------------------------------------------                                    668                 668


   In addition, $20,000 was expended for new work from contributed funds.

                               8. KENNEBUNK RIVER, MAINE
   Location. The source of Kennebunk River is in the central part
of York County in southwestern Maine. The stream flows about
15 miles in a southeasterly direction and discharges into the At-
lantic Ocean about 30 miles southwest of Portland, Maine. (See
U.S. Coast and Geodetic Survey Chart No. 1205.)
   Existing project. This provides for the construction of a stone
breakwater on the easterly side of the mouth of the river about 550
feet long, a pier or jetty on the westerly side of the mouth about
290 feet long, the construction of a wharf about 700 feet upstream
from the shore end of the breakwater (transferred to Treasury
Department in 1936), the construction of a jetty on the east bank
a short distance farther upstream, and securing a depth of 4 feet
at mean low water for an average width of 100 feet up to Kenne-
bunkport, a distance of about 1 mile, by dredging and rock re-
14               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

moval. The mean tidal range is 9 feet; the extreme 13.5 feet.
Work appears to have been commenced by the State of Massa-
chusetts in 1798, since which date a number of small appropria-
tions have been made for maintenance and further improvement.
The cost of new work for the completed project was $83,584. The
latest (1950) approved estimate for annual cost of maintenance is
$2,000.
  Those portions of the existing project adopted since 1829 were
authorized by the following river and harbor acts:
     Acts                          Work authorized                                         ,                Documents

Mar. 2, 1829     Repair of pier on east side of channel entrance
Aug. 14,1876     Deepening at Wading Place and Mitchells Point _        Annual Report 1875, p. 115.
Sept. 19, 1890   Jetty at Wading Place                                  H. Ex. Doe. 136, 51st Cong., 1st
                                                        .--------------------
                                                                          sess., and Annual Report 1890,
                                                                          p. 471.


   Local cooperation. None required.
   Terminal facilities. There are a total of 10 wharves in the
river. Nine of these are privately owned and one is publicly
owned by the Town of Kennebunkport, Me. None of these have
railroad connections or mechanical handling facilities. All are in
poor condition. The facilities are considered adequate for existing
traffic.
   Operations and results during fiscal year. A condition survey,
by hired labor, to determine the extent of repairs necessary to re-
store the breakwater and jetty at the mouth of the river, in prog-
ress at the beginning of the fiscal year, was completed. Plans and
specifications to restore the breakwater and jetty at the mouth of
the river, by contract, were initiated. Costs were $723, all main-
tenance funds.
   Condition at the end of the fiscal year. The existing project
was completed in 1893. The project depth of 4 feet was restored
in 1950. The costs under the existing project have been $219,727,
of which $83,584 was for new work and $136,143 was for mainte-
nance.
                                      Cost and financial summary

                                                  Fiscal year ending June 30                                          Total to June
                                                                                                               j-    30, 1954, includ-
                                                                                                                     Sing fiscal years
                               1950             1951              1952                   1953           1954          prior to 1950

New work:
   Appropriated --- --.                                      . .         .       .   .     .    .     . .
                                                                                                     =83,      .                    584
   C o st        -- . . .    . .   . -.   . .    .     .   . . .. . . . ..... -.                    .8..                        3 , 58 4
Maintenance:
   Appropriated      . - .     $65, 767     -$3, 524                                      $1,000       120, 000                156, 282
   Cost_____..... . . ..        39, 266       22, 976                -    -_                 138               723            136, 143

             9. ISLES OF SHOALS HARBOR, MAINE AND N. H.
  Location. A group of islands in the open sea about 6 miles
northeast of Portsmouth Harbor, N. H. Three of them, Smutty-
nose, Cedar and Star Islands, are so situated that, with the shoals
connecting them, they afford a small harbor of fair depth, open
only to the west and northwest, known as Gosport Harbor. (See
U. S. Coast and Geodetic Survey Chart No. 330.)
              RIVERS AND HARBORS ----NEW ENGLANI)                                     I)IVISION                              15
  Previous projects. The first work of improvement by the Gov-
ernment was ordered by the Act of March 3, 1821. Subsequent
modifications and additions were authorized by the act of May 7,
1822, and the River and Harbor Act of July 13, 1902. For scope of
previous projects see page 1739 of Annual Report for 1915.
  Existing project. This provides for the construction of three
rough stone breakwaters as follows: One from Smuttynose Island
westwardly to Malaga Island on the north side of the harbor, hav-
ing a length of 240 feet; one extending southeastwardly from
Smuttynose Island to Cedar Island, protecting the harbor on the
east, having a length of 700 feet; and a third extending south-
westwardly from Cedar Island to Star Island, affording protection
from the southeast and south, having a length of 530 feet. The
mean tidal range is 8.7 feet and the extreme 9.9 feet.
   The cost of new work for the completed project was $39,238,
exclusive of amounts expended under previous projects. There is
no approved estimate of cost for maintenance.
   The existing project was adopted by the River and Harbor Act
approved June 25, 1910 (H. Doc. No. 1122, 60th Cong., 2d sess.).
The latest published map is printed in the Annual Report for 1913,
page 1530.
   Local cooperation. None.
   Terminal facilities. There is one wharf near the hotel on Star
Island which is used to accommodate a passenger steamer plying
between Portsmouth, N. H., and the Island during 3 months of the
summer.
   Operations and results during fiscal year. Restoration of the
riprap breakwater between Star and Cedar Islands, by contract,
was started on August 21, 1953, and was still under way at the
end of fiscal year. During the period 1,200 tons of stone were
placed at a cost of $18,163, all maintenance funds.
   Condition at end of fiscal year. The existing project was com-
pleted in 1913. The breakwaters between Smuttynose Island and
Cedar Island are in good condition. The breakwater between Star
Island to Cedar Island is being repaired. The costs under the
existing project have been $92,917, of which $39,238 was for new
work and $53,679 for maintenance.
                                       Cost and financial summary

                                                  Fiscal year ending June 30                                      Total to June
                                                                           __.    ......       .          ....   30, 1954, includ-
                                                                                                                 ing fiscal years
                                1950           1951          1952        1953                      1954           prior to 1950

New work:
   Appropriated .       .              --- ------------ ------      -----------            --- -                          $80, 691
   Cost ..----------    ----------- ------------ ---------------------    ------------                                   -80,691
Maintenance:
   Appropriated---------------      -----------------------      $40, COO      --------                                    74, 262
   Cost-    __       . -.-.                                 -      1,254      $18, 163                                     53, 679

  1Includes $41,453 for new   work for previous projects.

                        10. NEWBURYPORT HARBOR, MASS.
  Location. Newburyport is on the south bank of Merrimack
River, about 2.5 miles above the mouth and about 48 miles by
16              REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954


water north of Boston. (See U. S. Coast and Geodetic Survey
Chart No. 331.)
   Existing project. This provides for two rubblestone jetties,
each 15 feet wide on top at elevation 12 feet above mean low water,
with slopes of 1 on 2 on the seaward face and 1 on 1 on the shore-
ward face; one projecting from the north shore, 4,118 feet, the
other from the south shore, 2,445 feet, converging until 1,000 feet
apart, and then extending seaward parallel to the axis of the chan-
nel for a distance of 1,000 feet; and for partially closing Plum
Island Basin by a timber dike about 800 feet long and 5.5 feet
above mean low water; the object being to create at the outer bar a
permanent channel 1,000 feet wide and at least 17 feet deep at
mean low water, to enable vessels of such draft as can proceed at
high tide to the wharves at Newburyport to enter the river at
mean low water; and a continuous channel from the sea to the
wharves at Newburyport, 15 feet deep and 400 feet wide through
the bar; thence 12 feet deep and 200 feet wide to and including a
widened turning basin in front of the wharves, subject to certain
conditions of local cooperation; pending compliance with these
conditions, the improvement to be in accordance with a plan to
provide a channel 12 feet deep and 400 feet wide through the bar;
thence 9 feet deep and 200 feet wide to and including a widened
turning basin in front of the wharves. The mean range of tide is
7.9 feet at the bar and 7.8 feet at Newburyport.
   The estimate of cost for new work (1954) is $650,000, exclusive
of $34,000 to be contributed by local interests. The latest (1950)
approved estimate for annual cost of maintenance is $25,000.
   The existing project was authorized by the following River and
Harbor Acts:
     Acts                          Work authorized                                    Documents

June 14, 1880   Construction of rubblestone jetties.
June 25, 1910   Dredging the bar at entrance to harbor....------------...   Annual Report, 1910 p. 59.
Mar. 2, 1945    Dredging channel from sea to wharves and a widened          H. Doc. 703, 76th Cong., 3d sess.
                turning basin.                                               Contains latest published map.


  Local cooperation. The River and Harbor Act of March 2,
1945, provides that local interests furnish free of cost to the
United States suitable spoil disposal areas, properly bulkheaded,
for new work and for subsequent maintenance, when and as re-
quired; hold and save the United States free from claims for dam-
ages resulting from the improvement; and contribute one-third of
the first cost, but not to exceed $34,000.
   Terminal facilities. The terminal facilities consist of 16
wharves extending along a frontage of about 3,500 feet of the south
bank of the Merrimack River below the highway bridge, and 1
small pier on the north side of the river.
  The terminal facilities are considered adequate for existing com-
merce. For full description see Port and Terminal Facilities of
the Ports of Northern New England, 1941.
  Operations and results during fiscal year. A condition survey,
by hired labor, to determine extent of shoaling in the 12-foot chan-
nel through the bar and the 9-foot channel to the wharves was in
                RIVERS AND HARBORS-NEW ENGLAND DIVISION                                                                                 17

progress at the end of the fiscal year. Costs were $1,933, all main-
tenance funds.
   Condition at end of fiscal year. The existing project was about
69 percent completed, the remaining portion consisting of dredg-
ing the channel from the sea to the wharves at Newburyport and a
widened turning basin, the depths to be determined by the com-
pliance of local interests with the conditions of local cooperation.
The north jetty was completed in 1914; the south jetty was com-
pleted, except for a length of about 30 feet at its outer end, in 1905.
These jetties are in good condition and completion of the south
jetty is not now considered necessary. Plum Island Basin was
partially closed in 1883 by the construction of a timber dike.
North Rock was removed in 1901. The latest survey (1946) over
the bar at the mouth of the river showed a channel with a con-
trolling depth of 10 feet at mean low water for a width of 300 feet,
and 6 feet to the wharves at Newburyport. The bar consists of
shifting sand, and conditions change rapidly and frequently. The
costs under the existing project have been $757,480, of which
$463,843 was for new work and $293,637 for maintenance.
                                                Cost and financial summary

                                                                Fiscal year ending June 30                                   Total to June
                                                                                                            _30,                1954, includ-
                                                                                                                             ing fiscal years
                                        1950                1951          1952              1953               1954           prior to 1950

New Work:
   Appropriated- .....    _      ....          _.---- .. ........                ---- _ _     .. ........                           $463, 843
   Cost---         .....----.. ------                      - .---------- ---------                                                   463, 843
Maintenance:
   Appropriated ....--------               $217 -.                                                                 $2, 000           293, 704
   Cost-----------------......              217 ------              -----------------------                         1,933            293,637


Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project __                 _-__-_--..___
                                             . ....... ____ ..........     $186, 157

    11.   GLOUCESTER                      HARBOR                    AND     ANNISQUAM                         RIVER,          MASS.

   Location. Gloucester Harbor is situated at the southern ex-
tremity of Cape Ann, about 23 miles northeast by water from
Boston Harbor. Annisquam River is a narrow tidal waterway
extending across the base of Cape Ann from Gloucester Harbor on
the south side to Ipswich Bay on the north side, a distance of ap-
proximately 4 miles. A reach of this waterway, at the Gloucester
Harbor end, for a length of about 1,800 feet, is known as the Blyn-
man Canal. (See U. S. Coast and Geodetic Survey Chart No. 243.)
   Previous projects. Projects for Gloucester Harbor were
adopted by River and Harbor Acts of June 10, 1872, August 5,
1886, and June 3, 1896. There were no previous projects for
Annisquam River. For further details see page 1740 of Annual
Report for 1915, and page 50 of Annual Report for 1937.
   Existing project. This provides:
   Gloucester Harbor: a. For a rubblestone breakwater 2,250 feet
long, surmounted by a superstructure of dry walls of heavy split
stone enclosing a core of rubblestone from Eastern Point over
Dog Bar to Cat Ledge.
  b. For the removal of three ledges in the inner harbor, 1 to 12
 18             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

feet and 2 to 15 feet depth at mean low water, and five ledges in
the outer harbor, 4 to 18 feet and 1 to 25 feet depth at mean low
water, aggregating a total of 2,206 cubic yards, place measurement.
   c. For removal to depth of 15 feet below mean low water of
ledges and boulders obstructing the approach to the wharves be-
tween Harbor Cove and Pews wharf, near the head of the inner
harbor; dredging to the same depth the channel leading past the
wharves and dredging Harbor Cove to the depth of 10 feet at mean
low water.
   Annisquam River: For a channel 8 feet deep at mean low water
60 feet wide from Gloucester Harbor to the Boston & Maine Rail-
road bridge, 100 feet wide from the railroad bridge to the mouth
of the river, and 200 feet wide across the bar in Ipswich Bay, in-
cluding the removal of a ledge near the Gloucester Harbor en-
trance; and for a dredged anchorage area about 17 acres in extent
and 8 feet deep at the entrance of Lobster Cove. The project
depths refer to mean low water.
   The mean range of tide in Gloucester Harbor is 8.7 feet; the ex-
treme range is 12.6 feet. The mean range of tide in Annisquam
River is 8.5 feet; the extreme range is about 10 feet.
   The estimate of cost for new work (1954) is $705,000 exclusive
of amounts expended on previous projects and $25,000 to be con-
tributed by local interests. The latest (1950) approved estimate
for annual cost of maintenance is $10,000.
   The existing project was authorized by the following river and
harbor acts:
      Acts                        Work authorized                                         Documents

Aug. 11, 1888   Removal of ledges and boulders, and dredging, in           Annual Report, 1887, p. 503.
                 Gloucester Harbor.
Aug. 18, 1894 I'onstruction of breakwater at entrance to Gloucester        H.     Ex. Doc. 56, 48th Cong., 2d
                Harbor from Eastern Point to Round Rock Shoal.             sess., and Annual Report, 1885.
                                                                                p. 534.
June 13, 1902   Termination at Cat Ledge of breakwater authorized          Annual Report, 1902, p. 89.
                 by act of Aug. 18, 1894.                                                                         t
June 25,1910    Removal of 8 ledges in Gloucester Harbor .......----------.. H. Doc. 1112, 60th Cong., 2d sess.
Aug. 30, 1935   Dredging in Annisguam River and removal of a ledge         Rivers and Harbors Committee,
                 in Gloucester Harbor near the entrance to Annis-          Doc. 39, 72d Cong., 1st sess.'
                 quam River.
Mar. 2,1945     Dredging 8-foot anchorage area in Lobster Cove,            H. Doc. 329, 77th Cong., 1st sess.'
                 Annisquam River.

  1 Contains latest published maps.

   Local cooperation. The River and Harbor Act of March 2,
1945, provides that local interests contribute one-third of the
initial cost of the improvement, but not to exceed $25,000, furnish
free of cost to the United States all lands, easements, rights-of-
way, and spoil disposal areas necessary for the improvement and
for subsequent maintenance, when and as required, and hold and
save the United States free from claims for damages resulting
from the improvement. Assurances of local cooperation were
furnished during fiscal year 1949.
   Terminal facilities. There are in Gloucester Harbor 61 wharves
worthy of mention. The depth beside the wharves varies from 0
to 20 feet at mean low water. Except for 3 wharves, 2 owned by
the city and the fish pier which is leased by the city from the Com-
monwealth of Massachusetts, all are private and are not available
                   RIVERS AND HARBORS-NEW ENGLAND DIVISION                                                         19

to the public. There are two commercial wharves on Annisquam
River on the east bank. These facilities are considered adequate
for the existing commerce of the port. For full description see
Port and Terminal Facilities at the Ports of Northern New Eng-
land, 1941.
   Operations and results during fiscal year. A condition survey,
by hired labor, to determine the extent of shoaling in the 8-foot
channel in the Annisquam River was completed during the fiscal
year. Costs were $1,916, all for maintenance.
   Condition at end of fiscal year. The existing project was about
77 percent complete. The existing project was completed in 1936
except for dredging the anchorage area in Lobster Cove in the
Annisquam River. The removal of all ledges and boulders in
Gloucester Harbor between Harbor Cove and Pews Wharf, and
other obstructing rocks was completed in 1894; and the removal
of a pinnacle rock in the outer harbor in 1896. The breakwater,
which was completed in 1905, was repaired in 1940 and is in good
condition. The removal of all ledges to project depth was com-
pleted in 1916. The improvement of Annisquam River was com-
pleted in 1936 at a cost of $33,976. The controlling depths over
the ledges in the outer harbor in 1916 were from 18 to 25 feet; over
ledge C in the inner Harbor in 1931, 14 feet; and over ledges A
and B in the inner Harbor in 1940, 13 and 15 feet respectively; 7
feet in the channel from Ipswich Bay to Gloucester Harbor with
the exception of encroachments on the west side of the channel
abreast Pearce Island having a depth of 0 feet, and on the east
side of the channel just north of Rust Island having a depth of 2
feet (1953), 5 feet in the northwesterly third and +5 feet in the
remaining part of the Lobster Cove anchorage. The costs under
the existing project have been $713,110, of which $535,154 was for
new work and $177,956 was for maintenance.
                                            Cost and financial summary

                                                       Fiscal year ending June 30                      Total to June
                                                                                                      30, 1954, includ-
                                                                                                       ing fiscal years
                                     1950            1951            1952           1953      1954      prior to 1950

New work:
   Appropriated---........         --------.-----         ---------------- ------------      ------------   1 $556,154
   Cost..----------.........----- ------------------------------------                     ----------         1556,154
Maintenance:
    Appropriated_ ------------ ------------------------------------            $1, 916                         177, 956
    Cost...........-----------------. -- .------------------------------------   1,916                         177,956


Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project....-...-.......-..-................................ ......... $169 ,846
  1 Includes $21,000 for new work for previous projects.

                                     12. BOSTON HARBOR, MASS.
   Location. This harbor includes all the expanse of tidewater
lying within a line from Point Allerton to Point Shirley and ex-
tending from that line westward to the mainland. This com-
prises an area of about 47 square miles, exclusive of the islands.
 (See U. S. Coast and Geodetic Survey Charts Nos. 246 and 248.)
    Previous projects. Adopted by the River and Harbor Acts of
20       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

March 2, 1867, June 14, 1880, September 19, 1890, June 3, 1896,
and July 25, 1912. For further details see page 1743 of Annual
Report for 1915, page 81 of Annual Report for 1917, and page 63
of Annual Report for 1938.
   Existing project. This provides for the following:
   a. A channel 40 feet deep in general, but 45 feet deep through
rock, from the sea to President Roads through Broad Sound, 2
miles, 900 feet wide except at the outer edge where it is widened
to 1,100 feet.
    b. Deepening to 40 feet the main ship channel from President
Roads to about 200 feet northerly of the site of Mystic Pier No. 1
Charlestown; having widths varying from 600 feet to 1,200 feet
with suitable widening at the bends. Length about 5.5 miles.
   c. An anchorage area 2,000 feet wide, 5,500 feet long, and 40
feet deep, on the north side of President Roads.
   d. Extension of President Roads anchorage 700 feet to the north
and 500 feet to the west at a depth of 40 feet, and dredging an area
to 35 feet lying west of the anchorage.
   e. Deepening to 40 feet that part of the approach channel to the
United States Navy drydock No. 3 at South Boston between the
main ship channel and the United States harbor line.
   f. A channel 35 feet deep along the same line as the 40-foot
main ship channel in the following manner: adjacent to the west-
erly side of the 40-foot main ship channel through Broad Sound
600 feet wide, a distance of about 2 miles; adjacent to the north-
erly side of the 40-foot main ship channel from President Roads to
abreast the Fish Pier 600 feet wide, a distance of about three
miles; adjacent to the westerly side of 40-foot main ship channel
from abreast Fort Point Channel to the Mystic River and Charles-
town Bridges and the entrance to the Chelsea River, having widths
varying from 100 feet to 1,000 feet, a distance of about 2 miles.
   g. A channel 2 miles long, 30 feet deep, and 1,200 feet wide from
the sea to President Roads through Broad Sound by a less direct
route than the 35- and 40-foot channels.
   h. A channel 27 feet deep and 1,000 feet wide from Nantasket
Roads to President Roads known as the "Narrows" Channel, 3
miles.
   i. A channel 15 feet deep, 300 feet wide, and 550 feet long
through the bar which extends from the north head of Long Island
to Nixes Mate Shoal, known as "Nixes Mate" or "Nubble" Channel.
   f. A channel in Chelsea River 30 feet deep and generally 200 feet
wide, from the mouth of the river, at the head of the 35-foot chan-
nel in Boston Harbor, to a point about 1 mile upstream of the
Chelsea Street 'Bridge, a distance of about 2 miles, thence a chan-
ned 8.4 feet deep to the 'Boston & Maine Railroad Bridge 150 feet
wide a distance of about one-half mile.
   k. Improvement of Reserved Channel east of L Street Bridge by
a channel 30 feet deep and 300 feet wide.
   1. The Fort Point Channel, 23 feet deep and 175 feet wide from
its entrance in Boston Harbor, about four-fifths of a mile to the
Dorchester Avenue (old Federal Street) Bridge.
  m. Sea walls of coursed stone and riprap protecting the most
exposed headlands and islands.
                RIVERS AND HARBORS----                NEW ENGLAND DIVISION                                 21
   All depths are referred to mean low water. The mean range of
tide is 8.9 feet at Boston Light, and 9.5 feet at Commonwealth
Pier, in Chelsea Creek, and in Fort Point Channel. The extreme
range is about 4 feet greater.
   The estimate of cost for new works (1954) is $19,640,000, ex-
clusive of amount expended on previous projects of sea walls for
which no estimate was given. The latest (1950) approval esti-
mate for annual cost of maintenance is $130,000.
   The existing project was authorized by the following River and
Harbor Acts:

     Acts                         Work authorized                                      Documents

Mar.   2,1825   Preservation of islands by sea walls.
Aug.   5,1886   Fort Point Channel_.... ________-- ____-__----.           H. Ex. Doc. 206, 48th Cong., 2d
                                                                           sess. Annual Report, 1885, p. 543.
                Channel 15 feet deep from Long Island to Nixes Mate       Annual Report 1887, p. 517.
                  Shoal (Nixes Mate or Nubble Channel).
July .13, 1892 Channel 27 feet deep from Nantasket Roads to Presi-        Annual Report, 1893, p. 766.
                  dent Roads.
Mar. 3,1899 For 300-foot channel from sea to the President Roads          H.    Doc. 133, 55th Cong., 2d sess.
                  through Broad Sound by less direct route than the            Annual Report, 1898, p. 886
                  35- and 40-foot channels.
June 13,1902 For 35-foot channel from the sea to Boston Naval             H. Doc. 119, 56th Cong., 2d sess.
                  Shipyard, Chelsea and Charles River Bridges.              Annual Report, 1901, p. 1096.
                Elimination from the project of the removal of Finns      Authorized by Chief of Engineers
                  Ledge at the outer entrance. .                            Mar. 11, 1913. _
Aug. 8, 1917 Depth of 40 feet (45 feet in rocks) in Broad Sound           H. Doc. 931, 63d Cong., 2d sess.)
                  Channel.
Aug. 30, 1935 2 Present project dimensions of channel from Presi-         H. Doc. 244, 72d Cong., 1st sess.
                  dent Roads to Commwealth pier No. 1, East
                  Boston and anchorage area north side of President
                  Roads.
     Do .____ Present project dimensions of that part of approach         Rivers and Harbors Committee     1
                  channel to U. S. Navy drydock No. 3, at South             Doc. 29, 74th Cong., 1st sess.
                  Boston between Main Ship Channel and United
                  States harbor line. .
Aug. 26, 193    Chelsea River Channel, 30 feet deep-.......--- .....      Rivers and Harbors Committee     1
                                                                            Doc. 24, 75th Cong., 1st sess.
Oct. 17, 1940   Reserved Channel 30 feet deep....        .    ----        H. Doc. 225, 76th Cong., 1st sess.2
Sept. 7, 1940   Abandons seaplane channel authorized in River and         Public Law 420, 78th Cong.
                 Harbor Act approved Oct. 17,   1940   (H.   Doc.  262,
                 76th Cong., 1st sess.).
Mar. 2,1945     Extension of 40-foot channel.................             H. Doe. 733, 79th Cong., 2d sess.'
July 24, 1946   Extension of President Roads Anchorage......-.....        H. Doc. 244, 80th Cong., 1st sess.'


  1 Contains latest published maps. See also Annual Report, 1911, p. 1178 (sea walls and Nixes Mate Chan-
uel) and Annual Report, 1903, p. 770 (Fort Point Channel).
  2 Authorized in part by Public Works Administration, Sept. 6, 1933.

   Local cooperation. Fully complied with.
   Terminal facilities. There are 183 wharves and piers in the
Harbor, not including the Mystic River, Weymouth Fore River,
and Town River, which are reported elsewhere. In addition, there
are 4 ferry slips and 2 car floats. Of the terminals, 28 are publicly
owned, 3 are open to public use, 77 have mechanical handling
facilities, and 57 have railroad connections. The facilities are
considered adequate for the present requirements of commerce.
 (For the latest full description of Terminal Facilities, see Port
Series No. 3--the Port of Boston, Mass., revised 1946.)
   Operations and results during fiscal year. Maintenance dredg-
ing, by contract, to restore project depth in the 39-foot Chelsea
River channel, in progress at the beginning of the fiscal year, was
completed on July 28, 1953. During the period a total of 35,076
cubic yards of ordinary material were removed. Snagging opera-
tions, by hired labor, were carried on throughout the year. Mis-
cellaneous inspections and reports were made on the project during
 22                 REPORT OF CHIEF OF ENGINEERS. U. S. ARMY. 1954

the year. The total costs were $52,384, all maintenance funds.
   Condition at end of fiscal year. The existing project is about
84 percent completed, the remaining portion consisting of dredg-
ing the extension of President Roads Anchorage 700 feet to the
north and 500 feet to the west at a depth of 40 feet, and dredging
an area to 35 feet lying west of the anchorage; and the completion
of the 40-foot main ship channel to project width for a distance of
about 4,000 feet along the east side at the upstream end of the
project. The seawalls have a total length of about 3.75 miles and
have been built and maintained on Great Brewster, Lovells, Gall-
ups, Long, Rainsford, Deer, and Georges Island and on Point
Allerton. The "Nixes Mate" or Nubble Channel was completed in
1892; the 30-foot channel in 1905; and 27-foot channel in 1907;
Fort Point Channel in 1909; the 35-foot channel in 1915; the
Broad Sound 40-foot channel in 1930; the 40-foot anchorage in
1937; the 30-foot Chelsea River Channel in 1940, except for the
small area immediately below the Chelsea Street Bridge which was
completed in 1946; and the 30-foot Reserved Channel in 1941.
   The controlling depths at mean low water in the various im-
proved channels of Boston Harbor at the dates they were last sur-
veyed were:
   a. Broad Sound 40-foot channel, 39 feet (1952)
   b. Main 40-foot ship channel to Commonwealth Pier No. 1, 37
feet in northerly three-quarters of the channel, 34 feet in the
southerly quarter (1952), Commonwealth Pier No. 1 to 200 feet
northerly of Mystic Pier No. 1, 40 feet (1951).
   c. Approach to Navy Drydock No. 3, 40 feet (1938).
   d. President Roads Anchorage; 37 to 39 feet in the northerly
half of the anchorage, 40 feet in the remainder (1952).
   e. Extension to President Roads Anchorage and 35-foot area 15
to 35 feet (1945).
   f. Broad Sound 35-foot channel, 37 feet (1952). Main 35-foot
ship channel, 32 feet (1952).
   g. Broad Sound, 30-foot channel, 30 feet (1952).
   h. Narrows Channel, generally 27 feet with the exception of an
encroachment 150 feet into the northerly limit of the channel in
the vicinity of "Narrows Light," a depth of +5.2 feet on this shoal
 (1952).
   i. Nubble Channel, 15 feet (1951).
   j. Chelsea River, 30 feet (1953), 8.0 feet in the 8.4-foot channel
 (1936).
   k. Reserved Channel, 30 feet (1952).
   1. Fort Point Channel, 20 feet in three-quarters of the channel
width and 16 feet in the easterly quarter (1952).
   The costs under the existing project to June 30, 1954, have been
as follows:

                                                                        New work         Maintenance                   Total

Regular funds .   .       .       ------------------------
                                       ..--------                        $14, 414, 832            $1, 937, 538           $16, 352, 370
                             ....
Public Works funds --------------------------------..                      1, 030, 806   -     __-_                        1, 030. 806
Emergency Relief funds --------  -                     -      --- ..          935, 303   ...............----------------      935, 303

       Total..      ........-----------------------------------------     16, 380, 941          1, 937, 538            18, 318, 479
                    RIVERS AND HARBORS--NEW ENGLAN)                                        DIVISION                    23
   In addition $17,767 has been expended from contributed funds,
all maintenance funds.
                                           Cost and financial summniary

                                                   Fiscal year ending June 30                               Total to June
                                                                                                           30, 1954, includ-
                                                                                                           ing fiscal years
                                    1950           1951         1952              1953           1954       prior to 19501
New work:
   Appropriated--------....... $400, 000        $380, 000   -$38, 538 ..........--------------             2 $17, 846, 064
   Cost...-----------------       5,101          225, 222     511, 140 ......   -                           217, 846, 064
                                                                                                    -..........
Maintenance:
     Appropriated--------........   15, 500       73, 000     235, 000         $127, 000         $7, 500        31, 959, 879
     Cost.................           2, 431       18, 769     260, 501          124, 059         52, 384        3 1,955, 417

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project. ........................................... ...... $3,259,059
1 Includes $1,465,123 for new work and $17,879 for maintenance for previous projects.
2   Includes $935,303 expended for new work from emergency relief funds. Also includes $1,030,806
expended for new work from Public Works funds.
  8In addition, $17,767 was expended for maintenance from contributed funds.

             13. DORCHESTER BAY AND NEPONSET RIVER, MASS.
   Location. Dorchester Bay is situated at the mouth of Neponset
River, in Boston Harbor. Neponset River rises in Foxboro, Mass.,
and flows in a northeasterly direction about 25 miles, emptying
into Dorchester Bay. (See U. S. Coast and Geodetic Survey Chart
No. 246.)
  Existing project. This provides for a channel 25 feet deep and
3CO feet wide from the Boston Harbor main ship channel to Com-
mercial Point, thence 15 feet deep and 100 feet wide to the Nepon-
set Highway Bridge. The project depths refer to mean low water.
The mean range of tide is 9.6 feet and the extreme range is 13.7
feet.
   The estimate of cost for new work (1954) is $770,000. The
latest (1950) approved estimate for annual cost of maintenance is
$7,000.
   The existing project was authorized by the following River and
Harbor Acts: The act of March 2, 1907 (H. Doc. 83, 59th Cong., 2d
sess.), provided for the 15-foot channel, and the act of March 2,
1945 (H. Doc. No. 394, 77th Cong., 1st sess.), provides for the 25-
foot channel. The latest published map is in the last project
document.
   Local cooperation. Conditions were imposed by the act of
March.2, 1907, that the portion of the river from Neponset High-
way Bridge to Milton Mills should be'dredged and maintained by
the Commonwealth of Massachusetts or other agency to the depth
of 6 feet at mean low water, 100 feet wide up to the Granite Street
Bridge, 1.15 miles; 75 feet wide thence to Godfreys Wharf, 1.25
miles; and thence 50 feet wide to the railroad bridge at Milton, a
distance of 250 feet. These conditions were accepted by resolves
of the Legislature of Massachusetts, approved June 24, 1907, and
March 5, 1908. The river was dredged by the Commonwealth of
Massachusetts in 1910 and has been maintained periodically by the
Commonwealth since that date.
   Terminal facilities. There are 16 wharves located on these
waterways which are used for commercial purposes.
24           REPORT OF CHIEF OF ENGINEERS. U. S. ARMY. 1.954

  Operations and results during fiscal year. Operations during
the fiscal year consisted of miscellaneous inspections and reports.
Costs amounted to $141, all maintenance funds.
  Condition at end of fiscal year. The existing project is about
22 percent completed, the remaining portion consisting of dredg-
ing a channel 25 feet deep and 300 feet wide from the Boston Har-
bor main ship channel to Commercial Point. Controlling depths
were 17 feet in Dorchester Bay to about 3,000 feet downstream of
Commercial Point; thence 13 feet to Commercial Point (1953);
thence 8 feet to the N. Y., N. H. & H. Railroad bridge (1953);
thence 13 feet to Neponset Highway Bridge (1953). The costs
under the existing project have been $130,341, of which $94,584
was for new work and $35,757 for maintenance.
                                    Cost and financial summary

                                                   Fiscal year ending June 30                  Total to June
                                                                                              30, 1954, includ-

                             1950           1951            1952            1953     1954      prior to 1950
New work:
   Appropriated ...                                                                                    $94, 584
   Cost         .. ...                                                                                  94,584
Maintenance:
   Appropriated                         -     ---      i------$..       -   $. 000
                                                                            $3,      - $834             35, 757
   Cost_ ...
         _            -...                             ... .        .        2.025      141             35, 757


Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project ..............                $675 .016
                                                                        $............

                                14. TOWN RIVER, MASS.
   Location. Town River is a tidal river 2 miles long, lying en-
tirely within the limits of the city of Quincy, just south of Boston,
Mass. It flows in an easterly direction and empties into Wey-
mouth Fore River at Quincy Point. (See U. S. Coast and Geodetic
Survey Chart No. 246.)
   Previous project. Adopted by the River and Harbor Act of
June 3, 1896. For further details, see page 65 of Annual Report
for 1907, and page 69 of Annual Report for 1938.
   Existing project. This provides for a channel 24 feet deep at
mean low water and generally 150 feet wide from deep water in
Weymouth Fore River to a point opposite the upstream end of the
Quincy Oil Co. terminal, a distance of 6,700 feet, with a turning
basin 18 feet deep, 400 feet wide, and roughly 1,000 feet long at
the inner end; and a channel 15 feet deep and 100 feet wide, thence
to a point just below the plant of the Quincy Electric Light &
Power Co., a further distance of 1,370 feet. The mean range of
tide is 9.5 feet. The extreme range is 11 feet.
   The cost of new work for the completed project was $372,392,
including $111,763 contributed by local interests but exclusive of
amounts expended under the previous projects. The latest (1950)
approved estimate for annual cost of maintenance is $9,000. The
existing project was adopted by the River and Harbor Act of
August 26, 1937 (H. Doc. 96, 75th Cong., 1st sess.). The latest
published map is in that document.
   Local cooperation. The River and Harbor Act of August 26,
              RIVERS AND HARBORS-NEW ENGLAND DIVISION                                                          25
1937, requires that local interests contribute 30 percent of the
initial cost of the entire improvement, furnish free of cost to the
United States a suitably located right-of-way 400 feet wide and
spoil disposal areas, bulkheaded where necessary, for new work
and for subsequent maintenance as required, and release the
United States from all claims for damages attributable to the work
of improvement. With the exception of furnishing certain ease-
ments, all conditions of local cooperation have been complied with.
   Terminal facilities. On the south bank of Town River are lo-
lated 8 wharves, 3 of which are used for boat building and repair
work, 3 used for receipt of petroleum products, 1 for receiving and
storing lumber, and 1 for receiving scrap materials. On the north
bank of the river is located a yacht building and repair yard. The
facilities are considered adequate for existing commerce.
   For full description, see The Port of Boston, Mass.-Port Series
3---Revised 1946.
   Operations and results during fiscal year. Operations during
the fiscal year consisted of preliminary work in connection with a
contract executed in April 1954, for maintenance dredging to re-
store project depth in the 24-foot channel. Costs amounted to
$1,668, all maintenance funds.
   Condition at end of fiscal year. The existing project was com-
pleted in 1940. Controlling depth is as follows: maintenance
dredging in the 24-foot channel in progress (1954), 14 feet in the
15-foot channel (1953), 17.6 feet in the turning basin (1947).
The total costs under the existing project have been $445,568, of
which amount $372,392 was for new work, including $111,763
contributed funds, and $73,176 for maintenance.
                                       Cost and financial summary

                                                 Fiscal year ending June 30                       Total to June
                                                                                             _   30, 1954, includ-
                                                                                                      fiscalicu-ing
                                                                                                               years
                                1950            1951        1952        1953       1954           prior to 1950

New work:
   Appropriated ---       ---     ------                                                                2$285,629
   Cost-     - ---.-                                           -- - -------   --------                   1285, 629
Maintenance:                               -                             $
   Appropriated ---------------            ---------------------        $718     $40, 000                  124, 085
   Cost..-----            - .              ... . ...      "               718       1, 668                  85, 753

12 Includes                                               for previous projects.
             $25,000 for new work and $12,557 for maintenance
    In addition, $11,763 wasexpended for new work from contributed funds.

                                15. HINGHAM HARBOR, MASS.
   Location. Hingham Harbor is situated in the southern part of
Hingham Bay, which comprises all that part of Boston Lower
Harbor south of Nantasket Roads. The harbor covers an area of
1 square mile, and has extensive mud flats, bare at low tide. (See
U. S. Coast and Geodetic Survey Chart No. 246.)
   Previous project. The original project, adopted by the Act of
March 3, 1875, was to widen and deepen the. natural channel by
dredging and blasting to the width of 100 feet and depth of 8 feet
at mean low water from deep water near the head of the harbor up
to the vicinity of Hingham wharves, a distance of about 2,500 feet.
In 1876, a channel 100 feet wide and 8 feet deep at mean low
26               REPORT OF CHIEF. OF ENGINEERS, U. S. ARMY. 1954

water was completed for a distance of 2,500 feet to the steamboat
wharf, whence it was extended for about 500 feet, with a width of
50 feet and a depth of 8 feet; in 1884, 3 cubic yards of ledge were
removed from the channel.
   Existing project. The existing project is to deepen the im-
proved channel, 2,500 feet long, 100 feet wide, to 10 feet at mean
low water and remove a midchannel ledge in the lower channel
between Langlee Island (formerly called Chandlers) and Ragged
Islands. The mean range of tide is 9.5 and the spring range is
11.0 feet. The cost of new work for the completed project was
$19,000. The latest (1950) approved estimate for annual cost of
maintenance is $1,200.
   The existing project was authorized by the River and Harbor
Act of August 5, 1886 (H. Ex. Doc. 137, 48th Cong., 2d sess.). By
the Act of March 2, 1907, without previous estimate, $10,000 was
appropriated for redredging the channel. By the River and Har-
bor Act of March 3, 1909, the unexpended balance of this appro-
priation was "made available for redredging and improving the
channel." The existing project was completed in 1893.
   Local cooperation. None required.
   Terminal facilities. There are four small wharves in Hingham
Harbor of the solid fill type, faced with granite. The facilities are
considered adequate for existing commerce.
   Operationsand results during fiscal year. A condition survey,
by hired labor, to determine extent of shoaling in the 10-foot chan-
nel was completed during the fiscal year at a cost of $493, all
maintenance funds.
   Condition at end of fiscal year. The existing project was com-
pleted in 1893. In 1911 the channel was redredged to the width
of 100 feet and depth of 8 feet at mean low water from deep water
near the head of the harbor to the steamboat wharf, a distance
of about 2,000 feet, and was also redredged for a further distance
of about 500 feet, 50 feet wide and 6 feet deep at mean low water.
The channel up to the steamboat wharf was restored to 100 feet
wide, 8 feet deep at mean low water in fiscal year 1949. The con-
trolling depth in the 10-foot channel to the steamboat wharf is 6
feet (1954).    The costs under the existing project have been
$70,803, of which $19,000 was for new work and $51,803 for
maintenance.
                                          Cost and financial summary

                                                      Fiscal year ending June 30                        Total to June
                                                                                                       30, 1954; includ-

                                   1950             1951               1952     1953          1954      prior to 1950

Appropriated                                                    _                 ----   I                    $28, 316
     Cost .
     Cost-----        ---------                        ..........-      ..   .28,
                                                                --------------
                                                              ----------
                                                  -------------------                                                316
                                                                                                               $.....-2
                                                                                                               ' 28, 316
Maintenance:
     Appropriated------       -----------------     --------------------------------
                                                                         .493                   $493             51,803
                                                                                                                 51,803
     A     t   e
     Cost--------          --       -                                      ----------
                                                     ------------------------                    493             51,803

I   Includes $9,316 for new work for previous projects.
                                  16. PLYMOUTH HARBOR, MASS.
   Location. This harbor is 45 miles by water south of Boston.
Its outer anchorage, the "Cow Yard," is common to Plymouth,
                RIVERS AND HARBORS-NEW ENGLAND DIVISION                                                                       27

Duxbury, and Kingston. (See U. S. Coast and Geodetic Survey
Chart No. 245.)
   Previous projects. Adopted by Acts of May 26, 1824, March 3,
1875, 1877, 1884, and 1885. For further details, see page 1746 of
Annual Report for 1915, and page 72 of Annual Report for 1938.
   Existing project. This provides for (a) protecting by riprap
the sections of Long Beach damaged by the storm of November
1898, and for restoring Eel River to its former course; (b) dredg-
ing a channel 18 feet deep at mean low water and 200 feet wide,
increased at the entrance and on curves, from the bay to the town
wharves, formerly in the areas south of the State Pier, a distance
of.about 2.5 miles, with a suitable turning basin at the inner end;
 (c) dredging a channel 150 feet wide, 15 feet deep at mean low
water, extending in a northwesterly direction about 0.3 mile from
a point off the site of northerly Craigs wharf (now State pier)
with a turning basin 300 feet square, and of the same depth, at its
northwesterly end; (d) maintenance of the area dredged to a
depth of 18 feet below mean low water by the Commonwealth of
Massachusetts, connecting the 15-foot channel with the 18-foot
channel in the vicinity of the State pier; and (e) dredging an
anchorage basin 18 feet deep at mean low water, 850 feet wide,
and 2,125 feet in average length on the southeast side of the proj-
ect channel near Long Beach. The mean range of tide is 9.6 feet;
the extreme range is 13.7 feet.
   The estimate of Federal cost for new work (1954) is $606,000.
   The latest (1950) approved estimate for annual cost of mainten-
ance is $12,000.
   The existing project was authorized by the following River and
Harbor Acts:

    Acts                                 Work authorized                                                  Documents
Mar. 3,1899                                                         ------------
                Beach protection----------............................-------........          Annual Report for 1899, p. 1089.
Mar. 4, 1913    Dredging 18-foot channel-----------------------.............................   H. Doc. 1194, 62d Cong., 3d sess.
Sept. 22,1922   Dredging 15 foot extension, including turning basin..                          H. Doc. 996, 66th Cong., 3d sessa
June 20,1938    Dredging 18-foot anchorage basin-----------------.....................         H. Doc. 577, 75th Cong., 3d sess.'

  IContains the latest published         maps.


   Local cooperation. The River and Harbor Act of June 20, 1938,
provided for an anchorage basin 18 feet deep at mean low water,
850 feet wide, and 2,125 feet in average length on the southeast
side of the project channel near Long Beach, provided local inter-
ests furnish, free of cost to the United States, spoil-disposal areas
for initial work and for subsequent maintenance as may be re-
quired, and contribute one-third the initial cost of the improve-
ment. These conditions have not yet been complied with.
   Terminal facilities. There are 3 wharves and 5 boatyards.
Two of the wharves are publicly owned, 1 by the town of Plymouth
and 1 by the Commonwealth of Massachusetts. These wharves are
open to the public free of charge. The third wharf is used in con-
nection with a yacht club. The wharves are of pile and timber
construction with timber decks. None of the wharves have rail-
road connections. Of the boatyards, two are used for the construc-
28              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

tion of new boats and the repair of old boats, and three are used
for the servicing and storage of boats. The facilities are consid-
ered adequate for the present requirements of commerce.
   Operations and results during fiscal year. Partial mainten-
ance dredging to 15 feet of the 18-foot channel, and dredging to
project depth of the 15-foot channel, by contract, which was in
progress at the beginning of the fiscal year was completed on 27
January 1954. During the period 191,450 cubic yards of ordinary
material and 7.1 cubic yards of boulders were removed at a cost
of $164,335, all maintenance funds.
   Condition at end of fiscal year. The existing project was about
25 percent completed. No work has been done on the 18-foot an-
chorage basin authorized by the River and Harbor Act of June 20,
1938. Work of protecting by riprap the sections of Long Beach
damaged by the storm of 1898 was completed in 1909. Eel River
was restored to its former course in 1904. The dredging of a
channel 18 feet deep at mean low water was completed in 1915.
The 15-foot channel was completed in 1927. The controlling
depths were as follows: 15 feet in the center half and 13 and 12
feet respectively in left and right outside quarters entering from
seaward in the 18-foot channel, 15 feet in the 15-foot channel, and
turning basin to the Town Wharf (1953), + 4 to 18 feet in the
18-foot anchorage (1950). The costs under the existing project
have been $555,957, of which $188,571 was for new work and
$367,386 for maintenance. In addition, $108,400 has been ex-
pended from contributed funds, of which $108,000 was for new
work and $400 was for maintenance.
                                           Cost and financial summary

                                                  Fiscal year ending June 30                                     Total to June
                                                                                                                30, 1954, includ-
                                                                                                                ing fiscal years
                                    1950         1951                1952                1953        1954        prior to 1950'

New work:..
   Appropriated--------    --------             ...                                                                     $377, 218
   Cost...---------------------     ------------------------------                                  --------------       377, 218
Maintenance: ..
    Appropriated ..---------                      $2, 500       .........------------   $195, 000    $45, 892            379, 056
    Cost ----    -   -
                     --...     --    -     -       2,500    -          .                  66, 900    164, 335            369, 399

  I Includes $188,647 for new work and $2,013 for maintenance for previous projects. In addition, $108,000
was expended for new work and $400 was expended for maintenance from contributed funds.
Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project-----... ----..-....
                                                       ------.........  .. $417, 429
                                                         ........---------..

                                    17. CAPE COD CANAL, MASS.
   Location. This waterway is a sea level canal, extending from
the head of Buzzards Bay, Mass., to a point on Cape Cod Bay about
15 miles southeast of Plymouth Harbor, Mass. In general direc-
tion the canal trends from Buzzards Bay easterly to Cape Cod Bay.
 (See U. S. Coast and Geodetic Survey Charts Nos. 251 and 1208.)
   Existing project. This provides for the purchase of the Cape
Cod Canal, including a 600-foot jetty and a 3,000-foot breakwater
at the east end of the canal at a cost to the United States of
$11,500,000; for an open canal 32 feet deep at mean low water,
with widths of 540 feet in the land cut, 500 feet in a straight cham
                 RIVERS AND HARBORS-NEW ENGLAND DIVISION                                              29
nel in Buzzards Bay to Wings Neck, and 700 feet beyond Wings
Neck; mooring basins consisting of a basin on the south side of
Hog Island channel 4,000 feet long, with widths varying from
0 to 400 feet, 32 feet deep at mean low water, and a basin at Sand-
wich 3,260 feet long, with widths varying from 0 to 385 feet, and
25 feet deep at mean low water; the construction of two fixed high-
way bridges having horizontal clearance of 500 feet, and a vertical
clearance of 135 feet at mean high water; the construction of a
vertical lift railroad bridge with a 500-foot span and 135-foot
clearance above mean high water when the span is raised; an im-
proved lighting system; other accessory and minor features which
may be deemed necessary and to be in accordance with plans ap-
proved by the Chief of Engineers, which include a dike extending
southwesterly 10,700 feet from Stony Point, a dike between Hog
and Mashnee Islands, a dike between Hog Island and Rocky Point,
a small East Boat Basin, 13 feet deep at mean low water on the
south bank of the canal, and a small West Boat Basin 18 feet deep
at mean low water on the north bank of the canal; a harbor of
refuge for small vessels by dredging a channel 150 feet wide and
15 feet deep at mean low water into Onset iBay and to the town
wharf in the village of Onset; for enlargement of the 15-foot turn-
ing basin at the town wharf and for an anchorage basin of about
16 acres, having a depth of 8 feet below mean low water, located
contiguous to the proposed 15-foot channel and turning basin.
   The land cut is 7.7 miles long, and with approach channels, the
total length of the canal is 171/2 miles.
   The mean range of tide in Cape Cod Bay at the Cape Cod Canal
entrance is 9.4 feet and in Buzzards Bay 4 feet at the Cape Cod
Canal entrance. The mean range of spring tides is about 13 feet
in Cape Cod Bay, and 6.5 feet in Buzzards Bay.
   The estimate of cost for new work (1954) is $31,573,000, includ-
ing $11,500,000, .purchase price of the canal, and properties which
were taken over by the United States on March 31, 1928. The
latest approved (1950) estimate for annual cost of operation and
maintenance is $600,000.
   The existing project was authorized by the following River and
Harbor Acts:
                Acts                        Work authorized                             Documents
Jan. 21, 1927 (sec. 2)               Purchase of canal from the Boston,
                           ..-----------                                  H. Doc. 139, 67th Cong.,      2d
                                   Cape Cod & New York Canal Co.,              ses.
                                  in accordance with contract dated
                                  July 29, 1921, executed by that com-
                                  pany. .
Included in Public Works Ad-     Construction of 3 bridges and widen-     H.      Doc. 795, 71st Cong., 3d
  ministration program, Sept.      ing canal to 250 feet.                      sess.
  6, 1933.
June 26, 1934 (Permanent Ap-     Operation and care of works of im-
  propriations Repeal Act). .     provement provided for with funds
                                  from War Department appropria-
                                  tions for rivers and harbors.
Included in Public Works Ad-     Construction of a mooring basin......    H.      Doc. 795, 71st Cong., 3d
  ministration program, Apr.                                                   sess.
  29, 1935.
Included in Emergency Relief     Dredging and bank protection       -
program, May 28, 1935.
            ----------------
Aug. 30, 1935_                   Existing project for main canal          Rivers and Harbors Committee,
                                   adopted.                                 Doc. 15, 74th Cong., 1st sess.'
Mar. 2, 1945_                .   15-foot channel and turning basin in     H. Doc. 431, 77th Cong., 1st
                                   Onset Bay. _                                sess.'

  SContains the latest published maps.
30       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

    Local cooperation. The River and Harbor Act of March 2,
1945, provides that local interests contribute one-half of the first
cost, but not to exceed $48,000, for the channel and turning basin
in Onset Bay and hold and save the United States free from all
claims for damages attributable to the work. It is expected that
these requirements will be met.
    Terminal facilities. There are four terminals on the canal.
Three are privately owned, 1 being used for the receipt and freez-
ing of fish and 2 for the receipt and storage of oil. The fourth ter-
minal is the State pier, owned by the Commonwealth of Massachu-
setts, and located on the north bank of the canal at Bourne Neck.
The terminals are considered adequate for the purposes for which
they are used.
    Operationsand results during fiscal year. Operation and main-
tenance of the Canal was carried on during the fiscal year with
the following results: Maintenance dredging in the land cut in the
vicinity of Sagamore Bridge, Hog Island Channel, and Cleveland
Ledge Channel, to restore project depth through various areas of
shoaling was started in November 1953 and completed in Decem-
ber 1953 by the Government hopper dredge Goethals. During this
period 345,340 cubic yards, pay place plus natural shoaling, of
ordinary material were removed. Further maintenance dredging
was started by the Goethals in June 1954 and was in progress at
the end of the fiscal year. During this period 247,828 cubic yards,
pay place plus natural shoaling, of ordinary material were re-
moved. Condition surveys, by hired labor, were conducted to
determine channel depths, dike conditions, and bank stabiliza-
tion. Roads, railroads, buildings, grounds, utilities and equipment
were maintained by hired labor. The canal was open to naviga-
tion, traffic was controlled in passing through, and the lights,
power, and signal systems maintained. Necessary repairs were
made to maintain the dikes, canal banks, dolphins, floats, docks
and fenders, by hired labor. Placing of bituminous seal-coat on
service roads along the Canal, by contract, was started in June
1954 and was still in progress at the end of the fiscal year. Miscel-
laneous real estate activities were carried on during the fiscal
year. Costs amounted to $585,382.
    The railroad bridge was maintained and operated. New creo-
soted wood ties were installed on bridge and approaches and
guard timbers and closure plates were renewed with the same tim-
ber. A new diesel engine powered auxiliary electric generator
unit for the railroad bridge was purchased, by contract, during the
fiscal year. Constructions, by hired labor, of a housing unit and
installation of the new electric generator for the railroad bridge
was initiated and was still in progress at the end of the fiscal year.
New power cables for the railroad bridge were purchased, by
contract, during the fiscal year. Costs amounted to $222,809.
    Total costs during the fiscal year amounted to $808,191, all
maintenance funds.
    Condition at end of fiscal year. The existing project is substan-
tially complete except for dredging the 15-foot channel from deep
water in the vicinity of Wickets Island to the town wharf at Onset
and enlargement of the 15-foot turning basin at the town wharf,
                 RIVERS AND HARBORS-NEW ENGLAND DIVISION                                                           31
and an 8-foot anchorage basin contiguous thereto, authorized by
the River and Harbor Act of March 2, 1945. The canal is crossed
by two high-level highway bridges and a vertical lift railroad
bridge. The canal in the land cut from the easterly entrance to
station 430 has a least bottom width of 480 feet, except opposite
the State Pier where the width is 450 feet. From station 430 to
Wings Neck (Hog Island Channel) the width is 500 feet and be-
yond Wings Neck (Cleveland Ledge Channel), 700 feet. The con-
trolling depths at mean low water for this project were: Canal in
land cut, 31 feet (1954) ; mooring basin, north side, easterly end,
14 feet (1954) ; Hog Island Channel, 29 feet (1954) ; Cleveland
Ledge Channel, 29 feet (1954) ; 9 feet alongside sheet piling bulk-
head east entrance, south side (1954) ; 21 feet in mooring basin,
south side, westerly end (1954) ; 10 feet in boat basin, south side,
east entrance (1954) ; 16 feet in Onset Bay Channel from the Cape
Cod Canal to Wickets Island (1943) ; 15 feet in channel to the town
wharf and the turning basin at the town wharf (1940) ; with
considerable shoaling along the limits; 2 to 6 feet in the 8-foot
anchorage.
   The total costs from regular funds have been $33,203,916, of
which $20,437,653 (including the purchase price of $11,500,000)
was for new work and $12,766,263 was for maintenance. The
total costs from public works funds have been $6,138,157 for new
work. The total costs from Emergency Relief appropriation funds
have been $4,849,740 for new work. The total costs, all funds,
have been $44,191,813, of which $31,425,550 (including the pur-
chase price of $11,500,000) was for new work and $12,766,263
was for maintenance. This includes the sum of $1,658,355 ex-
pended between March 31, 1928, and June 30, 1935, on the opera-
tion and care of the works of improvement under the provision of
the permanent indefinite appropriation for such purpose.
                                         Cost and financial summary

                                                  Fiscal year ending June 30                           Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                                  1950           1951          1952          1953           1954        prior to 1950

New work:..
   Appropriated--...    ...--------              -------------------------------------.....
                                          ---------                                                       $31, 425, 550
                     ------------....----------------------............------------........
   Cost-......--.......----.....                                                                            31, 425, 550
                                                                                            ........-----------....
Maintenance:_.
    Appropriated                   478, 000
                                 $--------     $535, 000     $445, 000      $638, 070      $788, 500        12, 824, 349
    Cost----------------          436, 163      465, 777      533,983        623,438        808, 191        12,766, 263


  1 Includes $6,138,157 for new work from Public Works funds and $4,849, 740 for new work from emer-,
gency relief funds.
Other new work data: Estimated additional amount needed to be appropri-
                                                              ... .....$147,450
                                               - -___.....--...
  ated for completion of existing project .-. ....

       18. POLLOCK               RIP SHOALS,               NANTUCKET                 SOUND,            MASS.
  Location. Pollock Rip Channel is the northerly passage through
the shoals off the eastern entrance to Nantucket Sound connecting
the deep water of the sound with that of the ocean. It is about 33
miles east from the harbor of Vineyard Haven, on the island of
Marthas Vineyard, Mass., and 60 miles south from Provincetown
 32             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Harbor at the northern extremity of Cape Cod. (See U. S. Coast
and Geodetic Survey Chart No. 250.)
  Existing project. This provides for dredging through the
shoals at the eastern entrance to Nantucket Sound with a Govern-
ment dredge, which is to assist the natural agencies in obtaining
such depth and width- as may be found practicable, but not exceed-
ing a depth of 30 feet at mean low water and a width of 1 mile.
The mean tidal ranges are about 3.7 feet at Monomoy Point, the
nearest land, and 6.7 feet at Chatham Light, about 9 miles to the
north of this point. The ranges of spring tides at these two points
are 4.4 and 7.9 feet. The ranges are largely affected by direction
and force of storms. The original expenditure authorized for ex-
perimental work was $250,000, and later the operation of a dredge
was authorized at an estimated annual cost of $200,000.
  The cost of the completed project was $1,083,504 for new work.
The latest approved (1950) estimate for annual cost of mainte-
nance is $60,000.
  The existing project was authorized by the following River and
Harbor Acts:
     Acts                          Work authorized                                        Documents

July 25, 1912   Experimental dredging through the shoals to deter-           H. Doc. 536, 62d Cong., 2d sess.
                 mine if a channel could be secured and maintained
                 not over 30 feet deep and not over 1 mile wide. -
July 27, 1916   Continuation of work with a Government-owned                 Rivers and Harbors Committee
                 hopper dredge.                                                Doc. 3, 64th Cong., 1st sess.


   The latest published map is in the Annual Report for 1915, page
2056.
   Local cooperation. None required.
   Terminal facilities. None.
   Operations and results during fiscal year. A condition survey,
by hired labor, to determine extent of shoaling in the 30-foot proj-
ect area, in progress at the beginning of the fiscal year, was com-
pleted. Costs were $617, all maintenance funds.
   Condition at end of fiscal year. The existing project was com-
pleted in 1925. The depths previously secured over the northern
tongue of the Stone Horse Shoals have been maintained. A cut
2,000 feet wide has been dredged through Bearse and Pollock Rip
Shoals. The controlling depth at mean low water was 29 feet for
a middle width of 1,000 feet (1953) ; 11 feet along the southerly
quarter (1953) ; 26 feet along the northerly quarter (1953). The
costs under the existing project have been $1,083,504 for new
work and $734,050 for maintenance, a total of $1,818,009.
                                        Cost and financial summary

                                                Fiscal year ending June 30                          Total to June
                                                                                                   30, 1954, includ-
                                                                                                   ing   fiscal    years
                                1950           1951           1952        1953          1954        prior to 1950

New work:
   Appropriated-------          ----      -----------------   ------------------    ------------          $1, 083, 504
    Cost_----------        ----------      ----------------------------------       -----------             1, 083, 504
Maintenance:
    Appropriated....         ------------                                 $2,100    .                             734, 505
    Cost .  .          .                                                   1, 483          $617                   734, 505
                 RIVERS AND HARBORS-NEW ENGLAND DIVISION                                                           33

             19. CROSS RIP SHOALS, NANTUCKET SOUND, MASS.
   Location. Nantucket Sound lies south of Cape Cod and north of
Nantucket and the eastern part of Marthas Vineyard Islands.
Cross Rip Shoals are a little southerly and easterly of the geo-
graphical center of the sound. They are about 17 miles east from
Vineyard Haven on the island of Marthas Vineyard and about 15
miles northwest from Nantucket Harbor. (See U. S. Coast and
Geodetic Survey Chart No. 1209.)
  Existing project. This provides for a channel 4,000 feet wide
and 30 feet deep at mean low water between Half Moon Shoal and
Cross Rip Shoal, about 1.7 miles. The mean tidal range id about 2
feet and the maximum range, due to the combined effect of wind
and other causes, is 3 feet or more.
   The cost of new works for the completed project was $24,200.
The latest (1950) approved estimate for annual cost of mainte-
nance is $8,000. The existing project was authorized by the River
and Harbor Act of July 3, 1930 (H. Doec. 182, 70th Cong., 1st sess.).
The latest published map is in the project document.
  Local cooperation. None required.
   Terminal facilities. None.
   Operationsand results during fiscal year. A condition survey,
by hired labor, to determine extent of shoaling in the 30-foot proj-
ect channel, in progress at the beginning of the fiscal year, was
completed. Costs were $457, all maintenance funds.
  Condition at end of fiscal year. The existing project was com-
pleted in 1931. The controlling depth was 28 feet at mean low
water (1953). The costs under the existing project have been
$24,200 for new work and $42,654 for maintenance, a total of
$66,854.
                                         Cost and financial summary

                                                  Fiscal year ending June 30                           Total to June
                                                                                                      30, 1954, includ-
                                                                                                      ing fiscal years
                                  1950          1951           1952        1953            1954        prior to 1950

New work:
   Appropriated-       ........---- ...------ --------------------------------------    -------                $24, 200
   Cost......------------..............---------------------------------------------   ----------               24, 200
Maintenance:
   Appropriated---------------- ----------- ..----....-------..              $1, 300   --..........             42, 654
                                        ....
   Cost-------------................ -----------------------------------         843          $457              42, 654



                             20. CUTTYHUNK HARBOR, MASS.
  Location. At the eastern end of Cuttyhunk Island, at the west-
ern entrance to Buzzards Bay, about 14 miles south of New Bed-
ford Harbor, Mass. (See U. S. Coast and Geodetic Survey Chart
No. 297.)
  Existing project. This provides for a channel generally 75
feet wide and 10 feet deep from the outer harbor to the westerly
terminal in Cuttyhunk Pond, about 3,500 feet; an anchorage in
the inner harbor 10 feet deep, 900 feet long, and 800 feet wide;
and for maintenance of the existing jetties. All depths refer to
mean low water. The mean and spring tidal ranges are 3.4 and
4.2 feet, respectively.                     The cost of the completed project was
34            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

$27,167 for new work, exclusive of $11,643 contributed by local
interests. The latest (1950) approved estimate for cost of annual
maintenance is $8,000.
   The existing project was authorized by the River and Harbor
Act approved August 26, 1937. The latest published map is in
the project document (H. Doc. 81, 75th Cong., 1st sess.).
   Local cooperation. Fully complied with. Spoil disposal areas
for maintenance will be furnished when required.
   Terminal facilities. Two town wharves of timber and pile
construction, having total berthing space of 400 feet, are open
to public, use. No mechanical handling facilities are available.
Facilities are considered adequate for existing commerce.
   Operations and results during fiscal year. A condition survey,
by hired labor, to determine the extent of repairs necessary to re-
store the protective barrier for channel maintenance was com-
pleted during the fiscal year. Plans and specifications have been
completed for repairs to the protective barrier. Total costs during
the fiscal year amounted to $2,084, all maintenance funds.
   Condition at end of fiscal year. The existing project was com-
pleted in 1939. The controlling depths at mean low water were 9.8
feet in the entrance channel (1952) ; 10 feet through the harbor
 (1939) ; and 10 feet except for minor shoals to 9 feet in the 10-
foot anchorage (1947). The costs from regular funds have been
$27,167 for new work and $336,732 for maintenance, a total of
$363,899. The costs from contributed funds were $61,643, of
which $11,643 was for new work and $50,000 for maintenance.
The total costs for all funds were $38,810 for new work and
$386,732 for maintenance, a total of $425,542.
                                      Cost and financial summary

                                            Fiscal year ending June 30                            Total to June
                                                                                                 30, 1954, includ-
                                                                                                 ing fiscal years
                               1950        1951        1952         1953             1954         prior to 19501

New work:..
   Appropriated----------------    ---------------------------------                ----------            $27, 167
   Cost.---------   ---------------------------------------------                  -----------             27, 167
Maintenance: ._
   Appropriated   --------    $177, 800    $69, 419    $20, 000   -$31,     210      $51, 958             386, 606
   Cost ..----------------     221, 950     43, 486     22, 228           9, 235        2, 084            336, 732

1 In addition, $11,643 was expended for new work and $50,000 was expended for maintenance from
contributed funds.

                             21. FALL RIVER HARBOR, MASS.
   Location. Situated at the mouth of Taunton River, on the east
side and at the head of Mount Hope Bay, which empties into the
ocean through Narragansett Bay and Sakonnet River. It is about
18 miles northerly from Newport Harbor. (See U. S. Coast and
Geodetic Survey Chart No. 353.)
  Previous projects. Adopted by River and Harbor Acts of June
23, 1874, March 3, 1899, June 13, 1902, and June 25, 1910. For
further details, see page 1749 of Annual Report for 1915, and page
106 of Annual Report for 1938.
  Existing project. This provides for a channel 35 feet deep and
400 feet wide adjacent to the waterfront from deep water west of
                RIVERS AND HARBORS-NEW ENGLAND DIVISION                                                 35
Common Fence Point through Mount Hope Bay and the harbor to
the wharves above the bridges, with increased width at the bend
on the approach below Slades Ferry Bridge, for a turning basin of
the same depth about 1,100 feet wide and 850 feet long above the
bridges between the Shell and Montaup wharves, for a channel 30
feet deep and generally 300 feet wide extending about 1 mile below
Slades Ferry Bridge, for removal of the lower end of Hog Island
Shoal to a depth of 30 feet and for the maintenance of the 25-foot
anchorage, about 42 acres in area, west of the harbor channel.
The length from Hog Island Shoal to the head of the project is
about 10.5 miles.
   The mean tidal range is 4.0 feet, Bristol Point, and 4.4 feet,
Fall River, and the maximum range, due to the combined effect of
wind and other causes, is 8 feet or more.
   The estimate of cost for new work (1954) is $3,682,000, exclu-
sive of amounts expended on previous projects. The latest (1950)
estimate for annual cost of maintenance is $30,000.
   The existing project was authorized by the following River and
Harbor Acts:

    Acts                          Work authorized                                   Documents
July 3,1930     30-foot channel including Hog Island Shoal and the     H. Doc. 158, 71st Cong., 2d sess.
                  maintenance of the 25-foot anchorage.
July 24, 1946   35-foot channel and turning basin---------.---------   H.     Doc. 628, 79th Cong., 2d sess.
                                                                            (Contains latest published map.)


   Local cooperation. Fully complied with, to the extent of the
work accomplished. Assurances furnished by city of Fall River
and town of Tiverton were approved November 2, 1948, by the
Assistant Secretary of the Army.
   Terminal facilities. There are 25 wharves and piers in Fall
River Harbor, of which 17 are active and in good condition, 7 are
inactive and in poor condition, and 1 is undergoing reconstruction.
Two of the wharves are publicly owned. One, owned by the city
of Fall River, is used as a landing for excursion boats, and the
other, a former steamship terminus, was reconstructed by the
Commonwealth of Massachusetts. It is a large, modern, deep-
water terminal for the receipt and shipment of general cargo.
The wharves are generally open pile and timber piers extending
from solid-filled stone bulkheads. Three have railroad connections
and eleven have mechanical handling facilities. The facilities are
considered adequate for the existing needs of general commerce.
 (For a further description of terminal facilities, see Port and Ter-
minal Facilities of Southern New England, 1941.)
   Operationsand results during fiscal year. Improvement dredg-
ing, by contract, to obtain the 35-foot channel in the vicinity of
Slades Ferry and Brightman Street bridges was accomplished
during the fiscal year, with the removal of 71,008 cubic yards of
hard-packed sand and gravel and 86 cubic yards of boulders. The
costs during the fiscal year were $114,351, all for new work.
   Condition at end of fiscal year. The existing project was about
70 percent completed. Improvement dredging, by contract, in the
vicinity of Slades Ferry and Brightman Street Bridges, initiated
36            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

in May 1954, was completed in June 1954. Separate contract will
be required for removal of ledge rock uncovered during these re-
cent dredging operations. The controlling depths at mean low
water were as follows: about 29 feet in the present 30-foot chan-
nel; 400 feet wide through Mount Hope Bay (1951) ; 35 feet in
35-foot Turning Basin (1950) ; 35 feet in the 35-foot channel to
the Gulf Oil Company wharf, with the exception of boulder areas
in the vicinity of Common Fence Point and the Bay Oil Co. wharf
where the controlling depths are 32.6 feet and 30.5 feet respectively
 (1950) ; 35 feet in the 35-foot channel from the Globe wharf to the
Shell Oil Co. wharf, with the exception of ledge on west limit of
the channel in the vicinity of the Slades Ferry bridge and Bright-
man Street bridge. The controlling depth over the ledge is about
30 feet (1954) ; 21 feet in the channel from the Gulf Oil wharf to
the Globe wharf (1944) ; 19 feet in the 25-foot anchorage (1942) ;
20 feet on Hog Island Shoal at west edge of channel (1940). To
complete the project requires removal of ledge rock at Hog Island
Shoal, and completion of the dredging of the 35-foot channel, from
the Gulf Oil wharf to the Globe wharf and removal of the ledge
in the vicinity of the Slades Ferry and Brightman Street Bridges.
The costs under the existing projects have been $2,611,182 for
new work and $313,106 for maintenance, a total of $2,924,288,
including $2,860 for maintenance dredging at the Firestone wharf
under section 3 of the River and Harbor Act of October 17, 1940.
                                        Cost and financial sumnmary

                                                Fiscal year ending June 30                        Total to June
                                                                                                 30, 1954, includ-
                                                                                                  ing fiscal years
                                 1950         1951         1952        1953            1954        prior to 19501

New work:
   Appropriated-....- -         $800, 000    $454, 000    $40, 954      -            $140, 000        $2, 967, 950
   Cost --------          --   1, 409, 518    553, 603     65, 394 - -... ...         114, 351         2, 941, 386
Maintenance:
   Appropriated-.......           39, 000       7, 430---     ------------    - -394,                         516
   Cost- -------------                 71      46,359 ----------    -         -----------                 394,516


1 Includes $330, 204 for new work and $81,410 for maintenance for previous projects.
Other new work data: Unobligated balance, fiscal year ending June 30, 1954           $13, 788
    Unobligated balances available for succeeding fiscal year ending
    June 30, 1955 ---------......          .........
                                     ----.............                                13, 788
                                                             .................---------------------
    Estimated additional amount needed to be appropriated for comp-
    letion of existing project-...........       ...........              . . ... 1,044, 254

               22. PROVIDENCE                   RIVER AND            HARBOR, R. I.
   Location. Providence River is formed at the city of Providence
by the junction of the Seekonk River and two small streams which
rise in northern Rhode Island. It is tidal and flows southerly in a
deep channel between broad flats about 8 miles, emptying into
Narragansett Bay. (See U. S. Coast and Geodetic Survey Chart
No. 278.)
   Previous projects. Adopted by River and Harbor Acts of
August 30, 1852, March 2 1867, March 3, 1873, June 18, 1878,
August 2, 1882, August 5, 1886, June 3, 1896, June 13, 1902, March
          RIVERS AND HARBORS-NEW ENGLAND DIVISION                37
3, 1905, March 2, 1907, June 25, 1910, and March 4, 1913. For
further details, see page 1750, Annual Report for 1915, page 96,
Annual Report for 1936, and page 111, Annual Report for 1938.
   Existing project. This provides for an approach channel 35
feet deep at mean low water and generally 600 feet wide through
the river from the deep water of Narragansett Bay opposite North
Point on Popasquash Neck to the turn below Field Point, 8.1 miles,
and thence with the same depth, and of width ranging up to 1,700
feet to Fox Point, excluding a marginal strip 75 feet wide channel-
ward of the established harbor lines, about 2.6 miles. The mean
tidal range is about 4.6 feet and the maximum range, due to the
combined effect of wind and other causes is 8 feet or more.
    The cost of the completed project for new work was $2,322,233,
exclusive of amounts expended on previous projects.
    The latest (1950) approved estimate for annual cost of mainte-
nance is $65,000.
    The existing project was authorized by the River and Harbor
Act of August 26, 1937 (H. Doc. 173, 75th Cong., 1st sess.). The
latest published map is in the project document.
    Local cooperation. Fully complied with. In addition to exten-
sive dredging prior to 1900 in the channel from Fox Point to the
head of navigation, the city of Providence has since spent about
 $216,000 in maintaining a 20-foot depth in this channel.
    Terminal facilities. There are 35 wharves (in use or usable
condition), including 1 owned by the State and 5 by the city
adjacent to the harbor area, Providence River below Crawford
Street, and Seekonk River below Red Bridge. The total available
berthing space is 19,170 feet. The municipal wharf at Field Point
and the State pier are open to general public use for commercial
purposes. One wharf is open to the public upon agreement with
the owner. Thirteen of the wharves have rail connections. The
facilities are considered adequate for existing commerce. (For
further details, see Port and Terminal Facilities of Southern New
England-1941.)
   Operations and results during fiscal year. A condition survey,
by hired labor, to determine extent of shoaling in the 35-foot ap-
proach channel and in the harbor was in progress at the end of
the fiscal year. Costs were $5,325, all maintenance funds.
   Condition at end of fiscal year. The existing project was com-
pleted in 1949. Under the existing project, a channel 600 feet
wide from the deep water of Narragansett Bay to the turn below
Field Point, thence to Fox Point, with a width ranging up to 1,700
feet, has been dredged to a general depth of 35 feet. The head of
commercial navigation is at Crawford Street Bridge, about 0.8
mile above Fox Point. The controlling depths at mean low water
were as follows: 33 feet in the channel from abreast North Point
to Field Point (1942-1948) ; thence generally 35 feet to Fox Point
 (1949). The costs under the existing project have been $3,487,-
567, of which $2,322,233 was for new work and $1,165,334 was for
maintenance.
38               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                         Cost and financial summary

                                                Fiscal year ending June 30                        Total to June
                                                                                                  30, 1954, includ-
                                                                                                  ing fiscal years
                                  1950         1951        1952            1953        1954        prior to 1950'

New work:
   Appropriated_     _           $210, 000                                              -               $6, 083, 645
   Cost----------------           210, 000                                                               6, 083, 645
Maintenance:
     Appropriated----...     -   -30, 544     $100, 000   $120, 000          $276       $9, 0            1,819,145
     Cost.................         604, 513     49, 097    184, 306                      5, 325          1, 815, 470

  1Includes $3,761,412 for new work and $650,136 for maintenance for previous projects.


                                     23. SEEKONK RIVER, R. I.
   Location. This river rises in the vicinity of Worcester, Mass.,
and flows in a general southeasterly direction for about 52 miles,
emptying into Providence Harbor at Providence. (See U. S. Coast
and Geodetic Survey Chart No. 278.)
   Previous projects. Adopted by River and Harbor Acts of
March 2, 1867, July 5, 1884, and March 3, 1899. For further de-
tails, see page 1749 of Annual Report for 1915, and page 113 of
Annual Report for 1938.
  Existing project. This provides for a channel 16 feet deep at
mean low water and 150 to 230 feet wide from Red Bridge up
to the ledge rock between the wharves at Pawtucket, 3.2 miles;
thence with same depth 100 to 60 feet wide throughout the ledge
to Division Street Bridge, 0.2 mile. The mean tidal range is about
4.6 feet at the mouth of the river and about 5 feet at Pawtucket,
and the maximum range due to the combined effect of wind and
other causes is 8 feet or more,
   The Federal cost of new work for the completed project was
$337,789, exclusive of amounts expended on previous projects.
The latest (1950) estimate for annual cost of maintenance is
$20,000.
The existing project was authorized by the following River and
Harbor Acts:

     Acts                            Work authorized                                        Documents
Mar.. 3, 1905     The 16-foot channel from Red Bridge in Providence,         H. Doc. 113, 56th Cong., 1st sess.
                    to Division St. Bridge in Pawtucket.
Mar.. 3, 1909     Provisional authorization to deepen the channel to         Specified in act.
                     18 feet at mean low water and increasing the width
                     at such places as would best serve the interests of
                    navigation.
Mar. 2, 1919      Widening the channel except through the ledge at           H. Doc. 1283, 64th Cong., 1st sess.
                    Pawtucket, to 150 feet.                                    (Contains latest published map.)
Sept. 22, 1922    Present project width of channel through the ledge         H. Doc. 654, 66th Cong., 2d sess.
                     at Pawtucket.


  Local cooperation. Fully complied with.
  Terminal facilities. Including the five terminals at and near
Phillipsdale, the facilities cover about 5,260 feet of docking space,
of which 700 feet is owned by the State of Rhode Island and 4,560
feet owned' and used by private owners. At the State terminal
100 feet of docking space is available for public use. The facilities
are considered adequate for the existing commerce.
  Operations and results during fiscal year. Maintenance dredg-
                      RIVERS AND HARBORS-NEW ENGLAND DIVISION                                                           39
ing, by contract, to restore project depth in the 16-foot channel
was started on December 22, 1953, and completed on March 2,
1954. During this period 219,123 cubic yards of ordinary material
were removed at a cost of $214,748, all maintenance funds.
   Condition at end of fiscal year. The existing project was com-
pleted in 1927. The controlling depths at mean low water were
16 feet (1954). The costs under the existing project have been
$337,789 for new work and $780,260 for maintenance, a total of
$1,118,049. In addition, the sum of $67,792 has been expended
for new work from contributed funds.
                                               Cost and financial summary

                                                         Fiscal year ending June 30                         Total to June
                                                                                                           30, 1954, includ-
                                                                                                           ing fiscal years
                                        1950            1951             1952     1953          1954        prior to 1950

New work:
    Appropriated                    -----------
                                     ..-------- ,       -----------------    ------------------ _ -----           1$672, 214
    Cost---....------.......     ------------       ----------- ---------------------- ------------                 672, 214
Maintenance:
    Appropriated--.....----...        -$6, 196                   ............      $2, 200     $213, 423            780, 260
         -----------...........------------------------------------
    Cost.................                                                                575       748
                                                                                                214,                   260
                                                                                                                    780,

1 Includes $334,425 for new work for previous projects. In addition, $67,792 has been expended for new
work from contributed funds.

                               24. PAWCATUCK RIVER, R. I. AND CONN.
   Location. Rises in Worden Pond, South Kingston, in south
central Rhode Island, and flows westerly and southerly, and enters
Little Narragansett Bay about 13 miles east of New London
Harbor. (See U. S. Coast and Geodetic Survey Charts Nos. 358
and 1211.)
   Previous projects. Adopted by the River and Harbor Acts of
March 3, 1871, August 14, 1876, and August 5, 1886. For further
details, see page 1752 of the Annual Report for 1915 and page 69
of the Annual Report for 1933.
   Existing project. This provides for a channel in Little Narra-
gansett Bay and in the river 10 feet deep at mean low water and
200 feet wide from Stonington to Avondale, about 4 miles; 100
feet wide from Avondale to the lower wharves at Westerly, about
3 miles; and 40 feet wide between the lower and upper wharves
of Westerly, about one-half mile; for the removal of obstruction
at Watch Hill, at the southeastern part of Little Narragansett
Bay; for a channel 10 feet deep and 100 feet wide from the mouth
of the river into Watch Hill Cove; for an anchorage basin in the
cove 10 feet deep and about 16 acres in area; and for a riprap
jetty 200 feet in length near the southwest corner of the basin.
The mean tidal range is about 2.5 feet and the maximum range,
due to the combined effect of wind and other causes, is 7 feet or
more.
   The estimate of cost for new work, (1954) is $266,000, exclusive
of $20,000 contributed by local interests, and exclusive of amounts
expended on previous projects. The latest (1950) approved esti-
mate for annual cost of maintenance is $5,000.
The existing project was authorized by the following River and
Harbor Acts:
40                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Acts                                 Work authorized                                        Documents

June 3, 1896        Present channel dimensions             --------------------H. Doc. 62, 54th Cong., 1st sess.t
Mar. 3, 1905        Removal of obstructions near Watch Hill----------...........    Specified in act.
Mar. 2, 1945        Channel, anchorage and jetty at Watch Hill Cove....             H. Doc. 839, 76th Cong., 3d sess.

1 Contains the latest published maps.


  Local cooperation. Fully complied with.
   Terminal facilities. There are five private wharves in use near
the head of navigation. At Watch Hill there are three public
wharves and the yacht club wharf with a total of about 500 feet
of berthage. Facilities are adequate for existing commerce.
  Operations and results during fiscal year. A condition survey,
by hired labor, to determine the extent of shoaling in the 10-foot
project channel in the vicinity of Rhodes Folly Beacon was com-
pleted during the fiscal years. Costs were $927, all maintenance
funds.
   Condition at end of fiscal year. The existing project was about
71 percent completed. The bay and river channels have been
dredged to project dimensions, except that the channel in the bay
has a general width of 100 feet, the channel in the river at Paw-
catuck Rocks a width of 80 feet, and there is a slight deficiency
in depth at the channel edge in the vicinity of Rhodes Folly
Beacon, due to ledge rock, or large boulders deeply embedded in
the bottom. The most obstructive boulders in the vicinity of
Watch Hill Cove have been removed, the work being completed
in 1913. The extension to the anchorage has been constructed.
The controlling depths at mean low water were as follows: 8 feet
in the maintained channel from abreast Rhodes Folly Light
through Little Narragannsett Bay to abreast Stanton Weir Point,
thence 7 feet to the upstream limit of the Federal project. An
encroachment at Sandy Point in the vicinity of Rhodes Folly
Light narrows the channel to a width of about 60 feet and a depth
of 9 feet (1952); 10 feet in channel from mouth of the river to
Watch Hill Cove anchorage basin (1949); and 10 feet in major
portion of Watch Hill Cove anchorage (1949). To complete the
project requires widening of the channel to 200 feet to Avondale,
the removal of rock at Pawcatuck Rocks and in the vicinity of
Rhodes Folly Light. The costs under the existing project have
been $181,777 for new work and $209,652 for maintenance, a
                                             Cost and financial summary

                                                      Fiscal year ending June 30                          Total to June
                                                                                                         30, 1954, includ-
                                                                                                         ing fiscal years
                                     1950           1951           1952            1953        1954       prior to 1950

New work:
   Appropriated..--------            $68, 500       -$2, 058 -----------------------                             315, 134
                                                                                                               1 $------------
   Cost---------------                96, 352 ---------------------------------                                  315,134
Maintenance:
   Appropriated _                           700 .   -.-...... --          .         $2, 879    $1, 000            209, 725
   Cost -----------------                   700 ------------------------             2, 879       927             209, 652

1Includes $133,357 for new work for previous projects. In addition, $20,000 was expended for new
work from contributed funds.
                RIVERS AND HARBORS-NEW ENGLAND DIVISION                                                             41
total of $391,429. In addition $20,000 was expended from con-
tributed funds for new work.
                           25. NEW LONDON HARBOR,                                 CONN.
   Location. On the north shore of Long Island Sound, at its east-
ern end and about 14 miles east of the mouth of the Connecticut
River. (See U. S. Coast and Geodetic Survey Chart No. 293.)
   Previous projects. Adopted by River and Harbor Acts of June
14, 1880, March 3, 1881, and July 13, 1892. For further details,
see Annual Reports for 1915 and 1938, pages 1753 and 116, re-
spectively.
   Existing project. This provides for an entrance channel gener-
ally 600 feet wide, widened at the approach to the State Pier 33 feet
deep and about 3.8 miles long from deep water in Long Island
Sound to the State Pier, a channel 400 feet or more in width, 23
feet deep, and about 6,000 feet long skirting the water front of
the city; branch channels 23 feet deep in Winthrop Cove and
east of Central Vermont Railroad pier generally 250 feet wide,
1,500 feet long and 100 feet wide, 1,000 feet long, respectively;
a maneuvering area 0 to 450 feet wide, 23 feet deep, west of
the main channel and south of the State Pier; and for dredging
Shaw Cove to a depth of 15 feet. The plane of reference is mean
low water, the mean tidal range being 2.6 feet. The maximum
tidal range, due to the combined effects of wind and other causes,
is 7 feet or more. The cost of new work for the complete project
was $567,974, exclusive of amounts expended on previous projects.
The latest approved (1950) estimate for annual cost of mainte-
nance is $10,000.
   The existing project was authorized by the following River
and Harbor Acts:
    Acts                             Work authorized                                          Documents

June 13, 1902   Waterfront channel and branch channels in Win-                    H. Doc. 392, 56th Cong., 1st sess.
                  throp Cove and east of Central Vermont Railroad
                  pier.
June 25, 1910   Dredging in Shaws Cove___.__ ______                  ________     H. Doc. 329, 60th Cong., 1st sess.z
July 27,1916                                                             ----
                Entrance channel__----...............----------................   H. Doc. 613, 63d Cong., 2d sess.'
Aug. 26, 1937   Maneuvering area and present project extent of en-                Rivers and Harbors Committee
                                                                                                         1
                  trance channel.                                                   Doc. 82, 74th Cong., 2d sess.

  1 Contains latest published maps.


  Local cooperation. Fully complied with.
   Terminal facilities. These comprise 44 wharves and piers in a
developed frontage of about 3 miles. Five piers are 'owned and
used by the Federal Government, 1 owned by the city, and 1 by
the State. Seven of the wharves are entirely or in part open to
general public use and two by agreement with the owners. Three
wharves have direct rail connections. The total available berthage
space is about 27,000 feet. Facilities are considered adequate for
existing commerce. (For further details, see Port and Terminal
Facilities at the Ports of Southern New England.)
   Operationsand results during fiscal year. A condition survey,
by hired labor, to determine the extent of shoaling in the 33-foot
main channel project and in the 23-foot waterfront channel project
42                  REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

was completed during the fiscal year. Costs were $5,788, all
maintenance funds.
   Condition at end of fiscal year. The existing project was com-
pleted in 1938. The controlling depths at mean low water were:
29 feet in entrance channel from Long Island Sound to State Pier,
not full width (1954); 20 feet in waterfront channel (1954); 22
feet in Winthrops Cove and east of C. V. Ry. Pier (1941); 23
feet in maneuvering area (1954); 15 feet (except minor shoals)
in Shaws Cove (1941). The costs under the existing project have
been $567,974 for new work and $224,825 for maintenance, a total
of $792,799.
                                                    Cost and financial summary

                                                                Fiscal year ending June 30                                  Total to June
                                                                                                                           30, 1954, includ-
                                                                                                                           ing fiscal years
                                           1950               1951              1952              1953          1954        prior to 1950

  New work:
                                                 ..--------------------------.......-----...
     Appropriated......-------- --------..................                                                                    $608, 774
                                                                                                             ------..............------
     Cost--------------------------                -------------------------- ----------------------                          1608, 774
Maintenance:
   Appropriated ................................-----------------------------------------------...........       $5,800             224, 837
   Cost--------------------                        ------------------------------------                           5, 788            224,825


  1Includes $40,800 for new work for previous projects.


                                            26. THAMES RIVER, CONN.

   Location. This a tidal estuary varying in width from about
400 feet to three-fourths of a mile, and extending from the junc-
tion of the Yantic and Shetucket Rivers at Norwich, Conn., 15
miles southerly to Long Island Sound at New London.              (See
United States Coast and Geodetic Survey Chart No. 359.)
   Previous projects. Adopted by the River and Harbor Acts of
July 4, 1836, and March 3, 1879. For further details, see page
1754 of Annual Report for 1915, and page 118 of Annual Report
for 1938.
   Existing project. This provides for a channel 25 feet deep and
250 feet wide to the upper end of Bartlett Crossover and thence
to Norwich generally 200 feet wide, with increased width in the
bends, through Long Reach, and at the head of navigation, a total
distance of about 8.6 miles; for widening the channel opposite
the submarine base by an average of about 350 feet with a depth
of 20 feet, the construction of five training walls of pile and stone
or riprap, having their tops at mean high water and with an
aggregate length of about 13,800 feet, located, respectively, at
Monhegan, Trading Cove, Long Rock, Rolling Mill, and Norwich,
and the removal of obstructions in the Shetucket River at Nor-
wich. The plane of reference is mean low water, the mean tidal
range being 2.6 feet at New London, and 3.1 feet at Norwich.
The maximum range, due to the combined effect of wind and
other causes, is 7 feet or more.
   The estimate of cost for new work (1954) is $1,360,000, ex-
clusive of amounts expended on previous projects. The latest
(1950) approved estimate for annual cost of maintenance is
$31,000.
                      RIVERS AND HARBORS-NEW ENGLAND DIVISION                                                         43
The existing project was authorized by the following River and
Harbor Acts:

    Acts                                     Work authorized                                   Documents
Aug. 2,1882           Training walls------------       ------------------        Annual Report, 1882, p. 606.
June 25, 1910         Removal of obstructions in the Shetucket River......       H. Doc. 397, 61st Cong. 2d sess.
Jan. 21, 1927         Channel 18 feet deep above Allyns Point---....-   -...H. Doc. 107, 69th Cong., 1st sess.
July 3, 1930          Present project dimensions of channel up to Allyns Rivers and Harbors Committee     1
                         Point.                                                       Doc. 14, 71st Cong., 2d sess.
Aug. 30, 1935         Present project dimensions of channel above Allyns         Rivers and Harbors Committee
                                                                                                        1
                        Point.                                                     Doc. 18, 74th Cong., 1st sess.
Mar.   2,1945         Increased width opposite submarine base, 20 feet deep.     H. Doc. 367, 76th Cong., 1st sess.'

  1 Contains latest published maps.


  Local cooperation. Fully complied with.
   Terminal facilities. Wharves along the river and at Norwich
are mainly of the bulkhead type, both with and without pile
aprons. The facilities are considered adequate for the existing
commerce.
   Operationsand results during fiscal year. Maintenance dredg-
ing, by contract, to restore project depth in the 25-foot channel
from the Submarine Base to Allyns Point was started on March
17, 1954, and completed on May 1, 1954. During this period
158,480 cubic yards of ordinary material were removed at a cost
of $136,263, all maintenance funds.
   Conditions at end of fiscal year. The existing project was sub-
stantially completed. The training walls were completed in 1906,
except the upper end of the Rolling Mill Dike, which is replaced
by adjacent shore improvements. The training walls are in 'fair
condition. The widening opposite the submarine base was com-
pleted in 1940 by the Navy Department. To complete the project
requires slight widening of the channel at the upper end of Long
Reach. The head of navigation is at Norwich, about 15 miles
above the mouth. The, controlling depth is 25 feet in the 25-foot
channel from the south end of the U. S. Submarine Base to Allyns
Point (1954), thence 22 feet in the middle half and 17 feet in the
outside quarters to Monhegan Dike Light, thence 24 feet in the
westerly three quarters and 19 feet in the easterly quarter to
the head of the project at Norwich (1953). The costs under the
existing project have been $1,323,571 for new work and $908,750
for maintenance, a total of $2,232,321.
                                                 Cost and financial summary

                                                       Fiscal year ending June 30                         Total to June
                                                                                                         30, 1954, includ-
                                                                                                         ing fiscal years
                                          1950        1951        1952         1953           1954        prior to 19501
New work:
    Appropriated--...
                  -------------   ------------------------------                        -------------         $1, 471, 919
    Cost----------------------------------------------------                           -- -------   -----      1, 471, 919
Maintenance:
    Appropriated........                  $153,811 -----------------------     $3, 600       $143, 100            952, 283
    Cost ........--------------........    274, 599 ------------------------    3, 501        136, 263            945, 346

  1Includes $148,348 for new work and $36,596 for maintenance for previous projects.
Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project.............................................. ............ $36, 429
 44        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

      27. CONNECTICUT     RIVER    BELOW    HARTFORD,     CONN.
     Location. This river has its source in Connecticut Lake in
  northern New Hampshire, flows southerly 380 miles, and empties
  into Long Island Sound at Saybrook, Conn., 14 miles west of
  New London. Hartford, now the head of commercial navigation,
  is 52 statute miles, by channel, from the mouth. (See U. S. Coast
  and Geodetic Survey Charts Nos. 215, 266, 267.)
     Previous project. Adopted by the River and Harbor Acts of
  July 14, 1836, and July 11, 1870. For further details, see page
  1754, Annual Report for 1915, and page 120, Annual Report for
  1938.
     Project for Eightmile River, Conn.: Elimination as separate
project. This provides for a channel 8 feet deep and 75 feet wide
from deep water in the Connecticut River to Hamburg and for
turning basin of the same depth, 150 wide, approximately 300
feet long at Hamburg. The project was adopted by the River
and Harbor Act of June 25, 1910. The costs and expenditures have
been $9,000, all for new work. In accordance with the River
and Harbor Act of May 17, 1950, the project for Connecticut River
below Hartford was modified to include the project for Eightmile
River, which was eliminated as a separate project. The afore-
mentioned act also provided for an anchorage basin 6 feet deep
and about 6.5 acres in area in the upper cove at Hamburg.
    Existing project. This provides for a channel 15 feet deep at
mean low water, 300 feet wide from the mouth to the Lyme rail-
road bridge, about 3.4 miles, and thence 150 feet wide to Hart-
ford, a total distance of 52 miles, the channel to be obtained by
dredging and the construction of dikes, training walls, revet-
ments, and the accessory works; for two riprap jetties at the
mouth of the river, the tops to be 5 feet above high water and
6 feet wide, the easterly one about 2,300 feet and the westerly about
2,750 feet in length; for a training dike about 3,700 feet long at
Hartford, and for anchorage 11 feet deep, about 12 acres, and
one, 6 feet deep, about 17 acres, in North Cove, Old Saybrook,
with an entrance channel 11 feet deep and 100 feet wide; for a
channel 8 feet deep, 75 feet wide about 1.5 miles in length from
the Connecticut River to Hamburg; a turning basin of the same
depth 150 feet wide and 300 feet long at Hamburg; and an
anchorage area at Hamburg 6 feet deep, about 6.5 acres in area,
in Eightmile River. The mean tidal range is 3.5 feet at the mouth,
and at summer stage is about 1 foot at Hartford. The maximum
tidal range at the mouth due to wind or other causes, is 8 feet
or more. At Hartford the usual rise due to spring freshets is
between 16 and 24 feet above mean low water. The maximum
recorded freshets at Hartford (March 1936) was 35.5 feet above
mean low water. Below Middletown the height of the crest of
the freshet decreases rapidly.
    The estimate of cost for new work (1954) is $1,339,000, ex-
clusive of $85,500 to be contributed by local interests. The latest
(1950) approved estimate for annual cost of maintenance is
$90,000.
  The existing project was authorized by the following River and
Harbor Acts:
                RIVERS AND HARBORS-NEW ENGLAND DIVISION                                                    45
    Acts                               Work authorized                                Documents
June 10, 1872   Jetties at the mouth----------..................     ---   Present project dimensions ap-
                                                                             proved by the Chief of Engi-
                                                                             neers, Dec. 22, 1887.
Mar. 3,1881     The Hartford dike_--_--          -----------------         Present project dimensions author-
                                                                             ized by the Chief of Engineers in
                                                                             1889.
June 25,1910    Channel and turning basin in Eightmile River----.......    H. Doc. 327, 60th Cong., 1st sess.
Feb. 27,1911    Present project dimensions of the channel over Say-        H. Doc. 1294, 61st Cong., 3d sess.
                  brook bar.
Mar. 2, 1919    Dikes, training walls, and revetments----....---------     H. Doc. 132, 65th Cong., 1st sess'
                                                                                                            1
Aug. 30,1935    Present project dimensions of channel and additional       H. Doc. 49, 73d Cong., 1st sess.
                  dikes, training walls revetments, and accessory
                  works.
May 24,1937     Park River declared nonnavigable----------....-..          Ltr. Sec. War, Apr. 21, 1937.
Mar. 2,1945     Channel and anchorages, North Cove, Old Saybrook.          H. Doc. 368, 76th Cong., 1st sess.'
May 17,1950     Channel, anchorage, and turning basin, Eightmile           H. Doc. 6664 80th Cong., 2d sess.
                  River.

  1Contains the latest published maps.
   Local cooperation. The River and Harbor Act of August 30,
1935, authorized the 15-foot channel up to Hartford and additional
dikes, training walls, and revetments, subject to provision that
local interests shall furnish, free of cost to the United States,
suitable areas for the disposal of dredged material during initial
construction and for future maintenance as and when needed.
Areas have been furnished where required and it is understood
that future requirements will be met. The River and Harbor
Act approved March 2, 1945, authorized the channel and anchor-.
ages in North Cove subject to the provisions that local interests
contribute in cash $67,500, but not to exceed 50 percent of the
initial construction cost and give assurances satisfactory to the
Secretary of War that they will provide a suitable public landing
in the cove. The River and Harbor Act of May 17, 1950, author-
ized the channel, anchorage, and turning basin in Eightmile River,
provided that local interests contribute in cash 50 percent of the
initial cost of dredging, but not to exceed $18,000; construct
public landing facilities of a design satisfactory to the Chief of
Engineers; provide suitable spoil disposal areas, as and when re-
quired, for new work and subsequent maintenance; and hold and
save the United States free from claims for damages resulting
from the improvement. It is expected that these conditions will
be met.
   Terminal facilities. On both the Connecticut and Eightmile
Rivers there are two or three wharves at each, of the river towns,
one or more in each town being open to public use. At Hartford
and at Middletown there is approximately one-half of wharf
frontage along the west bank of the river. The facilities are con-
sidered adequate for existing commerce.
   Operations and results during fiscal year. A survey, by hired
labor, to determine extent of repairs necessary to restore the east
jetty at Saybrook was completed during the fiscal year. Mainte-
nance dredging, by contract, to restore project depth in the 15-
foot channel from the mouth of the river to Hartford was started
on September 9, 1953, and completed on December 10, 1953. Dur-
ing this period 356,495 cubic yards of ordinary material were
removed. The total costs during the fiscal year were $206,081,
all maintenance funds.
46              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Condition at end of fiscal year. The existing project is about
62 percent completed. The 15-foot channel from the mouth to
Hartford, was completed in 1937. The Saybrook jetties and
training walls at Hartford, Clay Banks, and Sears Shoal were
completed in 1915. The stone dikes and timber spurs at Pistol
Point, Glastonbury, Press Barn, Naubuc, Cys Hollow, and Clay
Banks were completed in 1927 and those at Wethersfield in 1947.
Timber pile dikes at Press Barn were completed in 1940 and at
Glastonbury Bend in 1943. The Clay 'Banks, Cys Hollow, Naubuc,
Press Barn, Glastonbury (including Two Piers), and Gildersleeve
Island reaches have been revetted. The jetties at Saybrook need
repairs. The training walls, dikes, and revetments are generally
in good condition. To complete the project requires the construc-
tion of additional permanent works; dredging the channel and
anchorage in North Cove, Old Saybrook, Connecticut, and the
dredging of the 6-foot channel, turning basin, and anchorage in
Eightmile River at Hamburg. The head of commercial navigation
is at Hartford, 52 miles by channel from the mouth. A dam at
Holyoke, Mass., 34 miles above Hartford, completely interrupts
navigation. The controlling depths at mean low water are gen-
erally 15 feet to Hartford (1953) ; 1-foot in entrance channel to
North Cove (1938); 0 feet in anchorages in North Cove (1938);
7 feet in channel and basin in Eightmile River (1946); 1 to 6 feet
in anchorage at Hamburg (1946).
   The costs under the existing project have been $858,556 for
new work which includes $9,000 of completed new work (existing
project) transferred from Eightmile River project and $2,209,244
for maintenance, a total of $3,067,800.
                                                  Cost and financial summary

                                                               Fiscal year ending June 30                        Total to June
                                                                                                                30, 1954, includ-
                                                                                                                ing fiscal years
                                       1950                  1951            1952         1953       1954        prior to 19501
New work:
   Appropriated                  -----.......------------                                                           2 $1, 145, 930
   Cost-------            --------------------------------------------------------                                   2 1, 145, 930
Maintenance:
     Appropriated ....-     -          $58, 000             $160, 000       $10, 000    -$23, 780   $202, 951          2, 577, 349
     Cost----        _-------.
                           --          250, 692               10, 094        125, 409       7,149    206, 081          2, 575, 592

1 Includes $287,374 for new work and $366,348 for maintenance for previous projects.
2Includes $9,000 expended for new work for subproject: "Eight Mile River, Conn."
Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project .. __ - ------
                                                   ........ ........
                                                               _.................... . $480, 444
                                     28. MILFORD HARBOR, CONN.
  Location. On the north shore of Long Island Sound, about 8
miles west of New Haven Harbor. (See U. S. Coast and Geodetic
Survey Chart No. 219.)
  Previous projects. Adopted by acts of June 23, 1874, June 18,
1878, June 14, 1880, and August 2, 1882. For further details, see
Annual Report for 1915, page 1756, and Annual Report for 1938,
page 129.
                RIVERS AND HARBORS-NEW ENGLAND DIVISION                                                      47
  Existing project. This provides for two riprap jetties 510 and
250 feet in length on the east and west sides, respectively, of the
entrance to the river; a channel across the bar and through the
lower harbor 10 feet deep and 100 feet wide to Merwin's wharf,
a distance of about 3,000 feet; an anchorage basin of the same
depth, of about 6 acres east of the channel; a channel 8 feet deep
and 100 feet wide, widened at bends and at the upper end, from
Merwin's wharf to 400 feet above the town wharf, about 3,000
feet; and for an anchorage basin west of the channel inside of
the entrance 2,000 feet long and 7.8 acres, 10 feet deep in the
lower 600 feet and 8 feet deep above. All depths refer to mean
low water. The mean and spring tidal ranges are 6.6 and 7.8 feet,
respectively. The estimate of cost for new work (1954) is $95,000,
exclusive of $11,380 contributed by local interests and exclusive
of amounts expended on previous projects. The latest (1950)
approved estimate for annual cost of maintenance is $4,000.
  The existing project was authorized by the following River and
Harbor Acts:
    Acts                           Work authorized                                       Documents
June 2, 1874    East jetty at the mouth of the river ..   _---------------   H. Ex. Doc. 107, 42d Cong., 3d sess.,
                                                                               and Annual Report 1873, p. 1042.
                West jetty at the mouth of the river ...--------------       Authorized by Department Oct.
                                                                               16, 1879, Annual Report for 1879,
                                                                               p. 342.
June 13, 1902   Entrance channel and anchorage basin east of it-....         H. Doc. 280, 56th Cong., 1st sess.
Aug. 26, 1937   Anchorage west of the channel and present project            H. Doc. 77, 75th Cong., 1st sess.
                 dimensions of the channel above Merwin's wharf.               (Contains latest published map.)


  Local cooperation. Fully complied with. Spoil disposal areas
are required for maintenance.
   Terminal facilities. There are three bulkhead wharves near
the entrance used by the oyster industry. The town wharf near
the head of navigation is open to public use. The Connecticut
State Shellfish Commission operates a small wharf not open to
the public. There are also several yacht landings. The facilities
are ample for existing traffic.
  Operations and results during fiscal year. A condition survey,
by hired labor, to determine extent of shoaling in the 10-foot and
8-foot project channels and in the 10-foot and 8-foot project
anchorage basins was completed during the fiscal year. Costs were
$906, all maintenance funds.
   Condition at end of fiscal year. The existing project is 55 per-
cent completed. Work remaining to be done consists of a portion
of the 10-foot anchorage basin east of the channel where ledge
rock prevents completion at reasonable cost. The jetties were
completed in 1880. The controlling depths at mean low water are
as follows: 9 feet to Merwin's Wharf (1953) thence 4 feet to the
head of the project (1953) ; 0 to 10 feet in the East Basin (1931) ;
7 feet in the West Basin (1953). The costs under the existing
project have been $145,933, of which $46,376 was for new work
and $99,557 was for maintenance. In addition $11,380 was ex-
pended from contributed funds for new work.
48               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                              Cost and financial summary

                                                           Fiscal year ending June 30                                 Total to June
                                                                                                                      30, 1954, includ-
                                                                                                                      ing fiscal years
                                       1950              1951               1952              1953           1954      prior to 19501

New work:
   Appropriated---------       ------------
                                 -          ........    -       . - --.-      .       -.    ---- .$88,                              716
   Cost-----       -----------------------------------------                    ----------- -----------                         88, 716
Maintenance:
   Appropriated........           $500 .-----..------..--------..------------                     $906                        102, 717
   Cost....-----------------       263            $237       .-----------------------               906                       102, 717


1 Includes $42,340 for new work and $3,160 for maintenance for previous projects.
s In addition, $11,380 was expended for new work from contributed funds.
Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project...-... ...........................-..-..........   ... . $48, 624
                                                                                           ....

                                 29. SOUTHPORT HARBOR, CONN.
   Location. On the north shore of Long Island Sound, about 50
miles east of New York City. (See U. S. Coast and Geodetic
Survey Chart No. 220.)
  Previous projects. Adopted by the River and Harbor Act of
March 2, 1829, and modified in 1876 and 1881. A second project
was adopted by the River and Harbor Act of June 13, 1902, and
modified by the River and Harbor Act of July 25, 1912. For
further details, see Annual Reports for 1915 and 1936, pages
1758 and 121, respectively.
   Existing project. This provides for a stone breakwater about
1,320 feet long at the harbor mouth; a 1,350-foot dike along the
east side of the harbor; a channel 9 feet deep to the upper end
of the wharves, 100 feet wide from Long Island Sound to opposite
East Main Street, thence 400 to 175 feet wide; and for an anchor-
age basin 6 feet deep, 300 feet wide, and 500 feet long. The
reference plane is mean low water, the mean tidal range being
6.9 feet. The maximum range, due to the combined effect of wind
and other causes, is 11 feet or more.
   The cost of new work for the completed project was $54,213,
including $16,500 contributed by local interests but exclusive of
amounts expended on previous projects. The latest (1950) ap-
proved estimate for annual cost of maintenance is $2,500.
   The existing project was authorized by the following River and
Harbor Acts:
     Acts                                  Work authorized                                                    Documents
Mar. 2, 1829     Breakwater and dike--------------------------.................................   Annual Report for 1871, p. 824.
Aug. 30, 19351   Anchorage basin and present channel dimensions-.....                             Rivers and Harbors Committee
                                                                                                     Doc. 36, 74th Cong., 1st sess.
                                                                                                     (Contains latest published map.)

  I Also Emergency Relief Appropriation Act of May 28, 1935.

  Local cooperation. Fully compiled with.
  Terminal facilities. The several small wharves and private
landings for pleasure craft are ample for existing traffic.
  Operations and results during fiscal year. A condition survey,
by hired labor, to determine extent of shoaling in the 9-foot
project channel and in the 6-foot project anchorage was com-
                 RIVERS AND HARBORS-NEW ENGLAND DIVISION                                                      49
pleted during the fiscal year. Costs were $623, all maintenance
funds.
  Condition at end of fiscal year. The existing project was com-
pleted in 1936. The dikes are in fair condition and the break-
water is in good condition. The channel was restored to project
dimensions in 1948. The controlling depths at mean low water
are: 7 feet in the 9-foot channel from Long Island Sound to about
200 feet south of the Southport Breakwater Light, thence a shoal
about 200 feet wide extending across the channel in the vicinity
of the Southport Breakwater Light, having a depth of 2 feet in
the easterly half, and 6-feet in the westerly half of the channel,
thence 6 feet to the 6-foot anchorage; 5 feet in the 6-foot anchor-
age to the upstream limit of the Federal Project (1954).

                                        Cost and financial summary

                                                Fiscal year ending June 30                         Total to June
                                                                                                  30, 1954, includ-
                                                                                                  ing fiscal years
                                 1950          1951         1952          1953          1954       prior to 19501

New work:
   Appropriated ...------------------------------------------------------------                           $96, 927
     Cost
   Cost
Maintenance:
                                  ...
        ......... ---------- ------------          ------------ ------------ ------------ ------------         927
                                                                                                          2'296,
                                                                                                           96, 927

   Appropriated ---           -----------------------------------------------                 $623          42, 224
   Cost----------              ------------------------------------              ------------ 623           42, 224

  1 Includes $59,213 for new work and $8,932 for maintenance for previous projects.
  2 Includes $37,714 expended for new work from emergency relief funds. In addition, $18,285 has been
expended for new work from contributed funds, of which $1,785 was for work outside the approved
project.

                              30. NORWALK HARBOR, CONN.
   Location. On the north shore of Long Island Sound, about 40
miles east of New York City. (See U. S. Coast and Geodetic
Survey Charts Nos. 221 and 1213.)
   Previous projects. Adopted by River and Harbor Acts of June
10, 1872, June 3, 1896, and March 2, 1907. For further details
see page 1757 of Annual Report for 1915 and page 137 of Annual
Report for 1938.
   Existing project. This provides for a channel 12 feet deep from
the outer harbor to the highway bridge at South Norwalk, about
3.1 miles, 200 feet wide to Gregory (Dorlon) Point, thence 150
feet wide to South Norwalk, and 250 feet wide along the South
Norwalk wharves, thence a channel 10 feet deep and generally
100 feet wide to the head of navigation about 1.5 miles; an
anchorage basin 10 feet deep and about 17 acres in area opposite
Fitch Point; a channel 6 feet deep from the 10-foot anchorage
to East Norwalk, 125 feet wide to the bend beyond Third Street,
thence 150 feet wide to the head, a total distance of 2,900 feet;
and for an irregular-shaped anchorage basin of about 7 acres, 6
feet deep adjacent to the upper portion of the East Norwalk
channel. All depths refer to mean low water. The mean and
spring tidal ranges at South Norwalk are 7.1 and 8.4 feet, respec-
tively. The cost of new work for the completed project was
$368,612, exclusive of $34,500 contributed by local interests and
exclusive of amounts expended under previous projects. The
50               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

latest (1950) approved estimate for annual cost of maintenance
is $10,000.
   The existing project was authorized by the following River and
Harbor Acts:
     Acts                         Work authorized                                             Documents
Mar.    2,1919   South Norwalk and Norwalk channels; 10-foot an-              H. Doc. No. 1143, 63d Cong., 2d
                  chorage.                                                     sess.
Mar. 2,1945      East Norwalk channel widening and anchorage--......          H. Doec. No. 220, 76th Cong., 1st
                                                                               sess. (Contains latest published
                                                                                   maps.)



   Local cooperation. Fully complied with.
   Terminal facilities. There are two city wharves, neither of
which is in usable condition. There are 19 private wharves in use
or in usable condition having a total berthing space of about
3,100 feet.   One has rail connections.      None of the private
wharves are open to general use. The public wharves are inade-
quate for existing commerce.     (For further details, see Port and
Terminal Facilities of Southern New England, 1941.)
   Operations and results during fiscal year. A condition survey,
by hired labor, to determine extent of shoaling in the 10-foot
project channel from the Washington Street Bridge to Norwalk
was completed during the fiscal year. Maintenance dredging, by
contract, to restore project depths in the 12-foot main channel
and in the 6-foot East Norwalk channel was started on May 4,
1954, and was still in progress at the end of the fiscal year. Dur-
ing the period 107,671 cubic yards of ordinary material were
removed. The total costs during the fiscal year were $70,406.
   Condition at end of fiscal year. The existing project was com-
pleted in 1950. The controlling depths at mean low water are as
follows: maintenance dredging in progress in the 12-foot channels
from Long Island Sound to the Washington Street Bridge (1954),
thence 5 feet to the head of navigation in Norwalk (1953); 6 to
12 feet in the basin at Norwalk (1940); 5 feet in the 10-foot
anchorage basin (1953); maintenance dredging in progress in the
6-foot East Norwalk channel from Fitch Point Light to the
upstream limit of the Federal project (1954); 4 feet in the 6-foot
anchorage basin, East Norwalk (1954). The costs under the
existing project have been $368,612 for new work and $282,384
for maintenance, a total of $650,996. In addition, $35,500 was
expended for new work from contributed funds.
                                      Cost and financial summary

                                              Fiscal year ending June 30                                 Total to June
                                                                                                        30, 1954, includ-
                                                                                                        ing fiscal years
                               1950          1951          1952             1953             1954         prior to 19501
New work:
     Appropriated........      $22,000------------                     -$20, 077 ...........------------
                                                                                             2 $531, 129
     Cost ---------------      113,344   -$2, 171-----------------   ----                    .2                  531, 129
Maintenance:
   Appropriated-------........ --.....-----...---....
                                         200 -..........   3, 000                           $165, 000            443, 488
   Cost.------------------- ----------   200 -.......-.. - 2,609                              70,406             348, 504

1Includes $162,517 for new work and $66,120 for maintenance for previous projects.
I In   addition, $34,500 was expended for new work from contributed funds.
               RIVERS AND HARBORS-NEW ENGLAND DIVISION                                                51
                          31. STAMFORD HARBOR, CONN.
   Location. On the north shore of Long Island Sound, 32 miles
east of New York City. (See U. S. Coast and Geodetic Survey
Chart No. 221.)
   Previous projects. Adopted by the acts of August 5, 1886, and
July 13, 1892. For further details, see page 1758 of Annual Re-
port for 1915, and page 139 of Annual Report for 1948.
   Existing project. This provides for two detached breakwaters;
one 1,200 feet long on the easterly side, and one 2,900 feet long on
the westerly side of the channel at the entrance to the harbor; an
entrance channel 18 feet deep, 200 feet wide to the upper end of
the 18-foot anchorage, about 0.55 mile, and thence 15 feet deep to
the junction of the branches, about 0.5 mile; a channel in the west
branch 15 feet deep, 125 feet wide, and about three-fourths of a
mile long, and a basin of the same depth at the head of the branch
of such widths as to exclude extensive rock excavation along the
northeast side; a channel in the east branch 12 feet deep and 100
feet wide, with increased width at the turns, to a point 1,100 feet
from the head of navigation, thence of the same depth and from
85 to 125 feet wide to the head of navigation, a total distance of
about 1.5 miles; and anchorage basin 18 feet deep on the west side
of the 18-foot entrance channel, 600 feet wide, and 1,000 to 1,900
feet long, and an anchorage basin 8 feet deep adjacent to the East
Branch Channel, about 4.2 acres. The plane of reference is mean
low water, the mean tidal range being about 7.2 feet. The extreme
tidal range, due to the combined effects of wind and other causes,
is 12 feet or more.
   The estimate of cost for new work (1954) is $881,000, exclusive
of $169,635.85 contributed by local interests, and exclusive of
amounts expended on previous projects. The latest (1950) ap-
proved estimate for annual cost of maintenance is $30,000.
   The existing project was authorized by the following River and
Harbor Acts:
    Acts                        Work authorized                                   Documents
Mar. 2,1919     he East Branch channel and the present project        H. Doc. 1130, 63d Cong., 2d sess.
                width of the entrance channel.
Aug. 30,1935   The 8-foot anchorage area, the present project depth   Rivers and Harbors Committee
                of the upper portion of the entrance channel, and      Doc. 8, 74th Cong., 1st sess.
                the present project dimensions of the West Branch
                channel and basin.
Aug. 26,1937   The breakwaters, the 18-foot anchorage basin, and      Rivers and Harbors Committee
                present project depth of the outer section of the       Doc. 29, 75th Cong., 1st sess.'
                entrance channel.
July 24,1946   Substituted 8-foot anchorage basin adjacent to East    H. Doc. 676, 79th Cong., 2d sess.'
                 Branch channel for that in outer harbor.

  1Contain latest published maps.

  Local cooperation. The-conditions of local cooperation imposed
by the River and Harbor Acts of March 2, 1919, and August 26,
1937, have been fully complied with. The River and Harbor Act
approved July 24, 1946, authorized the 8-foot anchorage basin
adjacent to the East Branch channel subject to the condition that
responsible local agencies furnish assurances satisfactory to the
Secretary of War that they will provide free of cost to the United
States all necessary lands, easements, rights-of-way and spoil dis-
52             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

posal areas for new work and subsequent maintenance when and
as required; construct concurrently the necessary bulkheads, piers,
landing platforms, and service facilities which shall be open to all
on equal terms; and hold and save the United States free from
damages resulting from the improvement. Local interests were
informed under dates of September 22, 1948, April 5, 1949, May
13, 1949, and December 14, 1949, of the above-mentioned require-
ments of local cooperation. No statement has been received as to
when and if these requirements will be met.
   Terminal facilities. There are 21 privately owned wharves and
piers and one city wharf in use adjacent to the channels in the
East and West Branches. The total available berthage is about
4,500 feet. None of the wharves is open to general public use,
except the city wharf. Two have direct rail connections. The
facilities are considered adequate for existing commerce, but ad-
ditional pleasure-craft facilities are needed. (For further details,
see Port and Terminal Facilities of Southern New England, 1941).
   Operations and results during fiscal year. A condition survey,
by hired labor, to determine extent of shoaling in the 18-foot proj-
ect entrance channel, the 15-foot project West Branch channel and
basin and the 12-foot project East Branch channel was completed
during the fiscal year. Costs were $2,033, all maintenance funds.
   Condition at end of fiscal year. The existing project is about
91 percent completed. The East Branch channel has been com-
pleted except for a slight deficiency in width opposite Ludlow
Street. The West Branch channel and entrance channel north of
the 18-foot anchorage have been dredged to 15 feet and all of the
basin similarly deepened. The 18-foot entrance channel and 18-
foot anchorage basin have been substantially completed. The con-
trolling depths at mean low water are as follows: 17 feet in the
18-foot entrance channel (1954) ; 15 feet in the 15-foot entrance
channel (1954) ; 15 feet in the West Branch Channel to abreast
Cook Point, thence 13 feet in the easterly half and 15 feet in the
westerly half to the turning basin (1954) ; 15 feet in the down-
stream half and 12 feet in the upstream half of the 15-foot West
Branch turning basin (1954) ; 8 feet in the 12-foot East Branch
Channel (1954) ; 16 feet in the 18-foot anchorage (1954).        To
complete the project requires a slight widening (not essential to
navigation) in the East Branch channel opposite Ludlow Street
                                           Cost and financial summary

                                                        Fiscal year ending June 30                        Total to June
                                                                                                        30, 1954, includ-
                                                                                                         ing fiscal years
                                   1950               1951               1952    1953        1954         prior to 1950 1

New work:
    Appropriated------- ------------- -$53, 619 -------------------                                             $892, 824
                                                                                                              2-------
    Cost-----------------       $138-----------------------                     ----------   -----------         892, 824
Maintenance:
    Appropriated      ------------------------------------------------                         2, 500            230, 582
    Cost--------        --------------------------------------------                           2, 033            230,115


  1Includes $135,143 for new work and $59,420 for maintenance for previous projects.
  2 In addition, $169,636 was expended for new work from contributed funds.


Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project..................................................... $123, 319
                       RIVERS AND HARBORS-NEW ENGLAND DIVISION                                                                                               53
and the dredging of the 8-foot basin adjacent to the East Branch
channel. Costs under the existing project have been $928,376, of
which $757,681 was for new work and $170,695 was for mainte-
nance. In addition, costs have been $169,636 from contributed
funds for new work.
                                32. INACTIVE                          NAVIGATION                          PROJECTS

                                                                                       For last          Costs to June 30, 1954
                                                                                           full                                                   Estimated
                                                                                        report,                                                     amount
                              Name of project                                             see                                Operation            required to
                                                                                        annual             Con-              and main-             complete
                                                                                        report          struction             tenance

1.    Bagaduce River, Maine 1                  ----------------.......................---
                                                                                         1912               $28, 000                                     $50, 000
2.    Bar Harbor, Maine---........----.------                        ----               1932               406, 591 ...                ..                 75, 400
3.    Bass Harbor Bar, Maine-...........-...........                            ..      1920                   4, 076               3, 418             (*)
4.    Beals Harbor, Maine..-----------------------                                       1949 .--.....................                                  200, 000
5.    Bellamy River, N. H. 1 4             --------...........                          1897                 34, 643 .--...-.-....                     (*)
6.    Beverly Harbor, Mass._--------....------                               -           1951               197, 565                1, 718             (*)
7.    Block Island (Harbor of Refuge, R. I.) 1...........                               1953                576, 856            445, 202                  49, 000
8.    Block Island (Great Salt Pond, R. I.) 0 s...........                               1953               189, 037              96, 047           6 7 452, 000
9.    Boothbay Harbor, Maine 4.                 .         ..            .                1953                18, 000                   858             (*)
10.    Branford Harbor, Conn.................--                   .-..-.            . 1953                      9, 537           119, 346               (*)
11.    Bridgeport Harbor, Conn........................--                          .      1953            2, 206, 898          * 750, 779                 113, 000
12.    Bucksport Harbor, Maine--------............-..--                                   1907                18, 421                   279            (*)
13.    Burial Hill Reach, Conn.-- ------------------                                     19590------------------------10                                    8,000
14.    Buttermilk Bay (Channel), Mass.-:_________                            -:          1953                 31, 676 .          .----------.           (*)
15.    Camden Harbor, Maine ---------------.-.-                                          1945                 72, 400              31, 075             (*)
16.    Canapitsit Channel, Mass. 4.......................                                1899                   9, 113 .............                   (*)
17.    Carvers Harbor, Maine               --..       ----                               1915                 16, 000 .........-..                     (*)
18.    Cathance River, Maine 1 4-                                                         1884                21, 000 ......                            (*)
19.    Chatham (Stage) Harbor, Mass.----.....                               -          -..1953-       ....                                            11157, 000
20.    Clinton Harbor, Conn.....-.--......---..                                           1952             12 79, 005                1, 917             ()
21.    Coasters Island (Harbor), R. I. 4 1s................                               1911                  5, 500              13, 052            (*)
22.    Cobscook Bay, Maine 1          ---                         ----                   1866                   4, 173 .                    -           (*)
23.    Cocheco River, N. H. 1 4         -----                           ---.............. 1913               119, 089                9, 643             (*)
24.    Cohasset Harbor Mass. -----                ....--..                                19.--4----....
                                                                                          1949                  .14                                      165, 000
25.    Compo Beach, W5estport, Conn.                     ....------              ..      1950                 ---             --        -              15 55, 000
26.    Connecticut River (Above Hartford), Conn. 1i....                                   1932               116, 324               14, 374       17 12, 784, 000
27.    Criehaven Harbor, Maine--.........................                                 1939                40, 776                7, 956             (*)
28.    Damariscotta River, Maine 2 4_                 --...........---..                  1906                  5, 000 _----....-...-(*)
29.    Deer Island Thoroughfare, Maine                       ---------------              1916                40, 000 .............                    (*)
30. Duck Island Harbor Conn....
                            -------                                        ----            1953              367, 298             346, 319             (*)
31.    Duxbury Harbor, Mass....._____                                                      1949                                             -         18195, 000
32.    East Boothbay Harbor, Maine..- ----------                                         - 1953               6, 500                   16, 448        (*)
33.    Edgartown Harbor, Mass. Is ____                                                     1943         1925, 614 ............                        (*)
34.    Essex River, Mass... -----------                    ----------                      1948            21, 799                64 60, 050          (*)
35.    Exeter River, N. H. 2 ......                                             .-------- 1913             27, 454 .............                      (*)
36.    Falmouth Harbor, Mass.........---------------------. 1948                                                                                         55,000
                                                                                                                                                       o-------------
37.    Fivemile River Harbor, Conn. a 21-                        -                   . 1953                35,490                      31, 311            14,500
38.    Georges River, Maine                     --           --.............--------- 1935                 25, 788                     39, 566        (*)
3 9.   G re e n wic h B ay , R . I.- Is . . . . . . . . . . . . . . .               ..     18 9 3             2 , 0 0 0 - - - - - - . - - -..      - (*)
40.    Greenwich Harbor, Conn.------....                                -------            1953      22 181, 741                     s 64, 139        (*)
41.    Guilford Harbor, 4Conn...............-------....                                    1949                                                     24 110, 000
42.    Harraseeket River, Maine 24......................                                   1896            30, 963----                    -           (*)
43.    Hay (West) Harbor, Fishers Island, N. Y. Is......                                   1931               8, 401 ..                               (*)
44.    Hendricks Harbor, Maine---.....                   .---       --        ---          1949      --.-..-..--.         _...........                   15, 000
45.    Housatonic River, Conn.---.........................1953                                           234, 365           65  25 297, 743           1,
                                                                                                                                                       250 000
46.    Hyannis Harbor, Mass....                    .---------------------- 1951                           197, 383                     56, 265      2 234, 400
47.    Isle Au Haut Thoroughfare, Maine.....-.........                                     1949                                                          65, 000
48.    Ipswich River Mass ..                --                 ---.....           -.       1950               5, 618                    2, 151        (*)
49.    Jennings Beach and Ash Creek, Conn.-_________                                       1950       _                     -                         2715, 000
50.    Josias River, Maine_--..-..          .-               _---..
                                                        -...---.-.--.                      1952         2830, 658-                 -.-     -          (*)
51.    Kingston Harbor (North Plymouth), Mass. 2......                                     1895               8, 940 _---                     -       (*)
52.    Lake Winnepesaukee, N. H.-..-_.                           ------                    1952               7, 500                   29, 651        (*)
53.    Lamprey River, N. H. 2 -..........................                                  1913             19, 980                     8, 268        (*)
54.    Little Harbor, N. H. 4 29--.........................                                1909           133, 227                      3, 122        (*)
55.   Little Harbor, Woods Hole, Mass. s -- ----------                                    1906             18, 000 ---------                         (*)
56.    Lubec Channel, Maine-........-------------_____                               .     1950           134, 411                      7, 067        (*)
57.    Lynn Harbor, Mass......------------------------..                             .            ...............-----........
                                                                                           1951-----                                                    720, 000
58.    Machias River, Maine 2 4--                                                          1877            32, 000 -----.---.-.                       (*)
59.    Malden River, Mass. so.....-                                                        1922        s1 79, 866                      45, 097        (*)
60.    Manchester Harbor, Mass.----------......                                  .----.1949                                                            470, 000
61.    Marblehead Harbor, Mass..------...                             -------              1945   ...........                               584      ' 235, 000
62.    Matinicus Harbor, Maine---_____      4
                                                                  - _______......          1952             14, 000                     8, 413        (*)
63.    Mattapoisett Harbor, Mass. ......                                             .
                                                                                .-------   1950                                                       s 57, 000
64.    Medomak River, Maine_---------.....-----                                      . -1953                17, 000                    91, 593        (*)
65.    Menemsha Creek, Marthas Vineyard, Mass...                                           1953         5 56, 926 .............                       (*)


See footnotes at end of table.
 54                    REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


                                                                                        For last             Costs to June 30, 1954
                                                                                           full                                                          Estimated
                                                                                        report                                                             amount
                              _Name of project                                            see                                        Operation           required to
                                                                                        annual                 Con-                  and main-            complete
                                                                                        report              struction                 tenance


  66. Merrimack River, Mass. __... __                     ...
                                                        _...._.....__                         1940              115, 425                   147, 860         (*)
  6 7. M ian us R iv er , C o n n .. ...           . __. .__ _ .. ___ _ .___ __. . .          1952            36132, 435                         65         (*)
  68.                                    .....
       Moosabec Bar, Maine '............_______.                                              1930              114, 000                    12, 600         (*)
  69. Mystic River, Conn............._.............._                                         1953               11,526                     45, 320        37110, 500
  70. M ystic R iver, M ass.................                        ..... .......-            1953              770, 125                   208, 593        4, 500, 000
  71. N an tuck et (H arbor of R efuge), Mass.... ..........                                  1952              456,482                    277,300          38 240,000
  72. N arrag u ag u s R iver, M ain e 1 4_...... .. . . ____                . ....           1907                 49,644        .....- ...-                      (*)
  73. New Bedford and Fairhaven Harbor, Mass.. ---1953                                                     491, 686, 918              40 624, 230                 123, 000
  74. New Harbor, Maine -...-----------------.... 1937                                                           10,500                   12,566             (*)
  75. New Haven (Breakwaters), Conn.._                                    -                   1950            1,242,246                   40,254             (*)
  76. New Haven Harbor, Conn.....                              _                              1953         41 3,873, 620         42   1, 602,977                  509, 400
  77. N ewport H arbor, R. I........                       . ..
                                                       ____.___                  .________1953                  498, 828                  27, 500            (*)
  78. Owls Head Harbor, Maine 1 s_                              __        ___                 1855               17,897                        .---
  79. Passamaquoddy Tidal Power                _      Project, Maine_.....                    1935           6, 384, 394     ----           -                (a)
  80. Pepperells Cove, Maine '__.......___- ____.....                                         1920              158, 262                        138          (*)
  81. Pleasant River, Maine 4.......-        2                                                1892                3,500                     _        -       (*)
  82. Point Judith (Harbor of Refuge) and Point Judith
        Pond, R. I...............----------------------------                                 1953         442, 488,430       45 879, 025                    (*)
  83. Portsmouth Harbor, N. H.                        _                                       1892              130,393                ..-                   (*)
  84. Potowomut River, R. I. 1s                          _                                   1882                 5,000                                      (*)
  85. Provincetown Harbor, Mass...__                             _                           1949               131,653             42,129               46 1, 565,     300
  86. Richmond Harbor, Maine                     2       ______________                      1883                20,000                                      (*)
  87. Richmond's Island Harbor, Maine '.---------                                            1882               119,844 --                                   (*)
  88. Rockland Harbor, Maine_________________                                                1950               915,863             78,453                   (*)
  89. Rockport Harbor, Maine 1__________                                                     1915                32,000 -             -                      (*)
  90. Rockport Harbor, Mass. 8                                                               1905                22,000                                      (*)
  91. Royal River, Maine 13 4                                    ..     _                    1884                21,919               8,081                  (*)
  92. Saco River, Maine_...........--__---__............                                     1947            47531, 716           132, 019                         30, 300
  93. St. Croix River, Maine                             __            _____                 1950            48179,550              10,450                   (*)
  94. Sakonnet Harbor, R. I.4 15______...........                                  .....     1940                62,203             10,296                   (*)
  95. Sakonnet River, R. I. 1 49                                                             1909                38,427                                      (*)

  96. Salem Harbor, Mass. 6 .                     .                                          1953                48, 088              9, 043                  165, 000
  97. Sandy Bay (Harbor of Refuge) Cape Ann, Mass.' 50 1922                                                  1, 925, 553           15,926                  9, 975, 000
  98. Sasanoa River, Maine 1 4 .                      _______                 ..             1915                35,000 .............                        (*)
  99. Sasco Hill Beach, Conn....___._______..____.                                           1950    -                   ..-..                  .-          5121, 000
100. Scarboro River, Maine, between Prouts Neck and
        Pine Point ............................--------------------------------              1950             ...                                          52195, 000
101. Scituate Harbor, Mass.....                       _            _                        1953                  796
                                                                                                                179,                        7,431           (*)
102. Sherwood Island State Park, Conn._                              ___                    1950              ......                                      53 158, 700
103. South Bristol Harbor, Maine...- ____.____                                              1914                3,500                     ..-.-.-          (*)
104. Southport Beach, Conn...............___                                                1950     --                                                    64 14, 000
105. Stockton Harbor, Maine 84_                                                             1915                 33,000                                    (*)
106. Stonington Harbor, Conn....- _________________          --                             1950                                                           32 85, 000
107. Sullivan Falls Harbor, Maine 1 4_--                                                     1914                 19,871                    (*)
108. Taunton River, Mass....-----                        __-....__________....               1948                271,390                86 55 913, 600
109. Tenants Harbor, Maine--------__                                                         1920                 18,750                    (*)
110. U nion R iver, M aine s. . . .                           ._______ ___ _____             1912                146,855        16,589      (*)
111. Vineyard Haven Harbor, Mass. 18                                                    .. 1943                   27,186 .............       (*)
112.  Wareham     Harbor,      Mass.        8....                                            1896                 55,997   ... ..........        47, 800
113. W arren River, R . I. 1 _... .. . .. .. . .. __ _____                                   1890                  5,000                     (*)
114. W ellfleet Harbor,      M    ass........._............                               ._____
                                                                                             1949                .. .      . ...           56228, 000
115. Wells Harbor, Maine 4---__-_ ---    2                      _____            _____       1874                                 5, 000    (*)
                                                                                                                                            5749, 000
116. Westcott    Cove,    Conn..             ___                                             1948
117. Westport Harbor and Saugatuck River, Conn.. -..                                         1948                 15,160        14,121           15, 800
118. Westport River, Mass. 4 6--------------------. .                                        1942                                           5880, 000
119. Weymouth Back River, Mass. .__.__                                  .__________ 1944                      59 68, 740 -----                              (.)
120. Weymouth Fore River, Mass.                       60_s                        .          1953                355,227                134, 906             680, 000
121. Wickford Harbor, R. I....._                                                             1953           61   117, 733              ..- ...-             (*)
122. Wilson Point (Harbor), Conn. 4a1,                                                       1895                 54,177                  - -- _--          (*)
123. Winthrop Beach, Mass. Beach Erosion Control...                                          1950    ---                                                  62340, 000
124. Winthrop Harbor, Mass. 1 4                                                              1895                  8,992         -                          (*)
125. Wood Island Harbor, Maine and the Pool at
        Biddeford.....----------------------------------                                     1950    -                                                    68 153,       000
126. Woods Hole Channel, Mass.............._________                                         1940                230,000                   11,661           (*)
127. York Harbor,      Maine___                  ______________.__                           1953                 13, 400                  20,301           (*)




   *Completed.
    1 Abandonment recommended in H. Doc. 467, 69th Cong., 1st sess.
    2 Reported by the District Engineer as unworthy of further improvement.
    1 Improvements adequate for commerce.
    4 No commerce reported.
    5 Excludes $100,000 expended from contributed funds.
    6 Awaiting local cooperation.
    7 Exclusive of $8,000 to be contributed by local interests.
    s Curtailment recommended June 24, 1946, in H. Doc. 467, 69th Cong., 1st sess.
    9 Revoked during fiscal year $708.
   10oCosts to local interests $16,000 exclusive of Federal participation.
                RIVERS AND HARBORS-NEW ENGLAND DIVISION                                                   55
   11Exclusive of $43,500 to be contributed by local interests.
   Is Exclusive of $6,600 contributed by local interests.
   1, Maintenance unnecessary or not urgent.
   14Exclusive of $30,000 to be contributed by local interests.
   is Costs to local interests $110,000 exclusive of Federal participation.
  14 Awaiting local cooperation. Under date of January 14, 1939, the Chief of Engineers recommended modi-
fication of the existing project to provide for construction of a lock, dam, and power plant at Enfield Rapids
(H. Doc. 165, 76th Cong., 1st sess.).
Is
  1i Estimated cost of project $12,816,000; expenditures limited by law to $1,000,000.
      Exclusive of $35,000 to be contributed by local interests.
  1r In addition $10,000 was expended from contributed funds.
  20 Exclusive of $35,000 to be contributed by local interests.
  31Curtailment recommended Dec. 15, 1914, in H. Doc. 1419, 63d Cong., 3d sess.
   n Excludes $100,000 expended from contributed funds.
  2 Revoked during fiscal year $124.
  24 Exclusive of $25,500 to be contributed by local interests.
  25Revoked during fiscal year $10,190.
  26 Exclusive of $62,500 to be contributed by local interests.
  2~Costs to local interests $29,300, exclusive of Federal participation.
  28Exclusive of $35,000 expended by local interests for work on the project.
  79Elimination of maintenance dredging recommended in H. Doc. 467, 69th Cong., 1st sess.
  s Under State maintenance.
  31Exclusive of $62,000 expended from contributed funds.
  n2Exclusive of $5,500 to be contributed by local interests.
  " Exclusive of $60,000 to be contributed by local interests.
35
  24 Exclusive of $33,000 to be contributed by local interests.


37
      In addition $12,500 was expended from contributed funds for construction.
   s6Exclusive of $46,500 contributed by local interests.
      Exclusive of $14,000 to be contributed by local interests.
  a8Exclusive of $31,500 to be contributed by local interests.
  39In addition the sum of $20,400 was expended for construction from contributed funds.
  '4 Revoked during fiscal year $1,476.
  41 Includes $290,877 National Industrial Recovery funds and $59,207 Public Works funds.
  '9 Revoked during fiscal year $747.
  4 Work discontinued 1937. Facilities transferred to the War Assets Administration.
  " In addition the sum of $17,587 was expended for construction from contributed funds.
  4s Revoked during fiscal year $321.
  46 Exclusive of $760,000 to be contributed by local interests.
  ' Exclusive of $20,000 expended from contributed funds.
  48 Exclusive of $19,892 expended from contributed funds.
   49 Commerce included under Tiverton Harbor, R. I.
30   Abandonment recommended in H. Doc. 411, 64th Cong., 1st sess., and in Rivers and Harbors Committee
  Doc. 3, 65th Cong., 1st sess.
  51 Costs to local interests $42,000 exclusive of Federal participation.
   ~aExclusive of $10,000 to be contributed by local interests.
  53 Costs to local interests $316,000 exclusive of Federal participation.
  5' Costs to local interests $28,000 exclusive of Federal participation.
    s5Exclusive of $102,000 to be contributed by local interests.
  " Exclusive of $32,000 to be contributed by local interests.
67   Exclusive of $21,000 to be contributed by local interests.
  5sExclusive of $80,000 to be contributed by local interests.
  SExclusive of $20,000 expended from contributed funds.
  4*Modification recommended in H. Doc. 555, Eighty-second Congress, 2d sess.
  61Exclusive of $25,000 contributed by local interests.
  a Costs to local interests $680,000 exclusive of Federal participation.
  * Exclusive of $12,000 to be contributed by local interests.
  " Excludes $5,000 expended of contributed funds.
  65Excludes $200,000 to be contributed by local interests.
56       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

        33. MERRIMACK    RIVER BASIN, N. H. AND MASS.
   The works covered by the comprehensive plan are located on the
Merrimack River and its tributaries in New Hampshire and Massa-
chusetts.
   The Flood Control Act approved June 22, 1936, authorized the
construction of a system of flood control reservoirs in the Merri-
mack River Basin for the reduction of flood heights in the Merri-
mack Valley. The Flood Control Act approved June 28, 1938,
approved the general comprehensive plan for flood control and
other purposes as approved by the Chief of Engineers pursuant to
preliminary examinations and surveys authorized by the Act of
June 22, 1936, and modified the project to provide, in addition to
the construction of a system of flood control reservoirs, related
flood control works which may be found justified by the Chief of
Engineers.
   The following reservoirs and related flood control works were
proposed for construction under the comprehensive plan:
                                                                                              Reservoirs
                                              i~--                                                         ......

                                                                                              Distance                                                                                             Estimated cost
                                                                                               above                                                               Reservoir
                   Name                                    Nearest city                       mouth of Height                           Type                       capacity
                                                                                              Merrimack                                                                              Con-            Land and
                                                                                               River                                                                              struction          damages 1        Total
                                                                                                              -I*                                      -   II II                                               -!I
                                                                                                 Miles              Feet                           Acre-feet
Franklin Falls'...._
                   s                           Franklin, N. H........                              118. 2             140 Earth fill.............    154, 000                     $6, 167, 500       $1, 754, 000    $7, 921, 500
Mountain Brook ' 2--                           Keene, N. H......                                   167. 8              50 .....do.................     5, 300                           695, 000          79, 000        774, 000    0
Edward MacDowell .... _________________        Keene, N. H.............                            161.3               67 --..do...............       12, 800                      1, 717, 000          300, 000      2, 017, 000
Bennington..............................       Manchester, N. H....                                147.0               73 ..-.do._... . ..      ..    90, 000                      7, 779, 000        4, 621, 000    12, 4')0, 000   00
Beards Brook
          2
              .................       .        Concord, N. H.....                                  136. 4             115 ..-..do- _.... .....        35, 000                      6, 835,000            395, 000     7, 230, 000
Blackwater '........                     ..    Concord, N. H-.... .-..                             118. 8              75 ....do------ ---.....       46, 000                         763, 500           556, 500     1, 320, 000
                                                                                                                                                                                                                                     O

  1 Includes highway, railroad, and utility relocations.                                                                                                                                                                             O
  2 For details, see individual report.
  'A dam has been constructed at the site by private interests. Cost has not been revised on current price basis.
                                                                                                                                                                                                                                     t
                                                                                  Local protection projects

                                                                 Distance                                                                                                                Estimated cost
                                                                  above
                          Location                               mouth of                                   Type of structure
                                                                 Merrimack                                                                                              Con-                Land and                                 z
                                                                  River                                                                                               struction             damages 1                Total
                                                                                                                                                                                                                                     t
               2                                                    Miles
Nashua, N. H. ..................                                          65         Wall and levee.............-------------------..................-------------....      $270, 000                $3, 000           $273. 000     0
                                    -----------------------
North Andover and Lawrence, Mass.......
Lowell, Mass.......................................
                                                                          27. 3 -...
                                                                          39      .....
                                                                                        do......---------.
                                                                                       do......----------.................-------------            ....------------------.
                                                                                                                                                                           1,680,000
                                                                                                                                                                             490, 600
                                                                                                                                                                                                     43, 000
                                                                                                                                                                                                     90, 000
                                                                                                                                                                                                                      1, 723, 000
                                                                                                                                                                                                                         580, 600
                                                                                                                                                                                                                                     z
  ' To be borne by local interests.
  ' Completed. For last full report, see Annual Report for 1950.
  3 Completed. For last full report, see Annual Report for 1945.
                                                                                                                                                                                                                                     O
58       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  All operations pertaining to flood control in the Merrimack
River Basin are now carried on under and are reported under the
projects for the individual units of the comprehensive plan re-
ferred to above.
  No further expenditures are contemplated under the general
project for flood control in the Merrimack River Basin. For final
cost and financial summary, see Annual Report for 1946.
34. FRANKLIN FALLS RESERVOIR, MERRIMACK RIVER BASIN, N.H.
   Location. The dam is located on the Pemigewasset River in
New Hampshire, the main tributary of the Merrimack River, and
is about 21/2 miles upstream of Franklin, N. H. (See U. S. Geo-
logical Survey maps for Penacook and Holderness, N. H.)
   Existing project. The dam is of the rolled-earth type with a
dumped rock shell. It has a top length of 1,740 feet, a top width
of 25 feet, and a height of 140 feet above river bed. The spillway is
located on rock in the right abutment and is a low, concrete weir
with a crest length of 546 feet. The spillway approach and dis-
charge channels are in earth and rock cut and are 1,785 and 900
feet in length, respectively. The outlet works are on the right
bank of the river and consist of an intake channel 840 feet long,
and two 22-foot horseshoe-shaped conduits each 542 feet long and
each controlled by 4 broome gates operated through a control
tower from a gatehouse above. The outlet works also have a still-
ing basin and an outlet channel with a length of 2,350 feet. The
reservoir is operated for flood control purposes and has a storage
capacity of 154,000 acre-feet which is equivalent to 2.9 inches of
runoff from its drainage area of 1,000 square miles.
   The cost of the completed project was $6,167,500 for construc-
tion and $1,754,000 for lands and damages, a total of $7,921,500.
The latest (1952) approved estimate for annual cost of operation
and maintenance is $27,000.
   The project is a unit of the comprehensive plan for flood control
and other purposes in the Merrimack River Basin which was au-
thorized by the Flood Control Act approved June 22, 1936, and
modified by the Flood Control Act approved June 28, 1938.
   Local cooperation. Section 2 of the Flood Control Act ap-
proved June 28, 1938, applies.
    Operationsand results during fiscal year. New work: None.
   Maintenance: Operations consisted of periodic checking of gates
and operating equipment and general maintenance of roads, build-
ings, and grounds, including a bituminous seal coat for the access
road and the road across the dam. A six-inch cast iron water line
for fire-fighting and general use was laid from the operating build-
ings and connected to the city of Franklin water main along the
state highway at the entrance to the dam. Costs from regular
funds were $30,569.
    Reservoir operation: There were two periods of regulation at
Franklin Falls Reservoir during the fiscal year. In April, 19,000
acre-feet of storage, 12 percent of the total capacity, were utilized.
The computed peak inflow was 20,000 c.f.s. and the maximum
regulated outflow was 16,000 c.f.s.
  In May, 27,200 acre-feet of storage, 18 percent of the total capa-
                  FLOOD CONTROL--NEW ENGLAND DIVISION                                                            59
city, were utilized. The computed peak inflow was 23,000 c.f.s.
and the maximum regulated outflow was 16,500 c.f.s.
   Total costs during the fiscal year from regular funds were
$30,569.
   Condition at end of fiscal year. Construction of the dam and
appurtenant works was initiated in November 1939 and completed
in October 1943. Total costs for the project have been $8,154,458,
of which $7,921,531 was for new work and $232,927 for mainte-
nance.
                                 Cost and financial summary

                                        Fiscal year ending June 30                                   Total to June
                                                                                                    30, 1954, includ-
                                                                                                    ing fiscal years
                          1950         1951               1952             1953         1954         priorto 1950

New work:
   Appropriated........   $60, 000   -$30,000     ------------.........   -$11, 448       -$270          $7, 921, 531
               .
   Cost_----. ---.-. .     90, 897       3, 756               -$99                   ............
                                                                               7, 025------------         7,921, 531
Maintenance:
   Appropriated........    27, 000      12, 000             23,950          29,300       28,300              233, 050
   Cost---.-...-.....-.    22, 054      20, 279             22, 798         27,677       30, 569             232,927



35. EDWARD MacDOWELL RESERVOIR (FORMERLY WEST PETER-
   BOROUGH RESERVOIR), MERRIMACK RIVER BASIN, N. H.
   Location. The dam is located on Nubanusit Brook, a tributary
of the Contoocook River, and is one-half mile upstream from the
village of West Peterborough, N. H., and 14 miles east of Keene,
N. H. (See U. S. Geological Survey maps for Peterboro and
Monadnock, N. H.)
   Existing project. The dam is of the rolled-earth type with a
dumped rock blanket on the upstream face and a downstream rock
toe. It has a top length of 1,030 feet, a top width of 25 feet, and a
maximum height of 67 feet. The outlet works located in the west
abutment of the dam consist of an intake structure, a 7-foot square
conduit which is 275 feet in length and is controlled by three 3-foot
by 7-foot slide gates mechanically operated through a control tower
from a gate house above, and a stilling basin emptying into the
pool of the Verney Mills Dam. The spillway is a low, concrete
weir, 100 feet in length, with a 1,900-foot long approach channel,
a 3,080-foot long discharge channel, and a 2,540-foot long protec-
tive dike to guide the spillway discharge. The spillway is located
in a natural saddle on the north side of the reservoir approxi-
mately 3 miles from the dam site and discharges into Ferguson
Brook which, in turn, discharges into the proposed Bennington
Reservoir. The reservoir is operated for flood control purposes
and has a storage capacity of 12,800 acre-feet which is equivalent
to 5.5 inches of runoff from its drainage area of 44 square miles.
   The estimate of cost for new work (1954) is $1,717,000 for con-
struction and $300,000 for lands and damages, a total of $2,017,-
000. The latest (1952) approved estimate for annual cost of op-
eration and maintenance is $19,800.
   The project is a unit of the comprehensive plan for flood control
and other purposes in the Merrimack River Basin which was
60            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

authorized by the Flood Control Act approved June 22, 1936,
and modified by the Flood Control Act approved June 28, 1938.
The name "Edward MacDowell Dam" was adopted by section 206
of the Flood Control Act approved May 17, 1950.
   Local cooperation. Section 2 of the Flood Control Act ap-
proved June 28, 1938, applies.
   Operations and results during fiscal year. New work: None.
Payment was made on one claim in connection with construction
contract for the dam. Costs from regular funds were $47,584.
   Maintenance: Operations consisted of periodic checking of
gates and operating equipment and general maintenance of roads,
buildings, and grounds, including a bituminous seal coat for the
access road and the road across the dam. An underground water
storage tank for fire-fighting purposes was installed near the
operating buildings. Costs from regular funds were $19,718.
   Reservoir operation: The reservoir was regulated in April to
reduce flows on Nubanusit Brook. The maximum storage util-
ized was 1,900 acre-feet, 15 percent of the total capacity. The
computed peak inflow was 720 c.f.s. The outlet gates were
closed during the flood period. The maximum regulated outflow
to empty the reservoir was 550 c.f.s.
   Total costs during the fiscal year from regular funds were
$67,302.
   Condition at end of fiscal year. Construction of the dam and
appurtenant works was initiated in March 1948 and completed in
March 1950. Work remaining to be done consists of disposition
of condemnation cases in connection with land acquisition and
disposition of claim in connection with constructon. Total costs
for the project have been $2,079,293, of which $1,999,763 was
for new work and $79,440 was for maintenance.
                                     Cost and financial summary

                                            Fiscal year ending June 30                         Total to June
                                                                                              30, 1964, includ-
                                                                                               ing fiscal years
                              1960         1951         1952         1953          1954        prior to 1950

New work:
                       $371, 800 --.....---
   Appropriated......-------..                            .-       -- $27, 500   -$25, 479         $2, 016, 021
   Cost----------- -      785,358          $12, 152      $6, 589           377      47, 584         1, 999, 763
                           1, 000
   Maintenance ........--------              12, 300     16, 250       18, 600      17, 500             79, 660
   Cost.................    7, 582           19, 466     16, 127       16, 647      19, 718             79, 440


     Other new work data:
     Unobligated balance,fiscal year ending June 30, 1954                   .................        $3,957
     Unobligated balances available for succeeding fiscal year ending June 30,
       1955..........    ..................................................
                      .......                                                                    .... 3, 958
     Estimated additional amount needed to be appropriated for completion
     of existing project ---------.......................       .....................        ...... .. 979


36. BLACKWATER                RESERVOIR, MERRIMACK                         RIVER BASIN, N. H.
   Location. The dam is located on the Blackwater River in
New Hampshire, 8.2 miles above the confluence with the Con-
toocook River and 118.8 miles above the mouth of the Merrimack
River. It is in the town of Webster, just above the village of
            FLOOD CONTROL-NEW ENGLAND DIVISION                 61
Swetts Mills, 12.5 miles by highway northwest of Concord, N. H.
 (See U. S. Geological Survey maps for Penacook and Mount
Kearsarge, N. H.)
   Existing project. The dam is of the rolled-earth type with a
dumped rock blanket on the upstream face and a downstream
rock toe. It has a top length, including spillway, of 1,150 feet,
a top width of 39 feet and a maximum height, above river bed,
of 75 feet. There are also five earth dikes on the west side of
the reservoir having a respective length of 335, 170, 735, 175 and
240 feet and a respective maximum height of 29, 16, 40, 9, and 18
feet. The spillway is of the concrete, gravity type with a length
of 240 feet and has a 160-foot long approach channel and a 400-
foot long discharge channel. The outlet works are in the spill-
way and consist of three conduits, each controlled by a 3-foot
6-inch by 5-foot 3-inch slide gate hydraulically operated from a
gallery within the spillway. The dam and appurtenant works
contain a 16-foot diameter penstock intake and have been con-
structed to provide for future raising and the inclusion of power
at the site. The reservoir is operated for flood control purposes
and has a storage capacity of 46,000 acre-feet which is equiva-
lent to 6.7 inches of runoff from its drainage area of 128 square
miles.
   The estimate of cost for new work (1954) is $763,500 for
construction and $556,500 for lands and damages, a total of
$1,320,000. The latest (1952) approved estimate for annual cost
of operation and maintenance is $7,000.
   The project is a unit of the comprehensive plan for flood con-
trol and other purposes in the Merrimack River Basin which
was authorized by the Flood Control Act approved June 22, 1936,
and modified by the Flood Control Act approved June 28, 1938.
   Local cooperation. Section 2 of the Flood Control Act ap-
proved June 28, 1938, applies.
   Operations and results during fiscal year. New work: None.
   Maintenance:    Operations consisted of periodic checking of
gates and operating equipment and general maintenance of roads,
buildings, and grounds, including a bituminous seal coat for the
access road. Costs from regular funds were $6,099.
   Reservoir operation:     There was one period of regulation
during the year to reduce flood flows on the Blackwater River.
   In May, the maximum storage utilized was 9,800 acre-feet, 21
percent of the total capacity. The computed peak inflow was
2,100 c.f.s. Gates were closed during the flood period. The
maximum regulated outflow to empty the reservoir was 2,000
c.f.s.
   Total costs during the fiscal year from regular funds were
$6,099.
   Condition at end of fiscal year. Construction of the dam and
appurtenant works was initiated in May 1940 and completed in
November 1944. Work remaining to be done consists of consum-
mation of agreement for utility relocation. Total costs for the
project have been $1,370,458, of which $1,316,864 was for new
work and $53,594 for maintenance.
62                    REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954
                                                  Cost and financial summary

                                                         Fiscal year ending June 30                    Total to June
                                                                                                      30,1954, includ-
                                                                                                      ing fiscal years
                                           1950        1951         1952        1953       1954        priorto 1950

New work:
   Appropriated--------........            $96, 200              ........--...--- $3,916
                                                      -- $33, 000--------                   -$135      $1, 320, 000
   Cost----------------.................    11,910         1,420              ------------............ 1,316,864
                                                                        $911 ............
Maintenance:
   Appropriated..--------                    6,000       5,000        5,800       6,000      4, 500             53,800
   Cost----------------                      5, 472      5, 400       5,500       4, 452     6, 099             53, 594


Other new work data:
                                                                                  $136
    Unobligated balance, fiscal year ending June 30, 1954...............................
    Unobligated balances available for succeeding fiscal year ending June 30, 1955 136

                  37. BLACKSTONE RIVER BASIN, MASS., AND R. I.
     Location.                   The works covered by this project consist of a dam
and reservoir on the West River and local protection works at
three cities on the Blackstone River.
     Existing project.                            The Flood Control Act approved December
22, 1944, authorized the plan for a reservoir on the West River and
local protection works at Worcester, Mass., and Woonsocket and
Pawtucket, R. I., substantially in accordance with House Docu-
ment No. 624, 78th Congress, 2d session.
  The following individual projects comprise the authorized plan.
                                                                                                   Reservoirs

                                                                                                    Distance                                                                   Estimated cost
                                                                                                     above                                         Reservoir
                     Name                                        Nearest city                       mouth of Height              Type              capacity
                                                                                                   Blackstone                                                        Con-           Land and
                                                                                                     River                                                         struction        damages 1             Total
                                                                                               I             1    -     1                     1I               1                1                1


                                                                                                     Miles       Feet                              Acre-feet
West Hil----...........---------------------....   Worcester ,Mass..........----------------                                                                                                                      r25.8
                                                                                                                                                                                                                  fll900
                                                                                                                                                                                                                  $1,
                                                                                                                                                                                                                  977,
                                                                                                                                                                                                                  Earth
                                                                                                                                                                                                                   $2,
                                                                                                                                                                                                                   000
                                                                                                                                                                                                                   730,
                                                                                                                                                                                                                   000
                                                                                                                                                                                                                   $753,
                                                                                                                                                                                                                  43
                                                                                                                             - 1 -      4           1, 90
                                                                                                                                            Eathfil----------  125.1,97,00            75,   00       2,    3000
                                                                                                                                                                                                                  Q
  1   Includes highway, railroad, and utility relocations.                                                                                                                                                        O
                                                                                                                                                                                                                  0tJ
                                                                                     Local protection projects

                                                                    Distance                                                                                         Estimated cost
                                                                                                                                                                                                                  z
                                                                                                                                                                                                                  O




                                                                     above                                                                                                                                        O
                            Location                                mouth of                             Type of structure
                                                                   Blackstone                                                                         Con-              Land and
                                                                     River                                                                          struction            damages 1                   Total
                                                                                                                                                                                                                  z
                                                                      Miles
Worcester, Mass....---------------------------------       ----               48   Diversion tunnel and channel--...........----------------------.. $4,190, 000   $544, 000   $4, 734, 000
Woonsocket, R. I....-------------------        -----------------              15                                                                      1, 880, 000
                                                                                   Channel improvement ..--..............------------------------..........         160, 000    2,040, 000
                                                                                                                                                                                                                  t
Pawtucket, R. I....------------------------------------                        2                                                                                                   202,000
                                                                                   Flood wall-----..............------------------------------------202, 000 ..------------.............
                                                                                                                                                                                                                  z
  1 To be borne by local interests.                                                                                                                                                                               tJ

                                                                                                                                                                                                                  All


                                                                                                                                                                                                                  tr

                                                                                                                                                                                                                  O
                                                                                                                                                                                                                  z



                                                                                                                                                                                                                  QA3
64         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

       38. THAMES RIVER BASIN, CONN., R. I., AND MASS.
   Location. The works covered by this project are a series of
dams and reservoirs on tributaries of the Thames River in Massa-
chusetts and Connecticut, within a radius of 45 miles from Nor-
wich, Conn., and a channel enlargement on the Shetucket River
where it discharges into the Thames River at Norwich.
   Existing project. The Flood Control Act approved August 18,
1941, approved the plan for a system of reservoirs and channel
improvements in the Thames River Basin in accordance with
House Document No. 885, 76th Congress, 3d session, and author-
ized $6 million for initiation and partial accomplishment of the
project. The Flood Control Act approved December 22, 1944,
authorized the completion of the approved plan.
   The following individual projects comprise the approved plan:




     si 5--68.94
                                                                                                Reservoirs

                                                                                                Distance                                                                        Estimated cost
                                                                                                  above                                                Reservoir
                    Name                                       Nearest city                     mouth of       Height             Type                 capacity
                                                                                                Thames                                                                   Con-        Land and1
                                                                                                 River                                                                struction      damages          Total
                                                                                                   Miles        Feet                                     Acre-feet
Hodges Village.--------------------.....
Buffumville ...----------------------
                                         Webster, Mass..           -----------------------
                                         Webster, Mass.-_--------------------74.7
                                                                                                       74.5        55 Earth fill..........--------------    13, 000   $1, 431,000    $1, 609, 000   $3, 040, 000
                                                                                                                                                                                                                   0
                                                                                                                  66 -.     do-----------------12,700                  2,004,500         635, 500    2,640,000
East Brimfield.-------------             Southbridge, Mass.--------------------                       82.8         55 --.. do-----------------              30,000     1,747, 000     3,573,000      5,320,000     0
Westville....------------------------Southbridge, Mass.--------------.----                             77.2        36 Concrete-gravity                      12, 000    2, 545, 000    3, 345, 000    5, 890, 000
Mansfield Hollows'......-......-.-.-..   Willimantic, Conn.--------------------                        40.0        70 Earth fill....--------------          51, 000    4, 498, 500    2, 111, 500    6, 610, 000
Andover-------------------------Manchester,           Conn.....--------------------                    47. 0       80 ..... do.....-----------------        16, 800    3, 777, 000    1, 123, 000    4, 900, 000
South Coventry.                          Willimantic, Conn....................--------------------    41.6         94 ..... do..........                    36, 900    4, 434, 000    5,666,000     10,100, 000

  ' Includes highway, railroad, and utility relocations.
  2 For details, see individual report.

                                                                                      Local protection projects

                                                                    Distance                                                                                                Estimated cost
                                                                      above
                           Location                                 mouth of                             Type of structure
                                                                    Thames                                                                                      Con-            Land and
                                                                    ,ieRiver                                                                                 struction          damages 1           Total
                                                                                                                                                                                                     oa

                                                                      Miles
Norwich, Conn .......-------------------------------
                  -                                                    15         Channel improvement....................                                      $1,240,000             $72,000       $1,312,000

  1 To be borne by local interests.
  All operations previously reported are now contained in individual reports and
previous costs and expenditures have also been transferred to those projects.                                                                                                                                      z0
                                                                                                                                                                                                                    -
                                                                                                                                                                                                                   '-I




                                                                                                                                                                                                                   0n
66       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

              39. MANSFIELD HOLLOW RESERVOIR,
                  THAMES RIVER BASIN, CONN.
   Location. The dam is located at Mansfield Hollow, Conn., on
the Natchaug River, 5.3 miles above its confluence with the Wil-
limantic River. It is 4 miles northeast of the city of Willimantic,
Conn. (See U. S. Geological Survey maps for Spring Hill and
Willimantic, Conn.)
   Existing project. The dam is of the rolled-earth type with a
dumped rock blanket on the upstream face. It has a top length,
including spillway, of 12,422 feet, a top width of 15 feet, and a
maximum height of 70 feet. There are also five earth dikes north
of the dam and one earth dike south of the dam having a respec-
tive length of 190, 830, 464, 257, 766, and 104 feet and a respective
maximum height of 12, 55, 15, 11, 8, and 12 feet. The spillway is
located in the river channel and is of the concrete, gravity type
with a crest length of 690 feet. The outlet works are in the spill-
way and consist of five conduits, each controlled by a 5-foot 6-inch
by 7-foot slide gate hydraulically operated from a gallery within
the spillway. The reservoir is operated for flood control purposes
and has a storage capacity of 51,000 acre-feet which is equivalent
to 6.0 inches of runoff from its drainage area of 159 square miles.
   The estimate of cost for new work (1954) is $4,498,500 for con-
struction and $2,111,500 for lands and damages, a total of $6,610,-
000. The latest (1952) approved estimate for annual cost of op-
eration and maintenance is $25,000.
   The project is a unit of the comprehensive plan for flood control
and other purposes in the Thames River Basin which was author-
ized by the Flood Control Act approved August 18, 1941. (H.
Doc. 885, 76th Cong., 3d sess.)
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. New work: Opera-
tions consisted of land acquisition, relocation of utilities, payment
of contract claim, and miscellaneous work. Costs from regular
funds were $125,122.
   Maintenance:     Operations consisted of periodic checking of
gates and operating equipment and general maintenance of roads,
buildings, and grounds. "Costs from regular funds were $18,348.
   Reservoir operation: There was no significant regulation for
flood control required at Mansfield Hollow during the year.
   Condition at end of fiscal year. Construction of the dam, initi-
ated in July 1949, was completed in May 1952. Work to be done
consists of completion of relocation of utilities and state roads,
dispositon of land acquisition cases in condemnation, and seepage
investigations. Total costs have been $6,278,338, of which $6,238,-
349 was for new work and $39,989 for maintenance.
                              FLOOD CONTROL-NEW ENGLAND DIVISION                                                                    67

                                                       Cost andfinancial summary

                                                                      Fiscal year ending June 30                         Total to June
                                                                                                                        30, 1954, includ-
                                                                                                                        ing fiscal years
                                               1950               1951           1952           1953         1954        prior to 1950
New     work:


      Appropriated--------........--....-------               2, 500, 000     $3, 000, 000   -$385, 000    -$15, 000         $6, 610,000
      Cost--------------.....$1, 365,909                      2, 252, 139      1, 132, 651      992, 384     125, 122         6, 238, 349
Maintenance:
      Appropriated---          ------------------------------------                          23, 000          18, 000             41, 000
      Cost. -----------------------------------                                  ----------- 21,641           18, 348             39,989


Other new work data:
                                                                                      $248, 139
    Unobligated balance, fiscal year ending June 30, 1954 ................---.........----------
        Unobligated balances available for succeeding fiscal year ending June 30, 1955
                 ...                      ..              ----------------------------------------------- 248, 139

40. CONNECTICUT RIVER BASIN, VT., N. H., MASS., AND CONN.

   Location. The works covered by this project are a series of
dams and reservoirs on tributaries of the Connecticut River in
Vermont, New Hampshire, and Massachusetts, within a radius
of 230 miles from Hartford, Conn., and local protection works at
several cities in the basin.
   Existing project. The Flood Control Act, approved June 22,
1936, as amended by the act approved May 25, 1937 (Public Law
111, 75th Cong.), authorized the construction of 10 reservoirs on
tributaries of the Connecticut River in accordance with plans in
House Document No. 412, 74th Congress, 2d session, as the same
may be revised upon further investigation of the 1936 flood.
   The Flood Control Act, approved June 28, 1938, approved a gen-
eral comprehensive plan for the control of floods and other pur-
poses in the Connecticut River Valley, as set forth in House Docu-
ment No. 455, 75th Congress, 2d session, and authorized the sum
of $11,524,000 for construction of local flood-protection projects
in the plan. The act of October 15, 1940, modified the act of June
28, 1938, to provide additional protection at East Hartford, Conn.,
as set forth in House Document No. 653, 76th Congress, 3d session.
The act of August 18, 1941, modified the comprehensive plan ap-
proved in 1938 to include the improvements recommended in
House Document No. 653, 76th Congress, 3d session, and House
Document No. 724, 76th Congress, 3d session, with such further
modifications as may be found justifiable in the discretion of the
Secretary of the Army and the Chief of Engineers. The latter act
also authorized to be appropriated the additional sums of $6 mil-
lion for local protection works and $10 million for reservoirs. The
act of October 26, 1942 (Public Law 759, 77th Cong., 2d sess.),
further modified the plan by including the construction of Gully
Brook conduit at Hartford, Conn.
   The Flood Control Act, approved December 22, 1944, authorized
the expenditure of $30 million in addition to the previous authori-
zation for the comprehensive plan approved in 1938 and modified
the plan by (1) directing specific consideration of an alternative
plan of the Vermont State Water Conservation Board instead of
the Williamsville Reservoir in the West River Basin, Vt., (2)
directing consultation with the affected States during the course of
68       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

investigations and transmission of the proposal and plans to each
affected State for written views and recommendation for reservoir
projects heretofore authorized for construction at Cambridgeport,
Ludlow, South Tunbridge, and Gaysville, and resubmission of the
projects or modifications thereof to the Congress, and (3) re-
scinded the authorization for construction at the Sugar Hill site.
   The Flood Control Act of 1950 (Public, No. 576, 81st Cong., 2d
sess.), modified the project for flood control at Hartford, Conn.,
authorized by the Flood Control Act approved June 28, 1938, as
amended, to include Folly Brook dike and conduit.
   Following are lists of the reservoirs and local protection works
which were proposed for construction in the modified comprehen-
sive plan:
                                                                                                             Dams and reservoirs

                                                                                                                        Distance                                                                                         Estimated cost
                                                                                                                          above                                                            Reservoir
                        Name                                                   Nearest city                             mouth of         Height                     Type                    capacity
                                                                                                                        Connecti-                                                                              Con-        Land and
                                                                                                                        cut River                                                                           struction      damages '        Total

Vermont:              -- - -- - - -- - - -- - - - - - - - - - -
                                                                                                                          Miles           Feet                                              Acre-feet
   Victory2----....... - - - - - - - - - - - - - - - - - - St. Johnsbury--......--------------------                        306.0           85 Earth fill--....--...---.......                106, 400      $3, 701, 000     $899, 000    $4, 600, 000
   Union Village                                                White River Junction....------------------                  228. 4         170 ..... do         ---.................           38, 000       3, 111, 000       895, 000    4, 006, 000   r
   Gaysville--                          ------------- Rutland--... -------------------
                                   .................                                                                        246. 8         192 Concrete-------------.............             124, 150      11, 558, 000    5, 342, 000   16, 900, 000   0
     South Turnbridge-- ..---------                         Barre          ----.............. ------ -------                  234. 5        105     Earth fill-------..............               32, 600    3,138, 000     2,302, 000     5, 440, 000
   North Hartland ..--...--------------........                White River Junction....------------------                       211. 7      176   ..... do--------.........---........            71, 100    8, 550, 000    1, 100, 000    9,650, 000    0
   Ludlow--...............------......---------------....      Rutland--..................--------------------------            211.8       118   ..... do.................                       23, 900    2, 532, 000    3,158, 000     5, 690,000    0
   North Springfield ---------------                           Springfield-------------------                                   191.3       106   ..... do        ---------.......                50, 600    7,876, 000     1, 384, 000    9, 260, 000
   Brockway......................---------------------Bellows Falls.-------------------------                                   182.        122   .....- do.................                      37, 700    4, 801, 000    5, 899, 000   10, 700,000
   Cambridgeport-----------------Bellows                                  Falls-------------------------                        180. 3      101   ..... do........-........                       21, 600    4, 078, 000    1, 092, 000    5,170, 000
                        2      - - - - - - - - - - - - - - - - Rutland ----.........---.....-------......-----..--------.......
   The Island-....--------------------                                                                                          189. 6      100   ..... do......-----------------.......          19, 400    2,411, 000        899, 000    3, 310, 000   0
   Ball Mountain .................                         .. Brattleboro.........--------------------------178.                     2      247     Concrete arch.........                        54, 600   14, 946, 000       354, 000   15, 300, 000   0
   Townshend............--------------------Brattleboro -...........----....---------..-----------......                        168. 3      130     Earth fill--....---..--........               33, 000    9,021, 000     1,179, 000    10, 200, 000
New Hampshire:
   Sugar Hill -------------------                              Woodsvllle----...               -------------------              280. 9      163   .....    do...--------------                    91, 600   3, 500, 000    3, 385, 000     6, 885, 000
   West Canaan_- ------------------ Franklin....-------------233.                                                                    8       80   .....    do        -------.................     51, 000   3, 471, 000    5, 589, 000     9,060,000     -
   Claremont---                                                Claremont                   --------                  -----      202. 4      128   .....    do..--------------                     78, 300   8, 162, 000    4, 838, 000    13, 000, 000
   Surry Mountain-.................... Keene......--...------------------------                                                 174. 4       86   .....    do--...--   ------                     32, 500   1, 407, 200       324,100      1, 731, 300
   Honey Hill..---.----------------- Keene- ---------------------------                                                         168. 9       65   .....-   do...--------------                    26, 200   2,662, 000     1, 398, 000     4,060,000
Massachusetts:
   Birch Hil--------------------.......................... Gardner----------------------------                                  153. 3        56 .....     do---...----------                     49,900     1, 086, 000   3,151, 000     4,237, 000
     Tully       ---------------------- __---               Athol..---------------------------                                148.7           62-do--           -     -----------               -22,000      1,180,000        383,000     1,563,000
     Barre Falls----------------------                 Worcester----------------------- ---                                   130.2          62 Rock fill earth--------                           24,300    2,470, 000         30,000     2,500,000
     West Brookfield-------------..................... Worcester---------------------------                                   100. 5         30 Earth fill--------------                          33000     3,422, 000     5, 568, 000    8, 990, 000
     Knightville-     ....--- .-------------- Northampton ......------------------------                                      102.8         160 ..... do-----------------49,                         000    2, 395, 000       812, 000    3,207, 000


    'Includes highway, railroad, and utility relocations.                                                                                                                                                                                                oz
                                                                                                                                                                                                                                                         r
   'For details, see individual reports.
   'Alternate site to be selected. Cost has not been revised on current price basis.
                                                                                                Local protection"projects
                                                                                                                                                                                                                               C)
                                                                           Distance                                                                                                   Estimated cost
                                                                             above
                              Location                                     mouth of                                     Type of structure
                                                                           Connecti-                                                                               Con-                    Land and
                                                                           cut River                                                                            struction                  damages 2             Total
                                                                                    -~ mn         ~                     -                                       stuto                             n                            Fr


                                                                                 Miles
Northampton, Mass...                              --- -------....................... 94      Wall and levee----.. ....            ... .... .... ... .... ....            $960, 000              $150, 000       $1,110, 000    O
Holyoke, Mass....----------------...........................                           85   ..... do..---................................                               3, 418, 000              150, 000        3, 568, 000   d
Springdale, Mass.----.........................                   --                    84   ..... do--...........-......................                                  700, 000                57, 000           757, 000   -
CRivopee, Mass.l...                    --------..... --......................          80   ..... do---------------.....---------------do.                              1, 738, 000              250, 000        1, 988, 000
                                                                                       80   .....do        ----
                                                                                                      ---------   ---       ---.....--------------                      1, 138, 000               50, 000        1, 188, 000
West Springfield, Mass.--..------------.------ ----                                    76   .....
                                                                                                do-------------------...............                                    1, 579, 000               30, 000        1,609, 000
Springfield, Mass.----....--.---------.--------------                                  76                                                                                  932, 000              272, 000        1, 204, 000   C
Hartford, Conn....                 ------------------------------                      52      h--nedolimprve-----e- ------------                                       6, 760, 000              900, 000        7,660, 000
E as t H ar tfo r d , C onn .. . .  - ..--
                                      -- ---                           . . . . .
                                                     - - - - - -- - - --..             52          . .. .. .. ..-----------... .....--..... ..........
                                                                                            ---_-'do--                                                                  2, 135, 500              270, 000        2,405, 500    -
Winsted, Conn.'-.......--...-------------                                            115     Channel improvement......--..-......                                          172, 000               30, 000          202, 000
                                                                                                                                                                                      I                     I
  SDetails of these projects are given in individual reports.                                                                                                                                                                  O
  2 To be borne by local interests.

   All operations, costs and expenditures are contained in the individual reports.                                                                                                                                             z



                                                                                                                                                                                                                               00
                    FLOOD CONTROL--NEW ENGLAND DIVISION                                                71
   41. VICTORY           RESERVOIR,              CONNECTICUT                RIVER   BASIN,         VT.

   Location. The site of the proposed dam is on the Moose River,
17.4 miles above its junction with the Passumpsic. It is 1 mile
northeast of the village of Victory, Vt., and 11 miles northeast
of St. Johnsbury, Vt. (See U.S. Geological Survey map for
Burke, Vt.)
   Existing project. This project provides for the construction
of a rolled-earth dam having a top length of 1,000 feet and rising
85 feet above river bed. The spillway, at the right end of the
dam, will be a concrete weir, 50 feet in length. The outlet works
will consist of a 9-foot diameter conduit in the right abutment.
Control of the conduit will be accomplished by gates mechani-
cally operated through a control tower from a gatehouse above.
The reservoir will be operated for flood control and for conser-
vation for downstream regulation. It will have a total storage
capacity of 106,400 acre-feet which is equivalent to 26.6 inches
or runoff from its drainage area of 75 square miles.
   The estimate of cost for new work (1954) is $3,701,000 for con-
struction and $899,000 for lands and damages, a total of $4,-
600,000.
   The project is a unit of the comprehensive plan for flood con-
trol and other purposes in the Connecticut River Basin which
was authorized by the Flood Control Acts approved June 22,
1936, as amended, and June 28, 1938. (H. Doc. 455, 75th Cong.,
2d sess.)
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. Advance engineer-
ing and design was continued. Costs from regular funds for new
work were $15,591.
   Condition at end of fiscal year. No construction work has been
done on the project. Advance engineering and design was 46
percent complete. Total costs from regular funds have been
$103,446 for new work.
                                     Cost and financial summary

                                           Fiscal year ending June 30                       Total to June
                                                                                           30, 1954, includ-
                                                                                           ing fiscal years
                              1950        1951          1952         1953       1954        prior to 1950
New   work:
    Appropriated ------------------      $146, 000   -- $122, 759    $69, 705   $10, 500          $103, 446
    Cost-----------------
                   _      ____________          20         23, 221    64, 614    15, 591           103, 446



Other new work data: Estimated additional amount needed to be appro-
                                                                               ....--.. $4,496, 554
                                                                 - --. ..... -----....
    priated for completion of existing project....---------..-- ...


42. UNION VILLAGE RESERVOIR, CONNECTICUT RIVER BASIN, VT.

   Location. The dam is located on the Ompompanoosuc River,
four miles above its junction with the Connecticut River. It is
1/4 mile north of Union Village, Vt., and 11 miles north of White
72       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

River Junction, Vt. (See U.S. Geological Survey maps for Straf-
ford, Vt., and Mt. Cube, N.H. -Vt.)
    Existing project. The dam is of the rolled-earth type with a
dumped rock shell. It has a top length of 1,100 feet, a top width
of 30 feet, and a maximum height of 170 feet. The spillway is
approximately 350 feet from the right end of the dam and is of
the chute type with a low, curved, 400-foot long, concrete weir.
The approach channel and discharge chute are 1,000 and 1,130
feet long, respectively. The outlet works are in the right abut-
ment and consist of a 1,236-foot long, 13-foot diameter tunnel
through rock. Control of the outlet works is accomplished by
two 7-foot 6-inch by 12-foot broome gates mechanically oper-
ated through a shaft from a gatehouse above. The reservoir is
operated for flood control purposes and has a storage capacity
of 38,000 acre-feet which is equivalent to 5.7 inches of runoff
from its drainage area of 126 square miles.
    The estimate of cost for new work (1954) is $3,111,000 for
construction and $895,000 for lands and damages, a total of
 $4,006,000. The latest (1952) approved estimate for annual cost
of operation and maintenance is $19,000.
    The project is a unit of the comprehensive plan for flood con-
trol and other purposes in the Connecticut River Basin which
was authorized by the Flood Control Acts approved June 22,
1936, as amended, and June 28, 1938. (H. Doc. 455, 75th Cong.,
2d sess.)
    Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
    Operationsand results during fiscal year. New work: Opera-
tions consisted of completion of road relocation, continuation of
reservoir clearing, grading of slopes, and construction of box
culvert. Costs from regular funds were $77,819.
    Mainteriance: Operations consisted of periodic checking of
gates and operating equipment and general maintenance of
roads, buildings, and grounds, including a bituminous seal coat
for the access road and the road across the dam. A new cable
was installed in the 75-ton traveling crane in the gatehouse.
  Costs from regular funds were $13,086.
    Reservoir operation: The reservoir was regulated in April dur-
ing a period of rain and snowmelt. The computed peak inflow
was 2,300 c.f.s. The outflow was restricted to 750 c.f.s. during
the flood period and increased to 1,500 c.f.s. to empty the reser-
voir. The storage utilized was negligible.
     Total costs during the fiscal year from regular funds were
  $90,905.
     Condition at end of fiscal year. Construction of the dam was
  initiated in March 1947 and completed in June 1950. Work re-
  maining to be done consists of disposition of condensation cases
  in connection with land acquisition, relocation of telephone line,
  and completion of reservoir clearing. Total costs from regular
  funds have been $4,049,497, of which $3,984,154 was for new
  work and $65,343 for maintenance.
                       FLOOD CONTROL--NEW ENGLAND DIVISION                                                       73

                                          Cost and financial summary

                                                 Fiscal year ending June 30                           Total to June
                                                                                                    30, 1954, includ-
                                                                                                     ing fiscal years
                                   1950         1951         1952          1953          1954         prior to 1950

New work:
   Appropriated........          -$50, 000    -$15, 000      $50, 000 ..------------     $22, 000         $4, 006, 000
   Cost.................           366, 619      67, 685      17, 096      $10, 924       77, 819          3, 984, 154
Maintenance:
   Appropriated.......--------      19, 000       8, 200      12, 400       13, 500       13, 300             66, 400
   Cost_   ------------            - 7,119       19, 242      12, 400       13, 497       13, 086             65, 343



Other new work data:
     Unobligated balance,fiscal year ending June 30, 1954---......--....--...----------...........--......... $8, 171
     Unobligated balances available for succeeding fiscal year ending June 30,
     1955 ,....-...--.................                                                       . 8, 171
                                                                            .......................---------

                             43. BALL MOUNTAIN RESERVOIR,
                             CONNECTICUT RIVER BASIN, VT.
   Location. The site of the proposed dam is on the West River,
29.0 miles above its junction with the Connecticut River at Brat-
tleboro, Vt. It is 2 miles north of the village of Jamaica, Vt.
 (See U. S. Geological Survey map for Londonderry, Vt.)
   Existing project. This project provides for the construction
of a concrete arch dam with a crest length, including spillway
overflow section, of 1,140 feet. The dam will rise 247 feet above
river bed. The spillway overflow section will be located in the
center of the dam and will have a crest length of 470 feet. The
outlet works will consist of four 5-foot by 7-foot 6-inch conduits
through the dam. Control of the outlet works will be accom-
plished by gates hydraulically operated from a gallery at the
base of the dam. The reservoir will be operated for flood control
purposes and will have a storage capacity of 54,600 acre-feet
which is equivalent to 6.0 inches of runoff from its drainage area
of 172 square miles.
   The estimate of cost for new work (1954) is $14,946,000 for
construction and $354,000 for lands and damages, a total of
$15,300,000.
   The project is a unit of the comprehensive plan for flood con-
trol and other purposes in the Connecticut River Basin and was
authorized by the Flood Control Act approved December 22,
1944. (Public Law 534, 78th Cong., 2d sess.)
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. Subsurface explora-
tions for preparation of plans and specifications were substan-
tially completed. Costs from regular funds for new work were
$18,983.
   Condition at the end of fiscal year. Advance engineering and
design was 60 percent complete. No construction work has been
initiated. Total costs from regular funds have been $472,151 for
new work.
74              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                        Cost and financial summary

                                              Fiscal year ending June 30                      Total to June
                                                                                            30, 1954, includ-
                                                                                             ing fiscal years
                                 1950        19561       1952        1953        1954        prior to 1950

New work:
   Appropriated _---_.          -$90, 000   $105, 000   -$48, 000 -.----        ..-......           $472, 151
     Cost.....---------------    163, 867     34, 355     14, 121     $8, 345    $18, 983            472, 151


Other new work data: Estimated additional amount needed to be
                                                                      $14, 827, 849
  appropriated for completion of existing project-----....---...........---------------.....

                          44. SURRY MOUNTAIN RESERVOIR,
                          CONNECTICUT RIVER BASIN, N. H.

   Location. The dam is located on the Ashuelot River, 34.6 miles
above its junction with the Connecticut River and 5 miles north
of Keene, N. H. (See U. S. Geological Survey maps for Keene
and Bellows Falls, N.H.-Vt.)
   Existing project. The dam is of the rolled-earth type with a
dumped rock shell and a downstream rock toe. It has a top
length of 1,670 feet, a top width of 30 feet, and a height of 86
feet above river bed. The spillway is located at the right end of
the dam and is of the open side channel type with a low concrete
weir 338 feet in length. The spillway discharge channel is in
rock cut and is 2,000 feet in length. The outlet works, in the right
abutment, consist of a 748-foot long intake channel and a 10-foot
diameter, horseshoe-shaped tunnel through rock. The tunnel is
383 feet in length and discharges into the spillway channel.
Control of the outlet works is accomplished by two 4-foot 6-inch
by 10-foot broome gates mechanically operated through a shaft
from a gatehouse above. The reservoir is operated for flood con-
trol purposes and has a storage capacity of 32,500 acre-feet
which is equivalent to 6.1 inches of runoff from its drainage area
of 100 square miles.
   The cost of new work for the completed project was $1,407,-
200 for construction and $324,100 for lands and damages, a total
of $1,731,300. The latest (1952) approved estimate for annual
cost of operation and maintenance is $24,000.
   The project is a unit of the comprehensive plan for flood con-
trol and other purposes in the Connecticut River Basin which
was authorized by the Flood Control Acts approved June 22,
1936, as amended, and June 28, 1938. (H. Doc. 455, 75th Cong.,
2d sess.)
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. New work: None.
   Maintenance: Operations consisted of periodic checking of
gates and operating equipment and general maintenance of
roads, buildings, and grounds, including a bituminous seal coat
for the access road and the road across the dam. An under-
ground water storage tank for fire-fighting purposes was in-
                            FLOOD CONTROL-NEW ENGLAND DIVISION                                                                     75
stalled near the operating buildings. Costs from regular funds
were $17,520.
   Reservoir operation: The reservoir was regulated to reduce
flows on the Ashuelot River during five flood periods. The fol-
lowing is a summary of regulation for the year.

                                                 Computed             Minimum           Maximum
                                                   peak               regulated         regulated      Storage                %
                   Date                             inflow              outflow          outflow       utilized             total
                                                    C.F.S.               C.F.S.           C.F.S.       acre-feet          capacity
December...---..------------------..                         1, 800               0            820           6,200                   19
February........                                             1, 500
                                        ..----------------------                  0            750           3, 500                  11
March....................-------------------------           1, 200               0            790           2, 400                   7
           ------------------------
April--..........                                            2, 250               0            700           6, 400                  20
May.................---------------------------              1,200                0            650           2,700                    8



   Total costs during the fiscal year from regular funds were
$17,520.
   Condition at end of fiscal year. The project is complete. Con-
struction of the dam and appurtenant works was initiated in
August 1939 and completed in June 1942. Total costs for the
project have been $1,932,723, of which $1,731,319 was for new
work and $201,404 was for maintenance.
                                                   Cost and financial summary

                                                               Fiscal year ending June 30                              Total to June
                                                                                                                      30, 1954, includ-
                                                                                                                      ing fiscal years
                                           1950              1951           1952           1953          1954          priorto 1950

New work:
   Appropriated--.....------......-----------              -$6, 000                               ............ $1, 731319
                                                                                          -$2, 681------------
     Cost....----------------               14, 628           24, 776             $46                                   1, 731, 319
                                                                                          --......------------...........
Maintenance:
     Appropriated -----
                      ...                   22, 000           13, 000        17,800         16, 000     $17, 700              202, 300
     Cot----    .....------------           23, 714           17, 499        16, 858        17, 072      17, 520              201,404




45. BIRCH HILL RESERVOIR, CONNECTICUT RIVER BASIN, MASS.

   Location. The dam is located on the Millers River, 27.3 miles
above its junction with the Connecticut River. It is 1.3 miles
east of South Royalston, Mass., and 71/2 miles northwest of the
city of Gardner, Mass. (See U. S. Geological Survey maps for
Royalston and Winchendon, Mass.-N.H., and Templeton, Mass.)
   Existing project. The dam is of the rolled-earth type with a
dumped rock shell. It has a top length of 1,400 feet, a top width
of 25 feet, and a height of 56 feet above river bed. The spillway
consists of three concrete weirs located in two natural saddles
and an abandoned railroad cut northwest of the dam. The main
weirs have a crest length of 720 feet and 350 feet, respectively,
and the weir in the railroad cut has a crest length of 23 feet.
The outlet works are located on rock at the right end of the dam
and consist of an intake channel 1,500 feet in length, a gate
structure with a gatehouse directly above, and an outlet channel
1,150 feet in length. Control of the outlet works is accomplished
by four 6-foot by 12-foot roller gates mechanically operated from
the gatehouse above. The reservoir is operated for flood control
purposes and has a storage capacity of 49,900 acre-feet which is
76              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

equivalent to 5.3 inches of runoff from its drainage area of 175
square miles.
   The estimate of cost for new work (1954) is $1,086,000 for
construction and $3,151,000 for lands and damages, a total of
$4,237,000. The latest (1952) approved estimate for annual cost
of operation and maintenance is $17,800.
   The project is a unit of the comprehensive plan for flood con-
trol and other purposes in the Connecticut River Basin which
was authorized by the Flood Control Acts approved June 22,
1936, as amended, and June 28, 1938. (H. Doc. 455, 75th Cong.,
2d sess.)
   Local cooperation. Section 2 of the Flood Control Act approved
June. 28, 1938, applies.
   Operationsand results during fiscal year. New work: Opera-
tions consisted of construction of operator's quarters and nego-
tiations in connection with relocations and land acquisition.
Costs from regular funds were $16,142.
   Maintenance: Operations consisted of periodic checking of
gates and operating equipment and general maintenance of
roads, buildings, and grounds, including a bituminous seal coat
for the access road and the road across the dam. An under-
ground water storage tank for fire-fighting purposes was in-
stalled near the operating buildings. Costs from regular funds
were $16,947.
   Reservoir operation: There was one period of regulation at
Birch Hill during the year. In April, 4,100 acre-feet of storage,
8 percent of the total capacity, were utilized during a minor
regulation.
   Total costs during the fiscal year from regular funds were
$33,089.
   Condition at end of fiscal year. Construction of the dam and
appurtenant works was initiated in June 1940 and completed in
February 1942. Work remaining to be done consists of disposi-
tion of condemnation cases in connection with land acquisition
and abandonment of a section of road and consummation of
agreements for relocation of utilities. Total costs for the project
have been $4,361,479, of which $4,161,578 was for new work and
$199,901 was for maintenance.
                                       Cost and financial summary

                                             Fiscal year ending June 30                        Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                                1950        1951        1952          1953         1954        priorto 1950

New work:
    Appropriated    .--------   40, 000   -$18, 000 -----             $14, 000 -          -        $4,236,950
   Cost--------------_          50,978        7,932           $446      4, 223     $16, 142          4, 161,578
Maintenance:
    Appropriated--------    22, 000           9, 000        13, 900    13, 800      15, 500            199, 950
    Cost- ---          - -........
                            22, 812          18, 204        13,612     12,601       16,947             199,901


Other new work data:
Unobligated balance, fiscal year ending June 30, 1954--------------.......
                                                                    .      -----...
                                                                               $16, 449
    Unobligated balances available for succeeding fiscal year ending June
    30, 1955     ---......
                      ..........-.....                                          16, 449
     Estimated additional amount needed to be appropriated for completion
     of existing project..... ..........................                 ..
                                         ...........................-...... 50
              FLOOD CONTROL--NEW ENGLAND DIVISION                  77
   46. TULLY RESERVOIR, CONNECTICUT RIVER BASIN, MASS.
     Location. The dam is located on the Tully River, 3.9 miles
  above its junction with the Millers. It is 1 mile north of Fryville,
  Mass., and 31/ miles north of Athol, Mass. (See U.S. Geolog-
  ical Survey map for Royalston, Mass.-N. H.)
    Existing project. The dam is of the rolled-earth type with a
  dumped rock shell. It has a top length of 1,570 feet, a top width
  of 30 feet, and a height of 62 feet above river bed. The spillway
is constructed on rock in a saddle located about 800 feet from
the left end of the dam and is a low, concrete weir, 255 feet in
length. The spillway approach channel is 600 feet in length and
the discharge channel is of the chute type with a length of 1,775
feet. The outlet works, in the left abutment, consist of a 6-foot
diameter tunnel through rock. The tunnel is 274 feet in length
and is controlled by two 3-foot 6-inch by 6-foot slide gates me-
chanically operated through a shaft from a gatehouse above.
The outlet works intake and outlet channels are 500 and 580
feet long, respectively. The project was constructed with pro-
visions for future raising for the inclusion of power at the site.
The reservoir is now operated for flood control purposes and
has a storage capacity of 22,000 acre-feet which is equivalent to
8.3 inches of runoff from its drainage area of 50 square miles.
    The estimate of cost for new work (1954) is $1,180,000 for
construction and $383,000 for lands and damages, a total of
 $1,563,000. The latest (1952) approved estimate for annual cost
of operation and maintenance is $16,800.
    The project is a unit of the comprehensive plan for flood con-
trol and other purposes in the Connecticut River Basin which
was authorized by the Flood Control Acts approved June 22,
1936, as amended, and June 28, 1938. (H. Doc. 455, 75th Cong.,
2d sess.)
    Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
    Operationsand results during fiscal year. New work: Opera-
tions consisted of engineering studies made to determine the
value of power rights in connection with acquisition of certain
lands by condemnation proceedings. Trial of the case was com-
pleted and judgement obtained. Costs from regular funds were
$991.
    Maintenance: Operations consisted of periodic checking of
gates and operating equipment and general maintenance of
roads, buildings, and grounds. The State of Massachusetts ap-
plied a bituminous seal coat to the road across the dam. A small
corrugated iron storage building was erected near the dam. An
underground water storage tank for fire-fighting purposes was
installed near the operating buildings. A new cable was in-
stalled in the 15-ton traveling crane in the gatehouse. Costs from
regular funds were $15,674.
    Reservoir operation: Tully Reservoir was regulated in April
for a minor rise on the Connecticut River. During this period
6 percent of the total available storage was utilized.
    Total costs for the fiscal year from regular funds were $16,665.
78             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  Condition at end of fiscal year. Construction of the dam was
initiated in March 1947 and completed in September 1949. Work
remaining to be done consists of completion of disposition of
condemnation cases in connection with land acquisition. Total
costs have been $1,605,513, of which $1,539,682 was for new work
and $65,831 was for maintenance.
                                       Cost and financial summary

                                                   Fiscal year ending June 30                       Total to June
                                                                                                   30, 1954, includ-
                                                                                                   ing fiscal years
                                1950             1951            1952       1953         1954       priorto 1960

New work:
     Appropriated        .                    -$22, 000
                                   ..-----------------        .............-..........    -$83          $1, 562, 917
     Cost-....---------------   82, 509              5, 931       $2, 625   $1, 020         991          1, 539, 682
Maintenance:
     Appropriated--------       16, 000           10, 000         12, 600    13, 800     14, 000            66, 400
     Cost- ---------------      12,933            12,585          12,508     12,131      15,674             65,831


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954.................... $14,735
    Unobligated balances available for succeeding fiscal year ending June
    30, 1955................................................................   14,735
                                                                  ............--........
    Estimated additional amount needed to be appropriated for completion          p
    of existing project.......................................................      83

                           47. KNIGHTVILLE RESERVOIR,
                         CONNECTICUT RIVER BASIN, MASS.
   Location. The dam is located on the Westfield River, 27.5
miles above its junction with the Connecticut River. It is 4 miles
north of the town of Huntington, Mass., and approximately 12
miles west of the city of Northampton, Mass. (See U.S. Geolog-
ical Survey map for Westhampton, Mass.)
   Existing project. The dam is of the hydraulic-fill earth type
with a dumped rock shell and a downstream rock toe. It has a
top length of 1,200 feet, a top width of 30 feet, and a height of
160 feet above river bed. The spillway is a curved, concrete weir,
410 feet long, located on rock in a saddle at the right end of the
dam. The outlet works are in the right abutment and consist
of an intake channel 280 feet in length and a 16-foot diameter
tunnel through rock: The tunnel is 605 feet long and is con-
trolled by three 3-foot 6-inch by 12-foot broome gates mechan-
ically operated through a control tower from a gatehouse above.
Provision has been made for future installation of a penstock
for the development of power at the site in accordance with a
request by the Federal Power Commission. The reservoir is now
operated for flood control purposes and has a storage capacity
of 49,000 acre-feet which is equivalent to 5.6 inches of runoff
from its drainage area of 164 square miles.
   The estimate of cost for new work (1954) is $2,395,000 for con-
struction and $812,000 for lands and damages, a total of $3,207,000.
The latest (1952) approved estimate for annual cost of operation
and maintenance is $22,000.
   The project is a unit of the comprehensive plan for flood con-
trol and other purposes in the Connecticut River Basin which was
authorized by the Flood Control Acts approved June 22, 1936, as
                             FLOOD CONTROL--NEW ENGLAND DISTRICT                                                                            79
amended, and June 28, 1938. (H. Doc. 455, 75th Cong., 2d sess.)
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during the fiscal year. New work: Op-
erations consisted of completion of operator's quarters and en-
gineering studies to determine value of power rights in connection
with acquisition of certain lands. Costs from regular funds were
 $7,613.
   Maintenance: Operations consisted of periodic checking of gates
and operating equipment and general maintenance of roads, build-
ings and grounds. Costs from regular funds were $19,855.
   Reservoir operation: There were two periods of regulation at
Knightville Reservoir during the'year.
   In March, 3,900 acre-feet, 8 percent of the total storage capacity,
were utilized. The computed peak inflow was 4,000 c.f.s. The
outlet gates were closed during the flood period. The maximum
regulated outflow to empty the reservoir was 1,400 c.f.s.
   In April, 6,300 acre-feet, 13 percent of the total storage capacity,
were utilized. The computed peak inflow was 4,300 acre-feet. The
outlet gates were closed during the flood period. The maximum
regulated outflow to empty the reservoir was 3,100 c.f.s.
   Total costs during the fiscal year from regular funds were
$27,468.
   Condition at end of fiscal year. Construction of the dam was
initiated in August 1939 and completed in December 1941. Work
remaining to be done consists of disposition of condemnation cases
in connection with land acquisition. Total costs for the project
have been $3,391,670, of which $3,197,435 was for new work and
$194,235 was for maintenance.
                                                 Cost and financial summary

                                                            Fiscal year ending June 30                                       Total to June
                                                                                                                            30, 1954, includ-
                                                                                                                            ing fiscal years
                                          1950             1951             1952             1953             1954           prior to 1950

New work:
   Appropriated...-------.               $25, 000          $12, 000 --------                                       -              $3, 207, 000
     Cost .------------        -----       20, 168          24, 112            $1, 365        $7, 069          $7, 613              3, 197, 435
Maintenance:
   Appropriated--- ---- -                  22, 000           2, 500            16, 300         16, 000         18, 700                 194, 750
   Cost_-----------------                  18, 564          16, 916            16,901          15,113          19,855                  194, 235


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 ....-.---.....---------------.. $4, 565
    Unobligated balances available for succeeding fiscal year ending June
    30, 1955 ...........................................................................------------------------------------------------. 4, 565
             48. CHICOPEE,                       CONNECTICUT                       RIVER BASIN,                        MASS.
   Location. The Chicopee local protection works are located in
the city of Chicopee, Massachusetts. The project is on the east
bank of the Connecticut River, 80 miles above its mouth. (See U.S.
Geological Survey maps for Springfield North and Mt. Tom, Mass.)
   Existing project. The plan of improvement provides for the
construction of a system of earth levees and concrete floodwalls,
approximately 25,700 feet in length, and pumping stations for
the disposal of interior drainage. The system may be broken down
into three groups of protective works. The first group consists
80            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

of two short sections of levee in the extreme northern portion
of the city, known as the Willimansett section. The second group
consists of 20,200 feet of levee starting at high ground, about 2
miles below the Willimansett Bridge, and extending downstream
along the Connecticut River and up the north bank of the Chicopee
River to high ground above the Boston & Maine Railroad Bridge.
The third group consists of 3,200 feet of floodwall and 1,500 feet
of levee starting at high ground, above the highway bridge over
the Chicopee River, and extending downstream along the south
bank of the Chicopee River and the east bank of the Connecticut
River to high ground north of the highway bridge over the Con-
necticut River. The system also provides for 4 stop-log structures
and 6 pumping stations with appurtenant drainage structures.
The project, with the approved plan of reservoirs, is designed to
protect against a flood greater than any of record. The levee and
floodwall grades are, at all points, above the maximum stage of the
greatest flood of record, that of March 1936.
   The estimate of cost of new work (1954) is $1,738,000 for con-
struction and $250,000 for lands and damages.
   The project is a unit of the comprehensive plan for flood control
and other purposes in the Connecticut River Basin and was au-
thorized by the Flood Control Act approved June 28, 1938. (H. Doc.
455, 75th Cong., 2d sess.)
   Local cooperation. The city of Chicopee has fully complied with
the requirements of local cooperation for that portioh of the proj-
ect which has been constructed. In addition, the city contributed
$385 for the construction of a connecting sewer.
   Operations and results during fiscal year. Operations con-
sisted of construction of tie-in dike. Costs from regular funds
for new work amounted to $3,631.
   Condition at end of fiscal year. Construction of the authorized
project was initiated in March 1939 and completed in 1941, with
the exception of a section of dike in Willimansett and the Char-
bonneau Terrace pumping station. Work remaining to be done
consists of the completion of design and construction of the dike
in the Willimansett section and the Charbonneau Terrace pump-
ing station. Total costs for new work have been $295,000 from
Public Works Administration funds and $1,138,601 from regular
funds, a total of $1,433,601. In addition, costs of $385 apply to
contributed funds.

                                      Cost and financial summary

                                               Fiscal year ending June 30                  Total to June
                                                                                          30, 1954,includ-
                                                                                          Ing fiscal years
                               1950          1951        1952         1953      1954       prior to 1950
New work:
   Appropriated       .--.   --$88, 500   -$155, 000 .........
                                                     ------------------------   -$899         ' $1,433, 601
   Cost-----------------         4,450           190            $2     $, 700    3, 631         11,433, 601

  1 Includes $295,000 Public Works funds. In addition, the sum of $385 has been expended from con-
tributed funds for new work.
Other new work data: Estimated additional amount needed to be ap-
  propriated for completion of existing project..-............    $304, 399
                                                     ..............
                                                          :............
                    FLOOD CONTROL--NEW ENGLAND DISTRICT                                                         81
  49. WEST SPRINGFIELD, CONNECTICUT RIVER BASIN, MASS.
   Location. The West Springfield local protection works are lo-
cated in the town of West Springfield, Massachusetts. The project
is on the west bank of the Connecticut River, 76 miles above its
mouth. (See U.S. Geological Survey maps for Springfield South
and West Springfield, Mass.-Conn.)
   Existing project. This project consists of a system of earth
levees and concrete floodwalls approximately 24,500 feet in length.
The system starts at high ground, in the vicinity of Harrison Place,
and extends downstream along the Connecticut River and up the
north bank of the Westfield River to high ground at the Boston
& Albany Railroad. The work involved raising 13,700 feet of
existing levee, constructing 2,300 feet of floodwall, improving
2,400 feet of river bank, and treating 6,100 feet of existing levee
foundation. Three pumping stations with appurtenant drainage
facilities were also constructed for the disposal of interior drainage.
The project, with the approved plan of reservoirs, is designed to
protect against a flood greater than any of record. The levee and
floodwall grades are, at all points, above the maximum stage of the
greatest flood of record, that of March 1936.
   The cost of the completed project was $1,579,000 for construc-
tion and $30,000 for lands and damages.
   The project is a unit of the comprehensive plan of flood control
and other purposes in the Connecticut River Basin and was author-
ized by the Flood Control Act approved June 28, 1938. (H. Dec.
455, 75th Cong., 2d sess.)
   Local cooperation. The town of West Springfield has fully
complied with the requirements of local cooperation.
   Operations and results during fiscal year. Minor work to com-
plete the project and consisting of grading, revision of operations
manual, and preparation of as-built drawings was accomplished.
Costs from regular funds for new work were $7,662.
   Condition at end of fiscal year. The project is complete. Con-
struction of the authorized project was initiated in March 1939
and completed in July 1942 with the exception of foundation
treatment along the Westfield River south of Agawam Bridge,
which was initiated in May 1947 and completed in November
1947, and the relief well and drainage system, which was initiated
in August 1952 and completed in July 1953. Total costs have been
$245,000 from Public Works Administration funds and $1,333,724
from regular funds, a total of $1,578,724.

                                        Cost and financial summary

                                                 Fiscal year ending June 30                       Total to June
                                                                                                 30, 1954, includ-
                                                                                                 ing fiscal years
                                 1950         1951         1952         1953         1954          prior to 1950
New work:
   Appropriated--. -          -------------   $72, 000    $400, 000   -$85, 000    -$14, 276         1   $1, 578, 724
   Cost....----------------      $17, 063       11, 217      8, 278     298, 296        7, 662            1,578, 724


1 Includes $245, 000 Public Works funds.
82          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

         50. WINSTED,             CONNECTICUT              RIVER BASIN,             CONN.
   Location. The Winsted project is located in the city of Winsted,
Conn., on Mad River, a tributary of the Farmington River, which,
in turn, flows into the Connecticut River. (See U.S. Geological
Survey map for Winsted, Conn.)
   Existing project. This project involved the improvement of
the Mad River Channel to reduce flood heights. The work con-
sisted of removing an abandoned dam and excavating the channel
for 4,800 feet from Lake Street to a point approximately 1,600
feet below the Case Avenue Bridge. The channel excavation has
a bottom width varying from 7 feet to 25 feet and has 1 on 21/2
side slopes.
   The estimate of cost for new work (1954) is $172,000 for con-
struction and $30,000 for lands and damages.
   The project is a unit of the comprehensive plan for flood control
and other purposes in the Connecticut River Basin and was author-
ized by the Flood Control Act approved August 18, 1941. (H. Doc.
724, 76th Cong., 3d sess.)
   Local cooperation. The city of Winsted has fully complied with
the requirements of local cooperation.
     Operations and results during fiscal year.                            Work consisted of
completion of operations manual. Cost from regular funds for new
work were $141.
   Condition at end of fiscal year. Construction of the project was
initiated in May 1950 and completed in October 1951. Total costs
from regular funds have been $246,540 for new work. A portion
of the costs indicated for this project are reimbursable from the
bonding company due to default of contractor.

                                  Cost and financial summary

                                         Fiscal year ending June 30                     Total to June
                                                                                       30, 1954, includ-
                                                                                        ing fiscal years
                           1950        1951         1952         1953        1954        prior to 1950

New work:
   Appropriated.-- _       $88, 500    $75, 000 ............   -$38, 160      -$300            $246, 540
             ..
   Cost -----------    -    20, 591     64,663     $152,019           98         141            246, 540
                         FLOOD CONTROL-NEW ENGLAND DISTRICT                                                                       83

                     51.     INACTIVE                FLOOD            CONTROL               PROJECTS
                                                                        For last
                                                                          full         Costs to June 30, 1954
                                                                        report,                                         Estimated
                                                                          see                                             amount
                        Name of project                                 annual                         Operation        required to
                                                                        report           Con-          and main-         complete'
                                                                         for--        struction         tenance

1. Andcver Reservoir, Conn................---------------------------                                                     $4, 900,000
2. Barre Falls Reservoir, Mass.-------.               ------------ 1953                  $216,972 ----------- -2, 283, 028
3. Beards Brook Reservoir, N. H.............---.--                         1949             77, 812-.-.........             7,152,188
4. Bennington Reservoir, N. H........................ 1949                                204, 692                  .      12, 195, 308
                                                                                                                           1----.-.
5. Brockway Reservoir, Vt._----------------------- 1946                                                                    10,700,000
6. Buffumville Reservoir, Mass..-          _------         _--- ---        1953           114, 638 ------------ 2, 525, 362
7. Cambridgeport Reservoir Vt.............---------.....                                                                    5,170, 000
8. Claremont Reservoir, N. H.._                                            1949           206, 795 .............          12, 793,205
9. Clyde, R. I...._-_-----------------                    _---
                                                              ---           1948              8, 830                       , 601, 170
10. East Brimfield Reservoir, Mass.-----._--------                          1951            69, 942 _-----------5,250,               058
11. East Hartford, Conn..... ....------                  .-- ..--.          1951 1 2,135, 447-...-----....                    (2)
12. Gaysville Reservoir, Vt......-...-.-----------.-..-...-.............                                                   16, 900, 000
13. Hartford, Conn.__...             ...--.- . --------                     1953 106, 457, 222 _.                            11302, 778
14. Hodges Village Reservoir, Mass,.-.              --...---- ----- ---------. .....                 ---..........-          3, 040, 000
15. Holyoke, Mass......-----------------------------                        1953 Is 3, 418, 000 ..........                -(2)
16. Honey Hill Reservoir, N. H.-.......----------- .                        1949            92, 215 .........-.              3, 967, 785
17. Hopkinton-Everett Reservoir, N. H.--............... 1941                                67, 131 ..........            -(5)
18. Lowell, Mass.............-.------ -.-----------                         1945           490, 600 .----.-------             (2)
19. Ludlow Reservoir, Vt.-                  --------------------- -------------                                              5,690,000
20. Mountain Brook Reservoir, N. H.---------------.o1949                                    56,891-------------               (6)
21. Nashua, N. H.....                                                       1950
                                                             .....------------------------------
                                                                                        14270,000 -------------               (2)
22. North Andover and Lawrence, Mass............... 1949                                     19, 489 .............           1, 660, 511
23. Northampton, Mass.-.---- ..---                    ..--.------.--.       1950           960, 000 .........-..          -(2)
24. North Hartland Reservoir, Vt.-..--              .-.----------           1951            28, 961 ...-...-....             9, 621, 039
25. North Springfield Reservoir, Vt....- ..-- .--------- 1949                                 9, 005-............            9, 250, 995
26. Norwalk, Conn.---__ ....--.- -                         .-.----.-------  1952            52,150 --..........              (2) (7)
27. Norwich Channel Improvement,               Conn.............            1953           643,144     ._.........           17596, 856
28. Pawtucket, R. I.                                          .
                                       ------------------.-----..           1949 ------------....                               202, 000
29. Pontiac Diversion, R. I.........-             ...-.---------            1948            24, 217 ............. ()(')5, 245, 783
30. Riverdale, Mass.----- ----.------------------- 1952 15 1, 138, 075 .............                                          (2)
31. South Coventry Reservoir, Conn........---...                       .    1951            96,000 -..-.....            .  10, 004, 000
32. South Tunbridge Reservoir, Vt..-------------------------------- -------------                                            5,440,000
33. Springdale, Mass...---------- .             .------------------         1 952          700,  000-------------              (2)
                                                                                        16932, 000 .............------------- (2)
34. Springfield, Mass......---------------------------1950
35. Sugar Hill Reservoir, N. H.----------- ---------- 1946                     -- -------                 .             .
                                                                                                                   .-----      (8)
36. The Island Reservoir, Vt........ ...--..----------                    -- .... -            -. ..                         3, 310, 000
37. Thomaston Reservoir, Conn.---............-.--                           1952             25, 042 ..........             14, 974, 958
38. Townshend Reservoir, Vt.--...-- ------------                       .    1951             70, 505 ...-...-.....          10, 129, 495
39. West Brookfield Reservoir Mass........------- .                         1948             67, 154 ---..........           8, 922, 846
40. West Canaan Reservoir, N. H.----...---- -------- 1948                                    91, 900 ............            8,968, 100
41. West Hill Reservoir, Mass......                     --------......
                                                                    - ..    1951             82, 724 ..-..........           2, 647, 276
42. Westville Reservoir, Mass.. ........----.........                    . 1949              78, 568 ...........             5, 811, 432
43. Williamsville Reservoir, Vt....----............                         1949           146, 502 .............              (I)
44. Woonsocket, R. I.....---------------------------                        1953 -------             -------------            , 880, 000
45, Worcester Diversion, Mass .....--------------------                     1951             69, 737 .......            .    4, 120, 263

    1 1954 estimate except as otherwise noted.
        Completed.
    e 1949 estimate.
    SAuthorization expired due to failure of local interests to furnish assurances within the 5-year period
allowed by law.
      ' Bennington and Beards Brook Reservoirs have been substituted.
    67 A dam has been constructed at the site by private interests.
        Flood control work under authority of See. 205, Public Law 858, 80th Cong., 2d seas.
     8 Alternate site to be selected.
     ' The Island, Townshend and Ball Mountain Reservoirs have been substituted.
   16In addition, approximately $2,542,500 has been expended to date from contributed funds. During the
fiscal year an adjustment of $14,868 was credited to the Federal account and charged to the Contributed
funds account.
   InAdditional funds will be required from the City of Hartford.
   n In addition, $7,637 was expended from contributed funds.
     s In addition, $24,446 was expended from contributed funds.
   14In addition, $327 was expended from contributed funds.
   16In addition, $25,000 was expended from contributed funds.
   16In addition, $5,350 was expended from contributed funds.
   "Revoked during fiscal year $856.
        Assurances of local cooperation were approved by the Chief of Engineers on February 10, 1954.
84             REPORT OF CHIEF OF ENGINEERS, Ui S. ARMY, 1954

                          52. GENERAL INVESTIGATIONS
   Examinations and surveys. Costs and expenditures for exami-
nations and surveys during the fiscal year amounted to $466,968
(:including $69 for beach erosion and $437,251 for New Eng-
land-New York InterAgency Committee studies).          The unex-
pended balance of $15,291 at the end of the fiscal year plus an
allotment of $404,000, a total of $419,291, can be profitably ex-
pended in fiscal year 1955 for completion of studies for the New
England-New York InterAgency Committee and continuation of
navigation and beach erosion studies.
   Collection and study of basic data. Costs and expenditures
for collection and study of basic data during the fiscal year
amounted to $1,277 for flood emergency studies and $1,461 for
flood investigations. The unexpended balance of $262 at the end
of the fiscal year plus an allotment of $7,000, a total of $7,262,
can be profitably expended in fiscal year 1955 for continuation of
miscellaneous studies.
     53. INSPECTION OF COMPLETED FLOOD CONTROL WORKS
   In accordance with provision of the Flood Control Act of 1936,
as amended, local flood protection works constructed with Federal
funds are transferred to local interests to operate and maintain.
To insure compliance with regulations prescribed for their opera-
tion and maintenance, regular and periodic inspections of the fol-
lowing projects were made during the fiscal year:
       Northampton, Mass.               Springfield, Mass.
       Holyoke, Mass.                   Hartford, Conn.
       Springdale, Mass.                East Hartford, Conn.
       Riverdale, Mass.                 Winsted, Conn.
       Chicopee, Mass.                  Nashua, N.H.
       West Springfield, Mass.          Lowell, Mass.
   Portions of dikes, floodwalls, and a pumping station at West
Springfield were altered and rebuilt by local interests due to the
construction of a new highway along the river bank. Inspection
of this work to assure construction in accordance with Corps of
Engineers' standards was paid for by the Commonwealth of Mas-
sachusetts.
   In connection with inspections at East Hartford, practice exer-
cises, conducted by local Civil Defense authorities, were held to
test the effectiveness of local flood-fighting organization and co-
operating agencies.
   Cost for inspection work during the fiscal year amounted to
$1,644.
                                    Cost and financial summary

                                           Fiscal year ending June 30                    Total to June
                                                                                        30, 1954, includ-
                                                                                        ing fiscal years
                             1950        1951          1952       1953        1954        prior to 1950
Maintenance:
     Appropriated ....------...
                             $2, 867      $1, 607                 $2, 000     $1, 100            $13, 907
          --------------
     Cost...                  2, 867       1, 607 --          -    1, 456
                                                                   1-______    1, 644             13, 907
                         FLOOD CONTROL-NEW ENGLAND DISTRICT                                                                   85
    54. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
  Snagging and clearing of navigable streams and tributaries    in
the interests of flood control. (Sec. 18 of the 1946 Flood Control
Act).
   Pursuant to this authority $50,000 was made available in fiscal
year 1954 for clearing of Ashuelot River at Keene, N. H. Plans
and specifications were prepared, a contract awarded, and work
initiated. Costs for new work during the fiscal year were $14,407.
                                             Cost and financial summary

                                                        Fiscal year ending June 30                              Total to June
                                                                                                               30, 1954, includ-
                                                                                                                ing fiscal years
                                      1960           1951            1952           1953            1954         prior to 1950
New work:
   Appropriated--.....-----...............        -----------      -----------------------          $50, 000              $50, 000
   Cost .........----------....---...------------   ------------.......----------------------        14, 407               14, 407

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954................ .........                                $12, 468
    Unobligated balances available for succeeding fiscal year ending June
    30, 1955                                                                                                         12,468
                ........------------.......-------.................----...............--................----------------------.......................
               RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT                                                         87



      IMPROVEMENT OF RIVERS AND HARBORS IN THE
               NEW YORK, N. Y., DISTRICT
   This district comprises western Vermont, small portions of
western Massachusetts and Connecticut, eastern New York, in-
cluding Long Island, and northeastern New Jersey, embraced in
the drainage basins tributary to Lake Champlain and the St. Law-
rence River system east thereof and to the Atlantic Ocean from
New York-Connecticut State line to but not including Manas-
quan Inlet, N. J.
   It exercises jurisdiction, however, over all matters pertaining to
the improvement of the Great Lakes to Hudson River waterway.
Under the direction of the Secretary of the Army, the district engi-
neer, as Supervisor of New York Harbor, also exercises jurisdic-
tion under the laws enacted for the preservation of the tidal waters
of New York Harbor, its adjacent or tributary waters, and the
waters of Long Island Sound.
                                              IMPROVEMENTS

                     Navigation                                           Navigation-Continued
                                                   Page                                                             Page
1.   Port Jefferson Harbor, N. Y....                  87   23. New York and New Jersey
2.   Mattituck Harbor, N. Y..........                 89         Channels. ...                  .........          129
3.   Lake Montauk Harbor, N. Y._                      90   24. Newark Bay, Hackensack &
4.   Long Island Intracoastal Wa-                                Passaic Rivers, N. J..............                133
        terway, N. Y-.....---------.........           92   25. Great Kills Harbor, Staten
5.   Fire Island Inlet, N. Y __-..--.. ..             93         Island, N. Y.....................                 137
6.   Great South Bay, N.Y. ........___                94   26. Raritan River, N. J................--..             138
7.   Jones Inlet, N. Y ............                _  96   27. Shrewsbury River, N. J...........                   141
8.   East Rockaway (Debs) Inlet,                           28. Supervision of New York Har-
        N. Y .....................
                                 .........    ....---  98         bor..................................... ......   143
9.   Jamaica Bay, N. Y. .............. _             100   29. Inactive Navigation Projects..                      146
10.   Coney Island Channel, N. Y....                  102
11.   Bay Ridge & Red Hook                                                       Flood Control
        Channels, N. Y ................               103
12.   Gowanus Creek Channel, N.Y                      105   30. Hoosick Falls, Hoosic River
13.   East River, N. Y ....................           107         Basin, N. Y ........................              148
14.   Harlem River, N. Y..........                    109   31. North Adams, Hoosic River
15.   Hudson River Channel, New                                   Basin, M ass...........................           148
        York Harbor ..........................        111   32. Adams, Hoosic River Basin,
16.   Rondout Harbor, N. Y .. _......                 114         Mass ...................................          151
17.   Hudson River, N. Y..............                115   33. Inactive Flood Control Projects                     153
18.   Great Lakes to Hudson River                           34. General Investigations_.... .                       153
        Waterway, N. Y. .................             119   35. Inspection of Completed Flood
19.   Narrows of Lake Champlain,                                  Control Works........................             154
        N. Y. & Vt ............ ..............        122   36. Flood Control Works Under
20.   Burlington Harbor, Vt.............              123         Special Authorization............                 155
21.   New York Harbor, N. Y..........                 125
22.   New York Harbor, Collection
        of Drift ..................................   128

                          1. PORT JEFFERSON HARBOR, N. Y.
   Location. This is an indentation of the north shore of Long
Island, about 56 miles by water east of the Battery, New York
City, and 13.5 miles southeast of Bridgeport Harbor, Conn. It is
88               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

about 1.75 miles long and averages 0.7 mile wide. (See U. S. Coast
and Geodetic Survey Chart No. 361.)
   Previous projects. Adopted by River and Harbor Act of March
3, 1871, and modified in 1875 and 1877. For further details, see
Annual Reports for 1875, 1877, and 1915, pages 265, 221, and 1771,
respectively.
   Existing project. This provides for dredging a channel through
the entrance 300 feet wide and 16 feet deep at mean low water, for
repairing and enlarging two riprap jetties built under the previous
project, and for extending the east jetty a distance of 450 feet.
The length of channel included in the project is about 2,600 feet,
the length of the west jetty is 940 feet, and the projected length of
the east jetty about 2,000 feet. Mean tidal range, 6.4 feet inside of
entrance channel; mean range of spring tides, 7.7 feet; irregular
fluctuations due to wind and barometric pressure vary from 3.9
feet below mean low water up to 6.2 feet above mean high water.
   The estimate of cost for new work, revised in 1954, is $1,210,000,
exclusive of amounts expended under previous projects, $57,000
to be contributed by local interests. The latest (1938) approved
estimate for annual cost of maintenance is $2,500.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                        Work authorized                                Documen
Sept. 9,1890     Enlarging jetties and dredging channel 10 feet deep    Annual Report, 1     , p. 751.
                  and 200 feet wide.
Aug. 18,1894     Dredging channel 12 feet deep..-------------------     Annual Report,     95, p. 831.
July    3,1930   Channel 16 feet deep and 300 feet wide and extension   H. Doc. 305, 7      Cong., 1st sees.
                  of east jetty.                                         (Contains latest published map.)


  Local cooperation. The River and Harbor Act of July 3, 1930,
provides that local interests shall dredge the channel to full project
dimensions under plans to be approved by the Chief of Engineers
and the Secretary of War, or shall contribute $57,000 to the cost of
he work.
   Terminal facilities. There are 8 terminals with a total avail-
able berthage of 2,430 feet located at the head of the harbor, 1 of
which is a shipyard with storage space for 50 vessels and equipped
with 3 marine railways. One privately owned pier is open to the
public. The facilities are adequate for existing and reasonably
prospective commerce.
   Operationsand results during fiscal year. The cost of a survey
to determine the condition of the entrance channel was $646 for
maintenance.
   Condition at end of fiscal year. Work under the existing project
was commenced in May 1891 and is about 30 percent complete.
The channel was completed to a 12-foot depth by the United States
in 1903, and was partially dredged to a 16-foot depth by private
interests under the modified project in 1930 and 1931. The east
jetty has been built to a length of 1,500 feet and the west jetty to a
length of 940 feet, but of incomplete width and height. These
jetties have aided materially in maintaining the width and depth
of the dredged channel lying between them. No work of mainte-
nance or improvement has been done by the United States since
                RIVERS AND HARBORS--NEW YORK, N. Y., DISTRICT                                                   89
1909. When examined in October 1953, the controlling depth at
mean low water through the channel was 16 feet for a width vary-
ing from 70 to 300 feet. The work remaining to be done under the
existing project consists in completing the jetties to project di-
mensions and removing a few shoals left after the dredging of the
16-foot channel by private interests.
  The total cost of the existing project to June 30, 1954, was
$102,499, of which $91,227 was for new work and $11,272 for
maintenance.
                                        Cost and financialsummary

                                                  Fiscal year ending June 30                        Total to June
                                                                                                   30, 1954, includ-
                                                                                                    ing fiscal years
                                 1950          1951          1952          1953          1954        prior to 19501
New. work:
   Appropriated ......------------------------------------------------------------                         $171, 427
    Cost........---------------------------------- ----------------------               --------            171, 427
Maintenance: .
    Appropriated ........----------------------------------------       $700               -$54               11, 272
    Cost--------------------------------------------------------............                $646              11, 272

  1 Includes $80,200 for new work for previous projects.
  2 Exclusive of $57,000 to be contributed by local interests.


Other new work data: Estimated additional amount needed to be ap-
  propriated for completion of existing project---..--...---..---------............................ 2$1, 119,000

                               2. MATTITUCK HARBOR, N. Y.
   Location. This is a tidal inlet on the north shore of Long Island,
85 miles east of the Battery, New York City, and 24 miles south-
east of New Haven Harbor, Conn., extending southward about 21/4
miles to the village of Mattituck. (See U. S. Coast and Geodetic
Survey Chart No. 363).
   Existing project. This provides for a channel 7 feet deep at
mean low water from Long Island Sound to the bridge at Water-
ville, protected at the entrance by two parallel jetties 400 feet
apart, thence 7 feet deep at mean high water to the village of
Mattituck, the widths being 100 feet at the entrance and 80 feet
elsewhere. Total length of the channel is about 2.2 miles. Mean
tidal range at entrance, 4.9 feet; at Old Mill Bridge, Waterville,
5.1 feet; mean range of spring tides at entrance, 5.8 feet; at Old
Mill Bridge, 6 feet; irregular fluctuations due to wind and baro-
metric pressure vary from 2.2 feet below mean low water up to 6.6
feet above mean high water.
   The cost for new work for the completed project, including the
cost of maintenance up to June 30, 1909, was $133,344. The latest
 (1950) approved estimated cost of annual maintenance is $12,000.
   The existing project was authorized by the following River and
Harbor Acts:
     Acts                           Work authorized                                       Documents
June 3,1896      The 7-foot channel, and 2 riprap jetties-........---------..--... Annual Report, 1891, p. 843.
Aug. 30, 1935    250-foot extension to west jetty_ ------------------ H. Doc. 8, 71st Cong., 1st sess.
                                                                                    (Contains latest published map.)


   Local cooperation. Fully complied with.
   Terminal facilities. A bulkhead and pier approximately 100
90             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

feet in length are situated at the entrance to the harbor. There is
a timber bulkhead at Waterville, with available wharfage of 710
feet. At the head of the project there is a crib pier, in poor con-
dition, with 50 feet of available wharfage. These facilities are
considered adequate for existing commerce.
   Operations and results during fiscal year. The cost of a survey
to determine the condition of the channel was $285 for mainte-
nance.
   Condition at end of fiscal year. Work under the existing project
was commenced September 1900 and substantially completed Au-
gust 1938. The dredging was completed in 1914. The east jetty
was completed in 1906 for a length of 775 feet. The west jetty
was completed in 1938. When examined in May 1950 and October
1953, the controlling mean low water depth was 7 feet for a width
of 50 to 100 feet from Long Island Sound to 900 feet upstream
from south end of west jetty, thence 7 feet for a width varying
from 80 to 40 feet to Old Mill drawbridge, thence 4 feet for a width
varying from 80 to 30 feet to Long Creek, thence the depths de-
crease to zero at the village of Mattituck.
   The total cost of the existing project to June 30, 1954 was $347,-
025--$133,344 for new work and $213,681 for maintenance.
                                        Cost and financial summary

                                                  Fiscal year ending June 30                          Total to June
                                                                                                    30, 1954, includ-
                                                                                                     ing fiscal years
                                 1950          1951          1952          1953          1964          prior to 1950
New work:
   Appropriated----.......----...--.....--   ----------- ---------------------     --------------             33,844
   Cost      ----------------------------------------------------------------                                133, 344
Maintenance:
   Appropriated.
   Cost
                   ------    .          $900
                ........-----------------900
                                                $14, 885s ..
                                                  14,88 --------------------
                                                                               $00         -$15
                                                                                              285
                                                                                                             213, 681
                                                                                                             213, 681


                            3. LAKE MONTAUK                    HARBOR, N. Y.
   Location. This harbor is located on the east end of Long Island,
about 3 miles by land west of Montauk Point and 125 miles by
water east of New York City. It is landlocked on the east, south,
and west sides and is connected on the north with Block Island
Sound by an artifical inlet. (See U. S. Coast and Geodetic Survey
Chart No. 362.)
   Existing project. This provides for a channel 12 feet deep at
mean low water and 150 feet wide extending from the 12-foot con-
tour in Block Island Sound to the same depth in the existing yacht
basin east of Star Island; for a boat basin 10 feet deep, 400 feet
wide, and 900 feet long, located northwest of Star Island; and for
the repair and extension shoreward of the east and west jetties.
The length of section included in the project is 0.7 mile. Mean
tidal range, 1.9 feet; mean range of spring tides, 2.2 feet; irregular
fluctuations due to wind and barometric pressure vary from 2
feet below mean low water up to 7 feet above mean high water.
   The estimate of cost for new work, revised in 1954, is $452,000,
exclusive of $82,738 from the Navy Department funds. The esti-
mate of annual cost of maintenanice, made in 1950, is $7,500.
The existing project was adopted by the River and Harbor Act
         RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT              91
of March 2, 1945 (H. Doc. 369, 76th Cong., 1st sess.). For latest
published map, see project document.
   Local cooperation. The River and Harbor Act of March 2,
1945, provides that local interests shall:
   a. Furnish, free of cost to the United States, spoil disposal areas
for initial work and for subsequent maintenance when and as re-
quired.
    b. Hold and save the United States free from claims for dam-
ages that may occur from the construction and maintenance of the
improvements.
   c. Convey to the United States, free of cost, all necessary rights-
of-way and structures, including such absolute and indefeasible
easement in the body of water known as Lake Montauk Harbor
and in the shores and bed thereof as may be necessary to insure its
permanent dedication to the use and purpose of a public navigable
waterway.
   d. Give assurances satisfactory to the Secretary of War that
they will construct and maintain for free public use suitable road-
ways to permit access to the boat basin and inner harbor.
   e. Give assurances satisfactory to the Secretary of War that
they will construct and maintain a suitable public landing open to
all on equal and reasonable terms. And provided further that no
work be done by the United States until the rights-of-way, struc-
tures, and easement specified in c above have been conveyed to the
United States; and title to rights-of-way required for roadways
and landing facilities specified in d and e above, has been vested in
the county of Suffolk or the town of East Hampton, in the State of
New York. Under date of December 8, 1942, the Chief of Engi-
neers approved the instruments complying with condition c
above, and partially complying with items a and b. Work under-
taken in Lake Montauk Harbor in 1942 was not then a part of an
authorized river and harbor project but was performed for the
Navy Department. The conditions of local cooperation required
under the project were not considered wholly applicable.
   The supervisor, town of East Hampton, was notified of the con-
ditions of local cooperation in letter dated January 24, 1946. Local
interests have indicated that the remaining conditions will be met
within the near future.
   Terminal facilities. Water terminals, twenty in number, of
which three are not presently usable and one is under construc-
tion, with a total available berthage of 4,089 feet, are located on
the east side of Star Island, the lake area south of the island, at
the inner end of entrance channel. None of the terminals has rail
connections or is equipped with freight handling devices. Nine-
teen of the terminals are privately owned, and one is publicly
owned. Upon completion of a public landing to be constructed in
accordance with the requirements of local cooperation, the term-
inals will be adequate for existing commerce.
   Operations and results during fiscal year. The cost of a survey
to determine the condition of the channel was $400 for mainte-
nance.
   Conditions at end of fiscal year. Work under the existing proj-
ect was 31 percent completed. Dredging of the entrance channel
92             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

and shoreward extension of the west jetty were performed from
August 1942 to January 1943 at the request of the Navy Depart-
ment with Navy funds. When examined in October 1953, the con-
trolling depth at mean low water was 10 feet for a width varying
from 80 to 150 feet from a point in iBlock Island Sound about 300
feet north of the west jetty to the upstream limit in Yacht Basin
east of Star Island. The boat basin was found to have a depth of
from 10 to ±1.3 feet for a width of 400 feet. The work remaining
to be done to complete the project consists of dredging a boat basin
northwest of Star Island; repair of existing east and west jetties
and shoreward extension of the east jetty.
   The total costs to June 30, 1954, were $140,347-$82,738, Navy
funds for new work, and $57,609, regular funds for maintenance.
                                     Cost and financial summary

                                            Fiscal year ending June 30                      Total to June
                                                                                           30, 1954, includ-
                                                                                            ing fiscal years
                              1950        1951         1952         1953         1954        priorto 1950

New work:
   Appropriated,------------------------------------------.------------
   Cost---------------------------------------------------------------
Maintenance:
     Appropriated........
                    -------   $54,988        $413        $328         $400   ---.-------            $57, 609
     Cost................
           ----------------    54,988            413                            $400
                                                              328 ...-----------........             57,609

1Cost of $82,738 were applied against Navy funds.
Other new work data: Estimated additional amount needed to be ap-
  propriated for completion of existing project , , , , , , , , , , ,, , , , , , , , , $452, 000

          4. LONG ISLAND INTRACOASTAL WATERWAY, N. Y.
   Location. This waterway extends from East Rockaway Inlet,
on the south side of Long Island, to Great Peconic Bay at the east-
ern end of Long Island. The section included under this project
extends from Great South Bay opposite Patchogue to the south
end of Shinnecock Canal. (See U. S. Coast and Geodetic Survey
Chart No. 578.)
   Existing project. This provides for a channel 100 feet wide
and 6 feet deep at mean low water from the federally improved
channel in Great South Bay, opposite Patchogue to the south end
of Shinnecock Canal. The length of the section included in the
project is 34 miles. The mean tidal range varies from 1.0 foot in
Chinnecock Bay to 0.7 foot in Patchogue Bay; mean range of
spring tides varies from 1.2 feet to 0.8 foot; irregular fluctuations
due to wind and barometric pressure vary from 1.8 feet below low
water to 12.0 feet above mean high water.
   The cost for new work for the completed project was $235,964.
The latest (1950) approved estimated cost of annual maintenance
is $15,000.
   The existing project was adopted by the River and Harbor Act
of August 26, 1937 (H. Doc. 181, 75th Cong., 1st sess.). The latest
published map is in the project document.
   Local cooperation. Fully complied with except that local in-
terests are required to furnish suitable spoil disposal areas for
subsequent maintenance as required.
               RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT                                                                    93
   Terminal facilities. There are 17 boat repair and storage
yards within the area immediately adjacent to the Federal im-
provement. There is ample room for expansion and development
of terminals when future commerce warrants.
   Operations and results during fiscal year. The cost of a survey
to determine the condition of the channel was $951 for mainte-
nance.
   Condition at end of fiscal year. Work under the existing proj-
ect was commenced October 1939 and completed September 1940.
When examined in October 1953, the controlling mean low water
depth in the channel was 4 feet for a width of 100 feet.
  The total cost of the existing project to June 30, 1954, was
$328,088, of which $235,964 was for new work and $92,124 for
maintenance.
                                         Cost and financial summary

                                                       Fiscal year ending June 30                                  Total to June
                                                                                                                  30, 1954, includ-
                                                                                                                   ing fiscal years
                                  1950             1951                  1952                 1953      1954        prior to 1950

New work:
   Appropriated -------- ----------- .       .$235, --         -------------------.---.-------..                                964
   Cost---------         ------------------------------------------------------                                  ----      235,964
Maintenance:
   Appropriated........
                -------            $6, 005   ............----      ............               $1, 000    -- 49              92, 124
   Cost.----------------           32, 229   ........-- ..----....--- ...-----------.......   -----        951              92, 124



                                5. FIRE ISLAND INLET, N. Y.
  Location. Fire Island Inlet is situated on the south shore of
Long Island, about 50 miles by water south and east of the Bat-
tery, New York City. It is the main entrance into Great South
Bay from the Atlantic Ocean. (See U. S. Coast and Geodetic Sur-
vey Chart No. 578.)
  Existing project. This provides for the construction of a jetty
extending generally southwest and south for a length of 5,000 feet
from high ground on Democrat Point at the west end of Fire Is-
land, and a channel 10 feet deep and 250 feet wide from deep water
in the ocean to deep water within the inlet. Mean tidal range at
ocean and inlet ends of Democrat Point are 4.1 and 2.6 feet, re-
spectively. Irregular fluctuations due to wind and barometric
pressure vary from 2.5 feet below mean low water up to 2.6 feet
above mean high water.
   The cost for new work for the completed project was $594,355,
exclusive of $90,190 contributed by local interests. The estimate
of annual cost of maintenance, revised in 1950, is $110,000.
   The existing project was authorized by the following River and
Harbor Acts:
    Acts                             Work authorized                                                    Documents
Aug. 26,1937   Construction of jetty....---..----------------------- Rivers and Harbors Committee
                                                                                                 Doc. 33, 75th Cong., 1st sess.
May 17, 1950   Channel 10 feet deep-..-----............................--------------------... H. Doc. 762, 80th Cong., 2d seas.
                                                                                                 (Contains latest published map.)


  Local cooperation. The River and Harbor Act of May 17, 1950,
provides that local interests shall:
94               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   a. Furnish free of cost to the United States all lands, easements,
rights-of-way, and spoil disposal areas necessary for the new work
and subsequent maintenance, when and as required.
   b. Hold and save the United States free from any damages re-
sulting from the improvement.
   These conditions have not been fulfilled. The requirements un-
der the act of August 26, 1937, have been fully complied with.
   Terminal facilities. No terminals are within the area immedi-
ately adjacent to the Federal improvement. There are 42 com-
mercial and pleasure boating terminals with a total berthage of
15,935 feet located at Patchogue, Sayville, West Sayville, Islip, and
Bay Shore. In addition, 49 boat repair and storage yards are
located along the shores of Great South Bay and adjacent creeks.
The facilities are ample for present and probable future needs.
There is room for expansion should future commerce warrant.
   Operationsand results during fiscal year. The costs of surveys
to determine the condition of the channel were $1,931 for main-
tenance.
   Condition at end of fiscal year. Work under the existing proj-
ect was commenced June 1939. The jetty was completed in 1941
and in view of the fact that a survey made in November 1953 re-
vealed the existence of a channel with dimensions substantially the
same as those authorized, work under the existing project was
considered complete as of November 1953. When last examined
in May 1954 the controlling mean low water depth was 10 feet for
a width of 150 to 250 feet from deep water in the ocean to deep
water within the inlet. The jetty has surpassed its capacity as a
sand entrapping agent and when examined in October 1953 was
found to be in fair condition.
   The total costs of the existing project to June 30, 1954, were
$690,087-$594,355 United States funds and $90,190 contributed
funds-a total of $684,545 for new work and $5,542 for main-
tenance.
                                          Cost and financial summary

                                                   Fiscal year ending June 30                     Total to June
                                                                                                 30, 1954, includ-
                                                                                                  ing fiscal years
                                   1950          1951           1952      1953        1954          prior to 1950'
New work:
   Appropriated..
   Cost..      -
                ------- --------
                       ---------------
                                            ---------------------
                                       ----------------------
                                                                       --------------------
                                                                              --- -----------
                                                                                                         $594, 355
                                                                                                            594,355
Maintenance:
   Appropriated.                ..--------..
                         ....--------                     ............ $2, 000
                                                    $151------------                   $1, 983               6, 212
   Cost----------        -------------------                             1,383
                                                     151 ------------...........        1,931                5,542

   In addition $90,190 for new work was expended from contributed funds.

                                  6. GREAT SOUTH BAY, N. Y.
  Location. This is a lagoon inside the south shore of Long Is-
land, N. Y., about 26 miles long and 2 to 6 miles wide. The prin-
cipal entrance, through Fire Island Inlet, is about 50 miles by
water south and east of the Battery, New York City. (See U.S.
Coast and Geodetic Survey Chart No. 578.)
          RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT           95
    Previous projects. Adopted by the River and Harbor Act of
September 19, 1890. For further details, see page 1773, Annual
Report for 1915, and page 182, Annual Report for 1938.
    Existing project. This provides for a channel 200 feet wide and
10 feet deep at mean low water from Fire Island Inlet to the
central basin in Great South Bay, and a channel 8 feet deep and
100 feet wide from the central basin in the bay to the head of
navigation in Patchogue River. The length of section included in
the project is about 19.1 miles. Mean tidal range in the bay, 0.7
foot; mean range of spring tides, 0.8 foot; irregular fluctuations
due to wind and barometric pressure vary from 1.7 feet below mean
water up to 4.6 feet above mean high water.
    The estimate of cost for new work, revised in 1954, is $213,000
exclusive of amount expended under previous project. The latest
  (1950) approved estimate for annual cost of maintenance is $4,500.
    The existing project was adopted by the River and Harbor Act
of June 13, 1902 (H. Doc. No. 103, 56th Cong., 2d sess.). For
latest published map, see Annual Report for 1916, page 2018.
    Terminal facilities. Water terminals, 21 in number, with avail-
able wharfage of 5,045 feet, are located along the shores of Patch-
ogue River. One terminal has mechanical handling facilities;
seven have marine railways. There are 8 boat-building yards; 2
fuel-oil terminals; a coal yard; and 2 village wharves open to the
public. These facilities are considered adequate for the existing
commerce.
    Operations and results during fiscal year. The cost of a survey
to determine the condition of the channel was $1,878 for main-
tenance.
    Condition at end of fiscal year. Work under the existing project
was commenced November 1902 and is about 60 percent complete.
The channel in Patchogue River was completed in 1904. Of the
dredging through three bars, necessary to provide the projected
channel, only the easterly one, bar C, was dredged. The west
jetty, 1,700 feet long, completed under the previous project in
1897 and repaired in 1914, and the east jetty, formed of a sand
spit, 1,000 feet long, with a riprap extension 330 feet long, com-
pleted in 1917, are in good condition. When examined in October
1953 and May 1954, the controlling mean low water depth was 10
feet for widths of 140 to 200 feet from Fire Island Inlet to Point
of Woods except for three shoals bypassed by naturally deep
water, thence 7 feet to Green Point and 8 feet from there to
junction with channel to Patchogue River for widths of 200 feet,
thence 7 feet for widths of 50 to 100 feet to the head of project in
Patchogue River. The head of navigation is Division Street,
Patchogue, about 19.1 miles by channel from the entrance at Fire
Island Inlet.
    The work remaining to be done to complete the project consists
of dredging through two bars necessary to provide the projected
channel to Patchogue River.
    The total cost of the existing project to June 30. 1954. was
$255,162-$59,821 for new work and $195,341 for maintenance.



     Sig 4--95-126
96                     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                     Cost and financial summary

                                                               Fiscal year ending June 30                                     Total to June
                                                                                                                             30, 1954, includ-
                                                                                                  I                          ing fiscal years
                                              1950            1951         1952              1953                 1954        prior to 19501

New work:
     Appropriated            .....
                           ----........                  ..             .--                             .----- -         -            $99, 821
     Cost ..------------ ------------                    ------------     ----------------              --------
                                                                                                               -----                   99, 821
Maintenance:
     Appropriated ..-------                 -$17, 158            $565                                 $800         $1, 200            195, 463
     Cost.............-----------------..       37,529          1,617   ------------                                1,878             195,341


1 Includes $40,000 for new work for previous projects.
Other new work data: Estimated additional amount needed to be ap-
                                                          --......
propriated for completion of existing project -----------.....    .........-----------$153, 000

                                                     7. JONES INLET, N.                      Y.

   Location. This is a small inlet on the south shore of Long Island
connecting Hempstead Bay with the Atlantic Ocean. It is 37 miles
by water southeast of the Battery, New York City. (See U.S.
Coast and Geodetic Survey Chart No. 579.)
   Existing project. This provides for an entrance jetty and a
channel 12 feet deep and 250 feet wide, from that depth in the
ocean through the inlet to the Loop Causeway Bridge over Long
Creek. The length of section included in the project is about
2.1 miles. The mean tidal range varies from 4.2 feet at the ocean
entrance to 3.1 feet at the Loop Causeway Bridge; the mean range
of spring tides varies from 5.0 feet to 3.7 feet, respectively; ir-
regular fluctuations due to wind and barometric pressure vary
from 3.9 feet below mean low water up to 8.5 feet above mean
high water.
   The estimate of cost for new work, revised in 1954, is $1,785,000,
exclusive of $1,785,000 (one-half of total cost) to be contributed by
local interests. The estimate of annual cost of maintenance, re-
vised in 1949, is $65,000.
   The existing project was adopted by the River and Harbor Act
of March 2, 1945, (H. Doc. 409, 77th Cong., 1st sess.). For latest
published map see project document.
   Local cooperation. The River and Harbor Act of March 2,
1945, provides that local interests shall:
   a. Contribute 50 percent of the first cost of the improvement.
   b. Furnish assurances satisfactory to the Secretary of War
that they will provide free of cost to the United States all lands,
easements, rights-of-way, and spoil disposal areas needed for the
initial work and subsequent maintenance, when and as required.
   c. Hold and save the United States free of claims for damages
resulting from the improvements.
   d. Provide and maintain a channel 12 feet deep and generally
200 feet wide from the Loop Causeway Bridge over Long Creek to
the head of navigation in Freeport Creek at Mill Road.
   Assurances of compliance with the above conditions were ac-
               RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT                                                        97
cepted by the Secretary of the Army on April 15, 1953. Authority
was also granted by the Secretary of the Army on September 16,
1952, to accept an advance of funds amounting to $2,000,000 of-
fered by the State of New York, the County of Nassau and the
town of Hempstead to carry out the improvement at this time.
The sum of $2,715,000, $1,357,500 advanced and $1,357,500 con-
tributed, was deposited to the credit of the United States on July
2, 1953.
   Terminal facilities. Within the area tributary to Jones Inlet
there are a number of privately owned small wharves and 40 boat
repair and storage yards. The latter are equipped for the repair of
pleasure craft and fishing vessels.    In addition, there are nine
public wharves open to the public free of charge, with a total dock-
age of 2,180 feet. Additional terminals would have to be con-
structed for the receipt of commercial freight in any sizable
quantity.
   Operationsand results during the fiscal year. Under a contract
for construction of a stone jetty at the entrance to the inlet, work
was commenced November 18, 1953, and was in progress at the
end of the fiscal year. During the fiscal year, 259,727 cubic feet,
solid measure, of stone were placed at a cost of $286,118, including
the cost of engineering and design, for new work.
   Condition at end of fiscal year. Construction of the jetty is
about 14 per cent complete. The controlling mean low water
depth through the inlet was 6 feet along a circuitous course when
examined in September 1952.
   The work remaining to be done under the existing project con-
sists of completion of the jetty and dredging of the channel to its
authorized dimensions.
   The total cost of the existing project to June 30, 1954, was
$293,678-$5,000 United States funds, $143,059 contributed funds
and $143,059 advanced funds, a total of $291,118 for new work
and $2,560 for maintenance.
                                         Cost and financial summary
                                          UNITED STATES FUNDS

                                                  Fiscal year ending June 30                           Total to June
                                                                                                      30, 1954, includ-
                                                                                                      ing fiscal years
                                  1950           1951          1952          1953           1954        prior to 19501
New work:
   Appropriated........                  .....------------------------------------   $5,000                     $5, 000
   Cost.....----......-----.....--------.---------- -------                     .            .
                                                                                      5,000 -----------          5,000
Maintenance:
                     ---
   Appropriated........      -----------------------------------------------------------                         2, 560
   Cost -----------           -------------------------                  ---------------------------------       2,560

  1 Exclusive of $1,785,000 to be contributed by local interests.

Other new work data: Estimated additional amount needed to be ap-
  propriated for completion of existing project ...------------------............................... $1,780, 000
98              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                         ADVANCED FUNDS

                                           Fiscal year ending June 30                                                           Total to June
                                                                                                                               30, 1954, includ-
                                                                                                                               ing fiscal years
                              1950        1951                       1952            1953                 1954                   prior to 1950

New work:
   Appropriated                                                                                   $1, 357, 500                          $1, 357, 500
   Cost_         _                                                                                        143, 059                              143,059
Maintenance:
   Appropriated    .-
   Cost       _-        _


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954----....--..------............. $193, 909
    Unobligated balances available for succeeding fiscal year ending June
               . .....-----------------------------------------------
    30, 1955-----                                                                          93,909

                                     CONTRIBUTED FUNDS

                                           Fiscal year ending June 30                                                          Total to June
                                                                                                                           30, 1954, includ-
                                                                                                                            ing fiscal years
                              1950        1951                       1952           1953                  1954                  prior to 1950

New work:
   Appropriated                                                                            .- -   $1,357, 500                           $1, 357, 500
   Cost- _--                                                --------------------------------              143,059                               143,059
Maintenance:
   Appropriated
     Cost_                                       ---   -
                                                       --    -   -    -   -   --   -- - - - -     -   -    -   -   -   -   -    -   -   -   -    -   -   -




Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954        ...........--
                                                                     -         ............$193, 891
    Unobligated balances available for succeeding fiscal year ending
    June 30, 1955................-------------------------------------------- $193,891
    Estimated additional amount needed to be appropriated for com-
      pletion   of existing    project      -__-_                -.....                           ......           ......               427, 500


                  8. EAST ROCKAWAY                               (DEBS)            INLET, N. Y.

   Location. This inlet is situated on the south shore of Long
Island between the main body of the island and the western end
of Long Beach. It is 10 miles east of Rockaway Inlet and about
27 miles by water south and east from the Battery, New York City.
 (See U. S. Coast and Geodetic Survey Charts Nos. 579 and 1215.)
   Existing project. This provides for a channel 12 feet deep at
mean low water and 250 feet wide from the 12-foot contour in the
Atlantic Ocean to the 12-foot contour in Long Beach Channel, a dis-
tance of about 0.6 mile, protected by jetties. Mean tidal range, 4.1
feet; mean range of spring tides, 4.9 feet; irregular fluctuations
due to wind and barometric pressure vary from 4.1 feet below
mean low water up to 5.2 feet above mean high water.
   The estimate of cost for new work made in 1954 is $1,310,000 (ex-
cluding $100,000, local contribution). The latest 1950 approved
estimate for annual cost of maintenance is $20,000.
   The existing project was adopted by the River and Harbor Act
of July 3, 1930 (H. Doc. 19, 71st Cong., 1st sess.). The latest
published map is in the project document.
   Local cooperation. The River and Harbor Act of July 3, 1930,
provides that local interests shall contribute $100,000 to the cost
         RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT               99
  of the work; give assurances satisfactory to the Secretary of War
  and the Chief of Engineers that they will provide and maintain at
  their own expense interior channels suitable for navigation, not less
  than 12 feet deep, from East Rockaway Inlet to the Hempstead-
  Oyster Bay line, a distance of about 15 miles, to Hewlett Harbor
  and to Freeport Harbor; furnish, without expense to the United
  States, necessary land, easements and rights-of-way for construc-
  tion and maintenance of the jetties, and agree to hold and save the
  United States free of claims for damages to public and private
property resulting from the improvement.
     Assurances of compliance with the conditions of local coopera-
tion precedent to construction of entrance channel and east jetty
were approved by the Chief of Engineers and Secretary of War on
July 14 and 15, 1932, respectively. Local contribution of $100,000
was deposited to the credit of the United States on August 23,
  1932. Since the construction of the west jetty is not considered
necessary at this time, easements, rights-of-way, and release of
claims for damages necessary for construction are not being se-
cured.
     Terminal facilities. There are 33 terminals in Oceanside, Island
Park, Long Beach, and East Rockaway. Eight of these are oil
terminals-6 at Oceanside, one of which has a railroad spur, and
2 at Island Park. The other terminals consist of repair and moor-
ing docks with a berthage of 3150 feet. Of these 14 have marine
railways and 1 has mechanical handling facilities. There are public
wharves at East Rockaway and Woodmere, and the waterfront on
the north side of Long Beach has been bulkheaded. The facilities
are considered adequate for existing commerce.
    Operations and results during fiscal year. The U. S. seagoing
hopper dredge, Lyman was employed from September 24, 1953, to
October 25, 1953, in dredging to restore the project channel to a
depth of 12 feet. During the fiscal year 56,600 cubic yards, place
measurement, of material were removed at a cost of $64,797 for
maintenance, including the cost of engineering preliminary to
dredging.
    The cost of a condition survey was $863 for maintenance.
    The total cost was $65,660 for maintenance.
    Conditionat end of fiscal year. Work under the existing project
was commenced February 1933, and is about 85 percent complete.
The east jetty, 4,250 feet long, was completed in July 1934. The
project channel was completed in May 1935. When examined in
June 1954, the controlling mean low water depth through the best
available channel from deep water in Atlantic Ocean to deep water
in East Rockaway Inlet was 12 feet for a width varying from 250
to 170 feet. The easy jetty was in good condition. The work re-
maining to be done under the existing project consists of building
a west jetty, if necessary, to protect the channel.
    The total cost of the existing project to June 30, 1954 was
$832,344-$421,369 from regular funds and $82,600 from Public
Works funds, a total of $503,969 for new work and $328,375 from
regular funds for maintenance. In addition, the costs from con-
tributed funds were $100,000 for new work.
100              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                             Cost and financial summary

                                                        Fiscal year ending June 30                                  Total to June
                                                                                                                   30, 1954, includ-
                                                                                                                    ing fiscal years
                                      1950            1951             1952            1953            1954          prior to 19501

New work:
    Appropriated ................................---------------------------------------------------------                 $503, 969
    Cost.---------      -------------------------                                           --- --       ------------       503,969
Maintenance:
    Appropriated -----..--.---...    -                    $454        $96, 505       -$8,     727      $67, 500             330, 284
    Cost..-----------------------------                    454         85,878               1,831       65, 660             328, 375

1 In addition $100,000 for new work was expended from contributed funds.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project...............................-... ............... $806, 000


                                             9. JAMAICA BAY, N. Y.

   Location. This is a bay inside the south shore of Long Island,
the entrance being about 17 miles by water south and east of the
Battery, New York City. (See U. S. Coast and Geodetic Survey
Chart No. 542.)
   Previous projects. Adopted by the acts of June 14, 1880, and
July 13, 1892. For further details, see page 1770 of Annual Report
for 1915, and page 185 of Annual Report for 1938.
   Existing project. This provides for an interior channel ex-
tending from the vicinity of the Marine Parkway Bridge along the
west and north shores of the bay, 18 feet deep at mean low water
and 300 feet wide to Mill Basin, with a swinging basin, 1,000 feet
wide and 1,000 feet long at that point; thence 12 feet deep'and 200
feet wide to Fresh Creek Basin; and interior channel extending
from the same locality along the south shore to Head of Bay, 15
feet deep and 200 feet wide; a channel in Mott Basin, 15 feet
deep and 200 feet wide extending from the channel along the south
shore, 3,000 feet to the junction of the two branches, thence
2,200 feet in the north branch (Inwood Creek) and 3,200 feet
in the south branch; and an entrance channel connecting the two
interior channels with deep water in the Atlantic Ocean, of suit-
able hydraulic dimensions to maintain the present tidal prism in
the bay, but not less than 18 feet deep and 500 feet wide from
opposite Barren Island to Rockaway Point, thence enlarging to
not less than 20 feet deep and 1,000 feet wide to sea, protected by
one riprap jetty. Length of section included in project is 19.7
miles. Mean tidal range, 4.9 feet at Barren Island, and 5.1 feet at
Head of Bay; mean range of spring tides, 5.9 and 6.1 feet, re-
spectively; irregular fluctuations due to wind and barometric
pressure vary from 4 feet below mean water to 4.9 feet above
mean high water.
  The estimate of cost for new work, revised in 1954, excluding
amounts expended on previous projects but including $4,228,439
expended for new work under River and Harbor Act of June 25,
1910, is $5,178,000. The estimate of annual cost of maintenance,
revised in 1950, is $103,500.
The existing project was authorized by the following River and
Harbor Acts:
                RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT                                                             101

     Acts                                Work authorized                                               Documents
June 25,1910     Construction of 1 jetty..------------.......................------------   H. Doc. 1488, 60th Cong., 2d sess.
Mar. 2, 1945    Interior channel along west shore of bay, 18 and 12                        H. Doc. 700, 76th Cong., 3d sess.
                   feet deep; interior channel along south shore, 15
                  feet deep; entrance channel, 20 and 18 feet deep;
                  and 1 riprap jetty, all in lieu of work heretofore
                  authorized. Modified conditions of local coopera-
                  tion.
M4y 17, 1950     Channel 15 feet deep in Mott Basin including its 2                         IH. Doe. 665, 80th Cong., 2d sess.
                  branches.                                                                   (Contains latest published map.)



    Local cooperation. The River and Harbor Act of March 2,
  1945, provides that in lieu of conditions heretofore prescribed,
  local interests shall furnish free of cost to the United States, suit-
  able areas for the disposal of dredged materials for new work and
subsequent maintenance, when and as required, and shall hold and
save the United States free from claims for damages resulting from
the improvement. The city of New York was notified of the con-
ditions of local cooperation in letter dated January 25, 1946. In
letter dated February 7, 1946, the mayor of the city of New York
advised that disposal areas are available and that the necessary
document "holding the United States free from claim for dam-
ages" would be executed.
    The River and Harbor Act of May 17, 1950, provides that local
interests shall:
    a. Furnish free of cost to the United States all lands, easements,
rights-of-way, and suitable areas for disposal of dredged material
during construction of the project and for subsequent maintenance,
as and when required.
    b. Hold and save the United States free from damages due to
the construction works and subsequent maintenance.
    c. Perform all necessary alterations to the existing terminals
and bulkheads, and dredge adequate approaches thereto.
    These conditions have not been fulfilled.
    Terminal facilities. There are 40 terminals with a total avail-
able berthage of 16,493 feet located along the shores of Jamaica
Bay, most of which are concentrated at two general localities; Mill
Basin on the west shore, and from Seaside to and including Head
of Bay on the south shore. Two of the terminals are available
for public wharfage; none has direct rail connections. Nineteen
yacht clubs and 18 boatyards, equipped with marine railways, are
located within the bay. In addition, there are a number of small
landings for pleasure craft. The existing facilities are considered
adequate for existing commerce.
    Operationsand results during fiscal year. Under a contract for
repair of 225 linear feet of the jetty, work was commenced June
10, 1953, and was completed on August 10, 1953. During the
fiscal year, 609.2 tons of stone were placed at a cost of $12,913 for
maintenance.
    The cost of a condition survey, to determine the condition of a
portion of the interior channel was $1,951 for maintenance.
    The total cost of work was $14,864 for maintenance.
    Condition at end of fiscal year. Work under the existing proj-
ect was commenced August 1912 and is about 87 percent complete.
The westerly interior channel from Barren Island to Fresh Creek
102            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Basin and the swinging basin at Mill Basin have been dredged to
project dimensions. No new work dredging of the entrance chan-
nel was done, since depths were greater than those required under
the project. The east jetty, completed August 4, 1933, for a total
length of about 8,400 feet, was in good condition when examined
in August 1953.
  The controlling mean low water depths of the channels included
in this project are as follows:

                           Section                                        Depth         Width                     Date
                                                                          (feet)         (feet)
Entrance channel:
    From Atlantic Ocean to Rockaway Point ...........                           20           1, 000   June 1952.
    Rockaway Point to Barren Island             -...                            18              500       Do.
Interior channel (north and west shores):
    Barren Island to Mill Basin........_------------------                       18            300        Do.
    Swinging Basin ...... -------------------------.            ---              18          1,000        Do.
    Mill Basin to Fresh Creek Basin___--                                         12            200        Do.
Interior channel (south shore):
    Barren Island to Cross Bay Boulevard Br _....--                            1 15      180-200 June-July 1953.
    Cross Bay Boulevard Br. to Long Island R. R. Br_                  _          11      140-200    Do.
    Long Island R. R. Br. to Sommerville Basin....                                6      125-200    Do.
    Sommerville Basin to Mott Basin    ------------                               1      100-200    Do.
  Mott Basin to Head of Bay....                            ._-----------------15              200   Do.
Mott Basin-----................. --------- ..--             -------       (2)              (2)      Do.


  I Except for a shoal of 6 feet across the channel at Neponsit about 1.2 miles above junction.
  _ The controlling depth of existing channels is 9 feet for widths varying from 80 to 200 feet.


   The work remaining to be done under the existing project con-
sists of dredging the southerly interior channel, and the channel in
Mott Basin.
   The total cost of the existing project to June 30, 1954, was
$4,350,857-$4,228,440 for new work and $122,417 for main-
tenance.
                                         Cost and financial summary

                                                  Fiscal year ending June 30                                       Total to June
                                                                                                                  30, 1954, includ-
                                                                                                                   ing fiscal years
                                  1950          1951              1952                1953             1954   .     prior to 19501

New work:
   Appropriated                                                                                          ... .....       $4, 307, 772
   Cost _-                                                                                                                4, 307, 772
Maintenance:
    Appropriated-                 $1,900          -$290               $1,400          $38,014         --$4,734              127,627
    Cost_                          1, 180            430                 914           16, 654          14, 864             125, 378


  I Includes $79,332 for new work and $2,961 for maintenance for previous projects.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project .......... ...... .... .. ...... _ .                                           950, 000

                          10. CONEY ISLAND CHANNEL, N. Y.

  Location. This channel is situated on the east side of Lower
Bay, New York Harbor, about 9 miles south of the Battery,.New
York City. The channel is shown on United States Coast and
Geodetic Survey Chart No. 369, but it is not named.
  Existing project. This provides for a channel 600 feet wide and
20 feet deep at mean low water, extending from deep water
southwest of Nortons Point to deep water off Rockaway Inlet, a
total length of about 1% miles. Mean tidal range, 4.7 feet; mean
            RIVERS AND HARBORS--NEW                          YORK, N. Y., DISTRICT                     103
range of spring tides, 5.6 feet; irregular fluctuations due to wind
and barometric pressure vary from 3.9 feet below mean low
water up to 5.2 feet above mean high water.
   The cost for new work for the completed project was $111,371.
The latest (1950) approved estimate for annual cost of mainte-
nance is $12,000.
   The existing project was adopted by the River and Harbor Act
of March 2, 1907 (H. Doc. 442, 59th Cong., 2d sess.). The latest
published map is in the project document.
   Terminal facilities. There is a municipally owned pier built
out from the Coney Island shore for summer passenger travel;
it does not extend to the channel. It is sufficient for this use.
Commercially the channel is part of the water route between
New York Harbor and Jamaica Bay and points east along the
southern shore of Long Island. (For further details, see Port
Series No. 20, Corps of Engineers.)
   Operationsand results during fiscal year. The cost of a survey
to determine the condition of the channel was $296 for mainte-
nance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1913. When examined in June 1954, the controlling
mean low water depth was 20 feet for a width varying from
340 to 600 feet.
   The total cost of the existing project to June 30, 1954, was
$330,409-$111,371 for new work and $219,038 for maintenance.
                                        Cost and financial summary

                                               Fiscal year ending June 30                     Total to June
                                                                                             30, 1954, includ-
                                                                                             ing fiscal years
                                 1950         1951        1952          1953     1954         prior to 1950

New work:
   Appropriated    .----------                                    _ _                               $111, 371
   Cost-...-                   .......-- --
                           -- --                _            _                  - .                  111, 371
Maintenance:
   Appropriated--      ------------------------------------      ------------         $400           219, 142
   Cost_-------   --      ----------- ----------------- ------------------             296           219, 038



            11. BAY RIDGE AND RED HOOK CHANNELS, N. Y.
  Location. These channels lie along the east shore of the Upper
Bay, New York Harbor, and with Buttermilk Channel, form an
easterly channel along the Brooklyn waterfront from the Nar-
rows to East River. (See U. S. Coast and Geodetic Survey Charts
Nos. 369 and 541.)
  Previous projects. Adopted by River and Harbor Acts of
March 3, 1881, August 11, 1888, September 19, 1890, August 18,
1894, and June 3, 1896. For further details, see page 1768 of
Annual Report for 1915, and page 195 of the Annual Report
for 1938.
  Existing project. This provides for a channel 1,200 feet wide
and 40 feet deep at mean low water from the Narrows to Bay
Ridge Avenue, Brooklyn, thence 1,750 feet wide to the junction
of Bay Ridge and Red Hook Channels, thence 1,200 feet wide
through Red Hook Channel to the junction with Buttermilk Chan-
nel and a channel of the same depth extending into Gowanus Bay
 104               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

from the junction of Bay Ridge Channel with Red Hook Channel,
narrowing uniformly in width to about 500 feet at Twenty-eighth
Street, Brooklyn. Length of section included in the project, 4
miles. Mean tidal range, 4.7 feet; mean range of spring tides,
5.6 feet; irregular fluctuations due to wind and barometric
pressure vary from 3.9 feet below mean low water up to 5.2 feet
above mean high water.
    The cost for new work, for the completed project, was $4,277,-
196, exclusive of amounts expended on previous projects. The
latest (1950) approved estimate for annual cost of maintenance
is $230,000.
    The existing project was authorized by the following River
and Harbor Acts:
       Acts                               Work authorized                                       Documents

Mar. 3, 1899       Channel 40 feet deep and 1,200 feet wide.....-----------        H. Doc. 337, 54th Cong., 2d sess.
                                                                                       (Annual Report, 1897, p.:1177.)
Mar.     2,1907     Dredging to obtain, first, a depth of 35 feet, subse-
                      quently increasing depth to 40 feet for full width.
July     3, 1930    Widening of Bay Ridge Channel to 1,750 feet-.. __-_-            Rivers and Harbors Committee
                                                                                      Doc. 44, 71st Cong., 2d sess.
                                                                                       (Contains latest published map.)


   Terminal facilities. There are 53 terminals with a total avail-
able berthage of 72,819 feet and 8,232 feet of bulkheads and
wharves available for dockage. Twenty-four of the terminals
have mechanical handling devices and 20 have railroad connec-
tions. In addition, there are 6 railroad float bridges and 2 idle
ferry slips. Of the terminals, 1 is state-owned, 2 are Govern-
ment-owned, 13 are owned by the city of New York, and 1 is open
to public use. The terminal facilities are considered adequate
for existing commerce.
   Operations and results during fiscal year. The U. S. seagoing
hopper dredge Essayons was employed intermittently from Feb-
ruary 23, 1954, to May 19, 1954, to restore sections of Bay Ridge
and Red Hook Channels to partial project depth of 35 feet.
During the fiscal year 1,265,400 cubic yards, place measurement,
of material were removed at a cost of $294,327 for maintenance,
including the cost of surveys and engineering preliminary to
dredging.
   The cost of miscellaneous inspections and reports was $2,120
for maintenance.
   The total cost of work was $296,447 for maintenance.
   Condition at end of fiscal year. Work under the existing proj-
ect was commenced March 1901 and completed June 1940.
   The controlling mean low water depths of the channels in-
cluded in the project are as follows:
                               Section                                   Depth     Width            Date survey
                                                                         (feet)    (feet)
In Bay Ridge Channel from Narrows to Bay Ridge Ave.,                         37   1, 200-700   January-February 1954.
  Brooklyn.
From Bay Ridge Ave. to 45th St. (Pier 4)....        ----------------          35 1, 200-750    January-June 1954.
                                                                                      1, 200
Branch in Gowanus Bay         --...........................          .       30    600-230     March 1954.
Red Hook Channel- ..----.................                 ........           37 1, 100-500     March 1952.
                RIVERS AND HARBORS--NEW YORK, N. Y., DISTRICT                                            105
  The total cost of the existing project to June 30, 1954, was
$8,845,219-$4,212,637 regular funds and $64,560 Public Works
funds, a total of $4,277,197 for new work and $4,568,022 for
maintenance.
                                      Cost and financial summary

                                             Fiscal year ending June 30                        Total to June
                                                                                              30, 1954, includ-
                                                                           1ing                   fiscal years
                               1950         1951        1952        1953           1954        prior to 1950'

New work:
   Appropriated                                                     ---------                      $5, 523, 297
                                                                                                   $---------
   Cost--------          ----------------------------------------------------------                  5, 523, 297
Maintenance:
    Appropriated .......        $8, 000   -$2, 039     $184, 055   $122, 200      $291, 098          4,571, 998
    Cost....----------......     5,961                  055
                                          ..--------.184,              875
                                                                    112,              447
                                                                                   296,              4, 568, 022

  1Includes $1,246,100 for new work for previous projects.


                         12. GOWANUS CREEK CHANNEL, N. Y.
   Location. Gowanus Creek is a small tidal inlet extending about
11/2 miles from the north end of Bay Ridge Channel. The channel
is shown on United States Coast and Geodetic Survey Chart No.
369;-the entrance is shown on Jhart No. 541.
   Previous projects. Adopted by the River and Harbor Acts of
March 3, 1881 (under title of Gowanus Bay), August 11, 1888,
September 19, 1890, and June 3, 1896. For further details, see
Annual Report for 1915, page 1769, and Annual Report for 1938,
page 198.
   Existing project. This provides for a channel 30 feet deep at
mean low water, 500 to 200 feet wide, from 28th Street to Percival
Street, thence with the same depth for a distance of about 500
feet to the vicinity of Sigourney Street and narrowing to a width
of 100 feet, thence 18 feet deep and suitably widened to provide,
a width of 200 to 100 feet from Percival Street to the Hamilton
Avenue Bridge, and a branch channel 30 feet deep and 150 feet
wide in the lower 1,000 feet of Henry Street Basin. Length of
section included in the project, about 0.8 mile. Mean tidal range,
4.7 feet; mean range of spring tides, 5.6 feet; irregular fluctua-
tions due to wind and barometric pressure vary from 3.9 feet
below mean low water up to 5.2 feet above mean high water.
   The cost for new work for the completed project is $271,831,
exclusive of amounts expended under previous projects. The
latest (1950) approved estimate for annual cost of maintenance
is $7,500.
   The existing project was authorized by the following River
and Harbor Acts:

    Acts                         Work authorized                                   Documents
Mar. 3,1881     Dredging 18-foot channel   ----------------------- Annual Report 1896, p. 155.
July 16. 1952   Dredging 30-foot channel and branch channel-....... H. Doc. 318, 82d Cong., 2d sess.
                                                                          (Contains latest published map.)


  Local cooperation. The River and Harbor Act of July 16, 1952,
provides that local interests shall:
  a. Provide without cost to the United States all lands, ease-
  106                   REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

ments, and rights-of-way for the construction and maintenance of
the project, when and as required.
    b. Deepen the approaches and berths at the ship terminals in
order to secure the full advantages of the deeper channels.
    c. Hold and save the United States free from damages due to the
construction works; and also subject to the condition that no dredg-
ing shall be done by the Federal Government within 50 feet of any
wharf or structure unless a waiver of damage is signed by all
parties having an interest in such wharf or structure or by the port
authority or other financially competent agency. Assurances of
compliance with the above conditions were accepted by the Secre-
tary of the Army on February 18, 1954.
    Terminal facilities. There are 84 piers and bulkheads along this
waterway and Gowanus Canal, 3 of which, including a large grain
elevator, are owned and operated by the Port of New York Author-
ity as a grain terminal; 9 are owned by the city of New York; 15
are owned and operated by 2 shipyards; and the remainder are
privately owned and operated. The total available berthage is
about 44,529 feet. The terminals occupy practically the whole of
the waterfront. Ten have rail connections, and 38 are equipped
with mechanical handling devices.
    Operations and results during fiscal year. Under a contract
for dredging to a depth of 30 feet from the entrance to Sigourney
Street and also in a section 150 feet wide in the lower 1,000 feet
of Henry Street Basin, work was commenced March 3, 1954, and
completed April 20, 1954. During this period 179,831 cubic yards,
place measurement, of material were removed at a cost of $201,831
including the cost of engineering and design, for new work.
    Condition at end of fiscal year. Work under the existing proj-
ect was commenced July 1881 and completed April 1954. When
examined in March and April 1954, the controlling mean low water
depth was 30 feet for widths varying from 500 to 200 feet from
the entrance to Percival Street, thence 30 feet for widths varying
from 200 to 100 feet to Sigourney Street. The next reach from
Sigourney Street to the Hamilton Avenue Bridge was last examined
in June 1952, and found to be 18 feet deep for a width varying
from 200 to 50 feet except at its extreme northern corner near
the bridge where it shoals to 8 feet. The controlling depth in the
Henry Street Basin was found in April 1954, to be 30 feet for a
width of 150 feet.
   The total cost of the existing project to June 30, 1954, was
$345,462-$271,831 for new work and $73,631 for maintenance.
                                                            Cost and financial summary

                                                                         Fiscal year ending June 30                             Total to June
                                                                                                                               30, 1954, includ-
                                                                                                 I                              ing fiscal year
                                                  1950                1951            1952            1953           1954        prior to 19501

New work:
   Appropriated                    -       ---------             - ------------       ---                          $201, 831           $346, 831
     Cost           -   --   ---                                          ---                                       201, 831            346, 831
Maintenance:

     Appropriated_                                     $1, 763         $1,292               $455 ---------- --------------               73, 631
     Cost      --                      .                1, 763          1,292                455 ----------   --------------       -     73,631

   1Includes $75,000 for new work for previous                            projects.
           RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT            107
                       13. EAST RIVER, N. Y.
   Location. This is a tidal strait about 16 miles long and 600 to
4,000 feet wide, connecting Hudson River and the Upper Bay at
the Battery, New York City, with Long Island Sound at Throgs
Neck, New York City, and separating Long Island from Manhat-
tan Island and the mainland. (See U. S. Coast and Geodetic Sur-
vey Charts Nos. 223, 226, and 745.)
   Previous projects. Adopted by River and Harbor Acts of Au-
gust 30, 1852, July 25, 1868, March 3, 1899, and June 25, 1910.
For further details, see page 210, Annual Report for 1932.
   Existing project. This provides for channels of the following
dimensions (depths refer to mean low water) : From deep water
in the Upper New York Bay to Wallabout Channel, 40 feet deep
and 1,000 feet wide; from Wallabout Channel to Throgs Neck, 35
feet deep, with widths varying from about 550 to 1,000 feet, ac-
cording to locality; east of Welfare (Blackwells) Island up to
English Place (43d Dr.), Long Island City, 30 feet deep and vary-
ing in width from 500 to 900 feet, with widening in the approach
from the main channel; between South Brother and Berrian Is-
lands, 20 feet deep and 300 feet wide, with widening in the ap-
proach from the main channel; for the removal of Coenties Reef to
a depth of 40 feet, also the removal of the following rocks and
reefs lying outside of the limiting lines of the main channel to give
access to wharves: Along the Brooklyn shore, Brooklyn Bridge to
Manhattan Bridge (Fulton Ferry Reef), to a depth of 25 feet; Jay
Street Reef, 25 feet; Corlears Reef, 35 feet; Shell Reef, 25 feet;
Horns Hook, 40 feet; Rhinelander Reef, 26 feet; and reef off Oak
Point, 30 feet; and for the construction of a dike in Pot Cove in
Hell Gate. The length of the section included in the improvement
is about 16.5 miles. The mean range of tide varies according to
locality from 4 feet at North Third Street, Brooklyn, and 4.4 feet
at the Battery to 4.9 feet at Hallets Point, 6.3 feet at Port Morris,
and 7.1 feet at the eastern entrance at Throgs Neck; mean range
of spring tides 4.8, 5.3, 5.9, 7.6, and 8.5 feet, respectively; irregu-
lar fluctuations due to wind and barometric pressure vary accord-
ing to locality from 3.8 feet below mean low water at the Battery,
2.4 feet at North Third Street, Brooklyn, and 3.8 feet at Throgs
Neck up to about 5.2 feet above mean high water at the Battery
and 8.4 feet above mean high water at Throgs Neck; extreme
fluctuations do not seriously affect navigation.
   The cost for new work for the completed project, exclusive of
amounts expended on previous projects, was $23,849,719. The
latest (1950) approved estimate for annual cost of maintenance is
$25,000.
The existing project was authorized by the following River and
Harbor Acts:
 108                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

      Acts                                 Work authorized                                        Documents
                 I                     _


Mar. 3, 19151  Removal of Coenties Reef to 35 feet, conditioned                      H. Doc. 188, 63d Cong., 1st sess.
                 upon local interests increasing depth to 40 feet.
July 27,1916   Channel across Diamond Reef 35 feet deep and 1,000                         Do.
                 feet wide.
Aug. 8,1917 Channel east of Blackwells Island to 20 feet; channel                         Do.
                 between South Brother and Berrian Islands, to 20
                 feet; channel between North and South Brother
                 Islands to 26 feet.
    Do.......    Channel 40 feet deep through East River and Hell                    H. Doc. 140, 65th Cong., 1st sess.
                 Gate.
July 18,1918 Secure a depth of 40 feet in channel through East                       Specified in act.
                 River and Hell Gate as soon as practicable.
Sept. 22, 1922 Depth limited to 35 feet in the through channel be-                   Rivers and Harbors Committee
                 between Wallabout Channel and Throgs Neck.                            Doc. 3, 67th Cong., 2d sess.,
                 Channel east of Blackwells Island, 30 feet to Eng-                    (Contains latest published map.)
                lish Place and eliminated 20-foot channel north of
                 English Place. Eliminated channel between North
                 and South Brother Islands except as authorized
                 prior to existing project. Removal of certain rocks
                 and reefs and construction of dike in Pot Cove,
                 Hell Gate.

  1Pub. Res. 67, 63d Cong., 3d sess.

  Local cooperation. Fully complied with.
  Terminal facilities. There are 214 terminals with a total avail-
able berthage of 121,150 feet, along both shores of the East River
from the Battery to Clason Point. In addition, there are 10 ferry
slips and 20 carfloat bridges. Of the terminals, 99 are publicly
owned, 84 are equipped with mechanical-handling devices, and 43
have railroad connections. The facilities are considered adequate
for present needs.
   Operationsand results during fiscal year. The cost of a survey
to determine the condition of the channel in the vicinity of Cor-
lears Reef was $1,325 for maintenance.
   Condition at end of fiscal year. Work under the existing proj-
ect was commenced June 1916 and was substantially completed
September 1935.
    The controlling mean low water depths of the various channels,
as determined by intermittent surveys made during the period
1910 to 1954, are as follows:

                                             Section                                              Depth         Width
                                                                                                  (feet)        (feet)
From Upper Bay to Wallabout Chamel. _______.........               -.                 .---                 40   950-1, 000
Corlears Reef         -----------------..............................----------------                      29
From Wallabout Channel through west channel at Welfare (Blackwells) Island                                 35   550-1, 000
and Hell Gate to Throgs Neck at Long Island Sound.
East Channel at Welfare (Blackwells) Island:
  From Newtown Creek to English Place (43d Dr.) Long Island City
  From English Place to deep water off north end of Welfare Island ..-.......
                                                                                   ---------             1 30
                                                                                                          24
Between South Brother and Berrian Islands_...................__._____                      ____           20          300
Coenties Reef...........----     -------------------------------------                                    40
Fulton Ferry Reef----                 ------------------------....                       -----            25
Jay Street Reef-....     .. .. -----------                 -------------                                  20
Shell Reef........              ----------------------------                                              25
Horns Hook Reef .                                                              .
                                 .----------.------------------.----------------------                    40
Rhinelander Reef--                     -----------------       ---------------                            26
Reef off Oak Point -           .-------.-------.                     .-------------------
                                                                             ------------                 30

  1Except for scattered shoals in the vicinity of Belmont Island with least depth of 25.5 feet.
  The removal of a small shoal area along the east side of the 35-
foot channel between Grand Street and North Third Street, Brook-
            RIVERS AND HARBORS--NEW YORK, N. Y., DISTRICT                                             109
lyn, the construction of the dike at Pot Cove in Hell Gate, a part
of the widening near the pierhead line in Jay Street Reef, and
North Third Street, Brooklyn, were omitted as unnecessary, the
work completed being considered sufficient for the needs of navi-
gation.
   The total cost of the existing project to June 30, 1954, was
$24,746,965-$1,743,265 Public Works funds and $22,106,454
regular funds, a total of $23,849,719 for new work and $897,246
for maintenance.
                                     Cost and financial summary

                                             Fiscal year ending June 30                      Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                              1950          1951        1952        1953         1954        prior to 19501
New work:
   Appropriated......--------        -----------------------------------------------            $30, 037, 413
                    --   --  ---- ---------------- ----------------------
   Cost..............-----------------                                                           30, 037, 413
Maintenance:
   Appropriated-.......        $5, 900       $1, 229    $14, 000    $55, 180                         934, 911
   Cost-----------------        5, 900        1, 229      8, 580     59, 274      $1, 325            934,910

  1Includes $6,187,694 for new work and $37,664 for maintenance for previous projects.

                                14. HARLEM RIVER, N. Y.
   Location. Harlem River and Spuyten Duyvil Creek, both in-
cluded in the project for the improvement of Harlem River, are
two connecting tidal waterways, of a joint length of about 8 miles,
lying wholly within the limits of Greater New York and separating
Manhattan Island from the mainland.         (See U. S. Coast and
Geodetic Survey Chart No. 274.)
   Previous projects. Adopted by the River and Harbor Act of
June 23, 1874. For further details, see Annual Report for 1915,
page 1762, and Annual Report for 1938, page 210.
   Existing project. This provides for a continuous channel 15
feet deep at mean low water and 400 feet wide from East River to
Hudson River, except in the vicinity of Washington IBridge, where
the adopted width is 354 feet, and at the rock cut through Dyck-
mans Meadow, where it is 350 feet and the depth is 18 feet. It
also provides for straightening the channel at Johnson Iron Works
by making a cut 15 feet deep and 400 feet wide. The length of
channel included in the project is about 8 miles. The main tidal
range varies, according to locality, from 4.9 feet at Willis Avenue
Bridge to 3.8 feet at Spuyten Duyvil Bridge, range of spring tides,
5.9 and 4.5 feet, respectively. Irregular fluctuations due to wind
and barometric pressure vary from 3.8 feet below mean low water
up to 4.7 feet above mean high water at Willis Avenue Bridge and
from 3.7 feet below mean low water up to 4.9 feet above mean
high water at Spuyten Duyvil Bridge.
   The cost for new work, for the completed project, was $3,595,-
119, exclusive of amounts expended on previous projects. The lat-
est (1950) approved estimate for annual cost of maintenance is
$25,000.
The existing project was authorized by the following River and
Harbor Acts:
110               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


       Acts                        Work authorized                                   Documents
June 18, 1878     Channel 15 feet deep and 350 feet wide_         -       H. Ex. Doc. No. 75, Pt. 9, 43d
                                                                           Cong., 2d sess. (Annual Re-
                                                                           port, 1875, pt. 2, p. 224.)
                  Chief of Engineers authorized widening to 400 feet      Annual Report, 1886, p. 674.
                   throughout except at Dyckmans Cut, where width
                   was kept at 350 feet and depth increased to 18 feet.
                  Chief of Engineers in 1893 reduced width of channel     Annual Report, 1912, p. 198.
                    in vicinity of Washington Bridge to 354 feet.
Mar.    4, 1913   Straightening channel at Johnson Iron Works             H. Doc. No. 557, 62d Cong., 2d sess.
                                                                           (Contains latest published
                                                                           maps.)



    Local cooperation. Fully complied with.
    Terminal facilities. The length of the waterfront along both
shores of the Harlem River is about 16 miles, of which 4 miles are
unavailable for commercial use. There are 52 terminals with a
total available berthage of 17,865 feet. Thirty of the terminals
are owned by the city of New York. Twenty-four of the terminals
are equipped with mechanical handling devices and 13 have rail-
road connections. In addition, there are 5 railroad float bridges.
The terminal facilities are considered adequate for present needs.
    Operation and results during fiscal year. The cost of a survey
to determine the condition of the channel was $978 for mainte-
nance.
   Condition at end of fiscal year. Work under the existing proj-
ect was commenced January 1888, and was substantially com-
pleted May 1938. Remaining widening to be done in the section
above High Bridge is prohibited by the proximity of bulkheads to
the channel line. The present width is considered adequate for
navigation. No further improvement is contemplated under the
project. A channel 15 feet deep at mean low water and 400 feet
wide has been excavated from East River to High Bridge, thence
15 feet deep and 350 to 400 feet wide to the Hudson River. The
rock cut through Dyckmans Meadow was completed to 18-foot
depth and 350-foot width in 1896. The straightening of the chan-
nel at Johnson Iron Works was completed to 15-foot depth and 400-
foot width in 1938. The controlling depth from East River to
Hudson River, as shown by examination made in December 1949
and June 1954 was 13 feet at mean low water through a navigable
channel varying from 150 to 400 feet in width, except for a shoal
in the vicinity of Little Hell Gate having a minimum depth of 14
feet and scattered shoals between Sherman Creek and Broadway
Bridge having a minimum depth of 10 feet.
   The total cost of the existing project to June 30, 1954, was
$3,867,676-$3,595,119 for new work and $272,557 for mainte-
nance.
            RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT                                                   111
                                     Cost and financial summary

                                            Fiscal year ending June 30                           Total to June
                                                                                                30, 1954, includ-
                                                                                                ing fiscal years
                              1950         1951           1952      1953             1954         prior to 19501

New work:
   Appropriated  _ --        _                                                   _                    $3, 616, 119
   C ost....       - - - - -.                             ... ...          ...--. .. . .. .            3,616,119
Maintenance:
   Appropriated_        $4, 800             $2, 316                      $942         $2, 000            273, 579
   Cost -------- -       4, 800                 987         $387                          978            272, 557

1 Includes $21,000 for new work for previous projects.


          15. HUDSON RIVER CHANNEL,                              NEW YORK HARBOR
   Location. Hudson River empties into the Upper Bay of New
York Harbor at the Battery, New York City. The section included
under this title extends from deep water in upper New York Bay to
just north of Harlem River (Spuyten Duyvil Creek), a distance of
about 14.5 miles. (See U. S. Coast and Geodetic Survey Charts
Nos. 274, 745, and 746.)
   Previous projects. Adopted by River and Harbor Acts of
March 3, 1875, June 6, 1900, and March 3, 1905. For further de-
tails, see Annual Report for 1915, page 1765, and Annual Report
for 1938, page 213.
   Existing project. This provides for a channel 48 feet deep and
2,000 feet wide, suitably widened at the bends, from West 59th
Street, Manhattan, to West 40th Street, thence 45 feet deep of the
same width to deep water in Upper Bay; for a channel 40 feet
deep for the full width of the river extending from the north line
of 59th Street to the south side of Little Basin, and thence a chan-
nel of the same depth to deep water in the Upper New York Bay
off Ellis Island, substantially as shown on maps in House Docu-
ment 309, 72d Congress, 1st session, subject to the provision that
no dredging shall be done under the project within 50 feet of the
pierhead lines; a channel 750 feet wide and 30 feet deep along the
Weehawken-Edgewater water front; the removal of a shoal on the
New York side between West 59th and West 61st Streets to a depth
of 40 feet; and the removal of an obstruction north of the mouth
of Spuyten Duyvil Creek to the depth of the surrounding river
bottom. The length of channel included in the project is about
11 miles. The plane of reference is mean low water. Mean tidal
range at the Battery, 4.4 feet, and at West 129th Street, 4.1; mean
range of spring tides, 5.3 feet and 4.9 feet, respectively; irregular
fluctuations due to wind and barometric pressure vary from 3.8
feet below mean low water at the Battery up to 5.2 feet above
112                   REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

mean high water and at West 129th Street from 3.6 feet below
mean low water up to 5.3 feet above mean high water.
  The cost for new work for the completed project was $6,702,240,
exclusive of the amounts expended on previous projects. The latest
(1950) approved estimate for annual cost of maintenance is $390,-
000.
  The existing project was authorized by the following River and
Harbor Acts:
       Acts                            Work authorized                                Documents
                  i

Mar. 4,1913           Channel 30 feet deep from Ellis Island to Newark St., H. Doc. 719, 62d Cong., 2d sess.
                       40 feet deep through the shoal from Newark St. to
                        Castle Point and channel 26 feet deep and 550 feet
                        wide along Weehawken-Edgewater waterfront.
                        Removal of shoal east side of river between West
                        19th and West 32d Sts.; removal of rock near the
                        Battery to 40 feet, and removal of obstruction near
                        Spuyten Duyvil Creek.
Mar.     4,1915       Additional dredging through shoal from Newark St. Annual Report, 1914, pp. 234-235.
                        to Castle Point.
Aug.     8,1917       Removal of shoal between West 32d and West 61st H. Doc. 1697, 64th Cong., 2d sess.
                        Sts. to 40 feet and widening the 40-foot channel be-
                       tween the Battery and Canal St. to 2,000 feet.
Mar.     3,1925       Channel 30 feet deep and 750 feet wide along Wee- H. Doec. 313, 68th Cong., 1st sess.
                       hawken-Edgewater waterfront.
Jan.    21,1927       Modification of conditions of local cooperation affect-
                       ing channel along Weehawken-Edgewater water-
                       front.
July    3,1930        Channel 40 feet deep between pierhead lines from 20th H. D)oc. 450, 70th Cong., 2d sess.'
                       St., Manhattan, to a point 1,300 feet below Newark
                       St., Hoboken, thence 2,800 feet wide to deep water
                       off Ellis Island. Channel 30 feet deep between 40-
                       foot channel and channel along Jersey City water-
                       front.
Aug. 30. 19352        Widening the 40-foot channel to full width of river H. D)oc. 309, 72d Cong., 1st sess.'
                       from north line of 59th St. to south side of Little
                       Basin, thence a channel of same depth to deep water
                       off Ellis Island.
   Do         .. ..   Waiver of all conditions of local cooperation affecting Rivers and Harbors Committee
                       the channel along the Weehawken-Edgewater                Doc. 49, 72d Cong., 2d sess.
                       waterfront.
Aug. 26, 1937         Channel 45 and 48 feet deep and 2,000 feet wide....... Senate committee 1     print, 75th
                                                                              Cong., 1st sess.

I Contain latest published maps.
2 Also Public Works Administration Sept. 6, 1933, and Apr. 27, 1935.

   Terminal facilities. The length of waterfront included in the
project for improvement, measured along both shores of the
river, is 32 miles; of this length, 7 miles of the Manhattan water-
front and 10 miles of the New Jersey waterfront have been de-
veloped for commercial use. Along the Manhattan waterfront,
there are 101 terminals with a total available berthage of 126,826
feet, 19 ferry slips, and 8 car-float bridges. Along the Jersey
waterfront there are 147 terminals having a total available
berthage of 166,282 feet, and 19 ferry slips, 31 car-float bridges,
and 2 large shipyards with 6 floating drydocks. Of the terminals,
109 are publicly owned, 159 are equipped with mechanical handling
devices, and 135 have railroad connections. The facilities are ade-
quate for present requirements.
   Operations and results during fiscal year. The U. S. seagoing
hopper dredge Essayons was employed intermittently from August
24, 1953, to January 4, 1954, in dredging to restore the channel
along the Weehawken-Edgewater waterfront to a depth of 30
feet. During the fiscal year, 1,081,500 cubic yards, place measure-
                   RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT                                                            113
ment, of material were removed at a cost of $196,208 including en-
gineering preliminary to dredging for maintenance.
   The U. S. seagoing hopper dredge Essayons was also employed
intermittently from January 5, 1954, to May 20, 1954, in dredging
to restore the 48 foot project channel to its authorized dimensions.
During the fiscal year, 427,600 cubic yards, place measurement, of
material were removed at a cost of $128,704 including engineering
preliminary to dredging, for maintenance.
   The cost of a condition survey, studies, and miscellaneous in-
spections and reports was $21,147 for maintenance.
   The total cost of work was $346,059 for maintenance.
   Condition at end of fiscal year. Work under the existing proj-
ect was commenced April 1913 and was completed in September
1952. The work of widening and deepening Weehawken-Edge-
water Channel to project dimensions was completed in August
1937. The work of widening the 40-foot channel for the full
width of the river from Ellis Island to West 59th Street, Manhat-
tan, was completed in March 1939. The work of widening the 48-
foot project to full project width of 2,000 feet from West 40th
Street to West 59th Street was completed in November 1950.
Deepening of the 45-foot channel for a width of 2,000 feet from
Upper Bay to West 40th Street was completed to project dimen-
sions in September 1952.
   The controlling mean low water depths of the sections included
in the project are as follows:


                                   Section                            Depth
                                                                      (feet)       Width
                                                                                   (feet)                      Date

40-foot channel:
     From Ellis Island to W. 59th St--....----------------                  40   3,100-2, 200     April-June 1953.
45-foot channel:
    From Ellis Island to W. 40th St..-----------------                      45   2, 000-1, 700        Do.
48-foot channel:
    From W. 40th St. to West 59th St----------------                        48   1, 800-1, 500    June 1954.
Weehawken-Edgewater channel:
    From W. 59th St. to opposite Valvoline oil dock..                       30         250-750    August 1951-June 1954.
    From opposite Valvoline oil dock to W. 156 St.,                         27         300-750    November      1952-June
      Manhattan.                                                                                   1954.


  The total cost of the existing project to June 30, 1954, was
$11,374,058-$668,820 Public Works funds, and $6,033,420 regular
funds-a total of $6,702,240 for new work and $4,671,818 for
maintenance.
                                                    Cost and financial summary

                                                          Fiscal year ending June 30                           Total to June
                                                                                                               30, 1954, includ-
                                                                                                               ing fiscal years
                                             1950        1951        1952          1953           1954          prior to 1950'
New work:
    Appropriated ...--------               $400, 000    $300, 000   $250, 000    -$75, 383 --                         $6, 771, 870
    Cost__ __________ __
Maintenance:
                                            336, 453     362, 551    171, 516        4, 097   ------------             6, 771, 870
    Appropriated--------                   340, 000      158, 677    290, 000      225, 991      $339, 198            4, 676, 763
    Cost--.......------.......--------..   320, 599      174, 286     84, 364      424, 794       346, 059            4, 671, 817

  1Includes $69,629 for new work for previous project.
114             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                              16. RONDOUT HARBOR, N. Y.
  Location. This harbor comprises the tidal mouth, about 1.8
miles in length, of Rondout Creek, whose source is about 18 miles
west of Rondout. The creek empties into the Hudson River from
the west, about 89 miles north of the Battery, New York City, and
55 miles south of Albany. (See U. S. Coast and Geodetic Survey
Chart No. 283.)
  Existing project. This provides for a channel 100 feet wide,
widening at the bends, and 14 feet deep from deep water in Hudson
River to the highway bridge, 1.3 miles above the mouth, thence
12 feet deep to the west end of Island dock, 1.8 miles above the
mouth, two parallel dikes 350 feet apart, to maintain the channel,
and for a branch dike to extend upstream from the outer end of
the north dike to protect that dike from running ice in Hudson
River.
  Mean tidal range, 3.7 feet; mean range of spring tides, 4.2 feet;
extreme range, 8.2 feet; irregular fluctuations due to freshets vary
from 2 feet below mean low water up to 2.5 feet above mean high
water.
  The cost for new work for the completed project was $123,109.
The latest (1950) approved estimate for annual cost of main-
tenance is $11,500.
  The existing project was authorized by the following River and
Harbor Acts:

    Acts                         Work authorized                                  Documents

June 10,1872    Parallel dikes, branch dike, and entrance channel,     S. Ex. Doc. 35, 42d Cong., 2d sess.
                  14 feet deep.                                          Annual Report, 1872, p. 810.
Aug. 30, 1935   Extension of the 14-foot channel and for the 12-foot   Rivers and Harbors Committee
                 channel.                                                Doc. 17, 73d Cong., 2d sess. (Con-
                                                                         tains latest published map.)




   Local cooperation. Fully complied with.
   Terminal facilities. There are 17 timber wharves with a total
available dockage of 12,132 feet located along the waterway. Four
of the terminals are equipped with transfer facilities; all are
privately owned. The existing terminals appear to be adequate
for present needs of commerce. (For latest full description of
terminal facilities, see Port and Terminal Facilities at the Ports
on the Upper Hudson River, 1941, Corps of Engineers.)
   Operations and results during fiscal year. The cost of a survey
to determine the condition of the channel was $2,619 for main-
tenance.
   Condition at end of fiscal year. Work under the existing proj-
ect was commenced April 1873 and substantially completed
November 1938. Part of the diking originally proposed was not
built because it was deemed of doubtful usefulness. Two paral-
lel dikes of an aggregate length of about 5,000 feet, generally 350
feet apart, with a now obsolete spur from the old lighthouse
south of the south dike, have been built across the bar at the
mouth of the creek. A branch dike about 1,000 feet long, extend-
ing northerly from the outer end of the north dike, was also
               RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT                                                           115
constructed. The project channel was completed in 1938. When
examined in July 1953, the controlling depth at mean low water,
from the Hudson River to the highway bridge, was 14 feet for a
width varying from 60 to 100 feet, thence 10 feet for a width
varying from 75 to 100 feet to the head of the project.
   The total cost of the existing project to June 30, 1954, was
$335,262-$123,109 for new work and $212,153 for maintenance.
                                         Cost and financial summary

                                                   Fiscal year ending June 30                                Total to June
                                                                                                            30, 1954, includ-

                                  1950           1951            1952         1953   J         1954
                                                                                                            ing fiscal years
                                                                                                             prior to 1950

New work:
   Appropriated                  -     -------------              ------- ----------     ------------               $123, 109
   Cost-...--------- - ---------------                                  -----------  -- -------                      123,109
Maintenance:
   Appropriated --------------                   -   -$800                     $6, 120         -                     213, 112
    Cost              ..--------------------------------------          520     2,822              $2,619            212,153


                                    17. HUDSON RIVER, N. Y.
   Location. . This river has its source in the Adirondack Moun-
tains, about 250 miles in a direct line and 315 miles along its
course from the Battery, New York City, and flows in a generally
southerly direction into New York Bay. The section under im-
provement extends from New York City to Waterford, a distance
of about 156 miles. (See U. S. Coast and Geodetic Survey Charts
Nos. 282 to 284, inclusive.)
   Previous projects. The original project for improvement by
the United States was adopted by River and Harbor Act of June
30, 1834, and modified in 1852 and 1866.
   A second project was adopted by River and Harbor Act of July
13, 1892, and modified in 1899. For further details, see page 1764,
Annual Report for 1915, and page 226, Annual Report for 1938.
   Existing project. This provides for a channel 27 feet deep at
mean low water and 300 feet wide up to Hudson; thence of same
depth and 400 feet wide through rock cuts and 300 feet wide
elsewhere, from Hudson to the site of the former Albany-Green-
bush Bridge at Albany; thence 14 feet deep at lowest low water
and generally 400 feet wide to the Federal lock at Troy; and
thence of same depth and 200 feet wide to the southern limit of
the State barge canal at Waterford; with widening at bends and
in front of the cities of Troy and Albany to form harbors 12 feet
deep at lowest low water; and removal of State dam at Troy and
the construction of a lock and dam about 21/2 miles below Water-
ford.
   The channel is to be formed by dredging and rock excavation,
and to be maintained by dredging and by constructing new, and
raising and repairing old, longitudinal dikes, built partly under
previous projects and partly by the State of New York. The
mean range of pool elevation above the Federal dam at Troy, in
seasons of moderate rains, is about 2.2 feet, as determined in
1934. The mean tidal range is about 4.7 feet at the Federal dam
at Troy and about 4.6 feet at Albany, extreme range due to
freshets is 33.4 and 25.7, feet, respectively.
116                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   The normal pool level above the Federal dam from Troy to
Waterford is 14.33 feet above mean sea level at Sandy Hook, N. J.
In the tidal section of the river below the dam the assumed lowest
low water plane from Troy to Albany is 3 feet below mean sea
level at Sandy Hook, N. J.
   The following table contains information concerning the vari-
ous features of the lock and dam included in the existing project:
Location:
    Below Waterford...................................                                              miles
                                                                   ........-----------------------------------    2 .2
    Above Battery, New York City                      ---------.....--------..---------........     do----- 153.8
Locks:
    Clear width........................................                                             feet
                                                                   ........------------------------------------  44.44
    Greatest length available for full width...--------------....----.............                  do          492 .5
    Lift at lowest stages.........................                 ....---------------------------- do           17.3
    Depth on miter sills:
         Upper (at normal pool level) .....                                                         do ........  16 .3
         Lower (at lowest low water) -.................                                             do-----      13.0
Character of foundation: Rock.
Kind of dam: Fixed.
Type of construction: Concrete.
Completed: 1917.
Cost: $1,463,014.

   The estimated cost for new work, revised in 1954, is $17,680,-
000, exclusive of amounts expended on previous projects. The
latest (1950) approved estimate for annual cost of maintenance
is $381,300, including $65,300 for operation and care of the lock
and dam.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                              Work authorized                                          Documents'
June 25, 1910       Channel 12 feet deep from Hudson to Waterford, re-                 H. Doc. 719, 61st Cong., 2d sess.
                     moval of State lock and dam at Troy and construc-
                     tion of a new lock and dam.
Mar. 3,1925         Channel 27 feet deep from Hudson to Albany........                 H. Doc. 350, 68th Cong., 1st sess.
July     3, 1930    Channel 27 feet deep below Hudson--------------.................   H. Doec. 210, 70th Cong., 1st sess.
        (2)         Operation and care of lock and dam at Troy were in-
                s    cluded in project July 1, 1935.
Aug. 30, 1935       Relocation of the 12-foot channel between Troy and                 S. Doc. 155, 72d Cong., 2d sess.
                     Waterford.
June 20,1938        Deepening channel between Albany and Waterford                     H. Doc. 572, 75th Cong., 3d sess.
                     to 14 feet, with no change in depths for harbors in
                     front of Albany and Troy.

  1 These documents contain latest published maps.
  2 Permanent Appropriations Repeal Act approved June 26, 1934.
  3 PWA, Sept. 6, 1933.




  Recommended modification of project. Under date of January
23, 1953, the Chief of Engineers recommended modification of the
existing project to provide for a channel 600 feet wide from New
York City to Kingston and thence 400 feet wide to Albany, with
widening at the bends, a turning basin 700 feet wide and 1200
feet long at Albany, and two anchorages, one near Hudson and
one near Stuyvesant, each with a width of 400 feet and an average
length of 2400 feet; all with depths of 32 feet in soft material and
34 feet in rock; at an estimated cost to the United States of
$30,700,000 for new work and $170,000 annually for maintenance
in addition to that now required; subject to certain conditions of
local cooperation.
        RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT           117
   Local cooperation. Fully complied with.
   Terminal facilities. The piers and other terminal or transfer
facilities served by the improvement are as follows:
   Between Waterford and the Federal dam at Troy there are 14
wharves aggregating approximately 5,000 feet in length. The
State of New York has constructed a barge-canal terminal at
Cohoes. There is a dock 325 feet long on the west side of the
river just north of the Federal dam.
   At Troy there are nine terminals with available dockage of
2,383 feet, including the State barge-canal terminal with 960 feet.
In addition, 11/4 miles of concrete bulkhead were constructed
along the waterfront by the city of Troy. At Watervliet there is
a stone bulkhead 755 feet long. Between this point and Albany
there are 5 timber wharves aggregating 4,275 feet in length.
   At Albany, and Rensselaer on the east side of the river, there
are 30 terminals aggregating 18,661 feet of available berthage,
including a city-owned recreation pier of 900 feet and the State
barge-canal terminal with 1,586 feet located on the west side of
the river. These terminals are adequately served with railroad
trackage. There are 5 transit sheds, 1 warehouse, a 13,500,000-
bushel grain elevator, and a molasses-storage plant, all provided
by the Albany Port District Commission.
   Between Albany and Hudson there are about 100 timber
wharves aggregating 36,700 feet in length; at Hudson there are
12 timber wharves aggregating 5,000 feet in length; at Athens
there are 9 timber wharves aggregating 4,000 feet in length.
   Between Hudson and the upper limits of New York City the
entire waterfronts of Poughkeepsie, Newburgh, and Yonkers are
equipped with transfer facilities. At Poughkeepsie there are 14
terminals with available dockage of 7,823 feet, including a city-
owned pier of 270 feet. At Newburgh there are 17 terminals with
a total dockage of 8,431 feet, of which 1 with 90 feet of dockage
is open to the public. At Yonkers there are 28 terminals with
dockage of 10,659 feet, of which 531 feet are for public use.
   The existing wharves are ample for Hudson River traffic. (For
latest full description of terminal facilities, see Port and Termi-
nal Facilities at the Ports on the Upper Hudson River, 1941, and
Port and Terminal Facilities at the Port of New York, 1942,
Corps of Engineers.)
   Operationsand results during fiscal year. Under a contract for
dredging to restore the channel between North Germantown
Landing and Silver Point to project depths of 27 to 28 feet, work
was commenced April 16, 1954, and completed June 2, 1954.
During the fiscal year 182,850 cubic yards, place measurement,
were removed at a cost of $132,224, including engineering pre-
liminary to dredging, for maintenance.
   By use of Government plant and hired labor, brush and small
trees growing on 20,651 linear feet of dikes between Troy and
Hudson were sprayed and 55,549 linear feet of dikes were cleared
of dead brush and trees during the period July 1 to November 18,
1953. 27,527 linear feet of dikes were resprayed to kill regrowth
during the period of June 3 to 30, 1954, at a total cost of $12,291
for maintenance.
118      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   By use of Government plant and hired labor, stumps and snags
which formed a potential menace to navigation and other ob-
structions were removed from the shores and channel of the river
during the fiscal year at a cost of $8,234 for maintenance.
   The costs of condition surveys, tidal observations, miscellane-
ous inspections and reports, were $35,880 for maintenance.
   The lock and dam in the Hudson River at Troy, N.Y., was op-
erated and cared for during the fiscal year. Operation of the lock
for the 1953 navigation season was suspended December 9, 1953,
and resumed March 30, 1954, for the 1954 season. Under a con-
tract for painting the lower miter gates, work commenced Feb-
ruary 3, 1954, and was completed March 10, 1954. Under con-
tract for repairs to the powerhouse and lockmaster's cottage,
work commenced April 27, 1954, and was under way at the end
of the fiscal year. By use of Government plant and hired labor,
numerous repairs and activities preparatory to operation of the
lock and dam as well as repairs to the buildings, utilities, and
equipment were performed. The cost of all this work was $113,-
890 for operation and care of lock and dam at Troy, N. Y.
   The total cost of work was $302,519-$188,629 for maintenance
and $113,890 for operation and care of lock and dam at Troy,
N. Y.
   Condition at end of fiscal year. Work under the existing proj-
ect was commenced July 1910 and is about 96 percent complete.
The construction of new lock and dam at Troy, removal of old
dam at Troy, and construction of 15,545 linear feet of new dikes
have been completed. In the reconstruction of old dikes, 39,672
linear feet have been raised to the adopted crest height. The
channel from Albany to Waterford has been completed to a depth
of 14 feet, with the exception of a small part of the widening to
form a harbor at Troy, which work is not deemed necessary for
the present. The work of deepening the channel south of Albany
to 27 feet mean low water has been completed with the exception
of about 1,500 linear feet at the northern end.
   The controlling mean low water depth from New York City to
Hudson, N. Y., is 27 feet for a width varying from 300 to 400
feet, thence 27 feet for a width varying from 150 to 450 feet to
about 4,700 feet below the Dunn Memorial Bridge, thence 15 feet
for a width varying from 150 to 400 feet to the Dunn Memorial
Bridge.
   The controlling lowest low water depth from Albany to the
lock and dam at Troy is 14.0 feet for a width varying from 400
feet at Albany to 145 feet near the south entrance to the lock at
Troy. At the lock entrance it is 14 feet deep for a width of 45
feet. Controlling depth over the lock sills is 13.0 feet at the lower
sill. The controlling pool level depth above the lock at Troy to
Waterford, the head of the improvement, is 14 feet for a width of
about 200 feet.
   The work remaining to be done under the existing project con-
sists of completing the widening to form a harbor 12 feet deep in
front of Troy, the construction and reconstruction of dikes, and
deepening the northerly 1,500 feet of the 27-foot channel from
               RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT                                                                119
New York City to the site of the former Albany-Greenbush
Bridge.
  The total costs under the existing project to June 30, 1954,
were as follows:
                                                                                           _
                                                New work             Maintenance                 Oand
                                                                                                   perating           Total
                                                                                                      care
Regular funds ....                               $15,577,938               $5, 370, 796            $1,938, 039       $22, 886, 773
Public works funds_                                     238, 350                                                          238, 350
Emergency Relief funds_                                 311, 461                                                          311, 461

      Total_                                      16, 127, 749              5, 370, 796             1,938, 039        23, 436, 584


   In addition, the sum of $454,273 was expended between August
18, 1915, and June 30, 1935, on the operation and care of the work
of improvement under the provisions of the permanent indefinite
appropriation for such purposes.
                                         Cost and financial summary

                                                  Fiscal year ending June 30                                      Total to June
                                                                                                                 30, 1954, includ-
                                                                                                                 ing fiscal years
                                  1950           1951              1952                1953           1954        prior to 19501

New weork:
   Api propriated                  $19, 300----------          -- $18, 366 -----------.--                         - $21, 240, 342   2


   Cost-------        ----------        934 ....-               -.... .. .-...................                       21, 240, 342   2


Maintenance:
   ApIpropriated         ..- -- 1, 073, 500 -$210, 292             449, 368          $207, 189       $344, 431        27, 720, 917  T


             ----
   Cos t.............              448, 428      346, 652          512, 480           204, 967        302, 519        27, 655, 632  2




   Includes $5,112,594 for new work and $346,797 for maintenance for previous projects.
   Includes O. & C.
Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project...____
                                                 ................... ...................... $1,552,000

         18. GREAT LAKES TO HUDSON RIVER WATERWAY--
         ENLARGEMENT OF NEW YORK STATE BARGE CANAL
   Location. This waterway consists of that portion of the New
York State Barge Canal system extending from the Hudson River
at Waterford to Oswego Harbor on Lake Ontario. (See U. S.
Lake Survey Charts Nos. 182, 183, 184, and 185.)
   Existing project. This provides for the allotment of Federal
funds to the State of New York for expenditure under suitable
Federal control and supervision in the improvement of the canal
connecting Lake Ontario with the Hudson River. The improve-
ment provides for a depth of 13 feet below normal pool level
through all locks between Waterford and Oswego, deepening be-
tween locks to 14 feet below normal pool levels, widening at bends
and elsewhere, and increasing the overhead clearance to 20 feet at
maximum navigable stage at bridges and other overhead struc-
tures. The widths of channel to be provided under the project are
104 feet in earth cuts, 120 feet in rock cuts, 200 feet in river sec-
tions, with widening at bends and elsewhere as may be necessary.
   The length of the waterway included in this project is about 184
miles, of which 160 miles are in the Erie Canal from Waterford to
120             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Three Rivers Point and 24 miles are in the Oswego Canal from
Three Rivers Point to Oswego.
  The estimated cost for new work, made in 1954, is $32,800,000,
of which not more than $27,000,000 shall be expended on deepen-
ing between locks and raising of bridges and other overhead clear-
ances as contained in River and Harbor Committee Doc. 20, 73d
Congress, 2d session. No estimate of maintenance with Federal
funds is included, as maintenance of the canal is not a part of the
Federal project.

    Acts                         Work authorized                                  Documents

May 28, 19351   Deepening between the locks to 14 feet, increasing     Rivers and Harbors Committee,
Aug. 30, 1935    overhead clearances to 20 feet and widening at          Doc. 20, 73d Cong., 2d sess.'
                 bends and elsewhere.                                                                      2
Mar. 2,1945     Depth of 13 feet below normal pool level through all   S. Doc. 252, 79th Cong., 2d sess.
                 locks between Waterford and Oswego.

1 Emergency Relief Act of 1935.
2 Contains latest published map.



   Local cooperation. The River and Harbor Act of March 2,
1945, authorized the deepening of the locks subject to the condition
than an agreement be entered into between the United States and
the State of New York embodying certain limitations and provi-
sions to safeguard the interests of general commerce and naviga-
tion, insure Federal control of the disposition of Federal funds,
and provide for Federal supervision of the work performed. A
supplemental agreement dated June 5, 1947, containing all provi-
sions necessary for efficient prosecution of the improvement, was
entered into by the Chief of Engineers and the Department of
Public Works, State of New York. The requirements under the
prior acts have been fully complied with.
    Terminal facilities. The State of New York has provided ter-
minal and transfer facilities at all important points along the Erie
and Oswego Canals, and at Buffalo, Troy, Albany, and New York
Harbor. The freight-handling equipment, as well as the storage
and dock facilities, is governed by the requirements of the particu-
lar locality. The State-owned terminal at Oswego is equipped
with a grain elevator of 1,000,000 bushels' capacity. The Albany
Port District Commission has erected a grain elevator of 13,500,-
000 bushels' capacity at Albany. The Port of New York Authority
grain terminal in New York Harbor on Gowanus Bay has a
capacity of approximately 1,800,000 bushels.
   Terminals at Buffalo, Rochester, Syracuse, Schenectady, Troy,
Albany, and Oswego are provided with direct railroad connections.
All State-owned terminals are open to the public on equal terms.
Lakeport terminals are extensive in character. The available
terminals appear ample to meet all requirements.
   Operations and results during fiscal year. The cost of engi-
neering studies for lowering sills at various locations between
Waterford and Oswego, N. Y., and inspection of work under con-
tract at Lock 7, Erie Canal, was $1,506 for new work.
   Final costs have not been reported for work completed during
                RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT                                                                      121
the fiscal year under contract for lowering sills at Lock 7, Erie
Canal.
   Condition at end of fiscal year. Work under the existing project
was commenced in September 1935 and is about 79 percent com-
plete. The status of the channel deepening and widening is as
follows:

                                                                                                    Distance (miles)


                                                                                                          Work remaining to
                   From-                                              To-                     Com-                     be done
                                                                                              pleted
                                                                                                to
                                                                                              project    Work in                Future
                                                                                              depth      progress               work
Hudson River-----_  --------------                   Guard gate 2 at Waterford                    2. 6             _---------       0. 2
Guard gate 2 at Waterford            ........                             ---- _ -
                                                     Lock 10 at Cranesville....                  32. 2
Lock 10 at Cranesville -------------
                         _                                                   ...
                                                     Lock 16 at Mindenville------__              36. 1             -     -
Lock 16 at Mindenville_                 __-
                                   ......            Guard gate 5 at Herkimer...-------          15. 5        __                       .7
Guard gate 5 at Herkimer_                            Oswego Harbor          __                   96. 7    -

       Total (184 miles) .      -.       ...    ..    .   .   .   .   ..    ..   .   ..   .     183. 1   -_   ..                       .9



   Thirty-five barge canal bridges have been raised and one length-
ened to project clearance with Federal funds under this improve-
ment. Project vertical clearance has been provided at two addi-
tional bridges with Federal funds by construction of additional
spillway capacity at Herkimer, N. Y. Three additional bridges
were raised, 4 were removed and two were removed and replaced
by new structures at project clearance; all by other agencies.
   The present depth is 14 feet at normal pool levels for the follow-
ing width; 75 feet in earth cuts, 94 in rock cuts, and 200 feet in
canalized rivers and lakes. The 29 locks, 22 in Erie Canal east of
Three Rivers Point, and 7 in Oswego Canal, north of Three Rivers
Point, have a clear width of 43.5 feet, usable length of 300 feet, and
depth over miter sills of 12 feet. Numerous fixed bridges, trans-
mission lines, and other structures span the waterways. There
are 68 bridges between Waterford and Three Rivers Point and 13
between Three Rivers Point and Oswego. The minimum clear-
ance under existing bridges and other overhead structures is 14.66
feet above maximum navigable stage.
   Work of lowering lock sills to project depth is being prosecuted
by the State of New York in conjunction with contracts for neces-
sary maintenance of lock structures.
   The work remaining to be done to complete the project consists
of widening and deepening the channel by excavation, including
the removal of ledge rock and work incidental thereto, for a total
distance of 0.9 mile, as described in the above table, the raising of
21 barge canal bridges, the raising of 4 guard gates, the revetment
of banks with quarry stones where necessary and the deepening
to 13 feet through 26 locks.
   The total cost of the existing project to June 30, 1954, was
$22,777,707, for new work $17,964,307 was from regular funds
and $4,813,400 from Emergency Relief funds.
122             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                Cost and financial summary

                                                        Fiscal year ending June 30                                Total to June
                                                                                                                 30, 1954, includ-
                                                                                                                 ing fiscal years
                                       1950           1951           1952          1953           1954            prior to 19501

New work:
   Appropriated            ..................      -- $156, 466   -$52,     338    -_i-           $10, 000            $22, 786, 496
   Cost                          $1, 022, 889
                       .---------------               644, 470           20, 667    $1, 499         1, 506                 22, 777, 707
Maintenance:
   Appropriated                                                      -                -       -              -     --..-
   Cost-------------------------                                                              -
  1 Exclusive of $42,338 held in reserve by O.C.E. for future requirements.

Other new work data:
                                                                            $
    Unobligated balance, fiscal year ending June 30, 1954------_. ---.........      8, 789
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955 .8...                                                           8, 789
                                              --------------------------------------------
    Estimated additional amount needed to be appropriated for com-
       pletion of existing project----.......    ..                            10,013,000
                                                     ..........--------------------------
          19. NARROWS                      OF LAKE CHAMPLAIN,                          N. Y. AND VT.
   Location. This waterway, 37 miles long, comprises the south-
ern end of Lake Champlain and extends from Whitehall to Crown
Point, N. Y. The portion included in the project extends from
Whitehall, N. Y., at the southern extremity of the lake, northerly
to Benson Landing, Vt., a distance of 13.5 miles. (See U. S. Lake
Survey Chart No. 174.)
   Previous projects. Adopted by River and Harbor Acts of July
4, 1836, March 3, 1837, July 7, 1838, August 5, 1886, July 13, 1892,
and March 3, 1899. For further details, see page 256, Annual
Report for 1932.
   Existing project. This provides for a channel extending from
Whitehall, N. Y., at the head of Lake Champlain, to Benson
Landing, to be 12 feet deep at low lake level and generally 200
feet wide, and the installation of fender booms at Putts Rock,
Putts Leap, Narrows near Dresden, Pulpit Point, and Cedar
Mountain. The reference plane of low level is 93.0 feet above
mean sea level at Sandy Hook, N. J. The length of the section
included in the project for improvement is about 13.5 miles.
The usual annual variation of the lake level is 5.8 feet, and the
extreme variation varies from 0.6 foot below up to 8.8 feet above
the low lake level.
   The estimate of cost for new work, revised in 1954, is $2,140,-
000 exclusive of amounts expended on previous projects. The
latest (1950) approved estimate for annual cost of maintenance
is $9,000.
   The existing project was adopted by the River and Harbor Act
of August 8, 1917 (H. Doc. 1387, 62d Cong., 3d sess.). The latest
published map is in the project document.
   Terminalfacilities. Terminal facilities are located in Whitehall
Harbor and consist of three timber wharves, aggregating 4,200
feet in length. The State of New York has constructed a barge
canal terminal at Whitehall, just south of the terminus of the
canal, which has been equipped with a 15-ton hand-operated
derrick and a storehouse. The facilities are considered adequate
for present commerce.
                      RIVERS AND HARBORS--NEW YORK, N. Y., DISTRICT                                                                                       123
  Operations and results during fiscal year. Repairs to fender
booms were made during the fiscal year by Government plant and
hired labor at a cost of $1,627 for maintenance.
  The cost of a survey to determine the condition of the channel
was $2,559 for maintenance.
  The total cost of work was $4,186 for maintenance.
  Condition at end of fiscal year. Work under the existing proj-
ect was commenced June 1919 and is about 47 percent complete.
A channel 12 feet deep at low lake level and least width of 150
feet has been excavated throughout the length of the improve-
ment, except at the Elbow, where the width is 110 feet. Fender
booms have been placed at the Elbow (Putts Leap and Putts
Rock) and opposite the Delaware & Hudson railroad trestle. No
fender booms appear to be needed at the Narrows near Dresden,
Pulpit Point, and Cedar Mountain. The controlling depths at
low lake level, as disclosed by surveys made in August 1948, and
July 1953, through the reach included in the project, were as
follows:

                                           Locality                                                                                      Depth       Width
                                                                                                                                         (feet)      (feet)
Whiteball to the Elbow    _                                                                                                                   12         75-250
At the Elbow -_-____   _                                                                                                                      12            100
From the Elbow to Maple Bend                                                                                                    _             12        100-150
From Maple Bend to Red Rock Bay                                                                                                               12            150
From Red Rock Bay to Benson Landing .                         ..          .      .         .       .              .12                                   100-150


  The work remaining to be done to complete the project consists
of widening the channel throughout its length to the project
width of 200 feet.
  The total cost of the existing project to June 30, 1954, was
$854,686--$566,811 for new work and $287,875 for maintenance.
                                           Cost and financial summary

                                                        Fiscal year ending June 30                                                             Total to June
                                                                                                                                              30. 1954, includ-
                                                                                                                                              ing fiscal years
                                    1950               1951                    1952                        1953                     1954        prior to 19501
New work:
   Appropriated                                                                                                                                       $681, 811
   Cost                                                                                                                                                681,811
      Cost-----------------   --                 ----------            -   -  -   -   --
Maintenance:                                                           -----------             -   -   -    --    -   -   ------------                .681,   811



   Appropriated--------            $102, 000 1            -$41     J            $3, 200                           $386 .....                           307, 283
   Cost_                             55,809             42,649                      740                          2.046       $4.186                    307, 015

  1   Includes $115,000 for new work and $19,140 for maintenance for previous projects.

Other new work data: Estimated additional amount needed to be ap-
  propriated for completion of existing project _...-------------------$1 ,573,000
                                   20. BURLINGTON HARBOR, VT.
  Location. This harbor, about 100 acres in extent, is located in
a half-moon-shaped indentation in the eastern shore of Lake
Champlain, about 40 statute miles south of the international
boundary line, 70 statute miles north of the southern end or head
of the lake, and 20 statute miles southeast of the harbor at
Plattsburg, N. Y. (See U. S. Lake Survey Chart No. 172.)
      Existing project. This provides for a breakwater 6,000 feet
124             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

long located about 1,000 feet from the shore and practically
parallel with it, to be built of stone-filled timber cribs capped
with large stone or concrete. The completed breakwater is to
be in two sections, the northerly 500 feet being separated from
the southerly 5,500 feet by a gap 200 feet wide for the purpose
of safety in entering the harbor during storms. The reference
plane of low lake level is 93.0 feet above mean sea level at Sandy
Hook, N. J. The level of the lake has varied from 0.6 foot below
up to 8.8 feet above the low lake level. The usual annual variation
is 5.8 feet.
   The cost for new work for the completed project was $706,414.
The latest (1950) approved estimate for annual cost of mainte-
nance is $8,000.
   The existing project was authorized by the following River
and Harbor Acts:

    Acts                          Work authorized                                      Documents'
July 4,1836     Construction of first 1,000 feet of breakwater....--------. H. Doc. 131, 23d Cong., 1st sess.
June 23, 1866   Extension of 1,500 feet to breakwater......-------------- H. Ex. Doe. 56, 39th Cong., 2d sess.,
                                                                             pp. 17 and 179, printed in pts. 3
                                                                             and 4, Annual Report, 1866.
Mar. 3,1875     Extension of 2,000 feet to breakwater                         Annual Report, 1874, p. 274.
                                                                    ..--------------
                Chief of Engineers authorized extension southerly of       Annual Report, 1887, p. 2407.
                 1,000 feet and northerly for 500 feet.

1 For latest published map, see Annual Report for 1897, p. 3298.

   Terminal facilities. The terminals consist of bulkhead shore
front and open pile and solid filled piers having a total dockage
of 6,520 feet. Of the terminals, 5 wharves, 2 piers, and 1 ferry
slip are in use. Five of the terminals have railroad connections.
The facilities are considered adequate for present needs of com-
merce.
   Operations and results during fiscal year. The cost of miscel-
laneous studies and surveys was $4,072 for maintenance.
   Condition at end of fiscal year. The existing project was prac-
tically completed in 1890; part of the breakwater originally pro-
posed was not built, the work completed being considered suffi-
cient for the needs of navigation. The breakwater has been
built in two sections, 364 and 3,793 feet in length, respectively,
separated by a gap of 200 feet. Sections of the stone and con-
crete superstructure of the breakwater have been displaced by
wave action and the failure of the timbers in the tops of the
wooden cribs. The controlling depth in August 1948 was :about
10 feet at low lake level at the wharves, increasing considerably
toward the breakwater.
   The distinction between new work and maintenance was not
made in the early reports, hence it is impossible to separate the
costs prior to July 1, 1886.
   The total cost of the existing project to June 30, 1954, was
$988,138. Since June 30, 1886, the cost of maintenance was
$281,724, leaving $706,414 as the cost of new work, including
maintenance prior to June 1, 1886.
            RIVERS AND HARBORS--NEW YORK, N. Y., DISTRICT                                                        125
                                       Cost and financial summary

                                                Fiscal year ending June 30                             Total to June
                                                     __30,                                                1954, includ-
                                                                                                       ing fiscal years
                            1950            1951                1952           1953         1954        prior to 1950

New work:
   Appropriated                                 .-                                    -..                     $706, 414
   Cost-----------------.                                                                                      706, 414
Maintenance:                                                               '
   Appropriated       .            -     --..           ------------                        $5, 415            283, 067
   Cost-                                                          ------       ---            4, 072           281, 724



        21. NEW YORK HARBOR: ENTRANCE CHANNELS AND
                      ANCHORAGE AREAS
   Location. The works included under the above title are in the
upper and lower bays, New York Harbor. The harbor is 330
miles southwest by water of Boston Harbor, Mass., and 165 miles
northeast of the entrance to Delaware Bay, N. J. and Del.
   The upper bay extends southerly from the junction of Hud-
son and East Rivers opposite the Battery, New York City, a dis-
tance of about 51/2 miles to the Narrows. The lower bay extends
from the Narrows to the sea, a distance of about 9 miles. (See
U. S. Coast and Geodetic Survey Chart No. 369.)
   Existing project. This provides for the Ambrose Channel 45
feet deep and 2,000 feet wide, extending from the sea to deep
water in the lower bay, length about 10.2 miles; for Anchor-
age Channel, an extension of Ambrose Channel, with the same
depth and width, in the upper bay, opposite the anchorage
grounds, length about 5.7 miles; for Bayside-Gedney Channel
35 feet deep and 800 feet wide, extending from the sea to the
junction with Main Ship Channel, length about 6.2 miles; for
Main Ship Channel 30 feet deep and 1,000 feet wide, extend-
ing from Bayside-Gedney Channel to deep water in the lower
bay, length about 5.3 miles; for the removal of Craven Shoal
to a depth of 30 feet; for a channel 16 feet deep, 200 feet wide,
and about 2.3 miles long, extending from bell buoy 23 to Hoffman
and Swinburne Islands for an irregularly triangular-shaped an-
chorage area in the southerly half of Red Hook Flats (approxi-
mately 442 acres in extent), 40 and 30 feet deep; an anchorage
in the vicinity of Liberty (Bedloe) Island (about 160 acres in
extent) 20 feet deep, and for a channel along the New Jersey
pierhead line connecting Kill Van Kull with deep water in An-
chorage Channel, south of the Liberty Island anchorage, 20 feet
deep for a width of 500 feet with widening at bends to 800 feet
and a length of about 3 miles. The project depths refer to mean
low water. Mean tidal range, 4.7 feet; mean range of spring
tides, 5.6 feet; irregular fluctuations due to wind and barometric
pressure vary from 3.9 feet below mean low water up to 5.2 feet
above mean high water.
   The estimate of cost for new work, revised in 1954, is $17,647,-
000. The latest (1950) approved estimate for annual cost of
maintenance is $315,000.
126                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  The existing project was authorized by the following River
and Harbor Acts:

       Acts                           Work authorized                                     Documents
July     5, 1884   Main Ship-Bayside-Gedney to 30 feet for width of            Annual Reports, 1887, p. 62, and
                    1,000 feet (dimensions fixed by Secretary of War,           1888, p. 63.
                    Dec. 27, 1886, by authority of the act of Aug. 5, 1886).
Mar. 3,1899        Ambrose Channel (East Channel) to 40 feet-.. -         ..   H. Doc. 159, 55th Cong.,    3d
                                                                                                            sess.
                                                                                 (Annual Report 1899, p. 1279.)
June 25, 1910      Maintenance of entrance channel under 1 head .....
Aug. 8,1917        Anchorage Channel, the extension of Ambrose Chan-           H. Doc. 518, 63d Cong., 2d sess.
                     nel into Upper Bay.
    Do.......      Removal of Craven Shoal----------------------H.                Doc. 557, 64th Cong., 1st sess.
    Do.......      Channel between Staten Island and Hoffman and               H. Doc. 625, 64th Cong., 1st sess.
                    Swinburne Islands.
July    3, 1930    Relocation of southerly section of Anchorage Channel.       Rivers and Harbors Committee
                                                                                 Doec. 18, 71st Cong., 2d seass.
Aug. 30, 1935      Dredging south end of Red Hook Flats, Liberty               H. Doc. 183, 73d Cong., 2d sess.'
                    Island Anchorage, and channel along New Jersey
                    pierhead line.
    Do-......      Deepening Bayside-Gedney Channel to 35 feet for a           H. Doc. 133, 74th Cong., 1st sess.'
                    width of 800 feet.
Aug. 26, 1937      Deepening Ambrose and Anchorage Channels to 45              Senate committee       print,    75th
                    feet for-a width of 2,000 feet.                              Cong., 1st sess.'

  ' Contain latest published maps.

   Terminal facilities. The harbor consists of Upper Bay and
Lower Bay. In the Upper Bay there are 48 terminals with a
total berthage of 73,276 feet. In addition there are 6 car-float
 (railroad) bridges and 3 ferry terminals consisting of 7 slips.
These terminals are located along the westerly shore of the bay,
from St. George, Staten Island, to the Narrows and from Con-
stable Hook, Bayonne, to Ellis Island. The terminals along the
Brooklyn waterfront are reported under Bay Ridge and Red
Hook Channels. The Lower Bay is largely
terminals being confined to Gravesend Bay where there are 8
                                                              the                   -undeveloped,
terminals with a total berthage of 13,233 feet. Of the terminals
in the harbor, 46 are equipped with mechanical handling devices,
and 34 have railroad connections. The facilities are considered
adequate for present commerce.
   Operations and results during fiscal year. The U. S. seagoing
hopper dredge Essayons was employed intermittently from Au-
gust 9, 1953, to May 17, 1954, in dredging to restore the Main
Ship Channel to its authorized project dimensions. During the
fiscal year 974,280 cubic yards, place measurement, of material
were removed at a cost of $416,500 for maintenance, including
the cost of engineering preliminary to dredging.
   The cost of condition surveys, miscellaneous inspections, and
reports was $42,009 for maintenance.
   The total cost of work was $458,509 for maintenance.
   Condition at end of fiscal year. Work under the existing proj-
ect was commenced in 1885 and is about 95 percent complete.
   Main Ship and Bayside-Gedney Channels were completed to a
depth of 30 feet in February 1891. The deepening of Bayside-
Gedney Channel to 35 feet for a width of 800 feet was completed
in June 1939.
               RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT                                                     127
   Ambrose Channel was completed to a depth of 40 feet for a
width of 2,000 feet in April 1914, and was substantially com-
pleted to a depth of 45 feet for a width of 2,000 feet in 1951.
   Relocation of Anchorage Channel was completed to a depth
of 40 feet in October 1932. The center 800 feet was dredged to
45 feet in June 1947 and the westerly 600-foot strip in April
1948. The easterly 600-foot strip was substantially completed
in June 1953.
   The channel between Staten Island and Hoffman and Swin-
burne Islands was completed in December 1920 up to within 300
feet of the southerly limits of the project. The dredged channel
meets all the needs of navigation and no further work of im-
provement is contemplated for the present.
   The channel along the New Jersey pierhead line from Kill Van
Kull to Anchorage Channel was completed in March 1939.
Widening at bends near the southerly and northerly ends author-
ized in 1948 has not yet been done.
   The Red Hook Flats anchorage was completed to 40 and 30
feet and the Liberty (Bedloe) Island anchorage was completed
to 20 feet in October 1944.
   The controlling mean low water depths of the channels in-
cluded in this project are as follows:

                     Section                          Depth              Width                       Date
                                                       (feet)            (feet)
Ambrose Channel ....--------------------------                44 1,000 to 2,000--  ...         March to May 1954.
Main Ship Channel....-------------------------                30 500 to 1,000----------.....       Do.
Bayside-Gedney Channel                                        35 700 to 800----........            Do.
Anchorage Channel ..-                           -             45 2,000        ___              April 1951 to June 1953.
Craven Shoal ------------------ -------- -                  1 30 - _ - -      - --             July 1931.
Channel between Staten Island and Hoffman
  and Swinburne Islands:
    Buoy 23 to Hoffman Island -         _                     13 100 to 200 .    --------..    November 1943.
    Hoffman Island to Swinburne Island .-                     10 120 to 200                        Do.
Red Hook Flats Anchorage:
    40-foot area-      ..         .....--------------------- 35 ------------------ May-June 1954.
    30-foot area_.    _                                       26 __                                Do.
Liberty (Bedloe) Island Anchorage-           .-----         2 20 ------------------- January 1950.
Along New Jersey pierhead line _       - ---                  19 500 to 200                    February to March 1948.
                                                                                     ..----------


   Except for a shoal 100 by 600 feet with least depth of 27 feet located along westerly channel line.
   Except for scattered shoals along the westerly side having a minimum depth of 12 feet.

   The work remaining to be done under the existing project con-
sists of widening the existing 500-foot channel along the New
Jersey pierhead line to 800 feet at the southerly and northerly
bends.
   The total cost of the existing project to June 30, 1954, was
$20,960,269--$16,656,895 for new work, including $116,530 ap-
plied to removing wrecks authorized by acts prior to the adop-
tion of the existing project, and $4,303,374 for maintenance.




         Sig 5--127-158
128                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                 .1954
                                        Cost and financial summary

                                               Fiscal year ending June 30                          Total to June
                                                                                                   30, 1954, includ-
                                                                                                   ing fiscal years
                                 1950         1951        1952            1953        1954          prior to 1950

New work:
   Appropriated   .-------- $412, 000        $350, 000   $400, 000     $482,000      -$1,    068       $16, 656, 895
   Cost-----------------     382, 829         470, 733    309, 326      480, 503             429        16, 656, 895
Maintenance:
       Appropriated --------
                      _          117, 300       5, 000    134, 394         17, 000    450, 640           4, 308, 489
       Cost-------  --------     125, 804       5, 903     18, 177        119, 516    458, 509           4, 303, 374



Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project.._______.. .....
                                                          _......
                                                           _                $990, 000
                                                                  .................

22. NEW YORK HARBOR-COLLECTION                                       AND REMOVAL OF DRIFT

  Location. This project applies to the Lower and Upper Bays,
New York Harbor; East River, Harlem River, Hudson River
Channel, N. Y., New York and New Jersey Channels, Newark
Bay, N. J., and their tributaries.
  Existing project. This provides for the collection and removal
of drift from New York Harbor and its tributary waters, and
authorizes the Secretary of War to allot such amounts as may
be necessary for the work from appropriations for maintenance
and improvement of existing river and harbor works or other
available appropriations, and that this work shall be carried as
a separate and distinct project. It is wholly a work of mainte-
nance. The purpose of the work is to afford relief from variable
conditions of obstruction, and no advance estimate of the amount
of work required and its proper cost can be made.
  The existing project was authorized by the following River
and Harbor Acts:
       Acts                        Work authorized                                     Documents
Mar. 4, 1915       Allotment from appropriations made for New York
Aug.     8, 1917    Harbor and its immediate tributaries may be used
                    for collection and removal of drift in these water-
                    ways.
July     3, 1930   Carrying on this work as a separate and distinct
                    project.



   Terminal facilities. Described in the separate reports covered.
   Operationsand results during fiscal year. The U. S. drift col-
lector Driftmaster, steam lighter Gorham, motor tenders Daly
and Stanwix and auxiliary plant were assigned to the work of re-
moving and disposing of drift when not employed on other work.
There were removed and disposed of during the fiscal year 379,-
492 cubic feet (2,965 cords) of driftwood, ranging in size from
small blocks to timbers of large dimensions, including piles and
pieces of wreckage. The cost of this work was $267,561 for
maintenance.
   Condition at end of fiscal year. The existing project is one of
continuous maintenance for which no percentage of completion
exists. Navigation has been made safer by the continual patrol
of the harbor and the removal of large quantities of drift mate-
               RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT                                              129
rial. The total cost of operations to June 30, 1954, amounted to
$4,735,156 for maintenance.
                                          Cost and financial summary

                                                 Fiscal year ending June 30                    Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                                   1950        1951        1952        1953        1954         priorto 1950

Maintenance:
   Appropriated--------........   $258,000    $295, 300   $304, 500   $237, 225   $266, 000         $4, 735, 188
   Cost...----------------         258, 330    295, 850    301, 688    240, 907    267, 561          4, 735, 156



                 23. NEW YORK AND NEW JERSEY CHANNELS
   Location. These channels extend from deep water northwest
of Sandy Hook, through lower New York Bay and Raritan Bay, to
Perth Amboy, and thence through Arthur Kill, lower Newark Bay,
and Kill Van Kull to deep water in upper New York Bay. This
route is located approximately along the boundary line between the
States of New York and New Jersey. (See U. S. Coast and Geo-
detic Survey Charts Nos. 285, 286, and 369.)
   Previous projects. a. Raritan Bay. Adopted by River and Har-
bor Acts of March 3, 1881, September 19, 1890, and June 3, 1896.
   b. Staten Island Sound. Adopted by River and Harbor Acts of
June 23, 1874, March 3, 1875, June 14, 1880, August 11, 1888, May
15, 1889, and October 20, 1890, June 3, 1896, June 13, 1902, June 25,
1910, and March 4, 1913.
   c. New York and New Jersey channels. Adopted by River and
Harbor Act of September 22, 1922. For further details, see page
284 of the Annual Report for 1923, and page 194 of the Annual Re-
port for 1934.
   Existing project. This provides for a channel through lower
New York Bay, Raritan Bay, Arthur Kill, lower Newark Bay, and
Kill Van Kull to upper New York Bay, the depth to be 37 feet in
rock and 35 feet in soft material throughout, the width to be 600
feet across lower New York Bay and Raritan Bay and in the Ar-
thur Kill to a point 1,000 feet north of Smith Creek, widened to
800 feet in the vicinities of Seguine Point and Wards Point, re-
spectively, thence 500 feet wide to a point 1,000 feet south of the
former location of Buckwheat Island, thence 500 to 600 feet wide
and passing north of Shooters Island and protected by a dike on
its northern side to the junction of the channel into Newark Bay;
and thence 800 feet wide through Kill Van Kull to upper New York
Bay; with 2 anchorages 38 feet deep to accommodate 5 vessels
each, 1 in the vicinity of Sandy Hook and 1 south of Perth Amboy,
all with suitable easing at the bends and junctions. Length of
section included in project, 30.8 miles. In addition, the construc-
tion of a dike north of Shooters Island and two secondary channels
30 feet deep and 400 feet wide, one south of Shooters Island and
the other in Raritan Bay connecting with Raritan River, have been
completed under previous projects and are maintained under the
existing project. All depths refer to the plane of mean low water.
The mean range of tides varies between 4.7 and 5.1 feet; the mean
range of spring tides, 5.6 to 6.1 feet; irregular fluctuations due to
130              REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1,954
wind and barometric pressure vary from 3.9 feet below mean low
water up to 6.9 feet above mean high water.
  The estimate of cost of new work, revised in 1954, is $58,807,000,
exclusive of amounts expended on previous projects and exclusive
of $7,712 contributed by local interests. The estimate of annual
cost of maintenance, revised in 1950, is $195,000.
  The existing project was authorized by the following River and
Harbor Acts:

    Acts                           Work authorized                                      Documents

Sept. 6, 19331   Anchorage off Perth Amboy to 33 feet_             _   -_   Rivers and Harbors Committee
Aug. 30,1935                                                                  Doc. 17, 71st Cong., 2d seas.
May 28, 1935$    Channel 35 feet deep from lower bay to upper bay,          H. Doe. 133, 74th Cong., 1st sess.
Aug. 30, 1935     except between vicinity of Smith Creek and vicinity
                  of Piles Creek to 30 feet with anchorages 38 feet deep
                  at Sandy Hook and Perth Amboy.
May 17, 1950     Channel 35 feet deep from vicinity of Smith Creek to       H. Doc. 233, 81st Cong., 1st sess.
                  vicinity of Piles Creek.

 ' Public Works Administration.
3 Emergency Relief Act of 1935.
s Contain latest published maps.


   Local cooperation. Work under the acts of May 28, 1935, and
August 30, 1935, is subject to the following conditions of local co-
operation:
   a. That where the project channel encroaches upon upland prop-
erty and extends shoreward of harbor lines, the completion of the
encroaching portions of the project shall be deferred until the nec-
essary rights-of-way for channel purposes shall have been granted
free of cost to the United States; and
   b. That local interests provide areas of land adjacent to the
waterway, free of cost to the United States, for the disposal of
dredged materials, except where, in the judgment of the Chief of
Engineers, no suitable disposal areas exist.
   Under condition a, a portion of Buckwheat Island necessary for
channel purposes has been ceded to the United States. An ease-
ment dated August 4, 1942, approved by the Chief of Engineers on
September 5, 1942, conveyed to the United States, free of cost,
rights-of-way for channel purposes at Howland Hook, Staten Is-
land, N. Y. Condition b is being complied with. Authority was
granted by the Chief of Engineers on November 11, 1935, to re-
quire local interests to provide areas for the disposal of dredged
material only in the section of the waterway extending from the
vicinity of Outerbridge Crossing at Perth Amboy to the vicinity of
the channel north of Shooters Island:
   The River and Harbor Act of May 17, 1950, provides that local
interests shall:
   a. Provide without cost to the United States all lands, easements,
rights-of-way, and spoil disposal areas necessary for the construc-
tion and subsequent maintenance of the project, when and as
required.
   b. Hold and save the United States free from damages due to
the construction and subsequent maintenance of the project.
   c. Deepen the approaches and berths at the terminals which
would use the recommended improvement in order to secure the
full advantages of the deeper channel.
         RIVERS AND HARBORS--NEW YORK, N. Y., DISTRICT           131
    Assurances of compliance with the above conditions were ac-
cepted by the Secretary of the Army on March 4, 1954.
    Terminal facilities. There are 187 terminals with a total berth-
age of 119,916 feet. In addition, there are 7 ferry landings, and
2 car-float (railroad) bridges. Of the terminals, 101 are equipped
with mechanical handling devices, and 80 have railroad connec-
tions. Included in the terminals are five large shipyards. Five of
the terminals with a berthage of 1,693 feet are not used for water-
borne commerce. Two of the terminals have marine railways.
The facilities are considered adequate for existing commerce.
    Operations and results during fiscal year. Under a continuing
contract for dredging in Perth Amboy Anchorage to a depth of 25
and 37 feet, work was commenced July 24, 1951, and was accepted
as completed July 2, 1953. During the fiscal year 1,113 cubic
yards, place measurement, of material were removed at a cost of
 $558 for new work.
    The U. S. seagoing hopper dredge Essayons was employed inter-
mittently from July 1, 1953, to August 3, 1953, in dredging a por-
tion of the channel in lower New York Bay between Wards Point
and about 18,000 feet east of Seguine Point to a depth of 35 feet
and widening from 400 to 600 feet. During the fiscal year 414,300
cubic yards, place measurement, of material were removed at a
cost of $143,614 for new work, including the cost of engineering
and design.
    The U. S. seagoing hopper dredge Essayons was employed inter-
mittently from July 14, 1953, to May 14, 1954, in dredging a por-
tion of the channel in lower New York Bay in the vicinity of Wards
Point and Seguine Point to a depth of 35 feet. During the fiscal
year 533,600 cubic yards, place measurement, of material were
removed at a cost of $153,003, including the cost of engineering
preliminary to dredging, for maintenance.
    Under a contract for dredging to a depth of 35 feet in Arthur
Kill between the limits of Tremley Point and the southerly end of
Lakes Island, work was commenced June 8, 1954, and was in
progress at the end of the fiscal year. During the fiscal year 29,900
cubic yards, place measurement, of material were removed at a
cost of $42,677, including the cost of engineering and design, for
new work.
   Under a contract for dredging to a depth of 35 feet in Arthur
Kill between the limits of Grasselli and Tremley Point, work was
commenced April 9, 1954, and was still in progress at the end of
the fiscal year. During the fiscal year 888,200 cubic yards, place
measurement, of material were removed at a cost of $450,018,
including the cost of engineering and design, for new work.
   Under a contract for dredging to a depth of 30 feet in the chan-
nel south of Shooters Island, work was commenced March 1, 1953,
and completed June 10, 1953. No material was removed during the
fiscal year. However, the liquidation of this contract reflected a
final cost of $13,675 for maintenance during the fiscal year.
   Under a contract for dredging to restore previous project depth
of 30 feet in Arthur Kill between Tufts Point and Sewaren, N. J.,
work was commenced May 16, 1953, and completed June 11, 1953.
Final costs of $145 for maintenance under the previous project
were reported during the fiscal year.
132                  REPORT OF CHIEF: OF ENGINEERS, U. S. AtMY, 1954

   The costs of condition, surveys, miscellaneous inspections and
reports were $18,347 for maintenance.
   The total cost of work was $822,037, of which $636,867 was for
new work and $185,170 was for maintenance-$185,025 under the
existing project and $145 under the previous project.
   Condition at end of fiscal year. Work under the existing proj-
ect was commenced October 1933 and is about 70 percent complete.
Work completed thus far has consisted of providing project depth
of 35 feet in soft material and 37 feet in rock, 600 feet wide,
through lower New York Bay, Raritan Bay, and Arthur Kill to a
point 1,000 feet north of Smith Creek, except in the vicinity of
Seguine Point, where the width is 400 feet, the channel for full
width from 1,000 feet south of Buckwheat Island through Kill Van
Kull to upper New York Bay; and of providing depths of 37 and 25
feet in Perth Amboy Anchorage.
   In addition to the above-mentioned work, the construction of a
dike north of Shooters Island, two secondary channels 30 feet deep
and 400 feet wide, one south of Shooters Island, the other in Rari-
tan Bay connecting with Raritan River and a channel 30 feet deep
and 400 feet wide in Arthur Kill from a point 1,000 feet north of
Smith Creek to 1,000 feet south of Buckwheat Island have been
completed under previous projects.
   The controlling mean low water depths of the channel included
in the project are as follows:

                                    Section                                           Depth         Width                         Date
                                                                                      (feet)        (feet)
From main ship channel to Wards Point-----------------                                       35         450-800       March-April, 1954.
From Wards Point to Sewaren .___---.----------...                                            33         400-600         Do.
From Sewaren to Piles Creek ........---------------------------                              30         250-400       June 1951.
From Piles Creek to Elizabethport                                  ---__--.                  35         500-600       November 1939 to Au-
                                                                                                                        gust 1949.
From Elizabethport to Bergen Point-_-_-------------_       --       35                               600-800          September 1951.
From Bergen Point to Upper New York Bay                         ------------
                                                                    35                                      800       March 1944 to Jan. 1949.
Channel south of Shooters Island------------------------30                                                  400       March-May 1953.
Anchorage in the vicinity of Sandy Hook .......----------------     21                            .......----------   April 1951.
Anchorage south of Perth Amboy            ------------------- 37and25
Channel in Raritan Bay connecting with Raritan River..              28
                                                                                                  ----------..
                                                                                                            . June 1953.
                                                                                                    200-400 April 1951.



   The work remaining to be done under the existing project con-
sists of completing the deepening and widening of the entire chan-
nel to dimensions authorized by the River and Harbor Acts of
August 30, 1935, and May 17, 1950, and dredging the anchorage in
the vicinity of Sandy Hook.
  The total costs under the existing project to June 30, 1954, were
as follows:

                                                                                                                   Cost
                                                                                   New work                   Maintenance             Total
Regular funds---.........--------...................---------------------...... ..       $33,564,901              $2, 714,963  $36, 279, 864
Public works funds                            ...---------  ...-------------------------     807, 000          __-_.__..---..... 807, 000
Emergency Relief funds                    - -....
                                             . ..-   ----             ---....
                                                                          .             2, 023, 308       -       .. ___.         .   ..2,023,308

                                   _ -------
     Total United States funds-------              36, 395, 209                                                     2, 714, 963          39, 110,172
Contributed funds---........          ..--......-------7, 712
                             ... -----------------                                                            -      ......                    7,712
              Total, all funds----_---------------                      -__            36, 402,921                  2, 714,963           39, 117,884
                 RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT                                                          133
                                               Cost and financial summary

                                                          Fiscal year ending June 30                        Total to June
                                                                                                            30, 1954, includ-
                                                                                                            ing fiscal years
                                        1950           1951           1952          1953         1954       prior to 19501 2s

New work:
   Appropriated-.......              $1, 260, 000   $2, 665, 000   $1, 414, 000    $894, 000    $965, 000        $49, 572, 085
   Cost..--.......--------------         849, 742    1, 295, 694    1, 800, 124   1, 753, 917    636, 867         49, 205, 184
Maintenance:
     Appropriated          __           118, 000       860, 540       290, 200      377, 686     158, 324          3, 882, 056
     Cost-..... -           _ _ -_      123, 340       415, 394       708, 030      383, 641     185, 170          3, 875, 343

   1Includes $12,809,975 for new work and $1,160,235 for maintenance for previous projects.
   2In addition $7,712 for new work was expended from contributed funds.
   3 Includes $6,621 for new work and $1,621 for maintenance of Lemon Creek, S.I., N.Y.


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954........-----............-----. $66,822
    Appropriated for succeeding fiscal year ending June 30, 1955..........                       2,000,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955--------------....................................------...                   1,980,822
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project............... ....-................. ....................... 20,045 ,000



    24. NEWARK BAY, HACKENSACK AND PASSAIC RIVERS, N. J.
   Location. Newark Bay is an estuary about 11/4 miles wide and
6 miles long extending southerly from the confluence of the
Hackensack and Passaic Rivers to New York and New Jersey
Channels.
   The Hackensack River rises near Haverstraw, Rockland County,
N. Y., and flows into Newark Bay. It is about 45 miles long.
   The Passaic River rises in the highlands of northeastern New
Jersey and flows into Newark Bay. It is about 80 miles long.
 (See U. S. Coast and Geodetic Survey Charts Nos. 285 and 287.)
   Previous projects. Adopted by River and Harbor Acts of
August 30, 1852, June 10, 1872, June 14, 1880, June 13, 1902,
March 2, 1907, July 25, 1912, March 2, 1919, and September 22,
1922. For further details see pages 265 and 266 of Annual Re-
port for 1926; page 301, Annual Report for 1929; and page 244,
Annual Report for 1938.
   Existing project. This provides for the following:
   a. Newark Bay: A main channel 37 feet deep in rock and 35
feet-deep in other material, 550 feet wide at the entrance and
narrowing to 400 feet at 4,000 feet above the Central Railroad
of New Jersey bridge; thence continuing to that width and same
depths to the branch channel to Port Newark Terminal; thence
30 feet deep and 400 feet wide to the junction of the Passaic
and Hackensack River channels; removal of the east and west
cutoffs at the junction with Kill Van Kull and widening of bend
above the Central Railroad of New Jersey bridge to the same
depths, a distance of about 4.7 miles.
   b. A branch channel in Newark Bay 37 feet deep in rock and 35
feet deep in other material, 600 feet wide to the inshore channel
at Port Newark terminal, widened at the turn; thence an inshore
channel of the same depths and 400 feet wide; a total distance
of about 1.6 miles.
 134             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY. 1954

    c. Hackensack River: A channel 30 feet deep and 400 feet wide
from the upper end of the Newark Bay channel to the Central
Railroad of New Jersey bridge, about 1.1 miles; thence 30 feet
deep and 300 feet wide to a point about 2,000 feet north of the
Delaware, Lackawanna & Western Railroad bridge, 2.8 miles;
thence 12 feet deep and 200 feet wide to Little Ferry, 10.1 miles
and then 12 feet deep and 150 feet wide to the New York Susque-
hanna & Western Railroad bridge, 2.5 miles, a total distance for
the Hackensack River of about 16.5 miles.
   d. Passaic River: A channel 30 feet deep and 300 feet wide,
from Newark Bay to a point 3,000 feet above the Lincoln High-
way bridge, 2.6 miles; thence 20 feet deep and 300 feet wide to
the Nairn Linoleum Works, about 4.4 miles; thence 16 feet deep
and 200 feet wide to the Montclair & Greenwood Lake Railroad
bridge, about 1.1 miles; thence 10 feet deep and 150 feet wide to
the Eighth Street Bridge at Passaic, 7.3 miles, a total distance
for the Passaic River of 15.4 miles.
   All depths refer to the plane of mean low water. The mean
tidal range in Newark Bay is 4.9 feet; in Hackensack River at
Court Street Bridge, 5.3 feet; in Passaic River at Pennsylvania
Railroad freight bridge, 5.1 feet; and in Passaic River at the Greg-
ory Avenue Bridge, 5.1 feet; mean range of spring tides, 5.8, 6.4,
6.1, and 6.1 feet, respectively; irregular fluctuations due to wind
and barometric pressure vary from 3.7 feet below mean low water
up to 6.2 feet above mean high water.
   The estimate of cost for new work, revised in 1954, is $10,200,-
000, exclusive of amounts expended on previous projects. The
latest (1950) approved estimate for annual cost of maintenance
is $250,000.
   The existing project was authorized by the following River
and Harbor Acts:

       Acts                       Work authorized                                     Documents

Mar. 2, 1907  16-foot channel in Passaic River ............   __ ....    H. Doc.    441, 59th Cong., 2d sess.
Feb. 27,1911  Widening 16-foot channel in Passaic River ...     . -          Do.
July 25, 1912 20-foot channel in Passaic River--..----------             H. Doc.    707, 62d Cong., 2d sess.
    Do-._ ....12-foot channel in Hackensack River __.. ___-- .......     H. Doc.    643, 61st Cong., 2d sess.
Sept 22, 1922 30-foot channel in Hackensack River below Central          H. Doec.   206, 67th Cong., 2d sess.'
                 RR. of New Jersey bridge, 30-foot channel in
                 Newark Bay, and 30-foot Port Newark connecting
                 channel.
Jan. 21, 1927 10-foot channel in Passaic River- .---. -----          _   H. Doe. 284, 69th Cong., 1st sess.
    Do- ....  30-foot channel in Hackensack River above Central          H. Doec. 429, 69th Cong., 1st sess.'
                 RR. of New Jersey bridge.
July 3, 1930 30-foot channel in Passaic River------_         -------     H. Doec. 156, 71st Cong., 2d sess.'
Mar. 2, 1945 35 and 37 feet in main channel of Newark Bay and            S. Doc. 250, 79th Cong., 2d sess.
                 branch channel to and inshore channel at Port
                Newark Terminal and removal of portion of rock
                area at Bergen Point to same depths.
    Do . -....Modification of local cooperation for 10-foot channel      H. Doec. 430, 76th Cong., 1st sess.
                in Passaic River.


  1   Contains latest published map.


  Recommended modification of project. Under date of July 30,
1951, the Chief of Engineers recommended modification of the
existing project to provide for deepening the existing 30-foot
project channel in Hackensack River, including the 30-foot
approach channel in Newark Bay upstream from the branch
channel at Port Newark Terminal, to a depth of 34 feet at mean
         RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT             135
  low water in rock and 32 feet deep in other material with widen-
ing at bends, and for a turning basin 25 feet deep at the upper
  end of this channel, 800 feet wide and 1,000 feet long, at an esti-
  mated cost to the United States of $1,463,000 for construction
and $10,000 annually for maintenance in addition to the amount
  now required, subject to certain conditions of local cooperation.
     Local cooperation. Fully complied with as required by the
River and Harbor Act approved January 21, 1927, except that
local interests are required to provide suitable spoil disposal
areas for maintenance dredging in the 30-foot channel in the
Hackensack River above Central Railroad of New Jersey bridge;
in the 10-foot channel in the Passaic River; and whenever re-
quired by the Secretary of War, for dredging in the 30-foot chan-
nel in Newark Bay and the Hackensack River below the Central
Railroad of New Jersey bridge, as required by the River and
Harbor Act approved September 22, 1922.
     The River and Harbor Act of March 2, 1945, provides that
local interests shall:
    a. Agree to furnish, free of cost to the United States, all lands,
easements, rights-of-way, and spoil disposal areas needed for
new work and subsequent maintenance, when and as required;
     b. Hold and save the United States free from claims for dam-
ages resulting from the improvements;
    c. Provide and maintain suitable berthing areas at Port Newark
terminal.
    Assurances providing compliance with the local cooperation
requirements under this act were accepted by the Chief of Engi-
neers on March 22, 1950. In addition, the sum of $285,600 was
contributed by the Port of New York Authority to cover the cost
of dredging the berthing areas at Port Newark Terminal, which
work was completed by the United States in conjunction with
the excavation of the project channel during 1951.
    It further provided, for the 10-foot channel in Passaic River
from Montclair & Greenwood Lake Railroad bridge to the Eighth
Street Bridge in Passaic, that when spoil disposal areas are not
available, or the placing of dredge spoil ashore is uneconomical
as compared with other methods of disposal, local interests
shall not be required to furnish disposal areas for maintenance
dredging.
    Terminal facilities. Along the waterways of this project there
are 142 terminals with a total berthage of 58,276 feet as well as
a large shipyard. Of these, Port Newark, which is owned and
operated by the New York Port Authority, provides about 10,625
feet of wharfage. Fifty-seven of the terminals are equipped
with mechanical handling devices and 54 have railroad connec-
tions. Six of the terminals aggregating a berthage of 1789 feet
are not used for water-borne commerce. These facilities are
considered adequate for existing commerce.
    Operationsand results during fiscal year. Under a contract for
dredging to a depth of 35 feet in the branch and inshore chan-
nels at Port Newark and to a depth of 30 feet in Newark Bay,
in Hackensack River to about 1,500 feet north of the Pulaski
Skyway Bridge, and in Passaic River to about 2,500 feet north
136                  REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

of the junction with Hackensack River, work was commenced
April 6, 1953, and was completed November 27, 1953. During the
fiscal year 129,068 cubic yards, place measurement, of material
were removed at a cost of $110,909 for maintenance, including
the cost of surveys and engineering work incidental to dredging.
   The cost of condition surveys, miscellaneous inspections and
reports was $9,755 for maintenance.
   The total cost of work was $120,664 for maintenance.
   Condition at end of fiscal year. Work under the existing proj-
ect was commenced August 1907 and is about 89 percent com-
plete. The channels included in the project have been completed
to full project dimensions except for deepening the 20-foot main
channel in Passaic River from Jackson Street to Nairn Linoleum
Works. Deepening of the 35-foot main channel in Newark Bay,
including the triangular cutoffs at the entrance was completed
during April 1952.
   The controlling mean low water depths of the various chan-
nels, as shown by surveys made intermittently from September
1939 to September 1953, are as follows:

                                                     Section                                                                    Depth                Width
                                                                                                                                 (feet)               (feet)
In Newark Bay from mouth to junction with branch channel to Port Newark
  terminal---------------        --------------------------------.--.
                             -----                                                                                                        35             400-535
From junction with branch channel to Port Newark terminal to junction of
  Hackensack and Passaic Rivers------------................---...............----------------------------                                 30             380-400
In Hackensack River from Newark Bay to about 2,000 feet above the Delaware,
  Lackawanna & WesternR R bridge---------------------------------------..........................................                         30             220-400
From 2,000 feet above Delaware, Lackawanna & Western R R bridge to head of
project at the New York, Susquehanna & Western R R bridge----....----.                                                          -        12            :130-200
In Passaic River from Newark Bay to 1900 feet upstream from Junction Light..                                                              30                   300
From 1900 feet upstream from Junction Light to 3,000 feet above Lincoln High-
  way bridge                   ----------------------------------------------------------                                                 22             200-300
From 3,000 feet above Lincoln Highway bridge to Jackson Street hridge---_--                                                               17             300-180
From Jackson Street bridge to Nairn Linoleum Works-......................                                                                 15             150-300
From Nairn Linoleum Works to Montclair & Greenwood Lake R R bridge.....                                                                   12             150-100
From Montclair & Greenwood Lake R R bridge to 8th Street bridge............                                                                 9              60-150
From branch channel in Newark Bay to inshore channel at Port Newark ter-
  minal          .               .................--------------------------------------------------------------                          35             600-400


Minimum widths through bridge draws:
    Hackensack River:                                                                                                                                          Feet
               30-foot project.................-----------..................                                                                                   145
               12-foot project ...........-------------................                                                                                         56
       Passaic River:
           30-foot project ....---------.. ..........................................-------------------------------.                                          100
           20- and 16-foot projects ...........------------..................------------------------......................................                     70
               10-foot project             -.....-                                          .   ....-----------....................... ....................    45

   Hackensack River is navigable 201/2 miles above mouth to New
Milford. Passaic River is navigable 16 miles above mouth to
Dundee Rapids. The work remaining to be done under the exist-
ing project consists of the completion of the 35-foot main chan-
nel in Newark Bay and the 20-foot channel in Passaic River from
Jackson Street to the Nairn Linoleum Works. Work in the
Passaic River includes the removal of a small quantity of rock
on the west side of the channel above Center Street Bridge. Ad-
jacent property owners are opposed to this work.
   The total cost of the existing project to June 30, 1954, exclu-
sive of $285,600 contributed funds, was $12,780,062 for new work
and $3,762,104 for maintenance.
                     RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT                                                              137
                                                    Cost and financial summary

                                                              Fiscal year ending June 30                        Total to June
                                                                                                                30, 1954,includ-
                                                                                                                ing   fiscal   years
                                             1950          1951          1952         1953          1954        prior to 19501         2



New work:
      Appropriated--------                  $800, 000   $1, 100,000     $732, 000    $107, 898 ..------------         $10, 773,280
      Cost--- ----........                    72,902     1, 613, 209   1, 440, 201      1, 586- ...                    10,773, 280
Maintenance:
      Appropriated- _._..__                  469, 715      268, 262        3, 987     554, 900     -$7, 604              4, 903, 570
      Cost-------------..............--..    603, 097      275, 793        3, 416     424, 134      120, 664             4,900,472

  1   Includes $1,755,321 for new work and $1,138,368 for maintenance for previous projects.
   SIn addition $285,600 for new work was expended from contributed funds.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project...-----------------.................     $1,182,000
                                                                                  .....

                 25. GREAT KILLS HARBOR,                                   STATEN ISLAND, N. Y.
   Location. Great Kills is a small harbor contiguous to lower
New York Bay, located on the southeasterly shore of Staten
Island, N. Y., about 8 miles northwest of Sandy Hook, N. J., and
161/2 miles southwest of the Battery, New York City. (See U. S.
Coast and Geodetic Survey Chart No. 369.)
   Existing project. This provides for an entrance channel 10
feet deep and 150 feet wide from deep water in lower New York
Bay through the entrance to the harbor in the vicinity of the
present westerly end of Crooks Island, thence of same depth and
width along the west side of the harbor and for an anchorage
area of 138 acres and 8-foot depth. The length of the section
included in the project is about 1.9 miles. The mean range of
tide is 4.7 feet, mean range of spring tides, 5.6 feet; irregular
fluctuations due to wind and barometric pressure vary from 3.9
feet below mean low water up to 5.2 feet above mean high water.
   The cost for new work for the completed project was $137,302,
exclusive of $104,805 contributed by local interests. The latest
(1948) approved estimate for annual cost of maintenance is
$15,000.
  The existing project was authorized by the following River
and Harbor Acts:

       Acts                                     Work authorized                                      Documents
Jan. 21, 1927           Entrance channel to Crooks Island___-_                          H. Doc. 252, 69th Cong., 1st sess.
June 20, 1938           Extension of entrance channel and for an anchorage              H. Doc. 559, 75th Cong., 3d sess.
                         area.                                                            (Contains latest published map.)


   Local cooperation. Fully complied with except that local inter-
ests are required to furnish suitable spoil disposal areas for
maintenance.
   Terminal facilities. No terminals suitable for commercial pur-
poses have been established. There are eight small piers used
for mooring and landing purposes. Four commercial boatyards
are located at Great Kills. Upon completion of the two public
terminals to be constructed in accordance with the requirements
of local cooperation, the terminals will be sufficient for present
needs.
138                   REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Operationsand results during fiscal year. The cost of a survey
to determine the condition of the channel was $700 for main-
tenance.
   Condition at end of fiscal year. Work under the existing proj-
ect was commenced December 1934 and completed September
1948. Under a permit issued by the Secretary of the Army, the
city of New York dredged a portion of the anchorage and chan-
nel along the west side of the harbor in order to obtain fill for
park improvement purposes. When examined intermittently
from May 1947, to May 1954, the controlling mean low water
depth was 10 feet for widths of 110 to 150 feet in the entrance
channel from lower New York Bay to Crooks Point, thence of
same depth for a width of 150 feet to the head of the project,
and 8 feet in the anchorage.
   The total cost of the existing project to June 30, 1954, was
$281,217-$36,000 Public Works funds, $101,302 regular funds,
and $104,805 contributed funds, a total of $242,107 for new work
and $39,110 for maintenance.
                                                      Cost and financial summary

                                                                         Fiscal year ending June 30                        Total to June
                                                                                                                          30, 1954, includ-
                                                                                                                           ing fiscal years
                                              1950                 1951                1952           1953       1954       prior to 19501
New work:
   Appropriated--------                     $101, 248 ---------------------------------------------                               $137, 302
   Cost---------------................. -    101,248 -137--..---.--------------.----------..                                       137, 302
Maintenance:
   Appropriated........                             400 .-----              .- ...--.--------------                $700             39,110
   Cost..-----------------                          400     .......-.-                 . . --.--------------..
                                                                                                  .   .      .      700             39,110

   In addition $104,805 for new work was expended from contributed funds.
  2 Reimbursements of Advanced Funds originally expended in prior fiscal years.

                                                 26. RARITAN RIVER, N. J.
  Location. This river rises in the north-central part of New Jer-
sey and flows in a general southeasterly direction into Raritan
Bay, between Perth Amboy and South Amboy, about 24 miles by
water south of the Battery, New York City. (See U. S. Coast and
Geodetic Survey Chart No. 375.)
  Previous projects. A survey of Raritan River for the improve-
ment of New Brunswick Harbor was made in 1836. Subsequent
projects were adopted by acts of June 18, 1878, and March 3,
1881.
   For further details, see page 1777 of Annual Report for 1915,
page 359 of Annual Report for 1918, and page 259 of Annual
Report for 1938.
  Existing project. This provides for a channel 25 feet deep and
300 feet wide extending from the turn in New York and New
Jersey Channels near Great Beds Light to the Government wharf
on the main channel, a distance of 5.8 miles widened to 600 feet
for a length of 1,000 feet opposite the wharf to form a turning
basin of same depth; thence a channel 15 feet deep and 200 feet
wide to the Washington Canal, a distance of 3.0 miles; thence
10 feet deep in soft material, 11 feet deep in rock, and generally
100 feet wide with widening at bends to the Delaware and Rari-
                      RIVERS AND HARBORS-NEW YORK, N. Y. DISTRICT                                                      139
tan Canal entrance at New Brunswick, a distance of 5 miles;
and for a south channel, 25 feet deep and 300 feet wide from
the junction with the main channel at Keasby to the upper limit
of the Titanium Pigment Co. property, a distance of 0.8 mile;
thence 10 feet deep and 150 feet wide to the upper junction with
the main channel at Crab Island, a distance of 2.4 miles. The
plane of reference is mean low water. The mean range of tides
is5.1 feet at the mouth of the river and 5.6 feet at New Bruns-
wick; mean range of spring tides, 6.1 and 6.6 feet, respectively.
Irregular fluctuations due to winds and barometric pressure vary
from 3.6 feet below mean low water up to 6.9 feet above mean
high water.
   The estimate of cost for new work, revised in 1954, is $1,257,-
000, exclusive of amounts expended on previous projects and
exclusive of $66,000 contributed by local interests. The latest
(1940) approved estimate for annual cost of maintenance is
$60,000.
  The existing project was authorized by the following River
and Harbor Acts:

       Acts                                 Work authorized                                         Documents

Mar.        2, 1919    Channel 15 feet deep and 200 feet wide to Washington              H. Doc. 1341, 62d Cong., 3d sess.
                          Canal, thence 10 feet deep and 150 feet wide to canal
                         locks and 10 feet deep through south channel.
July        3,1930     Channel 25 feet deep and 300 feet wide up to New                  H. Doc. 127, 70th Cong., 1st sess.
                         York & Long Branch RR. bridge.
       Do           Channel 10 feet deep in earth and 11 feet in rock to
               ......                                                                    H. Doc. 454, 70th Cong., 2d sess.'
                      New Brunswick. Width reduced to 100 feet.
       Do _-.          Relocation of lower reach of south channel....----------.......   Rivers and Harbors Committee
                                                                                          Doc. 31, 71st Cong., 2d sess.'
Aug. 26, 1937          Channel 25 feet deep and 300 feet wide to junction of             Rivers and Harbors Committee
                        main and south channels, thence of same depth in                  Doc. 74, 74th Cong., 2d sess.'
                        south channel to Titanium Pigment Co.
Oct.    17,1940        Channel 25 feet deep and 300 feet wide from junction              Report on file in the Office, Chief
                        of main and south channels to the Government                      of Engineers(report not printed).
                        wharf, including a turning basin.

1 Contains latest published maps.

  Local cooperation. Fully complied with except that local inter-
ests are required to furnish spoil disposal areas for the mainte-
nance of the 25-foot channel from New York & Long Branch
Railroad bridge to junction of main and south channels, and in
the south channel to the Titanium Pigment Co. property.
   Terminal facilities. There are 13 piers and bulkheads with a
total berthage of 8,549 feet along the shores of Raritan River.
The Government has established a large ammunition and storage
depot and arsenal known as Raritan Arsenal on the river. One
of the terminals is municipally owned and is leased to private
interests. Nine of the terminals are equipped with mechanical
handling devices and 10 have railroad connections. In addition,
there is a boatyard with storage space for 100 craft. The ter-
minals are considered adequate for existing commerce.
   Operations and results during fiscal year. Under a contract
for dredging to a depth of 25 feet in the South Channel from its
junction with the Main Channel to the upper limit of the Titanium
Pigment Company wharf, and to a depth of 18 feet in .the Main
Channel upstream approximately 2,450 feet, work was commenced
November 19, 1953, and completed December 14, 1953. During the
140          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY; 1954

fiscal year 236,254 cubic yards, place measurement, of material
were removed at a cost of $94,792 for maintenance, including cost
of engineering preliminary to dredging.
   The U.S. seagoing hopper dredge Gerig was employed from
September 30, 1953, to October 30, 1953, in restoring the Main
Channel east of Arthur Kill Cut-Off Channel to 25 feet. During
the fiscal year 187,100 cubic yards, place measurement, of material
were removed at a cost of $115,498 for maintenance, including en-
gineering preliminary to dredging.
   The cost of miscellaneous inspections and reports was $1,988 for
maintenance.
   The total cost of work was $212,278 for maintenance.
   Condition at end of fiscal year. Work under the existing proj-
ect was commenced September 1919 and is about 96 percent com-
plete. The main channel has been dredged 25 feet deep and 300
feet wide from the junction with New York and New Jersey Chan-
nels to and including a turning basin of the same depth opposite
the Government wharf, except for a shoal along the northerly
channel line in the vicinity of the Victory Bridge, thence 15 feet
deep and 200 feet wide to the mouth of the Washington Canal,
thence 10 and 11 feet deep and 100 feet wide to the Delaware &
Raritan Canal outlet locks at New Brunswick. The south channel
has been dredged 25 feet deep and 300 feet wide for a distance of
3,200 feet, thence 10 feet deep and 150 feet wide for a distance of
12,400 feet to within 1,300 feet of the junction with the main chan-
nel at Crab Island.
   The model study of Raritan River was completed in March 1952.
   The controlling depths at mean low water are as follows:
                       Section                          Depth        Width                  Date
                                                        (feet)       (feet)
In main channel from New York and New Jersey chan-           25      300-170   April-November 1953.
  nels to junction with the south channel.
From south channel junction to lower end of Govern-          16      300-150   December 1953.
  ment wharf.
From lower end of Government wharf to upper end of           16      300-150   November 1952..
  Government wharf.
Turning Basin, opposite Government wharf.............         9      100-300       Do.
From upper end of Government wharf to the Washington         15      100-200   July 1946-July 1947.
  Canal.
From Washington Canal to the Delaware & Raritan              10       40-100   July 1946.
  Canal lock at New Brunswick.
In south channel to upper limit of Titanium Pigment          25          300   December 1953.
  dock.
From upper limit of Titanium Pigment Co. dock to                 9   150-50    December 1950.
Crossman's dock.
From Crossman's dock to junction with main channel               1   100-150   July 1947.
  opposite Crab Island.


  The work remaining to be done under the existing project is the
dredging of the south channel to a depth of 10 feet and 150 feet
wide for a length of 1,300 feet to the upper junction with the main
channel at Crab Island, and the removal of a shoal along the
northerly channel line in the vicinity of the Victory Bridge.
  The total cost of the existing project to June 30, 1954, was
$3,560,015, $878,315 from regular funds, $292,685 from Ordnance
funds, and $66,000 from contributed funds, a total of $1,237,000
for new work, and $2,323,015 from United States funds for main-
tenance.
                 RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT                                                           141
                                                   Cost and financial summary

                                                            Fiscal year ending June 30                         Total to June
                                                                                                              30, 1954, includ-
                                                                                                               ing fiscal years
                                          1950            1951           1952        1953         1954        prior to 1950 2

New work:
   Appropriated --------------------                                                          -------------         $1, 551, 470
   Cost  -----------------                     -----    -------      ------------ ------------ ------------          1, 551, 470
Maintenance:
   Appropriated........                     $219, 137     $99, 472      $119, 953   $133, 863    $213, 216           2, 436, 746
   Cost----------------.................
                                     -210,636             104,787        116, 802    138,826      212,278            2,434,434


  SIncludes $673,155 for new work and $111,419 for maintenance for previous projects.
  2 In addition $292,685 for new work was expended from Ordnance Funds and $66,000 for new work was
expended from Contributed Funds.
Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project__....-......-... .. . ....... ... ........... $86,000,

                                       27. SHREWSBURY RIVER, N. J.
    Location. This river is mainly a large tidal basin in the eastern
part of New Jersey, the outlet being at the southeast end of Sandy
Hook Bay, about 4 miles south from the point of Sandy Hook. (See
U. S. Coast and Geodetic Survey Chart No. 824.)
    Previous projects. Adopted by River and Harbor Acts of Au-
gust 30, 1852, March 3, 1871, March 3, 1879, modified in 1883 and
1887, and by the River and Harbor Act of March 2, 1919. For fur-
ther details, see page 1778 of Annual Report of 1915, page 373 of
Annual Report of 1918, and page 267 of Annual Report for 1938.
    Existing project. This provides for a channel 12 feet deep and
300 feet wide, following the westerly shore, from deep water in
Sandy Hook Bay to a point 600 feet south of the railroad bridge at
Highlands, a distance of 2.2 miles; then 9 feet deep and generally
150 feet wide, suitably widened at bends and turns, in the south
branch of the river to the Branchport Avenue Bridge in the city of
Long Branch, a distance of 6.8 miles; and for a channel in the
north branch 6 feet deep and 150 feet wide from the junction to
Red 'Bank, a distance of 6.1 miles; a turning basin and anchorage
in the vicinity of Red Bank, 6 feet deep and about 19 acres in area;
a channel in Claypit Creek, 6 feet deep and 100 feet wide from the
6-foot curve in the north branch to the head of the creek, a distance
of about 1.0 mile; a channel in Oceanport Creek, 6 feet deep, 100
feet wide and 2 miles long from the channel in south branch to
the New York and Long Branch Railroad Bridge; and for a channel
in Little Silver Creek, 6 feet deep, 100 feet wide and 1.6 miles long
from the channel in south branch to the Seven Bridge Road Bridge.
All depths refer to the plane of local mean low water. The mean
range of tide at Highlands is 3.8 feet; at Seabright, 1.7 feet; at
Branchport, 1.7 feet; and at Red Bank, 3 feet. Mean range of
spring tides is 4.7, 2.1, 2.2, and 3.6 feet, respectively. Irregular
fluctuations due to wind and barometric pressure vary from 1.7
feet below mean low water up to 6.5 feet above mean high water.
    The estimate of cost for new work, revised in 1954, was $996,-
000, exclusive of amounts expended on previous projects and ex-
clusive of $36,311 funds already contributed and $86,000 to be
contributed by local interests. The estimate of annual cost of
maintenance, revised in 1950, is $68,000.
142            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  The existing project was authorized by the following River and
Harbor Acts:

    Acts                          Work authorized                                   Documents

Mar. 2,1919 Channel 6 feet deep in North Branch __......_         ----   H. Doc. 1296. 62d Cong., 3d sess.
Aug. 30,1935 Channel 12 feet deep_ _ ___         ._____
                                               ____............          H. Doc. 157, 71st Cong 2d sess.
   Do_ .____ Channel 9 feet deep______________ ___-......
                                                   ........              Rivers and Harbors Committee,
                                                                           Doc. 31, 74th Cong., 1st sess.
May 17, 1950    Turning basin and anchorage 6 feet deep at Red           H. Doc. 285, 81st Cong., 1st sess.
                 Bank, and channels 6 feet deep in Claypit, Ocean-         (Contains latest published map).
                 port, and Little Silver Creeks.



   Local cooperation. The River and Harbor Act of May 17, 1950,
provides that local interests shall:
   a. Provide without cost to the United States all lands, easements,
rights-of-way, and spoil disposal areas necessary for the construc-
tion, and subsequent maintenance of the project, when and as
required.
   b. Hold and save the United States free from damages due to
the construction and subsequent maintenance of the improvement.
   c. Provide and maintain a suitable public wharf on each of the
creeks to be improved, which shall be open to all on equal terms.
   d. Remove at their own expense the Locust Avenue Bridge over
Claypit Creek.
   e. Make cash contributions of $25,000, $33,000, and $27,500
toward the cost of improvement of Claypit, Oceanport, and Little
Silver Creeks, respectively.
   Provided further that construction of any unit of the proposed
improvement may be undertaken independently of the other units
when the required local cooperation has been provided.
   These conditions have not been fulfilled. The requirements un-
der prior acts have been fully complied with.
   Terminal facilities. There are 33 terminals with a total berth-
age of 7,986 feet located on the waterway. Eight of the terminals
with a total berthage of 1,000 feet are open to the public. In addi-
tion, many private pleasure boat landings have been constructed
by owners of riverfront estates. Fifteen boatyards with storage
space for 670 craft and equipped with 21 marine railways are avail-
able. None of the terminals has direct rail connections. The facili-
ties are considered adequate for existing commerce.
   Operations and results during fiscal year. The cost of a survey
to determine the condition of the channel was $1,647 for main-
tenance. This survey was not completed at the end of the fiscal
year.
   Condition at end of fiscal year. Work under the existing proj-
ect was commenced October 1919, and is about 57 percent complete.
   The controlling mean low water depths of the channels included
in the project are as follows:
             RIVERS AND HARBORS--NEW YORK, N. Y., DISTRICT                                                                         143

                               Section                                      Depth         Width                         Date
                                                                            (feet)           (feet)

From Sandy Hook Bay to 600 feet south of railroad                               12. 0      300-250          September 1950.
  bridge at Highlands, N. J.
From 600 feet south of railroad bridge at Highlands, N. J.,                      9. 0             150             Do.
  to junction of north and south branches.
From junction of north and south branches to Branch-                             8.0           80-150       May-June 1950.
port Ave. bridge at Long Branch, N. J.

                  NORTH BRANCH
Junction with main channel to City Dock at Red Bank,                             6.0           75-150             Do.
  N. J.
From City Dock to head of project opposite Maple Ave.,                           4. 5             150             Do.
  Red Bank, N. J.
Anchorage and turning basin at Red Bank, N. J ...... _                           3.0              400       September 1947.
Claypit Creek from mouth to Locust Avenue Bridge.....                            1.4              100           Do.
Oceanport Creek, from junction with south branch to                              1.6              100           Do.
  New York and Long Branch Railroad Bridge.
Little Silver Creek, from junction with south branch to                         0. 8              100             Do.
  Seven Bridge Road.


   The river is navigable on the north branch to Red Bank; on the
south branch to Branchport; on Claypit Creek to Locust Avenue;
on Oceanport Creek to Oceanport Avenue; and on Little Silver
Creek to Seven Bridge Road.
   The work remaining to be done under the existing project con-
sists of dredging the turning basin and anchorage in the vicinity of
Red Bank, and the channels in Claypit, Oceanport, and Little Silver
Creeks as authorized by the River and Harbor Act of May 17, 1950.
   The total cost of the existing project to June 30, 1954, was
$801,159-$466,563 for new work and $334,596 for maintenance.
In addition, the costs from contributed funds were $36,311 for
new work.
                                          Cost and finan, ial summary


                                                         Fiscal year ending June 30                                      Total to June
                                                                                                                        30, 1954, includ-
                                                                                                                        ing fiscal years
                                   1950               1951           1952               1953               1954          prior to 19501 2

New work:
   Appropriated    -                                                                                    ---...                 $687, 457
   Cost_               -                      ---                                                                               687, 457
Maintenance:
   Appropriated            _       $98, 000         -$16, 010                                                 $2, 500            622, 055
   Cost_ - _                         5, 216            76, 774   -     --                                      1, 647            621, 202

  1 Includes $220,894 for new work and $286,606 for maintenance for previous projects.
  2 In addition $36,311 for new work was expended from contributed funds.
  3 Exclusive of $86,000 to be contributed by local interests.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project                                .     __......         ........                 $_529,000

                  28. SUPERVISION OF NEW YORK HARBOR
  The laws enacted for the preservation of the tidal waters of New
York Harbor, its adjacent or tributary waters, and the waters of
Long Island Sound are administered by the Supervisor of New
144             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

York Harbor. The Supervisor is charged under the laws with the
duties of preventing any obstructive or injurious deposits in the
waters under his jurisdiction and the prevention of any interfer-
ence with safe navigation of the channels of the harbor by deep-
draft vessels.
   The laws relating to the supervision of New York Harbor are the
Act of Congress approved June 29, 1888 (25 Stat. 209) as amended
by section 3 of the River and Harbor Act of August 18, 1894 (28
Stat. 360), section 8 of the River and Harbor Act of May 29, 1908
 (35 Stat. 424, 426), act of February 16, 1909 (35 Stat. 623), and
act of July 12, 1952 (66 Stat. 596) ; section 2 of the River and Har-
bor Act of August 18, 1894 (28 Stat. 360); and act of Congress
approved June 24, 1924 (Oil Pollution Act, 43 Stat. 604).
   Supervision was exercised by means of the U. S. Patrol Boats
Active and San Luis II, four patrol launches and shore patrol and
and inspection. Patrols were maintained to insure that no obstruc-
tive or injurious material was deposited at places other than the
designated dumping grounds; to keep the main channels free of
any interference to their safe navigation by deep-draft vessels;
and to prevent the discharge into navigable waters of waste oil
and sludge, rubbish, and other types of debris.
   The total cost of all work during the fiscal year, including the
cost of operating the vessels and the work of the office for the
supervision of New York Harbor to June 30, 1954, was $386,240.
   Summary of legal actions. The disposition of legal actions to
the end of the fiscal year for violations of act of June 29, 1888, as
amended, and the Oil Pollution Act of 1924, is as follows:
Number of cases reported to United States attorney for prosecution:
   Prior to fiscal year 1954 .-....-....                                                               1701
   During fiscal year 1954 ......             .35

        Total ....---......------.--   .--- -.......-.                                          -      1736
Number of convictions obtained or cases settled by compromise:
   Prior to fiscal year 1954 .....         .......-------------------------------------------          1155
   During fiscal year 1954     .....            - ----
                                       ......---------------           -37

     Total ...-----... ---.........  ...    -------..------------------------- 1192
Number of cases nolle prossed or discontinued:
   Prior to fiscal year 1954...----------------------------------------         442
                                         -. ...
   During fiscal year 1954_ ..-. _________--     --               -.              1

     Total ...--.....----
                   ......    ------------------------------...-----...--------- 443
Number of cases dismissed after trial:
   Prior to fiscal year 1954...--------------------------------------------58
                                        . . .. .
   During fiscal year 1954_ ..... ___._._.-..         ..                          0O..

     Total ......................------------------- --------.---------------                            58
Number of cases pending 30 June 1954 ..                        ---------------------------------.        23
     Grand total --------------------------------                                   .-          ----   1736
                   RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT                                                                          145
                                                    Cost and financial summary

                                                                 Fiscal year ending June 30                                     Total to June
                                                                                                                               30, 1954, includ-
                                                                                                                               ing fiscal years
                                            1950              1951              1952              1953              1954         prior to 1950
Maintenance:
                   -------
      Appropriated........                $373, 250         $432, 059         $470, 914          $315, 955         $388, 000       $11, 092, 962
      Cost----------------                 436, 460          433, 370          342, 310           457, 494          386, 240        11, 090, 913



   Summary of deposits. The amounts of material in cubic yards
disposed of under the supervision of the Supervisor of New York
Harbor since 1890, are as follows:
Material deposited at the mouth of the harbor:
   From 1890 to 1953 .... --------- - - - - - - - - - - -                                                                      834, 619, 654
   Fiscal year 1954:
         By United States seagoing hopper dredges from
           Anchorage Channel, Bay Ridge and Red
           Hook Channel, Buttermilk Channel, Hudson
           River Channel and Raritan Bay Channel........ 5,020, 311
         Operations by the United States under con-
           tract in maintenance and improvement of
           waterways.......-------..-..............----.............----.---------.................. 431, 194
         Other than United States operations----------.................... 8, 572, 126
                                                                                                                14,023,631     848,643, 285
Material deposited on shore, or behind bulkheads or dikes:
   From 1890 to 1953 ...................................................--
                                                                 ------.................-                                      505,643,650
   Fiscal year 1954:
         Operations by the United States under contract
           in maintenance and improvement of water-
           ways .---.....---...............................------------------------.....---....................  1,405, 717
         Other than United States operations---------                                .................. 13, 801, 786
                                                                                                             15, 207, 503      520, 851, 153
Material deposited in Hudson River at various dumping
grounds:
    From 1907 to 1953 .....................-------------------------................................. 33, 023, 601
    Fiscal year 1954------------------....................................-------...........................     445,904

                                                                                                      33, 469, 505
Material deposited in Long Island Sound, Fishers Island
Sound, Block Island Sound and Little Narragansett
Bay:
    From 1890 to 1953 ..----...-...--------.  ..-----------............... - . 93, 908, 717
    Fiscal year 1954......................................-----------------------------870, 675

                                                                         94, 779, 392
      G rand total .............................--............. . ... .... ........ .... 1, 497, 743, 335
All material deposited 1890 to 1953              .............. ...................      1,467, 195, 622
All material deposited fiscal year 1954 ................................                     30, 547, 713
146                    REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954
                                  29. INACTIVE NAVIGATION                                   PROJECTS


                                                                              For last        Cost to June 30, 1954
                                                                              full re-                                      Estimated
                             Name ofproject                                    port,                                         amount
                                                                              see an-                             Operation required to
                                                                              nual re-     Construction           and Main-complete
                                                                                port                               tenance
                                                                               for-

1.       Port Chester Harbor, N. Y-.---_ -. --.-...                -...    1953                1 $433, 470   1 $140, 729          " $93, 000
2.       Mamaroneck Harbor, N. Y........._.....----....1952                                    2 S 207, 404     4 55, 475             (5)
3.       Larchmont Harbor, N. Y ..---------------------                    1916                   6 76, 065           211            ()
4.       Echo Bay Harbor, N. Y...----------------------1953
                                     7-                    - - - - -                               8 64, 584      8 7,171             (
5.       New Rochelle Harbor, N. Y ____.__.._                              1949                   9 73, 214       22, 030            (6)
6.       East Chester Creek, N. Y...............-........                  1953              1211592, 057     12 380, 232            664, 000
7.       Westchester Creek, N. Y__.......................                  1953                 1s 175, 849 Is 258, 083              (5)
8.                                                  -----
          Bronx River, N. Y...............................                  1953            14 151 149, 946    14 366, 212            299, 000
9.       Harbor at Flushing Bay, N. Y___..             .        ......-- - 1953                 1 628, 502    16210, 365             710, 000
10.       Manhasset Bay, N. y.10___________1948                                                 _ .---------------     460         18 172, 000
11.       Hempstead Harbor, N. Y       _.-.----------          ---       -1953                       39, 468       68, 099            (5)
12.       Glen Cove Harbor, N. Y.' "      -----------.
                                             90-                            1911                     72,000 ------------           1,038, 000
13.       Glen Cove Creek, N. Y_ ---      __--- .------              -      1953                  17 29, 760       29, 108          19 70, 000
                                               1953
14. Huntington Harbor, N. Y-----................--.....                                           2171, 535            51, 556      2262,000
15.       Northport Harbor, N. Y.2_                    ...........-------...1949                                                    2460, 000
16.       Greenport Harbor, N. Y___   .......           __............      1953                   74, 681              18, 464      (5)
17.       Peconic River, N. Y___ .                        ------
                                           .................                1953                   25, 000             108, 388      (5)
18.       Sag Harbor, N. Y_ _--
                              -------------------------                     1953                 121, 805                1, 266      (5)
19.       Browns Creek, N. Y.7--------------------_                         1951                   33, 976              92, 507      447, 000
20.       Orowoe Creek, N. Y.o                               -----_--       1949 ---------------------------
                                                            ___.---------------                                                        50,000
21.       Sumpawanus (Babylon _Creek) Inlet, N. Y.'
22. Sheepshead Bay, N. Y .......
                            ----         -- --
                                 ............  1948
                                                      _....                 1895                     7, 000
                                                                                                          28
                                                                                                  2633, 828
                                                                                                                   .    3--
                                                                                                                         3,763
                                                                                                                                      (5)
                                                                                                                                      (5)
23.       Coney Island Creek, N. Y....._................ 1952                                          69, 489          1, 622       206,000
24.       Buttermilk Channel, N. Y- ----------......----- _                         1953       271, 941, 918         697, 228      1,274, 000
25.       Wallabout Channel, N. Y---..........                   -------            1953               18, 174        35, 295        (5)
26.       Newtown Creek, N. Y___         .......................                    1953       28 1, 168,354 28 917, 591             583, 000
27.       Irvington Harbor, N. Y.1o 20--o__-____-                               _   1948----------                  - 360              63, 000
28.       Tarrytown Harbor, N. Y._______________________                            1951               69, 836        57,944         (5)
29.       Peekskill Harbor, N. Y.........................               ---         1951               19, 400        59, 808         (51)
30.       Wappinger Creek, N. Y .....................----------------------         1950               13, 000        43,026         (5)
31.       Saugerties Harbor, N. Y.7 20__         .--.----------                 _   1949            2981, 905      so86, 294         (5)
32.       Ticonderoga River, N. Y.7 o__________ ___________                         1895               16,500    ------------        383, 000
33.       Port Henry Harbor, N. Y.7....-----------............---------             1931            12 69, 406         1,253         (5)
34.       Otter Creek, Vt. 20---o                -                 -----
                                                                 2 _ -- - - - - - - 1950               60,254          7, 619        143, 000
35.       Gordons Landing, Lake Champlain, Vt.                                      1892               34,750 ..                     (5)
36.       Plattsburg Harbor, N. Y----.....------------                            - 1953              198, 415       102, 452        (5)
37.       Channel between North7 and South Hero Islands,
            Lake Champlain, Vt. 20---o .                   ..-----                  1909            1 31, 000   .                    (5)
38.       St. Albans Harbor, Lake  7      Champlain, Vt.7 20.....                   1917                3, 125             385        (s)
39.       Swanton Harbor, Vt. 20o _____1888            _________2,                                     70, 500                       010, 000
40.       Rouses Point, Lake Champlain, N. Y.7..........                            1895               98, 468 ...----------          ()
41.       Great Chazy River, N. Y.7 20-------             ------------              1895               18,000 ------------            (5)
42.       Elizabeth River, N. J.10 ----                                ---          1953            S3 60, 481      n159, 391        190, 000
43.       Rahway River, N. J.1lo_   0.___        ..                                 1949            " 37, 000              307       192, 000
44.
45.
          Woodbridge Creek, N. J...-
          Lemon Creek, Staten Island N. Y.10_
                                                    ....-.------
                                                                      .-------...
                                                                                    1953
                                                                                    1937
                                                                                                  3_ 5 49, 823
                                                                                                      1s6, 621
                                                                                                                     177, 673
                                                                                                                     8 1, 621
                                                                                                                                      (5)
                                                                                                                                     200,000
46.       Washington Canal and South River, N. J........                            1953       37 8 206, 116      87208, 941          (5)
47.       Raritan River to Arthur Kill Cut-off Channel,
            N. J      -----------------------------------                           1953              810,500        970,498          (5)
48.       Cheesequake Creek, N. J._.--------------------- 1953                                         40, 000        26,152          333, 000
49.       Matawan Creek, N. J...---- --..........-..---------------........         1953               21, 000        73,964            24, 000
50.       Keyport Harbor, N. J._ .----------------------- 1953                                         40,475        174, 755         (5)
51.       Waycake   Creek,    N.  J.o
                                    10___----1949---                                1949       --....                       -         119, 000
52.       Shoal Harbor and Compton Creek, N. J....--------- 1953                                       47, 282     9 323, 151           45, 000
53.       Sandy Hook Bay at Leonardo, N. J.o----                                    1950   _-------                                -81,     000
54. Sandy Hook Bay, N. J-                    -----    ,___-- -                  1952             41 508,   936         4o 1, 270      (5)
55. Shark River, N. J-------------                         .
                                                        --..... __-_-. .        1953               150, 000            143, 316       (5)


     Includes $74,995 for new work and $16,369 for maintenance for previous projects.
      1
   2 Includes $80,724 for new work for previous projects.
   3 In addition, $18,728 for new work was expended from contributed funds.
   4 Includes $13,415 for maintenance for previous projects.
   SCompleted.
   6
     Includes $5,000 for new work for previous projects.
   7 Improvement adequate for commerce.
   8 Includes $47,368 for new work and $10 for maintenance under previous projects.
   9 Includes $43,175 for new work for previous projects.
  10 Awaiting local cooperation.
  11In addition, $14,403 for new work was expended from contributed funds for previous projects.
  12Includes $592,057 for new work and $380,232 for maintenance on previous projects.
  1
  3 Includes $77,182 for new work and $66,600 for maintenance for previous projects.
  14 Includes $69,036 for new work and $26,921 for maintenance for previous projects.
  1sIn addition, $10,000 for new work was expended from contributed funds.
  16Includes $238,873 for new work and $206,411 for maintenance under previous projects.
             RIVERS AND HARBORS-NEW YORK, N. Y. DISTRICT                                                 147
  17 In addition, $29,774 for new work was expended from contributed funds.
    18In addition, $50,000 to be contributed by local interests, but not forthcoming.
  19Exclusive of $69,500 to be contributed by local interests.
  *2No commerce reported.
  2 Includes $22,500 for new work under previous projects. In addition, $19,546 for new work was expended
from contributed funds.
  2 Exclusive of $31,454 to be contributed by local interests.
  2 No funds available.
  24 In addition, $15,000 to be contributed by local interests.
  28 In addition, $15,200 to be contributed by local interests.
  26
      Includes $26,000 for new work for previous projects.
  22 Include $496,250 for new work for previous projects.
    s Includes $401,261 for new work and $421,817 for maintenance for previous projects.
   29Includes $42,000 for new work for previous projects.

  31
   SoIncludes $15,000 for maintenance for previous projects.
  33  Includes $21,000 for new work for previous projects.
      In addition, $10,000 for new work was expended from contributed funds.
   asIncludes $60,481 for new work and $58,791 for maintenance for previous projects.
   " Includes $37,000 for new work for previous projects.
  3   Includes $19,000 for new work under previous projects.
    86These amounts also included in report for New York and New Jersey Channels. No work has been done
on the existing project for Lemon Creek.
    7 Includes $157,224 for new work and $84,934 for maintenance for previous projects.
   asIn addition, $365 for new work was expended from contributed funds.
  9   Includes $17,000 for new work and $169,709 for maintenance for previous projects.
   4oIncludes final expenditures of $22 for maintenance which were reported during fiscal year 1953 for a condi-
tion survey of the anchorage area completed in July 1951.
   n In addition, $53,790 for new work was expended from contributed funds.
    " Exclusive of $5,500 contributed funds.
   'a Estimated amounts required to complete were revised in 1954.
    " Costs of $209 were incurred during 1954 on a condition survey.
148             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,1954

              30. HOOSICK FALLS, HOOSIC RIVER BASIN, N. Y.
   Location. The Hoosic River rises in northwestern Massachu-
setts, flows generally north and northwest, crossing the southwest
corner of Vermont to the vicinity of Eagle Bridge, N. Y., where it
turns west and joins the Hudson River about 16 miles above Troy,
N. Y. It is 66 miles long and has a drainage area of 713 square
miles. Hoosick Falls, N. Y., is situated on the Hoosic River about
26 miles above the mouth. (See U. S. Geological Survey map cov-
ering Hoosick, N. Y.-Vt. quadrangle.)
   Existing project. This provides for channel widening for 3,300
feet, for removal of White Dam and channel excavation for 700
feet, and for construction of earth levees and concrete walls on both
banks of the river. The principal structures involved are rein-
forced concrete floodwalls approximately 900 feet in length on the
right bank and 700 feet in length on the left bank, an earth levee
approximately 2,400 feet in length along the right bank, an emer-
gency outlet section in the right bank flood wall, relocation of
Woods Brook in a concrete flume, and interior drainage structures.
   The current estimated Federal cost for new work (1954) is
$1,070,000, exclusive of land and other work to be provided by
local interests at an estimated cost of $96,000.
   The existing project was authorized by the Flood Control Act
approved June 22, 1936, and modified by the Flood Control Act
approved August 18, 1941. (See H. Doc. 182, 76th Cong., 1st sess.,
which contains the latest published map.)
   Local cooperation. Fully complied with.
   Operation and results during fiscal year. Preparation of final
engineering reports was in progress at the end of the fiscal year.
The cost for engineering was $2,674 for new work.
   Condition at end of fiscal year. Construction work under the
existing project was commenced on May 28, 1950, and completed
on June 6, 1952. Final engineering reports remain to be done.
The total cost of the existing project to June 30, 1954, was
$1,042,605 for new work.
                                         Cost and financial smmary

                                                Fiscal year ending June 30                     Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                                  1950        1951        1952         1953        1954         prior to 1950
New work:
   Appropriated------......--.   $350, 000   $500, 000   $206, 000   -$47, 852   -- -...
                                                                                     -----         $1, 052, 148
    Cost-----------------          39, 943    514, 939    430, 128      16,856      $2, 674          1,042, 605

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954......------...-----..--......
    Unobligated balances available for succeeding fiscal year ending June 30,
                                                                                   .                 $9,543
      1955 -......................
                               ---.- --- ---------... .-. --..
                       .....--.--                          .... ........   .......   9 ,543

              31. NORTH ADAMS, HOOSIC RIVER                               BASIN, MASS.
  Location. The Hoosic River rises in northwestern Massachu-
setts, flows generally north and northwest, crossing the southwest
corner of Vermont to the vicinity of Eagle Bridge, N. Y., where it
turns west and joins the Hudson River about 16 miles above Troy,
           FLOOD CONTROL-NEW YORK, N. Y., DISTRICT              149
N. Y. It is 66 miles long and has a drainage area of 713 square
miles. North Adams, Mass., is situated on the Hoosic River about
14 miles below the source of the river. (See U. S. Geological
Survey map covering Greylock, Mass.-Vt., quadrangle.)
   Existing project. This project provides for local channel im-
provement which would extend through the entire city for a dis-
tance of 9,100 feet along the North Branch, 8,100 feet along the
South Branch, and 12,100 feet along the main stream downstream
from the junction and including Braytonville. On the North
Branch the improvements would consist of a debris basin above
the Eclipse Dam; closure walls at the proposed new Hoosac Cotton
Mill Dam and a rectangular paved concrete chute. On the South
Branch, the improvements would consist of a closure levee with
a check dam and stilling basin; raising of the Boston & Albany
Railroad track; a new trapezoidal earth channel with levee; an
improved trapezoidal and rectangular earth channel with levee
and walls; and a rectangular paved concrete chute. At the junc-
tion, the improvements would consist of a rectangular concrete
chute to a drop structure and stilling basin below Brown Street;
closure levees; and rock-paved and improved earth channels. At
Braytonville the improvements would consist of a rock-paved
trapezoidal channel; a levee; an improved trapezoidal channel
with levee; and a new dam and stilling basin with closure levee.
Other work appurtenant to the project would involve bridge re-
construction and approaches; street and utility relocations; in-
terior drainage; and miscellaneous alteration, construction, and
demolition works.
    The estimated Federal cost for new work (1954) is $15,700,000,
exclusive of land and other work to be provided by local interests at
an estimated cost of $2,080,000.
    The existing project was authorized by the Flood Control Act
approved June 22, 1936, and modified by the Flood Control Act ap-
proved August 18, 1941. (See H. Doc. 182, 76th Cong., 1st sess.,
which contains the latest published map.)
    Local cooperation. In addition to the usual requirements for
local cooperation as provided by law, local interests are required
to give assurances satisfactory to the Secretary of the Army
that they will insure against future encroachments upon the
flood channels to be provided by the improvements. General
assurances of local cooperation in the entire project were execu-
ted by the mayor of North Adams on December 15, 1949. The
assurances were approved on March 3, 1950. In accordance
with a law enacted by the Commonwealth of Massachusetts in
1950, the State Department of Public Works on November 21,
1950, furnished general assurances of local cooperation on the
part of the State in the project, with the exception of operation
and maintenance of the project within the city of North Adams
which remains a responsibility of the city under assurances pre-
viously furnished by the city of North Adams. Lands, easements,
and rights-of-way for the first and second units of construction
were acquired by local interests on March 9, 1950, and March
27, 1952, respectively.    Acquisition of lands, easements, and
rights-of-way for the third unit of construction is in progress.
 150                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Local interests contributed $54,000 on June 9, 1950; $55,000 on
June 17, 1952; $4,000 on October 6, 1952; and $900 on December
2, 1952, a total of $113,900 for local work in connection with the
first and second units of construction.
    Operations and results during fiscal year. Preparation of con-
tract plans and specifications was in progress and model tests were
completed for the third unit of construction involving channel
excavation and concrete chute upstream of the second unit for
600 feet on the South Branch and 5,350 feet on the North Branch.
The cost for preliminary engineering was $30,315 for new work.
    Condition at end of fiscal year. Contract plans and specifica-
tions for the first and second units of construction and model
studies for the first, second, and third units have been completed.
Construction work under the existing project was commenced on
July 31, 1950, and is about 8 percent complete. The first unit of
construction, consisting of channel excavation, drop structure and
stilling basin, concrete walls and paving downstream from Brown
Street Bridge below the junction of North and South Branches,
was completed on May 29, 1952. The second unit of construction,
consisting of channel excavation, and construction of concrete
chute, concrete walls, and bridge abutments from Brown Street
Bridge upstream to the junction of the North and South Branches,
was completed on December 3, 1952. Preparation of plans and
specifications, model studies, and the construction of protective
works for the remainder of the project remain to be done. The
total cost of the existing project to June 30, 1954, exclusive of
$108,753 contributed funds, was $1,211,929 for new work.
                                           Cost and finan ial svmmary
                                               UNITED STATES FUNDS

                                                     Fiscal year ending June 30                          Total to June
                                                                                                        30, 1954, includ-
                                                                                                        ing fiscal years
                                    1950          1951           1952         1953            1954        priorto 1950
New work:
   Appropriated----........        $350, 000     $350, 000     $400, 000   -----------------------                  000
                                                                                                            1 $1,183,
    Cost-           -
            --------------           74, 415      187,214       459,554       378,845         30, 315          1,211,929

  1Exclusive of $32,000 borrowed.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954.............
                                                                 -----------     -- 28,929
    Uinobligated balances available for succeeding fiscal year ending June
    30, 1955 .......
                  .... .............
                                ....................
                                               . .............................
                                             ...                                 --28 ,929
    Estimated additional amount needed to be appropriated for com-
                                                                        .......14,517,000
      pletion of existing project.....................--------------------.......
                                               CONTRIBUTED FUNDS

                                                    Fiscal year ending June 30                          Total to June
                                                                                                        30, 1954, includ-
                                                                                                         ing fiscal years
                                    1950          1951          1952          1953            1954        priorto 1950
New work:
    Contributed-------- ------------
    Cost ........ ..--------------------------
                                                  $54, 000
                                                   36,708
                                                             - $11, _978      $59, 900
                                                                               60,067
                                                                                          -
                                                                                         ------------
                                                                                                   108, 753
                                                                                                                $113, 900


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 ..................------------
                                                                              5,147
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955.- .....
                 ............
                            .......-.
                                   ................. .......                  5 ,147
                                                                        ........-
                                                               ................--
            FLOOD CONTROL-NEW YORK, N. Y., DISTRICT             151
            32. ADAMS, HOOSIC RIVER BASIN, MASS.
   Location. The Hoosic River rises in northwestern Massachu-
setts, flows generally north and northwest, crossing the southwest
corner of Vermont to the vicinity of Eagle Bridge, N. Y., where it
turns west and joins the Hudson River about 16 miles above Troy,
N. Y. It is 66 miles long and has a drainage area of 713 square
miles. Adams, Mass., is situated on the Hoosic River about 6 miles
below the source of the river. (See U. S. Geological Survey map
covering Greylock, Mass.-Vt., quadrangle.)
   Existing project. This provides for channel improvements, for
a distance of approximately 2.2 miles, with floodwalls on both
banks of the stream from high ground below Plunkett Dam to a
proposed weir above Commercial Street; a concrete paved chute
or flume from this weir to a proposed stilling basin above the
mouth of the Tophet Brook and below Hoosac Street; an improved
earth channel with floodwalls, earth levees, a closure levee and
structure and two check dams from the mouth of Tophet Brook
to Lime Street; and a concrete chute drop structure and stilling
basin on Tophet Brook from Hoosac Street to junction with Hoosic
River. Other work appurtenant to the project involves alteration
of existing raceways, bridge reconstruction, street and utility re-
locations, and channel improvement of tributary brooks.
   The estimated Federal cost for new work (1954) is $5,580,000,
exclusive of land and other work to be provided by local interests
at an estimated cost of $647,000.
   The existing project was authorized by the Flood Control Act
approved August 18, 1941. (See H. Doc. 182, 76th Cong., 1st sess.,
which contains the latest published map.)
   Local cooperation. In addition to the usual requirements for
local cooperation as provided by law, local interests are required
to give assurances satisfactory to the Secretary of the Army
that they will insure against future encroachments upon the
flood channels to be provided by the improvements. General
assurances of local cooperation in the entire project were ex-
ecuted by the Board of Selectmen, town of Adams, on Novem-
ber 22, 1949. The assurances were approved on January 31,
1950. In accordance with a law enacted by the Commonwealth
of Massachusetts in 1950, the State Department of Public Works
on November 21, 1950, furnished general assurances of local co-
operation on the part of the State in the project, with the excep-
tion of operation and maintenance of the project in the town of
Adams which remains a responsibility of the town under assur-
ances previously furnished by the town of Adams.             Lands,
easements, and rights-of-way for the first and second units of
construction were acquired by local interests on March 29, 1950,
and March 27, 1952, respectively. Requisition of lands, easements
and rights-of-way for the third unit of construction is in progress.
Local interests are engaged in preliminary work to acquire lands,
easements, and rights-of-way for the fourth and fifth units of con-
struction. The sum of $11,200 was contributed by local interests
on June 1, 1950, for local utility relocation and bridge abutments
accomplished under the first unit of construction.
   Operations and results during fiscal year. Contract plans and
152             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

specifications for the third unit of construction involving channel
excavation and concrete walls from the downstream end of the
first unit for a distance of about 800 feet were completed during
the fiscal year.
   Model tests for the fourth unit of construction involving channel
excavation and concrete chute from below Hoosac Street to the
upstream limit of the project were in progress at the end of the
fiscal year.
   The cost for preliminary engineering was $45,070 for new work.
   Condition at end of fiscal year. Construction of the existing
project was commenced on June 23, 1950, and is about 17 percent
complete. The first unit of construction, consisting of channel
excavation and paving, construction of a drop structure and still-
ing basin and concrete walls in the middle portion of the project
downstream from Hoosac Street and Tophet Brook from its mouth
to Mill Street, was completed April 3, 1952. The second unit of
construction, consisting of channel excavation and paving and
construction of concrete walls on Tophet Brook from Mill Street
to Hoosac Street, was completed on November 20, 1952. Prepara-
tion of plans and specifications, model studies, and the construction
of protective works for the remainder of the project remain to be
done. The total cost of the existing project to June 30, 1954, ex-
clusive of $10,725 contributed funds, was $853,484 for new work.

                                           Cost and financial stonmar!i
                                            UNITED STATES FUNDS

                                                     Fiscal year ending June 30                              Total to June
                                                                                                            30, 1954, includ-
                                                                                                            ing fiscal years
                                   1950           1951           1952           1953           1954           prior to 1950
New work:
    Appropriated_--------         $350, 000      $245, 000      $225, 000        (1)                              (1)844, 000
    Cost................            35, 146       376, 180       213, 447       160, 2.50       45, 070              853, 484

  1 Exclusive of $20,000 borrowed.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 ...............                                       8--9,484
    Appropriated for succeeding fiscal year ending June 30, 1955...........                                      560,000
    Unobligated balances available for suicceeding fiscal year ending
      June 30, 1955-.......................... ...............................
                                                                 .          .....................                550,516
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project-.. .. ........... ...........                         .................     4 ,176 ,000

                                              CONTRIBUTED FUNDS


                                                     Fiscal year ending June 30                              Total to June
                                                                                                            30, 1954, includ-
                                                                                                            ing fiscal years
                                    1950           1951          1952           1953           1954           prior to 1950
New work:
     Contributed---------......... -----------    $11, 200 --------------------------------                        .$11,   200
     Cost---------------------------                   35 - - $10,366-----10,                                              72----------10,725


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954...................               $475
    Unobligated balances available for succeeding fiscal year ending June 30,
                             ........ ............. ..... ............
      1955.........................                                          ............. 475
                    FLOOD CONTROL-NEW YORK, N. Y., DISTRICT                                                       15'
                    33. INACTIVE                FLOOD CONTROL                     PROJECTS

                                                           For last        Cost to June 30, 1954           Estimated
                                                          full report                                       amount
                   Name of project                             see                                          required
                                                           annual            Con-         Operation            to
                                                            report        struction         and            complete'
                                                             for-                        maintenance
1. Bennington, Hoosic River Basin, Vt-------....            1941    __-      ___ _-..         -.         --. $1, 450, 000
2. East Barre Reservoir Winooski River Basin,
            ----------------------------------
      Vt......                                               1951           $82,901 ----------                 3, 527,100
3. Lamoille River, Vt.                                      1939
                                           ----__..................______... 49,837 --------.......               153,200
4. Proctor, Otter Creek Basin, Vt-----.........__1937 -_____-__-____--__---- --                      __-       4 119, 000
5. Rutland, Otter Creek, Vt----------..........--..--_      1952            82, 388 -____-------              4, 257, 600
6. Waterbury Reservoir, Winooski River
      Basin, Vt.---....------------------------              1951             9, 253           5 $1, 494          780, 700
7. Waterbury, Winooski River Basin, Vt___--_                1951       _______-___ _-_-_-            -1       3, 300, 000
8. Waterford, Hudson and Mohawk Rivers,
      N. Y. ...---------------------------                   1939   ....-------- 1-------------                1, 720,000
9. WR.
    Winooski River, Vt----------------------                 1940        4, 897, 427             1               (7)
10. Wrightsville    Reservoir,     Winooski River
      Basin, Vt....-----------------------------1951                           44, 640             -          2, 505, 400


  1 Revised in 1954.
  2 Unit of project completed.
    Includes $23,507 Emergency Relief funds.
  4Completion not desired by local interests.
  ' Costs incurred in fiscal year 1954, for scheduling of reservoir operations and preparing charts of monthly
reservoir regulation.
  ' Awaiting local cooperation.

  ? Completed.

                               34. GENERAL INVESTIGATIONS
   Examinations and surveys. During the fiscal year the total cost
for examinations and surveys was $147,708, excluding $26,467
contributed funds for beach erosion studies. The examination
and survey costs include $865 for navigation studies, $26,667 for
beach erosion cooperative studies, and $120,176 for special studies
 (New England-New York Resources Survey).
   The total expenditures for general investigations were $145,065
for examinations and surveys ($120,176 for the NENYIAC survey,
$865 for navigation studies and $24,024 for beach erosion coopera-
tive studies).
   The unexpended balance at the end of the fiscal year in the
amount of $18,529, exclusive of $41 unexpended contributed funds
for beach erosion cooperative study, will be applied as follows:
     Navigation studies .........................           $725
     Beach erosion cooperative study ...............          41
     NENYIAC resources study ..................           17,763
        Total ..................................        $18,529
  The additional sum of $262,000, including $246,000 for
NENYIAC resources study and $16,000 for navigation studies,
can be profitably expended during fiscal year 1955.
   Collection and study of basic data. During the fiscal year the
total costs for collection and study of basic data were $2,927. The
costs include $756 for flood emergency studies and $2,171 for flood
investigations.
  The total expenditures for collection and study of basic data
were $2,927.
154             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  The unexpended balance of $73 at the end of the fiscal year will
be applied to collection and study of basic data.
  The work performed during the fiscal year in connection with
the collection and study of basic data included the revision of the
District Flood Emergency Manual and the collection and analysis
of flood information at locations where formal reports have not
been specifically directed by Congress.
    35. INSPECTION OF COMPLETED FLOOD CONTROL WORKS
   Inspections of completed local flood control works are per-
formed periodically to determine the extent of compliance by
local interests with the requirements for operation and main-
tenance. During the fiscal year inspections were made of the
completed works at Adams, Mass.; East Barre Reservoir, Vt.;
Hoosick Falls, N. Y.; Montpelier Dam, Montpelier, Vt.; North
Adams, Mass.; Waterbury Reservoir, Vt.; and Wrightsville Res-
ervoir, Vt. Responsible local officials were advised of deficiencies
in operation and maintenance and corrective measures have been
proposed.
   The cost during the fiscal year was $300 for maintenance.
   The total costs to June 30, 1954, were $1,100 for maintenance.
                                          Cost and financial summary

                                                       Fiscal year ending June 30                       Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                                   1950              1951       1952         1953         1954          prior to 1950

Maintenance:
   Appropriated...
             --------------------                      $400 ------------        $400         $300                $1, 100
   Cost....-------------- ------------------------                     386          414          300              1, 100
                      FLOOD CONTROL-NEW YORK, N. Y., DISTRICT                                                                           155
  36. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION

   Snagging and clearing of navigable streams and tributaries in
the interests of flood control (section 13 of the 1946 Flood Control
Act)
   During the fiscal year the following work was performed: The
contract initiated in fiscal year 1953 for snagging and clearing
of Esopus Creek in the vicinity of Mt. Tremper and Shandaken,
N. Y., was completed at a cost of $39,840; preparation of con-
tract plans and specifications for snagging and clearing of Dock
Hill Brook, N. Y., was initiated at a cost of $830; and contract
plans and specifications for snagging and clearing of Pompton
River, Passaic River Watershed, N. J., was initiated at a cost
of $3,918.
   The total costs incurred during the fiscal year were $44,588
for new work.
   The total costs for all snagging and clearing work to June 30,
1954, were $250,280 for new work.
                                               Cost and financial summary

                                                             Fiscal year ending June 30                                        Total to June
                                                                                                                              30, 1954, includ-
                                                                                                                              ing fiscal years
                                        1950              1951              1952              1953              1954            prior to 1950

New work:
   Appropriated--------........         $89, 000        -$5, 677            $41, 366          $41,662           $49, 880              $301, 032
   Oost----------------                  69, 271          39, 821            80, 585          10, 648            44, 588               250, 280


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 ...........----------------- $50,702
    Unobligated balances available for succeeding fiscal year ending June 30,
        1955..........--...........----........................................---------------------------------------------....     50,702
  IMPROVEMENTS OF RIVERS AND HARBORS IN THE
          PHILADELPHIA, PA., DISTRICT

  This district comprises a portion of southeastern New York,
eastern Pennsylvania, western and southern New Jersey, north-
ern and southeastern Delaware, and a small part of northeast-
ern Maryland embraced in the drainage basin of the Delaware
Bay and River system and those basins tributary to the Atlantic
Ocean from Manasquan River, N. J., inclusive, to the south boun-
dary of Delaware. It also includes the Chesapeake and Dela-
ware Canal and the approach channel thereto in Chesapeake Bay
and Elk River, Md.
                                                    IMPROVEMENTS

                        Navigation                                               Navigation-Continued
1. Delaware River between Phila-                           12. Cold Spring Inlet, N. J .......---...                     178
       delphia, Pa., and Trenton,                           13. Absecon Inlet, N. J-..................                    180
       N . J ....--         -------------------------   157 14. Tuckerton Creek, N. J...............                      182
2. Delaware River, Pa., N. J., and                         15. Barnegat Inlet, N. J.........                             183
       Del., Philadelphia, Pa., to                          16. Manasquan River, N. J ........                            185
       the se a -------------------...................  160 17. New Jersey Intracoastal Water-
3. Delaware River at Camden,                                     way .....................                               187
       N . J .........-........-....................    164 18. Inactive navigation projects......---                     190
4. Schuylkill River above Fair-
       mount Dam, Pa.....................               165                       Flood Control
5. Schuylkill River, Pa................                166
6. Wilmington Harbor, Del ...........                  168 19. Bear Creek Reservoir, Lehigh
7. Inland Waterway from Dela-                                    River, Pa.. .......... . ... ............ .             190
       ware River to Chesapeake                             20. Allentown, Lehigh River, Pa.....                          191
       Bay, Del. and Md.................                171 21. Inactive flood control projects.                          192
8. Murderkill River, Del ........                _.... 173 22. General Investigations ....                               192
9. Indian River Inlet and Bay,                             23. Inspection of completed proj-
       Del ....................................         174       e c t s . .. . .. .. . .. . .. .. . .. . . ..........   193
10. Cooper River, N. J.. .. ..                     .. _ 176 24. Flood control work under special
11. Mantua Creek, N. J .......--..                      177       authorization _....-                      .--- .        193


     1. DELAWARE                   RIVER BETWEEN PHILADELPHIA,                                           PA., AND
                                         TRENTON, N. J.

   Location. This river has its source in southeastern New York,
flows in a general southerly direction 367 miles, forming the
boundary line between the States of New York and New Jersey
on the east and Pennsylvania and Delaware on the west, and
empties into Delaware Bay. (See U. S. Coast and Geodetic Sur-
vey Charts Nos. 1218, 280, 294, 295, and 296.)
   Previous projects. Adopted by River and Harbor Acts of June
10, 1872; March 3, 1875; June 14, 1880; July 5, 1884; August 18,
1894; March 2, 1907; June 25, 1910; July 25, 1912; June 5, 1920;
and March 3, 1925. For further details see page 1778 of the
Annual Report for 1915, page 311 of the Annual Report for
1924,1 page 220 of the Annual Report for 1934, and page 296,
Annual Report for 1938.
   Existing project. This provides for a channel 28 feet deep and
                                                                                                                 157
 158                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

300 feet wide from Allegheny Avenue, Philadelphia, to the Penn-
sylvania Railroad bridge at Delair; thence 25 feet deep and 300
feet wide to the upper end of the municipal marine terminal at
Trenton, including a turning basin 500 feet wide and 1,700 feet
long at the terminal; widening the 25-foot channel at bends
above Delair; and the maintehance of a channel 12 feet deep and
200 feet wide from the upper end of the 25-foot channel to the
Pennsylvania Railroad bridge at Trenton, dredged under a pre-
vious project. The project also provides for an auxiliary chan-
nel 20 feet deep and 200 feet wide east of Burlington Island ex-
tending easterly from the main channel to the upper end of the
United States Pipe & Foundry Co.'s property at East Burling-
ton, with a turning basin 450 feet wide at the upper end, an
anchorage 22 feet deep, 100 feet wide, and 400 feet long along
its west or landward side and 800 feet long along the west side
of the ship channel, opposite the mouth of Biles Creek, Pa., and
for the initial excavation only, of a cross channel 8 feet deep
and 200 feet wide through the artificial island opposite Delanco,
N. J. The total length of the section included in the project is
about 301/2 miles, excluding the auxiliary channel east of Bur-
lington Island which is 1.4 miles long, and the cross channel
opposite Delanco. The lower end is about 55 miles above the
mouth of the river at Liston Point and about 105 miles above the
harbor of refuge at the mouth of Delaware Bay. All depths
refer to the plane of mean low water. The mean tidal range
at Trenton is 6.7 feet, an increase of 1.3 foot since the completion
of the 25-foot channel. Freshets, which occur usually during
February and March, attain a height of 9 to 20 feet above mean
low water in the vicinity of Trenton. Navigation is occasionally
suspended during a portion of the winter months on account
of ice.
   The estimate of cost for new work, revised in 1954, is $5,248,000,
exclusive of amounts expended on previous projects and $15,000
contributed funds. The latest (1950) approved estimate for an-
nual cost of maintenance is $232,000.
   The existing project was authorized by the following River
and Harbor Acts:

       Acts                             Work authorized                                      Documents

July    3, 1930A channel 28 feet deep, 300 feet wide between Alle-              Rivers     and Harbors Committee
                gheny Ave., Philadelphia, Pa., and Delair bridge.                 Doec.   3, 71st Cong., 1st seas.
Aug. 30, 19352 Deepening the channel to 25 feet from Delair bridge              Rivers     and Harbors Committee
                to Trenton, N. J., and for maintenance of the 12-                 Doc.    11, 73d Cong., 1st sess.
                       foot channel from the upper end of the 25-foot proj-
                       ect to Pennsylvania     RR. bridge at Ferry St.,
                       Trenton.
       Do     .      Auxiliary channel, 20 feet deep, east of Burlington        Rivers and Harbors       Committee
                       Island.                                                 Doc. 66, 74th Cong., 1st sess.l
Aug. 26, 1937        A cross channel 8 feet deep, opposite Delanco, N. J.... Rivers and Harbors Committee
                                                                               Doec. 90, 74th Cong., 2d sess.
July 24, 1946        Anchorage at mouth of Biles Creek.....--------------....   H. Doc. 679, 79th Cong., 2d sess.

  1
  2Contains       latest published maps.
  Also Public Works Administration, Sept. 6, 1933, and Emergency Relief Administration, May 28, 1935.
       RIVERS AND HARBORS-PHILADELPHIA, PA., DISTRICT          159
   Recommended modifications of project. Under date of Novem-
ber 18, 1953, the Chief of Engineers recommended modifica-
tion of the existing project so as to provide for enlarging the
existing channel from Allegheny Avenue, Philadelphia, to the
Pennsylvania Railroad bridge at Delair, New Jersey, a distance
of 1.5 miles, to a depth of 42 feet in rock and 40 feet in other
material and a width of 400 feet, including relocation of the
channel at the railroad bridge and suitable reconstruction of the
bridge; for enlarging the existing channel from the railroad
bridge at Delair to the upstream end of Newbold Island, a dis-
tance of 22 miles, to a depth of 42 feet in rock and 40 feet in
other material and a width of 400 feet in the straight reaches
with suitable widening at bends; for deepening the existing chan-
nel from the upstream end of Newbold Island to the Trenton
Marine Terminal, including the turning basin, a distance of 5.5
miles, to 35 feet and widening the turning basin to 800 feet; for
constructing such bank protection works as may be necessary
and for eliminating the authorized anchorage near the mouth of
Biles Creek, Pennsylvania, all at an estimated cost to the United
States of $86,899,000 for construction and $759,600 annually for
maintenance in addition to that now required, subject to certain
conditions of local cooperation.     (H. Doc. No. 358, 83d Cong.,
2d sess.)
   Local cooperation. Fully complied with except that local inter-
ests are required to furnish suitable areas for disposal of dredged
material during maintenance as and when needed.
   Terminal facilities. There are 22 piers, wharves, and docks
within the improvement, exclusive of those within limits of city
of Philadelphia. The facilities are considered adequate for ex-
isting commerce. (For further details, see Port Series No. 9-
Revised 1947-Corps of Engineers.)
   Operationsand results during fiscal year. Under maintenance,
an adjustment was made to a contract for removal of shoals in
the 35-foot channel, completed the previous fiscal year, in the
amount of $3,853. Other maintenance costs were: miscellaneous
engineering, surveys, and channel examinations, $6,608, installa-
tion and operation of tide gage stations, $2,191, and miscella-
neous inspections and reports, $2,077, a total of $10,876.
   The cost for all work was $14,729 for maintenance.
   Condition at end of fiscal year. The existing project was about
99 percent complete. The channel between Philadelphia and
Trenton, including the channel east of Burlington Island, was
completed in 1937, and the cross channel opposite Delanco in
1939. The work remaining to be done is the dredging of the
anchorage at the mouth of Biles Creek.
   The latest examinations show minimum depths, at mean low
water, as follows:




     Sig 6-159-190
 160                  REPORT OF CHIEF OF EINGINEERS. U. S. ARMY. 1954


                                                                                                                                         Minimum depth

                                                                                                Project
        Date                                 Section                                             depth                     Left         Mid-                         Right
                                                                                                 (feet)                   outside    channel for                    outside
                                                                                                                          quarter    half project                   quarter
                                                                                                                        width (feet) width (feet)                    (feet)

March          1953    Allegheny Ave. to Delair bridge ..                                                    28                      28. 0               27. 8             27. 3
August         1953    Delair bridge to Newbold Island ..- -                                                 25                      21.7                22. 3             23.8
Sept.          1953    Newbold Island to Trenton Marine
                        Terminal .____ _ __----------------                                                  25                      10.0                11.2              11.3
Sept.          1953    Trenton Marine Terminal to Pennsyl-
                         vania Railroad bridge_-                                                             12                       8.2                 9.2               9.2
April          1951    Channel east of Burlington Island...                                                  20                       8.0                16.7               6. 5



    The total costs under the existing project were as follows:

                                                             Public works                       Emergency                              Regular                    Total
                                                                funds                           relief funds                            funds

New work ______________________                                        $2, 189, 956                  $2, 636, 456                         $363, 405                $5, 189, 817
Maintenance                                                            -------                           _                               1-----
                                                                                                                                         1, 740, 710                1, 740, 710

        Total__.           __________                                  $2, 189, 956                  $2, 636, 456                       $2, 104, 115               $6, 930, 527


  In addition, $15,000 contributed funds were expended for new
work.
  Deferred charges, undistributed, for the amortization of the
costs of disposal areas amount to $141,219.
                                                    Cost and financial srmmnar!l

                                                                       Fiscal year ending June 30                                                             Total to June
                                                                                                                                                             30, 1954, includ-
                                         1950                      1951                   1952                      1953             f       1954
                                                                                                                                                              ing fiscal years
                                                                                                                                                               prior to 1950

New work:
   A ppropriatedCs
           -_          -          ------------             ------------         -------------
                                                                                                                                                    _-            1$7,678,991
   Cost....... ....                -   - -   - -   - -        - -- -
                                                              -         -   -   - -   -     -    -   -       - -    -    -   -   -     -             -   _          7, 678, 991
Maintenance:
   Appropriated     _                  $145, 000         (.-$25,       000            $149, 319                    $687,500                   -$125                 2, 435, 157
   Cost. .     __                        36, 317                   80, 226              12, 624                     672, 270                 2 14, 292             22, 434, 218

  1 In addition, $15,000 contributed funds were expended for new work.
  2 Pending adjustment in the amount of $431 not included.


Other new work data: Estimated additional amount needed to be appropri-
   ated for completion of existing project............. ........................................ $58,200
2. DELAWARE                    RIVER, PA., N. J., AND DEL., PHILADELPHIA,                                                                                                 PA.
                                          TO THE SEA
   Location. See page 157, also United States Coast and Geodetic
Survey Charts Nos. 1218, 294, 295, and 280.
   Previous projects. Adopted by River and Harbor Acts of July
4, 1836; March 3, 1873; March 3, 1875; June 18, 1878; March 3,
1879; July 5, 1884; August 11, 1888; and March 3, 1899. For fur-
ther details, see page 1779 of Annual Report for 1915, and page
299, Annual Report for 1938.
   Existing project. This provides for a channel 37 feet deep
from Allegheny Avenue, Philadelphia, Pa., to the Philadelphia
Navy Yard, thence 40 feet to deep water in Delaware Bay, 800
feet wide in the straight reaches from Allegheny Avenue to a
point in Delaware Bay near Ship John Light, thence 1,000 feet
wide to deep water in Delaware Bay, with 1,200 feet width at
              RIVERS AND HARBORS-PHILADELPHIA,                               PA., DISTRICT               161
Bulkhead bar and 1,000 feet width at other bends and in Phila-
delphia Harbor; for an anchorage at Port Richmond 37 feet deep
and about 6,400 feet long; for an anchorage at Gloucester 30
feet deep and about 3,500 feet long; for an anchorage in the
vicinity of Mantua Creek 37 feet deep, 1,400 feet wide, and hav-
ing a mean length of 11,600 feet; and for an anchorage at Marcus
Hook 37 feet deep, 1,400 feet wide, and having a mean length of
10,500 feet. It also provides for the construction of dikes and
training works for the regulation and control of the tidal flow;
for straightening the channel and extending the 1,000-foot width
from Philadelphia Harbor to Horseshoe Bend; and for the main-
tenance of an area on the north side of the channel opposite the
Philadelphia Navy Yard between Shipway 3 and Schuylkill
River to a depth of 40 feet and a width of 150 feet on Mifflin
Range and 200 feet on West Horseshoe Range, and of any areas
dredged by local interests to a depth of 35 feet between the chan-
nel and a line 100 feet channelward of the pierhead line between
Point House wharf and the Philadelphia Navy Yard, when in
the opinion of the Chief of Engineers such areas are so located
as to be of benefit to general navigation. The total length of the
section included in the project is about 96.5 miles. All depths
refer to the plane of mean low water.
   The mean tidal range at various points on the river and bay
is as follows: Philadelphia, Pa., 6.0 feet; Chester, Pa., 5.7 feet;
New Castle, Del., 5.5 feet; Liston Point, Del., 5.8 feet; and Lewes,
Del., 4.1 feet. Under the influence of heavy and long-continued
winds the extreme tidal range is about 14 feet. The normal
maximum velocity of tidal currents in the dredged channel varies
between 2 and 31/2 miles per hour. Storm tides may increase the
maximum to as much as 41/2 miles per hour.
   The estimate of cost for new work, revised in 1954, is $34,184,-
000, exclusive of amounts expended on previous projects. The
latest (1950) approved estimate for annual cost of maintenance
is $6,165,000.
   The existing project was authorized by the following River
and Harbor Acts:


       Acts                        Work authorized                                    Documents

June 25, 1910     Channel 35 feet deep from Allegheny Ave., Phila-        H. Doc. 733, 61st Cong., 2d sess.
                   delphia, Pa., to Delaware Bay.
July     3,1930   Anchorages 35 feet deep at Port Richmond and            H. Doe. 304, 71st Cong., 2d sess.'
                   Mantua Creek, a 30-foot anchorage at Gloucester,
                   N. J., and extending the 1,000-foot channel width
                   in Philadelphia Harbor to Horseshoe Bend.
Aug. 30, 19352    An anchorage 35 feet deep at Marcus Hook, Pa-......     Rivers and Harbors Committee
                                                                            Doec. 5, 73d Cong., 1st sess.
June 20,1938      A channel 37 feet deep from Philadelphia-Camden         S. Doc. 159, 75th Cong., 3d sess.'
                   Bridge to the navy yard, thence 40 feet deep to deep
                   water in Delaware Bay.
Mar. 2, 1945      A 37-foot depth in channel from Allegheny Ave.,         H. Doc. 580, 76th Cong., 3d sess.'
                   Philadelphia, Pa., to Philadelphia-Camden Bridge
                   and in the anchorage at Port Richmond.
       Do-....... A 37-foot depth in and enlargement of anchorages        H. Doc. 340, 77th Cong., 1st sess.'
                   near Mantua Creek and Marcus Hook.
       Do....... Maintenance of enlarged channel opposite Philadel-       Specified in act.
                   phia Navy Yard. -

  SContains latest published maps.
  2 Also Public Works Administration, Sept. 6, 1933.
162      REPORT OF CHIEF OF ENGINEERS. I.    S. ARMY, 1954

   Recommended modifications of project. Under date of Novem-
ber 18, 1953, the Chief of Engineers recommended modification
of the existing project so as to provide for deepening the chan-
nel from the Philadelphia Naval Base to Allegheny Avenue,
Philadelphia, a distance of 8.5 miles. to 42 feet in rock and 40
feet in other material, with a width of 500 feet through Horse-
shoe Bend and 400 feet through Philadelphia harbor to Alle-
gheny Avenue, at an estimated cost to the United States of
$4,490,000 for construction with no additional cost for mainte-
nance, subject to certain conditions of local cooperation (H. Doc.
No. 358, 83d. Cong., 2d sess.)
   Local cooperation. The River and Harbor Act of June 20, 1938,
imposes the condition that the cities of Philadelphia and Camden
shall agree to dredge not less than 110,000 cubic yards annually
in maintaining the channel and anchorages in Philadelphia Har-
bor between Allegheny Avenue and the mouth of Schuylkill
River. This condition will become effective after completion of
initial dredging of the 40- and 37-foot channels below the Phila-
delphia-Camden Bridge.
   Terminal facilities. There are 244 wharves on the river be-
tween Allegheny Avenue, Philadelphia, and the sea, 188 located
on the waterfront of Philadelphia, Camden, and Gloucester and
55 below Philadelphia. Eight are owned by the United States,
5 by the States of Pennsylvania and New Jersey, 28 by munici-
palities, 78 by railroad companies, and 125 by private interests.
The public and railroad piers are open to public use, some free
and others on payment of charges. Most of the piers which are
equipped to handle general cargo have direct rail connections
with three railroad systems operating in the area. The facilities
are considered adequate for existing commerce. (For further
details, see Port Series Nos. 7 and 9-Revised, 1947-Corps of
Engineers.)
   Operations and results during fiscal year. Maintenance, con-
tract: A contract for maintenance dredging in Port Richmond
Anchorage was awarded May 27, 1954. To the end of the fiscal
year only preliminary work had been done. The costs were $823.
   Maintenance, hired labor: Dredging in the 40-foot channel was
in progress throughout the year. A total of 8,207,934 cubic
yards of material, place measurement, was removed by U.S. hop-
per dredges Comber, Essayons, Gerig, Goethals, and Langfitt, of
which 3,868,566 cubic yards were rehandled by U. S. pipeline
dredge Gillespie and 4,339,368 cubic yards were deposited outside
the channel limits. The costs were $2,578,341.
   Other hired labor costs were: Miscellaneous engineering, sur-
veys, and channel examinations, $89,868; model studies of shoal-
ing in Delaware River, $3,840, and studies of tidal flushing in
estuaries, $9,919, both by Waterways Experiment Station, Vicks-
burg, Miss.; and miscellaneous inspections and reports, $19,809;
a total of $123,437.
   Deferred charges amounting to $89,316, for maintenance of
disposal areas, were incurred, and $145,015 was charged off to
hopper dredging, making a net reduction of $55,699 in deferred
account.
              RIVERS AND HARBORS-PHILADELPHIA,                                                PA., DISTRICT                          163

   The amount of $10,000 was received during the fiscal year in
settlement of a Government claim for damages to Pea Patch
Island Dike caused by collision.
   The cost of all work was $2,636,903 for maintenance.
   Condition at end of fiscal year. The existing project was about
82 percent complete.      The 40-foot channel from Philadelphia
Navy Yard to the sea was completed in 1942. The enlarging
and deepening of Marcus Hook Anchorage was completed in
1947. The work remaining to be done is the completion of the
deepening and enlarging of Mantua Creek Anchorage, and the
deepening of the channel from Allegheny Avenue to the Phila-
delphia Navy Yard, including Port Richmond Anchorage, from
35 feet to 37 feet.
     The latest examinations show minimum depths, at mean
low water, available to navigation as follows:

                                                                                                   Miinimum depth

                                                                Project
    Date                       Section                          depth             Left              Left       Right                Right
                                                                 (feet)          outside           inside      inside         outside
                                                                                 quarter          quarter        uarter        qquarter
                                                                                                                                uarter
                                                                                  (feet)            (feet)      (feet)          (feet)
April 1954__    Allegheny   Ave. to Philadelphia-
                  Camden iridge ....   ..           ..                  8....
                                                                        37            33. 2           27.7          29. 3              25. 8
April 1954_     Philadelphia-Camden       IBridge  to
                  Navy Yard                                             37            32. 4           35. 2         33. 6              33. 2
June 1954---.   Philadelphia NavyYard-l to the Sea                      40            34. 2           36. 5         36. 8              35. 3




    The costs under the existing project were as follows:

                                                                    Public works                   Regular                  'ital
                                                                       funds                        funds

New work                               I                                        $813, 046          $27, 647, 563            $28, 460, 609
Maintenance                                                                                         68, 589, 117             68, 589, 117
     Total-------                                                                813, 046           96, 236, 680             '07,049, 726




  Deferred charges, undistributed, for the amortization of the
costs of disposal areas, amount to $1,011,107.
                                           ('Co. and     na   rial .CUwnry


                                                    Fiscal year ending June 30                                       Total to June
                                                                                                                    30, 1954, a includ-
                                                                                                                      ing fiscal year
                                1950              1951           1952                 1953              1954           prior to 1950


New work:
   Appropriated                                                                                                      .--     41, 436, 666
   Cost _                                                                                                                    415,436, 666
Maintenance:
   Appropriated-........ $3, 705, 411         $4, 133, 849    $3, 905, 449        $1, 823, 156      $3, 036, 350,            71, 092, 101
   Cost_ ___              3, 679, 898          3,178, 964      3, 941,639           1, 647, 540     22, 661, 795            270, 650, 525


  1Includes $12,976,058
                      for new work and $1,025,409 for maintenance for previous projects.
  2 Pending adjustment in the amount of-$24,892 not included,

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project_                        $5 ,723,400
164               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                      3. DELAWARE RIVER AT CAMDEN, N. J.
   Location. Camden, N. J., is located on the east bank of the
Delaware River, directly opposite the city of Philadelphia, Pa. It
is about 51 miles above the mouth of the river and about 101 miles
above the harbor of refuge at the mouth of Delaware Bay. (See
U. S. Coast and Geodetic Survey Charts Nos. 295 and 280.)
   Previous projects. Adopted by River and Harbor Act of June
25, 1910. No work was done on this project. For further details,
see page 321, Annual Report for 1932.
   Existing project. This provides for dredging in front of Cam-
den to a depth of 18 feet from that depth north of Cooper Point to
Berkley Street and 30 feet from the latter point to Newton Creek,
with the depth increased to 37 feet in front of the Camden marine
terminals, these depths extending from the ship channel in Dela-
ware River to a line parallel with and 50 feet distant from the
established pierhead line, and the 37-foot depth in front of the
Camden marine terminals extending about 2,900 feet along the
inshore side and about 5,100 feet along the ship channel. All
depths refer to the plane of mean low water.
   The distance from Cooper Point to Berkley Street is about 1.5
miles, and from Berkley Street to Newton Creek is about 2.5 miles.
The lower end of the project is about 99 miles above the harbor of
refuge at the mouth of Delaware Bay.
   The mean tidal range is 6.0 feet and the extreme tidal range un-
der the influence of prolonged heavy winds is about 14 feet.
   The estimate of cost for new work, revised in 1954, is $1,155,000,
exclusive of $15,000 contributed funds. The latest (1950) estimate
for annual cost of maintenance is $60,000.
   The existing project was authorized by the following River and
Harbor Acts:
       Acts                        Work authorized                              Documents

Mar.    2,1919    A depth of 30 feet from Newton Creek to Kaighn     H. Doc. 1120, 63d Cong., 2d sess.
                   Point, thence 18 feet to Cooper Point.
July    3, 1930   Extending the 30-foot depth upstream to Berkley    H. Doc. 111, 70th Cong., 1st sess.
                   St. terminal.
Mar.    2, 1945   A depth of 37 feet in front of the Camden marine   H. Doc. 353, 77th Cong., 1st sess.
                   terminals.

1 Contain latest published maps.


   Local cooperation. Fully complied with.
   Terminal facilities. There are 60 piers, wharves, and docks
along the Delaware River waterfront at Camden, including 3 oil
terminals on Pettys Island. Two are modern terminals designed
for overseas and domestic general cargo, and are open to all car-
riers on equal terms. They are the Beckett Street terminal, owned
by the South Jersey port district, and the Spruce Street municipal
pier, owned by the city of Camden. The piers have direct railroad
connections. The facilities are considered adequate for existing
commerce. (Fol further details, see Port Series No. 7-Revised
1947-Corps of Engineers.)
   Operations and results during fiscal year. Under maintenance,
surveys and channel examinations were made.                                    The costs were
$2,070.
           RIVERS AND HARBORS-PHILADELPHIA, PA., DISTRICT                                                            165
   Condition at end of fiscal year. The existing project was about
55 percent complete. The work remaining to be done is the deep-
ening of the area in front of the Camden Marine Terminal from 30
feet to 37 feet. The latest examination (April 1954) indicates that
project depths are well maintained in the completed portion of the
project except near Cooper Point at the northerly end, and that the
minimum depth in the 37-foot project depth area in front of the
terminal is 27.1 feet.
   The costs under the existing project, excluding $15,000 con-
tributed funds expended for new work, were $462,906 for new work
and $234,815 for maintenance, a total of $697,721.
                                       Cost and financial summary

                                               Fiscal year ending June 30                                  Total to June
                                                                                                          30, 1954, includ-
                                                                                                           ing fiscal years
                                1950         1951           1952          1953              1954            prior to 1950
New work
   Appropriated            __              - -          I   _-            _           i     _1                    $462,906
   Cost.-                              -           .-
                                           .. ......-            _-..
                                                                   ... .... ...      ._-_
                                                                                        _ .. ...                   462,906
Maintenance:
   Appropriated---------        $22, 000   $-20, 000         $-700        $46, 300
                                                                                           2"$1, 878...
                                                                                       -                            234, 816
   Cost_         -  -                363         923           739         44, 287                                ' 234, 623

  1 In addition $15,000 contributed funds were expended for new work.
  2 Pending adjustments in the amount of $193 not included.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project.......--------------------------........ $692,100

        4. SCHUYLKILL RIVER ABOVE FAIRMOUNT                                                   DAM, PA.
   Location. Schuylkill River has its source in Schuylkill County,
Pa., and flows southeasterly 150 miles to the Delaware River at
Philadelphia, Pa. (See U. S. Geological Survey quadrangle sheets
of Pennsylvania.)
   Existing project. This provides for the improvement of the
Schuylkill River above Fairmount Dam in the interest of naviga-
tion and other purposes by the removal of culm deposits from the
pools formed by Plymouth Dam, Flat Rock Dam, and Fairmount
Dam.
   The estimate of cost for this work, revised in 1954, is $4,589,000.
   The existing project was authorized by the River and Harbor Act
of July 24, 1946 (H. Doc. 529, 79th Cong., 2d sess.). The latest pub-
lished maps are contained in the project document.
   Local cooperation. Fully complied with.
   Operationsand results during fiscal year. New work, contract:
Preliminary work, including preparation of disposal area, laying of
pipeline, and assembling of dredges was completed. Dredging to
remove culm from Fairmount Pool commenced April 8, 1954, and
was in progress at the end of the fiscal year. A total of 1,730,000
cubic yards, place measurement, of material was reported removed.
The work is about 57 percent completed. The costs were $1,886,668.
   An adjustment was made to a contract for the removal of culm
from Plymouth and Flat Rock pools, completed in fiscal year 1953,
in the amount of $28,378.
   The cost of all work was $1,858,290 for new work.
   Condition at end of fiscal year. The existing project was about
166          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

52 percent complete. Construction of disposal areas for culm to be
removed from Plymouth and Flat Rock Pools and removal of culm
from Plymouth and Flat Rock Pools have been completed. The
work remaining to be done is the completion of the removal of culm
from Fairmount Pool.
   The costs under the project were $3,073,531 for new work.
                                   Cost and financial summary

                                             Fiscal year ending June 30                          Total to June
                                                                                                30, 1954, includ-
                                                                                                ing fiscal years
                            1950            1951          1952        1953           1954        priorto 1950

New work:
   Appropriated   --------
                       $365, 000       _                1,900, 000   $994, 000     $500, 000          $3, 794, 000
   Cost_                     42, 476       $310, 786       14, 334    823, 599   11, 858, 590        '3, 073, 831


  SPending adjustment in the amount of -$300       not included.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954___                                          $77,188
    Appropriated for succeeding fiscal year ending June 30, 1955..............                        795,000

                             5. SCHUYLKILL RIVER, PA.
   Location. This river has its source in Schuylkill County, Pa.,
flows in a general southeasterly direction 150 miles, and empties
into the Delaware River at Philadelphia, Pa. (See U. S. Coast and
Geodetic Survey Charts Nos. 295 and 280.)
   Previous projects. Adopted by River and Harbor Act of July
11, 1870, and modified April 26, 1892. (For further details, see
page 325, Annual Report for 1932.)
   Existing project. This provides for a channel 33 feet deep and
400 feet wide in Delaware River to the mouth and within the river
to 29th Street, three-fourths mile above the mouth; thence the
same depth and 300 feet wide to Passyunk Avenue Bridge, 31/2
miles above the mouth; thence 26 feet deep and 200 feet wide to
Gibsons Point, 41/2 miles above the mouth; and thence 22 feet deep
and 200 feet wide to University Avenue Bridge, 6 miles above the
mouth, including widening at bends. The total length of the sec-
tion included in the project is about 61/~ miles. All depths refer to
the plane of mean low water. The mean tidal range at the mouth
is 5.9 feet and at Grays Ferry Bridge about one-half mile below
University Avenue Bridge, 6.4 feet. The extreme tidal range, due
to freshets and prolonged heavy winds, is about 14 feet.
   The estimated cost for new work, revised in 1954, is $2,805,000,
exclusive of amounts expended on previous projects. The latest
 (1950) approved estimate for annual cost of maintenance is
$966,000, in addition to $1,300,000 required to restore project depth
below Passyunk Avenue Bridge as provided by the River and Har-
bor Act of July 3, 1930, and $1,036,000 for the restoration of proj-
ect depths above Passyunk Avenue Bridge as provided by the
River and Harbor Act of July 24, 1946.
   The existing project was authorized by the following River and
Harbor Acts:
            RIVERS AND HARBORS-PHILADELPHIA, PA., DISTRICT                                              167
     Acts                         Work authorized                                    i)ocuments

Aug. 8, 1917    Depths of 35 feet from mouth to Girard Point, thence      H. Doc. 1270, 64th Cong., 1st sess.
                  30 feet, 26 feet, and 22 feet to University Ave.
                  Bridge, Philadelphia.
July 3, 1930    A depth of 30 feet instead of 35 feet between the mouth   Rivers and Harbors Committee    t
                  and Girard Point, and the conditional restoration        Doec. 40, 71st Cong., 2d sess.
                  and maintenance of the channel below Passyunk
                  Ave., by the United States.                                                                 1
July 24, 1946   A depth of 33 feet from the channel in Delaware Riv-      H. T)oc. 699, 79th Con., 2d sess.
                 er to Passyunk Ave., restoration of the project
                  channel dimensions between Passyunk Ave., and
                  University Ave., and full maintenance of the
                  entire project.

1 Contains latest published   maps.


   Local cooperation. The River and Harbor Act of July 24, 1946,
imposed the condition that the city of Philadelphia agree to remove
60,000 cubic yards (place measurement) of material annually from
that portion or those portions of the project which the District En-
gineer may designate until such time as adequate municipal sew-
age-treatment works are constructed and placed in effective opera-
tion. This condition is being satisfactorily complied with. All
other requirements have been fully complied with.
   Terminal facilities. There are 43 wharves located within the
limits of the improvement. These terminals are considered ade-
quate for existing commerce. (For further details, see Port Series
No. 7-Revised 1947-Corps of Engineers.)
   Operations and results during fiscal year. Maintenance, con-
tract: Dredging in the channel between Passyunk Avenue and
University Avenue bridges was commenced February 17 and com-
pleted April 27, 1954. There were removed 395,280 cubic yards,
place measurement, of material at a cost of $340,158.
   Maintenance, hired labor: Dredging in the 33-foot channel be-
tween Delaware River and Passyunk Avenue bridge by the U. S.
hopper dredge Comber was in progress from July 1 to August 14,
1953. There were removed 143,224 cubic yards, place measure-
ment, of material. The costs, including rehandling with a United
States pipeline dredge, were $196,693.
   Other costs were: Miscellaneous engineering, surveys, and chan-
nel examinations, $13,368, and miscellaneous inspections and re-
ports, $4,387, a total of $17,755.
   The cost of all work was $554,606 for maintenance.
   In compliance with local cooperation requirements, the city of
Philadelphia dredged a total of 16,280 cubic yards of material from
the channel during the fiscal year.
   Condition at end of fiscal year. The existing project was about
98 percent complete. The 33-foot channel from Delaware River to
Passyunk Avenue Bridge was completed in 1949. The work re-
maining to be done is the removal of a few rock shoals above
Passyunk Avenue Bridge.
   The latest examinations show minimum depths, at mean low
water, available to navigation as follows:
168                REPORT        OF      CHIEF      OF ENGINEERS.                U.     S.      ARMY,            1954



                                                                                                   Minimum depths
                                                                 Project
       Date                            Section                    depth                 Left                 Mid-               Right
                                                                  (feet)              outside             channel for          outside
                                                                                      quarter             half project         quarter
                                                                                       (feet)            width       (feet)     (feet)




May 1954..... Delaware River to 29th St ..........                         33                22. 9                   28. 4               26. 2
   Do-........29th St. to Passyunk Ave._                                   33                23. 0                   26. 6               23. 3
June 1954......Passyunk Avenue to Gibson Pt....                            26                22. 7                   21. 8               21.5
      Do........ Gibson Pt. to University Avenue ..                        22                   12. 1                14. 1               11. 0


  The costs under the existing project were $2,753,038 for new
work and $10,048,108 for maintenance, a total of $12,801,146.
                                             Cost and financial summary

                                                    Fiscal year ending June 30                                            Total to June
                                                                                                                        30, 1954,1 includ-
                                                                                                                         ing fiscal years
                                      1950        1951         1952              1953                     1954            priorto 1950

New work:
      Appropriated_ _.            $--97, 963                                                                                  $3, 278, 038
      Cost......---------.....       70, 487---------------------------                         ------------                   3, 278,038
Maintenance:
      Appropriated ........           125, 078   $926, 000    $404, 643         $885, 070               $329, 000             10, 079, 905
      Cost..........      ------ 261, 249         914, 824    421, 246           627, 771               2 553, 086            10, 046, 589

  1 Includes $525,000 for new work and $0 for maintenance for previous projects.
  2 Pending adjustment in the amount of $1,520 not included.
Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project...........-...........................
                                                                     $52,000

                                 6.    WILMINGTON             HARBOR,                 DEL.


      Location.This harbor is formed by Christina River, which
rises in New Castle County, Del., flows northeasterly 16' miles,
passing through the city of Wilmington, Del., and empties into
Delaware River about 29 miles below Philadelphia, Pa. (See U. S.
Coast and Geodetic Survey Chart No. 294.)
   Previous projects. Work was done on Christina River from
1836 to 1838. The original project was adopted by River and
Harbor Act of July 11, 1870, and modified by River and Harbor
Acts of March 3, 1881, and July 5, 1884. For further details, see
page 1785 of Annual Report for 1915 and page 308 of Annual Re-
port for 1938.
   Existing project. This provides for a channel 30 feet deep and
400 feet wide in Delaware River to the mouth of Christina River
and within the river to Lobdell Canal, three-fourths mile above the
mouth; thence 21 feet deep and 250 feet wide to the mouth of
Brandywine River, 11/ miles above the mouth; thence the same
depth and 200 feet wide to the pulp works, 33/4 miles above the
mouth; thence decreasing to a depth of 10 feet in 750 feet to the
Pennsylvania Railroad bridge No. 4; and thence 7 feet deep and
100 feet wide to Newport, 9 miles above the mouth, including an
inner basin 30 feet deep formed by widening the channel to an
average width of 600 feet and extending upstream from the mouth
to Lobdell Canal. It also provides for the removal of about 1,200
feet of the outer end of a stone-filled, pile- and timber-crib jetty
constructed 2,150 feet long on the north side of the entrance; for
              RIVERS AND HARBORS-PHILADELPHIA, PA., DISTRICT                                                   169
a steel-sheet pile jetty 2,300 feet long, with 120-foot inshore wing,
on the south side of the entrance, and for a V-shaped stone-filled pile
and timber jetty at the mouth of Brandywine River, 430 feet long
on the Brandywine side and 260 feet long on the Christina side.
The total length of the section included in the project is about 91/2
miles. All depths refer to the plane of mean low water. The mean
tidal range at the mouth is 5.6 feet, and at Newport 3.9 feet. The
extreme tidal range due to prolonged heavy winds is about 13 feet.
   The estimate of cost for new work, revised in 1954, is $1,287,000,
exclusive of amounts expended on previous projects. The latest
 (1950) approved estimate for annual cost of maintenance is
$400,000.
The existing project was authorized by the following River and
Harbor Acts:

       Acts                             Work authorized                                       Documents
June    3, 1896 1Depths of 21, 10, and 7 feet and jetties__                    _ (fH. Doc. 66, 54th Cong,. 1st sess.;
Mar.    3,1899     J                                                               Annual Report, 1896, p. 973; An-
                                                                                 M nual Report, 1897, p. 1250.1
July 25, 1912          Purchase or construction of a dredge and auxiliaries,     H. Doc. 359, 62d Cong., 2d sess.
                        including a wharf and depot, and maintenance of
                        the project.
Sept. 22, 1922 1 Entrance channel and basin with 25-foot depth and (H. Doc. 114, 67th Cong., 1st sess.,
Mar. 3, 1925      construction by local interests of the new south    and Senate committee print, 68th
                   J jetty.                                                         Cong., 1st sess.
July    3, 1930        A 30-foot depth between Delaware River and the             Rivers and Harbors Committee
                        Lobdell Canal and modification or removal of a              Doc. 20, 71st Cong., 2d sess.
                        portion of the north jetty.
Aug. 30, 19352     Completion of the new south jetty by the United                Rivers and Harbors Committee
                    States; subject to the provision that the city of               Doc. 32, 73d Cong., 2d sess.
                        Wilmington shall reimburse the United States for
                        the cost, without interest, of any part of the struc-
                        ture that may subsequently be occupied and uti-
                     lized for city activities.
Oct.    17, 1940   Permit temporary occupancy by the city of Wil-                 H. Doc. 658, 76th Cong., 3d sess.
                        mington of any part of the south jetty for city ac-
                        tivities under revocable license, provided the occu-
                        pied portion of the jetty is properly maintained
                        without expense to the United States.

1 Contains latest published map.
2 Also May 28, 1935, under Emergency Relief Administration.


   Local cooperation. Fully complied with.
   Terminal facilities. A modern marine terminal is located just
inside the entrance to the harbor. This terminal is operated for the
city of Wilmington by a board of harbor commissioners, and is open
to all on equal terms. Railroad connection on the terminal wharf
provides for direct interchange of freight between car and ship.
There are 29 other wharves and landings within the Christina
River which forms the harbor. The facilities are considered ade-
quate for existing commerce. (For further details, see Port Series
No. 8-Revised 1947-Corps of Engineers.)
   Operations and results during fiscal year. Maintenance dredg-
ing in the channel between Delaware River and Lobdell Canal was
in progress at intervals during the fiscal year. There were re-
moved 434,000 cubic yards, place measurement, of material by
U.S. hopper dredges Gerig and Langfitt at a cost of $135,179, and
448,695 cubic yards, place measurement, of material by U.S. pipe-
line dredge Gillespie at a cost of $144,277.
   Other maintenance costs were: Miscellaneous engineering, sur-
veys, and channel examinations, $1,624; miscellaneous inspections
170                 REPORT                OF CHIEF OF ENGINEERS.                                            U. S. ARMY, 1954


and reports, $651; and operation of a stream gage at White Clay
Creek, near Newark, Del., in cooperation with United States
Geological Survey, $311; a total of $2,586.
   The cost of all-work was $282,042 for maintenance.
   Condition at end of fiscal year. The existing project was about
99 percent complete. The channel above Lobdell Canal and the
V-shaped stone-filled pile and timber jetty at the mouth of the
Brandywine River were completed in 1901. Removal of about
1,200 feet of the outer end of a stone-filled pile and timber jetty on
the north side of the entrance was completed in 1931. The steel
sheet-pile jetty, 2,300 feet long with a 120-foot inshore wing, on
the south side of the entrance was completed in 1936. The harbor
channel was completed to a width of 400 feet in 1931. The work
remaining to be done is deepening the inner basin from 25 to 30
feet.
  The latest examinations show minimum depths, at mean low
water, as follows
                                                                                                                            Minimum depth
                                                                                            Project
      Date                                          Section                                 depth               Left                 Mid-                 Right
                                                                                             (feet)           outside             channel for            outside
                                                                                                              quarter             half project           quarter
                                                                                                               (feet)             width (feet)            (feet)
June 1954-.----Delaware River to Lobdell Canal....                                                 30               27. 9                 26. 4                  24.0
July 1949------Lobdell Canal to Brandywine River_                                                  21                                    114. 2
    Do --.     Brandywine River to Market St ..__                                                  21                                    1____________
                                                                                                                                          15. 0
    Do _...... Market St. to pulp works.........------------                                       21 ----                               1 16. 0
    Do........ Pulp works to Pennsylvania R.R.                                                     10    -                                1 6.0      .
                 Bridge No. 4.
    Do_____ Pennsylvania R.R. Bridge No. 4 to                                                          7                     -           11 6.   1
                           Newport.

1 In 80 percent of project width.

  The costs under the existing project, excluding $60,000 con-
tributed funds expended for maintenance, were as follows:
                                                                                                   Emergency                     Regular
                                                                                                   relief funds                   funds                  Total
New work ........----                                                                                      $206, 177               $924, 356             $1, 130, 533
M aintenance ... ..           ..   ...-----                  -- -     -------                                                     7, 852, 622              7, 852, 622
      Ta :a l . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . .                                    8, 776, 978
                                                                                                            206, 177                                      8,983, 155


                                                        (o1 (and f/i1011(01 s walvylO!/

                                                                      Fiscal year ending June 30                                                 Total to June
                                                                                 ,                 ,                    ,                        30, 1954, includ-
                                                                                                                                                 ing fiscal years
                                               1950                 1951                 1952               1953                                  prior to 19502
New work:.
   Appropriated                                        ~~   -- - -
                                                     ----~ ------             - -- - ----- -
                                                                            ---                        -- - - - -                                        $1, 532, 654
   Cost--....-----                             --       --    --    --------      -----                -
                                                                                                   ------
                                                                                                   - -    -     -   -                                     1, 532, 654
Maintenance:
   A pproprialtdd                             $340, 000            $475, 000           $264, 200           $396, 000             $297, 000                7,934, 477
    (Cs                                        322, 869             489, 985            266, 781            329, 134             3 268, 976              S7, 839, 556


   I Inl.ies $402,121 for new work for previous Ir3  oj(cts.
    ItsIn1 ition
             1 $00,000  contri)buted funds were exi1pnd'.d for mai0tenance.
   S'(Prii:  adjustlne(nt in the amount of $13,066(not included.

Other new work data: Estimated additional amount ieedde to bIeaplro-
  priated for completion of existing project... __....._ __.__  .                                                                                        156 ,500)
        RIVERS AND HARBORS-PHILADELPHIA,         PA., DISTRICT    171
       7. INLAND WATERWAY FROM DELAWARE RIVER TO
                CHESAPEAKE BAY, DEL. AND MD.
    Location. This waterway begins at Reedy Point on Delaware
  River, about 41 miles below Philadelphia, Pa., and passes through
the sea level Chesapeake & Delaware Canal, a distance of 14 miles,
to Back Creek, at Chesapeake City, Md. It then passes for 5 miles
  down Back Creek, thence 9 miles down Elk River to Chesapeake
Bay and thence 18 miles down Chesapeake Bay to a point near
Pooles Island. A branch channel connects Delaware River at Dela-
ware City, Del., with the main channel at a point about 112 miles
west of Reedy Point. (See U. S. Coast and Geodetic Survey Charts
Nos. 294, 1226, 570, and 572.)
    Previous projects. The River and Harbor Act of August 8,
1917, made appropriation for preliminary studies with a view to
taking over the Chesapeake & Delaware Canal. The River and
Harbor Act of March 2, 1919, provided for the purchase of the
Chesapeake & Delaware Canal. The River and Harbor Acts of
January 21, 1927, and July 3, 1930, provided for dredging in Back
Creek, Md., and the construction of bridges and roadways. For
further details, see Annual Report for 1934, page 242, and Annual
Report for 1938, page 312.
    Existing project. This provides for a sea-level channel to ac-
commodate vessels drawing 25 feet and having a depth of 27 feet
and a width of 250 feet from Delaware River to Elk River and
thence 400 feet wide down Elk River and Chesapeake Bay to deep
water at or near Pooles Island; alteration of existing bridges over
the canal; extension of the entrance jetties at Reedy Point; the
enlargement of the anchorage and mooring basin in Back Creek to
afford an area about 400 feet wide, 1,000 feet long, and 12 feet
deep, including provision of sluice gates at the fixed highway
bridge; dredging the Delaware City Branch Channel to a depth of
8 feet and a width of 50 feet; deepening the existing basin to the
same depth; revetment of both banks east of Fifth Street Bridge;
and construction of bulkheads.
    The project also provides for the construction of a four-lane
high-level fixed highway bridge across the canal at or near St.
Georges, Del., of such type, design, and clearance for navigation as
are approved by the Chief of Engineers.
    The total length of the section included in the project, excluding
the Delaware City Branch Channel, which is about 2 miles long,
is about 46 miles. All depths refer to the plane of mean low water
in Delaware River. The mean tidal range at the Delaware River
entrance is 5.4 feet and in Elk River at the mouth of Back Creek,
2.2 feet. The extreme tidal range is from 6.3 feet above mean high
water to 3.0 feet below mean low water.
   The estimate of cost for new work, revised in 1954, is $14,682,-
000. The latest (1950) approved estimate of cost for annual main-
tenance is $825,000, including $225,000 for operation and care of
the waterway.
   The existing project was adopted by the River and Harbor Act
of August 30, 1935 (H. Doc. 201, 72d Cong., 1st sess., and Rivers
and Harbors Committee Does. 18 and 24, 73d Cong., 2d sess.).
  The act approved August 7, 1939 (Public Law 310, 76th Cong.,
172      REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

1st sess.), authorized the construction of a four-lane high-level
fixed highway bridge at or near St. Georges, Del.
   The latest published map of the canal is found in Rivers and
Harbors Committee Document No. 24, 73d Congress, 2d session.
Operation and care of the canal and appurtenant works were in-
cluded in the project July 1, 1935, under the provisions of the
Permanent Appropriations Repeal Act approved June 26, 1934.
   Recommended modifications of project. Under date of August
17, 1953, the Chief of Engineers recommended modification of the
existing project so as to provide for a depth of 35 feet over a bot-
tom width of 450 feet in the main channel of the waterway, includ-
ing a cut-off at the Pennsylvania Railroad crossing; a minimum
radius of curvature of 7,000 feet at bends; a high-level, fixed
bridge with vertical clearance of 135 feet and horizontal clearance
of 600 feet at the railroad crossing over the cut-off, the bridge
after completion to be owned and maintained by the railroad
company; high-level bridges to replace the highway bridges at
Summit and Reedy Point, with vertical clearances of 135 feet,
horizontal clearances of 500 feet, four traffic lanes at Summit, and
two traffic lanes at Reedy Point, provided that consideration shall
be given at the, time of construction of the project to provision of
more economical, alternative facilities to meet the needs of the
Reedy Point area in lieu of the high-level bridge; an anchorage
basin in Elk River 35 feet deep and 1,200 feet wide, with an aver-
age length of 3,700 feet; and revetment of the banks as necessary,
all at a cost to the United States of $96,000,000 for construction,
and $410,000 annually for maintenance in addition to that now re-
quired. (S. Doc. 123, 83d Cong., 2d sess.)
   Local cooperation. Fully complied with.
   Terminal facilities. Ample mooring facilities at the eastern
and western ends of the canal and bulkheads at Delaware City and
St. Georges have been constructed by the United States. A harbor
for small boats has been provided and a wharf has been con-
structed at Chesapeake City. The facilities are considered ade-
quate for existing commerce.
   Operations and results during fiscal year. Maintenance, con-
tract: Repair of 10 tieup dolphins at Reedy Point was commenced
June 7, 1954, and was in progress at the end of the fiscal year. The
costs were $185.
   Maintenance, hired labor: General operation of the waterway
was continued throughout the year at a cost of $200,894. Opera-
tion and maintenance of the bridges crossing the waterway was
continued throughout the year at a cost of $119,894. Maintenance
dredging by U.S. hopper dredge Gerig was in progress from Au-
gust 26 to September 30, 1953, and from March 21 to April 30,
1954. A total of 733,319 cubic yards, place measurement, of ma-
terial was removed at a cost of $220,966.
   Preliminary work in connection with stabilizing the piers of
Summit Bridge was in progress during the fiscal year at a cost of
$1,330.
   Other hired labor costs included: Maintenance and repairs to
banks, $38,495; drainage of banks, $22,764; maintenance and re-
pair of auxiliary works, $42,589; removal of obstructions and de-
             RIVERS AND HARBORS-PHILADELPHIA, PA., DISTRICT                                                                                173
bris, $22,765; miscellaneous engineering, surveys, and channel
examination, $25,783; and miscellaneous inspections and reports,
$2,882, a total of $155,278.
   The cost of all work was $698,547 for maintenance.
   Condition at end of fiscal year. The existing project was prac-
tically complete. The 27-foot channel was completed in 1938 and
the four-lane high-level fixed highway bridge at St. Georges in
1942. The work remaining to be done is deepening the Delaware
City Branch Channel from 6 feet to 8 feet from a point 400 feet
east of Fifth Street Bridge to its junction with the canal.
   The latest examinations show minimum depths, at mean low
water, as follows:

                                                                                                           Minimum depth
                                                                               Project
      Date                             Section                                 depth                Left               Mid-            Right
                                                                                (feet)             outside          channel for       outside
                                                                                                   quarter          half project      quarter
                                                                                                    (feet)          width (feet)       (feet)
June 1954 ...--  Delaware River to Elk River..-. .-                                   27                20. 5              23.0              20.5
April 1954....-- Elk River to Chesapeake Bay......                                    27                21.0                20. 6            18. 3
Decentbr 1946 Delaware City Branch Channel_                                            8            __-----------          1 1. 1


  1 In 80 percent of project width.


    The total costs under the existing project were as follows:

                                                                                     Emergency                  Regular
                                                                                     relief funds                funds                Total

New Work----......--        _---------------------------..
                                  _                                          $4, 756, 248                       $9, 788,338         $14, 544, 586
Maintenance....----- ----------            -----            ___
                                                         -------- --------
                                                                    ...              _                          13, 775,237          13, 775, 237
Operating and care-.....---------   -----------------------             ..-------------......                    6, 514, 588          6, 514, 588

       Total ..       ..-----
                           .....-----------------------------------.........               4, 756, 248         30, 078, 164           34, 834, 412


  Deferred charges, undistributed, for the amortization of the
costs of disposal areas, amount to $424,469.
                                              Cost and financial summary


                                                          Fiscal year ending June 30                                            Total to June
                                                                                                                              30, 1954, includ-
                                                                                                                               ing fiscal years
                                      1950              1951              1952               1953                   1954        prior to 1950
New work:
   Appropriated .-           _       -- $2, 650 -------------------                  ------------.------------                      $25, 254, 341
        --------------
    Cost_                               16, 444 .......                   ....              ....              ....                   25,254,341
Maintenance:
   Appropriated ....                   923, 000     -$130, 000        $1, 051, 130          $810, 000          $710, 000             27, 643, 395
   Cost...------- ------.           1, 127,153        -25, 591            501,165            959, 820          2 698, 784           2 27, 618, 280


  1 Includes $10,709,755 for new work and $6,903,748 for maintenance for previous projects.
  2 Pending adjustment in the amount of -$237 not included.


Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project-----------------------..................................................... $137,400

                                     8. MURDERKILL RIVER, DEL.
  Location. This river rises in Kent County, Del., flows north-
easterly 19 miles through the county, and empties into Delaware
174          'REPORT     OF CHIEF OF ENGINEERS, U. S. ARMY                                    1954

Bay about 25 miles above Cape Henlopen.        (See U. S. Coast and
Geodetic Survey Chart No. 1218.)
   Existing project. This provides for a channel 7 feet deep at
mean low water, 150 feet wide in Delaware Bay to the mouth, and
thence 80 feet wide to Frederica, 71, miles above the mouth. The
total length of the section included in the project is about 81,
miles. The mean tidal range at the mouth is 4.9 feet and at
Frederica 2.5 feet. The extreme tidal range is from about 1 foot
below mean low water to about 2 feet above mean high water.
   The estimate of cost for new work, revised in 1954, is $124,900.
The latest (1950) approved estimate for annual cost of main-
tenance is $7,800.
   This project was authorized by the River and Harbor Act of
July 13, 1892 (H. Ex. Doc. 21, 52d Cong., 1st sess., and Annual
Report for 1892, p. 981). The latest published map is in House
Document No. 1058, 62d Congress, 3d session.
   Local cooperation. None required.
   Terminal facilities. There are a number of light timber
wharves on both sides of the river near the mouth and two wharves
at Frederica, all of which are privately owned. The facilities are
considered adequate for existing commerce.
   Operations and results during fiscal year. Under maintenance,
surveys and channel examinations were made at a cost of $865.
   Condition at end of fiscal year. The existing project was about
63 percent complete. A channel 7 feet deep and 60 feet wide from
Delaware Bay to Frederica was completed in 1911. The work re-
maining to be done is the widening of the channel to project width.
The latest examinations show controlling depths at mean low
water as follows: In June 1954, in Delaware Bay, to the mouth,
3.3 feet; and thence, in June 1945, to Frederica, 5.0 feet. The
costs under the existing project were $37,630 for new work and
$205,469 for maintenance, a total of $243,099.
                                   Co.st afd fnancial summrnnar

                                                Fiscal year ending June 30                         Total to June
                                                                                                  30, 1954, Includ-
                            1950            1951                  1952       1953      1954        prior to 1950
New work:
   Appropriated                                       I                                                    $37, 630
   Cost                                     -         i              -                                      37, 630
Maintenance:
   Appropriated .    .    $-- 13, 000      $--2.291                          $1, 083   $2. 500             207, 104
   Cost                      12, 164 - -         -        ............   i    1,083    1 1.0633          <206, 238
1 Pending adjustment in the amount of -$768 not included.

Other new work data: Estimated additional amount needed to be appro-
                                                        ---..
  priated for completion of existing project ..................... . $86,400

                    9. INDIAN RIVER INLET AND BAY, DEL.
   Location. Indian River rises in Sussex County, Del., flows' est-
erly 13 miles into Indian River Bay which is a shalllow lagoon
6 miles long and 2 miles wide on the Delaware Coast about mid-
way between Cape Henlopen and the Maryland State line. The
inlet is an opening through the barrier beach separating Indian
              RIVERS AND HARBORS-PHILADELPHIA,                                  PA., DISTRICT               175
River Bay and the Atlantic Ocean. (See U. S. Coast and Geo-
detic Survey Chart No. 1219.)
   Previous projects. Adopted by River and Harbor Act of Au-
gust 2, 1882. For further details, see page 744, Annual Report
for 1888.
   Existing project. This provides for the fixation of the inlet by
the construction of two parallel jetties of steel sheet pile and
stone design extending to approximately the 14-foot depth curve
in the ocean, and for dredging an entrance channel 15 feet deep
and 200 feet wide, for a distance of 7,000 feet inshore from the
jetties; thence a channel 9 feet deep, 100 feet wide in the bay,
and 80 feet wide in the river, to and including a turning basin
9 feet deep, 175 feet wide, and 300 feet long at Old Landing;
thence a channel 4 feet deep and 60 feet wide to the highway
bridge at Millsboro. The project also provides that the interior
channel dimensions may, in the discretion of the Chief of Engi-
neers, be modified as may be found desirable to increase the
hydraulic efficiency of the channel, without increasing the cost.
The total length of the section included in the project is about
  33/ miles. All depths refer to the plane of mean low water.
The mean tidal range in the ocean at the inlet is 3.8 feet, and at
the highway bridge inside the inlet, 2.4 feet. The extreme tidal
range at the highway bridge is about 6 feet.
   The cost for new work for the completed project was $511,210,
exclusive of amounts expended on previous projects and exclu-
sive of $210,000 contributed funds. The latest (1950) approved
estimate for annual cost of maintenance is $36,000.
   The existing project was authorized by the following River
and Harbor Acts:

       Acts                          Work authorized                                     Documents
Aug. 26), 1937     A 15-foot inlet channel, steel and stone jetties, 6-foot   Rivers and Harbors Committee
                    channel from end of inlet channel to deep water in         Doc. 41, 75th Cong., 1st sess.'
                    the bay and authority to modify interior inlet
                    channel.
Mar.     2, 1945   A 9-foot channel from inlet to Old Landing, includ-        H. Doc. 330, 76th Cong., 1st sess.'
                    ing basin, and 4-foot channel to highway bridge at
                    Millsboro.


  'Contains latest published maps.


  Local cooperation. Fully complied with except that local inter-
ests are required to furnish suitable areas for disposal of
dredged material during maintenance as and when needed, and
provide terminal facilities.
   Terminal facilities. There is a privately owned basin with
berthing facilities for small boats located about three-fourths
mile west of the highway bridge near the inlet and one-quarter
mile north of the inlet channel connected therewith by a channel
6 feet deep and 40 feet wide; a United States Coast Guard wharf
on the north side of the inlet channel in the same locality; and
two wharves at Oak Orchard in Indian River Bay. The facilities
are considered adequate for existing commerce.
  Operations and results during fiscal year. Under maintenance
surveys and channel examinations were made at a cost of $3,674.
  Condition at end of fiscal year. The existing project was corn-
176            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

pleted in 1951. A channel 15 feet deep and 200 feet wide from
the ocean to a point 7,000 feet inshore from the ocean shoreline
was completed in 1938. The construction of two parallel jetties
spaced 500 feet apart, each 1,566 feet long with inshore end sec-
tions of steel sheet pile construction reinforced with stone, the
north jetty 904 feet long and the south jetty 890 feet long, and
the outshore end sections of all stone construction, was com-
pleted in 1939. The channel 9 feet deep, 100 feet wide in the
bay and 80 feet wide in the river, to and including a turning
basin 9 feet deep, 175 feet wide, and 300 feet long at Old Land-
ing, thence a channel 4 feet deep and 60 feet wide to the highway
bridge at Millsboro was completed in 1951.
   The controlling depths, at mean low water, were as follows:
In June 1954, through the inlet to the entrance to the small boat
harbor, 9.1 feet; thence, in June 1951, to Old Landing, 9.9 feet;
and thence, in -February 1951 to Millsboro, 6.1 feet.
   The costs under the existing project, excluding $210,000 con-
tributed funds expended for new work, were $511,210 for new
work and $265,718 for maintenance, a total of $776,928.
                                     Cost and financial summary

                                            Fiscal year ending June 30                           Total to Junel
                            __30,                                                                 19541, includ.
                                                                                                ing fiscal years
                              1950         1951            1952           1953       1954        prior to 19502
New work:
   Appropriated
   Cost...
                  .------    $320, 000   $-75, 200        $-3, 709    _                                $521, 210
                               24, 117     205, 686         11, 288                                        210
                                                                                                        521,
Maintenance:
   Appropriated_       _       20, 000                _      4, 863        $1, 000   $6, 000            268, 044
   Cost----_   _______             672      20, 000          4, 863         1, 000   t 4, 404     '     266, 448

  1 Includes $10,000 for new work for previous projects.
  2 In addition $210,000 contributed funds were expended for new work.
  ' Pending adjustment in the amount of -$730 not included.


                                    10. COOPER RIVER, N. J.
  Location. This river rises in Camden County, N. J., flows
northwesterly 13 miles, passing through the northern part of
the city of Camden, and empties into Delaware River opposite
the central portion of Philadelphia, Pa. (See U. S. Coast and
Geodetic Survey Charts Nos. 280 and 295.)
  Existing project. This provides for a channel 12 feet deep at
mean low water and 70 feet wide in Delaware River to the mouth
and within the river to what was formerly Browning Chemical
Works, 11/2 miles above the mouth. The total length of the section
included in the project is about 18/4 miles. The mean tidal range
at the mouth is 6 feet. The extreme tidal range is about 14 feet.
  The cost for new work for the completed project was $33,102.
The latest (1950) approved estimate for annual cost of mainte-
nance is $13,500.
  The existing project was adopted by the River and Harbor Act
of June 3, 1896 (H. Doc. 176, 53d Cong., 3d sess., and Annual Re-
port for 1895, p. 1102 et seq.). The latest published map is in
House Document 134, 63d Congress, 1st session.
   Local cooperation. None required.
            RIVERS AND HARBORS-PHILADELPHIA, PA., DISTRICT                                                        177
   Terminal facilities. There are 10 wharves on the river, all in
the city of Camden; 9 are privately owned and 1 is owned by the
city. The facilities are considered adequate for existing commerce.
   Operationsand results during fiscal year. Under maintenance,
a survey and channel examination was made at a cost of $2,643.
   Condition at end of fiscal year. The existing project was com-
pleted in 1920. The latest examinations, in September 1953, show
controlling depths at mean low water as follows: From Delaware
River to Pennsylvania Railroad bridge, 9.8 feet; and thence to
the upper end of the project, 8.6 feet.
   The costs under the existing project were $33,102 for new work
and $235,988 for maintenance, a total of $269,090.
                                              Cost and financial summary

                                                      Fiscal year ending June 30 _.                     Total to June
                                                           _30,                                           1954, includ-
                                                                                                        ing fiscal years
                                        1950        1951             1952              1953   1954       prior to 1950
New work:
   Appropriated...-------------                                ..........
                                         ------------------------         ------------------------              $33, 102
   Cost     .        ---       ---------
                      ...----------          --------------------- ---------------- ---------                    33,102
Maintenance:
   Appropriated..------_                $70, 000   $-2, 092 ---------------------             $2, 643           235, 988
   Cost.............-----------------     3, 701     64, 207 -----------------------           2, 643           235, 988


                                          11. MANTUA              CREEK, N. J.
   Location. This creek rises in Gloucester County, N. J., flows
northwesterly 161/2 miles and empties into Delaware River about
10 miles below Philadelphia, Pa. (See U. S. Coast and Geodetic
Survey Charts Nos. 280 and 295).
   Previous projects. Adopted by River and Harbor Act of Au-
gust 2, 1882; and modified in 1889. For further details, see page
1784, Annual Report for 1915, and page 342, Annual Report for
1938.
   Existing project. This provides for a channel 20 feet deep and
110 feet wide from that depth in Delaware River to the Grasselli
chemical plant of E. I. du Pont de Nemours & Co., a distance of
5,400 feet; thence 12 feet deep and 100 feet wide to the plant of
the Strathmann Sand & Gravel Co., 5,900 feet; thence 10 feet deep
and 60 feet wide to Friars Landing, 2,000 feet; and thence 7 feet
deep and 60 feet wide to Parkers Landing near Mount Royal, 2
miles; a dredged cutoff 3 feet deep and 50 feet wide across a bend
in the creek 9,000 feet above Mount Royal; and twin jetties at the
mouth of the creek. The section of the creek included in the exist-
ing project extends from Delaware River upstream 7 miles to 1
mile below the town of Mantua. All depths refer to the plane of
mean low water. The mean tidal range at the mouth is 5.9 feet; at
Paulsboro, 5 feet; at Mount Royal, 4.6 feet; and at Mantua, 3.5
feet. The extreme tidal range is about 10 feet.
   The cost for new work for the completed project was $166,687,
exclusive of amounts expended on previous projects. The latest
 (1950) approved estimate for annual cost of maintenance is
$13,800.
The existing project was authorized by the following River and
Harbor Acts:
 178                        RE'ORT OF CHIEF OF ENGINEERS, U. S. ARMY. 1954


       Acts             i                                       Work authorized                                                  Documents

Mar.     3, 1899            A channel of 12-foot, 8-foot,                  and 7-foot depth to Park-                H. Doec. 123, 55th Cong., 2d sess.
                             ers Landing, cutoff above                     Mount Royal, and jetties                   Annual Report 1898, p. 1122.1
                             at mouth.
Mar. 2, 1907                A dike across old mouth.                                             -                  Specified in act.
Aug. 30, 1935               A channel of 12-foot and                         10-foot depth to Friars                Rivers and Harbors Committee
                             Landing.                                                                                Doc. 14, 73d Cong., 1st sess.'
June 20, 1938               A channel of 20-foot depth                     to the Grasselli chemical                H. Doc. 505, 75th Cong., 3d sess.'
                             plant.

   These documents and H. Doc. 523, 61st Cong., 2d sess., contain the latest published maps.

   Local cooperation. Fully complied with except that local inter-
ests are required to furnish suitable spoil disposal areas for main-
tenance as required.
   Terminal facilities. There are nine wharves of pile and timber
construction on this stream. The facilities are considered ade-
quate for existing commerce.
  Operations and results during fiscal year. Under maintenance,
a survey and channel examination was made at a cost of $482.
   Condition at end of fiscal year. The existing project was com-
pleted in 1940. The jetties at the mouth were completed in 1913
and the channel dredging in 1940. The controlling depths, at
mean low water, were as follows: In September 1953, from Dela-
ware River to I. P. Thomas and Son Co. wharf, 12.0 feet; thence,
in December 1948 to Grasselli Chemical Plant, 10.3 feet; thence,
in June, 1945, to the highway bridge at Paulsboro, 11.1 feet;
thence, in April 1942, to Friars Landing, 11.5 feet; thence to
Parkers Landing, 6.5 feet; and thence to Mantua, 0.5 foot.
  The costs under the existing project were $166,687 for new
work and $183,825 for maintenance, a total of $350,512.
                                                                  Cost and financial summary

                                                                             Fiscal year ending June 30                                       Total to June
                                                                                                                                             30, 1954, includ-
                                                                                                                                             ing fiscal years
                                                       1950                1951           1952                 1953             1954          prior to 1950

New work:
   A p prop riated .                .        .         . .                                       -                                                   $169, 687
                                                                                                                                                      169, 687
   CostCt------------                   --       ------------       -------------------      ----    ------------       -----                         6,8


Maintenance:
    Appropriated _                    .                $-(000           $- 6, 291                                                      482            183, 825
    C ost..----- -               ----- j                2,111             56, 598 i__________           .
                                                                                                        --.....--.
                                                                                                                .                      482            183, 825

  I Includes $3,000 for new work for previous projects.

                                                    12. COLD SPRING INLET, N. J.
   Location. This inlet is located in Cape May County, southern
New Jersey, about 3 miles east of Cape May City and about 16
miles northeast of Delaware Breakwater. The inlet connects Cape
May Harbor and New Jersey Intracoastal Waterway with the
Atlantic Ocean and is about 1 mile in length. ( See U. S. Coast and
Geodetic Survey charts Nos. 234, 827, and 1219.)
   Existing project. This provides for an entrance channel 25
feet deep and 400 feet wide, protected by two parallel jetties, and
extending from the 25-foot depth curve in the Atlantic Ocean to a
               RIVERS AND HARBORS--PHILADELPHIA, PA., DISTRICT                                              179
line 500 feet harborward of a line joining the inner ends of the
jetties; thence 20 feet deep and 300 feet wide to deep water in
Cape May Harbor. The total length of the section included in
the project is about 21/4 miles. The mean tidal range at the
inner ends of the jetties is 4.3 feet. The extreme tidal range,
due to ocean storms, is about 11 feet.
   The cost for new work for the completed project was $879,275,
exclusive of $100,000 contributed by local interests and $50,000
Navy Department funds. The latest (1950) approved estimate
for annual cost of maintenance is $48,000.
   The existing project was authorized by the following River and
Harbor Acts:

        Acts                         Work authorized                                   Documents

M ar.     2, 1907   An inlet channel 25 feet deep and jetties        -         H. Doc. 388, 59th Cong., 2d sess.
Mar.      2, 1945   A 20-foot channel to deep water in harbor    ....----------H. Doc. 262, 77th Cong., 1st sess.'


  IThis     document and Annual Report for 1911, p. 1382, contain the latest published maps.

   Local cooperation. All cooperation required under the act of
1907 has been completed, except the work of deepening and en-
larging the inner harbor, which is 80 percent complete.
   Terminal facilities. Wharves with docking facilities for com-
mercial fishing vessels and fishing party boats are located on the
inner end of the harbor at Cape May. There is also a well-
equipped marine railway adjoining the fish dock, a number of
small wharves for private craft and party boats, and a yacht basin
with accommodations for about 50 boats. North of the inlet chan-
nel at Wildwood Crest is another large well-equipped wharf for
commercial fishing boats. Both fish docks have direct railroad
connections. The facilities are considered adequate for existing
commerce.
   Operations and results during fiscal year. Maintenance dredg-
ing in the channel between the jetties by the U.S. hopper dredge
Lyman was in progress from January 2 to January 20, 1954. A
total of 95,491 cubic yards of material, place measurement, was
removed at a cost of $41,668. Surveys and channel examinations
were made at a cost of $430.
   The cost of all work was $42,098 for maintenance.
   Condition at end of fiscal year. The project was completed in
1942. The jetties were completed in 1911 and the 25-foot channel
between the jetties in 1917. The 20-foot channel in the harbor
was completed in 1942 with Navy Department funds. The jetties
are spaced 850 feet apart. The east jetty is 4,548 feet long and
the west jetty 4,410 feet long, with inshore end wings 750 feet
and 297 feet long, respectively. The wings of both jetties and the
2,000-foot inshore end section of the west jetty are of stone-filled
pile and timber construction, and the entire east jetty and the out-
shore portion of the west jetty are of rubble mound construction.
   The latest examinations show minimum depths, at mean low
water, as follows:
180               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                                                        Minimum depths


                                  Section                               1      Left             Mid-              Right
                                                                              outside        channel for         outside
                                                                              quarter        half project        quarter
                                                                               (feet)        width (feet)         (feet)
                                                            I      __
Jan. 1954_.....    Between jetties_..------.-- ----------               25          20.0                19.7           18.8
Sept. 1949 ....    Inner end of jetties to Cape May Har-                20          12.4                16.7            7. 5
                     bor.
June 1945......    Thence to Coast Guard Wharves ._..                   20             8.5              18. 9           13.5


   The costs under the existing project, excluding $100,000 con-
tributed by local interests and $50,000 Navy Department funds
expanded for new work, were $879,275 for new work and $765,819
for maintenance, a total of $1,645,094.
                                        Cost and financial summar/
                            k



                                               Fiscal year ending June 30                                   Total to June
                                                                                                          30, 19541, includ-
                                                                                                           ing fiscal years
                                 1950         1951              1952         1953            1954           prior to 1950

New work:
   Appropriated..                                                                                                 $879, 275
   C ost.---   .-.---------                                                                                        879, 275
Maintenance:
   Appropriated........     $55, 000                        s.....
                                                            $-1,493           $6,000         $44, 000              769, 056
   C ost_- _ - --- ---       52, 740             $797-----_-----               4,664          42,098               765, 819


  1In addition, $50,000 Navy Department funds and $100,000 contributed funds were expended for new work


                                  13. ABSECON INLET, N. J.

   Location. This inlet is located on the coast of New Jersey about
65 miles north of Delaware breakwater, between Brigantine
Beach on the north and Absecon Beach on the south. It forms the
entrance to the harbor at Atlantic City, N. J. (See U. S. Coast
and Geodetic Survey Charts Nos. 826 and 1217.)
   Previous project. Adopted by River and Harbor Act of July
25, 1912. The project was completed in 1916. For further details
see Annual Report for 1936, page 319.
   Existing project. This provides for an inlet entrance channel
20 feet deep at mean low water and 400 feet wide, for an entrance
channel 15 feet deep and 200 feet wide from the inlet channel into
Clam Creek, and for a turning basin 15 feet deep within Clam
Creek. The act authorizing the inlet entrance channel also pro-
vides that should the channel at any time have a deleterious effect
on the Atlantic City Beach, work upon the improvement may cease,
it being understood that the project is adopted on the basis that
the interests of the beach in front of the city are superior to those
of the inlet. The total length of the section included in the project
is about 11/ miles. The mean tidal range in the ocean is 4 feet and
at the inlet gorge 3.6 feet. The extreme tidal range, due to ocean
storms, is about 11 feet.
   The estimate of cost for new work, revised in 1954, is $254,000.
            RIVERS AND HARBORS-PHILADELPHIA,                                PA., DISTRICT               181
The latest (1950) estimate for annual cost of maintenance is
$200,000.
  The existing project was authorized by the following River and
Harbor Acts:
     Acts                          Work authorized                                     Documents

Sept. 22, 1922   An inlet entrance channel 20 feet deep...-------------   H. Doc. 375, 67th Cong., 2d sess.
July 24,1946     A channel 15 feet deep into Clam Creek and a turning     H. Doc. 504, 79th Cong., 2d sess.
                   basin.                                                   (Contains the latest published
                                                                            map.)



   Local cooperation. Fully complied with except that local inter-
ests are required to furnish suitable spoil disposal areas for the
new work and subsequent maintenance when and as required for
the dredging of the entrance channel into Clam Creek and the
turning basin within Clam Creek.
   Terminal facilities. There are 9 wharves served by this im-
provement; 1 is Government owned, 6 are privately owned and open
to general public use upon payment of moderate wharfage, and 2
are publicly owned. Three of the wharves have direct railroad
connection. There is also a continuous line of piers or landing
places for pleasure craft on both sides of the large basins which
indent the south shore of the inner channel. There are 3 ship-
yards and 3 marine railways at this locality. The facilities are
considered adequate for the existing commerce.
   Operations and results during fiscal year. Maintenance dredg-
ing in the inlet channel by U.S. hopper dredge Lyman was in prog-
ress from October 26, 1953, to January 2, 1954, and from January
20 to February 5, 1954. There were removed 143,251 cubic yards,
place measurement, of material at a cost of $150,224. Surveys
and channel examinations were made at a cost of $282.
   The cost of all work was $150,506 for maintenance.
   ('ondition at end of fiscal year. The project was about 92 per-
cent complete. The inlet entrance channel was completed in 1938.
The work remaining to be done is the dredging of an entrance
channel from the inlet channel into Clam Creek and a turning
basin in Clam Creek.
   The latest examinations show minimum depths, at mean low
water, as follows:

                                                                                Minimum depth

                                                            Project
     Date                        Section                     depth         Left          Mid-         Right
                                                             (feet)       outside     channel for    outside
                                                                          quarter     half project   quarter
                                                                           (feet)     width (feet)    (feet)
Feb. 1954   ..    Entrance channel _ ___       __            . ...20          12. 0           5. 6         5. 2
Apr. 1953         Thence to Brigantine Bridge__----       __._----.--
                                                            .... .-_                         11. 2



  The costs under the existing project were $208,648 for new work
and $1,995,793 for maintenance, a total of $2,204,441.
 182            REPORT OF CHIEF OF ENGINEERS. U. S. ARMY. 1954

                                      Cost and financial summary

                                             Fiscal year ending June 30                        Total to June
                                                                                             30, 19541, includ-
                                                                                              ing fiscal years
                               1950        1951         1952         1953         1954          prior to 1950

New work:
   Appropriated --------                                                                              $435, 145
   Cost -                                                                                              435, 145
Maintenance:
   Appropriated               $159, 000    $62, 000     $18, 000     $98, 677    $158, 000          2, 241, 327
   Cost__                      150, 813      6, 697      85, 496      96, 556     150, 506          2, 231, 579

  1 Includes $226,497 for new work and $235,786 for maintenance for previous projects.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project ..                                                      45 ,400

                             14. TUCKERTON CREEK, N. J.
  Location. This creek rises in Ocean County, N. J., flows south-
erly 7 miles, and empties into Little Egg Harbor about 8 miles
north of Little Egg Inlet. (See U. S. Coast and Geodetic Survey
Charts Nos. 825 and 1216.)
  Existing project. This provides for a channel 6 feet deep, 80
feet wide from the head of Marchelder Channel in little Tucker-
ton Bay to the mouth; thence 75 feet wide to Parkers Landing, 1
mile above the mouth; thence 60 feet wide to West Tuckerton
Landing, 13/4 miles above the mouth; thence a channel 5 feet deep
and 60 feet wide to just above Scow Landing, 2 miles above the
mouth; and thence a channel 3 feet deep and 40 feet wide to the
mill dam at Tuckerton, 21/4 miles above the mouth. The total
length of the section included in the project is about 31/2 miles.
All depths refer to the plane of mean low water. The mean tidal
range is 2.5 feet. The extreme tidal range is from about 1 foot
below mean low water to about 1 foot above mean high water.
  The cost for new work for the completed project was $60,242.
The latest (1950) approved estimate for annual cost of mainte-
nance is $6,700.
  The existing project was authorized by the following River and
Harbor Acts:
    Acts                         Work authorized                                  Documents

June 13, 1902   For depths of 6, 5, and 3 feet _ _            ... _- H. Doc. 274, 56th Cong., 1st sess.
                                                        _-------------
Mar. 3, 1905    Substitution of channel as across Little Tuckertori  Specified in act. (H. Doc. 1040,
                 Bay.                                                 64th Cong., 1st sess., contains
                                                                      latest published maps.)


   Terminal facilities. There are a number of wharves and piers
of pile-and-timber construction along the creek. There are also
four boatyards with marine railways, and repair and storage
facilities located at Tuckerton. One wharf at Tuckerton is pub-
licly owned. The facilities are considered adequate for existing
commerce.
   Operations and results during fiscal year. Under maintenance,
surveys and channel examinations were made at a cost of $3,746.
          RIVERS AND HARBORS-PHILADELPHIA,                                       PA., DISTRICT                 183
   Condition at end of fiscal year. The existing project was com-
pleted in 1925. The controlling depths at mean low water, in
June 1954, were as follows: In the entrance channel and within the
creek to the Tuckerton Yacht Club, 2.3 feet; thence to Parkers
Landing, 1.2 feet; thence to Scow Landing, 1.5 feet; and thence to
the mill dam at Tuckerton, 3.3 feet.
   The costs under the existing project were $60,242 for new work
and $180,481 for maintenance, a total of $240,723.
                                     Cost awld f(inaur      il     summary

                                              Fiscal year ending June 30                              Total to June
                                                                                                     30, 1954, includ-
                                                                                                     ing fiscal years
                              1950          1951                 1952    1953              1954       priorto 1950
New work:
   Appropriated.          .             .       ..                           .         .                      $60, 242
   Cost_                                                                                                       60, 242
Maintenance:
   Appropriated               $3, 500        $- 157                          $4, 000       $4, 500            181, 363
   Cost                        3, 072                                        3, 872        13, 758          1 180, 493

   Pen ding adjustment in the amount of -$12         not included.


                              15. BARNEGAT INLET, N. J.
   Location. This inlet is located on the east coast of New Jersey,
about 50 miles south of Sandy Hook. It forms the main entrance
to IBarnegat Bay, the largest of the bays on the New Jersey coast
which are separated from the ocean by narrow barrier beaches.
The inlet lies between Island Beach on the north and Long Beach
on the south. (See U. S. Coast and Geodetic Survey Charts Nos.
825 and 1216.)
   Existing project. This provides for a channel 8 feet deep
through the inlet and 10 feet through the outer bar, the channel to
be protected by two converging stone jetties extending to the 12-
foot contour in the ocean and spaced 1,000 feet apart at the outer
ends; a channel of suitable hydraulic characteristics extending in a
northwesterly direction from the gorge in the inlet to Oyster Creek
Channel just northwest of Sunset Shoal, thence via Oyster Creek
Channel to deep water in the bay; and the maintenance of a chan-
nel 8 feet deep and 200 feet wide to connect Barnegat City Harbor
with the main inlet channel. The total length of the section in-
cluded in the project is about 4.5 miles. All depths refer to the
plane of mean low water. The mean tidal range at the inlet gorge
is 2.7 feet and in Barnegat Bay 0.5 foot. The extreme tidal range
at the inlet is from about 2 feet below mean low water to about
3 feet above mean high water.
   The cost for new work for the completed project was $448,849,
exclusive of $300,000 contributed by local interests. The latest
 (1950) approved estimate for annual cost of maintenance is
$43,000.
The existing project was authorized by the following River and
Harbor Acts:
184              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


    Acts                            Work authorized                                Documents
Aug. 30, 1935     An 8-foot depth through the inlet to Oyster Creek.    Rivers and Harbors Committee   l
                   Channel across inner bar, 10-foot depth through        Doc. 19, 73d Cong., 2d sess.
                   outer bar and for jetties.
Aug. 26, 1937    A channel of suitable hydraulic characteristics from   Rivers and Harbors Committee
                  the gorge to Oyster Creek Channel, and thence to        Doc. 85, 74th Cong., 2d sess.'
                   deep water in bay.
July 24,1946     Maintenance dredging of a channel to connect the       H. Doc. 358, 79th Cong., 2d sess.'
                  main inlet channel with Barnegat City Harbor.

1Contains     latest published maps.

   Local cooperation. The River and Harbor Act of July 24, 1946,
imposes upon the work authorized therein the condition that local
interests agree to hold and save the United States free from claims
due to the work. On August 13, 1946, local interests were noti-
fied of this requirement and requested to furnish the necessary
assurance that it would be met. This assurance was accepted on
May 21, 1954. Prior requirements have been fully complied with.
   Terminal facilities. There are three docks or terminals located
in the inner harbor at Barnegat City which furnish adequate
facilities for the present commerce of the locality. Two are
privately owned and are used for fishing interests. One is Gov-
ernment owned.
   Operations and results during fiscal year. Maintenance, con-
tract: A contract was awarded for repairs to the south jetty, dam-
aged in the storm of November 6-7, 1953. Work was commenced
June 7, 1954 and was in progress at the end of the fiscal year, The
costs were $8,927.
   Under a contract for dredging in the inlet channel only pre-
liminary work was done. The costs were $511.
   Maintenance, hired labor: Examinations of the channel and of
the jetties were made at a cost of $4,659.
   The cost of all work was $14,097 for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1940. The dredging of a channel from the inlet gorge
to Oyster Creek Channel 20 feet deep and 200 feet wide and thence
a channel 8 feet deep and 200 feet wide through Oyster Creek
Channel to Barnegat Bay was completed in 1939. The converging
jetties were completed in 1940. The north jetty is 4,900 feet long
and the south jetty 2,950 feet long. The inshore end sections, 769
feet and 450 feet long, respectively, are of pile-and-timber con-
struction reinforced with stone, and the outshore ends of both
jetties are of rubble-mound construction. The latest examina-
tions show a navigable channel with controlling depths, at mean
low water, as follows: In February 1954, from the ocean to the
inlet gorge, 4.2 feet; thence to the inner end of the inlet channel,
4.7 feet; and thence, in August 1946, through Oyster Creek Chan-
nel to Barnegat Bay, 6.9 feet.
   The costs under the existing project, excluding $300,000 con-
tributed funds expended for new work, were $448,849 for new
work and $1,191,927 for maintenance, a total of $1,640,776.
              RIVERS AND HARBORS-PHILADELPHIA,                                   PA., DISTRICT             185
                                         Cost and financial summary

                                                 Fiscal year ending June 30                       Total to June
                                                                                                30, 19541, includ-
                                                                                                 ing fiscal years
                                  1950          1951         1952         1953         1954       prior to 1950
New work:
                     .
   Appropriated ---------------------       ------------ ------------ ------------ ------------          $448, 849
   Cost    ....-----------------------------------------------------------------------------              448, 849
Maintenance:
   Appropriated...              $238, 000    $-12, 001 _ .         ...        $2, 000   $286, 750      1, 466, 580
   Cost---------------           385, 821       99, 535-----------        ------...
                                                                        ..........       2 12, 930     1,190, 760

  1 In addition, $300,000 contributed funds were expended for new work.
  2 Pending adjustments in the amount of $1,167 not included.

                                 16. MANASQUAN RIVER, N. J.
   Location. This is a small stream located in the eastern part of
New Jersey, rising near Freehold and flowing easterly to the At-
lantic Ocean, which it enters about 26 miles south of Sandy Hook.
 (See U. S. Coast and Geodetic Survey Chart No. 795.)
   Previousprojects. Adopted by River and Harbor Act of March
3, 1879. For further details, see Annual Report for 1909, page
186, and Annual Report for 1938, page 269.
   Existing project. This provides for a channel 14 feet deep and
250 feet wide, protected by jetties and other works, extending
from the Atlantic Ocean to the inner end of the north jetty, thence
12 feet deep and 300 feet wide to within 700 feet of the New York
& Long Branch Railroad bridge, thence of same depth and narrow-
ing to a width of 100 feet to within 300 feet of the bridge; for a
widening on the northerly side of the channel of 200 feet for a
distance of 3,150 feet to a depth of 8 feet; for an anchorage of 19
acres in area to a depth of 10 feet on the south side of the channel
and for an anchorage of 27.5 acres in area to a depth of 12 feet
about 0.5 mile west of route 35 highway bridge. Length of section
included in project is about 1.5 miles. Mean tidal range is 3.7
feet at the inner end of the inlet and 4 feet at ocean end; mean
range of spring tides, 4.4 and 4.8 feet, respectively; irregular
fluctuations due to wind and barometric pressure vary from 2.7
feet below to 7.5 feet above mean low water at the inner end of the
inlet.
   The estimate of cost for new work, revised in 1954, is $918,000,
exclusive of amount expended on previous projects and $300,000
contributed by local interests. The estimate for annual cost of
maintenance, revised in 1950, is $32,500.
   The existing project was authorized by the following River and
Harbor Acts:
       Acts                          Work authorized                                    Documents

July    3, 1930    Channel 8 feet deep and provision of works designed         H. Doc. 482, 70th Cong., 2d sess.
                    to secure the channel.
Aug. 30, 1935      Widening of channel on northerly side....       ...---------Senate committee document, 74th
                                                                                 Cong., 1st sess.
Mar.     2, 1945   Deepening channel to 12 and 14 feet; 10- and 12-foot H. Doe. 356, 77th Cong., 1st sess.
                    anchorages.                                                  (Contains latest published map.)
186      RE1PORT OF CHIEF OF ENGINEERS, U. S. ARMY,    1954

   Local cooperation. The River and Harbor Act of March 2,
1945, provides that local interests furnish, free of cost to the
United States, suitable areas properly diked for disposal of
dredged material, for new work and maintenance, when and as
needed; convey to the United States, free of cost, a perpetual ease-
ment to excavate all lands above ordinary high water required for
the improvement; and release the United States from all claims
for damage resulting from the improvement. Assurances of local
cooperation furnished by local interests in connection with the
deepening of the channel only, were approved by the Chief of
Engineers on February 15, 1951.
   The requirements under prior acts have been fully complied
with.
   Terminal facilities. Five landings with a total wharf age of 700
feet, used by commercial fishermen, and seven landings and boat
basins for pleasure craft are located along the river and its
branches. The pleasure boat landings and basins are equipped
with marine railways, boatbuilding and repair facilities, and boat
storage facilities. Two yacht clubs with a mooring capacity of 45
boats and numerous pleasure boat landings are also located along
the waterway. The existing facilities are considered adequate for
present requirements.
   Operations and results during fiscal year. Maintenance, con-
tract: Rehabilitation of the steel sheet pile bulkhead on the north
side of the channel was commenced March 15, 1954, and was in
progress at the end of the fiscal year. The costs were $62,625.
   Maintenance, hired labor: Surveys and channel examinations
were made at a cost of $945.
    The cost of all work was $63,570 for maintenance.
   Condition at end of fiscal year. The existing project was about
82 percent complete. Two rubble mound jetties, 1,230 feet long
north of the entrance and 1,030 feet long south of the entrance,
were completed in 1931. Two steel bulkheads, each 950 feet long,
at the inshore ends of the jetties were completed in 1937. A steel
bulkhead 698 feet long and two steel groins of an aggregate length
of 570 feet, constructed on the northerly beach, were completed in
1938. A channel 10 feet deep and 250 feet wide from the 10-foot
depth curve in the ocean to a point near the inshore ends of the
jetties and thence 8 feet deep and 300 feet wide to a point 700 feet
below the New York and Long Branch Railroad bridge was coim-
pleted in 1933, and the widening on the northerly side of the
channel was completed in 1938. The work remaining to be done is
the deepening of the channel between the jetties from 10 feet to
14 feet, thence the channel to a point 700 feet below the railroad
bridge from 8 feet to 12 feet, and extending the 12-foot channel
to within 300 feet of the railroad bridge; also the dredging of the
19-acre anchorage south of the channel and the 27.5-acre anchor-
age west of the highway bridge.
    The controlling depth in the channel at mean low water, in
December 1953, from the ocean to the inshore ends of the jetties
was 10.7 feet, and thence, in April 1953, to the railroad bridge
9.0 feet.
    The costs under the existing project, excluding $300,000 con-
           RIVERS AND HARBORS-PHILADELPHIA,                                         PA., DISTRICT                         187
tributed funds expended for new work, were $335,342 for new
work and $639,164 for maintenance, a total of $974,506.
                                           C('ost and fnacial
                                                       i      sommnary

                                                  Fiscal year ending June 30(                                    Total to June
                                                                                                               30, 1954', includ-
                                                                                                                ing fiscal years
                                    1950        19511              1952         1953           1954              priorto 1950

New work:
   Appropriate(]d - -               ----.                     ---------------                                           $374, 342
   Cost    - - - -
Maintenance:
                      -   -   -   ------          -     ---                                                              374, 342
   Appropriated                     $41, 000   $ --6, 347               $650    $6, 200        $76, 500                 655, 671
   Cost         _ -                 110, 346    -2, 683                  650     4, 676         632, 160                639, 808


  12 Includes  $39,000 for new work and $2,054 for maintenance for previous
     In addition $300,000 contributed funds were expended for new work.
                                                                                       projects.

  3 Pending adjustments in the amount of $1,410 not included.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project                                                               -   ..... $582 ,700

               17. NEW             JERSEY         INTRACOASTAL                     WATERWAY
   Location. This waterway, a sea-level inland water route ap-
proximately parallel with the New Jersey coast, extends from the
Atlantic Ocean at Manasquan Inlet, about 26 miles south of Sandy
Hook, N. J., to Delaware Bay about 3 miles above Cape May Point.
The waterway extends through the inlet and up Manasquan River
a distance of about 2 miles; thence by the Manasquan-Bayhead
Canal through high ground for a distance of 2 miles to the head of
Barnegat Bay. It then passes through a series of bays, lagoons,
and thoroughfares along the New Jersey coast to Cape May Har-
bor; thence across Cape May County to Delaware Bay through a
land cut by way of the New England Creek basin. (See U. S.
Coast and Geodetic Survey Charts Nos. 234, 795, 825, 826, 827,
1216, 1217, 1218, and 1219.)
   Existing project. This provides for a channel 12 feet deep at
mean low water and generally 100 feet wide, extending from the
Atlantic Ocean at Manasquan Inlet, N. J., to Delaware Bay above
Cape May, N. J., by the further improvement of Manasquan River
and Inlet, N. J., and the present New Jersey Intracoastal Water-
way, and by the construction of a canal of similar dimensions from
Cape May Harbor to Delaware Bay via the New England Creek
basin, with adequate jetties at the Delaware Bay entrance. The
total length of the project is about 117 miles. Normal tidal range
in sections of the waterway remote from inlets is 0.5 foot. Near
the inlets the mean tidal range generally is 3 feet; in the ocean, 4
feet; at the head of Cape May Harbor, 4.6 feet; and in Delaware
Bay, near the entrance, 4.7 feet.
   The estimate of cost for new work, revised in 1954, is $6,524,000,
exclusive of $1,824,940 Navy Department funds and $99,000 con-
tributed by local interests. The latest (1950) approved estimate
for annual cost of maintenance is $400,000.
   The existing project was adopted by the River and Harbor Act
approved March 2, 1945 (H. Doc. 133, 76th Cong., 1st sess.). The
latest published map is in the project document.
   The River and Harbor Act approved July 24, 1946 (Public 525,
188      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

79th Cong., 2d sess., as extenaed by Public Law No. 240, 82nd
Cong., dated Oct. 30, 1951), authorized the use for a period not to
exceed 6 years, of funds from appropriations heretofore or here-
after made for maintenance and improvement of rivers and har-
bors, for the maintenance of the canal from Cape May Harbor to
Delaware Bay constructed as an emergency wartime project with
Navy Department funds, including the cost of maintaining the
temporary railroad and seashore highway bridges over the canal.
   Local cooperation. The project is subject to the conditions that
the State of New Jersey cede to the United States all right, title,
and interest that it has acquired to lands, easements, rights-of-
way, and structures other than bridges for the Manasquan-Bay-
head Canal; that the State of New Jersey furnish, free of cost to
the United States, all lands, easements, rights-of-way, and disposal
areas required for construction of the Cape May Canal and for
improvement of the proposed waterway and for their subsequent
maintenance; that local interests provide, maintain, and operate
suitable bridges over the waterway; that the State of New Jersey
donate to the United States the navigation aids in use on the
present New Jersey Intracoastal Waterway; and that the State of
New Jersey hold and save the United States and its agents free
from any claims for damages resulting from the work of improve-
ment. Compliance with these conditions was completed January
15, 1954, except that local interests are required to furnish dis-
posal areas for the construction and the subsequent maintenance
of the proposed improvement.
   Terminal facilities. There are numerous piers, wharves, and
docks at resorts located at or adjacent to the waterway, most of
which are open to general public use, and fuel, water, and other
supplies are readily available. Public and privately owned boat
basins are located in a number of streams entering the bays and
thoroughfares through which the waterway passes. Boat repair
and storage yards with marine railways for small craft are also
scattered along the waterway. Transfer facilities, including facili-
ties for icing, storing, and shipping food fish, are available at
most of the larger communities along the waterway, including
Atlantic City, Wildwood, and Cape May. The plants at the two
latter places have direct railroad connections. The facilities are
considered adequate for existing commerce.
   Operations and results during fiscal year. Maintenance, con-
tract: Maintenance dredging to 6-foot depth in the channel be-
tween Great Egg Bay and Great Sound, was commenced April 26,
1954, and was nearing completion at the end of the fiscal year.
There were removed 150,000 cubic yards, place measurement, of
material, at a cost of $107,236.
   Maintenance, hired labor: Surveys and channel examinations
were made at a cost of $3,717, and banks and ditches along the
waterway were maintained at a cost of $51; a total of $3,768.
               RIVERS AND HARBORS-PHILADELPHIA, PA., DISTRICT                                                                        189
  The cost of all work was $111,004 for maintenance.
  Condition at end of fiscal year. The existing project was about
25 percent complete. A canal 12 feet deep and 100 feet wide from
Cape May Harbor to Delaware Bay was completed in 1942; 2
parallel stone jetties at the Delaware Bay entrance and a tem-
porary highway drawbridge in 1943; and a temporary highway
drawbridge and a railroad bridge in 1944, all with Navy Depart-
ment funds. The work remaining to be done is the dredging of a
channel 12 feet deep and 100 feet wide from the Atlantic Ocean at
Manasquan Inlet to Cape May Harbor.
  The latest examinations show controlling depths, at mean low
water, as follows:

                                                                                                        Depths


       Date                                Section                                  Left           Mid-channel                 Right
                                                                                  outside           for half-                 outside
                                                                                  quarter            project                  quarter
                                                                                   (feet)          width (feet)                (feet)
May           1946   N. Y. & L. B. Railroad bridge (Manasquan                                                  1 9.2
                       River) to Bayhead.
                     Bayhead to point opposite Waretown               _                                        1 5. 2
                     Thence to Little Egg Inlet       -----_       -.                                          1 2. 9
                     Thence to Albany Ave., Atlantic City                                                      1 3. 0
                     Thence to Ninth St., Ocean City_________                                                  1 5. 7
June          1954   Thence to Townsend Inlet ........--------------                                           1 4. 5
Jan.          1954   Thence to Rio Grande Ave. bridge, Wild-                                                   15. 2                  -
                         wood.
May           1946   Thence to Cape May Harbor ........-                                                       1 8.9
May           1954   Thence via Cape May Canal to Delaware                                  5. 2                   6. 7                   6. 5
                      Bay.
  1 In 80 percent of channel width.

  The costs under the existing project, excluding $1,824,940 ex-
pended for new work and $286,954 for maintenance from Navy
Department funds and $99,000 contributed funds expended for
new work, were $53,694 for new work, $378,891 for maintenance,
and $40,000 for operating and care, a total of $472,585.
                                           Cost (1 (1finan(cial summar!/


                                                      Fiscal year ending June 30                                      Total to June
                                                                                                                     30, 1954, 1 includ-
                                   1950              1951            1952            1953               1954
                                                                                                                          ing fiscal
                                                                                                                           prior  to years
                                                                                                                                     19502

New work:
   Appropriated-.            __                                                                                                   $53, 694
   Cost-..............             .....             ------     - ----------    !------------!------------                         53,694
Maintenance:
   Appropriated                    $57, 000          $31, 000        $32, 800       $14, 587        $191, 000                     498, 887
   Cost           _                 44, 272           40, 013         34, 379        15, 908        3103, 426                    S 411, 313

  1 In addition, $1,824,940 Navy Department funds and $99,000 contributed funds were expended for new
work.
  2 In addition, $286,955 Navy Department funds were expended for maintenance.
  3 Pending adjustments in the amount of $7,577 not included.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project................. ...... . $6,470,300
190            REP)ORT OF CHIEF OF ENGINEERS.                         LU. S. ARMY.         1054

                      18.    INACTIVE          NAVIGATION PROJECTS

                                                     For last       Cost to June 30, 1954         Estimated
                                                    full report                                    amount
                 Name of project                         see                                       required
                                                      annual          Con-       Operation            to
                                                       report      struction        and           complete
                                                        for-                    maintenance
  1. Absecon Creek, N. J-------------------------
2. Alloway Creek, N. J.2
                                                  ! 1950
                                                    1931
                                                                     $11, 934
                                                                      21, 398
                                                                                     $68,230
                                                                                      33, 002
                                                                                                     (1)
                                                                                                     (1)
3. Appoouinimink River, Del.' 3--------------      1931              36, 973         41,099          $15, 000
4. Big Timber Creek, N.2 J_                        1949            4 58, 665         11. 397        (1)
5. Broadkill River, Del.                           1953              68, 228        101, 854         (1)
6. Chester River, Pa.2 3 5.      .      ._____-_   1931                 6, 000           650           26,000
7. Cohansey River, N. J.2                          1953           6146, 756         194, 657        f1)
8. Delaware River, N. Y., N. J.,and Pa.,at or      1917       -                                      864, 000
      near the mouth of Neversink River 3 7
9. Dennis Creek, N. J.2                            1897               4.701 ..                       (1)
10. Double Creek, N. J.'                            1912               7, 800        (9)             f1)
11. Goshen Creek, N. J.2 3                          1905              15,359              870         (1)
12. Harbor of Refuge, Dela ware Bay. Del........ 1952          105, 162, 230         120, 456         (1)
13. Ice Harbor at Marcus IIook, Pa.      ..         1928            208, 964          14, 336         (1)
14. Ice Harbor at New Castle, Del."11 ...........   1898             224, 704                         (1)
15. Inland Waterway between
                          2
                                 Rehoboth Bay       1953             435, 383        101, 205          816, 600
      and Del. Bay, Del.
16. Inland Waterway from3 Chincoteaqgue Bay,        1939         '3 168, 412    14   5 42, 794        (1)
      Va. to Del. Bay, Del. 12
17. Leipsic River, Del."                            1931              36. 956          32, 243        (1)
18. Little Egg Harbor, N. J.37                       (16)             15, 048               --        (1)
19. Little River, Del.                              1________946      12, 016         47, 808         (1)
20. Maurice River, N. J.2 17__________________      1948          1Q143, 984         122, 380          130, 000
21. Mispillion River, Del.219_                      1951             365, 189        384, 567         (1)
22. Oldmans Creek, N. J.2 ______________________    1941              31,188          31, 736          260, 800
23. Raccoon Creek, N. J.22                          1949           2o83, 665         218, 936         (1)
24. Rancocas River, N. J.                  --       1942              44, 500         13, 090           138, 500
25. Salem River, N. J.2 21-
                         "                          1947          22107, 634         173, 154         2 28, 200
26. Smyrna River, Del. 4________________ ____       1949             198, 843        195, 609            11,200
27. St. Jones River, Del.5____________________      1950             207, 102         65, 318        1, 380, 500
28. Toms River, N. .J.......................... 1950                  10, 050         19,985            355, 000
29. Waterway from Indian River Inlet to Reho-       1950     ______________                           2 95, 000
      both Bay, Del.
30. Woodbury Creek, N.      J_                      1940           27 27, 093          55, 406        (1)


   1 Completed.
   2 Channel adequate for commerce.
   3 No commerce reported.
     Exclusive of $50,000 contributed by local interests.
   2 Includes $6,000 new work and $63 maintenance funds expended on previous project.
   6 Includes $36,000 new work funds expended on previous projects.
   7 Abandonment recommended in H. Doc. 467, 69th Cong., 1st sess.
   8 Exclusive of amount to be contributed by local interests. The authorization of this project provided for
local interests to deposit with the United States $54,780 for the accomplishment of certain work. The present
estimate for this work is $153,500.
   9 Maintenance assumed by local interests as required by law.
  10Includes $2,749,452 new work funds expended on previous projects.
  1 Harbor not now required for commerce.
  12Cost of maintaining bridges assumed by State of Delaware.
  13Entire amount expended on previous project, repealed in 1905.
  14 Exclusive of $2,000 contributed by State of Delaware.
  15 Includes $25,330 maintenance funds expended on previous projects.
  16 Last appropriation for the project was in 1852. No information is at hand relative to work done.
  17Awaiting local cooperation.
  18 Includes $43.000 new work funds expended on previous projects.
  15 Includes $148,798 new work and $61,172 maintenance funds expended on previous projects.
  20Includes $557 new work funds expended on previous projects.
  21Includes $55,809 new work and $48,000 maintenance funds expended on previous projects.
  '2 Exclusive of $51,825 contributed by local interests.
  23 In addition, local interests are required to contribute an equal amount.
  24Includes $55,085 new work and $22,723 maintenance funds expended on previous projects.
  25Includes $54,590 new work and $28,936 maintenance funds expended on previous projects.
  26Exclusive of $20,000 required to be contributed by local interests.
  27 Includes $2,950 new work funds expended on previous projects.
            19. BEAR         CREEK RESERVOIR,                     LEHIGH RIVER, PA.
  Location. The site of Bear Creek Reservoir is in northeastern
Pennsylvania on the Lehigh River between White Haven and Stod-
dartsville. The dam site is a short distance below the mouth of
Bear Creek, approximately 60 miles above the city of Allentown,
and 77 miles above the confluence of the Lehigh River with the
Delaware River at Easton, Pa. (See U. S. Geological Survey
quadrangle sheet "Stoddartsville, Pa.")
                FLOOD CONTROL-PHILADELPHIA, PA., DISTRICT                                         191
   Existing project. The plan of improvement provides for a
single-purpose flood-control reservoir having a capacity of 110,-
000 acre-feet, formed by an earth dam 3,000 feet long at the crest,
rising 234 feet above the river bed, with gate-controlled outlet
works discharging through a tunnel in the west abutment, and a
spillway located in the dam. The reservoir will control the runoff
from a drainage area of 288 square miles. The project was au-
thorized by the Flood Control Act approved July 24, 1946.
   The current estimate of Federal cost of new work, revised to
1954, is $16,820,000 for construction and $380,000 for lands and
damages, a total of $17,200,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year.                            Preliminary plan-
ning was done in connection with a relocation of the spillway. The
costs were $1,993.
   Condition at end of fiscal year.                    No construction work has been
done on the project. Preparation of plans and specifications is
about 34 percent complete. The costs were $493,483 for new work.
                                    Cost and financial summary

                                           Fiscal year ending June 30                    Total to June
                                                                                     - -30, 1954, includ-
                                                                                        ing fiscal years
                             1950         1951        1952        1953     1954          priorto 1950
New work:
   Appropriated--------      $90, 000    $90, 000   $-68,027       .       $4,517              $496, 490
   Cost.................      17, 483     31, 072        434               11, 867             1493, 357

  1 Pending adjustment in the amount of $126 not included.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954---...---------...............
                                                                          $3,130
    Unobligated balances available for succeeding fiscal year ending
    June 30, 1956---...---..---..--......................--...................
                                                                           3,130
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project---..............................................
                                                                     $16,703,500

                       20. ALLENTOWN, LEHIGH RIVER, PA.
   Location. Allentown is located in Lehigh County on the Lehigh
River, 17 miles above its mouth. (See U. S. Geological Survey
quadrangle sheets, "Allentown and Allentown West, Pa.")
   Existing project. The plan of improvement provides for wid-
ening and deepening the channel of Lehigh River and easing the
abrupt turn and approaches thereto at the mouth of Little Lehigh
Creek; it also provides for a training dike and levees, and the
necessary appurtenant structures. The project was authorized by
the Flood Control Act approved July 24, 1946. The estimated Fed-
eral cost of new work, revised in 1954, is $2,060,000 for construc-
tion. The estimated local cost for lands, damages, and utility al-
terations, revised in 1953, is $48,000.
   Local cooperation. Assurances of cooperation have not been
furnished by local interests.
   Operations and results during fiscal year. Subsurface investi-
gations of the project site and of prospective borrow areas, in
progress at the end of the previous fiscal year, were completed.


       Sig 7-191-222
192                   REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

A topographic survey of the project site, in progress at the end of
the previous fiscal year, was completed. The taking of borings,
under contract, was completed August 31, 1953. The costs were
$5,417.
  A model study and a report thereon, in progress at the end of
the previous year by the Waterways Experiment Station, Vicks-
burg, Miss., was completed at a cost of $8,711.
  Rain gages were operated in cooperation with United States
Weather Bureau at a cost of $365.
  The total costs were $14,493 for new work.
  Condition at end of fiscal year. No construction work has been
done on the project. Advance engineering and design is about
41 percent complete.
  The costs under the project were $89,304 for new work.

                                                   Cost and financial summary

                                                         Fiscal year ending June 30                                     Total to June
                                                                                                                       30, 1954, includ-
                                                                                                                       ing fiscal years
                                            1950        1951               1952               1953          1954        prior to 1950

New work:
       Appropriated ------------------                  $40, 000           $20, 000           $25, 000      $5, 000            $90, 000
       Cost -----------------------------                      942          43, 867            30, 003      14, 455            '189, 267


     1 Pending adjustment in the amount of $38 not included.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 ..-------------.........
                                                                              $733
    Unobligated balances available for succeeding fiscal year ending
                                                                 -------
      June 30, 1956 ...-.---------------------------. .....----.---         -733
    Estimated additional amount needed to be appropriated for com-
                                                                         1,970,000
      pletion of existing project-----..---...................-------------------
                         21. INACTIVE                  FLOOD CONTROL                                PROJECTS

                                                                       For last             Cost to June 30, 1954         Estimated
                                                                     full report,                                          amount
                        Name of project                                   see                                              required
                                                                       annual                Con-         Operation            to
                                                                        report             struction         and           complete
                                                                         for-                            maintenance
1.    Bethlehem, Pa---------------------------                           1950     ------                                    $7, 970, 000
2.    Dyberry Reservoir, Pa.-- ---------                                 1953                $128, 370 --------------        7, 211,600
3.    Mt. Holly, N. J -------------       ...-------------               1946                 283, 655        (1)             (2)
4.    Prompton Reservoir, Pa__----------------------                     1953                 167, 315 ..............        5, 412,700

     1 Maintenance assumed by local authorities as required by act authorizing the project.
     2 Completed.

                                        22. GENERAL INVESTIGATIONS
  Examinations and surveys. The cost of general investigations
during the fiscal year was $6,631, and the expenditures were
$6,566. The balance unexpended at the end of the fiscal year,
amounting to $3,633, will be applied to expenses to be incurred
under this heading. Additional funds in the amount of $10,300
can be profitably expended during the next fiscal year.
  Collection and study of basic data. The cost of the collection
and study of basic data during the fiscal year was $500. The ex-
penditures were $500, and there was no balance unexpended.
                         FLOOD CONTROL-PHILADELPHIA, PA., DISTRICT                                                    193
                        23. INSPECTION                   OF       COMPLETED            PROJECTS
      The cost of this work during the fiscal year amounted to $2.
                                                  Cost and financial summary

                                                         Fiscal year ending June 30                         Total to June
                                                                                                           30, 1954, includ-
                                                                                                           ing fiscal years
                                           1950         1951         1952       1953          1954           prior to 1950

Maintenance:
                ........-----------
    Appropriated--------                   $60                                            ----------                    $60
    Cost-------------- ------------------------                           $58                        $2                  60

Other new work data: Appropriated for succeeding fiscal year ending June 30,
   1955...............................................................------  $500

     24. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
   Small Flood Control Projects not specifically authorized by Con-
gress. (Section 212 of the 1950 Flood Control Act.)
   Pursuant to this authorization construction of a levee and flood-
wall for flood control protection on the Chester River above Ninth
Street, Chester, Pa., in progress at the end of the previous fiscal
year, under contract, was completed April 7, 1954. The costs were
$155,405 for new work. Conditions of local cooperation have
been fully complied with. A report on engineering studies in con-
nection with flood control protection in the Livingston Manor and
the Roscoe-Rockland areas, Sullivan County, N.Y., in progress at
the end of the previous fiscal year, was completed. The costs were
$108 for new work. The total costs, all for new work, were
$155,513.
   For flood control protection on the Chester River above Ninth
Street, Chester, Pa., construction of the levee and floodwall was
completed. The City of Chester assumed maintenance of the work
on June 1, 1954. The costs were $183,273 for new work. Engin-
eering studies, and a report thereon, in connection with flood
control protection in the Livingston Manor and the Roscoe-Rock-
land areas, Sullivan County, N.Y., were completed. The costs
were $6,811. The total costs, all for new work, were $190,084.
                                                  Cost and financial summary

                                                        Fiscal year ending June 30                          Total to June
                                                                                                          30, 1954, includ-
                                                                                                           ing fiscal years
                                          1950         1951         1952        1953         1954           prior to 1950
New work:
   Appropriated -...-.----- .                           $2, 000    $110, 300    $8, 700     $69, 258             $190, 258
           ----------------------------
   Cost.................                                    744        7, 501   26,324     1155, 498             1 190, 069

   1 Pending adjustment in the amount of $15 not included.

Other new work data: Unobligated balance, fiscal year ending June 30, 1954...... $189
                IMPROVEMENT OF RIVERS AND HARBORS
                    IN THE BALTIMORE, MD., DISTRICT
  This district comprises the watershed of the Susquehanna River
and its tributaries from headwaters in south-central New York
State through central Pennsylvania to its mouth in the Chesapeake
Bay; eastern Maryland, southwestern Delaware, and eastern Vir-
ginia, embracing Chesapeake Bay and its tributaries north of
Cove Point, Md., on the western shore of the bay, and Onancock
River, Va., on the eastern shore, and the watersheds tributary to
the Atlantic Ocean between the southern boundary of Delaware
and a point north of White Creek and Gargathy Inlet on the
Atlantic coast.
                                                   IMPROVEMENTS

          Navigation                                                    Flood control
                                                        Page                                                            Page
1.   Baltimore Harbor                                         15. Genegantslet Reservoir
        and Channels, Md..........._.......             195           Genegantslet Creek, N. Y.....                     219
2.   Baltimore Harbor, Md.                                    16. Southern New York Flood Con-
        Collection and Removal of                                    trol Project............................           219
        Drift...............------.................     200    17. Swoyersville and Forty Fort,
3.   Chester River, Md......___.........               201          Pa.....-.              .           .               234
4.   Cambridge Harbor, Md.............                 203    18. Williamsport, Susquehanna
5.   Honga River and Tar Bay                                        River, Pa...........................               235
         (Barren Island Gaps), Md.....                  205    19. York, Codorus Creek, Pa.........                     238
6.   Wicomico River, Md.............                   206    20. Inactive Flood-Control Proj-
7.   Pocomoke River, Md.................               208          ects..........................................     240
8.   Twitch Cove and Big                                      21. General Investigations.............                  240
        Thoroughfare River, Md.......                   210    22. Inspection of Completed Proj-
9.   Starlings Creek, Va.....__.___.........           211          ects.................... .....................--   240
10.   Tangier Channel, Va._. ............               212    23. Flood control work under spe-
11.   Waterway on the Coast of Vir-                                  cial authorization .................               241
        ginia........................................   213
12.   Ocean City Harbor and Inlet
        and Sinepuxent Bay, Md.. ..                     215
13.   Fishing Creek, Md....................             217
14.   Inactive Navigation Projects._                    218

                   1. BALTIMORE HARBOR AND CHANNELS, MD.
  Location. Baltimore Harbor is situated at the head of the navi-
gable portion of the Patapsco River about 12 miles from Chesa-
peake Bay. The river rises near the town of Westminster in
Carroll County, Md., and flows in a general southeasterly direction
for about 65 miles to enter the Chesapeake Bay. (See U. S. Coast
and Geodetic Survey Chart No. 549.)
  Previous projects. Patapsco River: The original project was
dated July 4, 1836. Modifications were contained in the River and
Harbor Acts of August 30, 1852; June 10, 1872; March 3, 1881;
June 3, 1896; March 3, 1905; March 3, 1909; February 27, 1911;
and March 4, 1913.
  Middle Branch: The original project was dated June 3, 1896.
  Curtis Bay: The original project was dated July 13, 1892. It
was modified by the River and Harbor Act of June 13, 1902.
                                                                                                             195
196       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

    York Spit: The original project was dated March 3, 1905.
    For further details, see pages 1787 and 1788 of the Annual Re-
port for 1915, and page 389 of the Annual Report for 1932.
    Existing project. This provides: (1) A uniform main chan-
nel depth of 39 feet between Cape Charles, Va., and Fort McHenry,
Baltimore, Md., with dimensions as follows: 39 feet deep and 1,000
feet wide between the curves of 39-foot depth in Chesapeake Bay
opposite York Spit, a distance of about 6.77 miles (under jurisdic-
tion of the Norfolk, Va., District) ; 39 feet deep and a general width
of 600 feet from the 39-foot depth curve in Chesapeake Bay to Fort
McHenry on the Patapsco River, a distance of about 20 miles; (2)
for branch channels with dimensions as follows: 35 feet deep and
400 feet wide from the main channel to head of Curtis Bay, a dis-
tance of about 2% miles; 35 feet deep and 400 feet wide from the
main channel at Fort McHenry to Ferry Bar, and thence 27 feet
deep and 250 feet wide to the Western Maryland Railway bridge,
a total distance of about 3% miles; (3) for widening the angle be-
tween the Fort McHenry and Ferry Bar Sections; (4) for widening
at the approaches and bends; (5) for the following anchorages-
Fort McHenry Anchorage, 3,500 feet long, 400 feet wide, and 35
feet deep; Riverview Anchorage No. 1, 4,500 feet long, 1,500 feet
wide, and 35 feet deep; Riverview Anchorage No. 2, 2,400 feet
long, 1,200 feet wide, and 30 feet deep; Quarantine Anchorage,
3,500 feet long, 600 feet wide, and 35 feet deep; (6) it is further
provided that as rapidly as the city of Baltimore, at its own ex-
pense, provides the 35-foot depth into the Northwest Branch
 (inner harbor) the United States shall take over the maintenance
of that depth (the United States maintains a channel 35 feet
deep, varying in width from 550 feet to 1,200 feet, and 5,100 feet
in length from Fort McHenry to and along the southwest side of
the inner harbor and a channel generally 95Q feet wide and 5,000
feet in length along the easterly side of the inner harbor) ; (7) for
a connecting channel with a depth of 27 feet and width of 400
feet from Cutoff-Brewerton Angle in the main channel to the
inland waterway from Delaware River to Chesapeake Bay; (8)
for a channel in Curtis Creek with a depth of 35 feet and width
of 200 feet from the head of the existing 35-foot project channel in
Curtis Bay to a point in the creek about 750 feet below the Pen-
nington Avenue Bridge; (9) for a channel 22 feet deep and gener-
ally 200 feet wide from the 22-foot depth curve in Curtis Creek im-
mediately below the Pennington Avenue Bridge, 18 feet over an
irregular area of about 3 acres at the head and adjacent to the 22-
foot channel; a depth of 15 feet for a general width of 450 feet
from the head of the 22-foot channel to the upper end of the
marginal wharf of the United States Ordnance Depot; (10) and
for a channel 22 feet deep and 200 feet wide from the 22-foot
depth curve south of the Baltimore & Ohio Railroad Bridge to
the vicinity of Arundel Cove, a distance of about 2,800 feet, thence
100 feet wide in Arundel Cove for a distance of about 2,100 feet;
with an anchorage basin approximately 700 feet square adjacent
to the channel southwesterly of the Coast Guard wharf.
   The estimate of cost for new work, revised in 1954, is $9,939,000
exclusive of amounts expended on previous projects.        The latest
                  RIVERS AND HARBORS--BALTIMORE, MD., DISTRICT                                             197
 (1950) approved estimate for annual cost of maintenance is
$400,000.
The existing project was authorized by the following River and
Harbor Acts:

       Acts                          Work authorized                                     Documents
                                                                                   i--


Mar. 3, 1905      Main channel 35 feet deep and 600 feet wide through-       H. Doe. 186, 57th Cong., 2d sess.
                    out.
Mar. 3, 1909      Anchorage basin near intersection of Fort McHenry
                    and Curtis Bay Channels (within original limit of
                    cost authorized by act of Mar. 2, 1907).
Feb. 27, 1911     Width increased at entrances and bends (increase
                    to be made within the limit of original estimate).
Aug.    8, 1917   Branch channel 35 feet deep to head of Curtis Bay,         H. Doc. 799, 64th Cong., 1st sess.
                    and one 35 feet deep and 400 feet wide into the
                    Southwest Branch of the Patapsco River to a point
                    near Ferry Bar, and 27 feet deep and 250 feet wide
                    to Western Maryland Ry. bridge, widened at ap-
                    proaches and bends, and with anchorage and turn-
                    ing basins. Inclusion of Patapsco River and tribu-
                    taries into one project for Baltimore Harbor.
Jan. 21, 1927     Change in location of the anchorage near upper end
                    of the Fort McHenry Channel.
July    3, 1930   Increased anchorage facilities__        ________________   Rivers and Harbors Committee   1
                                                                               Doc. 11, 70th Cong., 1st sess.
    Do....... For 37-foot depth in that portion of channel to Balti-         H. Doc. 29, 71st Cong., 1st sess.'
                more lying between the 37-foot depth curve near
                Baltimore Light to the Sparrows Point Entrance
                Channel; widening the angle between Fort Mc-
                Henry and Ferry Bar Section; and for width of
                400 feet in the Curtis Bay section.
Oct. 17, 1940 For  the 22-, 18-, and 15-foot channels in Curtis Creek        Adopted as a national-defense proj-
                from the 22-foot depth below Pennington Ave.                  ect (no printed report).
                Bridge to the upper end of the marginal wharf of
                the United States Ordnance Depot.
Mar. 2, 1945 Uniform main channel 39 feet deep from the ocean                H. Doc. 741, 79th Cong., 2d sess.
                through York Spit Section and Craighill Entrance
                to Fort McHenry, additional anchorage area 2,400
                feet long, 1,200 feet wide, and 30 feet deep; a con-
                necting channel 400 feet wide and 27 feet deep from
                Cutoff-Brewerton Angle in the main channel to the
                Inland waterway from Delaware River to Chesa-
                peake Bay; a channel in Curtis Creek 200 feet wide
                and 35 feet deep from the head of the existing 35-
                foot project channel in Curtis Bay to a point in the
                creek about 750 feet below the Pennington Ave.
                Bridge.
    Do ...... A channel 22 feet deep and 200 feet wide from the 22-          In accordance with plans on filein
                foot depth curve south of the Baltimore & Ohio                 the Office, Chief of Engineers.
                R.R. Bridge to the vicinity of Arundel Cove, a dis-
                tance of about 2,800 feet, thence 100 feet wide in
               Arundel Cove for a distance of about 2,100 feet;
                with an anchorage basin approximately 700 feet
               square adjacent to the channel southwesterly of
               the Coast Guard wharf.


1 Contains latest published maps.


   Local cooperation. The River and Harbor Act of August 8,
1917, required that on all new work under the project approved
by that act, except the channel into Curtis Bay, improvement by
the United States is conditional upon local interests providing,
free of cost to the United States, suitable disposal areas behind
bulkheads or other revetment, satisfactory to the district engi-
neer, whenever required by the Chief of Engineers. This condition
has been met as far as the channel has been completed.
   The River and Harbor Act of July 3, 1930, provided for increased
anchorage facilities subject to the provisions that no work shall be
started on the area therein recommended until local interests have
provided suitable disposal areas satisfactory to the district en-
gineer alongside of bulkheads behind which said interests will
agree to pump the material without delay to the Government work;
198       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

or, in lieu of the above requirement, agree to contribute the sum
of 5 cents per cubic yard, scow measure, to cover the additional
cost to the United States for disposal of the material on its own
dumping area. This condition has been met.
    The River and Harbor Act of March 2, 1945, required that
responsible local interests agree to hold and save the United States
free from claims for damage resulting from the work. This con-
dition has been met in a resolution adopted by the city council
of Baltimore and approved by the mayor on March 1, 1949.
    Terminal facilities. The Port of Baltimore consists of 46 miles
of waterfront, 30 of which miles are developed. There are 271
piers, wharves, and docks in Baltimore Harbor with depths in
the berthing areas ranging up to 40 feet at mean low water. Most
deep draft shipping, other than that handled at the wharves of
the numerous industrial plants, is concentrated at the modern
ocean terminals operated by three trunk-line railroads, the Bal-
timore & Ohio, the Pennsylvania, and the Western Maryland; and
by a terminal railroad, the Canton. All of these terminals are
equipped with depressed or apron tracks permitting the transfer
of cargoes directly between ship and car. Facilities also are pro-
vided at the rail terminals for the receipt and delivery of motor
truck freight. The railroads, with tracks extending to all por-
tions of the port area, have voluntarily granted 5 days free time
on piers to truck freight on both imports and exports. The sup-
porting yards for the railroad terminals can accommodate a total
of 11,800 cars and the combined ground storage capacity is
32,250 cars. Major facilities in the port include 3 grain elevators
with a total capacity of approximately 12 million bushels, 15
modern ore cranes with a total rated unloading capacity of more
than 11,000 tons per hour, 30 public general merchandise ware-
houses, 3 modern coal storage facilities, 4 coal piers, 13 oil re-
ceiving stations and 2 refining plants, and 12 shipbuilding and
ship repair yards. The shipbuilding and repair yards are equipped
with facilities for handling every type of vessel construction,
conversion, and repair. The facilities include 11 shipways rang-
ing in length from 150 to 650 feet, 7 floating drydocks with lifting
capacities of from 6,000 tons to 20,000 tons, 2 graving docks and
7 marine railways in addition to numerous outfitting piers and
shops. All piers are accessible by adequate paved highways. A
municipally owned belt-line railway some 3 miles long encircles
the upper end of the inner harbor and connects the tracks of the
Baltimore & Ohio, Pennsylvania, and Western Maryland Rail-
roads. The latest description of terminal facilities is contained
in the publication entitled "Port Series No. 10 (Revised 1946)"
on the Port of Baltimore, Md., issued by the Board of Engineers
for Rivers and Harbors.
   The State legislature has authorized the city of Baltimore to
incur an indebtedness of $60 million for further development of
         RIVERS AND HARBORS--BALTIMORE,      MD., DISTRICT      199
  port facilities. The Port of Baltimore Commission, which is
  charged with administration under this authorization, is reviewing
  requests from various companies who desire to obtain funds for
  construction and reconstruction of port facilities. The Commission
is presently processing applications for loans totaling more than
 $41 million. The Commission expects work utilizing most of these
funds to begin in the near future. Under authorization granted
by the former Port Development Commission, the following work
was completed: An $8,500,000 terminal pier at Port Covington,
and a $1,500,000 terminal pier on the Canton area of the port.
The Port of Baltimore Commission, with more liberal financing
powers, replaced the Port Development Commission.
    The City of Baltimore expends about $100,000 annually for
rehabilitation of existing structures.
    Operationsand results during fiscal year. New work dredging
by contract to provide project depth in the remaining uncompleted
800 feet width of the Brewerton-Fort McHenry angle and project
dimensions in a portion of the Fort McHenry section to complete
the main channel, was continued and completed October 12, 1953.
A total of 210,561 cubic yards, place measure, of material was re-
moved and deposited on the authorized dumping area in Chesa-
peake Bay at Kent Island, Md.
    New work dredging, by contract, to provide project dimensions
in the remaining portion of the Fort McHenry section was com-
menced January 28, 1954, and completed March 18, 1954. A total
of 317,889 cubic yards, place measure, of material was removed
and deposited on the authorized dumping area in Chesapeake Bay
at Kent Island, Md.
    Maintenance dredging, by contract, to restore previous projects
dimensions in portions of the Brewerton-Fort McHenry angle and
the Fort McHenry section was continued 'and completed October
12, 1953. A total of 70,249 cubic yards, place measure, of material
was removed and deposited on the authorized dumping area in
Chesapeake Bay at Kent Island, Md.
    Condition surveys and estimates of yardage of shoal material
were made during the fiscal year in all reaches of the main channel,
by hired labor.
    The total costs were $525,317, of which $427,574 was for new
work, and $97,743 was for maintenance.
    Condition at end of fiscal year. The existing project, excluding
the York Spit Channel which is under the jurisdiction of the Nor-
folk District, is about 85 percent complete.
    The work remaining to be done on the existing project, excluding
York Spit Channel, is completion of the Ferry Bar section from
Port Covington entrance channel to Ferry Bar; and completion of
the Spring Garden section, including a turning basin, from Ferry
Bar to the Western Maryland Railway bridge.
200                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

     The controlling dimensions are as follows:

                                    Section                                             Depth        Width            Date
                                                                                        (feet)       (feet)        ascertained

Craighill Entrance--...-..-------------------------------------                             38.0    600-1, 500   April 1954.
Craighill Section---...     --------------------------------------                          39. 0          600   March 1954.
Craighill-Cutoff Angle -----------    ---------              ------        ------           38.0    600-1, 729   March 1954.
Cutoff Section-....------------------                     -------------------               38. 0          500   May 1954.
Cutoff-Brewerton Angle-----                           ----                                  38.0    600-1, 540   May 1954.
Brewerton Section---                                                                        38.6           600   May 1953.
Brewerton, Fort McHenry Angle_                                                              40. 3   600-1, 240   May 1953.
Fort McHenry Section__--                                                                    39. 0          600   October 1952.
Northwest Branch (Inner Harbor):
     East Side Channel_......-------------------------                                      35.0          950    June 1950.
     West Side Channel ____           _......           ..--.               .....----       35. 0         950    June 1950.
     Turning Basin_.......-------------------                             --.---            30.0    950-1,200    June 1950.
Curtis Bay ...      ----- -----   ---- -----       ---- ----- ----                          35.0          400    October 1951.
Ferry Bar (to a point opposite Western Maryland Ry. piers)___                               35. 0         400    October 1951.
Ferry Bar (from a point opposite Western Maryland Ry. piers                                 19. 0         170    January 1950.
  to Ferry Bar).
Spring Garden Channel (Ferry Bar to Hanover St. Bridge) .-.                                 19.0          180    January 1950.
Spring Garden Channel (to old Southwest Baltimore Channel).                                  9. 5         250    August 1938
Connecting Channel to the Inland Waterway from Delaware                                     25.0          400    April 1954.
  River to Chesapeake Bay
Quarantine Anchorage ---------                                                              35.0           450   May 1951.
Fort McHenry Anchorage ---------------- --------------                                      34.0           400   July 1946.
Riverview Anchorage No. 1------------------------------------                               33.0        1, 500   June 1952.
Riverview Anchorage No. 2-...................................                               30.0        1, 200   February 1952.
Curtis Creek:
    Main Channel---     ..-   -------    -------------------                                35. 0         200    June 1948.
    Approach channel to Ordnance Depot .                       -----------                  22. 0         200    July 1941.
    Southerly Anchorage Area .-------------------------------                               15. 5         450    July 1941.
    Easterly Anchorage Area---....-----------------------------                             18. 2         320    July 1941.
    Channel to Arundel Cove -------------------------------                                 19. 4         200    April 1946.
     Channel in Arundel Cove.......----------                  .....-------- --..           21.1          100    April 1946.
    Anchorage Basin in front of Coast Guard Yard .............                              20. 5         700    April 1946.



The total costs under the existing project (including York Spit
Channel prior to fiscal year 1942) were $15,288,043, of which
$8,324,035 was for new work and $6,964,008 was for maintenance.
                                              Cost and financial summary

                                                        Fiscal year ending June 30                                Total to June
                                                                                                                 30, 1954, includ-
                                                                                                                 ing fiscal years
                                       1950            1951           1952               1953        1954        priorto 19501

New work:
   Appropriated --------             $650, 000       $650, 000       $800,000           $497, 000   $250,000         $17, 112, 599
   Cost----.-------.----               82, 364      1, 029, 700       619, 330           709, 960    427, 574         17, 088, 038
Maintenance:
   Appropriated-------..               461, 436       431, 491        369, 500           335, 000     33, 761           7, 378, 374
   Cost..---------------               445, 014        42, 073        698, 355           345, 932     97, 743           7, 363, 810

  1 Includes $8,764,003 for new work and $399,802 for maintenance for previous projects.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954..._...................                                      $24,560
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955..............................                                                                       24 ,560
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project-....-----........................... . . .......................                  1 ,590,400

                2. BALTIMORE HARBOR, MD., COLLECTION AND
                            REMOVAL OF DRIFT

   Location. The project applies to Baltimore Harbor, Md., and
its tributaries.
   Existing project. This provides for the collection and removal
               RIVERS AND HARBORS-BALTIMORE, MD., DISTRICT                                       201
of drift from Baltimore Harbor and its tributary waters, and au-
thorizes the Secretary of the Army to allot such amounts as may be
necessary for the work from appropriations for maintenance and
improvement of existing river and harbor works or other available
appropriations, and that this work shall be carried as a separate
and distinct project. It is wholly a work of maintenance. The
purpose of the work is to afford relief from variable conditions of
obstruction.
   The existing project was authorized by the River and Harbor
Act of June 30, 1948.
   Terminal facilities. Described in the report for Baltimore Har-
bor and Channels, Md.
   Operationsand results during fiscal year. Operations, by hired
labor, consisted of the collection and disposal of 42,309 cubic feet
 (330.5 cords) of driftwood, ranging from small blocks up to timbers
of large dimensions. The total costs, all for maintenance, were
$36,600.
   Condition at end of fiscal year. The existing project is one of
continuous maintenance for which no percentage of completion
exists. Navigation has been made safer by continual patrol of the
harbor and removal of drift material. The total costs, all for main-
tenance, were $214,519.
                                    Cost and financial summary

                                          Fiscal year ending June 30                    Total to June
                                                                                       30, 1954, includ-
                                                                                        ing fiscal years
                             1950        1951        1952        1953       1954         prior to 1950

Maintenance:
   Appropriated  --------    $60, 000    $57, 919   $30, 000     $30, 000   $38, 000          $215, 919
   Cost._ ._____ .____ .._    57, 919     55,144     33, 759      31,097     36, 600           214, 519



                                3. CHESTER RIVER, MD.

   Location. Chester River rises in Kent County, Del., flows in a
generally southwesterly direction, and empties into Chesapeake
Bay. Its total length is about 50 miles. Kent Island Narrows is a
passage connecting Chester River and Eastern Bay. Wells Cove
is an indentation on the easterly side of Kent Island Narrows about
0.4 mile south of the highway bridge crossing the Narrows. (See
U. S. Coast and Geodetic Survey Charts Nos. 548 and 1226.)
   Previous projects. The original project for the main river was
adopted by the River and Harbor Act of March 3, 1881. For
further details, see page 333 of Annual Report for 1935.
   Existing project. Provides for a channel 6 feet deep at mean
low water and 60 feet wide from Crumpton to Jones Landing, the
length of the section included in the project being about 5.5 miles,
the lower end of the section being about 37 miles above the mouth
of the river; for a channel 7 feet deep at mean low water and 100
feet wide from Chester River to Eastern Bay through Kent Island
Narrows; and a channel 7 feet deep at mean low water and 75
feet wide, extending from the 7-foot depth curve in Kent Island
Narrows 800 feet into Wells Cove with a basin of the same depth
202      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

and 300 feet square at the head of the channel. The mean range
of tide is 2.4 feet.
   The estimate of cost for new work, revised in 1954, is $48,000,
exclusive of the amount expended on previous projects. The latest
 (1950) approved estimate for annual cost of maintenance is $2,200.
The existing project was adopted by the River and Harbor Acts
of March 3, 1873, and September 19, 1890 (H. Ex. Doc. 65, 51st
Cong., 1st sess.), and June 30, 1948 (H. Doc. 380, 80th Cong., 1st
sess.). Maps of the locality are printed in House Documents 797
and 1587, 63d Congress, 2d and 3d sessions, respectively, and in
House Document 380, 80th Congress, 1st session.
   Local cooperation. Fully complied with except that local inter-
ests are required to furnish spoil disposal areas for future main-
tenance of the Wells Cove section of the project. Assurances of
local cooperation were accepted by the Secretary of the Army on
February 16, 1950.
   Terminal facilities. There are two bulkhead wharves on the
Chester River section, in poor condition, with dockage room of 100
and 120 feet, and available depths of 2 and 6 feet, respectively. In
Kent Island Narrows there are 8 timber pile wharves adjacent to
crab and oyster houses, in fair condition, aggregating approx-
imately 700 lineal feet of dockage, with available depths of from 3
to 13 feet. In Wells Cove there is a small wharf, a small marine
railway, and a public landing. All of the facilities are privately
owned except the public landing on Wells Cove. The facilities are
considered adequate for existing commerce.
   Operations and results during fiscal year. A condition survey
and an estimate of yardage of shoal material to be removed was
completed by hired labor. The total costs, all for maintenance,
were $1,405.
   Condition at end of fiscal year. The existing project is about 72
percent complete. The work remaining to be done to complete the
project is to widen the channel from the 75-foot dredged width
to the 100-foot project width in the Kent Island Narrows section.
The controlling depths, at mean low water, were 2.4 feet from
Crumpton to Jones Landing, ascertained in October 1946; 7.7 feet
in the Kent Island Narrows section from Eastern Bay to the bridge,
ascertained in June 1954; 2.6 feet from the bridge to Chester River,
ascertained in June 1954; 7.0 feet in the Eastern Bay section,
ascertained in June 1954; and 7.7 feet in the channel and anchor-
age basin in Wells Cove, ascertained in May 1950. The total costs
were $140,210, of which $32,453 was for new work and $107,757
was for maintenance.
                  RIVERS AND HARBORS-BALTIMORE, MD., DISTRICT                                                     203
                                                 Cost and financial summary

                                                        Fiscal year ending June 30                      Total to June
                                                                                                       30, 1954,1 includ-
                                                                                                       ing fiscal years
                                          1950        1951             1952          1953   1954         prior to 1950

New work:
   Appropriated ...-----..
                  --                      $16, 400   $-2, 008 --------------------                               $70, 495
   Cost--    -                             14, 317         76     -                                               70,495
Maintenance:
    Appropriated-...---..                  14, 900      -- 644                               $2, 000             108, 352
    Cost..............-----------------    14, 141         220   ---------                    1, 405             107, 757

  1 Includes $38,041 for new work for previous projects.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project __......-....... .... ...................... $15,500

                                          4. CAMBRIDGE HARBOR, MD.
   Location. This harbor is a tidal estuary on the south side of
Choptank River about 18 miles above its mouth. It is approx-
imately 70 miles southeast of Baltimore Harbor. (See U. S. Coast
and Geodetic Survey Chart No. 1225.)
   Previous projects. The original project was adopted by the
River and Harbor Act approved March 3, 1871, and was modified
by the acts of August 11, 1888, and June 13, 1902. For further
details see page 1789 of Annual Report for 1915, page 424 of
Annual Report for 1924, and page 373 of Annual Report for 1938.
   Existing project. This provides for a channel 150 feet wide and
16 feet deep at mean low water from that depth in Choptank River
to the Market Street Bridge over Cambridge Creek, thence 100 feet
wide and 16 feet deep to the head of the harbor, with a turning
basin of the same depth and of irregular dimensions comprising
approximately 2.4 acres; an anchorage basin 10 feet deep, 400 feet
long and 175 feet wide on the west side of the channel and a second
basin of the same depth 225 feet long and 200 feet wide on the
east side of the channel below the bridge; and a channel 60 feet
wide and 7 feet deep from that depth in Choptank River to the
municipal boat basin north of the harbor entrance. The mean
range of tide is about 1.7 feet.
   The estimated cost for new work, revised in 1954, $223,000 ex-
clusive of amounts expended on previous projects. The latest
(1949) approved estimate of cost for annual maintenance is $3,400.
   The existing project was authorized by the following River and
Harbor Acts:
204             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

    Acts                          Work authorized                                  Documents
Mar. 3,1925     Channel 12 feet deep and 150 feet wide to the draw-     H. Doc. 210, 68th Cong., 1st sess.
                 bridge 10 feet deep and 100 feet wide from the
                 bridge to the upper end of the harbor with a turn-
                 ing basin.
Aug. 26, 1937   Channel 14 feet deep from that depth in Choptank        Rivers and Harbors Committee
                 River to the head of the harbor with widths of           Doe. 7, 75th Cong., 1st sess.
                 150 feet below the Market St. Bridge in Cam-
                 bridge and 100 feet above, and a turning basin
                 of the same depth at the head of the channel;
                 for an anchorage basin 10 feet deep, 400 feet long,
                  and 175 feet wide on the west side of the channel
                  and a second basin of the same depth 225 feet
                 long and 200 feet wide on the east side of the chan-
                 nel; and a channel 60 feet wide and 7 feet deep
                 from that depth in Choptank River to the muni-
                  cipal boat basin.
June 30, 1948   Modification providing for present project.             H. Doc. 381, 80th Cong., 1st sess.
                                                                         Contains latest published maps.


   Local cooperation. Local interests are required to furnish free
of cost to the United States, all necessary rights-of-way and suit-
able spoil-disposal areas for the initial work and subsequent main-
tenance, as and when required; hold and save the United States
free from damage due to construction works; remove the wrecks
which lie in the area to be dredged at the head of the creek; and
lower the water main crossing the creek north of the Market
Street bridge. It is believed that these terms will be met.
   Terminal facilities. The water front of Cambridge is generally
built up of solid bulkhead wharves and pile and timber piers, only
a few of which have mechanical freight-handling facilities. With
the exception of a municipally owned terminal which is open to
the public, the wharves are privately owned. There are two marine
railways with boat-repair shops, five oil and gasoline terminals,
two large fertilizer companies and one large packing house located
on the shores of Cambridge Creek. The facilities are generally
adequate for existing commerce.
   Operations and results during fiscal year. A condition survey
and an estimate of yardage of shoal material to be removed was
completed by hired labor. The total costs, all for maintenance,
were $1,500.
   Condition at end of fiscal year. The existing project is 9 per-
cent complete. The work remaining to be done consists of that
work authorized by the River and Harbor Acts of August 26, 1937,
and June 30, 1948. The controlling depths at mean low water,
were 9.8 feet in midchannel for half-project width above the draw-
bridge to the turning basin at head of Cambridge Harbor, and 4.8
feet in the turning basin, ascertained in June 1954; and 5.4 feet
in the approach channel to the yacht basin, ascertained in July
1946. The total costs were $29,824, of which $20,653 was for new
work, and $9,171 was for maintenance.
               RIVERS AND HARBORS-BALTIMORE, MD., DISTRICT                                                       205
                                         Cost and financial summary

                                                  Fiscal year ending June 30                            Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                                  1950           1951          1952          1953           1954        prior to 1950

New work:
    Appropriated_                      ------------ ------------
                             ------------                                   ----------------------              $81, 974
    Cost..  --------                   ------------ ------------
                             ------------                                     -- ---------------------           81, 974
Maintenance:
    Appropriated --------.------------.------------. _...                                    $1, 500              9, 171
    Cost---------     ------------ -----------------------------------                        1, 500              9,171


  1 Includes $61,321 for new work for previous project.
Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project----............................................----------......... $202,300

5. HONGA RIVER AND TAR BAY (BARREN ISLAND GAPS),                                                                 MD.
   Location. Honga River is a tidal estuary of Chesapeake Bay
and penetrates Dorchester County on the Eastern Shore of Mary-
land between Hooper Islands and the mainland; Tar Bay is a water
area between Barren Island and the mainland peninsula and Hooper
Islands. Fishing Creek connects Tar Bay and Honga River. Back
Creek is a branch of Honga River extending into upper Hooper
Islands, the mouth is about 2 miles south of Fishing Creek. (See
U. S. Coast and Geodetic Survey Chart No. 1224.)
   Existing project. This provides for a channel 60 feet wide and
7 feet deep at mean low water from the 7-foot contour in Chesa-
peake Bay, through Tar Bay and Fishing Creek to the 7-foot con-
tour in Honga River, a length of 25,300 feet; and for a channel in
Back Creek 7 feet deep and 60 feet wide from the 7-foot depth
curve in Honga River to a point near the head of Back Creek, with
a turning basin of the same depth, 150 feet long and 200 feet wide
at the head of the channel, a length of about 5,500 feet. The mean
range of tide is about 1.4 feet.
   The estimate of cost of new work, revised in 1954, is $73,000.
The latest (1950) approved estimate of cost of annual maintenance
is $7,000. The existing project was adopted under the provisions
of the Emergency Relief Appropriation Act of 1935 and by the
River and Harbor Act of August 30, 1935 (Rivers and Harbors
Committee Doc. 35, 74th Cong., 1st sess.), and modified by the
River and Harbor Act of June 30, 1948 (H. Doc. 580, 80th Cong.,
2d sess.). Maps are published in the project documents.
   Local cooperation. The project was modified subject to the con-
ditions that local interests provide, without cost to the United
States, all necessary lands, easements, rights-of-way, and disposal
areas for execution of the project and for subsequent maintenance,
as and when required; hold and save the United States free from
206            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

damages due to construction and maintenance of the project; and
provide and maintain, without cost to the United States, a suitable
public landing and approach channel. Local interests have con-
structed the public landing, have made available sufficient spoil
disposal areas, and are prepared to dredge the approach channel
to the landing at the time the project is dredged.
   Terminal facilities. Numerous small private wharves are scat-
tered along Fishing Creek and Back Creek. A public wharf is
located on Fishing Creek. A public wharf, four oyster houses,
and a marine railway are located on Back Creek. The facilities
are adequate for existing and reasonably prospective commerce.
   Operations and results during fiscal year. A condition survey
and an estimate of yardage shoal material to be removed was com-
pleted by hired labor. The total costs, all for maintenance, were
$2,096.
   Condition at end of fiscal year. The existing project is about
39 percent complete. The channel from Chesapeake Bay, through
Tar Bay and Fishing Creek to Honga River, was completed in
1935. The work remaining to be done is the Back Creek section
of the project, which was authorized by the River and Harbor Act
of June 30, 1948. The controlling depth in the Honga River and
Tar Bay section of the project was 3.7 feet, at mean low water,
ascertained in May 1954. The condition of the Back Creek section
is as described in the project document. The total costs were
$84,070, of which $27,668 (Emergency Relief funds) and $951
 (regular funds) were for new work and $55,451 was for mainte-
nance.
                                        Cost and financial summary

                                               Fiscal year ending June 30                    Total to June
                                                                                             30, 1954, includ-
                                                                                             ing fiscal years
                                 1950         1951        1952        1953        1954         prior to 1950
New work:
   Appropriated--------
   Cost----.....------------..
                     ...
                                 $42, 000
                                      868
                                            $-41, 049 .     .-----------------------.------------
                                                   82 -----------------------------------
                                                                                                    1$28,619
                                                                                                  128, 619
Maintenance:
    Appropriated...----....----------.
                                    ---------------.       $2, 500     $-594       $2,400              55, 755
                           ------------ ------------
    Cost-........------------.........-                     2,989     -1, 083       2, 096             55, 451

  1 Includes $27,668 Emergency Relief funds.


Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project__... .........           ..$44,400
                                                                .........
                                                           .........
                                                       .......
                                                  ___....

                                   6. WICOMICO RIVER, MD.
   Location. This river has its source in the northern part of
Wicomico County, Md., and flows in a generally southwardly
direction, emptying into Monie Bay, a tributary of Tangier Sound.
 (See U. S. Coast and Geodetic Survey Charts Nos. 77 and 567.)
   Previous projects. Adopted by River and Harbor Act of June
10, 1872. For further details see page 1789 of Annual Report for
1915, and page 380 of Annual Report for 1938.
   Existing project. This provides for a channel 14 feet deep and
150 feet wide from Chesapeake Bay to Salisbury, the length of
the section included in the project being about 37 miles, including
about 12 miles from the mouth of the river to Chesapeake Bay;
                  RIVERS AND HARBORS-BALTIMORE, MD., DISTRICT                                            207
a depth of 14 feet in the channels and turning basins in the North
and South Prongs with channel widths of 100 feet and a basin 6
feet deep, 100 feet wide, and 400 feet long at Webster Cove with a
channel of the same depth and 60 feet wide, extending to the
6-foot contour in Wicomico River. The plane of reference is mean
low water. Mean range of tide is about 3 feet and the extreme
tidal range is 4.4 feet.
   The cost to the Federal Government for new work, for the com-
pleted project is $457,847, exclusive of amount on previous proj-
ects. The latest (1950) approved estimate for annual cost of
maintenance is $15,000.
   The existing project was authorized by the following river and
harbor acts:

       Acts                         Work authorized                                   Documents

Sept. 19, 1890    Channel 9 feet deep from Main St. Bridge to about        H. Doc. 20, 51st Cong., 1st sess.
                   "2 miles below.                                           and Annual Report, 1890, p. 947.
June    5, 1910   Extension of 9-foot depth into the North Prong from      H. Doc. 569, 61st Cong., 2d sess.
                   Main St. Bridge to the Salisbury Dam and turn-
                   ing basin.
Mar.    2,1919    Extension of 9-foot depth into South Prong to the        H. Doc. 1509, 63d Cong., 3d sess.
                   head of navigation at Cathell St., including a turn-
                   ing basin and extending the project down to the
                   mouth of the river in Monie Bay.
July 3, 1930      A 12-foot channel below the Main St. Bridge.
Aug. 26, 1937     A 14-foot channel, 150 feet wide, depths of 14 feet in   Senate   committee    print, 75th
                   the North and South Prongs and a basin 6 feet             Cong., 1st sess. (Contains latest
                    deep at Webster Cove and approach channel there-         published map.)
                    to of the same depth.


   Local cooperation. Fully complied with except local interests
are to furnish spoil disposal areas as required for future mainte-
nance.
   Terminal facilities. The present water front at Salisbury con-
sists of pile-and-timber bulkheads with earth fills. Some of the
wharves have warehouses and factories with mechanical freight-
handling facilities and rail sidings. With the exception of a wharf
on the North Prong owned by the State roads commission, and a
wharf on the South Prong, owned by the county, all of the termi-
nals are privately owned. A shipyard, with two marine railways
with capacities of 1,200 and 500 tons, respectively, is located on
the right bank of the river below the Prongs. Areas for the de-
velopment of new terminals on the North and South Prongs are
limited. Areas for a considerable expansion of terminal facilities
are available on the main river. A public wharf on the main river
at Salisbury is desirable but not essential.
   There is a pile-and-timber wharf which is situated about 4 miles
above the mouth of the river at Mount Vernon. There is a wharf
of similar construction at White Haven.
   Operations and results during fiscal year. A condition survey
and an estimate of yardage of shoal material to be removed from
the Webster Cove Channel was completed by hired labor. The
total costs all for maintenance were $1,213.
    Condition at end of fiscal year. The existing project was com-
pleted in 1942 except for the removal of boulders and debris which
were encountered in the South Prong at the Division Street bridge.
The controlling depths, at mean low water, were 11 feet in the
208              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

main river channel, ascertained in November 1948 and April 1949;
12.5 feet in the North Prong for half-project width and 10 feet
in the remainder ascertained in November 1948 and April 1949;
13 feet in the South Prong for half-project width and 7 feet in the
remainder, ascertained in August 1947; 2.1 feet in the Webster
Cove Channel for 80 percent of the project width, ascertained in
April 1954; and 2.5 feet in the Webster Cove basin for 80 percent
of the project width, ascertained in April 1954.
  The total costs were $792,376, of which $457,847 (regular funds)
and $14,000 (contributed funds) was for new work, and $320,529
was for maintenance.
                                        Cost and financial summary

                                                 Fiscal year ending June 30                         Total to June
                                                                                                    30, 1954, includ-
                                                                                                     ing fiscal years
                                 1950           1951           1952          1953        1954         prior to 1950

New work:
   Appropriated--_                                                 -----------------------                   457, 847
                                                                                                           $--------------------
   Cost------------          ----------------------------------------------- --------                      1 457, 847
Maintenance:
   Appropriated                 $-2, 925 ------------------- --------------               $1, 500            320, 816
   Cost-----------------            7,706---------------------------------............     1, 213            320, 529


  1In addition, $14,000 was expended from contributed funds for new work.

                                   7. POCOMOKE RIVER, MD.
   Location. This river is a tributary of Pocomoke Sound, an
estuary of and on the easterly side of Chesapeake Bay about 40
miles north of Cape Charles, Va.
   Previous projects. The original project for Pocomoke River
was adopted June 18, 1878, and modified by the River and Har-
bor Act of August 5, 1886. For further details, see page 1789,
Annual Report for 1915, and page 385, Annual Report for 1938.
   Existing project. This provides for a channel 7 feet deep and
100 feet wide from that depth in Pocomoke Sound through "The
Muds" to deep water in the river; and a channel 9 feet deep at
mean low water and 100 to 130 feet wide from Shad Landing to
above the bridge at Snow Hill, widened to 150 feet to form a
turning basin at the upper end, the length of the section included
in the project being about 4.5 miles, the lower end of the section
being about 25.7 miles above the mouth of the river. The mean
range of tide is 2.5 feet and the extreme tidal range is 3.7 feet.
   The estimated Federal cost of new work, revised in 1954, is
$183,000, exclusive of amounts expended under previous projects.
The latest (1950) approved estimate of cost for annual mainte-
nance is $21,000.
   The existing project was authorized by the following River
and Harbor Acts:
    Acts                            Work authorized                                       Documents
June 3, 1896      A 9-foot channel from Shad Landing to Snow Hill....-- Annual report for 1895, p. 1167.
Aug. 30,1935      For a channel 7 feet deep and 100 feet wide from      H. Doc. 227, 74th Cong., 1st sess.
                    Pocomoke Sound to Pocomoke River.                                                      1
Mar. 2,1945       Extension of channel above bridge at Snow Hill, H. Doc. 429, 76th Cong., 1st sess.
                    100 feet wide, 9 feet deep, widened to 150 feet to
                    form a turning basin at the upper end.

1 Contains latest published maps.
         RIVERS AND HARBORS-BALTIMORE, MD., DISTRICT              209
    Local cooperation. Fully complied with for the section of the
project from Pocomoke Sound to Pocomoke River and from
Shad Landing to the highway bridge at Snow Hill, authorized
by the acts of June 3, 1896, and August 30, 1935, except that local
interests are required to furnish releases from damage to oyster
beds and spoil disposal areas as required for future maintenance.
    The terms of local cooperation for the section of the project
above the highway bridge at Snow Hill, authorized by the Act
of March 2, 1945, have not been met. These terms are as fol-
lows: That local interests furnish, free of cost to the United
States, all lands, easements, and rights-of-way and spoil disposal
areas for the initial work and for subsequent maintenance, when
and as required; hold and save the United States free from
claims for damages resulting from the improvement; and con-
tribute one-half the initial cost of that portion of the project,
but not to exceed $4,250. Local interests are continuing their efforts
to comply with these requirements.
    Terminal facilities. The present waterfronts at Pocomoke City
and at Snow Hill consist of pile-and-timber bulkheads with earth
fills. Some have warehouses and factories with mechanical han-
dling facilities and rail sidings. Practically all are privately
owned; most of them are in bad repair. Any appreciable in-
crease in commerce at Pocomoke City would necessitate the con-
struction of a new terminal and the repair of existing terminals.
Considerable land areas are available for the development of
additional terminals if and when needed.
    Operations and results during fiscal year. Maintenance dredg-
ing, by contract, to restore "The Muds" section of the project
to authorized dimensions was continued and completed during
the fiscal year. A total of 66,615 cubic yards of material, place
measure, was removed and deposited on authorized spoil areas.
The total costs, all for maintenance, were $33,789.
    Condition at end of fiscal year. The existing project is 89 per-
cent complete. The work remaining to be done is the extension
of the channel to above the bridge at Snow Hill. The controlling
depths, at mean low water, are as follows: 8 feet through "The
Muds" to deep water in the river on the east side of Williams
Point, ascertained in July 1953; 9 feet in the section in Pocomoke
River from Shad Landing to Snow Hill, ascertained in March,
1948; and 3.4 feet in the natural channel above the bridge at
Snow Hill ascertained in 1939. The total costs were $423,401,
of which $161,926 was for new work and $261,475 was for main-
tenance.
210               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                           Cost and financial summary

                                                     Fiscal year ending June 30                          Total to June
                                                                                                        30, 1954, includ-
                                                                                                        ing fiscal years
                                   1950          1951             1952           1953         1954       prior to 1950 1

New work:
    Appropriated..        _ ___......           $-5,531    ------------                                         $182, 426
   Cost .....                             $40 __ .       .-----      _-182,                                            426
Maintenance:
    Appropriated -                 -2, 403 ------------           $90, 000   -----------.    $-8, 229            261, 475
    Cost--                  -        13, 714---
                                             ........---..          2, 198       $45, 784     33, 789            261, 475


  1Includes $20,500 for new work for previous projects.
Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project .. ___.. __........_.____....................... $21,100
       8. TWITCH COVE AND BIG THOROUGHFARE RIVER, MD.
   Location. This is a tidal waterway about 4 miles long travers-
ing Smith Island, Md., in a southeasterly direction from Chesa-
peake Bay on the west to Tangier Sound on the east. (See U. S.
Coast and Geodetic Survey Chart No. 1224.)
   Existing project. This provides for a channel 7 feet deep at
mean low water and 60 feet wide from Twitch Cove on Tangier
Sound through Big Thoroughfare River, thence through the canal
at Ewell, Md., thence through Levering Creek and Big Thorough-
fare River to the vicinity of Swan Point, thence of the same depth
and 100 feet wide through the offshore bar to deep water in Chesa-
peake Bay, with twin stone jetties at the entrance, the north jetty
being about 2,080 feet long, and the south jetty being about 1,800
feet long; an anchorage basin 7 feet deep, 100 feet wide, and 700
feet long connecting with the west side of the existing project
channel at Ewell; extension of the existing project channel in
Levering Creek, 6 feet deep, 60 feet wide, and 1,000 feet long; and
for a channel 4 feet deep and 25 feet wide around the point between
Big Thoroughfare River and Tylers River. The mean range of tide
is 1.7 feet, and the extreme tidal range is 3 feet.
   The estimate of cost for new work, revised in 1954, is $191,000.
The latest (1950) approved estimate for annual cost of mainte-
nance is $5,000.
   The existing project was authorized by the following River and
Harbor Acts:
       Acts                             Work authorized                                       Documents
July 25, 1912     A channel 4 feet deep and 25 feet wide from Tangier              H. Doc. 285, 62d Cong., 2d sess.
                   Sound into Big Thoroughfare River, and one of
                   the same dimensions around the point between
                   said river and Tylers River.
July    3, 1930   A channel 5 feet deep at mean low water and 25 feet              H. Doc. 313, 71st Cong., 2d sess.
                   wide from Twitch Cove on Tangier Sound through
                   Big Thoroughfare River to a point on Levering
                   Creek about 800 feet north of the canal at Ewell,
                    Md.
Aug. 30, 1935     A channel 7 feet deep and 60 feet wide from Twitch               Rivers and Harbors Committee,
                   Cove through Big Thoroughfare River to a point                    Doc. 67, 74th Cong., 1st sess.
                   on Levering Creek about 800 feet north of the canal
                   at Ewell, Md.
June 20, 1938     Present project dimensions of the main channel with              Rivers and Harbors Committee,
                   twin jetties at the entrance.                                     Doc. 49, 5th Cong., 2d sess.
                                                                                     (Contains latest published maps.)
May 17, 1950      Anchorage basin 7 feet deep, 100 feet wide, and 700              H. Doc. 340, 81st Cong., 1st sess.
                   feet long on west side of project channel at Ewell,
                   Md., and an extension of the existing project chan-
                   nel in Levering Creek, 6 feet deep, 60 feet wide,
                   and 1,000 feet long.
                RIVERS AND HARBORS--BALTIMORE, MD., DISTRICT                                                    211
   Local cooperation. Local interests are required to (1) furnish,
without cost to the United States, all lands, rights-of-way, and
spoil disposal areas for construction and maintenance of the im-
provement, when and as required; (2) hold and save the United
States free from all damages due to the construction and mainte-
nance of the improvement; (3) acquire and reserve for public use
an adequate land area adjacent to the anchorage basin with suit-
able access thereto; and (4) remove all structures within the lim-
its of the proposed improvement. It is believed that these condi-
tions will be met.
   Terminal facilities. There are numerous privately owned pile-
and-timber wharves and bulkheads at Ewell which are open to the
public for business transactions with the owners. A county wharf
is also located at the west end of the town. Five crab houses are
situated on Levering Creek, and one oyster house is located on the
project waterway west of the town of Ewell.
   Operation and results during fiscal year. Operations consisted
of making final payment for contract dredging completed dur-
ing the prior year. The total costs all for maintenance were
$924.
   Condition at end of fiscal year. The existing project was com-
pleted in November 1940, except for work authorized by the River
and Harbor Act of May 17, 1950. The project as a whole is 86
percent complete. The controlling depths, at mean low water,
are as follows: 6.5 feet from Tangier Sound to Ewell, ascer-
tained in September 1951; 7.0 feet from Ewell to deep water in
Chesapeake Bay, ascertained in January 1953; and 4.0 feet in
the channel in Tylers River, ascertained in September 1951. The
condition of the portion of the project authorized by the River
and Harbor Act of May 17, 1950, is as described in the project
document. The north and south jetties have settled in several
places. The north jetty was repaired during 1953. The total
costs were $268,832, of which $164,175 was for new work and
$104,657 was for maintenance.
                                              Cost and financial summary

                                                      Fiscal year ending June 30                     Total to June
                                                                                                     30, 1954, includ-
                                                                                                     ing fiscal years
                                       1950          1951        1952         1953         1954          priorto 1950
New work:
    Appropriated -------------------                ------------ ------------- ----------.......
                                                                                          ..     -----        $164, 175
    Cost-------------------- .                ------------------------- ------------------------               164, 175
Maintenance:
                ------
    Appropriated........               $25, 000   $--11, 468               ............
                                                                 $45, 000 ------------------------             111, 684
    Cost-----------------               14, 709       2, 954       4, 007          $33, 042   $924             104, 657


Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project__..________..................................................... $26,800

                                        9. STARLINGS CREEK, VA.
  Location. Starlings Creek, about 1,500 feet long, is an estuary
of Pocomoke Sound at the southerly end of Saxis Island, Acco-
mack County, Va., about 11 miles southeasterly of Crisfield, Md.
(See U. S. Coast and Geodetic Survey Charts Nos. 1223 and
1224.)
212            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  Existing project. This provides for a channel 7 feet deep at
mean low water and 60 feet wide from that depth in Pocomoke
Sound to the mouth of Starlings Creek, with a turning basin of
the same depth and 1,000 feet long and 100 feet wide inside the
entrance, all essentially as shown on the project map. The mean
range of tide is 2.4 feet. The total cost for new work for the
completed project was $16,537. The latest (1950) approved esti-
mate of cost for annual maintenance is $2,500. The existing
project was adopted by the River and Harbor Act of August 30,
1935. (See Rivers and Harbors Committee Doc. 46, 74th Cong.,
1st sess.) This document contains the latest published map.
  Local cooperation. Fully complied with except that local inter-
ests are to furnish spoil disposal areas as needed for future
maintenance.
   Terminal facilities. There is about 1,000 feet of bulkhead
wharf available inside the creek, a portion of which is at public
property and the balance is in front of the seafood packing
houses.
    Operationsand results during fiscal year.                                   A condition survey
and an estimate of yardage of shoal material to be removed was
completed by hired labor. The total costs all for maintenance,
were $1,303.
   Condition at end of fiscal year. The existing project was com-
pleted in 1937. The controlling depth, at mean low water, was
3 feet, ascertained in March 1954. The total costs were $52,323,
of which $16,537 was for new work and $35,786 was for main-
tenance.
                                       Cost and financial summary

                                               Fiscal year ending June 30                       Total to June
                                                                                               30, 1954, includ-
                                                                                               ing fiscal years'
                                1950          1951         1952          1953       1954         prior to 1950
New work:
   Appropriated-- .-------------            -------------------------------- -----------                $16, 537
   Cost ..---- --------     ---------          ---------- --------------    ------------                  16, 537
Maintenance:
    Appropriated-------- -----------...........----------- ----------------------    $1, 500             35, 983
    Cost-------- --     ----------- -----------------------------------               1, 303             35, 786



                                10. TANGIER CHANNEL, VA.
   Location. This is a tidal channel about 1 mile long, extending
from Tangier Island, Va., in a northeasterly direction to deep
water in Tangier Sound, Chesapeake Bay. (See U. S. Coast and
Geodetic Survey Chart No. 1223.)
   Existing project. This provides for a channel 8 feet deep at
mean low water and 100 feet wide from the 8-foot contour in
Tangier Sound to day marker No. 4, and thence 8 feet deep and
60 feet wide to the town of Tangier, with an anchorage basin
adjacent to the town 400 feet square and 7 feet deep. The length
of the section included in the project is about 1 mile, its lower
end extending into Tangier Sound. The mean range of tide is
1.7 feet and the extreme tidal range is 4.7 feet. The cost for new
work for the completed project was $72,969. The latest (1950)
approved estimate for annual maintenance is $2,250.
                RIVERS AND HARBORS-BALTIMORE, MD., DISTRICT                                                      213
   The existing project was adopted by the River and Harbor
Act of March 2, 1919 (H. Doc. 107, 63d Cong., 1st sess.) ; changes
in channel and anchorage dimensions were authorized by the
Public Works Administration January 3, 1934, and by the River
and Harbor Act of August 30, 1935 (Rivers and Harbors Com-
mittee Doc. 51, 72d Cong., 2d sess.), and modified by the River
and Harbor Act of March 2, 1945 (H. Doc. 141, 77th Cong., 1st
sess.). These documents contain the latest published maps.
   Local cooperation. Fully complied with, except that local inter-
ests are to furnish spoil disposal areas as needed for future
maintenance.
   Terminal facilities. There are three privately owned pile-and-
timber piers and a small marine railway adjacent to the west
side of the anchorage basin at Tangier. The piers are generally
open to the public when not in use by the owners.
   Operations and results during fiscal year. Dredging, by con-
tract, to restore the project to authorized dimensions commenced
May 3, 1954, and was completed May 10, 1954. A total of 31,622
cubic yards of material, place measure, was removed and depos-
ited on the authorized disposal areas. The total costs, all for
maintenance, were $26,929.
    Conditions at end of fiscal year. The project was completed in
April 1948. The controlling depths, at mean low water, are as
follows: 9.5 feet in the approach channel from Tangier Sound
ascertained in May 1954; 5.7 feet in the entrance to the channel,
ascertained in August 1953; and 6.2 feet in the basin, ascertained
in August 1953. The total costs were $161,213, of which $30,969
 (regular funds) and $42,000 (public work funds), were for new
work and $88,244 (regular funds) was for maintenance.
                                          Cost and financial summary

                                                  Fiscal year ending June 30                           Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                                       1950      1951          1952             1953        1954         priorto 1950

New work:
   Appropriated      ------------ ------------------------                 ------------      ----------
                                                                                             --                 $72, 969
   Cost_-- ----------------- --             ___            .-- -   -------------          ---------             1 72,969
Maintenance:
    Appropriated -------------------              $1, 794 -----------------------           $29, 100             90, 415
    Cost-----                                      1, 794--------
                                                           1,--   _-       ------            26, 929             88, 244

  1 Includes $42,000 public works funds.

                    11. WATERWAY ON THE COAST OF VIRGINIA
  Location. The waterway lies between the barrier beach along
the Atlantic Ocean on the east and the Virginia portion of the
mainland peninsula on the west. It extends from the south end of
Chincoteague Bay through a number of creeks, thoroughfares and
bays, to enter Chesapeake Bay in the vicinity of Fishermens Inlet,
just south of Cape Charles, the southern tip of the peninsula, for
a distance of 83.7 miles. (See U. S. Coast and Geodetic Survey
Charts Nos. 1220, 1221, and 1222.)
  Existing project. This provides for an inland waterway 6 feet
deep and 60 feet wide from Chesapeake Bay to Chincoteague Bay,
Va. The mean range of tide is about 3 feet. Greater fluctuations
214        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

in water level are caused by high winds and storms. The estimate
of cost for new work, revised in 1954, is $759,000. The latest
(1950) approved estimate for annual cost of maintenance is
$15,000.
   The existing project was adopted by the River and Harbor Act
of June 25, 1910 (H. Doc. 957, 60th Cong., 1st sess.), and modi-
fied by the River and Harbor Act of March 2, 1945 (H. Doc. 268,
76th Cong., 1st sess.). The latest published map is in the project
document.
   Local cooperation. Local interests are to furnish free of cost
to the United States, as and when required, all lands, easements,
and rights-of-way and spoil disposal areas for the initial work and
for subsequent maintenance, and hold and save the United States
free from all claims for damages resulting from the work of im-
provement. These terms have been partially met by local interests.
Local interests are expected to meet the terms when required, and
will furnish spoil disposal areas for subsequent maintenance.
   Terminal facilities. The larger towns in the area adjacent to
the route of the desired improvement have fairly substantial pile
and timber wharves which are used primarily by boats engaged in
the seafood business. There are also a number of small landings
scattered along the shore between the towns. The Pennsylvania
Railroad owns and operates a water terminal at Franklin City.
There are also wharves at the various Coast Guard stations in the
area. All of the wharves are privately owned, but are open to
the public for transaction of business with the owners. No
mechanical freight-handling facilities are available. The termi-
nals are adequate for existing commerce. A material increase in
commerce which would follow the proposed improvement makes
desirable but not essential the erection of adequate terminals at
Chincoteague, Wachapreague, Willis Wharf, and Oyster. Ade-
quate public facilities are available at Ocean City.
   Operations and results during fiscal year. Maintenance dredg-
ing, by contract, to a depth of 4 feet and width of 60 feet in the
channel in Kegotank Bay and a width of 50 feet in Bogues Bay
commenced on June 9, 1954, and was in progress at the end of the
fiscal year. A total of 21,900 cubic yards of material, place
measure, was removed and deposited on the authorized spoil areas.
The total costs all for maintenance were $10,440.
   Condition at end of fiscal year. The existing project is about
14 percent complete. The controlling depths, at mean low water,
were 3 feet in Cat River, ascertained in October 1945, 0 feet in
Bogues Bay, ascertained in April 1954, and 4.0 feet in Kegotank
Bay, ascertained in June 1954. The total costs of the existing
project were $145,927, of which $107,298 was for new work and
$38,629 was for maintenance.
                 RIVERS AND HARBORS-BALTIMORE, MD., DISTRICT                                                        215
                                            Cost and financial summary

                                                         Fiscal year ending June 30                        Total to June
                                                                                                          30, 1954, includ-
                                                                                                          ing fiscal years
                                    1950               1951             1952    1953           1954         priorto 1950

New work:
   Appropriated ----                                                                                                  298
                                                                                                                  $107,
   Cost                                 .....                                                                      107,298
Maintenance:
    Appropriated        ---------------------------------------------                          $27, 300             55,488
    Cost                            -           ---------------                                 10,440              38,629



Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project... . .------------------.......... --....-----.......
                                                                                     $651,700
12. OCEAN CITY HARBOR AND INLET AND SINEPUXENT BAY, MD.
   Location. Ocean City is on a barrier island between Sinepuxent
Bay and the Atlantic Ocean about 35 miles south of the entrance to
Delaware Bay. (See U. S. Coast and Geodetic Survey Chart No.
1220.)
   Existing project. This provides for the construction of an in-
let between the Atlantic Ocean and Sinepuxent Bay, with a depth
of 10 feet and width of 200 feet, protected on the south side by a
stone jetty 2,380 feet long and on the north side by a stone jetty
projecting 1,531 feet into the Atlantic Ocean and connected on the
shore to a timber and stone bulkhead 255 feet long, continuing with
a riprap dike 213 feet long and a steel sheet pile bulkhead 460 feet
long, along the shore of the inlet; a channel 6 feet deep and 150
feet wide from the inlet to Green Point, and thence 100 feet wide
into Chincoteague Bay; a channel 10 feet deep at mean low water,
100 feet wide, and 3,000 feet long from the inlet channel into the
marsh area south of the railroad on the west side of Sinepuxent
Bay, with two turning basins of the same depth; and for a channel
6 feet deep and 125 feet wide from the inlet channel to a point
opposite North Eight Street in Ocean City, thence 75 feet wide into
Isle of Wight Bay.
   The cost of new work for the completed project was $350,193,
exclusive of $500,000 contributed by local interests. The latest
 (1950) approved estimate for annual cost of maintenance is $32,-
000. The mean range of ocean tide is 3.4 feet.
   The existing project was authorized by the following River and
Harbor Acts:
     Acts                                Work authorized                                        Documents 1

Aug. 30, 19352   Construction of an inlet between the Atlantic Ocean                  Rivers and Harbors Committee
                  and Sinepuxent Bay, 10 feet deep and 200 feet wide,                   Doc. 38, 72d Cong., 1st sess.
                  protected by jetties, a channel 8 feet deep and 100
                  feet wide from the inlet to Ocean City, 6 feet deep
                  and 150 feet wide to Green Point, and 100 feet wide
       S          into Chincoteague Bay.
    Do _- ..     Modification providing a 10- by 100-foot channel                 Rivers and Harbors Committee
                  from the inlet to the west side of the bay with 2                 Doc. 60, 74th Cong., 1st sess.
                  turning basins, a channel 6 feet deep 125 feet wide
                  from the inlet channel to opposite North 8th St.,
                  Ocean City, and 75 feet wide into Isle of Wight
                  Bay.


  1Contains latest published maps.
  2 Included in Public Works Administration program Sept. 16, 1933. The site chosen for the inlet under
this authorization was that opened just south of Ocean City by natural forces during a severe storm in August
1933. This eliminated the necessity for an 8-foot channel from the inlet to Ocean City.
  ' Included in Emergency Relief program, 1935.
216             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Local cooperation. Fully complied with.
   Terminal facilities. There are two storage basins for pleasure
and small commercial craft and numerous privately owned pile-
and-timber piers and bulkhead wharves on the Sinepuxent Bay
side of Ocean City. The commercial fish harbor has a public bulk-
head landing about 1,000 feet long, several private bulkhead
wharves open to the public for transaction of business with the
owners, and a boat repair yard with a marine railway capable of
handling boats up to about 150 tons. The Baltimore, Chesapeake
& Atlantic Railway has a spur line parallel to and 200 feet from the
commercial fish harbor. Adequate space is available for expansion
of facilities if required.
   Operations and results during fiscal year. A condition survey
and an estimate of yardage of shoal material to be removed com-
menced and was in progress at the close of the fiscal year, by hired
labor. Repair of the steel sheet pile bulkhead on the north side of
the inlet west of Baltimore Avenue commenced September 4, 1953,
and was completed on December 10, 1953, by contract. The total
costs, all for maintenance, were $46,270.
   Condition at end of fiscal year. The existing project was com-
pleted in 1936. The controlling dimensions are as follows:

                                 Section                                         Depth        Width              Date
                                                                                  (feet)      (feet)          ascertained
Inlet Channel----------- ---------------------------------                            5. 0             200   Feb. 1954.
Commercial Fish Harbor..................-----------------------------------..        11. 7             100   July 1948.
Channel to Isle of Wight Bay Inlet to North 9th Street.......                         8. 0             125   Oct. 1944.
  North 9th Street into bay..................---------------------------------        2. 5              75   May 1954.
Channel in Sinepuxent Bay---------------------------------                            5. 0             150   July 1947.
Channel in Chincoteague Bay-------------------------------                            5. 0             100   July 1947.



  Depths refer to mean low water (Atlantic Ocean) at Ocean City,
Md., which datum is lower than that in the bays.
  The total costs of the existing project were $910,758, of which
$283,008 (public works funds) and $67,185 (Emergency Relief
funds) was for new work and $560,565 (regular funds) was for
maintenance. In addition, $500,000 of contributed funds was
expended for new work.
                                           Cost and financial summary

                                                    Fiscal year ending June 30                               Total to June
                                                                                                             30, 1954, includ-
                                                                                                             ing fiscal years
                                   1950           1951           1952             1953          1954          prior to 1950

New work:
                 .......................--..------...--..---.. ----------- ------------------------
    Appropriated----                                                                                                 $350, 193
    Cost -------      ---- ------------
                                     .         ------------ ------------ ------------ ------------                   1 350, 193
Maintenance:
   Appropriated-..-----------------.$-3, 314                      $2, 000         $55, 000 ....-,2-0-                 566, 975
    Cost ...-----------------          $337              113        1, 602           2, 717     $46, 270              560, 565


  1Includes $283,008 public works funds and $67,185 Emergency Relief funds; in addition, $500,000 contrib-
uted funds was expended fornew work.
                RIVERS AND HARBORS-BALTIMORE, MD., DISTRICT                                                                217
                                           13. FISHING CREEK, MD.
    Location. This creek is a narrow winding tidal stream which
enters Chesapeake Bay from the west 56 miles south of Baltimore
and about 26 miles south of Annapolis, Md. (See U. S. Coast and
Geodetic Survey Chart No. 1225.)
   Existing project. This provides for a channel 7 feet deep with
widths of 100 feet and 60 feet from deep water in Chesapeake Bay
to an anchorage of the same depth, 120 feet wide and 400 feet long,
located in the marsh 500 feet above the mouth of the creek, and
for twin stone jetties at the entrance, the north jetty being about
1,050 feet long, and the south jetty being about 1,100 feet long.
The mean tidal range is about 1 foot.
   The cost of new work for the completed project was $111,242.
The latest (1950) approved estimate of cost for annual mainte-
nance is $5,000.
   The existing project was adopted by the River and Harbor Act
of August 26, 1937 (H. Doc. 241, 75th Cong., 1st sess.). The latest
published map is in the project document.
   Local cooperation. Fully complied with, exceptthat local inter-
ests are to furnish spoil disposal areas as needed for future main-
tenance.
    Terminal facilities. Seven hundred feet of bulkhead wharf
are available on the south side of the entrance channel running west
from the bay shore, and a pile-and-timber wharf has been con-
structed on the west side of the basin by the United States Navy
Department.
   Operations and results during fiscal year. Maintenance dredg-
ing by contract to restore the project to authorized dimensions was
commenced and completed during the fiscal year. A total of 36,311
cubic yards of material, place measure, was removed and deposited
on the authorized spoil disposal areas. The total costs, all for
maintenance, were $19,007.
   Condition at end of fiscal year. The existing project was com-
pleted in 1942. The controlling depths, at mean low water, were
7.0 feet in the channel and 7.2 feet in the basin, ascertained in
July 1953. The total costs were $207,536, of which $111,242 was
for new work and $96,294 was for maintenance.
                                              Cost and financial summary

                                                          Fiscal year ending June 30                            Total to June
                                                                                                                30, 1954, includ-
                                                                                                                ing fiscal years
                                      1950              1951                  1952       1953        1954        priorto 1950
New work:
   Appropriated-----            ------------------------------------------------------                                  $111,242
   Cost-----------------                                                                                                 111,242
Maintenance:
    Appropriated ......              $33, 580          $-7,740            -              $24, 344   $-3, 907             96, 294
    Cost       .-----------------      1, 907           23, 932                 ----
                                                                               .--         1, 429     19, 007            96, 294
 218                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                               14. INACTIVE NAVIGATION PROJECTS

                                                                          For last        Cost to June 30, 1954
                                                                              full                                           Estimated
                                                                           report,                                             amount
                      Name of project                                        see                          Operation          required to
                                                                           annual          Con-           and main-          complete"
                                                                         report for      struction         tenance
  1. Middle River and Dark Head Creek, Md....                             1947             1$38, 715           $2, 955                2
2. Susquehanna River above and below Havre
      de Grace, Md............................-------------------------. 1950              3293, 570           89, 423                $30, 700
3. Northeast River, Md.__       ---------------------                    1948               28, 489           11, 802                2
4. Elk and Little Elk Rivers, Md.
                                                 4
                                                    ------------          1932              690, 121           44, 342                    10, 100
5. Rock Hall Harbor, Md...................---                            1953              139, 757           10, 301                    58, 000
6. Corsica River, Md.....-----------------------                         1948               39, 071           55, 908                2
7. Queenstown Harbor, Md..............------------------                 1947             2044, 858           27, 642                2
8. Channel Connecting Plain      5          Dealing Creek
       and Oak Creek, Md.                                                 1940
                                                                          1940                   112   ----.......                    148, 400
9. Claiborne Harbor, Md.------ _________-                                1933               42, 974        48, 584                   2
10. Knapps Narrows, Md...........___-                  _____         -    1951              746, 121        45, 403                   2
11. Black Walnut Harbor, Md.....4 _____-                                - 1950               32, 631 --------------
12. Tilghman Island Harbor,     4
                                        Md.      89 _........             1922                    30                                      11, 000
13. Tred Avon River, Md. 5 _                          -     _______
                                                                  --      1950             1012,693          4, 072                       58, 600
14. Town Creek, Md.-.-------...                        ----------. _      1950               43, 220 -
15. Island Creek, Md.....______.............__....                        1948                6, 230         1, 069               2
16. La Trappe River, Md...........-----                 --           -        1948            8,064            16, 000            2
17.   Choptank River, Md...---------------------
                               8     - - -                                    1953           84, 296         1139,251             2
18.   Tuckahoe River, Md. ..................                                  1923            9, 727           1, 093             2
19.   Warwick River, Md.".----------------------                              1948           22, 041          73, 272             2
20.   Waterway from Little 5Choptank River to
        Choptank River, Md. -139__305--__-                                    1939               305           -_                     105, 000
21.   Slaughter Creek, Md.,.......................                            1948            4, 140            1, 119            2
22.   Duck Point Cove, Md.-___-- ----__                         _____--       1951           25, 289 --
23.   Fishing Bay, Md.__------------------------                              1949           33, 874          46, 529             2
24.   Nanticoke River, Md._ ---------------------                             1950           73, 243           2, 732             2
25.   Nanticoke River (Including Northwest
        Fork), Del. and Md... --------------------                            1953         1748,815            38, 683                 95, 200
26.   Broad Creek River, Del......................
                            8s - - - - - - - - - - - - - - - - - - - - -
                                                                              1950          64, 520            45, 624            2
27.   Tyaskin Creek, Md.                                                      1923          16, 297            18, 266            2
28.   Upper Thoroughfare, Deal Island, Md......                               1953         1262,446         1 359, 790            2
29.   Lower Thoroughfare, at or near Wenona,
        Deal Island, Md.......................----.                           1951          44, 658           142,019             2
30.   Manokin River, Md.                                                 -
                                                        _------------------   1919         1534,788            31, 874            2
31.   Crisfield Harbor, Md.---------------------                              1948        21264,195           225, 724
32.   Broad Creek, Md.__------------------------                              1951          28, 227            58, 742            2
33.   Chincoteague Bay, Va._-------- ---------                8               1949          25, 126           23, 459             2
34.   Governors Run, Calvert County, Md. _ _ _ _                              1950   -------------                                     88, 000
35.   Herring Bay & Rockhold8 Creek,     -- - - - - -Md..-.....
                                                      -- -- -- -- -- -        1948           50, 591           9, 844
36.   Broadwater Creek, Md.'                                          _       1949                                                     97, 200
37.   Parish Creek, Md....
                        s           ___ -            __..........___
                                                                 -_...        1951         1619,170             6, 826            2
38. Cadle Creek, Md. 8s_- -           -- - - - -                              1949--------------------                  --    -        14, 000
39. Lake Ogleton, Md. '                                        _              1950    __._   .. _.......                              119, 000
40. Back Creek, Anne Arundel Co., Md.--------          1946                                  23, 061                89
41. Annapolis Harbor, Md.--------------------1946                                            34, 250            1, 672
42. Mill Creek, Md.1             _                     1949
                                    _------------------------                                                                             14, 000
43. Cypress Creek, Md.---.------_ -                           ---        -1947                3, 057 --------------

   1 Exclusive of $165,681 contributed by U. S. Navy Department.
   2 Completed.
   SIncludes $22,905 Works Progress Administration funds and $97,390 prior to adoption of the existing
project.
   SChannels adequate for present commerce.
   5Awaiting local cooperation for completion of the project.
   8 Exclusive of $8,414 contributed funds. Includes $79,625 expended prior to adoption of the existing project.

   7 Includes $46,121 public works funds.
   8 Abandonment recommended in 1926 (H.Doc. No. 457, 69th Cong., 1st sess.).
   9 Insufficient potential commerce to justify the improvement.
  10oIncludes $6,000 expended prior to adoption of the existing project.
  11 Revoked during fiscal year $604.
  12Includes $37,343 public works funds and $330 for previous project.
  Is Includes $34 for general supervision during fiscal year.
  14Includes $394 for general supervision during fiscal year.
  15Includes costs of $2,000 incurred outside the project limits.
  16Includes $19,170 Works Progress Administration funds.
  17Includes $5,000 for new work for previous project.
  18Funds have not been appropriated for accomplishment of new work.
  19Estimated amount required to complete was revised in 1954.
  20Includes costs of $19,000 for previous projects.
  21Includes costs of $87,740 for previous projects.
  22Includes costs of $2,839 for previous projects.
                     FLOOD CONTROL--BALTIMORE, MD., DISTRICT                                                  219
15. GENEGANTSLET                      RESERVOIR,             GENEGANTSLET CREEK, N. Y.
   Location. The Genegantslet dam site is on Genegantslet Creek,
3 miles above its junction with the Chenango River and about 2
miles west of Greene in Chenango County, N. Y. (See U. S.
Geological Survey quadrangle sheet, "Greene, N. Y.")
   Existing project. The plan of improvement consists of a dam
of the earth-filled type, 1,660 feet long at the top of the embank-
ment and rising 104 feet above the streambed with a gate-con-
trolled outlet and a chute spillway in the left abutment. Outlet
and spillway will be placed on rock. The reservoir will have a
storage capacity of 30,195 acre-feet at spillway crest. The reser-
voir area will be 923 acres, and the pool will extend 4.8 miles
upstream. The reservoir will control 90 percent of the watershed
of Genegantslet Creek, or 6 percent of the Chenango River water-
shed above Binghamton, N. Y. The existing project was author-
ized by the Flood Control Act approved December 22, 1944, as a
modification of the plan for flood control in southern New York
and eastern Pennsylvania authorized by the act of June 22, 1936,
as modified by the acts of June 28, 1938, and August 18, 1941 (H.
Doc. 702, 77th Cong., 2d sess.).
   The estimated Federal cost for new work, revised in 1954, is
$7,600,000, of which $6,841,000 is for construction and $759,000
for lands and damages.
   Local cooperation. None required, as section 2 of the Flood
Control Act, approved June 28, 1938, applies.
   Operations and results during fiscal year. Engineering studies
and preliminary design in connection with revision of the spillway
plan were continued during the fiscal year, by hired labor. The
total costs, all for new work, were $441.
   Condition at end of fiscal year. Foundation studies are com-
plete, except for construction of an exploration tunnel in the spill-
way area for which contract plans and specifications are complete.
Preliminary design plans are complete except for the revisions
resulting from the spillway model study. The work remaining to
be done is completion of foundation investigations, analysis of the
spillway model study report and completion of preliminary design,
preparation of contract plans and specifications, and construction
of the project. The total costs, all for new work, were $211,578.
                                            Cost and financial summary

                                                  Fiscal year ending June 30                         Total to June
                                     __                                                             30, 1954, includ-
                                                                                                    ing fiscal years
                                   1950          1951         1952          1953          1954       priorto 1950

New work:
    Appropriated       -     ------------         22, 000   $-34,000      $-4,000         $-422             $211, 578
    Cost_               --        $25,365         10,909       3,140        2,529            441             211, 578


Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project-------.....-------------................................... $7, 388, 000

         16. SOUTHERN NEW YORK FLOOD CONTROL PROJECT
  Location. The work covered by this project is in the upper
watershed of the Susquehanna River to and including the Chemung
220       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

River. This includes about 6,050 square miles in south central
New York, and about 1,480 square miles in northern Pennsylvania.
(See U. S. Geological Survey index maps of New York and Penns-
sylvania.)
    Existing project. The Flood Control Act approved June 22,
1936, authorized the construction of detention reservoirs and
related flood control works for protection of Binghamton, Hornell,
Corning, and other towns in New York and Pennsylvania, in ac-
cordance with plans approved by the Chief of Engineers on recom-
mendation of Board of Engineers for Rivers and Harbors. The
Flood Control Act approved June 22, 1936, was modified by the
acts approved June 28, 1938; August 18, 1941; December 22, 1944;
and May 17, 1950. The Flood Control Act approved May 17, 1950,
modified the local flood protection plan as originally authorized
for Corning, N. Y., to provide for flood protection on Monkey Run.
    The individual units which constitute the approved plan of im-
provement are described in the following paragraphs:
    Davenport Center Reservoir: This reservoir will be located on
Charlotte Creek near Davenport Center, N. Y. The dam will be
of the earth-filled type, 3,400 feet long at the top of the embank-
ment and rising 100 feet above the stream bed, with a concrete
spillway in the right abutment and the outlet conduit in the valley
floor. The reservoir will provide a storage capacity of 52,500 acre-
feet. The estimated Federal cost of new work, revised in 1954,
is $11,700,000, of which $8,202,000 is for construction and
$3,498,000 is for lands and damages.
    West Oneonta Reservoir: This reservoir will be located on Otego
Creek near West Oneonta, N. Y. The dam will be of the earth-
filled type, 1,200 feet long at the top of the main embankment and
rising 86 feet above the stream bed, with a concrete spillway and
outlet conduit in the right abutment. The main embankment will
be joined at the left abutment by a low dike, 6,700 feet in length.
The reservoir will provide a storage capacity of 34,500 acre-feet.
The estimated cost of new work, revised in 1954, is $11,900,000,
of which $9,084,000 is for construction and $2,816,000 is for lands
and damages.
    East Sidney Reservoir: This reservoir is located on Ouleout
Creek near East Sidney, N. Y. The dam is of the concrete gravity
and earth-filled type, 2,010 feet long at the top of the embank-
ment and rising 128 feet above the streambed, and 146 feet above
firm rock, with five gate controlled outlets in the spillway section of
the dam; 750 feet of the dam, including the spillway, is concrete
gravity section and 1,250 feet is rolled-earth embankment. The
reservoir provides a storage capacity of 33,494 acre-feet. The
estimated Federal cost of new work, revised in 1953, is $5,889,000
of which $5,269,000 is for construction and $620,000 is for lands
and damages.
   Copes Corner Reservoir: This reservoir will be located on But-
ternut Creek near Copes Corner, N. Y. The dam will be of the
earth-filled type, 1,150 feet long at the top of the embankment
and rising 75 feet above the streambed, with a concrete spillway
and outlet conduit in the right abutment. The reservoir will pro-
vide a storage capacity of 37,900 acre-feet.     The estimated Fed-
           FLOOD CONTROL--BALTIMORE,     MD., DISTRICT          221
eral cost of new work, revised in 1954, is $14,100,000, of which
$11,443,000 is for construction and $2,657,000 is for lands and
damages.
   Whitney Point Reservoir: The reservoir is located on the Otselic
River near Whitney Point, N. Y. The dam is of the earth-filled
type, 4,900 feet long at the top of the embankment and rising 95
feet above the streambed, with a concrete spillway and outlet
conduit in the left abutment. The reservoir has a storage capacity
of 86,440 acre-feet. The Federal cost of new work, completed in
1953, was $5,075,000, of which $3,978,533 was for construction
and $1,096,467 was for lands and damages.
   Arkport Reservoir: The reservoir is located on the Canisteo
River near Hornell, N. Y. The dam is of the earth-filled type, 1,200
feet long at the top of the embankment and rising, 113 feet above
the streambed, with a concrete spillway and outlet conduit in the
right abutment. The reservoir has a storage capacity of 7,900
acre-feet. The Federal cost of new work, completed in 1952, was
$1,910,000, of which $1,777,732 was for construction and $132,268
was for lands and damages.
   Almond Reservoir: This reservoir is located on Canacadea Creek
near Hornell, N. Y. The dam is of the earth-filled type, 1,260 feet
long at the top of the embankment and rising 90 feet above the bed
of the stream, with a concrete spillway and outlet conduit in the
left abutment. The reservoir provides a storage capacity of 14,800
acre-feet. The estimated Federal cost of new work, revised in
1954, is $5,551,000, of which $4,594,500 is for construction and
$956,500 is for lands and damages.
    Oxford, N. Y.: The plan of improvement provides for the con-
struction of earth levees and the clearing of the Chenango River
channel, consisting of the following features: About 2,100 feet of
earth levee on the left bank of the Chenango River, extending
from high ground near Cemetery Drive and running mostly along
the railroad to high ground near Main Street; removal of the
dam and island below Main Street; raising of the Delaware, Lacka-
wanna & Western Railroad over the levee; and appurtenant
closure and drainage structures. The improvement provides pro-
tection for the village of Oxford on the left bank against a flood
discharge substantially larger than the maximum flood of record,
which occurred in July 1935. The Federal cost of new work, com-
pleted in 1952, was $131,000, of which $96,944 was for construction
and $34,056 was for lands. The estimated local cost of lands and
damages, revised in 1952, is $11,000.
    Lisle, N. Y.: The plan of improvement provides for channel re-
alinement and the construction of earth levees and concrete flood-
walls, consisting of the following features: Relocation of about
3,000 feet of the Dudley Creek channel, extending from 1,200 feet
west of the intersection of Cortland and Main Streets to the con-
fluence with Tioughnioga River, realinement of some 5,700 feet of
the Tioughnioga River channel east of the village; about 4,150
feet of earth levee and 970 feet of concrete wall on the right bank
of Dudley Creek and the Tioughnioga River, extending from
Main Street just above Collier Street to the railroad crossing on
River Street; raising of about 1,860 feet of the Delaware, Lacka-
222         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

wanna & Western single-track railroad over the levee; relocation
of about 1,600 feet of Cortland Street; a new bridge over the re-
located Dudley Creek; and appurtenant drainage structures. The
improvement provides protection for the village of Lisle against
flood discharges 20 percent greater on the Tioughnioga River and
about 100 percent greater on Dudley Creek than the correspond-
ing discharges of the maximum flood of record, which occurred in
July 1935. The Federal cost of new work, completed in 1954, was
$661,199, of which $605,000 was for construction and $56,199 was
for lands and damages.
   Whitney Point, N. Y.: The plan of improvement provides for
channel realinement and construction of earth levees, consisting
of the following features: Realinement of about 1,800 feet of the
Tioughnioga River channel, above the confluence with the Otselic
River; about 7,100 feet of earth levee along the right bank of the
Tioughnioga River, extending from high ground on Main Street
above the village to Collins Street just below the village; and ap-
purtenant drainage structures. The improvement, supplemented
by the Whitney Point Reservoir above the area, provides protec-
tion for the village of Whitney Point against a flood discharge
approximately 20 percent greater than the maximum flood of
record, which occurred in July 1935. The Federal cost of new
work, completed in 1952, was $424,096, of which $411,653 was for
construction and $12,443 was for lands and damages. The esti-
mated local costs of lands and damages, revised in 1952, is
$100,500.
   Binghamton, N. Y.: The plan of improvement provides for the
construction of earth levees, concrete floodwalls, and appurtenant
drainage structures, consisting of the following features: About
850 feet of channel excavation and about 1,375 feet of earth levee
along Phelps Creek, town of Port Dickinson; new concrete wall on
the right bank of the Chenango River, extending downstream
from high ground near the city limits to the existing floodwall
below DeForest Street, a distance of about 520 feet; about 150
feet of concrete wall just below Cutler Dam; about 180 feet of
concrete wall at the pumphouse near McDonald Avenue; raising
the existing earth levees on the right bank of the Chenango River,
extending from Cutler Dam downstream for a distance of about
1,220 feet; about 2,915 feet of earth levee on the left bank of the
Chenango River north of the city limits in the village of Port
Dickinson, extending from Church Street to high ground just
north of the city line; about 3,900 feet of earth levee on the left
bank of the Chenango River, extending from DeForest Street to
Cutler Dam; new concrete floodwalls and riverbank revetment
for a distance of about 5,570 feet extending on the left bank of
the Chenango River from Cutler Dam to the junction with the
Susquehanna River; about 540 feet of new concrete floodwall and
raising about 1,085 feet of concrete floodwall on the right bank
of the Susquehanna River, extending from the Delaware, Lacka-
wanna & Western Railroad downstream to the Tompkins Street
Bridge; about 1,940 feet of earth levee; about 1,940 feet of con-
crete floodwall; and capping about 125 feet of concrete floodwall,
on the right bank of the Susquehanna River from Stuyvesent
             FLOOD CONTROL--BALTIMORE, MD., DISTRICT           223
Street to the mouth of the Chenango River; about 8,380 feet of
earth levee; about 2,180 feet of new concrete floodwall and rais-
ing about 125 feet of existing floodwall on the left bank of the
Susquehanna River extending from Pierce Creek to high ground
at State Highway No. 17; a debris dam and flume between Corbett
and Hotchkiss Streets and a concrete pressure conduit, 1,060 feet
long, to carry the flow of Park Creek from Vestal Avenue to the
Susquehanna River; about 665 feet of levee extending from the
Erie Railroad to high ground along the right bank of Chamberlain
Creek near the mouth; closure structures at the Erie Railroad and
at Court Street; a weir, a drop structure, and about 1,800 feet
of earth levee, about 2,235 feet of channel excavation; about 645
feet of channel paving, and raising about 470 feet of existing
concrete floodwall and about 200 feet of new concrete floodwall for
the improvement of Pierce Creek from its mouth to about 1,000
feet above Conklin Avenue; and appurtenant drainage structures.
The improvement, supplemented by authorized flood control dams
above the area, will provide protection for the city of Binghamton
against a flood discharge approximately 20 percent greater than
the maximum flood of record, which occurred in July 1935 on the
Chenango River and in March 1936 on the Susquehanna River.
The Federal cost of new work, completed in 1953, was $2,952,000,
of which $2,844,682 was for construction and $107,318 was for
lands and damages. The estimated local cost of lands and dam-
ages, revised in 1951, is $720,000. Local interests have contrib-
uted an additional amount of $163,095.63 for the construction of
improvements not included in the authorized project.
   Elmira, N. Y.: The plan of improvement provides for the con-
struction of earth levees, concrete floodwalls, a concrete conduit,
and a pumping station, and consists of the following features:
About 17,700 feet of earth levee, and about 4,100 feet of concrete
floodwall on the right bank of Chemung River, extending from
South Hoffman Street to a point below the city near the upper
end of Big Island; about 12,100 feet of earth levee and about 6,300
feet of concrete wall on the left bank of the Chemung River ex-
tending from Durland Avenue to the Delaware, Lackawanna &
Western Railroad at the mouth of Newtown Creek; about
10,000 feet of earth levee on the right bank of Newtown Creek,
extending from about the intersection of the Delaware, Lacka-
wanna & Western Railroad and East Church Street to high ground
near the intersection of Sullivan and Warren Streets; about 4,300
feet of earth levee on the right bank of Diven Creek; about 2,000
feet of concrete conduit enclosing Hoffman Brook from West
Second Street to the Chemung River; clearing islands and river
banks of trees and brush for a distance of about 31/2 miles in the
Chemung River; about 14,300 feet of earth levee on the left bank
of Seely Creek, extending from the Erie Railroad to the high
ground approximately 1,000 feet northwest of the intersection of
South Broadway and Pennsylvania Avenue; a pumping plant for
the disposal of interior drainage; an interceptor sewer about 6,000
feet long, varying in size from 48 to 96 inches in diameter; and
appurtenant structures. The improvement provides protection
for the city of Elmira against a Chemung River discharge ap-


     Sig 8-223-254
224       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

proximately equal to that of the maximum flood of record, which
occurred in May 1946. The estimated Federal cost of new work,
revised in 1954, is $6,755,300, of which $6,596,300 is for construc-
tion and $159,000 is for lands and damages. The estimated local
cost of lands and damages, revised in 1951, is $981,000.
    Corning, N. Y.: Flood protection for this community was origi-
nally authorized by the Flood Control Act of 1936. The plan of
improvement provides for the construction of a pumping station,
earth levees, and concrete floodwalls, consisting of the following
features: About 4,300 feet of earth levee, enlargement of about
8,610 feet of existing earth levee, and about 3,100 feet of concrete
floodwall on the right bank of Chemung River, extending from
the Erie Railroad bridge to high ground at Park Avenue below
the city; about 200 feet of concrete floodwalls; about 2,500 feet
of earth levees, and enlargement of about 11,500 feet of existing
earth levee on the left bank of the Chemung and Cohocton Rivers,
extending from the Erie Railroad bridge over the Cohocton River
to the mouth of Post Creek; about 2,500 feet of earth levee
and enlargement of about 4,700 feet of existing earth levee on
the right bank of Post Creek from its mouth to Watkins Street;
realinement of about 3,000 feet of channel, about 8,800 feet of
earth levee, about 3,000 feet of channel excavation, a pressure
conduit about 400 feet long, a drop structure and a weir for the
improvement of Cutler Creek, extending from its mouth to high
ground at Deckertown Road and Hornby Road; and appurtenant
drainage structures. Flood protection on Monkey Run was au-
thorized by the Flood Control Act of 1950. The plan of improve-
ment provides for the construction of 2,010 feet of open flume,
2,320 feet of pressure conduit, storm sewers and appurtenant fa-
cilities between the existing improved channel above Sixth Street
and the Chemung River at a point immediately east of Pine Street
East. The modified improvement will provide protection for the city
of Corning against a flood discharge in the Chemung River approxi-
mately equal to the maximum flood of record, which occurred in
May 1946, and on tributary streams against floods of greater
magnitude than known to date. The estimated Federal cost of new
work, revised in 1954, is $3,520,000, of which $3,362,317 is for
construction and $157,683 is for lands and damages. The esti-
mated local cost, revised in 1953, is $967,000, of which $717,900 is
for lands and damages and $250,000 is for construction of a portion
of the protection on Monkey Run.
    Painted Post, N. Y.: The plan of improvement provides for chan-
nel realinement and the construction of earth levees and concrete
floodwalls, consisting of the following features: Realinement of
about 6,000 feet of the Cohocton River Channel, extending from
about one-half mile above State Highway Route No. 17 to the
Chemung River; construction of about 2,500 feet of earth levee
and raising of about 1,200 feet of existing floodwall along the left
bank of the Cohocton River, extending from the mouth of Hodg-
man Creek to the Chemung River; about 2,900 feet of earth levee,
and about 2,100 feet of concrete floodwall, extending on the left
bank of Hodgman Creek, from its mouth to high ground above
State Highway No. 2; and appurtenant drainage structures.       The
            FLOOD CONTROL-BALTIMORE, MD., DISTRICT               225
improvement provides protection for the village of Painted Post
against a flood discharge approximately equal to the maximum
flood of record, which occurred in May 1946. The Federal cost
of new work, completed in 1952, was $414,181, of which $402,948
was for construction and $11,233 was for lands and damages. The
estimated local cost of lands and damages, revised in 1951, is
$55,000.
    Addison, N. Y.: The plan of improvement provides for the con-
struction of earth levees and concrete floodwalls, consisting of the
following features: Construction of about 3,100 feet of earth levee
and about 700 feet of concrete floodwall on the right bank of the
Canisteo River, extending from high ground on Steuben Street
near the Baltimore & Ohio Railroad to the mouth of Tuscarora
Creek; removal of existing dam, mill, and raceway, from the
channel; construction of about 2,200 feet of earth levee on the
left bank of Tuscarora Creek, extending from Tuscarora Street
to the Canisteo River; construction of 4,600 feet of earth levee
on the right bank of Tuscarora Creek, extending from high ground
at the southwest edge of the village to high ground at the south-
east edge of the village; and appurtenant drainage structures.
The improvement, supplemented by the Arkport and Almond
Reservoirs above the area, provides protection for the village of
Addison against a flood discharge on the Canisteo River approxi-
mately 28 percent greater than the maximum flood of record,
which occurred in July 1935. Protection is provided on Tuscarora
Creek against a flobd discharge approximately equal to the maxi-
mum flood of record, which occurred in May 1946. The Federal
cost of new work, completed in 1952, was $827,050, of which
$814,236 was for construction and $12,814 was for lands and
damages. The estimated local cost of lands and damages, revised
in 1951, is $125,500.
    Bath, N. Y.: The plan of improvement provides for the construc-
tion of earth levees and concrete floodwalls along the Cohocton
River, consisting of the following features: Construction of about
10,400 feet of earth levee and about 1,250 feet of concrete flood-
wall, extending from above Cameron Street to below the turnout
of the Bath & Hammondsport Railroad; including about 600 feet
of cutoff levee between the Delaware, Lackawanna & Western
Railroad and U. S. Highway No. 15; three stop-log structures
across railroad tracks; a sandbag opening at Cameron Street; and
a sill across the Delaware, Lackawanna & Western Railroad tracks
below Cameron Street; and appurtenant drainage structures. The
improvement provides protection for the village of Bath against
a flood discharge approximately equal to the maximum flood of
record, which occurred in July 1935. The Federal cost of new
work, completed in 1952, was $638,331 for construction. The
estimated local cost of lands and damages, revised in 1951, is
$56,700.
    Avoca, N. Y.: The plan of improvement provides for the con-
struction of earth levees, channel improvement, and channel re-
alinement, consisting of the following features: Improvement and
realinement of about 8,300 feet of the Cohocton River channel, ex-
tending from above the Erie Railroad to below the junction of
226      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Main Street and U. S. Highway No. 15; construction of about
8,500 feet of earth levee on the left bank of the Cohocton River,
extending from high ground above Alexander Avenue to about
1,300 feet below the junction of Main Street and U. S. Highway
No. 15; about 4,500 feet of earth levee on the right bank of Salmon
Creek, extending from high ground above Alexander Avenue to the
Erie Railroad; a new highway bridge for U. S. Highway No. 15
over the Cohocton River; raising of the Erie Railroad bridge 4
feet; and appurtenant drainage structures. The improvement
provides protection for the village of Avoca against a flood dis-
charge approximately double the maximum flood of record, which
occurred in July 1935. The Federal cost of new work, completed
in 1952, was $436,374, of which $406,589 was for construction and
$29,785 was for lands and damages. The estimated local cost of
lands and damages, revised in 1953, is $69,300.
   Canisteo, N. Y.: The plan of improvement provides for the con-
struction of earth levees, consisting of the following features:
About 8,000 feet of earth levees on the right bank of the Canisteo
River, extending from high ground 1,570 feet west of State High-
way Route No. 21 above the village to a point at the intersection
of Ordway Lane and East Main Street; about 7,400 feet of earth
levee on the left bank of Purdy and Bennett Creeks, extending
from Main Street Bridge to high ground above Greenwood Street;
1,000 feet of earth levee on the right bank of Bennett Creek, ex-
tending upstream from Main Street Bridge; a concrete check
dam with wing levees from Greenwood Street; a new highway
bridge at Greenwood Street; alterations to existing timber check
dams in IBennett Creek; channel excavation in Bennett and Purdy
Creeks; and appurtenant drainage structures. The improvement,
supplemented by the Arkport and Almond Reservoirs above the
village, provides protection for the village of Canisteo against a
flood discharge approximately 30 percent greater on the Canisteo
River than the maximum flood of record, and on Bennett and
Purdy Creeks the channel capacity will be approximately equal
to the discharge of the maximum flood of record, which occurred
in July 1935. The estimated Federal cost of new work, revised in
1954, is $976,000, of which $917,000 is for construction and
$59,000 is for lands and damages. The estimated local cost of
lands and damages, revised in 1951, is $72,000.
   Hornell, N. Y.: The plan of improvement provides for channel
realinement and the construction of earth levees, concrete flood-
walls, and check dams consisting of the following features: Re-
alinement of about 4,600 feet of Canisteo River channel, and about
5,800 feet of earth levee on its right bank, extending from Seneca
Street upstream to the junction of the Pittsburg, Shawmut &
Northern Railroad and the Erie Railroad; construction of about
4,500 feet of earth levee, extending on both sides of Seneca Street
           FLOOD CONTROL--BALTIMORE, MD., DISTRICT             227
from the Canisteo River to Wrightman Avenue and the junction of
Cleveland Avenue and Bethesda Drive; construction of about
7,200 feet of earth levee, about 2,500 feet of concrete floodwall,
and raising of about 1,500 feet of existing concrete floodwall, on
the right bank of the Canisteo River, and about 12,000 feet of chan-
nel improvement, extending from Seneca Street to the Erie Rail-
road; construction of about 2,500 feet of earth levee, about 2,100
feet of concrete floodwall on the left bank of the Canisteo River,
extending from a point opposite Walnut Street to the Erie Rail-
road; a ring-earth levee about 2,800 feet long around the sewage-
disposal plant on the left bank of the Canisteo River; about 4,500
feet of realinement and improvement of the Canisteo River chan-
nel, with about 4,500 feet of earth levee on its right bank, extend-
ing from Cedar Street downstream to about 1,400 feet above East
Avenue; about 2,400 feet of channel paving, 1,400 feet of earth
levee, raising of about 1,900 feet of concrete floodwall, and con-
struction of one check dam on Canacadea Creek; about 1,600 feet
of channel paving and construction of three check dams on Chaun-
cey Run with about 300 feet of new wall and about 300 feet of cap-
ping; a weir, a check dam, 3,030 feet of channel paving, 4,800 feet
of flood walls and levees, and related work on existing walls, all
on Crosby Creek; removal of 6 bridges, erection of 4 bridges,
miscellaneous bridge structures, and 3 drop structures; and ap-
purtenant drainage structures and small stream control works.
   The improvement, supplemented by the Arkport and Almond
Reservoirs above the area, provides protection for the city of
Hornell against a flood discharge approximately double the maxi-
mum flood of record, which occurred in July 1935. The estimated
Federal cost of new work, revised in 1954, is $4,238,000, of which
$3,643,000 is for construction and $595,000 is for lands and dam-
ages. Local interest raised or reconstructed three bridges over
the improvement and contributed $15,000 towards reconstruction
of a fourth bridge.
   Almond, N. Y.: The plan of improvement provides for chan-
nel realinement and the construction of earth levees, consisting of
the following features: About 4,750 feet of earth levee on the left
bank of Canacadea Creek and McHenry Valley Creek, extending
from high ground above the village to high ground below the vil-
lage; realinement of about 3,200 feet of channel on Canacadea
Creek, extending downstream from Angelica Street; and appurte-
nant drainage structures. The improvement will provide protec-
tion for the village of Almond against a flood discharge approxi-
mately equal to the maximum flood of record, which occurred in
July 1935. The estimated Federal cost of new work, revised in
1954, is $385,000, of which $379,000 is for construction and $6,000
is for lands and damages. The estimated local cost of lands and
damages, revised in 1949, is $24,000.
                                                                             Dams and reservoirs1

                                                                                                                                              Estimated Federal cost
                                                                                                    Distance   Height   Reservoir
               Name                                 Nearest city                           River     above       in     capacity
                                                                                                     mouth      feet    acre-feet          Con-       Lands and        Total
                                                                                                     miles                              struction      damages 4
                                     I                                   I
Davenport Center_                        Oneonta_                            Charlotte Creek__             5      100      52, 500     $8, 202, 000   $3, 498, 000   $11, 700, 000    d

West Oneonta ...                             do                              Otego Creek_                  2       86      34, 500      9, 084, 000    2, 816, 000    11, 900, 000o
East Sidney 2_ _ _                       Sidriey_                            Ouleout Creek_                4      146      33, 494      5, 269, 000       620, 000     5, 889, 000
Copes Corner_                                do ......                       Butternut Creek_              3       75      37, 900     11, 443, 000    2, 657, 000    14, 100, 000
Whitney Point                            Binghamton                          Otselic River___              1       95      86,440       3, 978, 533    1, 096, 467     5, 075, 000    O
Arkport -      -                         Hornell_                            Canisteo River__             50      113       7, 900      1, 777, 732       132, 268     1, 910, 000        -
Almond 2                                    do_                              Canacadea Creek_              3       90      14, 800      4, 594, 500       956, 500     5, 551, 000
      Total_______                                                                                                                   _'$44, 348, 765 $11, 776, 235   $56,125, 000

1 All dams are located in New York State; all are of earth fill type except East Sidney.
2 Reservoir in operation.
s Project completed.
4 Includes relocations.

                                                                                                                                                                                      z




                                                                                                                                                                                      50
                                                                                                                                                                                      20
                                                                             Local flood-protection works

                                                                                                                                                                    Estimated Federal cost
                                                                           Distance
     Location, New York                            River                   above
                                                                           mouth                             Type of structure                                             Lands and        Total
                                                                           miles                                                                          Construction      damages
      3
Oxford                            Chenango___                          _      40      Levee and channel improvement _-                                             $96, 944    $34, 056      $131, 000
Lisle'_____________   __          Tioughnioga_                                12      Wall, levee, and channel realinement-------                                  661, 801     56, 199       718, 000    0
Whitney Point                     Tioughnioga_                                10      Levee and channel realinement...        ...        ..--------------------- 411, 653       12, 443       424, 096    O
Binghamton3                       Susquehanna.                               328      Wall, levee, and conduit   ------------------------------
                                                                                                                               _                              '42, 844, 682    107, 318   42, 952, 000    O
Elmira' 2                         Chemung_                                    27      Wall, levee, and conduit...-                          -                  6, 596, 300     159, 000    6, 755, 300
Corning                           Chemung_                                    44      Wall, levee, flume and conduit___ _______________-_--_.                  53, 362, 317    157, 683   53, 520, 000    0
             3
Painted Post                      Cohocton__                                   0      Wall, levee and channel realinement-   __402,                                     948     11, 233       414, 181
Addison                           Canisteo_                                    8      Wall, levee and channel realinement_              -814,                           236     12, 814       827, 050
                                                                                                                                                                                                          z
Bath-      -                      Cohocton .............                      21      Wall and levee__                                                             638, 331--------     -     638, 331
Avoca3 _                          Cohocton                                    30      Levee, channel improvement & relinement .            .'                   406, 589        29, 785       436, 374
Canisteo_______________________   Canisteo__________                          36      Levee and wall___         ______                                          917, 000        59, 000        976, 000   H
Hornell_____________________
         7_                       Canisteo_                                   42      Wall, levee and channel realinement ___-__     ____-3,                    643, 000       595, 000     4, 238, 000   0
Almond                            Canacadea Creek                              6      Levee and channel realinement---------------------------                  379, 000         6,000         385, 000

      Total                                                                                                                                                 $21,174, 801   $1, 240, 531   $22, 415, 332
                                                           ---------

  1Project  in operation.                                                                                                                                                                                  H



  2 Part of project completed.                                                                                                                                                                            0
  ' Project complete.                                                                                                                                                                                     O
  4 Does not include contributed funds of $160,095.63 by the City of Binghamton and $3,000
by the village of Port Dickinson.
  5 Does not include $250, 000 of construction by State of New York and $40, 000 contrib-
uted funds by the City of Corning on Monkey Run.
  6 Does not include contributed funds of $15,000 by the City of Hornell.
  7 Local cooperation withdrawn, project authorization expired May 26, 1953.
                                                                                                                                                                                                          Os

                                                                                                                                                                                                          y



                                                                                                                                                                                                          H
                                                                                                                                                                                                          H
                                                                                                                                                                                                          H
230      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Local cooperation. Fully complied with, except as described in
the following paragraphs:
   Local cooperation for Almond, N. Y., has been withdrawn. Sec-
tion 2 of the Flood Control Act approved August 18, 1941, is effec-
tive, and authorization for the Almond, N. Y., project expired May
26, 1953.
   The Flood Control Act of 1950, which modifies the plan of im-
provement for Corning, N. Y., to include flood protection on Mon-
key Run, specifies, in addition to the general requirements, that
local interests shall (1) restore city streets and pavements over
the flume and conduit, including bridge slabs and superstructures
where highways cross the flume; (2) contribute $250,000 in cash
or an equivalent amount of construction or reconstruction work;
 (3) provide, operate, and maintain without cost to the United
States adequate pumping capacity for disposal of storm waters
draining through the property of the Corning Glass Works and not
intercepted by the Monkey Run improvement; and (4) protect
Monkey Run from any future encroachment or obstruction includ-
ing waste disposal that would reduce its flood-carrying capacity.
Formal assurances of cooperation by local interests have been
furnished and accepted, as follows: Local interests will construct
a portion of conduit of sufficient length to equal a cash contribu-
tion of $250,000.
   Operations and results during fiscal year. Davenport Center
Reservoir, N. Y.: Preliminary plans were revised to conform
with present criteria, by hired labor. The total costs, all for
new work, were $7,476.
   West Oneonta Reservoir, N. Y.: None.
   East Sidney Reservoir, N. Y.: Reimbursement to the State of
New York for the cost of lands acquired for the project was
continued, by hired labor, and installation of gate heaters was
completed, by contract. Normal operation and maintenance of
the project was continued, by hired labor. The total costs were
$19,176, of which $1,458 was for new work and $17,718 was for
maintenance.
   Copes Corner Reservoir, N. Y.: None.
   Whitney Point Reservoir, N. Y.: Normal operation and main-
tenance was continued, by hired labor. The total costs, all for
maintenance, were $15,637.
   Arkport Reservoir, N. Y.: Normal operation and maintenance
of the project was continued, by hired labor. The total costs,
all for maintenance, were $9,788.
   Almond Reservoir, N. Y.: Installation of the gate heaters and
reimbursement to the State of New York for the cost of lands
acquired for the project was completed by hired labor. Normal
operation and maintenance of the project was continued, by
hired labor. The total costs were $18,062, of which $5,264 was
for new work and $12,798 was for maintenance.
   Oxford, N. Y.: Normal operation and maintenance of the proj-
ect was continued, by hired labor. The total costs, all for main-
tenance, were $50.
   Lisle, N. Y.: Reimbursement to the State of New York for the
            FLOOD CONTROL-BALTIMORE, MD., DISTRICT             231
cost of lands acquired for the project was completed, by hired
labor. Normal operation and maintenance was continued, by
hired labor. The total costs were $2,941, of which $169 was for
new work and $2,772 was for maintenance.
   Whitney Point (Village), N. Y.: Normal operation and main-
tenance of the project was continued, by hired labor. The total
costs, all for maintenance, were $1,966.
   Binghamton, N. Y.: Normal operation and maintenance of the
project was continued, by hired labor. The total costs, all for
maintenance, were $3,770.
   Elmira, N. Y.: Reimbursement to the State of New York for
the costs of lands acquired for the project was continued, by
hired labor. Normal operation and maintenance of the project
was continued, by hired labor. The total costs were $7,430, of
which $4,830 was for new work and $2,600 was for maintenance.
   Corning, N. Y. (original project) : Normal operation and main-
tenance of the project was continued, by hired labor. The total
costs, all for maintenance, were $6,666.
   Corning, N. Y. (Monkey Run): Construction of a portion of
the conduit by the State of New York in fulfillment of the terms
of local cooperation commenced in September 1953 and was com-
pleted in April 1954. Construction of Monkey Run conduit, by
contract, commenced October 6, 1953 and was in progress at the
close of the fiscal year. The major items of construction in-
cluded removal of 798 cubic yards of concrete and masonry
structures, excavating 16,295 cubic yards of common material,
excavating 905 cubic yards of trench material, placing 8,920
cubic yards of backfill, placing 3,450 cubic yards of concrete,
erecting 19,570 square feet of conduit sheeting and shoring,
placing 512,570 pounds of steel reinforcement, and laying 1,550
square yards of gravel surfacing. Construction of the flume,
by contract, commenced April 6, 1954, and was in progress at
the close of the fiscal year. The major items of construction
included clearing of 50 percent of the site, excavating 1,300 cubic
yards of common material, pouring 676 cubic yards of concrete
for the intake, and placing 85,450 pounds of steel reinforcement.
The total costs, all for new work, were $551,235.
   Painted Post, N. Y.: Normal operation and maintenance of the
project was continued, by hired labor. The total costs, all for
maintenance, were $2,055.
   Addison, N. Y.: Normal operation and maintenance of the
project was continued, by hired labor. The total costs, all for
maintenance, were $989.
   Avoca, N. Y.: Normal operation and maintenance of the proj-
ect was continued, by hired labor. The total costs, all for main-
tenance, were $11,605.
   Canisteo, N. Y.: Reimbursement to the State of New York for
the cost of lands acquired for the project was continued, by hired
labor. The total costs were $10,550, of which $4,696 was for new
work and $5,854 was for maintenance.
   Hornell, N. Y.: Reimbursement to the State of New York for
cost of lands acquired for the project was continued, by hired
labor. Construction of levee closure across the abandoned Pitts-
232      REPORT Ofr CHIEF OF ENGINEERS, U. S. ARMY, 1954

burgh, Shawmut & Northern Railway Company tracks was com-
pleted; by hired ;labor. Normal operation and maintenance, of
the project was continued, by hired labor. The total costs were
$27,704, of which $19,649 was for new work and $8,055 was for
maintenance.
   Operations and results during the fiscal year. There were no
flood producing storms of consequence in the areas protected by
the Southern New York Flood Control project. The reservoir
gates at East Sidney Dam were operated during a minor flood
and ice jam on February 17th to 19th, 1954 and were effective
in reducing river stages at downstream centers.
   Federal maintenance responsibilities were carried out as re-
quired. Local interests, when required, carried out maintenance
responsibilities in accordance with flood control regulations pre-
scribed by the Secretary of the Army, and explanatory instruc-
tions contained in the respective operation and maintenance
manuals.
   The total costs were $697,100, of which $594,777 was for new
work, and $102,323 was for maintenance.
   Condition at end of fiscal year. The project is approximately
52 percent complete, exclusive of the Stillwater, Genegantslet,
and South Plymouth Reservoirs. The latter two reservoirs in
the State of New York and the Stillwater Reservoir in the State
of Pennsylvania, were authorized by the 1944 Flood Control Act
to supplement the comprehensive flood control program for South-
ern New York and Eastern Pennsylvania, and are reported sepa-
rately. The cost of new work and maintenance to June 30, 1954,
and the percentage of construction of new work completed for
each project unit are as follows:
                    FLOOD CONTROL---BALTIMORE,                    MD., DISTRICT                           233
                                                                    Cost to June 30, 1954         Percentage of
                                                                                                  construction
                              Unit                                                                 completed
                                                                 New work          Maintenance

Reservoirs:
    Davenport Center'-                                                   400
                                                                     $286,
    West Oneonta'...                                                   189,100
    E ast Sidney' _---_------- ---- --- ---- -------                5, 810, 698         79, 558     100   (1950)
    Copes Corner' -7_                                                  160, 700
    Whitney7 _Point __                                              5, 075, 000        205, 464     100   (1942)
    Arkport6 -                                                      1, 910, 000         74, 112     100   (1939)
    Almond _. -                                                     5, 547, 792         64, 890     100   (1949)
Local flood7 protection:
         7 _ _ __ _._._
    Oxford              __ . .. . . . . .. . . . . .. . . . .         131, 000           2, 085     100    (1938)
    Lisle _.....                7
                                                                      661, 199           8, 095     100    (1948)
   Whitney Point    2   Village                                       424, 096           7,669      100    (1948)
   Binghamton
           6  _       7                                            2, 952, 000          37, 151     100    (1943)
    Elmira'.  3    -     -     -   -     -    -                    6, 724, 210           4, 211     100   (1950)
    Cornings -       7_                                            2, 814,173           39, 368      80
   Painted 7Post _                                                    414, 181           7,105      100   (1938)
   Addison
         7      - -                                                   827, 050           5,390      100   (1947)
   Bath 7- -                                                          638,332                       100   (1948)
   Avoca                                                              436, 374          21, 032     100   (1939)
   Canisteo  4                                                        973,913           29,200      100   (1948)
   Hornell 6 s                                                     4,195, 684          100, 681     100   (1941)
   Almond Village'                                                     24,622 .

      T otal. . . .-- -- - - - - -         . . . . __ .         40, 196, 524(10)       686, 011


  1Cost for preliminary   work only.
  2 Does not include $163,096 contributed funds.
    8 Includes Monkey Run. Excludes $250,000 of construction by the State of New York and $40,000 con-
tributed funds by the City of Corning.
    4Includes Canacadea Creek, Chauncey Run, and Crosby Creek.
    5 Local cooperation withdrawn, project authorization expired May 26, 1953.
    6 Operationally complete.
      Financially complete.
    8 Does not include $15,000 contributed funds.
    9Year operationally completed indicated in parenthesis.
   '0 Does not include $178,096 contributed funds.


   The remaining work necessary to complete the existing project
is as follows: Reimburse the State of New York for the cost of
land acquired for East Sidney Reservoir and for the channel im-
provement portions of Elmira, Canisteo and Hornell local pro-
tection units; reimburse the State of New York for the cost of
relocating telephone lines on the Hoffman Brook portion of the
Elmira unit; and on Chauncey Run at Hornell; complete engi-
neering studies, design and preparation of plans and construct
the remaining project units comprising Davenport Center, West
Oneonta, and Copes Corner Reservoirs; complete construction of
flood protection on the Monkey Run modification of the Corning
unit; and prepare contract plans and specifications and install
gates on outlets at Lisle and on the original Corning unit.
   The total costs were $40,882,535, of which $39,461,252 (regular
funds) and $735,272 (Emergency Relief funds) were for new
work and $686,011 was for maintenance. In addition $178,096
was costed from contributed funds.
234                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                  Cost and financial summary
                                                     UNITED STATES FUNDS

                                                           Fiscal year ending June 30                      Total to June
                                                                                                          30, 1954, includ-
                                                                                                          ing fiscal years
                                          1950            1951         1952        1953        1954         prior to 1950
New work:
   Appropriated-........             $2, 095,000         $556, 000     $17, 033   $484, 400   $171, 499      1 $40,632, 354
    Cost.---------------               1, 957, 045        871, 115   1,134, 154    174, 257    594, 777       140,196, 524
Maintenance:
    Appropriated-........                  67, 500         66, 900      85, 432     82, 955    112, 500            703, 987
    Cost-----------------                  78, 186         77, 880      79, 598     84, 341    102, 323            686, 011

  1 Includes $735,272 Emergency Relief funds.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954......................                                            $63,785
    Appropriated for succeeding fiscal year ending June 30, 1955 .........                                                 364,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955-----......---...--....................---------..--------                                              427,785
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project---------...................------------------........................................ 37,544,000
                                                     CONTRIBUTED         FUNDS

                                                           Fiscal year ending June 30                      Total to June
                                                                                                          30, 1954, includ-
                                                                                                          ing fiscal years
                                         1950             1951         1952        1953        1954        prior to 1950
New work:
    Contributed--                   .-------------- $
    Cost......----------------------------............
                                                         $15, 000-            -               $40, 000
                                                                                   1,000............
                                                                                                                  $218, 096
                                                                                                                   178,096

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954........-..................... $40,000
    Unobligated balances available for succeeding fiscal year ending June 30,
                                                            ------------------- 40,000
                                                          ........--
      1955.......................................................

                       17. SWOYERSVILLE                          AND FORTY FORT, PA.
  Location. Swoyersville and Forty Fort, Pa., are situated on the
Susquehanna River in Luzerne County, Pa. (See U. S. Geologi-
cal Survey quadrangle sheet, "Pittston, Pa.")
    Existing project.                            The plan of improvement provides for the
construction of levees and related works along the north bank
of the Susquehanna River, along Abrahams Creek, and at Car-
penters Creek. The improvement will provide protection for
the communities of Swoyersville, Forty Fort, Wyoming, West
Wyoming,. Exeter, and part of West Pittston, against a flood dis-
charge equal to the maximum flood of record, which occurred
iri March 1936. The existing project was authorized by the
Flood Control Act approved June 22, 1936. (See H. Doc. 702,
77th Cong., 2d sess.)                             The estimated Federal cost for new work,
                           FLOOD CONTROL-BALTIMORE, MD., DISTRICT                                                      235
revised in 1954, is $4,160,000 for construction. The estimated
local cost of lands and damages, revised in 1952, is $166,800.
   Local cooperation. Formal assurances of cooperation by local
interests have been furnished and were approved on March 4, 1953.
   Operationsand results during fiscal year. Construction by con-
tinuing contract of the first unit of the project, along the right
bank of the Susquehanna River, commenced on July 9, 1953, and
was in progress at the close of this fiscal year. The major items
of work completed under the above contract included clearing
of the site, excavating 27,920 cubic yards of unclassified mate-
rial, excavating 213,850 cubic yards of borrow material, placing
130,960 cubic yards of levee embankment, and laying 4,054 linear
feet of corrugated metal pipe. Construction by continuing con-
tract of the second unit consisting of levee and diversion channel
for Abrahams Creek commenced on May 4, 1954, and was in
progress at the end of the fiscal year. Contract plans and speci-
fications for the third unit of the project were in progress. The
total costs, all for new work were $420,400.
   Condition at end of fiscal year. The first and second units of
construction are 40 percent and 2 percent complete, respectively.
Contract plans and specifications for the third unit of the project
will be completed early in 1955. The work remaining is com-
pletion of construction under the contracts for the first and
second units of the project; completion of contract plans, speci-
fications and construction of the uncompleted two units. The
total costs, all for new work, were $596,352.
                                        Cost and financial summary

                                              Fiscal    year   ending    June    30                     Total     to   June


                                                                                                       30, 1954, includ-
                                                                                                        ing fiscal years
                                 1950        1951              1952              1953        1954       priorto 1950
New work:
   Appropriated........          $48, 500    $50, 000      $-29,500             $896, 000   $400,
                                                                                                000               395, 000
                                                                                                                $1,
   Cost..-...-.-..--...-          45, 933      7, 182          11, 829            81, 008   420, 400               596, 352


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954............        115,242
    Appropriated for succeeding fiscal year ending June 30, 1955.......---.  400,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955......         ------------------------------------------ 515,242
      Estimated additional amount needed to be appropriated for com-
           pletion of existing project.........................       2,365,000
                                                  .....................................

                     18. WILLIAMSPORT,           SUSQUEHANNA RIVER, PA.
  Location. Williamsport, the county seat of Lycoming County,
Pa., is located on the left bank of the West Branch of the Sus-
236      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

quehanna River, 40 miles above its mouth. (See U. S. Geologi-
cal Survey quadrangle sheets, "Trout Run and Williamsport,
Pa.")
   Existing project. The plan of improvement provides for the
construction of a system of levees and concrete floodwalls and
appurtenant structures, consisting of the following features:
About 26,200 feet of earth levee and 3,060 feet of concrete flood-
wall along the left bank of the West Branch of the Susquehanna
River, extending from high ground near Sheridan Street, gener-
ally parallel to and on the right bank of Millers Run to the Sus-
quehanna River, thence extending upstream along the left bank
of the river and Lycoming Creek; about 29,900 feet of earth
levee and 860 feet of concrete floodwall along the left bank of
the West Branch of the Susquehanna River, extending from high
ground at Bottle Run generally parallel to and on the right bank
of Lycoming Creek to the Susquehanna River, thence extending
upstream along the left bank of the river to Carothers Lane,
thence to high ground along the Pennsylvania Railroad; about
11,400 feet of earth levee and 880 feet of concrete floodwall
along the right bank of the West Branch of the Susquehanna
River in South Williamsport, extending from high ground at
Central Avenue and Charles Street, along Charles Street to the
river, thence upstream along the river to high ground at May-
nard Street; a reinforced concrete pressure culvert about 1,390
feet long and a flume 470 feet long to provide for control of
Hagermans Run; 10 pumping stations for the disposal of inte-
rior drainage; and appurtenant closure and drainage structures.
The improvement will provide protection for the city of Wil-
liamsport and the borough of South Williamsport and part of
Old Lycoming Township against a flood discharge equal to the
maximum flood of record, which occurred in March 1936. The
existing project was authorized by the Flood Control Act ap-
proved June 22, 1936. The current estimated Federal cost of
new work, revised in 1954, is $13,500,000 for construction, which
does not include an estimated $117,061 of local contributions. The
estimated local cost of lands, damages, and utility relocations,
revised in 1952, is $1,717,800.
   Local cooperation. Local interests have furnished assurances
that all requirements will be complied with.
   Levee Unit No. 1: Construction by contract of the second phase
of seepage control system on the landside of the existing levee
on the left bank of the West Branch Susquehanna River com-
menced on February 3, 1953, and was completed on August 31,
1953. The major items of work included placing 2,027 cubic
yards of berm fill, and laying 319.7 linear feet of relief wells.
   Levee Unit No. 4: Construction by contract of levee unit 4A
was commenced on May 4, 1953, and was in progress at the close
of the fiscal year. The major items of work included, stripping
2,700 cubic yards of embankment foundation, excavation 10,940
cubic yards of common material, 59,000 cubic yards of channel
excavation, excavated 51,230 cubic yards of borrow material.
Construction by contract of Mill Race and Spring Run pumping
stations, and control manholes in levee unit 1, commenced
             FLOOD CONTROL--BALTIMORE, MD,, DISTRICT        !    237
on April 30, 1954, and was in progress at the close of the fiscal
year. The major items of work included, clearing of 50 percent
of the site, and excavating 150 cubic yards of unclassified mate-
rial. Construction by contract of levee unit 4B commenced on
March 24, 1954, and was in progress at the close of the fiscal
year. The major items of work included, stripping 4,900 cubic
yards of levee embankment foundation, excavating 16,500 cubic
yards of common material, 26,000 cubic yards of channel excava-
tion, excavating 56,000 cubic yards of borrow material, placing
24,500 cubic yards of miscellaneous fill, and placing 54,000 cubic
yards of levee embankment. Construction by contract of levee
unit 4C, commenced on June 16, 1954, and was in progress at
the close of the fiscal year.
   LeVee Unit No. 5: Construction by contract of levee units 5A
and 5B was continued and completed on October 1, 1953. The
major items of work accomplished during this fisal year were,
clearing 35 percent of the site, stripping 3,361 cubic yards of
material, excavating 108,852 cubic yards of unclassified and bor-
row material, and placing 84,313 cubic yards of levee embank-
ment.
    Construction of levee unit 5C by contract commenced on Feb-
ruary 25, 1953, and was in progress at the close of the fiscal year.
The major items of work accomplished during the fiscal year in-
cluded the excavation of 64,900 cubic yards of common material,
excavation of 147,000 cubic yards of borrow material, excavation
of 5,440 cubic yards of backfill, placing 180,100 cubic yards of
levee embankment, placing 13,000 cubic yards of miscellaneous
fill, placing of 6,210 cubic yards of riprap, and laying 1,900
square yards of gravel surfacing.
    Levee Unit No. 6: Raising of railroad tracks on Charles Street
by contract, commenced on November 9, 1953, and was completed
on December 15, 1953.
    The total costs, all for new work, were $1,110,599, of which
$1,081,556 was regular funds and $29,043 was contributed
funds.
    Condition at end of fiscal year. The entire project is 85 per-
cent complete. Responsibility for operation and maintenance of
the completed work on levee units 1, 2, and 3 was formally trans-
ferred to local interests on September 1, 1950, and levee unit 6
on August 30, 1952. The work remaining to be done is as follows:
    Levee Unit No. 3: Construction of control manholes with sluice
gates to supplement existing flap gates was approved on the two
conduits 24-inches in diameter and larger.
   Levee Unit No. 4: Complete construction of levee unit 4A, by
contract. Complete construction of Mill Race and Spring Run
pumping stations, and control manholes for levee unit 1, by con-
tract. Complete construction of levee unit 4B, by contract.
Complete construction of levee unit 4C, by contract.
   Levee Unit No. 5: Complete construction of levee unit 5C, by
contract.
   The total costs, all for new work, were $11,519,217, of which
$11,416,269 was regular funds, $101,061 was contributed funds,
and $1,887 was Emergency Relief funds.
238                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                Cost and financialsummary
                                                 UNITED STATES FUNDS


                                                         Fiscal year ending June 30                        Total to June
                                                                                                       30,1954, includ-
                                                                                                           ing fiscal years
                                         1950           1951        1952         1953         1954         priorto 19501

New work:
  Appropriated.-......                $1, 700, 000     $330, 000   $775,000   $1, 037, 500 $850,000            $12, 337,237
  Cost---------------..............    2, 172, 905      970, 644    49, 398       837, 242 1, 081, 66556        11, 418,156

  1Includes $1,887 Emergency Relief funds.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954............................         $156, 929
    Appropriated for succeeding fiscal year ending June 30, 1955.........-......               500, 000
    Unobligated balances available for succeeding fiscal year ending June 30,
                            ............................------------------------..--------
      1955 ..............------------.......                                                   656,929
                                                             ........................--..............
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project------                         ------------------------..--.  662, 800

                                                Cost and financial summary
                                                     CONTRIBUTED FUNDS

                                                         Fiscal year ending June 30                     Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                                         1950           1951        1952         1953        1954          priorto 1950

New work:
   Contributed---------  $39, 200   $-3, 140-----     -                         $32, 481      $3,043              $117, 061
   Cost----------   ------------------------------------                         29,681       29,043               101,061

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 .........................     $16, 000
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955....   .    ..      .. .....-----------------------------------------------.. 16,000

                                      19. YORK, CODORUS CREEK, PA.
   Location. York, Pa., is on Codorus Creek, 10 miles above its
confluence with the main Susquehanna River. Codorus Creek with
its tributary branches is located in York County in the south and
central parts of Pennsylvania. (See U. S. Geological Survey quad-
rangle sheets, "Pennsylvania--York and Hanover.")
   Existing project. The plan of improvement provides for the
construction of Indian Rock Dam, an earth and rock fill dam about
1,000 feet long at the top, rising 83 feet above the streambed, with
a reservoir providing for the controlled storage of 28,000 acre-feet
at the elevation of the spillway crest. The dam site is located on
the main branch of Codorus Creek about 3 miles above York. The
outlet works are located in the right abutment and the uncontrolled
spillway is located on the right bank, discharging upstream from
the. tunnel outlet. The reservoir will control the entire drainage
area of the main branch of Codorus Creek and 41 percent of the
drainage area above York. The plan also provides for improve-
ments to Codorus Creek channel in the vicinity of and through the
                      FLOOD CONTROL--BALTIMORE, MD., DISTRICT                                                  239
city of York for a distance of about 22,969 feet extending from
300 feet above Richland Avenue to a point downstream from the
Pennsylvania Railroad crossing known as Black Bridge. The im-
provements, which will increase the channel capacity to 24,000
cubic feet per second, include widening and deepening the chan-
nel, constructing bank protection, removing the York Roller Mill
Dam, and the construction of a low water channel approximately
3,900 feet in length in the vicinity of the York Roller Mill Dam.
The improvement will provide protection for the city of York
against a flood discharge approximately 33 percent greater than
the maximum flood of record, which occurred in August 1933.
   The existing project was authorized by the Flood Control Act
approved June 22, 1936, as amended by the Flood Control Act
approved June 28, 1938.
   The estimated Federal cost of new work, revised in 1954, is $5,-
090,000, of which $4,565,000 is for construction and $525,000 is for
lands and damages.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. Continued reim-
bursement to owners for title to land acquired for the channel por-
tion of the project; continued normal operation and maintenance
of the project, by hired labor. The total costs were $27,148, of
which $612 was for new work and $26,536 was for maintenance.
   Condition at end of fiscal year. Construction of the project was
completed in September 1952; however, the project was opera-
tionally complete in November 1947. The work remaining to be
done is complete reimbursement to property owners for lands
acquired for the channel portion of the project and prepare final
reports, by hired labor. The total costs were $5,251,672, of which
$5,036,006 (regular funds) and $11,588 (Emergency Relief funds)
were for new work and $204,078 was for maintenance.
                                         Cost and financial summary

                                               Fiscal year ending June 30                            Total to June
                                                                                                    30, 1954, includ-
                                  1950                                                              ing fiscal years
                                              1951            1952         1953        1954           prior to 1950
New work:
    Appropriated------------------            $90, 100 -.--          .   $---52, 000    $2, 000         1 $5, 049, 988
    Cost--.-------------         $126, 486     74, 871        $99, 452      14, 823           612       1 5,047, 594
Maintenance:
   Appropriated--------.......     20, 500     21,100         33, 568       20, 045     29, 000              207, 613
    Cost...-----------------       19, 518     21, 659        33, 424       19, 540     26, 536              204, 078

  1 Includes $11,588 Emergency Relief funds.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954.....$...  .......... $1,978
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955...................................................................   1,978
240            REPORT OF.CHIEF OF ENGINEERS, U. S. ARMY,: 1954

                    20. INACTIVE FLOOD CONTROL PROJECTS

                                                       For last            Cost to June 3l,-1954        Estimated
                                                      'full report                                        amount
                 Name of project                          :see                                           required
                                                        annual           Con-             Operation         to
                                                        report         struction             and .     .complete.314
                                                         for-                            maintenance
1. South. Plymouth Reservoir, Canasawacta
      Creek, N. Y.-------..--------        -              1953             2$100, 036              -      $7, 700, 000
2. Stillwater Reservoir, Lackawanna River, Pa.'          1953       : "      80, 000-     -_              8, 800, 000
 -3.Wllkes-Barre-Hanover Township,: Ssque-
      hanna River, Pa.     -1953                                        48,788, 957
4. Nanticoke, Pa:. - 7      ---    -                     1937
                                                          1937       _ __1,                                  700, 00Q
                                                                                                             953, 000
5. West Pittston, Pa. ___ .....
6. KingstonmEdwardsville; Susquehanna River,
      Pa.'                                                1953          94, 410, 969     ............ .       25, 000
7. Plymouth, Susquehanna River, Pa.........              1953         101, 866, 189
8. Sunbury, Susquehanna River, Pa.'       _              1953         "6, 062, 000                -           14, 000
9. Tyrone, Pa.'.__    __                                 1953           12135, 516                        8, 644, 00
                                        13
10. Federalsburg, Marshyhope Creek, Md. _____             1941               4, 061I                          515, 900


    1 Funds have not been appropriated for accomplishment of construction.
    2 Revoked during fiscal year $108.
    3 Estimate of Federal cost revised in 1954.
      Expended for general supervision during fiscal year $54. Includes $872,715 Emergency Relief funds. In
addition $36,375 Emergency Relief funds were expended prior to adoption of the project.
      Completed.
    6 No funds have been allotted and no work has been done on this project. In accordance with the provisions
of the 1941 Flood Control Act,, the 5-year limitation clause on assurances of local cooperation has been invoked.
The project authorization will expire Oct. 19, 1955.
    7 No funds have been allotted and no work has been done on this project. In accordance with the provisions
of the 1941 Flood Control Act, the 5-year limitation clause on assurances of local cooperation has been invoked.
The project authorization will expire Nov. 28, 1955.
   ' Project in operation.
      Expended for general supervision during fiscal year $772. Includes $1,162,548 Emergency Relief funds.
In addition $225,877 Emergency Relief funds were expended prior to adoption of the project..
  1oExpended for general supervision during fiscal year $157. Includes $4,357 Emergency Relief funds.
  11Expended for general supervision during fiscal year $1,603. In addition, $140,504 expended from con-
tributed funds.
  12Revoked during fiscal year $84.
  1s Awaiting local cooperation.
  14Estimated amounts required to complete were revised in 1954.


                              21. GENERAL INVESTIGATIONS
   Examinations and surveys. The cost of this work during the
fiscal year amounted to $13,310 of which $3,310 was for naviga-
tion studies, and $10,000 was for flood control studies.
   The balance unexpended June 30, 1954, $1,133 plus additional
funds in the amount of $31,354, a total of $32,487 will be applied
as follows:
      Navigation studies ........................       $22,487
      Flood control studies .......................      10,000

        Total ..................................                                   $32,487
  Collection and study of basic data.                             The cost of this work during
the fiscal year amounted to $1,854.                               The unexpended balance on
June 30, 1954 was $3,146.

                   22. INSPECTION OF COMPLETED PROJECTS
   Projects transferred to local interests for operation and main-
tenance were inspected as required by hired labor.
   Investigations of completed drainage structures to ascertain the
need for and cost to install emergency controls on outlets through
levees and floodwalls were made, by hired labor.
   The total costs during the year amounted to $20,500.
                  FLOOD CONTROL--BALTIMORE, MD., DISTRICT                                          241
                                Cost and financial summary

                                      Fiscal year ending June 30                          Total to June
                                                                                         30, 1954, includ-
                                                             1ing                             fiscal years
                         1950        1951         1952              1953      1954         prior to 1950

Maintenance:
   Appropriated                       $1, 540        $900              $800   $20, 500            $23, 740
   Cost                                   439       1, 726              930    14,422              17, 517



  23. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
   Snagging and clearing of navigable streams and tributariesin
the interests of flood control. (Sec. 13 of the 1946 Flood Control
Act).
   A study and review of the snagging and clearing project at
Newton Creek, Bainbridge, N. Y., was completed by hired labor.
The total costs, all for new work, were $2,380.
   Removal of debris and channel clearing on the Lackawanna
River and tributaries at Scranton, Pa., were completed in fiscal year
1943. Clearing and snagging operations on the Chenango River
at Port Dickinson, N. Y., and downstream from Cutler Dam at
Binghamton, N. Y., were completed in fiscal year 1950. Removal
of growth and obstructions on two islands and clearing of left
bank of the West Branch of the Susquehanna River in the vicinity
of Milton, Pa., was completed in fiscal year 1952. A study and
review of the project on Newton Creek, Bainbridge, N. Y., was
completed during fiscal year 1954. The work remaining to be done
is completion of the project on Newton Creek, Bainbridge, N. Y.
The total costs, all for new work, were $86,826.
                                Cost and financial summary

                                       Fiscal year ending June 30                         Total to June
                                                                                         30, 1954, includ-
                                                                                         ing fiscal years
                         1950        1951         1952              1953      1954         priorto 1950
New work:
   Appropriated          $50, 000    $20, 000   $-28, 233      $-12, 800 --- _-                   $86, 826
   Cost_ __________363     6,         35, 174      3, 622            163    $2, 380                86, 826



   Flood control emergencies-repair and flood fighting and rescue
work. (Sec. 210 of the 1950 Flood Control Act and supplemental
authorizations).
   Preliminary investigations, by hired labor, of outlets through
levees and floodwalls at Kingston-Edwardsville, Pa., was in prog-
ress at the close of fiscal year.
   Practice exercises for flood fighting and rescue work were held
at Sunbury, Pa. on April 25, 1954 with the assistance of interested
state and local agencies.
   Final reports and audits in connection with wall repairs at
Chauncey Run and Canacadea Creek, Hornell, N. Y. were continued
during the fiscal year by hired labor.
   Final reports for work accomplished on Lycoming Creek at Wil-
liamsport, Pa. were completed during the fiscal year by hired labor.
The total costs, all for maintenance, were $5,122.
   Emergency flood control repairs to Mile Post cutoff levee at Sun-
242           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

bury, Pa., resulting from the May 1946 flood were completed by
contract during the fiscal year 1947.
   Construction of river bank stabilization at Wilkes-Barre, Pa.,
was completed April 13, 1949, by contract.
   Emergency wall repairs along Chauncey Run and Canacadea
Creek, Hornell, N. Y. were completed by contract during fiscal year
1952.
   Emergency repairs to levee embankment along the right bank
of Lycoming Creek, at Williamsport, Pa., were completed during
fiscal year 1953, by contract.
   Practice exercises for flood fighting and rescue work were held
at Sunbury, Pa. on April 25, 1954, with the assistance of interested
state and local agencies.
   Emergency operations in connection with flood fighting have
been completed as required.
   The total costs, all for maintenance, were $314,346 of which
$269,261 was Federal funds and $45,085 was contributed funds.
                                     Cost and financial summary

                                           Fiscal year ending June 30                         Total to June
                                                                                             30, 1954, includ-
                                                                                             ing fiscal years
                              1950        1951         1952        1953           1954        priorto 1950

Maintenance:
   Appropriated........     -$41, 500    $115, 000     $1, 795    -$1,600       --$19, 500       1$318, 342
   Cost-----------------       13,483      22,254      64,599      13,377           5,122        1 314,346


1In   addition, $45,085 contributed funds was expended for maintenance work.
        IMPROVEMENT OF RIVERS AND HARBORS IN THE
                WASHINGTON, D. C., DISTRICT

   This district comprises a portion of south central Pennsylvania,
western Maryland, eastern West Virginia, and northern Virginia
embracing the western part of Chesapeake Bay and its tributaries
from Cove Point, Md., to a line due west through Wolf Trap Light
to the watershed line between the northerly arm of Winter Harbor
and Garden Creek, Va.
                                                             IMPROVEMENTS
                           Navigation                                                          Flood Control
                                                                 Page                                                               Page
1. Washington Harbor, D. C.........                              243     9. Anacostia River Basin, Flood
2. Potomac River, North Side of                                               Protection and Navigation
     Washington Channel, D. C.                                   246          Improvements, D. C. and
3. Potomac River and Tributaries                                              Md...........................................         259
     at and below Washington,                                           10. Cumberland, Md. and Ridge-
     D. C., Elimination of Water-                                             ley, W. Va..............................              260
     chestnuts----..------------..............................   248    11. Savage River Dam, Md.............                       263
4. Little Wicomico River, Va-..--...                             249    12. Salem Church Reservoir, Va.....                         264
5. Rappahannock River, Va.
6. Maintenance, Operation, and
                                                     ------..... 250    13. Inactive flood control projects..
                                                                        14. General investigations................
                                                                                                                                    266
                                                                                                                                    266
     Capital Outlay of the Wash-                                        15. Inspection of completed flood
     ington Aqueduct ....................                        252          control works .........----------................--   266
7. Inactive navigation projects......                            258
8. Inactive miscellaneous Civil
     Works projects------------........................          258

                                       1. WASHINGTON HARBOR, D. C.
   Location. Washington Harbor is located within the District of
Columbia at the junction of the Anacostia River with the Potomac
River which flows in a southeasterly direction 108 miles to the
Chesapeake Bay. It is southerly 202 miles by water from Balti-
more, Md., and northerly 195 miles from Norfolk, Va. (See U. S.
Coast and Geodetic Survey Chart No. 560.)
   Previous projects. The original project for the Potomac River
was adopted by the River and Harbor Acts of March 2, 1833, July
11, 1870, and August 2, 1882. For further details, see page 1791
of Annual Report for 1915, and page 295 of Annual Report for
1934. The River and Harbor Act of September 19, 1890, author-
ized an allotment for work on the Anacostia River; joint resolution
of Congress of April 11, 1898, made appropriation for a survey;
and a project was adopted by the River and Harbor Act of June
13, 1902 (H. Doc. 87, 55th Cong., 3d sess., and Annual Report for
1899, p. 1443). For further details see page 430 of the Annual
Report for 1932 and page 421 of Annual Report for 1938.
   Existing project. This project is a combination and extension
of the latest projects for the Potomac River at Washington, D. C.,
and the Anacostia River, D. C. The project provides for: (1) Vir-
ginia Channel, from Giesboro Point to Francis Scott Key Bridge,
24 feet deep and 400 feet wide, with the width increased as neces-
sary to afford a low water cross-section area of 25,000 square feet;
 (2) Washington Channel, from Hains Point to the head of Wash-
ington Channel, 24 feet deep and 400 feet wide; (3) Anacostia
                                                                                                                         243
244       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  River from Giesboro Point to Anacostia Bridge, 24 feet deep and
  400 feet wide, with turning basin 800 feet wide and approximately
2,400 feet long of same depth opposite the Naval Gun Factory;
  (4) Anacostia River from Anacostia Bridge, 24 feet deep and 200
feet wide to turning basin 400 feet square of same depth at foot
of Fifteenth Street SE. The channel lengths including turning
basins are: Virginia Channel, 25,000 feet; Washington Channel,
  10,000 feet: and Anacostia River, 15,000 feet; (5) operation and
maintenance of the inlet gates and lock and the outlet gates of the
Tidal Basin constructed under a previous project to flush the Wash-
ington Channel. The plane of reference is low water datum which
is 0.35 foot below mean low tide as observed from 1932 to 1942.
Tidal ranges are: Mean, 2.9 feet; irregular, 4.5 feet; and extreme,
10.7 feet.
    The estimate of cost to the Federal Government for new work,
revised in 1954, is $558,000, exclusive of amounts expended under
previous projects. The latest (1950) approved estimate for annual
cost of maintenance is $83,000.
    The existing project was adopted by the River and Harbor Act
of August 30, 1935 (Rivers and Harbors, Committee Doc. 22, 74th
Cong., 1st sess.). The latest published maps are in the project
document.
    Local cooperation. Not required.
    Terminal facilities. On the Virginia Channel (Georgetown
water front) there are 10 wharves generally of the bulkhead type,
of timber, stone, and concrete, privately owned. Railroad and
crane service are available at a number of the wharves. On the
Washington Channel there are 2 yacht basins with a total capacity
for 198 yachts, under jurisdiction of the District of Columbia and
12.wharves of open pile and bulkhead construction, all owned by
the Federal Government, but most of which are leased to private
parties or serve governmental agencies. On the Anacostia River
there are about 23/4 miles of commercial water front on which are
located 7 privately owned and 2 Government wharves, and 3,500
linear feet of bulkhead with slips for governmental agencies. In
addition, there are numerous small stagings and floats used by
yacht clubs for mooring small boats. Some of the wharves and
slips have transfer and rail facilities. The wharves of the Wash-
ington Harbor are only open to the public by special arrangement,
except for the District of Columbia fish wharves on the Wash-
ington Channel.
    Terminal facilities, except for those in the Washington Channel,
are considered adequate for existing commerce.
    Operations and results during fiscal year. The Tidal Basin
gates were repaired and operated by hired labor throughout the
year at a cost of $8,276.
   A hydrographic survey to determine channel conditions in the
          RIVERS AND HARBORS-WASHINGTON, D.C., DISTRICT                                       245
Virginia Channel from Hains Point to the Pennsylvania Railroad
bridge was made in September 1953. The work was accomplished
by hired labor and Government plant at a cost of $3,081.
  "-Maintenance dredging was performed by contract in the Vir-
ginia Channel from Hains Point to the Pennsylvania Railroad
bridge from April 15 to May 20, 1954. A total of 388,766 cubic
yards of material was dredged from the channel and deposited in
adjacent disposal area at a cost of $71,852.
   A hydrographic survey to determine channel conditions in the
Anacostia River from Hains Point to the Anacostia Bridge was
made in May 1954. The work was accomplished by hired labor
and Government plant at a cost of $1,615.
   The cost of miscellaneous inspections and reports chargeable to
the project was $7,755. The cost of supervision and administration
for the year was $1,865.
   Total costs for the year were $94,444, all for maintenance.
   Condition at end of, fiscal year. The existing:project was
started in April 1937 and was about 50 percent complete at the end
of the fiscal year. The channels and basins in the Anacostia River
are complete and those at the forks of the channel at Hains Point
are partially complete. Except for dredging between the limits of
2,000 feet above and 3,000 feet below the Memorial Bridge, no new
work has been done downstream of Key Bridge in Virginia Channel.
   The controlling depths in the channels throughout the harbor
were as follows:

                                                                Controlling
                         Name of channel                            depth
                                                                                      Date

Potomac River, Virginia Channel from Giesboro Point to Key     119. 2 feet    May 1954
  Bridge.
Washington Channel from Giesboro Point to Fourteenth           118.9 feet     February 1950
  Street Bridge.
Anacostia River from Giesboro Point to Anacostia Bridge ....   221. 5 feet    May 1954
Anacostia River from Anacostia Bridge to Fifteenth Street,     321.1 feet     October 1947
S. E.

1 For 200-foot width.
2 For 400-foot width.
E For 100-foot width.




The work remaining to be done to complete the project consists of:
   a. Removal of rock in Virginia Channel upstream of Memorial
Bridge.
   b. Dredging in Virginia Channel from Giesboro Point upstream
to a point 3,000 feet below Memorial Bridge.
   Total costs for the existing project were $988,422, of which
$162,006 was for new work and $826,416 was for maintenance.
This is exclusive of $4,000 for emergency dredging under provi-
sions of Section 3 of the River and Harbor Act of March 2, 1945.
246                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                   Cost and financial summary

                                                           Fiscal year ending June 30                  Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                                            1950         1951         1952        1953      1954        prior to 1960
New work:
   Appropriated. ----------------------------------------------------------      1$3,191,007
   Cost---------.......                              --------------------------  1 3, 191, 007
                          ..........---------.........-------......-----------.....
Maintenance:
   Appropriated........                    $204, 100   -- $24, 651    $12, 500    $25,900   $97, 200        a 2, 660, 782
   Cost----------------.................
                                 -          172, 327       10,134      12, 723     25,677    94, 444        ' 2, 658, 025

 'Includes $3,029,001 for new work and $1,831,609 for maintenance for previous projects.
sExclusive of $4,000 for emergency dredging under provision of section 3 of the River and HarborAct of
Match 2, 1945.
Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project................. ........................
                                                                             .. $396,1000
                                                                        ...........


               2. POTOMAC RIVER, NORTH SIDE OF WASHINGTON
                              CHANNEL, D. C.

   Location. The area covered by the project is the waterfront
channelward of Maine Avenue on the north side of Washington
Channel, extending upstream from Fort Leslie J. McNair (War
College) at Maine Avenue and P Street a distance of approximately
5,123 feet to the foot of Fourteenth Street SW., in the District of
Columbia. (See U. S. Coast and Geodetic Survey Chart No. 560.)
   Existing project. This provides for development of the com-
mercial waterfront of Washington Channel by construction of
(1) a yacht harbor in four sections on the upstream half of the
section, with berthing space for about 286 boats; (2) two wharves
for activities of the District of Columbia; (3) three wharves for
existing transportation lines and general service; (4) construction
of bulkhead walls; and (5) removal of the old and dilapidated
existing structures. The project further provides that during
the construction period the District Engineer be given jurisdiction
over the entire waterfront except the municipal fish wharf, and
that the completed work as well as the maintenance and adminis-
tration thereof should be under the Commissioners of the District
of Columbia.
   The estimate of cost to the Federal Government for new work,
revised in 1954, is $7,780,000, exclusive of $389,000 to be con-
tributed by the District of Columbia to cover the cost of two
wharves for District of Columbia activities. The latest (1950)
approved estimate for annual cost of administering unimproved
property owned under the project is $1,600.
   The existing project was, adopted by the River and Harbor Act
of August 30, 1935 (Rivers and Harbors Committee Doc. 13, 73d
Cong., 1st sess.).
   Detailed plans approved by the Chief of Engineers, September
       RIVERS AND HARBORS-WASHINGTON,       D.C., DISTRICT    247
24, 1945, provide for the following modifications in the items of
construction: (1) A yacht harbor in three sections on the up-
stream half of the waterfront with berthing space for about 356
boats; (2) one wharf for the combined use of the police and fire
departments of the District of Columbia; (3) three wharves for
existing transportation lines and general service; (4) construction
of bulkhead walls; and (5) removal of the old and dilapidated
existing structures.
   Local cooperation. Fully complied with.
   Terminal facilities. The entire waterfront is Government-
owned and facilities are leased to individuals or serve govern-
mental agencies. Two yacht basins to accommodate 198 yachts
and small boats together with a public sales and service pier, a
concrete pier 340 feet long and 100 feet wide for general com-
mercial use and a concrete pier 340 feet long and 75 feet wide for
use by excursion boats have been completed under the existing
project. Of the 12 commercial piers only 5 can be classed as
modern. The only wharves open to the public are those owned
by the District of Columbia at the municipal fish market where
daily rental rates are charged. The facilities are considered in-
adequate for existing commerce.
    Operations and results during fiscal year. Unimproved prop-
erties not required for construction were leased for private use at
a cost for the year of $1,938, chargeable to maintenance. Super-
vision and administration was $175.
    Total costs were $2,113, all United States funds.
    Condition at end of fiscal year. The existing project was
started in April 1938 and was approximately 24 percent complete
at the end of the fiscal year. Construction of Yacht Basins No. 1
and 2 was completed in November 1940 and the basins were leased
for commercial use and transferred to the District of Columbia
for operation and maintenance on December 3, 1940. Commercial
Pier No. 5 was completed in December 1941, and was transferred
to the District of Columbia for operation and maintenance on
March 21, 1942. The excursion pier (Pier 4) was completed in
March 1951 and was transferred to the District of Columbia for
operation and maintenance on April 25, 1951. Plans and specifica-
tions for Yacht Basin No. 3 were 75 percent complete, and for
Piers No. 2 and No. 3, were 7 percent complete. The work re-
maining to be done to complete the project consists of construc-
tion of two yacht basins; construction of two piers for activities
of the District of Columbia; construction of a pier for existing
transportation lines and general service; completion of bulkhead
walls; and completion of removal of existing structures.
    Total costs were $1,757,019, of which $1,744,692 was for new
work and $12,327 was for maintenance. In addition, $389,000
from contributed funds was expended for new work.
248           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                     Cost and financial summary

                                            Fiscal year ending June 30                        Total to June
                                                                                             30, 1954, includ-
                                                                                             ing fiscal years
                              1950        1951         1952        1953          1954        inprior to 1950

New work:
   Appropriated              $ 349, 700              -$3, 276        -$89     ____________        $1, 744, 692
   Cost_-- --------             50, 689   $302,087       2, 999                                  1 1.,744,692
Maintenance:
   Appropriated         _ ___________
                       ........             6, 727      1, 600       2, 000       $2, 000              12, 327
   Cost-      __ _       __.    ....        6,155       2,052        2,006         2,113               12, 327

  1In addition, $389,000 for new work was expended from Contributed Funds (see Annual Report for 1949).

Other new work data: Estimated additional amount needed to be appro-
                                                         _..._...__.....
  priated for completion of existing project_ ..... ____....             $6, 035, 000

       3. POTOMAC RIVER AND TRIBUTARIES AT AND BELOW
      WASHINGTON, D. C., ELIMINATION OF WATER CHESTNUT
   Location. The water chestnut, botanically known as Trapa
natans, is an annual fresh water plant infesting the navigable por-
tions of the Potomac River and its tributaries between Key Bridge
in the District of Columbia and Maryland Point, 48 miles down-
stream of Washington, D. C. Washington, D. C., is located 108
miles upstream of the mouth of the river. At the height of in-
festation in 1939, it covered about 10,000 acres of navigable waters
between these limits. (See U. S. Coast and Geodetic Survey Charts
Nos. 559 and 560.)
   Existing project. This provides a plan for complete eradication
of the water chestnut from the Potomac River and its tributaries
at and below Washington, D. C., by (1) 4 years of mechanical
cutting in heavily infested areas with manual removal of scattered
plants; (2) 3 years of intensive patrol and manual removal of
scattered plants; (3) 2 years of concentrated patrol during the
growing season; (4) 6 years of patrolling the entire area every
2 years. The tidal ranges are: Mean, 1.1 feet at Maryland Point
and 2.9 feet at Washington; irregular, 2 feet at Maryland Point
and 4.5 feet at Washington; extreme, approximately 7.5 feet at
Maryland Point and 10.7 feet at Washington.
   The estimate of cost to the Federal Government, made in 1947,
was $142,000, which is the total of annual costs over a 15-year
period, decreasing from $32,000 during the first year to $3,500
for the ninth year and an average of $1,000 for each of the 6
years thereafter. This is an average of $9,467 annually for the
15 years. If a longer period is required, the average annual cost
for each subsequent year is estimated to be $1,000. The work is
maintenance.
   The existing project was authorized by the River and Harbor
Act approved May 17, 1950 (H. Doc. 113, 81st Cong., 1st sess.).
The latest published map is in the project document.
   Operations and results during fiscal year. Removal of water
chestnut growth was in progress during July and August 1953 and
June 1954 in the following areas: Washington Harbor, Potomac
River at Alexandria, Virginia, Potomac River at Mt. Vernon, Vir-
ginia, Occoquan Creek, Virginia and Potomac River below Wash-
          RIVERS AND HARBORS-WASHINGTON, D.C., DISTRICT                                      249
ington, D. C., by Government plant and hired labor at a cost of
$16,029. The cost of miscellaneous inspections and reports charge-
able to the project was $9,227. Supervision and administration
was $830.
   Total costs for the year were $26,086, all for maintenance.
   Condition at end of fiscal year. Work on the elimination of
water chestnuts has been in progress since 1939 under allotments
for maintenance of five existing river and harbor projects. Prior
to the adoption of this project and through the fiscal year ending
June 30, 1950, a total of 25,000 acres of the growth has been cut
and recut from the Potomac River and its tributaries between
Washington, D. C. and Maryland Point. All infested areas have
been cut at least once. Two years of mechanical cutting in heavily
infested areas and manual removal of scattered plants as listed
for accomplishment under the eradication schedule for the existing
project have been completed under maintenance of other existing
river and harbor projects prior to adoption of the eradication
project.
   Prior to the adoption of the project and through the fiscal year
ending June 30, 1950, maintenance funds in the amount of $310,187
were expended for removal of water chestnuts. This amount in-
cludes $10,000 allotted under Section 3 of the River and Harbor
Act of July 3, 1950 and $10,000 allotted under Section 3 of the
River and Harbor Act of October 17, 1940 to ten tributaries of the
Potomac River, and the following maintenance funds from existing
river and harbor projects in the affected area: Washington Harbor,
D. C., $19,726; Potomac River at Alexandria, Virginia, $22,023;
Potomac River below Washington, D. C., $200,937; Potomac River
at Mt. Vernon, Virginia, $18,202; and Occoquan Creek, Virginia,
$29,300. The cost of miscellaneous inspections and reports charge-
able to the project was $10,057.
  In addition, a total of $101,162 contributed by the United States
Public Health Service was expended.
  Total costs for the existing project were $89,660, all for the
maintenance.
                             Cost and financial summary

                                   Fiscal year ending June 30                    Total to June
                                                                                30, 1954, includ-
                                                                                ing fiscal
                                                                                        years
                      1950        1951        1952        1953       1954             to1950
                                                                                  prior
Maintenance:
   Appropriated.                  $30, 500    $27, 000     $6, 200   $26, 000            $89, 700
   Cost .-         -17,               488      22, 345     23, 741    26, 086                89, 660


                   4. LITTLE WICOMICO RIVER, VA.
   Location. Little Wicomico River is a tidal estuary 6 miles in
length lying in Northumberland County, Va., flowing in a south-
easterly direction to the Potomac River, which it enters on the
right bank one-half mile upstream of its mouth and 1071/' miles
downstream from Washington, D. C. (See U. S. Coast and Geo-
detic Survey Chart No. 557.)
250            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Existing project. This provides for a channel 8 feet deep, 150
feet wide, and 4,800 feet long, extending from deep water in
Potomac River to deep water in Little Wicomico River, for two
stone jetties extending to the 8-foot contour in Potomac River, and
for bulkhead walls from the inner ends thereof extending suffi-
ciently into Little Wicomico River to stabilize the dredged inner
channel. The plane of reference is mean low water. The tidal
ranges in the Potomac River at the entrance are: Mean, 1.2 feet;
irregular, 2.5 feet; and extreme, approximately 7 feet. The mean
tidal range within the river is approximately 1 foot.
   The cost to the Federal Government for new work, for the com-
pleted project, was $81,885, exclusive of $5,000 to be contributed
by local interests. The latest (1950) approved estimate for an-
nual cost of maintenance is $6,600.
   The existing project was adopted by the River and Harbor Act
of August 30, 1935 (Rivers and Harbors Committee Doc. 24, 74th
Cong., 1st sess.). The latest published map is in the project
document.
   Local cooperation. Fully complied with.
   Terminal facilities. There are two wharves open to the public
and numerous small wharves and stagings for private use, an
oyster shucking and packing plant, and a marine railway and boat-
building yard. These facilities are considered adequate for present
commerce.
   Operations and results during fiscal year. None. The costs
were $5,202 for accounts payable from the preceding fiscal year,
all applied to maintenance.
   Conditionat end of fiscal year. The existing project was started
in October 1936 and was completed in December 1937. The con-
trolling depth in the entrance channel between the jetties in Janu-
ary 1953 was 8.0 feet at mean low water for a width of 150 feet.
The controlling depth within the creek in July 1945 was 7.9 feet
for a width of 150 feet.
   Total costs under the existing project were $195,313, of which
$81,885 was for new work and $113,428 was for maintenance.
In addition, $5,000 contributed funds were expended for new work.
                                         Cost and financial summary

                                                      Fiscal year ending June 30                          Total to June
                                                                                                         30, 1954, includ-
                                                                                                         ing fiscal years
                                 1950               1951               1952         1953       1954        priorto 1950

New work:
   Appropriated --         ------              ------------------------------.---                               1$81, 885
   Cost--------      ------------------------------------------------------------                                  81,885
Maintenance:
   Appropriated --------         $16, 400         -$2, 538                          $12, 000   $3, 788            113, 428
   Cost__
       ----------------           14, 227            -128                            10,586     5, 202            113, 428


  1In addition $5,000 for new work was expended from contributed funds.

                             5. RAPPAHANNOCK RIVER, VA.
   Location. Rappahannock River rises in the Blue Ridge Moun-
tains in Virginia, and flows southeasterly about 212 miles to enter
       RIVERS AND HARBORS-WASHINGTON,       D.C., DISTRICT     251
Chesapeake Bay, about 40 miles north of Old Point Comfort, Va.
 (See U. S. Coast and Geodetic Survey Charts Nos. 534, 535, 536.)
   Previous projects. The original project was adopted by the
River and Harbor Act of March 3, 1871, and modified in 1879. For
further details see page 1793 of Annual Report for 1915 and page
433 of Annual Report for 1938.
   Existing project. This provides for a channel 12 feet deep and
200 feet wide between the mouth and Port Royal and 12 feet deep
and 100 feet wide between Port Royal and Fredericksburg by
dredging and the construction of 20,401 feet of crib and pile dikes
and 1,906 feet of riprap stone dikes being designed to retain the
excavated material deposited behind them. The length of water-
way included in the project is 107 miles. The plane of reference
is mean low water. Tidal ranges are: Mean, 2.8 feet at Fredericks-
burg, 1.6 feet at Tappahannock; irregular, 3.5 feet at Fredericks-
burg, 2.5 feet at Tappahannock; extreme, 6 feet at Fredericksburg,
5 feet at Tappahannock.
   The cost to the Federal Government for new work for the com-
pleted project was $217,487, exclusive of amounts expended under
previous projects. The latest (1950) approved estimate for annual
cost of maintenance is $30,000.
   The existing project was adopted by the River and Harbor Act
of March 3, 1905 (Annual Report for 1906, pp. 1110-1113). The
latest published map is in the Annual Report for 1910, page 1364.
   Terminal facilities. In the section under improvement extend-
ing from Fredericksburg, Va., to Tappahannock, Va., a distance of
65 miles, there are 26 wharves, of which 9 are solid bulkhead type
and 17 are open pile structures. From Tappahannock to the mouth
there are 15 open pile wharves. Most of the wharves are open
to the public. The terminals are considered adequate for existing
commerce.
   Operations and results during fiscal year. Hydrographic sur-
veys to determine channel conditions were made of 18 bars down-
stream of Fredericksburg, Va., by Government plant and hired
labor at a cost of $7,398. Snags and overhanging trees were
removed from the channel between Fredericksburg and Port
Royal, Va., in May and June 1954. The work was accomplished by
the United States derrickboat Benning at a cost of $17,652. Super-
vision and administration was $666.
   Total costs for the year were $25,716, all for maintenance.
   Condition at end of fiscal year. The existing project was
started in July 1908 and completed in April 1910. The controlling
depth was 10.5 feet at Upper Spottswood Bar in September 1953.
   Total costs under the existing project were $1,254,997, of which
$217,487 was for new work and $1,037,510 was for maintenance,
which includes $995 for Parrotts Creek and $1,000 each for Green-
vale, Mill, Beach, and Queens Creeks. In addition, the cost from
contributed funds for maintenance on Queens Creek was $600.
252             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                        Cost and financial summary

                                                 Fiscal year ending June 30                    Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                                 1950        1951           1952        1953        1954       prior to 19501
New work:
   Appropriated                                                                                         $414, 633
   Cost                                     --                                                           414, 633
Maintenance:
   Appropriated ..... _-        $53, 500     $81, 803        $1, 600    $20, 500   $37, 712        2   1, 163, 086
   Cost   -................      53, 227      80, 076         3, 068     20, 952    25, 716        2 1, 151, 010


  1   Includes $197,146 for new work and $113,500 for maintenance for previous projects.
  2 In addition, $600 for maintenance was expended from contributed funds on Queens Creek.
           6. MAINTENANCE, OPERATION, AND CAPITAL OUTLAY
                    OF THE WASHINGTON AQUEDUCT
   Location. The diversion dam and raw-water intakes are lo-
cated on the Potomac River at Great Falls 131/2 miles northwest
of Washington, D. C.; the two collecting conduits, part of the
Dalecarlia receiving reservoir, and the booster pumping plant that
lifts the water from the forebay to the main body of the Dale-
carlia reservoir are located in Maryland; and all other structures
of the water-supply system including part of the raw-water collect-
ing system, the purification plants, pumping stations, storage
reservoirs, and transmission mains are located in the District of
Columbia (See U. S. Geological quadrangle, Washington and
Vicinity).
   The control of the water-supply system is vested in the Chief of
Engineers (See acts of March 3, 1859, and March 2, 1867, and Sec.
1800 of Revised Statutes).
   Existing project. The existing project provides for (1) oper-
ation, maintenance, repair, and protection of the water-supply
facilities and reservations including collection, treatment, purifi-
cation, pumping, transmission, and storage facilities; MacArthur
Boulevard; and meters on all Federal water services as authorized
by law; and (2) the planning and construction of increased supply
facilities in accordance with House Document 480, 79th Congress,
2d Session, dated August 15, 1945, as provided in Public Law 538,
81st Congress, Chapter 218, 2d Session, H. R. 8578, approved
June 2, 1950, and as provided in Public Law 364, 83d Congress,
2d Session, Chapter 218, H. R. 8097, approved May 18, 1954.
   By act, Public Law 378, 64th Congress, approved March 3, 1917,
the furnishing of water to adjacent Maryland areas from the
Washington water-supply system was authorized by the Congress;
by act, Public Law 119, 69th Congress, approved April 14, 1926,
the furnishing of water to Arlington County, Va., from the Wash-
ington water-supply system was authorized by the Congress; and,
by act, Public Law 118, 80th Congress, approved June 26, 1947,
the furnishing of water to Falls Church or any other competent
State or local authority in the Virginia metropolitan area, sim-
ilarly, was authorized.
   A description of the District of Columbia water-supply system
and of previous capital-improvement and operation-and-mainte-
       RIVERS AND HARBORS-WASHINGTON, D.C., DISTRICT            253
nance projects is printed on pages 2206-2208 and 2218-2220 of
the Annual Report of the Chief of Engineers, 1930; in an informa-
tion pamphlet published June 1939 and revised December 1950;
and in House Document 480, 79th Congress, 2d Session.
    Local cooperation. Prior to July 1, 1880, the expenses of the
Washington Aqueduct for construction, operation, and mainte-
nance were paid wholly out of the revenues of the United States.
From July 1, 1880, to June 30, 1882, the expenses of operation
and maintenance were paid one half by the United States and
the other half out of the general revenues of the District of
Columbia. From July 1, 1882, to June 30, 1898, one half of con-
struction costs were charged to a capital account on the books of
the Treasury to be repaid by the District of Columbia from water
rents with interest at 3 percent. From July 1, 1898, to July 1,
1916, the expenses of construction, operation, and maintenance
were paid one half from surplus general revenues of the District
of Columbia and the other half from the United States Treasury.
From July 1, 1916, to June 30, 1932, the expenses of construction
were paid 60 percent out of the general revenues of the District
of Columbia and 40 percent by the United States. From July 1,
1932, to March 31, 1953, all expenses for construction have been
paid out of the water revenues of the District of Columbia, to
which the United States contributed annually a lump sum. The
expenses of operation and maintenance, since July 1, 1916, to date,
have been paid wholly out of the water revenues of the District
of Columbia. From April 1953 to June 30, 1954, $1,900,000 were
borrowed from the United States Treasury as installments on
authority to borrow up to $23,000,000 to finance the expansion and
improvement of the water system by act approved June 2, 1950,
and known as Public Law 533, 81st Congress, 2d Session, Ch. 218,
H. R. 8578.
    By act approved May 18, 1954, and known as Public Law 364,
83d Congress, 2d Session, Ch. 218, H. R. 8097, also known as the
"District of Columbia Public Works Act of 1954", increased the
authority to borrow from the United States Treasury for the
expansion of the District of Columbia water system to $35,000,-
000; and provided, also, for payment by the Government of the
United States for all water and water services furnished.
    By act approved June 10, 1920, $25,000 were appropriated
wholly from United States revenues to prepare, among other
things, a report to assure an increased and adequate water sup-
ply for the District of Columbia and this report was the basis
for the improvements constructed from 1922 to 1927. Included
in the District of Columbia appropriation acts of 1941 and 1942,
approved June 12, 1940, and July 1, 1941, respectively, a total
of $40,000 was appropriated from the water fund, District of
Columbia, for the preparation of a report "for the development
of a plan to insure an adequate future water supply for the
District of Columbia and metropolitan area."          This report,
published as House Document 480, 79th Congress, 2d Session,
contains the comprehensive plan and program for the improve-
ments and additions to the water system safely and adequately
to meet the anticipated water demands to the year 2000.
254       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

    Annually, since July 1, 1920, on a percentage basis and, since
  July 1, 1924, on a lump-sum basis, the United States has con-
tributed to the support of the District of Columbia but no part
of such annual percentage or lump-sum contributions has been
allocated to the water fund, District of Columbia, before July 1,
1947.
    Beginning with the fiscal year 1948, pursuant to act, Public
Law 195, 80th Congress, approved July 16, 1947, an annual pay-
ment of $1,000,000 was authorized for water consumed by the
Federal Government. This sum is taken from the annual lump
sum contribution of the United States to the District of Colum-
bia.
    Act Public Law 533, 81st Congress, 2d Session, Ch. 218, H. R.
8578, approved June 2,. 1950, authorized the Secretary of the
Treasury to lend with a limit of $23,000,000 to the Commis-
sioners of the District of Columbia such sums as may hereafter
be appropriated to finance expansion and improvement of the
water system when sufficient funds therefor are not available
from the District of Columbia Water Fund established by law
  (D. C. code 1940 edition, title 1943, ch. 15). The above public
law was amended by Public Law 364, 83d Congress, 2nd Session,
Ch. 218, H.R. 8097, approved May 18, 1954, by striking the figures
 "23,000,000" and inserting in lieu thereof the figures "35,000,000."
    Operationsand results during the fiscal year. An uninterrupted
and adequate supply of purified water was furnished to the Dis-
trict of Columbia; to Arlington County, Va.; and to Federal
establishments in Arlington County, Va., and in Montgomery
and Prince Georges Counties, Md. The maximum daily con-
sumption was 262,960,000 gallons and the average daily con-
sumption was 165,641,323 gallons. Based upon the estimated
average number of consumers of 967,000 in the District of Colum-
bia and 150,000 in Arlington County, the average per capita
daily consumption was 148.291 gallons. The average daily con-
sumption in the District of Columbia alone was 149,226,534 gal-
lons or an average per capita consumption of 154.319 gallons per
day. The average daily amount of water furnished to Arlington
County and Falls Church, Va., was 15,399,312 gallons or an
average per capita consumption of 102.662 gallons per day.
The gross cost for the supply furnished the Virginia communi-
ties was reimbursed to the Water Fund, D. C. The average daily
consumption of water in all Federal Government establishments
including parks, zoological garden, etc., was 30,435,864 gallons.
A total of 370,649,000 gallons or an average of 1,015,477 gallons
per day was delivered to Maryland communities during the fiscal
year 1954 by the Water Division, D. C., through connections to
the Washington Suburban Sanitary District's system. On June
23, 1952, fluoridation equipment was put in service and the appli-
cation of sodium silicofluoride started, and has continued
throughout fiscal year 1954.
        RIVERS AND HARBORS-WASHINGTON,       D.C., DISTRICT     255
    The average turbidity of the raw water from the Potomac
River was reduced from 70 parts per million to 0.0 parts per
million and the average bacterial content was reduced from
1,900 to 1.0 per millimeter. Analyses were made for bacterium
colon on 99,872 tubes of water taken from 107 sampling points
in the purification and distribution systems. After sterilization
of the filter effluent, the average number of bacterium colon per
100 millimeters was found to be 0.0008 at Dalecarlia and 0.0 at
the McMillan filter plant. The average alkalinity of the filtered
water was 68 parts per million and the average pH value was
7.7 from the Dalecarlia filter plant, and 74.0 and 7.6 from the
McMillan filter plant. The average hardness was 113 parts per
million from Dalecarlia and 107 parts per million from McMil-
lan. Fluorine content of 3,800 water samples was determined.
   The direct operating costs of water treated and delivered to
the system per million gallons was $31.20 as compared with the
cost of $31.10 per million gallons in fiscal year 1953. The over-
all cost of water delivered, including depreciation and interest
was $59.58 per million gallons as compared with $58.61 in 1953.
   Construction work authorized with "no year" funds not pre-
viously reported as completed was as follows:
   Repair and rehabilitation of McMillan filter plant 64 percent;
circulating facilities in 1st and 2d high service reservoirs 76 per-
cent; Georgetown Castle gatehouse 90 percent; modification to
provide quality control of filtered water 67 percent; improving
conveying equipment for chemicals 82 percent; 30 million-gallon
clearwater basin at Dalecarlia 100 percent; conduit repairs
 (periodic) 100 percent; overhaul of wash-water valves 87 per-
cent; acquisition of supplementary land 66 percent; purchase
and installation of federal meters 85 percent; replacement of
roof over Dalecarlia filters 100 percent; auxiliary raw-water
supply at Dalecarlia 100 percent; hydro station improvements
11 percent and 3d high service transmission main 2 percent.
   The preparation of plans for capital outlay projects for in-
creasing the water supply progressed as follows:
   Third high service reservoir at Reno 85 percent; 48-inch pipe
line from Dalecarlia to Reno 100 percent for Part I (10,000 feet)
and 10 percent for Part II (1,700 feet) ; Crosstown interconnect-
ing main from Dalecarlia to low-service area 12 percent; McMil-
lan filter plant improvements 100 percent; new chemical build-
ing and operating center at McMillan 55 percent; Dalecarlia
pumping station 99 percent; Great Falls intake structure 10
percent; federal meters 85 percent; land acquisition 70 percent;
conduit repairs (periodic) 65 percent; Little Falls pumping sta-
tion, dam, and tunnel 90 percent.
   System costs. The total cost for the fiscal year was $2,781,-
460.31 distributed-




     Sig 9--255-286
256               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Financial statement:
  1.- Operating expenses*
        Collecting system..---....---..---------.........................-----........... $191,455 .71
        Purification system ................................................ 1,130, 493.44
        Pumping system-------.........----------------.......................................... 485,848.01
        Transmission system .-----...---..--------.........................---....-----....       63,856.17
                                                                                                              $1,871,653.33
   2. Capital outlay
        Third high reservoir, Reno.................................             $16, 286.24
        Utility relocations ...............................                      36, 747.94
        Federal meters ..............---....................................     46, 276.14
        Hydro electric station improvements..........                             4,244.77
        Advance planning..............................................        -199, 727.33
        Cathodic protection of flocculators.................                         183.71
        Circulating facilities and conduit repairs ..............                62, 186.80
        Remodeling Georgetown Reservoir.............                             38, 426.24
        Land purchases...................................                         7, 483.10
        Six new filters......................................................        276.70
        Dalecarlia 30 million-gallon clear water basin-....                     353, 022.43
        Dalecarlia Pumping Station................................              106, 492.49
        New McMillan Chemical Bldg., and Operating
        Center .......................................                               987.84
        Third high service transmission main................                     45,839 .81
        Great Falls intake structure ..................................              474.89
        Repairs to bridges and culverts............................                  508.85
        Overhaul of wash-water valves..............................               3, 832.23
        Little Falls Pumping Station, Dam, and Tunnel                           312,020.20
        Auxiliary raw-water supply-Dalecarlia....... ...                          9, 507.38
        Replace roof over Dalecarlia Filter Plant-.....                          18, 009.77
        Improve conveying equipment for chemicals......                           3,242.74
        Modifications, quality control filtered water......                       4,768.62
        Dalecarlia Reservoir raw-water intake and
           conduit............... ................. ...............-...-         11, 220.53
        Improvement of McMillan Filter Plant facilities                          29, 683.08                        1   ^^   r   1   M7k




                                                                                                                  1,      17
                                                                                                                         .995
   3. Deferred accounts ...                  ....----------------------------                           --..-     2, 188.19

         Total cost for fiscal year 1954.......... ...........                          2, 781, 460 .31
                                                                     ...........--------------------
                                             ..............................................
   *Operating expenses cost per million gallons------------------                                 $31. 20

Accident prevention:                                                     Government  Contractors    Total
  Man-hours exposure ...............-................ 628,291                           48,729   676,920
  Accidents ...............................-------------------------------         5           0        5
  Lost time (days) ........----------------...........------............        233            0     233
  Frequency (accidents per million man-hours
    worked) ....-..   -------------------------------                          7 .96       0 .00    7.39
  Severity (days lost per 1,000 man-hours
    worked)..........------------------------------                            0.37        0.00     0.34

  Visitors. 1,330 persons were conducted through the water
treatment and pumping plants and the bacteriological and chem-
ical laboratories. College engineering, science students, public
school pupils, and public officials numbered 1,300. Foreign vis-
itors totaled 30.
  Control. All funds were expended in conformity with the
legislative provision contained in the annual appropriation act
which was as follows:
  "Nothing herein shall be construed as affecting the superintendence and control
of the Secretary of the Army over the Washington Aqueduct, its rights, appurte-
nances, and fixtures connected with the same, and over appropriations and expendi-
tures therefor as now provided by law."
                 RIVERS AND HARBORS-WASHINGTON, D.C., DISTRICT                                                                           257
   Condition at end of fiscal year. The intakes, conduits, reser-
voirs, filter plants, pumping stations, mechanical equipment, and
structures with the exception of the McMillan filter structures
on which repairs are in progress were in a generally good con-
dition. However, the demands upon the supply system have
exceeded its nominal capacity and, for several years, its opera-
tion has been in the overload category. During maximum con-
sumption demand periods, the basic raw-water supply was ex-
ceeded and emergency equipment had to be utilized.
                          Cost and financial summary as of June 30, 1954
Net appropriations .................................................................------------------------------------         $76, 037, 136.22
Unexpended balance................-------------------............................... $16, 891, 112.32
Net available ..-----......................................................................------------------------------------.  16, 891, 112 .32
      Total costs ..................................................................-------------------------------------.       $59, 146, 023 .90

                                                              Division of costs

                                                                                             Paid by
                       Units                              United States                                                            Total
                                                                                District of             Water
                                                                                Columbia              Department
Construction ......................--------------------   $10, 965, 377. 11    $9, 109, 312. 82      $12, 269, 413.61        $32, 344, 103. 54
Maintenance ---------------------                    1, 250, 656. 36               955, 473. 18       24, 265, 600. 67        26, 471, 730. 21
Spring-water supply-----------------                    223, 621. 81                                                              223, 621. 81
Deferred charges -------------------------------.---                                                  -    106, 568. 34           106, 568. 34

         Total                                             12, 439, 655.28    110, 064, 786.00        36, 641, 582.62         59, 146, 023.90


  1 Includes such part of the annual lump sum contribution by the United States to the District of Columbia
that could be considered a direct Federal expenditure.
258                   REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954
                                   7. INACTIVE                      NAVIGATION                     PROJECTS
                                                                                                     _i




                                                                               For last           Cost to June 30, 1954                  Estimated
                                                                              full report                                                 amount
                         Name of project                                          see                                                     required
                                                                                annual              Con-            Operation                to
                                                                                report           struction             and               complete
                                                                                 for-                              maintenance

1.   Potomac River at Alexandria, Va.                        _.......               1953            $95,215                $216, 636
2.   Potomac River below Washington, D. C. -__                                      1953            153, 836               2893, 414
3.   Potomac River at Mt. Vernon, Va. .-.....                                       1950             17,000                  51, 486        $11, 000
4.   Accotink Creek, Va.'..------                       _--.-          .            1878              5, 000      -                         1637, 000
5.   Occoquan Creek, Va.              __________________                            1950            541, 253                112,686          22, 700
6.   Neabsco Creek, Va.' _______________                                            1884              5, 000          --     -              127, 000
7.   Aquia Creek, Va ...........................                         4_         1928            652, 465                 11, 750
8.   Potomac River at Lower Cedar           1       Point, Md.                      1920             10,234                    6,216
9.   Upper Machodoc Creek, Va. .                              7                     1916
                                                                                     19 5             20,281                    6,119
10.   Colonial Beach, Va., Shore Protection ...                            _              0                                                 16   49, 000
11.   Monroe Bay and Creek, Va.'                                                     1953             12. 460                 19, 164
12.   Neale Sound, Md...........                                   ....----------.   1950            812, 600                     900
13.   St. Catherine Sound, Md. -----------------                                     1949                                                    1627, 000
14.   St. Patricks Creek, Md.' ..                        -                           1950                                                    1620, 000
15.   Breton Bay, Md.'__"    ............ 1 -              ..........                1950           1047,924                  12,621        16 31, 600
16.   Nomini Bay and Creek, Va. 2 9                                                  1946            78. 446                  31, 234        1621,500
17.   Lower Machodoc Creek, Va. -                                          1         1904              9,916                      600
18.   Bransons Cove, Lower Machodoc Creek, Va.                                       1950             15, 755
19.   Channel to Island Creek, St. George Island,                                                    - - -_: -_ -_ -
                                                                                                .......--
        M d . ................. . .--                  .........         ...         1949                                                    1627,000
20.   Smith Creek, Md. ................-..                               .....       1936             5,252-
21.   Coan River, Va. 7 _-                                                _          1937                                                        81, 000
22.   Patuxent River, Md.S 11-- _                                                    1905           1214, 000.               ..     -            14, 000
23.   Hellen Creek, Md....----------------------                                     1950                                                        11,000
24.   St. Jeromes Creek, Md.3_..................                                     1951           17,857             -      24, 380
25.   Cockrell Creek, Va...                       ..----------------------           1949                                                   16116, 000
26.   Cranes Creek, Va..._______________________                                     1950              6, 274      --       - - - - -        1
27.   Dymers Creek, Va.* __-________ .....                  ______...                1953              5, 582                  4, 524
28.   Hoskins Creek, Va.' --                                                         1953           1444, 100                 48, 676
29.   Totuskey Creek, Va.9                               -                           1953            337, 648                 80, 612       16120,400
                                                                           9.
30.   Rappahannock River at Bowlers Wharf, Va.                                       1950                                                   16172, 000
31.   Mulberry Creek, Va. ......................                          _          1950                 2, 393               1, 767
32.   Urbanna Creek, Va ..          .--__............                                1951             38, 812 }               46, 822         16, 200
33.   Whitings Creek, Va.                                - - -)                      1949                                                    1631,000
34.   Carters Creek, Va. 7 _______________________                                   1951             28,398                 1 3, 176        1623,600
35.   Locklies Creek, Va.' -                                                         1928             11, 581                     519
36.   Mill Creek, Va.       -.-.-                                                    1937              5,445 -
37.   Broad Creek, Va.3_                                                             1952             27, 888                     824
38.   Jackson Creek, Va. ____                                                        1950              8, 500                     491
39.   Milford Haven, Va.          _                                                  1950             24. 568                 14, 278
40.   Snagging and clearing under authority of Sec-
        tion 3 of the River and Harbor Act aplproved
        March 2, 1945 -                               -            _                 1949                                      3,000..

   1 Completed.
   2 In addition, costs of $101,162 of U. S. Public Health Service funds were incurred for water chestnut eradi-
cation.
   s Channels adequate for commerce.
   ' No commerce reported.
   5 Includes $25,000 for new work for previous projects.

   6 Includes $31,065 for new work for previous projects.
   7 Awaiting local cooperation.
   8 In addition, there was a cost of $1,000 for new work from contributed funds.
   9 No funds available.
  10Includes $37,500 for new work for previous projects.
  11Abandonment recommended in 1903 (Rivers and Harbors Committee Doe. 32, 61st Cong., 2d sess.).
  12Includes $10,617 for new work for previous projects.
  1" In addition, there was a cost of $26,500 for new work for previous projects.
  14In addition, there was a cost of $500 for new work from contributed funds.
  15In addition, there was a cost of $700 for new work from contributed funds.
  16Estimated amounts required to complete were revised in 1954.

             8. INACTIVE MISCELLANEOUS                                                        CIVIL WORKS PROJECTS

                                                                                For last           Cost to June 30, 1954                 Estimated
                                                                               full report                                                amount
                          Name of project                                          see                                                   required
                                                                                annual              Con-            Operation                to
                                                                                 report          struction             and               complete
                                                                                  for-                             maintenance
       Anacostia Park and the reclamation and de-
        velopment of Anacostia River and flats from
        the mouth of the river to the District Line,
        D. C.- __ _-                     -     __                                    1953         $3, 910. 582 i ....             -..
                                                                                                                                   ...    1$3,177, 600

  1 Revised July 1954.
           FLOOD CONTROL-WASHINGTON,       D.C., DISTRICT        259
9. ANACOSTIA RIVER AND TRIBUTARIES, FLOOD PROTECTION
       AND NAVIGATION IMPROVEMENTS, DISTRICT OF
                COLUMBIA AND MARYLAND

   Location. This project is located on the Anacostia River at the
confluence of northeast and northwest branches at Bladensburg,
Md., about 9 miles above the mouth at Washington, D. C. (See
U. S. Coast and Geodetic Survey Chart 560.)
   Existing project. The project provides for channel improve-
ment of Anacostia River from the foot of Fifteenth Street SE. in
the District of Columbia, to the junction of northeast and north-
west branches at Bladensburg, Md.; channel improvement in north-
east branch from mouth upstream to near Longfellow Street in
Riverdale, Md.; channel improvement in northwest branch from
mouth upstream to near Thirty-eighth Street in Brentwood, Md.;
levees along both banks of the streams to protect Bladensburg,
Edmondston, Riverdale, Cottage City, and Colmar Manor, Md.; in-
terior drainage facilities in these communities, including four
pumping stations and the necessary intercepting sewers; and
alterations and reconstruction of highway and railroad bridges.
The portion of the channel improvement of Anacostia River from
the vicinity of Fifteenth Street SE. in the District of Columbia to
near Defense Highway bridge on U. S. Route 50, provides for a
navigation channel 8 feet deep and 80 feet wide with a commercial
boat basin, and a recreational boat basin having a capacity of 150
boats, both on the left bank of the river near Bladensburg, Md.
The estimated Federal cost for construction, revised in 1954 is
$7,600,000; the estimated cost to local interests for construction,
lands and damages is $5,280,900; a total of $12,880,900.
   The existing project was authorized by the Flood Control Act
approved May 17, 1950 (H. Doc. 202, 81st Cong., 1st sess.). The
latest map is in the project document.
   Local cooperation. The existing project was approved subject
to the conditions that local interests assume responsibility for fur-
nishing all lands, easements, rights-of-way, and spoil disposal areas
necessary for construction of the improvements and for subsequent
maintenance when and as required, including in this responsibility
the replacement of highway bridges and changes in streets, sewers,
drainage works, and other utilities except for replacement of the
railroad bridge; hold and save the United States free from damages
due to construction works; maintain and operate all the flood con-
trol features of the project in accordance with regulations pre-
scribed by the Secretary of the Army and maintain project depths
in the recreational boat basin and the commercial harbor; and pro-
vide and maintain without cost to the United States at both the
commercial and recreational boat basins necessary mooring facili-
ties including public landings with suitable supply facilities, open
to all on equal terms. Local interests furnished assurances meet-
ing in full the prescribed conditions of local cooperation. The as-
surances were approved by the Division Engineer, North Atlantic
Division on June 28, 1954.
   Operationsand results during fiscal year. Engineering investi-
gations were continued during the fiscal year by hired labor for
260                REPORT OF CHIEF                         )F ENGINEERS, U. S. ARMY, 1954

revision of hydrologic and hydraulic data, foundation investiga-
tions and planning of flood control structures. Design memoranda
No. 2, Hydraulics; No. 3, General Design Memorandum; No. 4,
Interior Drainage; No. 5, Northeast Branch; and No. 6, Relocation
of Baltimore and Ohio Railroad Bridge No. 1-A, were completed by
hired labor. Plans and specifications for construction of the first
unit of the project on the Northeast Branch were completed by
hired labor. Model tests for the high speed channel on the North-
west Branch were initiated by hired labor.
   Total costs for the year were $151,650, all Federal funds for new
work.
   Condition at end of fiscal year. Engineering investigations and
planning for the project were 68 percent complete at the end of the
fiscal year.
   Total costs to June 30, 1954, were $259,568, all Federal funds,
for new work.
                                                Cost and financial summary

                                                           Fiscal year ending June 30                                       Total to June
                                                                                                                           30, 1954, includ-
                                                                                                                            ing fiscal years
                                        1950             1951             1952             1953             1954             prior to 1950

New work:
   Appropriated.----------------- ------------                            $25, 000        $78, 000        $175, 000                $278, 000
     Cost.......
             __          .-                                                 9, 326          98, 592         151, 650                259, 568


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 ...............                                                         $4, 709
    Appropriated for succeeding fiscal year ending June 30, 1955 ...........                                                     900,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955 .....                                                                                                        904, 709
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project.............................................------------------------------------.........      6, 422, 000

                    10. CUMBERLAND, MD., AND RIDGELEY, W. VA.
   Location. Cumberland, Md., and Ridgeley, W. Va., are located
on the North Branch of the Potomac River, 21 miles upstream from
its junction with the South Branch of the Potomac River and 197
miles upstream from Washington, D. C. (See U. S. Geological Sur-
very quadrangles, Frostburg and Flint Stone, Md., W. Va., and Pa.)
   Existing project. This project provides for channel improve-
ments of North Branch of Potomac River from Western Maryland
Railway bridge in South Cumberland upstream to the mouth of
Wills Creek, with levees and fill along the left bank and levees along
the right bank from the downstream corporate limits of Ridgeley,
W. Va., to a point about 150 feet above Johnson Street Bridge;
channel improvements along Wills Creek from its mouth upstream
to a point in the Narrows about 500 feet upstream from highway
bridge on U. S. Highway No. 40; levee and flood wall in West Cum-
berland, Md., on left bank of North Branch of Potomac River from
mouth of Wills Creek upstream to Kelly Boulevard; levee and flood
wall in Ridgeley, W. Va., on right bank of North Branch of Po-
tomac River from Carpenter Avenue upstream to Patapsco Street
near the upstream corporate limits of Ridgeley, W. Va.; interior
drainage facilities in Cumberland and West Cumberland, Md., and
                 FLOOD CONTROL-WASHINGTON, D.C., DISTRICT                                        261
Ridgeley, W. Va.; removal of Chesapeake and Ohio Canal dam and
construction of a new industrial dam on North Branch of Potomac
River immediately above mouth of Wills Creek; and alteration and
reconstruction of highway and railroad bridges.
   The estimate of cost to the Federal Government for new work,
revised in 1954, is $15,900,000, exclusive of $1,050,000 to be con-
tributed by local interests, and $49,998, Emergency Relief funds.
The estimated total cost to local interests is $2,320,000.
   The existing project was authorized by the following flood-con-
trol acts:

     Acts                       Work authorized                          Documents and reports
June 22, 1936   Levees, retaining walls, a movable dam, and chan-   H. Doc. 101, 73d Cong., 1st sess.
                  nel clearing for Cumberland, West Cumberland
                  and South Cumberland, Md., and Ridgeley, W.
                  Va.
July 24,1946    Levees, walls, channel improvement, removal of      Report on file in the Office of the
                 Chesapeake and Ohio Canal dam and construction       Chief of Engineers.
                 of new industrial dam.


    Local cooperation. Assurances of local cooperation with the
project plan have been received. A total of $2,320,000 will be the
cost to local interests of which $1,050,000 will be in cash towards
construction and the balance will be for lands required for construc-
tion of the project and damages incurred. Funds, lands, and
rights-of-way are being furnished as required.
    Operations and results during fiscal year. Construction, by
continuing contract, was completed in May 1954 on section 1 of the
Wills Creek channel improvement. Costs for the year were $921,-
848, of which $917,297 was Federal funds and $4,551 was con-
tributed funds. Work on the Industrial Dam under a continuing
contract was completed in June 1954 except for strengthening and
protecting two piers of the Western Maryland Railway Company
bridge 1656. Costs for the year were $840,117, of which $625,084
was Federal funds and $215,033 was contributed funds. Construc-
tion of the West Cumberland floodwall under a continuing contract
was started in June 1954. There were no costs during the year.
Design engineering for features of construction not yet underway
was continued throughout the year by hired labor. Costs for the
year were $90,416, of which $81,116 was Federal funds and $9,300
was contributed funds. The costs for land acquisition during the
year were $273, and costs for the year in connection with lands and
damages by hired labor were $6,782, all Federal funds. Undis-
tributed Government costs were $176, all Federal funds.
   Total costs for the fiscal year for new work were $1,859,613, of
which $1,630,728 was Federal funds and $228,885 was contributed
funds.
   Condition at end of fiscal year. The existing project was about
35 percent complete at the end of the fiscal year. Construction of
the first unit of the project, consisting of four pressure conduits
and connecting sewers, started in March 1949 was completed in
November 1949. Construction of the second and final unit of in-
terior drainage pressure conduits and sewers, started in November
1949 under a continuing contract, was completed in December 1951.
262               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Construction of section 1 of the Wills Creek channel improvement,
started in April 1952 under a continuing contract, was completed
in May 1954. Construction of the Industrial Dam, started in April
1953 under a continuing contract, was completed in June 1954,
except for strengthening and protecting two piers of the Western
Maryland Railway Company bridge No. 1656. Construction of the
West Cumberland floodwalls was started in June 1954 under a con-
tinuing contract. Designs and construction plans for the various
units of construction were in the following stages of completion at
the end of the fiscal year:
                                                                                                                                        Percent
Unit                                                                                                                                   complete
              ........ ..---------....
Relocations------             ----     --..                                                                                              25
Channels:
    Potomac River, section 1..........------...-...-.       .         .        .         .....                                           95
    Potomac River, section 2.................-------------------------------------                                                       50
    Wills Creek, section 2...................       ----------------------------------------                                             85
       Wills Creek, section 3................. ...........              ............---------------------                                45
    Wills Creek, section 4 ...............                                                                                                15
Levees:
    Potomac River, section 1                                                     .......-------------------------------------.......     90
    Potomac River, section 2........                                 .......-------------------------------------.                       15
Floodwalls .--..                 ......              ..               ..........------------
                                                                ...----------------       ---------------------                          95
Pumping plants:
   Viaduct--     ----          --------............-----------------------......------------------                                       80
   Mill race........                                     ..........-------------------------------------------------                     60
       Ridgeley .--                 ---------------...............                                                           ......      40


  Total costs for the existing project to June 30, 1954, have been
$6,312,071, of which $5,600,844 was Federal funds, $661,229
contributed funds and $49,998 Emergency Relief funds, all for new
work.
                                             Cost and financial summary
                                             UNITED STATES FUNDS


                                                       Fiscal year ending June 30                                            Total to June
                                                                                                                           30, 1954, includ-
                                                                                                                            ing fiscal years
                                      1950           1951               1952               1953               1954            prior to 19501
New work:
    Appropriated     -......------..
                                  $744, 100      $1, 154, 000         $946, 000        $1,144,000            $950, 000             $5, 889, 170
    Cost----------------             702, 502        939, 843           565, 142        1, 082, 882         1, 630, 728            2 5, 650, 842

  1 Includes $49,998 expended from Emergency Relief Funds.
  2In addition, $661,229 for new work was expended from contributed funds.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-..........................                                             $184,853
    Appropriated for succeeding fiscal year ending June 30, 1955...........                                                       500, 000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955----------------.------------------------..                                                                        684, 853
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project.....................................................................                         9, 560, 800
                 FLOOD CONTROL--WASHINGTON,                           D.C., DISTRICT                     263
                                           Contributed Funds

                                            Fiscal year ending June 30                         Total to June
                                                                      •__"     _               30, 1954, includ-
                                                                                               ing fiscal years
                              1950         1951        1952       1    1953         1954         prior to 1950

New work:
    Appropriated---.. --_-   $500, 000 1-$50, 000    2-$17, 648       $251, 000 ..                     $683, 352
    Cost................      330,000 ...-......-       59,660          42, 684    $228, 885            661, 229


  1 Refund of contributed funds $50,000.
  2 Refund of contributed funds $70,000.


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-------...........            ...------ $16, 698
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955        -----------------------............             --------------------------      16,698
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project                  -----------------------------.....   -----       366, 648

                             11. SAVAGE RIVER DAM, MD.
    Location. On the Savage River, in Garrett County, Md., ap-
proximately 4.5 miles above the junction with North Branch of the
Potomac River, and immediately downstream of the junction of
Crabtree Creek and Savage River, and approximately 4 miles north-
west of Bloomington, Md. (See U. S. Geological Survey quad-
rangle, Grantsville, Md.-Pa.)
    Existing project. The construction of an earth and rockfill
dam, with a maximum height of 184 feet above the streambed, was
started in 1939 as a project of the Works Progress Administration,
under sponsorship of the Upper Potomac River Commission. Work
was suspended in December 1942, because of the war. The present
project provides for completion of the earth and rockfill dam by
the Corps of Engineers, United States Army, and includes placing
about 850,000 cubic yards of earth and rockfill embankment and
5,200 cubic yards of concrete in spillway and intake structure, in-
stallation of control equipment in tunnel control chamber, and
construction of operating house and other appurtenant structures.
The cost of the project to the Federal Government for the com-
pleted project was $2,071,939, exclusive of $200,000 to be con-
tributed by local interests. The project is primarily for regulation
of stream flow for industrial purposes, and pollution abatement,
with some incidental flood control. The reservoir will have a stor-
age capacity of 20,000 acre-feet. Authorization for the project is
contained in the Flood Control Act approved July 24, 1946 (H. Doc.
622, 79th Cong., 2d sess.).
   Local cooperation. Fully complied with.
    Operations and results during fiscal year. Minor structural
corrections were made and permanent signs installed by contract
during the year. The operation and maintenance manual, reservoir
regulation manual, sedimentation studies, surveys and miscel-
laneous engineering were completed during the year by hired labor.
   Total costs for the year were $6,935, all of which were Federal
funds.
   Condition at end of fiscal year. The existing project was ap-
proximately 60 percent completed by the Works Projects Adminis-
264            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

tration prior to the termination of the work in 1942. Construction
work, started under the adopted project in March 1949 under a
continuing contract, to complete the embankment portion of the
dam was completed in May 1950. A supply contract for fabrication
of slide gates and hydraulic equipment was awarded in August
1949 and completed in August 1950. A contract for repairs to the
relocated road was awarded June 1951 and completed in October
1951. A continuing contract for the completion of the spillway and
outlet structures and miscellaneous work, initiated in March 1950,
was completed in January 1952. A contract for clearing the reser-
voir area was awarded in November 1950 and completed in May
1951. A contract for stabilizing and reforesting borrow areas was
awarded in July 1950 and completed in June 1952. The entire
project was 100 percent complete at the end of the fiscal year and
was placed in operation during January 1952.
   Total costs to June 30, 1954, were $2,271,939, of which $200,000
was contributed funds and $2,071,939 was Federal funds.
                                      Cost and financial summary

                                             Fiscal year ending June 30                             Total to June
                                                                                                    30, 1954, includ-
                                                                                                    ing fiscal years
                               1950         1951         1952         1953           1954            prior to 1950


New work:
   Appropriated -          $1, 265, 000    $450, 000   -$65, 000    -$31, 000 ----              -     1$2, 075, 000
   Cost....---------------      71, 213     732, 490     181, 143      33, 045         6, 935          '2, 071, 939

  IIn   addition, $200,000 was expended from contributed funds (see Annual Report for 1950).

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954----............           $3, 061
                                                                          ....-----------
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955------............................................................             061

                   12. SALEM CHURCH RESERVOIR, VIRGINIA
  Location. The Salem Church multiple purpose reservoir, to be
located on the Rappahannock and Rapidan Rivers in Spotsyl-
vania, Stafford, Orange, Culpeper, and Fauquier Counties, Va.,
would be created by a concrete gravity dam on the Rappahan-
nock River, 5.6 miles above Fredericksburg, Va., and 113 miles
above the mouth. (See Army Map Service Quadrangle, Salem
Church, Va.)
  Existing project. The plan of improvement provides for con-
struction of a concrete gravity dam, approximately 1,460 feet
long, with a maximum height of 205 feet above bedrock, and
earth embankments extending from both abutments, totaling
                  FLOOD CONTROL--WASHINGTON, D.C., DISTRICT                                                  265
13,710 feet in length, with a maximum height of 35 feet. The
spillway, located in the concrete gravity section of the dam,
would be controlled by 8 crest gates 52 feet long by 35 feet high
and would have a discharge capacity of 567,000 cubic feet per
second. The project provides for a powerplant, to be con-
structed on the left bank of the river immediately downstream
from the dam, containing two 32,000-kilowatt generating units.
The reservoir will afford flood protection for Fredericksburg,
Falmouth, and areas downstream for a flood of 140,000 cubic
feet per second, which is equal to the greatest flood of record,
and will reduce the severity of floods of greater magnitude. The
estimated Federal cost for new work, revised in 1954, is $46,000,-
000, of which $43,200,000 is for construction, and $2,800,000 is
for lands and damages. Authorization for the project is con-
tained in the Flood Control Act approved July 24, 1946, which
stipulated that the maximum elevation of the power pool should
not exceed elevation 220 feet mean sea level. The latest pub-
lished maps are in the project document.        (See H. Doc. 119,
80th Cong., 1st Sess.)
    Local cooperation. None required.
    Operations and results during fiscal year. Reimbursement was
made to property owners in connection with rights-of-way for
foundation exploration, and preliminary plans were reviewed
to conform with present criteria, by hired labor. The total costs,
all for new work, were $1,156.
    Condition at end of fiscal year. No construction work has been
done. A design memorandum presenting a preliminary plan
for a dam with maximum power pool at elevation 220 feet mean
sea level, as provided in the authorization, is complete. Further
engineering studies have been indefinitely postponed. The work
remaining to be done is initiation and completion of detailed
design and preparation of contract plans and specifications by
hired labor and construction of the project by contract. The
total costs, all for new work, were $144,785.
                                           Cost and financial summary

                                                      Fiscal year ending June 30                   Total to June
                                                                                                  30, 1954, includ-
                                                                                                  ing fiscal years
                                   1950            1951         1952        1953       1954         prior to 1950
New work:
   Appropriated       _
                   .....          ________...     $100, 000    $32, 000      $2, 000      $785            $144, 785
   Cost.......     .....-----------------5, 541     58, 551     70, 220       4, 858     1, 156            144, 785


Other new work data: Estimated additional amount needed to be appro-
  -priated
         for completion of existing project................_............ ................... $45, 855,215
266.            REPORT. OF CHIEF OF ENGINEERS, U. S. ARMY, 1954
                     13. INACTIVE FLOOD-CONTROL PROJECTS

                                                            For last       Cost to June 30, 1954                Estimated
                                                           full report                                           amount
                  Name of project                             see                                               required
                                                            annual          Con-          Operation                to
                                                            report       struction           and                complete
                                                             for'-                       maintenance

1. Washington, D. 0.-and vicnity.            ._     .   1953,          $331,927 ----         __---              $1, 653,,700
2. Harpers Ferry, W. Va. --------------------           1937,. -------           ----------                         484, 500
3. Moorefield, W. Va.t __.i------_-------_--            1941               7 928-----__                            1366,200
4. Waynesboro:Va.--    .   --    --.-.-.--       --     1950 .-             -    -----                 -         13,191,600
5.' Emergencyi ooId-controlworkunder author-'         - 1950         '"-     7-
                                                                               --            -$56,274-           -.
      ity of the Flood Control Act. approved Au-
      gust 18, 1941.. .. .-                     -.-
'6. Snagging and. :clearing under :authority of          1950      -       i                   18, 418
      section 2 of the Flood Control Act applroved
      August 28,' 1937, as amended              _-
7. EmergIetyfbod-control worksmunder authoi-,           113                                  ;311 163-              -
      ity of the flood Control Act approved June
      23, 1947_
8. Small floodcoontrol projects under authority         1953    .   ---. ;136,500                               -       --
      of Section 205 of the Flood Conitrol Act ap-
     provedJune 30, 1948,,as amended.            .
9. Emergency flood-coitrol work under author                  1953                             105 813      -

   . Ity of Section 208 of the Flood Control         Act
     apprpve4 June 30,,1948.....---

1 Cost revised in 1954.
2 Recommended for abandonment in SurveyRtiprt g oPotoma)liver.date                       April30,- 1944,published as
House Document 622, 79th Congress, 2d Session.   ' -
SNo furids available.


                                14. GENERAL INVESTIGATIONS,

   Examinations and surveys. The ;costs of. navigation studies
during the fiscal year was $1,794. The balance unexpended. at
the end of the fiscal year, $153, will be applied during the fiscal
year 1955 for. the completing of survey reports for
and Monroe Creek, Virginia.                           -
                                                             Creek                             13onUm
   No work was performed oin examinations and surveys for
flood control .during the fiscal year
   The additional suim of $7,600 i needed to be appropriated for
the fiscal year 1956 for examination and survey reports.
   An anticipated sum of $13,100 is neede.d to be appropriated
for the fiscal year 1956 for examinations and surveys.
   Collection and study of basic data. For the collection and study
of basic data $1,940 was expended during the year for the prepa-
ration of flood manuals for the Washington District.
   The additional sum of $4,500 is needed to be appropriated for
the fiscal year 1956 for collection and study of basic data-
flood emergency studies.
       15. INSPECTION OF COMPLETED FLOOD CONTROL WORKS
  Approved regulations for operation and maintenance of flood
control works, Part 208 of Title 33, Code of Federal Regulations,
provide for semiannual inspection by the District Engineers of
completed projects which have been transferred to local inter-
ests for operation and maintenance. During the fiscal year 1954
the following inspections of completed flood control works have
been made:
  Savage River Dam, Md.                              An allotment of $2,550 was made dur-
                   FLOOD CONTROL-WASHINGTON, D.C., DISTRICT                                           267
ing the year for scheduling of flood control reservoir operations
at Savage River Dam. Operations during the year consisted of
inspections of the operations and hydrologic network, inspec-
tions to determine compliance with regulations for maintenance
of structures and equipment, and preparation of monthly reports
of operations, at a cost of $2,520. All structures inspected were
found to be in good condition.
   Washington, D. C., and Vicinity. The levee systems in Potomac
Park, which were constructed as part of the Washington, D. C.,
and Vicinity project, were inspected during the year. A section
along the toe of earth levee removed by the Naval Receiving
Station for use as a parking lot was called to the attention of
station officials who have furnished information that restoration
will be completed during the calendar year. All other project
features were found to be in good condition. No costs were
incurred for this work.
   Small flood control projects under authority of Section 205 of
the Flood Control Act approved June 30, 1948, as amended. In-
spections were made to determine the condition of earth levees
and appurtenances constructed under authority of section 205
of the Flood Control Act of June 30, 1948, amended by section
212 of the Flood Control Act of May 17, 1950, in the town of
Bridgewater, Virginia, at the junction of North River and Dry
River, which have previously been transferred to local interests
for operation and maintenance. It was found that maintenance
of the structures has been good. Small damage which has oc-
curred in the levee surface has been brought to the attention of
local interests and prompt attention has been promised. No costs
were incurred for the inspections.
   Emergency flood control work under authority of section 208 of
the Flood Control Act approved June 30, 1948. Inspections were
made to determine the condition of farm levees constructed
under authority of section 208 of the Flood Control Act of June
30, 1948 on the south branch of the Potomac River and tribu-
taries in West Virginia at 32 localities in Grant, Hardy, Hamp-
shire and Pendleton Counties from Romney to Franklin and
including Moorefield and Petersburg. In general, it was found
that maintenance of all structures has been good. In instances
where small damages have occurred the fact has been brought
to the attention of local interests and prompt repairs have been
promised. No costs were incurred for these inspections.
                                      Cost and financial summary

                                              Fiscal year ending June 30                     Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                               1950         1951        1952        1953         1954        prior to 1950
Maintenance:
   Appropriated---...    ------------ ------------ ----------- -----------        $2, 550             $2, 550
    Cost...-----------     --------------------- I---------- -----------------     2,520               2, 520
  IMPROVEMENT OF RIVERS AND HARBORS IN THE
            NORFOLK, VA., DISTRICT

   This district comprises a small portion of southeastern West
Virginia, central and eastern Virginia, and a portion of northern
North Carolina embraced in the west shore drainage basins
tributary to the southern part of Chesapeake Bay south of the
watershed line between the northerly arm of Winter Harbor and
Garden Creek, Va., and the eastern shore drainage basins south
of and including Onancock River, Va.; the drainage tributary to
the Atlantic Ocean from White Creek and Gargathy Inlet, in-
clusive, to the Virginia-North Carolina State line; the Roanoke
River Basin above Weldon, N. C.; the Meherrin River Basin
above Murfreesboro, N. C.; and the Chowan River Basin above
the confluence of the Nottoway and Blackwater Rivers, Va. It
also includes the Virginia portion of the Intracoastal Waterways
between Norfolk, Va., and Beaufort Inlet, N. C., and the portion
of the waterway from Norfolk to the sounds of North Carolina
north of Albemarle Sound.
                                         IMPROVEMENTS

                  Navigation                                          Flood control
                                               Page                                               Page
1. York Spit Channel, Va -...---.....          269 10. Roanoke River Basin, Va. and
2. Thimble Shoal Channel, Va......             270       N. C       --...
                                                                  __...---....   --.-........ .   288
3. James River, Va..........................   272 11. John H. Kerr Reservoir, Roan-
4. Appomattox River, Va_....__.......          274       oke River Basin, Va. and
5. Channel to Newport News, Va..               277       N. C_...................                 290
6. Norfolk Harbor, Va......----------....      278 12. Philpott Reservoir, Roanoke
7. Hampton Roads and the Har-                            River Basin, Va......................    292
     bors of Norfolk and Newport                   13. Gathright Reservoir and Fall-
     News, Va.-collection and                            ing    Spring         Reregulating
     removal of drift-__-..........            283       Dam, James River Basin, Va.              293
8. Atlantic Intracoastal Water-                    14. Inactive flood control projects..          294
     way between Norfolk, Va.                      15. General investigations ...............     294
     and the St. Johns River,
     Fla. (Norfolk District)-----..........    284
9. Inactive navigation projects....            288

                             1. YORK SPIT CHANNEL, VA.
   Location. York Spit Channel lies in the lower Chesapeake Bay
opposite the mouth of York River and about 20 miles northerly
from Atlantic Ocean at the entrance of Chesapeake Bay. (See
U. S. Coast and Geodetic Survey Chart No. 1222.)
   Previous project. The original project was adopted March 3,
1905. For further details see page 389 of the Annual Report for
1932.
   Existing project. This provides for a channel approximately
6.77 miles long, 1,000 feet wide, and 39 feet deep at mean low water
between the contours of that depth in Chesapeake Bay opposite
York Spit. Under ordinary conditions the mean tidal range is 2.5
feet and extreme 3.3 feet. The extremes of irregular fluctuation,
due to combined wind and tides, referred to mean low water, are
minus 2 feet and plus 9.5 feet.
                                                                                          269
270              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  The cost for new work for the completed project was $673,410.
The latest (1950) approved estimate for annual cost of mainte-
nance is $36,000.
  The existing project was authorized by the following River and
Harbor Acts:

       Acts                          Work authorized                                           Documents

Mar. 3, 1905      A channel 35 feet deep and 600 feet wide.        _             H. Doec. 186, 57th Cong., 2d sess.
Mar. 4, 1913      Channel width increased to 1,000 feet-___,.-----               H. Doec. 1190, 62d Cong., 3d sess.
July 3, 1930      Channel depth increased to 37 feet                             H. Doec. 29, 71st Cong., 1st sess.
Mar. 2, 1945      Channel depth increased to 39 feet ----------------            In accordance with report on file in
                                                                                    office of the Chief of Engineers
                                                                                    dated June 30, 1942. (Contains
                                                                                    latest published map.)


   Local cooperation. None required.
   Terminal facilities. York Spit Channel is an access channel
between lower and upper Chesapeake Bay. No terminal facilities
are located on the project.
   Operations and results during fiscal year. Maintenance condi-
tion and operation studies with Government plant and hired labor
were made during the year at a cost of $6,286.
   Condition at end of fiscal year. Construction of the existing
project was commenced in 1932 and continued intermittently to
February 1952 when the project was completed. The controlling
depths as ascertained in March, 1954, were 38.5 feet in midchannel
and 36.5 feet along the edges. Depths are referred to mean low
water.
   The total cost of the existing project prior to fiscal year 1942 was
included in the project for Baltimore Harbor and Channels, Md.
Since that date, the total cost to June 30, 1954 was $1,527,592, of
which $673,410 was for new work and $854,182 for maintenance.
                                        Cost and financial summary

                                                Fiscal year ending June 30                                Total to June
                                                                                                         30, 1954, includ-
                                                                                                          ing fiscal years
                                 1950         1951        1952               1953             1954        prior to 19501
New work:
                 --------
      Appropriated..            $400, 000   $300, 000    $109, 448 -------------.....------                      $673, 410
   Cost-- _-_------_-_           401, 613     94, 368      97, 324 ---         .673,                                  410
Maintenance:
      Appropriated.....              650       5, 500      12, 500-,        ------            $10,000             858,691
           .
      Cost__--    ----...          1,140       3, 613       1, 771           $11,821            6, 286            854, 182
  1   Costs prior to fiscal year 1942 are included in the project "Baltimore Harbor and Channels".


                            2. THIMBLE SHOAL CHANNEL, VA.
  Location. Thimble Shoal Channel lies in the lower portion of
Chesapeake Bay between Hampton Roads and the ocean, and is 20
miles northeast of the center of Norfolk Harbor, extending south-
easterly 11 miles from a point 11/4 miles east of Thimble Shoal
Lighthouse toward the entrance to Chesapeake Bay. (See U. S.
Coast and Geodetic Survey Chart No. 1222.)
  Previous projects. Adopted by River and Harbor Act of June
25, 1910. For further details see page 470, Annual Report for
1932.
                RIVERS AND HARBORS--NORFOLK, VA., DISTRICT                                               271
   Existing project. This provides for dredging a channel 11 miles
long, 750 feet wide, and 40 feet deep at mean low water. Under or-
dinary conditions the mean tidal range is 2.6 feet and the extremes
2 and 3 feet. The extremes of irregular fluctuation, due to com-
bined wind and tides, referred to mean low water, are -2 feet and
 +9.5 feet.
    The cost for new work, for the completed project, was $2,283,772,
exclusive of amounts expended on previous projects. The latest
 (1952) approved estimate of cost of annual maintenance is $26,500.
   The existing project was adopted by the River and Harbor Act of
August 8, 1917 (H. Doc. 140, 65th Cong., 1st sess.). The latest
published map is in House Document No. 551, 61st Congress, 2d
session.
   Recommended modifications of project. On February 19, 1954,
the Chief of Engineers recommended that the project be modified
to provide for an increase in the project width of the channel from
750 to 1,000 feet to a project depth of 40 feet, with no change in
alignment; and auxiliary channels 450 feet wide and 32 feet deep
adjoining each side of the recommended 1,000-foot channel
throughout its full length, at an estimated cost of $1,292,000 for
new work and $183,000 annually for maintenance in addition to
that now required. This recommendation is printed in Senate
Document No. 122, 83d Congress, second session.
   Local cooperation. None required.
   Terminal facilities. This project serves as an entrance channel
to Hampton Roads. For a description of terminal facilities, see
this heading under "Norfolk Harbor, Va.," "Channel to Newport
News, Va." etc.
   Operations and results during fiscal year. Maintenance condi-
tion and operation studies with Government plant and hired labor
were made during the year at a cost of $7,495.
   Condition at end of fiscal year. Construction of the existing
project was commenced in December 1917, and continued intermit-
tently to June 1929, when the work was completed. The control-
ling depths, as ascertained in April 1954, were 40 feet in mid-
channel and 38.9 feet along the edges. Depths are referred to
mean low water.
   The total cost of the existing project to June 30, 1954, was $3,-
406,816, of which $2,283,772 was for new work and $1,123,044 for
maintenance.
                                      Cost and financial summary

                                                    Fiscal year ending June 30                 Total to June
                                                                                              30, 1954, includ-
                                                                                               ing fiscal years
                               1950             1951            1952      1953      1954       prior to 19501

New work:
   Appropriated--------         --- ------------ ------------ ------------ ------          -----   $2, 617, 381
   Cost-----------------                  -------------------                                       2, 617, 381
Maintenance:
   Appropriated--------...      $5, 000          $1, 063        $9, 000      $624   $7, 500         1, 123, 048
   Cost ----------------         4, 350           3, 215         5, 507     4,117    7,495          1,123, 044

  1 Includes $333,609 for new work for previous projects.
272               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                         3. JAMES RIVER, VA.
   Location. This river is formed by the junction of the Cow-
pasture and Jackson Rivers in Botetourt County, Va., flows easterly
340 miles, and empties into Hampton Roads at Newport News, Va.
 (See U. S. Coast and Geodetic Survey Charts Nos. 529, 530, and
531.)
   Previous projects. Adopted by River and Harbor Act of July
11, 1870. For further details see page 1797 of Annual Report for
1915, and page 461 of the Annual Report for 1938.
   Existing project. This provides for a channel 25 feet deep and
300 feet wide from the mouth to Hopewell, 69.2 miles; thence 25
feet deep and 200 feet wide, following the cutoff route between
Hopewell and the Richmond deepwater terminal, 17.2 miles; thence
a channel 18 feet deep and 200 feet wide from the deepwater ter-
minal to the Richmond lock, 4.4 miles, and the removal of the
obstruction in Richmond Harbor known as Trigg cofferdam; for a
turning basin 200 feet wide, 600 feet long and 18 feet deep in
Richmond Harbor; and for maintenance of the turning basin at
Richmond Deepwater Terminal to a depth of 25 feet.
   Depths of channels are referred to mean low water. The total
length of channel included in the project is 90.8 miles, which is the
navigable section.
   The mean tidal ranges under ordinary conditions for different
parts of the river are as follows: Mouth, 2.7 feet; Jamestown, 1.85
feet; City Point, 2.8 feet; Dutch Gap, 3.5 feet; Richmond, 3.9 feet.
Following are the extreme ranges under ordinary conditions at the
same localities: Mouth, 2.1 to 3 feet; Jamestown, 1.6 to 2.3 feet;
City Point, 2.3 to 3.2 feet; Dutch Gap 2.9 to 3.9 feet; Richmond,
3.2 to 4.2 feet. The ordinary fluctuation of stage at Richmond, due
to floods, are 6 to 12 feet above mean low water. The extreme
fluctuations are 16 to 32 feet. The flood heights below Richmond
diminish rapidly, the extreme, according to available information,
being about 11 feet lower at Dutch Gap, 14 miles below, and 17 to
18 feet lower 20 miles below.
   The cost for new work, for the completed project was $6,796,240,
exclusive of the amount expended on previous projects. The
latest (1952) approved estimate of cost for annual maintenance
is $334,500.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                           Work authorized                                     Documents
July    5, 1884   Channel 22 feet deep from mouth to Richmond and             S. Ex. Doc. 147, 47th Cong., 1st
                   construction of spur and training dikes.            sess.
June 13,1902      Extension of improvement to Richmond lock gate.... 1
Mar.    3, 1905   Forming a turning basin by widening channel at              }H. Doc. 234, 56th Cong., 1st sess.
                    Richmond.J
July    3,1930    Existing project dimensions_...............   ...   ....    H. Doc. 314, 71st Cong., 2d sess.'
Aug. 26, 1937     Removal of the Trigg cofferdam_..-----------               - Rivers and Harbors Committee
                                                                                                      1
                                                                                Doc. 68, 74th Cong., 1st sess.
Mar. 2,1945       Turning basin in Richmond Harbor__.................         H. Doc. 738, 77th Cong., 2d sess.'
May 17, 1950       Maintenance of turning basin at Richmond Deep-             H. Doc. 191, 81st Cong., 1st sess.'
                    water terminal.

1Contains latest published maps.
          RIVERS AND HARBORS-NORFOLK, VA., DISTRICT            273
   Local cooperation. The conditions of local cooperation imposed
by the River and Harbor Acts of July 3, 1930, August 26, 1937,
March 2, 1945 and May 17, 1950, have been fully complied with.
   Terminal facilities. The river's commerce at Richmond is han-
dled at the city-owned terminals, city wharf, and Richmond dock,
and at 14 privately owned wharves located within or in the imme-
diate vicinity of Richmond Harbor. The Richmond deepwater ter-
minal at the head of the 25-foot depth serves oceangoing vessels
and the larger ships engaged in coastwide trade. Below the deep-
water terminal the improvement is served by 42 wharves. The
Richmond terminals and wharves, together with the wharves be-
tween Richmond and the river's mouth, are adequate for the river's
commerce.
   Operations and results during fiscal year. Maintenance dredg-
ing, under one contract, in Richmond Harbor and turning basin, at
Richmond Deepwater Terminal, and in Dancing Point---Swann
Point Shoal Channel was commenced July 31, 1953, and continued
to September 26, 1953, when the work was completed. There were
removed 41,466 cubic yards of material from Richmond Harbor
and turning basin, 60,277 cubic yards of material from the channel
and turning basin at Richmond Deepwater Terminal, and 287,664
cubic yards of material from Dancing Point---Swann Point Chan-
nel, a total of 389,407 cubic yards of material, all place measure-
ment. The cost of the work was $138,810.
   Maintenance condition and operation studies, with Government
plant and hired labor, were made during the year at a cost of
$23,330.
   Miscellaneous inspections and reports and compilation of com-
mercial statistics, with Government plant and hired labor, were
made during the year at a cost of $4,899.
   The total cost of the work for the fiscal year was $167,039, all
for maintenance.
   Condition at end of fiscal year. Construction of the existing
project was commenced in 1884 and continued intermittently
through the various modifications of the project to November 1947,
when the work was completed. Construction of the 25-foot chan-
nel between Hopewell, Va., and the mouth was commenced in
January 1931 and completed in March 1932. Construction of the
cutoffs between Hopewell, Va., and Richmond, Va., was com-
menced in February 1933 and completed in October 1937. The
remainder of the channel between Hopewell and Richmond was
completed in October 1938 with the exception of rock removal
at Falling Creek and between Richmond deepwater terminal and
Richmond which was accomplished between April and November
1947. Construction of the turning basin in Richmond Harbor
was commenced in October 1947 and completed in November 1947.
The controlling depths at mean low water are as follows:
274               REPORT OF CHIEF OF ENGINEERS, U, S. ARMY, 1954


                                                                                Controlling depths

                     Name of channel                                                        Mid-                    Date determined
                                                                         Left             channel       Right
                                                                       outside             for half    outside
                                                                       quarter            ;project     quarter
                                                                        (feet)              width       (feet).
                                                                                            (feet)


Mouth to Hopewell:
  Rocklanding Shoal Channel,
  Tribell Shoal Channel-.-     ...-
                                    ..     ....
                                            ---
                                       ....---
                                                      .-      :.. 25.0
                                                                   22. 7
                                                                         °
                                                                                             -25.0:
                                                                                              24. 0
                                                                                                       :    25.0
                                                                                                            24. 9
                                                                                                                       September 1950.
                                                                                                                       March 1954.
  Goose Hill Channel---,----.---------------                       23. 6                       24. 2        23.0       March 1954.
  Dancing Point-Swann.....----------..-..--       , --- .....      24. 4                       24.1         23.0       March 1954.
Point Channel:
Weyanoke Point Channel-----..._               -.      ...         25.0                      125.0          25.01 April 1948
  Jordon Point-Harrison Bar-Windmill Point Chan-                   20. 5                       23. 4        23. 7      May 1952.
      nel.
    City Point ChanneL..l-----.          - --        ..------      25.0                        25.0 .25.0              August 1949
Hopewell toRichmond Deepwater Terminal.........,                    4. 3                       24.9.      24.2         March 1953.
Richimond Deepwater Termiial toiBnk1on tine dock                 , 16. 4                       17.6:      18:0         March 1950l
Buxton .Line.dock. to a point, 200 feet downstream                  5.0                         7.6       11.0         May 1953.
  from Richmond lock.
A point
  the loer
          20feetIdownstreamn
                  ,      ..
                             from Richmond lock: to-                                           15.0 .,.
                                                                                                     ...               March 1950.



     The head of navigation for boat traffic is at Richmond, Va Navi-
gation: is practicablethroughou t the year
  The total cost of the dxisting project to June 30, 1954, was
$11,161,417, of whichi $6,796;240 was for new Work, representing
$6,212,404 from regular- fnhid s and $583,836 from Public Works
funds, and, $4,365,177, for maintenance, including $8388 applied
:to the removal of shoals 'in Bennetts Creek, Va., under the pro-
visions of section 3 of the River and Harbor Act approved Oc-
tober 17, 1940.
                                              Cost and financial summary

                                                           Fiscal year ending June 30                                    Total to June
                                                                                                                       30, 1954, includ-
                                                                                                                        ing fiscal years
                                       1950             1951          1952                  1953            1954          prior to 19501
New work::
   Appropriated...... ..------------------
                                    ........------------                             -         -----   ---------             $7, 559, 240
   Cost.. .................                                                       "..
                                                                    .7;..............7,                                          559, 240
Maintenance:
   Appropriated--.... .-              $288, 500         $465,157     $248, 500             $136, 142       $385, 000          4, 784, 603
   Cost--.........-----...--------- .393, 723             98, 427     403, 182              170, 755        167,039           4,365, 177

   1 Includes $763,000 for new work for previous projects.

                                       4. APPOMATTOX RIVER, VA.
     Location.              This river rises in Appomattox County, Va., flows
northeasterly 137 miles, and empties into the James River at
Hopewell, Va. The portion under improvement extends from its
mouth to Petersburg, Va., a distance of 111/2 miles, which is the
length of the tidal and navigable reach. (See U. S. Coast and
Geodetic Survey Chart No. 531.)
  Previous projects. None. A survey of the river was made
prior to the adoption of the existing project. For further details,
see page 469, Annual Report for 1938.
  Existing project. This provides for a channel 80 feet wide and
12 feet deep from the mouth of the river to a point 400 feet above
Lieutenant Run; thence 80 feet wide and of such depth, not ex-
                   RIVERS AND HARBORS-NORFOLK, VA., DISTRICT                                           275
ceeding 12 feet, as can be obtained without rock excavation to the
head of navigation at Petersburg; including a basin at the mouth
of Poes Run 200 feet long, 150 feet wide, and 20 feet deep: and a
turning basin at the mouth of Lieutenant Run 500 feet long, 140 to
160 feet wide, and 12 feet deep in the upper 300 feet, the removal
of rock to a depth of 18 feet in the north half of the lower 200 feet,
and removal of soft material to rock in the south half of the lower
200 feet of this basin. All depths are referred to mean low water.
   The project also provides for a dam at Petersburg and the ex-
cavation for a width of from 200 to 300 feet of a diversion channel
connecting the river above the dam with the river at a point 21/2
miles below; for about .1..' miles of levees on the low. grounds
between the navigable and. the diversion channels; for a highway
bridge and a railway bridge across the diversion channel; and for
other .workiincidental to the diversion channel.
   Under ordinary conditions the mean tidal range is 2.9 feet and
the extremes 2.4 and 3,3 feet. There are no records available of
the heights of stage due to ordinary floods. These are estimated
at 6 to 8 feet above mean low water at Petersburg, where the
extremes are from 15.6 feet to 17.1 feet.
   The estimated cost of new work, revised in 1954, is $1,210,000,
which includes the estimated cost (1909) of the diversion channel
and work incidental to its construction, $260,000. The estimated
cost of maintenance (1950) of the navigable channel is $15,000
annually.
   The existing project was authorized by the following river and
harbor acts:

       Acts                         Work authorized                                 Documents
Mar. 3,1871        Channel 12 feet deep at mean high water' and 60 feet Annual Rdport 1874, pt. II, p. 54.
                    wide.
June 13, 1902      Diversion channel and work incidental thereto....... IH. Doc. 139 56 Cong., 2-ses.
Mar. 3,1909        f                                                      and Annual Report, 19601, p. 1467.
June 25,1910        Increasing channel to width of 80 feet and mainte.   H. Doc. 952, 60th Conig., 1st sess.
                    .nance of diversion works.
Jan.    21, 1927   Channel 80 feet wide and 10 feet deep at mean low     H. Doe. 215, 69th Cong., 1st sess.
                     water between mouth and Petersburg.
Mar.     2,1945    Existing project dimensions.---------------------     H. Doc. 223, 76th Cong., 1st sess.
                                                                           (Contains latest published map.)


  Local cooperation. The conditions of local cooperation imposed
by the River and Harbor Act of January 21, 1927, have been fully
complied with.
   The River and Harbor Act of March 2, 1945, in adopting the
existing project dimensions, imposed the conditions that local in-
terest furnish, free of cost to the United States, all lands, ease-
ments and rights-of-way, and spoil disposal areas for the initial
work and for subsequent maintenance as required, and hold and
save the United States free from claims for damages attributable
to construction of the improvement. These conditions have been
fully complied with and approved by the Chief of Engineers on
May 10, 1948. Local interests are required to furnish suitable
spoil-disposal areas for subsequent maintenance.
   Terminal facilities. There are about 2,500 feet of wooden bulk-
head and a shore landing in Petersburg Harbor. There is also a
wooden bulkhead and pier and a shore landing, used for sand and
276                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

gravel loading, located about 3 miles downstream from Peters-
burg. These facilities are privately owned and are considered
adequate for existing commerce.
   Operationsand results during fiscal year. Maintenance condi-
tions and operation studies, with Government plant and hired
labor, were made during the year at a cost of $1,275.
   Condition at end of fiscal year. The existing project was about
83 percent complete at the end of the fiscal year. Construction of
the diversion channel and other work incidental thereto was com-
men-ced in 1904 and continued intermittently to October 1921 when
the work was completed. Construction of the channel 80 feet wide
and 10 feet deep at mean low water was commenced in September
1929 and continued intermittently to January 1931 when the work
was completed.
   The controlling depths at mean low water are as follows:

                                                                                      Controlling
                                                                                    depths: 80 per-
                                                                                    cent of project
                              Name of channel                                       width, 40 per-      Date determined
                                                                                     cent on either
                                                                                     side of center
                                                                                       line (feet)
Mouth to Lieutenant Run-------------------------------------                                   6. 9   November 1945-
                                                                                                       January 1946.
Lieutenant Run to Petersburg, Va............................-----------------------------      7.6    April 1950.
Turning basin at Lieutenant Run .............................                                +0. 3    April 1954.
Basin at Poes Run-------------------------------------------                                   9. 5   April 1950.



   The head of navigation for boat traffic is at Petersburg, Va.
Navigation is practicable throughout the year.
   The work remaining to be done to complete the project consists
of providing a channel 12 feet deep and generally 80 feet wide
from the mouth of the river to the lower end of the turning basin
at Lieutenant Run; a channel 80 feet wide and of such depth, not
exceeding 12 feet, as can be obtained without rock excavation from
the upper end of the turning basin to the head of the existing proj-
ect; extending the existing turning basin to a point 100 feet below
the center line of Lieutenant Run; widening this basin to 160 feet
at the bend at the mouth of the run and to 140 feet at the lower
end; removing all rock lying less than 18 feet below mean low
water in the north half of the lower 200 feet of the basin; remov-
ing soft material in the south half of the lower 200 feet of this
basin to rock; dredging the remainder of the turning basin to a
depth of 12 feet; and dredging a basin 20 feet deep, 150 feet wide,
and 200 feet long at the mouth of Poes Run. Depths are referred
to mean low water.
   The total cost of the existing project to June 30, 1954, was
$1,379,931, of which $847,841 was for new work, including $260,-
000 for the diversion channel and $532,090 for maintenance.
                     RIVERS AND HARBORS-NORFOLK, VA., DISTRICT                                                                   277
                                           Cost and financial summary

                                                   Fiscal year ending June 30                                           Total to June
                                                                                                                        30, 1954, includ-
                                                                                                                        ing fiscal years
                                    1950         1951                 1952                    1953           1954        prior to 19501
New work:
                        -----------............
   Appropriated-------........            -------------------                ----------- ------------                          $870, 341
   Cost....-------- ------------ ------------------------------------------------                                               870, 341
Maintenance:
   Appropriated..-------             $5,000                          ............ $1, 500
                                                --$1,427 ...........-----------                                                  532, 315
   Cost -----------------             3, 573      ----------------............------------..........           1, 275            532, 090

  1 Includes $22,500 for new work for previous projects.
Other new work data: Estimated additional amount needed to be appro-
                                                                     $362, 159
  priated for completion of existing project __..-...-..............................

                            5. CHANNEL TO NEWPORT NEWS, VA.
   Location. This channel lies to the west of the north entrance to
Norfolk Harbor Channel and connects deep water in James River
with Hampton Roads.       (See U. S. Coast and Geodetic Survey
Chart No. 400.)
   Previous projects. Adopted June 13, 1902. For further details,
see page 1797 of Annual Report for 1915, and page 459 of Annual
Report for 1938.
   Existing project. This provides for dredging a channel 40 feet
deep at mean low water, 600 feet wide, increased to 1,000 feet at
the ends, and 31/4 miles long through the shoal north of Middle
Grouiid Light. Under ordinary conditions the mean tidal range
is 2.7 feet and the extremes 2.1 and 3 feet. The extremes of ir-
reg ar fluctuations due to combined wind and tides, referred to
mean low water, are -2 feet and + 9.5_feet.
   The cost for new work, for the completed project, was $1,252,-
262, exclusive of the amount expended on previous projects. The
latest (1952) approved estimate for annual cost of maintenance is
$12,700.
   The existing project was authorized by the following river and
harbor acts:
     Acts                              Work authorized                                                        Documents

June 25, 1910         Channel 35 feet deep and 400 feet wide---------__                            H. Doc. 550, 61st Cong., 2d sess.
Aug. 8,1917           Channel 35 feet deep and 600 feet wide-_----------                           H. Doc. 605, 63d Cong., 2d sess.
                                                                                                    (Contains latest published map.)
Jan. 21, 1927         Existing project dimensions .....--------------------                        H. Doc. 486, 67th Cong., 4th sess.


  Local cooperation. None required.
   Terminal facilities. There are four piers at Newport News,
which are the property of the city, and which are open to general
public use on equal terms. All of the other piers and wharves
served by this improvement are owned by private corporations or
companies. The principal terminal and transfer facilities are
278                    REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

those of the Chesapeake & Ohio Railway Co. and the Newport
News Shipbuilding & Dry Dock Co. There are also at Newport
News a wharf used by steamers of the Eastern Steamship Co. and
a small boat harbor. The facilities are considered adequate for
present commerce.
   Operations and results during fiscal year. Maintenance condi-
tion and operation studies, with Government plant and hired labor,
were made during the year at a cost of $1,956.
   Condition at end of fiscal year. Construction of the existing
project was commenced in March 1929 and continued intermit-
tently to June 1931 when the work was completed. The control-
ling depths, as ascertained in March 1954, were 40 feet in mid-
channel and 40 feet along the edges. Depths are referred to mean
low water.
   The total cost of the existing project to June 30, 1954, was
$1,561,115, of which $1,252,262 was for new work and $308,853,
for maintenance.
                                                   Cost and financial summary

                                                          Fiscal year ending June 30                                Total to June
                                                                                                                   30, 1954, includ-
                                                                                                                    ing fiscal years
                                            1950        1951           1952            1953            1954          prior to 19501


New work:
   Appropriated          -----------.
                                -             ------------ ------------------------                 ------------         $1, 477, 262
   Cost-------------........................-----.......-------------------.....--
                                                                         ......--....------------------------.........    1,477, 262
Maintenance:
    Appropriated_-------_                   $4, 000    -$3,   435       $3, 500         $1, 200 -         -                 321, 733
    Cost..............-----------------..       415           202        1, 918             447           1, 956            321, 353

  1Includes $225,000 for new work and $12,500 for maintenance for previous projects.

                                             6. NORFOLK HARBOR, VA.
  Location. Norfolk, Va., is 187 miles south of Baltimore, Md.,
and 30 miles from the entrance to Chesapeake Bay at Cape Charles
and Cape Henry. The harbor extends from the 40-foot contour in
Hampton Roads to a point 2,500 feet above the Norfolk & Western
Railway bridge over the Southern Branch of the Elizabeth River,
a distance of 17.3 miles. (See U. S. Coast and Geodetic Survey
Charts Nos. 400 and 452.)
  Previous projects. Adopted by River and Harbor Acts of Au-
gust 14, 1876; July 5, 1884; modified June 30, 1885; and by River
and Harbor Acts of September 19, 1890; June 3, 1896; July 7,
1898; June 13, 1902; March 3, 1905; and March 2, 1907. For
further details see page 1795 of Annual Report for 1915, and page
454 of Annual Report for 1938.
  Existing project. This provides for a main channel 40 feet
deep, 750 feet wide, from Hampton Roads to the mouth of Southern
Branch of the Elizabeth River, and 450 feet wide up this branch
to the Belt Line Railroad bridge, a total distance of 13.2 miles,
including an approach and turning area to the same depth of a
         RIVERS AND HARBORS-NORFOLK, VA., DISTRICT             279
maximum width of 830 feet opposite the Norfolk Naval Shipyard,
extending downstream 3,250 feet from the Belt Line Railroad
bridge; thence 35 feet deep, 375 feet wide and 1.0 mile long to the
Virginian Railway bridge; then 35 feet deep, 250 feet wide, and 3.1
miles long to a point 1,900 feet above the Norfolk & Western Rail-
way bridge, with adequate widening of the channel at the bends,
a turning basin 35 feet deep and 600 feet by 600 feet at the up-
stream end, making a total distance of 17.3 miles; a channel in
the Eastern Branch, 25 feet deep, 500 feet wide, and 1.09 miles
long, from the 40-foot channel at the mouth to the Norfolk &
Western Railway bridge, including within its limits, for a distance
about 1,000 feet above the mouth, a channel 30 feet deep and 300
feet wide to a point opposite the terminal of the Imperial Tobacco
Co. in Berkley; thence 25 feet deep, 300 feet wide, and 0.55 mile
long, to the Campostella Bridge; thence 25 feet deep, 200 feet
wide, and 1.2 miles long to the Virginian Railway bridge; and for
maintenance at a depth of 25 feet of the existing turning basin ap-
proximately 51/ acres in extent at the head of the existing project
just below the Virginian Railway bridge; a channel in the Western
Branch, between the 40-foot channel at the mouth and a point
about 3,000 feet above the West Norfolk Highway bridge, a dis-
tance of about 1.72 miles; 24 feet deep, 300 feet wide, 0.78 mile,
and 200 feet wide, 0.37 mile to the bridge; thence 18 feet deep, 150
feet wide, 0.57 mile; a channel in Scotts Creek between the 40-foot
channel at the mouth and a point 100 feet above the Atlantic Coast
Line Railroad bridge (about 0.73 mile upstream), 12 feet deep
and 100 feet wide; anchorage areas on the west side of the 40-foot
channel opposite Lambert Point and south of Craney Island aggre-
gating 171 acres, consisting of: One anchorage space 1,200 by
2,400 by 30 feet deep; one anchorage divided into two spaces, each
1,200 by 1,200 by 22 feet deep; one space 900 by 1,900 by 16 feet
deep; and another anchorage of 45 acres, 12 feet deep, near Pin-
ner Point; and a trapezoidal-shaped disposal area of about 2,500
acres of flats adjacent to and north of Craney Island, enclosed by
stone-faced levees of sand pumped from existing deposits adja-
cent to and within the disposal area, three sluiceways in the west-
erly levee, two rehandling basins, each 200 by 800 feet, 40 feet
deep, spaced 500 feet apart, an approach and exit area 3,800 feet
long, 600 feet wide, and 28 feet deep connecting the rehandling
basins with the 40-foot channel. All depths are referred to mean
low water.
   The mean tidal range is 2.7 feet and the extreme 3 feet. The ex-
tremes of irregular fluctuations, due to combined effect of tides
and wind, referred to mean low water, are -- 2 feet and +9.62 feet.
   The estimate of cost for new work, revised in 1954, exclusive of
amounts expended on previous projects, is $16,683,000. The latest
 (1950) approved estimate for annual cost of maintenance is $943,-
500.
   The existing project was authorized by the following River and
Harbor Acts:
280                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


       Acts                             Work authorized                                          Documents
                           HAMPTON ROADS AND ELIZABETH RIVER

Mar. 2,1907        A channel 30 feet deep to the navy yard----------..............   H. Doc. 381, 59th Cong., 1st sess.
June 25,1910       Depth of 35 feet to the navy yard_..................              H. Doc. 551, 61st Cong, 2d sess.
Aug. 8,1917        Depth of 40 feet and width of 750 feet to the mouth               H. Doe. 140, 65th Cong., 1st sess.
                     of the Southern Branch.

                                       SOUTHERN BRANCH

June 25,1910       For a channel with depths of 22 and 25 feet-...........           H. Doc. 551, 61st Cong., 2d sess.
Aug. 8,1917        Depth of 40 feet and width of 450 feet from the mouth             H. Doc. 140, 65th Cong., 1st sess.
                    to the Belt Line RR. bridge.
Mar. 3,1925        Channel 30 feet deep and 375 feet wide to the Vir-                H. Doc. 226, 68th Cong., 1st sess.
                    ginian Ry. bridge, thence 25 feet deep and gener-
                    ally 200 feet wide to the Norfolk & Western Ry.
                    bridge.
Aug. 30, 19352     Depth of 25 feet and width of 200 feet from the Nor-              H. Doc. 182, 73d Cong., 2d sess.
                    folk & Western Ry. bridge to a point 2,500 feet
                    above, with a turning basin 500 feet square.
June 30,1948       Approach and turning area 40 feet deep and a maxi-                H. Doc. 545, 80th Cong., 2d sess.'
                    mum width of 830 feet opposite Norfolk Naval
                    Shipyard, thence a channel 35 feet deep and 375
                    and 250 feet wide to a point 1,900 feet above the
                    Norfolk & Western Ry. bridge and a turning basin
                    35 feet deep and 600 feet by 600 feet at the upstream
                    end.
                                       EASTERN BRANCH

July 5,1884        Improvement of the Eastern Branch .................               Annual Report 1885, p. 1015.
Mar. 2,1907
    Do.....
                   Width of 500 feet and depths of 25 feet and 22 feet..       --    H. Doc. 373, 59th Cong., 1st sess.
                   Removal of shoals at the mouth_----------...........              Specified in act.
Mar. 3, 1925       Depth of 25 feet and width of 200 feet from the Nor-              H. Doc. 226, 68th Cong., 1st sess.
                     folk & Western Ry. bridge to the Virginian Ry.
                     bridge.
July     3, 1930   The 30-foot channel to a point opposite the terminal              H. Doc. 37, 71st Cong., 1st sess.
                     of the Imperial Tobacco Co. in Berkley.
Mar. 2,1945        Depth of 25 feet and width of 300 feet from the Nor-              H. Doc. 224, 76th Cong., 1st sess.
                     folk & Western Ry. bridge to the Campostella
                     bridge.
                                       WESTERN BRANCH

Mar. 4,1913        Channel with depth of 24 feet and widths of 300 and               H. Doc. 566, 62d Cong., 2d sess.
                    200 feet to the West Norfolk highway bridge.
July     3, 1930    For the 18-foot channel to a point about 3,000 feet              H. Doc. 265, 70th Cong., 1st sess.'
                    above the West Norfolk highway bridge.

                                          SCOTTS CREEK

       Do .....    For the existing project dimensions.--        ...--------.-       H. Doc. 189, 70th Cong., 1st sess.

                                          ANCHORAGES

June 25, 1910      A 30-foot anchorage at Lambert Point .------- ---                 H. Doc. 551, 61st Cong., 2d sess.
Aug. 8, 1917       A 12-foot anchorage at Pinner Point and a 35-foot                 H. Doc. 605, 63d Cong., 2d sess.'
                     anchorage opposite Lambert Point.
July     3, 1930   Existing project dimensions of anchorage opposite                 H. Doc. 143, 70th Cong., 1st sess.
                     Lambert Point and elimination of the 35-foot
                     anchorage authorized by the act of Aug. 8, 1917.
Oct.    17, 1940   Extension of present 30-foot anchorage to afford 2                H. Doc. 683, 76th Cong., 3d sess.
                     anchorage spaces 22 feet deep and 1 anchorage space
                     16 feet deep.
                                         DISPOSAL AREA

July 24, 1946      A trapezoidal-shaped area of about 2,500 acres of flats           H. Doc. 563, 79th Cong., 2d sess.'
                    adjacent to and north of Craney Island, including
                    sluiceways, rehandling basins, and approach and
                    exit areas.

1 Contains latest published maps.
2 Included in Emergency Relief Administration program May 28, 1935.

   Recommended modifications of project. On February 19, 1954,
the Chief of Engineers recommended that the project be modified
to provide for (1) an increase in the project width of the channel
from 750 to 1,500 feet to a project depth of 40 feet, from the 40-
foot contour in Hampton Roads up Elizabeth River to a point just
south of the Hampton Roads Port of Embarkation piers, a total
distance of approximately 33,700 feet, such widening to be accom-
plished on the southeasterly and easterly sides thereof; at an
          RIVERS AND HARBORS-NORFOLK, VA., DISTRICT             281
estimated cost to the United States of $3,543,000 for new work
and $231,000 annually for maintenance in addition to that now
required, and (2) the elimination of the 30-foot, 22-foot, and 16-
foot anchorages presently located south of Craney Island and op-
posite Lambert Pbint, and in lieu thereof, the construction of an
anchorage 38 feet deep and 1,500 feet square, an anchorage 35
feet deep and 1,500 feet square, an anchorage 20 feet deep, 1,000
feet wide and 3,000 feet long, opposite Lambert Point and south of
Craney Island; at an estimated cost to the United States of $1,-
129,000 for new work and $53,000 annually for maintenance.
This recommendation is printed in Senate Document No. 122, 83d
Congress, second session.
   Local cooperation. The River and Harbor Act of July 3, 1930,
in adopting the project for a channel in the Eastern Branch, 30
feet deep and 300 feet wide, extending from the 40-foot channel to
a point opposite the terminal of the Imperial Tobacco Co., imposed
the condition that local interests give assurance satisfactory to the
Secretary of War and the Chief of Engineers that they will provide
and maintain, without cost to the United States, a branch channel
of equal depth to the tobacco terminal. This condition has not been
complied with.
   All prior requirements and conditions imposed by the River and
Harbor Acts of August 30, 1935, October 17, 1940, July 24, 1946,
and June 30, 1948, have been complied with.
   Terminal facilities. The terminal facilities within the limits of
this improvement include about 227 wharves, piers, etc., with an
aggregate length available for wharfage purposes of about 32
miles. It is considered that the facilities are adequate for the
present commerce of the port.
   Operationsand results during fiscal year. New work on Craney
Island Disposal Area, consisting of preparation of general design
memoranda, and plans and specifications, with Government plant
and hired labor, in progress at the beginning of the fiscal year was
continued intermittently to the end of the year. Bids were adver-
tised and a contract awarded for the initial phase of the Disposal
Area consisting of construction of an access road, sand levee, rock
riprap, and sluiceways. The cost of the preliminary work was
$113,273. No costs were incurred on the contract.
   Maintenance dredging, by contract, in the Eastern Branch of
the Elizabeth River, 25-foot channel to remove the shoal at the site
of the old Berkley highway bridge, was commenced May 12, 1954,
and continued to May 31, 1954, when the work was suspended to
make adjustments to utilities within the area. Work was not
resumed prior to the end of the fiscal year. There were removed
25,000 cubic yards of material, place measurement. The cost of
the work was $35,623.
   Maintenance condition and operation studies, with Government
plant and hired labor, were made during the year at a cost of
$30,474.
   Miscellaneous inspections and reports and compilation of com-
mercial statistics, with Government plant and hired labor, were
made during the year at a cost of $16,653.
   The total cost of the work for the fiscal year was $196,023, of
282             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

which $113,273 was for.new work and $82,750 for maintenance.
   Condition at end of fiscal year. The existing project was about
48 percent completer at the end of the fiscal year. Construction of
the 40-foot channel from Hampton Roads to the Belt Line Rail-
road bridge was commenced in July 1917 and continued intermit-
tently to May 1931, when the work was completed. Construction
of the Southern Branch 35-foot channel was commenced in May
1950 and completed in March 1951, except for dredging at the
Norfolk-Portsmouth Belt Line Bridge. Construction of the East-
ern Branch 25-foot channel was commenced in February 1928,
and completed in June 1928. A modification to widen a portion of
this channel was commenced in August 1948 and completed in
September 1950. Construction of the Western Branch 24-foot
channel was completed in 1914. Construction of the Western
Branch 18-foot channel was commenced in April 1931 and com-
pleted in May 1931. Construction of Scotts Creek was commenced
in September 1931 =and completed in December 1931. Construc-
tion of Pinner Point anchorage was completed in 1939. Construc-
tion of the Craney Island 30-foot anchorage was commenced in
January 1931 and completed in May 1931. The controlling depths
at mean low water are as follows:
                                                                 Controlling depths
                                                                         Mid-
                  Name of channel                             Left      channel        Right     Date determined
                                                            outside     for half      outside
                                                            quarter     project       quarter
                                                             (feet)      width         (feet)
                                                                         (feet)

40-foot channel:
     Hampton Roads to junction of branches ..-    ..    -      37. 5        37. 5        35. 0   March 1954.
     Junction of Branches to Belt Line RR. bridge-__           40.0         40.0         40.0    May 1951.
Southern Branch, Belt Line RR. bridge to point                 33. 1        33. 2        34. 0   February 1953.
  2, 500 feet above Norfolk & Western Ry. bridge.
Eastern Branch:
    Junction of branches to Norfolk & Western Ry.              25. 0        25.0         25.0    May 1951.
      bridge.
    Norfolk & Western Ry. bridge to Virginian Ry.              24. 5        24. 2        24. 4         Do.
     bridge.
Western Branch:
   Mouth to West Norfolk highway bridge-....                    13.-9       15. 7        16. 6   January 1949.
   West Norfolk highway bridge to point 3,000 feet              18. 0       18.0         18.0          Do.
     upstream.
Scotts Creek.-----..-------   -----------------------           6. 9         7. 4 I       7. 9   December 1948.


   The work remaining to be done to complete the project consists
of dredging a channel 30 feet deep and 300 feet wide in the Eastern
Branch between the 40-foot channel at the mouth and a point op-
posite the terminal of the Imperial Tobacco Co., a distance of about
1,000 feet; completion of dredging three additional anchorage
basins south of the present Craney Island 30-foot anchorage (two
anchorage spaces each, 1,200 by 1,200 feet to a depth of 22 feet,
and one anchorage space, 900 by 1,900 feet to a depth of 16 feet) ;
construction of a trapezoidal-shaped disposal area of about 2,500
acres on the flats adjacent to and north of Craney Island, includ-
ing sluiceways, rehandling basins, approach and exit areas, etc.;
and dredging at the Norfolk-Portsmouth Belt Line IBridge when
the present structure is replaced by a new bridge under the Tru-
man-Hobbs Act. Depths are referred to mean low water.
                      RIVERS AND HARBORS--NORFOLK, VA., DISTRICT                                                                                 283
  The total cost of the existing project to June 30, 1954, was
$14,623,212, of which $7,890,627 was regular funds and $49,978,
Emergency Relief funds, a total of $7,940,605 for new work; and
$6,682,607 regular funds for maintenance. In addition there were
costs of $23,936 of contributed funds for new work.
                                                    Cost and financial summary

                                                                 Fiscal year ending June 30                                         Total to June
                                                                                                                                   30, 1954, includ-
                                                                                                                                    ing fiscal years
                                            1950               1951              1952              1953               1954         prior to 1950 1 2

New work:
     Appropriated...             ..--------$554, 123         $767, 000       -$131,     835        $35, 000         $682, 000             $11, 094, 836
   Cost ----------------                    273,521           965, 813                4,324         11,200           113,273               10, 502, 309
Maintenance:
     Appropriated        --------           130, 000           290, 044          344, 553          127, 244           113, 000               6, 791, 420
     Cost----------------                   204,894            284, 571          311,006           174, 395            82,750                6,754,646


   21 Includes $2,561,704 for new work and $72.039 for maintenance for previous projects.
     In addition $23,936 for new work was expended from contributed funds.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954....--------------.....................                                                   $72,467
    Appropriated for succeeding fiscal year ending June 30, 1955............-----.. 3,000,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955 ..........................-----------------..-----------------------....................................................... 3,072,467
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project .._.......-..--------------                                                                                      5, 149, 868

       7. HAMPTON ROADS AND THE HARBORS OF NORFOLK AND
      NEWPORT NEWS, VA.-COLLECTION AND REMOVAL OF DRIFT

   Location. Hampton Roads is a natural harbor located 300 miles
south of New York and 180 miles south of Washington, D. C. Its
principal tributaries are James River, affording a natural deep
harbor at Newport News, Va.; the Elizabeth River, with its South-
ern, Eastern, and Western Branches, providing harbors for Nor-
folk and Portsmouth, Va.; and Hampton Creek serving the harbor
at Hampton, Va. (See U. S. Coast and Geodetic Survey Charts
Nos. 400 and 452.)
   Existing project. This provides for the collection and removal
of drift in Hampton Roads and its tributary waters and authorizes
the Secretary of the Army to allot such amounts as may be neces-
sary for the work from appropriations for the maintenance and
improvement of existing river and harbor works or from other
available appropriations, and that this work shall be carried on
as a separate and distinct project. It is wholly a work of mainte-
nance. The purpose of the work is to afford relief from variable
conditions of obstruction, and no advance estimate of the amount
of work required and its proper cost can be made.
   The existing project was authorized by the River and Harbor
Act of May 17, 1950, as specified in the act.
   Terminal facilities. For a description of the terminal facilities
on this project see this heading under "Norfolk Harbor" and
 "Channel to Newport News, Va."
   Operations and results during fiscal year. Maintenance opera-
  tions, consisting of collection and removal of drift material in the
284            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

harbors of Norfolk and Newport News, Va., and their tributaries,
with Government plant and hired labor, was carried on during the
year, as a cost of $17,496.
  Condition at end of fiscal year. The existing project is one of
continuous maintenance for which no percentage of completion
exists. Operations under the existing project were commenced
July 1, 1950. Costs for the removal of drift previous to that time
were carried under the project "Norfolk Harbor, Va."
  The total cost of the existing project to June 30, 1954, was
$62,376, all for maintenance.
                                   Cost and financial summary

                                           Fiscal year ending June 30                    Total to June
                                                                                        30, 1954, includ-
                                                                                        ing fiscal years
                            1950          1951        1952        1953       1954        priorto 1950

Maintenance:
   Appropriated _________    ..   _____   $20, 000    $15, 000    $11, 684   $20, 000            $66, 684
   Cost--   - -_       ____--__            14, 515     17,169      13, 196    17, 496             62, 376



8.ATLANTIC INTRACOASTAL WATERWAY BETWEEN NORFOLK, VA.,
     AND THE ST. JOHNS RIVER, FLA. (NORFOLK DISTRICT)

   Location. The improvement described herein consists of two in-
land water routes approximately paralleling the Atlantic coast
south of Norfolk, Va., and located (1) between a point in the
Southern Branch of Elizabeth River, Va., 2,500 feet above the
Norfolk & Western Railway bridge and the Virginia-North Caro-
lina State line in North Landing River, a distance of 27.2 miles,
and (2) between the mouth of Deep Creek, Va., and the mouth of
Pasquotank River, N. C., a distance of 64.6 miles. These routes
are shown on United States Coast and Geodetic Survey Charts
Nos. 452, 1227, 829, and 830.
   Previous projects. Partial projects were adopted by River and
Harbors Acts of March 3, 1873, June 18, 1878, March 3, 1879, June
14, 1880, March 3, 1881, and September 19, 1890. For further
details see page 497, Annual Report for 1932, and page 476, An-
nual Report for 1938.
   Existing project. This provides for a channel 12 feet deep at
mean low water and 90 feet to 250 feet wide following the Southern
Branch of Elizabeth River, 5.2 miles, the Virginia Land Cut, 8.3
miles, and North Landing River, 13.7 miles; the construction of a
tidal guard lock at Great Bridge, Va.; and for the protection of
the canal property in the vicinity of the lock against flooding by
storm tides through construction of necessary dikes and appurte-
nant works. It also provides for channels 10 feet deep at mean
low water and 80 feet to 100 feet wide in Deep Creek, 3.1 miles,
Turners Cut, 4.3 miles, and Pasquotank River, 35.1 miles; main-
taining Dismal Swamp Canal, 22.1 miles, to a depth of about 9
feet mean canal level over a width of 50 feet; the protection of
banks in Turners Cut with sheet piling, and cutting certain sharp
points in Pasquotank River to shorten its course.
                     RIVERS AND HARBORS-NORFOLK, VA., DISTRICT                                                          285
               Data relative to the completed locks included in the project

                                                                 Depth on
                                           Dimensions            miter sills
Miles
from                                          Great-                                                      Year
Nor-                Location          Width     est                                   Character of      opened       Actual
folk,                                    of   length                                  foundation        to navi-      cost
Va.                                  cham- avail-       Lift Upper Lower                                gation
                                        ber    able      (feet) (feet) (feet)
                                       (feet) for full
                                              width
                                               (feet)
  12.4     Albemarle and                  75      600     2.7    (1)     (1)         Piles in sand       1932      $499, 913.00
            ChesapeakeCanal                                                            and shells.
            (Great Bridge,
            Va.).
  10. 7    Dismal Swamp Ca-               52      300      12      12          12    Natural earth       1940       348, 878. 83
            nal (Deep Creek,                                                           with cutoff
            Va.).                                                                      walls.
  33.1     Dismal Swamp Ca-               52      300      12      12          13            ........
                                                                                    ..... do--------     1941       372, 556. 40
            nal (South Mills,
            N. C.).

  1 16 feet at mean low water.


   The Southern Branch of Elizabeth River and the Deep Creek
sections of the two routes are tidal, the mean range being about
2.7 feet with extreme of -2 and +9.6 feet. The remaining sec-
tions are non-tidal with fluctuations of 1 to 2 feet in level due to
winds.
   The estimate of cost for new work, made in 1950, was $3,435,300.
The latest (1952) approved estimate of cost for annual mainte-
nance is $544,300, including $405,500 for operating and care.
   The existing project was authorized by the following river and
harbor acts:
       Acts                       "     Work authorized                                           Documents

Mar. 3, 1899         Existing project dimensions and original route, water-  H. Doc. 317, 54th Cong., 1st sess.,
                      way from Norfolk, Va., to sounds of North Carolina.      and Annual Report, 1896, p. 1086;
                                                                               H. Doc. 131, 55th Cong., 3d sess.,
                                                                               and Annual Report, 1899, p. 1485.
July 25, 1912        Original route of the Norfolk-Beaufort Inlet section __ H. Doc. 391, 62d Cong., 2d sess.
    Do.......        Purchase of Chesapeake & Albemarle Co. Canal-...        H. Doc. 589, 62d Cong., 2d sess.
Mar. 3, 1925         Purchase of Lake Drummond Canal (Dismal Swamp           Rivers and Harbors Committee
                       Canal).                                                 Doc. 5, 67th Cong., 2d sess. 1
July      3, 1930    Construction of a tidal lock at Great Bridge at a limit S. Doc. 23, 71st Cong., 1st sess.
                       of cost not to exceed $500,000.
June 26,19342        Operating and care of the works of improvement pro- H. Doc. 117, 76th Cong., 1st sess.
                       vided for with funds from War Department appro-
                       priations for rivers and harbors.
Mar.      2,1945     Construction of dikes for protection of canal property H. Doc. 117, 76th Cong., 1st sess.
                       against floodtides_

  1 Contains latest published map, both routes.
  2 Permanent Appropriations Repeal Act.

  Local cooperation. None required.
  Terminal facilities. Terminal facilities serving the two water
routes at the northern terminus are described in the report for
Norfolk Harbor, Va. South of Norfolk there are 3 piers, 15
wharves, 6 landings, 5 marine railways, and 3 bulkheads serving
these routes. The landings are publicly owned and are open to the
public without charge. The remaining facilities are privately
owned and are open to the public at a nominal charge. These
facilities are considered adequate for existing commerce.
  Operations and results during fiscal year. Preliminary engi-
286      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

neering for maintenance dredging and for repairs to floor of
South Mills Bridge, with Government plant and hired labor,
were made during the year at a cost of $1,568.
   Maintenance snagging and bank trimming operations on both
waterways, with the U.S. derrick boat Roanoke, were carried on
during the year at a cost of $28,124.
   Installation of emergency power generating equipment for
Great Bridge lock, Great Bridge bridge, and North Landing
bridge, with Government plant and hired labor, was made during
the year at a cost of $8,583.
   Replacement of floor of Deep Creek bridge with steel grid
flooring, with Government plant and hired labor, was accom-
plished during the year at a cost of $7,439.
   Maintenance condition and operation studies, with Govern-
ment plant and hired labor, were made during the year at a cost
of $17,687.
   Miscellaneous inspections and reports and compilations of
commercial statistics, with Government plant and hired labor,
were made during the year at a cost of $5,955.
   Operation and care of the locks, bridges, spillways, wharves,
canal plant, grounds, roads, etc., was carried on during the year
as required at a cost of $229,716.
   The total cost of the work for the fiscal year was $299,072, all
for maintenance.
   Condition at end of fiscal year. The existing project was about
99 percent complete at the end of the fiscal year. Construction
of the Southern Branch of the Elizabeth River and North Land-
ing River portions of the project was commenced in 1915 and
continued intermittently to May 1920, when the work was com-
pleted. The Albemarle & Chesapeake Canal was acquired by
the United States from the Albemarle & Chesapeake Canal Co.
on April 30, 1913, for $500,000. Construction of the Deep Creek,
Turners Cut, and Pasquotank River portions of the project was
commenced in August 1899, and continued intermittently to June
1902, when the work was completed. The Dismal Swamp Canal
was acquired by the United States from the Lake Drummond
Canal & Water Co. on March 30, 1929, for $500,000.
   A tidal guard lock in the Albemarle & Chesapeake Canal at
Great Bridge, Va., was completed in 1932. Locks at Deep Creek,
Va., and South Mills, N. C., on the Dismal Swamp Canal were
built in 1940 and 1941, respectively.     (See table in paragraph
"Existing project.") The locks are in good condition.
   The controlling depths at the end of the fiscal year are as
follows:
                  RIVERS AND HARBORS--NORFOLK, VA., DISTRICT                                                             287
                                                                                  Controlling
                                                                                depths: 80 per-
                                                                                cent of project
                            Name of channel                                     width, 40 per-            Date determined
                                                                                cent on either
                                                                                 side of center
                                                                                   line (feet)
Southern Branch of the Elizabeth River, Va-....-........                --...            110. 5      July 1952.
Virginia Cut, Va...--               ----------------------
                                              __-----..     ___   ----                   2 12. 0     July 1948.
North Landing River, Va- .............-......-....
                                          -                            ...                 12. 0     May-Aug. 1953.
Deep Creek, Va----...............________          ..
                                              ______....          .____                   1 8. 6     October 1953.
Dismal Swamp Canal-......______.__._____........____                                      4 7. 4     January 1954.
Turners Cut, N. C...........-..__________..__        ..___.     .______   .5                8. 4     May-June 1951.
Pasquotank River, N. C-__ __ -              -____________-----____ __                     5 9. 4     January-February
                                                                                                       1947.
  1 Depths are referred to mean low water.
  2 Depths are referred to Virginia Cut datum.
  s Depths are referred to North Landing River datum.
  4 Depths are referred to canal datum.
  5 Depths are referred to ordinary low water.


   The work remaining to be done to complete the project con-
sists of protection to canal property in the vicinity of the lock
at Great Bridge, Va., against flooding by storm tides, through
construction of necessary dikes and appurtenant works.
   The total cost of the existing project to June 30, 1954, was
$12,342,702, of which $3,396,276 (including $1 million for the
purchase of the Albemarle & Chesapeake Canal and the Dismal
Swamp Canal) was for new work; $4,173,561 for maintenance;
and $4,772,865 for operation and care.
                                           Cost and financial summary

                                                    Fiscal year ending June 30                                 Total to June
                                                                                                              30, 1954, includ-
                                                                                                              ing fiscal years
                                    1950           1951           1952            1953             1954        prior to 1950 1


New work:
   Appropriated........  ---------- ------------------------                     ------------ ------------         '$3, 688, 372
   Cost------............------------ ------------------------------------------------                               3, 688, 372
Maintenance:
   Appropriated------......--. $777, 350        $453, 456          $297, 432          $247, 577 $331, 218            9, 055, 116
   Cost.........-.------         469, 435        604,688            418,040            309, 693  299,072             8, 999,230

  1 Includes $292,096 for new work and $52,804 for maintenance for previous projects.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project.............. ..-........................ .......... $39, 000




         Sig 10-287-318
 288               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                9. INACTIVE NAVIGATION PROJECTS

                                                              For last      Cost to June 30, 1954           Estimated
                                                             full report                                     amount
                     Name of project                             see                                        required
                                                              Annual          Con-           Operation          to
                                                               Report      struction            and         complete
                                                                for-                        maintenance
1.   Onancock River, Va.' 2-------_-___-___            _         1951       $187, 914          $100, 443      (3)
2.   Nandua Creek, Va. -------------                        - 1950             6, 988             2,988       (3)
3.   Occohannock Creek,  4  Va.'------------------1951                        13, 859            36, 723        $90, 100
4.   Quinby Creek, Va. ____-           l -____-   -________ -1953             23, 276     --------------        108, 700
5.   Little Machipongo River, Va.'------- __              -      1950         15, 000            12, 596      (')
6.   Oyster Channel, Va.'
                        4    ---------------------                1952         54, 600             6, 936      (S)
7.   Kings Creek, Va.     --    -         -     -                1950                                           122, 000
8.   Cape Charles City Harbor,
                           4        Va.' 5-                      1950         648, 381            80,716         207, 000
9.   Winter Harbor, Va. -__------------_____                    1950                                            239, 000
10.   Horn Harbor, Va.4l__      _________-_____                  1950          11, 487            21,472       (')
11.   Davis Creek, Va. - -________
                             1 _                                 1950                                            103, 000
12.   Mattaponi River, Va.' ---             --       -_          1950          83, 836           142, 519        160, 400
13.   Pamunkey River, Va.' __________________-_                  1951          31, 376           154, 346          35, 600
14.                              -
      York River, Va.-_ __-___-_______________          _        1941         180, 904           173, 355        128, 000
15.   Channel connecting York River, Va. with
        Back Creek to Slaight's Wharf 1 7- ..-..                 1950          14,   855          19, 828      (S)
16.   Little River (Creek), Va.- _ _ ____                        1952         168,   623         104,547       (S)
17.   Deep Creek (City of Warwick), Va.4_ ...                  -1951           25,   637          57, 178       199, 400
18.   Pagan River, Va.' 9--__-______________
                              1                         _        1950          51,   425         256, 414      (3)
19.   Nansemond River, Va. o             _              _        1952         167,   477         213, 045      (3)
20.   Portsmouth Harbor, Va. Channel to Nanse-
        mond Ordnance Depot 1-.    ....          -    --..       1947         165, 566           66, 162       ()
21.   Hampton Creek, Va.' 11   ______"_-_-___-_                  1950         249, 206           14, 129       (')
22.   Channel from Phoebus, Va. to deep water in
        Hampton Roads 112                                        1944          11, 500           11, 750       (S)
23.   Willoughby Channel, Va.'------------------                 1953           8, 500           17, 522       (s)
24.   Newport News Creek, Va.'-----------------                  1953         135, 600            5, 937       (S)
25.   Lafayette River, Va.     --------------------- 1950                      12, 048            1, 000       (3)
26.   Knobbs Creek, N. C.1_..___-.._____....-..                  1950          80, 500           25, 000       (')
27.   Blackwater River, Va.' 1S______ ____------____             1953          36, 044           77, 905        302, 000

   1 Channels adequate for commerce.
    2 Includes $33,549 for new work and $24,754 for maintenance for previous projects.
   3 Completed.
    4 Construction funds to complete project not available until later date.
    5 Includes $445,291 military funds expended for new work on adopted project and $83,041, military funds
expended for new work on wharf and bulkhead.
    6 Includes $51,249 for new work and $60,440 for maintenance for previous projects.
    SIn addition $2,500 for new work was expended from contributed funds.
    8 Federal funds expended by U. S. Navy for new work. In addition $16,995       expended from funds con-
tributed by the Pennsylvania Railroad Co. for new work.
    9 Includes $20,671 for new work for previous projects.
   10Includes $30,000 for new work and $7,000 for maintenance for previous projects.
   11Includes $12,000 for new work for previous projects and $62,969 expended from contributed funds for
new work.
   12 In addition $1,200 for new wors was expended from contributed funds.
   isIncludes $14,000 for new work for previous projects.


                       10. ROANOKE RIVER BASIN, VA. AND N. C.
   Location. The works covered by this project consist of a series
of dams and reservoirs in the Roanoke River and its tributaries
in Virginia and North Carolina, within a radius of 100 miles
from Danville,, Va.
   Existing project. The Flood Control Act approved December
22, 1944, approved the general plan for the comprehensive de-
velopment of the Roanoke River Basin for flood control and
other purposes as set forth in House Document 650, 78th Con-
gress, 2d session, and authorized the construction of the John H.
Kerr Reservoir (formerly known as the Buggs Island Reservoir)
on the Roanoke River in Virginia and North Carolina, and the
Philpott Reservoir on the Smith River in Virginia as the initial
step of this development.
   Following is a list of the dams and reservoirs included in the
comprehensive plan. The estimates of cost as given were revised
in 1954.
                                                                                    Dams and reservoirs

                                                                Distance                                                                                                               Estimated cost
                                                                 above                                                                 Reservoir          Power de-
             Name                        Nearest city           mouth 1                 Height of dam and type                          capacity         velopment
                                                                 (miles)                                                               (acre-feet)       (kilowatts)       Con-          Land and
                                                                                                                                                                        struction        damages 2          Total 3

John H. Kerr,  Va. and N. C.4__ Boydton, Va ...  ------             178. 7    144 feet, concrete gravity and earth fill                  2,   808, 000       204,000    61, 900, 000      25, 250, 000    87, 150, 000
Philpott, Va.
             4
                -------------      Bassett, Va _________            336. 2    220 feet, concrete gravity 5..           ......--------------   249, 800        14, 000   12, 180, 000       1, 160, 000    13, 340, 000
Gaston, Va. and N. C...._____
Roanoke Rapids, N. C.6
                                   Roanoke Rapids, N. C.
                                   _    ____do_____________
                                                                    144. 9
                                                                    137. 0
                                                                              108 feet, concrete gravity and earth fill-_
                                                                              75 feet, concrete gravity_
                                                                                                                                              432, 000
                                                                                                                                               59, 300
                                                                                                                                                              54, 000
                                                                                                                                                              83, 700
                                                                                                                                                                        27, 000, 000
                                                                                                                                                                        31, 300, 000
                                                                                                                                                                                           3, 500, 000
                                                                                                                                                                                              800, 000
                                                                                                                                                                                                          30, 500, 000
                                                                                                                                                                                                          32, 100, 000
                                                                                                                                                                                                                         O
                                                                                                                                                                                                                         0
                                                                                                                                                                                                                         O
Smith Mountain, Va ._________ Altavista, Va .......                 314. 2    244 feet, concrete gravity ---------------                      825, 000        41, 000   28, 000, 000       3, 800, 000    31, 800, 000
Leesville, Va____________________do..                               293. 7    95 feet, concrete gravity and earth fill___                      76, 900        20, 000    9, 100, 000       1, 000, 000    10, 100, 000   0
Taber, Va____-. ___-_____.. __________do_______                     275. O0   54 feet, concrete gravity                    _                   34, 000        12, 000    8, 000, 000       1, 700, 000     9, 700, 000
Melrose, Va-___                    Brookneal, Va_________           262. 9    110 feet, concrete gravity and earth fill_                      120, 000        43,000    17, 700, 000       6, 000, 000   723, 700, 000
Randolph, Va___________       __ Chase City, Va      -.-..          227.8     147 feet, concrete gravity and earth fill--                     305, 000        48, 000   22, 100, 000       4, 700,000     26, 800, 000
Stuart, Va. and N. C -             Spray, N. C ...-----------       297. 2    138 feet, earth fill_____________            ____               163, 000        15, 000    9, 000, 000       1, 100, 000    10, 100, 000
                                                                                                                                                                                                                         0
Schoolfield, Va. and N. C . -      Danville, Va ..-----         -   265. 9    126 feet, concrete gravity and earth fill__                     248, 000        80, 000   27, 800, 000       6, 400, 000    34, 200, 000   O

  1 Mouth of Roanoke River at Albemarle Sound.                                                            5 Authorizing legislation provided for earth dam; concrete, gravity dam constructed.
  2 Includes highway, railroad, and utilities relocation.                                                 6 Based on modified plan developed in fiscal year 1949.
  3 Exclusive of transmission lines.
                                                                                                                                                                                                                         O
                                                                                                          7 Includes cost of earth dam on Whipping Creek, diversion conduit, power canal, power-
  4 Details of these project items are given in individual reports.                                     house, etc.
                                                                                                                                                                                                                         O




                                                                                                                                                                                                                         H
                                                                                                                                                                                                                         CDl
290      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Local cooperation. None required.
   John H. Kerr and Philpott Reservoirs are the only projects in
the comprehensive plan that have been authorized for construc-
tion in accordance with the above authorization, and individual
reports on the two reservoirs are given in the following pages.
All operations previously reported under the heading, "Roanoke
River Basin, Va. and N. C.," for those two projects are now con-
tained in the individual reports, and previous costs and expendi-
tures have also been transferred to those reports.

  11. JOHN H. KERR RESERVOIR, ROANOKE RIVER BASIN, VA.
                        AND N. C.
   Location. The site for the John H. Kerr Dam is on the Roanoke
River, about 178.7 river miles above the mouth. It is in Mecklen-
burg County, Va., 20.3 miles downstream from Clarksville, Va.,
18 miles upstream from the Virginia-North Carolina State line,
and 80 miles southwest of Richmond, Va. At the elevation of
the top of gates, the reservoir will extend upstream on the Roa-
noke River 56 miles and on the Dan River 34 miles.
   Existing project. This project provides for the construction of
a concrete gravity dam with wing and saddle dikes on the right
and left banks, with a total length of approximately 22,285 feet.
The main dam consists of a nonoverflow concrete section on the
right bank 629 feet long, a concrete spillway section 1,092 feet
long, a concrete power intake section 614 feet long, and a con-
crete nonoverflow section on the left bank 450 feet long. The
right bank earth wing and saddle dikes total 9,050 feet in length
and the left bank wing and saddle dikes total 10,450 feet in
length. The maximum height of the concrete section is 144 feet
above bedrock and the earthfill dikes vary in height to a maxi-
mum of 45 feet. At the elevation of the top of gates, the dam
provides a total storage capacity of 2,808,000 acre-feet, of which
1,278,000 acre-feet is flood storage; 1,046,000 acre-feet, power
drawdown; and 484,000 acre-feet in dead storage below the sur-
face of the minimum power pool. The reservoir will be operated
as a unit of a coordinated system of reservoirs in the Roanoke
River Basin for the control of floods, the generation of hydro-
electric power, the regulation of low water flow for the abate-
ment of pollution, and for other purposes. The power installa-
tion is 204,000 kilowatts.
   The estimate of cost, revised in 1954, is $61,900,000 for con-
struction and $25,250,000 for lands and damages, including the
relocation of highways, railroads, and utilities, a total of $87,-
150,000 for new work.
   The existing project was authorized by the Flood Control Act
approved December 22, 1944, which approved the general plan
for the comprehensive development of the Roanoke River Basin
for flood control and other purposes as set forth in House Docu-
ment 650, 78th Congress, 2d session. The latest published map
is printed in the project document.
   Local cooperation. None required.
   Operationsand results during fiscal year. Operations, by hired
labor, consisted of land acquisition activities and preparation of
                         FLOOD CONTROL-NORFOLK, VA., DISTRICT                                                                         291
contract plans and specifications for the construction of the
project. The acceptance of options and filing of condemnation
proceedings on an additional 137 acres of land were accom-
plished. Seven relocation agreements relating to utilities,, rail-
roads, and highways were completed. One hundred and eight
outleases were processed. Planning for recreation and other
land uses and for reservoir regulation was continued during the
year.
   Operations by contract were continued for completion of the
radio communication system. Supply contracts for furnishing
flow meters, outdoor metering equipment, and carrier current
equipment have been completed. Four highway and railroad
relocations were completed.
   Contracts were continued for construction of the powerhouse
and switchyard. Contracts were initiated for construction of
two outpost points to include a boathouse, garage and storage
building, an administration building, and a comfort station.
Purchase of permanent operating equipment items was con-
tinued. A reservoir ditching program was initiated by hired
labor.
   Operation and maintenance of the project for flood control
and production of power was continued throughout the year.
All generating units were available for power production in
December 1953.
   The total cost of the work for the fiscal year was $2,234,008,
of which $1,784,004 was for new work and $450,004 for opera-
tion and maintenance.
   Condition at end of fiscal year. Construction of the project
was initiated in February 1946 and the project as a whole is
complete except for several minor supply contracts, reservoir
management facilities, and construction of recreational facilities
and resolution of claims against the Government, and judgments
in real estate condemnation cases. Production of power is under-
way and the project is providing flood protection.
   The total cost of the existing project to June 30, 1954, was
$84,971,974 of which $84,396,356 was for new work and $575,618
for operation and maintenance.
                                                Cost and financial summary

                                                            Fiscal year ending June 30                                    Total to June
                                                                                                                         30, 1954, includ-
                                                                                                                         ing fiscal years
                                         1950             1951             1952              1953            1954          priorto 1950
New work:
     Appropriated ......              . 800, 000 $25, 500, 000 $17, 000, 000
                                    $15,                                                  $7, 806, 000     $555, 200           $85, 761, 200
     Cost_    -                      16, 182, 126 19, 144, 021 19, 168, 522               14, 783, 565    1, 784, 004           84, 396, 356
Maintenance:
     Appropriated                __       _             __ -------
                                                      _--                                    125, 614        454, 600                580, 214
           .
     Cost-----------             ------------ ----------------                    -----      125, 614        450,004                 575,618


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-..-.                                     ...............                   $861, 853
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955 ....                     -----------------------------------------                                                861,853
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project------........--...................................---------------------------....................... 1,388,800
292       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

      12. PHILPOTT RESERVOIR, ROANOKE         RIVER BASIN, VA.
    Location. The site for the proposed Philpott Dam is on Smith
River, Va., 44.3 miles above its junction with the Dan River near
Leaksville, N. C., and 35 miles upstream from the Virginia-North
Carolina State line. It is in Franklin and Henry Counties, 34 air-
miles south of Roanoke, Va. At spillway crest elevation, the reser-
voir will extend upstream about 16 miles.
    Existing project. This project provides for the construction of
a concrete gravity dam 892 feet long with a maximum height of
220 feet. The dam consists of a nonoverflow concrete section on
the right bank 280 feet long, a concrete power intake section 92
feet long, an ungated spillway section 120 feet long, and a concrete
nonoverflow section on the left bank 400 feet long. The power-
house, located at the toe of the dam, has a total installation of
14,000 kilowatts.
    At the elevation of the maximum flood control pool, the reservoir
has a storage capacity of 249,800 acre-feet, of which 82,400 acre-
feet is reserved for the control of floods, 111,100 acre-feet for the
development of hydroelectric power, and 56,300 acre-feet is dead
storage. The reservoir will be operated as a unit of a coordinated
reservoir system for the control of floods in the Roanoke River
Basin, the generation of hydroelectric power, the regulations of
low water flow for the abatement of pollution, and for other
purposes.
   The estimate of Federal cost, revised in 1954, is $12,180,000 for
construction and $1,160,000 for lands and damages, including
highway, and other relocations, a total of $13,340,000 for new
work.
   The existing project was authorized by the Flood Control Act
approved December 22, 1944, which approved the general plan for
the comprehensive development of the Roanoke River Basin for
flood control and other purposes as set forth in House Document
650, 78th Congress, 2d session. The latest published map is printed
in the project document.
   Local cooperation. None required.
   Operations and results during fiscal year. Operations, by hired
labor, consisted of preparation of contract plans and specifications
for the construction of portions of the project and land acquisition
activities.
   Construction of the powerhouse was completed. Construction of
Buildings, Grounds and Utilities and procurement of Permanent
Operating Equipment was continued throughout the year. A
negotiated settlement was made with the State of Virginia for re-
location of Highway No. 623 and Highway No. 785. A contract
for radio communication equipment was completed.
   Operation and maintenance of the project was continued
throughout the year and production of power was initiated.
   The cost of the work for the fiscal year was $351,157, of which
$206,790 was for new work, and $144,367 for operation and main-
tenance.
   Condition at end of fiscal year. Construction of the project
was initiated in March 1948 and the project as a whole is complete
                    FLOOD CONTROL--NORFOLK, VA., DISTRICT                                                   293
except for some items of work under Buildings, Grounds, and
Utilities and Permanent Operating Equipment and cleanup work.
The entire reservoir area has been acquired with the exception of
2 tracts. Production of power has been initiated and the project
is providing flood protection.
   The total cost of the existing project to June 30, 1954, was
$13,420,833, of which $13,207,047 was for new work, and $212,923
for operation and maintenance.
                                       Cost and financial summary

                                               Fiscal year ending June 30                         Total to June
                                                   _30,                                              1954, includ-
                                                                                                  ing fiscal years
                               1950          1951            1952         1953         1954        priorto 1950
New work:
   Appropriated ....
                   -.       $2,500,000    $5, 235, 000    $2, 705, 000   $300, 000 ------------       $13,340,000
                      _ _
   Cost_---------------___ 3, 135, 142 5,363, 381 2,111, 791 1,279, 160               $206,790         13, 207, 047
Maintenance:
   Appropriated _ _ __ ____________.   ........          --
                                        ______ ............     69, 386                144, 400            213, 786
   Cost______--------.   .....
                            _.......     ............
                                                    ............          68, 556      144, 367            212, 923


Other new work data:
                                                                      $115, 657
    Unobligated balance, fiscal year ending June 30, 1954-------......................
    Unobligated balances available for succeeding fiscal year ending
       June 30, 1955                       ..
                                   .........
                              -........                              .............
                                                         ..----------................     115,657
                                                                                .....-.........

           13. GATHRIGHT RESERVOIR AND FALLING SPRING
            REREGULATING DAM, JAMES RIVER BASIN, VA.

   Location. The sites of the proposed Gathright and Falling
Spring Dams are on the Jackson River, a tributary of the James
River, at miles 43.4 and 35.1, respectively. The Gathright dam site
is located in the reach of the Jackson River known as the Gorge,
about 19 miles upstream from Covington, Va. The Falling Spring
dam site is located about 11 miles upstream from Covington and 1
mile south of the community of Falling Spring, Va. Both dam
sites are in Alleghany County. At the elevation of the top of
gates, Gathright Reservoir will extend upstream about 15 miles.
 (See Falling Spring and Mountain Grove, Va.-W. Va., quadrangles
of the U. S. Geological Survey.)
   Existing project. This project provides for the construction of
the Gathright Dam and the Falling Spring Reregulating Dam on
the Jackson River. The Gathright Dam will be a rockfill dam with
impervious earth core having a maximum height of 248 feet above
streambed and a crest length of 800 feet with a gated side-channel
concrete spillway. At the elevation of the top of gates, the dam
will provide a total storage capacity of 417,000 acre-feet, of which
110,000 acre-feet will be flood storage; 264,000 acre-feet, power
drawdown; and 43,000 acre-feet, dead storage. The powerplant
will have an installed capacity of 34,000 kilowatts. The variable
flow from this power installation will be reregulated by the Falling
Spring Dam, which will be a low, gravity-type, concrete structure,
with an earth embankment at the right abutment. The Falling
Spring Dam will have a maximum height of 64 feet and a crest
length of 850 feet, of which 640 feet will be concrete and 210 feet
will be earth fill. The storage at spillway crest elevation will be
294            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

4,700 acre-feet, of which 4,000 acre-feet will be available for
streamflow regulation.
   The estimate of Federal cost for the project, including both dams
and reservoirs, revised in 1954, is $24,840,000 for construction and
$2,460,000 for lands and damages, including highway, railroad, and
utility relocation, a total of $27,300,000 for new work.
   The project, as set forth in House Document 207, 80th Congress,
1st session, was authorized by the Flood Control Act approved July
24, 1946. The latest published map is printed in the project docu-
ment.
   Local cooperation. None required.
   Operations and results during fiscal year. New work on design
memorandum in progress at the beginning of the fiscal year was
continued intermittently throughout the year. Work was sus-
pended in October 1953 except for consolidation of records due to
the marginal economics of the project as authorized. The cost of
the work for the fiscal year was $53,256, all for new work.
   Condition at end of fiscal year. Advanced planning on the proj-
ect has been suspended due to the marginal economics of the proj-
ect as determined by design memorandum submitted to date. Ap-
proximately 10 percent of all planning for the project has been
completed.
   The total cost of the existing project to June 30, 1954, was
$98,851, all for new work.
                                   Cost and financial summary

                                           Fiscal year ending June 30                               Total to June
                                                                                                   30, 1954, includ-
                                                                                                   ing fiscal years
                             1950         1951         1952             1953            1954         prior to 1950
New work:
   Appropriated------------------     -----------------      -   .     $130, 000      -$27, 000            $103, 000
   Cost----------      ------------------------------------              45, 595         53, 256                98, 851

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 .......           $2,460
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955---------------------------------...         --------     2,460
    Estimated additional amount needed to be appropriated for com-
                                                                       27, 197, 000
      pletion of existing project-----...--.......................................

                 14.   INACTIVE         FLOOD CONTROL                         PROJECTS

                                                   For last           Cost to June 30, 1954           Estimated
                                                  full report                                          amount
                Name of project                       see                                              required
                                                   annual              Con-           Operation            to
                                                    report           struction         and             complete
                                                     for-                          maintenance

Snagging and clearing under authority of sec. 2      1950             $1, 000. 00 -                        (1)
  of the Flood Control Act approved Aug. 28,
  1937, as amended.

1 Completed
                          15. GENERAL INVESTIGATIONS
  Examinations and surveys. The total cost and expenditure of
examinations and surveys during the fiscal year was $1,232. The
unexpended balance for examinations and surveys on June 30,
1954, in the amount of $211, and an estimate of additional funds
           FLOOD CONTROL--NORFOLK, VA., DISTRICT              295
in the amount of $5,000, a total of $5,211, can be applied during
fiscal year 1955 to payment of expenses to be incurred under this
heading.
   Collection and study of basic data. The total cost and expendi-
ture of collection and study of basic data during the fiscal year
was $986. The unexpended balance on June 30, 1954, in the
amount of $2,446, and an estimate of additional funds in the
amount of $2,000, a total of $4,446, can be applied during fiscal
year 1955 to payment of expenses under this heading.
   The additional sum of $68,100 is needed to be appropriated
for fiscal year 1956, of which $59,100 can be applied to examina-
tions and surveys and $9,000 to the collection and study of basic
data.
  IMPROVEMENT OF RIVERS AND HARBORS IN THE
          WILMINGTON, N. C., DISTRICT

   This district comprises central and eastern North Carolina
embraced in the drainage basins tributary to the Atlantic Ocean
from the southern boundary of Virginia to Shallotte River, in-
clusive, with the exception of the Roanoke River Basin above
Weldon, N. C.; the Meherrin River Basin above Murfreesboro,
N. C.; and the Chowan River Basin above the confluence of the
Nottaway and Blackwater Rivers. It includes the portions of the
Atlantic Intracoastal Waterway from the northern boundary of
North Carolina to Little River, S. C., and the portion of the
Waterway from Norfolk, Va., to the Sounds of North Carolina,
south of the north shore of Albemarle Sound.
                                          IMPROVEMENTS

                   Navigation _                                  Navigation-Continued
                                                 Page                                          Page
1. Atlantic Intracoastal Water-                         6. Cape Fear River, N. C., above
     way between Norfolk, Va.,                               Wilmington .      ............    308
     and the St. Johns River, Fla.                      7. Wilmington Harbor, N. C .... __.    310
     (Wilmington district) .......      ______   297    8. Inactive navigation projects ....   313
2. Roanoke River, N. C__........ ......          301
3. Manteo          (Shallowbag) Bay,
     N . C.......______..... ___
                              ........ . ....    303                  Flood control
4. Channel from Pamlico Sound
     to Avon, N. C......-....-............       305 9. Inactive flood-control projects__      314
5. Morehead City Harbor, N. C..                                                  .... .. .
                                                 306 10. General investigations .-..           314

1. ATLANTIC INTRACOASTAL WATERWAY BETWEEN NORFOLK,
VA., AND THE ST. JOHNS RIVER, FLA. (WILMINGTON DISTRICT)
  Location. This waterway is a sea-level route through coastal
sounds and marine marshes, approximately paralleling the At-
lantic Coast between Norfolk, Va., and St. Johns River, Fla.
(See U. S. Coast and Geodetic Survey Charts Nos. 830 to 842,
inclusive.)
   The section within the Wilmington district begins at the Vir-
ginia-North Carolina State line and extends generally southerly
to Beaufort, thence southwestward to Cape Fear River, and
thence westward to Little River, S. C., 308 statute miles.
   Previous projects. Adopted by River and Harbor Acts of July
4, 1836; March 3, 1837; July 7, 1838; June 18, 1878; March 3,
1879; June 14, 1880; March 3, 1881; August 2, 1882; August 5,
1886; September 19, 1890; March 3, 1905; June 25, 1910; and
August 8, 1917. For further details, see page 1803 of Annual Re-
port for 1915; pages 585, 587, and 589 of Annual Report for 1917;
page 522 of Annual Report for 1926; page 497 of Annual Report
for 1932; and pages 476 and 523 of Annual Report for 1938.
  Existing project. This provides for a waterway 12 feet deep at
mean low water, with bottom widths varying from 90 feet in land
cuts to 300 feet in open waters; for the construction, operation,
and maintenance of suitable bridges; for a tidal lock in the land
cut near the Cape Fear River; for a channel 12 feet deep at mean
                                                                                      297
298      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

low water and 90 feet wide on the bottom in New River between the
Intracoastal Waterway and the Atlantic Coast Line Railroad bridge
at Jacksonville, N. C., 21 miles, and a basin at Jacksonville of the
same depth and varying in width; for a side channel 12 feet deep
and 90 feet wide to a turning basin of the same depth, 200 feet
wide and 350 feet long, opposite the principal wharves at Swans-
boro; for an entrance channel 6 feet deep and 90 feet wide at New
River Inlet, with connecting channel of same dimensions to the
Intracoastal Waterway near the mouth of New River; for six
mooring basins at various locations along the waterway; for a
channel 14 feet deep and 400 feet wide across the ocean bar at
Masonboro Inlet, thence 12 feet deep and 90 feet wide to the chan-
nel of the Intracoastal Waterway at Wrightsville by way of Banks
and Motte Channels; a turning basin 15 feet deep having a maxi-
mum width of 300 feet and length of 700 feet on the east side of
Banks Channel near Masonboro Inlet, with three 15-pile dolphins
therein; for a jetty on each side of Masonboro Inlet extending to
the 14-foot depth in the ocean; for a yacht basin 230 feet wide,
450 feet long, and 12 feet deep near the town of Southport, con-
nected with the waterway by a suitable channel of the same depth;
and for salt-water-intrusion preventive measures in the vicinity
of Fairfield, N. C., as follows: Construction of a pumping plant
and a dam, with control gates and appurtenant works on Fairfield
Canal near the Intracoastal Waterway; restoration and enlarge-
ment where necessary of Boundary Canal from the vicinity of
Swindell Canal to the vicinity of Baum Canal, together with
appurtenant works necessary to cut off inflow from other areas;
and construction of dams with 30-inch automatic floodgates across
Swindell, Florida, Burris, and Baum Canals near Mattamuskeet
Lake.
   That portion of the waterway north of the mouth of Neuse River
is nontidal; variation in the water surface, due to winds, seldom
exceeds 2 feet above or below mean stage. In the section between
Beaufort and Cape Fear River the tidal range varies from 31/ feet
at the inlets to 1 foot at points between. The tidal range for New
River varies from 31/ feet at New River Inlet to 1 foot at the head
of the marshes, and nothing at Tar Landing, 31 miles above. The
mean range of tide in the section from Cape Fear River, N. C., to
Little River, S. C., varies between 4.7 feet in Cape Fear River, 4
feet at intermediate inlets, and 2 feet at points midway between
inlets.*
   The estimate of cost for new work, revised in 1954, exclusive of
amounts expended on previous projects, is $10,338,000, exclusive of
jetties at Masonboro Inlet and the tidal lock; $11,928,000, includ-
ing the jetties; and $13,678,000, including the jetties and tidal
lock. The latest 1954 approved estimate for annual cost of main-
tenance is $472,100, which includes $95,000 for operating and care
of five highway bridges.
   The existing project was authorized by the following River and
Harbor Acts:
           RIVERS AND HARBORS-WILMINGTON, N.C., DISTRICT                                                   299
    Acts                         Work authorized                                        Documents
                I                                  _                    I_


July 25, 1912 Original route of the Norfolk-Beaufort Inlet section ._    H. Doc. 391, 62d Cong., 2d sess.
    Do....... Purchase of canal_...................... ............      H. Doc. 589, 62d Cong., 2d sess.
Aug. 8,1917 Change in route; following changes approved by               H. Doc. 1478, 63d Cong., 3d sess.,
                Secretary of War, Apr. 14, 1919:                          and H. Doc. 1136, 64th Cong., 1st
                    Albemarle Sound-Pamlico Sound section:                 sess.'
                       Changed from "Alligator River-Rose Bay
                         route" to "Alligator River-Pungo River
                         route."
                    Pamlico Sound-Neuse River section:
                       Changed from "Pamlico Sound-Brant Shoal-
                         Neuse River route" to "Goose Creek-Bay
                         River route."
    Do....... A 3-foot channel 100 feet wide fromBeaufort to Swans-          H. Doc. 1775, 64th Cong., 2d sess.
                boro, thence 40 feet wide to Jacksonville.
July 18, 1918 Alligator River-Pungo River route (proposed land               Approved by Secretary of War,
               cut connecting the rivers): Changed from a straight            May 15, 1919.
               line to a bent line approaching nearer the town of
                Fairfield, N. C.
Jan. 21, 1927 A 12-foot channel 90 feet wide from Beaufort to Cape           H. Doc. 450, 69th Cong., 1st sess.
                Fear River, N. C.
July 3, 1930 A waterway 8 feet deep and 75 feet wide from Cape               H. Doc. 41, 71st Cong., 1st sess.
                Fear River to Winyah Bay.
Mar. 4, 19332 Construction of a suitable bridge near Fairfield, N. C.        Rivers and Harbors Committee
                                                                               Doec. 5, 72d Cong., 1st sess.
June 26,19343 Operating and care of the works of improvement pro-
                vided for with funds from War Department appro-
                priations for rivers and harbors.
Aug. 30, 1935 A 10-foot channel 90 feet wide in New River from the           H. Doc. 67, 74th Cong., 1st sess.'
                Inland Waterway to Jacksonville.
Aug. 26,1937 Increasing dimensions of waterway to 12 feet deep               Rivers and Harbors Committee
                and 90 feet wide.                                              Doc. 6, 75th Cong., 1st sess.
   Do....... A 12-foot side channel 90 feet wide to Swansboro.....           Rivers and Harbors Committee
                                                                               Doec. 16, 75th Cong., 1st sess.'
June 20, 1938 To provide a yacht basin near Southport, 12 feet               H. Doc. 549, 75th Cong., 3d sess.1
                deep, 230 feet wide, and 450 feet long, with connect-
                ing channel.
   Do....... A 6-foot channel 90 feet wide from New River Inlet              H. Doc. 691, 75th Cong., 3d sess.'
                to the Inland Waterway.
Mar. 2, 1945 Six mooring basins-..................---..-.---..--.            H. Doc. 660, 76th Cong., 3d sess.'
   Do....... An 8-foot channel 90 feet wide from waterway to                 H. Doc. 346, 77th Cong., 1st sess.1
                Masonboro Inlet.
June 30, 1948 A 12-foot channel in New River ......................          H. Doc. 421, 80th Cong., 1st sess.'
May 17, 1950 Vicinity of Fairfield, drainage.....................            H. Doe. 723, 80th Cong., 2d sess.'
   Do....... Masonboro Inlet and connecting channels...........              H. Doc. 341, 81st Cong., 1st sess.'

  1Contains latest published maps.
  2 Public, No. 433, 72d Cong.
  s Permanent appropriations repeal act.


  Recommended modifications of project. To provide a side chan-
nel to Peltier Creek, west of Morehead City, the Chief of Engineers,
July 28, 1949, recommended that the project be modified to provide
for a channel 12 feet deep, 90 feet wide, and about 1,850 feet long
extending from the 12-foot-depth curve in the Intracoastal Water-
way in Bogue Sound into Peltier Creek, with a basin 12 feet deep,
200 feet wide, and 600 feet long at the inner end, all at an estimated
cost of $32,000 for construction, subject to certain conditions of
local cooperation (H. Doc. 379, 81st Cong., 1st sess.).
   Local cooperation. Complied with, except for the following:
   a. Channel in New River (H. Doc. 421, 80th Cong., 1st sess.),
which requires that local interests give assurances satisfactory
to the Secretary of the Army that they will furnish, free of cost
to the United States, all lands, easements, rights-of-way, and
suitable areas for disposal of dredged material during construc-
tion and for subsequent maintenance, as and when needed; hold
and save the United States free from damages due to the con-
struction works and subsequent maintenance, including damages
to oyster beds, and provide adequate terminal facilities at Jack-
sonville, open to all on equal terms.
300      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   b. Vicinity of Fairfield (H. Doc. 723, 80th Cong., 2d sess.),
which requires that local interests provide, without cost to the
United States, all lands, easements, and rights-of-way necessary
for construction, maintenance, and operation of the project; hold
and save the United States free from damage due to the construc-
tion works, and from all past damage in the area herein under
consideration, which may have been caused by salt-water in-
trusion as a result of construction of the land cut of the Intra-
coastal Waterway; obtain and hold rights-of-way to present canals
involved in the improvement, including the extinguishment of all
present claims of rights, title, and interest to any of the canals;
construct all necessary bridges and culverts for roads, and con-
struct, enlarge, and clean all canals and ditches necessary for the
efficient operation of the project; and maintain and operate the
works after completion.      Local interests, including the Hyde
County Board of Commissioners, have heretofore indicated that
they would comply with the provisions of local cooperation when
called upon to do so. In June 1954, local interests were advised
that before construction could start they would have to fulfill the
provisions of local cooperation. Those interests stated that they
would organize so that they would be in a position to comply with
those provisions.
   c. Masonboro Inlet and connecting channels (H. Doc. 341, 81st
Cong., 1st sess.), which requires that responsible local interests
give assurances satisfactory to the Secretary of the Army that
they will provide, without cost to the United States, all lands,
easements, rights-of-way, and spoil disposal areas necessary for
the construction and subsequent maintenance of the project, when
and as required, and hold and save the United States free from
damages due to the construction and maintenance of the im-
provements.
   Terminal facilities. There are numerous wharves and land-
ings along the present waterway, used mostly for shipping agri-
cultural and timber products and docking commercial and pleasure
fishing boats. These wharves are of the open pile and timber type.
The facilities are considered adequate for existing commerce.
   Operations and results during fiscal year. The work consisted
of maintenance dredging by contract, operation and care of five
bridges, condition and operation studies, and inspections and
reports.
   Between January 1 and March 7, 1954, the contract dredge
Hampton Roads on maintenance dredging removed 264,281 cubic
yards from shoals in the through waterway at a cost of $94,409.
   Between June 13 and 30, 1954, the contract dredge Savannah
on maintenance dredging removed 55,000 cubic yards from shoals
in the through waterway at a cost of $19,088.
   Condition and operation studies and inspections and reports
cost $9,095.
   The bridges at Coinjock, Fairfield, Wilkerson Creek, Hobucken,
and Core Creek were operated and maintained at a cost of $96,841.
   The total costs were $219,433 for maintenance.
   Condition at end of fiscal year. The entire project was about
91 percent completed.   That portion of the project between the
              RIVERS AND HARBORS-WILMINGTON, N.C., DISTRICT                                                             301
Virginia-North Carolina State line and Beaufort, N.C., was com-
menced in August 1923 and completed in February 1930; the 12-
foot channel between Beaufort and Cape Fear River was com-
menced in March 1927 and completed in December 1932; the 12-foot
side channel to Swansboro was commenced in December 1938 and
completed in January 1939; the 10-foot channel in New River to
Jacksonville was commenced in July 1939 and completed in Octo-
ber 1939; the 6-foot channel from New River Inlet to the Water-
way was commenced in March 1940 and completed in June 1940;
the 12-foot channel from Cape Fear River, N. C., to Little River,
S. C., was commenced in February 1939 and completed in June
1940; and the yacht basin at Southport was dredged during Sep-
tember 1940. No work has been done on providing a tidal lock in
the land cut near the Cape Fear River, six mooring basins at
various locations, a 12-foot channel in New River, dredged chan-
nels in Masonboro Inlet and connecting channels, jetties at Mason-
boro Inlet, or salt-water-intrusion preventive measures in the
vicinity of Fairfield, N. C. At the close of the fiscal year the
controlling depths were as follows: Between Virginia State line
and Beaufort, 10.0 feet; Beaufort to Cape Fear River, 9.8 feet; side
channel to Swansboro, 12 feet; channel in New River to Jackson-
ville, N. C., 6.5 feet; channel to New River Inlet, 5.0 feet; and
between Cape Fear River, N. C., and Little River, S. C., 11.0 feet.
   The total costs under the existing project to June 30, 1954, were
$16,424,500, including $80,282 Public Works funds, of which $9,-
401,800 was for new work and $7,022,700 for maintenance.
                                           Cost and financial summary

                                                      Fiscal year ending June 30                              Total to June
                                                                                                             30, 1954, includ-
                                                                                                             ing fiscal years
                                    1950            1951            1952           1953           1954        priorto 19501
New work:
                 . . ....
   Appropriated-----------                    ------------    ----------------       -------------------           $9, 600, 507
   Cost------------------- -------- ------------ ------------ ------------ ------------                             9, 600, 507
Maintenance:
   Appropriated--------........   $236, 800       $243, 962       $163, 500       $164, 018      $249, 953          7, 167, 970
   Cost-----------          ---    249, 100        230, 981        174, 796        160, 079       219, 433          7, 130, 334

  1 Includes $198,707 for new work and $107,634 for maintenance for previous projects.
    Total authorized project:
         Authorized project, excluding jetties at Masonboro Inlet and tidal lock in Snows Cut $ 741, 200
         Authorized project, excluding tidal lock----------------------------------------
                                                           .                                                        2, 331, 200
         Authorized project, excluding jetties.-.-----.--.----.-----------_      .-       ---.                      2, 686, 200

Other new work data:
    Appropriated for succeeding fiscal year ending June 30, 1955....-------........                              $195,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955....-----------------------------------------                                                   195,000
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project ....   -----------------------------...                                      4, 081, 200

                                      2. ROANOKE RIVER, N. C.
   Location. This stream rises in the Blue Ridge Mountains, west
of Roanoke, Va., and flows southeasterly about 200 miles to Clarks-
ville, Va., where it is joined by Dan River, its principal tributary;
and thence in the same general direction about 198 miles and
empties into the westerly end of Albemarle Sound, N. C. (See
302                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

U. S. Coast and Geodetic Survey Chart No. 1228 and Post Route
Map of North Carolina.)
   Existing project. This provides for dredging a channel 12 feet
deep and 150 feet wide from the 12-foot contour in Albemarle
Sound into Roanoke River and thence upstream to about 1 mile
above Plymouth, N. C., 10 miles; thence a channel 10 feet deep and
100 feet wide to Hamilton, 53 miles; thence a channel 8 feet deep
and 80 feet wide to Palmyra Landing, 18 miles, with a cutoff chan-
nel of like dimensions about 2 miles above Hamilton; and thence
a channel 5 feet deep and 50 feet wide to Weldon, N. C., 50 miles,
by dredging, snagging, and regulation. Depths of channels are
referred to mean low water. The rise and fall of the river from
freshets is from 18 to 33 feet for about 70 miles below Weldon,
but this fluctuation diminishes toward the mouth, the variations
in water levels being from 1 to 2 feet in the lower 15 or 20 miles.
The total length of channels included in the project is 131 miles.
   The estimate of cost for new work, revised in 1954, is $639,000.
The latest (1954) approved estimate for annual cost of mainte-
nance is $30,000.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                               Work authorized                                            Documents
Mar.     3, 1871   Improvement of the river between the mouth and                         S. Doc. 23, 42d Cong., 2d sess.,
                     Weldon.                                                                and Annual Report, 1872, p. 726.
July     3, 1930   Entrance channel 10 feet deep and 150 feet wide-......                 H. Doc. 211, 70th Cong., 1st sess.'
June 20, 1938      Present project dimensions...-------..................--------------   H. Doc. 694, 75th Cong., 3d sess.'


1Contains latest published maps.

  Local cooperation. Fully complied with.
   Terminal facilities. There are 8 wharves at Plymouth. One
mile farther upstream there is a large wharf and bulkhead, a
transit shed, and crane runway for handling woodpulp and pulp
materials. Between that point and Hamilton there are 10 wharves.
Between Hamilton and Halifax there are 13 log landings. These
facilities appear to be adequate for existing commerce.
   Operations and results during fiscal year. The work consisted
of clearing and snagging with Government plant and hired labor,
condition and operation studies, and inspections and reports.
   Between October 15 and December 3, 1953, the U.S. derrickboat
Northeast with hired labor removed obstructions from the channel
and banks between the mouth of the river and 79 miles upstream.
The costs were $8,045.
   Condition and operation studies and inspections and reports cost
$925.
   Total costs were $8,970 for maintenance.
   Condition at end of fiscal year. The existing project has been
completed to the practicable limit. Dredging to obtain the present
project dimensions from the mouth to Palmyra was commenced
in September 1940 and completed in August 1941. As it is im-
practicable to obtain and maintain the project above Palmyra by
            RIVERS AND HARBORS-WILMINGTON, N.C., DISTRICT                                         303
dredging, snagging, and regulation, the percentage of completion
is uncertain. At the close of the fiscal year the limiting depths
at local mean low water were as follows: Between Albemarle
Sound and 1 mile above Plymouth, 10.1 feet; thence to Hamilton,
7.6 feet; thence to Palmyra, 2.4 feet; and thence to Weldon, 1 foot.
The work remaining to be done consists of completing by dredg-
ing, snagging, and regulation, a channel between Palmyra and
Weldon to a depth of 5 feet and minimum width of 50 feet. The
total costs under the existing project to June 30, 1954, were $404,-
584 for new work and $244,163 for maintenance, a total of
$648,747.
                                  Cost and financial summary

                                          Fiscal year ending June 30                    Total to June
                                                                                        30, 1954, includ-
                                                                                        ing fiscal years
                             1950-        1951       1952        1953        1954        priorto 1950

New work:
   Appropriated -----.-------------  ------                                                     $404, 584
   Cost-----------       -------------------------------- ------------       -----------         404, 584
Maintenance:
   Appropriated                $283 ------------------------    $750          $9, 000            244, 769
   Cost....                     283   -               -          174           8,970             244,163


Other new work data: Estimated additional amount needed to be appropri-
                                                   - ......................
  ated for completion of existing project ................                  ............... $234, 400

                    3. MANTEO          (SHALLOWBAG)              BAY, N. C.
   Location. Manteo Bay, or Shallowbag Bay, a natural indenta-
tion of the shoreline, is on the northeastern side of Roanoke Island,
N. C. Oregon Inlet, the northernmost existing inlet in the barrier
beach, is southeast of Roanoke Island, 13 miles southeast of
Manteo. (See U. S. Coast and Geodetic Survey Chart No. 1229.)
   Existing project. This provides for a channel 14 feet deep and
400 feet wide from the Atlantic Ocean over the bar and through
Oregon Inlet, thence 12 feet deep and 100 feet wide via Old House
Channel to that depth in Pamlico Sound; a channel 12 feet deep
and 100 feet wide from Oregon Inlet to and including a turning
basin 12 feet deep, 200 feet wide, and 600 feet long at Manteo; a
side channel 12 feet deep and 100 feet wide from the Manteo-Ore-
gon Inlet Channel in Roanoke Sound to the wharves in Mill Creek
near Wanchese, including a turning basin 200 feet square; and a
channel 6 feet deep and 100 feet wide connecting the Manteo-Ore-
gon Inlet Channel near the mouth of Manteo Bay with water of
that depth in the north end of Roanoke Sound. The total length
of channels included in the project is about 25 miles. The varia-
tions of the water surface are due to winds and seldom exceed 2
feet above or below mean stage. The extreme range of wind
tides, determined by 1 year's gage readings at Manteo, is 5.1 feet.
The estimate of cost for new work, revised in 1954, is $1,168,200.
The latest (1954) approved estimate of annual cost of maintenance
is $122,000.
   The existing project was authorized by the following River and
Harbor Acts:
304               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

       Acts                        Work authorized                                  Documents
June 25, 1910     Channel 6 feet deep and 100 feet wide fromRoanoke      H. Doc. 906, 60th Cong., 1st sess.'
                   Sound to Manteo.
Oct.    17,1940   Connecting channel of same dimensions to Oregon        H. Doc. 313, 76th Cong., 1st sess.'
                   Inlet.
May 17, 1950      Channel 14 feet deep, 400 feet wide, from Atlantic     H. Doc. 310, 81st Cong., 1st sess.'
                    Ocean through Oregon Inlet, thence 12 feet deep,
                   100 feet wide, via Old House Channel to Pamlico
                   Sound; channel 12 feet deep, 100 feet wide, from
                   Oregon Inlet to and including turning basin 12 feet
                   deep, 200 feet wide, 600 feet long, at Manteo; side
                   channel 12 feet deep, 100 feet wide, from Manteo-
                   Oregon Inlet Channel to and including 200-foot-
                   square turning basin in Mill Creek near Wanchese.

1 Contains latest published maps.

   Local cooperation. Complied with, except as follows: Condi-
tions in House Document 310, 81st Congress, 1st session, which
require that local interests furnish, without cost to the United
States, all lands, easements, rights-of-way, and spoil-disposal areas
for initial work and subsequent maintenance, when and as re-
quired; remove existing structures from the rights-of-way; con-
tinue the maintenance of the public landing in Mill Creek; and hold
and save the United States free from damages due to the construc-
tion and maintenance of the project. Local interests appear will-
ing and able to meet the local cooperation requirements.
   Terminal facilities. There are 12 timber wharves on the im-
proved portion of Manteo Harbor, with a total frontage of approxi-
mately 1,100 feet, which are privately owned. Mill Creek has 7
timber wharves with a total berthing space of 600 feet, of which
6 are privately owned; the other is owned and operated by Dare
County, N. C. The existing facilities are considered adequate for
present commerce.
   Operationsand results during fiscal year. Costs for 19,461 cubic
yards of material dredged from shoals in channel between Manteo
and Oregon Inlet during fiscal year 1953, but which were not in-
cluded in 1953 fiscal year annual report, amounted to $7,438.
   Condition and operation studies and inspections and reports
cost $67.
   The total costs were $7,505 for maintenance.
   Condition at end of fiscal year. The existing project was about
14 percent completed. The 6-foot channel from Roanoke Sound
to Manteo was dredged during August and September 1911. The
channel to Oregon Inlet was commenced in August 1941 and com-
pleted in November 1941. No work has been done on the 14-foot
channel from the Atlantic Ocean over the bar and through Oregon
Inlet, nor the 12-foot channels from Oregon Inlet to Manteo, Pam-
lico Sound, and Mill Creek. At the close of the fiscal year the
controlling depth in the channel to Manteo and to Oregon Inlet
was 5.5 feet. The total costs under the existing project to June
30, 1954, were $63,384 for new work and $167,403 for mainte-
nance, a total of $230,787.
            RIVERS AND HARBORS-WILMINGTON, N.C., DISTRICT                                                                      305
                                           Cost and financial summary

                                                       Fiscal year ending June 30                                     Total to June
                                                                                                                     30, 1954, includ-
                                                                                                                     ing fiscal years
                                   1950               1951               1952                   1953     1954          priorto 1950
New work:
    Appropriated       ..-------------       ------------------------------------------------                                 $63, 384
    Cost-__                ----------------------------------------------------------                                          63, 384
Maintenance:
    Appropriated                    $3, 500 -----------------------...                       $35, 000   -$1, 065              168, 392
    Cost-----------------            3, 420            $80      .                             25, 441
                                                                                 ...------------            7, 505            167, 403


Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project..._................................................ $1,109,600

         4. CHANNEL FROM PAMLICO SOUND TO AVON, N. C.
   Location. The village of Avon is on the narrow barrier beach
between Pamlico Sound and the Atlantic Ocean, 9 miles north of
Cape Hatteras. West of the village the sound is 25 miles wide.
About 4 miles offshore in the sound, a shoal or bar parallels the
beach from Hatteras Inlet, 15 miles southwest of Avon, to Oregon
Inlet, 30 miles north of Avon. Cape Channel, a natural opening
in the bar 6 miles southwest of Avon, has a controlling depth of
6 feet; from that opening a depth of 5 feet is available to Black
Hammock Channel, a basin with depths of over 10 feet, 1,500 feet
from the shore line at Avon. Shoreward of the basin the water
is very shallow. (See U. S. Coast and Geodetic Survey Chart No.
1232.)
   Existing project. This provides for a channel from Pamlico
Sound to Avon, 6 feet deep and 100 feet wide, with a basin at the
shore end, same depth, 100 feet wide and 300 feet long. Lunar tides
are imperceptible. Normal variations in the water surface due to
wind action seldom exceed 1 foot, but may be as much as 5 feet
during severe storms. The cost to the Federal Government for new
work for the completed project was $28,000. The latest (1954)
approved estimate for annual cost of maintenance is $1,000.
   The existing project was adopted by the River and Harbor Act
of March 2, 1945 (H. Doc. 316, 76th Cong., 1st sess.). The latest
published map is in that document.
   Local cooperation. Fully complied with.
   Terminal facilities. There are two wharves in the basin at
Avon, with a total frontage of about 150 feet. The existing facili-
ties are considered adequate for present commerce.
   Operations and results during fiscal year. The work consisted
of preparation of plans and specifications for maintenance dredg-
ing. The costs were $411 for maintenance.
   Condition at end of fiscal year. The existing project was com-
menced in September 1946 and completed in October 1946. At the
close of the fiscal year the controlling depth to Avon was 6 feet.
The total costs under the existing project to June 30, 1954, were
$28,000 for new work, and $748 for maintenance, a total of
$28,748.
 306                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                Cost and financial summary

                                                         Fiscal year ending June 30                         Total to June
                                                                                                           30, 1954, includ-
                                                                                                           ing fiscal years
                                         1950            1951       1952         1953            1954        prior to1950
New work:
    Appropriated     .....--------.----- ------------.------------ ------------ ------------                        $28, 000
    Cost__----------       ------------------------ ----------- ----------- ------------                             28, 000
Maintenance:
                     ........ ------------------------
       Appropriated----                                           ------------        $337       $6, 300              6, 637
                                                     ------------..
       Cost------------ -----------------------..........                              337           411                  748


                                 5. MOREHEAD                    CITY HARBOR, N. C.
   Location. This harbor is on the northern shore of Bogue
Sound, adjacent to Beaufort Harbor and Inlet. New Bern, N. C.,
the nearest city of importance, is about 43 miles by inland water-
ways to the north and west. (See U. S. Coast and Geodetic Survey
Chart No. 420.)
   Previous project. The channel across the ocean bar was for-
merly improved under the title of Beaufort Inlet, N. C. The project
was adopted by the River and Harbor Act of March 3, 1905 (H.
Doc. 563, 58th Cong., 2d sess.). For further details, see page 470
of Annual Report for 1935.
   Existing project. This provides for a channel 30 feet deep and
400 feet wide across the ocean bar at Beaufort Inlet, thence same
depth and 300 feet wide to the marine terminals at Morehead City,
enlarged to 600 feet to form a turning basin at that point, and for
construction of jetties at the inlet; for a channel 12 feet deep and
100 feet wide from the 30-foot channel to 6th Street, Morehead
City, thence same depth and 200 to 400 feet wide to 10th Street,
thence 6 feet deep and 75 feet wide to deep water in Bogue Sound.
The average rise of the tide is about 2    feet at Morehead City and
31/2 feet at the inlet. Observations made in 1907 showed an ex-
treme range of 4.8 feet.
   The estimate of cost of new work, revised in 1954, is $3,770,000,
exclusive of amounts expended on previous projects. The latest
 (1954) approved estimate for annual cost of maintenance is $230,-
000.
   The existing project was authorized by the following River and
Harbor Acts.

       Acts                                 Work authorized                                       Documents
June 25,1910          Channel 10 feet deep and 100 feet wide to the wharves           H. Doc. 649, 61st Cong., 2d sess.
                        at Morehead City, thence 200 feet wide in front of
                      the wharves.
July      3, 1930    Channel 12 feet deep and 100 feet wide from the outer            H. Doc. 105, 70th Cong., 1st sess.
                        harbor to 6th St. in Morehead City, thence 200 to              (Contains the latest published
                        400 feet wide to 10th St., and a channel 6 feet deep           map.)
                      and 75 feet wide connecting with Bogue Sound.
Aug. 26, 19371       Channel 30 feet deep and 400 feet wide across the bar            Senate   Committee     Print,    74th
                        at Beaufort Inlet, thence 30 feet deep and 300 feet             Cong., 1st sess.
                        wide to the marine terminals at Morehead City.

  1 Included in PublicWorks Administration program, July 5, 1934, under the National Industrial Recovery
Act of 1933.
       RIVERS AND HARBORS-WILMINGTON, N.C., DISTRICT             307
   Local cooperation. The project provides that local interests
furnish, free of cost to the United States, spoil-disposal areas as
required for new work and for future maintenance and all other
lands needed for the improvement, and to the further condition
that local interests give assurances satisfactory to the Secretary of
War that an adequate terminal open to the public on uniform terms
will be available by the time the channel is completed. Terminals
have been completed and spoil-disposal areas for new work fur-
nished. Lands needed in connection with the construction of jet-
ties have not been furnished.
   Terminal facilities. There are 26 wharves along the main wa-
terfront of the town, with a total frontage of about 1,250 feet.
The marine terminals provide 2,731 feet of berthing space with a
depth alongside of 27 feet at mean low water, and facilities for
transfer of cargoes between rail and water carriers. The existing
facilities are considered adequate for existing and prospective com-
merce. For further details, see Port Series No. 12, revised 1950,
Corps of Engineers.
   Operations and results during fiscal year. The work consisted
of maintenance dredging with United States plant and hired labor,
repairs and replacement of dredging ranges, and condition and
operation studies.
   Between February 6 and June 30, 1954, the U.S. hopper dredges
Gerig, Lyman, and Hyde on maintenance dredging removed 797,-
083 cubic yards from shoals in the ocean-bar channel and the outer
end of the 30-foot channel at a cost of $216,403.
   Repairs and replacement of dredging ranges during the fiscal
year cost $978.
   Condition and operation studies and inspections and reports cost
$6,312.
   The total costs were $223,693 for maintenance.
   Condition at end of fiscal year. The existing project was about
38 percent completed. The part of the existing project providing
for a 12-foot channel to Morehead City; thence a 6-foot channel
westward to Bogue Sound was commenced in February 1931 and
completed in March 1931; the part providing for the 30-foot chan-
nel to the terminals was commenced in November 1935 and com-
pleted in August 1936. No work has been done on the jetties
proposed for Beaufort Inlet. At the close of the fiscal year a
depth of 30.0 feet was available in the ocean-bar channel; 29.8
feet in the 30-foot channel (inside) to the terminals at Morehead
City; 10.8 feet from deep water in the outer harbor to the foot of
Tenth Street, Morehead City, and thence 3.9 feet westward to
Bogue Sound. The total costs under the existing project to June
30, 1954, were $2,634,525, of which $613,106, including $59,630
regular funds and $553,476 Public Works funds, was for new work
and $2,021,419 for maintenance.
308                  REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                   Cost and financial summary

                                                               Fiscal year ending June 30                                  Total to June
                                                                                                                          30, 1954, includ-
                                                                                                                          ing fiscal years
                                           1950               1951            1952             1953            1954         prior to 19501

New work:
   Appropriated          ------------ ------------ -----------------------                               ------------              $657, 591
   Cost....--------       ------------          ------------           -----------------------               -------                657, 591
Maintenance:
   Appropriated------_.                $145, 000         $131, 700  $194, 000 $102, 350                    $291, 582              2, 375, 665
   Cost...
        ----------------                184, 854           131, 196  116, 439  178, 616                    2223, 693              2, 305, 977

   1   Includes $44,484 for new work and $284,557 for maintenance for previous projects.
   2 Minus $402, pending adjustment.


Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project-...-.-..-.................................... $3 ,156 ,900

                6. CAPE FEAR RIVER, N.                                      C., ABOVE WILMINGTON
   Location. This river is formed by the confluence of the Deep
and Haw Rivers at Moncure, Chatham County, N. C. Flowing
southeasterly, it empties into the Atlantic Ocean at Cape Fear,
near the southern extremity of the state. (See U. S. Coast and
Geodetic Survey Chart No. 426.)
  Previous projects. Adopted by acts of March 3, 1881, and June
13, 1902. For further details, see page 1805 of Annual Report for
1915, and page 535 of Annual Report for 1938.
  Existing project. This provides for a dredged channel from
Wilmington to Navassa (4 miles), 25 feet deep and generally 200
feet wide with a cutoff across Horseshoe Bend and a turning basin
550 feet long and 400 feet in average width at its head; and for
a navigable depth of 8 feet at low water from Navassa to the head
of navigation at Fayetteville, 115 miles above Wilmington, by
constructing three locks and dams and by dredging river shoals
between Navassa and Fayetteville. Data regarding locks and
dams are as follows:
                                                                                      Distance        Distance        Maximum
           Lock and dam                                 Location                     from Wil-         above           available     Lift
                                                                                      mington          mouth          dimensions

                                                                                       Miles           Miles             Feet        Feet
No. 1..------------------                   King Bluff----------------                  39              69            200 by 40       11
No. 2 -----------------------               Browns Landing .--------                    71             101            200 by 40        9
No. 3        .---------------------         Tolars Landing_ --                          95             125            300 by 40        9


                             Available
                             depth on
                             miter sills    Character                                                             Year of
  Lock and dam                at low        of founda-          Kind of              Type of construction         comple- Actual cost
                              Water             tion             dam                                                tion

                                 Feet
No. 1-------------                 9        Sand ._.__.        Fixed-....      Concrete lock, timber crib              1916       1$565, 856
                                                                                dam, rock filled.
No. 2                ..-------------12      . do-.......         do-.......    Concrete lock, dam rock                 1917        2 909, 633
                                                                                filled.
No. 3------------                   9      -__   do-.......      do-._.....    Concrete lock, concrete                 1935         660, 930
                                                                                dam.


  1 Includes $96,184 for increasing lift.
  2 Includes $356,443 for reconstruction and repairs.

  The tide ranges from 3.4 feet at Wilmington to 1 foot at Lock
No. 1, Kings Bluff, N. C., 39 miles above. The extreme range of
              RIVERS AND HARBORS-WILMINGTON, N.C., DISTRICT                                           309
lunar tides is 6.4 feet at Wilmington and 1.5 feet at Kings Bluff.
The maximum variation due to floods ranges from 70 feet at Fay-
etteville to 5 feet at Wilmington.
   The cost to the Federal Government for new work for the com-
pleted project was $2,339,798. The latest (1954) approved esti-
mate for annual cost of maintenance is $105,000, including $45,000
for operation and care of locks and dams.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                        Work authorized                                Documents

June 25, 1910     The 8-foot channel and construction of 2 locks and   H. Doc. 890, 60th Cong., 1st sess.
                   dams.
July     3,1930   Channel 22 feet deep to Navassa. (No work was done   Rivers and Harbors Committee
                   on this project.)                                     Do.   39, 71st Cong., 2d sess.
June 26, 19341    Operation and care of locks and dams provided for
                    with funds from War Department appropriations
                    for rivers and harbors.                                                                 s
Aug.30, 19352     Construction of Lock and Dam No. 3 and repairs       H. Doc. 786, 71st Cong., 3d sess.
                    and alterations to Locks and Dams Nos. 1 and 2.
Aug. 26,1937      Present project dimensions from Wilmington to        Rivers and Harbors Committee    5
                    Navassa with cut-off across Horseshoe Bend, and      Doc. 17, 75th Cong., 1st sess.
                    a turning basin.

  1 Permanent Appropriations Repeal Act.
  2 Included in Public Works Administration program, Sept. 27, 1933.
  S   Contains latest published map.

   Local cooperation. Fully complied with.
   Terminal facilities. There are six wharves between Wilming-
ton and Fayetteville, including the public terminal at that point.
They have a total frontage of about 700 feet. The terminals ap-
pear to be adequate for existing commerce.
   Operations and results during fiscal year. The work consisted
of maintenance dredging with leased plant, clearing and snagging
with Government plant and hired labor, condition and operation
studies, inspections and reports, construction of guard and guide
walls at locks and dams 1 and 2, and operation and maintenance
of three locks and dams.
   Between August 10 and September 12, 1953, the leased dredge
Marion on maintenance dredging removed 78,778 cubic yards from
shoals in the 8-foot channel to Fayetteville at a cost of $29,119.
   Between February 10 and June 17, 1954, the U.S. derrickboat
Northeast with hired labor removed obstructions from the chan-
nel and banks in the 8-foot channel to Fayetteville at a cost of
$15,811.
   Condition and operation studies and inspections and reports cost
$2,477.
   Between December 1, 1953, and June 30, 1954, guard and guide
walls at lock and dam 1 were 90 percent completed by contract at
a cost of $145,068.
   Between March 8, 1954, and June 30, 1954, guard and guide
walls at lock and dam 2 were 91 percent completed by contract at
a cost of $160,719.
   The three locks and dams were operated and maintained at a
cost of $38,023.
   The total costs were $391,217 for maintenance.
   Condition at end of fiscal year. The existing project is com-
310            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

pleted. The construction of locks and dams 1 and 2, and dredging
of river shoals, were commenced in August 1912 and completed
in July 1917. The construction of lock and dam 3 and repairs and
alterations to locks and dams 1 and 2 were commenced in January
1934 and completed in July 1935. The dredging of the 25-foot
channel to Navassa was commenced in November 1938 and com-
pleted in January 1939. The controlling depths are 22 feet from
Wilmington to Navassa, 4 miles; thence 18 feet to 9 miles above
Wilmington; thence 7.0 feet to Fayetteville, 115 miles above Wil-
mington. The total costs under the existing project to June 30,
1954, were $4,362,473 of which $2,339,798 (including $1,104,391
Public Works funds) was for new work, $1,224,999 for mainte-
nance, and $797,676 for operating and care.
                                      Cost and financial summary

                                              Fiscal year ending June 30                         Total to June
                                                                                                30, 1954, includ-
                                                                                                Ing fiscal years
                               1950         1951         1952         1953         1954          prior to 19501
New work:
   Appropriated       ----   --------       ----------------------------------------------           $2, 488, 917
   Cost....-----------------      -------------        ------------   -----------------------         2, 488, 917
Maintenance:
    Appropriated........      $152, 400     $68, 098     $95, 000    $235,051     $222, 000            2, 061, 223
    Cost- -----.... -----    - 130, 221      85, 351      50, 495      89, 626     391, 217            2, 030, 853

  1Includes $149,119 for new work and $8,178 for maintenance for previous projects.
                             7. WILMINGTON                HARBOR, N. C.
   Location. Wilmington Harbor, N. C., consists of a dredged
ship channel from the ocean across the entrance bar and up the
Cape Fear River to the mouth of Northeast (Cape Fear) River,
thence 2.75 miles up the latter to a turning basin at the upstream
end. (See U. S. Coast and Geodetic Survey Chart No. 426.)
   Previous projects. Authorized by River and Harbor Acts of
March 2, 1829; July 22, 1854; July 11, 1870; March 3, 1873; June
23, 1874; September 19, 1890; June 13, 1902; and March 2, 1907.
For further details, see page 1804 of Annual Report for 1915, and
page 533 of Annual Report for 1938.
    Existing project. This provides for a channel 35 feet deep and
400 feet wide from the 35-foot contour in the Atlantic Ocean
through the ocean-bar channel, thence 34 feet deep and 400 feet
wide to the upper end of the anchorage basin (foot of Castle St.)
at Wilmington, thence 32 feet deep and 400 feet wide to Hilton
Bridge over Northeast (Cape Fear) River, with increased widths
at bends; for an anchorage basin at Wilmington 34 feet deep, 2,000
feet long, 900 feet wide at the upper end, 1,100 feet wide at the
lower end, with approaches 1,500 feet long at the upper end and
4,500 feet long at the lower end with some widening of the transi-
tion channel at the downstream end; for a turning basin opposite
the principal terminals at Wilmington, 32 feet deep, 1,000 feet
long, 800 feet wide, with suitable approaches at each end; for a
channel 12 feet deep and 100 feet wide in the Cape Fear River,
from a point near the eastern entrance of the Intracoastal Water-
way to a connection with the main river channel at a point about
3 miles above; and for a channel 25 feet deep, 200 feet wide, from
Hilton Bridge over Northeast (Cape Fear) River to a turning
              RIVERS AND HARBORS-WILMINGTON, N.C., DISTRICT                                                311
basin of the same depth, 600 feet wide, 11/4 miles above. The plane
of reference is mean low water. The length of the deep-draft sec-
tion under improvement is about 311/4 miles, the upper limit being
11/4 miles above Hilton Bridge over Northeast (Cape Fear) River.
The average rise of tide is 4.7 feet at the ocean bar, 3.6 feet at
Keg Island, and 3.4 feet at Wilmington. The extreme range of
tides is about 8.5 feet at the ocean bar, 7.3 feet at Orton Cove,
and 6.4 feet at Wilmington.
   The estimated cost for new work, revised in 1954, is $6,710,000,
exclusive of amounts expended on previous projects. The latest
 (1954) approved estimate for annual cost of maintenance is $500,-
000.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                         Work authorized                                     Documents
July 25,1912      Channel 26 feet deep and 400 feet wide across the bar,    H. Doc. 287, 62d Cong., 2d sess.
                   thence same depth and 300 feet wide, increased at
                   bends, to Wilmington.
Mar.    2,1919    Channel 30 feet deep and 400 feet wide, across the        H. Doc. 746, 65th Cong., 2d sess.
                    ocean bar. (No work was done on this project.)
Sept. 22, 1922    A new channel across the ocean bar 30 feet deep and       H. Doc. 94, 67th Cong., 1st sess.
                    400 feet wide from Baldhead Point.
July    3, 1930   A 30-foot project to Hilton Bridge atWilmington, and      Rivers and Harbors Committee
                    a turning basin.                                          Doc. 39, 71st Cong., 2d sess.   1
Mar.    2,1945    Increase channel widths from 300 to 400 feet, turning     H. Doc. 131, 76th Cong., 1st sess.
                    basin from 600 to 800 feet, and a channel 12 feet
                    deep, 100 feet wide, from Inland Waterway to river
                    channels.                                                                               1
    Do.......     Increase length of southerly approach to anchorage        S. Doc. 83, 76th Cong., 1st sess.
                    basin from 1,500 to 4,500 feet, and increase depth of
                    channel from outer end of ocean bar to Wilming-
                   ton, including turning basin, from 30 to 32 feet.
    Do.......     Channel 25 feet deep, 200 feet wide, from Hilton          S. Doc. 170, 76th Cong., 3d sess.?
                    Bridge, Northeast (Cape Fear) River, to a turning
                    basin, same depth, 11 miles above.
May 17, 1950      Increase depth to 35 feet over ocean bar, thence 34       H. Doc. 87, 81st Cong., 1st sess.'
                    feet to upper end of anchorage basin, including
                    anchorage basin, and with some widening of the
                    transition channel at the anchorage basin.

1 Contains the latest published maps.

   Local cooperation. The River and Harbor Act of May 17, 1950,
provided that local interests furnish, without cost to the United
States, all lands, easements, rights-of-way, and spoil-disposal areas
necessary for construction and subsequent maintenance of the
project, when and as required; and hold and save the United States
free from damages due to the construction and subsequent main-
tenance of the project. Local interests appear willing and able
to fulfill the local cooperation requirements.
   Terminal facilities. There are 49 wharves of all classes at Wil-
mington, with a combined berthing space of 15,698 linear feet,
and depths of water alongside from 10 to 30 feet at mean low
water. Below Wilmington there are 27 wharves, which are con-
sidered adequate for present needs. For further details, see Port
Series No. 12, revised 1950, Corps of Engineers.
   Operations and results during fiscal year. The work consisted
of maintenance dredging by contract, repairs to dredging ranges
with Government plant and hired labor, condition and operation
studies, and inspections and reports.
   Between July 1 and 21, 1953, the contract dredge Pullen on
312              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

maintenance dredging removed 130,562 cubic yards from shoals in
river channels at a cost of $30,960.
   Between October 12 and 27, 1953, the contract dredge Hampton
Roads removed 121,173 cubic yards from shoals in front of the
North Carolina State Ports Authority Terminal at a cost of
$32,120.
   Between April 9 and June 30, 1954, the contract dredges Hamp-
ton Roads and Pullen removed 548,248 cubic yards from shoals in
the Anchorage Basin, Turning Basin, and river channels at a
cost of $140,899.
   Between February 8 and 9, 1954, the U.S. derrickboat Northeast
with hired labor made repairs to the Government-owned dredging
ranges at a cost of $497.
  Condition and operation studies and inspection costs were $17,-
505. The total costs were $221,981 for maintenance.
   Condition at end of fiscal year. The existing project was about
81 percent completed. Deepening and widening the river channel
to 32 feet by 400 feet, enlarging and deepening the anchorage
basin and southern approach thereto, and deepening the ocean-
bar channel to 32 feet, were commenced in April 1947 and com-
pleted to the foot of Castle Street at Wilmington in May 1949.
Dredging the 25- by 200-foot channel and basin in Northeast (Cape
Fear) River above Hilton Bridge was commenced in October 1948
and completed in November 1948. Dredging the 12- by 100-foot
channel from the Intracoastal Waterway to the ship channel in
the river was commenced in November 1948 and completed in
December 1948. No work has been done on the 32-foot project.
on that portion of the river channel above Castle Street, except
increasing the width of the turning basin to 800 feet, 30 feet deep,
and widening the east side of the river channel, in the vicinity
of the turning basin, to the harbor line, to a depth of 30 feet. No
work has been done on deepening the ocean-bar channel to 35 feet
nor the river channel and anchorage basin to 34 feet. At the close
of the fiscal year the controlling depths were 31.1 feet in the
ocean-bar channel, 30.8 feet in the river channel up to Castle Street
in Wilmington, 30.0 feet to and in the turning basin, 25.0 feet
to and in the turning basin in Northeast (Cape Fear) River, and
10.6 feet in the connecting channel with the Intracoastal Water-
way. The total costs under the existing project to June 30, 1954,
were $4,103,712 for new work and $7,361,114 for maintenance, a
total of $11,464,825.
                                          Cost and financial summary

                                                   Fiscal year ending June 30                     Total to June
                                                                                                  30, 1954, includ-
                                                                                                  ing fiscal years
                                   1950           1951        1952         1953        1954        prior to 19501

New work:
   Appropriated--------........     -$8, 083   ......
                                               -$8,       ........    . ....-        --------               729, 326
   Cost..----------             ----------        --------------------------------------------           8, 729, 326
Maintenance:
    Appropriated----- _.           246, 000      $246, 000   $304, 000    $519, 824   $296, 820          8, 073, 944
    Cost----....--------           230, 654       270,484     303,415      504, 141    221,981           7, 963, 728


   1Includes $4,625,614 for new work and $602,614 for maintenance for previous projects.
Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project._.__._.. ..... .________. $2 ,606 ,300
                   RIVERS AND HARBORS-WILMINGTON, N.C., DISTRICT                                                                           313
                               8. INACTIVE NAVIGATION PROJECTS

                                                                    For last           Cost to June 30, 1954                      Estimated
                                                                  full report                                                      amount
                     Name of project                                  see                                                         required
                                                                    annual              Con-              Operation                  to
                                                                    report            struction              and                  complete
                                                                     for-                                maintenance
1. Bay River, N. C.    __------------------------                    1950                 $44, 382              9 $49, 627             (3)
2. Beaufort Harbor, N. C.-------------------                         1953                 322, 322             10o441, 050             $154, 700
3.                   4 - C._-------------------
    Belhaven Harbor, N.    - -- -- -- -- -- -- -- -- -- --            1953                 126, 687                  2, 448             (3)
4. Black River, N. C. .          .                                   1941                  12, 358                 36, 072             (S)
5. Cashie River, N. C-....                                           1950                  40, 403                1115,495             (3)
6. Channel connecting Thoroughfare Bay with                          1950                   9, 000                 15, 549                30, 000
      Cedar Bay, N. C.
7. Channel from Back Sound to Lookout Bight,                         1953                  24, 676                    176, 126          105, 300
         N.   C.
8. Channel from Pamlico Sound to Rodanthe,                           1950                                              ____               45, 000
     N. C.
9. Chowan River, N. C.................---------------------          1950                               _                                30, 000
10. Contentnea Creek, N. C.1 4 s                                      1941                  64, 395                     32, 247         (3)
11.    Drum Inlet, N. C._______________________                      1953                   52, 828                    153, 813          (3)
12.    Edenton Harbor, N. C.____________________                     1950                   73, 750                      2, 971          (3)
13.    Far Creek, N. C.    ___-- __- ___ __----___-                  1953                   34, 500                    102, 873           179, 500
14.    Fishing Creek, N. C.4 5_                 ____                 1922
                                                                  -________                 22, 715                      8, 633          (3)
15.    Harbor of Refuge, Cape Lookout, N. C.1 __                     1934               1, 368, 799                     32, 854        9, 631, 200
16. Lockwoods Folly River,
                       1   N. C..........----              --         1950                  17, 818                     13, 094          147, 200
17. Mackay Creek, N. C. --7 _____--     -          _._.--.
                                                        - - -       2 1938                  13, 375                 4, 773              (s)
18. Masonboro Inlet, N. C. ....               ....__       ..         1948                                       1285, 631              (3)
19. Meherrin River, N. C........._...________-                        1950                   47, 734               49, 591              (S)
20. Neuse River, N. C.... 1                                   .
                                                .__.___
                                                      .___________    1950                 403, 066             i 288, 960               8 39, 900
21. Newbegun Creek, N. C. ' .4-_ ._____--           4     -         2
                                                                -____ 1928                    4, 802                   247              (3)
22. Northeast (Cape Fear) River, N. C.                                1950                   10, 688               61, 139              (s)
23. Pamlico and Tar Rivers, N. C.------.......                        1952                 674, 651             1 532, 636              (s)
24. Pembroke Creek, N. C. ..............-                             1950     -------------------------                           -       15, 000
25 .P e rq uim a ns R iv e r, N . C .' . --. . --..
                                                ... ... ...         2 19 1 0                 13 , 7 5 0 - _ _   15..   . - ---          (3)
26. Rollinson Channel, N. C .             .._--------------           1953                   20, 125             5123, 225                 54, 900
27. Scuppernong River, N. C................._                         1950                   81, 164               76, 847              (3)
28. Silver Lake Harbor, N. C. -_--------------                        1952                   67, 241             1648, 216              (3)
29. Shallotte River, N. C. -_-                                        1950                   18, 181                6, 468              (3)
30. Smiths Creek (Pamlico County), N. C.1____                         1950                   14, 472               23, 780              (3)
31. Smiths Creek (Wilmington), N. C.-.------                          1950                    8, 507                    18              (3)
32. South River, N. C ...........-----------------------              1936                   12, 452             1721, 624              (3)
33. Stumpy Point Bay,1 N. C................._                         1950                   40, 583                18s122              (3)
34. Swift Creek, N. C. 4________               _____                  1940                    1, 600                5, 422              (3)
35.
36.
37.
    Trent River, N. C._
    Wallace Channel, Pamlico Sound, N. C.
    Waterway connecting Pamlico Sound and
                                                         7
                                                           ----       1946
                                                                      1949
                                                                      1953
                                                                                           115, 199
                                                                                            45, 188
                                                                                                                   69, 787
                                                                                                                   35, 000
                                                                                                                19159, 013
                                                                                                                                        (S)
                                                                                                                                           25, 200
                                                                                                                                          130, 800
       Beaufort Harbor, N. C.
38. Waterway connecting Swan Quarter Bay                              1950                    8, 551                    10, 433            50, 500
      with Deep Bay, N. C.
39. Waterway-Norfolk, Va., to Sounds of N. C.                       2 1946-       ___________--------_                                  (3)
       (Wilmington district)'


   1 Channels adequate for commerce.
   2 Report of Norfolk, Va., district.
   S Completed.
   4No commerce reported in 1950-52.
   5 Abandonment recommended in 1926 (H. Doc. 467, 69th Cong., 1st sess.).
   6 Abandonment of portion above Snow Hill recommended in 1926 (H. Doc. 467, 69th Cong., 1st sess.).
   7 Snagging and clearing under section 3 of the River and Harbor Act approved March 2, 1945.
   8 Completed to practicable limit.
   9 Expended for condition surveys during fiscal year 1953, $108.
  to Expended for condition surveys during fiscal year 1954, $148.
  11Expended for condition surveys during fiscal years 1953 and 1954, $100.
  12Expended for miscellaneous surveys during fiscal years 1949, 1950, and 1953, $7,352.
  is Expended for condition surveys during fiscal year 1953, $114.
  14Expended for condition surveys during fiscal years 1953 and 1954, $283.
  15Expended for condition surveys during fiscal year 1954, $464.
  16Expended for condition surveys during fiscal years 1953 and 1954, $1,015.
  17Expended for condition surveys during fiscal year 1953, $154.
  18 Expended for condition surveys during fiscal year 1953.
  19Expended for condition surveys during fiscal year 1954, $452.
314              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                       9. INACTIVE FLOOD CONTROL PROJECTS

                                                            For last      Cost to June 30, 1954        Estimated
                                                           full report                                 amount
                    Name of project                             see                                    required
                                                             annual        Con-         Operation         to
                                                             report      struction         and         complete
                                                              for-                     maintenance

1. Goldsboro, Neuse River, N. C..... ..... ___.      -            1950      $50, 430         7$560        (s)
2. New River, N. C.;1'  __-___-__--1950                                      33, 896                       (3)
3. Pasquotank River, N. C..-------------------........            1952                                    $130, 000
4. Tar River, N. C.               __-------------------------    1939         81, 266 --------------       (3)
5. Tar River and Tributaries, N. C.1 4-----                - 1942 and       5 83, 584 --------------       (3)
                                                                  1947
6. Trent River, N. C.1                   _------------------------1953      6 49, 769 --------------       (')
7. White Oak Levees Cape Fear River (Bladen                       1947                      36, 460       (3)
     County), N. C.


     1 Work accomplished under authority of section 2 of Flood Control Act of August 28, 1937, as amended.
     2 Work accomplished under authority of section 5 of Flood Control Act of August 18, 1941.
     3 Completed.
     4Includes Contentnea Creek.
     s In addition, $17,680 of Works Progress Administration funds were expended.
     6 In addition, $15,000 of contributed funds were expended.
     7 Expended for condition and operation studies during fiscal year 1954.


                                10. GENERAL INVESTIGATIONS
   Examinations and surveys. A total of $2,978 was expended
for navigation studies during the fiscal year; the balance unex-
pended June 30, 1954, $527, will be applied to continue work on
these reports during the early part of the 1955 fiscal year.
   Flood control studies were made during the fiscal year at a cost
of $657; the unexpended balance of $5 in this allocation will be
expended during the 1955 fiscal year.
   An unexpended balance of $1,130 of Federal funds and an equal
amount of contributed funds will be applied during the fiscal year
to complete a Beach Erosion Cooperative Study.
   Total costs for examinations and surveys during the fiscal year
were $3,635; the balance unexpended June 30, 1954, $1,662, will
be expended during the fiscal year; no allotment is anticipated for
fiscal year 1955.
   Collection and study of basic data. An allotment of $1,400 was
made for these activities during the fiscal year. Various inspec-
tions and observations were made of flood situations during the
year at a cost of $450. The district Flood and Disaster Manual
was revised and distributed at a cost of $950; total costs were
$1,400. No funds remain from this allocation and no allotment is
anticipated for 1955.
          IMPROVEMENT OF RIVERS AND HARBORS
            IN THE CHARLESTON, S. C., DISTRICT*

   This district comprises all of South Carolina (except the local
watersheds draining into the Savannah River), western-central
North Carolina, and a very small portion of southwestern Vir-
ginia. It embraces the drainage basins tributary to the Atlantic
Ocean between Little River and Port Royal Sound, except the
watersheds of Mackay and Skull Creeks, and excluding Hilton
Head Island. It includes the Atlantic Intracoastal Waterway in
the same reach.
                                         IMPROVEMENTS

                  Navigation                                    Navigation-Continued
                                             Page                                                     Page
1. Atlantic Intracoastal Water-                     7. Table of inactive navigation
     way between Norfolk, Va.,                           projects .------------.............. --..............
                                                                                                      326
     and the St. Johns River, Fla.
     (Charleston District).............      315
2. Georgetown Harbor, S. C.....-..           317
3. Charleston Harbor, S. C..----.......      319                      Flood control
4. Ashley River, S. C.....................   322
5. Shipyard River, S. C................      323    8. Table of inactive flood con-
6. Emergency channel work-                               trol projects............................    326
     Shem Creek, S. C....------.-....        325    9. General investigations.---...---....-.         326

1. ATLANTIC INTRACOASTAL WATERWAY BETWEEN NORFOLK,
VA., AND THE ST. JOHNS RIVER, FLA. (CHARLESTON DISTRICT)
   Location. This section of the waterway begins at Little River
near the North and South Carolina State line, and extends gener-
ally southerly along the coast of South Carolina to Winyah Bay,
62 miles; thence 63.5 miles to Charleston; thence 84.5 miles to and
including Port Royal Sound; a total distance of 210 miles. (See
U. S. Coast and Geodetic Survey Charts Nos. 835, 836, 837, and
838.)
   Previous projects. Adopted by River and Harbor Acts of
March 3, 1881, and June 13, 1902. For further details, see page
613, Annual Report for 1932.
   Existing project. This provides for a waterway 12 feet deep at
mean low water and not less than 90 feet wide from Little River to
and including Port Royal Sound, with a branch channel of the
same dimensions to McClellanville, a total of 210 miles; for the
construction of three bridges crossing the waterway in Horry
County, S. C.; and for an anchorage basin 125 feet wide, 335 feet
long, and 12 feet deep near Myrtle IBeach, S. C. The mean range
of tide at Little River is 5 feet; Winyah Bay, at Georgetown, 3.3
feet; at Charleston, 5.1 feet; and at Port Royal Sound, 7.2 feet.
   The estimate of cost for new work (1954), exclusive of amounts
expended on previous projects, is $7,363,000. The latest (1954)
approved estimate for annual cost of maintenance is $207,600.



                                                                                            315
316                  REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

The existing project was authorized by the following River and
Harbor Acts:

     Acts                           Work authorized                                 Documents and reports
                                                                           I
                 I

Sept. 19, 1890       Channel from Minim Creek to Winyah Bay.......             Annual Report, 1889, p. 1184.
June 13, 1902        Channel from Charleston to a point opposite Mc-           H. Doc. 84, 56th Cong., 1st sess.,
                      Clellanville.                                             and Annual Report, 1900, p.
                                                                                 1908.
Mar.   2, 1907 Branch channel to McClellanville ..................             Annual Report, 1903, p. 1133.
Mar.   2, 1919 Extending the channel to Minim Creek, thence                    H. Doc. 178, 63d Cong., 1st sess.
                 through the Estherville-Minim Creek Canal to
                 Winyah Bay.
Mar. 3, 1925 Cut across the Santee Delta at Four Mile Creek ....               H. Doc. 237, 68th Cong., 1st sess.
    Do ..... Widening and deepening the waterway from Charles-                 S. Doc. 178, 68th Cong., 2d sess.
                 ton to Beaufort.
July 3, 1930   A waterway 8 feet deep and 75 feet wide from Cape               H. Doc. 41, 71st Cong., 1st sess.
                 Fear River to Winyah Bay.
Aug. 30, 19351 Construction of bridges across the waterway in                  Rivers and Harbors Committee
                 Horry County, S. C.                                             Doc. 14, 72d Cong., 1st sess.
Aug. 30, 19352 Cutoff between Ashepoo and Coosaw Rivers ........               H. Doc. 129, 72d Cong., 1st sess.
    Do'...... Enlarging the channel from Winyah Bay to Charles-                Rivers and Harbors Committee
                 ton, including the branch channel to McClellan-                 Doc. 11, 72d Cong., 1st sess.
                 ville, to depth of 10 feet and bottom width of 90 feet.
Aug. 26, 1937  Increasing dimensions of waterway to 12 feet deep               Rivers and Harbors Committee    5
                 and 90 feet wide.                                               Doc. 6, 75th Cong., 1st sess.
Mar. 2, 1945 Anchorage basin 125 feet wide, 335 feet long, 12 feet             H. Doc. 327, 76th Cong., 1st sess.
                 deep, near Myrtle Beach, S. C.

  1 Included in Public Works Administration program, Sept. 6, 1933.
  2 Included in Emergency Relief Administration program May 28, 1935.
  3 Contain latest published maps.


  Local cooperation. Fully complied with, except for conditions
in House Document 327, 76th Congress, 1st session, which require
that local interests furnish, free of cost to the United States, as
and when required, all lands, easements, and rights-of-way and
spoil disposal areas for the initial work and for subsequent main-
tenance; and give assurances, satisfactory to the Secretary of
War, that they will provide and maintain suitable mooring piles,
walkways, and road connections open to the public without cost,
and will provide and operate servicing facilities for recreational
craft, open to all on equal and reasonable terms, all as may be
required by the Secretary of War.
   Terminal facilities. There are rail-water terminals at George-
town, Charleston, Yonges Island, and Port Royal, and numerous
open-pile wharves mostly for shipping agricultural products, fish,
oysters, and pulpwood. These facilities are considered adequate
for existing commerce.
   Operations and results during fiscal year. The pipeline dredge
Northwood, by contract, restored project dimensions at 9 shoals
in a 20 mile reach between Little River and Winyah iBay, S. C.,
during September and November 1953, removing 78,233 cubic
yards of material at a cost of $46,799.
  The pipeline dredge Cherokee, by contract, restored project
dimensions at 8 shoals in a 49.2 mile reach between Winyah Bay
and Charleston, S. C., during December 1953 and January 1954,
removing 260,444 cubic yards of material at a cost of $58,990. The
pipeline dredge Hampton Roads, by contract, restored project di-
mensions at 5 shoals in a 17 mile reach between Charleston and
Port Royal Sound, S. C., during March 1954, removing 133,303
cubic yards of material at a cost of $34,812.
  The cost of surveys and supervision was $15,234. The total
              RIVERS AND HARBORS-CHARLESTON,                                      S.C., DISTRICT                       317
cost for the year was $155,835 for maintenance.
   Condition at end of fiscal year. The existing project was about
99 percent completed. That portion of the existing project pro-
viding for a channel 12 feet deep and 90 feet wide was completed
in 1940; the work remaining consisted of providing an anchorage
basin 125 feet wide, 335 feet long, and 12 feet deep near Myrtle
Beach, S. C. Surveys during June 1954 showed a controlling
centerline depth of 10 feet at mean low water between mile 342
at Little River, S. C., and mile 377, at Bucksport, S. C., in the Little
River to Winyah Bay section; thence 10 feet at mean low water
between mile 411 at the Winyah Bay end of the Estherville-Minim
Creek Canal and mile 464 at Charleston Harbor, in the Winyah
Bay to Charleston section; thence 10 feet at local mean low water
between miles 470 and 552 in the Charleston to Port Royal Sound
section. Surveys during June 1954 showed a controlling depth of
5.7 feet in the branch channel to McClellanville, S. C.
   The costs of the existing project to the end of the fiscal year
for new work have been $4,011,951 from regular funds, $3,259,-
294 from public works funds, and $74,643 from Emergency Relief
funds, a total of $7,345,888. The costs to the end of fiscal year for
maintenance have been $4,863,471 from regular funds, $13,308
from public works funds and $54,916 from Emergency Relief
funds, a total of $4,931,695. The total cost for all work has been
$12,277,583.
                                          Cost and financial summary

                                                   Fiscal year ending June 30                            Total to June
                                                                                                        30, 19541, includ-
                                                                                                            ing fiscal years
                                   1950           1951           1952          1953           1954           priorto 1950

New work:
   Appropriated ........-------------------- _   ---------.-------------------.                ------ ---        $7, 455, 378
   Cost_                   ------------------ --------------                 ------------------------                 4---------.
                                                                                                                   7, 455,  378
Maintenance:
   Appropriated.    _           $133, 646      $50, 543          $185, 195         $4, 473    $165, 161            5, 010, 444
   Cost   --                      295,541       .53, 455           178,142         11,771      155,723            25, 001, 006


  1 Includes $109,490 for new work and $69,422 for maintenance for previous projects.
  2 Includes $111 cost in excess of prepayments.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project _... ......                          $......
                                                         . ...................... $17,100

                               2. GEORGETOWN HARBOR, S. C.
   Location. On the coast of South Carolina, 50 miles northeast
of Charleston Harbor and 90 miles southwest of the entrance to
Cape Fear River, N. C. (See U. S. Coast and Geodetic Survey
Chart No. 787.)
   Previous projects. Adopted by River and Harbor Acts of Au-
gust 2, 1882; August 5, 1886; and June 25, 1910. For further de-
tails see page 1806 of Annual Report for 1915, page 549 of Annual
Report for 1938, and page 442 of Annual Report for 1944.
  Existing project. This provides for a channel 27 feet deep
from that depth in the Atlantic Ocean to and including a turning
basin in Sampit River, 600 feet wide across the outer bar and in
the gorge and 400 feet wide thence to a turning basin at the head
of the project via a cutoff across the peninsula in Sampit River,
with a side channel 2,400 feet long and not less than 250 feet wide
318                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

leading to a turning basin at the upper end of the built-up portion
of the city waterfront, widened at the bends, to be secured and
maintained by two jetties of stone on brush mattresses, springing
respectively from North and South Islands, the north jetty having
a length of 11,139 and the south jetty 21,051 feet. The project
also provides for the continued maintenance to a depth of 18 feet
for a width of 400 feet of the bypassed portion of Sampit River
opposite the city of Georgetown.
   The cost to the Federal Government for new work in complet-
ing the existing project was $4,615,904. The latest (1954) ap-
proved estimate for annual cost of maintenance is $326,000.
   The mean range of tide at Georgetown is 3.3 feet; spring tides
have a mean range of 3.9 feet.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                          Work authorized                                            Documents

Aug.     5, 1886   Jetties and earthen dike to protect south jetty- ..   ..   H.     Ex. Doc. 258, 48th Cong., 2d
                                                                               sess., and Annual Report, 1885,
                                                                               pp. 1154-1170, and H. Ex. Doc.
                                                                               117, 50th Cong., 2d sess., and An-
                                                                               nual Report, 1889, pp. 1110-1115.
June 25, 1910      Previous project channel dimensions and training           H. Doc. 398, 58th Cong., 2d sess.,
                    wall.                                                       and Annual Report, 1904, pp.
                                                                                   1591-1609.
Mar. 2,1945        27-foot channel from ocean, including a turning            H. Doc. 211, 76th Cong., 1st sess.
                    basin in Sampit River.                                         (Contains latest published map.)
June 30, 1948      Cutoff and side channel in Sampit River....------------S. Doc. 21, 81st Cong., 1st sess.



   Local cooperation. Fully complied with
   Terminal facilities. The terminal facilities at the port of
Georgetown served by this improvement consist of four wharves
of ordinary timber construction, one of creosoted timber construc-
tion, suitable for oceangoing vessels, and a number of smaller
wharves and landing places. These are considered adequate for
the present commerce of the port.
   Operations and results during fiscal year. The pipeline dredge
Barlow, by contract, during January and February 1954, per-
formed maintenance dredging to project depth for 300-foot width
in a 1.3 mile reach in Upper Winyah Bay channel and in Sampit
River from its mouth by the cutoff to the head of the project, in-
cluding a turning basin and widening a bend, removing 1,099,435
cubic yards of material at a cost of $200,592.
   The cost of surveys and supervision was $4,722. The total cost
during the year was $205,314.
   Condition at end of fiscal year. The existing project was com-
pleted in July 1951. The jetties were completed in 1903-4. The
crest elevations range from 8 to -- 4 feet and are as much as 12
feet below their original height. Dikes of various forms have
been built to protect the South Island beach and the shore end of
the south jetty. An earth dike 4,100 feet long has been con-
structed east of the eastern channel, largely from original channel
excavation, to assist in maintaining the channel. The Sampit
River entrance is protected on the east side by a timber and brush
training wall 2,000 feet long.
   Surveys in June 1954 showed a controlling depth of 25.3 feet at
                 RIVERS AND HARBORS-CHARLESTON, S.C., DISTRICT                                                                  319
mean low water for 600-foot width from the ocean to the Gorge
Channel, thence 27 feet for 300-foot width through the Gorge and
eastern channel, thence a controlling depth of 25 feet for 300-foot
width to the head of the project via Sampit River cutoff. The side
channel and turning basin have a controlling depth of 7 feet.
Centerline surveys made in May 1954 showed a controlling depth
of 8.5 feet in the bypassed portion of Sampit River.
  The costs of the existing project to the end of the fiscal year
have been $4,615,904 for new work and $3,297,119 for mainte-
nance, a total of $7,913,023.
                                                 Cost and financial summary

                                                        Fiscal year ending June 30                                     Total to June
                                                                                                                      30, 1954, includ-
                                                                                                           15         ing fiscal years
                                          1950        1951              1952             1953              1954        prior to 19501

New work:
      Appropriated...--------            $400, 000   $480, 000 -..-.....             -------.-
                                                                                  ............                             $7, 061, 755
      Cost....----------------            578, 685    361, 337           $15, 013 ---------------------                     7, 061, 755
Maintenance:
      Appropriated- ----..                323, 997    366, 443          781, 898       $192, 077          $207, 649         3, 415, 508
      Cost...........----------------     319,056     370, 467         606, 475          370, 254          205, 299         23,411, 661
  1 Includes $2,445,852 for new work and $114,556 for maintenance for previous projects.
  2 Includes $15 cost in excess of prepayments.


                                        3. CHARLESTON HARBOR, S. C.
   Location. On the coast of South Carolina, about 15 miles
southerly of the midpoint of the coastline, 50 miles southwest of
Winyah Bay, S. C., and 80 miles northeast of the mouth of the
Savannah River. (See U. S. Coast and Geodetic Survey Charts
Nos. 1239 and 470.)
   Previous projects. Adopted by River and Harbor Acts of Au-
gust 30, 1852; June 18, 1878; August 11, 1888; March 3, 1899;
June 25, 1910; August 8, 1917; and July 18,1918.
   For further details, see page 1808, Annual Report for 1915;
page 579, Annual Report for 1926; page 562, Annual Report for
1938.
   Existing project. This provides for commercial purposes a
channel 35 feet deep, 1,000 feet wide from the sea to the inner end
of the jetties, thence 600 feet wide to Town Creek, thence 500
feet wide through Town Creek, thence 600 feet wide to the navy
yard, and thence 400 feet wide to Goose Creek, with a turning
basin 700 feet wide at the port terminals, together with a channel
30 feet deep, 600 feet wide in Cooper River around the east and
north sides of Drum Island; also an anchorage area 30 feet deep in
the water area between Castle Pinckney and Fort Moultrie; also a
channel in Shem Creek 10 feet deep and 110 feet wide from a
flared entrance from Hog Island channel to and including a turn-
ing basin 130 feet wide and 400 feet long with the upper end 250
feet upstream of the Mount Pleasant public wharf.
   The estimate of cost for new work (1954) exclusive of amounts
expended on previous projects, is $4,520,000. The latest (1954)
approved estimate for annual cost of maintenance is $668,400.
   The existing project includes the maintenance of two entrance
jetties completed in 1895 under previous projects. These jetties


          Sig 11-319-350
320                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

are of stone on log-mattress foundation, the north jetty 15,443
feet long and the south jetty 19,104 feet long; the distance be-
tween their axes at the outer end is 2,900 feet. The height as
originally built, except the submerged inner portions and the gap
left in the south jetty, was 12 feet above mean low water for the
greater part of their length.
   The project also provides for a 40-foot channel 1,000 feet wide
from the sea to the inner ends of the jetties, described above,
thence 600 feet wide to the south pier at the navy yard, and thence
1,000 feet wide to the commandant's wharf, at an estimated first
cost of $3,603,000 and $250,000 annually for maintenance, both
figures being additional to the estimates for the commercial proj-
ect given above, and that it be considered as a national defense
rather than a commercial measure and be prosecuted only as
found necessary in the interest of national defense.
   The mean tidal range is 5.2 feet, though this is increased to 7
or 8 feet under the influence of northeast winds or prolonged
storms.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                          Work authorized                                     Documents

June 18, 1878      2 jetties' .    __ __...     _._. _ _.--____              Annual Report, 1878, pp. 553-572.
Aug. 8, 1917       Increase in depth to 30 feet with width of 500 feet be-   H. Doc. 288, 62d Cong., 2d sess.
                     tween the jetties and 1,000 feet seaward thereof.
July 18, 1918      The 40-foot channel to the navy yard. (Act provided       H. Doc. 1946, 64th Cong., 2d sess.,
                      that the 40-foot channel should not be undertaken        pt. 1, pp. 21-29, 57, 58, and 61-63.
                     "until the proposed new drydocks at this navy
                     yard, carrying a depth of 40 feet of water over the
                    blocks, has been authorized." This dock was
                    authorized in the Naval Appropriation Act ap-
                    proved July 1, 1918 (40 Stat. L. 725).)
Jan.    21, 1927   Present project dimensions of the channels for com-       H. Doc. 249, 69th Cong., 1st sess.
                    mercial purposes, and for the present project widths      (Contains latest published maps.)
                    of the 40-foot channel which was authorized as a
                    national-defense measure.
Oct.    17, 1940   The 35-foot channel depth from the sea to the head        H. Doc. 259, 76th Cong., 1st sess.
                     of the project via Cooper River and Town Creek,
                    also a channel in Shem Creek to Mount Pleasant,
                     110 feet wide and 10 feet deep, including a turning
                     basin at the upper end.
Mar.     2, 1945   An anchorage area 30 feet deep in the water area be-      H. I)oc. 156, 77th Cong., 1st sess.
                     tween Castle Pinckney and Fort Moultrie.

1 Completed under previous projects.


   Recommended modifications of project. In June 1954, the Chief
of Engineers recommended further modification of the project to
provide for deepening the existing 30-foot channel around the
north and east side of Drum Island to 35-foot depth at an esti-
mated cost of $200,000.
   Local cooperation. This project authorized in the River and
Harbor Act of October 17, 1940 (H. Doc. 259, 76th Cong., 1st
sess.), is subject to the requirements that local interests furnish,
free of cost to the United States, suitable spoil disposal areas as
and when required for initial work and for subsequent mainte-
nance. All prior requirements have been fully complied with.
   Terminal facilities. Piers and slips extend for about 1 mile
along the eastern waterfront of the city of Charleston, and an
additional mile is covered by marginal wharves.          The South
Carolina State Ports Authority operates the terminal at Columbus
        RIVERS AND HARBORS-CHARLESTON,         S. C., DISTRICT   321
  Street, large piers near Market Street, and operates the beltline
  railway serving all wharves and warehouses, and connecting with
trunklines entering the city. Modern facilities are also at the
  Southern Railway coal pier and the wharves of the Standard Oil
  Co., the Charleston Shipyards, Inc., the Seaboard Air Line Rail-
road, the Southern Railway Co., the Concentration Warehouse and
  Compress Co., and the Charleston Tidewater Terminals, Inc.
    On Cooper River above the navy yard a compress and warehouse
company has a marginal wharf 750 feet long; the Texas Corp., the
Sinclair Refining Co., and the Cooper River Terminals, Inc., main-
tain piers at their properties; and the South Carolina State Ports
Authority operates a large terminal capable of berthing four
cargo vessels. The facilities are considered adequate for existing
commerce. For further details, see Port Series No. 13, revised
1950, Corps of Engineers.
    Operationsand results during fiscal year. The pipeline dredge
Admiral, by contract, performed maintenance dredging during
May and June 1954 in the inner harbor as follows: 34-foot depth
for project width at shoals 6A and Town Creek Channel; 34-foot
depth for 400-foot width at shoals 5A and 6, Cooper River Chan-
nel north of Drum Island; and 30-foot depth for 600-foot width at
shoal 6 in Cooper River Channel east and north of Drum Island,
including widening at bends, removing 1,190,935 cubic yards of
material at a cost of $311,312. The U.S. hopper dredge Gerig and
hired labor, during January and February 1954, performed main-
tenance dredging in the entrance channel to project depth for
800-foot width in a reach extending from the 35-foot contour in
the ocean to South Channel; thence project depth for 600-foot
width at shoal 7 in Cooper River and South Channel; and 30-foot
depth for project width at shoal 6C in Cooper River east of Drum
Island, removing 1,058,217 cubic yards of material at a cost of
$138,054. The pipeline dredge Cherokee, by contract restored
project dimension in Shem Creek during May 1954, removing
28,936 cubic yards of material at a cost of $9,365. Diking of
spoil areas on Daniel Island was completed during November 1953,
a total of 17,476 lineal feet of dike and 3,214 lineal feet of drain-
age ditch was completed at a cost of $40,542. Diking of the spoil
area on the north end of Drum Island was completed during
January to June 1954, a total of 12,289 lineal feet of dike was built
at a cost of $24,448. Diking of the spoil area on the south end of
Drum Island was started May 25, 1954, and at the end of the fiscal
year 2,450 lineal feet of dike had been built at a cost of $2,909.
    Several supplementary tests of improvements plans were un-
dertaken in the model of Charleston Harbor at the U. S. Water-
ways Experiment Station. All field and laboratory work was
completed, and work was undertaken on the preparation of a final
report on the comprehensive investigations. Costs in connection
with the model and prototype studies were $52,722.
    The cost of surveys and supervision was $12,447. The total cost
for the year was $591,702, for maintenance.
    Condition at end of fiscal year. The jetties protecting the
Entrance Channel across the bar were completed in 1895. The
jetties are described in the "Existing Project." The existing proj-
322            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

ect was completed during May 1949, except for the anchorage
area 30 feet deep in the water area between Castle Pickney and
Fort Moultrie.
   Surveys during the latter part of the fiscal year in the En-
trance, South and Cooper River Channels showed a controlling
depth of 35 feet for 800-foot width from the 35-foot contour in the
ocean to South Channel; thence 35-foot depth for 400-foot width
to the head of the project, except at shoal 6 C in Cooper River
north and east of Drum Island where the controlling depth is 29.2
feet for 700-foot width. An after dredging survey made in Shem
Creek during May 1954 showed a controlling depth of 10 feet for
90-foot width.
   The cost of the existing project has been $1,857,964 from regu-
lar funds and $57,813 from public works funds, a total of $1,915,-
777 for new work, and $6,640,550 from regular funds and $56,087
from public works funds, a total of $6,696,637 for maintenance; a
grand total of $8,612,414, exclusive of $600 contributed funds.
                                             Cost and financial summary

                                                    Fiscal year ending June 30                       Total to June
                                                                                                     30, 1954, includ-
                                                                                                     ing fiscal years
                                     1950          1951        1952        1953           1954       prior to 195012

New work:
   Appropriated       ... .....       ----------- ------------------------ ------------
                             ------------                                                                 $8, 502, 233
   Cost    ....--....----------.. -------
                                  .....        ----------------------------------     ------------          8, 502, 233
Maintenance:
   Appropriated-       _----_.     $759, 826     $667, 872    $609, 394   $531, 162      $561, 557          7, 115, 781
   Cost----------------             807, 980      370, 472     656, 277    734, 380       591, 697          7, 098,621

  1 Includes $6,586,455 for new work and $401,989 for maintenance for previous projects.
  2 In addition $600 for maintenance was expended from contributed funds.
  3 Includes $5 cost in excess of prepayments.
Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project---............____ ............ .. $2,604,200

                                            4. ASHLEY RIVER, S. C.
  Location. Rises near Ridgeville, S. C., and flows southeasterly
40 miles, uniting with the Cooper River to form the harbor of
Charleston, S. C. (See U. S. Coast and Geodetic Survey Charts
Nos. 1239 and 470.)
  Previous projects. The original project was adopted by the
River and Harbor Act of June 14, 1880. For further details see
page 1809, Annual Report for 1915, and page 566, Annual Report
for 1938.
  Existing project. This provides for a channel 30 feet deep at
mean low water and 300 feet wide from the mouth to the Stan-
dard wharf, 7.8 miles, suitably widened at bends and at the head
of the improvement; and for maintenance, to a depth of 12 feet
and a width of 100 feet, of the approach channel to the municipal
yacht basin. The mean tidal variation is about 5.2 feet.
  The cost of new work for the completed projects, exclusive of
amounts expended on previous projects, was $260,996.
  The existing project was authorized by the following River and
Harbor Acts:
               RIVERS AND HARBORS-CHARLESTON,                                                   S. C., DISTRICT                   323
       Acts                                Work authorized                                                   Documents

July 25,1912      Channel 20 feet deep and 240 feet wide up to Stand-                           Rivers and Harbors Committee
                    ard wharf.                                                                      Doc. 4. 62d Cong., 2d sess.
Aug. 26, 1937     Enlarging channel to present project dimensions and                           Rivers and Harbors Committee
                   for maintenance of entrance channel to Municipal                                Doc. 449, 74th Cong., 2d sess.
                   Yacht Basin                                                                    (Contains latest published map.)

   Local cooperation. Fully complied with.
   Terminal facilities. The facilities extend 51/2 miles above the
United States Coast Guard wharf adjacent to Tradd Street and in-
clude the wharves of the American Agricultural Chemical Co.,
Planters Fertilizer & Phosphate Co., Koppers Co., and the Vir-
ginia-Carolina Chemical Corp. The fertilizer company wharves
are equipped with mechanical unloading devices. These terminals
are considered adequate for existing commerce. At the municipal
yacht basin there are three docks of creosoted-timber construc-
tion for the accommodation of local and transient yachts. For
further details see Port Series No. 13, revised 1950, Corps of
Engineers.
   Operations and results during fiscal year. The pipeline dredge
Clinton, by contract, on June 14, 1954 commenced restoring safe
navigable dimensions in the lower 3 miles of the main channel,
and to the end of the fiscal year had removed 152,070 cubic yards
of material at a cost of $34,732.
   The total cost for the year was $34,732.
   Condition at the end of fiscal year. The existing project was
completed in 1940. A survey of the main channel at the end of the
fiscal year showed a controlling depth of 25 feet for 300-foot width
from its mouth to the highway bridge, about 3 miles, thence 14
feet to the head of the project. A survey of the entrance channel
to the municipal yacht basin during May 1954 showed a controlling
depth of 5.2 feet for 70-foot width.
   The costs at the end of the fiscal year have been $260,996 for
new work and $425,798 for maintenance, a total of $686,794. In
addition $700 from contributed funds were expended for main-
tenance.
                                               Cost and financial summary

                                                           Fiscal year ending June 30                                  Total to June
                                                                                                                      30, 1954, includ-
                                                                                                                      ing fiscal years
                                      1950               1951               1952             1953          1954         prior to19501
New work:
   Appropriated---------------....--------------------------------------------                                                $260, 996
      Cost           --------------------------------------------------------------------                                      260, 996
Maintenance:
      Appropriated ..-------...       $11, 631          $108, 231 ----------------------..                $115, 000            506,065
      Cost-----------------            13,216            108,231------------                                34,456            2425,522


  1Does not include $700 contributed funds.
  2   Includes $276 cost in excess of prepayments.


                                         5. SHIPYARD RIVER, S. C.
  Location. This waterway is a salt water tidal tributary of
Charleston Harbor, S. C. It has its source about one-half mile
below the United States navy yard, whence it flows southerly
about 3 miles and empties into Cooper River about three-fourths
324               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

mile above Drum Island. (See U. S. Coast and Geodetic Survey
Chart No. 470.)
   Previous projects. Adopted by River and Harbor Acts of July
25, 1912; March 3, 1925; July 3, 1930; August 30, 1935; and Au-
gust 26, 1937.
   For further details of previous projects, see page 610, Annual
Report for 1932, and page 463, Annual Report for 1944.
   Existing project. This provides for a channel 30 feet deep at
mean low water and 200 feet wide, widened at the entrance, from
deep water in Cooper River to the vicinity of the plant of the
Pittsburgh Metallurgical Co., with a turning basin 30 feet deep
opposite the Gulf Oil Corp. terminal and a turning basin 30 feet
deep at the upper end of the project. The mean tidal variation
is 5.2 feet.
   The cost of new work for the completed project, exclusive of
amounts expended on previous projects, was $487,824. The latest
 (1.954) approved estimate for annual cost of maintenance is
$132,500.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                         Work authorized                                      Documents

July    3, 1930   Channel depths of 12 and 20 feet_______-
                                                     ......__-___            Rivers   and Harbors       Committee,
                                                                               Doc.   13, 71st Cong.,   2d sess.
Aug. 20, 1935     28-foot channel from Cooper River to the Gulf Oil          Rivers   and Harbors       Committee,
                    Corp.'s terminal, and the deepening of the channel        Doc.    43, 73d Cong.,    2d sess.
                    above that point to 20 feet from the depth of 12 feet
                    previously authorized without local cooperation.
Aug. 26, 19371    Enlargement of the channel to a depth of 30 feet and       Rivers and Harbors Committee,
                    a width of 200 feet up to the Gulf Oil Corp.'s ter-        Doc. 38, 75th Cong., 1st sess.'
                    minal, with a turning basin 30 feet deep at the latter
                    point.
Mar. 2, 1945      Extension of the existing 30-foot channel to vicinity        H. Doc. 93, 79th Cong., 1st sess.
                    of the Pittsburg Metallurgical Co. plant, with a
                    turning basin at the upper end.

  1 Included in Emergency Relief Administration program, May 28, 1935.
  2 Contains latest published map.


   Local cooperation. Fully complied with.
   Terminal facilities. In the lower three-quarter mile of the
channel are the large marginal wharves of the Gulf Oil Corp. and
the Shipyard River Terminal Co., the latter handling chiefly fer-
tilizer and fertilizer materials. These wharves accommodate deep-
draft, ocean-going vessels. On the upper channel is the Pittsburgh
Metallurgical Co.'s wharf for handling ores.
   Operations and results during fiscal year. The pipeline dredge
Pullen, by contract, restored project dimensions over the entire
project during November 1953 and January 1954, removing
484,107 cubic yards of material at a cost of $113,852.
   The cost of surveys and supervision was $861; the cost of
stream gaging was $3,675 and the cost of hydroclimatic network
was $3,150. The total costs during the year were $121,539 for
maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted during June 1951. After dredging surveys during January
1954, showed a controlling depth of 30 feet throughout the
project.
            RIVERS AND HARBORS-CHARLESTON, S. C., DISTRICT                                                           325
   The costs to the end of the fiscal year have been $456,260 from
regular funds and $31,564 from Emergency Relief funds, a total
of $487,824 for new work; and $1,449,871 from regular funds for
maintenance, a total of $1,937,695.
                                       Cost and financial summary

                                                Fiscal year ending June 30                                 Total to June
                                                                                                          30, 1954,1 includ-
                                                                                                          ing fiscal years
                                   1950       1951               1952          1953         1954            prior to1950
New work:
   Appropriated__---_         $375, 000                                                   ---                     $491, 974
   Cost                             4, 162   $370, 838                                                              491, 974
Maintenance:
   Appropriated    -               69, 100     66, 811          $124, 513      $92, 388    $123, 933              1, 453, 009
   Cost-_                          38, 997    107, 289           122, 213       93, 943     121, 516             21, 449, 848

  1 Includes $4,150 for new work for previous projects.
  2 Includes $23 cost in excess of prepayments.


   6. EMERGENCY OPERATIONS-PROTECTING, CLEARING AND
       STRAIGHTENING CHANNELS OF NAVIGABLE WATERS,
       PROJECTS NOT REQUIRING SPECIFIC AUTHORIZATION
   Under Section 3 of the River and Harbor Act approved March
2, 1945, an allotment of $2,500 from regular funds and an addi-
tional sum of $2,500 of contributed funds were received for clear-
ing a 1,150-foot reach next upstream from the head of the improved
authorized project channel in Shem Creek to restore its approxi-
mately natural dimensions of 10-foot depth at mean low water for
a bottom width of 90 feet, thereby providing safe navigation for
commercial vessels operating on the creek upstream of the im-
proved project channel.
   Operationsand results during fiscal year. The pipeline dredge
Cherokee, by contract, during May 1954 restored natural dimen-
sions of 10-foot depth for 90-foot bottom width in an 1,150-foot
reach of Shem Cheek next upstream from the head of the im-
proved project channel, by removing 19,438 cubic yards of mud,
sand, and silt at a cost of $2,500 from regular funds and $2,500
contributed funds.
   Condition at end of fiscal year. Natural channel dimensions of
10-foot depth for 90-foot bottom width obtained in the 1,150-foot
reach of Shem 'Creek next upstream from the improved project
channel.
   The costs to the end of the fiscal year for maintenance have
been $6,902 from regular funds and $2,500 from contributed
funds, a total of $9,402.
                                       Cost and      finanriat     summary
                                             United States Funds

                                               Fiscal year ending June 30                                  Total to June
                                                                                                          30, 1954, includ-
                                                                                                          ing fiscal years
                               1950           1951               1952          1953         1954            prior to 1950

Maintenance:
   Appropriated                -    $598-----         -------       -_----   -------
                                                                                  :             $2, 500              $6, 902
   Cost                                                                                          2, 500               6, 902

  Note: Does not include $2,500 contributed funds.
326                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                  CONTRIBUTED                    FUNDS

                                                            Fiscal year ending June 30                                         Total to June
                                                                                                                              30, 1954, includ-
                                                                                                                              ing fiscal years
                                        1950             1951              1952                1953            1954             prior to 1950

Maintenance:
                 ------------------------------------------------
   Appropriated.......                                                                                            $2, 500                 $2, 500
   Cost---------    -----------------------------------------------                                                2, 500                  2, 500


                  7. TABLE OF INACTIVE NAVIGATION PROJECTS

                                                                      For last                Cost to June 30, 1954              Estimated
                                                                     full report                                                   amount
                      Name of project                                     see                                                     required
                                                                       annual              Con-             Operation                to
                                                                       report           struction              and               complete
                                                                        for-                               maintenance

1.   Abbapoola Creek, S. C.....-------------------                     1947       ----------------------------                          $17,    000
2.   Beresford Creek, S. C.           ___......................        1947        ......-.......        . ----                          32,    000
3.   Congaree River, S. C.1.......---
                             . .                        .               1950                  $364, 824          $541, 860               170,    000
4.   Edisto River, 8. C.1--         5 _- - - - - - - - -
                                                                        1938                      33, 103              900             (')
5.   Great Pee Dee River, S. C.                            _ .         1950                    183, 712          269, 673             (s)
6.   Little Pee Dee River, S. C.1 2_.....                __-----_      1919                      19, 550          25, 650                 31,   000
7.   Lumber River, N. C. & S. C.'--------------                        1897                      19, 000 --------------                   16,   000
8.   Lynch River and Clark Creek, S. C.' 2.......                      1910                       9, 500 _                            (S)
9.   Mingo Creek, S. C.1...----------------------                      1950                      29, 050           7,150              (S)
10. Russell Creek, 8. C.....................-..                          1947-          -       -----         -        -         -        24, 000
11. Salkahatchie River, S. C.' 2                    -_   --....         1896                     15, 841                               (s)
12. Santee River, S. C.--.....----              --------                1950                     99, 750           178, 544            (')
13. Snagging and clearing under authority of
       sec. 3 of the River and Harbor Act approved
       March 2, 1945-------------------------                 1949                    .....              .       4,402                 ()
14. Waccamaw River, N. C. & S. C.5-----------1950                                              262, 814        197, 813                ()
15. Wateree River, S. C.1_                    __----------- - 1940                              60, 000        151, 784                (s)
16. Yadkln River, N. C.1 2___....___._____.__             .   1892                             102, 809 ---------------                      5, 000

   1No commerce reported.
   2 Abandonment recommended in 1926 (H.Doc. 467, 69th Cong., 1st sess.).
  ' Completed.
   ' Revoked in fiscal year 1950, $598.
  A Curtailment recommended in 1926 (H.Doc. 467, 69th Cong., 1st sess.).

             8. TABLE OF INACTIVE FLOOD CONTROL PROJECTS

                                                                      For last            Cost to June 30, 1954                  Estimated
                                                                     full report                                                     amount
                     Name of project                                    see                                                       required
                                                                      annual               Con-             Operation                to
                                                                      report            struction              and                complete
                                                                       for-                                maintenance

1. Edisto River, S. C................------------------------           1947                   1$6,  379 ------------.-.               $288, 600
2. Yadkin River, N. C..............__.....__...                         1952                    131, 500      "..    ....            13, 900, 000


  Note: The sum of $3,621 was revoked during the fiscal year 1948.


                                     9. GENERAL INVESTIGATIONS
   Examinations and surveys. The costs and expenditures of
navigation and flood control studies during the year were $1,812
and $378, respectively, a total of $2,190.
   The unexpended balance June 30, 1954, of $375 for navigation
studies, plus an anticipated allotment of $3,500 for flood control
studies, a total of $3,875 will be applied during the fiscal year
1955, to the payment of expenses to be incurred under these
headings.
           FLOOD CONTROL-CHARLESTON, S. C., DISTRICT           327
   Collection and study of basic data. The costs and expenditures
for collection and study of basic data during the year were $295.
The unexpended balance June 30, 1954, of $321, plus an antici-
pated allotment of $3,120, a total of $3,441 will be applied during
the fiscal year 1955 for the payment of expenditures to be incurred
in connection with the collection and study of basic data.
   IMPROVEMENTS OF RIVERS AND HARBORS IN THE
             SAVANNAH, GA., DISTRICT

   This district comprises a very small portion of southwestern
North Carolina, western South Carolina, eastern Georgia, and a
small portion of northeastern Florida embraced in the drainage
basins tributary to the Atlantic Ocean between Port Royal Sound,
S. C., and the harbor at Fernandina, Fla. It includes the Atlantic
Intracoastal Waterway between these points.
                                                               IMPROVEMENTS

                            Navigation                                                       Flood control
                                                                    Page                                                    Page
1. Atlantic Intracoastal Water-                                             5. Savannah River Basin, Ga. and
     way between Norfolk, Va.,                                                   S. C --------...........                     341
                                                                                                  ...... ---------...............
     and the St. Johns River, Fla.                                          6. Hartwell Reservoir, Savannah
     (Savannah District)-----                 ......----.....       329          River Basin, Ga. and S. C.....               341
2. Savannah Harbor, Ga.....--..-------........                      332     7. Clark Hill Reservoir, Savannah
3. Savannah River below Augus-                                                   River Basin, Ga. and S. C ....               343
     ta, Ga---.....---.....-----------...........................   337                     .........................
                                                                            8. Macon, Ga----------------                      344
4. Inactive navigation projects......                               340     9. Inactive flood control projects..              345
                                                                           10. General investigations...--------............. 345

1. ATLANTIC INTRACOASTAL WATERWAY BETWEEN NORFOLK,
VA., AND THE ST. JOHNS RIVER, FLA. (SAVANNAH DISTRICT)
   Location. This section of the waterway connects Port Royal
Sound, S. C., with Fernandina, Fla. (See U. S. Coast and Geodetic
Survey Charts Nos. 838-841, inclusive.) For Cumberland Sound
to St. Johns River section, see page 331.
   Previous projects between Savannah, Ga., and Fernandina,
Fla. Previous improvements in this section were authorized by
River and Harbor Acts of August 2, 1882; August 11, 1888; July
13, 1892, and March 3, 1905.
   For further details, see pages 1814, 1821-1823, Annual Report
for 1915, and page 585, Annual Report for 1938.
   Existing project. This provides for a waterway 12 feet deep at
mean low water and not less than 90 feet wide between Port Royal
Sound, S. C., and Savannah, Ga., for a waterway 12 feet deep at
mean low water, with widths of 90 feet in land cuts and narrow
streams and 150 feet in open waters, between Savannah, Ga., and
Fernandina, Fla., to follow in general the alinement of the existing
waterway, except for such cutoffs or other changes in the route
as may be found desirable and justified by the resultant benefits
to navigation; and for a suitable anchorage basin at Thunderbolt,
Ga. The total distance from Port Royal Sound, S. C., to Fernan-
dina, Fla., is 165 miles. The project also provides for the follow-
ing: (1) removing logs and snags from Generals Cut, Ga.; (2)
an alternative and more protected route 7 feet deep at mean low
water from Doboy Sound to Brunswick Harbor, via Darien River,
Three Mile Cut, Altamaha River, One Mile Cut, Buttermilk Sound,
Mackay River, Back River, Clubbs Creek, and Plantation Creek;
                                                                                                                  329
330      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

 (3) a protected channel 7 feet deep at mean low water and 75 feet
wide around St. Andrews Sound, extending from the main route of
the waterway in Jekyll Creek through Jekyll Sound, Little Satilla
River, Umbrella Cut, Umbrella Creek and its south branch,
through Dover Cut to Dover Creek, thence up Dover Creek and
through a narrow neck of land to Satilla River, thence through a
land cut south of Todd Creek and through Floyd Creek to the main
route of the waterway in Cumberland River; (4) a channel 5 feet
deep at mean low water and 50 feet wide to connect Baileys Cut to
Satilla River and Dover Creek, Ga.; (5) a loop 8 feet deep at mean
low water to reach the wharves at the southern end of Cumberland
Sound; (6) an alternative route 9 feet deep and 150 feet wide in
that part of Frederica River, Ga., not now traversed by the main
route, at no additional cost to the United States. In general, the
work is to be accomplished by dredging, supplemented by training
walls as necessary.
   The mean tidal range between Port Royal, S. C., and Fernan-
dina, Fla., is from 6 to 8 feet, with fluctuations from 11/2 to 21/2
feet, due to winds and lunar phases.
   The project has been completed at a cost of $763,599.20 for new
work, exclusive of amounts expended under previous projects.
The latest (1954) approved estimate for annual cost of mainte-
nance is $300,000.
                  RIVERS AND HARBORS-SAVANNAH,                               GA., DISTRICT                331
    The existing project was authorized by the following River and
Harbor Acts:

       Acts                         Work authorized                                     Documents


                      BEAUFORT,   S.C., TO SAVANNAH,    GA., SECTION

June 3,1896       Route No. 2 adopted----___---...     ..                    Doc. 295, 53d Cong., 3d sess.
                                                                      -H.H------
Mar. 3,1899       Route No. 1 adopted_-__-------.... ----------------      Do.'
July 25,1912      Provided for Archer Creek (this route now aban- H. Doc. 513, 62d Cong., 2d sess.
                    doned).

                    SAVANNAH, GA., TO FERNANDINA, FLA., SECTION
July 13,1892.     Original 7-foot channel.................._........-..-     H. Doc. 41, 52d Cong., 1st sess.
Mar. 3,1905       Provided for Skidaway Narrows_ __.....__.....       .      H. Doc. 450, 58th Cong., 2d sess.
July 25, 1912     Incorporated alternative routes previously improved        H. Doc. 1236, 60th Cong., 2d sess.'
                    as separate projects and the auxiliary channels.
                         CUMBERLAND SOUND, GA., AND FLA., TO
                            ST. JOHNS RIVER, FLA., SECTION
Mar.    4, 1913   For a channel 7 feet deep and 100 feet wide ...........-   H. Doc. 898, 62d Cong., 2d sess.
Aug.    8, 1917   Consolidation of the 3 sections, shown above, into
                   "Waterway between Beaufort, S. C., and St. Johns
                   River, Fla."
                    BEAUFORT, S. C., TO CUMBERLAND SOUND, GA.,
                                    AND FLA., SECTION

Mar. 2,1919       Removing logs and snags from Generals Cut._...._...        H. Doc. 581, 63d Cong., 2d sess.'
   Do.......      Improving Back River to provide a channel 7 feet           H. Doc. 1391, 62d Cong., 3d sess.
                    deep and 150 feet wide.
Mar.    3, 1925   Channel 75 feet wide between Beaufort, S. C., and          S. Doc. 178, 68th Cong., 2d sess.
                    Savannah, Ga.
July 3,1930       Channel from Baileys Cut to Dover Creek...........         S. Doc. 43, 71st Cong., 2d sess.'
Aug. 26,1937      A 7-foot protected channel around St. Andrew Sound.        Senate committee print, 74th
                                                                                Cong., 1st sess.'
              A 12-foot channel between Beaufort, S. C., and Sa-
    Do--.......                                                              Rivers and Harbors Committee
                vannah, Ga., via Beaufort River and Port Royal                 Doc. 6, 75th Cong., 1st sess.
                Sound.
June 20,1938 A 12-foot channel between Savannah, Ga., and                    H. Doe. 618, 75th Cong., 3d sess.
                Fernandina, Fla., various cutoffs; and anchorage
                basin at Thunderbolt, Ga.
Mar. 2, 1945  An alternative route 9 feet deep and 150 feet wide in          H. Doc. 114, 77th Cong., 1st sess.
                that part of Frederica River, Ga., not now trav-
                ersed by the main route, at no additional cost to the
                United States.

  1Contains   latest published maps.


   Local cooperation. Fully complied with.
   Terminal facilities. Exclusive of terminal facilities at the ports
of entry, this improvement serves numerous wharves, some of
which are open to the public on equal terms. These facilities are
considered ample for existing commerce.
   Operations and results during fiscal year. None. Office engi-
neering, miscellaneous reports, condition surveys, and inspections
with Government plant and hired labor cost $15,117.
   Condition at end of fiscal year. The main 12-foot channel of
the existing project was completed in 1941. The 7-foot protected
route around St. Andrew Sound was completed in 1939. The train-
ing walls and closure dams were completed in 1912, and are in
satisfactory condition. All other improvements were completed
in 1932.
   Since March 1943, the previous route of the Intracoastal Water-
way, through the westerly end of South Channel and the northerly
end of Wilmington River, has been superseded by the route
through the Elba-McQueens Island Cut and the northwesterly end
of St. Augustine Creek. The former route will be maintained to
332               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

a depth of 7 feet for traffic moving from Savannah to points
south of Savannah Harbor and for northbound traffic from south-
ern points below Savannah Harbor to Savannah, Ga. In April
1954, the main route had a controlling depth of 12 feet or more ex-
cept as follows: Ramshorn Creek (Mile 568.0 to 569.4), 11 feet;
Walls Cut (Mile 572.2), 11 feet; Fields Cut (Mile 573.5 to 573.7),
10 feet; St. Augustine Creek (Mile 578.5), 11 feet; Wilmington
River (Mile 579.5 to 579.9), 11 feet; Florida Passage (Mile 607.8),
11 feet; Doboy Sound (Mile 649.4), 11 feet; Rockdedundy River
(Mile 652.6 to 653.2), 10 feet; Little Mud River (Mile 653.2 to
656.0), 11 feet; Altamaha Sound (Mile 658.5), 11 feet; Butter-
milk Sound (Mile 662.8), 8 feet; St. Simon Sound (Mile 677.5),
10 feet; and Jekyll Creek (Mile 683.5), 11 feet.
  The costs under the existing project to June 30, 1954, were
$763,599 for new work and $4,159,705 for maintenance, a total
of $4,923,304.
                                             Cost and financial summary

                                                        Fiscal year ending June 30                               Total to June
                                                                                                                30, 1954, includ-
                                                                                                                ing fiscal years
                                      1950            1951            1952               1953        1954         priorto 19502

New work:
   Appropriated        ......------------ -------------------------------------                       ----------       $958, 096
   Cost _.---------             ------------  ------------ ----------             ---       ---------------------       958,096
Maintenance:
   Appropriated                    $149, 600      $174, 421         -$46, 900           $233, 263     $7, 000         4, 297, 980
   Cost-_-.----    .--                30, 160       174, 830            82, 530          224, 718    115, 099         4, 294, 484


  1 Plus $18 pending adjustment.
  2 Includes $194,497 for new work and $134,798 for maintenance for previous projects.


                                      2. SAVANNAH HARBOR, GA.

   Location. The entrance is 75 statute miles south of Charleston
Harbor, S. C., and 70 statute miles north of Brunswick Harbor,
Ga. (See U. S. Coast and Geodetic Survey Chart No. 440.)
   Previous projects. Adopted by specific acts of Congress May
18, 1826; March 3, 1855; August 7, 1856; and by River and Har-
bor Acts of March 3, 1873; June 23, 1874; September 19, 1890;
June 3, 1896; and June 13, 1902. For further details, see page
1810, Annual Report for 1915, and page 578, Annual Report for
1938.
   Existing project. This consists of eliminating the regulating
dam across South Channel, relocating the inland waterway in the
vicinity, further extending training walls, revetments, and jetties,
and providing for-
   a. Channels 36 feet deep and 500 feet wide across the ocean bar
between stations 245 and 194, 9.7 miles; thence 34 feet deep and
generally 400 feet wide, increased to 550 feet opposite the Atlantic
Coast Line terminals, between stations 194 and 103, with a turn-
ing basin 34 feet deep at the Mexican Petroleum Corp. refinery,
17.2 miles; thence 30 feet deep and 300 feet wide to the foot of
Kings Island, 0.6 mile; thence 30 feet deep and 200 feet wide to the
vicinity of the Atlantic Creosoting Co. terminal, with a turning
basin 30 feet deep, 2.1 miles; thence 30 feet deep and 200 feet wide
to a point 1,500 feet below the Atlantic coastal highway bridge,
         RIVERS AND HARBORS-SAVANNAH, GA., DISTRICT            333
with a turning basin 30 feet deep at the upper end, 1.45 miles; a
total length of 31.05 miles; and with such modifications thereof
as the Secretary of the Army and the Chief of Engineers may con-
sider desirable.
   b. Enlargement of contracted portions of the channel and such
enlargements of the channel as may be necessary to smooth out
abrupt changes and for otherwise improving the hydraulic condi-
tions with a view to reducing shoaling.
   c. The maintenance of the channels, anchorage basins, enlarge-
ments at Drakies Cut, Kings Island, West Broad and Barnard
Streets, mooring dolphins near Fort Oglethorpe, and the existing
training walls and jetties.
   The plane of reference is mean low water, which varies for
different parts of the harbor. The mean range of tide is 7.6 feet
at the upper end of the harbor and 7.1 feet at the lower end. Ex-
treme ranges are about 10.5 feet and 11 feet, respectively. Tides
below mean low water occur 6 or 7 times a month and minus 2-foot
tides occur from 6 to 8 times a year. The improvement has in-
creased the mean tidal range by about 2.8 feet at the upper end.
   The estimate of cost for new work, revised in 1954 is $8,957,000
exclusive of amounts expended on previous projects. The latest
 (1954) approved estimate for annual cost of maintenance is
$1,500,000.
334             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

    The existing project was authorized by the following River and
Harbor Acts:
     Acts                          Work authorized                                  Documents

June 23, 1874 Regulating works....                                 .---------------------------
                                                                         Annual Report, 1873, p. 747.
Mar. 2,1907   Tentative provision for a 26-foot channel from the H. Doc. 181, 59th Cong., 1st sess.
                quarantine station to the Seaboard Air Line Ry.
                bridge.
June 25,1910 Definite provision for the 26-foot channel.........
July 25, 1912 A 21-foot channel from the Seaboard Air Line Ry. H. Doc. 563, 62d Cong., 2d sess.
                bridge to the foot of Kings Island.
Aug. 8,1917 A 30-foot depth from the sea to the quarantine station. H. Doc. 1471, 64th Cong., 2d sess.
Jan. 21, 1927 A 21-foot channel above Kings Island-..............        H. Doec. 261, 69th Cong., 1st sess.
    Do....... Channel 30 feet deep, with general width 500 feet,         H. Doc. 262, 69th Cong., 1st sess.
                from the ocean to the quarantine station, thence
                26 feet deep, general width 400 feet, to the Seaboard
                Air Line Ry. bridge, thence 21 feet deep and 300
                feet wide to Kings Island.
              Widening at West Broad and Barnard Sts.; anchor-
                age basin; mooring dolphins; regulating dam across
                South Channel; relocation of the inland waterway;
                dredging Drakies Cut to 13 feet; widening to 525
               feet at Kings Island; extension of training walls,
               revetments, and jetties. Consolidation of projects
               relating to Savannah Harbor.
July 3, 1930 Channel 26 feet deep and 300 feet wide from the Sea- S. Doc. 39, 71st Cong., 1st sess.
                board Air Line Ry. bridge to the foot of Kings
                Island.
Aug. 30, 1935 Authorized the 30-foot project and eliminated from         H. Doec. 276, 73d Cong., 2d sess.
               the project: (a) the regulating dam across South
                Channel; (b) the relocation of the inland waterway;
               and (c) the further extension of training walls,
               revetments, and jetties.                                                                    1
Mar. 2, 1945 Deepening the channel and turning basin above the H. Dec. 283, 76th Cong., 1st sess.
                Seaboard Air Line Ry. bridge from 26 to 30 feet and
               widening the channel opposite the Atlantic Coast
               Line terminals to a maximum of 550 feet for a
               length of 5 000 feet.
Nov. 7,1945 Deepening the channels to 36 feet deep and 500 feet          H. Doc. 227, 79th Cong., 1st sess.'
               wide across the ocean bar between stations 245 and
               194; 34 feet deep and generally 400 feet wide, in-
               creased to 550 feet opposite the Atlantic Coast Line
               terminals, between stations 194 and 103, with a
               turning basin 34 feet deep at the Mexican Petro-
               leum Corp. refinery; and with such modifications
               thereof as the Secretary of War and the Chief of
               Engineers may consider desirable.
July 24, 1946 Extending channel 30 feet deep, 200 feet wide, up- H. Doc. 678, 79th Cong., 2d sess.'
               stream from Atlantic Creosoting terminal to a
               point 1,500 feet below the Atlantic coastal highway
               bridge, with turning basin 30 feet deep at upper end.

1 Contains the   latest published maps.

   Recommended modification of project.                              In house Document No.
110, 83d Congress, 1st session, it was recommended that the exist-
ing project be modified to provide for a channel 34 feet deep and
400 feet wide, from the upper end of the presently authorized
34-foot channel in the vicinity of the Mexican Petroleum Corp.
wharf to a distance upstream of about 1.6 miles, and to widen the
recommended channel at the upper end to form a turning basin
34 feet deep, 600 feet wide, and 700 feet long with the necessary
approaches. The estimated cost is $414,900 for the improvement
with no additional maintenance cost to that now authorized.
   Local cooperation. The River and Harbor Acts approved No-
vember 7, 1945, and July 24, 1946, impose the conditions that
local interests shall: (1) Provide free of cost to the United States,
all lands and rights-of-way required for the initial construction
and subsequent maintenance when and as required; (2) hold and
save the United States free from damages due to the construction
works. To date, the mayor and aldermen of the city of Savannah
         RIVERS AND HARBORS-SAVANNAH, GA., DISTRICT            335
have by appropriate resolution agreed to act as local assurer in
securing spoilage easements in Savannah Harbor. The city has
authorized the Savannah District Authority to conduct negotia-
tions and secure necessary easements. In keeping with the reso-
lution, the city has furnished the Government with indemnity
bond in the amount of $70,000 applicable over a term of 5 years
to assure payment of the eventual condemnation cost for securing
perpetual easements on 4 tracts of land. On request of the mayor
of the city of Savannah, condemnation proceedings were filed in
the United States District Court for the Southern District of
Georgia on December 11, 1952, for 1 parcel of land comprising
460 acres; and proceedings were filed in the United States District
Court for the Eastern District of South Carolina on December 23,
1952, for 3 parcels of land comprising a total of 6,667 acres.
Orders of possession were granted in both instances.           The
Savannah District Authority furnished two 20-year easements on 2
tracts of land located on Hutchinson Island, Ga. The Government
was also furnished with extensions of short term or temporary
easements on 2 parcels of land which will expire in March and
June 1955. Short term easements were accepted in lieu of long
term or perpetual easements pending disposition of above con-
demnation proceedings. The proceedings pending in the United
States District Court for the Southern District of Georgia, wherein
adverse decision was rendered, necessitated the filing of an appeal
to the Circuit Court. Pending a decision by the Circuit Court the
order of possession will remain in force. Trial was scheduled in
August 1954 to determine a just compensation for the 3 tracts of
land involved in proceedings in the District Court of South
Carolina.
   Terminal facilities. There are 51 piers and wharves to serve
waterborne commerce of the port. These facilities, with the use
of dolphins, have a combined berthing space of 33,800 feet, with
depths of water alongside ranging from zero to 32 feet at mean low
water. Six of these terminals are opposite the city on Hutchinson
Island; the remaining 45 are on the south side of the river between
3 miles below and 6.8 miles above the center of the city. Thirteen
piers and wharves are operated by railroads, 5 by oil companies, 2
by coal companies, 1 by a cotton warehouse company, 5 by ship re-
pair companies, 1 by a local steamship company, 7 by various
private industries, and 1 by the Georgia Ports Authority. The
site of a former shipyard has been acquired by the city of
Savannah for future development of industrial sites. There is a
large municipal wharf at the center of the city. All have railway
and highway connections, except the six on Hutchinson Island
which have rail connections only. The facilities are considered
adequate for existing commerce. For further details, see Port
Series No. 14, Corps of Engineers (revised 1946).
   Operations and results during fiscal year. New work: Channel
excavation, by contract, within the limits of the Seaboard Air
Line Railroad bridge was completed during August 1953, at a cost
of $5,983. The sum of $3,445 was charged during the year for
work accomplished during the previous fiscal year in connection
with the alterations to the Seaboard Air Line Railroad bridge.
 336            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

This amount will reflect as a credit to the alterations to the bridge.
Condition surveys cost $190. The total cost for new work was
 $9,618.
    Maintenance: The United States hopper dredge Langfitt oper-
ated on the bar channels during the period September 1-30, 1953,
removing 504,022 cubic yards of material at a cost of $101,743.
The contract dredge Admiral operated in the inner harbor during
the period July 1, 1953, to September 26, 1953, removing 3,128,593
cubic yards of material at a cost of $543,220. The United States
pipeline dredge Henry Bacon operated in the inner harbor during
the period December 1, 1953, to June 30, 1954, removing 3,338,610
cubic yards of material at a cost of $456,553. Increasing height
and cross section of existing spoil impounding dikes cost $37,755.
Dragging and sweeping the inner harbor channels cost $13,948.
Miscellaneous reports, inspections, condition and operation studies
cost $45,232. Included in this amount is $7,307 for the model
study of Savannah Harbor. Inspections, surveys, and layouts for
channel work cost $2,742. The total cost for maintenance was
$1,201,193.
   The following tabulation shows the name of plant, sections of
the harbor over which work was performed, yardage removed,
and method of dredging:

                                                                                         Cubic yards removed

                       Name of channel                             Station to station
                                                                                           Regular dredging

Dredge Langfitt:
   Tybee Knoll __-._------------------------------------                      196, 206                 257, 380
   Tybee Roads-------------------------------------------                     214-238                  246, 642

Dredge Admiral:
    City Front_-------------------------------------------                    122-127                  935, 026
   WreckS------------- ------------------- ----------                         127-136                  964, 481.
   5-Fathom Irole_  -------------------------------------
   Obstrietions-------------------------------------------
                                                                              136-140
                                                                              140-146
                                                                                                       490, 654
                                                                                                       288, 031
   Upper Flats------------------------------------------                      157-162                  177, 277
   Lower Flats----------------------------------------------                  12-167                   152, 846
   Quarantine ------------    -----------------------------                   191-194                  120, 278

Dredge Bacon:
   Whitehall _         ._.88-91                                                                          51, 866
   Kings Island -------------------------------------------                   100-106                   234, 309
   Marsh Island -----------------                                             108-114                   398, 231
   City Front     ---------       -----------------------                     118-125                1, 266, 859
   Wrecks--..--   -------------------------------------------                 127-136                   897, 572
   5-Fathom Hole----------------------------------                 ------     136-140                   426, 441
   Obstructions__- ___----------------------------------......                140-142                    63, 332

     Total cubic yards removed_ ............---------------   ---------------------                  6, 971, 225



   Condition at end of fiscal year. The existing project was about
97 percent completed. The 30-foot channel and extension of the
harbor above the Seaboard Air Line Railroad bridge was com-
pleted February 5, 1948. The 34-foot channel was completed
January 7, 1953. The 36-foot bar channel was completed April
15, 1951. The previous 30-foot project from the sea to old quar-
antine station was completed in 1930, and the rest of the 30-foot
channel in 1937. That part of the previous 26-foot channel from
the Seaboard Air Line Railroad bridge to the foot of Kings Island
was completed in 1931; the rest, from the foot of Kings Island to
the Atlantic Creosoting wharf, including the turning basin oppo-
                  RIVERS AND HARBORS-SAVANNAH, GA., DISTRICT                                                               337
site the Savannah Sugar Refinery's wharf, in 1937. Cross-tides
channel was closed with a hydraulic fill in 1937. The anchorage
basin and mooring dolphins near Fort Oglethorpe were completed
in 1926; of the 10 dolphins originally constructed, all have been
destroyed. The channel enlargements at Drakies Cut, Kings Is-
land, and at West Board and Barnard Streets, were completed in
1931, 1929, and 1924, respectively. Whitehall channel training
wall was completed in 1929 and was replaced by three spur dikes
in 1937; these spur dikes are in good condition. Fig Island train-
ing wall was raised and extended in 1940 and is in good condition.
Long Island training wall hydraulic fill was completed in 1931 and
other training walls and jetties prior to 1929, and are in fair con-
dition. The work remaining to complete the project consists of
construction of bank protection and extension of permeable dikes
in the upper reaches of the harbor.
   In June 1954, least depths in midchannel for half-project width
at mean low water were 35 feet from the sea to Blinker 24 (in the
vicinity of Fort Pulaski) ; thence 29 feet to the Mexican Petroleum
Corp.; thence 27 feet to the wharf of the Southern Paperboard
Corp.; thence varying from 27 feet to 10 feet at the extreme upper
limits of the harbor. The turning basins had the following con-
trolling depths: Kings Island Turning Basin, 31 feet; Whitehall
Turning Basin, 30 feet; and Port Wentworth Turning Basin, 21
feet in the lower half and 10 feet in the upper half.
   The costs under the existing project to June 30, 1954, have been
$8,694,243 for new work and $22,994,384 for maintenance, a total
of $31,688,627.
                                                Cost and financial summary

                                                         Fiscal year ending June 30                              Total to June
                                                                                                                30, 1954, includ-
                                                                                                                ing fiscal years
                                        1950          1951           1952           1953            1954         prior to 19502
New work:
     Appropriated ....-------- $405, 000             $540, 000     $245, 000     -$21, 564        -$2, 900          $15, 968, 598
     Cost .      .....----------------400, 946        512, 418      219, 372         15, 700          9, 618         15, 954, 627
Maintenance:
     Appropriated             ..--------. 747, 350    619, 853       887, 400     1, 289, 439     1, 310, 000         23, 569, 885
     Cost ...-----       ..---- .         786, 076    635, 478       920,194      1,121, 640     11, 196, 887         23, 288, 972

   1 Plus $4,306 pending adjustment.
   2 Includes $7,260,384 for new work and $298,894 for maintenance for previous projects.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-.....-....                                                      $13, 971
                                                                                                              ....---------------
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955..-------.........           ------------------------------------------------                                     13,971
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project...........................................................-----------------------------.. 248,800

                   3. SAVANNAH                       RIVER BELOW AUGUSTA,                               GA.
  Location. This river is formed by the confluence of the Tugaloo
and Seneca Rivers on the northwestern part of the South Carolina-
Georgia boundary line. It flows southeast 314 miles, forming the
boundary line, and empties into the Atlantic Ocean 16.6 miles be-
low Savannah, Ga. (See U. S. Geological Survey maps of South
Carolina and Georgia.)
  Previous project. Adopted by the River and Harbor Act of
 338                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

March 3, 1881. A subdivision between new work and mainte-
nance is not possible. For further details see page 1813, Annual
Report for 1915 and page 581, Annual Report for 1938.
    Existing project. Provides for a channel 9 feet deep and 90
feet wide (at ordinary summer flow, which corresponds to a dis-
charge of 5,300 second-feet at August, Ga., with the Clark Hill
power plant in operation), from the upper end of Savannah Har-
bor to the head of navigation at Augusta, 3 miles above Fifth
Street Bridge, about 199 miles. The improvement is to be ob-
tained by construction of one lock and dam at New Savannah
Bluff, use of contraction works, closure of cutoffs, bank protec-
tion, dredging, removal of snags, overhanging trees and wrecks,
and open-river regulation. The mean tidal variation at the mouth
of the river is 7.1 feet. The freshet variation above the normal
pool level (elevation 114.5 mean sea level) of the New Savannah
Bluff lock and dam at the head of the improvement is ordinarily
about 13 feet with an extreme of 34 feet. Pertinent data for the
lock and dam are given in the following table:
                                                 Lock and dam at New Savannah Bluff
Nearest railroad station......-------------...................----...........---.Augusta, Ga., 13 miles.
Distance above mouth of river-.._...-.........................-... 203 miles.
Lock dimensions                          __............ ................... .................. ... 56 by 360 feet.
Lift of lock---..........................................---..........------.........-----           .......-------... 12.7 feet.
Depth on lower miter sill at low water.............-----------...... 12.3 feet.
Depth on upper miter sill at normal pool level-........... 13.5 feet.
Character of foundations                                                                                                 Piles in sand, clay, and gravel.
                                                                                                                      .------------.-.
Kind of dam....-----                                  ...--......................------------------------------..        Fixed. 1
Type of construction-                              ---.----..-...
                                                             .           .             ...          -----                Concrete.
Completed ............--------------------------------                                                                   1937.
Total cost------......-------.....--..........--------------------.......................... $1,473,812.10.
  1   Five steel vertical-lift crest control gates, set between concrete piers and resting on concrete sill.

  The estimate of cost of new work, revised in 1954, is $6,982,000,
exclusive of amount expended on previous projects. The latest
(1954) approved estimate for annual cost of maintenance is $398,-
000 including $32,500 for operating and care.
  The existing project was authorized by the following River and
Harbor Acts:
       Acts                                     Work authorized                                                       Documents


Sept. 19, 1890        For a 5-foot channel ....               ---------------------------
                                                                      ,_               H.                  Doc. 255, 51st Cong., 2d sess.,
                                                                                                       and Annual Report, 1890; p. 1328.
June 25, 1910         Special improvement by bank-protection work of 20                               H. Doc. 962, 60th Cong., 1st sess.
                        or 25 miles of the river immediately below Augusta.
July     3, 1930      The present 6-foot channel project and the lock and                             H. Doc. 101, 70th Cong., 1st sess.
                dam.
Aug. 30,19351 Provision made for locating the lock and dam at New                                     Senate committee print, 73d Cong.,
                Savannah Bluff.                                                                        2d sess.
Aug. 26, 1937 Conditions of local cooperation modified......------------                              Rivers and Harbors Committee
                                                                                                         Doc. 39, 75th Cong., 1st sess.2
May 17, 1950          Provides for a 9-foot channel---.........................                          Doc. 6, 81st Cong., 1st sess.


  1 Included in the Public Works Administration program, Sept. 27, 1933.
  2 Contains latest published map.

  Local cooperation. The project provides that local interests
furnish, without cost to the United States, all necessary rights-of-
way and spoil disposal areas for the new work and subsequent
maintenance, when and as required; hold and save the United
States free from any damage resulting from construction and
         RIVERS AND HARBORS-SAVANNAH, GA., DISTRICT              339
maintenance of the improvement; and provide and maintain ade-
quate terminal and transfer facilities, including a suitable public
terminal at Augusta, Ga., open to all on equal terms.
    Terminal facilities. The only water terminals served by this
improvement are at Augusta and at or near Savannah. The city
of Augusta owns and operates, on equal terms to all, a wharf and
warehouse; a short distance below this terminal the Pure Oil Co.
has a terminal (storage capacity of 27,500 barrels) for berthing
and discharging oil barges; and just outside the eastern city
limits is the Merry Bros. Brick & Tile Co.'s terminal. This com-
pany also has terminal facilities at Savannah. At Savannah there
is one municipal wharf, suitable for berths for river steamers,
open to the public on equal terms. In addition, there are extensive
facilities at Savannah, privately owned, for oceangoing and smaller
vessels. Along the river there are numerous natural landings
without wharves or railway connections. The terminal facilities
are considered ample for existing commerce.
    Operations and results during fiscal year. None. Office engi-
neering, miscellaneous reports, condition surveys, and inspections
with Government plant and hired labor cost $3,938.
   The minimum daily flow of the river at New Savannah Bluff
Lock and Dam during the fiscal year 1954 was 5,300 cubic feet
per second. Minimum weekly flow was 5,590 cubic feet per second.
The minimum daily and weekly flows of record prior to 1954 were
1,105 and 1,220 cubic feet per second, respectively.
    Power plants with storage on the river are Clark Hill Dam, a
Federal multipurpose project 22 miles above Augusta; the Stevens
Creek plant, 9 miles above Augusta; and the 6 plants of the Georgia
Power Company on the headwaters. From the time that filling
of the Clark Hill Reservoir was begun in December 1951 until the
second generating unit was placed in operation in February 1953,
a flow of about 3,000 cubic feet per second or better was maintained
95 percent of the time. Since that time the flow releases from Clark
Hill have been those resulting from the operation of the project
in the interest of flood control, navigation and hydroelectric power,
which provides a minimum flow of 5,300 cubic feet per second at
the Butler Creek gage for navigation.
   Maintenance (operating and care): The lock and dam at New
Savannah Bluff was operated, and ordinary repairs and improve-
ments were made to the structure and appurtenant works at a cost
of $26,132.
   The total cost of work from regular funds was $30,070, of which
$3,938 was for maintenance and $26,132 for operating and care.
   Condition at end of fiscal year. The existing project was about
39 percent completed. The lock and dam at New Savannah Bluff
was completed in 1937 and is in good repair. In general, the open-
channel works are in fair condition; a few of the structures are
in need of repairs; however this work will be accomplished by
the authorized modification to the existing project. The control-
ling depth was 6 feet or greater 100 percent of the fiscal year.
This depth corresponds to a height of 5 feet on the Butler Creek
gage and to a discharge of 5,300 second feet. The work remain-
ing to be done to complete the project is as follows: deepen the
 340                   REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

channel to 9 feet and widen to 90 feet between the upper end of
Savannah Harbor and the present head of navigation at Augusta,
Ga.
   The cost on the project to June 30, 1954, was as follows:

                                                                                                              Regular         Public works
                                                                                                               funds             funds                Total
Costs:
    Construction__
                 -_                                                  -             ---                        $1, 117, 237      $1, 634, 562          $2, 751, 799
    Operation and maintenance                         --------------------.---                                 1, 777, 632 ..--------------            1, 777, 632
    Operation and care__--.                                --                    -___ _                           472, 116 -         -                    472, 116
          Total   ------------------                            --         -----------                         3, 366, 985        1, 634, 562          5, 001, 547



                                                           Cost and financial summary

                                                                             Fiscal year ending June 30                                         Total to June
                                                                                                                                               30, 1954, includ-
                                                                                                                                                ing fiscal years
                                                 1950                     1951               1952                 1953            1954           priorto 1950
New work:
   Appropriated                        ---- -----------------                       ------------------------------------                             $2, 845, 279
      Cost-                            -           -----                 -----                 ------------                                            2, 845, 279
Maintenance:
   Appropriated- .                $110, 100                              $76, 431           $52, 000              $71, 000        $20, 000             2, 253, 489
   Cost-----       ....---------- 114, 195                                77, 122            49, 701               70, 289        130, 066            22, 249, 743

  1 Plus $4 pending adjustment.
      2
    Does not agree with Form 3011 for June 30, 1954, accrued expenditures, by $251, amount carried as stock
June 30, 1953.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project_ .................. .............. $4, 230,200

                                       4. INACTIVE NAVIGATION PROJECTS

                                                                                         For last               Cost to June 30, 1954              Estimated
                                                                                     full report,                                                   amount
                         Name of project                                                   see                                                      required
                                                                                         annual                  Con-          Operation               to
                                                                                         report               struction           and               complete
                                                                                          for-                                maintenance
1. Altamaha, Oconee and Ocmulgee Rivers, Ga.'                                            1951                     $60, 847       $938, 135            (2)
2. Brunswick Harbor, Ga_-------------------                                              1953                3 2, 221, 121   3 42, 613, 646         1, 789, 900
3. Darien Harbor, Ga.'_ _                                                                1950                   5199, 723           44, 183      Completed
4. Fancy Bluff Creek, Ga.'--------------                                                 1935                       8, 000           4, 200         Do.
5. Fernandina Harbor,' Fla__                                                             1952                  3, 286, 818       6 899, 403            283, 200
6. Sapelo Harbor, Ga.- 8 --        -                                                     1929                      17, 906          17, 094      Completed
7. Satilla River, Ga.'                                                                   1951                       9, 452          37, 793         Do.
8. St. Marys River, Ga. and Fla., and North                                              1951                      15, 688          56, 860         1, 080, 300
      River, Ga.                             7
9. Savannah River above Augusta, 7Ga. 8_                                                 1929                     69, 600            5, 870         (9)
10. Savannah River at Augusta, Ga. --                                                     1929                  0 200, 556           17, 444      Completed

  1Channel     adequate for commerce.
   2 Existing project is such that percentage of completion cannot be stated.
   3 Includes $102,516 expended from public works funds: $97,521 for construction and $4,995 for operation and
maintenance. In addition, $10,000 was expended from contributed funds for construction.
   4 Includes $991 expended for general supervision during fiscal year 1954.
   5 Includes $54,929 expended on Doboy Bar.
   6 Includes $1,370 expended for general supervision during fiscal year 1954.
   7 Project recommended for abandonment in H. Doc. No. 467, 69th Cong., 1st sess.
   8No commerce reported.
   9 About 84 percent completed. Owing to construction of 2 power dams which have submerged much of
the work under the present and former projects, this improvement cannot be completed as originally planned.
  toIn addition, $185,000 was expended from contributed funds: $172,151 for construction and $12,849 for
operation and maintenance.
                   FLOOD CONTROL-SAVANNAH, GA., DISTRICT                                                           341
                5. SAVANNAH               RIVER BASIN, GA., AND S. C.
   Location. The works covered by this project consist of a series
of 11 dams and reservoirs on the Savannah River and its tribu-
taries in Georgia and South Carolina. (See U. S. Geological Sur-
vey Maps of Georgia and South Carolina.)
   Existing project. The Flood Control Act approved December
22, 1944, approved the general plan for the comprehensive devel-
opment of the Savannah River Basin for flood control and other
purposes recommended in House Document 657, 78th Congress, 2d
session, and authorized the construction of the Clark Hill Reservoir
on the Savannah River in.Georgia and South Carolina as the initial
step of this development at an estimated cost of $35,300,000. The
Flood Control Act approved May 17, 1950, authorized $50,000,000
to be appropriated for the construction of the Hartwell Reservoir
in the general plan for the comprehensive development of the Sa-
vannah River basin.
   Following is a list of the dams and reservoirs included in the
comprehensive plan. The estimated costs given were revised in
1954.
                                           Dams and reservoirs

                                                                                   Estimated cost

                Name                           River              Con-                          Reloca-
                                                               struction         Lands        tions and        Total
                                                                                              rights-of-
                                                                                                 way.
Clark Hill, Ga. and S. C..---.---------      Savannah_--       $66, 087, 500   $6, 684, 300   $5, 534, 200   $78, 306, 000
Hartwell, Ga. and S. C ____________           -do      _____    65, 377, 000   10, 495, 000   14, 765, 000    90, 637, 000
                           ...
Goat Island, Ga. and S. C------      -----
                                     .        .. do.....        31, 400,000        500, 000    4, 500, 000    36, 400, 000
Middleton Shoals, Ga. and S. C-....       -.      do--.
                                                  .----- -      15, 500, 000       200, 000       800, 000    16, 500, 000
Chattooga Units (4), Ga. and S. C- .-.       Chattooga___       39, 800, 000       300, 000    1, 600, 000    41, 700, 000
Tallow Hill, Ga _______________ _ _          Broad__ ....       36, 000, 000    1, 200, 000    1, 800, 000    39, 000, 000
Anthony Shoals, Ga.._-----------------        ____do    _.      15, 400, 000    1, 000, 000    1, 700, 000    18, 100, 000
Newry-Old Pickens, S. C---..---------.     Keowee_       __     25, 200, 000    2,100,000      2, 200;000     29, 500, 000


  Local cooperation. None required.
  Clark Hill and Hartwell Reservoirs are the only projects in the
comprehensive plan that have been authorized for construction.
Individual reports on the two reservoirs are given in the following
pages.

6. HARTWELL RESERVOIR, SAVANNAH RIVER BASIN, GA. AND S. C.
   Location. The site of the Hartwell Dam is on the Savannah
River 305 miles above its mouth and 89 miles upstream from Au-
gusta, Ga. At full-power-pool elevation, the reservoir will extend
7.1 miles up the Savannah River to the confluence of the Tugaloo
and Seneca, 41 miles up the Tugaloo, 27 miles up the Seneca to the
mouth of upstream Little River, S. C., thence 2 miles up Little
River to the Newry site, and 7 miles up the Keowee to the Old
Pickens site, and 8 miles up Deep Creek. (See U. S. Geological
Survey maps of Georgia and South Carolina.)
   Existing project. The Flood Control Act approved May 17,
1950, authorized $50,000,000 to be appropriated for constructing
the Hartwell Reservoir in the general plan for the comprehensive
development of the Savannah River basin approved in the Flood
Control Act of December 22, 1944, in addition to the authorization
342            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

for project construction in the act of December 22, 1944, recom-
mended in House Document No. 657, 78th Congress, 2d session.
This project, as now planned, provides for a gravity-type concrete
dam 1,925 feet long with earth embankments at either end, 9,566
feet long on the Georgia side and 6,283 feet long on the South
Carolina side. The total length of the dam will be about 17,774
feet, with a roadway over the top 24 feet wide. The main dam
will consist of two nonoverflow concrete sections, 542 feet long on
the Georgia side and 475 feet long on the South Carolina side, a
gravity-type concrete spillway 568 feet long equipped with 12
tainter gates 40 by 35 feet, in the channel, and an intake section
340 feet long with the powerhouse on the Georgia side of the river.
The maximum height of the concrete section will be 204 feet above
river bottom and the earthfill embankments will vary in height to
a maximum of about 106 feet. At full-power-pool elevation 660
the reservoir will provide a total storage of 2,562,600 acre-feet of
which 1,427,600 acre-feet will be usable. The initial power instal-
lation will be 180,000 kilowatts, and the ultimate will be 300,000
kilowatts.
   The estimated cost, revised in 1954, is $65,377,000 for construc-
tion, $10,495,000 for lands, and $14,765,000 for relocations and
rights-of-way, a total of $90,637,000.
   Local cooperation. None required.
   Operations and results during fiscal year. Design memoran-
dums on the construction bridge and diversion works were ap-
proved by the Office, Chief of Engineers on July 17, 1953, and
August 11, 1953, respectively. Design memorandums for the tur-
bines and governors and for the tailrace were submitted Septem-
ber 18, 1953, and April 1, 1954, respectively, and were approved
by the Office, Chief of Engineers on February 19, 1954, and June
29, 1954, respectively. Design memorandum on the single line
electrical diagram for the power plant was submitted October 15,
1953.
   The cost was $119,921.
   Condition at end of fiscal year. Advance planning was about
32 percent completed. Contract for reservoir mapping was about
98 percent completed.
   The cost for new work under the existing project to June 30,
1954 was $799,618.
                                        Cost and financial summary

                                               Fiscal year ending June 30                    Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                                 1950        1951        1952        1953        1954        prior to 1950
New work:
   Appropriated........------------------
                              ...........   $170, 000   $172, 600   $373, 000    $96, 000           $811, 660
   Cost ---------------------------           71,945     234,925     372, 827   1119, 974            799, 671

  1 Minus $53 pending adjustment.


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954..-..............     $11, 011
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955-----                                                        11, 011
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project .......-...............                  89, 825, 400
             FLOOD CONTROL-SAVANNAH, GA., DISTRICT               343
   7. CLARK HILL RESERVOIR, SAVANNAH RIVER BASIN, GA.
                        AND S. C.

  Location. The work covered by this project is a dam and reser-
voir on the Savannah River and its tributaries in Georgia and South
Carolina. (See U. S. Geological Survey maps of Georgia and South
Carolina.)
    Existing project. The Flood Control Act approved December
22, 1944, approved the general plan for the comprehensive devel-
opment of the Savannah River basin for flood control and other
purposes as recommended in House Document No. 657, 78th Con-
gress, 2d session, and authorized the construction of the Clark Hill
Reservoir on the Savannah River in Georgia and South Carolina
at an estimated cost, revised in 1954, of $78,306,000. The latest
 (1954) approved estimate for annual cost of maintenance and
operation is $534,000.
    The Clark Hill Reservoir is on the Savannah River, Ga., and
S. C., about 22 miles upstream from Augusta, Ga. The dam is
5,680 feet long, consisting of a concrete section 2,282 feet long
with a maximum height of 200 feet, and a controlled spillway sec-
tion 1,096 feet long. The concrete section is flanked on the west
by a rolled-earth embankment extending 2,069 feet to the abut-
ment, and on the east by a similar embankment 1,329 feet long.
The reservoir has a total storage capacity of 2,900,000 acre-feet,
of which 390,000 acre-feet will be reserved for flood control and
1,340,000 acre-feet will be used for the storage of water for gen-
erating hydroelectric power. The power installations will consist
of seven generating units of 40,000 kilowatts each, a total of 280,-
000 kilowatts.
   Local cooperation. None required.
    Operations and results during fiscal year. The powerhouse
structure was completed, and with minor exceptions, all interior
floors, tiling, trim, and finish were completed. Three additional
generating units were placed in productive operation on October
6, 1953, January 25, 1954, and May 27, 1954. The seventh and last
generating unit was practically completed, with commercial opera-
tion expected shortly after the close of the fiscal year. All acces-
sory electrical and mechanical powerhouse equipment had been
installed. Because of a change in the disposition of electric power,
plans for switching and metering equipment in the switchyard
were revised. The scroll case for station service turbine No. 1
failed after several months of operation, and a new scroll case was
installed. Generating of power was in progress.
   Operation and maintenance of the project by hired labor was
initiated during the year.
   The total cost of the work for the fiscal year was $4,121,386, of
which $3,789,333 was for new work and $332,053 was for opera-
tion and maintenance.
   Condition at end of fiscal year. The project, commenced in
November 1945, was 98.5 percent completed. All lands had been
acquired either in fee or by condemnation. All relocation had been
completed. Access roads to the reservoir were under construction.
   Six generating units were in commercial operation, and the
344            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

seventh unit was practically completed. The switchyard, formerly
considered complete, required the installation of additional equip-
ment because of a change in plans for power distribution.
  The costs under the existing project to June 30, 1954, have been
$77,102,260 for new work and $332,054 for maintenance, a total of
$77,434,314.
                                       Cost and financial summary

                                                Fiscal year ending June 30                                  Total to June
                                                                                                           30, 1954, includ-
                                                                                                           ing fiscal years
                                1950         1951             1952           1953             1954           prior to 1950
New work:
   Appropriated     -      $13, 000, 000 $19, 800, 000 $17, 200, 000      $4, 079, 000     $3, 426, 200        $77, 204, 014
   Cost__                   14, 432, 062  17, 860, 994  14, 894, 524       9, 408, 207     13, 711, 791         77, 102, 260
Maintenance:
    Appropriated                                                               15, 000        346, 500              361, 500
    Cost                                                                      - -            2330, 999              330, 999

   1 Does not agree with Form 3011 by $77,542. This was the credit balance of the Project Office on June 30
1953, and not considered in the total cost of permanent work to end of last fiscal year. (In accordance with
instructions on back of Form 1239 FY 1953). Line 3, column for 1954 and the total column worked in accord
ance with instructions on back of form. The last column is total allotment less unexpended balance on
June 30.-Form 3011.
  2 Plus $1,055 pending adjustment.

Other new work data:
    Appropriated for succeeding fiscal year ending June 30, 1955     $2, 170, 000
    Unobligated balances available for succeeding fiscal year ending
        June 30, 1955 --.....                        ...............-..         ... .- .           ....-     2, 170,000

                                           8. MACON, GA.
   Location. This project is on the west bank of the Ocmulgee
River and extends from the Fifth Street Bridge at Macon, Ga.,
downstream 13,000 feet, thence westward from the river to the
Southern Railway embankment, a total of 5.5 miles. The city of
Macon, Ga., is 205 river miles above the junction of the Ocmulgee
and Oconee Rivers, which form the Altamaha River 137 miles from
the Atlantic Ocean. (See U. S. Geological Survey map of Georgia.)
   Existing project. The existing project was authorized by the
Flood Control Act approved July 24, 1946. (See H. Doc. 560, 79th
Cong., 2d sess.) This provides for increasing the height and cross
section of the existing levee, which is 2.4 miles long, and con-
structing an extension to that levee for 3.1 miles, with appurtenant
structures. The project was completed October 13, 1950, and
turned over to local interests January 5, 1951, for operation and
maintenance. The total cost for the completed work was $363,-
580.49.
   Local cooperation. Fully complied with.
   Operations and results during fiscal year. Due to a minor
construction deficiency, which was unforeseen at the time of com-
pletion of the project, the Office, Chief of Engineers directed that
the project be reopened, and under date of April 2, 1954 issued an
allotment for $26,515. The cost for engineering and design was
$169 for new work.
   Condition at end of fiscal year. The project was reopened.
The total cost to June 30, 1954 was $363,750.
                   FLOOD CONTROL-SAVANNAH, GA., DISTRICT                                                       345
                                     Cost and financial summary

                                              Fiscal year ending June 30                              Total to June
                                                                                                     30, 1954, includ-
                                                                                                     ing fiscal years
                              1950         1951              1952        1953           1954           priorto 1950

New work:
   Appropriated        _     $184, 000                --    $45,420                     $26, 515             $390, 095
   Cost_                      209, 617    $102, 248               4                          165              363,645

  1 Plus $105 pending adjustment.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954      .........      $26, 450
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955                  .
                        --......   .      .      .       .      .       .      26, 450

                  9.   INACTIVE FLOOD                      CONTROL          PROJECTS

                                                        For last        Cost to June 30, 1954           Estimated
                                                      full report,                                       amount
                Name of project                            see                                           required
                                                        annual          Con-         Operation              to
                                                         report       struction         and             complete
                                                          for-                      maintenance
1. Augusta, Savannah River, Ga----------------_            1941         $643, 016   -------------      Completed
2. Emergency flood-control work under author-              1949                            $6, 531        Do
    ity of the Flood Control Act approved
    August 18, 1941, as amended.
3. Snagging and clearing under authority of sec.           1950            8,772                           Do.
     2 of Flood Control Act approved August 28,
     1937.



                           10. GENERAL INVESTIGATIONS
   Examinations and surveys. There were no funds appropriated
for examinations and surveys during the fiscal year, and no work
was done. The unexpended balance on June 30, 1954, was $405.
Additional funds are not required for the fiscal year 1955.
   Collection and study of basic data. Noncooperative stream
gaging-stream flow data: One stream gage (stage only) which is
not in the cooperative program was in operation on the Altamaha
River at Charlotte, Georgia during the fiscal year. This gage has
been in operation by the district since 1925, and because of its loca-
tion below the forks of the Altamaha River has been and continues
to be an important flood reporting station.
   Analysis of basic data-storm studies: During the year about 50
percent of the uncompleted storm program of the district was
accomplished.
   Flood emergency studies: Revision of the flood emergency man-
ual was about 50 percent completed June 30, 1954.
   The total cost during the year was $3,055. The unexpended bal-
ance June 30, 1954, $428, plus an allocation of $2,300, a total of
$2,728, will be applied to expenses incurred under this heading
during the fiscal year 1955.
       IMPROVEMENT OF RIVERS AND HARBORS IN THE
              JACKSONVILLE, FLA., DISTRICT
   This district comprises a portion of south-central Georgia and
all of peninsular Florida except a small northeastern portion, em-
bracing the watersheds tributary to the Atlantic Ocean and the
Gulf of Mexico from, but not including, the harbor of Fernandina,
Fla., to and including the Aucilla River. It also includes Puerto
Rico, the Virgin Islands of the United States, and other nearby
islands.
                                                IMPROVEMENTS

                      Navigation                                        Navigation-Continued
                                                    Page                                                         Page
1. Atlantic Intracoastal Water-                                  sahatchee River to Anclote
      way between Norfolk, Va.,                                                                                     384
                                                                  River, Fla ..---------------............................
      and the St. Johns River, Fla.                     11.     Charlotte Harbor, Fla................               387
       (Jacksonville District)............          347 12.     Tampa Harbor, Fla....................               389
2. Jacksonville Harbor, Fla....-------......       349 13.     Withlacoochee River, Fla------..........            396
3. Oklawaha River, Fla-------...-..--...........   354 14.     Removing the water hyacinth
4. Intracoastal Waterway, Jack-                                  from navigable waters in the
      sonville to Miami, Fla............            359           State of Florida-----------...................... 399
5. Canaveral Harbor, Fla.............              363 15.     Inactive navigation projects......                  401
6. Fort Pierce Harbor, Fla-------............      367
7. Port Everglades Harbor, Fla.....                369                Flood control
8. Miami Harbor, Fla....................           373
9. Okeechobee Waterway, Fla......                  378 16. Central and Southern Florida ...                     402
10. Intracoastal Waterway, Caloo-                       17. General investigations..............--------..       411

1. ATLANTIC INTRACOASTAL WATERWAY BETWEEN NORFOLK,
VA., AND THE ST. JOHNS RIVER, FLA. (JACKSONVILLE DISTRICT)

   Location. This section includes that part of the Intracoastal
Waterway between the southerly limit of Fernandina Harbor, Fla.,
at the junction of Lanceford Creek and Amelia River, and the St.
Johns River, Fla. (See U. S. Coast and Geodetic Survey Chart No.
577.)    (For Beaufort, S. C., to Cumberland Sound section, see
p. 331.)
   Previous projects. The first project for the improvements of
that part of the waterway was authorized by the River and Harbor
Act of May 23, 1828, and modified by River and Harbor Act of
June 23, 1874. For further details see Annual Report for 1915,
page 1823, and Annual Report for 1938, page 605.
   Existing project. This provides for dredging and maintaining
a channel 12 feet deep, with widths of 90 feet in land cuts and
narrow streams and 150 feet in open waters, following in general
the alinement of the existing waterway from Fernandina Harbor
to St. Johns River, about 21.9 miles, with a cutoff in Kingsley Creek
just north of the Seaboard Air Line Railroad bridge, and with such
additional cutoffs or other changes in the adopted route as may be
found desirable and justified by the resultant benefits to naviga-
tion. The mean range of tide is 6.1 feet at Fernandina and 3.8 feet
in the St. Johns River, with fluctuations from 1.5 to 3 feet, due to
winds and lunar phases.
                                                                                                      347
348             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   The actual cost of new work was $263,659, excluding amounts
expended under previous projects. The latest (1954) approved
estimate for annual cost of maintenance is $13,000.
   The existing project was authorized by the following River and
Harbor Acts:
    Acts                         Work authorized                                  Documents
Mar. 4, 1913    For a channel 100 feet wide and 7 feet deep  -.
                                                            _-_-.....   H. Doc. 898, 62d Cong., 2d sess.
June 20, 1938   For a channel 12 feet deep with present authorized      H. Doc. 618, 75th Cong., 3d sess.
                 widths and including a cut-off in Kingsley Creek,        (Contains the latest published
                 subject to the provision of additional cutoffs or        maps.)
                 changes in routing upon the approval of the Secre-
                 tary of War.


   Local cooperation. Fully complied with.
   Terminal facilities. There are no terminal facilities along this
section of the Intracoastal Waterway.
   Operationsand results during fiscal year. Maintenance: Dredg-
ing by contract to restore project depth over shoals at the Sisters
Creek bridge was begun February 8, and completed March 2, 1954.
Contract dredge Ideal removed 34,537 cubic yards of material at a
cost of $10,150. Hired labor surveys, inspections, and reports
throughout the fiscal year cost $673.
   The total costs for the fiscal year were $10,823 for maintenance.
   Condition at end of fiscal year. A 7-foot channel, dredged be-
tween October 1913 and February 1915, was deepened to 12 feet
with present authorized widths between November 1940 and Sep-
tember 1941, thereby completing the existing project. The length
of the waterway was reduced 2.4 miles between May and October
1943 by making five cutoffs and widening bends at three localities.
To safeguard navigation through bridge openings and to permit
breaking tows when tidal conditions are adverse, 14 protective and
10 tieup dolphins have been constructed at the Sisters Creek bridge
at the southerly entrance to the waterway, and 8 protective and 10
tieup dolphins have been constructed at the Kingsley Creek
bridges, about 4 miles south of Fernandina. At the Kingsley
Creek bridges, three of the four center protective dolphins, one on
the north side and two on the south side, have been destroyed.
According to surveys in July 1951 and August and September
1952, the controlling depth is 12 feet.
   The total costs under the existing project to June 30, 1954, have
been $263,659 for new work and $842,835 for maintenance, a total
of $1,106,494.
          RIVERS AND HARBORS-JACKSONVILLE,                                            FLA., DISTRICT                    349
                                     Cost and financial summary

                                                  Fiscal year ending June 30                                   Total to June
                                                                                                              30, 1954, includ-
                                                                                                              ing fiscal years
                              1950              1951           1952            1953            1954             prior to 19501

New work:
   Appropriated_                                                $ _,__
                                            _--------___-------...-_
                                                      -                   -,                      _$361,                   225
   Cost- - - - -    -     -    ---      -   -          -   -          -    -    -      -   -          -361,                225
Maintenance:
                      ---
   Appropriated- -_----.                        $1, 671        $50, 750         $4, 950        $10, 900                842, 950
   Cost    --
          -........-...-         $242               439          4, 684         54, 225        210, 838                842, 850


  1 Includes $97,566 for new work for previous project.
  2Differs from "Operation and results during fiscal year" by -$15.            Pending adjustment.

                          2. JACKSONVILLE                       HARBOR, FLA.
    Location. The St. Johns River rises in the marshes of Brevard
County, Fla., near the east coast, and flows northwesterly to Jack-
sonville, thence easterly into the Atlantic Ocean, 122 miles south
of Savannah River. Its total length is about 285 miles. (See U. S.
Coast and Geodetic Survey Chart No. 577.)
   Previous projects. Six appropriations for surveys and experi-
mental dredging on the bar were made from 1852 to 1878. Projects
for permanent improvement were adopted by the River and Har-
bor Acts of June 14, 1880, and June 3, 1896. For further details
see page 1823, Annual Report for 1915, and page 607, Annual Re-
port for 1938.
   Existing project. This provides for (1) A channel 34 feet deep
from the ocean to Commodore Point via a cutoff channel from St.
Johns Bluff (Fulton) to Dame Point and via Terminal Channel
along the west bank of the river to Commodore Point, and thence
30 feet to the Florida East Coast Railway bridge at Jacksonville,
with widths of 800 feet at the entrance and between the jetties,
from 900 to 1,200 feet in Pilot Town Cut, from 1,050 to 1,335 feet
in Mayport Cut, generally 500 feet in the St. Johns Bluff-Dame
Point Cutoff, 1,200 feet at Dame Point, 590 feet in Terminal Chan-
nel (with the westerly edge 60 feet from the new pierhead-bulk-
head line), from 400 to 900 feet in other cuts, increasing to as much
as 1,115 feet at bends, and 300 feet in Arlington Cut, which is 30
feet deep and generally parallel to Terminal Channel; (2) a depth
of 24 feet between that depth contour and the pierhead line at Jack-
sonville from Hogan Creek to the foot of Laura Street; (3) a depth
of 28 feet to within 60 feet of the pierhead line in the area between
the foot of Laura Street and the St. Elmo W. Acosta Bridge (for-
merly Duval County highway bridge) ; (4) a navigation and flood-
way channel 26 feet deep and 200 feet wide along the south side of
the Commodore Point terminals, terminating in deep water at each
end; (5) an approach and mooring basin 20 feet deep, 1,300 feet
350         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

long at the 20-foot depth contour and 600 feet long at the pierhead
line, in front of the Naval Reserve Armory in South Jacksonville;
and (6) construction of training walls and revetments.
   All depths are referred to local mean low water. No dredging is
to be done within 60 feet of a pierhead line, except at the Naval
Reserve Armory. Natural depths of 34 feet or more, for adequate
width, exist in midchannel from Commodore Point to the Florida
East Coast Railway bridge at Jacksonville.
   Two converging rubblestone jetties, built at the entrance under
a previous project, are maintained under the existing project. The
north jetty is 14,300 feet long, and the south jetty is 11,183 feet
long. The jetties are parallel and 1,600 feet apart for 4,022 feet
from the sea ends. Stone training walls have been built at seven
localities, involving about 7 miles of this class of structure. Stone
revetments at five localities provide about 3.7 miles of shore pro-
tection. The training walls and revetments are located between
Dame Point and Wards Bank, near the inner ends of the jetties.
About 4 miles of those structures are located along the shores of
the old channel which has now been replaced by the Dame Point-
Fulton Cutoff.
   The length of section included in the project is 26.1 miles via
the cutoff channel. The mean tidal range is 5.3 feet on the bar,
4.9 feet at Mayport, 2.6 feet at Dame Point (12 miles above the
entrance), and 1.1 feet at Jacksonville (St. Elmo W. Acosta
Bridge). The extreme range varies from about 9 feet on the bar
to about 1.5 feet at Jacksonville. Strong northeasterly winds raise
the water level about 2 feet at Mayport and Jacksonville. Strong
southwesterly winds lower the water about 1.5 feet at Mayport and
1 foot at Jacksonville.
   The estimate of cost for new work, approved in 1954, is $11,-
856,000 exclusive of amounts expended on previous projects. The
latest (1954) approved estimate for annual cost of maintenance is
$300,000.
              RIVERS AND HARBORS-JACKSONVILLE,                                FLA., DISTRICT              351

The existing project was authorized by the following River and
Harbor Acts:

       Acts                           Work authorized                                   Documents

                          ST. JOHNS RIVER, FLA. OPPOSITE THE CITY OF
                                        JACKSONVILLE

Mar. 2,1907       A depth of 24 feet at mean low water between the           H. Doc. 663, 59th Cong., 1st sess.
                   24-foot curve and the pierhead line at Jacksonville
                   from Hogan Creek to the Florida East Coast Ry.
                   bridge.
                                     ST. JOHNS RIVER, FLA.

June 14, 1880     Jetties at the entrance (maintenance only; new work        Annual Report for 1879, pp. 767-792.
                    completed under a previous project).
June    3, 1896   Extension of jetties, etc. (maintenance of jetties only;   H. Ex. Doc. 346, 53d Cong., 3d sess.
                    new work completed under a previous project).             and Annual Report for 1895, pp.
                                                                              1586-1604.
June 25,1910      Main channel, 30 feet deep at mean low water, and in       H. Doc. 611, 61st Cong., 2d sess.
                   general 300 feet wide (via Arlington Cut), increas-
                   ing to as much as 600 feet at bends and through
                   the jetties; for an anchorage basin at Mayport,
                   800 feet in width beyond the channel limits and for
                   training walls and revetments, all subject to modi-
                   fication in detail by the Chief of Engineers.
                   ST. JOHNS RIVER, FLA., JACKSONVILLE TO THE OCEAN

June    5,1920Consolidation of the above two projects to form a Specified in act.
                single project.
July 3,1930   Widening the bend at Dame Point (to 900 feet).         H. Doc. 483, 70th Cong., 2d sess.
Aug. 30, 1935 Widening Drummond Creek, Trout Creek, and Six          Senate committee print, 74th Cong.
                Mile Creek Cuts to 400 feet; and Terminal Channel      1st sess.
                30 feet deep and 400 feet wide along the terminals
                at Jacksonville.
Mar. 2, 1945  Maintenance of channel widths as they now exist; H. Doc. 322, 77th Cong., 1st sess.
                widening Terminal Channel (30 feet deep) to a
                width of 590 feet; dredging the 28-foot-depth area
                between the foot of Laura St. and the St. Elmo W.
                Acosta Bridge; the navigation and floodway chan-
                nel along the south side of the Commodore Point
                terminals; and the approach and mooring basin in
                front of the Naval Reserve Armory.
    Do....... The 34-foot channel depth via the existing channels S. Doc. 230, 78th Cong., 2d sess.'
                and Terminal Channel.
    Do....... A cutoff channel between Dame Point and St. Johns S. Doc. 179, 79th Cong., 2d sess.'
                Bluff, 34 feet deep, in lieu of deepening the exist-
               ing channel.

1Contains latest published maps.

   Local cooperation. All work authorized by the River and Har-
bor Act of March 2, 1945, is subject to the conditions that local
interests furnish, free of cost to the United States, all lands, ease-
ments, and rights-of-way and spoil disposal areas for the initial
work and for subsequent maintenance when and as required, and
hold and save the United States free from claims for damages re-
sulting from the improvement. It is provided that these require-
ments as to the 28-foot-depth dredging between the foot of Laura
Street and the St. Elmo W. Acosta Bridge and the dredging in
front of the Naval Reserve Armory may be waived or modified if
in the discretion of the Chief of Engineers such action is necessary
in the interest of national defense (H. Doc. 322, 77th Cong., 1st
sess.). The deepening of the improvement to 34 feet is subject to
the additional requirement (S. Doc. 230, 78th Cong., 2d sess.) that
local interests give assurances satisfactory to the Secretary of War
that they will modify terminal facilities as necessary to permit full
utilization of the deeper channel. A resolution adopted January
4, 1946, by the Jacksonville Chamber of Commerce, agreeing to


         Sig 12-351-382
352      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

comply with the above-mentioned features of local cooperation, was
accepted by the Secretary of War on February 11, 1946, as satis-
factory assurance of compliance. All spoil disposal areas and
rights-of-way required in connection with the new-work dredging
between Commodore Point and the ocean and for the cutoff channel
have been furnished.
   Terminal facilities. There are 81 piers and wharves serving
the water-borne commerce of the port. The depths of water vary
from 31 feet at the larger terminals to a few feet at the inner end
of the slips and at barge berths. The Jacksonville municipal ter-
minals at Talleyrand Avenue consist of three piers. There are 35
other piers and wharves used for handling the waterborne com-
merce of the port or mooring vessels, 11 of which are open to the
public. All have railway and highway connections except nine of
the smaller piers, which have highway connections only. Of the
remaining piers, 26 are used in connection with shipyards and
marine repair plants, 2 for recreational craft, 8 for industrial pur-
poses, and 7 are not used.
   In addition, privately operated piers and wharves are available
at Mayport, Fla., to serve the fishing industry, and facilities for
serving recreational craft are available at Fulton. The facilities
are considered adequate for existing commerce. (See Port Series
No. 15, revised 1947, Corps of Engineers.)
   Operationsand results during fiscal year. Maintenance: Dredg-
ing to restore project depth between Mayport and the ocean in
Pilot Town and Bar Cuts was performed between November 3 and
23, 1953, with U.S. hopper dredge Gerig. Removal of 236,230
cubic yards of material, place measurement, cost $78,858. Re-
moval of shoals between Drummonds Creek and Mile point cuts
was performed by contract between January 8 and April 20, 1954.
Dredge No. 3 and No. 5 removed 663,493 cubic yards of material
at a cost of $223,992. Hired labor surveys, inspections, and re-
ports throughout the fiscal year cost $8,766.
   The total costs for the fiscal year were $311,616 for maintenance.
   Condition at end of fiscal year. The existing project was about
97 percent completed. Dredging was begun about November
1910. A channel at least 30 feet deep and of practicable width
from the entrance to Jacksonville was completed in March 1922.
Widening the 30-foot channel to authorized widths was completed
in July 1937, except Terminal Channel, which was only 400 feet
wide. Deepening the existing channels to 34 feet including widen-
ing Terminal Channel to 575 feet was begun in July 1947, and was
completed in December 1951. The Dame Point-Fulton Cutoff was
opened to traffic in June 1951. The easterly end of Bar Cut was
dredged to depths of 40 and 42 feet and 700 feet wide between April
and September 1951. These depths were obtained to accommodate
United States Navy aircraft carriers at no cost to the project. A
depth of 24 feet was provided between the 24-foot contour and the
pierhead line at Jacksonville, from Hogan Creek to the Florida
East Coast Railway bridge, between October 1907 and January
1912. The two jetties at the entrance, constructed between De-
cember 1880 and June 1904 under a previous project, have been
maintained under the existing project. About 3,555 linear feet of
       RIVERS AND HARBORS-JACKSONVILLE, FLA., DISTRICT             353
the inner end of the north jetty has been capped with concrete.
All training walls and revetments considered necessary on 30-foot
project were constructed between July 1892 and May 1894 by Duval
County, and by the United States, under the former and existing
project, intermittently between October 1903 and September 1927.
The easterly end of Wards Bank training wall has been revetted
with granite riprap. Material dredged near the westerly end of
Bar Cut and deposited along the north side of the north jetty near
the Fort George River encroachment has effectively prevented
further erosion adjacent to that structure. The jetties are in fair
condition except as follows: South jetty: Capstone has been dis-
placed in isolated locations and at the outer 800 feet. North jetty:
The north shore line has receded about 1,200 feet leaving the jetty
exposed. Capstone has been displaced in the outer 300-foot sec-
tion and in the 1,200-foot section seaward of the monolithic cap.
The monolithic cap has been broken and concrete washed away in
two locations, one 25 feet long and the other 15 feet long, near the
middle of the section. Revetments and training walls: Ward Bank
training wall, having been reinforced with heavy capstone at the
easterly end by the Navy Department, is in good condition. The
800-foot westerly extension, a Wakefield-pile wall,, is in poor con-
dition but has been reinforced at its up-stream end with rubble
concrete by the Navy. Mile Point training wall is in good condi-
tion. The adjacent shore at the east end is eroding. White Shells
training wall is in poor condition, but prevents erosion of the shore.
Fulton training walls are in good condition, however, due to Dame
Point-Fulton Cutoff they are no longer in the proper location to
prevent the erosion now occurring in the vicinity of Fulton, Fla.
Dame Point training wall is in poor condition but is apparently pre-
venting erosion. Bank erosion, apparently resulting from recent
new work dredging operations, is visible at several locations, and
if it continues, remedial measures will be required. These areas
are (1) North bank of river from Haulover Creek (Pilot Town) to
the north jetty; (2) South bank east of Mile Point training wall;
 (3) South bank at Fulton, and (4) North bank from Dame Point
to Dunns Creek.
   The Matthews Bridge (fixed) crosses the river at mile 22.3.
Vertical clearance over the Terminal Channel is 148.3 feet and over
Arlington Cut, 86.8 feet.
   The controlling depths in the middle half of the channels from
the ocean to Jacksonville were 34 feet except as follows: Pilot
Town Cut 33.6 feet in November 1953; Mile Point Cut 33.1 feet in
April 1954; White Shells Cut 33.9 feet in April 1954; and Terminal
Channel 33.0 feet in June 1953. The limiting depth in the left and
right outside quarters of the channels from the ocean to Jackson-
ville was 28.6 feet (March 1954), a channel edge shoal in Dame
Point-Fulton Cutoff. A controlling depth of 24 feet was available
to the pierhead line between Hogan Creek and the foot of Laura
Street in 1934 and to within 60 feet of the pierhead line, thence to
the St. Elmo W. Acosta Bridge in 1938.
   The work remaining to be done to complete the project is as fol-
lows: Dredge the area between the foot of Laura Street and the St.
Elmo W. Acosta Bridge to a depth of 28 feet; dredge the navigation
354               REPORT OF CHIEF OF ENGINEERS, U.                                             S. ARMY, 1954


and floodway channel along the south side of Commodore Point
terminals; and dredge the approach and mooring basin in front of
the United States Reserve Armory.
   The total costs under the existing project to June 30, 1954, have
been as follows:
                                                                                                          Costs
                                      Funds
                                                                                     New work          Maintenance             Total
Regular------    ------------------------------------ $11, 160,131 $11,107,
                                                                          747                                                 $22,267,878
Public works-----------------------------------------290,013 ---------------                                                      290,013

     Total--....-..-.-..-...--.--------------------.                                 - 11, 450, 144       11, 107, 747         22, 557, 891


                                                       Cost and financial summary

                                                                Fiscal year ending June 30                               Total to June
                                                                                                                         30, 1954, includ-
                                                                                                                         ing fiscal years
                                           1950              1951         1952             1953           1954            prior to 19501

New work:
   Appropriated--------........           $735, 000       $1, 600, 000   $987, 000   ------------          -- $100           $14,970,281
   Cost-_.....--------                     135, 442        2, 240, 169    946, 389          -$100     ------------            14, 970, 281
Maintenance:
   Appropriated----...--.                    58, 050          40, 000     249,500        $115, 877       $314, 620            11, 654, 150
   Cost--- ----_   -                         44,923           53, 977     249, 517        116, 956       2311, 875            11, 651, 405

  1 Includes $3,520,137 for new work and $543,399 for maintenance for previous project.
  2 Differs from "Operation and results during Fiscal year" by -$259. Pending adjustment.

Other new work data: Estimated additional amount needed to be appro-
                                                                     $406, 000
  priate d for completion of existing project........................................

                                           3.    OKLAWAHA                RIVER,           FLA.

   Location. This river has its source in the system of large lakes
in the central part of the Florida peninsula and flows generally
northerly, then easterly, emptying into the St. Johns River 22
miles above Palatka. The extreme head of the system may be
taken as Lake Apopka, 120 miles above the mouth of the river.
   Previous projects. The first improvement was authorized by an
act of Congress approved February 24, 1835. For further details
see page 1825, Annual Report for 1915, and page 613, Annual Re-
port for 1938.
   Existing project. This provides for deepening the channel to
6 feet at mean low water from the mouth to the head of Silver
Springs Run, 57.7 miles; for clearing the channel of obstructions
from Silver Springs Run to Lake Griffin, including the Kyle and
Young Canal and its extension to Morrisons Landing and the J. D.
Young Canal from Morrisons Landing to Starkes Ferry (clear
title to the canals and sufficient land adjacent thereto to provide
for future widening has been conveyed to the United States) ; and
for maintaining the dikes with a view to obtaining a navigable
depth of about 4 feet to Leesburg, 85.7 miles above the mouth.
The work embraces dredging, snagging, making cutoffs at sharp
bends, removing overhanging trees and obstructive aquatic vege-
tation, and constructing a lock and dam at Moss Bluff to maintain
the water level in Lake Griffin. The project includes, under main-
tenance, the operation and care of that lock and dam.
                 RIVERS AND HARBORS---JACKSONVILLE, FLA., DISTRICT                                                                                       355
                                                        Lock and dam at Moss Bluff
Distance to nearest town--.                                    .               .                 ..----------------------------------------   20.2 miles by canals.
Name of nearest town ...................................................................... Leesburg, Fla.
Distance above mouth of river...---------....................----------------................................ 65.5 miles by canals.
Distance above mouth of Silver Springs Run.................................. 13.2 miles.
Width of lock chamber.....----...-----------------                                                                                            30 feet.
                                                                                                                                      ...-------------...
Greatest available length for full width....                                                      ..................--....----.........----    125 feet.
Lift above low water...... -----------------..------------....................................                                            ... 16 feet.
Depth on upper miter sill at normal pool level----_....-----                                                                                  9 feet.
                                                                                                                                      ...-------
Depth on lower miter sill at low water..-..-.--.                                                       -          ------............. 4.5 feet.
Character of foundation...................................................................... Piles in sand and
                                                                                                                                                 clay.
Character of construction--------.......                                  ----........
                                                                                 ..                                                      .. Concrete, with tim-
                                                                                                ....................---------------------...
                                                                                                                                                 ber gates.
Kind of dam-------........---------------------.................................................---....---..........----............----      Movable.
                                                          ---------------------------------
Type of dam--..---.....--.......................................................................                                              Needle.
Completed ..-----------------------------..............................................................---....................... 1925.
Total cost---.........---.....---..............-------------.................................------------------....................... $161,000.


The river is nontidal except for a short distance above the mouth
at the St. Johns River, where the mean range at low-water stage
is about 0.5 feet. The mean fluctuation due to rainfall is about 2
feet at the mouth, about 3 feet at the mouth of Silver Springs Run,
and about 2.5 feet at Lake Griffin. The extreme fluctuation is about
3 feet at the mouth, 5 feet at Silver Springs Run, and about 4.5
feet at Lake Griffin.
   The estimate of cost for new work, revised in 1954, is $442,000,
excluding amounts expended on previous projects. The latest
 (1954) approved estimate of annual cost of maintenance is $21,000,
including $15,000 for operation and care of the lock and dam.
   The existing project was authorized by the following River and
Harbor Acts:

      Acts                                         Work authorized                                                           Documents
Sept. 19, 1890         Clearing the river of obstructions to obtain a navi-                                 Annual Report for 1889, pp. 1360-
                        gable channel about 4 feet deep from the mouth                                      1364.
                        to Leesburg.
Mar. 2,1907            Deepening the channel to 6 feet at mean low water                                    H. Doc. 782, 59th Cong., 1st sess.
                        from the mouth of the river to the head of Silver
                        Springs Run.
June 25, 19101         Maintenance of levels in the lakes at the head of the                                Specified in act.
July 25, 1912f            river.
July 27,1916           Acceptance of certain artificial waterways and exten-                                Specified in Act.
                        sions thereof between Heather Island and Lake
                         Griffin as part of the waterway in lieu of portions
                        of the natural bed of the river.
        (1)            Operation and care of the lock and dam provided
                        for with funds from War Department appropri-
                        tions for rivers and harbors.

  1Permanent Appropriation Repeal Act of June 26, 1934.

The latest published maps are in House Document No. 514, 63d
Congress, second session, and Annual Report for 1891, page 1626.
   Local cooperation. Fully complied with.
   Terminal facilities. There are numerous privately owned land-
ings along this river, more or less in disrepair, and a municipal
wharf at Leesburg; no charges for wharfage. The facilities are
considered adequate for existing commerce.
   Operations and results during fiscal year. Maintenance: The
lock and dam at Moss Bluff were operated and maintained and the
356      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

buildings and grounds were cared for by hired labor at a cost of
 $9,246. Hired labor inspections and reports cost $751. The total
costs for the fiscal year were $751 for maintenance and $9,246 for
operations and care, a total of $9,997.
    Condition at end of fiscal year. The existing project was about
70 percent completed. By dredging, making cutoffs, and snagging
intermittently between January 1892 and June 1914, a clear chan-
nel with a depth of about 6 feet at ordinary stages was obtained to
a point about 32 miles above the mouth and thence about 4 feet
deep to the head of Silver Springs Run, 57.7 miles above the mouth.
A channel 4 feet deep at mean low water and 30 feet wide between
Silver Springs Run and Moss Bluff lock was dredged between late
1924 and November 1929. A lock and dam at Moss Bluff were con-
structed between about March 1923 and late 1925. For further
details relative to this lock, see paragraph "Existing project".
The United States reservation comprises 13.0 acres of land, two
dwellings, a storehouse, and other small buildings. Most of the
original dredging of the canal between Heather Island (6.3 miles
above the mouth of Silver Springs Run) and Starkes Ferry near
Lake Griffin was done by private interests between 1911 and 1923.
Between June 1929 and June 1930, the canal between Moss Bluff
lock and Starkes Ferry was enlarged to 8 feet deep by 50 feet wide
to provide for control of Lake Griffin. The dike on the east side of
the canal was repaired and improved as a maintenance feature
from June to December 1936.
   Although the river below Moss Bluff lock was in poor condition
from fallen and overhanging trees, at the close of the fiscal year it
was open and passable. The dikes below the lock are in poor con-
dition. High waters created by necessary heavy discharge of
water through the dam have developed numerous weak points.
Repairs are necessary. The valves on the lock gates are leaking
and the fender system is in poor condition; otherwise, the lock and
dam were in fair condition. The controlling depths at normal
stages were approximately as follows: Mouth of the river to Silver
Springs Run, 4.0 feet; Silver Springs Run, 5.5 feet; and Silver
Springs Run to Leesburg, 4 feet.
   The work remaining to be done to complete the project consists
of easing several sharp bends and obtaining project dimensions in
the section between the mouth of the river and the head of Silver
Springs Run. Completing the project is not considered necessary
at this time.
   The total costs under the existing project to June 30, 1954, have
been $311,352 for new work, $337,746 for maintenance, and $191,-
761 for operation and care, a total of $840,859. In addition, $11,414
were expended between August 1, 1929, and June 30, 1935, on the
operation and care of the works of the improvement under the pro-
visions of the permanent indefinite appropriation for such pur-
poses.
             RIVERS AND HARBORS-JACKSONVILLE, FLA., DISTRICT                                                357
                                        Cost and financial summary

                                                 Fiscal year ending June 30                        Total to June
                                                                                                  30, 1954, includ-
                                                                                                  ing fiscal years
                                 1950         1951          1952          1953         1954         prior to 19501
New work:
   Appropriated                 ---       ------------ --...                  .......------------------------
                                                                                                         $315,264
   Cost---------           ----------------------------------------------- -----------                     315, 264
Maintenance:
      Appropriated   _       $20, 350         $15, 631      $14, 000      $11, 552      $9, 800            541, 582
      Cost---------- ------- 20, 838           16, 003       12, 619       13, 109      29, 987            540, 912

  1   Includes $3,912 for new work for previous projects and $11,414 for operating and care under provisions
of the permanent indefinite appropriation.
  2   Differs from "Operation   and results during fiscal year" by +$10. Pending adjustment.

Other new work data: Estimated additional amount needed to be appro-
                                                                     $131,000
  priated for completion of existing project............................------------

4. INTRACOASTAL WATERWAY,                                JACKSONVILLE                 TO MIAMI, FLA.
    Location. The waterway extends from Jacksonville to Miami,
Fla., following the St. Johns River to the mouth of Pablo Creek,
20 miles, and thence following in general the line of a canal con-
structed by the Florida Coast Line Canal & Transportation Co.
 (See U. S. Coast and Geodetic Survey Charts Nos. 842-847.)
    Previous projects. Adopted by River and Harbor Acts of June
15, 1844, July 13, 1892, August 18, 1894, and Deficiency Act of
February 26, 1896. For further details, see page 1825, Annual
Report for 1915; page 655, Annual Report for 1926; and page 618,
Annual Report for 1938.
    Existing project. This provides for an inland waterway 12
feet deep at local mean low water and generally 125 feet wide from
Jacksonville to Miami, with such modifications in cutoff and other
questions of alinement as may be required by the Chief of Engi-
neers; for a turning basin 8 feet deep, 400 feet wide, and 800
feet long in the vicinity of Jacksonville Beach, Fla. (essentially
provided by local interests in connection with dredging to provide
fill for highway at no cost to the United States) ; for an entrance
channel 8 feet deep and 100 feet wide from the Intracoastal
Waterway to and including a turning basin of the same depth, 300
feet wide and 600 feet long, at Sebastian, Fla.; and for a basin 8
feet deep extending from the Intracoastal Waterway to the east-
erly shore, about 1,140 feet wide at the waterway and 280 feet
wide at the shore line, at or near Vero Beach, Fla. The length of
the waterway is 370 miles, of which 21 miles are included in the
project for improvement of Jacksonville Harbor, Fla. The proj-
ect also includes the operation and maintenance of the Palm Valley
highway bridge, the title to which was passed to the United States,
along with all other property of the Florida Coast Line Canal &
Transportation Co., under the conditions of local cooperation.
   The mean range of tide is 3.8 feet at the St. Johns River, 0.7
foot in the Indian River at Fort Pierce, 1.8 feet in Lake Worth at
the Port of Palm Beach terminals, 2.3 feet at the Port Everglades
terminals, and 2 feet in Biscayne Bay. The extreme range is about
7 feet at the St. Johns River, 1.5 feet at Fort Pierce, and 3 feet
in Biscayne Bay. Tidal effect is imperceptible at points along the
waterway distant from inlets.
358             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   The estimate of cost for new work, approved in 1954, is $26,-
251,000 excluding amounts expended on previous projects. The
latest (1954) approved estimate for annual cost of maintenance is
$322,000, including $20,000 for the operation and care of the
bridge near Palm Valley.
   The existing project was authorized by the following River and
Harbor Acts:

    Acts                            Work authorized                                   Documents
Jan. 21,1927      For a channel 8 feet deep and 75 feet wide from Jack-    H. Doec. 586, 69th Cong., 2d sess.
                   sonville to Miami.
July (, 1930      Fora width of 100 feet__             -------.-.--.           Doc. 71, 71st Cong., 2d sess.
                                                                             .-------
     (1)          Operation and care of the bridge near Palm Valley
                    provided for with funds from War Department ap-
                    propriations for rivers and harbors.
Aug. 26,1937      Turning basin in the vicinity of Jacksonville Beach._.   H. Doc. 180, 75th Cong., 1st sess.'
Mar. 2,1945       A channel 12 feet deep and 125 feet wide -----------                                      2
                                                                           H. Doc. 740, 79th Cong., 2d sess. 2
   Do.......      A side channel and basin at Sebastian-..-..-.-           H. Doec. 336, 76th Cong., 1st sess.2
   Do.......                                          .........
                  A basin at Vero Beach .............--                    H. Doec. 261, 76th Cong., 1st sess.

1 Permanent Appropriation Repeal Act of June 26, 1934.
2 Contains    latest published maps.

   Local cooperation. The conditions imposed by the River and
Harbor Acts approved January 21, 1927, and July 3, 1930, have
been fully complied with, including furnishing suitable spoil dis-
posal areas for subsequent maintenance of the improvement as and
when required. Subsequent acts authorizing enlargement of the
waterway have imposed the same requirement with respect to
spoil disposal areas for maintenance. The Florida Inland Navi-
gation District, a special taxing district empowered by State law
to comply with certain features of local cooperation, was requested
to furnish additional spoil disposal areas in perpetuity for a 25-
year maintenance program in the southerly and northerly halves
of the waterway on May 15 and July 1, 1944, respectively. Numer-
ous areas have been furnished and the Navigation District is
actively engaged in securing other areas by negotiation, or, when
necessary, by condemnation. The areas are being furnished at a
satisfactory rate. Temporary spoil disposal areas for maintenance
have been and are being furnished as and when required.
   The work authorized by the River and Harbor Act of August 26,
1937, is subject to the condition that local interests provide, free
of cost to the United States, all lands and rights-of-way necessary
for the improvement and for its subsequent maintenance when and
as required, and to the further condition that local interests pro-
vide, without cost to the United States, suitable highway connec-
tions and a bulkhead along the south side of the basin on plans
approved by the Chief of Engineers, and agree to maintain said
bulkhead and the land approaches thereto as a public terminal open
to all on equal terms. A resolution adopted by the city council of
Jacksonville Beach, Fla., agreeing to comply with those conditions,
was accepted by the Chief of Engineers on October 18, 1945, as
satisfactory assurance of compliance.        The lands needed for
rights-of-way and spoil disposal have been furnished. A highway
from Jacksonville to Jacksonville Beach, opened to traffic on De-
cember 14, 1949, satisfied the requirements as to highway con-
nections.
       RIVERS AND HARBORS--JACKSONVILLE,        FLA., DISTRICT    359
   All work authorized by the River and Harbor Act of March 2,
1945, is subject to the conditions that local interests furnish, free
of cost to the United States, all lands, easements, and rights-of-
way and spoil disposal areas for new work and for subsequent
maintenance, when and as required, and hold and save the United
States free from claims for damages resulting from the improve-
ment. The act imposed additional requirements as follows:          (1)
Deepening the waterway to 12 feet is subject to the conditions (H.
Doc. 740, 79th Cong., 2d sess.) that local interests bear the cost of
all alterations of bridges, cables, pipelines, and other structures
made necessary by the improvement and that, if for any cause the
Secretary of War finds it advisable, he may cause proceedings to
be instituted in the name of the United States for acquirement by
condemnation or otherwise of any lands, easements, rights-of-way,
and spoil disposal areas needed for the improvement, after receipt
of assurances satisfactory to him from responsible local agencies
that they will reimburse the United States for the costs; (2) pro-
vision of a side channel at Sebastian is subject to the condition
 (H. Doc. 336, 76th Cong., 1st sess.) that local interests give as-
surances satisfactory to the Secretary of War that they will pro-
vide and maintain suitable terminal facilities open to all on equal
terms; (3) provision of the basin at Vero Beach is subject to the
requirements (H. Doc. 261, 76th Cong., 1st sess.) that local inter-
ests furnish assurances satisfactory to the Secretary of War that
they will protect the shore line with an adequate bulkhead, and
provide, maintain, and operate terminals adequate for full utiliza-
tion of the improvement, open to all on equal and reasonable terms.
   A resolution adopted August 2, 1946, by the Florida Inland
Navigation District was accepted by the Chief of Engineers De-
cember 24, 1946, as satisfactory assurance that the Navigation
District will furnish, free of cost to the United States, all lands,
easements, rights-of-way, and spoil disposal areas, needed for new
work and subsequent maintenance when and as required, and will
hold and save the United States from damages resulting from the
construction and maintenance of the 12-foot project. The Naviga-
tion District assumes no responsibility for the additional require-
ment that local interests bear the cost of all alterations of bridges,
cables, pipelines, and other structures made necessary by the im-
provement (H. Doc. 740, 79th Cong., 2d sess.), as it is not empow-
ered by State law to comply with such features of local cooperation.
The bridges, cables, pipelines, and other structures are owned by
various individuals and public and private corporations. Most of
those structures were constructed under permits issued by or under
authority of the Secretary of War. Alteration of all bridges,
cables, pipelines, and other structures, made necessary by the
improvement, can properly be required of the owners under exist-
ing Federal law. Procurement by the Navigation District of the
required rights-of-way and temporary spoil disposal areas for
new work is virtually complete for some sections of the waterway,
and is well advanced and actively in progress in others. The Navi-
gation District states that it is in a position to furnish all remain-
ing areas in a short time after it is evident that funds will become
available. No delays due to lack of suitable rights-of-way and
360       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

spoil disposal areas, nor to alterations of bridges, cables, pipelines,
and other structures made necessary by the improvement, are
expected.
    A resolution adopted by the city of Vero Beach on August 8,
1945, agreeing to comply with the features of local cooperation
pertaining to the basin at Vero 'Beach, was accepted by the Secre-
tary of War on November 28, 1945, as satisfactory assurances of
compliance. On March 14, 1946, local interests were informed as
to the requirements imposed in connection with the provision of a
side channel at Sebastian, but no assurance of compliance with
those requirements has been received. Local interests have stated
that participation by them in meeting local cooperation require-
ments is contingent upon the prior opening of Sebastian Inlet.
    Terminal facilities. Extensive terminals with railway and
street connections are available at Jacksonville and Miami. Ter-
minals with railway and highway connections, for coastwise ves-
sels have been constructed at Fort Pierce (Indian River), Riviera
 (Lake Worth), and Port Everglades Harbor. Municipal piers or
wharves have been constructed at Titusville, Courtenay, Cocoa,
Melbourne, and Vero Beach for handling general freight, and at
St. Augustine, Daytona Beach, New Smyrna Beach, Eau Gallie,
West Palm Beach, and Miami for the use of recreational craft.
At Daytona Beach, Titusville, Eau Gallie, and Fort Pierce, yacht
basins open to the public have been provided. They are connected
with the Intracoastal Waterway by channels 6 to 8 feet deep and
80 to 100 feet wide. At Fort Pierce a channel 6 feet deep and 80
feet wide has been dredged by the United States from the Intra-
coastal Waterway to and up Taylor Creek to the U. S. Coast Guard
buoy depot. There are also a number of privately owned piers,
wharves, and landings at various points along the waterway. The
facilities are considered adequate for the existing commerce. (For
further details on facilities at Jacksonville, Fort Pierce Harbor,
Port of Palm Beach, Port Everglades, and Miami, see Port Series
Nos. 15 and 16, revised 1947, and Port and Terminal Facilities
Report, 1941, Corps of Engineers.)
   Operations and results during fiscal year. The following table
shows work accomplished during the fiscal year.
          RIVERS AND HARBORS-JACKSONVILLE, FLA., DISTRICT                                                      361

          Work and locality                 Plant                    Period                  Quantity         Cost


New work:
   Contract:
        Dredging to enlarge existing     Clinton and    July 1 to November 19,             2, 030, 032       $315, 861
         channel to 12 by 125 feet        Admiral         1953.                               cubic yards.
         between Haulover Canal
         and Eau Gallie, about 41.8
         miles (in progress and 38
         percent completed at begin-
         ning of fiscal year).
Maintenance:
   Contract:
       Dredging to 9-foot depth over     Hallandale_. Intermittently be- 69,240 cubic                          71,382
         critical shoal areas between                   tween July 1 and     yards.
         Vero Beach and Miami,                          October 10, 1953
         Fla. (in progress and 29 per-                  (clean up operations
         cent completed at beginning                    extended to January
         of fiscal year).                                 6, 1954).
        Dredging to remove      shoals   Ideal- .....    March 3, to June 30,              337,478 cubic      71,009
          with depths less than 12 feet                      1954 (88 percent com-     yards.
          between St. Johns River                            pleted).
          and Eau Gallie.
Hired labor:
   Real estate management.......----...-------------- Fiscal Year _.----------------_                           7 194
   Surveys_ --------------------------------- Fiscal              Year-------------------------                 3,820
   Inspections and reports-----.....---------------....... Fiscal Year ______--------------     _              10 637
      Total Maintenance-------------                ------------------------------------                      164, 042



    Operating and Care: The steel and concrete, double-leaf bascule
highway bridge near Palm Valley was operated and maintained
by hired labor throughout the fiscal year at a cost of $19,241.
    The total costs for the fiscal year were $315,861 for new work,
 $164,042 for maintenance, and $19,241 for operation and care, a
total of $499,144.
   Condition at end of fiscal year. The existing project was about
43 percent completed. A channel 8 feet deep at local mean low
water and 100 feet wide was dredged between March 1930 and
May 1935. The northerly 171 mile section between the St. Johns
River and Eau Gallie was enlarged to 12 by 125 feet between June
1951 and November 1953, except for a small plug, about one mile
long, at Daytona Beach. The plug was left because of the pro-
posed reconstruction of a highway bridge and realinement of the
channel. The turning basin at Jacksonville Beach was essentially
completed by local interests in connection with dredging to pro-
vide fill for the approaches to the McCormick Bridge in 1949, at
no cost to the project. A steel and concrete, double-leaf bascule
highway bridge near Palm Valley, to replace the temporary pon-
toon bridge at that locality was constructed between September
1936 and July 1937 at a cost of $117,917.
   The existing channel widths are reduced at 54 localities by
bridges, with a limiting horizontal clearance of 51 feet at the Deer-
field Beach Bridge.
362            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   When last surveyed the controlling depths were as follows:

                                            Dredged dimensions              Minimum    depths in channel
                                                                                entering from north

       Reach          Date of survey                                         Left  Midchannel     Right
                                         Length    Width         Depth     outside    for half   outside
                                         (miles)   (feet)        (feet)    quarter project width quarter
                                                                            (feet)     (feet)     (feet)

St. Johns River to Jun 1953 and
  St. Augustine.       Mar 1954....           37       125          12.0       8.6            10. 9            9.7
St. Augustine to     Jun 1953-
  Matanzas Inlet.      Apr 1954....           13       125          12.0      10.9            12.0          10.7
Matanzas Inlet to Nov 1951-
  Ponce de Leon In-   Jun 1953......          52     1125         112.0       18.3            18.8         17.7
  let.
Ponce de Leon Inlet Jun 1953 and
  to Haulover Canal    Jun 1954.....          28       125          12.0      11.4            12.0             9.9
  bridge.
Haulover Canal       Nov 1953......           44       125          12.0      12.0            12.0          12.0
  bridge to Eau
  Gallie.
Eau Gallie to Fort Jul 1952 .......           51       100           8.0       8.0             8.0             8.0
  Pierce.
Fort Pierce to St. Sep 1953.......            21       100           8.0       6.4             5.9             5.4
  Lucie Inlet.
St. Lucie Inlet to Sep 1953.......           102       100           8.0       8.0            8.0              8.0
  Miami Harbor.

1 Old 8- x 100-foot channel being used pending removal of plug (see par. above).

   The work remaining to be done to complete the project is as
follows: Complete enlargement of the waterway to 12 by 125
feet; provide a side channel and basin as Sebastian; and provide
a basin at Vero Beach.
   The total costs under the existing project to June 30, 1954, have
been as follows:

                                                                      RegularRegular Public
                                                                                     works             Total
                                                                       fund          funds


Cost:
   New work_____ _      __-       __ ____-___-------------$9,104, 519      $2,199, 842 $11, 304, 361
   Maintenance--.           -_------          --------       3,838,752----            - 3,838, 752
   Operation and care____________________________________
                       .228,200                                       -___________-         228, 200
      Total----.---------.   -----
                     __--------------_                       _        13,171,471     2,199,842        15,371,313
            RIVERS AND HARBORS-JACKSONVILLE, FLA., DISTRICT                                                    363
                                          Cost and financial summary

                                                  Fiscal year ending June 30                          Total to June
                                                                                                     30, 1954, includ-
                                                                                                     ing fiscal years
                                   1950        1951          1952           1953          1954        priorto 195012

New work:
   Appropriated--------........    $7,000     $500, 000   $2, 150, 000   $1,019, 200      $10, 100       $11, 405,174
   Cost-----------------           11,934      126, 643    1, 874, 217    1, 356, 540     315, 861        11, 399,136
Maintenance:
   Appropriated-........           95,091      205, 993       15, 302       156, 811      113, 100         4,307, 536
   Cost..-----------------         94, 318     188, 841       41, 012        62, 336    a 182, 930         4,283,000

  1Includes $94,775 for new work and $213,222 for maintenance for previous projects and $3,179 on operat-
     and care of the works of improvement under provisions of the permanent indefinite appropriation.
    In addition $5,500 was expended for maintenance from contributed funds.
  ' Differs from "Operation and results during fiscal year" by $+354. Pending adjustment.
Other new work data:
                                                                       $6,039
    Unobligated balance, fiscal year ending June 30, 1954------.................---...
    Unobligated balances available for succeeding fiscal year ending
                                                                        6,039
      June 30, 1955-............................---...........----------------
    Estimated additional amount needed to be appropriated for com-
                                                                      941, 000
      pletion of existing project.................................................

                                  5. CANAVERAL HARBOR, FLA.
   Location. On the east coast of Florida in Canaveral Bight,
about 146 miles south of the entrance to Jacksonville Harbor and
69 miles north of the entrance to Fort Pierce Harbor. (See U. S.
Coast and ,Geodetic Survey Chart No. 1245.)
   Existing project. This provides for a turning basin 27 feet
deep at mean low water and 1,000 feet wide, with lengths of 900
feet on the north side and 2,900 feet on the south side, near the
easterly shore of Banana River and inclosed by a dike; an en-
trance channel 27 feet deep and 300 feet wide extending from the
turning basin through the barrier beach, thence flaring to 400 feet
wide at the 27-foot contour in Canaveral Bight, protected at its
seaward entrance by two jetties to the 12-foot depth contour; a
barge canal 8 feet deep at local mean low water and 100 feet wide
from the turning basin to the Intracoastal Waterway; and a lock
50 feet wide and 250 feet long to pass the barge canal through the
dike inclosing the turning basin. The entrance channel is about
1.8 miles long and the barge canal about 7.6 miles long. The total
length of the project is 9.8 miles. Present plans will provide for
only the north jetty to extend to the 12-foot contour; the south
jetty will extend to the 8-foot contour.
                           Data relative to the proposed lock
Distance to nearest town..........................................
                                                          10.7 miles via 8-foot barge canal and
                                                            Intracoastal Waterway.
Name of nearest town------..    ------------...-------... Cocoa Fla.
Distance from Intracoastal Waterway Channel.. 7.2 miles.
                                                          50 by 250 feet.
Lock dimensions ---..----------..--.........--------.........---...............
                                   Varies with the tide.
Lift-............................................................--
                                             feet mean low water.
Depth on sills.............................................------------------
                                          Piles in sand.
Character of foundation-----.............--------------...............
                                          None.
Kind of dam---------.....................................---------...........
                    $2,129,000.
Estimated cost.........................-------------------------.............

   The mean range of tide is about 3.5 feet and the maximum range
about 6 feet. Onshore winds generally raise the water level from
4 to 6 feet above mean low water. There is no perceptible tidal
364      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

effect in Indian and ,Banana Rivers in the general vicinity, but the
level of the water is considerably affected by winds, northerly
winds causing a lowering of the waters and southerly winds caus-
ing them to rise above normal. Easterly winds cause a rise at
the western shores and westerly winds a rise at the eastern shores.
   The estimate of cost for new work, approved in 1954, is $4,320,-
000 including $850,000 contributed by local interests, but excluding
$90,000 received from the sale of dredged material. The estimate
also includes $665,000 for construction of jetties, but excludes
$183,188 maintenance funds for emergency construction of land-
ward section of the south jetty. The latest (1954) approved esti-
mate for annual cost of maintenance is $84,300, including $29,600
for operation and care of the lock. The existing project was au-
thorized by the River and Harbor Act approved March 2, 1945
 (H. Doc. 367, 77th Cong., 1st sess.). The latest published map is
in the project document.
   Local cooperation. The authorized work is subject to the con-
ditions that local interest contribute 50 percent of the estimated
first cost of the improvement, but not to exceed $850,000, and
furnish assurances satisfactory to the Secretary of War that they
will: (1) Furnish, free of cost to the United States, all lands, ease-
ments, rights-of-way, and spoil disposal areas required for the
improvement and its subsequent maintenance, when and as re-
quired; (2) construct, without cost to the United States and in
accordance with plans approved by the Secretary of War, adequate
piers, slips, warehouses, and transit sheds, a precooling plant with
a capacity of at least 120,000 standard boxes of citrus fruit per
week, a shipside citrus packing plant with a capacity of at least
50,000 standard boxes per week, direct and adequate highway con-
nections between the port terminals and the mainland and all
bridges made necessary by the entire improvement; (3) agree to
operate and maintain, free of cost to the United States, all port
facilities open to all on equal and reasonable terms; (4) agree to
receive and pay for at the rate of 6 cents per cubic yard not less
than 1,500,000 cubic yards of material to be dredged by the United
States from the barge canal or turning basin and deposited upon
the right-of-way for the causeway carrying the highway between
the port terminals and the mainland; and (5) provide, operate,
and maintain, free of cost to the United States, adequate railroad
connections between the port and the rail lines on the mainland
when the Secreary of War shall require it.
   An act of the Florida State Legislature in 1939, as amended in
1941, created the Canaveral Port District in Brevard County, and
a governing body known as the Canaveral Port Authority with
authority to construct and maintain in the district a deep-water
harbor with terminal facilities; to borrow not to exceed $5,000,000
through the issuance of revenue certificates and bonds; and to levy
an ad valorem tax on real and personal property in the port dis-
trict. Bond issues are to be ratified by the freeholders of the port
district in a public election.
   By letter dated February 22, 1947, the Canaveral Port Authority
informed the district engineer that the authority had caused plans
and specifications for the essential port facilities to be prepared by
           RIVERS AND HARBORS-JACKSONVILLE, FLA., DISTRICT                                                  365
contract. On January 19, 1949, the Canaveral Port Authority
adopted a resolution agreeing to assume full responsibility for the
requirements of local cooperation. That resolution was accepted
by the Assistant Secretary of the Army on November 21, 1949, as
satisfactory assurance of compliance. A bond issue of $1,365,000
for meeting certain of the requirements of local cooperation was
sold September 29, 1949. On November 28, 1949, the port au-
thority contributed the required $850,000 toward the cost of the
improvement, and has tendered payment of $90,000 for purchase
of 1,500,000 cubic yards of material to be dredged by the United
States from the barge canal and turning basin and deposited upon
the right-of-way for the causeway carrying the highway between
the terminals and the mainland. All rights-of-way and spoil dis-
posal areas required for original dredging have been furnished.
Plans and specifications for a bulkhead wharf were approved by
the Secretary of the Army on November 10, 1952.
   Terminal facilities. An 800-foot marginal wharf on the north
side of the turning basin accommodates shrimp and commercial
fishing boats. A 400-foot marginal wharf was constructed on the
south side of the basin and is operated by the Canaveral Harbor
Port Authority. Improvements in that area consisting of provid-
ing access roadways and utilities are planned by the port authority.
The Canaveral Corporation has contracted for construction of an
80,000 barrel capacity storage tank on the south side of basin.
A 55,000 barrel tank with facilities for gasoline and jet fuel and
delivery pipe lines to the harbor and barge canal at the west dike
are planned for the future.
   Operations and results during fiscal year. The following tabu-
lation shows works accomplished during the fiscal year.

       Work and locality                    Plant             Period                 Quantity            Cost

New work:
   Contract:
      Construction of north -                           December 15, 1953,      Foundation blank-       $365, 655
        jetty and seaward ex-                            to June 30, 1954        et stone 10,321
        tension of south jetty.                          (78 percent com-         tons, core stone,
                                                         pleted).                 3,260 tons, cap
                                                                                  stone, 14,755 tons,
                                                                                  filter stone, 748
                                                                                  tons, riprap 2,250
                                                                                  tons.
   Hired labor:
       Engineering     ..--------....---                                                                   9,580

        Total new work ._.....---                                                                       375, 235
Maintenance:
   Contract:
       Construction of shore- -                         July 1to November       2,880 c.y. excava-      169, 785
        ward section of south                             10, 1953.               tion, 3,502 S.F.
        jetty (in progress at                                                     piling, 16,579 tons
        beginning of fiscal year                                                  riprap.
        and 18 percent com-
        pleted).
   Hirredlabor:
       Dredge to remove ob-            U.S.   Hopper    August   4   to   20,   321,826 c.y. (bin        95, 421
        structive shoaling and           dredge Lyman    1953.                    measurement).
         increase     constricted
          cross section.
       Surveys---------------------------                                                                 3,196
       Inspection and reports....------------------                                                         417

        Total maintenance-.... ...-.........                                                            268, 819
366            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   The total costs for the fiscal year were $375,235 for new work,
including $50 contributed funds, and $268,819 for maintenance, a
total of $644,054.
   Condition at end of fiscal year. The existing project was about
50 percent completed. The 8-foot-depth barge canal, the 27-foot-
depth turning basin, and barrier cut to the 12-foot contour in the
ocean were dredged between June 1950 and January 1952. Fill
was placed on the causeway site and the dike was constructed con-
current with dredging. The dike separates the west section of
barge canal from the remainder of the barge canal and other
project works. The entrance channel seaward of the 12-foot
contour was dredged from January to March 1952. Project di-
mensions were not obtained in the ocean section as the work was
terminated at 90 percent completion due to lack of progress.
   Emergency construction of the shoreward section of a south
jetty, 813 feet long, and revetment, 445 feet long, was started in
June and completed in November 1953. That construction was
financed with Operation and Maintenance, General funds. The
north jetty 1,150 feet long and revetment 300 feet long were
constructed between December 1953 and June 1954. Seaward
extension of south jetty has not yet started. Condition of the en-
trance channel has, in general, gradually improved with pro-
gressive completion of north jetty. Shoaling near south bank has
moved westward. Waves overtopping south revetment causes
erosion. It appears that a bar is beginning to form in the entrance
channel seaward of the jetties. The beach adjacent to the south
jetty has advanced seaward, the shoreline now being about one-
third the length of the jetty from the shore end of jetty. Since
construction of north jetty, considerable material has accumu-
lated on both north and south sides, with most extensive changes
occurring on north side.
   When last surveyed controlling depths were as follows:

                               Project                 Controlling depths entering
                                                              from seaward

Name of channel                                        Left      Midchannel      Right       Date surveyed
                     Length     Width       Depth     outside      for half      outside
                     (miles)     (feet)     (feet)    quarter    project width quarter
                                                       (feet)        (feet)     (feet)

Entrance channel         0.6   400 to 300     27.0      20.0             25.0      20.5    April 1954.
Land cut-------.....     1.0         300      27.0     + 3.5             18.0       14.8       Do.
Turning basin....        0.6       1,000      27. 0      25. 1           25. 2      21.5   April and May 1953.
Barge canal,
east section.....       0.8         100       8.0        8.3             8.7       8.4    November 1951.
Barge canal,
west section..          6.8         100       8.0        8.0             8.5       8.5    July 1950 and
                                                                                             January 1951.


   The work remaining to be done to complete the project is extend
under existing contract, the south jetty to planned length and con-
struct the lock.
   The total costs under the existing project to June 30, 1954, have
been as follows:
           RIVERS AND HARBORS-JACKSONVILLE,                                         FLA., DISTRICT                    367

                                                                             Federal     Contributed              Total

Costs:
    New work---------------------------------------- $1,254,898            $940,000                              $2,194,898
    Maintenance. --------------- ------------------------- 430,632- ------                                   -      430,632
                                -----------------------
      Total----...........----....--------....                               1,685,530         940,000           2,625,530


                                        Cost and financial summary
                                        UNITED STATES FUNDS

                                                 Fiscal year ending June 30                               Total to June
                                                                                                        30, 1954, includ-
                                                                                                        ing fiscal years
                                 1950         1951           1952            1953          1954          prior to 1950 1
New work:
   Appropriated_-       __.--  ,i ...........-
                                         ,--        - $40, 500               $10, 000    $610, 000               $1, 491, 000
   Cost.------------    --- $90, 142   $640, 495        189, 701              31, 981    1 377, 358               1, 257, 070
Maintenance:
   Appropriated_-    -- _.......... _----------- _-----------                335, 450   95,400                         850
                                                                                                                    430,
   Cost---------     ------------------------------------                    161,814 1 268,960                      430,773

   Differs from "Operation and Results during Fiscal year" by $--2,173 new work and $-141 maintenance.
Pending adjustment.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954................                                  $41,043
    Unobligated balances available for succeeding fiscal year ending
      Ju ne 30, 1955 ................ ...........                 ...........            .. ........        41,043
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project....................................................................... 1,979,000

                                         CONTRIBUTED FUNDS

                                                 Fiscal year ending June 30                               Total to June
                                                                                                        30, 1954, includ-
                                                                                                        ing fiscal years
                                 1950         1951           1952            1953         1954           prior  to19501
New work:
   Appropriated --------       $940,000 -----           ------          --                               -         $940,000
   Cost--------------           183, 862      $326, 931     $426, 862         $2,    6            $50               940, 000

1 Includes $90,000 received from local interests in payment for 1,500,000 cubic yards of material for cause-
way fill-a local cooperation requirement.

                             6. FORT PIERCE HARBOR, FLA.
   Location.            On the east coast of Florida, about 218 miles south
of the entrance to St. Johns River and about 124 miles north of the
entrance to Miami Harbor.                         (See U. S. Coast and Geodetic Survey
Chart No. 582.)
  Existing project. This provides for the maintenance, enlarge-
ment, and deepening of the project developed by private interests,
to provide a channel 350 feet wide at the 27-foot contour in the
ocean, tapering to 200 feet wide at station 100+00 near the west-
erly side of the inlet, thence 200 feet wide across Indian River to
station 30+00, and thence flaring on the southerly side to form a
turning basin 1,650 feet long on the northerly side, 750 feet long
on the southerly side, and 900 feet wide, the depth to be 25 feet in
the basin and in the channel to station 130+00, and thence 27 feet
to the 27-foot contour in the ocean; and for maintenance of the
jetties at the ocean end of the inlet, and of shore revetments within
the inlet in prolongation of the jetties.                               The two parallel rubble-
 368            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

stone jetties with revetment extensions, constructed by local in-
terests to protect the entrance, are 900 feet apart, the north jetty
and revetment being about 3,500 feet long, and the south jetty and
revetment about 3,200 feet long. The length of the section in-
cluded in the project is about 3.5 miles. The mean range of tide
is about 2.6 feet at the entrance and 0.7 foot at the terminal, with
northeast tides as high as 5 feet above mean low water.
    The actual cost of new work was $337,183. The latest (1954)
approved estimate of annual cost of maintenance is $30,000.
    The existing project was authorized by the following River and
Harbor Acts:

    Acts                           Work authorized                                  Documents

Deficiency Act of      The expenditure of $20,000 for dredging the channel,     Specified in Act.
Mar. 4, 1931.          provided that local interests agree to maintain said
                        channel.
War Department         The expenditure of up to $30,000 for dredging the           Do.
  Appropriation         channel.
  Act, Mar. 4, 1933.
Aug. 30, 1935 (main-   For maintaining the channels, jetties, and revetments,   H. Doc. 252, 72d Cong., 1st
tenance included       and enlarging the channels and turning basin to the       sess. Rivers and Harbors
in Public Works        existing project dimensions.                              Committee Doo. 21, 74th
Administration                                                                  Cong., 1st sess. (Contains
program, Sept. 6,                                                               latest published maps.)
1933).


    Local cooperation. Fully complied with.
    Terminal facilities. These consist of two earth-filled piers re-
tained by steel sheet piling and forming a slip 200 feet wide by
330 feet long with bulkhead wharf at inner end. These facilities
afford a berthing space of about 1,653 feet. The south pier and
the bulkhead wharf are municipally owned, the pier having a
berthing space of 524 feet, with depths of 25.5 to 18 feet. A ware-
house (in poor condition, needs extensive repairs) 75 by 280 feet
is on the municipal pier, and a precooling plant 102 by 365 feet
occupies the north pier, just landward of which is another ware-
house, 50 by 100 feet. A fruit-packing house 170 by 390 feet is
at the west end of the slip. The north pier is served by railway
and both piers by highway connections. North of the turning
basin there is a bulkhead wharf with a depth of 15 to 12 feet with
ample room for open storage, and with tank storage in the rear
for petroleum products. The facilities are considered adequate
for existing commerce. (See Port and Terminal Facilities Report,
1941, Corps of Engineers.)
   Operations and results during fiscal year. Maintenance: U.S.
hopper dredge Lyman removed 153,190 cubic yards of material,
bin measurement, from shoals throughout the project, February
15 to March 9, 1954, at a cost of $55,864. Hired labor survey cost
$1,973. Hired labor inspections and reports cost $701.
   The total costs for the fiscal year were $58,538 for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in February 1938. Dredging was begun in July 1936 and
completed in February 1938. Restoration of the jetties originally
constructed by local interests was begun in October 1933, and
completed in August 1934 as a maintenance feature. Both jetties
            RIVERS AND HARBORS-JACKSONVILLE, FLA., DISTRICT                                                                                                         369
are in good condition. The revetments are in poor condition;
both are ragged, with nearly vertical faces along the water
side, resulting from loss of numerous stones into the water.                                                                                                        The
westerly 500 feet of the south revetment is in very poor condition;
of that section, the westerly 200 feet has disappeared and needs
replacing to prevent further shore erosion. Stones should also be
replaced in the adjacent 300 feet of that section.
    The controlling mean-low-water depths in March 1954 were as
follows:

                                                                           Project                                 Controlling depths entering
                                                                                                                         from seaward

                  Name of channel                                                                                                     Midchannel
                                                                                                                 Left                                Right
                                                                 Width                     Depth                outside                  for half   outside
                                                                 (feet)                    (feet)               quarter               project width quarter
                                                                                                                 (feet)                    (feet)    (feet)
                                                --   -      -              -     ---   i     -             -
                                                                                                          1-       --             1   -    -      -          1-




Bar cut-   .....-
             - -                 - - -                          350 to 270                           27                 26.0                          26.2            26.0
Land cut (between revetments)-_-                                270 to 225                           25                 27.3                          25.5            25.0
Channel across Indian River .......                                    200                           25                 27. 7                         26.1            25.3
Turning basin............-...--.                                200 to 900                           25                 25.0                          25.5            25.0



  The total costs under the existing project to June 30, 1954, have
been as follows:

                                                                                                                                          Costs
                                    Funds
                                                                                                     New work                    Maintenance                      Total

                                                                                                                                                                              '
Regular- .----------
                  .                                      ... -$337,-                                                183                   $527, 000               $864, 183
Public works _...                                                                                     ..........                           250, 000                250, 000
      Total .........               -       -                      .- .        .......           -         337, 183                        777,000            1,114.183



                                         Cost and .financialsummary


                                                           Fiscal year ending June 30                                                                  Total to June
                                                                                                                                                      30, 1954, includ-
                                                                                                                                                      ing fiscal years
                                  1950               1951                      1952                   1953                        1954                  prior to 1950
                                                                   -   i                     .   .    .. . ..           .   --

New work:
   Appropriated. _                                                                                                                                                $337,183
   Cost . ......                                                                                                                 -...-.
                                                                                                                                    .....                          337,183
Maintenance:
    Appropriated.Cs
          -.            _         $65,463                $2,511                $24, 704                   $2, 213                  $58,400                         777,148
    Cost_ _                   S    65,463                 2,511                 24,704                     1,928                  1 58,585                         777,047

  1 Differs from "Operation and results during fiscal year" by $-47. Pending adjustment.

                            7. PORT EVERGLADES                                             HARBOR, FLA.
   Location. On the east coast of Florida, about 23 miles north of
Miami and about 48 miles south of Palm Beach Harbor, Fla. The
site of the harbor is in Lake Mabel. (See U. S. Coast and Geodetic
Survey Chart No. 546.)
   Existing project. This provides for the maintenance, enlarge-
ment, and deepening of the improvements constructed by local
interests to provide a channel 500 feet wide at its seaward end,
converging to 400 feet at the jetty entrance, thence converging to
370              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

300 feet at a point 1,000 feet within the jetty entrance, and thence
300 feet wide, and flaring at the inner end to a turning basin 1,200
feet long and 2,250 feet wide over the major portion of its length,
all to a depth of 35 feet at mean low water; and the maintenance of
two converging rubblestone jetties constructed at the entrance to
protect the channel, and of two parallel steel-sheet-piling bulkheads
800 feet apart to protect the land points of the inlet from erosion.
The entrance channel is about 7,300 feet long. The jetties are 700
feet apart at the outer ends and 1,200 feet apart at the shore ends.
The north jetty is angular and about 1,450 feet long; the south
jetty is straight and about 1,250 feet long. Both jetties, which
were originally built to 6 feet above mean low water with top
widths of 6 feet at the shore ends and 12 feet at the sea ends, and
with side slopes of 1 on 11/2, have been reconstructed, and enlarged
in part, as follows: outer 900 feet of north jetty and outer 460 feet
of south jetty were raised to plus 8 feet, mean low water, with top
width of 12 feet, and slopes of 1 on 2 and with granite mounds at
the seaward ends, 24 feet in diameter and 15 feet above low water.
The mean range of tide is 2.5 feet at the entrance and 2.3 feet at
the terminals; the extreme range is about 4.5 feet, with storm tides
of about 6.5 feet.
   The actual cost of new work was $2,200,538. The latest (1954)
approved estimate of annual cost of maintenance is $42,500.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                        Work authorized                                     Documents
July    3,1930    Maintenance of the harbor as constructed by local        H.   Doc. 357, 71st Cong., 2d sess.
                   interests.
Aug. 30, 1935     For enlarging the entrance channel to existing project   Rivers and Harbors Committee
                   dimensions and completing the turning basin to            Doc. 25, 74th Cong., 1st sess.
                    1,200 feet square.
June 20,19388     For enlarging the turning basin by adding a trape-       H. Doc. 545, 75th Cong., 3d sess.
                    zoidal area 350 feet wide on the north side.
July 24,1946      For general widening of the turning basin by 200 feet    H. Doc. 768, 78th Cong., 2d sess.
                    on the north and 500 feet on the south, and for        (Contains latest published maps.)
                   enlarging the flare of the entrance channel at the
                    basin.



   Local cooperation. The River and Harbor Acts approved Au-
gust 30, 1935, and June 20, 1938, imposed the condition, among
others, that local interests provide suitable areas for the disposal
of dredged material for maintenance. In addition, the latter act
included the requirement that local interests agree to provide the
slips, piers, and other terminal facilities necessary for the full
utilization of the improvement. A resolution adopted January 26,
1939, by the Broward County Port Authority, agreeing to provide
suitable and sufficient slips, piers, and other terminal facilities
necessary for the full utilization of the improvement, was accepted
by the Chief of Engineers February 20, 1939, as satisfactory as-
surance of compliance with that part of the required local cooper-
ation. In partial compliance with the conditions, the port authority
has provided slip No. 2 described below under "Terminal facilities."
All other requirements affecting original construction as imposed
by the two acts have been fully complied with. Sufficient tempo-
       RIVERS AND HARBORS-JACKSONVILLE, FLA., DISTRICT            371
rary spoil disposal areas have been furnished for maintenance as
and when required.
    The River and Harbor Act approved July 24, 1946, imposed the
conditions that responsible local interests agree to (1) provide,
free of cost to the United States, all necessary lands and rights-of-
way and suitable spoil disposal areas, diked as necessary, for new
work and for subsequent maintenance, when and as required; (2)
promptly dredge and bulkhead slip No. 3 and the berth at the east
end of pier No. 3 on completion of the improvement in the southern
part of the turning basin by the Government; and (3) hold and
save the United States free from damages resulting from the work.
A resolution adopted by the Broward County Port Authority on
October 23, 1947, assuming responsibility for compliance with the
above provisions of local cooperation, was accepted by the Chief of
Engineers on October 30, 1947, as satisfactory assurance of com-
pliance. All new-work spoil areas and easements in perpetuity for
required rights-of-way have been furnished. Slip No. 3 has been
dredged to the dimensions and depth stated below under "Terminal
facilities."
   While not required under the conditions of local cooperation, the
Broward County Port Authority, in 1946, partially completed
dredging an area of about 125,000 square feet on the westerly side,
and within the project limits, of the 500-foot extension to the
southerly side of the turning basin.
   Terminal facilities. These consist of seven commercial wharf
facilities at Port Everglades owned and operated by Broward
County Port Authority, all open to the public. They are on the
three slips that have been dredged off the turning basin. Slips No.
1 and 2 are 35 feet deep, 300 feet wide, and are respectively. 1,200
feet and 700 feet long, with steel-sheet-pile bulkheads on both sides
of each slip and at the end of slip No. 1. Slip No. 2 was so con-
structed as to permit future extension to a length of 1,200 feet.
Slip No. 3, 1,200 feet long and 300 feet wide, is 35 feet deep but is
inactive at present due to construction in progress of steel-sheet-
pile bulkhead on the northerly side of slip No. 3 and the southerly
330 feet at the head of pier No. 1. This work, scheduled for com-
pletion on November 1, 1954, will complete the 497 feet of bulk-
heading at the 1head of pier No. 1, and the 1,200 feet on the south
side of this pier and will add three additional wharf facilities, mak-
ing a total of ten for the port. A modern steel transit shed, 75 by
1,120 feet, has been constructed on pier No. 2; a privately operated
precooling plant on pier No. 1; and a privately operated cement
storage warehouse 150 by 200 feet has been constructed on pier
No. 4. A new transfer bridge (loading ramp) for the operation of
the railway car ferry vessels of the Suwannee Trainferry Lines,
Inc., has been constructed and is in operation at the landward end
of slip No. 1. All wharves have railway and highway connections
and pipeline connections to one or more of the 15 storage depots
for petroleum products, one of which is also for blackstrap
molasses. The facilities are considered inadequate for the existing
commerce. (See Port Series No. 16, revised 1947, Corps of Engi-
neers.)
  Operations and results during fiscal year. Maintenance: Con-
372           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

tract dredging in the turning basin in progress at the beginning of
the fiscal year was completed July 13, 1953. Dredge Hallandale
removed 101,237 cubic yards of material at a cost of $87,448, which
cost covers 779,780 cubic yards removed in prior year but not costed
in that year. Hired labor inspections and reports cost $1,400.
The total costs for the fiscal year were $88,848 for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in January 1949. Local interests dredged an entrance chan-
nel 210 feet wide, 35 feet deep, and about 6,900 feet long, from the
ocean to a partially completed turning basin 1,200 feet square, and
constructed two converging angular-stone jetties to protect the
entrance channel and two steel-sheet-pile bulkheads to protect the
land points. The United States enlarged the entrance channel to
project dimensions, completed the 1,200-foot-square turning basin
to a depth of 35 feet, widened it to a maximum width of 2,250 feet,
and enlarged the flare of the south side of the entrance channel at
the basin between December 1936 and January 1949, and recon-
structed the jetties as a maintenance feature between May and
September 1932. The seaward end of the south jetty was straight-
ened in connection with jetty repairs between June and August
1940 (see paragraph "Existing project"). Both jetties are in good
condition. The steel-sheet-pile bulkhead at the inner end of the
south jetty is in poor condition, and the similar bulkhead on the
north side of the land cut is in fair condition. The sheet piling,
except for a short section at the seaward end, was cut off at the low-
tide line during construction for concrete capping, which was never
placed. The tie-back piles and deadman timbers have been vir-
tually destroyed above earth line by marine borers.
   When last surveyed (February and November 1953) the con-
trolling depths at mean low water were as follows:

                                                   Project              Controlling depths entering from
                                                                                    seaward

           Name of channel                                                        Midchannel
                                             Width        Depth       Left                              Right
                                                                     outside     Left      Right       outside
                                                                     quarter    inside     inside      quarter
                                                                                quarter    quarter

                                               Feet          Feet     Feet       Feet         Feet      Feet
Outer bar cut_    _          _              500 to 300        35.0      29. 1      35. 7       36. 1       30. 5
Bar cut .__________.. __.. .   ___ .____            300       35.0      24.8       36.8        36.9        32.7
Flare to turning basin__                   300 to 1,000       35.0      35.4       35.4        36.0        35.4
Turning basin.....___ ....
                     _________________           2,250        35.0      34.5       35.0        35.4        34.6



   The total costs under the existing project to June 30, 1954 have
been $2,200,538 for new work and $498,846 for maintenance, a total
of $2,699,384.
           RIVERS AND HARBORS-JACKSONVILLE, FLA., DISTRICT                                                                   373
                                                 Cost and financial summary

                                                          Fiscal year ending June 30                             Total to June
                                                                                                               30, 1954, includ-
                                                                                                               ing fiscal years
                                          1950          1951            1952           1953        1954          priorto 1950
New work:
   Appropriated           ......            -$2, 316---------                                                           $2, 200, 538
   Cost.......                                      ----....-----------------------------------
                                  ......----------------                                                ...----------    2, 200, 538
Maintenance:
   Appropriated           _   -           17, 705           $148         $2, 450      $147, 800   -$5, 100                 498, 852
   Cost------.........-             -     20, 854            148          2, 584        53, 711    188, 855                498, 852


  1 Differs from "Operation and results during fiscal year" by $-7.Pending adjustments.

                                            8. MIAMI HARBOR, FLA.
   Location. Miami is near the northerly end of Biscayne Bay,
about 335 miles southeasterly from the entrance to Jacksonville
Harbor. Miami River has its source in the Everglades and flows
southeasterly to enter Biscayne Bay at Miami. (See U. S. Coast
and Geodetic Survey Charts Nos. 547 and 1248.)
   Existing project. This provides for the following: (1) A
channel 30 feet deep and 500 feet wide from the 30-foot contour in
the ocean to near the outer end of the north jetty, thence 300 feet
wide through the entrance and across Biscayne Bay to and including
a turning basin 1,400 feet long and 1,350 feet wide on the westerly
side of Biscayne Bay in front of the municipal terminals at Miami;
 (2) two parallel rubblestone jetties at the entrance, 1,000 feet
apart and 3,000 and 2,750 feet long, respectively; (3) an approach
channel 300 feet wide and a turning basin of irregular shape about
2,000 feet square, both 30 feet deep, at Virginia Key, and dredging
12,060,000 cubic yards of material from the bay bottom in addition
to that to be dredged from the approach channel and turning basin
to provide fill for the island, with such modifications as in the dis-
cretion of the Secretary of the Army and the Chief of Engineers
may be advisable; (4) a channel 15 feet deep and 200 feet wide
from the mouth of Miami River to the turning basin at the munici-
pal terminals; (5) a channel 8 feet deep and 200 feet wide from
the mouth of Miami River to the Intracoastal Waterway and thence
100 feet wide to Government Cut; (6) a channel at the mouth of
Miami River, 15 feet deep at mean low water, 250 feet wide at the
outer end and tapering to 170 feet wide at Brickell Point in a dis-
tance of about 1,400 feet; thence a channel in Miami River, 15 feet
deep under flood conditions, 150 feet wide for 3 miles, thence 125
feet wide for 1.1 miles, and thence 90 feet wide for 1.4 miles; (7) a
channel 12 feet deep and 100 feet wide from Miami River to a har-
bor of refuge in Palmer Lake, the location of the harbor of refuge
and channel leading thereto being subject to modification at the
discretion of the Chief of Engineers; (8) an approach channel 6
feet deep and 700 feet wide to the harbor line at the seaplane base
at Dinner Key, with an enlargement at the inner end and with a
channel 8 feet deep and 50 feet wide along the easterly edge of the
widening.
   The plane of reference is mean low water, except for the 15-foot
channel in Miami River where depths are based on flood conditions.
The total length of the waterway under improvement is about 17.7
miles, including about 6 miles of entrance channel from the ocean
374                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

to and including the turning basin at the municipal terminals, 1.6
miles of approach channel to Virginia Key, 5.8 miles in Miami
River, 3.5 miles in the connecting channels leading therefrom into
the bay, and 0.8 mile at Dinner Key Airport.
   The mean tidal variation is 2.5 feet at the entrance and 2 feet in
the bay. The extreme variation is about 4.5 feet at the entrance
and 3 feet in Biscayne Bay. Strong easterly winds raise the water
level about 1.5 feet at the entrance and 1 foot in the bay. Strong
westerly winds lower the water level about 1 foot at the entrance
and about 0.5 foot in the bay.
  The estimate of cost for new work, approved in 1954, is $14,-
837,000, excluding $23,000 to be contributed by local interests.
The latest (1954) approved estimate of annual cost of maintenance
is $75,000.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                             Work authorized                                          Documents
                                           MIAMI RIVER

July     3,1930     The 15-foot channel in Miami, 150 feet wide at the               Specified in act.
                     mouth.
         (1)        The channel at the Dinner Key Airport-----------..............   S.Doc. 95, 72d Cong., 1st sess. and
                                                                                      specified in act.s
                                          MIAMI HARBOR

June 13,1902        An 18-foot channel in a land cut across the peninsula            H. Doc. 662, 56th Cong., 1st seas.
                      and construction of the north jetty.                             (Annual Report, 1900, p. 1987.)
Mar. 2,1907         Construction of the south jetty and increase of chan-            Specified in act.
                     nel width to 100 feet.
July 25,1912        Enlarging the channel to 20-foot depth and 300-foot              H. Doe. 554, 62d Cong., 2d sess.
                      width and extending the jetties.
Mar. 4,1913         Modification of local cooperation requirements im-               Specified in act.
                      posed by the act of July 25, 1912.
Mar. 3,1925         A channel 25 feet deep with present project widths               H. Doc. 516, 67th Cong., 4th sess.
                     from the ocean to Biscayne Bay thence 200 feet
                     wide across the bay to but not including the muni-
                      cipal turning basin, and extension of both jetties.
July     3, 1930    A channel width of 300 feet across the bay and en-               Rivers and Harbors Committee
                     larging the municipal turning basin, with expendi-                Doc. 15, 71st Cong., 2d sess.
                      tures thereon limited to $200,000.
Aug. 30,1935        A depth of 30 feet from the ocean to and in the turn-            Senate Committee        Print,   73d
                     ing basin, with the existing authorized project                   Cong., 2d sess.
                     widths, including the 300-foot width in the channel
                     across the bay.
Aug. 26,1937                                                     Rivers and Harbors Committee
                   Extending the turning basin 200 feet to the southward.
                                                                   Doe. 86, 74th Cong., 2d sess.
Mar. 2,1945 The Virginia Key improvement----....-------------S8. Doe. 251, 79th Cong., 2d sess.'
   Do....... For incorporation of the project for Miami River in H. Doc.91, 79th Cong., 1st sess.'
              that for Miami Harbor, the widening at the mouth
              of Miami River to existing project widths; the
              channels from the mouth of Miami River to the
              turning basin and to Government Cut; and the
              channel from Miami River to the harbor of refuge,
              provided that local interests contribute one-third
              of the cost.


1 War Department Appropriation Act approved July 14, 1932.
 ' Contains latest published maps.
 * Included in the Public Works Administration program Jan. 3, 1934.

   Local cooperation. All work authorized by the River and Har-
bor Act approved March 2, 1945, is subject to the conditions that
local interests furnish, free of cost to the United States, all lands,
easements, and rights-of-way and suitable spoil disposal areas for
the initial work and subsequent maintenance, as and when re-
quired, and hold and save the United States free from claims for
       RIVERS AND HARBORS-JACKSONVILLE,        FLA., DISTRICT    375
damages resulting from the improvement. Additional require-
ments imposed by that act are as follows: (1) The Virginia Key
improvement is subject to the conditions that local interests give
assurances satisfactory to the Secretary of War that they will
provide auxiliary channels and suitable airport and harbor terminal
facilities at Virginia Key generally in accordance with the plans
submitted by the district engineer and subject to such modifica-
tions as the Chief of Engineers may require, and provide such oper-
ating facilities as the United States may require; (2) the provision
of a channel from Miami River to the harbor of refuge is subject
to the conditions that local interests contribute one-third of the
initial cost of the channel, furnish assurances satisfactory to the
Secretary of War that they will provide and maintain suitable
depths in the harbor of refuge and construct and maintain ade-
quate mooring facilities therein, and agree that, at any time upon
the approach of a hurricane or severe storm and specifically upon
the request of the district engineer or his authorized represent-
ative, the refuge basin will be open to all without charge until
storm danger is past.
    On March 21, 1945, local interests were informed as to the re-
quirements of local cooperation imposed in connection with the
Virginia Key improvement. No assurance of compliance with those
requirements has been received. On September 5, 1945, the Com-
mission of the City of Miami, Fla., adopted a resolution agreeing
to assume responsibility for compliance with the local cooperation
requirements imposed in House Document No. 91, Seventy-ninth
Congress, first session, except those pertaining to the channel from
Miami River to the harbor of refuge in Palmer Lake. On May 9,
1946, that resolution was accepted by the Secretary of War as
satisfactory assurance of partial compliance.
    All prior requirements have been fully complied with.
    Termiial facilities. These consist of 38 piers and wharves of
which one is on Fisher Island, 5 are along the south side of Mac-
Arthur Causeway, 7 are on the west side of the Bay at Miami, and
25 are on Miami River. Seven of the facilities are open to the
public for handling general cargo. Four of these, including three
municipal piers on the west side of the Bay and a privately owned
wharf near the east end of the MacArthur Causeway, can accom-
modate deep-draft vessels. The other three general cargo facilities
are suitable for small vessels, and include the Florida East Coast
Railway wharf south of the municipal piers, and two privately
owned wharves on Miami River. All of the general cargo wharves
have highway and railway connections, except the causeway ter-
minal, which has highway connections, only. A municipal yacht
anchorage and basin, and a municipal wharf are open to the public
for recreational craft. Of the remaining piers and wharves, 4 in
the bay and 3 on Miami River are used for handling petroleum
products, 17 are used in connection with ship repair activities, and
6 are used for mooring vessels or handling private freight. Three
of these facilities have railway connections, and all have highway
connections except a petroleum wharf on Fisher Island. In addi-
tion, numerous landing facilities in and around Miami, especially
on Miami River, are designed for and used exclusively by recre-
376      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

ational craft. The facilities are considered inadequate for the
existing commerce. (See Port Series No. 16, revised 1947, Corps
of Engineers.)
   Operations and results during the fiscal year. Maintenance:
Hired labor maintenance of United States reservation and bank
revetments throughout year cost $9,696. Hired labor inspections
and reports cost $3,297. The total costs for the fiscal year were
$12,993 for maintenance.
   Condition at end of fiscal year. The existing project was about
49 percent completed. The main 30-foot entrance channel from the
ocean to and including the turning basin was dredged progressively
between August 1904 and March 1939. A land cut 20 feet deep and
300 feet wide was dredged across the peninsula to Biscayne Bay
between August 1904 and October 1923; a channel 25 feet deep
from the ocean to and including the former municipal turning basin
at Miami (200 feet wide across the bay, and following the aline-
ment of the former municipal channel) was dredged between July
1926 and December 1933, and was deepened to 30 feet, including
widening the channel across the bay to 300 feet and enlarging the
turning basin, between April 1934 and March 1939. A channel 15
feet deep at mean low water and 150 feet wide along the land point
at the mouth of Miami River for 1,400 feet, and thence northerly
along the bay front for about 1,200 feet, and a channel in Miami
River for 5.5 miles above its mouth, 15 feet deep under flood con-
ditions and of project widths, were dredged between March 1932
and August 1933. The channels at the Dinner Key seaplane base
were dredged between February and August 1933. These facilities
are no longer used by aircraft, and the Dinner Key base was taken
over by the City of Miami in 1947, converted to accommodate pleas-
ure boats, and is now known as the Dinner Key Marina. The two
stone jetties at the entrance were constructed to the 18-foot con-
tour between March 1904 and October 1908, extended 405 feet each
in 1922, and extended to their present lengths between September
1926 and March 1929. The north jetty and revetment is 4,688 feet
long, and the south jetty and revetment is 3,850 feet long.
   The south jetty, both revetments, and that part of the north
jetty landward of the low tide shore line in the ocean are in good
condition. Seaward of the low-tide shore line the north jetty is in
fair condition; that section was damaged during the hurricane of
November 1935. Numerous pieces of granite were dislodged from
the upper part of the jetty and now rest on the ocean bed along
the jetty. At several points in the jetty, the crest has been lowered
to the plane of mean high tide. No sand encroachment toward the
channel has taken place through the lowered sections. When last
surveyed, the controlling depths were as follows:
            RIVERS AND HARBORS-JACKSONVILLE, FLA., DISTRICT                                                                        377

                                                 Project                         Controlling depths, mean
                                               dimensions                               low water
            Name of channel                                                                                                  Date
                                                                       Left   Midchannel     Right
                                                                                                                           surveyed
                                            Width         Depth       outside    for half   outside
                                                                      quarter project width quarter

                                              Feet         Feet             Feet               Feet              Feet
Main entrance:
   From ocean through land cut and
     across
       Biscayne Bay_        ...     ....   500 to 300        30.0 ....                               30.0     ---------    May 1953.
       Turning basin .-------------            1,350         30.0      27.0                          28.9           26.9    Do.
Miami River:
   Biscayne Bay to South Fork,
     Miami River-__                              150          i 15                8.4                12.1            9.1   June 1944.
   South Fork, Miami River to
     Tamiami Canal_                              125          1 15               10.4                13.6           10.8     Do.
   Tamiami Canal to 36th St. bridge               90          115                                     6.9                    Do.
Dinner Key Airport:
   Approach channel 2 _-_       __-              700              6               5.7                 5.7            5.7   May 1940.
   Channel along easterly edge of
     widening                                        50           8              8.0                  8.0            8.0   1935.


  SUnder flood conditions.
  2   This channel is not used by aircraft. It is now used as entrance channel to Dinner Key Marina.
Breakwater now lies across 700-foot channel at its junction with Turning Basin.

   The work remaining to be done to complete the project is as fol-
lows: Provide an approach channel and turning basin 30 feet deep
at Virginia Key, and dredge 12,060,000 cubic yards of material
from the bay bottom, in addition to that to be dredged from the
approach channel and turning basin to provide fill for the island;
widen the channel ,t the mouth of Miami River by 20 to 100 feet
for 1,400 feet; widen the existing channel along the southerly end
of Bayfront Park north of Miami River to 200 feet, and thence pro-
vide a channel 15 feet deep and 200 feet wide to the turning basin
in front of the municipal terminals; provide a channel 8 feet deep,
200 feet wide from the mouth of the river to the Intracoastal Wa-
terway, and thence 100 feet wide to Government Cut; and provide
a channel 12 feet deep and 100 feet wide from Miami River to a
harbor of refuge in Palmer Lake.
   The total costs under the existing project to June 30, 1954, have
been as follows:

                                                                                                            Costs
                               Funds
                                                                                   New work           Maintenance            Total
                                                                             I




Regular- ....---                       -.---------              -..........-.....
                                                                           $5,016,248                       $1,579,822     $6,596, 070
Public works......                           ---------.............         2,202,126                 -         _           2,202,126
        Total........                                 . ----------    ...               7, 218,374           1, 579, 822    8, 798,196
 378             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                         Cost and financial summary

                                                  Fiscal year ending June 30                                Total to June
                                                                                                           30, 1954, includ-
                                                                                                           ing fiscal years
                                  1950           1951            1952               1953        1954        prior to 1950
New work:
   Appropriated__          _---    -      ....      -----
                                                 -........-       -$268                                         $7, 218, 374
   Cost -- -------------               $39         -$39       .--..---------.------------                        7, 218,374
Maintenance:
    Appropriated..--------         12, 300        13, 539         14, 600           $12, 500    $11, 950          1, 580, 131
    Cost-----------------          93, 291        12, 847         14, 780            11, 691   1 12, 402          1, 579, 231

  1Differs from "Operation and results during fiscal year" by $+591. Pending adjustment.
  2 In addition $23,000 to be contributed by local interests.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project ..-----...........................................-------- $7, 619, 000

                           9. OKEECHOBEE WATERWAY, FLA.
    Location. Caloosahatchee River has its source in Lake Okee-
  chobee and flows generally southwesterly, emptying into the Gulf
of Mexico through San Carlos Bay, about 30 miles south of the en-
trance to Charlotte Harbor. (See U. S. Coast and Geodetic Sur-
vey Charts Nos. 473, 1247, 1255, and 1289.)
    Lake Okeechobee is a large, fresh-water lake in south-central
Florida. (See U. S. Coast and Geodetic Survey Chart No. 1289.)
    St. Lucie Canal was constructed by the Everglades Drainage Dis-
trict as a control canal for Lake Okeechobee. It begins at about
the middle of the east shore of Lake Okeechobee, and empties into
the south fork of the St. Lucie River at St. Ludie lock. The length
of the canal is 23.9 miles. (See U. S. Coast and Geodetic Survey
Chart No. 1289.)
    St. Lucie River, South Fork, flows north from the entrance of
the St. Lucie Canal about 7.4 miles to Stuart, where it joints North
Fork to form the St. Lucie River, thence east, southeast, and east
about 7.7 miles, emptying into the Indian River opposite St. Lucie
Inlet. (See U. S. Coast and Geodetic Charts Nos. 1247 and 1289.)
    Taylor Creek is formed by several small streams in central
Okeechobee County, and flows generally southeasterly, emptying
into Lake Okeechobee at its most northerly extremity. (See U. S.
Coast and Geodetic Survey Chart No. 1289.)
    (For description of above waterways see p. 705, Annual Report
for 1932.)
    Previous projects. Original projects for Caloosahatchee River
below and above Fort Myers were adopted by River and Harbor
Acts of August 2, 1882, and August 11, 1888, respectively. The
next project was adopted by the River and Harbor Act approved
June 25, 1910, which authorized the present project depths in
Caloosahatchee River from Fort Myers to the Gulf of Mexico,
with a turning basin at Fort Myers, and was modified by the River
and Harbor Acts approved July 3, 1930, and August 30, 1935,
under the title "Caloosahatchee River and Lake Okeechobee drain-
age areas, Florida," to provide, among other things, for a navi-
gable channel across the State and for control of Lake Okeechobee,
including construction of locks at Ortona and Moore Haven. For
further details see page 1828, Annual Report for 1915; page 707,
Annual Report for 1932; pages 878-888, Annual Report for 1948;
          RIVERS AND HARBORS-JACKSONVILLE,                          FLA., DISTRICT            379
and pages 785 and 831, Annual Report for 1949.
   Existing project. This provides for (1) Replacing old locks
Nos. 1 and 2, St. Lucie Canal, by a single new lock with a usable
width of 50 feet, a usable length of 250 feet, a depth of not less
than 8 feet over the sills, and a new weir structure; (2) a channel
8 feet deep from Fort Myers to the Intracoastal Waterway near
Stuart, with widths of 90 feet from Fort Myers to Moore Haven,
thence 80 feet along the southerly shore of the lake to the hurri-
cane gate at Clewiston, thence 100 feet across Lake Okeechobee
to and in the St. Lucie Canal to St. Lucie lock, and thence 80 feet
to the Intracoastal Waterway; (3) a channel 8 feet deep and 100
feet wide from the project turning basin to the existing municipal
yacht basin at Fort Myers; (4) a basin 8 feet deep, 200 feet wide,
and 400 feet long at Stuart; and (5) under maintenance, the oper-
ation and care of St. Lucie lock.
   The project also includes maintenance of features completed
under previous projects as follows: (1) A channel 12 feet deep and
200 feet wide from the Gulf of Mexico to Punta Rasa, about 3.8
miles, thence 10 feet deep and 100 feet wide to Fort Myers (Edi-
son Memorial Bridge), about 16.3 miles, with a turning basin at
that point; (2) a channel in Taylor Creek 6 feet deep when the
lake is at elevation 12.56 mean sea level, and 60 feet wide from the
town of Okeechobee into the lake, 4 miles; (3) a navigation chan-
nel 6 feet deep and 80 feet wide following in general the south
shore of Lake Okeechobee from Clewiston to the St. Lucie Canal,
36.7 miles; and (4) the operation and care of the Moore Haven
and Ortona Locks.
   The total length of the waterway from the Gulf of Mexico to the
Intracoastal Waterway is about 154.6 miles via the channel across
Lake Okeechobee, or about 165.3 miles via the channel along the
south shore of the lake.
   On July 1, 1947, mean sea level datum, which is 1.44 feet above
the Lake Okeechobee datum previously used between the St. Lucie
and Ortona locks, was adopted for use throughout the project.
Project depths are based on minimum water elevations referred
to mean sea level, as follows:
                                                                                                Feet
St. Lucie River, Indian River (Intracoastal Waterway) to St. Lucie lock ...... -- 0.49
St. Lucie Canal and Lake Okeechobee St. Lucie lock to Moore Haven lock.... 13.00
Caloosahatchee Canal, Moore Haven lock to Ortona lock .................................... 10.06
Caloosahatchee River, Ortona lock to the Gulf of Mexico ...............................    ----0.88

  The following table shows the principal features of the locks
and dams (spillways are maintained under the flood control proj-
ect for Central and Southern Florida).
380               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


                                                        St. Lucie Canal                  Caloosahatchee Canal

                                                         St. Lucie lock'        Moore Haven                 Ortona lock
                                                            and dam                lock'                     and dam
                                                                                  I                  I




Distance from Lake Okeechobee....                .     23.9 miles -__                                    15.5 miles.
Nearest town (Florida).-.....-....-                    Stuart, 8 miles ..-    Moore      Haven,          La Belle, 8 miles.
                    3                                                            0.75 mile.
Lock dimensions a..............__     ___              50 x 250 feet -_____   50 x 250 feet- .....       50 x 250 feet.
Lift with minimum water elevations          ......     13 feet . ..........   2.5 feet-.... ......       11.5 feet.
Depth over sills:
    Upper-------------          -----                  13.8 feet_...__-____   10 feet.... . ..-.-        12 feet.
    Lower_-----    ---------                           12.2 feet-... . ----   11 feet..-.. . .....       11 feet.
Character of foundation... -..                         Pile.___-              Pile_-..       ----.       Pile.
Kind of dam....                  __                    Movable -... __        None_ __-----              Movable.
Type of construction:
   Lock........--- ................         _          Concrete and steel-                   Concrete and steel-
                                                                              Concrete and steel-
                                                        sheet piling.          sheet piling.   sheet piling.
    Dam ...........
                  ........ ......                      Concrete, Tainter-                    Concrete, Tainter-
                                                        gate controlled.                       gate controlled.
Date of completion.
                                                     - $2,019,335---------
                                                                              1935....... .  1937.
Actual cost._- __-___                                                                ------
                                                                              $556,850    .. $856,904.

    Old lock No. 2, constructed by Everglades Drainage District, is adjacent to the new lock and serve s
as an auxiliary. This lock is 30 by 130 feet in the clear, with a limiting depth of 6 feet on the lower sill.
  2 Combined hurricane gate and lock.
  3 Width of chamber and greatest length available for full width.
  SSubstantially completed in 1943 except for the installation of the Tainter gates in the dam in 1950.
  b Includes $79,474 for removing old lock No. 1.




   The mean range of tide at Punta Rasa is 1.7 feet and at Fort
Myers, 0.7 foot. The extreme range is about 4.5 feet at Punta Rasa
and about 2 feet at Fort Myers. At low-river stage, tidal influence
is perceptible at the Ortona lock, 57.3 miles above Punta Rasa.
The mean range of tide at St. Lucie Inlet is 2.6 feet and the ex-
treme range, about 4.5 feet. Tidal effect is perceptible to St.
Lucie lock, 15.1 miles. Lake Okeechobee is maintained, so far as
possible, between elevations 13 and 15 feet, mean sea level.
   The estimate of Federal cost for new work, approved in 1954,
excluding amounts expended on previous projects, is $3,809,000.
The latest (1954) approved estimate for annual cost of mainte-
nance is $232,500, including $119,000 for operation and care of
locks.
   The existing project was authorized by the following River and
Harbor Acts:
                  '-------------
       Acts                           Work authorized                                           Documents

Aug. 26, 1937      For construction of a new lock and weir structure in               Rivers and Harbors Committee
                     St. Lucie Canal.                                                   Doc. 28, 75th Cong., 1st sess. 1
Mat.    2, 1945    For deepening to 8 feet, with present widths, from                 H. Doc. 696, 76th Cong., 3d sess.
                     Fort Myers to the Intracoastal Waterway near
                     Stuart via the existing channel along the southerly
                     shore of the lake to Clewiston and a channel across
                     Lake Okeechobee.
    Do.....        For a channel from the project turning basin to the                H. Doc. 736, 79th Cong., 2d sess.'
                     municipal yacht basin at Fort Myers; and for a
                     basin at Stuart.
       (2)         Operation and care of locks and dams provided for
                     with funds from War Department appropriations
                     for rivers and harbors.


1 Contains latest published maps.
2 Permanent Appropriation Repeal Act of June 26, 1934.


   Local cooperation. All work authorized by the River and Har-
bor Act approved March 2, 1945, is subject to the conditions that
local interests furnish, free of cost to the United States, all lands,
       RIVERS AND HARBORS-JACKSONVILLE, FLA., DISTRICT           381

easements, rights-of-way, and spoil disposal areas when and as
required for the initial work and for subsequent maintenance, and
hold and save the United States free from all claims for damages
resulting from the improvement. The provision of a channel from
the project turning basin to the municipal yacht basin at Fort
Myers and of a basin at Stuart is subject to the additional require-
ments that local interests provide, maintain, and operate adequate
mooring and servicing facilities open to all on equal and reasonable
terms, make additional improvements to protect the Fort Myers
yacht basin from wave action, and inclose the Stuart basin in
accordance with plans to be approved by the Chief of Engineers.
    A resolution adopted November 10, 1945, by the IBoard of Com-
missioners of the Okeechobee Flood Control District (an agency
created by the State of Florida to comply with the requirements
imposed by the River and Harbor Act of July 3, 1930) agreeing
to comply with the requirements of local cooperation imposed in
reference to deepening the waterway to 8 feet between Fort Myers
and the Intracoastal Waterway (H. Doc. 696, 76th Cong., 3d
sess.) was accepted by the Chief of Engineers on February 18,
1946, as satisfactory assurance of compliance. All lands and
spoil disposal areas required for the initial work of deepening the
waterway to 8 feet have been furnished. On July 28, 1949, the
Okeechobee Flood Control District adopted two resolutions trans-
ferring the agreements, commitments, and assets of the Okeecho-
bee Flood Control District to the Central and Southern Florida
Flood Control District. On July 14, 1949, the Central and South-
ern Florida Flood Control District adopted a resolution accepting
the assets of the Okeechobee Flood Control District and assuming
its agreements and commitments as of midnight July 31, 1949.
On November 25, 1949; the Chief of Engineers authorized the
Jacksonville district engineer to notify both districts that the sub-
ject transfer was satisfactory to the Corps of Engineers.
    A resolution adopted November 17, 1949, by the City Council of
Fort Myers, agreeing to comply fully with all the requirements
in connection with the side channel at Fort Myers as set forth in
House Document 736, Seventy-Ninth Congress, second session,
was accepted by the Chief of Engineers on January 23, 1950, as
satisfactory assurance of compliance. On March 14, 1945, the
chamber of commerce and city of Stuart, Fla., were requested to
furnish a similar resolution in respect to the basin at Stuart, but
no action has been taken.
    All prior requirements have been fully complied with.
    Terminal facilities. In the vicinity of Fort Myers on the Caloo-
sahatchee River, these consist of three freight piers, one railroad
terminal pier, one municipal recreation pier, four privately owned
piers, and a municipal yacht basin. A mooring basin has been
provided at La Belle. There are numerous small wooden-pile
landings along the upper Caloosahatchee River, along the lake
shore, on St. Lucie Canal, and on St. Lucie River, including one
railroad terminal pier, a municipal pier, and a pier for handling
petroleum products at Stuart. A marginal wharf 30 feet long and
other limited facilities with highway and railway connections are
available on Taylor Creek at the town of Okeechobee. The facili-
382      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

ties are considered adequate for existing commerce.
   Operations and results during fiscal year. Maintenance: Re-
moval of shoals from St. Lucie River between St. Lucie lock and
the Intracoastal Waterway was accomplished with leased plant,
December 30, 1953, to January 31, 1954. Dredge No. 1 removed
97,539 cubic yards of material at a cost of $41,546. Grading of
spoil material from above operations by hired labor cost $3,517.
Removal of shoals in Caloosahatchee River near Ortona lock was
accomplished by leased plant, March 11 to 17, 1954. Dredge
Admiral removed 24,385 cubic yards of material at a cost of
$18,094. Spoil material from that job was graded by hired labor
at a cost of $353. Hired labor removal of floating and submerged
snags and obstructions cost $242. Hired labor surveys, inspec-
tions, and reports cost $10,245.
   Operating and care: Moore Haven and Ortona locks on the
Caloosahatchee Canal and St. Lucie lock on the St. Lucie Canal
were operated and maintained by hired labor throughout fiscal
year at a cost of $50,056.
   The total costs of all work for the fiscal year were $73,997 for
maintenance, and $50,056 for operation and care, a total of
$124,053.
   Condition at end of fiscal year. The existing project was about
99 percent completed, Construction of St. Lucie lock and spillway
at the lower end of St. Lucie Canal near Stuart was begun in Au-
gust 1939 and completed in June 1943 except for installation of
Tainter gates in the spillway, which was completed in March 1950.
An auxiliary lock gate has been installed in the upstream end of
old lock No. 2. That lock, constructed by the Everglades Drain-
age District, is adjacent to and supplements the new lock. Dredg-
ing to deepen the waterway to 8 feet between Fort Myers and the
Intracoastal Waterway near Stuart, with overdepth in St. Lucie
Canal, begun in June 1948, was completed, together with dredging
to provide a channel 8 feet deep and 100 feet wide to connect the
project turning basin at Fort Myers with the municipal yacht
basin, August 9, 1950.
   Features completed under the previous project and maintained
under the existing project are as follows: A channel 12 feet deep
and 200 feet wide from the Gulf of Mexico to Punta Rasa, and
thence 10 feet deep and 100 feet wide to Fort Myers, with a turn-
ing basin at that locality, January 1911 to January 1913; the im-
proved Caloosahatchee Canal and River channel from Moore
Haven to Fort Myers, 56.5 miles, providing a floodway and naviga-
tion channel at least 7 feet deep and 90 feet wide, and with a dis-
charge outlet capacity of 2,500 cubic feet per second from Lake
Okeechobee, February 1931 to June 1937; a channel 8 feet deep
and 80 feet wide in St. Lucie River between Palm City bridge and
St. Lucie lock, about 2.8 miles, September to December 1931; a
channel 6 feet deep and 60 feet wide in Taylor Creek from the town
of Okeechobee to Lake Okeechobee, about 4 miles, July 1936 to
March 1938; 58.3 miles of navigation channel from Moore Haven
lock to St. Lucie Canal, generally 8 feet or more deep with a mini-
mum width of 80 feet, following in general the south shore of the
lake, January 1932 to March 1936; a lock at Ortona, and a com-
             RIVERS AND HARBORS-JACKSONVILLE, FLA., DISTRICT                                                  383
bined lock and hurricane gate at Moore Haven, November 1934 to
June 1943.
   For work constructed under previous projects and now main-
tained under the flood control project for central and southern
Florida, see paragraph "Existing project," central and southern
Florida.
   For information relative to the St. Lucie, Moore Haven, and
Ortona locks, see table in the paragraph "Existing project."
Depths in excess of 8 feet exist in the St. Lucie Canal and across
Lake Okeechobee by following in general the south shore of the
lake. St. Lucie Canal was constructed 8 feet deep and 150 to 165
feet wide by the Everglades Drainage District between 1916 and
1928 as a control canal for Lake Okeechobee. The controlling
depths when last surveyed were as follows: Gulf of Mexico to
Funta Rasa, 12 feet for a width of 200 feet in August 1950; Punta
Rasa to Fort Myers, 10 feet for a width of 100 feet in August 1950;
Fort Myers to Ortona lock, 8 feet for a width of 90 feet in August
1950; Ortona lock to Lake Okeechobee at Moore Haven, 8 feet for
a width of 90 feet in April 1949; Lake Okeechobee from Moore
Haven to St. Lucie Canal via south-shore channel, 9 feet for a
width of 50 feet in April 1949; via Liberty Point floodway chan-
nel and open lake, 5 feet for a width of 60 feet in April 1950; via
Clewiston approach channel, 8 feet for a width of 100 feet in
March 1950; Lake Okeechobee to St. Lucie lock, 9 feet for a width
of 80 feet in November 1949; St. Lucie River from the lock to
Intracoastal Waterway near Stuart, 8 feet for a width of 80 feet
in March 1950; and Taylor Creek from the town of Okeechobee to
Lake Okeechobee, 6 feet for a width of 60 feet in February 1949.
The present controlling channel width of 80 feet is reduced to 50
feet at locks and at 19 localities by bridges.
  The work remaining to be done to complete the project is to
dredge a basin 8 feet deep, 200 feet wide, and 400 feet long at
Stuart.
   The total costs under the existing project to June 30, 1954, have
been $3,803,447 for new work, $415,762 for maintenance, and
$836,789 for operation and care, a total of $5,055,998.
                                          Cost and financial summary

                                                    Fiscal year ending June 30                       Total to June
                                                                                                   30, 19541, includ-
                                                                                                   ing fiscal years
                                   1950          1951          1952        1953        1954          prior to 19502

New work:
   Appropriated--      ---........ $300, 000   -$48, 830 ------------                                   $20, 025, 723
   Cost---_         ---             553, 253      25, 683 ------------                                   20, 025, 723
Maintenance:
   Appropriated- ...-..             361, 000      62, 000     $131, 396   $134, 305
   Cost-----------------            354, 236     172, 347      136, 269    135, 805   3$119, 500
                                                                                        122, 212
                                                                                                          8, 773, 475
                                                                                                          8, 831,860

  1 Includes $16,222,275 for new work and $7,581,150 for maintenance for previous projects.
  2 In addition $500,000 for new work and $1,000 for maintenance were expended on previous projects from
contributed funds.
  a Differs from "Operation and results during fiscal year" by $+1,841.  Pending adjustment.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project____....-...... ...-......................................... $5 ,000




         Sig 13-383-414
384      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

10. INTRACOASTAL WATERWAY, CALOOSAHATCHEE RIVER TO
                     ANCLOTE RIVER, FLA.
   Location. The waterway extends from the mouth of the Caloo-
sahatchee River at Punta Rasa, Fla., to the mouth of Anclote
River, Fla., following in general an almost continuous series of
protected inside waterways along the Gulf coast of Florida. (See
U. S. Coast and Geodetic Survey Charts Nos. 1255-1257.)
   Previous projects. Adopted by the following river and harbor
acts: For the improvement of the inside passage from Punta Rasa
to Charlotte Harbor (Pine Island Sound), act of June 13, 1902;
for Caseys Pass (Venice Inlet), act of August 30, 1935; for Sara-
sota Bay (including Little Sarasota Bay), acts of September 19,
1890, June 3, 1896, March 2, 1907, March 2, 1919, and August
26, 1937; and for Channel from Clearwater Harbor through Boca
Ciega Bay to Tampa Bay, acts of June 25, 1910, and March 2, 1919.
   For further details see page 291, Annual Report for 1904; page
776, Annual Report for 1918; page 662, Annual Report for 1938;
pages 720, 724-725, and 733-734, Annual Report for 1940; pages
692-694, Annual Report for 1941; and page 767, Annual Report
for 1945.
   Existing project. This provides for improvement of the section
of the Intracoastal Waterway from the Caloosahatchee River, Fla.,
to Anclote River, Fla., to a depth of 9 feet at mean low water and
a width of 100 feet, including deepening the existing 100-foot-
wide entrance channel at Caseys Pass (Venice Inlet) ; and for the
construction of a highway bridge over the land cut at Venice, the
operation and maintenance of the bridge to be assumed by local
interests. In the area between Venice and Lemon Bay, the Secre-
tary of the Army, acting through the Chief of Engineers, is au-
thorized to use the original or such other route as may be deemed
feasible by the Chief of Engineers and approved by the Secretary
of the Army. Two parallel jetties 300 feet apart, each 659.4 feet
long and consisting of 19 steel-sheet-pile cylinders connected by
steel-sheet-pile curtain walls, together with the wood-sheet-pile
bulkhead extensions and riprap shore revetments, were con-
structed at the Caseys Pass entrance under a previous project and
are maintained under the existing project. The waterway will
include the existing improved channels in Pine Island Sound from
Punta Rasa to Charlotte Harbor, in Little Sarasota Bay and Sara-
sota Bay from Nokomis to Tampa Bay, through the entrance from
the Gulf of Mexico at Caseys Pass (Venice Inlet), and in Boca
Ciega IBay from Clearwater Harbor to Tampa Bay. On Novem-
ber 4, 1949, the Secretary of the Army tentatively approved a
modification of the route between Caseys Pass and Lemon Bay to
provide a channel through Venice approximately paralleling Park
Boulevard.
   The total length of the waterway is 147.8 miles; the length of
the entrance channel at Caseys Pass is 0.67 mile. The mean
ranges of tide are 1.7 feet at Punta Rasa, 1 foot at Port Boca
Grande, 1.4 feet in Tampa Bay at Anna Maria, and 2 feet at the
entrance to Anclote River. The extreme ranges are about 4.5
feet at Punta Rasa, about 3 to 4 feet between Port Boca Grande
and Corey Causeway over Boca Ciega Bay, and about 5.5 feet at
       RIVERS AND HARBORS-JACKSONVILLE, FLA., DISTRICT                                              385
the entrance to Anclote River. Southerly winds over the area gen-
erally raise the water level by 1 to 1.5 feet; northerly winds lower
the water level by 1 to 2 feet.
  The estimate of cost for new work, approved in 1954, is $5,760,-
000 exclusive of amounts expended on previous projects. The lat-
est (1954) approved estimate for annual cost of maintenance is
$87,000.
The existing project was authorized by the following River and
Harbor Acts:

    Acts                          Work authorized                                   Documents
Mar. 2,1945     The 9-by 100-foot channel, deepening the existing       H. Doc. 371, 76th Cong., 1st sess.
                  channel through Caseys Pass to 9 feet; and con-         (Contains the latest published
                  struction of a highway bridge at Venice, operation     maps).
                  and maintenance to be assumed by local interests.
June 30, 1948   Use of the original or one of three designated alter-   Specified in act.
                  native routes between Caseys Pass and Lemon
                  Bay, provided that the cost to the United States
                  shall not exceed the cost of the original route.
May 17, 1950    Use of such previously authorized routes or any other   Specified in act.
                  route in the Venice and Lemon Bay area as may be
                  deemed feasible by the Chief of Engineers and ap-
                  proved by the Secretary of the Army.


    Local cooperation. The act which adopted the project imposed
the conditions that local interests furnish, free of cost to the
United States, all lands, easements, rights-of-way, and spoil dis-
posal areas for the initial work and for subsequent maintenance,
when and as required; hold and save the United States free from
claims for damages resulting from the improvement; and give as-
surances satisfactory to the Secretary of War that they will as-
sume maintenance and operation of the highway bridge to be con-
structed near Venice. The West Coast Inland Navigation District,
a special taxing district created by the Florida State Legislature
in 1947 to comply with requirements of local cooperation, adopted
a resolution on July 28, 1947, furnishing assurances of compliance.
That resolution was approved by the division engineer on Septem-
ber 19, 1947, as satisfactory assurance of compliance.
    Upon request, the district engineer furnished the West Coast
Inland Navigation District maps showing the spoil areas and
rights-of-way to be acquired for the sections of the waterway
from Tampa Bay to Anclote River and for Caloosahatchee River
to Tampa Bay on May 7 and July 15, 1948, respectively. The
Navigation District has indicated that it is ready to take immediate
action toward procurement of lands required for rights-of-way
and spoil disposal upon request of the district engineer. On April
13, 1950, the West Coast Inland Navigation District adopted a
resolution obligating itself to pay $59,770, representing the esti-
mated excess cost for constructing the Park Boulevard route over
that of the original route. That resolution was forwarded to the
Chief of Engineers on May 5, 1950.
    Terminal facilities. These consist of one phosphate-loading
wharf at Port Boca Grande; 1 municipal concrete pier, 1 railway
pier, 1 freight wharf, 1 marginal wharf 500 feet long on the ter-
minal island, and 10 privately owned landings, all at Sarasota;
6 wharves along IBoca Ciega Bay; and a number of small, privately
386            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

owned piers and wharves at various points along the waterway for
use of commercial fishing boats and recreational craft. The :mu-
nicipal pier and the freight wharf at Sarasota are open to the
public. The railway pier at Sarasota is used mainly for storing
Pullman cars. All other piers have highway connections only.
The facilities are considered adequate for the; existing commerce.
   Operations and results during fiscal year. Maintenance: Hired
labor inspections, reports, and preliminary planning for repairs
to Caseys Pass bulkheads and jetties cost $3,828.
   Condition at end of fiscal year. The existing project was about
3 percent completed. Work has been limited to completion of
about 28 percent of the required detail planning. Under previous
projects, channels, following in general the alinement of the proj-
ect waterway, have been dredged and jetties constructed as fol-
lows:

                       Work                             Depth          Width         Length            Dates
                                                        (feet)         (feet)        (miles)

Channel from Punta Rasa through Pine Island                    7              100         26   April to October 1903.
  Sound to Charlotte Harbor.
Channel in Little Sarasota Bay from Nokomis to                 4          50-75           18   1898 to June 1927.
  Sarasota.
Channel in Sarasota Bay from Sarasota to Tampa                 7              100         38   October 1891 to July
Bay.                                                                                            1939.
Entrance channel from the Gulf of Mexico at                    8              100       0.67   June to October 1937.
  Caseys Pass (Venice Inlet).
Two jetties, each 659.4 feet long and with bulkhead   ...   ............-...-....-             February to July 1937.
  extensions at Caseys Pass (maintained under the
  existing project).
Channel from Tampa Bay to Boca Ciega Bay_,                     8              100       1.25   January to July 1920.
Channel through lower Boca Ciega Bay to Blind                  7              100       7.75   August 1911 to March
Pass.                                                                                           1912.
Channel from Blind Pass to Clearwater Harbor.__                5                50        17   November 1910 to April
                                                                                                 1915.



   When last surveyed the controlling depths in midchannel for
one-half of former project widths were as follows: From Punta
Rasa through Pine Island Sound to Charlotte Harbor, 6 feet in
February 1940; Little Sarasota Bay from Nokomis to Sarasota, 3
feet, and thence in Sarasota Bay to Tampa Bay, 7 feet in Novem-
ber 1945; entrance channel from the Gulf of Mexico at Caseys Pass
 (Venice Inlet), 7.6 feet in December 1951; a channel between
Tampa and Boca Ciega Bays, 8 feet and thence through lower
Boca Ciega Bay to Blind Pass, 7.1 feet, in November 1939; and
from Blind Pass to Clearwater Harbor, 5 feet in April 1940. The
costs under the existing project to June 30, 1954, have been
$167,364 for new work and $44,199 for maintenance, a total of
$211,563.
              RIVERS AND HARBORS-JACKSONVILLE, FLA., DISTRICT                                                       387

                                                 Cost and financial summary

                                                            Fiscal year ending June 30                     Total to June
                                                                                                          30, 1954, includ-
                                                                                                          ing fiscal years
                                         1950             1951            1952       1953      1954        prior to 19501

New work:
      Appropriated --------..-------                 ... ----------        -$744-                                 $682, 844
   Cost            _-----------------     $5, 705             $432    ------------                                 682, 844
Maintenance:
      Appropriated .....                 -- 6, 729                          2, 300   $3, 954   $73, 200            564, 365
      Cost_                                     582 ------------            1, 687    4, 522   2 3, 792            494, 912

  1   Includes $515,479 for new work and $450,749 for maintenance for previous projects.
  2 Differs from "Operation    and results during fiscal year" by $+36. Pending adjustment.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project- ..........- __.....__..... .... $5 ,593,000

                                        11. CHARLOTTE HARBOR, FLA.
    Location. This harbor is a large bay on the west coast of
Florida. The entrance is 68 miles south of the entrance to Tampa
Bay and 150 miles north of Key West. (See U. S. Coast and Geo-
detic Survey Chart No. 1255.)
   Previous projects. Appropriations for removing obstructions
from Peace River (formerly Peace Creek) were made in 1881, 1882,
and 1886. Improvement of Charlotte Harbor and Peace River was
authorized by act of September 19, 1890. A project for improve-
ment of Pine Island Sound is now included in "Previous projects"
for Intracoastal Waterway, Caloosahatchee River to Anclote River,
Fla. For further details see page 152, Annal Report for 1890; page
1828, Annual Report for 1915; and page 769, Annual Report for
1945.
   Existing project. This provides for a channel 32 feet deep at
mean low water and 300 feet wide, increased to 700 feet wide at
the bend, from the Gulf of Mexico to Port Boca Grande, just inside
the entrance, thence 10 feet deep and 100 feet wide to the municipal
terminal at Maud Street, Punta Gorda, with a turning basin 200
feet square at the outer end of the terminal. The length of water-
way included in the project is about 4.5 miles from the Gulf of
Mexico to Port Boca Grande, and thence about 25 miles to Punta
Gorda.
   The mean tidal range is 1 foot at Port Boca Grande and 1.4 feet
at Punta Gorda. The extreme range is about 3 feet at Port Boca
Grande and 3.8 feet at Punta Gorda. Strong southwesterly winds
raise the water level about 1.5 feet, and strong northerly and
easterly winds lower it about 1 foot.
   The estimate of cost for new work, approved in 1954, exclusive of
amounts expended on previous projects and $15,563 contributed by
local interests, is $447,000. The latest (1954) approved estimate
of annual cost of maintenance is $29,000.
   The existing project was authorized by the following River and
Harbor Acts:
388                  REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


       Acts                                      Work authorized                                              Documents

July 25, 1912          A 24-foot channel 300 feet wide from the Gulf of Mexico                   H. Doc. 699, 62d Cong., 2d sess.
                         through the Boca Grande entrance.
Mar. 3,1925            A depth of 27 feet at the entrance and a width of 500                     H. Doc. 113, 66th Cong., 1st
                         feet at the bend.                                                         sess.
July      3,1930       The 10-foot depth to Punta Gorda and the turning                          Rivers and Harbors Committee
                          basin at that point.                                                     Doc. 1, 70th Cong., 1st sess.'
Aug. 26, 1937          The 30-foot depth at the entrance and the 700-foot                        Rivers and Harbors Committee,
                          width at the bend.                                                       Doc. 95, 74th Cong., 2d sess.
May 17, 1950           Deepening the entrance channel to 32 feet.                                H. Doc. 186, 81st Cong., 1st sess.'

   1 Contains latest published maps.

   Local cooperation. Deepening of the entrance channel to 32
feet (H. Doc. 186, 81st Cong., 1st sess.) is subject to the condition
that local interests furnish assurances satisfactory to the Secre-
tary of the Army that they will hold and save the United States
free from damage due to construction of the improvement.
   All prior requirements have been fully complied with.
   Terminal facilities. These consist of a phosphate wharf at Port
Boca Grande and a municipal earth-fill pier about 850 feet long, re-
tained by steel-sheet-piling, at Punta Gorda. Both wharves are
open to the public. Railway connections are available at Port Boca
Grande, and highway and railway connections are available at
Punta Gorda. The facilities are considered adequate for existing
commerce. (For further details see Port Series No. 8, Corps of
Engineers.)
   Operations and results during fiscal year. Maintenance: U. S.
hopper dredge Langfitt removed 167,486 cubic yards of material,
bin measurement, at a cost of $41,586, October 3 to 14, 1953.
Hired labor inspections and reports cost $783. The total costs for
the fiscal year were $42,369 for maintenance.
   Condition at end of fiscal year. The existing project was about
42 percent completed. A channel 24 feet deep and 300 feet wide
from the Gulf of Mexico to Port Boca Grande was dredged between
November 1912 and April 1913; was deepened to 27 feet (500 feet
wide at the bend) between October and November 1931; and was
further deepened to 30 feet (700 feet wide at the bend) between
August 1938 and August 1939. The 10-foot channel to Punta
Gorda was dredged from February to April 1931.
   When last surveyed the controlling depths were as follows:

                                                             Controlling depths entering from seaward

                 Name of channel                              Left out-          for
                                                                                Mdhanel           Right out-       Date surveyed

                                                             side quarter        project          side quarter
                                                                 (feet)          width               (feet)
                                                                                  (feet)


Outer bar cut--.                                                         28.0
                                  .................--------------------------          30.0               28.0   November 1953.
Widener..--.......-------------...----------------........             32.2            30.0               26.3       Do.
Inner bar cut----------------------------                              26.0            27.8               30.0    May 1953.
Channel to Punta Gorda ------------------------------                                      9.5   -------------    February 1950.


     The work remaining to be done to complete the project is dredg-
ing to deepen the existing entrance channel to 32 feet.
  The total costs under the existing project to June 30, 1954, have
            RIVERS AND HARBORS-JACKSONVILLE, FLA., DISTRICT                                                               389
been $193,965 for new work, and $790,123 for maintenance, a total
of $984,088. In addition, $15,563 was expended from contributed
funds for new work in Boca Grande entrance channel.
                                                Cost and financial summary

                                                                Fiscal year ending June 30                      Total to June
                                                                                                               30, 19541, includ-
                                                                                                               ing fiscal years
                                       1950                   1951        1952         1953        1954         prior to 19502

New work:
    Appropriated-------.......    -----------............            -------                ----    ------              $306, 965
              .            .
    Cost-----------------------                    - ------          --------------    -- ---------------------          306, 965
Maintenance:
    Appropriated___-
                   -                   $75, 085                $2, 449    $76, 150    -$4, 303     $42, 450              790, 204
    Cost----------------                75, 428                 2, 183     68, 940        3, 172   8 42, 376             790,130


  1Includes $113,000 for new work for previous projects.
  2 In addition $15,563 for new work was expended on the existing project from contributed funds.
  3 Differs from " Operation and results during fiscal year" by $-7.Pending adjustment.
Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project__....................................................... $253 ,000

                                         12. TAMPA HARBOR, FLA.
   Location. This harbor is a large natural indentation of the Gulf
of Mexico about midway of the western coast of the peninsula of
Florida. The entrance is about 220 miles north of Key West, about
330 miles from Pensacola, 360 miles from Mobile, and 512 miles
from New Orleans. (See U. S. Coast and Geodetic Survey Charts
Nos. 586, 587, and 1257.)
   Previous projects. Adopted by the following river and harbor
acts: For Tampa Bay, acts of June 14, 1880, and August 11, 1888;
for Tampa and Hillsboro Bays, acts of June 14, 1880, March 3,
1899, and March 3, 1905; for Hillsboro River, act of June 14, 1880.
For further details see pages 1829, and 1831 of the Annual Report
for 1915, and page 665, Annual Report for 1938.
   Existing project. This provides for (1) Channels from the
Gulf of Mexico through Tampa and Hillsboro Bays and upper
Tampa Harbor to the city of Tampa, and through Tampa Bay to
Port Tampa, 36 feet deep and 600 feet wide in Egmont Channel,
thence 34 feet deep with widths of 500 feet in Mullet Key Cut, 400
feet in Tampa Bay, Hillsboro Bay, Port Tampa, and Sparkman
Channels, and 30 feet deep with widths of 500 feet in Ybor Chan-
nel and 300 feet in Seddon and Garrison Channels; (2) widening the
bend between Sparkman Channel and Cut D of Hillsboro Bay Chan-
nel by 250 feet; (3) a turning basin 30 feet deep at the mouth of
Hillsboro River (west end of Garrison Channel), involving cutting
back the northwest corner of Seddon Island by 150 feet; (4) a turn-
ing basin 34 feet deep at the entrance to Ybor Channel, including
widening the bend between Sparkman and Garrison Channels by
cutting back the northeast corner of Seddon Island (to about 950
feet from the point of intersection of the edges of the two chan-
nels) and cutting off the resulting corners; (5) a turning basin at
the entrance to the Port Tampa terminals, 34 feet deep, 2,000 feet
long, and 750 feet wide; (6) maintenance of a channel dredged in
Hillsboro River under a previous project, 12 feet deep, 200 feet
wide, and 2,400 feet long, from the turning basin at the mouth to
 390                 REPORT OF CHIEF OF ENGINEERS., U. S. ARMY, 1954

a point 100 feet south of the Lafayette Street Bridge, and provi-
sion of a channel 9 feet deep and 100 feet wide, thence to a point
2,000 feet upstream from the Columbus Drive (formerly Michigan
Avenue) Bridge, with a removal of snags, wrecks, and piling,
thence to the Florida Avenue Bridge; (7) a channel 30 feet deep
and 200 feet wide from.the ship channel in Hillsboro Bay to and
including the existing turning basin in the Alafia River, to be en-
larged to a depth of 30 feet, a width of 700 feet, and a length of
1,200 feet; (8) construction of a breakwater of dredged material
at Peter 0. Knight Field, Davis Islands, about 2,000 feet long and
partially inclosing a landing basin for seaplanes (maintenance to
be assumed by local interests). The length of the section included
in the existing project is about 64.1 miles, including about 7.7 miles
in the Hillsboro River and about 3.6 miles in the Alafia River Chan-
nel. The plane of reference is mean low water.
   The mean range of tide is 1.3 feet at the lower end of the bay,
1.6 feet at Port Tampa, and 1.8 feet at Tampa. The extreme range
is about 3.8 feet at the lower end of the bay and 4.8 feet at Tampa.
Strong southwesterly winds raise the water level about 1.5 feet.
Strong northerly winds, which usually occur in winter, lower the
water level about 2 feet.
   The estimate of cost for new work, approved in 1954, is $21,-
383,000 excluding amounts expended on previous projects. The
latest (1954) approved estimate of annual cost of maintenance,
excluding the breakwater at Peter O. Knight Field, is $172,500.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                                Work authorized                                   Documents
                 I                     i
                                              TAMPA BAY

Mar.    3,1899       For a channel 27 feet deep from the Gulf of Mexico to       H.  Doc. 52, 55th     Cong., 3d sess.
                       Port Tampa, 500 feet wide across the bar and 300            (also printed in    Annual Report
                       feet wide in the bay.                                       1899, p. 1640).     Channel dim-
                                                                                  ensions specified   in act.
Mar.    3,1905       For a channel depth of 26 feet with sufficient width        Specified in act.
                      from the Gulf of Mexico to Port Tampa.
                                  TAMPA AND HILLSBORO BAYS

June 25, 1910        For a depth of 24 feet in Hillsboro Bay.                    H. Doec. 634, 61st Cong., 2d sess.
Aug. 8,1917          For a 27-foot depth from Gulf of Mexico up to and in        H. Doec. 1345, 64th Cong., 1st sess.
                      the several channels of Hillsboro Bay, the widths
                      to be 500 feet on the bar, 300 feet in Tampa Bay,
                      Ybor and Garrison Channels, and 200 feet in Hills-
                       boro Bay, Sparkman and Seddon Channels, with
                       turning basins at the mouth of Hillsboro River and
                       at Ybor Estuary.
                                           HILLSBORO RIVER

Mar.    3,1899       For a 12-foot channel to within 100 feet of the Lafayette   H. Doec. 545, 55th Cong., 2d sess.,
                       St. highway bridge (maintenance only); new work           and Annual Report for 1898, pp.
                       completed under a previous project under the title          1357-1360.
                       "Improving Hillsboro Bay, Fla."
                                           TAMPA HARBOR

Sept. 22, 1922       Consolidation of the above projects to form a single        Specified in act.
                      project for Tampa Harbor.
              RIVERS AND HARBORS-JACKSONVILLE, FLA., DISTRICT                                             391
       Acts                       Work authorized                                    Documents
July    3,1930Increasing the depth of Egmont Channel to 29 feet          H. Doc. 100, 70th Cong., 1st sess.
                 and the width of Sparkman Channel to 300 feet.
Aug. 30,19351 For a depth of 32 feet and a width of 600 feet on Egmont   S. Doc. 22, 72d Cong., 1st sess.
                 Bar, a depth of 30 feet and a width of 400 feet in
                 Mullet Key Cut, and a depth of 30 feet and a width
                 of 300 feet in all other project channels in Tampa
                Harbor (except in Hillsboro River and in the
                channel leading to Alafia River); and for a turning
                basin 2,000 feet long and 550 feet in maximum width
                at the entrance to the Port Tampa terminals.
June 20,1938 For widening the bend between Sparkman Channel              S. Doc. 164, 75th Cong., 3d sess.
                and Cut D of Hillsboro Bay Channel by 250 feet;
                widening Ybor Channel to 400 feet and extending
                the turning basin at the west end of Garrison Chan-
                nel (mouth of Hillsboro River) easterly for 300 feet.
   Do....... For construction of a breakwater at Peter O. Knight         Senate Committee   2    Print,      76th
                Field, Davis Islands, its maintenance to be as-            Cong., 1st sess.
                sumed by local interests.
Mar. 2,1945 For widening Sparkman Channel to 400 feet and                S. Doc. 183, 78th Cong., 2d sess.
                Ybor Channel to 500 feet; widening the bend be-
                tween Sparkman and Garrison Channels and
                additional 250 feet to extend the turning basin
                westerly; and widening the bend between Seddon
                and Garrison Channels by 150 feet (in lieu of 300
                feet previously authorized) to extend the turning
                basin easterly.                                                                                 2
Mar. 2,1945 For a channel 9 feet deep and 100 feet wide in the           H. Doc. 119, 77th Cong., 1st sess.
                Hillsboro River for about 2.4 miles above the upper
                end of the existing 12-foot channel, and for the re-
                moval of obstructions thence to the Florida Ave.
                Bridge.
Mar. 2,1946 For a channel 25 feet deep and 150 feet wide from the        S. Doc. 16, 77th Cong., 1st sess.
                Hillsboro Bay Channel to and including a turning
                basin in the Alafla River. (Revoked by act of May
                17, 1950.)
May 17,1950 For deepening Egmont Channel to 36 feet; enlarging           H. Doc. 258, 81st Cong., 1st sess.'
                Mullet Key Cut, Tampa Bay Channel, Hillsboro
                Bay Channel, Port Tampa Channel and Port
                Tampa turning basin to present project dimen-
                sions; deepening Sparkman Channel and Ybor
                turning basin to 34 feet; a channel 30 feet deep and
                200 feet wide from Hillsboro Bay Channel to and
               including a turning basin in Alafla River, 700 feet
                wide and 1,200 feet long (in lieu of the improvement
                previously authorized); and substantial widening
                at entrance, bends, and turns.

1 Included in Public Works Administration program Sept. 6, 1933.
2Contains the latest published maps.

  Recommended modification of project. Under date of March 9,
1950, the Chief of Engineers recommended modification of the
existing project to provide for removal of snags, wrecks, piling, and
similar obstructions from the channel of Hillsboro River between
the upstream end of the existing project at the Florida Avenue
Bridge and the city waterworks dam, at an estimated cost to the
United States of $16,600 (1954) for new work, provided that local
interests, among other requirements of local cooperation, maintain
the cleared channel after completion in accordance with regula-
tions prescribed by the Secretary of the Army (H. Doc. 567, 81st
Cong., 2d sess.).
   Local cooperation. The River and Harbor Act of June 20, 1938
 (S. Doc. 164, 75th Cong., 3d sess.), authorized widening the bend
between Sparkman Channel and Cut D of Hillsboro Bay Channel
by 250 feet, widening Ybor Channel from 300 to 400 feet, and ex-
tending the turning basin at the west end of Garrison Channel
392      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

easterly for 300 feet, subject to the conditions that local interests
furnish, free of cost to the United States, necessary rights-of-way
and suitable spoil disposal areas for new work and for subsequent
maintenance as required, and move and reconstruct all bulkheads,
wharves, buildings, roads, railroad tracks, and all other structures
as may be necessary.
   The River and Harbor Act of March 2, 1945, authorized the fur-
ther widening of Ybor Channel to 500 feet, widening Sparkman
Channel to 400 feet, widening the bend between Garrison and
Sparkman Channels, and reducing the widening between Seddon
and Garrison Channels from 300 to 150 feet (S. Doc. 183, 78th
Cong., 2d sess.), subject to the conditions that the City of Tampa
agree to commence and complete promptly, the construction of the
belt-line railroad and the paving of streets on the north and east
sides of Ybor Channel (first required by River and Harbor Act of
August 8, 1917, and complied with as regards the west side of the
channel) when necessary in the judgment of the Secretary of War;
and provided further, that local interests furnish, free of cost to
the United States, all lands required for the provision of the im-
provements and for the disposal of dredged material during con-
struction, and for subsequent maintenance as and when required,
and construct such bulkheads and retaining walls, and strengthen
or move adjacent structures, as may be required to safeguard both
the channels and the adjacent lands and structures, all in a manner
satisfactory to and approved by the Chief of Engineers and Secre-
tary of War, and agree to hold and save the United States free
from claims for damages resulting from the improvement.
   In 1945 the Florida Legislature adopted a bill creating the Hills-
borough County Port Authority as the governing body and au-
thority of the area defined in the act as Hillsborough County Port
District, comprising approximately the northwest quarter and
part of the southwest quarter of Hillsborough County. It includes
all channel and terminal areas of Tampa and Port Tampa, but
excludes the Alafia River and the relatively undeveloped area east
of the upper harbor. On September 9, 1949, the Hillsborough
County Port Authority adopted a resolution agreeing to comply
with all conditions imposed in Senate Document 164, Seventy-fifth
Congress, third session. On October 11, 1949, the port authority
adopted a resolution agreeing to, and assuming full responsibility
for compliance with, the requirements as set forth in Senate Docu-
ment 183, Seventy-eighth Congress, second session, except any re-
quirement to extend the trackage of the municipal belt-line rail-
road (extension not now required in accordance with the pro-
visions of the River and Harbor Act of May 17, 1950), but specifi-
cally including the obligation in respect to the portion thereof
already completed. The Chief of Engineers accepted those resolu-
tions on November 21, and December 28, 1949, respectively, as
satisfactory assurance of compliance.      The port authority has
furnished, or caused to be furnished, all lands, easements, rights-
of-way, and spoil disposal areas required for new work provided
for in those documents. All streets on the west side of Ybor
Channel have been paved, and the through streets on the north and
east sides have been paved. In addition, the port authority has
      RIVERS AND HARBORS-JACKSONVILLE, FLA., DISTRICT           393
furnished evidence satisfactory to the district engineer that the
United States will be held harmless in the event of sloughing of
banks as a result of dredging. The width of Ybor Channel has
been restricted to a minimum of 480 feet at some localities to make
unnecessary the construction of bulkheads and retaining walls and
the strengthening or moving of structures.
   The River and Harbor Act approved March 2, 1945, authorized
certain improvements in Hillsboro River (H. Doc. 119, 77th Cong.,
1st sess.) subject to the conditions that local interests furnish,
free of cost to the United States, all lands, easements, rights-of-
way, and suitable spoil disposal areas for initial work and subse-
quent maintenance when and as required; agree to make at their
expense necessary alterations to structures crossing the river; and
hold and save the United States free from claims for damages
resulting from the improvement. The Hillsborough County Port
Authority has indicated that it will comply with these require-
ments when it becomes evident that funds will be made available.
   The work authorized by the River and Harbor Act approved
May 17, 1950, is subject to the conditions that for new work re-
sponsible local interests give assurances satisfactory to the Secre-
tary of the Army that they will: (1) Provide without cost to the
United States all lands, easements, rights-of-way, and spoil dis-
posal areas necessary for construction and subsequent mainte-
nance of the project, when and as required; (2) hold and save the
United States free from damages due to the construction and sub-
sequent maintenance of the works; (3) construct such bulkheads
and retaining works, and strengthen or move adjacent structures
as may be required, prior to dredging, to safeguard the channels,
basins, and adjacent lands and structures, in accordance with
plans approved by the Chief of Engineers; (4) provide, prior to or
concurrently with the Federal improvement, additional or en-
larged slips and berthing space with necessary terminal facilities
at Port Tampa in accordance with plans approved by the Chief of
Engineers: (5) open existing terminal facilities on Alafia River to
all at the same rates and charges that apply to other Tampa Har-
bor terminals and expand those facilities as and when required to
meet the needs of commerce; and (6) open the terminal facilities
at Tampa Harbor to all on equal terms.
   The project document further provides: (1) that the existing
conditions of local cooperation whereby approval of wharfage
charges by the Secretary of War is required (River and Harbor
Act of August 8, 1917), be revoked; (2) that the requirements
pertaining to the municipal belt-line railroad imposed by the River
and Harbor Act of August 8, 1917 (H. Doc. 1345, 64th Cong., 1st
sess.) and by the River and Harbor Act of March 2, 1945 (S. Doc.
183, 78th Cong., 2d sess.) be modified so as to require no further
extension of trackage with the understanding that the city's obli-
gation with respect to the completed portion shall remain in force
until relieved by the Chief of Engineers.
   All other and prior requirements have been fully complied with.
   Terminal facilities. There are 57 piers and wharves at Tampa,
including 14 on Hillsboro River at Tampa, 28 other piers within
the Tampa City limits, 1 at East Tampa, 13 on the slip at Port
394       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Tampa, and 1 on old Tampa Bay at Rattlesnake, Fla. Those on
Hillsboro River are suitable for small vessels drawing up to 11
feet; all others are used by deep-draft vessels. The municipal
terminals are on Ybor Channel and consist of a slip 778 feet long,
250 feet wide, with a wharf on either side, one of which has a
steel-frame transit shed. The City of Tampa also owns a shore
wharf on Hillsboro River and another on Garrison Channel.
Forty-eight of the facilities, including the municipal slip, have
railway connections, and all have highway connections. The
municipal terminals, 1 city wharf, and 10 private terminals are
open to the public. The piers and wharves on the various channels
are used principally as follows: 39 for general chargo and private
commodities, 10 for mooring or berthing vessels at shipyards, and
3 for various industrial purposes; 5 are not in use. The facili-
ties are considered adequate for the existing commerce except at
Port Tampa. (See Port Series No. 17, revised 1947, Corps of
Engineers.)
    Operations and results during fiscal year. Maintenance: U. S.
hopper dredge Langfitt removed 7,917 cubic yards of material,
place measurement, from spot shoal in Egmont channel, October
15 to 17, 1953, at a cost of $8,179. Hired labor surveys cost $8,603.
Hired labor inspections and reports cost $6,130. The total costs
for the fiscal year were $22,912 for maintenance.
    Condition at end of fiscal year. The existing project was about
48 percent completed. Dredging was begun in August 1899 to
provide a channel 24 feet deep and of sufficient width from the
Gulf of Mexico to Port Tampa, and in November 1910, to provide
a channel of the same depth in Hillsboro Bay to Tampa. Dredging
has been continued intermittently to secure greater depths and
widths as authorized from time to time. Egmont Channel, 29
feet deep and 500 feet wide was completed in July 1931, and chan-
nels 30 feet deep, 400 feet wide at Mullet Key Cut and Tampa iBay
Channel Cut A, 300 feet wide thence to and including the Port
Tampa Channel, Hillsboro Bay Channel, Seddon Channel, Spark-
man Channel, Ybor Channel, and 275 feet wide in Garrison Chan-
nel were completed in June 1936. Egmont Relocation Channel, to
replace the old channel alinement on Egmont Bar, was dredged 32
feet deep and 600 feet wide from February 1938 to May 1939.
Sparkman Channel was widened to a total width of 400 feet and
the bends between Sparkman Channel and Cut D of Hillsboro Bay
Channel were widened to project dimensions between July 1947
and May 1949. A turning basin 2,750 feet long and 550 feet wide
was dredged at the entrance to the Port Tampa terminals between
November 1933 and December 1935. The turning basin at the
entrance to Ybor Channel was completed in July 1947, and that at
the west end of Garrison Channel (mouth of Hillsboro River), in
May 1949. Ybor Channel was widened to its present width be-
tween April and June 1950.
    A channel 12 feet deep and 200 feet wide in Hillsboro River
from the mouth to within 100 feet of the Lafayette Street Bridge
was dredged between December 1899 and about June 1905, under
a previous project, and has been maintained under the existing
project. The breakwater of dredged material at Peter O. Knight
          RIVERS AND HARBORS-JACKSONVILLE, FLA., DISTRICT                                                              395
municipal airport was constructed from August 1940 to January
1941, and the city of Tampa has formally assumed responsibility
for its care, preservation, and maintenance.
  The Tampa Bay bridge (fixed), under construction, will cross
cut A of Tampa Bay channel with vertical clearance of 149.0 feet
for 800 feet width.
  When last surveyed the controlling depths were as follows:

                          Dredged dimensions                     Controlling depths entering
                                                                        from seaward
                                                          I

                                         i




         Section                                              Left out-
                                                                           Channel
                                                                                              Right
                                                                                                         Date surveyed
                                                                           for half
                              Width          Depth              side
                                                                           dredged           outside
                              (feet)         (feet)           quarter       width            quarter
                                                               (feet)                         (feet)
                                                                            (feet)
                                                                                         i




Egmont        Relocation           600            32              32.1            32.0          31.0   August and
   Channel.                                                                                              November 1953.
Mullet Key Cut__..-.               400            30              30.3            30.3          31.8   August 1953.
Tampa Bay Channel:                                                                                     January 1948.
    Cut A      -...........        400            30              30.0    *30.0 (30.0)          31.0
     Cuts B to F..........         300            30              30.5    *30.0 (30.0)          31.0
Port Tampa Channel--....           300            30                      *30.0 (30.0)                 October 1952.
Port Tampa turning                 550            30                              30.0                 October 1952.
  basin.
Hillsboro Bay Channel:
    Cut A........-.......          300            30              30.0    *30.0 (30.0)          30.0   January 1948.
     Cut C...............          300            30              32.0            28.0          26.1   August 1953.
     Cut D--------------_          300            30              27. 3           27.0          25.0      Do.
Upper Harbor:
    Seddon Channel ...           300              30              27.8    *26.2 (28.5)          26.2   April 1952.
    Sparkman Channel _           400              30              28.8    *28.8 (28.8)          29.5      Do.
    Garrison      Channel      1 275              30              26.8    *24.8 (25.5)          25.2      Do.
       (west to east).
Ybor Channel-...........       2   480            30              30.8           28.8           29.0   August 1953.
Alafia Rivers............          150            23              14.7           17.0           11.0   April 1946.
Hillsboro River, mouth             200            12               9.0           10.9            9.0   March 1944.
  to Lafayette Street
  Bridge.
Thence to a point 2,000        4   100                9                           4.1                  1939.
feet upstream from
  Columbus Drive
  Bridge.

1 Project width 300 feet.
2 Project width at 500 feet.
8As dredged by local interests; project depth is 30 feet, and width 200 feet.
4 Project dimensions; no work has been done by the United States.
 * Figures enclosed in parentheses are controlling depths on centerline in October 1952.


  The work remaining to be done to complete the project is as
follows: Dredge a channel 9 feet deep and 100 feet wide in Hills-
boro River for about 2.4 miles above the upper end of the existing
12-foot channel, and thence remove obstructions to the Florida
Avenue Bridge; and the improvements authorized by act of May
17, 1950 (H. Doc. 258, 81st Cong., 1st sess.).
  The total costs under the existing project to June 30, 1954,
have been as follows:
396                  REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


                                                                                                                   Costs
                                       Funds
                                                                                              New work            Maintenance            Total

Regular........................................-------------------------------------------.     $7,391,414      $2, 759,374 $10,150,788
Public works........................----------------------------------------                     1,329,300 ---------------- 1,329,300
Emergency relief            ... -....----------
                                    .         .           ... ------------
                                                            ......                                1,463,000 -----. ---.        --..     1,463,000
        Total _---------              --------------------------------......                     10,183,714           2,759,374        12, 943, 088



                                                     Cost and financial summary

                                                                  Fiscal year ending June 30                                      Total to June
                                                                                                                                 30, 1954, includ-
                                                                                                                                 ing fiscal years
                                            1950               1951               1952                 1953        1954           priorto 19501

New work:
     Appropriated------....                $414, 987        -$25, 605 ....................................                            $11, 036, 764
   Cost.................                    333, 668            72, 249       .- -.           -----.               -......... 11, 036, 764
Maintenance:
     Appropriated..--------                   65, 300          257, 060         $202, 800              $15, 134    $20, 850             2, 776, 446
     Cost---.. - --.----                      62, 490          260, 134           203, 463              13, 889     222, 785            2, 776, 353

  1 Includes      $853,050 for new work and $17,107 for maintenance
                                                               '    for previous projects.
  2 Differs from "Operation and results during fiscal year                            by $+127.

Other new work data: Estimated additional amount needed to be appro-
                                                                     $11, 199,000
  priated for completion of existing project __.........-.................................

                                    13. WITHLACOOCHEE RIVER, FLA.
   Location. This river rises in the central part of the peninsula
of Florida and flows generally northwesterly and westerly, empty-
ing into the Gulf of Mexico about 20 miles southeast of Cedar Key,
Fla., and 95 miles north of the entrance to Tampa Bay. (See U. S.
Coast and Geodetic Survey Chart No. 1259.)
   Previous projects. A project for the improvement of the en-
trance was adopted by the River and Harbor Act of June 13, 1902.
For further details see page 1832 of the Annual Report for 1915,
and page 523 of Annual Report for 1934.
   Existing project. This provides for securing and maintaining
a channel 10 feet deep at mean low water and 100 feet wide from
the Gulf of Mexico to Port Inglis, just within the river entrance,
by dredging and rock excavation; maintaining the channel be-
tween the river mouth and Inglis (steam-electric plant) 10 feet
deep and generally 70 feet wide; and removing snags, overhang-
ing trees, and loose rock, and cutting through shoals in the upper
river, to make a draft of 2 feet available for about half the year as
far as Croom (formerly Pembertons Ferry), 85 miles above the
mouth. The Second Deficiency Appropriation Act, 1944, approved
June 28, 1944, authorized the use of appropriations for rivers and
harbors for the improvement, in the interests of national defense
and subject to the approval of the Chief of Engineers, of the
channel between the mouth of the river and Inglis. The author-
ized work comprises the provision of a practical channel 10 feet
deep at mean low water and 70 feet wide, with easing of bends,
from Port Inglis to the steam-electric plant at Inglis, by dredging
and rock excavation. The lengths of the sections included in the
project are 4.1 miles from the Gulf to Port Inglis, thence 6.4 miles
            RIVERS AND HARBORS--JACKSONVILLE, FLA., DISTRICT                                          397
to the steam-electric plant at Inglis, and thence about 78.6 miles to
Croom. The mean tidal range at the mouth is 2.8 feet and the
spring range about 3.5 feet. The effect of the tide is perceptible
for about 11 miles above the mouth. Strong southwesterly winds
raise the water level at the mouth about 1 foot, and strong north-
erly winds, which usually occur during the winter, lower the water
level about 1.5 feet. Freshets raise the water level in the upper
river from 4 to 6 feet and at the mouth about 1 foot.
   The estimate of cost for new work, revised in 1954, is $666,000
excluding amounts expended on previous projects, but including
$299,859 for the improvement of the channel between the mouth
and Inglis. The latest (1954) approved estimate of annual cost of
maintenance is $12,000.
   The existing project was authorized by the following River and
Harbor Acts:

     Acts                            Work authorized                                Documents

Mar. 3,1881      Improving river from mouth to Hays Ferry, 79 miles.     Annual Report, 1880, pp. 1110-1119.
Aug. 5,18861     Extending improvement to Croom (Pembertons              Annual Report, 1885, pp. 1277-1278.
                   Ferry), 6 miles above Hays Ferry.
Mar. 2, 1907     A depth of 10 feet below mean low water from the        H. Doc. 483, 59th Cong., 2d sess.
                  Gulf to Port Inglis.
June 28, 19442   Use of appropriations for rivers and harbors for im-    Specified in act.
                  proving the channel between the mouth and Inglis.
July 24,1946     Maintaining the channel 10 feet deep and generally      H. Doc. 293, 79th Cong., 1st sess.
                      70 feet wide between the river mouth and Inglis.     (Contains latest published maps.)

  'Modified in accordance with recommendations in Annual Report for 1885. (See also Annual Report for
    1887, p. 1248.)
  2Second Deficiency Appropriation      Act, 1944.

   Local cooperation. The River and Harbor Act approved July
24, 1946, imposed the condition that local interests agree to fur-
nish, free of cost to the United States, all rights-of-way and spoil
disposal areas necessary for the maintenance work when and as
required, and hold and save the United States free from damages
due to the maintenance work.
   Terminal facilities. These consist of one small timber dock at
Inglis, with shore facilities for fuel-oil storage; one dock at
Yankeetown, with shore facilities for gasoline storage; two small
docks for handling fish--one each at Yankeetown and Inglis; one
small dock at Panasoffkee, open to public use; and several privately
owned docks along the river. The facilities are considered ade-
quate for existing commerce.
   Operations and results during fiscal year. Maintenance: Con-
tract dredge No. 6 removed 55,288 cubic yards of material restor-
ing project depth from the Gulf of Mexico to the Power Plant,
April 14 to May 24, 1954, at a cost of $44,023. Hired labor inspec-
tions and reports cost $880. The total cost for the year was
$44,903 for maintenance.
   Condition at end of fiscal year. The existing project as a whole
was about 88 percent completed. The entrance channel was about
85 percent completed. A channel 10 feet deep and 85 feet wide
from the 10-foot contour in the Gulf of Mexico to Port Inglis was
dredged between April 1908 and November 1914. A practical
channel 10 feet deep and 70 feet wide, with easing of five sharp
bends, from the mouth of the river to the steam-electric plant at
398                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Inglis was provided by dredging and rock excavation between
June 1945 and March 1946. Removal of snags, overhanging
trees, sunken logs, loose rock and boulders, and some rock ledges
from the river between its mouth and Croom was begun in March
1882 and was practically completed in 1892, thereby enabling
light-draft boats to ascend the river to Croom, except at low-water
stages. Under permit granted by the Secretary of War on April
16, 1904, a power dam and a lock 134 feet by 36 feet, now owned
and operated by the Florida Power Corporation, were built about
11.4 miles above the mouth of the river. The dam creates a pool
extending nearly to Dunnellon, 24.5 miles above the mouth. The
lock, which had been inoperative since installation of the gates in
1916 except for about 7 months during 1926, was restored to
operating condition in January 1942. The lock is in poor condition
and the gates require considerable time and manpower to open
and close.
   When last surveyed, controlling depths were as follows: Gulf of
Mexico to Port Inglis 10.0 feet (based on 72 percent of channel
width) in May 1954; Port Inglis to power plant at Inglis, 10.0 feet
 (based on 80 percent of project width) in May 1954; Inglis to
Dunnellon, 4 feet in May 1940; and thence to head of navigation at
Croom, about 2 feet during half the year with 1 foot during low
stages. The depths are referred to mean low water Gulf datum,
between the entrance and the dam, and to local low-water stage of
the river above that point. The river from the Florida Power
Corporation dam, including Rainbow Run, to Stokes Ferry, was in
poor condition and snagging is necessary to clear the river for
navigation. From Stokes Ferry to Croom, the river was in fair
condition, having less fallen trees.
   The work remaining to be done to complete the project is the 15-
foot widening of the entrance channel to Port Inglis, which is not
considered necessary at this time.
   The total costs under the existing project to June 30, 1954, have
been $584,912 for new work and $227,600 for maintenance, a total
of $812,512.
                                                 Cost and financial summary

                                                        Fiscal year ending June 30                                      Total to June
                                                                                                                        30, 1954, includ-
                                                                                                                        ing fiscal years
                                          1950        1951            1952               1953               1954         prior to 19501
New work:
    Appropriated ...                                                                                   --------------              14, 912
                                                                                                                                $6-------------------------------
    Cost----...----------------------------                     ------------------------------------                             614, 912
Maintenance:
    Appropriated- -------                 $45, 029   -$7, 190           $3, 680            $4, 100          $44, 350             227,620
    Cost ---------------                   13, 644     26,124            3, 877             3, 372          2 44, 700            227,397


  1 Includes $30,000 for new work for previous project.
  2 Differs from "Operation and results during fiscal year" by $+203. Pending adjustment.
Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project-...................................................... $81,000
              RIVERS AND HARBORS-JACKSONVILLE, FLA., DISTRICT                                                                         399
      14. REMOVING THE WATER HYACINTH FROM NAVIGABLE
               WATERS IN THE STATE OF FLORIDA
   Location. The water hyacinth is found in the fresh water
streams and lakes in various parts of the district.
   Existing project. This provides for the destruction or removal
of the water hyacinth in the navigable waters of the State so far
as they constitute an obstruction to commerce, using any me-
chanical, chemical, or other means not injurious to cattle, and the
use of log booms to close sloughs and backwaters as an auxiliary
means. No estimate of the final cost of the work has been made.
The latest (1954) approved estimate of annual cost of mainte-
nance is $100,000.
   The existing project was authorized by the following River and
Harbor Acts:

      Acts                                   Work authorized                                                   Documents

Mar. 3,1899          For the construction and operation of a suitable                           H. Doc. 91, 55th Cong., 3d sess.
                        vessel, and for the use of log booms as adjuncts to                       and Annual Report 1899, pp.
                        the operation of the vessel, for the removal of water                     1613-1623.
                       hyacinths in the navigable waters of the State of
                       Florida.
June 13, 1902        For the extermination and removal of water hya-                            Specified in act.
                       cinths by any mechanical, chemical, or other means.
Mar. 3,1905          Prohibits the use of any chemical process injurious to                          Do.
                       cattle.



  Local cooperation. None required.
  Operations and results during fiscal year. Maintenance: Lo-
calities where hired labor operations were conducted during the
year and costs thereof are tabulated below:

                                                       Locality                                                                     Cost

St. Johns River and tributaries ......................................---------------------------------------------------..           $58, 496
Okeechobee Waterway.............----------------..........-----------------------------......................-----------------...       3, 375
Hillsboro River        ...-----------...               ...---------------------
                                                 ......-----                               -----------------------------                   148
Withlacoochee River---------------------------------------------------------------------                                                2, 728
Reports------------------------------------------------------------------------                                                            40
        Total cost ..-------....--------....---------------------------------------------------.                                       64, 787



  Condition at end of fiscal year. The project is for maintenance.
A chemical for spraying was tested in August and September
1900; spraying was begun in November 1902, but was discontinued
in February 1906 because of the injurious effect on cattle. Sub-
sequent operations through the fiscal year 1938 consisted chiefly
of breaking up jams and drifting, except from November 1909
to February 1918, when an elevator was used to either place the
plants on shore to form them in deep piles that could be carried
away by the currents. Later operations, through April 1948,
have consisted principally of construction of temporary and per-
manent traps at strategic points, and shredding with cutter
boats. Spraying with a new chemical, which is not injurious to
cattle or fish, was begun in March 1948, to supplement other
methods, and has proven to be highly effective. Since that date,
spraying has gradually become the principal method of destruc-
tion, supplemented by the methods previously in use. During
September 1949, large areas of hyacinths in the St. Johns River
400               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

were sprayed by airplane, with very satisfactory results. At the
close of the fiscal year, the St. Johns River and tributary streams,
Okeechobee Waterway, and Hillsboro and Withlacoochee (except
for one small jam above Weeds Landing bridge) Rivers were open
and in goo.d condition.
    Total cost under existing project to June 30, 1954, have been
$1,421,884 for maintenance.
                                          Cost and financial summary

                                                  Fiscal year ending June 30                   Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                                   1950        1951        1952         1953      1954          prior to 1950
Maintenance:
   Appropriated--------........   $102, 500    $57, 800    $75, 000    $53, 705   $65, 580          $1, 422, 791
   Cost----------------            107, 889     63, 728     76, 568     52, 239    164, 447          1, 421, 544

   1 Differs from "Operation and Results during fiscal year" by $+340.
                RIVERS AND HARBORS-JACKSONVILLE,                                                          FLA., DISTRICT                                    401
                              15.      INACTIVE                  NAVIGATION                          PROJECTS

                                                                         For last              Cost to June 30, 1954                             Estimated
                                                                        full report                                                                amount
                       Name of project                                      see                                                                    required
                                                                         annual              Con-                     Operation                        to
                                                                          report           struction                    and                        complete
                                                                           for-                                      maintenance                 (1954 prices)
                                                                                                $178.42
                                 - - -- - -        -------- - --
1. Anclote River, Fla.!. .                    .                               1950             $178, 427                        $88, 957               $68, 000
2. Arecibo Harbor P.R-------.........-----------                              1953        26 1, 128, 075                       S107, 771
3. Atlantic-Gulf Ship Canal, Fla.-------........                              1939           5, 099, 153
4. Cedar Keys Harbor, Fla.-...................                                1932              147, 021                             30, 000          (4)3, 500
5. Christiansted Harbor V I.'z............                                    1950                                                                     366, 000
6. Courtenay Channel,       Fla.       (7)  and       (8).._.
                          7 . .. .. .. .. .. .. .. .. ..                       1940                   22, 846                                          (4)
7. Crystal River, Fla. _.. 7                                                  1941                   25, 000                         19, 993          (4)
8. Eau Gallie Harbor, Fla. 8s .-.----........                                 1940                    9, 627       ..............
                                                                                                                                                       (4)
9. Fajardo Harbor, P. R.-----......------------                               1945                                                                    S420, 000
10. Guayanes Harbor, P.R.
                                  10o- ,- - - - -             - - -
                                                         .........             1945                                 .......... -
                                                                                                        ,999..............                           11161, 000
11. Homosassa River Fla.7.....................                                 1937                                             - -   - -697           (4)
12. Horseshoe Cove, Fla....
                          1                             __._ --
                                    -- -- -- -- -- -- -- --                    1950   ...........-..-               ----.........--                     244, 000
13. Hudson River Fla. .                                                        1950   ..............-                ..............-                    394,000
14. Intracoastal Waterway, Cross-Florida Barge
      Canal--.........--------------------------                               1951           1, 465, 081 ..............                           100, 535, 000
15. Intracoastal
            1    Waterway, Miami to Key West,
      Fla.                       7 - -- --- -- -- -- -- -                      1953              203, 368                            325             2, 860, 000
16. Key West Harbor, Fla.7 .....    -                                          1950           1, 040, 409                     238, 743               2, 047, 000
17. Kis s imm ee Riv er, Fl a . __ . ._. .. . . . . . . . .7. . .              1931               23, 479                       25, 202                (4)
18. Lake Crescent and Dunns Creek, Fla. to0....                                1931               10, 276                         8, 166                146, 000
19. Little M anatee River,. . Fla.'.................
                                 .         . .. .. .. .. .. .. ..              1949   .........---
                                                                                                 -                   .............-----                 158, 000
20. Manatee River, Fla.                . .                                     1938                  123, 350                 101, 214                   15, 000
21. Mayaguez Harbor, P.R......................
                                   7                                           1953                  168, 187                 138, 118
                                                                                                                                                       (4)
22. Melbourne Harbor, Fla. _..                                    7            1939                   17, 696
23. Naples to Big Marco .Pass                               . . . .....
                                          . . . . . . . . . Fla.
                               . . . . .Channel,                     . .       1950                   37, 525                         47, 329
24. New River,-  Fla.'.....
                         7 -- -- -- --- -- --- -- --                           1950                                                                         98,000
25. Orange River, Fla. .........................
                                               . .. .. .. .. ...               1937                    2, 000                          8, 574          (4)
26. Ozona Channel, Fla.----------                                ----         1950                                  ..............                          91, 000
27. Palm Beach, Fla., beach erosion control'.....                             1950                                  ..............                    (1s) 8, 000
                                                                    1                                                                              (1) 140, 000
28. Palm Beach, Fla., side channel and basin __                                1946
                                                                                                                               S5804, 055
29. Palm Beach Harbor, Fla ...................
                                         1 .. . . . . . . . . . . . .          1953           1, 688, 741                                             (4)
30. Pithlaehascotee River, 1    Fla.             __
                                   . .. .. .. .. .. .. .. .. .                 1950                                                                     162,000
31. Ponce Harbor, P.R. ..                1                                     1949           16176, 294                              57, 946        1,254,000
32. St. Augustine Harbor, Fla.                                  ....-------------
                                                                               1951           17464, 091                             159, 582        2, 582, 000
33. St. Johns River, Fla. Jacksonville to Lake
      Harney.              7
                                                                               1953        1, 171, 243      18459, 525             153, 000
34. St. Lucie Inlet, Fla. ...... __ _ _ _ _ _ _                               1949            123,602
35. St. Petersburg Harbor, Fla._               ...............                1950                           1969, 697
                                                                                              221, 578 ------------------------    271, 000
                                    1                                                                          97---------
36. St. Thomas Harbor, V.I. .___...............                               1949                                              3, 440, 000
37. San Juan Harbor, P.R....-----------------                                 1953       204, 330, 671   21 1,208, 081              64, 000
38. Snagging and clearing under authority of
      Section 3 of the River and Harbor Act of
      March 2, 1945.                                                          1953                    39, 288                22 197, 234        .--....--.....
                                    7                                          1940                  135, 053                             514
39. Steinhatchee River, Fla. 2            .................                                                                                            (4)
40. Suwannee River, Fla. _...._.._.._.......                                  1940                    76, 418                         37, 394           201, 000

   1 No funds available.
   2 In addition $288,000 were expended from contributed funds.
   3 Expended for general supervision during fiscal year $309.
   4 Completed.
   b Not formally adopted by Congress.     Modified plan is recommended in H.D. 194, 75th Cong., 1st sess.
   6 Emergency relief funds.
    7 Channels adequate for commerce.
    s No commerce reported.
   9 In addition $30,000 to be contributed by local interests.
  10Awaiting local cooperation.
  11In addition $40,000 to be contributed by local interests.
  12In addition $1,000 were expended from contributed funds.
   13The estimate of $8,000 represents the extent to which the Federal Government is authorized to partici-
pate and is one-third the cost chargeable to publicly owned shore frontage. The estimated cost to local
interests is $242,500.
  14Authorizing Act limits Federal participation to $140,000. In addition, $280,000 to be contributed by
local interests.
  15Expended for general supervision during the fiscal year $1,772.
  16In addition $21,960 were expended from contributed funds.
  17In addition $137,500 were expended from contributed funds.
  18Expended for general supervision during the fiscal year $1,464.
  19In addition $6,353 were expended from contributed funds.
  20In addition $100,000 were expended from contributed funds.
  21Expended for general supervision during fiscal year $4,166.
  22In addition $1,672 were expended from contributed funds. $269.02 contributed funds, surplus to needs
of the project, were returned to local interests during the fiscal year.
  23Curtailment of existing project recommended in H.D. 467, 69th Cong., 1st sess.
402      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

             16. CENTRAL AND SOUTHERN FLORIDA
   Location. The project area includes Lake Okeechobee, its regu-
latory outlets, and a large portion of the Everglades and east coast
areas to the south, all near the southern end of the Florida Penin-
sula. (See U. S. Coast and Geodetic Survey Charts. Nos. 473,
1247, 1248, and 1289 and "Florida Everglades Drainage District,"
Soil Conservation Service maps Nos. 1524 to 1561, July 1946.)
   Lake Okeechobee and its regulatory outlets lie in Palm Beach,
Martin, Okeechobee, Glades, Hendry, and Lee Counties. St Lucie
Canal flows from the lake to the Atlantic Ocean; the Caloosahatchee
River, from the lake to the Gulf of Mexico.
   The lower east coast region embraces the populous urban and
agricultural areas in Dade, Broward, and Palm Beach Counties.
The region lies along the coast from the St. Lucie Canal south to
near the tip of the State, and extends 9 to 20 miles inland.
   The conservation areas lie in Dade, Broward, and Palm Beach
Counties west of the lower east coast region, and include 1,344
square miles of the Everglades suitable only for water and wild-
life conservation.
   Lake Okeechobee agricultural area lies south of the lake, mostly
in western Palm Beach County, but including part of Hendry
County. The area embraces 1,130 square miles of muck and peat
land which is suited for long-term agricultural use.
   Previous projects. Previous projects consist of completed
works for control of Lake Okeechobee included in and constructed
under the navigation project for Okeechobee'Waterway, Fla. (for-
merly Caloosahatchee River and Lake Okeechobee drainage areas,
Florida), under provisions of River and Harbor Acts, approved
July 3, 1930, and August 30, 1935. For further information, see
pages 877-882, Annual Report for 1948, and page 785, Annual
Report for 1949.
   Existing project. This provides for modification and expansion
of the previous project to include the first phase of the compre-
hensive plan for flood control and other purposes in central and
southern Florida. The first phase of the plan provides for the fol-
lowing :
   a. Everglades-lower east coast area: (1) An east-coast pro-
tective levee from the Homestead area north to West Palm Beach
Canal; (2) improvements for partial completion of conservation
areas for water impoundment and flood discharge in the Ever-
glades area west of the east-coast protective levee, including levees
within the conservation area separating it into three parts, with
gated spillways for discharge of water from one part to the next
and, finally, through Tamiami Trail to the undeveloped area to the
south, and a bridge culvert where Tamiami Trail intersects the
proposed canal and levee on the west side of the conservation area;
 (3) local protection works in the area along the east coast from
northern Palm Beach County to southern Dade County, including
pump stations and complete protective works in the Davie agri-
cultural area, canal improvements and enlargements, new canals,
spillway headworks at the edge of the conservation area, bridge
crossings and outlet barriers.
         FLOOD CONTROL-JACKSONVILLE, FLA., DISTRICT             403
   b. Okeechobee-Everglades area: (1) A levee and canal encircl-
ing the developed portion of the Lake Okeechobee agricultural area
from Caloosahatchee River via Bolles Canal to Miami Canal, thence
south on Miami Canal about 9 miles, thence eastward to Hillsboro
Canal, thence southeastward to the limit of the agricultural area,
thence northward crossing West Palm Beach Canal and continuing
to St. Lucie Canal; (2) enlargement of Miami, North New River,
Hillsboro, and West Palm Beach Canals, within the protected area;
 (3) five feeder canals within the protected area; (4) three pump-
ing stations at Lake Okeechobee and pumping stations at the
eastern edge of the protected area on West Palm Beach and Hills-
boro Canals; (5) a spillway at the eastern edge of the agricultural
area on the new canal crossing West Palm Beach Canal, and cul-
verts in West Palm Beach Canal on both sides of the new canal;
 (6) improving control of Lake Okeechobee by enlarging St. Lucie
Canal, including modification of spillways and structures; (7) a
spillway at Moore Haven, with an outlet canal to Caloosahatchee
River; (8) enlargement of existing Lake Okeechobee levees, in-
cluding paving and revetment, and construction of levees on north-
east and northwest shores of Lake Okeechobee; (9) initiation of
construction and operation of a system of meteorological and hy-
drological stations; and (10) under maintenance, the operation
and care of the spillway to be constructed at Moore Haven and the
main spillways of the conservation area.
   Upon completion, local interests are to assume maintenance and
operation of all works in a and b above, except the gated spillways
referred to in a and features (6) through (10) in b, which works
will be operated and maintained by the United States. In ad-
dition, the project includes maintenance (since July 1, 1950) of
control works completed with river and harbor funds under the
previous navigation project for Okeechobee Waterway, Fla. (for-
merly Caloosahatchee River and Lake Okeechobee drainage areas,
Florida) as follows: (1) A levee about 67.8 miles long from Fish-
eating Creek to St. Lucie Canal, following in general the south
shore of the lake, and a northshore levee 15.74 miles long (those
levees are to be improved and enlarged under the existing project) ;
 (2) four auxiliary floodway channels extending into Lake Okee-
chobee at or near Liberty Point, mouth of Fisheating Creek, mouth
of Kissimmee River, and mouth of Taylor Creek; (3) collection
and evaluation of meteorological data; and (4) operation and care
of spillways at the St. Lucie and Ortona locks, 5 hurricane gates
on Lake Okeechobee, 16 drainage culverts through the west-,
south-, and east-shore levees and 4 on the north shore of Lake
Okeechobee, 16 drainage spillways along the St. Lucie Canal, and
an intercommunicating radiotelephone network of 8 stations.
   The following table shows the principal features of the hurricane
gates constructed under previous projects for the Okeechobee
Waterway, Fla., and maintained under the existing project since
July 1, 1950:
404            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


                                        Nearest   town
                                                                    Depth
                                                                    Depth town
                                                                    Nearest  Character            Year    A
     Hurricane gate No.'                                             over       of                com-     ctual
                                       Name              Distance           foundation           pleted    cost
                                                          (miles)

2------------------------         Clewiston, Fla....         0              10 Pile-------1935            $309, 748
3------------------------         Lake Harbor, Fla_          0.5            10 Rock-_...1935               316, 938
4....               ..-----------------------
                                  Belle Glade, Fla.          4.0            10 ... do-..... 1935           350, 025
5-----------------------
6-----------------------
                                  Canal Point, Fla_.
                                  Okeechobee, Fla.-
                                                             0
                                                             6.0
                                                                            10 _do
                                                                             7 Pile-   --   1935
                                                                                            1936
                                                                                                           262,465
                                                                                                           373, 273

  1 All are 50 feet wide, with available length unlimited. They are constructed of concrete with steel
sector gates, and have no lift. Hurricane gate No. 6 has an auxiliary culvert spillway with automatic
control.

   Lake Okeechobee is maintained, so far as possible, between
elevations 13 and 15 feet, mean sea level.
   The estimate of cost for new work, approved in 1954 is $98,-
645,600 United States funds and $15,738,000 contributed funds,
exclusive of river and harbor funds expended on previous projects.
In addition, the estimated cost to local interests of lands, rights-
of-way, and relocation is $9,417,700 (1954). The latest (1954)
approved estimate for annual cost of maintenance is $355,200, in-
cluding $66,900 for operation and care of protective works.
  The existing project was authorized by the following Flood
Control Acts:

    Acts                          Work authorized                                        Documents
June 30,1948   The first phase of the comprehensive plan for flood           H. Doc. 643, 80th Cong., 2d sess.
                control and other purposes, and authorized to be               (Containslatestpublishedmaps.)
                appropriated $16,300,000 for partial accomplishment
                of the first phase.
May 17,1950    Authorized to be appropriated an additional $20               Specified in act.
                million for continuation of the first phase.


    Local cooperation. The Flood Control Act approved June 30,
1948 (H. Doc. 643, 80th Cong., 2d sess.), imposed the conditions
that local interests shall provide all lands, easements, and rights-of-
way; make a cash contribution of 15 percent of the estimated con-
struction cost for each part of the work prior to its initiation (with
the provision that the total cash contribution for the entire com-
prehensive plan shall not exceed $29,152,000); and furnish as-
surances satisfactory to the Secretary of the Army that they will
hold and save the United States free from damages due to the con-
struction and operation of the works and that they will maintain
and operate all the works after completion in accordance with
regulations prescribed by the Secretary of the Army, except the
levees, channels, locks, and control works of the St. Lucie Canal,
Lake Okeechobee, and Caloosahatchee River, and the main spill-
ways of the conservation areas.
    In May 1949, the Florida State legislature passed legislation pro-
viding for creation of districts for flood control, reclamation, con-
servation, and allied purposes to cooperate with the United States
on Federal projects; for creation of the Central and Southern
Florida Flood Control District, and for consolidation of the
former Everglades Drainage District with that district; and for
other measures necessary for full compliance with all requirements
          FLOOD CONTROL--JACKSONVILLE, FLA., DISTRICT                            405
of local cooperation. A resolution adopted August 1, 1949, by
the Central and Southern Florida Flood Control District, assuming
full responsibility for compliance with the requirements of local
cooperation as set forth in the project document, was accepted by
the Chief of Engineers on November 25, 1949, as satisfactory as-
surance of compliance. The Flood Control District has furnished
right-of-way and other interests in land, and has contributed the
required 15 percent of the estimated construction cost for each
feature of the project, when and as requested by the district en-
gineer. In response to a request of local interests on June 10, 1950,
urging construction of the eastern boundary levees of the con-
servation area to an intermediate grade, the Chief of Engineers
outlined a general policy permitting such construction, provided
that local interests agree to maintain the levees at those heights
pending completion to full grade. The Central and Southern
Florida Flood Control District has agreed to assume full respon-
sibility for maintenance of the levees so constructed.
    The Flood Control District has accepted responsibility for opera-
tion and maintenance of features as they are completed and for-
mally transferred to them (See par. "Condition at end of fiscal
year" for features and transfer dates). Those features are peri-
odically inspected by the District Engineers' Staff and the Flood
Control District advised of maintenance needed.
    The Flood Control District has been authorized, and has obtained
Congressional approval to advance $2,900,000 to accelerate the
construction program beginning in the fiscal year 1955, and to re-
ceive credit for that amount on the total cash contribution required
of $29,152,000. In addition to the local cooperation requirements
for the authorized first phase, local interests propose additional
and related works in the form of a secondary system of channels
to further serve the land developer, who in turn will construct the
necessary laterals, field ditches, farm levees and pump units, all
of which will permit maximum benefits from the major flood con-
trol works as provided by the project. The Flood Control District
is now engaged in preliminary planning of the secondary system
of channels, and for the Everglades Agricultural Area estimates
the cost as follows:
   Secondary channel system_ ............................                  $6, 000,000
   Land development water control system (laterals, field ditches, etc.)   35, 700, 000

The Flood Control District proposes to provide the necessary
rights-of-way for the Secondary Channel system. The land de-
veloper, either an organized subdrainage district or individual
landowner, will bear the cost of construction of the secondary
channels and all cost for development of the farm protective works.
   Local interests are also performing work in the unauthorized
portion of the project which is not required by the authorizing
act. In 1950 the Flood Control District adopted a program of
emergency construction of new works or improvements of existing
works necessary to prevent flood damages in areas where the con-
struction of the works of the flood control program would be years
in being realized. This program is estimated by the Flood Con-
trol District to cost $2,000,000, of which $541,821 has been spent.
406             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Operations and results during fiscal year. The work accom-
plished during the fiscal year is tabulated below:

                         Work and locality                                               Period                      Cost

New work:
   Contract:
      Channels and canals:
          Construction of C-9, Sec. 3, 6.5 miles long (in                   July 1 to Sept. 2, 1953.             $    19,370
             progress and 96 percent completed at beginning
             of fiscal year).
          Construction of C-9, (continuing contract) Sec. 2,                July 1, 1953 to April 15,                436,565
             4.4 miles long (in progress and 20 percent com-                   1954.
             pleted at beginning of fiscal year).
          Construction of west 3.7 miles of C-11 (in progress               July 1 to Dec. 4, 1953.                   72, 641
             and 63 percent completed at beginning of fiscal
             year.
          Construction of C-12, 3.3 miles long and C-13, Sec.               July 16, 1953 to Feb. 26,                157, 727
             1, 7.6 miles long.                                               1954.
          Construction of C-13, Sec. 2, 2.7 miles long-.........            March 23, to June 15, 1954.               88, 706
      Levees:
          Construction of L-1, Sec. 1, east 10 miles to grade               July 1, 1953 to Feb. 1,                  276,827
             at elevation 27.75 ft., (in progress and 43 percent              1954.
             completed at beginning of fiscal year).
          Construction of L-7, about 16.8 miles long to inter-              July 1, 1953 to June 30, 1954            768,858
             mediate height, the south 8.8 miles at elevation                 (35 percent completed).
             20 feet thence sloping up to elevation 24 feet
             (continuing contract) (in progress and 3 percent
             completed at beginning of fiscal year).
          L-8 turfing...........--...........------.........--------        Oct. 21, 1953 to Jan. 30, 1954.           77, 972
          Construction of L-15 Sec. 2, 1st Stage, 8 miles long.             Jan. 28 to June 30, 1954 (23             202,313
             (continuing contract).                                           percent completed).
      Pumping plants and drainage facilities:
          Construction of pump station 5-A auxiliary struc-                 July 1, 1953 to January 23,              160,946
             tures S-5A E, W, and S (in progress and 65 per-                  1954.
             cent completed at beginning of fiscal year).
          Fabrication of machinery for pump station 5-A, 6                  July 1, 1953 to June 30, 1954        1,001,073
             units at 4,610 c.f.s. (in progress at beginning of               (Units 1, 2, and 3-99%,
             fiscal year).                                                    Units 4, 5, and 6--96%).
          Construction of structure for pump station 5-A                    July 1, 1953 to June 30, 1954            790,924
             (continuing contract) (in progress and 10 percent                (65 percent completed).
             completed at beginning of fiscal year).
          Construction of 5-11, 1st stage (in progress and 56               July 1, 1953 to March 12,                260,100
             percent completed at beginning of fiscal year).                  1954.
          Construction of S-29 (in progress and 83 percent                  July 1 to Nov. 30, 1953.                  66, 621
             completed at beginning of fiscal year).
          Fabrication of machinery for pump station 2                           May 22, to June 30, 1954              10,827
             (continuing contract).                                                (1 percent completed).
          Construction of structure for pump station 9                          Nov. 25, 1953 to June 30,            145,748
             (continuing contract).                                                1954 (8 percent completed).
          Fabrication of machinery for pump station 9                           June 25, 1953 to June 30,            381,130
             (continuing contract).                                                1954 (67 percent com-
                                                                                   pleted).
            Construction of pump station 13, including ma- June 29, 1953 to June 30,                                 269,519
              chinery.                                                             1954 (86 percent com-
                                                                                   pleted).
            Construction of S-33 and 36- ..........----............------------ __ July 20, 1953 to June 30,         132,664
                                                                                   1954 (85 percent com-
                                                                                   pleted).
            Construction of B-8 railroad bridge................. Construction not yet started                          1,374
            Minor costs incurred this fiscal year on work com- -............................                             616
              pleted in prior fiscal year.
    Hired labor:
       Repairs to levee 8 spillways-....---------------------.. March 10 to April 20, 1954.                            5, 040
       Engineering and design----- ._.     -------------------. Fiscal year_--                                       734,224
           Total new work...................-------------------               --------------- ---.....           6,061,785
                 FLOOD CONTROL-JACKSONVILLE, FLA., DISTRICT                                                  407

                         Work and locality                                        Period                   Cost

Maintenance:
    Contract:
        Clearing vegetation and debris from land side toe           June 21, to June 30, 1954                 1,291
          ditch, Lake Okeechobee levee.                               (7% completed).
        Repair crown road and slopes on levee between St.           Fiscal year.----------------...               617
          Lucie Lock and Arundel Shops.
    Hired labor:
        Inspection, patrol, and maintenance of Lake Okeecho-        Fiscal year_                             35, 244
          bee levee slopes ramps, crown roads, protective
          planting, and cattle fences.
        Collection and compilation of meteorological data,          Fiscal year                _             19,831
          stream gaging and maintenance and operation of
          meteorological stations.
        Periodic and miscellaneous surveys and inspections,         Fiscal year_                              9, 616
          supervision, administration, and other routine work.
        Cleanout of landside toe ditch Lake Okeechobee Levee        Fiscal year                _                   57
          between Culvert 11 and Canal Point, Fla.
        Clear silt, hyacinth, etc., from landside approach          Fiscal year_                              2, 671
          channels to culverts in Lake Okeechobee levees.
        Remove material from approach channels to Hurricane         Fiscal year            _                      894
          Gate Structures No. 3, No. 4, No. 5, and No. 6.
       Periodic inspection of features and structures trans-        Fiscal year                               1, 022
         ferred to local interests.
         Total maintenance---------...        ...----------....------------------------------         J      71,243



   Operating and care. The spillways at Ortona and St. Lucie
Locks, 5 hurricane gates on Lake Okeechobee, 16 drainage culverts
through the West-, South,- and east-shore levees and 4 on the
north shore of Lake Okeechobee, 16 drainage spillways along St.
Lucie Canal, and an intercommunicating radiotelephone network
of 8 stations were operated and maintained by hired labor. Hur-
ricane Gate No. 3 was dewatered and cleaned out by hired labor.
Sandblasting and painting metal surfaces by contract was started
May 31, 1954, and was 95 percent complete at the end of fiscal year.
Construction of rubble mound groin at existing Culvert No. 11 in
Lake Okeechobee levee was under contract but not started. The
cost for the fiscal year was $40,074.
   The total costs for the fiscal year were as follows:

                                                                         Costs
                 Funds
                                             New work       Maintenance           Operation           Total


United States_                                $5, 281, 047          $71, 243         $40, 074         $5, 392, 364
Contributed                                       780, 738 -------------------------------                780, 738

     Total__--------------------------         6,061,785            71,243             40, 074            6,173, 102



  Regulation. Lake Okeechobee was regulated during FY 1954
between elevations 13.3 and 17.6 feet, mean sea level datum, in
accordance with approved regulation schedules. Serious flooding
occurred in central and southern Florida during the fall of 1953.
Stages exceeded the maximum of record in the upper Kissimmee
and St. Johns River basins. Lake Okeechobee rose to 17.6 feet,
cresting on October 28-29, and water levels in the Everglades
were the highest since the flood of 1948. Lakes Kissimmee and
Tohopekaliga were a few tenths above the 1947 level, and at the
highest stages reached since gaging stations were established.
408      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

The flood was unusual in that it was caused by the accumulation
of rain from almost daily showers, and not by a hurricane or
single storm. During the period, June through October 1953, the
recorded rainfall in the area varied from 38 to 72 inches. Lake
Okeechobee inflow was the maximum of record for periods of 2 to
5 months. The one-month value was exceeded only by June 1930.
Very extensive flooding occurred and the President designated
central and southern Florida as a disaster area. The protective
works around Lake Okeechobee prevented overflow which would
have completely flooded large areas south and east of the lake
under natural conditions. Lake storage supplied adequate water
for agricultural needs during the dry season. The minimum ele-
vation during the year, 13.3 feet, occurred on July 1, 1953, and on
June 17, 1954. Average rainfall over Lake Okeechobee for the
fiscal year 1954 was 64.7 inches with the greatest monthly rain-
fall 10.68 inches, occurring in June. Average observed pan evapor-
ation around the lake was 61.2 inches. Inflow from the tributary
areas varied from about 1,400 cubic feet a second on May 26, 1954,
to 36,700 cubic feet a second on October 11, 1953, and totaled about
5,483,000 acre-feet for the year. The heavy inflow associated with
rainfalls during the periods July through October 1953, and April
through June 1954, made regulatory discharge from the lake
necessary. Regulatory discharges averaged about 7,800 cubic
feet a second through St. Lucie Canal from August 4, 1953, to
January 15, 1954, and 3,700 cubic feet a second from May 12 to
June 30, 1954; and 3,720 cubic feet a second through the Caloosa-
hatchee River from August 3, 1953, to June 30, 1954, except for
short periods when releases from the lake were shut off because
of local runoff from Caloosahatchee River basin. Releases after
January 15, 1954, were made to lower the lake prior to hurricane
season. Discharge through the Miami, North New River, Hills-
boro, and West Palm Beach Canals, and various pump units, for
agricultural uses and other purposes varied from zero to about
1,900 cubic feet a second.
   Condition at end of fiscal year. The project was about 17 per-
cent completed.
   The following features were constructed under previous projects
for the Okeechobee Waterway, Fla., and are maintained under
this project: A levee 67.8 miles long from Fisheating Creek to
St. Lucie Canal, following in general the south shore of the lake,
January 1932 to March 1936; a north-shore levee 15.74 miles long,
July 1936 to February 1938; the spillway at Ortona lock, Novem-
ber 1934 to August 1937; 4 auxiliary floodway channels extending
into Lake Okeechobee or at near Liberty Point, mouth of Fish-
eating Creek, mouth of Kissimmee River, and mouth of Taylor
Creek, June 1932 to February 1938; 5 hurricane gates through the
levees at entrance to canals at Clewiston, Lake Harbor, South Bay,
Canal Point, and Taylor Creek, November 1933 to December 1936;
16 drainage culverts through the west-, south-, and east-shore
levees, and 4 similar culverts through the north-shore levee, De-
cember 1933 to December 1936; and 16 drainage spillways at
drainage openings along the banks of the St. Lucie Canal, No-
vember 1934 to September 1935.
                          FLOOD CONTROL-JACKSONVILLE, FLA., DISTRICT                                                                         409
  Planning for the existing project was begun in November 1948
and has been continued. Construction under the existing project
has been accomplished as follows:
                                                                                   Grade (ele-                             Date transferred to
                          Feature                                     Length      vation) mean          Construction      flood control district
                                                                      (miles)        sea level            period            for operation and
                                                                                                                               maintenance


Channel and canals:
   C-9 (Sec. 2)     ----------------                                      4.4                          April 1953 to     May 7, 1954.
                                                                                                         April 1954.
    C-9 (Sec. 3)----------------                                          6.5                          July 1952 to      November 13, 1953.
                                                                                                         Sept. 1953.
    C-11.           --------------------                                  3.7                          Feb. to Dec.      January 15, 1954.
                                                                                                         1953.
    C-12 and 13 (Sec. 1)------------                                     10.9                          July 1953 to      April 15, 1954.
                                                                                                         Feb. 1954.
   C-13 (Sec. 2) -..---------------                                       2.7   ------   -----   ---   March to June     Scheduled for August
                                                                                                         1954.             1, 1954.
    C-42.- - - - - - - -                                         -        5.4                          June to Au-       January 1, 1952.
                                                                                                         gust 1950.
Levees:
   L-1 (Sec. 1)-------------------                                       10     I----------------      Jan. 1953 to      April 15, 1954.
                                                                                                         Feb. 1954.
   L-e:
          North (including tie back
           levee_.._------------                                         23.8          19 and 24       April 1951 to     November 13,         1953,
                                                                                                        October 1952.     May 7, 1954.
          South (including tie back
            levee)--                                                      5.4                    24
                                                                                                  July 1950 to           July 14, 1952.
                                                                                                    May 1951.
   L-30------------------------                                          13.9                 *18 May 1951 to            September 15, 1952.
                                                                                                    July 1952.
   L-31 (North part)---.-.---.                                           10.8      *17.4 to *14.0 March to Sep-          October 15, 1952.
                                                                                                    tember 1952.
   L-33 and 37__----------                                               14.8                 *18 March 1951 to          September 15, 1952.
                                                                                                    Feb. 1952.
   L-35 -_..-
           -- --- --
                   __--- - -                                     .-       4.8                 *20 March 1950 to          January 1, 1952.
                                                                                                    May 1951.
   L-35A _----                  _              _---------                 6.0                 *20 January to                 Do.
                                                                                                    July 1950.
   L-36_                   -
                      - --..--                     - ..- .---
                                                          -              11.4                 *20 March 1950 to              Do.
                                                                                                    May 1951.
   L-40:
       N orth ....                   -         .      -     -
                                                      .--- .---           2.6                *24       November          September 15, 1952.
                                                                                                        1950 to July
                                                                                                        1951.
          South.------------------                                       26.1                *24       May 1951 to       May 15, 1953.
                                                                                                        Dec. 1952.
   L-43:
       Initial........-------------                                       0.3              32.56       September to
                                                                                                         October 1950
          Reconstruction and exten-
           sion_ _     _     __-----------------                                           35-36       September to
                                                                                                         October 1952.
Pumping plants and drainage facili-
ties:
    Pump Station 5A auxiliary
       structures 5A-E, W&S....                                                                  July 1952 to            April 15, 1954.
                                                                                                   Jan. 1954.
          S-11------- -------------                                                              May 1952 to
                                                                                                   March 1954.
          S -24  --.-.- --.-...                           -.--.-                ---------------- March to Sep-           October 15, 1952.
          S-24A }                                                                                  tember 1952.
          8-29............
          S-29.....----     -   -   --   ---       -- -                         ---------------- Aug. 1952 to            December 11, 1953.
                                                                                                   Nov. 1953.
          S-32                                                                  ---------------- March 1951 to           September 15, 1952.
                                                                                                   Feb. 1952.
          S-32A_                                                                ---------------- May to July                 Do.
                                                                                                      1952.
          S-34 _-                                                               ----------------
                                                                                                 March 1951 to               Do.
                                                                                                   Feb. 1952.
          S-39_-..-                  ________---                                ---------------- August 1951                 Do.
                                                                                                   to Oct. 1952.
          S-76............._                         .........                  ---------------- April 1951 to           Nov. 13, 1953
                                                                                                   October 1952.

 *Intermediate height.
410                REPORT OF CHIEF OF ENGINEERS, U: S. ARMY, 1954

  The status of works under contract at the end of the fiscal year
was as follows.:

                             Feature                                         Construction                    Percent
                                                                               started                      completed

Railroad bridges:
    B-8--------------.......................------------------------                                   Not yet started.
Levees:
    L-7 (to intermediate height) -- ---------------------. January 1953 .........._                                        35
    L-15, Section 2 and culverts__----------------------- January 1954.........                                            23
Pumping plants and drainage facilities:
    Pump Sta. 2, machinery----              ------------------- May 1954---------------
    Pump Sta. 5A machinery:
        Units 1, 2, and 3_ ---------------------------               August 1952............                               99
        Units 4, 5, and 6---------------.....------------..          February 1953..........                               96
    Pump Sta. 5A, Str        ___.... ____.......__
                                                 .. ______________ March 1953.....__... .                                  65
    Pump Sta. 9, Str_..--------------                 -------------- November 1953.......                                   8
    Pump Sta. 9, Mach         ---------------------------            June 1953..............                               67
    Pump Sta. 13----     ---.-                                       ... do....---------------                             86
    S-33 and S-36---......-----------------------------..-. July 1953..............                                        85



  The work remaining to be done to complete the project is to
complete construction of features under contract and all remain-
ing works described in the paragraph "Existing Project."
  The total costs under the existing project to June 30, 1954, have
been as follows:

                                                                                        Costs

                         Funds
                                                             New work          Mainte-          Operation          Total
                                                                               nance             and care


United States_                                               $17, 686,288      $1,040,753          $153,964     $18,881,005
Contributed --                                                 2,415 231                                          2 415 231

      Total___                                                20,101,519        1,040,753           153,964      21,296,236




                                           Cost and financial summary
                                                United States Funds

                                                     Fiscal year ending June 30                              Total to June
                                                                                                            30, 1954, includ-
                                                                                                            ing fiscal years
                                    1950         1951            1952           1953            1954          prior to 19501

New work:
   Appropriated          .       $1, 500, 000 $6, 300, 000    $6, 000, 000   $4, 974, 000   ------------
                                                                                                      $18, 774, 000
    Cost_ _.   .     .               728,741   2,968,181       4, 864, 386    3,841,822     2$5, 289,512         17, 694, 753
Maintenance:
   Appropriated               _                  900,000         100,000         90,000         139,659            1, 229, 659
   Cost _..... . .            ____......         727,071         262,529         93,799       2 110, 891           1, 194, 290

   1 Exclusive of river and harbor funds expended on previous projects.
(See Cost and Financial Summary for the Okeechobee Waterway, Fla. project for those costs)
   2 Differs from "Operation and Results during fiscal year by $-8,465, new work and $-425, maintenance

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 ....                .
                                                                    .............. $13,522
    Appropriated for succeeding fiscal year ending June 30, 1955 ....---...-     4,250,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955 ...............--------------------------------------------- 4,263,522
    Estimated additional amount needed to be appropriated for com-
         pletion of existing project                                                75,621 ,600
                                                  ...............--..............................
                      FLOOD CONTROL--JACKSONVILLE, FLA., DISTRICT                                                                                                              411
                                                                            Contributed funds

                                                                                 Fiscal year ending June 30                                                           Total to June
                                                                                                                                                                     30, 1954, includ-
                                                                                                                                                                     ing fiscal years
                                                     1950                     1951                     1952                      1953                    1954          prior to 1950
New work:
   Appropriated--------                            $505, 740                $697, 325                $829, 650             $1, 424, 040                1'$452, 700        1$4, 029, 455
   Cost-----------------507,                                 850          -297, 384                    879, 422                  426, 716                780, 738          22,415, 231

Other new work data:
     Unobligated balance fiscal year ending June 30, 1954....-----------................. 3$1,421,265
     Contribution and advances for succeeding fiscal year ending June
         30, 1955---..--.....--..-------------------------..............................................................-------.....................                   43 ,470 ,500
     Unobligated balances available for succeeding fiscal year ending
       June 30, 1955....................................................................................---------------------------------------.4,891 ,765
     Estimated additional amount needed to be contributed for com-
       pletion of existing project------..                        --.........................---------.................      ----...........--8 ,346 ,200
  1 Includes     $2,094 returned to local interests, but not considered a reduction in allotment.
  2 Includes     $106,106 expended from contributed funds for work outside the scope of the authorized project.
  s Includes     $900,000 advanced funds (see par. "Local Cooperation").
  ! Includes     $2,000,000 funds to be advanced (see par. "Local Cooperation").


                                                17. GENERAL INVESTIGATIONS
  Examinations and surveys. Hired labor costs during the fiscal
year were $16,108. The balance unexpended and accounts receiv-
able at the end of the fiscal year, $86, together with $17,000 can
be profitably expended during the ensuing fiscal year.
  Collection and study of basic data. Hired labor costs on Storm
Studies feature were $969 during the fiscal year. The balance
unexpended and accounts receivable at the end of the fiscal year,
$31, will be expended on Storm Studies program during the en-
suing fiscal year.
                IMPROVEMENT OF RIVERS AND HARBORS
                    IN THE MOBILE, ALA., DISTRICT
  This district comprises a small portion of southeastern Ten-
nessee, western Georgia, western Florida, all of Alabama south of
the Tennessee River Basin, eastern Mississippi, and a small por-
tion of southeastern Louisiana embraced in the drainage basins
tributary to the Gulf of Mexico, west of the Aucilla River Basin,
to and including the Pearl River Basin. It includes the section of
the Gulf Intracoastal Waterway from St. Marks, Fla., to Lake
Borgne Light No. 41, Louisiana.
                                                          IMPROVEMENTS

                        Navigation                                                  Navigation-Continued
                                                             Page                                                                 Page
1. Gulf Intracoastal Waterway                                   9. Alabama-Coosa Rivers, Ala.
     between Apalachee                         Bay,                                     _
                                                                       and Ga ...............................                     432
     Fla        and the Mexican                               10. Howell Mill Shoals Dam, Ala-
     border (Mobile District).......                    413            bama-Coosa River, Ala. and
2. Apalachicola, Chattahoochee,                                        Ga    ..........------------............................   435
     and Flint Rivers, Ga. and                                11. Black Warrior, Warrior, and
     Fla ....--------------------------------------.............
                                                        417            Tombigbee Rivers, Ala-......,._.                           436
3. Buford Dam and Reservoir,                                   12. Biloxi Harbor, Miss ....................                       442
     Apalachicola, Chattahoochee,                              13. Gulfport Harbor, Miss..............                            444
     and Flint Rivers, Ga. and                                 14. Pearl River, Miss. and La ..........                           445
                                                        421 15. Inactive navigation projects......
     Fla .............................-------------------------------------............                                           448
4. Fort Gaines Lock and Dam,
     Apalachicola, Chattahoochee,                                                      Flood Control
     and Flint Rivers, Ga. and
     Fla ............................................   423 16. West Point, Chattahoochee
5. Jim Woodruff Lock and Dam,                                          River, Ga.............................. .                  448
     Apalachicola, Chattahoochee,                             17. Allatoona Reservoir, Coosa
     and Flint Rivers, Ga. and                                         River Basin, Ga......................                      449
         ....
     Fla ----------------------------------------       424 18. Rome, Coosa River, Ga _............                               451
6. East Pass Channel from the                                 19. Inactive flood control projects.                                452
     Gulf of Mexico into Choc-                                20. General Investigations ..............                           452
     tawhatchee Bay, Fla..............                  426 21. Inspection of completed flood
7. Mobile Harbor, Ala-..................                427            control works .........................                    452
8. Removing the water hyacinth,                               22. Flood control work under
     Mobile District ....................               431            special authorization .............                        453

1. GULF INTRACOASTAL WATERWAY BETWEEN APALACHEE
BAY, FLA., AND THE MEXICAN BORDER (MOBILE DISTRICT)
  Location. This section of the Gulf Intracoastal Waterway ex-
tends generally westward from Apalachee Bay through Ochlocko-
nee Bay, Ochlockonee, Crooked, and Carrabelle Rivers, and St.
George Sound to Apalachicola Bay; thence through Apalachicola
River, Jackson River, Lake Wimico, Searcy Creek, a land cut, and
Wetappo Creek to St. Andrew Bay, Fla.; thence through a land
cut to Choctawhatchee Bay, Fla.; thence through Santa Rosa
Sound to Pensacola Bay, Fla.; thence through Big Lagoon and
Old River, Fla., Perdido Bay, Fla. and Ala., Bay La Lanche, Wolfe
Bay, Portage Creek, Oyster Bay, and Bon Secour Bay, Ala., to
Mobile Bay, Ala.; thence through Mississippi Sound, Miss., and
Lake Borgne, La., to the Rigolets.
  Previous projects. Adopted by the River and Harbor Acts ap-
                                                                                                                       413
414                    REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

proved May 23, 1828, and July 25, 1912, for the section between
Mobile Bay and Mississippi Sound. For further details, see page
906, Annual Report for 1930.
   Existing project. This provides for a waterway 12 feet deep
and 125 feet wide at mean low water from Apalachee Bay, Fla., to
Mobile Bay, Ala., and 12 feet deep and 150 feet wide from Mobile
Bay, Ala., to the Rigolets, La. (Lake Borgne Light No. 41); for a
tributary channel (the Gulf County Canal), 9 feet deep, 100 feet
wide, and about 6 miles long connecting the Intracoastal Water-
way at White City, Fla., with St. Joseph Bay; and for the con-
struction of a movable span in the Georgia, Florida & Alabama
Railroad bridge crossing the Ochlockonee River near McIntyre,
Fla. Length of the waterway between the 12-foot depth con-
tours in Apalachee Bay and Lake Borgne Light No. 41 at the
Rigolets is 379 miles.
   The estimated cost of new work (1954) is $6,691,900, exclusive
of amounts expended on previous projects. The latest (1954) ap-
proved estimate for annual cost of maintenance is $345,000.
   The existing project was authorized by the following River and
Harbor Acts:
                   i




       Acts                             Work authorized                                       Documents
         -------   I                                                          I                          -   -----
                          APALACHICOLA BAY TO ST. MARKS RIVER, FLA.
                                                                                                                       t
Aug. 26, 1937          A channel 9 feet deep and 100 feet wide at mean low        H. Doe. 291, 75th Cong., 1st sess.
                         water from Apalachicola Bay, Fla., via St. George
                         Sound, Carrabelle, Crooked, and Ochlockonee
                         Rivers and Ochlockonee and Apalachee Bays to
                         St. Marks River, Fla.
                         APALACHICOLA RIVER TO ST. ANDREW BAY, FLA.

June 25, 1910          A channel 5 feet deep at mean low water and 65 feet        H. Doc. 670, 61st Cong., 2d sess.
                         wide at the bottom.
        (2)            A channel 9 feet deep at mean low water and 100            Rivers and Harbors Committee
                         wide at the bottom.                                        Doec. 52, 72d Cong., 2d sess.'

                            CHOCTAWHATCHEE BAY TO WEST BAY, FLA.
                                                                                                                       l
Aug. 30, 1935          A channel 9 feet deep at mean low water and 100 feet       H. Doe. 259, 72d Cong., 1st sess.
                         wide at the bottom.
June 25, 1910          A channel 6 feet deep at mean low water, with no           H. Doc. 565, 61st Cong., 2d sess.
                        reference to width.

                         CHOCTAWHATCHEE BAY TO PENSACOLA BAY, FLA.

Aug. 30, 1935          A channel 9 feet deep at mean low water and 100 feet       River and Harbors Committee
                        wide at the bottom.                                        Doc. 42, 73d Cong., 2d sess.'
                           PENSACOLA BAY, FLA. TO MOBILE BAY, ALA.

July    3, 1930        A channel 9 feet deep at mean low water and 100 feet       H. Doc. 42, 71st Cong., 1st sess.
                        wide at the bottom.
                            MOBILE BAY, ALA., TO NEW ORLEANS, LA.

July          A channel 300 feet wide and 10 feet deep from the 10-
         3, 1903                                                                  Rivers and Harbors Committee
               foot contour in Mobile Bay to the 10-foot contour                  Doc. 4, 71st Cong., 1st sess.'
                in Mississippi Sound.
    Do ...... A channel 100 feet wide and 9 feet deep from Lake                   H. Doc. 341, 71st Cong., 2d sess.
                Pontchartrain to Mississippi Sound.
                          APALACHEE BAY, FLA., TO NEW ORLEANS, LA.

July 23,1942           A channel 12 feet deep and_125 feet wide at mean low       Public Law 675, 77th Cong., and
                        water, except in the section between Mobile, Ala.,         H. Doc. 96, 79th Cong., 1st sess.
                         and New Orleans, La., where the width is to be
                         150 feet.
June 17, 1943          Conditional acquisition of Gulf Canal, Fla., and en-       H. Doc. 257, 76th Cong., 1st sess.,
                        largement of the canal to 9 feet deep and 100 feet         and Public Law 75, 78th Cong.,
                         wide.                                                      1stsess.
                 RIVERS AND HARBORS-MOBILE, ALA., DISTRICT                                          415

      Acts                          Work authorized                               Documents
Mar. 2,1945      Construction of a movable span in the Georgia,        H. Doe. 442, 76th Cong., 1st sess.
                  Florida & Alabama R.R. bridge crossing the
                   Ochlockonee River.
May 17, 1950     Abandonment and closure of original Channel be-       H. Doc. 325, 81st Cong., 1st sess.t
                  tween Big Lagoon and Pensacola Bay and con-
                   struction of a new channel to enter the bay north
                   of original entrance.

1   Contain the latest published maps.
2 ERA Act, May 28, 1935, and River and Harbor Act, Aug. 30, 1935.


   Local cooperation. The requirements of local cooperation for
this project have been fully compiled with except for the section
from Apalachee Bay to Carrabelle, Fla.
   The requirements of local cooperation for the section from
Apalachee Bay to Carrabelle, Fla., provide that local interests
undertake all necessary modifications of bridges over the water-
way, except the construction of a movable span in the Georgia,
Florida & Alabama Railroad bridge over the Ochlockonee River
near McIntyre, Fla., furnish, free of cost to the United States,
necessary rights-of-way and suitable spoil disposal areas for new
work and for subsequent maintenance as required, and release
the United States from all claims for damages incidental to the
work of improvement. Conditions of local cooperation required
by the 9- by 100-foot project authorized by the River and Harbor
Act of August 26, 1937, were fulfilled with exception of the pro-
vision concerning alteration of the Georgia, Florida & Alabama
Railroad bridge at McIntyre, Fla., which condition was removed
by authority of the River and Harbor Act of March 2, 1945. Local
interests were notified January 9, 1951, of the conditions of local
cooperation as altered by the authorization of a 12- by 125-foot
waterway in Public Law 675, 77th Congress (July 23, 1942), and
by revised regulations pertaining to bridge clearances across the
Gulf Intracoastal Waterway.
   Terminal facilities. Terminal facilities available for public
use are located at Carrabelle, Apalachicola, Panama City, and
Pensacola, Fla.; Mobile and Bayon La Batre, Ala.; Pascagoula,
Biloxi, Gulfport, Pass Christian, and Bay St. Louis, Miss. These
facilities are considered adequate for existing commerce.
   Operations and results during fiscal year. Repair and mainte-
nance work of the erosion-protective works on the Choctawhatchee
Bay-West Bay section of the waterway was performed by Govern-
ment plant and hired labor from July 1 to August 31, 1953, from
January 11 to 22, 1954, and from March 22 to April 15, 1954, at a
cost of $5,644.
   The U. S. pipeline dredge Josenhans removed 529,545 cubic
yards of material from the Apalachicola Bay section December
5, 1953 to January 30, 1954, at a cost of $52,179; 42,801 cubic
yards from the Apalachicola-St. Andrew Bay section March 9 to
March 18, 1954, at a cost of $10,067; and 68,147 cubic yards from
the Choctawhatchee Bay-West Bay section December 3 to 4,
1953, and March 22 to April 9, 1954, at a cost of $20,192. The U. S.
snagboat Albany removed 872 obstructions from the Apalachicola-
St. Andrew Bay section February 9 to March 4, 1954, at a cost of


          Sig 14---415-446
416                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

$10,497. The contractor's dredge Moreland removed 28,620 cubic
yards of material from the Pensacola Bay-Mobile Bay section
September 15 to 23, 1953, at a cost of $9,244. Miscellaneous
investigations and surveys of the entire waterway cost $21,561.
  The cost for the fiscal year was $129,384, charged to mainte-
nance.
  Condition at end of fiscal year. The existing project, com-
menced in 1911, was about 87 percent completed. The latest ex-
aminations show minimum depths, at mean low water, available
to navigation as follows:

                                                                                       Minimum depth


     Date                           Section                         Project          Left               Mid-          Right
                                                                    depth           outside          channel for     outside
                                                                     (feet)         quarter          half project    quarter
                                                                                     (feet)          width (feet)     (feet)
Jan. 1954- .....     Apalachicola Bay to Carrabelle, Fla.                 12              12. 0              12. 0          12. O0
Jan. 1954-.....      Apalachicola River to St. Andrew                     12               9.0                9.0            8. 5
                        Bay, Fla.
Jan. 1954 .....      Gulf County Canal, Fla........._...                   9               8. 2               8. 0           5. 1
May 1954.....        Choctawhatchee Bay to West Bay,                      12              10.0               12.0           10.0
                        Fla.
July 1952......      Choctawhatchee Bay to Pensacola                      12                 12. 0           12. 0          12.0
                       Bay, Fla.
Oct. 1953......      Pensacola Bay, Fla. to Mobile Bay,                   12                 11.0            11.0           11.0
                      Ala.
Sept. 1952.....      Mobile Bay, Ala. to the Rigolets, La.                12                 11.0            11. 5          11.0


   The work remaining to be done to complete the project consists
of dredging to project dimensions the section from Carrabelle,
Fla., to Apalachee Bay, Fla., via Carrabelle, Crooked, and Och-
lockonee Rivers, and Ochlockonee and Apalachee Bays, Fla.; and
dredging a channel to project dimensions from Big Lagoon to
Pensacola Bay along an alinement north of the present channel.
Due to abandonment of the Georgia, Florida & Alabama Railroad
under Interstate Commerce Commission permit, disposal of the
rail, and removal of the fixed bridge across the Ochlockonee River
at McIntyre, construction of a new bridge with a movable span at
that location, as authorized in the Act of March 2, 1945, is no
longer necessary.
   The cost for the existing project to June 30, 1954, were as
follows:

                                                                                                     Costs

                                                                         New work                Maintenance          Total


Regular funds________________                                                 $5, 494, 863            $3, 412, 101   $8, 906 964
Emergency Relief funds ____________________4340,                                       000                              340, 000
      Total-.........-----------              -------------------             5,834,863               3,412,101      9,246,964
                       RIVERS AND HARBORS-MOBILE, ALA., DISTRICT                                                       417
                                                   Cost and financial summary

                                                               Fiscal year ending June 30                    Total to June
                                                                                                             30, 1954, includ-
                                                                                                             ing fiscal years
                                           1950              1951         1952        1953        1954         prior to 19501
New work.:
   Appropriated...                             ------------------                                                 $5, 834, 863
   Cost...----------------------------------------------------------                                               5, 834, 863
Maintenance:
     Appropriated ....- . _               $198, 500        $117, 100    $127, 147     $98, 588   $138, 029         3, 421, 633
     Cost -----------------                157, 838         159, 021      92, 639     141, 648    129, 384         3, 412, 101

   1 Exclusive of $45,605 for new work and $65,137 for maintenance for previous projects.


Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project_ -...........-....--......... .. ...................... $857,000
      2. APALACHICOLA,                             CHATTAHOOCHEE, AND FLINT RIVERS,
                                                     GA. AND FLA.
   Location. The Apalachicola River is formed at the southwest
corner of the State of Georgia by the junction of the Chatta-
hoochee and Flint Rivers and flows south 108 miles, emptying into
Apalachicola Bay. The Florida River enters the Apalachicola
River from the east 45.4 miles above its mouth, and the River
Styx also enters from the east, 36.7 miles above its mouth. (See
U. S. Coast and Geodetic Survey Chart No. 1262).
   The Chattachoochee River, 418 miles long, rises in northeast
Georgia and flows southwesterly to West Point, and thence
southerly to join the Flint River at the southwest corner of
Georgia, forming the Apalachicola River. (See U. S. Geological
Survey maps for northwest Georgia).
   The Flint River, 330 miles long, rises in west-central Georgia,
flows generally southeasterly to Albany, and thence southwest to
the southwest corner of the State, where it joins the Chatta-
hoochee River to form the Apalachicola River. (See U. S. Geo-
logical Survey maps for southwest Georgia).
   Previous projects. Expenditures on the Apalachicola River
were made between 1828 and 1831, but apparently under no definite
project. In 1835 and 1836, appropriations were made for the
Chipola River. For further details, see page 690, Annual Report
for 1938. Projects for the Apalachicola River were adopted by
the River and Harbor Acts of June 23, 1874, June 13, 1902, Jan-
uary 6, 1934, and June 20, 1938. For further details, see the ex-
isting project for Apalachicola River, page 568, Annual Report
for 1944.
   Projects for the Flint River, Ga., were adopted by River and
Harbor Acts of June 23, 1874, and June 14, 1880. For further
details, see the existing project for Flint River, Ga., page 570,
Annual Report for 1944.
   The River and Harbor Act of July 13, 1892, made an appropri-
ation for the section of the Chattahoochee River between West
Point and Franklin, Ga., and appropriations therefor were con-
tinued until 1899, when they were discontinued. For further de-
tails, see page 1834, Annual Report for 1915, and page 696, Annual
Report for 1938. The River and Harbor Act of June 23, 1874,
adopted the project for the Chattahoochee River from its mouth
to Columbus, Ga. For further details, see existing project for
418      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

that river on page 572, Annual Report for 1944.
   For total cost and expenditures on all previous projects, see
cost and financial summary for the Apalachicola, Chattahoochee,
and Flint Rivers, Ga. and Fla., for the fiscal year 1945.
   Existing project. Prior to the River and Harbor Act approved
March 2, 1945, the existing project for the Apalachicola River
provided for a channel therein 6 feet deep at low water and 100
feet wide, to be secured by removing snags and overhanging trees
and by widening and straightening Moccasin Slough, for a channel
5 feet deep and 60 feet wide through the Cutoff, Lee Slough, and
lower Chipola River, together with snagging and dredging to a
depth of 6 feet the lower 2,500 feet of Styx River and improving
of Florida River by dredging a new outlet 6 feet deep, 80 feet
wide, and about 600 feet downstream of its present mouth; for the
Chattahoochee River, a channel 4 feet deep at low water and 100
feet wide from the mouth to Columbus, Ga., 164 miles, by re-
moving timber obstructions, dredging, contraction works, and
shore protection; and for the Flint River, a channel 100 feet wide
and 3 feet deep at extreme low water from the mouth to Albany,
103 miles, to be obtained by dredging, rock excavations, contrac-
tion works, and removal of snags, together with a channel for
light-draft steamers at moderate stages from Albany to Monte-
zuma, 79 miles, to be obtained by removing loose rocks, snags, and
overhanging trees.
   The River and Harbor Act of March 2, 1945, approved the
general plan presented in House Document No. 342, 76th Congress,
1st session, for the full development of the Apalachicola, Chatta-
hoochee, and Flint River system in the combined interest of navi-
gation and power, and authorized for the initiation and partial
accomplishment of that plan modification of the then existing
projects for the Apalachicola, Chattahoochee, and Flint Rivers to
provide for the construction of two of the locks and dams for a
9-foot project, one at Fort Benning and one at the junction, sup-
plemented by dredging and contraction works, to provide an
initial navigable depth of 6 feet to Columbus on the Chattahoochee
and to Bainbridge on the Flint at an estimated cost for new work
of $6,500,000, with annual maintenance of $200,000 in addition to
that previously authorized. The remaining elements of the ap-
proved plan included navigation-power dams with locks at the
Florence, Fort Gaines, Columbia, and Paramore Landing sites on
the Chattahoochee between the Junction and Fort Benning sites;
storage-power reservoirs on the upper Chattahoochee at the Ros-
well, Cedar Creek, and Lanier sites; storage-power reservoirs on
the upper Flint at the Woodbury No. 2, Potato Creek, and Au-
chumpkee Creek sites; dredging, cutoffs, contraction works, or
other open river methods, to provide, with the aforementioned
dams and flow regulation, channels 9 feet deep and 100 feet wide
from the mouth of the Apalachicola River to Columbus, 7 feet
deep and 100 feet wide in the Flint River from its mouth to Bain-
bridge, and 5 feet deep and 100 feet wide thence to Albany, at an
estimated construction cost to the United States of $66,629,000
for the full development.
    The River and Harbor Act of July 24, 1946, approved modifica-
                    RIVERS AND HARBORS-MOBILE, ALA., DISTRICT                                                                        419
tion of the general plan in accordance with House Document 300,
80th Congress, 1st session, to include improvements proposed by
the Chief of Engineers in lieu of the corresponding works of the
plan presented in House Document 342, 76th Congress, 1st session,
and authorized for the initiation and partial accomplishment of
the modified plan the construction of Buford multipurpose reser-
voir, Fort Benning lock and dam, and the Upper Columbia and
Jim Woodruff, formerly Junction, multiple purpose developments,
and supplemental channel work to provide a channel depth of 9
feet for a minimum width of 100 feet in the Apalachicola River,
to Columbus, Ga., on the Chattahoochee River, 268 miles, and to
Bainbridge, Ga., on the Flint River, 29 miles above its junction
with the Chattahoochee River. The Committee on Public Works
of the House of Representatives, by resolution adopted May 19,
1953, approved the plan as proposed by the Chief of Engineers for
a low dam at the Columbia site and a high dam at the Fort Gaines
site in lieu of a high dam at the Upper Columbia site and a low
dam at the Fort Benning site.
   The following table gives the various features of the proposed
locks and dams and multiple-purpose developments included in the
existing project:
                                                       Proposed structures

                                                        Jim Woodruff           Columbia              Fort Gaines              Buford
                                                        lock and dam         lock and dam           lock and dam               dam

Miles above mouth ..          __________------       ... 107.61--                          75.22-------........
                                                                             46.52---------..........                      348.52.
Nearest town---................-----------------..      Chattahoochee, Columbia,                    Fort Gaines,           Buford, Ga.
                                                           Fla.                Ala.                    Ga.
Distance (miles).......
                      ....--------------------
                                           1                                 3----------- 2----...-------......
                                                                                                      5.
Greatest lock length available for full                  450....----------   450.....---------      450-....
width (feet).
Width of chamber (feet)____-________                     82______            82...-----------.      82..
Lift(feet)---------------------------     33.0----------- 21.0 .....----------- 92.0.
Elevation of normal pool surface (msl)___ 77.0 ...........95.0 ._._._-- 190.0 .. _-.. 1070.0.
Depth over sills at low water (feet)      14. 0               --.
                                                         1 13.0      ...--------- 13.0_ ........
Character of foundation_                                 Limestone .-        Limestone....          Limestone .-           Rock.
Kind of dam__ ___________-- -----                       Fixed                Fixed- ......                     ..
                                                                                                    Fixed _____.           Fixed.
Height ofdam (feet).._________________                  67.-----------       58.......-----------   114.......----------   192.
Type of construction ----------------
                        _                                Concrete __         Concrete-......        Concrete,              Earth.
                                                                                                     earth.
Reservoir capacity (acre-feet)                          385, 000_       12,000-_ _-         924, 600.....                  2, 077, 000.
Power development (kilowatts) _____-_                   30,000 ._     __            ._____. 130,000--------                86,000.
Percent complete--------------
                  .                                     74---_------- ---------------- -------------.                      21.
Year opened to navigation                                                      -
Estimated cost:
    Construction _____________________                  $44, 444,900__....   $10, 640,600 .- $62, 457,000__..              $22, 763,100.
    Lands_________________                                2,468, 500__...         138, 400...__  6, 668,000....____          4,311,000.
    Relocations_                 .                           182, 600 --..                      17, 204,000__..             13,631, 900.

       Total_                                    .       47,096,000_          10,779,000 .-.         86,329,000 ....        40,706,000.

  1 Above mouth of Apalachicola River.
  2 Above mouth of Chattahoochee River.

   The estimated cost for new work, revised in 1954, is $185,890,-
000, exclusive of amounts expended on previous projects. The
latest (1954) approved estimated annual cost for maintenance is
$1,085,000 (includes $875,000 for operating and care).
   The mean range of tide at the mouth of the Apalachicola River
is 1.6 feet; at the point where the river is formed the variation
between low and high water is about 37 feet. On the Chatta-
hoochee River, the variation between average low and high water
is about 20 feet, and the extreme fluctuation is 65.3 feet at Eufaula.
420            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

On the Flint River, the extreme fluctuation of stage due to floods
was 40 feet, while the average variation between low and high
water is about 21.5 feet.
   Local cooperation. This provides that local interests agree to
furnish, free of cost to the United States, all lands, easements,
rights-of-way, and spoil disposal areas, as and when required, for
provision and maintenance of the channel in Apalachicola River
below Jim Woodruff Dam, to maintain and operate at their ex-
pense all utility and highway facilities which are relocated or
otherwise altered as a part of the improvement, to provide suit-
able public terminal facilities open to all on equal terms, and to
hold and save the United States free from damages which might
arise from the construction of the improvement.
   Terminal facilities. At Apalachicola, Fla., the facilities consist
of several marginal pile-and-timber wharves. The landing at
Blountstown, Fla., is a natural one. A private wharf at River
Junction, Fla., is used for landing and storing sand and gravel.
On the Flint River there is a natural landing at Bainbridge, Ga.,
and also at Albany, Ga. On the Chattahoochee River the terminals
consist of natural landings at Columbus, Ga., and Eufaula, Ala.,
and a masonry marginal landing at Columbus. These facilities
are considered adequate for the existing commerce.
   Operationsand results during fiscal year. The work performed
on the existing project consisted of continued construction on the
Buford and Jim Woodruff dams, and continued preliminary plan-
ning studies on the Fort Gaines dam. Information regarding
operations and costs applicable to the individual developments is
presented in the separate reports on the respective projects.
   The following table summarizes the costs for the fiscal year on
the overall project for the Apalachicola, Chattahoochee, and Flint
Rivers:

                                                                                  Costs

                          Structure                           Contract           Hired labor         Total


New work:
   Buford Dam ___ ___          __________-_______..
                                                . ...          $3, 041, 162          $260,100      $3,301,262
   Fort Gaines Lock and Dam ______________________....... ... .     _                 158, 855         158,855
  Jim Woodruff Lock and Dam                      -              6, 594, 314            60, 853      6, 655, 167

      T o tal __ ________________-
                               . .    . .   . .   .   ....       9 ,6 3 5,4 76        4 79 ,8 08   10 ,1 1 5 ,28 4



   Maintenance operations in connection with Jim Woodruff Lock
and Dam cost $1,170.
   The total cost on the existing project for the fiscal year was
$10,116,454, of which $10,115,284 was for new work and $1,170 for
maintenance.
   Condition at end of fiscal year. Information regarding condi-
tion at the end of the fiscal year of the individual developments
is presented in the separate reports on the respective projects.
   The controlling depths in the channel at the time shown were
as follows: Apalachicola River, 4.5 feet, June 1950; the Cutoff,
Lee Slough and Lower Chipola River, 5 feet, October 1943; mouth
                  RIVERS AND HARBORS-MOBILE, ALA., DISTRICT                                                        421
of Florida River and River Styx, 6 feet, October 1947; Chatta-
hooochee River, mouth to Columbus, 3 feet, June 1945; Flint River,
mouth to Bainbridge, 2.6 feet, and Bainbridge to Albany, 1.5 feet,
June 1941. Ordinarily, boats drawing 5 feet can operate through-
out the year on the Apalachicola River at a stage of zero on the
River Junction gage. Greater depths are usually available from
January to July of each year. On the Chattahoochee River, ves-
sels drawing less than 3 feet may operate throughout the year,
and 5 feet can ordinarily be carried from December to June. The
head of boat traffic on that river is Columbus, Ga. On the Flint
River, greater depths than those shown are generally available
between November and June of each year. The head of naviga-
tion for boat traffic on that river is Albany, Ga. The work remain-
ing to be done to complete the project consists of improving the
channel of the Apalachicola River from the mouth to Jim Woodruff
Dam, completing construction of Jim Woodruff Dam, and con-
structing Columbia Lock and Dam, Fort Gaines Lock and Dam,
and Buford Dam.
   The total cost under the existing project was $44,483,967, of
which $44,234,262 was for new work and $249,705 for mainte-
nance.
                                          Cost and financial summary

                                                   Fiscal year ending June 30                            Total to June
                                                                                                        30, 1954, includ-
                                                                                                        ing fiscal years
                                   1950          1951           1952           1953          1954        prior to 19501

New work:
    Appropriated-..._..        $7, 691, 000   $4, 520, 000   $7, 411, 152 $14, 365, 000 $12, 522, 000       $52, 094, 152
    Cost---------------         4, 542, 374    6, 538, 549    8, 042, 233 12, 401, 023 10, 115, 284          44, 234, 262
Maintenance:
    Appropriated ...               79, 737        12, 080         9, 488   ------------        3, 240            251, 775
    Cost_ ---------------          79, 877         4, 993        16, 979   -------------       1, 170            249, 705

  1 Exclusive of $1,885,117 for new work and $2,246,233 for maintenance on previous projects.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_........-......-.....                            $4, 029,408
    Appropriated for succeeding fiscal year ending June 30, 1955-..~....                                   15, 330, 000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955           -----------------------...---------------- 19, 359, 408
   Estimated additional amount needed to be appropriated for com-
      pletion of existing project---------------.................... .................................... 118, 466, 000
         3. BUFORD DAM AND RESERVOIR, APALACHICOLA,
       CHATTAHOOCHEE, AND FLINT RIVERS, GA., AND FLA.
   Location. Buford Dam is on the Chattahoochee River about
348.5 miles above its mouth, 50 miles above Atlanta, and 5 miles
northwest of the town of Buford, Ga. The reservoir extends
about 47 miles upstream along the Chattahoochee River, and about
21 miles up the Chestatee River, which enters the Chattahoochee
River 14.5 miles above the dam.
   Existing project. This project, now under construction, con-
sists of a rolled-fill earth dam 1,630 feet long, with crest at eleva-
tion 1,106 feet mean sea level, or about 192 feet above streambed
elevation; three earth saddle dikes with a total length of 6,600
feet; a chute spillway with crest at elevation 1,085; a powerhouse
in a deep cut with steel penstocks in tunnels, and concrete intake
422            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

structure at upstream end of tunnels; and a flood-control sluice
tunnel paralleling the power tunnels. The underlying foundation
is rock. The reservoir will have a gross capacity of 2,077,000
acre-feet, of which 192,000 acre-feet will be reserved for flood
control and 1,018,000 acre-feet will be used for hydroelectric
power, with normal pool elevation at 1,070. Power installations
will consist of one generating unit of 6,000 kilowatts, and two
units of 40,000 kilowatts each, or a total of 86,000 kilowatts.
   The approved estimated cost for new work, revised in 1954, is
$40,706,000, of which, $22,736,100 is for construction, $4,311,000
for lands and damages, and $13,631,900 for relocations. The latest
 (1954) approved estimate for annual cost of maintenance is $210,-
000, including operation and care.
   The River and Harbor Act of July 24, 1946, approved modifica-
tion of the general plan for full development of the Apalachicola,
Chattahoochee, and Flint River system, and authorized for the
initiation and partial accomplishment thereof the construction of
Buford multipurpose reservoir and other related developments in
accordance with House Document 300, 80th Congress, 1st session.
   Local cooperation. This prrovides that local interests agree to
maintain and operate at their expense all utility and highway
facilities which may be relocated or otherwise altered at part of the
improvement, and to hold and save the United States free from
damages which might arise from construction of the improvement.
   Operations and results during fiscal year. New work per-
formed under contract during the fiscal year was as follows:
   Main dam commenced....------........                          ----------------------------..........                 $277, 406
   Outlet works continued .------. ----.....                              ........---------.... --                       651, 031
   Power intake works commenced .....                  . . .                ...........------------------------------- 1,488,472
   Saddle dikes completed               ------------------------...--------------                                          3, 360
   Powerhouse equipment ...                        --------------------------------------                                      84
   Design and manufacture of turbines and generators continued-------.......--. 70, 895
   Tailrace completed---------------------------------------...                                                           52, 846
   Relocations of roads, railroads, and utilities              ....           ---- .---------------------....            499, 013
   Buildings, grounds and utilities.......---------------.....         ................-----------------                   2, 770

      Total contract costs..                      --------.....---------------.....-----------                   3,045, 877

  New work performed with hired labor consisted of continued
acquisition of lands and payment of damages at a cost of $259,864.
  The cost of stores and supplies was $236. An adjustment of
prior year cost of roads, railroads, and bridges resulted in a credit
of $4,715.
  The total cost during the fiscal year for Buford Dam and
Reservoir was $3,301,262.
  Condition at end of fiscal year. Construction of Buford Dam
and Reservoir, which was commenced in February 1950, was about
21 percent completed. Saddle dikes, spillway, and lining of tunnels
were completed. Construction of intake structures was well ad-
vanced and work on main dam had commenced. Design and
manufacture of turbines and generators was being continued.
Work in connection with land acquisition and relocation of roads
and utilities was in progress. Work remaining to be done includes
completion of dam, powerhouse, and switchyard; acquisition of
                RIVERS AND HARBORS-MOBILE, ALA., DISTRICT                                                          423
lands and relocation of roads and utilities; and clearing of the
reservoir area.
  The total cost under the existing project for Buford Dam and
Reservoir was $8,646,879 for new work.
                                        Cost and financial summary

                                                Fiscal year ending June 30                               Total to June
                                                                                                        30, 1954, includ-
                                                                                                        ing fiscal years
                                 1950         1951             1952.          1953           1954        priorto 1950

New work:
   Appropriated     _--------     1        $1, 318, 000     $1, 150,000    $4, 101,000    $5,120,000        $12,671, 000
   Cost---      --------                      669,614        1, 785, 537    2, 165, 034    3,301, 262          8, 646, 879

  1 Included under project for Apalachicola, Chattahoochee, and Flint Rivers, Ga. and Fla.
Other new work data:
    Unobligated balance, fiscal year ending; June 30, 1954....                $1, 942, 314
                                                                  ......----------
    Appropriated for succeeding fiscal year ending June 30, 1955......-..... 10, 310, 000
    Unobligated balances available for succeeding fiscal year ending
       Junie 30, 1955-........                                                                           11, 442, 314
     Estimated additional* amount needed to be appropriated for com-
       pletion of existing project-----------...     --..
                                                 --.. ---------------- 17, 725,000

         4. FORT GAINES LOCK AND DAM, APALACHICOLA,
        CHATTAHOOCHEE, AND FLINT RIVERS, GA., AND FLA.
   Location. The proposed Fort Gaines Lock and Dam will be
located on the Chattahoochee River about 75.2 miles above its
mouth and about 1.5 miles above the town of Fort Gaines, Ga:.
 (See U.S. Geological Survey maps for northwest Georgia.)
   Existing project. This project, as now planned, provides for a
concrete dam, gated spillway, and tandem locks, with earth em-
bankments at either side. The non-overflow section of the dam will
include powerhouse and intake structures. The gated spillway
will be 692 feet long with fixed crest at elevation 163 feet mean
sea level. The two earth embankments, of almost equal lengths,
will have a total length of 11,940 feet, with crest elevation at 216,
or about 114 feet above streambed elevation. The non-overflow
section of the concrete dam will have a total length of 712 feet, and
the deck of the powerhouse section will be at elevation 209. The
two locks in tandem will each have usable chamber dimensions of
82 feet by 450 feet, and a combined total lift of 92 feet with normal
upper pool elevation at 190. Depths will be 13 feet over lower
sill and 18 feet over upper still at normal pool elevation. The un-
derlying foundation is limestone. Total reservoir capacity will
be 924,600 acre-feet, with 209,800 acre-feet reserved for power.
Power installation will consist of 4 units of 32,500 kilowatts each,
or a total of 130,000 kilowatts.
   The approved estimated cost for new work, revised in 1954, is
$86,329,000, of which $62,457,000 is for construction, $6,668,000
for lands and damages, and $17,204,000 for relocations. The
latest (1954) approved estimate for annual cost of maintenance
is $254,000, including operation and care.
   The Committee on Public Works of the House of Representa-
tives, by resolution adopted May 19, 1953, approved the plan as pro-
posed by the Chief of Engineers for a high dam at the Fort Gaines
424             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

site and a low dam at the Columbia site in lieu of a low dam at the
Fort Benning site and a high dam at the upper Columbia site,
construction of which had been authorized by the River and Har-
bor Act of July 24, 1946, as initiation and partial accomplish-
ment of the plan for full development of the Apalachicola, Chat-
tahoochee, and Flint River system.
   Local cooperation. This provides that local interests agree to
maintain and operate at their expense all utility and highway
facilities which may be relocated or otherwise altered as part of the
improvement, to provide suitable public terminal facilities open
to all on equal terms, and to hold and save the United States free
from damages which might arise from construction of the im-
provement.
   Terminal facilities. On the Chattahoochee River the terminals
consist of natural landings at Columbus, Ga., and Eufaula, Ala.,
and a masonry marginal landing, at Columbus. These facilities
are considered adequate for existing commerce.
   Operations and results during fiscal year. New work: Hired
labor: Preliminary planning studies were continued and a general
design memorandum was completed. The total cost was $158,855
for new work.
   Condition at end of fiscal year. No construction has been per-
formed on this project. A memorandum on the general design
has been completed. Work remaining to be done prior to initiation
of construction consists of the preparation of plans and specifica-
tions.
   The total cost to June 30, 1954, under the existing project was
$580,635 for new work.
                                      Cost and financial summary

                                            Fiscal year ending June 30                     Total to June
                                                                                          30, 1954, includ-
                                                                                          ing fiscal years
                               1950        1951        1952        1953        1954         prior to 1950

New work:
   Appropriated           -
   Cost ....----------------
                                2
                                2
                                            2
                                            2
                                                        2
                                                        2
                                                                     1
                                                                 1$187, 598
                                                                              $152, 000
                                                                               158, 855
                                                                                                  $583, 113
                                                                                                   580, 635


  1Amounts shown are those carried on cost account (Form 38) for Upper Columbia Lock and Dam (Fort
Gaines L & D is now proposed in lieu of the formerly proposed Upper Columbia L & D).
  2 Amounts included under project for Apalachicola, Chattahoochee, and Flint Rivers, Ga., and Fla.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 .....--------------    $..2,479
                                                                                 20,000
    Appropriated for succeeding fiscal year ending June 30, 1955-----..---.........
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955.....------------------------------------------22,479
    Estimated additional amount needed to be appropriated for com-
                                                                            85, 726, 000
      pletion of existing project------.....................----------------------

          5. JIM WOODRUFF LOCK AND DAM, APALACHICOLA,
          CHATTAHOOCHEE AND FLINT RIVERS, GA., AND FLA.
  Location. Jim Woodruff Lock and Dam is on the Apalachicola
River, 107.6 miles above its mouth, about 1,000 feet below the
confluence of the Chattahoochee and Flint Rivers, and 1.5 miles
           RIVERS AND HARBORS-MOBILE, ALA., DISTRICT             .425
northwest of Chattahoochee, Florida.         The reservoir extends
about 52 miles upstream along the Chattahoochee River to the
vicinity of Columbia, Alabama, and about 47 miles upstream along
the Flint River, or 17 river miles above Bainbridge, Georgia.
  (See U. S. Geological Survey maps for Southwest Georgia.)
    Existing project. This project, now under construction, con-
sists of a concrete open-crest spillway 1,634 feet long on the right
bank, with crest at elevation 79.0 feet mean sea level; a single-
lift lock with usable chamber dimensions of 82 feet by 450 feet,
a maximum lift of 33.0 feet, and depth over sills of 14.0 feet; a
gated spillway 760 feet long with bridge at elevation 107 feet
mean sea level, or about 67 feet above streambed elevation; a
powerhouse with intake section constituting a portion of the dam;
an earth section 490 feet long to accommodate switchyard and
substation; and an overflow dike section 2,820 feet long on left
bank, with crest at elevation 85. ' The underlying foundation is
limestone. At normal pool elevation of 77, the reservoir will have
a total capacity of 385,000 acre-feet, of which, 37,000 acre-feet
will be used for the generation of hydroelectric power. The power
installations consist of 3 units of 10,000 kilowatts each, or a total
of 30,000 kilowatts.
    The estimated cost for new work, revised in 1954, is $47,096,000,
consisting of $44,444,900 for construction, $2,468,500 for lands
and damages, and $182,600 for relocations. The latest (1954)
approved estimate for annual cost of maintenance is $263,000, in-
cluding operation and care of lock and dam.
    The River and Harbor Act of July 24, 1946, approved modifica-
tion of the general plan for full development of the Apalachicola,
Chattahoochee, and Flint River system, and authorized for the
initiation and partial accomplishment thereof the construction of
Jim Woodruff, formerly Junction, multipurpose development and
other related developments in accordance with House Document
300, 80th Congress, 1st session.
    Local cooperation. This provides that local interests agree to
maintain and operate at their expense all utility and highway
facilities which are relocated or otherwise altered as a part of the
improvement, to provide suitable public terminal facilities open to
all on equal terms, and to hold and save the United States free
from damages which might arise from the construction of the im-
provement.
    Terminal facilities. A private wharf at River Junction, Fla., is
used for landing and storing sand and gravel. On the Flint River
there is a natural landing at Bainbridge, Ga., and also at Albany,
Ga. On the Chattahoochee River the terminals consist of natural
landings at Columbus, Ga., and Eufaula, Ala., and a masonry
marginal landing at Columbus. These facilities are considered
adequate for the existing commerce.
   Operations and results during fiscal year. New work performed
under contract during the fiscal year was as follows:
426.            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

     Construction of gated spillway continued.......           .......-------------------- $2, 372,589
     Lock guide walls and operating equipment--------.-.-.-..........                           16, 292
     Work on powerhouse continued....          ..                                              934, 195
     Design and manufacture of turbines and generators continued                               549, 754
     Powerhouse equipment....................--------------------------887,474
     Work on switchyard continued_....              ..                                          35, 881
     Construction of roads continued_.........                                                    2, 612
     Channel excavation.........-------------.........                                         214, 084
     Permanent operating equipment- ,.......__......
                                                  -    --.....                                   10, 664
     Relocations of roads and utilities continued--------..-.........___......_                 74, 373
     Reservoir preparation continued and clearing commenced_--...............                1,496,395
         Total contract costs                                        ----.-..--...--..----........          .          --      .    6, 594, 314
   New work performed with hired labor consisted of continued
acquisition of lands and payment of damages at a cost of $59,066,
and other miscellaneous work at a cost of $1,787.
   Maintenance operations in connection with the project cost
$1,170.
   The total cost during the fiscal year was $6,656,337, of which
$6,655,167 was for new work and $1,170 for maintenance.
   Condition at end of fiscal year. Construction of Jim Woodruff
Lock and Dam, which was commenced in September 1947, was
about 74 percent completed. Work on lock and fixed-crest spill-
way has been completed. Construction of gated spillway, power-
house, and switchyard, and preparation of reservoir area, were
well advanced. Work remaining to be done consists principally
of completion of gated spillway, powerhouse, and switchyard, and
some further reservoir clearing.
  The total cost under the existing project for Jim Wodruff Lock
and Dam was $3.4,873,445.
                                                Cost and financial summary

                                                               Fiscal year ending June 30                                        Total to June
                                                                                                                                30, 1954, includ-
                                                                                                                                ing fiscal years
                                        1950                 1951                   1952             1953           1954           prior to 1950

New work:
   Appropriated        --..              1             $2, 922, 000           $6, 309, 000 $10, 264, 000        $7, 250, 000         $38, 763, 000
    Cost       -1             .          1.........    $5, 948, 571           $6, 053, 839 $10, 030, 160        $6, 655, 167          $34, 873, 445
Maintenance:
    Appropriated------...         ---        ----------------------------------------                                 3, 240                 3, 240
    Cost ----------------                ----------------------------------------                                     1, 170                 1, 170

  1Included under project for Apalachicola, Chattahoochee, and Flint Rivers, Ga., and Fla.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954..__................... $2,084, 616
    Appropriated for succeeding fiscal year ending June 30, 1955............ 5, 000, 000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955-.....      .........         ...............................---------------------------                       7, 084, 616
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project.---.............---..........-------------------------......................................... 3,333, 000
   6. EAST PASS CHANNEL FROM THE GULF OF MEXICO INTO
                CHOCTAWHATCHEE BAY, FLA.
   Location. This is an entrance from the Gulf of Mexico into
Choctawhatchee Bay at the eastern end of Santa Rosa Island. It
is 48 miles east of the entrance into Pensacola Bay and 49 miles
west of the new entrance to St. Andrew Bay. (See U. S. Coast and
Geodetic Survey Chart No. 1264).
                   RIVERS AND HARBORS-MOBILE, ALA., DISTRICT                                                 427
   Existing project. This provides for maintenance of a channel
12 feet deep at mean low water, 180 feet wide, and about 3 miles
long from Choctawhatchee IBay into the Gulf of Mexico, and main-
tenance of a channel 6 feet deep, 100 feet wide, and about 2,000
feet long from the East Pass Channel into Old Pass Lagoon. The
mean range of tide is 1.3 feet; the extreme range, except during
storms, is 2.5 feet.
   The latest (1954) approved estimate for annual cost of mainte-
nance is $25,000.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                          Work authorized                                     Documents
July     3, 1930   Maintenance of a channel not less than 6 feet deep        H. Doec. 209, 70th Cong., 1st sess.
                    and 100 feet wide from Choctawhatchee Bay into
                    the Gulf of Mexico.
Oct. 24, 19511     Maintenance of entrance channel 12 feet deep and          H. Doc. 470, 81st Cong., 2d sess.'
                    180 feet wide and channel to Old Pass Lagoon 6 feet
                    deep and 100 feet wide.

1 Public Law 193, 82nd. Cong.
2 Contains latest published map.

   Local cooperation. Requires that local interests hold and save
the United States free from property damage that might result
from maintenance operations. Compliance not requested.
   Terminal facilities. The small privately owned pile-and-timber
piers used in connection with the fishing industry in this locality
are considered adequate for existing commerce.
   Operations and results during fiscal year. The U. S. pipeline
dredge Josenhans removed 67,676 cubic yards of material from
the entrance channel April 10 to 27, 1954, at a cost of $16,854.
Miscellaneous investigations and surveys cost $1,697.
   The cost for the fiscal year was $18,551 charged to maintenance.
   Condition at end of fiscal year. The existing project, which is
for maintenance, was commenced in 1930, and work carried on
intermittently since that time. The controlling depths, ascer-
tained in May, 1954, were 12 feet in the entrance channel and 6
feet in the channel to Old Pass Lagoon. The cost under the exist-
ing project was $178,062, for maintenance.
                                        Cost and financial summary

                                               Fiscal year ending June 30                          Total to June
                                                                                                  30, 1954, includ-
                                                                                                  ing fiscal years
                                 1950        1951         1952            1953         1954        prior to 1950
Maintenance:
   Appropriated..--......        $15, 000     $7, 004     $51, 867        $13, 700     $21, 107          $181, 246
   Cost-----------------          15,082       7, 054      51, 867         13, 072      18, 551            178, 062


                                  7. MOBILE HARBOR, ALA.
  Location. This harbor, located along the lower 5 miles of Mo-
bile River, is in southwestern Alabama, 91 miles by water west of
Pensacola Harbor, Fla., 90 miles east of Gulfport Harbor, Miss.,
and 144 miles by water northeast of the mouth of the Mississippi
River. (See U. S. Coast and Geodetic Survey Chart No. 1266.)
428      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Previous projects. The original project for the bar channel
was adopted by the River and Harbor Act of June 13, 1902. The
original project for the bay and river channels was adopted by the
River and Harbor Act of May 20, 1826, and subsequent projects
were adopted by the River and Harbor Acts of July 11, 1870;
March 3, 1879; August 11, 1888; March 3, 1899; June 25, 1910;
and August 8, 1917. For further details, see page 1840, Annual
Report for 1915; pages 802 and 807, Annual Report for 1916;
page 833, Annual Report for 1929; and page 718, Annual Report
for 1938.
   Existingproject. This provides for (1) a 36- by 450-foot chan-
nel about 1.5 miles long across Mobile Bar; (2) a 32- by 300-foot
channel in Mobile Bay to the mouth of Mobile River; (3) a 32-
foot channel in Mobile River to the highway bridge, the widths
varying from 500 to 775 feet; (4) a 25-foot channel from the
highway bridge to and up Chickasaw Creek to a point 400 feet
south of the mouth of Shell Bayou, the widths being 500 feet in
Mobile River and 250 feet in Chickasaw Creek; (5) an anchorage
area 32 feet deep, 200 feet wide, and 2,000 feet long opposite the
United States Quarantine Station on Sand Island; (6) a turning
basin 32 feet deep, 2,500 feet long, and 800 to 1,000 feet wide,
opposite the Alabama State Docks; (7) a 27- by 150-foot channel
from the mouth of Mobile River to and including a turning basin
250 feet wide and 800 feet long in Garrows Bend, and continuing
thence to a turning basin 800 feet long and 600 feet wide opposite
Brookley Air Force Base ocean terminal, thence a 27- by 150-foot
channel along Arlington pier to the Mobile Bay Channel; and (8)
maintenance by snagging Three Mile Creek from its intersection
with the Industrial Canal to Mobile River. The total length of
the bay and river channels is about 41.7 miles. The plane of refer-
ence is mean low water. Under ordinary conditions the mean
tidal range at the lower end of the improvement is 1.2 feet and at
the upper end 1.5 feet; the extreme tidal range is 3.4 feet at the
lower end and 3.6 feet at the upper end.
   The project was completed at a cost of $1,200,179 for new
work, exclusive of amounts expended on previous projects. The
latest (1954) approved estimate for annual cost of maintenance is
$400,000.
   The existing project was authorized by the following River and
Harbor Acts:
                       RIVERS AND HARBORS-MOBILE, ALA., DISTRICT                                         429
                                                                                                    1
       Acts                       Work authorized                                     Documents
                   i

July     3, 1930
              Present project dimensions across the bar and to the      Rivers and Harbors Committee
                mouth of Mobile River, thence 32 feet deep and 300        Doc. 26, 71st Cong., 2d sess.
                feet wide to the highway bridge; and for the an-
                chorage basin.
Aug. 26, 1937 For improvement of Three Mile Creek by snagging           Rivers     and Harbors       Committee
                from Mobile River to the Industrial Canal.                Doec.   69, 74th Cong.,   1st sess.
    Do._..... To provide a 600-foot channel 32 feet deep from a point   Rivers     and Harbors       Committee
                about 5,000 feet south of the mouth of Three Mile         Doe.    44, 75th Cong.,   1st sess.
                Creek to the highway bridge across Mobile River,
                subject to the provision that no dredging be per-
                formed within 50 feet of any pierhead line.
Oct. 17, 1940 To provide a channel 27 feet deep and 125 feet wide       H. Doc. 221, 76th Cong., 1st sess.
                from the Mobile River channel at itsmouth through
                Garrows Bend to and including a turning basin of
                the same depth, 800 feet long and 250 feet wide.
    Do----... Further modified to provide for extension of the chan-    H. Doc. 282, 76th Cong., 1st sess.
                nel through Garrows Bend 27 feet deep and 125 feet
                wide to and including a turning basin of the same
                depth, 800 feet long and 600 feet wide.
May 28,1935   Authorized and adopted the improvement of Chicka-         Emergency Relief Act of 1935.
Aug. 30, 1935   saw Creek by snagging and dredging.                     H. Doec. 47, 73d Cong., 1st sess.
Mar. 2, 1945  Adoption of existing channel through Garrows Bend         H. Doc. 282, 76th Cong., 1st sess.
                from Choctaw Point to Arlington pier, 27 feet deep
                and 150 feet wide, with 2 turning basins.
              Adoption of the existing channel alongside Arlington
                pier from the Mobile Bay Channel to turning basin
                at the inner end of Garrows Bend Channel, 27 feet
                deep and 150 feet wide.
              An anchorage area 32 feet deep, 200 feet wide, and
                approximately 2,000 feet long on the west side of
                the Mobile Bay Channel at the quarantine station
                on Sand Island, by extending the present anchorage
                southward 500 feet and northward to an inter-
                section with the Mobile River Channel.
              A channel 700 feet wide in Mobile River from the
                mouth to the first bend, 775 feet wide through the
                first bend, 600 feet wide thence to Alabama State
                docks pier A, south, and a turning basin opposite
                the Alabama State docks about 2,500 feet long,
                800 feet wide at the lower end, and 1,000 feet wide
                at the upper end, all to a depth of 32 feet.
              A channel 25 feet deep and generally 500 feet wide
               in Mobile River from the highway bridge to the
               mouth of Chickasaw Creek, thence 25 feet deep and
                250 feet wide in Chickasaw Creek to a point about
               400 feet below Shell Bayou.

1 Contain the latest published maps.

   Recommended modification of the project. Under date of July
31, 1952, the Chief of Engineers recommended modification of the
existing project to provide for enlarging the Mobile Bar Channel
to a depth of 42 feet and width of 500 feet, enlarging the Mobile
Bay main channel to a depth of 40 feet and width of 400 feet,
deepening the Mobile River Channel from the mouth to the high-
way bridge and the turning basin opposite the Alabama State
Docks to depths of 40 feet for widths essentially as provided for
under the existing project, and widening the river channel to 800
feet opposite Magazine Point to provide a turning basin 40 feet
deep and 1,400 feet long with additional tapered sections at each
end; at an estimated cost to the United States of $5,778,000 for
new work and $290,000 annually for maintenance in addition to
that now required; subject to certain conditions of local coopera-
tion (H. Doc. 74, 83d Cong., 1st sess.)
   Local cooperation. Fully complied with. For the work author-
ized in accordance with House Document No. 47, 73d Congress, 1st
session; Rivers and Harbors Committee Document No. 44, 75th
Congress, 1st session; House Document No. 221, 76th Congress,
1st session; House Document No. 282, 76th Congress, 1st session;
and House Document No. 739, 79th Congress, 2d session; local in-
430                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

terests are required to furnish necessary spoil-disposal areas for
subsequent maintenance as required.
   Terminal facilities. The modern rail-connected terminal facili-
ties at this port are considered adequate for existing commerce.
 (See Port Series No. 18, revised in 1949.)
   Operations and results during fiscal year. Maintenance: The
contractor's pipeline dredge Mansfield removed 765,863 cubic
yards of material in the Arlington Channel June 1 to 21, 1954,
and 235,241 cubic yards of material in the Mobile Bay Channel
June 22 to 30, 1954, at a cost of $73,819. The cost for buoy mark-
ing the wreck "Magnolia" was $477. Miscellaneous investigations
and surveys cost $21,804.
   The cost for the fiscal year was $96,100, charged to maintenance.
   Condition at end of fiscal year. The existing project, com-
menced in 1931, was completed in July 1949. The latest examina-
tion show minimum depths, at mean low water, available to navi-
gation as follows:

                                                                                                      Minimum depth

                                                                                 Project
       Date                                   Section                            depth         Left    Left   Right    Right
                                                                                  (feet)     outside inside   inside  outside
                                                                                             quarter quarter quarter quarter
                                                                                              (feet)  (feet)   (feet)  (feet)


February 1954         Bar Channel------_....._---------------                           36     36.0     36.0    36.0      36.0
                      Bay Channel:
January 1954              South end to beacon 24------------............--.             32     30.0     32.0    32.0      30.0
   Do-.......             Beacon 24 to beacon 38--------------.............             32     31.0     32.0    32.0      31.0
   Do.........            Beacon 38 to mouth of river--------.........                  32     31.0     32.0    32.0      32.0
                      River Channel:
January 1954              Mouth to first bend-----------------.................         32     30.0     31.5    29.0      26.0
    Do___....__          Through first bend....-.---------                              32     30.0     32.0    32.0      30.5
November 1953             Second bend to turning basin.......                           32     32.0     32.0    32.0      32.0
    Do.........          Turning basin                    -------....................   32     32.0     32.0    32.0      32.0
    Do-........          Turning basin to highway bridge.-.-                            32     32.0     32.0    20.0      15.5
                      Chickasaw Creek:
October 1953              Highway bridge to mouth of creek...                           25     25.0     25.0    17. 5     16.5
   Do......---------.    Mouth to 400 feet, south of Shell                              25     23.0     24.0    24.0      22.5
                           Bayou.
June         1954 Arlington Channel_.               -      -------                      27     27.0     27. 0   27.0      27.0
October      1953 Garrows Bend Channel-_-                            ...-------.        27     20.0     22.0    22.0      19.5
June         1954     Garrows Bend Turning Basin...----..-------.                       27     27.0     27.0    27.0      27.0
January 1954 Quarantine Station Basin---------------...............                     32     24.0     28.0    28.0      32.0



     A channel 27 feet deep and 150 feet wide alongside of Arlington
Pier from Mobile Bay Channel to the turning basin at the inner
end of Garrows Bend Channel was completed in April 1942.                                                                This
channel, constructed with military funds for the Brookley Air
Force Base, was included in the project for Mobile Harbor, Ala.,
by the River and Harbor Act approved March 2, 1945 (H. Doc.
282, 76th Cong., 1st sess., and H. Doc. 739, 79th Cong., 2d sess.).
   The costs on the existing project to June 30, 1954, were as
follows:
                      RIVERS AND HARBORS-MOBILE, ALA., DISTRICT                                                              431
                                                                                                         Costs

                                                                                         New work       Maintenance       Total

Regular funds------------           _,-                                     - --          $1, 144, 937      $6, 536, 416 $7, 681, 353
Public Works funds---- ----------------------------.. --                                       14, 000--14,                       000
Emergency Relief funds---...........................------------------------------....         41,242 ----------------        41, 242
        Total.----------..----------                               ---.--...
                                                                     ..                    1,200, 179       6,536,416     7,736,595


                                                   Cost and financial summary

                                                              Fiscal year ending June 30                            Total to June
                                                                                                                   30, 1954, includ-
                                                                                                                   ing fiscal years
                                           1950             1951              1952           1953         1954      prior to 19501
New work:
   Appropriated...           -$28, 988 ------- ------------------------------------                                      $1, 200, 179
   Cost....-----------------    64, 850                                                                                   1,200,179
Maintenance:
   Appropriated--...     _-    549, 250    $216, 031 $306, 050 $473, 369  $245, 410                                       6, 688, 870
   Cost .---------------- 493, 022          257, 945  350, 637  474, 598    96, 100                                       6, 536, 416

   1 Exclusive of $6,683,104 for new work and $4,096,681 for maintenance for previous projects.

      8. REMOVING THE WATER HYACINTH, MOBILE DISTRICT
  Location.                    Streams tributary to the Gulf coast in the Mobile
district.
  Existing project. This provides for the extermination or re-
moval of plants from the navigable waters of Florida, Alabama,
Mississippi, Louisiana, and Texas, so far as they are or may be-
come an obstruction to commerce, by any mechanical, chemical, or
other means whatsoever; for the construction and operation of
boats equipped with suitable machinery for such removal; and for
the construction and operation of log booms to prevent the drifting
of plants from one stream to another.
  The estimate of cost, made in 1899, was $25,000 each for 2 boats,
$10,000 for operation in each district, and $1,000 for the establish-
ment of booms. The latest (1954) approved estimate for annual
cost of maintenance is $15,000.
   The existing project was authorized by the following River and
Harbor Acts:

      Acts                                     Work authorized                                             Documents
Mar. 3,1899           Appropriations made for the States of Florida and                         H. Doc. 91, 55th Cong., 3d sess.
                       Louisiana and provided for the extermination or
                       removal of plants, the building of boats, and the
                       establishment of booms.
June 13, 1902         Use of any mechanical, chemical, or other means
                       whatsoever.
Mar. 3, 1905          Appropriation made available for the State of Texas.
    Do-,--            Appropriation made for Florida, provided that no
Mar. 2,1907            chemical process injurious to cattle shall be used.
July 25,1912          Appropriation made available for the State of Miss-
                       issippi, and also made available for use in that
                       State the operating plant pertaining to the work
                       in Louisiana.
July 27,1916          Appropriation made available for the State of Ala-
                        bama.
432            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  Local cooperation. None required.
   Operationsand results during fiscal year. United States plant
and hired labor operating in Alabama on Dog River July 1 to 3,
1953; Little and Big Briar Creeks, July 20 to 30, 1953; and Negro
Lake, Smith Bayou, Owl, Maple and Six Bits Creeks, Duck and
Squirrel Bayous, June 1 to 30, 1954, sprayed 257 acres of hyacinth.
  The cost for the fiscal year was $4,334, charged to maintenance.
   Condition at end of fiscal year. The existing project, which is
for maintenance, was commenced about 1899, and work has been
carried on as required since that time. The cost under the exist-
ing project was $444,287 for maintenance.
                                   Cost and financial summary

                                         Fiscal year ending June 30                        Total to June
                                                                                           30, 1954, includ-
                                                                                           ing fiscal years
                            1950        1951          1952           1953       1954         prior to-.1950

Maintenance:
   Appropriated--------     $25, 000    $25, 000     -$2,      532    $8, 221    $6, 989           $447, 553
   Cost -----------------    28, 358     17, 222            5, 578     7, 610     4, 334            444, 287



                9. ALABAMA-COOSA                   RIVERS, ALA. AND GA.
   Location. The Alabama River is formed 18 miles above Mont-
gomery, Ala., by the junction of the Coosa and Tallapoosa Rivers.
Thence it flows southwesterly through Alabama 318 miles, and
unites with the Tombigbee River about 45 miles north of Mobile,
in southwestern Alabama, to form the Mobile River. (See U. S.
Geological Survey maps for central and southwest Alabama.)
   The Coosa River is formed at Rome, Ga., in northwest Georgia,
by the junction of the Oostanaula and Etowah Rivers, which have
their sources in northern Georgia. From Rome the Coosa River
flows southwesterly through Georgia and Alabama 286 miles, and
unites with the Tallapoosa River near Montgomery, Ala., at about
the center of the State, to form the Alabama River. (See U. S.
Geological Survey maps for northeast Alabama and northwest
Georgia.)
   Previous projects. Previous projects for Alabama River were
adopted by the River and Harbor Acts of June 18, 1878, July 13,
1892, March 3, 1905, and June 25, 1910. For further details, see
page 1837, Annual Report for 1915; page 725, Annual Report for
1938; and paragraph "Existing project," page 592, Annual Re-
port for 1944.
   Previous projects for the Coosa River were adopted by the
River and Harbor Acts of August 14, 1876, September 18, 1890,
July 13, 1892, June 25, 1910, and June 26, 1934. For further de-
tails of previous projects, see page 1837, Annual Report for 1915;
page 728, Annual Report for 1938; and paragraph "Existing
project," page 594, Annual Report for 1944.
   Existing project. This provides for the initial and ultimate
development of the Alabama-Coosa Rivers and tributaries for
navigation, flood control, power, and other purposes, substantially
in accordance with plans being prepared by the Chief of Engi-
neers, with such modifications thereof from time to time as in the
                    RIVERS AND HARBORS-MOBILE, ALA., DISTRICT                                                                             433
discretion of the Secretary of War and the Chief of Engineers may
be advisable for the purpose of increasing the development of
hydroelectric power; for the initiation and accomplishment of the
ultimate plan, it authorizes appropriations in such amounts as
Congress may from time to time determine to be advisable, the
total of such appropriations not to exceed $60 million.
   The initial phase of the ultimate development provides for the
construction of Howell Mill Shoals, Jones Bluff, and Millers Ferry
multiple purpose improvements, Claiborne lock and dam, and sup-
plemental channel work to provide a channel depth of 9 feet for
navigation from the mouth of the Alabama River to Montgomery,
Ala. The variation between average high and low water is 40.4
feet. The extreme variation is 58 feet at Montgomery.
   The following table gives various features of the proposed locks
and dams and multiple purpose developments included in the exist-
ing project:
                                                    Proposed structures

                                                         Claiborne          Millers Ferry                Jones Bluff             Howell Mill
                                                       lock and dam         lock and dam                lock and dam             Shoals dam

Miles above mouth..........----------------- 861.......------------         1451........---------- 2501_____                     1062.
Nearest town------.......             _ _ -_Claiborne,                      Camden, Ala._ Benton, Ala.__                         Easonville,
                                               Ala.                                                                                 Ala.
Distance (miles) __-------------------- 7 ..----------...                   7-----------               3-----------...........   1.5.
Greatest lock length available for full 450 ..----------                    450 .....----------.       450______
  width (feet).
Width of lock chamber (feet)----------         82___.......                 82........-----------      82_.______-_
Lift (feet) .--    ........-----------------.. 20-----------.............   50-----------..........    45
Elevation of normal pool surface (mean                30__ ...        ...   80-..--.....--------.       125 .---------- 4903.
  sea level).
Depth over sills at low water (feet) _.  12 .........-..                    12.....                   -..-.
                                                                                                    12..
Character of foundation -------------- _ Rock ...        ..                 Rock.....--------. Rock..........                    Rock.
Kind of dam _-----_-----------------.-   Fixed-.......                      Fixed......... Fixed- .......                        Fixed.
Height of dam (feet)-----------------50....-----------                      85.......-----------... 91.......-----------...      115.
Type construction- .... _______-          ._ Concrete----                   Concrete ._...             Concrete-_._ Concrete.
Reservoir capacity (acre-feet) _____-.... .    ___
                                              ...---- ...--.                370,000-.......            250,000-....... 680,500.
Power development (KW) .                             __...
                                               .----------------                              ..
                                                                            57,000.....__ _____        51,000_.                  132,000.
Percent complete-......--        ---------------------------------------------
Year opened to navigation--.....---    -   -------------------------------------
Estimated cost:
     Construction___---.---------       -             $13,925, 800_... $30,900,100 ....  $40,057, 200...                         $57, 583, 500.
     Lands and damages______________---                   234, 000...___ 2, 237, 000..     1,123, 000.                            10,696,500.
     Relocations.   -------------------                 1,200,000....    2, 200, 000 ...   7, 468,200....                         20,000,000.

       Total cost-_        .-                             15,359,800 ..
                                               _-------------------           44,337,100_ .-             48,648,400 ....          88,280 000.

  1 Above mouth of Alabama River.
  2 Above mouth of Coosa River.
  3 Power pool.

   The estimated cost for new work, revised in 1954, is $198,295,-
300, exclusive of amount expended on previous projects. The
latest (1954) approved estimate for annual cost of maintenance is
$1,027,000 including operation and care.
   The existing project was adopted by the River and Harbor Act
of March 2, 1945 (H. Doc. 414, 77th Cong., 1st sess.). The latest
published map of Alabama River will be found in Annual Report,
1912, page 2124. Drawings of the Alabama-Coosa Rivers and
tributaries are contained in House Document No. 66, 74th Con-
gress, 1st session.
   Public Law 436, 83d Congress, approved June 28, 1954, sus-
pended authorization of the comprehensive plan, insofar as it
provides for the development of the Coosa River, to permit non-
Federal interests to develop the Coosa River by construction of a
434      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

series of dams in accordance with the conditions of a license, if
issued, pursuant to the Federal Power Act and in accordance with
certain other provisions and requirements of the aforementioned
Public Law.
   The latest published maps of the Coosa River will be found in
Annual Report, 1890, page 1644, for that portion of the river from
lock No. 4 to Greensport; Annual Report, 1891, page 1752, for that
portion between Wetumpka and lock No. 4; and Annual Report,
1913, page 2125, for the upper Coosa.
   Local cooperation. None required.
   Terminal facilities. On the east bank at Montgomery, a natural
landing connects with the city streets. The Wofford Oil Co. has a
small wharf about 10 miles below Montgomery equipped for
handling petroleum products. There are also various natuzal
landings along the river. These facilities and natural landings on
the Alabama River are considered adequate for the existing
commerce.
   At Rome, Ga., there is one small wharf on the left bank of
Oostanaula River, and a private wharf on the left bank of Etowah
River, used exclusively by the owners. These facilities and natural
landings on the Coosa River are considered adequate for the exist-
ing commerce.
   Operationand results during fiscal year. New work: Work on
engineering studies and advance planning for Howell Mill Shoals
Dam was continued at a cost of $38,614.
   Maintenance: Disposal of property resulted in a credit of $826.
   The total net cost was $37,788, consisting of a new work cost of
$38,614 and a credit of $826 from maintenance operations.
   Condition at end of fiscal year. No construction has been per-
formed on the existing project. The controlling depths on the
Alabama River, ascertained in 1938, were as follows; Mouth to
Selma, 4 feet; Selma to Montgomery, 3.5 feet; Montgomery to
Wetumpka, 3 feet. Boats drawing 3 feet or less can usually oper-
ate throughout the year; greater depths are usually available from
November to June each year. Zero readings on the gages at Selma
and Millers Ferry, Ala., indicate that a depth of 4 feet is available
at these locations. A zero reading on the gage at Montgomery,
Ala., indicates that a depth of 31/ feet is available. On the Coosa
River the controlling depth was 21/2 feet on several of the bars;
from Gadsden, Ala., to Woods Ferry, 37 miles, the controlling
depth was 3 feet, certain shoals being the controlling points. From
Woods Ferry to Lock 4, 9 miles, the controlling depth was 4 feet.
These depths are available throughout the year; increased depths
ordinarily exist between January and June, inclusive. Since all
existing locks on the river are inoperative, through navigation is
impossible.
   The cost under the existing project was $1,736,237, of which
$1,645,056 was for new work, $71,918 for maintenance, and $19,263
for operating and care.
                  RIVERS AND HARBORS--MOBILE, ALA., DISTRICT                                                435
                                          Cost and financial summary

                                                Fiscal year ending June 30                         Total to June
                                                                                                  30, 1954, includ-
                                                                                                  ing fiscal years
                                   1950        1951        1952          1953         1954         priorto 19501

New work:
   Appropriated......-------- $165, 000       $185, 000    $75, 600     $200, 000   -$41, 000          $1, 684, 600
   Cost.......                 208, 349
                        -........              193, 960    243, 813      101, 784       38, 614         1, 645, 056
Maintenance:
    Appropriated .......--------   22, 188        -51 ------------         5, 886       -826                91, 181
    Cost-----------------          23,777 ..---------------------- --      5,886        -826                91,181


  1 Exclusive of $3,692,483 for new work and $2,978,050 for maintenance on previous projects.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954......................      $39, 544
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955------------.--...-------------                                    39, 544
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project---------..---------------------               196, 611, 000

    10. HOWELL MILL SHOALS DAM, ALABAMA-COOSA                                                     RIVER,
                       ALA. AND GA.
  Location. The proposed Howell Mill Shoals Dam will be located
on the Coosa River about 106 miles above its mouth, 123 miles
above Montgomery, 11 miles northwest of Talladega, and about
11/2 miles south of Easonville, Alabama. The reservoir will extend
about 70 miles upstream along the Coosa River to the vicinity of
Gadsden, Alabama. ( See U. S. Geological Survey maps for central
Alabama.)
  Existing project. This project, as now planned, provides for
a concrete gravity-type dam and fixed-crest spillway with earth
embankments at either side, and three earth saddle dikes. The
nonoverflow section of the concrete dam will include powerhouse
and intake structures, and the nonoverflow section of earth dike on
left bank will provide for future installation, if needed, of a navi-
gation lock 82 feet by 450 feet, with maximum lift of 89 feet. Total
length of earth embankment will be 10,400 feet, and total length of
saddle dikes will be 7,500 feet, with crest elevation of 525 feet mean
sea level, or about 115 feet above streambed elevation. The non-
overflow sections of the concrete dam will have a total length of
1,050 feet and deck elevation at 519. The spillway will be 600 feet
long with crest elevation at 490. The underlying foundation is
rock. At normal pool elevation of 490 feet mean sea level, the
reservoir will have a gross capacity of 680,500 acre-feet, with
367,700 acre-feet usable for power. Initial power installation
will be 132,000 kilowatts, with provision for ultimate installation
of 198,000 kilowatts.
  The estimated cost for new work, revised in 1954, is $88,280,000,
of which, $57,583,500 is for construction, $10,696,500 for lands
and damages, and $20,000,000 for relocations. The latest (1954)
approved estimate for annual cost of maintenance is $388,000,
including operation and care.
  This project has been selected as one of the units authorized
for the initial phase of development of the Alabama-Coosa River
and tributaries by the River and Harbor Act of March 2, 1945, in
accordance with House Document 414, 77th Congress, 1st session.
436          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Public Law 436, 83rd Congress, approved June 28, 1954, sus-
pended authorization of the comprehensive plan, insofar as it
provides for the development of the Coosa River, to permit non-
Federal interests to develop the Coosa River by construction of a
series of dams in accordance with the conditions of a license, if
issued, pursuant to the Federal Power Act and in accordance with
certain other provisions and requirements of the aforementioned
Public Law.
   Local cooperation. For the initial development at Howell Mill
Shoals Dam, local interests will be required to operate and main-
tain all utility, rail, and highway facilities relocated because of the
improvement. For the ultimate development, when navigation is
provided, local interests will be required to assume the cost of
collateral facilities including navigation terminal facilities.
   Terminal facilities. At Rome, Ga., there is one small wharf on
the left bank of Oostanaula River, and a private wharf on the
left bank of Etowah River, used exclusively by the owners. These
facilities, together with natural landings on the Coosa River, are
considered adequate for the existing commerce.
   Operations and results during fiscal year. New work, hired
labor: Preliminary planning studies were continued at a cost of
$38,614.
   Condition at end of fiscal year. No construction has been per-
formed on the Howell Mill Shoals Dam project. Engineering and
advance planning studies were in progress.
   The total cost to June 30, 1954 under the existing project was
$1,004,056 for new work.
                                    Cost and financial summary

                                          Fiscal year ending June 30                          Total to June
                                                                            _                30, 1954, includ-
                                                                                             ing fiscal years
                             1950        1951        1952        1953             1954         prior to 1950

New work:
   Appropriated.......--      1           1                     $200, 000       -$41,  000         $1, 043, 600
   Cost .............         1           11                    $101, 784         $38, 614         $1, 004, 056


  1 Amounts included under project for Alabama-Coosa River, Ala., and Ga.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 .....--------------...........     $39, 544
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955.       -..............                                                    39, 544
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project                 ........
                                           --.....--... -          .       ........      87, 236, 000


11. BLACK WARRIOR, WARRIOR, AND TOMBIGBEE RIVERS, ALA.
   Location. The Black Warrior and Warrior Rivers, a single
stream, rise in northern Alabama above Birmingham and flow
generally southwesterly to unite with the Tombigbee River at
Demopolis, Ala. Thence, the Tombigbee flows south, uniting with
the Alabama River to form the Mobile River 45 miles above the
head of Mobile Bay. The distance by water from Mobile to the
vicinity of Birmingham is about 415 miles.
   Previous projects. The original project for the improvement:
          RIVERS AND HARBORS-MOBILE, ALA., DISTRICT             437
of Warrior River, now combined with Black Warrior and Tombig-
bee Rivers, was adopted by act of March 3, 1875. For further de-
tails, see page 1841, Annual Report for 1915, and page 732, Annual
Report for 1938.
   Existing project. This provides essentially for a canalized
channel with minimum depth of 9 feet and a width of 200 feet,
where practicable, from the mouth of the Tombigbee River, 45
miles above Mobile, to the vicinity of Birmingham, via the Tom-
bigbee and Warrior Rivers, to mile 447.6 on Sipsey Fork, mile 444.6
on Mulberry Fork, and mile 420.6 on Locust Fork, a total distance
of 426.6 miles. The lift is accomplished by 15 locks and dams,
one of the locks being a double-lift structure.
   The project also provides for construction of a new lock and
dam near Demopolis, Ala., to replace existing dams 4, 5, 6, and 7;
and for increasing the length of the spillway at dam 1. The River
and Harbor Act of March 3, 1909, granted discretionary authority
to the Secretary of War to reconstruct any existing structure
whenever reconstruction is absolutely essential to its efficient and
economical maintenance and operation. The reconstruction may
include such modification in plan and location as may be necessary
to provide adequate facilities for existing navigation. Under this
authority existing locks 8 and 9 will be replaced by a single lock
near Eutaw, Ala., and, locks 1, 2, and 3 on the lower Tombigbee
River will be replaced by a new lock and dam near Jackson, Ala.
The project also provides for operation and care of all locks and
dams.
   The following table gives various features of the existing locks
and dams included in the existing project:
                                                                                            Existing locks and dams

                                                              Great-                                                                                        Type construction
                    Dis-                                       est       Width               Depth
                   tance                            Dis-      length       of                 over                                                                                                   Date of                      Actucost
     Lock         above        Nearest town         tance      avail-    cham-      Lift     sills at            Character of          Kind of                                                       comple- Date opened           of lock and
                    Mo-                            (miles)      able       ber     (feet)      low               foundation             dam                                                            tion  to navigation             dan d
                   bile 1                                     for full    (feet)             water                                                        Lock                   Dam                                                               M
                  (miles)                                     width                           (feet)
                                                               (feet)
                                                                                                                                                                                                                                                   C
1       ...--------- 101.6   Salitpa, Ala.......         5     281.9      52           12      2 8.0       Soft rock -_..          .    Fixed.       Concrete..           Concrete......              1909      Sept. 6, 1908      $560,290.02     O
2- ----           . 172.6    Pennington, Ala             3     286.0      52            9      10.0        Hard clay.                    do           do                  Timber crib,                1915      Nov. 1, 1914        560,114.09
                                                                                                                                                                            stone-filled.
3-...-....-          194.6 Whitfield, Ala                 9    286.0      52           10       9.0     --...    do----.....- ..._           do--        do..........         do .....--------        1915       Sept. 21, 1914     609, 622, 80
4________            221.6 Demopolis, Ala_..              1    285.6      52           10       9.0     -...             _..-
                                                                                                                 do ......               .. do ..        do...         ....   do               .      1908       Dec. 1, 1908       479,000.00
5.________        . 236.6  Greensboro, Ala_.            17     285.6      52           10       9.0      -....   do.....___               _do....do...                   ... do......                 1908       Sept. 1, 1908      501,000.00
6 .--                257.1 Sawyerville, Ala__             6    285.6      52           10       9.0        Piles----------... -- - do..do-....do-.......------do--------...                           1908       Oct. 1, 1908       443,000.00
7-.-----..           272.6 Eutaw, Ala_...__.              6    284.7      52           10       9.0      -... do---  ...                  _---do--- -- do--           -----
                                                                                                                                                                      ..     do--------               1903       Nov. 7, 1903       225,600.00
8- -
9-..-------
             .------ 288.6
                     305.6
                           Akron, Ala ....
                           Moundville, Ala__
                                                          3
                                                          7
                                                               284.7
                                                               284.7
                                                                          51.65
                                                                          52
                                                                                       10
                                                                                       11
                                                                                                9.0
                                                                                                9.0
                                                                                                         ....- do .........
                                                                                                           _..do     .......
                                                                                                                                             do_.do..-------
                                                                                                                                             do          do........do
                                                                                                                                                                                  ........
                                                                                                                                                                                                 .
                                                                                                                                                                                                      1903
                                                                                                                                                                                                      1902
                                                                                                                                                                                                                 Jan. 1, 1903
                                                                                                                                                                                                               ....  do.......
                                                                                                                                                                                                                                    212,400.00
                                                                                                                                                                                                                                    202 440.00
                                                                                                                                                                                                                                                       z
Tuscaloosa- 351.35         Tuscaloosa, Ala    ...._--------    460.0      95           30      10.8        Hard blue shale ...do-.. _ do-_ ...                           Concrete... _-               1940       Aug. 29, 1939    4,450, 873.50
13__                 360.6 Peterson, Ala_____             3    285.5      52           11      10.7        Hard sandstone.                 .__do___    Stone    ....     Stone...--------             1905       July 4, 1905       203,700.00
              __
14 .-------- 364.1 __. do...___- _____--                  7    282.1      52           14       9.5        ... do_,          _--... ....-- do__
                                                                                                                                                               ____
                                                                                                                                                       Concrete__ Concrete- .....                     1910       Mar. 29, 1910      414,714.89     z
                                                                                                                                                                                                                                                   M




15         .____.... 370.6 Northport, Ala ..            20     282.1      52           14      10.0     -..... do.         ..        ... _d ___do do ........                do--------.........      1910       May 2, 1910        430,233.87
16 ____          . 377.1   Adger, Ala _______           21     285.5      52           21       9.5       .- _,do .. -               ___.. do...         do--..--.... ... do__-----.                  1915       Jan. 1, 1915        520, 853.68
17 3____..           378.6   -...
                           _do.______...__.             20     285.5      52           72       9.5         ... do...........do                  ...     do.....           . do .......               1915       May 13, 1915     43,424,858.98
   Total lift .........                                                              254

  1 Mileage from foot of Government St., Mobile, Ala.                                                                                                                                                                                                  00
  2 River is tidal below this lock, and depth over the lower miter sill is 9 feet about 91 percent of the time, the minimum depth being 6.9 feet at extreme low tide.
  3 Double lock.
  4 Does not include $1,435,635.76 estimated cost of land submerged, damage to structures, and cost of clearing.
                                                                                                                                                                                                                                                       00
                                                                                                                                                                                                                                                       C3[
                     RIVERS AND HARBORS-MOBILE,                                            ALA., DISTRICT                           439
   The following table gives the various features of the proposed
locks and dams included in the existing project:

                                                                    Jacksons                   Demopolis3                  Warrior'
                                                                 lock and dam                lock and dam               loc ckand dam


Miles above Mobilel -    -____._.._-___ _                     95.6-                   173.1
                                                                          ...------------      _...----------- 271.1
Nearest town-----       -__.....               .__
                                            ___..             Jackson, Ala ....       Demopolis, Ala ._ Eutaaw, Ala.
Distance (miles)....-------------           ---..             6--------------         2                         6.
                                                                                                ......--------------
Greatest lock length available for full                       600------------- 600           ___------ . 600.
width (feet).
Width of chamber (feet)-----------...................         110                 110- ......-- --- 110.
Lift (feet)----     ---------------------                     34 -------------- 40----- ---------- 22.
Elevation of normal pool surface (mean sea                    33.._-------------- 73-----------     95.
  level).
Depth over sills at low water (feet)- ......               13.0--------------- 14.0               ------------        13.0
Character of foundation ----------------                   Piling in sand and Selma chalk- ....                       Pilin g in clay.
                                                              clay.
Kind of dam-----.........           .-.              -     M ovable ..         ..--------Fixed ..--                   M ov able.
Height of dam (feet)......-----------------                65                            60-------------
                                                                           ....-------------                          65.
Type construction-__--------....-..          .         . Earth, concrete.... Concrete                     ...------   Eart h, concrete.
Percent complete-------                     .......                                      81__... ________--
Year opened to navigation_--------                       I          ------------------ --
Estimated cost:
    Construction -___.              -------------
                                          _                        - $24,387, 600                  $17, 557, 200               $18,724,000
    Lands and damages .___.___-                _____..
                                                  .                    3,184,300                      1, 715,000                   807, 000
    Relocations__.._________-            ______
                                             -    --    _     ----       139,000                         410,800                    13,000

        Total__............___________________     __..                  27,710,900                  19,683,000                 19, 544, 000


  1 Mileage from foot of Government St., Mobile, Ala.
  2 Replaces existing locks and dams Nos. 1, 2, and 3.
  3 Replaces existing locks and dams Nos. 4, 5, 6, and 7.
  ' Replaces existing locks and dams Nos. 8 and 9.


   Tidal influence extends from Mobile 101.6 miles to lock 1, where
the tidal effect is apparent only at low stages of river. At Mobile
the mean and extreme tidal ranges are 1.5 and 3.6 feet, respec-
tively. These are at times slightly increased by the effect of winds.
The greatest fluctuation of river stages is at Demopolis, Ala., the
maximum being 59.7 feet. The maximum fluctuations at other
points are 40 feet at lock 1, 101.6 miles from Mobile; 57.8 feet at
Tuscaloosa, 352.6 miles from Mobile; 13 feet at Birmingport, 409.6
miles from Mobile; and 27 feet at Cordova, 429.6 miles from Mobile.
The ordinary fluctuations at these points are at lock 1, 20 feet;
at Demopolis, 35 feet; at Tuscaloosa, 40 feet; at Birmingport, 4
feet; and at Cordova, 7 feet. The works of improvement have re-
duced the amount of fluctuations at different points by 3 to 10
feet.
   The estimated cost of new work, revised in 1954, is $83,271,100,
exclusive of amounts expended on previous projects. The latest
 (1954) approved estimate for annual cost of maintenance is $940,-
000, including operation and care.
440                   REPORT :OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

    The existing project was authorized by the following River and
Harbor Acts:

       Acts                            Work authorized                                        Documents
                  I                                                           I


July    5, 1884       Original appropriation for improving Black Warrior
                       River
                      Original project for slack-water improvement author-        Annual Report, 1887, pt. 2, pg. 1302.
                       ized by Secretary of War Apr. 19, 1887.
Mar.    3,1899        Construction of the first locks between Tuscaloosa
                       and Demopolis.
Sept. 19, 1890        Maintenance of the section of Tombigbee River be-
                       low lock 1 to its mouth (66 miles) included in the
                       existing project.
    Do....... Construction of locks and dams 1, 2, and 3. Merging                 H. Doe. 178, 56th Cong., 2d sess.,
               of the individual projects for the Black Warrior                     and Annual Report 1901, pt. 3,
               and Warrior Rivers and the Tombigbee River                           p. 1858. H. Doc. 165, 57th Cong.
               below Demopolis.                                                     1st sess., and Annual Report,
                                                                                    1902, p. 1293.
Mar.    2,1907        Construction of locks and dams, 14, 15, 16, and 17.
Mar.    3,1909        Provides for reconstruction of obsolete structures,         Public Law No. 317.
                        modified in plan and location, to provide efficient
                        and economical maintenance and operation.
Aug. 22, 1911         Lift of lock 17 changed to 63 feet, and construction        H. Doec. 72, 62d Cong., 1st sess.
                        of locks and dams 18 and 19 eliminated from the
                        project. Extension of slack-water improvement
                        to Sanders Ferry on Mulberry Fork and Nichols
                        Shoal on Locust Fork.
Mar. 2, 1919          Raising of various dams 2 feet and raising the lock         Annual Report, 1918, p. 876.
                        walls 2 feet at lock 1 to provide a minimum depth
                        of 8 feet at low water, widening the channel to 150
                        feet where practicable.
Aug. 30, 1935         For snagging Mobile River from the mouth of Chick-          H. Doc. 728, 71st Cong., 3d sess.
                        asaw Creek to the junction of the Alabama and
                        Tombigbee Rivers.                                                                            1
    Do...-.           Increase channel dimensions to 9 by 200 feet; con-          H. Doc. 56, 73d Cong., 1st sess.
                        struct crest gates at Lock and Dam 17; add flash-
                        boards at all dams; Sunflower Bend Cut-off.
    Do-------         Construction of a lock and dam below Tuscaloosa to          Rivers and Harbors Committee
                        replace original locks and dams 10, 11, and 12.             Doe. 26, 74th Cong., 1st sess.
June 26, 19342        Operation and care of locks and dams provided for
                        with funds from War Department appropriations
                        for rivers and harbors.
Mar. 2, 1945          Construction of a lock and dam near Demopolis to            H. Doe. 276, 76th Cong., 1st sess.
                        replace existing dams 4, 5, 6, and 7.
    Do. ...           Provide increased spillway capacity at dam 1_-_
                                                                    ....          H. Doc. 382, 77th Cong., 1st sess.

1 Contains latest published maps of the Tombigbee River and tributaries.
2 Permanent Appropriation Repeal Act.
 = Contains maps of the Warrior River system. For maps of the Warrior and Black Warrior Rivers, see
Annual Reports for 1911, p. 1702, and 1918, p. 2144, respectively.



   Local cooperation. Fully complied with.
   Terminal facilities. Facilities comprising loading and transfer
stations, wharves, etc., have been provided where required along
this waterway. All are privately owned and operated except the
terminals at Tuscaloosa, which are leased to a private company
but serve the general public, and the terminals at miles 357.6 and
409.6 which are owned and operated by the Inland Waterways
Corporation, but also serve the general public. These terminals
are considered adequate for the existing commerce.
   Operationsduring fiscal year. New work performed during the
fiscal year was as follows:
   Warrior Lock and Dam: New work, hired labor: Preparation of
design plans and specifications was continued at a cost of $94,541.
   Demopolis Lock and Dam: New work: Contract: Relocations of
          RIVERS AND HARBORS-MOBILE, ALA., DISTRICT              441
roads, railroads, and utilities were continued at a cost of $185,917;
reservoir clearing was continued at a cost of $838,304; construc-
tion of lock, dam, and appurtenances, was continued at a cost of
$5,311,662; and excavation of lock approach channels was con-
tinued at a cost of $367,051. Adjustment of prior year costs for
buildings, grounds, and utilities resulted in a credit of $22,615.
Hired labor: Acquisition of lands and payment of damages was
continued at a cost of $613,106. Other materials and supplies
cost $1,100. The total cost for new work on Demopolis Lock and
Dam was $7,294,525.
   Maintenance: The U. S. pipeline dredge Guthrie, operating
in the Warrior and Tombigbee Rivers July 1 to October 27, 1953,
and April 23 to June 30, 1954, removed 1,898,728 cubic yards of
material; the U. S. pipeline dredge Josenhans, operating July 1
to 4, 1953, and June 1 to 26, 1954, removed 155,264 cubic yards of
material; the U. S. snagboat Denison, operating in the Warrior and
Tombigbee Rivers July 1 to December 23, 1953, February 1 to 20,
1954, and April 1 to June 30, 1954, removed 8,449 cubic yards of
silt from lock approaches and 8,623 obstructions from channels;
the U. S. snagboat Montgomery, operating October 6 to December
15, 1953, and January 11 to June 30, 1954, removed 2,220 cubic
yards of silt and 2,370 cords of drift from locks and approaches,
and 1,121 obstructions from channels; all at a cost of $390,634 for
dredging and $142,114 for removal of snags and obstructions. Re-
habilitation of locks and dams cost $275,527. Miscellaneous sur-
veys and investigations cost $15,822. .Operation and care of locks
and dams cost $294,851.
   The total cost for the fiscal year was $8,508,014, of which $7,-
389,066 was for new work, and $1,118,948 for maintenance, includ-
ing operation and care of locks and dams.
   Condition at end of fiscal year. The existing project was com-
menced in 1887. Eighteen locks and dams comprising 70 percent
of the original project have been built. Three of these (10, 11, and
12) have been removed and replaced by the Tuscaloosa lock and
dam. (See table under "Existing project.") The channel has
been dredged, original snagging completed, and principal lock
houses built at all locks. A dredged channel through Sunflower
Bend cutoff on the Tombigbee River was completed in 1938. Con-
struction of crest gates on dam 17, Black Warrior River, was com-
pleted in 1938. Construction of Tuscaloosa lock and dam was com-
pleted in 1940. A depth of 9 feet and a minimum width of 100 feet
obtained throughout the improvement, and all-year navigation is
possible within these dimensions, except at lock 1 where the depth
over the lower miter sill is 9 feet about 91 percent of the time with
a minimum depth of 6.9 feet at extreme low tide. The work re-
maining to be done to complete the project consists of completing
construction of a new lock and dam near Demopolis, Ala., to replace
existing dams 4, 5, 6, and 7; constructing a new lock and dam near
Jackson, Ala., to replace existing locks 1, 2, and 3; and constructing
a new lock and dam near Eutaw, Ala., to replace existing locks 8
and 9.
442               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   The costs for the existing project to June 30, 1954, were as
follows:
                                                                                                   Costs


                                                                   New work             Mainte-            Operating            Total
                                                                                        nance              and care


Regular funds.......----------------------------                    $32,020, 904    $7, 714, 520    $15, 540,002            $55, 275, 426
Public Works funds ...---------------------                              79,220 -------------------------                         79, 220
Emergency Relief funds--------------_ __                                607, 308 ................-------               --.. 607, 308
       Total...........-------------------------------32, 707, 432                        7, 714, 520       15, 540, 002      55, 961, 954



  In addition, the sum of $8,932,687 was expended between July 1,
1896, and June 30, 1935, on the operation and care of works of im-
provement under the provision of the permanent indefinite appro-
priation for such purposes.
                                               Cost and financial summary

                                                          Fiscal year ending June 30                                     Total to June
                                                                                                                        30, 1954, includ-
                                                                                                                        ing fiscal years
                                        1950             1951            1952             1953             1954          prior to 1950

New work:
   Appropriated.-                   $ 1, 000, 000   $2, 200,000      $2,900, 000      $4, 202, 000      $6, 088, 000         $33, 065,673
   Cost--- ------------                , 645,224        484, 158      2, 345, 721      5, 212, 402       7,389, 066           32, 707, 432
Maintenance:
     Appropriated .......            1, 062, 300        995, 940       1, 192, 398        954, 567       1, 007, 626          23, 263, 612
     Cost------------.---.           1, 001, 564        951, 588       1, 274, 897        905, 931       1, 118, 948          23, 254, 522


   1 Exclusive of $606,931 for new work and $50,000 for maintenance on previous projects.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954.......                                                                  $120, 036
    Appropriated for succeeding fiscal year ending June 30, 1955...........                                                      5, 240, 000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955.......................----------------------------.............................-----.....          ------ 5, 360, 036
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project..------.......................                                                 -------..... . 44, 965, 000
                                                                                                ----------................

                                          12. BILOXI HARBOR, MISS.
   Location. On Mississippi Sound in southeastern Mississippi.
It is 32 miles by water west of Pascagoula Harbor, Miss., and 14
miles east of Gulfport Harbor, Miss.                                            (See U. S. Coast and Geodetic
Survey Chart No. 1267.)
  Previous projects. Adopted by the River and Harbor Acts of
August 2, 1882, and July 5, 1884. For further details, see page
1846, Annual Report for 1915; page 863, Annual Report for 1929;
and page 744, Annual Report for 1938.
  Existing project. This provides for a channel west of Deer
Island 10 feet deep and 150 feet wide from the 10-foot contour in
Mississippi Sound to the south waterfront of the city of Biloxi, and
thence north of Deer Island to deep water in Back Bay of Biloxi, an
over-all length of about 7 miles; for maintaining the Coast Guard
channel to a depth of 6 feet and a width of 300 feet; and for main-
taining the existing channel along the northerly side of United
States Highway 90 bridge, from the main channel in Biloxi Harbor
to the entrance to Ott Bayou, to a depth of 6 feet, a width of 40
                RIVERS AND HARBORS-MOBILE, ALA., DISTRICT                                                            443
feet, and a length of about 1 mile. The project also provides for
an entrance channel 6 feet deep, 50 feet wide, and about 1,800 feet
long into Old Fort Bayou, and an entrance channel 8 feet deep, 100
feet wide, and about 1 mile long through Cranes Neck into Bayou
Bernard. Under ordinary conditions, the mean tidal range is about
1.8 feet.
   The estimate of cost for new work, approved in 1954, is $64,800,
exclusive of amounts expended on previous projects and exclusive
of $5,000 contributed by local interests. The latest (1954) ap-
proved estimate for annual cost of maintenance is $21,000.
   The existing project was authorized by the following River and
Harbor Acts:

    Acts                               Work authorized                                            Documents'
July 3, 1930    Present project dimensions, ---       --................           -... H. Doc. 754, 69th Cong. 2d sess.
June 20, 1938   Relocation of channel---------
                                     ................                      ..-..        H. Doc. 639, 75th Cong., 3d sess.
Mar. 2,1945     Entrance channel 6 feet deep and 50 feet wide into                    H. Doc. 258, 76th Cong., 1st sess.
                 Old Fort Bayou.
    Do.... -    Entrance channel 8 feet deep and 100 feet wide                        H. Doc. 326, 76th Cong., 1st sess.
                  through Cranes Neck into Bayou Bernard.
May 17, 1950    Maintain channel 6 feet deep and 40 feet wide from                    H. Doc. 256, 81st Cong., 1st sess.
                   Biloxi Harbor to Ott Bayou.

1 Contain latest published maps.

   Local cooperation. Fully complied with except for the work
authorized in accordance with House Document 258, 76th Congress,
1st session, and House Document 326, 76th Congress, 1st session,
which provide that local interests furnish, free of cost to the United
States, as and when required, lands, easements, and spoil disposal
areas for the initial work and for subsequent maintenance, and hold
and save the United States free from claims for damages resulting
from the work.
   For work authorized in accordance with House Document No.
256, 81st Congress, 1st session, local interests are required to fur-
nish assurances satisfactory to the Secretary of the Army that
they will (1) furnish, free of cost to the United States, all lands,
easements., and spoil disposal areas for maintenance, when and as
required; and (2) hold and save the United States free from
damage, including damage to oyster beds, resulting from the work.
   Terminal facilities. These consist of a number of light timber
wharves at Biloxi, owned by private parties but available to the
public. These are considered adequate for the existing commerce.
   Operations and results during fiscal year. The contractor's
pipeline dredge Tchefuncta operating in Biloxi Harbor, removed
240,805 cubic yards of material January 20 to 31, 1954, and 195,204
cubic yards of material February 1 to 9, 1954, at a cost of $43,248.
Miscellaneous investigations and surveys cost $1,310.
   The cost for the fiscal year was $44,558, charged to maintenance.
   Condition at end of fiscal year. The existing project, com-
menced in 1931, was about 77 percent completed. The controlling
depths in the channels at the times shown were as follows: Missis-
sippi Sound channel, 10 feet, February 1954; entrance to Old Fort
Bayou, 1.5 feet, August, 1938; Crane's Neck Channel, 8 feet, De-
cember 1950; and channel to Ott Bayou 6 feet, November 1952.
The work remaining to be done to complete the project consists of
444               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

dredging a channel 8 feet deep and 100 feet wide thru Crane's Neck
into Bayou Bernard, and dredging an entrance channel 6 feet deep
and 50 feet wide into Old Fort Bayou.
   The costs for the existing project to June 30, 1954, were as
follows:
                                                                                                        Costs

                                                                                       New work        Maintenance         Total


Regular funds .     ---------------------------------                                      $49,780           $368,541      $418,321
Contributed funds-_                       -                                                  5,000             10,200        15, 200
      Total      --------------------------------------------                               54,780              378,741     433, 521


                                                  Cost and financial summary

                                                                 Fiscal year ending June 30                          Total to June
                                                                                                                    30, 1954, includ-
                                                                                                                    ing fiscal years
                                          1950                  1951        1952          1953           1954         prior to 1950
New work:
    Appropriated-.-                  _       --------------------------                   ----------
                                                                                           _------------                     $49, 780
                                                                                                                             $------------
    Cost...----------.......------------...... ------------          -------------                 --------- -----------      49, 780
Maintenance:
   Appropriated--------........           $26, 000              $25, 730   -$2, 423        $7, 355       $44, 746            368, 807
   Cost-.................                  26, 000               22, 243      1, 065        7, 276        44, 558            368, 541


   The amounts shown in the "Total" column are exclusive of $44,382 for new work and $86,309 for main-
tenance for previous projects.
   In addition to the amounts shown in the "Total" column, $5,000 for new work and $10,200 for main-
tenance was expended from contributed funds.
Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project...__-........................ ...... ............ $15, 000

                                        13. GULFPORT HARBOR, MISS.
  Location. On Mississippi Sound in southeastern Mississippi,
about 44 and 90 miles by water west of Pascagoula Harbor, Miss.,
and Mobile Harbor, Ala., respectively, and 78 miles east of New
Orleans (via the Gulf Intracoastal Waterway). (See U. S. Coast
and Geodetic Survey Chart No. 1267.)
  Previous projects. Adopted by the River and Harbor Acts of
March 3, 1899 (H. Doc. 120, 55th Cong., 3d sess.) ; March 2, 1907;
February 27, 1911; and January 21, 1927. For further details, see
page 1846, Annual Report for 1915; page 857, Annual Report for
1929; and page 747, Annual Report for 1938.
  Existing project. This provides for a channel 32 feet deep,
300 feet wide, and about 8 miles long across Ship Island Bar, a
channel 30 feet deep, 220 feet wide and about 11 miles long
through Mississippi Sound, and a depth of 30 feet in the 1,320- by
2,640-foot anchorage basin at Gulfport. Under ordinary conditions
the mean tidal range is about 13/4 feet, and the extreme tidal range
about 31/2 feet.
   The project has been completed at a cost of $635,758 for new
work, exclusive of amounts expended on previous projects. The
latest (1954) approved estimate for annual cost of maintenance is
$270,000.
   The existing project was adopted by the River and Harbor Act
approved July 3, 1930 (H. Doc. 692, 69th Cong., 2d sess.), and the
                      RIVERS AND HARBORS-MOBILE, ALA., DISTRICT                                                                  445
River and Harbor Act approved June 30, 1948 (H. Doc. 112, 81st
Cong., 1st sess.). The latest published maps of this locality are in
the project documents.
   Local cooperation. None required.
   Terminal facilities. The modern rail-connected terminal facili-
ties at this port are considered adequate for existing commerce.
 (See Port Series No. 19, revised in 1949.)
   Operations and results during fiscal year. The U. S. Hopper
Dredge Langfitt removed 748,962 cubic yards of material in the
Ship Island Bar channel August 4 to 26, 1953 and the contractor's
pipeline dredge Diesel removed 2,678,088 cubic yards of material
in the Mississippi Sound Channel November 15 to December 27,
1953, at a cost of $216,638. Miscellaneous investigations and sur-
veys cost $6,523.
   The total cost was $223,161 charges to maintenance.
   Condition at end of fiscal year. The existing project was
commenced in 1932 and completed in April 1950. The controlling
depths in the channels at the times shown were as follows: Ship
Island Bar Channel, 32 feet, March 1954; Mississippi Sound Chan-
nel south end to beacon 60, 30.0 feet, January 1954; beacon 60 to
sound end of basin, 30 feet, January 1954; and anchorage basin, 30
feet, November 1953.
   The costs under the existing project to 30 June 1954, were as
follows:

                                                                                                            Costs

                                                                                        New work           Maintenance         Total

Regular funds------------------------------                                                 $587, 875         $3, 064,131   $3, 652, 006
Public works funds_ -----            -----------------        ---------                       47, 883                            47,883
       Total-----.......   ..----------------------      --------------------                    635,758       3,064,131      3,699,889


                                               Cost and financial summary

                                                          Fiscal year ending June 30                                    Total to June
                                                                    .....                                              30, 1954, includ-
                                                                                                                       ing fiscal years
                                       1950              1951                1952            1953           1954        prior to 19501

New work:
   Appropriated..------.                             -$40, 000 ..
                                              447 .$557,                                                                        635, 758
    Cost-----        ----------        517, 447 ----------------------------------------------                                  635, 758
Maintenance:
    Appropriated------- .....           79, 000          247, 655           $254, 400      $230, 589       $224, 373          3, 066, 716
    Cost-----...... .......---
                       ---             177, 394          212, 389            289, 654       229, 243        223, 161          3, 064, 131


  "Exclusive of $269,017 for new work and $2,312,292 for maintenance for previous projects.


                                 14. PEARL RIVER, MISS. AND LA.
   Location. Pearl River rises in east-central Mississippi and
flows southwest about 172 miles to Jackson, Miss., thence southeast
about 269 miles to the head of its delta, where it divides into West
Pearl and East Pearl Rivers. The former flows about 34 miles to
the Rigolets, a tidal pass connecting Lake Pontchartrain with Lake
Borgne, an arm of the Gulf of Mexico.
   Previous projects. Adopted by the acts of June 14, 1880, and
446              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

April 21, 1900. For further details, see page 950, Annual Report
for 1922, and page 750, Annual Report for 1938.
   Existing project. This provides for a channel from the mouth
of West Pearl River for 58 miles to the mouth of Bogalusa Creek
at Bogalusa, La., 7 feet deep at low water with a bottom width of
100 feet in the river sections and 80 feet in the canal section; with
locks 65 by 310 feet clear inside dimensions.
   The plan of improvement may be divided into three sections as
follows: River section from the mouth of West Pearl River to mile
28.5 at Holmes Bayou with a channel 7 feet deep and 100 feet wide,
to be obtained by dredging, snagging, and cutoffs at sharp bends;
the canal section from mile 28.5 to mile 48.7 at Pools Bluff with a
channel 7 feet deep and 80 feet wide, to be obtained by the con-
struction of 3 locks in the canal with sills across Bogue Chitto at
mile 44 and across the river at mile 48.7; river section from mile
48.7 to mile 58 at the mouth of Bogalusa Creek, to be obtained by
dredging, snagging, and easing of bends. At Bogalusa the mean
variation of the water surface is 10 feet and the extreme, 23 feet.
   The following table gives various features of the locks included
in the existing project:
                      Lock                                        1                         2                      3


Miles above mouth--.....-----------------. 29.4_-------------                     40.7__-------------   43.9.
Nearest town.......------------------------ Pearl River, La_-. Bush, La.....--..------                  Sun, La.
Miles to nearest town--......---------------- 9--------------- 3--------------                          2.
Greatest length available for full width             310     .....-------------   310-------------      310.
  (feet).
Width of chamber (feet)---------------   65--------------                         65--------------      65.
Lift (feet)-..--  -----------------------26.7------------                         15.0__-------------   11.0.
Depth over sills at low water (feet)         ---     10 .......--------------     10--------------      10.
Character of foundation .             ..--------------.Sand, gravel, silt,        Sand, gravel, silt,   Sand, gravel, silt,
                                                       clay.                        clay.                 cl ay.
                    . -.-.-------.-.--
Type of construction----                           . Concrete and steel_ Concrete and steel. Concrete and steel.
Year completed----           ..---------------------- 1949-----------             1950------------.. 1950.
Date opened to navigation-------------                Nov. 1953-...--...          Nov. 1953            Nov. 1953.
Actual cost of lock..-------------------$2,119,110.22-.....                       $1,967,537.20 .....- $1,497. 539.37.



   The estimated cost of new work (1954) is $8,274,800, exclusive
of amounts expended on previous projects. The latest (1954) ap-
proved estimate of annual cost of maintenance is $150,000 includ-
ing operation and care.
  The existing project was adopted by the River and Harbor Act
of August 30, 1935, subject to the approval of the Board of Engi-
neers. This approval is contained in House Document No. 408,
Seventy-fifth Congress, second session, which document contains
the latest published map.
  Local cooperation. Fully complied with. Local interests are
required to furnish all flowage and dumping easements needed for
subsequent maintenance of the improvement, and to assume full
responsibility for all property damage incident to the maintenance
of the canal. (See H. Doc. 408, 75th Cong., 2d sess.)
   Terminal facilities. A privately owned wharf at the Pearl
River highway bridge near Pearl River Station, La., is used for
unloading logs. No other facilities exist except natural landings
at various locations on the river. These facilities are considered
adequate for existing commerce.
  Operations and results during fiscal year. New work:                                                                 Hired
                   RIVERS AND HARBORS-MOBILE, ALA., DISTRICT                                                                    447
labor: U. S. draglines No. 1 and No. 2 removed 82,150 cubic yards
of material in the lateral canal July 1 to 31, 1953; U. S. pipeline
dredge Josenhans removed 405,903 cubic yards of material in
Pearl River July 9 to October 31, 1953, and U. S. dragline No. 1
placed 12 cubic yards of gravel and 75 tons of riprap at the lower
wall of lock 1 at a total cost of $57,901. The U. S. draglines No. 1
and No. 2 removed obstructions in Pearl River between mile 48
and mile 58 from August 1 to October 31, 1953, at a cost of $53,954.
   Contract: Construction of Bogue Chitto and Pools Bluff sills was
completed Dec. 3, 1953, at a cost of $7,891. Preparatory work for
installation of motorized lock gate and valve machinery cost $1,478.
Preparatory work for construction of three additional lockkeepers'
houses cost $1,897.
   Maintenance: U. S. draglines No. 1 and No. 2 removed obstruc-
tions in Pearl River between mile 8 and mile 29 from November 1
to December 10, 1953 at a cost of $14,182. U. S. dragline No. 1
removed 576 obstructions from Pearl River June 14 to 25, 1954, at
a cost of $4,266. The U. S. pipeline dredge Josenhans operating in
Pearl River November 1 to 23, 1953, and June 29 to 30, 1954, re-
moved 80,110 cubic yards of material at a cost of $56,233. Re-
habilitation of locks and dams cost $5,894. Miscellaneous investi-
gations and surveys cost $8,211.
   Operating and care: Ordinary maintenance, repairs and im-
provement of the three locks cost $13,712.
   The total cost was $225,619, of which $123,121 was for new work
and $102,498 for maintenance including operation and care.
   Condition at end of fiscal year. The existing project, com-
menced in October 1938, was about 99 percent completed. Lock
No. 1 was completed in February 1949, lock 2 in June 1950, and
lock 3 in May 1950. Channel depths and widths as called for in
the plan of improvement prevail throughout the existing project.
The work remaining to be done to complete the project consists of
constructing one additional lockkeepers' house at each lock and
motorization of gate and valve operating machinery at locks 1, 2,
and 3.
   The cost of the existing project to June 30, 1954, was $8,311,160,
of which $8,176,286 was for new work and $134,874 for mainte-
nance, including operation and care.
                                              Cost and financial summary

                                                         Fiscal year ending June 30                                   Total to June
                                                                                                                     30, 1954, includ-
                                                                                                                     ing fiscal years
                                       1950            1951           1952               1953             1954         prior to 19501

New work:
      Appropriated-        -__..   $2, 009, 000 ------------        $978, 000 ------------------------                      8, 274, 777
      Cost--_-----------      --    2, 231,117           $30, 743     75, 448        $685,619            $123, 121          8,176, 286
Maintenance:
      Appropriated-----------------..                    15, 789        8, 000            11, 300         100, 900            135, 989
      Cost ---------------------------                   13, 266        6, 384            12, 726         102, 498            134, 874


  1   Exclusive of $144,443.31 for new work and $168,171.64 for maintenance for previous projects.

Other new work data:
    ITnobligated balance, fiscal year ending June 30, 1954....... .............                        . $75,013
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955......... ...........-................
                                     ..............................-................................... 75, 013
                                  .....


           Sig 15-447-478
448                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                          15.   INACTIVE               NAVIGATION              PROJECTS

                                                              For last       Cost to June 30, 1954               Estimated
                                                             full report                                          amount
                      Name of project                           see                                               required
                                                              annual          Con-           Operation               to
                                                               report      struction            and               complete
                                                               for-                         maintenance


  1. Apalachicola Bay, Fla ___________________..
                                          .      .             1953            $216, 758        10$781, 729              (1)
2. Bayou Coden, Ala...._______________
                              2                   ____...      1950                650                                    3$4,    000
3. Bayou Galere, Miss.                     .. .....           1946                                                            8, 900
4. Bayou La Batre, Ala 4-----------------------               1951            21, 052              113,167                  '88, 900
5. Blackwater River, Ala.                        -            1949            41, 650              106, 759          (1)
6. Bluff Creek, Miss.' s -......................              1893             1, 000                                (1)
7. Cahaba River, Ala.' 5 ..................
                                 -
                                            4                  1894            46, 000                                (6)
8. C arrab elle B a r and2 H arb o r, Fla . .-. .... ....     1950           363, 686              275, 535          (1)
9. Chitto Bogue, La. " ................... 4 .....            1909            14, 913               12, 930         3   185, 100
1.0 Choctawhatchee River, Fla. and Ala. _ __..                 1949           171, 885              266, 445          (1)
11. Dauphin Island Bay, Ala............ ______                 1950                                                   3 131,
                                                                                                                           000
12. East Pearl River, Miss.'....................               1951            37, 128               59, 325          (1)
13. Escambia and Conecuh Rivers, Fla. and Ala_                 1951           118, 336              110, 700          (1)
14. Fly Creek, Fairhope, Ala....................               1950                                                      3   14, 000
15. Harrison County, Miss., shore protection                   1953         1,133, 000                                (1)
      project.              2
16. Holmes River, Fla. '.......______ ...........              1931              8, 562              36, 800          (1)
17. La Grange Bayou, Fla__                   .                 1951             64, 151              43, 546         8 103,800
18. Leaf and Chickasawhay Rivers, Miss.2 55          ..        1919             23,090               42, 676          S126, 900
19. Noxubee River Miss 8.................                      1902             47, 528              14, 472          (1)
20. Ochlockonee (Ochlockney) River, Ga. and                    1900              5, 000                                      95, 000
        Fla.'   s
21.   Old Town Creek, Miss. s                                  1887             3, 000                                   $ 30, 000
22.   Oostanaula and Coosawattee Rivers, Ga.2 5__              1907            32, 656                               $ 177,      300
23.   Panama City Harbor, Fla__...............                 1953           890, 577        112, 095, 588           (1)

24.   Pascagoula Harbor Miss_____________                      1953           258,040         1, 520, 033                S44,000
25.   Pascagoula River, Kiss____________...
                                   4      _                    1953                              158, 855              (9)
26.   Pass Christian Harbor, Miss.          -.2                1947              1, 100 -----------------------------------
                                                                                                  36,9---                  23,000
27.   Pearl River, Miss., Edinburg to Jackson. 7 __            1911             31, 872           36, 991              S218,  000
28.   Pensacola Harbor, Fla................... __              1953         1, 095, 523    12 1, 451, 598                500, 800
29.   Port St. Joe Harbor, Fla ________________....            1953            579, 989       1s 397, 186               (1)
30. St. Marks River, Fla        _______________....
                                 ....                          1951            229, 742             6, 792
31. Tallapoosa River, Ala.,. 5__  _                            1893             43, 972
32. Upper Chipola River, Fla. from Marianna_                   1941             36, 781           63,193              s113, 200
       to its mouth. 5
33. Waterway connecting the Tombigbee &                        1953           713, 704...........               3 226, 340, 000
     Tennessee Rivers, Ala. and Miss.
34. Wolf and Jordan Rivers, Miss.'_...........                 1951             29, 195             82, 391           (1)




   1 Completed.
   2 No commerce reported.
    S1954 estimate.
   4 Channel adequate for commerce.
   s Abandonment recommended in H. Doc. 467, 69th Cong., 1st sess.
   6 Considered completed.
   7 Considered unworthy of further improvement.
   8 That portion of the Noxubee River in Noxubee County, Miss., was declared non-navigable on Feb. 24,

       19, Act S. 2337, 73rd Cong., 2d sess. (48 Stat. 356).
   9 Project provides for maintenance only.
  to Expended for general supervision during fiscal year, $1,115.
  11 Expended for general supervision during fiscal year, $3,132.
  12 Expended for general supervision during fiscal year, $4,020.
  15Expended for general supervision during fiscal year, $4,620.


                    16. WEST POINT,                   CHATTAHOOCHEE                    RIVER, GA.

   Location. The project is located on the Chattahoochee River at
West Point, Ga.
   Existing project. The project as originally authorized covered
the section of the river from the city of West Point to Langdale
Dam, a distance of about 7 miles, and consisted of increasing the
cross section of the Chattahoochee River at critical points, clearing
the floodway on both banks, constructing an earth levee 1,500 feet
long, and the construction of an additional span in the highway
bridge at West Point. The work was authorized by the President
under the provisions of the Emergency Relief Appropriation Act
                      FLOOD CONTROL-MOBILE, ALA., DISTRICT                                                  449
of April 8, 1935. This work, which was commenced in 1935, was
completed in 1937 at a total cost of $591,068, all from Emergency
Relief funds. (See Chattahoochee River, Ga., Flood Control, page
655 in Annual Report for 1937.) In September 1953 an allotment
of $14,000 was made from the appropriation for construction of
local flood protection projects to provide for replacement of the flap
gate outlet by a slide gate outlet through the levee at West Point.
The estimated cost of the project, revised in 1954, is $605,068, in-
cluding the cost of work completed in 1937.
   Local cooperation. Fully complied with.
   Operations and results during fiscal year. Engineering and de-
sign studies of the outlet gate were completed and a contract was
awarded for the construction thereof. The total cost was $1,094
for new work.
   Condition at end of fiscal year. The work remaining to be ac-
complished consists of the replacement of the existing flap gate
outlet by a slide gate outlet. All work preparatory to actual con-
struction of the slide gate has been completed. The total cost of
the project to June 30, 1954, was $592,162, of which $591,068 was
from Emergency Relief funds applied on works completed in 1937.
                                         Cost and financial summary

                                                       Fiscal year ending June 30                  Total to June
                                                                                                  30, 1954, includ-
                                                                                                  ing fiscal years
                                  1950               1951                1952   1953   1954        prior to 19501
New work:
   Appropriated        ---...........                         ------------             $14, 000           $605, 068
   Cost...---------    ----------------------------------------------                    1,094             592, 162

  1 Include $591,068 from Emergency Relief funds, applied on works completed in 1937.

Other new work data:
                                                                           ...$6,086
    Unobligated balance, fiscal year ending June 30, 1954-...........................
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955........................................-------------------------.   6,086

      17. ALLATOONA                   RESERVOIR, COOSA                          RIVER BASIN,          GA.
   Location. Allatoona Dam is on the Etowah River in fBartow
County, Ga., about 48 miles upstream from Rome, Ga., about 5
miles due east of Cartersville, Ga., and about 2,000 feet downstream
from the mouth of Allatoona Creek. The reservoir extends about
27 miles up the Etowah River at maximum-power-pool elevation
of 835 feet above mean sea level.
   Existing project. This provides for a dam and reservoir for
flood control, regulation of streamflow for navigation, and develop-
ment of hydroelectric power. The height above river bottom of
the concrete gravity-type dam is about 190 feet, from elevation 690
feet to 880 feet above mean sea level. The spillway, with crest at
elevation 835, is controlled by nine Tainter gates, 40 feet wide by
25 feet high, and two Tainter gates 20 feet wide by 25 feet high; it
has a discharge capacity of 318,500 cubic feet per second with wa-
ter surface at elevation 870.1. One 48-inch diameter sluicing con-
duit with free discharge valve, and four sluices 5 feet 8 inches wide
by 10 feet high, are included in the dam. The reservoir, covering
450      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  19,700 acres at elevation 860, has a storage capacity of 722,000
acre-feet. The estimated cost (1954) is $31,320,700. The latest
  (1954) estimate for annual cost of operation and maintenance is
 $277,000. This project was authorized by the Flood Control Acts
of August 18, 1941, and on December 22, 1944 (Public Law 228,
77th Cong., 1st sess.), as outlined in House Document 674, 76th
Congress, 3d session,
    Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
    Operations and results during fiscal year. New work, hired
labor: Lands and damages cost $2,219; continued construction of
recreation facilities cost $21,460; cost incidental to reservoir and
pool preparation was $529; installation of flood reporting network
and permanent operating equipment cost $16,135; construction
materials and equipment cost $1,033; and engineering and design
cost $9,967.
    Operation and maintenance: Operation and ordinary mainte-
nance of dam, reservoir, powerhouse, service facilities and recre-
ation facilities, and supervision and administration incidental
thereto, cost $210,211. Improvement and replacement of appur-
tenances to dam and powerhouse cost $10,411.
    The net total cost for the fiscal year was $271,965, of which
 $51,343 was for new work and $220,622 for operation and main-
tenance.
    Heavy rains in the headwater area during January 1954 caused
an 18-foot rise in the pool elevation, impounding about 166,000
acre-feet, of which 30,000 acre-feet was in flood control storage.
Natural stages at Rome, Ga., and Gadsden, Ala., were reduced
about 4 feet and 2 feet respectively, and corresponding reductions
in flood losses were estimated at $427,000, of which $161,000 were
urban.
    Condition at end of fiscal year. The existing project, com-
menced in March 1944, is practically completed. Major construc-
tion was completed and the last unit placed on the line in May
1950. Work remaining to be done consists of work in connection
with settlement of claims and damages, completion of recreational
facilities, completion of flood reporting network, and installation
of remote control operating equipment for dam and reservoir.
    The total cost under the existing project to June 30, 1954, was
$31,991,951, of which $31,120,383 was for new work and $871,568
for operation and maintenance.
                            FLOOD CONTROL-MOBILE, ALA., DISTRICT                                                               451

                                              Cost and financial summary

                                                        Fiscal year ending June 30                                  Total to June
                                                                                                                   30, 1954, includ-
                                                                                                                   ing fiscal years
                                       1950            1951            1952            1953            1954          prior to 1950

New work:
   Appropriated-.......            $6, 750, 000         -          -$133, 300      -$135, 065       -$79, 978           $31, 174, 977
   Cost---.------  --               5, 152, 979   $1, 210, 292        322, 770        330, 942          51, 343         131, 120, 383
Maintenance:
                   ---------
     Appropriated-........                            223, 600        194, 250        235, 000        241, 960               894, 810
               ..
     Cost..------.      ----------                    205, 075        205, 084        237, 218        220, 622               871, 568


   1Reflects $134,931 undistributed credit carried forward from prior fiscal year and which was not included
in prior years operation.
   2 Reflects $3,570 undistributed cost carried forward from prior fiscal year and which was not included in
prior years operation.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954.-----... .---------..............                                $46, 768
    Appropriated for succeeding fiscal year ending June 30, 1955:-----..........--..... 22, 000
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955 ..-----------------------------------------------                                                                 68, 768
    Estimated additional amount needed to be appropriated for completion
                                                                                                                           124,000
      of existing project ...........-----------.................... ...........................................---------------------------...

                                     18. ROME, COOSA RIVER, GA.
   Location. The project is located on the Coosa River, Ga., near
Rome, Ga.
   Existing project. The plan of improvement provides for the
construction of a system of levees and concrete flood walls consist-
ing of the following features: About 6,000 feet of earth levee and
546 feet of concrete flood wall along the right bank of the Oosta-
naula River, and about 3,000 feet of earth levee along the right
bank of the Coosa River; two pumping stations for the disposal
of the runoff and sewage from within the protected area during
periods of high water; two stoplog openings, equipped with stop-
logs and storage houses, to prevent overtopping of the levee in the
event of a flood of greater magnitude than the maximum on record.
The project provides for the protection of the fourth ward of the
city of Rome, Ga., against a flood of the magnitude of the maximum
flood on record, which occurred in 1886. The existing project was
authorized by the Flood Control Act approved June 22, 1936. This
work was completed in 1940 at a total cost of $366,213, of which
$273,152 was from regular funds, and $93,061 was from Emer-
gency Relief funds. In September 1953 an allotment of $25,000
was made from the appropriation for construction of local flood
protection projects to provide for modification of the existing out-
lets through the levee at Rome, Ga. The estimated cost of the
project, revised in 1954, is $392,640, including the cost of work
completed in 1940.
   Local cooperation. Fully complied with.
   Operations during fiscal year. Engineering and design studies
of the outlet works were completed and a contract was awarded
for the construction thereof. The total cost was $2,978 for new
work.
   Condition at end of fiscal year. The work remaining to be
accomplished consists of modification of the existing outlet works.
All work preparatory to actual construction has been completed.
452          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

The total cost of the project to June 30, 1954, was $370,618, in-
cluding $93,061 from Emergency Relief funds and $277,557 from
regular funds applied on works completed in 1940.
                                        Cost and financial summary

                                                  Fiscal year ending June 30                                          Total to June
                                                                                                                     30, 1954, includ-
                                                                                                                     ing fiscal years
                                1950            1951                  1952         1953              1954              prior to 1950
New work:
   Appropriated...      ---------                                                                    $25, 000                $392, 640
   Cost .--------         -----------     -----------------------------------                          2,978                  370, 618

  1Includes $93,061 from Emergency Relief funds, applied on works completed in 1940.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954----...---...............----          $8,932
    Unobligated balances available for succeeding fiscal year ending June 30,
       1955-----..   .......         ............-----------------------------------------.....  8,932

                19.   INACTIVE              FLOOD                   CONTROL             PROJECTS

                                                                For last         Cost to June 30, 1954                  Estimated
                                                               full report                                               amount
                Name of project                                     see                                                  required
                                                                annual             Con-          Operation                  to
                                                                 report         struction           and                  complete
                                                                 for-                           maintenance
1. Tombigbee River, Miss., and Ala-------------                    1941           $134, 801 ......------------....       $15, 981, 000
2. Prattville, Autauga Creek, Ala.-----___                 -       1946            649, 280                                  (1)
3. Collinsville, Ala-------------------------...........................
                                                 1940               71, 119 _----------_-                                    (4)
4. Pearl River, Miss. and La., at Jackson, Miss. 1937--------------------------         _                                     560,000
i Completed.
  11954 estimate.
2 Now included in comprehensive plan.
   Completed with funds appropriated for the maintenance and improvement of river and harbor works.
   No funds have been allotted and no work has been done on this project.

                           20. GENERAL INVESTIGATIONS
   Examinations and surveys. The cost during the fiscal year was
$35,491, of which $7,154 was for navigation studies, $22,304 for
flood control studies, $1,466 for cooperative beach erosion studies,
and $4,567 for miscellaneous studies. The unexpended balance of
$1,243 will be applied toward the completion of studies in progress.
An additional allotment of $119,800 could be profitably expended
during fiscal year 1955, of which $39,500 would be applied on navi-
gation studies, $48,000 on flood control studies, and $32,300 on
miscellaneous studies.
   Collection and study of basic data. The collection and study of
basic data during the fiscal year consisted of stream measurements
and the preparation of stage hydrographs at nine stations on tribu-
taries of the Mobile River system. The cost during the fiscal year
was $4,567.
    21. INSPECTION OF COMPLETED FLOOD CONTROL WORKS
  The local flood protection works for which inspection is per-
formed under this heading consist of levee projects at West Point,
Ga., on the Chattahoochee River; Elba and Geneva, Ala., in the
Choctawhatchee River basin; and Rome, Ga., Collinsville, Ala., and
                                FLOOD CONTROL--MOBILE, ALA., DISTRICT                                                 453
Prattville, Ala., in the Alabama-Coosa River basin. The projects at
Rome, Ga., and Collinsville, Ala., include pumping stations.
  Inspections were made during the fiscal year to determine the
extent of compliance with approved regulations for maintenance
and operation of the several projects. Responsible local officials
were advised of inadequacies in the maintenance and operation of
the local flood protection works under this jurisdiction where ap-
propriate.
  No costs were charged under this heading during the fiscal year.
  The total cost to June 30, 1954, was $400, charged to mainte-
nance.
                                                  Cost and financial summary

                                                         Fiscal year ending June 30                         Total to June
                                                                                                           30,1954, includ-
                                                                                                           ing fiscal years
                                          1950-        1951            1952        1953        1954          prior to 1950

Maintenance:
    Appropriated --------------------                     $400      ------------------------------------                $400
    cost   ----------------------------                       400   ------------------------------------                400



22. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION

   Snagging and clearing of navigable streams and tributaries in
the interests of Flood Control. (Section 13 of the 1946 Flood
Control Acts)
   The contractor cleared 30 acres and applied the aboricide treat-
ment during July and August 1953 to 170 acres of trees and under-
growth in the flood plain of the Chattahoochee River in the vicinity
of West Point, Ga. A hired labor crew cleared and treated 3 acres
of trees and stumps on an island in the river during February 1954.
The cost was $11,111, charged to new work.
   Snagging and clearing operations on the Chattahoochee River
in the vicinity of West Point, Ga., were commenced in 1948, and
have been carried on intermittently since. Other work under this
authority has been performed at various localities since 1939. The
total cost for work performed to June 30, 1954, under this author-
ity was $84,370 for new work.
                                                  Cost and financial summary

                                                        Fiscal year ending June 30                          Total to June
                                                                                                           30, 1954, includ-
                                                                                                           ing fiscal years
                                          1950         1951            1952        1953        1954        prior to 19501
New work:
   Appropriated                           $15, 500     $35, 000      -$7, 200      $26, 530       $500             $84, 370
   Cost-                                   40, 303      12, 320         27, 456     17, 719     11, 111             84, 370

  1 Exclusive of $245,981 for new work on previous projects.


  Small Flood Control Projects not specifically authorized by
Congress. (Section 212 of the 1950 Flood Control Act)
  Montezuma, Ga.: Work in connection with a project report cost
$4,000, charged to new work.
  Sowashee Creek, Meridian, Miss.: Plans and specifications were
454            REPORT OF CHIEF OF ENGINEERS, U. 8. ARMY, 1954

completed, and a contract for proposed work was awarded. The
cost was $3,066, charged to new work.
  Gordon Creek, Hattiesburg, Miss.: The project report was com-
pleted and plans and specifications were commenced at a cost of
$4,111, charged to new work.
  The total cost for new work under this authority was $11,177.
  The project report on Montezuma, Ga., was nearing completion.
All preliminary work preparatory to actual construction on So-
washee Creek has been completed. Plans and specifications for the
Gordon Creek project were well advanced. The total cost to June
30, 1954 for work performed under authority of section 212 of the
Flood Control Act approved May 17, 1950, was $157,658 for new
work.
                                       Cost and financial summary

                                               Fiscal year ending June 30                    Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                                1950         1951         1952        1953       1954         priorto 1950
New work:
   Appropriated------......--..----------
                                     .      $133, 000    $145, 500     -$612     $80, 000           $357, 888
   Cost_ .    _____ ..-----......--    ...-
                                          .   56, 306      70, 125     20, 050    11, 177            157, 658


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-.... .------------- $..107,347
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955..................................................................     107, 347
   IMPROVEMENT OF RIVERS AND HARBORS IN THE
           NEW ORLEANS, LA., DISTRICT
    This district comprises a portion of the State of Louisiana, in-
cluding the drainage area of the Red River south of Fulton, Ark.,
in Arkansas and Texas, embraced in the drainage basins tributary
to the Mississippi River and the Gulf of Mexico, except the Missis-
sippi River above mile 320 above Head of Passes, the drainage area
of the Ouachita-Black River Basin, and small eastern and western
portions of Louisiana tributary to Pearl River and Sabine River
and Lake.
    The district boundary extends in a northerly and westerly direc-
tion from the Gulf of Mexico along the easterly and northerly wa-
tershed line of the Sabine River and Lake to include the right-bank
tributaries of the Red River south of Fulton, Ark., in the States of
Arkansas and Texas, and the south bank levees immediately above
Fulton, Ark., in Miller County, Ark., and Bowie County, Tex.,
crossing the Red River at Fulton, Ark., thence north-northeast to
vicinity of Nashville, Ark., generally southeast along the divide be-
tween the Red and Ouachita-Black River watersheds to the con-
fluence of the Black and Red Rivers near Acme, La., eastward along
the north bank of the Red River; across Bayou Cocodrie at its con-
fluence with the Red River; southeast from Bayou Cocodrie to the
south end of the Shaw levee enlargement at levee station 7510;
due east to the thalweg of the Mississippi River (approximately
mile 318.0' AHP); along the thalweg of the Mississippi River to
mile 320 AHP; due east to the top of the east bank of the Missis-
sippi River; along the top of the east bank of the Mississippi River
to approximately mile 310 AHP; thence generally northeast along
the divide between the Buffalo-Homochitto and Amite River water-
sheds to the dividing line between the Lower Mississippi Valley and
South Atlantic Divisions near Bogue Chitto, Miss.; thence, along
that line and the westerly watershed line of the Pearl River Basin
to the north bank of the Rigolets; thence, along the north bank of
the Rigolets to Long Point Light; thence, following a line bearing
true south crossing the Intracoastal Waterway to Lake Borgne
Light No. 41; thence, generally easterly to a point 1 mile due south
of the southerly point of Grand Island; thence, to a point 1 mile
due. north of the northeasterly tip of the Isle au Pitre group of
islands; thence, to a point 1 mile due north of the northerly point
of the Chandeleur Islands; and thence, following a line bearing S.
500 E. into the Gulf of Mexico.
   It includes the sections of the Intracoastal Waterway from
Lake Borgne Light No. 41 to the Sabine River, and the Passes of
the Mississippi River. It exercises jurisdiction over flood control
work on the Mississippi River from mile 320 AHP to the Gulf of
Mexico; on the Red River including its south bank levees and
tributaries from Index, Tex., to its junction with Old River and the
Atchafalaya River; the Atchafalaya River; and in the Atchafalaya
Basin; and maintenance of the project navigation channel of the

                                                            455
456             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Mississippi River below mile 320 AHP, under the supervision of
the president, Mississippi River Commission, and the division
engineer, Lower Mississippi Valley Division. (For reports on
projects under Mississippi River Commission, see vol. 2 of this
report.)
                                                IMPROVEMENTS

                      Navigation                                      Flood Control-Continued
                                                     Page                                                    Page
1. Red River below Fulton, Ark__                    456 14. Texarkana Reservoir, Tex. .....                 498
2. Gulf Intracoastal Waterway                           15. Ferrells Bridge Reservoir, Tex__                500
      between Apalachee Bay, Fla.,                       16. Red River below Denison Dam,
      and the Mexican Border(New                               levees and bank stabilization
      Orleans district)......             ........   458        (New Orleans district)....                   501
3. Intracoastal Waterway, from                          17. Bayou Bodcau Reservoir, La ..                   503
      the Mississippi River to                           18. Wallace Lake Reservoir, La..                    505
      Bayou Teehe, La .........                      469 19. Bayou Pierre, La........ .. _.......            506
4. The Inland Waterway from                             20. Natchitoches Parish, La....                     507
      Franklin to the Mermentau                          21. Aloha-Rigolette Area, Grant
                                             ..
      River, La..................... .........       471       and Rapides Parishes, La....                  509
5. Mississippi River, Baton Rouge                       22. Bayou Teche and Vermilion
      to the Gulf of Mexico, La......                473       River, La.. .            -................ .. 510
6. Waterway from Empire, La., to                        23. Mermentau River, La ..............              513
      the Gulf of Mexico ................            482 24. Snagging and clearing under
7. Bayou Lafourche, La.......                       483       authority of sec. 2 of the
8. Bayou Teche, La......              ....          485       Flood Control Act approved
9. Mermentau          River,          Bayou                   August 28, 1937, as amended                   516
      Nezpique, and Bayou des                            25. Small flood control projects
      Cannes, La ...........................         488       under authority of sec. 205
10. Calcasieu River and Pass, La....                 490       of the Flood Control Act ap-
11. Removing the Water Hyacinth                                proved June 30, 1948, as
       (Louisiana) ... .....         ............    493                                                     518
                                                               amended ......................--------------------------.....
12. Inactive navigation projects......               495 26. Inactive flood control projects..               519
                                                         27. General investigations ..............           519
                    Flood Control                        28. Inspection of completed pro-
                                                               jects ............. ....................      520
13. Red River below Denison Dam,                         29. Flood control work under special
     New Orleans district.............               496                                                     520
                                                               authorization .........--------------------.........

                          1. RED RIVER BELOW FULTON, ARK.
   Location. Red River rises in the arid regions of eastern New
Mexico, flows in a general easterly and southeasterly direction for
1,300 miles, and enters the Mississippi River at Red River Landing,
La. (See U. S. Geological Survey State maps and Mississippi River
Commission alluvial valley quadrangle maps.)
   Previous projects. Authorized by River and Harbor Acts of
May 23, 1828; June 10, 1872; June 18, 1878; March 3, 1879; August
2, 1882; July 5, 1884; August 11, 1888; and September 19, 1890.
For further details, see page 1868 of Annual Report for 1915, and
page 895 of Annual Report for 1938.
   Existing project. This provides for continuing improvement of
Red River from Fulton, Ark., to the Atchafalaya River, La., 455.6
miles by systematic clearing of the banks, snagging, dredging
shoals, building levees (either alone or in cooperation with riparian
States), closing outlets, revetting caving banks, and preventing
injurious cutoffs. The lower end of this project is at Old River,
7.6 miles west of the Mississippi River. No proposed channel di-
mensions are given. The lower 28 miles of this project are a part
of the connecting link between the Ouachita and Black Rivers
             RIVERS AND HARBORS-NEW ORLEANS, LA., DISTRICT                                               457
navigation project and the Mississippi River, a distance of about
35 miles.
   Floods ordinarily cause fluctuations of stage between high and
low water of from 30 to 45 feet. Unusual floods occasionally in-
crease this range about 10 feet. The flood of March-April 1945
produced crest stages 1 to 3 feet higher than maximum previously
recorded.
   As the work is continuing, no estimate for completion was made.
The latest (1941) approved estimate for annual cost of mainte-
nance is $27,000.
   The existing project was authorized by the River and Harbor
Act of July 13, 1892 (Annual Reports for 1890, p. 1829, and for
1891, p. 1957), and modified by the River and Harbor Act of July
24, 1946, to authorize construction of the Overton-Red River water-
way to Shreveport, La., and provide a channel 9 feet deep and 100
feet wide from the Mississippi River to the north bank of Black
River (mile 35.5). (For latest published maps, see H. Doc. No.
378, 74th Cong., 2d sess.)
   Local cooperation. None required.
   Terminal facilities. None.
   Operations and results during fiscal year. Hired labor forces
conducted dredging surveys at a cost of $1,641, and the U. S.
dredge Todd, under the jurisdiction of the Vicksburg District, CE,
removed approximately 47,112 cubic yards of shoaled material
from Red River between mile 31 and the mouth of Black River
during the period September 23 to 26, 1953, at a cost of $10,298,
or a total cost of $11,939 for maintenance during the fiscal year.
   Condition at end of fiscal year. Maintenance in recent years
provides for navigation to Shreveport, La., at medium and high
stages. The head of navigation is the Arkansas-Oklahoma State
line, to which point boats may occasionally run during high water
if snags, overhanging trees, or similar obstructions do not inter-
fere. From January to July the prevailing stage is 6 feet and over,
and controlling depths are about 4 feet to Fulton, 5 feet to Shreve-
port, and 6 feet to Alexandria. During the remainder of the year
stages near zero may be expected, with controlling depths less than
1 foot from Fulton to Shreveport, 1 to 2 feet from Shreveport to
Alexandria, 4 feet from Alexandria to mouth of Black River, and
6.5 feet thence to mouth.
   Total costs under the existing project to the end of the fiscal year
were $409,929 for new work and $1,837,620 for maintenance, a
total of $2,247,548.
                                        Cost and financial summary

                                               Fiscal year ending June 30                    Total to June
                                                                                            30, 1954, includ-

                                 1950         1951         1952       1953        1954
                                                                                            ing fiscal years
                                                                                              prior to 19501
New work:
   Appropriated-- ---------------------- ------------------------------------
                                              -                                                  $1, 963, 806
   Cost-----            -------- -------------------------------------------            -----     1, 963, 806
Maintenance:
   Appropriated..-------_     $55, 500 -$5, 045 ..------------          $50, 000 $14, 000          1, 839, 680
    Cost---------------          51, 065 ---------------------         50, 000    11, 939          1,837, 620

  1Includes $1,553,878   for new work for previous projects.
458      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

2. GULF INTRACOASTAL WATERWAY BETWEEN APALACHEE BAY,
   FLA., AND THE MEXICAN BORDER (NEW ORLEANS DISTRICT)
    Location. The section of the Gulf Intracoastal Waterway within
the New Orleans District extends from Lake Borgne Light No. 41,
near the mouth of the Rigolets, to the Sabine River, La., and Tex.
    The section from Lake Borgne Light No. 41 to the Mississippi
River follows the Rigolets and Lake Pontchartrain to the lake end
of the State-owned Inner Harbor Navigation Canal, thence by way
of this canal to the Mississippi River, a distance of 40.5 miles. By
Public Law No. 675, 77th Congress, approved July 23, 1942, the
project was modified to provide for a land cut through the marsh
from the Rigolets to a point on the Inner Harbor Navigation Canal
about 2.25 miles from the Mississippi River, eliminating passage
through Lake Pontchartrain and five drawbridges, a distance of
30.8 miles to the Mississippi River by this route. From the Inner
Harbor Navigation Canal to the entrance to Harvey lock, the route
follows the Mississippi River for a distance of 5.5 miles.
    The section from the Mississippi River to Atchafalaya River, La.,
leaves the Mississippi River through Harvey lock about 3.3 miles
above Canal Street and follows Harvey Canal No. 1 and Bayou
Barataria to Bayou Villars, a land cut south of Lake Salvador to
Harvey Canal No. 2, Harvey Canal No. 2 to Larose, La., and a land
cut to Houma, La., thence over a land cut south of Bayou Black and
Bayou Cocodrie, thence through Bayou Cocodrie and a land cut to
Bayou Black; thence through Bayou Black, Bayou Chene, and
Bayou Boeuf to the Atchafalaya River, about 0.5 mile south of
Morgan City, La., a total distance of 95.5 miles.
   An alternate connection with the Mississippi River in the vicinity
of Algiers, La., about 10.3 miles below Harvey lock, consisting of a
lock and land cut about 9 miles in length intersecting the Intra-
coastal Waterway at about mile 6, is now under construction.
   An alternate route from the Mississippi River at Plaquemine,
La. (113 miles above New Orleans), follows Bayou Plaquemine and
lower Grand River to and through a lock at Bayou Sorrel in the
East Atchafalaya Basin protection levee, thence through the levee
borrow pit to Berwick Bay; and thence through Berwick Bay to
Morgan City, La., a total distance of 56 miles. This alternate route
is to be enlarged from the vicinity of Morgan City to Indian Village,
La., and to be extended from Indian Village, La., through Bayou
Grosse Tete and a new land cut to and through a new terminal lock
and entrance channel to the Mississippi River in the vicinity of
Port Allen, La., a total distance of 65 miles.
   The section from the Atchafalaya River to Vermilion River, La.,
begins at the western end of the Mississippi-Atchafalaya section
and follows the Atchafalaya River about 2.5 miles, portions of
Little Wax Bayou, Possum Bayou, cut-offs, a land cut passing
through North Bend Plantation to Bayou Bartholomew; Bayou
Bartholomew to Little Bay, a land cut skirting the north edge of
Cote Blanche Island and the west edge of Weeks Island to Ver-
milion River, about 24 miles below Abbeville, La., a total distance
of about 63.6 miles.
  Franklin Canal, St. Mary Parish, La., extends southwesterly
        RIVERS AND HARBORS--NEW       ORLEANS, LA., DISTRICT     459
  from Franklin, La., on Bayou Teche, for 5.15 miles to Bayou
  Portage, a section of "The Inland Waterway from Franklin to the
  Mermentau River, La.," and through the bayou for 0.75 mile to
  the Gulf Intracoastal Waterway, 121 miles west of Harvey lock.
     The section from Vermilion River to Mermentau River, La., be-
gins at the western end of the Atchafalaya;-Vermilion section and
follows Vermilion River 1.3 miles, a part of the Schooner Bayou
cutoff canal, and a land cut running in a general northwesterly
direction to Mermentau River at a point about 0.5 mile above its
entrance into Grand Lake and about 16 miles below the town of
Lake Arthur, La., a total distance of about 42.7 miles. Vermilion
lock has been constructed about 1.75 miles west of Vermilion River
to prevent the ingress of salt water from Vermilion Bay.
    The section from Mermentau River to Calcasieu River, La., be-
gins at the western end of the Vermilion-Mermentau section and
follows the Mermentau River upstream for about 1.5 miles, a land
cut running in a west-southwesterly direction to Lake Misere, pass-
ing north of the lake and Bayou Misere, westerly to Sweet Lake,
south and west of Sweet Lake, northwesterly to Bayou Tete Bois,
through Bayou Tete Bois, Black Bayou, and cutoffs to a point on
Calcasieu River about 16.6 miles below the city of Lake Charles,
La., a total distance of about 37.1 miles.
    Calcasieu lock has been constructed near the intersection of Cal-
casieu River and Intracoastal Waterway, mile 238, Gulf Section,
Calcasieu Parish, approximately 16.6 miles below Lake Charles,
La.
    The section from the Calcasieu River to Sabine River, La., and
Tex., begins at the western end of the Mermentau-Calcasieu sec-
tion, and follows the Calcasieu River upstream about 1.6 miles, a
land cut running in a southwesterly direction 2.8 miles, thence
west 22 miles to Sabine River at a point about 3 miles below
Orange, Tex., a total distance of about 27.1 miles.
     (See U. S. Coast and Geodetic Survey Charts Nos. 878-884, in-
clusive; Corps of Engineers, Mississippi River Commission alluvial
valley map; and Rigolets, Chef Menteur, St. Bernard, Spanish Fort,
Bertrandville, Lake Cataouatche (east), Barataria, Baton Rouge,
Grosse Tete, Chicot Lake, Foster, Napoleonville, Morgan City,
Belle Isle, Bayou Sale, Jeanerette, and Derouen quadrangles; U. S.
Geological Survey maps, New Orleans (east), Cut-off, Houma, Gib-
son, Abbeville (southeast), Abbeville (southwest), Schooner Bayou
(southeast), Schooner Bayou (southwest), Schooner Bayou
(northeast), Schooner Bayou (northwest), Grand Lake East
 (northeast), Grand Lake East (northwest), Latania Lake, Lake
Misere, Boudreaux Lake, Sweet Lake, Lake Charles, Moss Lake,
Black Lake, Cameron Farms, and Phoenix Lake quadrangles; and
navigation maps of Intracoastal Waterway, Port Arthur, Tex., to
New Orleans, La.)
    Previous projects. Previous projects for the different sections
of this improvement were adopted by the following River and
Harbor Acts: August 11, 1888; March 2, 1907; March 3, 1909;
June 25, 1910; February 27, 1911; July 25, 1912; August 8, 1917;
July 18, 1918; March 2, 1919; and September 22, 1922. For further
details, see pages 878-895 of Annual Report for 1924.
460      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Existing project. This provides for a waterway 384.1 miles
long which is 12 feet deep and 125 feet wide at mean low Gulf,
except in the section between Lake Borgne Light No. 41 and New
Orleans (via land cut through the marsh and Industrial Canal),
33.1 miles long where a width of 150 feet is provided; an alternate
route 9 feet deep by 100 feet wide between Lake Borgne Light No.
41 and New Orleans (via the Rigolets, Lake Pontchartrain, and
Industrial Canal), 40.5 miles long; an alternate connection with the
Mississippi River below Algiers, 12 feet deep and 125 feet wide
about 9 miles long; a channel 12 feet deep and 125 feet wide for
the Plaquemine-Morgan City alternate route from the Mississippi-
Atchafalaya section of the waterway, in the vicinity of Morgan City,
through Lower Atchafalaya River (Berwick Bay) and the borrow
pit of the East Atchafalaya protection levee to and through Bayou
Sorrel lock which was constructed under the existing project
"Flood control, Mississippi River and tributaries," thence through
Lower Grand River to Indian Village, and thence by way by Bayou
Grosse Tete and a new land cut to and through a new terminal lock
and entrance channel to the Mississippi River in the vicinity of
Port Allen, La., opposite the lower limit of the Port of Baton
Rouge; a channel 9 feet deep and 100 feet wide from Indian Village
on the Plaquemine-Morgan City alternate route through Bayou
Plaquemine and Plaquemine lock to the Mississippi River at Plaque-
mine, La.; improvement of Franklin Canal as a connecting channel
from Gulf Intracoastal Waterway (mile 121) to Franklin, La., to
afford a channel 8 feet deep and generally 60 feet wide with a width
of 100 feet in its upper 300 feet; and a salt-water guard lock (Cal-
casieu lock) in the waterway at mile 238 west of Harvey lock. The
project also provides for the following: Widening at bends; pass-
ing places; mooring basins; locks or guard locks; such railroad
bridges over artificial cuts as are necessary; purchase of pipeline
dredge; construction and operation of new drainage canals and
pumping facilities to restore parish drainage systems where inter-
cepted; construction of a double-leaf bascule, four-lane highway
bridge with approaches at State Highway No. 61, Louisiana; con-
struction of movable bridges at Missouri Pacific Railroad and State
Highway Nos. 31 and 996 (in lieu of the State Highway Bridge
No. 31, a tunnel is being constructed, additional cost over estimated
cost of bridge to be borne by local interests); fixed trestle bridges
for crossing of proposed landside drainage canals; lift bridges at
Louisiana Highway No. 168, Port Allen, La., at Texas & Pacific
Railway, Port Allen, La., and at Texas & Pacific Railway, Morley,
La.; construction of bulkheads and jetties at Lake Borgne and
Chef Menteur, La., if found necessary; and for annual payments
to the Board of Commissioners of the Port of New Orleans for use
of a portion of the Inner Harbor Navigation Canal. The length of
the waterway within the New Orleans District is 384.1 miles via
the northerly or Port Allen route; and 299.4 miles via the southerly
or Harvey Canal route.
   Under ordinary conditions the mean range of tide is about 10
              RIVERS AND HARBORS-NEW ORLEANS, LA., DISTRICT                                                       461
inches and the extreme range is 14 inches. A severe storm may
cause a high tide of from 6 to 9 feet.
   The total estimate of cost for new work, revised in 1954, exclu-
sive of amounts expended on previous projects, is $57,450,000,
divided as follows: Algiers lock and canal, $14,900,000; Plaque-
mine-Morgan City Route, $24,350,000; and remainder of waterway,
$18,200,000. The latest (1952) approved estimate for annual cost
of maintenance is $1,543,000, including $820,000 for regular main-
tenance and $723,000 for operation and care of locks and dams and
costs pertaining to use of necessary State-owned facilities in con-
nection with the Inner Harbor Navigation Canal.
   Bayou Sorrel lock and Bayou Boeuf lock were constructed and
are being maintained and operated with Flood Control, Mississippi
River and Tributaries, funds. Therefore, construction, mainte-
nance, and operation costs are not included in the approved esti-
mates referred to hereinbefore.
                                                     Inner Harbor Navigation Canal lock
Miles below New Orleans, La. (Canal St.) ........                                      2.9
Miles from Mississippi River:.....                                                     0.6
W idth of chamber.................. ...                                                75 feet.
Length available for full width..............                                          640 feet.
Lift.    --     -----......................................    ....---------------..   S0-17.4 feet.
Depth on miter sill at mean low Gulf level.........                                    31.5 feet.
Character of foundation .. ... . .                   __._._______                      Timber piles.
K ind of dam .... ............. ....    .... . . . .                                   None.
Type of construction .-.                                        --                     Reinforced concrete.
Opened to navigation.... . ........           - ............                           February 1923.
Cost (non-Federal) .......      .... .. ............    .     .                        $8,648,492.

                                                                  Harvey lock
Miles above New Orleans, La. (Canal St.) ....                                          3.3
Miles from Mississippi River ..          ._______                                      0.13.
Width of chamber .. ....... ..                ..                                       75 feet.
Length available for full width ............                                           425 feet.
Lift..._.......--.. ........-----------                                                0-19.6 feet.
Depth on miter sill at mean low Gulf level...........                                  12 feet.
Character of foundation __ ___... .                     ___
                                                   .________                           Timber piles.
Kind of dam ..........                                                                 None.
Type of construction .......                   ...                                     Reinforced concrete.
Opened to navigation .............                                                     1934 and completed 1935.
C ost - -    ....      .. .......... ... ..                                            $1, 775, 132.

                                                                  Algiers lock
Miles below New Orleans, La. (Canal St.)__.. ...                      7.
Miles from Mississippi River.......                     ._________.   0.38.
Width of chamber.....................        . .                      75 feet.
Length     available   for  full  width_.._...... .....               760 feet.
Lift.....-.... .         .........---........                         0-18 feet.
Depth on sill at mean low Gulf level_                                 13 feet.
Character of foundation _______.     . __.___________._______________Timber piles.
K ind of dam ............ ............ ............... None.
Type of construction .......                                        - Reinforced concrete.
Opened to navigation ....-.. ................                         Under construction.
Cost (estimated)-....X. ..                                            $5,060,900.
462                      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                                            Calcasieu lock
Miles below Lake Charles, La...............................                                                        16.6.
Miles from Calcasieu River ..............................                                                   ..     0.5.
Width between abutments.-------.....                                                ---------............. --      75 feet.
Length available for full width-.......-.-..........-.........                                                     1,180 feet.
Lift....................................................................-----------------------------------        0-4 feet.
Depth on sill at mean low Gulf level_......_...-..-............                                                    13 feet.
Character of foundation._ ___-------....__                                 --             .....                .   Concrete slab on preconsoli-
                                                                                                                      dated stiff clay.
Kind of dam....................------------------------------.                                                     None.
Type of construction .~...                                                                                         Reinforced concrete gate bays
                                                                                                                      with earth chamber.
Opened to navigation .................                                        .                                    December 1950.
Cost...  .......---........... . .     .                                          ..                               $2,133,527.

                                                                          Plaquemine lock
Miles above New Orleans, La. (Canal St.) ........-------- 113.
Miles from Mississippi River                        ____..... .___.__.        0.10.
Width of chamber                  --..........................           --   55 feet.
Length available for full width...                        _____               260 feet.
Lift---............--...................---------------------0-34 feet.
Depth on miter sill at mean low Gulf level................                    10 feet.
Character of foundation............                                           Timber piles.
Kind of dam ........-                     -           -          -   -        None.
Type of construction                                 ..............         . Concrete.
                                                                       .....--
Completed and opened to navigation.........                                   1909.
Cost...............................-----------------------------------        $1,302,006.

                                                                         Bayou Sorrel lock
Miles from New Orleans, La. (Canal St.):
     Via Plaquemine lock....................                          .                                            131.
     Via Harvey lock .....-.-                                                                                      135.
Miles from Mississippi River via Plaquemine
  lo ck .......... ......-- -- -- --... .. .. . .. . .. . ..                                                       18 .
Width of chamber-...                  -        -         -          -   -                                          56 feet.
Length available for full width.....................                                                               760 feet.
Lift-----............................-------------------------------                                               0.21 feet
Depth on sill at mean low Gulf level...........-.......                                                            14.31 feet.
Character of foundation--           .      -.---.--.--....-........                                                Timber piles.
Type of construction..-.......___....-------                                                                       Reinforced concrete gate bays
                                                                                                                      with earth chamber.
Opened to navigation ...................                                                                          June 1951.
Completed                                                                                                         October 1952.
Cost ....--.... :.--_ _     ..           . .                                                                      $4,700,948.

                                                                             Vermilion lock
Miles from Abbeville, La........           -                                26.
Miles from Vermilion River____  .------- ____-___-__-___.        .__ -1.75.
Width between abutments ____.___________..            .       ._________56 feet.
Length available for full width_........................             .__ . 1,182 feet.
Lift....  ------------------------------------------                        0-5 feet, either direction.
Depth on gate at mean low Gulf level .........                              11.3 feet.
Character of foundation_ -__-.     -       -----..------..                  Timber piles.
Kind of dam .-....-             -
                           - . --..                  .
                                        . -~.~.--------....        .         Reinforced concrete spillway
                                                                                dam, vertical cast-steel gates,
                                                                                timber-pile foundations.
Type of construction-..-..-.-               -------.      .        .        Reinforced concrete.
Opened to navigation                  _______           ._                  1933 and completed 1934.
                                                                           ...................
Cost...   ----------------..---------------.....................---.        $330,765.
              RIVERS AND HARBORS-NEW ORLEANS, LA., DISTRICT                                                       463
                                                  Bayou Boeuf lock
Miles from New Orleans, La. (Canal St.):
      Via Harvey lock.......------------------------96.6.
      Via Plaquemine lock.............. .. . ................ 170.0.
Miles from Mississippi River via Plaquemine lock ... 56.7.
Width between abutments----------............------........                              75 feet.
Length available for full width -.............-                                 ....--- 1,160 feet.
Lift........----...                                                                  ........--------------------
                                                                                         0-11.3 feet.
Depth on sill at mean low Gulf-...-...----------------.....     ...                       13 feet.
Character of foundation..........                     .....                 ...           Concrete slab on medium to
                                                                                             stiff clay.
Type of construction...........-                                             -            Reinforced concrete gate bays
                                                                                             with earth chamber.
Opened to navigation ...-.............-----------                        -........
                                                                      ----     --... Lock completed June 14, 1954;
                                                                                             approach channels under con-
                                                                                             struction.
Cost (estimated)--------..............------------------......................            $2,754,000.
The existing project was authorized by the following River and
Harbor Acts:
       Acts                           Work authorized                                        Documents
                  i-----                                    ---

Mar.    3, 1925 Construction of waterway from New Orleans, La.,                   H. Doc. 238, 68th Cong.lst sess.
                  to Galveston Bay, Tex.
Jan. 21, 1927   Extension of waterway to Corpus Christi, Tex ...         -         Do.
July - 3, 1930  A   channel 100 feet wide and 9 feet deep from Lake             H. Doc. 341, 71st Cong., 2d sess.
                  Pontchartrain to Mississippi Sound.
June 26, 19341 Operation and care of locks and dams provided for
                with funds from War Department appropriations for
                rivers and harbors.
July 23,1942 Enlargement of waterway from 100 feet wide and 9                   H. Doc. 96, 79th Cong., 1st sess.; H.
                  feet deep to 125 feet wide and 12 feet deep, from               Doc. 230, 76th Cong., 1st sess.'
                  Apalachee Bay, Fla., to Corpus Christi, Tex., and
                   its extension to the vicinity of the Mexican border,
                  except between Mobile Bay, Ala., and New Or-
                  leans, La., where the width shall be 150 feet; and
                  for rental of Inner Harbor Navigation Canal
                  facilities.
Mar. 2, 1945    Alternate connection with the Mississippi River in              S. Doc. 188, 78th Cong., 2d sess.
                   the vicinity of Algiers at New Orleans.
July 24, 1946   Enlargement and extension of the Plaquemine-Mor-                S. Doc. 242, 79th Cong., 2d sess.
                  gan City route from the Mississippi-Atchafalaya
                  section of the waterway, in the vicinity of Morgan
                   City, to and through a new terminal lock and en-
                   trance channel to the Mississippi River in the
                  vicinity of Port Allen, opposite the lower limit of
                  the Port of Baton Rouge.
    Do___------ Restoration, improvement and maintenance of the                 S. Doc. 189, 79th Cong., 2d sess.
                   Franklin Canal as a terminal branch channel, 8
                  feet deep and 60 feet wide from its confluence with
                  the Gulf-Intracoastal Waterway to Franklin, La.
    Do ..--- A salt-water guardlock in the waterway at mile 238                 S. Doc. 231, 79th Cong., 2d sess.
                  west of Harvey lock.


  1 Permanent Appropriation Repeal Act.
  2 Not mentioned in authorizing act.


   Local cooperation. Requirements of local cooperation for the
work performed by the United States prior to the modifications
since 1945 were fully complied with.
   Local cooperation for modifications since 1945 has been complied
with, except for that section of the waterway from Port Allen to
Indian Village, for which documents of local cooperation have been
requested.
   Terminal facilities. The terminals at New Orleans which are
most generally used by Intracoastal Waterway traffic are those
controlled by the State of Louisiana on the Inner Harbor Naviga-
tion Canal. Since April 1, 1944, the portion from the Mississippi
River to its intersection with the New Orleans-Rigolets section of
 464      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   the Gulf Intracoastal Waterway has been under lease to the United
   States and is now operated by the United States toll-free, 24 hours
   per day. Except for the terminal facilities at New Orleans, facili-
   ties are in general confined to privately owned piers, wharves, or
   oil docks. At Morgan City on the Atchafalaya River there are two
   large and three small wharves open to all without charge. The
  facilities are considered adequate for existing commerce.
      Operations and results during fiscal year. New work by con-
  tract: Alternate connection in the vicinity of Algiers, La., also
  known as the Algiers lock and canal. The following work, in prog-
  ress at the beginning of the fiscal year or contracted during the
  fiscal year, was completed on dates indicated:
      Construction of Plaquemines and Orleans Parishes pumping
  stations on June 9 and 16, 1954, respectively; installation of power
  cable for Orleans Parish pumping station on April 9, 1954; con-
  struction of reservation building and appurtenances for Algiers
  lock on November 11, 1953; and the installation of a chain link
  fence on Algiers lock reservation on July 27, 1953, all at a cost of
  $487,093.
     Purchases of equipment for the Plaquemines and Orleans Par-
  ishes pumping stations amounted to $355,079.
     On June 21, 1954, construction of concrete bridge was completed
  under contract for Plaquemines Parish road relocation and access
  road, which work was commenced on February 5, 1954, and at the
  end of the fiscal year was 74 percent complete. All necessary cul-
verts have been installed, the detour road has been completed, and
parish road relocation is in progress. Costs were $104,772.
     Construction of second lift of Algiers navigation canal levee
commenced on May 7, 1954, and at the end of the year approxi-
mately 35,586 cubic yards were placed in constructing 6,800 linear
feet of west levee and 52,573 cubic yards were placed in construct-
ing 9,300 linear feet of east levee, at a cost of $23,021.
     Under a reimbursable contract with the State of Louisiana,
Department of Highways, for highway relocations, including a
vehicular traffic tunnel and necessary bridges, construction con-
tracts have been awarded as follows:
     For a vertical lift bridge over Algiers Cutoff Canal for State
Route No. C-1509: Work on this contract, in progress at the be-
ginning of the fiscal year, was 24 percent complete, with the fol-
lowing work accomplished: Driving of all concrete substructure
piles and timber piles for north and south fender system complete,
and construction of concrete roadway, sidewalk, and concrete
spans commenced.
     For grading, drainage structures, and bituminous surface treat-
ment of Cutoff and Twelve-Mile Point highways. This contract
commenced during the previous fiscal year and is 81 percent com-
plete. During the year culverts were installed along both high-
ways and hauling of shell was completed. Twelve-Mile Point
highway and embankment were rolled, bladed, and compacted, a
concrete steel bridge was built across drainage canal, and two
24-foot approach slabs were poured for use in connection with
this bridge. Grading and shelling of Ammunition Dump Road
was completed. Cutoff highway was rolled, bladed, and com-
       RIVERS AND HARBORS-NEW ORLEANS, LA., DISTRICT             465
pacted. Approximately 232 linear feet of curb and gutter concrete
for neutral ground at intersection of Ammunition Dump Road
and road "B" were poured.
   For construction of Belle Chasse vehicular traffic tunnel. Work
on this contract commenced on February 16, 1954. At the end of
the fiscal year construction was 17 percent complete with excava-
tion for structures in progress, clearing and grubbing of approxi-
mately 14 acres completed, slopes dressed, and well-point system
installed. The first section of the concrete slab has been poured
in the tunnel site and work was started on the roadway that
constitutes the east and west approaches of the tunnel.
   For construction of fixed bridges at State Routes Nos. C-31 and
C-1460 over Plaquemines drainage canal. Work on this contract
has not commenced.
   For construction of Bayou Barataria Road: To date spoil bank
borings have been made.
   Costs on these contracts were $711,486.
   The contract for designing, fabricating, erecting, and testing a
50-ton stiffleg derrick is 82 percent complete and the contract for
the manufacture and delivery of emergency dam girders and of
needle dam girders, including the girder supports, is 75 percent
complete. Costs on these contracts were $191,861.
   Work under lump sum contract for design, plans, and specifica-
tions for a vertical lift bridge, a fixed span bridge, approaches, and
appurtenances to relocate the New Orleans and Lower Coast Rail-
road facilities affected by the Algiers lock and canal project, com-
menced in previous fiscal year, was 95 percent complete, with costs
of $289. A reimbursable contract has been entered into with the
railroad covering engineering, inspection, and deferred construc-
tion for this work, which will be accomplished by continuing con-
tract. The work has been advertised and bids are scheduled to be
opened July 30, 1954.
   A reimbursable contract has been entered into, subject to the
approval of the Chief of Engineers, with the Southern Bell Tele-
phone and Telegraph Co. for alteration of their facilities across
Algiers lock and canal project near Belle Chasse, Plaquemines
Parish, La.
   Delayed costs on contract for guide walls completed in previous
fiscal year amounted to $455.
   Water was supplied to Algiers lock during the fiscal year at a
cost of $3,229.
   New work by hired labor: For the Plaquemine-Morgan City
alternate route: preparation of plans and specifications for reloca-
tion of railroad bridge at Morley, La.; of right-of-way maps; and
of engineering studies in connection with design memorandum on
Port Allen lock; and model studies, soil borings, and analysis,
were continued at a cost of $28,771.
   For the Algiers lock and canal: repairs to power cable, condi-
tion check of structure; obtaining discharge measurements for
Orleans and Plaquemines Parishes pumping stations, and inspec-
tion of equipment for these stations; miscellaneous work and weed
cutting; interim dressing of levees in Orleans Parish; and placing
of third layer of earthfill, approximately 8,174 cubic yards, on
466           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

approach embankments at vertical lift bridge State Route No.
C-1509, were performed at a cost of $26,465; and procurement of
local cooperation, preparation of relocation agreements, of engi-
neering and design, and of plans and specifications, and soil bor-
ings were continued at a cost of $17,366.
   Maintenance by contract: A total of 2,320.48 stations were
dredged by the following contract dredges during the period
February 11 to June 30, 1954, in restoring project dimensions to
approximately 67 miles of the channel in the New Orleans-Rigolets
section and Mississippi River-Vermilion River section:
     Dredge Tchefuncta .............................................          ... ............. ..... 1,716.74 stations
     Dredge Blackwater-...........................................................................      126.25 stations
     Dredge Moreland II -....-.-.....     -...................... __ ........................   .....   121.00 stations
     Dredge Paul F. Jahncke-....__.... .....-............ .._ .......               ........... .....   356.49 stations

  Costs covering this contract dredging amounted to $404,371.
  Approximately 564,017 cubic yards of shoaled material were
removed by leased dredges as follows:

                                                                     Pontchartrain        Tchefuncta        Natchez

Inner Harbor Navigation Canal forebay____ ________-_-                 -      112, 115   ----------------
Plaquemine lock forebay and tailbay          ---                                                 48, 460
                                    -----------------------------------
Wax Lake Outlet crossing....----------------                                                                   403, 442



   In addition, the leased dredge Grand Bay removed a shoal from
the waterway at mile 6.1 east of Harvey lock. The cost of work
by leased dredges was $174,480.
   Maintenance by hired labor: Preliminary plans and specifica-
tions; acquisition of rights-of-way; procurement of local cooper-
ation; miscellaneous investigations and surveys; supervision, in-
spection, and patrol of the waterway; removal of snags and other
obstructions to navigation; stream gaging; and preparation of
agreements and economic justification study for navigation proj-
ects, were continued by hired labor at a cost of $143,841.
   A report and study of caving banks west of Harvey, La., was
continued at a cost of $2,135, and the damaged bulkhead on the
waterway at Houma, La., was removed at a cost of $3,056.
   Dredging to remove debris and deposits from gate pits at each
end of Harvey, Plaquemine, and Inner Harbor Navigation Canal
locks was performed at a cost of $5,720, and clearing willows from
banks of waterway west of Harvey lock, which obstructed the view
around bend for navigation, was accomplished at a cost of $17,143.
Wheel wash operations were used for removal of shoaling in
Plaquemine lock forebay at a cost of $3,785.
   Balance of cost for fiscal year 1954, incidental to rental lease
for use of Inner Harbor Navigation Canal facilities, was $123,000.
   Costs for collection and compilation of commercial statistics
and processing of permits and leases for the project were $23,416.
   Costs for deferred items on this project amounted to $66,420.
   Operating and care: The locks were operated throughout the
fiscal year.          The locks, grounds, and structures were maintained
          RIVERS AND HARBORS-NEW ORLEANS, LA., DISTRICT                                                        467
in good condition, and all necessary and routine work thereon
performed by hired labor at the following costs:
   Calcasieu lock ..............       ...................           ------------------------. $63, 302
      Havylc
   Harvey   lock ----------------------------------------------------------
                          _......  . ... ...............
                                                                                                         - 9,2
                                                                                                 - -.- -.........
                                                                                                              96, 721
   Inner Harbor Navigation Canal lock                  .....................--------------------------      170,844
   Plaquemine lock ..             ...------------------------------------------                               92,870
   Vermilion lock ...          ...        ...         .......................................                 81,863
   Algiers lock .....         ....                                                                             1,065
                                                         ..........................................------------------------------------

      Total-....     .   -.-.....-..-.                                                       ... 506, 665
                                                                                   . ............
   The cost of operating the Paris Road pontoon bridge and the
Florida Avenue bridge was $75,103, including replacing of wooden
deck and reconstruction of approaches at Paris Road Bridge.
   The following contract work was performed at the locks:
   Reconstruction of the fender system at the Inner Harbor Navi-
gation Canal, commenced under continuing contract in previous
fiscal year, was completed on November 9, 1953.
   Repairs to Inner Harbor Navigation Canal, commenced in pre-
vious fiscal year, were completed on May 10,, 1954, and construc-
tion of the northeast dolphin and fender system at this lock was
accomplished during the period November 30, 1953, to January
21, 1954.
   The guide walls and fender system at Calcasieu lock were re-
paired during the period February 9 to March 3, 1954.
   The foundations of the two residences at Harvey lock were re-
constructed and appurtenant repairs were made to the houses dur-
ing the period January 23 to March 10, 1954.
   The costs chargeable to these contracts were $328,345.
   Hired labor forces removed fender system framework from
emergency dam girder recess on lake end of Inner Harbor Naviga-
tion Canal lock; made repairs to the Harvey Canal lock, restored
the dam to the by-pass channel at Vermilion lock during the period
January 14 to March 15, 1954; and made repairs to the concrete
mats in lock chamber at Calcasieu lock, all at a cost of $97,280.
   The total costs during the fiscal year (all funds) were $3,924,-
643 of which $1,949,887 was for new work; $967,365 for mainte-
nance; and $1,007,391 for operating and care.
   Condition at end of fiscal year. The project, as modified by
River and Harbor Acts approved March 2, 1945, and July 24,
1946, is 44 percent complete.
   Plaquemine lock was completed in 1909; its reservation com-
prises 19 acres. Vermilion lock was completed in 1934; the
ground on which it is constructed is possessed by the United States
under an easement deed to a strip of land 300 feet wide along the
Intracoastal Waterway. Harvey lock was completed in 1935; the
reservation comprises 3.3 acres. Inner Harbor Navigation Canal
lock was leased by the United States from the Board of Commis-
sioners of the Port of New Orleans effective April 1, 1944. Bayou
Sorrel lock, constructed with funds for Flood Control, Mississippi
River and Tributaries, and located in the East Atchafalaya Basin
protection levee, was opened to navigation June 4, 1951, and com-
pleted October 1, 1952. The lock is used as part of the Gulf Intra-
coastal Waterway alternate route from Plaquemine, La., to Mor-
 468      REPORT OF CHIEF OF :ENGINEERS, U. S. ARMY, 1954

gan City, La. Calcasieu lock, which was opened to navigation on
December 18, 1950, was physically completed on April 25, 1952.
    Dredging of the canal, except for the work authorized under
River and Harbor Acts of March 2, 1945, and July 24, 1946, was
commenced on December 19, 1942, and completed on June 9, 1944.
    Dredging Franklin Canal to an interim 8- by 50-foot section was
completed during the period July 26, 1949, to March 14, 1950.
    The alternate connection below Algiers, with new lock, is ap-
proximately 67 percent complete, with the following work having
been accomplished to date at a cost of $10,014,519: Completion
of lock structure and backfill, excavation of Plaquemines Parish
and Orleans Parish drainage canals and pumping station sites and
erection of the respective pumping stations, including purchase of
equipment; partial completion of guide levees and navigation
canal; purchase and installation of power cable for Orleans Parish
pumping station; installation of a chain link fence on Algiers lock
reservation; and relocation and alteration of reservation buildings
and construction of appurtenances; and work in progress under a
reimbursable contract with the Department of Highways, State of
Louisiana, for the relocation of State Routes Nos. C-1509 and
C-996, including fixed bridges over drainage canals as required,
construction of Algiers Cutoff Canal bridge, construction of a
vehicular traffic tunnel for State Route No. 31 crossing of the
navigation canal, and for construction of Bayou Barataria Road.
Also in progress is construction of parish road relocation and ac-
cess road, Plaquemines Parish, La., the second lift of Algiers
navigation canal, and work under a lump sum contract for the
design, plans and specifications for a vertical lift bridge for the
New Orleans and Lower Coast Railroad crossing of the navigation
canal and a fixed bridge over the drainage canal.
   Contracts have been entered into for the construction of fixed
bridges at State Routes Nos. C-31 and C-1460 over Plaquemines
drainage canal under reimbursable contract with the Department
of Highways, State of Louisiana, and for the construction of Or-
leans Parish pumping station access road.
   New work remaining to complete the project, besides that which
is now in progress and/or under contract, consists of: Alternate
connection below Algiers with new lock: completion of navigation
canal, including the river approach channel; removing plugs and
shaping levees; and construction of a vertical lift railroad bridge,
a fixed bridge and track raising for the New Orleans and Lower
Coast Railroad crossing.        Plaquemine-Morgan City alternate
route: Dredging 12- by 125-foot alternate route between Port
Allen and Morgan City, with construction of lock in vicinity of
Port Allen, three bridges, and relocation of highways, railroads,
and utilities. Lake Borgne Light No. 41 to the Vermilion River
section: Construction of a permanent bridge at Louisiana High-
way No. 61 (Paris Road), mile 13.0, and construction of bulk-
heads and jetties at Chef Menteur and Rigolets at miles 22.7 and
33.7, respectively, all east of Harvey lock, completion of Franklin
canal, and other minor items.
   The controlling depths, mean low Gulf (June 1954), were: Lake
                 RIVERS AND HARBORS--NEW ORLEANS, LA., DISTRICT                                                                        469
Borgne Light No. 41 to Sabine River, 12 feet; and Plaquemine-
Morgan City alternate route, 9 feet.
   The total costs under the existing project to the end of the
fiscal year (all funds) were $43,252,379 of which $25,776,031 was
for new work (including $353,541, public works funds, and $330,-
370 contributed funds), $9,621,566 for maintenance including
$11,457 covering cost of deferred items, and $7,854,781 (exclud-
ing $521,485 costs for works of improvement under provisions
of the permanent indefinite appropriation for such purpose) for
operation and care of locks and bridges. In addition, the sum of
$521,485 was expended between January 1, 1927, and June 30,
1935, on the operating and care of works of improvement under
the provisions of the permanent indefinite appropriation for such
purpose.
                                                 Cost and financial summary

                                                            Fiscal year ending June 30                                         Total to June
                                                                                                                           30, 1954, includ-
                                                                                                                           ing fiscal years
                                         1950             1951             1952              1953              1954        priorto 19501 2

New work:
   Appropriated .. __                $2, 500,000      $3, 450, 000     $4, 366, 543           $60, 000          $35, 000         $33, 645, 371
   Cost .. __ __-   -                 1, 669, 567      1, 327, 602      1, 213, 992        2, 969, 426       1, 949, 887          29, 908, 269
Maintenance:
   Appropriated-      -_               1, 522, 180      2, 310, 450      1, 544, 913       1, 573, 728       1, 882, 563           18, 664, 702
   Cost--------------                  1, 435, 516      1, 857, 752      1, 832, 567       1, 834, 179       1, 974, 756           18,479, 554

   1 Includes $4,320,698 for new work; $454,259 for maintenance; and $548,948 for operating and care for previ-
ous projects.
   2 Included in these totals are $353,541, NIRA funds (new work); $1,070,433, permanent indefinite appro-
priation and $11,457 covering cost of deferred items (maintenance); and $75,000 from appropriation for main-
tenance and operation of dams and other improvements of navigable waters.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954...........                                                                $1,011,844
                                                                                                                             ..----------.
    Appropriated for succeeding fiscal year ending June 30, 1955-....--------                                                           750, 000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955         --------------------..                                     -------------------- 1,761,844
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project-----...----......--..............----------------.......................-------................... 27, 375, 327

                                                              Fiscal year ending June 30                                    Total to June
                                                                                                                           30, 1954, includ-
                                                                                                                           ing fiscal years
                                          1950            1951             1952              1953              1954            prior to 19501
New work:
   Appropriated                           $4, 000                         -$4,    000 -----------            2 -$8, 897              $330,370
   Cost..                                 57, 103 -                                    I                 I             -330,             370

     1   Includes contributed funds in amount of $295,267 and advanced funds in amount of $35,103.
     2 Refund of trust funds.

3.        INTRACOASTAL                     WATERWAY, FROM THE MISSISSIPPI                                                          RIVER
                                            TO BAYOU TECHE, LA.
  Location. This waterway extends in a westerly direction from
the Mississippi River, at or near Harvey, La., to Bayou Teche, La.,
above Morgan City. This route follows the Harvey Canal No. 1,
and Bayou Barataria from the Mississippi River to Lake Salva-
dor; thence across Lake Salvador; thence through Harvey Canal
No. 2 to Bayou Lafourche and up this bayou to Lockport; thence
through the Company Canal to Bayou Terrebonne and up this
470         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

bayou to the vicinity of Houma; thence through a land cut to
Bayou Black; thence along Bayou Black, Bayou Chene, and Bayou
Boeuf to Morgan City; thence up the Atchafalaya River to the
mouth of Bayou Teche, a total distance of 115 miles. (See U. S.
Coast and Geodetic Survey Chart No. 1116; U. S. Geological Sur-
vey maps, New Orleans, East Bertrandville, Lake Cataouatche
East, Barataria, Cut-Off, Houma, and Gibson quadrangles; Corps
of Engineers, Mississippi River Commission alluvial valley map,
and Morgan City and Belle Isle quadrangles; and navigation maps
of Intracoastal Waterway and Atchafalaya River system.)
   Existing project. This provides for a waterway from the Mis-
sissippi River to Bayou Teche having a depth of 5 feet below mean
low Gulf level and a bottom width of 40 feet, with appropriate
side slopes. This project has been largely superseded by the Gulf
Intracoastal Waterway (New Orleans district). Under ordinary
conditions the mean range of tide is about 10 inches, and the
extreme range about 14 inches. A severe storm may cause a high
tide of from 6 to 9 feet.
   The estimate of cost for new work, revised in 1922, is $875,000.
The latest (1950) approved estimate for annual cost of mainte-
nance is $20,000. The existing project was adopted by the River
and Harbor Act of March 2, 1919 (H. Doc. 610, 63d Cong., 2d
sess.). The latest published map is printed opposite page 2401 of
the Annual Report for 1920.
   Local cooperation. Fully complied with.
   Terminal facilities. On Bayou Terrebonne, at Houma, there
are several small privately owned wharves. On the Atchafalaya
River at Morgan City there are two large and three small wharves
open to all without charge and there are several private wharves.
The facilities are considered adequate for existing commerce.
   Operationsand results during fiscal year. Restoration of Black
Bayou channel to a 5-foot depth by snagging and hand clearing be-
tween mile 83.5 and the highway bridge at Gibson, La., was ac-
complished by hired labor during the period December 7 to 11,
1953, at a cost of $3,506 for maintenance.
   Condition at end of fiscal year. This project has not been com-
pleted and has been superseded for most of its length by the pres-
ent 12- by 125-foot Gulf Intracoastal Waterway which coincides
with or parallels it. Only those sections of the project which are
used for navigation are being maintained. The total costs were
$9,873, all for maintenance.
   All costs and expenditures incurred prior to July 1, 1939, are
reported under previous projects of the Gulf Intracoastal Water-
way between Apalachee Bay, Fla., and the Mexican Border (New
Orleans district).
                                  Cost and financial summary

                                         Fiscal year ending June 30                Total to June
                                                                                  30, 1954, includ-
                                                                                  ing fiscal years
                           1950        1951        1952        1953     1954        prior to 1950
Maintenance:
   Appropriated........       $500 ---------------------------------    $3, 506             $9, 873
   Cost-----------------       500 ----------------------------------    3,506               9,873
             RIVERS AND HARBORS--NEW ORLEANS, LA., DISTRICT                                         471
          4. THE INLAND WATERWAY FROM FRANKLIN TO THE
                       MERMENTAU RIVER, LA.
   Location. This canal extends from Hanson lock on Bayou Teche
through Hanson Canal and Bayou Portage to the Intracoastal
Waterway, and along the Intracoastal Waterway to mile 161, west
of Vermilion Bay. The total length of the waterway is 26.8 miles.
 (See U. S. Coast and Geodetic Survey Chart No. 1116; Corps of
Engineers, Mississippi River Commission alluvial valley map, and
Foster, Bayou Sale, Jeanerette, and Derouen quadrangles; U. S.
Geological Survey maps, Abbeville (southeast), and Abbeville
 (southwest).)
   Existing project. This project, as modified by the River and
Harbor Act approved July 24, 1946 (S. Doc. 231, 79th Cong., 2d
sess.), provides for a waterway from Bayou Teche at or near
Franklin, La., to the western end of Vermilion Bay, having a depth
of 5 feet below mean low Gulf and a bottom width of 40 feet, with
appropriate side slopes; also the purchase of the Hanson Canal.
   This project, reported in the Annual Report for 1924 under the
headings, Intracoastal Waterway, Franklin to Mermentau, La.,
and Intracoastal Waterway from Vermilion River to Schooner
Bayou, La., has been superseded for most of its length by the
project "Gulf Intracoastal Waterway (New Orleans District)."
The River and Harbor Act approved July 24, 1946 (S. Doc. 231,
79th Cong., 2d sess.), authorized the incorporation of the existing
project "Inland Waterway from Franklin, La., to the Mermentau
River," west of Vermilion Bay, in the modified Flood Control, Gen-
eral, project "Mermentau River, La." Under ordinary conditions
the mean range of tides is about 10 inches and the extreme range
about 14 inches. A severe storm may cause a high tide of from
6 to 9 feet.
   The estimate of cost for new work (revised in 1950) is $125,000.
The latest (1952) approved estimate for annual cost of mainte-
nance is $22,000, including $12,000 for operation and care of
Hanson lock.
   Data regarding the lock are as follows:
                                               Hanson lock
Miles from Franklin, La ........                                        1.5.
Miles from Bayou Teche ..........                                       0.
Width of chamber ..............                                         26.5 feet.
Length available for full width                -------                  937 feet.
Lift.....-----------------------------                   -              0-5 feet.
Depth on miter sill at low water_................ .          .   .      5 feet.
Character of foundation ......                  .
                                           ___.__.__.                   Timber piles.
                                   --- - -- -
K ind of dam ...........................--                              None.
Type of construction ...........--.....                                 Concrete buttresses, wooden miter
                                                                            gates, earth-lock chamber.
Completed                                                               1907. Operated by the United
                                                                 -___-.._..
                                                                            States since 1923.
Cost.     -..-....   .                                                  $65,000, including 4.1 miles of
                                                                            canal.
472              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  The existing project was authorized by the following River and
Harbor Acts:

     Acts                          Work authorized                                  Documents
Mar. 2, 1907 The general project (waterway from Franklin to the           H. Doc. 640, 59th Cong., 2d sess.
              Mermentau River, La.).
Mar. 3,1909 (Authorized the Secretary of War to make such
Feb. 27,1911  changes in location of channel as might be desir-
              able.
July 25,1912 Authorized the purchase of the so-called Hanson
              Canal between Bayou Teche and Cote Blanche
              Bay, at a cost not to exceed $65,000.
Mar.   2, 1919                                                     H. Dec. 1336, 62d Cong., 3d sess.
                 Construction of the Schooner Bayou cutoff--.........
                                                                           (Contains latest published maps.)
June 26, 19341   Inclusion of operation and care of locks in project
                   provided for with funds from War Department ap-
                   propriations for rivers and harbors.
July 24, 1946    The incorporation of the existing project west of Ver-   S. Doc. 231, 79th Cong., 2d sess.
                  milion Bay in the modified project "Mermentau
                  River, La."

  1 Permanent Appropriations Repeal act.

   Local cooperation. Fully complied with.
   Operationsand results during fiscal year. Costs in the amount
of $1,873, operating and care, were incurred for maintenance of
Hanson lock. Normally the gates are left in an open position
and are operated only as required.
   Condition at end of fiscal year. The project was considered
complete prior to the modification by the River and Harbor Act
approved July 24, 1946, which provided for channel enlargement
and realignment from Vermilion Bay to White Lake and from
White Lake to Grand Lake; for channel enlargement of North
Prong of Schooner Bayou and for construction of a gated control
structure in the new channel near Schooner Bayou lock, and the
incorporation of the existing project "Inland Waterway from
Franklin to the Mermentau River, La.," west of Vermilion Bay,
in the modified Flood Control, General, project "Mermentau River,
La." The Hanson Canal and lock were acquired on October 16,
1923; the lockmaster's house was completed in 1924; and was
moved to Berwick lock during the period August 27 and October
26, 1951. The United States property on which the lock is situated
is a strip of land 300 feet wide between parallel lines running from
Bayou Teche to Bayou Portage, containing 148 acres. Dredging
from Vermilion Bay to the Mermentau River was completed in
1912.
   The controlling depths, mean low Gulf (April 1953), were:
From Gulf Intracoastal Waterway through Cut-Off Canal, 6.5
feet; to Schooner Bayou, 12 feet; to White Lake, 11 feet; over bar,
3 feet; to Grand Lake, 6 feet; over bar, 3 feet; to Gulf Intracoastal
Waterway, 5 feet.
   The total costs to the end of the fiscal year were $791,518, of
which $249,052 was for new work, $137,262 for maintenance, and
$405,204 was for operating and care.
            RIVERS AND HARBORS-NEW ORLEANS, LA., DISTRICT                                                       473
                                      Cost and financial summary

                                              Fiscal year ending June 30                               Total to June
                                                                                                      30, 1954, includ-
                                                                                                      ing fiscal years
                               1950          1951        1952              1953            1954         prior to 19501
New work:
   Appropriated ---------------    -------     -----------------------------         ------------             $249, 052
   Cost--------------------                                                                  --                249, 052
Maintenance:
   Appropriated -------
   Cost-------------      [  $10, 800
                               11,687
                                              $7, 950
                                               4, 647
                                                        -$1,     000
                                                               1,572
                                                                       -    __
                                                                           $1, 900
                                                                                            $2, 000
                                                                                              1,873
                                                                                                               542, 969
                                                                                                               542, 466

  1 Includes $165,299 from permanent indefinite appropriation for operating and care.


       5. MISSISSIPPI RIVER, BATON ROUGE TO THE GULF OF
                                             MEXICO, LA.
   Location. The Mississippi River between 'Baton Rouge and the
Gulf of Mexico flows in a general southeasterly direction through
the southeastern portion of the state of Louisiana. At the Head of
Passes, 233.1 miles below the Louisiana Highway Commission
bridge at Baton Rouge, the river is broken up into three main
passes: Southwest Pass, South Pass, and Pass a Loutre, two of
which, Southwest Pass and South Pass, are improved under the
existing project. The distances from Head of Passes to the
mouths of Southwest and South Passes are 20.1 miles and 13.5
miles, respectively. The mouth of Southwest Pass is 141 miles
west of Mobile, Ala., and 349 miles east of Galveston, Tex. The
mouth of South Pass is 18.5 miles northeast of the mouth of South-
west Pass. (See U. S. Coast and Geodetic Survey Charts Nos.
1269, 1271, and 1272; Corps of Engineers, Mississippi River
Commission alluvial valley map and Zachary, Baton Rouge, White
Castle, Donaldsonville, Thibodaux, Mount Airy, Bonnet Carre,
Hahnville, New Orleans, St. Bernard, Bertrandville, Barataria,
Pointe a la Hache, and Forts quadrangles; and United States Geo-
logical Survey maps, Empire, Cubits Gap, Pass a Loutre (west),
Pass a Loutre (east), Southwest Pass, South Pass, Burrwood, and
Mud Pan Bayou quadrangles.)
   Previous projects. Previous projects for the different sections
of this improvement were adopted by the following River and Har-
bor Acts; July 4, 1836; March 3, 1837; August 30, 1852; July 8,
1856; and January 21, 1927. For further details, see page 1847,
Annual Report for 1915; page 724, Annual Report for 1937; and
pages 767 and 775, Annual Report for 1938.
   Existing project. This provides for channel dimensions as fol-
lows:
   Between a line one-half mile below the Louisiana Highway Com-
mission bridge at Baton Rouge and the upper port limits of New
Orleans, a distance of 128.6 miles, 35 feet deep (mean low Gulf)
by 500 feet.
   Within the limits of the port of New Orleans, where that author-
ity has jurisdiction over both banks of the river, a distance of 17.2
miles, 35 feet deep (mean low Gulf) and a maximum width of
1,500 feet, measured from a line generally 100 feet from the face
of the left-bank wharves, but not closer than 100 feet to wharves
on the right bank.
474      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

    From the lower limits of the port of New Orleans to the Head of
Passes, a distance of 86.7 miles, 40 feet deep (mean low Gulf) by
1,000 feet wide.
    Southwest Pass from Head of Passes to the outer ends of the
jetties, a distance of 21.2 miles, 40 feet deep (mean low Gulf) by
800 feet wide.
    Southwest Pass bar, 40 feet deep (mean low Gulf) by 600 feet
wide.
    South Pass from Head of Passes to the outer ends of the jetties,
a distance of 14.2 miles, 30 feet deep (mean low Gulf) by 450 feet
wide.
    South Pass bar, 30 feet deep (mean low Gulf) by 600 feet wide.
   The general plan of improvement of Southwest Pass provides
for contracting the pass to a uniform cross section with approxi-
mately 1,420-foot surface width by means of jetties, spur dikes,
and bulkheads; for channel improvement by dredging and retain-
ing the dredged material between the dikes, bulkheads, and jetties;
for dredging a channel through the outer bar inclining to the left
of the jetty axis; for the construction of small revetted openings
through the narrow portions of the banks of the pass for purpose
of strengthening these banks; for closure of minor outlets not
required for maintenance of the banks; for the construction of
sills to prevent the enlargement of the Jump and Cubits Gap; for
dredging to elevation minus 40 feet in the river at Head of Passes,
as far as Cubits Gap, a distance of 3.5 miles; for repairs to sill
across Pass a Loutre and bank revetment at Head of Passes; for
construction of dikes with a view to reducing the width of the
river above Head of Passes; for the construction of a submerged
deflecting dike above the Head of Passes; and for other minor
work. The east jetty is approximately 24,950 feet in length and
the west jetty 19,699 feet. The jetties are composed of a substruc-
ture of brush mattresses, originally built to about the elevation of
mean low water, surmounted with a superstructure of concrete
and large riprap. Spur dikes are composed of cribwork of round
piling filled with willows and stone, or with a curtain of round piles
along the upstream face.
    The general plan of improvement of South Pass provides for the
construction and maintenance of jetties and spur dikes; mainte-
nance of a sill across Pass a Loutre; for dredging a channel 40 feet
deep and no specified width through the shoals of the river between
Cubits Gap and Head of Passes, 31/ miles, and for seaward exten-
sion of east jetty at mouth of pass; removal of west dike and con-
struction of spur dikes and bank revetment at Head of Passes;
removal of false point at the head of South Pass to bottom eleva-
tion of minus 45 feet and revetment of new bank line. The east
jetty foundation is 12,070 feet long; the inner east jetty is 11,170
feet long; the west jetty is 7,820 feet long; and the inner west jetty
is 4,710 feet long. The jetties are composed of a substructure of
brush mattresses surmounted by a superstructure of stone and
concrete. Spur dikes are composed of a cribwork of round piling
filled with willows and stone.
    The plane of reference is mean low Gulf level. Variation of
water surface is 16 inches at the mouths and 10 inches at the heads
             RIVERS AND HARBORS-NEW                           ORLEANS, LA., DISTRICT                      475
of the passes, due to tides. The extreme range of tides at the
mouths of the passes due to storms is about 28 inches. At New
Orleans the extreme range of water surface is about 20 feet due
to floods. At Baton Rouge the extreme range is about 45 feet due
to floods.
   The existing project for Mississippi River, Baton Rouge to the
Gulf of Mexico, La., was authorized by the following River and
Harbor Acts:
     Acts                           Work authorized                                     Documents
Mar.    3,1875 Authorized James B. Eads and associates to create
June   19,1878  and maintain a wide and deep channel, South                 ISpecified in acts.
Mar.    3,1879  Pass.
June   6,19001 For maintenance by the United States and the ap-                  Do.
                propriation of not exceeding $100,000 annually for
                that purpose, South Pass.
June 13, 1902 For a navigable channel in Southwest Pass of 35-foot          H. Doc. 329, 56th Cong., 1st sess.,
                depth, the details of the work subject to modifica-          and Annual Report, 1900, p. 2287.
                tion at the discretion of the Secretary of War.
May 28, 1908 Dredging shoals between Head of Passes and Cubits              Specified in act.
                Gap.
                 1For
                   dredging in the river.._...................
                                                           _                    Do.
    Do.......    SRemovalof west dike and construction of spur dikes        Report by Board of Engineer offi-
              J and bank revetment at Head of Passes.                         cers (Annual Report, 1916, pp.
                                                                              2420-2426).
Mar. 3,1909   Provision made for increasing the plant by the addi-          Specified in acts.
                tion of a large dredge.
       (2)    Further contraction of the lower mile of the jetty            Interim report of board on revised
                channel in Southwest Pass to a width of 1,420 feet            plan for navigation structures,
                by means of dikes, and removal of the sill across             Cubits Gap to the mouth of the
                the head of South Pass.                                       Passes, Oct. 20, 1934.
      (2)     Removal of the sill across the head of South Pass....             Do.
June 26, 1934 For continuing maintenance operations with funds              Permanent Appropriations Re-
                from regular annual War Department appropria-                 peals Act.
                tions, South Pass.
      (3)     Spur dikes at the head of Southwest Pass and the              Second interim report of board on
                construction of new dikes and extension of existing           revised plan for navigation struc-
                dikes on the east bank of the Mississippi River at            tures, Cubits Gap to the mouths
                Pilottown, La.                                                of the Passes, July 12, 1935.
     (4)      Additional spur dikes at the head of Southwest Pass           Final report of board on revised
                and construction of new dikes and extension of                plan for navigation structures,
                existing dikes in the lower jetty channel, South-             Cubits Gap to the mouths of the
                west Pass.                                                    Passes, Dec. 20, 1935.
June 20,1938 Channel 35 feet deep at mean low water and 1,000 feet          H. Doc. 597, 75th Cong., 3d sess.
                wide, Head of Passes to upper limits of the port of
                New Orleans; 35 feet deep and 500 feet wide to a line
                M-mile below river bridge at Baton Rouge, except
                that within the limits of the port of New Orleans
                the channel shall be 1,500 feet wide.
     (5)      Dredging in Mississipp iRiver between Cubits Gap              Interim report of board of officers
                and Head of Passes to bottom elevation of 55 feet             appointed to determine what
                and construction of bank control structures and               work may be advisable to com-
               channel correction dredging in Southwest Pass be-              plete the existing project for
               low mile 10.                                                   Southwest Pass,      Mississippi
                                                                              River * * *; dated June 10, 1938.
       (5)       Improvement at the head of SouthPass by removal of             Do.
                   the false point at this locality to a bottom elevation
                   of at least 45 feet, including revetment of the new
                   bank line.
Mar. 2, 1945     Combines projects of Mississippi River, Baton Rouge        H. Doc. 215, 76th Cong., 1st sess.
                   to New Orleans, Mississippi River, South Pass,            (Contains latest published map.)
                   and Southwest Pass, adding thereto project for
                   Mississippi River from New Orleans to Head of
                   Passes, to provide a single project "Mississippi
                   River, Baton Rouge to the Gulf of Mexico," with
                   channel dimensions as follows: Baton Rouge to
                   New Orleans, 35 feet deep, mean low Gulf, by 500
                   feet wide; port limits of New Orleans, 35 feet deep,
                  mean low Gulf, by 1,500 feet wide; New Orleans to
                   Head of Passes, 40 feet deep, mean low Gulf, by
                   1,000 feet wide; Southwest Pass, 40 feet deep, mean
                  low Gulf, by 800 feet wide; Southwest Pass Bar
                   Channel, 40 feet deep, mean low Gulf, by 600 feet
                  wide; South Pass, 30 feet deep, mean low Gulf, by
                   450 feet wide; South Pass Bar Channel, 30 feet
                  deep, mean low Gulf, by 600 feet wide.

1 Emergency act.
2 Authority of Secretary of War, Oct. 31, 1934.
a Authority of Secretary of War, Sept. 20, 1935.
4 Authority of Secretary of War, July 22, 1936.
5 Authority of Secretary of War, June 30, 1938.
476      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   The estimate of cost for new work (revised in 1954) is $32,885,-
000. The latest (1952) revised estimate of cost for annual main-
tenance is $1,750,000.
   Recommended modification of project. House Document No.
245, 82d Congress, 1st session, provides for construction of two
new features:
       (1) A seaway canal, 36 feet deep and 500 feet wide, extend-
           ing 70 miles as a land and water cut from Micheaud
           southeasterly to Lake Borgne, and across Chandeleur
           Sound to the 38-foot contour in the Gulf of Mexico, with
           protective jetties, a permanent retention dike through
           Chandeleur Sound, and a wing dike along the islands as
           required.
       (2) An inner tidewater harbor consisting of a 1,000 by
           2,000-foot turning basin 36 feet deep at the landward
           end of the seaway canal, and a connecting channel 36
           feet deep and 500 feet wide extending westerly along the
           Gulf Intracoastal Waterway from the turning basin to
           the Industrial Canal.
   The Federal cost of this modification is estimated on the basis
of 1948 prices at $67,000,000 for construction and $1,000,000 an-
nually for maintenance.        The estimated non-Federal cost is
$610,000.
   Local cooperation. None required.
   Terminal facilities. Some 100 piers, wharves, or docks serve
the port of New Orleans. Practically all wharves on the east or
left bank parallel the river bank forming nearly a continuous cov-
ered quay about 10 miles long.
   A foreign trade zone is located in the port of New Orleans.
   Public wharves controlled by the Board of Commissioners of the
port of New Orleans (the dock board) cover 62 percent of the im-
proved water front. The board also controls the terminal facilities
on the Inner Harbor Navigation Canal (the Industrial Canal)
which connects the Mississippi River with Lake Pontchartrain
and turning basin (1,000 by 1,000 feet). Since April 1, 1944, the
portion of the Inner Harbor Navigation Canal from the Missis-
sippi River to its intersection with the New Orleans-Rigolets sec-
tion of the Gulf Intracoastal Waterway, exclusive of terminal fa-
cilities, but inclusive of the lock and the bridges at St. Claude
Avenue and at Florida Avenue, has been under lease to the United
States and is now operated by the United States on a toll-free
basis, 24 hours per day. From the turning basin to the river the
canal has a controlling depth of 30 feet. A quay wharf of rein-
forced concrete, 265 feet wide by 2,400 feet long owned by the
dock board is located on the west bank of the canal.
   All public port facilities are served by paved roadways (gener-
ally city streets) and by the Public Belt Railroad, municipally
owned and operated, which connects with all 12 trunk lines enter-
ing New Orleans.
   The existing terminal facilities include a ship-side grain eleva-
         RIVERS AND HARBORS-NEW ORLEANS, LA., DISTRICT                                          477
tor, general cargo and cotton wharves, fruit landings, bunkering
facilities, terminal warehouses, railroad terminals, marine rail-
ways, and drydocks. They are considered adequate for present
commerce. (For further details see Port Series No. 20, "The Port
of New Orleans, La." 1947.)
   Modern terminal facilities were installed by the city of Baton
Rouge in 1926. A reinforced concrete dock for deep-sea vessels,
308 feet in length, has a covered shed area of approximately 20,000
square feet and is equipped with a 12-ton locomotive crane. At-
tached to the downstream end of the wharf is a floating wharf
boat 231 by 401/2 feet, of 2,000-ton capacity. The facilities are
served by a transfer boat and municipal terminal, having a ca-
pacity of 40 cars per day.
   Private terminals for handling oil and other products are located
at points on both sides of the river between New Orleans and
Baton Rouge.
   The facilities are considered adequate for the existing com-
merce.     (For further details, see "Port Facilities" included in
"Flood Control and Navigation Maps of the Mississippi River,
Cairo, Ill., to the Gulf of Mexico, Louisiana," published by the
President, Mississippi River Commission.)
   Operations and results during fiscal year. No new work was
performed during the fiscal year.
   Maintenance work performed on the project was as follows:
  a. Baton Rouge to New Orleans: Maintenance work consisted of
removing 116,200 cubic yards of material by hired labor and U. S.
dredge Langfitt at Red Eye Crossing, mile 223.0 above Head of
Passes, along the alinement of the front and rear range lights for
a distance of approximately 2,500 feet. Maintenance dredging
was also performed at Medora Crossing, mile 211.5 above Head of
Passes, for a distance of approximately 1,500 feet by hired labor
and U. S. dredge Langfitt, removing 15,278 cubic yards of material.
Maintenance work also consisted of dredging 156,777 cubic yards
of material by hired labor and U. S. dredge Lang fitt at Granada
Crossing, mile 203.0 above Head of Passes, for a distance of
approximately 2,500 feet.
  Reconnaissance surveys were made of Red Eye, Medora, Gra-
nada and Philadelphia Point Crossings, as required.
  Costs for this work were as follows:
   Maintenance by hired labor: Dredging and surveys .. __.................................   $51,559
   b. New Orleans Harbor: Maintenance dredging was accom-
plished by leased dredges Paul F. Jahncke, Tchefuncta, and Pont-
chartrain, removing 1,253,815 cubic yards of material from the
channel to provide project dimensions within the harbor at New
Orleans beyond the 100-foot line from the face of the wharves
along the left bank, from the Public Coal Wharf intermittently
downstream to and including the Bay Petroleum wharf. The
distance actually dredged was 23,430 feet and the following work
was performed:
478              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


                                                                                                                         Cubic
                                                    Location                                                             yards
                                                                                                                        removed

Dredge Paul F. Jahncke:
    Erato-Julia Street wharves_                                  ----------------        ---------------------             2,400
Dredge Tchefuncta:
   Public coal wharf _ _                    ------------------------------------                                          62,415
Dredge Pontchartrain:
   Public coal wharf...             ----------------------------------------------                                        77,140
   Public grain elevator wharf--..-------                        ------------------------------------------               50,550
   Public cotton warehouse wharf --------- -------                                    ---     -----------------------    103,345
   Stuyvesant docks...---------------------------------                                                                  157, 235
   Orange-Robin   Street   wharves        --------------------                                                           149 535
   Erato-Julia Street wharves _-----------                .-                                                             180, 225
   Robin-Poydras Street wharves---- ----                               ----------------------------------------          302,480
   Bienville-Toulouse Street wharves _--------------                           -                                         115,315
   Bay Petroleum wharf..                                                          -----------------------------------
                                                      ...........--------------------                                     53,175



   On November 17, 1947, contract was entered into with the
Board of Commissioners of the Port of New Orleans for a more
efficient and expeditious use of dredges to provide navigable depths
in the project channel in the Port of New Orleans, and within the
100-foot limit along the left bank wharves. On November 17,
1952, a supplemental agreement extended the contract for a period
of five years. During the fiscal year under this reciprocal agree-
ment 35,673 cubic yards were removed by leased dredge Pont-
chartrain from within the 100-foot line and 83,050 cubic yards
were removed by the Board of Commissioners outside the 100-
foot line.
   River traffic signal lights in the vicinity of Westwego, La.,
Gretna, La., and Governor Nicholls Street in New Orleans, to
govern the movement of vessels during flood stages on the Missis-
sippi River in the vicinity of Algiers Point, Port of New Orleans,
were not used during the fiscal year as the highest stage recorded
on the Carrollton gage was 7.6 feet.
   Necessary surveys to determine the condition of the channel in
the harbor were made.
   Costs were as follows:
      Maintenance by contract: Dredging by leased plant---------..----....... .                                    $331, 057
      Maintenance by hired labor: Maintenance of signal light towers ......--                                            917
          Total......       ..
            Total ------------------------------------------------------------------                        -                974
                                                                                                                        331,,97
                                                                                                                        33

   c. Southwest Pass: Maintenance work consisted of dredging
200,875 cubic yards of material by hired labor and U. S. dredge
Langfitt at the Head of Passes for a distance of approximately
2,400 feet along the entrance ranges into Southwest and South
Passes.
   Restoration of structures at east and west headlands, Head of
Passes, was accomplished during the period August 26, 1953, to
February 10, 1954, by contract, when 6,204.56 tons of stone were
placed in restoring 1,120 linear feet of dike at east headland and
580 linear feet of dike at west headland. Approximately 640
linear feet of timber pile trail dikes were built at east headland
and 675 linear feet at west headland.
   Repairs to dike at west headland, Head of Passes, commenced
on March 13, 1954, under contract and are now in progress. Ap-
       RIVERS AND HARBORS--NEW ORLEANS, LA., DISTRICT                                               479
proximately 94 percent of the work had been accomplished at the
end of the fiscal year with 2,760 tons of stone placed in stone dike
over a distance of 650 linear feet and 1,129.67 tons of stone placed
in brush dike over a distance of 400 linear feet.
   At the Southwest Pass Bar and lower jetty channel, mainte-
nance work consisted of dredging 440,673 cubic yards of material
by hired labor and U. S. dredge Langfitt between mile 19.2 below,
Head of Passes and the end of the jettied channel, a distance of
approximately 5,000 feet. Also, at this location between Ranges
152 and 224, a distance of approximately 7,000 feet, 339,352 cubic
yards of material were removed by hired labor and U. S. dredge
A. Mackenzie.
   At mile 13.5 below Head of Passes, maintenance dredging was
performed by hired labor and U. S. dredge Langfitt removing
243,685 cubic yards of material between Ranges 96 and 172 for a
distance of approximately 7,600 feet.
   During the period March 22, 1954, to June 30, 1954, east jetty,
Southwest Pass, was capped for a distance of 1,850 linear feet
by the placing of 14,631.25 tons of stone and restored to grade
and section over a distance of 1,275 linear feet by the placing of
3,980.45 tons of stone, all by contract.
   Repair and maintenance of outlets and miscellaneous structures,
inspections, routine channel surveys, miscellaneous hydraulic in-
vestigations, and examinations and observations were made by
hired labor forces. Shore and floating plant and the Burrwood
reservation were maintained.
Costs were as follows:

   Maintenance by contract:
       Repairs to east and west headland structures, Head of Passes ..-.... $288, 280
       Repairs to east jetty, Southwest Pass .........    ..  .............  281,478
   Maintenance by hired labor:
       Dredging....-----------------------------------------247,279
       Repair and maintenance of outlets and miscellaneous structures....      3,938
       Routine channel surveys, miscellaneous observations and opera-
         tion of Burrwood Base .....     ..
                                        ............     .        .          172, 365
          Total ... .................                             --.------......                 993, 340


  d. South Pass: At mile 2 below Head of Passes, maintenance
work consisted of dredging 202,990 cubic yards of material by
hired labor and U. S. dredge Langfitt between Ranges 52 and 88

'U.
for a distance of approximately 4,000 feet. At South Pass Bar,
    S. dredge Langfitt removed 183,141 cubic yards of material
between the end of the jetties and a distance of 3,700 feet into the
Gulf of Mexico.
  Routine channel surveys and miscellaneous observations were
made.
  Costs were as follows:
   Maintenance by hired labor:
       Dredging.........                  -     -----------------.....                            $42, 865
       Routine channel surveys, miscellaneous observations, and plans and
          specifications .....................                           ------------------         4, 674

          Total ......         ...-........................                                   .    47, 539


     Sig 16-479.510
480                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   e. Cost for collection and compilation of commercial statistics
and processing of permits for the project was $24,476.
  f. Cost for supervision, inspection and reports, and maintenance
of channel patrol from Baton Rouge to the Gulf of Mexico was
$10,864.
  g. Hydraulic surveys, investigations, and studies continued
through fiscal year 1954. Data obtained included complete hydro-
graphic surveys of Southwest and South Passes and the river be-
low Wilder Flats, as required; continuous water-level records at
controlling points throughout the passes; discharge measurements
in each of the three main passes; and gagings of minor outlets.
Periodic surveys were made of Southwest and South Passes, of
both bar channels, at the Head of Passes, at Pass A Loutre, Cubits
Gap, and the New Orleans Harbor.
   Average discharge at each of the three main passes of the lower
Mississippi River in percentages of the total discharge of the river
at the Head of the Passes during the flood cycles are as follows:

                             1945     1946     1947     1948     1949     1950     1951     1952     1953    19541


Southwest Pass....           34.25    34.28    38.15    34.96   36.07     36.24   35.00    35.00    34.96    None
South Pass-------........    18.41    17.36    18.37    18.46   17.43     18.30   20.28    20.65    20.45    made.
Pass a Loutre ..-            47.34    48.36    43.48    46.58   46.50     45.46   44.72    44.35    44.59


       Total-.......        100.00   100.00   100.00   100.00   100.00   100.00   100.00   100.00   100.00

  1 No flood cycle during this year.



   h. The total costs for the fiscal year were $1,459,752 for main-
tenance.
   Condition at end of fiscal year. The project as a whole is 77
 (revised) percent complete.
   a. Baton Rouge to New Orleans, New Orleans Harbor, and New
Orleans to Head of Passes: This portion of the project was com-
pleted in 1940 and maintenance dredging is required at river cross-
ings above New Orleans and in the New Orleans Harbor. Minor
deficiencies in project dimensions at the lower end of Dumaine
Street and Governor Nicholls Street wharves in the New Orleans
Harbor were not corrected because of the presence of revetment
mattresses at these points. Existing depths opposite these loca-
tions are adequate for present and anticipated future commerce.
   The normal width of channel between 35-foot contours within
the limits of the port of New Orleans varies from 1,600 to 2,400
feet. Thalweg depths exceed 100 feet. Shoals along edges of the
channel, which develop at various points during high river stages,
make dredging necessary when river stages fall to maintain proj-
ect depths to wharves along the east bank.
   A natural channel of project dimensions or greater was avail-
able throughout the remainder of this portion of the project.
   b. Southwest Pass: Deepening of the pass and bar channel from
35 to 40 feet, mean low Gulf, as approved by Act of March 2, 1945,
is yet to be performed.
   Maintenance dredging in the Lower Jetty Channel was in prog-
ress at the end of the fiscal year.
             RIVERS AND HARBORS--NEW                              ORLEANS, LA., DISTRICT                                 481

    The east and west jetties have been restored to effective grade
and section.
   East and west headland structures, Head of Passes, have been
restored to effective grade and section.
   All permeable pile dikes for channel contraction are in good
condition.
   For last complete report on the existing works of this pass,
see pages 695-696 of the Annual Report for 1953.
   Channel conditions on June 30, 1954, were as follows:

                                                                                          35-foot channel
                                                                   Length                                           Minimum
                                                                       of                                            central
                                                                   channel          Minimum          Average          depth
                                                                    (miles)          width            width           (feet)
                                                                                      (feet)          (feet)

Entrance channel into head of the pass_ .-----------  ---                    1.0             700             795               38
Through pass from head to sea end of jetties-...........                    19.1             100             670               34
Through bar channel at mouth of pass-.................                       1.3             700             900               37



  c. South Pass: A good channel was available throughout the
length of the pass during the fiscal year with dredging required
only on the bar and at mile 2 below Head of Passes.
  All outlets in the pass should be reinforced with stone to prevent
erosion of banks on the South Pass side. An outlet structure at
mile 7.9 below Head of Passes will be constructed on the right
bank.
  The east jetty has been restored to effective grade and section.
  Work will commence on restoration of the west jetty.
  For last complete report on the existing works of this pass, see
page 696 of the Annual Report for 1953.
  Controlling channel conditions on June 30, 1954, were 34 feet
over the bar channel at the Gulf entrance to the pass.
  Total costs under the existing project to the end of the fiscal
year were $61,133,119 of which $25,296,902 was for new work, and
$35,836,217 for maintenance including $298,283 covering cost of
deferred items.
                                          Cost and financial summary

                                                    Fiscal year ending June 30                                Total to June
                                                                                                              30, 1954, includ-
                                                                                                              ing fiscal years
                                   1950          1951           1952               1953            1954       prior to 19501 2

New work:
   Appropriated-----.---------
    Cost-               -----       $2, 084
                                               1--------------$7,181 ---------------------
                                                 $1,327                50-         ----
                                                                                                                   $27, 026,890
                                                                                                                   20-----------
                                                                                                               -27,026890
Maintenance:
    Appropriated-........        2, 413, 370   1, 897, 627    2, 044, 300     $1,938, 109     $1, 214, 400          36, 074, 968
    Cost.- -------------         2, 261, 103   1, 896, 147    2, 166, 210      1, 806, 707     1, 459, 752          36,005, 272

   1Includes $1,729,989 for new work and $169,055 for maintenance for previous projects.
  SIncluded in maintenance total is $3,379,676 from permanent indefinite appropriationand $298,283 to cover
cost of deferred items.
Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project.................................................... $7, 588, 099
482       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   6. WATERWAY FROM EMPIRE, LA., TO THE GULF OF MEXICO
    Location. Waterway from Empire, La., to the Gulf of Mexico
via Bayous Long and Fontanelle. (See U. S. Geological Survey
map, Empire quadrangle.)
    Existing project. The plan of improvement provides for con-
struction and maintenance of a waterway, 10 miles long, from the
State-owned canal and lock at Empire, La., to the Gulf of Mexico,
to provide a channel 9 feet deep and 80 feet wide, and for the
initial construction of rubble-stone jetties inshore of the 6-foot
depth contour, with landward extensions thereof as required to
prevent flanking, and for seaward extensions to the 9-foot depth
contour if and when it becomes apparent that such extensions will
be more economical than maintenance dredging of the entrance
channel.
    The estimate of cost of new work (revised in 1954) is $2,600,-
000, including $1,534,900 for extension of jetties to the 9-foot
depth contour. The approved estimate of cost for annual mainte-
nance is $40,000.
    The existing project was authorized by the River and Harbor
Act approved July 24, 1946. (See H. Doc. 697, 79th Cong., 2d
sess.) The only published map is in this document.
    Local cooperation. Fully complied with, except for furnishing
of title information, which local interests have partially prepared.
    Operationsand results during fiscal year. Acquisition of rights-
of-way without reimbursement was carried on by hired labor at a
cost of $1,053 for new work.
    Maintenance dredging to restore the channel to project dimen-
sions from mile 0 at the Gulf shoreline to the 9-foot depth contour
in the Gulf of Mexico and from mile 2.2 upstream to mile 3.3, a
distance of 1.65 miles, was accomplished by the contract dredge
Harvey during the period May 21 to June 7, 1954, when 76,997
cubic yards were removed at a cost of $24,318 for maintenance.
Total costs were $25,371.
   Condition at end of fiscal year. The project is physically com-
plete, unless at a later date it is found necessary to extend the
jetties to the 9-foot depth contour.
   Work on the project was initiated on July 31, 1948, and com-
pleted on June 13, 1950, during which period the 9- by 80-foot
channel from Empire, La., to the Gulf of Mexico, 10 miles, was
excavated by contract.
   A total of 3,736 linear feet of jetties was constructed by con-
tract to the 6-foot depth contour, 1,818 linear feet on east jetty and
1,918 linear feet on west jetty, during the period June 23, 1949, to
February 18, 1950.
   The controlling depths, mean low Gulf, were: (June 1954)
From the 9-foot depth contour in the Gulf to mile 9, project dimen-
sions obtain; (December 1953) to mile 10, 7 feet.
   The total costs to the end of the fiscal year were $1,127,425 of
which $1,066,189 was for new work and $61,236 for maintenance.
           RIVERS AND HARBORS--NEW ORLEANS, LA., DISTRICT                                            483
                                      Cost and financial summary

                                               Fiscal year ending June 30                  Total to June
                                                                                           30, 1954, includ-
                                                                                           ing fiscal years
                              1950           1951        1952        1953       1954        prior to 1950
New work:
   Appropriated-........     $500, 000      $118, 000 ..----------------------------------      $1, 100, 000
   Cost...                    809, 045         3, 590     $1, 880     $7, 036    $1, 053          1, 066, 189
Maintenance:
   Appropriated--_                   800       -380       43, 000    -6, 500     27, 300             64, 220
   Cost_ -                           420 -----------
                                         ..               39, 699    -3, 201     24, 318             61, 236

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954............................               $154
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955....--------------------------------------                                         154
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project   --------.........
                                            --............... ................................
                                                                -------..                      1,500,000

                               7. BAYOU LAFOURCHE, LA.
  Location. Prior to 1902 Bayou Lafourche was an outlet of the
Mississippi River, its head being at Donaldsonville, La., 80 miles
above New Orleans. It flows in a general southerly direction to the
Gulf of Mexico, a distance of 107 miles. (See U. S. Coast and
Geodetic Survey Charts Nos. 1116 and 1274; Corps of Engineers,
Mississippi River Commission alluvial valley map; Donaldsonville,
White Castle, Napoleonville, Thibodaux, and Lac des Allemands
quadrangles; and United States Geological Survey maps Houma,
Cut-Off, Lake Felicity, Mink Bayou, Leeville, and Belle Pass quad-
rangles.)
  Previous projects. Authorized by River and Harbor Acts of
June 18, 1878, and August 11, 1888. For further details, see page
850 of Annual Report for 1915, page 833 of Annual Report for
1925, and page 791 of Annual Report for 1938.
  Existing project. This provides for the permanent closure of
the head of the bayou, without a lock; for a channel 6 feet deep
and 60 feet wide from Napoleonville to the Intracoastal Waterway
at Lockport; and a channel of same dimensions from the Intra-
coastal Waterway at Larose to the Gulf of Mexico via Belle Pass;
the closure of Pass Fourchon; and for a jettied entrance at the
mouth of Belle Pass. The total length of improvement is about
79.25 miles. Under ordinary conditions the mean range of tide is
about 3 inches at the head and 10 inches at the mouth of the bayou.
Tropical hurricanes have been known to cause a variation of 10
feet at the mouth and severe rains and overflow have caused a
variation of 3 to 10 feet at the head.
  The estimate of cost for new work (revised in 1954) is $1,110,-
000. The latest (1952) approved estimate of cost for annual main-
tenance is $50,000.
  The existing project was adopted by the River and Harbor Act of
August 30, 1935 (H. Doc. 45, 73d Cong., 1st sess.). The latest
published map is in the project document.
 484               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Local cooperation. Fully complied with.
   Terminal facilities. There are numerous private warehouses
and wharves and stiff-leg derricks for handling cane along the
bayou. At Thibodaux there is a dock with freight transfer and
warehouses. At Lockport the Barker Barge Line has a large wharf
with covered shed, and the Southern Pacific Railroad maintains a
large wharf with covered shed. At Golden Meadow each of the
seafood canneries has docking facilities suitable for its needs.
Four oil companies have docks at Leeville for transferring the
production of the Leeville oilfields to barges. The terminal facili-
ties are considered adequate for existing commerce.
   Operations and results during fiscal year. Hired labor carried
on engineering surveys, mapping, stream gaging, and channel
patrol at a cost of $3,422.
   Cost for collection and compilation of commercial statistics and
processing of permits for the project was $7,462.
   Repair of the jetties at Belle Pass between stations 0+00 and
-5+68 by buttressing the sheet pile sections by placement of
stone, in progress at the beginning of the fiscal year, was com-
pleted on August 20, 1953. During the fiscal year 6,697 tons of
stone were placed in repairing east jetty between stations -3+00
and -5+68 and -2+00 and 2+20, and west jetty between sta-
tions -2+70 and -5+69.         The groin was extended from station
-1+20 to -2+40 seaward, all at a cost of $91,269. The total
costs were $102,153 for maintenance.
   Condition at end of fiscal year. The existing project is 24 (re-
vised) percent complete.
   The dredging between Larose, La., and the Gulf of Mexico was
completed in 1939. The jetties at the mouth of Belle Pass were
completed in 1939, but were subsequently damaged by storm action,
which required the placement of additional stone adjacent to both
sides of the steel sheet pile jetties in 1940, and the repair and
extension of the jetties in 1941.
   During the fiscal year 1948 the stone jetties were repaired and
extended inland about 700 feet from the shoreline; and the steel
sheet pile section was strengthened, for about 250 feet Gulfward of
stone jetties, by the placement of stone on both the Gulf and bayou
sides. On May 31, 1949, an automatic tide gage for recording
hurricane and storm tides was installed.
   Since 1948, the following repairs have been made to the jetties
at Belle Pass:
Fiscal                              Stone placed,                                                                        Repairs,
year                                   tons                                        Location                            linearfeet

1952...--.......---.......---. 3,326.65.......................---------------east jetty ..................................--------------    315
1953........     ............. 7,096.90----------------.......................      west jetty               -.... .                        298
                                                                                                                                   ....--------------
                                                  ---------.............
                                                                       ....         east jetty ..................................-------------
                                                                                                                                            508
1954.... .... .............-----------------..
                                 6,697.09 ..-- -------..           --.............. west jetty.. -------------................................
                                                                                                                                            298
                                                ---------....................       in groin---..------................................-----120
  Work remaining to be done under the existing project consists of
dredging the project channel between Lockport and Napoleonville,
La.
  The controlling depths, mean low Gulf (May 1954) were: Over
bar, 7 feet; through Belle Pass, 7 feet; to Havoline Canal, 6 feet; to
              RIVERS AND HARBORS--NEW                                  ORLEANS, LA., DISTRICT                               485

Leeville, 7 feet; to Golden Meadow, 8 feet; to Larose, 7 feet; to
Lockport (mile 56), 7 feet; (January 1953) to Thibodaux, 4 feet;
to one-half mile above Thibodaux, 2 feet (dead vegetation blocks
channel above this point).
  The total costs under the existing project to the end of the fiscal
year were $833,863, of which $271,089 was for new work and
$562,774 for maintenance.
                                            Cost and financial summary

                                                       Fiscal year ending June 30                                  Total to June
                                                                                                                  30, 1954, includ-
                                                                                                                  ing fiscal years
                                     1950            1951             1952            1953            1954         prior to 1950'
New work:
   Appropriated-ot...------------..------------.------------------------------------                                     $524, 024
   Cost----------        ------------------------     -----------------------  ----------                              -- 524,024
Maintenance:
    Appropriated........                 $174        $52, 480         $3, 000        $221, 105      -$15,   000           578, 598
     Cost-----------------              1, 809         5,882           55, 602        104, 577        102, 153            578, 219

   1Includes $252,935 for new work and $15,445 for maintenance for previous projects.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project.................. ............................ $838, 911

                                            8. BAYOU TECHE, LA.
   Location. Bayou Teche has its source in Bayou Courtableau, in
St. Landry Parish, and flows in a southeasterly direction, a distance
of 125 miles, to where it joins the lower Atchafalaya River, about
101/2 miles above Morgan City, La. (See U. S. Coast and Geodetic
Survey Chart No. 1116, and Corps of Engineers, Mississippi River
Commission alluvial valley map, and Palmetto, Opelousas, Caren-
cro, Arnaudville, St. Martinville, Loreauville, Derouen, Jeanerette,
Foster, and Belle Isle quadrangles.)
   Previous projects. Authorized by River and Harbor Acts of
July 11, 1870, and September 19, 1890. For further details, see
page 1851, Annual Report for 1915, and page 798, Annual Report
for 1938.
   Existing project. This provides for a channel 8 feet deep and
80 feet wide on the bottom from the mouth of the stream to New
Iberia, La., 54.5 miles, thence 6 feet deep and 60 feet wide on the
bottom to Keystone lock, 18 miles, and thence 6 feet deep and 50
feet wide on the bottom at Arnaudville, La., 34 miles, to be secured
by dredging, removing snags and overhanging trees, and construc-
tion of a lock and dam and regulating works. The plane of refer-
ence is mean low Gulf level.
                                                       Keystone lock
Miles from New Iberia ..              ...........................------------------------------ -    18.
Miles from Intracoastal Waterway .. __.-....-....................                                    82.5.
Width of chamber .....                   ----------------------------------                          36 feet.
Length available for full width...-.-.....................                                 _         160 feet.
Lift ....................-------------------------------------------                                 8 feet.
Depth on miter sill at mean low Gulf level-..__-.--...                   -.........    . ___....           Do.
Character of foundation-                     .     .
                                          ----------.... .        .              .                .. Timber piles.
Kind of dam                -..       ------------------------...------. Timber, rock-fill.
Type of construction--..---.....                   ........       ........................--------------------------
                                                                                                     Concrete.
Year completed......-------------.....................--------------------.......................... 1913.
Cost ..... ..... ......        ..................               . .......................... ..      $257,720.
486               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   The raising of the pool level by 1.5 feet above Keystone Dam by
the installation of movable crest gates on the dam is provided for
in the flood-control project for Bayou Teche and Vermilion River,
La. Under the project "Flood control, Mississippi River and tribu-
taries," East and West Calumet floodgates, with a width of 60 feet
and sill elevation of -9.02 feet, mean low Gulf level, were con-
structed in Bayou Teche at the east and west approaches to Wax
Lake Outlet during the period February 21, 1949, and September
22, 1950, and a lock was constructed in the lower Atchafalaya River
in the vicnity of Berwick, La., during the period November 16,
1948, and September 7, 1951.
                                                  Berwick lock
Miles north of Berwick, La ..-.........                                                   1.7.
Miles below mouth of Bayou Teche..................                                        9.0.
W idth of chamber...... ... ... ..... .. .. .. .. .. .. ..                                45 feet.
                                                                                   ..--------------
Length available for full width.............------------........                          300 feet.
Lift .....                                                                                          feet.
                                                                                          0-------0-14.5
                                                                                          0----------------.-----
Depth on miter sill at mean low Gulf level                                                9.0.
Character of foundation                                -              -.....
                                                                  -.....    ....          Timber piles.
Kind of dam -......................  . ..                                                 None.
Type of construction -....-..-.. . . . . . . . . .                                  .     Reinforced concrete.
Open to navigation                                               -.............           November 1950.
Completed                                                        --..                     September 1951.
                        .. ... . . .. . .. . . . .. . . ..
Cost------------........-$....                                                            $2,100,000.

   Under ordinary conditions the mean range of tide is about 10
inches at the mouth, 4 inches just below the lock, and zero above
the lock, the extreme range of tide being about 12 inches, 6 inches,
and zero, respectively. The variation of the water surface above
Keystone lock due to freshets is from 2 to 7 feet, while just below
the lock it has been as high as 12 or 15 feet and near the mouth
about 4 or 5 feet.
   The estimate of cost for new work (revised in 1953) is $1,064,-
000, exclusive of amount expended on previous projects. The
latest (1950) approved estimate for annual cost of maintenance
from mouth to Arnaudville is $12,000, plus $21,000 for operating
and care of the lock and dam.
   The existing project was authorized by the following River and
Harbor Acts:

     Acts                            Work authorized                                      Documents

Sept. 19, 1890    Improvement of the stream from its mouth to St.              Annual Report, 1889, p. 1532.
                    Martinville by removing obstructions and dredg-
                    ing.
Mar.    2,1907    Construction of lock and dam and the extension of            H. Doc. 527, 59th Cong., 1st sess.
                    the improvement to Arnaudville, La.
Mar.    2, 1919   Increase of channel dimensions from mouth to Key-            H. Doc. 1329, 62d Cong., 3d sess.
                    stone lock.
June 26, 19341    Operation and care of lock and dam provided for
                   with funds from War Department appropriations
                    for rivers and harbors.

  1 Permanent Appropriation Repeal Act.
  For latest published map, see H. Doc. 288, 66th Cong., 1st sess.
        RIVERS AND HARBORS-NEW ORLEANS, LA., DISTRICT               487
   Local cooperation. Fully complied with.
   Terminal facilities. Small, privately owned wharves are avail-
able at all the towns along the bayou; public landing is permitted
without charge. There are privately owned terminals for trans-
ferring crude oil to barges near the towns of Charenton, Jeanerette,
Olivier, and St. Martinville. The facilities are considered adequate
for existing commerce.
   Operations and results during fiscal year. Design drawings
and specifications were completed by the Lower Mississippi Valley
Division office and hired labor made a condition survey for main-
tenance dredging and accomplished noncooperative stream gaging.
   Keystone lock was operated throughout the fiscal year, and the
lock, dam, structure, and grounds were maintained, as necessary.
   The total costs were $21,722, of which $7,689 was for mainte-
nance and $14,032 for operating and care.
   Condition at end of fiscal year. The existing project is approxi-
mately 67 percent complete.
   Keystone lock and dam were completed in 1913. The dredging
and snagging done in 1916 completed that part of the existing
project for the 6- by 50-foot channel from Arnaudville to Keystone
lock. The contract dredging done in 1918-20 completed that part
of the previous project for a 6- by 50-foot channel from Keystone
lock to mile 39.7 above the mouth. The 8- by 80-foot channel from
New Iberia to the mouth is 98 percent complete. From the mouth
to mile 5.8 a channel 8 by 80 feet, or greater, already existed, and
a new channel has been excavated, 8 by 80 feet from this point to
mile 50.06, about 3.65 miles below New Iberia, and 8 by 60 feet
from this point to New Iberia.
   The work required to complete the existing project is the widen-
ing of channel to a bottom width of 80 feet from mile 50.06 to New
Iberia, and to a bottom width of 60 feet from New Iberia to Key-
stone lock.
  Keystone lock is in good condition. Plans and specifications for
a new concrete cap on the existing dam at Keystone lock to raise
the existing structure have been completed.
  The controlling depths, mean low Gulf (October 1953), were:
From mile 0 to mile 8, 6 feet; to mile 20, 7 feet; to Charenton
Drainage Canal (mile 29.5), 7.8 feet; to west side "Y" Charenton
Drainage Canal, 2.8 feet; to mile 33, 12.7 feet; to New Iberia (mile
54.5), 6 feet; to Keystone lock (mile 72), 5 feet; to mile 87.5, 7 feet.
  The total costs under the existing project to the end of the fiscal
year were $1,396,922, of which $708,625 was for new work, $346,-
493 for maintenance, and $355,836 for operating and care. In
addition, the sum of $91,389 was expended between July 1, 1913,
and June 30, 1935, on the operation and care of the works of im-
provement under the provisions of the permanent indefinite appro-
priation for such purposes.
488             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                          Cost and financial summary

                                                    Fiscal year ending June 30                           Total to June
                                                                                                        30,1954, includ-
                                                                                                        ing fiscal years
                                   1950          1951           1952           1953          1954         prior to 19501

New work:
  Appropriated........  ------------------------------------------------------------                             $754, 330
                                  --... ----------- ---------------------------
   Cost-----------------..............                                                                            754, 330
Maintenance:
    Appropriated--------........   $22, 000      $35, 880       $19, 000       $18,953       $22, 000            803, 051
    Cost-----------------           18, 645       24, 992        25, 078        21, 319       21, 722            793, 719


   i Includes $45,704 for new work for previous project; operating and care work includes $91,389 permanent
indefinite appropriation.
Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project.............. ...................------...............----------... $355, 375

    9. MERMENTAU RIVER, BAYOU NEZPIQUE, AND BAYOU DES
                        CANNES, LA.
   Location. Mermentau River is formed by the junction of
Bayous des Cannes and Nezpique, 2.25 miles above Mermentau,
La., flows in a' southwesterly direction, and empties into the Gulf
of Mexico.
   Bayou Nezpique rises in Evangeline Parish, flows in a southerly
direction, and empties into the Mermentau River.
   Bayou des Cannes rises in Evangeline Parish, flows in a south-
southwesterly direction, and empties into the Mermentau River.
 (See U. S. Coast and Geodetic Survey Charts Nos. 1116 and 1278,
and U. S. Geological Survey maps, Evangeline, Hathaway, Mer-
mentau, Jennings, Lake Arthur, Gueydan, Thornwell, Latania
Lake, Catfish Lake, Grand Cheniere, and Bayou Lebauve quad-
rangles.)
   Existing project. The projectprovides for the removal of ob-
structions to navigation to secure the natural channel throughout
the entire Mermentau River, a distance of 71.5 miles, and through
Bayou Nezpique from its mouth to 25 miles above, and Bayou des
Cannes from its mouth to Evangeline Bridge (mile 8.5); for im-
proving the channel in Lower Mud Lake by constructing a brush
dam to concentrate the action of the current and by dredging; and
for removing a portion of the wrecked dam 7 miles above the
mouth; and for dredging a channel 9 feet deep over a bottom width
of 100 feet from the Intracoastal Waterway to the junction of
Bayous Nezpique and des Cannes.
   That part of the project below Grand Lake, mile 25, has been
superseded by the flood control project "Mermentau River, La."
   Under ordinary conditions the mean range of tide on the Mer-
mentau River near the mouth is 10 inches and near the head about
3 inches, the extreme range being 14 inches and about 5 inches,
respectively. The variation of the water surface near the mouth
may be as much as 7 or 8 feet, due to hurricanes on the Gulf, and
near the head from 8 to 12 feet, due to freshets. On Bayou Nez-
pique, under ordinary conditions, the range of tide is about 3
inches at the mouth and nothing at the head. On Bayou des
Cannes, under ordinary conditions, the range of tide is about 3
inches at the mouth and nothing at the head.
             RIVERS AND HARBORS-NEW ORLEANS, LA., DISTRICT                                                489

  The cost of new work for the project, completed in fiscal year
1935, was $57,555, including $29,974 from public works funds.
The latest (1950) approved estimate of cost for annual mainte-
nance is $2,500.
  The existing project was authorized by the following River and
Harbor Acts:

     Acts                         Work authorized                     .              Documents
July 13,1892     General project-------------   ------------------        Annual Report, 1891, p. 1862.
July 27,1916     Removal of portion of wrecked dam near mouth of          H. Doc. 1232, 64th Cong., 1st sess.
                   Mermentau River.
Mar. 2,1919      Improvement of Bayou des Cannes..................        H. Doc. 1398, 65th Cong., 3d sess.
Aug. 30, 19351   Channel in Mermentau River 9 feet deep plus 1 foot       Rivers and Harbors Committee
                   overdepth from Intracoastal Waterway to the              Doc. 36, 72d Cong., 1st sess.
                   source at confluence of Bayous Nezpique and des          (Contains latest published map.)
                   Cannes.

  'Included in the Public Works Administration program Mar. 28, 1934.

   Local cooperation. Fully complied with.
    Terminal facilities. There are several small, privately owned
wharves at Grand Cheniere and a public terminal at the town of
Lake Arthur. At Mermentau, La., the Southern Pacific Railroad
owns a wharf served by a spur track. Privately owned terminals
for transferring crude oil to barges are at the following locations:
One on Lake Arthur near the town of Lake Arthur; 1 on the Mer-
mentau River near the town of Mermentau; 2 on Bayou Nezpique
near Jennings; and 4 on Bayou des Cannes, 1 near Evangeline, 1
at Mermentau, and 2 near Jennings. The facilities are considered
adequate for existing commerce.
   Operationsand results during fiscal year. Preparation of plans
and specifications for maintenance dredging was accomplished by
hired labor at a cost of $9.
   Cost for collection and compilation of commercial statistics and
processing of permits for the project was $1,036.
   Channel improvement of Mermentau River to remove a point
just below the Southern Pacific Railroad bridge, was commenced
under contract on April 27, 1954, and at the end of the fiscal year
20,699 cubic yards had been removed by dragline over a distance of
708 linear feet; however, a considerable amount of this material
has to be rehandled to comply with requirements for spoil disposal
and some sections of the channel will require additional dredging.
The costs incurred for this work amounted to $7,082. The total
costs were $8,127 for maintenance.
   Condition at end of fiscal year. The existing project, except for
the 9- by 100-foot channel, was completed in 1917. The 9- by 100-
foot channel was completed in 1935.
   The controlling depths, mean low Gulf, were (June 1954)
Mermentau River: Over bar, 4 feet; to mile 0, 10 feet; through
cut in Lower Mud Lake to Upper Mud Lake, 7 feet; to Catfish
Point, 6 feet; to Gulf Intracoastal Waterway through Grand Lake,
2.5 feet; (April 1953) dimensions exceeding those of the project
obtain through the rest of the waterway to the head of navigation
at mile 71.5; Bayou Nezpique: Mile 0 to Mile 9.5, 17 feet; Bayou
des Cannes: Mile 0 to mile 5, 12.5 feet.
  The total costs (regular funds) under the existing project to the
490                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

end of the fiscal year were $112,358, of which $27,580 was for new
work and $84,778 for maintenance. In addition, $29,974 was ex-
pended for public works funds for new work.
                                              Cost and financialsummary

                                                        Fiscal year ending June 30                                   Total to June
                                                                                                                    30, 1954, includ-
                                                                                                                    ing fiscal years
                                       1950           1951        1952          1953               1954               prior to 19501

New work:
      Appropriated          -.                                                             -$57,         .                       555
          ---------------------
      Cost..        __                         '   --- -- -         --   ----   -      -    -       -        -57,                555
Maintenance:
      Appropriated                _     $1, 500                                 $35, 886        -$20,      000                91, 663
      Cost ..........              .     1,507 .874                                                     8, 127                84, 778

  1   Includes $29,974 from public works funds, new work.


                                  10. CALCASIEU RIVER AND PASS, LA.
  Location. Calcasieu River has its source in southwestern
Louisiana, and flows in a general southerly direction to the Gulf
of Mexico. About 25 miles from the Gulf it debouches into Cal-
casieu Lake, which lake is about 18 miles long. The connection be-
tween the lake and the Gulf, about 7 miles long, is known as
Calcasieu Pass. (See U. S. Coast and Geodetic Survey Charts Nos.
591 and 592; U. S. Geological Survey maps, Edna, Thompson Bluff,
Hecker, Moss Bluff, Lake Charles, West Lake, Moss Lake, Hack-
berry, Sweet Lake, Brown's Lake, Holly Beach, Grand Bayou and
Cameron quadrangles; and Corps of Engineers navigation maps
of Intracoastal Waterway and Atchafalaya River system.)
  Previous projects. The original project for this improvement
was adopted by the River and Harbor Act of June 10, 1872. Ap-
propriations were made by the River and Harbor Acts of March 3,
1881, August 2, 1882, July 5, 1884, and August 11, 1888. The proj-
ect was modified by the River and Harbor Acts of September 19,
1890, July 13, 1892, and September 22, 1922. For further details,
see Annual Report for 1936, page 719, and Annual Report for 1938,
page 819.
  Existing project. This provides for a channel 35 feet deep and
250 feet wide (49.5 miles long) from the wharves of the Lake
Charles Harbor and Terminal District by way of Calcasieu River
including Clooney Island Loop, to the head of Choupique cutoff;
thence by a land-and-water cut along the west shore of Calcasieu
lake; thence to and through Calcasieu Pass by a designated route
to the Gulf of Mexico, subject to such change in alignment as is
approved by the Chief of Engineers; the reconstruction and exten-
sion of the existing jetties initially to the seaward end of the east
jetty, and further extension to the 15-foot depth contour if found
advisable to reduce maintenance dredging costs; dredging a channel
35 to 37 feet deep and 250 feet wide between jetties, and an ap-
proach channel 37 feet deep and 400 feet wide from the sea end of
the jetties to a depth of 37 feet in the Gulf of Mexico; also for the
improvement of the river from Lake Charles to Phillips Bluff (52.6
miles) by removing logs, snags, overhanging trees, and by dredg-
ing. Total length of improvement is 102.1 miles. Under ordinary
             RIVERS AND HARBORS--NEW ORLEANS, LA., DISTRICT                                              491
conditions, the mean range of tide is 10 inches at the mouth, dimin-
ishing to zero at Phillips Bluff, the extreme range being 14 inches
and zero, respectively.
  The estimate of cost for new work, including $5,783,400 for the
extension of the jetties to the 15-foot depth contour (revised in
1954), is $13,646,000. The latest (1952) approved estimate for
cost of maintenance is $278,000 annually.
  The existing project was authorized by the following River and
Harbor Acts:

    Acts                           Work authorized                                      Documents

                 Modification of original project of 1872, dated May 12,   H.      Ex. Doc. 46, 46th Cong. 3d
                   1881, provided for general improvement of the river          sess.; and Annual Report 1881,
                  from Phillips Bluff to the mouth by removing logs,            p. 1301.
                  snags, and overhanging trees, and by dredging.
Aug. 26, 1937    Channel 30 feet deep and 250 feet wide from the Lake      H. Doc. 299, 75th Cong., 1st sess.
                  Charles docks to the Gulf of Mexico.
Mar.   2, 1945   Channel 30 feet deep and 250 feet wide around Cloo-       H. Doc. 465, 77th Cong., 1st sess.
                   ney Island.
July 24,1946     Channel depth of 35 feet from the wharves of the Lake     S. Doc. 190, 79th Cong., 2d sess.
                  Charles Harbor and Terminal District, including            (Contains latest published map.)
                  Clooney Island Loop, to the jetty channel, a uni-
                   formly increasing depth of 35 to 37 feet in the jetty
                   channel, and a depth of 37 feet in the approach
                   channel in the Gulf of Mexico.



    Local cooperation. Fully complied with.
    Under date of January 5, 1922, a permit was granted by the As-
sistant Secretary of War to the police jury of Calcasieu Parish to
enlarge this river where necessary between Lake Charles and the
eastern end of the Calcasieu-Sabine section of the Intracoastal Wa-
terway to a depth of 30 feet over a bottom width of 125 feet.
    Terminal facilities. Terminal facilities at the Port of Lake
Charles are owned by the Lake Charles Harbor and Terminal Dis-
trict and operated by a board of commissioners. In addition to the
municipally owned terminals, there are several privately pwned and
operated wharf structures located on the existing ship channel.
 (For further details, see Port Series No. 21, "The Port of Lake
Charles, La.," revised 1947.)
    Operations and results during fiscal year. Hired labor forces
carried on the following new work activities during the fiscal year:
Acquisition of rights-of-way for spoil disposal areas, engineering,
surveys and mapping, and gages and observations, at a cost of
$11,824.
    Work on the lump sum contract for the construction of ferry
approaches, State Highway No. 104 ferry over Calcasieu Pass, en-
tered into with the State of Louisiana, Department of Highways,
in the previous fiscal year was started on September 21, 1953, and
at the end of the fiscal year was 70 percent complete, with costs of
$42,917 for new work.
   Hired labor carried on condition surveys, channel patrol, and
acquisition of rights-of-way, with costs of $19,518 for maintenance.
    The U. S. dredge Langfitt removed 503,427 cubic yards during
the period October 17 to 27 and December 8 to 18, 1953, in dredg-
ing shoals from the approach channel and bar of Calcasieu River
and Pass, at a cost of $78,090 for maintenance.
   Funds in the amount of $500 were transferred to the U.S.
492          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Geological Survey as the project's pro-rata share of costs for opera-
tion of the cooperative stream-gaging program.
   Costs for collection and compilation of commercial statistics and
processing of permits for the project were $8,270.
   Approximately 8,377,832 cubic yards were removed from Cal-
casieu River during the period August 1953 to April 1954 in re-
storing project depth between miles 5 and 27 and 32.9 and 33.3,
at a cost of $649,297 for maintenance, with 4,953,088 cubic yards
having been removed by the contract dredge Mansfield and 3,427,-
744 cubic yards by the contract dredge C. B. Harris.
   Total costs for the fiscal year were $810,415, of which $54,740
was for new work and $755,675 was for maintenance.
   Condition at end of fiscal year. The project as modified is 94
percent complete, exclusive of extending the jetties seaward to the
15-foot depth contour, if and when found necessary.
   Dredging under the existing project, prior to the modifications
adopted by the River and Harbor Acts of March 2, 1945, and July
24, 1946, was completed in 1941, and the 30- by 250-foot ship chan-
nel was formally opened to deep-draft traffic on July 12, 1941.
   Work on the modified project of deepening the 250-foot channel
to 35 feet from Lake Charles to the 37-foot depth contour in the
Gulf of Mexico was initiated on September 7, 1948, and completed
on April 25, 1953. This work was accomplished as follows:

85- by 250-foot channel from Lake Charles Harbor
  downstream:                                              Commenced           Completed
To Gulf Intracoastal Waterway, mile 12.8,                Sept. 7, 1948      Feb.   2, 1949
  dredge Texas.
From Gulf Intracoastal Waterway, mile 12.8               Sept.    5, 1949   Apr.    6, 1950
  to mile 24.1, dredge Duplex.
From mile 24.1 to mile 30.4, and dredging in             Feb.    10, 1949   May    11, 1949
  the 6- by 20-foot connecting channel, dredge
  Texas and two draglines.
From mile 30.4 to mile 32, dredge Mobile..............   July    26, 1950   Aug.    6, 1950
A survey showed that project depths obtained             Oct.    15, 1950   Apr.   25, 1953
  between miles 32 below Lake Charles and
  the approach channel, a distance of approxi-
  mately 5 miles. Deepening existing approach
  channel to -37 feet, mean low Gulf, from
  inside jetties to the 37-foot depth contour in
  the Gulf of Mexico, a distance of about 11 miles,
  U.S. dredge Langfitt.

   A turning basin or ship anchorage for vessels using the water-
way was constructed during the period April 26 and June 1, 1952,
between St. John's Island and vicinity of Cameron, La., a distance
of approximately 1.1 miles.
   The Calcasieu Pass jetties, initiated under the previous project
and completed in May 1942, extend to the 10-foot depth contour
and are in good condition. The east jetty, approximately 8,620 feet
long, has been built to approximately 6 feet above mean low Gulf,
and extends seaward from the existing Gulf shoreline a distance of
            RIVERS AND HARBORS--NEW ORLEANS, LA., DISTRICT                                                       493
6,820 feet. The west jetty, 8,050 feet long, has been built to ap-
proximately 4 feet above mean low Gulf and extends seaward from
the existing Gulf shoreline a distance of 6,795 feet.
   The jetty structure is considered complete unless at a later date
it is found necessary to extend the jetties seaward to the 15-foot
depth contour, as provided for in the project.
   Work remaining to be done to complete the project consists of
completing construction of approaches to ferry crossing Calcasieu
Pass, now in progress; improving navigation conditions in the wa-
terway by means of channel rectification between approximate
miles 25.5 and 28.7, and extending the jetties seaward to the 15-
foot depth contour, if and when found necessary.
   The controlling depths, mean low Gulf, were: (December 1953)
bar channel, 37 feet; (June 1952) end of jetties to mile 5, 35 feet;
 (April 1954) to mile 33.3, 35 feet; to mile 54, 15 feet; to mile 58, 12
feet; to mile 64, 9 feet; to mile 66.0 (Hecker), 12 feet; to mile 71.4,
4 feet (non-navigable above this point, due to snags and trees).
   The total costs of the existing project to the end of the fiscal year
were $9,280,612, of which $7,372,033 was for new work and $1,-
908,580 was for maintenance.
                                     Cost and financial summary

                                             Fiscal year ending June 30                                 Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                              1950         1951             1952           1953             1954        prior to 19501
New work:
   Cost..----    ------       867,148      466, 933        216, 452       $561,   620    . $54, 740           7, 867, 946
Maintenance:
   Appropriated........        77, 000       2, 360-    ..--...       .    400, 000         356,000           2,103, 756
   Cost_........_.._..          1,405        7, 955 -.-......-.-..        -....    -..      755, 675          2, 103, 430

  1Includes $495,914 for new work and $194,851 for maintenance for previous projects.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954------------........... ---............
                                                                                       $662
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955------...............--..........--......--................           6662
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project-......-......--....
                                            .. ...........                        5,802, 305
                                                     ..................................

          11. REMOVING THE WATER HYACINTH (LOUISIANA)
   Location. Lakes and streams tributary to the Gulf coast.
   Existing project. This project provides for the removal of
plants from the navigable waters of the States of Florida, Ala-
bama, Mississippi, Louisiana, and Texas, so far as they are or may
become an obstruction to navigation, by any mechanical, chemical,
or other means whatsoever; for the construction and operation of
boats equipped with suitable machinery for such removal; and for
the construction and operation of booms to prevent the drifting
of plants from one stream to another. The latest (1950) approved
estimate for annual cost of maintenance is $500,000.
494             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

The existing project was authorized by the following River and
Harbor Acts:

    Acts                           Work authorized                                   Documents

Mar. 3,1899      Made appropriations for the States of Florida and        H. Doe. 91, 55th Cong., 3d sess.
                    Louisiana and provided for the extermination or
                    removal of plants, the building of boats, and the
                    establishment of booms.
June 13, 1902     Authorized the use of mechanical, chemical, or other
                    means whatsoever.
Mar. 3,1905       Made the appropriation available for the State of
                    Texas.
Mar. 3,1905      (In making appropriations for Florida, provided that.
Mar. 2,1907     l no chemical process injurious to cattle shall be used
July 25,1912      Made the appropriation available for the State of
                    Mississippi and also made available for use in that
                    State the operating plant pertaining to the work in
                   Louisiana.
July 27,1916     Made the appropriation available for the State of
                   Alabama.



   Local cooperation. None required.
   Terminal facilities. The terminal facilities of the various
streams from which hyacinths were removed are described in the
report for the improvement of these streams.
   Operationsand results during fiscal year. A well balanced com-
bination of mechanical and chemical methods of destruction was
undertaken to take the maximum advantage of funds available.
Economics in effect resulted in curtailed operations and limited
the work to only those main waterways over which the major
portion of navigation moves. Preventive maintenance work in
secondary streams and feeder areas was sharply curtailed with
a resultant increase in vegetation in these areas. Some momen-
tary inconvenience was caused at times when this vegetation dis-
gorged into the main streams after a heavy squall. Feeder areas
previously freed of the hyacinth and placed on a patrol mainte-
nance basis have now become heavily infested with alligator weed
which has not proved susceptible to chemical treatment.
   A total of 39,527,834 square yards of vegetation was destroyed
by chemicals and 8,814,750 square yards by machinery in Bayou
Black, Lake Cataouatche and feeder streams, streams of the Lake
des Allemands ,Basin, the Lake Dauterive area, the Intracoastal
Waterway, Bayou Lafourche, streams of the Lake Maurepas
Basin, the Bayou Penchant-Bayou Copassaw area, the Plaquemine
Waterway, and in Bayous Teche, Misere, and Lacassine.
   Operations were conducted on a curtailed schedule with the
work being confined to the main navigational channels on a re-
curring basis. Some handicap to navigation resulted. No perma-
nent results can be expected on this basis as work must be
accomplished in feeder areas and secondary streams if complete
reinfestation of the main channels is to be avoided. Operations
were conducted only in areas where severe hardship would have
resulted if the work had not been undertaken.
   The total costs to the end of the fiscal year were $222,248 for
maintenance.
   Condition at end of fiscal year. From 1900 to 1902 a boat with
suitable machinery for destroying the hyacinth by crushing was
operated.           From that time until 1937 hyacinths were destroyed
                RIVERS AND HARBORS-NEW ORLEANS, LA., DISTRICT                                                                  495
through the use of a solution of arsenic and caustic soda which
was sprayed on the vegetation, removal by hand crews and con-
trolled in their movements by means of booms and barricades.
The use of arsenic has been discontinued and hand removal has
been supplanted by use of mechanical equipment in conjunction
with the chemical spray (2,4-Dichlorophenoxyacetic acid). Pres-
ent methods of control are by means of mechanical rotary saw
type destroyers, chemical treatment, and the use of booms and
barricades. Excellent results are being obtained on water hya-
cinths by these methods.
   The total costs to the end of the fiscal year were $3,982,078 for
maintenance including $15,762 covering cost of deferred items.
                                          Cost and financial summary

                                                     Fiscal year ending June 30                                   Total to June
                                                                                                                 30, 1954, includ.
                                                                                                                 ing fiscal years
                                   1950           1951            1952             1953             1954          priorto 1950
Maintenance:
   Appropriated ......            $300, 000      $254, 560       $201, 700       $218, 395         $220, 000          $3, 982, 147
   Cost ....--------------         356, 567       269, 880        203, 629        197, 040          222, 248          1 3, 982, 078

      1 Increased by $15,762 to cover cost of deferred items.


                         12.    INACTIVE            NAVIGATION                    PROJECTS

                                                              For last          Cost to June 30, 1954               Estimated
                                                             full report                                             amount
                    Name of project                             see                                                  required
                                                              annual              Con-         Operation                to
                                                              report           struction          and                complete
                                                               for-                           maintenance
                                                                         ,.~
  1. Overton-Red River Waterway, La...........                  1952              189, 763 ..              .         $84, 810, 237
2. Sulphur River, Ark., and Tex__-----------                   1919               45, 989    ..   . .. .. ..            (1)
3. Cypress Bayou and Waterway between Jef-                     1953              202,817           2 341, 589          (1)
      ferson, Tex., and Shreveport, La.
4. Bayou Dorcheat, Loggy Bayou and Lake                        1887                 5,000                              (1)
      Bisteneau, La."'5
5. Cane River, La....---------------------------               1910                 2, 500             2, 000           (1)
6. Bayou Bonfouca, La __--.                  ---...--          1953              6 30, 997            22, 953          (1)
7. Bayou Lacombe, La_-            -       -        -           1950                 4, 716             1,394           (1)
8. Chefuncte River and Bogue Falia, La .......                 1953              724, 563             49, 473          (1)
9. Tangipahoa River, La .....................                  1950                11, 500            15, 203          (1)
10. Pass Manchac, La---_----------------------                  1953                 1, 374            10, 039          (1)
11. Tickfaw, Natalbany, Ponchatoula, and                        1950                 8, 115            32, 416          (1)
      Blood Rivers, La.
12. Amite River and Bayou Manchac, La.......                   1950               728, 234           7 63, 534          (1)
13. Bayou Grosse Tete, La---------------------         4       1950                29, 392             67, 781            205, 608
14. Big Pigeon and Little Pigeon Bayous, La. '                 1936                                    37, 669           (1)
15. Bayous LaLoutre, St. Malo and Yscloskey,                   1953                43, 620             56, 229                60, 380
      La.
16. Bayou Dupre, La-------------------------                   1950                38, 915             26, 890          (1)

17. Grand Bayou Pass, La_------------------                    1950                 7, 676             14, 480          (1)
18. Barataria Bay, La.----------------------                   1950                73, 037             47, 551          (1)
19. Bayou Terrebonne, La._                                     1950              7120, 089            231, 694          (1)
20. Little Caillou Bayou, La_---------.    --.--               1952                77, 761            240, 448          (1)
21. Waterway from Intracoastal Waterway to                     1950                51, 280              1, 543          (1)
      Bayou Dulac, La. (Bayous Grand Caillou
      and LeCarpe, La.) "
22. Atchafalaya River, Morgan City to the Gulf                 1953               501, 963            285, 390          (1)
      of Mexico, La.
23. Petit Anse, Tigre, and Carlin Bayous, La.                  1953               298, 314          8 157, 916          (1)
24. Bayou Vermilion, La ..-------------      -----             1947                34, 00             200, 169          (1)
496               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                  12. INACTIVE NAVIGATION                                 PROJECTS---Continued

                                                               For last         Cost to June 30, 1954              Estimated
                                                              full report                                            amount
                    Name of project                                see                                              required
                                                                annual            Con-         Operation               to
                                                                 report        struction          and               complete
                                                                  for-                        maintenance
25. Waterway from White Lake to Pecan Island,                     1948                904
                                                                                    10,               10, 742          (')
     La.
26. Bayou Plaquemine Brule, La................                    1950             32, 760     36, 780      (1)
27. Bayou Queque de Tortue, La................                    1950             33, 355      4, 776      (1)
28. Lake Charles Deep Water Channel, La......                     1950-      .............    241, 896     (10)
29. Vinton Waterway, La....
                          --------------------                    1950                                 56,000(11)
                                                                              .---------------------------
30. Removing snags and other floating and sunk-                   (12)
     en obstructions in the Atchafalaya and
     Old Rivers from the junction with the
     Mississippi and Red Rivers down the
     Atchafalaya as far as Melville, La., and
     from the Mississippi River within the
     limits of the New Orleans district.
31. Channel improvement under authority of                        1952      .............. 68, 508 ...........
     section 3 of the River and Harbor Act ap-
     proved Mar. 2, 1945.

  1 Completed.
  2 In addition, $50,000 was expended from contributed funds.
  ONo commerce reported.
    Channel adequate for existing commerce.
  0 Abandonment recommended in H. Doc. 1692, 64th Cong., 2d sess. and H. Doc. 467, 69th Cong., 1st sess.

  0 In addition, $5,500 was expended from contributed funds.
  7Includes previous project costs.
  8 Cost this fiscal year covers sale of stock other than revolving fund.
  9 This project has not been completed as it has been incorporated in the flood control, general, project,
"Mermentau River, La."
  10This is a maintenance project and no future work is scheduled.
  11Due to decline of traffic, local interests are no longer sufficiently interested to provide rights-of-way
and dumping privileges.
  12No work has been performed in the New Orleans district under this title.


                                            Cost and financial summary

                                                       Fiscal year ending June 30                                Total to June
                                                                                                             30, 1954, includ-
                                                                                                         ing fiscal years
                                     1950           1951           1952             1953            1954 prior  to1950'
New work:
   Appropriated........--.........    --$10,176 ............--------------------------........................         $298, 314
   Cost...----------  .    $30, 145 ............ ..............................                                         298,314
Maintenance:
   Appropriated.. -...... -13, 500        3, 470      -$1, 628            $115, 524        -$4, 770                     157, 916
   Cost.................      1,526       1,842 ..........                  110, 722                 32                 157, 916

  1Includes $47,858 public works funds, new work.


  13. RED RIVER BELOW DENISON DAM, NEW ORLEANS DISTRICT
   Location. The work covered by this project is located on the
Red River and its tributaries below Denison Dam, in Oklahoma,
Arkansas, Texas, and Louisiana.
   Existing project.    The Flood Control Act approved July 24,
1946, approved the general plan for flood control on Red River
below Denison Dam, Tex. and Okla., which provides for the con-
struction of six flood-control reservoirs in combination with ex-
isting or authorized Federal and non-Federal levee improvements,
modified as required, and channel stabilization at locations where
levee setbacks are impossible or uneconomical. This act further
authorized the incorporation of the several separate existing
projects for flood control along the Red River below Denison,
above the jurisdiction of the Mississippi River Commission, into
                        FLOOD CONTROL-NEW ORLEANS, LA., DISTRICT                                                                     497
this project. The total estimated cost to the United States (re-
vised in 1954) is $89,326,309) of which $74,873,336 is for con-
struction in addition to that required for the incorporated projects
  (H. Doec. 602, 79th Cong., 2d sess.).
   Following are lists of the reservoirs and local protection works
considered in the general flood-control plan for the Red River
below Denison Dam, and the existing flood-control projects in-
corporated into the project, in the New Orleans district:
                                                                New projects

                                                                                  Drainage           Storage,
                                                                                     area                           Flood      Estimated
                    Project                                Stream                  (square          conserva-      control        st
                                                                                   miles)              tion      (acre-feet)      cost


Texarkana Reservoir, Tex. 1-......   Sulphur River. _.           3, 400 145,300  2,509, 000 $33, 000, 000
Ferrels Bridge Reservoir, Tex. 1... Cypress Creek...                850   3, 800   587, 200  20, 900, 000
Mooringsport Reservoir, La. and ...      do..---------.......... 2, 740 150, 000   660, 000  11, 200, 000
  Tex. 2
Bayou Pierre in vicinity of Shreve .   ----------- ------------ ------------ -----------         243,336
  port, La. 3
                                                       ------------. ------------ ------------
Red River levees and bank stabili- ------- ---..............                       .....                                          9,530, 000
   zation below Denison                 Dam,
   Tex., Ark., and La. 1

         Total.......--------------                        ------------------------                    ------- ------------     74,873,336


   1 Details presented in individual report.
     For last full report, see Annual Report for 1952.
   a For last full report, see Annual Report for 1951.
     Actual cost.

                                                        Incorporated projects

                                                                                                                               For last full
                     Project                                      Type of work                      Flood Con- Estimated       report, see
                                                                                                     trol Act     cost         Annual Re-
                                                                                                                               port for-


Hempstead County Levee District                    Levee enlargement----.....                   .     1938        1$88, 006       1941
  No. 1, Ark.
Red River Parish, La__                                    do...........--------...---..-------        1936        1 149,435       1939
Natchitoches Parish, La-----------........ ..      Levee and appurtenances_.-                         1936       1, 580, 000       (2)
Grant Parish, below Colfax, La-.....               Levees ........--------------                      1938         1 38,809       1941
Aloha-Rigolette area, Grant and                    Levee and appurtenances_                -          1941       1,653,800         (2)
  Rapides Parishes, La.
Pineville, Red River, La----............--        ...-----do--------.------------                     1941        1232, 426       1953
Colfax, Grant Parish, La----------............ Cut-off-------------------......................       1938       1 3 70,348       1938
Saline Point, La--....---...                .....
                                         -------          do....--------------------                  1936       1 124,111        1945
Red River in vicinity of Shreveport,               Bank protection-----------.........                1944      1 3,908,000       1953
  La.
Black Bayou Reservoir, La. 4........ Flood control reservoir-......                                   1936          714, 000      1945
Bayou Bodcau Reservoir, La.....--------                  do-__------------.                           1938       4,076, 000        (2)
Bayou Bodcau, Red Chute, and                       Channel improvement-......                         1941        1 306, 509      1948
  Loggy Bayou, La.
Wallace Lake Reservoir, La-......... Flood control reservoir......                                    1936       1,212,000         (2)
Bayou Pierre, La..................                 Channel enlargement.......                         1936        1 299, 529       (2)

  1 Actual cost.
  2 Included in this report.
  a Completed under provisions of section 7 of the Flood Control Act approved May 15. 1928, as amended
by sec. 9 of the Flood Control Act approved June 15, 1936, and included in 1939 Annual Report of the
President, Mississippi River Commission, page 2214.
  4 Work not started.


   Local cooperation. See individual reports.
   Operations and results during fiscal year. Hired labor forces
made studies to determine the economic justification of Millwood
Reservoir, Ark., on a current basis, involving routing of historic
floods and determination of benefits below Fulton, Ark., in the
498          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

New Orleans district, CE. These studies were made for the Tulsa,
Okla. district, CE, at a cost of $2,971.
   For projects in the New Orleans district, CE, see individual
reports.
                                      Cost and financial summary

                                              Fiscal year ending June 30                     Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                               1950        1951         1952         1953         1954       priorto 1950

New work:
   Appropriated--     -   -------------------------------------------------       $3, 000            $3, 000
   Cost    ------------                                  --------          ----    2, 971              2, 971


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954                         $................
                                                                            .... $29
    Unobligated balances available for succeeding fiscal year ending June 30,
                          .....--                 ...... ------ ... ----.....---- 29
                           ...............----------........
      1955........------.......--

                          14. TEXARKANA             RESERVOIR, TEX.
    Location. The work covered by this project is on the Sulphur
River in Cass and Bowie Counties, Tex. The dam site is 45 miles
above the mouth of Sulphur River, and approximately 8 miles
southwest of Texarkana, Tex.
   Existing project. The plan of improvement provides for the
construction of an earth-fill dam 18,500 feet long and 100 feet high,
including a spillway 200 feet wide and outlet works with a capacity
of 27,600 cubic feet per second. The reservoir will control the
runoff from 3,400 square miles of drainage area, and will have
a storage capacity of 2,654,300 acre-feet, of which 145,300 acre-
feet are for conservation and the remainder for flood control.
The estimate of cost (approved in 1953) is $33,000,000, of which
 $28,894,800 is for construction and $4,105,200 is for lands and
damages. The existing project was authorized by the Flood
Control Act approved July 24, 1946 (H. Doc. 602, 79th Cong.,
2d sess.). The latest published map is in the project document.
   Local cooperation. None required.
   Operationsand results during fiscal year. Plans and specifica-
tions; malaria, hydraulic, and engineering studies; gages and
observations of discharge sediment; establishment of sediment
ranges; printing of regulations and maintenance manuals; main-
tenance of slopes of terrace and floodplain section on completed
contracts, and maintenance during construction, were carried on
by hired labor with costs of $69,074.
   Costs of $31,613 for flood fighting operations in the New
Orleans district charged to the project in the previous fiscal year
were credited to the project and the sum of $5,757,000 deposited
in Federal court in connection with condemnation proceedings
against the St. Louis Southwestern Railway has been returned
and credited to the project, as well as $85, representing refund of
salvage value of property removed by former owner.
   Costs for land acquisition amounted to $529,832, and for leas-
ing land to private parties, $1,456.
  Charges for real estate activities in connection with relocations
of utilities and cemeteries amounted to $59,407.
              FLOOD CONTROL-NEW ORLEANS, LA., DISTRICT                                  499
    The amounts of $805 and $900 were transferred to the United
  States Weather Bureau and U. S. Geological Survey, respectively,
for the project's pro-rata share of the cooperative hydroclimatic
  network and the cooperative stream-gaging program.
    Total hired labor costs were minus $5,127,224.
    Construction of the spillway, outlet structures, and closure
section, in progress under a continuing contract at the beginning
of the fiscal year, was completed May 8, 1954.
    Under a continuing contract for clearing approximately 15,838
acres in the reservoir area, clearing operations continued except
during the months of February, March, and April when only minor
work could be accomplished due to high water stages in the areas
to be cleared. At the end of the fiscal year the contract was 44
percent complete.
    Relocation of seven cemeteries in the reservoir area was ac-
complished by contract during the period November 2, 1953, to
March 31, 1954.
    Work was initiated on the relocation of the St. Louis-South-
western Railway during the fiscal year. A reimbursable agree-
ment was entered into with the Railway Company covering the
relocation which provides for construction of timber trestles,
ballast and track work, and relocation of Western Union telegraph
and signal lines by the owner and for the remainder of the work
to be accomplished by the government. Three continuing con-
tracts have been awarded for the remainder of the work, two of
which were for construction of the embankment sections and cul-
verts, and one for the construction of 8 steel bridges required for
the relocation.
   Construction by the owner was initiated February 4, 1954,
when work in connection with relocation of signal and telegraph
poles was commenced; however, work under this agreement con-
sisted mostly of procuring and stockpiling material. Construction
of the embankment sections was initiated April 5, 1954, and is
approximately 3 percent complete. Construction of the steel
bridges was initiated June 21, 1954.
   The status of other relocations under reimbursable contract, in
progress at the end of the fiscal year, was as follows:
   Alteration of Texas State Highway No. 8, initiated September
9, 1953, 36 percent complete.
   Alteration of American Telephone and Telegraph lines, initiated
in April 1954, 7 percent complete.
   Relocation, rearrangement, and alteration of power lines in
Bowie, Cass, Morris, Red River, and Titus Counties, Texas, initi-
ated on September 9, 1953, 20 percent complete.
   Cost charges on these contracts were:
   Spillway, outlet structures, and closure section-...      -..---------------- $1, 193, 287
   Clearing ....      --------------------------------    -883,                           321
   Relocations ..-.                                                               1, 364, 995

  Delayed contract costs for construction of floodplain section
amounted to $3,241.
  Total contract costs were $3,444,844.
  The total costs were minus $1,682,380 for new work.
500              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Condition at end of fiscal year. The project is 58 percent com-
plete.
   Construction work on this project was initiated on August 18,
1948, and to date clearing of the dam site, construction of the
terrace, floodplain sections, and spillway, outlet structures, and
closure section, relocation of State Highway No. 11, designated as
U. S. Highway No. 59, and of County Road, Precinct No. 1, Bowie
County, Tex., alteration of telephone facilities, and relocation and
alteration of 6.9 miles of transmission lines across Texarkana
Reservoir have been accomplished.
   The work remaining to complete the project, besides that which
is under contract and in progress, consists of relocation of U. S.
Highway No. 67 and Bowie County roads, construction of access
roads, channel improvement, construction of reservation buildings
and appurtenances, construction of public-use facilities, and real
estate activities.
   The total costs to the end of the fiscal year were $19,089,283 for
new work.
                                            Cost and financial summary

                                                      Fiscal year ending June 30                             Total to June
                                                                                                            30, 1954, includ-
                                                                                                            ing fiscal years
                                     1950           1951           1952           1953           1954         prior to 1950
New work:
     Appropriated.-.             $5, 000, 000   $1, 300, 000   $4, 000, 000   $4, 974, 000    $5, 000,000        $24, 274,000
     Cost----------------         1, 191, 408    3, 276, 037    5,093,347     10, 203,395 -1, 682,380              19, 089,283

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954.............................                         $523, 950
    Appropriated for succeeding fiscal year ending June 30, 1955.......... 3, 300, 000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955.....                   ---------------------------------------                           3,823,950
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project----....--..--...                                                           5, 426,000
                                                     .....................--------......--.......--------.........-----...........

                         15. FERRELLS BRIDGE RESERVOIR, TEX.
   Location. The work covered by this project is on Cypress
Creek in Marion, Harrison, Upshur, Morris, and Camp Counties,
Tex., 9 miles west of Jefferson, Tex.
   Existing project. The plan of improvement provides for the
construction of an earthfill dam, 10,000 feet long and approxi-
mately 80 feet high, and includes a 200-foot spillway with a ca-
pacity of 68,200 cubic feet per second. The reservoir will control
the runoff from 850 square miles of drainage area, and will have
a gross storage capacity of 842,000 acre-feet, including 587,200
acre-feet of flood-control storage, 3,800 acre-feet of conservation
storage, and 251,000 acre-feet for municipal and industrial water
supply. The reservoir will extend 28 miles upstream. The project
will afford substantial flood protection of Cypress Creek Valley
from the dam site to confluence with the Red River and, together
with the operation of the other reservoirs.proposed in the Red
River Basin, will provide flood protection along the main stem of
the Red River below Denison Dam.
   The estimate of cost (revised in 1953) is $18,300,000 for con-
struction and $2,600,000 for lands and damages, a total of
                FLOOD CONTROL--NEW ORLEANS, LA., DISTRICT                                             501
$20,900,000. The project was authorized by the Flood Control Act
approved July 24, 1946. (H. Doc. 602, 79th Cong., 2d sess., which
contains the latest published map.)
   Local cooperation. None required.
   Operations and results during fiscal year. Hydraulic studies,
field investigations and laboratory tests; design drawings and
specifications for dam and structure; and preliminary plans,
studies, and specifications for alteration of utilities and highway,
were continued by hired labor. Design memoranda are being pre-
pared by Lower Mississippi Valley Division office, except memo-
randa numbered 4 and 5. Design memorandum No. 4, covering
real estate, has been completed by the New Orleans district, CE,
and forwarded to the Chief of Engineers for approval. Design
memorandum No. 5, relocations, is in preparation, and work on
plans and specifications for relocation of Farm-to-Market Road
No. 726 has been initiated by the New Orleans district, CE. Hired
labor costs were $49,136.
   Funds in the amount of $1,000 were transferred to the United
States Weather Bureau as the project's pro-rata share of costs
for operation of the cooperative hydroclimatic network.
   The total cost of new work was $50,136.
   Condition at end of fiscal year. No construction work has been
performed on the project.
   The total costs to the end of the fiscal year were $491,049.
                                     Cost and financial summary

                                            Fiscal year ending June 30                       Total to June
                                                                                             30, 1954, includ-
                                                                                            ing fiscal years
                             19560        1951         1952         1953         1954        prior to 1950
New work:
                -------
   Appropriated........       95, 000    $128, 000   -- $98, 148   $160, 000   -$18, 000            $496, 852
   Cost-----------------      98, 327      63, 753       46, 751     86, 062      50, 136            491, 049


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954...... ...
    Appropriated for succeeding fiscal year ending June 30, 1955............
                                                                                        ......$5, 669
                                                                                             750, 000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955-----...... ..............................................                755,669
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project.....................................................--
                                                        -...---.......-- -               19, 653, 148

      16. RED RIVER BELOW DENISON DAM, LEVEES AND BANK
                 STABILIZATION (NEW ORLEANS DISTRICT)
   Location. The improvements covered by this project are lo-
cated along both banks of Red River from the vicinity of Index,
Tex., mile 497, to the latitude of Alexandria, La., mile 121 (mile
105, 1946 survey) on the north bank, and to the latitude of Boyce,
La., mile 141, on the south bank.
   Existing project. The plan of improvement provides for modi-
fication as required of existing or authorized Federal and non-
Federal levee improvements for conveyance of peak flows of the
design flood with a minimum freeboard of 3 feet, except where a
3-foot superiority for the "South Bank Red River Levee" is
presently prescribed; and for extension of the channel stabiliza-
 502            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

tion program envisaged by the existing project, "Red River in the
Vicinity of Shreveport, La.," by construction of bank protection
works at locations where levee setbacks are impossible or un-
economical, and to prevent the disruption to transportation fa-
cilities when threatened by caving banks, all between Denison
Dam and the upper limit of the Mississippi River backwater, below
which is under the jurisdiction of the Mississippi River Commis-
sion.
    The existing project was authorized by the Flood Control Act
approved July 24, 1946. (H. Doc. 602, 79th Cong., 2d sess., which
contains the latest published map.)
    The estimate of cost (approved in 1954) is $9,530,000.
    Local cooperation. Local interests are required to: (1) Provide
without cost to the United States the rights-of-way required for
the work; (2) hold and save the United States free from damages
due to the construction of the works; and (3) maintain and op-
erate the works after completion. Local interests have met the
requirements on all work accomplished and have indicated their
desire to comply with the requirements as needed.
    Operationsand results during fiscal year. Hired labor carried
on preparation of preliminary plans and specifications, acquisition
of local cooperation, hydrological studies, surveys. and engineer-
ing and design, at a cost of $25,017, and restored Wincy Bayou
levee over a distance of 139 linear feet at a cost of $2.760.
   Approximately 7,087 linear feet of standard board revetment
were constructed on Red River during the fiscal year as follows:
                                                                 Period                             Linear feet
     Location                                                 accomplished                          constructed
McNeely Bend, La., R-156.8-L                              7-21-53 to 12-1-53 ..............            2, 056
Armistead, La., R-243.0-R .....-------------             12-31-53 to 2-14-54 ..............         ... 500
Eagle Bend, La., R-300.3-R--........-.. ................. 4-2-54-in progress ...                 ..    2,954
                                                                                              ...----------......
Lucas Bend, La., R-295.8-R------......       -----....................
                                                          3-11-54-in progress ..---............-       1, 577

   The costs for this construction amounted to $480,012.
   Contracts have been entered into for construction of approxi-
mately 2,925 linear feet of standard board revetment at Brownlee
Bend, R-314.1-L, for which preliminary costs amounted to $4,156,
and approximately 3,930 linear feet at Cash Bend, R-320.5-R;
however, construction work under these contracts has not com-
menced.
   The total costs for the fiscal year were $511,944.
   Condition at end of fiscal year. The project, on which construc-
tion commenced on February 15, 1948, is 47 percent complete, with
approximately 57 miles of the left bank and 100 miles of the right
bank levees improved, and 12,937 linear feet of dike and 10,143
linear feet of board revetment constructed.
   The total costs to the end of the fiscal year were $4,495,849,
new work.
                FLOOD CONTROL-NEW ORLEANS, LA., DISTRICT                                                  503

                                     Cost and .financialsummary

                                             Fiscal year ending June 30                     Total to June
                                                                                           30, 1954, includ-
                                                                                           ing   fiscal   years
                              1950         1951         1952         1953       1954        priorto 19501

New work:
   Appropriated..--------    $520, 900    $500, 000        ,       $324, 000   $565, 000          $4,704,505
   Cost. - -693,                  929      552, 319    $208, 037     28, 700    511,
                                                                                  944               4,495, 849
  'Includes $212,105 expended by Tulsa District for cost of Index unit.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954.........--------------.......
                                                                              $41, 719
    Appropriated for succeeding fiscal year ending June 30, 1955-------....   450,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955------------..-----------------------------491, 719
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project.......------------------------------      4,375,495


                      17. BAYOU BODCAU RESERVOIR, LA.

     Location. The work covered by this project is in Red River
Basin on Bayou Bodcau in Bossier Parish, La., 72 miles above the
mouth of Loggy Bayou and 35 miles northeast of Shreveport, La.
  (See U. S. Geological Survey State map, scale 1:500,000.)
     Existing project. The plan of improvement provides for the
construction of an earthfill dam rising 76 feet above the stream
bed with a reservoir providing a flood control storage capacity
of 357,000 acre-feet. The outlet works are located in the south
abutment, and an uncontrolled spillway is located on the north
abutment. The reservoir will control 656 square miles, or 53 per-
cent, of the entire drainage area of Bayou Bodcau. The construc-
tion of a floodway for the diversion of Bayou Bodcau and Cypress
Bayou to improve flood protection was authorized by the Flood
Control Act approved June 22, 1936. This authorization was mod-
ified by the Flood Control Act approved June 28, 1938, which au-
thorized the construction of a reservoir and other flood-control
works, in lieu of the construction of a floodway for the diversion
of Bayou Bodcau and Cypress Bayou, La., to improve flood pro-
tection, and further modified by the War Department Civil Appro-
priation Act approved June 28, 1939, which provided that the
reservoir and other flood-control works on Bayou Bodcau and
Cypress Bayou, La., authorized by the Flood Control Act approved
June 28, 1938, shall be constructed in accordance with the revised
plans and cost estimates in the Office, Chief of Engineers.
    The estimate of cost for new work (revised in 1954) is $3,195,773
for construction, and $880,227 for lands and damages, a total of
$4,076,000. The latest (1952) approved estimate of annual cost
of maintenance is $15,000.
    The latest published map is in House Document 378, 74th Con-
gress, 2d session.
    Local cooperation. None required.
    Operations and results during fiscal year. Hired labor con-
tinued land acquisition and flood damage studies at a cost of $1,359
for new work, and carried on routine studies, malaria control,
gages and observations, stream gaging, and operation and main-
504               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

tenance of the reservoir at a cost of $9,931 for maintenance.
  Funds in the amount of $600 were transferred to the United
States Weather Bureau as the project's pro rata share of costs
for operation of the cooperative hydrologic network.
  The total costs were $11,890, of which $1,359 was for new work
and $10,531 was for maintenance.
                                                Reservoir operations

                                                                                       Storage  Inflow 1           Outflow 1
                                                                                      (acre-feet)

July 1, 1953 ..                                              .........--.      .---      20,120               50         1,430
June 30, 1954     ------------------------------------------------                          210             20             10
July 1, 1953 (maximum).....
                         -------------------------------------                           20122----.....   1,600       --- 430
May 19, 1954 (maximum)_-------------------------------------                                              1,600.

  1 Cubic feet per second.

   Number of visitor-days of recreational use-11,600 (fiscal year
1954).
   Condition at end of fiscal year. The project was completed on
November 21, 1950, except real estate activities which remain to
be completed.
   Construction work was initiated on April 23, 1947, and on
December 1, 1948, the main dam and spillway were completed.
The outlet structure was constructed during the period April 8,
1948, to December 17, 1949, and on July 14, 1948, Bayou Bodcau
was diverted from its natural bed and flowed through the outlet
structure for the first time. Relocation and alteration of utilities
and roads have been accomplished as follows:
                                                                                 Commenced                     Completed

Alteration      to pipe line, United Gas Pipe Line Co. Oct.      6, 1947 Jun.                                      29, 1948
Alteration      of parish road and bridges---------....................
                                                          Sept. 12, 1949 Aug.                                      24, 1950
Relocation       of State Highway No. 70...................
                                                       .Oct.    25, 1949 Nov.                                      21, 1950
Anchoring       of seven bridges on State route No. 182 Nov. 16, 1949    Nov.                                      26, 1949
Alteration      to pipe line, Triangle Pipe Line Co.... Nov. 20, 1949    Feb.                                      15, 1950

  The total costs to the end of the fiscal year were $4,124,202, of
which $4,075,040 was for new work and $49,162 for maintenance.
                                          Cost and financial summary

                                                    Fiscal year ending June 30                                Total to June
                                                                                                              30, 1954, includ-
                                                                                                              ing fiscal years
                                   1950           1951            1952           1953              1954        prior to 1950
New work:
   Appropriated...--------.... $360,000 ..........-----------------           -$345, 125             ----          $4,075, 875
   Cost......----.......----------....
                                781,424       $207, 153          $81, 255          20, 545          $1, 359         4, 075, 040
Maintenance:
   Appropriated--------             10, 000         9,000            8, 500        11, 000          11, 000               500
                                                                                                                        49,
   Cost.------------      ----       2,382         15, 096          10, 615        10,539           10,531              49,162


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954.............-.................
                                                                              $835
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955-----..........................------------.......................   835
     Estimated additional amount needed to be appropriated for completion
       of existing project .................................................
                                                                    ...... 125
           FLOOD CONTROL--NEW ORLEANS, LA., DISTRICT              505
                18. WALLACE LAKE RESERVOIR, LA.
     Location. The work covered by this project is in Red River
  Basin on Cypress Bayou, Caddo, and De Soto Parishes,' La., 66
  miles above the mouth of Bayou Pierre and about 14 miles south-
  east of Shreveport, La. (See U. S. Geological Survey State map,
  scale 1:500,000.)
     Existing project. The plan of improvement provides for the
  construction of an earthfill dam 4,940 feet long at the top, in-
  cluding 644 feet of spillway and outlet works, rising 48 feet above
  the stream bed, with a reservoir providing for storage of 96,100
  acre-feet, including a conservation pool of 7,800 acre-feet. The
  outlet works and uncontrolled spillway are centered about 1,250
feet north of the south abutment. The reservoir will control 260
square miles, or about 20 percent of the total drainage area of
Bayou Pierre, Cypress Bayou, and tributaries combined, and will
afford protection against floods for an area of about 90,000 acres of
valley below the dam.
    The existing project was authorized by the Flood Control Act
approved June 22, 1936 (H. Doc. 378, 74th Cong., 2d sess.).
    The estimate of cost for new work (revised in 1954) is $1,142,-
064 for construction and $69,936 for preparation of land titles,
a total of $1,212,000. The latest (1952) approved estimate for
annual cost of maintenance is $10,000.
    The latest published map is in House Document No. 378, 74th
Congress, 2d session.
    The Flood Control Act approved July 24, 1946, incorporated this
project in the new project "Red River below Denison Dam."
    Local cooperation. Local interests, represented by the Board
of Commissioners of Caddo Levee District, have furnished as-
surances, agreeing to furnish free of cost to the United States all
the land, rights-of-way, easements, and servitudes required for
the project. The dam site area, which was acquired in fee, has
been conveyed to the United States. Practically 85 percent of the
flowage easements in the reservoir area has been acquired by the
local agency and conveyed to the United States. Due to inability
to clear title to some tracts and unreasonable requests of land-
owners as to prices offered for such easements, the local agency,
by resolution adopted on November 20, 1951, requested that con-
demnation proceedings be filed in its behalf to acquire flowage
easements over the remaining portion of the reservoir.
    Five declarations of taking have been filed covering 73 tracts.
It is estimated that local interests will make the additional funds
available so that two declarations of taking covering the final 27
tracts may be filed during fiscal year 1955.
    Operations and results during fiscal year. Hired labor forces
continued processing of rights-of-way at a cost of $5,684 for new
work and carried on maintenance of the dam, engineering studies
and investigations, stream gaging, and gages and observations at
a cost of $4,484 for maintenance.
    Funds in the amount of $1,493 and $300 were transferred to
the United States Weather Bureau and the U. S. Geological Sur-
vey, respectively, as the project's pro rata share of costs for opera-
506            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

tion of the cooperative hydrologic network and the cooperative
stream-gaging programs.
   The total costs were $11,961, of which $5,684 was for new work
and $6,277 for maintenance.
                                       Reservoir operations

                                                                      Storage        Inflow 1       Outflow 1
                                                                     (acre-feet)

Ju ly 1,1953..._ __-- .    .     .     --..       ...      -              7, 440               0               1
                ___ --- _ -- - -..... .. ... .. ..--....... ....--
June 30, 1954- ..                                                         7,170                0               0
May 14, 1954 (maximum)-_                                                 24,030           5, 550           1,510

  1Cubic feet per second.

   Number of visitor-days of recreational use-26,100 (fiscal year
1954).
   Condition at end of fiscal year. All construction work on the
project was completed on December 28, 1946; completion of
processing of rights-of-way remains to complete the project.
   The main portion of the dam was constructed during the fiscal
year 1943; the stabilization of the railroad embankment was ac-
complished during the period June 19 to November 20, 1946; and
placing of fill in the closure section of the dam was accomplished
during the period November 24 to December 28, 1946.
   The total costs to the end of the fiscal year were $1,256,443,
of which $1,198,161 was for new work and $58,282 for maintenance.
                                   Cost and financial summary

                                         Fiscal year ending June 30                           Total to June
                                                                                             30, 1954, includ-
                                                              1ing                                 fiscal years
                            1950        1951        1952         1953              1954         prior to 1950

New work:
   Appropriated               .                      $3, 000     $10, 000          $4,
                                                                                     500            $1, 199, 500
   Cost$                       $495        $781      3,200           8,118          5,684            1,198,161
Maintenance:
   Appropriated -....   _    10,000       6,000      6,500           8,000          6,800               59,300
   Cost                      18,525       9, 291     6, 670          8, 773         6, 277              58, 282


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-..........................
                                                                                   . $1, 339
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955------------------------...
                        .........-------------------------                            1,339
    Estimated additional amount needed to be appropriated for completion
      of existing project..................--------------------.........             12, 500
                                                           .......----------...........---------...
                                   19. BAYOU PIERRE, LA.
   Location. The work covered by this project is in Red River
Basin below Shreveport, La., along the channel of Bayou Pierre
from its mouth at Grand Ecore, La., upstream to its confluence
with Bayou Wincy, a distance of 30 miles. (See U. S. Geological
Survey State map, scale 1:500,000.)
   Existing project. The plan of improvement provides for widen-
ing of the channel at intervals, totaling 12.9 miles and snagging
of 29.7 miles. The project will reduce flood damage and improve
sanitary and living conditions over a wide area.                                      The existing
                   FLOOD CONTROL-NEW ORLEANS, LA., DISTRICT                                           507
project was authorized by the Flood Control Act of June 22, 1936
 (H. Doc. 378, 74th Cong., 2d sess.).
   The cost of constructing the project, completed in 1939, was
$299,529. The estimated annual cost of maintenance is $13,500.
   The latest published map is in House Document No. 378, 74th
Cong., 2d session.
   Local cooperation. None required.
   Operationsand results during fiscal year. Surveys, engineering
studies, and drafting for clearing and snagging the bayou were
completed and flood damage surveys, condition and operation
studies, and gages and observations were carried on by hired labor,
all at a cost of $7,323.
   Work under hired labor directive for clearing and snagging
Bayou Pierre, mile 29.4 to mile 11.8, commenced in previous fiscal
year, was stopped on July 27, 1953, owing to lack of funds when
all work required had been completed from upper limit of job to
mile 22.95 on east bank and to mile 23.05 on west bank. Work
under this directive was resumed on June 6, 1954, and to the end
of the year was 88 percent complete with the west bank cleared
between miles 22.3 and 18.7 and the east bank between miles 23
and 21.8. Fiscal year costs for this clearing and snagging
amounted to $19,392. Total costs were $26,714 for maintenance.
   Condition at end of fiscal year. New work under the existing
project was completed in the fiscal year 1939.
   The total costs to the end of the fiscal year were $404,045, of
which $299,529 was for new work including $38,529 from Emer-
gency Relief funds, and $104,516 for maintenance.
                                       Cost and financial summary

                                              Fiscal year ending June 30                    Total to June
                                                                                           30, 1954, includ-
                                                                                           ing fiscal years
                                1950        1951         1952        1953       1954         prior to 19501
New work:
   Appropriated- -------                                                                           $299, 529
   Cost -299,                                                                                            529
Maintenance:
   Appropriated                $15, 000   -$35, 000      $6, 000     $29, 574   $19, 000            111, 574
   Cost-_                        5, 731        6, 842     6, 904      18, 559    26, 714            104, 516

  1 Includes   $38,529 from Emergency Relief funds, new work.

                             20. NATCHITOCHES PARISH, LA.
   Location. The work covered by this project is on the south
bank of Red River in Natchitoches Parish, La., between miles 160
and 202 above the mouth of Red River. (See U. S. Geological
Survey State map, scale 1:500,000.)
   Existing project. The plan of improvement provides for the
raising and enlargement of the existing levee and the construction
of new levee between the hills near Grand Ecore, La., at mile 202
above the mouth of Red River, and the hills below Cane River
near its mouth at mile 160 above the mouth of Red River; the
construction of a dam across Cane River near its mouth; the ex-
cavation of drainage canals for intercepted drainage; and a di-
version channel from Cane River to Red Bayou, a distance of
508      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

approximately 5.5 miles, for protection of approximately 135,000
acres of land in the Cane Island area from Red River overflow.
The existing project was authorized by the Flood Control Act
approved June 22, 1936 (H. Doc. 378, 74th Cong., 2d sess.).
     The estimate of cost (revised in 1954) is $1,580,000 (Federal)
and $250,000 (non-Federal), all for construction.
     The latest published map is in House Document No. 378, 74th
Congress, 2d session.
     Local cooperation. Local interests furnished assurances on
January 23, 1952, which were approved by the Division Engineer
on April 21, 1952, that they will: (1) Provide without cost to the
United States all lands, easements, and rights-of-way necessary
for the construction of the project; (2) hold and save the United
States free from damages due to the construction works; and
  (3) maintain and operate the works after the completion in ac-
cordance with regulations prescribed by the Secretary of the
Army. Local interests contributed $250,000 towards the cost
of construction of the Cane River-Red Bayou diversion channel.
Difficulty was encountered in furnishing rights-of-way and two
tracts were condemned by the United States on behalf of local
interests. It is estimated that the condemnation proceedings will
be concluded by the Department of Justice on or about July 1, 1955.
    Operations and results during fiscal year. Flood damage sur-
veys, engineering and design, acquisition of rights-of-way, gages
and observations, and civil works investigation program were
carried on by hired labor at a cost of $39,085.
    The project's pro-rata share for the Mississippi Basin Model
was $29,710.
    Excavation of Cane River-Red Bayou diversion channel, com-
menced under a continuing contract in previous fiscal year, was
94 percent complete at the end of the fiscal year, with 3,327,698
cubic yards excavated in constructing 0.73 mile of new channel
and effecting 3.88 miles of channel enlargement this fiscal year.
A total of 214,343 cubic yards was excavated in completing ap-
proximately 11/2 miles of drainage ditch. Costs for this work
were $414,643.
    Contract has been awarded for the construction of 565 linear
feet of the Cane River dam and 4,333 linear feet of tie-in levee, but
the work has not commenced. Preliminary Government costs on
this contract amounted to $1,752.
    The total Government costs for new work were $485,190. In
addition, costs from contributed funds for construction amounted
to $250,000.
    Condition at end of fiscal year. Construction of the project
commenced in fiscal year 1938 and is now 86 percent complete,
with 36.2 miles of levee constructed and enlarged and 5.1 miles
of diversion channel excavated.
    Completion of the Cane River to Red Bayou diversion channel,
which channel is practically complete; construction of the Cane
River dam and tie-in levee now under contract; ditching for in-
tercepted drainage; and erosion control work, remain to complete
the project.
  The total Government costs for new work to the end of the
                       FLOOD CONTROL-NEW ORLEANS, LA., DISTRICT                                                                 509
fiscal year were $1,354,168. In addition, costs from contributed
funds amounted to $250,000.
                                                       Cost and financial summary

                                                                         Fiscal year ending June 30                    Total to June
                                                                                                                      30, 1954, includ-
                                                                                                                      ing fiscal years
                                              1950                1951            1952         1953        1954        priorto 1950

New work:
   Appropriated........
                    ---------------                       ------------           $360, 000    $348,000    $349,000          $1, 575, 700
   Cost.................
        -----------              ------------------------                          37,623       88, 590    485, 190          1, 354, 168


Other new work data:
                                                                              $189, 460
    Unobligated balance, fiscal year ending June 30, 1954...........................
    Unobligated balances available for succeeding fiscal year ending June 30,
       1955........------------------------------               ---------- 189,460

                                                          CONTRIBUTED FUNDS

                                                                    Fiscal year ending June 30                         Total to June
                                                                                                                      30, 1954, includ-
                                                                                                                      ing fiscal years
                                             1950                 1951            1952         1953        1954        priorto 1950

New work:
   Appropriated      ------------------------------------     $250, 000
                                                   ............                                                               $250, 000
    ost.....-------------------------------------------------           $250, 000
                                                   ............ -----............                                              250, 000



              21. ALOHA-RIGOLETTE AREA, GRANT AND RAPIDES
                               PARISHES, LA.
   Location. The work covered by this project lies on the left bank
of Red River in Grant and Rapides Parishes, between miles 125
and 171 above the mouth. (See U. S. Geological Survey State map,
scale 1:500,000.)
   Existing project. The plan of improvement provides for pro-
tection of some 46,000 acres of alluvial plain in the Aloha-Rigolette
area, now subject to overflow by Red River waters, by enlarging
and raising the existing levee from mile 151. to mile 141, and
extending it to the hills on the left bank of Bayou Rigolette.
Interior drainage, intercepted by levee construction, is to be chan-
neled to and through Bayou Rigolette to a sump and a floodgate
system in the levee at Bayou Rigolette, by construction of a
diversion ditch from Bayou Darrow to Saline Bayou, and fills at
head of Bayou Darrow, and channel clearing of Bayou Rigolette
and portions of Waden and Saline Bayous.
  The existing project was authorized by the Flood Control Act
approved August 18, 1941, which modified the project for Grant
Parish below Colfax, La., as authorized by the Flood Control Act
approved June 28, 1938, to provide for construction of the above
described works.
  The estimate of cost (approved in 1954) is $1,652,800 (Federal)
for construction and $50,000 (non-Federal) for rights-of-way.
  Local cooperation. Fully complied with.
  Operations and results during fiscal year. Hired labor forces
restored approximately 6.29 miles of Red River levees during the
period March 29 to June 16, 1954, with costs of $20,365.
510          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   During the period July 8, 1953, to April 2, 1954, Bayou Rigolette
floodgate was constructed by contract at a cost of $304,757.
   Construction of approximately 4,000 linear feet of embankment
on Bayou Rigolette, R-124.5-L, by contract, completing the em-
bankment to the hills, was accomplished during the period July
15, 1953, to June 30, 1954, with seeding and final dressing remain-
ing to be accomplished on approximately 881 linear feet of the
embankment. Costs for this embankment construction amounted
to $83,323.
   Total fiscal year costs were $408,445 for new work.
   Condition at end of fiscal year. The project is approximately
99 percent complete. Construction commenced on June 3, 1948,
and at the end of the fiscal year approximately 18 miles of new
levee and 4 miles of riverside enlargement had been constructed.
Bayou Darrow has been separated from Bayou Rigolette and its
flow diverted into Saline Bayou through the diversion ditch which
was excavated during the period June 28 to November 6, 1948.
Bridges at miles 0.40, 2.05, and 4.1 over the diversion ditch were
completed during the period October 4, 1948, to May 24, 1949, and
33.30 miles of waterway were cleared during the period July 16,
1948, to February 18, 1950. Bayou Darrow closures were effected
during the period May 16 to August 22, 1949.
   Seeding and final dressing of approximately 881 linear feet of
embankment remain to complete the project.
   The total costs to the end of the fiscal year were $1,634,437 for
new work.
                                     Cost and financial summary

                                                 Fiscal year ending June 30                   Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                              1950             1951        1952        1953        1954        priorto 1950
New work:
   Appropriated----       -_ $500, 000 ----                           $186, 550   $146, 936        $1,652, 800
   Cost----------------.....
                  ..         469, 008         $319, 517    $32, 159      4, 676    408, 445          1, 634, 437

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_.                     $47, 899
                                                                        ..------------....---
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955 ........-.. .          . ...................
                                                 ...............
                                                             . .......
                                                                     . .          47, 899

              22. BAYOU TECHE AND VERMILION RIVER, LA.
   Location. Bayou Teche has its source in Bayou Courtableau,
in St. Landry Parish, and flows in a southeasterly direction a dis-
tance of 125 miles to its confluence with the lower Atchafalaya
River, about 101/2 miles above Morgan City, La. Vermilion River,
also called Bayou Vermilion, is formed by the junction of Bayous
Fusilier and Bourbeau, west of Arnaudville, La., and flows in a
southwesterly direction to the western end of Vermilion Bay, a
distance of 72 miles. Bayou Teche is connected with the Vermilion
River by Bayou Fusilier at Arnaudville; and by Ruth Canal, an
artificial, privately owned, nonnavigable waterway, constructed for
diversion of water from Bayou Teche to Vermilion River for rice
irrigation.       (U. S. Coast and Geodetic Survey Charts Nos. 1116 and
             FLOOD CONTROL--NEW ORLEANS, LA., DISTRICT            511
   1277; Corps of Engineers, Mississippi River Commission alluvial
   valley maps; and U. S. Geological Survey maps.)
      Existing project. This provides for the excavation of a navi-
   gable channel (51 miles long) 8 feet deep and 80 feet wide from the
  8-foot depth contour in Vermilion Bay to the Gulf Intracoastal
   Waterway, thence 9 feet deep by 100 feet wide from the Gulf In-
  tracoastal Waterway to Lafayette, La. (fixed bridge at Louisiana
  State Highway No. 1092), with additional enlargement below
  Abbeville necessary to provide adequate capacity for flood flows;
  improvement of Vermilion River from Lafayette, La., mile 52.0, to
  its junction with the lower end of Ruth Canal, mile 57.2, by both
  widening and deepening so as to provide a channel of 60-foot bot-
  tom width at minus 6.0 feet, mean Gulf level, in order to provide
  adequate capacity for flood discharges from the upper Vermilion
  River Basin, and also serve irrigation interests by conducting the
  flow of Ruth Canal to the lower Vermilion River during the rice
  season.
      Clearing and enlargement of the channel from Ruth Canal to
  Bayou Fusilier by both widening and deepening so as to provide a
  cross-section approximately 50 percent larger than that of the
  existing channel. This improvement is required in the interest of
  flood control in the upper Vermilion Basin.
     Enlargement of the channel of Bayou Teche from its head in
  Bayou Courtableau to a point approximately 21 miles downstream
  thereof, by widening and deepening so as to provide a channel of
  35-foot bottom width at minus 2 and minus 3, mean Gulf level.
     Increasing the height of Keystone Dam from its present crest
  elevation of 8.0 feet, above mean low Gulf, by 3 feet (later revised
to 1.5 feet) by the installation of movable crest gates. (See in-
dividual report of navigation project for Bayou Teche, La.)
     In connection with the improvements outlined above, the project
provides for replacement of an existing pontoon bridge at Wood-
lawn on the navigable portion of Vermilion River with a vertical
lift structure. Relative minor work, consisting of lengthening and
strengthening of approaches, is required on five existing movable
bridges over Vermilion River below Lafayette, La., located at
Louisiana State Highway No. 43 at Perry, La.; Southern Pacific
Railroad at Abbeville, La.; Louisiana State Highway No. 25 at
Abbeville, La.; Milton, La.; and U. S. Highway No. 90 (Pinhook
Bridge) just below Lafayette, La. Similar work on existing fixed
spans over nonnavigable streams is provided for on eleven bridges
over Bayou Vermilion above Lafayette, La., and three over upper
Bayou Teche.
    The estimate of cost for new work (revised in 1954) is $2,912,-

 .The
000 (Federal) and $150,000 (non-Federal).
         latest (1952) approved estimate of Federal cost of annual
maintenance is $25,000.
    The existing project was authorized by the Flood Control Act of
August 18, '1941 (S. Doc. 93, 77th Cong., 1st sess., which also con-
tains the latest published map).
    Local cooperation. Fully complied with for new work.
    Final acquisition of the rights-of-way for future maintenance by
formal acts of conveyance is in process and local interests have
     Sig 17-511-542
512      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

completed acquisition of approximately 70 percent of rights-of-
way required for maintenance.
    Operations and results during fiscal year. Hired labor com-
pleted preliminary plans and specifications for dredging in Ver-
milion River at a cost of $35 for new work, and continued super-
vision, inspection, and patrol of the waterway, preparation of
reports, stream gaging, drafting, engineering and design, gages
and observations, and acquisition of rights-of-way, at a cost of
 $11,767 for maintenance.
    Channel restoration was accomplished by the contract dredge
Moreland II during the period April 23 to May 16, 1954, when six
stations were excavated at Onion Bayou Crossing and 95 stations
were excavated in Vermilion Bay channel. The cost of this work
was $27,496.
   The total costs were $39,298, of which $35 was for new work and
 $39,263 was for maintenance.
    Condition at end of fiscal year. The project on which construc-
tion commenced on March 20, 1944, is now approximately 99 per-
cent complete.
    Channel improvement on Vermilion River consisted of con-
structing an 8- by 80-foot channel from the 8-foot depth contour
in Vermilion Bay to the Gulf Intracoastal Waterway; a 9- by 100-
foot channel from Gulf Intracoastal Waterway to mile 52 (it was
necessary to redredge Vermilion River channel between miles 36.9
and 46.0 during the fiscal year 1953, to reestablish project dimen-
sions, due to sedimentation caused by deposits from tributary
streams excavated by local interests) ; and a 6- by 60-foot channel
from mile 52 to mile 57.4. Channel enlargement was accomplished
between miles 3.5 and 17.5 and 57.4 and 76.21. Clearing and snag-
ging was accomplished in Bayou Fusilier and Bayou Vermilion be-
tween miles 67.7 and 79, and an earth dike was constructed in
Bayou Fusilier. The channel of Bayou Teche was improved be-
tween miles 103.8 and 124.8. A new bridge was constructed over
Vermilion River at Woodlawn, the bridge at Milton was recon-
structed; modification of railroad bridge numbered 3.78 and Lou-
isiana State Highway bridges numbered 988 over Bayou Vermilion
and 245 over Bayou Fusilier has been accomplished; the bridge at
Pinhook was altered, and riprap was placed to insure bridge against
possible damage by bank caving; and excavation and riprapping
was performed in the vicinity of Southern Pacific Railroad bridge,
Lafayette, La. Local interests have constructed improvements in
Ruth Canal.
   Work remaining to complete the project consists of raising the
crest of Keystone Dam, a feature of the River and Harbor project
"Bayou Teche, La.," to provide an increase of 1.5 feet in the pool
elevation above Keystone Dam, in order to increase the flow
through Ruth Canal into Vermilion River, and miscellaneous minor
items. This work will be accomplished in connection with the
modification of Keystone Dam under the Bayou Teche, La., project.
   The controlling depths, mean low Gulf, Vermilion River, were:
 (May 1954) Over the bar, project depth obtained; (November
1953) to Gulf Intracoastal Waterway, 5 feet; (April 1953) to Ab-
beville, 9 feet; to Woodlawn bridge, 8 feet; and to Pinhook bridge,
                     FLOOD CONTROL-NEW ORLEANS, LA., DISTRICT                                                                513
5 feet, except a plug 600 feet long about one mile below the bridge,
3.5 feet.
   The total costs under the existing project to the end of the fiscal .
year were $3,163,366, of which $2,891,678 was for new work and
$271,688 for maintenance.
                                           Cost and financial summary

                                                   Fiscal year ending June 30                                       Total to June
                                                                                                                   30, 1954, includ-
                                                                                                                   ing fiscal years
                                    1950         1951               1952          1953                   1954        priorto 1950

New work:
   Appropriated----_ --------------             $375, 000 [---------....        ---...............   .                  $2, 892, 000
   Cost ----------------.. $209, 172             212, 114       $29, 383        $165, 170                   $35          2, 891, 678
Maintenance:
   Appropriated ......                25, 000   ......-----------    89, 000       53, 225               39, 600            271, 825
   Cost       ..   ..-----------------19,645         7,663           18,848 .     126,501                39,263             271, 688


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 ...................---------------                           322
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955 ..--..............................................................                                          322
    Estimated additional amount needed to be appropriated for completion
      of existing project ....... ............. ........................--------------------------------------..... 20,000

                                   23. MERMENTAU RIVER, LA.
    Location. The work covered by this project is located 35 to 70
miles southeast of Lake Charles, La., along the lower Mermentau
River below Grand Lake, mile 25, to the Gulf of Mexico; the Inland
Waterway from Vermilion Bay to White Lake, White Lake to
Grand Lake, and from Schooner Bayou to the Intracoastal Water-
way-Gulf section (Schooner Bayou cutoff); the North Prong of
Schooner Bayou; and the waterway from White Lake to Pecan
Island, La., an artificial canal, extending from the 5-foot-depth
contour in White Lake, almost due south for a distance of approxi-
mately 1.8 miles to Pecan Island. (See U. S. Coast and Geodetic
Survey Charts Nos. 1277 and 1278, and U. S. Geological Survey
maps.)
    Previous project. Authorized by Flood Control Act of August
18, 1941. For further details, see page 1034 of Annual Report for
1946.
    Existing project. The plan of improvement covers flood con-
trol, navigation, irrigation, and salinity control in the coastal marsh
of the lower Mermentau River Basin and provides for channel
enlargement of the lower Mermentau River below Grand Lake,
mile 25, to a minimum section of 3,000 square feet below mean low
Gulf level for discharge of flood flows; construction of a sector
gated control structure at Catfish Point, mile 24 above mouth of
Mermentau River for discharge of flood flows and control of tidal
flows and salt-water intrusion in the Mermentau River; channel
enlargement and realinement of the Inland Waterway from Ver-
milion Bay to White Lake, 12.04 miles, and from White Lake to
Grand Lake, 6.14 miles, to a minimum section of 3,000 square feet
below mean low Gulf level or interflow between lakes and discharge
of flood flows; construction of a sector gated control structure in
the enlarged channel immediately north of the abandoned
 514              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Schooner Bayou lock reservation for discharge of flood flows and
control of tidal flows and salt-water intrusion; channel enlargement
"of North Prong of Schooner Bayou and Schooner Bayou cutoff, 6.69
miles, to 6 by 60 feet, mean low Gulf level, for navigation pur-
poses; and maintenance of the existing 5- by 40-foot, mean low
Gulf level, waterway from White Lake to Pecan Island, La., 1.8
miles long, for navigation.
    In addition, the project provides for the incorporation of that
section of the project, "Inland Waterway from Franklin, La., to
Mermentau River," west of Vermilion Bay, a waterway that in-
cluded the Schooner Bayou lock.
    Because of the failure of both east and west gates, Schooner
Bayou lock has been closed by a dike across the east approach chan-
nel and traffic has been routed through the new control structure.
    Under ordinary conditions the mean range of tide on the Mer-
mentau River near the mouth is 1.6 feet and near the head about
3 inches. The variation of the water surface near the mouth may
be as much as 7 or 8 feet, due to hurricanes on the Gulf, and near
the head from 8 to 12 feet, due to freshets.
    The estimate of cost for new work (approved in 1954) is $4,-
637,000. The latest (1952) approved estimate for annual cost of
maintenance and operation is $93,600.
   The existing project was authorized by the following acts:

     Acts                           Work authorized                                   Documents

Aug. 18, 1941     Channel enlargement, lower Mermentau River,              S. Doc. 94, 77th Cong., 1st sess.
                   from mile 15 to the Gulf of Mexico; and construc-
                   tion of a lock and control spillway at Catfish Point,
                   mile 24.
July 24, 1946 2   Channel enlargement; lower Mermentau River below         S. Doc. 231, 79th Cong., 2d sess.2
                   Grand Lake, mile 25; construction of a gated control
                   structure at or near Grand Cheniere, mile 7; channel
                   enlargement and realignment of Inland Waterway
                   from Franklin, La., to Mermentau River, La., from
                   Vermillion Bay to White Lake, via new channel,
                   and from White Lake to Grand Lake; channel
                   enlargement of North Prong of Schooner Bayou;
                   construction of a gated control structure in     the
                   new channel near Schooner Bayou lock; and inclu-
                   sion of the project "Waterway from White Lake to
                   Pecan Island, La." and the portion of the project
                   "Inland Waterway from Franklin, La., to the
                   Mermentau River," west of Vermillion Bay in the
                   modified project "Mermentau River, La."


1 Flood Control Act.
2 River and Harbor Act.
3 Contains latest published map.


  Local cooperation. Fully complied with.
   Operations and results during fiscal year. Preparation of re-
port on engineering studies and acquisition of rights-of-way were
carried on by hired labor at a cost of $1,461 for new work.
  Work on raising grade and restoring sections of north and south
dikes at Catfish Point control structure initiated by hired labor
           FLOOD CONTROL--NEW ORLEANS, LA., DISTRICT             515
during the previous fiscal year was completed July 2 with costs of
 $6,584 for maintenance.
    Biological investigations and report of Mermentau River by con-
tract consultant were completed at a cost of $876.
    Maintenance funds in the amount of $805 and $900 were trans-
ferred to the United States Weather Bureau and the U. S. Geologi-
cal Survey as the project's pro rata share of costs for operation of
the cooperative hydroclimatic network and the cooperative stream-
gaging program.
    Patrol of the waterway, gages and salinity observations, biologi-
cal investigations, and planning were carried on by hired labor at
a cost of $22,936 for maintenance.
    Schooner Bayou and Catfish Point control structures were oper-
ated as required during the fiscal year to conserve fresh water by
maintenance of normal lake stages and to prevent uncontrolled
tidal inflow during the rice irrigation season; to release promptly
flood waters during abnormal stages; and to limit minimum stages
in interest of navigation. The cost charges were $22,929 and
 $32,058, respectively, for the operation of Schooner Bayou and
Catfish Point control structures.
    The total costs were $88,548, of which $1,461 was for new work,
 $32,100 for maintenance, and $54,987 for operating and care.
    Condition at end of fiscal year.     The project, on which work
commenced April 21, 1947, was completed July 10, 1952, except real
estate activities, since it has been determined that the remaining
authorized work, construction of bulkhead at the mouth of the
waterway, "White Lake to Pecan Island, La.," is not required.
    New work dredging on the existing project was accomplished
during the period April 21, 1947, to June 21, 1952.
    Catfish Point control structure was constructed during the period
November 6, 1948, to August 16, 1951. The reservation comprises
9.7 acres.
    Schooner Bayou lock and control structures: Schooner Bayou
lock and dam were completed in 1913 and 1914, respectively, and
the lockmaster's house in 1917. The lock was closed to navigation
May 7, 1951, and abandoned by authority of the Chief of Engineers
on October 9, 1951. Permanent closure of the lock channel and
tie-in dikes was completed on September 22, 1951.
    Construction of the control structure and dikes was accomplished
during the period August 8, 1949, to May 22, 1951. The reserva-
tion comprises 6.9 acres.
    The controlling depths, mean low Gulf, were: Mermentau River:
 (June 1954) Over bar, 4 feet, to mile 0.0, 10 feet; through cut in
Lower Mud Lake to Upper Mud Lake, 7 feet; through Upper Mud
Lake, 6 feet; to Catfish Point, 10 feet; to Gulf Intracoastal Water-
way through Grand Lake, 2.5 feet; Waterway from White Lake to
Pecan Island, La.; (May 1953) Over bar to Pecan Island, 5 feet.
   The total costs to the end of the fiscal year were $4,975,827, of
which. $4,627,903 was for new work, and $347,924 for operation
and maintenance, including $13,163, river and harbor funds.
516            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                          Cost and financial summary

                                                   Fiscal year ending June 30                           Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                                   1950          1951         1952          1953         1954           priorto 1950

New work:
   Appropriated........         $1, 500, 000    $800, 000    $707, 000   -$362, 593 -   1,-----. ---        $4, 637, 000
   Cost . . ........ 1, 456, 504               1, 856, 328    342, 724       29, 167      $1, 461            4, 627, 9031
Maintenance:
   Appropriated .....--------       60, 000       38, 000      80, 000       91, 201      62, 600               347, 964
   Cost--.___      ..-              34, 589       51, 672      80, 585       78, 856      87, 087              345, 9242


  1In addition, $2,000 expended from contributed funds for maintenance.
  2 Includes $13,163 of river and harbor funds for maintenance.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954--..-.. .--...---...-....--. $1,758
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955.....------------------------------------------------                        1,758

24. SNAGGING AND CLEARING UNDER AUTHORITY OF SECTION 2
    OF THE FLOOD CONTROL ACT APPROVED AUGUST 28, 1937,
                      AS AMENDED
   The Flood Control Act approved August 28, 1937, as amended
by the Flood Control Acts approved August 11, 1939, August 18,
1941, and July 24, 1946, authorized the allotment of not to exceed
$1,000,000 from flood-control appropriations for any one fiscal
year for the removal of accumulated snags and other debris, and
clearing and straightening the channel in navigable streams and
tributaries thereof, when in the opinion of the Chief of Engineers
such work is advisable in the interests of flood control: Provided,
That not more than $50,000 shall be expended for this purpose for
any single tributary from the appropriations for any one fiscal
year.
   During the fiscal year approximately 651,873 cubic yards were
excavated in improving 13.45 miles of channel in Bayou des Cy-
prairres, Brush Bayou, and Day Creek.
   Contract has been awarded for construction of approximately
1.9 miles of channel enlargement and realinement in Natalbany
River. No work was accomplished during the fiscal year.
   The total costs were $104,885 for new work.
   To date, the following work has been completed under this au-
thorization in the New Orleans district:
                        FLOOD CONTROL-NEW ORLEANS, LA., DISTRICT                                                                     517

                                         Item                                           Improvement
                                                                                           (miles)            Completion
                                                                                                                date               Cost


Barkman Creek, Tex.:
    Clearing and snagging -----------------                              __-----.0.06-5.2
                                                                                                            August 1949......      $60,357
     Excavation......--------------------------------                                         0.05.-8.69
Bayou des Cyprairres, La., channel enlargement, excava-
  tion        ........   .....................-----------------------------------------------        5.4    November 1953-..         42,498
Bayou Francois, La., clearing and snagging.... ......--------------- 0-8.26                                April 1948____....       13,500
Bayou Galion, La., clearing and snagging                         -----------------              10-18.32   September 1947   --      25,501
Bayou L'Eau Bleu, excavation-.........                                ________       -____ 3.16-11.5       September 1948 .- -     44,081
Bayou Vincent:
     Excavation---.------------------------------------                                       0.48-1.35
     Clearing and snagging __9-                     ---            __
                                                                    --         --_____        0. 00-0. 49   December 1947.--        13,000
Brush Bayou, channel improvement and realinement.....                                            0-4.35    December 1953_-         48,317
Cane Creek:2.39-3.00
     Excavation (122,846 cubic yards) --------------------                                    3.90-4.75
     Clearing and snagging....                   ...-------------------------                 4.75-5. 45    August 1950......
     Denton Creek___..............                  .......... _        .......         0.00-0.70                                   37,645
     Realinement (25,763 cubic yards)- ----..............                               3.14-3.90       November 1950__.
Day Creek, Tex., and Ark., channel improvement and re-
  alinement ...------------------ ------------------------                                     3.7       October 1953-.....         29, 622
Little Cypress River, Tex.               1I....................                                ...... . January 1951.....           12,626
Mustang    Creek:
     Excavation        ..............      ...                ....       ..     ..     26.39-25.60      May 1948........            25,000
     Clearing and snagging_____-...... ....               . ...            .....       25.60-19.90      July 1948.........
     Excavation....-----------------------------------_                                25.60-23.47      November 1952...            17, 033
Natalbany River, La.:                                                                  14.95-12.54
     Excavation -           -         ....                                             12.45-11.93
                                                                             .-----------------------------------
                                                                                                        SMarch 1953-......          49, 480
     Clearing and snagging- ___________.     ...             ._______----              12.54-12.45
New River:
     Excavation..........-----------------------------                      ------ 0.00-2.22            April 1948-........         31,500
     Clearing and snagging..........----------------------------                        5.00-11.50      June 1948.........31,          500
Ponchatoula Creek, clearing and snagging-                                                3.8-7.09       May 1949___ ......          10,464
Posten Bayou, La., and Ark.:
     Clearing and snagging             ----------------------                           8.76-12.17
                                                           -                         { 2.20-4. 60       April 1951_.. __            46,021
     Excavation (202,450 cubic yards)- --------
Selsers Creek, La., clearing and snagging......------------------                              0.415    July 1950-,._....            4,958
Sulphur River, Tex., 3.14 miles---.....................                            .        185-195     October 1952-.....          46,082
Swan Lake, Ark., clearing, snagging, and channel enlarge-
  ment-------------------------...................................--.........              (2)                                       2, 200
Wallace Bayou, La., clearing and snagging---.--------.                                   0.0-3.2        September 1951 ..           11,502
Yellow Water River, La., clearing and snagging----.....                                  0.0-2. 75      October 1950_..-.            3,136


  1 Due to high stages on Little Cypress River, it was necessary to terminate contract covering this work
by supplemental agreement on Jan. 18, 1951.
  s The work on Swan Lake was advertised on Oct. 30, 1947; however, the bids were canceled and this
work was accomplished with that done on Red River levees below Denison Dam.


  The total costs to the end of the fiscal year were $574,524 for
new work.
                                                           Cost and financial summary
                                    |-

                                                                    Fiscal year ending June 30                             Total to June
                                                                                                                          30, 1954, includ-
                                                                                                                          ing fiscal years
                                               1950               1951           1952           1953           1954        prior to 1950

New work:
   Appropriated_ _                          $115,
                                            _        000          $14,305       $122,010        $87,877       -$6, 562            $597,431
   Cost.   _-                                    29, 372           94, 058        31, 797       100, 395       104, 885            574, 524


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954.............................. $7, 007
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955...     .................................................................................. ................. 7,007
 518                  REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   25. SMALL FLOOD CONTROL PROJECTS UNDER AUTHORITY OF
       SECTION 205 OF THE FLOOD CONTROL ACT APPROVED
                   JUNE 30, 1948, AS AMENDED

   The Flood Control Act approved June 30, 1948, as amended by
the Flood Control Act approved May 17, 1950, authorized the allot-
ment of not to exceed $3,000,000 from flood-control appropriations
for any one fiscal year for the construction of small flood-control
projects not specifically authorized by Congress, and not within
areas intended to be protected by projects so authorized, which
come within the provisions of section 1 of the Flood Control Act
of June 22, 1936, when in the opinion of the Chief of Engineers
such work is advisable; Provided, That not more than $150,000
shall be allotted for this purpose at any single locality from the
appropriations for any one fiscal year, and that the work shall be
complete in itself and not commit the United States to any addi-
tional improvement to insure its successful operation..
   During the fiscal year Bayou Choupique was improved by con-
tract under this authority. Work commenced on July 11, 1953,
and was completed on May 2, 1954, when 405,918 cubic yards had
been excavated in constructing-a diversion channel over a distance
of approximately 2.6 miles, and 168,363 cubic yards had been ex-
cavated in completing channel enlargement over a distance of
approximately 2.7 miles. A control structure was constructed near
the head of the diversion channel and since completion, repairs to
hinges on gates of this structure were accomplished by contract.
The costs were $112,229, new work.
   The total costs to the end of the fiscal year under this authority
were $217,109.
                                               Cost and financial summary
                                                       CONSOLIDATED

                                                          Fiscal year ending June 30                      Total to June
                                                                                                         30, 1954, includ-
                                                                                                         ing  fiscal years
                                        1950            1951         1952        1953'        1954         prior to 1950

New work:
   Appropriated..       ------..                       $100, 000
                                               ..------------         $2, 000   $143, 179   -$10, 000            $235, 179
   Cost--------------------------....                       7, 073    88, 284      9, 523     112, 229            217, 109


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954..-----------..... -- $18, 070
    Unobligated balances available for succeeding fiscal year ending June 30,
            1955............-------------------------------------------------                                   18, 070
                    FLOOD CONTROL--NEW ORLEANS, LA., DISTRICT                                                                      519
                    26. INACTIVE FLOOD CONTROL PROJECTS

                                                                  For last          Cost to June 30, 1954                 Estimated
                                                                 full report                                                amount
                    Name of project                                 see                                                    required
                                                                  annual              Con-           Operation                to
                                                                  report           struction            and                complete
                                                                    for-                            maintenance
1. Hempstead County Levee District No. 1,                          1941              $88, 006 -----------                      (2)
      Ark.'                       1- - - - - - - - - -       -
2.  Mooringsport Reservoir, La.                    ... _            1951                69, 008         _
                                                                                                   _----------    $11,130,992
3.  Black Bayou Reservoir, La.'___________... __                    1945       .                                       714, 000
4.                         1 of Shreveport, La.'
    Red River in the vicinity                                       1953            3, 908, 000 ....-----.-----       (2)
5.  Red River Parish, La.' .---.------.---.---                      1939               149, 435 ...--------------    (2)
6.  Bayou Bodcau, Red Chute, and Loggy                              1948               319, 200 --------------       (2)
      Bayou, La.'
7. Bayou Pierre in the vicinity of Shreveport,                     1951             ' 243, 336      .--------------            (2)
      La.'
8. Colfax, Grant Parish, La.' s..                                  1938               70, 348 --------------                      (2)
9. Grant Parish below Colfax, La. _____----             _          1941               38, 809 ..------------                     (2)
10. Pineville, Red River,
                     I.    La.'_ .. ________-----                   1953              232, 426 ..............----------           (2)
11. Saline Point, La.'-----------------------    __        -        1945              124, 111 ..............                      (2)
12. Emergency bank protection work under                            1953             6293,096 ......................------------------
      authority of sec. 14 of the Flood Control
      Act approved Dec. 22, 1944, as amended.


I 1Incorporated in the project "Red River below Denison Dam."
  2 Completed.
  3 Work not started; deferred pending further study.
4 In addition, $89,047 was expended from contributed                 funds.
  s Completed under provisions of sec. 7 of the Flood                 Control Act approved May 15, 1928, as amended
by sec. 9 of the Flood Control Act approved June 15,                  1936, and included in 1939 Annual Report of the
President, Mississippi River Commission, page 2214.
  6 In addition $115,138 was expended from contributed                funds.


                                  27. GENERAL INVESTIGATIONS
  Examinations and surveys. The cost of work during the year
was $92,335, of which $19,149 was for navigation studies; $8,680
was for flood control studies; $6,489 was for beach erosion co-
operative studies; $53,408 was for special studies (Arkansas-
White-Red River report) and $4,609 was for collection and study
of basic data. The unexpended balance was $20,957 and there
were no accounts receivable.
  The unexpended balance plus an additional sum of $125,000 can
be profitably expended during fiscal year 1955 as follows:
      Accounts payable......... ..............................                                                 ..              $1, 772
      Examination and surveys:
          Navigation studies .....................................................
          Flood control studies ..-----------
                                                                                                             $28,
                                                                                                  $........ 492
                                                                                                      20, 148
          Beach erosion cooperative studies-available for revocation                                         11
          Special studies .....................................................- ................. 50, 157
               Total examination and surveys.........................................                                          98,808
             Collection and study of basic data........................................................                        45,377

                                                                                                                             145,957
520               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Collection and study of basic data. The following work accom-
plished under collection and study of basic data consisted of non-
cooperative stream gaging in areas not properly chargeable to
reports or projects, $2,038; storm studies of the unprecedented
rainfall of April-May 1953, $1,021; flood emergency studies for
use in development of flood fight plans, $760; and flood investiga-
tions in areas not properly chargeable to reports or projects, $791.
                       28. INSPECTION OF COMPLETED PROJECTS
   Inspection of completed flood control structures was made in
the Arkansas, Middle Red River, and Shreveport sectors, to de-
termine the condition of these structures and the need for future
repairs. The costs were $3,075.
                                              Cost and financial summary

                                                        Fiscal year ending June 30                                   Total to June
                                                                                                                    30, 1954, includ-
                                                                                                                    ing fiscal years
                                       1950           1951            1952              1953            1954          priorto 1950
Maintenance:
   Appropriated____.                 .-----------       $2, 750                         $3, 000         $4, 300               $10, 050
     Cost -----------------            ---            - 1, 547              $15          2, 662          3, 075                  7, 299


    29. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
  Flood Control Emergencies---Repair and Flood Fighting and
Rescue Work. (Section 208 of the 1948 Flood Control Act,
section 210 of the 1950 Flood Control Act, and supplemental
authorizations).
  During the fiscal year the following work was completed and/or
accomplished under such authority:

                                                                          Linear feet
                                Item                                        of im-         Commenced                Completed
                                                                          provement

Section 210, Flood Control Act 1950
Hired labor:
     Cockfield levee restoration, Cane River Levee and
       Drainage D istrict- ..- __-     _ __.                   . .             3, 509    May 1954_                May 1954.
     All necessary repairs were made to the following
       Sulphur River levees over the limits of the levee
      indicated:                                                                         February 1954.     -     May 1954.
         Item SS-20.8-L, Delta County Levee Improve-
           ment District No. 2_                  __.._.._...... --                675
         Item MS-243.0-R and MS-241.0-L, Delta
            County Levee Improvement District No. 8:
             south bank._.                                                    17, 794
             north bank-_.   ---------------                                   7,147
         Item S-191-L, Red River County Levee Im-
           provement District No. 1          ------------------ 30, 889
         Item NS-5.0-R, Lamar County Levee Im-
           provement District No. 1          -------------......36,391
         Shell Point levee repairs, 19th Louisiana Levee
           and Drainage District, mile 170, over a dis-
           tance of ._..........----------------          ---------               425    December 1953-1 January 1954             1.
Section 208, Flood Control Act 1948:
     Kelly Lake levee setback,
         Item R-417.5-R, Red River levees,
         Miller County, Ark- .               .                  -.-
                                                   ..------------------        1, 400    April 1954.-             In progress.

  1 Work was stopped in January 1954 owing to shortage of funds; approximately 50 percent of the neces-
sary repairs had been accomplished.

    Repairs were made to the floodgate at Hempstead, Ark., by
                 FLOOD CONTROL-NEW ORLEANS, LA., DISTRICT                                                 521
contract, and real estate activities were carried on in Garland
Levee District by hired labor.
   The costs for the work performed this fiscal year amounted to
$90,680 and costs for emergency flood-fighting operations were
$44,003, making total costs $134,683.
   The total costs to June 30, 1954, under this authority were
$9,749,358, of which $2,254,230 was for new work and $7,495,128
for maintenance. In addition, $71,500 was expended from con-
tributed funds.
                                       Cost and jfinancial summary
                                            CONSOLIDATED


                                             Fiscal year ending June 30                         Total to June
                                                                                               30, 1954, includ-
                                                                                               ing fiscal years
                                1950        1951           1952      1953        1954           prior to 19501
New work:
   Appropriated                         - -$1, 121     --........                                   $2, 254, 230
   Cost- - --.  - --    -__ _          .......                              .-          .--
                                                                                         ...         2, 254, 230
Maintenance:
   Appropriated.             $511, 000      556, 042     $233,500    $50, 000    $85, 890             7, 518, 064
   Cost                     1, 344, 685     523, 833      336, 179   128,672     134,683              7, 495, 128

  1 In addition, $70,000 expended from contributed funds for maintenance at Gahagan Bend and $1,500 for
maintenance at Miller County Levee District No. 2.
       IMPROVEMENT OF RIVERS AND HARBORS IN THE
               VICKSBURG, MISS., DISTRICT

   The district comprises a very small portion of southwestern
Tennessee, western Mississippi, southern Arkansas, and north-
eastern Louisiana as embraced in the drainage basins of the eastern
tributaries of the Mississippi River south of Horn Lake Creek to
and including Buffalo River, and of the western tributaries from
and including the Arkansas River from a point 3 miles upstream
from Pine Bluff, and the Ouachita and Black Rivers and tributaries
in Arkansas and Louisiana.
                                                       IMPROVEMENTS
                      Navigation                                       Flood Control--Continued
                                                         Page                                               Page
1. Arkansas River and trib-                                     9. Calion, Ouachita River, Ark.....         535
     utaries, Ark. and Okla............                  523 10. Local protection, Pine Bluff,
2. Ouachita and Black Rivers,                                      Ark................................... 536
     Ark. and La............................             523 11. Bayou Bartholomew, Ark. and
3. Inactive navigation projects......                    528       La...............................      537
                                                             12. Existing levees, floodwalls and
                    Flood Control                                    extensions   thereto from
                                                                     Bastrop, La., to mouth of
4. Ouachita    River and trib-                                       Boeuf River and at West
     utaries, Ark. and La...............                 529         Monroe, La ......................      537
5. Blakely Mountain Dam on                                   13.   Bawcomvillet La.......................   538
    Ouachita River, Ark...............                   530 14.   Big Black River, Miss..............      539
6. De Gray Reservoir, Caddo                                  15.   Homochitto River, Miss............       539
       River, Ark......                 ..........       532 16.   Inactive flood control projects..        541
7. Little Missouri River Basin,                              17.   General Investigations ..............    541
     Ark. ..........................................     532 18.   Flood controlwork under special
8. Murfreesboro Reservoir, Muddy                                     authorizations ...................     541
       Fork (Little Missouri River,
       Ark.) .......................................     535

     1. ARKANSAS RIVER AND TRIBUTARIES, ARK. AND OKLA.
  A consolidated report on this project for the Vicksburg, Little
Rock, and Tulsa Districts, submitted by the Little Rock District,
Southwestern Division, is on page 643.
              2. OUACHITA AND BLACK RIVERS, ARK. AND LA.
  Location. Ouachita River rises in Polk County, Ark., and flows
about 600 miles in a general southeasterly and southerly direction
through Arkansas and Louisiana. It is joined by Tensas and
Little Rivers at Jonesville, La., below which place it is called Black
River, and enters Red River 35.5 miles above its mouth. (See
Mississippi River Commission alluvial valley map and Moro Bay,
Ingalls, Strong, Felsenthal, Haile, Drew, Monroe, Columbia, Fort
Necessity, Harrisonburg, Manifest, Tooleys, and Deer Park quad-
rangle maps.)
  Previous projects. The project was adopted by the River and
Harbor Acts of March 3, 1871, June 10, 1872, August 14, 1876, and
July 5, 1884. A separate project for work in the Ouachita River
                                                                                                   523
524      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

between Camden and Arkadelphia was adopted by the River and
Harbor Act of August 11, 1888. For further details, see page
1869 of the Annual Report for 1915, and page 900 of the Annual
Report for 1938.
   Existing project. This provides for a navigable depth of 61f2
feet at low water from the mouth of Black River., La., to Camden,
Ark., a distance of 351 miles, by the construction of 6 locks and
dams, with necessary dredging, and for removal of logs, wrecks
and overhanging trees, etc., between mouth of Black River and
Arkadelphia, Ark., 417 miles, and for a channel 7 feet deep and
of suitable width from the improved channel of the Ouachita
River above dam No. 6 to the vicinity of the railroad bridge over
Lake St. Mary, thence a canal of the same depth and 70 feet in
width along the south side of the railroad embankment to high
ground with a suitable turning basin near Felsenthal, a distance
of 3,600 feet. The project also provides for operation and care
of all locks and dams included therein.
   The River and Harbor Act of May 17, 1950, authorized the modi-
fication of the existing project and the project for the Red River
below Fulton, Ark., to provide a channel 9 feet deep and 100 feet
wide from the authorized 9-foot navigation project at mile 31 on
the Red River to the mouth of Black River at mile 35.5, thence
from the mouth of Black River to Camden, Ark., mile 351 on the
Ouachita River, to be obtained by lengthening and deepening
the six existing locks, channel realinement cutoffs where neces-
sary, rehabilitation of the dams, dredging and contraction works,
including the deepening of the Felsenthal Canal below the pre-
viously authorized depth.
   The location and description of the locks and dams which are
included in the project are contained in the table following:
                                                                           Locks and dams, Ouachita River, Ark. and La.

                                                                           Greatest                                Depth
                                         Distance   Above      Width        avail-        Lift         Eleva-         on                                                           Year
                                                    mouth                                                                                                                          Ye        Year
                                          from                 With
                                                                of           able                       tion-       miter       Character     Kind                                opened Year
No.                                                                                        at                                                                  Type of                         of
              Location                                of                    length        low         normal        sill at         of         of               ype o               to         o           Cost
                                                    Black                  for full                     pool       normal       foundation    dam                                    vi-construction
                                                    River                   width                     surface        pool                                                         gation                             M
                                                                            of lock                                 level                                                                                            C
                                                                                                                                                                                                                     cr
                                         Miles      Miles      Feet         Feet         Feet         Feet         Feet
  2   Harrisonburg, La.....                   0.1      73.3           55           268      14.4
                                                                                                      M.S.L.
                                                                                                          21.5            6.9   Piling in    Movable.     Concrete Poiree need-       1918     1921    $470,395
                                                                                                                                                                                                                     z
                                                                                                                                 clay.                       le dam; steel miter-                                         0
                                                                                                                                                             ing lock gates.
  3   Riverton, La.......-..                  2.0     134.0           55           268      14.8          36.2            6.5   Piling in    .__do.....-_ ... do_...-...     .  -. -- 1919     1920        681,073
                                                                                                                                  sand.
  4   Monroe, La-----------...........        4.0     178.1           55           268          8.9       44.9            6.5 _--do-....... do..........do            .     _____   1915       1915 11,225,813
  5   Sterlington Reach, La_                  0.6     208.3           55           268          6.9       51.7            6.6 Piling in ___do- ...         Concrete       Chanoine  1924       1926    901,096
                                                                                                                                 clay.                      wicket dam; steel
                                                                                                                                                            mitering gates.
  6   Near Felsenthal, Ark..                  3.3     238.7           55           268          9.7       61.6            7.6 Piling in ___d--                do_........
                                                                                                                                                                      _____      __ 1913       1923    2 914,845     C
                                                                                                                                 sand.
  8   Near Calion, Ark                       10.5     297. 5          55           268      13.5          75.1            6.5 Piling in ___do-...........do---------------1912                 1926    3   915,446
                                                                                                                                  clay.
                                                                                                                                                                                                                     r2
  1 Includes cost of original structure completed in 1915 at a cost of $641,630. Dam                              2 Includes cost of original structure to June 30, 1919 ($559,539), and the cost of modifi-
failed Aug. 10, 1917, and was rebuilt 1918-22 at a cost of $584,183 under permanent indefi-                     cations to permit elimination of lock and dam 7 ($355,305).                                          ci
nite appropriation for operating and care of canals. Type of dam now is concrete Poiree                           3Includes actual cost of original structure to June 30, 1919 ($592,922) and the cost of
needle pass and Chanoine wicket weir.                                                                           modification to permit elimination of locks and dams 7 and 9 ($322,524).                             CJZ




                                                                                                                                                                                                                     H


                                                                                                                                                                                                                     Cl



                                                                                                                                                                                                                     0
                                                                                                                                                                                                                     01




                                                                                                                                                                                                                     091
526                  REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Floods ordinarily caused fluctuations of stage from 25 to 45 feet
between high and low water. Extreme floods occasionally increase
this range about 10 feet.
   The latest approved (1954) estimate of cost for new work is
$19,142,000, which includes $58,000 for Felsenthal Canal. The
latest approved (1954) estimate of cost for annual maintenance
is $500,000 of which $200,000 is for operation and care of locks
and dams.
   The existing project was authorized by the following River and
Harbor Acts:

     Acts                              Work authorized                                      Documents


Mar. 3, 1871         Open-channel work from Arkadelphia to the mouth_.         Ex. Doc. 60 pt. 4, 41st Cong.,
                                                                              H.
                                                                             3d sess., Annual Report 1876,
                                                                             p. 336.
July 5, 1884         Extension of open-channel work into Black River-... Annual Report, 1883, p. 1155.
June 13, 1902        Construction of locks and dams 4 and 6 (canalization  Specified in act.
                      work based on report contained in H. Doc. 448,
                      57th Cong., 1st sess.; Annual Report 1902, p. 1435).
Mar. 2, 1907         Construction of locks and dams 2 and 8; elimination       Do.
                       from the plan of lock and dam 1.
June   25,   191.0                                                            Do.
                     Obtaining sites for locks and dams 3 and 7----------..........
July   25,   1912                                                             Do.
                     Construction of locks and dams 3 and 7-..........-----------....
Aug.    8,   1917    Construction of lock and dam 5----
                                                     ....-----------------    Do.
Mar.    2,   1919    Modification of locks and dams 6 and 8 by raising     Rivers and Harbors Committee
                      their pool levels which with dredging obviates the     Doc. 7, 65th Cong., 2d sess.
                      necessity for constructing locks and dams 7 and 9.
June 26, 1934 1      Operating and care of locks and dams provided for
                      with funds from War Department appropriations
                      for rivers and harbors.
Aug. 26, 1937        For the 7-foot channel and construction of a canal       Senate      committee
                                                                                                2       print,   75th
                      3,600 feet long to Felsenthal, Ark.                          Cong., 1st sess.
Mar. 2, 1945         Modification of local cooperation by elimination of           H. Doc. 104, 76th Cong., 1st sess.
                       requirement for provision of highway from main
                       highway system to the canal terminal, for Felsen-
                       thal Canal.                                                                                2
May 17, 1950         Modification of existing project to provide for 9-foot   S. Doc. 117, 81st Cong., 1st sess.
                       channel and deepening of canal to Felsenthal, Ark.

1 Permanent Appropriations Repeal Act.
2 This document contains published maps.

   Local cooperation. Local interests are required to give assur-
ances satisfactory to the Secretary of the Army that they will
furnish free of cost to the United States all lands, easements,
rights-of-way, and overflow and spoil disposal areas necessary for
the construction of the project and subsequent maintenance as
and when required; bear the cost of alteration or replacement of
existing highway bridges where necessary; provide adequate
terminal and transfer facilities, open to all on equal terms; and
hold and save the United States free from damage due to the
construction works. Fully complied with for completed portions
of the project.
   Terminal facilities. At Camden, Ark., there is a privately-
owned loading dock with gasoline operated crane. At Calion,
Ark., there is a privately-owned conveyor and dock for unloading
logs. At Champagnolle Landing there is a privately-owned dock
for the loading of gasoline into barges. At Sterlington, La., there
is a private loading dock for loading chemicals. At West Monroe,
         RIVERS AND HARBORS--VICKSBURG,       MISS., DISTRICT     527
  La., there is one privately-owned warehouse. These facilities are
  considered adequate for existing commerce.
     Operationsand results during fiscal year. Maintenance dredg-
  ing was done in the channel of the stream at 58 locations between
  Camden, Ark., and the mouth of Black River. A total of 955,384
cubic yards of material was moved, including 782,316 cubic yards
by the United States cutterhead dredge Todd, and 173,068 cubic
yards by the United States cutterhead dredge No. 2.
     A sheet pile weir was constructed by hired labor at Treadway
Slough at Camden, Ark., involving the placement of 418 tons of
riprap and 197 lengths of 17.5-foot sheet piling.
     The six locks and dams were operated in a satisfactory condition
throughout the fiscal year by hired labor.
     The total costs during the fiscal year were $519,495, of which
 $16,124 were for construction of sheet pile weir at Treadway
Slough, $317,867 were for maintenance dredging, and $185,503
were for operating and care.
     Condition at end of fiscal year. The project providing for a
depth of 6.5 feet has been completed and is being maintained.
New work under the modified project has not been started.
     The six locks and dams embraced in the existing project for
slackwater improvement of the Ouachita River were completed
in 1924 and provide navigation to Camden, Ark. (See table under
existing project.)
     Construction of the canal to Felsenthal, authorized in 1937, has
not been started.,
     The head of navigation is Arkadelphia, Ark., to which point
boats may occasionally run during high water if snags, overhang-
ing trees, or similar obstructions do not interfere. From January
to June the gage at Monroe generally exceeds pool stage (13.3
feet), caused by the river above, and minimum depths exceeding
7 feet are usual between the mouth of Black River and Camden,
Ark., a distance of 351 miles. At intervals during this period, the
reading of the Camden gage exceeds 15 feet, and minimum depths
of 7 feet may be expected between Camden and Arkadelphia.
During the remainder of the year the pools furnished by the six
dams, with moderate dredging in Black and Ouachita Rivers,
provide depths of 6.5 feet between the mouth of Black River and
Camden, Ark., and depths of only a few inches may be expected
between Camden and Arkadelphia, Ark.
    At the end of the fiscal year project depth of 6.5 feet below mean
low water was available between Camden, Ark., and the mouth of
Black River.
   The total costs to the end of the fiscal year under the existing
project were $4,574, 551 for new work, $4,353,588 for maintenance,
and $2,713,165 for operation and care of locks and dams, totaling
$11,641,304.
    In addition, the sum of $2,940,952 was expended between Janu-
ary 25, 1913, and June 30, 1936, on the operation and care of the
works of improvement under the provision of the permanent in-
definite appropriation for such purposes.
 528             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                            Cost and financial summary

                                                      Fiscal year ending June 30                            Total to June
                                                                                                           30, 1954, includ-
                                                                                                           ing fiscal years
                                     1950           1951            1952         1953          1954         prior to 19501
New work:
     Appropriated-------- ------------ -----------------------               ----------------------             $5, 248, 619
    Cost--------             ------- ---------------------------------     ------------                           5, 248, 619
Maintenance:
    Appropriated-----......-    $498, 675   $430, 000 $185, 000  $446, 300    $516, 000                         10, 003, 668
    Cost   ----------------      364, 793    525, 871  243, 140   431, 642     519, 495                         10, 007, 705

    Includes $674,068 for new work for previous projects.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project........................ ...................... $19, 142,000


                           3. INACTIVE               NAVIGATION                PROJECTS

                                                               For last       Cost to June 30, 1954           Estimated
                                                             full report                                       amount
                    Name of project                              see                                           required
                                                               annual           Con-         Operation            to
                                                               report        struction          and            complete
                                                                for-                        maintenance
  1. Bayou Bartholomew, La. and Ark-----------...........         1931            $45, 874        $42, 857       (1 2   5)
  2. Bayous D'Arbonne and Corney, La.........    --------         1941             19, 000
                                                                                    3, 347
                                                                                                   37, 804
                                                                                                    2, 086
                                                                                                                 (1s)
                                                                                                                 (14)
  3. Bear Creek, Miss---- ----........-.-.. -- -                  1920
  4. Big Black River, Miss....-------------                       1895             15, 000 .-------------          4)
  5. Big Sunflower River, Miss--- --....---             -         1942            560, 027        459, 328       (112)
  6. Boeuf River, La- -.------           - --.---           _     1949             30, 000        103, 737     (11 So 1)
  7. Homochitto River, Miss--- ___--.....-.-- .                   1910             15, 482          8, 518        (1)
  8. Little Missouri River, Ark--------------...-                 1873             19, 992 ..--------------      (1 4)
9. Little River, La-------------.-----------                     1890              2, 500 --------------       (1 11)
10. Little Tallahatchie River, Miss------------..............     1913             19, 000                        (--------------
                                                                                                                   1)
11. Mouth of Yazoo River, Miss---- -....-.- -                     1953         1, 179, 211        145, 217       (17)
12. Removing snags and wrecks from the Miss-                      1948     .............          272, 500        (9)
      issippi River below the mouth of Missouri
      River and from the Old and Atchafalaya
       Rivers.
13. Saline River, Ark............................                1931             26, 900        12, 792        (13 4)
14. Steele and Washington Bayous and Lake                        1947             19, 050        10, 110         (78)
      Washington, Miss.
15. Tallahatchie and Coldwater Rivers, Miss.                     1939            43, 481        173, 066         (1e)
16. Tchula Lake, Miss--        ------...------------ - 1921                      19, 385         26, 585          (1)
17. Tensas River and Bayou Macon, La-.-. --                      1949            38, 367         85, 352        (1 0)
18. Yalobusha River, Miss--...........--- .......------------....
                                                              -- 1937             7, 000         15, 936        (141)
19. Yazoo River, Miss        ----..........................      1947           359, 661        480, 605        (16 7)

     1 Completed.
     2 Abandonment recommended in H. Doc. 1692, 64th Cong., 2d sess., and H. Doc. 467, 69th Cong., 1st sess.
       Channels adequate for existing commerce.
       Abandonment recommended in H. Doc. 467, 69th Cong., 1st sess.
     5 See report of the Mississippi River Commission for operations in connection with the Yazoo Basin
flood-control project including channel clearing and rectification and Grenada Reservoir on Yalobusha
River.
     6 See report of the Mississippi River Commission for operations in connection with the Yazoo Basin
flood-control project, including Sardis Dam and Reservoir, on the Little Tallahatchie River, Arkabutla
Dam and Reservoir on Coldwater River, Enid Dam and Reservoir, on Yocona River, and channel clearing
on Tallahatchie and Little Tallahatchie Rivers.
    ?No funds available.
    S Abandonment recommended in H. Does. 1694, 64th Cong., 2d sess., and 467, 69th Cong., 1st sess. See
report of Mississippi River Commission for operations in connection with the Big Sunflower River, etc.,
Mississippi flood control project, including channel clearing and snagging in Steele Bayou.
    9 No funds available under this project. Work is being carried on under appropriation Flood Control,
Mississippi River and Tributaries.
   to Report of New Orleans district, pp. 919-920 for fiscal year 1949.
   11Due to decline of traffic, local interests are no longer sufficiently interested to provide rights-of-way
and dumping privileges.
   12Project curtailment recommended by elimination of work between Pentecost and mouth of Hush-
puckena River. (Abandonment of entire project erroneously recommended in H. Doc. No. 467, 69th Cong.,
  Ia
1st sess.)
      Project curtailment recommended by elimination of work above Girard, La. (Abandonment of entire
project erroneously recommended in H. Doc. No. 467, 69th Cong., 1st sess.)
                 FLOOD CONTROL--VICKSBURG, MISS., DISTRICT                                                        529
          4. OUACHITA RIVER AND TRIBUTARIES, ARK. AND LA.
                                     (FLOOD CONTROL)
   Location. Ouachita River rises in Polk County, Ark., and flows
about 600 miles in a general southeasterly and southerly direction
through Arkansas and Louisiana. It is joined by Tensas and Little
Rivers at Jonesville, La., below which place it is called Black River,
and enters Red River 35.5 miles above its mouth. (See U. S.
Geological Survey State maps and Mississippi River Commission
Alluvial Valley quadrangle maps.)
   The Ouachita River Basin embraces about 25,000 square miles.
Headwater streams drain about 3,500 square miles of rugged ter-
rain of the Ouachita Mountains (including some 1,500 square miles
of the Ouachita National Forest). Downstream the basin com-
prises about 21,500 square miles of hilly uplands and broad plains.
Below Riverton, La., approximately 1,490 square miles are in the
Red River backwater area.
   Existing project. The River and Harbor Act of May 17, 1950
 (S. Doc. No. 117, 81st Cong., 1st sess.), approved the general plan
for flood control on Ouachita River and tributaries, Arkansas and
Louisiana, which provides for the construction of one multiple-
purpose and one flood control reservoir; protection works for three
localities and channel improvement at several points. This act
further authorized the incorporation into the general plan of the
several separate existing projects for flood control along the
Ouachita River and tributaries in the basin above the lower end
of the levees on the east bank of Ouachita River.
   Following are lists of the reservoirs and local protection works
included in the general flood control plan for the Ouachita River
and tributaries, and the existing flood control projects incorporated
into the project:
                                            New projects

                                                               Drainage        Storage (acre-feet)
                                                                                                           Estimated
                 Project                       Stream             area
                                                                (square                                    E
                                                                                                           construc- dstt
                                                                   miles)       Power           Flood      tion cost 1
                                                                                                control

De Gray Reservoir, Ark. 5                  Caddo River....               453   2 420, 000       250,000    $26, 817, 500
Murfreesboro3 Reservoir, Ark.               Muddy
                                         -_._....  Fork....              121                     71, 400     4,190, 000
Callon, Ark.                               Ouachita River                                                       537,000
Local Protection, Pine Bluff, Ark.                                  -_                                          185, 000
Bayou Bartholomew, Ark. and La., in-      -1,730,000
  eluding Deep Bayou, and Overflow
Creek.s
Extension of floodwall at Monroe, La._     Ouachita River -                      -   -      -                   136,000
Bawcomville, La. 5                          .. do--- -----------                                              '288,000

11954.
2 Includes 75,000 acre-feet of conservation storage.
3 Existing project authorized Aug. 18, 1941, and amended by Flood Control Act of May 17, 1950.
4 Includes 3,400 acre-feet of conservation storage.
5 Details presented in individual report.
6 Details presented in S. Doc. 117, 81st Cong., 1st sess.
7 Under sec. 6, Flood Control Act approved May 15, 1928.
530           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                        Incorporatedprojects

                                                                    Flood     Estimated          For last full
                Project                         Type of work       Control   construction       report, see an-
                                                                     Act         cost          nual report for-

Blakely Mountain Reservoir (Lake Oua-
  chita), Ark.'
                                                       --------
                                              Reservoir.........    1944     2$30,800,000          .    (a)
Little Missouri River Basin, Ark.'_--         Reservoir and '       1944     213,   429, 700            (8)
                                                channel im-
                                                provement.
Existing levees and floodwalls and ex-        Levees and flood-    1928-50    6   3,055,956             (3)
tensions thereto from Bastrop, La. to         walls.                (45)
mouth of Boeuf River and at West
Monroe, La.'
Columbia, La-----------------.... .-..        Flood protection_-    1936          * 204,740            1941


1 Details presented in individual reports.
21954.
3 Included in this report.
4 River and Harbor Act of May 17, 1950.
6 Transferred from F. C. M. R. & T.
6 Actual cost of completed project.


   Local cooperation. Requirements of local cooperation for flood-
control improvements within the basin have been met except for
new projects authorized by the act of 1950 on which local interests
have indicated their willingness to comply with requirements.
 (See individual statements for further details.)
   Operations and results during fiscal year. The operations dur-
ing the fiscal year, together with costs for those projects on which
work was in progress, are shown in individual reports.
   Condition at end of fiscal year. The condition of the various
projects on which work has been initiated is given in individual
reports.
     5. BLAKELY MOUNTAIN DAM ON OUACHITA RIVER, ARK.
   Location. The work covered by this project is at the head of
Lake Hamilton (pool of Carpenter Dam) and approximately 10
miles northwest of Hot Springs, Ark., in Montgomery and Garland
Counties, Ark. (See U. S. Geological Survey State map, scale
1:500,000.)
   Previous project. Authorized by the Flood Control Act of 1938,
this provided for participation by the United States in the cost of
construction of a multiple-use reservoir not to exceed $2,000,000.
No construction was undertaken.
   Existing project. This provides for construction of Blakely
Mountain Dam on Ouachita River for flood control and other
purposes in the Ouachita River Basin with a gross storage capacity
of 2,768,000 acre-feet and power installation totaling 75,000 kilo-
watts (2 units at 37,500 kilowatts each).
   The latest approved (1954) estimate of cost is $30,800,000 for
construction and $250,000 for annual maintenance and operation.
   The project was authorized by the Flood Control Act approved
December 22, 1944, and incorporated into the Ouachita River and
tributaries project by the 1950 River and Harbor Act. (See H.
Doc. 647, 78th Cong., 2d sess., which contains the latest pub-
lished map.)
   Local cooperation. None required.
           FLOOD CONTROL--VICKSBURG, MISS., DISTRICT             531
    Operations and results during fiscal year. Contract for con-
struction of main dam and intake structures was completed
September 29, 1953. Work under continuing contract for con-
struction of power plant was continued and is 74 percent complete.
    Work under supply contracts for design and purchase of power
plant and electrical equipment was continued. A radio trans-
mission tower, purchased under supply contract, was erected by
hired labor.
    Contact for clearing the second and major portion of the reser-
voir was completed November 18, 1953. Topping of trees in the
reservoir was continued by hired labor and is 58 percent complete.
Relocation of Forest Service trails was completed. Work under
negotiated contract for relocation of U. S. Highway No. 270 and
State Highway No. 27 was continued and is 93 percent complete.
Relocation of U. S. Highway No. 270 was completed June 15, 1954.
Contract for construction of reservation buildings was completed
November 23, 1953. Work under negotiated contract for reloca-
tion of Washita and South Fork roads in Montgomery County
was initiated in September and completed in October, 1953. Nego-
tiated contract for relocation of power line was completed De-
cember 31, 1953. Work under negotiated contracts for relocation
of telephone lines was initiated August 11 and Ocotber 2, 1953,
respectively, and completed August 30 and November 27, 1953,
respectively.
    Construction of access roads at various points in the Lake
Ouachita area was initiated by hired labor May 5, 1954, and is
25 percent complete.
    The completed works were maintained.
    The master plan for public use facilities was approved by Office,
Chief of Engineers as pertaining to the allocation of areas to be
developed; however, the administration of lands as presented in
the plan is being studied in Office, Chief of Engineers.
    There were 52,500 visitor-days for recreation.
    Costs during the fiscal year were $7,741,197 for new work and
$37,727 for maintenance, totaling $7,778,924.
    Condition at end of fiscal year. Construction of the spillway,
tunnels and appurtenances, and main dam and intake structures
is complete. Construction of power plant is in progress. Supply
contracts for design and purchase of power plant and electrical
equipment are continuing. A radio transmission tower has been
erected by hired labor. Relocations of telephone and power trans-
mission lines are complete. Relocations of Garland and Mont-
gomery County roads are complete. Relocations of cemeteries in
Garland and Montgomery Counties are complete. Relocation of
Forest Service trails is complete. Relocation of U. S. Highway No.
270 is complete. Relocation of State Highway No. 27 is in prog-
ress. Relocation of power lines in connection therewith is com-
plete. Construction of reservation buildings is complete. Clearing
of the reservoir is complete except for topping of trees. Topping
of trees is in progress. Preliminary report on public use facilities
has been approved by Office, Chief of Engineers. The master plan
has been approved by Office, Chief of Engineers as pertaining to
the allocation of areas to be developed; however, the administra-
 532                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

tion of lands as presented in the plan is being studied in Office,
Chief of Engineers. Construction of access roads at various
points in the Lake Ouachita area is in progress.
    Acquisition of land in the dam and Lake Ouachita areas, in-
volving a total of 82,372 acres, is complete.
    The project as a whole was initiated in August 1947 and is 90
percent complete. Working remaining to complete the project
consists of completion of the power plant, completion of topping
of trees, and development of public use facilities.
    The total costs to the end of the fiscal year were $27,815,730
for new work and $37,727 for maintenance, totaling $27,853,457.
                                                  Cost and financial summary

                                                              Fiscal year ending June 30                                       Total to June
                                                                                                                              30, 1954, includ-
                                                                                                                              ing fiscal years
                                           1950             1951              1952               1953            1954           prior to 1950

New work:
   Appropriated
   Cost ... .....
                          _ -
                                   .-
                                        $2, 300,000
                                         2, 970, 782
                                                        $2, 800, 000
                                                         4, 429, 348
                                                                          $5, 700, 000
                                                                           3, 834, 464
                                                                                           $4,018, 000
                                                                                            4, 119, 651
                                                                                                             $4, 957, 290
                                                                                                              7,741, 197
                                                                                                                                    $28, 075, 290
                                                                                                                                     27, 815, 730
Maintenance:
      Appropriated------------------                                                       - -                    45, 000                  45,000
      Cost-_    -                                                                                                 37, 727                  37, 727


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954...----------................                                                     $28, 724
    Appropriated for succeeding fiscal year ending June 30, 1955-..........                                                              2,867, 710
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955............................................................................----------------------------------------. 2,896, 434

                       6. DE GRAY RESERVOIR, CADDO RIVER, ARK.
   Location. The work covered by this project is located on Caddo
River (mile 8), a tributary of Ouachita River, in a narrow, rocky
gorge, in Clark and Hot Spring Counties, Ark., approximately 10
miles north of Arkadelphia, Ark. (For latest published map, see
H. Doc. 117, 81st Cong., 1st sess.)
   Existing project. The plan of improvement provides for the
construction of a multiple-purpose flood control and power reser-
voir at a site on Caddo River designed as "De Gray," as a feature of
the Ouachita River and tributaries comprehensive plan for flood
control. The reservoir will provide a gross storage capacity of
670,000 acre-feet. Power installation will consist of two 16,000
kilowatt units.
   The latest approved (1954) estimate of cost is $26,817,500 for
construction and $250,000 for annual maintenance and operation.
   The project was authorized by the River and Harbor Act ap-
proved May 17, 1950. (See S. Doc. 117, 81st Cong., 1st sess.)
   Local cooperation. None required.
   Operations and results during fiscal year. None.
   Condition at end of fiscal year. The work has not been started.
                           7. LITTLE MISSOURI RIVER BASIN, ARK.
  Location. The Little Missouri River rises in the southeastern
corner of Polk County, Ark., on the southern slope of the Missouri
Mountains and flows in a southeasterly direction a distance of 147
                   FLOOD CONTROL-VICKSBURG, MISS., DISTRICT                                                  533
miles in a tortuous course to enter the Ouachita River 27.6 miles
above Camden, Ark.
   Terre Noire Creek rises in the Athens Plateau, midway between
Arkadelphia and Amity in Clark County, and flows in a general
southeasterly direction a distance of about 45 miles to enter Little
Missouri River on the left bank 2 miles above the mouth of the
parent stream.
   Ozan Creek, formed by the junction of North Fork, Middle Fork,
and South Fork near Blevins, in Hempstead County, flows in a gen-
eral northeasterly direction a distance of about 25 miles to join
Little Missouri River on the right bank at mile 73.2 above the
mouth.
   Existing project. The Flood Control Act approved August 18,
1941, approved the plan for the Narrows Reservoir for flood control
and other purposes on the Little Missouri River, Ark., and for local
flood protection on the main river below Murfreesboro, Ark., and
on the Terre Noire and Ozan Creeks, as set forth in House Docu-
ment 837, 76th Congress, 3d session, and authorized $3,000,000 for
the initiation and partial accomplishment of the project. The
Flood Control Act approved December 22, 1944, authorized the
completion of the project for Little Missouri River in Arkansas.
   The plan of improvement provides for the construction of the
Narrows Reservoir on the Little Missouri River above Murfrees-
boro, Ark., with a gross storage capacity of 410,000 acre-feet and
a powerplant at the dam site with an initial installation of hydro-
electric generating facilities having a capacity of 17,000 kilowatts
and with provisions for future enlargement of those facilities;
channel clearing and snagging on the Little Missouri River above
the mouth of Ozan Creek, and the excavation of 31 cutoffs below
the mouth of Ozan Creek; snagging of the channel of Terre Noire
Creek between the Missouri-Pacific Railroad crossing and the
mouth, the enlargement of 0.9 mile of silted creek channel, the
repair of levee crevasses in the side levees, and the construction
of required drainage ditches; and the excavation of 20 cutoffs on
Ozan Creek between the lower end of the existing drainage ditches
and the mouth.
   The following is a list of the individual projects considered in
the approved plan:


                                                                                   Estimated cost
              Location                       Type of protection
                                                                         Federal         Local        Total

Narrows Reservoir (Lake Greeson)         Reservoir and powerplant_     1 $12, 706,000 --------.    I$12,   706, 000
  near Murfreesboro, Ark.
Little Missouri River, Murfreesboro,     Channel improvement---
                                                              ...---       1 530, 000   $40, 000       1 570, 000
  Ark. to mouth.
Terre Noire Creek, Ark       _    _. _   Channel improvement and            123, 700     10,000            133, 700
                                          repairs to levees.
Ozan Creek, Ark----------------          Channel improvement ......         1 70, 000     8, 000           178, 000

  1 Revised 1954.
  Note. Incorporated into the Ouachita River and tributaries project by the 1950 River and Harbor Act.


   Local cooperation. Fully complied with on Terre Noire Creek.
 534             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Assurances received and approved for work on Ozan Creek and
Little Missouri River.
   Operations and results during fiscal year. Narrows Reservoir
 (Lake Greeson): The facility was maintained and operated and
generation of power was continued throughout the fiscal year. A
total of 18,340,100 kilowatt-hours was produced, of which 18,173,-
340 kilowatt-hours were furnished the Southwestern Gas & Elec-
tric Co. under contract between that company and the Southwest-
ern Power Administration.
   There were 474,300 visitor-days for recreation.
   On July 1, 1953, the flood control pool was empty and storage in
the power pool amounted to 184,300 acre-feet of water. Maximum
pool elevation, 546.9 feet above mean sea level, or 1.1 feet below
maximum power pool elevation, occurred July 27, 1953. Peak in-
flow was 15,000 cubic feet per second on July 27, 1953. On June
30, 1954, the flood control pool was empty and storage in the power
pool amounted to 159,900 acre-feet of water.
   Ozan Creek: Preparation of plans and specifications was com-
pleted.
   Little Missouri River below Murfreesboro: Preparation of plans
and specifications was completed.
   Costs during the fiscal year were $8,302 for new work and $198,-
116 for maintenance, totaling $206,418.
   Condition at end of fiscal year. Narrows Reservoir (Lake
Greeson) : The project was initiated in April 1946 and completed in
February 1953. Generation of power, and maintenance and oper-
ation of the facility are continuing.
   Terre Noire Creek: The improvement is complete. Repairs to
levees were accomplished with emergency funds.
   Ozan Creek: Preparation of plans and specifications is complete.
   Little Missouri River below Murfreesboro: Preparation of plans
and specifications is complete.
   Total costs to the end of the fiscal year were $12,869,803 for
new work and $716,448 for maintenance, totaling $13,586,252.

                                         Cost and financial summary

                                                  Fiscal year ending June 30                      Total to June
                                                                                                 30, 1954, includ-
                                                                                                 ing fiscal years
                                  1950           1951         1952        1953        1954         priorto 1950
New work:
   Appropriated-........ $3, 510, 000             $237, 805   $123, 509    $4, 500   -$3, 437         $12,876,728
   Cost---------------    3,149, 681               464,841      77,897    103,670       8,302          12, 869,803
Maintenance:
   Appropriated ........------     ....----------- 149, 000   170, 000    200, 000    201, 000            720, 000
   Cost--------------      ......------------      155,257    169,861     193,213     198,116             716, 448


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954......---------..............
                                                                                 $154
    Appropriated for succeeding fiscal year ending June 30, 1955------....... 538, 427
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955.....---- ------------------                   -------------------  538,581
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project--------------....................................
                                                                               14, 545
           FLOOD CONTROL-VICKSBURG, MISS., DISTRICT            535
8. MURFREESBORO RESERVOIR, MUDDY FORK (LITTLE MISSOURI
                     RIVER, ARK.)
  Location. The work covered by this project is located on Muddy
Fork (mile 2) of Little Missouri River, in a narrow gorge in Pike
County, Ark., approximately 3 miles northwest of Murfreesboro,
Ark. (For latest published map, see S. Doc. 117, 81st Cong., 1st
sess.)
  Existing project. The plan of improvement provides for the
construction of a flood control reservoir as a feature of the
Ouachita River and tributaries comprehensive plan for flood con-
trol. The reservoir will provide a gross storage capacity of 71,400
acre-feet.
  The latest approved (1954) estimate of cost is $4,190,000 for
construction and $30,000 for annual maintenance and operation.
  The project was authorized by the Flood Control Act approved
May 17, 1950. (See S. Doc. 117, 81st Cong., 1st sess.)
  Local cooperation. None required.
   Operations and results during fiscal year. None.
   Condition at end of fiscal year. The work has not been started.
No funds have been authorized for appropriation, pending further
study of desirability for local contribution.

               9. CALION, OUACHITA RIVER, ARK.
   Location. The work covered by this project is on the west bank
of the Ouachita River near Calion, a small town in Union County,
Ark., about 307 miles above the mouth of Black River and 13 miles
northeast of El Dorado, Ark. (See U. S. Geological Survey map,
scale 1:500,000.)
   Existing project. The plan of improvement provides for the
construction of levees and appurtenances for the protection of the
town of Calion, Ark., Calion Lumber Co. property and Lake Calion.
   The latest approved (1954) estimate of cost is $537,000 for
construction.
   The existing project was authorized by the Flood Control Act
of August 18, 1941 (H. Doc. 427, 76th Cong., 1st sess.), as
amended by the Flood Control Act of May 17, 1950.
   Local cooperation. Local interests are required to furnish all
rights-of-way necessary for the improvements without cost to the
United States; maintain the works after completion in accordance
with regulations prescribed by the Secretary of the Army; and hold
and save the United States free from damages that may result
from or be occasioned by construction of the improvement. Local
interests have signified their willingness to comply with these re-
quirements.
   Operations and results during fiscal year. None.
   Condition at end of fiscal year. Preliminary work was initiated
in fiscal year 1945 on preparation of plans, but was suspended in
view of the statement of local interests that they were unable to
comply with the requirements of local cooperation. The project
was amended in fiscal year 1950 to include protection work for the
expanded area, with the assurance of local interests that the re-
536          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

quirements for local cooperation will be met. Construction work
has not been started. Emergency work, consisting of grading of
the riverbank at the most critical point, laying riprap revetment
along about 100 feet of riverbank and relocating about 1,500 linear
feet of adjacent county road has been accomplished with flood con-
trol, general, emergency funds.
   Costs and expenditures to June 30, 1954, were $110 for new work.
               10. LOCAL PROTECTION,                 PINE      BLUFF, ARK.
   Location. The work covered by this project is located in Jeffer-
son County, Ark., in the vicinity of Pine Bluff, Ark. (For latest
published map, see S. Doc. 117, 81st Cong., 1st sess.)
   Existing project. The plan of improvement involves channel
improvement on the Bayou Bartholomew tributary Pine Bluff out-
let canal, and construction of an intercepting canal from Harding
Drain to Bayou Bartholomew, and clearing of 4 miles of Bayou
Bartholomew.
   The cost of the completed work was $172,582.
   The project was authorized by River and Harbor Act approved
May 17, 1950. (See S. Doc. 117, 81st Cong., 1st sess.)
   Local cooperation. Local interests are required to furnish with-
out cost to the United States, all lands, rights-of-way and ease-
ments necessary for construction of the project; bear the cost of
construction of new highway bridges and alteration or replacement
of existing highway bridges where necessary; clear the channel of
Harding Drain of obstructions to flood flows and construct the nec-
essary laterals; hold and save the United States free from damage
due to the construction work; and to maintain and operate all the
works after completion in accordance with regulations prescribed
by the Secretary of the Army. All requirements with respect to
construction have been met except clearing of the channel of Hard-
ing Drain. Assurances of local cooperation were furnished by the
Harding Drain Improvement District September 23, 1952, and
approved by Lower Mississippi Valley Division by first indorse-
ment dated October 3, 1952. (File 601.52 Ark.R.-Pine Bluf-Gen.)
   Operationsand results during fiscal year. Work under contract
was completed April 28, 1954.
   Total costs during the fiscal year were $122,769 for new work.
   Condition at end of fiscal year. The project was initiated in
February 1953 and completed in April 1954.
   Total costs to the end of the fiscal year were $172,582 for new
work.
                                 Cost and financial summary

                                       Fiscal year ending June 30                        Total to June
                                                                                        30, 1954, includ-
                                                                                        ing fiscal years
                          1950        1951        1952        1953          1954         prior to 1950

New work:
   Appropriated-------- ----- --------------- $265, 000     -$80, 000    .$185,                       000
   Cost    - --....
                 ------------- ------------     19, 610        30, 202      $122, 769            172, 582

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954                     12,418
                                                                   --.................
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955.... ...............................................................
                                          .--..                               12,418
            FLOOD CONTROL--VICKSBURG, MISS., DISTRICT             537
             11. BAYOU BARTHOLOMEW, ARK. AND LA.
   Location. The work covered by this project is located in south-
east Arkansas and northeast Louisiana, and includes the channel
of Bayou Batholomew and its tributaries Deep Bayou and Over-
flow Creek. (For latest published map, see S. Doc. 117, 81st Cong.,
1st sess.)
   Existing project. The plan of improvement provides for inter-
mittent clearing and snagging and closure of high-water outlets on
the main stem; on Deep Bayou, the enlargement of the channel be-
tween miles 2 and 15 and the diversion of the stream by a canal into
Bayou Bartholomew at a point 10 miles below its present mouth;
and clearing and enlargement of the Overflow Creek channel below
mile 23.
   The latest approved (1954) estimate of cost is $1,730,000.
   The project was authorized by River and Harbor Act approved
May 17, 1950. (See S. Doc. 117, 81st Cong., 1st sess.)
   Local cooperation. Local interests are required to furnish with-
out cost to the United States all lands, rights-of-way, and ease-
ments necessary for construction of the project, bear the cost of
construction of new highway bridges and of alteration or replace-
ment of existing highway bridges where necessary; hold and save
the United States free from damage due to the construction works;
and maintain and operate all the works after completion in ac-
cordance with regulations prescribed by the Secretary of the
Army.
   Operations and results during fiscal year. None.
   Condition at end of fiscal year. The work has not been started.

   12. EXISTING LEVEES, FLOOD WALLS, AND EXTENSIONS
  THERETO FROM BASTROP, LA., TO MOUTH OF BOEUF RIVER
                 AND AT WEST MONROE, LA.

   Location. The work covered by this project is located along the
banks of the Ouachita River from the lower end of the levees on
the east bank and upstream, including existing and projected
levee works and flood walls. (For latest published map, see S. Doc.
117, 81st Cong., 1st sess.)
   Existing project. The work covered by this project includes
existing levees, flood walls, and extensions thereto from Bastrop,
La., to mouth of Boeuf River and at West Monroe, La. The Bastrop
to Monroe and West Monroe, La., levees, protection works on the
east bank of Ouachita River at Monroe, La. and vicinity, and those
on the east bank of Ouachita River from above Sterlington, La.,
to below Monroe, La., and the levee walls at Monroe and West Mon-
roe, La., were constructed as a part of the Boeuf floodway project,
approved May 15, 1928, until the fiscal year 1936 when the Boeuf
floodway project was abandoned. The works were carried to com-
pletion as a part of the "Ouachita River Levee System" under the
appropriation for Flood Control, Mississippi River and tributaries.
The Columbia, La., levee was constructed by authority of Flood
Control Act of June 22, 1936 (S. Doc. No. 196, 73d Cong., 2d sess.).
The extension of the flood wall at Monroe, La., to partially close an
 538               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

existing gap was authorized by the River and Harbor Act of May
17, 1950 (S. Doc. 117, 81st Cong., 1st sess.).
  The actual costs of completed works included in this project are
as follows:
Columbia, La., levee-------------....................----..............................................-------------------------.1 $204, 740
Monroe levee wall, West Monroe levee wall, Monroe levee, West Monroe
  levee, Sterlington to Monroe, La                                     .
                                                               ---------...             .  -------------------
                                                                                                       .           .              2 2, 649, 295
Monroe to Sandy Bayou levee (completed to Indian Mound)........---------........--...                                                2 406, 661
  1 Constructed under F. C. G.
2 Constructed under F. C. M. R. & T. and reported in annual report of the Mississippi River Com-
mission. Costs include $134,876 contributed funds.


   The latest approved (1954) estimate of cost of the extension of
the floodwall at Monroe, La., is $136,000.
   Local cooperation. Fully complied with for completed projects
in accordance with requirements of the governing acts. Drainage
works have been constructed by local interests from Bastrop to
Sandy Bayou and at West Monroe. Local interests have also con-
tributed funds, as cited above, in accordance with the requirements
under section 6 of the Flood Control Act approved May 15, 1928.
For the partial closure of the floodwall at Monroe, La., local in-
terests are required to furnish without cost to the United States
all lands, rights-of-way, and easements necessary for construction
of the projects; bear the cost of construction of new highway
bridges and of alteration or replacement of existing highway
bridges where necessary; hold and save the United States free
from damage due to the construction works, and to maintain and
operate all of the works after completion in accordance with regu-
lations prescribed by the Secretary of the Army.
   Operations and results during fiscal year. None.
   Condition at end of fiscal year. Same as shown under "Exist-
ing project."
                                             13. BAWCOMVILLE,                            LA.

   Location. The work covered by this iproject is at Bawcom-
ville, La., a small town in Ouachita Parish, La., approximately 2
miles west of the Ouachita River and approximately 2 miles south-
west of Monroe, La. (See S. Doc. 117, 81st Cong., 1st sess.)
   Existing project. The plan of improvement provides for the
construction of a loop levee, and supplementary drainage works
consisting of a pumping plant, floodgates, and appurtenant ditches
for the protection of Bawcomville, La., as a feature of the Ouachita
River and tributaries comprehensive plan for flood control.
   The latest approved (1954) estimate of cost is $288,000 includ-
ing Government cost of $192,000 under section 6, Flood Control Act
of May 15, 1928, and $96,000 from contributed funds.
   The existing project was authorized by the Flood Control Act
approved May 17, 1950. (See S. Doc. 117, 81st Cong., 1st sess.)
   Local cooperation. Fully complied with.
   Operationsand results during fiscal year. Preparation of plans
and specifications, soils investigations, surveys and mapping for
construction of two pumpiring plants and modification of floodgates
were completed.
                    FLOOD CONTROL-VICKSBURG, MISS., DISTRICT                                          539
   Government costs were $30,734 under section 6, Flood Control
Act of May 15, 1928.
   Condition at end of fiscal year. Construction of the Bawcom-
ville new levee, involving the placement of 283,482 cubic yards of
levee embankment and 234 linear feet of culvert pipe was com-
pleted Novemebr 21, 1950, with funds under section 6, Flood Con-
trol Act of May 15, 1928. Work remaining to complete the project
consists of the construction of two pumping plants and modifica-
tion of floodgates.
   The total Government costs to the end of the fiscal year were
$92,963. In addition, costs from contributed funds amounted to
$31,114.
                                 14. BIG BLACK RIVER, MISS.
   Location. The work covered by this project is on Big 'Black
River, Miss., which flows into the Mississippi River about 25 miles
below Vicksburg, Miss. (See U. S. Geological Survey State map,
scale 1:500,000.)
   Existing project. The plan of improvement provides for im-
provement of the 'flood channel by means of channel clearing and
suitable cutoffs from a point between Choctaw and Webster Coun-
ties, Miss., to the mouth, 325.6 miles. The project lessens the fre-
quency and duration of floods on 180,000 acres of bottom lands.
The existing project was authorized by the Flood Control Act
approved June 22, 1936. The cost of completed work was $910,185.
   The latest approved (1954) estimate for annual Federal cost of
maintenance is $50,000.
   Local cooperation. None required. (Sec. 2 of the Flood Con-
trol Act of June 28, 1938, applies.)
   Operationsand results during fiscal year. Channel maintenance
work, snagging, was completed on a total of 33.5 miles of the
waterway.
   Cost of maintenance was $38,822.
   Condition at end of fiscal year. The existing project was com-
pleted in 1941 and is being maintained.
   Total costs to the end of the fiscal year were $910,185 for new
work and $597,585 for maintenance, totaling $1,507,770.
                                        Cost and financial summary

                                              Fiscal year ending June 30                    Total to June
                                                                                           30, 1954, includ-
                                                                                           ing fiscal years
                                 1950        1951        1952        1953       1954        prior to 1950
New work:
   Appropriated..-------......   ----------------------------------------------
                      ....------........                                                           $910, 185
   Cost- ---------   ---------------------------------------------- --    --------                  910, 185
Maintenance:
   Appropriated ..-------        $60, 000    $16, 000    $13, 400    $58, 000   $54, 400            618, 300
   Cost......----------------     50, 459     36, 356     17, 737     63, 285    38, 822            597, 585



                                15. HOMOCHITTO            RIVER, MISS.
  Location. The project is located along the Homochitto River in
Adams and Wilkinson Counties, Miss. (See Corps of Engineers,
540                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Mississippi River Commission alluvial valley maps and Artonish,
Woodville, and Kingston quadrangles.)
   Existing project. The plan of improvement provides for the
construction of a number of cutoffs, aggregating approximately
5.8 miles in length, which will reduce the length of the river from
Rosetta, Miss., to its mouth from 37.7 miles to 30.6 miles; con-
struction of small earth dams at points where the new cutoffs leave
and reenter the existing channel; clearing and snagging operations
along both banks from mile 1 to mile 35; and blasting along sides
and bottoms of the channel where its development is retarded by
stumps or hard non-erodible clay strata.
   The project results in clearing the riverbed and banks of obstruc-
tions, shortening the channel, and producing a more uniform slope,
thereby resulting in faster runoff of floodwaters in the basin, mini-
mizing the damage to crops and highways and making practicable
more general use of farm and timber lands which have been hither-
to subject to frequent extended inundation. The existing project
was authorized by the following Flood Control Acts:


    Acts                                        Work authorized                                  Documents and reports

June 22, 1936        Small earth dams at heads of minor tributaries and                     None.
                      channel improvement for flood control.
June 28, 1938        Additional channel improvements and related works                      None.
                      for flood control.
Aug. 18, 1941        Additional channel improvements and related works                      None.
                      for flood control on main river and tributaries.




  The cost of the completed work was $205,000. The latest (1954)
approved estimate for annual Federal cost of maintenance is
$5,000.
   Operations and results during fiscal year. No maintenance
work was done. Stream gaging and inspections were continued
with maintenance funds.
  Cost of maintenance was $1,636.
  Condition at end of fiscal year. The existing project was com-
pleted in 1948 and is being maintained.
  Total costs to the end of the fiscal year were $205,000 for new
work and $129,254 for maintenance, totaling $334,254.


                                                  Cost and financialsummary

                                                           Fiscal year ending June 30                          Total to June
                                                                                                               30, 1954, includ-
                                                                                                                ing fiscal years
                                           1950          1951          1952           1953          1954         priorto 1950
New work:
   Appropriated-------- ------------ ----------------------------------------- ---                                     $205, 000
   Cost-- --    -------------------------------------------------------------                                           205, 000
Maintenance:
   Appropriated                            $25, 000 ------------
                                                     .....           -$13, 400    ------------         $600             130, 200
   Cost--------------...............---.    21, 533        $3, 085       1, 618        $1,998         1, 636            129, 254
                 FLOOD CONTROL--VICKSBURG, MISS., DISTRICT                                                          541
                 16.   INACTIVE            FLOOD CONTROL                       PROJECTS

                                                     For last          Cost to June 30, 1954                Estimated
                                                   full report,                                               amount
                Name of project                        see                                                   required
                                                     annual              Con-           Operation               to
                                                     report           struction            and               complete
                                                      for-                             maintenance
1. Buffalo River, Miss_-----------------------         1940 ----------------------                               1 2$235,000
2. Emergency Bank Protection (section 14 of            1953                          ..........---..----------------....
                                                                           $107, 816---
     1946 Flood Control Act).
3. Flood Control Emergencies-Repair and Flood          1953             ' 566, 628        $4, 504, 360 ...---------
     Fighting and Rescue Work (section 210 of
     1950 Flood Control Act).

1 1954.
 $ Deferred indefinitely because of insufficient justification under present conditions.
 $ Does not include $4,677 from contributed funds.

                            17. GENERAL INVESTIGATIONS
   Examinations and surveys. The cost of examinations and sur-
veys during the fiscal year was $35,806. The balance unexpended,
$1,916, will be applied to completion of studies in connection with
the participation of the Vicksburg district in the preparation of
the Arkansas-White-Red River Basins report.
   The additional sum of $37,500 can be profitably expended dur-
ing the fiscal year 1955 to complete the work assigned to the
Vicksburg district in connection with the preparation of the
Arkansas-White-Red River Basins report.
   The cost of collection of basic data during the fiscal year was
$1,946. The balance unexpended, $54, will be applied to continua-
tion of collection of basic data.
   The additional sum of $20,000 can be profitably expended during
the fiscal year 1955.
   Collection and study of basic data. Storm studies: Routine
work was continued on storm studies assigned to this district. A
preliminary investigation was made of data on the May 1953 storm.
   Flood investigations: Flood damage surveys were made of the
May 1953 floods in the Ouachita and Yazoo River Basins.
18. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATIONS
   Snagging and Clearing of Navigable Streams and tributariesin
the Interests of Flood Control (Section 13 of the 1946 Flood Con-
trol Act)
   With funds previously appropriated and contributed under this
head, the following work was done during the fiscal year: Contract
for the improvement of Little Bayou Boeuf, La., between miles
14.53 and 18.92 was completed July 24, 1953. A total of 221,046
cubic yards of material was excavated from the channel. Hired
labor work consisting of the cleanout of the lower 4 miles of Tucker
Bayou, Miss., was initiated July 6, and completed September 2,
1953. A total of 20,930 cubic yards of material was excavated,
and 3.6 miles of channel cleanout was accomplished. Total Gov-
ernment costs under this heading to the end of the fiscal year were
$811,541 for new work. In addition, costs from contributed funds
amounted to $17,128.
542                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                 Cost    and      financial      summary

                                                   UNITED STATES FUNDS
                                                 LITTLE BAYOU BOEUF, LA.

                                                                                                                                        1
                                                               Fiscal year ending June 30                               Total to June
                                                                                                                       30, 1954, includ-
                                                                                                                        ing fiscal years
                                          1950             1951               1952            1953         1954          prior to 1950
New work:
   Appropriated.-------- -------                -$3, 099 ------------                        $49, 000 ........                   75, 901
   Cost............----------------$23, 680 ------------------------............              25, 490      $23, 510              75, 901



                                                  Cost and financial summary
                                                    CONTRIBUTED FUND
                                                 LITTLE BAYOU BOEUF, LA.

                                                            Fiscal year ending June 30                                  Total to June
                                                                                                                       30, 1954, includ-
                                                                                                                        ing fiscal years
                                          1950             1951               1952           1953         .1954          prior to 1950
New work:
                            ------------......----.....--- ....----------....
   Contributed--------..................                                                     $26, 000    -$8, 872               $17, 128
   Cost---------------............      ....---------...........--------------...--------.    16,000         1,128               17,128



                                                 Cost and financial summary
                                                  TUCKER BAYOU, MISS.

                                                               Fiscal year ending June 30                              Total to June
                                                                                                                      30, 1954, includ-
                                                                                                                      ing fiscal years
                                         1950             1951                1952           1953          1954         prior to 1950
New work:
                          ............
   Appropriated--------........------------ ----............------------....... -$36, 882                -$2, 253              $34, 629
   Cost------------------------- -----------------------                              424                  34, 205              34,629



                                               Cost and financial summary
                                              WALKER; LAKE CANAL, MISS.

                                                               Fiscal year ending June 30                              Total to June
                                                                                                                      30, 1954, includ-
                                                                                                                      ing fiscal years
                                         1950             1951                1952           1953         1954          prior to 1950
New work:
     Appropriated--------........ --     -----------------------                             $46, 000    -$7, 349              $38, 651
     Cost----              ------------------------------------                               38,651                            38, 661
      IMPROVEMENT OF RIVERS AND HARBORS IN THE
            MEMPHIS, TENN., DISTRICT

  This district comprises a portion of southeastern Missouri and
southern Illinois, the western portions of Kentucky and Tennessee,
a small portion of northern Mississippi, and northeastern Ar-
kansas. It includes the area embraced in the drainage basins of
the eastern tributaries of the Mississippi River south of the Ohio
River Basin to Nonconnah and Horn Lake Creeks, inclusive, and
those of the western tributaries south of the Little River Diversion
Channel and Commerce, Mo., including the St. Francis River
Basin, and the White River and tributaries below Peach Orchard
Bluff, Ark., on the right bank and this basin below Augusta, Ark.,
on the left bank.
                                            IMPROVEMENTS

                       Navigation                                   Flood Control-Continued
                                                  Page                                                           Page
1. Wolf River (Memphis Harbor),                         4. Mounds and Mound City, Ohio
      Tenrn-....---.....---.. ........ .. .....   543         River Basin, Ill----.......-------..............   546
2. Table of inactive projects ....---.           545    5. Table of inactive projects..........                 548
                                                         6. General investigations--................             548
            Flood Control                                7. Flood control work under special
                                                                                 -------------
                                                              authorization ........................             548
3. Memphis, Wolf River, and
     Nonconnah Creek, Tenn ..----                 545


                1. WOLF RIVER                (MEMPHIS HARBOR),                         TENN.
   Location. Wolf River rises in Benton County, Miss., and flows
generally northwesterly about 100 miles, through Shelby County,
Tenn,, emptying into the Mississippi River within the corporate
limits of the city of Memphis, Tenn. (See Mississippi River Com-
mission alluvial valley maps, scale 1:62,500, and scale 1:500,000.)
  Previous projects. The River and Harbor Act of August 18,
1894, authorized dredging at the mouth of Wolf River as an item
in the improvement of Memphis Harbor, the work being carried
out under the supervision of the Mississippi River Commission.
  Existing project. This provides for a channel 9 feet deep at
low water from its mouth to Hindman Ferry Road (5.5 miles)
with bottom widths of 250 feet from the mouth to Keel Avenue
and 200 feet from Keel Avenue to North Second Street Road, and
thence 125 feet wide from North Second Street Road to Hindman
Ferry Road.
  The estimate of cost for new work, revised in 1952, is $1,504,000.
The latest (1954) approved estimate of cost for annual mainte-
nance is $105,000.
  The work of improvement under the existing project up to North
Second Street Road (3.5 miles) was authorized September 6, 1933,
by the Public Works Administration, and the existing project was
adopted by the River and Harbor Act approved August 30, 1935
(Rivers and Harbors Committee Docs. 26, 72d Cong., 1st sess.,
and 45, 74th Cong., 1st sess.). Sketch maps are printed in the
project documents.
                                                                                                      543


      Sig 18-543.574
544            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Local cooperation. The work under the existing project is
subject to the condition that local interests shall furnish, free of
cost to the United States, all rights-of-way required for channel
enlargement and straightening, and suitable areas with retaining
levees where needed for disposal of dredged material during initial
construction and future maintenance as and when needed, and
shall furnish assurances satisfactory to the Secretary of Army
saving the United States free from damages resulting from the
work. The work is also subject to the provision that no works
shall be undertaken on any section of the channel through or
above any bridge until such bridge has been altered in a manner
satisfactory to the Secretary of Army, without cost to the United
States. The conditions as pertaining to the improvement up to
North Second Street Road have been complied with. Conditions
above that point have not been complied with.
   Terminal facilities. There are 24 terminals in the lowermost 3
miles of Wolf River. Five terminals are operated by common car-
riers, 3 by contract carriers, and 16 are operated privately.
   Operationsand results during fiscal year. Maintenance dredg-
ing during the fiscal year 1954 was conducted with leased plant.
The dredge Burlington moved a total of 1,377,741 cubic yards of
material in maintaining a channel of project dimensions.
   The total costs for the year were $193,617.
   Condition at end of fiscal year. The existing project was about
50 percent complete. At the end of the fiscal year ample depths
existed in the channel below a point 900 feet above Hall Street.
Project depth at low water is maintained in this reach by dredging
as required.
   From this point to beyond North Second Street Road depths of
from 1 to 2 feet obtain during the low water season. The work
remaining to be done to complete the project is the extension of
the channel from North Second Street Road to Hindman Ferry
Road.
   Exclusive of maintenance dredging done during the fiscal year
1936 with Mississippi River funds which were included in the
annual report of the Mississippi River Commission for that year
under the caption "dredges and dredging," the total costs to June
30, 1954, were $1,933,250, of which $586,500 were from Public
Work funds for new work, $1,329,250 were from regular funds for
maintenance, and to cover the cost of retaining levees required of
local interests, there have also been costs charged to contributed
funds amounting to $17,500.
                                       Cost and financial summary

                                                      Fiscal year ending June 30                              Total to June
                                                                                                             30, 1954, includ.
                                1950              1951             1952             1953            1954     prior to 1950 1
New work:
   Appropriated
   Appropriated-------     -----------     -----      ------   ------------    ---------      ------------           $586, 500
                                                                                                                     $586,500

   Cost_------- ---        --               -------
                                           I---                  -------- -----------------     -----                  86,500
Maintenance:
   Appropriated .               $90, 000         $77, 761          $95, 000        $88, 730     2$197, 351          1, 334, 728
   Cost_-- --- ---- ----        102, 973          91, 621           91, 931         90,056         193,617          1, 329, 250

   1In addition, $17,500 for new work was expended from contributed funds.
    Includes $1,851.47 which was moved in to Wolf River, Tenn. from M. & I., contingencies in conversion
to new appropriation structure 1 July 1953.
                    RIVERS AND HARBORS-MEMPHIS, TENN., DISTRICT                                                                      545

                                   2. INACTIVE NAVIGATION PROJECTS

                                                                            For last       Cost to June 30, 1954            Estimated
                                                                          full report,                                      amount
                        Name of project                                        see                                          required
                                                                            Annual          Con-          Operation            to
                                                                            Report        struction           and           complete
                                                                              for-                       maintenance
1. St. Francis and L'Anguille Rivers and Black-
     fish Bayou, Ark.................------------------------.
                                         -                     1943                       $92, 000.34     $300, 449.43         (1)
2. Obion River, Tenn...........................1911                                        28, 716.75     .-.----------..      (S)
3. Forked Deer River, Tenn., including South
    Fork. ..---------------------------------                                 1912         25, 000. 00      12, 818.50         (1)
4. Removing snags and wrecks from the Missis-
    sippi River below the mouth of Missouri
    River and from the Old and Atchafalaya
    Rivers-----.......--...       ..... ....                                  1948
                                                          ...-------------------------.                    318,833.56          ()
5. White River, Ark. (below Peach Orchard
    Bluff)......................-------------------------------- .            1951         25, 000. 00   1, 360, 578. 97       (1)

  1 Existing project is for maintenance only.
  9   Recommended for abandonment in H. Doc. 467, 69th Cong., 1st sess.
  a Completed.
  4   No funds available under this project. Work is being carried on under "Appropriation, flood control,
Mississippi River and tributaries."


      3. MEMPHIS, WOLF RIVER, AND NONCONNAH CREEK, TENN.

    Location. The work covered by this project lies within and
adjacent to the city of Memphis in Shelby County, Tenn., on the
left bank of Wolf River and the right bank of Nonconnah Creek
from the confluence of these streams with the Mississippi River
upstream for approximate distances of 10 and 4 miles, respec-
tively. (See U. S. Geological Survey map of Tennessee, scale
1:500,000, and Mississippi River Commission alluvial valley maps,
scale 1:62,500 and 1:500,000.)
   Existing project. The plan of improvement provides for the
construction of a system (eight sections) of levees, flood walls,
and bank protection, consisting of the following features: About
22,000 feet of earth levee and two concrete railroad floodgates
along the right bank of Nonconnah Creek, extending from high
ground near Tennessee Chute south of Riverside Park to high
ground at Bodley Avenue east of Prospect Street; about 15,600
feet of concrete flood wall, and 31,500 feet of earth levee along
the left bank of Wolf River, extending from downtown Memphis
to high ground near Douglas Park; construction of 6 new pumping
stations and 8 storage reservoirs with appurtenant works for the
disposal of interior drainage; and the construction of a culvert
under North Bellevue Boulevard near Cypress Creek for the en-
largement of the Cypress Creek Reservoir. The projct will pro-
vide protection, with 3 feet freeboard, for the city of Memphis and
adjacent areas against a Mississippi River flood of 54.5 feet stage,
or 4.1 feet higher than the maximum flood of record, which oc-
curred in February 1937. The project was adopted by the Flood
Control Act approved August 28, 1937, and so modified by the
War Department Civil Appropriation Act approved June 28, 1939,
that the cost of providing pumping stations and outlet works for
interior drainage shall be borne by the United States, and further
amended by the Flood Control Act approved July 24, 1946, to in-
crease the total estimated cost of the project by $1,500,000. The
current (1954) estimated cost of construction, is $11,500,000.
 546                   REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

    Local cooperation. General assurances given by the city of
Memphis and Shelby County, Tenn., were approved by the Secre-
tary of War on August 2, 1938. All rights-of-way for the project
have been provided by local interests with the exception of
section 5 and subsections 1-A and 1-E.
    Operations and results during the fiscal year. Planning and
design were continued during the year for sections of the project
not yet completed. Section 1-D and Section 7 are complete, and
Section 1-C is about 95 percent complete. A contract has been
awarded on Section 1-B and work was initiated.
    The costs for the year were $919,493, all for new work.
    Condition at end of fiscal year. Sections 8, 6, 4, and 2 levees,
section 3 wall, Nonconnah Creek, Cypress Creek, May Street,
Workhouse Bayou, Fairfax and Marble Bayou pumping stations,
and appurtenant works have been turned over to local interests
for maintenance and operation.
   The total costs to June 30, 1954, were $8,875,933, all for new
work.
                                                       Cost and financial summary

                                                                     Fiscal year ending June 30                                          Total to June
                                                                                                                                        30, 1954, includ-
                                                                                                                                        ing fiscal years
                                              1950               1951               1952               1953               1954            prior to 1950

New work:
   Appropriated--------.....                $360, 000          $500, 000          $750, 000          $697, 000          $400, 000               $9, 635, 700
                        1,163, 594 537, 186
      Cost-----------...............                                                476, 187           172, 261           919, 493               8, 875, 933

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 ..                                                                            -          $...... 122
                                                                                                                                                   $267,
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955.................................------------------......---------------...................................------........        267, 122
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project ..                                    ... .... ........ .... ....... -                                             864, 300
                                                                                                                                           .- . 1,1..-.........


         4. MOUNDS AND MOUND CITY, OHIO RIVER BASIN, ILL.

   Location. This project is located in Pulaski and Alexander
Counties, Ill., on the right bank of the Ohio River and about 8
miles above the mouth.
   Existing project. The plan of improvement provides for the
construction Of a system of levees and concrete flood walls and
channel diversion, consisting of the following features: The Ohio
River section, including 4,860 feet of new earth levee, 20,120 feet
of levee enlargement, and 785 feet of concrete wall, extending
from high ground about 3 miles north of Mound City along the
river side of State Highway No. 37 and the right bank of the
Ohio River to a point about 2,000 feet northwest of the mouth of
Cache River; the Cache River diversion, unit 1, including the con-
struction of 4,830 feet of new earth levee, and unit 2, including
the construction of 600 feet of new earth levee, and unit 3,
including the construction of 2,450 feet of new earth levee
extending downstream along the Ohio River from the
lower end of the Ohio River section across the old bed of the
Cache River to the northeast corner of the Cairo drainage district
                      FLOOD CONTROL-MEMPHIS, TENN., DISTRICT                                                                           547
levee, construction of 1 new highway bridge and 2 new railroad
bridges across the diversion channel, 2 pumping plants for disposal
of interior drainage, and other appurtenant structures. Units
1 and 2 of the Cache River diversion include excavation of the
diversion channel from the abandoned Illinois Central Railroad
bridge location over the Cache River near Cache, Ill., to the
Mississippi River near the Beechridge gage and construction of
a new earth levee from high ground just east of the upstream end
of the diversion channel to the northwest corner of the existing
Cairo drainage district levee.
    The project will provide protection for Mounds and Mound City,
Ill., and about 8,600 acres of agricultural land against Ohio and
Mississippi River floods equal to the maximum flood of record,
which occurred in 1937.
    The estimated cost of the project (1954) is $1,060,056, ex-
clusive of pumping plant for which the need has not been definitely
determined, and of which an amount not exceeding $635,000 may
be applied to lands and damages; the estimated non-Federal cost
is $9,300. The current (1952) estimate of the annual cost of
maintenance of the Cache River diversion channel and levee is
$6,500.
    The existing project was authorized by the Flood Control Act
approved June 28, 1938.
    Local cooperation. Provisions of section 2 of the Flood Control
Act, approved June 28, 1938, apply to the diversion of the Cache
River and the adjacent levee; whereas the provisions of section
3 of the Flood Control Act approved June 22, 1936, apply to the
remaining levees and flood walls. However, the City of Mounds,
Ill., has recently furnished assurances and has assumed the obliga-
tion of maintaining the Cache River diversion levee. Rights of
way for the levee and flood wall were accepted on June 7, and
July 25, 1940.
    Operations and results during fiscal year. The Government
performed routine maintenance of the Cache River diversion levee.
    The costs during the fiscal year were $2,202.
    Condition at end of fiscal year. Construction of the project was
started in June 1940 and at the end of the fiscal year was com-
plete, exclusive of pumping plants. The work remaining consists
of the construction of the pumping plants.
    The costs to the end of the fiscal year were $1,035,290 for new
work.
                                             Cost and financial summary

                                                          Fiscal year ending June 30                                      Total to June
                                                                                                                         30, 1954, includ-
                                                                                                                         ing fiscal years
                                      1950             1951             1952             1953               1954           prior to 1950

New work:
   Appropriated..$--------             43, 200                           $4, 590                                                  $1. 060, 056
   Cost--.-------------               164, 829         178, 477          60, 415          50, 082              2, 202              1,035, 290

   * Amount of $21,189 transferred from Louisville District which was actually appropriated prior to F. Y.
1954 and has been reflected on reports by that district.

Other new work data:
                                                                          __... $19,127
    Unobligated balance, fiscal year ending June 30, 1954....__..-.-.---.---..
    Unobligated balances available for succeeding fiscal year ending June 30,
        1955..................................................................................      ...........................     19,127
548               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                          5. INACTIVE FLOOD CONTROL PROJECTS

                                                                        For last                 Cost to June 30, 1954                      Estimated
                                                                       full report                                                           amount
                     Name of project                                       see                                                               required
                                                                         annual                  Con-                  Operation                to
                                                                         report               struction                   and               complete
                                                                          for-                                        maintenance
1. Clarendon to Laconia Circle, White River                                 1937          -------............--------------                  $8, 960,000
     Basin, Ark.
2. Big Creek and L'Anguille River, White River                              1937          ...----------------------...........                   86 000
     Basin, Ark.
3. Flood control work under authority of sec. 205                           1952                 62, 821.43 ------- ------ Completed.
     of the Flood Control Act approved June 30,
     1948, as amended.



                                     6. GENERAL INVESTIGATIONS
   Examinations and surveys. The cost of work during the fiscal
year was $25,566 and the unexpended balance was $1,110. The un-
expended balance plus an anticipated allocation of $28,000 will be
applied to reports under way. The additional sum of $55,000 can
be profitably expended in fiscal year 1956.
   Collection and study of basic data. The cost of work for collec-
tion and study of basic data for the fiscal year was $457 and the
unexpended balance was $128. The unexpended balance will be
used as needed. The additional sum of $600 can be profitably
expended in fiscal year 1956.
   7. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
  Snagging and clearing of navigable streams and tributariesin
the interests of flood control. (Section 13 of the 1946 Flood Con-
trol Act).
  Funds were made available during fiscal year 1954 ($50,000) for
snagging and clearing on Float Road Slough (Cache River Trib-
utary), Ark. A contract has been awarded but no work started.
  Channel clearance, consisting of removal of snags, drift, and
other debris, by contract was accomplished as follows:

                                                                                                          Proposed                Com-        Fiscal
                                          Item                                                              work                 pleted      year 1954
                                                                                                           (miles)               (miles)       cost

Middle Fork, Obion River, Tenn.l                       _
                                                 --------------------------------
                                                               -- - - - - - - - - - - - - - - - - - - - - -           6.3             6.3    $35, 418.78
Crooked Creek (Obion River system), Tenn........................
                                                     1- - - - - - - - - - - - - - -                                   3.8             3.8     17,188.52
Middle Fork, Forked Deer (Obion R. system),
                                     2 -- -- --Tenn.
                                               -- -- -- -- -- -- -- -- -- - --                                        5.2             5.2     33,320.06
Float Road Slough (Cache River), Ark. .                                                                               6.2               0      4,033.88

1 Work completed.
2 Under contract.

   Total channel clearance work performed to June 30, 1954, is as
follows:
                                                                                                                                                  Miles
      Hatchie River (and its tributaries), Tenn. and Miss .................................. 184.2
      Obion River (and its tributaries), Tenn....-----------..........---------------....................................... 245.0
      Mayfield Creek, Ky. .......................-   .....---           .....................................................
                                                                               -...                                                       5.0
      Loosahatchie River, Tenn-----...................------------------------.......................................------.............. 3.1
      St. Francis River (and its tributaries), Ark .....................................................                                  3.6
   The total costs to June 30, 1954, were $1,035,010 of which $995,-
                      FLOOD CONTROL-MEMPHIS, TENN., DISTRICT                                                             549
010 was from regular funds and $40,000 from emergency relief
funds.
                                             Cost and financial summary
                     MIDDLE FORK OBION RIVER NEAR DRESDEN, TENN.


                                                         Fiscal year ending June 30                            Total to June
                                                                                                              30, 1954, includ-
                                                                                                              ing fiscal years
                                     1950             1951             1952          1953          1954         prior to 1950

New work:
   Appropriated ....             .......------------------------------------         $50, 000    -$9, 987              $40, 013
   Cost-------------------------------------...............---------......             4, 594      35, 419              40, 013



                                             Cost and financial summary
                             CROOKED CREEK, CARROLL COUNTY, TENN.


                                                         Fiscal year ending June 30                            Total to June
                                                                                                              30, 1954, includ-
                                                                                                              ing fiscal years
                                     1950             1951             1952          1953         1954          prior to 1950

New work:
   Appropriated ----- ...           ------- ------------------------          ...   $30, 304    -$10, 450              $19, 854
   Cost....----------        ----------------------------------                       2,666        17,188               19,854



                                             Cost and financial summary
                     MIDDLE FORK OF THE FORKED DEER RIVER, TENN.

                                                         Fiscal year ending June 30                            Total
                                                                     . .. .       .                           30,         June
                                                                                                                  1954,toinclud-
                                                                                                              ing fiscal years
                                     1950            1951              1952         1953          1954         prior to 1950

New work:
   Appropriated--------......       $50, 000       -$11, 156                        $50, 000     -$2, 723              $86, 121
   Cost-----------------             38, 844       -----------------------           13,957        33, 320              86, 121



                                            Cost and financial summary
                            FLOAT ROAD SLOUGH, WALNUT RIDGE, ARK.


                                                         Fiscal year ending June 30                            Total to June
                                                                                                             S30, 1954, includ-
                                                                                                              ing fiscal years
                                     1950            1951              1952         1953          1954          prior to 1950

New work:
   Appropriated.......       ------------------------          ------------ ------------          $50, 000             $50, 000
   Cost-----------------------------                                ------------                    4, 034               4, 034


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 ...                         $18,300
                                                                    .........................
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955              .....
                            . ...... . .....
                 -...........-....            ....
                                                 ................
                                                             . .... ........  .... 18 ,300

                                            Cost and financial summary
                 HURRICANE AND AUNT BETTY RODGERS DITCHES, ARK.

                                                        Fiscal year ending June 30                            Total to June
                                                                                                             30, 1954, includ-
                                                                                                             ing fiscal years
                                    1950             1951              1952         1953          1954         priorto 1950
New work:
   Appropriated --          ------------------------------------                    $42, 000    -$13, 252              $28, 748
   Cost----------            ------------------------------------                    28,748                             28, 748
550             REPORT OF CHIEF OF iENGINEERS, U. S. ARMY, 1954

  Flood control emergencies-repair and flood fighting and rescue
work (Section 210 of the 1950 Flood Control Act and supplemental
authorizations).
  The total costs of work performed under this authorization dur-
ing the fiscal year were $11,120.
  The total costs to June 30, 1954, were $2,805,349.
                                          Cost and financial summary

                                                  Fiscal year ending June 30                           Total to June
                                                                                                      30, 1954, includ-
                                                                                                      ing fiscal years
                                  1950         1951           1952        1953           1954           prior to 1950
Maintenance:
   Appropriated.                 $392,919     $162, 879       $15,198      -$870       -$2, 000             $2, 818,565
    Cost ....----------------     620, 901     258,331        118, 064         8,044      11,120             2, 805,349



  Flood control emergencies--repairand flood fighting and rescue
work-emergency repairs, Mississippi River, Dyer County Levee,
Tenn. (1st Deficiency Appropriation Act of 1949).

                                          Cost and financial summary

                                                 Fiscal year ending June 30                            Total to June
                                                                                                      30, 1954, includ-
                                                                                                      ing fiscal years
                                  1950         1951           1952        1953          1954            priorto 1950

Maintenance:
   Appropriated__  --------      $135, 000     $19, 529                  -
                                                              $30, 000 .....           -$2,    000            $182, 529
    Cost..........-----------------14, 309      32, 487       103, 352     $8, 044        11, 120              169, 313


   Emergency bank protection (Section 14 of the 1946 Flood Con-
trol Act).
  Funds were made available during fiscal year 1954 ($50,000) for
emergency bank protection work in Oak Donnick Floodway, Ark.,
for the protection of U. S. Highway No. 63 bridge.
  The cost of work for the year was $175. The unexpended bal-
ance of $49,825 will be used to complete the work.
                                         Cost and financial summary

                                                 Fiscal year ending June 30                            Total to June
                                                                                                      30, 1954, includ-
                                                                                                      ing fiscal years
                                 1950          1951           1952       1953           1954           priorto 1950

New work:
   Appropriated         ------------------------------------ -                          $50,000                $50,000
   Cost         ....       ...           --               -     - ----   -----                 175                 175


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954........     ...... $49, 825
                                                                  ------------.
    Unobligated balances available for succeeding fiscal year ending June 30,
          1955 _.
                ......----------.........                                                            ...... 49, 825
       IMPROVEMENT OF RIVERS AND HARBORS IN THE
               GALVESTON, TEX., DISTRICT

   The Galveston District comprises the drainage basin of all the
short streams arising in the coastal plain of Texas and flowing into
the Gulf of Mexico, including the entire basin of Buffalo Bayou,
San Jacinto, San Bernard, Lavaca, Navidad, Mission and Aransas
Rivers. It also includes the lower basins of the major streams
flowing into the Gulf as follows: Sabine River, Texas and Louisi-
ana, below Orange; Neches River below Beaumont; Trinity River
below Liberty; Brazos River below the confluence with Navasota
River; Colorado River below Austin, Guadalupe River below the
confluence with the San Marcos River; San Antonio River below
Goliad; Nueces River below Calallen. It further embraces the
coastal area situated to the east of the Missouri-Pacific Railroad
between Calallen and Raymondville, and all of Starr, Hidalgo,
Cameron, and Willacy Counties, covering the Lower Rio Grande
Valley.
                                                IMPROVEMENTS

                     Navigation                                           Navigation-Continued
                                                    Page                                                              Page
1. Sabine-Neches Waterway, Tex..                   551 11. Clear Creek and Clear Lake,
2. Gulf Intercoastal Waterway                                Tex----..........---------................ ------..........581
      between Apalachee Bay, Fla.,                      12. Dickinson Bayou, Tex.........---------....                   582
      and the Mexican border                            13. Chocolate Bayou, Tex...---------..........                   583
      (Galveston district)................          557 14. Freeport Harbor, Tex..--------.............                  584
3. Galveston Harbor and Chan-                          15. Channel from Pass Cavallo to
                       ----------------
      nel, Tex...................................   565       Port Lavaca, Tex.........---------..........               587
4. Texas City Channel, Tex..........               568 16. Port Aransas-Corpus Christi
5. Channel to Port Bolivar, Tex....                570       Waterway, Tex.....-................                        589
6. Houston Ship Channel, Tex......                 572 17. Brazos Island Harbor, Tex........                            594
7. Double Bayou, Tex....................           575
8. Anahuac Channel, Tex..............              576                       Flood Control
9. Trinity River and tributaries,                      18. Buffalo Bayou, Tex..-----...-----..............              599
      Tex....--------------------                   577 19. Table of Inactive Projects..........                         601
10. Cedar Bayou, Tex.............-----------.....   579 20. General Investigations--------............                   602

                        1. SABINE-NECHES WATERWAY,                                     TEX.
  Location. This is a consolidation of the old improvements of
"Harbor at Sabine Pass and Port Arthur Canal" and "Sabine-
Neches Canal, including Sabine River to Orange and Neches River
to Beaumont, Texas." Sabine Pass is on the Gulf of Mexico, ap-
proximately 58 miles east of Galveston and 280 miles west of South-
west Pass, Mississippi River. It connects Sabine Lake with the
Gulf of Mexico. The Port Arthur Canal extends from near the
upper end of Sabine Pass to the Port Arthur docks at the mouth of
Taylors Bayou, a distance of 7 miles. Near its upper end, the
Sabine-Neches Canal joins and extends to the mouth of the Neches
and Sabine Rivers. The waterway next extends up the Neches
River to Beaumont and up the Sabine River to Orange. (See U. S.
Coast and Geodetic Survey Charts Nos. 517 and 533.)
  Previous projects. The original project for improvement of
Sabine Pass was adopted by River and Harbor Act of March 3,
1875, and subsequent projects and modifications by River and Har-
bor Acts of August 2, 1882, June 3, 1896, June 13, 1902, and June
19, 1906.           The Port Arthur Canal was conveyed to the United
                                                                                                          551
552                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

States free of cost in 1906, and the River and Harbor Act of July
25, 1912, incorporated it in the project. The Sabine and Neches
Rivers were first improved under the River and Harbor Acts of
June 18, 1878, and March- 3, 1899, and the Sabine-Neches Canal
was first improved under the River and Harbor Acts of March 3,
1905, and March 2, 1907. The project was enlarged by the River
and Harbor Acts of February 27, 1911, July 25, 1912, March 2,
1919, and September 22, 1922.
   For further details, see page 1863 of Annual Report for 1915 for
the Sabine and Neches Rivers, Sabine Pass, and Port Arthur Canal,
and page 985 of the report for 1916 for Sabine-Neches Canal.. (See
also pp. 1100 and 1105 of Annual Report for 1921 and p. 874 of
Annual Report for 1926.)
   Existing project. : The existing project dimensions provided for
in the various channels and basins comprising the waterways are
shown in the following tabulation:
                                                                                                           Adopted project dimensions

              Section of Sabine-Neches Waterway, Tex.                                                                                     Depth in
                                                                                                                                         feet below
                                                                                                      Bottom width in feet               mean low
                                                                                                                                         Gulf level
                                                                                            -i                                         I--   ~   --    -




Sabine Pass outer bar channel_____.__.__ ..................                             _        800-........................                              37
Sabine Pass jetty channel .... _______.---.............                          -
                                                                                 ....            500 at inner end, increasing                    (0)
                                                                                                   to 800 at outer end.
Sabine Pass channel..-        --    .     -----................... - 500....--.--..-............-                                                          36
Sabine Pass anchorage basin..............._.........._.......        800 by 3,000 long, exclusive                                                          34
                                                                                                   of channel.
Port Arthur Canal.....................----            -------..........                          400.....-..-..--.-.--.-...-.-                             36
Entrance to Port Arthur turning basin._...... ...                             ....    ..         250 to 540 ........
                                                                                                            ____.......                                    36
Port Arthur:
    East turning basin .................................-----------------------------            420 by 1,800 long ...........                             36
    West turning basin.........._______-.................                                        600 by 1,700 long ............                            36
    Channel from Port Arthur west turning basin to Taylors                                         _- - - - - - - - - - . -
                                                                                                 250                                                       36
        Bayou turning basin.
Taylors Bayou turning basin________________________..______                                      150 to 1,000 by 2,900 long-....                           36
Sabine-Neches Canal:
    Port Arthur Canal to mouth of Neches River_---------                                         400 _ __ - - - - --.......     -                          36
    Mouth of Neches River to mouth of Sabine River ........                                      150........-------------------                            30
Neches River, mouth to Beaumont turning basin, including                                         350 ....-..................                               36
  cutoffs.
Beaumont turning basin_...................______..........                                       500 by 1,500 long __........                              34
Beaumont turning basin extension..._________...............                                      350 by 2,300 long...........                              34
Neches River from Beaumont turning basin to vicinity of                                            ....... . .. . .. . .. .
                                                                                                 200                                                       30
  Pennsylvania shipyard.
Sabine River, mouth to cutoff near Orange-__.---..--...---...                                    125 .............. ..                                     30
Sabine River to Orange municipal wharf .....................                                     200 by 3,000 long-...........                             30
Sabine River cutoff to highway bridge....... ................                                    150.0-------------------         25
Adams Bayou ............................------------------------------------                                                      12
                                                                                                 100-------------------.........................
Cow Bayou:
    Channel..--------..-------------------------------------                                     100 ......   0._............                              13
    Turning basin- ---------------------------------------                                       300 by 500_                      ._                       13

  1 36 at inner end, increasing to 37 at outer end.

   The project also provides for two stone jetties at the Sabine Pass
entrance from the Gulf of Mexico, the western jetty to be 21,860
feet long and the eastern jetty to be 25,270 feet long. The project
further provides for the removal of the guard lock in the Sabine-
Neches Canal, the construction of suitable permanent protective
works along the Sabine Lake frontage owned by the city of Port
Arthur to prevent dredged material from entering Sabine Lake and
to prevent the erosion of the material deposited, the reconstruction
of the Port Arthur Bridge, and the relocation of the Port Arthur
field office.
   The mean tidal variation at the entrance is about 11/2 feet,                                                                                        at
               RIVERS AND HARBORS-GALVESTON, TEX., DISTRICT                                         553
Port Arthur about 1 foot, and at Orange and Beaumont about five-
tenths foot. Prolonged north winds during the winter season have
depressed the water surface as much as 3.4 feet below mean low
tide while tropical disturbances have caused heights as much as 7
feet above mean low tide.
   The estimate of cost for new work, exclusive of $385,500 con-
tributed funds and value of useful work performed by local inter-
ests and of amounts expended on previous projects, is $15,301,000
 (July 1954). The latest approved estimate for annual cost of
maintenance is $786,700 (July 1954), exclusive of $1,835,000
 (July 1954) estimated cost of rehabilitating jetties.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                         Work authorized                               Documents
July 25,1912   Existing project dimensions of jetties, a 26-foot chan- H. Doc. 773, 61st Cong., 2d sess.
                 nel through Sabine Pass, Port Arthur Canal, and
                  Port Authur turning basin; a new turning basin at
                 Port Arthur 26 feet deep, 600 feet wide, and 1,700
                 feet long; a 25-foot depth in Sabine-Neches Canal,
                 Neches River to Beaumont and Sabine River to
                  Orange, including cutoffs and widening of the
                 channels as recommended by the Chief of Engi-
                 neers and approved by the Secretary of War, and
                 purchase of a new dredge.
Sept. 22, 1922 Deepening the channels to 30 feet from the Gulf to H. Doe. 975, 66th Cong., 3d sess.
                  Beaumont, with increased widths and an anchor-
                 age basin in Sabine Pass 32 feet deep over an area
                 of about 2,000 by 1,000 feet.
    Do....... Deepening the Port Arthur turning basin and con- S. Doec. 152, 67th Cong., 2d sess.
                 necting channels thereto to 30 feet. For taking over
                 and deepening Taylors Bayou turning basin and
                 connecting channel to 30 feet. For a 30-foot depth
                 in the channel from the mouth of Neches River
                 to cutoff in Sabine River near Orange.
Mar. 3, 1925 Removal of guard lock in Sabine-Neches Canal-......       H. Doe. 234, 68th Cong., 1st sess.
Jan. 21,1927 Increased widths of channels as follows: Sabine Pass H. Doe. 287, 69th Cong., 1st sess.
                 jetty channel and Sabine Pass to 300 feet, Port
                 Arthur Canal to 200 feet; Sabine-Neches Canal,
                 from Port Arthur Canal to mouth of Neches River,
                 to 150 feet. For dredging 2 passing places in Sabine-
                 Neches Canal, easing of bends, removal and recon-
                 structing Port Arthur field office, extending Beau-
                 mont turning basin upstream 200 feet above the
                 new city wharves, and for an anchorage basin in
                 Sabine Pass, 4,500 feet long, 800 feet wide, and 30
                 feet deep.
Aug. 30, 1936' A depth of 32 feet in the channels from the Gulf to the Rivers and Harbors Committee
                 Beaumont turning basin, including all turning           Doec. 27, 72d Cong., 1st sess.
                 basins at Port Arthur.
   Do....... Deepening the channels to 34 feet with increased Rivers and Harbors Committee
                 widths from the Gulf to the Beaumont turning            Doec. 12, 74th Cong., 1st sess.
                 basin, including all turning basins at Port Arthur.
   Do....... Construction of suitable permanent protective works Specified in act.
                 along the Sabine Lake frontage owned by the city
                 of Port Arthur.
Aug. 26, 1937 Taking over and maintaining channel from Sabine Rivers and Harbors Committee
                 River to Orange municipal wharf.                        Doe. 3, 75th Cong., 1st sess. 4 4
   Do-...... Dredging 500 feet from the eastern end of Harbor Rivers and Harbors Committee
                 Island and for abandonment of the channel south         Doec. 20, 75th Cong., 1st sess.
                  and west of Harbor Island.
June 20,1938 Increased widths of channels from the Gulf to the H. Doe. 581, 75th Cong., 3d sess.
                 Beaumont turning basin and channel connecting
                 Port Arthur west turning basin and Taylors Bayou
                 turning basin, deepening the Beaumont turning
                 basin and Beaumont turning basin extension to 34
                 feet; and for dredging a new cutoff from Smiths
                 Bluff cutoff to McFaddin Bend.
Oct. 17,1940 Abandonment of the Orange turning basin; dredge a S. Doe. 14, 77th Cong., 1st sess.
                 channel 25 feet deep, 150 feet wide, suitably wid-
                 ened on bends, to the highway bridge and dredge
                 a cutoff channel opposite Orange 25 feet deep and
                 200 feet wide, approximately 2,400 feet long.

  1   Pvqvi   sly authorized Sept. 6, 1933, by Public Works Administration.
554              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


    Acts                         Work authorized                                 Documents
                 i                                                  I
Mar.   2, 1945Extension of Beaumont turning basin upstream 300 H. Doc. 685, 76th Cong., 3d sess.
                feet.
    Do ----   Widening Port Arthurwest turning basin to 600 feet.. S. Doc. 60, 77th Cong., Ist sess.
    Do ...-- Dredging a channel from. the Beaumont turning             S. Doc. 158, 77th Cong., 2d sess.
                 basin to vicinity of Pennsylvania Shipyard, 200         (Contains the latest published
                feet wide and 30 feet deep.                              maps.)
July 24, 1946 Deepening the Sabine Pass outer bar channel to 37 H. Doc. 571, 79th Cong., 2d sess.
                feet and the Sabine Pass jetty channel to 37 feet at
                the outer end, decreasing to 36 feet at the inner end,
                deepening to 36 feet Sabine Pass Channel, Port
                 Arthur Canal, Port Arthur east and west turning
                basins, Taylors Bayou turning basin, and the
                channel from Port Arthur west turning basin to
                 Taylors Bayou turning basin, deepening to 36 feet
                and widening to 400 feet the Sabine-Neches Canal
                from Port Arthur Canal to the mouth of Neches
                 River except through Port Arthur bridge; deepen-
                ing the Neches River channel from the mouth to'
                the Beaumont turning basin to 36 feet with widen-
                ing to 350 feet from Smiths Bluff to the Beaumont
                turning basin; deepening the junction area on
                Neches River at the Beaumont turning basin to 36
                feet; and widening the Sabine-Neches Canal be-
                tween the Neches and Sabine Rivers to 150 feet.
    Do------- Improvement of Cow Bayou, Tex., by the construc- H. Doc. 702, 79th Cong., 2d sess.
                tion of a channel 100 feet wide and 13 feet deep at
                mean low tide and about 7.7 miles long, extending
                from the navigation channel in Sabine River to a
                point 0.5 mile above the county bridge at Orange-
                field, Tex., with a turning basin 300 feet wide, 500
                feet long, and 13 feet deep at Orangefield.
    Do __--   Improvement of Adams Bayou, Tex., to provide a H. Doc. 626, 79th Cong., 2d sess.
                channel 12 feet deep at mean low tide and 100 feet
                wide on bottom extending from the 12-foot depth
                in the Sabine River to the first county highway
               bridge across the bayou, a distance of about 8,600
               feet.
May 17, 1950 Deepening to 36 feet and widening to 400 feet the H. Doc. 174, 81st Cong., 1st sess.
                Sabine-Neches Canal in the vicinity of Port Arthur
               bridge; reconstruction of the Port Arthur Bridge
               and relocation of the Port Arthur field office.

   The project is subject to the condition that no dredging shall be
done by the United States within 50 feet of existing pierheads or
established pierhead lines.
   Recommended modification of project. Under date of January
23, 1953, the Chief of Engineers recommended modification of the
existing project to provide for rectification of certain reaches of
the existing Sabine Pass Channel, Sabine-Neches Canal, and
Neches River and Sabine River Channels; widening to 350 feet the
entrance channel to the Port Arthur turning basins; widening the
curve at the junction of Port Arthur and Sabine-Neches Canals;
relocation and enlargement of the Sabine Pass anchorage basin to
a depth of 34 feet, a width of 1,500 feet, and a length of 3,000 feet;
widening to 200 feet the Sabine-Neches Canal from the mouth of
Neches River to the mouth of Sabine River and the Sabine River
Channel to the upper end of the existing project at Orange, except
for the channel around Harbor Island at Orange; deepening to 30
feet the Sabine River Channel from the cutoff near the Orange
municipal slip to the upper end of the project, except around Har-
bor Island; and enlarging the area at the entrance to the Orange
municipal slip to provide a maneuvering basin; with such modifica-
tions thereof as in the discretion of the Chief of Engineers may be
advisable; at an estimated cost to the United States of $6,875,000
for new work and $121,000 annually for maintenance in addition
to that now required (Senate Doc. No. 80, 83d Congress, 2d sess.)
   Local cooperation. Fully complied with except for certain pro-
                RIVERS AND HARBORS-GALVESTON, TEX., DISTRICT                                                555
visions of the River and Harbor Acts of June 20, 1938, and July 24,
1946. Cooperation remaining consists of (1) furnish free of cost
to the United States rights-of-way and spoil disposal areas for
initial work and for subsequent maintenance, when and as re-
quired, and release the United States from any claims for damages
due to construction and subsequent maintenance for widening a
part of the channel connecting Port Arthur west turning basin and
Taylors Bayou turning basin (act of June 20, 1938), and (2) fur-
nish without cost to the United States all lands, easements, rights-
of-way, and spoil-disposal areas which are necessary for construc-
tion and maintenance of the upper 0.6 mile of Cow Bayou Channel
 (act of July 24, 1946).
   Terminal facilities. Modern terminal facilities adequate for
present commerce exist. (See pp. 839 and 840, Annual Report for
1938, and Port Series No. 22 (revised 1946), Corps of Engineers.)
   A number of small privately owned docks have been constructed
at various locations along the waterway since 1946. Terminal facil-
ities have been constructed in the Port Arthur turning basin by
Warren Petroleum Co. and the U. S. Steel Products Co. Moderniza-
tion and enlargement of terminal facilities have been performed at
a number of terminals including Bethlehem Shipyards, Burton
Shipbuilding Co., Gulf Oil Corp., Atlantic Refining Co., Kansas City
Southern Railway Co., Port of Beaumont, Pure Oil Co., Sun Oil Co.,
and Magnolia Petroleum Co.
   Operations and results during fiscal year. New work: Work
under contract for construction of a protective fender for the east
foundation pier of the Port Arthur bridge was completed during
the period July 1 to 9, 1953, at a cost of $2,832.
   Maintenance: Condition surveys and miscellaneous inspections
and reports were performed at a cost of $58,468. Preliminary sur-
veys, plans and specifications were made for the construction of
dredging range towers for hopper dredging at a cost of $1,593.
Work under the contract during the period December 16, 1953, to
February 27, 1954, was done at a cost of $22,128.
   A total of 6,018,525 cubic yards of material were removed from
123,762 linear feet of channels and basins at a cost of $671,507, as
follows:

   Government                                                                  Cubic        Linear feet
    plant or                     Location                      Period          yards        of channel     Cost
     contract                                                                 removed        dredged


Contrat-..-------...   Port Arthur Canal, Port Ar-        July 1 to Nov. 3,   1, 863, 920       20,590    $222, 037
                        thur turning basins and             1953.
                         Sabine-Neches Canal.
    Do ...    ..----------.Sabine Pass Anchorage Basin,   Jan. 4 to May 11,   2, 782, 738       70, 739    302,368
                             Sabine - Neches     Canal,     1954.
                        Neches   River Channel,
                        Beaumont Turning Basin
                        Extension and Beaumont
                        Turning Basin.
Government hop-        Outer bar and jetty channel...     January    1   to   1,371,867         32, 443    147, 102
per dredge     A.                                          Mar. 8, 1954.



    The total cost of all work for the fiscal year was $756,528, of
which $2,832 was for new work and $753,696 was for maintenance.
  Condition at end of fiscal year. The existing project was about
556            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

99.6 percent complete. The Sabine Pass jetties are completed to
full project dimensions. Enlargement of the Sabine Pass outer bar
and jetty channels, Sabine Pass Channel, Port Arthur Canal, turn-
ing basins at Port Arthur, Sabine-Neches Canal, the Neches River
from its junction with the Sabine-Neches Canal to the Beaumont
Turning Basin, Adams Bayou, Cow Bayou to and including the
turning basin, relocation of the Port Arthur field office, and recon-
struction of the Port Arthur bridge was completed. The work re-
maining consists of completing widening and deepening of the
channel from Port Arthur west turning basin to Taylors Bayou
turning basin, and dredging Cow Bayou above the turning basin
near Orangefield.
   The controlling depths below mean low tide in the various chan-
nels and basins were as follows: Sabine Pass outer bar channel, 35
feet; Sabine Pass jetty channel, 34 feet; Sabine Pass Channel, 35
feet; Sabine Pass anchorage basin, 37 feet; Port Arthur Canal, 30
feet; Port Arthur entrance to and including east and west turning
basins, 31 feet; channel connecting Port Arthur west turning basin
with Taylors Bayou turning basin, 35 feet; Taylors Bayou turning
basin, 36 feet; Sabine-Neches Canal from Port Arthur to mouth of
Neches River, 29 feet; Neches River, mouth to Beaumont turning
basin, 36 feet; Beaumont turning basin, 36 feet; Beaumont turning
basin extension, 36 feet; Neches River Channel from Beaumont
turning basin extension to vicinity of Pennsylvania shipyards, 25
feet;: Sabine-Neches Canal, mouth of Neches River to mouth of
Sabine River, 31 feet; Sabine River, mouth to cutoff near Orange,
26 feet; Channel to Orange municipal wharf, 29 feet; Sabine River
cutoff to highway bridge at Orange, 26 feet; Adams Bayou, 13 feet,
and Cow Bayou, including turning basin at Orangefield, 11 feet.
   The total cost of the existing project to June 30, 1954, was as
follows:

                                                                                                                          '
                                                                                New work        Maintenance.l     Total

Regular funds....- --------------------------------------                       $13,874, 590      $12, 639,932   $26,514,522
Public works funds_ --     --------------------- _                                1,363,652     _ _________       1 363 652
     Total United States funds ....          .     _                        _    15, 238,242      12,639,932     27,878,174
Contributed funds (existing project) -                                               353,4500     12..      2    2-77 500

     Total all funds ..-----------...--------                                    15,591,742       12,639,932 1 28, 231,674
Value of useful work performed------------32,000   ------------------                                               32, 000
      Total cost of project       _ _. ...          .   -..
                                                        ...   -...----...        15, 623, 742     12, 639, 932   28. 263,674
               RIVERS AND HARBORS--GALVESTON,                                    TEX., DISTRICT                     557
                                               Cost and financial summary

                                                         Fiscal year ending June 30                       Total to June
                                                                                                         30, 1954, includ-
                                                                                                         ing fiscal years
                                        1950          1951         1952         1953        1954         prior to 1950 12

New work:
    Appropriated........               $749, 961   $1, 500,000    $430, 500   -$20, 000    -$7, 718          $20, 419,074
    Cost..- .-- --...              -    786, 389    1,347, 312     708,972      343, 795       2, 832         20, 419, 074
Maintenance:
    Appropriated .......--------        570, 000      540, 382    439, 185     685, 050     584, 230           15, 023, 547
    Cost.--.---.- ......-               486, 800      658, 240    424,647      543,401     8753,   514         15, 019,427

  1 Includes $5,180,832 for new work and $2,379,677 for maintenance for previous projects.
      In addition, $931,007 for new work was expended from contributed funds.
    ' Difference of $182 between F Y 54 costs shown above and that shown in "Operations and results during
fiscal year" is due to under-estimation of prepayments for June 1954.
Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project.--.i_.....-:.................... ......................          $62, 800

2. 'GULF INTRACOASTAL WATERWAY BETWEEN APALACHEE
BAY, FLA., AND THE MEXICAN BORDER (GALVESTON DISTRICT)
   Location. This section of the Gulf Intracoastal Waterway ex-
tends from a point on the Sabine River about 3 miles below Orange,
Tex., to Brownsville, Tex., a distance of about 421 miles; with a
flood-discharge channel, about 7 miles in length, in the Colorado
River, extending from Matagorda, Tex., to the Gulf of Mexico; a
tributary channel in the San Bernard River, extending from the
Intracoastal Waterway crossing to the State highway bridge some
30 miles above the crossing; a tributary channel, in the Colorado
River, extending from the Intracoastal Waterway upstream a dis-
tance of 17 miles; a tributary channel: about 14 miles in length
extending from the Intracoastal Waterway to Palacios, Tex.; a
tributary channel about 2 miles in length, extending from the
Intracoastal Waterway to Rockport, Tex.; a tributary channel
about .6 miles in length extending from the Intracoastal Waterway
near Port Aransas, Tex., to .the town of Aransas Pass, Tex.; a
tributary channel about one-fourth mile in length extending from
the. Intracoastal Waterway near Port O'Connor, Tex., into Bar-
room Bay; a tributary channel extending about 45.5 miles from the
Intracoastal Waterway by way of Seadrift to a point in the Guada-
lup River 3 miles above Victoria, Tex.; a tributary channel in Red
Fish Bay extending from the Intracoastal Waterway to Port Mans-
field, Tex., a distance of about 11/2 miles; and a tributary channel in
the Arroyo Colorado extending from the Intracoastal Waterway to
558      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

a point near Harlingen, Tex., a distance of about 31 miles and side
channels in the vicinity of Port Isabel, Tex. (See U. S. Coast and
Geodetic Survey Charts Nos. 1116, 1117, 592, 533, 1279, 1280, 1282,
1283, 1284, 1285, 1286, 1287, and 1288.)
    Previous projects. Sabine River Galveston Bay section:
None.
    a. West Galveston Bay and Brazos River Canal, Tex., River and
Harbor Acts of July 13, 1892, July 8, 1896, and June 13, 1902, the
latter providing for the purchase of the Galveston and Brazos River
Canal, and the act of March 2, 1907.
    b. Channel between Brazos River and Matagorda Bay, Tex.,
River and Harbor Acts of June 25, 1910, and March 2, 1919. The
act of July 25, 1912, provided for the construction of highway
bridges at points where the waterway intersected existing county
roads.
    c. Channel from Pass Cavallo to Aransas Pass, Tex., River and
Harbor Acts of March 2, 1907, and July 25, 1912.
    d. Guadalupe River, Tex., River and Harbor Act of March 2,
1907.
    For further details, see page 1102 of the Annual Report for
1922; pages 941, 944, and 947 of Annual Report for 1926; and page
845 of Annual Report for 1938.
    Existing project. The existing project provides for a channel
12 feet deep at mean low water over a bottom width of 125 feet,
with such passing places, widening at bends, locks or guard locks,
and railway bridges over artificial cuts as are necessary from the
Sabine River to Brownsville, Tex.; for the purchase or construction
of a 20-inch pipe-line dredge; for the maintenance of a suitable
flood discharge channel in the Colorado River from Matagorda,
Tex., to the Gulf of Mexico; for a tributary channel 9 feet deep and
100 feet wide in the San Bernard River, extending from the main
channel to the State highway bridge some 31 miles above the mouth
of the stream; for a tributary channel in the Colorado River 9 feet
deep and 100 feet wide, extending from the main channel upstream
a distance of 17 miles, with a turning basin of the same depth, 400
feet wide and 500 feet long at the head of the improvement; for a
tributary channel 9 feet deep and 100 feet wide from Palacios, Tex.,
through Trespalacios and Matagorda Bays to the main channel; for
a tributary channel 9 feet deep and 200 feet wide from the main
channel to the harbor at Rockport, Tex., and improvement of that
harbor to a depth of 9 feet; for rerouting the main channel along
the north shore of Red Fish Bay between Aransas Bay and Corpus
Christi Bay with no change in present authorized dimensions; for
a tributary channel 12 feet deep and 100 feet wide from the main
channel near Port Aransas, Tex., to the town of Aransas Pass,
Tex., ending in a basin of the same depth, 300 feet wide and 2,200
feet long; for a tributary channel 6 feet deep and 60 feet wide from
the main channel near Port O'Connor, Tex., into Barroom Bay; for
         RIVERS AND HARBORS--GALVESTON, TEX., DISTRICT            559
a tributary channel 9 feet deep and 100 feet wide extending from
the main channel in San Antonio Bay to Victoria, Tex.:; for a tribu-
tary channel 12 feet deep and 125 feet wide in Red Fish Bay from
the main channel to Port Mansfield with a turning basin 400 feet by
600 feet and 12 feet deep at Port Mansfield; for a tributary channel
12 feet deep and 125 feet wide from the main channel to the vicin-
ity of Harlingen, Tex., via the Arroyo Colorado with a turning
basin 12 feet deep, 400 feet wide, and 500 feet long at the upper
end; for side channels 12 feet deep and 125 feet wide and 6 feet
deep and 60 feet wide leading from Laguna Madre around the south
part of Port Isabel, Tex., a total length of 11/2 miles; for an alter-
nate channel 12 feet deep and 125 feet wide across South Galveston
Bay between Bolivar Peninsula and the Galveston Causeway; and
for operating and care of the waterway. From the Sabine River
 (3 miles below Orange, Tex.) to the Port Arthur Canal, from Port
Bolivar to the west end of Galveston Channel, from Port Aransas
to Corpus Christi and from Port Isabel to Brownsville, Tex., the
waterway coincides with deep water channels improved and main-
tained under other projects.
    The mean tidal variation is 0.5 foot at Orange, 1 foot at Port
Arthur, 1.3 feet in Galveston Bay, 1.5 feet at Freeport, 1 foot in
Matagorda Bay, 1 foot in San Antonio Bay, 1 foot at Corpus Christi,
1.5 feet at Port Isabel, and 1.5 feet at Brownsville. The extreme
ranges of tide under ordinary conditions are 1 foot at Orange, 1.5
feet at Port Arthur, 2 feet in Aransas Bay, 2.0 feet at Freeport,
1.5 feet in Matagorda Bay, 1.5 feet in San Antonio Bay, 1.5 feet at
Corpus Christi, 2 feet at Port Isabel, and 1.5 feet at Brownsville.
The height of tides is dependent largely on the wind. Strong north
winds have depressed the water surface as much as 2 feet below
mean low tide.
   The modified route of the main channel between Aransas Bay
and Corpus Christi Bay is subject to the provision that no dredging
shall be done by the United States within 50 feet of any wharf or
structure, the proposed drawbridge piers and fenders near Aransas
Pass, Tex., being excepted from this provision.
   The tributary channel in the Colorado River is subject to the pro-
vision that no dredging shall be done by the United States within
  Sfee       nwharf or structu        exceting the highway bridge
which crosses the river a mile 8.3.
   The tributary channel from Palacios, Tex., through Trespalacios
and Matagorda Bays, the tributary channel to Aransas Pass, Tex.,
and the tributary channel to Harlingen, Tex., are subject to the
provision that no dredging shall be done by the United States
within 50 feet of any wharf or structure.
   The estimate of cost of new work is $36,245,000 (July 1954),
exclusive of amounts expended on previous projects. The latest
approved estimate for annual cost of maintenance is $1,714,700
(July 1954), including $408,250 for operation and care of
structures.
 560           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

The existing project was authorized by the following river and
Harbor Acts:

     Acts                           Work authorized                                    Documents 1

Mar. 3, 1925       Channel 9 feet deep and 100 feet wide, from Sabine        H. Doc. 238, 68th Cong., 1st sess.
                     River to Galveston Bay, and for a 20-inch pipeline
                     dredge.
Jan. 21, 1927 Channel 9 feet deep and 100 feet wide, from Galves-               Do.
                     ton Bay to Corpus Christi.
Aug. 26, 1937 Maintenance of a flood-discharge channel in the               Senate Committee print, 75th
                     Colorado River.                                           Cong., 1st sess.
June 20, 1938 Channel 9 feet deep and 100 feet wide in San Bernard          H. Doc. 640, 75th Cong., 3d sess.
                     River, Tex.
     Do.------ Channel in the Colorado River, 9 feet deep and 100            H. Doc. 642, 75th Cong., 3d sess.
                    feet wide, with a turning basin.
     Do-.......    Channel 9 feet deep and 100 feet wide from Palacios       H. Doc. 564, 75th Cong., 3d sess.
                     through Trespalacios and Matagorda Bays.
     Do....... Channel 9 feet deep and 200 feet wide from the main           H. Doc. 641, 75th Cong., 3d sess.
                    channel to the harbor at Rockport, and improve-
                    ment of that harbor to a depth of 9 feet.
     Do-.......    Channel 6 feet deep and 100 feet ' wide from the main     H. Doc. 643, 75th Cong., 3d sess.
                    channel to Aransas Pass, Tex.
July 23, 1942 Enlargement of waterway- from Sabine River to                  Public Law 675, 77th Cong.
                     Corpus Christi and its extension to Brownsville,
                     Tex., so as to provide a depth of 12 feet and width
                    of 125 feet throughout.
Mar. 2, 1945 Channel 6 feet deep and 60 feet wide from main chan-           H. Doc. 428, 76th Cong., 1st sess.
                    nel near Port O'Connor, Tex., into Barroom Bay.
    Do     -...... Enlargement of channel from main channel to Aran-         H. Doc. 383, 77th Cong., 1st sess.
                    sas Pass, Tex., to provide a depth of 9 feet and
                    width of 100 feet.
Mar. 2, 1945 'Channel 12 feet deep and 125 feet wide from main               S. Doc. 248, 78th Cong., 2d: sess.
                    channel to Red Fish Landing, Tex., with a turning
                    basin.
    Do....... Channel 12 feet deepiind 125 feet wide from main               H. Doc. 402, 77th Cong., 1st sess,
                    channel to vicinity of Harlingen, Tex., via Arroyo         (See Public Law 14, 79thCong.)
                    Colorado, with a turning basin.
Julyj24, 1946 Filling a portion of the shallow-draft channel adja-           H. Doc. 627, 79th Cong., 2d sess.
                    cent to the Port Isabel turning basin, construction
                    of a channel to connect the shallow-draft channel
                    with the main channel near the shore line of Laguna
                    Madre, and enlargement of the shallow-draft chan-
                    nel west of this connection, all to a depth of 12 feet
                    and bottom width of 125 feet.
    Do....... Rerouting the main channel along the north shore of            H. Doc. 700, 79th Cong., 2d sess.
                    Red Fish Bay between Aransas Bay and Corpus
                    Christi Bay with no change in present authorized
                    dimensions and to provide for deepening the tribu-
                    tary channel from Port Aransas to the City of Aran-
                    sas Pass to 12 feet and extension of the turning basin
                    to a length of 2,200 feet at the same depth.
May 17, 1950 Alternate channel 12 feet deep and 125 feet wide across         H. Doc. 196, 81st Cong., 1st sess.
                    South Galveston Bay between Port Bolivar and the
                    Galveston causeway.
    Do....... "Red Fish Landing" changed to "Port Mansfield,                 Public Law 516, 81st Cong.
                    Tex."
July 12, 1952 Incorporate a channel 9 feet deep and 100 feet wide            Public Law 527, 82d Coig., 2d
                    from the main channel by way of Seadrift to a point       sess., and H. Doc. 247, 76th
                    on the Guadalupe River 3 miles above Victoria,            Cong., 1st sess.
                    Tex., authorized by River and Harbor Act of March
                    2, 1945, as a part of the Intracoastal Waterway.

  I H. Doc. 230, 76th Cong., 1st sess., and the project documents contain the latest published maps.

  Operating and care of the waterway was included in the project
July 1, 1935, under the provisions of the Permanent Appropriations
Repeal Act approved June 26, 1934.
  Recommended modification of project. Under date of Decem-
ber 22, 1949, the Chief of Engineers recommended modification of
the existing project to provide a basin for a harbor of refuge for
small craft at Seadrift 9 feet deep at mean low water, 200 feet wide,
and 1,000 feet long with an entrance channel 9 feet deep and 100
feet wide from the authorized side channel to Seadrift, and sur-
rounded by a protective levee with its top at elevation 20, with such
modifications thereof as in the discretion of the Chief of Engineers
         RIVERS AND HARBORS--GALVESTON, TEX., DISTRICT             561
may be advisable at an estimated cost to the United States of $52,-
000 for construction and $1,200 annually for maintenance in addi-
tion to that now required. (H.D. 478, 81st Cong., 2d sess.) Under
date of June 26, 1953, the Chief of Engineers recommended modi-
fication of the existing project to provide for widening the tribu-
tary channel between Port Aransas and the city of Aransas Pass to
125 feet; straightening the connecting channel to Conn Brown
Harbor and widening it to 125 feet; and maintaining Conn Brown
Harbor by the United States; all to a depth of 12 feet; with such
modifications thereof as in the discretion of the Chief of Engineers
may be advisable; at an estimated cost to the United States of
$29,000 for construction and $4,000 annually for maintenance in
addition to that now required. (H.Doc. 376, 83d Cong., 2d Sess.)
   Local cooperation. Fully complied with except for the follow-
ing, local interests being required to: (1) furnish free of cost to the
United States rights-of-way and spoil disposal areas for construc-
tion and maintenance for rerouting the main channel along the
north shore of Red Fish Bay between Aransas Bay and Corpus
Christi Bay (Act of July 24, 1946) ; (2) for the upper 31/2 miles of
the tributary channel in the San Bernard River, furnish free of
cost to the United States, all lands, easements, rights-of-way, and
spoil disposal areas for initial work and for subsequent mainte-
nance (Act of June 20, 1938) ; (3) for the tributary channel in the
Colorado River, provide without cost to the United States, all lands,
easements, right-of-way, and spoil disposal areas for initial work
and for subsequent maintenance (Act of June 20, 1938); (4) for
the tributary channel into Barroom Bay, furnish, free of cost to
the United States, all necessary lands, easements, rights-of-way,
and suitable areas for disposal of spoil, as and when needed, and
hold and save the United States free from any claim for damages
resulting from the construction and maintenance of the channel
(Act of Mar. 2, 1945) ; (5) for the navigation channel on the Guada-
lupe River to Victoria, Tex., furnish free of cost to the United
States all lands, easements, rights-of-way, and spoil disposal areas
for construction and for subsequent maintenance as required, hold
and save the United States free from all claims for damages that
may result from the construction and maintenance of the channel,
bear all costs of required bridge modification and give assurances
satisfactory to the Secretary of the Army that they will provide
adequate terminal facilities, including turning basins at Seadrift
and Victoria; and, (6) for the upper 5 miles of the tributary chan-
nel in the Arroyo Colorado to the vicinity of Harlingen, Tex.; pro-
vide, free of cost to the United States, all necessary lands, ease-
ments, rights-of-way, and spoil disposal areas for the initial im-
provement and its subsequent maintenance, when and as required
(Act of March 2, 1945).
   Terminal facilities. There are terminal facilities at Orange,
Port Arthur, Galveston, Freeport, Port Lavaca, Port Aransas, Cor-
pus Christi, Port Isabel, and Brownsville where this waterway co-
incides with channels improved under other projects. (See Port
Series No. 22 (Revised 1946), No. 23 (Revised 1948), and No. 25
(Revised 1948), Corps of Engineers, and reports on Freeport Har-
bor; Channel from Pass Cavallo to Port Lavaca, and Brazos Is-
562      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

land Harbor, Tex.). There are privately owned piers and wharves
at Port Bolivar, Palacios, Rockport, Seadrift, and Aransas Pass,
and municipal wharves at Palacios and Aransas Pass. An assem-
bling basin 300 feet wide by 5,500 feet long with mooring facilities.
Government owned, is under construction at Port Bolivar, Texas,
for interchange purposes of navigation between shallow and deep
draft channels. The facilities are adequate for existing commerce.
   Operations and results during fiscal year. New work: Civil
works investigations were made at a cost of $3,980. Work under
contract for the construction of locks at the Colorado River flood-
gates was continued during the period July 1, 1953, to April 27,
1954, at a cost of $528,116. Preliminary surveys, plans, and speci-
fications for dredging an alternate channel betwen Port Bolivar
and the Galveston Causeway were made at a cost of $3,176, and
work was performed by contract during the period January 23 to
May 22, 1954, removing 2,692,498 cubic yards of material from
36,242 linear feet of the channel, at a cost of $184,718. Prelim-
inary surveys, plans and specifications for turfing at the Colorado
River Locks were made at a cost of $170, and work under the con-
tract during the period May 26 to June 30, 1954, was performed
at a cost of $7,424. Preliminary surveys, plans and specifications
for the construction of mooring walls at the Colorado River Locks
were made at a cost of $1,312.
   Maintenance: The Mud Bayou Bridge near High Island, Tex.,
the Brazos River floodgates near Freeport, Tex., and the Colorado
River Locks, near Matagorda, Tex., were operated and maintained
by hired labor at a cost of $30,343, $62,894, and $55,590, respec-
tively. Condition surveys and miscellaneous inspections and re-
ports were made at a cost of $97,768. Preliminary surveys, plans
and specifications for repairs to the East floodgate at the Colorado
River floodgates were made at a cost of $4,945 and work under the
contract during the period 28 January to June 30, 1954, was per-
formed at a cost of $169,271. Preliminary surveys, plans and
specifications for cathodic protection for the Brazos River flood-
gates and the Colorado River floodgates were made at a cost of
$1,404 and $1,970, respectively. Preliminary surveys, plans and
specifications were made for drilling a new water well at the East
Gate, Brazos River floodgate, at a cost of $232, and work under
the contract during the period March 19 to April 9, 1954, was per-
formed at a cost of $7,007. Preliminary surveys, plans and speci-
fications for the construction of a steel sheet pile guide wall at
Mud Bayou Bridge were made at a cost of $1,170, and work under
the contract during the period October 9, 1953, to April 2, 1954,
was performed at a cost of $60,806.
   Preliminary surveys, plans, and specifications for the construc-
tion of an access road and retaining levee at Mud Bayou Bridge
were made at a cost of $1,008. Preliminary surveys, plans and
specifications for the reconstruction of the Port O'Connor jetties
were made at a cost of $1,247. Preliminary surveys, plans and
specifications for driving reference line piling and the construc-
tion of survey tables in San Antonio and Aransas Bays were made
at a cost of $2,730, and work under the contract during the period
December 16, 1953, to January 23, 1954, was performed at a cost
            RIVERS AND HARBORS-GALVESTON, TEX., DISTRICT                                              563
of $13,477. Work under contract for driving reference line piling
and the erection of informational signs during the period July 1 to
8, 1953, was performed at a cost of $6,596. Preliminary surveys,
plans and specifications for driving reference line piling between
Corpus Christi Bay and the Mud Flats were made at a cost of
$1,513, and work under the contract during the period November
23 to December 4, 1953, was performed at a cost of $8,288. Pre-
liminary surveys, plans and specifications for dredging an assem-
bling basin, entrance channel, and the construction of 28 mooring
dolphins near Port Bolivar were made at a cost of $3,425, and
hired labor work in connection with the contract was performed
at a cost of $608. Preliminary surveys, plans and specifications
for dredging in San Antonio and Aransas Bays were made at a
cost of $3,367.
   A total of 3,335,404 cubic yards of material was removed by
contract from 193,274 linear feet of channel at a cost of $355,450,
as follows:

                                                                        Cubic yards Linear feet
              Location                              Period              of channel     of channel    Cost
                                                                         dredged        dredged

Laguna Madre Mud Flats Area . _ _ .       July 1 to 28, 1953___-            427,348        18,739    $37,707
Corpus Christi Bay to Baffin Bay.__ _-    July 1 to 11, 1953 ---            111,183        20 800      9, 228
Port Isabel to Mud Flats-....---     __   March 8 to June 24, 1954___     1,850,599        99,935    202,090
Freesport Harbor to Gulf, Tex .. _...     March 30 to June 30, 1954         165,004        16, 200    37, 227
Tributary Channel to Palacios ......      April 26 to May 29, 1954 -        381, 270       29, 600    36,139
Matagorda, Tex. to Matagorda Bayy         June 8 to June 30, 1954           400, 000        8,000     33,059



   The total cost for all work during the fiscal year was $1,620,-
005, of which $728,896 was for new work and $891,109, including
$396,640 for operation and care of Mud Bayou Bridge, Brazos
River floodgates, and Colorado River floodgates and/or locks, was
for maintenance.
   Condition at end of fiscal year. The existing project was about
68.9 percent complete. The dredging of the main channel from
the Sabine River to Rockport and from Corpus Christi Bay to Port
Isabel was completed. The tributary channel in the San Bernard
River was completed to 26 miles upstream. The tributary channel
via the Arroyo Colorado to Harlingen was completed to the South-
ern Pacific Railroad bridge about 5 miles east of Harlingen, Tex.
The tributary channel to Palacios, to Aransas Pass, and Rockport,
Tex., were completed. Channel to and turning basin at Port Mans-
field were completed. Shallow draft side channels in the vicinity
of Port Isabel, Tex., were completed. Construction of a railway
bridge near High Island, Tex., of two floodgates at the Brazos River
crossing, and of two floodgates at the Colorado River crossing were
completed. Work remaining consists of dredging the modified
route of the main channel in the vicinity of Aransas Pass, Tex.,
tributary channel in the Colorado River, completing tributary
channels to Harlingen and in the San Bernard River, dredging
branch channel into Barroom Bay, dredging tributary channel to
Victoria, Tex., and completing the conversion of floodgates at the
Colorado River crossing into locks.
   The controlling depths over usable widths at mean low water
 564               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

were 11.0 feet from the Sabine River to Galveston; 10.9 feet from
Galveston to Freeport Harbor; 10.0 feet from Freeport Harbor
to the Colorado River; 9 feet from the Colorado River to Port
O'Connor; 10.3 feet from Port O'Connor to Corpus Christi; 9 feet
from Corpus Christi Bay to Banderia Island (Mile 616 west of
Harvey Lock) ; 9.0 feet from Banderia Island to the Arroyo Colo-
rado; 10 feet from the Arroyo Colorado to Port Isabel; Colorado
River flood discharge channel, 3 feet across Gulf bar, 9.0 feet to
main channel, 8.0 feet in the lower 26-mile reach and 2.3 feet in
the upper reach of the tributary channel in the San Bernard River;
8.2 feet in the lower 2-mile reach, 3.3 feet in the lower 8-mile reach
and not navigable in the reach above mile 8 of the tributary chan-
nel in the Colorado River; 7 feet in the harbor basin and 8.8 feet
in the dredged portion of the tributary channel to Rockport, Tex.;
9.8 feet in the tributary channel to Palacios, Tex.; 2 feet in the
Bay across San Antonio Bay to Seadrift, but 0 feet along the pro-
posed location of channel to Victoria; 10 feet in the tributary chan-
nel to Aranasas Pass, Tex.; 0 feet in the branch channel into Bar-
room Bay; 11.0 feet in the channel to Port Mansfield; 9.2 feet in
the completed portion of the tributary channel to Harlingen, Tex.;
and 9.2 feet in the side channels at Port Isabel, Tex.
   The total cost of the existing project to June 30, 1954, was as
follows:

                                                                                     New work           Maintenance       Total

Regular funds I--                    ------                                          $24, 492,133       $12,126,195     $36,618,328
Public works funds                                -------------------------
                                 ______________________________                           466,477                           466, 477
      Total------------------------------------------                                 24,958,610        212,126,195     37.084,805

  1 Includes Guadalupe River, Tex.
   2 Does not include the following cost for operation and care: The total cost of operation and care of the
Mud Bayou Bridge, Brazos River Floodgates, and the Colorado River Floodgates and/or locks to June
30, 1954, was $4,591,377, including $33,173 of permanent indefinite appropriation funds.

                                                 Cost and financial summary

                                                             Fiscal year ending June 30                             Total to June
                                                                                                                   30, 1954, includ-
                                         1950             1951          1952           1953             1954        prior to 19501es
New work:
   Appropriated --------
                    ..                  $620, 000        $900, 000     $925, 386    $1, 143, 000     $649, 600         $25,843,146
   Cost---------------                   598, 364         734, 142      778, 167     1, 891, 733    2 729, 309          25, 665, 732
Maintenance:                                                                                                                       e
    Appropriated-........             1, 802, 409.      1, 478; 661   1, 356, 489    1;424;590      1,381, 462          18,892, 566
    Cost-----.....-----..             2, 796,
                                            670         1, 562, 860   1, 274, 321    1,766,
                                                                                          375       3   888, 880        18, 241, 908

   1Includes $706,709 for new work and $1,526,564 for maintenance for previous projects.
   2 Difference of $413 between F Y 54 costs shown above and that shown in "Operations and results during
fiscal year" is due to over estimation of prepayments for June 1954.
   8 Difference of $2,229 between F Y 54 costs shown above and that shown in " Operations and results during
fiscal year" is due to under-estimation of prepayments for June 1954.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954------------............. $175, 997
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project----....---.... -----....------------.. ... ------............
                                                                                 11, 056, 432
        RIVERS AND HARBORS-GALVESTON, TEX., DISTRICT             565
          3. GALVESTON HARBOR AND CHANNEL, TEX.
   Location. This is a consolidation of the authorized improve-
ments at Galveston, Tex., which includes the projects formerly
identified as Galveston Harbor, Tex.; Galveston Channel, Tex.;
and the Galveston seawall extension. The entrance to Galveston
Harbor is located on the Gulf of Mexico, on the northern portion
of the coast of Texas, 328 miles west of Southwest Pass on the
Mississippi River and 278 miles northeast from the mouth of the
Rio Grande. Galveston Channel extends from a point in Galveston
Harbor between Bolivar Peninsula and Fort Point across the former
inner bar to and along the wharf front of Galveston, and has a
length of about 5 miles and a width of 1,200 feet. (See U. S. Coast
and Geodetic Survey Chart No. 520.)
   Previous projects. The original project for the improvement
of Galveston Harbor, Tex., was authorized by the River and Har-
bor Acts of June 23, 1874, June 14, 1880, and August 5, 1886. For
further details see page 1854, Annual Report for 1915, and page
851, Annual Report for 1938.
   Existing project. The existing project provides for a channel
800 feet wide and 38 feet deep, from deep water in the Gulf of
Mexico to a point between the jetties 2 miles west of the seaward
end of the north jetty, thence 800 feet wide and 36 feet deep to
Bolivar Roads; a channel 36 feet deep at mean low tide and 1,200
feet wide from Bolivar Roads (outer end of the old inner bar near
Fort Point) to 43d Street, thence to 51st Street with a width of
1,200 feet and 32 feet deep, in the city of Galveston, and for its
extension to 57th Street, to a depth of 32 feet and a width of 1,000
feet; when the interests of navigation and commerce require it;
for two rubblestone jetties extending from Galveston Island (on
the south) and Bolivar Peninsula (on the north) into the Gulf of
Mexico (the south jetty being 35,900 feet long and the north jetty
25,907 feet long) ; the construction of 13 groins to protect the sea
wall along the Gulf shore from about 12th to 61st Streets, Gal-
veston Tex.; for an extension of the sea wall, which lies along the
Gulf front of Galveston, from its angle at 6th Street and Broad-
way to the south jetty, with protection at its junction with the
south jetty, and for an extension of the existing sea wall in a
southwesterly direction from its present terminus near 61st Street
for a distance of approximately 16,300 feet along the shore of the
Gulf of Mexico.
   Under ordinary conditions, the mean tidal range in Galveston
Harbor is 1.6 feet on the outer bar and 1.4 feet on the inner bar
with extreme ranges of 2.3 and 2.1 feet respectively. The mean
tidal range in Galveston Channel is about 1.3 feet and the extreme
range about 2 feet under ordinary conditions. The height of the
tides in both Galveston Harbor and Channel is dependent largely
on the wind, and during strong "northers" in the winter season
the water surface may be depressed 2 feet below mean low tide.
The estimated Federal cost of new work is $15,702,000 (July
1954), the estimated cost to local interests is $3,580,300; the total
 566             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

estimated cost is $19,282,000 (July 1954). The latest approved
estimate for annual cost of maintenance of the project is $606,750
 (July 1954), exclusive of $4,870,000 (July 1954) estimated cost
of rehabilitating jetties.
    The existing project was authorized by the following River and
Harbor Acts:
                                                                            i




     Acts                           Work authorized                                       Documents


Aug. 5, 1886    Construction of 2 rubblestone jetties at entrance to           H. Doc. 85, 49th Cong., 1st sess.,
                  Galveston Harbor.                                               and Annual Report, 1886, p.
                                                                                  1311.
June 13, 1902   A channel 1,200 feet wide and 30 feet deep from Bolivar        H. Doc. 264, 56th Cong., 2d sess.
                   Roads (outer end of the old inner bar near Fort
                   Point) to 51st St.
Mar. 3, 1905    Purchase or construction of a hydraulic pipeline dredge.       Specified in act.
Mar. 2, 1907    Extension of the jetties to present project length and         H. Doc. 340, 59th Cong., 2d sess.,
                   construction and operation of a dredge.                        and Rivers and Harbors Com-
                                                                                  mittee Doc. 11, 59th Cong., 2d
                                                                                  sess.
     Do....... Extension of Galveston Channel from 51st to 56th                 H. Doc. 768. 59th Cong., 2d sess.
                     Sts., with depth of 30 feet and width of 700 feet.
June 25, 1910     Conditional extension of the Galveston Channel H. Doc. 328, 61st Cong., 2d sess.
                    between 51st and 57th Sts., with a depth of 30 feet
                    and a width of 1,000 feet.
July 27, 1916    Extension of the sea wall at Galveston from angle at H. Doc. 1390, 62d Cong., 3d sess
                    6th St. and Broadway to a point abreast of the
                    nearest battery at Fort San Jacinto.
July 18, 1918    Deepening the harbor channel to 35 feet and widening H. Doc. 758, 65th Cong., 2d sess.
                    to 800 feet for an experimental period of 2 years.
Sept. 22, 1922   Further extension of the sea wall at Galveston to a H. Doc. 693, 66th Cong., 2d seas.
                   junction with the south jetty and protection of this
                   junction; and for repairing the seawall in front of
                    the Fort Crockett Reservation.
Jan. 21, 1927    Deepening Galveston Channel to 32 feet; and main- H. Doc. 307, 69th Cong., 1st seas.
                   tenance of Galveston harbor channels to dimen-
                   sions of 800 feet wide, 35 feet deep on outer bar and
                   34 feet deep on inner bar.
Aug. 30, 19351   Maintenance of State Highway Ferry Landing Chan- Rivers and Harbors Committee
                    nels to dimensions of 12 feet deep and 100 feet wide. Doc. 31, 72d Cong. 1st sess.
Aug. 30, 1935    Construction of 13 groins along Gulf Shore from 12th H. Doc. 400, 73d Cong., 2d sess.
                   to 61st Sts., in city of Galveston, at a limited cost
                   of $234,000. (10 groins were constructed under this
                   limitation.)
    Do.......    Deepening Galveston Channel to 34 feet from Bolivar Rivers and Harbors Committee
                   Roads to 43d St.                                       Doc. 61, 74th Cong., 1st seas.
    Do.......    Deepening Galveston Entrance Channel to 36 feet Rivers and Harbors Committee
                   from the Gulf of Mexico to a point 2 miles west of     Doc. 57, 74th Cong., 1st seas.
                   seaward end of north jetty.
Apr. 4, 1938 2   Completion of the project for the construction of 13 Public Law 463, 75th Cong.
                   groins.
June 30, 1948    Deepening Galveston Harbor to 38 feet from the H. Doc. 561, 80th Cong., 2d sess.'
                   Gulf to a point 2 miles west of seaward end of north
                   jetty and 36 feet thence to Bolivar Roads; revoking
                   authority for maintenance of ferry channels, and
                   deepening Galveston Channel to 36 feet from
                   Bolivar Roads to 43d St., provided that no dredging
                   be done by the United States within 50 feet of any
                   existing pierhead, pierhead line, wharf, or structure.
May 17, 1950     Constructing an extension of the existing Galveston H. Doc. 173, 81st Cong., 1st sess.'
                   seawall from its present terminus near 61st St., in a
                  southwesterly direction for a distance of approxi-
                  mately 16,300 feet along the shore of the Gulf of
                   Mexico.

I Previously authorized Sept. 6, 1933, by Public Works Administration.
2 Public Law No. 463, 75th Cong.
8 Contains latest published maps.



   Local cooperation. Fully complied with except for the furnish-
ing by local interests of assurances satisfactory to the Secretary
of the Army that they will hold and save the United States free
from claims for damages due to the construction and maintenance
of the Galveston Channel portion of the project as modified by the
River and Harbor Act of June 30, 1948, and furnishing land
         RIVERS AND HARBORS-GALVESTON,         TEX., DISTRICT      567
  easements required by the River and Harbor Act of May 17, 1950,
  in connection with the extension of the Galveston seawall subse-
  quent to the initial extension by local interests.
    Terminal facilities. There are no terminals on Galveston Har-
  bor, but it is the entrance channel leading to the extensive terminal
  facilities located on Galveston Channel, Texas City Channel, and
  Houston Ship Channel. The terminal facilities on Galveston Chan-
  nel are located almost entirely on the south side of the channel.
The principal wharves are owned by the city of Galveston and
  extend from 10th Street to 41st Street. Reconstruction of piers
and transit sheds is in progress and timber bulkheads and aprons
have been replaced with steel bulkheads and concrete aprons and
concrete slab decks at piers 10, 34, 35, 36, 37, 38 and 40 (Code Nos.
958, 917, 915, 912, 910, 909, and 907, Port Series No. 23, revised
  1948). Facilities are listed in the above Port Series and Port
Series No. 6, Part 1, Corps of Engineers, and are considered ade-
quate for existing commerce.
    Operations and results during fiscal year. New work: Work
was done by contract during the period July 1 to November 30,
1953, on the westerly extension of the Galveston seawall at a cost
of $182,117, all from contributed funds.
    Maintenance: The Government hopper dredge A. Mackenzie
removed 753,930 cubic yards of material from the inner and outer
bar channels during the periods from August 17 to October 16,
1953, and from May 16 to June 17, 1954, at a cost of $207,518. The
Government hopper dredge Lang fitt removed 563,900 cubic yards
of material from the inner and outer bar channels during the
period October 27 to December 8, 1953, at a cost $140,657. Condi-
tion surveys and miscellaneous inspections and reports were made
at a cost of $28,888. Minor repairs to the existing sea wall ex-
tension slope and pavement were made at a cost of $1,000.
    The total cost of all work for the fiscal year was $560,180, of
which $182,117 was for new work and $378,063 was for mainte-
nance.
    Condition at end of fiscal year. The existing project was about
54.9 percent complete. The jetties were completed in 1910. The
35-foot harbor channel was completed in 1922. The first seawall
extension, with fill and paving, was completed in 1926. The 36-
foot outer bar harbor channel and the 34-foot Galveston Channel
from Fort Point light to 43d Street was completed in the fiscal
year 1938. The groins along the gulf side of Galveston sea wall
were completed in 1939. The inner and outer harbor bar channels
were completed in the fiscal year 1950 to depths of 36 and 38 feet,
respectively. The westward extension of the Galveston seawall,
with fill and paving was approximately 33 percent complete at the
end of fiscal year 1954. The work remaining consists of dredg-
ing Galveston Channel to a depth of 36 feet from Bolivar Roads
to 43d Street and to a depth of 32 feet from 43d Street to 57th
Street over a 1,200-foot bottom width from 43d Street to 51st
Street and a 1,000-foot bottom width from 51st Street to 57th
Street, the work on the latter section being contingent on the de-
velopment of the waterfront facilities on the Chicago, Rock
Island & Gulf Railway and adjacent properties; and completing
 568                   REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

the 16,300-foot extension of the existing Galveston sea wall from
its present terminus approximately 5,400 feet southwest of 61st
Street in a southwesterly direction along the shore of the Gulf of
Mexico. The controlling depth below mean low tide in the outer
bar harbor channel, the inner bar harbor channel, and Galveston
Channel were 37 feet, 35 feet, and 31 feet, respectively. The total
cost of the existing project to June 30, 1954, was as follows:

                                                                                                     New work             Maintenance                Total


United States funds (regular):
    Channel----_                                                         ---------------                  $4, 713, 760
                                                                                                          $------------------- $12, 382, 376        $17, 096, 136
   Seawall ..............-----.......---------..........-----...-------------......                        2, 289, 214              159, 117          2, 448, 331
   Public  works        funds                  -----------------------........................   ---...       ........               13, 121              13, 121

     Total United States funds_,--__---- ......                  -                -___                     7, 002, 974        12, 554, 614           19, 557, 588
Contributed funds.....................................-----------------------------------                  3, 580, 275   ---------------              3, 580, 275

         Total cost of project-................... .............                                          10, 583, 249        12, 554, 614           23, 137, 863



                                                          Cost and financial summary

                                                            UNITED STATES FUNDS


                                                                         Fiscal year ending June 30                                            Total to June
                                                                                                                                               30, 1954, includ-
                                                                                                                                               ing fiscal years
                                                 1950                1951                1952                 1953             1954             prior to 1950 1

New work:
   Appropriated .-------..                     $175, 000 --------------------.....                                                                 $15, 424, 970
   Cost--------..........--------.....          175, 000 .-----------------------------........                                                     15, 424, 970
Maintenance:
   Appropriated.--------                        557, 136           $426, 050            $155, 400            $428, 077        $383,400               12, 650, 775
   Cost......----------------                   747, 768            271, 534             329, 109             438, 368        2376, 236              12, 638, 914


   1 Includes $8,421,996 for new work and $86,126 for maintenance for previous projects.
   2 Difference of $1,827 between F Y 54 costs shown above and that shown in" Operations and results during
fiscal year" is due to under-estimation of prepayments for June 1954.

Other new work data: Estimated additional amount needed to be appro-
   priated for completion of existing project...................                                                                                $8 ,697 ,000

                                                             CONTRIBUTED FUNDS


                                                                         Fiscal year ending June 30                                           Total to June
                                                                                                                                             30, 1954, includ-
                                                                                                                                             ing fiscal years
                                                1950                1951                 1952                 1953             1954            prior to 1950
New work:
   Appropriated........
                ----------------                   ..        $2,870, 000--                                                                          $, 580, 275
   Cost.---------------                                          26,674
                                                          .------------                $982, 779          $1,678, 431        $182, 117               3,580,275


                                           4. TEXAS CITY CHANNEL, TEX.
   Location. Texas City is on the mainland of Texas on the west
side of Galveston Bay, about 10 miles northwest of the city of
Galveston. (See U. S. Coast and Geodetic Survey Charts Nos. 520
and 1282.)
   Previous projects. Adopted by River and Harbor Act ap-
proved March 3, 1899, and enlarged by River and Harbor Act
approved June 25, 1910 (H. Doc. 328, 61st Cong., 2d sess.). For
further details see page 1856, Annual Report for 1915, and page
858, Annual Report for 1938.
                RIVERS AND HARBORS--GALVESTON,                             TEX., DISTRICT                    569
   Existing project. This provides for a channel 36 feet deep at
mean low tide and 400 feet wide on bottom from deep water in
Galveston Harbor to the harbor at Texas City, a distance of about
61/2 miles, with a pile dike on its north side 28,200 feet long covered
with clay and other material dredged from the channel with a
harbor 1,000 feet wide on bottom and 36 feet deep at mean low
tide extending approximately 4,250 feet to the southward of the
south property line of the Monsanto Chemical Co., and for the
construction of a rubble-mound dike a short distance south of the
existing pile dike and extending between stations -1+600 (the
shore) and 26+000, a distance of 27,600 feet. Under ordinary con-
ditions the mean tidal range is about 1.3 feet and the extreme
range is about 2 feet.      The height of tide is dependent largely
on the wind, and during strong "northers" in the winter season
the water surface may be depressed 2 feet below mean low tide.
   The estimate of cost for new work is $3,201,100 (July 1954) ex-
clusive of amounts expended on previous projects and exclusive of
$28,740 contributed by local interests. The latest approved esti-
mate of cost of annual maintenance of the channel and dike is
$164,000 (July 1954) exclusive of $632,500 (July 1954) estimated
cost of rehabilitating rubble mound dike.
   The existing project was authorized by the following River and
Harbor Acts:

    Acts                            Work authorized                                      Documents


Mar. 4, 1913     A channel 300 feet wide and 30 feet deep and construc-        H. Doc. 1390, 62d Cong., 3d sess.
                  tion of a pile dike 28,200 feet long north of channel.
July 3, 1930     For a harbor 800 feet wide and 30 feet deep at Texas          H. Doc. 107, 71st Cong., 1st sess.
                   City, and the construction of a rubble-mound dike.
Aug. 30,19351    Extension of rubble-mound dike to the shore line-.....        Rivers and Harbors Committee
                                                                                 Doc. 4, 73d Cong., 1st sess.
    Do....... Deepening the channel and harbor to 32 feet...........           Rivers and Harbors Committee
                                                                                 Doc. 46, 73d Cong., 2d sess.
   Do-.......   Deepening the channel and harbor to 34 feet------.......---.   Rivers and Harbors Committee
                                                                                 Doc. 62, 74th Cong., 1st sess.
Aug, 26, 1937   An extension to the harbor, 1,000 feet southward, 800          Rivers and Harbors Committee
                 feet wide and 34 feet deep, provided that no dredging          Doc. 47, 75th Cong., 1st sess.
                 be done by the United States within 75 feet of any
                 pierhead line or structure.
June 30, 1948   Deepen channel and harbor to 36 feet, widening                 H. Doc. 561, 80th Cong., 2d sess.
                 channel to 400 feet and harbor to 1,000 feet and                (Contains latest published
                 changing name of project to "Texas City Channel,               map.)
                 Tex.," provided no dredging be done by the United
                 States within 50 feet of any existing pierhead,
                 pierhead line, wharf, or structure.

1 Previously authorized Sept. 6, 1933, by Public Works Administration.


   Local cooperation. Under the provisions of the River and Har-
bor Acts of August 26, 1937, and June 30, 1948, local interests are
required to furnish free of cost to the United States necessary
rights-of-way and suitable spoil disposal areas for new work and
for subsequent maintenance as required and release the United
States from claims for damages attributable to the work of im-
provement and furnish assurance satisfactory to the Secretary of
the Army that they will construct a common-carrier oil terminal
substantially as proposed. None of these conditions have been
complied with. All prior requirements have been fully complied
with.
  Terminal facilities. Modern                              terminal            facilities,        privately
 570                  REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

owned, are located on the mainland at the inner end of this channel
  and are considered adequate for existing commerce.        (See Port
Series, No. 23, revised 1948, Corps of Engineers.) A sea train
terminal, privately owned, was completed in 1940.
    Operationsand results during fiscal year. Maintenance: Condi-
tion surveys and miscellaneous inspections and reports were made
at a cost of $6,463. Preliminary surveys, plans, and specifications
for dredging the Texas City Channel and Turning basin were made
at a cost of $1,464 and work was done under the contract during
the period from January 13 to February 25, 1954, removing
1,503,283 cubic yards of material from 31,753 linear feet of chan-
nel at a cost of $104,947. The total cost for all work during the
fiscal year was $112,874.
    Condition at end of fiscal year. The existing project was 72
percent complete. The work remaining consists of extending the
turning basin 1,000 feet southward and enlarging the project, in-
cluding the turning basin extension, to a depth of 36 feet over a
bottom width of 400 feet in the channel and 1,000 feet in the
turning basin. The channel and turning basin, except the author-
ized extension referred to above, were completed in 1937 to a depth
of 34 feet over bottom widths of 300 feet and 800 feet, respectively.
The pile dike was completed in 1915; the rubble mound dike in
1934. The controlling depth in the channel was 35 feet and in the
completed portion of the turning basin was 35 feet at mean low
tide. The total cost of the existing project to June 30, 1954, was
as follows:
                                                                                                New work         Maintenance             Total

Regular funds-....-------------------------------------$2, 151, 680        $4, 342, 154                                                 $6, 493, 834
Public works funds-.
                 __-----   ----     __136,                      296 ...............                                                         136, 296

     Total United States funds---.............. .......                                    .      2, 287, 976       4, 342, 154          6, 630, 130
Contributed funds-.....   ------------.--.----                                      -28,                  741   ---------------              28, 741

         Total all funds.........-----------------..........................----------------      2,316,717         4, 342,154           6, 658,817


                                                       Cost and financial summary

                                                                     Fiscal year ending June 30                                    Total to June
                                                                                                                                  30, 1954, Includ-
                                                                                                                                  ing fiscal years
                                              1950                1951               1952            1953           1954          prior to 1950 12
New work:
   Appropriated.....---------------------------------------------------------                                                           $2, 654, 799
    Cost-----.......-----......... ---------------------                       -------------- --------- ------------                     2,654, 799
Maintenance:
    Appropriated-------........             $166, 000              $5, 798         $129, 000      -$12, 130        $130, 200             4, 554, 984
    Cost----------------                      167, 115             $5, 800           109, 797          6, 729       112,851              4, 537, 214

    1Includes $366,823 for new work and $195,083 for maintenance for previous projects.
  2 In  addition, $28,741 for new work was expended from contributed funds.
   ' Difference of $23 between F Y 54 costs shown above and that shown in "Operations and results during
fiscal year" is due to under-estimation of prepayments for June 1954.
Other new work data: Estimated additional amount needed to be appro-
priated for completion of existing project........................................................ $913, 100

                                5. CHANNEL TO PORT BOLIVAR, TEX.
   Location. Port Bolivar is at the end of Bolivar Peninsula and
4 miles north of the city of Galveston.                                                          The channel connects the
                 RIVERS AND HARBORS--GALVESTON, TEX., DISTRICT                                          571
port with the channel in Galveston Harbor. (See U. S. Coast and
Geodetic Survey Chart No. 520.)
   Previous project. Adopted by the River and Harbor Act of
March 2, 1907. For further details see page 1856, Annual Report
for 1915, and page 860, Annual Report for 1938.
   Existing project. This provides for a channel 30 feet deep at
mean low tide and 200 feet wide on bottom, beginning at deep
water in Galveston Harbor and extending to a turning basin 1,600
feet long, with an average width of about 750 feet and 30 feet deep
at mean low tide in front of the wharves. Under ordinary con-
ditions the mean tidal range is about 1.3 feet and the extreme
range about 2 feet. The height of tides is dependent largely on the
wind, and during strong "northers" in the winter season the water
surface may be depressed 2 feet below mean low tide.
  The estimated cost of new work is $156,500 (July 1954), ex-
clusive of amount expended on previous projects. The latest ap-
proved estimate for annual cost of maintenance of the channel and
of a portion of the turning basin in front of the highway ferry
landing to a depth of 20 feet over a bottom width of 200 feet is
$14,500 (July 1954), these dimensions being sufficient to accom-
modate existing commerce.
  The existing project was authorized by the following River
and Harbor Acts:

       Acts                         Work authorized                                   Documents


June 25, 1910     Excavation of a channel 30 feet deep and 200 feet wide   H. Doc. 328, 61st Cong., 2d seas.
                    with turning basin 1,000 feet square.
Mar.    2,1919    Increase length of turning basin to 1,600 feet and       H. Doc. 1122, 65th Cong., 2d sess.
                    decrease width to about 750 feet.                        (Contains the latest published
                                                                             map.)

   Recommended modifications of project. Under date of June 24,
1926, the Chief of Engineers recommended that the project be
curtailed by providing for a channel depth of 20 feet, 200 feet
wide, with a turning basin of the same depth 500 feet square (H.
Doc. 467, 69th Cong., 1st sess.).
   Local cooperation. None required.
    Terminal facilities. The terminals are privately owned and
consist of two slips and two piers. The piers, 400 feet wide by
1,200 feet long and 210 feet wide by 1,200 feet long, are badly
deteriorated and not in use. The slips are used as anchorages by
shallow draft vessels.    A highway ferry landing owned by the
State of Texas is located at the south end of the turning basin.
The facilities are considered adequate for existing commerce.
   Operations and results during fiscal year. Maintenance: Con-
dition surveys and miscellaneous inspections and reports were made
at a cost of $101. Preliminary surveys, plans, and specifications
for dredging a portion of the turning basin in front of the high-
way ferry landing were made at a cost of $550 and work was done
under the contract during the period January 8 to 10, 1954, re-
moving 69,387 cubic yards of material from 700 linear feet of chan-
nel at a cost of $5,037. The total cost was $5,688.
   Condition at end of fiscal year. The existing project was 54
percent complete. The channel, 200 feet wide, and turning basin,
572              REPORT OF CHIEF OF ENGINEERS; U. S. ARMY, 1954

1,000 feet square, were completed in 1912. The work remaining
consists of enlarging the turning basin to project dimensions.
Project dimensions have not been maintained in the completed
part since lesser dimensions are adequate for existing commerce.
   The controlling depths at mean low tide over usable widths were
20 feet in the channel, 7 feet in the turning basin at entrance to
slip No. 3, and 13 feet in the channel to the State Highway ferry
landing.
   The total cost of the existing project to June 30, 1954, was $695,-
907, of which $85,214 was for new work and $610,693 was for
maintenance.
                                        Cost and financial summary

                                                Fiscal year ending June 30                   Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                                 1950         1951        1952         1953         1954      prior to 19501
New work:
   Appropriated _---        --------- ------------ ------------ ------------_$133,925
                                                                               ------------
   Cost.    .                 -----------
                     ..----------          ----------------------- ------------------------          133, 925
Maintenance:
   Appropriated_-- .---           $- 750
                                  $20,          $8, 665    $4, 500     $470       $7, 000            658, 388
   Cost-----------------           20, 541       5, 426     7,990       371        5,688             656, 794

  1   Includes $48,711 for new work and $46,101 for maintenance for previous projects.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project-------------....................... ........ .....   $71,300

                          6. HOUSTON SHIP CHANNEL, TEX.
   Location. The channel connects Galveston Harbor, at a point
opposite Port Bolivar, with the city of Houston, Tex., extending
50 miles in a northwesterly direction across Galveston Bay through
the San Jacinto River and Buffalo Bayou to a turning basin at the
head of Long Reach with a light draft channel 7 miles long from
the turning basin to Main Street, Houston. (See U. S. Coast and
Geodetic Survey Charts Nos. 1282 and 532.)
   Previous projects. Authorized by River and Harbor Act of
June 10, 1872, modified in 1877, and by River and Harbor Acts of
March 3, 1879; March 3, 1899; February 20, 1900; March 3, 1905;
and March 4, 1913. For further details see page 1856 of the An-
nual Report for 1915 and page 862 of the Annual Report for 1938.
   Existing project. This provides for a channel 36 feet deep at
mean low tide from deep water in Galveston Bay to and including
the Houston turning basin, with a width of 400 feet from Bolivar
Roads to 5,000 feet above Baytown, thence 350 feet to the mouth
of Boggy Bayou, thence 300 feet to the Houston turning basin
 (about 1,000 feet wide) ; for turning points at the mouth of Hunt-
ing Bayou and at the lower end of Brady Island; for such off-chan-
nel silting basins on any part of the waterway as the Chief of
Engineers may consider advisable; and for suitable widening of
the bends at Lynchburg, Norsworthy, Manchester, and Harris-
burg. The project also provides for suitable widening of the chan-
nel in front of the navigation district's wharf at Manchester; for
certain cutoffs and easing of sharp bends; for construction of a
dike 26,000 feet long to protect the channel in upper Galveston
Bay; for a light draft extension of the channel 10 feet deep at mean
                     RIVERS AND HARBORS--GALVESTON,                        TEX., DISTRICT                  573
low tide and 60 feet wide, without easing the bends, through
Buffalo Bayou from the turning basin to the mouth of White Oak
Bayou in Houston, Tex.; and for a branch channel 10 feet deep
at mean low tide and 60 feet wide in the old channel of Buffalo
Bayou behind Brady Island. The mean tidal range under ordinary
condtions is 0.6 foot to 1.3 feet in the lower part of Galveston Bay;
0.6 foot to 1.3 feet in the upper bay; and 0.5 foot to 1 foot in the
San Jacinto River and Buffalo Bayou. The extreme ranges under
ordinary conditions are about 2 feet, 1.2 feet, and 1 foot, respec-
tively. Freshets sometimes cause rises of over 12 feet in Buffalo
Bayou. The height of the tides, however, is dependent largely on
the wind, and during strong "northers" in the winter season the
water surface may be depressed 2 feet below mean low tide.
   The estimate of cost for new work is $17,406,000 (July 1954),
exclusive of amounts expended on previous projects, and exclusive
of $1,365,000 contributed by local interests. The latest approved
estimate for annual cost of maintenance is $901,700 (July 1954).
   The existing project was authorized by the following River and
Harbor Acts:

        Acts                            Work authorized                                  Documents


Mar.       5, 1905    Easing or cutting off sharp bends and construction of    Rivers and Harbors Committee
                       a pile dike.                                              Doc. 35, 61st Cong., 2d sess.
Mar. 2, 1919          A channel 30 feet deep, widening bend at Manchester      H. Doc. 1632, 65th Cong., 3d sess.
                       and enlarging the turning basin.
Mar. 3, 1925          A light-draft extension of the channel to the mouth of   H. Doe. 93, 67th Cong., 1st sess.
                        White Oak Bayou.
July       3, 1930    Widening the channel through Morgan Point and to         H. Doc. 13, 71st Cong., 1st seas.
                       a point 4,000 feet above Baytown and widening
                       certain bends.
Aug. 30,19351         Deepening to 32 feet in the main channel and turning     Rivers and Harbors Committee
                       basin, and for a 400-foot width through Galveston         Doc. 28, 72d Cong., 1st sess.
                        Bay.
       Do......       Deepening to 34 feet in main channel and widening        Rivers and Harbors Committee
                       from Morgan Point to turning basin.                       Doc. 58, 74th Cong., 1st sess.
Mar. 2, 1945          Branch channel2 10 feet deep and 60 feet wide behind     H. Doc. 226, 76th Cong., 1st sess.
                        Brady Island.
    Do -
       ....           Widening the channel from Morgan Point to lower          H. Doc. 256, 76th Cong., 1st sess.
                       end of Fidelity Island with turning points at the
                       mouth of Hunting Bayou and lower end of Brady
                       Island.3
    Do .......        Widening the channel from lower end of Fidelity          H. Doc. 737, 79th Cong., 2d sess
                       Island to Houston turning
                                               3   basin and dredging off-
                       channel silting basins.
June 30, 1948         Deepening to 36 feet from Bolivar Roads to and in-       H. Doc. 561, 80th Cong., 2d sess.
                       cluding main turning basin at Houston, Tex.,              (Contains   latest  published
                       including turning points at Hunting Bayou and             map.)
                       Brady Island.3

  1 Previously authorized Sept. 6, 1933, by Public Works Administration.
  2 No dredging within 15 feet of any wharf or structure.
  8 No dredging within 50 feet of any wharf or structure.


   Local cooperation. Fully complied with except for part of the
work authorized by the River and Harbor Acts of March 2, 1945,
and June 30, 1948, which is subject to the provisions that local in-
terests shall furnish, free of cost to the United States, necessary
rights-of-way for the widening and deepening of the channel and
suitable areas for the disposal of dredged material during initial
construction and for future maintenance as and when needed, and
release the United States from all claims for damages due to the
construction and maintenance of the project. Release from dam-
age liability has been accepted by the Secretary of the Army.
574               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Local cooperation remaining consists of acquiring land easements
from Green's Bayou to the turning basin at Houston, Tex.
   Terminal facilities. The city of Houston and the Harris County
Houston Ship Channel Navigation District have constructed mod-
ern terminals which supplement privately-owned wharves. The
existing facilities are considered adequate for existing commerce.
 (See Port Series No. 24 (revised 1948), Corps of Engineers.)
Dock No. 9, 500 feet long, and dock No. 16, 598 feet long, have
been built in the turning basin since 1948 by the navigation dis-
trict for public use, and construction of dock No. 8, 624 feet long
is completed and in public use since June 1954.
   Operations and results during fiscal year. Maintenance: Con-
dition surveys and miscellaneous inspections and reports were made
at a cost of $39,793. Preliminary surveys, plans, and specifica-
tions for dredging the channel from Hunting Bayou to Sims Bayou
were made at a cost of $3,205. A total of 3,907,231 cubic yards
of material was removed from 43,856 linear feet of channel at a
cost of $424,549, as follows:

     Government                                                        Cubic        Linear feet
      plant or                    Location              Period         yards        of channel    Cost
       contract                                                       removed        dredged

        ..
Contract----------
                ..       Baytown to Lynchburg.      July 1 to Sept.   1, 359, 539       18,000    $180, 666
                                                      2, 1953.
Contract ...----------   Morgan Point to Baytown.   Dec. 21, 1953     2, 547,692        25, 856    243,883
                                                      to Apr. 8,
                                                      1954.



   The total cost for the fiscal year was $467,547.
   Condition at end of fiscal year. The existing project was 78.9
percent complete. The 34-foot project was completed in 1941. The
36-foot project has been completed from Bolivar Roads to Green's
Bayou.
   Work remaining consists of dredging light-draft extension of
channel from the turning basin to the mouth of White Oak Bayou;
constructing a dike 26,000 feet long to protect the completed chan-
nel in upper Galveston Bay; dredging a light-draft channel be-
hind Brady Island; and widening and deepening from Green's
Bayou to the turning basin, including turning points at Hunting
Bayou and Brady Island.
   The controlling depths at mean low tide were as follows: Bol-
ivar Roads to Morgan Point, 35 feet; Morgan Point to Baytown,
36 feet; Baytown to Boggy Bayou, 35 feet; Boggy Bayou to Man-
chester, 32 feet; Manchester to the turning basin, 34 feet; in the
turning basin, 36 feet; light-draft channel from turning basin
to mouth of White Oak Bayou, 6 feet; and channel behind Brady
Island 5.0 feet.
   The total cost of the existing project to June 30, 1954, was as
follows:
                    RIVERS AND HARBORS-GALVESTON,                                                    TEX., DISTRICT                             575

                                                                                         New work                Maintenance               Total

Regular funds_ ..           .____ _______________$______                                $10,     819, 405         $16, 828, 773          $27, 648, 178
P u b l i c wo rk s fu n ds      .     _.         . .  ...
                                                        .......                         -.    2 , 6 12, 9 3 2    .        .                 2, 6 12, 932

          Total United States funds ....                                                     13, 432, 337             16, 828, 773         30, 261, 110
Contributed funds-              -     .       -..   -....   .     .       .........          1,365, 000 ...............                    1, 365, 000
          Total all funds _._..            ____________________........                      14, 797, 337             16, 828, 773         31, 626, 110



                                                     Cost and financial summary

                                                                  Fiscal year ending June 30                                        Total to June
                                                                                                                                   30, 1954,includ-
                                                                                                                                   ing fiscal years
                                             1950                1951         1952                1953                1954           prior to 19501 s

New work:
    Appropriated-........              $1, 250,000            $800, 000     $909, 000         -$27, 000            -$8,      198         $17, 537, 494
    Cost-----------   ---               1, 207, 093          1, 083, 008     578, 167            596, 680       ------------
                                                                                                                     _17,                     537, 494
Maintenance:
       Appropriated --------.....            796, 000            888,812      993, 000            202, 900            585, 270            18, 301, 129
       Cost.............----------------     411,723             589,162   1, 023, 671            715,192         3   467, 787            18, 042,155

   1 Includes $4,105,157 for new work and $1,213,142 for maintenance for previous projects.
   2 In addition, $2,574,179 for new work and $200,000 for maintenance was expended from contributed funds.
   SDifference of $240 between F Y 54 costs shown above and that shown in'"Operations and results during
fiscal year" is due to over-estimation of prepayments for June 1954.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project ..__...$............................ $3,963,400

                                               7. DOUBLE BAYOU, TEX.
    Location. This bayou enters upper Galveston Bay on the east
side about 30 miles north of Galveston and about 81/4 miles south
of Anahuac. (See U. S. Coast and Geodetic Survey Chart No.
1282.)
    Existing project. The existing project provides for a channel
6 feet deep at mean low tide and 100 feet wide through the bar at
the mouth of Double Bayou. Under ordinary conditions the mean
tidal range is about 0.5 foot and the extreme range is about 1.2
feet. The height of tides is dependent largely on the winds, and,
during strong "northers" in the winter season, the water surface
may be depressed 11/2 feet below mean low tide.
   The latest approved estimate for annual cost of maintenance is
$12,000 (July 1954).
   The existing project was authorized by the River and Harbor
Act approved March 3, 1899 (H. Doc. 387, 55th Cong., 2d sess.).
The latest published map is contained in the project document.
   Local cooperation. None required.
   Terminal facilities. The terminal facilities on this waterway
are confined to small wharves for local use and an oil dock. They
are considered adequate for the present commerce.
   Operations and results during fiscal year. Maintenance: Con-
dition surveys and miscellaneous inspections and reports were
made at a cost of $1,164. Preliminary surveys, plans and specifi-
cations for dredging the channel were made at a cost of $321.
   The total cost for the fiscal year was $1,485.
   Condition at end of fiscal year. The existing project was com-
pleted in 1941. The controlling depth was 4 feet at mean low tide.

          Sig 19--575.606
576            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

The total cost of the existing project to June 30, 1954, was $217,-
816, of which $10,310 was for new work and $207,506 was for
maintenance.
                                          Cost and financial summary

                                                      Fiscal year ending June 30                   Total to June
                                                                                                  30, 1954, includ-
                                                                                                  ing fiscal years
                                  1950               1951         1952       1953        1954       priorto 1950

New work:
   Appropriated--.------------------------ -----------------------------------                             $10,310
                ..- ....--------------------------------------------- ------------
   Cost---- -------                                                                                         10,10
Maintenance:
   Appropriated-__ ---    -$2, 000    $18. 925     -$500        $920      $22, 900                        229, 169
    Cost ..---..-----------     ......------------    18, 507        455           710   11,481           207, 502

  1Difference of $4 between fiscal year 1954 costs shown above and that shown in "Operations and results
during fiscal year" is due to under-estimation of prepayments for June 1954.


                               8. ANAHUAC                       CHANNEL, TEX.
   Location. The town of Anahuac is on the northeast side of
upper Galveston or Trinity Bay, opposite the mouth of the Trinity
River, 38 miles north of Galveston and 25 miles northeast of Sea-
brook. (See U. S. Coast and Geodetic Survey Chart No. 1282.)
   Existing project. There is no definite project for this channel.
The River and Harbor Act approved March 3, 1905, contained an
item for "Improving West Galveston Bay Channel, Double Bayou,
and mouths of adjacent streams, including Trinity River, Anahuac
Channel, and Cedar Bayou," but at the time of the appropriation
no recommendation of definite channel dimensions had been made
to Congress. A channel 6 feet deep at mean low tide and 80 feet
wide was dredged in 1905 from Galveston Bay to the wharves at
Anahuac, a distance of 16,000 feet. Under ordinary conditions the
mean tidal range is about 0.75 foot and the extreme range is about
1.2 feet. The height of tide is dependent largely on the wind, and
during strong "northers" in the winter season the water surface
may be depressed 11/2 feet below mean low tide.
   The latest approved estimate for annual cost of maintenance is
$33,800 (July 1954). The latest published map is contained in
House Document No. 440, 56th Congress, 1st session.
   Local cooperation. None required.
   Terminal facilities. The terminal facilities are at Anahuac and
consist of several small privately owned wharves and slips for local
use. They are considered adequate for existing commerce.
   Operations and results during fiscal year. Maintenance: Con-
dition surveys and miscellaneous inspections and reports were
made at a cost of $246. A total of 177,107 cubic yards of material
was removed by contract from 11,280 linear feet of channel dur-
ing the period from December 17, 1953, to January 29, 1954, at a
cost of $34,194.
   The total cost for the fiscal year was $34,440.
   Condition at end of fiscal year. The existing project was com-
pleted in 1911. The controlling depth was 6 feet at mean low tide.
The total cost of the existing project to June 30, 1954, was
$595,195, of which $5,975 was for new work and $589,220 was for
maintenance.
               RIVERS AND HARBORS-GALVESTON, TEX., DISTRICT                                                             577
                                           Cost and fnancial summary

                                                      Fiscal year ending June 30                              Total to June
                                                                                                              30, 1954, includ-
                                                                                                              ing fiscal years
                                   1950              1951             1952              1953       1954        priorto 1950

New work:
    Appropriated ---      -----------------------------------------------------------                                   $5, 975
    Cost_---------           ------------ ------------------------------------------------                               5,975
Maintenance:
    Appropriated ------           $12, 500          $15, 926          $27, 300        -$2, 500     $34, 140           589, 229
    Cost--- --- -----------         44, 550           19, 270            1,291           27, 431   134, 439           589, 219

   ]Difference  of $1 between fiscal year 1954 costs shown above and that shown in "Operations and results
during fiscal year" is due to under-estimation of prepayments for June 1954.


                 9. TRINITY RIVER AND                                   TRIBUTARIES,                TEX.

    Location. This river rises in north-central Texas and flows
southeasterly about 760 miles, discharging into Galveston Bay, 37
miles northeasterly from Galveston (U. S. Geological Survey base
map, Texas, scale 1:500,000).
    Previous projects. The project outlined in House Document
No. 409, 56th Congress, 1st session, was adopted in part by the
River and Harbor Acts of June 13, 1902, March 3, 1905, March 2,
1907, June 25, 1910, July 25, 1912, March 4, 1913, and July 27,
1916, each of which acts authorized the construction of certain
named locks and dams. The portion of the project relating to
locks and dams construction was abandoned by the River and Har-
bor Act of September 22, 1922. For further details, see page 1113
of Annual Report for 1921, and page 986 of Annual Report for
1932.
    Existing project. With abandonment of the lock and dam con-
struction, the improvement: of the Trinity River by a channel 6
feet deep and of navigable width from the mouth to Liberty (river
mile 41.4) was left as the existing project, being continued as
provided for in the River and Harbor Act of July 25, 1912. The
existing project was modified by the River and Harbor Act of
March 2, 1945, which approved a comprehensive plan of develop-
ment of the Trinity River and tributaries, Tex., in accordance
with the recommendations set forth in House Document No. 403,
77th Congress, 1st session, subject to such future modifications as
in the discretion of the Chief of Engineers and the Secretary of
the Army may be advisable. That comprehensive plan of devel-
opment provided for a navigable channel from a point in Galveston
Bay at the Houston Ship Channel to a terminus at Fort Worth,
Tex. Such navigable channel was to be not less than 9 feet in
depth, and to have a minimum bottom width of 200 feet in Galves-
ton Bay and 150 feet in the river section on tangents, with shunt-
ing places and suitable widening on curves, and with a turning
basin at Liberty. The navigation locks would have clear inside
dimensions of 75 feet by 400 feet. The 1945 act, however, author-
ized for construction at this time only that portion of the channel
as far upstream as Liberty, Tex.
   The River and Harbor Act of July 24, 1946, further modified
the comprehensive plan for the Trinity River Basin development
so as to locate the section of the navigation channel below Ana-
578      REPORT OF CHIEF OF ENGINEERS U. S:. ARMY, 1954

huac nearer the eastern shore of Trinity Bay, in accordance with
the recommendations of the Chief of Engineers in House Docu-
ment No. 634, 79th Congress, 2d session. This modification pro-
vides for a navigation channel 9 feet deep and 150 feet wide from
the Houston Ship Channel near Red Fish Reef along the easterly
shore of Galveston Bay with a protective embankment to the
mouth of the Trinity River near Anahuac.
   The estimated Federal cost of this portion of the comprehensive
plan below Liberty is $7,750,000 (1949), exclusive of amounts ex-
pended on previous projects. The latest approved estimate for
annual cost of maintenance and operation is $120,000 (July 1954).
The latest published maps are contained in House Document No.
634, 79th Congress.
   The estimated first cost to the United States of the approved
comprehensive plan for canalization to Fort Worth is $96 million
 (1939 prices), with $1,760,000 annually for maintenance and
operation.
   Under ordinary conditions the mean tidal range in the bay is
from about 0.6 foot to about 1.2 feet. The height of tide is depend-
ent largely on the wind, and during strong northerly winds in the
winter season the water surface may be depressed 1.5 feet below
mean low tide.
   Local cooperation. The work recommended in House Document
403, 77th Congress, is authorized subject to the conditions that
local interests furnish necessary rights-of-way, suitable areas for
disposal or dredging material, and make necessary changes in
utilities crossing the natural river channel below Liberty; and give
assurances satisfactory to the Secretary of the Army that they will
provide adequate terminal and transfer facilities on the waterway,
and hold and save the United States free from claims for damages
that may result from construction and operation of the improve-
ments.
  Local interests have not complied with conditions of local co-
operation for the portion of the channel from Anahuac to Liberty,
but have fully complied with the conditions contained in House
Document 634, 79th Congress, 2d session, for the completed por-
tion of the channel below Anahuac.
   Terminal facilities. There are five wharves on this river be-
tween the mouth and a point 38 miles upstream at Liberty, Tex.
Four range from 10 to 20 feet in length; the fifth, at Liberty, is
150 feet in length. All are privately owned, and usage is free at
all except one. One has a hand derrick; the other four have no
freight handling facilities. They have no physical connection with
any railroad. They are adequate for the existing commerce, and
there is ample room for future enlargement.
   The Texas Gulf Sulphur Co. has constructed a channel 12.5 feet
deep, 100 feet wide, and 4,500 feet long from mile 11.1 on the
Trinity River to a slip 12.5 feet deep, 380 feet wide, and 1,320 feet
long, with terminal and transfer facilities for the unloading of
sulphur from the Moss Bluff mines.
   Operations and results during fiscal year. Maintenance: Con-
dition surveys and miscellaneous inspections and reports were
made at a cost of $1,111. The removal of snags and logs from the
                 RIVERS AND HARBORS-GALVESTON,                                     TEX., DISTRICT                    579
river section of the channel to Liberty between Anahuac and
Wallisville with hired labor and Government plant was performed
at a cost of $2,565. Preliminary surveys, plans and specifications
were made at a cost of $422. A total of 25,637 cubic yards of ma-
terial was removed under contract from mile 9.9 to mile 10.4 of
the river section of the Channel to Liberty during the period
February 1 to 9, 1954, at a cost of $7,948.
   The total cost for the fiscal year was $12,046.
   Condition at end of fiscal year. The navigation channel below
Liberty, Tex., is 13 percent complete. The original project was
completed in 1925. The channel from its junction with the Houston
Ship Channel to a point 1 mile below Anahuac, Tex., has been
dredged to a depth of 9 feet below mean low tide over a bottom
width of 150 feet. The controlling depth between the Houston
Ship Channel and a point 1 mile below Anahauc, Tex., was 2.5 feet
at mean low tide. The controlling depth between the mouth of the
Trinity River and mile 28.5 was 7 feet, and 3 feet thence to Lib-
erty. Authorized construction remaining under the comprehen-
sive plan consists of completing that portion of the navigation
channel from 1 mile below Anahuac to Liberty, Tex. The total
cost of the existing project to June 30, 1954, was $1,271,234, of
which $1,042,660 was for new work and $228,574 was for mainte-
nance.
                                               Cost and financial summary

                                                          Fiscal year ending June 30                       Total to June
                                                                                                          30, 1954, includ-
                                                                                                          Ing fiscal years
                                                                                                                       1
                                        1950             1951        1952        1953           1954      prior to 1950 2

New work:
   Appropriated                        $167, 000       -$39, 570    -$6, 525                                    $2, 933, 066
   Cost..    - _           _........    768, 507         106, 000      6, 913     $1, 195                        2, 933, 066
Maintenance:

    Appropriated               _ ........        ,__      11, 984     17, 460     42, 555       $5, 900            774, 456
    Cost..............-.          .....        ... I      11, 204      4, 502     47, 927   i   12, 048            772, 238

  1Includes $1,956,406 for new work and $543,662 for maintenance for previous projects.
  SIn addition, $66,000 for new work was expended from contributed funds.
  $ Difference of $2 between fiscal year 1954 costs shown above and that shown in "Operations and results
during fiscal year" is due to over-estimation of prepayments for June 1954.
Other new work data: Estimated additional amount needed to be appro-
priated for completion of existing project                          --.........
                                             --------------------......................
                                                                            $6,707,339

                                            10. CEDAR BAYOU,                    TEX.
  Location. This bayou is about 30 miles long. It flows to the
south and empties into the northwest corner of upper Galveston
Bay, about 112 miles below the mouth of San Jacinto River and
about 281/ miles north of Galveston, Tex. (See U. S. Coast and
Geodetic Survey Chart No. 1282.)
  Previous projects. Adopted by the River and Harbor Acts of
September 19, 1890, and July 13, 1892. For further details see
page 869, Annual Report for 1938.
  Existing project. This provides for a channel 10 feet deep at
mean low tide and 100 feet wide from the Houston Ship Channel
to a point on the bayou, 11 miles above the mouth. The project
also includes the jetties at the mouth of the bayou provided for
under the previous project. Under ordinary conditions the mean
580               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

tidal range is about 0.6 foot and the extreme range 1.2 feet. The
height of tides is dependent largely on the wind, and during strong
"northers" in the winter season the water surface may be de-
pressed 2 feet below mean low tide.
   The estimate of cost for new work is $41,700 (July 1954), ex-
clusive of amounts expended on previous projects, and $25,000 to
be contributed by local interests. The latest approved estimate for
annual cost of maintenance is $33,000 (July 1954).
   The existing project was adopted by the River and Harbor Act
of July 3, 1930 (S. Doc. 107, 71st Cong., 2d sess.). The latest pub-
lished map is in this document.
   Local cooperation. The River and Harbor Act, approved July
3, 1930, provides that local interests shall contribute 50 percent of
the estimated first cost of the improvement, but not to exceed $25,-
000, and shall furnish, without cost to the United States, all neces-
sary easements, rights-of-way, and dumping grounds.
   These conditions have not been completely met, but local inter-
ests have complied with all the necessary requirements to complete
the channel to the first bend in Cedar Bayou above the mouth.
   Terminal facilities. The terminal facilities consist of a few
small wharves, privately owned, for local use located at various
places along Cedar Bayou, an oil loading wharf owned by the
Atlantic Pipe Line Co. located one-half mile above the mouth of the
bayou, and an oil loading wharf owned by the Sinclair-Prairie Oil
Co. located 11 miles above the mouth of the bayou. The present
facilities are considered adequate for existing commerce.
   Operations and results during fiscal year. Maintenance: Con-
dition surveys and miscellaneous inspections and reports were
made at a cost of $561.
   Condition at end of fiscal year. The existing project was about
37.7 percent complete. The channel was completed in 1931 to
project dimensions from the Houston Ship Channel to the first
bend in Cedar Bayou above the mouth. Two brush and stone jet-
ties have been constructed at the mouth of Cedar Bayou. Work
remaining consists of dredging the channel to project dimensions
from the first bend above the mouth to a point 11 miles above the
mouth. The controlling depths at mean low tide were 9 feet from
Houston Ship Channel to the first bend in Cedar Bayou above the
mouth and 6 feet thence to a point in the bayou 11 miles above the
mouth.
   The total cost of the existing project to June 30, 1954, was as
follows:

                                                                             New work        Maintenance     Total

Regular funds......----------------------------------------                     $12, 575         $378, 655    $391, 230
Contributed funds...-------------------------------------                        12, 576 -       -12,               576
      Total..................-------------------------------------------..       25,151           378,655      403,806
                RIVERS AND HARBORS--GALVESTON,                                          TEX., DISTRICT                    581
                                           Cost and financial summary

                                                      Fiscal year ending June 30                                 Total to June
                                                                                                                30, 1954, includ-
                                                                                                                ing fiscal years
                                    1950            1951            1952            1953           1954         prior to 1950   1
New work:
   Appropriated-- .---           --                     ------------.........- ............
                                        ............ ............---                                                     $51, 663
                                                                                          ----
   Cost-----------------------....-----------------------------------------......... ............                         51, 663
Maintenance:
    Appropriated-                -- $10, 000       $50, 673          $1, 200        $66, 535        $1 200               450,025
      Cost---------------            33,053          51, 618             750            66,045            558            448,437

  'Includes $39,087 for new work and $69,784 for maintenance for previous projects.
  2 In addition, $12,576 for new work was expended from contributed funds.
  1 Difference of $3 between fiscal year 1954 costs shown above and that shown in "Operations and results
during fiscal year" is due to under-estimation of prepayments for June 1954.
Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project....----- ...--------.......--..........-............-----....-----. $12,570

                  11. CLEAR CREEK AND CLEAR LAKE, TEX.
  Location. Clear Creek has its source about 13 miles south of
Houston, Tex., and flows southeast for a distance of about 25
miles, emptying into the west side of upper Galveston Bay at a
point 24 miles northwest of Galveston, Tex. (See U. S. Coast and
Geodetic Survey Chart No. 1282.)
  Existing project. This provides for a channel 7 feet deep at
mean low tide and 75 feet wide from deep water in Galveston Bay
to a new entrance to Clear Creek, and a channel 7 feet deep and 60
feet wide in Clear Creek and Clear Lake to the county highway
bridge at League City. Under ordinary conditions the mean tidal
range is about 0.8 foot and the extreme range is 1.4 feet. The
height of tides is dependent largely on the wind and during strong
"northers" in the winter season the water surface may be de-
pressed 2 feet below mean low tide.
   The latest approved estimate for annual cost of maintenance is
$7,200 (July 1954).
   The existing project was authorized by the following River and
Harbor Acts:

     Acts                               Work authorized                                              Documents

June 13, 1902    A channel 4 feet deep and 50 feet wide--------------................      H. Doc. 449, 56th Cong., 1st sess.
Aug. 30, 1935    Enlargement of the channel to depth of 6 feet and                         H. Doc. 264, 73d Cong., 2d sess.
                  width of 60 feet.
Mar. 2, 1945     Realinement, enlargement, and extension of the chan-                      H. Doec. 319, 77th Cong., 1st sess.
                   nel to the highway bridge near League City.                               (Contains      latest    published
                                                                                             map.)


   Local cooperation. Fully complied with.
   Terminal facilities. The terminal facilities consist of small pri-
vately owned wharves for local use located at the town of Sea-
brook, at the mouth of the creek, and at various points along the
length of the waterway. They are considered adequate for exist-
ing commerce.
   Operations and results during fiscal year. Maintenance: Con-
dition surveys and miscellaneous inspections and reports were
made at a cost of $1,504.
 582              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Condition at end of fiscal year. The existing project was com-
pleted June 14, 1950. The controlling depth at mean low tide was
5 feet to the upper entrance to Clear Creek, thence natural dimen-
sions of the creek upstream to the end of the project which are
considered adequate for existing traffic.
   The total cost of the existing project to June 30, 1954, was
$170,736, of which $66,934 was for new work and $103,802 was for
maintenance.
                                          Cost and financial summary

                                                 Fiscal year ending June 30                        Total to June
                                                                                                  30, 1954, includ-
                                                                                                  ing  fiscal years
                                   1950        1951            1952         1953       1954        prior to 1950

New work:
    Appropriated        .--        $54, 700   -- $9, 057   -          --              - -                  $66, 934
    Cost   ...--------------     -45643-                                                                    66, 934
    Appropriated            __        _          -255      -1,              $---270     $1, 800            104, 282
    Cost__.... .___..____ I            313, .. ... .... ..            .    i 1, 086     11, 343            103, 641


  1Difference of $161     between fiscal year 1954 costs shown above and that shown in "Operations and results
during fiscal year" is due to under-estimation of prepayments for June 1954.


                                  12. DICKINSON BAYOU, TEX.
   Location. This bayou enters Galveston Bay on the west side
about 20 miles northwest of Galveston.         (See U. S. Coast and
Geodetic Survey Chart No. 1282.)
   Existing project. This provides for a channel 6 feet deep at
mean low tide and 60 feet wide along the present route from the
natural 6-foot depth in Galveston Bay through Dickinson Bay and
Dickinson Bayou to the Galveston, Houston & Henderson Railroad
bridge at Dickinson, Tex. Under ordinary conditions the mean
tidal range is about 1 foot and the extreme range about 1.4 feet.
The height of tides is dependent largely on the wind, and during
strong "northers" in the winter season the water surface may be
depressed 21/2 feet below mean low tide.
   The latest approved estimate for annual cost of maintenance is
$1,300 (July 1954).
   Authority for the original dimensions (4 by 50 feet) of this
channel is explained in the Annual Report for 1931, page 1093.
The River and Harbor Act approved June 20, 1938, authorized the
present project dimensions (H. Doc. 568, 75th Cong., 3d sess.).
The latest published map is in this document.
   Local cooperation. Fully complied with.
   Terminal facilities. The terminal facilities consist of small pri-
vately owned wharves for local use. They are considered adequate
for the existing commerce.
   Operations and results during fiscal year. Condition surveys
and miscellaneous inspections and reports were made at a cost of
$197.
   Condition at end of fiscal year. The existing project was com-
pleted in 1940. The controlling depth was 6 feet at mean low tide.
The total cost of the existing project to June 30, 1954, was $91,401,
of which $33,942 was for new work and $57,459 was for mainte-
nance.
             RIVERS AND HARBORS--GALVESTON,                                     TEX., DISTRICT                  583

                                      Cost and financial summary

                                                    Fiscal year ending June 30                         Total to June
                                                                                                      30, 1954, includ-
                                                                                                      ing fiscal years
                               1950                1951        1952            1953          1954       prior to 1950

New work:
   Appropriated_ _ -                                                                                           $33, 942
   Cost ....                          ------------                    ------- ------------                      33,942
Maintenance:
   Appropriated........                             -$361    __       -           $670                          57,553
   Cost ...............      ..   ..------------       132     -                   379        1$198             57, 460

  1 Difference of $1 between fiscal year 1954 costs shown above and that shown in "Operations and results
during fiscal year" is due to over-estimation of prepayments for June 1954.


                            13. CHOCOLATE BAYOU, TEX.
   Location. The source of the bayou is about 25 miles southwest
of Houston and the mouth is in Chocolate Bay, an arm of West
Galveston Bay, about 12 miles north of San Luis Pass and 28 miles
west of Galveston. It is tidal throughout its length, and the lowest
stages occur during the winter season. The authorized section
extends from the Gulf Intracoastal Waterway through Chocolate
Bay to the mouth of the bayou, a distance of about 5.6 miles.
   Existing project. The existing project, adopted by the River
and Harbor Act approved March 2, 1907 (H. Doc. 445, 56th Cong.,
1st sess.) ; modified by the River and Harbor Act approved March
2, 1945 (H. Doc. 337, 76th Cong., 1st sess.) ; and further modified
by the River and Harbor Act approved May 17, 1950 (H. Doc. 768,
80th Cong., 2d sess.), provides for a channel 4 feet deep at mean
low tide and 100 feet wide through Chocolate Bay to the extent
necessary to afford a connection between Chocolate Bayou and the
Gulf Intracoastal Waterway. Under ordinary conditions the mean
tidal range is about 1 foot and the extreme range about 11/2 feet.
The height of tide is largely dependent on the force and direction
of the wind and during strong "northers" in the winter season the
water surface may be depressed 2 feet below mean low tide.
   The estimate of cost of new work is $54,000 (July 1954). The
latest approved estimate for annual cost of maintenance is $11,400
 (July 1954). The latest published map is contained in House
Document No. 768, 80th Congress, 2d session.
   Local cooperation. None required.
   Terminal facilities. The terminal facilities consist of small pri-
vately owned wharves located at various points along the bayou.
They are considered adequate for existing commerce.
   Operations and results during fiscal year. Maintenance: Con-
dition surveys and miscellaneous inspections and reports were
made at a cost of $277.
   Condition at end of fiscal year. The existing project was 12
percent complete. The controlling depth in the channel from its
confluence with the Gulf Intracoastal Waterway through Choco-
late Bay to the mouth of the Bayou was 4 feet at mean low tide
over a bottom width of 60 feet.
   The total cost for the existing project to June 30, 1954, was
$71,950, of which $6,512 was for new work and $65,438 was for
maintenance.
584                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                    Cost and financial summary

                                                                   Fiscal year ending June 30                                            Total to June
                                                                                                                                        30, 1954, includ-
                                                                                                                                         ing fiscal years
                                            1950                  1951             1952                     1953           1954           priorto 1950

New work:
    Appropriated,--------------------                        --                  ------------
                                                                               ---------------------                                      -        $6, 512
    Cost-----------------------------------------------                                                -----------------------                      6,512
Maintenance:
   Appropriated .......
                  -   -                     $33, 000             -$1, 663----...--------..                    $920                                 65, 505
    Cost....        .........-----------------..31, 337   ..--           ..---------------------.........     576                $277             65, 438


Other new work data: Estimated additional amount needed to be appropri-
    ated for completion of existing project------.......---...-.....                                 $47,500
                                                                     ......... ....... .........--------------

                                         14. FREEPORT HARBOR, TEX.
   Location. This harbor is formed by the improvement of the
Brazos River, Tex., from the mouth to Freeport, about 6 miles
above. (See U. S. Coast and Geodetic Survey Chart No. 525.)
    The mouth of the Brazos River is about 47 miles southwest of
Galveston Harbor entrance and about 137 miles northeast of
Aransas Pass (Port Aransas).
    Previous projects. Authorized by River and Harbor Act of
June 14,1880. For further details see page 1860 of Annual Report
for 1915, and page 872 of Annual Report for 1938.
    Existing project. This provides for a project depth of 38 feet
at mean low tide in the outer bar channel from that depth in the
Gulf of Mexico to a point within the jetties; thence 36 feet in the
authorized channels and basins to and including the upper: turning
basin about one-half mile below the Stauffer Chemical Co. plant,
with two turning basins, one 700 by 700 feet at Brazosport and
one 600 by 600 feet at the upper end of the channel, the channel
to have a width of 300 feet seaward of the jettied entrance, 200
feet from the jettied entrance to the Brazosport turning basin,
widened at the bend, and averaging 375 feet, thence to the upper
turning basin; the widths in the approaches to the turning basins
to converge within a distance of 800 feet from the width of the
turning basin to the width of the channel; and for the extension
of the channel with a depth of 30 feet and a width of 200 feet to
and including a turning basin, 500 by 500 feet, near the, Stauffer
Chemical Co. plant at Freeport, when required in the interests of
commerce and navigation. The work is to be accomplished as may
be found desirable, by dredging, by jetties at the mouth of the
harbor, and by a diversion dam in the Brazos River, a diversion
channel, and necessary auxiliary works in general accordance with
plan No. 6, as proposed by the district engineer, together with a
lock in the diversion dam, approximately 200 feet long, 55 feet
wide and 121/2 feet deep over the miter sills. The River and Har-
bor Act of July 3, 1930, modified the act of March 3, 1925, so as
to provide that when local interests shall have furnished assur-
ances satisfactory to the Secretary of the Army that they will
maintain the diversion channel, the United States shall assume the
cost of maintenance of the navigable channel, estimated at $75,000
annually, including care and operation of the lock, if provided
 (Rivers and Harbors Committee Doc. 18, 70th Cong., 1st sess.).
                  RIVERS AND HARBORS-GALVESTON, TEX., DISTRICT                                            585
   Under ordinary conditions the mean tidal range is about 1.5
feet and the extreme range about 21/2 feet. Freshets in the river,
except under extreme conditions, do not cause a greater variation
in the water surface than the tidal action.
   The estimated cost of new work is $1,692,700 (July 1954), ex-
clusive of $758,300 contributed funds and $1,299,700 remaining to
be contributed by local interests upon request. The latest ap-
proved estimate of cost of annual maintenance is $286,300 (July
1954).
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                                Work authorized                             Documents


Mar. 3, 1899        Dredging and such other work as may be deemed            Specified in act.
                     most effective in the judgment of the Secretary of
                     War in improving and developing the harbor; for
                     taking over the jetties :and other privately built
                     works at the mouth of the river.
Mar. 2, 1907        Examination authorized. The work was subsequently        H. Dec. 1087, 60th Cong., 2d sess.
                     confined to maintenance of the jetties.
Feb. 27, 1911       Repairs to jetties ariddreding...... ......-- ........   Specified in act.
Mar. 4, 1913.       Construction of a seagoing hopper dredge, 1 the cost         Do.
                     to be charged to this' improvement and 1 to Aran-
                     sas Pass.
Aug. 8, 1917        Purchase. of one 15-inch pipeline dredge and equip-      H.Doc. 1469, 63d Cong., 3d seas.
                     ment, its operation for an experimental- period of 3
                     years,.the operation of the seagoing dredge 3 time
                     for 3 years, and repairs to the jetties.
Mar. 3, 1925        Diversion dam, diversion channel, and necessary          Rivers and Harbors Committee
                      auxiliary works.                                         Doc. 10, 68th Cong., 2d sess.
July    3, 1930     Maintenance of the diversion channel at the expense      Rivers and Harbors Committee
                      of local interest.                                       Doc. 18, 70th Cong., 1st sess.
Aug. 30,19351       Dredging the channels and turning basins to greater      Rivers and Harbors Committee
                      depths. (Project completed to within 3 mile of           Doc. 15, 72d Cong., 1st sess.
                      the upper limit of the channel with Public Works
                      Administration funds and contributed funds.)
   Do....... Maintenance of the present project dimensions of the            Rivers and Harbors Committee
                      channels and turning basins at Federal expense.          Docs. 15, 72d Cong., 1st sess.,
                                                                               and 29,2 73d Cong., 2d sess.
May 17, 1950        Deepening outer bar channel to 38 feet, mean low         H. Doc. 195,2 81st Cong., 1st sess.
                      tide, from the Gulf to a point within the jetties;
                      thence 36 feet in the authorized channels to and
                      including the upper turning basin.

1Included        in Public Works Administration program, Sept. 6, 1933.
2 Contains latest published maps.

  Local cooperation. All required local cooperation has been fully
complied with, except the contribution toward the cost of extension
of the channel to Freeport, which has not been requested (River
and Harbor Act of Mar. 3, 1925). Construction of a lock in the
diversion dam (River and Harbor Act of Mar. 3, 1925) ; and local
cooperation requirements for work authorized by the River and
Harbor Act of May 17, 1950 (H. Doc. 195, 81st Cong., 1st sess.).
  Terminal facilities. The terminal facilities consist of small pri-
vately owned wharves. Other facilities privately owned are one
sulfur loading dock, three oil docks, an acid dock, and two shell
unloading docks. The present facilities are considered adequate
for existing commerce.
  The Brazos River Harbor Navigation District plans to open in
October 1954 a 200- by 2,500-foot entrance channel to a 600- by
650-foot turning basin with a 650-foot steel and concrete dock and
a 150- by 396-foot transit shed over rail facilities permitting all-
weather work without damage to cargo.
586                   REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Operations and results during fiscal year. Maintenance: Con-
dition surveys and miscellaneous inspections and reports were
made at a cost of $12,891. Preliminary surveys, plans and speci-
fications for the construction of hopper dredge range towers were
made at a cost of $317. A total of 816,611 cubic yards of material
was removed from a total of 24,300 linear feet of channel at a
cost of $185,576, as follows:
      Government                                                                                                  Cubic             Linear feet
       plant or                                     Location                                 Period               yards             of channel         Cost
         contract                                                                                               removed               dredged
Government              hop-        Sea bar and jetty channel.                          Julyl4toAug.                  428, 638           12, 200       $68, 175
    per dredge                                                                             16, 1953.
    .4. Mackenzie.
      Do -----------.............---....   do     _           ...----------------      Oct.17 to Nov.              234, 000                3, 400       55, 937
                                                                                         16, 1953.
      Do.........-------------......-do ..........-------------------                  Mar. 9 to Apr.                 153, 973             8, 700       61, 464
                                                                                         5, 1954.


   The total cost of all work for the fiscal year was $198,784.
   Condition at end of fiscal year. The existing project was 52.7
percent complete. The existing project has been improved to a
depth of 32 feet to and including the upper turning basin. The
work remaining consists of deepening the channel to and including
the turning basin near Stauffer Chemical Co. plant and construct-
ing a lock in the diversion dam in the old Brazos River. The con-
trolling depth at mean low tide in the various channels and turning
basins (middle half of channel), were as follows:
   Channel from deep water in the Gulf of Mexico to seaward end
of jetty, 32 feet; channel from seaward end of jetty to Brazosport
turning basin, 29 feet; Brazosport turning basin, 32 feet; channel
from Brazosport turning basin to upper turning basin, 33 feet;
upper turning basin, 32 feet; channel from upper turning basin to
Stauffer Chemical Co. plant, 19 feet; and turning basin at Stauffer
Chemical Co. plant, 20 feet. The total cost of the existing project
to June 30, 1954, was as follows:
                                                                                                  New work               Maintenance                Total


Regular funds....-----------...................-----........-------------------.........               $1, 101, 062         $4, 136, 421            $5, 237, 483
Public works funds-----------................-------------------------........................             116, 575 -116,
                                                                                                                    ..............                           575
         Total United States Funds....------------------------                                          1, 217, 637              4, 136, 421         5,354, 058
Contributed funds......------------------------------------                                               758,303                 ------               758, 303
         Total all funds...............--------------------------------- 1, 975, 940                                         4, 136, 421            6, 112, 361
                   RIVERS AND HARBORS-GALVESTON, TEX., DISTRICT                                                 587
                                          Cost and financial summary

                                               Fiscal year ending June 30                             Total to June
                                                                                                     30, 1954, includ-
                                                                                                     ing fiscal years
                                   1950         1951          1952        1953            1954       prior to 1950   1 2



New work:
       Appropriated....----------------------------------------------------------                         $1, 364, 735
   Cost----....--          ------------------------------------------------------------                     1, 364, 735
Maintenance:
      Appropriated-----........   $265, 000    $131, 603    $143, 711    $320, 792       $191, 600          4, 141, 998
       Cost----------------        252, 504     144, 166      139, 516    312, 245      '198, 760           4, 136, 397

  1   Includes $147,098 for new work for previous projects.
   2 In addition, $758,303 for new work was expended from contributed funds.
  * Difference of $24 between fiscal year 1954 costs shown above and that shown in "Operations and results
during fiscal year" is due to under-estimation of prepayments for June 1954.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project . -...............
                                                          ............. $474,700

      15. CHANNEL FROM PASS CAVALLO TO PORT LAVACA, TEX.
   Location. The bar at Pass Cavallo is 125 miles southwest of
Galveston entrance and 54 miles north of Aransas Pass. Port
Lavaca lies 26 miles to the northwest of the pass, across Matagorda
and Lavaca Bay. (See U. S. Coast and Geodetic Chart No. 1117.)
   Existing project. This provides for a depth of 9 feet and a
width of 100 feet from Lynns Bayou at Port Lavaca, Tex., to deep
water in Matagorda Bay near Port O'Connor, Tex., a distance of
about 11 miles; for a channel 6 feet deep and 100 feet wide from
Port Lavaca via Lavaca Bay, Lavaca, and Navidad Rivers to Red
Bluff about mile 3 on the Navidad River, a total distance of 20
miles; and for a harbor of refuge 9 feet deep near Port Lavaca
with an approach channel 9 feet deep and 100 feet wide. Under
ordinary conditions the mean tidal range is about 1 foot and the
extreme range about 2 feet. The height of tide is dependent
largely on the wind, and during strong "northers" in the winter
season the water surface may be depressed 2 feet below mean
low tide.
   The estimate of cost for new work is $457,000 (July 1954). The
latest approved estimate of cost for annual maintenance is $49,-
700 (July 1954).
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                            Work authorized                                     Documents


June 25, 1910       Channel to Port Lavaca, Tex., 7 feet deep and 80 feet        H. Doc. 1082, 60th Cong., 2d sess.
                     bottom width.
Aug. 30, 1935       Extension of 7-foot channel to the shore line of Lavaca      Rivers and Harbors Committee
                     Bay at the mouth of Lynns Bayou.                              Doc. 28, 74th Cong., 1st sess.
Aug. 26, 1937       Deepen and widen channel to present project dimen-           Rivers and Harbors Committee
                     sions.                                                        Doc. 37, 75th Cong., 1st sess.1
Mar.    2, 1945     Extension of the channel 6 feet deep and 100 feet wide       H. Doc. 314, 76th Cong., 1st sess.'
                     from Port Lavaca by way of Lavaca Bay, Lavaca
                     and Navidad Rivers to Red Bluff, a distance of 20
                     miles.
      Do-.......    To provide a harbor of refuge 9 feet deep near Port          H. Doc. 731, 79th Cong., 2d sess.
                     Lavaca and an approach channel 100 feet wide and
                     equal depth.

  1 Contain latest published maps.
 588.              REPORT OF CHIEF :OF ENGINEERS,: U. S. ARMY, 1954

    Local cooperation. Under the River and Harbor Act of March
2, 1945, local interests are required to furnish, free of cost to the
United States, all necessary land, easements, and rights-of-way
and suitable spoil disposal areas for the initial construction and
subsequent maintenance when and as required; hold and save the
United States free from damages that may result from the con-
struction and maintenance of the project; and provide necessary
mooring facilities to which all vessels shall have free and equal
access during storm periods, none of which has been complied
with. Requirements under prior acts have been complied with.
    Terminal facilities. The terminal facilities consist of several
privately owned piers and three privately owned slips at Port
Lavaca, and a municipally owned wharf, turning basin, one oil
dock, and refrigerated seafood processing and packing plant at
the mouth of Lynns Bayou. The municipally owned facilities are
open to the general public and are adequate for existing commerce.
In addition, there is a privately owned channel, turning basin with
private wharves, oil dock, and loading facilities owned by Alumi-
num Co. of America at Point Comfort, Tex.
    Operations and results during fiscal year. Maintenance: Con-
dition surveys and miscellaneous inspections and reports were
made at a cost of $3,379. Preliminary surveys, plans and specifi-
cations for dredging between Lynns Bayou and Magnolia Beach
were made at a cost of $2,218 and 381,303 cubic yards of material
were removed from 35,500 linear feet of channel during the period
from January 27 to February 22, 1954 at a cost of $30,267.
    The total cost for the fiscal year was $35,864.
    Condition at end of fiscal year. The existing project was 27
percent complete. The channel from the 9-foot contour in Mata-
gorda Bay to the mouth of Lynns Bayou was completed in 1939.
The work remaining consists of dredging the channel through
Lavaca Bay and the Lavaca and Navidad Rivers to Red Bluff on
the Navidad River and dredging the harbor of refuge and approach
channel at Port Lavaca. The controlling depth at mean low water
in the completed channel was 9.1 feet. The total cost of the exist-
ing project to June 30, 1954, was $525,100, of which $125,494 was
for new work and $399,606 was for maintenance.
                                             Cost and financial summary

                                                        Fiscal year ending June 30                        Total to June
                                                                                                          30, 1954, includ-

                                      1950            1951        1952          1953           1954        prior to 1950

New work:
   Appropriated ----              - ------------     --------------------------------------------                 $125, 494
   Cost---.........-- ----------------------------            ----------- ----------- ------------                 125, 494
Maintenance:
     Appropriated ....- -            -- $1, 500      -$1, 089     $52, 300    -$9, 460        $35, 700             399, 679
     Cost---------- ------              60, 375          1, 438    39, 438        3, 227      1 35, 874            399, 616


  1 Difference of $10 between fiscal year 1954 costs shown above and that shown in "Operations and results
during fiscal year" is due to over-estimation of prepayments for June 1954.
Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project..----------............................------------................. $331, 500
                    RIVERS AND HARBORS--GALVESTON,                                                  TEX., DISTRICT                   589
          16. PORT ARANSAS-CORPUS                                              CHRISTI WATERWAY,                       TEX.:
   Location. This is a consolidation of the old improvements of
Port Aransas, Tex., and the channel from Aransas Pass to Corpus
Christi, Tex. Aransas Pass is on the southern portion of the coast
of Texas, 180 miles southwest of Galveston and 132 miles north
of the mouth of the Rio Grande. Aransas Pass connects Corpus
Christi Bay and Aransas Bay with the Gulf of Mexico. The water-
way extends from deep water in the Gulf through the Aransas
Pass jettied entrance, thence westerly 203/%miles to and including
a turning basin at Corpus Christi, thence westerly 13/4 miles
through the Industrial Canal to and including the turning basin
a Avery Point, thence westerly 41/4 miles to and including a turn-
ing basin near Tule Lake. (See U. S. Coast and Geodetic Survey
Charts Nos. 523, 1285 and 1286.)
   Previous projects. The original project for improvement of
Aransas Pass (Port Aransas) was authorized by the River and
Harbor Act of March 3, 1879. The improvement was taken over
by the Aransas Pass Harbor Co. on June 30, 1890, under authority
of the act of May 12, 1890. This company relinquished its rights
to the United States on March 27, 1899. The channel from Aransas
Pass to Corpus Christi was first improved under the River and
Harbor Acts of March 2, 1907, and June 25, 1910.
   For further details, see page 1861 of Annual Report for 1915
and page 877 of Annual Report for 1938.
  Existing project. The existing project dimensions provided for
in the various channels and basins comprising this waterway are
shown in the following tabulation:
                                                                                  Adopted project dimensions


Section of the Port Aransas-Corpus                                                                                        Depth in
      Christi Waterway, Tex.                                                                                             feet below
                                                                              Bottom width in feet                       mean low
                                                                                                                         Gulf level

Aransas Pass outer bar-----------..............        700,,,--------------.......................-----------------                  38
Aransas Pass jetty channel--------..........           600 from inner end to opposite station 90, north jetty,                 (1)
                                                         thence increasing to 700 at outer end of jetty.
Inner basin at Harbor Island-.....              -650       by southerly 1,000 long----------------------------                        36
                                                       650 by northerly 2,000 long_---.....       --... -....     -......             30
Channel to town of Port Aransas.._                     100....................................................                        12
Channel from Port Aransas to Cor-                      400.............------------------------......-----------------------          36
pus Christi turning basin.
Corpus Christi turning basin-......                    1,000 by 5,500 long (includes approach to turning basin).                          36
Industrial Canal...............----------------....    200 ......------------------------..............-                                  36
Turning basin at Avery Point-----..1,000 by 1,200 long-----------------------------------                                             36
Channel to vicinity of Tule Lake-_.  200------------------------------------------36
Turning basin near Tule Lake-.....                     900 by 1,000 long .................................-...                        36

      feet from inner end to opposite station 90, north Jetty, increasing to 38 feet at outer end of jetty.
    S36

   The project also provides for two rubblestone jetties at Aransas
Pass entrance, extending into the gulf from St. Joseph and Mus-
tang Islands, the project lengths of which are 11,190 and 8.650 feet,
respectively. The project further provides for a stone dike on St.
Joseph Island about 19,100 feet long connecting with the north
jetty and extending up this island to prevent a channel being cut
around the jetty.
   Under ordinary conditions, the mean tidal range at Aransas Pass
is about 1.1 feet and the extreme range about 2 feet, and at Corpus
590               :REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Christi the mean range about 1 foot and the extreme about 1 i
feet. The heights of tides are dependent largely on the strength
and directions of winds, and during strong "northers" in the winter
season the water surface may be depressed as much as 3 feet below
mean low Gulf level.
   The estimated cost for new work, exclusive of amounts expended
on previous projects, and exclusive of $216,400 contributed by
local interests, is $30,999,000 (July 1954). The latest approved
estimated for annual cost of maintenance is $773,600 (July 1954)
 (exclusive of $5,195,000 (July 1954) estimated cost of rehabilitat-
ing jetties).
   The existing project was adopted by the following River and
Harbor Acts:
       Acts                        Work authorized                                    Documents
                  i_




Mar.    3, 1899Acquisition of the old curved portion of the north           Specified in act.
                jetty previously constructed by private parties.
June 13, 1902  Completion of north jetty in accordance with the plans           Do.
Mar. 3, 1905    of its builders.
Mar. 2, 1907   Connection of old curved jetty to St. Joseph Island,         Rivers and Harbors Committee
                and construction of south jetty.                              Doec. 5, 59th Cong., 2d sess.
Feb. 27, 1911  Dredging roadstead in Harbor Island Basin to depth           H. Doc. 1094, 61st Cong., 3d ses.
                of 20 feet and construction of 10,000 linear feet of the
                stone dike on St. Joseph Island.
Mar. 4, 1913   Deepening of channel between jetties and the Harbor          H. Doe. 1125, 62d Cong., 3d sess.
                Island Basin to depth of 25 feet, extension of jetties
                seaward, extension of dike on St. Joseph Island
                9,100 feet, and dredging the approach channel 12
                feet deep to town of Port Aransas.
Sept. 22, 1922 Dredging channel from Aransas Pass to Corpus                 H. Doc. 321, 67th Cong., 2d sess.
                 Christi, 25 feet deep, 200 feet bottom width.
July 3, 1930 Deepening entrance channel from Gulf of Mexico to              H. Doc. 214, 70th Cong., 1st sess.
                Harbor Island and provision of an inner basin at
                Harbor Island of reduced area but greater depth.
    Do         Aransas Pass to Corpus Christi Channel with depth            Rivers and Harbors Committee
                of 30 feet.                                                   Doc. 9, 71st Cong., 1st sess.
Aug. 30, 19351 Enlarging all channels from the Gulf to the western          Rivers and Harbors Committee
                end of basin dredged by Humble Oil & Refining                 Doc. 35, 72d Cong., 1st sess.
                 Co. at its docks on Harbor Island, with Public               and 40, 73d Cong., 2d sess.
                Works Administration funds.
    Do -- --- Maintenance of channel and maneuvering basin be-              H. Doc. 130, 72d Cong., 1st sess.
                tween breakwater and western shoreline of Corpus
                 Christi Bay.
    Do ------ Maintenance to 30 feet depth, except on strips lying          Rivers and Harbors Committee
                50 feet channelward of any established pierhead lines         Doc. 13, 74th Cong., 1st sess.
                or within 50 feet of the foot of any wharf or structure
                of the approach channel, turning basin at Corpus
                 Christi, Industrial Canal and turning basin at
                 Avery Point.
    Do ...     Maintenance and deepening to 32 feet of the channel          Rivers and Harbors Committee
                from deep water at Port Aransas to and including              Doec. 63, 74th Cong., 1st sess.
                 the turning basin at Corpus Christi.
June 20, 1938 Extend the main turning basin at Corpus Christi               H. Doc. 574, 75th Cong., 3d sess.
                 westward 2,500 feet at its present width and depth,
                 deepen the existing Industrial Canal and turning
                 basin to 32 feet and for the extension of this canal at
                 a depth of 32 feet and general width of 150 feet,
                 westward along Nueces Bay shore to a turning
                 basin 32 feet deep, 900 feet wide, and 1,000 feet long
                 near Tule Lake.
Mar. 2, 1945 To provide a depth of 34 feet in all project channels          H. Doc. 544, 78th Cong., 2d seas.
                 and basins from Port Aransas to and including the
                 Tule Lake turning basin, for a width of 250 feet
                 from Port Aransas to the breakwater at Corpus
                 Christi, for a width of 200 feet in the Industrial Canal
                 and in the channel between the Avery Point and
                 Tule Lake turning basins, and for widening the
                 Avery Point turning basin to 1,000 feet.
June 30, 1948  Deepen   entrance channel to 38 feet from Gulf to outer      H. Doc. 560, 80th Cong., 2d sess.
                 end of jetty; 38 feet decreasing to 36 feet thence to        (Contains the latest published
                 station 90, north jetty; and 36 feet in all other deep       map.)
                 water channels and basins except 2,000-foot un-
                 dredged part of inner basin at Harbor Island, and
                 for a width of 400 feet in the channel from Port Aran-
                 sas to the maneuvering basin at Corpus Christi.

   Included in Public Works Administration program Sept. 6, 1933, and Feb. 16, 1935.
        RIVERS AND HARBORS--GALVESTON,       TEX., DISTRICT     591
    Recommended modifications of project. Under date of June 8,
1950, the Chief of Engineers recommended modification of the ex-
isting project to provide for an anchorage basin 12 feet deep at
mean low water, from 300 to 400 feet wide, and 900 feet long in
Turtle Cove adjacent to the existing channel and turning basin at
Port Aransas, Tex., with such modifications thereof as in the dis-
cretion of the Chief of Engineers may be advisable at an estimated
cost to the United States of $30,000 for new work and $1,000 an-
nually for maintenance in addition to that now required (H. Doc.
654, 81st Cong., 1st. sess.).
    Under date of August 26, 1952, the Chief of Engineers recom-
mended that the project be modified by providing for a branch
channel 32 feet deep and 150 feet wide, extending northerly from
the main channel in the vicinity of Port Ingleside, along the north
shore of Corpus Christi Bay to the Reynolds Metals Co. plant and
for a turning basin 32 feet deep and 800 feet square near the plant,
in the general vicinity of La Quinta, Tex., with such modifications
thereof as in the discretion of the Chief of Engineers may be ad-
visable at an estimated cost to the United States of $795,000 for
new work, and $4,000 annually for maintenance in addition to
that now required. (H. Doc. 89, 83d Cong., 1st sess.)
    Local cooperation. Fully complied with except for the pro-
visions of the River and Harbor Acts of June 20, 1938, March 2,
1945, and June 30, 1948, local interests being required to deepen
and maintain at their own expense the channel through and for
a distance of 50 feet on each side of the bridge at the entrance of
the Corpus Christi turning basin, furnish, free of cost to the
United States, all necessary lands, easements, rights-of-way, and
spoil disposal areas for the initial work and for subsequent main-
tenance as and when required, and furnish assurances satisfactory
to the Secretary of the Army that they will hold and save the
United States free from damages due to construction and mainte-
nance of the improvement: And provided further, That construc-
tion of the extension from Avery Point to Tule Lake shall not be
undertaken until and unless local interests furnish assurances sat-
isfactory to the Secretary of the Army that bona fide arrange-
ments have been made with various industries to guarantee addi-
tional tonnage sufficient to warrant the construction and mainte-
nance of that canal to any point up to and including the proposed
turning basin near Tule Lake, none of which has been complied
with, except that assurances and evidence of arrangements with
industries to guarantee sufficient tonnage to warrant the improve-
ment have been furnished and accepted for the extension from
Avery Point to Tule Lake.
    Terminal facilities. Terminal facilities located on Harbor Is-
land at the head of Aransas Pass, Ingleside, Corpus Christi, La
Quinta, and Avery Point are considered adequate for existing
commerce. (See Port Series, No. 25, revised in 1948, Corps of
Engineers.)
  The following changes were not incorporated in Port Series No:
25: Humble Oil and Refining Co., Port Ingleside Dock, Port Series
No. 25 Map Reference 26, has been removed. Humble Pipe Line
Co. barge dock at Harbor Island, Port Series No. 25 Map Refer-
592         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

ence No. 27, has been rebuilt. The reconstructed dock provides a
berthing space of 450 feet with, dolphins. Humble Pipe Line Co.
oil docks at Harbor Island, Port Series No. 25 Map Reference Nos.
28 and 29 have been rebuilt. The reconstructed docks provide a
berthing space of 1,600 feet, 800 feet at each dock, with dolphins.
The Atlantic Pipe Line Co. oil dock at Harbor Island, Port Series
No. 25 Map Reference No. 30 has been rebuilt. The reconstructed
dock provides a berthing space of 845 feet, with dolphins. A pier
with conveyors for handling bauxite and with berthing spaces for
deep draft vessels of 700 feet on the upper side and 625 feet on
the lower side has been constructed on the north shore of Corpus
Christi Bay at La Quinta at the westerly end of a 32-foot by 125-
foot private channel, 6 miles long, which joins the Port Aransas-
Corpus Christi Waterway at a point opposite McGloins Bluff. An
oil dock with 700 feet of berthing space, with dolphins, has been
constructed on the south side of the industrial canal at Corpus
Christi approximately midway between map reference Nos. 15
and 16, Port Series No. 25. A 2 million bushel grain elevator is
located on the north side of the industrial canal at Corpus Christi
about opposite the oil dock described above. The dock alongside
the elevator provides 500 feet of berthing space, with dolphins.
A barge channel has been constructed westward from Avery Point
turning basin for a distance of 3.26 miles.    A dock for handling
bulk sulfuric acid with a berthing space of 200 feet, with dolphins,
is located on the southerly side of the channel approximately 2
miles westerly from Avery Point. An oil dock with a berthing
space of 180 feet, with dolphins, is located on the southerly side
of the channel approximately 11/2 miles westerly from Avery Point.
    Operations and results during fiscal year. Maintenance: Con-
dition surveys and miscellaneous inspections and reports were
made at a cost of $26,882. Preliminary surveys, plans and specifi-
cations for repairs to the South Jetty were made at a cost of
$3,919. Preliminary surveys, plans and specifications were made
for driving reference line piling in the bay at a cost of $1,601.
Costs for work under the contract during the period April 22 to
May 4, 1954, amounted to $4,528. A total of 1,063,339 cubic yards
of material was removed from 26,225 linear feet of channel and
basins at a cost of $170,235, as follows:

    Government                                                    Cubic      Linear feet
     plant or                Location              Period          yards     of channel    Cost
     contract                                                    removed      dredged
Hopper dredge A.   Sea bar and jetty channel.   Nov. 17 to.       180, 972        7,125    $63,255
  Mackenzie.                                    Dec. 11, 1953.
   Do-----------   Sea bar and jetty channel.   May 4 to 15,       92, 199        2,600     27,921
                                                  1954.
Contract   __......
             _     Bay  channel, maneuvering    Dec. 28, 1953     790,168        16, 500    79,059
                    basin and main turning       to Jan. 27,
                    basin.                        1954.



   The total cost for the fiscal year was $207,165.
            RIVERS AND HARBORS-GALVESTON, TEX., DISTRICT                                                              593
   Condition at end of fiscal year. The existing project was 19.8
percent complete. The two jetties have been partially completed,
the north jetty being 9,240 feet long and the south jetty 7,385 feet
long. A stone dike 20,991 feet long connecting with the north
jetty was completed on St. Joseph Island in 1916. The inner basin
at Harbor Island has been dredged to 30 feet below mean low tide
over an area 650 feet wide and about 1,000 feet long. The channel
from the inner basin to town of "PortAransas was completed in
1914. The 34-foot project, except for the Tule Lake extension,
was completed in 1946. In 1949 the Tule Lake extension was
dredged to partial dimension with contributed funds.
   The work remaining consists of extending the north and south
jetties; extending inner basin at Harbor Island; deepening the outer
bar to 38 feet, the jetty channel to 36 and 38 feet, all other deep
water channels, including the previously dredged part of the inner
basin at Harbor Island, to 36 feet, widening to 400 feet from Port
Aransas to the maneuvering basin at Corpus Christi; removing
200 feet of breakwater and completing channel from Avery Point
turning basin to and including a turning basin near Tule Lake.
Extension of the inner basin at Harbor Island and extension of the
jetties are not required at the present time.
   The controlling depths below mean low tide in the various chan-
nels and basins were as follows: Aransas Pass outer bar channel,
39 feet; Aransas Pass jetty channel, 36 feet; inner basin at Harbor
Island 31 feet, exclusive of main channel; channel from inner
basin to west end of Humble Oil & Refining Co. basin, 37 feet;
channel to town of Port Aransas, 7 feet; turning basin at Port
Aransas, 9 feet; channel from west end of Humble Oil & Refining
Co. basin to Corpus Christi turning basin, 33 feet; Corpus Christi
turning basin, 31 feet; industrial canal, 35 feet; Avery Point turn-
ing basin, 36 feet; and channel from Avery Point turning basin to
a point near the proposed Tule Lake turning basin, 12 feet.
   The total cost of the existing project to June 30, 1954, was as
follows:
                                                                            New work        Maintenance          Total

Regular funds-....... ,  . ...       .      ..    .   .   .       .    ..    $5, 651, 471       $11, 138, 747   $16, 790, 218
Public works funds-------------      -----------------------                     324, 287 .--------...--             324, 287
     Total United States funds....
                                _        _____________                ___     5, 975, 758       11, 138, 747     17, 114, 505
Contributed funds_.  ._ .__.   __          ____________________                  216, 422           152, 555         368, 977
     Total all funds-_---------------___________              _             - 6, 192, 180       11, 291, 302     17, 483, 482
594           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                      Cost and financial summary

                                             Fiscal year ending June 30                        Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                               1950         1951         1952         1953         1954        prior to 195012

New work:
   Appropriated...------------------  -------            -                   ------------
                                                                      .---------                    $7, 348, 293
                                                                                                    $------------
   Cost .... -------.------------.------------.------------             .-----------------------     7, 348, 293
Maintenance:
   Appropriated ....        $977, 000    $619, 238 * $279, 100       $326, 006    $677, 598         11, 680, 734
   Cost----------------      495, 914   1, 129, 950   380, 490        402, 927     207, 731         11, 201, 765

  1 Includes $1,372,534 for new work and $62,452 for maintenance for previous projects.
  sIn addition, $216,422 for new work and $152,555 for maintenance was expended from contributed funds.
  ' Difference of $566 between fiscal year 1954 costs shown above and that shown in " Operations and results
during fiscal year" is due to over-estimation of prepayments for June 1954.
Other new work data:
    Appropriated for succeeding fiscal year ending June 30, 1955----.........--.-- 400, 000
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project          ------------------------...... 24, 607,000

                         17. BRAZOS ISLAND HARBOR, TEX.
   Location. At the extreme south end of the coast of Texas, about
7 miles north of the mouth of the Rio Grande, and about 125 miles
south of Port Aransas. The harbor is at the inner end of Brazos
Santiago Pass, which lies between Brazos and Padre Islands, and
is the natural outlet from the Laguna Madre to the Gulf of Mexico.
 (See U. S. Coast and Geodetic Survey Chart No. 1288.)
   Previous projects. Authorized by River and Harbor Acts of
June 18, 1878, March 3, 1881, and March 2, 1919. For further
details, see page 1017, Annual Report for 1932, and page 882,
Annual Report for 1938.
   Existing project. This provides for depths of 38 feet in the
channel from deep water in the Gulf of Mexico through Brazos
Santiago Pass and 36 feet in all other channels and basins; and
widths of 300 feet in the channel from deep water in the Gulf of
Mexico through Brazos Santiago Pass, 200 feet in the channel
across Laguna Madre, 200 feet in the Port Isabel Channel includ-
ing the "wye" junction with the Brownsville Channel, 200 feet in
the Brownsville Channel for a distance of about 12.6 miles and 300
feet for a distance of about 1.4 miles; from 550 feet to 1,000 feet in
the Brownsville turning basin from this point for a distance of
2,640 feet over a bottom width varying from 550 feet to 1,000 feet;
for a small boat basin 12 feet deep, 300 feet wide and 1,500 feet in
length with a connecting channel 12 feet deep and 125 feet wide
adjacent to the existing Brownsville Channel; and for 36 feet in
the Port Isabel turning basin for a distance of 2,900 feet over a
bottom width varying from 200 feet at its entrance to 1,000 feet,
connecting with the existing turning basin. All depths refer to
mean low tide. The project also provides for two jetties at the
Brazos Santiago Pass entrance. Under ordinary conditions the
mean tidal range is about 11/2 feet and the extreme range about 2
feet. The height of the tides is dependent, to some extent on the
wind, and during strong "northers"in the winter season the water
surface in the southern end of the Laguna Madre may be raised 4
feet or more above the mean low tide in the Gulf.
   The estimate of cost for new work is $8,000,000 (July 1954),
                     RIVERS AND HARBORS-GALVESTON, TEX., DISTRICT                                      595
which is exclusive of $1,683,300 contributed by local interests and
of amounts expended on previous projects. The latest approved
estimate of annual cost of maintenance is $347,400 (July 1954).
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                       Work authorized                                    Documents
        ----------   I       --




July          Jetty channel, all inside channels and turning basins,
        3, 1930                                                           Rivers   and Harbors Committee
                and 2 rubble mound jetties.                                Deoc.   16, 71st Cong., 2d sess.
May 24, 1934  Local cooperation requirements modified to provide          Rivers   and Harbors Committee
 (PWA)          for the contribution of sufficient funds to cover the      Doc.    10, 71st Cong., 1st sess.
Aug. 30, 1935    entire cost of the original dredging of all inside
                channels and turning basins.
Aug. 26, 1937 Deepening the jetty channel to 31 feet and all inner        Rivers and Harbors Committee
                channels and the Brownsville and Port Isabel                Doc. 32, 75th Cong., 1st sess.
                 turning basins to 28 feet, provided no dredging will
                 be done at public expense within 50 feet of any es-
                 tablished pierhead line, wharf, or other structure.
Mar. 2, 1945 Enlargement of Port Isabel turning basin to 1,000 feet       H. Doc. 335, 76th Cong., 1st sess.
                by 1,300 feet with a flared entrance.
    Do....... Deepening to 35 feet channel from the Gulf of Mexico        H. Doc. 347, 77th Cong., 1st sess.'
                through Brazos Santiago Pass; deepening to 33 feet
                and widening to 200 feet channel across Laguna
                 Madre; deepening to 32 feet channels from Laguna
                 Madre to and including turning basins at Browns-
                 ville and Port Isabel; widening turning basins; and
                dredging present shallow-draft channel south of
                 Port Isabel from railroad bridge to Laguna Madre
                and connecting channel to Port Isabel turning basin
                 to provide a depth of 6 feet and width of 60 feet.
July 24, 1946 An additional connecting channel 150 feet wide and          H. Doc. 627, 79th Cong., 2d sessl.
                32 feet deep between the Port Isabel channel and
                 the Brownsville channel; and transfer shallow-
                draft channels at Port Isabel to Gulf Intracoastal
                Waterway.
May 17, 1950 Deepening to 38 feet in outer bar channels and 36 feet       H. Doc. 192, 81st Cong., 1st sess.'
                in all other authorized channels and basins; widen-
                ing all other channels to 200 feet, except a section in
                the Brownsville Channel which will be widened
                to 300 feet; extending the existing turning basins at
                Brownsville and Port Isabel; and for construction
                of a small boat basin with a connecting channel
                adjacent to the Brownsville ship channel.

1 Contains latest published maps.


   Local cooperation. Fully complied with except as required by
the River and Harbor Act of May 17, 1950 (H. Doc. 192, 81st
Cong., 1st sess.), local interests being required to furnish, without
cost to the United States, all lands, easements, rights-of-way, and
spoil disposal areas necessary for construction, maintenance, and
operation of the modified project, when and as required; hold and
save the United States free from damages due to construction and
maintenance of the project; construct suitable docks on the Port
Isabel turning basin extension; and install and maintain in the
small boat basin suitable mooring facilities to which all vessels
shall have free and equal access during storm periods, none of
which has been complied with, except that the assurances required
by the authorizing legislation have been furnished and accepted.
   Terminal facilities. On the westerly side of the turning basin
at Port Isabel is located a wharf, 550 feet long containing a sheet-
metal transit shed 100 by 350 feet and a precooling plant with a
capacity of approximately 24 cars every 8 hours. A sheet-metal
warehouse 100 by 200 feet is located about 70 feet west of the
transit shed. About 200 feet south of this wharf is a dock, 600
feet long by 16 feet wide, used for unloading tropical fruits and
 596      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  equipped with facilities for supplying diesel fuel to ships at the
  rate of 200 gallons per minute. Along the north end of the turn-
  ing basin a 2-level oil dock, 400 feet long, is equipped with facili-
  ties for receiving and loading oil cargoes into barges and for bunk-
  ering ships. All of the above facilities, owned by the Port Isabel-
  San Benito Navigation District, are serviced by railroad and high-
way connections and are open to all on equal terms. All docks
and wharves are equipped with facilities for servicing ships with
fresh water and electric current. An oil refinery and two storage
tank farms, all privately owned, are located near the Port Isabel
turning basin. This refinery has a maximum capacity of 15,000-
barrel topping unit and 4,000-barrel platforming unit and a com-
bined tank storage capacity of 1,224,000 barrels. Adjacent to the
turning basin and having access to the Gulf Intracoastal Water-
way is a shallow draft channel, 11/2 miles long, on which is located
about three-fourths of a mile of privately owned low-level wharves
equipped with facilities for handling tropical fruits, barge traffic,
and sea foods. Additional facilities on this channel include 3
marine filling stations, 2 machine shops, several marine ways for
handling small craft and medium size barges, an ice plant, and a
quick-freeze plant for servicing boats handling seafoods. These
facilities are privately owned and operated, and are available on
an individual contract basis.
    Along the north side of the Brownsville turning basin the
Brownsville Navigation District has constructed three concrete
wharves. Two of these wharves are 440 feet long and 165 feet
wide with a timber dock extension 100 feet long and 36 feet wide.
A metal warehouse 120 by 400 feet is located on each concrete
wharf. The third wharf is 400 feet long and 165 feet wide and
contains a 120- by 390-foot metal warehouse. Also on the north
side of the turning basin is located a concrete decked steel sheet
pile dock 1,000 feet long and 140 feet wide with a 500- by 100-foot
metal warehouse located on the dock. Along the west end of the
basin is a concrete wharf 450 feet long and 165 feet wide contain-
ing a 400- by 120-foot metal warehouse with an adjoining truck-
unloading apron 100 feet by 16 feet. All of the above terminals
have rail facilities. On the west end of the basin is a timber dock
400 feet long used for servicing small craft. Located on the south-
west corner of the turning basin is a marine ways for servicing
shrimp boats and other small craft and a repair shop operated in
connection therewith, all of which are privately owned. On the
south side of the turning basin, towards the west end, is located a
concrete barge dock 300 feet long and 100 feet wide with a 400-
foot unloading and storage apron, and a steel warehouse of 25,000
square-foot area, complete with railroad spur track. Also located
on the south side of the basin is a concrete dock 525 feet long and
20 feet wide, with 2 open steel sheds 32 by 280 feet located thereon.
This dock is equipped with complete systems for handling tropical
fruits and is served by two railroad spur tracks. On the west side
of the south slip is located a concrete open dock 500 feet long and
100 feet wide, equipped with a railroad spur track to the rear of the
apron. On the east side of the turning basin is a timber wharf 10
feet wide and 800 feet long for docking and servicing shrimp
        RIVERS AND HARBORS-GALVESTON, TEX.; DISTRICT              597
trawlers. There are also 4 marginal timber docks, each 11 feet
wide and 100 feet long, extending into the basin from shore at 52-
foot intervals. This entire area is served by an open, hard-surfaced
road and parking area. On the north side of the channel and to the
east of the turning basin are located three 500-foot oil docks with
direct pipeline connections to the bulk-oil terminals and to the
chemical refining and separating plants, also a 350-foot concrete
oil-barge dock with direct pipeline connections to the chemical re-
fining and separating plants. North of the general cargo terminal
is a privately owned, high-density cotton compress, with a storage
capacity of 46,000 bales, covering an area of 347,000 square feet.
Also north of the general cargo terminal is a bonded warehouse
having a storage capacity of 10 acres and equipped with rail
facilities. On the southwest corner of the navigation district
property is located a privately owned cotton compress and ware-
house equipped with two high-density presses having 320,000
square feet of storage space and a storage capacity of 60,000 bales.
In addition, two cotton compresses .are located in the city of
Brownsville, Tex. These compresses have combined storage capac-
ity of 90,000 bales and are serviced by direct rail and truck con-
nections with port facilities. The Brownsville Navigation District
employs 1 rubber-tired mobile crane of 15-ton capacity on the
terminal. Diesel fuel is available at the dock on the south side of
the basin. The oil docks are equipped with facilities for handling
and/or storing crude and refined oil. These oil docks have direct
pipeline connections to the various oil storage terminals. There
are 5 privately owned terminals equipped with facilities for han-
dling petroleum products having a combined maximum storage ca-
pacity of 1,288,605 barrels. Two chemical refining and separating
plants are located on navigation district property to the east of the
port proper, and have adequate facilities servicing the oil docks,
including railroad and highway connections which are open to all
on equal terms. The Brownsville Navigation District has dredged
a basin for shrimp trawlers and small fishing boats located 4.4 miles
east of the Brownsville turning basin. It consists of 2 slips each
400 feet wide, 1,500 feet long, and 15 feet deep, connected to the
Brownsville ship channel by a channel 800 feet long and 100 feet
wide. There are 7,600 linear feet of docking space for the fishing
and shrimp boats including 14 fuel and icing piers. There are 11
fish and shrimp processing and freezing plants in operation or
under contract along the two slips. A modern marine railway is
being constructed which is equipped with facilities for handling up
to 5 boats at a time, which is to be enlarged at a later date to handle
up to 10 boats at a time. Additional facilities at this basin include
6 fuel and ice plants, 4 radio and Loran repair shops, 1 electric re-
pair shop and 4 marine engine repair shops. The facilities are
privately owned and operated, and are available on an individual
contract basis.
   Operations and results during fiscal year. Maintenance: Con-
dition surveys and miscellaneous inspections and reports were made
at a cost of $26,398. Preliminary surveys, plans, and specifications
were completed for repairs to two rubble stone jetties at Brazos
Santiago Pass at a cost of $6,902. Work under the contract during
598                   REPORT OF CHIEF OF ENGINEERS, U. S. ARMY', 1954

the period February 23 to June 30, 1943, consisted of placing 1,537
tons of cover stone, 3,458 tons of core stone, 265 tons of riprap
stone, 2,683 cubic yards of concrete and 590 displaced cover stone
picked up and replaced, all on the south jetty, at a cost of $238,164.
A total of 1,005,706 cubic yards of material was removed from
30,400 linear feet of channel at a cost of $158,125, as follows:

      Government                                                                                   Cubic          Linear feet
       plant or                             Location                            Period             yards          of channel        Cost
       contract                                                                                  removed           dredged

Contract----------............   Brownsville Channel.                        Jan. 5 to Mar.            749, 828       22, 400       $98, 088
                                                                               5, 1954.
Government hop-                  Outer bar and jetty channel.                Apr. 6 to May             255, 878        8, 000        60, 037
per dredge A.                                                                 3, 1954.
   Mackenzie.


   The total cost for all work during the fiscal year was $429,589.
   Condition at end of fiscal year. The existing project is 66 per-
cent complete. The 25-foot project channels and jetties were com-
pleted in 1936. The deepening of the sea bar and jetty channels to
the 31-foot depth and of the inside channels and basins to the 28-
foot depth was completed in 1940. Widening and deepening the
Port Isabel turning basin as authorized by the River and Harbor
Act of March 2, 1945, was completed in 1947. The 32-foot project
channels and basins were completed in 1949. Work remaining
consists of deepening the entrance channel to 38 feet at mean low
tide from deep water in the Gulf of Mexico through Brazos San-
tiago Pass, deepening to 36 feet all other channels and turning
basins, widening to variable widths certain sections of the channels,
extending the Brownsville and Port Isabel turning basins and con-
structing a small-boat turning basin with a connecting channel
adjacent to the Brownsville ship channel.
   The controlling depths at mean low tide in the various channels
and basins comprising the waterway were as follows:
                                                                                                                           Depth in feet
                                                                                                                     below mean-low-tide

Jetty channel from deep water in gulf to inside Brazos Santiago Pass                                        36
                                                                                                       ..........
From inside Brazos Santiago Pass to westerly side of Long Island ........                                   30. 5
Westerly side of Long Island to turning basin at Port Isabel                       ...................      2..........
                                                                                                            29.   5
Turning basin at Port Isabel.. ....-...................... . ....... ..................                     31
Channel from westerly side Long Island to turning basin at Brownsville.                                     28. 6
Turning basin near Brownsville ...                  ............ ..... ......
                                               _........                      ....       .........          30. 8

   The total cost of the existing project to June 30, 1954, was as
follows:

                                                                                     New work             Maintenance            Total


Regular funds ...................                              ....
                                                        _________.                    $1, 860, 747        $3, 640, 812          $5, 501, 559
Public work funds                      __   _ _______                 ____       _     2, 848, 560----.....-..                   2, 848, 560

     Total United States funds                            -------                        4, 709, 307          3, 640, 812     8, 350, 119
Contributed funds.... .... ..                        __       .....    ...--             1, 683, 258                          1, 683, 258
                                                                                                                  .-------------

        Total all funds          ..   ____________          ____         ____            6, 392, 565          3,640, 812        10, 033, 377
                         FLOOD CONTROL-GALVESTON, TEX., DISTRICT                                                            599
                                                  Cost and financial summary

                                                             Fiscal year ending June 30                           Total to June
                                                                                                                  30, 1954, includ-
                                                                                                                  ing fiscal years
                                          1950            "1951              1952         1953         1954       prior to 195012
New work:
   Appropriated                                     --                                                                  $5,385, 162
   Cost ...------------------------------------------------------------------                                            5, 385,162
Maintenance:
   Appropriated .                       $185, 000          $370, 961          $394, 055   $96, 235    $739, 700         3, 956,670
   Cost                                  189, 598             20, 647          657, 113   177, 759   '429, 886          3, 641, 109


     Includes $799,217 for new work for previous projects.
   2In addition, $1,806,619 for new work was expended from contributed funds.
  sDifference of $297 between fiscal year 1954 costs shown above and that shown in "Operations and results
during fiscal year" is due to over-estimation of prepayments for June 1954.

Other new work data: Estimated additional amount needed to be appro-
                                                                     $3,284,900
  priated for completion of existing project..-----------...................-------

                                           18. BUFFALO BAYOU, TEX.
   Location. These improvements are located on Buffalo Bayou,
a tributary of the San Jacinto River, in Harris County, west and
northwest of the city of Houston, Tex. (See U.S.G.S. quadrangle
sheets for Harris County.)
   Existing project. The authorized plan provides for the im-
provement of Buffalo Bayou and its tributaries above the turning
basin (Houston) of the Houston Ship Channel to control floods for
the protection of the city of Houston, and to prevent the deposition
of silt in the turning basin of the ship channel by construction of
detention reservoirs, enlargement and rectification of channels,
construction of control works, and any diversions which may be
found advisable. The authorized cost of Federal construction is
limited to $9,000,000. The estimated Federal cost is $9,000,000
for construction and $13,400,000 for lands and relocations; the
estimate of cost to local interests, made in 1951, is $22,130,700, a
total of $44,530,700 (July 1954). The estimated annual cost of
maintenance is $91,250 (July 1954).
   The existing project was authorized by the River and Harbor
Act approved June 20, 1938 (H. Doc. 456, 75th Cong., 2d sess.),
and the Flood Control Act approved August 11, 1939.
   The elements of the plan of improvement as authorized at this
time consist of the Addicks, Barker, and White Oak detention res-
ervoirs, the North and South Diversion Canals, and the rectification
of Buffalo Bayou channel. Completed construction at this time
consists of Addicks Dam and Barker Dam and channel rectification
in Buffalo Bayou to a point about 6 miles downstream of the dams.
The two dams control 129 and 150 square miles, respectively.
Barker Dam is an earthfill detention dam 71,900 feet long, includ-
ing outlet works, and approximately 37 feet high, with a reservoir
capacity of 207,000 acre-feet. Addicks Dam is an earthfill deten-
tion dam 61,166 feet long, including outlet works, and approxi-
mately 49 feet high, with a reservoir capacity of 204,500 acre-feet.
Each dam has outlet works consisting of 3 gated and 2 ungated
culverts.
   Recommended modification of project. Under date of June 18,
1952, the Chief of Engineers recommended modification of the
existing project to provide, in lieu of the features of the existing
600          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

project, for Barker and Addicks Reservoirs on Buffalo Bayou, and
for clearing, straightening, enlarging, and lining where necessary
on the channels of Buffalo Bayou, Brays Bayou, and White Oak
Bayou, with such modifications thereof as in the discretion of the
Chief of Engineers may be advisable at an estimated additional
first cost to the United States of $25,997,000 for new work and a
total of $115,000 annually for operation and maintenance of Barker
and Addicks Reservoirs. (H. Doc. 250, 83d Cong., 2d sess.).
   Local cooperation. The requirements are not being complied
with in view of the interim report status of the remaining con-
struction. The offer of the Harris County flood control district
to advance the sum of $2,900,000 to the Department for prosecu-
tion of the Buffalo Bayou project was accepted by the Secretary of
War on December 18, 1940, and July 10, 1945.
   Operations and results during fiscal year. New work: Opera-
tion during the fiscal year consisted of continuation of land ac-
quisition for Barker Reservoir, Addicks Reservoir, and Buffalo
Bayou rectified channel at a cost of $778.
   Maintenance: Routine operations, maintenance and care were
carried on from July 1, 1953 to June 30, 1954, on Barker and Ad-
dicks Dams and the rectified channel at a cost of $77,627. Pre-
liminary surveys, plans, and specifications were made for the crown
widening and application of seal coat on Addicks Dam at a cost of
$581. The total cost of all work for the fiscal year was $78,986,
of which $778 was for new work and $78,208 for maintenance.
   Condition at end of fiscal year. The existing project was 26
percent complete. Construction of Barker Dam was completed in
February 1945. Addicks Dam and channel rectification to South
Canal were completed in October 1948.
   Land acquisition for Barker and Addicks Dams and channel rec-
tification work was 99 percent complete.
   No work was done on the second stage development which in-
cludes construction of South Canal and its appurtenant intersection
dam and rectification work.
   To complete the project, subsurface explorations and detailed
design must be completed and construction of remaining units of
the authorized project accomplished.
   Total cost under the existing project to June 30, 1954, was as
follows:


                                                                     New work          Maintenance          Total
Regular funds---...  ----------------------------------               $8, 472, 794              $705, 501   $9, 178, 295
Advance funds.---------_---------------------------------              2, 900, 000 -------------             2, 900,000

      Total for all work---      ..---------------.---------------    11, 372, 794             705, 501     12, 078, 295
                     FLOOD CONTROL-GALVESTON, TEX., DISTRICT                                                               601
                                          Cost and financial summary

                                                    Fiscal year ending June 30                                 Total to June
                                                                                                              30, 1954, includ-
                                                                                                              ing fiscal years
                                    1950           1951           1952            1953          1954           prior to19501
New work:
   Appropriated------........ ....------------.   $234, 500       $60, 000 .. ,.-----         -$63,    800         $8, 474,
                                                                                                                          228
           __---....... $79, 633
   Cost- ...-                                      203,334         92, 938    $27, 881                 778          8, 472,
                                                                                                                          794
Maintenance:
   Appropriated_------- _           116,900         64, 600        90, 000         81, 800          82, 000           724, 650
   Cost----------....--..            93, 535        79, 347        85, 911         81, 548      2   78, 929           706, 222

   1In addition, $2,900,000 for new work was expended from funds advanced by Harris County Flood Con -
trol District.
   2 Difference of $721 between fiscal year 1954 costs shown above and that shown in "Operations and results
during fiscal year" is due to over-estimation of prepayments for June 1954.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_---
                                                         ..--.-.-----.-..      $1,433
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project.     -      -................           11, 027, 075
                                                 .......................................

                           19. INACTIVE NAVIGATION PROJECTS
                                                  River and Harbor

                                                              For last,        Cost to June 30, 1954             Estimated
                                                           full report,                                           amount
                   Name of project                              see                                              required
                                                              annual            Con-          Operation             to
                                                              report          struction         and              complete
                                                               for-                          maintenance
1. Johnsons Bayou, La.                                              1933
                                    ...............----------------------     $2, 261.35       $54, 042.26           (2)
2. Mouth of Trinity River, Tex.'.....          .......... 1928                79, 540. 44       10, 870.95           (2)
3. Bastrop Bayou, Tex..            ..----------------------         1931       9, 920. 22       27, 129. 21           $23, 760
4. Brazos River, Tex., from Velaseo to old Wash-                    1924     216, 989. 48      223,010.  52           130, 400
     ington.
5.East Bay Bayou (Hannas      Reef), Tex.' a-----                   1922       2, 476.02           847. 80               500
                                                                                                                       72,
6. Oyster Creek, Tex.' .       ..-----------------------            1922       6, 942. 24        7,556. 73           (2)
7. Corpus Christi, Tex., channel to Navy sea-                       1946  1, 194, 344. 69       15,579. 63           (2)
     plane base, Encinal Peninsula.
8.Little Bay, Tex..........................-------------------------------
                                                                    1951                                               32, 900

     1Channel adequate for commerce.
  'Completed.
  * No commerce reported.
  4The River and Harbor Act of May 17, 1950 (H. Doc. 768, 80th Cong., 2d sess.) revoked the 6-foot channel
for Bastrop Bayou as authorized by the River and Harbor Act of Mar. 2, 1945 (H. Doc. 337, 76th Cong.,
1st sess.), and reauthorized only that portion of the existing 4- by 100-foot project lying westward of the
Gulf Intracoastal Waterway..

                                                    Flood Control

                                                             For last        Cost and expenditures to            Estimated
                                                           full report            June 30, 1954                  Estiamount
                   Name of project                              see                                               required
                                                             annual              Con-         Operation               to
                                                              report          struction          and             complete
                                                               for--                         maintenance
1. Snagging and clearing under authority of sec.               1943           $25, 702.86 .............. (')
     2 of the Flood Control Act approved Aug.
     28, 1937, as amended.
2. Emergency flood control work under authority                1949       ......-...          $406,075. 31           (')
     of the Flood Control Act approved Aug. 18,
     1941, as amended.
3. Emergency flood control work under authority                1949 -(..                       364, 659.90           (')
                                                                                                                     '1,
     of Public Laws 138 and 318, 78thCong., and
     Public Law, 75,79th Cong.

1Completed.
602                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                 Cost and financial summary
                                                  NAVIGATION PROJECTS


                                                            Fiscal year ending June 30                                      Total to June
                                                                                                                         , 30, 1954, includ-
                                                                                                                           ing fiscal years
                                         1950             1951             1952             1953             1954            priorto 1950
New work:
   Appropriated -------- ------------ -----------------       ----------- ---                                   -   --           $1, 512, 474
   Cost-----------------------------                 ------------             -                             -                     1,512,474
Maintenance:
   A ppropriated - - - -- -- -- --.-   -- -- -- -.--    - -- --.--- -- -- -                                 -- --.---               339,037
   Cost . .........-                                                                                                                339,037




                                                FLOOD CONTROL PROJECTS


                                                             Fiscal year ending June 30                                      Total to June
                                                                                                                          30, 1954, includ-
                                                                                                                          ing fiscal years
                                         1950             1951             1952             1953             1954           priorto 1950
New work:
   Appropriated ......---------------------.........................--------- ......-----------         ...........
                                                                                                  ..----------------------          $25, 703
   Cost..............----------------- ------------..................------------ ------------  ...        ............              25, 703
Maintenance:
   Appropriated..-------------------- ------------ ----------------------------------                                             1, 770, 735
   Cost -----------------------------------------------------------------------------                                             1, 770, 735



                                     20. GENERAL INVESTIGATIONS
   Examinations and surveys. The cost of work during the year
was $60,609. The balance unexpended at the end of the fiscal year
was $315, and accounts receivable at the end of the fiscal year
were $279.
   The balance of $594 will be applied to studies under way. The
estimated additional sum of $70,600 can be profitably expended
during fiscal year 1955.
   Collection and study of basic data. Activities under this head-
ing during the fiscal year included (1) collection of rainfall data for
storm studies as requested by other districts; (2) study and re-
vision of a storm and flood emergency manual which programs the
Galveston District operates during major storms and floods, and
 (3) investigation of current floods in the Lower Rio Grande Valley
including surveys and estimates of flood damages and collection of
rainfall and stream flow data.
IMPROVEMENT OF RIVERS AND HARBORS IN THE FORT
            WORTH, TEX., DISTRICT
   The district comprises that portion of Texas south of the Red
River drainage basin exclusive of the drainage basin of the Rio
Grande and its tributaries above and including the Pecos River;
exclusive of the drainage basins of all the short streams arising in
the coastal plain of Texas and flowing into the Gulf of Mexico, in-
cluding the entire basin of Buffalo Bayou, San Jacinto, San Ber-
nard, Lavaca, Navidad, Mission, and Aransas Rivers; exclusive of
the lower basins of the major streams flowing into the Gulf as fol-
lows: Sabine River below Orange, Neches River below Beaumont,
Trinity River below Liberty, Brazos River below confluence with
Navasota River, Colorado River below Austin, Guadalupe River
below confluence with San Marcos River, San Antonio River below
Goliad, and Nueces River below Calallen; and exclusive of the
coastal plain situated to the east of the Missouri-Pacific Railroad
between Calallen and Raymondville, and all of Starr, Hidalgo,
Cameron, and Willacy counties, covering the Lower Rio Grande
Valley. The district includes that portion of western Louisiana
in the Sabine River drainage basin above Orange, Texas, and the
portion of eastern New Mexico embraced in the drainage basins of
the Brazos and Colorado Rivers.
                                                      IMPROVEMENTS

                         Navzgation                                            Flood control-Continued
                                                          Page                                                                   Page
1.Neches and Angelina Rivers,                                   12. Whitney Reservoir,                      Brazos
     Tex ............................................     604          River, Tex ........-------------......................    618
2. McGee; Bend Reservoir, An-                                    13. Belton Reservoir, Leon River,
     gelina River, Tex.........                           605          Tex ..................................                    613
3. Dam B Reservoir, Neches                                       14. Hords Creek, Pecan Bayou,
     River, Tex, ..----                                   606          Tex...........................................            614
4. Inactive navigation projects......                     607    15. San Angelo Reservoir, North
                  Flood control                                        Concho River, Tex................                         622
                                                                 16. Canyon Reservoir, Guadalupe
5. Trinity River and tributaries,                                      River, Tex.........------------ ---....                   624
         Tex .........       ...................-------   607
                                                                 17. Inactive flood control projects..                           625
6. Lavon Reservoir, Tex................                   609
                                                                                                                                 625
7. Garza-Little Elm Reservoir,                                   18. General Investigations ..............
        Tex.....-----..........-------------------...     610    19. Inspection of completed proj-
8.   Grapevine Reservoir, Tex_ .......                   612          ects----.. --, .       .       ..--------------           625
9.   Dallas Floodway, Tex ...........                    614    20. Emergency flood control work..                              626
10.   Benbrook Reservoir, Tex ......                      616    21. Floodcontrol work under special
11.   Fort Worth Floodway, Tex......                      617          authorization ............  .                        ..   627




                                                                                                                    603
604                  REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                            1. NECHES AND ANGELINA RIVERS, TEX.
   Location. The Neches River has its source 60 miles southeast
of Dallas and flows generally southeast 416 miles to Sabine Lake 4
miles east of Port Arthur, Tex. The Angelina River flows south-
east 200 miles to its confluence with the Neches River 126 miles
above its mouth. The authorized features are located as follows:
Rockland Dam on Neches River approximately 3 miles west of
Rockland, Tex.; McGee Bend Dam on Angelina River approxi-
mately 10 miles northwest of Jasper, Texas; Dam A on Neches
River approximately 4 miles west of Horger, Tex.; Dam B on
Neches River approximately one-half mile north of Town Bluff,
Tex. (See U. S. Geological Survey Base Map, Northeast Texas,
Scale 1:500,000.)
   Existing project. The plan of improvement provides for dams
and reservoirs to be located at the Rockland and McGee Bend dam
sites on the Neches and Angelina Rivers, respectively, which will
effect a large measure of flood protection to agricultural lands in
the lower river valley and to the city of Beaumont, reduce the
hazards to navigation resulting from floods, and provide a regu-
lated flow in the lower river to supply municipal, agricultural, and
industrial demands. In addition, these proposed projects would
permit the development of a large amount of firm power and afford
opportunities for recreation.
   The plan also provides for construction of Dam A, located on the
Neches River below Rockland Dam, for the development of power;
and Dam B, located below the confluence of the Angelina and
Neches Rivers, to regulate the daily fluctuations in discharge from
the turbines in the upper projects and to develop a limited amount
of power.
   Construction of Rockland and Dam A Reservoirs and of power
facilities at Dam B is to be deferred until justified by future con-
ditions.
   As itemized in the tables below, the estimate of cost for new
work, revised in 1954, is $106,185,350, including $5,000,000 non-
Federal costs. The flood control works included in the compre-
hensive plan are listed below:
                                                                                   Name of dam

                                                    Rockland       McGee Bend
                                                     Dam              Dam                    Dam A              Dam B

                          Rockland,       Jasper,
Nearest city----........----......----------...         Horger,                                            Town Bluff,
                               Tex.         Tex.           Tex.                                               Tex.
                           Neches River Angelina River Neches River
Stream-----------............-----...............                                                           Neches River

Drainage area, square miles ...... 3626---..........--. 3453 --...........    3778-...-..- 7585
Distance above mouth of Neches 160.4--------.......... 151.3--------..........142--....-.. -113.7
  River (river-mile)
Height of dam above river bottom 106.........-----...   128.......----------. 49 .....-..... 45.
  (feet).
Type of dam-             .           Earthfill-.....
                              .--.--.------             Earthfill......       Concrete and Concrete and earth
                                                                               earth
Storage capacity-flood     control 1, 020,100.        . 1,148, 900......      None ........  None.
  (acre-feet)
Power and regulation of flow 1, 125, 500-..             1, 383, 500.-....     Pondage-_...   94, 200.
  (acre-feet).
Dead storage (acre feet)........ 1, 141, 700......      1, 508, 400.....None......... None.
        Total storage (acre-feet)......           3,287,300 ------
                                                                1 4,   040,   800-----   Pondage_____1   94, 200.
              RIVERS AND HARBORS-FORT WORTH, TEX., DISTRICT                                                                  605

                                                                            Name of dam

                                           Rockland            McGee Bend
                                             Dam                  Dam                  Dam A                         Dam B

Nearest city--------- ---------        Rockland,                 Jasper,            Horger,                   Town Bluff,
                                           Tex.                     Tex.               Tex.                      Tex.
Stream_............----..--      ..- . Neches River            Angelina River      Neches River                Neches River
Power development (KW)........           13, 500.........      45,000_........     2, 700      __........   2, 935
Estimated cost (1954):
     Construction_.                       $40, 822, 500-....
                                    ..--------                 $40, 392, 800....   $3, 213. 400.....        $6, 561, 150
     Lands and damages....-----------      5, 477, 500....       8, 307, 200....            6,600.....       1,404,200
        Total--......---------.----. $46, 300, 000.... I $48, 700, 000... $3, 220, 000.....                 2$7, 965, 350
  1Includes $3 million contributed funds.
  2 Includes $2 million contributed funds.

    See individual reports for further details.
          2. McGEE BEND RESERVOIR, ANGELINA RIVER, TEX.
   Location. The improvement is located on the Angelina River
25.2 miles upstream from its confluence with the Neches River and
about 10 miles northwest of Jasper, Tex.
   Existing project. The plan of improvement, a unit of the com-
prehensive plan for flood control, water conservation, and hydro-
electric power development in the Neches-Angelina Rivers Basin,
provides for the construction of a rolled earthfill embankment
10,950 feet in length, three earthen saddle dikes totaling 7,470
feet, and an uncontrolled concrete spillway 400 feet long. The top
of the dam will be about 128 feet above the river bed. The reser-
voir will have a storage capacity of 4,040,800 acre-feet including
1,148,900 acre-feet of flood control storage, 1,383,500 acre-feet of
power storage, and 1,508,400 acre-feet of dead storage. The capac-
ity of the initial installation of hydroelectric generating facilities
will be 45,000 kilowatts.
   The estimated cost of the project (1954) is $40,392,800 for con-
struction and $8,307,200 for land and damages, a total of $48,-
700,000, including $3 million to be contributed by local interests.
   The existing project was authorized by the River and Harbor
Act approved March 2, 1945 (Public Law No. 14, 79th Cong., 1st
sess.) in accordance with the plan of improvement outlined in
Senate Document No. 98, 76th Congress, 1st session.
   Local cooperation. The project was adopted subject to the pro-
vision that before construction is started upon any element, the
State of Texas or other responsible local agency give assurances
satisfactory to the Secretary of the Army that upon completion of
the entire project it will contribute toward the first cost of the work
the sum of $5,000,000. The Lower Neches Valley Authority has
furnished assurances, which were accepted by the Assistant Secre-
tary of the Army on November 13, 1947, that at any time after
Congress appropriates sufficient funds for the construction of Dam
B Reservoir, which by the addition of $2,000,000 would be sufficient
to complete Dam B Reservoir, upon demand by the Secretary of the
Army it will contribute $2 million toward the cost of construction
of Dam B Reservoir; and upon completion of McGee Bend Reser-
voir on the Angelina River, it will contribute $3 million toward the
606         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

first cost of the work. To date, local interests have contributed $2
million toward the first cost of Dam B Reservoir.
   Operations and results during fiscal year. Operations during
the fiscal year consisted of review of preliminary investigations and
engineering studies with a view to reducing the size of the project.
   Total cost during the fiscal year was $12,730, all for new work
from regular funds by hired labor.
   Condition at end of fiscal year. The existing project was 2 per-
cent complete. Engineering and design was 28 percent complete.
   Total cost to June 30, 1954, was $705,877, all for new work from
regular funds.
                                  Cost and financial summary

                                          Fiscal year ending June 30                    Total to June
                                                                                       30, 1954, includ-
                                                                                       ing   fiscal    years

                           1950         1951        1952        1953         1954       priorto 1950
New work'
   Appropriated           $200, 000 ----------   -$103,743      $50, 000   -$30, 000              $706, 457
   Cost_          _ _ _     81, 017   $132,483       26,334       6,690       12,730                  705,877

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-                     $580
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955--------------------------------...              ----------  580
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project                         ............ 44, 993, 543
                                          -........-...............

              3. DAM B RESERVOIR, NECHES RIVER, TEX.
   Location. The improvement is located on the Neches River
with dam site about 12.4 miles below the mouth of the Angelina
River,-one-half mile north of Town Bluff, Tex., and 93 river miles
north of Beaumont, Tex.
   Existing project. The plan of improvement, a unit of the com-
prehensive plan for flood control, water conservation, and hydro-
electric power development in the Neches-Angelina Rivers basin,
consists of a concrete and earth dam consisting of 6,100 feet of
uncontrolled spillway, 326 feet of gated channel spillway, and a
nonoverflow section 272 feet long. The top of the dam is about 45
feet above the river bed. The reservoir has a storage capacity for
conservation of 94,200 acre-feet.
   The estimated cost of the project (1954) is $6,561,150 for con-
struction and $1,404,200 for lands and damages, a total of $7,-
965,350 including $2 million contributed by local interests. The
estimated cost of annual maintenance is $62,000 (1954).
   The existing project was authorized by the River and Harbor Act
approved March 2, 1945 (Public Law 14, 79th Cong., 1st sess.), in
accordance with the plan of improvement outlined in Senate Docu-
ment No. 98, 76th Congress, 1st session.
   The River and Harbor Act approved June 30, 1948, modified this
project so as to provide that the local agency which gives assur-
ances that upon completion of the entire project it will contribute
toward the first cost of the work the sum of $5 million, will be
permitted to withdraw from the pool of Dam B not to exceed 2,000
cubic feet of water per second for its own use (Public Law 858,
80th Cong., 2d sess.).
                RIVERS AND HARBORS-FORT WORTH, TEX., DISTRICT                                                                        607
   Local cooperation. Fully complied with.
   Operations and results during fiscal year. Operations during
the fiscal year consisted of continuation of land acquisition by hired
labor, and completion of right bank earthwork and initiation of
bank slope protection by contract.
   Routine maintenance was carried on from July 1, 1953, to June
30, 1954.
   Total cost during the fiscal year was $227,405 for new work and
$60,650 for maintenance, a total of $288,055, all from regular funds.
   Conditions at end of fiscal year. Construction of the project
was started during March 1947, and the project was ready for
beneficial use in April 1951. At the end of the fiscal year the
project was 99 percent complete. Land acquisition was 96 percent
and construction was 99 percent complete. Work remaining to be
done to complete the project consists of completion of land acqui-
sition and completion of bank slope protection.
   The total costs to June 30, 1954, for regular funds were $5,-
886,463 for new work and $153,239 for maintenance, a total of
$6,039,702.
   The total costs to June 30, 1954, for contributed funds were
$2,000,000 for new work.
                                                      Cost and financial summary

                                                                   Fiscal year ending June 30                               Total to June
                                                                                                                           30, 1954, includ-
                                                                                                                           ing fiscal years
                                             1950                1951               1952          1953         1954         prior to 1950
New work:
   Appropriated- .... --.-..........                           $970, 100            $61, 300     $677, 600   -$34, 650          $5, 965, 350
   Cost.-..------------        $1, 624, 965                   1, 600, 083           159, 400      410, 523      227, 405         5, 886, 463
Maintenance:
    Appropriated-------     .....----------............-----------..........         67, 980       31, 746      57, 500             157, 226
        ......-..............-----.....
    Cost----                      --------------------------                         60, 075       32, 514      60, 650             153, 239

  Note. In addition, $2 million for new work was expended from contributed funds.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954...........-------------..... $55, 455
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955-------.........
                       --.........................................................      55,455
                                 4. INACTIVE NAVIGATION PROJECTS

                                                                                For last        Cost to June 30, 1954         Estimated
                                                                               full report                                     amount
                       Name of project                                            see                                          required
                                                                                annual            Con-        Operation           to
                                                                                report         struction         and           complete
                                                                                 for-                        maintenance
1. Dam A Reservoir, Neches River, Tex.'--------.....                              1952            $21, 700 --------------       $3, 198, 300
2. Rockland Reservoir, Neches River, Tex.2.....                                   1952            510, 200 --------------       45, 789, 800

1Dependent upon construction of Rockland Reservoir.
2 Deferred until justified by future downstream development.

                       5. TRINITY RIVER AND                                           TRIBUTARIES,               TEX.
   Location. These improvements are located in the upper portion
of the Trinity River Basin within a 50-mile radius of Dallas, Tex.
   Existing project. The River and Harbor Act approved March
2, 1945, adopted the comprehensive plan of improvement for navi-
gation, flood control, and allied purposes, in the Trinity River Basin,
          Sig 20--607-638
    608               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

as outlined in House Document No. 403, 77th Congress, 1st session.
This plan provides for the construction at this time of Benbrook,
Little Elm, and Grapevine Reservoirs, the modification of Garza
Dam, and the improvement of the levees and floodways at Fort
Worth and Dallas, for flood protection and water conservation. The
act also adopted the modification contained in House Document
533, 78th Congress, 2d session, which provides for the construction
of the Lavon Reservoir on the East Fork of the Trinity River. The
River and Harbor Act approved July 24, 1946, modified the author-
ized Lavon Reservoir to provide for conservation storage as may
be determined warranted by the Secretary of War upon the rec-
ommendations of the Chief of Engineers. The Civil Functions
Appropriation Act, approved October 24, 1951, further modified
Lavon Reservoir to provide for construction of water conservation
and utilization facilities, the cost of these facilities to be repaid by
local interests. The existing project maps are contained in the
project documents. As itemized in the tables below, the estimate
of cost for new work, revised in 1954, is $76,066,281, including
$11,812,181 non-Federal costs.                                                      The flood control works included
in the comprehensive plan are listed below:
                                                              Dams and reservoirs

                     Name                               Benbrook                           Lavon                        Grapevine                Garza-Little Elm


Stream .. __________....--.-                   _   Clear Fork _____                East Fork......     Denton Creek__                            Elm Fork.
Nearest City_---------------__                     Benbrook-... _                  Lavon_.........     Grapevine ..- -                           Lewisville.
Drainage area square miles -..                     433______________               777_-----------694-----------                                 1658.
Distance above mouth (miles__                      15_                             55.9 _-----------   11.7-........ _                           30.
Height (feet)...-------------                      130_-----------                 69_------------     137_-----------                           125.
Type_..----.-----.-----------                      Earthfill ---                   Earthfill________ Earthfill -.--                              Earthfill.
Flood control storage capacity                     170, 350 .........              275, 600 .......... 238, 250-       .-_       -.-             526, 700.
   (acre-feet).
C on s e rv a t i on st ora ge c ap ac i t y       7 2 , 5 0 0 . . . . . . . . . . 10 0 , 0 0 0                   16 1, 2 5 0 . . . . . . . .. . 4 3 6 , 0 0 0.
   (acre-feet).
Se d im e n t atio n r e s e r ve c a p ac it y
   (acre-feet)
                                                   15 , 75 0 . . . . ..-.                                                         ------
                                                                                 .-4 7 , 8 0 0 . .- . . . . . . . . 3 6 , 0 0 0 ---              5 3 , 5 00.

Capacity, total (acre-feet)....                    258, 600       -....
                                                                  -                423, 400 --------              435, 500--------                1, 016, 200.

Estimated cost:
    Construction .... _______.                               ---..
                                                   $8, 619, 700                    $8, 690, 726 -.---             $7, 732, 265 .. _--             $14, 529, 630.
    Lands and damages _...                         $2, 326, 000- .                 $2, 483, 274- ......           $2, 599, 600- .....              $8, 578, 436.

    Total__________________                        $10, 945, 700 ....----         $11, 174, 000 ..--              1 $10, 331, 865_-__            2 $23, 108, 066.


    1 Includes $2,060,465 non-Federal costs.
    2 Includes $3,410,066 non-Federal costs.

                                                     Local flood protection works

                                                                                                                                       Estimated cost
                                                           Distance                                                                                  .-
     Location                    Stream                      above                Type structure                                          Lands
                                                             mouth                                                  Construc-              and                    Total
                                                             (miles)                                                  tion               damages'

Fort Worth..           Clear and West                           560          Levee and channel                      $8, 388, 150          $914, 500        2   $9,302, 650
                        Forks.                                                 clearing.
Dallas         - -     Elm Fork and Trin-                       505          Levee, channel                         10, 815, 500           388, 500        ' 11, 204,000
                        ity River.                                            clearing, and mod-
                                                                              ification of interior
                                                                              drainage.


1Non-Federal    costs.
2 Includes $5,437,650 non-Federal costs.
' Includes $904, 000 non-Federal costs.

     See individual reports for further details.
           FLOOD CONTROL-FORT WORTH, TEX., DISTRICT                609
                    6. LAVON RESERVOIR, TEX.
   Location. The improvement is located in Collin County, Tex.,
on East Fork of Trinity River, 55.9 miles above its confluence with
the Trinity River and about 22 miles northeast of Dallas, Tex.
    Existing project. The plan of improvement, a unit of the com-
prehensive plan for flood control in the Trinity River Basin, con-
sists of an earthfill dam, approximately 9,499 feet in length, includ-
ing a gate-controlled concrete spillway 568 feet in length located
in the right abutment. The dam has a maximum height of 69
feet above the stream bed. The reservoir provides a storage
capacity of 275,600 acre-feet for flood control, 100,000 acre-feet for
conservation, and a sedimentation and dead storage reserve of
47,800 acre-feet, a total of 423,400 acre-feet. The reservoir ex-
tends 10 miles up the East Fork and 16.1 miles up Pilot Grove
Creek.
    The estimated cost of the project (1954) is $8,690,726 for con-
struction and $2,483,274 for lands and damages, a total of $11,174,-
000. The estimated cost of annual maintenance is $78,000 (1954).
    The existing project was authorized by the River and Harbor
Act approved March 2, 1945. (See H. Doc. 403, 77th Cong., 1st
sess., and H. Doc. 533, 78th Cong.) The project was modified by
the River and Harbor Act approved July 24, 1946, and the Civil
Functions Appropriation Act, 1952. The latest published maps are
contained in the project documents.
    Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies. Local interests are required by law to repay
the cost of a water supply intake structure constructed under au-
thorization "provided in the Civil Functions Appropriations Act,
1952, approved October 24, 1951 (Public Law 203, 82d Cong., 1st
sess.). The North Texas Municipal Water District, a State-author-
ized agency, has been organized for the purpose of assuming the
required responsibilities.
    Negotiations with the North Texas Municipal Water District
have been consummated and a formal contract drafted for rights to
conservation storage in the project. The cost to local interests,
including the cost of the water supply intake structure, is now
estimated at $1,220,291.
    Operations and results during fiscal year. Operations during
the fiscal year consisted of continuation of land acquisition and
preparation of detailed plans and specifications by hired labor,
completion of relocation of G.C.&S.F. RR and completion of em-
bankment by continuing contracts, and initiation of construction
of project buildings by contract.
   Routine maintenance was carried on from July 1, 1953, to June
30, 1954.
   Total costs during the fiscal year were $605,023 for new work
and $50,531 for maintenance, a total of $655,554, all from regular
funds.
    Condition at end of fiscal year. Construction of the project
was started during January 1948, and the project was ready for
beneficial use in October 1953. At the end of the fiscal year the
project was 96 percent complete. Land acquisition was 94 percent
and construction was 96 percent complete. Work remaining to be
610                  REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

done to complete the project consists of relocation of Collin County
roads, completion of land acquisition, and completion of construc-
tion of project buildings.
   The total costs to June 30, 1954, for regular funds were $10,-
720,752 for new work and $74,143 for maintenance, a total of
$10,794,895.
                                                    Cost and financialsummary

                                                                Fiscal year ending June 30                                          Total to June
                                                                                                                                   30, 1954, includ-
                                                                                                                                   ing fiscal years
                                            1950               1951              1952              1953              1954            priorto 1950

New work:
   Appropriated.--...-..$2, 604, 300                      $3, 436, 000      $1, 500, 000         $184, 600        -$45, 800              $11, 174,000
      Cost---------------                2, 632, 319       3, 047, 814        1, 741, 987       1, 169, 857          605, 023             10, 720, 752
Maintenance:
     Appropriated------........ ------------ ------------                          7, 000           22, 450            46, 500                  75, 950
     Cost....-------------------------------------                                 5, 600           18, 012            50, 531                  74,143


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954............................ $235, 567
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955------------------.................-------------------.....................................................................--- 235,567

                           7. GARZA-LITTLE ELM RESERVOIR, TEX.
   Location. The improvement is located in Denton County, Tex.,
on Elm Fork of Trinity River, 30 river miles above its confluence
with Trinity River and about 22 miles northwest of city of Dallas,
Tex.
   Existing project. The plan of improvement, a unit of the com-
prehensive plan for flood control in the Trinity River Basin, pro-
vides for the construction of a single earth-filled dam and reservoir
on Elm Fork at a site below the existing Garza Dam. This reser-
voir, designated as the Garza-Little Elm Reservoir, replaces the
Little Elm Reservoir, the modified Garza Reservoir, and the
Aubrey Reservoir. The reservoir provides a storage capacity of
526,700 acre-feet for flood control, 436,000 acre-feet for conserva-
tion, and a sedimentation reserve of 53,500 acre-feet-a total of
1,016,200 acre-feet. 'Of the total conservation storage, 415,000
acre-feet are to be provided for the city of Dallas, the incremental
cost of which is to be borne by the city.
   The estimated cost of the project (1954) is $14,529,630 for con-
struction and $8,578,436 for lands and damages, a total of $23,-
108,066, including $3,410,066 to be contributed by local interests.
The estimated cost of annual maintenance is $100,000 (1954).
   The existing project was authorized by the River and Harbor
Act approved March 2, 1945. (See H. Doc. 403, 77th Cong., 1st
sess., which contains the latest published map.)
   Local cooperation. Construction of the project is subject to
the condition that local interests (city of Dallas) contribute the
incremental cost now estimated to be $3,410,066, for which they
will receive 310,000 acre-feet of conservation storage. In addition,
the city of Dallas will convey sufficient interests over all lands
          FLOOD CONTROL-FORT WORTH, TEX., DISTRICT              611
comprising the existing reservoir and appurtenances now con-
trolled by the city of Dallas, to insure the proper operation and
management of the project, the power to control and limit develop-
ment, including improvements existing on Garza Dam, the reser-
voir lands, and appurtenances and the right to breach Garza Dam
in such manner and degree deemed necessary by the United States
for the Garza-Little Elm Reservoir, and in exchange for these
rights and privileges the city of Dallas is to receive 105,000 acre-
feet of additional conservation storage in the Garza-Little Elm
Reservoir.
   A water conservation contract with the City of Dallas was ap-
proved by the Secretary of the Army on July 16, 1953. To date,
$3,400,000 has been contributed by the city of Dallas. The remain-
ing 21,000 acre-feet of conservation storage has been made avail-
able to the city of Denton, Texas under contract approved by the
Secretary of the Army on May 24, 1954 at a cost now estimated
at $219,450.
   Operations and results during fiscal year. Regular funds:
Preparation of detailed plans and specifications and land acquisi-
tion were continued by hired labor. Relocation of highways and
railroads was continued by continuing contracts. Relocation of
utilities and reservoir clearing was continued by contract. Com-
pletion of embankment was continued and construction of outlet
works was completed by continuing contracts.
   Routine maintenance was carried on from July 1, 1953, to June
30, 1954.
   The total costs during the fiscal year for regular funds were
$2,539,033 for new work and $30,274 for maintenance, a total of
$2,569,307.
   Contributed funds: Land acquisition was continued by hired
labor, and completion of embankment was continued by continuing
contract.
   The total cost during the fiscal year for contributed funds was
$1,366,514 for new work.
   Condition at end of fiscal year. Construction of the project was
started during November 1948, and the project is scheduled to
be ready for beneficial use in November 1954. At the end of the
fiscal year the project was 73 percent complete. Engineering and
design was 94 percent, land acquisition 61 percent complete, and
construction 79 percent complete.
   Work remaining to be done to complete the project consists of
completion of land acquisition, completion of relocation of high-
ways, railroads, and utilities, completion of reservoir clearing,
completion of embankment, construction of project buildings, and
construction of recreation facilities.
   The total costs to June 30, 1954, for regular funds were
$14,963,526 for new work and $30,274 for maintenance, a total of
$14,993,800.
   The total costs to June 30, 1954, for contributed funds were
$1,933,514 for new work.
612            REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

                                          Cost and financial svmmary
                                            UNITED STATES FUNDS


                                                    Fiscal year ending June 30                                  Total to June
                                                                                                               30, 1954, includ-
                                                                                                               ing fiscal years
                                .1950           1951            1952                1953            1954         priorto 1950

New work:
    Appropriated-........    $2, 232, 300    $3, 000, 000    $3, 000, 000        $4, 179, 000   $3, 250, 000        $16, 697, 600
   Cost.-------..--              835, 645     1, 944, 965     3, 743, 079         5, 122, 523    2, 539, 032         14, 963, 526
Maintenance:
    Appropriated                               --                 -    -             -              30, 900              30, 900
    Cost--------        ------------------------                                   - -              30,274               30, 274


Other new work data:
      Unobligated balance, fiscal year ending June 30, 1954 ..-.                $1,363, 795
                                                                      _..........
                                                                            -
      Appropriated for succeeding fiscal year ending June 30, 1955........       3, 000,000
      Unobligated balances available for succeeding fiscal year ending
        June 30. 1955.--.----....        .-------------------------..
                                            .                                    4, 363, 795
      Estimated additional amount needed to be appropriated for com-
                                        -.   .....
         pletion of existing project..........-.                                       ...-....-
                                                                            . ....-......                                  400

                                            CONTRIBUTED FUNDS

                                                 Fiscal year ending June 30                                     Total to June
                                                                                                               30, 1954, includ-
                                                                                                               ing fiscal years
                                1950            1951            1952                1953            1954         priorto 1950

New work:
   Appropriated...
                --------    ------                  ------------ . $267, 000                    $2, 633, 000        $3, 400, 000
   Cost    ...----------...------------
                                .....          $500,000------------67, 000                       1,366, 514          1, 933, 514


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 -....
                                                           ..........- $1,327,849
    Unobligated balances available for succeeding fiscal year ending
        June 30, 1955 ........      .....
                            .......... ..                    ....      -------
                                                                       ..-----                           1 ,327 ,849
                                                                                     .- .......................-
      Estimated additional amount needed to be appropriated for com-
        pletion of existing project-.......-...-.-...                                                                 10 ,066

                            8.. GRAPEVINE                   RESERVOIR, TEX.
   Location. The improvement is located in Tarrant and Denton
Counties, Tex., on Denton Creek, 11.7 river miles upstream from
its confluence with the Elm Fork of the Trinity River and about
20 miles northwest of the city of Dallas, Tex.
   Existing project. The plan of improvement, a unit of the com-
prehensive plan for flood control in the Trinity River Basin, con-
sists of an earth dam approximately 12,850 feet in length, includ-
ing an uncontrolled concrete spillway 500 feet in length, located
in the left abutment. The dam has a maximum height of 137
feet above the streambed. The reservoir provides a storage
capacity of 238,250 acre-feet for flood control, 161,250 acre-feet
for conservation purposes, and a sedimentation reserve of 36,000
acre-feet. The reservoir extends 22.2 miles upstream. The esti-
mated cost of the project (1954) is $7,732,265 for construction
and $2,599,600 for lands and damages, a total of $10,331,865, in-
cluding $2,060,465 to be contributed by local interests. The esti-
mated cost of annual maintenance is $68,000 (1954).
   The existing project was authorized by the River and Harbor
Act approved March 2, 1945. (See H. Document 403, 77th Cong.,
           FLOOD CONTROL-FORT WORTH, TEX., DISTRICT              613
1st sess.) The project document contains the latest published map.
    Local cooperation. In accordance with the recommendation
contained in the project document, construction of the project is
subject to the condition that local interests (Park Cities) con-
tribute $607,000 toward the cost of the project, for which they
will receive 50,000 acre-feet of conservation storage. The project
also provided for an exchange of 75,000 acre-feet of storage be-
tween Grapevine and Lake Dallas in order to secure additional
flood control storage in the modified Lake Dallas (Garza). This
exchange is no longer required under the new Elm Fork Reservoir
plan consisting of the Grapevine and Garza-Little Elm Reservoirs;
however, the city of Dallas has requested that the project include
85,000 acre-feet of conservation storage for which the city of
Dallas will pay the incremental cost now estimated to be $1,453,465.
Negotiations with Park Cities have been consummated and a
water conservation contract drafted; to date, Park Cities have
contributed the entire amount of $607,000. A water conservation
contract with the city of Dallas was approved by the Secretary of
the Army on March 17, 1954. To date, the city of Dallas has con-
tributed $1,425,000.
    In addition, a water conservation contract with'the city of
Grapevine was approved by the Secretary of the Army September
14, 1953, for 1,250 acre-feet of conservation storage at a cost now
estimated to be $19,987. To date, the city of Grapevine has paid
the amount of $1,481.70.
    Operations and results during fiscal year. Regular funds:
Preparation of detailed plans and specifications and land acquisi-
tion were continued by hired labor.
    Routine maintenance was carried on from July 1, 1953, to June
30, 1954.
    The total costs during the fiscal year for regular funds were
$89,062 for new work and $55,357 for maintenance, a total of
$144,419.
    Contributed funds: Relocation of Denton County roads was
initiated by contract.
    Total cost during the fiscal year for contributed funds was
$84,430 for new work.
    Condition at end of fiscal year. Construction of the project
was started during December 1947, and the project was ready for
beneficial use in July 1952. At the end of the fiscal year the proj-
ect was 97 percent complete. Engineering and design was 99
percent complete, land acquisition 95 percent complete, reloca-
tions were 90 percent complete, and construction was completed.
Work remaining to be done to complete the project consists of
completion of land acquisition and completion of relocation of
county roads.
    The total costs to June 30, 1954, for regular funds were $8,209,-
351 for new work and $96,376 for maintenance, a total of
$8,305,727.
  * The total costs to June 30, 1954, for contributed funds were
$1,845,480 for new work.
614                  REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                      Cost and financial summary
                                                        UNITED STATES FUNDS


                                                                  Fiscal year ending June 30                                             Total to June
                                                                                                                                        30, 1954, includ-
                                                                                                                                        ing fiscal years
                                              1950               1951               1952               1953               1954            prior to 1950
New work:
   Appropriated- .......                 $3, 500, 000       $1, 741, 000         ___              -$715, 000         -$244, 600                 $8, 271, 400
   Cost- -----....-----.                  2, 153, 383        3, 314, 666       $1,638, 060         -475, 760              89, 062                8, 209, 351
Maintenance:
      Appropriated___     ...-----     _-             -_____
                                                         _-____                       19, 300           25, 617            53, 000                    97, 917
      Cost ---------------------------                                                19, 300           21, 719            55,357                     96,376


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954............................ $54,575
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955..................................................................           54,575


                                                         CONTRIBUTED FUNDS


                                                                   Fiscal year ending June 30                                            Total to June
                                                                                                                                        30, 1954, includ-
                                                                                                                                        ing fiscal years
                                              1950               1951               1952               1953               1954            priorto 1950

New work:
      Appropriated ---- .------------      ------------                             907, 000     ------------             125, 000              $2,032,000
      Cost---------------        $156, 250           $2, 500                        318, 764          $921, 786            84, 430               1, 845, 480


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954------...--..........---...--...... $55, 620
    Appropriated for succeeding fiscal year ending June 30, 1955-------.............. 28, 465
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955......................................................................................----------------------------------------------- -........ 84,085


                                             9. DALLAS FLOODWAY, TEX.

   Location. The floodway is located on Elm Fork and West Fork
of the Trinity River at Dallas, Tex.
   Existing project. The plan of improvement, a unit of the com-
prehensive plan for flood control in the Trinity River Basin, pro-
vides for the strengthening of the levees and the clearing of the
floodway. The estimated Federal cost of these modifications
 (1954) is $10,300,000, and the estimated cost to local interests is
$904,000, which includes $300,000 cash contribution and $604,000
for lands and damages and construction, a total of $11,204,000.
   The existing project was authorized by the River and Harbor
Act approved March 2, 1945. (See H. Doc. 403, 77th Cong., 1st
sess.) The latest published map is contained in the project docu-
ment.
   River and Harbor Act approved May 17, 1950 (Public Law 516,
81st Cong., 2d sess.) modified this project so as to provide im-
provements for interior drainage within the leveed areas.
   Local cooperation. In addition the project is authorized sub-
ject to the conditions that local interests authorize and permit
                        FLOOD CONTROL-FORT WORTH, TEX., DISTRICT                                                                               615
the modifications of the levees and floodways at Dallas, remove or
adjust all obstructing bridges and other utilities as required by
the Secretary of the Army, prevent obstructions and encroach-
ments from being placed in the floodway, construct necessary im-
provements to the interior drainage facilities for the delivery of
runoff to the pumps and sluices, and contribute $300,000 in cash
toward the construction of the Turtle Creek pressure sewer when
and as required. The required $300,000 cash contribution was re-
ceived on February 26, 1953.
   Operations and results during fiscal year. Regular funds:
   Engineering and design were continued by hired labor. Con-
struction of pumping plant A was continued by contract, and ex-
cavation of sump area A was continued by continuing contract.
Turfing of levee slopes was initiated by contract.
   Total cost during the fiscal year was $746,659 for regular funds,
all for new work.
   Contributed funds: Construction of Turtle Creek pressure sewer
was initiated by continuing contracts.
   Total cost during the fiscal year was $109,061 for contributed
funds, all for new work.
   Condition at end of fiscal year. Construction of the project was
started during January 1953, and the project is scheduled to be
ready for beneficial use in June 1957. At the end of the fiscal
year the project was 14 percent complete. Engineering and design
was 59 percent complete, and construction was 12 percent com-
plete. Work remaining to be done to complete the project consists
of completion of pumping plants and sump areas, completion of
Turtle Creek pressure sewer, completion of sluices and detention
basins, strengthening of levees, and channel excavation.
   The total cost to June 30, 1954, for regular funds was $1,361,599,
all for new work.
   The total cost to June 30, 1954, for contributed funds was
$109,061, all for new work.
                                                    Cost and financial summary
                                                      UNITED STATES FUNDS


                                                                Fiscal year ending June 30                                         Total toJune
                                                                                                                                  30, 1954, includ-
                                                                                                                                  ing fiscal years
                                            1950              1951              1952              1953              1954               prior to 1950
New work:
   Appropriated..-------------------                           61, 871          $42, 600      $1, 045, 000         $430, 000              $1, 761, 471
      -----------------
   Cost_                       $1, 610                         44, 998           74, 521          333, 900          746,659                 1, 361, 599

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954......-----......-------                                                        $303, 181
    Appropriated for succeeding fiscal year ending June 30, 1955----.........--..                                                       1,300, 000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955.......................                                                                    .....................     1, 603, 181
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project............---------------.......................................................--------------...    7,238, 529
616          REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

                                     CONTRIBUTED FUNDS


                                            Fiscal year ending June 30                     Total to June
                                                                                          30, 1954, Includ-
                                                                                          ing fiscal years
                            1950          1951         1952          1953       1954        priorto 1950

New work:
    Appropriated    ------------ ------------ ------------          $300, 000    $7,393           $307, 393
    Cost                              ---------------------------               109,061             109,061

Other new work data:
                                                                                   ..
    Unobligated balance, fiscal year ending June 30, 1954 ..............--------------- $7, 393
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955..                  -------------------------------------------------          7,393

                       10. BENBROOK RESERVOIR, TEX.
   Location. The improvement is located in Tarrant County, Tex.,
on Clear Fork of Trinity River, 15 river miles upstream from its
confluence with the West Fork of the Trinity River, about 10
miles southwest of Fort Worth, Tex.
   Existing project. The plan of improvement, a unit of the com-
prehensive plan for flood control in the Trinity River Basin, pro-
vides for the construction of an earthfill dam 9,130 feet in length,
including an uncontrolled concrete spillway 500 feet in length
located in the left abutment. The dam has a maximum height of
130 feet above the streambed. The reservoir provides a total
storage capacity of 258,600 acre-feet, of which 170,350 acre-feet
are for flood control, 72,500 acre-feet for conservation storage, and
a sedimentation reserve of 15,750 acre-feet. The reservoir ex-
tends 10.6 miles upstream. The estimated cost of the project
 (1954) is $8,619,700 for construction and $2,326,000 for lands and
damages, a total of $10,945,700. The estimated cost of annual
maintenance is $65,000 (1954):
   The existing project was authorized by the River and Harbor
Act approved March 2, 1945. (See H. Doc. 403, 77th Cong., 1st
sess., which contains the latest published maps.)
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. Operations during
the fiscal year consisted of continuation of engineering and de-
sign and land acquisition by hired labor, and completion of reloca-
tion of Tarrant County roads by contract.
   Routine maintenance was carried on from July 1, 1953, to June
30, 1954.
   Total cost during the fiscal year was $45,631 for new work and
$43,858 for maintenance, all from regular funds, a total of $89,489.
   Condition at end of fiscal year. Construction of the project was
started during May 1947, and the project was ready for beneficial
use in September 1952. At the end of the fiscal year the project
was 99 percent complete. Land acquisition was 96 percent com-
plete, and construction was 99 percent complete. Work remaining
to be done to complete the project consists of completion of land
acquisition and construction of project buildings.
   The total costs to June 30, 1954, were $10,791,520 for new work
                FLOOD CONTROL--FORT WORTH, TEX., DISTRICT                                                 617
and $82,219 for maintenance, a total of $10,873,739, all from
regular funds.
                                      Cost and financial summary

                                                 Fiscal year ending June 30                     Total to June
                                                                                                30, 1954, includ-
                                                                                                ing fiscal years
                               1950           1951         1952          1953        1954         priorto 1950

New work:
   Appropriated--------     $3, 500,000    $1, 947, 000   $339, 000   -$398, 000     $26, 400       $10,945,700
   Cost...---------------    4, 023, 098    2, 156, 384    864, 697       402, 224    45, 631        10, 791, 520
Maintenance:
   Appropriated....... ------------
                                 .   __    .-.-             19, 076       21, 000     44, 000             84,076
   Cost-----------------        ------------                18, 439       19, 922     43,858              82, 219


Other new work data:
                                                                              $150, 384
    Unobligated balance, fiscal year ending June 30, 1954 _.$......................
    Unobligated balances available for succeeding fiscal year ending June 30,
                                            --------------------------------- 150,384
       1955---------------...................................................

                        11. FORT WORTH FLOODWAY, TEX.
   Location. The floodway is located on the West Fork and Clear
Fork of the Trinity River at Fort Worth, Tex.
   Existing project. The plan of improvement, a unit of the com-
prehensive plan for flood control in the Trinity River Basin,
provides for raising and strengthening the present levees with
material excavated from the channel and floodway, clearing the
floodway of timber and debris, removing obstructions and en-
larging bridge openings by excavation in order to provide a safe
capacity in the Clear Fork portion of 60,000 second-feet and 95,000
second-feet in the West Fork portion of the floodway downstream
of the confluence of the Clear and West Forks. The estimated
Federal cost of this modification (1954) is $3,865,000. The esti-
mated cost of non-Federal participation is $5,437,650.
   The existing project was authorized by the River and Harbor
Act approved March 2, 1945. (See H. Doc. 403, 77th Cong., 1st
sess.) The project document contains the latest published map.
   Local cooperation. In addition the project is authorized subject
to the conditions that local interests authorize and permit the
modification of the levees and floodways at Forth Worth, remove
or adjust all obstructing bridges and other utilities and dams as
required by the Secretary of the Army and prevent obstructions
and encroachments from being placed in the floodway.
   Operations and results during fiscal year. Regular funds:
Engineering and design was continued by hired labor. Channel
excavation, levees, and drainage facilities were continued by con-
tinuing contract, and alteration of railroad and highway bridges
were completed by contract.
   Total cost during the fiscal year for regular funds was $982,827,
all for new work.
   Contributed funds: That portion of channel excavation being
performed for the benefit of local interests was continued by
continuing contracts.
   Total cost during the fiscal year for contributed funds was
$76,550, all for new work.
618                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Condition at end of, fiscal year. Construction of the project was
started during June 1950, and the project is scheduled to be ready
for beneficial use in June 1955. At the end of the fiscal year the
project was 76 percent complete. Engineering and design was
98 percent complete, construction was 66 percent complete, and
alterations to railroad and highway bridges were completed. Work
remaining to be done to complete the project consists of com-
pletion of channel excavation, levees, and drainage structures.
   The total cost to June 30, 1954, for regular funds was $2,993,626,
all for new work.
   The total cost to June 30, 1954, for contributed funds was
$96,550, all for new work.
                                                     Cost and financial summary
                                                       UNITED STATES FUNDS

                                                                    Fiscal year ending June 30                                         Total to June
                                                                                                                                      30, 1954, includ-
                                                                                                                                     ing fiscal years
                                             1950               1951               1952              1953               1954            priorto 1950

New work:
   Appropriated........                    $500, 000          $650, 000          $700, 000          $697, 000          $950, 000              $3, 625,000
   Cost----------------                     115,065            176,333            613, 721           992, 019           982,827                2, 993, 626

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954---............................ $439, 535
    Appropriated for succeeding fiscal year ending June 30, 1955------..............                                                                  240,000
    Unobhgated balances available for succeeding fiscal year ending June 30,
      1955............................-----.............................-----.....................-------..........................-----------------. 679,535

                                                         CONTRIBUTED FUNDS

                                                                    Fiscal year ending June 30                                         Total to June
                                                                                                                                      30, 1954, includ-
                                                                                                                                      ing fiscal years
                                             1950               1951               1952               1953              1954            prior to 1950

New work:
   Appropriated-----........ ------------ ------------............$20, 000                           $46, 550           $30, 000                  $96, 550
      Cost                                           .......-----------------       20, 000     ..... '..      .          76, 550                   96, 550


Other new work data:
        Appropriated for succeeding fiscal year ending June 30, 1955................. $94, 100
        Unobligated balances available for succeeding fiscal year ending June 30,
         1955.......................-------------...........----...............   94, 100

                    12. WHITNEY RESERVOIR, BRAZOS RIVER, TEX.
  Location. The improvement is located on the Brazos River,
Tex., about 442 miles above the mouth of the river, 5.5 miles south-
west of Whitney, Tex., and about 38 miles upstream from the city
of Waco, Tex. (See U. S. Geological Survey sheets; Waco, Cle-
burne, and Grandbury, scale 1:125,000, and Whitney, Blum, and
Morgan, scale 1:62,500.)
  Existing project. The plan of improvement consists of a con-
crete dam about 1,674 feet long at the top, including an 824-foot
           FLOOD CONTROL-FORT WORTH, TEX., DISTRICT                619
gate-controlled spillway section; 2 earthen embankment sections
totaling 8,201 feet; and saddle dikes 7,820 feet long. The top of
the dam is about 167 feet above the river bed. The reservoir
provides a controlled storage capacity of 2,017,500 acre-feet, in-
cluding 1,630,500 acre-feet of flood control storage, 131,700 acre-
feet of power storage, and 255,300 acre-feet of dead storage. A
powerhouse is located adjacent to the right bank immediately
downstream from the nonoverflow section of the dam. The ca-
pacity of the initial installation of hydroelectric generating facili-
ties is 30,000 kilowatts. The project which controls 17,656 square
miles affords substantial flood protection to the city of Waco, Tex.,
and the lower Brazos River Valley, and provides for generation
of hydroelectric power, and for other beneficial water uses.
    The estimated cost of the project (1954) is $35,623,624 for con-
struction and $5,084,376 for lands and damages, a total of
 $40,708,000.    The estimated cost of annual maintenance is
 $250,000 (1954).
    The Flood Control Act, approved August 18, 1941, approved the
existing project in accordance with the recommendation of the
Chief of Engineers in House Document 390, 76th Congress, 1st
session, which contains the latest published maps, and authorized
 $5 million for the initiation and partial accomplishment of the
project. The Flood Control Act approved December 22, 1944,
authorized completion of this project.
    Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
    Operations and results during fiscal year. Operations during
the fiscal year consisted of continuation of engineering and design
and land acquisition by hired labor. Construction of the power-
house and appurtenant equipment was completed by continuing
contract. Construction of Blum access road and bridge and con-
struction of project buildings was completed by contract.
    Routine maintenance was carried on from July 1, 1953, to June
30, 1954.
    Total costs during the fiscal year were $478,565 for new work
and $169,206 for maintenance, a total of $647,771, all from
regular funds.
    Condition at end of fiscal year. Construction of the project was
started during June 1946, and the project was ready for flood con-
trol use in December 1951. The first power was placed on the line
in June 1953. At the end of the fiscal year the project was 99
percent complete. Engineering and design was 99 percent com-
plete, land acquisition 94 percent complete, and relocations and
construction were completed. Work remaining to be done to com-
plete the project consists of completion of land acquisition and
deferred maintenance of the M.K.T. RR.
   The total costs to June 30, 1954, were $40,198,220 for new work
and $284,919 for maintenance, a total of $40,483,139, all from
regular funds.
620            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                       Cost and financial sun mary

                                                 Fiscal year ending June 30                         Total to June
                                                                                                    30, 1954, includ-
                                                                                                    ing fiscal years
                                1950           1951          1952           1953         1954         priorto 1950

New work:
   Appropriated    - -- _   $10, 500, 000 $14, 745, 000   $3, 800, 000   -$626, 000       .             $40, 707, 500
   Cost-- ....- ....--       13, 210, 796   8, 689, 432    5, 769, 419    2, 190, 850   $478, 565        40, 198, 220
Maintenance:
   Appropriated_                 _----------_-_------------41, 400          102, 983     148, 700           293, 083
   Cost...------------------------_            _------------ 38,231          77, 482     169, 206           284, 919


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 ..............-        $440, 586
    Unobligated balances available for succeeding fiscal year en'ding
      June 30, 1955          -----------...--....... ---------------------------  440, 586
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project       --------------------...-..                        500----------------

                 13. BELTON            RESERVOIR, LEON RIVER, TEX.

   Location. The improvement is located on the Leon River about
16.7 miles above the confluence of the Leon and Lampasas Rivers,
and about 3 miles north of Belton, Bell County, Tex. (See U. S.
Geological Survey base map, scale 1:500,000 and U. S. Geological
Survey, Belton Sheet, scale 1:62,500.)
   Existing project. The plan of improvement consists of a 1,300-
foot spillway, 3,806 feet of earthen embankment, and 418 feet of
dike. The top of the dam will be about 196 feet above the river-
bed. The reservoir will have a controlled storage capacity of
1,097,600 acre-feet, including 887,000 acre-feet of flood control
storage, 125,700 acre-feet of conservation storage, and 84,900
acre-feet of sedimentation storage. The project which controls
3,412 square miles will afford substantial flood protection of Leon
River Valley from Belton Dam site to confluence with Lampasas
River; Little River Valley from confluence of Leon and Lampasas
Rivers (miles 101.7) to the mouth; Brazos River Valley from
Little River (miles 315.8) to the mouth.
   The estimated cost of the project (1954) is $9,147,875 for con-
struction and $4,502,125 for lands and damages, a total of $13,650,-
000. The estimated cost of annual maintenance is $77,000 (1954).
   The Flood Control Act of 1946, approved July 24, 1946, author-
ized construction substantially in accordance with recommenda-
tions of the Chief of Engineers, as contained in his report dated
April 19, 1946 (since published as H. Doc. 88, 81st Cong., 1 sess.),
at an estimated cost of $15,500,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operation and results during fiscal year. Operations during
the fiscal year consisted of continuation of engineering and design
and land acquisition by hired labor, completion of relocation of
highways by contract, continuation of relocation of utilities by
contract, initiation of relocation of county roads by contract, com-
pletion of reservoir clearing by contract, and continuation of
completion of embankment and construction of spillway by con-
tinuing contract.
                       FLOOD CONTROL-FORT WORTH, TEX., DISTRICT                                                                           621
   Routine maintenance was carried on from July 1, 1953 to June
30, 1954.
   Total costs during the fiscal year were $2,911,184 for new work
and $23,796 for maintenance, a total of $2,934,980, all from
regular funds.
   Condition at end of fiscal year. Construction of the project was
started during June 1949, and the project was ready for bene-
ficial use in March 1954. At the end of the fiscal year the project
was 87 percent complete. Engineering and design was 97 percent
complete, land acquisition was 72 percent complete, relocations
were 93 percent complete, and construction was 95 percent com-
plete. Work remaining to complete the project consists of
completion of land acquisition, completion of relocations, com-
pletion of construction of embankment and spillway, and con-
struction of project buildings.
   The total costs to June 30, 1954, were $11,927,104 for new work
and $23,796 for maintenance, a total of $11,950,900, all from
regular funds.
                                                  Cost and financial summary

                                                               Fiscal year ending June 30                                     Total to June
                                                                                                                             30, 1954, includ-
                                                                                                                             ing fiscal years
                                         .1950              1951             1952             1953              1954           prior to 1950

New work:
   Appropriated _ _._-
                   ..                 $1, 488, 200     $2, 763, 500      $4, 000, 000     $2, 488, 000        $901, 900            $12, 291, 600
   Cost----------------                   651, 207       1,690, 200        1,913,971        4, 419, 342      2, 911, 184            11, 927, 104
Maintenance:
     Appropriated --------          ---------------               ------------            ------------.
                                                                                             ......              30, 000                  30, 000
     Cost--------         -----------------------------------------------                                        23, 796                  23, 796


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-....$.------------ $64, 138
    Appropriated for succeeding fiscal year ending June 30, 1955.....                                                                  1, 348, 100
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955....---------------------------------------1,412,238
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project ................................................................---------------------------------...     10, 300

             14. HORDS CREEK RESERVOIR, PECAN BAYOU, TEX.
  Location. The improvement is located on Hords Creek, a tribu-
tary of Pecan Bayou, about 13.5 miles west of Coleman, Tex., and
about 27.8 miles upstream from the mouth of Hords Creek. (See
U. S. Geological Survey sheets, Grosvenor and Zephyr, scale
1:62,500.)
   Existing project. The plan of improvement consists of a com-
pacted earthfill dam approximately 6,300 feet in length with a
maximum height of 91 feet and a crown of 24 feet; semiauto-
matically controlled outlet works and uncontrolled channel spill-
way; and water supply appurtenances consisting of an approach
channel, intake structure and a 24-inch water line through the dam.
   The reservoir provides a storage capacity of 25,310 acre-feet, of
which 2,860 acre-feet is allocated to dead storage, 5,780 acre-feet
to conservation storage, and 16,670 acre-feet to flood control
storage.
  The project is part of the plan of improvement on Pecan Bayou
for flood control and allied purposes. The dam controls 48 square
622            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

miles, and affords substantial flood protection to the city of Cole-
man, Tex., and to agricultural lands in the Hords Creek Valley,
and provides municipal water supply for the city of Coleman.
   The cost of the project (1954) is $2,029,734 for construction and
$250,012 for lands and damages, a total of $2,279,746, including
$105,078.69 contributed by local interests. The estimated cost of
annual maintenance is $47,000 (1954).
   The Flood Control Act approved August 18, 1941, authorized
the plan of improvement for flood control and allied purposes on
Pecan Bayou and tributaries set forth in House Document 370,
76th Congress, 1st session, and authorized $1,400,000 for initia-
tion and partial accomplishment of the plan of improvement. The
Flood Control Act approved December 22, 1944, authorized com-
pletion of the plan.
   Local cooperation. Fully complied with.
   Operations and results during fiscal year. Routine mainte-
nance was carried on from July 1, 1953, to June 30, 1954.
   Total cost during the fiscal year was $30,815 for maintenance,
all from regular funds.
   Condition at end of fiscal year. Construction of the project was
started during February 1947, and the project was ready for bene-
ficial use in June 1948. At the end of the fiscal year the project
was 100 percent complete.
   The total costs to June 30, 1954, for regular funds were
$2,174,667 for new work and $120,899 for maintenance, a total of
$2,295,566.
   The total costs to June 30, 1954, for contributed funds were
$105,079 for new work.
                                        Cost and financial summary

                                                 Fiscal year ending June 30                           Total to June
                                                                                                     30, 1954, includ-
                                                                                                     ing fiscal years
                                1950           1951           1952       1953          1954            prior to 1950

New work:
   Appropriated -------------    ....---     -$36, 190 ....               $9, 857------------..$2,             174, 667
   Cost .-------- -------       $82, 842        27, 572       $26, 890    16, 746 ------------              2, 174, 667
Maintenance:
   Appropriated      ....---     28, 500        16, 960        23, 100    22, 500      $30, 000               121, 060
   Cost--------27,                     399      18, 053        22, 430    22, 201        30, 815              120, 899

  Note. In addition, $105,079 for new work was expended from contributed funds.


   15. SAN ANGELO RESERVOIR, NORTH CONCHO RIVER, TEX.
  Location. This improvement is located on the North Concho
River, a tributary of the Concho River, about 6.6 miles above the
mouth of the North Concho River near the city of San Angelo,
Tex. (See U. S. Geological Survey base map, Texas, scale 1:500,-
000, and sheet Wall, scale 1:62,500.)
  Existing project. The plan of improvement consists of the
San Angelo Reservoir on the North Concho River upstream from
San Angelo for the control of floods and the conservation of water.
  The dam is of earth-filled type with an uncontrolled concrete
spillway located in a draw to the south of the dam. The maximum
height of the dam is 128 feet above the valley floor. The reservoir
has a total capacity of 391,500 acre-feet, of which 33,900 acre-feet
                FLOOD CONTROL-FORT WORTH, TEX., DISTRICT                                                      623
is allocated to sedimentation storage, 80,400 acre-feet to conserva-
tion storage, and 277,200 acre-feet to flood control storage.
   The reservoir provides substantial flood protection to the flood
plains of the Concho and lower Colorado Rivers and to the city of
San Angelo.
   The estimated cost of the project (1954) is $11,238,043 for con-
struction and $3,463,357 for lands and damages, a total of
$14,701,400. The estimated cost of annual maintenance is $62,000
 (1954).
   The Flood Control Act approved August 18, 1941, authorized the
plan of improvement for flood control on the North Concho River,
Tex., as set forth in House Document 315, 76th Congress, 1st ses-
sion, and authorized $2 million for the initiation and partial ac-
complishment of the project. The Flood Control Act approved
December 22, 1944, authorized completion of this project.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies to the San Angelo Reservoir.
   A water conservation contract with the Upper Colorado River
Authority for conservation storage in the reservoir was approved
by the Secretary of the Army on October 11, 1948, at an estimated
cost of $755,000. To date the Upper Colorado River Authority has
made payments in the amount of $229,688.76.
    Operations and results during fiscal year. Operations during
the fiscal year consisted of construction of a protective fence at
the outlet works, construction of a government boat dock by con-
tract, and continuation of land acquisition by hired labor.
    Routine maintenance was carried on from July 1, 1953, to June
30, 1954.
    Total cost during the fiscal year was $150,809, all from regular
funds, of which $104,888 was for new work and $45,921 for
maintenance.
    Condition at end of fiscal year. The existing project was 99
percent complete. Construction of the project commenced during
May 1947. The project was ready for beneficial use in February
1952. Work remaining to be done to complete the project consists
of completion of land acquisition.
    Total cost under the existing project to June 30, 1954, all from
regular funds, was $14,749,287, of which $14,656,033 was for new
work and $93,254 for maintenance.


                                        Cost and financial summary

                                                   Fiscal year ending June 30                         Total to June
                                                                                                     30, 1954, includ-
                                                                                                     ing fiscal years
                                 1950           1951           1952         1953          1954         prior to 1950
New work:
   Appropriated....----      $3, 900,000    $2, 500, 000   $1, 200, 000   -$28,000     -$115, 700        $14, 701, 400
   Cost----------------       5, 260, 775    4, 616, 781       887, 949     210, 772      104, 888        14, 656, 033
Maintenance:
   Appropriated ..-------------.........---- ......------------ 28, 700      24, 950       41, 658             95, 308
   Cost...........      ------------........................    25, 440      21, 893       45, 921             93,254


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954.-..--............ $45, 016
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955 ........-..-.-
                  . ...... ... ... .............-                             45,016
624             REPORT OF CHIEF OF ENGINEERS, U.                           S. ARMY,        1954


          16.   CANYON          RESERVOIR,             GUADALUPE             RIVER,              TEX.
   Location. The improvement is located in Comal County, Tex.,
on the Guadalupe River, 303 miles above its mouth, and about 12
miles northwest of New Braunfels, Tex.
   Existing project. The plan of improvement provides for the
construction of an earthfill dam 6,990 feet long, consisting of a
main dam 4,540 feet long, a gate-controlled concrete gravity saddle
spillway section 896 feet long, and dikes totaling 1,554 feet. Maxi-
mum height of dam is 237 feet above the riverbed. The reservoir
will have a total storage capacity of 1,144,800 acre-feet, includ-
ing 337,700 acre-feet of flood control storage, 445,100 acre-feet
for conservation storage and possible future power development,
and 362,000 acre-feet of dead storage. The power installation will
have a total installed capacity of 45,000 kilowatts. The dam will
control 1,425 square miles.
   The estimated cost of the project (1954) is $30,590,000 for con-
struction and $2,210,000 for lands and damages, a total of $32,-
800,000.
   The existing project was authorized by the River and Harbor
Act approved March 2, 1945 (H. Doc. 247, 76th Cong., 1st sess.),
subject to the following provision:
  That whenever any power project, not under Federal license, is benefited
by the Canyon Reservoir project, the Federal Power Commission after notice
to the owner or owners of such unlicensed project and after opportunity for
hearing, shall determine and fix a reasonable and equitable annual charge to
be paid to the United States, on account of such benefits by said owner or
owners or other recipients of such benefits.
   The latest published map is in the project document.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. Operations during
the fiscal year consisted of completion of design memorandum on
power development and a review of preliminary investigations and
engineering studies with a view to elimination of power develop-
ment.
   Total cost during the fiscal year was $1,238, all for new work
from regular funds by hired labor.
   Condition at end of fiscal year. The existing project was 2 per-
cent complete. Engineering and design was 26 percent complete.
  Total cost under the existing project, all for new work from
regular funds, was $558,828.
                                       Cost and financial summary

                                              Fiscal year ending June 30                          Total to June
                                                                                                  30, 1954, includ-
                                                                                                  ing fiscal years
                                1950        1951        1952        1953            1954            prior to 1950

New work:
    Appropriated --------..... $150, 000    $56, 100     -$872       $3, 000 ............                 $558, 828
    Cost.----------------       150,122     104, 992      5,121       1, 762           $1, 238             558, 828


Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project_................................................ $32,241,172
                 FLOOD CONTROL--FORT WORTH, TEX., DISTRICT                                                       625
                  17.    INACTIVE             FLOOD          CONTROL PROJECTS

                                                          For last        Cost to June 30, 1954           Estimated
                                                         full report                                        amount
                Name of project                             see                                             required
                                                          annual           Con-          Operation             to
                                                          report         struction          and            complete
                                                           for-                         maintenance
                              1
1. Brady, Brady Creek, Tex. ------------------
                             2                _             1949         $72,077. 61 ------------        $1, 872, 922.39
2. Eastland, Leon River, Tex. ---___ --- ____-              1948         ---------------------               193, 000. 00
3. Lake Brownwood Reservoir, Pecan Bayou,                   1952          190, 444.61-15,                    009, 555. 39
    Tex.5

  1 Five year limitation for local assurances expired Feb. 1, 1954. This project will be deleted in future
submissions of the annual report.
  2 No appropriations to date.
  s Awaiting Congressional action on project modifications.


                              18. GENERAL INVESTIGATIONS
   Examinations and surveys. The cost of work performed on
authorized reports during the fiscal year amounted to $26,160.
   The uncosted balance of $801 at the end of the fiscal year, plus
an allotment of $10,000 will be applied to continuation of studies
on Richland, Chambers, and Cedar Creeks.
   Collection and study of basic data. The cost of work on collec-
tion and study of basic data during the fiscal year amounted to
$4,000. Work performed consisted of stream gaging, collecting
rain gage data, storm studies, sedimentation studies, flood emer-
gency studies, reservoir regulation studies, hydrologic studies, and
flood investigations.
   An allotment of $27,000 can be profitably expended for work
under this category during fiscal year 1955.
                19. INSPECTION                  OF COMPLETED PROJECTS
  Inspection of completed local flood protection projects is made
periodically in compliance with Section 208.10 of Title 33, Code of
Federal Regulations, which contains regulations for the operation
and maintenance of local flood protection works approved by the
Secretary of the Army in accordance with authority contained in
Section 3 of the Flood Control Act of June 22, 1936.
  Floodways and levees of the Dallas Floodway, Fort Worth Flood-
way, and Pleasanton Floodway, as well as 28 levee districts, have
been inspected during the fiscal year.
  The cost of work under this heading during fiscal year 1954 was
$2,323.
                                          Cost and fnancial summary

                                                 Fiscal year ending June 30                             Total to June
                                                                                                      30, 1954, includ-
                                                                                                      ing fiscal years
                               1950            1951           1952           1953           1954        prior to 1950

Maintenance:
   Appropriated ......   __       -_.......    $3, 000         $3, 900        $2, 500       $2, 300             $11, 700
   Cost                                            379          6, 521         2, 356        2, 323              11, 579
626      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

            20. EMERGENCY FLOOD CONTROL WORK
   Small flood control projects not specifically authorized by Con-
gress under authority of section 205 of the Flood Control Act ap-
proved June 30, 1948, as amended.
    Pursuant to this authorization allotments totaling $279,451
have been made in fiscal years 1951-1954, inclusive, covering four
projects, namely: flood protection along the Atascosa River at
Pleasanton, Texas; flood protection along San Diego Creek at Alice,
Texas; flood protection along Tranquitas Creek at Kingsville,
Texas; and flood protection along Paesta Creek at Beeville, Texas.
    Pleasanton: The project is located at Pleasanton, Atascosa
County, Texas, on the Atascosa River, approximately 56 miles
above its confluence with the Nueces River and 33 miles south of
San Antonio, Texas, and provides for channel enlargement along
the Atascosa River for a distance of 13,385 feet, channel enlarge-
ment along Bonita Creek for a distance of 3,900 feet, clearing
the channel of the Atascosa River of brush and small growing
timber from river mile 53.0 to river mile 57.1, an earth levee 1,970
feet long along the left bank of Bonita Creek, and scour protec-
tion in the excavated channel of the Atascosa River at the Missouri
Pacific Railroad bridge, U. S. Highway 281 bridge, and the County
highway bridge. The project has been completed and was ac-
cepted by the city of Pleasanton on September 1, 1953.
   Total cost during the fiscal year was $296. The total cost under
the existing project to June 30, 1954, was $123,801, all for new
work from regular funds.
   San Diego Creek: The project is located at Alice, Jim Wells
County, Texas, on San Diego Creek. The city of Alice is approxi-
mately 40 miles west of Corpus Christi, Texas, and 120 miles south
of San Antonio, Texas. The proposed project provides for chan-
nel enlargement along San Diego Creek for a distance of 17,251
feet, construction of a levee 18,019 feet long, and one section of
steel sheet pile wall with concrete cap totaling 227 feet in length,
both located along the right bank of the San Diego Creek and
generally parallel to the improved channel. The estimated Federal
cost for construction (1954) is $145,650. The estimated cost to
local interests includes $28,120 for lands and damages and a cash
contribution of $12,000, a total of $40,120.
   The total cost during the fiscal year was $12,154. The total cost
under the existing project to June 30, 1954, was $19,154, all for
new work from regular funds. Allotments for the Alice project
totaled $145,650 to June 30, 1954.
   Tranquitas Creek: The proposed project is located at Kingsville,
Kleberg County, Texas, on Tranquitas Creek. The city of Kings-
ville is located about 34 miles southwest of Corpus Christi, Texas,
and about 140 miles southeast of San Antonio, Texas. The pro-
posed project provides for channel enlargement along Tranquitas
Creek for a distance of about 12,600 feet, clearing about 150 acres
along Tranquitas Creek channel from its mouth upstream about
31,500 feet, and channel paving under two highway bridges and
                  FLOOD CONTROL-FORT WORTH, TEX., DISTRICT                                                 627
one railroad bridge. The estimated Federal cost for construction
 (1954) is $111,000. The cost to local interests, including lands
and damages and enlargement of one highway bridge opening, is
estimated at $51,000. The total cost during the fiscal year was
$4,235. The total cost under the existing project to June 30, 1954,
was $4,235, all for new work from regular funds. Allotments for
the Kingsville project totaled $7,000 to June 30, 1954.
   Paesta Creek: The proposed project is located at Beeville, Bee
County, Texas, on Paesta Creek. The city of Beeville is located
about 50 miles northwest of Corpus Christi, Texas, and about 84
miles southeast of San Antonio, Texas. Surveys and studies were
initiated but since Federal responsibility was not involved and a
project could not be developed under Section 212, preliminary in-
vestigations were accordingly discontinued.
   Total cost during the fiscal year was $2,160, and the total cost
under the existing project to June 30, 1954, was $2,160. Allot-
ments for the Beeville project totaled $3,000 to June 30, 1954.
                                       Cost and financial summary

                                               Fiscal year ending June 30                         Total to June
                                                                                                 30, 1954, includ-
                                1950          1951          1952         1953         1954        prior to 1950

New work:
    Appropriated--..--_--------------        $93, 700 ---               $38, 100     $147, 651           $279, 451
    Cost-----------------------                11, 849      $10, 411     108, 246      18,845             149,350

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954.....------------........... 8129, 741
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955...............-----------                                       ----------. 129, 741
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project.......-----------.... ----.......................
                                                                            ------  ------------........ 104, 000

21. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
  Flood Control Emergencies--Repair and Flood Fighting and
rescue work (Section 210 of the 1950 Flood Control Act and sup-
plemental authorizations).
  The cost of work performed during the fiscal year amounted to
$63,810.
  Operations consisted of completing repairs on breached sections
of levees in three levee districts, and flood fighting on the Sabine
River.
                                       Cost and financial summary

                                               Fiscal year ending June 30                         Total to June
                                                                                                 30, 1954, includ-
                                1950
                                                                                                 ing fscal years
                                              1951          1952         1953         1954        prior to 1950
Maintenance:
    Appropriated-........      $134,923       $10, 722      $48, 920      $9, 542    $197, 200           $608, 307
    Cost ----------------       144, 044      112, 344       15, 970      31,080       63,810             461, 585
FLOOD CONTROL IMPROVEMENTS IN THE ALBUQUERQUE,
                N. MEX., DISTRICT

   The district comprises the watershed of the Canadian River and
tributaries entering the river west of the Texas-New Mexico State
line; the watershed of the Arkansas River and tributaries entering
the river west of and including Walnut Creek, Kans., the watershed
of the Rio Grande and tributaries entering the river west of and
including the Pecos River and its tributaries; and the watershed of
the Mimbres River and its tributaries in New Mexico.
                                                       IMPROVEMENTS

                  Flood control                                           Flood control-Continued
                                                         Page                                                     Page
1. Pueblo, Arkansas River, Colo_.                         629  6. Rio Grande Floodway, Rio
2. John Martin Reservoir, Arkan-                                    Grande, N. Mex...              ............   636
     sas River, Colo. (formerly                                7. Inactive flood control projects..               638
     Caddoa Reservoir)            ---....------.....      630 8. General investigations--............             638
3. Conchas Reservoir, Canadian                                 9. Inspection of completed flood
     River, near Tucumcari, N.                                      control works..........................       638
     Mex-........................................         632 10. Scheduling of flood control res-
4. Chamita Reservoir Project, Rio                                   ervoir operations....................         639
     Chama, N. Mex.....................                   633 11. Flood control work under special
5. Jemez     Canyon              Reservoir,                         authorizations.............__..........       639
     Jemez Creek, N. Mex-----......--....                 635

                         1. PUEBLO, ARKANSAS RIVER, COLO.
   Location. The project is located in the city of Pueblo, Pueblo
County, Colo., on the Arkansas River, about 171 miles downstream
from its source and about 1,279 river miles upstream from its
mouth. (See U. S. Geological Survey Maps, Pueblo, Colo., quad-
rangle, 1:125,000.)
   Existing project. The plan of improvement provides additional
local flood protection for the area subject to inundation by back-
water at Pueblo, Colo., by the construction of a levee extending
from the north abutment of the Santa Fe Avenue Bridge to high
ground, adjacent to the Missouri Pacific Railroad right-of-way, the
levee to have a 10-foot crown width and a 4-inch filter blanket and
10 inches of riprap cover on the river side; and a drainage struc-
ture with flap gates under the levee. The estimated Federal cost
of construction is $201,958 and the estimated cost to local interests
is $4,950 for lands and damages, a total of $206,908 (1954).
   The existing project was authorized by the Flood Control Act
approved May 17, 1950. (See H. Doc. 327, 81st Cong., 1st sess.)
   Local cooperation. In addition to the usual requirements, local
interests are required to protect the flood carrying capacity of the
floodway, between river miles 1,276.5 and 1,281.5, from future
encroachments or obstructions and preserve and maintain un-
impaired the capacity of the old channel of the Arkansas River
between the Southern Colorado Power Co.'s dam and the proposed
levee crossing for the purpose of handling internal drainage.

                                                                                                      629
630         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Operations and results during fiscal year. Construction of the
project by contract was completed during fiscal year 1953. The
costs during the fiscal year were $63.
  Condition at end of fiscal year. The construction of the project
which was initiated on May 1, 1952, was completed on November
11, 1952. Maintenance of the project has been assumed by local
interests in accordance with the requirements of the authorizing
act. Total costs under the existing project to June 30, 1954, were
$201,958, all for new work.
                                   Cost and financial summary

                                         Fiscal year ending June 30                  Total to June
                                                                                     30, 1954, includ-
                                                                                     ing fiscal years
                            1950        1951       1952         1953       1954       priorto 1950
New work:
   Appropriated--------.......-............        217, 500   -$15, 171    -$371             201, 958
   Cost--------------- _--------._-.-----112,          001      $89, 894       $63           201, 958



      2. JOHN     MARTIN RESERVOIR, ARKANSAS RIVER,                                  COLO.
                    (FORMERLY CADDOA RESERVOIR)
   Location. John Martin Reservoir is located on the Arkansas
River 1,155 miles upstream from its mouth, 295 miles downstream
from its source, and in Bent County, about 18 miles upstream from
the city of Lamar, Colo. ( See U. S. Geological Survey maps for
Lamar and Las Animas (Colo.) quadrangles, scale 1:125,000.)
   Existing project. The existing project consists of a dam and
reservoir for flood control and water conservation in Colorado and
Kansas. The dam is a concrete and earth fill structure approxi-
mately 130 feet high with an overflow gated spillway 1,174 feet
long. The earth section extending to the abutments flanks the
concrete gravity section in the valley, and earth dikes on each
abutment in continuation of the earth section extend to high
ground, making the overall length of the structure approximately
2.6 miles. The reservoir, which controls 18,933 square miles, is
one unit of a comprehensive reservoir plan for flood control in the
Arkansas River Basin, has a storage capacity of 279,200 acre-feet
for flood control, and 383,700 acre-feet for conservation, a total of
662,900 acre-feet.
   The estimated cost is $11,591,400 for construction, $3,546,500
for lands ahd damages, a total of $15,137,900 (1954). The current
estimated annual cost of maintenance and operation is $88,000
 (1954).
   The existing project was authorized by the Flood Control Act
approved June 22, 1936, under the title "Caddoa Reservoir, near
Lamar in Colorado." (See H. Doc. 308, 74th Cong., 1st sess., which
contains the latest published maps.) The War Department Civil
Appropriation Act approved June 24, 1940, provided that from and
after the approval of that act, the Caddoa Reservoir project for
flood control and water conservation in Colorado and Kansas should
              FLOOD CONTROL-ALBUQUERQUE, N. MEX., DISTRICT                                                      631
be known and designated on the public records as the John Martin
Reservoir project.
    Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
    Operations and results during fiscal year. Construction of a
maintenance building was authorized this fiscal year from new
works funds. This building had previously been budgeted as an
:item of rehabilitation under Operation and Maintenance, General.
Plans and specifications for the Maintenance Building were com-
pleted in May 1954 and construction is scheduled to start imme-
diately after July 1, 1954.
    Regulation of the conservation storage in the reservoir was con-
tinued under the rules and regulations of the Arkansas River Com-
pact. The reservoir was empty at the beginning of the fiscal year
and remained empty until July 12, 1953. Storage began on that
date and a maximum elevation of 3,791.94 was reached on July 14,
1953. The reservoir was empty again during the following periods:
July 30 to August 2, August 5 to August 17, and August 30 to
November 23, 1953, and from April 15, 1954, to the end of the
fiscal year. During these periods all river flow was passed through
the reservoir. Total releases for the fiscal year were 119,869 acre-
feet, all of which were for irrigation. Irrigation releases ended
November 23, 1953, and resumed April 7, 1954.
    The costs during the fiscal year were $7,187 for new work and
 $104,167 for maintenance.
    Condition at the end of fiscal year. The existing project is com-
plete. The completed dam and appurtenances have been in opera-
tion about 51/ years. The construction of the maintenance build-
ing, which was authorized this fiscal year from new work funds,
will be started immediately after July 1, 1954.
    The total costs to the end of the fiscal year under the existing
project were $15,017,499 for new work, $860,743 for maintenance.
In addition, costs from Emergency Relief funds for new work have
been $59,977.15.
                                       Cost and financial summary

                                                    Fiscal year ending June 30                       Total to June
                                                                                                    30, 1954, includ-
                                                                                                    ing fiscal years
                               1950               1951         1952        1953       1954           priorto 1950

New work:
      Appropriated.. __...    $100, 000 ...................                           $67, 900      * $15, 077, 922
                                                                                      $....-$----1----
   Cost.-----------------       19, 999           $99, 919     $3, 459      $2, 351    15, 855     * 1 15, 016, 167
Maintenance:
      Appropriated --------     70, 000             73, 500     99, 000    135, 700       90, 766              892, 266
          -- --------
      Costp          --        100, 139             66, 656    106, 869     92, 860   2   96, 253          2   852, 829


   * In addition $59,977 were expended from Emergency Relief Funds for new work.
  I In addition $1,332 costs are recorded in general ledger account 114-Prepayments for accrued cost dis-
tributions.
   2 In addition $7,914 costs are recorded in general ledger account 114-Prepayments for accrued cost dis-
tributions.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 ................-................ $960
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955.................................----.............................                 960
632      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

3. CONCHAS RESERVOIR, CANADIAN          RIVER, NEAR TUCUMCARI,
                        N. MEX.

   Location. The dam is located in San Miguel County, N. Mex.,
on the Canadian River approximately one-fourth mile downstream
from the confluence of the Canadian and Conchas Rivers. It is
approximately 30 miles northwest of Tucumcari, N. Mex., and 743
miles upstream from the mouth of the Canadian River. The Ca-
nadian River has a total length of approximately 906 miles, rises
in the northeastern part of New Mexico, and flows south and east
to the Arkansas River in the vicinity of Webbers Falls, Okla. (See
U. S. Geological Survey State map of New Mexico, scale 1:500,000,
and U. S. Geological Survey topographic map, Tucumcari quad-
rangle; scale 1:125,000.)
   Existing project. The existing project consists of a flood con-
trol dam and reservoir which will also be used for irrigation and
water supply purposes. The dam consists of a concrete gravity
main section 235 feet high and 1,250 feet long located in the Ca-
nadian River Canyon, together with earth dikes on each side having
an overall length of about 3.7 miles. The main section contains
conduits located in its base capable of releasing water to maintain
low water flow and for drainage of the reservoir, and an overflow
spillway 300 feet in length. The earth dikes are of varying heights
up to 100 feet and the north dike contains a concrete ogee type
emergency spillway 3,000 feet long. The project involved about
836,000 cubic yards of concrete, 3,600,000 cubic yards of fill, and
1,300,000 cubic yards of excavation. The reservoir has a gross
storage capacity of 566,000 acre-feet, consisting of 279,000 acre-
feet for water conservation and irrigation, 196,000 acre-feet for
flood control, and 91,000 acre-feet dead storage. The dam controls
7,409 square miles of drainage area. The Federal cost was $15,-
488,908.56, including $2,279,325.70, the cost of initiating construc-
tion of the project under authority of the Emergency Relief
Appropriation Act .of 1935. The estimated annual cost of main-
tenance and operation is $86,000 (1954).
   The project is based on the report of the Canadian River, N.
Mex., Tex., and Okla., dated June 1, 1931, made in compliance with
House Document 308, 69th Congress, 1st session, and approved by
the President, July 29, 1935, under the provisions of the Emer-
gency Relief Appropriation Act of 1935, and adopted by Congress
in the Flood Control Act of June 22, 1936 (H. Doc. 308, 74th Cong.,
1st sess.).
   Operations and results during fiscal year. Operation of the
reservoir was continued. The structures were maintained in a
serviceable condition.
   The reservoir reached a maximum elevation of 4,174.90 on Sep-
tember 3, 1953, and a minimum elevation of 4,162.07 on July 5,
1953. Irrigation releases ended December 10, 1953, and resumed
March 8, 1954. Total releases for the fiscal year were 79,179 acre-
feet, of which 72,142 acre-feet were for irrigation, 43 acre-feet for
power production, 354 acre-feet conduit releases and 6,640 acre-
feet miscellaneous losses. 2,520 acre-feet were released to Bell
               FLOOD CONTROL-ALBUQUERQUE, N. MEX., DISTRICT                                                   633
Ranch for irrigation and 69,622 acre-feet to the canal of the Tu-
cumcari irrigation project, under development by the United States
Bureau of Reclamation.
   The costs for the year were $91,650 for maintenance.
   Condition at end of fiscal year. The existing project was essen-
tially completed in 1940. The reservoir and appurtenances were
in good condition and in operation at the end of the fiscal year.
Irrigation of some lands under the project was begun on November
24, 1945. The costs to the end of the fiscal year from reguhar funds
were $12,339,605 for new work, and $1,075,307 for maintenance.
   The costs to the end of the fiscal year from Emergency Relief
funds were $869,977.75 for new work.
   The total costs to the end of the fiscal year for all funds from
departmental appropriations were $13,209,583 for new work and
$1,075,307 for maintenance. In addition, the costs for work accom-
plished in initiating the project under the provisions of the Emer-
gency Relief Appropriation Act of 1935 were $2,279,325.70.
                                        Cost and financial summary

                                              Fiscal year ending June 30                           Total to June
                                                                                                   30, 1954, includ-
                                                                                                   ing fiscal years
                                 1950        1951         1952         1953            1954          prior to 1950

New work:
   Appropriated._______           21, 209                                         _                    * 13, 209, 583
   Cost_______________            15, 459     15, 085       4, 456       _        __          _        *13, 209, 583
Maintenance:
    Appropriated        __        159, 600    62, 500      87, 695      86, 000          91, 100          1, 121, 774
    Cost                 _----------------
                                  139, 906   189, 423      97, 369      47, 348        1 85, 640        1 1, 069, 297

   * Includes $3,492,696, Maintenance and Improvement funds and $869,978 Emergency Relief funds, but
does not include $2,279,326, the cost of initiating the project under authority of the Emergency Relief Appro-
priation Act of 1935.
   1In addition $6,010 costs are recorded in general ledger account 114-Prepayments for accrued cost dis-
tributions.

      4. CHAMITA            RESERVOIR PROJECT,                       RIO CHAMA, N. MEX.
   Location. The Chamita Reservoir project is one unit of the
flood control phase of the comprehensive plan for the Rio Grande
and tributaries, New Mexico. The authorized project provides for
the construction of only one dam, a high dam, to be located at river
mile 5 in Rio Arriba County about 6 miles northwest of Espanola,
N. Mex.; however, on the basis of further studies and investiga-
tions, a substitute plan has been developed which is composed of a
combination of two dams, one of which is a low dam at the author-
ized Chamita site and the other a high dam at a site near Abiquiu,
N. Mex. Both dam sites are located in Rio Arriba County, N. Mex.,
on Rio Chama, a tributary of the Rio Grande. Low Chamita Dam
is approximately 5 miles upstream from the confluence of Rio
Chama and Rio Grande, and is about 6 miles northwest of Espanola,
N. Mex. Abiquiu dam site, located near the town of Abiquiu, N.
Mex., is about 25 miles upstream from the Chamita dam site. The
Abiquiu Dam will control 2,147 square miles and the Chamita Dam
979 square miles. (See U.S. Geological Survey map for plan and
profile of Rio Chama, N. Mex., from mouth to mile 103, sheet 1.)
The substitute plan is considered the most economical and practical
plan for protecting the Espanola and Middle Valleys of Rio Grande
634      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

from sediment and floods originating in the Rio Chama watershed.
It will also provide the same degree of protection as the authorized
plan and will offer several distinct advantages, including a very
substantial saving in first cost.
   Existing project. The plan of improvement provides for con-
struction of two dams for flood control and sediment storage as an
aid in the prevention of flood damages and river sedimentation in
Espanola and Middle Valleys of Rio Grande in New Mexico.
   Abiqutu Dam is an earthfill dam about 1,500 feet in length,
rising 318 feet above streambed, with a combination type outlet
works. This outlet works provides for controlled and uncontrolled
releases of flood waters. The controlled outlet consists of a 12-foot-
diameter conduit with regulating gates, and the uncontrolled out-
let consists of a 10-foot-diameter inclined tunnel which discharges
into the 12-foot-diameter tunnel below the regulation gates. The
inlet to the uncontrolled outlet would be provided with a concrete
ogee weir 16 feet high which limits the flood control and sediment
storage capacity of the reservoir to 562,000 acre-feet. After com-
pletion of Low Chamita Dam, the concrete weir at the inlet to the
uncontrolled outlet would be removed which would reduce the flood
and sediment storage capacity of the reservoir to 449,000 acre-feet
and limit the combined capacity of Abiquiu and Low Chamita Dams
to 700,000 acre-feet for flood and sediment storage. An uncon-
trolled spillway with bottom width of 25 feet would be located in a
natural saddle about 1 mile north of the left abutment. The reser-
voir will have a capacity of 1,211,000 acre-feet at spillway crest.
The uncontrolled outlet tunnel was provided in order to limit the
reservoir storage to the required flood and sediment control capaci-
ties pursuant to the provisions of the authorizing legislation and
to satisfy the interests of the State of Texas under the Rio Grande
Compact.
   Low Chamita Dam is an earthfill dam about 5,700 feet in length,
rising to a height of 148 feet above streambed, with an offchannel
uncontrolled, concrete-lined spillway, and an outlet works com-
prised of a gate structure, stilling basin, and a flood control conduit
13 feet in diameter. The reservoir will have a storage capacity at
spillway crest of 251,000 acre-feet for flood control and sediment
storage.
   The estimated costs are as follows:
   Abiquiu Dam: $12,350,000 for construction and $250,000 for
lands and damages, a total of $12,600,000 (1954).
   Low Chamita Dam: $13,743,000 for construction and $957,000
for lands and damages, a total of $14,700,000 (1954).
   Total project cost (substitute plan-Abiquiu and Low Chamita
Dams combined): $26,093,000 for construction and $1,207,000 for
lands and damages, a total of $27,300,000 (1954).
   The existing project was authorized by the Flood Control Acts
approved June 30, 1948, and May 17, 1950.
   Operationsand results during fiscal year. Engineering studies
were continued and subsurface explorations were initiated for
Abiquiu Dam. The costs during the fiscal year were $124,546 for
new work.
               FLOOD CONTROL-ALBUQUERQUE,                             N. MEX., DISTRICT                   635
  Condition at the end of the fiscal year. Planning is 38 percent
complete. Total costs under the existing project to June 30, 1954,
were $436,292 all for new work.
                                          Cost and financial summary

                                                Fiscal year ending June 30                      Total to June
                                                                                                30, 1954, includ-
                                                                                                ing fiscal years
                                   1950        1951        1952         1953        1954         priorto 1950

New work:
    Appropriated--------........   $75, 000   $127, 000    $56, 100     $55, 000   $132, 000           $445, 100
    Cost-----------------           36,695     112, 202    109, 203      53, 646   * 118, 153          * 429, 899

   * In addition $6,393 costs are recorded in general ledger account 114-Prepayments for accrued cost dis-
tributions.

Other new work data:
                                                                            $198
    Unobligated balance, fiscal year ending June 30, 1954------.................---...
    Appropriated for succeeding fiscal year ending June 30, 1955------............
                                                                         175,000
    Unobligated balances available for succeeding fiscal year ending
                                                                         175, 198
      June 30, 1955-----------------------------------------..................
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project.....................-------------------.........
                                                                     26, 679,900

5. JEMEZ CANYON DAM AND RESERVOIR, JEMEZ CREEK, N. MEX.
   Location. The project is located in Sandoval County, N. Mex.,
on Jemez Creek approximately 2 miles upstream from the conflu-
ence of Jemez Creek and Rio Grande, about 5 miles northwest of
Bernalillo, New Mexico. (See U. S. Geological Survey map for
Bernalillo quadrangle, scale 1:125,000.)
   Existing project. The plan of improvement consists of a dam
and reservoir for flood control and sediment storage. The dam is
an earthfill dam rising 136 feet above the stream bed with an
ungated saddle spillway. The dam has a length of 780 feet for the
earthfill section plus an additional 500 feet for the spillway. The
reservoir, which controls 1,034 square miles, is one unit of the
flood control phase of a comprehensive plan for Rio Grande and
tributaries, New Mexico, will have a capacity for flood control and
for sediment storage of 120,000 acre-feet, of which it is estimated
that 73,000 acre-feet will be available for the storage of flood-
waters at the end of 50 years.
   The estimated costs are $4,048,700 for construction and $6,900
for lands and damages, a total of $4,055,600 (1954).
   The estimated cost of annual maintenance is $33,000 (1954).
   The existing project was authorized by the Flood Control Acts
approved June 30, 1948, and May 17, 1950.
   Operations and results during fiscal year. Construction of the
dam and spillway, the Santa Ana Pueblo protection works and pub-
lic use facilities by contract was completed. The construction of
additional facilities and structural repairs by contract was initiated
on February 15, 1954, and was completed on May 5, 1954. Manuals
for operation and maintenance and reservoir regulation were pre-
pared. All land acquisition was completed.
   Since the project was completed and placed in operation in Oc-
tober 1953, the sluice gates have been kept open. During the fall
and winter months, the flow was very low and of no consequence.
636           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

There was no occasion for flood control regulation. The maximum
peak flow through the dam during the snow melt runoff was about
1,000 cubic feet per second.
   The costs during the fiscal year were $563,952 for new work and
413,678 for maintenance.
   Condition at the end of the fiscal year. Construction of the
project was initiated on May 4, 1950, and was completed on October
7, 1953.
   Total costs under the existing project to the end of the fiscal year
were $4,050,285 for new work and $13,678 for maintenance.
                                     Cost and financial summary

                                            Fiscal year ending June 30                              Total to June
                                                                                                   30, 1954, includ-
                                                                                                   ing fiscal years
                              1950         1951         1952            1953         1954            priorto 1950

New work:
   Appropriated ....... $750,000 $500, 000             $900, 000   $2, 044, 627   -$139,    000         $4, 055, 627
              -
   Cost ....... _    - 236,384             933,985      781, 082    1, 534, 882     1563, 723           14, 050, 056
Maintenance:
   Appropriated   --                                         -.     -    -             15, 434               15, 434
   Cost - - . . . . . . . .--                                                        2 12, 080             2 12, 080

   1 In addition $229 costs are recorded in general ledger account 114-Prepayments for accrued cost dis-
tributions.
   2 In addition $1,598 costs are recorded in general ledger account 114-Prepayments for accrued cost dis*
tributions.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954                     $1, 116
                                                                         ......
                                                               .....................
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955----....---------.................................................   1,116

         6. RIO      GRANDE          FLOODWAY,            RIO      GRANDE,                 N.     MEX.
    Location. The project is located on the Rio Grande in New
Mexico. It covers the section of the river commencing near Truth
or Consequences (formerly Hot Springs) and going upstream to
the lower end of the Rio Grande Canyon, approximately 14 miles
upstream from Espanola.
    Existing project. The plan of improvement provides for flood
protection and major drainage improvements by channel rectifica-
tion and levee enlargement and construction as a joint undertaking
by the Bureau of Reclamation and the Corps of Engineers between
river miles 123 and 394 (river mile 0 being at the intersection of
the New Mexico-Texas State line with the international boundary
at El Paso). The portion to be accomplished by the Corps of Engi-
neers will consist of levee enlargement and construction and bank
protection work where necessary to protect levees. Levees con-
structed by local interests now exist through the reach of the river
involved, but are not uniform as to grade, section or standard of
construction and in many places are threatened by the meandering
river channel. These levees will be modified and supplemented by
additional levees where required. The levees as modified or con-
:structed will have a standard section with a crown of 10 feet, 3 on
1 side slopes and a freeboard of 3 feet above maximum water sur-
face.
  Based on studies performed it is definitely known that the cost
of the proposed work for the entire floodway, if accomplished to
               FLOOD CONTROL-ALBUQUERQUE, N. MEX., DISTRICT                                                637
adequate standards, will exceed by several times the estimated
cost as contained in the authorized plan. The authorized plan was
predicated upon general investigations and local conditions prevail-
ing in the mid-1940's; however, as a result of detailed engineering
investigations and designs the plan has been materially altered,
taking into account recent local developments, and previously un-
disclosed foundation and seepage conditions. The character and
amount of stabilization works have also been increased based upon
further design studies and observation of the river's behavior.
Since detailed plans and specifications and engineering and design
studies are not sufficiently advanced, except for the Albuquerque
unit, to determine the quantities of work involved from which a
realistic estimate of cost of the entire floodway can be determined,
it was decided to initiate construction in the Albuquerque unit first-
with funds appropriated for fiscal year 1953 and 1954 and initiate
a review of the entire project with a view to development of a firm
plan for the remainder of the floodway. At the time this decision
was made an estimate of $5 million (1954) was established for
levee and flood control work in the Albuquerque unit only. Several
plans of improvement have been investigated; however, a firm plan
has not been adopted.
    The project was authorized by the Flood Control Acts approved
June 30, 1948, and May 17, 1950.
    Local cooperation. In addition, local interests must assume
responsibility for all highway bridge and public utility relocations
or replacements required.
    Operations and results during fiscal year. Engineering and
design studies and the review of the entire project were continued.
Construction of the first phase of the Albuquerque Unit by contract
was initiated on May 21, 1954. Plans and specifications for Phase
II of the Albuquerque Unit were completed and work on the plans
for Phase III was initiated. The costs during the fiscal year were
$185,924.
    Condition at the end of the fiscal year. The general design
memorandum is approximately 75 percent complete. All planning
for the Albuquerque Unit is approximately 80 percent complete.
Construction of the Albuquerque Unit is 1 percent complete. Total
costs under the existing project to June 30, 1954, were $371,217.
                                         Cost and financial summary'

                                                Fiscal year ending June 30                       Total to June
                                                                                                30, 1954, includ-
                                                                                                ing fiscal years
                                  1950        1951         1952         1953         1954        priorto 1950
New work:
   Appropriated..    ..--------   $50, 000    $10, 000   -$15, 481     $249, 000   $300, 000            $693, 519
   Cost.--_ _-----------            2, 331     33, 588        8, 600    140. 774   * 173, 064          * 358, 357

   * In addition $12,860 costs are recorded in general ledger account 114-Prepayments for accrued cost dis-
tributions.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 .91,                        024
    Appropriated for succeeding fiscal year ending June 30, 1955_.               650, 000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955-      ---         -    - -   --      -     -   --........    741, 024
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project ......-.      ..                            3, 656, 4811
638                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                             7. INACTIVE FLOOD CONTROL PROJECTS

                                                                                                     Cost and expenditures to
                                                                                  For last                 June 30, 1954                Estimated
                       Name of project                                           full report                                             amount
                                                                                       see                                               required
                                                                                     annual            Con-           Operation             to
                                                                                     report          struction           and             complete
                                                                                      for-                           maintenance
1. Colorado Springs, Fountaine Que Bouille
     River, Colo.....----------------------------                                     1952       1$804, 008. 05            (2)             $1, 806, 972
2. Trinidad, Purgatoire River, Colo ..-------------                                   1951             53, 027.93          (3)
3. Creede, Willow Creek, Colo----------_   -------                                    1952            219, 788. 99         (2)
4. Bluewater Floodway, Bluewater Creek, N.
    Mex............-------......................--------------------------..          1951       ----------...-            ()            5 248, 000. 00

  1Does not include $242,000 contributed funds.
  2 Maintenance   assumed by local interests as required by the authorizing act.
 ' A requirement of local cooperation.
4 Pending final action on Purgatoire (Picket Wire) River, Colo, review survey report which was sub-
mitted by the district on June 30, 1953, and was forwarded to the Chief of Engineers on October 1, 1953.
 ' In addition, local interests are required to contribute the sum of $75, 000 toward the cost of construction.

                                            8. GENERAL INVESTIGATIONS
   Examinations and surveys.                                                         The cost of all work under this
heading during the fiscal year was $97,331. The balance unex-
pended at the end of the fiscal year, $9,627, and $74,000 to be al-
lotted for fiscal year 1955, amounting to a total of $83,627 will be
applied to accounts payable on June 30, 1954, $11,098, and as
needed during fiscal year 1955 for expenditures under this heading.
Included under this heading are a special study involving a com-
prehensive basin-wide investigation covering the Arkansas, White
and Red River Basins; Ark., La., Okla., Tex., N. Mex., Colo., Kans.,
and Mo., as reported in Vol. 1, and several flood control studies.
    Collection                  and study                     of      basic data.                    Also included under this
heading are miscellaneous studies involving the collection and
study of basic data such as, stream flow data, recording rain gage
data, hydrometeorological studies, Fish and Wild Life studies,
storm studies, sedimentation studies, flood emergency studies,
reservoir regulation studies, hydrologic studies, and flood investi-
gations not assignable to authorized projects or studies.
       9. INSPECTION OF COMPLETED FLOOD CONTROL WORKS
   The cost of all work under this heading during the fiscal year
was $152. Included under this heading is the inspection of com-
pleted flood control projects which have been transferred to local
interests for operation and maintenance. During the fiscal year
projects in Colo. and N. Mex. were inspected.
   Total costs for all work under this heading to the end of the
fiscal year were $1,203.
                                                          Cost and financial summary

                                                                         Fiscal year ending June 30                                    Total to Jlme
                                                                                                                                      30, 1954, includ-
                                                                                                                                      ing fiscal years
                                                1950                 1951                1952             1953          1954            prior to 1950

Maintenance:
     Cost       _--.--d                ------------                            126            $648             277              152              1,203
            FLOOD CONTROL-ALBUQUERQUE, N. MEX., DISTRICT                                                 639
10. SCHEDULING                  OF FLOOD CONTROL RESERVOIR                              OPERATIONS
   The Flood Control Act approved December 22, 1944, Section 7,
Public Law 534, 78th Congress, 2d Session, authorized the Secre-
tary of War to prescribe regulations for the use of storage allocated
for flood control or navigation at all reservoirs constructed wholly
or in part with Federal funds provided on the basis of such pur-
poses, and the operation of any such project shall be in accordance
with such regulations: Provided, that this section shall not apply
to the Tennessee Valley Authority, except that in case of danger
from floods on the Lower Ohio and Mississippi Rivers, the Ten-
nessee Valley authority is directed to regulate the release of water
from the Tennessee River into the Ohio River in accordance with
such instructions as may be issued by the War Department.
   Pursuant to this Act, expenditures were made during fiscal years
1952 and 1953 for scheduling of flood control reservoir operations
and the preparation of reservoir regulation manual for Platoro
Dam, located on the Conejos River, near the Town of Platoro, Cone-
jos County, Colo. Platoro Dam was authorized by the Congress in
the Interior Appropriation Act of 1941 (Act of June 18, 1940, ch.
395, 54 Stat. 406). (See House Doc. 693, 76th Cong., 3d Session.)
Construction of the project was completed by the Bureau of
Reclamation during fiscal year 1952.
   There were no flood control operations of Platoro Reservoir dur-
ing the fiscal year. Work on the reservoir regulation manual was
continued.
   Costs during the fiscal year were $9,517.
   Total costs for all work under this heading to the end of the fiscal
year were $11,975.
                                            Cost and financial summary

                                                   Fiscal year ending June 30                    Total to June
                                                              ._
                                                               .30,                                1954, includ-
                                                                                                ing fiscal years
                                     1950        1951        1952        1953        1954        prior to 1950

Maintenance:
   Appropriated                                               $2, 300     $9, 000    $4, 700             $16, 000
   Cost --   .       ..-- -I-   --          .                     809      1, 649    * 9, 388           * 11, 846


   * In addition $129 costs are recorded in general ledger account 114-Prepayments for accrued cost dis-
tributions.


11. FLOOD         CONTROL                   WORK        UNDER       SPECIAL         AUTHORIZATION
   Snagging and clearing of navigable streams and tributariesin
the interests of flood control. (Section 13 of the 1946 Flood Con-
trol Act.)
   A project was approved at Roberta, Colo., on Timpas Creek, a
tributary of the Arkansas River, but work was suspended before
construction was initiated and the project was canceled during
the fiscal year after it developed that local interests were unable
to comply with the requirements of local cooperation.
   There were no costs during the fiscal year.




       Sig 21--639-670
640         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                            Cost and financial summary

                                    Fiscal year ending June 30                         Total to June
                                                                                      30, 1954, includ-
                                                                                      ing fiscal years
                     1950        1951        1952         1953              1954        priorto 1950

New work:
   Appropriated      $15, 714   -$6, 519     $54, 784    -$1, 623         -$17, 151          $142, 182
   Cost__             30, 157      36, 370     4, 256       27, 069   -                       142, 182



    Emergency bank protection (Section 14 of the 1946 Flood Con-
trol Act).
    There were no costs during the fiscal year.
    Small flood control projects not specifically authorized by Con-
gress. (Section 212 of the 1950 Flood Control Act).
    Pursuant to this authorization, expenditures were made in the
amount of $34,916 during fiscal years 1951, 1952 and 1953 for
project reports on emergency flood control measures for protection
of the city of Socorro, N. Mex., along Pinon Canyon at Trinidad,
Colo., and for the Arkansas River levee, Great Bend, Kans. In-
strumental surveys, hydrologic studies, economic studies and in-
vestigations, engineering design, and cost estimates of the Socorro,
N. Mex., project were completed in fiscal year 1951; however, the
report was not submitted for the reason that investigations re-
vealed that a project providing a higher degree of protection would
be justified. Approval was given to submit the review report on
the Rio Grande in the vicinity of Socorro, authorized by resolution
of the Senate Committee on Public Works adopted September 8,
1950, in lieu of the project report.
   During the fiscal year plans and specifications for the Pinon
Canyon Dam at Trinidad, Colo., 73 feet high, 695 feet long with a
75-foot spillway, ogee weir, uncontrolled, flood control storage
560 acre-feet, located on Pinon Canyon Arroyo, 0.6 miles above
Trinidad, Colo., were completed and construction was initiated on
January 27, 1954, and is scheduled to be completed on September
18, 1954.
   The project on the Arkansas River levee, Great Bend, Kans., on
the left bank of Arkansas River, 23,500 ft. of levees, average
height, 10 feet, was cancelled after it developed that local interests
were unable to furnish the necessary rights-of-way and easements
in support of assurances given the Government.
   Costs during the fiscal year were $115,212.
   Total costs for all work under this heading to the end of the
fiscal year were $150,128.
              FLOOD CONTROL-ALBUQUERQUE, N. MEX., DISTRICT                                               641
                                      Cost and financial summary

                                                 Fiscal year ending June 30                    Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                               1950           1951         1952        1953        1954         priorto 1950

New work:
   Appropriated ..        -                    15, 300     $4, 920    $162, 470     -$417             $182, 273
        _________________ __________
   Cost..                                       7,492      12,424       15,000    * 114,179          * 149, 095


  * In addition $1,033 costs are recorded in general ledger account 114-Prepayments for accrued cost dis-
tributions.
Other new work data:
                                                                              $19,518
    Unobligated balance, fiscal year ending June 30, 1954-----------................-
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955 _ ..-.......................                                        19,518

  Flood control emergencies---repairand flood fighting and rescue
work. (Section 210 of the 1950 Flood Control Act and supple-
mental authorizations).
  A project for channel improvement and repair on Rio
Grande at Riverside and Espanola, N. Mex., was authorized near
the end of the fiscal year. Steps were taken prior to the end of
the fiscal year to secure and verify assurances of local cooperation.
Construction will be started during the first part of the next fiscal
year. In addition funds were expended during the fiscal year for
emergency flood fighting operations on the Arkansas and Pecos
Rivers.
  Costs during the fiscal year were $2,019.
                                      Cost and financial summary

                                                Fiscal year ending June 30                     Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                              1950            1951        1952        1953         1954         priorto 1950

Maintenance:

   Cost   -----------------
   Appropriated_----          $48, 315
                               36, 441
                                              $32, 045
                                               14, 598
                                                          $28, 208
                                                           53, 209
                                                                      $86, 767
                                                                       48, 403
                                                                                  $124, 000
                                                                                   11, 338
                                                                                                     $418, 607
                                                                                                   * 1 248,   366

  * Does not include $41,343 stock account.
   1 In addition $681 costs are recorded in general ledger account 114-Prepayments for accrued cost dis-
tributions.
  (Credit of $4,456 received from Abeytas-Bernardo Area Project for sand bags and steel cable.)


  Emergency flood control work under authority of Public Laws
138 and 318, 78th Congress; Public Law 75, 79th Congress; and
Public Laws 102 and 858, 80th Congress.
  There were no costs during the fiscal year.
  Emergency Flood Control Work under authority of Public Law
371, 82d Congress, approved June 4, 1952.
642            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Pursuant to this authorization, expenditures were made during
fiscal year 1953 and 1954 for repair and rehabilitation of levees
and levee protection works damaged by floods on Rio Grande in
New Mexico in the areas and locations listed below:

                                              Area of location                                                        June 0, 1954


Abeytas-Bernardo area-_ - ...          .....  .................        --     -1                                             $131, 014
Santa D omingo area-_--    - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - -                                       29, 879
Opposite Jemez Creek -..................-----                                                                                   89, 762
Bernalillo Sawm ill area _ -- - -- -- - -- -- - -- -- - -       . . . . . .. . . . . . .                                        79, 083
Sandia Pueblo area - - - - - _- - - - - - _-_-- - _- - - - - --                              - -- -              --             84, 682
Chical area_ -_-- --_ - --                  --------------
                                        --------                        -------     --------------                             64, 816
                                                                                                                               8---
Los Lentes area-..    __...                                                          __-                    --    -            73, 006
Below Los Lunas..     . . .      . .     . .    .     . .     . .   .   . .      . . . . . . .       .    . .     .            32, 806


  1 Includes $44, 119 by transfer of funds from the Bureau of Reclamation.


   In addition to levee repairs and rehabilitation, construction in
the Abeytas-Bernardo area involved closing a breach in the levee
to keep the river from entering a riverside drain and bypassing
its present channel and causing damage to an adjacent U. S. High-
way 60 bridge across the drain and a large section of the track
of the A. T. & S. F. Ry. and a section of U. S. Highway 85 that
parallels the drain. In addition, the Bureau of Reclamation trans-
ferred funds in the amount of $44,119 to the Corps of Engineers
for the construction of a reinforced concrete drainage structure
at a major break in the levee near Bernardo, N. Mex., to be used
for diversion of low flows of the river into the San Francisco drain-
age canal for irrigation purposes. The Bureau of Reclamation
was performing work in the area simultaneously with that being
performed by the Corps of Engineers and the inclusion of the
drainage structure in the Corps' portion of the work resulted in
the most economical contract operations by both agencies.
   Construction in the Abeytas-Bernardo area was initiated on
April 20, 1953, and completed Oct. 12, 1953, and construction in
the other seven areas listed above was initiated on April 9, 1953
and completed September 26, 1953.
   Costs during the fiscal year were $278,550.
   Total costs for all work under this heading to the end of the
fiscal year were $585,048.
                                              Cost and financial summary

                                                            Fiscal year ending June 30                                 Total to June
                                                                                                                      30, 1954, includ-
                                                                                                                      ing fiscal years
                                      1950             1951               1952            1953             1954        prior to 1950

Maintenance:
    Appropriated-   -                   ---           .---
                                                    -----------     ----------            615, 938       -$30, 890           * 585, 048
    Cost _-------------   ---------              ------------------------
                                                       :                                  306, 498         278,550           * 585, 048

   * Includes $44,119 from Bureau of Reclamation.
    IMPROVEMENTS OF RIVERS AND HARBORS IN THE
            LITTLE ROCK, ARK., DISTRICT

  This district comprises the northern and western portions of
Arkansas, a portion of southern Missouri, and a small portion of
eastern Oklahoma embraced in the drainage basins of the Ar-
kansas River and tributaries above and exclusive of Pine Bluff,
Ark., and below the mouth of Poteau River, near Fort Smith, Ark.,
and of the White River and tributaries above Peach Orchard Bluff,
Ark.
                                           IMPROVEMENTS

                   Navigation                                     Flood control-Continued
                                                Page                                                        Page
1. Arkansas River and tributaries,                             9. From North Little Rock to
     Ark. and Okla., navigation                                     Gillett, Ark. (above Plum
                                                     643
     features..........------------..........-------.....-------    Bayou)........................... ...   661
2. Inactive navigation projects .....                650 10. South Bank Arkansas River
                                                                     (head of Fourche Island to
                Flood control                                       Pennington Bayou), Ark -......          662
3. White River Basin, Little Rock                            11. Arkansas River Basin, Little
     D istrict ....................................  650            Rock District .........-...........     663
4. Table Rock Reservoir, White                               12. Blue Mountain Reservoir, Ar-
     River Basin, Mo....................             653            kansas River Basin, Ark........         664
5. Bull Shoals Reservoir, White                              13. Nimrod Reservoir, Arkansas
     River Basin, Ark..................              655            River Basin, Ark .............          666
6. Norfork Reservoir, White River                            14. Inactive flood control projects..          668
     Basin, Ark....---.-.-. - - .. --......          656 15. General investigations ...........             668
7. Clearwater Reservoir, White                               16. Inspection of completed flood
     River Basin, Mo...                 ......... 658               control works _......................   669
8. Crawford County Levee Dis-                                17. Flood control work under special
     trict, Arkansas River, Ark ..                   660            authorization ... _.................    669

  1. ARKANSAS RIVER AND TRIBUTARIES, ARK. AND OKLA.,
                  NAVIGATION FEATURES
   Location. The Arkansas River rises in the Rocky Mountains
near Leadville, Colo., and flows southeastward for about 1,450
miles through the States of Colorado, Kansas, Oklahoma, and
Arkansas to join the Mississippi River at a point about 575 miles
above the Head of Passes, La. (See U. S. Geological Survey State
maps, scale 1:500,000.)
   Previous projects. Previous projects were adopted by the
River and Harbor Acts of July 3, 1832, April 8, 1876, March 3,
1879, June 14, 1880, July 5, 1884, August 5, 1886, August 11, 1888,
June 13, 1902, and March 2, 1907. For further details, see page
1066, Annual Report for 1932, and pages 744, 864, and 881, Annual
Report for 1943.
   Existing project. The River and Harbor Act of July 24, 1946,
approved the multiple purpose plan recommended in the report of
the Chief of Engineers dated September 20, 1945 (H. Doc. 758,
79th Cong., 2d sess.), and letter of the Chief of Engineers dated
March 19, 1946, and limited appropriations thereunder to $55
million for initiation and partial accomplishment of the project.
The Flood Control Act of June 30, 1948, increased the authoriza-
tion for appropriations by $1 million by authorization to construct,
as an emergency measure, bank protection and control works at
                                                                                                643
644            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Bradens Bend, Okla., thereby increasing the total authorization
to $56 million. The River and Harbor and Flood Control Acts of
May 17, 1950, increased the' authorization for appropriations an
additional $80 million or to a total of $136 million and modified
the multiple-purpose plan and the general comprehensive plan
for flood control by substitution of Keystone Reservoir, located
on the Arkansas River 538.9 miles above the mouth, for the ap-
proved Mannford Reservoir on the Cimarron River and by deletion
of the approved Blackburn and Taft Reservoirs on the Arkansas
River as recommended by the Chief of Engineers (S. Doc. 107,
81st Cong., 1st sess.). Details concerning the Keystone Reservoir
are shown under flood control, Tulsa district.
   The existing project provides for improvement of the Arkansas
River and tributaries by construction of coordinated developments
to serve navigation, produce hydroelectric power, afford additional
flood control, and provide related benefits in connection with other
activities such as recreation and wildlife propagation. The naviga-
tion features provide for a channel 9 feet deep following generally
the Verdigris River from Catoosa, Okla., 52 miles downstream to
the Arkansas River; thence along the channel of the latter stream
to mile 51 (1940 survey) ; thence by a land cut, designated as the
Arkansas Post route, to the White River at mile 18.3; thence
along the channel of the White River to mile 7.8; thence by a land
cut to the Mississippi River at a point about 590.5 miles above the
Head of Passes, La. The waterway would be canalized throughout
its length by 3 navigation locks and dams on the Verdigris River
and 16 navigation locks and dams and 4 navigation and hydro-
electric power dams downstream therefrom. The four navigation
and power dams are the Webbers Falls, Short Mountain, Ozark,
and Dardanelle projects. Lock chambers are 110 by 600 feet on
the Arkansas and White Rivers and 83 by 600 feet on the Verdigris
River. A minimum channel width of 150 feet is proposed for the
Verdigris River section and 250 feet for the Arkansas and White
River sections.
   The Federal cost of the project (July 1954) is $909,360,000 for
new work and is itemized in the following table.
                Feature                                             Location'                            Estimated
                                                                                                            cost
         TULSA DISTRICT

      :MvAIN STEM RESERVOIRS

Webbers Falls Dam and Reservoir..... Verdigris River-mile 4, Arkansas River-mile                         $75, 800, 000
                                      432.3.
Short Mountain Dam and Reservoir ... Arkansas River-mile 432.3 to 395.4_                                 116, 000,000
           LOCKS AND DAMS
No. 3_                                       Verdigris River-pool-mile          52 to 37.2 -              19, 500, 000
           - ...__...
        -----
N o . 2 . .-              --   _..---..
                                   . . . . . V erdigris R iv er- p o ol- m ile 3 7.2 to 19.4 ...
                                             Verdigris River-pool-mile 19.4 to 4- --
                                                                                                          15,700 , 000
                                                                                                          14, 900, 000
No. 1_                                                                                        ___   -.

Channel cutoffs,    enlargements,      and    Verdigris River-mile 63 to mile0.                            19, 900, 000
turning basin.
No. 25--.................
           _       . ............ Arkansas River-pool-mile 395.4 to 376.2..                               31, 400, 000
                            ........Arkansas River
Dredging......................                        _                                                   12,600, 000

  BANK STABILIZATION AND CHANNEL
           RECTIFICATION

Short Mountain to Wilsons Rock                Arkansas River-mile 395.4 to 376.5 .                         9, 800, 000
Wilsons Rock to Fort Smith......              Arkansas River-mile 376.5 to 362 .......                     6, 100, 000
     Total, Tulsa district .................                       .........-                       -.   321,200, 000
See footnotes at end of table.
               RIVERS AND HARBORS-LITTLE ROCK, ARK., DISTRICT                                                                          645

                   Feature                                                          Location I                                 Estimated
                                                                                                                                  cost
                                                                                -                                            ~~~I-------
      LITTLE ROCK DISTRICT

           MAIN STEM RESERVOIRS

Ozark Dam and Reservoir _.......                                 Arkansas River-mile 346.5 to 319_ _                            $54, 800, 000
Dardanelle Dam and Reservoir .... _ .                            Arkansas River-mile 301.8 to 257.8_                             94, 600, 000
              LOCKS AND DAMS
No. 22-A                -  --                                    Arkansas River-pool-mile 376.2 to 346.5 .....     23, 800, 000
Dredging                                                         Arkansas River..........................----- 2, 300, 000
No. 19-A .....     .          .       ...-.    ..   . .          Arkansas River-pool-mile 319 to 301.8         --
                                                                                                             ---.- 17, 800, 000
No. 13-A                                                         Arkansas River-pool-mile 257.8 to 227.9 ....      19, 900, 000
Dredging                                                         Arkansas River....      ..-------------------      5, 900, 000
No. 12-A                                                         Arkansas River-pool-mile 227.9 to 208.2_ _ _ _.   19, 200, 000
No. 11-A                                                         Arkansas River-pool-mile 208.2 to 193.9 _ ___     17, 700, 000
No. 10-A .. ....   . ..           ... . .     ..                 Arkansas River-pool-mile 193.9 to 170.9_ __ _     19, 000, 000
No. 9-A .                 .             .                        Arkansas River-pool-mile 170.9 to 153.5 _ __      26, 100, 000
                                                                 Arkansas River-pool-mile 153.5 to 145-.. --       19, 900, 000
No. 7 --    ....                                                 Arkansas River-pool-mile 145 to 128_.. ..    _ _. 18, 800, 000
Dredging plant, including channel snag                                                                                           11,600, 000
ging and dredging.

   BANK STABILIZATION AND CHANNEL
            RECTIFICATION

Fort Smith to Mill Creek Mountain..                              Arkansas   River-pool-mile   362 to 327 ..                      13, 400, 000
Mill Creek Mountain to Morrisons Bluf                            Arkansas   River-pool-mile   327 to 285 __ _____                 5,600, 000
Dardanelle Rock to Morrilton Bridge.                             Arkansas   River-pool-mile   257 to 221_                        13, 900, 000
Morrilton Bridge to Fourche La Fave_                             Arkansas   River-pool-mile   221 to 192.........                 8, 000, 000
Fourche La Fave to Little Rock-......                            Arkansas   River-pool-mile   192 to 165.5.. _ _ _ .             11, 700, 000
Little Rock to Jefferson County Fre                              Arkansas   River-pool-mile   165.5 to 115.6 _ ___               21, 600, 000
  Bridge.

        Total, Little Rock district ......                                                                                      425, 600, 000
        VICKSBURG DISTRICT
              LOCKS AND DAMS
N o. 6 .       --- -- - -- - - -- -.                 ...         Arkansas River-pool-mile 128 to 65.3 (mile                      24, 304, 100
                                                                  115.6 mile 71.2).
No. 5                                                            Arkansas River-pool-mile 65.3 to 51.2_......                    19, 215, 800
No. 4                                                            Arkansas River-pool-mile 51.2 to 37.7 . ..                      20, 258, 200
No. 3                                                            Pool-Arkansas River mile 37.7 to navigation                     28, 043, 900
                                                                  route mile 13.2.
No. 2                                                            Pool-navigation route mile 13.2 to navigation                   10, 980, 500
                                                                  route mile 10.3.
No. 1                                                            Pool-navigation route mile 10.3 to navigation                   21, 666, 800
                                                                  route mile 5.7
   BANK STABILIZATION AND CHANNEL
            RECTIFICATION

Jefferson County free bridge to Rob Roy                          Arkansas River-mile 101.7 to 89                                  6, 965, 100
   Bridge.
Rob Roy Bridge to Arkansas Post Canal                            Arkansas River-mile 89 to 42.....              ..               28,864, 600
Arkansas Post Canal to Yancopin                                  Arkansas River-mile 42 to 23.5                                   1, 798, 000
   Bridge.
Yancopin Bridge to mouth_ _ _ _.......                           Arkansas River-mile 23.5 to 0 ..                                   463, 000

        Total. Vicksburg district                          ...                                ...                    -          162, 560, 000

        Total navigation project                                                                    ......               .      909, 360, 000


1 Mileage from 1940 survey for Tulsa and Little Rock districts and 1943 survey for Vicksburg district.
   Includes cost of all plant and repair depot for entire project.



   The active features of the project are reported individually on
following pages.
  The existing project was authorized by the River and Harbor
Act of July 24, 1946, as amended by the Flood Control Act of June
30, 1948, and the Flood Control Act of May 17, 1950. (See H. Doc.
758, 79th Cong., 2d sess., which contains the latest published
maps.)
   Local cooperation. Local interests are required to provide
adequate terminal and transfer facilities for navigation and bear
the increased cost of maintenance and operation of all altered rail
646      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

and highway routes, including bridges and appurtenances, utilities,
and other existing improvements, other than federally owned.
   Terminal facilities. Terminal facilities along the Arkansas
River consist of a paved bank slope, under municipal control, at
Little Rock; privately owned log slips at sawmills and stave mills
at Little Rock; and sand and gravel derricks and elevators at Van
Buren, Dardanelle, Little Rock, and Pine Bluff. These facilities,
which are adequate for existing commerce on the river, are located
at or near rail connections.
   Operations and results during fiscal year. Planning and con-
struction of the multiple-purpose project were limited to emer-
gency bank stabilization and channel rectification. Observation
and study of bank caving conditions were continued and plans and
specifications prepared for emergency bank stabilization and chan-
nel rectification works at specific localities. For details see indi-
vidual reports on following pages.
   The costs during the fiscal year were $3,543,081, of which
$3,479,478 was for new work and $63,603 was for maintenance.
The costs for new work include $1,183,485 for the Tulsa District,
$1,754,892 for the Little Rock District, and $541,101 for the Vicks-
burg District. The maintenance costs were for the Vicksburg
District.
   Condition at end of fiscal year. Planning for the development
of the overall plan has been suspended. Definite Project studies
are 54 percent complete for the Dardanelle Dam and Reservoir
and 40 percent complete for Lock and Dam No. 7. Construction
of the emergency bank stabilization and channel rectification is
54 percent complete. The completed bank stabilization and chan-
nel rectification work amounts to about 10 percent of that work
for the existing project. Details of the progress of the emer-
gency bank stabilization and channel rectification work are given
by districts in the individual reports on the following pages.
   The total costs to the end of the fiscal year were $13,994,469,
of which $13,930,866 was for new work and $63,603 was for main-
tenance. The costs for new work include $3,855,574 for the Tulsa
District, $6,494,047 for the Little Rock District, and $3,581,245
for the Vicksburg District. The maintenance costs were for the
Vicksburg District.

      BANK STABILIZATION AND CHANNEL RECTIFICATION,
      ARKANSAS RIVER, ARK. AND OKLA. (TULSA DISTRICT)

   Location. The bank stabilization, cutoffs, and channel improve-
ment work are located in the reach of the Arkansas River between
Short Mountain Dam site and Fort Smith, Ark., river miles 395.4
and 362, respectively. (See U. S. Geological Survey maps for Sans
Bois (Okla.), Sallisaw (Okla.), and Fort Smith (Ark.-Okla.) quad-
rangles, scale 1:125,000.)
   Existing project. The project consisting of training dikes, cut-
offs, revetment, and other channel work, forms a unit in the
multiple-purpose plan and provides for navigation of the Arkansas
River. The reach and location of each bank stabilization and
channel rectification project are contained in the following table.
              RIVERS AND HARBORS-LITTLE ROCK, ARK., DISTRICT                                                            647

                                        Reach                                                       Location of reach
Short Mountain to Wilsons Rock                    - -Mile      _                                 395.4 to mile 376.5.
Wilsons Rock to Fort Smith    ---------------------------------                             Mile 376.5 to mile 362.0.



   The estimated cost (July 1954) is $15,605,000 for construction
and $295,000 for lands and damages, a total of $15,900,000 for
new work.
   The existing project was authorized by the River and Harbor
Act approved July 24, 1946. (See H. Doc. 758, 79th Cong., 2d sess.)
   Since the corrective bank stabilization in the reach between
Wilsons Rock and Fort Smith will also protect the critical location
on the right bank of Arkansas River in vicinity of Bradens Bend,
Okla., the bank protection work under the Bradens Bend project as
authorized by the Flood Control Act of June 30, 1948, will not be
performed. Other data concerning the Bradens Bend project are
shown under flood control, Tulsa district.
   Local cooperation. See requirements for entire project.
   Operations and results during fiscal year. Construction of
emergency bank stabilization and channel rectification work on
the Arkansas River between Wilsons Rock, Okla., and Fort Smith,
Ark., was continued by contract. The work accomplished con-
sisted of the placement of 6,138 linear feet of pile dikes and 13,389
linear feet of bank revetment.
   The costs during the fiscal year were $1,183,485, all for new
work.
   Condition at end of fiscal year. Emergency bank stabilization
and channel rectification works in the vicinity of Bradens Bend
were initiated on May 1, 1952, and are 59 percent complete. A
total of 25,705 linear feet of pile dikes and 29,069 linear feet of
bank revetment have been completed.
   The total costs to the end of the fiscal year were $3,855,574, all
for new work.
       BANK STABILIZATION AND CHANNEL RECTIFICATION,
         ARKANSAS RIVER, ARK. (LITTLE ROCK DISTRICT)
   Location. The several bank stabilization and channel rectifica-
tion projects are laid out in various reaches extending from fixed
point to fixed point on the Arkansas River from 115.6 to 362.0
miles above the mouth.
   Existing project. The bank stabilization and channel rectifica-
tion program is a part of the general overall long range plan for
multiple-purpose development of the Arkansas River. The reach
and location of each bank stabilization and channel rectification
project are contained in the following table.

                                       Reach                                                        Location of reach
Fort Smith to Mill Creek Mountain-----_ - ..--------------------                            Mile 362 to mile   327.
Mill Creek Mountain to Morrisons Bluff-....    --------------------                         Mile 327 to mile   285.
Dardanelle Rock to Morrilton Bridge ...................--------------------------           Mile 257 to mile   221.
Morrilton Bridge to Fourche La Fave..........................--------------------------     Mile 221 to mile   192.
Fourche La Fave to Little Rock ..................................                -          Mile 192 to mile   165.5.
Little Rock to Jefferson County Free Bridge-......-.....-..........                       . Mile 165.5 to mile 115.6.
648      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  The estimated cost (July 1954) is $72,799,000 for construction
and $1,401,000 for lands and damages, totaling $74,200,000 for
new work.
  The existing project was authorized by the River and Harbor
Act approved July 24, 1946. (See H. Doc. 758, 79th Cong., 2d
sess.)
    Local cooperation. See requirements for entire project.
    Operations and results during fiscal year. In the reach from
Fort Smith to Mill Creek Mountain, contract work was initiated
and completed for excavation of 8,200 feet of cutoff channel at
Trustee Bend and 8 tracts of land comprising 733 acres'were
acquired.
    In the reach from Dardanelle Rock to Morrilton Bridge, con-
struction of 13,500 linear feet of revetment was completed by con-
tract, excavation of 19,600 linear feet of pilot channel at Holla
Bend was initiated and completed by contract, contract was
awarded for construction of control works at Holla Bend, contract
was initiated and completed for construction of 2,700 linear feet of
rock fill dikes at Carden's Bottom, and 24 tracts of land comprising
3,874 acres were acquired.
    In the reach from Morrilton Bridge to Fourche La Fave, con-
tract was initiated and completed for construction of 750 linear
feet of rock fill dike at Cadron Ridge.
    In the reach from Little Rock to Jefferson County Free Bridge,
works by contract were initiated and completed on 3,150 linear
feet of pile dikes at Estes Place and 5,000 linear feet of trench
fill revetment at Waring Bend, contract work was continued on
construction of revetment at Estes Place and Waring Bend, con-
tinuing contract was completed for construction of a portion of
the river closure structure at Hensley Bar cutoff, and 16 tracts of
land comprising 364 acres were acquired.
    The costs during the fiscal year were $1,754,892, all for new
work.
    Condition at end of fiscal year. In the reach from Fort Smith
to Mill Creek Mountain, excavation of the pilot channel at Trustee
Bend is complete.
    In the reach from Dardanelle Rock to Morrilton Bridge, bank
stabilization on the right bank between river miles 252.6 and 251.1
is complete, a pile dike at river mile 254 is complete, excavation
of the Holla Bend cutoff pilot channel is complete, and construction
of 3 pile dikes at Carden's Bottom is complete.
    In the reach from Morrilton Bridge to Fourche La Fave, excava-
tion of the pilot channel for the Morrilton cutoff and construction
of the revetment on the left bank of the cutoff and the upstream
control works are complete, and construction of the Cadron Ridge
dikes on the left bank near river mile 204 is complete.
    In the reach from Little Rock to Jefferson County Free Bridge,
first stage construction of pile dikes and revetment at Estes Place
and revetment at Waring Bend are complete, second stage con-
struction of revetment at Estes Place and Waring Bend is about
54 percent complete, bank stabilization on both banks between
river miles 127.8 and 121.3 is complete, and excavation of the
pilot channel and construction of the upstream control works and
           RIVERS AND HARBORS-LITTLE ROCK, ARK., DISTRICT                                           649

the revetment on the right bank at Hensley Bar are complete.
  The total costs to the end of the fiscal year were $6,494,047, all
for new work.

      BANK STABILIZATION AND CHANNEL RECTIFICATION,
         ARKANSAS RIVER, ARK. (VICKSBURG DISTRICT)

  Location. The bank stabilization and channel rectification proj-
ects are laid out in reaches extending from fixed point to fixed point
on the Arkansas River from the mouth to 101.7 miles above the
mouth. (River miles as measured on the 1943 survey.)
  Existing project. The bank stabilization program is a part of
the general overall long-range plan for multiple-purpose develop-
ment of the Arkansas River. Studies indicate that the banks of
the river can be effectively stabilized only by completing an entire
reach between two relatively stable or fixed points. The reach
and location of each bank stabilization and channel rectification
project are contained in the following table.

                               Reach                                          Location of reach I

Jefferson County Free Bridge to Rob Roy Bridge_- ______............    Mile 101.7 to mile 89.
Rob Roy Bridge to Arkansas Post Canal__________________________..      Mile 89 to mile 42.
                                          _
Arkansas Post Canal to Yancopin Bridge_ _ _ _............... _
                                                             .._       Mile 42 to mile 23.5.
Yancopin Bridge to mouth -...........................----             IMile 23.5 to mile 0.

  SRiver mileage from 1943 survey.


   The estimated cost (July 1954) is $38,090,700 for construction.
   The existing project was authorized by the River and Harbor
Act approved July 24, 1946. (See H. Doc. 758, 79th Cong., 2d sess.)
   Local cooperation. See requirements for entire project.
   Operations and results during fiscal year. Pile dike construc-
tion in the New Gascony Reach was completed by contract. Re-
vetment and pile dike construction in the New Gascony Reach
 (Madding) was initiated and completed by contract. Work under
contract for construction of additional revetment and pile dike
in the New Gascony Reach (Trulock) was initiated and is 67 per-
cent complete. Repairs were made by hired labor to the revetment
and pile dikes at Medford Bend.
   The costs during the fiscal year were $541,101 for new work
and $63,603 for maintenance, totaling $604,704.
   Condition at end of fiscal year. Studies, planning, and design
are in progress. Operative bank stabilization works in place in-
clude 30,670 linear feet of revetment and 13,651 linear feet of pile
dikes.
   Bank stabilization and channel rectification works have been
constructed in the Arkansas River between Pine Bluff, Ark., and
the mouth under appropriation for flood control, Mississippi River
and tributaries, of which 33,275 linear feet of pile dikes and 21,755
linear feet of revetment are operative. This work is reported in
the annual report of the President, Mississippi River Commission.
   The total costs to the end of the fiscal year were $3,581,245 for
new work and $63,603 for maintenance, totaling $3,644,848.
650                  REPORT OF CHIEF OF ENGINEERS,                                               U.   S. ARMY,        1954


                                                      Cost and financial summary

                                                                   Fiscal year ending June 30                                  Total to June
                                                                                                                              30, 1954, includ-
                                                                                                                              ing fiscal years
                                               1950              1951           1952             1953          1954            prior to 1950

New work:
   Appropriated.              - - -.   $1, 850, 000           $838, 000      $4, 208, 039   $3, 841, 000    $3, 731, 627          $14,968,666
   Cost ----------------                   710. 770          1, 173, 613      1, 791, 413    6, 508, 674     3, 479, 478           13, 930, 866
Maintenance:
      Appropriated                    -               --------                               -   -              65, 000                    65, 000
      Cost ---------------------------------                                                                    63,603                     63,603

   Note-Costs do not include $380,967 for new work and $942,244 for maintenance applicable to previous
projects which have been included in prior year cost and financial summaries.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 .....------------
                                                                 _            $692, 698
    Appropriated for succeeding fiscal year ending June 30, 1955 .-.. 3, 000,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955       ------.... ...... -------------------------------- 3, 692, 698
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project..----------..------------------..891, 391, 334

            Unobligated balance for maintenance, fiscal year ending June 30,
              1954    --------------..........------------------                                                                           1,397

                                  2. INACTIVE NAVIGATION PROJECTS

                                                                            For last         Cost to June 30, 1954               Estimated
                                                                           full report                                             amount
                       Name of project                                          see                                               required
                                                                             annual            Con-          Operation               to
                                                                              report        struction           and              complete
                                                                               for-                         maintenance

1.   Black River, Ark. and Mo .------------------                             1950               $80, 000        $658, 222             (1)
2.   Current River, Ark. and 2Mo_-           - -                              1950                17, 000          125, 912           (')
3.   Upper White River, Ark.                                                  1952               813,197      3 1, 788, 374           (4
4.   White River, Ark. (above Peach Orchard                                   1950               337, 802        5785,666             ('
       Bluff).

   1 Channel adequate for existing commerce. Completion not contemplated.
   2 Federal operation and maintenance was terminated June 30, 1952, due to lack of commerce. Facilities
at lock and dam No. 1 operated and maintained by city of Batesville, Ark., under 25-year license since
that date.
   SIncludes $1,071 expended for maintenance in fiscal year 1954 and $1,187,283 from permanent appropriation
for operating and care, and cost applicable to operating and care operations in the amount of $60,614 paid
from funds allotted during fiscal years 1937 and 1938 to White River for operations on both White and
Upper White River projects.
   4 Completed.
   5 Includes $359, Little Red River, and excludes $60,614, Upper White River, Ark.


                  3. WHITE RIVER BASIN, LITTLE ROCK DISTRICT
  Location. These improvements are located on the White River
and tributaries thereof and are in the States of Arkansas and
Missouri. More definite locations of the individual items are given
in the following paragraph.
   Existing project. The Flood Control Act of June 28, 1938, ap-
proved the general comprehensive plan for flood control and other
purposes in the White River Basin, as set forth in Flood Control
Committee Document 1, 75th Congress, 1st session, with such
modifications thereof as in the discretion of the Secretary of War
and the Chief of Engineers may be advisable, and authorized the
sum of $25 million for reservoirs, for the initiation and partial
accomplishment of the plan, the reservoirs to be selected and ap-
proved by the Chief of Engineers.                                                        The Flood Control Act ap-
                      FLOOD CONTROL-LITTLE ROCK, ARK., DISTRICT                                                          651
proved August 18, 1941, authorized to be appropriated the sum
of $24 million, in addition to previous authorizations, for the prose-
cution of the comprehensive plan approved in the act of June 28,
1938, for the White River Basin in Missouri and Arkansas, in-
cluding the projects for flood control and other purposes recom-
mended by the Chief of Engineers in House Document 917, 76th
Congress, 3d session, and the modifications in the Norfork Reser-
voir project recommended by the Chief of Engineers in House
Document 290, 77th Congress, 1st session. The Flood Control
Act approved December 22, 1944, authorized to be appropriated the
sum of $45 million, the Flood Control Act approved July 24, 1946,
authorized to be appropriated the sum of $40 million, and the
Flood Control Act approved May 17, 1950, authorized to be ap-
propriated the sum of $35 million, in addition to previous au-
thorizations, for the prosecution of the comprehensive plan. The
reservoirs included in the comprehensive plan are listed below:

                                    Dis-               Drain-                          Power
                                   tance                 age   Height of dam Reservoir develop- Total
Reservoir             River        abovel Nearest town area above streambed capacity   ment    estimated
                                   mouth               (square    and type     (acre-    (kilo-   cost 1
                                   (miles)              miles)                 feet)    watts)
                                             I_

Table Rock      2   White ___
                           ..-     528.8      Branson, Mo_ 4, 020        253 feet concrete 3, 462, 000 84, 000      78, 700, 000
                                                                           gravity     and
                                                                           earthfill.
Bull Shoals 2 ..... do ..          418.6      Amos, Ark___ 6, 036        258 feet concrete- 5, 408, 000 160, 000    76, 329, 000
                                                                           gravity.
Lone Rock__ Buffalo __...            3.6      Lone Rock,      1, 331     216 feet concrete-    687, 000    (3)      29, 460, 000
                                                Ark.                       gravity.
Norfork 2 ...       North Fork_      4.8      Norfork, Ark.   1, 806     222 feet concrete- 1, 983, 000 70, 000     28, 700, 000
                                                                           gravity.
Clearwater 2 Black -_--.           257.4      Piedmont,         898      154 feet earthfill_ 413, 000      (3)       9, 721, 200
                                                  Mo.
WaterValley         Eleven Point    12.6  Watervalley,        1, 152     157 feet earthfill_ 1,563, 000      (4)    15, 000, 000
                                           Ark.
Bejl Foley...       Strawberry      26.2 Smithville,            520      113 feet earthfill_j   245, 000     (3)     9, 750, 000
                                           Ark.
Greers Ferry Little        Red_     77.2 Heber Springs,       1, 147     158 feet concrete-     524, 000     (3)    17, 800, 000
                                           Ark.                            gravity.

1 July 1954 price levels.
2 For details of this project, see individual report.
SNone.
  4 Includes provisions for future power installation.


   Clearwater, Norfork, Bull Shoals, and Table Rock Reservoirs
were selected and approved for construction by the Chief of En-
gineers in accordance with the above authorization and individual
reports on the four reservoirs are given in the following pages.
All costs and expenditures for those four reservoirs previously
reported under the heading "White River Basin, Little Rock dis-
trict" have been transferred to the individual reports.
   Local cooperation.                         Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations              and     results          during      fiscal       year.         Stream          gaging       was
continued by hired labor. Preparation of a master plan for reser-
voir regulation was initiated by hired labor.
  One noteworthy rise occurred on the Upper White and North
Fork Rivers during the fiscal year. Regulation of flow on the
North Fork River in the Norfork Reservoir and on Upper White
652             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

River in the Bull Shoals Reservoir during the fiscal year prevented
flooding of about 7,780 acres of improved land of which approxi-
mately 3,730 and 4,050 was credited to Bull Shoals and Norfork,
respectively. Flood modifications on the White River at Calico
Rock, 17 miles downstream from the mouth of the North Fork
River and 59 miles downstream from Bull Shoals Dam, and at
Newport, 102 miles downstream from Calico Rock, are given in
the following tabulation.
                                                                     Bull                                   White River
                          Item                                      Shoals              Norfork
                                                                Reservoir           Reservoir
                                                                                                        Calico      Newport,
                                                                                                                          2
                                                                                                      Rock, Ark.'    Ark.


Date of peak inflow.. ------------------------- May 3, 1954                        May 2, 1954
Peak inflow, cubic feet per second...............-----------------.. 18, 500           23, 900          .
Outflow coincident with peak uncontrolled flow
at Calico Rock, cubic feet per second....------------                 4, 360              3 1, 230         - -- --------
Maximum pool elevation, feet above mean sea level                      610. 8                523. 2
Corresponding storage utilized, acre-feet-----------..               152, 100              42, 400          -       -
Experienced crest stage, feet ..       .   .   .   .   .   ..   .    . ..    . .    .      . -..            13. 4         19. 8
Estimated crest stage without Bull Shoals and
Norfork Reservoirs, feet-------------------      ----------------------                                    15. 3           22. 0
Estimated reduction in stage, feet            - -
                                     _ .-----------               --
                                                       . __---------     ------------                        1.9             2.2


  1Appreciable overflow begins at 19 feet.
  'Appreciable overflow begins at 18 feet.
  ' For generation of continuous power.
    Flood regulated in power pool.

   The pool elevation of the Norfork Reservoir at the beginning of
the fiscal year was 549.65 feet above mean sea level, corresponding
to 1,200,300 acre-feet of total storage. At the end of the fiscal
year the pool elevation was 519.54 feet above mean sea level,
corresponding to 670,600 acre-feet of total storage. The maximum
pool elevation during the fiscal year was that recorded at the be-
ginning of the fiscal year. The pool elevation of the Bull Shoals
Reservoir at the beginning of the fiscal year was 649.85 feet above
mean sea level, corresponding to 2,863,600 acre-feet of total stor-
age; and at the end of the fiscal year was 603.16 feet above mean
sea level, corresponding to 1,307,000 acre-feet of total storage.
The maximum pool elevation during the fiscal year was that
recorded at the beginning of the fiscal year.
  The costs during the fiscal year were $8,653, all for new work.
   Condition at end of fiscal year. Planning is 57 percent com-
plete for Water Valley Reservoir, 15 percent complete for Lone
Rock Reservoir, and 22 percent complete for Greers Ferry Reser-
voir. The progress on projects selected for construction is given
in individual reports.
  The total costs to the end of the fiscal year were $823,416, all
for new work.
             FLOOD CONTROL--LITTLE ROCK, ARK., DISTRICT                                          653
                                 Cost and financial summary

                                       Fiscal year ending June 30                      Total to June
                                                                                       30, 1954, includ-
                                                                                       ing fiscal years
                          1950        1951       1   1952      1953         1954        priorto 1950

New work:
   Appropriated ....-    $150,006    $100,000    --$142, 185   $40,000    -$15, 000            $824, 515
   Cost.                   28, 006     87, 477        5, 838    15, 247       8, 653            823, 416


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954._                        $1, 099
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955.......: ......    .                             .......         1,099
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project ..........--------------------------------- 71, 185, 485


     4. TABLE       ROCK RESERVOIR,                  WHITE     RIVER BASIN, MO.

   Location. The Table Rock Dam site is at mile 528.8 on the
White River in Taney County, Mo., about 8 miles upstream and
southwest of Branson, Mo. (See sectional aeronautical chart,
Tulsa sheet, scale 1:500,000; Harrison sheet NJ15-11, Army Map
Service series V502, scale 1:250,000; U. S. Geological Survey map
for Forsyth, Mo., quadrangle, scale 1:125,000.) From the dam
the reservoir will extend westward into Stone and Barry Counties,
Mo., and into Boone, Carroll, and Benton Counties, Ark.
   Existing project. The existing project is approved for the com-
bined purposes of flood control, the generation of hydroelectric
power, and for other beneficial uses. The project plan provides
for construction of a dam 6,423 feet long consisting of a concrete
gravity structure across the main part of the valley with two
rolled earthfill abutment sections and a hydroelectric power gen-
erating plant. The concrete portion of the dam will be 1,602
feet long and 261 feet high above the lowest point of foundation.
The left abutment embankment will be 3,798 feet long, with a
maximum height of 172 feet. The right abutment embankment
will be 1,023 feet long, with a maximum height of 35 feet. The
concrete portion of the dam will include a spillway section 531
feet long which will be bridged for a roadway across the dam. The
flow over the spillway will be controlled by 10 radial crest gates
45 feet wide and 37 feet high. Flow through the dam will be
regulated by four 4- by 9-foot conduits equipped with hydraulically-
operated slide gates. The total discharge capacity of the outlets
will be 14,500 cubic feet per second with the reservoir filled to the
top of flood control pool, elevation 931. Flow to the powerplant
will be through four 18-foot-diameter penstocks. The powerhouse
at the downstream base of the dam will provide space for four
50,000-kilowatt generating units, two of which will be installed
initially. The two initial units will produce, during an average
year, 456 million kilowatt-hours of energy. The switchyard will
be located on the left bank downstream from the powerhouse. The
reservoir formed by the Table Rock Dam will be one unit of a
comprehensive plan for flood control and other purposes in the
White River Basin and will control the runoff from an area of
approximately 4,020 square miles. The reservoir will have a total
654          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

storage capacity of about 3,462,000 acre-feet, of which 760,000
will be for flood control and 2,702,000 for the generation of hydro-
electric power. The reservoir will have an area of 52,300 acres
at top of flood control pool, elevation 931, and 43,100 acres at top
of power pool, elevation 915. The reservoir area will be developed
for recreational purposes and provisions will be made for con-
servation of wildlife.
   The estimated cost of the project (July 1954) is $72,931,000
for construction and $5,769,000 for lands and damages, totaling
 $78,700,000.
    The existing project was authorized by the Flood Control Act
approved August 18, 1941. (See H. Doc. 917, 76th Cong., 3d sess.,
which contains the latest published map.)
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. Construction of the
access road by contract was completed. Declaration of taking
was filed on 2 tracts of land totaling 801 acres. Acquisition of
the quarry and reservoir area by hired labor was suspended during
the fiscal year. Preparation of plans and specifications by hired
labor was continued.
   The costs during the fiscal year were $351,194, all for new work.
   Condition at end of fiscal year. Preliminary work is 66 percent
complete. Preparation of plans and specifications is about 95
percent complete. The office, service buildings, utilities, access
road, and clearing of the dam site are complete. Drilling and
grouting are 30 percent complete. Land for the dam site and
work area has been acquired. The project as a whole is 3 percent
complete.
   Work remaining to complete the project includes completion of
construction plans and specifications; preparation of a master plan
for reservoir management and recreation; land acquisition for
the reservoir; relocations; construction of the dam, powerhouse,
switchyard, and appurtenances; installation of power-generating
and other allied electrical equipment; and construction of facilities
for reservoir management and recreation.
   The total costs to the end of the fiscal year were $2,664,076, all
for new work.
                                       Cost and financial summary

                                                Fiscal year ending June 30                             Total to June
                                                                                                      30, 1954, includ-
                                                                                                      ing fiscal years
                                1950           1951           1952           1953          1954         priorto 1950

New work:
                --------
   Appropriated_.              $125, 000      $100, 000     $150, 000    $2, 985, 000 -$1,349, 546          $2, 801, 460
   Cost----------------          36, 065       153, 249      120, 154     1, 246, 527       351,194          2, 664, 076


Other new work data:
                                                                      ..
    Unobligated balance, fiscal year ending June 30, 1954.-------------...                                $135,770
    Appropriated for succeeding fiscal year ending June 30, 1955-.......                                 4, 849, 546
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955..........---------.. ------------------------------                                  4, 985, 316
    Estimated additional amount needed to be appropriated for com-
       pletion of existing project-..--.....................--...................................--..---.... 70, 958,994
           FLOOD CONTROL-LITTLE ROCK, ARK., DISTRICT               655
   5. BULL SHOALS      RESERVOIR, WHITE RIVER BASIN, ARK.
    Location. The Bull Shoals Dam is located at mile 418.6 on the
White River in Baxter and Marion Counties, Ark., about 7 miles
north of Cotter, Ark., and 10 miles west of Mountain Home, Ark.
  (See sectional aeronautical chart, Tulsa sheet, scale 1:500,000.)
The Bull Shoals Reservoir extends northwest along White River to
the Ozark Beach Dam at mile 506.1 and comprises lands in Taney
and Ozark Counties, Mo., and Boone, Marion, and Baxter Counties,
Ark.
    Existing project. The project plan consists of a gravity-type
concrete dam 2,256 feet long and 258 feet in height above the
streambed, and a hydroelectric power generating plant. The dam
consists of a spillway section 808 feet long located above the river
channel and two nonoverflow sections contiguous thereto and ex-
tending into the abutments. The spillway is controlled by 17 radial
crest gates 28 feet high by 40 feet long. The flood control outlets
consist of sixteen 4- by 9-foot conduits through the dam at the base
of the spillway which are controlled by hydraulically operated slide
gates. The total capacity of the outlets is 49,000 cubic feet per
second, with the reservoir filled to the top of the power pool, eleva-
tion 654. The powerhouse at the base of the dam, on the left side
of the spillway, is provided with eight penstocks, and four 40,000-
kilowatt generating units with provisions for installation of four
additional generating units in the future. The reservoir, which is
one unit of a comprehensive plan for flood control and other pur-
poses in the White River Basin, controls the runoff from an area of
approximately 6,036 square miles. The reservoir has a total stor-
age capacity of about 5,408,000 acre-feet, of which 2,360,000 acre-
feet is for flood control and 3,048,000 acre-feet is for the generation
of hydroelectric power.
    The estimated cost of the project (July 1954) is $70,452,000 for
construction and $5,877,000 for lands and damages, totaling $76,-
329,000. The estimated cost of annual maintenance is $385,000
 (July 1954).
    The existing project was authorized by the Flood Control Act of
August 18, 1941. (See H. Doc. 917, 76th Cong., 3d sess., which
contains the latest published map.)
    Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
    Operations and results during fiscal year. Contract for reloca-
tion of Missouri State Highway No. 80 bridge over White River was
continued. One contract for road relocation was completed and
one was continued. One contract for relocation of an electric trans-
mission line was awarded and one contract for relocation of a tele-
phone line was completed. Contracts were awarded for bituminous
surfacing of two access roads, construction of information center,
and for additions to the stilling basin. Contracts were completed
for furnishing the main control switchboard, automatic telephone
system, and carrier current and machine shop equipment; and for
bituminous surfacing of the abutment connecting roads. Installa-
tion of load control, carrier current, and miscellaneous electrical
equipment by hired labor was initiated. Drilling and grouting by
hired labor were continued. Water supply wells and passenger
656           IREI()ORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

elevators were completed by contract. Land acquisition was com-
pleted on 43 tracts totaling 2,400 acres.
   Ordinary operation and maintenance of the project were con-
tinued. No major repairs or replacements of flood control or elec-
trical generating equipment were required during the fiscal year.
A total of 334,661,000 kilowatt-hours of electrical energy was de-
livered to the Southwestern Power Administration for sale.
   The results of operation of the Bull Shoals Reservoir for flood
control are shown under the heading, "White River Basin, Little
Rock district."
   The costs during the fiscal year were $2,303,779, of which $1,-
989,074 was for new work and $314,705 was for maintenance.
   Condition at end of fiscal year. Construction of the project
was initiated in April 1946 and the project was ready for beneficial
use for flood control in February 1951 and for generation of elec-
trical energy in September 1952. The dam and appurtenances are
98 percent complete, and the powerhouse and appurtenances are 97
percent complete. The project as a whole is 98 percent complete.
   Work remaining to complete the project includes completion of
relocation work and land acquisition; installation of switchboards,
transformers, and load control, carrier current, and machine shop
equipment; surfacing of access roads; drilling and grouting; addi-
tions to stilling basin; information center; and miscellaneous minor
construction work by hired labor.
   The costs to the end of the fiscal year were $75,213,641, of which
$74,605,954 was for new work and $607,687 was for maintenance.
                                      Cost and financial su rmrary

                                              Fiscal year ending June 30                              Total to June
                                                                                                     30, 1954, includ-
                                                                                                     ing fiscal years
                               1950          1951            1952          1953          1954          prior to 1950

New work:
   Appropriated          $512,901, 500 $16, 272, 000     $14, 960.000     $995, 000     $768, 800         $75, 097, 300
   Cost- .......          15,028,377    15, 412, 982      13, 731, 952   5, 097, 450   1, 989, 074         74, 605, 954
Maintenance:
   Appropriated . _ _ ...... .  _ . ------------              51,461       256, 000      306, 000             613, 461
   Cost ..-..-                               - -              51, 276      241, 705      314, 705             607, 687


Other new work data:
    IUnobligated balance, fiscal year ending June 30, 1954-...............--------------.$230, 740
    Appropriated for succeeding fiscal year ending June 30, 1955........-------. 931, 200
    Unobhgated balances available for succeeding fiscal year ending
                                                                             . .........
      June 30, 19551..........................................................          1,165, 293
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project..----------....................................          300, 500
     Unobligated balance for maintenance, fiscal year ending June 30,
        1954 .. ..                                  ..                                                        3, 353


          6. NORFORK RESERVOIR, WHITE RIVER BASIN, ARK.
   Location. The Norfork Dam is located on the North Fork River
about 4.8 miles above its confluence with the White River, near
Norfork, Baxter County, Ark. (See U. S. Geological Survey map
for Mountain Home, Ark., quadrangle, scale 1:125,000). Norfork
Reservoir extends northward from the dam across Baxter County,
Ark., into Ozark County, Mo.
           FLOOD CONTROL-LITTLE ROCK, ARK., DISTRICT              657
    Existing project. The plan of improvement consists of a con-
crete gravity-type dam 2,624 feet long and 222 feet in height above
the streambed. The dam consists of a spillway section 568 feet
long located above the river channel and two nonoverflow sections
contiguous thereto and extending into the abutments.
    The spillway is controlled by 12 radial crest gates 28 feet high
and 40 feet long. The flood control outlets consist of eleven 4- by
6-foot conduits through the dam at the base of the spillway which
are controlled by hydraulically-operated slide gates. The total
capacity of the outlets is about 23,000 cubic feet per second with
the reservoir filled to top of power pool, elevation 552. The power-
house at the base of the dam on the right side of the spillway is
provided with two penstocks and two 35,000-kilowatt generating
units. Two additional penstocks are provided through the dam for
installation of additional generating units in the future.
    The reservoir, which is one unit of a comprehensive plan for flood
control and other purposes in the White River Basin, controls 1,806
square miles, or practically the entire drainage area of the North
Fork River. It has a total storage capacity of about 1,983,000 acre-
feet, of which 732,000 acre-feet is for flood control and 1,251,000
is for generation of power.
    The estimated cost of the project (July 1954) is $27,508,000 for
construction and $1,192,000 for lands and damages, totaling $28,-
700,000. The estimated cost for annual maintenance is $260,000
  (July 1954).
    The existing project was authorized by the Flood Control Act ap-
proved June 28, 1938, as amended by the Flood Control Act
approved August 18, 1941. (See H. Doc. 290, 77th Cong., 1st sess.,
which contains the latest published map.)
    Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
    Operations and results during fiscal year. Six contracts for
furnishing miscellaneous electrical equipment were awarded, 4
were completed, and 1 was continued. Three contracts for bitu-
minous surfacing of access roads were awarded and 1 was com-
pleted. Removal of the test tainter gate by hired labor was
completed. Water supply wells were completed by contract. Con-
struction of sanitary facilities for public use by contract was con-
tinued. Installation of powerhouse control lighting by hired labor
was initiated.
    Ordinary operation and maintenance of the project were con-
tinued. No major repairs or replacements of flood-control or elec-
trical generating equipment were required during the fiscal year.
A total of 132,752,700 kilowatt-hours of electrical energy was de-
livered to the Southwestern Power Administration for sale.
    The results of operating Norfork Reservoir for flood control are
shown under the heading, "White River Basin, Little Rock dis-
trict."
    The costs during the fiscal year were $342,507, of which $95,639
was for new work and $246,868 was for maintenance.
    Condition at end of fiscal year. Construction of the project is
essentially complete. Construction was initiated in October 1940
and the project was ready for beneficial use for flood control in
658                  REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

June 1943 and for generation of electrical energy in June 1944.
  Work remaining to complete the project includes the procure-
ment and installation of miscellaneous electrical equipment and
construction of facilities for reservoir management and recreation.
  The total costs to the end of the fiscal year were $30,376,080, of
which $28,269,432 was for new work and $2,106,648 was for main-
tenance.
                                                  Cost and financial summary

                                                        Fiscal year ending June 30                          Total to June
                                                                                                           30, 1954, nclud-
                                                                                                           ing fiscal years
                                           1950        1951        1952          1953           1954         priorto 1950

New work:
   Appropriated --------                  $744,053     $98, 000    $3, 400   _              -$100, 000         $28, 700, 000
   Cost---------------                   1, 400, 161   192, 574   124, 444       $63,074         95, 639        28, 269, 432
Maintenance:
   Appropriated                            227, 000    250, 000   233, 500       210, 500      237, 000          2, 111, 400
    Cost............----------------..    256, 857     249, 489   226, 786       212, 369      246, 868                648
                                                                                                                 2, 106,

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954               .....------------ 430, 568
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955------..     .............-------------------------------------                 430, 568
    Unobligated balance for maintenance, fiscal year ending June 30,
      1954------------
            .----                           --   - -           --------- ------------ 4, 432


        7. CLEARWATER                           RESERVOIR, WHITE                  RIVER BASIN, MO.

   Location. Clearwater Dam is located in Wayne and Reynolds
Counties, Mo., on the Black River, 257.4 miles above its confluence
with the White River, 6 miles southwest of Piedmont, Mo., and 32
miles northwest of Poplar Bluff, Mo. (See U. S. Geological Survey
map for Piedmont, Mo., quadrangle, scale 1:62,500.) From the
dam, the reservoir extends northward and westward in Reynolds
County.
   Existing project. The plan of improvement consists of an
earthfill dam 4,225 feet long and 154 feet in height above the
stream bed. Outlet works consisting of a gate-controlled, concrete-
lined tunnel are located in the right abutment and discharge into
the river below the dam. An uncontrolled, concrete-type ogee spill-
way is located on the right abutment with overflow discharging
into Webb Valley and reentering the river at a point about 1 mile
downstream from the dam. The reservoir, which is one unit of a
comprehensive plan for flood control and other purposes in the
White River Basin, controls the runoff from an area of approxi-
mately 898 square miles. It provides storage capacity of about
391,000 acre-feet for flood control, and a permanent pool of about
22,000 acre-feet for recreational purposes and as a wildlife refuge.
   The estimated cost of the project (July 1954) is $9,125,700 for
construction and $595,500 for lands and damages, totaling $9,-
721,200. The estimated cost for annual maintenance (July 1954)
is $75,000.
   The existing project was authorized by the Flood Control Act
approved June 28, 1938. (See Flood Control Committee Doc. 1,
75th Cong., 1st sess.)
                    FLOOD CONTROL-LITTLE ROCK, ARK., DISTRICT                                                                     659
  Local cooperation. Section 2 of the Flood Control Act, approved
June 28, 1938, applies.
  Operations and results during fiscal year. Ordinary operation
and maintenance were continued. The acquisition of lands for
surcharge storage, initiated in fiscal year 1953, was deferred.
  Two noteworthy rises occurred on the Black River above the
Clearwater Reservoir during the fiscal year. Flooding was pre-
vented on an average of about 1,055 acres of cultivated land for
each rise. The results of regulation on the river stages at Poplar
Bluff, 46.4 miles downstream, are given in the following tabulation.

                           Clearwater Reservoir                                                   Poplar Bluff, Mo.'


                                         Outflow
                                       coincident     Maximum            Corre-                          Estimated
                 Peak inflow with peak                pool eleva-      sponding          Experi-         crest stage        Estimated
Date of peak in- (cubic feet) flow from                tion (feet        flood-        enced crest        without           reduction
        flow          per second)         uncon- above mean             control        stage (feet) Clearwater               in stage
                                       trolled area sea level)          storage                        Dam                     (feet)
                                        (cubic feet                    (acre-feet)                          (feet)
                                       per second)
May 2, 1954 _                 8, 000            400          503.3           18, 000              9..5              16. 0            6.5
June 10, 1954 ...             7, 100         2, 250          504. 1          19, 800              9. 2              14. 7            5. 5


1 Appreciable overflow begins at 12 feet.


   The pool elevation at the beginning of the fiscal year was 495.01
feet above mean sea level, corresponding to 23,570 acre-feet of total
storage; and was 494.55 feet above mean sea level at the end of
the fiscal year, corresponding to 22,820 acre-feet of total storage.
The maximum pool elevation during the fiscal year was 504.10 feet,
corresponding to 41,720 acre-feet of total storage. Sufficient re-
leases were made from the reservoir during the low-water periods
to supply municipal water for Poplar Bluff and for other usages.
The conservation pool elevation was fluctuated during the warm
months as an aid in the control of mosquitoes.
   The costs during the fiscal year were $103,952, of which $49,232
was for new work and $54,720 was for maintenance.
   Condition at end of fiscal year. The project is complete. Con-
struction was initiated in June 1940, and the project was ready for
beneficial use in March 1948.
   The total costs to the end of the fiscal year were $10,070,446, of
which $9,714,730 was for new work and $355,716 was for main-
tenance.
                                             Cost and financial summary

                                                       Fiscal year ending June 30                                      Total to June
                                                                                                                      30, 1954, includ-
                                                                111                                                   ing fiscal years
                                   i 1950             1951            1952             1953              1954           prior to 1950

New work:
    Appropriated--..------......       $59,960    -$306,000      -_---_ .-              -
                                                                                       ...- .-       -$33, 602               $9, 714, 730
    Cost-_---------------              183, 280      432, 165     $188,722             $24,027          49, 232               9, 714, 730
Maintenance:
    Appropriated ......                 52, 000       51,000           66, 645          63, 200           56, 500               360, 345
    Cost_                               57, 863       54, 582          64, 127          66, 008           54, 720               355, 716


Unobligated balance for maintenance, fiscal year ending June 30, 1954 ...........
                                                                            $4,497
660      REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

8. CRAWFORD COUNTY LEVEE DISTRICT, ARKANSAS RIVER, ARK.
   Location. This project is located on the left bank of the Arkan-
sas River from a point near the eastern limits of the city of Van
Buren, Ark. (mile 352.7) to a point near the mouth of Frog Bayou
(mile 331.9), Crawford County, Ark. (See U. S. Geological Survey
map for Fort Smith (Ark.) quadrangle.)
   Existing project. The plan of improvement consists of a com-
pacted earthfill levee, approximately 19.8 miles long, extending
from the downstream end of the Van Buren, Ark., project at mile
352.7 downstream to mile 332, near the mouth of Frog Bayou.
This levee follows the alinement of a former levee except at loca-
tions where encroachments of the river made it advisable to set
the levee farther from the banks. Six new drainage structures,
equipped with floodgates, have been built. The existing project
for the Crawford County levee district, which is a modification of
the previously authorized flood control project, provides protection
for approximately 15,060 acres of rural lands and communities by
a levee having a 11/-foot freeboard above a confined flood profile
based on a flow of 800,000 cubic feet per second in the river. The
modified project differs from the previously authorized project in
that it provides a levee grade about 7 feet higher and a compacted
earthfill embankment.
   The estimated Federal cost of the project (July 1954) is $2,-
003,000 for construction and the estimated cost to local interests
for lands and damages is $86,000, a total of $2,089,000.
   The existing project was authorized by section 3 of the Flood
Control Act approved August 18, 1941, and modified by: Section
10 of the Flood Control Act approved December 22, 1944; section
3 of the Flood Control Act approved July 24, 1946; and by section
203 of the Flood Control Act approved June 30, 1948. (For latest
printed maps, see H. Doc. 447, 78th Cong., 2d sess.)
   Local cooperation. Assurances of local cooperation were sub-
mitted by local interests and were approved by the Secretary of
War on April 17, 1947.          All rights-of-way have been fur-
nished.
   Operations and results during fiscal year. Construction of a
setback levee in the vicinity of river mile 338 was initiated by con-
tract January 4, 1954, and completed March 18, 1954. The work
consisted of the placement of 282,601 cubic yards of compacted
levee embankment, and seeding and fertilizing. The setback levee
was transferred .to local interests for operation and maintenance
on April 5, 1954.
   The costs during the fiscal year were $49,226, all for new work.
   Condition at end of fiscal year. The project is complete.
   The total costs to the end of the fiscal year were $2,001,820, all
for new work.
              FLOOD CONTROL-LITTLE ROCK, ARK., DISTRICT                                          661
                             Cost and .I;nan ialsum m.ary/

                                      Fiscal year en(ling June 30                        Total to June
                                                                                           1954, includ-
                                                                                          g30,
                                                                                        ing fiscal years
                      1950          1951         1952         1953           1954         prior to1950
New work:
   Appropriated      $300, 000   -- $116, 054   $131, 354    --
                                                              _          -$140,   180        $2,001,820
   Cost.                 641
                      293,          357,
                                       229         11, 737     $2, 289        49,
                                                                                226           2, 001,820


            9. FROM NORTH LITTLE ROCK TO GILLETT,                                   ARK.
                        (ABOVE PLUM BAYOU)
   Location. The project is located in Pulaski and Jefferson
Counties, Ark., along the left bank of the Arkansas River between
river miles 163 and 105. (See U. S. Geological Survey State map
of Arkansas, scale 1:500,000.)
   Existing project. This improvement comprises the upstream
portion of the entire project for flood control extending from North
Little Rock to Gillett, Ark. The portion of the project considered
herein consists of a system of levees and necessary drainage struc-
tures along the left bank of the Arkansas River from North Little
Rock downstream to and along the right bank of Plum Bayou in
the vicinity of Rob Roy, Ark. The work comprises about 50 miles
of earthfill levee and 38 drainage structures, of which 29 are cor-
rugated metal pipe, 5 are reinforced concrete, and 4 are corrugated
metal pipe extensions. The project provides for the protection
of communities and about 550,000 acres of agricultural lands.
The levee has a freeboard above the confined flow line of the
1927 flood of 3 feet for that portion of the levee upstream from
the Jefferson County Free Bridge (mile 115.6-1940 survey), and
2 feet downstream from that point to Plum Bayou. The portion of
this levee project below Plum Bayou is under the jurisdiction of the
Vicksburg District.
   The existing project was authorized by the Flood Control Act
approved June 22, 1936. (See H. Doc. No. 308, 74th Cong., 1st
sess., which contains the latest published maps.)
   The Federal cost of the completed project is $845,300 for new
work, and the estimated cost to local interests for lands and dam-
ages is $65,000.
   Local cooperation. All requirements of local cooperation have
been fulfilled.
   Operations and results during fiscal year. Surveys and studies
were conducted by hired labor to review the existing profile of the
levee as constructed to determine whether the grade of certain
portions should be modified under present conditions and the esti-
mated cost of such revisions, if any.
   The costs during the fiscal year were $4,386, all for new work.
662          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Condition at end of fiscal year. The project is complete. Con-
struction was begun May 31, 1938, and the project was completed
October 18, 1939.
   The costs to the end of the fiscal year were $845,300 for new
work, including $86,724 from Emergency Relief funds.

                                      Cost and financial summary

                                                   Fiscal year ending June 30                   Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                               1950             1951               1952      1953   1954        prior to 1950

New work:
   Appropriated ------------          ------------------------------------          $4, 386         1 $845, 300
   Cost--------          ------------------------------------                   -    4,386           1845, 300

  1Includes $86,724 Emergency Relief funds.


10. SOUTH BANK ARKANSAS RIVER (HEAD OF FOURCHE ISLAND
                          TO PENNINGTON BAYOU), ARK.

   Location. This project is located on the right bank of the
Arkansas River, beginning at mile 161.4, near the eastern limits of
the city of Little Rock, Pulaski County, Ark., and extending down-
stream to mile 141.1. (See U. S. Geological Survey State maps,
scale 1:500,000.)
   Existing project. The plan of improvement consists of a com-
pacted earthfill levee along the right bank of the Arkansas River,
between miles 161.4 and 141.1, thence across Pennington Bayou
and Harris Bayou to high ground, about 3 miles east of Hensley,
Ark. The levee, about 19.1 miles long, follows in general the aline-
ment of the existing levees along the river. Fifteen drainage
structures are provided for interior drainage.
   The existing project which is a modification of a previously au-
thorized flood control project provides protection for approximately
32,000 acres of rural land in three separate levee systems known as
the Fourche Island levee, the Fourche Place levee, and the Woodson
levee, by a levee having a 11/2 -foot freeboard above a confined flood
profile based on a flow of 800,000 cubic feet per second in the Ar-
kansas River. The modified project differs from the previously au-
thorized project in that it provides a levee grade about 2 feet
higher and a compacted earthfill embankment.
   The estimated Federal cost of the project (July 1954) is $1,-
358,200 for the construction and the estimated cost to local inter-
ests for lands and damages is $71,064, a total of $1,429,264.
   The existing project was authorized by section 3 of the Flood
Control Act approved August 18, 1941, and modified by section 10
of the Flood Control Act approved December 22, 1944. (For latest
printed maps, see H. Doc. 447, 78th Cong., 2d sess.)
   Local cooperation. Assurances of local cooperation were sub-
mitted by local interests and approved by the Secretary of War
on February 28, 1947. All rights-of-way have been furnished.
   Operations and results during fiscal year. Repair of a slide
                   FLOOD CONTROL-LITTLE ROCK, ARK., DISTRICT                                               663
in the project levee was initiated by hired labor September 11,
1953, and completed October 21, 1953. The work consisted of the
removal of unsatisfactory material and the placement of about
11,000 cubic yards of compacted levee embankment. That portion
of the project which had not been transferred to local interests
for operation and maintenance was transferred to the Woodson
Levee District on December 9, 1953.
  The costs during the fiscal year were $6,268, all for new work.
  Condition at end of fiscal year. The project is complete.
  The total costs to the end of the fiscal year were $1,358,151, all
for new work.
                                       Cost and financial summary

                                              Fiscal year ending June 30                          Total to June
                                                                                                 30, 1954, includ-
                                                                                                 ing fiscal years
                                1950         1951        1952        1953          1954           prior to 1950

New work:
   Appropriated_          _    $459, 560   -$90, 000                -- $1, 000   -$7,      408         $1, 358, 151
   Cost ....----------------    428,375      231, 726    $96,013           517          6, 268          1, 358,151



        11. ARKANSAS              RIVER        BASIN,      LITTLE           ROCK        DISTRICT
   Location. These improvements are located on tributaries of
the Arkansas River and are in the State of Arkansas. More defi-
nite locations of the individual items are given in the following
paragraphs:
   Existing project. The Flood Control Act approved June 28,
1938, approved the general comprehensive plan for flood control
and other purposes in the Arkansas River Basin as set forth in
Flood Control Committee Document 1, 75th Congress, 1st session,
with such modifications thereof as in the discretion of the Secre-
tary of War and the Chief of Engineers may be advisable, and
authorized the sum of $21 million for reservoirs, for the initiation
and partial accomplishment of the plan, the reservoirs to be
selected and approved by the Chief of Engineers, subject to the
provision that the authorization shall include the Canton Reser-
voir on the North Canadian River in Oklahoma, as set forth in
House Document 569, 75th Congress, 3d session. The Flood Con-
trol Act approved August 18, 1941, modified the general compre-
hensive plan to include the reservoirs in the Grand (Neosho)
River Basin in Oklahoma and Missouri and in the Verdigris River
Basin in Kansas in accordance with the recommendations of the
Chief of Engineers in House Documents 107 and 440 of the 76th
Congress, 1st session, and, in addition to previous authorizations,
the latter act authorized to be appropriated the sum of $29 million
for the prosecution of the comprehensive plan. The Flood Control
Act approved December 22, 1944, authorized to be appropriated the
sum of $35 million, the Flood Control Act approved July 24, 1946,
authorized to be appropriated the sum of $40 million, and the Flood
Control Act approved May 17, 1950, authorized to be appropriated
the sum of $15 million, in addition to previous authorizations for
the continued prosecution of this comprehensive plan. The reser-
664            REPORT OF CHIEF OF ENGINEERS. U. S. ARMY. 1954

voirs within the Little Rock district included in the comprehensive
plan are listed below:
                                                 Reservo irs

                                Dis-                     Drain-                       Reser-      Power
                                tance                      age      Height of          voir      develop-      Final
   Name           River        above       Nearest        area     dam above         capacity     ment         cost
                               mouth        town          (sq.     streambed           (acre-     (kilo-
                               (miles)                   miles)     and type           feet)      watts)

Blue Moun-     Petit Jean_..     74.4    Blue Moun-        488    115 feet; earth-    258, 000     (2)      $4, 771, 050
  tain.'                                   tain, Ark.               fill.
Nimrod '-_     Fourche La        62.6    Nimrod, Ark.      680    97 feet; con-      336, 000      ( )       3, 772, 420
                 Fave.                                            crete-gravity.


1 For details of this project, see individual report.
2 None.
3 Includes provision for future power installation.


   Blue Mountain and Nimrod Reservoirs were selected and ap-
proved for construction by the Chief of Engineers in accordance
with the above authorization, and individual reports on the two res-
ervoirs are given in the following pages. All operations and costs
previously reported under the heading "Arkansas River Basin, Lit-
tle Rock district" for those two projects are now contained in the
individual reports.

12. BLUE MOUNTAIN RESERVOIR, ARKANSAS RIVER BASIN, ARK.
   Location. The Blue Mountain Dam is located in Yell County,
Ark., on the Petit Jean River about 74.4 miles above its confluence
with the Arkansas River, and about 12 miles south of Paris, Logan
County, Ark. Blue Mountain Reservoir extends westward from
the dam into Logan County. (See U. S. Geological Survey map for
Magazine, Ark., quadrangle, scale 1: 125,000.)
   Existing project. The plan of improvement provides for the
construction of an earthfill dam about 2,800 feet long and about 115
feet in height above the stream bed. Outlet works consist of a
gate-controlled, concrete lined tunnel through the right abutment,
discharges from which are directed back into the Petit Jean River
at a point about 3,000 feet below the dam. An uncontrolled saddle
spillway is located on the left abutment, about 1,200 feet down-
stream from the dam axis. The reservoir, which is one unit of a
comprehensive plan for flood control and other purposes in the Ar-
kansas River Basin, controls 488 square miles, or approximately
46 percent of the total drainage area of the Petit Jean River. It
provides storage capacity of about 233,000 acre-feet for flood con-
trol, and a permanent pool of about 25,000 acre-feet for recrea-
tional purposes and as a wildlife refuge.
   The cost of the completed project is $4,225,163 for construction
and $545,887 for lands and damages, totaling $4,771,050. The
estimated cost (July 1954) of annual maintenance, is $65,000.
   The existing project was authorized by the Flood Control Act
approved June 28, 1938. (See Flood Control Committee Doc. 1,
75th Cong., 1st sess.)
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
                     FLOOD CONTROL-LITTLE ROCK, ARK., DISTRICT                                                                                    665
    Operations                 and results during fiscal year.                                                  Ordinary mainte-
nance and operation of the project were continued.
   Two notable rises occurred on the Petit Jean River during the
fiscal year. Flooding was prevented on an average of about 6,260
acres of improved land for each flood. The results of flow regula-
tion on river stages at Danville are given in the following tabula-
tion. Danville is 25.6 miles downstream from the dam and just
downstream from the mouth of Dutch Creek which is the principal
tributary of the Petit Jean River.

                      Blue Mountain Reservoir                                                                   Danville, Arkansas 1


                               Outflow                                        Estimated
                              coincident Maximum       Corre-                 crest stage
                 Peak inflow with peak pool eleva- sponding         Experi-    without                                                     Estimated
Date of peak in- (cubic feet flow from tion (feet      flood-    enced crest     Blue                                                      reduction
      flow       per second)    uncon- above mean control        stage (feet) Mountain                                                      in stage
                             trolled area sea level)  storage                    Dam                                                         (feet)
                              (cubic feet            (acre-feet)                 (feet)
                             per second)
Jan. 20, 1954-....              6, 500              140            388. 7              15, 200                17. 5              21. 1              3. 6
May 2, 1954...                 13, 900               30            393.4               34, 200                24. 4              27. 0              2. 6


  1 Appreciable overflow begins at 17 feet.


   The pool elevation at the beginning of the fiscal year was 385.87
feet above mean sea level, corresponding to 30,370 acre-feet of
total storage. At the end of the fiscal year the pool elevation was
384.93 feet above mean sea level, corresponding to 27,490 acre-feet
of total storage. The maximum pool level during the fiscal year
was 393.4 feet above mean sea level, corresponding to 58,800 acre-
feet of total storage. The conservation pool elevation was fluctu-
ated during the warm months as an aid in the control of mosqui-
toes. Sufficient releases were made from the reservoir during low-
water periods to supply municipal water for Danville and for other
usages.
   The costs during the fiscal year were $57,963, all for mainte-
nance.
   Condition at end of fiscal year. The project is complete. Con-
struction was initiated in May 1940 and the project was ready for
beneficial use in March 1947.
   The total costs to the end of the fiscal year were $5,181,012, of
which $4,771,050 was for new work and $409,962 was for mainte-
nance.
                                                Cost and financial summary

                                                            Fiscal year ending June 30                                              Total to June
                                                                                                                                   30, 1954, includ-
                                                                                                                                   ing fiscal years
                                         1950              1951              1952                 1953                1954              prior to 1950

New work:
    Appropriated_     _ ..               $24, 685         -$6, 500                -$215          -$4, 165                                   $4, 771, 050
   Cost __--_..            .              28, 428           48, 566                9, 736            3, 932-      -     --         --        4, 771, 050
Maintenance:
    Appropriated                          47, 000           42, 000               63, 155           56, 000           $58, 500                 413, 155
    Cost..             -                  71, 359           45, 687               60, 492           58, 206            57, 963                 409, 962


Other new work data: Unobligated balance for maintenance, fiscal year
  ending June 30, 1954                                            .............       ...........                                             $2, 978
666       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


      13. NIMROD RESERVOIR, ARKANSAS RIVER BASIN, ARK.
   Location. The Nimrod Dam is located in Perry County, Ark.,
on the Fourche La Fave River, 62.6 miles above its confluence with
Arkansas River, and about 19 miles southeast of Danville, Yell
County, Ark. (See U. S. Geological Survey map for Hot Springs,
Ark., quadrangle, scale 1: 125,000.)     Nimrod Reservoir extends
westward from the dam into Yell County.
   Existing project. The plan of improvement provides for the
construction of a concrete gravity type dam 1,012 feet long and
about 97 feet in height above the streambed. It consists of a spill-
way section 198 feet long located above the river channel, and two
nonoverflow sections contiguous thereto and extending into the
abutments. Seven gate-controlled conduits for regulating and dis-
charging flood flows are located through the base of the spillway
section. In addition, two smaller valve-controlled conduits are pro-
vided through the spillway section for regulating low flows. Pen-
stocks and provisions for future spillway gates have been installed
to provide for future power generation. The reservoir, which is
one unit of a comprehensive plan for flood control and other pur-
poses in the Arkansas River Basin, controls 680 square miles, or
approximately 60 percent of the entire drainage area of the
Fourche La Fave River. It provides storage capacity of about
307,000 acre-feet for flood control, and a permanent pool of about
29,000 acre-feet for recreational purposes and as a wildlife refuge.
   The cost of the completed project is $3,117,342 for construction
and $655,078 for lands and damages, totaling $3,772,420. The esti-
mated cost (July 1954) of annual maintenance is $65,000.
   The existing project was authorized by the Flood Control Act
approved June 28, 1938. (See Flood Control Committee Doc. 1,
75th Cong., 1st sess.)
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. Ordinary mainte-
nance and operation were continued. Radio facilities for transmis-
sion of hydrologic data were modified by installation of a 100-foot
antenna tower and elimination of radio relay station. An area li-
censed to the Arkansas Game and Fish Commission for wildlife
management purposes was developed for migratory waterfowl by
and at the expense of the licensee.
   Three notable rises occurred on the Fourche La Fave River dur-
ing the fiscal year. Flooding was prevented on an average of about
1,520 acres of improved land for each rise. The results of flood
regulation on river stages at Aplin are given in the following tabu-
lation. Aplin is 13.7 miles downstream from the dam and just
downstream from the mouth of South Fourche La Fave River
which is the principal tributary.
                  FLOOD CONTROL-LITTLE ROCK, ARK., DISTRICT                                                                         667
                            Nimrod Reservoir                                                             Aplin, Ark.'

                                      Outflow
                                   coincident        Maximum            Corre-                           Estimated
                    Peak inflow with peak            pool eleva-      sponding            Experi-         crest stage         Estimated
Date of peak in- (cubic feet flow from tion (feet                       flood-         enced crest         without             reduction
      flow       per second)    uncon- above mean                      control         stage (feet)        Nimrod               in stage
                             trolled area sea level)                   storage                              Dam                   (feet)
                                     (cubic feet                      (acre-feet)                           (feet)
                                    per second)
Jan. 21, 1954- .--        4, 850               975          345. 0           11, 800           13. 3                18. 2              4. 9
Apr. 17, 1954 ..          6, 600               400          345.4            14, 100           14. 2                17. 4              3. 2
May 2, 1954 ..           36, 000                10          359. 7          119, 600           33.0                 34. 2              1.2


  1 Appreciable overflow begins at 17 feet.


   The pool elevation at the beginning of the fiscal year was 342.66
feet above mean sea level, corresponding to 31,350 acre-feet of total
storage. At the end of the fiscal year the pool elevation was 343.27
feet above mean sea level, corresponding to 33,700 acre-feet of total
storage. The maximum pool level during the fiscal year was 359.7
feet above mean sea level, corresponding to 148,600 acre-feet of
total storage. The conservation pool was lowered gradually during
the warm months as an aid in the control of mosquitoes. Sufficient
releases were made from the reservoir during low-water periods to
supply water requirements downstream.
   The costs during the fiscal year were $57,579, all for mainte-
nance.
   Condition at end of fiscal year. The project is complete. Con-
struction was initiated in January 1940 and the project was ready
for beneficial use in January 1942.
   The total costs to the end of the fiscal year were $4,378,918, of
which $3,772,420 was for new work and $606,498 was for mainte-
nance.
                                           Cost and financial summary

                                                       Fiscal year ending June 30                                      Total to June
                                                                                                                      30, 1954, includ-
                                                                                                                       ing fiscal years
                                    1950             1951            1952               1953             1954               prior to 1950
New work:
     Appropriated-........         $163, 461         $10, 000   ____________           -$1, 941 ... -                          $3, 772, 420
     Cost------------ --            167, 629          60, 790        $17, 585              4, 352 ----          .               3, 772, 420
Maintenance:
    Appropriated                     59, 000          59, 500         60, 400            41, 000         $57, 500                  609, 333
    Cost     ---                     72, 611          62, 696         61, 545            40, 565          57, 579                  606, 498


Other new work data: Unobligated balance for maintenance, fiscal year
  ending June 30, 1954.....--................................................................................. $2,758
668             REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

                    14. INACTIVE             FLOOD            CONTROL PROJECTS

                                                            For last    Cost to June 30, 1954        Estimated
                                                        full report                                    amount
                  Name of project                             see                                     required
                                                            annual        Con-         Operation         to
                                                             report    struction          and         complete
                                                              for-                    maintenance
                                                    1
1. BlackRiver,PoplarBluff, Mo., toKnobel,Ark                 1953       $584, 315                  2 $4, 151, 270
2. Carden's Bottom drainage district No. 2,                  1951        919, 955    ............... (A)
     Arkansas River, 4- Ark.    - -
3. Clarksville, Ark. ......._.......           .....         1953                                         268, 000
4. Conway County levee districts Nos. 1, 2, and   1952                 1, 018, 840      _.....           (3).
                                                                                                           )
     8, Arkansas River, Ark.
5. Conway County levee district No. 6-------
                                        ........--
                                             4
                                                   1952                   390, 952                        (8)
6. East Poplar Bluff and Poplar Bluff, Mo. ....   1953                    39, 927                        814, 073
7. Faulkner County, Arkansas River, Ark.. __.                1941         99, 511                        (3)
8. Fort Smith, Arkansas River, Ark.......__ _                1951     51, 077, 546......                 (3)
9. Little Rock, Arkansas River, Ark.._-------                1951        883, 227 -.....                 (3)
10. McLean Bottom levee district No. 3, Ark-                  1950        422, 549 .......                ()
       ansas River, Ark.
11.   Near Dardanelle, Arkansas River, Ark _ _..             1953         198,   069 .-.........          (3)
12.
13.
      Newport, W hite River, Ark _    -     r------
      North Little Rock, Arkansas River, Ark_...
                                                             1941
                                                             1943
                                                                          314,   276 -                    (3)
                                                                          501,   639    ..--------        (3)
14.   Roland drainage district, Arkansas River,              1950         269,   907     -                (S)
       Ark.
15. Skaggs Ferry, Black River, Ark-.....___ ..               1941          81, 023 ..-                    (3)
16. South Bank Arkansas River (Tucker Lake),                 1950         376, 597 ........               (3)
      Ark.
17. Van Buren, Arkansas River, Ark      .....------------    1952         438, 222                        (8)
18. Village Creek, White River and Mayberry                  1941         532, 310                        (8)
      districts, Ark.
19. West of Morrilton, Arkansas River, Ark ----              1953       1, 191, 359   ....                898, 641

  1 In conformance with provisions of sec. 2 of the 1941 Flood Control Act, local interests were notified
October 1, 1952, that authorization for construction of the Missouri portion of the project will expire 5 years
from that date unless assurances of local cooperation satisfactory to the Secretary of the Army are received
prior to that date.
  2 For Missouri portion (Arkansas portion completed).
  $ Completed.
  4 Awaiting appropriation of funds for construction.
  5 Excludes work completed with contributed funds in the amount of $8,604.
  SAwaiting local cooperation.


                              15. GENERAL INVESTIGATIONS
   Examinations and surveys. The costs during the fiscal year
were $69,784, all for special studies.
   The balance unexpended June 30, 1954, including accounts re-
ceivable, $1,062, will be applied during the fiscal year 1955 to pay-
ment of outstanding liabilities and other expenses to be incurred
under this heading.
   Additional funds in the amount of $65,000 can be profitably
expended during the fiscal year 1955 for a comprehensive investi-
gation of the Arkansas, White, and Red River Basins.
   Collection and study of basic data. Ninety-four gaging sta-
tions were operated during the fiscal year, 38 of which were oper-
ated cooperatively by the U. S. Geological Survey and the Corps of
Engineers, and the remainder independently by one or the other
of these agencies. Suspended sediment samples were collected
at 40 stations during the fiscal year in cooperation with the U. S.
Geological Survey and suspended loads were determined at cer-
tain stations.    Approximately 120 rainfall and/or river re-
porting stations were operated in a cooperative program by the
U. S. Weather Bureau and the Corps of Engineers for use in fore-
casting stream flow for flood warning and operation of reservoir
projects. Records also were collected at certain hydro-climatic
rainfall stations under a cooperative program of the two agencies.
Two storm studies were under way during the fiscal year and
                  FLOOD CONTROL-LITTLE ROCK, ARK., DISTRICT                                                        669

general hydrologic studies relating to stream flow frequency and
distribution were initiated.
  The costs during the fiscal year were $2,565, of which $902 was
for storm studies and $1,663 was for flood investigations.
      16. INSPECTION OF COMPLETED FLOOD CONTROL WORKS
  Approved regulations for operation and maintenance of flood
control works, part 208 of title 33, Code of Federal Regulations,
provide for semiannual inspection of completed projects which
have been transferred to local interests for operation and mainte-
nance.
  Inspections of the local flood protection projects included under
this heading were made during the fiscal year to determine the
extent of compliance with approved regulations for maintenance
and operation of these projects. Responsible officials of the im-
provement districts concerned were advised of inadequacies in the
maintenance and operation of the local flood protection works
under this jurisdiction where appropriate.
  The costs during the fiscal year were $2,660, all for maintenance.
  The total costs to the end of the fiscal year were $9,000, all for
maintenance.
                                                Cost and financial summary

                                                       Fiscal year ending June 30                        Total to June
                                                                                                       130, 1954, includ-
                                                                                                        Ing fiscal years
                                         1950        1951        1952           1953       1954          prior to 1950
Maintenance:
   Appropriated                                       $2, 000     $2, 500        $2, 000    $2, 500               $9, 000
   Cost .. _____...    .             .      .   I      1, 793      2, 449         2, 098      2, 660               9, 000



  17. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
   Emergency bank protection (Section 14 of the 1946 Flood Con-
trol Act).
   Work accomplished under this heading during the fiscal year
consisted of the construction of emergency bank stabilization on
the left bank of the White River near Newport, Ark. The work,
which was initiated by contract February 6, 1954, and completed
March 29, 1954, consisted of the placing of 6,000 linear feet of
piling and 6,400 tons of rock.
   The costs during the fiscal year were $48,117, all for new work.
   The total costs to the end of the fiscal year were $87,025, all for
new work.
   The costs to the end of the fiscal year from contributed funds
were $74,535.
                                                Cost and financial summary

                                                       Fiscal year ending June 30                        Total to June
                                                                                                        30, 1954, includ-
                                                                                                        ing fiscal years
                                     1950            1951        1952           1953       1954           prior to 1950
New work:
   Appropriated                                      $11,092    --------    I     --       $48, 117            1 $87, 025
   Cost ...--         ---..   ...-                                                          48,117             1 87,025


SExcludes contributed funds in the amount of $74,535.
670           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  Flood control emergencies--repairand flood fighting and rescue
work. (Section 210 of the 1950 Flood Control Act and supple-
mental authorizations.)
  Work accomplished under this heading during the fiscal year
consisted of planning for a setback levee in the Dardanelle drain-
age district and repairs to the From North Little Rock to Gillett,
Ark., levee in the vicinity of Arkansas river mile 126. The repair
work was initiated April 13, 1954, and completed June 25, 1954,
by hired labor and consisted of the removal of about 10,000 cubic
yards of objectionable material in an area of slides and the placing
of 30,000 cubic yards of compacted levee embankment.
  The costs during the fiscal year were $12,345, all for mainte-
nance.
  The total costs at the end of the fiscal year were $473,754, all
for maintenance.
                                    Cost and financial summary

                                           Fiscal year ending June 30                       Total to June
                                                                                           30, 1954, includ-
                                                                                           ing fiscal years
                             1950        1951        1952        1953          1954         prior to 1950

Maintenance:
   Appropriated ......     -- $18, 009   $18, 000   $112, 509    $11, 364    -$78, 309             $484, 100
   Cost _    __        _       62, 630        283     20, 625      19, 965       12, 345            473, 754


Other new work data: Unobligated balance for maintenance, fiscal year
  ending June 30, 1954 ......                                         $10, 346
    IMPROVEMENTS OF RIVERS AND HARBORS IN THE
              TULSA, OKLA., DISTRICT
   This district comprises southern Kansas, small portions of
southwestern Missouri and west Arkansas, northern Oklahoma,
the northern portion of the Texas Panhandle, and small portions
of northeastern New Mexico and southeastern Colorado embraced
in the drainage basin of the Arkansas River, and its tributaries
above the mouth of the Poteau River, inclusive, and below the
mouth of Walnut Creek near Great Bend, Kans., exclusive of that
portion of the watershed of the South Canadian River and its
tributaries west of the Texas-New Mexico State line; and a portion
of western Arkansas, the northern portion of the State of Texas,
and the southern portion of the State of Oklahoma embraced in the
drainage basin of the Red River and its tributaries above Fulton,
Ark.
                                                  IMI PROVE MENTS

                        Navigation
  1. Arkansas River and tribu-
                                                         Page   I          Flood control-Continued
                                                             15. Hulah Reservoir, Caney River,
                                                                                                                            Page

       taries, Ark. and Okla.............                671       Okla ....                                                686
  2. Inactive navigation projects ----..                 672 16. Strawn      Reservoir, Grand
                                                                   (Neosho)      River  Basin,
                      Flood control                                     K a n ...   -------------------------------------   687
                                                              17. Carthage, Mo .......-.................                    688
3. Hutchinson, Arkansas River,                               18. Pensacola Reservoir, Arkan-
       Kans ............. ..... ..... ........           672         sas River Basin, Okla............                      689
4. Wichita and Valley Center,                                19. Fort Gibson Reservoir, Ar-
       Kans .......... ....... .... ..........           673         kansas River Basin, Okla.... .                         690
5. Tulsa and West Tulsa, Ar-                                20. Tenkiller Ferry Reservoir, Ar-
      kansas River, Okla......... ......                 675        kansas River Basin, Okla......                          692
6. Fort Supply Reservoir, North                             21. Wister Reservoir,                    Arkansas
      Canadian River, Okla...........                    676        River Basin, Okla .. ..... ..........                   694
7. Canton Reservoir, Arkansas                               22. Arkansas River Basin, Tulsa
      River Basin, Okla..........-.....                  677        District ................................               695
8. Oklahoma            City         Floodway,               23. Denison Dam (Lake Texoma)
      North Canadian River, Okla                         679        Red River, Tex. and Okla......                          696
9. Great Salt Plains Reservoir,                             24. Red River below Denison Dam,
      Salt Fork of Arkansas River,                                  Tulsa District ................                         698
      O k la .............. ..........................   680 25. Millwood           Reservoir,             Little
10. Keystone Reservoir, Arkansas                                    River, Ark..............................                699
      River, Okla --..................                   681 26.
                                                                  Inactive Flood Control Proj-
11. Polecat Creek, Okla. (Heyburn                                   e c ts -- - - - - - - - - - - - - - - - - - - -
      Reservoir and channel im-                                                                                             700
      provements) .............                          682 27. General Investigations ......-                             701
12. Fall River Reservoir, Arkan-                             28. Inspection of Completed Proj-
      sas River Basin, Kans ...........                  683        ects ..................... ...............              702
13. Toronto Reservoir, Arkansas                              29. Flood Control Work Under
      River Basin, Kans .....                            684        Special Authorization............                       702
14. Oologah Reservoir, Arkansas                              30. Scheduling of Flood Control
      River Basin, Okla................                  685        Reservoir Operations-..............                     703

      1. ARKANSAS RIVER AND TRIBUTARIES, ARKANSAS AND
                         OKLAHOMA
  A consolidated report on this project for the Vicksburg, Little
Rock, and Tulsa districts, submitted by the Little Rock District,
Southwestern Division, is on page 643.
                                                                                                                  671


           Sig 22--671-702
672           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                      2.   INACTIVE          NAVIGATION             PROJECTS

                                                    For last    Cost and expenditures
                                                                      June 30, 1954   to        Estimated
                                                  full report                                   amount
                Name of project                        see                                      required
                                                    annual         Con-          Maintenance       to
                                                    report       struction                      complete
                                                     for-

1. Red River from Fulton, Ark., to mouth of          1924          $378, 574        $182, 157      (1)
    Washita River, Okla.'


  'Curtailment of project is recommended in H. Doc. 947, 64th Cong., 1st sess.
   'Maintenance only.


                  3. HUTCHINSON, ARKANSAS RIVER, KANS.
   Location. The project is located on the Arkansas River and
Cow Creek, a tributary of the Arkansas River, in the immediate
vicinity of Hutchinson, Kans. (See U. S. Geological Survey maps
for Lyons and Hutchinson, Kans. quadrangles, scale 1:125,000.)
   Existing project. The project provides for a diversion chan-
nel and a system of levees to protect the city of Hutchinson, Kans.,
and vicinity from floodwaters of Arkansas River and Cow Creek,
starting at river mile 817 on the Arkansas River and extending
about 9 miles upstream. The plan of improvement consists of a
300-foot-wide leveed diversion canal approximately 1 mile west of
the city limits of Hutchinson, intercepting Cow Creek at mile 14.9
above its mouth and carrying floodwaters from the creek south
for about 2 miles to enter the Arkansas River upstream from
Hutchinson. The levee on the left bank of the diversion canal
starts at the hills about 41/2 miles north of the canal to intercept
all of Cow Creek floodwaters. The combined flow of the creek and
the river is confined past the city by levees on both sides of the
river, forming a 1,000-foot floodway. The flanking levee on the
left bank of the Arkansas River has an opening at about mile 821
at the mouth of the present Harsha drainage canal. Protection
against backwater of the Arkansas River up the existing canal is
provided by increasing the height of the existing levees. Addi-
tional protection is provided to a rural area west of the diversion
canal by a loop levee, and to the urban area of the Island Park
subdivision, northwest of Hutchinson, by a ring levee.
   The flanking levee on the right bank of the Arkansas River,
which protects the town of South Hutchinson, starts at mile 822.3
above the mouth of the river and extends downstream to mile
818.5.
   The estimated Federal cost (1954) is $4,020,000 and the esti-
mated non-Federal cost is $2,274,000.
   The existing project was authorized by the Flood Control Act
approved June 22, 1936. (See House Document 308, 74th Con-
gress, 1st Session, which contains the latest published maps.)
   Local cooperation. Resolutions by the city of Hutchinson,
agreeing to meet the requirements were submitted by the city
under the dates of March 16 and 30, 1945, and were approved by
the Secretary of War on July 4, 1945. The city of Hutchinson
has granted rights of entry for the entire project. The city has
secured the necessary assurances from the State of Kansas that
highways would be relocated in accordance with the project plan,
                     FLOOD CONTROL-TULSA, OKLA., DISTRICT                                                          673
and all required utility relocations under contract.
   Operations and results during the fiscal year. Construction of
a flanking levee along the left bank of the Arkansas River and in-
cluding a diversion channel, a training levee, and improvements
to the existing Harsha drainage canal, was continued from 73 to
100 percent completion, by continuing contract. Relocations and
alterations to existing railroad facilities were continued from 33
to 86 percent of completion under cost-reimbursable contracts.
Construction of a flanking levee along the right bank of the river
adjacent to the City of South Hutchinson was started September
15, 1953, and completed February 10, 1954, by contract. The last
phases of the project, consisting of two ring-levee areas west and
northwest of Hutchinson, were started, by contract, on May 13,
1954, and the work continues.
   The cost of new work during the fiscal year was $1,714,818.
   Condition at end of fiscal year. Construction operations were
initiated April 10, 1952, by contract. Completed portions of the
project have been transferred to the city of Hutchinson, for mainte-
nance and operations. The entire project is 89 percent complete
and all work required to complete the Federal portion of the proj-
ect has been contracted.
   The total cost of new work to the end of the fiscal year was
$3,313,366.
                                       Cost and financial summary

                                                    Fiscal year ending June 30                           Total to June
                                                                                                        30, 1954, includ-
                                                                                                        ing fiscal years
                                1950             1951           1952           1953          1954         prior to 1950

New work:
   Appropriated----   ---.---              . -$1, 180, 000   $1, 900, 000   $1, 393, 000    $447, 000        $4, 020, 000
   Cost- ..----- ------          34, 564            9, 020        45,815     1,300,201     1, 714,818         3, 313, 366


Other new work data :
    Unobligated balance, fiscal year ending June 30, 1954..-.....-........ -  $522, 167
    Unobligated balances available for succeeding fiscal year ending June 30,
        1955          ...       ..............-------------------
                                                              ----------.........                            522, 167


4. WICHITA AND VALLEY                              CENTER, ARKANSAS RIVER, KANS.

  Location. The project is located on the Arkansas River, and
Little Arkansas River and Chisholm Creek, tributaries of the
Arkansas River, in the immediate vicinity of Wichita and Valley
Center, Kans. (See U. S. Geological Survey map for Wichita,
Kans., quadrangle, scale 1:125,000.)
  Existing project. The project provides for a diversion chan-
nel and a system of levees to prevent flooding in the Cities of
Wichita and Valley Center, Kansas, and environs, starting at a
point 760 miles above the mouth of the Arkansas River and extend-
ing upstream about 33 miles. Under the plan Little Arkansas
River will be diverted into the Arkansas River by means of a flood-
way beginning at a point about 2 miles northwest of Valley Center
and extending southward to the Arkansas River (at river mile
785.7) about 9 miles northwest of Wichita. The flows of Chisholm
Creek and its middle and west branch tributaries will be collected
674      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

by a system of levees and channels north of Wichita and diverted
across the Little Arkansas River into the Arkansas River (at mile
780). The combined flows of the Little Arkansas River, Chisholm
Creek, and Arkansas River will be confined and diverted to the
west of the city by a floodway, with existing stream channels
being utilized to carry flood flows to the limit of their capacity.
This by pass floodway will begin at a point about 3.1 miles down-
stream from the Kansas State Highway 96 river crossing and will
provide a channel having a normal bottom width of 80 feet and an
average depth of 10.9 feet. Levees flanking the floodway will, in
general, be spaced 900 feet center to center with an average height
of 8.5 feet and a crown width of 8 feet or more. From the Arkansas
River the floodway would extend southwest 2 miles to intercept
Big Slough, along Big Slough for 5 miles, thence south and south-
east 2.5 miles to intercept Cowskin Creek, along Cowskin Creek
for 2 miles, thence east, and southeast about 5 miles entering the
Arkansas River approximately 1 mile northwest of Derby, Kans.
 (at river mile 760). Existing levees and drainage canals previously
constructed by local interests, are being enlarged, strengthened, or
rectified as required. The completed system with five control
structures will provide about 91.2 miles of levee.
   The estimated Federal cost (1954) is $13,300,000 and the esti-
mated non-Federal cost is $6,580,000.
   The existing project was authorized by the Flood Control Act,
approved June 22, 1936. (See H. Doc. 308, 74th Cong., 1st sess.,
which contains the latest published maps.)
   Local cooperation. The city of Wichita has furnished assur-
ances of local cooperation for the entire project which were ap-
proved by the Secretary of War on February 25, 1946. Right of
entry has been granted the entire project except in the Chisholm
Creek area. Acquisition of the right-of-way for this remaining
portion of the project is under way by local interests.
   Operations and results during the fiscal year. Construction of
the project was continued from 21 to 37 percent completion, by
contract. The work accomplished was on the Big Slough-Cowskin
Floodway west and south of the city. Additional construction,
consisting of 10.7 miles of training levee, flanking the Arkansas
River northwest of the city, was initiated, by contract. Negoti-
ations were continued with railroad companies whose facilities
will be affected and engineering and design studies in connection
with preparation of contract plans and specifications for comple-
tion of the project were continued, all by hired labor.
   The cost of new work during the fiscal year was $1,780,731.
   Condition at end of fiscal year. Construction by contract for
clearing, snagging, widening, and otherwise improving the exist-
ing East Branch interception canal and Wichita drainage canal,
initiated on May 8, 1950, was completed August 23, 1950. This
portion of the project was transferred to the City of Wichita,
Kansas, on February 7, 1951, for future maintenance and opera-
tion. Construction was continued on Big Slough-Cowskin Flood-
way, the largest single feature of the project. Work on this fea-
ture started June 9, 1950, and at the end of the fiscal year Big
                       FLOOD CONTROL-TULSA, OKLA., DISTRICT                                                    675
Slough-Cowskin Floodway was approximately 62 percent complete,
including the required relocations. Construction of the lower
segments (parcel "A", phases I and II) are complete except for
certain gaps where work is held in abeyance pending the com-
pletion of railroad bridge crossings. The third segment (parcel
"B", phase I) was started February 25, 1953, and the work is under
way, by continuing contract. The project as a whole is 37 per-
cent complete. In general, the work required to complete the
project, in addition to Big Slough-Cowskin Floodway, consists of
construction of the Little Arkansas River Floodway and Chisholm
Creek Diversion Canal.
  The total cost of new work to the end of the fiscal year was
$4,817,819.
                                        Cost and financial summary

                                                 Fiscal year ending June 30                          Total to June
                                                                                                     30, 1954, includ-
                                                                                                     ing fiscal years
                                 1950         1951          1952          1953           1954         prior to 1950

New work:
    Appropriated  _   _
                      _..____     _------   _------------_ $500, 000   $1, 990, 000   $1, 100, 000        $5, 753, 000
    Cost----------------   $161, 785      $378,521         149, 499     2, 018, 849    1, 780, 731         4, 817, 819


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954------..................----..    $368,333
    Appropriated for succeeding fiscal year ending June 30, 1955 .........--- 1,800,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955 .........  .............   ......    . . ..............               2, 168, 333
                                                                             .......------------------------------------
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project _... . _ _-.....    ..........        ..                5, 747, 000

        5. TULSA AND WEST TULSA, ARKANSAS RIVER, OKLA.
  Location. The project is located on the Arkansas River at
Tulsa and West Tulsa, Okla. (See U. S. Geological Survey maps,
Hominy, Okla., and Claremore, Okla., quadrangles, scale 1:125,-
000.)
   Existing project. The project consists of a system of levees
to prevent flooding at Tulsa, West Tulsa, and Sand Springs, Okla.,
starting at a point on the Arkansas River about 521.3 miles above
the mouth and extending upstream approximately 10 miles. The
plan of improvement provided for raising the existing left-bank
levee, connecting the discontinuous portions of the levee and
constructing a leveed floodway up Black Boy Creek with levees
and diversion ditches eastward and westward thereof, and raising
the existing right-bank levee to grade and constructing the neces-
sary appurtenances thereto. The left bank levee begins at mile
531.3 above the mouth of the Arkansas River and ends at mile
524.0. The right bank levee begins at mile 526.7 and ends at mile
521.3.
  The estimated Federal cost (1954) is $2,785,100. The estimated
non-Federal cost for lands, rights-of-way, and damages is $265,000.
  The levees and appurtenant works were authorized by the Flood
Control Act approved August 18, 1941. (See H. Doc. 157, 77th
Cong., 1st sess., which contains the latest published maps.)
  Local cooperation. Fully complied with.
676                  REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Operations and results during fiscal year. Installation of auto-
matic type gate on 108-inch storm sewer, started during the prior
fiscal year, was completed, by contract.
   The cost of new work during the fiscal year was $3,907.
   Condition at end of fiscal year. The completed project was
accepted by Drainage District No. 12, Tulsa County, Okla., on
August 7, 1945, and has been maintained and operated at no cost
or expense to the Federal Government. However, as a result of
survey and based upon experience at other projects, a large un-
gated storm sewer under the levee has been protected by instal-
lation of automatic gates. Such installation will preclude the
possibility of sewer joint failure due to the extreme pressures
which will be exerted on the land side during flood stages of the
river.
   The total costs of new work to the end of the fiscal year were
$2,785,070.
                                                 Cost and financial summary

                                                         Fiscal year ending June 30                     Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                                          1950          1951          1952       1953       1954        priorto 1950

New work:
   Appropriated..__               .      -- $3, 618 _    -$5,                         000    -$912          $2, 785, 070
   Cost.---------........----..       -------------           ----------------
                                                           -----                      181     3, 907         2, 785, 070




6. FORT SUPPLY RESERVOIR,                                      NORTH CANADIAN                 RIVER, OKLA.
   Location. Fort Supply Reservoir is located on Wolf Creek, a
tributary of the North Canadian River, about 12 miles northwest
of Woodward, Woodward County, Okla.             (See sectional aero-
nautical chart, Wichita sheet, scale 1:500,000.)
   Existing project. The plan of improvement consists of an
earthfill dam and concrete spillway with a total length of 11,865
feet, rising 85 feet above the stream bed, the reservoir providing
for storage of 92,700 acre-feet for flood control and 13,400 acre-
feet for a permanent pool for recreation and preservation of wild-
life, or a total storage of 106,000 acre-feet. The outlet works,
consisting of a semi-elliptical conduit controlled by three 7 - by
16-foot vertical-lift gates, and a stilling basin, are located in the
left abutment. A concrete chute-type spillway, 540 feet long,
controlled by a concrete weir at the upstream end, provides for
the passage of flood flows around the left end of the dam. The
reservoir controls 1,735 square miles, or practically the entire
drainage area of Wolf Creek, and is operated as a unit of the co-
ordinated reservoir system for flood control in the Arkansas River
Basin.
   The costs were $7,232,649 for construction and $245,000 for
lands and damages, a total of $7,477,649. The estimated cost of
annual maintenance is $69,000 (1954).
   The existing project was authorized by the Flood Control Act
approved June 22, 1936. (See H. Doc. 308, 74th Cong., 1st sess.)
  Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
                       FLOOD CONTROL-TULSA, OKLA., DISTRICT                                                   677
   Operations and results during the fiscal year. All completed
structures were operated and maintained in a serviceable con-
dition throughout the year, by hired labor.
   The costs during the fiscal year were $50,799, all for mainte-
nance.
   Condition at end of fiscal year. Construction of the project is
complete. Mobilization for construction of the project was started
in March 1938. After a construction camp had been built, actual
construction work on the dam was started during October 1938,
by contract. Four years later, the project was placed in operation.
However, after the temporary construction camp office building
had deteriorated, the last item of construction, consisting of erec-
tion of a prefabricated steel maintenance building, was completed
on March 31, 1952, by hired labor. No additional new work con-
struction is presently scheduled for this project.
   Total receipts frontoutleasing Government-owned land through
fiscal year 1954 amount to $19,141. Such receipts are not in-
cluded in the cost and financial summary shown below.
   The total cost of new work to the end of the fiscal year was
$7,477,649, of which $7,390,611 was from regular funds and
$87,038 was from Emergency Relief funds. The total cost of
maintenance was $549,228 all from regular funds.
                                         Cost and financial summary

                                                   Fiscal year ending June 30                      Total to June
                                                                                                   30, 1954, includ-
                                                                                                   ing fiscal years
                                  1950          1951         1952         1953          1954        prior to 1950

New work:
   Appropriated
   Cost .
                  - ..-----------------
                       - $116,          500
                                    30,322
                                              -$55, 500
                                                   5, 515
                                                            -$2, 275
                                                               22,888
                                                                           -$76
                                                                            -76
                                                                                    _                  I $7, 477, 649
                                                                                                       1 7,477,649
Maintenance:
   Appropriated     ------         80, 000       60, 000      55, 371     44, 600       $49, 200            549, 571
   Cost-----------------          85, 437        55, 562      56, 776     47, 532        50, 799            549, 228

I Includes   $87,038 Emergency Relief funds.

     7. CANTON RESERVOIR,                           ARKANSAS RIVER BASIN, OKLA.

   Location. Canton Reservoir is located on the North Canadian
River about 394 miles above its mouth and about 3 miles north
of Canton, Blaine County, Okla.        (See sectional aeronautical
chart, Wichita sheet, scale 1: 500,000.)
  Existing project. The plan of improvement consists of an
earthfill dam and concrete spillway with a total length of 15,100
feet, rising 73 feet above the riverbed, with a reservoir providing
for the storage of 260,000 acre-feet for flood control and 130,000
acre-feet for conservation of water and siltation reserve, or a
total storage capacity of 390,000 acre feet. Of the conservation
storage, 69,000 acre-feet is allocated for future irrigation and
38,000 acre-feet is allocated for future municipal water supply.
The outlet works consist of three 7- by 12-foot gated sluices
through the spillway weir. A concrete spillway, controlled by
sixteen 40- by 25-foot gates on the weir crest, provides for the
passage of flood flows around the right end of the dam. The
reservoir controls 12,641 square miles, and is operated as a unit
678            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

of the coordinated reservoir system for flood control in the Ar-
kansas River Basin.
  The costs were $9,607,622 for construction and $719,953 for
lands and damages, a total of $10,327,575. The estimated cost
of annual maintenance is $103,000 (1954).
   Authorizations for the project are listed below:

               Act                            Work authorized                          Documents and reports
Flood Control Act June 28,1938.    Construction of dam and appurtenant               House Document       569. 75th
                                     facilities.                                   Congress, 3d Session.
Flood Control Act July 24, 1946.   Irrigation storage in the reservoir.          In accordance with Section 8
                                                                                   of Flood Control Act of
                                                                                   December 22, 1944.
Flood Control Act June 30, 1948.   Water supply storage in the reservoir.        In accordance with Section 6
                                                                                   of Flood Control Act of
                                                                                   December 22, 1944.



   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. All completed struc-
tures were operated and maintained in a serviceable condition
throughout the fiscal year, by hired labor. Construction of ad-
ministration and maintenance buildings, the last item of project
construction, was completed December 15, 1953, by contract.
   The costs during the fiscal year were $58,517 for new work and
$95,666 for maintenance.
   Condition at end of the fiscal year. The project as a whole is
complete. Actual construction work on the dam was initiated in
December 1940 and impoundment was commenced April 15, 1948.
No additional new work construction is presently scheduled for
this project.
   Total receipts from outleasing Government-owned land through
fiscal year 1954 amounts to $57,775. Such receipts are not included
in the cost and financial statement shown below.
   The total cost of new work to the end of the fiscal year was
$10,327,575 and the total cost of maintenance was $530,380.
                                      Cost and financial summary

                                               Fiscal year ending June 30                           Total to June
                                                                                                    30, 1954, includ-
                                                                                                    ing fiscal years
                               1950         1951          1952            1953           1954         priorto 1950

New work:
   Appropriated........       $165,000      $81, 000                      $59, 600                      $10, 327, 575
    Cost_------------          178, 787     108, 830      $2, 619           2, 483       $58, 517        10, 327, 575
Maintenance:
   Appropriated..--------      106, 500      85, 000      76, 347         102, 206        83, 800            531, 153
   Cost----------------        105, 420      74, 972      85, 809          91, 213        95, 666            530, 380
                      FLOOD CONTROL--TULSA, OKLA., DISTRICT                                    679
8. OKLAHOMA CITY FLOODWAY, NORTH CANADIAN RIVER, OKLA.
   Location. The project is located on the North Canadian River
at Oklahoma City, Okla. (See U. S. Geological Survey map,
Chickasha, Okla, quadrangle, scale 1: 125,000.)
   Existing project. The plan of improvement consists of an
enlarged and straightened channel through the city, designed
to carry 45,000 cubic feet per second. The improvement will be
about 13.4 miles in length, beginning about 1 mile upstream from
South May Avenue (river mile 273.7) and extending to the vi-
cinity of Spencer, Okla. (river mile 257.5). The major part of
the improvement will be about 13 feet deep and will have a bot-
tom width of 425 feet. The side slopes will be lined with stone.
Natural drainage ways will be modified to drain into the canal by
the construction of 15 lateral drainage ditches. Excavated ma-
terial will be placed in old channel and low areas.
   The estimated Federal cost (1954) is $10,500,000 and the non-
Federal cost is $7,020,000.
   Local cooperation. Local interests advised that the city of
Oklahoma City was in process of acquiring rights-of-way for the
entire project. Rights of entry have been furnished for the lower
half of the project.
   Authorizations for the project are listed below:

               Act                          Work authorized             Documents and reports
Flood Control Act July 24, 1946.   Channel improvement with levees.   House Document      572, 79th
                                                                       Congress, 2d Session.
Flood Control Act May 17, 1950.    Canal plan of improvement.         Report of OCE.



   Operations and results during fiscal year. Construction of the
first segment of the floodway (vicinity of 4th Street to the down-
stream limits) was completed and second segment (vicinity of
Robinson Avenue to 4th Street) was initiated on April 24, 1954,
and continued to 3 percent completion, by continuing contract.
Negotiations, by hired labor, were continued with owners of the
railroad facilities requiring alteration or relocation due to con-
struction of the floodway.
   The cost during the fiscal year was $1,388,408, all for new work.
   Condition at end of fiscal year. Construction of the first seg-
ment of the floodway is complete. Railroad negotiations and con-
struction of the second segment are under way. Considering the
project as a whole, 19 percent of all required work has been ac-
complished and the work continues.
   The total cost to the end of the fiscal year was $2,027,977, all
for new work.
680            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                        Cost and financial summary

                                               Fiscal year ending June 30                         Total to June
                                                                                                 30, 1954, includ-
                                                                                                 ing fiscal years
                                1950          1951        1952         1953          1954         priorto 1950

New work:
   Appropriated--........------------      -- $216, 000 ............   796, 000   $1, 500, 000        $2, 680, 000
   Cost----------------        $92, 616       40, 369      $8, 249     372, 417    1,388, 408          2, 027, 977

Other new work data:
                                                                        $378, 645
    Unobligated balance, fiscal year ending June 30, 1954.......................
                                                                       1,650, 000
    Appropriated for succeeding fiscal year ending June 30, 1955.............
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955 ---.......................................................
                                                                    .. 2,028,654
    Estimated additional amount needed to be appropriated for com-
                                                                         170, 000
      pletion of existing project........:........................................

9. GREAT SALT PLAINS RESERVOIR, SALT FORK OF ARKANSAS
                      RIVER, OKLA.
   Location. Great Salt Plains Reservoir is located on the Salt
Fork of the Arkansas River 103.3 miles above its mouth, and about
12 miles east of Cherokee, Alfalfa County, Okla. (See sectional
aeronautical chart, Wichita sheet, scale 1: 500,000.)
   Existing project. The plan of improvement consists of an
earthfill dam and spillway 6,010 feet long, rising 72 feet above the
riverbed, with a reservoir providing for the storage of 245,300
acre-feet for flood control and 46,700 acre-feet for siltation, recre-
ation, and preservation of wildlife, or a total storage capacity of
292,000 acre feet. A concrete cascade-type spillway 310 feet wide,
containing three gravity-type concrete weirs, provides for the pas-
sage of flood flows around the right end of the dam into the river
valley below. The outlet works consist of four ungated 10- by 12-
foot conduits through the center section of the upper weir. The
reservoir controls 3,200 square miles, and is operated as a unit of
the coordinated reservoir system for flood control in the Arkansas
River Basin.
   The costs were $4,109,831 for construction and $488,800 for
lands and damages, a total of $4,598,631. The estimated cost of
annual maintenance is $62,000 (1954).
   The existing project was authorized by the Flood Control Act
aproved June 22, 1936. (See H. Doc. 308, 74th Cong., 1st sess.,
which contains the latest published maps.)
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. The project struc-
tures were operated and maintained in a serviceable condition
throughout the year, by hired labor.
   The cost for maintenance during the fiscal year was $49,784.
   Condition at end of fiscal year. Construction of the project is
complete. Mobilization for construction of the project was started
in May 1938. After a construction camp had been built, actual
construction work on the dam was initiated on September 28, 1938.
Approximately three years later the project was placed in opera-
tion during July 1941. No additional new work construction is
presently scheduled for this project.
                   FLOOD CONTROL--TULSA, OKLA., DISTRICT                                              681
   Collections from outleasing Government-owned land amount to
a total of $3,715 through fiscal year 1954. Such receipts are not
included in the cost and financial summary tabulated below.
   The total cost of new work to the end of the fiscal year was
$4,598,631, of which $4,573,887 was from regular funds and $24,-
744 was from Emergency Relief funds. The total cost of mainte-
nance was $586,465, all from regular funds.
                                    Cost and financial summary

                                           Fiscal year ending June 30                        Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                             1950         1951        1952         1953          1954        priorto 1950

New work:
   Appropriated    -  _..   $31, 000    -$39, 052          _      -$3, 317 --- _---------       '$4, 598, 631
   Cost -----------------    75, 322       22, 009       $278 ------------------------          1 4,598,631
Maintenance:7
   Appropriated              86, 400       75, 000     38, 599     509, 994      $46, 700            586, 593
   Cost-----------------     98, 736       60, 797     51, 121      49, 070       49, 784            598, 465


  'Includes $24,744 Emergency Relief funds.


       10. KEYSTONE            RESERVOIR,            ARKANSAS                 RIVER,        OKLA.
  Location. The work covered by this project is located on the
main stem of the Arkansas River 538.9 miles above its mouth, and
about 2 miles downstream from the mouth of the Cimarron River
near Keystone, Okla., and about 15 miles west of Tulsa, Okla.
(See U.S. Geological Survey map for Hominy, Okla., quadrangle,
scale 1:125,000, Skedee and Yale, Okla., quadrangles, scale
1:62,500.)
   Existing project. The plan of improvement provides for con-
struction of a multiple purpose reservoir which will control 74,331
square miles, and which will be operated as a unit of the coordi-
nated system for flood control in the Arkansas River Basin, and as
a part of the multiple purpose plan for navigation, hydroelectric
power, flood control, and other purposes, Arkansas River and
tributaries, Arkansas and Oklahoma. Under the plan, the reser-
voir will have a total storage capacity of 1,879,000 acre-feet, of
which 1,216,000 acre-feet will be allocated to flood control, 198,000
acre-feet to power, and 465,000 acre-feet will be set aside for con-
servation and sedimentation reserve of which 50,000 acre-feet
would be for water supply. The dam will consist of an earthfill
structure with a gate-controlled concrete spillway located in the
river channel and rising 123 feet above the streambed. The struc-
ture will be 4,650 feet long, with the power intake and powerhouse
located adjacent to the spillway. Power design criteria at present
provide for installation of three 20,000 kilowatt units, a total of
60,000 kilowatts.
   The estimated costs (1954) are $58,680,000 for construction and
$94,320,000 for lands and damages, a total of $153,000,000.
   The existing project was authorized by the Flood Control Act
approved May 17, 1950, (see Senate Document 107, 81st Congress,
1st session, which contains the latest published map.)
  Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
682                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Operationsand results during fiscal year. Preparation of engi-
neering design memoranda were continued, by hired labor.
   The cost for new work during the fiscal year was $129,037.
   Condition at end of fiscal year. Engineering studies and inves-
tigations required prior to initiation of construction contract plans
and specifications are essentially complete.
   The total cost of new work to the end of the fiscal year was
$629,277. This amount includes the sum of $214,000 expended on
the previously authorized Mannford Reservoir, replaced by Key-
stone Reservoir authorized by the 1950 Flood Control Act.
                                                 Cost and financial summary

                                                             Fiscal year ending June 30                                      Total to June
                                                                                                                            30, 1954, includ-
                                                                                                                            ing fiscal years
                                         1950              1951             1952              1953             1954           prior to 1950
New work:
   Appropriated........------------------------
                         .........----          $150,000                                    $161, 000        $126,297                 $651, 297
   Cost-.-..-.....-.... ........- .-   $1, 405   77, 966                                     208,273          129,037                  629,277

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954...................--------------                                                $7, 020
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955...............           -------------------------------------.                                                        7, 020
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project-------------------------...................................................----.................. 152, 348, 703

       11. POLECAT CREEK, OKLA. (HEYBURN RESERVOIR                                                                              AND
                    CHANNEL IMPROVEMENTS)
   Location. Polecat Creek is a minor tributary to the Arkansas
River near Sapulpa, Creek County, Okla. (See U. S. Geological
Survey maps for Nuyaka, Hominy, and Claremore, Okla., quad-
rangles, scale 1:125,000.)
   Existing project. The plan of improvement provides for flood
protection in the Polecat Creek Valley by means of a reservoir at
mile 48.6, near Heyburn, Okla., which controls 123 square miles
and channel improvements at Sapulpa on Rock Creek, its major
tributary, and on Polecat Creek below the mouth of Rock Creek.
The Heyburn Dam is an earthfill structure 2,920 feet long and
rising 89 feet above the streambed with the reservoir providing a
storage capacity of 49,500 acre-feet for flood control and 10,200
acre-feet for siltation, recreation and preservation of wildlife, a
total of 59,700 acre-feet. Outlet works consist of an uncontrolled
ci'cular drop inlet conduit. An uncontrolled saddle spillway,
located about 1,000 feet west of the right abutment, provides for
the passage of flood flows into the river below. The channel of
Rock Creek from mile 4.4 to the mouth has been cleared by re-
moval of debris and about 1.3 miles of this length is deepened.
The channel of Polecat Creek is cleared from the mouth of Rock
Creek, mile 21.2 to the Arkansas River.
   The Federal costs were $1,758,900 for construction and $615,200
for lands and damages in the Heyburn Reservoir area, a total of
$2,374,100. The estimated non-Federal cost is $113,000. The
estimated cost of annual maintenance is $40,000 (1954).
                          FLOOD CONTROL-TULSA, OKLA., DISTRICT                                                        683
   The existing project was authorized by the Flood Control Act
approved July 24, 1946, (see House Document No. 290, 80th Con-
gress, 1st session, which contains the latest published maps.)
   Local cooperation. Section 2 of the Flood Control Act, ap-
proved June 28, 1938, applies to the Heyburn Reservoir. Channel
improvement works have been transferred to local interests for
operation and maintenance.
   Operationsand results during fiscal year. All completed struc-
tures were operated and maintained in a serviceable condition
throughout the fiscal year, by hired labor.
   The costs during the fiscal year were $507 for new work and
$37,716 for maintenance.
   Condition at end of fiscal year. Construction of the project is
complete. Construction of the dam, by contract, was started
March 9, 1948, and completed October 11, 1950. Embankment
closure was completed June 25, 1950, and the pool was filled to
conservation level by March 1951. Channel improvements below
the reservoir were completed September 24, 1952. No additional
new work construction is presently scheduled for this project.
   Total receipts from outleasing Government-owned land through
fiscal year 1954 amount to $10,952. Such receipts are not included
in the cost and financial statement shown below.
   The total costs of new work to the end of the fiscal year were
$2,374,100 for new work and $128,799 for maintenance.
                                               Cost and financial summary

                                                     Fiscal year ending June 30                             Total to June
                                                                                                            30, 1954, includ-
                                                                                                            ing fiscal years
                                        1950        1951          1952         1953             1954          priorto 1950

New work:
   Appropriated--------......          $900, 000   $225, 000 .....           -$50, 900 ......------------        $2, 374, 100
   Cost.----------------                724, 075    274, 892      $66, 682      28, 169             $507,         2, 374, 100
Maintenance:
   Appropriated ....................                 24, 000       36, 801       30, 400         37, 700            128,901
   Cost-__--. -----.... -- _.-..               -     21, 926       34, 993       34, 164         37, 716            128, 799



12. FALL RIVER RESERVOIR, ARKANSAS RIVER BASIN, KANS.
  Location. Fall River dam is located on the Fall River about
54 miles above its confluence with the Verdigris River and about
4 miles northwest of Fall River, Greenwood County, Kans. (See
U. S. Geological Survey map for Eureka, Kans. quadrangle, scale
1:125,000.)
   Existing project. The plan of improvement consists of an
earthfill dam and concrete spillway with a total length of about
6,015 feet and rising 94 feet above the streambed with a reservoir
providing for the storage of 236,000 acre-feet for flood control
and 27,000 acre-feet for water supply, pollution abatement, silta-
tion, recreation, and preservation of wildlife, a total of 263,000
acre-feet. A concrete channel spillway, controlled by eight 50- by
25-foot gates on the weir crest, provides for passage of flood flows
into the river valley below. The outlet works consist of seven 5-
by 8.5-foot gated sluices through the spillway weir. The reservoir
684            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

which controls 585 square miles is operated as a unit of the com-
prehensive reservoir system for flood control in the Arkansas
River Basin.
   The costs were $8,505,261 for construction and $1,949,500 for
lands and damages, a total of $10,454,761. The estimated cost of
annual maintenance is $92,000 (1954).
   The existing project was authorized by the Flood Control Act
approved August 18, 1941. (See H. Doc. 440, 76th Cong., 1st sess.,
which contains the latest published map.)
   Local cooperation. Section 2 of the Flood Control Act, ap-
proved June 28, 1938, applies.
   Operations and results during fiscal year. All project struc-
tures were operated and maintained in a serviceable condition
throughout the year, by hired labor.
   The costs for maintenance during the fiscal year were $73,671.
   Condition at end of fiscal year. Construction of the dam was
started on May 9, 1946, by contract. Embankment closure was
completed May 30, 1949, the conservation pool was filled by June
9, 1949, and dedication ceremonies were held September 5, 1949.
No additional new work construction is presently scheduled for
this project.
   Total receipts from outleasing Government-owned land through
fiscal year 1954 amount to $142,428. Such receipts are not in-
cluded in the cost and financial summary shown below.
   The total cost of new work to the end of the fiscal year was
$10,454,761 and the total cost of maintenance was $379,969.
                                     Cost and financial summary

                                              Fiscal year ending June 30                      Total to June
                                                                                             30, 1954, includ-
                                                                                             ing fiscal years
                              1950          1951         1952        1953         1954         prior to 1950
New work:
   Appropriated   --         $250, 000   -$262, 600                 -$5, 239                     $10, 454, 761
     os£_              --     333, 645       124, 877    $8, 507      -- 2, 384                   10, 454, 761
Maintenance:
   Appropriated- ..--          95, 000       70, 000      77, 583     66, 300     $73, 200            382, 083
   Cost__-_--------_  ---      92, 668       64, 840      81, 951     66, 839      73,671             379, 969


   13. TORONTO              RESERVOIR,             ARKANSAS         RIVER         BASIN,        KANS.
  Location. The Toronto Dam site is located on the Verdigris
River about 271.5 miles above its mouth and 4 miles south and east
of Toronto, Woodson County, Kans. (See U. S. Geological Survey
map for Fredonia, Kans., quadrangle, scale 1:125,000.)
  Existing project. The plan of improvement provides for an
earthfill dam about 4,583 feet long, with a maximum height of 90
feet above the streambed. The spillway and control works will be
combined in a concrete structure located near the right abutment
of the dam. The reservoir will have a total capacity of 195,000
acre-feet, of which 171,000 acre-feet will be for flood control and
24,000 acre-feet for water supply, pollution abatement, siltation,
recreation, and preservation of fish and wildlife. The reservoir
which will control 730 square miles will be operated as a unit of
the comprehensive reservoir system for flood control in the
Arkansas River basin.
                          FLOOD CONTROL--TULSA, OKLA., DISTRICT                                          685
   The estimated costs (1954) are $10,797,300 for construction and
$8,902,700 for lands and damages, a total of $19,700,000.
   The project was authorized by the Flood Control Act, approved
August 18, 1941. (See H. Doc. 440, 76th Cong., 1st sess., which
contains the latest published map.)
   Local cooperation. Section 2 of the Flood Control Act, ap-
proved June 28, 1938, applies.
   Operations and results during fiscal year. Preparation of con-
struction plans and specifications and other engineering studies
for flood control features were continued by hired labor.
   The cost during the fiscal year was $5,593, all for new work.
   Condition at end of fiscal year. Construction plans and specifi-
cations have been completed to a point where the initial construc-
tion contracts could be advertised.
   Total cost of new work to the end of the fiscal year was $339,996.
                                           Cost and financial summary

                                                 Fiscal year ending June 30                     Total to June
                                                                                               30, 1954, includ-
                                                                                               ing fiscal years
                                    1950        1951        1952        1953        1954        priorto 1950

New work:
   Appropriated--------........     $50, 000    $40, 000   $122, 100    $25, 000   -$61, 500           $345, 600
     Cost.................           19, 520      9, 344    169, 877     25, 012      5, 593            339,996

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 _--                                         $5, 604
    Appropriated for succeeding fiscal year ending June 30, 1955-----------                          500, 000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955----.................----------------------------------                           505, 604
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project-----------.....-----....... .... --------......... 18,             854, 400

   14. OOLOGAH                    RESERVOIR,         ARKANSAS          RIVER       BASIN, OKLA.
   Location. Oologah Reservoir is located on the Verdigris River
90 miles above its confluence with the Arkansas River and about
10 miles northwest of Claremore, Rogers County, Okla. (See U. S.
Geological Survey maps for Claremore and Nowata, Okla. quad-
rangles scale 1:125,000.)
   Existing project. The plan of improvement provides for con-
struction of an earthfill dam 4,100 feet long and rising 129 feet
above the riverbed. The reservoir would provide for 950,000 acre-
feet for flood-control storage and 25,000 acre-feet for conservation,
a total of 975,000 acre-feet. A gated concrete conduit will be
constructed through the embankment to form the outlet works.
A gated spillway will be located in a saddle about 2 miles from the
left abutment and would provide for passage of floodwaters into
the valley below the dam.
   The estimated costs (1954) are $10,593,200 for construction,
and $20,826,800 for lands and damages, a total of $31,420,000.
   The project would be constructed initially for flood control with
power facilities added at such time that the oilfield in the upper
portion of the reservoir area is depleted. The reservoir which will
control 4,339 square miles, will be operated as a unit in the com-
prehensive plan for development of the Arkansas River Basin.
686          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


              Acts                       Work authorized                       Documents
Flood Control Act, June 28,      Construction of a flood control reser- House of Representatives Com-
  1938.                            voir.                                  mittee Document No. 1, 75th
                                                                          Congress, 1st Session.
River and Harbor Act, July 24,   Installation of hydro-electric power House Document No. 758, 79th
1946.                             facilities.                            Congress, 2d Session.



   Local cooperation. Section 2 of the Flood Control Act, ap-
proved June 28, 1938, applies.
   Authorizations for the project are listed below:
   Operations and results during fiscal year. The project is in a
stand-by status and no funds were expended during the fiscal year.
   Condition at end of fiscal year. The dam site area comprising
871 acres has been acquired. Access road to the dam site is com-
plete. Contract plans and specifications for the first phases of
construction were essentially completed by October 25, 1951.
However, all work on the plans was discontinued on that date
in view of the intent of the Civil Functions Appropriation Act,
1952.
   Total cost of new work to the end of the fiscal year was $391,810.

                                    Cost anti financial summary

                                           Fiscal year ending June 30                     Total to June
                                                                                         30, 1954, includ-
                                                                                         ing fiscal years
                             1950        1951         1952        1953         1954        priorto 1950

New work:
  Appropriated_______       $350,000 __________    _________  ___________    -$79, 190           $391, 810
   Cost____________          177,623     $90,812       $2,720      -$345    ..........            391,810


Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project                 __...
                                                               .___....          $31,028, 190
                                                                        .. ...........
                                                                    -.....




               15. HULAH RESERVOIR,                  CANEY RIVER, OKLA.

   Location. The Hulah Dam is located on Caney River 96 hiles
above its confluence with the Verdigris River and is about 15
miles northwest of Bartlesville, near Hulah, Osage County, Okla.
 (See U. S. Geological Survey maps for Pawhuska, Okla. and
Sedan, Kans. quadrangles, scale 1:125,000.)
   Existing project. The plan of improvement consists of an
earthfill dam and concrete spillway with a total length of 5,200
feet rising 94 feet above the riverbed, with a reservoir providing
for the storage of 265,000 acre-feet for flood control and 30,000
acre-feet for conservation, siltation, recreation, and preservation
of wildlife. A concrete channel spillway, controlled by ten 40- by
25-foot gates on the weir crest, provides for the passage of flood
flows over the dam into the river valley below. The reservoir,
which will control 732 square miles, is operated as a unit of the
coordinated reservoir system for flood control in the Arkansas
River Basin.
   The estimated costs (1954) are $7,911,000 for construction and
                               FLOOD CONTROL-TULSA, OKLA., DISTRICT                                                                                 687
$2,988,800 for lands and damages, a total of $10,899,800.                                                                                          The
estimated cost of annual maintenance is $84,000 (1954).
   The existing project was authorized by the Flood Control Act
approved June 22, 1936. (See H. Doc. 308, 74th Cong., 1st sess.,
which contains the latest published maps.)
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. All project struc-
tures were operated and maintained in a serviceable condition.
New work accomplished consists of construction of an overlook
building, by contract, remodeling of existing buildings to provide
family quarters suitable for operative personnel, was performed
by hired labor.
   The costs during the fiscal year were $23,120 for new work and
$64,309 for maintenance.
   Condition at end of fiscal year. The dam was constructed
under a two-phase program. Construction of the embankment
and excavation for the spillway was started May 5, 1946, and com-
pleted August 7, 1947. The second stage, consisting of the em-
bankment closure section and completion of spillway was started
April 5, 1948, and completed June 20, 1950. Impoundment to con-
servation pool level was completed- September 24, 1951. No addi-
tional new work is presently scheduled for this project. However,
final costs are outstanding.
   Collections from outleasing Government-owned land total $74,-
352 through fiscal year 1954. Such receipts are not included in the
cost and financial summary below.
   The total cost of new work to the end of the fiscal year was
$10,896,454 and the total cost of maintenance was $222,765.
                                                     Cost and financial summary

                                                                 Fiscal year ending June 30                                           Total to June
                                                                                                                                     30, 1954, includ-
                                                                                                                                     ing fiscal years
                                             1950               1951              1952               1953               1954           prior to 1950

New work:
      Appropriated-                 -$4,     248, 000         $195, 700       -$222, 839        -$102, 300               $3, 100            $10, 899 800
       ---------------
   Cost_                                   4, 571, 617       1, 158, 074         157, 690          -43, 489              23, 120             10, 896, 454
Maintenance:
     Appropriated                ....--------------------        42, 000            61, 584           55, 500            63, 900                  222, 984
     Cost---------             -----------------                 33, 694            68, 089           56, 673            64, 309                  222, 765


Other new work data:
    ITnobligated balance, fiscal year ending June 30, 1954-...-$_....                                                                                $3, 346
    Unobligated balances available for succeeding fiscal year ending June 30,
       1955..................................................................--------------------------------------------......................--...  3, 346


16. STRAWN RESERVOIR, GRAND (NEOSHO) RIVER BASIN, KANS.
  Location. The Strawn Dam site is located on the Grand (Neo-
sho) River about 358.4 miles above its mouth and 1.5 miles north-
west of Strawn, Coffey County, Kans. (See U. S. Geological Sur-
vey maps for Burlington and Emporia, Kans., quadrangles, scale
1:125,000.)
  Existing project. The plan of improvement provides for the
688            REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

construction of an earthfill dam and concrete spillway with a total
length of about 11,160 feet, with a maximum height of 78 feet
above the streambed. The concrete structure includes combined
control works and spillway having net width of 600 feet and lo-
cated in the valley near the left abutment of the dam. The reser-
voir will have a total capacity of 387,900 acre-feet, of which 320,-
600 acre-feet will be for flood control and 67,300 acre-feet for
water supply, pollution abatement, siltation, recreation and preser-
vation of fish and wildlife. The reservoir, which will control 2,927
square miles, will be operated as a unit of the reservoir system for
flood control in the Grand (Neosho) River Basin.
   The estimated costs (1954) are $15,960,000 for construction
and $26,050,000 for lands and damages, a total of $42,010,000.
   The project was authorized by the Flood Control Act approved
May 17, 1950. (See H. Doc. 442, 80th Cong., 2d sess., which con-
tains the latest published maps.)
   Local cooperation. Section 2 of the Flood Control Act, ap-
proved June 28, 1938, applies.
   Operations and results during fiscal year. Engineering and
design studies preparatory to actual preparation of construction
contract plans and specifications were completed, by hired labor.
   The cost of new work during the fiscal year was $5,000.
   Condition at end of fiscal year. Preliminary engineering and
design studies required prior to actual initiation of construction
contract plans and specifications are complete.
   The total cost to the end of the fiscal year amounts to $265,000,
all for new work.
                                         Cost and financial summary

                                                  Fiscal year ending June 30                     Total to June
                                                                                                30, 1954, includ-
                                                                                                ing   fiscal    years

                                  1950           1951           1952       1953       1954        priorto 1950

New work:
   Appropriated------..........---------------------.......... $250, 000   $10, 000   $5, 000              $265,000
   Cost-----------------------------
                             ............ ------........        197, 958    62, 042    5, 000                  265, 000

Other new work data: Estimated additional amount needed to be ap-
                                                                  $41,745, 000
  propriated for completion of existing project.....................................


                                          17. CARTHAGE, MO.
  Location. The project is located on Spring River, a tributary
of the Grand (Neosho) River in the Arkansas River Basin, in the
immediate vicinity of Carthage, Jasper County, Mo. (See U. S.
Geological Survey map for Carthage, Mo. quadrangle, scale
1:125,000.)
  Existing project. The plan of improvement provides for the
construction of a levee on the northeast side of Carthage, Mo., to
prevent flooding from Spring River and Carter Creek. The levee
would extend upstream along the south bank of Spring River for
a distance of about 1 mile. A grade elevation for the top of levee
would be so constructed as to provide a freeboard of 3 feet above
the project design flood.
                       FLOOD CONTROL-TULSA, OKLA., DISTRICT                                              689

   The estimated Federal cost (1954) is $383,000, and the esti-
mated non-Federal cost is $36,600.
   The existing project was authorized by the 1948 Flood Control
Act approved June 30, 1948. (See H. Doc. 445, 80th Cong., 2d sess.,
which contains the latest published maps.)
   Local cooperation. In addition, local interests are required to
furnish acceptable assurances that the flood carrying capacity
of the existing stream channels will not be decreased. To date,
these requirements have not been met; however, legally qualified
organization is being formed to comply with local cooperation
requirements.
   Operations and results during fiscal year. Engineering and
design studies in connection with preparation of contract plans
and specifications were essentially completed, by hired labor.
   The cost of new work during the fiscal year amounted to $4,986.
   Condition at end of fiscal year. Contract plans and specifica-
tions have been completed to a point where construction can be
initiated as soon as construction funds are appropriated.
   The total cost of new work to the end of the fiscal year was
$15,686.
                                    Cost and financial summary

                                             Fiscal year ending June 30                   *     Total to June
                                                                                               30, 1954, includ-
                                                                                               ing fiscal years
                             1950           1951        1952        1953        1954            priorto 1950

New work:
   Appropriated   --    -    $14, 300   -             -- $3, 714     $8, 600   -$3,      500            $15, 686
   Oost---------------.
                   2, 818                   $6, 966          802         114          4, 986             15, 686


Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project ......--
                                                ... ................._ .. $.
                                                                          $367, 314


18. PENSACOLA              RESERVOIR, ARKANSAS RIVER BASIN, OKLA.
   Location. Pensacola Dam is located on the Grand (Neosho)
River, 77 miles above its mouth, and adjacent to the town of Dis-
ney, Mayes County, Okla. (See U. S. Geological Survey maps for
Pryor, Wyandotte, Vinita, Okla., and Siloam Springs, Ark., quad-
rangles, scale 1:125,000.)
   Existing project. During fiscal year 1941 the Grand River
Dam Authority, an agency of the State of Oklahoma, under a
license dated July 26, 1939, issued by the Federal Power Commis-
sion, completed the construction of a reservoir for flood control
and hydroelectric power at the Pensacola site in the Arkansas
River Basin. The dam is of the concrete, multiple arch type,
6,565 feet long and 147 feet above the stream bed. The existing
dam and reservoir provides 1,653,000 acre-feet of storage to top
of power pool and 245,000 acre-feet of flood control storage. The
flood control storage lies between elevations 745 and 750. How-
ever, under the terms of the Federal Power Commission license,
the dam and appurtenant structures were constructed to a height
which would allow storage of flood waters to elevation 755 (Pen-
sacola datum) when necessary lands or rights-of-way were ac-
quired by the Federal Government.
690               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   The Flood Control Act approved August 18, 1941, modified the
general comprehensive plan for flood control and other purposes
for the Arkansas River Basin to include the Pensacola, Markham
Ferry, and Fort Gibson Reservoirs in the Grand (Neosho) River
Basin in Oklahoma and Missouri, in accordance with recommenda-
tions of the Chief of Engineers in House Document 107, 76th Con-
gress, 1st session. The improvements recommended in that docu-
ment included a reservoir for flood control at the Pensacola site
which provided for 960,000 acre-feet of flood control storage.
   The existing project now provides for making available 278,000
acre-feet of flood control storage between elevations 750 and 755
in addition to the storage provided in the project as constructed
by the Grand River Dam Authority. Flowage easements for cer-
tain portions of the necessary lands have been acquired by the
Federal Government through the Southwestern Power Admin-
istration, Department of the Interior, and the Federal Works
Agency. The estimated cost (1954) for acquisition of additional
flowage easements necessary for operation of the reservoir to ele-
vation 755 is $1,710,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. Flood control stor-
age in the pioject was operated by the Grand River Dam Authority
 (an agency of the State of Oklahoma) under the direction of the
Corps of Engineers. The Grand River Dam Authority was reim-
bursed for their expense in connection with maintaining and
operating local protection works at Wyandotte, Okla.
   The cost during the fiscal year was $2,224.
   Condition at end of fiscal year. Real estate planning studies
necessary prior to completion of the land acquisition program,
initiated by other agencies, are essentially complete.
   The total costs to the end of the fiscal year were $52,126 for new
work and $7,868 for maintenance.
                                               Cost and financial summary

                                                          Fiscal year ending June 30                                    Total to June
                                                                                                                       30, 1954, includ-
                                                                                                                       ing fiscal years
                                        1950             1951             1952            1953              1954        prior to 1950
New work:
                                                              --        $2, 261
    Appropriated----........------------ ----------............--............         .------------------------                 $52, 126
    Cost---------------- -----------                  $75                     33 ------------------------                        52, 126
Maintenance:
   Appropriated--------........     ------------           3, 200            1,000          $2, 000          $1, 700              7, 900
    Cost-           .             .------------
                                    ------------           2, 797              626           2, 221           2,224               7, 868



19. FORT GIBSON RESERVOIR, ARKANSAS RIVER BASIN, OKLA.
   Location. The Fort Gibson dam is located on the Grand (Neo-
sho) River, 7.7 miles above its mouth, and about 5 miles north
and east of Fort Gibson, Muskogee County, Okla. (See U. S. Geo-
logical Survey maps for Muskogee and Pryor, Okla., quadrangles,
scale 1:125,000.)
   Existing project. The plan of improvement consists of a con-
crete gravity-type dam, 2,850 feet long at the top, rising 110 feet
             FLOOD CONTROL--TULSA, OKLA., DISTRICT               691
above the streambed, with a reservoir providing for the storage
of 922,000 acre-feet for flood control and 365,000 acre-feet for
storage to top of power pool. The project includes a powerhouse
structure, a gate-controlled spillway, and two nonoverflow abut-
ment sections. The powerhouse structure is located on the left
bank of the existing river channel with the spillway structure ex-
tending across the river channel and a major portion of the right
bank flood plain. The reservoir, which controls 12,492 square
miles, will be operated as a unit of the three-reservoir system on
the lower Grand (Neosho) River, and as one unit in the compre-
hensive plan for the Arkansas River Basin. The hydroelectric
development consists of 4 units having an installed capacity of
45,000 kw. The ultimate planned is for 6 units with a total of
67,000 kw.
   The estimated costs (1954) are $28,842,100 for construction and
$13,157,900 for lands and damages, a total of $42,000,000. The
estimated cost of annual maintenance is $340,000 (1954).
   The War Department Civil Appropriation Act, 1947 (Public
Law 374, 79th Cong.), approved May 2, 1946, provided that in the
construction of the Fort Gibson flood control project in Oklahoma,
the Chief of Engineers is authorized and directed to cooperate
with the officials of the city of Muskogee in protecting the domestic
water supply of such city.
   The existing project was authorized by the Flood Control Act
approved August 18, 1941. (See H. Doc. 107, 76th Cong., 1st sess.,
which contains the latest published map.)
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during the fiscal year. All completed
structures were operated and maintained in a serviceable condi-
tion throughout the fiscal year, by hired labor. In general, the
new work accomplished consisted of construction of floating bulk-
head, a stop-log structure for the power intake works, mechanical
adjustments to power generating equipment, and construction of
administrative facilities, all by contract. Construction of an ad-
ministrative and maintenance building, an overlook, and a paint
and oil storage building were started, by contract, on August 6,
1953, and are now 95 percent complete.
   A total of 39,497,200 kilowatt hours was generated at this proj-
ect during the fiscal year, all of which was delivered to the South-
western Power Administration for marketing.
   The costs during the fiscal year were $473,094 for new work and
$298,448 for maintenance.
   Condition at end of fiscal year. Initial project construction be-
gan in March 1942 with the construction of temporary field office
buildings but further construction at the project was held in abey-
ance during World War II. Construction of the concrete dam and
spillway, the largest single feature of the project, started by con-
tract on May 22, 1946, was completed on June 15, 1950, at a total
cost of $17,058,525. Impoundment of the power pool was com-
pleted March 13, 1953, and dedication ceremonies were held June
6, 1953. All four power generating units have been installed and
692                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

tested. Starting dates for commercial power generation were as
follows:
   Unit No. 1-March 30, 1953; Unit No. 2-March 31, 1953;
Unit No. 3-May 29, 1953; and Unit No. 4-Sept. 2, 1953.
   As parts of the highway relocation work were constructed in
accordance with the desires of the Oklahoma Highway Depart-
ment, utilizing their specifications, the State of Oklahoma con-
tributed $34,340.12 for fiscal year 1950, and $80,933.58 during
fiscal year 1951, to defray the extra expense incurred by the Gov-
ernment in construction of the improved facilities.
   The total receipts from outleasing Government-owned land
through fiscal year 1954 amount to $451,909. Such receipts are
not included in the cost and financial summary tabulated below.
   The total cost to the end of the fiscal year was $41,642,726 of
which $40,703,415 was from regular new work funds, and $824,-
037 was from regular maintenance funds, and $115,274 was from
special funds contributed for betterments.
                                                 Cost and financial summary

                                                             Fiscal year ending June 30                                     Total to June
                                                                                                                           30, 1954, includ-
                                                                                                                           ing fiscal years
                                         1950              1951              1952             1953             1954          prior to 1950
New work:
   Appropriated- ......             $$12, 000, 000     $4, 946, 500     $2, 400, 000     -$103, 000      ------------           1   $40, 996, 500
   Cost---------------                 5, 452, 679      5, 574, 800      3, 783, 523      4, 362, 008        $473, 094              1 40,   703, 415
Maintenance:
     Appropriated ........                 58, 000         133, 500         157, 210          177, 006         302, 200                     827, 916
     Cost--------_      ---- --           53, 376          135, 365         155, 706         181, 142          298, 448                     824, 037

   1 Does not include $115,274 contributed funds.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-.............-----------$251, 554
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955------...........................................................................-----------------------------------.251, 554
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project ..............                                     ...... . ........ ...... .                       1, 003, 500

  20. TENKILLER                       FERRY RESERVOIR, ARKANSAS RIVER BASIN,
                                                OKLA.
   Location. The Tenkiller Ferry dam is located on the Illinois
River 13 miles above its confluence with the Arkansas River, and
about 7 miles northwest of Vian, and 7 miles northeast of Gore,
Sequoyah County, Okla. (See U. S. Geological Survey maps for
Muskogee, Okla. and Tahlequah, Okla. and Ark. quadrangles,
scale 1:125,000.)
   Existing project. The plan of improvement consists of an
earthfill dam 3,000 feet long and rising 197 feet above the riverbed.
The reservoir which controls 1,610 square miles provides for the
storage of 600,000 acre-feet for flood control and 630,000 acre-feet
of storage to the top of power pool or total gross capacity of
1,230,000 acre-feet. A gated concrete spillway is provided at a
saddle in the right abutment and a 19-foot diameter gated conduit
through the ridge forms the outlet works. A second 19-foot gated,
conduit, adjacent to the outlet conduit, forms a power penstock.
A dike 1,350 feet long with a maximum height of 25 feet extends
                     FLOOD CONTROI-TULSA, OKLA., DISTRICT                                         693
along the saddle ridge between the dam and spillway. The hydro-
electric development consists of 2 units with an installed capacity
of 34,000 kw.
   The estimated costs for the project (1954) are $19,451,700 for
construction and $2,988,300 for lands and damages, a total of
$22,440,000. The estimated cost of annual maintenance is $235,000
 (1954).
   Authorizations for the project are listed below:


              Act                            Work authorized                  Documents and reports
Flood Oontrol Act, June 28, 1938.1Construction of a flood control reser-   House of Representatives Com-
                                   voir.                                    mittee Document No. 1, 75th
                                                                            Congress, 1st Session.
River and Harbor Act, July 24, Installation of hydroelectric       power   House Document No. 758, 79th
  1946.                          facilities.                                 Congress, 2d Session.



   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. All completed struc-
tures were operated and maintained in a serviceable condition
throughout the fiscal year, by hired labor. Construction of the
project as a whole was continued from 97 percent to 98 percent
completion. The work accomplished consisted of mechanical ad-
justments, final installation of tainter gates and testing of power
generating equipment, by contract. Commercial sale of power
from Unit No. 2 started November 16, 1953, and from Unit No. 1
on December 3, 1953. Other new work consisted of construction
of access roads and boat launching ramps, by hired labor, and
initiation of construction on quarters for operative personnel, by
contract.
   Power generated during the fiscal year amounted to 43,337,900
kilowatt hours and was delivered to the Southwestern Power Ad-
ministration for marketing.
   The costs during the fiscal year were $329,329 for new work and
$174,400 for maintenance.
   Condition at end of fiscal year. Initial construction, consisting
of access roads, clearing dam site, and first stage embankment
construction, was started June 17, 1947. Construction of the
second stage embankment was started March 14, 1950, and com-
pleted May 2, 1952, while construction of the spillway, outlet and
diversion tunnels, gate tower and access road to the powerhouse,
was started February 9, 1949, and completed July 12, 1951.
   Except for completion of contracts now underway covering
construction of quarters for operative personnel and installation
of minor operating control equipment, the work required to com-
plete the project consists of additional public-use facilities.
   A bridge requiring relocation was constructed in accordance
with the desires of the Cherokee County highway commissioners,
utilizing their specifications. Cherokee County contributed $946
during fiscal year 1952 to defray the extra expense incurred by the
Government in constructing the improved facilities.
   Total receipts from outleasing Government-owned land through
694,              REPORT OF CHIEF OF ENGINEERS, U. S'. ARMY, 1954

fiscal year 1954 amount to $21,224. Such receipts are not included
in the cost and financial summary shown below.
   Total cost to the end of the fiscal year was $22,273,367, of which
$21,977,446 was from new work funds, $294,975 from maintenance
funds, and $946 from special funds contributed for betterments.
                                             Cost and financial sunmary

                                                         Fiscal year ending June 30                          Total to June
                                                                                                            30, 1954, includ-
                                                                                                            ing fiscal years
                                      1950            1951            1952          1953         1954        prior to 1950

New work:
   Appropriated........ $5, 500, 000 $5, 065, 000                 $3, 500, 000   $2,115, 000    $191, 700      1$22, 294, 905
   Cost._---_..-- -.....          5, 021, 867       4, 826, 268    4, 208, 569    3, 518, 689    329, 329       1 21, 977, 446
Maintenance:.
   Appropriated-          ...---------------------                    47, 800        73, 994     173, 900            295, 694
   Cost--- -------.------                  --------                   41, 366        79, 209     174,400             294, 975


  'Does not include $946 contributed funds.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 ....                                       $270, 584
                                                                                     ..........------------
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955........ -----------------------....................... ........ . ......... 270,584
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project----..........-----------------------------145,095

     21. WISTER                RESERVOIR, ARKANSAS                               RIVER BASIN, OKLA.

   Location. The Wister dam is located on the Poteau River about
61 miles above its confluence with the Arkansas River and about 2
miles south of Wister, Le Flore County, Okla. (See U. S. Geologi-
cal Survey map for Winding Stair, Okla. quadrangle, scale
1:125,000.)
   Existing project. The plan of improvement consists of an
earthfill dam about 5,700 feet long and rising 99 feet above the
riverbed, with a reservoir storage of 400,000 acre-feet for flood
control and 30,000 acre-feet for siltation, recreation, and preser-
vation of wildlife. An uncontrolled concrete spillway located in
a ridge in the right abutment provides for passage of flood flows
into the valley below the dam. The outlet works consist of two
16-foot by 12-foot 10-inch gated conduits near the present channel.
A dike about 2,400 feet long and 40 feet in maximum height is
provided in the right abutment. The reservoir, which controls
993 square miles, is operated as a unit of the coordinated reservoir
system for flood control in the Arkansas River Basin.
   The estimated costs (1954) are $7,587,700 for construction and
$2,859,300 for lands and damages, a total of $10,447,000. The
estimated cost of annual maintenance is $92,000 (1954).
   The existing project was authorized by the Flood Control Act
approved June 28, 1938. (See Flood Control Committee Doc. 1,
75th Cong., 1st sess., which contains the latest published maps.)
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
                          FLOOD CONTROL-TULSA, OKLA., DISTRICT                                                695
   Operations and results during fiscal year. The project was
operated and maintained in a serviceable condition throughout the
fiscal year, by hired labor. New work costs were applied to settle-
ment of deficiency judgments and land condemnation proceedings.
Estimated flood losses prevented by the existence of the project
amounted to $477,000 during the fiscal year and receipts from out-
leasing Government-owned land totaled $7,273.
   The costs during the fiscal year were $1,014 for new work and
$82,050 for maintenance.
   Condition at end of fiscal year. The project is essentially com-
plete and is in operation. Construction of the embankment, spill-
way and outlet works was started April 10, 1946; embankment
closure operations were started June 18, 1948, and completed May
26, 1949. However, initial storage operations were not begun
until October 4, 1949, inasmuch as the land acquisition and relo-
cation programs were not far enough advanced to permit storage
prior to that date. Dedication ceremonies were held June 16,
1951. The work remaining to financially complete the project
consists of possible settlement of outstanding claims.
   Total receipts from outleasing Government-owned land through
fiscal year 1954 amounts to $32,079. Such receipts are not in-
cluded in the cost and financial summary shown below.
   The total costs to the end of the fiscal year were $10,428,000 for
new work and $423,507 for maintenance.
                                           Cost and financial summary

                                                     Fiscal year ending June 30                      Total to June
                                                                                                    30, 1954, includ-
                                                                                                    ing fiscal years
                                    1950          1951          1952        1953         1954         prior to 1950
New work:
               --------
   Appropriated...                 $107, 321      $92, 000    -$60, 321    -$2, 000      $19, 000       $10, 447, 000
   Cost---------------            1, 044, 494     269, 823      -2, 281         659        1, 014        10, 428, 000
Maintenance:
   Appropriated--------........     107, 100       83, 800       77, 290     78, 100      80, 900           427, 190
   Cost.----------------            109, 750       77, 885       80, 867     72, 955      82, 050           423, 507


Other new work data:
    Tnobligated balance, fiscal year ending June 30, 1954 -..........                 $19,000
    Unobligated balances available for succeeding fiscal year ending June 30,
                 ......
      1955------.........    .......                         .................
                                    ...................-----------------.........----..
                                                                                .....19,000

               22. ARKANSAS                     RIVER        BASIN, TULSA              DISTRICT
  Location. These improvements are located on the Arkansas
River and tributary streams in the States of Kansas and Oklahoma.
  Existing project. The general comprehensive plan for flood
control and other purposes in the Arkansas River Basin was
adopted by Congress in 1938. The original authorization of $21
million has been modified by subsequent additions and revisions to
the plan and the present basin authorization is $283,573,000.
  The reservoirs within the Tulsa District included in the com-
prehensive plan are listed below:
696                    REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


                                                                                                          Estimated cost 1

                  Reservoir                                   River
                                                                                 Construction             Land           Relocations       Total


Canton 2.._-----_------___-_
          2 -- -- -- -- -- -- --        - --          North Canadian-                9, 607, 575            645,   200     $ 74, 800      10, 327, 575
Keystone ....................                         Arkansas---..........         58, 680, 000        10, 820,   000    83, 500, 000   153, 000, 000
Toronto 2.-        -       -.       - .......
                                       . --...._      Verdigris--..-.-....          10, 797, 300         2, 292,   000     6, 610, 700    19, 700, 000
Fall River 2_           __         -- _____ -         Fall River. -.....             8, 505, 261         1, 687,   100        262, 400    10, 454, 761
Oologah 2       __................                                  ---------
                                                      Verdigris.......              10, 593, 200         8, 311,   000    12, 515, 800    31,420,000
Tenkiller _Ferry 2-                  -           .Illinois      .    - -.. ...      19, 451, 700         1, 484, 300       1, 504, 000    22,440, 000
Wister 2_        --       .                   __      Poteau.                    -.... 7, 587, 700       1, 133, 700     1, 725, 600      10, 447, 000
Neodesha S.. ...                        3
                                                      Verdigris         ........      12, 600, 600       1, 474, 000     4, 025, 400      18, 100, 000
Elk City (Table Mound) .                       - ..   Elk...........-..               16, 585, 000       2, 339, 000     7, 406, 000      26, 330, 000
Pensacola 2                 -................         Grand (Neosho)_...---------                        1, 710, 000 --       ---          1, 710, 000
Markham Ferry               ----...........           Grand (Neosho)_                 30, 111, 300       1, 990, 000     9, 598, 700      41, 700, 000
Fort Gibson 2-...._.__-_-                   _         Grand (Neosho)_                 28, 842, 100       3, 398, 500     9, 759, 400      42, 000, 000
Eufaula .................                             Canadian           ..           72, 678,100       12, 382, 000    67, 939, 900     153, 000, 000


   1 Includes reservoir management and facilities for public use of the reservoir area.
   2 See individual report for details of this project.
   = See inactive flood control projects.
   4 For acquisition of additional flowage easements only.

  The following projects are reported individually in the pre-
ceding pages: Canton, Fall River, Tenkiller Ferry, Wister, and
Fort Gibson Reservoirs, completed or essentially complete; Oologah
Reservoir on which construction was initiated but is now in a
stand-by status; Keystone and Toronto Reservoirs now in the de-
tailed planning stage; and Pensacola Reservoir constructed by the
Grand River Dam Authority with flood control regulations as-
signed as a responsibility of the Corps of Engineers.
      The remaining projects are reported inactive at this time.
      Authorizations for the comprehensive plan are listed below:

                        Act                                           Work authorized                                Documents and reports

Flood Control Act, June 28,                            Oologah, Canton, Tenkiller              Flood     Control
                                                                                                     Ferry,          Committee
  1938.                                                 and Wister Reservoirs.                   Document No. 1, 75th Con-
                                                                                                 gress, 1st Session.
Flood Control Act, August 18,                          Markham Ferry, Fort Gibson, Pensa- House Documents Nos. 107
  1941.                                                 cola, Fall River, Elk City, Toronto,     and 440, 76th Congress, 1st
                                                        and Neodesha Reservoirs.                 Session.
River and Harbor Act, July 24,                         Eufaula Reservoir...-------.---------. House Document No. 758, 79th
  1946.                                                                                          Congress, 2d Session.
Flood Control Act, May 17,                             Keystone Reservoir--___   ------      - Senate Document No. 107,
  1950.                                                                                          81st Congress, 1st Session.



23. DENISON DAM (LAKE TEXOMA), RED RIVER, TEX. AND OKLA.
   Location. The Denison Dam is located on Red River, 726 miles
above the mouth of the river and 5 miles northwest of Denison,
Tex. (See U. S. Geological Survey maps for Denison, Tex., and
Tishomingo, Okla., quadrangles; scale 1:125,000.)
  Existing project. The plan of improvement consists of a rolled
earthfill dam 15,200 feet long, rising 165 feet above the stream bed
with the reservoir providing 2,690,400 acre-feet of flood control
storage, 1,784,300 acre-feet of power storage, 1,223,000 acre-feet
for accumulation of silt, and 21,300 acre-feet for conservation
purposes. The outlet works, consisting of a gate-control house
and eight conduits, each 20 feet in diameter, and the powerhouse,
are located on the right abutment. A chute-type spillway 2,000
feet wide located in a saddle on the right bank will discharge flood
flows through a creek to a point 1 mile below the dam. The plan
of improvement also provides for the diversion of the Washita
              FLOOD CONTROL-TULSA, OKLA., DISTRICT              697
  River and the construction of levees to protect the Cumberland oil
  field from inundation.
     The project, which controls 39,719 square miles, provides for
  flood protection to lands in Texas, Oklahoma, Arkansas, and
Louisiana, the generation of power, improvement of navigation,
regulation of the flow of the Red River, and for other beneficial
uses. The hydroelectric development consists of 2 units having an
installed capacity of 70,000 kw. The ultimate installation planned
is for 5 units with a total of 175,000 kw.
     The estimated costs (based upon installation of three power
generating units) (1954) are $47,333,300 for construction and
 $18,566,700 for lands and damages, a total of $65,900,000. The
estimated cost of annual maintenance is $435,000 (1954).
     The existing project was authorized by the Flood Control Act
approved June 28, 1938, and amended by section 4, Public Law
868, 76th Congress, 3d session, approved October 17, 1940. (See
H. Doc. 541, 75th Cong., 3d sess., which contains the latest pub-
lished maps.)
     The congressional act, Public Law 454, 78th Congress, chapter
456, 2d session, approved September 30, 1944, provided that from
and after the enactment of that act the lake formed by the im-
pounding of waters of the Red River by Denison Dam, shall be
known and designated on the public records as Lake Texoma.
     The congressional Act, Public Law 273, 83d Congress, chapter
487, 1st session, approved August 14, 1953, further modified the
project by authorizing the making of a contract with the city of
Denison, Texas, for storage for a regulated water supply.
     Local cooperation. Section 2 of the Flood Control Act, ap-
proved June 28, 1938, applies.
     In aceordance with authority in Public Law 273, 83d Cong., 2d
sess., a water conservation contract with the City of Denison,
dated August 31, 1953, was approved by the Chief of Engineers.
This contract makes available 21,300 acre-feet of conservation
storage at an annual cost of $13,800.
     Operations and results during fiscal year. All completed struc-
tures were operated and maintained in a serviceable condition
throughout the fiscal year, by hired labor. Repairs to powerhead
gates, including installation of gate limit switch and position
indicator, were completed, by hired labor. The new work accom-
plished by contract consists of procurement and installation of
additional communication facilities, namely, load control and tele-
metering equipment and carrier current equipment.
    Receipts from outleasing Government-owned land during the
fiscal year amount to $123,532. Power generated by operation of
the project during the fiscal year amounted to 192,420,000 kilo-
watt hours. This power was delivered to the Southwestern Power
Administration for marketing.
    The cost during the fiscal year was $10,671 for new work and
$437,788 for maintenance.
    Condition at end of fiscal year. Construction of the project was
started in August 1939. Storage of water for power generation
was begun January 7, 1944, and power from the first installed unit
was available for sale on March 9, 1945. The second power unit
698            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

was placed in operation on September 18, 1949. The project as
authorized provides for ultimate installation of five power units.
With the exception of construction required to install future
power generating units, the project is essentially complete.
  The total receipts from outleasing Government-owned land
through fiscal year 1954 amount to $746,213. Such receipts are
not included in the cost and financial summary shown below.
  The total cost of new work to the end of the fiscal year was
$60,072,324 and the total cost of maintenance was $3,753,076.
                                  Cost and financial summary

                                         Fiscal year ending June 30                   Total to June
                                                                                      30, 1954, includ-
                                                                                      ing fiscal years
                           1950        1951        1952         1953       1954         priorto 1950

New work:
   Appropriated ...
                  __      $550, 000       000
                                      $208,       $400,
                                                      000        $5, 000      300
                                                                            $8,           $60, 105, 289
   Cost----------------    882, 102    411, 478    138, 362    343, 301     10, 671        60, 072, 324
Maintenance:
   Appropriated-------
                .......    523, 000    492, 000    463, 334    387, 000    421, 000         3, 760, 566
   Cost----------------    537, 460    465, 592    467, 600    373, 355    437, 788         3,753,076


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954.....-------....                       $19, 927
                                                                                        ----.................
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955....                                    ------------------------------------------
                                                                                                  19,927
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project--------....-..--...... ........
                                                                .....                        5, 794,  711
                                                                          ......----------..............

      24. RED RIVER BELOW DENISON DAM, TULSA DISTRICT
   Location. The work covered by this project is located on the
Red River and its tributaries below Denison Dam, in Oklahoma,
Arkansas, Texas, and Louisiana.
   Existing project. The Flood Control Act approved July 24,
1946, approved the general plan for flood control on Red River
below Denison Dam, which provides for the construction of six
flood control reservoirs in combination with existing or authorized
Federal and non-Federal levee improvements, modified as re-
quired, and channel stabilization at locations where levee setbacks
are impossible or uneconomical.       This act further authorized
the incorporation of the several separate existing projects for
flood control along the Red River below Denison, above the juris-
diction of the Mississippi River Commission, into this project.
The total estimated cost to the United States in the Tulsa district
 (1954) is $103,794,500 for construction and lands and dam-
ages. The project was authorized substantially in accordance
with House Document No. 602, 79th Congress, 2d session, which
contains the latest published map.
   The reservoirs and bank stabilization included in the general
flood control plan for the Red River below Denison Dam within the
                    FLOOD CONTROL-TULSA, OKLA., DISTRICT                                                        699
limits of the Tulsa District are reported on as noted in the follow-
ing table:

                             Dis-     Height                                             Cost (1954)
                            tance of Dam Drainage           Reservoir
     Name         Nearest   above   and     area             capacity        Con-            Land and
                   city     mouth type   sq. miles          (acre-feet)           on
                                                                          sstruction         damage
                                                                                             damages          Total

Boswell2  Reser- Boswell,     18. 9     '95        2, 273   1, 135, 000 $21, 767, 500         3, 432, 500 $25, 200, 000
voir.              Okla.
Hugo      Reser- Hugo,        20. 7     489        1, 706     850, 000    20, 132, 400        2, 337, 600   22, 470, 000
voir.2             Okla.
Millwood Reser- Millwood      16. 0     '97        4, 144   2, 260, 000   31, 155, 100       24, 744, 900   55, 900, 000
voir.1             Ark.
Bank s stabiliza- Index,     485.3 -......................------------          ----------                     222, 105
tion.              Ark.


1Details are presented in individual report.
2 See inactive flood control projects.
8 Details of entire program reported under New Orleans District.
4 Earthfill Dam.

          25. MILLWOOD                RESERVOIR,            LITTLE RIVER,                        ARK.
   Location. The Millwood dam site is located on the Little River,
16 miles above its mouth, and about 10 miles northwest of Fulton,
Hempstead County, Ark. (See sectional aeronautical chart, Shreve-
port sheet, scale 1:500,000.)
   Existing project. The plan of improvement provides for con-
struction of an earthfill dam and concrete structure 18,900 feet
long and rising about 97 feet above the streambed, with reservoir
storage of 2,208,000 acre-feet for flood control and 52,000 acre-feet
for siltation, recreation, and preservation of wildlife. A concrete
channel spillway, controlled by twelve 40- by 30-foot gates on the
weir crest, will provide for the passage of flood flows into the
valley below. The reservoir which will control 4,144 square miles
will be operated as a unit of a reservoir system for flood control
in the Red River Basin.
   The estimated costs (1954) are $31,155,100 for construction and
$24,744,900 for lands and damages, a total of $55,900,000.
   The existing project was authorized by the Flood Control Act,
approved July 24, 1946. (See House Document No. 602, 79th
Congress, 2d Session, which contains the latest published map.)
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. Economic studies in
connection with the project site selection report were continued,
by hired labor.
   The cost of new work during the fiscal year was $1,983.
   Condition at end of fiscal year. Project is in preliminary plan-
ning stage with studies and design required prior to actual initia-
tion of construction about 41 percent complete.
   The total cost and expenditures to the end of the fiscal year
amount to $196,813, all for new work.
 700                REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

                                                Cost and financial summary

                                                            Fiscal year ending June 30                                Total to June
                                                                                                                      30, 1954, includ-
                                                                                                                      ing fiscal years
                                        1950            1951              1952          1953              1954          prior to 1950

New work:
   Appropriated ......-  $200, 000                     $50, 000        -$55, 170                            $2, 000             $196, 830
   Cost-----------------   93, 910                      94, 084            6, 549             $287           1, 983              196, 813


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 .............-......                                                      $17
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955..----....----. ..-----                                                          ...- -------------...........    17
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project-----...............................................-----------------------...  ......... 55, 703, 170

                      26. INACTIVE                  FLOOD CONTROL                             PROJECTS

                                                                   For last          Cost to June 30, 1954              Estimated
                                                                  full report                                             amount
                     Name of project                                 see                                                 required
                                                                   annual              Con-            Operation            to
                                                                   report           struction            and             complete
                                                                    for-                              maintenance

       ARKANSAS RIVER, MAIN STEM AND MINOR
                   TRIBUTARIES

1.   Big Slough to Belle Plaine, Kans. 5..........               11937                                                   $6,490,000
2.   Augusta, Kans. -.... . . . . ..------------------11938                                                                    (')
3.   Winfleld Kans.......--------------                          11937
4.   Jenks, Okla, .-------.---          ..---------------.        1950               $344, 797
5.   Kaw, Okla ....... _---...............                ..----  1953                 34, 284

                NORTH CANADIAN RIVER

6. Optima Reservoir, Okla ..................                          1952            168, 068 -.........                22, 68, 932
                GRAND (NEOSHO) RIVER

7.   Monett, Missouri 2 7___........_______.......1948                                                                         757, 000
8.   Florence, Kans . 8................           11937                                                                          6, 000
9.   Iola, Kans ..................------          1 1939         22,290                                                        (4)
10.   Council Grove Reservoir, Kans..............    1952                                                                 11, 935, 000
11.   Marion Reservoir, Kans ......--............. 1952       .-    623
                                                                    .305,                                                  7,755,000
12.   Cedar Point Reservoir, Kans ................   1952                                                                  6, 385,000
13.   Markham Ferry Reservoir                        1953
                                   ................--------------                      305,   623                         41, 700, 000

                    VERDIGRIS RIVER

14. Verdigris2 River from mouth to Madison,                        11938                                                    ' 913, 000
      Kans. 6
15. West of Fredonia, Wilson County, Kans.'                 5_.    11937                                                        741, 000
16. West of Benedict, Wilson County, Kans. 5___                    11937                                                        765, 000
17. West of Elk City, Montgomery County,                           11937                                                        319, 000
      Kans.' 5
18. Caney Creek, Washington County, Okla.,                         1   1937                                                     616, 000
      and Chautauqua and Montgomery Coun-
      ties, Kans.s 5
19. Neodesha Reservoir, Kans _..............                           1952             97, 910-                          18,002, 090
20. Elk City Reservoir, Kans_------                                    1952             89, 893 ---....--        -        26, 240, 107
                    CANADIAN RIVER

21. Eufaula Reservoir, Okla_                        -----              1952            950, 101      .________           152,     09,899
            SALT FORK OF ARKANSAS RIVER
                         2
22. Blackwell, Okla.         5..   --    --             .          11937                                                        197, 000

  See footnotes at end of table.
                       FLOOD CONTROL---TULSA, OKLA., DISTRICT                                                   701

                                                       For last        Cost to June 30, 1954           Estimated
                                                      full report                                       amount
                  Name of project                          see                                          required
                                                        annual          Con-         Operation             to
                                                        report       struction         and             complete
                                                         for-                       maintenance
            NORTH FORK OF RED RIVER

23.   L     Reservoir, North Fork of Red River,          1942         $1, 130, 000 __-----                (10)

                     RED RIVER

24. Boswell Reservoir, Boggy Creek, Okla.......          1952            128, 786------------          $25, 071, 214
25. Hugo Reservoir, Kiamichi River, Okla-....            1952             60, 000 _ .........           22, 410, 000
26. Snagging and Clearing Under Authority of             1952             21, 490 ...........              (4)
      F. C. Act Approved July 24, 1946
27. Emergency Bank Protection Work Under                 1950             53, 996_(4)
     Authority of the F. C. Act Approved De-
     cember 22, 1944
28. Emergency Bank Protection Work Under                 1953            188, 523                         (4)
     Authority of the Flood Control Act Ap-
     proved July 24, 1946
29. Emergency Flood Control Work Under                   1953--------------             $1, 671, 753      (4)
     Authority of Public Laws Nos. 138 and 318,
     78th Congress, Public Law No. 75, 79th
     Congress, and Public Laws Nos. 102 and
     858, 80th Congress
30. Emergency Flood Control Work Authority               1953                                 5, 519      (4)
     of Public Law 371, Approved June 4, 1952

     1In 1937 the projects were reported by the Memphis District; in 1938 and 1939 by the Little Rock District.
  2    Awaiting local cooperation.
    ' Project completed by Kansas Works Progress Administration.
    'Complete.
     5 In conformance with provisions of the 1941 Flood Control Act, local interests were notified on April 18,
1952, that authorization for construction of the project will expire 5 years from that date unless assurances
of local cooperation satisfactory to the Secretary of the Army are received prior to that time.
    6 In conformance with provisions of the 1944 Flood Control Act, local interests were notified on April 24,
1952, that authorization for construction of the project will expire 5 years from that date unless assurances
of local cooperation satisfactory to the Secretary of the Army are received prior to that time.
    7 In conformance with provisions of the 1948 Flood Control Act, local interests were notified on November
7, 1952, that authority for construction of the project will expire 5 years from that date unless assurances of
local cooperation satisfactory to the Secretary of the Army are received prior to that time.
    a In conformance with provisions of the 1948 Flood Control Act, local interests were notified on February
5, 1954, that authority for construction of the project will expire 5 years from that date unless assurances of
local cooperation satisfactory to the Secretary of the Army are received prior to that time.
    9Some work on this project was done by Wilson County (Kans.) Civil Works Administration in 1933
and 1934.
    10Project was constructed by U. S. Bureau of Reclamation for irrigation. Participation by Dept. of Army
was for financing flood control portion of project, and this participation has been completed.
    n To be constructed by the Grand River Dam Authority, an agency of the State of Oklahoma. A bill is
pending in Congress which would provide for Federal participation to an amount of $6,500,000 in payment
for the flood control portion of the project.

                             27. GENERAL INVESTIGATIONS

   Examinations and surveys. The costs of general investigations
during the fiscal year were $235,130, of which $231,630 was for
engineering studies in connection with preparation of examination
and survey reports and $3,500 was for collection and study of basic
data. At the end of the fiscal year, the balance unexpended from
previous allotments amounted to $7,486. This amount will be
applied to continued studies and preparation of reports assigned
to this office. Estimated additional funds which can be profitably
expended in the succeeding fiscal year amount to $197,000 for
examinations and surveys and $23,900 for collection and study of
basic data.
702           REPORT OF CHIEF OF ENGINEERS, U.- S. ARMY, 1954

   Collection and study of basic data. As noted above, the sum of
$3,500 was expended during fiscal year 1954 for work under this
heading. These costs were applied as follows: $1,499 was for
observing and compiling data on stream flow, and $2,001 was for
analysis of basic data required for keeping up-to-date information
essential to properly evaluate the continuing and recurring water
resource development program.
                   28. INSPECTION OF COMPLETED PROJECTS
    The costs under this heading are incurred during semiannual
inspections conducted to see if local interests are complying with
existing regulations and requirements in maintaining and oper-
ating projects constructed with Federal funds and transferred to
them.
   Inspections conducted during the fiscal year indicate that exist-
ing agreements and regulations are being complied with at the
following projects: (1) Tulsa-West Tulsa Levee, Okla.; (2) Jenks
Levee, Okla.; (3) Polecat Creek Channel Improvement, Okla.;
 (4) Iola Levee, Kans., anid (5) Completed portions of Wichita
Levees, Kans.
    The cost of work under this heading during fiscal year 1954 was
$932.
                                      Cost and financial summary

                                                Fiscal year ending June 30                   Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                               1950            1951       1952        1953         1954       priorto 1950

Maintenance:
   Appropriated---------___       ___-__   -   $2, 000     $1, 020       $300        $600             $3, 920
    Cost _______     _____--------
                              -          _      1, 487        959            517      932              3, 895



  29. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
    Flood control emergenices-repairand flood fighting and rescue
work (Section 210 of the 1950 Flood Control Act and supplemental
authorizations).
    Under this heading the cost of all work accomplished during the
:fiscal year amounted to $27,303. This work consisted of needed
levee repairs at 6 separate locations, of which 3 levees were in
Kansas and 3 were in Oklahoma. Repairs to Council Grove Levee
on the Neosho River in Kansas was the largest levee repair effected
during fiscal year 1954. This levee repair cost $22,081. Hired
labor operations performed under this heading consisted of prac-
tice exercises on flood fighting which cost $361, all other operations
were performed by contract.
                    FLOOD CONTROL-TULSA, OKLA., DISTRICT                                                    703
30. SCHEDULING OF FLOOD CONTROL RESERVOIR OPERATIONS
  The work accomplished under this heading consists of operating
activities necessary in the basin wide coordination of functional
scheduling of releases from reservoirs operated by other agencies.
  Hired labor costs during the fiscal year were $1,197, all from
maintenance funds. At the end of the fiscal year, there was an
unobligated balance of $303. This amount, together with an ex-
pected allotment of $1,000 during fiscal year 1955, a total of $1,303,
will be applied to continued scheduling and coordination activities.
                                         Cost and financial summary

                                                       Fiscal year ending June 30                  Total to June
                                                                                                  30, 1954, includ-
                                                                                                  ing fiscal years
                                 1950               1951                 1952   1953   1954        prior to 1950

Maintenance:
   Appropriated     ------------------------------------------------                    $1, 500             $1, 500
   Cost ---------      -----------------------------------------------                   1, 197              1, 197




      Sig 23-703.7384
      IMPROVEMENT OF RIVERS AND HARBORS IN THE
                ST. LOUIS, MO., DISTRICT
   This district comprises those portions of southwestern Illinois
and eastern Missouri embraced in the drainage basin of the
Mississippi River and its western tributaries, exclusive of the
Missouri River, between the mouth of the Ohio River and mile
300 above the same, and of its eastern tributaries to Hamburg
Bay at mile 261 on the left bank, exclusive of the tributary basin
of the Illinois Waterway upstream of the new La Grange Lock
and Dam at mile 80.15 above the confluence of the Illinois and
Mississippi Rivers. The district also includes the drainage basin
in Missouri tributary to the Little River diversion channel. Re-
port on Mississippi River between the Missouri River and mile
300 is included in the report on Mississippi River between Missouri
River and Minneapolis, Minn. Report on that portion of the
Illinois River downstream of the new La Grange Lock and Dam is
included in report on Illinois Waterway, Illinois, contained in the
report of the district engineer, Chicago, Ill.
                                         IMPROVEMENTS

                    Navigation                                 Flood control-Continued
                                              Page                                               Page
1. Mississippi River between the                          15. Stringtown-Fort Chartres and
       Ohio and Missouri Rivers......                 706        Ivy Landing, Ill...................      719
2. Mississippi River between the                         16. Fort Chartres and Ivy Land-
       Missouri River and Minnea-                                ing drainage district No. 5,
       polis, Minn. (St. Louis Dis-                              Ill ................                     720
       trict) ................-. - - ....             709 17. Harrisonville and Ivy Landing
3. Illinois Waterway, Ill ..........                 709        drainage and levee district
4. Inactive Navigation Projects.._                   709        No. 2, Ill ..... ...............         721
                                                          18. Columbia drainage and levee
                  Flood control                                  district No. 3, Ill.................-    722
                                                          19. Wilson and Wenkel and Prairie
5.   East Cape Girardeau and Clear                              duPont drainage and levee
        Creek drainage district, Ill....              709        districts, Ill............... .........  723
6.   Cape Girardeau, Mo..................            710 20. East St. Louis and vicinity, Ill            724
7.   North Alexander drainage and                        21. Chouteau, Nameoki and Venice
        levee district, Ill ..................        711        drainage and levee district,
8.   Clear Creek drainage and levee                             Ill..        .................           725
        district, Ill..............................   712 22. Wood River drainage and levee
9.   Miller Pond drainage district,                             district, Ill .........................  726
        Ill ..................        .............   713 23. Carlyle Reservoir, Upper Miss-
10.   Preston drainage and levee                                 issippi River Basin, Ill-..........      727
        district, Ill....            ..        .      714 24. Upper Mississippi River Basin,
11.   Grand Tower drainage and                                   St. Louis District..............         728
        levee district, Ill....................       715 25. Inactive flood control projects..           730
12.   Degognia and Fountain Bluff                         26. General investigations................      730
        levee and drainage district,                      27. Inspection of completed works,
                                                      716        flood control projects .............
        Ill..........................-------......----------..............                                731
13.   Perry County drainage and                           28. Flood control work under spe-
        levee districts, Nos. 1, 2 and                           cial authorization....................   731
        3, Mo--..................................---- 717 29. Miscellaneous investigations....            732
14.   Prairie du Rocher and vicini-                       30. Regulation, other regulatory
        ty, Ill..                                     718        functions.......... .........  ...... .. 732
                                                                                         705
706      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

1. MISSISSIPPI RIVER BETWEEN THE OHIO AND MISSOURI RIVERS
    Location. The Mississippi River rises in Lake Itasca, Minn.,
and, from that lake flows in a southerly direction about 2,350 miles
and empties into the Gulf of Mexico. The portion included in this
report embraces the 95-mile section known as the middle Missis-
sippi, between the tributary Ohio and Missouri Rivers, about 984
to 1,179 miles from the Gulf.
   Previous projects. The original project for the improvement of
the Mississippi River between the Ohio and Missouri Rivers was
recommended by a board of engineers in a report, dated April 13,
1872, and concurred in by the Chief of Engineers. For further
details, see page 1879 of the Annual Report for 1915, and page
1014 of the Annual Report for 1938.
   Existing project. This provides for obtaining and maintaining
a minimum channel depth of not less than 9 feet, a minimum
width of not less than 300 feet at low water, with additional widths
in bends from the mouth of the Ohio River (about.984 miles from
the Gulf) to the northern boundary of the city of St. Louis, 191
miles; thence 200 feet wide, with additional width in bends to the
mouth of the Missouri River, 4 miles; to be obtained: First, by
regulating works, for closing sloughs and secondary channels, and
narrowing the river; by building new banks where the natural
width is excessive and protecting new and old banks from erosion
where necessary to secure permanency; second, by dredging or
other temporary expedients to maintain channels of project di-
mensions; third, by construction of works authorized for the
Chain of Rocks reach in the River and Harbor Act of March 2,
1945, which approved a comprehensive plan for development of
the Mississippi River at Chain of Rocks so as to provide for con-
struction of a lateral canal at an estimated first cost to the United
States of approximately $10,290,000, with annual maintenance
and operation cost of $70,000, subject to such modification as the
Chief of Engineers may find necessary when the project is under-
taken; and to authorize the relocation of the river channel and
reclamation of the area in Sawyer Bend for airport, park, recrea-
tional, and similar purposes at a cost to local interests of approxi-
mately $17,555,000: Provided, That any modification of the pres-
ent river channel required by the civic development be deferred
until completion of the lateral canal in the interest of navigation
and that the river diversion work connected with such civic de-
velopment be under the supervision of the Chief of Engineers in
order to insure that the interests of interstate and foreign com-
merce be properly protected: And further provided, That local in-
terests hold and save the United States free from any claims for
damages that might be incurred due to the construction, mainte-
nance, or operation of such civic development or any part thereof
 (H. Doc. 231, 76th Cong., 1st sess.).
   The estimated cost of new work (1954) is $97,713,000. The
estimated annual cost of maintenance (1954) is $1,370,000.
                  RIVERS AND HARBORS-ST. LOUIS, MO., DISTRICT                                                 707
The existing project was authorized by the following River and
Harbor Acts:
       Acts                           Work authorized                                       Documents
                                                                              i

                  Project for regulating works adopted in 1881.           (To Annual Report, 1881, p. 1536.
                   obtain a minimum depth of 8 feet.)
June 3, 1896
June 13, 1902     Dredging introduced as part of the project--.......------
Mar. 2, 1907
Mar. 3, 19051     These acts practically abrogated that part of the
Mar. 2, 19071       project for the middle Mississippi which proposed
                    regulating works.
June 25, 1910     Regulating works restored to the project and appro-             H. Doc. 50, 61st Cong., 1st sess.,
                    priations begun with a view to the completion of                and H. 2 Doc. 168, 58th Cong.,
                    the improvement between the Ohio and Missouri                   2d sess.
                     Rivers within 12 years at an estimated cost of
                    $21,000,000, exclusive of amounts previously ex-
                     pended.
Jan.   21, 1927   For a depth of 9 feet and width of 300 feet from the            Rivers and Harbors Committee,
                     Ohio River to the northern boundary of the city of             Doec. 9, 69th Cong., 2d sess.
                    St. Louis, with the estimated cost of maintenance
                    increased to $900,000 annually.
July    3, 1930   Project between the northern boundary of the city of            Rivers and Harbors Committee,
                    St. Louis and Grafton (mouth of Illinois River)                 Doc. 12, 70th Cong., 1st sess.
                    modified to provide for a channel 9 feet deep and
                    generally 200 feet wide with additional width
                    around bends, at an estimated cost of $1,500,000,
                    with $125,000 annually for maintenance.
Mar.    2, 1945   Modified to provide for construction of a lateral canal         H. Doc. 231, 76th Cong., 1st sess.
                    with lock at Chain of Rocks, at an estimated first
                    cost to the United States of about $10,290,000, with
                    $70,000 annually for maintenance and operation.

  1Also joint resolution,   June 29, 1906.             2 Contains latest published map.


   See House Document 669 (76th Cong., 3d sess.) for report of
Chief of Engineers dated February 27, 1940, containing a general
plan for improvement of the Mississippi River between Coon
Rapids Dam and the mouth of the Ohio River for purposes of
navigation, power development, the control of floods, and the needs
of irrigation.
   Recommended modifications of project. By letter dated July
28, 1952, the Chief of Engineers recommended that the existing
project be modified to provide for a small-boat harbor opposite
Chester, Ill., consisting of a basin with a project depth of 6 feet,
250 feet wide, 650 feet long with an approach channel of the same
depth, 50 feet wide and approximately 1,200 feet long. The esti-
mated cost of construction to the United States (1950) is $57,700.
First costs to be borne by local interests are estimated at $58,700,
including a cash contribution estimated at $29,000. (H. Doc. No..
230, 83d Cong., 1st sess.)
   Terminal facilities. Most of the water terminal and transfer
facilities of the district are described in volumes 1 and 4 of the
four-volume report of the Board of Engineers for Rivers and Har-
bors, entitled "Survey of Terminals and Landings on the Inland
Waterways of the United States."
   Operations and results during fiscal year. Construction works
were carried on by contract and by hired labor with Government
plant, weather conditions and river stages being favorable for
construction during most of the year. Regulating works were
maintained, and project dimensions of channels were secured by
dredging.
  New work: Costs of $747,429 were incurred on the improvement
708      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

at Chain of Rocks as follows: By contract, construction of locks,
 $41,334; construction of canal, $382,404; construction of levees,
 $132,889; pumping plants and drainage facilities, $5,000; perma-
nent operating equipment, $8,169; engineering and design, $80,940;
miscellaneous costs, $75,338; real estate expense, management, ap-
praisals, condemnations, mapping, and surveying, $25,349, and
pending adjustment, -$3,994.
    Maintenance: Dikes (14,745 linear feet) and revetments (3,350
linear feet) were repaired at a cost of $682,281. The required
9-foot channel was maintained by two United States hydraulic
dredges. Channel dredging was performed at 69 localities with
Government plant and hired labor, removing 6,054,721 cubic yards
of sand and gravel at a cost of $984,177, and pending adjustment
 $8,667. The channels dredged had a combined length of 34.35
miles, an average width of 307.1 feet, and an average gain in
depth of 7.02 feet.
    Hydrographic (dredge) surveys were made covering 208 miles
of river, costing $23,300. Aids to navigation were installed at a
cost of $39,631. Other miscellaneous costs by hired labor were:
gages, $19,000; commercial statistics, $6,000; cooperative stream
gaging, $24,700; discharge observations, $2,400 and engineering
planning, $1,000, all charged to maintenance. The cost of oper-
ation and care of lock No. 27 was $85,956. The total cost of all
maintenance, including operation and care, was $1,877,112. The
total costs of all work for the fiscal year were $2,624,541, all from
regular funds.
    Condition at end of fiscal year. Construction on the existing
project was initiated in 1881, and the project has been in beneficial
use practically from its inception. Work under the project (in-
cluding the Chain of Rocks canal) is about 84 percent complete.
The quantities required to complete the project are estimated at
125,440 linear feet of dikes, 129,705 linear feet of revetment,
280,000 cubic yards of rock removal, and minor items of work at
Chain of Rocks. Dikes and revetments were in poor condition
along some reaches of river due to critical damage inflicted by
heavy ice flows during the winter of 1950-51 and by floods in
spring and summer of 1951. The channel as a whole has been
greatly improved by the work that has been completed to date.
Dredging is required at low stages to remove temporary shoals
and maintain the required channel depths.
   The project dimensions of channels have generally been main-
tained throughout the navigation season. The navigation season
formerly extended from the middle of February to the middle of
December, the river being generally closed by ice the remainder
of the year. However, in recent years increased demands of com-
merce and the use of steel hull boats have combined to extend
the navigation season throughout the year except when blocked
by heavy running ice or gorges. The river is generally above the
10-foot stage, St. Louis gage, for 6 months of the year, latter part
of February to latter part of August, during which time project
channel depths generally prevail without dredging. The mean
stage of the river, St. Louis gage, was 7.64 feet for the fiscal
year 1953 and 4.56 feet for the fiscal year 1954.
                   RIVERS AND HARBORS-ST. LOUIS, MO., DISTRICT                                                                       709

    The costs and expenditures under the existing project to June
30, 1954 have been as follows:
                                                                                      Public works Emergency
                                                                   Regular funds         funds     repair funds                  Total
             ___
New work--------------___              ----------------             $76, 574, 736     $3, 462, 154    $996, 748                $81, 033, 639
Maintenance          ....                                             37, 579, 945---
                                          .............-----------------------------              ...                           37, 579, 945
Operation and care       ..                    ........-----------------------....
                                                                          266, 805 ----..-------------------                        266,805
      Total.......................------------------------------     144, 421, 486       3, 462, 154             996, 748      118,880,389


                                               Cost and financial summary

                                                            Fiscal year ending June 30                                      Total to June
                                                                                                                         30, 1954, includ-
                                                                                                                         ing fiscal years
                                       1950              1951             1952            1953                1954         prior to 1950
New work:
   Appropriated-_.....     $9, 750, 000              $8, 830, 000      $5, 000, 000    $1, 143,000      -1                     $83, 171, 142
   Cost-----. -.--------   11, 712, 827               8, 449, 126       2, 263, 874     4, 293, 137          $747, 429          82, 450, 259
Maintenance:
   Appropriated...--------     975, 000                  901, 800       1, 365, 200     1, 457, 950      1,994, 072             37, 965, 360
   Cost----------.... ----     897, 808                  806, 920       1, 269, 562     1, 756, 766      1,877, 112             37, 846, 750

  I Includes $1,416,620 for new work for previous projects.
  2 In addition $87,083 for new work and $31,417 for maintenance were expended from contributed funds.

Other new work data:
     Unobligated balance, fiscal year ending June 30, 1954..........................                        $29,222
     Estimated additional amount needed to be appropriated for com-
       pletion of existing project..................................................................... 15, 958, 478

   2. MISSISSIPPI RIVER BETWEEN THE MISSOURI RIVER AND
           MINNEAPOLIS, MINN. (ST. LOUIS DISTRICT)
See report, "Mississippi River between the Missouri River and
Minneapolis, Minn.," page 742.

           3. ILLINOIS WATERWAY,                                     ILL.       (ST.     LOUIS           DISTRICT)

See report, "Illinois                        Waterway, Ill.," page 1130.
                             4.:     INACTIVE                NAVIGATION PROJECTS

                                                                     For last           Cost to June 30, 1954                Estimated
                                                                    full report,                                               amount
                    Name of project                                     see                                                    required
                                                                      annual            Con-            Operation                 to
                                                                      report          struction            and                complete
                                                                       for-                            maintenance
1. Cuivre River, Mo.' 2.-.-.-
2. Kaskaskia River, Ill.2 3
                                                        -               1883
                                                                        1896
                                                                                          $12, 000
                                                                                           10, 461 -
                                                                                                      -------------         Inactive.
                                                                                                                            Completed,
                                                                                                                              inactive.

  I River declared nonnavigable by act of Mar. 23, 1900.
  a No commerce reported.
  a By authority of the Chief of Engineers, dated Dec. 12, 1895, this work was dropped from the duties in
charge of the St. Louis district (Annual Report, Chief of Engineers, 1896, p. 1761).

   5. EAST            CAPE          GIRARDEAU AND CLEAR                                       CREEK               DRAINAGE
                                        DISTRICT, ILLINOIS

   Location.               This project is in the north end of Alexander County,
Ill., on the left bank of Mississippi River between river miles 46 and
57 above the Ohio River. The district includes the bottom lands
710               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

between the river on the west and south, the old channel of Clear
Creek on the north, and the Illinois Central Railroad on the east.
   Existing project. This provides for raising and enlarging the
entire levee system consisting of 10 miles of riverfront levee and
0.9 mile of back levee, all of which was previously constructed by
the United States, and the construction of appurtenant works con-
sisting of gravity drainage and closure structures, surfacing of
service roads on the levee crown, and altering railroads at one levee
crossing. This project when completed will not in itself afford com-
plete protection to this district; but in combination with and upon
completion of authorized work in the Miller Pond, the North
Alexander, the Clear Creek, and the Preston drainage and levee
districts, protection will have been provided to this and the other
districts named against a flood of about 50-year frequency. The
estimated total construction cost (1954), including $207,000 of
1936 funds used for temporary levee. repair, resulting from the
1943 flood, is $2,085,000. The project was authorized by the Flood
Control Act of June 22, 1936.
   Local cooperation. Assurance of local cooperation approved
by the county court of Alexander County, Ill., was approved by
the Secretary of War on July 30, 1940. Local interests have
provided evidence of acquisition of the necessary rights-of-way
for construction of work completed to interim grade and work
now under construction to design grade. Local interests have
informally indicated that they will be able to fulfill requirements
of local cooperation for the remaining work features as required.
   Operationsand results during fiscal year. Costs incurred were
$41,015 for preliminary engineering and design and $10,117 for
other distributive costs. Work by contract consisted of levee con-
struction $72,387, drainage facilities $15,025, and pending adjust-
ment -$420. Total costs for the fiscal year were $138,964.47 for
new work.
   Condition at end of fiscal year. Construction on the existing
project was initiated in July 1940, and the project was ready for
beneficial use in the fall of 1941. Work under the project is about
67 percent complete. The total costs to June 30, 1954, were $1,394,-
048.29 for new work.
                                              Cost and financial surnmary

                                                        Fiscal year ending June 30                              Total to June
                                                                                                                30, 1954, includ-
                                                                                                                ing fiscal years
                                     1950            1951            1952           1953            1954         prior to 1950

New work:
    Appropriated_____           _----------        $270, 000        $500, 000      $224, 000     .......              $1, 605, 047
    Cost             -                $4, 081         47, 346         94, 020       605, 671        $138, 964          1, 394, 048


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954..........------------.............                              $120, 548
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project----------..-................................................---------------------......  479,953

                                        6. CAPE GIRARDEAU, MO.
    Location. This project is in Cape Girardeau County, Mo., on
the right bank of Mississippi River between river miles 49 and 53.
                  FLOOD CONTROL-ST. LOUIS, MO., DISTRICT                                                       711
The area to be protected includes the low lying lands along the
river front of Cape Girardeau between the river and the bluffs.
   Existing project. The plan of improvement provides for the
construction of a series of earth levees and concrete floodwalls
including essential railroad and street alterations, necessary sewer
alterations, construction of pumping plants, and drainage and
closure structures. The project, when completed, will afford pro-
tection to the low lying area of Cape Girardeau, Mo., against a
flood of about 180-year frequency. The estimated total construc-
tion cost, revised in 1954, is $8,010,000. The project was author-
ized by the Flood Control Act approved May 17, 1950 (H. Doc. 204,
81st Cong., 1st sess.).
   Local cooperation. Assurances of local cooperation have been
received from two local improvement districts organized and
known as the Main Street levee improvement district and the
North Main Street levee improvement district. Local interests
have also furnished other data showing financial and legal ability
to carry out their obligations and have agreed to contribute
$255,000 toward construction cost of the work.
   Operations and results during fiscal year. Costs incurred were
$51,873, of which $37,400 was for preparation of definite project
report, and $14,473 for planning subsequent to definite project
report.
   Condition at the end of fiscal year. Construction on the existing
project has not been started. It is anticipated that reach 2 of the
project will be ready for beneficial use by June 1960. Total costs
to June 30, 1954, were $178,000.
                                 Cost and financial summary

                                          Fiscal year ending June 30                                 Total to June
                                                                                                    30, 1954, includ-
                                                                                                    ing fiscal years
                          1950          1951         1952           1953                 1954        priorto 1950

New work:
   Appropriated___ __---------------
                          ........   -              $100, 000       $40, 000             $50, 000           $190, 000
   Cost-----------------..------------                38, 242        87, 885              51, 873            178, 000


Other new work data:
    Appropriated for succeeding fiscal year ending June 30, 1955.-...........                            $75, 000
    Estimated additional amount needed to be appropriated for com-
       pletion of existing project __     ...   .               -          ...........        ......... 7,745,000


7. NORTH       ALEXANDER            DRAINAGE             AND LEVEE                       DISTRICT, ILL.
    Location. This project is in the north end of Alexander County,
Ill., on the left bank of Mississippi River between river miles 51
and 58 above the Ohio River. The district includes the bottom
lands between the Clear Creek drainage and levee district on the
north, the bluffs on the east and west, and the East Cape Girardeau
and Clear Creek drainage district on the south and west.
    Existing project. This provides for raising and enlarging the
entire levee system consisting of 5.2 miles of levee, which was
previously reconstructed by the United States, and the construc-
tion of appurtenant works such as gravity drainage structures,
surfacing of service roads on the levee crown, provision of seepage
712         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

corrective measures, and altering the railroads at one levee crossing.
The project when completed will not in itself afford complete pro-
tection to this district; but in combination with and upon com-
pletion of authorized work in the East Cape Girardeau and Clear
Creek drainage district, and in the Miller Pond, the Clear Creek,
and the Preston drainage and levee districts, protection will have
been provided to this and the other districts named against a flood
of about 50-year frequency.      The estimated total construction
cost (1954) is $1,130,000. The project was authorized by the
Flood Control Act of June 22, 1936.
   Local cooperation. Assurances of local cooperation approved
by the county court of Alexander County, Ill., have been furnished
and were approved by the Secretary of War on June 22, 1939.
Local interests have provided evidence of the acquisition of the
necessary rights-of-way for the construction of work completed
to interim grade. Compliance with the requirements of local
cooperation for the additional work required for completion of
the project has not as yet been requested.
   Operationsand results during fiscal year. Costs incurred were
 $81,625 of which $82 was for relocations, $20,716 for levee con-
struction, $53,370 for engineering and design, $7,965 for miscel-
laneous costs, and $508 for pending adjustments.
   Condition at end of fiscal year. Construction was initiated on
the existing project in July 1939, and the project was ready for
beneficial use in September 1941. Work under the project is about
36 percent completed. The total costs to June 30, 1954, were
 $405,806 for new work.
                                   Cost and financial summary

                                              Fiscal year ending June 30                     Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                            1950              1951         1952      1953        1954        prior to 1950

New work:
   Appropriated ---        ....----------------
                                             --------   ----------   $25, 000   $300, 000           $624, 483
   Cost-----------------        $355             $333         $835    25, 133     81, 625            405, 806


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954........................... .$33, 496
    Appropriated for succeeding fiscal year ending June 30, 1955-----....--....... 505,000

      8. CLEAR CREEK DRAINAGE AND LEVEE DISTRICT, ILL.
   Location. This project is in Union and Alexander Counties,
Ill., on the left bank of Mississippi River between river miles 57
and 66 above the Ohio River. Except for some lowlands and
islands along the river, the district includes practically all the bot-
tom lands between the river and the bluffs and between Ware, Ill.,
on the north and McClure, Ill., on the south.
    Existing project. This provides for raising and enlarging the
existing levee system by reconstructing approximately 10.9 miles
of riverfront levee and 10.1 miles of back levee and the construc-
tion of appurtenant works consisting of gravity drainage struc-
tures, seepage corrective measures and surfacing service roads on
the levee crown. The project, when completed, will not in itself
afford complete protection to this district; but in combination
                          FLOOD CONTROL-ST. LOUIS, MO., DISTRICT                                         713
with and upon completion of authorized work in the East Cape
Girardeau and Clear Creek drainage district, and the North Alex-
ander, the Miller Pond, and the Preston drainage and levee
districts, protection will have been provided this and the other
districts named against a flood of about 50-year frequency. The
estimated total construction cost (1954) including $23,000 of 1936
funds used for temporary levee repair, resulting from the 1943
flood, is $4,750,000. The project was authorized by the Flood Con-
trol Act of June 22, 1936.
   Local cooperation. Forms of assurances of local cooperation
for the construction of the entire project were approved by the
Secretary of War on July 6, 1940. Local interests have provided
evidence of the acquisition of the necessary rights-of-way for
all construction work completed or under construction and have
indicated that they will be able to fulfill local cooperation re-
quirements for the remaining work features as required.
   Operations and results during fiscal year. Costs incurred were
$32,815 for engineering and design, $3,390 for other distributive
costs, and $94 for pending adjustments. Work by contract con-
sisted of levee construction at a cost of $3,779. The total costs
were $40,077.98 for new work.
   Condition at end of fiscal year. Construction on the existing
project was initiated in August 1940, and the project was ready for
beneficial use in December 1941. Work under the project is about
58 percent complete. The total costs to June 30, 1954 were $2,775,-
070.94 for new work.
                                              Cost and financial summary


                                                     Fiscal year ending June 30                 Total to June
                                                                                               30, 1954, includ-
                                                                                               ing fiscal years
                                       1950        1951        1952        1953      1954       priorto 1950

New work:
   Appropriated......               ----------------------------------------------------------- $2,680, 217
                                    ......
   Cost----------------..........
                              ...      $54,020     $43,142    $14,298      $71,112   $40,078               071
                                                                                                      2,775,


Other new work data:
                                                                           $5,196
     Unobligated balance, fiscal year ending June 30, 1954............--------------..
                                                                          200,000
     Appropriated for succeeding fiscal year ending June 30, 1955..............
     Estimated additional amount needed to be appropriated for com-
       pletion of existing project ...-..            ..... .........    1........
                                                                    ... 1,869, 783
               9. MILLER POND DRAINAGE DISTRICT, ILLINOIS
   Location. This project is in Union County, Ill., on the left
bank of Mississippi River between river miles 65 and 69 above the
Ohio River. The district includes the bottom lands between the
Missouri Pacific Railroad on the west and the bluffs on the east,
and extends from the Clear Creek drainage and levee district on
the south to Wolf Lake, Ill., on the north.
   Existing project. This provides for the raising and enlarging
of the entire levee system consisting of 2.8 miles of levee, which
was previously constructed by the United States, and the construc-
tion of service roads on the levee crown. The project when com-
pleted will not in itself afford complete protection to this district;
but in combination with and upon completion of authorized work
 714            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

in the East Cape Girardeau and Clear Creek drainage district, and
in the North Alexander, the Preston, and the Clear Creek drainage
and levee districts, protection will have been provided to this and
the other districts named against a flood of about 50-year fre-
quency. The estimated total construction cost, reviewed in 1954,
is $164,000. The project was authorized by the Flood Control Act
of June 28, 1938.
    Local cooperation.                      Assurance of local cooperation approved
by the county court of Union County, Ill., has been furnished,
and was approved by the Secretary of War on July 3, 1940. Re-
quirements of local cooperation for all work completed and under
construction are fully complied with.
    Operation and results during fiscal year.                                              Cost incurred was
$24,882 of which $863 was for engineering and design; $2,141 for
miscellaneous costs, and pending adjustments $3. Costs incurred
by contract were $21,875 for levee construction.
    Conditions at end of fiscal year.                                Construction was initiated on
the existing project in July 1940, and the project was ready for
beneficial use in December 1941. Work under the existing project
is about 94 percent complete. The total costs to June 30, 1954
were $153,727.
                                         Cost and financial summary

                                                 Fiscal year ending June 30                                 Total to June
                                                                                                           30, 1954, includ-
                                                                                                           ing fiscal years
                                  1950         1951               1952           1953            1954        prior to 1950
New work:
    Appropriated -            -               $117, 700   . ...       ..     .    .         ......                $155, 952
    Cost   --                     $2, 746       10, 816           $11, 123       $68,654         $24,882           153,727

Other new work data:
    Unobligated bialance, fiscal year ending June 30, 1954 ................. -------------.                       $2,225
    Estimated additional amount needed to be allotted for completion of
      existing project------...................................................---------------------- -----....-- 8,048
     10. PRESTON            DRAINAGE AND LEVEE DISTRICT, ILLINOIS
   Location. This project is in Union County, Ill., on the left
bank of Mississippi River between river miles 66 and 76 above the
Ohio River. The district includes practically all the bottom lands
between Mississippi River on the west, Big Muddy River on the
north, the bluffs on the east and Clear Creek drainage and levee
district on the south.
   Existing project. This provides for raising and enlarging 8.9
miles of riverfront levee and the construction of appurtenant
works consisting of gravity drainage structures, one highway
closure structure, surfacing of service roads on the levee crown,
provision of seepage corrective measures, and altering railroads
at levee crossings. The project, when completed, will not in
itself afford complete protection to this district; but in com-
bination with and upon completion of authorized work in the
East Cape Girardeau and Clear Creek drainage district, and the
North Alexander, the Miller Pond, and the Clear Creek drainage
and levee districts, protection will have been provided to this
and the other districts named against a flood of about 50-year
frequency.            The estimated total construction cost (1954)                                                      is
                        FLOOD CONTROL-ST. LOUIS, MO., DISTRICT                                                     715
 $2,450,000. The project was authorized by the Flood Control Act
approved June 22, 1936.
    Local cooperation. Forms of assurance of local cooperation,
approved by the county court of Union County, Ill., were ap-
proved by the Secretary of War on June 23, 1945. Local interests
have fully complied with all requirements of local cooperation
for that portion of the project completed or under construction;
but have not yet complied with requirements for the additional
features of work necessary for completion of the project.
    Operations and results during fiscal year. Cost incurred was
 $320,686, of which $4,687 was for engineering and design. Other
distributive costs were $19,640 and $409 for pending adjustments.
Contract costs were $295,812 for railroad relocations and $138
for levee construction.
    Conditions at end of fiscal year. Construction was initiated on
the project in October 1945, and the project was ready for bene-
ficial use in fall of 1947. Work under the existing project is about
73 percent complete. The total costs to June 30, 1954, were
 $1,783,789.
                                          Cost and financial summary

                                                   Fiscal year ending June 30                           Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                                   1950          1951             1952        1953           1954        priorto 1950

New work:
    Appropriated--------          $200, 000   -$150, 000 .    .                                              $1,713, 000
    Cost-----------------           26, 356       40, 482         $2, 940     $37, 863     $320, 686          1, 783, 789

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954................                                 ......  $2, 597
    Appropriated for succeeding fiscal year ending June 30, 1955................. 175,000
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project-................................................................................. 562, 000
11. GRAND TOWER DRAINAGE AND LEVEE DISTRICT, ILLINOIS
   Location. This project is in Jackson County, Ill., and Perry
County, Mo., on the left bank of Mississippi River between river
miles 75 and 84 above the Ohio River. The project, as enlarged by
the inclusion of part of Grand Tower Island, Mo., is bounded by
the Mississippi River on the west, Big Muddy River on the south
and east, Fountain Bluff on the northwest and the Degognia and
Fountain Bluff levee and drainage district on the north.
   Existing project. This provides for raising, enlarging, and
extending the existing levee system by construction of about 5.3
miles of riverfront levee, and 11.9 miles of back and flank levees
along the Big Muddy River, together with appurtenant works
consisting of gravity drainage structures, highway closure struc-
tures, surfacing of service roads on the levee crown, borrow pit
and seepage corrective measures and altering railroads at levee
crossings. The project, when completed, will not in itself afford
complete protection to this district; but in combination with
and upon completion of authorized work in the Degognia and
Fountain Bluff levee and drainage district, protection will have
been provided to this and the other district named, against a
flood of about 50-year frequency. The estimated total construc-
716               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY. 1954

tion cost (1954) is $4,800,000. The project was authorized by
the Flood Control Act approved June 28, 1938.
   Local cooperation. Forms of assurances of local cooperation
approved by the county( court of Jackson County, Ill., for recon-
struction of the project to the grade revised in 1944 were ap-
proved by the division engineer, Upper Mississippi Valley
Division, on October 22, 1947. Local interests have provided evi-
dence of acquisition of the necessary rights-of-way for all con-
struction work completed or under construction, and have indicated
that they will be able to fulfill local cooperation requirements for
the remaining work features as required.
   Operations and results during fiscal year. Costs incurred were
$63,593, for preliminary engineering and design; $77,432 for other
distributive costs, and $44 for pending adjustments. Work by
contract consisted of railroad relocations, $295,826; construction
of levees, $606,306; and pumping plants and drainage facilities
$108,336. The total costs were $1,151,537 for new work.
   Condition at end of fiscal year. Construction on the existing
project was initiated in October 1948, and the project was ready
for beneficial use in the spring of 1953. Work under the project is
about 87 percent complete. The total costs to June 30, 1953, were
$4,160,844 for new work.
                                            Cost and financial summary

                                                       Fiscal year ending June 30                               Total to June
                                                                                                               30, 1954, includ-
                                                                                                               ing fiscal years
                                      1950           1951            1952           1953            1954         prior to 1950
New work:
    Appropriated...                 $669, 700           000
                                                    $200,          $800, 000       $716, 000      $217, 847          $3, 933,547
                              -
     Cost.------------- 477, 952                     974, 783       226,468       1,189, 620         537
                                                                                                 1,151,                4, 160, 844

Other new work data:
    Appropriated for succeeding fiscal year ending June 30, 1955..-------............. $390, 000
    Estimated additional amount needed to be appropriated for comple-
      pletion of existing project--------.....................................................-------------------------.. 476, 453

12. DEGOGNIA AND FOUNTAIN BLUFF LEVEE AND DRAINAGE
                   DISTRICT, ILLINOIS
   Location. This project is in Jackson County, Ill., on the left
bank of Mississippi River between river miles 84 and 100 above
the Ohio River. The district embraces practically all the bottom
lands between the river and the bluffs and between Cora, Ill., on
the northwest and the Grand Tower drainage and levee district
on the south.
   Existing project. This provides for raising, enlarging, and
extending the existing levee system by reconstruction of 8.7 miles
of riverfront levee, 0.9 mile of upper flank levee along Degognia
Creek, construction of 4.6 miles of new riverfront levee and 4.2
miles of new back levee along the Big Muddy River, and the con-
struction of appurtenant works consisting of gravity drainage
structures, highway closure structures, surfacing of service road
on the levee crown and altering railroads at levee crossings. The
project, when completed, will not in itself afford complete protec-
tion to this district; but in combination with and upon completion
                       FLOOD CONTROL--ST. LOUIS, MO., DISTRICT                                                 717
of authorized work in the Grand Tower drainage and levee district,
protection will have been provided to this and the other district
named, against a flood of about 50-year frequency. The esti-
mated total construction cost (1954) is $6,080,000. The project
was authorized by the Flood Control Act approved June 22, 1936.
   Local cooperation. Assurances of local cooperation approved
by the county court of Jackson County, Ill.; were approved by the
Secretary of War September 7, 1944. Local interests have pro-
vided evidence of the acquisition of the necessary rights-of-way
for the construction of work completed or under construction
and have indicated the requirements of local cooperation for
the remaining features of work will be fully complied with.
   Operations and results during fiscal year. Costs incurred were
$77,275 for engineering and design; $20,657 for miscellaneous
costs; and $-1.150 for pending adjustments. Work by contract
cost $100,173 for levee construction. The total costs were $196,-
954.65.
   Conditions at end of fiscal year. Construction was initiated on
the existing project in September 1945, and the project was ready
for beneficial use in the fall of 1950. Work under the project is
about 67 percent complete. The total costs to June 30, 1954, were
$4,094,530.54 for new work.
                                           Cost and financial summary

                                                     Fiscal year ending June 30                       Total to June
                                                                                                     30, 1954, includ-
                                                                                                     ing fiscal years
                                    1950           1951            1952       1953        1954        priorto 1950

New work:
   Appropriated.. -----------------------------------------------
                     .                                                                   $570, 000        $4, 461, 000
   Cost.................
        --------------        142, 227          $225, 630         $119, 043   $48, 617    196,955          4,094, 531

Other new work data:
                                                                       $103, 158
    Unobligated balance, fiscal year ending June 30, 1954--.......................
                                                                         550, 000
    Appropriated for succeeding fiscal year ending June 30, 1955............
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project.................................................
                                                                      1, 069,000

13. PERRY COUNTY DRAINAGE AND LEVEE DISTRICTS NOS. 1,2,
                    AND 3, MISSOURI
   Location. This project is in Perry County, Mo., and Randolph
County, Ill., on the right bank of Mississippi River between river
miles 94 and 111 above the Ohio River. The project, as enlarged by
inclusion of Crain and Puckett Islands, includes that portion of the
bottom lands between the river and the bluffs and between Red
Rock Landing, Mo., and Kaskaskia Island.
   Existing project. This provides for raising and enlarging the
existing levee system by reconstruction of 7.7 miles of riverfront
levee, 14.1 miles of back levee, and 4.0 miles of upper flank levee;
construction of 7.3 miles of new riverfront levee; and the construc-
tion of appurtenant works consisting of gravity drainage struc-
tures, highway closure structures, surfacing of service roads on
the levee crown and altering railroads at levee crossings. The
project, when completed, will afford protection to the district
against a flood of about 50-year frequency. The estimated total
718            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

construction cost (1954), including $41,000 of 1936 funds used
for temporary levee repairs, resulting from the 1943 flood, is
$8,140,000. The project was authorized by the Flood Control Act
approved June 22, 1936.
   Local cooperation. Assurances of local cooperation for the
project were approved by the Secretary of War as follows:
District No. 1, December 30, 1936; district No. 2, March 16,
1937; district No. 3, September 29, 1936. Requirements of local
cooperation for all work completed and under construction are
fully complied with. Local interests have informally indicated
they will be able to fulfill local cooperation requirements for the
remaining work as required.
   Operations and results during fiscal year. Costs incurred were
$108,142 for engineering and design; $81,255 for miscellaneous
costs; $5,947 for material on hand; and $-164 for pending ad-
justments. Levee construction by contract cost $581,199. The
total costs were $776,379.02 for new work.
   Condition at end of fiscal year. Construction was initiated on
the existing project in December 1937 and the project was ready
for beneficial use in the fall of 1946. Work under the existing
project is about 45 percent complete. The total costs to June 30,
1954, were $3,693,522.51 for new work.
                                       Cost and financial summary

                                             Fiscal year ending June 30                               Total to June
                                                                                                     30, 1954, includ-
                                                                                                     ing fiscal years
                                1950        1951          1952          1953              1954         priorto 1950
New work:
                 --------
   Appropriated ....          $744, 100    $300, 000   $1, 000, 000    $796, 000    ..                    $3, 745, 375
   Cost----------------.........233, 150    460, 737       423, 497   1, 156, 333        $776, 379         3, 693, 523


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954---------....... --............
                                                                                  $20,295
    Appropriated for succeeding fiscal year ending June 30, 1955...........
                                                                        ------- 265,000
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project------..........................-----------------
                                                                               4, 129, 625

                14. PRAIRIE DU ROCHER AND VICINITY, ILL.
   Location. This project is in Randolph County, Ill., on the left
bank of Mississippi River between river miles 118 and 130 above
the Ohio River. The district includes the bottom land between the
river and the bluffs, and extends from the present channel of
Prairie du Rocher Creek on the north to the Kaskaskia River on the
south.
   Existing project. This provides for reconstructing about 2.4
miles of upper flank levee, constructing 0.5 miles of new upper
flank levee, 10.4 miles of new riverfront levee, and 2.8 miles of new
lower flank levee, and constructing appurtenant works, consisting
of gravity drainage structures, highway and railroad closure struc-
tures, surfacing of service roads on the levee crown, borrow pit
and seepage corrective measures and altering railroads at a levee
crossing. The project, when completed, will afford protection
to this district against a flood of about 50-year frequency, The
estimated total construction cost (1954) is $3,932,000. The proj-
                    FLOOD CONTROL-ST. LOUIS, MO., DISTRICT                                                              719
ect was authorized by the Flood Control Act approved July 24,
1946 (H. Doc. 222, 80th Cong., 1st sess.).
   Local cooperation, Forms of assurances of local cooperation
approved by the county court of Randolph County, Ill., for the
construction of the entire project have been received from the
Prairie du Rocher and Modoc levee and drainage district and
from the Edgar Lakes drainage and levee district. The assur-
ances were approved by the division engineer, Upper Mississippi
Valley Division, on November 6, 1947. Local interests have pro-
vided evidence of acquisition of the necessary rights-of-way for all
work completed or under construction and have indicated that they
will be able to fulfill local cooperation requirements for the re-
maining work features as required.
   Operation and results during fiscal year. Costs incurred were
$14,693 for engineering and design; $59,953 for miscellaneous
costs; $-14,069 for credit to stores account; and $-3,961 for
pending adjustments. Work by contract consisted of $11,092 for
drainage facilities; $399,525 for levee construction; and $-137
reimbursed by the Missouri Pacific Railroad on relocations. The
total costs were $467,095.69 for new work.
   Condition at end of fiscal year. Construction on the existing
project was initiated in August 1948, and the project was ready
for beneficial use in April 1951. Work under the project is about
93 percent complete. The total costs to June 30, 1954, were $3,-
653,630.96 for new work.
                                        Cost and financial summary

                                                   Fiscal year ending June 30                                  Total to June
                                                                                                            . 30, 1954, includ-
                                                                                                              ing fiscal years
                                 1950             1951             1952             1953        1954            priorto 1950

New work:
   Appropriated    .. _-   _    $700, 000        $100, 000        $900, 000       $653, 000 __-,_--     _-         $3, 804, 000
   Cost       -      -         1, 039, 929        542, 636         158, 473    1 1, 098, 981    $467, 096           3, 653, 631


  1 Includes the amount of $13,697.09 which was omitted from costs in 1953 annual report.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954---.....------....-........ .                               $4, 387
    Estimated additional amount needed to be appropriated for comple-
        tion of existing project             .   - --
                                                 ....        ..                 ....-
                                                                    .......-------------..          -......-...
                                                                                                            ....   103, 000


   15. STRINGTOWN-FORT                           CHARTRES AND                          IVY LANDING, ILL.
    Location. This project is in Monroe and Randolph Counties,
Ill., on the left bank of Mississippi River between river miles 130
and 137 above the Ohio River. The project includes all of the
Stringtown district and the downstream portion of the Fort Char-
tres and Ivy Landing district and includes the bottom lands be-
tween the river and the bluffs and extends from Prairie du Rocher
Creek on the south to the north boundary of the Stringtown dis-
trict.
    Existing project. This provides for raising, enlarging, and
extending the existing levee system by reconstruction of 4.7 miles
of existing riverfront levee, construction of 2.6 miles of new river-
front levee, reconstruction of 2.3 miles of existing lower flank
720         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

levee, construction of 0.4 mile of new lower flank levee, and appur-
tenant works consisting of gravity drainage structures, one high-
way closure structure, surfacing of service. roads on the levee
crown, borrow pit and seepage corrective measures and altering
railroads at one levee crossing. The project, when completed,
will not in itself afford complete protection to this district; but
in combination with and upon completion of authorized work
in the Fort Chartres and Ivy Landing drainage district and the
Harrisonville and Ivy Landing drainage and levee district, pro-
tection will have been provided to this and the other districts
named against a flood of about 50-year frequency. The estimated
total construction cost (1954) is $2,225,000. The project was au-
thorized by the Flood Control Act approved June 28, 1938.
   Local cooperation. Fully complied with.
   Operations and results during fiscal year. Costs incurred were
$7,438 for engineering and design, $14,319 for miscellaneous costs;
$-11,081 for credit to stores account; and $328 for pending ad-
justments. Contract costs consisted of $138,489 for levee con-
struction, and $-497 reimbursed by the Missouri Pacific Railroad
for relocations. The total costs were $148,995.84 for new work.
   Condition at end of fiscal year. Construction on the existing
project was initiated in January 1948, and the project was ready
for beneficial use in the fall of 1950. Work under the project is
about 93 percent complete. The total costs to June 30, 1954, were
$2,071,919.69 for new work.
                                   Cost and financial summary

                                            Fiscal year ending June 30                      Total to June
                                                                                           30, 1954, includ-
                                                                                           ing fiscal years
                            1950           1951        1952        1953         1954        prior to 1950

New work:
   Appropriated..._       -$75, 000    .                          $400, 000 ._.------..          $2, 163, 997
   Cost.. -  -    -         151, 475       $79, 374    $65, 109    328, 293    $148, 996          2, 071, 920


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954.............................. $81,266
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project................................... . . . _. __....-...........
                                                                                 ....         .. 61, 003
16. FORT CHARTRES AND IVY LANDING DRAINAGE DISTRICT
                                           NO. 5, ILL.
   Location. This project is in Monroe County, Ill., on the left
bank of Mississippi River between river miles 137 and 141 above
the Ohio River. The district includes that portion of the bottom
lands between the river and the bluffs, the Harrisonville and Ivy
Landing drainage and the levee district No. 2 on the north and the
north boundary of the Stringtown district on the south.
   Existing project. This provides for the construction of about 3
miles of riverfront levee and the construction of appurtenant works
consisting of gravity drainage structures, seepage corrective meas-
ures and surfacing of service roads on the levee crown. The
project does not in itself afford complete protection to this dis-
trict; but in combination with and upon completion of authorized
work in the Harrisonville and Ivy Landing drainage and levee
district and the Stringtown-Fort Chartres and Ivy Landing dis-
                    FLOOD CONTROL--ST. LOUIS, MO., DISTRICT                                               721
trict, protection will have been provided this and the other districts
named against a flood of about 50-year frequency. The estimated
total construction cost (1954) is $1,240,000. The project was
authorized by the Flood Control Act approved June 22, 1936.
   Local cooperation. Fully complied with.
   Operations and results during fiscal year. Costs incurred were
$5,888 for engineering and design; $16,644 for miscellaneous items,
and $680 for pending adjustments. Construction of levees by con-
tract cost $96,833. The total costs were $120,044.62 for new work.
   Condition at end of fiscal year. Construction was initiated on
the existing project in August 1947, and the project was ready for
beneficial use in the fall of 1950. Work under the project is about
85 percent complete. The total costs to June 30, 1954, were $1,-
053,793.67 for new work.
                                       Cost and financial summary

                                               Fiscal year ending June 30                        Total to June
                                                                                                30, 1954, includ-
                                                                                                ing fiscal years
                                1950          1951          1952          1953       1954         priorto 1950
New work:
   Appropriated-                .     ....    . ....-    5 .....     "   $249,900    $47, 200        $1, 097, 185
   Cost .............----------------   $21,501     $2 325      $426      139, 339   120, 045         1,053, 794


Other new work data:
                                                                   --.. $41, 893
    Unobligated balance, fiscal year ending June 30, 1954......----------........
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project           __--.........................
                                        ---                          -. 142,815

17. HARRISONVILLE                   AND IVY LANDING DRAINAGE AND LEVEE
                                 DISTRICT NO. 2, ILLINOIS
   Location. This project is in Monroe County, Ill., on the left
bank of Mississippi River between river miles 141 and 156 above
the Ohio River. The district is bounded by Fountain Creek and
the Mississippi River on the north and west, on the east by the
bluffs and by Fort Chartres and Ivy Landing drainage and levee
district No. 5 on the south.
   Existing project. This provides for raising and enlarging the
existing levee system by the reconstruction of about 9.8 miles of
riverfront levee, 5.4 miles of flank levee, the construction of 6.2
miles of new levee, and the construction of appurtenant works con-
sisting of gravity drainage structures, Fountain Creek diversion
channel, surfacing of service roads on the levee crown, borrow pit
and seepage corrective measures and altering railroad at one
levee crossing. The project, when completed, will not in itself
afford complete protection to this district; but upon completion
of authorized work in the Fort Chartres and Ivy Landing drain-
age and levee district and the Stringtown-Fort Chartres and Ivy
Landing district, protection will have been provided this and the
other districts named against a flood of about 50-year frequency.
The estimated total construction cost (1954) is $4,500,000. The
project was authorized by the Flood Control Act approved June
22, 1936.
   Local cooperation. Fully complied with.
   Operations and results during fiscal year. Costs incurred were
$16,733 for engineering and design; $43,294 for miscellaneous
722                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

items; $-2,516 for credit to stores and account; and $-768 for
pending adjustments. Levee work by contract cost $387,540.
The total costs were $444,282.91 for new work.
   Condition at end of fiscal year. Construction was initiated on
the existing project in May 1946, and the project was ready for
beneficial use in the fall of 1950. Work under the existing project
is about 93 percent complete. The total costs to June 30, 1954, were
$4,199,734.27 for new work.
                                                Cost and financial summary

                                                           Fiscal year ending June 30                                    Total to June
                                                                                                                        30, 1954, includ-
                                                                                                                        ing fiscal years
                                         1950            1951             1952            1953             1954           priorto 1950

New work:
   Appropriated --------                $17, 500 ---                                                      $429, 947            $4,349,947
     Cost----------------               245, 273         $30, 355          $3, 700       $388, 044         444, 283             4, 199, 734

Other new work data:
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project..........................................--------------------------........................------.. $150, 053
18. COLUMBIA DRAINAGE AND LEVEE DISTRICT NO. 3, ILLINOIS
    Location. This project is in Monroe County, Ill., on the left
bank of Mississippi River between river miles 157 and 166.5 above
the Ohio River. The district embraces most of the bottom lands
between the river and the bluffs and between Fountain Creek on
the south and Columbia Creek on the north.
    Existing project. This provides for raising and enlarging the
existing levee system by the reconstruction of about 10.4 miles of
riverfront levee and 9.7 miles of flank levee, and the construction of
appurtenant works consisting of gravity drainage structures, sur-
facing of service roads on the levee crown, seepage corrective
measures and altering railroads at levee crossings. The project,
when completed, will afford protection to this district against a
flood of about 50-year frequency. The estimated total construc-
tion cost (1954), including $45,000 of 1936 funds used for
temporary levee repair, resulting from the 1943 flood, is $2,917,000.
The project was authorized by the Flood Control Act approved
June 22, 1936.
    Local cooperation. Local interests have provided evidence of
the acquisition of the necessary rights-of-way for all work com-
pleted or under construction and have indicated that they will
be able to fulfill local cooperation requirements for the remaining
work as required.
    Operationsand results during fiscal year. Costs incurred were
$22,011 for engineering and design; $32,734 for miscellaneous
items; and $28 for pending adjustments. Work by contract con-
sisted of levee construction at a cost of $203,264 and drainage
structure at a cost of $11,466. The total costs were $269,502.94
for new work.
    Condition at end of fiscal year. Construction on the existing
project was initiated in June 1938, and the project was ready for
beneficial use in the fall of 1941. Work under the project is about
88 percent complete. The total costs to June 30, 1954, were $2,-
553,699.92 for new work.
                          FLOOD CONTROL-ST. LOUIS, MO., DISTRICT                                                                   723
                                               Cost and financial summary

                                                          Fiscal year ending June 30                                   Total to June
                                                                                                                      30, 1954, includ-
                                                                                                                      ing fiscal years
                                        1950            1951             1952            1953             1954          priorto 1950
New work:
   Appropriated --------              $372, 100 ---                    $400, 000       $299, 000$2,                             777, 000
     Cost-_-.                          484,333         $408, 160          78,495         492, 687       $269, 503             2, 553, 700


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954----------....---.......---.........--. -- 97, 761
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project------................----------....-------------------............................................. 140,000

19. WILSON                AND         WENKEL AND PRAIRIE DU PONT                                                    DRAINAGE
                                      AND LEVEE DISTRICTS, ILL.

    Location. This project is in Monroe and St. Clair Counties, Ill.,
on the left bank of Mississippi River between river miles 168 and
175 above the Ohio River. The district includes the bottom lands
between the river and the bluffs and extends from the approach to
the Jefferson Barracks bridge north to Prairie du Pont Creek. The
district is now known as the Prairie du Pont drainage and levee
district.
    Existing project. This provides for raising and enlarging the
existing levee system by the reconstruction of about 3.7 miles of
riverfront levee and 3.6 miles of upper flank levee; construction of
3.6 miles of new lower flank levee; and the construction of appur-
tenant works consisting of gravity drainage structures, highway
closure structures, surfacing of service roads on the levee crown,
borrow pit corrective measures and altering railroads at levee
crossings. The project, when completed, will afford protection
to this district against a flood of about 200-year frequency. The
estimated total construction cost (1954) is $4,190,000.            The
project was authorized by the Flood Control Act approved June
22, 1936.
   Local cooperation. Local interests have provided evidence of
the acquisition of the necessary rights-of-way for all work com-
pleted or under construction, and have indicated they will be
able to fulfill local cooperation requirements for the remaining
works as required.
   Recommended modifications of project. The Chief of Engi-
neers, by letter dated March 22, 1954, recommended, subject to
certain conditions of local cooperation, modification of the existing
project for the Wilson and Wenkel and Prairie du Pont drainage
and levee district, Illinois, to eliminate the lower flank levee and to
substitute therefor a riverfront levee and a lower flank levee along
Columbia Creek to provide flood protection for Fish Lake drain-
age and levee district No. 8, Illinois. The Federal cost (1954) is
$480,000. The non-Federal cost for meeting the stipulated condi-
tions of local cooperation is $143,100. (H. Doc, No. 396, 83d Cong.,
2d sess.)
   Operationsand results during fiscal year. Costs incurred were
$49,292 for engineering and design; $10,864 for miscellaneous
items; $5,618 for stores account; and $462 for pending adjust-
ments. Work by contract consisted of levee construction at a cost
724          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

of $71,337; and railroad relocations at a cost of $68. The total
costs were $137,640.52 for new work.
   Conditions at end of fiscal year. Construction was initiated on
the existing project in November 1935, and the project was ready
for beneficial use in the fall of 1950. Work under the project is
about 38 percent complete. The total costs to June 30, 1954, were
$1,581,678.56 for new work.
                                  Cost and financial summary

                                        Fiscal year ending June 30                          Total to June
                                                                                           30, 1954, includ-
                                                                                           ing fiscal years
                           1950        1951          1952           1953        1954        prior to 1950

New work:
   Appropriated _         $
                         ___$43,.903             .   -          .....          $280, 000        $1, 857, 097
   Cost-   . _            $76,352      193,106       $69, 689       $91, 461    137, 641          1,581, 679


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954..               $187,462
                                                             ...------------...
                                                                  -
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project ---............                        2,332,903


                    20. EAST ST. LOUIS AND VICINITY,                           ILL.
    Location. This project is in St. Clair and Madison Counties,
Ill., on left bank of Mississippi River between river miles 175 and
195 above the Ohio River. The project includes all the bottom
lands between the bluffs on the east and Mississippi River and
Chain of Rocks canal on the west, and extends from Cahokia diver-
sion channel on the north to Prairie du Pont Creek on the south.
    Existing project. This provides for raising and enlarging the
existing levee system by the reconstruction of about 9.0 miles of
riverfront levee, 4.9 miles of upper flank levee, 7 miles of the lower
flank levee, construction of 0.9 mile of new riverfront levee, and
0.4 mile of riverfront floodwall, together with the necessary appur-
tenant works consisting of gravity drainage structures, closure
structures at highway crossings, alterations and reconstruction of
existing pumping plants, surfacing of service roads on the levee
crown, seepage corrective measures, and making necessary altera-
tions to railroad tracks and bridges at levee crossings. Approxi-
mately 10 miles of the project riverfront levee need not be
constructed as protection will be provided along this reach by
the levee constructed as part of the Chain of Rocks canal. The
project, when completed, will afford protection to the area against
a flood of about 200-year frequency. The estimated total con-
struction cost (1954) is $12,900,000. The project was authorized
by the Flood Control Act approved June 22, 1936.
    Local cooperation. Assurances of local cooperation for the
entire project were approved by the Secretary of War on March
24, 1937. Local interests have provided evidence of acquisition
of the necessary rights-of-way for all work completed or under
construction and have indicated they will be able to fulfill local
cooperation requirements for the remaining work as required.
  Operationsand results during fiscal year. Costs incurred were
$147,698 for engineering and design; $64,973 for miscellaneous
                                FLOOD CONTROL-ST. LOUIS, MO., DISTRICT                                                  725
items; $23,899 for stores account; and $3,185 for pending adjust-
ments. Work by contract consisted of railroad relocations at a
cost of $68; levee construction at a cost of $548,320; floodwall con-
struction at a cost of $30,244; and pumping plants and drainage
facilities at a cost of $73,339. The total costs were $891,725.65 for
new work.
   Condition at end of fiscal year. Construction was initiated on
the existing project in November 1937, and project was partially
ready for beneficial use in fall of 1942; also the locally constructed
levee has never been overtopped. Work under the existing project
is about 40 percent complete. The total costs to June 30, 1954,
were $5,217,935.85 from regular funds, all for new work.
                                                  Cost and financial summary

                                                          Fiscal year ending June 30                           Total to June
                                                                                                              30, 1954, includ-
                                                                                                              ing fiscal years
                                            1950         1951.         1952           1953         1954         prior to 1950
New work:
   Appropriated...-----..---.              $520, 900    $200, 000   $1, 500, 000   $1, 294, 000   $100, 000        $5, 869, 200
    Cost.......----------------.........    657, 306   1,181, 247      411, 921     1,261,519      891, 726         5, 217, 936


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954....----.....------..                     ..  . $401, 679
    Appropriated for succeeding fiscal year ending June 301 1955................                          650,000
    Estimated additional amount needed to be appropriated for com-
                                                                                        --------------- 6,380,800
      pletion of existing project..---------....------............................................


21. CHOUTEAU, NAMEOKI, AND VENICE DRAINAGE AND LEVEE
                                                   DISTRICT, ILLINOIS
   Location. This project, in Madison County, Ill., lies on, but
not adjacent to, the left bank of the Mississippi River between river
miles 188 and 195 above Ohio River, and is bounded on the north by
Cahokia diversion channel, on the east by East Side levee and sani-
tary district, and on the west by the east levee of the Chain of
Rocks canal, running to a point on the south.
   Existing project. This improvement was authorized by the
Flood Control Act of June 22, 1936, and provides for raising and
enlarging the existing levee system. However, the project was
modified by the Chain of Rocks canal, authorized by the River and
Harbor Act of March 2, 1945. As the major portion of the district
lies east of the Chain of Rocks canal, it will be protected by
the canal and the East St. Louis, Ill., levees. It is proposed to
reconstruct or relocate, adjacent to the Chain of Rocks canal levee,
the existing pumping plant of this district under authority con-
tained in the Flood Control Act of June 22, 1936. The current
estimated construction cost approved in 1951 is $190,000.
   Local cooperation. Assurances of local cooperation approved
by the county court of Madison County, Ill., have been furnished
and were approved by the Chief of Engineers on June 23, 1950.
   Operations and results during fiscal year. Costs incurred were
$141 for engineering and design, $26 for miscellaneous items, and
$138 for hired labor work on pumping plant. The toal costs were
$304.64 for new work.
726          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Condition at end of fiscal year. Construction on the existing
project was initiated in June 1950, and the project was ready for
beneficial use in the fall of 1951. Work under the existing project
is 100 percent complete. The total costs to June 30, 1954, were
$185,440.01 for new work.
                                  Cost and financial summary

                                        Fiscal year ending June 30                        Total to June
                                                                                         30, 1954, includ-
                                                                                         ing fiscal years
                           1950        1951        1952        1953            1954       prior to 1950
New work:
   Appropriated .-....    - $30, 000   $30, 000                           -   -$4,300            $185, 700
   Cost _______ _______       9, 669   146, 716     $1, 089     $1, 518            305            185, 440


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954......                                    $260

  22. WOOD RIVER DRAINAGE AND LEVEE DISTRICT, ILLINOIS
   Location. The project lies in Madison County, Ill., on the left
bank of Mississippi River between river miles 195 and 203 above
the Ohio River. The district includes the bottom lands between the
river and the bluffs and extends from the Cahokia diversion chan-
nel on the south to opposite lock and dam No. 26 at Alton, Ill., on
the north. The small industrial cities of Hartford, Wood River,
Roxana, and East Alton and part of the Alton riverfront, lie within
the district.
   Existing project. This provides for raising, enlarging, and
extending the existing levee system; and includes the reconstruc-
tion of 5.4 miles of existing flank levee along Wood River, 2.6 miles
of existing lower flank levee along Cahokia diversion channel, and
0.6 mile of existing lower flank levee along Indian Creek; construc-
tion of 2 miles of new flank levee along Wood River; 8.1 miles of
new riverfront levees along the Mississippi River; and 1.4 miles of
new lower flank along the Cleveland, Cincinnati, Chicago & St.
Louis Railroad; together with the necessary appurtenant works
consisting of gravity drainage structures, highway and railroad
closure structures, alterations to existing or construction of new
pumping plants, surfacing of service road on the levee crown, mak-
ing necessary alterations to railroad tracks and bridges at levee
crossing, seepage corrective measures and construction of a low-
water dam at the mouth of Wood River. The project when com-
pleted will afford protection to this district against a flood of
about 200-year frequency. The estimated total construction cost
(1954) is $13,100,000. The project was authorized by the Flood
Control Act of June 28, 1938.
   Local cooperation. Local interests have provided evidence
of the acquisition of the necessary rights-of-way for all work
completed or under construction and have indicated they will be
able to fulfill local cooperation requirements for the remaining
work as required.
   Operationsand results during fiscal year. Costs incurred were
$136,996 for engineering and design; $88,271 for miscellaneous
items; and $13 for pending adjustments. Work by contract con-
sisted of levee construction at a cost of $559,094; and pumping
                   FLOOD CONTROL-ST. LOUIS, MO., DISTRICT                                                 727
plants and drainage facilities at a cost of $339,040. The total costs
were $1,123,413.76 for new work.
   Condition at end of fiscal year. Construction was initiated on
the existing project in July 1947, and the project was ready for
beneficial use in the fall of 1952. Work under the project is about
51 percent complete. The total Federal costs to June 30, 1954, were
$7,778,927.61 for new work. In addition, $23,000 have been ex-
pended from contributed funds. Total costs to June 30, 1954, were
$7,801,927.61.
                                     Cost and financial summary

                                             Fiscal year ending June 30                         Total to June
                                                                                               30, 1954, includ-
                                                                                               ing fiscal years
                              1950          1951        1952         1953          1954          prior to 1950
New work:
   Appropriated   .......    $425, 000     $280, 000   $915, 000    $844, 000     $500, 000          $7, 745, 000
   Cost                     1, 294,-642   1, 782,119    461, 175   1, 391, 842   1, 123, 414          7, 778, 928


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954--------........-..       --.. ... $41,053
    Appropriated for succeeding fiscal year ending June 30, 1955..------..........            345, 000
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project ........................ ----------.............         5, 010, 000

  23. CARLYLE RESERVOIR, UPPER MISSISSIPPI RIVER BASIN,
                         ILLINOIS
   Location. The Carlyle Reservoir will be located on the Kas-
kaskia River, Ill., extending from about mile 107 to mile 148 above
the mouth of that river, which enters the Mississippi River at mile
118 above the mouth of Ohio River. The dam will be located at
mile 107, about one mile upstream from the town of Carlyle, and
the proposed reservoir will extend northeastward through Clinton,
Marion, and Fayette Counties, Ill.
   Existing project. The plan of improvement provides for the
construction of a compacted earth-fill dam across the main valley
floor, and a reinforced concrete spillway with tainter gates and
sluices. The crest of the dam will be at elevation 474, approxi-
mately 55 feet above the valley floor. The total length of the
structure including the spillway section will be about 6,535 feet.
The spillway structure will consist of an ogee overflow section sur-
mounted by seven 40-foot by 30-foot tainter gates. The outlet
works for controlling discharge under normal operating conditions
will consist of four rectangular 8-foot by 10-foot sluices located in
the nonoverflow section of the spillway. Because of the topography
near the dam it will be necessary to construct three earth-fill sad-
dle dams, one north and two east of Carlyle, in order to contain the
maximum pool level proposed for the reservoir. Total length of
these embankments will be about 35,650 feet. The maximum res-
ervoir area will be 57,500 acres. The total storage capacity is 983,-
000 acre-feet, of which 700,000 acre-feet will be for flood control,
233,000 acre-feet for water supply, pollution abatement, fish and
wildlife, and recreational use, and 50,000 acre-feet for sediment
retention. Total drainage area above the dam site is 2,680 square
miles. The storage of flood waters in the reservoir will provide
728         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

substantial flood control benefits to about 42,000 acres of land on
Kaskaskia River outside levee districts below the dam, in addition
to providing navigation and flood control benefits on the middle and
lower Mississippi Rivers, and recreation, pollution abatement, wa-
ter supply and fish and wildlife benefits on the Kaskaskia River.
   The Carlyle Reservoir was made eligible for selection as a unit of
the general comprehensive plan for flood control and other purposes
in the upper Mississippi River Basin under the Flood Control Act
approved June 28, 1938. The latest estimate of the cost of the
project (revised in 1954) is $32,500,000 of which $26,980,000 is for
construction and $5,520,000 is for lands and damages.
  Local cooperation. None required.
   Operationsand results during fiscal year. None.
   Condition at end of fiscal year. No work has been done. Plan-
ning will be initiated in fiscal year 1955.
                              Cost and financial summary
Other new work data:
    Appropriated for succeeding fiscal year ending June 30, 1955............     $50, 000
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project-.-....... ...     --.--....                32, 450, 000

  24. UPPER       MISSISSIPPI RIVER            BASIN, ST. LOUIS          DISTRICT
   Location. The Mississippi River Basin above the Ohio River,
exclusive of the Missouri River Basin, in the St. Louis district.
   Existing project. The Flood Control Act of June 28, 1938,
approved the general comprehensive plan for flood control and
other purposes in the upper Mississippi River Basin described in
the Flood Control Committee Document 1, 75th Congress, 1st ses-
sion, with such modifications thereof as in the discretion of the
Secretary of War and the Chief of Engineers may be advisable,
and authorized $6,600,000 for reservoirs and $2,700,000 for local
flood-protection works on the upper Mississippi and Illinois Rivers;
the reservoirs and local protection projects to be selected and ap-
proved by the Chief of Engineers. The act specifically provides
that the authorization shall include the enlargement and extension
of a system of levees located on the south side of the Sangamon
River east of Chandlerville, Ill., as set forth in House Document
No. 604, 75th Congress, 3d session. The Flood Control Act of
December 22, 1944, authorized to be appropriated the additional
sum of $10 million for prosecution of the comprehensive plan, in-
cluding the Red Rock Reservoir on the Des Moines River. The
Flood Control Act of July 24, 1946, authorized an additional ap-
propriation of $10 million for prosecution of the comprehensive
plan. The Flood Control Act of May 17, 1950, authorizes an addi-
tional appropriation of $15 million for the prosecution of the com-
prehensive plan. The following individual projects located in the
St. Louis district were considered in the comprehensive plan.
                         FLOOD CONTROL-ST. LOUIS, MO., DISTRICT                                                                               729
                                                                  Reservoirs
~_                                                      ___                                                                        4




                                                                                                                                          Total
                  Name                             Tributary basin                                          State                       estimated
                                                                                                                                           cost 1
                                       I----                                            I                                  -       1-


Merameo ...---........                    Meramec..-                                 . Missouri-..                                      $25, 100, 000
Union.., ..............                          do .
                                                    -...                          . .. . . .do..__.
                                                                               -....                                                     16, 200, 000
                  -...
Cedar Hill- -- ......
                                   -    l----do------

                                                                                                                                         21, 400, 000
Carlyle 2...............                  Kaskaskia.                                        Illinois...                                  32, 500, 000
Joanna ......
        -     ........                    Salt.......                       ......          Missouri_.                                   33, 700, 000
                                                                                                                                   e




  SEstimate revised in 1954.
  2   See individual report for details of project.


                          Estimated construction costs of levee
Mississippi River:
   Wood River levee project, Illinois 1 2............................... ---.-...---------------.                              $13, 100, 000
      Stringtown-Fort Chartres and Ivy Landing, 11l.1 2_                 .                                                         2,225,000
      Kaskaskia Island levee project, Illinois 2..............                                                                     3,050,000
      Grand Tower levee project, Illinois 1 2..........................                                                            4, 800,000
      Miller Pond levee project, Illinois 1 2.............................                                                            164,000
Illinois River:
      Meredosia Lake and Willow Creek levee, Illinois S                                                                                  249,738
Kaskaskia River, Ill.:
      Levees between New Athens and Carlyle, Ill2..............                                                                    7, 700,000
  ' See individual report for details of project.
  2 Estimate revised in 1954.
  3 Complete.

  Operationsand results during fiscal year. There were no costs
for general studies on the development of the comprehensive
basin plan.
  Condition at end of fiscal year. The progress of work on levee
projects selected for construction under this authorization is given
in individual reports. The total costs and expenditures for general
studies for the development of the comprehensive basin plan to
June 30, 1954, were $823,643.51 from regular funds for new work.
                                               Cost and financial summary

                                                              Fiscal year ending June 30                                        Total to June
                                                                                                                               30, 1954, includ-
                                                                                                                               ing fiscal years
                                   1950                    1951         j     1952              1953                1954         prior to 1950
New work:
   Appropriated                  _$100, 000             -$28,    585        -$4,     272 --            ..   . .........                   $823, 644
   Cost .-----                         82, 757                43, 798              4, 222 -------------------------                         823, 644
                                                  ~                                         .                                  1
730             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                   25.     INACTIVE            FLOOD           CONTROL             PROJECTS

                                                                       Cost and expenditures
                                                            For last      to June 30, 1954                 Estimated
                                                        full report,                                        amount
                  Name of project                             see                                           required
                                                            annual        Con-             Operation           to 1
                                                            report     struction              and           complete
                                                             for-                         maintenance
1. Cache River diversion, Ill___---...-.-..        --.      1953          $2, 837, 114                         (2-
2. Emergency bank protection for certain high-              1950               50, 000
      way and railroad facilities at Price Land-
      ing, Mo. (Sec. 12, Flood Control Act of
      Dec. 22, 1944)
3. Emergency repairs to levees on Mississippi,              1953      .                     1,033, 279         ()
      Illinois and Kaskaskia Rivers, and flood
      fighting and rescue work (Sec. 5, Flood
       Control Act of Aug. 18, 1941, as amended)
4. Emergency protection for certain highway                 1952              50, 000                         (2)
      and railroad facilities at Chester, Ill. Bridge
       (Sec. 12, Flood Control Act of Dec. 22, 1944).
  5. Emergency protection for Illinois approach,             1946              25, 000                         ()
       Chain of Rocks Bridge (Sec. 12, Flood Con-
      trol Act of Dec. 22, -1944).
6. Kaskaskia Island drainage and levee district,            1949             296, 521 I--........---- -   1 $2, 753,500
      Ill.
  7. McGee Creek levee and drainage district,                1940                                               597,000
      Illinois River, Ill.5
8. Meredosia Lake and Willow Creek drainage                 1944             249, 738                          (2)
                                       6 - -- Ill.
      and levee districts, Illinois River,              -
9. Riverland drainage district, Mo. .......                 1938                                                288, 000
10. Ste. Genevieve levee district No. 1, Mo.4_..._           1949                                             1, 720, 000
11. St. Louis County
                  7       drainage and levee dis-            1938                                                695, 000
      trict, Mo.
12. Wiedmer Chemicals
                  8         drainage and levee dis-          1938                                               511,000
      trict, Mo.

  1 Revised in 1954.
  2 Completed.
  $ Work complete pending another flood.
  4 Work deferred pending a review of H. Doc. 669, 76th Cong., 3d sess., which may modify the project
recommended in H. Doec. 727, 77th Cong., 2d sess., authorized by the Flood Control Act of Dec. 22, 1944.
  6 Work deferred pending decision regarding alterations to Wabash R. R. bridge at Meredosia, Ill.
  6 Low-lying lands in this district acquired under authority of the River and Harbor Act of Aug. 26, 1937;
protection for remaining lands in the district deferred pending further study.
  7 May be modified due to selection of this area by city of St. Louis for a second major airport, which would
require greater protection than previously contemplated.
  SAction deferred pending further study.


                              26. GENERAL INVESTIGATIONS

   Examinations and surveys. The costs and expenditures of all
general investigations during the fiscal year were $61,086. There
were no accounts receivable nor unexpended balances at the end of
the fiscal year. The anticipated allotment of $51,920 will be applied
to collection and study of basic data and to advancement or com-
pletion of work on the following reports: Illinois River and Kas-
kaskia River, Ill., Ste. Genevieve-St. Marys, Crystal City-Festus,
and Mississippi River, Missouri River to Minneapolis, Minn. (Agri-
cultural Areas). Cost of examinations and surveys for fiscal year
was $56,586.
  Collection and study of basic data. During the fiscal year work
was performed on the comprehensive stream gaging program,
sedimentation studies, flood investigations, and revision of the flood
emergency manual. Collection and study of basic data cost $4500
during the fiscal year.
                       FLOOD CONTROL-ST. LOUIS, MO., DISTRICT                                                                         731
     27. INSPECTION OF COMPLETED WORKS FLOOD                                                                       CONTROL
                          PROJECTS

  During the fiscal year costs and expenditures incurred for in-
spection of local protection projects were $12,134.48. The total
costs and expenditures to June 30, 1954, were $24,350.00.
                                             Cost   and     financial         summary



                                                          Fiscal year ending June 30                                    Total to June

                                      1950           1951                 1952                 1953         1954
                                                                                                                       ing
                                                                                                                        fiscal
                                                                                                                          years
                                                                                                                       30, 1954, includ-

                                                                                                                         prior to 1950

Maintenance:
   Appropriated                                             250- .......
                                                        $____8,                    .            $4, 000     $12, 100              $24, 350
                ...----
   Cost..... -______             .
                                __                       8, 250 ......                           3, 966      12, 134               24, 350



28. FLOOD CONTROL- WORK UNDER SPECIAL AUTHORIZATION
  Snagging and clearing of navigable streams and tributariesin
the interests of flood control. (Section 18 of the 1946 Flood Con-
trol Act.)
  During the fiscal year costs of $13,350 under this authorization
were incurred at Indian Creek and Macoupin Creek, Ill. The total
costs to June 30, 1954, were $167,727.53.
                                             Cost   and     financial         summary



                                                        Fiscal year ending June 30                                      Total to June
                                                                                                                       30, 1954, includ-
                                                                                                                       ing fiscal years
                                      1950           1951                 1952                 1953         1954         prior to 1950

New work:
   Appropriated--...      ...         $30, 000      -$7, 912        ...........                $23, 700     $6, 000              $167, 788
   Cost--------                        72, 599         34, 573         ..........-----------    16, 290     13, 350               167, 728


Other new work data:
    Unobligated balance, fiscal year ending June 30; 1954..__...-...............-............ $60

  Flood Control Emergenices--Repair and Flood Fighting and
Rescue Work. (Section 210 of the 1950 Flood Control Act and
previous authorizations.)
  Pursuant to these authorizations, a total of $13,546,553.92 has
been allotted to the St. Louis district to June 30, 1954, for emer-
gency flood control work, exclusive of $55,415.37 contributed funds.
  Emergency flood control work along the Mississippi and Kas-
kaskia Rivers was completed during the fiscal year 1954 at a cost
of $48,592.74. The total costs and expenditures to June 30, 1954,
were $13,546,553.92.
                                             Cost and      financial          summary


                                                        Fiscal year ending June 30                                      Total to June
                                                                                                                       30, 1954, includ-
                                                                                                                       ing   fiscal   years
                                      1950           1951                 1952                 1953         1954         prior to 1950
Maintenance:
   Appropriated .--------.....       $625, 602      -$5, 560           $1, 020, 000             $395, 800   $2, 390          $13, 546, 554
   Cost_-----------------             783, 468       105, 513           1, 024, 178              377, 406   48, 593           13, 546, 554
732           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                     29. MISCELLANEOUS               INVESTIGATIONS
  During the fiscal year costs incurred for miscellaneous investi-
gations were $10,181.00. The total costs to June 30, 1954, were
$68,704.
                                   Cost and financialsummary

                                          Fiscal year ending June 30                          Total to June
                                                                                             30, 1954, includ-
                                                                                             ing fiscal years
                            1950        1951         1952           1953          1954         prior to 1950
Maintenance:
   Appropriated.....         $7, 890     $6, 973      $5, 414           $3, 000   $10, 181             $68, 704
   Cost-........-....-..      7, 890      6, 973       5, 414            3, 000    10, 181              68, 704



         30. REGULATION,               OTHER REGULATORY FUNCTIONS
   During the fiscal year costs incurred were $6,922 for permits;
$503 for examination and inspection of bridges; $4,362 for inves-
tigations of wrecks; and $913 for pending adjustments. The total
costs for the fiscal year were $12,700.00. The total costs to June
30, 1954, were $1,004,523.45.
                                   Cost and financialsummary

                                         Fiscal year ending June 30                           Total to June
                                                                                             30, 1954, includ-
                                                                                             ing fiscal years
                            1950        1951        1952            1953          1954        priorto 1950

Maintenance:
                  -------
   Appropriated......       $45, 476    $13, 641    $15, 033              -       $12, 700         $1, 004, 523
   Cost__    __-      -      45, 476     13,641      15, 033 _ _.   _              12, 700          1, 004, 523
  MISSISSIPPI RIVER BETWEEN THE MISSOURI RIVER
              AND MINNEAPOLIS, MINN.

   The section of the river covered in this report is divided into
three reaches, under the supervision and direction of district engi-
neers at St. Louis, Mo., Rock Island, Ill., and St. Paul, Minn.
   The section in the St. Louis district extends from the mouth of
the Missouri River to mile 300 above the Ohio River, a distance of
about 105 miles; the Rock Island district extends from mile 300 to
mile 614, a distance of about 314 miles; and the St. Paul district
extends from mile 614 to the Minneapolis, St. Paul & Sault Ste.
Marie Railway bridge, Minneapolis, a distance of about 244 miles.
   Location. The Mississippi River rises in the nothern part of
Minnesota, flows about 2,350 miles in a southerly direction, and
empties into the Gulf of Mexico. The portion included in this re-
port extends from the mouth of the Missouri River to the Minne-
apolis, St. Paul & Sault Ste. Marie Railway bridge, Minneapolis, a
distance of about 663 miles.
   The latest map and profile showing this section of the river is
published in House Document 669, 76th Congress, 3d session. A
map showing Lake Pepin is published in House Document 511, 79th
Congress, 2d session. A map of the section Minneapolis to Du-
buque is published in House Document 515, 79th Congress, 2d ses-
sion. A map showing location of drainage districts (Bellevue,
Iowa, to Missouri River) is published in Rivers and Harbors Com-
mittee Document No. 34, 75th Congress, 1st session.
   Previous projects. Adopted by the River and Harbor Acts of
June 10, 1872; June 18, 1878; August 18, 1894; February 9, 1905;
March 3, 1905; March 2, 1907; June 25, 1910; September 22, 1922;
March 3, 1925; January 21, 1927; and July 3, 1930.
   For further details, see pages 1879, 1880, and 1887 of the Annual
Report for 1915; pages 1106, 1107, and 1108 of the Annual Report
for 1932; and pages 1047 of the Annual Report for 1938.
                                                           733
                                                                                                                                     Depth on
                                           Location                          Lock dimensions                                         miter sill                              Character of foundation
                          -      -                                    I-                                          -I                        ----     ;---       ---------------
                                                                                                                                                                                                               Percent        Estimated
                                                                                                                       upper                                                                                     com-   Year    cost of
                                                                                         Great-                        nor-                                                                                     preted opened each lock
                                                                           Width           est                         mal                                                                                      locks,   to   and dam,
                          Miles                                               of         length                         pool                                                                                    dams, naviga- including
                          above             Distance from                  cham-          avail-        Lift           eleva- Upper Lower                                  Lock                   Dam             and   tion   work in
                           Ohio             nearest town                     ber          able          (feet)         tion 1 (feet) (feet)                                                                     work             pool
                          River                                             (feet)       for full                                                                                                              in pool
                                                                                          width                                                                                                                                                        O
                                                                                          (feet)
                                                                                     I              I             I             t           i               i                     -   -


                                                                                                                                                                                                                                                       O
St. Anthony      Falls,       853.9    In city of Minneapolis,                 56            400         49. 2         799. 2       15. 7          13. 7        Some limestone, Limestone            _--_..      (2)                S$18,353,900
upper lock.                             Minn.                                                                                                                   mainly sand-                                                                          H
                                                                                                                                                                  stone. No piles.
St. Anthony Falls,            853. 3   ....do.- - - -       - -                56            400        526.9          750. 0       13.7        5 10. 3         Sandstone. No         Sandstone.-------                50           4 11, 548, 300
  lower lock and dam.                                                                                                                                             piles.
                                                                               56           400         535.9          725. 1       S13.5          10. 1        Rock and piles in                                                                      ©
Lock and dam 1....___         847. 6   Minneapolis-St. Paul- _                 56           400          35.9                         S12.5         7.6                               Piles in gravel.....        100        1917       62,328,800
                                                                                                                                                                 gravel.
Lock and dam 2______                   S1.3
                                          milesabove Hastings,                110           500           12. 2                      16.0          15. 1        Piles in sand, silt,  Piles in sand, silt,        100        1930                      O
                              815. 2     Minn.                                110          8600           12. 2        687. 2        22.2          13.0           clay.                 and clay.                      99    1948   }    6, 550,400    ©R
Lock and dam 3_______         796. 9   6.1 miles above Red                    110           600            8.0         675. 0        17. 0         14. 0            do .------------- Piles in sand--....
                                                                                                                                                                   -....                                               91    1938        6, 174, 600
                                          Wing, Minn.
Lock and dam 4 _____-         752. 8   Alma, Wis_ ...  _                      110           600           7.0          667. 0       17. O0         13.0   Piles in sand and Piles in sand and                          91    1935        5, 284, 100   z
                                                                                                                                                            gravel.             gravel.                                                                i,,,-
Lock and dam 5_ _____         738. 1   Minneiska, Minn _...                   110           600           9.0          660.0        18. 0          12. 0 .....do ......       Piles in sand-.....                      92
Lock and dam 5A ---           728. 5   3 miles above Winona,                  110           600           5.5          651.0        18. 0          12. 5 Piles in sand ...-. .....do-..........                        78
                                                                                                                                                                                                                             1935
                                                                                                                                                                                                                             1936
                                                                                                                                                                                                                                         5, 560, 400
                                                                                                                                                                                                                                         5, 883, 400
                                                                                                                                                                                                                                                       z
                                         Minn.
Lock and dam 6..____          714. 3   Trempealeau, Wis .-...                 110            600          6. 5         645. 5       17. 0          12. 5        Piles in sand,            Piles in sand and       100        1936        4, 893, 900   ©C
                                                                                                                                                                 gravel, and silt.          clay.
Lock and dam 7_...___         702. 5   Dresbach, Minn .--..                   110            600          8.0          639.0        18. 0          12. 0        Piles in sand and         Piles in sand-_-             92    1937        6, 087, 300
                                                                                                                                                                  gravel.
Lock and dam 8.._____         679. 2   Genoa, Wis _...._._...                 110           600           11.0         631. 0       22.0           14. 0        Piles in      sand,       Piles in sand and            91    1937        6, 649, 100   ACr
                                                                                                                                                                 gravel, and                gravel.                                                    i-,,
                                                                                                                                                                 broken rock.                                                                          CA
Lock and dam 9.._____         647. 9   3.3 miles below Lynx-                  110            600          9.0          620. 0       16. 0          13. 0        Piles in sand---          Piles in sand ..--           91i   1938        7, 212, 000
                                          ville, Wis.
Lock and dam 10 _____         615. 1   Guttenberg, Iowa,                      110           600            8.0         611.0        15. 0          12. 0         ..... do----------        do-........-                89    1936       5, 370,000
Lock and dam 11 .....         583. 0   3.7 miles above Dubuque,               110           600           11. 0        603.0        18. 5          12. 5        Piles in         sand, .....
                                                                                                                                                                                           do-...........              99    1937       7, 387, 200
                                          Iowa.                                                                                                                     gravel, and silt.
Lock and dam 12 -----556. 7            Bellevue, Iowa ..     ......           110            600          9.0          592. 0       17. 0          13. 0        Piles in sand and Piles in sand and                    99    1938        5, 509, 100
                                                                                                                                                                    gravel.              gravel.
Lock and dam 13 .....         522. 5   4.3 miles above Clinton,               110           600           ILO          583.0        19.0           13. 0        Piles in sand, clay, ..... do      -..........         99    1938        7, 889, 700
                                         Iowa.                                                                                                                      and gravel.
Lock and dam 14______         493. 3   3.7milesbelow Le Claire,               110            600          11.0         572. 0       20. 5          13. 5        Rock ......-....        Rock...........                98    1939       5,873, 600
                                          Iowa.
Le Claire Lock (Canal)        493. 1   3.9milesbelowLe Claire,                 80           320           11.0                      17. 6          10.9 -.....        do---------I................                100        1922
                                          Iowa.
Lock and dam 15......         482. 9   Foot of Arsenal Island,                110           600           16. 0        561. 0 1124.0               11.0
                                          Rock Island, Ill.                   110           360           16. 0               11 17. 0             11.0
                                                                                                                                                                }---do----__,---------_ R ock......... ..              95    1934       9, 055, 100
Lock and dam 16....__         457. 2   1.8 miles above Musca-                 110           600            9.0         545.0     17.0              12. 0        Piles in sand and Piles in sand and                    99    1937       6, 779, 300
                                          tine, Iowa.                                                                                                              gravel.                gravel.
     Lock and dam 17-.....                  437. 1        4.2 miles above New                    110         600             8.0         536.0O        16. 0             13.0       do............
                                                                                                                                                                                 .....          Piles in sand......                    95        1939         6, 742, 800
                                                             Boston, Ill.
     Lock and dam 18...                     410. 5        6.5 miles above Burling-               110         600             9.8         528.0         16. 5             13. 7   Piles in sand-...
                                                                                                                                                                                                 Piles in sand and                     90        1937        8, 133,900-
                                                             ton, Iowa.                                                                                                                            gravel.
                                                                                                            358
an   Lock and dam 19_____ 364. 2                          Keokuk, Iowa ..... .                   110
                                                                                                 110      1,200            38.2          518.2         14. 0              9.2 Rock.............. Rock....----------             1100l            1913   12   15, 175, 000
     Lock and dam 20__    343.2                           0.9 mile above Canton,                 110        600            10. 0         480. 0        15.0              12. 0 .....
                                                                                                                                                                         12.0      do.............
                                                                                                                                                                                                 Rock and piles in                     97        1936         6, 391, 500
                                                             Mo.                                                                                                                                   sand and gravel.
     Lock and dam 21.. ..                   324. 9        2.1 miles below Quincy,                110         600           10. 5         470. 0        16. 5                   Piles in sand and Piles in sand and                     96        1938         6, 479, 100
                                                             Ill.                                                                                                                gravel.           gravel.
Wh
to   Lock and dam 22 _...                   301. 2        1.5 miles below Saver-                 110         600           10.2          459. 5         18. 0            13.8 Rock..__-....   .  Rock ......----------.                99        1938         5, 217, 800
                                                             ton, Mo.
     Lock and dam 24-.....                   273. 4       Clarksville, Mo..___....               110          600          15. 0 449. 0                 19.0             12. 0   Rock; piles in sand. Piles in sand......              92        1940         7, 067, 000
     Lock and dam 25-......                  241. 4       Cap Au Gris, Mo_ _....                 110          600          15. 0 434. 0                 19.0             12. 0   Piles in sand and Piles in sand and                   93        1939         9, 069, 200      M
                                                                                                                                                                                   gravel.              gravel.
     Lock and dam 26                                                                             110         600         s 22.0        419.0 1132. 0                   1412. 0
      (Henry T. Rainey                       202.9        Alton, Ill. -                          110         360           22.0      .......   16.0                    1412. 0   Piles in sand   --..   Piles in sand .-...            84        1938        15, 272, 900       -
      Dam).
             Total locks and              J-                                                    -1-1-                                                    -i        1-


                                                                                                                                                                                                                                                          213, 939, 400
              dams.

                                                                  ADDITIONAL FEATURES ENTERING INTO COST OF PROJECT
     Facilities for public use, convenience, and safety-----    ........... ......................................................                                              .............................                                                      400
                                                                                                                                                                                                                                                            $980, 400----------------------------
     Miscellaneous harbor improvements..........................................................................................................--------------------------------------------------------------------------------------------------5                         00
                                                                                                                                                                                                                                                           1, 892,300.....................................
     Rectification of damages caused by seepage and backwater--------------....----------------------------------------------------------------------------------- . 5, 356, 600
                                                                                                                                                                                                                                                                            l
                                                                                                                                                                                                                                                                            0
     Regulating work between lock and dam 26 (Henry T. Rainey Dam) and the Missouri River (actual cost) ..............                                                                            ..... ................          ...                         545, 000
                                                                                                                                                                                                                                              .....------------------------------------------------
                                                                                                                                                                                                                                                                            0
     Miscellaneous................----------...........                                                                                                 ..
                                                                                                                     ..............................................-----------------------------------------------------------------------------                488  300................
                                                                                                                                                                                                                                                                488, 300
                                     -----------
              Total additional features.......                              - -.----                ----------- ------------------------------------------------------------ -----------------------------                                                     9,, 262, 600
              Total existing project-               -           .                                             -      ---.......
                                                                                                           ..---------             ...            _-.............---      -      ----..                                            _    ....--          16 223, 202, 000        r
        1 Elevations of pools 1 to 22 and at St. Anthony Falls are mean sea level 1912 adjust-                                                     1 Depth over upper poiree sill. Depth over upper miter sills is 27 feet at locks 15; and
     ment; pools 24, 25, 26 are mean sea level 1929 adjustment.                                                                                  34 feet at main lock 26.
        2 Existing dam, owned by Northern States Power Co., is complete. Construction of                                                           12 In addition, cost of $640,868 for first lock, was reported by the Mississippi River
     lock has not been started.                                                                                                                  Power Co., transferred to Government free in lieu of improvements destroyed. (Annual
        3 Includes dredging above upper lock. (Federal cost only.)                                                                               Report, 1928, pp. 1118-1119.) Present estimate includes $13,900,000 for main lock and
          Includes lower approach dredging and dredging between upper and lower locks.                                                           appurtenant work.
     (Federal cost only.) Excludes $1,100,000 contributed funds.                                                                                    Is Lift above possible future pool. Lift at extreme low water about 28.2 feet.
        5 Based on pool elevation of 723.1 in pool 1 which is crest of dam. Pool is normally                                                        14 Based on possible future pool.
     maintained at elevation 725.1 by flashboards.                                                                                                  i5Excludes $81,200 contributed funds.
        6 Includes $1,325,700 for bluff protection completed. In addition, $1,948,800 was ex-
     pended from previous projects and $1,349,600 from O&C appropriation for first of twin
                                                                                                                                                    16In addition, $620,000 was expended from the allotment for examinations, surveys,
                                                                                                                                                 and contingencies, covering the original 9-foot survey, and a total of $613,600 was expended                                   z
     locks. Does not include lock and dam replacement program.                                                                                   by the Works Progress Administration for miscellaneous clearing and esplanade work in
        7Old upper guard sill.                                                                                                                   the Rock Island district.
        s Landward lock.
        ' In addition, $1,965,300 was expended from previous projects.
       10Existing Le Claire Canal lock is used as auxilliary to lock 14; previous project costs,
     $540,000.
736            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Existing project. This project provides for a channel of 9-foot
depth and of adequate width between the mouth of the Missouri
River (1,179 miles from the Gulf) and the Minneapolis, St. Paul &
Sault Ste. Marie Railway bridge at Minneapolis, by the construc-
tion of a system of locks and dams, supplemented by dredging. The
project also provides for further improvement at St. Paul to pro-
vide a basin 9 feet deep, varying in width from 400 to 1,100 feet and
extending downstream from the Robert Street Bridge for a dis-
tance of 2.7 miles, and at Minneapolis to provide adequate terminal
facilities, and for miscellaneous and other harbor improvements.
   Pertinent data for existing and proposed locks and dams, etc.,
are given in table above. All dams are concrete. Three dams (St.
Anthony Falls, 1, and 19) are fixed, the remainder are movable.
   The estimate of cost for new work, revised in 1954, is':$223,-
202,000, which includes $29,902,200 for work upstream from the
lower Northern Pacific Railway bridge at Minneapolis (St. Anthony
Falls), but is exclusive of amounts expended on previous projects.
The latest approved estimate for maintenance is $4,060,000 an-
nually.
   The existing project was authorized by the following acts and
related documents:

             Acts                              Works authorized                               Documents

River and Harbor Act of           Dredging channels to landing places- ......       None.
Sept. 22, 1922.
River and Harbor Act of           Project adopted from Illinois River to            H. Doc. 290, 71st Cong., 2d
July 3, 1930, as amended by        Minneapolis; Chief of Engineers granted          sess.
P. R. No. 10, Feb. 24, 1932.       discretionary authority to make such
                                    modification in plan as may be deemed
                                    advisable.
Permanent     Appropriation       Operation of snag boats and operation and         None.
  Repeal Act, June 26, 1934.        care of locks and dams to be provided for
                                    with funds from Department of the Army
                                    appropriations for rivers and harbors.
River and Harbor Act of           Missouri River established as lower limit         H. Doc. 137, 72d Congi
  Aug. 30, 1935.                    of the project.                                  1st sess.
River and Harbor Act,. of         Extension of 9-foot channel above St. An-                    Do.
  Aug. 26, 1937.                    thony Falls, Minn., including adequate
                                    terminal facilities for Minneapolis, Minn.
River and Harbor       Act   of   St. Paul Harbor-......-...-. ......      --       Rivers and Harbors Com-
Aug. 30, 1935.                                                                       mittee Dooe. 44, 74th Cong.,
                                                                                      1stsess.
River and Harbor Act of Determine damages to drainage and levee                     Rivers and Harbors Com-
  Aug. 26, 1937.                      districts caused by seepage and back-           mittee Doec. 34, 75th Cong.,
                                      water, and cost of making rectification         1st sess.
                                      thereof.
Flood Control Act of Dec. 22, Public park and recreational facilities .-            None.
  1944.
River and Harbor Act of Red Wing, Minn., harbor .........          _....    __      H. Doe. 103, 76th Cong.,
  Mar. 2, 1945.                                                                      1st sess.
     Do___                          Remedial works to correct damages caused        H. Doe. 137, 76th Cong., 1st
                                      by seepage and backwater at Cochrane,           sess.
                                      Wis.
     Do-------         --
                  -------        -. Such changes or additions to the payments,
                                      remedial works, or land acquisitions au-
                                                                                    None.
                                      thorized by the River and Harbor Act of
                                      Aug. 26, 1937 (River and Harbor Com-
                                      mittee Doec. 34, 75th Cong., 1st sess.), as
                                      the Chief of Engineers deems advisable.
     Do      ..-------------        St. Paul, Minn., Channel enlargement,           H. Doec. 547, 76th Cong.,
                                      small-boat harbor, and roadway.                 3d sess.
None-- ..       .     ----------
                       ..-------    Vertical bridge clearance at Minneapolis to     S. Doc. 54, 77th Cong., 1st
                                      be 26 feet above the estimated stage for.       sess.
                                      discharge of 40,000 c. f. s.
River and Harbor Act of Winona, Minn., basin-...__ ..                    _.......   H. Doe. 263, 77th Cong.,
  Mar. 2, 1945.                                                                      1st sess.
     Do._                    ___ - Future modification of lock and dam No. 2        H. Doec. 432, 77th Conga,
                                      for power development.                         1st sess.
                      MISSISSIPPI RIVER-MISSOURI RIVER AND MINN.                                                               787
                   Acts                                   Works authorized                                         Documents


River and Harbor Act of                    Lake City, Minn., harbor_-                                 H. Doc. 511, 79th Cong., 2d
  July 24, 1946.                                                                                        sess.
      Do__-..---______                     Wabasha, Minn., harbor. _--------                          H. Doc. 514, 79th Cong., 2d
                                                                                                           sess.
        Do-----------------                Payment of damages caused by backwater                     H. Doe. 515, 79th Cong., 2d
                                            and seepage, pools 3 to 11.                                 sess.
        Do....-----------------            Hastings, Minn., harbor .-                                 H. Doc. 599, 79th Cong., 2d
                                                                                                           sess.
        Do _            _      _        Lansing, Iow a, harbor ....
                        .-----------------                                  ...........-....          S. Doc. 192, 79th C ong., 2d
                                                                                                        sess.                    d
River     and Harbor Act of                Fort Madison, Iowa, harbors .-..........                   H. Doc. 661, 80th Cong., 2
June 30, 1948.                                                                                            sess.
River and Harbor Act of Payment of damages caused by pool No. 14                                      S. Doc. 197, 80th Cong., 2d
  May 17, 1950.                at Clinton, Iowa.                                                        sess.
     Do......---------------- Davenport, Iowa, harbor _      --_                                      H. Doc. 642, 80th Cong., 2d
                                                                                                           sess.
        Do _______                 _       Muscatine, Iowa, harbors ................                  H. Doc. 733, 80th Cong., 2d
                                                                                                           sess.
        Do --                              Alma, Wis., harbor___-                                     H.     Doc. 66, 81st Cong., 1st
                                                                                                           sess.
        Do-        -------------           Hannibal, Mo., harbor__-                                   H. Doc. 67, 81st Cong., 1st
                                                                                                           sess.
        Do ..                              Prairie du Chien, Wis., harbors...                    ..   H. Doc. 71, 81st Cong., 1st
                                                                                                           sess.
        Do----------------                 Opposite Hamburg, Ill., harbor .....                 ___   H. Doc. 254, 81st Cong., 1st
                                                                                                           sess.
        Do--------       _______       i   Rock Island, Ill., harbor                                  H. Doc. 257, 81st Cong., 1st
                                                                                               .---------------
                                                                                                           sess.
        Do. .................-             P--ermits such change in location of the Wi-               None.
                                              nona, Minn., boat basin authorized by
                                              River and Harbor Act of Mar. 2, 1945 (H.
                                              Doc. 263, 77th Cong., 1st sess.), as the
                                              Chief of Engineers deems advisable.



   See House Document 669 (76th Cong., 3d sess.), for a report of
Chief of Engineers dated February 27, 1940, containing a general
plan for improvement of the Mississippi River between Coon Rap-
ids Dam and the mouth of the Ohio River for purposes of naviga-
tion, power development, the control of floods, and the needs of
irrigation.
   Local cooperation. a. Extension of the 9-foot channel above St.
Anthony Falls is authorized subject to the conditions that local
interests contribute $1,100,000 to the first cost of the improvement
as a whole and provided that responsible local agencies furnish
assurances satisfactory to the Secretary of War that they will:
 (1) Make the necessary alterations to highway bridges and pub-
licly owned utilities, (2) furnish free of cost to the United States
all lands, easements, and rights-of-way necessary for the channel
and lock and dam construction, and (3) furnish at their own ex-
pense suitable spoil disposal areas for the new work and for sub-
sequent maintenance when and as required. Assurances of local
cooperation were approved by the Secretary of War on October 2,
1945. The city of Minneapolis has made payment of the $1,100,000
cash contribution and has furnished land as required for work
underway. Possession of lands on the right bank in the vicinity of
the lower dock has been obtained by the Government in condemna-
tion proceedings instituted for the city of Minneapolis at the ex-
pense of the city. Consummation of this matter is expected in the
fall term of court.
   b. The provision of a basin at Winona, Minn., is subject to the
conditions that local interests revet the river face of the terminal
property; furnish assurances satisfactory to the Secretary of War
that they will construct adequate terminal facilities at the basin
738'     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

and provide necessary floating booms, wharves, and servicing facili-
ties at the small boat harbor open to the public on equal terms;
furnish free of cost to the United States, all necessary rights-of-
way and spoil disposal areas for new work and subsequent main-
tenance when and as required; and hold and save the United States
free from claims for damages resulting from the improvement.
Assurances covering the commercial harbor, requested on August
8, 1947, have not been received. Change in location of the small-
boat harbor was authorized by the Rivers and Harbors Act ap-
proved May 17, 1950. Assurances for this harbor have not been
requested.
   c. The provision of a small boat harbor at Hastings, Minn., is
subject to the condition that responsible local agencies furnish
assurances satisfactory to the Secretary of War that they will pro-
vide free of cost to the United States all necessary lands, ease-
ments, and rights-of-way; provide spoil disposal areas for new
work and subsequent maintenance when and as required; and pro-
vide the necessary floating booms, slips, and service facilities open
to all on equal terms. Local interests were formally requested to
furnish assurances on March 17, 1950. Assurances were approved
by the Secretary of the Army on July 7, 1950. Local interests who
were proceeding with acquisition of lands have suspended opera-
tions until availability of construction funds is known.
   d. The provision of a small boat harbor at Lansing, Iowa, is
subject to the condition that local interests furnish assurances
satisfactory to the Secretary of War that they will provide without
cost to the United States all necessary lands, easements, rights-of-
way, and disposal areas for new work and subsequent maintenance
when and as required; and provide the necessary floating booms,
slips, and servicing facilities open to all on equal terms. The condi-
tions of local cooperation have not been met in whole or in part.
Local interests have not been formally notified of the required con-
ditions or requested to furnish assurances.
   e. The provision of a small boat harbor at Alma, Wis., is subject
to the condition that local interests agree to provide all lands, ease-
ments, and rights-of-way, not now owned by the United States, for
the construction and maintenance of the project; construct and
maintain an adjacent parking area and an access road to the harbor
site; and provide necessary mooring facilities and utilities, includ-
ing a public landing with suitable supply facilities, open to all on
equal terms. The conditions of local cooperation have not been
met in whole or in part. Local interests have not been formally
notified of the required conditions or requested to furnish assur-
ances.
   f. The provision of the harbors at Prairie du Chien, Wis., is
subject to the condition that local interests agree to furnish with-
out cost to the United States all lands, easements, and rights-of-
way necessary for construction and maintenance of each of the
harbor improvements, when and as required; protect the upstream
corner of the fill at the freight harbor with revetment, or furnish
funds for this work if accomplished by the United States, and
maintain the fills at both harbors without cost to the United States;
provide and maintain at local expense adequate public terminal and
          MISSISSIPPI RIVER-MISSOURI RIVER AND MINN.                739
transfer facilities in connection with the commercial freight har-
bor, open to all on equal terms; and provide and maintain at the
small boat harbor, without cost to the United States, adequate
mooring facilities and utilities, including a public landing with
suitable supply facilities, open to all on equal terms. Assurances
of local cooperation were received on December 28, 1953, and ap-
proved by the Secretary of the Army on May 11, 1954.
   g. The provision of a small-boat harbor and freight terminal ap-
proach channel at Fort Madison, Iowa, is subject to the conditions
that for each improvement local interests agree to furnish free of
cost to the United States all lands, easements, rights-of-way and
spoil disposal areas necessary for the new work and for subsequent
maintenance, when and as required, and hold and save the United
States free from damages due to construction and maintenance of
the improvements; that for the small boat harbor, local interests
agree to provide necessary mooring facilities and utilities, includ-
ing a public landing with suitable supply facilities and access road,
these harbor facilities to be open to all on equal terms; and that in
connection with the approach channel, local interests agree to pro-
vide adequate public terminal and transfer facilities, mooring fa-
cilities, access roads, storm drains, retaining walls, and police and
fire protection, these facilities and services to be available to all on
equal terms. These requirements have not been met. However,
local interests have furnished assurances of their willingness and
ability to comply.
   h. The provision of a small boat harbor at Davenport, Iowa, is
subject to the conditions that local interests furnish, without cost
to the United States, all necessary lands, easements, and rights-of-
way for construction and maintenance of the improvements; hold
and save the United States free from damage due to the construc-
tion and maintenance of the works; and provide and maintain an
access road, a parking area, and necessary mooring facilities and
utilities, including a public landing with suitable servicing and
supply facilities, and police and fire protection, open to all on equal
terms. The conditions of local cooperation have not been met in
whole or in part. Local interests have not been formally notified
of the required conditions or requested to furnish assurances.
   i. The provision of a small boat harbor at Rock Island, Ill., is
subject to the conditions that local interests furnish, without cost
to the United States, all necessary lands, easements, and rights-of-
way for construction and maintenance of the improvement when
and as required; hold and save the United States free from dam-
ages due to the construction and subsequent maintenance of the
project; provide and maintain without cost to the United States
an access road, a parking area, a boathouse, and the necessary
mooring facilities and utilities, including a public landing with
suitable servicing and supply facilities open to all on equal terms;
maintain the levee around the major portion of the harbor area
constructed from the materials dredged from the entrance chan-
nel; and establish a competent and properly constituted public body
empowered to regulate the use, growth, and free development of
the harbor facilities. The conditions of local cooperation have not
been met in whole or in part. Local interests have not been for-
740      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

mally notified of the required conditions or requested to furnish
assurances.
   j. The provision of a small boat harbor at Hannibal, Mo., is
subject to the conditions that local interests furnish, without cost
to the United States, all necessary lands, easements, and rights-of-
way for construction and maintenance of the improvement, when
and as required; and provide and maintain, without cost to the
United States, necessary mooring facilities and utilities, including
a public landing with suitable supply facilities, open to all on equal
terms. The conditions of local cooperation have not been met in
whole or in part. Local interests have not been formally notified of
the required conditions or requested to furnish assurances.
   k. The provision of a small boat harbor and freight terminal ap-
proach channel at Muscatine, Iowa, is subject to the conditions that
for each improvement local interests agree to furnish free of cost to
the United States all lands, easements, rights-of-way, and spoil dis-
posal areas necessary for the new work and for subsequent main-
tenance when and as required, accomplish without cost to the
United States all necessary alterations of sewers and other utilities,
maintain the ultilities, protect the fill at the harbor improvements
with revetment or furnish funds for this work if accomplished by
the United States, maintain the fill without cost to the United
States, and hold and save the United States free from all damages
resulting from construction and maintenance of the improvements;
that for the small boat harbor local interests agree to provide nec-
essary mooring facilities and utilities, including a public landing
with suitable supply facilities, boathouse, access road, and parking
area, open to all on equal terms; and that in connection with the
improvement to accommodate freight commerce, local interests
furnish assurances satisfactory to the Secretary of the Army that
immediately after the filling of the industrial site has been accom-
plished, they will provide adequate public terminal and transfer
facilities, including material-handling facilities, mooring facilities,
access roads, and police and fire protection, these facilities and
services to be available to all on equal terms; that they will see to
it that immediately upon completion of the fill a grain elevator of
approximately 250,000 bushel capacity designed to make shipments
by river is provided at the site and that they will foster develop-
ment of the site in other respects to assure full realization of the
waterborne freight potentialities of this portion of the improve-
ments. The conditions of local cooperation have not been met in
whole or in part. Local interests have not been formally notified
of the required conditions or requested to furnish assurances.
   1. The provision of a small boat harbor on the Missouri side of
the river opposite Hamburg, Ill., is subject to the conditions that
local interests agree to furnish, without cost to the United States,
all lands, easements, rights-of-way, and spoil disposal areas neces-
sary for the new work and for subsequent maintenance, when and
as required; hold and save the United States free from any dam-
ages resulting from construction and maintenance of the improve-
ment; provide and maintain an adequate ferry service, necessary
mooring facilities, and utilities, including a public landing with
suitable supply facilities, a suitable access road between Elsberry
          MISSISSIPPI RIVER-MISSOURI RIVER AND MINN.              741
levee and the ferry landing, and a suitable parking area, the ferry
service and these facilities to be available to all on equal terms;
maintain, without cost to the United States, all the improvements
added to the existing river project by the proposed modification
except for maintenance of project depths in the harbor basin and
its entrance; and establish a public body having authority to co-
operate financially and to operate the essential facilities. The con-
ditions of local cooperation have not been met in whole or in part.
Local interests have not been formally notified of the required con-
ditions or requested to furnish assurances.
    m. The provisions of local cooperation for the remedial works at
Cochrane, Wis., for the improvement of the commercial harbor and
enlargement of the existing small boat basin at Lake City, Minn.,
for the improvement of the channel at St. Paul and dredging of
small boat harbor at the lower end of Harriet Island, and for the
harbors at, Red Wing, Minn., and Wabasha, Minn., have been fully
complied with. 1.:
    Terminal facilities. A complete list of terminals is contained in
the book titled "The Middle and Upper Mississippi River," revised
to Decemnber 31, 1946. This book may be obtained from the Dis-
trict Engineer, Corps of Engineers, United States Army, St. Louis,
Mo.
    Operations and results during fiscal year, Regular funds.
    St. Paul District: New work. Extension of channel above St:
Anthony Falls: Construction of the lower lock and dam by con-
tinuing contract was increased from 41.3 to 65.7 percent complete.
    Construction during the year was entirely in the lock area.
Fabrication of gates and machinery was carried on and completed
units were shipped and stored.
    Locks and dam 1: The contract for construction of a protective
cribbing type retaining wall and. other work for the protection of
the bluff adjacent to and downstream from the land wall of the
locks was completed.
    Lock and dam 2: A contract has been awarded for surfacing the
access road and esplanade and other work in the vicinity of the
damsite. No work has been initiated.
    Seepage damages, pools 3-11: Claims were processed by hired
labor as evidence of title was received, and four claims totaling
$2,100.00 were processed for payment.
    Miscellaneous: Designs in connection with extension of channel
above St. Anthony Falls and for work on bluff protection at locks
and dam 1 were carried on by hired labor.
    Land and flowage acquisition: Office work in connection" with
acquisition of land at St. Anthony Falls was carried on by hired
labor.. Condemnation action by the United States is being done at
the request of local interests with reimbursement by them.
    Cost of work by classes: Design, engineering, etc., for St. An-
thony Falls, $48,532; design, engineering, etc., general, $12,182;
lock and dam construction, $2,122,562; protection of bluff, $214,-
951; administration and payment of seepage damages and land
acquisition, $3,746. Cost by hired labor, $65,541; by contract,
$2,340,432. Total cost of new work was $2,458,656 Federal funds
and -- $56,683 contributed funds.
742      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Maintenance: Channel dredging was performed at 62 localities
by Government plant and hired labor. A total of 2,324,934 cubic
yards of material and 24 snags were removed at a cost of $553,335.
Miscellaneous surveys and shore protection work were carried on
at a cost of $48,625. The total cost of maintenance was $601,960.
   Operating and care: The locks and dams were operated as re-
quired and necessary repairs were made thereto and to appurtenant
structures, including the final stage of remedial work on the ogee
section of dam 1, construction of a remedial dike at lock and dam
3, and repair and repainting of miter gates at lock 4. Cost of opera-
tion including repairs was $1,068,927 for the year.
   The cost of work (St. Paul District) for the year was $4,072,860,
of which $2,401,973 was for new work, $601,960 was for mainte-
nance, and $1,068,927 for operating and care.
   Rock Island district: New work. Construction of new main lock
No. 19 and appurtenances at Keokuk, Iowa, by contract, was coy-
tinued. Construction of stage I of the lock, consisting of the loweri
river wall, the lower land wall, and rock excavation at the lower
lock approach, was completed in April 1954; construction of stage
II, consisting of the new lock proper including esplanade, lock
gates, Tainter valves, operating machinery and accessories and
appurtenances was initiated in May 1954. Studies relative to rec-
tification of damages to drainage and levee districts were carried
on by hired labor.
   Cost of work by classes: New main Lock No. 19, $1,901,674;
and rectification of damages to drainage and levee districts, $71,-
016. Total cost by hired labor, $333,284; by contract, $1,639,406.
   Maintenance: Operating and care. The locks and dams were
operated as required and necessary repairs made thereto and to
appurtenant structures at a cost of $1,689,937.
   The cost of the work (Rock Island District) during the fiscal
year, all from regular funds, was $3,662,627, of which $1,972,690
was for new work, and $1,689,937 was for operating and care.
   St. Louis district: New work. Partial rectification of damages
in pool No. 25 cost $7,004.89.
   Maintenance. Work on rehabilitation of gates, lock and dam 26
was performed by contract at a cost of $223,499.16. Channel
dredging was performed at 6 localities with, Government plant and
hired labor. A total of 262,940 cubic yards of material was re-
moved from the main channel at a cost of $59,597.34. Other costs
by hired labor were: Repairs to lock No. 26, $152,453.14; surveys,
$5,056.83; gages, $10,499.34; aids to navigation, $13,034.36; con-
struction of emergency bulkhead recesses and dummy sill trusses,
 $68,022.05; and miscellaneous work, $27,446.97; and pending ad-
justment, $-6,535.51. The total cost of maintenance was $553,-
073.66.
    Operating and care. The locks and dam were operated as re-
quired and necessary repairs were made thereto and to appurtenant
structures at a cost of $248,589.94.
                    MISSISSIPPI RIVER-MISSOURI RIVER AND MINN.                          743
   The costs during the fiscal year for the three districts were as
follows:

                                      St. Paul       Rock Island     St. Louis      Total

Costs:
    New work ______________________    $2,401,973      $1,972,690     $     7,005   $4, 381,668
    Maintenance..________________       1, 670,887      1,689,937         801,663    4,162,487

                      -4,
         Total costs_-.....               072, 860      3,662, 627        808,668    8,544,155



   Condition at end of fiscal year. The 9-foot channel as a whole
was about 75 percent complete.
   St. Paul district: Work completed. Locks and dams 1 to 10, in-
clusive (except for relatively minor appurtenant work) ; major
improvements of harbors at St. Paul and Minneapolis; boat harbors
at St. Paul, Red Wing, Wabasha, and Lake City, Minn.; remedial
drainage ditch at Cochrane, Wis.; miscellaneous channel dredging
and realignment; channel markers; pool clearing; and studies rela-
tive to public-use planning have been completed. A total of 207
claims for seepage damages, totaling $88,591.75, have been proc-
essed for payment. For information pertaining to locks and dams,
see table under paragraph "existing project."
   Status of land and flowage acquisition. Approximately 50,630
acres of land in fee including 45,158 acres wherein use of land by
the Department of the Interior is provided for in accordance with
a cooperative agreement and general plans, and easements on
15,244 acres of land including easements retained on 51 acres of
land originally acquired and subsequently sold were owned or con-
trolled in pools 1-10, inclusive, at the close of the fiscal year. In
addition, easements over approximately 156 acres of land for har-
bors and St. Anthony Falls have been obtained and the Department
of the Army holds special rights over 62,874 acres of land owned
by the Department of the Interior in pools 3-10, inclusive. Acqui-
sition of 4.6 acres of land at St. Anthony Falls is pending. Com-
pletion of land and flowage acquisition for portions of the project
completed or presently under construction is expected in fiscal year
1955.
   Work remaining to complete the portion of the project in the St.
Paul District consists of the following: completion of extension of
the channel above St. Anthony Falls, initiated in October 1948 and
about 23 percent complete; esplanade at 2 for which contract has
been awarded; guide wall extensions at 3 to 10, inclusive, except at
6; construction of stage-recorder houses at various sites, realign-
ment of channel at Wilds Bend; harbor improvements at Hastings
and Winona, Minn., Alma and Prairie du Chien, Wis., and Lansing,
Iowa; construction of public-use facilities; remainder of payment
for seepage damages, pools 3 to 11, inclusive; and completion of
land acquisition at St. Anthony Falls.
   The condition of the channel on June 30, 1954, was such that con-
trolling depths of 9 feet at low water and minimum widths for
long-haul common carrier service were being maintained in all
pools, except St. Anthony Falls.
744           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  The total costs under the existing project (St. Paul District) to
June 30, 1954, including $277,152 contributed funds expended for
new work, were as follows:

                                          Regular        Public works     Emergency        Total
                                           funds            funds         relief funds


Costs:
    New work_..______________________     $31,823, 153     $24, 210,071     $9,071, 214    $65, 104, 438
    Maintenance                          123, 184, 891 ....                                   184,891
                                                                                            23,
      Total costs_    -   -                55,008,044,      24,210,071       9,071,214      88, 289,329


I Includes $762,196 expended between 1930 and 1936 on the operating and care of the works of improve-
ment under the provisions of the permanent indefinite appropriation for such purposes.

   The above costs and expenditures for new work, regular funds,
include $159,359 transferred from Rock Island District covering
pro rata share of cost of Derrickboat Hercules.
    Rock Island district: Work completed. Locks and dams 11 to
22, inclusive (except proposed main lock and appurtenances at 19,
and appurtenant works at various localitieS); alterations to Eagle
Point Bridge; rock excavation in pool 20; diversion of Henderson
River; partial conglomerate dredging in pool 19; partial clearing in
'pools; partial removal of old lateral dam along" LaClaire Canal;
channel alignment in pools 14, 16, 18, and 21; addition to pump
house and installation of machinery in Union Township drainage
:district, Mo.; seepage ditch and remedial works in Des Moines
County drainage district No. 7, Iowa; remedial works in the Sny
Island levee drainage district, Ill.; extensions to upper river walls
at locks 11, 16, 18, 20, and 21; guide wall extension at lock 11;
mooring levee at lock 20; upper approach dikes at locks 13, 17, and
22; and compensation to the city of Clinton, Iowa, for damages
caused by pool 14 have been completed. For information pertain-
ing to locks and dams, see tabulation under paragraph "Existing
project."
   Status of land and flowage acquisition:' Acquisition of land in
pools 11 to 22, inclusive, consisting of 94,003 acres in fee and 10,304
acres in flowage easement, has been completed.
   Work remaining to complete the portion of the project in the
Rock Island district consists of the following: Main lock and appur-
tenant works at 19; guide wall extensions at 16, 18, 20, and 21;
mooring facilities at 11, 12, 14, 15, 16, 17, 18, and 22; removal of
remainder of lateral dam in pool 14; clearing in pools 12, 13, 14, 17,
18, 19, 21, and 22; rock and conglomerate excavation in pools 14,
15, 16, 17, 18, 19, and 21; harbor improvements at Fort Madison,
Iowa; Hannibal, Mo.; Davenport, Iowa; Rock Island, Ill.; and Mus-
catine, Iowa; rectification of damages to drainage and levee dis-
tricts; construction of public use facilities, and miscellaneous mi-
nor items.
                MISSISSIPPI RIVER--MISSOURI                            RIVER AND MINN.                         745
   The totalkcosts under the existing project (Rock Island District)
to June 30, 1954, were as follows:

                                               Regular            Public works         Emergency          Total
                                                funds                 funds            relief funds


Costs:
    New work...                                $45, 062535          $17,403,322          $11,338,865     $73, 804, 722
    Maintenance                                1 23, 781, 207 -                                           23, 781, 207
         Total costs........       ....         68, 843, 742         17, 403, 322         11, 338, 865    97,585,
                                                                                                                929

  I Includes the sum of $395,442, expended between 1930 and 1936 on the operating and care of the works of
improvement, under the provisions of the permanent indefinite appropriation for such purposes.

   The above costs for new work, regular funds, exclude $207,167
transferred to the St. Paul and St. Louis districts covering their
pro rata shares of cost of derrickboat Hercules.
   St. Louis district: Work completed. Locks and dams at Nos. 24,
25, and 26 (Henry T. Rainey Dam) (except appurtenant works)
and dikes and revetments have been completed. For information
pertaining to locks and dams, see table under paragraph "Existing
project."
   Status of land and flowage acquisition: Acquisition of land in
pools 24, 25, and 26, involving 41,213 acres of land in fee and
flowage easements over 6,549 acres, has been completed.
   Work remaining to complete: The portion of the project in the
St. Louis District consists of the following: guide wall extensions
at locks 24, 25, and 26; purchase and installation of emergency
bulkheads and construction of derrick and storage yard at lock
and dam 26; clearing in pool 26; rectification of damages to drain-
age and levee districts in pools 25 and 26; construction of facilities
for public use; and construction of small-boat harbor facilities on
the Missouri side of the river opposite Hamburg, Ill.
   The condition of the channel on June 30, 1954, was such that
controlling depths of 9 feet at low water and generally suitable
widths for long haul common carrier service were maintained in all
pools and between lock and dam 26 and the Missouri River.
   The total costs under the existing project (St. Louis District) to
June 30, 1954, were as follows:

                                               Regular            Public works         Emergency         Total
                                                funds                funds             relief funds


Costs:
   New work -. ..         .   . . . .          $14,775,013          $10, 282, 566              266
                                                                                         $2,440,         $27, 497,845
   Maintenance ...........                     10,094,571 ----              --------                     -10, 094 571
     Total costs-------         --------   -   24,869, 584           10, 282, 566         2, 440, 266     37, 592, 416



   The above costs for new work, regular funds, include $47,808
transferred from the Rock Island District covering pro rata cost
746                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

of derrick boat Hercules; but do not include $687,709 expended
by Rock Island District in pool No. 24.
       The total costs to June 30, 1954, for the three districts in the
project, including contributed funds expended for new work, were
as follows:

                                                          Regular            Public works             Emergency
                                                           funds                funds                                         Total
                                                                                                      relief funds


Costs:
   New work. ----------------------                       $91, 660,701            $51, 895, 959         $22, 850, 345       $166, 407, 005
   Maintenance--------------------                         57, 060,669     ----------------                                   57, 060, 669
        Total costs--------                     -     -148,      721,370           51,895, 959           22,850,345           223, 467,674

  1 Includes $1,157,638 expended between 1930 and 1936 on operating and care of the works of improvement,
under provisions of the permanent indefinite appropriation for such purposes.


                                               Cost and financial summary
                                                 UNITED STATES FUNDS

                                                           Fiscal year ending June 30                                    Total to June
                                                                                                                        30, 1954, includ-
                                                                                                                        ing fiscal years
                                        1950             1951              1952            1953              1954       prior to 1950 1    2
New work:
   Appropriated-               -_
                         $2, 467, 000
   Cost..--------------- 1, 432,007
                                                     $1, 671, 600
                                                      1, 268, 738
                                                                      $1, 957, 770
                                                                       2, 190, 543
                                                                                       $2, 567, 730
                                                                                        3, 287, 900
                                                                                                         $5, 468, 400
                                                                                                          4, 438, 351
                                                                                                                            $217, 582, 275
                                                                                                                             215, 142, 498
Maintenance:
   Appropriated....... ,  4,021, 000                  3,679,469        3,300,800        4, 329,867        4, 173, 930          65,    930
   Cost------ ---------   3, 993, 672                 3, 686, 970      3, 381, 475      4, 356, 058       4, 162, 488          65,33, 266

   1 Includes $49,012,646 for new work and $8,472,597 for maintenance for previous projects.
   2 In addition $277,152 for new work was expended from contributed funds.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954---------..                                          ............-----.     $46, 588
    Appropriated for succeeding fiscal year ending June 30, 1955------............                                                4,670,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955           -------.........
                                       --....                .....
                                                           -------.                  -- --..-------       .....              --...4, 716, 588
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project..............--..........---.....................................-------------...              49, 962, 371

                                                Cost and financial summary
                                                    CONTRIBUTED FUNDS

                                                              Fiscal year ending June 30                                 Total to June
                                                                                                                        30, 1954, includ-
                                                                                                                        ing fiscal years
                                        1950              1951             1952             1953             1954         prior to 1950

New work:
   Appropriated--------------------........... ....---------.------------------.                                               $1, 181, 200
   Cost          .          ... $295, 716             $256,919              ....       -$300      000         56, 683              277, 152


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-..--....                                    $653, 701
                                                                                           .---------..
    Unobligated balances available for succeeding fiscal year ending
                                                                ......          --....
      June 30, 1955..............................----------------------------..... ...---.  .......... 653, 701
                                                                                           ----..
IMPROVEMENT OF RIVERS AND HARBORS IN THE ROCK
            ISLAND, ILL., DISTRICT

    This district comprises portions of western Illinois, southwestern
Wisconsin, southern and southwestern Minnesota, eastern and cen-
tral Iowa, and northeastern Missouri, embraced in the drainage
basin of the Mississippi River and its eastern and western tribu-
taries between mile 300 (above the mouth of the Ohio River) and
mile 614, and of its eastern tributaries only, between Hamburg
Bay, at mile 261, and mile 300. This district also includes the Illi-
nois and Mississippi Canal and the drainage basin of Bureau Creek,
Ill.
   That section of the Mississippi River between mile 300 and mile
614 is included in the report on Mississippi River between Missouri
River and Minneapolis, Minn.
                                                IMPROVEMENTS

                      Navigation                                               Flood control
                                                     Page                                                    Page
1. Mississippi River between the                             5. The Sny Basin, Ill.......................    753
       Missouri River and Minne-                             6. Coralville Reservoir, Upper
       apolis, Minn. (Rock Island                                 Mississippi River Basin, Iowa              754
       District)---..-.-.--.----........... ......   747     7. Upper Mississippi River Basin,
2. Illinois and Mississippi Canal,                                Rock Island District..... ........         755
      Ill ----......-..............                  747     8. Inactive flood control projects..            756
3. Mill Creek and South Slough                               9. General investigations................       757
      at Milan, Ill ....-........ ........... ...    751    10. Inspection of completed flood
4. Inactive navigation projects ....                 752          control works .....................        757
                                                            11. Flood control work under
                                                                  special authorization........__     ....   757


1. MISSISSIPPI RIVER BETWEEN THE MISSOURI RIVER AND
       MINNEAPOLIS, MINN. (ROCK ISLAND DISTRICT)
   For report on this improvement, see page 742.

                   2. ILLINOIS AND MISSISSIPPI                            CANAL, ILL.
   Location. This canal connects the Illinois and the Mississippi
Rivers, proceeding from a point on the Illinois River about 12
miles from La Salle across the State of Illinois to the Mississippi
River at the mouth of Rock River.
   Existing project. This provides for the construction of a canal
from the Illinois River, near Bureau, running westerly via the Bu-
reau Creek Valley to Rock River, near Colona, thence in the bed of
Rock River to the rapids near Milan, and thence to the Mississippi
River at the mouth of Rock River, at Rock Island, the length of the
main line being 75 miles. The feeder, 29.3 miles in length, extends
from Rock Falls on Rock River to the summit level of the canal,
about 28 miles from the Illinois River.
   There are 32 locks in the main canal, described in the following
tabulation. There is also a lock and controlling works at the head
                                                                                                   747
748                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

of the feeder at Rock Falls and a lock in Rock River at Rock Falls
connecting the pool of the Government dam with the pool of the
power company's dam below. This lock has dimensions similar to
those in the main canal and cost $75,000.
   The cost of new work for the completed project was $7,605,143.41.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                            Work authorized                                     Documents

                   .Existing project adopted       ----------------------       H.  Ex. Does. 316 and 429, 51st
Sept. 19,1890                                                                     Cong., 1st seas; Annual Re-
                                                                                  port, 1890, p. 263.
                   [Estimate of cost for new work revised to $8,01-1,551.12__   H. Doc. 297, 57th Cong., 1st sess.
June 26, 19341      Operation and care of the works of improvement pro-
                     vided for with funds from War Department appro-
                      priations for rivers and harbors.
July     3, 1930    For payment of $8,450.75 to the Mud Creek special           H. Doc. 108, 70th Cong., Istsess.
                      drainage district for work accomplished by the said
                      district.
        Do    --    Secretary of War authorized to expend from funds            Specified in act.
                      appropriated and available for maintenance and
                      improvement of existing river and harbor works
                      the sum of $25,235 as a contribution toward the
                      relocation and reconstruction of the highway
                      bridge across the Illinois and Mississippi Canal
                      at Wyanet, Bureau County, Ill., known as bridge
                     No. 10.

  1   Permanent Appropriation Repeal Act.
The latest published map is shown .on page 2013 of Annual Report for 1908.
                                                                     Table showing featuresof the Illinois and Mississippi canal
                                                                                                        LOCKS


                                                        Location                                                 Locks
                                                                                                                                                                                                                               cii

                                  Distance
                                                                                                   Dimensions                Depth on miter sill                                                                               z
                                                                                                                                                                                         Year
          Name                         from                                                                                                                Character of                opened to        Total cost
                                      Missis-     Distance from nearest town or                   Greatest                                                 foundation                 navigation
                                       sippi
                                      River
                                      (miles)
                                                  mouth of navigable tributary           Width of length
                                                                                         chamber available
                                                                                          (feet)  for full
                                                                                                   width
                                                                                                   (feet)
                                                                                                                  Lift
                                                                                                                 (feet)
                                                                                                                               Upper
                                                                                                                               (feet)
                                                                                                                                           Lower
                                                                                                                                           (feet)
                                                                                                                                                                                                                               a
Lock   1_.............                  74. 87   Illinois River, 2,000 feet west -..--        35      143.08         9. 0          8. 17      7.0   Sand and clay........... Oct. 24, 1907                 $41,305. 03
Lock   2_.              ___             73. 91   At Bureau._                                  35      143. 08        9.0           8.17       7.0   Sand, clay, and gravel... .....            do-.....     42, 099.69         0i
Lock   3.............._                 73.29    M  mile west of Bureau ... ____---           35      143.08         9.0           8. 17      7.0   Quicksand and gravel..                                  39, 172. 01
Lock   4_.............                  71.75    2% miles west of Bureau __....               35      143. 08        9.0           8.17       7.0   Sand and gravel......... .....             do ......    39, 357. 10
Lock   5_........._....                 70.63    3Y miles west of Bureau. _......             35      143. 08        8.0           8.17       7.0  .....do-.---.-..-.---.-...            ..... do......     39, 509. 45        0     '
Lock   6...........-------------...     68. 75   5 miles west of Bureau...........            35      143. 08:      10. O0         8.-17      7.0   Sand, hardpan, and                                      41, 927. 72
                                                                                                                                                      gravel.                                   do..-...
                                                                                                                                                                                          ....----
Lock 7...............                   68.00    3 miles east of Tiskilwa..........._         35      143.08         8.0           8.17       7.0   Loam and sand-.......                                   35, 635. 09
Lock 8_.............                    67. 02   2 miles east of Tiskilwa .... __ __          35      149. 75        8.0           8;17       7.0 ..... do...................            ..... do .....     36, 274. 37
Lock 9-..............                   66.80    1% miles east of Tiskilwa__.....__           35      149. 75        8.0           8.17       7.0   Clay._.              .-..---.                           32, 134. 93        r
Lock 10_....__.______                   64. 98   At Tiskilwa......................            35      149. 75        9.0           8. 17      7.0   Sand and gravel......... .....             do ......    36,113.71
Lock 11............__                   64. 13   1 mile west of Tiskilwa-.....____            35      149. 75-       9.0           8.17       7.0 .....do--..........              .---- ..... do ......    36, 710. 05
Lock 12__________                       63. 56   1% miles west of Tiskilwa .. _....           35      149.75         8.0           8.17       7. 0 .....do--........- ----               ..... do-......    33, 827.14
Lock 13...........___                   62. 83   3 miles west of Tiskilwa ..........          35      146. 75       10. O0         8.17       7.0   Loam and clay.......... ....               do ...
                                                                                                                                                                                              ----          32, 294. 88
Lock 14.._____        . .__.            62. 02   3 miles east of Wyanet-....__....            35      149.75        10. 0          8.17       7.0   Sand and gravel......... .....             do....
                                                                                                                                                                                                 o .......  31, 524. 90        -
Lock 15_..... ......                    61.42    2% miles east of Wyanet..........            35      149. 75       10.0           8.17       7.0 .....do--...................             .--_do.......
                                                                                                                                                                                         ..... do .......   29, 974. 01        .
Lock 16_............                    61.23    2 miles east of Wyanet............           35      149. 75       11.0           8.17       &7. Loam, clay and sand . - .....          .... _do.......
                                                                                                                                                                                               do .......   34, 089.
                                                                                                                                                                                                                5    19,
Lock 17....                             60. 98   1% miles east of Wyanet........._            35      149.75        10.0           8.17             Sand and gravel--------                                 32, 576. 27
Lock 18_............                    59. 90   1 mile east of Wyanet........ ._._           35      149.75         9.0           8.17       7. O0 Clay and gravel.........
                                                                                                                                              7.0                                                           35, 372. 69    3
Lock 19 ...._ .... _._                  59. 12   At Wyanet ......                             35      149.75        10. 0          8.17       7.0   Sand and gravel-.........                               34, 239. 36        -
Lock 20...           ___                58. 09   1 mile west of Wyanet..___.......            35      149. 75       11.0           8.17       7.0   Loam, clay and sand-.... .....             do.......    363838. 76         C
Lock 21-.............                   57. 83   13 miles west of Wyanet..........   1        35      149.75        11.0           8.17       8.0       do-..................
                                                                                                                                                       -..                                                  38,026.88          H
Guard lock........                      29.20    29 miles north main-line canal ....          35      149. 00     (2)              8. 30      6.5 Limestone--............. .....               do.......    32,678. 57
Rock River lock 3 ._                    29. 20   At Rock Falls, Ill...-.....--....--          35      143.08      (2)              8. 47      6.6 .. ..do ---............... 1913                           75, 605. 01
Lock 22..............                   46. 32   13 miles west of Wyanet ........             35      143.08        9.0            8.17       7.0   Clay..................                       24,
                                                                                                                                                                                       . Oct. do......1907  42, 458. 63        H
Lock 23.............                    37. 12   10 miles east of Geneseo .........           35      143.08       11.0            8.17       7.0 ..... do..... ...........           _.                    41, 777. 95
Lock 24.............                    27. 05   At Geneseo..------------....-----            35      143.08       11.0            8.17       7.0   Clay and gravel......... ....                           47, 059. 15
Lock 25..............                   21. 56   5% miles west of Geneseo..........           35      143.08        8.0            8. 17      7.0                                                       _
                                                                                                                                                                                              _do .......   40, 492. 10
                                                                                                                                                    Sand._..-----                 -
  See footnotes at end of tables
                                                                      Table showing features of the Illinois and Mississippi canal--Continued
                                                                                                           LOCKS-Continued

                                                            Location                                                               Locks

                                                                                                               Dimensions                           Depth on miter sill
                               Distance                                                                                                         i
                                                                                                                                                                                                                         Year
          Name                  from                                                                                                                                                          Character of             opened to             Total cost         0
                                Missis-            Distance from nearest town or                       Greatest                                                                               foundation               navigation                               b
                                sippi              mouth of navigable tributary               Width of  length
                                River                                                         chamber available                     Lift             Upper              Lower                                                                                   t-4
                                (miles)                                                         (feet) for full                    (feet)            (feet)             (feet)
                                                                                                        width                                                                                                                                                   0
                                                                                                         (feet)


Lock   26 .........                 20.   46                           _
                                             5 miles east of Colona_ _.....                               35        143.08              9.0               8. 17               7.0  Sand..------------- -. Oct. 24,1907             $40, 428. 75                 0i
Lock   27.                          18.   13 2% miles east of Colona ___.- -                              35        143. 08              8.0              8.17                7.0  Gravel__                  . ....... do.......    39, 090. 66
                                                                                                                                                                                   Rock           _.... .. ..
                                                                                                                                                                                              .. ...
Lock
Lock
       28__
       29-- ..--..
                                    15.
                                    13.
                                          70
                                          37
                                             At Colona----.....-- ---------
                                             2% miles west of Colona ........
                                                                                                          35
                                                                                                          35
                                                                                                                    143.08
                                                                                                                    143. 08
                                                                                                                                         8.0
                                                                                                                                        11.0
                                                                                                                                                          8. 17
                                                                                                                                                          8. 17
                                                                                                                                                                              7.0
                                                                                                                                                                              7.0  ...do ......
                                                                                                                                                                                                                 ......do .......
                                                                                                                                                                                                  ...... ....... do ......
                                                                                                                                                                                                                                    30, 808. 53
                                                                                                                                                                                                                                    37,262. 65                  zC
Lock   30- -_......                  4.   62 1% miles east of Milan .-......                              35        149.00               0                7.00                7.0  Rock, etc., hardpan__          .... do .     ..  71, 588.00                   H




Lock   31. .......                   2.   02 1 mile west of Milan                                         35        145. 42              6.0              7.17                7.0  Clay and gravel ...... -------      do.-.-..     38, 711.44
Lock   32- .......                       .15 3% m iles wes t of M ilan .. . .. . . . .                    35        143. 08             12. 0             8. 00               7. O0 .- do ................     -----   do----- $1 85, 468. 31

        Total cost,
         locks ..                                                                                                                                                                                                    _----------------       $1,382,432.98
                                     I                                                                                                          1                  l                t                            1                       i
                                                                                                                                                                                                                                                                 00
                                                 ADDITIONAL FEATURES ENTERING INTO COST OF PROJECT
                                                                                                                                                                                                                                               $128, 857.97
                                                                                                                                                                                                                                                                 F



Sterling Dam and dams at Milan, Ill -----------------     _ -- __..--.           ...
B rid ges.. . .-. .- -. . --. . -. -. . - . -. --. . .- -. . - . - . . . .                                                                                                                                                                    1, 513, 823. 25
Culverts---                                                                  .. .   ..   ..   .. .   ..        ..   . . .     ..   ..    . ..       .. .. .       ..         . .    .     .      .   .       .   .    . - . ---- .
                                                                                                                                                                                                                                                 410, 198. 19    00
                                                                                                                                                                                                                                                                 ca




H ouses..._ ..... _. ___          _ _         ..                              .       _. .__                    .
                                                                                                      . ............... .        .        .       .        ..                                   .........                                         76, 974. 69
Surveys, flowage, and right-of-way--...-------------         --...-----------------------------------------------------------------------------                                                                                                  726, 656.61     te.
Excavations, embankments, clearing, fences, etc ...----    ---------------------------------------------------------------..                                                                                                                  2, 956, 451.61
Rock River pool-dredging, removing snags and stumps, etc __.------..             -------      --------- ------            . . ..           ...       ...        ..-------------------
                                                                                                                                                                      --------------------- ------------                                         152, 439. 58
Contribution to Mud Creek special drainage district-dredging          -------        ------------------------------                                                    ---------
                                                                                                                                                         - --------------------             -----------                                            8, 450. 75
Contributions to State of Illinois-relocation and reconstruction of highway bridge at Wyanet, Ill                                  -----------------------------------------------                                                               25,235.00       F
Miscellaneous_- _ . . . . . . . . . . . . . . . . . . . . . . . . -------------------------------------------------------------------------
                                                                                                            . . . . . . . . . . . . . . . . . . ..-----------------------                                                                       223, 622. 78

        Total additional features              -----.--------------------                       .                                                                 -..                                                                         6, 222, 710. 43

        Total cost of project-.....               _                                                                                                                     _.              . .                              .     .              7, 605, 143. 41

   1 Feeder section.                                                                          NOTE.-There are no dams except at the guard lock and lock 30. At the former locality
  2 Variable.                                                                               there is a fixed dam across the Rock River, with a movable crest constructed of wood,
   * Rock River lock is on Rock River at Rock Falls, Ill. It is located in the south end of concrete, and steel; at lock 30 there are crib dams across the north and south channels of
the Sterling Dam and about 600 feet below the guard lock of the Illinois and Mississippi Rock River. The north dam has a 60-foot opening and has been superseded by a concrete
('anal (feeder section).                                                                    power dam a short distance below; the south dam adjoining lock 30 has been reinforced
                                                                                            with concrete laid in the water.
             RIVERS AND HARBORS-ROCK ISLAND, ILL., DISTRICT                                                                                   751
   Local cooperation. Fully complied with.
   Terminal facilities. None.
   Operationsand results during fiscal year. The canal structures
were not operated or maintained for purposes of navigation during
the fiscal year. Minimal maintenance pending disposal of the canal
was performed by hired labor. A detailed study of the problems
involved in effecting disposal of the lands and facilities was in prog-
ress. Federal, State, and local governmental agencies and private
interests were contacted to obtain their views relative to the use of
the lands and facilities for park or other beneficial purposes, and
assumption of the responsibility for future operation and mainte-
nance. The costs during the fiscal year were $87,545 for operation
and care.
   Condition at end of fiscal year. The existing project was com-
pleted in 1918. Locks, dams, aqueducts, buildings, and other ap-
purtenances are in fair-to-poor condition. Tabulation under para-
graph "Existing project" gives data regarding the principal fea-
tures of construction. Since June 30, 1951, canal structures have
not been operated or maintained for purposes of navigation, in ac-
cordance with the policy of the Corps of Engineers to suspend lock
operation and maintenance of waterways affording little or no
benefit to general commerce and navigation, and to eliminate non-
essential maintenance expenditures.
  The total costs to June 30, 1954, from regular funds was
$10,632,282, of which $7,580,143 was for new work and $3,052,139
was for operation and care. The costs from Emergency Relief
funds for removal of snags and stumps in Rock River Pool were
$25,000, all new work. In addition, the sum of $4,143,282 was ex-
pended between April 1895 and June 30, 1936, on the operation and
care of the works of improvement under the provisions of the per-
manent indefinite appropriation for such purposes.

                                                 Cost and financialsummary

                                                             iscal year ending June 30                                              Total to June
                                                                                                                                   30, 1954, includ-
                                                                                                                                   ing fiscal years
                                         1950             1951                 1952                1953               1954          prior to 1950

New work:
   Appropriated---- ------------                -----            --.------------      ------- -------          -----------               $7, 605, 143
   Cost   ---------------------------                   -----------------                -------    -----     -----          ---          7, 605,143
Maintenance:
   Appropriated                         $200,000        $168, 000            $130, 000             $84, 900           $80, 000          2 7, 196. 582
   Cost--------              --          206,313         179,993               125,898              81,325             87, 545            7,195,421

  1 Includes $25,000 Emergency Relief funds.
  2 Includes $4,143,282 for operating and care under the "Permanent Indefinite Appropriation".


       3. MILL               CREEK AND                    SOUTH                    SLOUGH AT MILAN, ILL.
  Location. Mill Creek empties into South Slough about 1 mile
east of the town of Milan, Ill., and 6.5 miles above the mouth of
South Slough, which empties into the Mississippi River.
  Previous projects. Adopted by the River and Harbor Act of
January 21, 1927. (For further details, see p. 1132, Annual Report
for 1932, and p. 1081, Annual Report for 1938.)
  Existing project.                             This provides for floodgates in the walls of
752               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

the Illinois and Mississippi Canal, or other devices for carrying the
floodwaters of Mill Creek across the canal right-of-way into Rock
River; for the construction of a levee on the east bank of Mill Creek
extending from the Chicago, Rock Island & Pacific Railroad to the
canal embankment; for the construction of a levee on the west bank
of Mill Creek and its extension in a westerly direction to a connec-
tion with Water Street at the point E, shown on map of project
document; and for the removal of obstructions in Mill Creek and
South Slough. The cost of new work for the completed project was
$63,633.58. The estimated cost of maintenance, revised in 1954, is
$10,000 annually.
   The existing project was adopted by the River and Harbor Act
approved July 3, 1930 (Rivers and Harbors Committee Dec. 19, 71st
Cong., 2d sess.). The latest published map is in the project docu-
ment.
   Local cooperation.: Fully complied with.
   Terminal facilities. None.
   Operations and results during:fiscal year. Hired labor forces
cut brush and willows on the banks of Mill Creek and South Slough,
performed minor dredging and snagging, and operated spillway
gates.
   The costs during the fiscal year were $2,131 for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1932. The project was in fair condition at the end of the
fiscal year. The total costs under the previous project were $85
for new work and under the existing project to June 30, 1954, were
$137,665, of which $63,634 was for new work and $74,031 was for
maintenance.
                                                  Cost and financial summary

                                                               Fiscal year ending June 30                                Total to June
                                                               -30,                                                            1954, includ-
                                                                                                                   15   ing fiscal years
                                         1950               1951              1952            1953          1954             priorto 1950

New work:
   Appropriated-------------------------------------------------------------                                                            $63, 719
   Cost--_-----------------------------------------------------------                                                                    63, 719
Maintenance:
   Appropriated.-------             $37, 000                 $5, 500         -$2, 000          $2, 000       $3, 000                     74,900
   Cost__.....        ..-------------- 7, 051                22, 968           11,524           2,000         2,131                      74, 031



                              4. INACTIVE NAVIGATION                                         PROJECTS

                                                                          For last          Cost to June 30, 1954              Estimated
                                                                        full report,                                            amount
                     Name of project                                    see annual                                             required to
                                                                          report                                                      plete
                                                                           for-            New work      Maintenance            com

Remove obstructions from Rock River, Ill.
  (under sec. 3, 1930 River and Harbor Act)_.-.-                            1952                           $4, 500.00              (1)
Remove obstructions from Galena River, Ill.
  (under sec. 3, 1930 River and Harbor Act)-......1952                                 -                    1,000.00               ()
Dredging in Iowa River, Iowa (under sec. 3, 1945
                         ..................... 1952
River and Harbor Act)...---------------------                                                              5,000.00
                                                                                                            5,------------         (1)
Removal of two sunken vessels at Quincy, Ill.
  (under sec. 19, 1899 River and Harbor Act).....                          1952                                975.68
                                                                                                           4--------------3,       (1)


  SCompleted.
           FLOOD CONTROL-ROOL   K ISLAND, ILL., DISTRICT         753
                       5.: THE SNY BASIN, ILL.
   Location. This project i loeated in the basin of the Sny, a
former bychannel of the Mississippi River, in Pike, Adams, and
Calhoun Counties, Ill., approximately miles 260.9 to 315.4 above
the mouth of the Ohio River. The major tributaries of the Sny
are McCraney, Hadley, Kiser, Six Mile, and Bay Creeks. Several
minor tributaries include Fall, Pigeon, Horton, and Dutch Creeks.
 (The entire Sny Basin is shown on topographic maps of the U. S.
Geological Survey, scale 1:62,500, dated 1921-28.)
   Existing project. The plan of improvement now being con-
sidered for the prevention of interior flooding within the Sny bot-
tom lands consists of construction of two retarding and desilting
reservoirs for Pigeon Creek and for Horton-Dutch Creeks; con-
struction of three diversion channels for McCraney-Hadley Creeks,
Kiser Creek, and Six Mile-Bay Creeks to conduct the runoff from
the uplands drainage area directly to the Mississippi River; im-
provement of certain reaches of the Sny channel to collect bottom-
land runoff; construction of three pumping stations; construction
of. a closing levee to exclude backwater up the Sny; construction
of aqueducts or culverts to pass drainage which would otherwise
be blocked; and the construction of remedial works necessitated
by the improvements.
   The estimated Federal cost for construction of the project, re-
vised in 1954, is $18,507,800. The project was authorized by the
Flood Control Act approved July 24, 1946, substantially in ac-
cordance with the recommendations of the Chief of Engineers in
House Document 713, 79th Congress, 2d session. The latest pub-
lished map is in the project document.
   Local cooperation. Section 3 of the Flood Control Act approved
June 22, 1936, applies. In addition, local interests will be re-
quired to furnish necessary authority to abandon obstructive
bridges, and make all necessary alterations and relocations of
highway bridges, roads, subsurface drains, and public utilities
affected by the improvement.
   Local interests were informed of the local cooperation require-
ments on September 8, 1947. Assurances, executed by the com-
missioners of the Sny Island levee drainage district on February
9, 1948, were forwarded on July 25, 1952, to the Chief of Engineers,
and acceptance thereof was authorized on August 8, 1952. The
assurances were formally accepted by the district engineer on Sep-
tember 6, 1952.
   In order that the Sny Island levee drainage district may raise
the necessary funds to meet the local cooperation requirements, it
will be necessary to secure court approval of the project. The
drainage district must file a petition accompanied by detailed con-
struction plans and rights-of-way maps in the county court. These
construction plans and rights-of-way maps will be furnished the
drainage district by the Rock Island district office.
   Operations and results during fiscal year. Preliminary plan-
ning, including field surveys, design, and estimates, by hired labor,
was continued during the fiscal year. The costs during the fiscal
year were $62,657 for new work.
   Condition at end of fiscal year. Construction has not been
754                     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

started. Preliminary planning of the project, by hired labor, is
about 40 percent complete. The total costs to June 30, 1954, were
$505,974 for new work.
                                                     Cost and financial summary

                                                              Fiscal year ending June 30                                    Total to June
                                                                                                                            30, 1954, includ-
                                                                                                                            ing fiscal years
                                              1950          1951           1952              1953                1954         prior to 1950

New work:
   Appropriated--------........              $100, 000 -2, 100, 000     -$16, 000            $70, 000            $30,000           $508, 700
     Cost----------------.................    108, 934       35, 723         16, 307          34, 617             62, 657           505, 974


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 ....--------------                                                       $...2,726
    Appropriated for succeeding fiscal year ending June 30, 1955..........                                                         70,000
    Unobligated balances available for succeeding fiscal year ending
            June 30, 1955. ...................           -- -----   .    .......----.---..          ------....                     72, 726
       Estimated additional amount needed to be appropriated for com-
            pletion of existing project................................... .                                                  17, 929, 100
                                                                                                           ...........------------------------------.

  6. CORALVILLE RESERVOIR, UPPER MISSISSIPPI RIVER BASIN,
                           IOWA
    Location. The work covered by the project is on the Iowa
River, upstream from the city of Iowa City, in Johnson County,
Iowa, approximately 83 miles above the mouth of the Iowa River
which empties into the Mississippi River about 433 miles above the
mouth of the Ohio River.
   Existing project. The plan of improvement provides for the
construction of an earth-filled dam rising approximately 100 feet
above the streambed, a 500-foot uncontrolled spillway, outlet works
to control the flow of the river to bankfull stage below the dam, and
a reservoir providing for a controlled storage of 492,000 acre-feet.
The project will minimize flood damages on the Iowa River from the
dam to the mouth of the Cedar River. It will provide a large degree
of protection for lands along the Iowa River below the mouth of the
Cedar River, and significant reductions of Mississippi River flows
at Keokuk, Iowa, and reduction in flows at Cairo, Ill. The existing
project was selected and approved by the Chief of Engineers under
the general authorization contained in the Flood Control Act
approved June 28, 1938. The estimated Federal cost, revised in
1954, is $19,643,500, including $13,807,500 for construction and
relocations, and $5,836,000 for lands and damages.
   Local cooperation. None required.
   Operations and results during fiscal year. Preliminary plan-
ning was continued. Land acquisition, including mapping and sur-
veying, appraisals, purchases, and condemnations, was performed.
The total costs during the fiscal year were $98,979 for new work.
   Condition at end of fiscal year. Construction of the project
was started in July 1949, and is 33 percent complete. Stage I (con-
sisting of site clearing, construction of a portion of the earth-
embankment section of the dam, placing of protection stone, in-
stallation of piezometer and settlement gages, and construction of
field office building) was completed in 1949. Stage II (consisting
of construction of outlet works) was completed in 1953.                                                                             Pre-
                        FLOOD CONTROL--ROCK ISLAND, ILL., DISTRICT                                                                         755
liminary planning is 77 percent complete. Work in connection with
lands and damages is 53 percent complete. Of a total of some 34,000
acres which will be involved in land acquisition, to date 15,702
acres have been acquired in fee, flowage easements have been ob-
tained for 798 acres, and 119 acres have been transferrd from
other Government agencies. All existing features of' the project
are in good condition. The principal features of work remaining
to complete the project are stage III (consisting of construction of
spillway and completion of embankment section of dam) and rem-
edial works. The total costs to June 30, 1954, were $5,492,286 for
new work.
                                                  Cost and financial summary

                                                              Fiscal year ending June 30                                       Total to June
                                                                                                                              30, 1954, includ-
                                                                                                                              ing fiscal years
                                          1950              1951             1952              1953              1954           prior to 1950
New work:
   Appropriated--------               $2, 455,500       $2, 400, 000 ---------------------------------                               $6,010,148
     Cost- - -------------             1,220, 418        1, 502, 613     $1, 098, 537         $810, 244          $98, 979             5, 492, 286

   1 $341,500    reserved in Office, Chief of Engineers.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954--------... ----.............                                                   $434, 651
    Appropriated for succeeding fiscal year ending June 30, 1955-----                                                  ..........--. 1,750,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955--..---....------------.........--...........................................................-------------.......... 2, 174, 651
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project---.........................------------------------...............................----..... 11,883, 352

  7. UPPER MISSISSIPPI RIVER BASIN, ROCK ISLAND DISTRICT
   Location. The Mississippi River Basin above the Ohio River,
exclusive of the Missouri River Basin, in the Rock Island district.
   Existing project. The Flood Control Act of June 28, 1938, ap-
proved the general comprehensive plan for flood control and other
purposes in the Upper Mississippi River Basin described in Flood
Control Committee Document 1, 75th Congress, 1st session, with
such modifications thereof as in the discretion of the Secretary of
War and the Chief of Engineers may be advisable, and authorized
$6,600,000 for reservoirs and $2,700,000 for local flood-protection
works on the Upper Mississippi and Illinois Rivers; the reservoirs
and local protection projects to be selected and approved by the
Chief of Engineers. The act approved June 28, 1938, specifically
provides that the authorization shall include the enlargement and
extension of a system of levees located on the south side of the
Sangamon River east of Chandlerville, Ill., as set forth in House
Document 604, 75th Congress, 3d session. The Flood Control Act
of December 22, 1944, authorized to be appropriated the additional
sum      'f
        $10,000,000 for prosecution of the comprehensive plan, in-
cluding the Red Rock Reservoir on the Des Moines River. The
Flood Control Act of July 24, 1946, authorized to be appropriated
the additional sum of $10,000,000 for prosecution of the compre-
hensive plan. The following individual projects located in the
Rock Island district were considered in the comprehensive plan:
756               REPORT QF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                     RESERVOIRS

                                                                                                                   Total
               Name.                         Tributary basin                           State                    estimated
                                                                                                               Federal cost


Central City_ ----          .                          ---------
                                        Waps sipinicon__    ___          Iowa -.                           S    '$9 ,490000
           ...-
Coralville __        ......             Iowa.                               .do .                               S--19,643,500
Rochester ........                               -- --------
                                        Cedal r---           - --                                      S'13,        300,000
                                                                         ...do ....
Red Rock-.-                             Des l Moines -        -- -                                              ' 77,700,000

                                                       LEVEES


Union     Township       drainage   -                                    Missouri-                               $109,620.64
  district.s

  1 Estimate revised in 1954.
  2See individual report for details of project.
  3 Completed. For last full report, see Annual Report for 1947, p. 1420.


    Operations and results during fiscal year.                                             None, except for
work on the Coralville Reservoir project as shown in individual
report.
    Condition at end of fiscal year.                             The progress of work on reser-
voir projects selected for construction under this authorization is
given in individual reports. No work has been performed in con-
nection with general studies for the development of the comprehen-
sive basin plan.

                       8.       INACTIVE FLOOD CONTROL PROJECTS

                                                            For last        Cost to June 30, 1954              Estimated
                                                          full report,                                 _        amount
                     Name of project                           see                                              required
                                                             annual           Con-         Operation               to
                                                             report        struction          and              complete
                                                              for-                        maintenance
                                                                                                                     ()
Green Island levee and drainage district No. 1,                1938
  Iowa.
Carroll County levee and drainage district No. 1,              1938                                                  (1)
  Illinois.
Keithsburg drainage district, Illinois ....2 _.....            1938                                                  ()
Janesville and Indian Ford Dams, Wis. ........                 1938      . . . . . . . .. . . . . .             $         103,
                                                                                                                             000
Gregory drainage district, Missouri-...........                1940           $77, 100          ----       -         (z)
South Quincy drainage and levee district, Illinois_            1940            61,200                                (3)
Penny Slough, Rock River, Ill____ .           ..               1940            85, 800                               (5)
Fabius River drainage district, Missouri ......                1941            60,500                                (3)
South River drainage district, Missouri ....._.                1941            55,300          -.-                   (3)
Sny Island levee drainage district, Illinois       -----       1942            61,400                                (3)
Union Township drainage district   2 levee, Missouri           1947           109,621            --                  (3)
Sabula, Mississippi River, Iowa                     -          1947                100                                     67,900
                                                                                                                     (3)
Green Bay levee and drainage district No. 2,                   1949           299, 000
  Iowa
Henderson County drainage district No. 3,                      1949            42, 700                               (3)
  Illinois.                                2
Des Moines River at Des Moines, Iowa ........                  1950             1,519                                 718, 480
Elkport, Turkey River, Iowa ......            ----             1951            34,200
Galena, Galena River, Ill ........                             1952           844,100
Henderson   River. Ill.4................
                                     4
                                                               1952            28,000                               2, 632, 000
Freeport on Pecatonica River, Ill.4                __          1952            48,075                               1, 041, 925
Mississippi River at Canton, Mo. -.                            1952                                                 1, 290, 000
Rock River, Ill. and Wis., at South Beloit, Ill.4_.            1952                                                    120, 000
                                                                                                                     (5)
Emergency flood control work under authority                   1952                            $234,
                                                                                                   260
  of the Flood Control Act approved Aug. 18,
  1941, as amended.
Red Rock Reservoir,
              4        Upper Mississippi River                 1953         1, 295, 300                          76, 404, 700
  Basin, Iowa

  ' District acquired by the United States.
    Deferred pending further study.
  * Completed and transferred to local interests for maintenance and operation.
  4No funds available.
  5All work presently contemplated under this authorization has been completed.
               FLOOD CONTROL-ROCK ISLAND, ILL., DISTRICT                                        757
                           9. GENERAL INVESTIGATIONS
  Examinations and surveys. The costs and expenditures during
the fiscal year were $30,245 for examinations and surveys. The
balance unexpended at the end of the fiscal year, $646, will be
applied to continuation of work during fiscal year 1955.
  The additional sum of $67,600 can be profitably expended for
work during fiscal year 1955.
  Collection and study of basic data. Collection and study of
basic information pertaining to river and harbor and flood control,
and related programs were performed during the fiscal year. This
~work consisted of stream gauging, precipitation studies, fish and
wildlife studies, storm studies, sedimentation studies, flood emer-
gency studies, and various related hydrologic studies.
  The costs and expenditures for collection and study of basic data
during the fiscal year were $6,000.
    10. I:NSPECTION          OF COMPLETED FLOOD CONTROL WORKS
   Federal flood control regulations (Part 208 of Title 33, Code of
Federal Regulations) provide that the structures and facilities
constructed by the United States for local flood protection shall be
continuously maintained in such a manner and operated at such
times and for such periods as may be necessary to obtain the maxi-
mum benefits. Completed flood control works in the Rock Island
District which have been transferred to local interests for opera-
tion and maintenance were periodically inspected during the fiscal
year to assure that these results were being obtained. The costs
during the fiscal year were $4,978 for maintenance.
                                   Cost and financial summary

                                         Fiscal year ending June 30                    Total to Tune
                                                                                       n 1954, iticlud-
                                                                                      30,
                            1950        1951        1952        1953       1954       i g fiscal years
                            190         19561       1952        1953       1954        prior to 1950

Maintenance:
   Appropriated --------                 $3, 250--- ....--       $3, 000    $4, 500            $10, 750
   Cost...           ---
               ......--    --------       3,250 .........         1, 019     4, 978              9, 247



11. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
   Snagging and clearing of navigable streams and tributaries in
the interest of flood control. (Section 13 of the 1946 Flood Con-
trol Act.)
   Operations during the fiscal year consisted of channel straighten-
ing of the Fabius River in Marion County and Fabius River Drain-
age Districts, Marion County, Mo. The work consisted of excava-
tion of approximately 5,540 linear feet of new river channel,
construction of two closing dikes in the existing river channel, and
disposal of surplus excavated materials in spoil areas. Construc-
tion was started in October 1953, and completed in December 1953,
a total of 228,516 cubic yards of material having been excavated.
The costs during the fiscal year were $40,430 for new work,: of
which $16,000 was contributed by local:interests.
  The total costs under this authority to June 30, 1954, were $132,-
694, of which $16,000 was contributed by local interests.
758                  REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                  Cost and financial summary

                                                               Fiscal year ending June 30                             Total to June
                                                                                                                     30, 1954, includ-
                                                                                                                     ing fiscal years
                                          1950                1951        1952               1953         1954         prior to 1950
New work:
      Appropriated_               -         -$13, 000 -$13,                    000            $9, 264     $50, 000          1 $142, 264
      Cost...............-----------------.           ------------
                                                32, 250                     8, 728            13, 536      24, 430           1 116, 694



  1
   Includes $19,000 for snagging and clearing on Bay Creek, Sny Island Levee Drainage District, Ill.,
formerly considered a separate project. See Annual Report for year 1947.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954...........             $25, 570
                                                                        ....----------....
    Unobligated balances available for succeeding fiscal year ending June 30,
       1955.....-------------------------------------------------25, 570

                                                  Cost and financial summary

                                                               Fiscal year ending June 30                             Total to June
                                                                                                                     30, 1954, includ-
                                                                                                                     ing fiscal years
                                          1950                1951        1952               1953         1954        prior to 1950

New work:
   Appropriated-----..... _       ..-----.------------- ------------ ------------                         $16, 000            $16, 000
   Cost--------.          .-----------------------------------------------............                     16,000              16, 000


   Small flood control projects not specifically authorized by Con-
gress. (Section 212 of the 1950 Flood Control Act.)
   Preparation of a project report on the effect of floods in Okabena
Creek at Worthington, Minn., was completed during the fiscal year.
The project as recommended in the report was approved for con-
struction by the Chief of Engineers under the above authority at
an estimated total cost of $134,500, including Federal costs esti-
mated at $77,600. Construction has not been started. The costs
during the fiscal year were $8,352 for new work.
   The total costs under this authority to June 30, 1954, were $8,500
for new work.
                                                  Cost and financial summary

                                                                Fiscal year ending June 30                            Total to June
                                                                                                                     30, 1954, includ-
                                                                                                                     ing fiscal years
                                          1950                1951        1952               1953         1954        prior to 1950

New work:
   Appropriated--..              -----------------------------------                          $3, 500      $5, 000             $8. 500
      Cost     ------------------------------------------------                                     148     8, 352              8,500


Other new work data: Estimated additional amouint needed to be appro-
   priated for completion of existing project--                                      -----           .............
                                                                                               -----------------------      77, 600

  Flood control emergencies-Repairand flood fighting and rescue
work. (Section 210 of the 1950 Flood Control Act and supple-
mental authorizations.)
   Pursuant to these acts, the amount of $3,167,886 has been al-
lotted to the Rock Island District for emergency flood control work.
During the fiscal year, 5 emergency levee-repair jobs were com-
pleted. The costs during the fiscal year were $65,515 for main-
tenance.
               FLOOD CONTROL--ROCK ISLAND, ILL., DISTRICT                                     759
  The total costs under this authority to June 30, 1954, were $3,-
167,886.
                                 Cost andfinancial summary

                                       Fiscal year ending June 30                    Total to June
                                                                                    30, 1954, includ-
                                                                                    ing fiscal years
                          1950        1951        1952        1953       1954         prior to 1950

Maintenance:
   Appropriated--...... -$21, 310    $296, 800   $407, 200   $810, 400    $2, 800        $3, 167, 886
        ---------------
   Cost................    41,681      70,090     898,88      494,151     65, 515         3,167, 886
      IMPROVEMENT OF RIVERS AND HARBORS IN THE
               ST. PAUL, MINN., DISTRICT
   This district comprises western Wisconsin, a small western por-
tion of the upper peninsula of Michigan, the major portion of Min-
nesota, northern and eastern North Dakota, and small portions of
northeastern South Dakota and northern and northeastern Iowa
embracing the drainage basins of the Mississippi River and tribu-
taries from its source to mile 614 above the mouth of the Ohio
River; the Red River of the North and tributaries; those streams
north of the Missouri River Basin in North Dakota; and the United
States waters of the Lake of the Woods and its tributaries. That
section of Mississippi River above mile 614 is included in the re-
port on Mississippi River between Missouri River and Minneapolis,
Minn.
                                                 IMPROVEMENTS

                      Navigation                                    Flood Control-Continued
                                                      Page                                      Page
1. Mississippi River, between the                             9. Red Lake River, Minn., in-
    Missouri River and Min-                                        cluding Clearwater River,
    neapolis, Minn. (St. Paul                                      M inn    .------- ..-
                                                                                      .- .-. .....
                                                                                                ... 775
    D istrict) ..................                     761    10. Homme Reservoir and Dam,
2. Warroad Harbor and River,                                       N . D ak ... .........       ........
                                                                                          .......    778
       M inn ..-......................-- --- .        761    11. Lake Ashtabula and Baldhill
3. Baudette Harbor, Minn .--------- _                 763          Dam, Sheyenne River, N.
4. Reservoirs at headwaters of                                     Dak _         ...............
                                                                                       ......        780
                                                                                           .............
     Mississippi River ...-------                     764    12. Lake Traverse and Bois de
5. Minnesota River, Minn.._.           ....           767          Sioux River, S. Dak. and
6. St. Croix River, Wis. and                                       M inn .........-
                                                                                 _ ....       - -    782
     M inn ........................................   768    13. Mississippi River near Aitkin,
7. Inactive navigation projects.----                  770                 _... .........
                                                                   M inn ..                          784
                                                                                           ......-..........
                                                             14. Lac    qui Parle        Reservoir,
                                                                   Minnesota River, Minn .--... 785
                   Flood Control                             15. Inactive flood control projects-.   788
                                                             16. General investigations................
                                                                                                     788
8. Red River of the North Drain-                             17. Inspection of completed works__ 788
    age Basin, Minn., S. Dak.,                               18. Flood control work under spe-
    and N. Dak .......      ..                        770                                            789
                                                                   cial authorization ...................

  1. MISSISSIPPI RIVER, BETWEEN THE MISSOURI RIVER AND
          MINNEAPOLIS, MINN. (ST. PAUL DISTRICT)
  For report on this improvement, see page 741.
                     2. WARROAD HARBOR AND RIVER, MINN.
  Location. Warroad Harbor and River are at the southwestern
extremity of Lake of the Woods, 36 miles west of the mouth of
Rainy River. (See U. S. Lake Survey Chart No. 84, Lake of the
Woods.)
  Existing project.                      Provides for dredging and maintaining a
channel 8 feet deep from the landing at Warroad to deep water in
the lake, the channel being 9,200 feet long, 200 feet wide within
the harbor, and 300 feet wide out in the lake; for a turning basin
500 by 900 feet to a depth of 8 feet; and for a pile-brush-stone jetty
on the north side of the channel extending from the shore 700 feet
                                                                                         761
762             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

into the lake. The project depth is referred to low water datum
for Lake of the Woods, which is 1,056 feet above mean tide at
New York.
   The estimate of cost for new work, revised in 1954, is $439,000.
The latest (1928) approved estimate of cost for annual mainte-
nance is $10,000.
   The existing project was authorized by the following River and
Harbor Acts:

    Acts                                 Work authorized                                     Documents

Mar. 3, 1899     Dredging bar at mouth of Warroad River ......    -----------     Specified in act.
June 1: 10      } Entrance channel 300 feet wide and        7 feet deep-_.   ..   H. Doc. 92, 56th Cong., 2d sess.
Mar. 3, 1905     Enlargement of turning basin ...........--------------------     H. Doc. 703, 61st Cong., 2d sess.
July 25, 1912    Deepening to 8 feet.....................

  1 Appropriation.

   The latest published map is opposite page 1984 in the Annual
Report for 1911.
   Recommended modificationsof project. Under date of April 19,
1948, the Chief of Engineers recommended that the project be
curtailed by reducing the channel width to 100 feet and the turning
basin to 250 feet.
   Local cooperation. None required.
   Terminal facilities. A pile-and-plank wharf 80 feet in length
has been provided by the village of Warroad for free use by the
public. There are two commercial fish wharves 60 feet in length,
not open to the public, one of which is served by a spur track.
There are also a number of minor wharves.
   These facilities are ample for the needs of existing commerce.
   Operations and results during fiscal year. One inspection was
made by hired labor. Costs for the year were $22.
   Condition at end of fiscal year. The project as a whole is 76
percent complete. The protective jetty completed in 1910 and
reconstructed as a rubble mound in 1929, is in good condition. The
turning basin at the Warroad wharves was completed in 1911, and
a channel 200 feet wide and 8 feet deep was completed in 1915.
The controlling depth in the channel is 2.5 feet below low water
datum which is 1,056 feet above mean tide level at New York, for
a least width of 100 feet. Annual maintenance is necessary. The
shore revetment is in need of minor repairs.
   The uncompleted part of the existing project consists of widen-
ing the lake channel from 200 to 300 feet for a distance of 7,460
feet. The additional width is not necessary to meet present re-
quirements.
   The total costs under the existing project to June 30, 1954, were
$83,805 for new work and $379,929 for maintenance, a total of
$463,734.
                 RIVERS AND HARBORS-ST. PAUL, MINN., DISTRICT                                                                 763
                                         Cost and financial summary

                                                Fiscal year ending June 30                                          Total to June
                                                                                                                   30, 1954, includ-
                                                                                                                    ing fiscal years
                                  1950         1951           1952            1953                  1954              prior to 1950
New work:
                 ............
    Appropriated---------------------------                ----------      .........
                                                                          --------............--- ------------............   $83, 805
                  .
   Cost.-----------..       ------------ -----.------- ----------- -----------                      ----- -        -          83, 805
Maintenance:
    Appropriated ...              $33, 700    -$7, 000         -$1, 810          $2, 500     ..-.-------                     380, 336
    Cost-----------------          42, 436      33, 543   ............            2, 071                   $22               379, 929


Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project ... ............ ....... ... ................... .... $355, 195

                                3. BAUDETTE HARBOR, MINN.
   Location. The Baudette River has its source in the swamplands
of northern Minnesota and flows in a northeasterly direction to
Rainy River at Baudette, Minn., about 10 miles from where Rainy
River empties into Lake of the Woods. (See U. S. Geological Sur-
vey map of Minnesota.)
   Existing project. The project provides for dredging a channel
6 feet deep and 75 feet wide extending from the mouth of Baudette
River upstream a distance of about 2,000 feet with an increase in
width at the inner end to form a turning basin with a maximum
width of 230 feet.
   The project depth is referred to low water datum at Baudette,
which is taken as 1,056 feet above mean tide level at New York.
The ordinary seasonal variation of water level is about 2 feet.
   The cost of new work for the completed project was $36,415.
The latest (1945) approved estimate for annual maintenance is
$800.
The existing project was authorized by the following River and
Harbor Acts:
       Acts                          Work authorized                                                 Documents

Mar.    2,1919     Dredging - -              ----------                            H. Doc. 109, 63d Cong., 1st sess.
Mar.    2,1945                                            ...-----.
                   Present dimensions of channel and basin---                _     H. Doc. 109, 63d Cong., 1st sess.
                                                                                     (Contains the latest published
                                                                                     map.)

   Local cooperation. Fully complied with.
   Terminal facilities. The village of Baudette has a timber
wharf, and its use is open to all on equal terms. The State of
Minnesota has constructed a boathouse and warehouse adjoining
the public wharf. In addition to the foregoing, there are several
privately owned small and little used wharves on both sides of the
river.
   Operations and results during fiscal year. None.
   Condition at end of fiscal year. The existing project was com-
pleted in 1950. The project depth of 6 feet was available in the
channel on June 30, 1954.
   The costs were $36,415 for new work and $13,042 for mainte-
nance, a total of $49,457.
                                                   I
764            REPORT; OF CHIEF iOF ENGINEERS. U S. ARMY, 1954

                                    Cost and financialsummary

                                           Fiscal year ending June 30                               Total to June
                                                                                                   30, 1954, includ-
                                                                                                   ing fiscal years
                             1950         1951           1952         1953              1954        priorto 1950
New work:
   Appropriated              $24, 500      $7, 391                            -                              $36, 415
   Cost ....                    322
                              11,          20,569                            ..                               36,415
Maintenance:
   Appropriated                                 ------                                                        13,042
   Cost......13,042



    4. RESERVOIRS             AT HEADWATERS                     OF    MISSISSIPPI                   RIVER
  Location. Reservoirs are located on the Mississippi River and
several of its tributaries, in Itasca, Beltrami, Hubbard, Aitkin,
Cass, and Crow Wing Counties, Minn., as follows:

                                                Outlet                                              Area
      Name of reservoir                                   Above       Watershed          Original       Reservoir
                                        River              St.         (square            Lake           (square
                                                           Paul         miles)            (square          miles)
                                                          (miles)                         miles)

Winnibigoshish_                Mississippi ...........          408          1, 442            117             179. 4
Leech Lake__,                  Leech ...........
                      ...............         _ ...             410          1, 163            173             250. 9
Pokegama       _-              Mississippi--------              344          1660               24              35. 0
Sandy Lake-               _    Sandy -----------------          267               421            8              16. 6
Pine River._                   Pine -.--------------            199               562           18              23. 7
Gull Lake_ - -                 Gull .      --                   168               287           20              20. 5


1Exclusive of area controlled by Winnibigoshish and Leech Lake Dams.

   Previous project. Adopted by the River and Harbor Act of
June 14, 1880. For further details, see page 1888 of the Annual
Report for 1915, and page 1098 of the Annual Report for 1938.
   Existing project. This provides for the reconstruction of the
five original reservoir dams, viz, Winnibigoshish, Leech Lake,
Pokegama, Sandy Lake, and Pine River, and the construction of
Gull Lake Reservoir.
   The cost of new work for the completed project was $881,985,
exclusive of amount expended on previous projects. The latest
approved (1954) estimate of cost of maintenance and operation of
the reservoirs is $77,000 annually. The above dams are of solid
concrete construction, Pokegama being built on bedrock and the
others on pile foundations. The Sandy Lake Dam includes a lock
160 feet long, 30 feet wide, with a maximum lift of 9.5 feet and a
depth of 2.5 feet on the lower sill at low water. The abandonment
of the ditches to connect Long Lake to Round Lake and Round
Lake to Gull Lake was recommended in House Document 413, 64th
Congress, 1st session, and was ordered by Congress in the River
and Harbor Act of July 27, 1916.
                 RIVERS AND HARBORS-ST. PAUL, MINN., DISTRICT                                              765

The existing project was authorized by the following River and
Harbor Acts:

     Acts                               Work authorized                                  Documents
Mar. 3,1899       For reconstruction of 4 of the 5 original dams, and
                    surveys to determine the extent of lands over-
                    flowed by the reservoirs.
Mar. 2,1907       Reconstruction of Sandy Lake Dam and the con-
                    struction of Gull Lake Reservoir.
June 25,1910      Construction of an equalizing canal between Win-            H. Doc. 363, 61st Cong., Sd seas.
                    nibigoshish and Leech Lake Reservoirs (no work
                    was done and this part of the project was aban-
                   doned in the act of Mar. 4, 1915).
June 26, 19341    Operation and maintenance provided for with funds
                    from War Department appropriations for rivers
                    and harbors.

  i Permanent Appropriations Repeal Act.
  For map see page 1978, Annual: Report for 1911.


                 Lower operating limits by regulations approved Feb. 4, 1936, and
                                     modified Dec. 29, 1944

                 Reservoir                   Minimum                       Reservoir                 Minimum
                                             stage (feet)                                       .   stage (feet).

Winnibigoshish                                              6 Sandy Lake                       ....                 7
Leech Lake- .0....             .....                        O0 Pine River       ......------ ....                   9
Pokegama      ..---------------------                       6 Gull Lake...-----   ---------------------             5



   Local cooperation. Fully complied with.
   Terminal facilities. None.
   Operationsand results during fiscal year. The reservoirs were
operated according to plan and necessary repairs were made to the
structures. At the beginning of the: fiscal year the reservoirs were
all:;at approximate summer operating levels. Heavy rains during
the first 10 days of July caused moderate rises in stages especially
at Pokegama and Sandy Reservoirs. The stages had barely re-
turned to normal when heavy rains again occurred during the first
part of August. Flood stage was exceeded at Aitkin, Minn., and
damage stages were exceeded at Pokegama and Sandy Reservoirs.
It is estimated that regulation of the reservoirs reduced the crest
stage at Aitkin (15.10) by about 1.5 feet. Following this flood, the
reservoirs receded and normal stages were maintained until No-
vember when lowering of the reservoirs was started in accordance
with normal winter operating procedure. The last reservoir to be
lowered was Pokegama which reached minimum operating stage
during the first 10 days of April just prior to the spring breakup.
Combined snow-melt and heavy rains caused flood stage to be ex-
ceeded again at Aitkin (crest stage 14.7 on May 6, 1954) with dam-
age stages again being exceeded at Pokegama and Sandy Reser-
voirs. It is estimated that operation of the reservoirs resulted in
a reduction of about 1.8 feet at Aitkin. Following this flood, the
stages in the reservoirs declined to normal operating stages and so
remained until the end of the fiscal year. Storage at the end of
the fiscal year amounted to about 603,000 acre-feet.
766             REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954


                                 Mean monthly stages for the fiscal year 1

                                                   1953                                            1954

         Reservoir
                               July   Aug.    Sept.    Oct.    Nov.    Dec.       Jan.   Feb.   Mar.    Apr.   May June
                           Feet Feet Feet Feet Feet Feet Feet Feet Feet Feet                                    Feet      Feet
Winnibigoshish-..........10. 44 11. 12 11.25 10. 82 9. 90 9. 18 8.55 8.07 8.10 8.87                            10.14      10. 66
Leech Lake.------------ 2.56 2. 58 2. 51 1.96 1.36 1.10 0.87 0.62 0.64 1.21                                     2.11       2. 33
          ------------
Pokegama...............    9.67 10.62    9. 91 8. 98 8. 76 8. 24 7. 67 7. 54 7.00 8.43                         11.39       9.10
                          10.01 11.49 9. 26 8. 82 8. 38 7. 72 7. 08 7. 02 7.02 8.94
Sandy Lake-----------..............                                                                            11.69       9. 34
                          12. 80 13. 11 13. 20 12.35 11.22 11.68 11. 18 11.02 11.20 12. 13
Pine River-----------...............                                                                           13.02      13. 06
                           5.96 6.17 5.94 5.60 5.64 5.69 5.06 3.80 5.13 5.44
Gull Lake-------------................                                                                          6. 14      6.25

  1The mean monthly stage is the average of the stages on the 1st, 10th, 20th, and the last day of
the month.

   The total costs for the year were $59,791 for operation and care.
   Condition at end of fiscal year. The existing project was com-
pleted in 1937. The five dams originally built of timber have been
reconstructed of concrete. A concrete dam has been constructed
at Gull Lake. Three dikes at Winnibigoshish, 4 at Pokegama, 2 at
Sandy Lake, and 16 at Pine River have been constructed. Flowage
rights have been acquired on all lands affected by the construction,
maintenance, and operation of the reservoirs. Structures are in
fair condition except for aprons at three sites.

                                                       Previous projects             Existing projects
                                    Capacity at
                                     maximum                                                                   Total cost
           Reservoir                stage (cubic       Com-           Cost         Comrn         Cost
                                        feet)         pleted                       pleted
Winnibigoshish....                       -- 42, 163, 000, 000 1884
                                   _---.....                            $214, 000 1900    $173, 470 $387,470
Leech Lake..-------------32, 379, 000, 000 1884                          171, 805 1902      84, 380  256,185
Pokegama..------..........----------....     5, 260, 000, 000 1884        85, 000 1904     126, 030  211, 030
Sandy Lake--------------..................   3, 158, 000, 000 1895       114, 000 1909     117, 020  231, 020
Pine River----------.................-----   7, 733, 000, 000 1886        97, 000 1907     133,320   230,320
Gull Lake--------. -------- 3, 085, 000,000--------------                         1913
                                                             ..........-----............-   86, 826   86, 826
                                                                                           160,939   160, 939
Surveys and flowage rights...............-------------------------------...............................
       Total, new work---------------------                          681,805 ..        ....       881,985          1,563, 790
Total operating and care--------------------------100,857 ----------            .      ..         825, 466           926,323
Permanent indefinite appro-
  priation for operating and
  care, Feb. 1, 1895, to end of
  fiscal year 1936.......-------...----------------...--..-------.......------------......        967, 197              967, 167

      Total--------------93, 778, 000, 000----------
                                          ..........                   782, 662   ----------    2, 674, 648       3, 457, 310



   The total costs under the existing project to June 30, 1954, were
$1,707,452, being $881,985 for new work and $825,466 for oper-
ating and care. In addition, the sum of $967,197 was expended
between February 1, 1895, and June 30, 1936, on the operation and
care of the works of improvement under the provisions of the per-
manent indefinite appropriation for such purposes.
               RIVERS AND HARBORS--ST. PAUL, MINN., DISTRICT                                                         767
                                                      Cost and financial summary

                                                             Fiscal year ending June 30                     Total to June
                                                                                                          30, 1954,1 includ-
                                                                                                          ing fiscal years
                                               1950        1951         1952        1953       1954         prior to 1950
New work:
   Appropriated_                     --                           --                            --              $1, 563, 790
   Cost .   --------------------------------                                                                      1,563,790
Maintenance:$,
   Appropriated_...._ _                    $292, 000     -$98, 300      $37, 000    $71, 100   $54, 000          1, 906, 030
   Cost_-----......   ._                    164, 216         62, 996     76, 894     66, 112    59, 791          1,893, 521

   Includes $681,805 for new work and $100,857 for maintenance from previous project.


                                          5. MINNESOTA RIVER, MINN.
   Location. This river rises in Big Stone Lake, Minn. and S.
Dak., and flows southeasterly about 224 miles to Mankato, Minn.,
thence northeasterly about 106 miles to join the Mississippi River
opposite St. Paul, Minn. (For general location, see U. S. Geological
Survey map of Minnesota.)
   Previous projects. The original project was adopted by the
River and Harbor Act of March 2, 1867, and modified by the River
and Harbor Acts of August 11, 1888, and July 13, 1892. For fur-
ther details, see page 1890 of Annual Report for 1915, and page
1105 of Annual Report for 1938.
   Existing project. This provides for open-channel improvement
from the Mississippi River to Shakopee (25.6 miles) to obtain a
channel with 4 feet of water from the Mississippi River to Shako-
pee, which will accommodate vessels of 3-foot draft.
   The cost for new work for the completed project was $12,730,
exclusive of amounts expended on previous projects. The latest
 (1954) approved estimate for annual cost of maintenance is $2,500.
The existing project was adopted by the River and Harbor Act of
July 13, 1892 (p. 2209 of the Annual Report for 1891). The latest
published map will be found on page 1574 of the Annual Report for
1888.
   Local cooperation. None required under the existing project.
   Local interests on March 27, 1942, requested that the section of
the channel between the mouth and Savage, Minn., mile 13.2, be
dredged to a depth of 9 feet, and the Secretary of War under au-
thority contained in section 4 of the River and Harbor Act ap-
proved March 4, 1915, authorized acceptance of a total of $139,-
670.91 as local contribution to defray costs of dredging in excess
of the authorized 4-foot project depth.
   Terminal facilities. At Port Cargill, mile 13.1, Cargill, Inc.,
owns and operates a launching ways, a dock 650 feet in length with
warehouse adjacent, with additional mooring space 1,300 feet in
length and has facilities for loading grain and vegetable oils and
receipt of coal. Northern States Power Co. is operating a terminal
for the receipt of coal on the left bank at mile 9.0.
   Operations and results during fiscal year. Condition surveys
and snagging were carried on by hired labor at a cost for the
year of $1,905.




      Sig 25--767-798
76$                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

      Condition at           end of fiscal year.              The existing project was com-
pleted in 1931. Additional channel dredging (see "Local coopera-
tion"), completed in July 1943, provides: A channel with minimum
depth of 9 feet and a width of 100 feet from the mouth to Port
Cargill, mile 13.1, except that the 9-foot depth is restricted to a
width of 74 feet at the Chicago, Milwaukee, St. Paul & Pacific Rail-
road bridge mile 1.6; and a launching basin at Port Cargill, near
Savage, Minn., with depths up to 20 feet. Depths in this reach
greater than project depth are not dependable. Navigation was
practicable from Port Cargill, mile 13.1, to Shakopee for drafts not
in excess of 3 feet. The total costs and expenditures under the
existing project to June 30, 1954, were $92,688, being $12,731 for
new work and $79,957 for maintenance. In addition, the cost and
expenditure from contributed funds was $139,671 for new work
dredging to a depth of 9 feet, under the provisions of section 4 of
the River and Harbor Act of March 4, 1915.
                                         Cost and financial summary

                                               Fiscal year ending June 30                                    Total to June
                                                                                                           30, 1954,1 includ-
                                                                                                           ing fiscal years
                                  1950        1951          1952             1953          1954              prior to 19502

New work:
      Appropriated.                                                                    --------       --              130, 273
                                                                                                                     $-----
      Cost.-----------       --------         -------    -----------------             ---------                      130, 273
Maintenance:
      Apprppriated       -         $4, 000   -$3,856 -__----_--              $3, 400        $2, 500                     81, 080
      Cost------------       --     1,263       2, 063 ......---..            2, 873         1,905                      79,958

  1 Includes $117,542 for new work for previous project.
  2 In addition $139,671 for new work was expended from contributed funds.

                         6. ST. CROIX RIVER, WIS. AND MINN.
   Location. The source of the river is in northwestern Wiscon-
sin. It is about 164 miles long and for its greater part forms the
boundary between Wisconsin and Minnesota. It flows southwest-
erly and then southerly into the Mississippi River at Prescott, Wis.,
41.7 miles below the Northern Pacific Railway bridge, Minneapolis,
Minn. The portion included in this improvement extends from the
mouth to Taylors Falls, Minn., a distance of 51.8 miles. (See U. S.
Geological Survey map of Minnesota, scale 1:500,000, for general
location.)
  Existing project. This provides for the maintenance of a chan-
nel, 9 feet in depth and of suitable width from the mouth to Still-
water, Minn., 24.5 miles, created by the improvement of the upper
Mississippi River; a channel 3 feet deep at mean low water, be-
tween Stillwater and Taylors Falls (27.3 miles) ; improvement of
the ihrbor and water front at 'StilIwater; and a small boat harbor
at Hudson, Wisconsin.
                                                           $256,000.
   The estimate of cost of new work, revised in 1954, is
   Tie ,latest (1954) approved estimate for annual cost of inainte-
nance for that portion of the project between the mouth an Still-
wateris $10,000. The latest autho'ization (1954) for maiitea ice
work on the reach between Stillwater and Taylors Falls is limited
to an expenditure of not to exceed $5,000 per year.
                RIVERS AND HARBORS-ST. PAUL, MINN., DISTRICT                                      769
  The existing project was authorized by the following River and
Harbor Acts:

     Acts                         Work authorized                                Documents
June 18, 1878    Dredging, etc., for a 3-foot channel between the     H. Ex. Doc. 75, pt. 6, 43d Cong.,
                   mouth and Taylors Falls.                             2d sess.; Annual Report 1875,
                                                                           372.
                                                                        p. 372.
June 3,1896      Harbor and waterfront at Stillwater_ _
Jan. 21, 1927    A 6-foot channel to Stillwater    -------------------H. Doc. 378, 69th Cong., 1st sess.
Aug. 30, 1935    The 9-foot channel from the mouth to Stillwater .    H. Doc. 184, 72d Cong., 1st sess.
May 17,1950      Small-boat harbor at Hudson    .------------------- H. Doc. 184, 81st Cong., 1st sess.



   The latest published map is in House Document 462, 71st Con-
gress, 2d session.
   Local cooperation. Local interests for Hudson Harbor are re-
quired to give assurances satisfactory to the Secretary of the Army
that they will: (1) provide, without cost to the United States, all
lands, easements, and rights-of-way necessary for construction of
the project and subsequent maintenance, when and as required;
 (2) hold and save the United States free from damages due to the
construction of the project; (3) provide and maintain, without cost
to the United States, access roads, parking and storage areas, moor-
ing facilities, and utilities, including a public landing with suitable
supply facilities, open to all on equal terms; and (4) establish a
competent and properly constituted public body empowered to
regulate the use, growth, and free development of the harbor
facilities with the understanding that such facilities shall be open
to all. on equal terms. Local interests have not been formally re-
quested to furnish assurances.
   Terminal facilities. At Stillwater there is a concrete paved
levee, 550 feet long and 40 feet wide, sloping from the top of the
riverbank to the water. There is also a piling and timber trestle
wharf on the right bank, of which 276 feet is dock and 96 feet ap-
proach. At other points along the river, landing may be made on
the banks. Facilities are considered adequate for existing com-
merce.
   Operations and results during fiscal year. Dredging was ac-
complished at miles 6.4 and 16.7 and condition surveys and mis-
cellaneous inspections and reports: were carried on, all by hired
labor at a cost of $27,530.
   Conditionat end of fiscal year. All new work was completed in
1930 except the authorized harbor at Hudson. The extension to
provide a 9-foot channel from the mouth to Stillwater was com-
pleted on August 12, 1938, when full pool at dam No. 3 of the Mis-
sissippi River canalization project was reached. The minimum
draft from Stillwater to Taylors Falls is about 1 foot at extreme
low water; from mouth to Stillwater, 9 feet. The total costs to
June 30, 1954, were $339,020, being $150,410 for new work and
$188,611 for maintenance.
770                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                               Cost and financial summary

                                                          Fiscal year ending June 30                                                Total to June
                                                                                                                                   30, 1954, includ-
                                                                                                                                   ing fiscal years
                                        1950            1951               1952                  1953                 1954           prior to 1950
New work:
     Appropriated-               - _               _                 -          -          --               ----                           $150, 410
     Cost- _-                      --                                                        -          -                                   150, 410
Maintenance:
   Appropriated ---           _-_        $9, 100         $3, 186     -                           $3, 600              $26, 000              188, 640
   C ost.                                 7, 283          5,003          -_.        ...-          2, 041               27, 530              188, 611



                              7. INACTIVE NAVIGATION                                         PROJECTS

                                                                     For last          Cost and expenditures to                       Estimated
                                                                   full report,              June 30, 1954                             amount
                                                                        see                                                            required
                     Name of project                                 Annual                                                               to
                                                                     Report                  Con-                   Operation         complete
                                                                       for-                struction                   and
                                                                                                                   maintenance
1. Mississippi and Leech Rivers, Minn.'-_-               .....           1929                $277, 615                  $40, 251     Completed.
2. Red River of the North, Minn. and N. Dak._                    2       1921                 293, 344                   76, 209
3. Mississippi River between Brainerd and                                1925                  47, 794                    3, 891
     Grand Rapids, Minn.'
4. Lake Traverse, Minn. and S. Dak.' 4
5. Red L ake and Red La k e Riv er, M inn.'
6. Wisconsin River, 7 Wis.' - -6--.........----
                                                         -_-
                                                          -   _-
                                  - -- - - - - - - - - - - - - -
                                                                         1921
                                                                         1923
                                                                         1888
                                                                         1950
                                                                                                      92
                                                                                                  9, 070
                                                                                                 67, 585
                                                                                                               - --    ----------
                                                                                                                         -                  $10, 400
7. Black River Wis. .............                                                                                            -
8. Zippel Bay arbor, Minn.-               --------------                 1928                    27, 900                 11, 139             67, 100

   1No commerce reported.
   2 Abandonment recommended in 1915 (H. Doc. 1666, 63d Cong., 3d sess.) and June 24, 1926 (H. Doc. 467,
69th Cong., 1st sess.
   'Abandonment recommended June 24, 1926 (H. Doc. 467, 69th Cong., 1st sess.)
   ' Abandonment recommended in 1915 (H. Doc. 439, 64th Cong., 1st sess.) and June 24, 1926, (H. Doe. 467,
69th Cong., 1st sess).
   s Originally included in project "Fox and Wisconsin Rivers, Wis." Abandonment of improvement of
Wisconsin River by channel contraction works recommended in 1886-87 (H. Ex. Doc. 65, 49th Cong., 2d
sess.).
   6 Expenditures included under project "Fox and Wisconsin Rivers, Wis." No breakdown available.
   ?Channel adequate for existing commerce.

8. RED RIVER OF THE NORTH DRAINAGE BASIN, MINN., S. DAK.,
                      AND N. DAK.
   Location. The Red River of the North Basin, within the United
States, includes the northeastern corner of South Dakota and much
of eastern North Dakota and northwestern Minnesota. The Red
River of the North, formed by the confluence of the Otter Tail and
Bois de Sioux Rivers, flows northward through this region, forming
the boundary between North Dakota and Minnesota. (For general
location of the basin, see the U. S. Geological Survey maps of the
States of Minnesota and North Dakota.)
   Previous projects. Other flood control projects on tributaries
                     FLOOD CONTROL-ST. PAUL, MINN., DISTRICT                                               771
of the Red River of the North, coordinated with but not a part of
this project, are as follows:

                         Name of project                             Authorization                Status

Lake Traverse and Bois de Sioux River, S. Dak. and Minn_ Flood Control Act                 Placed in operation
                                                           approved June 22,                 in 1942.1
                                                           1936.
Lake Ashtabula and Baldhill Dam, Sheyenne River, N. Dak Flood Control Act                  Placed in operation
                                                           approved Dec. 22,                 in 1951.1
                                                           1944.
Red Lake River, Minn., including Clearwater River, Minn_     do-       ---                 Substantially
                                                                                                    1     com-
                                                                                             pleted.
Homme Reservoir and Dam (Park River), N. Dak .......            __do-                      Placed in operation
                                                                                             in 1951.1
Pembina River Reservoir, N. Dak___________                            ddo----   - --...    Planning suspended.
Tongue River Reservoir, N. Dak ...                                     do                      Do.

  1   Complete report on these projects may be found elsewhere in the report of this district.

  Improvements for navigation in the basin were authorized by
the following River and Harbor Acts:

       Acts                         Work authorized                                     Documents
Aug. 14, 1867     Dredging and removal of obstructions in the Red           Inactive,. Abandonment recom-
                    River of the North from Breckenridge, Minn., to           mended in 1915 (H. D. 1666-63-3)
                   the international boundary.                                and June 24, 1926 (H. D. 467-69-
                                                                              1).   For last full report, see
                                                                              Annual Report for 1923.
June     3,1896   Amends above act to include improvements on Red           Inactive. For last full report, see
                    Lake River between Red Lake and Thief River               Annual Report for 1923.
                    Falls, Minn.
July 25, 1912     Improvement of Lake Traverse by construction of a         Never undertaken. Abandonment
                    channel between the upper and lower basins.              recommended in 1915 (H. D. 439-
                                                                             64-1) and June 24, 1926 (H. D.
                                                                             467-69-1). For last full report, see
                                                                             Annual Report for 1921.



  Existing project. The project includes improvements for local
protection in the interest of flood control and major drainage to be
accomplished by channel improvement, levees, etc., in addition to
the construction of a multiple purpose reservoir on Otter Tail River
to control floods and, in conjunction with the previously authorized
Federal reservoir projects at Baldhill site of the Sheyenne River
and at Red Lake, to increase low flows for water supply and pollu-
tion abatement. The units in the comprehensive basin plan are as
follows:
772                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                                                                                              Total esti-
                 Name of unit                                       State                               Type                    mated
                                                                                                                              (1954) Fed-
                                                                                                                                eral cost

Orwell Reservoir (Otter Tail River) ... Minnesota_                                        Reservoir                      ----
                                                                                                                  ...--------   I $1, 889, 000
Sheyenne River....             ..-------------------     North Dakota .........           Channel improvement__                     ,934, 000
Wild Rice and Marsh Rivers .                   _-----Minnesota                      _   _     do --        __--------       -         424, 000
Rush River .... _ ..........      -            ....... North Dakota ----... .........         do-         - -- -                      598, 000
Sand Hill River...------------------- Minnesota ....... _                             -   --- do------------------                    772, 000
Mustinka River- ..............
Maple River.---------- _-----.....
                                                      ..... do  -----------
                                                         North Dakota_ --
                                                                                           -- do ------------------
                                                                                              do
                                                                                                                                      439, 000
                                                                                                                                   1, 260, 000
O tter Tail River-         -         - _             _ M innesota -------------.....          do        _                             170, 000
Bois de Sioux and Red Rivers at Wah- Minnesota and North ..... do                                    --        ------- -....-        624, 000
  peton-Breckenridge.                                       Dakota.
Red River at Grand Forks-East Grand                       -_ .do---------------           Levees and floodwall                .- 2, 340, 000
  Forks.
Red River at Fargo-Moorhead --                                       -         -
                                                              do--.................       Channel improvement2,2, 750, 000
                                                                                              levees.
        Total estimated cost                                                                                    -      ----     12 200, 000


  'Includes $182,000 for lands. Estimated (1954) annual cost of maintenance                                 (operating and care) for
this unit is $8,800.


   The project was authorized by the Flood Control Act approved
June 30, 1948, which authorized the appropriation of funds for the
partial accomplishment of the plan. The Flood Control Act of 1950
authorized completion of the plan. The latest published map is in
the project document (H. Doc. 185, 81st Cong., 1st sess.).
   Local cooperation. The improvements, with the exception of
the proposed Orwell Reservoir on the Otter Tail River, are subject
to the conditions that local interests will (1) provide, without cost
to the United States, all lands, easements, rights-of-way, and spoil
disposal areas necessary for the construction and subsequent main-
tenance of the project, when and as required; (2) hold and save
the United States free from damages due to the construction and
subsequent maintenance of those works; (3) maintain the channels
after completion in accordance with regulations prescribed by the
Secretary of the Army; and (4) make at their own expense all nec-
essary changes to utilities, highways, and bridges, including ap-
proaches. No local cooperation is required in connection with the
proposed reservoir on the Otter Tail River.
   Immediately following authorization of the basin project, local
interests from the entire basin signified their desire that construc-
tion of Orwell Reservoir be given first priority. At a subsequent
meeting of the Tri-State Waters Commission with representatives
from the three States involved and local interests, a priority was
established for the local flood-protection units authorized in the
basin project. Actual priority has depended largely upon ability
of local interests to fulfill local cooperation requirements.
   Local interests for the Otter Tail and Rush River units were for-
mally requested to furnish assurances on August 7, 1950, and
January 26, 1954, respectively. Local interests for other units
have not been formally advised in writing of the requirements of
local cooperation. However, assurances have been furnished as
            FLOOD CONTROL-ST. PAUL, MNN,      DISTRICT          773
follows with dates of approval indicated: Wild Rice-Marsh, De-
cember 30, 1949; Mustinka, June 16, 1950; Sand Hill, January 9,
1950; Otter Tail, October 27, 1950; and Grand Forks, July 23, 1953.
Those for the Rush have been submitted for approval. Local in-
terests at East Grand Forks state that they are unable to furnish
assurances at this time. Lands required for construction on the
Wild Rice, Marsh, Otter Tail and Mustinka Rivers and at Grand
Forks have been furnished. Those on the Rush have been acquired
by local interests and rights-of-entry will be furnished the Govern-
ment after approval of assurances.
   The completed Wild Rice River improvements were formally
transferred to local interests effective on August 1, 1952.
   Operations and results during fiscal year. Advance planning
was carried on for the Sand Hill and Rush Rivers and Grand Forks
improvements. Detailed planning was continued for Fargo-Moor-
head improvements. Miscellaneous designs and public contacts
were carried on for other units. Work leading to final action on
acquisition of lands for Orwell Reservoir was continued. Contracts
for channel improvements on the Marsh and Otter Tail Rivers were
completed. The contract for bulkheads at Orwell Dam was con-
tinued. Contracts were awarded for Mustinka River and Grand
Forks improvements and were brought to 21 percent and 14 percent
completion, respectively. A relocation agreement was consum-
mated with the Chicago, Milwaukee, St. Paul and Pacific Railroad
for its bridge over the Mustinka River, and alterations have been
completed.
   According to plan the Orwell pool was in the process of being
lowered at the beginning of the fiscal year. The pool continued to
be drawn down during July, reading 1047.5 by the 28th where it
was held until the end of August. Excessive rainfall occurred in
the upper lake region the last 4 or 5 days of August resulting in an
inflow into the Reservoir averaging 500-600 second-feet lasting
through November. The outflow was regulated to provide protec-
tion to Wahpeton causing the pool to reach elevation 1053.5 by the
6th of September. On September 18, the outflow was adjusted to
allow the pool to fill before the freezeup. Full pool (elevation
1070.0) was reached by October 26, 1953, and was held throughout
November. Beginning about December 1, 1953, the outflow was
adjusted to draw the pool down to elevation 1048.0 prior to the
spring breakup. The drawdown was accomplished by March 15,
1954. :Inflow increased about this time and on four separate occa-
sions before the end of the fiscal year, runoff was stored in the
reservoir to prevent damages downstream, especially at Wahpeton,
North Dakota. The final rise was caused by heavy rainfall during
the period May 31 to June 19, 1954, and resulted in the highest
stage (elevation 1059.74 on June 16) reached in the pool following
the breakup. By the end of the fiscal year, the pool had been drawn
down to elevation 1050.0, 2 feet above minimum pool elevation.
   Costs for new work for the fiscal year were as follows:
774            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


                                           Unit                                                                   Costs
O rwell R eservoir- ------
                        . . -. -. . . . . . . . - . ........     .......   .......   ........                        $68, 220
Sheyenne R iver ... - - - - - - - - - - - - - - - - - - - - - - - --                                      -   -
W ild Rice and Marsh Rivers        -.----
                                      ---- ---- ---- ---                  --- ----       --
                                                                                          ----------------           107, 999
R ush R iver -----------------------------------       ----......... . . .--.             ---- - -                     4, 419
Sand Hill River .-.    .     .  . .    .   .   .   ..                                     -                           21, 808
Mustinka River ----------------
                         _                                                                       ------               84, 453
Maple River - -                                                                                           .               672
                                                                                                                          672---------------
Otter Tail River- -                                                                                       -           90, 504
Wahpeton-Breckenridge----------------------------------------------                      -                                201
Grand Forks-East Grand Forks      -..............................          .                 .                       112, 063
Fargo-Moorhead.----------------- .-----------
                                        - -                       - - - --                                -           29, 769
      Total Red River of the North                                                                                   520, 108



   Cost of work by classes: Advanced planning, including designs,
$122,253; land acquisition, $5,427; construction of channel im-
provements, $275,145; levees and interior drainage, $62,800; re-
locations, $1,126; other, $53,357. Costs by hired labor, $125,185;
by contract, $394,923. In addition, costs for operation and main-
tenance of Orwell Dam were $17,549. Total costs for the year were
$537,657.
   Condition at end of fiscal year. Detailed plans for Orwell, Wild
Rice-Marsh, Sheyenne, Mustinka, Rush, Sand Hill, Otter Tail, and
Grand Forks-East Grand Forks features have been completed, and
are 96 percent and 50 percent complete, respectively, for Fargo-
Moorhead and Wahpeton-Breckenridge features. Designs have
been completed for Orwell Dam, Wild Rice-Marsh, Otter Tail, Mus-
tinka, and Grand Forks features, and are in progress for the Rush
and Sand Hill portions of the project. A total of 1,985 acres of land
has been acquired. Channel improvement on the Wild Rice River
was started in August 1950 and completed in July 1952. The Or-
well Reservoir feature was initiated in May 1951 and was sub-
stantially completed in June 1953. Closure of the dam was made
in August 1952 and the dam was placed in operation in the spring
of 1953. Channel improvements on the Otter Tail River were
initiated in January 1953 and were completed in June 1954. Con-
tracts for Marsh River channel improvements were initiated in
October 1953 and completed in June 1954. The project as a whole
is 28 percent complete.
   Work remaining to complete the project includes completion of
minor work at Orwell, and improvements on Sand Hill, Rush,
Sheyenne, and Maple Rivers, and at East Grand Forks, Fargo-
Moorhead, and Wahpeton-Breckenridge, as well as completion of
contracts in progress.
                         FLOOD CONTROL--ST. PAUL, MINN., DISTRICT                                                                       775
     Total costs to June 30, 1954, for new work are as follows;
                                                            Unit                                                                 Costs
Orwell Reservoir ...................................                                                                             $1, 869, 757
                                                                                                         ..-----------------------------------------------------.
Sheyenne River--------- ------------              ------------------              -------------           -------                    31, 613
Wild Rice-Marsh Rivers                   .......                       .....-------------------------------------------------------400, 949
Rush River -...                                                                                                                      25, 135
                                                                                                           ...-------------------------------------------------------
Sand Hill River                                       .... ...---------------------------------------------------------------        64, 582
Mustinka River...------           --------------------------------------------------------                                          154, 059
Maple River ---             ----------------------------------. -------------                   -------------------                    1, 054
Otter Tail River _..----..-- -     --------------------------------------------..------.                                            168, 496
Wahpeton-Breckenridge           ---------------------       ------------------------------------                                       9, 240
Grand Forks-East Grand Forks-------------------------------------------                                          ...                223, 941
F ar go- M oor h ead . . ..                      .          ... ....                      _.             .                           80 , 9 2 7

        Total Red River of the North                   ----------------------------------------------
                                                       .............                                                                3, 029, 753


  Costs to June 30, 1954, for operation and maintenance of Orwell
Dam are $26,197. Total costs for the project to date are $3,055,950.
                                                 Cost and financial summary

                                                                Fiscal year ending June 30                                  Total to June
                                                                                                                           30, 1954, includ-
                                                                                                                           ing fiscal years
                                         1950                1951              1952          1953              1954          priorto 1950


New work:
   Appropriated _.._ _               $1,547,898        -_                     $700, 000     $622, 000      1$455, 000           1 $3, 521,100
   Cost.       -                        190, 257            $335, 787        1,031, 164      828,905         520, 108              3,029, 753
Maintenance:
   Appropriated    _                                                -_                          9,450           16,900                  26, 350
   Cost_ --..                                                            .    ----------        8,648           17,549                  26,197

   I Exclusive of     $265,000 loan returned to Aitkin project.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954__                $280,975
    Appropriated for succeeding fiscal year ending June 30, 1955------ -300,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955_                                      -                      580,975
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project_             -                             6,805,700

9. RED LAKE                     RIVER, MINN., INCLUDING                                        CLEARWATER                        RIVER,
                                              MINN.
   Location. The works covered by this project lie along the upper
reach of the Red Lake River and also along the Clearwater River,
a tributary of the Red Lake River, between a point near Plummer,
Minn., and a point just above the mouth of Ruffy Brook. Red Lake
River, the principal tributary of the Red River of the North, has
its source at the outlet of Lower Red Lake in the northwestern por-
tion of Minnesota and has a total length of about 196 river miles.
It flows in a westerly direction to its junction with the Red River
of the North at East Grand Forks, Minn. The meandering length
of the Clearwater River in its general westerly course from its
source near Ebro, Minn., to its junction with the Red Lake River at
Red Lake Falls, Minn., is about 205 miles. (For general location,
see U. S. Geological Survey map of Minnesota.)
   Existing project. The following features are included in the
plan of improvement: Rectification and enlargement of 27.5 miles
of the channel of the Red Lake River so as to provide sufficient
channel capacity throughout the reach between river mile 154.3
near High Landing, Minn., and a point 4.5 miles east of the west
776      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

boundary of the Indian Reservation, and the reach from the ioutlet
of Lower Red Lake to a point 3.2 miles westerly thereof; modifica-
tion of the existing stop-log structure, which was constructed at
the outlet of Lower Red Lake by the Indian Service, so as to provide
for the installation of three hand operated lift gates, and one stop-
log bay; raising 6.9 miles of highway at west end of Lower Red
Lake to prevent overtopping; and rectification, clearing, and en-
largement of 47.3 miles of the channel of the Clearwater River so
as to provide sufficient channel capacity between river mile 31.8 at
Plummer, Minn., and mile 79.1 upstream from the mouth of Ruffy
Brook. The channel improvements eliminate a large percentage
of the flood damages resulting from overflow of the rivers and pro-
vide adequate channels in Red Lake and Clearwater Rivers to carry
the discharge from drainage ditches. Modification of the existing
control works at the outlet of Lower Red Lake provides for a dis-
charge capacity of 1,000 cubic feet per second through the struc-
ture when the lake is at normal elevation (1,174) and will insure
the release of sufficient water to provide water supply and pollution
abatement benefits to municipalities along Red Lake River, and
along the Red River of the North below the mouth of Red Lake
River.
   The estimated cost to the United States for new work, revised in
1954, is $2,786,000. The approved (1954) estimated annual cost to
the United States for maintenance is $10,000.
   The project was authorized by the Flood Control Act approved
December 22, 1944 (H. Doc. 345, 78th Cong., 1st sess.). The latest
published map is contained in the project document.
   Local cooperation. The improvement is subject to the condi-
tions that responsible local interests give assurances satisfactory
to the Secretary of the Army that they will, without cost to the
United States, provide all flowage easements and rights-of-way;
hold and save the United States free from damages due to the con-
struction works and operation; make a cash contribution of $33,220
in lieu of altering bridges; take over the maintenance and subse-
quent replacement of all bridges improved by the United States;
maintain the improved river channels; control the contamination
by rural areas and villages without sewer systems of Red Lake,
Clearwater, and Thief Rivers; require that municipalities which
discharge sewage into Red Lake, Clearwater, or Thief River treat
their sewage before discharge into the streams so as to effect a
reduction in the biochemical oxygen demand of not less than 85
percent for towns of 1,000 population or greater and of 35 percent
for municipalities having a population of less than 1,000; and pre-
vent the construction of any new dams or the raising of any exist-
ing dams in Red Lake, Clearwater, or Thief Rivers downstream
from Lower Red Lake, Clearwater Lake, or Mud Lake unless au-
thorized by the Department of the Army.
   An existing drainage district reorganized by order of court has
voluntarily furnished all assurances except those on pollution which
were furnished by the Minnesota Water Pollution Control Com-
mission. All of these assurances were accepted October 3, 1947. A
contribution of $33,220 was received from local interests in July
1948, however, alteration of the River Valley Bridge was performed
            FLOOD CONTROL-ST. PAUL, MINN., DISTRICT              777
by local interests and $3,200 was refunded to them in July 1953
for that work.
   All rights-of-way and easements outside the Indian reservation
have been acquired by the Red Lake Drainage and Conservancy
District as local agency, and permit to the Government for con-
struction has been granted.
   On October 22, 1947, the Red Lake Indian Council adopted a
resolution authorizing the Office of Indian Affairs, Interior De-
partment, to carry out necessary transfer of authority to the
Department of the Army. The Indian Council passed another
resolution on October 28, 1948, which indicated the council's desire
for preservation of marsh areas within the reservation. Upon
further study, the council on April 17, 1949, revised their resolu-
tion of October 28, 1948, in favor of a modified plan within the
reservation. On December 2, 1949, the Acting Secretary of the
Interior authorized construction work along the Red Lake River
right-of-way within the reservation, subject to certain conditions
and subject to formal application for necessary easements and
rights-of-way.    Formal application was forwarded to the Secre-
tary of the Interior on February 10, 1950. As it was construed by
the Acting Secretary of the Interior that existing resolutions did
not cover the Clearwater River, a new resolution dated February
19, 1950, was secured from the Tribal Council specifically including
work along the Clearwater River.
   All completed portions of the projects except the outlet struc-
ture, the control structures on Butcher Knife Creek, and the weir
on the Red Lake River within the Indian Reservation have been
formally transferred to local interests, and the transferred portions
were accepted on March 29, 1954.
   Operations and results during fiscal year. Design was contin-
ued by hired labor. A contract for stage 3 channel improvement
on the Clearwater River was completed. A contract for snagging
and clearing from the lower end of the channel excavation to
Plummer, Minn. on the Clearwater River was awarded but work
has not been initiated. Some minor work was accomplished by
hired labor. Excavation under the River Valley bridge was accom-
plished by contract and alteration of the structure was completed
by local interests.
   At the beginning of the fiscal year, Red Lake was at normal
elevation, 1174.0. Only small fluctuations in stages occurred
throughout the entire fiscal year. The low stage, elevation 1173.3,
occurred during November 1953; the high stage, elevation 1174.70,
occurred June 18, 1954. Little difficulty was encountered down-
stream inasmuch as discharges were regulated in the range from
175 to 500 second-feet throughout the entire year.
   Costs for the year for new work were $13,076, United States
funds as follows: Design, engineering, etc., $5,656; channel im-
provements, $11,754; other construction, -$4,334.       Cost by hired
labor, $9,818; by contract, $3,258. Costs for the year for operation
and care were $6,461. Total costs for the fiscal year were $19,537.
   Condition at end of fiscal year. Detailed plans and flowage
surveys are completed; plans and specifications are substantially
completed. Construction was initiated in February 1948, on the
778                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Red Lake River, and in October 1948, on the Clearwater River. All
channel improvement on the Red Lake River and all excavation on
the Clearwater River have been completed. About 6,576,700 cubic
yards of material have been removed under the seven contracts
embracing this work. The project was substantially completed in
June 1953, only minor work remaining to be done. Operation of
the Red Lake Dam was taken over by the Department of the Army
from the Department of the Interior, Office of Indian Affairs, on
April 1, 1951. Channels are in good condition and have indicated
the effectiveness of the project. Project as a whole is 99 percent
complete.
  Total cost of new work for the project to June 30, 1954, was $2,-
779,260, of which $2,749,240 were Federal funds and $30,020 were
contributed funds. Cost of operation and care was $14,382. Total
costs were $2,793,642.
                                               Cost and financial summary
                                                   UNITED STATES FUNDS


                                                             Fiscal year ending June 30                    Total to June
                                                                                                          30, 1954, includ-
                                                                                                          ing fiscal years



New work:
   Appropriated------
                 ....                  $718, 400         $229, 100 -                           $40, 000         $2, 795,000
   Cost---------------                  579,252           546,192      $699,621   $280,077      13,076           2,749,240
Maintenance:
   Appropriated -------                   5,000           -2,000         2,120       4,000       6,100              15, 220
   Cost---..........--        --- --    ------.                  792     3,545       3,584       6,461              14,382


Other new work data: Unobligated balance, fiscal year ending June 30, 1954__ $35, 835
                                                   CONTRIBUTED FUNDS


                                                           Fiscal year ending June 30                      Total to June
                                                                                                          30, 1954, includ-
                                                                           195                            ing fiscal years
                                        1950              1951         1952        1953        1954         priorto 1950


New work:
   Appropriated---                                                                              $3,200             $30,020
   Cost                  -.            $20,682      --                            - $3,200     -- --30,020


                         10. HOMME             RESERVOIR                AND       DAM,       N. DAK.
   Location. The dam site is located on the South Branch of the
Park River, about 4 miles upstream from Park River, N. Dak., and
62.1 miles above the mouth of the Park River. South, Middle, and
North Branches, the headwater streams of the Park River, rise in
Cavalier County in northeastern North Dakota and flow in an
easterly direction to an almost common confluence near Grafton,
N. Dak., forming the main stream which flows easterly 35 miles to
join the Red River of the North about 35 miles south of the inter-
national boundary. (For general location, see U. S. Geological
Survey map of North Dakota.)
   Existing project. The following features are included in the
plan of improvement: An earthfill dam, having a height of about
67 feet above the streambed and a length of 865 feet; a 5-foot in-
side diameter concrete conduit under the dam, with control gates
located in tower at upstream end; and a spillway adjacent to the
dam with 150-foot crest at an elevation of 19 feet below the darn
             FLOOD CONTROL--ST. PAUL, MINN., DISTRICT            779
crest and a chute with a bottom width of 150 feet. Partial flood
control protection is afforded by the reservoir of 7,100 acre-feet
capacity which is created by the dam, and the reservoir storage
capacity of 3,650 acre-feet below spillway crest (1,080) is used to
provide a flow of about 5 second-feet in the river to meet the water
conservation needs in the reach from the dam to Grafton, N. Dak.
In addition, a 16-inch cast-iron pipe water supply outlet through
the dam has been provided at the request of local interests with
payment by them.
    The estimated cost to the United States for new work revised in
1954 is $1,339,000. The (1954) estimated annual cost of mainte-
nance is $9,500.
    The project was authorized as "Park River Reservoir" by the
Flood Control Act approved December 22, 1944 (S. Doc. 194, 78th
Cong., 2d sess.) and was redesignated "Homme Reservoir and
Dam" by Public Law 435, 80th Congress, 2d session, approved
March 5, 1948. The latest published map is contained in the proj-
ect document.
    Local cooperation. The improvement is subject to the condi-
tions that local interests make a cash contribution of $40,000
toward the construction cost, and give assurances satisfactory to
the Secretary of War that they will provide, without cost to the
United States, all lands, easements, and rights-of-way necessary
for the construction of the project; make necessary changes in
roads, bridges, and utilities; maintain the channel below the res-
ervoir; hold and save the United States free from damages due to
the construction works; limit future construction of dams below
the reservoir; and prevent the discharge of raw sewage into the
river by municipalities.
    Provisions of local cooperation have been complied with.
    Operation and results during fiscal year. Minor engineering
work was accomplished by hired labor. The structure was oper-
ated and necessary repairs were made by hired labor.
    At the beginning of the fiscal year, the pool was at elevation
1064.0, 16.0 feet below full pool elevation. In order to extend the
available storage for water supply at downstream points for as long
a period as possible, an outflow of 0.5 second-foot was maintained
until the latter part of August. At that time requests for addi-
tional water from downstream points resulted in increasing the
outflow to 3 second-feet which in turn was maintained until the
pool was filled to elevation 1080.0 on June 9, 1954. With a con-
tinued rise in stage, the overflow over the spillway caused a crest
discharge of about 200 second-feet on June 14. By the end of the
fiscal year, the pool had dropped to 1080.0 and the discharge to
about 3 second-feet.
   Costs for the year for new work were $3,031 for engineering by
hired labor. Costs of operation and maintenance for the year were
$9,171. Total costs for the year were $12,202.
   Condition at end of fiscal year. Design and construction of the
project are completed, except for remaining construction of public-
use facilities most of which has been deferred indefinitely. Con-
struction was initiated in April 1948, and major structures were
completed in May 1951. The project as a whole is 98 percent com-
780            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

plete. Structures are: in good condition.
  The total cost of new work for the project to June 30, 1954, was
$1,363,846, of which $1,307,626 were Federal funds and $56,220
were contributed funds. Cost of operation and maintenance was
$22,735. Total cost for all work was $1,386,581.
                                    Cost and financial summary

                                            Fiscal year ending June 30                   Total to June
                                                                                        30, 1954, includ-
                                                                                        ing fiscal years
                             1950         1951        1952         1953       1954        priorto 19501


New work:
   Appropriated -   -   -   $277, 902   -$55, 288     $77, 500 i                            2 $1, 339, 000
   Cost_---                  380,696      248, 175     98,797      $46, 462   $3, 031          1,307,  626
Maintenance:
   Appropriated .......      4, 500         31300       2, 400       3,800    11,200              25, 200
   Cost ..   . .         ..
                    ____________            2, 303      4,664        6,597     9,171              22, 735


Other new work data: Unobligated balance, fiscal year ending June 30, 1954_ 2 $31,386
1 In addition $56,220 for new work was expended from contributed funds.
2 Including $29,900 in OCE reserve.

11. LAKE ASHTABULA AND BALDHILL DAM, SHEYENNE                                               RIVER,
                       N. DAK.
   Location. The Baldhill Dam site is located on the Sheyenne
River, 16 miles upstream from Valley City, N. Dak., and about 271
miles above the mouth. The Sheyenne River rises in central North
Dakota and flows 500 miles generally southeast to enter the Red
River of the North about 10 miles north of Fargo, N. Dak. (For
general location, see U. S. Geological Survey map of North Dakota.)
   Existing project. The plan of improvement provides for the
construction of an earthfill dam, having a height of about 61 feet
above the streambed and a total length of 1,650 feet, with a con-
crete spillway-control section consisting of a concrete gravity ogee
section with overall length, including piers, of 140 feet. The crest
is at elevation 1,252 and is surmounted by three standard design
Tainter gates each 40 feet long and top elevation at 1,267. A gate-
controlled 3-foot diameter conduit has been provided in each of the
two center piers. The dam creates a reservoir of 70,700 acre-feet
capacity and controls the runoff from an effective drainage area of
1,988 square miles, thereby providing a substantial degree of flood
control to the cities, villages, and urban areas along the Sheyenne
River and providing substantial water supply and pollution abate-
ment for the section of the Sheyenne River below the dam and the
section of the Red River of the North below the mouth of the
Shevenne River. In order that a part of the regulated flow may be
available for water supply and pollution abatement in the Red
River of the North at Fargo, N. Dak., the plan also provides for the
construction of a low diversion dam in the Sheyenne River 35 miles
above the mouth, and a short ditch leading thence to the existing
Stanley ditch, the latter to be cleared and deepened to the Red
River of the North which it enters about 9 miles above Fargo.
   The estimated cost (1954) to the United States for new work is
$2,653,000. The estimated annual cost (1954) for maintenance is
$30.000 for operating and care of the Baldhill Dam.
  The project was authorized by the Flood Control Act approved
            FLOOD CONTROL-ST. PAUL, MINN., DISTRICT              781
December 22, 1944 (H. Doc. 193, 78th Cong., 2d sess.). The latest
published map is contained in the project document. The reservoir
above Baldhill Dam has been designated as Lake Ashtabula by
Public Law 772, 81st Congress, 2d session, approved September 8,
1950.
   Local cooperation. The improvement is subject to the condi-
tion that no funds shall be expended on construction of the project
until local interests have contributed $208,000 toward the first cost
of the reservoir and until responsible local agencies have given
assurances satisfactory to the Secretary of War that they will (1)
hold and save the United States free from damages due to the con-
struction works; (2) bear the expense of all necessary alterations
of utilities, roads, highways, and bridges; (3) construct, operate,
and maintain the Fargo diversion dam and diversion ditch im-
provements in accordance with plans and regulations to be ap-
proved by the Secretary of War; (4) maintain the channels below
the reservoir in satisfactory condition for the flow of water re-
leased from storage, to include the prevention of encroachments on
the carrying capacity of the channel- which would unduly interfere
with the conveyance of floodwater; and (5) establish and enforce
suitable regulations to prevent pollution of the waters of Sheyenne
River.
   Provisions of local cooperation have been complied with except
for construction of the Fargo diversion dam and ditch, assurances
for which, furnished by the city of Fargo, were approved by the
Secretary of War on June 26, 1947. Plans for this feature are sub-
stantially complete.
   Operations and results during fiscal year. Designs were car-
ried on by hired labor. Construction of gantry crane was com-
pleted by contract. Contracts for two stages of fencing and tree
planting in the reservoir area were in progress. A contract for
construction of an access road to a recreation area was awarded
and brought to 80 percent completion.
   Structures were operated as re.quired and necessary repairs made
by hired labor.
   The reservoir was full (elevation 1266.0) at the beginning of
the fiscal year. Inasmuch as normal weather conditions occurred,
operation according to plan was carried out throughout the year.
Except for the period August 1-16, 1953, when the discharge was
reduced to zero to facilitate repair work by the State of North
Dakota on a small dam downstream, a discharge of about 15 sec-
ond-feet was maintained until December 13, 1953, for water supply
and pollution abatement. On December 14, the discharge was
increased to 60 second-feet to provide storage for the spring runoff.
This discharge was maintained until spring breakup and resulted
in lowering the reservoir to elevation 1263.4, assuring ample
capacity for the small runoff anticipated. The reservoir was filled
to normal elevation (1266.0) on June 22 following heavy rains and
the outflow was increased to about 500 second-feet during the last
week in June 1954, thus maintaining a full reservoir. The reser-
vqir discharges include withdrawals, varying up to 5 second-feet,
by 'the U. S: Fish and Wildlife Service for operation of their fish-
Thring    ponds immediately below the dam. Reservoir levels main-
782            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

tained during the summer season were very satisfactory from the
recreational standpoint with the total fluctuation below full pool
being less than 0.7 foot.
   Costs for the year for new work were $23,733, being $5,783 for
designs and $17,950 for miscellaneous construction. Costs by con-
tract, $17,950; by hired labor, $5,783. Costs for the year for
operation and maintenance were $47,560. Total costs for the year
were $71,293.
   Condition at end of fiscal year. Preliminary planning, includ-
ing designs and master plan for public-use facilities, is substan-
tially complete. Land acquisition for the project, including acqui-
sition of 7,816.5 acres in fee and easements on 666.2 acres, has been
completed. Construction was initiated in July 1947 and major
features were completed in November 1950. The dam was placed
in emergency operation in April 1950 and in permanent operation
in the spring of 1951. Structures are in good condition.
   Completion of work presently under contract will complete the
project except for minor items and construction of additional
public-use facilities, which has been indefinitely deferred.
   Total costs of new work to June 30, 1954, were $2,834,732, being
$2,626,732 Federal funds and $208,000 contributed funds. Total
costs of operation and maintenance were $125,438. Total costs for
all work were $2,960,170.
                         Cost and f[nancial summnary

                                          Fiscal year ending June 30                    Total to June
                                                                                       30, 1954, includ-
                                                                                       ing fiscal years
                              1950       1951           1952       1953      1954        priorto 19501

New work:
   Appropriated. ... _ _     $310,000   $318, 650 -...         .         .                  $2,653, 150
   Cost..ce:        .    _    523,053    162, 741      $144, 532   $67,746   $23,733         2,626, 732
Maintenance:
   Appropriated ----- __        5.500     35, 350        17, 200    20,650    46,900            125,600
   Cost -----------------         338     35,563         21,210     20,767    47,560            125,438

1In addition $208,000 for new work was expended from contributed funds.
Other new work data: Unobligated balance, fiscal year ending June 30,
  1954 ______
           _                                                          $13,298. 17

12. LAKE TRAVERSE AND BOIS DE SIOUX RIVERS, S. DAK. AND
                        MINN.

   Location. The works covered by this project lie along Lake
Traverse and Bois de Sioux River between the upper end of Lake
Traverse at Browns Valley, Minn., and the mouth of Bois de Sioux
River at Breckenridge, Minn. The lake drains through the river
to the Red River of the North, and the two waters form a portion
of the boundary between the State of Minnesota and the States of
North and South Dakota. For general location, see United States
Geological Survey map of Minnesota.
   Existing project. The plan of improvement provides for use of
Lake Traverse as a flood control and water conservation reservoir
and for channel improvement in the river below the lake. It in-
cludes construction of a dam near White Rock, S. Dak., at the north
end of Lake Traverse, a structure at the Reservation Highway
            FLOOD CONTROL--ST. PAUL, MINN., DISTRICT            783
crossing for control of the upper section of the reservoir, levees,
and embankments necessary near Browns Valley, Minn., and chan-
nel improvement of approximately 24 miles of the Bois de Sioux
River from the outlet of Lake Traverse northward toward Breck-
enridge, Minn. The dam near White Rock, S. Dak., consists of a
control section with concrete abutments, piers, and stilling basin
and 3 Tainter gates, each 13 feet wide by 16 feet deep between two
sections of rolled-fill embankment with a total length of approxi-
mately 14,550 feet from high ground on the Minnesota side to high
ground on the South Dakota side. This dam supplemented by
channel improvement of the Bois de Sioux River downstream and
an embankment approximately 5,000 feet long at the south end of
Lake Traverse for the protection of Browns Valley, Minn., consti-
tutes the flood control feature of the project. The structure at
Reservation Highway crossing consists of a stone-paved dike spill-
way with superimposed stop-log spans with total length of approxi-
mately 113 feet between steel-sheet pile abutment walls behind
which compacted fill with soil-cement slab pavement connects with
the existing highway, and is operated to maintain the water level
in the upper section of the lake. The project, with reservoir ca-
pacity for flood control of 137,000 acre-feet, affords protection to
about 42,000 acres of agricultural land from floods up to those
which may be expected to occur once in 30 years and should restore
Lake Traverse to its former natural condition as a habitat for an
abundance of wildlife and fish.
   The cost of the completed project was $1,332,200. The latest
 (1954) approved estimate of annual cost of maintenance is $16,000.
   The existing project was authorized by the Flood Control Act
approved June 22, 1936.
   Local cooperation. None required.
   Operations and results during fiscal year. The project was
operated according to plan and necessary repairs were made by
hired labor.
   At the beginning of the fiscal year both Lake Traverse and White
Rock Pools were slightly above conservation elevations 976.0 and
972.0, respectively. High evaporation and little inflow during the
summer and fall caused a general drop in the pools to 975 and 970.5
on November 1. The White Rock Pool froze virtually to the bottom
in late November precluding any discharge from the dam. Little
change occurred throughout the winter. Breakup began about
March 15. However, not until late in June as a result of rain did
the pools fill to normal. It was unnecessary to release any dis-
charge from White Rock Dam throughout the entire breakup
period to the end of the fiscal year.
   Costs for the year were $17,972 for operation and maintenance
by hired labor.
   Condition at end of fiscal year. The existing project was com-
pleted in June 1948. Fee title to 1,315.48 acres and easements on
5,952.35 acres of land have been acquired. The White Rock Dam
and Reservation control structure are in operation, and the struc-
tures and appurtenances are in good condition. The roadways
across structures are open to public travel.
   The total costs under the existing project to June 30, 1954, were
784            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

$1,476,235, being $1,332,200 for new work and $144,035 for oper-
ation and maintenance.
                                   Cost and financial summary

                                            Fiscal year ending June 30                        Tota:.to June
                                                                                              30, 1*4, includ-
                                      II                         ring                            fioc' years
                            1950           1951        1952             1953       1954        priorto 1950


New work:
   Appropriated--------------                                                                      $1,332,200
   Cost                                                                             -,             . .- 332,200
Maintenance:
   Appropriated .....       $8, 000        $9,650      $14,200          $13,700    $18, 900           146, 950
   Cost..----------------    9,300         10, 552      13,206           13, 966    17, 972           144, 035


                13. MISSISSIPPI RIVER NEAR AITKIN, MINN.
    Location. The area under consideration lies mainly in Aitkin
County in northeastern Minnesota, approximately 80 miles west
of Lake Superior and about 100 miles north of Minneapolis and St.
Paul. The Mississippi River in this area flows in a general south-
westerly direction through Aitkin County. Aitkin, Minn., is on
the Mississippi River 1,055.9 miles above the mouth of the Ohio
River (for general location, see U. S. Geological Survey map of
Minnesota).
    Existing project. The following features are included in the
plan of improvement. A diversion channel on a general east-west
alinement between miles 1,064 and 1,040.4 on the Mississippi River,
being a channel about 6 miles in length and, with the exception of
a contracted section at each end of the main diversion channel, a
bottom width of 90 feet and 1 on 3 side slopes; a channel about
1,100 feet in length permitting the Little Willow River to enter
the main diversion channel and a 2,800-foot channel diverting
Wakefield Creek into the main diversion channel; erosion control
structures at the mouth of the Little Willow and Wakefield Creek
diversions and one other point. In addition, two supplementary
diversion channels are located downstream, the 800-foot Pine Knoll
diversion between miles 1,040.9 and 1.040.1 and the 1,300-fo6t Tow
Head Rapids diversion located between miles 1,031.4 and 1,030.5.
The improvements will alleviate the flood condition and improve
drainage in and near Aitkin, Minn.
   The estimate of cost (1954) to the United States for new work
is $1,532,300.
   The project was authorized by the Flood Control Act approved
June 30, 1948 (H. Doc. 599, 80th Cong., 2d sess.). The latest pub-
lished map is in the project document.
   Local cooperation. The improvement is subject to the condi-
tions that responsible local interests give assurances satisfactory
to the Secretary of the Army that they will (1) provide, without
cost to the United States, all lands, easements, and rights-of-way
necessary for the construction of the project; (2) hold and save the
United States free from damages due to the construction works;
 (3) bear the expense of all necessary construction or alterations
of utilities, roads, highways, and bridges; (4) maintain all works
after completion in accordance with regulations prescribed by the
Secretary of the Army; and (5) prevent future encroachments in
                        FLOOD CONTROL-ST. PAUL, MINN., DISTRICT                                          785
the flood plain of the Mississippi River within the limits of the
project.
   The responsibility for local cooperation has been assumed by the
Aitkin Drainage and Conservancy District which has furnished
assurances and provided necessary rights-of-entry to lands re-
quired for construction.
   Operations and results during fiscal year. Designs were car-
ried on by hired labor. A contract for construction of the main
diversion channel, including Wakefield Creek diversion, was
brought from 37 percent completion to 94 percent completion. A
contract for outlet control and lower bank protection was com-
pleted. A contract for the inlet control, approach dredging and
upper bank protection was awarded and brought to 25 percent
completion.
   Costs for the year for advance planning by hired labor were
$8,219, and for construction by contract were $738,013. Total
costs were $746,232.
   Conditions at end of fiscal year. Preparation of detailed plans
is complete and plans and specifications as a whole are substantially
complete. Construction was initiated in September 1952 and the
project is 79 percent complete. Work on Pine Knoll and Tow Head
Rapids cutoffs and the outlet control structure and lower bank pro-
tection are complete. Work on the main diversion channel, upper
control, and appurtenant work is in progress. A total of 3,860,300
cubic yards of material has been removed under all contracts. A
contract for the Little Willow River diversion and county ditch
No. 11 drop structure remains to be initiated. Completion of that
contract and contracts under way will complete the project. Total
costs for the project to June 30, 1954, were $1,215,822 for new
work.
                                         Cost and financial summary

                                               Fiscal year ending June 30                      Total to June
                                                                                              .10,
                                                                                                1954. includ-
                                                                                              lng fiscal years
                                  1950        1951        1952        1953          1954        priorto 1950


New work:
   Anoropriated        .....      $25, 000    $47, 590   $600, 000   $597, 000 _                    $1, 269, 590
   Cost ___                            845     12,184      63,514     393,047      $746,232          1,215,822


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_                       $931
    Appropriated for succeeding fiscal year ending June 30, 1955              450,000
    Unobligated balances available for succeeding fiscal year ending June 30,
       1955-------------------_                                                                     450,931

  14. LAC QUI PARLE RESERVOIR, MINNESOTA                                           RIVER, MINN.
   Location. The works covered by this project lie along Marsh
and Lac qui Parle Lakes and the Minnesota River between the head
of Marsh Lake and Granite Falls, Minn. For general location, see
United States Geological Survey map of Minnesota.
   Existing project. Construction of the Lac qui Parle Reservoir
was initiated as a Works Progress Administration project spon-
sored by the State of Minnesota, prior to its authorization as a
Federal project by the Flood Control Act approved June 22, 1936.
786      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

The present plan of improvement provides for completion and
maintenance by the Department of the Army of the structures on
Marsh and Lac qui Parle Lakes and the Chippewa River diversion
works, substantially completed by the Work Project Administra-
tion for use of Marsh and Lac qui Parle Lakes as flood control and
water conservation reservoirs, and for channel improvement of the
Minnesota River below the lakes. The project includes a main dam
at the outlet of Lac qui Parle Lake, a structure between Marsh
Lake and Lac qui Parle Lake, for control of the Marsh Lake Res-
ervoir, a dam and diversion channel near Watson, Minn., for di-
verting floodwaters of the Chippewa River into the Lac qui Parle
Reservoir, necessary alterations to highways, railroads, and
bridges in the vicinity, and improvement of the channel of the
Minnesota River at various locations between Lac qui Parle Lake
and Granite Falls. The Lac qui Parle Dam, which carries a high-
way across the Minnesota River, consists of a control structure of
12 bridge spans incorporating sluice gates and fixed spillway weirs,
a 2,500-foot emergency spillway, and sections of highway embank-
ment connecting with high ground on either side of the valley.
The Marsh Lake Dam consists of a 112-foot concrete spillway, and
two sections of dredged earthfill totaling approximately 9,700 feet
in length, including an auxiliary 90-foot grouted riprap overflow
spillway. The Chippewa River flood diversion dam consists of a
concrete fixed crest structure supporting a highway bridge, and a
section of earthfill through which is provided a conduit for dis-
charge of low water flow. The diversion channel for passing flood-
waters of the Chippewa River into the Lac qui Parle Reservoir is
3,500 feet in length cut through a natural ridge separating the
river and an arm of the lake and includes a six-span concrete sub-
merged weir, also supporting a bridge, which allows a reverse flow
from the lake. A rolled earthfill dike extending along the lower
south side of the channel is an extension of the diversion dam and
serves also to protect the adjacent railroad tracks from being
flooded. Completion of the project included improvements to Lac
qui Parle Dam and spillway, improvements to Marsh Lake Dam,
access roads, and dike, Great Northern bridge alterations, and con-
struction of a Tainter gate at the Chippewa Dam, and stage-
recorder houses. Improvement of the Minnesota River between
Lac qui Parle Lake and Granite Falls consists of rock removal, snag
removal, and cutoffs at various locations to provide for increasing
the bank-full capacity of the channel. The project, with reservoir
capacity of about 96,700 acre-feet for flood control above normal
elevations of the two conservation pools, provides protection for
agricultural lands against summer floods. Storage of 58,500 acre-
feet for conservation purposes provided below normal elevations
of conservation pools results in improved lake levels for recreation
and game conservation in addition to providing for increased low
water flow downstream for agricultural interests and for sewage
disposal at Granite Falls.
   The estimate of cost (1954) to the United States for completion
of the project is $564,000 for construction and $397,000 for lands
                     FLOOD CONTROL--ST. PAUL, MINN., DISTRICT                                       787
and damages. The estimated (1954) annual cost of maintenance
is $23,000.
    Local cooperation. None required.
    Operations and results during fiscal year. Work pertaining to
transfer of land from the State of Minnesota to the United States
was continued by hired labor. Structures were operated according
to plan and necessary repairs were made to structures including
repairs to Watson Sag channel earlier damaged by floods.
    At the beginning of the fiscal year Lac qui Parle Reservoir was
at elevation 940.3 and receding from a moderate size flood. The
stage had nearly returned to normal when additional rain resulted
in a second rise cresting at elevation 938.5 on August 14. The pool
returned to normal elevation 931.2 and was maintained at normal
elevation until 15 February when it was lowered according to plan
to provide storage for the spring breakup. A low pool elevation
of about 928.0 was reached on March 10. Low inflows from the
spring breakup and from subsequent rains were easily stored in the
reservoir with a crest elevation of 933.1 on April 1 and without
exceeding bank-full stages downstream. Normal elevations were
attained by the end of the fiscal year.
    Costs for the year for new work were $317,365, being $7,365 for
hired labor and $310,000 for land payments. Costs for operation
and maintenance were $38,153. Total costs were $355,518.
   Condition at end of fiscal year. Transfer of the project from
the State of Minnesota to the United States was consummated on
September 7, 1950. Previously operated by the State of Minnesota,
the project has been operated by the Government according to the
approved plan of operation since that time. Easements on 32.8
acres of land have been obtained, and 516.3 acres of land have been
acquired in fee; easements on 14,642.6 acres of land are in process
of acquisition. Construction under the present plan of improve-
ment was started in September 1941 and was completed in Decem-
ber 1951. All structures are in good condition. Completion of
land acquisition will complete the project.
   Total costs under the existing project to June 30, 1954, were
$1,093,526, of which $917,491 was for new work and $176,035 was
for operation and maintenance.
                                    Cost and financial summary

                                           Fiscal year ending June 30                    Total to June
                                                                                        30, 1954, includ-
                             1950        1951         1952        1953        1954       prior to 1950


New work:
   Appropriated               -      -- --                                                      $961,000
   Cost--   -- --      -     $20,598    $116,933    $103,867       $2,888    $317,365            917,491
Maintenance:
   Appropriated-             18,500      -4,600       63, 300      61,900      22,100            179,700
   Cost____-__   .     .                  16,595      40,428       74,408j     38,153            176,035


Other new work data: Unobligated balance, fiscal year ending June 30, 1954_ 1 $31,059
1Includes $9,200 in OCE reserve.
788            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                  15. INACTIVE FLOOD CONTROL PROJECTS

                                                     For last          Cost and expenditures to             Estimated
                                                    full report,                June 30, 1954                amount
                Name of project                      anseeal                                                 required
                                                      report               Con-           Operation          complete
                                                       for-            struction             and
                                                                                         maintenance
Pembina River Reservoir, N. Dak--------------          1950                  $50, 000                           1$760, 000
Tongue River Reservoir, N. Dak--...............        1950                   23, 695           --     --        1 856, 300
Upper Mississippi River Basin (St. Paul district)      1950        -   -                                     2 23, 700, 000
  Black River Reservoir, Wis.
Dry Run, Iowa....-----------------------------         1951                1, 706, 900      -               Completed._


  1 Further work deferred pending review of H. Doc. 565, 78th Cong., 2d sess.
  2 Has not been selected for construction.
  8 Exclusive of $42,765.80 expended from contributed funds.

                           16. GENERAL INVESTIGATIONS
   Examinations and surveys. The cost of general investigations
during the fiscal year was $112,231. The balance unexpended at
the end of the fiscal year, $4,893 plus an additional allotment for
fiscal year 1955 will be used to continue work on authorized exami-
nations and surveys and collection and study of basic data. The
additional sum of $208,600 can be profitably expended in fiscal year
1956.
   Collection and study of basic data. Under the category "Col-
lection and Study of Basic Data," streamflow data was obtained by
Corps of Engineer gaging beyond the cooperative stream-gaging
program; hydraulic laboratory work was continued in the meas-
urement and analysis of the sediment load in streams, a flood
emergency manual was reviewed and revised, and International
Joint Commission activities for regulation of Lake of the Woods
waters were accomplished. Costs for the fiscal year under this
category, included in the costs indicated above, were $25,129.
                   17. INSPECTION OF COMPLETED WORKS
   Inspections under this heading are made of completed flood con-
trol projects which have been transferred to local interests for op-
eration and maintenance. The inspections are for the purpose of
determining that the project channels are kept clean and unob-
structed, dikes and revetments are in good condition, and struc-
tures are in good repair and operable. Two inspections of the Dry
Run, Iowa project were made during the year. The project was
found in good condition, although minor deficiencies were called to
the attention of the local operating official. Costs for the year were
$163. Total costs to June 30, 1954, were $328.
                                     Cost and financial summar y

                                            Fiscal year ending June 30                                   Total to June
                                                                                                        30, 1954, Includ-
                                                                                                        ing fscal years
                              1950        1951           1952                1953          1954          priorto 1950

Maintenance:
   Appropriated-  .- ---.. ------            $300         -$220                 $425            $300                 $805
   Cost----------     ------------             80      -------                    85             163                  328
                       FLOOD CONTROL         ST. PAUL, MINN., DISTRICT                           789

18. FLOOD              CONTROL      WORK       UNDER          SPECIAL        AUTHORIZATION
  Snagging and clearing of navigable streams and tributaries in
the interests of flood control. (Sec. 13 of the 1946 Flood Control
Act.)
  In addition to funds previously allotted under this heading, the
sum of $10,000 was made available during fiscal year 1954 for snag-
ging and clearing on the South Fork of the Crow River at Hutchin-
son, Minn. No work has been done. With funds allotted prior to
this fiscal year, work was accomplished by hired labor on the Min-
nesota River in the vicinity of Montevideo, Minn., during the period
October 19 to November 6, 1953, and by contract on the Redwood
River in the vicinity of Marshall, Minn., during the period Sep-
tember 21 to December 11, 1953. Costs for the year were $38,852.
                                 Cost and financial summary

                                            Fiscal year ending June 30                 Total to June
                                                                                       30, 1954, includ-
                                                                                       ing fiscal years
                             1950          1951        1962        1953       1954      prior to1950

New work:
   Appropriated -            $70,000       $52,431     $85,000     $54,300    $5,600          $267,331
   Cost-.-----------          30,707        89,187       6,961      91,624    38,852           257,331


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954          -          $10,000
    Unobligated balances available for succeeding fiscal year ending June 30,
                                       -
      1955 -- - - - - - - - -- - - - - - - - - - --- - - - -                   10,000
  Small flood control projects not specifically authorized by Con-
gress. (Sec. 212 of the 1950 Flood Control Act.)
           SWAN CREEK NEAR CASSELTON, NORTH DAKOTA
   The project for improvement of Swan Creek, near Casselton,
N. Dak., was approved and funds were allotted for construction
prior to this fiscal year. Approval was subject to general require-
ments specified by the Flood Control Act of June 22, 1936, as
amended, with the additional provision that local interests assume
all construction costs in excess of $150,000 and make such funds
available to the District Engineer prior to initiation of construc-
tion. Assurances submitted by the North Dakota State Water
Conservation Commission have been approved covering the provi-
sions of local cooperation including the provisions for assuming all
costs in excess of $150,000 and for assuming the additional costs
of a modified channel alignment requested by local interests. The
Swan Creek Water Conservation and Flood Control District, the
sponsoring agency, had acquired substantially all of the lands re-
quired for construction, but on June 7, 1954, that agency requested
a 6-month delay in proceeding with further work on the project to
permit local interests to make a restudy of the whole drainage
problem in light of the overall expenditures presently con-
templated.
   Plans and specifications for the channel excavation are substan-
tially complete and an agreement has been consummated with the
Northern Pacific Railway Company for relocation of a bridge over
Swan Creek. All further work in connection with this project has
 790          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

been indefinitely suspended except for whatever contacts may be
required with local interests in connection with their restudy of the
project.
   Cost of the work during the fiscal year was $5,890. Total costs
to June 30, 1954, are $17,496.
                      RUSH CREEK, RUSHFORD,                          MINNESOTA
   The sum of $10,000 was allotted for the purpose of a report on
Rush Creek at Rushford, Minn. to determine the extent of work
to be done, if any, at that location. Studies progressed to the point
where it was determined that the total project cost would be about
$700,000 of which local interests would be required to furnish
about $550,000. Inasmuch as local interests cannot contribute that
amount, studies were suspended and remaining funds revoked. A
further study of the situation at Rushford will be accomplished as
an interim survey under existing authority for a flood control sur-
vey of the Root River basin. Costs for the fiscal year and total
costs of the work were $9,430.
            REDWOOD RIVER BELOW MARSHALL, MINNESOTA
  The sum of $5,000 was allotted for the purpose of a report on
Redwood River below Marshall, Minnesota to determine the extent
of work to be done, if any, at that location. Work on the report
by hired labor is about 9 percent complete. Costs for the fiscal
year and total costs to June 30, 1954, are $862.
                                          Cost and financial summary
                      SWAN CREEK NEAR CASSELTON, NORTH DAKOTA

                                                 Fiscal year ending June 30                   Total to June
                                                                                             30, 1954, includ-
                                                                                             ing fiscal years
                                   1950        1951       1952         1953       1954        prior to 1950

New work:
   Appropriated----      ..                                $6, 500    $143, 500     --               $150, 000
   Cost                       ----------
                        -----.....                          4,669        6, 937    $5,890              17,496



Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_-----------     $132, 504
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955                     --------                                132,504
                              RUSH CREEK, RUSHFORD,              MINNESOTA

                                                 Fiscal year ending June 30                   Total to June
                                                                                             30, 1954, includ-
                                   1950        1951       1952         1953       1954        prior to 1950

New work:
   Appropriated -----        --     -   -    -   -   -                             $9, 430             $9, 430
   Cost- ... .. .. ..   ...-----      .
                                   --...
                                   ----   ----- - __                 - - - -        9,430               9,430
                  FLOOD CONTROL-ST. PAUL, MINN., DISTRICT                                       791
                  REDWOOD RIVER BELOW MARSHALL,                    MINNESOTA
       --
                                          Fiscal year ending June 30                   Total to June
                                                                                      30, 1954, includ-
                                                                                      ing fiscal years
                             1950        1951          1952       1953      1954        priorto 1950


New work:
   Appropriated ...... _ _                                                   $5,000             $5,000
   Cost.    --                                  - --                           862                862


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954            - - -    $4,138
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955 _-________-_-__                      -___
                                            ___---                             4,138

   Flood control emergencies--Repair and flood fighting and rescue
work. (Sec. 210 of the 1950 Flood Control Act and supplemental
authorizations.)
   Under the above authority, costs during the fiscal year were
$34,160, being $2,000 for final payment for repairs to Prairie Island
levee at Winona, Minn., by contract and $32,160 for emergency
work in the Mississippi, Minnesota, and Red River of the North
drainage basins.
                                    Cost and financial summary


                                          Fiscal year ending June 30                   Total to June
                                                                                      30, 1954, includ-
                                                                                      ing fiscal years
                             1950        1951          1952      1953       1954        prior to 1950


Maintenance:
   Appropriated        _                $124,562       $47,285   $225,300   $34,160           $431, 307
   Cost_                                  77, 957       93,890    225,300    34,160            431,307
     IMPROVEMENT OF RIVERS AND HARBORS IN THE
             KANSAS CITY, MO., DISTRICT
   This district comprises a portion of southwestern Iowa; north-
western, central, and western Missouri; northern Kansas; south-
ern Nebraska; and a portion of northeastern Colorado embraced in
the drainage basin of the Missouri River and tributaries:from Rulo,
Nebr., to the mouth. The report on the navigation project for the
section of the Missouri River from Kansas City, Mo., to Rulo, Nebr.,
is included in report upon improvement of rivers and harbors in
Omaha, Nebr., district.
                                    IMPROVEMENTS

                                          Page                                     Page
                  Navigation                           Flood Control-Continued
1. Missouri River, Kansas City.                 7. Kanopolis Reservoir, Missouri
    to Rulo............. -                 793       River Basin, Kansas .........812
2. Missouri River, Kansas City                  8. Tuttle Creek Reservoir, Mis-
    to mouth                               793       souri River Basin, Kansas .....814
                                                9. Topeka, Kansas River, Kansas     816
                Flood Control                  10. Chariton River, Mo........... 817
                                               11. Pomme de Terre Reservoir,
3. Missouri River Basin, Kansas                      Missouri River Basin, Mis-
      City District .....            -
                                _...-..    797       souri   ..   ..               819
4. Missouri River Agricultural                                                      820
                                               12. Table of Inactive Projects ........
    levees, Sioux City, Ia., to                13. General Investigations_ ...........
                                                                                    820
    mouth ..-........... .....             799 14. Inspection of Completed Proj-
5. Kansas Citys, on Missouri and                     ects ................. 820
    Kansas Rivers, Mo. and                     15. Flood control work under spe-
    Kansas-                   _            802                                      821
                                                     cial authorization ................
6. Harlan   County    Reservoir,
    Missouri River Basin, Ne-
    braska ....                            810
               1. MISSOURI       RIVER, KANSAS CITY TO RULO
  See report on Missouri River, Kansas City to Sioux City, page
825.
          2. MISSOURI RIVER, KANSAS CITY TO THE MOUTH
   Location. The Jefferson, Madison, and Gallatin Rivers conjoin
at Three Forks, Mont., to form the Missouri River, which flows
southeasterly 2,464.41 miles across or along seven States to the
Mississippi River, 17 miles above St. Louis. For description, see
page 1149, Annual Report for 1932. Practically the entire length
of the section from Kansas City to the mouth is contained within
the State of Missouri.
   Previous projects. The first appropriation for improvement by
regulation was made in the River and Harbor Act of June 18, 1878.
The original plan for comprehensive improvement was adopted by
the River and Harbor Act of August 2, 1882, modified by River and
Harbor Acts of July 5, 1884, September 19, 1890, and June 13, 1902.
For further details, see page 1891 of Annual Report for 1915, and
page 1153 of Annual Report for 1938.
   Existing project. This provides for a channel of 9-foot depth
and width not less than 300 feet, to be obtained by revetment of
11941 adjusted mileage.
                                                                            793
794               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

banks, construction of permeable dikes to contract and stabilize
the waterway, cutoffs to eliminate long bends, closing of minor
channels, removal of snags, and dredging as required. Length of
section under improvement (mouth to upper end of Quindaro
Bend) is 386.2 miles.' Ordinary and extreme fluctuations of stage
are 16 and 38 feet, respectively.
  The estimated cost for new work (1954) is $119,000,000 exclu-
sive of amounts expended on previous projects. The estimated
cost for annual maintenance is $2,450,000.
  The existing project was authorized by the following River and
Harbor Acts:

       Acts                          Work authorized                                 Documents

July 25,1912       Project adopted for securing a permanent navigable     H. Doc. 1287, 61st Cong., 3d sess.
                    channel of 6-foot depth.                                (Contains latest published map.)
Aug.    8, 1917    This act fixed the upstream limit of the improvement   H. Doc. 463, 64th Cong., 1st sess.
                     at the upper end of Quindaro Bend (386.2 miles         (Contains latest published map.)
                     from the mouth), and provided for dredging.
Mar.    3, 1925    For a minimum width of 200 feet, with a reasonable
                    additional width around the bends.
Aug. 30, 1935      For completion of improvement from the mouth to        H. Doec. 238, 73d Cong., 2d sess.
                    Sioux City, Iowa.                                       (Contains latest published map.)
Mar.    2,1945     For securing a navigable channel of 9-foot depth and   H. Doec. 214, 76th Cong., 1st sess.
                     a minimum width of 300 feet.                           (Contains latest published map.)


   Local cooperation. The project provides that cooperation from
benefited localities may be required, in case a comprehensive plan
is adopted by Congress, for an apportionment of expense, where
any improvement confers special benefit; and receipt of contribu-
tions from private parties, to be expended with Government funds
upon authorized works where such would be in the interest of navi-
gation, is authorized by the River and Harbor Act of March 4,
1915. The Secretary of the Army has approved the general prin-
ciple of cooperative construction on the Missouri River below Kan-
sas City on the basis that 25 percent of the cost of any special in-
stallation shall be paid by the United States and 75 percent by the
local interests.
   The total amount contributed by local interests in cooperation
with the United States from 1918 to June 30, 1954, was $675,-
662.80, of which $8,647.11 was returned to contributors.
   Terminal facilities. Facilities for transferring grain, petrole-
um products, and other commodities are maintained at various lo-
cations on this section of the river. These facilities are listed in
the following table:
1 1941 adjusted   mileage.
                RIVERS AND HARBORS--KANSAS CITY, MO., DISTRICT                                                                                             795
                                                                                                                                           Location 2

                                                                                   1
                                  Description of facility                                                                       Miles
                                                                                                                                above
                                                                                                                               mouth            Nearest town
                                                                                                                                (1932
                                                                                                                               mileage)

Existing facilities:
    Oil-loading facilities-                                                                                                       379. 6   Kansas City, Kans.
    Grain elevator, conveyor, and dock, publicly owned, leased to                                                                 379. 1      Do.
     private concern.
    Warehouse, escalator, bulk-handling dock, and concrete loading                                                                378. 6   Kansas City, Mo.
      platform, publicly owned, leased to a private corporation.
    Loading platform.....----------- ----------                                                ----------------                   378. 2       Do.
    Warehouse and concrete loading platform, publicly owned,                                                                      377. 2       Do.
     leased to Department of the Army.
    Facilities for transferring sand and gravel-.............. ........                                                           377. 1        Do.
          Do          ........-----------           .        ..............   322. 0                                                       Lexington, Mo.
           Do    _      - _-_-       ..
                                    --        ..    .......
                                                    .. .. .                   297. 4
                                                                      ...---------                                                         Waverly, Mo.
    Grain-loading facilities ____________________________________             297. 15                                                           Do.
    Facilities for transferring sand and gravel ..        --------          s227. 2                                                        Glasgow, Mo.
    Grain-loading facilities _____________.       .                         s226.9
                                                        .______________________.                                                                Do.
    Facilities for transferring sand and gravel_                              196. 5                                                       Boonville, Mo.
           Do-------------------------------------                                                                              S186. 0    Rocheport, Mo.
           Do     - -         -   -       -        - -          --- -             - - - - - - - - -                              142. 8    Jefferson City, Mo.
          Do                                                                                                                     S 96. 8   Hermann, Mo.
          Do-------------------------------                          --                                                            67. 5   Washington, Mo.
          Do .- .---              _-
                                  -.-- -- -- - -- -- - -- - -- -- - -- -- - -- -                                                   28. 0   St. Charles, Mo.
    Proposed facilities:
    Grain-loading facilities -___-                            __         ____-__                           -----                 384. 4    Kansas City, Kans.
           Do_
           D o-------- -----                                        --                                           -               380. 0        Do.
    Molasses-unloading facilities_______________________ ______                                                                  378. 1    Kansas City, Mo.
    Coal-unloading facilities -__ _________________     _________                                                                369. 8        Do.
    Oil-unloading facilities-           --                                                                                       367. 8    Sugar Creek, Mo.
         Do__
          D   o - -   - - - - -   - -      - -      - - - - - - -   - - - - - -    - - - - - - -   - - - - - -   - - - - - -    3257. 0    Dewitt, Mo.
    General purposes facilities_                                                                                                  196. 5   Boonville, Mo.
    Tank-unloading facilities_______________________________________                                                              196. 0       Do.
    Oil-unloading facilities                        ___                                                                           192. 0       Do.
    Grain-loading facilities___________________________ ______________                                                            134.0    Osage City, Mo.
    Bulk-handling facilities ______________________________                                                                         5.0    St. Charles, Mo.

   Privately owned and operated unless otherwise indicated.
2 On right bank unless otherwise indicated.
s On left bank.

   Operations and results during fiscal year. New work: This
work consisted of preliminary work in connection with the acquisi-
tion of right-of-way at a cost of $3,704 and the construction, by
contract, of 30 dikes and 14 dike extensions totaling 13,266 linear
feet, and 6 lengths of revetment totaling 15,367 linear feet, at a
total cost of $1,120,804, and construction, by hired labor, of 14
dikes and 3 dike extensions totaling 8,547 linear feet, a length of
revetment of 1,100 linear feet and the removal of points at 11
localities, at a total cost of $694,628 and engineering, design and
surveys at a cost of $71,107. The total cost of new work (includ-
ing pending adjustment of $2,553) was $1,892,796.
   Maintenance: This work consisted of the repair, by contract, of
17,225 linear feet of dikes and 36,222 linear feet of revetment, at a
total cost of $1,178,768, and the accomplishment, by hired labor,
of the following: Removal of 3,118,790 cubic yards of material
from 7 localities by the U. S. Dredges Black, Mitchell, and Clark,
at a total cost of $396,341; the repair of 44,632 linear feet of dikes
and 162,978 linear feet of revetment at a total cost of $1,594,264;
snagging at a total cost of $7,090; reconnaissance and channel
marking for navigation at a total cost of $288,666; real estate man-
agement services at a total cost of $16; stream gauging for special
studies and working data at a cost of $22,038; and engineering,
design, and surveys, including channel surveys, in connection with
maintenance works, at a total cost of $171,382. The total cost of
796            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

all maintenance work was $3,658,565.                                 The total costs for the fiscal
year were as follows:

                                                                       New work            Maintenance             Total

Regular funds---      ...--------------------                           $1, 892, 796         $3, 658, 565          $5, 551, 361


   Condition at end of fiscal year. The existing project was about
87 percent complete at the end of the fiscal year, based on the
present approved estimate of cost. The physical extent of; :work
accomplished was 1,869,478 linear feet of dikes, 1,325,157 linear
feet of revetment, 29,499 linear feet of abatis, 27,493 linear feet
of bank protection, 35,842 linear feet of retards, 30,299 linear feet
of levees, five revetment spillways, excavation of 7,537,789 cubic
yards of material in construction of pilot canals, removal of 141,-
042 linear feet of existing structure, dredge fills totaling 1,546,493
cubic yards, removal of 432,664 cubic yards of rock, removal of
82,805,096 cubic yards of material by dredging, and removal of
5,439,461 cubic yards of material in the improvement of 'bank
alinement. Although additional dikes and revetments are required
to attain the project dimensions, a channel with a minimum depth
of 61/2 to 7 feet and a minimum width of 200 feet is available
throughout the navigation season, which covers approximately :the
period from March 15 to November 30. The controlling: depth
throughout this section of the river on June 30, 1954, was gener-
ally 8 feet at which time there was an average discharge at Kansas
City, Mo., of approximately 59,000 cubic feet per second. The
practical draft at ordinary stages of the river is 61/ feet. This
section of the river has been used for commercial navigation since
June 1935.
   The total cost of the existing project to June 30, 1954, was as
follows:

                                                                       New work            Maintenance             Total


Regular funds-...___.                                       -   ..     $88,060,999          $48, 980,462        $137, 041, 461
Emergency relief funds-                                         -        1, 375,243              133,757           1,.509, 000
Public works funds- ..                                                   6, 468,491    -                           6, 468, 491

                                                                        95, 904, 733         49, 114, 219        145, 018, 952


                                     Cost and financial summary
                                             CONSOLIDATED

                                               Fiscal year ending June 30                                    Total to June
                                                                                                            10, 1954, 'includ-
                                                                                                            ing fiscal years
                              1950            1951          1952             1953             1954            priorto 1950


New work:
   Appropriated            $1, 885, 000   $2, 250, 000   $2,300, 000     $2, 586,000       $1,885,000           $103'812, 358
   Cost -.-----
           .                2,133, 336     1,613,940      2,279,824       3,289, 057        1,892, 796           103,809,210
1Maintenance:
      oppropriated-         2, 660,000     2, 225, 000    2,570,1000      3,193, 700        3,658,000             49,539, 887
     ost
   ,....                   '2,833,894      2, 041,509     2,663,897       3, 295,455        3,658,565            ,49,539, 887


  1Inceludes $644,374 costs of new work and $22,642 for maintenance from contributed funds.
I In'cludes $7,260,103 costs if new work and $403,027 for maintenance for previous projects.
                       FLOOD CONTROL--KANSAS CITY, MO., DISTRICT                                                                          797
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954                      $3, 149
    Appropriated'for succeeding fiscal year ending June 30, 1955______     2,000,000
    :Unobligated balancesavailable for succeeding fiscal year ending June
      30, 1955.-------                                                     2, 003, 149
    Estimated additional amount needed to be appropriated for comple-
      "tion of existing project_                                          15, 187, 642

              3. MISSOURI RIVER BASIN, KANSAS CITY ;DISTRICT
   Location. The flood control improvements included in this
project are located on and along the Missouri River and several of
the principal tributaries of the Missouri River and are located in
the States comprising the Missouri River Basin.
  Existing project. The general comprehensive plan for flood
control and other purposes in the Missouri River Basin provides
for levees along the Missouri River between Sioux City, Iowa, and
the mouth, flood protection works at certain municipalities, and
reservoirs located on the main stem of the Missouri River and on
the tributaries for control of flood flows at the dam site.                                                                              The
existing project was authorized by the following flood control acts:

      Acts                                    Work authorized                                                    Documents
                                                  I                                            I                                                -


June 28,1938         Adopted general comprehensive plan for Missouri                               Flood Control Commiittee Doc. 1,
                      River Basin and authorized $9,000,000 for initiation                           75th Cong., 1st sess.
                      and partial accomplishment.
Aug. 18, 1941        Modified the general comprehensive plan to include                            H. Doc. 842, 76th Cong., 3d sess.
                      Harlan County dam and reservoir on the Repub-
                      lican River, Nebr.; other supplemental flood con-
                      trol works on the upper Republican River; and
                      authorized $7,000,000 additional expenditure.
Dec. 22, 1944        Expanded the general comprehensive plan for the                               H. Doc. 475, 78th Cong., 2d sess.;
                      Missouri River Basin and authorized $200,000,000                               S. Doc. 191, 78th Cong., 2d sess.;
                      additional expenditure.                                                        S. Doc. 247, 78th Cong., 2d sess.
July 24, 1946        Authorized an additional expenditure of $150,000,000
                      for prosecution of the general comprehensive plan
                      for the Missouri River Basin.
May 17,1950          Authorized an additional expenditure of $250,000,000
                      for prosecution of the general comprehensive plan
                      for the Missouri River Basin.



   Included in the comprehensive basin plan are the following proj-
ects in the Kansas City district:
                                                                                                                                           ----
                                                                                                                                Estimated
                                                         Project                                                               Federal cost


Missouri River agricultural levees, Rulo to mouth________ _________                                                 ____...           $116, 000, 000
Kansas Citys, Mo., and Kans_ .........
                                   __.-----------.............
                                                  _                                                         --             ------       45, 600, 000
Pioneer Reservoir, Arikaree River, Colo. and Kans .                              ._______..
                                                                                    __________                .        .        .       20,000, 000
R ed W illow R eservoir, R ed W illow C reek, N ebr......                      .. .. _____- ... . . . -- .                              12, 500, 000
Indianola, Republican River, Nebr----...-----                                  -         -.--------------                                    67, 275
Bartley, Republican River, Nebr ..          __.___  _           .______________._....-----------------.                                     118, 269
Harlan County Reservoir, Republican River, Nebr_                      ..........                          _.........................    45, 268, 000
Kanopolis Reservoir, Smoky Hill River, Kans                               -           -..........--                            ---...   12, 297, 000
Tuttle Creek Reservoir, Big Blue River, Kans ..........------..------                                                                   89, 900, 000
Chillicothe Reservoir, Grand River, Mo ..                      .........---------------                        -------------            65, 800, 000
Osceola Reservoir, Osage River, Mo ___________ ________________________. .                                                             116, 000, 000
South Grand Reservoir, South Grand River, Mo _______________________________..              .            .          .            .      29, 200, 000
Pomme de Terre Reservoir, Pomme de Terre River, Mo                                              ---------------                         22, 500, 000
R ich land R eservoir, G asconade R iver, M o -.- . . . . . . . . . ..-----.-- .-------- 33, 300, 000
Arlington Reservoir, Gasconade River, Mo                                            .                  -
                                                                                                 ---------------------                  27, 200, 000
                                                                                                                           I
798      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Recommended modification of project. Under date of Febru-
ary 28, 1949, the Chief of Engineers recommended that the existing
general comprehensive plan for flood control and other purposes in
the Missouri River Basin be further modified and expanded to pro-
vide for Milford and Perry Reservoirs on Republican and Delaware
Rivers, Kans., respectively, and for local flood protection at Bea-
trice and Hubbell, Nebr.; Abilene, Salina, Marysville, Manhattan,
Topeka (North Topeka and vicinity), Fort Riley, Lawrence, and
Merriam, Kans.; and for flood control and major drainage on
Stonehouse Creek, Kans., all in the Kansas River Basin at an esti-
mated Federal cost of $41,805,000 for construction (H. Doc. No.
642, 81st Cong., 2d sess.).
   Under date of May 4, 1949, the Chief of Engineers recommended
that the existing general comprehensive plan for flood control and
other purposes in the Missouri River Basin be further modified to
provide for Rathbun Reservoir on Chariton River, Iowa, and for
flood protection works at Mystic, Iowa, at an estimated Federal
cost of $14,554,000 for constructing Rathbun Reservoir and $29,-
640 for construction of improvements at Mystic, Iowa (H. Doc.
No. 561, 81st Cong., 2d sess.).
   Under date of August 15, 1949, the Chief of Engineers recom-
mended that the general comprehensive plan for flood control and
other purposes in the Missouri River Basin approved by the Flood
Control Act of June 28, 1938, as modified by subsequent acts, be
modified and expanded to include the construction of nine reser-
voirs and two local protection projects in the Osage River Basin at
an estimated additional cost to the United States of $137,694,000
for construction (H. Doc. No. 549, 81st Cong., 2d sess.).
   Operations and results during fiscal year. The operations dur-
ing the fiscal year, together with costs and expenditures for those
projects on which plans were in preparation or on which construc-
tion had been initiated, are shown in following individual reports.
   Under sections 7 and 9 of Public Law 534, Flood Control Act,
approved December 22, 1944, the Corps of Engineers is responsible
for detailed scheduling of operations of storage capacity reserved
for or assigned to flood control in reservoirs constructed by the
Bureau of Reclamation as well as those constructed by the Corps
of Engineers.
   Condition at end of fiscal year. The condition of the projects
discussed in individual reports is given in those reports. The total
cost and expenditures to June 30, 1954, exclusive of the cost and
expenditures for projects discussed in individual reports, for spe-
cial engineering studies in connection with the comprehensive plan,
was $55,568.55.
   The cost for maintenance (scheduling of flood control reservoir
operations) was $63,384.
                   FLOOD CONTROL-KANSAS CITY, MO., DISTRICT                                                              799
                                         Cost and financial summary

                                                         Fiscal year ending June 30                            Total to JTune
                                                                                                               30, 1954, includ-
                                                                                                               ing fiscal years
                                  1950                  1951        1952           1953             1954        priorto 1950

New work:
    Appropriated_                        ------------          ------------   -----------          ------------         $55, 569
                                                                                                                        $------------
    Cost                                        ------------ ----------
                             I .....---------.------------                    -------------- ------------                55,569
Maintenance:
    Appropriated -----------------                  $44, 000       $35, 000       $39, 000          $57, 000            175,000
    Cost---------------------------                  35,782         43,191         32,554            63,384             174,912


  Notes: The allotments and costs shown above for new work cover 21 x 3113 Flood Control, General
funds allotted to the "Republican River Basin Reservoirs (Medicine Creek Reservoir), Colorado, Nebraska
and Kansas."
  The allotments and costs shown above for maintenance cover 21 x 3123 Flood Control, General, funds
allotted to "Scheduling of Flood Control Reservoir Operations."

4. MISSOURI RIVER AGRICULTURAL LEVEES, SIOUX CITY, IOWA,
                 TO THE MOUTH (RULO, NEBR., TO MOUTH)
   Location. On both banks of the Missouri River from Sioux
City, Iowa, to the mouth near St. Louis, Mo., a distance of approxi-
mately 760 miles.
   Existing project. The plan of improvement provides for a
series of levee units and appurtenant works along both sides of
the Missouri River from Sioux City, Iowa, to the mouth, for the
protection of agricultural lands and small communities against
floods. The estimate of cost (1954) for that portion of the project
from Rulo, Nebr., to the mouth is $122,900,000, of which $116,-
000,000 is the Federal cost for construction, $6,900,000 is for lands
and damages to be borne by local interests. The existing project
was authorized by the following Flood Control Acts:

    Acts                              Work authorized                                                Documents
Aug. 18, 1941    Levees along both sides of the river from Sioux City                  H. Doc. 821, 76th Cong., 3d sess.
                   to Kansas City.
Dec. 22,1944     Extended project from Kansas City to the mouth                        H. Doc. 475, 78th Cong., 2d sess.;
                   and provided for increased protection.                               S. Doc. 191, 78th Cong., 2d sess.;
                                                                                            S. Doc. 247, 78th Cong., 2d sess.


   Local cooperation. Section 3 of the Flood Control Act approved
June 22, 1936, as amended by the Flood Control Act approved De-
cember 22, 1944, applies. Local interests have furnished rights-of-
way for construction of levees in units R 513-512 (secs. I and II),
R 500, L 488, R 482, L 476, L 448-443 (secs. I and II), R'440, and
L 400. Local interests have also indicated their interest in the
early construction of other units of the project.
   Operations and results during fiscal year. Unit L 519-L 512-L
504: Detail project plans and specifications for the construction of
levees and appurtenances for this unit are being accomplished by
hired labor, approximately 2 percent of the work being completed
at a total cost for the fiscal year of $17,947.
   Unit R 513-R 512: The Design Memorandum No. 1 for Under-
seepage Control was completed and approved by OCE. The con-
struction of floodway clearing and levee surfacing were completed
by contract at a cost during the fiscal year of $68,429. Engineer-
ing and design work in connection with the above was accomplished
        Sig 26---799-830
800      REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

by hired labor at a cost during the fiscal year of $13,456. The total
cost during the fiscal year was $81,885.
   Unit R 500: The completion of the levee surfacing and slope and
toe protection were accomplished by contract, during the fiscal year
at a cost of $6,185. The installation of piezometer tubes by hired
labor was accomplished during the fiscal year at a cost of $2,435.
   Engineering and design in connection with the above was accom-
plished by hired labor at a cost during the fiscal year of $5,877.
The total cost for this unit for the fiscal year was $14,497.
   Unit L 497: Work was continued on the Design Memorandum,
and plans and specifications by hired labor, bringing them up to 50
percent and 45 percent of completion, respectively, at a cost of
$2,118 for the fiscal year.
   Unit L 488: The Design Memorandum was brought to 95 percent
of completion, and the plans and specifications were brought to 60
percent of completion on underseepage control during the fiscal
year, at a cost of $17,598. The total cost for the fiscal year was
$17,598.
   Unit R 482: The construction of raising, riprap slope protection,
and surfacing existing levee was completed by contract at a cost of
$144,645. The installation of piezometer tubes by hired labor was
completed at a cost of $1,723. Engineering and design in connec-
tion with the above was accomplished by hired labor at a cost dur-
ing the fiscal year of $18,809. The total cost for the fiscal year was
$165,177.
   Unit L 476: Revision of Design Memorandum No. 1 for Under-
seepage Control was completed. The installation of piezometer
gages was completed by hired labor at a cost of $1,901. Construc-
tion of channels, raising levee crown, and modification of drainage
structure was completed by contract at a cost of $30,698 for the
fiscal year. Engineering and design in connection with the above
was accomplished by hired labor at a cost during the fiscal year of
$20,514. The total cost for the fiscal year was $53,113.
   Unit L 448-443: The Design Memorandum No. 1 for Underseep-
age Control was completed. The construction of surfacing and
raising levee crown was completed by contract during the fiscal
year at a cost of $69,672. Seeding levee crown was completed by
hired labor at a cost of $1,328. Engineering and design in con-
nection with the above was accomplished by hired labor at a cost
during the fiscal year of $28,870. The total cost for the fiscal year
was $99,870.
   Unit R 440: Design Memorandum No. 1 for Underseepage Con-
trol was completed and approved. Plans and specifications for
underseepage control and Doniphan Creek diversion were com-
pleted. A contract for underseepage control was initiated and
work initiated during the fiscal year at a cost of $8,494. Engi-
neering and design in connection with the above was accomplished
by hired labor at a cost during the fiscal year of $23,211. The
total cost for the year was $31,705.
   Unit L 400: Design Memorandum No. 1 for Underseepage Con-
trol on Unit L 400 was completed and approved. The total cost for
the year was $17,248.
  The preparation of detailed project plans for Units L 289, L 330,
           FLOOD CONTROL--KANSAS      CITY, MO., DISTRICT         801
L 385, L 392, R 395, L 408, 408.2, L 426, L 434.5, L 435, L 455,
R 471, and general engineering on the remaining units was under-
way, by hired labor, at a cost during the fiscal year of $48,792. The
total cost during the fiscal year for the Missouri River agricultural
levees project (including pending adjustment of $2,882) was
$553,832.
   Condition at end of fiscal year. The existing project was about
10 percent complete at the end of the fiscal year based on the
present estimated cost. Construction of the project was initiated
in June 1948 with the start of construction of levees for Unit L 488.
   During April 1952 there occurred a flood which overtopped or
breached all privately constructed farm levees from Rulo, Nebr., to
Kansas City, Mo., and damaged approximately 60 percent of those
from Kansas City to the mouth. This flood exceeded all floods
occurring during the past century in the reaches above Leaven-
worth, Kans. The only levees in the Kansas City to Rulo section
that did not fail during this April 1952 flood were the seven levee
units constructed by the Corps of Engineers under the Missouri
River agricultural levees project. The status of individual units of
the project at the end of the fiscal year was as follows:
   Unit L 519-L 512-L 504: The preparation of definite project
plans and contract plans and specifications was underway.
   Unit R 513-R 512: Definite project plans and contract plans and
specifications for the construction of levees have been completed.
The construction of 8.6 miles of levee in section I of this unit and
of 8 miles of levees in section II of this unit has been completed.
The construction of 2.5 miles of levees in the Mooney drainage ditch
section has been completed. Surfacing of levees and channel clear-
ing is also completed.
   Unit R 500: Definite project plans and contract plans and speci-
fications for construction of levees have been completed. The
construction of 4.1 miles of levees, including surfacing and slope
protection for this unit was completed.
   Unit L 497: The preparation of definite project plans and con-
tract plans and specifications was underway.
   Unit L 488: Definite project plans and contract plans and speci-
fications for the construction of levees have been completed. The
construction, surfacing, and seeding of 11.5 miles of levees in this
unit have been completed. The preparation of the Design Mem-
orandum and plans and specifications for underseepage control was
underway.
   Unit R 482: Definite project plans and contract plans and speci-
fications for the construction of levees have been completed. The
construction of 8.3 miles of levees, including underseepage control
in this unit, was completed. Surfacing, slope protection, modifica-
tion of drainage structures, and installation of piezometer tubes
is completed.
   Unit L 476: Definite project plans and contract plans and specifi-
cations for the construction of levees have been completed. The
construction of 6.7 miles of levees, including surfacing in this unit,
has been completed. Levee raising, slope protection, and installa-
tion of piezometer gauges is completed. Revision of Design Mem-
orandum No. 1 for Underseepage Control was completed.
   Unit L 448-L 443: The construction of 8.3 miles of levee to pro-
802          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

tect section I of this unit, and construction of 5.8 miles of levee to
protect section II of this unit, including slope and toe protection,
is completed. The construction of Cloverdale Drain levees is com-
plete. Levee raising, surfacing, and seeding was completed. The
Design Memorandum No. 1 for Underseepage Control was com-
pleted.
   Unit R 440: The construction of 9.6 miles of levees in this unit,
including surfacing, has been completed. Design Memorandum
No. 1 for Underseepage Control, plans and specifications for under-
seepage control and Doniphan Creek diversion were completed.
The construction of underseepage control is underway.
   Unit L 400: Definite project plans and contract plans and specifi-
cations were completed. Design Memorandum No. 1 for Under-
seepage Control was completed.
   Unit L 330: The contract for expert engineering services in con-
nection with surveys for design of levee is completed.
   Units L 455, L 435, 434.5 (bridge), L 426-419, 408.2 (bridge),
L 408, R 395-393, L 392, L 385, R 471-R 460-L 466 and R 289-R
272: Preliminary work in connection with the preparation of de-
tailed project plans was underway.
   The total cost of the existing project (all new work) to June 30,
1954, was $11,735,201.
                                   Cost and financial summary

                                         Fiscal year ending June 30                   Total to June
                                                                                      30, 1954, includ-
                                                                                      ing fiscal years
                            1950        1951        1952        1953       1954         priorto 1950

New work:
   Appropriated ------    $3, 611,350 $374,900   $1, 543,900   $319, 000   $75, 000       $12,955, 150
   Cost_---------------    4,545,105 2,260,800       536,605    913, 975   552, 832        11,735, 201


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954---------__ $1,134,247
    Appropriated for succeeding fiscal year ending June 30, 1955-.....   350, 000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955 ----------------------------------------           1,484,247
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project_ ------------------------------- 103,044,850
5. KANSAS CITYS ON MISSOURI AND KANSAS RIVERS, MO. AND
                         KANS.
   Location. Kansas Citys on Missouri and Kansas Rivers in
Missouri and Kansas. The municipal and industrial areas which
require flood protection extend from the mouth of the Kansas River
about 61/2 miles up and 91/2 miles down the Missouri River and
91/2 miles up the Kansas River.
   Existing project. The general plan of improvement contem-
plates protection works, consisting principally of levees and flood-
walls, for 13 separate project units, which are designated as fol-
lows: Argentine; Armourdale; Central Industrial; Fairfax-Jersey
Creek; North Kansas City; East Bottoms; channel improvement,
Kansas River; bridge and approach alterations, Kansas River;
channel improvement, Missouri River; floodway improvement, Mis-
souri River; Birmingham; Blue Valley Industrial; and Liberty
Bend cutoff.
                 FLOOD CONTROL--KANSAS CITY, MO., DISTRICT                                            803
   The existing project was authorized by the following Flood Con-
trol Acts:

     Acts                         Work authorized                                  Documents

June 22, 1936   Levees and floodwalls for the protection of the Kan-    H. Doec. 195, 73d Cong., 2d sess.
                 sas Citys, at an estimated construction cost not to
                 exceed $10,000,000, estimated cost of lands and
                 damages, $8,000,000.
Dec. 22,1944    Modified and extended the project to provide con-       H. Doc. 342, 78th Cong., 1st sess.
                 struction of cutoffs and protection for additional
                 areas at an estimated additional cost of $8,445,000.
July 24,1946    Authorized the Chief of Engineers to include neces-
                 sary railroad bridge and approach alterations as a
                 Federal responsibility.


   Recommended modification of project. Under date of April 29,
1954, there was introduced into the House of Representatives a
bill (H.R. 8951, 83d Congress, 2d Session) to authorize a modifica-
tion to the project adopted by the Flood Control Act of June 22,
1936, to provide flood protection for the Kansas Citys, Kansas and
Missouri, as modified and extended by the Flood Control Act of
December 22, 1944, to provide that the Chief of Engineers may
contribute not to exceed $2,750,000 to the cost of an alternate plan
of flood protection to be constructed by local interests in the lower
Armourdale area of the Kansas Citys project.
   The estimated cost (1954) is $51,440,000 of which $45,600,000
is the Federal cost and $5,840,000 is for lands and damages to be
borne by local interests.
   This project will be operated as part of the comprehensive plan
for the Missouri River Basin and it is contemplated that, with res-
ervoir control, substantially complete flood protection will be pro-
vided for the Kansas Citys. The units involve construction
approximately as follows:
   Argentine unit: The original levees and floodwalls built by pri-
vate interests were of sufficient height to protect the district from
the design flood, but to correct inadequate design and improper
materials used in constructing the levees it was originally planned
to strengthen the levees, install necessary facilities for control of
underseepage, and construct a pumping unit. Since the inade-
quacies of the original construction by private interests are being
corrected through proper design and selection of materials in the
emergency restoration necessitated by the flood of 1951, the levee
work formerly contemplated under this unit no longer will be re-
quired. However, studies subsequent to the flood of 1951 indicated
the necessity for constructing protection for the approaches to the
Argentine Boulevard and the West Kansas Avenue bridges.
   Armourdale unit: The earth levee along the left bank of the
Kansas River from mile 6.7 to mile 2.91 is of sufficient heights to
provide protection from the design flood. The project provides for
raising the existing levee from mile 2.9 to 2.8; 1 constructing a new
levee riverward of the existing floodWall from mile 2.8 to 1.7;1
replace existing floodwall with a new floodwall from mile 1.7 to
1;1 construct a new levee from mile 1 to 0.7;1 and construction of
new floodwall, including the replacement of a short section of exist-
  1Above mouth of Kansas River.
804,         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

ing wall from mile 0.7 to 0.3.1 The downstream end of the new
wall will connect with the southern terminus of the existing Fair-
fax District levee.
   Central Industrial unit: Beginning at the south end of the
Armour-Swift-Burlington Bridge over the Missouri River, mile
376.9,2 the existing and proposed protection for the district extends
upstream along the right bank of the Missouri River to the mouth
of the Kansas River, mile 378.8,2 a distance of 1.9 miles, and thence
upstream along the right bank of the Kansas River to mile 3.4,1 in
the vicinity of the Seventh Street Bridge, a total distance of 5.3
miles. The plan of improvement consists of the construction of
concrete floodwalls and earth levees to protect the portion of the
unit lying in the State of Missouri, and the raising of existing
structures and construction of new concrete floodwalls and earth
levees to protect the portion of this unit located in the State of
Kansas.
   Fairfax-Jersey Creek unit: About 30,900 feet of earth levee,
1,981 feet of concrete floodwalls, and 32,100 feet of bank-protection
works, extending along the right bank of the Missouri River from
a point immediately above the Kansas City, Kans., water and light
plant (mile 385.3)2 downstream to the mouth of the Kansas River,
thence along the left bank of the Kansas River to the vicinity of
the intercity viaduct (mile 0.3) ;1 pumping plants ; and appurtenant
works. Subsequent to the construction of the above work, the ele-
vation of the design flood has been raised due to a decrease in the
width of the floodway, necessitating the raising of the Fairfax-
Jersey Creek flood-protection works.
   North Kansas City unit: Beginning at a point northwest of the
Kansas City, Mo., municipal waterworks, the existing and proposed
protection for the unit extends downstream along the left bank of
the Missouri River for a distance of about 6.55 miles and opposite
approximately Missouri River mile 375; thence north along the
right bank of Rock Creek to the Wabash Railroad right-of-way, a
distance of about 0.8 mile; thence northwesterly along a drainage
ditch to high ground northeast of the Kansas City, Mo., municipal
waterworks, a distance of about 1.6 miles. The plan of improve-
ment consists of raising and realinement of existing levees and a
railroad embankment and the construction of new earth levees and
concrete floodwalls to protect the city of North Kansas City, Mo.,
and the municipal airport and waterworks for the city of Kansas
City, Mo. The total length of the proposed system is 9 miles.
   East Bottoms unit: Beginning at the south end of the Armour-
Swift-Burlington bridge over the Missouri River, mile 376.9,2 the
existing and proposed protection for the district extends down-
stream along the right bank of the Missouri River to the mouth of
the Big Blue River, thence southwesterly along the left bank of Big
Blue River to high ground. The proposed improvements will con-
sist of levees and a floodwall and appurtenances. The plan also
contemplates necessary rectification of the Big Blue River channel
near the mouth of this stream.
   Channel improvement, Kansas River unit: Bank-stabilization
SAbove   mouth of Kansas River.
2Above   mouth of Missouri River.
                FLOOD CONTROL-KANSAS CITY, MO., DISTRICT        805
works along:the right bank of the Kansas River from the Seventh
Street Bridge to the Kansas City Terminal Railway bridge (mile
3.50 to mile 2.491) ; excavation of a foreshore bar along the right
bank of the Kansas River, extending from the Kansas City South-
ern Railroad bridge (mile 0.84)1 to the mouth; and removal of
major obstructions from the bed of the main channel of the Kansas
River between the Argentine Bridge (mile 5.13)1 and the mouth.
   Bridge and approach alterations, Kansas River unit: In order to
permit the free passage of drift during flood periods, it is contem-
plated that all bridges across the Kansas River between mile 5.13
and the mouth which do not now provide adequate floodway will be
raised above the design flood profile. This would involve the per-
manent raising of 4 highway and 3 railroad bridges, and provision
of facilities for the temporary raising during flood periods of 3
other railroad bridges.
   Channel improvement, Missouri River unit: The work contem-
plated under this unit consists of dredging of a foreshore bar along
the left bank of the Missouri Riverin the vicinity of mile 377.5; and
of dredging the left bank where it extends riverward of the adopted
channel alinement in the vicinity of mile 374. 2 In addition, excava-
tion of the abandoned overbank area between the North Kansas
City levee and the present channel to approximately low water ele-
vation is contemplated. Replacement of the left-bank approach
fills to the Armour-Swift-Burlington and Hannibal bridges by ap-
proach spans is provided in the plans and is necessitated by the
widening of the Kansas City reach by setting back the North
Kansas City levee and dredging the abandoned overbank area.
   Floodway improvement, Missouri River unit: The work contem-
plated under this unit consists of removing brush and timber from
the area riverward of the existing Birmingham drainage district
levee along the left bank of the Missouri River between mile 370
and mile 363 and of removing brush from the area riverward of
the proposed East Bottoms levee along the right bank between
mile 373.5 and mile 367.8.2
    Birmingham unit: In order to provide protection to the Birming-
ham district, various upstream sections of the Birmingham levee,
between mile 371.7 and mile 365.5,2 will be raised by the addition'
of rolled fill and downstream sections will be strengthened.
   Blue Valley Industrial unit: The work contemplated under this
unit consists of the construction of levees and floodwalls at ap-
proximately present Big Blue River mile 5.4 to provide flood pro-
tection for a section of the Big Blue River Valley.
   Liberty Bend Cutoff: The work under this unit consists of the
construction of a main cutoff channel beginning at mile 363.7 and
extending downstream to mile 358.5;2 a second cutoff channel from
mile 358.5 to mile 357 ;2 and a new highway bridge where the main
cutoff channel intersects U. S. Highway No. 71 (bypass), which at
present crosses the Missouri River north of the proposed cutoff at
mile 361.2
    Local cooperation. The necessary assurances of cooperation
by local interests with respect to the Flood Control Act of June
I Above mouth of Kansas River.
2Above   mouth of Missouri River.
806           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

22, 1936, were approved by the Secretary of War as follows:
  Argentine; Armourdale; bridge and approach alterations,
Kansas River; Central Industrial (Kansas section); channel im-
provement, Kansas River; and Fairfax-Jersey Creek units, ap-
proved July 6, 1938.
  Central Industrial (Missouri section) and East Bottoms units,
approved March 22, 1941.
  North Kansas City unit, approved June 17, and June 20, 1941.
  Birmingham unit, approved December 11, 1945.
  New assurances of cooperation by local interests in compliance
with the further provisions of the Flood Control Act approved De-
cember 22, 1944, were approved by the Secretary of the Army on
April 23, 1946. Rights-of-way for the Central Industrial; channel
improvement, Kansas River; channel improvement, Missouri Riv-
er; Fairfax-Jersey Creek; East Bottoms; Armourdale; and North
Kansas City units of the projects have been furnished.
  Local interests have contributed a total of $616,165 for work
desired, but not required, to provide the protection authorized un-
der the project, as follows:
Unit                                                                                    Amount
Fairfax-Jersey Creek                                                                  $157, 940
                                                                                 .................
Central Industrial-..       . ....         ............                  ..   ..            9, 150
Armourdale..                  ..-----------------------------
                      -------------------....                                             19, 950
North Kansas City                           ----            ----------               222, 314
East Bottoms- ....... ............-                                                   206, 811
        Total --                  .-                                                  616, 165

   Operationsand results during the fiscal year. Operations under
this project consisted of the following:
  Argentine Unit: Construction by contract of (AT&SF) pumping
plant was completed at a cost during the fiscal year of $16,141;
surfacing levees and gating drainage outlets was completed at a
cost during the fiscal year of $31,952. Also, preparation of "as-
built" drawings and general engineering studies were continued at
a total cost of $978. The total cost for this unit during the fiscal
year was $49,071.
  Armourdale Unit: Construction, by contract, was continued on
the Osage Avenue pumping plant at a cost during the fiscal year
of $132,213; surfacing of levees was completed at a cost of $4,284;
and gating of outlet structures in the upstream portion was com-
pleted at a cost of $121,839. Engineering and design in connection
with the above, and general engineering studies applicable to all
units of the project were accomplished at a cost during the fiscal
year of $15,974. The total cost for this unit during the fiscal year
was $274,310.
  Birmingham Unit: Preparation of detailed project plans and
contract plans and specifications for levees in the portion of the unit
downstream from station 250+00 and for the underseepage for
the entire unit was completed, and general engineering studies ac-
complished at a total cost during the fiscal year of $38,577.
  Bridge and Approach Unit: Construction for the raising of East
Kansas Avenue Bridge was completed at a cost of $112,092 for the
fiscal year. Alteration of Missouri Pacific Bridge No. 72 across the
           FLOOD CONTROL-KANSAS       CITY, MO., DISTRICT        807
Kansas River was completed this fiscal year at a cost of $41,374.
Engineering and design, and general engineering studies on the
above was accomplished by hired labor at a cost of $2,133. The
total cost for the unit for the fiscal year was $155,599.
    Central Industrial Unit: Construction of toe and bank protec-
tion for the Kansas section and levee surfacing, by contract, was
completed at a cost of $10,366. A contract for the construction of
the Turkey Creek sewer emergency gate has been awarded. Prep-
aration of detailed project plans and contract plans and specifica-
tions was accomplished during the fiscal year at a cost of $23,257.
The total cost for this unit during the fiscal year was $33,623.
    Channel improvement, Kansas River Unit: Removal of obstruc-
tions from the Kansas River channel, which consisted of 6,115
cubic yards of stone and concrete, 455 old piling and 710 tons of
miscellaneous metals was accomplished, by hired labor, by the
U. S. dredges Black, Campbell and Keokuk at a cost of $267,971.
Engineering and design incidental to the above and general engi-
neering studies were accomplished at a cost of $996. The total
cost during the fiscal year for this unit was $268,967.
    Channel improvement, Missouri River Unit: Construction, by
contract, of Part II, bank stabilization and channel excavation was
completed at a cost of $73,495; and extension of the A. S. B. and
the Hannibal bridges was initiated at a cost during the fiscal year
of $326,412. Engineering and design incidental to the above and
general engineering studies were accomplished during the fiscal
year at a cost of $4,058. The total cost of this unit during the
fiscal year was $403,965.
    East Bottoms Unit: Construction of toe and bank protection was
completed at a cost of $404,441. Engineering and design, and
general engineering studies in connection with the above work was
accomplished by hired labor at a cost of $5,548. The total cost for
thefiscal year for this unit was $409,989.
    Fairfax-Jersey Creek Unit: Construction, by contract, of pump-
ing plants F2, F3, F6, and F9 was continued through the fiscal year
at a cost of $321,226; raising existing protection was completed
and modification of existing protection at the upstream end of unit
was continued at a cost of $62,418; surfacing levees was completed
at a cost of $26,215; modification of pumping plants F1, F4, F5, F7,
and F8 was initiated at a cost of $189,354, and Jersey Creek sewer
and shutter gate were completed at a cost of $115,987. Engineer-
ing and design and general engineering studies were completed at
a cost of $58,702. The total cost for the unit during the fiscal year
was $773,902.
    Liberty Bend Cutoff Unit: Preparation of final records of land
acquisition was accomplished at a total cost of $174.
    North Kansas City Unit: Construction, by contract, of levees,
three pumping plants, and levee surfacing was completed during
the fiscal year at a cost of $158,245. Engineering and design and
general engineering studies was accomplished at a cost of $15,178.
The total cost for the unit during the fiscal year was $173,423.
    The total cost during the fiscal year for the Kansas Citys project
  (including contributed funds of $31,459 and pending adjustment
of $-3,238) was $2,609,822.
808      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

    Condition at end of fiscal year. The existing project was about
74 percent complete at the end of the fiscal year, based on the pres-
ently authorized estimated cost. Construction of the project was
started in April 1940 with the initiation of construction of levees
and incidental work in the Fairfax-Jersey Creek unit of the project.
    Argentine Unit: The inadequacies of the original construction of
the levees were corrected through proper design and selection of
materials in the emergency restoration, and the Santa Fe pumping
plant was restored under the emergency program. Surfacing and
gating of drainage outlets is complete, except for gating outlet at
station 248+17.
    Armourdale Unit: The construction of approximately 7,300
linear feet of levees and about 4,400 linear feet of floodwall to pro-
tect the section of this unit from Kansas River mile 2.84 down-
stream to mile 0.30 was completed. A contract for the construc-
tion of the Osage Avenue pumping plant is 98 percent complete.
Surfacing of levees and gating of drainage outlets for upstream
portion is complete.
    Birmingham Unit: Raising and strengthening the levees up-
stream from station 250+00 in the vicinity of Missouri River mile
365.5 have been completed. Preparation of contract plans and
specifications for the downstream portion of the levees and under-
seepage control for the upstream portion is complete.
    Blue Valley Industrial Unit: Detailed project plans and interior
drainage studies have been completed.
    Bridge and approach alterations, Kansas River Unit: The James
Street, Central Avenue, Kansas City Southern Railway, and Kansas
City Stock Yards Co. bridges have been raised. Construction to
provide lifting facilities for the Chicago, Rock Island & Pacific and
Union Pacific Railroad bridges has been completed. Contract plans
and specifications for the raising of the other bridges, except the
Kansas City Terminal Railway bridge, have been substantially
completed. Contracts for raising the East Kansas Avenue Bridge
and the Missouri Pacific Railroad bridge No. 72 are complete.
    Central Industrial Unit--Missouri section: The floodwalls, lev-
ees, and the pumping plants to protect this section of the central
industrial unit have been completed. The improvements to protect
this section consist of 7,812 linear feet of floodwalls and appur-
tenances, 429 linear feet of earth levee to full grade and section,
429 linear feet of revetment of levee slope, a new pumping plant,
and an addition to another pumping plant.
    Central Industrial Unit-Kansas section: The construction of
levees, floodwalls, and pumping plants to protect this section of the
unit have been completed. Bank and toe protection is complete.
The improvements to protect this section consist of approximately
  9,266 linear feet of levee, 772 linear feet of new floodwall, raising
  8,586 linear feet of existing floodwall, and underseepage control
  system, two pumping plants, and an addition to another pumping
plant.
     Channel improvement, Kansas River unit: The stabilization of
  the right bank of the Kansas River from the Seventh Street Bridge
  to the Kansas City Terminal Railway bridge and the removal of a
foreshore bar at the mouth of the Kansas River have been com-
            FLOOD CONTROL---KANSAS       CITY, MO., DISTRICT          809
pleted. This work consisted of the excavation and disposition of
361,013 cubic yards of material in connection with the removal of
the foreshore bar, and removal of 14,255 cubic yards of objection-
able material, placement of 34,047 cubic yards of earth fill, 25,426
tons of stone, and 4,149 squares of bank paving in connection with
bank stabilization. Removal of obstructions was accomplished by
hired labor.
    Channel improvement, Missouri River unit: Construction of part
I of this unit, which consists of 2,106,630 cubic yards of random
and impervious fill, 318 square yards of surfacing, 195,290 tons of
stone for filter blanket, riprap, rockfill toe and rockfill dikes, 237,220
pounds of reinforcing steel, 16,845 pounds of miscellaneous metals,
270 linear feet of fencing is complete. Extensions of the Hannibal
and A. S. B. bridges are 53 percent complete. Channel excavation
by contract is complete.
    Construction by contract of bank stabilization, part II, is com-
plete. This work consisted of excavation of 337,999 cubic yards
of material, removal of 771 cubic yards of obstruction and wood
piling, placement of 36,203 tons of riprap and rockfill toe.
   East Bottoms unit: The construction of about 46,200 linear feet
of levee and 1,750 linear feet of floodwall and appurtenances was
initiated in April 1948 and has been completed. The construction
of six pumping plants is complete. Surfacing of levees and slope
and toe protection, except at the new Paseo Bridge, has been com-
pleted.
   Fairfax-Jersey Creek unit: This unit has been completed except
for the raising of levees and floodwalls, completion of the under-
seepage control system, and construction of additional pumping
plants; the original levees and floodwalls were completed in May
and June 1941. Three pumping plants were constructed subse-
quent to completion of the levees and floodwalls, and construction
of four additional pumping plants is underway. Completed work
included the construction of 30,900 linear feet of earth levees, a
levee drainage system, approximately 14,974 squares of founda-
tion and toe-protection mattress, 30,881 squares of revetment-
paving, 965 linear feet of steel sheetpile wall, and 1,981 linear feet
of floodwalls. Partial installation of an underseepage control sys-
tem has also been completed. Construction, by contract, for the
raising of the levees, the Jersey Creek sewer, the Jersey Creek
sewer shutter gate, stoplog gap, emergency gates, and stage III
underseepage control is complete. The modification of five pump-
ing plants is underway.
   Liberty Bend Cutoff unit: The construction of a new highway
bridge, excavation of 2 cutoffs, relocation of 2 pipelines, construc-
tion of levees along both banks of the upper cutoff and the con-
struction of approximately 5,000 linear feet of revetment along
the left bank of the upper cutoff have been completed. The con-
struction of 9,994 linear feet of revetment to divert the river
through the new channel and protect the right bank of the lower
cutoff, and an extension to the Liberty, Mo., sewer system have
also been completed.
   North Kansas City unit-airport section: The airport section is
that portion of the North Kansas City unit lying west of and up-
810          REPORT OF CHIEF OF ENGINEERS, U: S. ARMY, i1954

stream from the Hannibal Bridge on the left bank of the Missouri
River. Approximately 20,200 linear feet of levees, including stop-
log and sandbag gaps and appurtenances, 19,800 linear feet of
levee slope and bank protection, 552 linear feet of floodwall, and
160 linear feet of retaining wall were completed in October 1947.
The installation of underseepage wells, installation of additional
pumping capacity in one pumping plant, and installation of a col-
lector system for the underseepage control system have also been
completed.
   North Kansas City unit--lower section: The lower section of the
North Kansas City unit is that portion of the unit lying east of
and downstream from the Hannibal Bridge. Raising and relo-
cating existing levees and construction of three new pumping
plants have been completed.
   The total cost, all new work, of the existing project to June 30,
1954, was $34,222,172, exclusive of contributed funds of $616,165.
                                   Cost and financial summary
                                        CONSOLIDATED FUNDS


                                             Fiscal year ending June 30                           Total to June
                                                                                             -   30, 1954, includ-
                                                                                                 ing fiscal years
                           .1950            1951         .1952           1953         1954        prior to 1950

New work:
   Appropriated-__   -   $5, 000,000     $6, 775,237   $8,887,250    -$418, 000      -$2, 686         $39, 165, 265
   Cost---------------    5, 924, 930     2,237,424     3,394, 588    3, 667, 544   2,609,822          34,222,172


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954__-------        $4, 175, 106
    Unobligated balances available for Succeeding fiscal year ending June
      30, 1955_ -------------------------------------------                4,175, 106
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project      _      -          ---------            7,050,900
6. HARLAN COUNTY RESERVOIR, MISSOURI RIVER BASIN, NEBR.
   Location. The dam site for the Harlan County Reservoir is
located on the main stem of the Republican River approximately
235 miles above the confluence of the stream with the Smoky
Hill River. The site is located in Harlan County, Nebr., about
3 miles east of Republican City, Nebr., and 13 miles west of
Franklin, Nebr.
   Existing project. The plan of improvement provides for the
construction of an earthfill dam, with a height of about 106 feet
above the streambed and a total length of 11,950 feet, including a
gate controlled concrete gravity type spillway section located near
the center of the dam. The reservoir will provide for 850,000 acre-
feet of storage, of which 500,000 acre-feet will be used for flood
control and 350,000 acre-feet for irrigation and sedimentation
allowance. The reservoir will control the runoff from approxi-
mately 83 percent of the drainage area of the Republican River
and would afford complete control for all floods of record.
   It is contemplated that the Harlan County Reservoir will be
operated to provide protection from floods on the Republican River
to small communities and agricultural land lying within the flood
plain below the dam and in combination with proposed reservoirs
            FLOOD CONTROL--KANSAS      CITY, MO., DISTRICT         811
to be located on other major tributaries of the Kansas River to
reduce flood heights at the Kansas Citys. The reservoir will also
be operated to provide storage for the irrigation of 86,700 acres of
land below the dam. This project is one unit of the general com-
prehensive plan for flood control and other purposes in the Mis-
souri River Basin authorized by the Flood Control Act, approved
June 28, 1938 (Flood Control Committee Doc. 1, 75th Cong., 1st
sess.), as modified by the Flood Control Act, approved August 18,
1941 (H. Doc. 842, 76th Cong., 3d sess.), to include this project,
and expanded by the Flood Control Act, approved December 22,
1944 (H. Doc. 475, and S. Does. 191 and 247, 78th Cong., 2d sess.).
    The estimated cost (1954) is $45,268,000, of which $41,410,500
is for construction, and $3,857,500 is for lands and damages.
    Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
    Operations and results during the fiscal year. New work: All
work in connection with the relocation of Republican City, a por-
tion of Alma, Nebraska, Oberlin Branch of the C. B. & Q. Railroad,
county roads, Federal and state highways, long distance telephone
lines, and rural power lines and sale of salvaged railroad materials
was accomplished, by contract, at a cost during the fiscal year of
$17,716. The construction of access roads within the reservoir
area was initiated, by contract, at a total cost during the fiscal year
of $35,381. Surplus materials remaining from construction of the
spillway were disposed of at a credit of $34,896. Buildings and
structures on land acquired for construction of the project were
disposed of during the fiscal year at a net credit of $7,342. Con-
struction, by hired labor, during the fiscal year consisted of the
following: clearing and seeding an area near Alma, Neb., and
planting and cultivation of trees and shrubs, at a cost of $7,435;
construction of a ramp for Government boats, marine storage shed,
wood barriers, wood and metal information signs, seeding areas
near the dam, and other miscellaneous items at a cost during the
fiscal year of $15,796; drilling water supply well and procurement
of picnic tables and refuse cans, at a cost during the fiscal year of
$669. Engineering and design in connection with the above work
and preparation of plans for future construction were accom-
plished, by hired labor, at a cost during the fiscal year of $53,431.
The total cost for new work during the fiscal year (including pend-
ing adjustment of $-146) was $88,044.
   Maintenance. This work consisted of operation, maintenance,
and rehabilitation of the project, by hired labor, at a cost during
the fiscal year of $107,161.
   The total cost for the fiscal year was $195,205 ($88,044 for new
work and $107,161 for maintenance).
   Condition at end of fiscal year. Construction of the project
was initiated in August 1946. The project was approximately 99
percent complete at the end of the fiscal year.
   Construction of the embankment and spillway is completed.
This work consists primarily of the excavation of 16,795,291 cubic
yards of material, the placing of 9,948,186 cubic yards of imper-
vious fill, 431,276 cubic yards of random fill, 1,236,130 cubic yards
of pervious fill, and 1,536,114 cubic yards of berm fill in the em-
812            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

bankment and levees, and placement of 445,484 cubic yards of con-
crete, 177 linear feet of clay pipe, 4,030 gallons of asphalt, and
4,295,606 pounds of reinforcing steel and 4,188,392 pounds of mis-
cellaneous metals in the spillway. Temporary bridges constructed
across the Republican River and the spillway approach channel
have been removed. The relocation of 32 miles of railroad is com-
plete, and the relocation of about 48 miles of Federal and State
highways have been completed. Relocation of cemeteries and
county roads has been completed. Relocation of rural power and
gas lines and electrical distribution facilities have been completed.
Removal of abandoned railroad line has been completed. Reloca-
tion of Republican City and a portion of Alma, Nebr., has been
completed. Clearing of the reservoir area has been completed.
   The acquisition of 31,766 acres of land for the dam and reservoir
and for the relocation of railroad lines and county roads has been
completed. The procurement of a standby generator, construction
of two permanent residences, and an administration building have
been completed. The construction of an access road and facilities
for health and safety are complete. The total cost, all new work,
of the existing project to June 30, 1954, was $45,132,575 ($44,991,-
119 for new work excluding materials valued at $24,198 that were
received without charge to project funds, and $141,456 for main-
tenance).
                                       Cost and financial summary

                                                     Fiscal year ending June 30                           Total to June
                                                                                                         30, 1954, includ-
                                                                                                         ing fiscal years
                               1950                 1951        1952           1953           1954         priorto 1950

New work:
   Appropriated      --   $11, 250,000 $15, 475, 575         -$215,975      -$276, 000     -$373, 000       $45, 268, 000
   Cost_                   16, 163, 697  7, 876,938           4, 737, 607    1, 464, 592      *88, 044       44, 991,119*
Maintenance:
   Appropriated..-               ------------                                   50,000        110,000            160,000
   Cost                                -        -                               34,295        107,161            141,456


  * Excludes cost of materials furnished without cost valued at $24,198.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954---_--------     $266,919
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955----------        ---------- ------------------------ 266,919

   7. KANOPOLIS             RESERVOIR,                     MISSOURI           RIVER         BASIN, KANS.
   Location. The Kanopolis Dam site is located on the Smoky
Hill River about 19 miles west and 16 miles south of Salina, Kans.,
and is approximately 205 river miles above the mouth of the
stream.
   Existing project. The plan of improvement provides for the
construction of an earthfill dam, with a height of about 131 feet
above the streambed and a total length of 15,400 feet, including
4,300 feet of dike section on the left abutment and 2,600 feet of
dike section on the right abutment. The reservoir will provide a
storage capacity of 450,000 acre-feet, of which 400,000 acre-feet of
capacity is for flood control and 50,000 acre-feet for recreation and
streamflow regulation. The outlet works and spillway are located
in the right abutment. The reservoir will control approximately
            FLOOD CONTROL-KANSAS CITY, MO., DISTRICT              813
95 percent of the drainage area of the Smoky Hill River above
Salina, Kans.
    It is contemplated that the Kanopolis Reservoir will be operated
in combination with proposed reservoirs to be located on other ma-
jor tributaries of the Kansas River. The primary purpose of the
project is flood control for municipal and agricultural areas along
the Smoky Hill and Kansas Rivers, with incidental benefits in re-
ducing Missouri and Mississippi River flood stages.
    This project is one unit of the general comprehensive plan for
flood control and other purposes in the Missouri River Basin au-
thorized by the Flood Control Act approved June 28, 1938 (Flood
Control Committee Doc. 1, 75th Cong., 1st sess.), as modified by
the Flood Control Act of August 18, 1941, and expanded by the
Flood Control Act approved December 22, 1944 (H. Doc. 475, and
S. Docs. 191 and 247, 78th Cong., 2d sess.).
    The estimated cost (1954) is $12,297,000, of which $10,882,000
is for construction, and $1,415,000 is for lands and damages.
    Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
    Operations and results during fiscal year. New work: The
cost of acquisition of flowage easements for spillway discharge for
the fiscal year was $48,864. Engineering and design for the fol-
lowing work was accomplished during the fiscal year at a cost of
 $13,622. Stabilization of roads, Stage 2, was initiated by contract
at a cost during the fiscal year of $4,216. The construction of a
permanent warehouse, and modification of the water supply system
were completed by contract, at a cost during the fiscal year of
 $38,175.
    Operations by hired labor consisted of the following: Planting
trees and shrubs, repaving of outlet channel; construction of a
service road on the downstream berm, and boat ramps; procure-
ment and installation of information signs; installation of a stand-
by ventilator; construction of a permanent septic tank; modifica-
tions to existing water system; and electrical service to the pump
house, at a cost during the fiscal year of $20,788.
    The total cost for the fiscal year for new work, including pending
adjustment of $394, was $126,059.
    Maintenance: This work consisted of the operation of the proj-
ect and maintenance and rehabilitation of the project, by hired
labor, at a cost during the fiscal year of $89,636.
    The total cost for the fiscal year was $215,695 ($126,059 for
new work and $89,636 for maintenance).
    Condition at end of fiscal year. Construction of the project was
initiated in June 1940. The project was approximately 99 percent
complete at the end of the fiscal year based on the estimated cost of
completion, the dam and spillway being completed and ready for
use in May 1948. The acquisition of easements at dam site, and
land for the dam site and reservoir area, has been completed. The
relocation of roads has been completed. Construction of the diver-
sion works has been completed. Construction of the diversion
works involved the excavation of 248,955 cubic yards of material
and the placement of 17,791 cubic yards of backfills and embank-
ment, 2,061,285 pounds of reinforcement steel, 1,270,448 pounds
of steel bracing, and 22,158 cubic yards of concrete. Construction
of the dam and excavation of the spillway have involved the ex-
cavation of 19,725,320 cubic yards of material, the placement of
814            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

2,067,368 cubic yards of pervious fill, 5,302,322 cubic yards of
random fill, 4,664,181 cubic yards of impervious fill, 2,072,696
cubic yards of fill in the upstream blanket, 1,025,196 cubic yards
of fill in the downstream berm of the embankment, 239,575 cubic
yards of sand and gravel filter and riprap on the upstream slope of
the embankment, the placement of 899,856 pounds of reinforce-
ment steel and bracing, and 10,060 cubic yards of concrete in con-
nection with construction of a sill in the spillway and drainage
gutters on the downstream slope of the embankment, and spot
sodding and mulching 175 acres on the downstream slope of the
embankment. The installation of piezometer gages is complete.
The temporary Government field office, garage, warehouse, tem-
porary residences, and other miscellaneous buildings have been
completed. The administration building, permanent residence,
shelter house, and comfort station are complete. The installation
of a standby generator and construction of other miscellaneous
facilities, such as sedimentation and degradation ranges, access
roads, fencing, landscaping, forestation, planting, boat ramps, and
other public use facilities, is complete. The stabilization of the
surface of major access roads, a service road on the downstream
berm, and other minor public use facilities are underway.
   The total cost of the existing project to June 30, 1954, was
$12,693,113 ($12,252,743 for new work, excluding materials valued
at $7,885, that were received without charge to project funds, and
$440,370 for maintenance).
                                      Cost and financial summary

                                              Fiscal year ending June 30                    Total to June
                                                           ...       ._                     30, 1954, includ-
                                                                                            ing fiscal years
                               1950        1951        1952         1953         1954         priorto 1950


New work:
   Appropriated --------
                       $218, 000         1-$70, 000    $35, 000    $239, 500   -$50, 500         $12, 297,000
   Cost          ---    257, 355           126, 493     151, 712     68,124      126, 059         .12252, 743
Maintenance:
   Appropriated-        -      55,000       82, 500     79,000       90 000      93, 000             451,500
   Cost_                       55, 879      86,135      77,332       83,909      89, 636             440, 370


1 Funds   in the amount of $70,000 of a total of $270,000 previously revoked were retained by OCE.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_------------        $43,803
    Unobligated balances available for succeeding fiscal year ending June 30,
    1955_-                                                                     43,803

8. TUTTLE CREEK RESERVOIR,                            MISSOURI RIVER BASIN, KANS.
   Location. The proposed dam site for the Tuttle Creek Reser-
voir is located on the main stem of the Big Blue River, approxi-
mately 12 miles above the mouth of the stream in Riley and Potta-
watomie Counties, Kans. The site is about 12 miles northwest of
Manhattan, Kans.
  Existing project. A preliminary plan of this project provides
for a dam approximately 7,200 feet long to be constructed ap-
proximately 135 feet high. This project is one unit of the general
comprehensive plan for flood control and other purposes in the
               FLOOD CONTROL-KANSAS CITY, MO., DISTRICT

Missouri River Basin authorized by the Flood Control Act approved
June 28, 1938 (Flood Control Committee Doc. 1, 75th Cong., 1st
sess.), as modified by the Flood Control Act approved August 18,
1941, and expanded by the Flood Control Act approved December
22, 1944 (H. Doc. 475, and S. Does. 191 and 247, 78th Cong., 2d
sess.). The estimated cost (1954) is $89,900,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. Construction of the
outlet works conduits, first stage of embankment and spillway ex-
cavation, and a temporary construction bridge across the river
channel was completed, by contract, at a cost during the fiscal year
of $1,014,980.
   Expenses in connection with closing and recordations on land
acquired, and settling resettlement cases total $14,625 for the
fiscal year.
   Engineering and design in connection with work underway and
preparation of contract plans and specifications for future con-
struction was continued by hired labor at a cost during the fiscal
year of $125,342.
   The total cost for the fiscal year, including pending adjustment
of $-188, was $1,154,759.
   Condition at end of fiscal year. Construction of the project
was initiated on October 7, 1952, and construction of the outlet
works conduits and the first stage embankment and spillway exca-
vation was started.
   The acquisition of 4,402 acres of land has been completed. Con-
struction of temporary bridge and administrative facilities and
parking areas, and installation of radio facilities have been com-
pleted. Work in connection with construction of the outlet works
conduit and first stage embankment and spillway excavation con-
sisted of placement of 1,446,106 cubic yards of embankment;
excavation of 1,793,329 cubic yards of material for the spillway
and outlet works; and placement of 17,355 cubic yards of concrete,
1,208,386 pounds of reinforcement steel, and placement of 2,114
cubic yards of riprap. Work at the site was suspended in Decem-
ber 1953 due to non-appropriation of additional funds.
   The total cost of the existing project, all new work, at the end
of the fiscal year was $4,922,635.
                                   Cost and financial summary

                                                    Fiscal year ending June 30                     Total to June
                                                                                                  30, 1954, Includ-
                                                                                                  ing fiscal years
                           1950            1951              1952          1953         1954       prior to 1950


New work:
   Appropriated .                                           $561, 395   $4,975,000   -$615,700          $5, 131, 780
   Cost._--------- -----      ..   ---------   ..            366, 910    3,169,019    1,154,759          4,922, 635


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-............      $187,630
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955------------------------------------        ---------------    187,630
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project---                                   -     84,766.220
816       REPORT OF CHIEF OF ENGINEERS. U       S. ARMY. 1954

                 9. TOPEKA, KANSAS RIVER, KANS.
    Location. This project is located on the right and left banks of
the Kansas River at Topeka, Kans.
    Existing project. The plan of improvement provides for the
raising and extending of existing levees and the construction of
new levees and floodwalls, consisting of the following features:
7,200 feet of earth levee, 2,016 feet of concrete floodwall, and 6,350
feet of bank protection works, along the right bank of the Kansas
River, extending from the Chicago, Rock Island & Pacific Rail-
road bridge over Ward Creek to high ground upstream from the
Atchison, Topeka & Santa Fe Railroad bridge; 1,662 feet of flood-
wall and 943 feet of levee around the municipal waterworks; about
5,120 feet of bank protection works along the left bank of the Kan-
sas River; 23,175 feet of levee and 700 feet of floodwalls around
North Topeka; and numerous appurtenant features. The project
when completed will provide protection to North Topeka, South
Topeka (between Ward Creek and the Atchison, Topeka & Santa
Fe Railroad shops), and the municipal waterworks, against a flood
equivalent to that of 1903. The existing project was authorized
by the Flood Control Act approved June 22, 1936 (H. Doc. 195,
73d Cong., 2d sess.). The estimated Federal cost of construction
of the modified plan, revised in 1954, is $3,100,000, and the esti-
mated non-Federal cost of lands and damages is $481,400 to be
borne by local interests.
    Recommended modification of project. Under date of Febru-
ary 28, 1949, the Chief of Engineers recommended that the existing
project be modified and expanded to provide protection to addi-
tional areas in and around North Topeka, Kans. The modified plan
of improvement contemplates relocation of the channels of Soldier
and Half Day Creeks to improve drainage conditions, raising of
existing levees, and construction of new levees along the Kansas
River and Soldier and Half Day Creeks to protect approximately
6,000 acres of land in the flood plain, and construction of pumping
plants. House Resolution 4997, 82d Congress, 2d session, proposed
authorization of these improvements, together with other im-
provements in the Kansas River Basin recommended in House
Document 642, 81st Congress, 2d session.
   Local cooperation. The conditions of local cooperation have
been fully complied with except for the North Topeka unit.
   The city of Topeka has furnished certified copies of a court order
dismissing the litigation that resulted in the curtailment of con-
struction of the North Topeka unit of the project in February 1940
after a suit was brought against the city of Topeka and others to
enjoin construction of the North Topeka flood protection works.
Acquisition proceedings with respect to rights-of-way for the
North Topeka unit were essentially completed by local interests
prior to curtailment of the project. Local interests have indicated
an intense interest in early construction of the project. The city
of Topeka has contributed to the United States a net sum of $7,-
659.31 to defray the cost of incidental features of construction at
the city waterworks, desired by the city but not required for
adequate flood protection.
                         FLOOD CONTROL-KANSAS CITY, MO., DISTRICT                                                             817
   Operations and results during fiscal year. Engineering studies
were continued by hired labor at a cost of $26.
   Condition at end of fiscal year. The existing project was ap-
proximately 25 percent complete at the end of the fiscal year. The
work accomplished consists of the removal of objectionable mate-
rial and placing of 174,569 cubic yards of earthfill in an earth
levee; construction of 2,016 linear feet of concrete flood wall, 6,421
linear feet of bank paving, 2,600 linear feet of waterworks protec-
tion, 3 protection enclosures at the waterworks, 1 floodgate, 9 sewer
outlet extensions, and appurtenant features; and seeding of levees.
   The work remaining to be done to complete the existing project
consists of the construction of the North Topeka unit. Commence-
ment of this work was postponed indefinitely in February 1940
after a suit was brought against the city of Topeka and others to
enjoin construction of the North Topeka flood-protection works.
The city of Topeka has furnished evidence that the litigation has
been settled and has requested that construction of the modified
plan (H. Doc. 642, 81st Cong., 2d sess.) be initiated at an early
date.
   The total cost of the existing project, all new work, at the end
of the fiscal year was $755,510 including $7,659 from contributed
funds.

                                                     Cost and financial sunmmary

                                                                     Fiscal year ending June 30                      Total to June
                                                                                                                    30, 1954, includ-
                                                                                                                    ing fiscal years
                                            1950                   1951        1952         1953        1954         prior to 1950

New work:
   Appropriated ............------..------------....-----............             000  -$50, 000
                                                                               $-------70,            -$10, 300            *$755, 529
     Cost.....              -----                ---............   .--.   .      7, 933       1,722            26           *755,510

  * Includes $7, 659 contributed fund.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-_------------         $19
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955___                                                                19
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project      _                                     2,352,130
                                              10. CHARITON RIVER, MO.

  Location. The Chariton River rises near Osceola in south
central Iowa and flows in easterly and southeasterly directions ap-
proximately 140 miles to the Iowa-Missouri State line, thence south
approximately 138 miles to its confluence with the Missouri River
about 7 miles above Glasgow, Mo. The drainage basin of the
Chariton River is approximately 150 miles long and 25 miles wide.
  Existing project. The plan of improvement in general con-
templates drainage and protection works consisting principally of
the construction of levees, clearing and enlarging of the river chan-
nel, and the construction of cutoffs and drainage ditches for three
project units, which are designated as follows: Chariton County
unit, Macon-Adair Counties unit, and Reinhart Ranch Channel cut-
off unit. The existing project was authorized by the Flood Con-
818           REPORT OF CHIEF OF ENGINEERS, U:. S. ARMY, 1954

trol Act approved December 22, 1944 (H. Doc. 628, 78th Cong.,
2d sess.).
    The estimated cost of the project, revised in 1954, is $3,561,000,
of which $3,400,000 is Federal cost for construction and $181,000
is the cost of lands and damages to be borne by local interests. The
units involve construction approximately as follows:
    Chariton County unit: The plan of improvement provides for
cutoffs, clearing, and enlarging the existing channel of the Chari-
ton River and construction of tieback levees along both banks of
this river.
    Macon-Adair Counties and Reinhart Ranch units: The plan of
improvement provides for cutoffs and clearing and enlarging the
existing channel of the Chariton River.
    Local cooperation. All rights-of-way for construction of chan-
nel improvement works have been furnished. Rights-of-way for
levee construction are being obtained.
    Operations and results during fiscal year. A short section of
channel was improved and a channel block replaced, by hired labor,
at a total cost during the fiscal year of $465. Engineering and de-
sign in connection with the above, and definite design studies in
connection with construction of tie-back levees along the new
channel of the Chariton River near the mouth were accomplished,
by hired labor, at a cost during the fiscal year of $12,924. The
total cost during the fiscal year, including pending adjustments of
 $135 was $13,524.
    Condition at end of fiscal year. Construction of the project
was initiated in February 1948. The project was 32 percent com-
plete at the end of the fiscal year based on the present approved
working estimate. The construction of cutoffs, enlarging, and
clearing the Chariton River channel from mile 13.6 to the mouth
and the construction of revetment and bank protection at the
mouth was completed. The construction of cutoffs, enlarging, and
clearing of the Chariton River channel from mile 13.6 to 19.9 in
upper Chariton County unit was completed. The construction of
ditches, cutoffs, and enlarging and clearing of the Chariton River
channel in the Macon-Adair Counties and Reinhart Ranch units
was completed. Engineering and design for construction of tie-back
levees along the new channel near the mouth was underway. The
total cost, all new work, of the existing project to June 30, 1954,
was $1,099,936.
                                    Cost and financial summary


                                             Fiscal year ending June 30                   I Total to,
                                                                                                    June
                                                                                          30, 1954,   includ-
                                                                                          ing fiscal years
                             1950          1951        1952         1953        1954        priorto 1950


New work:
   Appropriated-.....                  1$400,000
                                         -$428,000    $111,000 -               -$6,588           1,146, 412
   Cost ----------------     167,707        129,640    255,908      $66,I281     13,524          1,099,936

1 Funds in the amount of $428,000 (of a total of $760,000 previously revoked) were retained by Office.
Chief of Engineers.
             FLOOD CONTROL-KANSAS            CITY, MO., DISTRICT              819
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_--_---------      $46,476
    Unobligated balances available for succeeding fiscal year ending June
    30, 1955 ------------------------------------------------                46,476
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project-_                              _ _-_-_-  _ 2,253,588

11. POMME DE TERRE RESERVOIR, MISSOURI RIVER BASIN, MO.
    Location. The proposed dam site for the Pomme de Terre Res-
ervoir is located on the main stem of the Pomme de Terre River,
approximately 38 miles above the mouth of the stream in Hickory
County, Mo., the reservoir extending upstream into Polk County,
Mo. The site is about 3 miles south of Hermitage, Mo., and 37
miles east and north of Lebanon, Mo.
   Existing project. A preliminary plan of this project provides
for a dam about 3,570 feet long to be constructed to an elevation
approximately 137 feet above the river bed. This project is one
unit of the general comprehensive plan for flood control and other
purposes in the Missouri River Basin, authorized by the Flood Con-
trol Act approved June 28, 1938 (Flood Control Committee Doc. 1,
75th Cong., 1st sess.), as modified by the Flood Control Act ap-
proved August 18, 1941, and expanded by the Flood Control Act
approved December 22, 1944 (H. Doc. 475, and S. Does. 191 and
247, 78th Cong., 2d sess.).        The estimated cost (1954) is
$22,500,000.
   Recommended modification of project. Under date of August
15, 1949, the Chief of Engineers recommended that the general
comprehensive plan for flood control and other purposes in the
Missouri River Basin be modified and expanded to include addi-
tional construction (H. Doc. 549, 81st Cong., 2d sess.). The addi-
tional construction recommended included the provision for power
generating facilities along with the provision for construction of
other projects.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. Advance engineer-
ing and design in connection with preparation of contract plans
and specifications for the initial contracts for construction of the
project was continued, by hired labor, at a cost during the fiscal
year of $70,127.
   Condition at end of fiscal year: Advance engineering and de-
sign for preparation of plans for the initial contracts for construc-
tion of the project is approximately 85 percent complete.
   The total cost of the existing project, all new work, at the end
of the fiscal year was $494,533.
820               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                              Cost and financial summary

                                                              Fiscal year ending June 30                                         Total to June
                                                                                                                                30, 1954, includ-
                                                                                                                                ing fiscal years
                                                                             1952          1953               1954                priorto 1950


                                                                            $307,300    -$140,000           -$7, 000                      $522, 502
                                                                             94,335         66,556            70,127                       494,533



Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954                  27 969
                                                                          $-------------
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955                   --                                        27,969
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project   -------------------------------- 21,977,498

                              12. TABLE OF INACTIVE PROJECTS

                                                                        For last        Cost to June 30, 1954                      Estimated
                                                                       full report                                                  amount
                     Name of project                                        see                                                     required
                                                                         annual           Con-           Operation                     to
                                                                          report       struction            and                    complete
                                                                           for-                         maintenance

                        Navigation

Gasconade River, Mo-...................              ......               1931            139, 003                85,077            (1)  (1) (s)
O sage R iver, M o., lock and d am _ .....         .....       ...._      1952            658, 076               850, 495             (1) (5)

                       Food control

Arlington Reservoir, Mo ........                              - 1948
                                                      ..------------                        8, 651 --------------                    27, 191, 349
Richland Reservoir, Mo_--._      .--.-          -__.__. -           1948                    8, 548 ..----------                      33, 291, 452
Osceola Reservoir, Mo---.....       --. --......-.-            -... 1948                  572, 545--------.-.                       115, 427, 455
Indianola, Nebraska...................-------------------------           1950             67, 275      .......--------------             (4)
Pioneer Reservoir, Missouri River Basin, Kansas                           1952             95, 692           ..........              19, 904, 308
Bartley, Missouri River Basin, Nebr.-------------                         1953            118, 269 --                                  (4)

  1 Improvement adequate for existing needs.
  2 Curtailment of project recommended in H. Doc. 467, 69th Cong., 1st sess.
  3 Project for maintenance only.
  'Completed.
   SOperation of lock and dam placed in standby status.

                                   13. GENERAL INVESTIGATIONS
   Examinations and surveys-flood control studies. Preliminary
examinations and survey reports were under preparation by hired
labor at a cost during the fiscal year of $43,461. Funds remaining
amounting to $42 plus the allotment of $35,200 will be applied dur-
ing the fiscal year ending June 30, 1955, to the continuation of
work on preliminary examinations and survey reports presently
assigned to this district.
   Collection and study of basic data. The collection of stream
flow and rainfall data, and flood damage investigations, were ac-
complished by hired labor at a cost during the fiscal year of $6,944.
                     14. INSPECTION                      OF COMPLETED PROJECTS
  Inspection of completed works was made during the fiscal year
in the Kansas City District on the following flood protection
projects:
                    FLOOD CONTROL---KANSAS CITY, MO., DISTRICT                                                         821
Project                                                                                                      Inspection cost
Missouri River Agricultural Levees           ---------------              -------------.................    . $2,043
Kansas City Flood Control Project--...-------..             ........-------------..............---
                                                                                             ---...............   1, 879
Chariton River, Missouri                                        .......................                              418
                                                                                       ................------------------------------
Topeka, Kansas...---------....           . -----
                                  -------..
                                   .                                            ... ................---------------------------
                                                                ..................                                   164
Stonehouse Creek, Kansas           .. ..........                             .............----------------------------------------
                                                                                                                     132
Seward, Nebraska....-----------...--....                                         ...................-------          151
Bartley, Nebraska..................                                                                                  204
                                                                                                  ..........----------------------------
Indianola, Nebraska ...-----------.. ..........................----------------------------------                    171
Mouth of Delaware River, Kansas ..--------------......                                                               111
                                                                                                 ........---------------------
Smoky Hill River, South of Solomon, Kansas...............................----------                                   85
Kansas River at Lawrence, Kansas--------.............        .......... ...............--------------------------     95
Republican River, near McCook, Nebraska ...... ----------------------------.                                         148

    The total cost during the year was $5,601.
                                         Cost and financial summary

                                                  Fiscal year ending June 30                                 Total to June
                                                                                                            30_ l.0 _innlnd-




    15. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
  Snagging and clearing of navigable streams and tributaries in
the interests of flood control. (Section 13 of the 1946 Flood Con-
trol Act.)
  No work was performed during the fiscal year.
                                         Cost and financial summary

                                                  Fiscal year ending June 30                                 Total to June
                                                                                                            30, 1954, includ-
                                                                                                            ing fiscal years
                                  1950          1951            1952                1953          1954        prior to 1950

New work:
    Appropriated-- ------        $12,000       -$7,945                              $6,000        -$2,687            $24,480
    Cost .        ---                 134         3, 920    .........------------    3, 313 ............              24,480



  Emergency bank protection (Section 14 of the 1946 Flood Con-
trol Act).
  Construction of bank protection on the right bank of the Kan-
sas River near Eudora, Kans., to protect the county highway bridge
approach was completed during the fiscal year at a cost of $48,103.

                                         Cost and financial summary

                                                 Fiscal year ending June 30
822          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Small flood control projects not specifically authorized by Con-
gress. (Section 212 of the 1950 Flood Control Act.)
   Costs were incurred on the following projects during the fiscal
year:
   Stonehouse Creek, Jefferson County, Kans.: Construction of a
levee along the left bank of Stonehouse Creek near Williamstown,
Kansas; extension of a bridge; and improvement of the channel
was initiated during fiscal year 1951 and completed during fiscal
year 1953 except for outstanding costs. Outstanding costs liqui-
dated during the fiscal year were $6.
   Seward, Big Blue River, Nebr.:, Construction of approximately
12,000 feet of levee, excavation of approximately 3,000 feet of cut-
off channel, and construction of drainage outlets was initiated dur-
ing fiscal year 1952. The project has been completed except for a
small amount of bank paving. Costs incurred during the fiscal
year were $7,839.
   Missouri River at New Haven, Mo.: Engineering and design in
connection with the preparation of contract plans and specifica-
tions for construction of about 2,260 feet of levee and other drain-
age improvements was initiated during fiscal year 1953 and com-
pleted this fiscal year. Costs incurred during the fiscal year were
$9,028.
   The total cost of work performed during the fiscal year was
 $16,873.
                                     Cost and financial summary

                                            Fiscal year ending June 30                    Total to June

                              1950        1951         1952        1953       1954        priorto 1950

New work:
   Appropriated_        .                $146, 700     $7, 000    $148,700    $192, 652         $445, 052
   Cost ------........ _ _------            8,664      88,813      171, 118     16.873           285,468


Other new work data: Unobligated balance, fiscal year ending June 30, 1955_ $159, 584
  Flood control emergenices-repairand flood fighting and rescue
work. (Section 210 of the 1950 Flood Control Act and supple-
mental authorizations.)
  The following work was performed during the fiscal year:
Descriptionof work                                                                Cost during fiscal year
Flood fighting and rescue work ..........-.......          ....                               . $27,
                                                                                                $....797
Restoration of flood control facilities at the Kansas Citys:
    Argentine Unit-restoration of levees and pumping plant-.......-----------....... 134, 317
    Armourdale Unit---restoration of levees, floodwalls and drainage
       facilities--------    -----------------------......................
                             ......................................................            380,514
    Central Industrial Unit-restoration of bank protection_--..                                  10, 329
                                                                                      --..................
    Fairfax-Jersey Creek Unit-restoration of levee, floodwall and seepage
       control system, and removal of debris           --------------------.-----....            36, 982
    North Kansas City Unit-restoration of levee....---------........---...........                4,989
    Kansas River channel-removal of flood debris......----------..................               28, 126
    Repair of freeboard gages------           -------------.-...             ----------------     2,540
Repair of federally constructed Missouri River Agricultural Levees.............    ----          14, 841
Repair of farm levees.................----------------------..................                   93, 957
Construction in connection with closure of St. Joseph avulsion....--...............               5, 399
Engineering, design and surveys-----------------------------...-----......                       25,013
Undistributed costs .... .....................----------------------..                           18, 584
        Total        ..... ...............                                                     783,388
               FLOOD CONTROL-KANSAS CITY, MO., DISTRICT                                        823
                                    Cost and financial summary

                                              Fiscal year ending June 30              Total to June
                                                                                     30, 1954, includ-
                                                                                     ing fiscal years
                             1950            1951        1952        1953 =   1954    prior to 1950




1 Exclusive of $131,343 contributed funds.
    IMPROVEMENTS OF RIVERS AND HARBORS IN THE
              OMAHA, NEBR., DISTRICT

   This district comprises a small portion of southwestern North
Dakota, all of South Dakota except the northwestern corner and a
small northeastern portion, southeastern corner of Montana, east-
ern and south central Wyoming, a portion of north central Colo-
rado, all of Nebraska except the southern portion, western Iowa,
and a small portion of southwestern Minnesota, all embraced in
the drainage basin of the Missouri River along the main stem and
tributaries to Rulo, Nebr., except for that portion of the James
River lying in North Dakota.
   The navigation improvement of that section of the Missouri
River from Rulo, Nebr., to Kansas City, Mo. (Quindaro Bend), is
under the jurisdiction of the Kansas City, Mo., district.
                                          IMPROVEMENTS

                  Navigation                                     Flood Control-Continued
                                               Page                                                      Page

1. Missouri River, Kansas City                         9. Cherry Creek Dam and Reser-
     to Sioux City... .. ........              825          voir, Colo..............................     840
2. Inactive navigation projects...             829    10. Chatfield Reservoir,                 South
                                                            Platte River..........................       841
                  Flood Control                       11. Missouri River agricultural
                                                            levees, Sioux City to Mouth
3. Fall River Basin, S. Dak ..         -       829           (Sioux City, Iowa to Rulo,
4. Missouri River Basin, Omaha                              Nebr.).......       ....      ............   842
                      -- -.. ..-......
     district .... ...--                       831    12. Council Bluffs, Missouri River
5. Oahe Reservoir, Missouri River                           Basin, Iowa ............ .. .........        843
     Basin, S. Dak. and N. Dak .--             832    13. Omaha, Missouri River Basin,
6. Fort Randall Reservoir, Mis-                             Nebr....................................     844
     souri River Basin, S. Dak ---             834    14. Inactive flood control projects..              845
7. Gavins Point Reservoir, Mis-                       15. General investigations_...........             845
     souri River Basin, S. Dak.                       16. Inspection of completed works__                846
     and Nebr..........--- .. ........------   837    17. Flood control work under spe-
8. Missouri River, Kenslers Bend,                           cial authorization ....-.........            847
     Nebr. to Sioux City, Iowa...              839

            1. MISSOURI RIVER, KANSAS CITY TO SIOUX CITY
   Location. The Jefferson, Madison, and Gallatin Rivers conjoin
at Three Forks, Mont., to form the Missouri River, which flows
southeasterly 2,464.41 miles across or along seven States to the
Mississippi River, 17 miles above St. Louis.
  The river is the boundary between the States of Missouri, Kan-
sas, Nebraska, and Iowa. For description, see page 1149, Annual
Report for 1932.
   Previous projects. Under the River and Harbor Act of August
14, 1876, the first regulation works were constructed at St. Joseph
and Nebraska City, but a project for systematic river improve-
ment was not adopted until August 2, 1882, modified by the River
and Harbor Acts of July 5, 1884, September 19, 1890, and June 13,
1902. For further details see page 1893, Annual Report for 1915,
and page 1175, Annual Report for 1938.
11941   adjusted mileage.
                                                                                                825
826               REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

   Existing project. This provides for a channel of 9-foot depth
and width not less than 300 feet, to be obtained by revetment of
banks, construction of permeable dikes to contract and stabilize the
waterway, cutoffs to eliminate long bends, closing of minor chan-
nels, removal of snags and dredging as required. Length of sec-
tion under improvement (upper end of Quindaro Bend to Sioux
City) is 376.3 miles. The ordinary fluctuation is about 14 feet and
the extreme fluctuation about 38 feet.
   The estimated cost of new work, revised in 1954, is $214,600,000
exclusive of amounts expended on previous projects. The esti-
mated cost of annual maintenance is $3,050,000.
   The existing project was authorized by the following river and
harbor acts:

                                                                                                                1
       Acts                              Work authorized                                           Documents

Jan. 21, 1927      Appropriation of $12,000,000 authorized for the exist-              H. Doc. 1120, 60th Cong., 2d sess.
                    ing project.
July    3, 1930    Appropriation of $15,000,000 additional authorized;
                    additional allotments totaling $29,153,108 were
                    made by the Public Works Administration under
                    the provisions of the National Industrial Recovery
                    Act of June 16, 1933, and $9,669,791.92 allotted under
                    the provisions of the Emergency Relief Appropria-
                    tion Act of Apr. 8, 1935.
Aug. 30,1935       For completion of the project from the mouth to                     H. Doc. 238, 73d Cong., 2d sess.
                    Sioux City, Iowa.
Mar. 2, 1945       For a channel of 9-foot depth and 300-foot width......              H. Doec. 214, 76th Cong., 1st sess.

  1 Contains the latest published maps of Missouri River.

    Local cooperation.                        None required.
   Terminal facilities. Facilities for loading and unloading grain,
petroleum products, and other commodities are at various locations
of the river. These facilities are listed in the following table:
                                                                                                   Location z

                            Description of facility I                                   Miles
                                                                                        above           Nearest town
                                                                                       mouth 3

Ways for manufacturing and launching floating equipment .......                           670. 3   Blair, Nebr.
Temporary terminal with facilities for handling and storing petro-                        640. 6   Omaha, Nebr.
  leum products.
Grain elevator, headhouse and conveyor, gantry crane, and dock,                           632. 3       Do.
  publicly owned.
Dock, and warehouse, publicly owned-.-....-..----..-.......-.-.--                         608. 5   Plattsmouth, Nebr.
Grain elevator, privately owned, and a temporary wooden platform                          579. 6   Nebraska City, Nebr.
  with a 60-foot boom for loading and unloading barges, publicly
  owned.
Temporary oil line to river bank_...................___________                           514. 4   Rule, Nebr.
Ways for manufacturing, repairing and launching floating equip-                           407. 2   South Leavenworth,
  ment.                                                                                             Kans.
Government-owned strategic petroleum oil liquid storage depot,                            387. 5   Kansas City, Mo.
  left bank.
Sand and gravel transfer ---.......--------------.............----------....--------      407.3    Leavenworth, Kans.
Sand and gravel transfer_ ___..........................                                   434. 6   Atchison, Kans.
Sand and gravel transfer....................                        .... ___......        461.2    St. Joseph, Mo.
Sand and gravel transfer-----........................----------------------------         514. 5   Rule, Nebr.

  1 Privately owned and operated unless otherwise indicated.
  2 On right bank unless otherwise indicated.
  81941 adjusted mileage unless otherwise indicated.

  The above-listed facilities are considered adequate for existing
commerce.
         RIVERS AND HARBORS-OMAHA, NEBR., DISTRICT               $27

   Promotion of additional terminals, however, has been indicated
at the following locations as soon as conditions warrant: Sioux
City, Whiting, Onawa, California Junction, Blencoe and Council
Bluffs, Iowa; Decatur, Tekamah, Blair and Rulo, Nebr.; St. Joseph,
Mo., and Leavenworth, Kans.
   Operations and results during fiscal year. New work: This
work consisted of construction, by contract, of 84 pile dikes and
10 pile dike extensions totaling 35,622 linear feet, 14 lengths of
revetment totaling 25,765 linear feet, at a total cost of $2,952,920;
construction, by hired labor, of 19 pile dikes and 2 pile dike exten-
sions totaling 9,139 linear feet, and 7 lengths of revetment totaling
14,302 linear feet, and removal of 14,179 linear feet of existing
structures, at a total cost of $721,778; acquisition of 29.94 acres
of right-of-way and preliminary work in connection with acquisi-
tion of right-of-way at a total cost of $7,016; removal of 2,206,-
160 cubic yards of material from 2 localities by the U. S. dredge
Lewis at a cost of $126,887; engineering, design and surveys at a
cost of $75,394, plus prepayments in the amount of $8,573. The
total cost of new work, all prosecuted with regular funds (includ-
ing pending adjustments of $1,086) was $3,893,654.
   Maintenance: This work consisted of construction, by contract,
of repair and replacement of 30,996 linear feet of pile dikes, and
61,381 linear feet of revetment, at a total cost of $1,357,798; the
accomplishment, by hired labor, of repair or replacement of
19,108 linear feet of pile dikes, and 105,024 linear feet of revet-
ment, and removal of 419 linear feet of existing structures, at a
total cost of $1,495,384; removal of 735,860 cubic yards of mate-
rial from 2 localities by the U. S. dredge Lewis, and 93,510 cubic
yards of material from 3 localities by the U. S. dredge Chitten-
den, at a total cost of $60,761; removal of 514,110 cubic yards of
material from 3 localities by the U. S. dredges Black and Mitchell
at a total cost of $97,984; dredging 1,150,990 cubic yards of fill in
damaged channel line structures with the U. S. dredge Lewis at a
cost of $66,095; real estate management and completion of acqui-
sition of right-of-way for St. Joseph avulsion at a total cost of
$1,309; and reconstruction of power lines, telephone lines, and ac-
cess road at St. Joseph avulsion at a total cost of $11,260. The cost
of engineering, design and surveys in connection with hired labor
maintenance work was $118,993. Other miscellaneous costs, all
charged to maintenance, were: Stream gaging for a special studies
and working data at a cost of $17,525; snagging at a cost of $3,245;
surveys and mapping at a cost of $25,141; navigation studies at a
cost of $34,751; miscellaneous investigations and reports at a cost
of $3,074; reconnaissance and marking channel for navigation at
a cost of $95,160, minus prepayments in the amount of $14,494.
The total cost of all maintenance prosecuted with regular funds
was $3,373,986.
   The total cost for the fiscal year was $7,267,640, of which $3,-
893,654 was for new work and $3,373,986 for maintenance.
   Condition at end of fiscal year. Construction was initiated on
the project in fiscal year 1928 and is scheduled for completion in
fiscal year 1963. The work on the entire project Kansas City, Mo.
 (upper end of Quindaro Bend) to Sioux City, Iowa, was approxi-
828           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

mately 53 percent complete at the end of the fiscal year, based on
the present approved estimate of cost.
   Kansas City to Omaha: The work on this section of the project
was approximately 74 percent complete at the end of the fiscal year.
The work remaining to be done to complete this section of the proj-
ect consists principally of the construction of additional bank sta-
bilization structures and the strengthening of existing pile struc-
tures to improve their effectiveness and to prevent their deteriora-
tion prior to final stabilization of the banks. Considerable progress
has been made in alleviating the more critical erosion problems
caused by severe floods, curtailment during World War II, and in-
sufficient funds since the war. A reliable channel suitable for lim-
ited navigation is available through this section. The practical
draft at ordinary stages of the river is 6 to 61/2 feet, with additional
depths available during high stages. Commercial navigation was
inaugurated on this section in May 1939 but was interrupted due
to the war from 1942 until October 1946.
   Omaha, Nebr., to Sioux City, Iowa: The work between Omaha,
Nebr., and Sioux City, Iowa, was approximately 31 percent com-
plete at the end of the fiscal year. Loss of alinement and progres-
sive destruction of control works continue in most parts of this
section of the river, owing to natural deterioration of the struc-
tures as a result of curtailment of work during World War II,
inadequate funds for new work and maintenance since the war,
and several extreme high waters. Much of the river has reverted
to its original wild state, and bank erosion is severe at many loca-
tions. The rate of destruction has far exceeded the work accom-
plished with the limited funds available, with the result that there
is no improvement for the channel for this section as a whole.
Channel conditions limit practical drafts to 31/2 feet.
   Under the existing project for systematic work on the 9-foot
channel, the work accomplished includes 1,271,775 linear feet of
revetment for permanently fixing the banks, 2,341,390 linear feet
of pile dikes, 10,142 linear feet of rock dikes, 143,884 linear feet of
abatis, 2,287 linear feet of jetties, recrowning 700 linear feet of an
existing levee, 19,218 linear feet of retards for stabilization of
channel widths, construction of five impermeable structures to
close off auxiliary channels, construction of48,237 linear feet of
asphalt revetment, effecting three channel cutoffs, and removal of
87.976,638 cubic yards of material dredged from the channel to
obtain project depth and width.
   The total cost of work under the existing project to June 30,
1954, is:

                                                                                         Cost
                                                                    New work          Maintenance        Total


Regular funds .____ _____ ____..
                            .. . .. . . . . .. .                     $75, 558, 152     $37, 676, 518   $113, 234, 670
Public works funds_ _ ______....
                            __ . . . . . . .. .. . . . . .
                          ....-                                       29, 038, 236          114, 180     29, 152, 416
Emergency relief funds__.. ...-
                             ..    .            -
                                          ........     . - .-
                                                    --..               9, 613, 073           56, 645      9, 669, 718

     Total funds -- ..     ..   ..   ..   . ...---------------------- 114, 209, 461     37, 847, 343    152, 056, 804
                RIVERS AND HARBORS--OMAHA, NEBR., DISTRICT                                                              829
                                         Cost and financial summary

                                                    Fiscal year ending June 30                              Total to June
                                                                                                            30, 1954, includ-
                                                                                                            ing fiscal years
                                  1950          1951              1952             1953         1954         priorto 1950


New work:
    Appropriated- ...         $2, 865, 000   $3, 750,000      $4, 000,000     $4,223,000     $3, 500,000      1$116,865, 558
    Cost-----. ----------      2, 929, 685    2, 484,336       3,603, 319      5,959,473      3,893, 654       1116, 796, 078
Maintenance:
    Appropriated        -       3, 790,000    3, 373, 500      4,182, 000      5, 520, 700    3,251,000         2 38, 529, 034
    Cost-- ---                  3, 03, 77
                            .-----            3,111, 640       4, 034, 078     6,136,140      3,373,986         238, 417, 547

  1 Includes $29,038, 236 National Industrial Recovery Act Funds and $9,613,073 Emergency Relief Funds
Also includes an amount for previous project of $2,586,617.
  sIncludes $114,180 National Industrial Recovery Act Funds and $56, 645 Emergency Funds. Also.
includes an amount for previous project of $570,204.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_-------------      $59,808
    Appropriated for succeeding fiscal year ending June 30, 1955_ ----     6,300,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955...----------      ------------------------------- 6,359,808
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project---------       ---------------------       94,021,059

                        2. INACTIVE NAVIGATION                                 PROJECTS
                                                                             Cost and expenditures to
                                                             For last              June 30, 1954               Estimated
                                                            full report,                                        amount
                  Name of project                               see                                             required
                                                             annual                                                to
                                                              report         New work        Maintenance        complete
                                                               for-
1. Missouri River, Sioux City, Iowa, to Fort                   1948           $3, 123,141        $644,863           (1)
    Benton, Mdnt.
2. Big Sioux River, S. Dak., and Iowa......----------          1952                                               1$844,   000


  1 No work is scheduled for the fiscal years 1955 and 1956.


                             3. FALL RIVER BASIN,                             S.    DAK.
   Location. The work covered by this project is located in
Custer and Fall River Counties, S. Dak., in and near the town of
Hot Springs. The Hot Springs unit is in the town of Hot Springs,
immediately south of the junction of Cold Brook and Hot Brook
which combine to form Fall River; the Cold Brook Reservoir unit
is approximately 11/4 miles north of the town of Hot Springs on
Cold Brook; and the Cottonwood Springs unit is approximately
41/ miles west of the town of Hot Springs on Cottonwood Springs
Creek, one-half mile upstream from its confluence with Hot Brook.
   Existing project. The project as authorized by the Flood Con-
trol Act approved August 18, 1941, is a plan of flood protection on
the Fall River and tributaries, South Dakota, substantially in ac-
cordance with the recommendations of the Chief of Engineers in
House Document 655, 76th Congress, 3d session. The general plan
of improvement provides for the protection from flood damage of
the people and property of the town of Hot Springs, S. Dak.
   The Hot Springs channel improvement unit provides for the
widening, deepening, and straightening of the present channel of
Fall River from a point near the confluence of Hot Brook and Cold
Brook to a point 400 feet below the Eighth Street Bridge or a total
830      REPORT OF CHIEF OF ENGINEERS. U. S. ARM , 1954

distance of approximately 6,000 feet. Clearing of trees, boulders,
concrete slabs, and all obstructions to flow is provided for.
   The Cold Brook Reservoir unit is designed to control an area of
70.5 square miles, and have a capacity of 6,000 acre-feet at spillway
crest, with surcharge at maximum pool of 5,114 acre-feet. The
following features are included: Construction of an earthfill dam
with uncontrolled outlet; an uncontrolled reinforced concrete con-
duit under the dam; and a spillway with a discharge capacity of
85,000 cubic feet per second. at maximum pool elevation through
solid rock adjacent to the reservoir.
   The Cottonwood Springs Reservoir unit will control an area of
26 square miles and have a capacity of 6,160 acre-feet at spillway
crest with surcharge at maximum pool of 2,114 acre-feet. The
following features are included: Construction of an earthfill dam
faced upstream and downstream by dump rock; an uncontrolled
reinforced concrete conduit under the dam; and a spillway of 16,100
cubic feet per second capacity at maximum pool elevation through
the solid rock right abutment.
   The (1954) estimated Federal cost is $4,600,000, the estimated
local cost (1954) is $138,200.
   Local cooperation. In addition to the usual requirements for
local cooperation as provided by law, local interests are required
to bear the expense of bridge modifications and give assurances
satisfactory to the Secretary of War that they will take such
measures as may be necessary to prevent any encroachments upon
the flood channel capacities to be provided by the improvements.
   The assurances of local cooperation for the Hot Springs unit
were approved by the Secretary of War, May 18, 1946.
   Operation and results during fiscal year. (Regular funds.)
Engineering and design studies in connection with foundation
grouting of the left abutment of the Cold Brook Unit were con-
tinued. A contract for roads and parking area at Cold Brook Dam
was advertised and all bids were rejected. Definite project report
studies required for the Cottonwood Reservoir Unit were contin-
ued. Preparation of the master plan for reservoir management
and public use development was continued. Total cost of new work
for the fiscal year was $12,610.
   Operation and care activities included the administration of the
project area; sediment and stream gaging activities and miscel-
laneous items of ordinary repairs, maintenance, improvements and
reconstruction. The total cost of operation and care activities dur-
ing the fiscal year was $6,804.
   Condition at end of fiscal year. Construction of the Hot Springs
Unit was completed during fiscal year 1951. The cost for this unit
was $1,063,945, all from regular funds, with the exception of con-
tributed funds in the amount of $4,250. Construction of the Cold
Brook unit dam and appurtenances was completed by contract in
fiscal year 1953 with the exception of a road and parking area
which are to be readvertised in the late summer of 1954. Prepara-
tion of the master plan for the Cold Brook Reservoir- management
and public use development was approximately 90 percent com-
plete. Engineering and design studies in connection with the foun-
                      FLOOD CONTROI-OMAHA, NEBR., DISTRICT                                                       831
dation grouting of the left abutment were essentially completed.
Definite project report studies required for the Cottonwood Res-
ervoir Unit were in progress. The total cost of new work to the
end---of the fiscal year was $2,665,607 of which $2,661,357 was
regular funds and $4,250 contributed funds.
   The total cost of operation and care activities to the end of the
fiscal year was $6,804.
                                      Cost and financial summary

                                              Fiscal year ending June 30                                Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                               1950         1951            1952               1953         1954         prior to 1950

New work:
   Appropriated_--.          $397, 000    $400, 000        $425, 000      $425, 000       -$96, 665        1$2, 733,335
   Costace:
        ...                    71,789
                                  ,        578,075          519,507        320,479            12,610        12, 661,357
Maintenance:
   Appropriated-                  ---
                         ----------       - ------    --    .......    ---.-                  7,600               7,600
                        ....
    Cost-------------- -------------..
                                    ..    ...-----------------------.                         6,804               6,804

  I In addition, the sum of $4,250 was expended from contributed funds.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_----              $71,978
    Appropriated for succeeding fiscal year ending June 30, 1955             96,665        --------
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955--------------                                                168,643
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project_   -- -                                    1,770,000

                4. MISSOURI           RIVER BASIN,                    OMAHA           DISTRICT
  Location. The flood control improvements included in this
project are located on and along the Missouri River and several of
the principal tributaries of the Missouri River and are located in
the States comprising the Missouri River Basin.
   Existing project. The general comprehensive plan for flood
control and other purposes in the Missouri River Basin provides
for levees along the Missouri River between Sioux City, Iowa, and
the mouth and reservoirs located on the main stem of the Missouri
River and on the tributaries for control of flood flows at the dam
sites. The existing project was authorized by the following flood
control acts:

     Acts.'                       Work authorized                                           Documents'

June 28, 1938   Adopted general comprehensive plan for Missouri                  Flood Control Committee Doc. 1,
                 River Basin and authorized $9,000,000 for initiation              75th Cong., 1st sess.
                 and partial accomplishment.
Aug. 18,1941    Modified the general comprehensive plan to include               H. Doc. 842, 76th Cong., 3d sess.
                 Harlan County Dam and Reservoir on the Repub-
                 lican River, Nebr., and authorized $7,000,000
                 additional expenditure.
Dec. 22,1944    Expanded the general comprehensive plan for the                  H. Doe. 475, 78th Cong., 2d sess.;
                 Missouri River Basin and authorized $200,000,000                  S. Doe. 191, 78th Cong., 2d sess.;
                 additional expenditure.                                           S. Doc. 247, 78th Cong., 2d sess.
July 24, 1946   Authorized an additional expenditure of $150,000,000
                 for prosecution of the general comprehensive plan
                 for the Missouri River Basin.
May 17, 1950    Authorized an additional expenditure of $250,000,000
                 for prosecution of the general comprehensive plan
                 for the Missouri River Basin.

  ' Contain the latest published maps of Missouri River Basin.




        Sig 27-831-862
832              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  Included in the comprehensive plan are the following projects in
the Omaha district:

                                                 Project                                                      Estimated
                                                                                                              Federal cost

Missouri River agricultural levees, Sioux City, Iowa, to Rulo, Nebr                   _-------------------      1 $40, 200,000
Oahe Reservoir, S. Dak. and N. Dak....-----------------                              -------------------------   316, 000, 000
Fort Randall Reservoir, S. Dak....-------                      --------------------------------                1 195, 000,000
Gavins Point Reservoir, S. Dak. and Nebr----------------------------------------1 53, 000,000
Big Bend Reservoir, S. Dak__..---------------------------------------------------                                  71, 500,000
Omaha Nebr........................................------------------------------------------------------------    1 5, 896, 374
CouncilBluffs, Iowa ....                  -------------------------------------.--------------------              1 2, 557, 680
Sioux City, Iowa--                    -----------------------------------------------------------                 1 1,230, 000


  1Details presented in individual report.

   Operations and results during fiscal year. The operations dur-
ing the fiscal year, together with costs for those projects on which
plans were in preparation, are shown in individual reports.
   Condition at end of fiscal year. The conditions of the various
projects on which work had been initiated are given in individual
reports.
   Under sections 7 and 9 of Public Law 534, Flood Control Act,
approved December 22, 1944, the Corps of Engineers is responsible
for detailed scheduling of operations of storage capacity reserved
for or assigned to flood control in reservoirs constructed by the
Bureau of Reclamation as well as those constructed by the Corps
of Engineers. The cost of work under this heading during the
fiscal year was $38,952.

                                           Cost and financial summary

                                                     Fiscal year ending June 30                              Total to June
                                                                                                             30, 1954, includ-
                                                                                                             ing fiscal years
                                    1950            1951           1952           1953           1954         priorto 1950

Maintenance:
                   -------------
    Appropriated-..............                    $15,000         $20, 000       $28, 000       $32, 700             $95, 700
    Cost-------
         .      ----------   --------               12, 393         22, 546        20,593         38, 952              94, 484



                  5. OAHE RESERVOIR, MISSOURI RIVER BASIN,
                             S. DAK. AND N. DAK.

   Location. The Oahe dam site is located on the Missouri River
in Hughes and Stanley Counties, S. Dak., about 6 miles northwest
of Pierre, S. Dak., and 1,123 miles above the mouth of the river.
   Existing project. This provides for the construction of a
rolled earthfill dam with a maximum height of 242 feet and reser-
voir for flood control, irrigation, navigation, hydroelectric power,
and other purposes, with a gross storage capacity of 23,600,000
acre-feet at maximum operating pool. It provides for the initial
             FLOOD CONTROL--OMAHA, NEBR., DISTRICT              833
power installation of two units nominally rated at 85,000 kilowatts
each. The existing project was authorized by the Flood Control
Act, approved December 22, 1944 (Public Law 534, 78th Cong., 2d
sess.), as part of the general comprehensive plan for flood control
and other purposes in the Missouri River Basin. The estimated
cost (1954) is $316,000,000 for the initial project only, which in-
cludes initial power installation only.
   Local cooperation. Section 2 of the Flood Control Act, ap-
proved June 28, 1938, applies.
   Operations and results during fiscal year. (Regular funds.)
Acquisition of lands for the dam site and reservoir was continued.
Construction contracts for the sheet pile wall and closure of the
exploratory drift were completed. Delivery was made on initial
supply contracts for lightning arrestors, circuit breakers, auto-
transformers and disconnect switches to be used initially in the
temporary switchyard. Continuing contracts were initiated for
earthwork stage III, and the outlet works stage I consisting of six
intake structures and six reinforced concrete tunnels 19 feet 9
inches in diameter and approximately 1,600 feet long. Work on
these contracts during the year included placement of approxi-
mately 4,500,000 cubic yards of embankment and placement of
10,000 cubic yards of concrete in the intake structures. A con-
tinuing contract for construction of the administration facilities
was initiated. A continuing contract was negotiated with the
South Dakota Highway Department for the relocation of U. S.
Highways 212 and 12. A contract for the storm sewer outfall
ditch at Pierre, S. Dak., was initiated and completed.
   The total cost of new work during the fiscal year was $4,958,130.
   Conditions at end of fiscal year. Construction was initiated on
the project in August 1948 and is scheduled for completion in
1963. Work in connection with the preparation of detailed plans
was complete. Plans and specifications for the downstream tun-
nels of the outlet works were completed and approved. Prepara-
tion of contract plans and specifications was approximately 43 per-
cent complete. Construction of housing facilities, west access
road, access railroad, earthwork stage I, earthwork stage II, sheet
pile wall, closure of the exploratory drift, and the storm drainage
system was complete. Delivery was made on circuit breakers,
autotransformers, disconnect switches and lightning arrestors.
Continuing contracts for earthwork stage III and outlet works
stage I were approximately 40 percent and 6 percent complete,
respectively. A continuing contract was awarded for the adminis-
tration facilities at the dam site and was approximately 9 percent
complete. The entire project was approximately 6 percent com-
plete. Additional work required to complete the project includes
additional earthwork; remainder of outlet works; powerhouse;
spillway; reservoir and pool preparation, including relocation of
existing facilities; and acquisition of additional lands.
   The total cost of new work to the end of the fiscal year was
$20,341,532.
834           REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

                                    Cost and financial summary

                                              Fiscal year ending June 30                             Total to June
                                         _          _30,                                                1954, includ-
                                                                                                     ing fiscal years
                             1950            1951             1952          1953          1954        priorto 1950


New work:
   Appropriated.-......   $1,500,000   $3, 600,000         $3,770, 000   $2,985, 000   $6, 550,000       $22, 905,000
   Cost --------------     1,681,091    3,237,823           3,556,714     3,605,872     4,958,130         20,341,532


Other new work data:
     Unobligated balance, fiscal year ending June 30, 1954-_-- -----                                        $2, 045
     Appropriated for succeeding fiscal year ending June 30, 1955 --    10,700,000
     Unobligated balances available for succeeding fiscal year ending
       June 30, 1955 _      aoteet-r                       cfr-         10,702,045
     Estimated additional amount needed to be appropriated for com-
       pletion of existing project       _    __ _          ---------- 282,395,000

6. FORT RANDALL RESERVOIR, MISSOURI RIVER BASIN, S. DAK.

   Location. The Fort Randall dam site is located on the Missouri
River in Charles Mix and Gregory Counties, S. Dak., about 82 miles
above Yankton, S. Dak. The site is 922 miles above the mouth of
the Missouri River and 162 miles above Sioux City, Iowa.
   Existing project. This provides for the construction of a rolled
earthfill dam with a maximum height of 160 feet and a reservoir
for flood control, irrigation, navigation, hydroelectric power, and
other purposes, with a gross storage capacity of 6,300,000 acre-feet
at maximum operating pool. It provides for the ultimate power in-
stallation of eight units nominally rated at 40,000 kilowatts each.
   The project was authorized by the Flood Control Act approved
December 22, 1944 (Public Law 534, 78th Cong., 2d sess.), as part
of the general comprehensive plan for flood control and other pur-
poses in the Missouri River Basin. The estimate of cost (1954) is
$195,000,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operation and results during fiscal year. (Regular funds.)
Preparation of contract plans and specifications by hired labor was
continued. Contracts for design and preparation of contract plans
and specifications for the hydroelectric power plant and the rail-
road bridge across the Missouri River for the relocated Chicago,
Milwaukee, St. Paul and Pacific Railroad were continued. Acquisi-
tion of land was completed and disposal of improvements thereon
was continued. A negotiated contract with the State of South
Dakota for the relocation of South Dakota State Highway No. 47
and U. S. Highways Nos. 16, 18, and 281 was continued. A nego-
tiated contract with the Chicago, Milwaukee, St. Paul, and Pacific
Railroad for relocation of railroad facilities in the vicinity of
Chamberlain and Oacoma, S. Dak., was continued. Continuing
contracts for the relocation of the Chicago, Milwaukee, St. Paul
and Pacific Railroad at Chamberlain, S. Dak., Stages I, IIA, and III
were completed; stages IIB and IV were continued, and stage V
 (salvage of existing line) were initiated. The railroad company
began operating over the new line on December 7, 1953.
  Negotiated contracts for the municipal water works, Chamber-
              FLOOD CONTROL-OMAHA, NEBR., DISTRICT                 835
  lain, South Dakota, and relocation of Oacoma Township Roads,
  Lyman County, S. Dak., were completed. Negotiated contracts
  for relocation of municipal sewer facilities at Chamberlain, S. Dak.,
  and relocation of the Northwestern Bell Telephone Company's toll
  line near Chamberlain, S. Dak., were continued. Contracts were
  negotiated and work initiated by the owners for relocation of trans-
  mission lines owned by the West Central Electric Cooperative and
  the facilities of the Fort Hale Telephone Company. Negotiations
for relocating the power lines of the Central Electric and Gas Com-
pany were initiated. A continuing contract for the water supply
  system, Chamberlain, S. Dak., was completed. Negotiated con-
tracts with the owners for relocation of facilities of the Scalp Creek
Telephone Company, the Valley Telephone Company, and the
Trans-Township Telephone Company were completed. Condemna-
tion proceedings for the relocation of county and township roads
in Charles Mix County were initiated, and work was completed
under continuing contracts for the roads in Gregory and Lyman
Counties, S. Dak., Earthwork, stage IV, was essentially completed
and earthwork, stage V, was continued. Approximately 6,600,000
cubic yards of materials were excavated, of which 3,750,000 cubic
yards were placed in the embankment. A contract for embank-
ment relief wells was completed.
     Contracts for intake gates, gate hoists, penstocks, and surge
tanks and stages I and II of spillway construction were continued.
Contracts for furnishing the floating boom, stoplog, lifting beam,
gate seals, and trashrack rake for the intake structures; regulating
gate and frame and regulating gate hoist for the outlet structure;
and monorail equipment for the spillway were initiated. A con-
tinuing contract for reservoir clearing was completed. Contracts
for furnishing turbines, governors, generators, power transform-
ers, and switchgear were continued. Two generators were placed
in operation during the fiscal year. Contracts for construction of
a public service building, roads, parking areas, and boat ramps,
and initial wildlife habitat planting were started. Pursuant to an
agreement made with the Bureau of Indian Affairs, contracts for
relocation of roads serving the Crow Creek Indian Reservation at
Fort Thompson, S. Dak., were initiated. Preparation of plans and
specifications for the remaining Indian Agency facilities were vir-
tually completed. Bank slope protection, sections II and III in the
vicinity of Chamberlain, S. Dak., were well advanced.
    The total cost of new work during the fiscal year was $35,-
843,461 from regular funds.
    Operation and maintenance activities included the initial opera-
tion of two generating units of the powerhouse, regulation of the
reservoir through operation of the outlet works, training of power-
house operators, reservoir regulation studies, and miscellaneous
items of ordinary repairs and maintenance. The total cost of
operation and maintenance activities during the fiscal year was
$212,938, all from regular funds.
    Conditions at end of the fiscal year. Construction was initiated
on the project in May 1946 and is scheduled for completion in 1957.
Preparation of detailed plans was complete, and preparation of
contract plans and specifications by hired labor was about 94 per-
836       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  cent complete. Contracts for design and preparation of contract
  plans and specifications for the hydroelectric power plant and the
  Chicago, Milwaukee, St. Paul and Pacific Railroad bridge were each
approximately 99 percent complete. Acquisition of land for the
  dam and reservoir was complete; however, 428 tracts were still in
litigation at the end of the fiscal year. Under the negotiated con-
tract with the State of South Dakota for highway relocation U. S.
Highways 18 and 281 have been routed across the dam, although
final location of a portion of the road is dependent ipon completion
of the embankment. The relocated U. S. Highway 16 is in use
although surfacing of that portion from the west end of the Mis-
souri River bridge to Oacoma had just been started at the end of
the year, and work on South Dakota State Highway No. 47 was in
progress. The relocation of the Chicago, Milwaukee, St. Paul, and
Pacific Railroad was complete except for stage V (salvage) and the
formal transfer of lands involved. The relocation of the municipal
water supply system at Chamberlain, S. Dak., was complete and
the relocation of that city's municipal sewer facilities was 94 per-
cent complete. Bank slope protection in the vicinity of Chamber-
lain, S. Dak., was approximately 29 percent complete. Relocation
of roads in Gregory and Lyman Counties, S. Dak., was complete,
and roads in Charles Mix County were in condemnation. Remain-
ing utility relocations, including telephone and power facilities,
were 13 percent complete. Reservoir clearing was complete.
Earthwork stage V (final) was approximately 48 percent com-
plete. The spillway was essentially complete. Continuing con-
tracts for furnishing generators, hydraulic turbines, turbine gov-
ernors, power transformers, oil circuit breakers, main control
boards, main and neutral switchgear, oil-filled pipe cable, and out-
door switchgear were in progress. Two generators were in opera-
tion, the first having gone on the line on March 15, and the second
on May 18. A total of 68,114,000 kilowatt hours of electricity was
produced during fiscal year 1954. Continuing contracts for con-
struction of powerhouse superstructure and penstocks and surge
tanks were approximately 73 and 70 percent complete, respectively.
Filling of the operating or power zone of the pool proceeded as
river flow permitted. On June 30, 1954, the pool was at approxi-
mate elevation 1,320 and a total volume of 1,835,000 acre-feet of
water was impounded in the reservoir.
    The entire project was 84 percent complete.
    The major items of work remaining on this project are: comple-
tion of work in progress described above; regulating gate struc-
tures; embankment crest roadway and lighting; seeding and
planting of embankment and reservoir areas; riprap on embank-
ment as needed; construction of reservoir approach roads and pub-
lic access facilities.
   The total costs to the end of the fiscal year were $163,852,963
for new work and $212,938 for maintenance, all from regular funds.
                       FLOOD CONTROL--OMAHA, NEBR., DISTRICT                                                  837
                                           Cost and financial summary

                                                     Fiscal year ending June 30                     Total to June
                                                                                                    30, 1954, includ-
                                                                                                    ing fiscal years
                                   1950            1951           1952       1953        1954         priorto 1950

New work:
   Appropriated-.-         -$23,  655,000    $32, 580, 000 $33,064,975 $31, 975,025 $13, 000, 000      $165,897, 700
   Cost--------------...       23,066,868     23,966, 599   19, 862,165 34, 903, 774 35,843, 461        163, 852, 963
Maintenance:
   Appropriated ......      ------------     ------------------    ------ ------------   224, 200            224, 200
   Cost ...---------------------------                                                   212, 937            212,937


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954        __           $6,938
    Appropriated for succeeding fiscal year ending June 30, 1955 -        15,500,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955-               ------------------------------------------ 15,506,938
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project----------       ---------------------- 13,602,300

7. GAVINS POINT RESERVOIR, MISSOURI RIVER BASIN, S. DAK.
                       AND NEBR.
    Location. The Gavins Point Dam site is located on the Missouri
River in Yankton County, S. Dak., and Knox County, Nebr., about
4 miles upstream from Yankton, S. Dak., and about 850 miles
above the mouth of the river.
    Existing project. This provides for the construction of a con-
crete and rolled earthfill dam with a maximum height of 72 feet and
a reservoir for flood control, irrigation, navigation, hydroelectric
power, and other purposes, with a gross storage capacity of 540,-
000 acre-feet at maximum operating pool. It provides for the
ultimate power installation of three units nominally rated at 33,333
kilowatts each.
   The existing project was authorized by the Flood Control Act
approved December 22, 1944 (Public Law 534, 78th Cong., 2d
sess.), as part of the general comprehensive plan for flood control
and other purposes in the Missouri River Basin. The estimate of
cost (1954) is $53,000,000.
   Local cooperation. Section 2 of Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. (Regular funds.)
Preparation of contract plans and specifications were continued by
hired labor. A contract for the design and preparation of contract
plans and specifications for the hydroelectric power plant was con-
tinued. Acquisition of land for the dam site and reservoir area was
continued. Contracts for furnishing hydraulic turbines, turbine
governors, and for furnishing and installing generators were con-
tinued. A contract for the construction of the powerhouse sub-
structure; intake structure, spillway, and stage II earthwork was
continued. The quantities of excavation and embankment com-
838          REPORT OF, CHIEF OF ENGINEERS, U. S. ARMY, 1954

pleted during the year were approximately 4,870,000 and 3,430,000
cubic yards, respectively. Supply contracts were awarded for bulk-
heads and stoplogs, powerhouse crane, transformers, monorail, in-
take Gantry crane, intake gates, oil circuit breakers, trashrack,
floating boom, main control boards, 15 KV transformer leads, 13.8
KV switchgear, 460-V unit type substation,.draft tube crane, ice
skimmer and unwatering pumps and controls. A construction con-
tract for the powerhouse superstructure and a supply contract for
the station service control center and convertible panel boards were
under advertisement. Bids were opened and award was pending
on switchyard and transformer yard structures. Contract plans
and specifications were completed for reservoir clearing and the
relocation of the Springfield sewer. Relocations of South Dakota
State and county highways were being negotiated.
   The total cost of new work during the fiscal year was $9,728,086.
   Condition at end of fiscal year. Construction on the project
was initiated in March 1952 and is scheduled for completion in
1958. Preparation of detailed plans was complete and preparation
of contract plans and specifications by hired labor was about 67
percent complete. The contract for the design and preparation of
contract plans and specifications for the hydroelectric power plant
was about 94 percent complete. Construction of the south access
road, improvements to the Yankton Bridge, administration build-
ing, and utilities for the administration building was complete.
The contract for stage I earthwork was complete. The contract
for the powerhouse substructure, intake structure, spillway and
stage II earthwork was about 45 percent complete. To date a total
of 6,368,000 cubic yards of excavation and 5,430,000 cubic yards
of embankment has been completed. A contract to furnish hy-
draulic turbines was about 19 percent complete and a contract to
furnish and install generators was about 2 percent complete. The
entire project is approximately 28 percent complete.
   The major items of work remaining to be awarded consist of the
construction of the powerhouse superstructure, installing me-
chanical and electrical equipment in the powerhouse and switch-
yard, relocation of roads, clearing of the reservoir area, and the
acquisition of additional lands.
   The total cost of new work to the end of the fiscal year was $14,-
626,229, all of which was from regular funds.
                                   Cost and financial summary

                                         Fiscal year ending June 30                      Total to June
                                                                                        30, 1954, includ-

                            1950        1951         1952         1953        1954       prior to 1950


New work:
   Appropriated ........   $168,785    $20,000    $2,000,000   $7,712,000 $0,000,00         $20, 380, 785
   Cost ..                  196, 696    121,964      463,085    3,901,073   9,728,086        14,626,229


Other new workl data:
    Unobligated balance, fiscal year ending June 30, 1954       _ _             $392
    Appropriated for succeeding fiscal year ending June 30, 1955__        11,300,000
    Unobligated balances available for succeeding fiscal year ending June
        30, 1955             .---                             -------- 11,300,392
      Estimated additional amount needed to be appropriated for comple-
        tion of existing project __                                                      21,319,215
             FLOOD CONTROL-OMAHA, NEBR., DISTRICT                839
8. MISSOURI RIVER,     KENSLERS BEND, NEBR., TO        SIOUX CITY,
                              IOWA

    Location. This project is located along the Missouri River be-
tween Ponca Bend, Nebr., and the combination bridge at Sioux
City, Iowa.
    Existing project. The existing project authorized by the Flood
Control Act approved August 18, 1941, and modified by the Flood
Control Act approved June 30, 1948, provides for the construction
of dikes, revetments and channel improvement along the Missouri
River from Miners Bend and vicinity, S. Dak. and Nebr., to Sioux
City, Iowa.
    The estimated cost of new work under the project (1954) is
$10,700,000.     The estimated cost of annual maintenance is
 $153,000.                                                       ..::
    Local cooperation. Fully complied with.
    Operations and results during fiscal year. New work consisted
of construction, by contract, of 2 lengths of revetment totaling
12,072 linear feet at a cost of $480,868.
    Maintenance consisted of repair of 800 linear feet of dikes, by
contract, at a cost of $100,552.
    The total cost for the fiscal year was $581,420.
    Condition at end of fiscal year. Work on the project was started
in June 1946 and was approximately 40 percent complete on June
30, 1954, based on the present estimate of cost. The project is
scheduled for completion in fiscal year 1958.
   The physical extent of work accomplished at the end of the fiscal
year includes the completion of 550 linear feet of rock dikes, 7,441
linear feet of pile dikes, and 71,802 linear feet of revetment.
   Construction to prevent bank erosion was started at bluff con-
tact on the right bank in Kenslers Bend, about twelve miles up-
stream from the Combination Bridge at Sioux City, Iowa. The
works necessary to control bank erosion in this reach are about 78
percent completed. The work is effective in controlling the bank
erosion on the right bank in Kenslers Bend, and partially effective
in controlling bank erosion on the left bank in the McCook Lake
area and on the right bank in Big Sioux Bend. Erosion is active
on the left bank in Upper Sioux City Bend since construction has
not been started which will control bank erosion at this site.
   Work has not been started in the upper limits of the project in
the Miners Bend area.
   The total cost of the project at the end of the fiscal year was
$4,695,684, of which $4,250,806 was for new work and '$444,878
was for maintenance.
840                    REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                       Cost and financial summary

                                                               Fiscal year ending June 30                       Total to June
                                                                                                                30, 1954, includ-
                                                                                                                ing fiscal years
                                                1950         1951         1952        1953           1954         prior to 1950


New work:
    Appropriated -------                       $395, 000   $1,014,609 ----------------------        $500, 000        $4, 287, 669
    Cost-.......----....---....--------.....    576,536       554,116    $505, 590  $403, 291        480,868          4,250,806
Maintenance:
    Appropriated--------                        147,000       58,000       70,000      57, 000        99,000             446, 000
    Cost-----------------                        89,795      112894        70,013      56,625        100, 552            444,878


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954.$--------------7,622
    Appropriated for succeeding fiscal year ending June 30, 1955--.    ..     600,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955---------------------------------------------                   607,622
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project------------------------                   - 5,812,331
                                                                           5----

                   9. CHERRY CREEK DAM AND RESERVOIR, COLO.
   Location. The Cherry Creek Dam and Reservoir is located on
Cherry Creek in Arapahoe County, Colo., approximately          miles
southeast of the city of Denver, Colo. Cherry Creek joins the
South Platte River within the city limits of Denver.
   Existing project. The project consists of a rolled earthfill dam
with maximum height of 140 feet above the stream bed and 14,300
feet in length. The project includes a reinforced concrete outlet
works and an uncontrolled side channel spillway canal discharging
into the adjacent Toll Gate Creek, thus bypassing the city of Den-
ver. The Cherry Creek project provides reservoir storage capacity
of 95,000 acre-feet below the spillway canal invert and surcharge
storage of 136,400 acre-feet above this elevation. Initial plan for
operation is for flood control only. The plan of operation in the
ultimate development for multiple purpose uses includes 10,000
acre-feet for sediment storage, 85,000 acre-feet for conservation
purposes, and surcharge storage for flood control purposes. The
estimated cost of the initial project for flood control only (1954)
is $14,567,270.
   The existing project was authorized by the following flood con-
trol acts:

    Acts                                          Work authorized                                     Documents
Aug. 18, 1941           The initiation and partial accomplishment of the                H. Doe. 426, 76th Cong., 1st sess.
                           project.
Dec. 22,1944            Completion of the plan approved in the act of Aug. 18,                Do.
                           1941.
    Do-.......          General comprehensive plan, Missouri River Basin.. H. Doe. 475, 78th Cong., 2d sess.;
                                                                                            S. Doc. 191, 78th Cong., 2d sess.;
                                                                                            S. Doc. 247, 78th Cong., 2d sess.


  Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
  Operations and results during fiscal year. (Regular funds.)
This project was completed on June 30, 1953. Litigation to estab-
                      FLOOD CONTROL-OMAHA, NEBR., DISTRICT                                                 841
lish equitable payment for certain tracts of reservoir land and
flowage rights was continued. The total cost of new work during
the fiscal year was $1,707.
   Operations and care activities included the administration of the
project area; continuation of sediment studies and stream gaging
activities; and continuation of miscellaneous items of ordinary
repairs, maintenance, improvements, and reconstruction. The total
cost of operation and care activities during the fiscal year was
$47,605.
  Condition at end of fiscal year. Construction on the project
was initiated in fiscal year 1943 and was physically complete on
June 30, 1953. Final litigation to establish equitable payment for
certain tracts of reservoir land and flowage rights is still pending.
The total cost of new work to the end of the fiscal year was $14,-
566,215. The total cost of operation and care activities was
$105,287, all from regular funds.
                                          Cost and financial summary

                                                Fiscal year ending June 30                       Total to June
                                                                                                 30, 1954, includ-
                                                                                                 ing fiscal years
                                   1950        1951           1952        1953        1954        prior to 1950

New work:
    Appropriated ------.....   $   150,000    $216,708    -------------   $35, 000   -$ 5,000        $14,567, 270
    Cost- .....-       .       3,397,106       361,626      $ 56, 373      21,154       1,707          14,566,214
Maintenance:
   Appropriated ...-------- ------------        20, 000        27,000      30,000      33,700-            110, 700
   Cost...-------------------------             10, 099        24,352      21, 297     47,605             105, 287


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954                     ---------------
                                                                              $1,056
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955_ --------------------------------------------------                 1,056

10. CHATFIELD RESERVOIR SOUTH PLATTE RIVER BASIN, COLO.
   Location. The Chatfield Reservoir Project, Colo., is located on
the South Platte River in northeast Colorado, approximately 8
miles southwest of the city of Denver.
   Existing project. The project consists of an earth-fill dam
approximately 132 feet high with a gross storage capacity of 200,-
000 acre-feet. This project is a unit of the plan of improvement
for the main stem and certain tributaries of the South Platte River
for flood control and allied purposes. The project was authorized
by the Flood Control Act approved May 17, 1950, substantially in
accordance with the recommendations of the Chief of Engineers
in House Document 669, 80th Congress, 2d session. The act au-
thorized $26,300,000 for partial accomplishment of the work
described in House Document 669. The estimated cost for new
work (1954) is $32,600,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. No work has been
initiated under this project.
   Condition at end of fiscal year. No work has been initiated.
842             REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

                                    Cost and financial summary
Other new work data:
    Appropriated for succeeding fiscal year ending June 30, 1955-.    - -    $30,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955_------------------------------                                 30,000
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project --------------------------------
                                           _                              32,570,000

11. MISSOURI RIVER AGRICULTURAL LEVEES, SIOUX CITY, IOWA,
     TO THE MOUTH (SIOUX CITY, IOWA, TO RULO, NEBR.)
   Location. The Missouri River rises in southwestern Montana
and flows generally southeasterly 2,464.4 miles across or along
seven States to a confluence with the Mississippi River 17 miles
above St. Louis, Mo. The project covers only the portion from
Sioux City, Iowa, to the mouth or approximately 760 miles of the
river.
   Existing project. The plan of improvement provides for a
series of levee units and appurtenant works along both sides of the
Missouri River from Sioux City, Iowa, to the mouth, for the pro-
tection of agricultural lands and small communities against floods.
The estimate of cost for that portion of the project from Sioux
City, Iowa, to Rulo, Nebr. (1954) is $45,555,000, of which $40,200,-
000 is Federal cost for construction and $5,355,000 is local cost for
lands and damages. This cost includes funds necessary to connect
one unit of this project to the authorized Hamburg, Iowa, project
on the Nishnabotna River.
   The existing project was authorized by the following Flood Con-
trol Acts:

     Acts                        Work authorized                                   Documents'
Aug. 18, 1941   Levees along both sides of the river from Sioux City   H. Doc. 821, 76th Cong., 3d sess.
                  to Kansas City.
Dec. 22, 1944   Extended project from Kansas City to the mouth and     H. Doe. 475, 78th Cong., 2d sess.;
                  provided for increased protection.                    S. Doe. 191, 78th Cong., 2d sess.
                                                                         S. Doec. 247, 78th Cong., 2d sess.

  1 Contain the latest published maps of Missouri River Basin.

  Local cooperation. Section 3 of the Flood Control Act approved
June 22, 1936, as amended by the Flood Control Act approved
December 22, 1944, applies. Units on which construction has
been completed have been turned over to local interests and local
cooperation requirements are being fulfilled in accordance with
formal assurances previously furnished. Local interests have
either furnished, or have indicated that they will furnish, assur-
ances of the required cooperation for units that are programmed
for construction.
  Operationsand results during the fiscal year. (Regular funds.)
Preparation of detailed plans and contract plans and specifications
was continued by hired labor. Preparation of a revised design
memorandum for Unit R-616 was completed and forwarded for
approval. Preparation of the revised design memorandum for
Unit L-614 was continued. Contracts for surfacing levee crests
                  FLOOD CONTROL--OMAHA, NEBR., DISTRICT                                             843

of units L-575, R-562, L-627-624, R-548, L-550, and L-536 were
completed.
  The total cost of new work during the fiscal year was $550,355.
  Conditions at end of year. Construction was initiated on the
project in November 1947 and is scheduled for completion in 1964.
Construction is complete on all units for which construction funds
have been appropriated. Engineering and design on the entire
project is about 69 percent complete. The entire project was ap-
proximately 35 percent complete, based on the present approved
estimate of cost.
  The total Federal cost of new work to the end of the fiscal year
was $13,865,962, all from regular funds.
                                    Cost and financial summary

                                            Fiscal year ending June 30                     Total to June
                                                                                          30, 1954, includ-
                                                                                          ing fiscal years
                             1950          1951        1952         1953        1954       priorto 1950

New work:
   Appropriated       -   $1,861,350    $1,615,000    $768,100     $179,000    $ 25,000       $13,942,450
   Cost.-   -     -        3, 533,966    2,593,247     720,331      848,240     550,355        13, 865,962


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954__               $76,347
    Appropriated for succeeding fiscal year ending June 30, 1955 -----     50,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955_ _ -___                                _                   126,347
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project   -------------------------------- 26,207,550

      12. COUNCIL           BLUFFS,          MISSOURI            RIVER        BASIN, IOWA
   Location. On the left bank of the Missouri River in the vicinity
of Council Bluffs, Iowa.
   Existing project. The plan of improvement provides for the
construction of levees and appurtenant works in the vicinity of
Council Bluffs, Iowa, on the left bank of the Missouri River, for
protection of municipal and industrial areas, from floods of past
magnitude. The existing project was authorized in the Flood
Control Act approved August 18, 1941, and in the Flood Control
Act approved December 22, 1944. The estimated cost of the im-
provement (1954) is $2,703,480, of which $2,557,680 is Federal
cost for construction and $145,800 is local costs for lands and dam-
ages.
   Local cooperation. Fully complied with.
   Operations and results during fiscal year. (Regular funds.)
This project was completed during fiscal year 1954. The major
item of work was the surfacing of the crest of the Indian Creek
levees. The final item of the project was turned over to local in-
terests on May 7, 1954. The total cost of new work during the
fiscal year was $43,872.
   Condition at end of fiscal year. Construction was initiated on
the project in July 1946 and was completed in fiscal year 1954.
The total Federal cost of the project was $2,557,680. In addition,
the sum of $12,840 has been expended from contributed funds.
844           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                      Cost and financial summary

                                                Fiscal year ending June 30                       Total to June
                                                                                                30, 1954, includ-
                                                                                                ing fiscal years
                               1950            1951          1952        1953        1954        priorto 1950

New work:
   Appropriated    -...        $400,000   -$    90,000       $75, 000   $200,000    -$77, 320        $2,557, 680
   Cost                         916,510        274, 273       93,016     100,896       43,872        12, 557, 680

1 In addition, the sum of $12,840 was expended from contributed funds.


                 13. OMAHA, MISSOURI RIVER BASIN, NEBR.
   Location. This project is located on the right bank of the Mis-
souri River in the vicinity of Omaha, Nebr.
   Existing project. The plan of improvement provides for the
construction of levees and appurtenant works along the right bank
of the Missouri River, for protection of municipal and industrial
areas, from floods of past magnitude. The existing project was
authorized in the Flood Control Act approved December 22, 1944
 (Public Law 534, 78th Cong., 2d sess.), as part of the general com-
prehensive plan for flood control in the Missouri River Basin. The
estimated cost of improvement (1954) is $6,258,374 of which
$5,896,374 is Federal cost for construction and $362,000 is local
cost for lands and damages.
   Local cooperation. Fully complied with.
   Operations and results during fiscal year. (Regular funds.)
This project was completed during fiscal year 1954, the final item
of the project being turned over to local interests on May 7, 1954.
The total cost of new work during the fiscal year was $2,203.
   Conditions at end of the fiscal year. Construction was initiated
in July 1946 and the project was completed during fiscal year 1954.
The total Federal cost of the project was $5,896,374.

                                      Cost and financial summary

                                                Fiscal year ending June 30                       Total to June
                                                                                                30, 1954, includ-
                                                                                                ing fiscal years
                               1950            1951          1952        1953        1954        prior to 1950


New work:
   Appropriated..--.....   $  335,000     -$    14,609 ...              $154, 600   -$3, 617        $5, 896, 374
   Cost.-------------       1,534,200          284, 807      $12, 973    148,887       2, 203        5, 896,374
                       FLOOD CONTROL--OMAHA, NEBR., DISTRICT                                            845

                   14. INACTIVE FLOOD CONTROL PROJECTS

                                                      For last      Cost and expenditures to     Estimated
                                                     full report,         June 30, 1954            amount
                 Name of project                          see                                     required
                                                       annual          Con-       Operation          to
                                                        report      struction       and          :complete
                                                         for-                    maintenance
Council Bluffs, Iowa (act of 1936)..............           1939               $325 ....-.-.
                                                                                         -(1) .
Belle Fourche, Cheyenne River, S. Dak.........             1940            37, 410 ......                      (1)
Missouri River, Niobrara, Nebr.........-.... .           - 1945            99, 370            $5, 633          (s)
Platte River near Schuyler, Nebr_.-----..--. .             1948            74, 940 ...........                 (s)
Nishnabotna River at Hamburg, Iowa .......... 1948                        236, 000 ...-....           -.       ()
Denison, East Fork of Boyer River, Iowa-......             1949             4, 300-..-.-..--....               (2)
Castlewood Dam and Reservoir, Cherry Creek                 1943            56, 721 .............           $14, 343, 279
  and tributaries, Colorado
Morrison, Bear Creek, Coleo  _-................            1950            30, 000 .......-.-.-.-               656, 000
Sioux City, Missouri River Basin, Iowa---------.........   1950             1,215--------------              1,228,749
Big Bend Reservoir, Missouri River Basin--......           1952   ............................              71, 500,000
Boulder, Cole _------------5                               1952
                                                  --------------     ---------               -----              551,000
Erie, Colo.--.-------------..-------_.                     1952 -------                                          59,000
Little Sioux River and its tributaries, Iowa-...... 1952                  152,100----------                  5, 457, 900
Elkhorn River Basin, Omaha district------...........       1952   ...-.-- ..--- ......-                      4, 052, 000
Disaster operation "Snowbound"...............              1952       7, 005, 939     . ..-....          .     (C)
South Platte River levees and channel improve-             1953   ..............---------------........    $31,800, 000
  ments, Chatfield Reservoir to Fort Morgan,
  Colo.

  1 Completed as a Public Works Administration project.
  2 All of the work contemplated under this authorization has been completed.
  sProject complete.

                             15. GENERAL INVESTIGATIONS

   Examinations and surveys, flood control studies. Reports on
the following investigations were submitted to the Chief of Engi-
neers during the fiscal year:
   Survey on Flood Control for Shell Creek and Its Tributaries,
Nebraska.
   Review on Flood Control for Gering and Mitchell Valleys, Ne-
braska.
   Work was continued on the following investigations during the
fiscal year:
   Survey on Flood Control for Floyd River and Its Tributaries,
Iowa (85 percent complete).
   Survey on Flood Control for James River and Its Tributaries,
N. Dak. and S. Dak. (22 percent complete).
  Survey on Flood Control for Platte River and Its Tributaries,
Nebraska (49 percent complete).
   Total cost of the above investigations for the fiscal year was
$41,201.        The unexpended balance of $2,386 will be applied toward
completion of these investigations.                          It is estimated that an addi-
846              REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

tional $64,800 can be profitably spent during fiscal year 1955 to
continue the program of flood control examinations and surveys as
follows: Floyd River, $14,000; James River, $30,800; and Platte
River, $20,000.
   Collection and study of basic data. Storm studies and sediment
studies, all of minor scope, pertaining to the analysis of basic data
for tributary streams and their basins were initiated during the
fiscal year. The cost of this work was $4,486. The unexpended
balance of $14 will be used to continue the studies.
   The scope of this program has been expanded to include hydro-
logic studies and the collection and analysis of noncooperative
stream and rain-gage data. The sum of $16,000 can be profitably
expended for the program during fiscal year 1955.
                       16. INSPECTION OF COMPLETED WORKS
   Inspections of completed flood protection projects constructed
with Federal funds in the Omaha District are made in accordance
with Federal Regulations to assure that the works are being prop-
erly operated and maintained and are in readiness to perform their
mission at all times.
   Inspection of completed works during the fiscal year 1954 con-
sisted of inspection of the following local flood protection projects:
Project                                                                                       Inspection cost
Belle Fourche, Cheyenne River, S. Dak .........                        ..................                       $115. 00
Fall River Basin, S. Dak. (Hot Springs Channel Improvement) ...................                                  125.00
City of Aurora, Westerly Creek, Colo............                   ..........-------------------------------...  150.00
Platte River Near Schuyler, Nebr .....----------                -                 ----------------                35.00
Omaha Missouri River Basin, Nebraska....              ...        ...................                             650.00
Councii Bluffs, Missouri River Basin, Iowa.                -.............    ........                            375.00
Agricultural Levee Unit L-627......         -----------------------------------.. 150.00
Agricultural Levee Unit L-624                ----------------------------------- 100.00
Agricultural Levee Unit R-580_                                                                                    50.00
Agricultural Levee Unit I-575........                                                                            450. 00
Agricultural Levee Unit L-561 .              ...
                                     -........                                        .             .            125.00
Agricultural Levee Unit L-550.........-----------------------------------225.00
Agricultural Levee Unit L-536.................. ...................------------..........
                                                                                       ....                      150.00
Agricultural Levee Unit R-573...........-----------------------------------                                       75.00
Agricultural Levee Unit R-562 ..-...  _-..-........-----------                                                    75.00
Agricultural Levee Unit R-548                                  ------------                                      150.00
          Total inspection cost..........
                                       ---------------.......                                   $3, 000.00

    The total cost during the fiscal year was $3,000.00.

                                         Cost and financial summary

                                                  Fiscal year ending June 30                  Total to June
                                                                                             30, 1954, includ-
                                                                                             ing fiscal years
                                  1950          1951            1952       1953     1954       priorto 1950

Maintenance:
    Appropriated .__     .         --             700----
                                                $__1, ..                   $2.000   $x,000             $6,700
    Cost..                                          234         $1,466 1    2,000    3,000              6, 700
                      FLOOD CONTROL--OMAHA, NEBR., DISTRICT                                           847
  17. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
   Snagging and Clearing of Navigable Streams and Tributaries
in the interests of Flood Control. (Section 13 of the 1946 Flood
Control Act.) No work was performed during the fiscal year.
                                   Cost and financial sunmlmar!/

                                            Fiscal year ending June 30                       Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                            1950         1951          1952       1953            1954       prior to 1950

New work:
   Appropriated   .        ----                                                    -                  $1,000
   Cost                            -                                                                   1,000



  Emergency Bank Protection (Section 14 of the 1946 Flood Con-
trol Act). Work during the fiscal year consisted of strengthening
2,572 linear feet of pile dike protecting the River Road at Sioux
City, Iowa, at a total cost of $46,202.

                                   Cost and financial summary

                                          Fiscal year ending June 30                         Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                            1950         1951          1952       1953            1954       prior to 1950

New work:
   Appropriated ..         $ 93,269     -$5, 905              _   $85,000    -$    7,019         $1, 103, 195
   Cost----------------     101, 782       6,972 ..-     -         27, 981        46, 202         1,099, 397


Other new work data: Unobligated balance, fiscal year ending June 30, 1954__ $3,798

   Small Flood Control Projects not specifically authorized by
Congress. (Section 212 of the 1950 Flood Control Act.) Costs
were incurred on the following projects during the fiscal year:
   Buffalo Creek, vicinity of Scranton, N. Dak.: Preparation of a
project report on the flood problem along Buffalo Creek. Work was
initiated in fiscal year 1953 and continued during fiscal year 1954
at a cost of $969.
   Spring Creek at Herreid, S. Dak.: Construction of a levee and
appurtenant works at Herreid, S. Dak. Work was initiated in fiscal
year 1953 and completed during fiscal year 1954 at a cost of
$42,672.
   Aurora, Westerly Creek, Colo.: Construction of a detention dam
and reservoir for the flood protection of Aurora, Colo. Work was
initiated in fiscal year 1953 and completed except for minor items
during fiscal year 1954 at a cost of $136,939.
   The total cost incurred during the fiscal year was $180,580.
848               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                               Cost and financial summary

                                                    EFiscal    year ending June 30                            Total to June
                                                                                                              30, 1954, includ-
                                                                                                              ing fiscal years
                                        1950        1951            1952         1953             1954         priorto 1950


New work:
    Appropriated-......__.____....         ..-                     $35,500
                                                                   $____        $152,500         $ 14,716             $202,716
    Cost_-                        _5,                                   661       11,623          180, 580             197, 864


Other new work data: Unobligated balance, fiscal year ending June 30, 1954__ $1,877

   Flood control emergencies--repairand flood fighting and rescue
work. (Section 210 of the 1950 Flood Control Act and supple-
mental authorization.) The following work was performed dur-
ing the fiscal year:
   Continuation of the 1952 flood damage repairs consisting of the
restoration of privately constructed levees by the placement of
earth fills and construction: of appurtenant- erosion protection
works; restoration of federally constructed Missouri River Agri-
cultural Levees; and repair of sewers, gate structures and appur-
tenances of the Omaha, Nebraska flood protection works.
   Repair of damage by the 1953 flood to the Floyd River channel
at: Sioux City, Iowa.
   Flood fighting and rescue work in connection with the 1954 flood
on the Big Sioux, Little Sioux, Floyd, and Vermillion Rivers; and
engineering studies for the repair of flood control structures dam-
aged thereby.
   The total cost of work performed duringthe fiscal yeaE was
$1,468,276.
                                               Cost and financial summary

                                                     Fiscal year ending June 30             .     .           Total to June
                                                                                                              30, 1954, includ-
                                                                                                      Sing        fiscal years
                                        1950        1951           1952          1953             1954         prior to 1950


Maintenance:
    Appropriated- ..... -$ 76, 826                 $464,094    .$4,974,i
                                                                       25     $5, 763,975   $      273,000        $14,113,022
    Cost--------------368,515                       243, 878     4864841       4,796, 536       1, 468, 276       113, 970, 162


  1 In addition, the sum of $40,838 was expended from contributed funds, and $100,000 from the appropria-
tion Mississippi River and tributaries.
     FLOOD CONTROL IMPROVEMENTS IN THE GARRISON,
                   N. DAK., DISTRICT

   This district comprises a portion of northwestern, southwestern,
and south central North Dakota, a small portion of northwestern
South Dakota, northeastern Wyoming, and southeastern Mon-
tana. It includes the watershed of the Missouri River and its
tributaries between the mouth of the Yellowstone River (N. Dak.)
and the North Dakota-South Dakota State line and that portion of
the James River Basin lying in North Dakota.
                                            IMPROVEMENTS

                                                Flood Control
                                                    Page                                                 Page
1. Missouri River Basin, Garrison                       4.   Inactive flood control projects ..-          853
    District   .                                    849 5.   General investigations ..............        854
2. Garrison Reservoir, Missouri                         6.   Inspection of completed projects             854
    River Basin, N. Dak.... ..                      850 7.   Flood control work under special
3. Mandan, N. Dak ........................          853                              _____
                                                               authorization______ ___...........        854

                1. MISSOURI RIVER BASIN, GARRISON DISTRICT
   Location. The flood control improvements included in this
project are located on and along the Missouri River and several of
the principal tributaries of the Missouri River.
   Existing project. The general comprehensive plan for flood
control and other purposes in the Missouri River Basin provides for
levees along the Missouri River between Sioux City, Iowa, and the
mouth and reservoirs located on the main: stem of the Missouri
River and on the tributaries for control of flood flows at the darn
sites. The existing project was authorized by the following flood
control acts:

       Acts                         Work authorized                                   Documents'
June 28, 1938     Adopted general comprehensive plan for Missouri         Flood Control Committee. Dec. 1,
                   River Basin and authorized $9,000,000 for initiation     75th Cong., 1st sess.
                   and partial accomplishment.
Aug. 18,1941      Modified the General comprehensive plan to include      H. Doc. 842, 76th Cong., 3d sess.
                   Harlan County Dam and Reservoir on the Repub-
                    lican River, Nebr. and authorized $7,000,000 for
                   additional expenditure.
Dec. 22, 1944     Expanded the general comprehensive plan for the         H. Doc. 475, 78th Cong., 2d sess.;
                   Missouri River Basin and authorized $200,000,000         S. Doc. 191, 78th Cong., 2d sess.;
                   additional expenditure.                                  S. Doc. 247, 78th Cong., 2d sess.
July 24, 1946     Authorized an additional expenditure of $150,000,000
                   for prosecution of the general comprehensive plan
                    for the Missouri River Basin.
May 17, 1950      Authorized an additional expenditure of $250,000,000
                    for prosecution of the general comprehensive plan
                    for the Missouri River Basin.


     ' Contain the latest published maps of Missouri River Basin.

                                                                                                849
850           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  Included in the comprehensive plan are the following projects in
the Garrison District:

                                                                                               Estimated
                                          Project                                             Federal cost


Garrison Reservoir, N. Dak_                                                                         279, 000, 000
                                                                                                   $-------------------------------------



   Operations during the fiscal year. The operations performed
during the fiscal year 1954 for projects on which work was under
way are given in the individual reports. Under sections 7 and 9
of Public Law 534, Flood Control Act approved December 22, 1944,
the Corps of Engineers is responsible for detailed scheduling of
operations of storage capacity reserved for or assigned to flood
control in reservoirs constructed by the Bureau of Reclamation, as
well as those constructed by the Corps of Engineers. The costs
during the fiscal year under this heading were $14,998.
  A balance of $130.00 is available for further work in connection
with the scheduling of flood control reservoir operations.
                                     Cost and .financial summary

                                             Fiscal year ending June 30                      Total to June
                                                                     _______30,                1954, includ-

                              1950          1951        1952        1953          1954
                                                                                             ing   fiscal years
                                                                                              prior to 1950


Maintenance:
   Appropriated- .......-             -      $6, 500    $3, 000      $3, 000      $12, 000                $24, 500
   Cost--                      -              6,500        875        1, 997       14, 998                 24, 370



  2. GARRISON RESERVOIR,                           MISSOURI       RIVER BASIN, N. DAK.
   Location. The Garrison dam site is located on the Missouri
River in McLean and Mercer Counties, N. Dak., about 11 miles
south of Garrison, N. Dak., and 9 miles west of Coleharbor, N. Dak.
The site is 1,455.0 (1941 adjusted river miles) miles above the
mouth of the river and 77 miles above Bismarck, N. Dak.
   Existing project. The project plan provides for the construc-
tion of a dam and reservoir for flood control, irrigation, navigation,
hydroelectric power, and other purposes. The dam will be a rolled
earth-fill structure with a crest length of 12,000 feet and a maxi-
mum height of 210 feet. The spillway will be controlled by 28
tainter crest gates 29 feet high and 40 feet long located in the east
abutment. Reinforced concrete outlet works containing five power
tunnels and three flood-control tunnels will be located in the west
abutment. A hydroelectric power generating plant will be located
adjacent to the outlet works. The reservoir will have a gross stor-
age capacity of 23,000,000 acre-feet for multiple purpose use in-
cluding 4,900,000 acre-feet as dead storage. The existing project
was authorized by the Flood Control Act approved December 22,
1944 (Public Law 534, 78th Cong., 2d sess.), as part of the general
comprehensive plan for flood control and other purposes in the Mis-
souri River Basin. The estimated cost, $279,000,000 (July 1954)
is for the initial project only, which includes initial power installa-
                 FLOOD CONTROL-GARRISON, N. DAK., DISTRICT        851
tion of three 80,000 kilowatt units and initial protection in the
vicinity of Williston, N. Dak., but is exclusive of diversion into the
Dakotas.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies. ($24,000 contributed by local interests
specifically for the construction of the New Town School.)
   Operationsand results during the fiscal year. Surveys, founda-
tion explorations, engineering studies, sedimentation program, and
designs for the detailed plans were continued during the fiscal year.
General design memoranda were completed for protective works
for Williston and vicinity. Plans and specifications were completed
for the following major items:
   Embankment-stage V, reservoir clearing-stage I, relief well
channel, spillway monorail hoist, Snake Creek-U.S. 83-paving,
spillway stop-log hoists, trash racks, several Indian road reloca-
tions; and miscellaneous minor items. Negotiations were com-
pleted for relocation of several utility cooperatives, county roads
and minor items. Master reservoir plan was completed. Construc-
tion features completed during the year included: relocation of sev-
eral Indian reservation roads, BIA streets, buildings and utilities,
Indian cemeteries, Snake Creek-embankment and relief wells,
Sanish Bridge substructure, and Otter Tail Power Company electric
lines; reservoir clearing-stage I; embankment--stage IV; a num-
ber of riprap contracts; west abutment grouting-section IV; east
abutment grouting-section I; embankment relief wells and chan-
nel; intake structure; hoists, gates and other operating equipment;
auto transformers; permanent water intake-Riverdale; several
items of permanent operating equipment and other minor items.
   In addition the following items of work were carried on or
initiated during the fiscal year: Embankment--stage V; relocation
of BIA buildings, schools, streets, and utilities; New Town School;
reservoir clearing--stage I; west and east abutment grouting;
embankment relief wells and channel; spillway gate hoists; trash
racks; powerhouse and switchyard; penstocks and surge tanks;
main control switchboards; station switchgear and transformers;
15 KV switchgear and generator leads; switchyard steel and equip-
ment; oil circuit breakers; oil filled pipe cable system; two 300-ton
cranes; turbines, governors, and generators; spillway structure and
gates;. concrete aggregates Sanish Bridge superstructure; reloca-
tion of Indian roads, township, county, state, and Federal high-
ways; relocation of railroads and telegraph lines; relocation of
public utilities; several items of permanent operating equipment;
and miscellaneous minor hired labor and contract items.
   Preparation of engineering data, tract maps, appraisal reports,
and acquisition of lands in the construction and reservoir areas
were carried on throughout the fiscal year. The total cost of new
work during the fiscal year was $42,699,677* from regular funds.
   Condition at end of fiscal year. In addition to completion of
contract plans and specifications as listed in the preceding section,
preliminary studies, design and preparation of plans and specifica-
tions are underway for the spillway stilling basin, protective works-
Williston, reservoir clearing-stage II, east abutment grouting-
* Exclusive of $24,000 expended from contributed funds.
852             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

section III, 12.5 KV connection to spillway, dam and roadway
lighting, Williams County roads-bridges, and permanent operating
equipment. Negotiations, plans and specifications are in progress
for various relocation features. A program of sedimentation
studies and degradation investigations is being continued. Field
investigations and laboratory tests on foundation and embankment
materials are in progress. Permanent work on the project is ap-
proximately 73 percent complete. The percentage of completion
ot the following major features at the end of the fiscal year is as
follows :
       -Features                                                                                        Percent
                                                                                                       complete
Lands and damages              ..        ........-----------------------------------------          --- 83
Relocations----------                          ------------------------------------------                  54
     Roads------            ---------                   ---------------------------------------            74
     Railroads--------------------------------------------------                                           89
     Cemeteries, utilities, structures.....-----------------------------------                             24
Reservoir and pool preparation                     .....----------------------------------          ---- 37
Damn...     -----..-------------..-..                    -----------------------------                     7..7....-
                                                                                                           77
Power plant...................                                                                             55
     Powerhouse------------------------------------------------- 65
     Turbines and generators-----...............................----------------------------------         44
     Switchyard, accessory, and miscellaneous.--------------------------                                   57
Roads, railroads, and bridges               ......        --------------------------------------- 72
Recreation facilities .          .............--------------------------------------------             -- 19
Buildings, grounds, and utilities..-------------------------------------.95
Permanent operating equipment-----..............--------------------------------                           33
Engineering and design          .......                             .                        ..------------------------------.
                                                                                                           84

Total cost of new work to the end of the fiscal year was $202,927,-
529 from regular funds, and $24,000 from contributed funds.
                                       Cost and financial summary

                                              Fiscal year ending June 30                       Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                                1950         1951         1952         1953          1954       priorto 1950


New work:
    Appropriated- ._.       $27, 500,000 $30,969,000 $37, 083,700 $30, 848,000 $27, 500,000       $206, 680, 70(
    Cost -----               29,978,079 29, 045, 251  25, 801, 808 32,125,643 42,699,677           202,927,529


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_---------                             $1,734,006
    Appropriated for succeeding fiscal year ending June 30, 1955-                               25,000,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955_          -----------------------------                                         26,734,006
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project_---------------                        -                         47,319,30(E

                                       Cost and financialsummary

                                              Fiscal year ending June 30                      Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                                1950         1951         1952         1953         1954       prior to 1950


New work:
    Appropriated .-----------------------------------------------                   $24,000            $24 00
    Cost-.         ------                                                     --     24,000             24 009
                    FLOOD CONTROL-GARRISON, N. DAK., DISTRICT                                                               853

                                       3. MANDAN,                    N. DAK.
   Location. This project is located on both banks of the Heart
River at Mandan, N. Dak.
   Existing project. The plan of improvement provides for the
construction of levees and appurtenant works along the left bank
of the Heart River for the protection of municipal areas and along
the right bank of the Heart River for the protection of the State
Training School.
   The existing project was authorized in the Flood Control Act
approved July 24, 1946. (See H. Doc. 294, 79th Cong., 1st sess.);
by the Third Deficiency Appropriation Act of 1949, approved Oc-
tober 10, 1949; and as modified by the Flood Control Act approved
May 17, 1950. The estimated cost of improvement (July 1954) is
$691,000, of which $552,000 is Federal cost for construction and
$139,000 is local cost for lands and damages.
   Local cooperation. Local interests have met the requirements
of local cooperation in connection with the levee project, but have
not yet furnished the required assurances in connection with in-
terior°' drainage facilities.
   Operations and results during the fiscal year. The operation
and maintenance manual was completed. The total cost during the
fiscal year was zero.
   Condition at end of fiscalyear. Construction of levees, and
appurtenant facilities is complete. The operation manual is com-
plete and record drawings for the project and plans and specifica-
tions for interior drainage facilities are essentially complete. The
cost to June 30, 1954, was $480,144, all regular funds.
                                       Cost and financial summary

                                               Fiscal year ending June 30                                     Total to June
                                                                                                             30, 1954, incluid-
                                                                                                             ing fiscal years
                                1950          1951             1952         1953                 1954          priorto 1950


New work:
   Appropriated--------        $177,700 --                                                                           $551,700
    Cost----------------        380,735       $22,162            $1,902      $1,467                                    480,144

Other new work data: Unobligated balances available for succeeding fiscal
      year ending June 30, 1955  ____--- _--      -______ -      __     _ 1 $71,556
  1$71,556 funds revoked during fiscal year 1954 restored in fiscal year 1955.
                     4. INACTIVE FLOOD :CONTROL PROJECTS
     ..                                                   For last      Cost and expenditures to
                                                          For last            June 30, 1954                     Estimated
                                                        full report,                                    ,,        amount
                   Name of project                          see                                                  required
                                                          annual           Con.                Operation            to
                                                          report         struction                and           complete
               -                                           for-                               maintenance
1. Jamestown Reservoir, N. Dak..                --            1950
                                              ---....---.......             $40, 000.............                     (1)
2. Marmarth, Little Missouri River, N. Dak....              1938             ..............                          (2)


  1Reservoir now  under construction by the Bureau of Reclamation.
   =The leveesystem at the town of Marmarth, N. Dak., was improved by the Works Progress Adminis-
tration. An investigation of the project to improve existing levees to protect the principal portion of the town
of Marmarth against floods showed that the authorized project was inadequate, consequently an interim
report (Senate Document No. 134, 81st Congress, 2d Session) to the review report on the Little Missouri
River has been prepared which recommends authorization of a more comprehensive flood control project
at Marmarth, N. Dak. Local interests have furnished tentative assurances that they will furnish necessary
local cooperation for this recommended project.
854                    REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                 5. GENERAL INVESTIGATIONS
   Examinations and surveys--flood control studies. The cost of
work on examinations and surveys was $27,146, and the unex-
pended balance on June 30, 1954, was zero. Funds in the amount
of $6,800 can be profitably expended for continuation of work on
examinations and surveys presently assigned to this office.
   Collection and study of basic data. Preparation of the Flood
Emergency Manual and nonproject studies pertaining to relation-
ships between rainfall and resulting runoff, analysis of past floods,
and related hydrologic studies were completed at cost of $1,950 for
the fiscal year. A balance of $50 is available for further work in
this category.
                         6. INSPECTION         OF COMPLETED                 PROJECTS
  Inspection of completed works during the fiscal year in the Gar-
rison District consisted of inspection of the following local flood
protection project:
                       Project                                                                           Inspection cost
Mandan Levee, Mandan, N. Dak                                                                                 $547.00
                                                                                                       -........


  The total cost during the fiscal year was $547.00. The unex-
pended balance of $168.00 is available for further work under this
heading.
                                         Cost and financial summary

                                               Fiscal year ending June 30                               Total to June
                                                                                              __       30, 1954, includ-
                                                                                                       ing fiscal years
                                  1950        1951           1952        1953             1954          prior to 1950

Maintenance:
   Appropriated_                                 $500 - -           -       $500             $300                $1,300
   Cost ...------                                    230        $249            106              547               1,132



  7. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
  Emergency bank protection. (Section 14 of the 1946 Flood
Control Act.) No work was performed during the fiscal year.
                                         Cost and financial summary

                                                 Fiscal year ending June 30                             Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                                 1950         1951           1952        1953             1954          prior to 1950

New work:
   Appropriated_                                     -.---    --
                                                             $50,000    -$ 2,603 ...                            $47,397
   Cost .-   --   __     .                    --------        31,245      16,152      .                          47, 397
               FLOOD CONTROL--GARRISON, N. DAK., DISTRICT                                          855
  Flood Control Emergencies--Repair and Flood Fighting and
Rescue Work.   (Section 210 of the 1950 Flood Control Act and
supplemental authorizations.)                          Flood fighting and rescue work
was performed during the fiscal year at a cost of $2,931.
                                      Cost and financial summary

                                               Fiscal year ending June 30                 Total to June
                                                                                         30, 1954, includ-
                                                                                         ing fiscal years
                              1950          1951        1952         1953       1954      prior to 1950

Maintenance:
                --
   Appropriated _        -   -$      372   $141, 530    $10, 000     $80, 000                    $381, 208
   Cost ---         --            7, 345    136,972      14,558       77,068    $2,931            381,208
       IMPROVEMENT OF RIVERS AND HARBORS IN THE
               FORT PECK, MONT., DISTRICT

   This district comprises all of Montana east of the continental
divide except the Little Missouri River watershed; the small por-
tions of western North Dakota embraced in the watersheds of
Yellowstone River, and Big Muddy Creek; and northern Wyoming
embraced in the drainage basin of the Missouri River and trib-
utaries above the mouth of the Yellowstone River, inclusive.
                                                       IMPROVEMENTS

                         Navigation                                                 Flood Control-Continued
                                                              Page                                                                     Page

1. Missouri River at Fort Peck,                            Mont_.                  .........-------------------.                      863
      Mont......................___.........__        7. Sheridan, Yellowstone River
                                                  -. 857
2. General investigations---------..............    860    and Tributaries, Wyo------...........                                      864
3. Inactive navigation projects ....                 8. Greybull, Yellowstone River,
                                                     861
                                                            Wyo...                   ----..- --..................................      864
              Flood Control                           9. -Inactive flood control projects..                                            865
                                                     10. General investigations................                                        865
4. Missouri River Basin, Fort                       11. Inspection of completed proj-
      Peck District............................861          ects.................................--...........--------------           866
5. Havre, Milk River, Mont..........            862 12. Flood control work under spe-
6. Billings, Yellowstone River,                            cial authorization .....--------....----                              ..   866

                     1. MISSOURI                 RIVER            AT FORT PECK, MONT.
   Location. The site of the Fort Peck Reservoir is in the Mis-
souri River Valley in McCone, Valley, Garfield, Phillips, Petro-
leum, and Fergus Counties, Mont. The dam site is approxi-
mately 11 miles above the mouth of the Milk River in sections 14,
15, 16, 21, and 22, T. 26 N., R. 41 E. The west (left) abutment is
in Valley County and the east (right) abutment is in McCone
County. Nearest towns are Glasgow, 17 miles northwest, and
Nashua, 9 miles north.
   Existing project. The project provides for construction of an
earth dam and power plant for impounding water for the improve-
ment of navigation on the Missouri River, Sioux City to the mouth,
for the production of power, and for flood control, irrigation and
related uses, as a unit in the main stem system of reservoirs. The
estimate of cost for new work (July 1954) is $158,300,000. De-
tailed data regarding the project are as follows:
                                                             Description

Location, miles above mouth of Missouri River ........... ----------------------                                              1, 868.7
Concrete spillway in right abutment, discharge capacity (second-feet)....                                                     250, 000
Height of main dam above stream bed (feet) _.........................---...                                                     250. 5
Height of crest stone above stream bed (feet) ....................................-......                                      250.0
Elevation of crest stone (feet, mean sea level)..................................                                            2,280.0
Tunnels for releasing water from reservoir (4), diameter (feet) ..............                                                  24'8"
Powerplant-initial installation, one 35,000-kilowatt unit and one
  15,000-kilowatt unit (kilowatts) .....  .. .............         ....................                                 ..      50, 000
                                                                                                                        857
858                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                    Descriptions-Continued

Powerplant-present installation, two 35,000-kilowatt units and one
  15,000-kilowatt unit (kilowatts) .......------------..............................--------------..................-----.      85, 000
Powerplant-installation presently planned: two 35,000-kilowatt units,
  one 15,000-kilowatt unit and two 40,000-kilowatt units (kilowatts)._..                                                       165, 000
Maximum pool level (feet, mean sea level) ...                       ...........................             .                    2, 250
Normal pool level (feet, mean sea level) ........ _........._-                                               ..-...              2, 246
Crest length of dam (feet)..--------------..----------------...--..------...                                                    21,026
Maximum storage capacity (acre-feet)                                              ....--------------------------           19, 412, 000
Maximum surface area of reservoir (acres) ...................                                                                  245, 000
                                                                                                              .....-------------------------
Maximum length of reservoir (miles)           ......................-----------------------------.....                              189
Clear width of reservoir (miles) ..   ------------....----......----..----. ..----....--                               :             16
Normal operating storage capacity (acre-feet)--..--...-.                             ...........                           18, 400,000
Total construction cost of project (estimated)..........-----------.....                        (Jul. 1954) 158,300, 000
Annual operation and maintenance cost (estimated) .-------....... (Jul. 1954)                                                $310,000
Date construction started, Oct. 23, 1933
Date of completion, June 30, 1960 (estimated)
Datum--mean sea level (1929 adjustment, U. S. Coast and Geodetic
  Survey).
     The existing project was authorized by the following acts:
       Acts                                Work authorized                                                 Documents
Aug. 30, 19351      Construction of earth dam ..................---------------------      H.     Doc. 238, 73d Cone., 2d sess.
May 18, 19382       Completion, maintenance, and operation of a hydro-                          (Specified in act.)
                      electric powerplant, subject 'to certain provisions
                      contained in the act respecting the transmission
                      and sale of electric energy. This act also authorizes
                      the installation of additional power generating
                      facilities by the Secretary of War when deemed
                      necessary in the judgment of the Bureau of Rec-
                      lamation.
Dec. 22, 1944 s Modified authorization to provide for full multiple                        H.    Doc. 475, S. Doc. 191 and S.
                 purpose operation.                                                             Doc. 247, all of 78th Cong.,
                                                                                                2d sess.
June    3, 1948 4 Payments to be made to school districts serving proj-                    (Specified in act.)
                      ect as reimbursement for educational facilities (in-
                      cluding transportation to and from school) to
                      pupils who are dependents of persons engaged in
                      the construction, operation, and maintenance of
                      the project.

  1 Included in Public Works Administration program in 1933.
2  Pub. Law 529, 73d Cong., 3d sess.
  a Pub. Law 534, 78th Cong., 2d sess.
  4Pub.  Law 586, 80th Cong., 2d sess.

   Maps showing transportation facilities, power-market area,
powerplants, etc., are contained in Senate committee print, 75th
Congress, 2d session.
   Local cooperation. None required.
   Terminal facilities. None
   Operation and results during the fiscal year. New work ac-
complished during the fiscal year included completion of contract
construction on slope stabilization in the tunnel outlet area; com-
pletion of a preliminary design contract and the initiation of a
continuing contract for the preparation of final designs and plans
and specifications for the second powerplant; and miscellaneous
hired labor planning and construction work on the first power plant,
dam, tunnels, spillway, recreational facilities, and planning and
exploratory work for the second power plant. The total cost of
new work was $257,130, all regular funds:
   Operation and maintenance: The reservoir was operated
throughout the fiscal year for the maintenance of navigation on
the Missouri River, and incidental purposes of flood control and
hydroelectric power production. Releases for these purposes also
        RIVERS AND HARBORS-FORT PECK, MONT., DISTRICT                         859
served the needs for water supply and sanitation along the river
below the dam. Total releases from the reservoir amounted to
about 7,600,900 acre-feet, equivalent to a mean annual flow of about
10,500 cubic feet per second. The gross electric energy produced
by the three generating units amounted to 614,963,700 kilowatt-
hours. The net electric energy generated, exclusive of power for
station use, was 613,983,000 kilowatt-hours. In addition to the
operation and maintenance of the reservoir, dam, spillway, tun-
nels, power plant, operators' village facilities, etc., a program of
sediment studies and an experimental contract for upstream face
riprap repairs on Dam was accomplished. The total cost of oper-
ation and maintenance during the fiscal year amounted to $736,-
511. Reimbursement from the Bureau of Reclamation for the pro
rata share of the cost of operation and maintenance of the power
plant, reimbursement from other districts for the pro rata share
of costs of the sediment studies, reimbursement resulting from
furnishing of operators' village facilities, and distribution of pro
rata share of camp operation cost to other funds reduced the net
cost to $394,829, all regular funds.
   Condition at end of fiscal year. The status of the existing proj-
ect as a whole is 84 percent complete. The major items of work
remaining to be completed are the second power plant and the
permanent operators' quarters. Work was started in October
1933 and is scheduled for completion in June 1960; however, all
work except the second power plant and the permanent operators'
quarters is scheduled for completion by the end of June 1955.
   Dam: Clearing and grubbing, stripping the base of the dam, con-
strUction of sheet piling cutoff wall, the rock and gravel toes, the
hydraulic fill, raising the crest of the dam to 2280.5 feet mean sea
level, construction of a bituminous surfaced roadway thereon, and
installation of a night lighting system are complete. The following
quantities have been placed:
                                                                       Cubic yards
   Hydraulic fill
                ..............             ......                 .....
                                                                     122, 178, 000
   Rolled fill
            ........
               ..                                                       3,450, 288
   Gravel at toe of dam -.-.-
                         .. .        .. . ..........      -   -         3,112, 904
   Rock at toe of dam        - -....                                      289, 297
   Gravel on upstream face of dam.......                                  797, 236
   Fieldstone on upstream face of dam__........______..                   209, 070
   Salvage field stone on upstream face of dam-...........        129, 887
   Quarry stone on upstream face of dam..                           4, 198
                                                      ... .___.. 5.......__.__
                                                                   89. 427
   Salvage quarry stone on upstream face of dam .........................

A total of 13,847,287 cubic yards of material has been removed
from the spillway channel and 268,625 cubic yards of concrete has
been placed in the channel lining; 291,826 cubic yards of concrete
have been placed in the bridge, columns, piers, foundations, floor
slab, and training wall of the gate structure. Sixteen gates have
been erected and the operating equipment installed. Spillway stop
logs have been installed as well as the hoist car. The four diver-
sion tunnels, having an aggregate length of 25,294 linear feet, are
practically complete with the exception of the revision of flow
regulation facilities for tunnels 3 and 4. The dam and appurtenant
works are approximately 99 percent complete.
   Reservoir: Acquisition of land for the reservoir and dam site
860            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

areas is complete. A total of 289,009 acres have been acquired of
which 119,671 acres were public domain land.
   Power plant: The first power plant and appurtenant works are
98 percent complete. Two 35,000 kilowatt units and one 15,000
kilowatt generating unit are in operation. A preliminary design
contract for the second power plant has been completed and a final
design and plans and specifications contract has been initiated.
Hired labor planning and exploration work on the second power
plant are being continued.
   The work remaining to complete the project consists of com-
pleting the second power plant, completion of the permanent oper-
ators' quarters, and miscellaneous items to complete the dam and
appurtenant works, and the first power plant.
   The total cost of new work to June 30, 1954, is $132,529,089 of
which $55,887,775 was regular funds; $8,650,000 were power plant
funds; $49,521,087 were public works funds; and $18,470,227 were
Emergency Relief funds. The total cost of operation and main-
tenance was $4,808,374 as of June 30, 1954.
                                       Cost and financial summary

                                                Fiscal year ending June 30                     Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                                1950          1951         1952        1953        1954        priorto 1950

New work:
   Appropriated .--          $2, 500, 000    $883, 000   $644, 000     $25, 000   $150, 000      $132, 793, 771
   Cost_-----------   ----    2, 699,125    2, 608,833    821, 015     282, 721    257, 130       132, 529, 089
Maintenance:
   Appropriated ------.         478, 500      567, 500    490, 000     300, 000    325, 000          4, 859, 376
   Cost_-- -------------        478, 500      520, 925    474, 111     241, 634    394, 829          4, 808, 374



Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954         - -          $128,602
    Appropriated for succeeding fiscal year ending June 30, 1955_ - -           220,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955_--                                                               348,602
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project_ _                               ___        25,286,229
                                                                       _-___-_

                              2. GENERAL INVESTIGATIONS
Examinations and surveys, navigation studies. There was no
work accomplished and no cost incurred during the fiscal year.
                                       Cost and financial summary

                                               Fiscal year ending June 30
           RIVERS AND HARBORS-FORT PECK, MONT., DISTRICT                                             861
                      3. INACTIVE NAVIGATION PROJECTS
                                                     ::For last   Cost and expenditures
                                                    full report      toJune 30, 1954            amount
                Name of project                          see                                   required
                                                      annual        Con-       Operation          to
                                                      report      struction       and          complete
                                                       for-                   maintenance
Claimsfor damages, river and harbor work.--.... .....--    .          $9, 297                      ()------------
Expenditures
  i.         in connection with disaster opera-       1949            14, 000 .-- --               (1)
tion "Snowbound"

  1 Operation completed.



           4. MISSOURI            RIVER     BASIN, FORT PECK                    DISTRICT

   Location.         The flood control improvements included in this proj-
ect are located on and along the Missouri River and several of the
principal tributaries of the Missouri River and are located in the
States comprising the Missouri River Basin.
   Existing project. The general comprehensive plan for flood
control and other purposes in the Missouri River Basin provides for
levees along the Missouri River between Sioux City, Iowa, and the
mouth, and reservoirs located on the main stem of the Missouri
River and on the tributaries for control of flood flows at the dam
sites. The existing project was authorized by the following Flood
Control Acts:

    Acts                          Work authorized                                 Documents'

June 28,1938   Adopted general comprehensive plan for Missouri         Flood Control Committee Doc. 1
                 River Basin and authorized $9, 000,000 for initia-      75th Cong., 1st sess.
                 tion and partial accomplishment.
Aug. 18,1941   Modified the general comprehensive plan to include      H. Doc. 842, 76th Cong., 3d seas.
                 Harlan County Dam and Reservoir on the Repub-
                lican River, Nebr., and authorized $7,000,000 addi-
                 tional expenditure.
Dec. 22,1944   Expanded the general comprehensive plan for the         H. Doc. 475, 78th Cong., 2d sess.;
                 Missouri.River Basin and authorized $200,000,000       S. Doc. 191, 78th Cong., 2d sess.;
                 additional expenditure.                                S. Doc. 247, 78th Cong., 2d sess.
July 24,1946   Authorized an additional expenditure of $150,000,000
                for prosecution of the general comprehensive plan
                for the Missouri River Basin.
May 17, 1950   Authorized an additional expenditure of $250,000,000
                for prosecution of the general comprehensive plan
                for the Missouri River Basin.

1 Contain the latest published maps of Missouri River Basin.


   Condition at end of fiscal year. Under sections 7 and 9 of Pub-
lic Law. 534, Flood Control Act approved December 22, 1944, the
Corps of Engineers is responsible for detailed scheduling of oper-
ations. of storage capacity reserved for or assigned to flood control
in reservoirs constructed by the Bureau of Reclamation, as well
as those constructed by the Corps of Engineers. Cost incurred dur-
ing the fiscal year was $46,966.
862           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                     Cost and financial summary

                                           Fiscal year ending June 30                    Total to June
                         i                                                              30, 1954, includ-
                                                                                        ing fiscal years
                              1950        1951        1952        1953       1954         prior to 1950

Maintenance:
   Appropriated_ -_      ---      .       $22, 000   $38, 200     $34, 000   $33, 200
                                                                              46,966
                                                                                                $127, 400
   Cost--_____________   ____________      14,047     30,871       32,768                        124,652


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954             -    -    $2,011
    Appropriated for succeeding fiscal year ending June 30, 1955        - - - - 34,000
    Unobligated balances available for succeeding fiscal year ending June 30,
        1955-_                 -36,011


                             5. HAVRE, MILK RIVER,                MONT.
   Location. The work covered by this project is located at Havre
and vicinity on Milk River, Mont., 401.8 river miles upstream from
its confluence with the Missouri River.
   Existing project. The plan of improvement provides for the
protection of areas subject to flooding in the city of Havre, Mont.
The project includes two units, the Bull Hook unit and the Milk
River unit. The Bull Hook unit consists of 2 rolled earthfill dams,
1 on Scott Coulee and 1 on Bull Hook Creek, approximately 2,500
feet south of the city; a diversion channel to connect Scott Coulee
to Bull Hook Creek just upstream of the dams; a combined dis-
charge and spillway channel to divert flood flows into a coulee
emptying into Milk River just east of the city; a small diversion
dam in this coulee and a spillway to divert extreme flood flows into
a drainage area to the northeast. The Milk River unit consists of
a system of levees on both banks of the Milk River along the
northern edge of the city, and provisions for pumping internal
drainage and sewage during high water periods. The project was
authorized by the Flood Control Act approved December 22, 1944
 (S. Doc. 103, 78th Cong., 1st sess.). The current estimated Federal
cost (July 1954) is $1,950,000; the estimated local cost (July 1954)
is $162,000 for utility modifications, lands, rights-of-way, ease-
ments, relocations, and damages.
   Local cooperation. In addition to the usual requirements for
local cooperation as provided by law, local interests are required
to move certain buildings, raise the railroad and highway grades
and provide structures, move a powerline, and construct fences
and road crossings. Local interests have indicated their willing-
ness and ability to comply with all requirements.
   Operation and results during the fiscal year. Work was con-
tinued on field surveys and investigations and detailed plans, and a
construction contract was initiated on the Bull Hook Unit. The
total cost during the fiscal year was $326,373.
   Condition at end of the fiscal year. Preparation of detailed
plans for Bull Hook Unit is 100 percent complete and for Milk
River Unit is 75 percent complete. Construction of the Bull Hook
Unit is approximately 25 percent complete. The total cost to June
30, 1954, was $478,378, all regular funds.
                FLOOD CONTROL--FORT PECK, MONT., DISTRICT                                       863
                                 Cost and financial summary

                                         Figcal year ending June 30                    Total to June
                                                                                      30, 1954, includ-
                                                                                      ing fiscal years
                          1950          1951         1952       1953       1954        priorto 1950

New work:
   Appropriated ..        $7, 000       $10, 000 .             $348,000   $400,000            $850, 000
   Cost----- - - --   .    9, 822   1    12, 026       $392      50,005    326, 373            478,378


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954----                 $31,839
    Appropriated for succeeding fiscal year ending June 30, 1955--------- 500,000
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955      ---------------------- -------------------------- 531,839
    Estimated additional amount needed to be appropriated for completion
      of existing project      ------------------------------------ 600,000

                 6. BILLINGS, YELLOWSTONE                     RIVER, MONT.

   Location. The work covered by this project is located at Bill-
ings and vicinity on Yellowstone River, Mont., 346 river-miles up-
stream from its confluence with the Missouri River.
   Existing project. The overall plan of improvement for the flood
protection of Billings and contiguous areas consists of a system of
ditches, channels, and levees by means of which floodwaters ap-
proaching the city from the west, east, or south may be diverted
away from the area subject to flooding. The proposed plan is
divided into three separate units. The western unit of the plan
consists of an interception ditch which will divert runoff from
west of Billings into the Yellowstone River. Reinforced concrete
spillways will divert storm waters from four irrigation canals
which cross the alinement of the proposed interception ditch, and
drainage from other areas will enter the ditch through control
spillways. Necessary appurtenances to the interception ditch are
a reinforced concrete stilling basin, earth levees, a reinforced con-
crete chute and stilling basin. A railroad bridge and several addi-
tional highway bridges, over the proposed interception ditch and
other similar improvements, will be necessary for completion of
this unit. The eastern unit of the plan is designed to protect the
fairgrounds and adjacent areas east of Billings from floods on
Alkali Creek. The proposed plan consists of two sections of levee
along the right bank of the existing channel; a cutoff channel 510
feet long excavated through the rock escarpment; and an enlarge-
ment of the existing channel from the stilling basin to the Yellow-
stone River. A railroad bridge will be necessary for this unit.
The southern unit of the overall plan is designed to protect the
areas south and east of Billings from floods on the Yellowstone
River. This unit consists of a levee beginning at high ground
south of the city and extending 25,475 feet along the left bank of
the river, and necessary appurtenant interior drainage structures.
An existing levee will be incorporated into the proposed works.
The project was authorized by the Flood Control Act approved
May 17, 1950 (H. Doc. 216, 81st Cong., 1st sess.). The estimated
Federal cost (July 1954) is $3,800,000; the estimated local cost
(July 1954) is $302,000 for relocations, lands, and damages.

       Sig 28--863-894
864              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  Local cooperation. In addition to the usual requirements for
local cooperation as provided by law, local interests are required
to remove or relocate all structures at or near the alinement of
the proposed work, provide all bridges and similar improvements,
and construct or relocate roads. Local interests have indicated
their willingness and ability to comply with all requirements.
   Operation and results during the fiscal year. No work was ac-
complished during the fiscal year.
   Condition at end of fiscal year. No work has been initiated.
                             Cost and financial summary
Other new work data: Appropriated for succeeding fiscal year ending June 30,
  1955 __----_                                                                 $25,000


                  7. SHERIDAN, YELLOWSTONE            RIVER, WYO.
    Location. The work covered by this project is located at Sheri-
dan and vicinity on both sides of Goose Creek approximately 11.6
miles above the junction of that stream with the Tongue River.
   Existing project. The overall plan of improvement for flood
protection at Sheridan consists of a system of levees and flood walls
in combination with alterations of the channels of Goose Creek
and Little Goose Creek. The area subject to flooding from Little
Goose Creek will be protected by approximately 12,800 feet of
levee, 2,750 feet of vertical concrete flood wall and approximately
1,500 feet of new channel. The proposed works for protection of
areas along Big Goose Creek include approximately 1,700 feet of
new channel, 28,600 feet of levee, 330 feet of concrete flood wall,
and 9,500 feet of improved channel. Riprap will be placed on
earth slopes for a distance of 50 feet above and below all bridges,
and the outside banks on all curves where erosion is likely to occur.
Grouted riprap will be placed in drop sections of both streams.
The project was authorized by the Flood Control Act approved
May 17, 1950 (H. Doc. 216, 81st Cong., 1st Sess.). The estimated
Federal cost (July 1954) is $2,360,000; the estimated local cost
 (July 1954) is $42,000 for relocations, lands, and damages.
   Local cooperation. In addition to the usual requirements for
local cooperation as provided by law, local interests are required
to remove or relocate all structures at or near the alinement of
the proposed work, provide all bridges and similar improvements,
and construct or relocate roads. Local interests have indicated
their willingness and ability to comply with all requirements.
   Operation and results during the fiscal year. No work was ac-
complished during the fiscal year.
   Condition at end of fiscal year. No work has been initiated.

                 8. GREYBULL, YELLOWSTONE            RIVER, WYO.
   Location. The work covered by this project is located at Grey-
bull and vicinity on Big Horn River, Wyo., 183 river miles upstream
from its confluence with the Yellowstone River.
   Existing project. The plan of improvement provides for the
                        FLOOD CONTROL-FORT PECK, MONT., DISTRICT                                                                                                   865
protection of areas subject to flooding in the city of Greybull, Wyo.
The project is designed to give flood protection to residences, busi-
ness establishments, industrial areas, public buildings, and facili-
ties of the Chicago, Burlington, & Quincy Railroad, and consists of
approximately 12,330 feet of levee along the left bank of the Big
Horn River. The levee will have a crest width of 10 feet, a land-
ward slope of 1 on 3.5, and riverward slope of 1 on 3, except for a
short distance at the south end where the riverward slope will be
1 on 2. A stoplog structure will be provided where the levee
crosses the railroad track at the upstream end of the project.
Three sections of the levee will be protected against erosion by 2
to 3 feet of dumped rock riprap. Existing levees, which presently
provide protection against minor floods, will be incorporated into
the proposed works wherever possible. The project was authorized
by the Flood Control Act approved May 17, 1950 (H. Doc. 216, 81st
Cong., 1st sess.). The estimated Federal cost (July 1954) is $743,-
000; the estimated local cost (July 1954) is $66,000 for utility mod-
ifications, lands, and damages.
   Local cooperation. In addition to the usual requirements for
local cooperation as provided by law, local interests are required
to raise highway grades, relocate a sewage pumphouse, and re-
move existing structures. Local interests have indicated their
willingness and ability to comply with all requirements.
   Operation and results during the fiscal year. No work was ac-
complished during the fiscal year.
   Condition at end of fiscal year. No work has been initiated.
                                                      Cost and financial summary
Other new work data: Appropriated for succeeding fiscal year ending June 30,
    1955                             ---                                                  ---                                                 _             $40,000

                           9. INACTIVE FLOOD CONTROL PROJECTS

                                                                                   For last               Cost to June 30, 1954                        Estimated
                                                                                 full report                                                             amount
                      Name of project                                                 see                                                               required
                                                                                   annual                 Con-                Operation                    to
                                                                                   report              struction                 and                    complete
                                                                                    for-                                     maintenance
             2s - - - - - - - -            - -- -- -      -- -- -- -             - - - - - - - - - - - - - - - - - - - - -- - - - - - - - -- -- - - - - -
Buffalo, Wyo. -....
                 - -- -- -- --       -           - - - - - - - - - - - - -- _-   -- -- -- -- -- -- -- - -- -- -- - - - -- -- -- -- -- -- -                  $66-- 000
                                                                                                                                                            $643,
Dayton, Wyo....                                                                                                                                               121, 000
Forsyth, Mont-........--.- _--
                           .----- _ "-- -                                 -          1950                   $255, 177 ..............--------------
                                                                                                                                     (1)
Glasgow, Mont                   .---------.----.--------------....1939                                         16, 832 ---------------                       (1)
Harlem, Mont.__-----------------............................
                      2- - - - - - - -       --------- ----                                           - - ---------------
                                                                     - - - - - - - - - - - - - -5,- -015
                                                               - - -1952                                    - -- -- -- -- -- -- -                               79, 985
Miles City, Mont.2- - - - - - - - - -      ------- - -- -- - - -- -- -- -- - - -- -- -- -- -- -- - - -- -- -- -- -- --                                  -   1, 290, 000
           3 -- - -...- - - - - - - -----
Monarch, Wyo.                          -- - - - - - - - - - -
                                                                                                                                                              240, 000
Saco, Mont. ........                             ..           ........               1938                           655 ..............                         96, 355

   SProject completed.
   2 Authorized by the 1950 Flood Control Act. No planning or construction funds have been allotted.
   = Authorized by the 1936 Flood Control Act.



                                         10. GENERAL INVESTIGATIONS
  Examinations and surveys-flood control studies. The cost in-
curred from flood control studies on the Milk River and on the Sun
River and Tributaries during the fiscal year was $11,155. The Milk
River study was completed during the fiscal year. The unexpended
balance of $54 plus an allotment of $15,000 for fiscal year 1955 will
866             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

be profitably expended for the continuation of flood control studies
on the Sun River and Tributaries during fiscal year 1955.
   Collection and study of basic data. The cost of collection and
study of basic data, which included work in connection with the
preparation and revision of the Flood Emergency Manual, Annual
Flood Report, and the collection of current flood information per-
taining to serious floods on streams for which formal reports have
not been specifically directed by Congress, was $3,980, during the
year.
                     11. INSPECTION OF COMPLETED PROJECTS
  The work included in this feature consists of periodic inspections
of local flood protection projects to ascertain whether projects are
properly operated and to point out essential maintenance and re-
pair work which should be accomplished.
   Total cost and expenditure incurred in connection with this work
during the fiscal year was $1,196, distributed as follows:
          Location                                                                                                                      Cost
     Glasgow, M ont.........                 ....                             ---- ---- ---- ---- ---- ---- -
                                                                             -----                                      -
                                                                                                                       ----        $ 196
     Shields Riv., Mont ..          --........... .                                                                                     400
     Three Forks, Mont ................                                           -.-.                                                  300
                              ------------.
     Forsyth, Mont _-----------....                                                                             -     -       .300
                                          Cost and financial summary

                                                     Fiscal year ending June 30                                        Total to June
                                                                                                                      30, 195 4, includ-
                                                                                                                      ing fis cal years
                                   1950             1951        1952             1953                  1954            prior to 1950


Maintenance:
   Appropriated                                     $1,200         $800                 $800                $1, 200               $4,000
   Cost.----------                        -          1,015             685          1,100                    1,196                 3,996

Other new work data:
   Unobligated balance, fiscal year ending June 30, 1954                                                                                 $4
   Appropriated for succeeding fiscal year ending June 30, 1955_ __       .                                                       1,500
   Unobligated balances available for succeeding fiscal year ending June 30,
      1955 ----   -     -      -      -    - -     --           -     -                                                          1,504


  12. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
   Snagging and clearing of navigable streams and tributaries in
the interests of flood control. (Section 13 of the 1946 Flood Con-
trol Act.)
   Work was performed during the fiscal year on the following
streams:
                                                                                                                                 Coast for
     Name and location                                                                                                        fiscal year
    Belt Creek, Montana-... --.....                                                                                           $37,006
    Highwood Creek, Montana ...                                                                                                24,099
    Shonkin Creek, Montana .....                                                                                                 8,467
    Teton River, Montana ..........                                                                                             11,534
       Total-.. . ..............              ...                                . --          --.   ----                 .    81,106


  The work was completed on all streams except Belt Creek which
will be completed during fiscal year 1955 with available funds.
               FLOOD CONTROL-FORT PECK, MONT., DISTRICT                                                      867
                               Cost and financial summary

                                         Fiscal year ending June 30                                Total to June
                                                 _              -30,                                 1954, includ-
                                                                                                   ing fiscal years
                        1950            1951         1952                1953         1954          prior to 1950

New work:
   Appropriated                    --   --                               $42,000      $84,601              $126,601
   Cost ...- --                                   - ----                  42,000       81,106               123,106


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_------------        $3,459
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955_                                                                    3,459

  Emergency bank protection.      (Section 14 of the 1946 Flood
Control Act.)
  Funds were allotted in June 1954 for emergency bank protection
on the Jefferson River in the Waterloo area near Whitehall, Mont.
No work was performed during the fiscal year. The work will be
completed during fiscal year 1955 with available funds.
                               Cost and financial summary

                                         Fiscal year ending June 30                                 Total to June
                                                                                                   30, 1954, includ-
                                                                                                   ing fiscal years
                        1950            1951         1952      i         1953          1954         prior to 1950

New work:
   Appropriated _       $51,727     -$21, 117                                   566   $50,000              $214, 371
   Cost_. -----          30, 608            2                                    6    --- ____ -            164, 371


Other new work data: Unobligated balance, fiscal year ending June 30, 1954__ $50,000

  Small flood control projects not specifically authorized by Con-
gress. (Section 212 of the 1950 Flood Control Act.)
  Reconnaissance reports were prepared for flood control projects
at Belt, Choteau, and Plentywood, Mont. A design report was
completed for West Glendive, Mont., and design memoranda for
Belt, Mont., were initiated and will be completed with available
funds during fiscal year 1955. The total cost during the fiscal
year was $16,168.
                               Cost and financial summary

                                         Fiscal year ending June 30                                 Total to June
                                                                                                   30, 1954, includ-
                                                                                                   ing fiscal years
                        1950            1951         1952                1953          1954          prior to 1950

New work:
   Appropriated.        $46,700     -$20,953      - _
                                                    --------   -......                 $18,650              $44, 397
   Cost _--               4,540          21,207                                         16,168               41,915


Other new work data: Unobligated balance, fiscal year ending June 30, 1954__ $2,482

  Flood control emergencies--Repair and flood fighting and res-
cue work. (Section 210 of the 1950 Flood Control Act and supple-
mental authorizations.)
868            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  Work was performed during the fiscal year at the following
costs:
                                                                      --....
      Flood fighting and rescue work ----------..--...--......---....--.....        ----------........ $47, 573
      Levee repairs, Shields River, Mont----------................................---------------       18,041
        Total..............................................             ....------------------------------55, 614

                                       Cost and financial summary

                                                Fiscal year ending June 30                       Total to June
                                                                                                30, 1954, includ-
                                                                 S     19         11954             fiscal
                                                                                                ingrior to years
                                                                                                           1950
                                1950         1951         1952       1 1953         1954




1 Exclusive of contributed funds in the amount of $5,990.
                                                       OHIO RIVER

   For the actual construction of locks and dams, and the opera-
tion and care of the completed structures, the river is divided into
3 sections under the immediate supervision and direction of dis-
trict engineers at Pittsburgh, Huntington, and Louisville.
   The Pittsburgh section extends from the head of the river at
Pittsburgh, Pa., to a point between Captina Island and Powhatan
Point, a distance of 109 miles, and includes Emsworth, Dashields,
and Montgomery locks and dams and locks and dams 7 to 13, in-
clusive; the Huntington section extends from mile 109 to mile
409.3, immediately downstream from Aberdeen, Ohio, a distance
of 300.3 miles, and includes locks and dams 14 to 23, inclusive,
Gallipolis locks and dam, and locks and dams 27 to 33, inclusive;
the Louisville section extends from mile 409.3, immediately down-
stream from Aberdeen, Ohio to the mouth of the river, a distance
of 571.7 miles, and includes locks and dams 34 to 39, inclusive, locks
and dam 41 (with the Louisville and Portland Canal) and locks
and dams 43 to 53, inclusive.
                                                        IMPROVEMENTS

                                                             Navigation
                                                                                                                                     Page
1. Construction of locks and dams on the Ohio River------------------...................................---..........                869
2. Open channel work, Ohio River...............................-------------------------------.......................... .........   875
  Note. Tributary navigation projects and all flood control projects in the Ohio
River Basin are contained in the reports of the districts included in the Ohio River
Division.

   1. CONSTRUCTION OF LOCKS AND DAMS ON THE OHIO RIVER
   Location. The Ohio River is formed by the junction of the
Allegheny and Monongahela Rivers at Pittsburgh, Pa., and flows
in a general southwesterly direction for a distance of 981 miles to
join the Mississippi River near Cairo, Ill. For description of the
river see page 1227, Annual Report for 1932.
   Previous projects. The first lock and dam on the Ohio River
was provided for by River and Harbor Act of March 3, 1879. The
construction of dams was provided for by River and Harbor Acts,
as follows: Dam 6, September 19, 1890; dams 2, 3, 4, and 5, June
3, 1896; 13 and 18, March 3, 1899; 8, 11, 19, and 37, June 13, 1902;
26, March 2, 1907. For further details see page 1907 of Annual
Report for 1915. For expenditures on the previous 6-foot canaliza-
tion see paragraph "Condition at end of fiscal year" of this report.
   Existing project. This provides for the improvement of the
entire river by the construction of locks and dams to provide a
channel depth of 9 feet and for the widening of the Louisville and
Portland Canal at Louisville, Ky. The project provides for a lock
with usable dimensions of 110 by 600 feet at each dam and in addi-
tion an auxiliary lock 56 by 360 feet at Emsworth, Dashields,
Montgomery, and dam 41 and 110 by 360 feet at Gallipolis. Dash-
ields is a fixed dam, while Emsworth, Montgomery, and Gallipolis
                                                                                                                         869
870               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

are fixed dams with movable crests. The remainder of the 46 dams
are of the movable type, with navigable pass varying in width
from 600 to 1,248 feet. In addition to the navigable pass, the mov-
able type dams are also provided with one or more regulating
weirs. At dam 41 a canal (Louisville and Portland) extends along
the left bank for a distance of 2 miles, with the locks at the lower
end.
   Operation and care of the locks and dams were included in the
project July 1, 1935, under the provisions of the Permanent Ap-
propriations Repeal Act approved June 26, 1934.
   The estimate of cost of new work (existing project) (1954) ex-
clusive of Gallipolis locks and dam reported under the Kanawha
River project, is $529,681,400. The foregoing estimate does not
include expenditures on previous projects.
   The estimate of annual cost of operation and maintenance of
locks and dams. (1954) is $7,150,000.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                         Work authorized                                   Documents
June 25, 1910     Construction of 54 locks with movable dams, widen-       H. Doc. 492, 60th Cong., 1st sess.
                   ing of the Louisville and Portland Canal to 170 feet,
                   and a new lock at the lower end. The act also
                   granted discretionary authority to the Secretary of
                   War to make such modifications in the project as
                   appeared advisable.
July    18,1918   Elimination of locks and dams in the lower river         H. Doc. 1695, 64th Cong., 2d sess.
                   where the project depth of 9 feet could be satis-
                   factorily maintained by open channel work. Secre-
                   tary of War authorized to substitute fixed dams
                   for movable dams wherever, in his opinion, they
                   may be advisable.


   Under the authority granted in the River and Harbor Act of
June 25, 1910, the Louisville and Portland Canal has been widened
to 200 feet; locks and dams 40 and 42 have been eliminated; locks
and dams 1 and 2 replaced by the Emsworth locks and dam; lock
and dam 3 replaced by the Dashields locks and dam; and locks and
dams 4, 5, and 6 replaced by the Montgomery locks and dam. Locks
and dams 24, 25, and 26 were replaced by Gallipolis locks and dam
which was authorized by the act of August 30, 1935, and con-
structed under the project for improving lower Kanawha River.
   Table A contains data relative to the various features of the
locks and dams included in the existing project. Table B lists the
principal towns and cities along the Ohio River with their mileage
below Pittsburgh, Pa.
                                                                                                                                           Table A

                                                                                                                                            Lock
                                                Location
                                                                                                         Dimensions                           Depth on
                                                                                                                                              miter sills                                                                                                  Per-   Year                   Actual
TLcklr I,^"'j                                                                                                                          I                                                                                                                   cent- opened                   cost to
and                                                                                                                                                                                                                                                         age     to                   date of
dam                                                                                                       Greatest                                                             Character of                       Character of                             com-   navi-                 each lock
            Miles                                                                        Width             length                                                              foundation                        dam foundation                           pleted gation                 and dam
            below                   Distance from nearest town or                          of               avail-   Lift                  Upper          Lower
            Pitts-                  mouth of navigable tributary                         cham-               able   (feet)                 (feet)         (feet)
            burgh                                                                         ber              for full
                                                                                         (feet)             width
                                                                                                            (feet)
                                                                                                                    -I                                f                                                                                               i
   1                         Replaced---...............-----------------                                                                                                                  ....    ..       ..- - -              - ... -   -   -   -       ..-. -   ..-- -   -   -   -     $870,0 34
                  6.2        Emsworth locks and dam, Emsworth,                                 110            60               18.0         117. 0          12. 9        Rock....            ____            Rock and piles---                  ....            100          1921      2 5,861, 765
                               Pa.                                                              56
   2                         Replaced-----.......-------.-----------                                                                                                                                 -.......-...... --... --.-..--..............                                           976, 767
   3                            do---       .---------------------
                                               -....                                                          360                                                                                             .. . . . . . . .. .. . .. .. . . . . . . . . . . . . . . . . . . .- 1, 144 , 5 88
                13.3         Dashields locks and dam, 1.6 miles be- J                          110            600          I0.                                                                                                                                                                         0
                              low Sewickley, Pa.                         1                      56            360                           113. 4        3 17.5         Rock___                   -         Rock.---------------                              100           1929       43, 528,955
   4                         Re   a l d
                             nevict~~~,,-,u,,-------------------------                   ---                                                                                                    .......----....-..
                                                                                                                                                                                           ......--                                                        ..............                1, 071, 472
   5                         .... do                     .    -. ....
                                                    -............            --       .........                                                                                                        -.......--....-...........--------                       ............             1,080,132     O
                               .. do..... .._.. ..
   6                          --  do-     - - - - --- - --.- --            -..-. . ..
                                                                         ...
                                                                                           -   -    -                                                                                                                                                                                    1,123, 442
                31. 7        Montgomery locks and dam, 1.4 miles 1                  110                       600              19.4         1 16.0        312.7          Rock andd piles ...-                 Rock and piles......                              100          1936      s 5, 737, 611
                                above Industry, Pa.                                   56                      360                                                                                                                                                                                      t-'
   7             36. 5       Midland, Pa-----........------...---------------..:    110                       100               6.9           15. 4        11.0          Rock -                                            ___..._-..._                         100          1914        1, 075, 000   -Piles_
                                                                                                                                                                                                                                                                                                       d


   8             46. 4       1.7 miles below Newell, W. Va......----------. 110                               600               6.4           15. 4        12.0          Piles in gravel         ------       Rock; piles in gravel                             100          1911        1, 167, 456
                 54. 4       New Cumberland     6   locks and dam, Strat- f 110                              1200              22.6           19.2          12. 7        Rock-__                              Rock...........------------------------------                                 242, 847
                                tonville, Ohio                                   . 110                        600
   9             56. 1       New Cumberland, W. Va ..........---                    110                       600               7.4           15.4          11.0        .....do_..                           Piles in gravel....-------                         100          1914        1, 177, 100
  10             66. 2       1.8 miles above Steubenville, Ohio-.----               110                       600               8.4           16. 4         11. 0        Rock an d piles in                            do .                  . ...--------------00           1915        1, 138, 000
                                                                                                                                                                           gravel.
  11             76.9        2.5 miles below Wellsburg, W. Va                                      110        600                7.3          15.4          11.1         Piles in sand and                    Piles in sand and                                 100          1911        1,162,165
                                                                                                                                                                           gravel.                                gravel.
  12             87.4                        -
                             Warwood, W. Va -__                 -       --                         110        600                8.4          15. 4         11.0        .....do..__.....                               do....--------------100                               1916        1, 166, 104
  13             96. 1       McMechen, W. Va_-                                    -                110        600                7.3          13.8           9.5         ....do... S......              .Rock;              piles in sand                       100          1911        1, 222, 389
                                                                                                                                                                                                                  and gravel.
  14            114. 0       Woodland, W. Va ..__.         .      _     _                      110            600                8.3          16.4          11.0         Rock.... .-..--                      Rock .----------..                                100          1917        1,133, 371
  15            129. 1       New Martinsville, W Va              __                            110            600                7.8          15.4          11.0                                           ....       do...--------------100                                 1916        1,180,478
                                                                                                                                                                        .....do. ....                                                                                                    1, 275, 532
  16            146. 5       Ben Run, W. Va.............---------------------                  110            600                7.8          15. 4         11.2                                           .... do .--------------                              100          1917
  17            167. 5       4.5 miles above Marietta, Ohio....----------                      110            600                8.2          15.4          11.0             do._ ------------- do..............--------------100                                            1918 ----- 1, 362, 591
  18            179. 9       4.7 miles above Parkersburg, W. Va ....                           110            600                6.2          14.2          11.0          ._do__. .                    .__         .do.....-...-.....                           100          1910           927, 091
  19            192. 2       Little Hocking, Ohio....------------------                        110            600                7.7          16.9          11.0         Piles in sand, gravel ..... do..............                                           100          1916        1, 213, 848
                                                                                                                                                                           and roc ck.
  20            202. 5        Belleville, W. Va---------------------           110          600                                7.5            15.4         11. 0         Rock,__. ...........                      .do-------------                             100          1917           936, 696
  21                                                                                        600                                                                                                                                                                 100          1919        1, 484, 562
  22
                214. 6        1.4 miles above Portland, Ohio...----------      110                                             5.6            15.4         11.0         .....do...............-..... S.....do.............--------------.
                                                                                                                                                                                                                      do--------------..............
                                                                                                                                                                                                                                                                100          1918        1, 218, 798
                220. 9        Ravenswood, W. Va....------------------          110                            600              7.8            15.4         11.2         .....do.._
                                                                                                                                                                             do... ----------............---.....do-------------...............100
  23            231.4                                                                                                                                      13.5         .....                                                                                                1921        1, 851, 488
                              Millwood, W. Va...---------------------110                    600                                5.6            16.4
                              Replaced             ..... . ,.............
                                                              -           ......                                                                                                                                                                                -..               .      1, 187, 542
  24                         .....do---------------------- ----------- ---                                                                                                                                     .... ....... ....... ...... ....           ... ... . ... ..- 1,925,205
  25                     .   --    d o .. ... ... .. ... ... ... .. ... ... ... .. .........-                            ...          ' .. . .
                                                                                                                                    . ---..           .                             .        .         ..                                                             ..        .        1,307,241
        I                          --   --
                                        -   -   _                                                                                                                   i
        279. 2   Gallipolis locks and dam, 0.7 mile below [              110      600
                                                                                        26.0     18.0       12. 0        Rock--___......_____           Rock.............-          100      1937         (7)          O
                 PfHogsett,  W. Va.                                      110      360
  27    301.0    3.6 miles above Procterville, Ohio_.._.                 110      600    6.4     15. 4      11. 1 .....do-............... ..... do ............... 100  1923                            2, 015, 601    1>
  28    311.6    3.3 miles below Huntington, W. Va__..                   110      600    7.1     15. 4      11.0  .....do-....................                     100  1915
                                                                                                                                               do-----.......-----........                              1, 063, 133
  29    319.9    2.7 miles above Ashland, Ky..._ _.... .                 110      600    8.0     15. 4      11.0  .....do............... .....                     100
                                                                                                                                                do------............... 1916                            1,088, 802
  30    339.4    3.3 miles below Greenup, Ky-...... ___                  110      600    7. 5    15. 4      11.0  .....-
                                                                                                                       do............... .....                     100
                                                                                                                                                do----...............   1923                            1, 579, 618
  31    359.3    3.3 miles below Portsmouth, Ohio.. __..                 110      600    7. 5    15. 4      11.0  .....do...............  ..... do.'.............  100  1919                            1, 359, 231
  32    382. 6   1 mile above Rome, Adams County,                        110      600    7.5     15.4       11.0   Piles in sand and       Caissons on sand        100  1926                            2, 951, 216
                   Ohio.                                                                                             gravel.                 and gravel.
  33    405. 1   3.5 miles above Maysville, Ky_ __.__                    110      600    7.0     15.4       11.0 ....do.....---.......-    Piles in sand and       100  1921                             1, 937,166
                                                                                                                                             gravel.
  34    434. 1   Chilo, Ohio _. _......._ _ _     .... ..                110      600    5.6     15. 4      11.0 ..... do--------............do...............     100  1925                            3, 437, 057
  35    451.0    1 mile below New Richmond, Ohio._.__                    110      600    6.4     15. 4      11.0 ..--...
                                                                                                                   __. do ...............
                                                                                                                       do--.............. .'.._do............... 100    1919                            1, 894, 942        .
  36    460. 9   9.3 miles above Cincinnati, Ohio__-__                   110      600    7.9     15. 4      11. 1                         ..... do..............   100  1925                            3, 704, 535
  37    483.2    Fernbank, Ohio_.........       .________                110      600    7.8     12. 3      11.0   Rock............... Rock................        100  1911                            1,297, 924     O
  38    503. 3   Maxville, Ky-.......-...............                    110      600    7.3     15. 4      11.0   Piles in sand and Piles in sand and             100  1924                            2, 857, 040
                                                                                                                     gravel.                 gravel.
  39    531. 7   1 mile above Markland, Ind ____
                                             ........                    110      600    6.0     15. 4      13. 0 .....-
                                                                                                                       d o-..............d Rock and piles in       100  1921                            2,222,448
                                                                                                                                             sand and gravel.
   40          Eliminated            ____              ________
                                                                                  600
   41   604. 4 Louisville, Ky __               __________                         360   37.0     19. 0      11.0                                        Rock....-----------         100      1921      S7, 658,134
   42          Eliminated        _         _                                                                                           ----------------------
                                                                                                                        ----------------------------
                                                                         110                                              Rock..............
   43   633. 2 3.3 miles below West Point, Ky ........                            600     9. 0   15.4        11.0                                         Pile ................              1921            242
                                                                                                                                                                                                        2,592,
   44   663. 2 Leavenworth, Ind.....____                                 110              7.0    15. 4       13. 0                                        Rock and pile-.......      100     1925       2, 818, 763
                                                                                                                                       ----------------------
                                                                                                             13. 0 ----------------------------
                                                                         110      600
   45   703. 0 Addison, Ky           -------------                                600     9.0    17. 4               Rock--
                                                                                                                     Pile...............                 .....
                                                                                                                                               ....---------- do ..............100           1927       3, 202,587
   46   757. 3 Owensboro, Ky ... ...              . _                    110             11.0    17. 4       11.0                                         Pile ..............   __   100
                                                                                                                                                                                     10.     1928       3, 127, 981
                                                                         110      600                                                                                                100
   47   777. 7 Newburg, Ind----------.................                            600
                                                                                          9.0    15.4        11.0                                        .....do..............               1928       4, 415, 526        i
   48   809. 6 5.8 miles below Henderson, Ky .........                   110              7.0    15.4        13. 0 Pile--do                  -----        .....do...............     100     1922       3, 062, 700
                                                                         110      600                                                                     Rock....._ _ __...
   49   845. 0 2.4 miles below Uniontown, Ky --..          -
                                                                                  600
                                                                                         11.0    17. 4       13. 0                                                                   100     1928       3, 325, 297
   50   876. 8 1 mile below Weston, Ky_                                  110             10. 0   17. 4       11.0                                         Rock and pile-.......      100     1928       3, 751, 614
                                                                                                                                                                                     100                               M
                                                                         110...
                                                                         110      600                                    -______-------------

   51   903.1 0.6 miles below Golconda, Ill ...........                                   8.0    15. 4       11.0                                         Pile...............                1929       4, 370, 566    +
   52
   53
        938. 9 1.4 miles below Brookport, Ill
        962.6 10.8 miles above Mound City, Ill
                                                         -.--..---       110
                                                                         110
                                                                                  600
                                                                                  600    12.0
                                                                                         13. 4
                                                                                                 15. 4
                                                                                                 15. 4
                                                                                                             11.0 ... do-..-..
                                                                                                            99.6
                                                                                                                         Pile-     --    ..----
                                                                                                                                        ,------------    ..... do...............
                                                                                                                                                                                     100
                                                                                                                                                                                     100     1928
                                                                                                                                                                                             1929
                                                                                                                                                                                                        4, 461, 462
                                                                                                                                                                                                        5, 410, 668
                                                                                                                                                                                                                       Go
                                                                                  600                                Rock...----------- .....
                                                                                                                         ---   _do-_------------               do................. . . . .
   54   974. 2   Mound City, Ill___                 --     -   -         110      600   (10)     (1o)       ('0)         Rock---------------              Gravel..............                            (10)


                      Total   ...   .   -........                                                                                                                                                   11 122, 356, 523   Go
                                                                     i                                              i




   1 Depths as shown are on emergency-dam foundation and are controlling depths.                        9 Dam below was not commenced. Depth on lower miter sill at low water.
   2 Change from fixed dam to lift-gate dam completed in 1938. Replaces movable dams                    10oNecessity for construction has not yet been determined.
1 and 2.                                                                                                11Exclusive of $7,054,731; details below:
   a Depths as shown are on poiree dam foundation and are controlling depths.                                               Additiona features entering into cost of project
   ' Fixed Dam. Replaces movable dam 3.                                                                   Louisville and Portland Canal and Indiana chute (under previous                                              mC



   5 Lift-gate dam. Replaces movable dams 4, 5, and 6.                                                     project) __---------------------------------                   ---------                      5, 359, 203   P




   6 Will replace locks and dams 7, 8, and 9.                                                                                                                                 --
                                                                                                          Examinations, surveys, contingencies, plant and miscellaneous.,--.......                         966, 232
   7 Roller-gate dam. Replaces movable dams 24, 25, and 26. Cost not included in total,                   Planning of Greenup locks and dam---...............................
                                                                                                                                                                         .    379, 622
as it was constructed under project for improving lower Kanawha River.                                    Planning of Markland (formerly Fernbank) locks and dam.............                              349.674
   Completed with large new lock in 1921. Completed with new dam and raised canal
and lock walls in 1928. Construction of an auxiliary lock commenced in 1929, which lock                                                                                                                  7,054,731
was completed in 1930.                                                                                                                                                                                129,411,254
                                                                                                                   Total----------------------------------------------
                                                      OHIO RIVER                                                                  873
                                                              Table B

                                Miles                                              Miles                                        Miles
          Location              below                  Location                    below                   Location             below
                                Pitts-                                             Pitts-                                       Pitts-
                                burgh                                              burgh                                        burgh

Pittsburgh, Pa____....__          ..
                              ________    Portsmouth, Ohio..._                .356.0         Rockport, Ind...-----------.      742. 2
Ambridge, Pa-----------... .     15.9     Maysville, Ky.....-----              - 408.6       Owensboro, Ky--------.........    756.5
Aliquippa, Pa-----------...      20.0     Newport, Ky.....----                 - 469.8       Newburgh, Ind..----------         778. 0
East Liverpool, Ohio---....      43.5     Cincinnati, Ohio....----. 470. 2                   Evansville, Ind---------..     .  792. 3
Steubenville, Ohio-....          68.0     Covington, Ky.......----------          470.5      Henderson, Ky.---------- 803.9
Wheeling, W. Va__   -----        90.5     Lawrenceburg, Ind.......                492.9      Mt. Vernon, Ind---------. 829.1
Bellaire, Ohio-----------94. 5            Aurora, Ind----------..............     496. 7     Uniontown, Ky----------           842. 5
Marietta, Ohio....----------    172.0     Carrollton, Ky--........... 545.7                  Shawneetown, Ill----..-           857. 8
Parkersburg, W. Va.-....        184.6     Madison, Ind____-..........             557. 7                           -902.
                                                                                             Golconda, Ill__.........               5
Point Pleasant, W. Va.._        265. 2    Jeffersonville, Ind..                   602. 7     Paducah, Ky------------           934. 5
Gallipolis, Ohio-__----..       269. 7    Louisville, Ky----------...........     603. 7     Metropolis, Ill.----------        943. 8
Huntington, W. Va-......        308.3     New Albany, Ind-.......                 608.5      Joppa, Ill..---------------951.4
Catlettsburg, Ky-....        . 317. 2     Leavenworth, Ind- _                     664.0      Mound City, Ill---------......... 973. 4
Ashland, Ky--         -____-    322. 6    Cannelton, Ind---..-------...           724. 0                -------------
                                                                                             Cairo, Ill...                     979. 3
Ironton, Ohio...-----------327.2          Tell City, Ind_ ........                727. 0



   Terminal facilities. Modern public terminals, with warehouses,
equipped with operating machinery for transferring materials
have been constructed by private interests at some of the larger
cities and towns.
   The latest published list of terminals on the Ohio River appears
in Transportation Series No. 2, 1929. The list is brought up to date
each year as of June 30 and can be obtained from the division en-
gineer, Ohio River Division, Cincinnati, Ohio.
   Operations and results during fiscal year. New work: All new
work was done by hired labor. The costs were as follows:
New Cumberland locks and dam: Preparation of detailed construction plans
  for locks and appurtenances....----------------------------------$26, 203
Greenup locks and dam: Completion of general design memorandum; initi-
  ation and completion of memorandum on analysis of design of lock walls;
  continuation of flowage studies and design of locks; continuation of model
  studies of the filling and emptying system for the locks                                       ......---    ..... 102,303
Markland locks and dam: Continuation of general design memorandum
  studies, planning for preparation of plans and specifications and continu-
  ation of model studies-----........................................-------------------------------...    .......   67, 522

          Total for new work............................-------------------------------------                               196, 028

  Operation and maintenance, general: The locks and dams were
operated as required, and necessary repairs and improvements
were made thereto, and to the operators' quarters, grounds and
esplanades to the extent of funds available. The costs by districts
were as follows:

                        Class of work                                       Pittsburgh      Hunting-         Louisville       Total
                                                                                                ton-

Operation and ordinary maintenance--...               --........----          $966, 018     $1, 658, 064     $1, 685, 052   $4, 309, 134
Rehabilitation---__. ------------------------                                  753, 475         375, 953      1, 423, 895    2, 553, 323
      Total._____ _ _ _-__.._- . ......
                                  -_              .     -       -........    1, 719, 493     2,034, 017       3, 108, 947    6, 862, 457
874                  REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

     Summary of costs during the fiscal year is as follows:

                                                                                                       Costs
                                    Funds
                                                                                                            Operation and main-
                                                                                           New work          tenance, general

Regular.................................------------------------------------------------              028   $196,      $6, 862, 457



   Condition at end of fiscal year. The navigation system of 46
locks and dams is in operation and 9-foot navigation throughout
the entire length of the river is generally available at all times.
At certain unstable bars the project depth is maintained by dredg-
ing, supplemented by contraction works.           (See project "Open
Channel Work, Ohio River", p. 875.) Table A under "Existing
project" shows cost and year of completion of locks and dams now
in operation. The following originally contemplated work remains
to be completed: Raising crest of dam 14; construction of bear-
traps at dam 21 and construction of additional beartraps at dams
18, 22, 23, 27, 30, 39, and 43. In addition to completion of the above
work, the following betterments are proposed to certain existing
structures in order to provide adequate facilities for present day
navigation: Construction of guard wall and guide wall extensions
at locks and dams 35, 41, 44, 45, 46, 48, 49, 50, 51, and 52. Also,
part of the works of the existing project do not provide adequate
facilities for present day navigation due to obsolescence of the
structures. Since repair and modernization of these facilities
would be extremely costly, replacement and reconstruction must
be undertaken as soon as funds can be made available for the pur-
pose. Funds have been made available for initiation of construc-
tion in fiscal year 1955 of the New Cumberland locks and dam
 (Strattonville, Ohio) to replace locks and dams 7, 8, and 9. Other
replacement and reconstruction facilities proposed are: Construc-
tion of Pike Island locks and dam to replace locks and dams 10 and
11; construction of locks and dam in the vicinity of Greenup, Ky.,
to replace locks and dams 27, 28, 29, and 30; construction of locks
and dam in the vicinity of New Richmond, Ohio, to replace locks
and dams 31, 32, 33, and 34; construction of locks and dam in the
vicinity of Markland, Ind., to replace locks and dams 35, 36, 37, 38,
and 39; the reconstruction of lock and dam 41; and construction
of Wabash Island locks and dam to replace locks and dams 48
and 49
                                                           OHIO RIVER                                                            875

      The costs to the end of the fiscal year for the existing project
were as follows:

                                                                                                            Costs
                                       Funds
                                                                                        New work         Operation
                                                                                                        and mainten-
                                                                                                        ance, general        Total

Regular......------------------------------------------$107, 950, 288                       $82, 527, 612 $190, 477, 900
Public works---.... --------------------------------------                    3, 258, 368 .............. 3, 258; 368
Emergency relief-......1-----------                        ------------ ---   1,198, 837          19, 000    1, 217, 837
Maintenance and operation- ..---------------------------                  -------------- 2, 081, 900         2,081, 900
        Total...............................-----------------------------------------   112, 407, 493    1 84,628, 512     197, 036, 005

  1 In addition, surplus property valued at $98,459 was transferred to the project without reimbursement

   The cost of the previous 6-foot canalization project was $17,003,-
761, which was the expenditures to June 30, 1910. The total cost
to date of new work, including the cost of old structures which have
been replaced, is $129,411,254.
   In addition, the sum of $36,943,217 was expended between Oc-
tober 7, 1885, and June 30, 1937, on the operation and care of the
works of improvement under the provisions of the permanent in-
definite appropriation for such purposes.
                                                Cost and       financial summary
                                                              Fiscal year ending June 30                               Total to June
                                                                                                                      30, 1954, includ-
                                                                                                                      ing fiscal years
                                         1950             1951              1952           1953           1954          prior to 19501


New work:
   Appropriated ------         -- $178, 700              $140, 000        $249, 881      $239, 291       $180, 000       $129,433,  402
   Cost--------------...-        -175, 184                 55, 408         139,962        465, 614        196,028         129, 411, 254
Maintenance:
   Appropriated -------6, 456, 330                     6, 645, 910       6, 617, 564    6,827,328       7, 265, 000       122, 563, 679
   Cost....                      6, 487, 288
                    ...--------------                  6, 366, 866       6, 681, 704    6, 903, 725     6,862,457        2121, 571, 729

1   Includes $17,003,761 for new work and $920,945 for maintenance for previous projects.
2In!addition,   surplus property valued at $98,459 was transferred to the project without reimbursement.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-_-----    -       $12,967
    Appropriated for succeeding fiscal year ending June 30, 1955_.--- .1,090,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955        -----------------------------------             -   1,102,967

                           2. OPEN CHANNEL WORK, OHIO RIVER
  Open channel work on the Ohio River is in charge of the district
engineer in whose district the work is located.
  For information as to the limits of the three districts on the
876       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Ohio River, see page 869. The portion of the river included in
the project extends from the head of the river at Pittsburgh, Pa.,
to the mouth of the Cache River (Mound City, Ill.), a distance of
974.7 miles. Open channel improvement from the mouth of the
Cache River to the mouth of the Ohio River is under the jurisdic-
tion of the Mississippi River Commission.
   Existing project. Prior to the completion of the canalization
project, no project depth had been fixed by Congress under the
project for open channel work, but in order to properly aid packet
and barge navigation it was found necessary to secure a low water
channel having a minimum depth of from 4 to 6 feet, and a width,
depending upon the difficulty of running the channel, of from 400
to 600 feet; also to permit the movement of large coal tows, which
movement occurred at stages of water exceeding 10 feet, it was
found necessary to remove the points of projecting bars which
formed at various locations along the river. The accomplishment
of this purpose involved the concentration of current by closing
back channels at islands with low dams, the contraction and
straightening of wide, open channels by low dikes, dredging of
bars and shoals, and the removal of snags and wrecks.
   Since the completion of the canalization project, the work under
the project for open channel work provides mainly for widening,
deepening, and maintenance of the channel in the pools of the dams,
and in the open river section of the river below lock and dam 53
so as to provide and maintain the full project depth of 9 feet con-
templated by the canalization project. Channel widths generally
are in excess of 500 feet, except at critical bars where there is peri-
odic recurrent shoaling. Channels 300 feet in width are main-
tained at critical bars by periodic dredging. Such channels may
become constricted to a width of 250 feet before dredging can be
accomplished. These channel widths are the minimum that will
facilitate the movement of the present day barge tows. The ac-
complishment of this work not only involves dredging of bars and
shoals, but the construction and maintenance of back channel dams,
dikes and bank revetments for stabilizing the channel, and the re-
moval of snags and wrecks.
   Incidental to the direct improvement of the Ohio River is the
construction and maintenance of ice piers as required for the pro-
tection of river craft.
   The stage of extreme high water on the Ohio River varies from
46 feet at Pittsburgh, Pa., to 80 feet at Cincinnati, Ohio, with 57.2
feet at Louisville, Ky. (head of falls), 53.8 feet at Evansville, Ind.,
and 59.5 feet at Cairo, Ill. (mouth of river).
   The estimated cost of new work (1954) is $22,718,000, which is
exclusive of the additional ice piers authorized by the River and
Harbor Act of January 21, 1927, and the reforestation of sloughs
                                               OHIO RIVER                                                  877
on Kentucky Peninsula near Evansville, Ind., authorized by the
River and Harbor Act of July 3, 1930. The estimate of annual cost
of operation and maintenance (1954) is $1,114,000.
  The existing project was authorized by the following River and
Harbor Acts:

       Acts                          Work authorized                                    Documents
Mar. 3,1827       The project adopted by this act originally covered the
                   entire length of the Ohio River from its mouth near
                   Cairo to Pittsburgh, a distance of 981 miles. It pro-
                   vided for the removal of all obstructions which tend
                    to endanger steamboat navigation.
Jan. 21,1927      Construction of ice piers as a part of the project, with   H. Doc. 187, 67th Cong., 2d sess.
                   funds allotted from the appropriations for general
                   open-channel work.
July    3, 1930   Reforestation of the sloughs on Kentucky Peninsula         H. Doc. 409, 69th Cong., 1st sess.
                   near Evansville, Ind., and a 200-foot strip along the
                   upstream bank and for bank protection at an
                   estimated cost of $200,000.


   Operation of snag boats on the Ohio River below the Pennsyl-
vania State line was included in the project July 1, 1935, under the
provisions of the Permanent Appropriations Repeal Act approved
June 26, 1934.
   Local cooperation. The River and Harbor Act approved Janu-
ary 21, 1927, authorizing the construction of ice piers for general
open-channel work, imposes the condition that before work is begun
on any ice pier, local interests convey to the United States free of
cost such riparian rights as may be deemed necessary in connection
with the improvement at the locality (H. Doc. 187, 67th Cong., 2d
sess.). Existing ice piers are adequate for present purposes and
local cooperation is not needed since no additional construction is
under consideration.
   The River and Harbor Act approved July 3, 1930, authorizing
the reforestation of the sloughs on Kentucky Peninsula near Evans-
ville, Ind., and a 200-foot strip along the upstream bank and for
bank protection, provides that no expense shall be incurred by the
United States for acquiring of any lands required for the purpose
of this improvement (H. Doc. 409, 69th Cong., 1st sess.). However,
since no serious overbank erosion has occurred since the bank revet-
ment in 1933-34, reforestation is not considered justifiable at this
time and no local cooperation is required.
   Terminal facilities. See page 873.
   Operations and results during fiscal year. Dredging, where
required to provide an adequate and dependable channel of project
depth at minimum pool conditions, was executed. The dikes and
revetments were maintained and the routine work of maintaining
navigation aids, removing snags, making channel studies and
hydrographic surveys was performed as required. The specific
work accomplished during the year was as follows:
878             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  Operation and maintenance, general: The following dredging
and other maintenance work was performed:
Operation and ordinary maintenance:
    Channel sweeping and fathometer soundings; hydrographic surveys;
       channel inspections and aids to navigation; miscellaneous inspec-
      tions and reports---------...........................................----    $218, 280
Rehabilitation:
    Dredging (hired labor):                                       Cu. yards  Cost
         Pittsburgh District.............  ...----------------     30,490 $33,099
         Louisville District--.. ..---....     -       --..    1, 269, 749 205,087
                                                                                                             238, 186
     Snagging and clearing .............-
                                  ..............
                                           .. ........
                                                     .....
                                                       .                                                     313
                                                                                                   --...............--

        Total          ......          ...                                                                   456, 779

   The total cost during the fiscal year on the entire river, all for
operation and maintenance, general, was $456,779.
   Condition at. end of fiscal year. The work under this project
is about 71 percent complete. In addition to dredging, local stabili-
zation of channel has been effected at various points by construc-
tion of dikes and revetment. The work which remains to be done
consists of dredging to widen the channel at various points to the
project depth and placing of revetment at various points to further
stabilize the channel and protect the banks against erosion.
   The total.costs of the existing project to the end of the fiscal year
were as follows:

                           Class of work                            Regular          Public works             Total
                                                                     funds              funds

New work_                                                          $14, 922, 024         $1, 040, 236       $15, 962, 2 i0
Operation and maintenance, general                          __     1 31, 833, 204                  -
                                                                                                   -         31, 833, 204
      Total .
      Total_______________________________________________          46, 755,
                                                                    46,      228
                                                                        755, 228    i 1,040,236
                                                                                         1, 040, 236         47, 795, 464
                                                                                                             47795,464

  1 This amount includes $1,000 for removal of obstructions in Licking River under authority of section 3 of
the River and Harbor Act approved July 3, 1930.


  In addition, the sum of $1,621,349 was expended between Sep-
tember 19, 1890, and June 30, 1936, in the operation of snag boats
under the provision of the permanent indefinite appropriation for
such purposes.
                                           Cost and financialsummary

                                                 Fiscal year ending June 30                              Total to June
                                                                                                         10, 1954, includ-
                                                                                                        ing fiscal years
                                   1950         1951        1952          1953            1954            priorto 1950

New work:
    Appropriated_ --.---          $250,000     $130,000    $175,000     -$3, 600    -$1, 565                 $15,962,260
    Cost________                   320,763      159,565     214,335         1,753 -..........                 15,962,260
Maintenance:
    Appropriated ..                753,100      905,710   1, 154,818 1,100, 500           484,615             33, 549,608
    Cost..--------------           789,917      945,710   1,076,236 1,061,900            1476, 587            33, 454, 553

  1 Includes $19,808 undistributed costs 30 June 1953.
    IMPROVEMENT OF RIVERS AND HARBORS IN THE
            NASHVILLE, TENN., DISTRICT

  This district comprises portions of southern Kentucky, south-
western Virginia, western North Carolina, northern Georgia and
Alabama, northeastern Mississippi and practically all of Tennessee
except the western portion, and embraces the drainage basins of
the Tennessee and Cumberland Rivers and their tributaries.
                                      IMPROVEMENTS

             Navigation                              Flood Control-Continued
                                          Page                                       Page
1. Cumberland River, Tenn. and                 7. Wolf Creek Reservoir, Ohio
      Ky....----...------------------       879      River Basin, Ky----------...............     899
2. Tennessee River, Tenn., Ala.,               8. Dale Hollow Reservoir, Ohio
      and Ky           -----------------
                       ......            .. 889      River Basin, Tenn. and Ky...                 901
3. Inactive navigation projects..--- 894       9. Center Hill Reservoir, Ohio
                                                     River Basin, Tenn .....-.                    904
               Flood Control                   10. Ohio River Basin, Nashville,
                                                     Tenn., district...............-------------. 906
4. Middlesboro,      Cumberland               11. Inactive flood-control projects..              90&
                          ---------
      River Basin, Ky--.....               895 12. General investigations......---------........  908
5. Pineville, Cumberland River                13. Flood control work under spe-
      Basin, Ky .....                      896       cial authorization ........----------        909
6. Barbourville, Kyy                      897

                 1. CUMBERLAND             RIVER,    TENN. AND KY.
   Location. This river is formed by the junction of Poor and
Clover Forks in Harlan County, Ky., about 692.8 miles above its
mouth, and flows west to Burnside, Ky., from whence it makes a
loop southwestward into Tennessee, passes Nashville, and returns.
northwestward to Kentucky, emptying into the Ohio near Smith-
land, Ky. (See U. S. Geological Survey base maps of Tennessee
and Kentucky.)
   Previous projects. Below Nashville: The River and Harbor
Act of July 3, 1832, made the first appropriation for this section of
the river, but the River and Harbor Act of March 3, 1871, was the
first to define a project for its improvement. The River and Harbor
Act of September 19, 1890, adopted a special project for the im-
provement of the mouth of the river. For further details see page
1901 of Annual Report for 1915, and page 1208 of Annual Report.
for 1938.
   Above Nashville: Adopted by River and Harbor Acts of August
14, 1876, March 3, 1881, and July 5, 1884. For further details see
page 1898 of Annual Report for 1915, and page 1208 of Annual
Report for 1938.
   Existing project. Below Nashville: Prior to adoption of the,
9-foot navigable channel defined in succeeding paragraphs, the
project for this section of the river provided for the construction of
locks and dams A, B, C, D, E, and F, and dredging in the 43.6 miles
from lock F to the mouth to secure 6-foot navigation at extreme.
low water from the mouth to lock and dam 1, Nashville, Tenn.
                                                                             879
880               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

 (188.4 miles above the mouth), the first lock constructed under the
project for the section of the river above Nashville. The surmount-
ing of dams A to F with movable crests was also provided.
   Dredging in the lower river was made unnecessary by the con-
struction of lock and dam 52, Ohio River, which created a pool of
more than 6-foot depth from lock F to the mouth.
   The cost of new work for completion of the 6-foot navigation
project was $4,706,883, excluding amounts expended on .previous
projects.
   The principal features of the locks and dams included in the
project are given in the following table:
                                                   Lock A                         Lock B                        Lock C


Nearest railroad station_..___. Fox Bluff, Tenn. at Hickory Point, Tenn.,                                Sailors Rest, Tenn.,
                                      station.                         2% miles.                           1 mile.
Distance above mouth of river-- 150.6 miles___   ............140.3miles_.---------- 108.5 miles.
Lock dimensions 1_-         -____.__52 by 280 feet--------.......... 52 by 280 feet--------.......... 52 by 280 feet.
Normal pool level---......--...     371.9 feet, mean sea 358.6 feet, mean sea 346.8 feet, mean sea
                                      level.                           level.                              level.
Lift above normal pool of dam 13.3 feet ________   .......           11.8 feet..........------------..   12.3 feet.
  below.
Depth on miter sills at normal f10.5 feet, upper- __... 10.1 feet, upper                   ---.          10.5 feet, upper.
  pool.                            110.3 feet, lower-....... 10.3 feet, lower                    .---- 10.2 feet, lower.
Character of foundation-...._.. Rock ....       _-                   Rock      ....--------------. Rock.
Kind of dam _____________ Fixed_--------------                       Fixed_---------                     Fixed.
Type of construction 2--....___....Stone masonry lock, Concrete lock, timber                             Concrete lock, timber
                                      timber crib dam.                 crib dam.                           crib dam.
Placed in operation..---------- Nov. 26, 1904 ........------- Nov. 9, 1916__...........                  Sept. 2, 1918.
Cost of lock and dam .--------......$490,011 __ ----.-               $679,683------------............... $721,381.


                                                  Lock D                          Lock E                        Lock F


Nearest railroad station ........ Cumberland City,                             Cadiz, Ky., 12miles __ Eddyville, Ky., 1 mile.
                                              Tenn., 21 miles.
Distance above mouth of river__ 88 miles------------     ............ 66.3miles--___.............              43.6 miles.
Lock dimensions 1----_--                    52 by 280 feet-.........           52 by 280 feet--........        52 by 280 feet.
Normal pool level-----------.............. 334.5 feet, mean sea 323.6 feet, mean sea 313.5 feet, mean sea
                                              level.                             level.                           level.
Lift above normal pool of dam 10.9 feet------------                            10.1 feet------------           11.5 feet.
  below.
Depth on miter sills at normal 110.3 feet, upper- ...... 10.7 feet, upper- .....10.6 feet, upper.
  pool.                                    110.3 feet, lower-_ _ _ 10.6 feet, lower- ...... 12.4 feet, lower.
Character of foundation--..__           .. Rock _____................          Rock .                          Rock S.
                                                                                                      ..--------------
                                            Fixed...--------------............ Fixed --------------
Kind of dam---------------...................                                                                  Fixed.
Type of construction 2---____ . Concrete lock, timber Concrete lock, timber                                    Concrete lock, timber
                                              crib dam.                          crib dam.                         crib dam.
Placed in operation.....---------- Dec. 21, 1916---------.... Nov. 20, 1922--------........                    Nov. 1, 1923.
Cost of lock and dam...                 .. $629,255 .........------------..    $1,075,810-.......____._.       $1,110,743.

  1 Clear width and length available for full width.
  2With   concrete cap and movable crest.
  s Abutment founded on piles; dam partly on rock and partly on gravel.

   The extreme fluctuation in the stage of the river varies from
about 23 to 60 feet at different localities. Fluctuations below ex-
treme high water are so variable that it is impracticable to fix the
stage commonly referred to on other streams as ordinary high
water.
   The River and Harbor Act approved July 24, 1946 (Public Law
525, 79th Cong., 2d sess.), authorized the further improvement of
the Cumberland River between the mouth and Nashville for 9-foot
navigation; the increased project depth to be obtained by construc-
tion of 3 moderate height dams with lockage facilities, designated
as Kuttawa (Eureka), Dover, and Cheatham, to replace the exist-
ing locks A to F, inclusive, below Nashville, and lock 1, above Nash-
ville.        (See H. Doc. 761, 79th Cong., 2d sess.)                                         The cost (1954) of
               RIVERS AND HARBORS-NASHVILLE, TENN., DISTRICT                                                                         881
canalization with locks 110 feet wide and 800 feet long is estimated
as $50,620,000. Supplemental authority contained in Public Law
396, 82d Congress, 2d session, approved June 19, 1952, provides
for the construction of facilities for the generation of hydroelectric
power at Cheatham Dam, at an additional cost of $18,200,000.
   The principal features of the locks and dams comprising the
modified project for 9-foot navigation and power production are as
follows:
                                                                                               Lock and dam


                                                                                                    Dover                  Cheatham
                                                                  1Kuttawa

Nearest town-_             ..          -                         Kuttawa, Ky.,                Cumberland                 Ashland City,
                                                                  9 miles.                       City, Tenn.,             Tenn., 9 miles.
                                                                                                4 miles.
Distance above mouth of river _        ._____.                     32.2 miles- ......         100.1 miles-......     148.7 miles.
Lock dimensions 1.-    ...-         - -         _                  110 by 800 feet_..         110 by 800 feet.---    110 by 800 feet.
Normal pool level ____      . ______..
                                   ..         _. ..                328 feet, mean             355 feet, mean         385 feet, mean
                                                                     sea level.                 sea level.              sea level.
Lift at normal pool levels______...........___ .....               26 feet...........         27 feet-...........    30 feet.
Depths on guard sills at normal pool levels.......                 16.0 feet, upper..         16.0 feet, upper--     17.0 feet, upper-
                                                                   12.0 feet, lower_..        13.0 feet, lower..     13.0 feet, lower.
Character of foundation....                                        Rock ..........            Rock-_........         Rock.
Kind of dam .......           ..... _ ......       ..... ........  Fixed 2..........          Fixed 2_.........      Fixed 2.
Type of construction_........__          __.___.._____ _ __ Concrete-.....                    Concrete----.......    Concrete.
Power development:
    Number of units                __
                                   _....__
                                 .___ ..... _       ..       .....                                                   3.
    Generator rating (kilowatts) .........                                                                           12,000.
    Total installation (kilowatts) ..........                                                                        36,000.
Percentage of com pletion                  _____ ______ . ____ _                                                     44.
Estimated cost:
    Lock and dam ...............           ...............
    Power plant__                               _------.-              $15, 859, 000                $21, 261, 000             $13, 500, 000
                                                                                                                               18, 200, 000
                                                                                         I-             --          I-
        Total, project.                                                 15, 859, 000                 21, 261, 000              31, 700, 000

  1 Clear width and length available for full width.
  2 Gate-controlled spillway across stream channel.


   The existing project for the section below Nashville was author-
ized by the following River and Harbor Acts:

       Acts                                Work authorized                                                   Documents
July 13, 1892      Provision made for lock A__..._.._                   Annual Report, 1890, p. 2151.
June 25,1910       Provision made for locks B to F, and for dredging H. Docs. 758, 60th Cong., 1st sess.,
                     below lock F.                                        and 1481, ' 60th Cong., 2d sess.
Aug. 30, 19352     Repairing dams A to F, inclusive, and surmounting H. Doc. 38, 73d Cong., 1st sess.
                     same with movable crests.
July 24,1946       Provision of 9-foot channel by the construction of 3 H. Doc. 761, 79th Cong., 2d sess.
                     moderate height dams below Nashville.
June 19,1952       Provision for hydroelectric power production as a----------
                    function of Cheatham Dam.

  1   Contains latest published maps.
  2 Included   in Public Works Administration program Sept. 6, 1933.


  Above Nashville: The River and Harbor Acts of August 5, 1886,
March 2, 1907, March 2, 1919, and June 5, 1920, provided for the
construction of locks and dams 1 to 17 and 21 to secure 6-foot navi-
gation at low water from Nashville (lock and dam 1, 188.4 miles
above the mouth) to Waitsboro Shoals (a distance of 324.6 miles),
and 4-foot navigation from Waitsboro Shoals to Burnside (3 miles) ;
provision also being made for the periodic removal of snags and
similar obstructions from Nashville (lock and dam 1) to Burnside
 882              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

 (327.6 miles). The project as modified by the River and Harbor
Act of July 3, 1930, further provided for raising dam 1 by 3 feet
 (Rivers and Harbors Committee Doec. 26, 70th Cong., 2d sess.).
   Under the above authority, locks and dams 1 to 8, inclusive, and
21 were completed and placed in operation during the period 1888--
1924. The raising of dam 1 by installation of crest wickets was
completed in October 1931. Proposed locks and dams 16 and 17
were eliminated from the project upon authorization of Wolf Creek
Reservoir (p. 899), the construction of which has also resulted in
the permanent inundation of lock and dam 21.
   The estimated cost for new work, last revised in 1947, is $14,-
600,000; including $25,000 for raising dam 1, and excluding the
costs of projected locks and dams 16 and 17 eliminated by Wolf
Creek Reservoir.
   The principal features of the existing locks and dams 1 to 8, in-
clusive, are given in the following tabulation; for comparable
details on lock and dam 21 (abandoned) and the other structures
contemplated under the project, see Annual Report for 1950:

                                       Lock 1                     Lock 2                              Lock 3                         Lock 4


Nearest railroad sta-        Nashville, Tenn.,            Madison, Tenn.,                      Hendersonville,                 Gallatin, Tenn., 5
  tion.                        2% miles.                    1% miles.                            Tenn. 3 miles.                  miles.
Distance above mouth         188.4 miles .....----        201 miles__________                  218.1 miles -------             237 miles.
  of river.
Lock dimensions 1            52 by 280 feet -----         52 by 280 feet.-----                 52 by 280 feet -. -    52 by 280 feet.
Normal pool level -- .       377.4 feet, mean             386.4 feet, mean                     397.5 feet, mean       410.8 feet, mean
                               sea level.                   sea level.                           sea level.             sea level.
Lift above normalpool        5.5 feet _...----            9 feet.......------                  11.1 feet .---     --- 13.3 feet.
  of dam below.
Depth on miter sills at J9.5 feet, upper-.....            7.5 feet, upper        --            6.6 feet, upper        -       7.9 feet, upper.
  normal pool.           10.5 feet, lower -          -    9.5 feet, lower ..                   7.5 feet, lower   .            6.6 feet, lower.
Character of founda- Rock            ....----------       Rock----                     -       Rock ---.- -      -            Rock.
  tion.
Kind of dam-        . * Fixed ...------          Fixed .__......._ Fixed .....- ...                                           Fixed.
Type of construction    Stone masonry            Stone masonry Stone masonry                                                  Stone masonry
                                lock, timber
                                         2         lock, timber         lock, timber                                            lock, timber
                                crib dam. "        crib dam;3 con-      crib dam; con-                                          crib dam; 3  con-
                                                   crete cap.           crete cap.                                              crete cap.
Placed in operation....      Nov. 26, 1904...... Oct. 9, 1907...____.._Oct. 15, 1908 -_----                                   Nov. 17, 1909.
Cost of lock and dam_.              - ........
                             $395,634            $340,242-........ $348,354-- ........                                        $346,430.
                                   1                  1                                    1                              l




                                       Lock 5                     Lock 6                             Lock 7                          Lock 8
                           I------------I             1

Nearest railroad sta-        Lebanon, Tenn.,              Hartsville, Tenn.,                   Carthage, Tenn., Carthage,                     Tenn.
tion.                         10 miles.                    4 miles.                             8Y2 miles.           5 miles.
Distance above mouth         264.7 miles-........         281.6 miles........                  299.7 miles __....-- 317 miles.
of river.      1
Lock dimensions '_           52 by 280 feet-......        52 by 280 feet-......                52 by 280 feet...... 52 by 280 feet.
Normal pool leveL---         421.5 feet, mean             435.2 feet, mean                     445.5 feet, mean 458.2 feet, mean
                               sea level.                   sea level.                           sea level.           sea level.
Lift above normal pool       10.7 feet-----------         13.7 feet...------......--           10.3 feet.........._ 12.7 feet.
  of dam below.
Depth on miter sills at 16.6 feet, upper.....             8.3 feet, upper-..... 6.6 feet, upper ...                           6.7 feet, upper.
  normal pool.          \7.9 feet, lower-.....            6.6 feet, lower-..... 8.3 feet, lower. _--                          6.7 feet, lower.
Character of founda- Rock............                     Rock....       ..------.. Rock-----------                           Rock.
  tion.
Kind of dam.--------- Fixed.............                  Fixed __-.........                   Fixed.............             Fixed.
Type of construction... Stone masonry                     Stone masonry                        Stone masonry                  Concrete lock, tim-
                           lock, timber                     lock, timber                         lock, timber                   ber crib dam.
                           crib dam; con-                   crib dam; con-                       crib dam; con-
                           crete cap.                       crete cap.                           crete cap.
Placed in operation.... Oct. 18, 1909.......              Oct. 21, 1910.......                 Oct. 18, 1910-------           Sept. 15, 1924.
Cost of lock and dam.. $373,590 ...........               $369,357_-_---....                   $378,568---.......--           $680,915.


  SClear width and length available for full width.
  SWith concrete cap and movable crest.
  SWith timber cap set on concrete cap.
                RIVERS AND HARBORS-NASHVILLE,                                                   TENN., DISTRICT                               883
   The extreme fluctuation in the stage of the river varies from
about 20 to 40 feet at different localities. Fluctuations below ex-
treme high water are so variable that it is impracticable to fix the
stage commonly referred to on other streams as ordinary high
water.
   The River and Harbor Act approved July 24, 1946 (Public Law
525, 79th Cong., 2d sess.) also authorized, in addition to the further
improvement for navigation between the mouth and Nashville, the
construction of Old Hickory, Carthage, and Celina Dams above
Nashville for navigation and power. The cost (1954) including a
lock at Old Hickory, is estimated as $122,964,000. Prosecution of
the modified project for this section of the river will eliminate ex-
isting locks and dams 2 to 8, inclusive, and precludes further con-
sideration of the previously projected locks and dams 9-15, inclu-
sive. (See H. Doc. 761, 79th Cong., 2d sess.)
   The principal features of the authorized reservoir units are as
follows:

                                                                                                 Dam and reservoir
                                                                          Old Hickory                   Carthage                     Celina

Nearest town...-.......------.--------                              Old Hickory,      Carthage,                               Celina, Tenn.,
                                                                       Tenn.,3miles.    Tenn., 5miles.                          5 miles.
Distance above mouth of river (miles)-...........                   216.2--...-.. ... 313.5 ... . ..                          385.7.
Lock dimensions (feet) 1----------------------...........           84 by 400-......
Lift at normal pool levels (feet)-------------... --                60 ..............
Depths on guard sills at normal pool levels (feet)_ (17.0                upper -..--
                                                                   ,13.0, lower -----
Character of foundation------- -------                    ----------Rock----------- Rock ...........                          Rock.
Height of dam (feet)----..------------------------ 98--------------                   98.............                         86.
Type of dam...---------------------------------                    Concrete gravity Concrete gravity                          Concrete gravity
                                                                       and earthfill.   and earthfill.                            and earthfill.
Spillway:
  Gross length (feet) _-----------------                        325 ------ -                   -- 265 -----                   290.
  Netlength (feet)-----------------------------..........       270------------..                 225_--                  -   250.
Crest gates:
  Type ,, . .....-----------------------.                       Tainter ...-...                   Tainter__               .   Tainter.
  Number.......                ........------------------------ 6-------------
                                                                    ........                      5--                     -   5.
  Size (feet)----------------..------------------               45 by 41 ------.. 45 by 41_                                   50 by 37.
Discharge capacity (cfs)....                                    226,000......---------            176,000___                  142,000.
Operating levels (feet, mean sea level):
    M axim um regulated surcharge ..........                    450 ----. -                 --    508 ------                  555.
    Normal pool----...--........           ...-------------     445------------                   500 -                  .    550.
    Conservation pool.........._...............                 442..------------                 497 --..               .    549.
Reservoir capacity (acre-feet):
    Flood control 2----------------------------............... 125,000 ..                  .      106,000 - ....              59,000.
    Pondage allowance for power- ........-- ---                 63,000.....                ...    32,000 -------..            10,000.
     Conservation...-------------------                         357,000-........                  217,000 ......              179,000.
      Total..............-------------------..........          545,000. ..                ...    355,000 -         ....      248,000.
Power development:
    Number of units ............-..........-----                4--.............----------        4------------..3.
    Generator rating (kilowatts) .............                  25,000---------...........        23,000---------.            23,000.
    Total installation (kilowatts).-..               - ..-100,000-------........-- 92,000- __... .                            69,000.


Estimated cost:
    Construction.._ ----------------                                           $39, 186, 800              $33, 019, 300              $28, 542, 900
    Lands and damages..........................                                 10, 713, 200                5, 544, 700                5, 957, 100
                           ----------
        Total...............---                      --      _...                49, 900, 000              38, 564, 000                 34, 500, 000

  1 Clear width and length available for full width.
  2   Surcharge storage.
884              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   The existing project for the section above Nashville was author-
ized by the following River and Harbor Acts:

       Acts                        Work authorized                                     Documents
Aug.    5,1886   Provision made for locks and dams; the Secretary of        Annual Report 1884, p. 1663.
                   War to determine the final plan of improvement.
                 Dimensions of the locks fixed in accordance with re-       Annual Report 1888, p. 1622, and
                  ports of Mar. 30, 1887, and Nov. 25, 1890.                 Annual Report 1892, p. 1933.
Mar.    2,1907   Adoption of the report of the Board of Engineers,          H. Doc. 699, 59th Cong., 1st sess.
                   dated Feb. 26, 1906, limiting the lock and dam con-
                   struction to locks and dams 1 to 7, and 21.
Mar. 2,1919      Provision made for locks and dams 8 to 17.....----------   Rivers and Harbors Committee
                                                                              Doc. 10, 63d Cong., 2d sess.
June 5, 1920     Authorizes work to proceed in Tennessee without
                  waiting for action of local interests in Kentucky.
July    3,1930   Raising dam 1, 3 feet---...- -    --------     Rivers and Harbors Committee
                                                                 Doec. 26, 70th Cong., 2d sess.
June 26,19341 Operation and care of locks and dams provided for
                with funds from War Department appropriations
                for rivers and harbors.
July 24, 1946 Construction of Old Hickory, Carthage, and Celina H. Doc. 761, 79th Cong., 2d sesso
                Dams above Nashville for navigation and the de-
                velopment of power resources.

 'Permanent Appropriations Repeal Act.


   The current (1954) estimate of annual cost for operation and
maintenance of both sections of the river is $850,000.
   Recommended modification of project. Senate Document No.
81, 83d Congress, 2d session, recommends modification of the
existing project for navigation on the Cumberland River, Tenn.
and Ky., to provide, in lieu of the presently authorized works at:
Kuttawa, mile 32.2, and Dover, mile 100.1, for the construction
of a multipurpose improvement for navigation, flood control, and
hydroelectric power consisting of a dam, lock, and power plant in
the vicinity of mile 30.5 on the lower Cumberland River and a
canal for navigation and other purposes connecting the proposed
reservoir with the reservoir formed by Kentucky Dam on the
Tennessee River, at a total estimated cost to the United States of
$145,000,000 for construction and $433,000 annually for mainte-
nance and operation.
   Local cooperation. Below Nashville: None required. Above
Nashville: Fully complied with.
   Terminal facilities. At Nashville, Tenn., there is a five-story
terminal building 300 feet long and 140 feet wide, built of rein-
forced concrete, having large and convenient loading platforms,
electric elevator and crane, with railroad connections, municipally
owned and open for public use. At Clarksville, Tenn., there is a
privately owned warehouse with inclined tramway. Privately
owned terminals for the transfer of petroleum products have been
constructed at Dover, Clarksville, and Nashville, Tenn. There are
also privately owned terminals located near Smithland, Ky., used
for the transfer of riprap rock; at Dycusburg, Ky., for the transfer
of fluorspar; at Clarksville, Tenn., for the transfer of sand and
gravel; and at Nashville, Tenn., for the transfer of sand and
gravel, scrap metals, molasses, and forest products. In addition
to the foregoing there are many unimproved private landings
along the river. The facilities are considered adequate for existing
commerce.
  Operations and results during fiscal year. a. Below Nashville:
        RIVERS AND HARBORS-NASHVILLE, TENN., DISTRICT           885
Operations for completion of the Cheatham unit of the existing
project as modified for 9-foot navigation were continued.
   The principal items of work under the continuing contract for
construction of the dam were brought to the following percentages
of completion: Cofferdam, 100 percent; common excavation, 58
percent; rock excavation, 98 percent; concrete placed, 99 percent;
tainter gate anchorages, 100 percent; steel sheet piling for power-
house cofferdam, 93 percent; and power plant cofferdam installa-
tion, 82 percent. Approximate quantities of the major items of
work accomplished were: Common excavation, 19,610 cubic yards;
rock excavation, 138,300 cubic yards; concrete placed, 16,270
cubic yards; miscellaneous metal and pipe placed, 72,240 pounds;
and steel sheet piling furnished, 1,193,040 pounds.
    First stage excavation for the power plant under a continuing
contract was completed during the year, with approximately
13,160 square feet of line drilling, 9,900 cubic yards common
excavation, and 54,100 cubic yards rock excavation being accom-
plished. A contract for design of the power plant was initiated,
and operations under contracts for furnishing upstream emer-
gency dam and for additional reservoir clearing (1,995 acres)
were initiated and completed. Work under contracts for turbine
and generator manufacture was continued. Necessary relocations
of roads in Dickson County, Tennessee, were effected under an
agreement entered into with the county.
    In addition to preparation and issuance of plans and specifica-
tions for the work items contracted during the year, hired labor
operations included planning for additional roadway relocations
and completion of plans and specifications for the following:
Railroad relocations; powerhouse substructure; accessory elec-
trical equipment; draft tube gantry, and 275-ton cranes; intake
and draft tube gates; permanent upper lock gate sill; and demoli-
tion of locks and dams A and No. 1. Land acquisition activities
were continued; 152 acres within the reservoir area being acquired
in fee simple and 461 acres in easement. Negotiations with the
Tennessee Central Railway for necessary railroad relocations were
completed.
   The costs for new work were $3,959,248.
   Maintenance by Government plant and hired labor consisted of
navigation inspections, removing 9,815 cubic yards of mud and
5,626 snags from the channel, and dredging 82,465 cubic yards of
material at the following sites: 47,550 cubic yards at Devils
Potato Hill IBar (Mile 65.0); 7,755 cubic yards at Kuttawa Bar
 (Mile 40.4) ; 13,200 cubic yards at Shelley Island Bar (Mile 54.0) ;
6,435 cubic yards at Kuttawa Ferry Bar (Mile 41.8) ; and 7,525
cubic yards below Cheatham lock and dam (Mile 148.3). The cost
of operation and maintenance was $78,980.
    b. Above Nashville: Construction under the modified project
for this section of the river was continued under contracts for
features of the Old Hickory unit. With completion of the lock
and dam structures during the year, the following quantities of
the major items of work were accomplished: Common excavation,
338,200 cubic yards; rock excavation, 5,730 cubic yards; im-
pervious fill, 77,400 cubic yards; random fill, 58,650 cubic yards;
886      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

concrete placed, 58,470 cubic yards; reinforcing steel installed,
456,500 pounds; and miscellaneous metal work installed, 451,300
pounds. Contracts for furnishing spillway bulkheads and clearing
a portion of the reservoir area (10,480 acres) were initiated and
completed.
   Work accomplished under a continuing contract awarded during
the year for construction of the power plant consisted principally
of mobilization of forces and plant, acquisition of materials, and
initiation of cofferdam placement. Miscellaneous activities were
continued under outstanding contracts for turbines and governors,
generators, cranes, transformers, and accessory electrical equip-
ment in accordance with delivery schedules.
    Negotiations were continued with owning agencies for adjust-
ment of natural-gas transmission lines and with individual
counties regarding county and farm road relocation. Work under
agreements entered into with Sumner and Wilson Counties, Tenn.,
was commenced by those counties.            An agreement was also
reached with one of the two gas-line companies involved.
    Design of the power plant was performed by contract. Hired
labor operations included preparation and issuance of plans and
specifications for the other work items contracted during the year,
preparation of such for additional reservoir clearing (4,950 acres),
and partial accomplishment of engineering and design studies for
required channel dredging, demolition of existing locks, and
additional road relocations. Approximately 16,125 acres of land
in the reservoir area were acquired, 16,085 acres in fee simple
and 40 acres in easement.
    Preliminary work (engineering and design) only in connection
with the Carthage and Celina units of the modified project for this
section of the river was performed. Mapping of both reservoirs
by contract was completed. Definite design studies for Carthage
Dam, comprising investigations and preliminary designs required
for definition of overall features of the project, were prosecuted
by hired labor and brought to about 65 percent completion.
    The costs for new work were $13,221,074. No channel main-
tenance costs were incurred.
    c. Operation and maintenance of locks and dams: Old Hickory
lock was placed in temporary operation during the year for the
passage of tows during construction of the power plant. Locks
A to F, Cheatham, and 1 to 7, inclusive, were operated as required.
Maintenance, improvement, and reconstruction work was held to
a minimum in compliance with policy concerning the use of critical
materials and equipment, and in view of the development of new
navigation facilities now under way. Repairs were made to a
broken gate pintle at lock A and to the filling valves at locks
B, C, D, E, F, and 2. The emptying valves at lock C were rebuilt.
Other operations included construction of steel steps at the up-
stream end of lock E; and the installation of electric lines to the
abutments at locks B-F, inclusive, in connection with provision
of flood-lighting facilities. The cost of operation and maintenance
was $619,370.
    The total costs during the fiscal year were $17,878,672, of which
       RIVERS AND HARBORS-NASHVILLE, TENN., DISTRICT            887
$17,180,322 was for new work, and $698,350 for operation and
maintenance.
   Condition at end of fiscal year. a. Below Nashville: All locks
and dams under the existing 6-foot navigation project for this
section of the river have been completed, affording full project
depth between the mouth and Nashville throughout the entire year.
The initiation of work on lock and dam A in June 1895 marked
the commencement of construction under the project. The dates
on which the individual locks and dams were completed and
placed in operation are given in the tables under paragraph
"Existing project."
   New work under the authorized modification of the existing
project for 9-foot navigation, as a whole, was approximately 20
percent complete. Engineering and design were about 60 percent
complete.
   Construction under the modified project was commenced in
April 1950 when operations were initiated under a continuing
contract for construction of the Cheatham lock, access road, and
operations building. The lock was placed in temporary operation
on December 12, 1952. Work under a continuing contract for
construction of the dam was initiated in August 1952, and at the
end of the year was 90 percent complete. Contracts for the
following had been completed: Spillway bulkheads; emergency
dam; reservoir clearing (2,275 acres) ; removal of a cemetery in
vicinity of the dam; relocation of affected roads in Dickson County,
Tennessee; and first stage excavation for the power plant. Work
under contracts for turbine and generator manufacture was in
progress. A contract was awarded near the end of the year for
demolition of existing locks and dams A and No. 1, but work has
not been started. Approximately 99 percent of the lands requited
for purposes of the project has been acquired, about 5,714 acres
in fee simple and 1,325 acres in easement. The Cheatham project
as a whole was 44 percent complete.
   The total costs for this section to June 30, 1954, were $19,796,-
789, including $685,000 from Public Works funds. Of this amount,
$19,022,539 was for new work, and $774,250 for operation and
maintenance.
   b. Above Nashville: Prior to modification of the existing proj-
ect for this section of the river in 1946, locks and dams 1 to 8,
inclusive, and 21 had been completed; the initiation of work on
lock and dam 1 in September 1888 marking the commencement of
construction under the project. The dates on which the completed
structures 1 to 8 were placed in operation are given in the table
under paragraph "Existing project." Lock and dam 21, completed
in October, 1911, has since been inundated by Wolf Creek Reser-
voir (described on p. 899), which also eliminated projected locks
and dams 16 and 17. Operation of lock 21 was discontinued on
May 4, 1947; custodial services only being maintained until May
31, 1949, at which time the structure was abandoned. Owing to
cessation of river traffic above Carthage, Tenn., lock 8 was placed
in an inoperative status on November 30, 1951. Lock and dam 3
was operated to June 14, 1954, at which time the structure was
inundated by the Old Hickory reservoir.
888       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

     With Old Hickory lock now in temporary operation, the existing
locks and dams provide, at extreme low water, a navigable channel
6 feet deep from Nashville (lock and dam 1,188.4 miles above the
mouth) to Niagara Shoals, a distance of 143 miles. In the
shallowest part of the uncanalized reach between the head of pool,
lock and dam 8, and Wolf Creek Dam at mile 460.9 above the
mouth, the depth at extreme low water is about 0.5 foot. In this
section, 3-foot navigation is practically certain from February 1
to May 1, and usually possible from January 1 to June 1. Four-
foot navigation is usually possible from February 1 to May 1, but
no period can be fixed during which it is reasonably certain.
Navigation of vessels drawing over 4 feet is uncertain at all times.
When the Celina gage reads 1 foot, 16-inch navigation is practi-
cable, and for each additional foot of reading on this gage, the
navigable depth is increased 0.8 foot.
     New work under the authorized modification of the existing
project for this section of the river, as a whole, was 22 percent
complete. Engineering and design were 44 percent complete.
     Construction of Old Hickory under the modified project was
commenced in January 1952, and the contract for the lock and
dam structures has been completed. The lock was placed in
temporary operation on June 14, 1954. Work under a continuing
contract for construction of the power plant was initiated in
March 1954, and was approximately 5 percent complete at the end
of the fiscal year. A contract covering access road construction
and excavation in the switchyard area had been completed. The
status of various contracts for Government-furnished equipment
items was as follows: Turbines, 92 percent complete; generators,
91 percent; main transformers, 90 percent; 275-ton powerhouse
crane, 77 percent; 75-ton crane, 87 percent; 15-ton gantry crane,
77 percent; and accessory electrical equipment, 63 percent.
    Approximately 23,556 acres, or 79 percent of the necessary
reservoir lands, have been acquired in fee simple; and 40 acres
in easement. A portion of the area, 10,480 acres, has been cleared
by contract. Relocation work was in progress at the end of the
year under road construction agreements with two of five counties
involved.
    The Old Hickory project as a whole was about 54 percent
complete.
    The total costs for this section to June 30, 1954, were $31,578,-
231, of which $31,220,620 was for new work and $357,611 for
operation and maintenance.
    c. Operation and maintenance of locks and dams: Locks A-F,
1, 2, and 4-7, inclusive, and the new Cheatham and Old Hickory
locks were in operation, the structures and appurtenances having
been maintained in serviceable condition.
    The total costs under the existing project for the entire stream
were $59,125,059, of which $50,243,159, including $685,000 from
Public Work funds, was for new work, and $8,881,900 for opera-
tion and maintenance. Surplus property valued at $5,748 was
transferred to the project without reimbursement. In addition, the
sum of $3,266,706 was expended between July 1, 1905, and June 30,
           RIVERS AND HARBORS-NASHVILLE,                                 TENN., DISTRICT                       889
1935, on the operation and care of the works of improvement under
the provisions of the permanent indefinite appropriation.
                                     Cost and financial summary

                                              Fiscal year ending June 30                             Total to June
                                                                                                     30, 1954, includ-
                                                                                                     ing fiscal years
                              1950          1951           1952          1953            1954         priorto 19501


New work:
   Appropriated-.......    $1,516, 000   $2,455,200     $5, 250,000 $16,255,000      3$18, 191,680      8$52, 290, 534
    Cost----------------      462, 887    1, 987, 939    4,607,131    17, 235, 708    17,180, 322         51, 069, 412
Maintenance:
   Appropriated --------      852,450       527, 959       728, 000      558, 147         697, 500        12, 187, 674
   Cost----------------       793 056       608, 883       601, 109      686, 362         698, 351       212, 148, 606


  1 Includes $826,253 for new work and $3,266,706 for maintenance for previous projects.
2 In addition, surplus property valued at $5,748 was transferred to the project without reimbursement.
3 Includes construction funds borrowed from other projects in amount of $2,230,000.
4 Excludes construction funds borrowed during fiscal year 1954 from other projects.
  5 Total for completion of existing project including Dover and Kuttawa locks and dams. The authoriza-
tion of the recommended Lower Cumberland lock and dam, which is a substitute for Dover and Kuttawa
locks and dams, will increase this amount by $166,915,300.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_            _-      $132,431
    Appropriated for succeeding fiscal year ending June 30, 1955-....     4 15,560,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955_-------------------_       -------------------- 15,692,431
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project_ __               -____________--- ----  133,512,120

               2. TENNESSEE RIVER, TENN., ALA., AND KY.
   Location. The Tennessee River is formed by the junction of
the French Broad and the Holston Rivers in eastern Tennessee,
4.4 miles above the Gay Street Bridge at Knoxville, flows south-
west into northern Alabama, thence in a generally westerly course
across north Alabama, to the northeast boundary of Mississippi,
thence nearly due north across Tennessee and Kentucky, entering
the Ohio River at Paducah, 652.1 miles from the junction of the
French Broad and Holston Rivers. (See U. S. Geological Survey
base map of the Tennessee River Basin.)
   Previous projects. a. Above Chattanooga: Adopted by the
River and Harbor Acts of August 30, 1852, June 10, 1872, August
18, 1894, and July 25, 1912.
   b. Chattanooga to Riverton: Adopted by the River and Harbor
Acts of August 30, 1852, July 25, 1868, March 3, 1871, September
19, 1890; acts of April 26, 1904, and January 7, 1905; and River
and Harbor Acts of March 2, 1907, June 25, 1910, July 25, 1912,
July 27, 1916, and March 3, 1925.
   c. Below Riverton: Adopted by the River and Harbor Acts of
July 25, 1868, September 19, 1890, August 18, 1894, March 3, 1899,
and July 25, 1912.
   For further details see pages 1902 to 1906 Annual Report for
1915, pages 1190-1194, 1196-1216, and 1220-1222, Annual Report
for 1929, and page 1216, Annual Report for 1938. The costs for
permanent work were $15,123,219.
   Existing project. The River and Harbor Act of July 3, 1930
 (Public No. 520, 71st Cong., 2d sess.), authorized the permanent
improvement of the river for a navigable depth of 9 feet at low
890      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

water from the mouth to Knoxville, Tenn., a distance of about 650
miles, to be obtained by the construction of low dams; provided,
that under the provisions of the Federal Water Power Act a high
dam with locks may be substituted for any two or more of the low
dams and built by private interests, States, or municipalities; and
provided further, that in case high dams are built before the
United States shall have built the projected locks and low dams
which are to be replaced, the United States shall contribute to the
cost of the substituted structures an amount equal to the estimated
cost of the work of navigation for which substitution is made.
 (See H. Doc. 328, 71st Cong., 2d sess.)
   The estimated cost of the authorized project as contained in
House Document 328, 71st Congress, 2d session, exclusive of
amounts expended on previous projects, is $74,709,000 for new
work and $40,000 annually for the maintenance and operation of
each lock and dam. The latest published maps are in the project
document.
   The above-mentioned act also authorized the appropriation of
$5,000,000 for the prosecution of work on this project. The only
construction performed by the Corps of Engineers thereunder was
the construction of the lock at the General Joe Wheeler Dam and
miscellaneous appurtenant improvements. No low dams were
constructed under this authorization.
   The cost of new work completed by the Corps of Engineers is
$2,244,236, excluding amounts expended on previous projects.
The current (1954) estimate of annual cost for operation and
maintenance of channels, the 10 locks, and dam 1 (including the
locks constructed by the Tennessee Valley Authority and operated
by the Corps of Engineers) is $800,000.
   Under the provisions of the Tennessee Valley Authority Act of
1933, approved May 18, 1933 (Public Law 17, 73d Cong.), as
amended by an act approved August 31, 1935, the Tennessee Valley
Authority is given power to construct such dams in the Tennessee
River as will provide a 9-foot channel and maintain a water supply
for same from Knoxville to its mouth.
   The Tennessee Valley Authority program provides for obtaining
the authorized 9-foot project by the construction of high dams and
locks and utilization of certain locks and dams previously con-
structed under the jurisdiction of the Corps of Engineers.
   The following table contains information concerning various
features of the locks and dams now comprising the existing 9-foot
project:
                                          Location                                                                 Lock                                                          Dam

                                                                             Dimensions                          Minimum
                                                                                                                  depth on                                                                          Estimated
                                                                                                                 guard sills                        Per                                             or actual         "
    Name of project      1    Miles                                         Length            Lift                                  Character     cent-   Year          Kind       Type of            cost of
                              above         Distance from         Width     avail-                                                  of founda-    age of opened          of      construction       each lock
                              mouth         nearest town             of      able                                                       tion       com- to navi-        dam                         and dam
                                                                  cham-       for    Nor-        Maxi-                                           pletion gation
                                                                    ber      full     mal        mum           Lower      Upper
                                                                   (feet)   width    (feet)      (feet)        (feet)     (feet)
                                                                            (feet)

Kentucky.......------------     22. 4   0.5 mile above Gil-           110     600      56. 0         73. 3       12. 7      11. 0   Limestone       100   1942      Fixed_ Concrete and                   (2)
                                        bertsville, Ky.                                                                                                                     earth fill.
Pickwick Landing....           206.7    4.4 miles above Ham-         110      600      55.0          63.0        12. 8     10. 0    __.do-...
                                                                                                                                           .        100   1937      .__do... do.......                    (s)
                                          burg, Tenn.
No. 1-- -------------         256.8     0.3 mile above railroad       60      298       4.0          10.0        13.7     411.2     ..
                                                                                                                                     _do--.....     100   1926     ___do___ Concrete......            s 989, 215
                                          bridge at Florence,
                                           Ala.
Wilson.                        259. 4   2.9 miles above Flor-         60               90.0          90. 0      6 11.1      11.2     do------       100   1927     --    do---   _do        _-- .   746, 973,   540
General Joe Wheeler__          274. 9   18.4 miles above Flor-
                                           ence Ala.
                                                                      60      360      48. 0         51. 5        13. 2     14. 7 __.do-            100   1934     _..do___            do    ..      81, 796, 295
                                                                                                                                                                                                     8.


Guntersville -..         .-.. 349.0     9.1 miles below Gun-          60      360      39. 0         45. 0       11.8       13.0 ___do.._____       100   1937             Concrete and
                                                                                                                                                                   _..._do___                             (s)
                                           tersville Ala.                                                                                                                   earth fill.
Hales Bar    10. ..            431. 1   33.0 miles below Chat-        60      265      39. 0         41. 0       10. 7      16. 7 -..do.......      100   1913      _do__ Concrete -- __.
                                                                                                                                                                   .-                                      236, 389
                                           tanooga, Tenn.
Chickamauga_,           .... 471. 0     6.9 miles above Chat-         60      360      49. 0         53.'0       13.8       10. 0 ___do.....        100   1937     -._do___ Concrete         and          (s)
                                           tanooga, Tenn.                                                                                                                          earth fill.
Watts Bar ........... 529. 9            6.8 miles above Breed-        60      360      58. 0         70. 0       11.8       12. 0   Shale....       100   1941     .. do...          do...                ()
                                           enton, Tenn.
Fort Loudoun            ...... 602.3    1.3 miles above Lenoir        60      360      72. O0        80. 0       11.8       12.0    Limestone       100   1943     .__do__...do....---------              (3)
                                           City, Tenn.

    1 H. Doc. 328, 71st Cong., 2d sess., contains table, pp. 98-99, giving pertinent informa-                  6 Tailwater in canal; flight of 2 locks.
tion concerning low dams contemplated under 1930 project. Annual Report, Chief of
Engineers, for 1938, pp. 1218-1219, contains similar information pertaining to low dams
                                                                                                               7  Constructed by Corps of Engineers under authority of sec. 124, National Defense
                                                                                                             Act of June 3, 1916 (H. Doe. 1262, 64th Cong., 1st sess.). Actual cost of lock and dam.
                                                                                                                                                                                                                      H
in addition to existing locks and dams, including those constructed or under construe-                          s Actual cost of lock only as constructed by Corps of Engineers; dam constructed by
tion by the Tennessee Valley Authority.                                                                      Tennessee Valley Authority.
    'Lock and dam constructed by Tennessee Valley Authority.                                                   9 Actual cost to United States of existing lock; cost of existing lock and dam to power
    ' Lock and dam constructed by Tennessee Valley Authority. Design for lock prepared                       company was about $6,686,700. Structure built under supervision of Corps of Engineers.
with Corps of Engineers forces and funds.                                                                      10 Reconstruction of dam by Tennessee Valley Authority for raising pool level com-
    ' Minimum upper pool corresponding to fixed crest of dam.                                                pleted in 1948.
    SConstructed by Corps of Engineers; actual cost of lock and dam. Crest of dam raised                                                                                                                              00
1,7 feet by Tennessee Valley Authority in 1948.                                                                                                                                                                      €g
892       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

    The functions of the Corps of Engineers since adoption of the
Tennessee Valley Authority Act of 1933 have been those of cooper-
ation with the Authority through preparing (with Corps of
Engineers forces and funds) the designs of locks at Pickwick,
Guntersville, Chickamauga, Watts Bar, and Fort Loudoun Dams;
and, in accordance with the general navigation laws placing con-
trol and supervision over navigable waters in the Secretary of the
Army, the Corps of Engineers: Operates and maintains all locks,
lifts, or other facilities in aid of navigation; maintains navigation
channels and safety harbors by performing all necessary dredging
and snagging operations; examines and passes upon plans for all
bridges, wharves, or other structures in navigable waters prior to
construction, including construction plans involving the alteration
or modification of existing channels; establishes harbor lines
where essential to the preservation and protection of harbors;
provides for removal of unlawful structures, including wrecks;
cooperates and reviews plans of individuals, corporations-
municipal or private-in the improvement of navigable waters
at their own expense and risk; issues rules and regulations govern-
ing the opening and operation of drawbridges, the transportation
and dumping of dredgings or other material into navigable waters;
promulgates rules and regulations governing the use, administra-
tion, and navigation of navigable waters, including harbors there-
of; compiles statistics of waterborne commerce. The division of
responsibility regarding the project is outlined in memorandum
of agreement dated July 11, 1946, between the Tennessee Valley
Authority and the Corps of Engineers.
    Local cooperation. The River and Harbor Act of July 3, 1930,
requires no local cooperation in the construction of the alternate
system of low dams. It does, however, provide that in case high
dams are built before the United States shall have built the pro-
jected locks and low dams which are to be replaced, the United
States shall contribute to the cost of the substituted structures an
amount equal to the estimated cost of the works of navigation for
which substitution is made.
    Terminal facilities. Public use river terminals with railroad
connections, owned by the Tennessee Valley Authority, have been
constructed at Decatur and Guntersville, Ala., and Chattanooga
and Knoxville, Tenn. River terminals with railroad connections,
municipally owned, have been constructed at Sheffield, Ala., and
Chattanooga, Tenn. The other public terminals are mostly unim-
proved landings. Government-owned facilities for the transfer of
coal are located at Huntsville Arsenal, Ala., and at the following
Tennessee Valley Authority steam-electric powerplants along the
river: Colbert, Wilson, and Widows Creek in Alabama; and Hales
Bar, Watts Bar, and Johnsonville in Tennessee. Near Johnson-
ville, Tenn., there is a privately owned railroad siding. Railroad
inclines and sidings are available at Sheffield, Decatur, Hobbs
Island, Guntersville, and IBridgeport, Ala., and Chattanooga, Tenn.
Privately owned terminals have been constructed for the transfer
of certain commodities as follows: Molasses at Knoxville, Tenn.;
automobiles and miscellaneous merchandise at Guntersville, Ala.;
coal at Calvert City and Grand Rivers, Ky., and Chattanooga,
        RIVERS AND HARBORS--NASHVILLE,       TENN., DISTRICT      893
Tenn.; grain at Decatur and Guntersville, Ala., and Chattanooga,
Tenn.; petroleum products at Sheffield, Decatur, and Guntersville,
Ala., Reidland, Ky., and Perryville, Chattanooga, and Knoxville,
Tenn. In addition to the foregoing there are many unimproved
private landings along the river. The facilities are considered
adequate for existing commerce.
    Operations and results during fiscal year. No new work was
accomplished. Maintenance by Government plant and hired labor
consisted of navigation inspection; condition surveys; painting
clearance gages and warning stripes; dredging 13,350 cubic yards
of material at Diamond Island Bar (mile 197) ; and removing 3,128
cubic yards of material and 1,500 snags from harbors and channels.
The cost of maintenance was $43,038.
    Operation and care of locks and dams: All locks were operated
and lock appurtenances and standby plant were maintained as re-
quired. Maintenance and improvement and reconstruction work
was held to a minimum in compliance with current policy concern-
ing use of critical materials and equipment. Work previously in-
itiated in connection with refinishing the interior of the operations
building at Guntersville lock and construction of control shelters at
Kentucky and Pickwick locks was completed during the year. Ken-
tucky lock was unwatered, the emptying and filling valves recon-
ditioned, and repairs made to air and water lines. Quoins and miter
seals were reconditioned at Pickwick lock, the lower gates painted,
and repairs made to oil pumps. Additional items consisted of re-
pairs to joint seals in the Guntersville lock tunnel; overhaul of
operating machinery at Chickamauga lock; repairs to roof of op-
erations building and overhaul of machinery at Watts Bar lock;
resetting the stone entrance to the operations building at Fort
Loudoun lock; and the review, correction, and reproduction of the
Guntersville lock "as constructed" drawings. The cost of operation
and care was $592,971. The total cost of operation and mainte-
nance, general, during the fiscal year was $636,009.
    Condition at end of fiscal year. The existing project was com-
plete. Construction under the project was commenced in January
1933, when work was initiated on Wheeler lock. With the opening
of Kentucky lock for permanent operation in September 1944, all
projected locks and dams had been completed, affording a navigable
depth of 9 feet between the mouth and Knoxville, Tenn. (head of
river), except in the lock 1 canal and a short stretch in the upper
reaches of Hales Bar pool. Dredging in the canal and the raising of
dam 1 and Hales Bar Dam remaining under the Tennessee Valley
Authority program to provide full project dimensions were com-
pleted by that agency in 1948. The table under the paragraph
"existing project" gives the year opened to navigation and other
information concerning the 10 locks now in operation.
   The completed locks were operated and maintained under the
permanent indefinite appropriation to the end of fiscal year 1935,
as follows: Hales Bar, since November 1, 1913; lock (and dam) 1,
since March 1, 1926; Wilson, since June 1, 1927; and Wheeler, since
November 27, 1934.
   Subsequent to June 30, 1935, operation and maintenance of lock
and dam 1, Hales Bar, Wilson, and Wheeler locks have been carried
894                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

on with funds appropriated for the preservation and maintenance
of river and harbors, as well as the following: Pickwick Landing
lock, since September 1, 1937; Guntersville lock, since September 1,
1937; Chickamauga lock, since October 15, 1937; Watts Bar lock,
since March 3, 1941; Kentucky lock, since February 10, 1942; and
Fort Loudoun lock, since October 10, 1943.
      The total costs for the existing project were as follows:

                                                                                              Costs

                      Funds
                                                          New work               Maintenance           Operation                 Total
                                                                                                       and care

                         ....
Regular .--------------.....     -------- -                    $2, 244, 236        $2, 774, 677        1 $7, 417, 300       1$12, 436, 213
Maintenance and operation                - -                                                                  11, 665              11, 665
Increase of compensation, rivers and har-
  bors 1919 (certified claims) - .-.. --                ----       -----...-.                                                               5
                                                                                    2, 774, 682           17, 428, 965
        Total   -         --                                    2, 244, 236         2, 774, 682           17, 428, 965           12, 447. 883

  1   In addition, surplus property valued at $963 was transferred to the project without reimbursement.

  In addition, the sum of $2,889,149 was expended between 1890
and June 30, 1935, on the operation and care of the works of im-
provement under the provisions of the permanent indefinite ap-
propriation.
                                            Cost and financial summary

                                                      Fiscal year ending June 30                                          Total to June
                                                                                                                         30, 1954, includ-
                                                                                                                         ing fiscal years
                                     1950            1951                 1952         1953                1954           priorto 19501

New work:
   Appropriated ------- -----------             - --
                                          .- . ..---    -  -                                                                 $16,251,428
    Cost- - - - -.. -. .
   Cost-
Maintenance:
                        --.---..                                       ..
                                                  .. .. ..... .. . . -------
                           ...----------------------....                                            -----------               16,251,428
   Appropriated..    --------
                            $671,750  $603,741   $573, 000   $636,053   $677, 200                                                14,265,466
    Cost----------------     744,387   624,630    599,614     719,608    636,009                                             2   14,208,822

1 Includes $14,007,193 fornew work and $4,005,175 for maintenance for previous projects.
2 In addition, surplus property valued at $963 was transferred to the project without reimbursement.

                          3. INACTIVE                 NAVIGATION PROJECTS

                                                                  For last           Cost to June 30,1954                   Estimated
                                                                 full report                                                  amount
                    Name of project                                   see                                                    required
                                                                   annual             Con-             Operation                to
                                                                   report          struction              and                complete
                                                                    for-                              maintenance
1. Caney Fork River, Tenn               -       -  --                1895              $27,   828     --........................
2. Clinch River, Tenn.
                     2-
                        and Va.'  ---
                                       - -- --- - - - -
                                    - -- -
                                                                     1923               53,   949              $7, 873             $677, 000
3. Duck River, Tenn. . ............
                               2       - - - ...                     1887               13,   000
4. Elk River, Ala. and Tenn. ._           .__ _ .     .              1904                4,   000         --   _-__                (s)
5. French Broad and Little Pigeon Rivers,                            1931              249,   605              33, 554              533,000
    Tenn.4 5             2- - - - - - - - - - - - - - -
6. Hiwassee River, Tenn.2            - ....
                                        -- -- - -        ...         1923              113, 311                 9, 754               83, 000
7. Holston River, Tenn.               __..........__    ..           1911                5, 714       .
8. Little Tennessee River, Tenn------..                              1888                 5, 510
9. Obey River, Tenn...------------------------           1887                          11, 500 ------------                       (3)
10. Red River, Tenn.............------------------------- 1884                           5, 000 .
11. South Fork of Cumberland River, Ky -.....1892                                       11, 967 .     .      .               .       .


  IRecommended  for abandonment in H.
  2 Recommended for abandonment in H.
                                                    Doc. 532, 64th Cong., 1st sess.
                                                    Doc. 467, 69th Cong., 1st sess.
  3 Completed.
    Commercial statistics for this project are given in pt. 2 of report.
  5 Recommended for abandonment in H. Doc. 428 and 489, 64th Cong., 1st sess.
                  FLOOD CONTROL--NASHVILLE, TENN., DISTRICT                                                       895
            4. MIDDLESBORO, CUMBERLAND RIVER BASIN, KY.
   Location. This project is located at Middlesboro, Ky., on Yel-
low Creek, a tributary entering the Cumberland River about 660
miles above its mouth.
   Existing project. The improvement provides for a system of
canals and levees around one side of the town, arranged so as to
divert most of the headwaters of Yellow Creek away from the pres-
ent channel through the heart of the city. The series of canals
and levees are about 4 miles in length, beginning on Bennetts Fork
at the western edge of the town and ending at Yellow Creek near
the Keystone Tanning & Glue Co. at the northern edge of the town.
The cuts involved excavation of approximately 695,000 cubic yards
of material, of which about 410,000 cubic yards were utilized in the
levee system. Besides construction of the diversion channel, there
was other incidental work, which included the installation of cul-
verts and the relocation and rebuilding of roadways and bridges.
The project diverts from the business district and from a large part
of the residential section the floodwaters which originate in that
part of the basin lying north and west of the city, thus affording
protection; in a large measure, to life and property from these
headwater floods which cause the greatest damage. The project
was authorized by the Flood Control Act approved June 22, 1936.
The cost of the completed project is $817,830. The current (1954)
estimate of annual cost for operation and maintenance is $5,800.
   Local cooperation. None required.
   Operations and results during fiscal year. New work: None.
   Maintenance: Levees, canals, and appurtenances were main-
tained by hired labor at a cost of $9,579.
   Condition at end of fiscal year. New work under the existing
project was completed in March 1945, when final settlement was
made with the city of Middlesboro in connection with the acquisi-
tion and transfer to the United States of rights-of-way and flowage
easements. Construction of the canal and levee system, initiated
in May 1938, was completed and the improvement placed in opera-
tion in December 1939. Relocation work was completed in Septem-
ber 1940.
   The total costs to June 30, 1954, were $874,952, of which $817,-
830, including $38,876 from Emergency Relief funds, was for new
work and $57,122 for maintenance. In addition surplus property
valued at $4 was transferred to the project without reimbursement.
                                           Cost and financial summary

                                                    Fiscal year ending June 30                          Total to June
                                                          . .. .... ..
                                                        .....        .. . .                   .   ..    30, 1984, in clu d-
                                                                                                        ing fiscal years
                                    1950          1951            1952              1953      1954       priorto 1950


New work:
   Appropriated---       ----   -       ------------      -----------    - ------                                $817,830
   Cost                                       --
                                             ------------                                                         817,830
Maintenance:
   Appropriated --.. . -             $4, 000        $2,000    .    $3, 000          $8, 500   $11,800               60,000
   Cost--...-------                   1,948          4, 774         4,259            7,834      9,579             1 57,122


  I.In   addition, surplus property valued at $4 was transferred to the project without reimbursement.



           Sig 29-895-926
896      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

        5. PINEVILLE,    CUMBERLAND      RIVER BASIN, KY.
   Location. This project is located at Pineville, Ky., on the Cum-
berland River about 655 miles above the mouth.
   Existing project. The plan of improvement comprises the con-
struction of a system of earth levees and concrete floodwalls, with
appurtenant facilities, to afford protection for the city and its resi-
dential suburb, Wallsend, against a flood equal in magnitude to the
maximum of record (1946). The freeboard allowance is 5 feet for
the upstream section of the proposed works above Pine Street
Bridge, and 3 feet downstream. Protection for Pineville proper is
to be provided by about 5,950 feet of concrete walls and two rela-
tively short levee sections, 400 feet in total length, beginning at a
connection with United States Highway No. 25E near the upstream
limit of the city and following in general the top of the left bank
of the Cumberland River to terminate in the approach to the Ten-
nessee Avenue (Pineville-Wallsend) bridge. Raising of the bridge
and the provision of ramps or gated structures at necessary high-
way and street crossings will maintain access to the protected area.
Two pumping stations, with appurtenant outlet works and inter-
cepting sewers, will provide for the disposal of interior drainage.
Including extension of a roadway ramp to high ground south of
the intersection of United States Highway No. 25E with the Ten-
nessee Avenue bridge approach, the overall reach of the structures
in the Pineville section of the project approximates 6,800 feet. On
the right bank of the river provision is made for about 3,500 feet
of earth levee to partially encompass Wallsend, beginning and ter-
minating within a distance of 1,500 feet in the embankment of the
Louisville & Nashville Railroad which runs along the northern
edge of the community. Incidental construction in this section in-
cludes necessary ramp crossings, sewer modifications, and one
pumping station. The project was authorized by the Flood Con-
trol Act approved June 22, 1936. The estimated Federal cost of
new work (1954) is $1,720,000; the estimated non-Federal cost is
$450,000.
   Local cooperation. Subsequent to passage of the authorizing
act, local interests expressed inability to fulfill the requirements.
Following the flood of January 1946, however, interest in the
project was renewed, and informal assurances were furnished
at a public hearing on April 27, 1946, and at a further meeting on
December 22, 1947, relative to flood control in the upper Cumber-
land River Basin, that the conditions of local cooperation would
be fully complied with. Formal and final assurances were ac-
cepted by the Corps of Engineers on May 15, 1953. 'Bonds in the
amount of $200,000 of an issue voted for financing the city's
share of the project costs were sold on January 5, 1953, and the
acquisition of necessary lands and rights-of-way initiated. Prop-
erties affected by project features under construction have been
acquired. Regular contact is maintained with city officials relative
to local responsibilities, and they have demonstrated the ability
to meet the requirements for construction as scheduled.
   Operations and results during fiscal year. Work under con-
tract for the first unit of construction was completed during the
                        FLOOD CONTROL-NASHVILLE, TENN., DISTRICT                                                     897
year. Unit 1 embraces about 2,940 feet of the floodwalls and re-
lated drainage facilities designed for protection of Pineville proper,
beginning within 360 feet of the upstream limit of the proposed
works and extending along Cumberland Avenue to a point about
750 feet below the Pine Street Bridge. Construction of Unit 2,
comprising remaining floodwalls and drainage facilities (exclusive
of pumping plants) in the Pineville section, was initiated under a
contract covering drainage features only.
    Engineering and design by hired labor were continued. Definite
design studies for pumping plants in both sections of the project
and plans and specifications for unit 2-floodwalls (Pineville sec-
tion) were essentially completed. Planning for unit 3---embank-
ments (Pineville section) and the Wallsend section levee and drain-
age facilities was initiated.
    The costs during the year for new work were $390,218.
    Condition at end of fiscal year. Construction of the project
was commenced in July 1953. With completion of unit 1 and par-
tial accomplishment of the interior drainage work included in unit
2, the project as a whole at the end of the fiscal year was 26 percent
complete. Engineering and design were 85 percent complete.
    The total costs to June 30, 1954, were $452,960 for new work.
                                                    Cost and financial summary

                                                          Fiscal year ending June 30                       Total to June
                                                                                                          30, 1954, includ-
                                                                                                          ing fiscal years
                                           1950          1951        1952         1953         1954         prior to 1950

New work:
   Appropriated                             -........           ..   $25,000     $249, 000    $400, 000           $674, 000
   Cost --------------------------------------                          -----     62, 529     390, 431             452, 960

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_-----------     $152,963
    Appropriated for succeeding fiscal year ending June 30, 1955--------   230,000
    Unobligated balances available for succeeding fiscal year ending June
         30, 1955--                                                     -        --      --                     382,963
     Estimated additional amount needed to be appropriated for completion
       of existing project                                                                                     816,000

                                                 6. BARBOURVILLE,               KY.
   Location. The project is located at Barbourville in Knox
County, Ky., on the right bank of the Cumberland River at mile
635.2.
   Existing project. The plan of improvement provides for the
construction of local flood protection works at Barbourville, Ky.,
which consist principally of a system of levees having an average
height of 15 feet, beginning at a point where branches of the
Louisville & Nashville Railroad enter the main line northeast of
town and following in general the top of bank of Richland Creek
and the Cumberland River a distance of about 18,400 feet to ter-
minate into the Louisville & Nashville Railroad embankment south-
east of the town. Provision for a low area immediately across the
railroad consists of regrading an adjoining high knoll and con-
struction of a concrete and steel pile I-type wall, about 330 feet in
length, having a gated opening to pass U. S. Highway 25E and
898          REPORT OF CHIEF OF ENGINEERS. U. S. ARMY;                                    1954

extending to high ground beyond. Other incidental construction
includes 9 gravity outlet structures and 4 combined gravity outlets
and pump stations, with intercepting ditches or pipe lines, for dis-
posal of interior drainage; and 6 ramps at road and street cross-
ings. The proposed works will afford protection for the town
against the greatest flood of record (1946) with a freeboard of 3
feet.
   The project was authorized by the Flood Control Act approved
May 17, 1950. The estimated cost of new work (1954) is $1,650,000
for construction (Federal) and $265,000 for lands and damages
 (non-Federal).
   Local cooperation. The plan of improvement and the require-
ments of cooperation were first discussed at a meeting with local
interests on May 18, 1948. The project was approved by the city
council on May 21, 1948, and bonds were subsequently voted for
financing the city's share of the project costs. Formal assurances
of cooperation were attested by an instrument executed by the
city of Barbourville on August 13, 1953, and accepted by the
Corps of Engineers on September 9, 1953. Preliminary work in
connection with title evidence, appraisals, and optioning prereq-
uisite to acquisition of necessary lands and rights-of-way has
been initiated.
   Operations and results during fiscal year. Definite design
studies on all features of the project except pumping plants were
completed. The preparation of plans and specifications was initi-
ated and brought to a stage which will permit contracting for the
first unit of construction as scheduled early in the fiscal year 1955.
Unit I embraces 6,885 feet of levee and related drainage facilities,
including pumping plant outlets, beginning at a point about 50 feet
downstream from the Walker Park (Kentucky Highway No. 459)
Bridge across Richland Creek, then following the creek and main
stream to the tie-in with the railroad embankment southeast of
town. The costs during the year for new work were $42,178.
   Condition at end of fiscal year. Engineering and design were
40 percent complete.
   The total costs to June 30, 1954, were $55,530 for new work.

                                     Cost an d financial summar!l


                                              Fiscal year ending June 30                          Total to June:
                                                                                                 30, 1954, includ-
                                                                                                 ing fiscal years
                              1950           1951         1952       1953          1954            priorto 1950


New work:
   Appropriated                                                      $25,000       $40,000              1$65, 000
   Cost-----..------------            --   --------- -----------      13,352        42,178                 55,530

1 Includes $10,000 transferred from Carthage, Cumberland River, Tenn., project during fiscal year 1954.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-------_ -                                     $9,470
    Appropriated for succeeding fiscal year ending June 30, 1955------ -                               350,000
    Unobligated balances available for succeeding fiscal year ending June
              ----------
      30, 1955__              -----------------      ------------------                                359,470
      Estimated additional amount needed to be appropriated for comple-
        tion of existing project_-                                             -             -      1,235,000
           FLOOD CONTROL-NASHVILLE, TENN., DISTRICT              899
     7. WOLF CREEK RESERVOIR,        OHIO RIVER BASIN, KY.
   Location. The site of the Wolf Creek Dam is on the Cumber-
land River, 460.9 miles above its mouth. It is in Russell County,
Ky., and is about 10 miles southwest of Jamestown, Ky., and 12
miles north of Albany, Ky. Wolf Creek Reservoir extends 101
miles up the mainstream, 48 miles up the South Fork of Cumber-
land River, and lies within Russell, Clinton, Wayne, Pulaski,
McCreary, Laurel, and Whitley Counties, Ky.
   Existing project. The plan of improvement provided for the
construction of a combination earth and concrete gravity-type
dam, 5,736 feet long and 258 feet in height above its lowest foun-
dation; and a hydroelectric power generating plant. The dam con-
sists of a rolled earth embankment section extending 3,940 feet
from the right abutment across the flood plain portion of the val-
ley, and a concrete structure, 1,796 feet in length, comprised of
spillway, power intake, and adjacent nonoverflow sections, con-
necting the embankment with the left abutment. The spillway
contains 6 gate-controlled conduits and is surmounted with 10
tainter crest gates to provide for regulating and discharging flood
flows. The powerhouse, a reinforced concrete structure of the
conventional indoor type, is located directly at the downstream
base of the power intake sectibn of the dam through which six
penstocks were constructed. The power installation consists of
six 45,000 kilowatt generating units. The project is one unit of a
coordinated plan for the control of floods and the development of
the water resources of the Cumberland River Basin, this plan in
turn forming an integral part of the comprehensive plan of devel-
opment for the Ohio and Mississippi Rivers. At maximum con-
trolled pool level, top of spillway crest gates, the reservoir covers
an area of 63,530 acres and provides a storage capacity of 6,089,000
acre-feet, of which 2,094,000 is allocated for flood control and 2,-
142,000 for power drawdown, leaving a minimum pool of 1,853,000
acre-feet available at all times for public use and conservation
purposes. The drainage area controlled is 5,810 square miles or
approximately one-third of the Cumberland River Basin. The
project was selected for construction under the general authoriza-
tion for the Ohio River Basin contained in the Flood Control Act
approved June 28, 1938, and the additional authorization contained
in the River and Harbor Act approved July 24, 1946. The current
 (1954) estimated cost of the project, including the six-unit power
installation, is $79,278,000. The estimate of annual cost for oper-
ation and maintenance of the project (1954) is $440,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. New work: A con-
tract covering installation of terminal facilities for an additional
transmission line was initiated and completed during the year, the
required plans and specifications having been prepared by hired
labor. Real estate activities included legal action in connection
with pending condemnation cases; investigation of lands affected
by flows from maximum power production, which may necessitate
acquisition of additional easements; negotiations regarding dam-
ages to county roads below the dam; and action to acquire flowage
900       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

easements over 5,341 acres of land from another Government
agency.
    Operation and maintenance: The dam was operated and the
structures and appurtenances maintained as required. Operation
of the power plant was continuous except for normal interruptions
and necessary shutdowns for inspection and maintenance pur-
poses. Under existing regulations, the total net energy generated
  (445,626,000 kilowatt-hours) was made available through the De-
partment of the Interior to the Tennessee Valley Authority for
distribution.
    Regulation of the reservoir during the year was limited to re-
leases for the generation of power, with a maximum release for
this purpose of 21,200 cubic feet per second. The average pool ele-
vation was 699.8 feet, which is 23.2 feet below the spillway crest
level. Reservoir storage varied from a minimum of 1,892,000
acre-feet on January 14, 1954, corresponding to a pool elevation of
674.1 feet, to a maximum of 3,626,000 acre-feet on May 3, 1954,
corresponding to elevation 715.5. During the occurrence of a flood
in the latter part of January, the combined effect of this project
and the Dale Hollow and Center Reservoirs resulted in computed
crest reductions on the Cumberland River of 18.3, 25.6, 9.1, and 8.7
feet at Celina, Carthage, Nashville, and Clarksville, Tenn., respec-
tively. During the drought experienced in the latter part of 1953,
releases from the project, together with those from Dale Hollow
and Center Hill Reservoirs, provided sufficient flow in the Cumber-
land River to meet the minimum requirements for water supply,
pollution abatement, and navigation. In this connection, the mini-
mum monthly average flow at Nashville, which would have been a
record low of 300 cubic feet per second under natural conditions,
was increased to 2,500 cubic feet per second.
    Activities under the reservoir management program, comprising
shoreline sanitation, malaria control, conservation, land manage-
ment and disposal, and operation and maintenance of public use
facilities, were continued.
    The costs were $563,524, of which $258,345 was for new work
and $305,179 for operation and maintenance.
    Condition at end of fiscal year. The project as a whole was 99
percent complete. Construction of right and left bank access roads
and the provision of a temporary construction camp at the project
site for Government inspection personnel were completed during
early stages of the project. Work under the original contract for
construction of the dam and appurtenant works was begun in
August 1941, but was terminated in 1943 in interest of the war
effort, when only about 8 percent complete. Under a new con-
tinuing contract awarded for completion of the dam, work was com-
menced in September 1946 and completed in August 1951. Closure
of the dam was effected in December 1950, at which time the proj-
ect was placed in operation for flood control. The powerplant was
constructed during the period November 1949-March 1953, with
the six power units being placed in operation on the following
dates: October 6, 1951; October 31, 1951; December 16, 1951;
March 17, 1952; July 24, 1952; and August 22. 1952.
  Reservoir operations including mapping (731 square miles),
                  FLOOD CONTROL-NASHVILLE, TENN., DISTRICT                                             901
clearing (48,775 acres), removal and salvage of improvements
(91,475 acres), and necessary relocations have been completed.
Acquisition has been completed on 92,833 acres in fee simple and
584 acres in easement. Disposal action has been completed on 64
acres in fee to the Cincinnati Southern Railway, and on 114 acres
in easement to the Commonwealth of Kentucky.
   Total costs to June 30, 1954, were $79,378,238, of which $78,-
500,212 was for new work and $878,026 for operation and mainte-
nance. In addition, surplus property valued at $34,432 was trans-
ferred to the project without reimbursement.
                                        Cost and financial summary

                                              Fiscal year ending June 30                      Total to June
                                                                                             30, 1954, includ-
                                                                                             ing fiscal years
                                 1950        1951         1952          1953       1954        prior to 1950


New work:
     Appropriated .... _    $15,030, 700 $22,000,000   $2,000,000   -$2;040,000                  $78,837,824
     Cost            ..      3......
                             17,184,702   14,203,729    7,445,666     1,386,018   $258,345       178, 500,212
Maintenance:
     Appropriated-     _     -               117,000      254,000      231,400     311,900           914,300
     Cost ...                                 71,034      213,044      288,769     305,179           878,026

I   In addition, surplus property valued at $34,432 was transferred to the project without reimbursement.

Other new work data:
   Unobligated balance, fiscal year ending June 30, 1954 __           _   $326,334
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955-_        - --     neede toaprpite               -oplto      326,334
    Estimated additional amount needed to be appropriated for completion
      of existing project_     -                                   -       440,200

8. DALE HOLLOW RESERVOIR, OHIO RIVER BASIN, TENN. AND KY.
   Location. Dale Hollow Dam is located on the Obey River 7.3
miles above its confluence with the Cumberland River (mile 380.9)
at Celina, Tenn. It is in Clay County, Tenn.,;and is about 80 miles
northeast of Nashville, Tenn., 28 miles north of Cookeville, Tenn.,
13 miles west of Byrdstown, Tenn., and 3 miles east of Celina,
Tenn. Dale Hollow Reservoir extends about 51 miles up the main
stream, 10 miles up the East Fork, and 6 miles up the West Fork of
Obey River, and lies within Cumberland and Clinton Counties, Ky.,
and Clay, Pickett, Overton, and Fentress Counties, Tenn.
   Existing project. The plan of improvement provided for con-
struction of a concrete gravity-type dam, 1,717 feet long and 200
feet in height above its lowest foundation; and a hydroelectric
power generating plant. The dam consists of spillway and power
intake sections across the flood plain portion of the valley width,
flanked by nonoverflow transition sections terminating in the abut-
ments. Four gate-controlled conduits through the base of the
spillway section and six tainter crest gates provide for regulating
and discharging flood flows. The powerhouse, a reinforced concrete
structure of the conventional indoor type, is located directly at the
downstream base of the power intake section of the dam through
which three penstocks were constructed. The power installation
consists of three 18,000-kilowatt generating units. The project is
one unit of a coordinated plan for the control of floods and the
development of the water resources of the Cumberland River
902      REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

Basin, this plan in turn forming an integral part of the compre-
hensive plan of development for the Ohio and Mississippi Rivers.
At maximum controlled pool level, top of spillway crest gates, the
reservoir covers an area of 30,990 acres and provides a storage
capacity of 1,706,000 acre-feet of which 353,000 is allocated for
flood control and 496,000 for power drawdown, leaving a minimum
pool of 857,000 acre-feet available at all times for public use and
conservation purposes. The drainage area controlled is 935 square
miles or 99 percent of the Obey River Basin. The project was
selected for construction under the general authorization for the
Ohio River Basin contained in the Flood Control Act approved
June 28, 1938, and the additional authorization contained in the
River and Harbor Act approved July 24, 1946. The estimated cost
 (1954) of the project, including the three-unit power installation,
is $25,961,000. The current (1954) estimate of annual cost for
operation and maintenance of the project is $300,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. New work (con-
tract): Operations incident to installation of the third and final
power unit were completed, including work under all supply con-
tracts for equipment furnished by the Government.
   New work (hired labor): Hired labor operations involved com-
pletion of final real estate audit and accomplishment of remaining
work in connection with installation of reservoir regulation and
hydrologic network.
   Operation and maintenance: The dam was operated and the
structure and its appurtenances maintained as required. Opera-
tion of the powerplant (two units) was continuous during the year
except for normal interruptions and necessary shutdowns for in-
spection and maintenance purposes. The third generator unit was
placed on the line in November 1953. Under existing regulations,
the total net energy generated (70,473,000 kilowatt-hours) was
made available through the Department of the Interior to the Ten-
nessee Valley Authority for distribution.
   Regulation of the reservoir during the year was limited to re-
leases for the generation of power, with a maximum release for
this purpose of 5,700 cubic feet per second. The average pool ele-
vation was 639.8 feet, which is 11.2 feet below the spillway crest
level. Reservoir storage varied from a minimum of 859,000 acre-
feet on January 9, 1954, corresponding to a pool elevation of 631.1
feet, to a maximum of 1,233,000 acre-feet on May 3, 1954, cor-
responding to elevation 646.5. During the occurrence of a flood
in the latter part of January, the combined effect of this project
and the Wolf Creek and Center Hill Reservoirs resulted in com-
puted crest reductions on the Cumberland River of 18.3, 25.6, 9.1,
and 8.7 feet at Celina, Carthage, Nashville, and Clarksville, Tenn.,
respectively. During the drought experienced in the latter part
of 1953, releases from the project, together with those from Wolf
Creek and Center Hill Reservoirs, provided sufficient flow in the
Cumberland River to meet the minimum requirements for water
supply, pollution abatement, and navigation. In this connection,
the minimum monthly average flow at Nashville, which would have
                  FLOOD CONTROL-NASHVILLE, TENN., DISTRICT                                                                903

been a record low of 300 cubic feet per second under natural con-
ditions, was increased to 2,500 cubic feet per second.
   Activities under the reservoir management program, comprising
shoreline sanitation, malaria control, conservation, land manage-
ment and disposal, and operation and maintenance of public use
facilities were continued.
  The costs were $636,287, of which $408,870 was for new work
and $227,417 for operation and maintenance.
   Condition at end of fiscal year. The project as a whole, includ-
ing the third and final power unit, was 99 percent complete. Work
under the contract for construction of the dam and its appur-
tenances was initiated in March 1942, and final closure of the dam
was effected in October 1943, at which time the project was placed
in operation for flood control. The powerplant, with two 18,000
kilowatt generating units (initial development) in commercial
operation, was completed in April 1949. Generating units Nos. 1
and 2 were placed on the line December 18, 1948, and January 26,
1949, respectively. Installation of the third and final generating
unit (initiated in March 1952) was completed during the year, with
the unit having been placed in commercial operation on November
17, 1953. Work under all supply contracts for component parts
and necessary accessory equipment for the third unit has been
completed.
   All lands required for project purposes, totaling 52,496 acres,
have been acquired; comprising 52,405 acres in fee simple, 89 acres
of flowage easements, and 2 acres of road easements. Reservoir
operations including mapping (258 square miles), clearing (17,168
acres), removal and salvage of improvements, relocations, and
development of management and public use facilities have been
completed. Construction of relocated Tennessee Highway No. 42
Bridge, removal of 6 highway bridges, relocation of 2,293 graves,
and clearing of 10,179 acres of the reservoir area were accom-
plished by contract.
   The total costs to June 30, 1954, were $27,326,038, of which
$25,869,488 was for new work and $1,456,550 for operation and
maintenance. In addition, surplus property valued at $28,029 was
transferred to the project without reimbursement.
                                           Cost and financial summary

                                                      Fiscal year ending June 30                           Totaf to June
                                                                                                          30, 1954, includ-
                                                                                                          Ing fiscal years
                                    1950             1951        1952          1953        1954 :          prior to 1950


New work:
   Appropriated--
    >Cost-__---
Maintenance:
                          -----
                       _------
                                   $570, 000 ----------
                                    238, 373        $253,597
                                                                $500, 000
                                                                 516, 730
                                                                            $1,292,100
                                                                             1, 108, 431
                                                                                           $40,000
                                                                                           408, 870
                                                                                                              $251961,100
                                                                                                              125;   S,    488

   Appropriated     -----           221,800          255,400     241,000       230, 700    224,100               1,485,100
   Cost ..-
         -    - - - - - -- -        220,821          213, 070    233,233       250, 645    227, 417            2 1,-456, 550


1In   addition, surplus property valued at $27,908 was transferred to the project without reimbursevnent.
2 In addition, surplus property valued at $121 was transferred to the project without reimbursemett.

Other new work-data:
    Unobligated balance, fiscal year ending June 30, 1954:-                                           -        $91,517
       Unobligated balanices available for succeeding fiscal year ending June 30,
         1955                  -               --                                                                91,517
904      REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

   9. CENTER HILL     RESERVOIR,     OHIO   RIVER BASIN,     TENN.
   Location. The site of the Center Hill Dam is on the Caney Fork
River, 26.6 miles above its confluence with the Cumberland River
 (mile 309.2) at Carthage, Tenn. It is in DeKalb County, Tenn.,
and is about 55 miles east of Nashville, Tenn., 30 miles north of
McMinnville, Tenn., 20 miles west of Cookeville, Tenn., and 14 miles
southeast of Carthage, Tenn. Center Hill Reservoir extends about
64 miles up the main stream and about 10 miles up Falling Water
River and lies within DeKalb, Putnam, White, and Warren Coun-
ties, Tenn.
   Existing project. The plan of improvement provided for con-
struction of a combination earth and concrete gravity-type dam,
2,160 feet long and 250 feet in height above its lowest foundation;
and a hydroelectric power generating plant. The dam consists of a
rolled earth embankment section extending 778 feet from the left
abutment across the flood plain portion of the valley, and a con-
crete structure, 1,382 feet in length, comprised of spillway, power
intake, and adjacent nonoverflow sections, connecting the embank-
ment with the right abutment. The spillway contains six gate-
controlled conduits and is surmounted with eight tainter crest
gates to provide for regulating and discharging flood flows. In
addition to the main dam structure, the project provided for con-
struction of a rolled earth dike, 770 feet in length, to close a saddle
in the reservoir rim on the right bank near the dam site. The
powerhouse, a reinforced concrete structure of the conventional
indoor type, is located directly at the downstream base of the power
intake section of the dam through which three penstocks were
constructed. The power installation consists of three 45,000 kilo-
watt generating units. The project is one unit of a coordinated
plan for the control of floods and the development of the water
resources of the Cumberland River Basin, this plan in turn forming
an integral part of the comprehensive plan of the development for
the Ohio and Mississippi Rivers. At maximum controlled pool
level, top of spillway crest gates, the reservoir covers an area of
23,060 acres and provides a storage capacity of 2,092,000 acre-feet,
of which 762,000 is allocated for flood control and 492,000 for power
drawdown, leaving a minimum pool of 838,000 acre-feet available
at all times for public use and conservation purposes. The drainage
area controlled is 2,195 square miles, or approximately four-fifths
of the Caney Fork River Basin. The project was selected for con-
struction under the general authorization for the Ohio River Basin
contained in the Flood Control Act approved June 28, 1938 and the
additional authorization contained in the River and Harbor Act
approved July 24, 1946. The (1954) estimated cost of the project,
including the three-unit power installation, is $44,240,000. The
 (1954) estimate of annual cost for operation and maintenance of
the project is $345,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. New work (con-
tract): Under an agreement entered into with the State of Ten-
nessee for a connecting access road from U. S. Highway No. 70N
          FLOOD CONTROL-NASHVILLE, TENN., DISTRICT              905
to the roadway across the dam, the State prepared necessary plans
and specifications and essentially completed construction.
   New work (hired labor) : Construction consisted of replacing an
unsatisfactory item of powerplant control equipment. Real estate
activities were continued with legal action being taken in connec-
tion with pending condemnation cases.
   Operation and maintenance: The dam was operated and the
structure and its appurtenances maintained as required. Opera-
tion of the powerplant was continuous except for normal interrup-
tions and a few periods of short duration for inspection and main-
tenance purposes. Under existing regulations, the total net energy
generated (306,231,000 kilowatt-hours) was made available
through the Department of the Interior to the Tennessee Valley
Authority for distribution.
   Activities under the reservoir management program, comprising
shoreline sanitation, malaria control, conservation, land manage-
ment and disposal, and operation and maintenance of public use
facilities were continued.
   Regulation of the reservoir during the year was limited to re-
leases for the generation of power, except during the period Janu-
ary 25-31, 1954, when flood control releases were made to empty
the flood control portion of the reservoir. The maximum release
occurred on January 25, 1954, and totaled 29,100 cubic feet per
second. A minimum flow of zero obtained when the powerplant
was not in operation. The average'pool elevation was 637.3 feet,
which is 10.7 feet below the spillway crest level. Reservoir storage
varied from a minimum of 839,000 acre-feet on January 13, 1954,
corresponding to a pool elevation of 618.1 feet, to a maximum of
1,446,000 acre-feet on January 25, 1954, corresponding to elevation
654.3. During the occurrence of a flood in the latter part of Janu-
ary, the combined effect of this project and the Wolf Creek and
Dale Hollow Reservoirs resulted in computed crest reductions on
the Cumberland River of 18.3, 25.6, 9.1, and 8.7 feet at Celina,
Carthage, Nashville, and Clarksville, Tenn., respectively. During
the drought experienced in the latter part of 1953, releases from
the project, together with those from Wolf Creek and Dale Hollow
Reservoirs, provided sufficient flow in the Cumberland River to
meet the minimum requirements for water supply, pollution abate-
ment, and navigation. In this connection, the minimum monthly
average flow at Nashville, which would have been a record low of
300 cubic feet per second under natural conditions, was increased
to 2,500 cubic feet per second.
   The costs were $445,982, of which $217,614 was for new work
and $228,368 for operation and maintenance.
   Conditionat end of fiscal year. The project as a whole was 99
percent complete. Work under the contract for construction of
the dam, appurtenant works, and access roads was begun in March
1942, but was suspended in March 1943 in interest of the war effort,
when about 40 percent complete. Operations were resumed in
January 1946. Closure of the dam was effected in November 1948,
at which time the project was placed in operation for flood control.
Work under the prime contract as modified to include construction
of the powerplant was completed in November 1951. Generator
906            REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

units Nos. 1, 2, and 3 were put in service commercially on Dec~in-
ber 11, 1950, January 17, and April 11, 1951, respectively.
   Work under agreement with and contracted for by the State of
Tennessee for a connecting access road from U. S. Highway No.
70N to the roadway across the dam was approximately 90 percent
complete.
   Reservoir operations, including mapping (178 square miles),
clearing (15,850 acres), removal and salvage of improvements,
cemetery removals, and relocation of Tennessee State Highway
Nos. 26 (Sligo) and 56 bridges, have been completed. All neces-
sary reservoir lands have been acquired; 37,744 acres having been
obtained in fee simple, 87 acres in road and flowage easements, and
829 acres by transfer from another Government agency. In addi-
tion, a total of 427 acres of land situated below the dam has been
approved for acquisition in easement because of damages incurred
from project operation. Of this amount, 334 acres have been ac-
quired. Disposal action on transfer of 79 acres in road easements
to the State of Tennessee has been completed.
   Total costs to June 30, 1954, were $44,913,981, of which $43,-
951,740 was for new work and $962,241 for operation and main-
tenance. In addition, surplus property valued at $51,285 was
transferred to the project without reimbursement.
                                    Cost andfinancial summary

                                                 Fiscal year ending June 30                       Total to June
                                                                                                 30, 1954, includ-
                                                                                                 ing fiscal years
                             1950            1951         1952         1953            1954        prior to1950

New work:
   Appropriated ....      $6, 300,000    $6, 260,000 _                $239, 000   -    -             $44,237,700
   Cost                    9---------------
                           9,390, 556      3, 848, 683   $472,242      113, 679       $217,454       1 43, 951,   740
Maintenance:
   Appropriated - -_ .-       65, 400        244,300      210,000      234, 100        2070300            981, 100
   Cost------.    -           66,602         174,178      224,441      249,857         228,368            962,241


i In addition, surplus property valued at $51,285 was transferred to the project without reimbursement.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_-----------     $183,808
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955____________             __------------------------------    183,808

      10. OHIO RIVER BASIN, NASHVILLE,                                   TENN., DISTRICT:
   Location. The works covered by this project are a series of
levees, flood walls, channel improvements, and reservoirs in the
Ohio River Basin within the confines of the Nashville, Tenn., dis-
trict.
   Existing project. The Flood Control Act approved June 28,
1938, approved the general comprehensive plans for flood control
and other purposes in the Ohio River Basin as set forth in House
Flood Control Committee Document No. 1, 75th Congress, 1st ses-
sion, with such modification thereof as, in the discretion of the
Secretary of War and the Chief of Engineers, may be advisable,
and for initiation and partial accomplishment of the plan, author-
ized $75,000,000 for reservoirs and $50,300,000 for the local flood
protection works, the individual projects to be selected and approved
                        FLOOD CONTROL-NASHVILLE, TENN., DISTRICT                                                                   907
by the Chief of Engineers subject to the provision that the author-
ization shall include the diversion of Cache River above Cairo, Ill.,
and the protection of the area north of Cairo drainage district by
levees, at an estimated cost of $2,000,000.
   In addition to previous authorizations, the Flood Control Acts
approved August 18, 1941, December 22, 1944, July 24, 1946, and
May 17, 1950, authorized sums of $45,000,000, $70,000,000, $125,-
000,000, and $100,000,000, respectively, for the further prosecution
of the comprehensive plan for the Ohio River Basin approved in
the act of June 28, 1938, as amended and supplemented by the sub-
sequent acts of Congress.
   The following is a list of the individual projects considered in the
comprehensive plan within the confines of the Nashville, Tenn.,
district:
                                                   Local protection projects

                                                                                                        Estimated costs

                          Location                             Type of protection
                                                                                              Federal          Non-Fed-         Total
                                                                                                                 eral

Middlesboro (Yellow Creek), Ky.'                     __----------Levees ------------            $581, 000       $161, 000       $742, 000


                                                             Reservoirs


           Tributary basin and reservoir                                              Stream                                Total esti-
                                                                                                                        mated cost

                      CUMBERLAND

Center Hill, Tenn.2_                   2 - - - - - - - .----------------------
                                                       -- -- -- - Caney Fork     River.......---------------       _        $44, 240, 000
Dale Hollow, Tenn. and Ky.                            Obey River---------------------------                                  25, 961, 000
Rossview Tenn. and Ky-----------------.....           Red River -------------------------- ___-                              12, 5690,000
Stewarts Ferry, Tenn. ................---             Stones River ...------------------------                               23, 400, 000
Three Islands, Tenn
                2   ..............                    Harpeth     River
                                          .....--------------------     ..------------------------                           19, 900, 000
Wolf Creek, Ky. ............................                   Cumberland River            ....---------------------         79, 278, 000


  I For last full report, see annual report for 1949.
  2 Details of this project are given in individual report.
  3 For last full report, see annual Report for 1953.


   Operations and results during fiscal year. No costs were in-
curred.
   Condition at end of fiscal year. The status of Wolf Creek, Dale
Hollow, and Center Hill Reservoirs, selected for construction under
this authorization, is given in individual reports.
   With the completion of definite project plans in fiscal year 1949,
further work on the Middlesboro (Yellow Creek), Ky., local pro-
tection project was deferred pending action with respect to local
cooperation. The city of Middlesboro passed an order at a regular
council meeting on January 14, 1946, pledging fulfillment of the
required conditions, but has taken no additional steps toward fur-
therance of the project.
   Engineering and design for Stewarts Ferry Reservoir were dis-
continued in fiscal year 1953, when about 40 percent complete,
pending restudy of the plan of improvement in the light of changed
conditions.
908            REPORT OF CHIEF OF. ENGINEERS, U                                   S. ARMY, 1954

   Advance planning for Three Islands and Rossview Reservoirs,
the remaining projects considered in the comprehensive plan with-
in the Nashville District, also has been suspended in lieu of more
urgent work. Detailed plans previously developed for both proj-
ects are subject to certain supplementary studies and investiga-
tions, and consequent revisions, to reflect current conditions and
engineering practices. Mapping of the reservoir area (213 square
miles), reservoir area-capacity determinations, and additional
foundation investigation work for further site analysis studies in-
cident to revision of the Three Islands project plans have been
completed.
   The total costs to June 30, 1954, were at $518,212.
                                        Cost and financial summary
                                              CONSOLIDATED


                                                  Fiscal year ending June 30                             Total to June
                                                                                                        30, 1954, includ-
                                                                                                        ing fiscal years
                                 1950         1951            1952          1953             1954          prior to 1950

New work:
   Appropriate d -     -.....    $80, 000    $274, 000     -$209,300     -$148,840    -                              $518,212
   Cost_. -                       54,976       12,772             ,539          659    -                              518,212



                     11. INACTIVE            FLOOD 'CONTROL PROJECTS

                                                          For last        Cost to June 30, 1954              Estimated
                                                         full report                                          amount
                 Name of project                             see                                              required
                                                          annual           Con-            Operation                 to
                                                           report        struction            and            complete
                                                           for-                           maintenance
Chattanooga, T enn.,
                   2 -
                       and Rossville, G a.'   -   - -
                                                            1949           $180, 997 -                      __f---
Cumberland, K y. .. _.........              ... .           1952            ..      .. _     ....     ..
                                                                                                    .___              $89, 000
Snagging and c learing under authority of see-              1953             24, 748 _                               (3)
tion 2 of the F lood Control Act, Aug. 28, 1937,
as amended

  a Local interests having failed to meet the requirements of cooperation, authority for the project expired
December 31, 1953.
  2 Lower priority project.
  S No further work currently scheduled.



                                12. GENERAL INVESTIGATIONS
   Examinations and surveys. The costs and expenditures during
the year were $4,886. The balance unexpended ($868) and ac-
counts receivable ($3) on June 30, 1954, plus allotments for the
fiscal year 1955 of $3,000 for examinations and surveys and an
anticipated allotment of $3,000 for collection and study of basic
data, a total of $6,871, will be applied to the preparation of one
flood control study and the collection and study of basic data.
   The additional sum of $46,100 can be profitably expended for
scheduled work under this heading during the fiscal year 1956 for
work to be accomplished under this heading.
   Collection and study of basic data. The collection and study of
basic data during fiscal year 1954 consisted of the following: col-
lection of rain and stream flow data and revision of Flood Emer-
gency Manual.
                 FLOOD CONTROL--NASHVILLE, TENN., DISTRICT                                    909
13. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
   Flood control emergencies---Repairand flood fighting and rescue
work. (Section 210 of the 1950 Flood Control Act and supple-
mental authorizations.)
   In addition to previous allotments, totaling $26,466 for emer-
gency flood-control work pursuant to this authority within the
Nashville district, funds in the amount of $2,418 were allotted dur-
ing the fiscal year ending June 30, 1954, for reimbursement of ex-
penses incurred by the district in connection with protection of
Corps of Engineers property at Cheatham lock and dam and liaison
with local agencies and municipalities during the flood experienced
in the Cumberland River basin in January 1954.
   Total costs to June 30, 1954, were $28,884.
                                      Cost and financial summary

                                            Fiscal year ending June 30              Total to June
                                                                                   30, 1954, includ-
                                                                                   ing fiscal years
                              1950         1951        1952        1953   1954       prior to 1950

Maintenance:
   Appropriated .......        $5,1        $11,433                        $2,418            $28,884
   Cost--...---------------     5,2         11,433                         2,418             28,884
      IMPROVEMENT OF RIVERS AND HARBORS IN THE
               LOUISVILLE, KY., DISTRICT

  This district comprises a portion of southwestern Ohio, west cen-
tral Kentucky, a small portion of north central Tennessee, all of
Indiana except the northern part and southeastern Illinois except
the Cairo-Mounds-Mound City area, all included in the drainage
basin of the Ohio River and its tributaries (exclusive of the Ten-
nessee and Cumberland Rivers) from mile 409.3 (below Pitts-
burgh) immediately downstream from Aberdeen, Ohio, to the
mouth.
                                                    IM   [PROV]EMENTS

                        Navigation                                              Flood Control-Continued
                                                           Page                                                               Page
  1. Locks and dams 34 to 39, 41,                     15. Cannelton, Ohio River Basin%
       and 43 to 53, Ohio River........          911        Ind .........                 ................. ...               932
2. Ohio River open channel work                 911 16. Rough River Reservoir and
                                                 911
3. Kentucky River, Ky.................. channel improvement, Ky....                                                          933
4. Green, Barren, and Nolin                         17. Vincennes, Ohio River Basin,
       Rivers and Bear Creek, Ky....            914         Ind-............................... ...                           935
5. Inactive navigation projects.....           919   18. Brevoort Levee, Wabash River
                                                            Basin, Ind.................. .....                                936
                     Flood Control                   19. Cagles Mill Reservoir, Ohio
                                                919         River Basin, Ind......................                            937
6. Newport, Ohio River Basin, Ky
7. Covington,           Ohio River Basin,           20. New Harmony Bridge, Ohio
       Ky............................................
                                                920         River Basin, Ill. and Ind._..                                     938
8. Cincinnati, Ohio River Basin,                    21. Rosiclare, Ill-----------...................-..                      939
               . ........................ 922 22. Paducah, Ohio River Basin, Ky
       Ohio ....                                                                                                              940
9. West Fork of Mill Creek Reser-                   23. Reevesville, Ohio River Basin,
      voir, Ohio River Basin, Ohio..            924         Ill.........               ............... ....................   941
10. Jackson, Ohio River Basin, Ky               925 24. Ohio River Basin, Louisville,
11. Jeffersonville-Clarksville, Ohio                        Ky., District.................                                    .943
       River Basin, Ind ................        926 25. Inactive flood control projects .                                     947
12. Louisville, Ohio River.Basin,                                                                                             947
      Ky..............................               26. General investigations .......... ._
                                                927
13. New Albany, Ohio River Basin,                    27. Inspection of completed proj-
      Ind ........     .....   .....
                                   .....
                                      ..... ... 930
                                         .....              ects....................................-----------------         948
14. Hawesville, Ohio River Basin,                    28. Flood control work under spe-
      Ky .........................       .........
                                       ....     931         cial authorization . ..............                               948

    1. LOCKS AND DAMS 34 TO 39, 41 AND 43 TO 53, OHIO RIVER
    For report on this improvement, see page 869.
                       2.    OHIO         RIVER,           OPEN          CHANNEL WORK
    For report on this improvement, see page 875.
                                        3. KENTUCKY RIVER, KY.
   Location. The Kentucky River is formed by the confluence of
its North and Middle Forks about 4 miles east of the town of
Beattyville in east central Kentucky, the South Fork joining the
main stream at that place, and flows in a general northwesterly
direction 258.6 miles and empties into the Ohio River at Carroll-
                                                                                                                  911
912      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

ton, Ky., mile 545.8 below Pittsburgh, Pa. (See U. S. Geological
Survey Chart for State of Kentucky; scale, 1:500,000.)
   Existing project. The project provides for 14 locks and fixed
dams to give in connection with the improvement of the Ohio
River, slack water navigation of 6 feet minimum depth from the
Ohio River to points on the three forks a short distance above
Beattyville, Ky. The length of the 6-foot-depth project on the
main system of the Kentucky River is 258.6 miles to the conflu-
ence of the Middle and North Forks.' The river frequently rises to
a height of 35 feet or more. Extreme flood height at lock 1 due to
backwater from Ohio River when in flood is 60.3 feet, while ex-
treme floods reach a height of 47.6 feet at lock 4, and 35.5 feet at
lock 14. At some intermediate locks the extreme height of floods
exceeds 40 feet. All flood heights are referred to upper pool gages.
   The cost of new work for the completed project, which contem-
plated the rehabilitation of the 5 State locks and dams and the
extension of slack water to the three forks at Beattyville, was
$4,176,749. The estimate of annual cost of operation and mainte-
nance of the Kentucky River (1953) is $397,000. The estimate of
annual cost of operation and maintenance of the Kentucky River
 (1954) is $351,000 of which $291,000 is for operating and care of
locks and dams and $60,000 for channel work.
   The existing project was adopted by the River and Harbor Act
of March 3, 1879, in accordance with the report published in House
Executive Document 47, 45th Congress, 3d Session (Annual Re-
port, 1879, p. 1398). Operation and care of the locks and dams
were included in the project July 1, 1935, under the provisions of
the Permanent Appropriation Repeal Act, approved June 26, 1934.
No project map of the river has been published.
   The following statement shows the characteristics of the several
locks and dams in this project:
              RIVERS AND HARBORS--LOUISVILLE, KY., DISTRICT                                                      913

                                            Lock

                Location                        Dimensions

                                              Great-
Dam                                              est                                        When
                                              avail-            Depth                        com-           Cost
                                                able      Lift    on      Foundation        pleted
                                 Miles Clear length        of   lower
         Nearest town            from width (full        lock miter
                                 mouth (feet) width      (feet)   sill
                                                 of             (feet)
                                              lock)
                                               (feet)

 ' 1   Carrollton, Ky.....         4. 0    38      145     8. 2   14. 8   Rock and clay_ 2 1882
12    Lockport, Ky-....          31. 0    38      145    13. 9    6. 1 Rock-------
                                                                                  ........--1882
13    Gest, Ky----------... .    42.0     38      145    13.2     6.5 .....   do .     ... 1882        3   $1, 350, 385
14    Frankfort, Ky _-_          65. 0    38      145    13.2     6.3 .....   do,_ ..-. 1882
15    Lawrenceburg, Ky_          82. 2    38      145    15. 0             .... ......
                                                                   6. 4 I _do                  1886 J
16    Versailles, Ky-.....       96. 2    52      147    14.0     6.4   R o c k and          1894             314, 847
                                                                           piles.
17    High Bridge, Ky.__        117. 0    52      147   15.3      6. 8   Rock___ -...        1897             290, 768
18    Nicholasville, Ky__       139.9     52      146   18.7      6. 0 .....  do             1900             275, 463
  9    Valley View, Ky.._        157. 5    52      148   17. 3     6. 6 _      do ......      1903             237, 646
10    Richmond, Ky.....         176. 4    52      148   17.0      6.0 _       do         .1904                221, 500
11    College Hill, Ky._        201.0     52      148   18. 0     6. 0 ..-. do       ..      1906             296, 593
12    Ravenna, Ky- ....         220.9     52      148 6 18. 0     6. 0 -do
                                                                          .         ---       1910             425, 693
13    Willow, Ky-.. ..          239. 9    52      148   16. 0     7. ... do            .. 1915                461, 476
514   Heidelberg, Ky ..         249.0     52      148 718. 0     77.0 .       do.. .         1917             392, 902

1 Fixed dam, crib construction.
   Date reconstruction was completed by United States.
S Built by the State of Kentucky. Cost is given for repairs by United States only.
4 Fixed dam, concrete construction.
5 Fixed dam, concrete construction, movable crest.
6 With nhovable wooden crest in operation on lock 12.
7 With movable wooden crest in operation on lock 13.


   Terminal facilities. Tanks for receiving gasoline are located
at or near Carrollton, Frankfort and Camp Nelson, Ky. Ter-
minals for loading coal are located at Beattyville and Heidelberg,
Ky., and for unloading coal at Clays Ferry, Ford, and Carrollton,
Ky. There is a stone loading terminal at Boonesboro, Ky. and ter-
minals for receiving sand and gravel at Frankfort and Carrollton,
Ky.
   Operations and results during fiscal year. Work during the
fiscal year consisted of the operation and maintenance of the 14
locks and dams, and the removal of shoals, snags, and slides, as
required to maintain an adequate channel for existing traffic be-
tween the mouth of the river and Beattyville, Ky., in the pool of
Dam No. 14.
   The costs were $188,612 for operation and ordinary maintenance
of locks and dams and $24,253 for rehabilitation of channels in
pools of dams, a total of $212,865, all from regular funds.
   Condition at end of fiscal year. The existing project was com-
pleted in 1917. The work accomplished under the project has been
the rehabilitation of the five old State locks and dams and the con-
struction of new locks and dams Nos. 6 to 14, inclusive. The year
of completion of the various locks and dams is given in the table in
the varagraph "Existing project."
914            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   The canalization system on the Kentucky River is in only fair
condition. The condition of the concrete-capped, stone-filled timber
crib dams at locks 1 to 8, inclusive, varies from fair to poor, and
the limestone walls at locks 1 to 6, inclusive, and lock No. 8 are
wearing away by erosion. The remaining locks and dams, Nos. 9 to
14, inclusive, are of concrete construction and the masonry is gen-
erally in good condition. The controlling navigable depth in the
section covered by the existing project was 6 feet at the end of the
fiscal year.
   All locks were staffed with two employees each for the lockage
of the limited amount of commercial traffic using the river. Oper-
ation of locks 8-14, inclusive, subsequent to June 30, 1955, is con-
tingent on the development of sufficient commercial traffic in this
reach of waterway to justify the continued maintenance of naviga-
tion facilities at Federal expense.
   The costs to the end of the fiscal year were as follows:

                                                         Regular            Maintenance and                 Total
                                                                              operation funds


New work ..-.------------------------------                $4, 176, 749 --------------------                  $4, 176, 749
Operation and maintenance, general _......                  3, 711, 620                      $51, 000          3, 762, 620
      Total .....                                           7, 888, 369                     51, 000             7, 939, 369



  In addition, the sum of $6,405,372 was expended between July 5,
1884, and June 30, 1937, on the operation and care of the works of
improvement under the provisions of the permanent indefinite ap-
propriation for such purposes.
                                       Cost and financial summary

                                                Fiscal year ending June 30                                Total to June
                                                                                                         30, 1954, includ-
                                                                                                         ing fiscal years
                                1950          1951           1952             1953              1954       prior to 1950


New work:
    Appropriated ------ _-- ..             -------------- -------- ------------ ------------                   $4,176,749
    Cost-..--       ---                        ---            -----                                             4, 176, 749
Maintenance:
   Appropriated     -          $257, 700     $329, 853     $206,400         $300, 750        $244, 704         10, 229, 922
   Cost                         286, 650      298, 611      194,662          331, 419        1217,151          10,167, 991


   1 Includes undistributed costs June 30, 1953, distributed to features in fiscal year 1954 $4, 286, not reported
as this fiscal year costs on PB12.


4. GREEN, BARREN, AND NOLIN RIVERS, AND BEAR CREEK, KY.
  Location. Green River rises in Casey County, Ky., flows in a
northwesterly direction 370 miles, and empties into the Ohio River
about 8 miles above Evansville, Ind.
  Barren River rises in Monroe County, Ky., flows in a north-
         RIVERS AND HARBORS--LOUISVILLE,      KY., DISTRICT      915
westerly direction 130 miles, and empties into Green River one-
half mile above lock 4 and 149.5 miles above the mouth of Green
River.
   Bear Creek rises in Grayson County, Ky., flows in a southerly
direction 40 miles, and empties into Green River 0.3 mile above new
lock 5 and 168.4 miles above the mouth of Green River.
   Nolin River rises in Larue County, Ky., flows in a southwesterly
direction about 105 miles, and empties into the Green River 1.8
miles above lock 6 and 183.5 miles above the mouth of Green River.
   Existing project. This provides for locks and dams Nos. 1
through 6 on the Green River, lock and dam No. 1 on the Barren
River and for the improvement of Nolin River and Bear Creek by
the removal of obstructions.
   The original authorization provided for the purchase of improve-
ments made prior to 1884, by the State of Kentucky, consisting of
locks and dams 1 to 4, Green River, and 1, Barren River, which
gave a continuous 4-foot depth for navigation from Bowling Green,
on the Barren River, to the mouth of Green River. Subsequent
authorizations provided for the reconstruction of lock 2, Green
River (in 1893) ; the upstream extension of slack water navigation
on Green River to Mammoth Cave, Ky., by the construction of
locks and dams 5 and 6, and by the removal of snags and slides;
the construction of new locks at dam 1, Barren River, and at dam
5, Green River; the raising of the crest of dam 5, Green River, 2
feet, by means of a movable A-frame top; the improvement of
Nolin River by the removal of obstructive bars, boulders, over-
hanging rocks, and snags; and the improvement of Bear Creek by
removing snags and widening bends. The reconstruction of dam
2, Green River; and the construction of new and larger locks at
dams 1 and 2, Green River, was approved on July 29, 1953, by the
Secretary of the Army under authority of Section 6 of River and
Harbor Act of March 3, 1909.
   The project for Green River extends from the mouth to Mam-
moth Cave, Ky., a distance of 197.8 miles; for Barren River from
the mouth to Bowling Green, Ky., a distance of 30.1 miles; for
Nolin River from the mouth to Meredith Ferry, a distance of 73/4
miles and for Bear Creek, Ky., for a distance of 8 miles above its
mouth. The navigable depth of the improved portions is limited to
5.5 feet by the elevations of the existing lock miter sills.
   Fluctuations in stage vary considerably at the different locks.
At lock 3, Green River, ordinary fluctuations due to high stages are
from 12 to 15 feet above the pool level, and at lock 1, Barren River,
from 7 to 10 feet above pool. The maximum stages of record are
34 feet above normal pool stage at lock 3, Green River, and 29 feet
at lock 1, Barren River. These stages were obtained during the
floods of 1937 and 1913, respectively.
   The principal data concerning the locks and dams are shown in
the following table:
916                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


                      Location                                                                                         Depth             Depth
                                                                                 Greatest                           on lower            on upper
                                                                                 length                                miter              miter
                                                  Distance                       of lock                               sill at            sill at
                                                    from          Width of      available        Lift at              normal             normal
  Lock                                            mouth of          lock         for full        normal                 pool               pool
  and                                               river         chamber         width           pool                 level               level
  dam             Nearest town                     (miles)          (feet)        (feet)          (feet)               (feet)             (feet)


                  GREEN RIVER

         1      Spottsville, Ky.....                    9. 1           35. 5          139. 0          111.8                    9. 0            6. 7
New 1    7-.......do_____..........                     9,1            84. 0          600, 0          111.8                   11, 3           12.1
    2     Rumsey, Ky_ .....                            63. 1           36. O0         141.0            14.3                    5. 5            7. 8
New 2 8__.......do ...........                         63.1            84.0           600. 0           14.3                   11.7            15.0
    3     Rochester, Ky          -_                   108. 5           35. 8          137. 5           17. 0                   5. 6            7. 3
    4     Woodbury, Ky_..                             149. 0           35. 8          138. 0           16. 4                   6. 5            7.1
New 5     Glenmore, Ky_...                            168. 1           56. 0          360. 0           15. 2                   9. 3           12. 0
    6     Brownsville, Ky._.                          181.7            36.0           145. 0            9. 2                   8. 8            8.0

                  BARREN RIVER

     1          Greencastle, Ky_      -.              2   15. 0        56. 0          360. 0           15. 2                  9. 3            12.1)0


   Lock                Character of                        Kind                   Type of                         Year                Cost of lock
and dam               foundation                         of dam                construction                    completed              and dam
                                                                                    -----                     I -----------      I           ---
                       GREEN RIVER
    1...... Shale and coal....... Fixed.....                          Wood crib, concrete cap-....               1835-40               $179, 110.00
New 1 ..........do..___           ---- do...                           - d o -..........     ...........            (7)
            Shale ....... .......                                     Wood.cribh- ....-------                      1895
New 2 s.... -.. do ... .._ ...... S-----do
                                         ..-.                         Concrete masonry-.........                     (8)
            Rock.........._....   .....do . -                         Wood crib .................                1833-36                121,377. 00
                  .....do .........                      ...
                                                      .....  do-_.    ... do ..        ...                         1839
                                                                                                    ..----------------                  125, 718.00
New 5_......       Piles and rock..               _    -=-   do _do---Concrete masonry- .... __-                   1934 4             1.020, 867. 89
                   Gravel--.-..-   ..                                 Wood crib, concrete cap ---    ,             1905                 168, 415.00

                      BARREN RIVER
     1 ......
     1......       Gravel                                              -
                                                                      .-     do -. -----         .    .-- -           1841             *871, +55.00
                   Piles in gravel         -..-                                                                       1934
                        -        --- --                --
1At normal pool dam 48, Ohio River.
2 Distance from mouth of Green River is 164.5 miles.
a With movable A-frame crest 3 feet high.
   Includes $4,033.50 for purchase of land.
SDoes not include $179,434.58, cost of old lock and dam 5.
8 Includes $729,269 for the new large lock completed in 1934, of which $1,800 was for purchase: of
                                                                                                  chad.
7 New lock under construction.
8 New lock and dam under construction.


   The estimated cost of new work in Green and Barren Rivers
 (1954) is $12,856,540; of new work in Nolin River, $15,000; and of
new work in Bear Creek, $23,000, of which $10,000 is to be eon-
tributed by local interests; a total of $12,894,540.
   The estimate of annual cost of operation and maintenance of
existing facilities on the Green River between the mouth of the
Green River and Bowling Green on the Barren River (1954) is
$167,500, of which $107,500 is for operating and care of locks and
dams Nos. 1-4 Green River and No. 1, Barren River, and $60,000
for channel work.
                  RIVERS AND HARBORS-LOUISVILLE, KY.,: DISTRICT                                                   917
       Acts                            Work authorized                                          Documents
Aug. 11,1888      Purchase of the original improvements.....------------........   H     Ex. Doc. 111, 49th Cong., 2d
                                                                                    sess; Annual Report 1887, p. 1903.
Mar. 3,1893 1 Construction of lock 2, Green River..--------------...............   Annual Report, 1891, p. 2439.
July 13 1892      Construction of lock 5, Green River..................
July 13 1902      Construction of lock 6, Green River..................            Annual Report, 1891, p. 2478.
Mar.     3,1905   Appropriation of $5,000 made for continuing the im-
                   provement of Green River above the mouth of Big
                    Barren River, with the following proviso: "That
                    the Secretary of War may, in his discretion, expend
                    such portion of said amount as may be necessary
                    for removal of snags in Nolin River."
Mar. 3,1909       Construction of new lock No. 1 and new lock and                  Senate Doc. No. 82, 83rd Congress,
                   dam No. 2, Green River.                                           2d session.
July    3, 1930   Constructionoftnew locks at dam 5, Green River, and              Rivers and Harbors Committee
                   dam 1, Barren River; modification of dam 5, Green                 Doc. 2, 71st Cong., 1st sess., and
                       River, widening of bends in Bear Creek, Ky.                     H. Doc. 685, 69th Cong., 2d sess.
June 26, 1934 2 Operation and care of locks and dams with War De-
                    partment appropriations for rivers and harbors.
Aug. 80,1935      Improvement of Nolin River        ----
                                                  ---------------                  H. Doc. 480, 72d Cong., 2d sess. s

1   Deficiency act.
2 Permanent Appropriations Repeal Act.
s Contains latest published map of the lower 12 miles of Nolin River. For map of the Green, Barren,
Rough and Nolin Rivers and Bear Creek, see Senate Doc. No. 82, 83d Congress, 2d session.


   Recommended modifications of project. Modification of the
project to provide for widening and deepening the navigable chan-
nel in the lower 103 miles of Green River to provide a width of 200
feet and a depth of 9 feet, and guide fenders and cells at restricted
bridge openings for navigation safety, at an estimated cost to the
United States of $3,358,000 for construction, $50,000 for aids to
navigation and $25,000 for additional annual operation and main-
tenance, is recommended in report on "Green and Barren Rivers,
Kentucky," published in Senate Doc. No. 82, 83d Congress, 2d sess.
This report also recommends that existing authorities for the im-
provement of Bear Creek, and for the removal of obstructions on
Nolin River, be revoked.
   Local cooperation. The River and Harbor Act of July 3, 1930,
provides that in connection with the improvement of Bear Creek,
Ky., local interests are to contribute $10,000 to the first cost of the
dredging, provide necessary rights-of-way at the bends, furnish
without cost to the United States satisfactory areas for the dis-
posal of excavated material, and assume all flowage damages along
Bear Creek. These conditions have not been met.
   The River and Harbor Act of August 30, 1935, provides that
local interests provide any land or easements required for the pur-
pose of the improvement of Nolin River. Local interests: have been
unable to obtain easements required for the removal of overhang-
ing rock ledges at Whistle Mountain.
   Terminal facilities. There are two terminals for receiving
gasoline on the Barren River at Bowling Green, Ky., and one on
the Green River at South Carrollton, Ky., and one terminal for
loading crude oil on the Green River at Spottsville, Ky. There is
one terminal for loading coal at Paradise, Ky. (near Rockport)
and one terminal for receiving coal at the Kentucky Utilities power
plant at South Carrollton, Ky.
   Operations and results during fiscal year. New work: Work
during the fiscal year consisted of preparation of plans and speci-
fications for reconstruction of Lock No. 1 and Lock and Dam No. 2,
purchase of lands for the new structures at both sites, and initia-
918             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

tion of contract reconstruction of Lock No. 1 in June 1954. A con-
tract was awarded in June 1954 for reconstruction of Lock and
Dam No. 2, however, no work thereon had been started by the end
of the fiscal year.
   Operation and maintenance, general: Work during the fiscal year
consisted of completion of design memorandum for the proposed
new lock No. 1 and lock and dam No. 2, Green River; the operation
and maintenance of locks and dams Nos. 1 to 4, Green River and
No. 1, Barren River; and the removal of shoals, snags and slides
as required to maintain an adequate channel for existing traffic
between the mouth of the Green River and Bowling Green, Ky.
   The costs during the fiscal year were as follows:
        New work:
          Engineering and design, and land acquisition
            expense for new lock 1 and new lock and
            dam 2, Green River ......................                                                       $ 80,363
        Operation and maintenance, general:
          Completion of design memorandum. $100,000
          Operation of locks and dams.......             71,682
         Channel work ...................              100,009                                               271,691
              Total, all from regular funds ............                                                    $352,054

   Condition at end of fiscal year. The canalization system on the
Green and Barren Rivers is in only fair condition, except lock 1,
Barren River, and lock and dam 5, Green River, which are in good
condition. The controlling navigable depth in the section of river
between Bowling Green, Ky., and the mouth of Green River was
5.5 feet at the end of the fiscal year. Operation of locks Nos. 5 and
6, Green River, was discontinued on August 1, 1951, as these locks
were no longer used by commercial traffic. At the end of the fiscal
year work had been initiated on the construction by contract of
new lock No. 1, Green River, and a contract had been awarded for
the construction of new lock and dam No. 2, Green River.
   New work remaining to be done consists of the removal of over-
hanging rock ledges at Whistle Mountain on Nolin River, provided
for by the River and Harbor Act of August 30, 1935; the improve-
ment of Bear Creek, provided by the River and Harbor Act of
July 3, 1930; and the construction of replacement lock No. 1, and
lock aiid dam No. 2'. The costs to the end of the fiscal year were
as follows:

                                                        Maintenance            Public        Emergency
                                      Regular           and operation          works           relief         Total
                                                             funds             funds           funds


New work------------------..           $2, 440,132 -----------.........---       $85, 000 .............. $2, 525,132
Operation and maintenance,
General.-----------------              2,120, 734              $19, 000 ---       -------        $2, 000           734
                                                                                                              2, 1411;
      Total ----               ..--------...
                                         4, 560, 866                000
                                                                  19,             85,000           2,000      4, 666,866


    In addition, the~:              im of $3,842,667 was expended between 1888
and June 30, 1934, on the operating and care of the works of im-
                    RIVERS AND HARBORS-LOUISVILLE, KY., DISTRICT                                                                   919
provement under provisions of the permanent indefinite appro-
priation for such purposes.
                                                   Cost and financial summary

                                                           Fiscal year ending June 30                                     Total to June
                                                                                                                         30, 1954, includ-
                                                                                                                         ing fiscal years
                                            1950         1951              1952              1953           1954          priorto 1950


New work:
      Appropriated------------                                        ----------------------               $840, 000          $3, 284,769
      Cost------------------------------------                                    -   -                      80,363            2,525,132
Maintenance:
      Appropriated     .- -               $193,800     $153,237            $81,600          $108,500        272, 200            5,994,248
      Cost_-------------                   183,478      108, 057           133,491           106, 712     1 276,767             5,984,401


  I Reported cost for fiscal year 1954 includes cost of $5, 076 incurred in fiscal year 1953 and carried in clearing
account June 30, 1953.

Other new work data.
    Unobligated balance, fiscal year ending June 30, 1954_ ------------- $135,655
   Appropriated for succeeding fiscal year ending June 30, 1955 ------. 4,800,000
    Unobligated balances available for succeeding fiscal year ending June
            30, 1955_                      _ - _ __-                                                                        4,935,655
        Estimated additional amount needed to be appropriated for comple-
          tion of existing project-_-_---------------------               4,420,000

                                 5. INACTIVE NAVIGATION PROJECTS

                                                                       For last            Cost to June 30, 1954             Estimated
                                                                      full report,                                            amount
                        Name of project                                   see                                                 required
                                                                       annual                Con-        Operation              to
                                                                       report             struction         and              complete
                                                                        for--                           maintenance
1. Licking River, Ky ......-----------------------
                           2- - - - - - - - - - - - - - - - - - - -      1901                $13, 045   ..----------------------
2. Tradewater River, Ky. -                                               1941                 18, 568          $7, 571 Completed.
3. White River, Ind. ----------------------
                                         __                 ___          1909                119, 312                      D--------------
                                                                                                                            Do.
4. Clearing navigable streams under authority                            1951                                  12, 131     Do.
     of Public Law 14, 79th Cong.
5. Rough River, Ky.2--------------------------                           1952                105, 500         101, 196          Do.


     1 Recommended for abandonment in H. Doc. 467, 69th Cong., 1st seas.
     -No commerce reported.
                               6. NEWPORT, OHIO RIVER BASIN, KY.
   Location. In Campbell County, Ky., on the left bank of the
Ohio River and the right bank of the Licking River at their con-
fluence, 470 miles below Pittsburgh, Pa.
   Existing project. The plan of improvement provides for the
construction of 8,000 feet of earth levee, 1,805 feet of concrete
wall, 2,435 feet of cellular-type steel sheet piling wall, three pump-
ing plants, and other necessary appurtenances. The line of pro-
tection begins at high ground near the east end of Lexington Ave-
nue, extends in a northwesterly direction to the left bank of the
Ohio River, thence downstream to the mouth of the Licking River
and upstream along the right bank of Licking River to high ground
in the vicinity of Lowell and 12th Streets. The section along Lick-
ing River from Chestnut Street to Hodge Street is cellular-type
steel sheet piling wall and the section from Hodge Street to Lowell
and 12th Streets is concrete wall.
      The project provides protection for the city of Newport, Ky.,
920              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

against Ohio River and Licking River floods equal to the 1937 flood
 (maximum of record) with a 3-foot freeboard.
   The estimated cost of the project (1954) is $7,251,000; the actual
non-Federal cost is $299,000.
   The existing project has been selected for construction under
the general authorization for the Ohio River Basin contained in
the Flood Control Act approved June 28, 1938.
   Local cooperation. Fully complied with.
   Operations and results during fiscal year. Work consisted of
making modification and repairs to the cellular-type steel sheet
piling wall, sewers, etc. Routine maintenance of the project was
performed by local interests. There was no flood during the year
which required operation of the project.
   The costs during the fiscal year were $95,225 for new work.
   Condition at end of fiscal year. Construction of the project was
started in April 1946 and completed June 1954 except for the modi-
fications and repairs which were completed in August 1953. The
project was assigned to local interests for maintenance on Septem-
ber 29, 1951.
   The total costs to the end of the fiscal year were $7,130,076 from
regular funds and $6,150 from Emergency Relief funds, a total of
$7,136,226, all for new work.
                                           Cost and financial summary

                                                 Fiscal year ending June 30                    Total to June
                                                                                              I 30, 1954, includ-
                                                                                                ing fiscal years
                                    1950        1951            1952    1953        1954        priorto 19501


New work:
   Appropriated          .       $2, 200,000   $333,000   ---   ----    200,000   ---------          $7,200,351
   Cost-.------- -----       -    2,646,980    859, 672     $272,2601   320,629   2$109,416           7,136, 226

  I Includes $6,150 Emergency Relief funds.
  2   Difference between current fiscal year costs reported in column 1954 and those reported in "Operation
and results during fiscal year" is as follows: fiscal year 1953 undistributed costs distributed to features
in fiscal year 1954, $14,191.16.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954--............. $64,125
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955-------------------------------------------------                   64,125
    Estimated additional amount needed to be appropriated for completion
      of existing project_                                                    50,649

                      7. COVINGTON,               OHIO RIVER BASIN, KY.
   Location. In Kenton County, Ky., on the left bank of the Ohio
River and the left bank of the Licking River at their confluence,
470.5 miles below Pittsburgh, Pa.
   Existing project. The plan of improvement provides for the
construction of 2,390 feet of earth levee and 3,580 feet of concrete
wall along the Ohio River; 8,370 feet of earth levee and 1,220 feet
of concrete wall along the Licking River; 10 pumping plants; and
other necessary appurtenances. The Ohio River section begins
near Second and Wright Streets, extends along the left bank of the
river on or near Second Street to Washington Street, then north-
            FLOOD CONTROL--LOUISVILLE, KY., DISTRICT               921
east to Riverside Drive, paralleling Riverside Drive on the south
side to Greenup Street, thence along the west side of this street in
a southerly direction to high ground. The Licking River section
begins about 300 feet east of Eighth and Garrard Streets, parallels
this latter street and Prospect Street at a distance of about 300 feet
on the riverside to 12th Street, thence parallel to Maryland Street
on the riverside for 800 feet, thence in a southerly direction paral-
lel and adjacent to the left bank of Licking River to a point near
Oakland Street 500 feet south of Wallace Avenue, thence about 300
feet west to high ground. This section also includes about 900 feet
of earth levee on Eastern Avenue between Wallace Avenue and
26th Street, and about 300 feet of concrete wall to protect Booth
Hospital in the vicinity of Kennedy and Third Streets. The project
will provide protection for the city of Covington, Ky., against Ohio
and Licking River floods equal to the 1937 flood (maximum of rec-
ord) with a 3-foot freeboard.
    The (1954) estimated Federal cost of the project is $7,550,000;
the estimated non-Federal cost is $765,000.
    The existing project has been selected for construction under the
general authorization for the Ohio River Basin contained in the
Flood Control Act approved June 28, 1938.
    Local cooperation. Bond issue to cover rights-of-way and
damage costs were voted on November 6, 1945. Formal assur-
ances of local cooperation were adopted on November 29, 1945,
by the board of commissioners of the city of Covington and ap-
proved September 26, 1947. Rights-of-way have been acquired
necessary for construction work, except for ponding area at
Willow Run pumping plant. The rights-of-way for outlets of
ponding area at 24th Street pumping plant is presently being
acquired.
    The funds contributed for joint design, engineering studies, and
construction of sewer facilities along Licking River totaled $265,-
124. This work is beyond the scope of the authorized Federal
project.
    Operations and results during fiscal year.. Construction was
continued on section C by continuing-contract; on the five pumping
plants along Licking River by continuing-contract; and, coordina-
tion of sewers and pumping facilities under contract with sanita-
tion district No. 1 of Campbell and Kenton Counties, Ky.
    The costs during the fiscal year were $1,910,593 from regular
funds and $172,938 from contributed funds, a total of $2,083,531,
all for new work.
    Condition at end of fiscal year. Construction of project was
started in July 1948 and was 85 percent complete at the end of the
fiscal year. The construction of sections A and B, Russell Street,
Main Street, and Willow Run pumping plants is complete including
dehumidification of these plants. Construction of section C is 90
percent complete, and of Court, Kennedy, Pleasant, 19th and 24th
Streets pumping plants is 62 percent complete. Contract with San-
itation District No. 1 of Campbell and Kenton Counties, Ky., which
includes the construction of sewers and the 8th Street and Patton
Street pumping plants, is reported to be about 80 percent complete.
The work remaining to be done consists of completion of construc-
922             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

tion of section C, the five pumping plants along Licking River and
8th Street and Patton Street pumping plants.
   The total costs to the end of the fiscal year were $6,419,375 from
regular funds, $7,454 from Emergency Relief funds, and $265,124
from contributed funds, a total of $6,691,953, all for new work.
                                     Cost and financial summary

                                              Fiscal year ending June 30                            Total to June
                                                                                                   30, 1954, includ-
                                                                                                   ing fiscal years
                              1950           1951          1952          1953          1954         priorto 19501

New work:
    Appropriated           $1, 041, 700     $890, 000   $1, 400, 000    $821, 000   $1, 100, 000         $6, 720, 154
    Cost- ---        -        969,445      1, 278,044       196, 468   1,185, 995    1, 910, 593          6,426, 829

  1 Includes $7,454 Emergency Relief funds.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-_----------     $126,703
    Appropriated for succeeding fiscal year ending June 30, 1955------- 800,000
    Unobligated balances available for succeeding fiscal year ending June
                                                                                                   -
      30, 1955 ---------------------------------------------               926,703
    Estimated additional amount needed to be appropriated for completion
      of existing project ---------------------------------------           29840

                                          CONTRIBUTED FUNDS


                                              Fiscal year ending June 30                            Total to June
                                                                                                   30, 1954, includ-
                                                                                                   ing fiscal years
                              1950           1951          1952          1953          1954          priorto 1950


New work:
   Appropriated ........                                               $246, 262       $60, 000            $306, 262
   Cost.--                                                               92,186        172,938              265,124


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_               - - $41,138
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955__    _______ _                                               __    41.138

                    8. CINCINNATI,            OHIO RIVER BASIN, OHIO

   Location. The project is located in the city of Cincinnati on
the right bank of the Ohio River, in Hamilton County, Ohio, 472.5
miles below Pittsburgh, Pa.
   Existing project. The project consists of a barrier dam across
Mill Creek near its mouth, and a concrete wall, with appurtenant
works, extending from the east bank of the creek along the Ohio
River to high ground near the intersection of Baymiller and Ken-
yon Streets. The project protects Mill Creek Valley and a small
portion of the river front section of Cincinnati against Ohio River
floods of 1937 magnitude (maximum of record) with a 3-foot free-
board. The barrier dam includes a pumping installation to dispose
of discharges of Mill Creek (drainage area 165 square miles) into
the Ohio River during flood periods. The entire project involved
the construction of a barrier-dam pumphouse including pumps, mo-
tors and all necessary electrical and other mechanical equipment;
appropriate outlet works to pass Mill Creek discharges during nor-
                   FLOOD CONTROL-LOUISVILLE, KY., DISTRICT                                              923
mal periods; 600 feet of levee and 820 feet of wall between the
western abutment of the dam and pumphouse; and about 5,660 lin-
ear feet of concrete wall to form the eastern closure of the dam.
The project also provides gates, drainage-disposal facilities, and
other appurtenant works.
   The estimated Federal cost of the project (1953) is $9,977,800;
the estimated non-Federal cost is $1,027,600.
   The project was selected for construction under the general au-
thorization for the Ohio River Basin contained in the Flood Control
Act approved June 28, 1938.
   Local cooperation. All requirements have been fulfilled. Dur-
ing the fiscal year 1945, modifications of the Evans Street sewer
were performed with funds in the amount of $10,693 furnished by
the city of Cincinnati. During fiscal years 1947 and 1948, funds
in the amounts of $174,283 and $6,874, respectively, were supplied
by the city of Cincinnati for sewer modifications near Carr Street
and relocation of traffic gates. This work is beyond the scope of
the authorized Federal project.
   The funds furnished were in excess of total expenditures for this
work by an amount of $20,123, which has been returned to the city.
   Operations and results during fiscal year. The work performed
during the fiscal year consisted of installing electric tape gages and
starting the preparation of operations and maintenance manual.
Routine maintenance of the project was accomplished by local in-
terests. There was no flood during the year which required opera-
tion of the project.
   The costs during the fiscal year were $156 from regular funds for
new work.
   Condition at end of fiscal year. Construction of the levees,
walls and the barrier dam was complete. Six pumping units were
in operating condition in the barrier-dam pumping station. The
project is complete except for completion of the operations and
maintenance manual.
   The total Federal costs to the end of the fiscal year were $9,955,-
057 from regular funds and $9,360 from Emergency Relief funds,
a total of $9,964,417. In addition, surplus property valued at $19,-
959 was transferred to the project without reimbursement.

                                     Cost and financial summary

                                               Fiscal year ending June 30                    Total to June
                                         _   ______30,                                         1954, includ-
                                                                                             ing fiscal years
                              1950           .1951         1952       1953         1954      prior to 19501 2


New work:
   Appropriated- ..-----     $650, 000                   -$27,100     $22, 100                   2 $9,977, 760
   Cost----------------       816,365         $9,551         2,362     29,0981 .     $1566        39,964, 417
1In addition $171,727 for new work was expended from contributed funds.
2Includes $9,360 Emergency Relief funds and $650,000 from appropriation 21X3113.010 flood control
general refund to the City of Cincinnati, repayment of funds advanced.
  3 In addition, surplus property valued at $19,959 was transferred to the project without reimbursement.

Other new work data.:
    Unobligated balance, fiscal year ending June 30, 1954                                           $4,343
     Unobligated balances available for succeeding fiscal year ending June 30,
       1955                                                                                           4,343
924       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

9. WEST FORK OF MILL CREEK RESERVOIR, OHIO RIVER BASIN,
                         OHIO
    Location. The site of the West Fork of Mill Creek Dam is on
the west fork of Mill Creek 6.5 miles above its junction with Mill
Creek and 2 miles northeast of Mount Healthy, Ohio, and about 10
miles north of downtown Cincinnati. The reservoir will extend up-
stream about 3 miles and all lies within Hamilton County, Ohio.
    Existing project. The plan of improvement provides for the
construction of a dam for flood control, recreation, and reduction
of pumping requirements at the Mill Creek barrier dam. The dam
consists of an earth embankment with a maximum height of about
100 feet and a total length of 1,100 feet. The improvement in-
cludes a gate-controlled concrete conduit 10.5 feet in diameter un-
der the embankment along the right abutment and an uncontrolled
spillway through the right abutment ridge, and appurtenant work.
A permanent pool at elevation 675 having an area of 183 acres is
provided. The storage between elevations 675 and 702 amounting
to 9,850 acre-feet, which is equivalent to 6.3 inches of runoff from
the 29.5 square miles of drainage area above the dam, will be re-
served for flood control and reduction of pumping requirements at
the Mill Creek barrier dam.
    The estimated Federal cost of the project (1953) is $2,981,700;
the estimated non-Federal cost is $570,801 which amount includes
$50,000 contributed in fulfillment of project authorization. The
estimated annual cost for operation and maintenance of the project
 (1953) is $26,700.
    The latest published map is contained in House Document No.
198, 80th Congress, 1st session.
    The existing project was selected for construction under the ad-
ditional authorization for the Ohio River Basin contained in the
Flood Control Act approved July 24, 1946.
    Local cooperation. Local interests are required to release
necessary land under their control at no cost to the United States
and give assurances that they will prevent future channel en-
croachment below the dam site in connection with the flood con-
trol reservoir. In case the reservoir is enlarged to include a con-
servation pool, local interest must contribute one-half the addi-
tional cost of such pool, including one-half of the cost of relocation
of sanitary sewer, and agree to hold and save the United States
free from damages resulting from its provision. The board of
county commissioners of Hamilton County, Ohio, adopted a reso-
lution on October 8, 1947, signifying willingness to fulfill local co-
operation requirements including the provision of the conservation
pool. Assurances of local cooperation were executed on the same
date. A contract with the United States for the relocation of the
sanitary sewer outside the reservoir area in order to include the
conservation pool in the project has been accepted by Hamilton
County, in which the United States pays one-half the cost of such
relocation work.
   The amount of $50,000, required as a local contribution toward
the additional cost of providing the conservation pool, has been
furnished by the Hamilton County Commissioners.
  The Hamilton County Park District has undertaken the devel-
                         FLOOD CONTROL--LOUISVILLE, KY., DISTRICT                                                             925
opment and management of recreation facilities in the reservoir
area for use of the public in accordance with license granted by
the Secretary of the Army on October 31, 1951.
   Operations and results during fiscal year. A contract was
awarded and completed for provision of additional facilities. In-
stallation of miscellaneous operating equipment was performed by
hired labor. Preparation of the operations and maintenance man-
ual and master plan for recreation was completed. Routine oper-
ation and maintenance was performed during the fiscal year.
   The costs during the year were $61,681 for new work and
$21,446 for operation and maintenance.
   Condition at end of fiscal year. Construction of the project
was started in March 1949 and completed in December 1952 except
for minor items of work. The work remaining at the end of the
fiscal year consists of water service connection and other miscel-
laneous minor items of work.
   The total costs for new work to the end of the fiscal year were
$2,945,256 from regular funds and $50,000 from contributed funds,
a total of $2,995,256.
   The total costs for operation and maintenance to the end of fiscal
year were $37,981.
                                               Cost and financial summary

                                                                Fiscal year ending June 30                           Total to June
                                                                        _ _ _1_ _    _    _      _   _          -   30, 1954, includ-
                                                                                                                    ing fiscal
                                                                                                                            years
                                        1950                  1951             1952       1953           1954        prior to 19501


New work:
   Appropriated .....-                $1,041,700            $900,000 -$400,000           -$60,000                         $2,981,700
   Cost..                                648,644             699,458    599,339            794,680          681
                                                                                                         $61,              2,945,256
Maintenance:
   Appropriated -           -!_____                  I.-----------       ...
                                                                         !__      -
                                                                                __---.     19,000         24,840              43,840
   Cost-- .-----------     ----                ---             --    -   -----.            16,535         21,446              37,981


1 In addition, $50,000 fornew work was expended from contributed funds.
Other new work data:
     Unobligated balance, fiscal year ending June 30, 1954__                                                        - -   $34,316
     Utnobligated balances available for succeeding fiscal year ending June 30,
         1955 .                   -                                                                                        34,316

                          10. JACKSON, OHIO RIVER BASIN, KY.
   Location. In Breathitt County on the North Fork of the Ken-
tucky River, 305 miles above the Ohio River.
   Existing project. The project consists of excavation of a cut-
off channel across the neck of an ox-bow bend. The new channel
has a length of about 150 feet, a base width of 200 feet and a depth
of about 60 feet. It will shorten the stream length by about 4.25
miles and will reduce flood heights at Jackson, Ky., from 4 to 6
feet on all floods, resulting in the elimination of 75 percent of the
flood damages now sustained by the city:
   The estimated Federal cost of the project (1954) is $260,000, the
non-Federal cost is $3,000.
   The project was selected for construction under the additional
authorization for Ohio River Basin contained in the Flood Control
Act approved December 22, 1944.
   Local cooperation. Officials of Jackson, Ky., have adopted a
926           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

resolution giving assurances of local cooperation.
   Operations and results during fiscal year. There was no work
done during the year due to no available funds.
   Condition at end of fiscal year. Work on surveys, explorations
and preparation of plans is 9 percent complete. The total costs to
the end of the fiscal year were $1,880. The total expenditures
were $1,880.
                                      Cost and financial summary

                                                Fiscal yea       ending June 30               Total to June
                                                                                             30, 1954, includ-
                                                                                             ing fiscal years
                               1950         1951                1952       1953       1954     priorto 1950

New work:
   Appropriated.....------------            -$3, 100             -$20                                  $1, 880
   Cost...-----------------        $30   .....    ...--------       67                                  1,880


Other new work data:
    Appropriated for succeeding fiscal year ending June 30, 1955--------      12,000
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955------------------------------------------------------_             12,000
    Estimated additional amount needed to be appropriated for completion
      of existing project           -------------------------------------- 246,120

11. JEFFERSONVILLE-CLARKSVILLE,                                       OHIO       RIVER BASIN, IND.
   Location. The Jeffersonville-Clarksville area is located in Clark
County, Ind., on the right bank of the Ohio River, 603 miles below
Pittsburgh, Pa.
   Existing project. The plan of improvement provides for the
construction of a system of levees and concrete flood walls, con-
sisting of the following features: Section I, an earth levee 19,630
feet in length, including 7,030 feet of roadway levee and 12,600
feet of new earth levee, extending from high ground near Silver
Creek and Emery Crossing Road along the right bank of the Ohio
River to the foot of Smyser Avenue in Clarksville; section II, unit
1, 8,810 feet of concrete wall extending along the right bank of
the Ohio River from near the foot of Penn Street downstream to
the vicinity of Smyser Avenue to join with section I; section II,
unit 2b, 450 feet of concrete wall and 1,540 feet of new earth levee
extending from high ground near Jefferson and High Streets to
join unit 1 near Penn Street; section II, unit 2a, 5,570 feet of new
earth levee across low ground northeast of Jeffersonville; 10
pumping plants for the disposal of interior drainage, and ap-
purtenant works.
   The project provides protection for the adjoining municipalities
of Jeffersonville, Clarksville, and Claysburg, and approximately
3.8 square miles of contiguous agricultural and suburban areas
against Ohio River floods equal to the flood of 1937 (maximum of
record) with a 3-foot freeboard.
   The estimated cost of the project (1954) is $4,196,600 of which
an amount not exceeding $166,320 may be applied to lands and
damages; the estimated non-Federal cost is $590,888.
   The existing project has been selected for construction under the
general authorization for the Ohio River Basin contained in the
                   FLOOD CONTROL-LOUISVILLE, KY., DISTRICT                                             927
Flood Control Act approved June 28, 1938.
   Local cooperation. On March 15, 1940, the President approved
a waiver of 36 percent of the estimated cost of lands, easements
and rights-of-way, under the provisions of section 8 of the Flood
Control Act approved August 11, 1939. Fully complied with.
   Operationsand results during fiscal year. The dehumidification
test was continued and completed including preparation and sub-
mission of report. Final settlement made of contract for construc-
tion of east section pumping plants. Prototype test on syphonic
action is awaiting suitable river conditions for completion. There
was no flood during the year which required operation of the
project.
   The costs during the fiscal year were $3,195 for new work.
   Condition at end of fiscal year. Construction of the project was
started in July 1940 and substantially completed in October 1949.
The project has been assigned to local interests for maintenance
and operation. The work remaining consists of completion of
studies for prototype test on syphonic action.
   The total costs to the end of the fiscal year were $4,182,512 from
regular funds and $3,953 from Emergency Relief funds, a total of
$4,186,465, all for new work.
                                      Cost and financial summary

                                               Fiscal year ending June 30                    Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                               1950        1951         1952         1953     1954           prior to 19501

New work:
   Appropriated     -        -$25, 000    -$7, 500       $6, 500                        -         $4, 190, 407
   Cost..                -    122,416         1, 301      1,464     :$1,663    $3,195              44 86,465

IIncludes   $3,953 Emergency Relief funds.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-_-----------        $3,942
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955-----           --------------------------------------------         3,942
    Estimated additional amount needed to be appropriated for completion
      of existing project------- ---------------------------                   6,193

                   12. LOUISVILLE, OHIO RIVER BASIN, KY.
   Location. Louisville is located in Jefferson County, Ky., on the
left bank of the Ohio River, 607 miles below Pittsburgh, Pa.
   Existing project. The plan of improvement provides for the
construction of a system of levees and concrete flood walls consist-
ing of the following features: Section A, including 941 feet of
earth levee and 9,313 feet of concrete wall, extending from high
ground northeast of the intersection of Brownsboro Road and
Mellwood Avenue downstream across Beargrass Creek in a west-
erly direction to high ground near the intersection of Preston and
Main Streets; section AA, including 3,500 feet of concrete wall,
extending from the intersection of Preston and Main Streets north
and west of industrial and commercial developments to high
ground at Third and Main Streets; section B, including 6,052 feet


      Sig 30--927.958
928      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

of earth levee and 8,896 feet of concrete wall, extending from high
ground near Fourth and Main Streets downstream along the left
bank of the Ohio River to the approach fill of the Kentucky and
Indiana terminal railroad bridge; section C, including 9,024 feet of
earth levee, extending from the lower end of section B downstream
along the northwest edge of the city area to high ground along
Northwestern Parkway and the west end of Main Street; section
D, including 7,368 feet of earth levee and 2,725 feet of concrete
wall, extending from high ground in Shawnee Park downstream
along the river bank to a point near the corporate limits of the
city of Louisville; section E, including 43,997 feet of earth levee
and 94 feet of concrete wall, extending downstream from the lower
end of section D along the river bank to the mouth of Cane Run
ditch, thence upstream along the right bank of this ditch and Big
Run ditch to high ground at United States Highways No. 31W and
60 near Greenwood Avenue; 14 pumping plants for disposal of
interior drainage; and other appurtenant structures.
   The project will provide protection for the city of Louisville,
Ky., and adjacent highly developed county area at the southwest-
ern limits of the city against Ohio River floods equal to the flood
of 1937 (maximum of record).
   The estimated Federal cost of new work (1954) is $26,659,000;
the estimated non-Federal cost is $2,500,000.
   The existing project has been selected for construction under
the general authorization for the Ohio River Basin contained in the
Flood Control Act approved June 28, 1938.
   Local cooperation. Bond issue to cover rights-of-way costs
was voted on November 5, 1940. Formal assurances of local co-
operation, dated February 28, 1941, have been furnished in ac-
cordance with a resolution of the board of aldermen of the city
of Louisville adopted February 25, 1941. A copy of resolution
supplementing the previous resolution adopted by board of alder-
men on August 24, 1953 assuring fulfillment of local cooperation
requirements for section AA has been furnished. Rights-of-way
for sections A, B, C, D, E, and the 14 pumping plants have been
acquired.
   The funds contributed for joint design, engineering studies, and
construction of interior drainage facilities beyond the scope of the
authorized Federal project totaled $1,616,600 at the end of the
fiscal year, of which $26,057 was contributed by the City of Louis-
ville and $1,590,543 was contributed by the Louisville and Jeffer-
son County Metropolitan Sewer District.
   Operations and results during fiscal year. Construction of
pumping plants located at 5th, 10th, 17th, 4th and Buchanan
Streets and at the State Fairgrounds was completed during fiscal
year. Additional relief wells for section E were also completed.
Construction was continued on Lee's Lane, Mill Creek, and
Paddy's Run pumping plants under continuing-contract. Bear-
grass Creek pumping plant construction was initiated in July 1953
by continuing-contract and continued during the year. General
design memorandum for section AA was completed in June 1954.
Operations and maintenance manual preparation was continued.
Local interests performed routine maintenance of the previously
                   FLOOD CONTROL-LOUISVILLE, KY., DISTRICT                                                        929
assigned portion of the project.
   The costs during the fiscal year were $3,930,535 from regular
funds and $2,789 from contributed funds, a total of $3,933,324,
all for new work.
   Condition at end of fiscal year. Construction of the project was
started in March 1947 and was 78 percent completed at the end of
fiscal year. Construction of sections A, part 1 and 2, B, C, D, and
E, and Shawnee, 4th, Buchanan, 5th, 10th, 17th, 27th, and 34th
Streets, and State Fairgrounds pumping plants, including dehu-
midification of plants except State Fairgrounds, was completed at
end of fiscal year. Beargrass Creek pumping plant construction
was 33 percent completed; pumping plants at Lee's Lane, Mill
Creek and Paddy's Run were 99 percent completed; dehumidifica-
tion of State Fairgrounds, Lee's Lane, Mill Creek and Paddy's Run
was 56 percent completed. Preparation of operations and mainte-
nance manual 65 percent completed. The work remaining consists
of completion of work presently under contract which includes
four pumping plants and dehumidification of five pumping plants,
and the construction of section AA wall and pumping plant.
   The total costs to the end of fiscal year were $20,912,851 from
regular funds, $8,902 from Emergency Relief funds and $1,615,277
from contributed funds, a total of $22,537,030, all for new work.
                                         Cost and financial summary
                                            UNITED STATES FUNDS


                                                  Fiscal year ending June 30                            Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                                  1950           1951          1952          1953          1954          priorto 19501

New work:
   Appropriated_           -   $4, 092,500    $3, 600,000   $4, 500,000   $4, 229,000------------          $23547, 794
    Cost-                       2,295, 046     3,271, 664    2699,998      2660, 746    2 $3,930921,                753

  I Includes $8,902 Emergency Relief funds.
  2 Difference between current fiscal year costs reported in column 1954 and those reported in "Operations
and results during fiscal year" is as follows: Fiscal year 1953 undistributed costs distributed to features
in fiscal year 1954, $75.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_------ --       $1,873,455
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955_--                                                          1,873,455
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project.          _                                 3,111,206
                                             CONTRIBUTED FUNDS

                                                   Fiscal year ending June 30                          Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                                  1950           1951          1952          1953          1954         priorto 1950

New work:
   Appropriated ........         $22,236     $1,075, 254     $208, 193      $307, 716       $3, 200         $1,616, 600
   Cost_..                         7, 236       932,864       312, 043       360,344         2, 789          1,615,277


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_------------        $1,106
    Unobligated balances available for succeeding fiscal year ending June 30,
       1955__                                                                  1.106
930      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

           13. NEW ALBANY, OHIO RIVER BASIN, IND.
   Location. In Floyd County, Ind., on the right bank of the Ohio
River, 608 miles below Pittsburgh, Pa.
   Existing project. The plan of improvement provides for the
construction of 2.8 miles of earth levee, 0.7 mile of concrete wall, 6
pumping plants and other necessary appurtenant structures. The
main portion of the levee and walls begins at high ground near
Glenwood Court and extends downstream along the right bank of
Silver Creek to the right bank of the Ohio River, thence down-
stream' along the bank of the river across Falling Run Creek to
high ground at Main Street. Also included is a short section of
levee across Slate Run Creek near its entrance into Silver Creek.
   The project will provide protection for the city of New Albany,
Ind., against Ohio River floods equal to the flood of 1937 (maxi-
mum of record) with a 3-foot freeboard.
   The estimated cost of the project (1954) is $5,363,000; the esti-
mated non-Federal cost is $740,000.
   The existing project has been selected for construction under the
general authorization for the Ohio River iBasin contained in the
Flood Control Act approved June 28, 1938.
   Local cooperation. The New Albany Flood Control District
was organized on June 4, 1946, by order of the Floyd County
circuit court. Assurances of local cooperation were executed
by this district on March 15, 1947. Acquisition of rights-of-way
is complete. Over the past 5-year period, formal requests have
been made of local interests to furnish necessary ponding areas.
None of these areas have been acquired. The city of New Albany
has contributed $31,989 for modification of sewers in connec-
tion with flood wall construction and $95,000 has been paid by
Southern Railway Co. for provision of additional embankment
along the levee for a distance of 5,400 feet, from a point about
300 feet from the downstream end of the levee to the East Fourth
Street, on which to relocate their main track. This work is be-
yond the scope of the authorized Federal project.
   Operation and results during fiscal year. Construction of sec-
tion II, part 2 and the three pumping plants of east section :was
completed. The construction of the three west section pumping
plants was continued during the fiscal year under continuing-con-
tract. Dehumidification of the east section pumping plants was
initiated and completed. Minor repairs and reconditioning of
existing flood protection were initiated under contract.
   The costs during fiscal year were $777,379 from regular funds
and $11,220 from contributed funds, a total of $788,599 for new
work.
   Condition at end of fiscal year. Construction was started in
March 1948 and was 97 percent completed at the end of fiscal year.
The construction was completed for section I parts 1 and 2, section
II, parts 1 and 2, and east section pumping plants located at Slate
Run, East Market Street and Chambers Street including dehumidi-
fication. The three pumping plants of the west section were 98
percent completed. Minor repairs and reconditioning was 85
percent completed.    The remaining work consists of completion
                     FLOOD CONTROL--LOUISVILLE, KY., DISTRICT                                            931
of contracts in force and preparation of operations and mainte-
nance manual.
   The total costs to the end of fiscal year were $5,223,523 from
regular funds, $3,278 from Emergency Relief funds and $123,858
from contributed funds, a total of $5,350,659, all for new work.
                                     Cost and financial summary
                                         UNITED STATES FUNDS



                                                Fiscal year ending June 30                     Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                              1950           1951        1952         1953          1954       priorto 19501

New work:
   Appropriated...        $1, 600, 000    $1, 950,000    $75, 000    $329,000    -$129, 600         $5, 362, 659
   Cost_      _              791,733         972,779     750,384    1,257, 767     777, 379          5,226,801

1 Includes $3,278 Emergency Relief funds.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-----_--_---     $109,654
    Unobligated balances available for succeeding fiscal year ending June
       30, 1955       _                                              ---------                      109,654

                                         CONTRIBUTED FUNDS

                                              Fiscal year ending June 30                       Total to June
                                                                                              30,1954, includ-
                                                                                              ing fiscal years
                             1950            1951        1952         1953         1954         priorto 1950

New work:
   Appropriated              $30,000              -     $123,989 ' -$27, 000 .-
                                                                              __                    2 $126,989
   Cost_                                                  24,038     88,600      $11,220               123,858


I Refund to Southern Railway Company.
2 Includes $31,989 by city of New Albany and $95,000 by Southern Railway Co.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954---__--------        $3,131
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955 _ -------------------------------------------------                 3,131

                  14. HAWESVILLE,                OHIO RIVER BASIN, KY.
   Location. In Hancock County, Ky., on the left bank of the Ohio
River, 723.9 miles below Pittsburgh, Pa.
   Existing project. The plan of improvement provides for the
construction of 4,653 feet of earth levee, required diversion sewers,
one pumping plant and other necessary appurtenances. The earth
levee has an average height of 19.5 feet and begins at high ground
about 400 feet east of the courthouse square and extends in a
northeasterly direction along the left bank of Coperas Branch to
the left bank of the Ohio River, thence downstream along the Ohio
River to the mouth of Lead Creek, thence upstream along the
right bank of Lead Creek to high ground at United States Highway
60. It will provide protection for the city of Hawesville, Ky.,
against Ohio River floods equal to the 1937 flood (maximum of
record) with a 3-foot freeboard.
   The current (1954) estimated Federal cost of new work is
$970,000; the estimated non-Federal cost is $68,000.
932          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   The existing project has been selected for construction under
the general authorization for the Ohio River Basin contained in
the Flood Control Act approved June 28, 1938.
   Local cooperation. Formal assurances of local cooperation,
dated September 3, 1946, have been adopted by the common council
of the city of Hawesville. Acquisition of the rights-of-way is
complete.
   Operations and results during fiscal year. Construction and
dehumidification of the pumping plant were completed during
fiscal year. Minor reconditioning of existing flood protection was
initiated and completed by contract. Preparation of operations
and maintenance manual completed. The project was assigned to
local interests for maintenance and operation on October 1, 1953.
There was no flood during the year which required operation of
the project.
   The costs during the fiscal year were $13,917 for new work.
   Condition at end of fiscal year. Construction of the project was
started in May 1950 and completed in October 1953. Preparation
of operations and maintenance manual was completed. Operation
and mainteriance was assigned to local interests.
   The total costs to the end of fiscal year were $968,797 for new
work.
                                   Cost and financial summary

                                           Fiscal year ending June 30                  Total to June
                                                                                       30, 1954, includ-
                                                                                       ing fiscal years
                            1950          1951        1952        1953       1954        priorto 1950

New work:
   Appropriated _.....   $650, 000   _              $108,000     -$6, 000   -$3, 845           $970,021
   Cost-----------------   37,822        $463,209    251,112      148,250     13,917            968,797


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_------------        $1,224
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955___---------------------------------------------                     1,224

               15.   CANNELTON,              OHIO      RIVER BASIN,           MD.
   Location. Cannelton is located in Perry County, Ind., on the
right bank of the Ohio River, 724 miles below Pittsburgh, Pa.
   Existing project. The plan of improvement provides for the
construction of 2,269 feet of earth levee, beginning at high ground
450 feet southwest of the intersection of St. Louis and Long Ave-
nues and extending in a westerly direction to the bank of the Ohio
River at the end of Hafele Street; 4,790 feet of concrete wall,
extending from the lower end of the levee downstream along the
bank of the Ohio River on the riverside of Front Street to the inter-
section of Herzeele Street, thence in a northerly direction along
the Southern Railway tracks to a point near the intersection of
Second and Hunt Streets; 1,351 feet of earth levee, extending from
the lower end of the concrete wall in a northerly direction to high
ground at the northwestern limits of the city; three pumping
plants for disposal of interior drainage; and other appurtenant
structures.
                 FLOOD CONTROL--LOUISVILLE, KY., DISTRICT                                  933
   The project provides protection for the city of Cannelton, Ind.,
against Ohio River floods equal to the 1937 flood (maximum of
record) with a 3-foot freeboard.
   The current estimated cost of new work (1954) is $1,930,000;
the estimated non-Federal cost is $40,000.
   The existing project has been selected for construction under the
general authorization for the Ohio River Basin contained in the
Flood Control Act approved August 28, 1937.
  Local cooperation. Formal assurances of local cooperation,
dated August 14, 1945, have been furnished in accordance with
resolution of the city council of Cannelton adopted on the same
date. The rights-of-way for the levee section were approved on
January 27, 1947, and all rights-of-way for the wall section and
the pumping plants have been acquired. Formal requests have
been made of local interests to furnish necessary areas for pond-
ing at Castleberry Creek and 4th Street Ditch pumping plants.
These areas have not been acquired.
   Operations and results during fiscal year. Engineering studies
for necessary corrective measures and modifications were made
during the fiscal year. A contract was awarded in June 1954 for
minor curb and pavement construction along Front Street. Local
interests performed routine maintenance of the project. There
was no flood during the year which required the operation of the
project.
   The costs during fiscal year were $1,032 for new work.
   Condition at end of fiscal year. Construction of the project was
started in March 1947 and completed in October 1950. The project
was assigned to local interests for operation and maintenance on
October 24, 1950. The work remaining consists of completion of
the work presently being performed.
  The total costs to the end of fiscal year were $1,914,678 from
regular funds and $239 from Emergency Relief funds, a total of
$1,914,917.
                                   Cost and financial summary

                                           Fiscal year ending June 30           Total to June
                                                                                30, 1954, includ-
                                                                         1954   ing  fiscalyears
                                                                                 prior  to 19501
                            1950          1951        1952        1953


New work:



1Includes $239 Emergency Relief funds.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-----------__        $13, 534
    Unobligated balances available for succeeding fiscal year ending June 30,
       1955-                                     -                                     13,534

16. ROUGH RIVER RESERVOIR AND CHANNEL IMPROVEMENT, KY.
  Location. The dam site for the Rough River Reservoir is lo-
cated on Rough River, 89.3 miles above its confluence with Green
River and about 160.3 miles above the Ohio River. The reservoir
will extend upstream in the valley a distance of about 30 miles and
934       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

will lie in Breckinridge, Grayson, and Hardin Counties, Ky. The
channel improvement work is located on Rough River, Barnett
Creek and North Fork Barnett Creek.
    Existing project. The plan of improvement includes the con-
struction of a dam for flood control and conservation. This unit
as now planned provides for a rolled earth and rock dam with an
uncontrolled spillway on the left abutment and a gate-controlled
outlet works with stilling basin located along the toe of the right
abutment; necessary relocation of roads, utilities and cemeteries;
acquisition of land needed for the reservoir area and other required
appurtenant facilities.
    The authorized channel improvements, located in Ohio County,
Ky., consists of clearing the banks and minor channel cleaning of
the Rough River channel from its mouth at Livermore, Ky., to the
mouth of Caney Creek, a distance of 64 miles; channel rectifica-
tion on Barnett Creek from its mouth to mile 6.7; and channel
rectification on the North Fork Barnett Creek, a tributary which
enters Barnett Creek at mile 6.15, from its mouth to mile 2.3.
    The estimated cost of new work revised in 1954 is $8,490,000
for the reservoir; $780,000 Federal cost for Rough River bank
clearing and channel cleaning, and $4,000 non-Federal; $100,000
Federal cost for the Barnett Creek section and $18,000 non-
Federal. The latest published map is contained in House Docu-
ment No. 535, 78th Congress, 2d session.
    The existing project has been selected for construction under the
general authorization for the Ohio River Basin contained in the
Flood Control Act approved June 28, 1938. Modification of the
previously approved plan to include the channel improvement
items was authorized by the Flood Control Act approved Decem-
ber 22, 1944.
   Local cooperation. No local cooperation is required for the
construction of the reservoir unit. The provisions of section 3 of
the Flood Control Act of 1936, are applicable to the channel im-
provements.
    Operations and results during fiscal year. Field surveys and
explorations, and engineering studies were continued. Preparation
of general design memorandum No. 1 and design memorandum
No. 2 covering design of outlet works and access road for Rough
River reservoir was completed in September 1953. The prepara-
tion of construction plans was started for the outlet works and
access road of the reservoir.
   The costs during the fiscal year were $40,683 for new work.
   Condition at end of fiscal year. The general design memoran-
dum No. 1 for Rough River reservoir and design memorandum No.
2 covering the outlet works and access road design were completed.
Plans for construction of outlet works and access road were 94
percent completed at end of fiscal year. There has been no con-
struction started on this project.
   The total costs to the end of fiscal year were $129,677 for new
work.
                    FLOOD CONTROL--LOUISVILLE,                       KY., DISTRICT                        935
                                     Cost and financial summary

                                              Fiscal year ending June 30                        Total to June
                                                                                 _i__     ___   30, 1954, includ-
                                                                                                ing fiscal years
                              1950           1951       1952          1953              1954      priorto 1950


New work:
    Appropriated- --. _ ---                                           $50, 000      $32, 500            $131, 342
    Co t - ----- -.            .-       --                     --.     40,152        40,683              129,677


Other new work data:
     Unobligated balance, fiscal year ending June 30, 1954_---                 $1,584
     Unobligated balances available for succeeding fiscal year ending June
       30, 1955------_  ---     ---------           --------------------          ,
                                                                                1,584
    Estimated additional amount needed to be appropriated for comple-
       tion of existing project        ---------------------------------   9,238,658

                    17. VINCENNES,             OHIO RIVER BASIN,                   IND.
     Location. In Knox County, Ind., on the left bank of the Wabash
  River, 128 miles above the mouth.
    Existing project. The plan of improvement provides for con-
  struction of 3.9 miles of earth levee, 0.5 mile of levee enlargement,
  0.8 mile of concrete wall, 5 pumping plants, alteration of 3 railroad
bridges and other necessary appurtenances. It will provide pro-
tection for the city of Vincennes, Ind., against Wabash River floods
equal to the maximum of record.
    The estimated Federal cost of new work (1954) is $4,210,000;
the estimated non-Federal cost is $285,000. The latest published
map is contained in House Document 197, 80th Congress, 1st
session.
    The existing project has been selected for construction under the
additional authorization for the Ohio River Basin contained in the
Flood Control Act approved July 24, 1946.
    Local cooperation. Assurances of local cooperation in accord-
ance with the city council resolution were executed on November
28, 1951. Acquisition of rights-of-way for section A, parts 1 and 2
and section B, part 1 is completed and the remainder is under
way.
    Operations and results during fiscal year. Preparation of plans
and specifications for construction of section B, part 1, were com-
pleted and plans and specifications for section B, part 2, were
started. Construction of section A, part 2, was completed, except
for surging and testing wells, during fiscal year. Contract was
awarded and construction was initiated on section B, part 1. De-
sign studies were continued under contract by Baltimore & Ohio
Railroad for the alteration of their bridge and approaches.
    The costs during the fiscal year were $515,498 for new work.
    Conditions at end of fiscal year. Construction was started in
May 1952, and was 28 percent completed at the end of fiscal year.
Construction of section A, part 1 and 2, was completed except surg-
ing and testing wells on part 2. Section B, part 1, construction
was 27 percent complete at end of year. Design studies for the
alteration of B. & O.Railroad bridge and approaches were reported
to be 15 percent complete. The work remaining consists of com-
pletion of construction of section B, part 1, construction of section
936            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

B, part 2, construction of five pumping plants, the alterations of
B. & O. R.R. bridge, Second Street bridge, C. & E.I. R.R. bridge,
and P.C.C. & St. L. R.R. bridge.
  The total costs to the end of fiscal year were $1,194,024 for new
work.
                                   Cost and financial summary

                                         Fiscal year ending June 30                        Total to June
                                                                                          30, 1954, includ-
                                                                                          ing fiscal years
                            1950        1951        1952        1953          1954         priorto 1950

New work:                   40
   Appropriated _ _ _          ,000      .        $300, 000    $498, 000   $1, 200, 000        $2, 088,000
   Cost .----------------   17, 703     $30,862    100,934      510,305        515,498          1,194, 024


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954------------      $257,092
    Appropriated for succeeding fiscal year ending June 30, 1955--------    500,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955      ---------------------------------------------           757,092
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project_ - -                            --         1,622,000

                18. BREVOORT LEVEE, WABASH                        RIVER, IND.
  Location. The Brevoort levee is located in Knox County, Ind.
on the left bank of the Wabash River, 104.5 to 127.5 miles above
the mouth, and on the right bank of the White River, 6.3 to 22.2
miles above its mouth.
  Existing project. The plan of improvement provides for the
construction of a system of earth levees consisting of the following
features: Section I, approximately 16.2 miles in length, extending
upstream from high ground at the Claypole Hills along the left
bank of the Wabash River to a point approximately 3 miles above
the Cleveland, Cincinnati, Chicago & St. Louis Railway bridge
across the Wabash River to St. Francisville, Ill.; section II, ap-
proximately 5 miles in length, extending from the upstream end
of section I along the left bank of the Wabash River to high ground
near the southwest city limits of Vincennes, Ind.; section III,
approximately 10.1 miles in length, extending upstream along the
right bank of the White River from high ground at Claypole Hills
to the downstream end of the Dicksburgh Hills and from the up-
stream end of the Dicksburgh Hills to the right bank of the Deshee
River diversion channel at its confluence with White River; section
IV, approximately 4.6 miles in length, extending along the right
bank of the Deshee River diversion channel from the upstream end
of section III, to the Chicago & Eastern Illinois Railroad embank-
ment north of the Deshee River diversion channel bridge; section
V, approximately 1.2 miles in length, extending from the upstream
end of section IV along the north bank of the Deshee River to high
ground near the Decker Road; one new pumping plant for the dis-
posal of interior drainage; and appurtenant drainage structures.
   The project will provide protection for approximately 50,000
acres of overflow land, and the villages of Zigville, St. Thomas,
Brevoorts, and Cathlinette Settlement against agricultural season
floods. Flood stages equal to or in excess of the established pro-
                 FLOOD CONTROL-LOUISVILLE, KY., DISTRICT                                                937
tection grade may be expected to occur on an average of seven
times in each 100-year period.
   The estimated Federal cost of new work (1954) is $2,090,000;
the estimated non-Federal cost is $250,000. The latest published
map is contained in House Document 100, 73d Congress, 1st
session.
   The existing project was authorized by the Flood Control Act
approved June 22, 1936.
   Local cooperation. Fully complied with for work completed.
   Operations and results during fiscal year. Revision of opera-
tion and maintenance manual was completed. Local interests per-
formed routine maintenance of the project. There was no flood
during the year which required operation of the project.
   The costs during the fiscal year were $980 for new work.
   Condition at end of fiscal year. Construction work on the proj-
ect was started in July 1938, and completed in September 1947.
All completed parts of the levee are in good condition except for
portions which are threatened by caving banks. The work re-
maining to be done consists of strengthening a portion of the exist-
ing levee along the Wabash River and alteration of one affected
railroad bridge.
   The total costs to the end of the fiscal year were $1,230,873 for
new work.
                                     Cost and financial summary

                                           Fiscal year ending June 30                         Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                              1950        1951          1952        1953          1954          prior to 1950

New work:
   Appropriated .   .$ -- -      -      -$45,000   --   -
                                                        -      ----$16,000   --   --               $1,230,873
   Cost-__----      -          $4,348       3,957           $972      3,969            $980          1,230,873

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project                               $----------------

     19. CAGLES         MILL RESERVOIR,                     OHIO RIVER BASIN, IND.
   Location. The site of the Cagles Mill Dam is on Mill Creek, 2.8
miles above its entrance into Eel River, and 7 miles west of Clover-
dale, Ind. It is in Putnam County, Ind., and is about 25 miles east
of Terre Haute, Ind. The Cagles Mill Reservoir will extend up-
stream about 11 miles and will lie in Putnam and Owen Counties,
Ind.
   Existing project. The plan of improvement provides for the
construction of a dam for flood control and recreation. It includes
an earth and rockfill embankment with a maximum height of 150
feet and a length of 900 feet, an outlet tunnel through the right
abutment with control gates and stilling basin and an opencut
spillway through a low point in the left abutment. A permanent
pool at elevation 636, having a capacity of 27,100 acre-feet and an
area of 1,400 acres, is also included in the plan. The storage
between elevations 636 and 704 amounting to 201,000 acre-feet,
which is equivalent to 12.8 inches of runoff from the 295 square
938              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

miles of drainage area above the dam, is reserved for flood control.
Also included in the project are the acquisition of necessary, lands,
clearing the permanent pool area of all timber and brush, and the
relocation of a section of State Highway 42 which will be affected
by the reservoir.
   The estimated cost of new work (1953) is $4,121,000.
   The (1953) estimated annual cost of maintenance and operation
is $31,000.
   The existing project was selected for construction under the
general authorization for the Ohio River Basin contained in the
Flood Control Act approved June 28, 1938.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies. The State of Indiana has undertaken the
development and management of recreation facilities for use of the
public in the reservoir area in accordance with license granted by
the Secretary of the Army on January 17, 1952.
   Operations and results during fiscal year. Final settlements
made for relocation of State Highway 42 and electric lines.
Miscellaneous minor corrective measures were accomplished.
Routine operations and maintenance was performed during the
year.
   The costs during the fiscal year were $96,841 for new work and
$24,427 for operation and maintenance.
   Conditions at end of fiscal year. Construction of the project
was started in July 1948 and was completed at the end of fiscal
year 1953, except for minor items of work. The work remaining
consists of making final payments for oil line relocation and ac-
complishing other necessary minor items of work.
   The total costs to the end of fiscal year were $4,100,662 for new
work and $43,402 for operation and maintenance.
                                                    Cost and financial summary

                                                                 Fiscal year ending June 30                             Total to June
                                                                                                                    30, 1954, includ-
                                                                                                                    ing fiscal years
                                         1950                1951               1952       1953        1954             prior to 1950

New work:
   Appropriated                     $2, 500, 000          -$83, 000         -$400, 000    -$19, 000        -      - .       $4, 121,000
   Cost...                              610, 559            869, 483           657, 078     653, 205   $96, 841              4,100, 662
Maintenance:
   Appropriated .             ....----   .                     -------... ----------...
                                                    ..---------------                        21,000     27,360                  48,360
   Cost ......., ----._.---       ...           -        ------------ --------...            18,975     24,427                  43,402


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_         -----      $10,837
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955--_-                                                                 10,837

20. NEW HARMONY BRIDGE, OHIO RIVER BASIN, ILL. AND IND.
   Location. The New Harmony Bridge is located across the
Wabash River at mile 51.5 above the mouth. The bank protection
work is located in White County, Ill., and Posey County, Ind.,
along the Wabash River at and above the bridge.
  Existing project. The plan of improvement consists of bank
protection and control works on the banks of the Wabash River to
           FLOOD CONTROL--LOUISVILLE, KY., DISTRICT             939
arrest bank caving conditions which are endangering the safety of
the bridge structure. The bridge supports United States Highway
460 and is the only highway across the Wabash River between
Mount Carmel, Ill. (mile 96), and the mouth of this stream.
   The estimated Federal cost of the project (1954) is $663,000,
the estimated non-Federal cost is $65,000.
   The existing project was authorized in the Flood Control Act
approved May 17, 1950.
  Local cooperation. The owners of the New Harmony Bridge
have indicated willingness to fulfill these requirements.
   Operations and results during fiscal year. None.
   Condition at end of fiscal year. Work had not been started on
the preparation of plans and specifications. Construction of the
project had not been started.
   There have been no costs.
                       21. ROSICLARE, ILL.
   Location. In Hardin County, Ill., on the right bank of the Ohio
River, 892 miles below Pittsburgh, Pa.
   Existing project. The plan of improvement provides for the
construction of 3,455 feet of earth levee, required sewer alter-
ations, one pumping plant and other necessary appurtenances. The
earth levee has an average height of 21 feet. Section I begins at a
point about 200 feet northeast of the intersection of Second and
Hopkinton Streets and extends 1,950 feet in a southwesterly direc-
tion along the riverside of Second Street and parallel to the right
bank of the Ohio River, crosses Willow Creek and thence in a
southerly direction for 500 feet to high ground. Section II is 1,062
feet in length and crosses a low swale approximately 3,000 feet
southwest of the city of Rosiclare. Protection will be provided for
the city of Rosiclare and valuable mining properties and proces-
sing plants west and southwest of the city against Ohio River
floods equal to the 1937 flood (maximum of record) with a 3-foot
freeboard.
   The estimated Federal cost of new work (1954) is $624,000;
the estimated non-Federal cost is $120,000.
   The latest published map is contained in Senate Document No.
125, 80th Congress, 2d session.
   The existing project was authorized in the Flood Control Act
approved June 30, 1948.
   Local cooperation. The city of Rosiclare adopted assurances
of local cooperation on September 30, 1949. Acquisition of rights-
of-way for the levee and appurtenances is completed. Ponding
area has not been furnished.
   Operations and results during fiscal year. Preparation of op-
erations and maintenance manual was completed during fiscal
year. Dehumidification of the pumping plant was completed. A
contract was awarded and completed for reconditioning of the
flood protection works. The project was assigned to local interests
for operation and maintenance on September 1, 1953, and routine
maintenance was performed by them for the remainder of the
year. There was no flood during the year which required operation
940           REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

of the project.
   The costs during the fiscal year were $8,542 for new work.
   Condition at end of fiscal year. Construction of the project
was started June 20, 1950, and was completed in September 1953.
  The total costs to the end of fiscal year were $622,484 for new
work.
                                   Cost and financial summary

                                         Fiscal year ending June 30                    Total to June
                                                                                      30, 1954, includ-
                                                                                      ing fiscal years
                            1950        1951        1952        1953        1954       prior to 1950

New work:
   Appropriated ........   $250, 000   $385, 000               -..$5,000   -$5, 968           $624, 032
   Cost-...                  47,874     318, 595   $195, 331      52,142      8,542            622, 484


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954----------_   --     $1,548
    Unobligated balances available for succeeding fiscal year ending June 30,
       1955__                                                                  1,548

                    22. PADUCAH, OHIO RIVER BASIN, KY.

   Location. Paducah is located in McCracken County, Ky., on
the left bank of the Ohio River, 934.4 miles below Pittsburgh, Pa.
   Existing project. The plan of improvement provides for the
construction of a system of levees and concrete flood walls, con-
sisting of the following features: Section A, an earth levee 13,920
feet in length, extending from high ground south of United States
Highway No. 60, near Levin Avenue along the bank of the Ohio
River to the foot of Terrell Street; section B, unit 1, including 530
feet of new earth levee and 7,100 feet of concrete wall, unit 2, in-
cluding 2,730 feet of new earth levee and 8,770 feet of concrete
wall, and a barrier dam, 367 feet long, across Island Creek, the
entire section extending from the upstream end of section A along
the bank of the Ohio River to the foot of Mill Street; section C,
and earth levee, 31,520 feet in length, extending from the up-
stream end of section B in a general southerly direction to high
ground north of the Illinois Central Railroad bridge over Bee
Slough, 12 pumping plants for the disposal of interior drainage
and appurtenant structures.
   The project provides protection for Paducah, Ky., against Ohio
River floods equal to the 1937 flood (maximum of record) with a
3-foot freeboard.
   The estimated Federal cost of the project (1954) is $4,638,000,
of which an amount not exceeding $160,000 may be applied to
lands and damages; the estimated non-Federal cost is $202,000.
   The existing project was selected for construction under the
general authorization for the Ohio River Basin contained in Flood
Control Act approved August 28, 1937.
   Local cooperation. On April 22, 1938, the President approved
a waiver of 40 percent of the estimated cost of lands, easements,
and rights-of-way under provisions of Section 1 of the Flood
Control Act approved August 28, 1937. Rights-of-way for con-
struction have been furnished in accordance with this waiver.
                  FLOOD CONTROL-LOUISVILLE, KY., DISTRICT                                                   941
Acquisition of flowage easement in Bee Branch area outside
levees is pending. The project was assigned to local interest for
operation and maintenance as of July 15, 1949.
   Operations and results during fiscal year. The contract for de-
humidification of pumping plants was completed during fiscal
year. Routine maintenance was performed by local interests. There
was no flood during the year which required operation of the
project.
   The costs during fiscal year were $33,499 for new work.
   Condition at end of fiscal year. Construction was started in
August 1939 and was completed in January 1950. Operations dur-
ing subsequent floods revealed some deficiencies in performance of
drainage works and pumping plants. This supplemental work was
completed at the end of fiscal year 1953. Dehumidification of
pumping plants is complete. The work remaining consists of re-
medial work required on drainage facilities and final settlement for
lands, easements, and rights-of-way upon decision of pending
court cases and settlement of pending claim.
   The total costs to the end of fiscal year were $4,377,818 from
regular funds and $4,623 from Emergency Relief funds, a total of
$4,382,441 for new work.
                                    Cost and financial summary

                                              Fiscal year ending June 30                          Total to June
                                                                                                 30, 19541,includ-
                                                                                                 ing fiscal years
                             1950         1951          1952         1953             1954        prior to1950


New work:
   Appropriated     .-       $21, 300    $268, 498 -                 $86, 889   ...                    $4, 485,071
   Cost --                    24, 624       9,296       $46,362       36,745          $33, 499          4,382,441

1 Includes $4, 623 Emergency Relief funds.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-__---------     $102,630
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955      ---------------------------------------------          102,630
    Estimated additional amount needed to be appropriated for completion
      of existing project_ --------------------------------------          152,929

                  23. REEVESVILLE, OHIO RIVER BASIN, ILL.
   Location. The project is located in Pope, Massac, Johnson, and
Pulaski Counties, Ill., in the Bay Creek-Cache River Valley. These
streams form a connecting valley across the southern tip of the
State of Illinois from the Ohio River at mile 910 on the east to
mile 975 on the west. During high floods, backwater from the
Ohio River overflows the flood plain of the Bay Creek-Cache River
Valley.
   Existing project. The plan of improvement provides for the
construction of 2 levees, one known as the Reevesville levee and
the other as the Cache River levee. The Reevesville levee begins at
high ground about 1 mile north of Reevesville, Ill., and extends
eastward to the double track main line of the Illinois Central Rail-
road, thence continues in a general southerly direction for a dis-
tance of 2 miles crossing the Golconda branch of the Illinois
942           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Central Railroad, thence east along the Bay Creek relief channel
at a distance of about 200 to 800 feet from the right bank to State
Highway 145, and thence in a southeasterly direction to high
ground about 1,000 feet south of the Bay Creek relief channel.
This levee is 4.9 miles long and has an average height of 11 feet.
The Cache River levee begins at high ground on the right bank of
the Post Creek cutoff approximately 700 feet upstream from the
Chicago & Eastern Illinois Railroad crossing of this stream and
parallels the old spoil bank levee for about 2,000 feet along Post
Creek at a distance of about 150 feet, thence continues upstream
along the landside of the spoil bank levee on the right bank of
Forman floodway ending at the gravel road along the New York
Central Railroad. The total length of the Cache River levee is 3.7
miles with an average height of 10 feet. In addition, the plan in-
cludes a short levee about 550 feet long across a low swale a
short distance east of Karnak, ll., and other appurtenant struc-
tures.,
   The project provides protection for the city of Reevesville, Ill.,
the urban centers of Belknap, Karnak, and Ullin, Ill., 7 smaller
towns, 4 railroads, several miles: of main highways and 23,500
acres of tillable land, against Ohio River and Bay Creek floods
equal to the 1937 flood (maximum of record) with a 3-foot free-
board.
   The estimated Federal cost of new work (1954) is $600,300; the
estimated non-Federal cost is $40,000.
   The existing project was selected for construction under the
general authorization for the Ohio River Basin contained in the
Flood Control Act approved June 28, 1938.
   Local cooperation. Fully complied with.
   Operations and results during fiscal year. The reseeding of
levee and repair to drainage structure was completed by contract
during the year. Final settlement of the contract for construction
of levee and appurtenances was made. Routine maintenance was
performed by local interests on the project. There was no flood
during the year requiring operation of the project.
   The costs during the fiscal year were $25,917 for new work.
   Condition at end of fiscal year. Construction of the project
was started in July 1949, and was completed in September 1952.
Local interests were assigned the operation and maintenance of
the project on October 3, 1954.
   The total costs to the end of fiscal year were $600,300 for new
work.
                                   Cost and financial summary

                                            Fiscal year ending June 30                   Total to June
                                                                                         30, 1954, includ-
                                                                                         ing fceal years
                            1950          1951         1952        1953        1954       priorto 1950


New work:
   Appropriated .--------   $66, 700   -$170, 000    ........      $21,300    -$1, 700           $600, 300
   Cost ----------------    166,296       179, 542    $147,757      38, 211     25,917            600, 300
            FLOOD CONTROLr-LOUISVILLE, KY., DISTRICT             943
      24. OHIO RIVER BASIN,      LOUISVILLE,   KY.,   DISTRICT
   Location. The works covered by this project are a series of
levees, flood walls, channel improvements, and reservoirs in the
Ohio River Basin within the confines of the Louisville, Ky., dis-
trict.
   Existing project. The Flood Control Act approved August 28,
1937, authorized the construction of the levees, flood walls, and
drainage structures, for the protection of cities and towns in the
Ohio River Basin, the projects to be selected by the Chief of En-
gineers with the approval of the Secretary of War, in accordance
with House Flood Control Committee Document 1, 75th Congress,
1st.. session, at a cost not to exceed $24,877,000 for construction,
which was authorized to be appropriated for this purpose.
   The Flood Control Act, approved June 28, 1938, approved the
general comprehensive plan for flood control and other purposes
in the Ohio River Basin as set forth in House Flood Control Com-
mittee Document No. 1, 75th Congress, 1st session, with such
modifications thereof as, in the discretion of the Secretary of War
and the Chief of Engineers may be advisable, and for initiation
and partial accomplishment of the plan, authorized $75,000,000
for reservoirs and $50,300,000 for local flood protection works, the
individual projects to be selected and approved by the Chief of
Engineers subject to the provision that the authorization shall in-
clude the diversion of Cache River above Cairo, Ill., and the pro-
tection of the area north of the Cairo drainage district by levees,
at an estimated cost of $2,000,000.
   The Flood Control Act approved August 18, 1941, authorized
the sum of $45,000,000 for the further prosecution of the compre-
hensive plan approved in the act of June 28, 1938, for the Ohio
River Basin.
   The Flood Control Act approved December 22, 1944, authorized
the sum of $70,000,000 for the further prosecution of the approved
comprehensive flood control plan for the Ohio River Basin. This
act modified the previous plan within the Louisville District to
include the plan of improvement for flood control and other pur-
poses in the Kentucky River Basin in accordance with recom-
mendations of the Chief of Engineers in House Document No. 504,
78th Congress, 2d session, flood protection works at Taylorsville,
Ky., and on Rough River and tributaries, Kentucky, in accordance
with recommendations of the Chief of Engineers in Senate Docu-
ment No. 105, 78th Congress, 1st session, and House Document
No. 535, 78th Congress, 2d session, respectively.
   The Flood Control Act approved July 24, 1946, authorized the
sum of $125,000,000 for further prosecution of the comprehensive
plan approved in the act of June 28, 1938, for the Ohio River
Basin, modified within the Louisville district to include the plan of
improvement for flood control in the Wabash River Basin, Ill.,
and Ind., substantially in accordance with the recommendations
of the Chief of Engineers in House Document No. 197, 80th Con-
gress, 1st session, and the West Fork Reservoir on the West Fork
of Mill Creek in Ohio, substantially in accordance with recom-
mendations of the Chief of Engineers in House Document No. 198,
80th Congress, 1st session.
 944              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

    In addition to previous authorizations, the Flood Control Act ap-
proved May 17, 1950, authorized the sum of $100,000,000 for
further prosecution of the comprehensive plan approved in the act
of June 28, 1938, as amended. This act modified the comprehen-
sive plan within the Louisville district to include necessary bank
stabilization measures at the New Harmony Bridge, Indiana and
Illinois at an estimated cost of $500,000. Also included in the act
was the provision that the Mining City Dam and Reservoir, Ky.,
and alternates therefor, shall not be constructed if such construc-
tion would have any adverse effect on Mammoth Cave National
Park.
   The following is a list of the individual projects considered in
the comprehensive plan within the confines of the Louisville, Ky.,
district:
                                            Local protection projects

                                                                                            Estimated cost

                   Location 1                             Type ofprotection                                           Total
                                                                                          Federal       Non-
                                                                                                       Federal

Adams Levee, Ind. (Wabash River).... Levee- ....              __       .-- -         $233, 000          $13, 000      $246,000
Alton, Ind-.....             .------.-----------------.do-............._              255, 000           40, 000       295, 000
Augusta, Ky ...... _                        ...-----------
                                                     Wall and levee.......... 1, 220, 000               620, 000     1, 840, 000
Aurora, Ind-....-----------------------             ...  do...__-............      4, 300, 000        1,190, 000     5,490, 000
Barnett 2Creek, Ky. (Rough River Channel improvement._                                118,000             18, 000       100, 000
  Basin). 5
Bellevue, Ky-                 ..             .       Wall and levee ......... 1, 570, 000               400, 000     1, 970, 000
Bonpas Creek, Ill. (Wabash River Channel improvement__                                478, 000          240, 000        718, 000
  Basin).
Bromley, Ky-.......................---               Wall  and levee ........      1, 250, 000          925, 000      2,175, 000
Brookport, Il.6...
            prt
              I.,_,----_----------_
                 ---
                                       ....         _...do_..............             608, 000           10, 000         618, 000
California (Cincinnati), Ohio.........__            ..- do       --............... 1, 750, 000          720, 000     2, 470, 000
Cannelton, Ind.....----------.......--------        ---   d o ---.   .-   .--      1, 930, 000
                                                                                ..-----                  40, 000      1, 970, 000
Carrollton, Ky__...--------------------             Levdo...
                                                    .__.do_.......... ... . .    2, 220, 000             97, 000     2,317, 000
Caseyville, Ky ..-------------- -------             Levee__.                        396, 000             35, 000         431, 000
Cave-in-Rock, Ill_..-         ___-----__----_             _do..........--....       661, 000            125, 000         786, 000
Chilo, Ohio....--....------------------------       Wall and levee .....         -  899, 000            120, 000     I, 019, 000
Cin cinn ati, Oh io 2.. . .......... .......        Wall and barrier dam -_      9, 977, 760          1,027, 600    11, 005, 360
Cincinnati, Ohio (Unit 2)-....__........            Wall and levee_......___    16, 800, 000          2, 900, 000   19, 700, 000
Cincinnati, Ohio (Unit 4 remainder)....             W all................. 4, 900, 000                   621, 000   15, 521, 000
Cleves, Ohio-...-----------------------             Levee__                      1, 240, 000              67, 000    1, 307, 000
Clinton, Ind. (Wabash River)...........            . ..- do..... .... . . .          77, 000               9, 000        86, 000
Cloverport, Ky .....................                Wall and levee ..........       728, 000            193, 000        921,   000
Concordia, Ky...........---------------------
                2- -                                Levee_-_-----                   590, 000             55, 000        645,   000
Covington, Ky. ...         .....        ..          Wall and levee ........      7, 550, 000            765, 000     8, 315,   000
Dayton, Ky-------------------...                    Wall and levee .....   ___   3, 700, 000          1, 110, 000    4, 810,   000
Deer Creek, Prairie Levee, Ind. (Wa-                Levee_        ..         ..     153, 000               9,000        162,   000
bash River).
Delphi, Ind. (Wabash River) 86........                                       144, 563
                                                                           -do...............
                                                                                          10, 000                      154, 563
Derby, Ind....----..---------------------          Wall and levee........    553, 000     67, 000                      620, 000
Dover, Ky--....-------------------                 Levee___- - -- - - - -    648, 000    585, 000                    1, 233, 000
                     ..
Elizabethtown, Ill ___...-----------               Wall and levee.........   559, 000    153, 000                       712, 000
England Pond Levee, Ill. (Wabash                   Levee--                   534, 000     30, 000                      564, 000
  River).
Evansville, Ind....-------------------       Wall and levee ._-_ ..  11, 100, 000                     1, 690, 000   12, 790, 000
Fletcher and Sunshine Gardens Levee, Levee .................. 395, 000                                    24, 000       419, 000
  Ind. (Wabash River Basin).
Frankfort, Ky. (Kentucky River)-...... Wall and levee......... 2, 930, 000                            1, 110, 000   4, 040,    000
Golconda, Ill.4..........................       do.....                  487, 107
                                                                     -....                               29, 820       516,    927
Grandview Ind         ......
                        ..          ........ Levee ......                580, 000                       133, 000       713,    000
Greenfield Bayou Levee, Ind. (Wabash .....      do ................. 1, 530, 000                        265, 000    1, 795,    000
  River).
Harrisburg, Ill.........................     Wall and levee ..... __     849, 656                        20, 000          656
                                                                                                                       869,
Hawesville, Ky._______.......................      Levee................ ..                970, 000      68, 000    1, 038,000
Higginsport, Ohio--...-----.............----....   Wall and levee.........                 944, 000     320, 000    1,264, 000
Honey Creek Levee, Ind. (Wabash                    Levee...................                653, 000      32,000        685, 000
   River).
Island Levee, Ind. (Wabash River).....             Levee .................. 1, 240, 000                 226, 000    1, 466, 000
Jackson, Ky. (Kentucky River        2
                                         Basin)-    Cut-off channel-........    260, 000                  3, 000       263, 000
Jeffersonville-Clarksville, Ind.'........          Wall and levee......... 4, 196, 600                  590, 888    4, 787,488
Lawrenceburg, Ind.....................             ....do.....-              2, 433, 414                284, 725    2, 718, 139
Leavenworth, Ind.....---..............             Wall and levee.....       1, 470, 000                266, 000    1, 736, 000
Levee Unit 1, Eel River, Ind. (Wabash              Levee...................     204, 000                 40, 000       244,000
  River Basin).
                            FLOOD CONTROL-LOUISVILLE, KY., DISTRICT                                                                                      945
                                           Local protection projects--Continued

                                                                                                               Estimated cost

                        Location 1                                  Type of protection                                            No-                 Total
                                                                                                           Federal               Non-
                                                                                                                                Federal

Levee Unit 2, Eel River, Ind. (Wabash                            Levee _________________                     2, 090, 000          715, 000          2, 805, 000
   River Basin).
Levee Unit 1, Little Wabash River, Ill.                           .. .do___                                  2, 060, 000          153, 000          2, 213, 000
   (Wabash River Basin).
Levee Unit 2, Little Wabash River, Ill. .....                          do -                                  1, 320, 000           70, 000          1,390, 000
   (Wabash River Basin).
Levee Unit 6, Wabash River, Ill. (Wa-                              ...do. .                                  1, 160, 000           56, 000          1,216, 000
   bash River Basin).
Levee Unit 17, Wabash River, Ind. .....                                do-----                                  614, 000           53, 000            667, 000
   (Wabash River Basin).
Levee Unit 1, White River, Ind. (Wa-                               . .do .. .. .. . .. ..                    1, 560, 000          105, 000          1, 665, 000
   bash River Basin).
Levee Unit 2, White River, Ind. (Wa-                                   do                                       518, 000           67, 000            585, 000
   bash River Basin).
Levee Unit 7, White River, Ind. (Wa-                                                                         1, 070, 000           80, 000          1,150, 000
   bash River Basin).
Lew isport, K y ------------------------                        Wall and levee .---                  _--        448, 000         220, 000             668,000
Louisville, Ky. _.................                        ___      -- do-------------                      26, 659, 000        2, 500, 000         29, 159, 000
Ludlow, Ky ---.....---------------                              ---- do--..-----------                      2, 540, 000          745, 000           3, 285, 000
Madison Ind .----------                                           ---do ......                              3, 820, 000          360, 000           4, 180, 000
Mason I. Niblack Levee, Ind. (Wa- Levee ..                                       ...----------              2, 530, 000          226, 000                 000
                                                                                                                                                     2, 756,
   bash River).
Mauckport, Ind..----------.-----                                     -do------------                            506, 000         105, 000             611, 000
McGinnis Levee, Ind. (Wabash River                                ---. do            -----------            1, 820, 000          104, 000           1,924, 000
   Basin).
Metropolis, Ill-_ ._..........-...-                         . Wall and levee .- _-___.                      3, 070, 000          431, 000          3,501,000
Milton, Ky .....-----.--------------                            W all ...... ............                   2, 480, 000           41, 000          2, 521, 000
Moscow, Ohio....----------------------
                             2
                                                                 Levee __----------                          1,.170, 000          372, 000          1, 542, 000
New Albany, Ind.                                                 Wall and levee       -__--                  5, 363, 000          740, 000          6, 103, 000
New Amsterdam, Ind_--                                           Levee--------------                             476, 000          13, 000             489, 000
New Harmony Bridge, Ill. and Ind. __ Bank protection ......                                                      663, 000          65, 000             728, 000
New Harmony, Ind. (Wabash River)__ Levee--------------                                                           616, 000          25, 000             641, 000
New Richmond, Ohio_______                                       Wall and levee ........                     3, 200, 000          720, 000          3, 920, 000
Newport, Ky.............------              ---                      .do.........---           ......--- 7, 251, 000             299, 000          7, 550, 000
Owensboro, Ky     2 ........---------------                     .. ..do - .... .... ....                        886, 000         195, 000          1, 081, 000
Paducah, Ky. .                                                         do            ........-------------   4, 638, 000          202,000           4;840, 000
Patriot, Ind---....---------------------                        Levee..........--------------                   753, 000         372, 000          1, 125, 000
Prestonville, K y -----------------------                       Wall and levee- ... _.                      1, 710, 000           55, 000          1, 765, 000
Raccoon    Levee,        Ind.       (Wabash         River)    _  Levee------........---------                    307, 000          33, 000             340, 000
Reevesville, Ill. (Cache River) 2 8                                    do__--------                             600, 300           40, 000             640, 300
Ripley, Ohio-------.------------------                           Wall and levee------        .               1,940, 000           810, 000          2, 750, 000
Rising Sun, Ind__                                                 --- do ....                                   896, 000             000
                                                                                                                                  280,              1,:: 000
                                                                                                                                                    l176,
Rochester and McCleary's Bluff Levee, Levee_--------------                                                      830, 000          110, 000             940, 000
   Ill. (Wabash River).
Rockport, Ind------------------                                  Wall and levee ......---                       466, 000           133,   000          599, 000
Rome, Ind......                 -----------------
                                   ...--                         Levee---------                                 359, 000            67,   000          426, 000
Rough River, Ky. (Rough River) 2                      5___       Channel improvement..                           780, 000            4,   000          784, 000
Russell and Allison Levee, Ill. (Wabash                          Levee_----_----             -               3, 830, 000        1, 890,   000       5, 720, 000
   River).
Shawneetown, Ill______                                           Wall and levee...___- _                     1, 810, 000          361, 000          2, 171, 000
Shufflebarger Levee, Ind. (Wabash Levee--------------                                                       2, 380, 000           90, 000          2, 470, 000
   River Basin).
Smithland, Ky..______________________                            Wall and levee .-......                        864, 000          414, 000          1, 278, 000
Sturgis, Ky. (Tradewater River) - ...                            Levee -                                         578, 000          69, 000             647, 000
Sugar-Creek Levee, Ind. (Wabash                               -----    d o ._... .. .. ..-                .     304, 000           27, 000             331, 000
  River).
Taylorsville, Ky.    4      (Salt River).4......... _                  do      -                                373, 050           63,    310          436, 360
Tell City, Ind. ._.___..                         ... ........ Wall and levee---- ..                             897, 661           32,    710          930, 371
T olu, K y...............................                        Levee ......                                   303, 000           35,    000          338, 000
Tri Pond Levee, Ill. (Wabash River)___ -----                           d o ...........           ......         863, 000           70,    000          933, 000
Troy, Ind.....-----------------------                            Wall and levee--__-____                        502,  000         133,    000          635, 000
                         6
Uniontown, Ky.                                                   Levee---                                    1,075, 000            72,    200       1, 147, 200
Utica, Ind............................                            .. .do.....                                1, 570,  000         120,    000       S'1,
                                                                                                                                                       690, 000
Vevay, Ind.. _........_                   -         __---
                                                      2                                                      1, 170, 000          146,    000       '1316, 000
Vincenfnes, Ind. (Wabash River). __...                           Wall and levee_---- ...                     4, 210, 000          285,    000       4 495, 000
West Point, Ky -..                          ..          .       .....do . . -. -                             1, 480, 000          290,    000       1, 770, 000
Westport, Ky_.                          _        __              Wall_                                       1,610, 000            41,    000       1, 651, 000
West TerreHaute, Ind. (Wabash River)                             Levee-                                         383, 000           93,    000          476, 000
Wilder, Ky               _          __----------                 Wall    and    levee      .--....           2, 190, 000          220,    000         410, 000
                                                                                                    I                       !                   I




    1 All projects are located on the Ohio River unless otherwise noted.
   2 Details of this project are given in individual report.
   SSubstitute project for Bellnap, Karnak, and Ullin, Ill.
   4Complete. See Annual Report for 1952 for last report showing details.
  5 Part of Rough River Reservoir and channel improvement project, Kentucky. Details of this project are
given in individual report.
  6 Complete. See Annual Report for 1953 for last report showing details.
946              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                              Reservoirs

                 Tributary basin                                                                                         Total
                  and reservoir                                                  Stream                             estimated cost

Great Miami River:
    Brookville, Ind --------------------..                   East Fork of Whitewater River-----------..                $15, 800, 000
    Metamora, Ind- _                          -       -      West Fork of Whitewater River-..-.._ _-                    35, 300, 000
Green River:
    Mining City, Ky ..........             ..           ..-  Green River .---------------------------                    69,100, 000
    Nolin, Ky......------------------------ Nolin River-----------                                                       14, 300, 000
    No. 2, Barren, Ky----------------------                  Barren River...---------------------------                  19, 323, 000
    No. 2, Green, Ky -....---....                                   River ---------...--.----------------
                                                             G--Green                                                     6, 800000
                                   .
    Rough, Ky.......................                 ... . Rough River-----             -.-------  --------               8, 490,000
Kentucky River:
    Booneville, Ky _                                         South Fork of Kentucky River.-----------                    17, 000 000
    Buckhorn, Ky           .                 ....         .  Middle Fork of Kentucky River             .........          7,020,000
   Jessamine Creek, Ky                             . ..      Kentucky River ----------                  .
                                                                                                    - ------             46, 900,000
Licking River:
    Cave Run, Ky                      .          ...        Licking River -------------------------.                    13, 900, 000
    Falm outh, Ky-----------------------........                 do                    .. ... .. ... .. ..
                                                                         .. ... .. ... .-..                             25, 800 000
Little Miami River:
    Caesar Creek Ohio                          ................--- Caesar Creek----..----------------   -----.           6, 190, 000
    East Fork, Ohio ..                                          . East Fork.------------------------------               9,130, 000
Mill Creek:
fWest   Fork, Ohio'                       r           _      West Fork of Mill Creek.........          -........        2, 981,700
Wabash River:
    Cagles Mill Ind.....            .. ...                    Mill Creek---..-..-------------------------                4, 121, 000
   Mansfield, Ind_              -.....  ....
                                         .           -____-   Raccoon Creek--------------------------                    5,680,000

  1Details of this project are given in individual report.
  'Non-Federal cost is $520,801 additional.
  ' See Annual Report for 1950 for last report showing details.
    Part of Rough River Reservoir and channel improvements project, Kentucky. Details of this project
are given in individual reports.

    Operationsand results during fiscal year.                                              Operations consisted
of surveys, explorations, and engineering studies required for the
preparation of detailed plans and general design memoranda.
   The costs during the fiscal year were $23,074 for new work.
  Condition at end of fiscal year. Surveys, explorations, engineer-
ing studies and preparation of detailed plans were well advanced
on those units in the general comprehensive plan for flood control
in the Ohio River Basin which are under consideration for con-
struction in the near future. The status of projects selected for
construction under this authorization is given in individual re-
ports.
    The total costs to the end of fiscal year were $1,487,178.
                                                 Cost and financial summary




New work:
   Appropriated ...- _.  -$610,000
   Cost-_--------------.    100,440


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954               _      $4,861           --------------
    Appropriated for succeeding fiscal year ending June 30, 1955----- --       70,000
    Unobligated balances, available for succeeding fiscal year ending June 30,
       1955----------       ----------------      ---------------------        74,861
                   FLOOD CONTROL--LOUISVILLE, KY., DISTRICT                                                      947
                   25. INACTIVE FLOOD CONTROL PROJECTS

                                                        For last       Cost to June 30, 1954            Estimated
                                                       full report                                       amount
                 Name of project                            see                                          required
                                                         annual         Con-          Operation             to
                                                          report     struction           and            complete'
                                                           for-                      maintenance
1. Anderson, White River, Ind._........... _             1940            $5, 724...........               $548, 276
2. Brookport, Ohio River Basin, Ill............          1953           592, 522 ......-..-...              14; 978
3. Delphi, Ohio River Basin, Ind., (Wabash               1953           144,563 ..............            (s)
      River).
4. Emergency bank protection (Sec. 14 of the             1952          S106, 816 ..............           (a)
      1946 Flood Control Act).
5. Evansville, Ohio River Basin, Ind....                 1953         2, 227, 556 ...........            8, 872, 500
6: Flood Control Emergencies Repair and flood            1953                               417, 600      ()
      fighting and reserve work. (Sec. 210 of the
      1950 Flood Control Act and supplemental
      authorizations).
7. Gill Township Levee Unit, Wabash River,               1948           561, 200 .............            (3)
      Ind.
8. Golconda, Ohio River Basin, Ill..........             1952            487, 108 ..............          (8)
9. Harrisburg, Ohio River Basin, Ill............         1952            849, 656 .............           (8)
10. Indianapolis, Ind.' ____                   __
                                         ._,____-         1953         1, 859, 363-------
11. Lawrenceburg, Ohio River Basin, Ind.....              1953         2, 433, 414
12. Levee Unit No. 3, East Fork of White River,           1938                 275...........             2, 639, 725
      Ind.'
13. Levee Unit No. 1, Wabash River, Ill.11........        1938                                            3, 230, 000
14. Levee Unit No. 2, Wabash River, Ind.'......           1938                                            2, 920, 000
15. Levee Unit Nos. 3 and 4, Wabash River, Ill.           1938                216...........              6, 469, 784
      and Ind.
16. Levee Unit No. 5, Wabash River Ind.'......            1952            88,368 -- --- -- -              8, 051, 632
17. Levee Unit No. 8, White River, fInd.........          1952           700, 534 ..............           (3)
18. Levee Unit No. 9, White River, Ind........            1939                                                21, 700
19. Levee Unit No. 10, White River, Ind.2......           1939                                               155, 000
20. Logansport, Wabash River Ind. ..........              1939                                            2, 440, 000
21. Lyford Levee Unit, Wabash River, Ind.....             1944           267, 391 ..............           (s)
22. Muncie, Ind................................           1952           880, 652 .............               27,348
23. Orleans, Ind................................          1952             1 922                             309, 000
24. Peru, Wabash River, Ind.2.................            1951                            _
                                                                           1,922...............
                                                                                         -.               7, 258, 078
25. Saylersville, Licking River, Ky.. ...........         1946            12,000 ............                604, 000
26. Shoals, East Fork of White River, Ind.2.....          1938                                               543, 000
27. Small Flood Control Projects not specifically         1953            70, 304 .............            (s)
      authorized by Congress (Sec. 212 of the 1950
      Flood Control Act).
28. Snagging and clearing of navigable streams
      and tributaries in the interests of flood con-
                                                          1953            26,569     --    ..     .        (s)
      trol (Sec. 13 of the 1946 Flood Control Act).
29. Taylorsville, Ohio River Basin, Ky. (Salt
      River).
                                                          1952          6 373, 050   -............         (')
30. Tell City. Ohio River Basin, Ind............          1952           897, 661-.............            (a)
31. Terre Haute, Wabash River, Ind.7...........           1938                                               199, 000
32. Uniontown, Ky_............................            1953         1,066, 506 ..............               8, 494
33. Wabash, Wabash River, Ind.2..............             1938       ..............---.....-.-....           872, 000

  1Revised   in 1954.
  2 Awaiting local cooperation.
  s Completed.
  ' Partially completed. Awaiting local cooperation.
  5Partially completed. Remaining construction suspended.
  6 In addition, contributed funds in the amount of $5,000 were expended.
  7 Partially completed by Works Progress Administration.

                             26. GENERAL INVESTIGATIONS

   Examinations and surveys. The cost for examinations and
surveys for the fiscal year amounted to $27,351. Funds available
in fiscal year 1955 will be applied to the preparation of 1 naviga-
tion study (survey) and 6 flood control studies (5 surveys-i pre-
liminary examination).
   Collection and study of basic data. Collection and study of
basic data during the year consisted principally of annual revision
of the flood emergency plan, miscellaneous hydrologic studies re-
lating to river and harbor flood control work, and study of stream
gaging equipment program. Cost for the fiscal year was $8,482.
Funds available in fiscal year 1955 will be applied to the collection
and study of basic data.
948            REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

       27. INSPECTION OF COMPLETED                             FLOOD CONTROL WORKS
   The Flood Control Act approved June 22, 1936, and subsequent
acts require local interests to furnish assurances that they will
maintain and operate certain local protection projects after com-
pletion in accordance with regulations prescribed by the Secretary
of the Army. District engineers are responsible for the adminis-
tration of these regulations within the boundaries of their respec-
tive districts. The (1953) estimate of the annual cost of this work
in the Louisville District is $16,000.
   Maintenance inspections were made during the fiscal year of
completed units of 25 projects transferred to local interests for
maintenance and operation. Local interests were advised, as neces-
sary, of measures required to maintain these projects in accord-
ance with standards prescribed by the regulations.
   The cost during the fiscal year was $13,605 for maintenance.
The total costs to the end of the fiscal year were $51,838, all for
maintenance.
                                      Cost and financial sumn'lary

                                             Fiscal year ending June 30                         Total to June
                                                                                               30, 1954, includ-
                                                                                               ing fiscal years
                               1950         1951        1952         1953           1954        priorto 1950


Maintenance:
   Appropriated .....------------------..   $11, 500    $12, 000    $16, 000        $14, 700            $54, 200
   Cost-----------------.........            10,964      11,456      15,812          13,605              51,837


28. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
   Flood Control Emergencies--Repairand flood fighting and res-
cue work. (Sec. 210 of the 1950 Flood Control Act and supple-
mental authorizations.)
   Operations during the fiscal year consisted of completion of con-
struction of emergency repairs performed by contract to the
Greenfield Bayou Levee, Wabash River, Ind., which were made
necessary by caving banks.
   The costs during the fiscal year were $6,460 for maintenance
work.
                                      Cost and financial summary

                                             Fiscal year ending June 30                        Total to June
                                                                                               30, 1954, includ-
                                                                               SI              ing fiscal years
                              1950          1951        1952        1953            1954         prior to 1950

Mair
       IMPROVEMENT OF RIVERS AND HARBORS IN THE
              HUNTINGTON, W. VA., DISTRICT
   This district embraces those portions of the States of Ohio, Ken-
tucky, West Virginia, Virginia, North Carolina, and Pennsylvania
lying in the drainage basins of the Ohio River and tributaries, from
about mile 109 between Captina Island and Powhatan Point, Ohio,
to about mile 409.3 immediately downstream from Aberdeen, Ohio,
a distance of about 300.3 miles, including the following streams im-
proved for slack-water navigation: Ohio River, with its locks and
dams 14 to 23, inclusive, Gallipolis locks and dam, and locks and
dams 27 to 33, inclusive; Muskingum River, Ohio; Little Ka-
nawha River, W. Va.; Kanawha River, W. Va., Big Sandy River, W.
Va., and Ky., including Levisa and Tug Forks.
                                            IMPROVEMENTS

                     Navigation                                   Flood Control-Continued
                                                 Page                                                   Page
1.   Construction of locks and dams,                       13. Bluestone         Reservoir,        Ohio
        Ohio River .... .... .........                  949       -River Basin, W. Va.......... 967
2.   Ohio River open channel work..                    949 14. Sutton Reservoir, Ohio River
3.   Muskingum River, Ohio.....                        949        Basin, W. Va ........        ......       969
4.   Kanawha River, W. Va............                  952 15. Huntington, Ohio River Basin,
5.   Inactive navigation projects ..                   956        W . Va.........           . ....... 970
                                                            16. Dewey Reservoir, Ohio River
                     Flood Control                                 Basin, Ky                   ......        971
                                                            17. Ashland, Ohio River Basin, Ky__              972
6.   Massillon, Ohio River Basin,                          18. Portsmouth-New Boston, Ohio
        O hio ... .... .... .... .... .... .... .... .. 956        River Basin, Ohio............             973
7.   Muskingum River Reservoirs,                           19. Delaware Reservoir, Ohio River
        O hio ............. ............. ............  958        Basin, Ohio               .      _...     974
                                                                                                    ....-.....
8.   Newark, Ohio River Basin,                             20. Maysville, Ohio River Basin,
        Ohio .            -                             962        K y. ..                            ...... 975
                                                                                 ... ........... ......
9.   Dillon Reservoir, Ohio River                          21. Ohio River Basin, Huntington
        Basin, Ohio..........                           962        District .. ....    ...................   977
10.   Roseville, Ohio River Basin,                          22. Inactive flood control projects_             981
        O hio - - - - - - - - - --..........--          963 23. General Investigations ...                   981
11.   Parkersburg, Ohio River Basin,                        24. Inspection of completed proj-
        W. Va ......................................    964        e c ts ...........                  .... 981
                                                                                                 .- ....-
12.   Tom Jenkins Reservoir, Ohio
        River Basin, Ohio. __. __......                 965

         1. CONSTRUCTION                OF LOCKS AND DAMS, OHIO RIVER
      For report on this improvement, see page 869.
                      2. OHIO RIVER OPEN CHANNEL WORK
      For report on this improvement, see page 875.
                              3. MUSKINGUM               RIVER,        OHIO
      Location.        The Muskingum River, 112.45 miles in length, and
lying entirely in the State of Ohio, is formed by the junction of the
Walhonding and Tuscarawas Rivers at Coshocton,' Ohio, flows in a
southerly direction and empties into the Ohio River at Marietta,
Ohio, 172.2 miles below Pittsburgh, Pa.
                                                                                               949
950               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Existing project. This authorized the taking over, restoration,
maintenance, and operation of the State works and plant to provide
slack-water navigation between lock 1, at Marietta, Ohio, and
Dresden, Ohio, a distance of 92.85 miles. Navigation is afforded by
11 locks and dams and 4 short lateral canals. The maximum depth
which it is now possible to maintain without extensive improve-
ment is 4.5 feet, although in certain portions 5.5 feet is available.
Above the site of the old lock 11 the minimum depth actually main-
tained is 2 feet. The navigable depth between lock 1 and the mouth,
a distance of 0.25 mile, is provided by dam 18, Ohio River; and by
dredging.
   The original estimate of cost of restoring the dams taken over
from the State of Ohio was $200,000. To this was added later the
construction of a new lock and dam 11, at a cost of about $143,000,
the repair and extension of a levee at dam 10, and some minor
work, the net total expended from specific appropriations having
been $301,912. The construction of a new lock 1 was done in con-
nection with the construction of an ice harbor as part of the Ohio
River improvement and was not a part of this project. Operating
and care of the locks and dams were included in the project July 1,
1935, under the provisions of the Permanent Appropriations Repeal
Act approved June 26, 1934. An index map of Muskingum River is
printed in House Document 251, 78th Congress, 1st session.
  The existing project was authorized by the following river and
harbor acts

       Acts                        Work authorized                                     Documents


Aug.    5, 1886   For taking over from the State of Ohio the locks and    H.    Ex. Doc. 48, 49th Cong., 1st
                   dams then in existence (1 to 10) and the restoration        sess. (Annual Report, 1886, p.
                   of these works by the United States.                        1551).
Mar.    3, 1905   Construction of lock and dam 11 and the extension of    H. Doc. 241, 58th Cong., 2d sess.
                   the levee at lock 10 and for other work of minor
                   importance.
June 26, 1934     Operation and care of locks and dams provided for
                   with funds from War Department appropriations
                   for rivers and harbors.

  ' Permanent Appropriations Repeal Act.

  The following table gives the characteristies of the' locks and
dams:
                                                                                                                   Mi ukingum River


                                                                                            Lock                                                                                   Dam
                                        Li                                                                                                                                                                                                     -4
                                                           Dimensions
Lock                                                                          Upper         Lower                                                                                                                    When
and         Location (nearest                                                  sill          sill                                                                                                                    com-          Total
dam          town, all in Ohio)          Miles                      Great-    below         below          Lift                                                                          Type of construction        pleted          cost 1
                                          from            Width       est     upper         lower         (feet)                   Foundation                      Foundation              (all fixed dams)
                                         mouth            (clear)   avail-     pool          pool
                                                           (feet)    able      (feet)        (feet)
                                                                    length
                                                                     (feet)
       SI                                             I                I                I             r   -            -   -   -   -   -   -   -   -                                1                            1     - -
                                                                                                                                                                                                                       I-     1 -    --   -
                                                                                                                                                                                                                                               -4
  1
  2
            M arietta     -___.
            Devols.............
                                ..__-         0.25
                                              5.79
                                                            55. 8
                                                            35. 8
                                                                     179
                                                                     160
                                                                                7.58
                                                                                6.00
                                                                                       11.56
                                                                                        5.56
                                                                                                               4.292
                                                                                                              10. 76
                                                                                                                        Piles in sand and gravel_ Sand and gravel ........ Rock-filled timber crib__
                                                                                                                        Rock       -................... Rock................        .... do....----------------
                                                                                                                                                                                                                      1890 a $327, 500
                                                                                                                                                                                                                      1840     91, 000         z
  3         Lowell ______
                      -                      13. 60         35. 8    160        7.07    5.91                  14. 19    Piles in gravel-. .......            do........- --         ..... do.....-----------          1840    --
                                                                                                                                                                                                                              160,000
  4         Beverly 4..........              24. 60         35. 2    160        6.00    5. 61                  9.32     Gravel ............              Rock and gravel_----_-_ .... do....---------------.          1840    122, 000
  5         Luke Chute.--------              34. 12         35. 8    160        6.00    5. 66                 10. 76    Rock....------                  .....do ......     ....... __do....----------------
                                                                                                                                                                                       .                              1840     91, 000         H
  6         Stockport-..........             40.17          35. 8    160        6.00    5.20                  12. 33        do .. .. ..
                                                                                                                       -.....                     - ---  Rock .......    . ...    . -.-- do---------------..       . 1840      88,000          z
                                                                                                                                                                                                                                               0J
  7
  8
            McConnellsville 4. _
            Rokeby lock-........
                                             49. 40
                                             57. 45
                                                            35. 8
                                                            35. 9
                                                                     160
                                                                     160
                                                                                6.01
                                                                                8.00
                                                                                        5.43
                                                                                        5. 55
                                                                                                              10.10
                                                                                                              10. 96
                                                                                                                        ...do___
                                                                                                                        Piles and grillage .......
                                                                                                                                                         Rock and gravel....... ..... do.....---------------- 1840
                                                                                                                                                         Piles in sand and gravel. .... do ..----------------         1840
                                                                                                                                                                                                                              127, 000
                                                                                                                                                                                                                               90, 000
                                                                                                                                                                                                                                               zH
                                                                                                                                                                                                                                               rd

  9         Philo..............              68.56          35.8     160        8.00    5.22                  11.01     R ock ...................        Rock ------------------    -.. do-.....         -........ -. 1891 5   86, 000
10         Zanesville 4 e-....              76. 60         35.4     156.5      6.30  1 7.09                  15.43     Rock and gravel --._ . .. Soft rock.....--------              .. do..--------------1840               127, 000
                                                                     158. 5            12.30
11                                                                             8.96                          11.757
            Ellis .. . .- -         .        85. 92         36.0     160
                                                                              l4.96
                                                                                     }6.67
                                                                                              1                7.758 }Piles in sand and gravel_        (0)...--.        ........                -------------- 1910 10
                                                                                                                                                                                        Concrete_                                   143, 285   -4
                                                                                                                                                                                                                ------ --                      H
   1Cost to the United States, $301,912, exclusive of cost of lock and dam 1, which was     6 Double lock; flight of 2 tandem.                                                                                                                 -4
constructed under the Ohio River project.                                                   7 Dam equipped with Boule movable-crest gates, 4 feet high.
   2Normal lift above normal pool of dam 18, Ohio River. Lock 1 has intermediate gate;     S Crest of fixed part.                                                                                                                              0
only lower chamber usable.                                                                  9 150 feet of dam aljacent to lock on piles in sand and gravel. Remainder of dam, in-                                                              Hf
   s Replaced an older look on opposite side of river.                                   eluding pier and abutment, on rocks.
     Lateral canal between dam and lock.                                                   10Replaced an older lock and dam located 2.6 miles farther upstream.
   a Replaced an older lock constructed in 1840 at lower end of lateral canal, which was
also abandoned.
952            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Local cooperation. Fully complied with.
   Terminal facilities. One yard for unloading sand and gravel is
situated at mile 0.2. The terminal facilities are considered adequate
for existing commerce.
   Operationsand results during fiscal year. Operation and main-
tenance, general: Lock and dam 1, only, was operated by the Fed-
eral Government to meet the needs of existing commerce. The cost
of maintenance during the fiscal year was $8,856.
   Condition at end of fiscal year. The existing project was com-
pleted in 1910. The locks and dams are in fair to poor condition.
General commercial navigation on the waterway has declined to
the extent that Federal expenditures for continued operation of
this waterway is no longer justified. Accordingly, operations at
locks 2 to 11, inclusive, were discontinued as of midnight June 30,
1952, while operations at lock 1 were discontinued as of midnight
June 30, 1954, and all locks placed in a standby status. Lock and
dam 10 is being operated and maintained by the city of Zanesville
in connection with utilizing the waters of the river as a source of
water supply. The channel is not being maintained. For details of
locks and dams, see table under paragraph "existing project." The
total Federal cost under the existing project to the end of the fiscal
year was $2,478,210, of which $301,912 was for new work, and
$2,176,298 was for maintenance. In addition, the sum of $3,995,356
was expended between April 7, 1887, and June 30, 1936, on the
operation and care of the works of improvement under the provi-
sions of the permanent indefinite appropriation for such purposes.
Also, in addition $5,663 for operation and care was expended from
contributed funds.
                                         Cost and financial summary

                                                   Fiscal year ending June 30                          Total to June

                                  1950        1951            1952        1953
                                                                                               1ing
                                                                                              1954
                                                                                                       30, 1954, includ-
                                                                                                           fiscal years
                                                                                                        prior to 19501


New work:
   A ppropriated   .....   .--                                              I                                  $301912
   Cost--              -------                --                            --------------.                     301,912
Maintenance:
   Appropriated ... - --         $151, 900   $271, 100 -$157,818         $275, 500            $9,300          6 175 368
   Cost--.   -----                 107,117    100,012      69,037         280,862              8,856          6,171,654


1In addition $5,663   for maintenance was expended from contributed funds.


                                 4. KANAWHA RIVER, W. VA.
   Location. This river, 97 miles in length, is formed by the junc-
tion of the New and Gauley Rivers, a short distance above Kanawha
Falls, W. Va., flows in a general northwesterly direction, and
empties into the Ohio River at Point Pleasant, W. Va.
   Previous projects. The original project was adopted by the
River and Harbor Act of March 3, 1873, and modified by the River
and Harbor Act of March 3, 1875 (Annual Report for 1875, pt. 2,
pp. 90-98). For further details see page 1913, Annual Report for
1915, and page 1309, Annual Report for 1938.
  Existing project. The existing project provides for three dams
on the Kanawha River, with twin locks having usable dimensions
              RIVERS AND HARBORS-HUNTINGTON,                               W. VA., DISTRICT              953
of 56 by 360 feet, and one dam on the Ohio River near Gallipolis,
Ohio, with one lock 110 by 600 feet and one lock 110 by 360 feet, to
furnish a 9-foot navigable depth from the mouth to a point 90.57
miles above.
   The cost for new work for the existing project as completed was
$22,872,770. The latest (1954) approved estimate for annual cost
of operation and maintenance is $406,000.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                         Work authorized                                    Documents


July     3, 1930   Replacement of old locks and dams 2 to 5, inclusive,     H. Doc. 190, 70th Cong., 1st sess.
                    by construction of 2 new dams and dredging.
June 26, 19341     Operating and care of locks and dams provided for
                    with funds from War Department appropriations
                    for rivers and harbors.
Aug. 30, 19352     Replacement of old locks and dams 6 to 11, inclusive,    H. Doc. 31, 73d Cong., 1st sess.3
                    by construction of 1 new dam on the Kanawha
                    River and 1 new dam on the Ohio River below
                    mouth of the Kanawha River, and pertinent work.

  1   Permanent Appropriations Repeal Act.
  2   Included in the Public Works Administration program Sept. 6, 1933.
  3 Contains latest published maps.

  The following table gives the characteristics of the locks and
dams:
                                                                                           Kanawha River

                                                                 Lock                  Available depth
                            Location                          dimensions               over miter sills
                                                                                       at normal pool
                                                                                         levels
                                                             'Great-        Lift at                                                                                                             Year
                                                                est         normal                            Character of                                 Type of construction                   of       Cost of      M
   Lock                                          Dis-         avail-         pool                             foundation              Kind of dam                of dam                         com-     locks and
                                                tance          able  Width levels                                                                                                              pletion      dams 1
                     Nearest town              above         length  (feet)  (feet) Upper Lower
                                               mouth             of                 (feet)     (feet)
                                               (miles)        cham-                                                                                                                                                     0
                                                                ber
                                                              (feet)
                                                                                                                                                                                                                        C)
London 2... London, W. Va ----------........    82.76           360       56      24       18       12 Rock      .....----------...Roller gates-..... Concrete movable crest.                   1934     $3, 269, 828
Marmet 2._ Marmet (Belle), W. Va...__           67.75           360     456       24       18       12 ..... do...........          ..... do-.........._ ... do  -                 -.................
                                                                                                                                                                                                1934      3, 565, 947
Winfield 2._ Winfield (Red House),              31. 12          360     4 56      28       18       12 ..... do-.....-.........do--...............do .................                          1937      6,340, 076
              W. Va.                                                                                                                                                                                                    0
Gallipolis    Gallipolis, Ohio-----------        ()      (      360     110       26       18       12         do.....do...........     do...       ....     do.................                1937      9, 696,919

                                                                                                                                                                                                                        z
  1 Includes cost of flowage easements.                                                                   s 14 miles below Point Pleasant, W. Va., on the Ohio River.
  2Hydroelectric   plant, licensed by Federal Power Commission, at this site.                             4Two locks each, 56 feet by 360 feet.                                                                         z



                                                                                                                                                                                                                        +1,
                                                                                                                                                                                                                        0s
      RIVERS AND HARBORS-HUNTINGTON,        W. VA., DISTRICT     955
   Local cooperation. Under license 1175, issued by the Federal
Power Commission, the Kanawha Valley Power Co. has con-
structed hydroelectric plants at London and Marmet locks and
dams, a license fee of $32,000 per annum having been fixed for each
site. The Kanawha Valley Power Co. has also constructed a hydro-
electric plant at Winfield locks and dam, under license 1290, a
license fee of $40,000 per annum having been fixed.
   Terminal facilities. The public terminal facilities consist of a
paved landing at Charleston, W. Va. Numerous coal tipples, owned
by private interests, exist, available for use only to the owners for
loading into barges the coal mined by them. Other privately owned
facilities are as follows: Two coal unloading terminals at Belle, 1
at Glasgow and 1 at Cabin Creek; 11 gasoline and oil unloading
stations at Boomer, Cabin Creek, Charleston, North Charleston,
South Charleston, and St. Albans; 2 docks at Nitro for handling
acid; 2 docks at South Charleston and 1 at Nitro for unloading
sulphur; 9 terminals at Belle, North Charleston, South Charleston,
and Institute for handling chemicals; a terminal at Alloy generally
used for unloading coke; 1 dock each at Riverside and Sattes for
handling scrap metal; and a sand and gravel unloading terminal
at Charleston. The terminal facilities are considered adequate for
existing commerce.
   Operations and results during fiscal year. New work: The
audit of real estate acquisitions in the Marmet and Winfield pools
was completed. This concluded, in all respects, work authorized
under, the paragraph "existing project."
   Operation and maintenance, general. The locks and dams were
operated as required, and necessary repairs and improvements
were made thereto, and to the appurtenant structures and grounds.
Channel work consisting of periodic inspections and snagging oper-
ations was conducted as required and miscellaneous administrative
functions pertinent to navigation were carried on throughout the
year.
   The total cost for the fiscal year, all from regular funds, was
$463,156, of which $152 was for new work and $463,004 was for
maintenance.
   Condition at end of fiscal year. Construction of the existing
project was commenced in 1931 and completed in 1937. At the end
of fiscal year 1954, all flowage easements required had been pro-
cured, final records and reports had been prepared, and the exist-
ing project was complete in all respects. All structures are in oper-
ation and available depth for navigation is 9 feet from the mouth
of the river to the head of the improvement. Above the improved
portion of the river, the minimum depth in the channel is less than
1 foot. For details of the locks and dams, see table under paragraph
"existing project."
 956              REPORT          OF CHIEF OF ENGINEERS, U.                                S. ARMY, 1954


   The total cost, all funds, to the end of the fiscal year for the
existing project was as follows:

                  Class of work                        Regular           Public works            Emergency                    Total
                                                        funds               funds                Relief funds


New work _ _.__-.       .----      .    ..------$9,369,334                   $9, 004,800            $4, 498,636              $22, 872,770
Operation and maintenance, general   -..-        4,499, 625            .         ------------                                  4,499, 625

         Total         .......
                      ____________________    ...      13,868,959             9,004,800              4,498,636                27, 372, 395



       In addition, surplus property valued at $4,546 was transferred
to the project without reimbursement.
  In addition, the sum of $5,159,879 was expended between July
1884, and June 30, 1936, on the operation and care of the work of
improvement under the provisions of the permanent indefinite ap-
propriation for such purposes.
                                           Cost and financial summary

                                                    Fiscal year ending June 30                                     Total to'June
                                                                                                                   30, 1954, includ-
                                                            .                                                      ing fiscal years
                                    1950        1951              1952              1953             1954            prior to 19501


New work:
   Appropriated-          --     -$320, 000   -$80, 000 ..-----------            -$10,900        ..------------          2   $27, 167, 382
   Cost.-------------               -1,229          5,490          $3,399                  343           $152                227,167,382
Maintenance:
       Appropriated                326, 000     293,400           285, 500         320, 314          461,100                   9, 692, 433
       Cost ...--                  346,502      303797            288,117          309, 246          463,004                   9,659, 504


      Includes $4,294,612 for new work and $3,883,513 for maintenance for previous projects.
     2 Includes $4, 498, 636 Emergency Relief funds and $9, 004,800 Public Works funds.
     3 In addition, surplus property valued at $4,546 was transferred to the project without reimbursement.

                               5. INACTIVE NAVIGATION                            PROJECTS

                                                             For last           Cost to June 30, 1954                    Estimated
                                                            full report                                                   amount
                   Name of project                               see                                                      required
                                                              annual             Con-             Operation                  to
                                                               report         struction              and                 complete
                                                                for-                             maintenance
1. Big Sandy River, W. Va. and Ky., including    1952      $1, 586, 236                           1 $1, 471, 299                (2)
     Levisa and Tug Forks
2. Elk River, W. Va__ . __________ __________    1903           30, 259                                                         (3)
3. Gauley River, W. Va           ..--... .        903.1.761.. 14,761
                                                 1903                                                                -          (4)
4. Guyandot River, W. Va ...........      -..... 1915
                                         -..                    27,500                           --------------                 (5)
5. Little Kanawha River, W. Va                   1952
                                      ............--          470, 536                                 891, 354                 (6)
6. New River, Va. and W. Va .....                               1899                109, 691                ..                  (5)
7. Scioto River at Portsmouth, Ohio ..                          1953                 10, 951             16, 593              ' $129, 049

  1 In addition, funds in the amount of $27,523 were contributed by local interests for maintenance of Lock
No. I during fiscal years 1953 and 1954.
  2 Operation and maintenance of the project except Lock 1 suspended June 30, 1951. Dam 1, Big Sandy
River being operated for high water navigation, the costs being reimbursed by local interests.
  $ Work closed September 1902. Property transferred to Kanawha River improvements.

  4 Work closed September 1902. Abandonment recommended in H. Doc. 467, 69th Cong., 1st sess.
  5Work suspended.
  6 Operation and maintenance suspended June 30, 1951.
    Monetary limitation of authorizing act is $75,000.

                       6. MASSILLON,            OHIO RIVER BASIN,                                 OHIO
  Location. Massillon, Ohio, is located in Stark County, on the
Tuscarawas River, 200 miles above the mouth of the Muskingum
River.
          FLOOD CONTROL-HUNTINGTON,       W. VA., DISTRICT       957
    Existing project. The project providing for improvement of
the channel of the Tuscarawas River, together with the construc-
tion of drainage facilities, levees and pump stations, consists of
the following features: 12,800 linear feet of channel rectification
and improvements; 4,300 feet of new channel; 2 reinforced con-
crete pressure conduits with a total length of 4,300 feet; 15,900
feet of earth levee; 200 feet of concrete wall; 4 pump stations;
and 3 gate openings. The project necessitated the relocation of 6
miles of railroad; the construction of 5 railroad bridges, railroad
terminal facilities, 1 highway bridge, and 2 highway viaducts; the
removal of 3 railroad bridges, 1 highway bridge and 10,550 feet of
railroad track; and the raising of 1 highway bridge. The project
provides protection (with 3-foot freeboard) against a flood with
peak discharge 20 percent greater than maximum of record. The
existing project was selected for construction under the general
authorization for the Ohio River Basin, contained in the Flood
Control Act approved June 28, 1938. The estimate of cost for new
work (1954) is $8,617,300, which includes a contribution of $477,-
800, by local interests, for additional construction and alterations
beyond the scope of the authorized Federal project. The latest
 (1953) approved estimate for annual cost of maintenance is $5,000.
    Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
    Operations and results during fiscal year. New work: Work
in connection with the acquisition of land was continued and as-
sistance was given the Department of Justice in the condemnation
proceedings involving the acquisition of third party interests in
certain railroad lands. Drawings showing "as-built" conditions
were prepared.
    Operation and maintenance, general. Routine inspections of the
improved channels were conducted and remedial work was per-
formed as required to maintain the channel in a satisfactory con-
dition.
    The total cost was $13,391, of which $5,772 was for new work
and $7,619 was for maintenance.
    Condition at end of fiscal year. The project, construction of
which was initiated in July 1940 and suspended during the war
years, was completed for beneficial use in October 1951. The drain-
age structures and appurtenances including pressure conduits, gate
openings, and pump stations have been turned over to the city for
maintenance and operation. The improved channels and levees,
maintained by the United States, are in good condition. Work re-
maining to complete the project consists of acquiring one tract of
land from the Ohio Water Service Co., the acquisition of which is
covered in a relocation agreement, and involves the conveyance of
certain waterline easements to the company over Government
lands. The conveyance to the company is being held in abeyance
pending completion of condemnation proceedings for acquisition
of third party interests in 31 railroad tracts. The entire project is
about 99 percent complete. The total cost to the end of the fiscal
year was $8,140,930, of which $8,132,638 was for new work and
$8,292 was for maintenance. In addition, $477,813 for new work
was expended from contributed funds.
958             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                           Cost and financial summary

                                                        Fiscal year ending June 30                     Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                                    1950            1951         1952         1953           1954       prior to 19501

New work:
   Appropriated         _       $1, 860, 000       $624, 800     $27, 000   -$52, 600   -                   $8, 139, 473
   Cost-----..... -              1, 760,163       1,233,967      369, 328      16,637        $5, 772         8,132,638
Maintenance:
   Appropriated                      ------------------------      5,000        5,000         -300                9,700
   Cost _.....-----------------------                                446          227         7,619               8,292

1In addition $477, 813 for new work was expended from contributed funds.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_------------        $4,535
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955           --------------------------------------                    4,535

                      7. MUSKINGUM                    RIVER RESERVOIRS,                     OHIO
   Location. The Muskingum River lies in southeastern Ohio and,
with its tributaries, drains approximately 8,000 square miles. Its
headwaters rise about 25 miles south of Lake Erie and it flows
into the Ohio River at Marietta, Ohio, 172.2 miles below Pitts-
burgh, Pa.
   Existing project. This project provides for the construction,
operation, and maintenance of 14 reservoirs and appurtenant works
in the Muskingum River Basin. It was originally authorized by the
Public Works Administration February 20, 1934, to include 15 res-
ervoirs as set forth in an official plan prepared by the Corps of En-
gineers and adopted by the Muskingum watershed conservancy
district of Ohio, the sponsoring agency. Subsequent amendments
to the official plan provided, among other things, for the elimina-
tion of one reservoir and the inclusion and later elimination of a
project for channel improvement of the Tuscarawas River at Mas-
sillon, Ohio. Allotments totaling $27,190,000 were made from:De-
cember 1933 to July 1937 by the Public Works Administration to
aid in financing construction of this project. The project was oper-
ated and maintained by the conservancy district from July 1938 to
August 1939 when it was taken over by the Corps of Engineers for
maintenance and operation in accordance with the provisions of
the Flood Control Act approved August 11, 1939.
   The Flood Control Act approved June 28, 1938, authorized and
directed the Secretary of War to reimburse the conservancy dis-
trict a sum not to exceed the actual expenditures made by it in
acquiring lands, easements, and rights-of-way for reservoirs in the
Muskingum River Valley, such reimbursements not to exceed
$4,500,000, nor include any expenditures for lands, easements, and
rights-of-way heretofore or hereafter purchased from said district
by the United States. The first allotment under this authorization
was made June 29, 1939, from the War Department Appropriation
Act of June 28, 1939.
   The Flood Control Act approved August 11, 1939, contained the
provisions that the Muskingum River reservoirs be included in the
flood control plan for the Ohio River Basin authorized in the Flood
Control Act approved June 28, 1938; that section 2 of the latter act
          FLOOD CONTROL--HUNTINGTON,      W. VA., DISTRICT       959
apply to those reservoirs; and that the conservancy district be re-
lieved of any obligation to maintain and operate the dams.
   The Flood Control Act approved July 24, 1946, authorized such
channel rectification works or other measures at or below the Mus-
kingum River reservoirs as in the discretion of the Chief of Engi-
neers and the Secretary of War may be found necessary to provide
for the most efficient operation of those reservoirs, at an estimated
cost of $2,200,000.
   The estimate of cost for new work (1954), excluding the cost to
the Muskingum Watershed Conservancy District, is $40,630,000,
of which $18,561,900 is for construction and $22,068,100 is for
lands and damages. The latest (1954) approved estimate for an-
nual cost of maintenance is $238,000. For further details see
Annual Report for 1946, page 1734.
   The following table gives the principal features of the 14 reser-
voirs:




     Sig 31-959-990
                                                                                                               Muskingum River Reservoirs                                                                                                        0

                                                                                                                                                    Reservoir                                                    Estimated cost

                                                                                                                                     Elevations,                          Capacity
             Name of                                                                  Location of dam                               mean sea level
No.          reservoir 2                         Stream                                (nearest town,                    Drain-
                                                                                        all in Ohio)                    age area                                                                                                                 0
                                                                                                                                                                                                    Con-          Lands and        Total         O


                                                                                                                        (square                Conser-                    Water                   struction        damages
                                                                                                                         miles)    Spill-      vation          Flood      conser-   Total
                                                                                                                                   way          pool          control     vation (acre-feet)                                                     C
                                                                                                                                                                                                                                                 0
                                                                                                                                                            (acre-feet) (acre-feet)                                                              0
                                                                                                                                                                                                                                                 3-

  1   Atwood.......----------          Indian Fork__...__...__        _ New Cumberland.---.                70                         941          928         26, 100      23, 600     49, 700     $517, 100       $822, 600     $1, 339, 700
  2   Beach City...--..--.             Sugar Creek ._________.. Beach City______ ____                     300                         976. 5       948         70, 000       1, 700     71, 700    1, 331, 600     2, 086,200      3, 417, 800
  3   Bolivar...._______........       Sandy Creek-...........          Bolivar---------------            502                         962          895        149, 600            0    149, 600    2, 884, 100     2, 949, 800     5,833, 900
  4   Charles Mill........             Black Fork.___________. Mifflin....----------------                216                      1, 020          997         80, 600       7,400      88, 000    1, 479, 700        893,200      2, 372, 900
  5   Clendening..--...        _       Brushy Fork-...          .-..    Tippecanoe                     ----.....
                                                                                                           70                         910. 5       898         27, 500      26, 500     54, 000       626, 000        464,100      1, 090, 100   z
  6   Dover..............              Tuscarawas River ......          Dover----_______-_ --          1, 397                         916          874        202, 000       1, 000    203, 000    2, 053, 600     5, 617,500      7, 671, 100
  8   Leesville .........              McGuire Creek-....               Leesville _______ ____             48                         977. 5       963         17, 900      19, 500     37, 400       719, 200        216, 100        935, 300
  9   Mohawk.......---------.          Walhonding River-..._.           Nellie______..-___-___       4 1, 501                         890          799. 2     285,000             0    285, 000    2,620, 200      2, 448,900      5, 069, 100
10   Mohicanville ...-.               Lake Fork---________ Mohicanville____ -__                          269                         963          932        102, 000            0    102, 000       589, 500        667000       1,256,500     w
11   Piedmont _-........              Stillwater Creek        ..-----  Piedmont .......       _ ___       84                         924. 6       913         31, 400      33, 600     65,000     1, 268, 100        564,600      1,832,700
12   Pleasant Hill--     ....         Clear Fork..----_______ _ Perrysville ------------                 199                      1, 065       1, 020         74, 200      13, 500     87, 700    1, 342, 300        723,700      2, 066, 000
13   Senecaville_ -- __               S eneca Fork ....            . Senecaville ------------            121                         842. 5       832. 2      45, 000      43, 500     88, 500       648,100      1, 085, 800     1, 733, 900
14   Tappan----------..        ...    Little Stillwater Creek__ Tappan_-............                      71                         909          899. 3      26, 500      35, 100     61, 600    1, 246, 800     1, 912,200      3,159, 000    z
15   Wills Creek--.. _          ..    Wills Creek. ___         ...__   Conesville                   -------------
                                                                                                        5844                          779          742        190, 000       6, 000    196, 000    1, 235,600      1, 616, 400     2, 852, 000
                                                                                                                                                                                                                                                 00
              Total....           .........     ----------------- ---------------------------------------------------                                       1, 327, 800    211, 400 1, 539, 200   18,561,900      22,068,100      40,630,000
                                                                                                                                                                                                                                                 00
  2The construction of Freeport Dam QNo. 7) was eliminated by the amended official                                                  S 777 square miles net area.
plan approved by the Chief of Engineers, May 16, 1935.
  2 For details of individual dams, see p. 1256, Annual Report 1942.
                                                                                                                                    45 817 square miles net area.
                                                                                                                                       723  square miles net area.




                                                                                                                                                                                                                                                 ca

                                                                                                                                                                                                                                                 c3n
                 FLOOD CONTROL--HUNTINGTON, W. VA., DISTRICT                                                  961
    Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies to this project, subject to certain provisions
contained in the Flood Control Act approved August 11, 1939. For
further details see Annual Report for 1942, page 1257.
    Operations and results during fiscal year. New work: Work
in connection with the acquisition of flowage easements was con-
tinued and 4 tracts were acquired during the year.
    Operation and maintenance, general: The 14 reservoirs were
operated as required to reduce local flooding and necessary repairs
were made to the structures and appurtenances. The total cost, all
from regular funds, was $252,101, of which $43,647 was for new
work, and $208,454 was for maintenance.
    Condition at end of fiscal year. Construction of the project
was initiated in January 1935. With the completion of the Dover
Reservoir in November 1938, all of the 14 flood control dams, in-
cluded in the project, were completed and in operation. The major
items of presently authorized work remaining to be done consist
of completing acquisition of flowage easements, and remedial
work in the channel downstream from the Charles Mill Dam. Work
in connection with the acquisition of land was in progress and of
the 4,730 tracts authorized for acquisition, excluding the Charles
Mill project, 4,707 tracts have been acquired. Neither the con-
struction nor the acquisition of lands or easements have been ini-
tiated for the channel remedial work below Charles Mill Dam.
Work presently authorized for this project is about 97 percent com-
plete. The costs to the end of the fiscal year were as follows:
    Regular funds: $14,695,199, of which $12,372,255 was for new
work, and $2,322,944 was for maintenance.
    National Industrial Recovery funds: $27,190,000 for new work.
    The total cost, all funds, was $41,885,199, of which $39,562,255
was for new work and $2,322,944 was for maintenance. In addi-
tion, surplus property valued at $4,109 was transferred to the
project without reimbursement.
                                      Cost and financial summary


                                                   Fiscal year ending June 30                      Total to June
                                                                                                   30, 1954, includ-
                                                                                                   ing fiscal years
                               1950             1951        1952          1953          1954        priorto 1950

New work:
   Appropriated-...__       $1, 391, 500       $250, 000   $472,000    -$276, 000   ------------     I $39, 774, 761
                      308,145
   Cost----------------_                        669,401     371,080       944,
                                                                             732       $ 43,647        139,562,255
Maintenance:
   Appropriated..--------      247, 400         154,800     198,500      213, 160       194,800          2,325,899
   Cost----------------        272,374          252, 229    238, 588     204,831        208, 454        22,322, 944

I Includes   $27,190,000 National Industrial Recovery Act funds.
2 In addition, surplus property valued at $4,109 was transferred to the project without reimbursement.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954__-----------        $68,452
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955---------------------------------------------                        68,452
    Estimated additional amount needed to be appropriated for completion
       of existing project -----------------                                                            855,200
962            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                       8. NEWARK, OHIO RIVER BASIN, OHIO
   Location. Newark, Ohio, is located in Licking County at the
junction of the North and South Forks of the Licking River, 29
miles above its confluence with the Muskingum River at Zanesville,
Ohio.
   Existing project. This provides for a total of 31,500 linear feet
of channel improvements of the Licking River, North and South
Forks of Licking River, and Raccoon Creek; 5,450 feet of levee
along North and South Forks of Licking River; and pump station
and sump for the disposal of interior drainage. The project pro-
vides protection for the city of Newark against floods 22 percent
greater than that of 1913 (one of the greatest of record) with a
3-foot freeboard. The existing project was selected for construction
under the general authorization for the Ohio River Basin contained
in the Flood Control Act approved June 28, 1938. The project was
constructed at a Federal cost of $785,880. In addition, the esti-
mated cost to the city of Newark under provisions of section 2 of
the Flood Control Act, approved June 28, 1938, was $21,000. The
latest (1953) approved estimate for annual cost of maintenance
is $3,500.
   Local cooperation. Fully complied with.
   Operationsand results during fiscal year. Operation and main-
tenance, general: Routine inspections of the improved portion of
the channel were conducted and remedial work was performed as
required to maintain the channel in a satisfactory condition. The
cost during the fiscal year was $2,426, for maintenance.
   Condition at end of fiscal year. The project, construction of
which was initiated in July 1940, was completed for beneficial use
in November 1941. The pump facilities and levees have been turned
over to the city for maintenance and operation. The improved chan-
nels, maintained by the United States, are in good condition. The
total cost of the existing project, to the end of the fiscal year was
$888,826, of which $785,880 was for new work and $102,946 was
for maintenance.
                                         Cost and financial summary

                                                   Fiscal year ending June 30                    Total to June
                                                                                                 30, 1954, includ-
                                                                                                 ing fiscal yearsr
                                  1950           1951       1952         1953        1954         priorto 1950,

New work:
   Appropriated----------$1,620-                                                                         $785, 880
   Cost---------      ---- ----     -138 --------------------------------------------                     785,880
Maintenance:
   Appropriated-_- __- -------       -      --   $3, 850     $4, 000      $3, 500   -$     800            104,050
   Cost-...-------------   ----     2,241         8,979         316        3,855         2,426            102,946

            9. DILLON RESERVOIR, OHIO RIVER BASIN,                                          OHIO
  Location. The dam site of the Dillon Reservoir is located on
Licking River, Ohio, 5.8 miles above the confluence of the Licking
and Muskingum Rivers at Zanesville, Ohio.
  Existing project. The plan of improvement provides for the
construction of a rolled earthfill dam having a maximum height of
118 feet and a total length of 1,350 feet; controlled outlet works
discharging through twin conduits located in the right abutment;
              FLOOD CONTROL--HUNTINGTON, W. VA., DISTRICT                                             963
an uncontrolled spillway in the left abutment; 2 rolled earthfill
dikes which will prevent diversion of water into Wakatomika Creek
valley; and 2 rolled earthfill dikes which will prevent diversion of
water into the Bartlett Run valley. The reservoir created, providing
for the storage of 273,800 acre-feet, will control a drainage area
of 748 square miles, and necessitates the relocation or reconstruc-
tion of 19.5 miles of railroad track, 12.2 miles of roads, 32.7 miles
of powerlines, 34.2 miles of communication lines, and 17.2 miles
of pipelines. The reservoir will be operated as a unit of the co-
ordinated reservoir system for the protection of Zanesville, Ohio,
and the Muskingum and Ohio River Valleys generally. The exist-
ing project was selected for construction under the general au-
thorization for the Ohio River Basin contained in the Flood Control
Act approved June 28, 1938. The estimate of cost for new work
 (1954) is $28,100,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operationsand results during fiscal year. Surveys, studies, and
preparation of plans pertinent to the remaining phases of the
Baltimore and Ohio Railroad relocation in the reservoir area were
continued by hired labor. The cost of new work during the fiscal
year was $33,899.
   Condition at end of fiscal year. Construction of the project
was initiated in July 1946, when relocation of the Baltimore and
Ohio Railroad in the reservoir area was commenced. This phase of
the project has been brought to about 77 percent completion. Con-
struction of Nashport Dike, together with relocation of affected
highway and utility facilities, is complete. Relocation agreements
have been entered into with the 18 owners having facilities affected
by the Baltimore and Ohio Railroad relocation. Of the estimated
800 tracts of land required for the project, 131 tracts have been
acquired. The entire project is about 31 percent complete. The
total cost of new work to the end of the fiscal year was $8,819,602.
                                    Cost and financial summary

                                            Fiscal year ending June 30                       Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                             1950          1951        1952        1953         1954         prior to 1950


New work:
                  --
   Appropriated- .....    $1,277,600    $ 926,200     $100, 000   $112,000    .........          $ 9, 189, 800
   Cost...-- -----           657, 260    1,191, 423    720, 025     17, 580     1$36, 510         8,819602


1Includes $2,611 undistributed tools and equipment cost 30 June 1953.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_---------       $21,713
    Unobligated balances available for succeeding fiscal year ending June
    .30, 1955--------      --------------------------------------          21,713
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project-------------------- ------------ 18,910,200

                 10. ROSEVILLE, OHIO RIVER BASIN, OHIO
  Location. The project is located at Roseville in Muskingum
and Perry Counties, Ohio, on Moxahala Creek about 6 miles up-
964            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

stream from its confluence with Jonathan Creek of the Muskingum
River.
   Existing project. The project provides for complete protection
of Roseville by channel rectification and levee construction. The
work involves the improvement of 7,291 feet of the channel of
Moxahala Creek, construction of about 5,370 feet of levee along
the left bank of Moxahala Creek, construction of 1 pump station
and intercepting sewer, relocation of 1 railroad bridge, alteration of
2 highway bridges, and necessary utility changes. The project has
been selected for construction under the general authorization for
the Ohio River Basin, contained in the Flood Control Act approved
June 28, 1938. The estimated Federal cost of the project (1954) is
$1,030,000, the estimated non-Federal cost is $56,000.
   Local cooperation. Local interests have furnished assurance of
local cooperation.
   Operations and results during fiscal year. Plans and specifica-
tions, prepared during the preceding fiscal year by contract, were
reviewed preparatory to securing final approval. The cost of new
work during the fiscal year was $1,041.
   Condition at end of fiscal year. Detailed plans and specifica-
tions for construction of the project are complete and have been
reviewed preparatory to securing final approval. The total cost of
new work to the end of the fiscal year was $73,446.
                                        Cost and financial summary

                                               Fiscal year ending June 30                     Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                               1950          1951              1952       1953       1954     priorto1950

New work:
   Appropriated ______ ___________        ___________           $4, 363   $24, 400                   $74, 537
   Cost-...-__--___- __----   ______-         $1,213              1,407    22,268    $1,041           73,446

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_------------        $1,091
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955_-                                                                   1,091
    Estimated additional amount needed to be appropriated for completion
       of existing project                          -----------------                             955,500

            11. PARKERSBURG,                    OHIO RIVER BASIN, W. VA.
   Location. The project is within the confines of the city of
Parkersburg, W. Va., located on the left bank of the Ohio River,
184 miles below Pittsburgh, Pa.
   Existing project. This consists of about 9,600 feet of earth
levees and 10,400 feet of concrete walls extending along the Ohio
and Little Kanawha Rivers; 6 electrically operated pump stations
for the disposal of interior drainage; appurtenant drainage
structures; and 14 gate openings. The project provides protection
for the city of Parkersburg against floods of 1913 magnitude
 (maximum of record) with a 3-foot freeboard. The existing project
was selected for construction under the general authorization for
the Ohio River Basin, contained in the Flood Control Act approved
June 28, 1938. The estimated Federal cost of the project (1954) is
$6,594,600, the estimated non-Federal cost is $300,000.
                 FLOOD CONTROL--HUNTINGTON, W. VA., DISTRICT                                           965
   Local cooperation. Fully complied with.
   Operations and results during fiscal year. Plans and specifica-
tions covering the provision of emergency controls on outlets
through the levee and wall were prepared and a contract for ac-
complishing the work was awarded. The cost of new work dur-
ing the fiscal year was $2,149.
   Condition at end of fiscal year. Construction of the project was
initiated in March 1946. The work initially contemplated was com-
pleted in May 1950, at which time the project was turned over to
the city of Parkesburg for maintenance and operation. As a result
of studies made subsequent to the date the project was turned
over to the city, it was found necessary to provide emergency
controls on outlets through the levee and wall. A contract for
constructing the remedial work was awarded just prior to the
end of the fiscal year. The costs for new work to the end of the
fiscal year were as follows:
   Regular funds: $6,513,319.
   Emergency Relief funds: $3,145.
   The total costs were $6,516,464.
   In addition, surplus property valued at $2,562 was transferred
to the project without reimbursement.
                                       Cost and financial summary

                                              Fiscal year ending June 30                       Total to June
                                                     ....--                                 30, 1954, includ-
                                                                                            ing fiscal years
                                1950         1951        1952         1953          1954       priorto 1950


New wok'.
   Appripriated              $1,396, 900       .-. .
                                              ...       -- $1, 500   -$3,130        $79,5.70       $6,593,885
   Cost .                     1,222,093      $20,159           912      3,272         2,149        I6,516,464

1   In addition, surplus property valued at $2,562 was transferred to the project without reimbursement.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954              - -    $38, 357
    Unobligated balances available for succeeding fiscalfyear ending June 30,
      1955 ..                              .           ---
                                                  ...............     .-        -
                                                                               38,357      -
        12. TOM JENKINS RESERVOIR, OHIO RIVER BASIN, OHIO
  Location. The dam site of the Tom Jenkins Reservoir is located
on East Branch of Sunday Creek, a tributary of Hocking River,
Ohio, about 3 miles north of the village of Glouster and 57.2 miles
above the mouth of Hocking River.
  Existing project. The project consists of a rolled earthfill dam
having a maximum height of 84 feet and a total length of 944 feet;
controlled outlets works discharging through a tunnel located in
the left abutment; and an uncontrolled spillway in the ridge run-
ning south from the dam site. The reservoir created, providing for
the storage of 17,600 acre-feet for flood control and 9,300 acre-feet
for conservation and water supply for a total of 26,900 acre-feet
controls 32.8 square miles of the drainage area of East Branch,
and necessitated the relocation of 0.5 mile of county roads and 0.7
mile of pipeline. The reservoir affords substantial protection to the
Sunday Creek Valley and serves as a unit of the coordinated reser-
966      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

voir system for the protection of the Hocking River and Ohio River
Valleys. The reservoir also provides an assured water supply to
villages, industries, and coal mine operations in the Sunday Creek
Valley. The existing project was authorized under the Flood Con-
trol Act approved December 22, 1944. The estimate of cost for new
work (1954) is $2,869,000, of which $2,084,000 represents Federal
cost and $785,000 represents cost to local interests. The latest
 (1954) approved estimate for annual cost of maintenance is
$27,000.
   Local cooperation. Local or State interests are required to fur-
nish funds for the project equal to the difference between the total
estimated first cost and the capitalized flood control benefits. House
bill 496 passed by the Ohio State Legislature appropriated funds to
cover local and State obligations relative to the project. By agree-
ment entered into January 22, 1948, between the Department of the
Army, Corps of Engineers, and the Division of Conservation and
Natural Resources, Department of Agriculture, State of Ohio, the
State contributed $495,000 to be applied toward the cost of con-
struction of the project, and retained $290,000 of the total amount
to be contributed, for acquisition of lands and interests in land
being acquired by the State in the reservoir area. However, the
State was unable to acquire certain reservoir lands and requested
the United States to acquire such lands. The State has contributed
$80,000 additional to the United States for the purchase of these
lands. The agreement provides further that, subject to appropria-
tions made by the General Assembly of the State of Ohio, the State
will contribute to the Government annually, the sum of $1,500 as
the pro rata share chargeable to the State covering the annual cost
of operating the project insofar as water supply features are
concerned.
   Operations and results during fiscal year. New work: The in-
stallation of stream gaging facilities and construction of facilities
for the accommodation and protection of the visiting public were
completed. Work in connection with the acquisition of land was
continued and assistance was given the Department of Justice in
negotiating for stipulations covering tracts acquired by con-
demnation.
   Operation and maintenance, general: The reservoir was operated
to reduce local flooding as required and necessary repairs were
made to the structures and appurtenances.
   The total cost from Federal funds was $22,051, of which minus
$4,597 was for new work and $26,648 was for maintenance. In addi-
tion, $14,028 for new work was expended from contributed funds.
    Condition at end of fiscal year. The dam is complete and the
reservoir is in operation, affording substantial protection to the
Sunday Creek Valley as well as serving as a unit of the coordinated
reservoir system for the protection of the Hocking River and Ohio
River Valleys. The reservoir also provides an assured water supply
to villages, industries and coal mine operations in the Sunday Creek
Valley. Construction of the dam was started in March 1948 and
completed in February 1950. The project is complete in all respects
except for land acquisition work consisting of assisting the De-
partment of Justice in processing through trial 11 mineral cases.
               FLOOD CONTROL--HUNTINGTON, W. VA., DISTRICT                                                 967
The total cost to the end of the fiscal year from Federal funds was
$2,164,984, of which $2,077,323 was for new work and $87,661 was
for maintenance. In addition, $571,344 for new work was expended
from contributed funds.
                                    Cost and financial summary
                                        UNITED STATES FUNDS

                                              Fiscal year ending June 30                         Total to June
                                                                                                 30, 1954, includ-
                                                                                                 ing fiscal years
                             1950           1951         1952           1953           1954       priorto 1950

New work:
   Appropriated-..._...   $1, 166,600 ..----------                     -$6, 800 ------------          $2, 084,200
   Cost----------------      988,366        $88, 305     $48,909          31,940      -$4,597           2,077,323
Maintenance:
   Appropriated --             12,500         16,400      17, 400         21,800        21,262             89, 362
   Cost----                     7,492         17,056      16,909          19,556        26,648             87,661


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_------------        $6,877
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955      -------------------------------------------------              6,877
                                    Cost and financial summary
                                        CONTRIBUTED FUNDS

                                              Fiscal year ending June 30                          Total to June
                                                                                                 30, 1954, includ-
                                                                                                 ing fiscal years
                             1950           1951         1952           1953           1954       priorto 1950


New work:
   Appropriated........
                ------------------    $25,000            $55,000                 ..                       575,000
   Cost....------------------------------------           59,206 ...------------       $14,028            571,344


      13. BLUESTONE RESERVOIR, OHIO RIVER BASIN, W. VA.
   Location. On New River, W. Va. and Va., about 2.5 miles above
Hinton, W. Va., and 1 mile above the confluence of the New and
Greenbrier Rivers.
   Existing project. The project provides for a concrete gravity
dam having a maximum height of 180 feet and an overall length of
2,048 feet, consisting of 790 feet of spillway section, 330 feet of
powerhouse intake structure, and 928 feet of nonoverflow sections
and abutments. The reservoir created, extending approximately 36
miles upstream from the dam and providing for the gross storage
of 631,000 acre-feet, is being operated as a unit of the coordinated
reservoir system for the protection of the New, Kanawha, and Ohio
Valleys generally. The estimate of cost for new work (1954) is
$28,965,300. The latest (1954) approved estimate for annual cost
of maintenance is $88,000. The existing project was authorized by
the Flood Control Acts approved June 22, 1936, and June 28, 1938.
Prior to the foregoing authorizations, under provisions of Execu-
tive Order No. 7183A, September 12, 1935 (which authorized the
construction of a reservoir dam on New River for the reduction
of flood heights in the Kanawha and Ohio Valleys, and for the
development of power), surveys, foundation explorations, clearing
of reservoir area, design of dam, and the acquisition of land were
undertaken. The sum of $543,960 from emergency relief funds
was allotted for initiating this work. For further details, see page
968            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

1453 of the Annual Report for 1939.
   Local cooperation. Section 2 of the Flood Control Act approved
Jne 28, 1938, applies.
   Operations and results during fiscal year. New work: Installa-
tion of stream gaging facilities, establishment of sedimentation
ranges, construction of facilities for the accommodation and pro-
tection of the visiting public, and removal of a railroad bridge over
the Greenbrier River were completed. Relocation of 1 cemetery con-
taining 17 graves was accomplished by contract. Construction of
radio network for hydrologic data was continued. Land acquisition
work for the project was completed and consisted of acquiring 13
tracts required for the radio network facilities and 1 tract required
in connection with removal of a cemetery from the reservoir area.
   Operation and maintenance, general: The reservoir was operated
for the benefit of flood control as required, and necessary repairs
were made to the dam and to operator's quarters and grounds
throughout the year. Facilities for the accommodation and protec-
tion of the visiting public were maintained in good condition.
   The total cost was $158,986, of which $91,134 was for new work
and $67,852 was for maintenance.
   Condition at end of fiscal year. The dam is complete and the
reservoir is in operation as a unit of the coordinated reservoir
system for the protection of: the New, Kanawha, and Ohio Valleys,
generally. Construction of the dam, initiated in January 1942, was
suspended during the war years and completed in April 1952 upon
completion of the installation of crest gates and hoists. Construc-
tion of a radio network for hydrologic data was in progress and
well advanced at the end of the year. Upon conclusion of this item
and other minor items of work, the project will be complete in all
respects. The total cost to the end of the fiscal year was $29,222,156,
of which $28,878,624 was for new work, and $343,532 was for
maintenance. In addition, surplus property valued at $26,839 was
transferred to the project without reimbursement.
                                    Cost and financial summary

                                0      :    Fiscal year ending June 30                          Total to June
                                                                                                30, 1954, includ-
                                                                                                ing fiscal years
                             1950          1951         1952        1953              1954       priorto 1950

Neow work:
   Appropriated- ....     $1,178,000   -$318, 700               -$56, 000.------------
                                                      ...........--------                         1 $28, 890, 260
    ost---
        ....-------------    952,557    1,616,370 $1,317,826         93, 396          $91,134      12 28, 878, 624
Maintenance:
   Appropriated-------.....   58,700       58,600        88,600      60,833            70,600            347,333
   Cost - ---------........
                         .. . 44 050       74, 859       70,872    '76, 963            67,852            343, 532

1Includes $543,960 Emergency Relief funds.
2In addition, surplus property valued at $26,839 was transferred to the project without reimbursement.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954__                    ----------------
                                                                              $7,536
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955-------------------------            -------------------- ----- 7,536
    Estimated additional amount needed to be appropriated for completion
       of existing project             -          -                       --                           75,000
                  FLOOD CONTROL-HUNTINGTON, W. VA., DISTRICT                                              969
            14. SUTTON RESERVOIR,                      OHIO RIVER BASIN, W. VA.
    Location. The dam site of the Sutton Reservoir is located on
Elk River, W. Va., 1 mile above the town of Sutton, W. Va., and
approximately 101 miles above the mouth of Elk River.
   Existing project. The plan of improvement provides for the
construction of a concrete gravity dam having a maximum height
of 237 feet; and an overall length of 1,208 feet, consisting of 280
feet of spillway section and 928 feet of nonoverflow sections and
abutments. The reservoir created, providing for the storage of
265,300 acre-feet, will control a drainage area of 537 square miles,
and necessitates the relocation of 8.6 miles of railroad tracks, 9.7
miles of roads, and miscellaneous public utility service lines. The
reservoir will be operated as a unit of the coordinated reservoir
system for the protection of the Elk, Kanawha, and Ohio Valleys
generally. The existing project was selected for construction under
the general authorization for the Ohio River Basin contained in the
Flood Control Act approved June 28, 1938. The estimate of cost for
new work (1954) is $32,600,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. Work under an
agreement with the Baltimore and Ohio Railroad Co. for design
of structures for the remaining relocation work was completed. The
cost of new work during the fiscal year was $99,755.
   Condition at end of fiscal year. Construction of the project
was initiated in October 1949, when contract work was begun on
sealing an abandoned coal mine at the dam site. This phase of the
project has been completed. Other construction work completed
consists of section 1 (grading) of the Baltimore and Ohio Railroad
relocation. Of the estimated 523 tracts of land required for the
project, 98 tracts have been acquired. The entire project is about
5 percent complete. The cost of new work to the end of the fiscal
year was $1,729,208.
                                    Cost and financial summary

                                             Fiscal year ending June 30                        Total to June
                                                __                         _-30,                 1954, includ-
                                                                                               ing fiscal years
                             1950          1951         1952        1953            1954        prior to 1950


New work:
   Appropriated ..-....   $1,000,000                              -$94, 600 ---                     $1, 861,400
   Cost-----325,792                        696,058 -$257,183         79, 077       $112, 984          1,729,208


1Includes $13,229 undistributed tools and equipment and sub-office costs 30 June 1953.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-_------                                   $40, 833
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955 ----------------------------------------------
                    .                                                                                 40,833
    Estimated additional amount needed to be appropriated for comple-
       tion of existing project               _
                                       -------------                                            30,738,600
970      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

          15. HUNTINGTON, OHIO RIVER BASIN, W. VA.
   Location. The work covered by this project is within the con-
fines of the city of Huntington, W. Va., on the left bank of the Ohio
River, from mile 304.25 to 313.12 below Pittsburgh, Pa.
   Existing project. Section I: This part of the project consists
of about 19,400 feet of earth levee and 2,200 feet of concrete wall
extending along the Ohio River and landward to high ground at the
western extremity of the project; 6 electrically operated pump
stations for the disposal of interior drainage; appurtenant drainage
structures; and 6 gate openings. Protection is provided for the west
end of Huntington against floods of 1937 magnitude (maximum of
record) with a 3-foot freeboard. This section of the existing project
was selected for construction under the general authorization for
the Ohio River Basin contained in the Flood Control Act approved
June 28, 1938. This section of the project was constructed at a
Federal cost of $2,327,700. The estimated cost to the city of Hunt-
ington for lands and damages was $655,000.
   Section II: This part of the project consists of about 17,900 feet
of concrete wall extending along the Guyandot and Ohio Rivers; 24
gate openings and storage houses; 7 pump stations for the disposal
of interior drainage; and a continuous toe drain adjacent to the
landward side of the base of the wall. Protection is provided for
the business section of Huntington against floods of 1937 magni-
tude (maximum of record) with a 3-foot freeboard. This section of
the existing project was selected for construction under the general
authorization for the Ohio River Basin contained in the Flood Con-
trol Act approved August 28, 1937. This section of the project was
constructed at a Federad cost of $2,543,265. The estimated cost to
the city of Huntington for lands and damages was $412,000.
   Section III: This part of the project consists of about 16,800 feet
of concrete walls and 4,600 feet of earth levees extending along the
Guyandot and Ohio Rivers and landward to high ground at the east-
ern extremity of the project; 4 electrically operated pump stations
for the disposal of interior drainage; appurtenant drainage struc-
tures; and 15 gate openings. Protection is provided for the east end
of Huntington against floods of 1937 magnitude (maximum of
record) with a 3-foot freeboard. This section of the existing project
was selected for construction under the general authorization for
the Ohio River Basin contained in the Flood Control Act approved
June 28, 1938. This section of the project was constructed at a
total cost of $2,129,427, of which $2,127,127 was Federal cost and
$2,300 was contributed by local interests. The estimated cost to the
city of Huntington for the lands and damages was $440,000.
   Local cooperation. Fully complied with.
   Operationsand results during fiscal year. Section II: Remedial
works, involving the railroad embankment at the point where the
upstream end of the barrier ties into high ground, were constructed
under an agreement with the Chesapeake and Ohio Railway. The
cost of new work during the fiscal year was $5,823.
   Condition at end of fiscal year. Section I: Construction of this
section was initiated in May 1940 and completed in December 1942;
The cost of new work to the end of the fiscal year was as follows:
              FLOOD CONTROL--HUNTINGTON,                          W. VA., DISTRICT                   971
  Regular funds: $2,325,200.
  Emergency relief funds: $2,500.
  The total cost, all funds, was $2,327,700.
  Section II: Construction of this section was initiated in August
1938. The work initially contemplated was completed in May 1940.
Subsequent to the date the project was turned over to the city,
remedial works, involving the railroad embankment at the point
where the upstream end of the barrier ties into high ground, were
constructed. The cost of new work to the end of the fiscal year was
as follows:
  Regular funds: $2,479,265.
  Emergency relief funds: $64,000.
  The total cost, all funds, was $2,543,265.
  Section III: Construction of this section was initiated in July
1941 and completed in December 1947. The cost of new work to the
end of the fiscal year was as follows:
  Regular funds: $2,124,627.
  Emergency relief funds: $2,500.
  The total cost, all funds, was $2,127,127.
  In addition, $2,300 for new work was expended from contributed
funds.
                                   Cost and financial summary

                                          Fiscal year ending June 30                       Total to June
                                                                                          30, 1954, includ-
                                                                                          ing fiscal years
                            1950         1951        1952           1953         1954       prior to 19501

New work:
   Appropriated ..-----------                         $6, 000-.-.        --.
                                                                      ............           2$6, 998,   092
   Cost....--------------------------------------           159            $18   $5,823        6, 998,092

1 In addition $2,300 for new work was expended from contributed funds.
2 Includes $69,000 Emergency Relief funds.


           16. DEWEY RESERVOIR, OHIO RIVER BASIN, KY.
    Location. The dam site of the Dewey Reservoir is located on
Johns Creek, about 7 miles southeast of Paintsville, Ky., and 5.4
miles above the confluence of Johns Creek and Levisa Fork of Big
Sandy River.
    Existing project. The project consists of a rolled earthfill dam
having a maximum height of 118 feet and a total length of 913
feet; controlled outlet works discharging through a tunnel in the
left abutment; an uncontrolled spillway discharging through a
channel excavated in the left or west abutment; and a rolled earth-
fill dike which blocks a low divide to Brandykeg Creek and the
Levisa Fork. The reservoir created, providing for the storage of
93,300 acre-feet, controls 207 square miles of the drainage area of
Johns Creek, and necessitated the relocation or reconstruction of
8.3 miles of roads, 9.7 miles of pipelines, and 5.2 miles of telephone
lines. The reservoir is being operated as a unit of the coordinated
reservoir system for the protection of the Levisa Fork, Big Sandy,
and Ohio Valleys generally. The existing project was selected for
construction under the general authorization for the Ohio River
Basin contained in the Flood Control Act approved June 28, 1938.
972            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

The estimate of cost for new work (1954) is $6,415,000. The latest
(1954) approved estimate for annual cost of maintenance is
$50,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operationsand results during fiscal year. New work: Installa-
tion of stream gaging facilities was completed. Work in connection
with the acquisition of land was continued and consisted mainly of
assisting the Department of Justice in obtaining stipulations and
processing through trial, the tracts being acquired through con-
demnation proceedings in the United States district court.
   Operation and maintenance, general: The reservoir was operated
for the benefit of flood control, as required, and necessary repairs
were made to the dam, and to the operator's quarters and grounds
throughout the year. Facilities for the accommodation and protec-
tion of the visiting public were maintained in good condition.
   The total cost was $74.252, of which $36,716 was for new work
and $37,536 was for maintenance.
   Condition at end of fiscal year. The dam is complete and the
reservoir is in operation as a unit of the coordinated reservoir
system for the protection of the Levisa Fork, Big Sandy, and Ohio
Valleys generally. Construction of the dam was started in March
1946 and completed in July 1949. All construction operations, in-
cluding the relocation of highway and utility facilities affected by
the project are complete. Title to the 407 tracts of land required for
the project have been acquired. Land acquisition work is complete
except the possible retrial of one large mineral acquisition owner-
ship in which the owner requested a new trial. The case is now
pending in the U. S. Circuit Court of Appeals. The total cost to the
end of the fiscal year was $6,495,984. of which $6,326.120 was for
new work and $169,864 was for maintenance. In addition, surplus
property valued at $17,200 was transferred to the project without
reimbursement.
                                       Cost and financial summary

                                               Fiscal year ending June 30                   Total to June
                                                             -.                             30, 1954, includ-
                                                       I                                    ing fiscal years
                                1950        1951           1952        1953       1954        priorto 1950


New work:
   Appropriated   .______   $  900,000     $523,800                  -$225, 100   - -            $6, 414, 700
   Cost_-------        --    1,292, 573     315,063        $78,970       90,226   $36,716        '6,326, 120
Maintenance:
   Appropriated                 41, 400      14, 650       46,100       33, 907   33, 900            169, 957
   Cost-----------------        19,337       38,294        39,166       35, 532   37y536             169, 864


1 In addition, surplus property valued at $17,200 was transferred to the project without reimbursement.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_                    $87,501
    Unobligated balances available for succeeding fiscal year ending June 30,
       1955_--------------                                                                         87,501

                     17. ASHLAND, OHIO RIVER BASIN, KY.
   Location. The work covered by this project is within the con-
fines of the city of Ashland, Ky., located on the left bank of the
                 FLOOD CONTROL-HUNTINGTON, W. VA., DISTRICT                                              973
Ohio River, 322 miles below Pittsburgh, Pa.
   Existing project. The plan of improvement provides for the
construction of about 13,530 feet of concrete walls and 777 feet of
earth levees extending along the Ohio River; 6 electrically operated
pump stations and necessary appurtenant drainage structures for
disposal of interior drainage; and 17 highway, railroad, and pedes-
trian gate openings. The project will provide protection for main
business and residential sections of the city of Ashland against
floods ofi1937 magnitude (maximum of record) with a 3-foot free-
board. The existing project was selected for construction under
the general authorization for the Ohio River Basin contained in
the Flood Control Act approved June 28, 1938. The project was
constructed at a Federal cost of $3,695,647. The estimated cost
to the city of Ashland for lands and damages was $313,000.
   Local cooperation. Fully complied with.
   Operations and results during fiscal year. Work under con-
tracts for constructing section 3 of the project (remaining wall and
levee sections) and 5 pump stations was completed. Final reports
and "as-built" drawings were prepared. Completion of the fore-
going operations concluded all work on the project. The cost of new
work during the fiscal year was $539,590.
   Condition at end of fiscal year. The project, construction of
wh$h~iwas initiated in July 1949, was completed for beneficial use
in Dcember 1953, and turned over to the city of Ashland for main-
tenance and operation in February 1954. At the end of the year
final :records and reports had been prepared and the project was
complete in all respects. The total cost of new work to the end of
the fiscal year was $3,695,647.
                                       Cost and financial summary

                                              Fiscal year ending June 30                       Total to June
                                                                 . _      .
                                                                         _30,   .          .      1954, includ-
                                                                                               iig fiscal years
                                1950        1951         1952           1953        1954        prior to 1950


New work:
     Appropriated---------$819,100         $ 43500 $2,000,000      $     440,600 -$20,000           $3, 695,647
     Cost -----------------
                 ..  ....    353,177        581,761   211,169          1,914,477 1 540,929           3,695,647


1   Includes $1,339 undistributed tools and equipment cost June 30, 1953.

     'I85 PORTSMOUTH-NEW BOSTON, OHIO RIVER BASIN, OHIO
   Location. The project is located at the cities of Portsmouth and
New Boston, Ohio, on the right bank of the Ohio River above the
mouth of the Scioto River in Scioto County, Ohio. The project ex-
tends from mile 350.2 to mile 356.5 below Pittsburgh.
   Existing project. This consists of about 21,000 feet of earth
levees and 21,400 feet of concrete walls extending along the Ohio
and Scioto Rivers; 12 electrically operated pump stations; 14 gate
openings and 2 service openings; 2 traffic ramps; relocation of ap-
proximately 4,500 feet of the Scioto River channel; and appurten-
ant drainage structures. The project provides protection for the
cities of Portsmouth and New Boston, Ohio, against floods of 1937
magnitude (maximom of record) with a 3-foot freeboard. The
974           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

existing project was selected for construction under the general
authorization for the Ohio River Basin contained in the Flood
Control Act approved June 28, 1938. The project was constructed
at a Federal cost of $9,545,546. The estimated non-Federal cost was
$525,150, which includes $15,150 contributed by local interests
toward construction of the project.
   Local cooperation. Fully complied with.
   Operations and results during fiscal year. Final reports and
"as-built" drawings were prepared to complete all work on the
project. The cost of new work during the fiscal year was $23,577.
   Condition at end of fiscal year. The project, construction of
which was initiated in June 1940, was completed for beneficial use
and turned over to the cities of Portsmouth and New Boston for
maintenance and operation in May 1950. Construction work on the
project was suspended during the period 1943-1945 due to the war
emergency. At the end of fiscal year 1954 final records and reports
had been prepared and the project was complete in all respects. The
total cost of new work to the end of the fiscal year was $9,545,546.
                                      Cost and financial summary

                                               Fiscal year ending June 30                 Total to June
                                                                                          30, 1954, includ-
                                                                                          ing fiscal years
                               1950        1951           1952        1953       1954      prior to 19501

New work:
   Appropriated .......    $   30,000      -            -$28, 000      $6, 500    -$843       2$9, 545,546
     Cost---------------   1, 550,892      $36, 605        5, 978       2, 556   23,577         9,545, 546


1 In addition $15,150 for new work was expended from contributed funds.
2 Includes $10,089 from Emergency Relief funds.

         19. DELAWARE RESERVOIR, OHIO .RIVER BASIN, OHIO
   Location. The dam site is located on Olentangy River about 6
miles above and north of Delaware, Ohio, and 32 miles above the
confluence of the Olentangy and Scioto Rivers at Columbus, Ohio.
The reservoir is located in Delaware, Marion, and Morrow Counties,
Ohio.
   Existing project. The project consists of a rolled earth fill dam
having a gate controlled concrete gravity ogee type spillway in
the channel containing five outlet conduits. The dam is about
18,600 feet long, having a maximum height of 92 feet. The reser-
voir created, providing for the storage of 132,000 acre-feet from a
tributary drainage area of 381 square miles, necessitated the
construction of levee protection works, complete with pump sta-
tions and drainage structures, for the village of Waldo, Ohio, the
relocation or reconstruction of 7.6 miles of roads, 6.5 miles of
powerlines, 7 miles of telephone lines, and 7.6 miles of pipelines,
and the relocation of 4 cemeteries containing 1,744 graves. The
reservoir is being operated as a unit of the coordinated reservoir
system for the protection of the Olentangy, Scioto, and Ohio
Valleys generally. The existing project was authorized by the
Flood Control Act approved June 28, 1938. The estimate of cost
for new work (1954) is $7,642,000. The latest (1954) approved
estimate for annual cost of maintenance is $37,000.
              FLOOD CONTROL-HUNTINGTON,                           W. VA., DISTRICT                    975
   Local cooperation. Section 2 of the Flood Control Act of June
28, 1938, applies.
   Operationsand results during fiscal year. New work: Installa-
tion of stream gaging facilities and construction of facilities for
the accommodation and protection of the visiting public were com-
pleted. Work in connection with the acquisition of land consisted
of assisting the Department of Justice in obtaining stipulations
covering seven tracts being acquired through condemnation pro-
ceedings in the United States district court.
   Operation and maintenance, general: The reservoir was operated
as required to reduce local flooding and necessary repairs were
made to the structures and appurtenances throughout the year.
   The total cost was $81,270, of which $49,681 was for new work
and $31,589 was for maintenance.
   Condition at end of fiscal year. The dam is complete and the
reservoir is in operation as a unit of the coordinated reservoir
system for the protection of the Olentangy, Scioto, and Ohio
Valleys generally. Construction of the dam was started in April
1946, and completed in July 1948. All construction operations, in-
cluding the relocation of highway and utility facilities affected by
the project are complete. Title to the 377 land tracts required for
the project has been acquired. Work remaining in connection with
the land acquisition program consists of assisting the Department
of Justice in processing through trial 11 condemnation cases. The
total cost to the end of the fiscal year was $7,765,514, of which:
$7,611,713 was for new work and $153,802 was for maintenance.
In addition, surplus property valued at $10,176 was transferred to
the project without reimbursement.
                                     Cost and financial summary

                                             Fiscal year ending June 30                     Total to June
                                                                                           S30, 1954, includ-
                                                                                           ing fiscal years
                              1950         1951        1952         1953         1954        prior to 1950


New work:
   Appropriated
      pCost    d--   -..
                      -.     $689,000
                              547,721
                                         -$177, 500
                                            489,835
                                                      -$70,000
                                                         48,860
                                                                   -$89,800| .
                                                                      61,099
                                                                                       .
                                                                                 $49,681
                                                                                                 $7,641,656
                                                                                                 17,611,713
Maintenance:
   Appropriated ..-
   Cost.--
                       -       26, 500
                               24,257
                                            18,500
                                            25,186
                                                        32,900
                                                        29,612
                                                                     32, 300
                                                                     28,128
                                                                                  26,900
                                                                                  31,589
                                                                                                     156,10(
                                                                                                     153,802

1 In addition, surplus property valued at $10,176 was transferred to the project without reimbursement.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954           -    -    $27,459
    Unobligated balances available for succeeding fiscal year ending June 30,
       1955       ___    _________-_______ ___27,459
               20. MAYSVILLE, OHIO RIVER BASIN, KY.
   Location. The work covered by this project is within the con-
fines of the city of Maysville, Ky., located on the left bank of the
Ohio River, 408 miles below Pittsburgh, Pa.
   Existing project. The plan of improvement provides for the
construction of about 7,350 feet of concrete walls and 6,850 feet of
earth levees extending along Goose Creek and the Ohio River; 5
electrically operated pump stations and necessary appurtenant
drainage structures for disposal of interior drainage; 10 gate open-
 976          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

ings; and 2 ramps for traffic during nonflood periods. The project
will provide protection for the city of Maysville against floods of
1937 magnitude (maximum of record) with a 3-foot freeboard.
The existing project was selected for construction under the gen-
eral authorization for the Ohio River Basin contained in the Flood
Control Act approved June 28, 1938. The estimated Federal cost
 (1954) is $6,660,000, the estimated non-Federal cost is $525,000.
   Local cooperation. Fully complied with.
   Operationsand results during fiscal year. Work under contract
for constructing section 3 of the project (additional wall and levee
sections) was completed. Construction of Limestone Creek levee
and extension by contract, was continued and advanced froFn 8
percent to 88 percent completion. Work under three supply con-
tracts for furnishing and delivering pumping equipment was con-
tinued throughout the period. A contract for construction of sec=
tion 4 (final wall and levee sections) was awarded, however work
under the contract was not initiated. The preparation of plans and
specifications, by hired labor, for final wall and levee sections to-
gether with pumping plants was continued throughout the year.
The cost of new work during the fiscal year was $955,583.
   Condition at end of fiscal year. Construction of the project
was initiated in July 1949. Sections 1, 2, and 3 of the project, con"
sisting principally of earth levee, concrete wall, a new creek chan-
nel, one culvert, and appurtenances are complete. The Limestone
Creek culvert and gatewell are also complete. Construction of
Limestone Creek levee and extension, by contract, is well ad-
vanced. Work under three supply contracts for furnishing and de-
livering pumping equipment was nearing completion at the end of
the year. A contract for construction of section 4 (final wall and
levee sections) had been awarded but construction operations had
not been initiated. In addition to work in progress, the major items
of work remaining to complete the project consist of construction
of the projects 5 pump stations and installation of pumping equip-
ment. The entire project is about 50 percent complete. The total
Cost of new work to the end of the fiscal year was $3,373,796.
                                    Cost and financial summary

                                           Fiscal year ending June 30                      Total to June
                                                                                           30, 1954, includ-
                                                                                           ing fiscal years
                             1950         1951        1952          1953         1954       priorto 1950


New work:
   Appropriated--- ----.    $819,100    $121,100   $1,000,000   $   995,000   $1,000,000        $4, 319,794
   Cost-----------------     382,960     515,170      388,012    1,049,626 1957,834                   796
                                                                                                 3,373,


1Includes $2,251 undistributed tools and equipment cost June 30, 1953.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954---------_    -- $616,735
    Appropriated for succeeding fiscal year ending June 30, 1955-_         800,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955------------------------------- ----------------- 1,416,735
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project--_   -      .------ -     -     -      1,540,200
          FLOOD CONTROL-HUNTINGTON, W. VA., DISTRICT              977
         21. OHIO RIVER BASIN,     HUNTINGTON DISTRICT
    Location. The works covered by this project are a series of
levees, flood walls, channel improvements, and reservoirs in the
Ohio River Basin within the confines of the Huntington, W. Va.,
district.
    Existing project. The Flood Control Act approved August 28,
1937, authorized the construction of levees, flood walls, and drain-
age structures for the protection of cities and towns in the Ohio
River Basin, the projects to be selected by the Chief of Engineers
with the approval of the Secretary of War, in accordance with
House Flood Control Committee Document No. 1, 75th Congress,
1st session, at a cost not to exceed $24,877,000 for construction,
which amount was authorized to be appropriated for this purpose.
    The Flood Control Act approved June 28, 1938, approved the
general comprehensive plan for flood control and other purposes in
the Ohio River Basin as set forth in House Flood Control Commit-
tee Document No. 1, 75th Congress, 1st session, with such modifica-
tions thereof as, in the discretion of the Secretary of War and the
Chief of Engineers, may be advisable, and for initiation and par-
tial accomplishment of the plan, authorized $75,000,000 for
reservoirs and $50,300,000 for local flood protection works, the
individual projects to be selected and approved by the Chief of
Engineers.
    The Flood Control Act approved August 11, 1939, contained the
provision that the Muskingum River Valley dams and reservoirs as
set forth in the official plan of the Muskingum watershed conser-
vancy district shall be included in the flood control plan of the Ohio
River Basin authorized in the Flood Control Act approved June
28, 1938.
    In addition to previous authorizations the Flood Control Act ap-
proved August 18, 1941, authorized the sum of $45,000,000 for the
further prosecution of the comprehensive plan approved in the
act of June 28, 1938, for the Ohio River Basin, modified to include
the Allegheny Reservoir project in accordance with the recommen-
dation of the Chief of Engineers in House Document No. 300, 76th
Congress, 1st session.
    The Flood Control Act approved December 22, 1944, authorized
the additional sum of $70,000,000 for the further prosecution of
the comprehensive plan approved in the act of June 28, 1938, as
modified by the act approved August 18, 1941, for the Ohio River
Basin, including the Burr Oak Reservoir on the Hocking River,
Ohio, substantially in accordance with the recommendations of the
Chief of Engineers in House Document No. 762, 77th Congress, 2d
session, at an estimated cost of $400,000.
   The Flood Control Act approved July 24, 1946, authorized the
additional sum of $125,000,000 for the further prosecution of the
comprehensive plan approved in the act of June 28, 1938, as
amended and supplemented by subsequent acts of Congress includ-
ing the local flood protection works at Galax, Va., on Chestnut
Creek, substantially in accordance with the recommendations of
the Chief of Engineers in House Document No. 506, 78th Congress,
978               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

1st session, at an estimated cost of $276,125.
     The Flood Control Act approved May 17, 1950, authorized the
additional sum of $100,000,000 for the prosecution of the compre-
hensive plan for the Ohio River Basin approved in the act of June
28, 1938, as amended and supplemented by subsequent acts of
Congress.
  The following is a list of the individual projects considered in the
comprehensive plan within the confines of the Huntington District.

                                              Local protection projects

                                                                                            Estimated cost
                 Location 1                       Type of protection
                                                                                Federal         Non-federal       Total
                                              I                            I                I                 I




Aberdeen, Ohio.....................                 Wall and levee--........               $1, 430, 000 $ 55,000 $ 1,485, 000
Ashland, Ky 24........................ --..                do..---............            5 3,695,647      313,000    4,008, 647
A thalia, Ohio-..................... ... Levee.............---....                             630,000     187, 000      817,000
Belpre, Ohio-......               .....            Wall and levee-........                 3,570,000      448,000    4, 018000
Brooklyn, W. Va .....................            .....    do............---....            5,200, 000     226, 000   5,426,000
Buena Vista, Ohio ...............                      -- do..            ---............      593,000     197, 000      790,000
Burlington, Ohio_........                          Levee .........                --          146, 000    117, 000      263,000
Catlettsburg, Ky 3......                            Wall and levee......                    4,560,000      510,000    5,070,000
Ceredo-Kenova, W. Va 4-                           ..... do-.....-----------               5 2, 568, 463    265,000    2,833,  463
Chambersburg, Ohio ......                          .... do-...-----.-----.                  1,600,000       53,000    1, 653,000
Chesapeake, Ohio_.......                 _     ._ Levee------..............-----               330,000     139,000       469,000
Cheshire, Ohio_._                                  .... do-...----------                       419,000     147, 000      566, 000
Clarington, Ohio.............._._..... Wall and levee-........                              2, 710,000     249,000 2, 959, 000
Clifton, W. Va ......................- Levee--....----------                                   230,000     113,000       343,000
Coal Grove, Ohio _________._ Wall and levee-........                                           888, 000     55,000       943,000
Friendly, W. Va...................... -----       ,--do,,------------
                                                          do----------------                   655,000      61,000       716,000
Fullerton, Ky.________.__                __                                                 1 090,000      178,000   1,268,000
Galax (New River Basin), Va 4........               Channel improvement                      S480, 536     185, 000      684, 718
                                                       and levee.
Gallipolis, Ohio........................ Wall and levee-........                            2,670,000     839,000    3,509, 000
Greenup, Ky ------------------- ....----                  do................------------    2, 660,000    512,000 3,172,000
Hanging Rock, Ohio................... Levee....------------                                    467, 000   155,000        622,000
Hartford, W. Va_..___................ Wall and levee .......                                2,880,000     222, 000 3,102,000
Henderson, W. Va...............     _____           Levee__--.----------                       437,000    188,000        625,000
Hockingport, Ohio._.....- ___..        ...     . Levee-...------------                         568, 000   242,000        810, 000
Huntington, W. Va.
    Sec. 1 (West end) 24 .___________ Wall and levee......                                5 2, 327, 700   655, 000   2,982, 700
    Sec. 2 (Business section) 2 4........ Wall--                        ----------        5 2,543, 265    412,000    2,955,265
    Sec. 3 (Guyandot) 2 4______________ Wall and levee........                            5 2,127,127     442,300    2, 569, 427
Ironton, Ohio 4_______________________ ..... do.....-----------                           S2, 543,396     669,000    3,212,396
Letart, W. Va.---------------------- ...--do.........-----------                               938,000     123,000 1,061,000
Letart Falls, Ohio....                             .... do................------------         992,000     126,000   1,118,000
Manchester, Ohio....................                Levee-----............                  1,330, 000    377, 000   1,707,000
Mapleshade, Ohio ...........-._......             .....do-----.............----1,330,000                  298, 000   1,628,000
Marietta, Ohio__..            _---------------      Wall and levee........                14,000,000      822,000   14,822,000
Mason, W. Va ..........--.--.--...                 ....   do.................               1,040,000     238,000 1,278,000
        2 (Muskingum River Basin),
Massillon                                           Channel improve-                        8,139, 500    477,800    8,617, 300
  Ohio.        2                                       ment, wall and levee.
Maysville, Ky. -----------.........---              Wall and levee........                  6, 660,000    525,000    7,185,000
Middleport, Ohio......----..........-- ..... do-....------------                            4, 590, 000   366,000    4,956,000
Miller, Ohio..... ..................... Levee................------------                      519.000    173,000        692, 000
Millwood, W. Va_.....                        - - Wall and levee........                        843,000     134,000       977, 000
New Martinsville, W. Va-............                   -....
                                                          do----------.................     4,670,000     643,000 5,313,000
New Matamoras, Ohio_--__-_..                 :- _ .... do_.-------...                 --    2, 090,000    285,000 2,375,000
Newark (Muskingum River Basin), Channel improvement                                         S785, 880       21,000       806,880
  Ohio.' 4                                            and levee.
Newport, Ohio-....................... Levee.................                                   318, 000     84,000       402,000
Normal, Ky........................... Wall and levee........                                   648,000    235,000        883,000
Parkersburg, W. Va._................. Wall and levee........                                6,594,600     300, 000   6, 894,600
Point Pleasant, W. Va.4------------ .--- do-- --------                                    S2, 829, 296    278,000 3,107,296
Pomeroy, Ohio-----.---..-__.......-- .....                do..,,,-------,
                                                  .....do..---............                16, 500,000     346, 000  16,846, 000
Portland, Ohio__.                                                                           1,040,000     104,000    1,144,000
                                                  .....do.................                               S525,150   10,070,969
Portsmouth-New Boston, Ohio 2.....         4                                              S9, 545, 546
Powhatan Point, Ohio ................ ...do....-------                                      4,720,000     397, 000   5,117,000
Proctor, W. Va ....         _________               Levee .....------ ----                     334,000    121,000        455,000
Proctorville, Ohio___________ Resettlement .......                                          2, 700,000               2,700,000
Racine, Ohio                                        Wall and levee........                     985,000    120,000    1,105,000
Ravenswood, W. Va..........                       ----- do---------------                   1,470,000     106,000    1,576, 000


  See footnote at end of table.
                    FLOOD CONTROL-HUNTINGTON,                           W. VA., DISTRICT                      979
                                Local protection projects--Continued

                                                                                        Estimated cost
                    Locationt                 Type of protection
                                                                         Federal           Non-federal     Total
                                          i881,000
Riverview, W. Va.... .                __    . Levee.--     ___----          881,000            115, 000      996, 000
Roseville (Muskingum River Basin), Channel improvement                    1,030,000           9 56, 000    1,086,000
  Ohio.'
Russell, Ky.4 ....._....                       Levee (backwater pro-       5 237,193            10,000       247,193
                                                 tection).
St. Marys, W. Va..__       .......             Wall and levee- ......     1,510,000            139,000     1,649,000
Sardis,  Ohio..... ...--------------------     Levee.................       285,000             60,000       345,000
Sciotoville, Ohio. . .....       .    . .... Wall and levee- ......       1,460,000            377,000     1,837,000
Sistersville, W . Va.....................     ---....
                                                   do ..............      1, 770, 000          269,000     2,039,000
South Point, Ohio.................... ..... do....-------------             992,000            117, 000    1,109,000
South Portsmouth, Ky.............. Levee....                                370,000            137, 000      507, 000
Syracuse, Ohio ......................              do_.. -          -     1,220,000
                                                                           -..                 100,000     1,320,000
Vanceburg, Ky..................... Wall and levee-...-.-                  1,860,000            541,000     2, 401,000
Waverly, W. Va............-.......            .....do...... . . .. .      3,480,000            251,000     3,731,000
Williamstown, W. Va...__......__ Wall and levee......                     2,580, 000           136,000     2,716,000
Woodlands, W. Va ................---           Levee-...                     206,000            28,000       234,000
Zanesville (Muskingum River), Ohio._ Wall and levee .......               8, 110, 000       13,000,000    21,110,000


  12 All projectsare located on the Ohio River unless otherwise noted.
    For details, see individual report.
  a See Annual Report for 1950 for individual report.
  4 Construction completed.
  5 Actual cost.
  b Includes $2,300 of construction funds contributed by local interests.
  7 Construction funds contributed by Massillon Conservancy District.
  S Includes $15,150 of construction funds contributed by local interests.
  9 Construction funds to be contributed by local interests.
980                  REPORT OF CHIEF OF ENGINEERS, U. S.:ARMY, 1954

                                                                    Reservoirs

                                                                                                                                            Total
                   Tributary basin and reservoir                                                         Stream                           estimated
                                                                                                                                             cost

Big Sandy:
    Clintwood, Va_.               -- ___--                         -__________              Pound River-----------------                     $ 6,080,000
    Dewey, Ky.........................-------------------------------Johns                         Creek........-----.........                 6, 415, 000
    Fishtrap, Ky..................-------                       -------------- Levisa Fork....-------------------                             28, 300,000
    Haysi, Va            ............ __--------------Russell                                       Fork ........------------------           10,100,000
Guyandot: Mud River, W. Va. ........-.                                     .---       -Mud        River___....__          _________           10, 600, 000
Hocking:
    Logan, Ohio           -------------------------------                                   Clear Creek....--------------------                4,230, 000
    Tom Jenkins, Ohio 1 __                         -_____---...________.._____              East Branch of Sunday Creek-....2 2, 084,000
Kanawha:
    Big Bend, W. Va                    _____.......--_-___---             ___-              Greenbrier River---------------                   13,900, 000
    Birch, W. Va..............------------------------------.....                           Birch River.............-------------------..      6,450,000
    Bluestone, W. Va.....--------------------------New                                            River..-------------------28, 965,300
    Moores Ferry, Va......................-----------------------------....do....-----------------------25,600,000
    Poca, W. Va..-------------------------------Pocatalico                                             River -.---------------                21,600,000
    Summersville, W. Va .                   --------.....--------------.. Gauley River ..------------------                                   34,300,000
    Sutton, W. Va.----...                            ..         ....-------...---------------
                                                                                            Elk River-....-------------------- 32,600,000
Little Kanawha:
    Burnsville, W. Va ......---------------------------                                     Little Kanawha River------------                   6, 520,000
    Steer Creek, W. Va - ______________..  --                        ____..._          _... Steer Creek .                                      8,520,000
                                                                                                                           .--------------------
    West Fork, W. Va.--------------------------                                             West Fork-------------------..............-- 6,640, 000
Muskingum:
    Dillon, Ohio 1_.           .        .     .                  ...                        Licking River-.-----------------                  28,100,000
    Frazeysburg, Ohio_--.---.----                               _____------ -               Wakatomika Creek--------------                     5, 470,000
    Millersburg, Ohio-.....                                                         ___ Killbuck Creek----------------
                                                                                   •________-____-                                            12,000,000
Muskingum River Reservoirs, Ohio (System of 14 On various streams-......-........                                                             40,630,000
reservoirs) 1.
Scioto:
    Big Darby Creek, Ohio___                            ________                            Big Darby Creek...............--------------- 18, 600,000
    Deer Creek, Ohio....________-----                    __---.-----------             . Deer Creek......-------------------                  13,200,000
    Delaware, Ohio 1_.....__.---------                                                      Olentangy River.................----------------   7, 642,000
    Paint Creek, Ohio ... _________----------                                               Paint Creek................-------------------13,800,000
    Rocky Fork, Ohio 3......---....---.........--..-----....---.                            Rocky Fork--......--.....--------------..
                                                                                                                                   .....      4410,000
Twelve Pole Creek: East Lynn, W. Va_----                                   ..
                                                                          ____-             East Fork-------------------------                 9, 020,000


  1 For details, see individual report.
  2 Total cost $2,869,200, the additional $785,000 to be contributed by local interests.
  3 See Annual Report for 1950 for individual report.
  4 Total cost $6,349,000, the additional $1,939,000 to be contributed by local interests.

   Operations and results during fiscal year. None.
   Condition at end of fiscal year. Preliminary surveys and plans
have been completed for a number of the projects included in the
comprehensive plan. The status of projects selected for construc-
tion under this authorization is given in individual reports. As a
result of the curtailment of planning functions, work under this
heading has been suspended. The costs of new work to the end of
the fiscal year were as follows:
   Regular funds: $516,727.
   Emergency relief funds: $10,920.
   Total, all funds: $527,647.
                                                   Cost and financial summary

                                                                Fiscal year ending June 30                                           Total to June
                                                                                                                                    30, 1954, includ-
                                                                                                                                    ing fiscal years
                                            1950              1951               1952                 1953           1954                to 1950
                                                                                                                                     prior

New work:
   Appropriated.                 -                        -$474,444         -$118,514            _.          _._._._..          -          1 $527,647
   Cost-----     -                   -     $44,332            33, 043            1,810       -                ---      -527,647

  1 Includes $10,920 Emergency Relief funds.
                     FLOOD CONTROL-HUNTINGTON, W. VA., DISTRICT                                                                        981
                         22. INACTIVE FLOOD CONTROL PROJECTS

                                                                                            Cost to June 30, 1954
                                                                        For last                                   ..       .    Estimated
                       Name of project                                 full report                                                 amount
                                                                      see annual                             Operations          required to
                                                                      report for-- Construction                and                complete
                                                                                                            maintenance

1. Ceredo-Kenova, Ohio River Basin, W. Va.....                                   1944       $2, 568,463 -----.---...-                (1)
2. Emergency flood control work under authority
     of the Flood Control Act approved Aug. 18,
           ass aened-----------------------
     1941, 194,amended-_                                                         1952
                                                                                 15-------------------
                                                                                            .....         .           $44, 891
                                                                                                                      $489           ()
                                                                                                                                     (2
3. Emergency flood control work under authority
     of Public Law No. 75, 79th Congress and
     Public Law No. 102, 80th Congress---------........                          1953 -54,194                                        (2)
4. Emergency flood control work under authority
     of the Flood Control Act approved June 30,
     1948...     -------.......................------------ .............        1950                                   8, 338       (3)
5. Galax, Ohio River Basin, Va....                    ----------------- 1953                     480, 536 ...-------                 (1)
6. Ironton, Ohio River Basin, Ohio....--------------                             1952        2, 543,397 ...-------------             (1)
7. Point Pleasant, Ohio River Basin, W. Va.....                                  1953         2, 829, 297 --------------             (1)
8. Russell, Ohio River Basin, Ky----------------1953                                              237,193-------------               (1)
9. Snagging and clearing under authority of sec-
     tion 2 of the Flood Control Act approved
     August 28, 1937, as amended---_-------_                              ------ 1953             113,990--------------              (4)

  1 Completed.
  2 Emergency flood operations completed during fiscal year 1952.
  a Emergency flood operations completed during fiscal year 1950.
  4 Snagging and clearing operations completed during fiscal year 1953.

                                     23. GENERAL INVESTIGATIONS
  Examinations and surveys. The costs and expenditures during
the year were $8,939. The balance unexpended on June 30, 1954,
$1,451 plus an allotment for fiscal year 1955 of $27,200, a total of
$28,651 will be applied to the preparation of 1 navigation study
(survey), 5 flood control studies (3 surveys-2 preliminary exami-
nations) and the collection and study of basic data.
     The additional sum of $26,000 can be profitably expended during
the fiscal year ending June 30, 1956, for work to be accomplished
under this heading.
   Collection and study of basic data. The collection and study of
basic data during fiscal year 1954 consisted of the following: Col-
lection of stream flow data, revision of Flood Emergency Manual,
and flood investigations.
       24. INSPECTION OF COMPLETED FLOOD CONTROL WORKS
   The Flood Control Act approved June 22, 1936, and subsequent
acts require local interests to furnish assurances that they will
maintain and operate certain local protection projects after com-
pletion in accordance with regulations prescribed by the Secretary
of the Army. District Engineers are responsible for the adminis-
tration of these regulations within the boundaries of their respec-
tive districts. The current (1954) estimate of the annual cost of
this work in the Huntington District is $3,000.
   Maintenance inspections were made during the fiscal year of
completed units of projects transferred to local interests for main-
tenance and operation. Local interests were advised, as necessary,
of measures required to maintain these projects in accordance with
standards prescribed by the regulations.
   The cost during the year was $3,026 for maintenance.
  The cost to the end of the fiscal year was $11,406 for mainte-
nance.
982                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                             Cost and financial summary

                                                    Fiscal year ending June 30                    Total to June
                                                                                                 30, 1954, includ-
                                                                                                 ing fiscal years
                                      1950        1951        1952         1953       1954        prior to 1950

Maintenance:
   Appropriated                                     4, 300     $2, 500
                                                   $--------------------    $1, 741    $3, 000            $11, 541
   Cost ---------------------------                4,141        1,900        2, 338     3,026              11,406
       IMPROVEMENT OF RIVERS AND HARBORS IN THE
               PITTSBURGH, PA., DISTRICT
  This district comprises a portion of eastern Ohio, western Penn-
sylvania, southwestern New York, northern West Virginia, and
northwestern Maryland embraced in the drainage basin of the
Ohio River and tributaries above mile 109 (below Pittsburgh), be-
tween Captina Island and Powhatan Point, Ohio.
                                              IMPROVEMENTS
                     Navigation                                       Flood Control-Continued
                                                    Page                                                      Page
1.   Allegheny River, Pa., con-                       15. Crooked Creek Reservoir, Ohio
        struction of locks and dams..              983       River Basin, Pa......................            1007
2.    Tygart River Dam, W. Va........              987 16. Johnstown, Ohio River Basin,
3.    Monongahela River, Pa., and                                         ---.--.
                                                             Pa-------------.....
                                                                               . --.    .             .       1008
        W. Va .............................        989 17. Conemaugh River Reservoir,
4.    Ohio River above mile 109,                             Ohio River Basin, Pa-............                1010
        lock and dam construction....              995 18. Loyalhanna Reservoir, Ohio
5.   Ohio River, open-channel work                995       River Basin, Pa...................               1012
6.   Inactive navigation projects ..              996 19. Elkins, OhioRiverBasin, W. Va..                    1014
                                                       20. Uniontown, Pa......................                1015
                                                       21. Youghiogheny River Reservoir,
                                                             Ohio River Basin, Pa.                            1015
                 Flood Control                         22. Berlin Reservoir, Ohio River
                                                             Basin, Ohio......................                1017
7.   Portville, Ohio River Basin,                     23. Mosquito Creek Reservoir, Ohio
         N. Y .......  ..........................  996       River Basin, Ohio..................              1019
8.   Olean, Ohio River Basin, N. Y..              997 24. Wellsville, Ohio River Basin,
9.   Bradford, Pa...................              998       Ohio................ .........................   1021
10.   Tionesta Reservoir, Ohio River                   25. Wheeling-Benwood, Ohio River
        Basin, Pa................................  999       Basin, W. Va-......-...--...........             1022
11.   East Branch, Clarion River                       26. Ohio River Basin, Pittsburgh,
        Reservoir, Ohio River Basin,                         Pa. District.....................                1025
         Pa.....  .....    _._..._....... ......  1000 27. Inactive flood control projects..                  1026
12.   Johnsonburg, Ohio River Basin,                   28. General investigations ............                1027
                                                  1003 29. Inspection of completed flood
         Pa..............................................
13.   Punxsutawney,         Ohio River                       control works ..........................         1027
         Basin, Pa....         ..........         1004 30. Flood control work under special
14.   Mahoning Creek Reservoir,                              authorization....              .......           1027
        Ohio River Basin, Pa........              1005

1. ALLEGHENY RIVER, PA.-CONSTRUCTION OF LOCKS AND DAMS
   Location. This river rises in northern Pennsylvania, flows
northwestward into New York, thence generally southwestward to
Pittsburgh, Pa., where it joins with the Monongahela River to form
the Ohio. Its length is 325 miles. (See U. S. Geological Survey
charts for western Pennsylvania and southwestern New York.)
   Existing project. This provides for eight locks and dams to
afford slack water navigation from Pittsburgh, Pa., to above East
Brady, Pa., a distance of 72 miles. Original locks and dams 2 and 3
were replaced by new locks and dams 2 and 3 in 1934. Lock and
dam 1 was eliminated in 1938 by the raising of the Emsworth Dam,
Ohio River. The controlling depth throughout the canalized portion
is 9 feet at normal pool level, and the channel width varies from a
                                                                                                     983
984               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

minimum of 200 feet to full width of river at the mouth.
  The cost of new work for the completed project is $18,157,860.
The latest (1954) approved estimate for annual cost of operation
and maintenance is $425,000.
  The existing project was authorized by the following river and
harbor acts:

       Acts                            Work authorized                                        Documents

Aug.    5, 1886   For lock and dam 1. (Fixed dam contemplated. On                  Annual Report, 1886, p. 1545, and
                    Sept. 29, 1891, the Secretary of War authorized the             Annual Report, 1891, p. 2366.
                    change to a movable dam.)
June 3, 1896      For locks and dams 2 and 3_---....._...........---------------   H. Doc. 204, 54th Cong., 1st sess.,
                                                                                     and Annual Report, 1896, p. 2212.
July 25, 1912 For locks and dams 4 to 8, inclusive ...............                 H. Doc. 540, 62d Cong., 2d sess.
July 3, 1930  For a depth of 9 feet in the lower 61 m iles-... ........            H. Doc. 356, 71st Cong., 2d sess.
Aug. 30, 19351Replacement of lock and dam 1 by a dredged chan-                     Rivers and Harbors Committee,
               nel, 9 feet deep and 200 feet wide up to lock 2, and                  Doc. 16, 72d Cong., 1st sess.
               construction of new locks and dams 2 and 3, to
               replace existing locks and dams 2 and 3.
    Do .......Construction of lock and dam 9, raising of the crest                 H. Doc.:721, 71st Cong., 3d sess.,
               of dam 8, and dredging a navigable channel at the                     and Rivers and Harbors Com-
               head of pool 8.                                                       mittee, Doc. 27, 73d Cong., 2d
                                                                                     sess.
June 26, 19342    Operation and care of locks and dams provided for
                   with funds from War Department appropriations
                   for rivers and harbors.

  1 Included in the Emergency Relief Administration program Apr. 8, 1935.
  2Permanent Appropriations Repeal Act.
                                                                                                                Locks and dams, Allegheny River, Pa.

                                                                                                                Depths          onmiter
                         Location                           Dimensions                                            sills at normal             Character of foundation                    Type of construction
                                                                                                                  pool level 1                                                                                      Per-
                                                                                         Lift      at                                                                                                               cent-         Year
                                                                              normal                                                                                         Kind of                                age of    opened Estimated or
No.                                                     Width         Avall-   pool                                                                                           dam                                   com-        to    actual cost
        Miles                                                           able   level                                                                                                                                 ple-      navi-
        above              Nearest town                 chain-        length   (feet) Lower                                       Upper          Lock            Dam                      Lock         Dam           tion     gation                         0
        mouth                                             her         to full         (feet)                                      (feet)
                                                          (er         width
                                                         (feet)        (feet)


   2        6.7       Aspinwall, Pa                           56               360             11.0                   19.0           10.0 Rock...              Rock      -    Fixed__   Concrete-    Concrete__        100    2 1934      $1,763,485
   3       14.5       Cheswick, Pa                            56               360             13. 5                  10. 8          11.8   .. do...           Pile-rock_____o            do        ___do              100    2 1934       1,875, 665
   4       24.2       Natrona, Pa                             56               360             10.5                   10.0            8.5 - _do__              Rock ____       do      _dodoo                          100      1927       1,707, 690
   5       30.4       Freeport, Pa .-..-...                   56               360             11.8                   10.5           10.3  Piling___           Crib-pile ..... do ____  _do         ___do   -....      100      1927       1,940, 537
   6       36.3       Clinton, Pa                   -         56               360             12.2                   10. 6          10. 8     Rock
                                                                                                                                               P.do              d           .___dodo           -    do                 100       1928     1, 523,959
   7       45.7       Kittanning, Pa_                         56               360             13. 1                   9. 8          10.9      Piling      -    do             do        do____       do               100        1930     1,460, 008
   8       52.6       Templeton, Pa_-_____                    56               360             17.9                   10.4           13.8      Rock__...       Rock-pile .. _-do __      do______     do ______        100        1931     2,848, 920
   9       62.2       Rimerton, Pa    .......                 56               360             22.0                   10.5           11.3        do   _        Rock    _      _dodo___
                                                                                                                                                                               do                     d..              100        1938     2,510,373
    Total--              -----------------------------------------------                                                                           -------------------           -------------------------------------------              15,630,637
Abandoned lock and dam 1 _-_                                                                                                                                                                                                                  591, 187   H
Abandoned lock and dam 21..------------                                    -         -     -            -                                                                                                                                    544, 929
Abandoned lock and dam 3                                      --....................................                                                                                                                                         310, 103
Demolishing old dam 1     3------------                                              -                                 -                  ------------------------------------------------------------------                  -               26, 001
Dredging channel ...............                .       .      .      ..             .         .            .     .        ..             .   .   .  .       .------------------------------------------------                       --    1,055,(003
       Total---....             -                                  -----------------------------------------------------------------------------                                                                                   --     18, 157,860

  1 All depths as shown are on guard sills and are controlling depths.
  2 Dates shown represent replacements structures.
                                                                                                                                                                                                                                                         C0
                                                                                                                                                                                                                                                         H

                                                                                                                                                                                                                                                         y


                                                                                                                                                                                                                                                         -4
                                                                                                                                                                                                                                                         y



                                                                                                                                                                                                                                                         00
986      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Local cooperation. Fully complied with.
   Terminal facilities. The city of Pittsburgh has constructed a
modern wharf for river freight. There are numerous privately
maintained terminals and docks consisting of tipples, various types
of hoists, chutes, and pipelines for use in loading and unloading
coal, coke, sand, gravel, limestone, cement, petroleum products,
steel products, and other commodities. The transshipment of
freight between river and railroads is handled at privately owned
river-to-river terminals.
   Operations and results during the fiscal year. Operation and
maintenance, general: Reestablishment of control monuments and
bench marks for navigation surveys were performed by hired
labor. Dredging the channel below Lock 7 was completed by the
United States derrick boat Monallo, a total of 28,050 cubic yards
being removed. Snagging operations were also performed.
   The locks and dams were operated as required and necessary re-
pairs and improvements made thereto and to the appurtenant
structures to maintain them in a serviceable condition. In addition
to ordinary repairs to structures and plant, the following major
work was performed by hired labor: at Lock 2, repairs were made
to the upper river wall gate, upper land wall gate operating ma-
chinery and lower land wall gate anchorage; and radio-telephone
system installed; at Locks 3 and 4, repairs were made to the power-
house roof; at Lock 5, repairs were made to the esplanade and
powerhouse roof; at Lock 6, repairs were made to oil lines and
powerhouse roof; repairs to esplanade and top of river wall were
initiated; at Lock 7, repairs were made to the powerhouse roof and
oil lines at the upper and lower cross-overs replaced; at Lock 8,
repairs were made to the powerhouse roof, guard fence and tur-
bines; new timbers were installed in needle beam recesses; repairs
were made to the electrical system and lights installed at miter of
gates; at Lock 9, repairs were made to air compressor and standby
plant, electrical system, upper end of miter timbers on lock gates,
powerhouse roof and guard fence; painting of dwellings was ini-
tiated; at Locks 2 to 9, dredging of lock chambers and approaches
was completed; and installation of safety signs was completed
partially.
   The costs were $344,679, of which $21,657 was for channel main-
tenance and $323,022 for operation and care of locks and dams.
   Condition at end of fiscal year. The existing project is com-
plete, the last lock being placed in service in 1938. All locks and
dams are in good condition. The navigation channel has been
widened at certain points and, in general, maintained to project
depth thus affording adequate depth for passage of commercial
tows.
   The costs of the existing project to the end of the fiscal year
were as follows:
             RIVERS AND HARBORS-PITTSBURGH, PA., DISTRICT                                                          987

                                                                                             Costs
                            Funds
                                                                                       Operation and
                                                                  New work             maintenance,            Total
                                                                                         general

Regular ----.----------------....                                       454, 074
                                                                  $-------------$14,               232
                                                                                             $5,515,         $19,969,306
Maintenance and operation -----------------------------                   16, 000                                  16,000
Public works---_-------------------------------         1-250, 049--------------                               1,250,049
                         ------------------             2,453,737 --
Emergency relief-............................................                                                  2,453,737
                                                   --------
     Total.................................................        18,157, 860               5, 531,232       23, 689, 092



  In addition, the sum of $3,528,159 was expended between Janu-
ary 1, 1903, and June 30, 1935, on the operation and care of the
works of improvement under the provisions of the permanent in-
definite appropriations for such purposes.
                                        Cost and financial summary

                                              Fiscal year ending June 30                              Total to June
                                                                                                     30, 1954, includ-
                                                                                                     ing fiscal years
                                 1950        1951        1952            1953                1954         priorto 1950

New work:
   Appropriated-----
               .....---.     $      325----------
                                         ..........--       -$5-----------------------$18,                       157, 860
   Cost_-----------------           35       $ 4,571                                [                       1 18, 157,
                                                                                                                     860
Maintenance:
   Appropriated .-------- 352,400            337,830    332, 500       $369, 900         $336,500             9,072,080
        ...------------
   Cost--                 345,192            322,581    351,664         364, 914          344,679             9,059,390'


1 Includes $2,453,737 from Emergency Relief funds and $1,250,049 from public works funds.


                            2. TYGART RIVER DAM, W. VA.
   Location. The dam site is located on the Tygart River in Tay-
lor County, W. Va., about 22.7 miles above the mouth of the river at
Fairmount, W. Va. It is 2.25 miles upstream from Grafton, W. Va.,
and about 78 miles south of Pittsburgh, Pa. The reservoir is located
in Taylor and Barbour Counties, W. Va. (See U. S. Geological
Survey charts for Fairmont, Thornton, and Belington, W. Va.)
   Existing project. The construction of a concrete gravity dam
was authorized by the Public Works Administration January 11,
1934, and adopted by the River and Harbor Act approved Aug-
ust 30, 1935. This dam is 1,921 feet in length at the top and rises
207 feet above the river bed at the uncontrolled center spillway
section, which is flanked by abutment sections 23 feet higher. The
structure provides for the gross controlled storage of 289,600 acre-
feet of water from a tributary drainage area of 1,183 square miles.
Approximately 278,400 acre-feet of this controlled storage are
available for flood prevention in the Monongahela and Ohio Val-
leys, while the remaining 11,200 acre-feet are permanent storage.
Low water control is also provided by storing 100,000 acre-feet
during the spring months for release during low rainfall periods
to make up the deficiency of water in the Monongahela River. Two
penstocks are contained in the dam for possible future generation
of hydroelectric power.
 988      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

     The cost of new work for the completed project is $18,431,844.
  The latest (1954) approved estimate for annual cost of operation
  and maintenance is $46,000.
     Operations and results during fiscal year. Operation and
maintenance, general: The reservoir was operated effectively, as
  required, and necessary repairs were made to the dam and its ap-
purtenances and to operators' quarters and grounds.
     No damaging floods occurred on the Monongahela or the upper
  Ohio River (above Mile 109) during the year. Four moderate rises
occurred during which suspension of navigation along the upper
end of Lock 15 Pool, Monongahela River, was averted for various
periods by reservoir storage. These rises occurred on January 16,
  1954, March 2, 1954, March 13, 1954, and April 17-18, 1954. The
  first two averted suspension of navigation for 11/2 days, the third
  rise for 21/2 days and the fourth rise for 1 day. Intermittent mod-
erate rainfall and snow melt during March 10-13, 1954, produced
a moderate rise which resulted in the use of the maximum amount
and percent of flood control storage for the year. The reservoir
rose to elevation 1061.1 on March 15, 1954, or 51.1 feet above the
winter pool. This represents an impoundment of 50,200 acre-feet
above pool or about 18 percent of the usable capacity of the
reservoir.
     During protracted periods in August, September, October, and
November, 1953 runoff was deficient in the Monongahela River
Basin so that normal pool stages (in the Monongahela River) were
maintained only by the release of navigation storage from Tygart
Reservoir. The critical low flow period reached 83 days and 66 days,
respectively, for the upper and lower Monongahela River during
which time navigation would have been completely suspended. The
direct benefits to navigation totalled $2,040,000 for low flow aug-
mentation in the Monongahela River. It is noteworthy that the in-
flow into the reservoir for the 3-month period, September through
November, 1953, which totalled only 0.05 inch in runoff, was the
lowest since 1930.
    During January 21-31, 1954, reservoir outflow was regulated to
accommodate navigation repair work at Lock 13, Ohio River. Dur-
ing the remainder of the year routine operations were made in ac-
cordance with the storage schedule, except on the occasion of 9
minor rises when some water was stored and released as river
conditions permitted. The water stored during one of the minor
rises caused the reservoir pool to rise to elevation 1100.0 on Au-
gust 10, 1953, or 16.1 feet above normal drawdown pool level for
that date. This level, the highest reached during the year, repre-
sents an excess impoundment of 27,600 acre-feet or about 14 per-
cent of the usable flood storage capacity of the reservoir for that
date.
    Activities under the reservoir management comprising sanita-
tion measures, conservation, land management and operation and
maintenance of public use facilities were continued.
    The costs were $35,123, all for operation and maintenance.
               RIVERS AND HARBORS-PITTSBURGH, PA., DISTRICT                                                                                  989
   Condition at end of fiscal year. The authorized project is com-
plete. The reservoir is in operation for low water control in the
Monongahela River and for the purpose of flood protection in the
Monongahela and Ohio Valleys. Construction of the dam was
started in 1935 and placed in operation in 1938.
   The costs of the project to the end of the fiscal year were as
follows:

                                                                                                                    Costs

                                  Funds                                                                       Operation and
                                                                                               New work       maintenance,               Total
                                                                                                                 general

Regular-...-----------------------------------           $6431,849            $537, 806                                                 $6 969,655
Public works....--------------------------------------10000,000    ----.-------                                                         10 000, 000
Emergency relief --        ....       --....-.. ......._               . .. -              .    1,999,995     ...-.---          -1-j     1 999, 995
     Total     ------------...................................--------------------------       18, 431, 844              $537,806       18, 969, 650



                                                Cost and financial summary

                                                              Fiscal year ending June 30                                            Total to June
                                                                                                                                30, 1954, includ-
                                                                                                                                ing fiscal years
                                       1950                 1951                 1952               1953            1954          priorto 1950


New work:
   Appropriated -           -        -- $1, 296 ------      ------------------------ ------------ 1 $18,431,844
   Cost------.. -----      --                    4-----------------------------------    ---------                                     118,431,844
Maintenance:
   Appropriated. --------               55, 000              38,000              $32, 000          $30, 000         $38, 000               544, 999
   Cost....--------------               51,259               49,793               36,484            33,616           35,123                537,806.


1 Includes $1,999,995 from Emergency Relief funds and $10,000,000 from public works funds.

                 3. MONONGAHELA RIVER, PA. AND W. VA.
   Location. This river is formed by the junction of the Tygart
and West Fork Rivers about 1 mile south of Fairmont, W. Va., and
flows in a northerly direction 128 miles to its junction with the Alle-
gheny River, forming the Ohio River at Pittsburgh, Pa. (See U. S.
Geological Survey charts for southwestern Pennsylvania and north-
ern West Virginia.)
   Previousprojects. These provided for acquisition by the United
States in 1897 of original locks 1 to 7, inclusive, which were built
by the Monongahela Navigation Co., and the extension of slack
water navigation to the head of the river by the construction of
original locks 8 to 15, inclusive, prior to 1904. The projects were
adopted by the River and Harbor Acts of June 10, 1872, June 3,
1896, and June 4, 1897. For further details see page 1910 of Annual
Report for 1915, and page 1248, Annual Report for 1938.
   Existing project. This provides for the improvement of the
river by 12 locks and dams to afford slack water navigation for its
entire length from Pittsburgh, Pa., to above Fairmont, W. Va.,
Original locks and dams 7, 8, and 9 were replaced by new locks and
dams 7 and 8 in 1925. Increased traffic necessitated an enlargement
and improvement of locks and dams 1 to 6 between Pittsburgh and
990      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Rices Landing, Pa., by the building of two parallel chambers and
fixed concrete dams. Locks and dam 1 were eliminated in 1938 by
the raising of the Emsworth Dam, Ohio River. Reconstruction of
locks 2 provides for two modernized navigation locks, one 110 by
720 feet and one 56 by 360 feet. Locks and dams 5 and 6 are inade-
quate for the present traffic and are nearing the end of their eco-
nomic life and should be replaced.
   Original locks and dams 10 to 15, inclusive, are inadequate for
the present traffic and should be replaced as soon as practicable.
Construction of Morgantown lock and dam was the initial step in
the replacement program, and replaced locks and dams 10 and 11.
Hildebrand and Opekiska locks and dams will replace locks 12 to 15,
inclusive. Alterations to dam 8 will raise pool 8 by 4 feet. Comple-
tion of these improvements from dam 8 upstream will provide for
the entire river length a minimum channel depth of 9 feet, varying
in width from a minimum of 300 feet to practically full width at
the mouth.
   The estimate of cost for new work (1954) (exclusive of amounts
expended on previous projects) is $118,491,000. This amount is ex-
clusive of contributed funds in the estimated amount of $540,000.
The latest (1954) approved estimate for annual cost of operation
and maintenance is $1,575,000.
   The existing project was authorized by the following river and
harbor acts:
                       RIVERS AND HARBORS-PITTSBURGH,                            PA., DISTRICT               991
                       i




      Acts                                  Work authorized                                Documents
- -
Mar. 1, 1899               Enlargement and improvement of lock and dam 6; Annual Report, 1897, p. 2423.
                            additional works at lock 3; new repair steamer and
                            new dredge boat with equipment; all at an esti-
                            mated cost of $185,556.
June 13, 1902              Rebuilding of lock and dam 2 "in accordance with Annual Report, 1909, p. 1756.
                            report submitted by the engineer in charge, Feb.
                            4, 1902" (report not printed), at estimated cost of
                            $655,961. (Estimate increased in 1910 to $698,961.)
Mar. 3, 1905               Acquisition of land and additional improvements at Annual Report, 1904, p. 460.
                            5 and 6 at a cost of $7,850.
      Dol. ....            Rebuilding of lock and dam 3 at estimated cost of H. Doc. 209, 58th Cong., 2d sess.
                            $589,196.
Mar. 2, 1907               Reconstruction of lock and dam 5 at estimated cost of       Do.
                            $756,042.
Mar. 4,          913       Reconstruction of lock and dam 6 at estimated cost of H. Doc. 1217, 62d Cong., 3d sess.
                             $356,400. (Estimate increased in 1916 to $418,860.)
Sept. 22, 1922             Additional improvements atestimated cost as follows: H. Doc. 288, 67th Cong., 2d sess.
                              Guide walls and guard walls, 1 to 6_.. $1, 255,130
                              Lengthening land chamber of lock 3
                                                                              787, 722
                                to 720 feet.........................----------------------
                              New chamber (360 feet long), lock 4_. 699,786
                              Lock and dam 7 ..------------.....-----      1,161,241
                              Lock and dam 8---....---                     1,165,758
                                                               ....-----------.
                              Lock and dam 7 (second chamber)...              419,126
                              Lock and dam 8 (second chamber)..               504,465
                              Reconstruction of dam 4....------------- 397, 211
                              Marine ways, repair plant, office and
                                warehouse-----------------__  ......----     250,000
                          Total..     ..     ..----------------------
                                                                   6,640,439
July 3, 1930    For construction of new locks and dam 24 miles be-              Rivers and Harbors: Committee,
                  low the existing structure, at estimated cost of                Doec. 22, 70th Cong.5 2d sess.
                  $2,175,000 in lieu of the work authorized at old lock
                  and dam 4.
Jan. 31, 19311 Chief of Engineers authorized to locate the new locks
                  and dam above the existing structure and on such
                  site as he may deem most desirable.
June 26,~1934 2 Operation and care of locks and dams provided for
                 with funds from War Department appropriations
                 for rivers and harbors.
May 17, 1950 Modification of the existing project as follows:                   Senate Doec.   100, 81st Cong., 1st
                     Provide for 2 new locks and dams similar to the              seSs.
             I          Morgantown lock and dam to replace existing
                       locks and dams 12 to 15, inclusive.
                     Provide for a movable crest on existing dam 8 to
                        raise the existing pool-full elevation 4 feet.
                    Provide for a navigation channel of 300-foot
                       minimum bottom width and a 9-foot project
                       depth above lock and dam 8.
                    Provide for an extension of the navigable channel
                       of the upper Monongahela River, into the
                       lower Tygart River for a distance of 2.1 miles at
                       a maximum bottom width of 200 feet and a
                       9-foot project depth.

12 Permanent
    Pub. Res. 117, 71st Cong., 3d sess.
               Appropriations Repeal             Act.




          Sig 32-991-1022
                                                                                          Locks and dams, Monongahela River, Pa. and W. Va.

                                                                                                      'Depths on miter
                          Location                         Dimensions                                   sills at normal Character of foundation                                                   Type of construction
                                                                                                        pool level 1                                                                                                                              Per-
                                                                                           Lift at
                                                                                           _          _                                                                                                                                          cent-         Year
                                                                                   normal                                                                                   Kind of                                                              age of       opened Estimated or
No.                                                                       Avail-    pool                                                                                    dam                                                                  com-           to   actual cost
                                                            i               able    level                                                                                                                                                          ple-        navi-                        b
                            Nearest town                  chai-            length   (feet)                Lower    Upper       Lock                     Dam                                           Lock                       Dam              tion         gation
                                                                                                                                                                                                                                                                                            0
                                                                                                                                                                                                                                                                                            O

                                                           ber             to full                        (feet)   (feet)
                                                          (feet)
                                                                           width
                                                                            (feet)

         1-
                                                                                                                                                                                                                        f




     2         11.2   Braddock, Pa ......                  3456               4362            8.71         10.7      11.6   Piles ...... Crib pile.-- Fixed .....                               Concrete_                   Concrete_.                100      1905 2       6$18,415,098
    3         23.8    Elizabeth, Pa_______..                3 56                    3720      8.2 1        11.6      11.9   Rock-......do-.... - -- do   ..     .                                     do-......do                                     100      19072           1,681,538
     4         41.5   Charleroi, Pa- -. .          .        356{                    360      1.6           10.7      14.0   Piles      Piles...... __do ..                          _do.___i               do__                                       100      1932 2          2,173,767    tJ
                                                                                                                                                                                                                                                                                            O
    5         56.5    Brownsville, Pa.....                  3 56                    360      12.4          11.1      11.5   Rock pilej Crib pile l     do -                          .do........-do.......                                            100      1909 2          1,074,812
    6         68.3    Rices Landing, Pa ......              356                     360      13.1          10.5      11.3   Rock-      Crib rock    ...do....                          do                Timber                                       100      1916 2            770,449
                                                                                                                                                                                                           and con-
                                                                                                                                                                                                           crete.                                                                           z
    7          Greensboro, Pa_---
               85.0                                                56               360      15.0          10.0      10.5   do..                    Rock                  .do.... -    do..              Concrete.                                    100      19252           2,639,804
    8          Point Marion, Pa -...
               90.8                                               556               360      15.0          10.0      10.5 _.do-                 .      do.                .do.....     do...         .. do ....--                                     100      19253           2,086,438    C
              102.0
               Morgantown Lock and                            8    14               600      18.0          14.5      17.8 _ do                 .-.....
                                                                                                                                                    .do ...----           Movable __do.                .do .                                          100      1950            8,778,000    z
                  Dam, Morgantown,                                                                                                                                          crest.                                                                                                          tC
                  W. Va.
  12   109.5 Little Falls,.W. Va-...                                  56            182      10.7           7.0       7.0     do         ...     do ...                   Fixed .         -..         do-..          ..
                                                                                                                                                                                                                    __.      do...                     100     1903              200,550
  13   111.7 .... do -     . ...- .. .. .. ..                     R

                                                                      56            182      10.7           7.0       7.0     do-.....do......do--...do...                                                                .. do ...                    100     1904              190,691
                                                              u
                                                                                                                                                                                                                                                                                            ;.
  14   115.3 Lowsville, W. Va .......                         5
                                                                      56            182      10.7           7.1       7.0 -. do---          - _-_do.-.                    ._do----              -_do--..                 _--do---.                    100      1903              210,127
  15   124.6 Hoult, W. Va-.. __-__.                                   56            182      10.7           7.0       7.0   -do       ....---    do        ...                  do...------------
                                                                                                                                                                                              do...                     .. do                          100     1903              175,829
Marine ways, etc .........             .----------.                                                                                                                                                                                                                              250,000
                                   .-
Abandoned lock and dam ___-___-_____.                                      .....-                                                                ----------------------------                   .--                                                                            1,019,907
Abandoned lock and dam 4 ..----......                                                                                                                                                                                                                                            780,816
Abandoned lock and dam 7- ...........                                                                                                                                                                                                                                   .        213,776
Abandoned lock and dam 8 -........                 .                                  -------                                .-------------------                                                                                                                                245,900
Abandoned lock and dam 9 --------.....                                                                                                                                              .......
                                                                                                                                                                                 ......                             .                                                            191,000
Abandoned lock and dam 10 ______________                                                                                                                                                                                    ..                                                   210,445
Abandoned lock and dam 11_                  -..........                                                                              .    ..     .     . ..      .    .              .            .             .                 ..                                             227, 668
Dredging...._....--------------------.                                                                                                   ..................                                                                                                                      587,899         .
         Total-.......      ...-----------------                                                                                                                                                                                       --------------------                  42,124,514


  1 All depths as shown are on gtuard sills and are controlling depths.                                                           4 Dimensions for existing locks: reconstruction provides for 1 chamber 110 x 720 feet and
  2Dates shown for locks and dams Nos. 2 to 8, inclusive, represent reconstruction,                                             auxiliary chamber 56 x 360 feet.
    22Chambers.                                                                                                                   ' Includes $17,510,000 for reconstruction of locks, of which $540,000 is to be contributed.
         RIVERS AND HARBORS-PITTSBURGH,        PA., DISTRICT     993
   Terminal facilities. The city of Pittsburgh has constructed a
modern wharf for river freight. Boat landings are maintained by
some municipalities along the river.
   A large number of tipples at mines and various types of hoists at
manufacturing plants and sand and gravel supply companies are
maintained for private use in loading and unloading coal, coke,
billets, steel products, sand, gravel, and other commodities. These
terminals and docks are not available for the purpose of general
commerce.
   A number of docks and pipelines are also privately maintained
for petroleum and acid products. Marine ways are maintained by
some of the larger industries. There are also several terminals for
rail-to-river and river-to-rail transfer.
   Existing private terminals are adequate for shipments and re-
ceipt in the Pittsburgh district of the type of commerce now in
existence. The provision of river-to-rail and rail-to-river transfer
terminals on an extensive scale is not important, since 98 percent
of traffic using the river passes through the private terminals,
which are more than adequate for the prospective commerce.
   Operations and results during fiscal year. New work: Recon-
struction of locks 2: Engineering and design, including the check-
ing of change orders and the preparation of as built plans were
completed for the 110 foot lock chamber.
   Construction of the 110-foot lock and appurtenances was com-
pleted during the year. The work performed included the comple-
tion of the concreting of the upper and lower miter sills, the emer-
gency dam sill, the lock chamber floor and the esplanade in which
was placed approximately 18,000 cubic yards of concrete. Also com-
pleted during the year was the emergency dam, the emergency dam
monorail and hoists, the butterfly valves, the operating machinery
including the electric light and power installation and the lock
gates. The upper and lower approaches to the 110 foot lock cham-
ber were dredged and the rock pavement placed in the approaches.
The remaining part of the cellular cofferdam was removed and all
painting and testing completed. The final inspection was made and
the lock accepted November 12, 1953. A storehouse building was
erected behind the land wall by contract.
   Morgantown lock and dam: Remaining work on as built plans
was completed. Payment of executed option price on sewer claim
and acquisition cost was completed. Work relative to land acquisi-
tion was completed.
   Dam 8: Advance planning on this project was brought to a de-
sirable stopping point early in the fiscal year and further engineer-
ing and design activities temporarily deferred.
   Hildebrand lock and dam: Advance planning was in progress
throughout the year. The general design memorandum was com-
pleted. Detailed design and preparation of plans for the lock were
in progress.
   Operation and maintenance, general: Reestablishment of control
monuments and bench marks was in progress during the year.
Snagging was performed where required. Condition surveys were
made at various locations and dredging to project dimensions per-
994      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

formed. A total of 13,305 cubic yards was removed from the chan-
nel at several locations and deposited in disposal areas by the
United States Derrickboat Monallo.
    The locks and dams were operated as required and necessary
repairs and improvements made thereto and to the appurtenant
structures to maintain them in a serviceable condition. In addition
to ordinary repairs to structures and plant, the following major
work was performed by hired labor:
    Locks 3: The powerhouse was rebuilt, lower lock gates in the land
chamber replaced, stone placed at the upper guard wall and the tur-
bine repaired; refacing of the upper guard wall by guniting
was initiated; at locks 4, valves and sills and the turbine were
repaired; at locks 5, gate and valve operating machinery and the
top of the lower guide wall were repaired; at locks 6, repairs were
made to the turbine and gate and valve operating machinery, and
lower lock gates, river chamber, repaced; installation of the visual
signal system and repairs to lock walls and valves, sills and gates,
land chamber, completed; at locks 7, repairs were made to the tur-
bine and lock valves and wickets were installed in the upper lock
gates; at locks 8, repairs were made to the turbine and valves;
at Morgantown locks, a walkway under the bridge was installed;
at locks 2-15, lock chambers and approaches were dredged.
    The costs were $2,055,169, of which 838,922 was for new work,
$24,159 for channel maintenance, and $1,192,088 for operation
and care at locks and dam.
    Condition at end of fiscal year. The locks and dams are in op-
eration and are complete except for replacement of locks 5 and 6,
raising the crest of dam 8, and replacement of locks 12 to 15, :in-
clusive, by construction of Hildebrand lock and dam and Opekiska
lock and dam. A controlling depth of 9 feet in the navigation chan-
nel is maintained from Pittsburgh to the upper reaches of pool 8
which has a controlling depth of approximately 7 feet. The recent
construction of Morgantown lock and dam provides for a 9-foot
channel from Morgantown dam to lock and dam 12. Upon comple-
tion of improvements at dam 8, and construction of Hildebrand
lock and dam and Opekiska lock and dam, a minimum channel
depth of 9 feet will exist for the entire length of the river, varying
in width from a minimum of 300 feet to full width of the river at
the mouth. Reconstruction of the 56-foot lock (river chamber) at
locks 2 was commenced by contract January 7, 1949, and was ac-
cepted as complete June 29, 1951. Construction of the 110-foot lock
 (land chamber) was initiated by contract June 26, 1951, and was
completed November 29, 1953. Construction of Morgantown lock
and dam was started by contract September 9, 1948, and accepted
as complete December 22, 1950. All miscellaneous appurtenances
pertaining to the new lock are complete. Relocations and land ac-
quisition are complete. No work has been performed in connection
with the proposed replacement of locks and dams 5 and 6. In con-
nection with the proposed improvements at dam 8, a definite pro-
ject report is complete and detailed design studies initiated. Work
on this project has been temporarily deferred. The general design
              RIVERS AND HARBORS-PITTSBURGH,                               PA., DISTRICT                      995
memorandum is complete and was submitted March 25, 1954, for
Hildebrand lock and dam. Detailed design and preparation of plans
is in progress.
   Work remaining for completion of the project consists of the
following: Replacement of locks 5 and 6; raising the crest of dam
8; construction of Hildebrand lock and dam which will replace
existing locks and dams 12 and 13; and construction of Opekiska
lock and dam to replace existing locks and dams 14 and 15.
   The total costs of the existing project to the end of the fiscal
year were as follows:

                                                                                      Costs

                           Funds                                                 Operation and
                                                                  New work       maintenance,              Total
                                                                                      general

Regular___                                                        $36, 289,673        $15,109,982        $51, 399,655
Maintenance and operation_______________________________                                  150,000            150,000
      Total                                                       36, 289, 673         15, 259, 982       51, 549, 655



   In addition the sum of $20,446,587 was expended between July 7,
1897, and June 30, 1937, on the operation and care of the works
of improvement under the provisions of the permanent indefinite
appropriation for such purposes.
                                     Cost and financial summary

                                             Fiscal year ending June 30                               Total to June
                                                                                                  30, 1954, includ-
                                                                                                  ing fiscal years
                              1950        1951         1952            1953            1954           priorto 19501

New work:
   Appropriated-__--_ $6, 615,000 $5,511,000        $4, 064,400    $2,696,000     $    321,589           $41,744,502
   Cost----------- -    8,778,155 4,297,271          2,904, 523     5,006,351          838,922            41, 710,214
Maintenance:
   Appropriated      _- 1, 426,870   986, 260        1, 745, 100 1, 335, 100       1, 110, 000            35, 770, 471
   Cost--------------- 1,399,260 1,058,401           1,462,060 1,464,219           1,216,247              35,707, 311


  1Includes $5,420,541 for new work and $742 for maintenance for previous projects.
Other new work data:
     Unobligated balance, fiscal year ending June 30, 1954_------------                   $33,695
     Appropriated for succeeding fiscal year ending June 30, 1955----- --                  40,000
     Unobligated balances available       for succeeding       fiscal year ending June
       30, 1955 ----------------------------------------------                             73,695
     Estimated additional amount needed to be appropriated for comple-
  tion of existing project_                                                            82,127,039

4. OHIO RIVER ABOVE MILE 109, BETWEEN CAPTINA ISLAND
AND POWHATAN POINT, CONSTRUCTION OF LOCKS AND DAMS
    For report on this improvement, see page 869.
                     5. OHIO RIVER, OPEN-CHANNEL WORK
    For report on this improvement, see page 875.
996               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                            6. INACTIVE NAVIGATION PROJECTS

                                                                            Cost to June 30, 1954
                                                              For last                                  Estimated
                     Name of project                      full report                                     amount
                                                          see annual                   Operations       required to
                                                          report for-    Construction     and            complete
                                                                                      maintenance

1.   Allegheny River, Pa., open-channel work..                 1934       $197, 000.00   $133,839.89         (1)
2.   Beaver and Mahoning Rivers, Pa. and Ohio 2__              1938                                      $57, 000, 000
3.   Buckhannon River, W. Va.3 4                               1893          5,500.00    ---                 (1)
4.   Cheat River, W. Va.3 4_________________________           1895         12,996.84 -                     (1)
5.                          .... ____....______
     Pittsburgh Harbor, Pa_____                         .      1922        110,662.90      81,613.33        (1)
6.   Youghiogheny River, Pa---        .................  ..    1952       5 47,194.75   6 126, 239.25    78,785,000
   1 Completed.
  2 Under date of Jan. 23,1939, the Chief of Engineers recommended the construction of a waterway ex-
tending from the Ohio River through the Beaver, Mahoning and Grand River Valleys to Lake Erie (H.
Doc. 178, 76th Cong., 1st sess.).
  3 Abandonment recommended in H. Doc. 467, 69th Cong., 1st sess.
  4 No commerce reported.
     5 Previous project data.
     e Includes $1,700 expended under previous project.
     7 Lack of interest in project.

                       7. PORTVILLE,              OHIO RIVER BASIN, N. Y.
   Location. The village of Portville is located on the east bank of
the Allegheny River between two tributaries, Oswayo and Lilli-
bridge Creeks in the southeastern corner of Cataraugus County in
southwestern New York. Dodge Creek, another tributary, flows
through the village. It is located in an essentially flat flood plain,
approximately 265 miles above the mouth of the Allegheny River
at Pittsburgh, Pa. (See U. S. Geological chart for Olean, N. Y.)
   Existing project. The plan of improvement provides for the
construction of dikes and flood walls along Dodge Creek, Oswayo
Creek and the Allegheny River, realinement of Lillibridge Creek,
erection of appurtenant structures, and provision of internal drain-
age facilities. The project is designed to accommodate discharges
slightly greater than that of the maximum flood of record. The
existing project was authorized by the Flood Control Act approved
July 24, 1946.
   The Federal cost of the completed project is $2,070,484; non-
Federal cost $353,000.
   Local cooperation. Formal assurances of local cooperation
have been received from the State of New York.
   Operations and results during fiscal year. New work: Miscel-
laneous engineering and design work was completed by hired labor.
Settlement was made on a claim arising from construction of qnit 2.
   The costs, all for new work, were $11,760.
   Condition at end of fiscal year. Construction of unit 1 of the
flood protection works was started by contract July 23, 1949, and
was completed October 24, 1950. Unit 2 of the project was started
by contract May 22, 1950, and was completed November 8, 1951.
The State of New York has formally accepted the completed pro-
ject and assumed the responsibility for maintenance and operation
in accordance with operations manuals furnished them. Construc-
tion of Main Street Bridge by the State of New York was corre-
lated with construction of the project. The cost borne by the Gov-
                  FLOOD CONTROL-PITTSBURGH,                           PA., DISTRICT                    997
ernment was representative of the cost of raising the bridge had
that plan been followed.
  The total costs to the end of the fiscal year were $2,070,484, all
for new work.
                                    Cost and financidl summary

                                             Fiscal year ending June 30                       Total to June
                                                                                             30, 1954, includ-

                             1950         1951         1952           1953         1954       priorto 1950


New work:
   Appropriated_      _ .   $520, 900   $1,198,100 .             --   $14, 200   -$34, 316         $2, 070,484
   Cost ------------- ---    435,264     1,076,310     437,030          3,975       11,760          2,070,484



                      8. OLEAN, OHIO RIVER BASIN, N. Y.
    Location. The city of Olean is located at the confluence of the
Allegheny River and Olean Creek in the southeastern corner of
Cattaraugus County in southwestern New York. It is situated in
a broad glacial outwash filled valley of the Allegheny River in the
maturely dissected Allegheny plateau approximately 258 miles
above the mouth of the Allegheny River at Pittsburgh, Pa. (See
U. S. Geological Chart for Olean, N. Y.)
    Existing project. The plan of improvement provides for the
improvement and extension of the existing dike and appurtenant
structures along the Allegheny River, Olean Creek, and Kings
Brook, together with certain limited channel improvements in the
Allegheny River and Kings Brook. The project is designed to ac-
commodate discharges slightly greater than that of the maximum
flood of record. The existing project was authorized by the Flood
Control Act approved July 24, 1946.
    The Federal cost of the completed project is $3,217,531; non-
Federal cost $597,000.
   Local cooperation. Formal assurances of local cooperation
have been received from the State of New York.
    Operations and results during fiscal year. New work: Engi-
neering and design was completed during the year. Settlement was
made on a claim arising for construction of Unit 2B. Seeding of
the dike was accepted.
   The costs were $3,365, all for new work.
    Condition at end of fiscal year. Construction of the project by
contract was started April 19, 1948. The work was accomplished
by units, namely, units 1, 2A and 2B. Unit 1 was started April 19,
1948, and was completed May 31, 1949. Unit 2A was started July 7,
1949, and completed May 31, 1951. Unit 2B was started June 1,
1950, and completed October 4, 1952. The completed units were
turned over to the State of New York on December 22, 1950, July
19, 1951, and September 29, 1952, respectively, for assumption of
operation and maintenance in accordance with operation manuals
furnished them.
   The total costs to the end of the fiscal year were $3,217,531, all
for new work.
998         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                   Cost and financial summary

                                          Fiscal year ending June 30                    Total to June
                                                         s lya .... .30,
                                                        endng                               1954, includ-
                            1950         1951
                                                    -



                                                        1952          1953   1954
                                                                                        ing fiscal years
                                                                                          priorto 1950

New work:
   Appropriated ........   $744,100   $1, 200,000   $ 42,900      $  1,700   -$4,169          $3, 217,531
   Cost----------------     855,437    1,015,905     740,495       110,302      3,365          3,217,531



                                      9.BRADFORD, PA.
   Location. The city of Bradford is located at the junction of the
East and West Branches of Tunungwant Creek in northern
McKean County, northwestern Pennsylvania. It is situated in the
well-known Bradford oil field on a broad plain at the head on Tun-
ungwant Creek, a tributary of the upper Allegheny River, in the
maturely dissected northern part of the Kanawha section of the
Appalachian province, approximately 159 miles northeast of Pitts-
burgh, Pa. (See U. S. Geological charts for Bradford, Pa.-N. Y.,
Kinzua, Pa.-N. Y., and Salamanca, N. Y.)
   Existing project. The plan of improvement provides for in-
creasing the channel capacity by deepening, lining and construc-
tion of cutoffs in the existing channels. The extent of the plan in-
volves 'improvements for Tunungwant Creek, East Branch, West
Branch, Foster Brook, Bolivar Run, and Kendall Creek. The proj-
ect is designed to accommodate discharges 50 percent greater
than that of the maximum flood of record. The existing project
was authorized by the Flood Control Act approved May 17, 1950.
   The estimated Federal cost for new work (1954) is $8,100,000;
the estimated non-Federal cost is $1,940,000.
   Local cooperation. Specific requirements of local cooperation
required by the authorizing act are set forth in report of the Chief
of Engineers published in Senate Document 20, 81st Congress, 1st
session. A Bradford district flood control authority, composed of
representatives of Bradford, McKean County, Borough of Lewis
Run, and Foster, Bradford and Lafayette Townships, Pa., has been
constituted under the laws of Pennsylvania to conduct flood. con-
trol affairs for the Bradford area. This authority expects to provide
the required local cooperation. The Commonwealth of Pennsyl-
vania has been active in solving the flood problem existing at Brad-
ford and has improved the lower portion of Tunungwant Creek,
conforming to the project plan.
   Operations and results during fiscal year. New work: Advance
engineering and design for a general design memorandum was
completed. Field surveys were also completed. Preparation of con-
tract plans and specifications was initiated.
   The total costs were $26,545, all for new work.
   Condition at end of fiscal year. A general design memorandum
is complete. Preparation of contract plans and specifications is
under way. Construction of the project has not been initiated.
   The total costs to the end of the fiscal year, all for new work,
were $62,574.
                 FLOOD CONTROL-PITTSBURGH, PA., DISTRICT                                      999
                                   Cost and financial summary

                                          Fiscal year ending June 30                  Total to June
                                                                                   30, 1954, includ-
                                                                                   ing fiscal years
                            1950         1951       1952         1953       1954      priorto 1950


New work:                                                        $
   Appropriated -.......
                       ........           ..
                                         _....-..  .-            $54,000    $10,000          $64,000
   Cost .........-----    ------------       ---------            36,029     26,545           62,574


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954--- ---------       $1, 426
    Appropriated for succeeding fiscal year ending June 30, 1955_-           80,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955---,-------------------------              ---------- ----     81,426
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project--------------------------------            7,956,000

        10. TIONESTA            RESERVOIR,          OHIO RIVER             BASIN, PA.

   Location. The dam site is located on Tionesta Creek, 1.25 miles
above the junction of the creek with the Allegheny River at Tio-
nesta, Pa., and about 78 miles northeast of Pittsburgh, Pa. The
reservoir is located entirely in Forest County, Pa. (See U. S. Geo-
logical Survey charts for Tionesta, Tidioute, and Sheffield, Pa.)
   Existing project. This provides for the construction of a flood
control reservoir dam of the earthfill type with separate uncon-
trolled saddle spillway and tunnel outlet works. The dam is 1,050
feet long at the top, rises 154 feet above the stream bed, and pro-
vides for the gross storage of 133,400 acre-feet of water from a
tributary drainage area of 478 square miles. Of this storage
125,600 acre-feet are available for flood prevention at Pittsburgh
and in the upper Ohio Valley, generally. The remaining 7,800 acre-
feet are in permanent storage. The reservoir is operated as a unit
of a coordinated reservoir system for the protection of Pittsburgh
and the upper Ohio Valley generally. The existing project was au-
thorized by the Flood Control Act approved June 22, 1936 and
June 28, 1938.
   The cost of the completed project is $5,213,401. The latest
 (1954) approved estimate for annual cost of operation and main-
tenance is $61,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operationsand results during fiscal year. Operation and main-
tenance, general: The reservoir was operated for the benefit of
flood control, as required, and necessary repairs were made to the
dam and its appurtenances and to the operators' quarters and
grounds. In addition to ordinary repairs to structures and plant,
gate hoist cables were replaced.
   No damaging floods occurred on the Allegheny or Upper Ohio
River (above mile 109) during the year. Heavy rainfall during
February 28 to March 1, 1954, produced a moderate rise which re-
sulted in the reservoir reaching the highest level during the year,
elevation 1114.5 on March 3 or 29.5 feet above minimum pool.
This represents an impoundment of 22,900 acre-feet above that
 1000             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

pool or about 18 percent of the usable capacity of the reservoir.
The reservoir pool was drawn down below minimum pool during
April 28 to May 1, 1954. An oil line broke in a headwater stream
of the basin releasing crude oil which drained into the reservoir.
To decrease the reservoir pollution, the pool was lowered rapidly
as the oil reached the reservoir pool pulling practically all the oil
through the outlet tunnel. The discharge was regulated during
May 13 to 27, 1954, to facilitate the construction of an outflow
gage house downstream from the outlet tunnel. During the re-
mainder of the year, routine operations were made except on the
occasion of 18 minor rises when some water was stored and re-
leased as: river conditions permitted.
   Activities under the reservoir management program comprising
sanitation measures, conservation, land management and opera-
tion and maintenance of public use facilities were continued.
   The total costs were $51,495, all for operation and maintenance.
   Condition at end of fiscal year. The dam and its appurtenances
are complete, and the reservoir is in operation as a unit of the
reservoir system designed for the protection of Pittsburgh and the
reduction of flood heights in the upper Ohio Valley, generally. Con-
struction of the dam was started in May 1938 and completed in
January 1941. All work relative to relocations and acquisition of
land is complete. The total acreage involved has been acquired
and consists of 3,040 acres in fee simple and flowage easements
over 349 acres. A master land use plan is complete.
   The total costs to the end of the fiscal year were as follows:
Regular funds:
    New work.    ....................................... ..............................               $5 189, 200
    Operation and maintenance, general.........................408,                                           710
      Total-....----:.........                                                                          5, 597, 910
Emergency Relief funds: New work                          ------------------.......-------------            24,201

          Total costs, all funds...................--------------------------------                     5, 622, 111

                                           Cost and financial summary

                                                     Fiscal year ending June 30                       Total to June
                                                                                                     30, 1954, includ-
                                                                                                     ing fiscal years
                                    1950           1951           1952           1953      1954        prior to 1950

New work:
   Appropriated ........                         -$60,000 - ------- -- -----
                                                                          ---   --   ------              S$5,213,401
   Cost --------------              $59,921          4, 412  $14,407 -- - - - -    -----                  . 5' 213, 401
Maintenance:
    Appropriated ..          .       44,000         43,800         32, 500       $56,000   $50,600            417,100
     Cost...
          _ _______..        .       46,642         33, 904        42, 819        50,971    51,495            408, 710


  I Includes $24,201 Emergency Relief funds.

   11. EAST BRANCH, CLARION RIVER RESERVOIR, OHIO RIVER
                         BASIN, PA.

  Location. The dam site is located in Elk County, Pa., on the
East Branch of the Clarion River above Middle Fork, approxi-
mately 7 miles above the junction of the East and West Branches
            FLOOD CONTROL-PITTSBURGH,       PA., DISTRICT        1001
  of the Clarion River at Johnsonburg, Pa., and approximately 151
  miles northeast of Pittsburgh, Pa. The reservoir is located entirely
  in Elk County, Pa. (See U. S. Geological Survey chart for Mount
  Jewett, Pa.)
     Existing project. This provides for the construction of a reser-
  voir dam of the rolled earthfill type with gate-controlled concrete
  tunnel under right abutment and a paved uncontrolled spillway
  on the left abutment slope. The dam, 1,725 feet long at the top
  and rising 184 feet above the stream bed, will provide for the gross
  controlled storage of 84,300 acre-feet, from a tributary drainage
  area of 72.5 square miles. Of the total storage, 83,300 acre-feet
  will be available for flood control and low water regulation pur-
  poses, in the Clarion River Valley below. The remaining 1,000
  acre-feet will be in permanent storage. The reservoir will be oper-
  ated as a unit of a coordinated reservoir system for the protection
of Pittsburgh and the upper Ohio Valley, generally. The project
was selected for construction under the general authorization for
the Ohio River Basin contained in the Flood Control Acts approved
June 28, 1938, and December 22, 1944. The estimate of cost for
new work (1954) is $9,003,000. The latest (1954) approved esti-
mate for annual cost of operation and maintenance is $34,000.
    Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
    Operations and results during fiscal year. New work: Engi-
neering and design work was continued during the year by hired
labor. Preparation of plans and specifications for recreation facili-
ties was under way by hired labor. Construction of the operators'
quarters, permanent warehousing, utilities and parking area was
completed by contract November 25, 1953. General cleanup and
landscaping was completed by hired labor. Remedial measures for
the outlet works were completed by hired labor. Installation of
recording gages was initiated. Acquisition of land and related
work was continued.
    Operation and maintenance, general: The reservoir was oper-
ated for the benefit of flood control, as required, and necessary re-
pairs were made to the dam and its appurtenances.
    Heavy rainfall late on August 9, 1953, over the upper Clarion
River Basin after a period of appreciable antecedent rainfall
caused nuisance flooding at Ridgway and light flooding at Johnson-
burg. The Clarion River crested on the 10th at 7.2 feet at John-
sonburg and 7.4 feet at Ridgway, while the reductions by the reser-
voir were 3.0 feet and 2.85 feet, respectively. Moderate flood bene-
fits were achieved by this reservoir along the upper Clarion River
valley and were as follows: Ridgway Damage District, $43,400;
Johnsonburg Damage district, $24,900. The water stored during
this flood caused the reservoir to rise to elevation 1658.5 on the
12th or 9.2 feet above the normal drawdown pool level on that
date. This represents an impoundment of 8,800 acre-feet above
schedule or about 22 percent of the usable flood storage capacity of
the reservoir for that date. This rise resulted in the use of the
maximum amount and percent of flood control storage for the year.
    Heavy rainfall on March 1, 1954, over the upper Clarion River
1002     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Basin caused nuisance flooding at both Johnsonburg and Ridgway.
The Clarion River crested in the evening on the 1st at 6.5 feet at
Johnsonburg and 9.0 feet at Ridgway, while the reductions by the
reservoir were 1.0 feet and 0.7 foot, respectively. Light flood bene-
fits were achieved along the Upper Clarion River valley and were
as follows: Ridgway Damage District, $11,700; Johnsonburg Dam-
age District, $8,800. Water was stored during this flood in accord-
ance with the low water storage schedule, the reservoir pool rising
to the upper storage guide for early March.
   During the remainder of the year, routine operations were made
in accordance with the low water schedule for maintaining satis-
factory flows in the upper Clarion River, except on the occasion of
17 minor rises when water was stored, with the excess above nor-
mal schedule storage being released as river conditions permitted.
Heavy rainfall during April 26-27, 1954, produced a minor rise
which resulted in the reservoir reaching the highest level during
the year, elevation 1671.5 on the 29th, or 1.5 feet above summer
pool. This represents an impoundment of 1,800 acre-feet above
summer pool or about 91/2 percent of the usable summer flood stor-
age capacity of the reservoir.
   On November 22, 1953, the reservoir had fallen to elevation
1621.2, the lowest elevation for the 1953 low water season; the
season of the low water reservoir operation which was on a com-
plete low water storage schedule.
   The total costs were $206,630, of which $174,915 was for new
work and $31,715 for operation and maintenance.
   Condition at end of fiscal year. The opencut excavation for the
outlet works was started June 1947 and completed May 1948. Con-
struction of the outlet works commenced June 8, 1948, and ac-
ceptance of the work was made May 29, 1951. A contract for fur-
nishing operating equipment and its installation in the control
tower of the outlet works is complete. Construction of the embank-
ment and spillway was initiated July 20, 1949, and was accepted
as complete July 17, 1952. Reservoir clearing was completed
July 3, 1952. Construction of the operators' quarters, permanent
warehousing, utilities and parking area by contract was initiated
March 10, 1953, and was accepted as complete November 25, 1953.
Landscaping and general cleanup is complete. Remedial measures
for the outlet works are complete. Land acquisition and related
work is approximately 95 percent complete. The total acreage in-
volved is 2,072 acres and consists of 1,252 acres in fee simple and
flowage easements over 820 acres. Of a total of 62 tracts, 57 have
been acquired to date. The dam was placed in operation during
June 1952 for flood control and stream flow regulation (water
supply and pollution abatement).
   Work remaining to be done consists of miscellaneous engineer-
ing and design, acquisition of land, installation of recording gages,
and construction of recreation facilities.
   The total costs at the end of the fiscal year were $8,969,427, of
which $8,914,293 was for new work and $55,134 for operation and
maintenance, general.
                 FLOOD CONTROL--PITTSBURGH,                                 PA., DISTRICT                    1003
                                          Cost and financial summary

                                                   Fiscal year ending June 30                         Total to June
                                                                                        __30,            1954, includ-
                                                                                                     ing fiscal years
                                  1950            1951          1952         1953           1954       prior to 1950

New work:
   Appropriated-._----       $2,200,000        $1,300,000    $2,000,000     $313,900     -$14, 232         $8, 988,268
       ---------------
   Cost....                   1, 707, 661       2, 735,182    2, 398, 327    150,012       174,915          8,.914, 293
Maintenance:
   Appropriatednan-                                                8,500      18,000        28,900             55,400
   Cost.-----------..    ----.--------------                       2,968      20, 451       31,715             55,134



Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_-                 - $23,469
    Appropriated for succeeding fiscal year ending June 30, 1955--------- 14,232
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955____                                            -37,701

                12. JOHNSONBURG, OHIO RIVER BASIN, PA.
   Location. The city of Johnsonburg is located at the confluence
of the East and West branches of Clarion River in Elk County, Pa.,
about 100 miles northeast of Pittsburgh, Pa. (See U. S. Geological
Survey chart for Ridgeway, Pa.)
   Existing project. The plan of improvement provides for con-
struction of dikes, walls, and appurtenant drainage facilities, pri-
marily along the right bank of the West Branch of Clarion River,
and improvement of the channel of the West Branch and Silver
Creek. The existing project was authorized by the Flood Control
Act of 1944.
   The estimated Federal cost for new work (1954) is $750,000;
the estimated non-Federal cost is $127,000.
   Local cooperation. The borough of Johnsonburg has signified
by letter their willingness to comply with the requirements for
local cooperation.
   Operations and results during fiscal year. New work: A gen-
eral design memorandum and plans and specifications for Unit I
were completed.
   The total costs were $29,999, all for new work.
   Condition at end of fiscal year. A general design memorandum
and plans and specifications for construction of Unit I are com-
plete. Construction has not been initiated.
   The total costs to the end of the fiscal year, all for new work,
were $53,850.
1004        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                 Cost and financial summary

                                       Fiscal year ending June 30                    Total to June
                                                                                 30, 1954, includ-
                                                                                 ing fiscal years
                          1950        1951        1952        1953:     1954         prior to 1950


New work:
   Appropriated- --.. .     $21,
                               551   -$4, 000      -$700----       --   30,000              $53,
                                                                                               851
   Cost...-----------------  5,580     15,035       2,642------------   29,999               53,850


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 _..                       $1
    Appropriated for succeeding fiscal year ending June 30, 1955_-            300,000
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955_             --     -------- -------             -------    ------ 300,001
    Estimated additional amount needed to be appropriated for completion
      of existing project_       --                                           396,149

            13. PUNXSUTAWNEY,                OHIO        RIVER BASIN,          PA.
   Location. The borough of Punxsutawney is located on Mahon-
ing Creek in Jefferson County, Pa., approximately 85 miles north-
east of Pittsburgh, Pa. It is situated on a comparatively wide,
alluvial flood plain about 52 miles above the mouth of the stream
and 30 miles above the Mahoning Creek flood control dam. (See
U. S. Geological Survey charts for Punxsutawney and Smicks-
burg, Pa.)
   Existing project. The plan of improvement consists princi-
pally of deepening, widening, and straightening the creek channel
for a distance of approximately 18,838 feet, and complementing
this with approximately 10,352 feet of rolled fill dikes, 2,627 feet of
walls, 700 feet of pressure conduit for Barrett Run, and internal
drainage facilities including a pumping station and flush house.
The project is designed to accommodate discharges 20 percent
greater than that of the maximum flood of record. The existing
project was authorized by the Flood Control Act approved June 28,
1938.
   The estimated Federal cost for new work (1954) is $3,585,200;
the estimated non-Federal cost is $199,000. The latest (1954) ap-
proved estimate for annual cost of maintenance is $8,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operationsand results during fiscal year. New work: All work
relative to land acquisition and related work was completed. Pre-
paration of plans and specifications for remedial control facilities
on outlets through the dike were initiated during the year by
hired labor.
   Operation and maintenance, general: Routine inspections were
made throughout the year.
   The total costs were $2,582, of which $707 was for new work and
$1,875 for operation and maintenance.
   Condition at end of fiscal year. The project is complete ex-
cept for remedial control facilities on outlets through the dikes.
Construction was accomplished by units consisting of units 1, 2,
2A, and 2B. Construction of unit 1, involving 10,200 linear feet of
improvement was started in May 1946 and was completed in May
                  FLOOD CONTROL -PITTSBURGH,                             PA., DISTRICT ....             1005

1947.: Unit 2 (initial work), consisting of relocation of sewers
and construction of the Barrett Run conduit, was started in De-
cember 1947 and was completed in August 1948. Unit 2A, involv-
ing 4,400 linear feet of improvement was started in April 1948
and was completed in April 1949. Unit 2B, involving 4,225 linear
feet of improvement, was started in February 1949 and was com-
pleted in June 1950. Relocations are complete. Acquisition :of
land is complete. The total acreage involved in unit 1 consists of
perpetual easements over 49.7 acres and temporary easements over
18.9 acres. The total acreage involved in unit 2 consists of per-
petual easements over 47.8 acres and temporary easements over
1.9 acres. On July 31, 1950, the Borough of Punxsutawney
formally accepted the complete project and assumed the responsi-
bility for maintenance and operation. Work remaining to be done
consists of construction of remedial control facilities on outlets
through the dike (unit 2--initial work).
   The total costs to the end of the fiscal year were $3,591,178, of
which $3,581,077 was for new work and $10,101 for operation and
maintenance, general. In addition, $180,485 was expended from
contributed funds.
                                     Cost and financial summary
                                        UNITED STATES FUNDS

                                                Fiscal year ending June 30                       Total to June
                                                                                                30, 1954, includ-
                                                                                                ing fiscal years
                              1950             1951         1952          1953       1954        priorto 1950

New work:
   Appropriated.            $830,000        -$150,000     ..-----        --$7,800   -$7,000         1$3585,163
   Cost --...-.-
         .       ..-         797, 446           33, 690     $19, 361      -9, 409         707       13, 581,077
Maintenance:
   Appropriated              --------           14,000        3,000       -8, 000      1,400              10, 400
   Cost ---------------   ----------- .
                                      --         1,971        5, 750          505      1, 875             10,101


 '.In addition $180,485 for new work was expended from contributed funds.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954             -  - - $ 4,086
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955_                            -                    -                  4,086
                                     Cost and financial summary
                                           CONTRIBUTED FUNDS


                                                Fiscal year ending June 30                       Total to June
                                                                                                30,1954,includ-
                                                                                                        years
                                                                                                ing fical
                              1950             1951         1952          1953       1954        priorto 1950

New work:
   Appropriated---- ----------------------                -$30, 000     - -       *-$18,297             $180,485
   Cost----------------  $37,256                                          $11,403----- ...               180,485


                                         tothe Borough ofPunxsutawney, Punxsutawney, Pa.
 *Refund ofthe unexpended balance of$18,297

  14. MAHONING CREEK RESERVOIR,                                        OHIO RIVER BASIN, PA.
   Location. The dam site is located on Mahoning Creek in Arm-
strong County, Pa., 21.6 miles above the junction of the creek with
the Allegheny River. It is about 61/2 miles southeast of New Bethle-
hem, Pa.; and about 51 miles northeast of Pittsburgh, Pa.                                                 The
1006     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

reservoir is located in Armstrong, Ind., and Jefferson Counties, Pa.
(See U. S. Geological Survey charts for Rural Valley and Smicks-
burg, Pa.)
   Existing project. This provides for the construction of a flood
control reservoir dam of the concrete :gravity type with a gate-
controlled center spillway flanked by abutment sections joining the
valley sides. The dam is 926 feet long at the top, rises 162 feet
above:the stream-bed, and provides for the gross controlled storage
of 74,200 acre-feet of water from a tributary drainage area of 339
square.miles. Of this storage 69,700 acre-feet are available for
flood prevention at Pittsburgh and in the upper Ohio Valley, gen-
erally. The remaining 4,500 acre-feet are in permanent storage.
Two penstocks are contained in the structure for possible future
generation of hydroelectric power. The reservoir is operated as a
unit of a coordinated reservoir system for the protection of Pitts-
burgh and the upper Ohio Valley, generally. The existing project
was authorized by the Flood Control Acts approved June 22, 1936,
and June 28, 1938. The cost of the completed project is $6,421,345.
The latest (1954) approved estimate for annual cost of operation
and maintenance is $47,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operationsand results during fiscal year. Operation and main-
tenance general: The reservoir was operated for flood control, as
required, and necessary repairs made to the structure and to the
operators' quarter and grounds throughout the year.
    No damaging floods occurred on the Allegheny or upper Ohio
River (above mile 109) during the year. Heavy rainfall during
February 28-March 1, 1954, produced a moderate rise which re-
sulted in the reservoir reaching the highest level during the year,
elevation 1127.6 on March 3, 1954, or 52.6 feet above minimum
pool. This represents a net impoundment of 20,000 acre feet above
that pool or about 29 percent of the usable capacity of the reservoir.
During the remainder of the year routine operations were made
except on the occasion of 18 minor rises when some water was
stored and released as river conditions permitted.
    Activities under the reservoir management program comprising
sanitation measures, conservation, land management and operation
and maintenance of public use facilities were continued. An access
road and parking area were resurfaced by contract.
    The total costs were $38,969, all for operation and maintenance.
    Condition at end of fiscal year. The dam and its appurtenances
are complete and the reservoir is in operation as a unit of the
reservoir system designed for the protection of Pittsburgh and the
reduction of flood heights in the upper Ohio Valley generally.
Construction of the dam was started in February 1939 and com-
pleted in June 1941. All work in connection with relocations and
acquisition of land is complete. The total acreage involved has been
acquired and consists of 2,533.49 acres in fee simple and flowage
easements over 76.89 acres.
    The total costs to the end of the fiscal year were as follows:
                 FLOOD CONTROL-PITTSBURGH, PA., DISTRICT                                                              1007

                                                                                                    Costs

                               Funds                                                           Operation and
                                                                                 New work      maintenance,          Total
                                                                                                   general

Regular..i   . .                 -            .       .     .                 "        I$6,395,674      $339,944   $6,735,618
Emergency relief-----------          ....         .        ....     ..---------------------
                                                                                   -        25,671----------------     25,671
     TTotal-     ------------------------------------------ 6,421,345                                  339,944      6,761,289


                                            Cost and financial summary

                                                           Fiscal year ending June 30                         Total to June
                           "     '                                                 __                        30, 1954, includ-
                                                                                                             ing fiscal years
                                1950                      1951        1952          1953          1954         priorto 1950

New work:
   Appropriated--- ---..--------                  ----$62, 609                                                   '1$6, 421,345
   Cost------.. -----.. --  $12,149                        629                                                     1 6, 421, 345
Maintenance:
   Appropriated-........     27, 000                      25, 000     $36, 000      $21, 000     $36, 300             341,300
   Cost----------------      32,524                       21,097       31,145        26, 950      38,969              339,944


1Includes $25,671 Emergency Relief funds.

  15. CROOKED            CREEK RESERVOIR,                                    OHIO RIVER              BASIN,          PA.
   Location. The dam site is located on Crooked Creek 6.7 miles
above the junction of the creek with the Allegheny River near Ford
City, Pa., and about 32 miles northeast of Pittsburgh, Pa. The
reservoir is located entirely in Armstrong County, Pa. (See U. S.
Geological Survey charts for Freeport and Elders Ridge, Pa.)
   Existing project. This provides for the construction of a flood-
control reservoir dam of the earthfill type with separate uncon-
trolled saddle spillway and tunnel outlet works. The dam is 1,480
feet long at the top, rises 143 feet above the streambed, and pro-
vides for the gross storage of 93,900 acre-feet of water from a
tributary drainage area of 277 square miles. Of this storage 89,400
acre-feet are available for flood prevention at Pittsburgh and in
the Upper Ohio Valley, generally. The remaining 4,500 acre-feet
are in permanent storage. The reservoir is operated as a unit of a
coordinated reservoir system for the protection of Pittsburgh and
the upper Ohio Valley generally. The existing project was author-
ized by the Flood Control Acts approved June 22, 1936, and June
28, 1938. The cost of the completed project is $4,204,888. The latest
 (1954) approved estimate for annual cost of operation and main-
tenance is $37,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operationsand results during fiscal year. Operation and main-
tenance, general: The reservoir was operated for the benefit of
flood control, as required, and necessary repairs were made to the
dam and its appurtenances and to operators' quarters and grounds.
   No damaging floods occurred on the Allegheny or upper Ohio
River (above mile 109) during the year. Heavy rainfall during
February 28-March 1, 1954, produced a moderate rise which
1008           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

resulted in the reservoir reaching the highest level during the year,
elevation 864.5 on March 3, 1954, or 24.5 feet above minimum pool.
This represents a net impoundment of 14,300 acre-feet above that
pool or about 16 percent of the usable capacity of the reservoir.
During the remainder of the year routine operations were made
except on the occasion of 16 minor rises when some water was
stored and released as river conditions permitted.
   Activities under the reservoir management program comprising
sanitation measures, conservation, land management and operation
and maintenance of certain public use facilities were continued.
   The total costs were $24,823, all for operation and maintenance.
   Condition at end of fiscal year. The dam and its appurtenances
are complete and the reservoir is in operation as a unit of the
reservoir system designed for the protection of Pittsburgh and the
reduction of flood heights in the upper Ohio Valley, generally.
Construction of the dam was started in March 1938 and completed
in October 1940. All work relative to the relocations and acquisition
of land is complete. The total acreage involved has been acquired
and consists of 3,563.55 acres in fee simple and flowage easements
over 99.98 acres.
   The total costs to the end of the fiscal year were as follows:

                                                                                                  Costs

                                Funds                                                          Operation and
                                                                                 New work      maintenance,         Total
                                                                                                  general

Regular              ---------------------------------------                     $4, 141,000        $393, 529     $4,534,629
Emergency relief..     ..       ............-------------------
                                                      -----------------               63,788                          63,788
     Total........------.......----------------------------------------
                                                                ...     .         4,204,888            393,529     4,598,417



                                         Cost and financialsummary

                                                      Fiscal year ending June 30                            Total to June
                                                                             -                              30, 1954, includ-
                                                                                                            ing fiscal years
                                 1950              1951               1952         1953         1954         priorto 1950

New work:
   Appropriated .------------------------------------                                                              4,204,888
                                                                                                                  $---------------------
   Cost------------ -----         $3,958           $27,381                                                        4,204,888
Maintenance:
   Appropriated-- ------          65,000             36, 500          $27,500      $24,500      $21,200              396,700
   Cost----------------..         72, 608            32,848            25,464       29,226       24,823              393,529

  Includes $63,788 from Emergency Relief funds.

                     16. JOHNSTOWN, OHIO RIVER BASIN, PA.
   Location. The city of Johnstown is located in southwestern
Cambria County, Pa., approximately 58 miles east of Pittsburgh,
Pa. It is situated in a deep and comparatively narrow valley at the
junction of Stony Creek and Little Conemaugh River, which unite
to form the Conemaugh River. (See U.S. Geological Survey Chart
for Johnstown, Pa.)
  Existing project. The plan of improvement provides for in-
creasing the channel capacity by enlarging and realining the exist-
                      FLOOD CONTROL-PITTSBURGH, PA., DISTRICT                    1009
ing channels and protecting the banks with concrete pavement.
Miscellaneous features of work include relocation of railroad tracks,
highway and utilities, and alterations to sewers, drains, bridge
piers, and other structures. The improvement involves about 46,290
feet of channel as follows: The Conemaugh River for a distance of
19,270 feet extending from the "Point" downstream to about
2,650 feet below the Pennsylvania Railroad bridge at Dornick
Point; the Little Conemaugh River for a distance of 6,950 feet from
the "Point" upstream to about 150 feet below the Pennsylvania
Railroad bridge in the vicinity of Fifth Street; and Stony Creek for
a distance of 20,700 feet from the "Point" upstream to about 500
feet above the Ferndale Bridge in the vicinity of the borough of
Ferndale. The project is designed to accommodate discharges
equivalent to those of the March 1936 flood, the maximum natural
flow of record, with a minimum of overbank flow and to practically
eliminate damages therefrom. The existing project was authorized
by the Flood Control Acts, approved June 22, 1936, and August
28, 1937.
   The cost of the completed project is $8,865,388. The latest (1954)
approved estimate for annual cost of maintenance is $14,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. Operation and main-
tenance, general: The channel was maintained in a satisfactory
condition. Stream gaging activities were performed by hired labor.
Broken concrete paving was repaired and wood handrail replaced
by hired labor. Willow growth was removed from the channel by
contract.
   The costs were $21,303, all for operation and maintenance.
   Condition at end of fiscal year. The improved channels are
fully complete. Construction was accomplished by units, consisting
of units 1, 2, 3, and supplementary unit 2A, all in the Conemaugh
River section; unit 4, comprising the Little Conemaugh River sec-
tion; and units 5 and 6 comprising the Stony Creek section. Con-
struction of the project commenced in August 1938 and was
completed in November 1943. Footer protection for unit 4 was
completed November 1949. All work relative to relocations and
acquisition of land is complete. The total acreage involved has been
acquired and consists of 0.60 acre in fee simple and flowage ease-
ments over 397.16 acres.
   The total costs to the end of the fiscal year were as follows:

                                                                Costs

                            Funds            IOperation and
                                               New work      maintenance,      Total
                                                                general

Regular___--    -     --                       $8, 831,965       $135, 787    $8, 967,752
Emergency relief_..                                 33,423 ----------------..      33,423
      Total    ..... ... .......                8, 865,388         135,787     9, 001,175
1010         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                       Cost and financial summary

                                                Fiscal year ending June 30                              Total to June
                                                                                                       30, 1954, includ-
                                                                                                      ing fiscal years
                                1950           1951          1952           1953           1954         prior to 1950


New work:
   Appropriated .-----      -$24,585                                                                       1$8,865,388
   Cost.----------------      495,960      -----------------------      -----      -----     -               8,865,388
Maintenance:
   Appropriated_...._ -          18,000         $4, 000       $5, 500       $27,800        $26, 500             151,200
   Cost------------- ----....    17, 371         1,360         7, 967        20,044         21,303              135, 787

 ' Includes $33,423 from Emergency Relief funds.

  17. CONEMAUGH RIVER RESERVOIR, OHIO RIVER BASIN, PA.
   Location. The dam site is located on the Conemaugh River in
Indiana and Westmoreland Counties, Pa., 7.5 miles above the junc-
tion of Conemaugh River and Loyalhanna Creek, which form the
head of Kiskiminetas River. It is about 2 miles northeast of Tunnel-
ton, Pa., and about 42 miles east of Pittsburgh, Pa. The reservoir
is located in Westmoreland and Indiana Counties, Pa. (See U. S.
Geological Survey charts for Latrobe, New Florence, and Elders
Ridge, Pa.)
   Existing project. This provides for the construction of a flood
control reservoir dam of the concrete gravity type with a gate-
controlled center spillway flanked by abutment sections joining the
valley sides and an earth embankment terminating in the right abut-
ment. The dam, 1,265 feet long at the top and rising 137 feet above
the stream bed, will provide for the gross controlled storage of
274,000 acre-feet of water from a tributary drainage area of 1,351
square miles. Of this storage, 270,000 acre-feet will be available for
flood control purposes. The remaining 4,000 acre-feet will be in
permanent storage. The reservoir will be operated as a unit of a
coordinated reservoir system for the protection of Pittsburgh and
the upper Ohio Valley, generally. The existing project was author-
ized by the Flood Control Acts approved June 22, 1936, and June 28,
1938.
   The estimated cost for new work (1954) is $45,984,000. The latest
 (1954) approved estimate for annual cost of operation and main-
tenance is $48,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. New work: Engi-
neering and design work were continued during the year.
   Installation of 2 gantry cranes and 14 crest gates, operators'
quarters, storage facilities, public sanitary building and appurten-
ant work, and the dike in the vicinity of Blairsville were completed
by contract during the year. Grading and landscaping were com-
pleted by hired labor. Filling of building foundations and general
cleanup was continued by hired labor.
   In connection with railroad relocations, the Pennsylvania Rail-
road completed operations performed under agreement, which in-
volves alterations to their facilities.
  Work on highway relocations was completed in the reservoir area
as provided for in an agreement with the Commonwealth of Penn-
            FLOOD CONTROL-PITTSBURGH, PA., DISTRICT              1011
sylvania. Relocations or alteration of township roads was completed
as provided for in an agreement. Negotiations with various owning
agencies relative to relocation of utilities in the reservoir area were
continued with work completed on a number of them. Land acquisi-
tion and related work was continued by hired labor.
   Operation and maintenance, general: The reservoir was operated
effectively for flood control as required.
   No damaging floods occurred on the Allegheny or upper Ohio
River (above Mile 109) during the year. Heavy rainfall during
February 28-March 1, 1954, produced a moderate rise which
resulted in the reservoir reaching the highest level during the year,
elevation 928.9 on March 3, 1954, or 48.9 feet above minimum pool.
This represents a net impoundment of 59,600 acre-feet above that
pool or about 22 percent of the usable capacity of the reservoir. The
reservoir was maintained several feet below minimum pool from
July 26, 1953, until August 27, 1953, in order to remove and burn
the debris against the trash boom in the reservoir above the dam.
The outflow was regulated on September 18, 1953, to present a
certain desired effect of outflow from the sluices at the time of the
dedication cermony for the Conemaugh Dam conducted by Major
General Samuel D. Sturgis, Jr., Chief of Engineers. During the
remainder of the year, routine operations were made except on
the occasion of 11 minor rises when some water was stored and
released as river conditions permitted.
   The costs during the year were $2,796,540, of which $2,754,824
was for new work and $41,716 for operation and maintenance.
   Condition at end of fiscal year. Construction of the dam and
appurtenant work was commenced by contract April 25, 1949, and
accepted as complete December 31, 1952. Drilling and grouting the
foundation of the dam by contract commenced June 4, 1952, and
was completed January 14, 1953. Clearing the reservoir area of
floatable material is complete. Contracts to furnish and erect 2
gantry cranes and 14 crest gates were commenced November 16
and: December 9, 1951, and were completed August 6, 1953, and
September 4, 1953, respectively. Construction by contract of opera-
tors' quarters, storage building and public sanitary building was
commenced November 22, 1952, and completed July 21, 1953. Con-
struction of the dike in the vicinity of Blairsville was started
August 1, 1953, and completed January 28, 1954.
   Relocation of the main line of the Conemaugh division of the
Pennsylvania Railroad was started by contract April 1946 and was
accepted by the railroad September 19, 1950. Removal of old track,
bridge superstructures, etc., from the relocated main line of the
Pennsylvania Railroad was completed May 29, 1951. Utilities
affected by the railroad relocation are all complete. Relocation of
the Indiana branch of the Pennsylvania Railroad at Blacklick, Pa.,
was commenced December 16, 1951, and completed November 20,
1952. Work under agreement with the Pennsylvania Railroad pro-
viding for construction or alteration to its facilities is complete.
   All work performed under an agreement with the Commonwealth
of Pennsylvania providing for relocation or alteration to highways
is complete. Work under agreement for relocation or alteration to
township roads is complete. Negotiations with various owning
 1012            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

agencies relative to utility relocations in the reservoir area are
practically complete, and the work in progress.
   Land acquisition and related work is proceeding satisfactorily
and is about 98 percent complete. The total acreage involved for
the railroad relocation is 1,334 acres and consists of 1,331 acres in
fee and easements over 3 acres. Total tracts involved are 114, all of
which have been acquired. The total acreage involved for the dam
and reservoir is 7,401 acres and consists of 7,004 acres in fee and
easements over 397 acres. The total tracts involved are 927, of
which 909 have been acquired.
   Work remaining for completion of the project is as follows:
Engineering and design and acquisition of land and related work
by hired labor; relocation or alteration to utilities in the reservoir
area.
   The total costs to the end of the fiscal year were $44,665,292, of
which $44,606,023 was for new work and $59,269 for operation and
maintenance, general. The above mentioned costs include $5,351
from Emergency Relief funds.
                                        Cost and financial summary

                                                 Fiscal year ending June 30                             Total to June
                                                                                                        30, 1954, includ-
                                                                                                        ing fiscal years
                                 1950          1951               1952          1953          1954       prior to 1950


New work:
   Appropriated -             $7,
                              $-- 400, 000   8,453,400         $9, 500,000   $1, 580,000   -$264, 922      1 $45,   983, 770
   Cost-_....--------------    7, 299, 581   8, 255, 348        6,074, 853    3,480, 921    2,754,824      1 44, 606,023
Maintenance:
    Appropriated-           _   __.. ..-------
                                         _______.____._           -__ 24,000                  36,100                60,100
    Cost---------..
                 ...........-------------------------------------     17,553                  41,716                59, 269


1 Includes $5,351 from Emergency Relief funds.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_                $138,746
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955                          -                  -     -         138,746

      18. LOYALHANNA                    RESERVOIR,                   OHIO       RIVER         BASIN,        PA.
   Location. The dam site is located on Loyalhanna Creek, 4.5
miles above the junction of the creek with the Conemaugh River at
Saltsburg, Pa., and about 29 miles east of Pittsburgh, Pa. The
reservoir is located entirely in Westmoreland County, Pa. (See U. S.
Geological Survey chart for Latrobe, Pa.)
   Existing project. This provides for the construction of a flood-
control reservoir dam of the concrete gravity type with a gate con-
trolled center spillway flanked by abutment sections joining the
valley sides, and an earth embankment section terminating in the
left abutment. The dam, 960 feet long at the top, rises 114 feet
above the stream bed, and provides for the gross controlled storage
of 95,300 acre-feet of water from a tributary drainage area of
290 square miles. Of this storage 93,300 acre-feet are available for
flood prevention at Pittsburgh and in the upper Ohio Valley, gener-
ally. The remaining 2,000 acre-feet are in permanent storage. One
penstock is contained in the structure for possible future genera-
tion of hydroelectric power. The reservoir is operated as a unit of
                    FLOOD CONTROL--PITTSBURGH, PA., DISTRICT                                      1013

a coordinated reservoir system for the protection of Pittsburgh and
the Upper Ohio Valley, generally. The existing project was author-
ized by the Flood Control Acts approved June 22, 1936 and June 28,
1938. The cost of the completed project is $5,452,862. The latest
 (1954) approved estimate for annual cost of operation and main-
tenance is $35,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. Operation and main-
tenance, general: The reservoir was operated for flood control, as
required, and necessary repairs made to the structure and to the
operators' quarters and grounds throughout the year.
   No damaging floods occurred on the Allegheny or upper Ohio
River (above Mile 109) during the year. Heavy rainfall during
February 28-March 1, 1954, produced a moderate rise which re-
sulted in the reservoir reaching the highest level during the year,
elevation 931.3 on March 3, 1954, or 21.3 feet above minimum pool.
This represents a net impoundment of 10,250 acre-feet above that
pool or about 11 percent of the usable capacity of the reservoir.
During the remainder of the year, routine operations were made
except on the occasion of 12 minor rises when some water was
stored and released as river conditions permitted.
   Activities under reservoir management program comprising
sanitation, conservation, land management and operation and
maintenance of public use facilities were continued.
   The total costs were $26,709, all for operation and maintenance.
   Conditions at end of fiscal year. The dam is complete and the
reservoir is in operation as a unit of the reservoir system designed
for the protection of Pittsburgh and the reduction of flood heights
in the upper Ohio Valley, generally. Construction of the dam was
started in October 1939 and completed in June 1942. All work
relative to relocations and the acquisition of land is complete. The
total acreage acquired consists of 3,415.12 acres in fee simple and
flowage easements over 79.84 acres.
   The total costs to the end of the fiscal year were as follows:

                                                                                   Costs

                            Funds                                               Operation and
                                                                  New work      maintenance,    Total
                                                                                   general


Regular-.._-----     -----------------------------------------    $5, 445,523        $374,947   $5,820,470
Emergency relief- -- _--------------------------------------           7, 339---------------        7,339
     Total   ----------------------------------------- --------    5, 452,862         374,947   5, 827, 809
1014         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                     Cost and financialsummary


                                             Fiscal year ending June 30                           Total to June
                                                                                                S30,. 1954, includ-
                                                                                                 ing fiscal years
                              1950          1951            1952          1953       1954          priorto 1950

New work:
                                                                                 I
   Apprpriated    .....                   -$17,101          ----                                       $5,452,862
   Cost--    ..     ..--------------
                              $52,  490            89   ------   -.....                      ,         1 5,452,862
Maintenance:
   Appropriated...- - -        54,000        27, 000        $24,500       $26,500    $22, 300              376,000
            a...
   Cost .... ..........        33,176        41,679          26,382        29,155     26,709               374,947

I Includes $7,339from Emergency Relieffunds.

                  19. ELKINS, OHIO RIVER BASIN, W. VA.
    Location. The city of Elkins is located on the Tygart River in
north central Randolph County, W. Va., approximately 155 miles
south of Pittsburgh, Pa. It is situated at the downstream end of a
long, broad reach of the upper Tygart Valley, approximately 75
miles above the mouth of the river. (See U. S. Geological Survey
chart for Elkins, W. Va.)
    Existing project. The plan of improvement provides for divert-
ing flood discharges from the upstream arm of the loop of the
natural river channel into an artificial cutoff channel, thereby by-
passing the city of Elkins. The improvement consists of a fully
impervious rolled-earth upstream diversion dike, approximately
1,250 feet long; a diversion or cutoff channel, approximately 1,600
feet long, 140 feet wide and 15 feet deep; a downstream protection
dike, approximately 2,500 feet long; controlled inlet and outlet
conduits through the dikes; a pondage basin within the protected
area to store storm runoff during diversion periods; and an inci-
dental pondage basin upstream from the diversion dike to aid low
water flow. The structures of the project will be adequate to provide
complete protection of Elkins against the maximum flood of rea-
sonable expectancy. The existing project was authorized by the
Flood Control Act approved June 28, 1938.
   The Federal cost of the completed project is $1,772,627; non-
Federal cost $40,000. The latest (1954) approved estimate for
annual cost of maintenance is $4,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. New work: All
work relative to acquisition of land was completed by hired labor.
   Operation and maintenance, general: Stream gaging and chan-
nel maintenance operations were performed during the year'.
   The total costs were $7,313, of which $2,867 was for new work
and $4,446 for operation and maintenance.
   Condition at end of fiscal year. Construction of the flood pro-
tection works was commenced in May 1946 and completed in May
1949. The project, except that portion of channel maintained by
the Federal Government, has been operated and maintained by the
City of Elkins since March 31, 1949. All work in connection with
relocations is complete. Land acquisition and related work is com-
plete. The total acreage involved consists of 43.19 acres in fee
                    FLOOD CONTROL-PITTSBURGH, PA., DISTRICT                                              1015
simple and flowage easements over 526.04 acres.
  The total costs to the end of the fiscal year were $1,782,728, of
which $1,772,627 was for new work and $10,101 for operation and
maintenance.
                                           Cost and financial summary

                                                    Fiscal year ending June 30                   Total to June
                                                                                                 30, 1954, includ-
                                                                                                 ing fiscal years
                                    1950           1951         1952       1953        1954       prior to 1950


New work:
   Appropriated _....          __        -......   $17,609 I_$6,                051   -$1,073         $1, 772, 627
   Costa. e:    ._ ___.
                      ..         :$17,497           11,495       $27,032     13,711      2,867         1,772,627
Maintenance:
   Appropriated ..                    4,000          2,000          500       1,500     2,600              10,600
   Cost .........----      -
                           .            485          2, 901         957       1,313     4,446              10, 101



                                           20. UNIONTOWN, PA.
   Location. The city of Uniontown is located on Redstone Creek
in Fayette County, southwestern Pennsylvania, approximately 50
miles south of Pittsburgh, Pa. (See U. S. Geological Survey chart
for Uniontown, Pa.)
   Existing project. The plan of improvement provides for chan-
nel improvements by widening and deepening with some realign-
ment of Redstone Creek and Coal Lick Run. The stream banks
and improvements thereon would be protected by slope paving and
walls locally where necessary. The existing project was authorized
by the Flood Control Act approved June 30, 1948.
  The estimated Federal cost for new work (1954) is $1,470,000;
the estimated non-Federal cost is $237,000.
  Local cooperation. Specific requirements of local cooperation
required by the authorizing act are set forth in report of the Chief
of Engineers published in House Document 301, 80th Congress, 1st
session. Informal assurances of local cooperation have been re-
ceived from the city council of the city of Uniontown.
   Operationsand results during fiscal year. New work: None.
  Conditions at end of fiscal year. No work has been performed
on the project.
21. YOUGHIOGHENY RIVER RESERVOIR, OHIO RIVER BASIN, PA.
   Location. The dam site is located on the Youghiogheny River
about 74.2 miles above its junction with the Monongahela River at
McKeesport, Pa. It is 1.2 miles upstream from Confluence, Pa., and
about 57 miles southeast of Pittsburgh, Pa. The reservoir is located
in Fayette and Somerset Counties, Pa., and Garrett County, Md.
 (See U. S. Geological Survey charts for Confluence, Pa., Accident,
Md., West Virginia, and Pennsylvania.)
   Existing project. This provides for the construction of a reser-
voir dam of the rolled earthfill type with separate uncontrolled side
channel spillway and tunnel outlet works. The dam is 1,610 feet
long at the top, rises 184 feet above the stream bed, and provides
for the gross storage of 254,000 acre-feet of water from a tribu-
tary drainage area of 434 square miles. Of this storage 5,200 acre-
1016     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

feet are in permanent storage and the remaining 248,800 acre-
feet are available for flood control, navigation aid, and pollution
abatement purposes. The reservoir is operated as required for
flood prevention purposes as a unit of a coordinated reservoir sys-
tem for the protection of Pittsburgh and the upper Ohio Valley
generally. The project was selected for construction under the gen-
eral authorization for the Ohio River Basin contained in the Flood
Control Act approved June 28, 1938.
   The cost of the completed project is $9,674,904. The latest
 (1954) approved estimate for annual cost of operation and main-
tenance is $63,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. Operation and main-
tenance, general: The reservoir was operated for flood control, as
required, and necessary repairs made to the structure and to the
operators' quarters and grounds throughout the year.
   No damaging floods occurred on the Youghiogheny or Upper
Ohio River (above mile 109) during the year. During the entire
year, routine operations were made in accordance with the low
water schedule for maintaining satisfactory flows at Connellsville,
Pa., except on the occasion of 10 minor rises when water was
stored, with the excess above normal schedule storage being re-
leased as river conditions permitted. Heavy rain showers during
June 8 to 11, 1954, produced a moderate rise which resulted in the
reservoir reaching the highest level during the year, elevation
1443.5 on June 15, 1954, or 4.5 feet above summer pool. This rep-
resents an impoundment of 12,900 acre-feet above summer pool,
or about 13 percent of the usable summer flood storage capacity
of the reservoir.
   On January 9, 1954, the reservoir had fallen to elevation 1349.0,
the lowest level in the past 6 years of complete multiple-purpose
regulation. It is significant that the inflow into the reservoir for
the 7-month period, June through December 1953, which totalled
2.3 inches in runoff, was the lowest in the last 24 years, since 1930.
Low water releases from this reservoir provided a dilution factor
of slightly more than seven to one to the Youghiogheny River dur-
ing the period, July through November 1953. Combined with Ty-
gart Reservoir releases, this more than doubled the flow in the
lower 15.6 miles of the Monongahela River during the critical low
flow period from late August through early December 1953. This
reservoir achieved great benefits by low flow augmentation for the
highly industrialized and densely populated area using the You-
ghiogheny River and lower Monongahela River for water supply
by improvement of water quality by dilution.
   Activities under reservoir management program comprising
sanitation, conservation, land management and operation and main-
tenance of public use facilities were continued.
   The total costs were $43,891, all for operation and maintenance.
   Condition at end of fiscal year. The dam is complete and the
reservoir is in operation for flood control, navigation, and pollution
abatement purposes. For flood control, the reservoir is operated
                 FLOOD CONTROL-PITTSBURGH, PA., DISTRICT                                          1017
as a unit in the reservoir system designed for the protection of
Pittsburgh and the reduction of flood heights in the upper Ohio
Valley, generally. Construction of the dam was started in June
1940 and completed in May 1944. All work relative to relocations
and acquisition of land is complete. The total acreage involved has
been acquired, and consists of 4,033.19 acres in fee simple and
flowage easements over 0.48 acre. A license has been issued the
Commonwealth of Pennsylvania covering fish conservation and
management in the Pennsylvania portion of the reservoir.
   The total costs to the end of the fiscal year, all from regular
funds, were $10,100,175, of which $9,674,904 was for new work
and $425,271 for operation and maintenance, general.
                                    Cost and financial summary

                                          Fiscal year ending June 30                       Total to June
                                                                                          30, 1954, includ-
                                                                                          ing fiscal years
                            1950         1951        1952         1953          1954       prior to 1950


New work:
   Appropriated------------------       -$5, 000       -$71                                    $9,674,904
   Cost---------------     $121, 871       5, 784      2,735 ----------------   ------          9,674,904
Maintenance:
   Appropriated  -.....     111,000       53,100      49, 500    $43,000        $39,200            427, 200
   Cost--.   ____ _ __       56,418       45, 841    103,734      44,940         43,891            425,271



           22. BERLIN RESERVOIR, OHIO RIVER BASIN, OHIO
   Location. The dam site is located on the Mahoning River about
73 miles above its confluence with the Shenango River. It is about
10 miles above the existing Milton Reservoir Dam and 35 miles up-
stream from Warren, Ohio. The reservoir is located in Portage,
Mahoning, and Stark Counties, Ohio. (See U. S. Geological Survey
charts for Warren, Ravenna, and Alliance, Ohio.)
   Existing project. This provides for the construction of a reser-
voir dam with a partially controlled, concrete, gravity center spill-
way flanked by rolled earthfill abutment sections joining the valley
sides. The dam is 5,750 feet long at the top, rises 101.5 feet above
the stream bed, and provides for the gross controlled storage of
91,200 acre-feet of water from a tributary drainage area of 249
square miles. Of this storage 1,800 acre-feet are in permanent
storage and the remaining 89,400 acre-feet are available for flood
control and water supply purposes in the industrialized Mahoning
Valley below. The project was selected for contruction under the
general authorization for the Ohio River Basin contained in the
Flood Control Act approved June 28, 1938.
   The cost of the completed project is $6,288,676. The latest
 (1954) approved estimate for annual cost of operation and main-
tenance is $60,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operationsand results during fiscal year. Operation and main-
tenance, general: The reservoir was operated effectively for flood
control and for low water regulation, as required, and necessary
repairs made to the structure and to the operators' quarters and
grounds throughout the year.
1018     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   No damaging floods occurred on the Mahoning, Beaver, or Ohio
River (above mile 109) during the year. Heavy rain on March 1,
1954, caused a minor rise along the upper Mahoning River. The
Mahoning River at Warren (South Street gage) crested at 6.25
feet on the 3d while the reduction by the reservoir in conjunction
with Milton Reservoir (owned by the City of Youngstown) averted
nuisance flooding. Water was stored during this rise in accordance
with the low water storage schedule, and was the first break in the
replenishment of low water storage which was critical. It is note-
worthy that the total inflow for December 1953 through February
1954, 0.84 inch of rainfall, was the lowest in 20 years since De-
cember 1933-February 1934. Heavy rain on April 26-27, 1954,
caused another minor rise along the upper Mahoning River. The
Mahoning River at Warren crested at 7.85 feet on the 28th, while
the reduction by the reservoir in conjunction with Milton Reservoir
averted nuisance flooding. The water stored during this major
rise caused the reservoir to rise to elevation 1026.8 on the 28th
or 2.1 feet above the summer pool. This represents an impound-
ment of 8,100 acre-feet above that pool or about 25 percent of the
usable summer flood storage capacity of the reservoir. During
September and October 1953 additional flow from storage was sup-
plied to relieve to some extent the critical drawdown condition at
Mosquito Creek Reservoir from that normally imposed for satis-
fying the low water temperature control schedule at Youngstown.
A more equitable balance of storage in the overall three-reservoir
system was achieved for the Mahoning River basin by this pro-
cedure. Routine operations were made throughout the year in
accordance with the low water schedule for maintaining satisfac-
tory flows at Leavittsburg and Youngstown. A total of 12 minor
rises occurred during which water was stored according to the
low water storage schedule for subsequent release during the 1954
low water season.
   Activities under the reservoir management program comprising
sanitation, conservation, land management and operation and main-
tenance of public use facilities were continued. Construction of a
public sanitary building was completed by contract. Contract
operations for paving of an access road were initiated.
   The total costs were $58,196, all for operation and maintenance.
   Condition at end of fiscal year. The dam is complete and the
reservoir is in operation for flood control and low water regulation
purposes in the industrialized Mahoning Valley below. Construction
of the dam was started in January 1942 and completed in June
1943. All work relative to relocations and land acquisition is com-
plete. The total acreage involved has been acquired and consists
of 6,931 acres in fee simple and flowage easements over 1,059
acres.
   The total costs to the end of the fiscal year, all from regular
funds were $6,699,209 of which $6,288,676 was for new work and
$410,533 for operation and maintenance, general.
                 FLOOD CONTROL-PITTSBURGH, PA., DISTRICT                                           1019
                                     Cost and financial summary

                                            Fiscal year ending June 30'                    Total to June
                                                                                           30, 1954, includ-
                                                                                           ing fiscal years
                              1950         1951        1952         1953        1954        prior to 1950


New work:
   Appropriated --------   -------       -$40, 000   -$50, 000     -$2,324-$6,288,                       676
   Cost-------------         $101,847      22, 874     105, 277       1,556                       6, 288, 676
Maintenance:
   Appropriated ......_       43,000       39,000       63, 500     70, 500      54, 200            426, 900
   Cost ----------------      49,536       33,252       63,366      63, 270      58,196             410,533



  23. MOSQUITO CREEK RESERVOIR, OHIO RIVER BASIN, OHIO
   Location. The dam site is located on Mosquito Creek, 9 miles
above the junction of the creek with the Mahoning River at Niles,
Ohio, and about 18 miles upstream from Youngstown, Ohio. The
reservoir is located in central Trumbull County, northeastern Ohio.
 (See U. S. Geological Survey charts for Bristolville and Kinsman,
Ohio, and Pennsylvania.)
   Existing project. This provides for the construction of a reser-
voir dam of the rolled earthfill type with outlet facilities through
the dam, and an uncontrolled natural wasteway to discharge over-
flow from the reservoir. The wasteway is located at the upper end
of the reservoir area on the low-lying reach of the Mosquito Creek-
Grand River Divide and overflow will be discharged into the Grand
River, a tributary of Lake Erie. The dam is 5,650 feet long at the
top, rises 47 feet above the stream bed, and provides for the gross
controlled storage of 104,100 acre-feet of water from a tributary
drainage area of 97 square miles. Of this storage, 96,100 acre-
feet are available for low water regulation and flood control pur-
poses in Mahoning and Beaver Valleys below. A modicum of effect
applies to the upper Ohio River Valley, below the mouth of the
Beaver River. Of the remaining 8,000 acre-feet, 6,000 acre-feet
are available for water supply storage and 2,000 acre-feet are in
permanent storage. The reservoir is operated for flood prevention
purposes as a unit of a coordinated reservoir system. The project
was selected for construction under the general authorization for
the Ohio River Basin contained in the Flood Control Act approved
June 28, 1938.
   The cost of the completed project is $4,035,400. The latest (1954)
approved estimate for annual cost of operation and maintenance
is $39,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. Operation and main-
tenance, general: The reservoir was operated effectively for flood
control and for low water regulation, as required, and necessary
repairs made to the structure and to the operators' quarters and
grounds throughout the year. In addition to ordinary repairs to
structures and plant, repairs were made to the stilling basin by
hired labor.
   No damaging floods occurred on the Mahoning, Beaver or Ohio
River (above mile 109) during the year. Routine operations were
made throughout the year in accordance with the low water sched-
1020            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

ule for maintaining satisfactory flows at Youngstown. During No-
vember 18 to 29, 1953, the reservoir pool was at the lowest elevation
for the 1953 low water season, elevation 891.3. This is the lowest
elevation since 1945, the first year of satisfactory low water stor-
age in the reservoir. Except for a short period in February 1954,
a nominal flow of 4 to 5 second-feet was released from November
18, 1953, until June 8, 1954, while the net inflow was stored from
14 minor rises in accordance with the low water schedule for sub-
sequent release during the 1954 low water season. The outflow
was increased during February 9 to 16, 1954, to satisfy minimum
winter flow requirements for the Mahoning River at Youngstown.
This is the first time since the dam was placed in operation in 1944
that low water storage was used to satisfy river requirements dur-
ing the winter season, the normal storage period.
   The outlet works were closed during November 2 to 16, 1953,
while work was being done on the intake installation for water
supply to the Warren, Ohio, water treatment plant below the dam.
The water supply diversion from the reservoir to the City of War-
ren Filtration Plant started on May 13, 1954.
   Heavy rain during June 16 caused a moderate rise which re-
sulted in the reservoir reaching elevation 900.9 on the 19th. This
level was the highest reached by the reservoir pool during the year
when 78,700 acre-feet of water was in storage. This level, 0.5 feet
below summer pool, is the lowest annual maximum elevation since
the reservoir has been in operation.
   The total costs were $30,476, all for operation and maintenance.
   Condition at end of fiscal year. The dam and appurtenances
are complete and are in operation for flood control and low water
regulation purposes in the industrialized Mahoning and Beaver
Valleys below. Construction of the dam was started in July 1943
and was ready for beneficial use in January 1944. All work rela-
tive to relocations and acquisition of land is complete. The total
acreage involved in the acquisition of land consists of 11,213.98
acres in fee simple and flowage easement over 275.21 acres. The
State of Ohio has obtained a license from the Secretary of the
Army for development and operation of recreation facilities in the
reservoir area.
   The total costs to the end of the fiscal year were $4,260,761 of
which $4,035,400 was for new work and $225,361 for operation and
maintenance, general.
                                         Cost and financial summary

                                               Fiscal year ending June 30                                 Total to June
                                                                                        ..              130, 1954, includ-
                                                                                                          ing fiscal years
                                  1950        1951        1952            1953               1954          prior to 1950

New work:
   Appropriated ........        ..-          ,$ 9       - - -        --     -           - -         -4,-035,400 $I,_
   Cost         _          --    $167,441     $49,620     $ 7,548 -              __ _   -     .   --   .-       4,035,400
Maintenance:
   Appropriated      ---...       36, 000     28, 000      24, 000        $36,500            $22, 200              227, 800
   Cost     .                     35,933       21,587      27,084          33,842             30,476               225, 361
            FLOOD CONTROL-PITTSBURGH, PA., DISTRICT              1021
           24. WELLSVILLE, OHIO RIVER BASIN, OHIO
    Location. The city of Wellsville is located in Columbiana
County, on the right bank of the Ohio River, 48 miles below the
head' of the river at Pittsburgh, Pa. (See U. S. Geological Survey
chart. for Wellsville, W. Va., Ohio and Pa.)
    Existing project. Section I: This provides for the construction
of a concrete flood wall and earth dike at the upper end of the city,
consisting of the following features: 1,564 feet of concrete flood
wall and 476 feet of earth dike extending from a rocky cliff above
the Lisbon Street Highway Bridge along Little Yellow Creek to
the Pennsylvania Railroad, thence downstream along the Ohio
River, paralleling the railroad to high ground at Third Street;
three pumping plants, two sanitary and one storm water; three
gates for passing traffic, one on State Highway No. 7 and two for
industrial spur tracks; and appurtenant drainage structures.
    The project has been selected for construction under the general
authorization for the Ohio River Basin contained in the Flood Con-
trol Act approved August 28, 1937, and provides partial protection
to the city of Wellsville. The estimated Federal cost for new work
 (1954) is $397,800; the estimated non-Federal cost is $113,000.
    Section II: This provides for the construction of a concrete flood
wall and earth dike at the lower end of the city, consisting of the
following features: 345 feet of concrete flood wall and 5,250 feet of
earth dike extending generally parallel to and on the river side of
the main line track of the Pennsylvania Railroad along the Ohio
River from Eighteenth Street to the vicinity of the underpass on
State Highway Route No. 7; one pumping plant for storm water;
one industrial spur track crossing and closure; and appurtenant
drainage structures. The project supplements section 1 and pro-
vides complete protection with a minimum freeboard of 3 feet for
the city of Wellsville against all floods up to that of March 1936,
the maximum of record.
   'The project has been selected for construction under the general
authorization for the Ohio River Basin contained in the Flood Con-
trol Act approved June 28, 1938. The estimated construction cost
 (1954) is $158,800.
    Local cooperation. The city of Wellsville has furnished assur-
ances and all evidences of title necessary for the construction of
the complete project.
    Operations and results during fiscal year. New work: Section
I: Preparation of plans and specifications for remedial control
facilities on outlets through the dikes and flood wall were initiated
by hired labor.
    The costs, all for new work, were $318.
    Section II: Preparation of plans and specifications for remedial
control facilities on outlets through the dikes and flood wall were
initiated by hired labor.
    The costs, all for new work, were $234.
    Condition at end of fiscal year. Section I: This section of the
project is complete. On August 22, 1942, the City of Wellsville
formally accepted the floodwall for operation and maintenance.
The total costs to the end of the fiscal year, all for new work, were
$384,216 of which $370,194 was from regular funds and $14,022
1022         REPORT OF CHIEF OF ENGINEERS. U. S. ARMY. 1954

from Emergency Relief funds. Work remaining to be done con-
sists of construction of remedial control facilities on outlets
through the dike and flood wall.
   Section II: This section of the project is complete. On August
22, 1942, the City of Wellsville formally accepted the floodwall for
operation and maintenance. The total costs to the end of the fis-
cal year, all for new work, were $156,416 from regular funds.
Work remaining to be done consists of construction of remedial
control facilities on outlets through the dikes and flood wall.
                                    Cost and financial summary
                                         CONSOLIDATED

                                            Fiscal year ending June 30                         Total to June
                                                                                              30, 1954, includ-
                                                                                              lg fiscal years
                             1950        1951        1952         1953             1954         prior to 1950


New work:
   Appropriated   -   -                                             --             $16, 500      "1.$556, 580
   Cost                                                                  - .----        552          1 540, 632

1 Includes $14,022 from Emergency Relief funds.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_------              $-15,948
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955----------------        --                       ---                                       .15,948




        25. WHEELING-BENWOOD, OHIO RIVER BASIN, W. VA.
   Location. The city of Wheeling is located along the left bank of
the Ohio River in Ohio County, W. Va., approximately 58 miles
southwest of Pittsburgh, Pa. It extends from. mile 85.5 to mile 93
below the head of the river at Pittsburgh, Pa., and includes areas
lying north and south of Wheeling Creek for a total distance of 9
miles. Benwood is located in Marshall County, W. Va., on the left
bank,.of the Ohio River immediately downstream from Wheeling
and extends from mile 93 to mile 95.7. (See U. S. Geological Sur-
vey Chart for Wheeling, W. Va., Ohio, and Pennsylvania.)
   Existing project. The project is located along the left bank of
the Ohio River between river mile 90.4 and river mile 95 and lies
partially in the city of Wheeling, Ohio County, W. Va., and par-
tially in the city of Benwood, Marshall County, W. Va. Incided
are flood-protection works consisting of dikes and flood walls with
traffic openings, drainage facilities, and pump stations, as required.
The flood protection works along the Ohio River will consist of a
continuous dike-wall system with traffic openings across the rail-
roads at the upper and lower ends. The lower end of Wheeling
Creek will be confined in pressure conduits from which flood walls
will extend up both banks of Wheeling Creek, with traffic openings
at railroads and streets, as required. The project is designed to
provide protection against a design flood which is approximately
equivalent to the natural profile of the record March 1936 flood.
The existing project was authorized by the Flood Control Act ap-
proved June 28, 1938.
  The estimated Federal cost for new work (1954) is $21,500,000;
the estimated non-Federal cost is $4,940,000.
                     FLOOD CONTROL--PITTSBURGH, PA., DISTRICT                                       1023
    Local cooperation. The Wheeling Planning Commission is the
designated agency for obtaining local cooperation. The city of
Wheeling, W. Va., executed formal assurances under date of March
25, 1952, and the city of Benwood, W. Va., under date of April 28,
1952. West Virginia has enabling legislation which will permit
both Wheeling and Benwood to place themselves in position to ful-
fill the assurances in connection with which further action is being
taken by local interests to demonstrate their ability to meet the
requirements of local cooperation.
    Operations and results during fiscal year. New work: Advance
engineering and design continued throughout the year in connec-
tion with the proposed improvement along Wheeling Creek and
Ohio River, upstream from Wheeling Creek.
    The total costs were $5,315, all for new work.
    Condition at end of fiscal year. A definite plan of improvement
has been developed, and advance engineering and design in connec-
tion therewith is in progress. Construction of the project has not
been initiated.
    The total costs to the end of the fiscal year, all for new work,
were $269,901.
                                       Cost and financialsummary

                                                 Fiscal year ending June 30                 Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                                1950          1951        1952.        1953       1954        prior to 1950


New work:
   A ppropriated . .......      $75, 000 i   $100, 000                 $42, 700                     $276, 700
   Cost      -.            ..    74,367        50,287     $26,992       54,231     $5,315            269, 901


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954--_----------    $6,739
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955_-        _                                                  6,739
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project ..       - ..... .. ... .. ... .. .. 21,223,300
                                  -..- ..---
           26. OHIO RIVER BASIN, PITTSBURGH, PA., DISTRICT

   Location. The works covered by this project are a series of
levees, flood walls, channel improvements, and reservoirs in the
Ohio River Basin within the confines of the Pittsburgh, Pa., dis-
trict.
   Existing project. The Flood Control Act approved August 28,
1937 authorized the construction of levees, flood walls, and drain-
age structures for the protection of cities and towns in the Ohio
River Basin, the projects to be selected by the Chief of Engineers
with the approval of the Secretary of War, in accordance with
House Flood Control Committee Document No. 1, 75th Congress,
first session, at a cost not to exceed $24,877,000 for construction,
which amount was authorized to be appropriated for this purpose.
   The Flood Control Act of June 28, 1938, approved the general
comprehensive plan for flood control and other' purposes in the
Ohio River Basin as set forth in House Flood Control Committee
Document No. 1, 75th Congress, first session, with such modifica-




      Sig 33-1023-1054
 1024            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

tion thereof as, in the discretion of the Secretary of War and the
Chief of Engineers, may be advisable, and for initiation and partial
accomplishment of the plan, authorized $75,000,000 for reservoirs
and .$50,300,000 for local flood protection works, the individual
projects to be selected and approved by the Chief of Engineers
subject to the provision that the authorization shall include the
diversion of Cache River above Cairo, Ill., and the protection of the
area north of the Cairo drainage district by levees, at an estimated
cost of $2,000,000.
    The Flood Control Act approved August 18, 1941, authorized the
sum of $45,000,000 for the further prosecution of the comprehen-
sive plan approved in the act of June 28, 1938 for the Ohio River
Basin, modified to include the Allegheny Reservoir project in ac-
cordance with the recommendation of the Chief of Engineers in
House Document No. 300, 76th Congress, first session.
    The Flood Control Act approved December 22, 1944, authorized
the sum of $70,000,000 for the prosecution of the comprehensive
plan approved in the act of June 28, 1938, as modified by the act
approved August 18, 1941, fOr the Ohio River, including additional
projects in tributary basins.
    The Flood Control Act approved July 24, 1946, authorized the
sum of $125,000,000 for the further prosecution of the compre-
hensive plan for the Ohio River Basin approved in act of June 28,
1938, as amended and supplemented by subsequent acts of Con-
gress, including additional projects in tributary basins.
   The Flood Control Act approved May 17, 1950, authorized the
sum of $100,000,000 for the prosecution of the comprehensive plan
for the Ohio River Basin approved in the act of June 28, 1938, as
amended and supplemented by subsequent acts of Congress, in-
cluding additional projects in the tributary basin.
   The following is a list of the individual projects considered in the
comprehensive plan within the confines of the Pittsburgh District:
                                             Local protection projects

                                                                                              Estimated costs
                Location 1                       Type of protection
                                                                                Federal         Non-federal            Total

Adena, Ohio (Short Creek).----------      Channel-__.___ .....-             $    202,000         $       50,000   $    252,000
Allegany, N. Y. (Allegheny River) _ . Levee--------------                        786,000                 50,000        836, 000
Bellaire, Ohio _-------------------- Wall and levee .......                   7, 660,000             1,870,000      9, 530,000
Brackenridge, Tarentum and Natrona, Wall ----------------
                                               ...                           11, 800, 000            3,080,000     14, 880,000
Pa. (Allegheny River).
Brilliant, Ohio--....---- -----------_---    do          -                      3,240,000              276,000        3,516,000
Brockway, Pa. (Allegheny River Wall and levee                ......                477, 000            167, 000         644, 000
Basin).
Coraopolis, Pa. -.--------------------
                                  Wall-__-..____---__--_
Dillonvale, Ohio (Short Creek) .-...
                                  Channel---------------
                                                                                3,080,000
                                                                                  283,000
                                                                                                       466,000
                                                                                                        43,000
                                                                                                                      3,546, 000:
                                                                                                                        326,000
Elkins, W.
        2  Va. (Monongahela River              Channel diversion      .     51, 772,627                 40, 000       1, 812,627
  Basin) .
Empire, Ohio          ....------------------ Wall-----------------... ...       3,030,000              234,000        3,264,000
Follansbee, W. Va ....---------------- -----    do---- ------------
                                                                ..              2,670,000              232,000        2,902000
Freeport, Pa. (Allegheny River)......__----do----------------1,480,000                                  21,000        1,501, 000
Industry, Pa .....--------------------         Wall,levee and channel           1, 560, 000            136,00Q        1,696, 000
Johnsonburg, Pa. (Allegheny River              Wall....-----------------          750,000              127,000          877,000
  Basin).2 s
Johnstown,     Pa.    (Allegheny     River     Channel- .......... .            8, 865,388-                           8, 865,388
Basin).:
Kittanning,    Pa., Part I (Allegheny            al   .__.   ------------
                                                              ..........          130, 317                , 000         132, 317
River) .
Kittanning, Pa., Part II (Allegheny            Walki-...-.... --                5,940,000              352,000        6,292,000
River).
See footnotes at end of table.
                             FLOOD CONTROL--PITTSBURGH, PA., DISTRICT                                                                              1025
                                              Local protection projects-Continued

                                                                                                                    Estimated costs

                       Location 1                               Type of protection
                                                                                                      Federal           Non-federal              Total

Lake Chautauqua and Chadakoin                        Channel       __ -              -       2, 490,000                      1,130, 000         3,620,000
   River. N. Y. (Allegheny River
   Basins.                                     3
Latrobe, Pa. (Allegheny River Basin) ..... do--------                        -------            207, 659                       44,400            * 252,059
Leetsdale, Pa............-....                 .. Levee__.-----------                        1,270,000                        141,000           1,411,000
Martins Ferry, Ohio4 ....        .        ....      Wall and levee .------                   8,630 000                        836,000           9,466,000
McKees Rocks, Pa.......                  ....       Wall_...-------___                       5,470, 000                       197, 000          5,667, 000
Mingo Junction, Ohio.................             ----- do....-------      ---------         1,920,000                        310,000           2,230,000
Moundsville, W. Va--___. __________            _Wall and levee_--------                      3,070,000                        605,000           3,675,000
Neville Island, Pa...            _       _       --...---do..... ...---------------- 3,210,000                              1,830,000           5,040,000
New Cumberland, W. Va...                         ----- do....---------....-------2,760, 000                                   421,000           3,181,000
New Kensington and Parnassus, Pa. Wall..                          .....---------...-------- 7,900,000                         148, 000          8, 048,000
   (Allegheny River).
Olean, N. Y. (Allegheny River) 2 3.... Levee...---------------                             53,217, 531                         597, 000       53,814,531
Pittsburgh, Pa. (Golden Triangle)....               Wall..-----------------9, 390,000                                         429,000           9, 819, 000
Pittsburgh, Pa. (North Side) ....                   _-----do ---------------               22,400, 000                      1,760,000         24,160, 000
Pittsburgh, Pa. (The Strip)             _-------.----- do .--------------- 10,700,000                                       2,560,000          13,260,000
Portville, N. Y. (Allegheny River) 2 3 __ Levee---------------                             52,070,484                         353,000         52,423, 484
Punxsutawney, Pa. (Allegheny River                  Channel and levee ..                     3,585, 200                       199,000           3,784,200
  Basin).'
Ridgway, Pa. (Allegheny River Basin). Channel                      -...........    -           480,000                          13,000            493,000
Rochester, Pa ----------------------- Wall-----------------3,350,                                   000                        622,000          3,972, 000
St. Marys, Pa. (Allegheny River Channel-                                         -____.... -__.455,000                          14,000            469, 000
  Basin).
Smiths Ferry, Pa. _________-____                    Wall____.           _2,                    120,000                        229,000          2,349,000
Strattonville, Ohio---. --                     -----...do.........----------------           2,780,000                        336,000          3,116,000
Warwood, W. Va....-----------------do.----------------                                       1,740,000                        376,000          2,116,000
Wellsburg, W. Va ------------                       Wall and levee_              -          3, 270,000                      1,160,000          4,430, 000
Wellsville, Ohio, Sec. I 2...a______________ -- do ......---   ---            ---              397, 800                       113,000             510,800
Wellsville, Ohio, Sec. II      -      -    -     - __- -do-........                  .         158,800 -                       -                  158,800
West Bridgewater, Pa__                              Wall ._______________                   2,340,000                         517, 000         2,857,000
Wheeling-Benwood, W. Va._...--------                Wall and levee -------                 21, 500, 000                    4,940,000          26,440,000
Wheeling, W. Va. (North Wheeling) _ Wall-..                              --------------    11, 700,000                     2,700, 000         14, 400,000
Wheeling, W. Va. (Wheeling Island) _ Wall and levee....--------                            13, 300, 000                    2,470,000          15, 770,000
Wilcox, Pa. (Allegheny River Basin)._ Levee___-..-..........                                   232, 000                        20,000             252,000

  4 All projects are located on the Ohio River unless otherwise noted.
  s Reported in detail in an individual report.
  3 Completed.
  4 Reported in detail in Annual Report for 1941.
  5 Actual cost.

              26.       OHIO RIVER BASIN, PITTSBURGH,                                                         PA.        DISTRICT
                                        Reservoirs

                                                                                                                                               Total
                      Tributary basin and reservoir                                                          Stream                          estimated
                                                                                                                                                cost


Allegheny:
    Allegheny River, Pa.- ----.               ..-      ----------.-
                                                           .     ..              .                Allegheny River.-. ---..                     $92,360, 000
    Conemaugh River, Pa......                                                   ........--------------------------
                                                                                                  Conemaugh River__-----                        45,984,000
    Crooked Creek, Pa.                                                                            Crooked Creek...-------------
                                                                 .............----------------------------                                      3 4, 204,888
    East Branch Clarion River, Pa.                                   .....------------------- Clarion River--....-______                    --     9, 003,000
    French Creek,a  P.         ------------------------------                                     French Creek....--------         ------.      18,500,000
    Loyalhanna, Pa.           -------------------------------                                     Loyalhanna Creek -----------                  35,452,862
    Mahoning Creek, Pa...---------------------------Mahoning                                                       Creek.._____...... 3 6, 421, 345
    Redbank, Pa ...---...............------------------------------                               Redbank Creek...-------------                 39,800,000
    Tionesta; Pa.1.--------------                                                            .. Tionesta Creek...------------                   3 5,213,401
Beaver:
    Berlin, Ohio '        ....------ -....-- ---------------                                    t Mahoning River....---.--.--.                     6,288,676
    Eagle Creek, Ohio-------...             .......                       ......-------------...Eagle Creek............___..___                 12,700,000
    Mosquito Creek, Ohio 1 ...........                           ..
                                                                ___-              ......          Mosquito Creek......-...._._                  34,035,400
    Shenango, Pa., and Ohio....-____-                                 ____.. .........            Shenango River.....--              ..--------...23,500,000
Monongahela:
    Turtle Creek, Pa.2..............................-
    West Fork River, W. Va....
    Youghiogheny River, Pa.1----------__
                                                    _----------------- ---
                                                    ,----           --             --
                                                                                        J   ..-- Turtle Creek---------------................-- 8,480000
                                                                                                  West Fork River------..............
                                                                                                  Youghiogheny River..........
                                                                                                                                                18,800,000
                                                                                                                                                   9,674,904

  1 Reported in detail in an individual report.
  9 Exclusive of $2,808,000 to be borne by local interests.

  3 Completed, actual cost.
1026           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Local cooperation. The local protection project for Wilcox,
Pa., has been deferred due to the inability of local interests to
furnish assurances of local cooperation prescribed by law. In
accordance with section 3 of the act of Congress approved Decem-
ber 22, 1944 (Public Law 534, 78th Cong.), local interests were
formally notified of the required conditions of local cooperation
and of the 5-year period within which assurances must be fur-
nished. Accordingly, the commissioners of Elk County and super-
visors of Jones Township were notified March 6, 1950, in regard to
the project for Wilcox, Pa. Acknowledgement was made by the
commissioners of Elk County, March 10, 1950.
   Operations and results during fiscal year. Operations per-
formed during the year consisted of surveys, investigations, stud-
ies, and preparation of project plans for the development of the
general comprehensive plan for flood control in the Ohio River
Basin.
   The costs during the year were $13,881.
   Condition at end of fiscal year. The preparation of project
plans and construction plans and specifications was well advanced.
The status of projects selected for construction under this authori-
zation is given in individual reports.
   The total costs to the end of the fiscal year were $960,208 of
which $943,482 was from regular funds and $16,726 from emer-
gency relief funds.
                                      Cost and financial summary
                                               CONSOLIDATED

                                                Fiscal year ending June 30                                     Total to June
                           .   .      .   ..     ..  . ...                 .                   .          .   30, 1954, includ-
                                                                                                              ing fiscal years
                               1950            1951          1952            1953                  1954         prior to 1950

New work:
   Appropriated .-----         $92, 449   -$123, 636      -$132, 215         $18, 515              $15,000           '$963,059
   Cost-...----------------     50,147         71, 222         25,169         17,568                13,881           1 960,208

I Includes $16,726 from Emergency Relief funds.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_-_----------        $2,852
    Appropriated for succeeding fiscal year ending June 30, 1955--------- 25,000
    Unobligated balances available for succeeding fiscal year ending June 30,
        1955_                                                            ---------------------                        27,862

                  27. INACTIVE FLOOD CONTROL PROJECTS

                                                                           Cost to June 30, 1954
                                                          For last                                                Estimated
                 Name of project                         full report                                amount
                                                         see annual                    Operations required to
                                                         report for-    Constructiorn     and      complete
                                                                                      maintenance

1. Emergency flood control work under authority             1952            --....
                                                                        --.......          _          $4,630          ()
    of the Flood Control Act approved August
    18, 1941, as amended.
2. Emergency flood control work under authority             1949                .....                 $2, 336         (s)
    of Public Law No. 102, 80th Cong., 1st Sess.
3. Kittanning (pt I) Ohio River Basin, Pa-.......           1949             $130,317 .......-......                  ()
4. Latrobe, Ohio River Basin, Pa-......--------             1951               207,659      --------------            (I)


' Completed.
                                FLOOD CONTROL--PITTSBURGH, .PA.,. DISTRICT                                1027




                                      28. GENERAL INVESTIGATIONS
     Examinations and surveys. The cost of general investigations
  for the fiscal year amounted to $21,723, of which $18,238 was for
  examinations and surveys and $3,485 was for collection and study
  of basic data. The balance unexpended on June 30, 1954, $4,036,
  plus an allotment of $29,500 for examinations and surveys, and an
  anticipated allotment of $5,000 for collection and study of basic
  data, a total of $38,536, will be applied to the preparation of 5
  flood control studies (2 surveys and 3 preliminary examinations)
  and the collection and study of basic data.
     The additional sum of $69,300 can be profitably expended during
  the fiscal year 1956 for work to be accomplished under this heading.
     Collection and study of basic data. Collection and study of
  basic data during the year consisted principally of general cover-
  age, noncooperative stream gaging activities, and hydrologic
  studies.
            29. INSPECTION OF COMPLETED FLOOD CONTROL WORKS
    The Flood Control Act approved June 22, 1936, and subsequent
acts require local interests to furnish assurances that they will
maintain and operate certain local protection projects after com-
pletion in accordance with regulations prescribed by the Secretary
of the Army. District engineers are responsible for the administra-
tion of these regulations within the boundaries of their respective
districts. The (1953) estimated cost of this work is $1,500.
    Maintenance inspections were made during the fiscal year of
completed units of projects transferred to local interests for main-
tenance and operation. Local interests were advised, as necessary,
of measures required to maintain these projects in accordance
with standards prescribed by the regulations.
    The costs for maintenance during the fiscal year were $1,663.
The total costs to the end of the fiscal year were $3,686.
                                             Cost and financial"summary

                                                   Fiscal year ending June 30                    Total to June
                                                                                                30, 1954, includ-
                                                                                                ing fiscal years
                                      1950        1951          1952       1953      1954         prior to 1950

Maintenance:
i-si-p
                    ---------
         Appropriated..............                 $900 [...    ..    .   $1, 200   $1, 800,                 900
         Cost --------- ----                                      $566      1, 458   $1,663                3,686



     30. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
  Snagging and clearing of navigable streams and tributaries in
the interests of flood control. (Section 13 of the 1946 Flood Con-
trol Act.)
  During the fiscal year construction of the project on Bingamon
Creek at and in the vicinity of Wyatt, Harrison County, W. Va.,
was completed on July 29, 1953. This work had been initiated No-
vember 18, 1952. Construction of the project on Polk Creek at
Weston, W. Va., was started July 27, 1953, and completed No-
vember 5, 1953.
1028            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  The total costs incurred during the fiscal year were $42,576, all
for new work.
   The total costs to the end of the fiscal year amounted to $216,702.
                                            Cost and financial summary

                                                          Fiscal year ending June 30                       Total to June
                                                                                                           30, 1954, includ-
                                                                                                           ing fiscal years
                                     1950               1951         1952        1953        1954           prior to 1950


New work:
   Appropriated-------_                   -$3,095_------------      $31,000      $44, 000   -$7, 503               $216,702
   Cost -------------------------------------                         2,287       22,634      42,576                216,702


  Small Flood Control Projects not specifically authorized by Con-
gress. (Section 212 of the 1950 Flood Control Act.)
  The following projects were selected for construction under
authority of this act:
                                    SLOVAN, RACCOON CREEK, PA.
    The unincorporated community of Slovan is located about 20
miles west of Pittsburgh in Washington County, Pa., on Burgetts
Fork, about 21/2 miles upstream from the junction with Raccoon
Creek which flows into the Ohio River about 6 miles below Monaca,
Pa. (See U.S. Geographical Survey sheet for Burgettstown, Pa.)
    The plan of improvement provides for widening, deepening, and
straightening the channel of Burgetts Fork through Slovan and
vicinity for a distance of about 1.8 miles, filling the bypassed
reaches of the old channel, disposing of all excess excavated ma-
terial in certain reaches along the new channel, and protecting the
banks of the new channel in certain locations.
   :Local cooperation. Formal assurances dated May 21, 1952,
were furnished by the County of Washington, Pa., and were
accepted May 26, 1952.
    Operationsand results during fiscal year. New work: Remain-
ing work of installation of a project identification sign was com-
pleted by hired labor. The costs for the fiscal year were $289.
    Coordination'at end of fiscal year. Construction of the project
.by contract was started July 6, 1952, and completed November 26,
1952. The project was transferred to local interests for assump-
tion and maintenance December 12, 1952. The costs to the end of
the fiscal year were $57,811.
                                            Cost and financial summary

                                                         Fiscal year ending June 30                        Total to June
                                                                                                       -   30, 1954, includ-
                                                                                                           ing fiscal years
                                     1950               1951        1952         1953       1954            prior to 1950


New work:
   Appropriated----....----------------                             $60, 000    -$1, 900     -$289                 $57, 811
   Cost---           ------------           ---------                 8,756      48,766       -289                   57,811
                     FLOOD CONTROL--PITTSBURGH, PA., DISTRICT                                          1029
                      BURGETTSTOWN,                       RACCOON         CREEK,      PA.
   The incorporated borough of Burgettstown, Pa., is located about
20 miles west of Pittsburgh in Washington County, Pa., on Bur-
getts Fork about 1 mile upstream from the junction with Raccoon
Creek which flows into the Ohio River about 6 miles below Monaca,
Pa. (See U. S. Geological Survey chart for Burgettstown, Pa.)
   The plan of improvement provides for widening, deepening, and
straightening the channel of Burgetts Fork through Burgettstown,
Pa., and vicinity for a distance of about 2 miles, filling the by-
passed reaches of the old channel, disposing of all excess exca-
vated material in certain reaches along the new channel, and pro-
tecting the banks of the new channel in certain locations.
   Local cooperation. Formal assurances dated May 21, 1952,
were furnished by the County of Washington, Pa., and were
accepted May 26, 1952.
   Operations and results during fiscal year. New work: Remain-
ing work of installation of a project identification sign was com-
pleted by hired labor. The costs for the fiscal year were $256.
   Condition at end of fiscal year. Construction of the project was
started by contract July 6, 1952, and completed November 26, 1952.
The project was transferred to local interests for assumption of
operation and maintenance on December 12, 1952. The costs to
the end of the fiscal year were $83,129.
                                         Cost and financial summary

                                                  Fiscal year ending June 30                    Total to June
                                                                                         -     30, 1954, includ-
                                                                                               ing fiscal years
                                  1950          1951           1952         1953      1954       priorto 1950

New work:                                                             I
   Appropriated ...-------------------                     -   $96,000    -$12,500    -$371             $83,129
   Cost--------------            ----------------------         10,571       72,302      256             83,129



   In addition to those projects selected for construction, investiga-
tions are under way to determine the economic advisability and
plan of improvement at the following locations:
     Buffalo Creek at Rachel, W. Va.
     Wallace, W. Va.
     Amsterdam, Ohio
   Studies for an interim report, on advisability of undertaking a
212 project were in progress for Wallace, W. Va. A brief definite
project report was completed for Amsterdam, Ohio, and submitted
May 20, 1954.
   The costs for these projects for the fiscal year were $8,263. The
costs to the end of the fiscal year for these projects were $11.021.
1030           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                           Cost and financial summary
                                   BUFFALO CREEK, RACHEL, W. VA.


                                                        Fiscal year ending June 30                        Total to June
                                                                                                         30, 1954, includ-
                                                                                                         ing fiscal years
                                   1950               1951         1952        1953        1954           prior to 1950


New work:
   Appropriated---....     .
                         ------------------------ ------------                  $2,000                             $2,000
    Cost----------       ------------------------------------                    1,843            $374              1,880


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954__                      $120
    Unobligated balances available for succeeding fiscal year ending June 30,1955 120

                                           Cost and financial summary
                                                   WALLACE, W. VA.


                                                        Fiscal year ending June 30                       Total to June
                                                                                                         30, 1954, includ-
                                                                                                         ing fiscal years
                                   1950               1951         1952        1953        1954           prior to 1950

New work:
   Appropriated-----          -----------------------                           $5,000                             $5,000
   Cost........------------------------------------------------                    284     $2,407                   2,691

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954---------------      $2,309
    Unobligated balances available for succeeding fiscal year ending June 30,
         1955--__                                                                                                2,309


                                           Cost and financial summary
                                                 AMSTERDAM, OHIO


                                                        Fiscal year ending June 30                        Total to June
                                                                                                         30, 1954, includ-
                                                                       191ing                               fiscal years
                                   1950               1951         1952       1953         1954           prior to 1950

New work:
    Appropriated - -        -                                -         -        $6, 500                            $6,500
    Cost-- - -. - .- . --....   -
                       - . .i ........                ::------
                                                           ---
                                                             :: ---
                                                                  : -:               631   $5,819                   6,450


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 -            -           $50
    Unobligated balances available for succeeding fiscal year ending June 30, 1955 50
     IMPROVEMENT OF RIVERS AND HARBORS IN THE
             DULUTH, MINN., DISTRICT
  This district comprises northeastern Minnesota, northwestern
Wisconsin, and the northern portion of the Upper Peninsula of
Michigan, embracing the United States waters of Lake Superior
west of the head of St. Marys River and its tributary drainage
basin. It includes Isle Royale in Lake Superior.
                              IMPROVEMENTS

             Navigation                         Navigation-Continued
                                 Page                                        Page
1. Grand Marais Harbor, Minn__ 1031    10. Presque Isle Harbor, Mich-.      1046
2. Two Harbors (Agate Bay),
      Minn ------------------
                                        11. Marquette Harbor, Mich    --..   1047
                                 1033   12. Grand Marais Harbor of
3. Duluth-Superior Harbor,                   Refuge, Mich- -______-         1048
      Minn. and Wis-----------1034      13. Inactive navigation projects__   1050
4. Port Wing Harbor, Wis .--.. 1037    14. General Investigations ------    1050
                          -
5. Cornucopia Harbor, Wis_      1038
6. Ashland Harbor, Wis        _ 1040                 Flood control
7. Ontonagon Harbor, Mich---    1041
8. Keweenaw Waterway, Mich__ 1042      15. Flood control work under
9. Grand Traverse Bay Harbor,                special authorizations------   1050
      Mich_------------------_   1045

                 1. GRAND MARAIS HARBOR, MINN.
   Location. The harbor is situated on the north shore of Lake
Superior, 106 miles northeasterly from Duluth, Minn. (See U. S.
Lake Survey Chart No. 9.)
   Existing project. This provides for rock-filled timber crib
breakwater piers 350 feet in length from the east and west points
of the bay to narrow the entrance; for constructing concrete sea-
walls across the ledge at the southeast corner of the harbor; for
dredging an anchorage area of 36.5 acres to a depth of 16 feet with
depths near the entrance of 18 and 20 feet, and for a small boat
basin 100 feet wide, 600 feet long, and 8 feet deep in the north-
western part of the harbor protected by a breakwater 600 feet long
with a rubble mound shore connection. All depths are referred to
low water datum for Lake Superior, which is 601.6 feet above mean
tide at New York. The ordinary seasonal variation of water level
extends from 0 to +1 foot above low water datum. The harbor
is subject to extreme fluctuations of water level of a temporary
nature, due to wind and barometric conditions, of about 1 foot
above or below the mean lake level prevailing at the time.
   The estimate of cost for new work (1954) is $421,500. The
latest (1954) approved estimate of cost for annual maintenance
is $8,000.
                                                                      1031
1032            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

The existing project was authorized by the following River and
Harbor Acts:

    Acts                              Work authorized                                Documents 1

Mar. 3, 1879    Breakwaters and dredging of anchorage area of 26           H. Ex. Doc. 75, 43d Cong., 2d sess.
                  acres to 16 feet.                                          (Annual Report, 1875, p. 184).
Aug. 30, 1935   Sea walls across ledge in the southeast corner of the      Rivers and Harbors Committee
                 harbor, enlarging the anchorage basin and deepen-           Doc. 27, 72d Cong., 1st sess.
                 ing of entrance.
May 17, 1950    Small boat basin with breakwater.......---------------..   H. Doc. 187, 81st Cong., 1st sess.'

  I Contains latest published map.
   Local cooperation. The improvement authorized by the act of
May 17, 1950, is subject to the conditions that responsible local
interests give assurances satisfactory to the Secretary of the Army
that they will-
   a. Provide without cost to the United States all lands, easements,
rights-of-way, and spoil disposal areas necessary for the construc-
tion and subsequent maintenance of the work, when and as re-
quired.
   b. Hold and save the United States free from damages due to
the construction and subsequent maintenance of the works.
   c. Provide and maintain without cost to the United States, and
in accordance with plans approved by the Chief of Engineers, a
suitable and adequate wharf for the accommodation of small craft
which shall be open to all on equal terms.
   d. Establish a competent and properly constituted public body
empowered to regulate and manage the inner harbor facilities.
   Local interests were notified on September 29, 1950, of the re-
quired conditions of local cooperation.
   None of the above conditions have been complied with.
   Terminal facilities. There are two general merchandise
wharves, and several fish wharves, all privately owned. These
facilities are considered adequate for existing commerce.
   Operations and results during fiscal year. Condition surveys
were made at a cost of $1,674 and miscellaneous inspections and
reports cost $129. All work was performed by hired labor and use
of Government plant. The total cost was $1,803 for maintenance.
   Condition at end of fiscal year. The existing project is about
77 percent complete. Project depths of 16 feet in the anchorage
basin and 18 to 20 feet in the entrance channel are available.
Private parties dredged 420,795 cubic yards of gravel from the
harbor between 1922 and 1930 under permits and without cost to
the United States. To complete the project there remains the con-
struction of the inner small boat basin and protecting breakwater.
   The concrete sea walls are in excellent condition. The break-
waters are in good condition. The gravel spit along the eastern
side of the harbor is too low to prevent waves from rolling into
the harbor during severe storm periods.
   The total costs of the existing project at the end of the fiscal
year were $209,820 for new work and $128,077 for maintenance,
a total of $337,897.
                   RIVERS AND HARBORS-DULUTH, MINN., DISTRICT                                                  1033
                                                Cost and financial summary

                                                       Fiscal year ending June 30                       Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                                       1950           1951         1952        1953         1954        priorto 1950


New work:
               ------------------------
   Appropriated....                                            ------------ ------------ ------------          $209, 820
      Cost--------            ------------        ------------------------------------------------              209, 820
Maintenance:
    Appropriated ------------------........            -$688                                 $2, 400            128,674
      Cost-----------------                   $974 ---------------------------------          1,802             128,076

   1 Operation and results during fiscal year $1803, less pending adjustment of $1.
Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project                               $___________
                                                                        $211,700

                          2. TWO HARBORS (AGATE BAY), MINN.
    Location. The harbor is situated on the north shore of Lake
Superior, 27 miles northeasterly from Duluth, Minn. (See U. S.
.Lake Survey Chart No. 96.)
    Existing project. This provides for narrowing the natural en-
trance by the construction of two breakwaters, 1,625 feet and 900
feet long, from the eastern and western points of the bay, re-
spectively; and for dredging a maneuvering area on the north side
of the harbor to depths of 26 and 28 feet, referred to low water
datum for Lake Superior, which is taken at 601.6 feet above mean
tide at New York. The ordinary seasonal variation of water level
extends from 0 to +1 foot above low water datum. The harbor is
subject to extreme fluctuations of water level of a temporary na-
ture, due to wind and barometric conditions, of about 1 foot above
or below the mean lake level prevailing at the time.
    The cost for new work for the completed project was $3,554,154.
The latest (1954) approved estimate for annual cost of main-
tenance is $14,000.
    The existing project was authorized by the following River and
Harbor Acts:

     Acts                                 Work authorized                                   Documents

                  (Breakwater and dredging----------------------H. Ex. Doc. 94, 48th Cong., 2d sess.
Aug. 5, 1886       Construction of 2 breakwater piers.........---------------. Annual Report for 1887, p. 1952.
Aug. 30, 1935      Shore connection to east breakwater and dredging of         Rivers and Harbors Committee
                    maneuvering area.                                            Doe. 17, 72d Cong., 1st sess.
Nov. 7, 1945       Construction of new east breakwater and enlarge- H. Doc. 805, 78th Cong., 2d sess.
                     ment of maneuvering basin.                                     (Contains the latest published
                                                                                    map.)


  Local cooperation. Fully complied with.
   Terminal: facilities. There are no publicly owned wharves.
The ore docks, coal dock, merchandise wharf, and tug wharf are
privately owned. Facilities are considered adequate for existing
commerce.
  Operations and results during fiscal year. Condition surveys
were made at a cost of $3,651 and miscellaneous inspections and
reports cost $757. The last breakwater was riprapped with stone
1034           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

at a cost of $15,840 and repairs to the timber superstructure in
progress at the close of the fiscal year cost $986. All work was
performed by hired labor and use of Government plant. The total
cost was $21,234 for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1950. The breakwaters are in good condition. The proj-
ect depths in the maneuvering area were available at the end of
the fiscal year. The total costs were $3,554,154 for new work, and
$262,371 for maintenance, a total of $3,816,525.
                                       Cost and financial su nmmary

                                                Fiscal year ending June 30                           Total to June
                                                                                                    30, 1954, includ-
                                                                                                    ing fiscal years
                                1950          1951            1952            1953       1954         prior to 1950

New work:
   Appropriated
   Cost---
Maintenance:
            ---   --_   -
                            -$1,250,000
                                863,536
                                             $ 6,692
                                              368,586   ---
                                                                        ---
                                                                                     -     -
                                                                                                         $3, 554, 154
                                                                                                          3,554,154
   Appropriated       ---                                     $15,263    .-              $42, 000            283, 137
   Cost      ------------         ------   ------              15,263                    120,946             262, 083


1 Operations and results during fiscal year $21,234, less pending adjustment of $288.

            3. DULUTH-SUPERIOR                       HARBOR, MINN., AND WIS.
   Location. This harbor is at the extreme western end of Lake
Superior. The cities of Duluth, Minn., and Superior, Wis., are
situated on the north and south sides, respectively. (See U. S.
Lake Survey Chart No. 966.)
   Previous projects. Superior and Duluth were separate im-
provements until consolidated by the River and Harbor Act of
June 3, 1896. The original project for the harbor at Superior City
was adopted by River and Harbor Act of March 2, 1867; for
Duluth Harbor by River and Harbor Act of March 3, 1871. These
projects were modified by River and Harbor Acts of March 3,
1873; March 3, 1881; July 5, 1884; August 5, 1886; August 11,
1888; and July 13, 1892. For further details, see page 1929 of
Annual Report for 1915, and page 1400 of Annual Report for 1938.
   Existing project. This provides for the following work:
   a. Rebuilding the canal piers at Duluth entry with stone-filled
timber-crib substructure and concrete superstructure 1,734 feet
long and 300 feet apart for 1,250 feet, then flaring to 540 feet
apart at the harbor end.
   b. Replacing the north and south piers at Superior entry with
concrete piers 2,096 and 1,584 feet long respectively, 500 feet apart
for 808 feet then flaring at the harbor end.
   c. Constructing 4,205 feet of rubble-mound breakwater, 900 feet
of concrete pierheads on stone-filled cribs, and 896 feet of concrete
shore revetments at Superior entry, the lake ends being 600 feet
          RIVERS AND HARBORS-DULUTH. MINN., DISTRICT               1035
  apart on the 30-foot contour in prolongation of the entrance chan-
  nel and diverging to 2,100 feet apart at the shore line.
     d. A flared lake approach to Duluth entry 32 feet deep, and a
  channel between the piers 32 feet deep at the pierheads, gradually
  decreasing to 26 feet at the harbor basin.
     e. A depth of 26 feet in the northern part of the harbor basin
  inside Duluth entry consisting of 201 acres; and a depth of 25 feet
in the southern portion of the harbor basin, East Gate Basin, and
in Superior Front Channel, through Superior Bay, 600 feet in
width, extending to Superior Harbor Basin, a distance of 13,200
feet.
     f. A flared lake approach to Superior entry 32 feet deep; a chan-
nel between the breakwater entrance and the pierheads with a
width varying from a minimum of 600 feet to a maximum of 1,100
feet, 32 feet deep at the breakwater entrance, gradually decreasing
to 28 feet at the pierheads; a stilling basin of 20 acres, 24 feet deep,
inside the breakwater; and a channel between the piers, 28 feet
deep at the pierheads, gradually decreasing to 25 feet at the harbor
basin.
     g, A harbor basin of 290 acres, 25 feet deep, inside Superior
entry; a channel in Allouez Bay 2,100 feet long, 400 feet wide, and
22 feet deep; a depth of 25 feet in the south channel of St. Louis
Bay from the entrance (East Gate Basin) to the cross channel,
inclusive, with widths varying from 500 to 900 feet.
     h. A depth of 25 feet in a cross channel, with a minimum width
of 1,150 feet, and a depth of 25 feet in the north channel of St.
Louis Bay opposite the cross channel; elsewhere in the north chan-
nel and the south channel and the St. Louis River to a point 9,600
feet above the Grassy Point Bridge, a depth of 21 feet, and, except
at Arrowhead Bridge, a minimum width of 400 feet; and a chan-
nel thence up St. Louis River 20 feet deep and 200 feet wide to
Spirit Lake (southerly end of Big Island) a distance of about
14,200 feet.
    i. A channel in Howards Bay 6,000 feet long, narrowing in
width from 300 to 125 feet, and 21 feet deep; and a channel 3,300
feet long, 100 feet wide, and 20 feet deep at Twenty-first Avenue
West in Duluth.
    The project depths are referred to low water datum for Lake
Superior, which is 601.6 feet above mean tide at New York. High-
est single gage reading, November 28, 1905, was 3.7 feet above low
water datum; lowest single gage reading, January 23, 1926, was
1.95 feet below low water datum; the annual fluctuation is about 1
foot.
    The estimate of cost for new work (1954) is $7,482,000. The
latest (1954) approved estimate of cost for annual maintenance is
$140,000.
    The existing project was authorized by the following River and
Harbor Acts:
1036              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


       Acts                         Work authorized                                  Documents


June    3, 1896   Dredging --.   ----------------------------------       H. Ex. Doc. 59, 53d Cong., 3d sess.,
                                                                            and Annual Report, 1895, p. 2538.
June 13, 1902    Rebuilding piers at Superior entry-------------
Mar. 2, 1907     Enlargement of plan for Superior entry and addi-         H. Doc. 82, 59th Cong., 2d sess.
                  tional dredging near draw span of the Northern
                  Pacific R. R. bridge.
May    28, 19081 Dredging additional area for the basin inside Duluth    H. Doc. 221, 60th Cong., 1st sess.
                  entrance to 22-foot depth.
July   27, 1916 Enlarging Superior Harbor Basin ...-           --        H. Doc. 651, 64th Cong., 1st sess.
Mar.    2, 1919 Removal of shoal point at southerly end of the East      H. Doc. 1018, 64th Cong., 1st sess.
                  Gate Basin.                                              H. Doc. 245, 69th Cong., 1st sess.
Jan.   21,1927Howards Bay Channel, 20 feet dand                                  Rivers and Harbors Con-
July    3, 1930                                                            mittee Dec. 32, 71st Cong., 2d
                                                                           sess.                            3
Aug. 30, 1935 2   Present project dimensions of the channels and basins_ H. Doc. 482, 72d Cong., 2d sess.
July 16, 19524    Deepen Superior Front Channel and a portion of H. Doc. 374, 82d Cong., 2d sess.
                    East Gate Basin to 25 feet.


  1Administrative   act, sec. 4.
  2 Included in the Public Works Administration program Sept. 6, 1933.
  3 Contains last published map.
  4 Public Law 568.

   Local cooperation. Public Law 568, July 16, 1952, provides
that local interests shall give assurances satisfactory to the Secre-
tary of the Army that they will provide without cost to the United
States all necessary lands, easements, and rights-of-way for the
initial construction, and for subsequent maintenance when and as
required; and hold and save the United, States free from damages
due to the construction and maintenance of the project. Nego-
tiations with local interests are in progress. There are no prior
requirements of local cooperation.
   Terminal facilities. The terminal facilities, consisting of
wharves, ore docks, and grain elevators, are believed to be adequate
for existing commerce, and are being increased as necessity de-
mands.
   Operations and results during fiscal year. Condition surveys
were made at a cost of $26,190, miscellaneous inspections and re-
ports cost $12,720, and the maintenance of parks and grounds cost
$8,719. The breakwaters at the Superior entry were riprapped at
a cost of $18,995. Repairs to the Duluth canal piers in progress
at the close of the fiscal year cost $8,202. Dredging 240,986 cubic
yards of material for restoration of project depth in entrance chan-
nels and interior basins cost $140,379. All work was performed by
hired labor and use of Government plant. The total cost was $215 -
205 for maintenance.
   Condition at end of fiscal year. The existing project is about
92 percent complete.
   Project depths are available in the harbor as shown by surveys
completed in March 1954, except for Superior Front Channel and
scattered shoals in Superior Harbor Basin, East Gate Basin, Cross
Channel, and Howards Bay.
   The entrance piers and breakwaters are all in fair condition
except for concrete superstructure on a portion of the north pier
at Duluth entry which requires reinforcement, and a portion of the
south pier at Superior entry which is being undermined and re-
quires reinforcement.
  To complete the project there remains the deepening of Superior
                RIVERS AND HARBORS--DULUTH, MINN., DISTRICT                                                        1037
Front Channel to 25 feet.
  The total cost was $10,706,987, of which $6,857,291 was for new
work and $3,849,696 for maintenance.
                                        Cost and financial summary

                                                  Fiscal year ending June 30                               Total to June
                                                                                                           30, 1954, includ-
                                                                                                           ing fiscal years
                                 1950           1951            1952             1953           1954        prior to 1950

New work:
   Appropriated     ----------- ------------ ------------------------                         ---------        1$8, 404, 486
   Cost--------------- --..---------------
Maintenance:
                                                               ---------
                                                       .----------                        ------------          18, 404,486
    Appropriated-..------       $143,200       $162, 000      $222, 001      $235, 500         $223, 800          3,883,662
    Cost--------------- --       193,939        178,901         197,661          220,390           457
                                                                                              2 218,            2 3,   853, 415

   1Includes $1,547,195 for new work.
  3 Operation and results during fiscal year $215,205, plus pending adjustment of $3, 052, and unbilled re-
ceivables of $200. Stock on hand June 30, 1954, $467.
Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project_ -------- _  --        -      $624,700

                                4. PORT WING HARBOR, WIS.
   Location. The harbor is situated on the south shore of Lake
Superior, 34 miles easterly from Duluth. (See U. S. Lake Survey
Chart No. 96, Lake Superior.)
   Existing project. This provides for the construction of two
parallel piers at the entrance 200 feet apart and 800 and 825 feet
long, respectively, the piers to consist of two rows of piling filled in
with slabs and topped with large rock; for the construction of a
return pile revetment at the inner end of the east pier 45 feet in
length, to preserve the sand spit from erosion; for dredging two in-
ner channels 8 feet deep, one extending southerly 340 feet with a
width of 60 feet, and one easterly, 1,170 feet with a width of 70
feet, from an irregular shaped turning basin 15 feet deep at the
inner end of the piers, and for dredging a channel 150 feet wide
with a 15-foot depth between the piers.
   The project depth is referred to low-water datum for Lake Supe-
rior, which is 601.6 feet above mean tide at New York. The or-
dinary seasonal variation of water level extends from 0 to ±1 foot
above low water datum. The harbor is subject to extreme fluctu-
ations of water level of a temporary nature, due to wind and baro-
metric conditions, of about 1 foot above or below the mean lake
level prevailing at the time.
   The estimated cost for new work (1954) is $86,000. The latest
(1954) approved estimate for maintenance is $20,000.
   The existing project was authorized by the following River and
Harbor Acts:

    Acts                             Work authorized                                            Documents

June 13, 1902   Construction of parallel piers and dredging---------..........     H. Doc. 114, 56th Cong., 1st sess.
June 30, 1948   Dredging of inner channels and abandonment of cer-                 H. Doc. 668, 80th Cong., 2d sess.
                  tain revetments and channels.                                         (Contains latest published map.)
1038           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  Local cooperation. Fully complied with.
   Terminal facilities. There are four privately owned fishing
wharves which are considered adequate for existing commerce.
   Operations and results during fiscal year. Condition surveys
were made, at a cost of $462, with hired labor and use of Govern-
ment plant. The total cost was $462.
   Condition at end of fiscal year. The existing project, which is
about 75 percent complete, consists of two entrance piers, 800 and
825 feet long, completed in 1917; a pile revetment 45 feet long at
the inner end of the east pier and perpendicular to it, completed in
1903; an entrance channel 150 feet wide in the lake approach and
100 feet wide in the harbor, extending from deep water in the lake
to a distance of 200 feet inside the inner end of the east pier, and
a portion of the turning slip 150 feet wide and extending 200 feet
east of the face of the east pier, dredged to a depth of 15 feet below
low water datum in 1911; two inner channels 8 feet deep, one ex-
tending southerly 340 feet with a width of 60 feet and one easterly
1,170 feet with width of 70 feet, from the inner turning basin,
completed in 1950. The east pier is in good condition. The west
pier is in poor condition due to decay, wear of ice, and settlement
of stone and slab filling.
   At the close of the fiscal year the controlling depth was 8.5 feet
in the lake approach, 10.5 feet between the piers, 7 feet in the
easterly boat channel, and 1 foot in the south channel. To complete
the project it would be necessary to widen the channel 506 feet
between the piers.
   The total costs and expenditures were $387,146, of which $63,-
393 was for new work and $323,753 for maintenance.
                                  Cost and financial summary

                                          Fiscal year ending June 30                    Total to June
                                       .. .    ..        .        .        .            30, 1954, includ-
                                                                                        ing fiscal years
                           1950         1951         1952        1953          1954       priorto 1950

New work:
   Appropriated-. .-
                   -      $20, 000    -$4, 962$                                                   63,393
   Cost .................-- 11,235      3,803.-        -.-   ..........                           63,393
Maintenance:
   Appropriated .-...      49,000        10,000    -$1,486        -$486        $1,200            324,491
   Cost_-   -  -           91,635        79,010 --------           1,045          462            323,753


Other new work data: Estimated additional amount needed to be appropri-
                                          -_
  ated for completion of existing project _       _          ___      -                       $_22,600

                         5. CORNUCOPIA HARBOR, WIS.
   Location. The harbor is located at the mouth of the Siskiwit
River on the south shore of Lake Superior, 49 miles east from
Duluth, Minn. (See U. S. Lake Survey Chart No. 96.)
  Existing project. This provides for an entrance channel 50 feet
wide and 10 feet deep between the piers constructed and main-
tained by local interests from Siskiwit Bay to a turning basin 200
feet long, 8 feet deep, and 140 feet wide, with a maximum width of
about 180 feet; and two inner channels 50 feet wide and 8 feet
deep, with lengths of 150 and 300 feet. All depths are referred to
low water datum for Lake Superior, which is taken at 601.6 feet
                 RIVERS AND HARBORS-DULUTH, MINN., DISTRICT                                    1039
above mean tide level at New York. The ordinary seasonal vari-
ation of water level extends from 0 to +1 foot above low water
datum. The harbor is subject to extreme fluctuations of water
level of a temporary nature, due to wind and barometric conditions,
of about 1 foot above or below the mean lake level prevailing at the
time.
    The cost for new work for the completed project was $10,190.
The latest (1954) approved estimate of cost for annual main-
tenance is $6,000.
    The existing project was authorized by River and Harbor Act
approved August 26, 1937 (Senate committee print, 75th Cong.,
1st sees.). This document contains the latest published map.
    Recommended modification of project. The Chief of Engineers
in a letter of March 1954 to the Secretary of the Army recom-
mends, subject to certain conditions of local cooperation, modifica-
tions of existing project to provide for reconstruction and Federal
maintenance of the east and west entrance piers, including an in-
crease of 25 feet in the length of the west pier, and extension of ex-
isting westerly inner channel for a distance of 300 feet at a depth
of 8 feet and a width of 50 feet. The total estimated first cost
 (1953) is $220,000, with no increase in the estimated cost of an-
nual maintenance.
   Local cooperation. Fully complied with.
    Terminal facilities. About 1,100 linear feet of privately owned
docking space have been improved for small fishing boats. These
facilities are adequate for existing commerce.
    Operations and results during fiscal year. Condition surveys
were made at a cost of $736. Dredging 7,328 cubic yards of ma-
terial, in progress at the close of the previous fiscal year, for
restoration of project depth by removal of shoal in entrance chan-
nel, was completed at a cost of $7.371. All work was performed
by hired labor and use of Government plant. The total cost for
maintenance was $8,107.
   Condition at end of fiscal year. The existing project was com-
pleted in 1939. The controlling depths at the end of the fiscal
year were 8.5 feet in lake approach, 6 feet in the channel between
the piers and 6.8 feet in the inner slips.
   The total costs were $57,553, of which $10,190 was for new work
and $47,363 for maintenance.
                                   Cost and financial summary

                                          Fiscal year ending June 30                    Total to June
                                                                                       30,1954, includ-

                            1950        1951              1952   1953       1954        prior to 1950

New work:
   Appropriated ....                                                                           $10, 190
   Cost                                                                --    -10,190
Maintenance:
    Appropriated    ----    $1, 000      -$940     i --           $8, 436   $9, 150             48,406
    Cost------   --------       175            122 '-__-_--        8,436     8, 107             47,363
1040             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                   6. ASHLAND HARBOR, WIS.
   Location. The harbor is situated at the head of Chequamegon
Bay, on the south shore of Lake Superior. (See U. S. Lake Survey
Chart No. 964.)
   Existing project. This provides for an 8,000-foot breakwater
and a dredged channel along the dock front, 75 feet outside the
harbor line, 20 feet deep and 200 feet wide from a point 400 feet
west of Seventeenth Avenue West produced to Eighth Avenue
West produced; and a flared channel 21 feet deep, 750 feet wide at
its westerly end and 400 feet wide at its easterly end and from
Eighth Avenue West produced to Ellis Avenue produced; for an
entrance channel 21 feet deep and 400 feet wide extending in a
northerly direction from the easterly end of this channel; and a
basin 25 feet deep and about 4,800 feet long, extending from a point
about 400 feet west of the Soo dock to a point 1,000 feet east of the
Chicago & North Western dock 3, and extending from a line 75 feet
outside of the harbor line to deep water in the bay.
   The project depths are referred to low water datum for Lake
Superior, which is 601.6 feet above mean tide at New York. The
ordinary seasonal variation of water level extends from 0 to +-1
foot above low water datum. The harbor is subject to extreme
fluctuations of water level of a temporary nature, due to wind and
barometric conditions, of about 1 foot above or below the mean
lake level prevailing at the time.
   The cost for new work for the completed project was $779,078.
The latest (1954) approved estimate for annual cost of mainte-
nance is $19,000.
   The existing project was authorized by the following River and
Harbor Acts:
     Acts                             Work authorized                                    Documents

Aug. 5, 1886        Breakwater 7,900 feet long and dredging to remove a       H. Ex. Doc. 89, 48th Cong., 2d sess.
                      shoal.                                                    Annual Reports, 1886, p. 1674;
                                                                                and 1887, p. 1966.
Aug. 11, 1888       Appropriation of $60,000 for "Continuing improve-
                     ment on the enlarged project." (On the completion
                     of the Poe lock in 1896, with an available depth of 20
                     feet, the dredging at Ashland Harbor was carried to
                     a similar depth.)
                    Detached breakwater extending 4,700 feet out from
Mar. 3, 1899          the shore at a point 2,600 feet east of the main
June 6, 1900         breakwater (prolonged) and parallel thereto.
Aug. 8, 1917        Project modified by omitting the detached break-          H. Doc. 1698, 64th Cong., 2d sess.
                     water and defining the depth and extent of the
                     channel to be dredged.
July 3, 1930        Widening of part of the present channel for an en-        S. Doc. 133, 71st Cong., 2d sess.
                      trance channel and for the basin in the eastern part
                     of the harbor.
Aug. 30, 1935   1   Deepening east basin to 25 feet and the west channel,     Rivers and Harbors Committee
                                                                                Doc. 46, 72d Cong., 1st sess. 2
                     as far as 8th Ave. West, extended, to 21 feet.
Mar. 2, 1945        Widening the west channel to a width of 750 feet at its   H. Doc. 337, 77th Cong., 1st sess.
                     westerly end.

  1 Included in Public Works Administration program, Sept. 6, 1933.
  2 Contains latest published map.

SLocal cooperation. Fully complied with.
  Terminal facilities. The city of Ashland owns 4,150 feet of
water front, exclusive of street ends, for future public needs.
  The wharves for handling coal, ore, and pulpwood are served by
              RIVERS AND HARBORS-DULUTH, MINN., DISTRICT                                              1041
railroads. The facilities are considered adequate for existing com-
merce.
   Operations and results during fiscal year. Condition surveys
were made at a cost of $876 and miscellaneous inspections and re-
ports cost $163. Repairs were made to the rubble mound break-
water at a cost of $21,605. All work was performed by hired labor
and use of Government plant. The total cost was $22,644 for
maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1950. The breakwater is in good condition, except for
some settlement, which should be brought up to the prescribed el-
evations. At the end of the fiscal year, project depths were avail-
able in the west channel and east basin, except for minor shoals
in the east basin maneuvering area. The total cost was $1,307,070,
of which $779,078 was for new work, and $527,992 for main-
tenance:
                                    Cost and financial summary

                                          Fiscal year ending June 30                           Total to June
                                                                                       _30,       1954, includ-
                                                                                              ing fiscal years
                             1950        1951       1952         1953           1954            prior to 1950

New work:
   Appropriated ----   __    $45,000     $ 1,703                                                      $779, 078
   Cost                       31, 853     11,850                                                       779, 078
Maintenance:
   Appropriated- ..
                 -  .          2,300        381                   $7, 000       $24, 400               530, 786
   Cost __________             3,547       1,686                   7,648    i   22,643               1529, 677


  I Operation and results during fiscal          lesspending adjustment of $1. Stock on hand June
                                      year $22,644
30, 1954, $1,686.

                            7. ONTONAGON HARBOR, MICH.
    Location. The harbor is situated on the south shore of Lake
Superior. It consists of the improvement of the mouth of Onto-
nagon River. (See U. S. Lake Survey Chart No. 95.)
    Previous project. Adopted by River and Harbor Act of March
2, 1867. For further details see page 1931 of Annual Report for
1915, and page 1406 of Annual Report for 1938.
    Existing project. This provides for a flared lake approach
channel 17 feet deep with widths narrowing from 400 feet at the
outer end to 150 feet opposite the outer end of the west pier; a
channel between the piers 150 feet wide, 17 feet deep in the outer
250 feet, and 15 feet deep in the inner 2,200 feet; an inner basin
15 feet deep and 900 feet long, extending between lines 50 feet
from the existing wharves on each side of the river, the maximum
width being 285 feet; and the maintenance of this channel, basin,
and the 4,990 feet of entrance piers. The project depth is referred
to low water datum for Lake Superior, which is taken at 601.6 feet
above mean tide level at New York. The ordinary seasonal vari-
ation of water level extends from 0 to +1 foot above low water
datum. The harbor is subject to extreme fluctuations of water
level of a temporaryjnature, due to wind and barometric conditions,
of about 1 foot above or below the meican lake level prevailing at the
time..  -
 1042               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   The cost for new work for the completed project was $19,620,
exclusive of the amount expended on previous project. The latest
 (1954) approved estimate for annual maintenance is $40,000.
   The existing project was authorized by the following River and
Harbor Acts:
       Acts                                Work authorized                                            Documents

June 25, 1910      Channel 17 feet deep and 150 feet wide through the                     H. Doc. 602, 61st Cong., 2d sess.
                      bar and 15 feet deep and 100 feet wide between
                      the piers, and pier maintenance.
Aug. 26, 1937      Present project widths and inner basin   .        ------------         Senate committee print, 74th
                                                                                             Cong., 2d sess. (Contains the
                                                                                             latest published map.)


   Local cooperation. None required.
    Terminal facilities. There are no publicly owned wharves.
There are 1 merchandise and coal wharf, 1 coal wharf, and a few
small fish wharves in active use. The terminal facilities are con-
sidered adequate for the commerce of the harbor.
    Operations and results during fiscal year. Condition surveys
were made at a cost of $1,580 and miscellaneous inspections and
reports cost $221. All work was performed by hired labor and use
of Government plant. The total cost was $1,800 for maintenance.
    Condition at end of fiscal year. The existing project was com-
pleted in 1938. The piers are in fair condition except for a break
in the outer end of the east pier and minor repairs needed on stone
covered portions. At the close of the fiscal year, the controlling
depths were 7.8 feet in the lake approach channel, 10 feet in the
easterly 100 feet of the channel between the piers and 5 feet in the
harbor basin. The total costs were $19,619 for new work and
 $920,376 for maintenance, a total of $939,995.
                                              Cost and financial summary

                                                        Fiscal year ending June 30                             Total to June
                                                                                                               30, 1954, includ-
                                                                                                               ing fiscal years
                                      1950             1951            1952            1953         1954        priorto 1950

New'work:
     Appropriated -- ------------               ------------ ---------------------------------                          304,421
     Cost....---------    ------------------------            ------------                                              304,421
Maintenance:
     Appropriated.--------$60, 800                     $43, 000           $380         $18, 600      $2, 650         1,041, 760
     Cost ---------------.................---
                       59,807 43, 340  83   19,077                                                   21,803         21,040, 396

  '"Includes $284,801 for new work and $113,327 for maintenance for previous projects.
  2Operation and results during fiscal year $1,800, plus pending adjustment of $3. Stock on hand June
30, 1954, $6,691.

                               8. KEWEENAW WATERWAY, MICH.
  Location. This waterway is a navigable channel, minimum
width 300 feet, 25 miles long, partly natural and partly artificial,
across Keweenaw Point, Mich. (See U. S. Lake Survey Chart No.
944.)
  Existing project. This provides for the following work:
  a. A waterway across Keweenaw Peninsula via Portage Lake,
25 feet deep and 300 feet wide, increased to 400 feet through Port-
                 RIVERS AND HARBORS-DULUTH, MINN., DISTRICT                                             1043
age Lake below the shoal at its head and with a straight cutoff
channel from Princess Point to Messners Point.
   b. Flaring eastern entrance from Keweenaw Bay, 28 feet deep in
the outer portion, diminishing to 25 feet in the inner portion, pro-
tected by a breakwater 5,714 feet long.
   c. A mooring basin inside the east entrance, one-half mile long,
800 feet wide, and 25 feet deep, with mooring piers protected by
fender piling.
   d. Converging breakwaters at the western entrance, with west-
erly breakwater 2,645 feet long and easterly breakwater 2,485 feet,
having an entrance 500 feet wide between the breakwaters.
   e. A western entrance channel 32 feet deep lakeward of the en-
trance between the breakwaters, diminishing to 25 feet in quiet
water and enlarged inside of the breakwaters into a maneuvering
basin, 1,000 feet in maximum width and 3,000 feet long.
   f. A mooring basin inside the west entrance 3,600 feet long and
800 feet wide and 25 feet deep, with mooring piers protected by
fender piling.
   g. Reveting the banks as necessary.
   h. Pierheads 400 feet long at the west entrance to the canal.
   The project depth is referred to low water datum for Lake Supe-
rior, which is 601.6 feet above mean tide at New York. On account
of its length, the waterway is affected in a very slight degree by
lake fluctuations of short duration. The annual fluctuation is about
1 foot.
   The estimate of cost for new work (1954) is $8,120,000. The
latest (1954) approved estimate for annual cost of maintenance is
$100,000.
   The existing project was authorized by the following River and
Harbor Acts:

     Acts                           Work authorized                                    Documents

Sept. 19, 1890   Acquisition of the waterway; for a 16-foot channel of      H. Ex. Doc. 105, 49th Cong., 2d
                  70-foot bottom width, renewal of canal revetments,         sess., and Annual Report, 1887,
                  the reconstruction and extension of piers at the           p. 1977.
                  upper entrance to 30-foot depth of water, and at the
                  proper time for the increase of the channel depth to
                  20 feet with bottom width of not less than 120 feet
                   (increase in width and depth of channel was ap-
                   proved Mar. 15, 1898).
June 25, 1910    Anchorage basin just within the lower entrance,            H. Doc. 325, 60th Cong., 1st sess.
                   about     mile long, 800 feet wide; a mooring pier
                   on its westerly side 2,000 feet in length, and for the
                   purchase of the necessary land.
Mar. 8, 1919     Princess Point Cut-off Channel._--   _--------------- H. Doc. 835, 63d Cong., 2d sess. 2
Aug. 30, 19351   General deepening, widening, and straightening of H. Doc. 55, 73d Cong., 1st sess.
                   channels and basins to provide 25-foot depth with
                   additional over depth at entrances, extension of the
                   lower entrance breakwater, and the necessary alter-
                   ation or replacement of structures due to deepening
                   of the channels.

1 Included in the Emergency Relief Administration        program, May 28, 1935.
2 Contains the latest published maps.



   Local cooperation. None required.
   Terminal facilities. The 6 coal docks, 3 general merchandise
wharves, and several minor wharves, all privately owned, are
served by improvements made along Keweenaw Waterway. The
 1044                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

city of Hancock has 2 publicly owned wharves. The village of
Houghton has wharf improvements at the ends of 3 streets. The
facilities are considered adequate for existing commerce.
    Operations and results during fiscal year. Condition surveys
were made at a cost of $8,305 and miscellaneous inspections and
reports cost $4,195. Removal of old timber revetment was ac-
complished at a cost of $6,445. Repairs to west breakwater cost
 $38,047. Removal of floating obstructions cost $342. Dredging
accomplished in the previous fiscal year involved an additional cost
of $42. All work was performed by hired labor and use of Gov-
ernment plant. The total cost was $57,376 for maintenance.
    Condition at end of fiscal year. The existing project is 75 per-
cent complete. The breakwaters are in good condition except for a
weakness occurring in about 300 feet of the substructure of the
breakwater at the lower entrance,' and the stone-covered portions
of the breakwaters at the upper entrance are in need of minor
repairs. The remaining timber revetments along the waterway
are in poor condition. The mooring pier at the Lily Pond requires
repairs to halt movement, and permit dredging to project depth
adjacent thereto, and that at the Portage River harbor of refuge is
in good condition.. Annual redredging of channels will be required
indefinitely. The controlling depth on June 30, 1953, was 25 feet.
To complete the project there remains the extension of the lower
entrance breakwater, and the necessary alteration or replacement
of structures due to deepening of channels.
   For work performed with regular funds, the costs of the exist-
ing project were $5,772,115 for new work and $3,267,628 for main-
tenance, a total of $9,039,743.
   For work performed with Emergency Relief funds the total
costs and expenditures were $182,826, all for new work. The total
cost, all funds, was $9,222,569 of which $5,954,941 was for new
work and $3,267,628 for maintenance.
   In addition, the sum of $402,242 was expended between 1893
and 1917 on the operation and care of the works of improvement
under the provisions of the permanent indefinite appropriations
for such purposes.

                                       Cost andfinancial summary

                                             Fiscal year ending June 30                      Total to June
                                                                                             30, 1954, includ-
                                                                                             ing fiscal years
                                1950        1951        1952        1953         1954         prior to 1950

New work:
     Appropriated -----         -$420                                                              $5, 954,941
     Cost...-----------------   17,422                     ---                          __          5,954,941
Maintenance:
   Appropriated-......          28,000     $106,000    $67,500      $31,664     $60,600            3,683, 940
   Cost-----------------        49,427       87,297     73,266       31, 572    1 57,099'         13, 680, 582

  1 Operation and results during fiscal year $57,376, less pending adjustment of $277. Stock on hand June
30, 1954, $10,990.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project- -;_-
                                                -    -    --        ' $2, 165,100
            RIVERS AND HARBORS-DULUTH, MINN., DISTRICT                                          1045
                9. GRAND TRAVERSE BAY HARBOR, MICH.
   Location. The harbor is located at the mouth of the Traverse
River on the eastern shore of the Keweenaw Peninsula about 20
miles northeasterly from the Portage Entry to Keweenaw Water-
way. (See U. S. Lake Survey Chart No. 94.)
   Existing project. This provides for 2 parallel piers having
lengths of 650 feet and 380 feet for the north and south piers, re-
spectively; for an entrance channel between the piers 50 feet wide
and 12 feet deep; and for a harbor basin with a depth of 10 feet for
a maximum width of 200 feet and a maximum length of 450 feet.
   Project depths are referred to low water datum for Lake Supe-
rior, which is 601.6 feet above mean tide at New York. The or-
dinary seasonal variation of water level extends from 0 to +1 foot
above low water datum. The harbor is subject to extreme fluctu-
ations of water level of a temporary nature, due to wind and baro-
metric conditions, of about 1 foot above or below the mean lake
level prevailing at the time.
   The cost for new work for the completed project was $197,771.
The latest (1954) approved estimate of cost for annual mainte-
tenance is $1,000.
   The existing project was authorized by the River and Harbor
Act approved March 2, 1945 (H. Doc. 446, 78th Cong., 2d sess.).
This document contains the latest published map.
   Local cooperation. Fully complied with.
   Terminal facilities. There are several privately owned fishing
wharves. The facilities are considered adequate for existing com-
merce.
   Operations and results during fiscal year. Condition surveys
were made by hired labor and use of Government plant at a total
cost of $303 for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1950. The new entrance piers are in good condition ex-
cept that certain alterations are needed to more adequately protect
the harbor from storms from the east to southeast. The control-
ling depths at the end of the fiscal year were 9 feet in the lake ap-
proach, 8.5 feet in the entrance channel and 6 feet and 2.5 feet in
the southern and northern portions of the harbor basin, respec-
tively. The total cost was $287,177, of which $197,771 was for new
work and $89,406 for maintenance.
                                   Cost and financial summary

                                           Fiscal year ending June 30                    Total to June
                                                                                        30, 1954, includ-
                                                                                        ing fiscal years
                           1950          1951      • 1952         1953         1954      priorto 1950

New work:
   Appropriated_t
       .   ..
            . ..-                         --        _------      -$2, 229 ------------          $197,771
   Cost_---___
             ____--_      $150,555            ------------------------------------
                                         $20,431                                                 197,771
Maintenance:
   Appropriated....................        3,352     $86,173   ------------.......
                                                                        $1,100   90,625
   Cost ..----------------------           3,352      85,372            380      1307             89,410

1Operation and resultsduring   fiscal
                                     year $303,plus pending adjustment of$4.
1046            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                             10. PRESQUE ISLE HARBOR, MICH.
   Location. This harbor (formerly known as Marquette Bay
Harbor of Refuge, Mich.), situated on the south shore of Lake Su-
perior within the city limits of Marquette and about 3 miles distant
from Marquette Harbor, is about 1       miles long and / 2 -mile wide
and is protected by a breakwater. It is an indentation in the shore
behind Presque Isle Point. (See U. S. Lake Survey Chart No.
935.)
   Existing project. This provides for a 2,816-foot breakwater off
Presque Isle Point consisting of 216 feet of shore connection, 1,000
feet of stone-filled timber cribs, and 1,600 feet of rubble-mound
section; and dredging the harbor to a depth of 26 feet in the inner
portion, with 28 feet at the entrance, both depths referred to low
water datum for Lake Superior, which is 601.6 feet above the mean
tide at New York. The ordinary seasonal variation in water level
extends from 0 to +1 foot above low water datum. The harbor is
subject to extreme fluctuations of water level of a temporary na-
ture, due to wind and barometric conditions, of about 1 foot above
or below the mean lake level prevailing at the time.
   The cost for new work for the completed project was $898,809.
The latest (1954) approved estimate of cost for annual mainte-
nance is $5,500.
   The existing project was authorized by the following river and
harbor acts:

    Acts                             Work authorized                                        Documents

June 3, 1896
June 13, 1902
                Breakwater, 1,000 feet long    ---
                Shore extension, 216 feet long--
                                                           .-   -..   _           H. Doe. 318, 54th Cong., ]st sess.
                                               ...-.......            __ __       Annual Report for 1903, pp. 474,
                                                                                   1823.
Aug. 30, 1935   For dredging and rubble-mound extension to break-                 H. Doe. 473, 72d Cong., 2d sess.
                  water, 1,600 feet long. Changed designation of              I     (Contains the latest published
                  project.                                                         map.)


  Local cooperation. None required.
   Terminal facilities. There is 1 merchandise wharf and 1 ore
dock. The facilities are considered adequate for existing com-
merce.
   Operations and results during fiscal year. Condition surveys
were made at a cost of $569 and miscellaneous inspections and re-
ports cost $207. Repairs to rubble mound breakwater cost $24,-
605. All work was performed by hired labor and use of Government
plant. The total cost was $25,381 for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1939. The breakwater is in fair condition but requires
replacement of some stone. The controlling depth was 26 feet.
The total costs were $1,041,230 of which $898,809 was for new
work and $142,421 for maintenance.
                    RIVERS AND HARBORS-DULUTH, MINN., DISTRICT                                                            1047
                                               Cost and financial summary

                                                           Fiscal year ending June 30                              Total to June
                                                                                                                  30, 1954, includ-
                                                                                                                  ing fiscal years
                                        1950            1951          1952        1953               1954          priorto 1950


New work:
   Appropriated              -   --                   ..        ---               -------- ---          ---               $898,809
   Cost..--------------------                       --------                                    --            -            898,809
Maintenance:
    Appropriated
    Cost_
                            -         ---------------------
                                       - - --
                                               7
                                            $88--  $122.I
                                                                                   $1,400
                                                                                    1,400
                                                                                                     $28,000
                                                                                                     1 23,133
                                                                                                                           146,039
                                                                                                                           140,172

  1 Operation and results during fiscal year $25,381, less pending adjustment of $2,248.

                                      11. MARQUETTE HARBOR, MICH.
   Location. This harbor is situated in Marquette Bay on the
south shore of Lake Superior, 160 miles west of Sault Ste. Marie,
Mich., and 256 miles east from Duluth, Minn. (See U. S. Lake
Survey Chart No. 935.)
   Existing project. This provides for a 4,500-foot breakwater,
the inner 3,000 feet of stone-filled timber cribs, and the outer 1,500
feet of rubble-mound construction, and dredging the harbor basin
to a depth of 25 feet, giving a protected area of 350 acres. The
project depth is referred to low water datum for Lake Superior,
which is 601.6 feet above mean tide at New York. The ordinary
seasonal variation in water level extends from 0 to +1 foot above
low water datum. The harbor is subject to extreme fluctuations of
water level of a temporary nature, due to wind and barometric
conditions, of about 1 foot above or below the mean lake level pre-
vailing at the time.
   The cost for new work for the completed project was $1,117,312.
The latest (1954) approved estimate of cost for annual main-
tenance is $10,000.
   The existing project was authorized by the following River and
Harbor Acts:

     Acts                                 Work authorized                                             Documents

Mar. 2, 1867        Breakwater, 2,000 feet long -----------------------..           H. Ex. Doc. 56, 39th Cong., 2d sess.,
                                                                                     pts. 1 and 2, and Annual Report,
                                                                                     1866, pp. 8 and 77.
Aug. 11, 1888       Extending the breakwater 1,000 feet--------------               Annual Report, 1889, pp. 272 and
                                                                                        2021.
June 25, 1910       Additional 1,500-foot extension to the breakwater and H. Doc. 573, 61st Cong., 2d sess.
                     removing a shoal in the northerly partof the harbor.
Aug. 30, 19351      Deepening of the harbor basin to 25 feet-----
                                                               ......--. Rivers and Harbors Committee
                                                                           Doc. 20, 72d Cong., 1st sess.'

  1Included in the Public Works Administration program, Sept. 6, 1933.
  s Contains the latest published map.


  Local cooperation. None required.
   Terminal facilities These consist of 1 ore dock, 1 coal dock,
and 2 oil wharves. There are also several small fish wharves with-
out railroad connections. The facilities are considered adequate
for existing commerce.
  Operations and results during fiscal year. Condition surveys
were made at a cost of $712 and miscellaneous inspections and re-
1048            REPORT OF CHIEF OF ENGINEERS, U: S. ARMY, 1954

ports cost $41. Repairs to rubble mound breakwater, in progress
at the close of the previous fiscal year, were completed at a cost of
$1,002. All work was performed by hired labor and use of Gov-
ernment plant.. The total cost was $1,775 for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1935. The concrete-covered breakwater was completed in
the fiscal year 1905, the rubble-mound portion of the breakwater
in 1922, and the dredging in 1935. The rubble-mound portion of
the breakwater is in fair condition but requires replacement of
some stone and patching and resurfacing are necessary on a por-
tion of the concrete-capped breakwater. The controlling depth in
the harbor is 25 feet.
   The total cost was $1,531,396, of which $1,117,312 was for new
work and $414,084 for maintenance, including $72,188 public
works funds for new work.
                                             Cost and finantial summary

                                                     Fiscal year ending June 30                              Total to June
                                                                                                       - _30, 1954, includ-
                                                                                      I                   ing fiscal years
                                      1950        1951                   1952       1953          1954      priorto 1950

New work:
     Appropriated
     C ost- - - -
                      -.         ---...-....
                      .-- --.......- - - -------------
                                   "--    i_-
                                                  =...
                                                  -
                                                           ..-
                                                  ------.------------
                                                       ------------------                      -----------.
                                                                                                                 $1,117,312
                                                                                                                  1,117,312
Maintenance:                 ,
     Appropriated.-------         -- $1,000       $16,000               -$1,263     $21, 300     -$2, 000           416,77(
     Cost----------                   1,675        14,827                       -    14,859        11, 759          414, 088

1   Operation and results during fiscal year $1, 755, plus pending adjustments of $4.


              12. GRAND                MARAIS HARBOR OF REFUGE,                                     MICH.
   Location. The harbor is situated on the south shore of Lake
Superior, 314 miles east of Duluth, Minn., and 93 miles west of
Sault Ste. Marie, Mich. (See U. S. Lake Survey Chart No. 9.)
   Existing project. This provides for parallel timber-crib piers
500 feet apart-aggregate length 4,566 feet--extending out to a
depth in the lake of 22 feet at ordinary low water; for closing the
natural entrance by a pile dike 5,770 feet long; and for dredging a
channel 300 feet wide and 18 feet deep between the piers, and 500
feet wide and 20 feet deep at the lake approach. The project depth
is referred to low water datum for Lake Superior, which is 601.6
feet above mean tide at New York. The ordinary seasonal vari-
ation in water level extends from 0 to +1 foot above low water
datum. The harbor is subject to extreme fluctuations of water
level of a temporary nature, due to wind and barometric conditions,
of about 1 foot above or below the mean lake level prevailing at
the time.
   The estimate of cost for new work (1954) is $1,070,000. The lat-
est (1954) approved estimate for annual maintenance is $30,000.
   The existing project was authorized by the following River and
Harbor Acts:
                RIVERS AND HARBORS-DULUTH, MINN., DISTRICT                                                     1049

    Acts                            Work authorized                                          Documents

                  Existing project, except for pile dike-----                    Specified in act.
June 14, 1880    Exsting project, except for pile dike      ......              Annual Report, 1881, p. 2050.
                 For pile dike...._-------------------------------              Annual Report, 1895, p. 351.
May 17, 1950     800 foot extension of west pier....--------------------        H. Doc. 751, 80th Cong., 2d sess.


  SContains latest published map.

   Local cooperation. None required.
   Terminal facilities. There is no rail connection with the harbor.
There are several small fish wharves. The facilities are considered
adequate for present needs.
   Operations and results during fiscal year. Condition surveys
were made by hired labor and use of Government plant at a total
cost of $2,620 for maintenance.
   Condition at end of fiscal year. The existing project is 80 per-
cent complete. Parallel piers were built 500 feet apart, 1,912 and
1,545 feet long, respectively, including 100 feet of pile revetment at
the inner end of each pier; a channel 250 feet wide and 18 feet
deep was dredged between the piers from the lake to the bay; and
a pile dike was built in 1895-97 to close a natural entrance 5,770
feet in width. The west pier is in poor condition and requires re-
pairs. The superstructure of the outer 744 feet of the east pier
has been rebuilt in concrete and the balance of this pier is in fair
condition but needs some timber decking and stone cover. The
timber portion of the pile dike is in poor condition and the stone
protection has settled. Some portions of the dike have been en-
tirely destroyed by storm action. The controlling depths at the
end of the fiscal year were 15.8 feet deep in the lake approach and
17.0 feet in the channel. To complete the project there remains to
construct an 800 linear foot extension to the existing west pier,
and dredging to widen the inner portion of the channel from 250
feet to the project width of 300 feet.
   The costs were $355,885 for new work and $818,133 for main-
tenance, a total of $1,174,018.
                                        Cost and financial summary

                                                Fiscal year ending June 30                             Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                                 1950          1951             1952        1953            1954        priorto 1950

New work:
    Appropriated                            -----......                 -----------                           $355, 885
                                                                                                              $..........
   Cost---------------                  -----------.........---------------------
                               --------..
                                    .                                                       ------------        355,885
Maintenance:
    Appropriated ..             $166, 000     $ 44,000      $ 53, 243       $16, 286         $2, 200           820,081
    Cost -..............-         16,308       136,501       111,992         13, 918         12,549            818061


  I Operation   and results during fiscal year $2,620, less pending adjustment of $71.
Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project-                              $714,100              - --
1050            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                        13. INACTIVE            NAVIGATION                  PROJECTS

                                                                           Cost to June 30, 1954
                                                          For last                                          Estimated
                   Name of project                      full report                                           amount
                                                        see annual                   Operations             required to
                                                        report for-    Construction     and                  complete"
                                                                                    maintenance


1.   Bayfield Harbor, Wis. 2__ _               -_           1950                                                147, 300
                                                                                                                $--------------------
2.   Beaver Bay Harbor, Minn. 2.................            1945      -                                         216, 200
3.   Big Bay Harbor, Mich ...--------------------           1949                                              ' 188,000
4.                             ------------------
      Black River Harbor, Mich....                           1950           10 $6,800 -----------                238, 000
5.   Chippewa Harbor, Isle Royale, Mich. 1.                 1950                 1,300                .          84, 500
6.   Eagle Harbor, Mich. 13                                 1945               93,000            $8, 993      j 105,000
7.   Knife River Harbor, Minn.'           _ -               1953      --------------------------                 38,000
8.   Lac La Belle Harbor, Mich------------------            1949       -_--                                     156,000
9.   Little Lake Harbor, Mich.
                            2    3             _             1945 --   ----------------------                    248,000
10.   Lutsen Harbor, Minn.    _ -                   - .      1945--                                             *328,800
11.   Whitefish Point Harbor, Mich-...             -         1951              8,920--------------               356,100


    1 Channels adequate for commerce.
    2 Awaiting local cooperation.
    3 Exclusive of $66,785 to be contributed by local interests.
      4
      Exclusive of $38,875 to be contributed by local interests.
    5 Exclusive of $27,850 to be contributed by local interests.
    6 Exclusive of $38,190 to be contributed by local interests.
    ? Exclusive of $38,000 to be contributed by local interests.
    8 Exclusive of $57,670 to be contributed by local interests.
      9
      Modificationof project now before Congress.
  1 o Amount contributed by local interests.
  11 Revised in 1954.
    s Exclusive of $23,200 to be contributed by local interests.
   13 Assurances of local cooperation approved on Mar. 22, 1948.


                              14. GENERAL INVESTIGATIONS
      Funds appropriated during fiscal year 1954 for .general investi-
gations were allotted to the Milwaukee District by the Chief of En-
gineers for performing this portion of the Duluth District work.

      15. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
  Snagging and clearing of navigable streams and tributaries in
the interests of flood control. (Section 13 of the 1946 Flood Con-
trol Act.)
  A contract awarded in fiscal year 1953 for snagging and clearing
a 3-mile section of North Fish Creek, Bayfield County, Wisconsin,
was completed. The total costs for the fiscal year were $919.92.
The total cost, all new work, was $28,106.
                                        Cost and financial summary

                                               Fiscal year ending June 30                              Total to June
                                                                                                      30, 1954; includ-
                                                                                                      Ing fiscal years
                                 1950         1951           1952          1953            1954         priorto 1950

New work:
   Appropriated                   $ 106              -$10,                      000 -                           $28,106
   Cost--......-.-                 7,-500-                                    9,080           $920               28,106



  Small flood control projects not specifically authorized by Con-
gress. (Section              212
                     of the 1950 Flood Control Act.)
  Pursuant to the above authorization, the small flood control
project at Bayfield, Wisconsin, was approved. The authorized
project provides for an inlet structure, steel culvert, open concrete
                    FLOOD CONTROL-DULUTH, MINN., DISTRICT                              1051
flume and outfall structure to protect the city of Bayfield by di-
verting the flow in Ball Park Creek. The estimated cost is $207,-
000.
   Formal assurances have been given that the items of local co-
operation as required by Section 205 of the Flood Control Act of
1948, as amended, will be furnished by local interests.
   The design memorandum and accompanying maps were com-
pleted on September 15, 1953, and approved by the Chief of En-
gineers on March 12, 1954. Plans and specifications for the pro-
posed structures were completed on June 17, 1954. The total costs,
all for new work, were $7,893.
   The work remaining to be done consists of awarding the con-
tract for the construction. The total estimated cost of construc-
tion is $207,000 of which $147,800 is to be assumed by the Federal
Government and $59,200 by local interests. The total costs, all for
new work, were $7,893.
                                     Cost and financial summary

                                              Fiscal year ending June 30




I Operations   and results during fiscal year $7,893, and pending adjustment of $3.
       IMPROVEMENT OF RIVERS AND HARBORS IN THE
               MILWAUKEE, WIS., DISTRICT

      This district comprises eastern Wisconsin, the southern central
portion of the Upper Peninsula of Michigan, the western half of
the Lower, or southern, Peninsula,.. and a small.portion of northern
Indiana, embracing Lake Michigan and its tributary drainage
basins west of the Straits of Mackinac, exclusive of those between
the southern boundary of Wisconsin and the drainage basin of St.
Joseph River, Mich., and Ind.
                                 IMPROVEMENTS

                Navigation                          Navigation-Continued
                                     Page                                        Page
1. Manistique Harbor, Mich .        1053 19. Holland Harbor, Mich-             1092
2. Menominee Harbor and River,           20.  Grand Haven Harbor and
      Mich. and Wis    _             1055        Grand River, Mich              1095
3. Oconto Harbor, Wis_ ......       1057 21. Muskegon Harbor, Mich             1097
4. Green Bay Harbor, Wis . --       1059 22. White Lake Harbor, Mich.._        1099
5. Fox River, Wis________           1061 23., Pentwater Harbor, Mich __        1100
6. Sturgeon Bay and Lake Michi-          24. Ludington Harbor, Mich _          1102
      gan Ship Canal, Wis .....      1066 25. Manistee Harbor, Mich _-          1104
                       -
7. A1 ama Harbor, Wis___            1068 26. PortageLake Harbor of Refuge,
8. Iwaunee Harbor, Wis              1070        IManistee County, Mich         1106
9.   Two Ribers Harbor, Wis_ .      1072 27. Frankfort Harbor, Mich___         1107
10.   Manitowoc Harbor, Wis          1074 28. Leland Harbor, Mich               1109.
11.   Sheboygan Harbor, Wis .        1076 29. Traverse City Harbor, Mich_       1110
12.   Port Washington Harbor, Wis_   1078 30. Charlevoix Harbor, Mich_      _   1111
13.   Milwaukee Harbor, Wis . ---    1080 31. Inactive Navigation Projects -    1113
14.   Racine Harbor, Wis _....       1083
15. Kenosha Harbor, Wis -___         1085                 Flood control
16. St. Joseph Harbor, Mich          1087
17. South Havenl Harbor, Mich___     1089 32.: Generaflinvestigations -
18. Saugatuck. Harbor and Kala-           33. Flood control work under
      ma.6 River, Mich: _            1091        special authorization_   S     1118.


                      1. MANISTIQUE HARBOR, MICH.
      Location. This harbor is on the north shore of Lake Michigan,
about 135 miles noirtheasterly from Green Bay Harbor and 220
miles northerly from Milwaukee.              (See U. S. Lake Survey Chart.
No. 701.)
  Previous projects. Adopted by River and Harbor Act of June
14, -1880. Further details, see page 1933 of Annual Report for
1915 and.page 1422 of Annual Report for 1938.
  Exi     g project. This provides for two breakwaters extend-
ing from the shore on either side of the mouth of the Manistique
River, 1,744 feet and 1,480 feet in length for the east and west
breakwaters, respectively, and for a pier 375 feet long on the west
side at the river mouth. It further provides for an entrance chan-
nel 19 feet deep from that depth in the lake to a point.about 300
feet landward of the harbor entrance, thencQ 18 feet to a point
                                                                       1053
1054           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

about 1,150 feet upstream from the mouth of the river, and thence
18 feet, except where rock is encountered at less depth, for a fur-
ther distance of about 500 feet, with widths of 276 feet at the
breakwater entrance, increasing to 475 feet through the outer
basin, decreasing to 215 feet at the river mouth, thence varying
from 180 feet to 325 feet at the upper limit; the total length of
channel being about 4,100 feet. The breakwaters are formed of
stone-filled piling and timber cribs, capped with concrete super-
structure; the west pier is formed of stone-filled plank cribs.
   The project depth is referred to low water datum for Lake Mich-
igan, which is 578.5 feet above mean tide at New York. The fluc-
tuations of water level are seasonal changes of about one-half foot
above or below the annual mean stage and extreme fluctuations of
a temporary nature, due to wind and barometric pressure, of about
11/2 feet above or below the mean lake level prevailing at the time.
   The estimate of cost for new work (1954) is $715,900, exclusive
of amounts expended on previous projects. The latest (1954) ap-
proved estimate for annual cost of maintenance is $30,500.
   The existing project was authorized by the following River and
Harbor Acts:

    Acts                          Work authorized                                   Documents

Mar. 3, 1905   Breakwaters and outer harbor-----------.-------           H. Doc. 429, 58th Cong., 2d sess.
Mar. 2, 1907   Present location of west breakwater and pier at river     Annual Report, 1908, p. 648, and
                 mouth.                                                    unpublished report of Mar. 13,
                                                                           1908, approved by Secretary of
                                                                           War, Apr. 3, 1908.
May 17, 1950   Present project dimensions of channel-........_._.--    . H. Doc.' 721, 80th Cong., 2d sess.l

1Contains latest   published map.


   Local cooperation. The act of May 17, 1950, provided that re-
sponsible local agencies shall furnish assurances satisfactory to the
Secretary of the Army that they will hold and save the United
States free from damage due to the construction work and the sub-
sequent maintenance thereof. Local interests were notified on July
19,1950, of the required conditions and requested to furnish as-
surances that they will be met. Negotiations for the above assur-
ances are in progress. All prior requirements have been complied
with.
   Terminal facilities. In addition to a car-ferry slip there are 2
coal and building material wharves, 2 fishing wharves, and numer-
ous lumberyard slips. While these facilities are considered fairly
adequate for existing commerce, it is believed that a wharf, with
rail connection and under public control, should be provided.
   Operations and results during fiscal year. Operations consisted
of dredging 31,559 cubic yards of material with hopper dredge for
restoration of project depth at a cost of $22,682. Condition sur-
veys were accomplished at a cost of $3,239. Miscellaneous in-
spections and reports cost $475. A rubble mound shore connection
at the inner end of the east breakwater 200 feet long was con-
structed at a cost of $19,209. All work was performed by hired
labor and use of Government plant except for the construction of
            RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                             1055
the rubble mound shore connection. The total cost was $45,605 for
maintenance.
   Condition at end of fiscal year. The project in effect prior to
the modification of May 17, 1950, was completed in 1917. No work
has been done on the last modification of the project providing for
present dimensions of channel. The construction of the break-
waters inclosing the basin was commenced in May 1911 and com-
pleted in November 1914. Construction of the plank-crib pier was
commenced in May 1909 and completed in October 1909. Dredg-
ing of the channel to 18 feet over practically all the area below the
car-ferry slip was commenced in June 1915 and completed in July
1915. Dredging of the channel above the slip to ledge rock was
commenced in July 1917 and completed in August 1917. The
breakwaters are in generally good condition. The plank-crib pier
is in a very dilapidated condition and should be rebuilt. The con-
trolling depths at low water datum at the close of the fiscal year
were 16.4 feet in the channel through the outer basin to the river
mouth, thence 14.8 feet in the river to about 500 feet above the
car-ferry slip, decreasing to about 11.6 feet along the easterly limit
of the channel opposite the car-ferry slip. The costs under the ex-
isting project were $307,252 for new work and $328,653 for main-
tenance, a total of $635,905.
                                     Cost and financial summary

                                            Fiscal year ending June 30                       Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                              1950         1951         1952         1953         1954       priorto 1950

New work:
   Appropriated _      ,    --                                 -     -                              $311, 207
   Cost __                                                                                         1 311,207
Maintenance:
   Appropriated .......       $19, 000     $30,371         $500     $17, 000     $29, 800            329,597
   Cost-----------------       12, 263      29,614        1'414       1, 665     245,545             328, 593

1 Includes $3,955 for new work for previous projects.
2 Operations and results during fiscal year $45,605 less pending adjustment of $60.
Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project _ _----------_    _        _ $                        $408,600
        2. MENOMINEE HARBOR AND RIVER, MICH., AND WIS.
   Location. On the west shore of Green Bay, distant about 49
miles northeasterly from Green Bay Harbor, and about 155 miles
from Milwaukee via Sturgeon Bay Canal. (See U. S. Lake Survey
Chart No. 723.)
  Previous projects. Prior to 1902 the harbor and river consti-
tuted two works.
   Harbor: River and Harbor Acts of March 3, 1871, September
19, 1890, and March 3, 1899.
   River: River and Harbor Acts of September 19, 1890, July 13,
1892, and June 3, 1896.
   For further details see page 1933 of Annual Report for 1915 and
page 1424 of Annual Report for 1938.
   Existing project. This provides for protecting the mouth of the
river by parallel piers 400 feet apart and about 1,870 and 2,681
feet in length for the north and south piers, respectively; for a
channel 21 feet deen from that depth in the bav to the upper end



      Sig 34--1055-1086
1056              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

of the Marinette municipal wharf, about 4,700 feet above the Og-
den Street Bridge, and 10,700 feet from the outer end in the bay
where the width is 600 feet, reducing to 300 feet between the
piers and up to Ogdon Street Bridge, thence 200 feet in the river
to the upper end of the municipal wharf, with an enlarged turn-
ing basin 21 feet deep on the south side of the channel just below
that wharf, and for a channel 12 feet deep and generally 90
feet wide upstream from the upper end of the municipal wharf
for a distance of 2,500 feet to the vicinity of the Marinette Yacht
Club. Except for 168 feet of concrete caissons at outer end of
south pier, the piers are formed of stone-filled piling and timber
cribs, the entire north pier and 2,156 feet of the south pier having
been repaired with concrete superstructure.
   The project depths are referred to low water datum for Lake
Michigan, which is 578.5 feet above mean tide at New York. The
fluctuations of water level are seasonal changes of about one-half
foot above or below the annual mean stage, and extreme fluctu-
ations of a temporary nature, due to wind and barometric pres-
sures, of about 11/2 feet above or below the mean lake level prevail-
ing at the time.
   The cost for new work was $149,505 exclusive of amounts ex-
pended on previous projects. The latest (1954) approved estimate
for annual cost of maintenance is $26,000.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                         Work authorized                                   Documents

Mar. 3, 1871      Entrance piers 1 ___--........................._         Annual Report, 1867, p. 132.
June 13, 1902     Consolidation of the project for the harbor and river,   H. Doc. 419, 56th Cong., 1st sess.
                    and for a channel 18 feet deep.
Mar. 4, 1913      Partial restoration of the work above the bridge which
                    had been eliminated by the act of Mar. 3, 1905.
July    3, 1930   For 20-foot depth in the channel and 18-foot depth in    H. Doc. 171, 70th Cong., 1st sess.
                    the turning basin.
Aug. 30, 1935     For 21-foot depth in the channel and the turning basin   Rivers and Harbors Committee
                    and enlargement of the turning basin.                    Doc. 28, 73d Cong., 2d sess.   2
Mar. 2, 1945      For extending channel 12 feet deep, to vicinity of       H. Doc. 228, 76th Cong., 1st sess.
                    Marinette Yacht Club.


  1 Completed under previous projects.
  2 Contains latest published map.


   Local cooperation. Fully complied with.
   Terminal facilities. In addition to a car-ferry slip, there are
numerous wharves for handling coal, building materials, and mis-
cellaneous commodities. The city of Marinette has provided a
public wharf. The facilities are considered fairly adequate for ex-
isting commerce, except that there is need for a public wharf
owned by the city of Menominee, with warehouse and railway
connection.
   Operations and results during fiscal year. Condition surveys
were made at a cost of $5,018. Miscellaneous inspections and re-
ports cost $258. The preparation of plans and specifications for
reconstruction of 612 feet of south pier cost $5,914 and outer end
of north pier cost $3,366. All work was performed by hired labor
and use of Government plant. The total cost was $14,556.
            RIVERS AND HARBORS-MILWAUKEE,                                                 WIS., DISTRICT               1057
   Condition at end of fiscal year. The project in effect prior to
the modification of March 2, 1945, was completed in 1938. No ad-
ditional work is necessary to provide a depth of 12 feet in the ex-
tension of the channel to the vicinity of the Marinette Yacht Club
as project depth or more is now available. The entrance piers
were completed in 1884 and are in generally good condition except
for portions of the south pier and the outer end of the north pier
which require repairs. Dredging of the channel below the Mari-
nette municipal wharf and enlarging the turning basin, to existing
project depth, was commenced in May 1938 and completed in No-
vember 1938. The inner 654 feet of the north pier is no longer es-
sential for the preservation of the channel and is therefore main-
tained only for a length of about 1,216 feet.
   The controlling depths at low water datum at the close of the
fiscal year were 21 feet in the channel to the Marinette municipal
wharf and in the turning basin, except in the southerly 140 feet of
the basin, where it shoals to about 8.4 feet along the extreme
southerly limit.
   The channel above the municipal wharf for a distance of 2,500
feet to the vicinity of the Marinette Yacht Club has depths gradu-
ally decreasing from 12 to 7 feet. The river is available for rafting
and logging for about 102 miles above its mouth. The costs under
the existing project were $149,505 for new work and $566,841 for
maintenance, a total of $716,346.
                                         Cost and financial summary

                                                      Fiscal year ending June 30                               Total to June
                                                                                                               30, 1954, includ-
                                                                                                               ing fiscal years
                                 1950               1951               1952             1953        1954        priorto 19501

New work:
   Appropriated_---      ---------- ...----------------------------------------------                                  $461,928
   Cost---------------------...............-----------------------------------------------                              461,928
Maintenance:
   Appropriated .....-            $4, 000           $10, 889            $3, 500         $13, 500   $211, 200            801, 554
   Cost ............               6,302             11,023              3, 437          11,688     213, 675            602,154


1 Includes $312,423 for new work and $36,194 for maintenance for previous projects.
   Operations and results during fiscal year $14,556, less pending adjustment of $881.

                                    3. OCONTO HARBOR, WIS.
  Location. On the west shore of Green Bay, distant about 31
miles northeasterly from Green Bay Harbor, Wis., and about 25
miles southwesterly from Menominee Harbor, Mich., and Wis., at
the mouth of Oconto River. (See U. S. Lake Survey Chart No.
703.)
  Previous projects. Adopted by River and Harbor Act of Au-
gust 2, 1882. A modification of this project was approved by the
Chief of Engineers March 11, 1897. For further details see page
1934 of Annual Report for 1915 and page 1427 of Annual Report
for 1938.
  Existing project. This provides for protecting the river mouth
by parallel piers 140 feet apart extending from the shore line on
either side of the Oconto River, 1,350 and 2,200 feet in length for
the north and south piers, respectively, and for a channel 15 feet
1058            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

deep at low water datum from that depth in the bay up the river, a
distance of 800 feet above its mouth to the upper end of the turning
basin, a total length of 3,800 feet, varying in width from the 150
feet at the outer end, increasing to 300 feet near the outer end of
the south pier, reducing to 100 feet between the piers and enlarg-
ing to 375 feet in the turning basin. The piers are formed of slab-
and stone-filled piling, about 70 feet of the outer end of the south
pier having been capped with concrete superstructure.
   The project depth is referred to low water datum for Lake
Michigan which is 578.5 feet above mean tide at New York. The
fluctuations of water level are seasonal changes of about one-half
foot above or below the annual mean stage and extreme fluctua-
tions of a temporary nature due to wind and barometric pressure,
of about 11/2 feet above or below the mean lake level prevailing at
the time.
   The cost for new work for the completed project was $46,185,
exclusive of amounts expended under previous projects. The lat-
est (1954) approved estimate for annual cost of maintenance is
$3,000. The existing project was authorized by the following River
and Harbor Acts:

    Acts                          Work authorized                                        Documents

Aug. 2, 1882    Piers, except for inner 300 feet of south pier and 250   Annual Report, 1881, p. 2066.
                 feet of north pier built by city.'
June 25, 1910   Present project dimensions of channel and turning        H.    Doc. 538, 61st Cong., 2d sess.
                 basin.                                                       Plan C.2

1 Completed under previous projects.
2 Contains latest published map.

   Local cooperation. Fully complied with.
   Terminal facilities. These consist of 2 municipally owned
wharves of 400- and 100-foot frontage, respectively, for miscel-
laneous freight, which are open to general public use. The facili-
ties are considered adequate for existing commerce.
   Operations and results during fiscal year. Operations consisted
of commencing the preparation of plans for the reconstruction of
the outer 70 feet of the south pier at a cost of $103. Condition sur-
veys were made at a cost of $719. All work was performed by
hired labor and use of Government plant at a total cost for main-
tenance of $822.
   Condition at end of fiscal year. The existing project was com-
pleted in 1912. The piers were completed in 1885. Dredging of
the channel and turning basin to existing project depth was com-
menced in July 1911 and completed in May 1912. The north pier is
washed out. The south pier is in poor condition. The controlling
depths at low water datum at the close of the fiscal year were 7.2
feet in the entrance channel and 3.5 feet over a width of about 80
feet on the north side of the turning basin along the municipal
wharf. The river is available for logging and rafting for a dis-
tance of about 50 miles above its mouth. The costs under the ex-
isting project were $46,185 for new work and $40,945 for main-
tenance, a total of $87,130.
              RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                                   1059
                                         Cost and financial summary

                                                  Fiscal year ending June 30                         Total to June
                                             S.                                                      30, 1954, includ-
                                                                                                     ing fiscal years
                                  1950        1951                  1952   1953          1954          prior to 19501


New work:
   Appropriated-------- ------------ ------------ --------------                    ------      ..           $130,754
    Cost         ---       ---     -------    -------------------                                             130,754
Maintenance:
    Appropriated .-.--             -$500           $419                      $800            $600              49,674
             .
    Cost----------------              711           831      -----------        9             822              49,106

  ' Includes $84,569 for new work and $8,161 for maintenance for previous project.


                                 4. GREEN BAY HARBOR, WIS.
   Location. Located at the mouth of the Fox River, at the head of
Green Bay, distant about 180 miles from Milwaukee, Wis., via
Sturgeon Bay Canal, and about_ 49 miles southwesterly from Men-
ominee Harbor, Mich., and Wis. (See U. S. Lake Survey Chart No.
725.)
   Previous projects. Adopted by River and Harbor Act of June
23, 1866. This project was modified by the River and Harbor Acts
of June;23, 1874; July 13, 1892; and June 3, 1896. For further
details see page 1934 of Annual Report of 1915 and page 1431,
Annual Report of 1938.
   Existing project. This provides for an outer channel in Green
Bay about 10 miles long and 22 feet deep, from that depth in the
bay at the mouth of Fox River, varying in width from 500 feet at
the outer end to 300 feet at the river mouth, including widening of
the bend outside of Tail Point Light; for protecting the portion
through Grassy Island, about 700 feet long, on the east side by a
stone-filled timber pile revetment capped with concrete superstruc-
ture; for straightening the channel from the inner end of Grassy
Island to the river mouth; for widening the channel in Fox River
through the city of Green Bay by the removal of shoals at the
mouth of East River and between the two upper railroad bridges to
a depth of 22 feet; for a turning basin 22 feet deep at the mouth of
East River; for a turning basin 20 feet deep above the Chicago
& North Western Railway bridge near the southern limits of the
city of Green Bay; for an inner channel in the river 150 feet wide
and 18 feet deep extending upstream about 31/2 miles from the
latter turning basin to De Pere, terminating in another turning
basin 18 feet deep with sufficient area to accommodate 500-foot
vessels.
   The project depths are referred to low water datum for Lake
Michigan, which is 578.5 feet above mean tide at New York. The
fluctuations of water level are seasonal changes of about one-half
foot above or below the annual mean stage and extreme fluctu-
ations of a temporary nature, due to wind and barometric pressure,
of about 21/ feet above or below the mean lake level prevailing at
the time.
   The estimate of cost for new work for the entire project (1954)
is $1,780,000, exclusive of amounts expended on previous projects
and excluding $70,000 contributed and $30,000 to be contributed
 1060            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

by local interests. The latest (1954) approved estimate for an-
nual cost of maintenance for the entire project is $50,000.
   The existing project was authorized by the following River and
Harbor Acts:

     Acts                         Work authorized                                  Documents


June 23, 1866    Outer channel and revetment at Grassy Island   1.      Annual Report, 1867, p. 70.
July 13, 1892    Inner channel 1__................................      Unpublished report approved Aug.
                                                                          3, 1892.
June 25, 1910                                        ___
                 Turning basin at De Pere-..__ ... ....      . ___
                                                               -_-
                                                                        H . Doc. 522, 61st Cong., 2d sess.
                                                                        H. Doc. 1017, 64th Cong., 1st sess.2
Aug. 8, 1917     Maintenance of the turning basin at De Pere _
Mar. 3, 1925     Increasing depth of inner channel and turning basin    H. Doc. 294, 68th Cong., 1st sess.
                  to 18 feet.
Aug. 30, 19353   Deepening outer channel to 22 feet with widening       Rivers and Harbors Committee    2
                  and straightening inside of Tail Point Bend, widen-     Doc. 40, 72d Cong., 1st sess.
                  ing the channel in Fox River through the city of
                  Green Bay to a depth of 22 feet.
Aug. 26, 1937    Turning basin above the Chicago & North Western        Rivers and Harbors Committee
                  Ry. bridge.                                             Doc. 73, 74th Cong., 2d sess.s
                                                                                                       2
Mar. 2, 1945     Turning basin at mouth of East River                  H. Doc. 95, 76th Cong., 1st sess.
                                                                .-------------

I Completed under previous projects.
2 Contain latest published maps.
3 Included in the Public Works Administration program, Jan. 3, 1934.



   Local cooperation. The act of March 2, 1945, provided that
local interests furnish, free of cost to the United States, all lands,
easements, and righas-of-way and spoil disposal areas for the ini-
tial work and for subsequent maintenance as required and contrib-
ute $30,000 toward the cost of dredging the turning basin at the
mouth of East River. Assurances of local cooperation were fur-
nished by the city of Green Bay and were approved by the Chief
of Engineers on December 6, 1950.
   All prior requirements have been complied with.
   Terminal facilities. There are numerous wharves for the han-
dling of coal, petroleum products, grain, pulpwood, wood pulp,
sulpher, cement, building materials, and miscellaneous commodities
located on this waterway. Green Bay has provided a municipal
wharf open to the public. These facilities are considered ade-
quate for existing commerce.
  Operationsand results during fiscal year. Operations consisted
of dredging 115,220 cubic yards of material with dipper dredge
for restoration of project depth at a cost of $51,542. Condition
surveys were made at a cost of $6,540. Miscellaneous inspections
and reports cost $847. All work was performed by hired labor
and use of Government plant. The total cost for maintenance was
$58,929.
   Condition at end of fiscal year. The project in effect prior to
the modification of March 2, 1945, was completed in 1938. No
work has been done on the last modification of the project pro-
viding for a turning basin at the mouth of East River. Deepen-
ing and widening the outer channel in Green Bay, to existing
project depth and width, was commenced in August 1934 and com-
pleted in November 1936. Dredging the channel in Fox River
through the city of Green Bay was commenced in May 1935 and
completed in November 1935. Dredging the turning basin above
the Chicago& North Western Railway bridge was commenced in
August 1938 and completed in September 1938. Dredging the
             RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                                              1061
inner channel and turning basin to existing project depth was
commenced in June 1926 and completed in October 1926. The
east revetmet at Grassy Island, built in 1869, is in generally good
condition. The west revetment was entirely removed in July
1935. The controlling depth at low water datum at the close of
the fiscal year was 19.6 feet in the outer channel and 22 feet in
the channel through the city of Green Bay, 18.7 feet in turning
basin above railway bridge, 13.3 feet in the inner channel, and 18
feet in the turning basin at De Pere except for some shoaling at
upper end. The head of deepwater navigation is at De Pere.
   The costs under the existing project were as follows:

                                                                        New work             Maintenance             Total


Regular funds -__                                                           $   667, 917        $1, 053, 710         $1, 721, 627
Public Works funds-__             -           -                                 940, 800                                 940, 800

     Total ..................---------------------------------------         1,608, 717          1,053,710            2,662,427



  In addition $70,000 contributed funds were expended on new
work.
                                         Cost and financial summary

                                                      Fiscal year ending June 30                          Total to June
                                                  ----
                                                   -___._--       -    ___ __--~                __ __~_ !30, 1954, includ-
                                                                                                               ing fiscal years
                                  1950            1951           1952              1953           1954          prior to 19501

New work:
   Appropriated                                                                                                    2 $2, 005, 691
   Cost$                                                                                                            22,005, 691
Maintenance:
   Appropriated                   $65,500         $42, 500       $63, 400         $58, 500       $58, 900             1, 062, 824
   Cost_        -                  71,012          43,185         62,777           58,237         58,929              1,062,628

1 Includes $396,974 for new work and $8,918 for maintenance for previous projects.
2 In addition $70,000 for new work was expended from contributed funds.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project  __                           $171,300

                                            5. FOX RIVER, WIS.
   Location. This river rises in Columbia County, Wis., and flows
in a northerly direction into Green Bay. Its length is about 176
miles. The Wolf River, physically the main river but by designa-
tion a tributary of the Fox, rises in the central part of Forest
County, Wis., and flows in a southerly direction about 220 miles
into the Fox River 10 miles above Oshkosh. (See U. S. Lake
Survey Chart No. 726 for Lake Winnebago and lower Fox River.)
   Previous projects. As provided by special act of July 7, 1870,
and River and Harbor Act of June 10, 1872, the original project
was modified by the River and Harbor Act of March 3, 1873.
   The improvement of the Wisconsin River was abandoned in
1887 (Annual Report for 1887, p. 2096). For further details see
page 1940 of Annual Report for 1915 and page 1434 of Annual
Report for 1938.
  Existing project. This provides for deepening and widening
the channel of Fox River from De Pere, 7 miles above the mouth,
1062              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

to Portage, Wis., a total length of 156 miles, the depth between
De Pere and Montello, 125 miles, to be 6 feet, with 9.6 feet in rock
cut below De Pere lock and 7 feet in other rock cuts on the lower
river below Menasha lock; and from Montello to Portage, 31
miles, the depth to be 4 feet; the width of channel from Lake Win-
nebago to Montello to be 100 feet, with necessary widening at
bends; for the construction and reconstruction of 27 locks and 16
dams; for a concrete retaining wall at Kaukauna; for construction
and maintenance of harbors having depths of 6 feet on Lake Win-
nebago; for widening Neenah Channel to 100 feet, with a 6-foot
depth for a length of about 1 mile; and for dredging, snagging,
and otherwise improving Wolf River from its mouth to New Lon-
don, a distance of 47 miles, the depth to be 4 feet. All depths are
referred to standard low water.
   Ordinary and extreme fluctuations of water level above and be-
low mean stages on various parts of the improvement, due to floods
and other causes, are about as follows:

                                                      Ordinary fluctuations              Extreme fluctuations

                       Place
                                                    Above mean         Below mean Above mean        Below mean
                                                    stage (feet)       stage (feet) stage (feet)    stage (feet)
                                                I                  I                 I

Lower Fox River at De Pere Dam_ __                          1.0                1.4            2.5               4.0
Lake Winnebago ___________...._....___                      1.2                1.3            2.2               3.7
Upper Fox River at Berlin Dam_                              2.7                1.4            5.7               2.0
Wolf River at New London-_----.----                         5.0                2.6            8.8               3.0



   The estimated cost of new work (1954) is 2,958,300 for the up-
per river and $799,400 for the lower river; a total of $3,757,700
exclusive of the amounts expended on previous projects. The latest
 (1954) approved estimate for annual cost of maintenance is $20,-
000 for the upper river, if project dimensiosn are once fully ob-
tained and $110,000 for the lower river; a total of $130,000. The
latest (1954) estimate of annual cost of operation and care of the
locks and dams is $250,000.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                       Work authorized                                        Documents


Aug.    5, 1886    Improvement of Fox River                         Annual Report, 1885, pp. 2041-2045
                                                                                         t
                                                                      (plan of board approved Dec.
                                                                     10, 1884, as modified by Corps of
                                                                     Engineers, May 14, 1886).
Sept. 19, 1890    Dredging Fond du Lac Harbor on Lake Winnebago__ H. Ex. Doec. 24, 51st Cong., 1st sess.
                                                                     Annual Report, 1890, p. 2390.
June 3, 1896      Improvement of Wolf River________ _________       No prior survey or estimate.
   Do ......      Improvement of Stockbridge, of Calumet and Miller                Do.
June 13, 1902     Bay, and of Brothertown Harbors, on Lake Winne-
Mar. 2, 1907      bago.
Mar. 3, 1925    Increased depth in rock cuts on lower river, widening        H. Doe. 294, 68th Cong., 1st sess.
                  Neenah Channel, and for a concrete retaining wall
                  at Kaukauna.
June 26, 1934 1 Operation and care of locks and dams provided for
                  with funds from War Department appropriations
                  for rivers and harbors.

  1Permanent Appropriations Repeal Act.
The latest published maps are contained in H. Doc. 146, 67th Cong., 2d sess., and in H. Doc. 294, 68th
Cong., 1st sess.
                                                                                   Locks and dams, Fox River, Wis.

                                                                                                             Depth at nor-
                                        Dis-                                                                   mal pool
                                       tance                             Dis-   Clear   val-Character                                                                                             Date of
                                                                                Clear
                                                                         NameoockordatDus-
                                                                                        vlal
     Name of lock or dam               fromn      Nearest town           tance width   able       Lift                                f found       Kin of        Type of construction            omple-        Actual
                                      Green                                           length     (feet)     Breast     Lower                         dam                                                         cost
                                        Bay                             (miles) (eet)  (feet)               wall I     miter             tion                                                       tion
                                      (miles)                                                                (feet)     sill
                                                                                                                       (feet)

De Pere lock 2_________________             7.1 De Pere....... ........ 36.0    146.0     8.9                  10.3      12.0         Rock...---          _ .. Concfete             -------.............. 1936 $229,307.79
De Pere Dam 2________________.............. 7.2     do--------             -                                                     .do       ....Fixed 3 4 ..-         do-....----------                    1929   209,536.08
Little Kaukauna lock 2 ......              13.0                          36.0
                                                                    6.....      146.0     7.2                   8.0      9.5      Clay -....        -------- S.le ado-                                    1938
                                                                                                                                                                                           .....------------     362,426.81
Little Kaukauna Dam 2.......               13.1 .....
                                                    do......        6 .......................              . ..............       Clay and Fixed 3 4__ Piles and concrete-                                1926    179,397.62
Rapide Croche lock 2_.........
                           2              19.2    Wrightstown_.              2    36.0    146.0     8.3         8.8       9.3
                                                                                                                                    gravel.
                                                                                                                                  Rock ...                      Concrete-----........-----...             1934    228, 738. 33   zM
Rapide Croche Dam2 _____..._              19.3   .....do........             2                                                  ---do..... Fixed 34. _ .....do                 ----..........--------     1930    118,975.40
Kaukauna fifth lock _________..........
                              2           22.8    Kaukauna....                    35.6    144.0     9.1         6.7       7.4   .-.do......                     Composite---....------                    1898   513.309.90      00
Kaukauna fourth lock2 ........            23.1       do_..._...
                                                 .....                            36.6    144.1    10.2         6.9       6.0   ___do......                     Stone masonry .......                     1879     37,536.37
Kaukauna third lock .........             23.3   -....do-.......                  30.6    144.0    10.2         6.9       6.3                                  .....       _ .
                                                                                                                                                                     do. _...             ..              1879     39,948.41
Kaukauna second lock      2    2.......   23.4   .....
                                                     do.......                    35.0    144.0     9.6         6.0       6.0   ... do.- --                    ---- do---------------                     1903     24,312.77
Kaukauna first lock2      s ..........    23.6   .....do.........                 35.1    144.4    11.0         6.9       6.0   ...do ...                            do.............-----------
                                                                                                                                                               .....----                                  1883     38, 703.52
Kauhauna Dam ..............               24.0        do.........
                                                  --..--                                                                        ___do_.......
                                                                                                                                ---     do--.----               Concrete--.....---                        1931    123,763.41
Kaukauna guard lock--.........            24.0   .....do........                   40.0                         9.4             --.do ...                       Stone   masonry-__            ....-       1891     12,630.30
Little Chute combind lock:                                                                                                      _.do.......
    Lower 22--........---.-.....          25.4    Little Chute --            1     35.4   146.5    10.9         6.0       8.6    . do ... ...                    ---.....
                                                                                                                                                                     do-....-------                       1879
                                                                                                                                                                                                                }102,303.82
    Upper ----------              2       25.4   .....do.........            1     36.3   144.1    10.6         7.6       6.0     Hardpan - Fixed 34__. ----.....do------.            ------              1879
Little Chute second lock s....            26.4   .....    do.........              35.0   144.2    13.8         8.0       6.2     RockSand......               ------do                                   1881     48,555.36     C
Little Chute first (guard) lock 2         26.5   -...-
                                                    do.........                    35.4                         6.6                                            ..... do. _---- ---              ---       1904     5 7,816.56    M
Little Chute Dam 2-.........              26.6   .....
                                                     do.........                                                                  Eartdo.....                   Concrete-.......              -           1932     82, 533.74    W




Cedars lock 2-_-_--_ ------ _ ...         27.3       do---------
                                                 -----                       1                                            7.3
                                                    ---   do-........              35.0   144.0      9.8        6.8               Claydo----      Fixed __. Stone masorry- .. __-
                                                                                                                                                 -----------                                              1888     34,972.19
Cedars Dam 2__-_-_-_-_--                _ 27.4                               1                                                    Eardoth.....           3
                                                                                                                                                                 Concrete___       _____                  1933     84,872.55
Appleton fourth lock22........            30.7     Appleton......            1     35.0   144.0      7.6        8.1       7.9   __do .. ... Fixed 4_. Stone masonry-.......                               1907      40,892.55
Appleton lower dam .........              30.9   -...do-.........                                                                ___do-......                    Concrete-.....-----                 - 1934         73,902.53
Appleton third lock 2_2 --- ...           31.3       do_ ....
                                                 .....                             35.0   144.0      8.7        6.0       8.6   --- do-......                   Stone masonry-.......
                                                                                                                                                  Fixed 3 ... ..----
                                                                                                                                                                                                          1909      32,238.39        0
Appleton second lock - -........          31.6   .....    do.......                35.1   144.6      9.6        6.9       6.0     Clay ......                         do................------------      1901      22, 939.54
Appleton first lock 2...........
Appleton upper dam------....
Menasha lock 2----........-.-.
                                          31.9
                                          32.2
                                          37.0
                                                 .....
                                                     do......
                                                 .....
                                                     do .....
                                                  Menasha_ .
                                                                                   35.0

                                                                                   35.4
                                                                                          144.7

                                                                                           144.0
                                                                                                    10.0
                                                                                                     8.5
                                                                                                                6.6
                                                                                                                7.2
                                                                                                                          6.0

                                                                                                                          8.0
                                                                                                                                  Rockth.....
                                                                                                                                   _do------
                                                                                                                                  Clay-.....
                                                                                                                                                  Fixed 34... .....   do--................----------
                                                                                                                                                                 Concrete----------..............
                                                                                                                                                                 Composite ---------............ 1899
                                                                                                                                                                                                          1884
                                                                                                                                                                                                          1940
                                                                                                                                                                                                                   36,004.48
                                                                                                                                                                                                                  151,558.40
                                                                                                                                                                                                                 5 19,326.46
                                                                                                                                                                                                                                     8
                                                                                                                                                                                                                                     0
                                                                                                                                                                                                                                     H
Menasha Dam 2_____________                37.8   .....
                                                     do ........                                                                  Hardpan.- Fixed 3.... Concrete---------                                 1937      84,686.04        0
Eureka lock .................             81.0    Eureka ......              2     35.0    148.6     2. O       7. 9     10.1     Sand_....                      Stone masonry and                        1876      51,127.51
                                                                                                                                                                   concrete.                                                         O
Eureka Dam-------------.....          81.2     do _.                                 -....                                        Earth_:__.                     Timber and plank ...                     1877      10,276.15
Berlin lock-- ...                     89.3  Berlin......                           34.8   148.6      1.3                  9.2     Clay ....                      Stone masonry--..-----                    1878     44,370.98
Berlin Dam-                 .................
                                      89.4 .....
                                               do......                                                                           Earth ....                     Timber cribs-------..........             1894     14,747.14        CD
White River lock...-.........         99.3 Princeton ...                           34.5   148.5      1.9                 10.7     Clay .....                     Stone masonry-........                    1878     58,709.94
White River Dam...-----...            99.2 --...
                                               do.........                                                                        Earth .....                    Timber cribs-.........                    1895     17,285.64
  See footnotes]at endjof table.
                                                                                       Locks and dams, Fox River, Wis.-Continued
                                                                                                                                                               i                 i                                i
                                                                                                                            Depth at nor-
                                                Dis-                                                                          mal pool
                                               tance                                         Clear    Avail-                                                                                                       Date of
       Name of lock or dam                     from       Nearest town              tDis-              able       Lift                           Character          Kind of                                                   Actual
                                                                                    tance    width                                               of founda-                          Type of construction         comple-
                                              Green                                (miles)   (feet)   length     (feet)    Breast     Lower          tion            dam                                            tion       cost
                                                Bay                                                    (feet)              wall 1     miter
                                              (miles)                                                                       (feet)      sill                                                                                                 M

                                                                                                                                       (feet)
                                                                                                                                                                                                                                             O

Princeton lock.................                 108.6 Princeton.....               3      34.9            148.4          1.5      7. 3    9.5 Sand----             -----------    Stone masonry.          __-         1878   $51, 577. 84    y
Princeton Dam                                   108.6 .....- do---......---
                                ----................                               3 ----------                     ------------------------... do......            Fixed __..    Timber cribs..                      1898    11, 265.69
Grand River lock----............----.           129.2 Montello......               3      34.7            148.3          1.4      6.4     9.8 Clay.------__------___            - Stone masonry         ___           1878    56,989.43      C2

Grand River Dam-----.........---....             129.2 -....-- do......------...   3 ...................................                          Clay and          Fixed 3 ' ._ Timber cribs-..--___.                1898     8, 446.86
                                                                                                                                                     sand.
Montello lock' ---            .                132.5      ..... do--...........-..        35.3            137.0          3.8      4.8     5.7 Sand                 ...-
                                                                                                                                                                ___....           Composite _________                 1901    5 4,889.83
Montello Dam 2
                                                                                                                                                                                                                                             M



                     _                         132.6     -..... do...--------- ----           ----                                       _____-- .----------..-
                                                                                                                                                     do...__..Fixed 4..           Timber cribs ........               1933    5 6,772.55
Governor Bend lock --..........                156.7       Portage.......          6      35.0            137.0          3.8    6 7.0     5.2 _..do._____-----              ----- do......-----------                 1931   5 30,825.38     0




Governor Bend Dam 2.........                   156.7      -..... do....-----       6 ------------------------------..........                       do ..           Fixed--__      ..
                                                                                                                                                                                  __do__ ------                       1865       (7)
Fort Winnebago lock _____.........             160.9      ..... do.....--------.   2      34.7            137.0          6.4      5.8     5.6 Clay-----_   ...--                  Composite- ...-....
                                                                                                                                                                            -______                     _     _       1936    521, 515. 46   M




Portage lock .-----                            163.1     ____do.........-----........     35.2            146.0          2.3     10.5     8. 2 Sand....--------------Concrete....                   ..                1928    179, 604.83    z




  1 Depth shown in on breast wall, which is controlling depth for upper pool.                                                  5 Partially rebuilt.                                                                                          W




 : Original structure built prior to assumption of control by the United States on                                             6 Depth shown is on upper sill, which is controlling depth.
Sept. 18, 1872.                                                                                                                * Unknown.
  ' Provided with sluices.
  ' Flash boards used.

                                                                                                                                                                                                                                             !"




                                                                                                                                                                                                                                                  1;1


                                                                                                                                                                                                                                                  il
             RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                         1065
   Recommended modifications of project. Legislation authoriz-
ing the abandonment of that part of the improvement of Wolf
River above Fremont and the upper Fox River from the mouth
of the Wolf to the Wisconsin River has been recommended in House
Document No. 146, 67th Congress, 2d session.
   Local cooperation. None required.
   Terminal facilities. The wharf and landing facilities are, in
general, adequate for the accommodation of existing commerce.
   Operations and results during fiscal year. Condition surveys
were .made at a cost of $3,352 and miscellaneous inspections and
reports cost $2,196. Supervision and inspection cost $11,120; lock
operations, $104,199, ordinary repairs to locks and dams, $13,048;
maintenance of buildings and grounds, $16,484.
   The lower gates at Appleton first lock were rebuilt and the sluice
gates at Appleton lower dam and lock gates at DePere lock were
sandblasted and painted; new stop log timbers were provided at
Cedars Lock, Little Kaukauna Lock and Rapid Croche Lock; a
pipe flume was constructed at Kaukauna first lock; at Little Chute
Guard Lock, the gate arms were renewed, all at a cost of $49,991.
New roofs were installed on lockmaster's dwelling at Appleton
second, Little Chute third and Rapid Croche locks, and a new
water supply well was drilled at Rapid Croche lock dwelling, all at
a cost of $3,255. Repairs to canal banks from DePere to Menasha
were made at a cost of $6,071. Dredging of material for the re-
moval of shoals along the river channel between DePere and
Menasha cost $4,156. All work was performed by hired labor and
use of Government plant except for the well drilling. The total
cost was $213,872 for operation and maintenance. Rent receipts
during the fiscal year amounted to $5,965, leaving a net cost of
$207,907.
   Condition at end of fiscal year. The existing project is about
44 percent complete (upper river, 25 percent; lower, 83 percent).
Twenty-two original locks and nine original dams have been re-
built; five additional locks and dams have been built by the United
States. (See existing project for year of completion of each.) The
structures and the dredging in pools have increased the original
depths generally about 2 feet. The controlling depths at standard
low water at the close of the fiscal year were as follows:
Fox River:
    De Pere to mouth of Wolf River ----------------------------------------                            6.0O
    Thence to Eureka lock-.......................................                                      3.2
Wolf River:
    Mouth to 1 mile below Partridge Crop Lake                        -...........                      3.5
    Thence to New London ................                 ..........     .      ... ..                 2.0
Harbors on Lake Winnebago                .......------------------------               ----------- 1.0-3.0
  The practicable drafts of vessels are aboue one-half foot less
than the controlling depths which prevail throughout the year ex-
cept when the rivers are frozen, usually from December 1 to April
1. As commerce no longer existed on the upper Fox River from
the Wolf River to the Wisconsin' River, Federal expenditures for
continuing the operation of the nine locks on this portoin of the
project were no longer justified. Accordingly the operation of
these structures was discontinued in July 1951. The work remain-
ing to be done to complete the project is dredging in the upper Fox
1066                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

River and the upper portion of the Wolf River and rock removal
and deepening Neenah Channel on lower Fox River; which are no
longer considered necessary. Except for Menasha lock, which
should be rebuilt, the existing locks and dams are in generally fair
to good condition. The costs under the existing project were
$871,724 for new work and $5,971,012 for operation and main-
tenance, a total of $6,842,736. In addition, the sum of $3,795,495.53
 (including $89,309.40 under previous projects) was expended be-
tween July 5, 1884, and June 30, 1935, on the operating and care
of the works of improvement under the provision of the perma-
nent indefinite appropriation for such purposes.
                                          Cost and financialsummary

                                                   Fiscal year ending June 30                           Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                                   1950           1951          1952           1953            1954     priorto 19501


New work:
   Appropriated ........                                             -------------------   -     ---         $4,111, 634
   Cost------          -----------------------------------------------------------                            4,111634
Maintenance :
   Appropriated........          $246,000       $270, 000      $265, 900      $242, 500    $221, 000          9,779, 255
   Cost-.---------------          341,645        297,950        287,861        249,661     2 209,384          9,768,016

1Includes $3,239,910 for new work and $89,309 for maintenance for previous projects.
2 Operations and results during fiscal year $207,907, plus pending adjustment of $1,477.
Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project--_--- - ------------- $2,886,000
    6. STURGEON BAY AND LAKE MICHIGAN SHIP CANAL, WIS.
  Location. This improvement is on the west shore of Lake
Michigan, distant about 52 miles northeasterly from Green Bay
and about 128 miles northerly from Milwaukee. (See U. S. Lake
Survey Chart No. 728.)
  Previous projects. Adopted by River and Harbor Acts of
March 3, 1873, and June 14, 1880. The United States assumed pos-
session of the canal April 25, 1893, as authorized by the River
and Harbor Act of July 13, 1892. The original project for the
canal was adopted by the River and Harbor Act of August 18, 1894,
modified by River and Harbor Act of June 3, 1896. For further
details, see page 1935 of Annual Report for 1915 and page 1441 of
Annual Report for 1938.
  Existing project. This provides for an outer harbor or stilling
basin protected by two converging breakwaters, each 1,344 feet in
length, extending from the shore on either side of the easterly or
Lake Michigan end of the canal; for a revetted canal 7,200 feet in
length, varying in width from 160 to 250 feet; for a channel 23
feet deep in rock cut, extending from that depth in Lake Michi-
gan to about 800 feet west of the east entrance of the revetted
canal, a length of about 0.6 mile; thence a channel 22 feet deep
through an additional 6,400 feet of revetted canal and through
Sturgeon Bay to the vicinity of Sherwood Point, a length of about
8 miles, the total length of channel being about 8.6 miles; the width
of channel being 600 feet in Lake Michigan, reducing to 200 feet
through the harbor and 130 to 220 feet through the revetted canal,
thence 250 feet through Sturgeon Bay to a point 5,400 feet north-
                RIVERS AND HARBORS-MILWAUKEE, IiWIS., DISTRICT                                                    1067
west of the railroad bridge in the city of Sturgeon Bay and thence
500 feet to the vicinity of Sherwood Point; for a;turning basin 20
feet deep, on the southwesterly side of the channel, southeasterly
of the highway bridge, between the city and the Bushman wharves;
and that the turning basin immediately west of the revetted canal
be eliminated from the project. The breakwaters are formed of
stone-filled piling and timber cribs and have been provided with
concrete superstructures; the revetments are formed of timber and
steel piling, 886 feet having been provided with concrete super-
structure.
   The project depth is referred to low water datum for Lake
Michaigan, which is 578.5 feet above mean tide at New York. The
fluctuations of water level are seasonal changes of about one-half
foot above or below the annual mean stage, and extreme. fluctua-
tions of a temporary nature, due to wind and barometric:pressure,
of about 11/2 feet above or below the mean lake level prevailing at
the time.
   The cost for new work for the completed project was $736,303,
exclusive of amounts expended on previous projects. The latest
 (1954) approved estimate for annual cost of maintenance is
$120,000.
   The existing project was authorized by the following River and
Harbor Acts:

     Acts                          Work authorized                                                Documents

Mar. 3, 1873     Breakwaters 1_     -     ___- ..--------
                                        -___                                         H.   Ex. Doc. 34, 42d Cong., 2d sess.
                                                                                     H...............
                                                                                        Annual Report, 1872, p. 171.
July 13, 1892    Acquisition of the canal..            -------------..............   H.    Ex. Doc. 106, 49th Cong., 2d
                                                                                          sess.
June 13, 1902    Canal revetments and consolidation of the canal and                 H. Doc. 117, 56th Cong., 2d sess.
                   harbor works.
Aug. 30, 1935    Present project dimensions of the channels and elimi-               Rivers and Harbors Committee
                   nation of turning basin; immediately west of the                    Doc. 9, 74th Cong., 1st sess.2
                  revetted canal.                                                                                     2
Mar. 2, 1945     Turning basin between the city and the Bushman                      H. Doc. 421, 78th Cong., 2d sess.
                  wharves.

1 Completed under previous projects.
2 Contain latest published maps.

   Local cooperation. Fully complied with.
   Terminal facilities. As the canal and connecting channel is a
through waterway, the only terminal facilities are in the city of
Sturgeon Bay, 4 miles from the west end of the revetted portion of
the canal. These facilities consist of 4 coal wharves, 4 ship-build-
ing yards, and 1 package-freight wharf. The city of Sturgeon Bay
has provided a public wharf. There is also an inactive large stone
wharf located about 5 miles northwesterly from the city of Stur-
geon Bay. The facilities are considered adequate for existing com-
merce.
   Operationsand results during fiscal year. Operations consisted
of dredging 25,250 cubic yards of material with dipper dredge for
restoration of project depth in the canal at a cost of $15,601. Com-
pletion of maintenance dredging with Government hopper dredge
at the harbor entrance, in progress at the close of the previous
fiscal year, cost $210. Condition surveys cost $6,499 and mis-
cellaneous inspections and reports cost $553. The preparatio i of
1068               REPORT OF CHIEF OF ENGINEERS. U. S. ARMY. 1954

plans and specifications for reconstruction of 301 feet of the south
revetment cost $2,191. The reconstruction of 700 feet of the
north revetment, in progress at the close of the previous fiscal year,
was completed at a cost of $35,326. All work was performed by
hired labor and use of Government plant except for the reconstruc-
tion of 700 feet of the north revetment. The total cost was $60,380
for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1946. The breakwaters were completed in 1880, and the
canal revetments in 1903. Dredging and rock removal at the
easterly entrance to the canal and dredging in the westerly section
of the canal, to existing project depth, were commenced in May
1940 and completed in September 1940. Deepening and widening
the middle section of the canal to existing project depth and width
was commenced in May 1942 and completed in August 1942.
Dredging of the turning basin was commenced in June 1946 and
completed in July 1946. The breakwaters are in generally good
condition. The canal revetments require repairs and backfilling.
The controlling depths at low water datum at the close of the fiscal
year were 20.5 feet in the canal and 19.5 feet in the turning basin.
The costs under existing project were $736,303 for new work and
$1,818,958 for maintenance, a total of $2,555,261. In addition,
the sum of $425,259.17 (including $189,319.35 under previous
proiects) was expended between April 25. 1893, and June 30. 1917,
on the operating and care of the works of improvement under the
provision of the permanent indefinite appropriations for such pur-
poses.
                                                     Cost and financial summary

                                                           Fiscal year ending June 30                   Total to June
                                                                                                       30, 1954, includ-

                                             1950         1951        1952
                                                                                  1ing
                                                                                  1953      1954
                                                                                                            fiscal years
                                                                                                         prior to 19501

New work:

   Cost --....------------------------------------                                                            1,059,722
Maintenance :
   Appropriated ..- -             - -      $192, 500     $ 22,020     $4, 000    $168,300   $68, 500          2, 319, 555
   Cost . ..                                116,653       104,426      5,452      131,838   260,369           2,274,617

1 Includes $323,419fornew work and $219,730formaintenance forprevious projects.
2 Operation and results
                       during fiscal           lesspending adjustment
                                   year $60,380,                     of $11.

                                               7. ALGOMA         HARBOR, WIS.
  Location. Algoma Harbor is on the west shore of Lake Michi-
gan, distant about 68 miles from Green Bay via Sturgeon Bay
Canal and about 115 miles northerly from Milwaukee. (See U. S.
Lake Survey Chart No. 703.)
  Previous projects. Adopted by the River and Harbor Act of
March 3, 1871, and modified by River and Harbor Acts of March 3,
1873; March 3, 1875; July 5, 1884; and March 3, 1899. For further
details, see page 1935 of Annual Report for 1915, and page 1445,
Annual Report for 1938.
  Existing project. This provides for an outer harbor 14 feet
deep enclosed by a north pier, 1,102 feet long, extending approxi-
mately normal to the shore, and a south breakwater, 1,530 feet
               RIVERS AND HARBORS-MILWAUKEE,                          WIS., DISTRICT                1069
long, extending from the shore at a point about 1,000 feet south of
the remaining 481 feet of the pier on the south side of the channel
at the mouth of Ahnapee River, and for a channel of same depth as
outer harbor, except where rock is encountered at less depth, ex-
tending from that depth in the lake up the river a distance of 1,000
feet from its mouth, a total length of about 2,100 feet; this channel
varies in width from 175 to 80 feet at Second Street Bridge. The
piers are formed of stone-filled timber cribs and piling and the
breakwater of stone-filled timber cribs, concrete caissons, and pil-
ing. The north pier and south breakwater have been provided with
concrete superstructure.
   The project depth is referred to low water datum for Lake Michi-
gan, which is 578.5 feet above mean tide at New York. The fluctua-
tions of water level are seasonal changes of about one-half foot
above or below the annual mean stage and extreme fluctuations of
a temporary nature, due to wind and barometric pressure, of about
11/2 feet above or below the mean lake level prevailing at the time.
   The cost for new work for the completed project was $99,236,
exclusive of amounts expended on previous projects. The latest
(1954) approved estimate for annual cost of maintenance is
$13,000.
   The existing project was authorized by the following River and
Harbor Acts:

    Acts                         Work authorized                                 Documents

Mar. 3, 1871    North pier or breakwater 1-.   - .__-__....--     .   Annual Report, 1871, p. 126.
Mar. 2, 1907    South breakwater and present project dimensions of    Unpublished        report   submitted
                 channel and basin.                                     Sept. 25, 1907.
                                                                                    2   (No prior survey
                                                                        or estimate. )

  Completed under previous projects.
2 The latest published map is in Annual Report, 1908, p. 1954.


    Local cooperation. None required.
    Terminal facilities. These consist of a coal wharf and several
fishing wharves. The facilities are considered adequate for exist-
ing commerce.
    Operations and results during fiscal year. Condition surveys
by hired labor and use of Government plant were made at a cost
of $1,075 for maintenance.
    Condition at end of fiscal year. The existing project was com-
pleted in 1909. The north pier was completed in 1890, the south
pier and breakwater and dredging in 1909. The north pier and
south breakwater are in generally good condition. The south stub
pier at the river mouth is in a dilapidated condition and should be
rebuilt. The controlling depths at low water datum at the close of
the fiscal year were 14 feet in the entrance channel to the outer
end of south stub pier, decreasing to 11 feet to the coal wharf at
the inner end of the north pier, thence 6 feet in a narrow channel to
Second Street Bridge. The Ahnapee River is navigable for a dis-
tance of about 2 miles from its mouth for vessels drawing not more
than 4 feet. The costs under the existing project were $99,236
for new work and $263,521 for maintenance, a total of $362,757.
1070          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                     Cost and financial summary

                                            Fiscal year ending June 30                         Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                              1950        1951          1952        1953         1954          prior to 1950 1


New work:
   Appropriated      .------------ ------------ ------------
   Cost--------........ ------------.
                                                                ------------  ------------
                                        ------------ ------------------------------------
                                                                                                      $292, 010
                                                                                                       292, 010
Maintenance:
   Appropriated-------          $7, 000      -$452 ------------     $1, 000        $150                272, 248
   Cost-----------------       6, 738       1,180   -----                  36         1,075            272,209

I Includes $192,774 for new work and $8,688 for maintenance for previous projects.


                             8. KEWAUNEE HARBOR, WIS.
   Location. On the west shore of Lake Michigan, distant about
105 miles northerly from Milwaukee and about 78 miles from Green
Bay, via Sturgeon Bay Canal. The harbor is at the mouth of the
Kewaunee River. (See U. S. Lake Survey Chart No. 73.)
   Previous projects. The original project was adopted by the
River and Harbor Act of March 3, 1881. For further details, see
page 1936 of Annual Report for 1915, and page 1447 of Annual Re-
port for 1938.
   Existing project. This provides for a converging north break-
water and shore connection about 3,130 feet long, removal of about
1,400 feet of the total length of about 1,850 feet of the north pier,
a south pier about 1,850 feet long, an entrance channel, about 2,800
feet long and 20 feet deep, leading to an interior turning basin of
the same depth, the entrance channel to have a general width, of
505 feet for a distance of about 1,500 feet through the outer basin,
decreasing thence to about 156 feet between the piers to the
turning basin; also for removal of the outer south shoal to a depth
of 22 feet. The parallel piers are formed of stone-filled piling and
are capped with concrete superstructure, except for 216 feet of the
south pier which consists of steel sheet piling. The north break-
water is formed of concrete caissons and the north-shore connec-
tion is a rubble mound.
   The project depth is referred to low water datum for Lake Michi-
gan, which is 578.5 feet above mean tide at New York. The fluctu-
ations of water level are seasonal changes of about one-half foot
above or below the annual mean stage, and extreme fluctuations of
a temporary nature, due to wind and barometric pressure, of about
11/2 feet above or below the mean lake level prevailing at the time.
   The estimate of cost for new work (1954) is $1,160,000, exclusive
of amount expended on previous projects. The latest (1954) ap-
proved estimate of annual cost of maintenance is $20,000.
                 RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                                                    1071
The existing project was authorized by the following River and
Harbor Acts:
       Acts                                  Work authorized                                                    Documents

Mar. 3, 1881         Entrance piers      1------...-................----......-                    Annual Report, 1881, p. 2082.
June 25, 1910        Turning basin_ ----------------------------------                             H. Doc. 324, 60th Cong., 1st sess.
Aug. 30,19352        North breakwater, removal of old north pier, widen-                           Rivers and Harbors Committee
                        ing and deepening entrance channel and turning                                 Doc. 43, 72d Cong., lst[sess.'
                        basin to 20 feet, and removal of outer south shoal.

   1 Completed under previous projects.
   2 Included in the Emergency Relief program, May 28, 1935.
   3 Contains latest published map.


   Local cooperation. Fully complied with.
   Terminal facilities. Besides two car-ferry slips, there is a coal
wharf, a grain wharf, a shipbuilding yard, and several fishing
wharves. These facilities are considered adequate for existing
commerce.
   Operations and results during fiscal year. Condition surveys
were made at a cost of $1,848 and miscellaneous inspections and
reports cost $269. The preparation of plans, etc. for repairs to
outer end of south pier cost $1,327. All work was performed by
hired labor and use of Government plant. The costs were $3,444
for maintenance.
   Condition at end of fiscal year. The existing project is about 71
percent complete. The work remaining to be done consists of re-
moval of the outer shoal and an additional 700 linear feet of the
north pier; widening of the inner 700 feet of the channel through
the outer basin, and closing the gap in the north-shore connection,
all of which is not considered necessary under present conditions.
The piers were completed in 1897 and are in generally good condi-
tion except that the south pier requires repairs. Construction of
the north breakwater and shore connection, except for a gap of
150 feet about 830 feet from the shoreward end, and the removal
of the outer 706.5 linear feet of the north pier were commenced in
September 1935 and completed in June 1937. Dredging the en-
trance channel and interior basin, to existing project depth, was
commenced in April 1938 and completed in October 1938. The con-
trolling depth at low water datum at the close of the fiscal year was
20 feet in the entrance channel, and 18.1 feet between the piers and
over an area 400 by 400 feet in the turning basin. The Kewaunee
River is navigable for a distance of about 61/2 miles above the
mouth for craft drawing not more than 4 feet. The costs under
the existing project were as follows:

                                                                                        New work         Maintenance          Total

Regular funds--------------------------------                                              $ 72,057            $384,480         $456, 537
Emergency Relief funds__      ----------             ---------------              ---       420, 000                             420, 000
       Total.........-----------------------------------------                             492,057             384,480           876.536
1072           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                    Cost and financial summary

                                                Fiscal year ending June 30                       Total to June
                                                                                                 30, 1954, includ-
                                                                                                 ing fiscal years
                             1950             1951                 1952     1953        1954       prior to 1950

New work:
   Appropriated     _........                                                                            $641, 369
   Cost         ------------        ----------------------------                   --                     641,369
Maintenance:
   Appropriated .---         $23,847          $13, 500             $1,500    $9,000     $1,350            472, 878
   Cost-----------------      21,560           13,439               2,312     6,820      3,444            472,844

1Includes $149,312 for new work and $88,364 for maintenance for previous projects.
Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project__ ___       _      _ _ __     $668,000

                           9. TWO RIVERS HARBOR, WIS.
    Location. This harbor is on the west shore of Lake Michigan,
distant about 82 miles northerly from Milwaukee and about 101
miles from Green Bay via Sturgeon Bay Canal. (See U. S. Lake
Survey Chart No. 73.)
    Previous projects. Adopted by the River and Harbor Act of
March 3, 1871. For further details, see page 1936 of Annual Re-
port for 1915, and page 1450 of Annual Report for 1938.
   Existing project. This provides for two entrance piers at the
mouth of Twin Rivers, 245 feet apart at the outer ends and 750
feet apart at the shore line, having lengths of about 1,642 feet and
1,720 feet for the north and south piers, respectively; for a channel
2,600 feet long and 18 feet deep extending from that depth in the
lake to an inner basin of the same depth at the confluence of the
East and West Twin Rivers, the channel varying in width from
500 feet at the outer end to 200 feet between the piers; for a revet-
ment about 450 feet long on the north side at the inner end of the
channel and for a small stilling basin beyond the shore line on the
north side of the channel. The piers are formed of stone-filled tim-
ber cribs and piling, and have been provided with concrete super-
structure; the pile revetment on north side of channel is also pro-
vided with concrete superstructure.
   The project depth is referred to low water datum for Lake Michi-
gan, which is 578.5 feet above mean tide at New York. The fluctua-
tions of water level are seasonal changes of about one-half foot
above or below the annual mean stage and extreme fluctuations of
a temporary nature, due to wind and barometric pressure, of about
11/2 feet above or below the mean lake level prevailing at the time.
   The estimate of cost for new work (1954) is $89,000, exclusive
of amounts expended on previous projects. The latest (1954) ap-
proved estimate of annual cost of maintenance is $30,000.
                  RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                          1073
The existing project was authorized by the following River and
Harbor Acts:

       Acts                           Work authorized                                   Documents

Mar. 3, 1871       South pier, 750 feet of north pier, and about 44 feet of   Annual Report, 1871, p. 123 (as
                     north revetment.'                                         modified by the Chief of Engi-
                                                                                neers Feb. 27, 1897).
Mar.    2, 1907    Remainder of north pier and stilling basin_.-
                                                               -....-         H. Doc. 730, 59th Cong., 1st sess.
                                                                                (Modification of plan A.)
Aug. 30, 1935      Deepening entrance channel and inner basin to 18           Rivers and Harbors Committee2
                     feet.                                                     Doc. 25, 73d Cong., 2d sess.


I Completed under previous projects.
2 Contains latest published map.




   Local cooperation. Fully complied with.
   Terminal facilities. These consist of a coal wharf and several
fishing wharves. The city has provided a wharf for public use.
These facilities are considered adequate for existing commerce.
   Operations and results during fiscal year. Operations consisted
of dredging 57,820 cubic yards of material with dipper dredge for
restoration of project depth at the entrance channel at a cost of
$34,122. Repairs to the outer end of the north pier, in progress at
the close of the previous fiscal year, were completed at a cost of
$644. Condition surveys cost $1,284 and miscellaneous inspections
and reports cost $38. All work was performed by hired labor and
use of Government plant. The total cost was $36,088 for main-
tenance.
   Condition at end of fiscal year. The existing project is about 88
percent complete. The ywork remaining to be done consists of
dredging a 10-foot width along each side of the lakeward portion
of the entrance channel between the piers. This dredging was
necessarily omitted to avoid removal of riprap along the entrance
piers and thereby endangering them. The present width of chan-
nel is considered adequate for present and reasonably prospective
commerce. The south pier was completed in 1883 and is in gener-
ally good condition. The north pier was completed in 1908. Dredg-
ing of the entrance channel and inner basin to existing project
depth was commenced in March 1937 and substantially completed
in May 1937. The controlling depth at low water datum at the
close of the fiscal year was 18 feet in the channel between the piers
and 14.6 feet in the inner basin. East and West Twin Rivers are
navigable for about 3 and 7 miles, respectively, from the harbor
piers for craft drawing not more than 4 feet. The costs under the
existing project were $74,722 for new work and $779,787 for
maintenance, a total of $854,509.
1074             REPORT: OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                               Cost and financial summary

                                                           Fiscal year ending June 30                                 Total to June
                                                                                                                      30, 1954, includ-
                                                                                                                      ing fiscal years
                                      1950               1951                1952            1953           1954       prior to 19501


New work:
   Appropriated--------........   .-----...-----------------------------------------------                                    $287,579
   Cost --------------------------------------.-----------                                          ----------             -287,579
Maintenance:
   Appropriated-----.......           $27, 500           $55, 500             $4,800         $77,000       $38, 200            812,712
   Cost.. .. -----------               26,610             55,537               5, 590         79, 401       35, 895            812, 712

  1 Includes $212,857 for new work and $33,113 for maintenance for previous projects.
  2 Operations and results during fiscal year $36,088 less pending adjustment of $189; and stock on.hand
June 30, 1953 included in fiscal year 1954 costs in the amount of $6.
Other new work data: Estimated additional amount needed to be appropri-
ated for completion of existing project-____ -- ______    __- ___  _ $14,300

                                  10. MANITOWOC HARBOR, WIS.
   Location. This harbor is on the west shore of Lake Michigan,
distant about 79 miles northerly from Milwaukee and about 106
miles from Green Bay via Sturgeon Bay Canal. (See U. S. Lake
Survey Chart No. 735.)
   Previous projects. The original project was adopted in 1854,
the first appropriation for the improvement having been made by
the River and Harbor Act of August 30, 1852. The project was
modified by subsequent River and Harbor Acts of March 3, 1881,
September 19, 1890, June 3, 1896, and June 13, 1902. For further
details, see page 1937 of Annual Report for 1915, and page 1453 of
Annual Report for 1938.
   Existing project. This provides for an outer harbor or stilling
basin formed by two breakwaters extending from the shore on
either side of the mouth of the Manitowoc River 425 feet apart at
their outer ends and diverging to a distance of about 2,325 feet
apart at their inner ends, having lengths of 2,540 feet and 2,290
feet for the north and south breakwaters, respectively; for a chan-
nel 21 feet deep, extending from that depth in the lake through the
outer harbor to the mouth of the river, a total length of about
2,500 feet, with a width of about 650 feet; for a channel 21 feet
deep in Manitowoc River from the river mouth to the second rail-
way bridge, a distance of approximately 1.7 miles, with widths of
180 feet at the mouth, reducing to 150 feet at the upper end, with
intermediate reductions and enlargements; for removal of old
north stub pier at the river entrance; and for dredging in the outer
harbor an approach channel 21 feet deep to a proposed city termi-
nal on the lake front south of the shore end of the south break-
water. The breakwaters are formed of stone-filled timber cribs,
concrete caissons, and piling, all of which are capped with concrete
superstructures.
   The project depth is referred to low water datum for Lake Michi-
gan, which is 578.5 feet above mean tide at New York. The fluctu-
ations of water level are seasonal changes of about one-half foot
above or below the annual mean stage, and extreme fluctuations of
a temporary nature, due to wind and barometric pressure of about
11/2 feet above or below the mean lake level prevailing at the time.
              RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                                 1075

  The estimate of cost for new work (1954) is $729,000, exclusive
of amounts expended on previous projects. The latest (1954) ap-
proved estimate for annual cost of maintenance is $30,000.
  The existing project was authorized by the following River and
Harbor Acts:

       Acts                           Work authorized                                       Documents

Mar.    2, 1907   Breakwaters---........_----.............--------------.....    H. Doc. 62, 59th Cong., 1st sess.,
                                                                                  as modified by Rivers and Har-
                                                                                  bors Committee Doc. 3, 59th
                                                                                  Cong., 2d sess.
Aug. 30, 1935     Present project dimensions of channel through outer            Rivers and Harbors Committee
                    basin, removal of old north stub pier, and approach           Doc. 39, 73d Cong., 2d sess.
                    channel to a proposed city terminal south of shore
                    end of the south breakwater.
Aug. 26, 1937     Channel in the river-...____---    __----------------     ..   Rivers and Harbors Committee
                                                                                   Doc. 80, 74th Cong., 2d sess.
                                                                                   (Contains latest published map.)



   Local cooperation. The act of August 30, 1935, provided that
the work of dredging an approach channel to the proposed city
terminal in the outer harbor "shall not be undertaken until local
interests shall have submitted assurances satisfactory to the Sec-
retary of War that such terminal will be constructed." The plan
for the municipal terminal has been abandoned. All other re-
quirements have been complied with.
   Terminal facilities. There are 3 car-ferry slips, 2 grain eleva-
tors, 2 shipbuilding yards, and several wharves used for handling
coal, building materials, cement, and miscellaneous commodities.
While these facilities are considered fairly adequate for existing
commerce, it is believed the city should provide a suitable wharf
with warehouse and railway connection, which should be open to
the general public.
   Operations and results during fiscal year. Operations consisted
of dredging 28,090 cubic yards of material with dipper dredge for
restoration of project depths in entrance and river channels at a
cost of $13,653. Repairs to outer 148 feet of south breakwater
cost $14,275. Refilling and riprapping the south breakwater with
2,007 tons of stone cost $14,332. Condition surveys cost $2,018
and miscellaneous inspections and reports cost $460. All work was
performed by hired labor and use of Government plant. The total
cost was $44,738 for maintenance.
   Condition at end of fiscal year. The existing project is about 87
percent complete. The work remaining to be done consists of dredg-
ing the approach channel in the outer harbor, which is not now
desired by local interests. The breakwaters completed in 1910 are
in generally good condition, except for some minor repairs required.
The dredging of the channel through the outer basin to existing
project depth, and the removal of a portion of the old north stub
pier at the river entrance were commenced in May 1937 and com-
pleted in December 1937. Dredging of the river channel was com-
menced in June 1939 and completed in July 1942. The controlling
depth at low water datum at the close of the fiscal year was 21 feet
in the channel through the outer basin and in the river to the
second railway bridge. The costsunder the existing project were
1076          REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

$436,752 for new work and $838,097 for maintenance, a total of
$1,274,849.
                                     Cost and financialsummary

                                            Fiscal year ending June 30                        Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                              1950         1951         1952         1953         1954         priorto 1950


New work:
   Appropriated    ---------------------------------                                                  $836, 878
   Cost---------------- -----   -----------------------------------------------                        836,878
Maintenance:
   Appropriated .......       $35, 000     $60,000      $11, 500     $19, 750     $31, 400             894,640
   Cost----------.... ---      30,492       61, 783      17,412        3,017      s 40, 576            888,223

I Includes $400,126 for new work and $54,288 for maintenance for previous projects.
2 Operations and results during fiscal year $44,738 less pending adjustment of $4,162.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project___    __--_                   $292,300

                            11. SHEBOYGAN HARBOR, WIS.

   Location. This harbor is on the west shore of Lake Michigan,
distant about 26 miles south from Manitowoc and about 55 miles
north of Milwaukee. (See U. S. Lake Survey Chart No. 735.)
   Previous projects. The original project was adopted by the
River and Harbor Act of June 23, 1866, and modified by River and
Harbor Acts of March 3, 1873, March 3, 1881, August 18, 1894,
March 3, 1899, and June 13, 1902. For further details, see page 1937
of Annual Report for 1915, and page 1456 of Annual Report for
1938.
   Existing project. This provides for an outer harbor or stilling
basin formed by a breakwater extending from the shore about
2,100 feet north of the remaining 456 feet of the pier and revetment
on the north side of the channel at the mouth of the Sheboygan
River for a total length of 3,829 feet, and a south pier 2,750 feet
long extending into the lake about normal to the shore on the south
side of the mouth of the river, and for a turning basin 900 feet wide
and 20 feet deep in the outer harbor with an entrance channel
about 3,500 feet long through the south side of the basin, the
depth being 25 feet from the lakeward end to a point 500 feet shore-
ward of the end of the north breakwater, decreasing to 21 feet in
the next 300 feet and continuing at the latter depth to the inner
end of the improved channel, the widths to be 400 feet at the
lakeward end and 500 feet through the turning basin, decreasing
to 200 feet at the river mouth. The north breakwater is formed
of stone-filled timber cribs, concrete caissons, and piling, all of
which is capped with concrete superstructure. The south pier and
north stub pier and revetment are formed of timber cribs and
piling, all of which have also been provided with concrete super-
structure. -
   The project depth is referred to low water datum for Lake
Michigan, which is 578.5 feet above mean tide at New York. The
fluctuations of water level are seasonal changes of about one-half
foot above or below the annual mean stage and extreme fluctua-
tions of a temporary nature, due to wind and barometric pressure,
                RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                    1077
of about 1 /2 feet above or below the mean lake level prevailing at
the time.
   The cost of new work for the completed project was $446,771, ex-
clusive of amounts expended on previous projects. The latest
 (1954) approved estimate of annual cost of maintenance is
$30,000.
The existing project was authorized by the following River and
Harbor Acts:

    Acts                          Work authorized                               Documents

Mar. 2, 1907     North breakwater __.__.-- ____---
                                             . __._ _-_---...
                                                        ..           H. Doc. 62, 59th Cong., 1st sess.
Jan. 21, 1927    Preserving south pier as part of project, providing H. Doc. 475, 68th Cong., 2d sess.
                  turning basin, and elimination of proposed south
                  breakwater.
Aug. 30, 1935    Present project dimensions of channel__-....__   ... Rivers and Harbors Committee
                                                                        Doc. 47, 74th Cong., 1st sess.
                                                                       (Contains latest published map.)



    Recommended modifications of project. The Chief of Engi-
neers in House Document 554, 82d Congress, 2d session, before
Congress, recommends modifications of the existing project to
provide for a width of 450 feet at the lakeward end of the en-
trance channel, extension of the 25-foot channel to a point 700 feet
shoreward of the outer end of the north breakwater, depths de-
creasing from 25 to 21 feet in a farther shoreward distance of 300
feet, extension of the 21-foot project channel upstream to the south
side of Maryland Avenue with a general width of about 165 feet
and maximum width of 370 feet, and a channel 15 feet deep with
general width of 100 feet, extending from the south side of Mary-
land Avenue to the north side of Jefferson Avenue, with no dredg-
ing to be done by the Federal Government within 25 feet of any
wharf or bulkhead. The estimated cost of this modification as
contained in the document is $199,100. The latest (1954) estimate
is $217,200.
   Local cooperation. None required.
    Terminal facilities. These consist of several wharves used for
handling coal, building material, fish, and miscellaneous commodi-
ties. The city has provided a public warf. The facilities are con-
sidered adequate for existing commerce.
   Operationsand results during fiscal year. Operations consisted
of riprapping the north breakwater with 3,361 tons of stone at a
cost of $23,054 and filling south pier with 1,488 tons of stone at a
cost of $6,093. Condition surveys cost $1,231 and miscellaneous
inspections and reports cost $293. All work was performed by
hired labor and use of Government plant. The total cost was
$30,671 for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1938. The south pier was completed in 1904. Construc-
tion of the north breakwater was commenced in October 1913 and,
completed in October 1915. Dredging of the turning basin was
commenced in October 1928 and completed in September 1931.
Dredging of the entrance channel to existing project depth was
commenced    in June 1938 and completed in July 1938. The piers
1078           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

and breakwaters are in generally good condition except that the
concrete superstructure on the north shore connection is disin-
tegrating and requires repairs. The inner 260 feet of the south
pier has been replaced with a revetment by private interests under
permit granted July 16, 1931, by the Secretary of War. The pier
is therefore maintained only for a length of about 2,490 feet. The
controlling depths at low water datum at the close of the fiscal year
were 23 feet at the entrance for 500 feet, thence 21 feet in channel,
and 19.1 feet in turning basin. Sheboygan River is navigable for
a distance of about 2.4 miles above its mouth for craft drawing
not more than 2 feet. The costs under the existing project were
$446,771 for new work and $799,262 for maintenance, a total of
$1,246,033.
                                        Cost and financial summary

                                              Fiscal year ending June 30                    Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                                 1950        1951        1952        1953        1954        priorto 19501

New work:
   Appropriated           ----          - - -----------------------------   --    -     -          $934,588
   Cost--------       ------------------------------------------------           ------------        934,588
Maintenance:
   Appropriated ....- - - -      24, 000     $29, 000    $24, 500    $18,450     $28, 750            886,404
   Cost------------      -----   23,275       36,119      19,484      15,592     230, 670            886, 392

I Includes $487,817 for new work and $87,131 for maintenance for previous projects.
2 Operation and results during fiscal year $30,671, less pending adjustment of $1.

                     12. PORT WASHINGTON                        HARBOR, WIS.
   Location. On the west shore of Lake Michigan, distant about
53 miles south from Manitowoc and about 29 miles north from
Milwaukee. (See U. S. Lake Survey Chart No. 74.)
   Previous projects. The original project was adopted by the
River and Harbor Act of July 11, 1870, and was modified by the
River and Harbor Act of August 14, 1876. For further details, see
page 1938 of Annual Report for 1915, and page 1459 of Annual
Report for 1938.
   Existing project. This provides for a north breakwater and
shore connection approximately 2,537 feet long, extending from the
shore about 1,350 feet north of the remaining 125 feet of the old
north pier; removal of 650 feet of the north pier; for extending a
privately owned south breakwater about 456 feet into the lake to
form an entrance about 350 feet in width, and for an outer turning
basin 750 feet wide and 21 feet deep with an entrance channel
about 2,400 feet long and 21 feet deep through the south side of
the basin, the width being 110 feet at the inner end of the north
pier and about 275 feet at the harbor entrance, leading to two
interiors basins 18 feet deep, the west basin being 140 feet wide
and 490 feet long and the north basin 190 feet wide and 750 feet
long. The north breakwater is formed of concrete caissons and the
shore connection of interlocking steel-sheet piling of the cellular
and single-wall type. The south breakwater is formed of concrete
caissons and rubble mound. The north stub pier is formed of
stone-filled steel-sheet piling.
   The project depth is referred to low water datum for Lake
              RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                            1079
Michigan, which is 578.5 feet above mean tide at New York. The
fluctuations of water level are seasonal changes of about one-half
foot above or below the annual mean stage, and extreme fluctua-
tions of a temporary nature, due to wind and barometric pressure,
of about 11/2 feet above or below the mean lake level prevailing
at the time.
   The cost for new work for the completed project was $810,709,
exclusive of the amounts expended on previous projects. The lat-
est (1954) approved estimate for annual cost of maintenance
is $14,500.
   The existing project was authorized by the following River and
Harbor Acts:
     Acts                            Work authorized                                Documents

July 11, 1870     North pier and south basin 1......_            .       H. Ex. Doc. 28, 41st Cong., 2d sess.,
                                                                           and Annual Report, 1870, p. 119.
Aug. 14, 1876     North basin 1-.... ,..----        .----         -..    Annual Report, 1876, pt. 2, p. 379.
Aug. 30, 1935 2   North Breakwater, removal of 650 feet of north pier,   H. Doe. 168, 72d Cong., 1st sess.,
                    outer turning basin, present project dimensions        and Rivers and Harbors Com-
                    of channel and basin and extension of south break-     mittee
                                                                                3 Doc. 41, 74th Cong., 1st
                    water.                                                 sess.

  1 Completed under previous projects.
  2 Work recommended in H. Doc. 168, 72d Cong., 1st sess., included in Public Works Administration pro-
gram, Sept. 6, 1933.
  3 Contains latest published map.

   Recommended modification of project. The Chief of Engineers
in House Document 446, 83rd Congress, 2d session recommends,
subject to certain conditions of local cooperation, modifications
of the existing project to provide for extending the lakeward
end of existing north breakwater 1,280 feet, increasing the top
elevation of the north caisson breakwater to 10 feet above low
water datum and placing rubble on its lakeward and harbor sides;
removing about 392 feet of caissons and 64 feet of rubble mound
in the existing south breakwater to a depth of 24 feet below low
water datum; enlarging the outer basin by deepening an additional
150 feet landward of existing basin to 21 feet below low water
datum; and relocating channel lines to correspond with the im-
provements. The estimated first cost for this modification as con-
tained in the document is $2,515,000, with an increase in annual
maintenance of $2,000.
   Local cooperation. Fully complied with.
    Terminal facilities. There are two coal and building-material
wharves and several fishing wharves. The city has provided a
wharf which is open to public use. These facilities are considered
adequate for existing commerce.
   Operations and results during fiscal year. Operations consisted
of dredging 23,150 cubic yards of material at a cost of $13,779.
Condition surveys cost $1,397 and miscellaneous inspections and re-
ports cost $336. All work was performed by hired labor and use
of Government plant. The total cost was $15,512 for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1936. Construction of the north breakwater and the re-
moval of the outer portion of the north pier were commenced in
April 1934 and completed in December 1934. Dredging of the en-
1080                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

trance channel, outer turning basin, and the interior basins to ex-
isting project depth, was commenced in July 1934 and completed
in December 1934. Construction of the south breakwater was com-
menced in July 1936 and completed in October 1936. The break-
waters and the north stub pier are in good condition. The original
south pier, completed in 1893, was entirely removed in 1932 by
private interests under permit granted October 25, 1930, by. the
Secretary of War and replaced with a coal wharf. A south rubble-
mound breakwater about 500 feet long was constructed in 1934
by private interests as an extension of their coal wharf in accord-
ance with local cooperation requirements of House Document No.
168, 72d Congress, 1st session. The controlling depth at low water
datum at the close of the fiscal year was 19 feet in the Govern-
ment entrance channel and turning basin. The interior basins had
a controlling depth of 16.0 feet. The area between the south line
of the Government entrance channel and the harbor face of the
private coal wharf, which is maintained by private interests, had
a controlling depth of 19.5 feet. The costs under the existing pro-
ject were as follows:

                                                                             New work             Maintenance            Total


Regular funds ...--------------------------------                                    $207, 714          $245,907            $453, 621
Public works funds- _ _                   __                                          602, 995   -------------               602,995

        Total ...-------.....-----..     ---------------------                        810,709            245,907           1,056,616



                                               Cost and financial summary

                                                               Fiscal year ending June 30                           Total to June
                                                                                                                    30, 1954, includ-
                                                                                                                    ing fiscal years
                                        1950               1951           1952            1953           1954        prior to 19501


New work:                                                                        -
      Appropriated ..                                                                                                       $999, 204
      Cost - - - - - - - - - - -                    - --   -                                                                 999,204
Maintenance:
      Appropriated..  - --              $8, 500                $7, 500    $14, 000         $1,000        $20, 850            267,141
      Cost-----------------              7, 454                 7, 276     14,258             359        219,782             265,300


  1 Includes $188,495 for new work and $15,123 for maintenance for previous projects.
  2   Operations and results during fiscal year $15,512, plus pending adjustment of $4,270.


                                       13. MILWAUKEE                     HARBOR, WIS.
   Location. On the west shore of Lake Michigan, distant about
85 miles northerly from Chicago and about 83 miles west of Grand
Haven, Mich. (See U. S. Lake Survey Chart No. 743.)
   Previous projects. The original project for improvement of
Milwaukee Harbor was adopted by act of March 3, 1843, and modi-
fied by River and Harbor Acts of August 30, 1852, April 10, 1869,
and March 3, 1899. The original project of the harbor of refuge
was adopted by River and Harbor Act of March 3, 1881. The pro-
ject of June 13, 1902, consolidating the harbor and harbor of refuge
was modified by River and Harbor Act of March 3, 1905. For
further details, see page 1938 of Annual Report for 1915, and page
1462 of Annual Report for 1938.
                 RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                                        1081
   Existing project. This provides for a north breakwater 9,954
feet long and a south breakwater of 9,671 feet, more or less, in
length, extending to the shore, thereby forming a protected basin
in which is being developed a commercial harbor by the city of
Milwaukee, the width of entrance between the 2 breakwaters being
about 500 feet. It further provides for the protection of the river
mouth by 2 piers, 358 feet apart at the outer ends and 552 feet
apart at the shore line, 1,656 and 1,608 feet in length for the north
and south piers, respectively; for a channel 21 feet deep, extend-
ing from that depth in the lake to the mouth of the river, a total
length of about 2,850 feet, the width of channel outside the piers
to be 600 feet; for dredging channels 21 feet deep in the rivers
from the inner ends of the entrance piers to the North Humboldt
Avenue Bridge on the Milwaukee River, to a point 100 feet west
of the west line of North 25th Street extended, on the Menomonee
River and to the South Kinnickinnic Avenue Bridge on the Kin-
nickinnic River; for dredging to 21 feet a portion of the outer
harbor between East Wisconsin Avenue extended and East Bay
Street extended and easterly of a line 50 feet lakeward of the pier
head line; and the abandonment of so much of the previous project
as related to dredging inside the shore line for the formation of
turning basins and widening channels. The breakwaters are
formed of stone-filled timber cribs and concrete caissons, all of
which are capped with concrete superstructures. The inner en-
trance piers are formed of concrete caissons, stone-filled timber
cribs, and piling and are also provided with concrete superstruc-
tures.
   The project depth is referred to low water datum for Lake Michi-
gan, which is 578.5 feet above mean tide at New York. The fluctu-
ations of water level are seasonal changes of about one-half foot
above or below the annual mean stage and extreme fluctuations of
a temporary nature, due to wind and barometric pressure, of about
1 feet above or below the mean lake level prevailing at the time.
   The estimate of cost for new work (1954) is $4,939,000, exclusive
of the amounts expended on previous projects. The latest (1954)
approved estimate for annual cost of maintenance is $113,000.
   The existing project was authorized by the following River and
Harbor Acts:

     Acts                              Work authorized                                               Documents


Aug. 30, 1852     North pier                     -.                  ___ _
                                          .______________________________.                S. Doc. 175, 25th Cong., 2d sess.
Mar. 3, 1881      Inner 7,600 feet of north breakwater                -................   Annual Report, 1881, p. 2122.
Mar. 2, 1907      South pier.     Extending north breakwater 1,000 feet__                 Annual Report, 1906, p. 1752. (No
                                                                                           prior survey or estimate affecting
                                                                                           the breakwater extension.)
Sept. 22, 1922    Extending north breakwater, for a south breakwater,                     H. Doc. 804, 66th Cong., 2d sess.
                    for present project dimensions of the inner entrance
                    channel.
Aug. 30, 1935     Dredging a portion of the outer harbor to 21-foot depth                 H. Doc. 289, 72d Cong., 1st sess.
Mar. 2. 1945      Dredging river channels to 21-foot depth-----------.............        S. Doc. 29, 76th Cong., 1st  -ess.'
I Completed under previous projects.
2 Contains latest published map.

  Local cooperation. The act of August 30, 1935, provided that
the original dredging of the outer harbor area be done by the city
1082     REPORT OF CHIEF OF ENGINEERS, U. S. ARMVY, 1954

of Milwaukee and the city of Milwaukee be reimbursed at actual
cost but not to exceed 10 cents per cubic yard, place measurement,
for original dredging done subsequent to the authorization of the
work by Congress. Agreement covering the dredging was executed
by the Secretary of War February 23, 1934, after this work was
originally authorized as part of the Public Works program.
   All other requirements have been complied with.
   Terminal facilities. There are 4 car-ferry slips, numerous
wharves, private and municipal, used for the handling of coal,
grain, building materials, cement, petroleum products, and mis-
cellaneous commodities. As the facilities in the inner harbor are
considered inadequate for existing commerce, the Milwaukee Har-
bor Commission is engaged in building an outer harbor.
   Operations and results during fiscal year. Condition surveys
were made at a cost of $2,139, and miscellaneous inspections and
reports cost $2,195. Reconstruction of 1025.5 linear feet of south
pier was completed at a cost of $134,715. Riprapping breakwaters
with 7,855 tons of stone cost $57,065. Preparation of plans and
specifications for reconstruction of 800 feet of north breakwater
cost $2,014. All work was performed by hired labor and use of
Government plant, except for the reconstruction of 1025.5 linear
feet of the south pier. The total cost was $198,128 for main-
tenance.
   Condition at end of fiscal year. The project in effect prior to
the modifications of August 30, 1935, and March 2, 1945, was com-
pleted in 1934. No work has been done on deepening the outer
harbor area to 21 feet north of the inner entrance piers, nor on
the last modification of the project providing for dredging the river
channels to 21 feet deep. The north breakwater was completed for
a length of 8,210 feet in 1909. Construction of 1,744 feet in ex-
tension of the north breakwater was commenced in May 1924 and
completed in August 1925, making the total length 9,954 feet.
The north pier was completed in 1905 and construction of the south
pier was commenced in April 1909 and completed in November
1910. Construction of the south breakwater and shore connection
was commenced in May 1925 and completed in October 1929, except
for placing additional riprap and rebuilding about 756 feet of the
breakwater damaged by a storm of October 22-23, 1929. Rebuild-
ing the damaged section of the south breakwater and placing of
additional riprap was commenced in April 1931 and completed in
August 1932. Dredging for deepening and widening the entrance
channel to existing project depth and width, was commenced in
May 1929 and completed in September 1930. Placing additional
small stone around the caisson breakwaters to chink the voids in
the large riprap was commenced in 1930 and completed in 1934.
Prior to the modification of August 30, 1935, the city of Milwaukee
dredged the area in the outer harbor south of the inner-entrance
piers and lakeward of the pierhead line to more than 21 feet below
datum without cost to the United States.
   The concrete superstructures and the timber crib section of the
north breakwater and the harbor piers are showing some distinte-
gration and require repairs, The south breakwater and shore con-
nections are in generally good condition. The controlling depth at
             RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                            1083
low water datum at the close of the fiscal year was 21 feet and
more in the entrance channel through the outer basin and between
the inner piers, 24 feet in the Milwaukee River to Water Street
Bridge, 18.5 feet to Juneau Avenue Bridge and 18 feet to end of
project; 22 feet in Kinnickinnic River to 200 feet upstream of car
ferry slip, 19.5 feet to Kinnickinnic Avenue Bridge and 21 feet in
the Menomonee River to the 16th Street Bridge, thence 19.9 feet
to Northwestern-Hanna dock, thence 17 feet to 13 feet to upper
end of project. The costs under the existing project were $4,537,-
812 for new work, $1,880,913 for maintenance, a total of $6,418,725.
                         Cost and financial summary

                                             Fiscal year ending June 30                       Total to June
                                                                                             30, 1954, includ-
                                                                                             ing fiscal years
                               1950        1951         1952         1953         1954         prior to 19501

New work:
   Appropriated_      _-----------------------------------------------------------                $5,831,032
   Cost.....                           ---
                            - - - - .....-        ------------      --     --
                                                                           -                       5,831,032
Maintenance:
   Appropriated-_ _..-..- .   $168, 500    $63,000      $41,500     $303,900     $ 78,150          2, 352, 776
   Cost--------__ --           263,118      66,305       39,108      170, 782   2 198, 706         2,340, 796

  SIncludes $1,293,220 for new work and $459,305 for maintenance for previous projects.
  2 Operations and results during fiscal year $198,128, plus pending adjustment of $578.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project _____________                  401,200
                                                                        $___________

                                14. RACINE          HARBOR, WIS.
   Location. On the west shore of Lake Michigan, distant about
26 miles southerly from Milwaukee and about 64 miles northerly
from Chicago. (See U. S. Lake Survey Chart No. 745.)
   Previous projects. The original project was adopted by the
citizens of Racine about 1842 or 1843. The citizens' project was
modified by acts of June 23, 1866, March 3, 1899, and June 13, 1902.
For further details, see page 1939 of Annual Report for 1915, and
page 1465 of Annual Report for 1938.
   Existing project. This provides for a north breakwater 2,640
feet long extending from shore at a point about 1,350 feet north of
the remaining 180 feet of pier on the north side of the channel at
the mouth of Root River, and for a south breakwater 2,652 feet long
extending from the city rubble mound about 1,650 feet south of the
remaining 22.5 feet of pier on the south side of the channel at the
mouth of the river. It further provides for a channel, through the
outer basin, 23 feet deep from that depth in the lake to a point
about 400 feet inside the entrance, thence 21 feet to a point about
750 feet westward of the outer end of the north stub pier, with
widths of 350 feet at the entrance, increasing to 1,000 feet through
the outer harbor and decreasing to 190 feet in the river to a point
about 750 feet westward of the outer end of the north stub pier,
the total length of channel being about 2,300 feet; thence a chan-
nel 19 feet deep in Root River to a point about 195 feet below the
north line of Bridge Street extended, a distance of about 2,900 feet,
with widths of 190 feet at the lower end reducing to 95 feet at the
upper end, with intermediate reductions and enlargements; and
1084            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

removal of shoals about one-half mile lakeward of the harbor en-
trance to a minimum depth of 25 feet. The breakwaters and south
stub pier are formed of stone-filled timber cribs, concrete caissons,
and piling, all being capped with concrete superstructures. The
north stub pier is formed of stone-filled steel-sheet piling.
   The project depth is referred to low water datum for Lake Michi-
gan, which is 578.5 feet above mean tide at New York. The fluctua-
tions of water level are seasonal changes of about one-half foot
above or below the annual mean stage, and extreme fluctuations
of a temporary nature, due to wind and barometric pressure, of
about 11/2 feet above or below the mean lake level prevailing at
the time.
   The cost for new work for project as completed was $777,775,
exclusive of the amounts expended on previous projects and exclu-
sive of inner 300 linear feet of pile pier and 450 linear feet of rubble
mound, originally part of south breakwater but no longer consid-
ered necessary. The latest (1954) approved estimate for annual
cost of maintenance is $41,000.
   The existing project was authorized by the following River and
Harbor Acts:
    Acts                         Work authorized                                       Documents

Mar. 2, 1907 \Breakwat                                                  fH. Doc. 62, 59th Cong., Ist sess.,
June 25, 1910 /Breakwaters.-----------...
                                .and -          ---    -     ...   --   1     Annual Report, 1909, p. 1973.
Aug. 26, 1937   Removal of shoals lakeward of harbor entrance, en-          Rivers and Harbors Committee,
                 largement of 19-foot channel through outer basin             Doec. 46, 76th Cong., 1st sess.
                 and 19-foot channel in river.
Mar. 2, 1945    Present project dimensions of channel through outer         H. Doec. 816, 77th Cong., 2d sess.,
                 basin and in river,                                          and H. Doc. 255, 78th Cong., 1st
                                                                              sess. (Contains latest published
                                                                              maps.)


   Local cooperation. Fully complied with.
   Terminal facilities. These consist of several wharves used for
handling of coal and fish. The city has provided a public wharf
with warehouse.
   Operations and results during fiscal year. Condition surveys
were made at a cost of $1,924 and miscellaneous inspections and
reports cost $142. Breakwaters were riprapped with 998 tons of
stone at a cost of $5,081. All work was performed by hired labor
and use of Government plant. The total cost was $7,147 for main-
tenance.
   Condition at end of fiscal year. The existing project was sub-
stantially completed in 1946. Construction of the north break-
water and shore connection was completed in November 1918. Re-
moval of the old north pier was completed in 1913. Construction
of the south breakwater and shore connection and the removal of
the old south pier were commenced in June 1916 and completed in
December 1924. Removal of the outer shoals widening and deepen-
ing the channel through the outer basin to existing project depth
and width, and dredging of the river channel were commenced in
July 1946 and completed in November 1946. The concrete super-
structure on north breakwater and shore connection is disintegrat-
ing and requires repairs. The south breakwater and shore connec-
tion and stub piers are in generally good condition. The controlling
               RIVERS AND HARBORS-MILWAUKEE,                                          WIS., DISTRICT                  1085
depths at low water datum at the close of the fiscal year were 21
feet in the channel through the outer basin and for a distance of
about 600 feet in the river, thence 17.5 feet to 100 feet downstream
from State Street Bridge and 15.9 feet to upper limits of project.
The costs under the existing project were $777,775 for new work
and $660,454 for maintenance, a total of $1,438,229.
                                                 Cost and financial summary

                                                       Fiscal year ending June 30                             Total to June
                                                                                                              30, 1954, includ-
                                                                                                              ing fiscal years
                                       1950           1951                1952     1953              1954       prior to 19501


New work:
   Appropriated .                 ......                     _                     ---------......      ..         $1,205,016
   Cost                                  -----
                             ___------------            --.-----------.                                              1,205,015
Maintenance:
   Appropriated-         -             $56,500       $103,500             $8,000   $18,500           $8,200            740,486
   Cost---------------                     40, 614    120, 551             9,281    19,191           27,172            740, 016


1Includes $427,240 for new work and $79,537 for maintenance for previous projects.
2 Operation and results during fiscal year $7,147 plus pending adjustment of $25.

                                       15. KENOSHA HARBOR, WIS.
   Location. On the west shore of Lake Michigan distant about
35 miles southerly from Milwaukee and about 54 miles northerly
from Chicago. (See U. S. Lake Survey Chart No. 74.)
   Previous projects. The original project was adopted by the
River and Harbor Act of August 30, 1852, and modified by River
and Harbor Acts of June 23, 1866, September 19, 1890, March 3,
1899, and June 13, 1902. For further details, see page 1939 of
Annual Report for 1915, and page 1468 of Annual Report for 1938.
   Existing project. This provides for a detached breakwater
796 feet long, and for 2 parallel piers about 250 feet apart, 1,077
feet and 1,872 feet in length for the north and south piers, respec-
tively. It further provides for an entrance channel 200 feet wide
and 21 feet deep, from that depth in the lake a distance of 2,750
feet to an interior basin 21 feet deep; and for a channel 21 feet deep
and generally 70 feet wide, extending 475 feet northwesterly from
the northwest corner of the interior basin to within 35 feet of the
50th Street Bridge. The breakwater is formed of stone-filled tim-
ber cribs; the piers are formed of stone-filled timber cribs and pil-
ing. The entire north pier, 1,175 feet of the south pier, and the
entire breakwater are capped with concrete superstructure. The
inner 697 feet of the south pier has been provided with a steel sheet
pile face.
   The project depths are referred to low water datum for Lake
Michigan, which is 578.5 feet above mean tide at New York. The
fluctuations of water level are seasonal changes of about one-half
foot above or below the annual mean stage, and extreme fluctua-
tions of a temporary nature, due to wind and barometric pressure,
of about 11/2 feet above or below the mean lake level prevailing at
the time.
   The estimate of cost for new work (1954) is $76,000, exclusive
of amounts expended on previous projects and excluding $3,000 to
be contributed by local interests. The latest (1954) approved esti-
mate for annual cost of maintenance is $24,000.
1086              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  The existing project was authorized by the following River and
Harbor Acts:
       Acts                         Work authorized                                           Documents


Mar. 3, 1899      Parallel piers and 600 feet of breakwater t        --------
                                                                         ---  H. Doc.       328, 54th Cong., 2d sess.;
                                                                                     Annual Report, 1897, p. 2772;
                                                                                     H. Doc. 164, 55th Cong., 3d sess.,
                                                                                     Annual Report, 1899, p. 2817.
Mar.    2, 1907   Extending breakwater 200 feet _               -                  H. Doc. 62, 59th Cong., 1st sess.,
                                                                                    and Rivers and Harbors Com-
                                                                                    mittee Doc. 3, 59th Cong., 2d
                                                                                    sess.
Aug. 30, 19352    Present project dimensions of entrance channel and           Rivers and Harbors Committee
                   basin.                                                        Doc. 19, 74th Cong., 1st sess.  3
May 17, 1950      Channel northwesterly from basin---                          H. Doc. 750, 80th Cong., 2d sess.


1 Completed under previous projects.
2Included in the Emergency Relief program May 28, 1935.
3 Contains latest published map.


   Local cooperation. The act of May 17, 1950, provided that
local interests shall furnish assurances satisfactory to the Secre-
tary of the Army that they will hold and save the United States
free from damages resulting from the initial construction and fu-
ture maintenance dredging operations, and contribute $3,000 to-
ward the cost of the improvement. Local interests were notified on
July 19, 1950, of the required conditions and requested to furnish
assurances that they will be met.
   Terminal facilities. There are several wharves used for han-
dling coal, building materials, and miscellaneous commodities, and
also several fishing wharves. While these facilties are considered
generally adequate for existing commerce, more efficient use of ex-
isting terminals and utlization of available frontage for develop-
ment of additional terminals should be made.
   Operations and results during fiscal year. Condition surveys
were made at a cost of $1,607 and miscellaneous inspections and
reports cost $100. The piers were riprapped with 924 tons of stone
at a cost of $7,239. All work was performed by hired labor and
use of Government plant. The total cost was $8,946 for mainte-
nance.
   Condition at end of fiscal year. The project in effect prior to
the modification of May 17, 1950, was completed in 1936. No work
has been done on the last modification of the project providing for
channel northwesterly from the basin. The north pier completed
in 1895, the south pier in 1900, and the breakwater in 1909, are in
generally good condition. Dredging of the entrance channel and
interior basin to existing project depth, was commenced in October
1935 and completed in April 1936. The controlling depth at low
water datum at the close of the fiscal year was 21 feet in the en-
trance channel and the inner basin and 16.8 feet in the inner chan-
nel. The costs under the existing project were as follows:

                                                                    New work          Maintenance          Total


Regular funds ______________________________       _                    $40, 553            $601, 401         $641, 954
Emergency Relief funds _____________ _________________                   27, 658                                27, 658
       Total_-      _   --                      -.                       68, 211             601,401           669, 612
                 RIVERS AND HARBORS-MILWAUKEE;                                                       WIS., DISTRICT                      1087
                                                 Cost and financial summary

                                                              Fiscal year ending June 30                                         Total to June
                                                                                                                                 30, 1954, includ-
                                                                                                                               Sing fiscal years
                                          1950            1951                1952               1953               1954       1 prior to 19501

New work:
   Appropriated----------------........
   Cost
                                                 --              ------------
          --------------------------------------------------------------------
                                                                                          -----------------------                        $522,051
                                                                                                                                          522,051
Maintenance:
     Appropriated --------                $21, 500              $292           $1, 500           $29, 400            $9, 450              623, 733
     Cost...-----------------              19,691     .......------------..     2,060              29,481             8,946               623,219

  I Includes $453,839 for new work and $21,818 for maintenance for previous projects.

Other new work data: Estimated additional amount needed to be appropriated
   for completion of existing project _-                              -              -------                               ---          $7,800


                                     16. ST. JOSEPH HARBOR, MICH.
    Location. Located on the east shore of Lake Michigan, distant
about 60 miles easterly from Chicago and about 24 miles southerly
from South Haven. (See U. S. Lake Survey Chart No. 758).
    Previous projects. The original project was adopted by the
River and Harbor Act of July 4, 1836, and modified by the River
and Harbor Act of June 23, 1866, March 3, 1875, June 14, 1880, and
July 13, 1892. For further details, see page 1945 of Annual Re-
port for 1915, and page 1470 of Annual Report for 1938.
    Existing project. This provides for protecting the mouth of
the St. Joseph River by 2 piers, 250 to 325 feet apart at their inner
and outer ends, respectively, having lengths of 2,854 feet on the
north side and 2,603 feet on the south side. It further provides for
a channel 21 feet deep from Lake Michigan to the mouth of the
Benton Harbor Canal, a length of about 6,900 feet, with widths of
265 feet at the outer end of the piers, 190 feet at the inner end of
the piers and revetments, thence generally 215 feet to the lower
end of the turning basin, increasing to 250 feet above the turning
basin to the mouth of the Paw Paw River, thence generally 110 feet
in the Paw Paw River to the mouth of the Benton Harbor Canal;
for dredging the channel in the Benton Harbor Canal up to the
west line of Ninth Street, a length of about 2,800 feet, to a depth
of 18 feet and width of 80 feet; for dredging a turning basin 18
feet deep on the north side of channel above the mouth of the Mor-
rison Channel; and that the turning basin near the mouth of the
Paw Paw River be eliminated from the project. The piers and
revetments are formed of stone-filled timber cribs and piling,
capped with concrete superstructure.
   The project depths are referred to low water datum for Lake
Michigan, which is 578.5 feet above mean tide at New York. The
fluctuations of water level are seasonal changes of about one-half
foot above or below the annual mean stage, and extreme fluctua-
tions of a temporary nature, due to wind and barometric pressure,
of about 11/2 feet above or below the mean lake level prevailing at
the time.
   The estimate of cost for new work (1954) is $472,000, exclusive
of amounts expended on previous projects. The latest (1954) ap-
proved estimate for annual cost of maintenance is $46,000.


          Sis 35--1087-1118
1088              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

The existing project was authorized by the following River and
Harbor Acts:

       Acts                         Work authorized                                        Documents


Mar. 3, 1875      Interior revetment   I1....   __.. ___________________   __... H. Ex. Doc. 160, 43d Cong., 2d sess.,
                                                                                 and Annual Report, 1875, pt. I,
                                                                                 p. 263.
June 14, 1880     Benton Harbor Canal 1-           -   -   ___ -___ - _ __- _ _.Annual
                                                           -                  .        Report,      1880, pp. 2030,
                                                                                2031, and 2049-2055.
Mar.    3, 1899   For present project dimensions of the piers and for a        H. Doc. 307, 55th Cong., 2d sess.,
                    turning basin.                                              and Annual Report, 1898, p. 2496.
Aug. 30, 1935     Present project dimensions of the channel and turn-          Rivers and Harbors Committee
                    ing basin, near mouth of Paw Paw River.                      Doc. 52, 74th Cong., 1st sess.
June 2, 19372     Abandonment of the easterly 1,000 feet of the canal
                   above the west line of 9th St.                                                                   1
Mar. 2, 1945      Turning basin above mouth of Morrison Channel                H. Doc. 129, 76th Cong., 1st sess.
                    and elimination of turning basin near mouth of
                    Paw Paw River.

  1 Completed under previous projects.
  2 Public 130, 75th Cong., 1st sess.
  3 Contains latest published map.


   Local cooperation. The act of March 2, 1945, provided that
local interests furnish, free of cost to the United States, all lands,
easements, and right-of-way and spoil disposal areas for the initial
work and for subsequent maintenance as required and hold and
save the United States free from claims for damages resulting
from the dredging of the turning basin just above the mouth of
Morrison Channel. Assurances of local cooperation were furnished
by the city of St. Joseph and were approved by the Chief of Engi-
neers on January 22, 1951.
   All prior requirements have been complied with.
   Terminal facilities. There are several wharves used for han-
dling coal, building materials, petroleum products, and miscellan-
eous commodities and one shipbulding yard. A package-freight
terminal is also available for use. While these facilties are gener-
ally adequate for existing traffic conditions, a public wharf open for
all on equal terms should be provided.
   Operations and results during fiscal year. Condition surveys
were made at a cost of $1,752, and miscellaneous inspections and
reports cost $676. Repair to 108 linear feet of north pier, in prog-
ress at the close of the previous fiscal year, was completed at a
cost of $14,634. Dredging 95,994 cubic yards of material, by hop-
per dredge for restoration of project depth in entrance channel
and 20,095 cubic yards by dipper dredge for restoration of project
depth in river channel, were accomplished at a cost of $28,069 and
$14,661, respectively. All work was performed by hired labor and
use of Government plant. The total cost was $59,792 for mainte-
nance.
   Condition at end of fiscal year. The project in effect prior to
the modification of March 2, 1945 was completed in 1938. No work
has been done on the last modification of the project providing for
a turning basin just above the mouth of the Morrison Channel.
The piers and revetments completed in 1904 are in generally good
condition except that a portion of the north revetment and pier
requires repairs. Dredging of the channel to existing project
depth was commenced in August 1938 and completed in October
             RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                             1089
1938. The controlling depths at low water datum at the close of
the fiscal year were 24 feet in the entrance channel; thence 21 feet
in the channel between the piers to Benton Harbor Canal and 17.3
feet in Benton Harbor Canal decreasing to 14.7 feet at Ninth
Street. The costs under the existing project were $366,683 for new
work and $1,251,119 for maintenance, a total of $1,617,802.
                                      Cost and financial summary

                                              Fiscal year ending June 30                      Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                               1950         1951         1952       1953            1954       priorto 19501


New work:
   Appropriated...-------------------------            ------------------------ $ 869,769
                                              ----------
   Cost-------                               -------------------- --
                         ----------------------                          ---------- 869,769
Maintenance:
    Appropriated --------
                 ...           $59,000      $30,000     $111,500      $63,000      $62,000           1,251,261
    Cost-----------------       59,792       30,204       90,828       85,649      2 58,147          1,251,243


  1Includes $503,113 for new work for previous projects.
  2 Operations and results during fiscal year $59,792, plus pending adjustment of $24; and less stock on hand
June 30, 1953 included in 1954 cost, in amount of $1,669.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project                               $_________________
                                                                         105,300

                         17. SOUTH HAVEN HARBOR, MICH.
   Location. Located on the east shore of Lake Michigan, distant
about 77 miles northeasterly from Chicago and about 24 miles
northerly from St. Joseph. (See U. S. Lake Survey Chart No. 76.)
   Previous projects. The original project was adopted by the
River and Harbor Act of March 2, 1867, and modified by the River
and Harbor Acts of June 14, 1880, August 2, 1882, and August 11,
1888. (For further details, see p. 1947 of Annual Report for 1915,
and p. 1473 of Annual Report for 1938.)
   Existing project. This provides for protecting the mouth of
Black River by two piers and revetments, 190 to 166 feet apart,
with lengths of 2,143 feet and 2,182 feet for the north and south
sides, respectively; for an entrance channel 21 feet deep to the
shore line; thence a channel 19 feet deep and 130 feet wide, ex-
tending up the river to a turning basin 375 feet wide and 19 feet
deep, located immediately below the Dyckman Avenue Bridge. The
length of entrance channel to the inner end of the piers is about
2,700 feet and in the river to the bridge 2,400 feet. The piers and
revetments are formed of stone-filled timber cribs and piling and
are capped with concrete.
   The project depths are referred to low water datum for Lake
Michigan, which is 578.5 feet above mean tide at New York. The
fluctuations of water level are seasonal changes of about one-half
foot above or below the annual mean stage, and extreme fluctua-
tions of a temporary nature, due to wind and barometric pressure,
of about 11/2 feet above or below the mean lake level prevailing at
the time.
   The estimate of cost of new work (1954) is $316,000, exclusive
of the amounts expended on previous projects. The latest (1954)
approved estimate for annual cost of maintenance is $35,000.
1090            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  The existing project was authorized by the following River ~ad
Harbor Acts:
    Acts                          Work authorized                                  Documents


Aug. 11, 1888   Channel from inner end of piers to highway bridge ..    No. prior survey or estimate.
Mar. 3, 1905    Present dimension of piers and for a turning basin.__   H. Doc. 119, 58th Cong., 2d seas.
Aug. 30, 1935   Present project dimensions of channel and turning       Rivers and Harbors Committee
                  basin.                                                  Doc. 9, 73d Cong., 1st sess.,' and
                                                                          unpublished review report of
                                                                          Chief of Engineers, dated Dec.
                                                                          21, 1934.


  1Completed    under previous projects.
  2 Contains latest published map.



   Local cooperation. The act of August 30, 1935, provided "that
no expense shall be incurred by the United States for acquiring of
any lands required for the purpose of this improvement." Accord-
ing to latest information, no land will be required, as enlargement
of the basin is not desired by local interests. All prior require-
ments have been complied with.
   Terminal facilities. These consist of several wharves used for
handling coal, building materials, wood pulp, fish, and miscellane-
ous commodities. The city has constructed a municipal wharf and
warehouse. The municipal wharf is leased to a private corpora-
tion which operates it in the interest of general commerce on like
terms for like service. The facilities are considered adequate for
existing commerce.
   Operations and results during fiscal year. Condition surveys
were made at a cost of $929, and miscellaneous inspections and re-
ports cost $68. The north pier was riprapped with 872 tons of
stone at a cost of $3,970. Dredging 63,130 cubic yards of material
with dipper dredge for restoration of project depth cost $34,585.
Completion of maintenance dredging with hopper dredge, in prog-
ress at the close of the previous fiscal year, cost $295. All Work
was done by hired labor and use of government plant. The total
cost was $39,847 for mainteance.
   Condition at end of fiscal year. The existing project is about 87
percent complete. The work remaining to be done consists of en-
largement of the turning basin, which is not now desired by local
interests. The present width of the turning basin is 260 feet. The
piers and revetments completed in 1913 are in generally good con-
dition, except that a portion of the north pier requires repairs.
Dredging of the channel and existing turning basin to existing
project depth, was commenced in May 1938, and completed in June
1938. The controlling depth at low water datum at the close of
the fiscal year was 21 feet in the entrance channel and 19 feet in
the channel between the piers and in the turning basin. The costs
under the existing project were $204,047 for new work and $944,-
640 for maintenance, a total of $1,148,687.
              RIVERS AND HARBORS-MILWAUKEE,                                    WIS., DISTRICT                       1091
                                        Cost and financial summary

                                                  Fiscal year ending June 30                               Total to June
                                                                                           -              30, 1954, inolud-
                                                                                                          ing fiscal years
                                 1950          1951          1952    {       1953      1       1954         prior to 1950

New work:
   Appropriated                                                                                                 $   391,280
   Cost                                                       -391                                                      280
Maintenance:
   Appropriated                 $140, 500      $42, 629      $1, 500         $29,200           $37,700           1,073,782
   Cost ...........              123, 902       65,061        1,368i          29,240           2 37,749          1,073,782

1 Includes $187,233 for new work and $131,239 for maintenance for previous projects.
2 Operations and results during fiscal year $39,847, less pending adjustment of $2,098.
Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project--     ___ __   _--- -------   $112,000

        18. SAUGATUCK HARBOR AND KALAMAZOO RIVER, MICH.
   Location. Located on the east shore of Lake Michigan, distant
about 90 miles northeasterly from Chicago and about 22 miles
northerly from South Haven. (See U. S. Lake Survey Chart No.
76.)
   Previous projects. The original project was adopted by the
River and Harbor Act of July 25, 1868, and modified by the River
and Harbor Act of July 11, 1870. For further details, see page
1947 of Annual Report for 1915, and page 1475 of Annual Report
for 1938.
   Existing project. This provides for an entrance channel be-
tween parallel piers, 200 feet apart, having lengths of 2,778 and
2,514 feet for the north and south piers, respectively, and for a
channel 16 feet deep and 100 feet wide, extending from that depth
in Lake Michigan to the mouth of the river, thence 14 feet deep, 90
feet wide, in the Kalamazoo River up to Saugatuck, a distance of
9,000 feet. The piers are formed of stone-filled timber cribs, and
piling and are capped with concrete except for the inner 276 feet of
the north revetment.
   The project depths are referred to low water datum for Lake
Michigan, which is 578.5 feet above mean tide at New York. The
fluctuations of water level are seasonal changes of about one-half
foot above or below the annual mean stage and extreme fluctua-
tions of a temporary nature, due to wind and barometric pressure,
of about 11/2 feet above or below the mean lake level prevailing at
the time.
   The cost for new work for the completed project was $274,295
exclusive of the amount expended on previous projects. The latest
 (1954) approved estimate for annual cost of maintenance is
$22,000.
   The existing project was adopted by the following River and
Harbor Acts:
       Acts                          Work authorized                          1                  Documents

June    3, 1896   Entrance channel, piers, and revetments                      IH: Doc. 192, 54th Cong., 1st sess.,
                                                                                  Annual Report, 1896, vol. 2, pt.
                                                                              1  5,p. 2739.
Mar     2 1907    Deepening entrance to 16 feet----------------                 Annual Report, 1907, p. 646.
June 25, 1910     Deepening channel in river to 14 feet ...-             .      H. Doc. 63,; 61st Cong., 2d sess.

  The latest published map is in H. Doc. 608, 64th Cong., Istsess.
1092              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Recommended modifications of project. Legislation authoriz-
ing the abandonment of the project has been recommended in
House Document No. 292, 65th Congress, 1st session.
   Local cooperation. None required.
   Terminal facilities. At the village of Saugatuck there are sev-
eral landing places for small vessels and one for commercial ves-
sels. At the village of Douglas there is a landing pier. The termi-
nal facilities are available for general use and are considered ade-
quate for existing commerce.
   Operations and results during fiscal year. Condition surveys
were made at a cost of $351, and miscellaneous inspections and re-
ports cost $78. The total cost was $429 for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1911. Pier construction and dredging between the piers
was completed in 1908; dredging in the river was completed in
1911. The piers and revetments are in generally good condition
except that a portion of the south revetment has failed and should
be rebuilt. The controlling depth at low water datum at the close
of the fiscal year was 13 feet in the channel between the piers and
9.7 feet in the river to Saugatuck. The costs under the existing
project were $274,295 for the new work and $606,939 for mainte-
nance, a total of $881,234.
                                           Cost and financial summary

                                                   Fiscal year ending June 30                   Total to June
                                                                                               30, 1954, includ-
                                                                                               ing fiscal years
                                    1950        1951          1952       1953       1954        prior to 19501

New work:
   Appropriated-         -.                                                                           $364,527
   Cost   ---                                          ---                      -   -364,527
Maintenance:
   Appropriated_-_ ---              $28, 500     $6, 500 _!........... $1,000        $1,350             725, 276
   Cost      ...-----------------    30,082       5,169 _ .... _        1, 137         2430             724,494


  1 Includes $90,232 for new work and $117,554 for maintenance for previous proicets.
  2 Operations and results during fiscal year $429, plus pending adjustment of $1.


                                    19. HOLLAND              HARBOR, MICH.
   Location. Located on the east shore of Lake Michigan, distant
about 95 miles northeasterly from Chicago and about 23 miles
southerly from Grand Haven.        (See U. S. Lake Survey Chart
No. 763.)
   Previous project. The original project was adopted by the
River and Harbor Act of August 30, 1852, and modified by the
River and Harbor Acts of June 23, 1866, March 3, 1873, March 3,
1879, July 5, 1884, and July 13, 1892. For further details see page
1948 of Annual Report for 1915, and page 1478 of Annual Report
for 1938.
   Existing project. This provides for protecting the outlet of the
channel from Lake Macatawa (formerly Black Lake) by two con-
verging breakwaters having lengths of 752 and 801 feet for the
north and south breakwaters, respectively, and with widths be-
tween them of 300 feet at the outer end and 740 feet at the inner
end; for inner piers and revetments along the channel from Lake
            RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                          1093
Macatawa about 180 feet apart, with lengths of 1,755 and 1,639
feet for the north and south piers, respectively; and for dredging a
channel 23 feet deep from that depth in Lake Michigan to a point
400 feet inside the entrance between the breakwaters, thence de-
creasing to 21 feet at the outer end of the inner piers, thence 21
feet between the inner piers and through Lake Macatawa to the
turning basin at Holland; for widening the turning basin to 600
feet, 21 feet deep within the channel limits and 18 feet deep outside
the channel limits, the width of channel being 300 feet through the
outer harbor, thence reducing from 140 feet to 110 feet between
the inner piers and revetments, thence increasing to 150 feet in
the channel in Lake Macatawa to the turning basin, the length of
the dredged channel, including that in the westerly end of Lake
Macatawa, being about 1 mile, and that in the easterly end of Lake
Macatawa, including the turning basin, being about 3 miles, the
total distance from the outer end of the channel to the wharves at
Holland being 5.5 miles. The breakwaters, piers and revetments
are built of stone-filled timber cribs and piling, all of which are
capped with concrete superstructure.
   The project depths are referred to low water datum for Lake
Michigan, which is 578.5 feet above mean tide at New York. The
fluctuations of water level are seasonal changes of about one-half
foot above or below the annual mean stage, and extreme fluctua-
tions of a temporary nature, due to wind and barometric pressure,
of about 1 1/ feet above or below the mean lake level prevailing at
the time.
   The cost of new work for the completed project was $452,402,
exclusive of amount expended on previous project. The latest
 (1954) approved estimate for annual cost of maintenance is
$30,000.
The existing project was authorized by the following River and
Harbor Acts:
     Acts                       Work authorized                                   Documents


Aug. 30, 1852   Artificial channel between Lake Macatawa and Lake     S. Ex. Doc. 42, 35th Cong., 1st sess.,
                  Michigan.'                                            p. 84.
Mar. 2, 1867    Piers and revetments     -:                           Annual Report, 1866, p. 106
Mar. 3, 1899    Extending inner piers__                               H. Doc. 272, 54th Cong., 2d sess.,
                                                                        and Annual Report, 1897, p. 2950.
Mar. 3, 1905    Converging breakwaters     -        -Annual                    Report, 1905, p. 2176.
July 3, 1930    Channel to Holland and a turning basin at Holland__   H. Doc. 588, 69th Cong. 2d sess.
Aug. 30, 1935   Present projectdimensions  of channels and turning    Rivers and Harbors Committee     2
                  basin.                                                Doc. 48, 74th Cong., 1st sess.


  1 Completed under previous projects.
2  Contains latest published map.


   Recommended modification of project. The Chief of Engineers
in House Document 282, 83d Congress, 2d session, recommends,
subject to certain conditions of local cooperation, modifications of
existing project to provide for (1) widening the bend in the
revetted entrance channel into Lake Macatawa from 130 to 235 feet
abreast the angle in the existing north revetment, by the construc-
tion of 1,020 feet of new revetment along the south side of the
widened channel and the removal of the old revetment and land
channelward of the new structure to a depth of 21 feet; and (2)
1094          REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

dredging a chanel in Black River 21 feet deep and 110 feet wide
extending 2,600 feet upstream from the existing turning basin
with suitable widening in the vicinity of its junction with the turn-
ing basin, and for widening the turning basin from 600 to 750 feet
at a depth of 18 feet and extending it upstream to join the new
river channel. The total estimated first cost as contained in the
document is $560,600 with an increase in the estimated cost of
annual maintenance of $5,700. The latest (1954) estimate of
first cost for this modification is $574,400.
   Local cooperation. None required.
   Terminal facilities. The wharves are located at the city of Hol-
land, at the inner end of Lake Macatawa, and are used for han-
dling coal, building materials, petroleum products, and miscel-
laneous commodities. Two shipbuilding yards are located on the
south shore of Lake Macatawa. The city of Holland has provided
a public wharf for small craft. These facilities are considered
adequate for existing commerce.
   Operations and results during fiscal year. Condition surveys
were made at a cost of $6,013 and miscellaneous inspections and
reports cost $597. Preliminary planning for future reconstruc-
tion of 493 lineal feet of north pier and revetment cost $21.
Dredging 50,941 cubic feet of material, with hopper dredge, was
accomplished at a cost of $16,895. All work was performed by
hired labor and use of Government plant. The total cost was
$23,526 for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1938. The breakwaters, piers, and revetments completed
in 1910 are in generally good condition except that portions of the
north pier and revetment require repairs. Dredging of the en-
trance channel to existing project depth, and the channel and
turning basin in Lake Macatawa was commenced in May 1938,
and completed in October 1938. The controlling depths at low
water datum at the close of the fiscal year were 21 feet in the
channel to Lake Macatawa, 20 feet in the inner channel in Lake
Macatawa to the wharves at Holland, and 18 feet in the turning
basin. The costs under the existing project were $452,402 for new
work and $920,606 for maintenance, a total of $1,373,008.
                                     Cost and financial summary

                                             Fiscal year ending June 30                      Total to June

                                          Sing                                                 fiscal years
                              1950         1951         1952         1953         1954       prior to 1950'

New work:
   MAinteae---------------------
   Appropriated.     ......                                                                ,022
                                       ----------- ---------------------------------- $ 629,022
                                  --..---------------..----.
              _    ...I .. ..... ... . .. .... .. .. ....
   Cost. ............                                                                   629 022
Maintenance:
   Appropriated-----...       $15, 000     $21, 000     $20, 000     $13,200      $23, 400        1,048,569
   Cost-----------------       17,471        10, 456     21, 800      12, 626     123, 520        1,048,198

  Includes $176,620 for new work and $127,598 for maintenance for previous projects.
2 Operations and results during fiscal year $23,526, less pending adjustment of $6.
       RIVERS AND HARBORS-MILWAUKEE,        WIS., DISTRICT   1095
    20. GRAND   HAVEN    HARBOR AND     GRAND   RIVER,   MICH.
   Location. The harbor is located on the east shore of Lake Mich-
igan, distant about 108 miles northeasterly from Chicago and
about 23 miles northerly from Holland. The river rises in Jack-
son County, Mich., and flows in a general westerly direction into
Lake Michigan, with a total length of about 260 miles. (See U. S.
Lake Survey Chart No. 765, and U. S. Geological Survey Grand
Rapids quadrangle.)
   Previous projects. The original project for the river was
adopted by the River and Harbor Act of March 3, 1881.        A new
project was adopted by the River and Harbor Act of June 3,
1896, and was modified by the River and Harbor Act of June 13,
1902. For further details, see page 1949 of Annual Report for
1915, and page 1481 of Annual Report for 1938.
   Existing project. This provides for protecting the mouth of the
river by piers and revetments, 415 feet apart at the entrance
diminishing to 390 feet inside, about 3,569 and 5,549 feet in
length for the north and south sides, respectively, and for a chan-
nel 23 feet deep and generally 300 feet wide and 1,500 feet long
from that depth in the lake to a point about 1,000 feet inside the
pier ends; thence 21 feet deep and 300 feet wide and 11/4 miles
long to the car-ferry slip, with an enlargement at the upper end;
thence 21 feet deep and 300 feet wide and 11/4 miles long from
the car-ferry slip to the Grand Trunk Railway bridge at Ferrys-
burg; with a turning basin 18 feet deep on the south side of the
channel just below that bridge; thence a channel 18 feet deep and
generally 100 feet wide to deep water in Spring Lake, a distance
of about 1,350 feet in the river and about 1,750 feet up the outlet
from Spring Lake; and for a channel in Grand River 8 feet deep
at low water datum, 100 feet wide and 14         miles long to Bass
River, the total length of river channel being about 171/2 miles.
The piers and revetments are built of stone-filled timber cribs and
piling, all of which are capped with concrete superstructure.
   The estimate of cost of new work (1954) is $1,003,400, exclu-
sive of amounts expended on previous projects. The latest (1954)
approved estimated for annual cost of maintenance is $103,000.
   The project depths are referred to low water datum for Lake
Michigan, which is 578.5 feet above mean tide at New York. The
fluctuations of water level in the harbor are seasonal changes of
about one-half foot above or below the annual mean stage, and ex-
treme fluctuations of a temporary nature, due to wind and baro-
metric pressure, of about 1     feet above or below the mean lake
level prevailing at the time.
1096                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

The existing project was authorized by the following River and
Harbor Acts:

        Acts                           Work authorized                                   Documents

June    23,   1866
June    14,   1880     iers andrevetments                                    S. Ex. Doc. 42, 35th Cong., 1st sess.,
Sept.   19,   1890          a    v      t      .     .     -ir.pp.                 89, 91.
July    13,   1892
July 3, 1930          Present project dimensions of the harbor channel to    S. Doc. 88, 71st Cong., 2d sess.l
                        Grand Trunk car-ferry slip and the river channel;
                       eliminating all of that portion of Grand River
                       above Bass River; consolidation of the projects for
                       the harbor and river.
Aug. 26, 1937         Channel to Spring Lake-_     ___ _______------         Rivers and Harbors Committee
                                                                               Doc. 1, 75th Cong., 1st sess. 1
Mar. 2, 1945          Present project dimensions of harbor channel from      H. Doc. 661, 76th Cong., 3d sess.
                      car-ferry slip to Grand Trunk Ry. bridge and the
                      turning basin.

  1 Contain latest published maps.


    Local cooperation. Fully complied with.
    Terminal facilities. In addition to a car-ferry slip, there are
several wharves used for handling coal, building materials, pe-
troleum products, fish, and miscellaneous commodities. The car-
ferry slip is not in use at present. The facilities are considered
adequate for existing commerce except that there should be a
public wharf in Grand Haven for transfer between rail and water.
    Operations and results during fiscal year. Condition surveys
were made at a cost of $6,722 and miscellaneous inspections and
reports cost $1,281. Reconstruction of 652 lineal feet of south
pier and 695 lineal feet of north pier, in progress at the close of
the fiscal year, cost $176,016 and $120,405, respectively. Dredg-
ing 122,910 cubic yards of material with hopper dredge, for
restoration of project depth in entrance and river channel, and
27,895 cubic yards with bucket dredge, for restoration of project
depth in turning basin on Grand River below Grand Trunk West-
ern Railway bridge, was completed at costs of $38,243 and $24,-
430, respectively. All work was performed by hired labor and
use of Government plant except for the reconstruction of the
south and north piers. The total cost was $367,097 for main-
tenance.
    Condition at end of fiscal year. The existing project is about 98
percent complete. The work remaining to be done consists of a
small amount of dredging on the northerly side of the inner chan-
nel at the point of land 1,350 feet upstream from the inner end of
the north revetment. This dredging cannot be done without re-
vetting the bank or endangering private cottages. The present
channel past this site, having at least width of 240 feet, is con-
sidered adequate for present and reasonably prospective com-
merce. The piers and revetments were completed in 1893 and are
in fair condition except that portion of the old timber crib piers
require repairs. Dredging of that portion of the channel between
the car-ferry slip and the Grand Trunk Railway bridge to a width
of 200 feet, was commenced in August 1930, and completed in
October 1930, with advanced funds. Dredging of the river above
the railway bridge to Bass River to existing project depth, was
             RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                           1097
commenced in April 1931 and completed in June 1931. Dredging
the channel into Spring Lake was commenced in September 1938
and completed in November 1938.
   Widening of the channel between the car-ferry slip and the
Grand Trunk Railway bridge to 300 feet and dredging the turning
basin on the south side of the channel just below that bridge were
commenced in October 1948 and completed in September 1949.
The controlling depths at low water datum at the close of the
fiscal year were 23 feet at the entrance; thence 21 feet between
the piers and in the river to the Grand Trunk Railway bridge, and
18 feet in the turning basin, and thence 8 feet to Bass River and
17 feet in the outlet from Spring Lake. The costs under the
existing project were $964,851 for new work and $3,112,893 for
maintenance, a total of $4,077,744.
                                      Cost and financial summary

                                              Fiscal year ending June 30                    Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                               1950         1951            1952     1953        1954         prior to 19501


New work:
                        -$7, 874 ------------------------
   Appropriated .....------                                                                      $1 276,180
    Cost-------------    -     114,206                                                             1---,276,180
Maintenance:
    Appropriated----.....      134,000     $114, 200    $231, 500   $301, 200   $471,900          .3426, 966
    Cost-- --------------       92,937      144,109      186, 432    148,284    2366, 828         3,126, 408

  lInicLdes $311,329 for new work and $13,427 for maintenance for previous projects.
  2Operations   and results during fiscal year $367,097, plus pending adjustment of $88; and less stock on
hand previous fiscal year transferred from project, $357.
Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project___ ___ -     -     ----        $-_____--
                                                                        $38,600

                             21. MUSKEGON HARBOR, MICH.
  :Location. This harbor is on the east shore of Lake Michigan,
distant about 114 miles northeasterly from Chicago and about 80
miles easterly from Milwaukee. (See (U. S. Lake Survey Chart
No. 767.)
   Previous projects. Adopted by the River and Harbor Act of
March 2, 1867, and modified by the River and Harbor Acts of June
10, 1872, June 23, 1874, August 2, 1882, September 19, 1890, August
18, 1894, March 3, 1899, and June 13, 1902. For further details, see
page 1950 of Annual Report for 1915; page 1399, Annual Report
for 1924; and page 1484, Annual Report for 1938.
   Existing project. This provides for an exterior basin in Lake
Michigan, formed by 2 arrowhead breakwaters, the south 1,514
feet and the north 1,404 feet long, 500 feet apart at the outer ends
diverging at an angle of about 90°, the inner ends connected with
the shore by suitable structures, 1,660 feet and 1,561 feet long on
the north and south sides, respectively; for the removal of 1,003
feet of the existing north pier and 1,106 feet of the existing south
pier; for repairing and maintaining the revetment around the old
car-ferry slip on the south side of the entrance channel; for
dredging channel 380 feet wide at the entrance, thence increasing
to 650 feet wide at a point about 300 feet inside the entrance,
thence decreasing toward the new pierheads to 500 feet wide and
1098            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

240 feet wide between the piers, with depths varying from 24 feet
at the harbor entrance to 21 feet at the shore line and in the inner
channel to Muskegon Lake, about 6,050 feet from the harbor en-
trance. The south breakwater and shore connection are built of
concrete caissons and piling capped with concrete; the north
breakwater is a rubble mound; the inner piers and revetments are
built of stone-filled timber cribs and piling, all having been capped
with concrete.
   The project depth is referred to low water datum for Lake Michi-
gan, which is 578.5 feet above mean tide at New York. The fluc-
tuations of water level are seasonal changes of about one-half foot
above or below the annual mean stage, and extreme fluctuations of
a temporary nature, due to wind and barometric pressure, of
about 11/2 feet above or below the mean lake level prevailing
at the time.
   The cost of new work, for the completed project was $1,900,922,
exclusive of amounts expended:on previous projects. The latest
 (1954) approved estimate for annual cost of maintenance is
$28,000.
   The existing project was authorized by the following River and
Harbor Acts:

    Acts                         Work authorized                                 Documents

June 13, 1902   Piers and revetments--.............. ........-.       H. Doc. 104, 56th Cong., 2d sess.
Mar. 3, 1925    Breakwaters and present project dimensions of chan-   H. Doc. 494, 67th Cong., 4th sess.
                 nel.
Aug. 30, 1935   Repairing revetment around car-ferry slip-    -_-_--...
                                                                  Rivers and      Harbors Committee
                                                                        Doc. 64, 74th Cong., 1st sess.
                                                                        (contains latest published map.)


   Local cooperation. Fully complied with.
   Terminal facilities. The main terminals are at the city of
Muskegon, at the inner end of Muskegon Lake, and include a car-
ferry slip, a large privately owned wharf equipped with warehouse,
transit shed, and cold-storage plant, and several wharves used for
handling coal, petroleum products, building materials, and miscel-
laneous commodities. There is also a sand wharf at the west end
of Muskegon Lake south of the inner end of the improved channel.
These facilities are considered adequate for existing commerce.
   Operations and results during fiscal year. Condition surveys
were taken at a cost of $2,000 and miscellaneous inspections and
reports cost $874. Repairing outer end of north rubble mound
breakwater cost $26,435 and riprapping south breakwater with
2,154 tons of stone cost $6,018. Dredging with hopper dredge,
completed in the previous fiscal year, involved an additional cost
of $80. All work was done by hired labor and use of Government
plant. The total cost was $35,407 for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1938. Construction of the south breakwater and shore
connection was commenced in May 1928 and completed in Decem-
ber 1930. The construction of the north breakwater and shore
connection and the removal of portions of the old piers were com-
                   .              'i::   '   ,: i ".."
                  RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                                                   1099
menced in June 1930, and completed in December 1931. Deepening
and widening of the entrance channel to existing project depth and
width, were commenced and completed in June 1932. Repairs to
the south revetment around the old car-ferry slip were commenced
in May 1938, and completed in October 1938. The outer 54 feet of
the south breakwater were removed in 1939, thereby increasing the
width between the outer ends of the breakwaters to 555 feet. The
south breakwater is therefore maintained for only a length of
about 1,460 feet. The breakwaters and shore connections are in
generally good condition except that the outer end of the north
breakwater requires repairs. The inner piers and revetments are
in fair condition.
   The controlling depths at low water datum at the close of the
fiscal year were 24 to 21 feet in the channel through the outer har-
bor and 21 feet between the inner piers to Muskegon Lake. The
costs under the existing project were $1,900,922 for new work and
and $718,162 for maintenance, a total of $2,619,084.
                                                     Cost and financial summary

                                                               Fiscal year ending June 30                               Total to June
                                                                                                                        30, 1954, includ-
                                                                                                                        ing fiscal years
                                            1950              1951        1952         1953                  1954        prior to 1950 1


New work:
     Appropriated -----------------------------------------
     Cost---"----------
Maintenance:
                                     ---                :
                                                   -------               ---
                                                                         ...
                                                                                            ------------------
                                                                                 ....--------------------.
                                                                                                                             $2,514,330
                                                                                                                                 514,3

     Appropriated-- .....-----$51,500                         $27,000     $15,500      $10,500               $32,200           1, 164,947
     Cost ------------- --     46, 867                         29, 581     13,914        9,388               235, 405          1,164,343

1   Includes $613,408 for new work and $446,183 for maintenance for previous projects.
2   Operations and results during fiscal year $35,407, less pending adjustment of $2.


                                      22. WHITE LAKE HARBOR, MICH.
   Location. On the east shore of Lake Michigan, about 120 miles
northeasterly from Chicago and about 45 miles southerly from
Ludington. (See U. S. Lake Survey Chart No. 768.)
   Existing project. This provides for the abandonment of the
old outlet and the creation of a new channel 16 feet deep, 200 feet
wide, and about 1,950 feet long from Lake Michigan to White Lake
between parallel piers and revetments having lengths of 1,717 feet
and 1,953 feet on north and south sides, respectively. The piers
and revetments are built of stone-filled timber cribs and piling, all
of which are capped with concrete superstructure. The project
depth is referred to low water datum for Lake Michigan, which is
578.5 feet above mean tide at New York. The fluctuations of
water level are seasonal changes of about one-half foot above or
below the annual mean stage and extreme fluctuations of a tem-
porary nature, due to wind and barometric pressure, of about 11/2
feet above or below the mean lake level prevailing at the time.
  The cost of new work, for the completed project, was $207,862.
The latest (1954) approved estimate for annual cost of mainten-
ance is $13,000.
1100             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  The existing project was authorized by the following River and
Harbor Acts:
     Acts                         Work authorized                                               Documents


Mar. 2, 1867
  lar. 5,
July      1873
       3, 1884   New channel, with piers and revetments--.....-----..
                                                   .             .                   Unpublished survey report of 1866.
July 13, 1892
Mar. 2, 1907     Present project depth of channel-.__         _--
                                                           ---------.                No prior survey or estimate:

  The latest published map is in H. Doc. 2053, 64th Cong., 2d sess.


   Local cooperation. None required.
   Terminal facilities. There is a coal wharf located about three-
fourths of a mile south of the village of Montague, at the inner end
of White Lake. Across the lake, at the village of Whitehall, there
are several wharves available for boats of shallow draft. These
facilities are considered adequate for existing commerce.
   Operations and results during fiscal year. Condition surveys
were made at a cost of $1,118 and miscellaneous inspections and
reports cost $127. Dredging 57,315 cubic yards of material, with
hopper dredge, for restoration of project depth in entrance chan-
nel, was accomplished at a cost of $32,492. All work was per-
formed by hired labor and use of Government plant. The total cost
was $33,737 for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1908. The piers and revetments were completed in 1900
and the dredging in 1908. The piers and revetments are in good
condition. The controlling depth at low water datum at the close
of the fiscal year was 16 feet in the entrance channel and between
the piers to White Lake. The costs under the existing project Were
$207,862 for new work and $585,734 for maintenance, a total of
$793,596.
                                      Cost and financial summary

                                               Fiscal year ending June 30                                    Total to June
                                                                        _                                    30, 1954, includ-
                                                                                                             ing fiscal years
                               1950           1951          1952                1953           1954            prior to 1950

New work:
   Appropriated_                          -                                 -----------                              $207, 862
    Cost-                         -                    -    --                                           -            207,862
Maintenance:
   Appropriated      -_        $9,000         $8, 500 -                           $3,500      $33,450                 585,854
    Cost         _    --        8, 837         9,187         .-                    3,093      1 33,734                585, 731


1 Operations and results during fiscal year $33,737, less pending adjustment of $3.


                           23. PENTWATER HARBOR, MICH.
  Location. On the east shore of Lake Michigan, about 146 miles
northeasterly from Chicago and about 14 miles southerly from
Ludington. (See U. S. Lake Survey Chart No. 77.)
  Existing project. This provides for widening the old entrance
                RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                             1101
channel to 150 feet between parallel piers and revetments, the
channel to extend from Lake Michigan to Pentwater Lake, with a
depth of 16 feet. The piers and revetments are built of stone-filled
timber cribs and piling, all of which have been provided with con-
crete superstructure.
   The project depth is referred to low water datum for Lake Michi-
gan, which is 578.5 feet above mean tide at New York. The fluc-
tuations of water level are seasonal changes of about one-half foot
above or below the annual mean stage and extreme fluctuations of
a temporary nature, due to wind and barometric pressure, of about
11/2 feet above or below the mean lake level prevailing at the time.
  The estimate of cost for new work (1954) is $245,000. The latest
(1954) approved estimate of annual cost of maintenance is $22,000.
   The existing project was authorized by the following River and
Harbor Acts:
    Acts                           Work authorized                                       Documents

Mar. 2, 1867
Mar. 3, 1873      Piers and revetments; dredging_----..   ....---------     H. Ex. Doc. 70, 39th Cong., 2d sess.
July 13, 1892
Mar. 2, 1907      Present project depth of channel-----------       -----   H.   Doc. 181, 59th Cong., 2d sess.


  The latest published map is in H. Doc. 303, 66th Cong., 1st sess.


   Recommended modificationsof project. The project was recom-
mended for abandonment in House Documents Nos. 429, 64th
Congress, 1st session, and 467, 69th Congress, 1st session.
   Local cooperation. None required.
   Terminal facilities. A number of small, privately owned
wharves are grouped at the west end of Pentwater Lake. These
facilities are considered adequate for existing commerce.
   Operations and results during fiscal year. Condition surveys
were made at a cost of $676 and miscellaneous inspections and re-
ports cost $48. All work was performed by hired labor and use
of Government plant. The total cost was $724 for maintenance.
   Condition at end of fiscal year. The existing project is about 78
percent complete. The work remaining to be done consists of con-
structing a 200-foot extension to the south pier which is not con-
sidered necessary under present conditions. The north pier and re-
vetment was completed in 1885 for a length of 2,226 feet and the
south pier and revetment in 1889 for a length of 1,847 feet. The
net length of the north pier and revetment is now 2,022 feet, 204
feet having been removed in 1931. Dredging of the channel was
completed in 1907. The piers and revetments are in fair condition.
The controlling depth at low water datum at the close of the fiscal
year was 5.9 feet in the entrance channel and 4.1 feet in the channel
between the piers to Pentwater Lake. The cost under the existing
project was $179,899 for new work and $539,377 for maintenance,
a total of $719,276.
1102        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY. 1954

                                   Cost and financial summary

                                              Fiscal year ending June 30                         Total to June
                                                                                      S30,          1954, includ-
                                                                                                ing fiscal years
                            1950            1951               1952      1953       1954          prior to 1950


    work:
NewAppropriated------------     -------------------------------..-----            ----...-              $179, 899
   Cost-------------------------------------------                                                       179,899
Maintenance:
   Appropriated.    --     $20,000         $30,865              $1,000   $2,300          $350            539,799
   Cost .          .------- 20,091          31,311               1,001    1,502           724            539,377


Other new work data: Estimated additional amount needed to be appropri-
ated for completion of existing project- - -    __-----------  --      $65,100

                         24. LUDINGTON                     HARBOR, MICH.
   Location. This harbor is located on the east shore of Lake
Michigan, distant about 156 miles northeasterly from Chicago and
about 67 miles northerly from Grand Haven. (See U. S. Lake Sur-
vey Chart No. 774.)
   Previous projects. The original project was adopted by the
River and Harbor Act of March 2, 1867, and modified by the River
and Harbor Acts of August 5, 1886, August 11, 1888, and March 3,
1899. For further details, see page 1951 of Annual Report for
1915, and page 1491 of Annual Report for 1938.
   Existing project. This provides for an exterior basin in Lake
Michigan, formed by 2 breakwaters, each with main arm 1,800 feet
long, 400 feet apart at the outer ends, diverging at an angle of 900,
and with shore connections, 1,103 feet and 2,004 feet in length for
north and south breakwaters, respectively; for the removal of the
outer end of inner piers; for dredging the exterior basin to a depth
of 18 feet; and for an inner channel about 2,000 feet long connect-
ing Pere Marquette Lake and Lake Michigan, the minimum navi-
gable width being 150 feet and depth of 18 feet. The breakwaters
and inner piers and revetments are built of stone-filled timber cribs
and piling, all of which are capped with concrete superstructure,
except for the inner 350 linear feet of the south revetment which
consists of steel sheet piling.
   The project depth is referred to low water datum for Lake Michi-
gan, which is 578.5 feet above mean tide at New York. The fluc-
tuations of water level are seasonal changes of about one-half foot
above or below the annual mean stage, and extreme fluctuations of
a temporary nature, due to wind and barometric pressure, of about
11/2 feet above or below the mean lake level prevailing at the time.
   The cost for new work for the completed project was $1,036,086,
exclusive of amount expended on previous project. The latest
 (1954) approved estimate for annual cost of maintenance is
$32,000.
               RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                                1103
The existing project was authorized by the following River and
Harbor Acts:
    Acts                          Work authorized                                         Documents


Mar. 2, 1867    Entrance piers.             ..------------------------------   A.
                                                                               Annual Report, 1867, p. 114.
Mar. 3, 1899    Pier extension reconstruction, and repairs to exist-           H. Doc. 273, 54th Cong., 2d sess.,
                 ing structures, and present project dimensions of              and Annual Report, 1897, p.
                 channel.                                                        2951.
Mar. 2, 1907    Breakwaters, shore connections, and removal of outer           H. Doc. 62, 59th Cong., 1st seas.,
                 ends of the 2 inside piers.                                    and Rivers and Harbors Com-
                                                                                mittee Doc. 3, 59th Cong., 2d sess.

The latest published map is in the Annual Report for 1914, p. 2974.


    Local cooperation. None required.
    Terminal facilities. In addition to the main terminal of the
Pere Marquette Railway Co., consisting of three car-ferry slips and
a wharf with warehouses, there are several wharfs used for han-
dling coal, building materials, and miscellaneous commodities.
These facilities are considered adequate for existing commerce.
    Operations and results during fiscal year. Condition surveys
were made at a cost of $2,072 and miscellaneous inspections and
reports cost $607. Repairs to 500 lineal feet of south breakwater,
in progress at the close of the fiscal year, cost $71,285. Break-
waters were riprapped with 995 tons of stone at a cost of $7,307.
Preparation of plans for future structure repairs cost $676. Dredg-
ing 32,172 cubic yards of material, with hopper dredge, was ac-
complished at a cost of $11,660. Dredging, with hopper dredge,
completed in previous fiscal year involved an additional cost of
 $524. All work was performed by hired labor and use of Govern-
ment plant, except for the repairs to 500 lineal feet of south break-
water. The total cost was $94,131 for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1918. Construction of the breakwaters was commenced
in 1908 and completed in May 1911. The construction of the shore
connections was commenced in 1912 and completed in November
1914. The dredging was completed in 1917, and the placing of ad-
dition stone as riprap in 1918. The breakwaters and shore connec-
tions and the inner piers and revetments are in generally good con-
dition except that the outer end of the north pier and a portion of
the south shore connection substructure are in poor condition and
require repairs. The outer 100 feet of the south breakwater were
removed by private interests in 1939, by authority of the Chief of
Engineers dated June 2, 1939, thereby increasing the width be-
tween the outer ends of the breakwaters to 475 feet. The south
breakwater is therefore maintained for only a length of about
1,700 feet. The controlling depths at low water datum at the
close of the fiscal year were 26 feet at harbor entrance, thence de-
creasing through the outer basin to 18 feet at lakeward end of the
inner piers and in the channel between the inner piers and revet-
ments to Pere Marquette Lake. The costs under the existing pro-
ject were $1,036,086 for new work and $1,372,456 for maintenance,
a total of $2,408,542.
1104          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                       Cost and financial summary

                                             Fiscal year ending June 30                     Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                                1950        1951        1952         1953        1954        priorto 19501


New work:
   Appropriated-------. ---------------        ---    --------- ------------ ------------        $1, 527,502
    Cost----------------------             ------------------- ------------ ------------           1,527, 502
Maintenance:
   Appropriated ....--------    $24, 000    $67, 000    $41, 500     $13,200    $133, 600          1,536,848
   Cost   -----------            24, 311     68,933      39,520       15, 726    294, 066          1, 498,842

1 Includes $491,416 for new work and $126,451 for maintenance for previous projects.
2 Operations and results during fiscal year $94,131, less pending adjustment of $65.
                                                                                            .

                               25. MANISTEE            HARBOR,       MICH.
    Location. On the east shore of Lake Michigan, distant: about
179 miles northeasterly from Chicago and about 26 miles northerly
from Ludington. (See U. S. Lake Survey Chart No. 776.)
    Previous projects. Adopted by the River and Harbor: Acts of
March 2, 1867, June 10, 1872, March 3, 1873, March 3,:1875, Au-
gust 14, 1876, September 19, 1890, July 13, 1892, March 2, 1907,
and June 25, 1910. For further details, see page 1952 of Annual
Report for 1915, and page 1493 of Annual Report for 1938.
    Existing project. This provides for an entrance channel 23 feet
deep, 570 feet wide, 1,600 feet to the outer end of the south pier;
thence 21 feet deep between the piers and in the river, 250 to 220
feet wide for a distance of 2,000 feet; and thence with a minimum
width of 100 feet from the inner end of the north revetment to
Manistee Lake, about 6,400 feet. The project also provides for a
south breakwater having a main arm 1,300 feet long and a shore
connection 1,185 feet long, north pier and revetment 2,797 feet
long, and south pier and revetment 770 feet long. The breakwater,
shore connection, and north pier are built of stone-filled timber
cribs and piling and are capped with concrete superstructure. The
south pier and revetment consists of steel sheet piling with stone
fill in pier.
    The project depths are referred to low water datum for Lake
Michigan, which is 578.5 feet above mean tide at New York. The
fluctuations of water level are seasonal changes of about one-half
foot above or below the annual mean stage, and extreme fluctua-
tions of a temporary nature, due to wind and barometric pressure,
of about 11/2 feet above or below the mean lake level prevailing at
the time.
   The estimate of cost for new work (1954) is $762,300, exclusive
of amount expended on previous projects. The latest (1954) ap-
proved estimate for annual cost of maintenance is $33,000.
                  RIVERS AND HARBORS-MILWAUKEE, WIS.; DISTRICT                                          1105
The existing project was authorized by the following River and
Harbor Acts:
       Acts                         Work authorized                                     Documents


Mar. 2; 1867 Entrance piers----------------------....           _            Annual Report, 1867, p. 115.
Sept. 19, 1890 Extending the channel 8,000 feet to connect with              Annual Report, 1891, p. 2678.
                Manistee Lake, and further pier extension.
July 25, 1912 Depth of 20 feet in the outer harbor, 570 feet wide to         H. Doc. 599, 62d Cong., 2d sess,
                    outer end of south pier and 18 feet deep in the river;
                    south breakwater with shore connection; and ex-
                     tension of north pier if required.
July    3, 1930    Present project dimensions of the channel through         S. Doc. 131, 71st Cong., 2d sess.
                    outer basin and channel in the river.
Mar. 2, 1945       Removal of old south revetment; construction of new       H. Doc. 380, 77th Cong., 1st sess.
                    south pier and revetment; and widening river en-           (Contains latest published map.)
                    trance channel.


    Local cooperation. The act of July 3, 1930, provided "that no
work shall be undertaken on the section of the river through and
above the bridges until they have been modified in a manner satis-
factory to the Secretary of War." The Smith Street Bridge and
the railroad bridge have been rebuilt, but the Maple Street High-
way Bridge has not been rebuilt.
    All other requirements have been complied with.
    Terminal facilities. There is a Government wharf and a private
sand wharf on the north side of the river and a package-freight
wharf: with warehouse and a coal wharf on the south side. Indus-
tries on Manistee Lake have wharves used for handling coal, salt,
building materials, and pulpwood. The city has provided a wharf
on the south side of the river for general public use. The facilities
are 6oisidered adequate for existing commerce.
    Operations and results during                          fiscal
                                           year. Condition surveys
were made at a cost of $1,915 and miscellaneous inspections and
reports cost $479. The outer end of the north pier was repaired
at a cost of $64,239. Construction of stone wing wall along the
south pier involved the placement of 1,006 tons of stone at a cost
of $12,205. Dredging 49,694 cubic yards of material, with hopper
dredge, was accomplished at a cost of $13,413. Dredging, with
hopper: dredge, completed in previous fiscal year involved an addi-
tional cost of $828. All work was performed by hired labor and
use of Government plant. The total cost was $93,078 for main-
tenance.
    Condition at end of fiscal year. The existing project is about 98
percent complete. The work remaining to be done consists of
dredging the river to protect dimensions from about 800 feet below
Maple Street Highway Bridge to Manistee Lake. This cannot be
done until Maple Street Bridge has been rebuilt and until a large
part of the river banks are revetted by private interests. The
north pier and revetment, completed in 1893, the south breakwater
and shore connections, completed in 1920, and the south pier and
revetment, completed in 1950, are in generally good condition. Pile
clusters should be placed along the north pier for protection from
vessels. Dredging of the outer basin and the river channel to a
point about 800 feet below Maple Street Bridge to existing project
depth was commenced in October 1939 and completed in May 1940.
Removal of old south revetment, construction of new south pier
 1106            REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

and revetment, and widening otheof     river entrance channel was
commenced in June 1949 and completed in June 1950. The control-
ling depths at low water datum at the close of the fiscal year were
23 feet in the outer basin, and in the channel between the piers,
thence 21 feet in the river to Manistee Lake. The costs under the
existing project were $745,774 for new work and $923,521 for
maintenance, a total of $1,669,295.
                                               Cost and financial summary

                                                     Fiscal year ending June 30                         1 Total to June
                                    i                           1952
                                                                  __       __!                           30, 1954, includ-
                                                                                                         ing fiscal years
                                        1950        1951        1952             1953       1954           prior to 1950'

New work:
    Appropriated                        $17, 874   -$9, 094     -$2, 489    _ -
                                                                            --                                $1, 100,773
     ost----.........                   260, 015    -1, 918 -     __                                           1, 100, 773
Maintenance:
    Appropriated .......                 35, 000      2,000      20,500          $59,100    $57, 000            1, 076, 127
    Cost........-----------------        40,682       1,922      21,979           19,795    2 71, 170           1,073,130


  1Includes $354,999 for new work and $150,910 for maintenance forprevious projects.
  2 Operation and results during fiscal year $93,078, less pending adjustment of $1,301; less stock on hand
June 30, 1953 included in 1954 costs, $20,607.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project____________________________ $16,500

26, PORTAGE                LAKE HARBOR OF REFUGE,                                       MANISTEE          COUNTY,
                                        MICH.
   Location. On the east shore of Lake Michigan, distant about
186 miles notheasterly from Chicago and about 37 miles northerly
from Ludington. (See U. S. Lake Survey Chart No. 777.)
   Existing project. This provides for a harbor of refuge, with an
entrance channel from Lake Michigan to Portage Lake, 300 feet
wide and 18 feet deep, protected by stone-filled timber crib and pile
piers and revetments. The piers and revetments have been pro-
vided with concrete superstructure.
   The project depth is referred to low water datum for Lake Michi-
gan, which is 578:5 feet above mean tide at New York. The fluctua-
tions of water level are seasonable changes of about one-half foot
above or below the annual mean stage, and extreme fluctuations of
a temporary nature, due to wind and barometric pressure, of about
1/2 feet above or below the mean lake level prevailing at the time.
   The cost for new work for the completed project was $256,129.
The latest (1954) approved estimate for annual cost of main-
tenance is $12,000.
   The existing project was authorized by the River and Harbor
Act of March 3, 1879 (Annual Report for 1879, p. 1634). The
latest published map is in House Document No. 588, 64th Congress,
1st session.
  Recommended modifications of project. Legislation authorizing
the abandonment of the project for this harbor is recommended in
House Document No. 588, 64th Congress, 1st session.
   Local cooperation. None required.
    Terminal facilities. There are inexpensive landing places at the
                RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                                                                   1107

inner end of Portage Lake. The facilities are considered adequate
for existing commerce.
   Operations and results during fiscal year. Condition surveys
were made by hired labor and the use of Government plant at a
total cost of $559 for maintenance.
   Condition at end of fiscal year. The existing project was sub-
stantially completed in 1912. The piers and revetments were com-
pleted in 1901. The dredging was completed in 1812 except for a
small amount of hard material in the inner half of the channel.
The piers and revetments are in good condition. The controlling
depth at low water datum at the close of the fiscal year was 8.8 feet
at the harbor entrance and 11 feet in a channel about 100 feet wide
between the piers to Portage Lake. The costs under the existing
project were $256,129 for new work and $461,311 for maintenance,
a total of $717,440.
                                               Cost and financial summary

                                                                 Fiscal year ending June 30                                            Total to June
                                                                                                                                      30, 1954, includ-
                                                                                                                                      ing fiscal years
                                    1950                      1951                1952                   1953          1964            priorto 1950


New work:
     Appropriated .                                 ---                    -------              -         ---      -----------                $256, 129
     Cost-----------------         -------------------.................        -----------------------                        -----            256, 129
Maintenance:
   Appropriated--------........     $18, 500                -$1,506         ............ $2,000 .....-----                                     461,635
     Cost-----------------            17,599                          262 --------           ---           1,118          $559                 461,311



                                  27. FRANKFORT                                HARBOR,                     MICH.

   Location. This harbor is on the east shore of Lake Michigan,
distant about 204 miles northeasterly from Chicago and about 28
miles northerly from Manistee. (See U. S. Lake Survey Chart No.
77.)
   Existing project. This provides for an exterior basin in Lake
Michigan, formed by two breakwaters, 450 feet apart at the outer
ends, diverging at an angle of about 90 °, the main arm and the
shore conection on the north breakwater being 972 and 1,000 feet in
length, respectively, and the main arm and the shore connection of
the south breakwater being 1,188 and 1,400 feet in length, re-
spectively; for the removal of 801 feet of the north and 1,172 feet
of the south pier; dredging the basin 20 feet deep and 800 feet
wide at the entrance, decreasing toward the new pierheads to 600
feet wide; dredging the channel between the piers 18 feet deep to
Lake Betsie (Aux Becs Seies) ; and dredging to a depth of 18 feet,
to within 50 feet of existing structures, that area in Lake Betsie
west of the east boundary of Fifth Street extended. The break-
waters and shore connections are built of concrete caissons and
piling capped with concrete. The inner piers and revetments are
built of stone-filled timber cribs and piling, all having been capped
with concrete, except for 251 feet of the south revetment which
consists of steel sheet piling.
  The project depth is referred to low water datum for Lake Michi-
gan, which is 578.5 feet above mean tide at New York. The fluctu-
ations of water level are seasonal changes of about one-half foot
1108              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

above or below the annual mean stage, and extreme fluctuations of
a temporary nature, due to wind and barometric pressure, of about
1/2 feet above or below the mean lake level prevailing at the time.
   The cost for new work for the completed. project was $1,741,827.
The latest (1954) approved estimated annual cost of maintenance
is $24,000.
   The existing project was authorized by the following River and
Harbor Acts : .

       Acts                           Work authorized                                  Documents

June 23, 18661I    A new outlet of 12 feet deep protected by piers and     H. Doc. 482, 55th Cong., 2d sess.
Mar. 3, 1925      'Exterior   breakwaters, removal of portions of piers,
                    and for present project dimensions of channel.
                                                                           H. Doc. 208, 68th Cong., 1st sess.

Aug. 26, 1937      Dredging the area in Lake Betsie__---------------       H. Doc. 511,.. 74th Cong., 2d sess.:

  I   Amended 1868, 1879, and 1892.
  2 Contains latest published map.

   Local cooperation. Fully complied with.
   Terminal facilities. The railroad terminal, consisting of two
car-ferry slips, is on the south side at inner end of the entrance
channel. There are also several fishing wharves. The city has con-
structed a wharf on the north side of Lake Betsie available for
boats of shallow draft, The facilities are considered adequate fbor
existing commerce.
   Operations and results during fiscal year. Condition surveys
were made at a cost of $2,977 ard miscellaneous inspection and re-
ports cost $358. The breakwaters were riprapped with 2,790 tons
of stone at a cost of $17,530. All work was performed by hired
labor and use of Government plant. The total cost was $20,865 for
maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1939. Construction of the south breakwater and shore
connection, removal of a portion of the south pier, and dredging of
the south half of the channel to existing project depth, were com-
menced in May 1928, and completed in October 1931. The north
breakwater and shore connections, removal of a portion of the
north pier and dredging the remainder of the channel, to existing
project depth, were commenced in April 1932, and completed in
October 1932. Dredging of the area in Lake Betsie was commenced
in May 1939, and completed in July 1939. The breakwaters, shore
connections, and revetments are in generally good condition; the
inner piers require repairs. The controlling depths at low water
datum at the close of the fiscal year were 22 feet at harbor en-
trance, thence decreasing through the outer basin to 20 feet at
lakeward end of the inner piers and thence 18 feet in the channel
between the inner piers and revetments to Lake Betsie. The depth
over the dredging area in Lake Betsie was 16.8 feet. The costs
under the existing project were $1,741,827 for new work and
$693,722 for maintenance, a total of $2,435,549.
              RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                                    1109
                                           Cost and financial summary


                                                 Fiscal year ending June 30                            Total to June
                                                                                                      30,1954, includ-
                                                                                                      ing fiscal years
                                    1950        1951        1952              1953         1954        priorto 1950


New work:
   Appropriated ----------------------------                .   ------------------------                    $1, 741,827
   Cost      -----       -- --------------------------------------------------------                         1,741,827
Maintenance:
    Appropriated,-.......          $66, 500     $33, 500    $4, 500            $3, 300     $21, 100            697, 155
    Cost--------... -------         26,084       80,007      1, 494             2,977      1 18,634            691,491

1 Operation and results during fiscal year $20,865, less pending adjustment of $2,231.

                                   28. LELAND HARBOR, MICH.
    Location. This harbor is on the east shore of Lake Michigan at
the mouth of Carp (Leelanau) River, Mich., distant about 240 miles
northeasterly from Chicago and about 40 miles northerly from
Frankfort. (See U. S. Lake Survey Chart No. 705.)
    Existing project. This provides for the removal of the wrecked
outer portions of the old privately owned piers; for the construc-
tion of new piers converging from shore to an entrance 60 feet
wide, the lengths to be 370 and 440 feet for the north and south
piers, respectively; and for an entrance channel 6 feet deep and 40
feet wide, the inner end of channel being about 300 feet inside of
the harbor entrance. The new piers are built of piling filled with
stone.
    The project depth is referred to low water datum for Lake Michi-
gan, which is 578.5 feet above mean tide at New York. The fluc-
tuations of water level are seasonal changes of about one-half foot
above or below the annual mean stage, and extreme fluctuations of
a temporary nature, due to wind and barometric pressure, of about
11/2 feet above or below the mean lake level prevailing at the time.
    The cost for new work for the completed project was $64,181.
The latest (1954) approved estimate for annual cost of maintenance
is $7,000.
    The existing project was authorized by the River and Harbor Act
of August 30, 1935 (Rivers and Harbors Committee Doc. 23, 74th
Cong., 1st sess.). The latest published map is in the project docu-
ment.
    Local cooperation. None required.
    Terminal facilities. There are privately owned wharves on each
side of the inner harbor extending from the dam, located about 400
feet above the mouth of the river, for a distance of about 200 feet
downstream, used principally by the local fishing interests and to
some extent by Government mail, Coast Guard, and lighthouse
boats. All available dockage space is utilized.
   Operations and results during fiscal year. Condition surveys
were made at a cost of $559 and miscellaneous inspections and re-
ports cost $8. All work was performed by hired labor and use of
Government plant. The total cost was $567 for maintenance.
1110                    REPORT OF CHIEF OF ENGINEERS. U. S. ARMY. 1954

   Condition at end of fiscal year. The existing project was com-
pleted in 1937. Construction of the converging piers, removal of
the outer portions of the old privately owned piers, and dredging of
the entrance channel were commenced in September 1936, and com-
pleted in June 1937. The upper portions of the converging piers
require repairs. The remaining portions of the private piers are in
poor condition. Prior to the work done by the Government the
harbor had been built and maintained entirely by local interests.
Carp River, about 4,000 feet long, connects Leelanau Lake with
Lake Michigan. There is a concrete dam with a 10-foot head about
400 feet above the river mouth. The controlling depths at low
water datum at the close of the fiscal year were 10.1 feet at en-
trance, reducing thence to 3.1 feet at the inner end of the channel
through outer harbor, and 1.0 feet in river to the dam. The costs
under the existing project were $64,181 for new work and $77,279
for maintenance, a total of $141,460.
                                                       Cost and financial summary

                                                                Fiscal year ending June 30                                Total to Jun
                                                                                                                         30, 1954, includ-
                                                                                                                         ing fiscal years
      --   -    -
               -~-- -   -   -       -      -   1950
                                                ----       -   1951    ----   1952           1953
                                                                                             ---    -
                                                                                                              1954   -
                                                                                                                           priorto 1950
                                                                                                                         igfsa      er




New work:
   Appropriated __- '                   ..........
                                                 -                                     ---               --                       $64, 181
   Cost-.---                -       .64,                                                                                                 181
Maintenance:
   Appropriated-.....t                     .     - .. |        -$192   .        ..------------ 37, 800          $450               78,552
   Cost-           -        -   -                $644             287 -.        - -          36,411            1566                77,279

I Operation and results during fiscal year $567, less pending adjustment of $1.

                                29. TRAVERSE CITY HARBOR, MICH.
   Location. On the south end of the West Arm of Grand Traverse
Bay, distant about 45 miles southwesterly from Charlevoix and 92
miles northerly from Frankfort. (See U. S. Lake Survey Chart
No. 706.)
   Existing project. This provides for dredging a basin, 600 feet
wide and 1,000 feet long, with depth of 14 feet in the outer 500 feet
of the area and 10 feet in the remainder, protected by a breakwater
about 1,300 feet in length, on the west side of the West Arm about
11/4 miles north of the city limits.
   The project depth is referred to low water datum for Lake Michi-
gan, which is 578.5 feet above mean tide at New York. The fluctua-
tions of water level are seasonal changes of about one-half foot
above or below the annual mean stage, and extreme fluctuations of
a temporary nature, due to wind and barometric pressure, of about
21/2 feet above or below the mean lake level prevailing at the time.
   The cost for new work for the completed project was $239,557.
The latest (1954) approved estimate for annual cost of main-
tenance is $3,500.
   The existing project was authorized by the River and Harbor
Act of June 30, 1948 (H. Doc. 546, 80th Cong., 2d sess.). The
latest published map is in the project document.
   Local cooperation. Fully complied with.
  Terminal facilities. Elmwood Township, Leelanau County, has
            RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                                1111
provided a wharf open to all on equal terms. There are 2 privately
owned coal wharves, 2 privately owned wharves for the receipt of
petroleum products, and a small municipal yacht harbor beyond the
limits of the existing project. The facilities are considered ade-
quate for existing commerce.
   Operations and results during fiscal year. Condition surveys
were made at a cost of $848 and miscellaneous inspections and re-
ports cost $19. All work was performed by hired labor and use of
Government plant. The total cost was $867 for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in August 1951. Construction of the breakwater commenced
inMay 1950 and was completed in August 1951. Dredging of the
mooring basin commenced in August 1950 and was completed in
December 1950. The controlling depths at low water datum at the
close of the fiscal year were 14 feet in the outer half of the basin
and 10 feet in the inner half. The costs under the existing project
were 239,557 for new work and $2,029 for maintenance, a total
of $241,585.
                                     Cost and financial summary

                                           Fiscal year ending June 30                           Total to June
                                                                                                30, 1954, includ-
                                                                                                ing fiscal years
                              1950        1951        1952         1953              1954         prior to 1950

New work:
   Appropriated_  __    $245, 000        -$1, 730     -$3, 713 --........
                                                                        -           --                  $239, 557
                         114,175
   Cost....----------------               117,441        7,941                                           239,557
Maintenance:
   Appropriated._.----        .......--
                                    . .          ......             $2,000               $750              2,750
   Cost--------.... ---....                                          1,162i              866               2,028


1Operation and results during fiscal year $867, less pending adjustment   of $1.


                         30. CHARLEVOIX HARBOR, MICH.
   Location. On the east shore of Lake Michigan, distant about
276 miles northeasterly from Chicago and about 75 miles northerly
from Frankfort. (See U. S. Survey Chart No. 789.)
   Existing project. This provides for a channel 18 feet deep from
that depth in Lake Michigan to that depth in Lake Charlevoix pro-
tected where needed by piers and revetments. The piers at the en-
trance are formed of stone-filled timber cribs and rubblestone, being
781 feet and 452 feet in length on north and south sides, respec-
tively. The entire south pier and the outer 303 feet of the north
pier have been provided with concrete superstructure. The revet-
ments are built of piling and are capped with concrete.
   The project depth is referred to low water datum for Lake Michi-
gan, which is 578.5 feet above mean tide at New York. The fluctua-
tions of water level are seasonal changes of about one-half foot
above or below the annual mean stage, and extreme fluctuations of
a temporary nature, due to wind and barometric pressure, of about
11/2 feet above or below the mean lake level prevailing at the time.
   The cost for new work for the completed project was $82,223. The
latest (1954) approved estimate of cost for annual maintenance is
$15,000.
1112            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

The existing project was authorized by the following River and
Harbor Acts:
    Acts                          Work authorized                                   Documents


Aug. 14, 1876   Channel from Lake Michigan to Round Lake, pro-          S. Ex. Doc. 16, 44th Cong., 1st
                 tected where needed by piers and revetments.             sess., and Annual Report, 1876,
                                                                          p. 523.
Aug. 2, 1882    Channel from Round Lake to Lake Charlevoix-.....        No prior survey or estimate.
June 13, 1902   Project depth increased to 15 feet --------------------     Do.
June 20, 1938   Project depth increased to 18 feet-- ----.   ---------  S. Doc. 163, 75th Cong. 3d sess.
                                                                          (Contains latest published map.)



   Local cooperation. None required.
   Terminal facilities. These consist of several small landing
places in Round Lake at Charlevoix used for handling fish and mis-
cellaneous commodities. The city of Charlevoix has provided a
public wharf south of the inner end of the lower south revetment.
A wharf for receipt of petroleum products is located on the west
end of Lake Charlevoix. There are coal wharves at Advance and
Boyne City at the inner end of Lake Charlevoix. The city of Boyne
City has provided a public wharf for small craft. These facilities
are considered adequate for existing commerce.
   Operations and results during fiscal year. Condition surveys
were made at a cost of $1,419 and miscellaneous inspections and
reports cost $91. The reconstruction of 196.5 lineal feet of south
revetment was accomplished at a cost of $67,234. All work was
performed by hired labor and use of Government plant. The total
cost was $68,744 for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1939. The north pier and revetment of the lower channel
were completed in 1880, and the south pier and revetment in 1889.
The revetments of the upper channel were completed in 1885.
Dredging of both channels to existing project depth, was com-
menced and completed in August 1939. The north revetment of the
upper channel has been entirely removed, a portion being removed
in 1928 and the remainder in 1930. The piers and revetments of
the lower channel and the south revetment of the upper channel
are in fair condition. The controlling depths at low water datum
at the close of the fiscal year were 18 feet in the lower channel to
Round :Lake and in the upper channel to Lake Charlevoix. The
costs under the existing project were $82,223 for new work and
$473,467 for maintenance, a total of $555,690.
                                       Cost and financial summary

                                              Fiscal year ending June 30                      Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                                1950         1951         1952        1953         1954        priorto 1950

New workI
   Appropriated----------------------                   ----------      ------                        $ 82, 223
                                                                                                     .....
   Cost---------------- ----------- -----------          -     ----     -----------------               82, 223
Maintenance:
                 ...--
   Appropriated---          $11, 000     -$688             $1000        $4,100      $68,750            474, 725
   Cost ....                  9,435       1,805               501        3,348     1!69,031            473,754


  1Operations   and results during fiscal year $68,744, plus pending adjustment of $287.
                RIVERS AND HARBORS-MILWAUKEE, WIS., DISTRICT                                                   1113
                         31.   INACTIVE           NAVIGATION                PROJECTS

                                                                           Cost to June 30, 1954
                                                           For last                                        Estimated
                     Name of project                     full report                                         amount
                                                         see annual                  Operations            required to
                                                         report for-   Construction     and                 complete
                                                                                    maintenance

                                5                           1920                  -     -      $63, 000        (3 )
  1.   Arcadia Harbor, Mich.__________________                         _   ____ __ _
2.    Big Suamico River, Wis.' _____________-
                                   -___                     1951              $20, 243           19, 450       (3)
3.    Cedar River Harbor, Mich.' 2_!                       1896               28,464                        6 $409, 500
4.    Gladstone Harbor, Mich.' 2                           1912                7,281                252        (3)
5.    Gray's Reef Passage, Mich. :-                 -      1937              109, 521 ...--------------       (3)
6.    Harbors at Washington Island, Wis.'     .......      1950               62,838             1, 143       6 71, 000
7.    Pensaukee Harbor, Wis.'_---------------_          -1951                 34, 035           22,460        (3)
8.    Petoskey Harbor, Mich.'1             - -             1896              118, 239           91, 666       (3)
9.    South Milwaukee Harbor, Wis.2 4____________          1906                5,000       - -       -         578, 000
10.    St. James Harbor (Beaver Island), Mich. 7            1952                                              68 38,000
11.    St. Joseph River, Mich.' 2-....-                     1923                4,555            5,195         (3)


   1Channels adequate for commerce.
   2 Abandonment recommended in 1926 (H. Doc. 467, 69th Cong., 1st sess.).
   3 Completed.
   4 No commerce reported.
   5 Abandonment recommended in 1916 (H. Doc. 668, 64th Cong., 1st sess.).
   6 Revised in 1954.
   7 Assurances of local cooperation requested Mar. 3, 1945. Negotiations for compliance are in progress.
   8 Exclusive of $7,500 to be contributed by local interests.


                               32. GENERAL INVESTIGATIONS
  Examinations and surveys. All work under this heading is for
the Milwaukee and Duluth Districts. The features included are
Flood Control Studies, Navigation Studies, Beach Erosion Coop-
erative Studies, and Miscellaneous Studies. The total costs during
the fiscal year were $26,6801. The balance unexpended of $5,5172
will be applied to completing studies under way at end of fiscal
year. A total of $64,600 additional funds can be profitably ex-
pended during fiscal year 1955.
   Collection and study of basic data. The cooperative stream
gaging program cost $2,400. The precipitation studies cost $2,400.
There were no funds expended on fish and wildlife studies or beach
erosion development studies. Miscellaneous studies cost a total
of $1,637.

       33. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
   Small flood control projects not specifically authorized by Con-
gress. (Section 212 of the 1950 Flood Control Act.)
   A design memorandum was prepared in connection with proposed
work for flood protection on the Oconto River at Oconto, Wiscon-.
sin. The work proposed consists of dredging at a total estimated
cost of $138,500. The report was completed on June 29, 1954. The
total costs, all for new work, were $3,892.




  1Includes $5,603 contributed funds.
  2 Includes $3,797 contributed funds.
1114         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                      Cost and financial summary

                                            Fiscal year ending June 30              Total to June
                                                                                   30, 1954, includ-
                                                                                   ing fiscal years
                               1950        1951        1952        1953   1954       prior to 1950

New work:
   Appropriated - -_---- __             ._                                $4,000             $4,000
   Cost_                       -
                          _------      _-_
                                      ---_--  __-
                                           --..................
                                                         ---_.....         3,892              3,892


Other new work data: Estimated additional amount needed to be appropriated for
  completion of existing project____________ ..
1 Project not yet approved.
  IMPROVEMENTS OF RIVERS AND HARBORS IN THE
            CHICAGO, ILL., DISTRICT

   This district comprises southeastern Wisconsin, northeastern
and central Illinois, and portions of northwestern Indiana and
southwestern Michigan included in the drainage basin of the Illi-
nois River above the south boundary of the Federal property at
the new LaGrange lock and dam, exclusive of the basin of Bureau
Creek, Ill. It also includes the southern end of Lake Michigan and
its tributary drainage basins from the southern boundary of Wis-
consin to the drainage basin of the St. Joseph River, Mich., and
the waterways connecting the Illinois River with the Chicago and
Calumet Rivers.
                                   IMPROVEMENTS

               Navigation                         Flood Control--Continued
                                      Page                                       Page
1. Waukegan Harbor, Ill             1115       drainage and levee districts,
                                   1117
2. Chicago Harbor, Ill ..............        Ill.                             1142
                                                  River, Ill-------...............
                                   1120 11. Coal Creek drainage and levee
3. Chicago River, Ill...................
4. Calumet Harbor & River, Ill. &            district, Ill. River, Ill ....   1143
                                                                         _____..
                 ...........
      Ind-.............__   .......1122 12. Mouth of Sangamon River, Ill 1144
                                   1125 13. Beardstown, Illinois River, Ill__1145
5. Indiana Harbor, Ind..................
6. Michigan City Harbor, Ind .....1128 14. Pekin-La Marsh drainage and
                                    1130
7. Illinois Waterway, Ill. & Ind....                                            1146
                                                levee district, Ill. River, Ill....
8. Inactive navigation projects 1140 15. Upper Mississippi River basin,
                                                                   - __.... 1147
                                            Chicago District ...-.-..-..
                                      16. Inactive flood control projects.. 1148
             Flood Control            17. General investigations.....-------- 1148
                                      18. Inspection of completed flood
                                 1140
9. Farm Creek, Ill-.. .. .............     control works .........   ..      1149
10. Lacey, Langellier, West Ma-       19. Flood control workunder special
      tanzas and Kerton Valley              authorization.......--......1149

                       1. WAUKEGAN           HARBOR,   ILL.
   Location. This harbor is on the west shore of Lake Michigan,
distant about 51 miles south of Milwaukee and about 38 miles
north of Chicago. (See U. S. Lake Survey Chart No. 74.)
  Previous project. An appropriation was made by the River and
Harbor Act of August 30, 1852, for a breakwater. This work was
abandoned. The original project was adopted by River and Harbor
Act of June 14, 1880, and modified by River and Harbor Act of
August 2, 1882. For further details, see page 1940 of Annual Re-
port for 1915, and page 1508 of Annual Report for 1938.
  Existing project. This provides for-
  a. A northerly exterior breakwater, about 1,900 feet long ex-
tending easterly from the shore 1,030 feet, and thence southeast-
erly 870 feet to the outer end, forming a protected outer harbor.
   b. Parallel piers from the outer harbor to an inner basin, about
240 feet apart and 1,613 and 3,212 feet long for the north and south
piers, respectively, the inshore end of the south pier diverging
southward opposite the inner basin.
   c. An entrance channel 390 feet wide and 22 feet deep, extending
                                                                        1115
1116              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

from that depth in the lake to the outer end of the north pier,
reducing to a channel between piers 200 feet wide and 18 feet
deep to the inner basin, an inner basin 18 feet deep, about 1 3 acres,
protected on the east side by a revetment 882 feet long, and an
anchorage area 8 feet deep, about 6 acres, in the southwest corner
of the inner basin.
   The project depth is referred to low water datum for Lake Mich-
igan, which is 578.5 feet above mean tide at New York. , The fluc-
tuations of water level are seasonal changes of about one-half foot
above or below the annual mean stage, and extreme fluctuations of
a temporary nature, due to wind and barometric pressure, of about
11/ feet above or below the mean lake level prevailing at the time.
   The estimated cost of new work, revised in 1954, is $591,000, ex-
clusive of amounts expended on previous projects, and excluding
$20,000 (cost of bulkhead and boat stalls) to be contributed by
local interests. The latest (1954) approved estimate for annual
cost of maintenance is $25,000, on completion of the project.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                         Work authorized                                         Documents

June 14, 1880     Parallel piers and basin   -                .
                                                        -....-....       .....   Annual Report, 1880, p. 1942.
Aug.    2, 1882   Modified location of harbor entrance 1-_           _           Annual Report, 1882, pp. 277, 2163.
June 13, 1902     Detached breakwater, extension of piers, increasing            H. Doc. 343, 56th Cong., 1st sess.
                   width of harbor at inner end of north pier, and
                   dredging channel and basin to existing project
                   depth.
July    3, 1930   Extension of breakwater to shore, dredging near the            Rivers and Harbors Committee
                   outer end of the north pier, and enlarging the inner            Doc. 27, 71st Cong., 2d sess.
                   basin.                                                                                          5
Mar. 2, 1945      Dredging an entrance channel to existing project               H. Doc. 116, 77th Cong., 1st sess.
                   dimensions from the outer end of the north pier to
                   the project depth in the lake, and dredging an
                    anchorage area in the southwest corner of the inner
                    basin to the existing project depth. Abandonment
                    of dredging the triangular area in the southwest
                    corner of the inner basin to a depth of 18 feet.

  1 Completed under previous projects.
  2Contains latest published map.

   Local cooperation. The act of March 2, 1945, provided that
dredging of the anchorage basin shall not be commenced until
local interests furnish assurances to the Secretary of War that
they will remove the abandoned water intake pipes; construct an
adeauate bulkhead in front of the city park and in front of the
adjacent United States property; furnish, free of cost to the United
States, the land necessary for the anchorage area; release the
United States from all claims for damages resulting from the im-
provement and provide and maintain adequate mooring facilities.
Local interests were informed of requirements on July 1, 1946.
Permit authorizing construction of the required bulkhead was is-
sued by Department of the Army on August 25, 1948, and com-
pliance with the remaining requirements is anticipated on comple-
tion of the bulkhead.
   Terminal facilities. There are four commercial docks. The
most important cargoes handled are coal and iron and steel prod-
ucts.         In addition, there are two publicly owned docks, one of
                   RIVERS AND HARBORS--CHICAGO, ILL., DISTRICT                                                               1117
which is owned by the city and is used for fishing, and the other
is owned by the United States Government and used exclusively
by the Corps of Engineers. The city dock is considered adequate
for existing commerce.
   Operations and results during fiscal year. Condition surveys,
inspections and reports were conducted by hired labor at a cost
of $6,474. Stone placement for breakwater repair was performed
by contract at a cost of $16,348. The total costs for the fiscal year
were $22,822, all maintenance.
   Condition at end of fiscal year. The existing project is 92 per-
cent complete. The work remaining to be done to complete the
project consists of dredging to provide an anchorage area in the
southwest corner of the inner basin. The north pier and east re-
vetment (completed in 1904) are in fair condition and the south
pier (completed in 1909) is in good condition. The outer 600 feet
of breakwater (completed in 1904). and the shore-arm extension
 (completed in 1931) are in good condition except for deterioration
at the outer end. The controlling depths are 18.6 feet in the en-
trance channel to the outer end of the south pier, over a channel
250 feet wide measured from the south channel; and 18.1 feet in
the remaining portion of the entrance channel and inner basin,
except for minor shoals along edges of the channel. Depths are
based on soundings taken in June 1954, and are referred to low-
water datum. The mean-water level in June 1954, was 3.03 feet
above, datum.
   The total costs of the existing project to June 30, 1954, were
$1,579,184 of which $536,758 was for riew work and $1,042,426
for maintenance.
                                         Cost and financial summary

                                                   Fiscal year ending June 30                                         Total to June
                                                                                                                     30, 1954, includ-
                                                                                                                     ing fiscal years
                                  1950            1951                    1952            1953           1954         priorto 1950 1

New work:
   A ppropriated    . . ...                       ..............                      _
                                                                                 ......... ...........          ..         $ 754,991
   Cost-----                                 ..        ....        ....      -------------.          .                        754, 991
Maintenance:
   Appropriated          -.       $76, 500         $5, 000                $5, 000         $26, 800       $22, 800           1, 058,137
   Cost-    --       -        -   96,178            3, 742                 6, 502          26,835         22, 822           1,058,137


1 Includes $218,233 for new work and $15,711 for maintenance for previous projects.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project ___________________ $54,000

                                   2. CHICAGO                      HAIRBOR, ILL.
   Location. Northeastern Illinois, near the southern end of Lake
Michigan; 85 miles in a southerly direction from Milwaukee, Wis.
 (See U. S. Lake Survey Chart No. 752.)
   Previous projects. Adopted by River and Harbor Act of March
2, 1833, and modified by River and Harbor Acts of June 23, 1866,
March 2, 1867, July 1, 1868, and April 10, 1869. Work was con-
tinued under these projects until 1870. (For further details, see
p. 1941 of Annual Report for 1915, and p. 1510 of Annual Report
for 1938.)
1118              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Existing project. This provides for the following work:
   a. An inner breakwater, all of timber cribs, enclosing an inner
basin of about 224 acres in extent, the breakwater being in two sec-
tions, as follows: The main inner breakwater 4,036 feet long with
300 feet of shore return on north end; a southerly extension 2,550
feet long.
   b. An exterior breakwater enclosing an outer basin of about 970
acres in extent, the breakwater being in three sections, exclusive of
gaps, as follows: The shore extension at north end built of timber
cribs and 2,250 feet long; the main exterior breakwater, built of
timber cribs and 5,413 feet long; and the southerly extension, built
of rubble mound and concrete caissons and 5,000 feet long, exclu-
sive of the harbor entrance gap of 500 feet.
   c. Maintenance dredging to a depth of 21 feet of that part of the
inner basin lying north of a line drawn eastwardly perpendicular
to the eastern boundary of Grant Park, from the northern end of
said boundary, and also of the entrance to Chicago River from the
lake to Rush Street over a width varying from 470 to 190 feet.
   d. Maintenance of that section of the north pier, 900 feet long,
located east of the entrance to Ogden slip.
   The project depth is referred to low water datum for Lake Mich-
igan, which is 578.5 feet above mean tide at New York.
   Seasonal fluctuations in mean stage from low water in winter to
high water in summer average about 1.2 feet. Local and tem-
porary fluctuations of 0.1 to 0.5 foot, due to wind and difference
in barometric pressure, occur daily. Seiches of 3 to 4 feet occur at
infrequent intervals.
   The cost for new work for the completed project was $3,409,844,
exclusive of amounts expended on previous projects. The latest
 (1954) approved estimate of annual cost of maintenance is
$50,000.
The existing project was authorized by the following River and
Harbor Acts:

       Acts                            Work authorized                                    Documents


July 11, 1870     Inner breakwaters and inner basin.          ---------------- H.sess.,
                                                                                   Ex. Doc. 114, 41st Cong., 2d
                                                                                        and Annual Report, 1879,
                                                                                pp. 1562-1567.
June 14, 1880     Exterior breakwater_------.....-.........   ---    ___-      Annual Report, 1879, pp. 1562-1567.
Mar. 3, 1899      Present project depth in the basin, and entrance to          Annual Report, 1897, pp. 2790-2791.
                    Chicago River.
July 25, 1912     Shore-arm and southerly extension of the exterior            H. Doc. 710, 62d Cong., 2d sess.
                    breakwater.
Mar.    2, 1919   Modification of the area to be dredged in the inner          H. Doc. 1303, 64th Cong., Ist seas.
                    basin.
Mar.    3, 1931   Shore-arm extension of the exterior breakwater trans-        Public, 797, 71st Cong.
                    ferred to Lincoln Park Commissioners.
Mar.    2, 1945   Resumption of jurisdiction over the shore-arm exten-         Public 14, 79th Cong.
                    sion breakwater and over certain navigable waters
                    in Lake Michigan which lie in the northwestern
                    part of the outer harbor.


  The latest published map of this harbor is in the Annual Report
for 1914. opposite page 2,924.
             RIVERS AND HARBORS--CHICAGO, ILL., DISTRICT       1119
    Local cooperation. Fully complied with.
    Terminal facilities. There are 32 docks for handling various
types of cargo. The most important cargoes handled are coal,
overseas package freight, and newsprint. Passenger excursion
steamers are served by 6 of these 32 docks. There is 1 privately
owned marine service mooring and 2 yacht club docks. The city
of Chicago owns 5 docks, none of which are used for commercial
purposes at the present time. The United States Government has
6 docks; 2 are used by the Coast Guard, 2 by the Navy, and 2 by
the Corps of Engineers.
    Operations and results during fiscal year. Condition surveys,
inspections and reports, were conducted by hired labor at a cost of
 $11,091. Repairs to the shore-arm extension of the exterior break-
water, and to the inner breakwater, were suspended. Twelve
percent of the work is completed. Repairs to stone protection-
exterior breakwater were performed by contract, at a cost of
 $41,079. The total costs for the fiscal year were $52,170, all
maintenance.
    Condition at end of fiscal year. The existing project was com-
pleted in 1923. The entrance to Chicago River has been improved
by the construction of parallel entrance piers, and dredging of a
channel 190 to 470 feet in width, and a depth of 21 feet below
datum. The northerly arm of the inner breakwater (timber 4,034
feet, with 304 feet of shore return on the north end, completed in
1875; concrete superstructure completed in 1934) is in good con-
dition. The southerly arm (timber 2,544 feet, completed in 1880;
concrete superstructure completed in 1930) is in fair condition.
The exterior breakwater (timber 5,418 feet, completed in 1889;
concrete superstructure completed in 1930), the southerly exten-
sion (rubble mound 2,227 feet, completed in 1917), and the south
arm (rubble mound 1,532 feet, completed in 1920; and concrete
caisson 1,185 feet, completed in 1922) are in fair condition. The
shore-arm extension (timber 2,250 feet, completed in 1917) has
deteriorated above the water line. Repairs are in progress and by
June 30, 1952, approximately 61 percent of the deteriorated por-
tion was replaced by a concrete superstructure. The north pier
 (concrete superstructure, 975 feet, completed in 1908 and repaired
in 1949) is in good condition. The controlling mid-channel depth
from the west end of the lock near the mouth of the Chicago River,
to the Michigan Avenue bridge, is 21 feet. Depths are based on
soundings taken in December 1952, and are referred to low-water
datum. The mean water level, lakeward of the lock, in June 1954
was 3.03 feet above datum. The water level landward of the lock
is controlled, the level being maintained at an elevation lower than
that of Lake Michigan except during excessive storm runoff.
   The total costs of the existing project to June 30, 1954, were
$5,942,649 of which $3,409,844 was for new work and $2,532,805
for maintenance.




     Sig 36-1119.1150
1120           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                     Cost and financial summary              ..                          .
                                               Fiscal year ending June 30                    Total toJune
                                                                                             30, 1954, ffiiclud-
                                                                                             ing fiscal.years
                              1950            1951         1952       1953        1954         priorto 1950

New work:
   Appropriated . ...-                                                                   -        1$3, 855, 849
   Cost---------------------              -          -                                              3,855, 849
Maintenance:
   Appropriated.. - - - -    $300, 500    $413, 000        $8, 000    $53, 005    $15, 000           2,787,406
   Cost----------_  --        220,421 1    170,961         42,407      57,107      52,170            2,532, 805


1 Includes $446,005 for new work for previous projects.


                                 3. CHICAGO RIVER, ILL.
  Location. Cook and Lake Counties, Ill., the navigable portions
being wholly in Cook County and the city of Chicago. (See U.: S.
Lake Survey Chart No. 752.) For description, see page 1467 of
Annual Report for 1932.
  Previous projects. Adopted by the River and Harbor Act of
June 3, 1896, modified by acts of March 3, 1899, and June 13, 1902.
For further details, see page 1942 of Annual Report for 1915, and
page 1513 of Annual Report for 1938.
  Existing project. This provides for maintenance dredging to 21
feet below the hydraulic grade line, corresponding to low water
datum ,in Lake Michigan, of the main river from Rush Street to
the junction of the North and. South Branches. (0.7 mile),:                                             'the
North Branch from the junction to North Avenue (2.22 miles),
the North Branch Canal:(1.04 miles), and the North Branch tiurn-
ing. basin; the channels, and turning basins to be maintained, to
project depth to within 20 feet ofexisting docks. It also provides
for dredging a channel 9 feet: deep. to within 30 feet of existing
bulkheads and river banks, from North Avenue to Belmont Av-
enue,. thence 9 feet.deep and 50 feet wide to Addison Street. The
wdh.of channel in the main river varies from 200 to 300 feet,: in
North Branch from 50 to 150 feet, and in North Branch Canal
froi 70 to 110 feet..
   All fdepthsare referred to low water datum for Lake Michigan,
which is 578.5 feet abovemean tide at New York, with due. al-
lowance for hydraulic grade resulting from the drainage canal.
   The.estimate of cost for new work, revised in 1954, is $585,000,
exclilsiV eof amount expended on previous project. The latest
 (1954) approved estimate of annual cost of maintenance is
$46,000.
                  RIVERS AND HARBORS-CHICAGO, ILL., DISTRICT                                               1121
  The existing project was authorized by the following River and
Harbor Acts:
    Acts                            Work authorized                                        Documents 1

Mar. 3, 1899    For project depth of 21 feet in lieu of that fixed by act       Specified in act.
                  of June 3, 1896.
June 13, 1902   Turning basins___....________________________................       Do.
Mar. 2, 1907    Interpreted by Chief of Engineers, Apr. 11, 1908, as            H. Doc. 95, 56th Cong., 1st sess.
                 adopting the new work of the then existing project               (Annual Report, 1900, p. 3863,
                  for 21-foot depth.,                                             and Annual Report, 1909, p. 709.)
Mar. 2, 1919    Eliminated all work, except maintenance of the main             H. Doc. 1294, 64th Cong., 1st sess.
                  river, North Branch, North Branch Canal, and
                 turning basin.                                                                                     2
July 24, 1946   Dredging channel 9 feet deep to within 30 feet of ex-           H. Doc. 767, 78th Cong., 2d sess.
                 isting bulkheads and river banks from North Ave.
                 to Belmont Ave., thence 9 feet deep and 50 feet wide
                 to Addison St.

   The latest published map is in the Annual Report for 1914, opposite p. 2928.
2 Contains latest published map of the North Branch above North Ave.


   Recommended modifications of project. On February 28, 1949,
the Chief of Engineers recommended modification of the existing
project for Chicago River, Ill., to provide for a channel 9 feet deep
and 50 feet wide in the North Branch of Chicago River and North
Shore Channel between Addison Street, Chicago, and Main Street,
Skokie, with three passing places 45 feet wide and 500 feet long,
in accordance with the plans of the district engineer, at an es-
timated cost to the United States of $776,000 for new work and
$16,500 annually for maintenance in addition to the amount now
required, subject to certain requirements of local cooperation.
   Local cooperation. The act of July 24, 1946, provided that the
improvement of the channel is subject to the condition that local
interests furnish assurances satisfactory to the Secretary of the
Army that they will hold and save the United States free from
damages which may result from construction and maintenance of
the improvement. The above requirement has not been complied
with.
   Terminal facilities. There are 58 docks handling lake vessel
and river barge cargoes. The most important cargoes handled are
sand and gravel, coal, salt, cement, and petroleum products. There
are 4 boatyards, 3 of which are used for servicing recreational
craft and 1 engaged- in constructing and servicing small craft as
well as small Navy vessels. The city of Chicago owns 2 docks
which are not used for commercial purposes at this time. The
United States Government has 2 docks which are used by the Corps
of Engineers exclusively.
  SOperations and results during fiscal year. Condition surveys,
inspections and reports, were conducted by hired labor at a cost
of $15,894. The total costs for the fiscal year were $15,894, all
maintenance.
   Condition at end of fiscal year. The project is complete except
for the work authorized by the River and Harbor Act of: July 24,
1946. The controlling mid-channel depths are as follows: In the
main river, 21.0 feet; in the North Branch to North Avenue, 21.0
feet; North Avenue to Addison Street, 10.0 feet; and in the North
Branch Canal, 18.7 feet. Depths in the turning basin are generally
21.0 feet or more Depths are based upon soundings taken in
1122           REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

January, February, May, and June 1953 and are referred to low-
water datum. The water level in the Chicago River is controlled,
the level being maintained at an elevation lower than that of Lake
Michigan, except during excessive storm run-off into the river.
The heads of navigation for deep-draft vessels are Belmont Avenue
on the North Branch, and Leavitt Street on the West Fork of the
South Branch, 5.97 and 5.52 miles, respectively, from Michigan
Avenue Bridge. The head of navigation for barge traffic is near
Touhy Avenue on the North Shore Channel, about 11 miles from
the Michigan Avenue Bridge.
   The total costs of the existing project to June 30, 1954, were
$1,941,675 of which $544,679 were for new work, and $1,396,996
for maintenance.
                                        Cost and financial summary

                                              Fiscal year ending June 30                     Total to June
                                                                               __           30, 1954., nclud-
                                                                                            ing fiscal years
                                1950         1951       1952         1953        1954         prior to 1950

New work:
   Appropriated -__                                                                               $1,500, 565
   Cost---------------                 ------------------------------------------------            1,500,565
Maintenance:
   Appropriated-   _       _i   $203,000     $ 7 000    $10,000     $151,425     $10, 500          1,506, 910
           _ ---
   Cost------          -         199,784      10.259      9,981      145,599      15, 894          1, 506,459


1Includes $955,886 for new work and $109,463 for maintenance for previous projects.
Other new work data: Estimated additional amount needed to be appropri-
ated for completion of existing project      -_
                                              ___    ___    __          $40,000

            4. CALUMET                 HARBOR AND RIVER, ILL. AND IND.
   Location. Northeastern Illinois (Cook County), near the south-
ern end of Lake Michigan, 121/2 miles south of Chicago Harbor,
and known on the Great Lakes as South Chicago Harbor. it being
in the southerly part of and within the corporate limits of the city
of Chicago, except for a part of the breakwaters and of the an-
chorage behind same, which are in Indiana The Calumet River
is within the Chicago city limits. (See U. S. Lake Survey Chart
No. 75.) For description, see page 1471 of Annual Report for 1932.
   Previous projects. The original project for Calumet Harbor
was adopted by River and Harbor Act of July 11, 1870, and modi-
fied August 11, 1888. Work was continued under these projects
until 1896.
   The original project for Calumet River was adopted by River
and Harbor Act of July 5, 1884, and modified August 5, 1886. For
further details, see page 1943 of Annual Report for 1915, and page
1515 of Annual Report for 1938.
   Existing project. This provides for the following work:
   a. For an outer harbor protected by a breakwater extending
eastward from the shore about 4,400 feet and thence southeasterly
about 8,100 feet to the harbor entrance.
   b. For an approach channel 3,200 feet wide and 28 feet deep
through the shoals outside the breakwater.
  c. For an outer harbor channel and anchorage area 3,000 feet
wide and 26 feet deep.
                  RIVERS AND HARBORS-CHICAGO, ILL., DISTRICT                                        1123
   d. For an entrance channel to the river 350 feet wide and 26 feet
deep to the Elgin, Joliet & Eastern Railway bridge.
   e. For a channel in Calumet River of 200-foot minimum width,
25 feet deep to the Semet-Solvay wharf near 111th Street, thence
23 feet deep through the rock section to near 114th Street, thence
21 feet deep to 122nd Street, and thence 21.5 feet deep to and in-
cluding turning basin No. 5.
   f. For widening and straightening the river channel, except
through the rock cut, to within 20 feet of bulkhead lines now or
hereafter established.
   g, For five turning basins spaced along the river channel, of
suitable size for turning the largest lake cargo vessels, and each of
the same depth as the adjacent channel.
   The project depths are referred to low water datum for Lake
Michigan, which is 578.5 feet above mean tide at New York.
   Fluctuations in stage of the river are practically those resulting
from changes of water level in Lake Michigan. On Lake Michi-
gan, seasonal fluctuations in mean stage from low water in winter
to high water in summer average about 1.2 feet. Local and tem-
porary fluctuations of 0.1 to 0.5 feet, due to wind and difference
in barometric pressures, occur daily. Seiches of 3 to 4 feet occur
at infrequent intervals.
   The estimate of cost for new work, revised in 1954 is $11,447,-
000, exclusive of amounts expended on previous projects. The
latest (1954) approved estimate of annual cost of maintenance
is $115,000.
   The existing project was adopted by the following River and
Harbor Acts:

     Acts                         Work authorized                                    Documents


                  MI                                                     Annual Report, 1896, pp. 2584, et
June 13,19029 Outer harbor protected by breakwater                 i seq., and H. Doc. 277, 54th Cong.
                                                                  I 1st sess.
Mar. 3, 1905 5 turning basins....___________________________._      H. Doc. 172, 58th Cong., 2d seas.
June 25, 1910 Provided for shape and dimensions of turning basins. H. Doc. 349, 60th Cong., 1st sess,
Sept. 22, 1922   Consolidated the 2 projects for Calumet Harbor and
                  Calumet River.                                                                              2
Aug. 30,1935'    Detached breakwater; dredging the outer harbor to       H.   Doc. 494, 72d Cong., 2d sess.
                  existing project depth and dimensions; deepening
                  river-entrance channel and river to existing project
                  depths; widening and straightening the river chan-
                  nel; deepening the 5 turning basins to the same
                  depth as the adjacent channel.                                                              2
Mar. 2, 1945     Provide an approach channel to the harbor 3,200 feet    H. Doe. 233, 76th Cong., 1st sess.
                  wide and 28 feet deep through the shoals outside
                   the breakwater and for closing the existing gap
                  between the breakwaters.

I Included in Public Works Administration program Sept. 6, 1933, and Dec. 16, 1933.
2 Contains latest published maps of the river.
3 Contains latest published map of the harbor.


  Local cooperation. The act of March 3, 1905, required, as a
condition precedent to Federal expenditures upon any 1 of the 5
turning basins, the donation to the United States of the land neces-
sary for that turning basin. As a result the land needed for turn-
ing basins 1, 3, and 5 was conveyed to the United States. The total
area thus conveyed is 17.85 acres, and the value of the land at
the time of its conveyance was approximately $35,700.
1124     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   The act of August 30, 1935, provided that the widening of the
channel at any locality, or the future excavation of a turning
basin, shall not be commenced until local interests have furnished,
free of cost to the United States, the lands or easements necessary
for such widening or excavation, and have either provided any
necessary bulkheads, or have released the United States from
all damages to adjacent lands by reason of the excavation.
   The Republic Steel Corp. has dredged a new turning basin on
the east side of the Calumet River just north of 122d Street, to
replace the original turning basin 3, and has constructed a bulk-
head along the channel side of the original basin 3, and reclaimed
the area to provide land for plant expansion. The corporation has
also built a bulkhead along two portions of the east side of the
river between a point opposite the Semet-Solvay slip and the new
turning basin 3, and has widened and deepened the east side of the
rock section between the United States east channel line and its
bulkhead. The United States has widened and deepened two por-
tions of the east side of the river between the south end of the
rock section and turning basin 3, mile 4.7. Local interests donated
the necessary land for the widening.
   Terminal facilities. There are 42 docks handling lake vessel
and river barge cargoes. The most important cargoes handled are
iron ore, grain, coal, limestone, sand and gravel, iron and steel
products, and miscellaneous package freight. There are 2 boat-
yards, 1 for repairs to large lake vessels (this yard has 2 large
drydocks), and the other boatyard has 1 floating drydock for re-
pairing and building commercial river craft. The United States
Government owns one dock which is used by the Corps of: Engi-
neers only. There are no other publicly owned docks on the Calu-
met River, except for the one reserved for the exclusive use of
the one city of Chicago fireboat.
   Operations and results during fiscal year. Maintenance: Con-
dition surveys, inspections, reports, and flue dust investigations
were conducted by hired labor at a total cost of $44,131. Stone
protection for breakwater repair was performed by contract, at a.
cost of $16,817. The total costs for the fiscal year were $60,948,
all maintenance.
                                            -done
   Condition at end of fiscal year. The existing project is 52 per-
cent complete. The work remaining to be             to complete the
project consists of the construction of turning basins 2 and 4;
dredging portions of the outer harbor; deepening, widening, and
straightening the Calumet River; dredging an approach channel
to the harbor through the shoals outside the detached breakwater;
and closing the gap between the breakwaters. The timber[ break-
water (6,712 feet, was completed in 1904; concrete superstructure
was completed in 1924) is in fair condition. The cellular type
steel-sheet pile breakwater (5,007 feet, was completed in 1935)
is in good condition. Under permit from the Secretary of War,
the Youngstown Sheet & Tube Co. and its predecessors have re-
moved all of the south pier (completed in 1897) and replaced it
with a concrete dock wall 2,961 feet in length and 50 feet south-
erly. of thepier's original location. Under permits from the De-
partment, the: Defense Plant Corporation has built two sections
                  RIVERS AND HARBORS-CHICAGO, ILL., DISTRICT                                                     1125

of bulkhead on the east side of the river between a point opposite
the Semet-Solvay slip and the new turning basin 3 at mile 4.7.
The United States has widened and deepened the channel adjoin-
ing the new bulkhead except along the rock section, where the
widening was done by the corporation. Depths in the outer har-
bor vary from 21 to 28 feet. Controlling mid-channel depth in the
entrance channel is 22.5 feet. The controlling mid-channel depth
in the river is 19.0 feet, up to and including turning basin 5.
Depths are based on soundings taken in February, March and
April 1954, and are referred to low-water datum. The mean water
level in June 1954 was 3.03 feet above datum. The head of navi-
gation for deep-draft vessels in the river is at turning basin 5 at
the entrance to Lake Calumet.
   The total costs, all funds, to June 30, 1954, were $8,907,613, of
which $5,871,010 were regular funds and $3,036,603 were Public
Works funds; $5,616,541 being for new work and $3,291,072 for
maintenance.
                                        Cost and financial summary

                                                  Fiscal year ending Jane 30                             Total to June
                                                                                   _30,
                                                                               __-_-_                       1954, includ-
                                                                                                        ing fiscal years
                               1950             1951                1952          1953       1954         prior to 19501

New work:
   Appropriated .-             -$3,131      ...        -.       -    -$6,472,514
   Cost ......                       43                                                                        6,472,514
Maintenance:
   Appropriated .-....         211,000          $22,752         $122, 500         $19,165    $59, 300          3,337,087
   Cost    .   -               210,176           23,620     1     59,907           79, 326    60,948           3,336,302

1 Includes $855,973 for new work and $45,230 for maintenance for previous projects.

Other new work data:
    Appropriated for succeeding fiscal year ending June 30, 1955--..                                        $180,000
    Unobligated balances available for succeeding fiscal year ending June
       30, 1955---------------------_                                                                         180,000
    Estimated additional amount needed to be appropriated for comple-
       tion of existing project            --           -       ---------
                                                                       -_.--                              5,650,500

                                5. INDIANA HARBOR, IND.
  Location. Northwestern Indiana (Lake County),, on southwest
shore of Lake Michigan,18 miles southeast of Chicago Harbor.
(See U. S. Lake Survey Chart No. 755.)
  P'IrOious project. Adopted by River and Harbor Act of June
25, 1910?.;For further details, see page 1943 of Annual Report for
1915, and page 1520 of Annual-,,Report for 1938.
  Existing project. This provides for-
  a. .A northerly rubble-mound breakwater 2,520 feet long, an
easterly reinforced concrete-caisson breakwater 1,507 feet long, an
extension. of this latter breakwater about 2,300 feet to the north,
and the construction and placing of a lighthouse crib.
  b. An entrance channel generally 800 feet wide, with a depth of
28 feet at the outer end and 26 feet at the inner end.
  c. Dredging the anchorage and maneuver basin in the outer har-
bor,to a depth of 26 feet, and the channel between the bulkhead fills
in t. outer harboir to a depth of 25 feet.
   d2IWidening the main stem of the Indiana Harbor Canal to a
1126            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

bottom width of 260 feet with a depth of 22 feet from the outer
harbor to The Forks, and dredging the Calumet River Branch
from The Forks to 141st Street to the same width and depth.
   e. A channel 22 feet deep and 160 feet wide in the Lake George
Branch from The Forks to White Oak Avenue.
   f. The maintenance of a channel 20 feet deep and 80 feet wide
in the remainder of the Calumet River Branch south of the north
line of 141st Street, except the removal of sewage deposits and
other city refuse, after completion and acceptance from private
parties.
   g. The construction of a turning basin at The Forks 22 feet deep.
   That part of the Calumet River Branch Channel from the north
line of 141st Street to the Grand Calumet River has not as yet
been completed by local interests or accepted for maintenance by
the United States.
   The project depths are referred to low water datum for Lake
Michigan, which is 578.5 feet above mean tide at New York.
   Seasonal fluctuations in mean stage from low water in winter
to high water in summer average about 1.2 feet. Local and tem-
porary fluctuations of 0.1 to 0.5 foot, due to wind and difference
in barometric pressures, occur daily. Seiches of 3 to 4 feet occur
at infrequent intervals.
   The estimate of cost for new work, revised in 1954, is $4,600,-
000, exclusive of amount expended in previous project. The latest
 (1954) approved estimate for annual cost of maintenance is
$100,000.
The existing project was authorized by the following River and
Harbor Acts:

     Acts                            Work authorized                                 Documents
                            S-----                                     i




June 25, 1910  Outer harbor and maintenance of inner harbor                H. Doc. 1113, 60th Cong., 2d sess.
                channel.
Mar. 4, 1913   Breakwaters ................................ ..   ...       H. Doe. 690, 62d Cong., 2d sess.
Mar. 2, 1919   Lighthouse crib, present length and alinement of the        Rivers and Harbors Committee
                easterly and northerly breakwaters.                         Doe. 6, 65th Cong., 2d sess.
Mar. 20, 1922 Modified the length of channel to be maintained in           Public 176, 67th Cong.
                extension to Lake George.
Mar. 3, 1925 Authorized the Secretary of War to modify the proj-
                ect so far as relates to length and alinement of
                 breakwaters and to sell to Youngstown Sheet &
                 Tube Co. approximately 1,180 linear feet of shore
                ward end of the existing north breakwater.
July 3, 1930 Existing project channel width and depth in the               Rivers and Harbors Committee
                 Lake George Branch, turning basin at The Forks.             Doec. 21, 71st Cong., 2d seas.
June 30, 1932 Authorized the Secretary of War to sell to the Inland        Public 219, 72d Cong.
                 Steel Co. approximately 1,903 linear feet of the
                southerly end of the existing east breakwater.
Aug. 30, 19351 Extension to easterly breakwater; dredging entrance         Rivers and Harbors Committee
                channel and outer harbor; deepening channel                  Doe. 29, 72d Cong., 1st seas.
                between bulkhead fills; widening the main stem of
                the canal and the portion of the Calumet River
                 Branch to 141st St.
Aug. 26, 1937 Modified conditions of local cooperation required            Rivers and Harbors Committee
                before enlargement of the Indiana Harbor Canal              Doec. 13, 75th Cong., 1st sess.2
                 is undertaken by the United States.

  'Included in the Public Works Administration program, Sept. 6, 1933, and July 25, 1934.
  2 Contains latest published map.


  Local cooperation. The act of August 26, 1937, provides that
the enlargement of the Indiana Harbor Canal shall not be under-
taken until local interests have furnished a right-of-way 300 feet
            RIVERS AND HARBORS--CHICAGO, ILL., DISTRICT            1127
  wide and have constructed substantial bulkheads along the chan-
  nel on the established lines shown on the map accompanying Rivers
  and Harbors Committee Document 13, 75th Congress, 1st session,
  provided that the improvement on one side may proceed in any
  section on fulfillment of the conditions for that side of the section,
  and provided further, that south of the turning basin at The Forks
  (beginning 450 feet south of the intersection of the present Calu-
met Branch and main-stem bulkhead lines),widening and deep-
  ening by the United States shall be done only as the rights-of-way
and bulkheads on at least one side of the channel are continuously
  provided southward from the above limit of the turning basin at
  The Forks. To provide for the 300-foot channel, a parcel of land
  (of about 4.6 acres), generally 100 feet wide, lying on the east
side of the Calumet River Branch, commencing at the north
side of 141st Street and extending northward toward The
Forks for a distance of about 2,107 feet, has been conveyed to and
accepted by the United States. Local interests have also con-
structed about 1,350 feet of bulkhead along the east side of the
Calumet River Branch, and have reconstructed the bulkhead on
the west side from The Forks to 141st Street. The Defense Plant
Corporation has built a bulkhead along the east side of the canal
between the Pennsylvania Railroad Co.'s bridge and Dickey Place
Bridge; the United States has widened and deepened the east side
of this portion of the widening. All prior requirements have been
fully complied with.
    Terminal facilities. There are 16 docks handling lake and river
cargoes. The most important cargoes handled are iron ore, petrol-
eum products, limestone, iron and steel products, sand and gravel,
and coal. There are no public docks in this harbor.
    Operations and results during fiscal year. Condition surveys,
inspections, reports, and flue dust investigations were conducted
by hired labor at a cost of $30,242. Dredging in the harbor and
in the canal was performed, by contract, and 66,968 cubic yards
of material were removed at a cost of $81,280, of which approxi-
mately $66,600 was reimbursed by the U. S. Steel Company. The
total cost for the fiscal year was $44,922 all maintenance.
    Condition at end of fiscal year. The existing project is 80 per-
cent complete. The work remaining to be done to complete the
existing project consists of completing the widening of the main
stem of the Indiana Harbor Canal to a bottom width of 260 feet,
with a depth of 22 feet from the outer harbor to The Forks; com-
plete widening of the Calumet River Branch from The Forks to
141st Street to the same width and depth, and complete deepening
and widening to full project dimensions of the upper 3,400 feet
of the Lake George Branch. The north breakwater (rubble
mound, 2,520 feet, completed in 1922) is in good condition except
that some riprap is required. The east breakwater (concrete
caisson, 1,507 feet, completed in 1926) and northerly extension
 (rubble mound, 2,324 feet, completed in 1935) are in good condi-
tion except that some riprap is required. The controlling mid-
channel depths are as follows: 26 to 28 feet in the entrance chan-
nel parallel to the rubble mound breakwater and generally 21
feet or more in the outer harbor; 19.0 feet between thebulkheads
 1128            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

of the teel companies to the 5 bridges; 21.0 feet from the 5
bridges to the turning basin at The Forks; 25 feet in the turning
basin at The Forks; from 20 feet at the basin entrance to 16 feet
at a point 140 feet from the south side of the basin, in the turn-
ing basin east of Canal Street; 22.2 feet from the turning basin
at The Forks to 141st Street Bridge; and 22.0 feet from the turn-
ing basin to 750 feet above the Indianapolis Boulevard bridge, on
the Lake George Branch. Depths are based upon soundings taken
April 1951, February 1954, March 1954, and June 1954 and are
referred to low-water datum. The mean level in June .1954:was
3.03 feet above datum. The head of navigation for commercial
vessels is at the Baltimore & Ohio Terminal Railroad Bridge,-on
the Lake George Branch, about 3 miles from the outer harbor, and
at a point about 2,200 feet from The Forks on the Calumet River
branch, about 2.5 miles from the outer harbor.
   The total costs of the existing project to June 30, 1954, all
funds, were $5,749,398, of which $4,131,354 were regular funds
and $1,618,044 Public Works funds; $3,628,688 being for new
work and $2,120,710 for maintenance.
                                       Cost and financial summary

                                                Fiscal year ending June 30                    Total to June
                                                    .   .           ..                    .   30, 1954, includ-
                                                                                              ing fiscal years
                                1950         1951        1952         1953         1954        priorto 1950'


New work:
   Appropriated ..---..  ------- ---------------      ---- ----------------------    -$3, 689,356
   Cost                   _
                          _------------------------
                .....--------------------
                                      ------------                             ---------3,689,356
Maintenance:
   Appropriated ..- -        $93, 000     $101,000 . $92,000   $43, 465   $36, 400      2,123,913
   Cost...-----------------   69,795       116,519    94,647    41,309     44,922       2,123,219

1   Includes $60,668 for new work and $2,509 for maintenance for previous projects.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project --------------------
                                               ___             _        $971,300

                           6. MICHIGAN CITY HARBOR, IND.

   Location. Northwestern Indiana (in La Porte County), on the
southeasterly shore of Lake Michigan, 38 miles in a southeasterly
direction from Chicago Harbor. (See U. S. Lake Survey Chart
No. 75.) For descriptions, see page 1482 of Annual Report for
1932.
   Previous projects. Adopted by River and Harbor Act of July
4, 1836, and work was continued under this project until 1870. For
further details, see page 1944 of Annual Report for 1915, and page
1524 of Annual Report for 1938.
   Existing project. This provides for-
   a. A detached breakwater, east and west entrance piers, and a
dredged channel, 120 to 150 feet wide and 18 feet deep, from Lake
Michigan to the upper of two turning basins, which are also to have
a depth of 18 feet.
   b. The repair and restoration of the westerly 1,000 feet of the
old east breakwater.
   c. Dredging an anchorage shoreward of the restored section to
                        RIVERS AND HARBORS-CHICAGO,                           ILL., DISTRICT             1129
a depth of 12 feet in the northerly portion and 8 feet in the south-
erly portion.
   d. Enlarging the entrance to this basin through the east pier to
a width of 66 feet.
   The project depth is referred to low water datum for Lake
Michigan, which is 578.5 feet above mean tide' at New York.
   Seasonal fluctuations in mean stage from low water in winter
to high water in summer average about 1.2 feet. Local and tem-
porary fluctuations of 0.1 and 0.5 foot, due to wind and difference
in barometric pressures, occur daily. Seiches of 3 to 4 feet occur
at infrequent intervals.
   The cost for new work for the completed project was $1,212,385,
exclusive of amount expended on previous project. The latest
 (1954) approved estimate for annual cost of maintenance is
$35,500.
  The existing project is based on the following reports and River
and Harbor Acts:
       Acts                             Work authorized                                  Documents

                  -   East breakwater and old east pier enclosing the outer   Recoinmendation of a Board of
                       basin.                                                  Engineers, Annual Report, 1870,
                                                                               p. 123.
                      Extension of east pier---   _,               _-         Reports of Boards of Engineers,
                                                                               Annual Report, 1881, pp. 2187-
                                                                               2189; Annual Report, 1882, pp.
                                                                               2264-2266.
Mar: 3, 1899          Extension of east pier and construction of detached     Annual Report, 1897, pp. 2903-2904.
                        breakwater.
Mar.    3, 1905       Lower turning basin._______
                      Rebuilding of the west pier as at present located.      Joint resolution of Congress ap-
                       Present project dimensions of entrance channel.          proved May 13, 1908, Public 23.
Jan. 21, 1927         Existing project depth in channel, and in lower and     H. Doe. 279, 69th Cong., 1st sess.
                       middle turning basins, elimination of the improve-
                       ment of Trail Creek above the middle turning
                       basin and of the uncompleted portion of the de-
                        tached breakwater, abandonment of east break-
                       water and old east pier enclosing the outer basin.
Aug. 30, 1935         Restoration and repair of westerly 1,000 feet of east   Rivers and Harbors Committee
                       breakwater, dredging outer basin, and enlarging         Doc. 34, 74th Cong., 1st sess.
                       the entrance to the basin through the east pier.         (Contains latest published map.)



   Local cooperation. Fully complied with.
   Terminal facilities. There are 4 fish docks in this project. The
only commodity handled at this harbor is fresh fish. There are 2
small boatyards, which repair and construct recreationial craft
only. The one public dock is owned by the city and has not been
used for commercial purposes to date.
   Operations and results during fiscal year. Condition surveys,
inspections and reports, were performed by hired labor at a cost
of $2,875. Stone placement for breakwater repair was performed
by contract at a cost of $26,313. Repairs to detached breakwater
were performed by contract at a cost of $27,955. The total costs
for the fiscal year were $57,143, all maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted, in December 1936. Concrete superstructure, 1,304 feet,
on the detached breakwater, completed in 1925, is in fair condi-
tion, and the entrance piers, completed in 1931, are in good condi-
tion. Under permit from the Secretary of War, the Northern
Indiana Public Service Co., has removed 615 feet of the inner end
of the west pier and about 719 feet of the bulkhead south of the
1130             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

pier, and has replaced them with a steel-sheet pile bulkhead lo-
cated landward of the former dock line. The area channelward of
the new bulkhead was dredged by the permittee to 18 feet. Depths
in the entrance channel up to the Franklin Street Bridge vary
from 11 to 25 feet. Between the Franklin Street Bridge and the
turning basin at the head of the project, the depths vary from
1.0 to 15.0 feet in a channel about 60 feet wide, except in the
draws of the Michigan Central Railroad Company's Bridge where
the width is about 40 feet. The turning basin at the head of the
project has shoaled above datum. Available anchorage depths in
the basin are 12 feet in the northerly portion and 8 feet in the
southerly portion.
  Depths are based upon soundings taken during June 1953 and
are referred to low-water datum. The mean water level in June
1954 was 3.03 feet above the datum. The head of navigation for
commercial vessels is the turning basin at the head of the project,
1.04 miles above the outer end of the west pier. Above this point,
depths are only sufficient for small launches.
  The total costs of the existing project to June 30, 1954, were
$2,631,214 of which $1,212,385 were for new work and $1,418,829
for maintenance.
                                              Cost and financial summary

                                                      Fiscal year ending June 30                             Total to June
                                                                                                            30, 1954, includ-
                                                                                                            ing fiscal years
                                       1950         1951             1952           1953         1954           priorto 1950

New work:
    Appropriated       -----------.-             ----------- -- -----------------          --------------   -     1 $1, 499,774
     Cost......--------------------------------------------- -----------------------                                1,499,774
Maintenance:
   Appropriated- ..--
                    --            $22, 500         -$1,742            $2, 500       $3, 100      $92, 400           1,454,286
   Cost ....     ...-----------------37, 524    ------------ -         2,441         2,959        57,143            1,418,829

  1 Includes $287,389 for new work for previous projects.


                       7. ILLINOIS WATERWAY, ILL. AND IND.
   Location. The Illinois River (entirely within the State of Il-
linois), formed by the confluence of the Kankakee and the Des
Plaines Rivers, flows in a southwesterly direction and enters the
Mississippi at Grafton, Ill., about 38 miles above St. Louis.
   The Illinois Waterway comprises the Illinois River from its
mouth t.the confluence of the Kankakee and Des Plaines Rivers,
a distance of 273 miles; the Des Plaines River to Lockport, a dis-
tance of 18.1 miles, and the Chicago Sanitary and Ship Canal and
the south branch of the Chicago River to Lake Street, Chicago, a
distance of 34.5 miles. Also from a point 12.4 miles above Lock-
port, Ill., the waterway comprises the Calumet-Sag Channel and
the Little Calumet and Calumet Rivers to turning basin 5, near
the entrance to Lake Calumet, a distance of 23.8 miles; and the
Grand Calumet River from the junction to 141st Street, deep
 (lake) draft navigation, a distance of 9 miles, and to Clark Street,
Gary, Ind., a distance of 4.2 miles.
            RIVERS AND HARBORS--CHICAGO, ILL., DISTRICT          1131
     Previous projects. The original project was adopted by the
  River and Harbor Acts of August 30, 1852, April 10, 1869, July
  11, 1870, June 14, 1880, and March 2, 1907. For further details,
  see page 1945 of Annual Report for 1915, and page 1172 of An-
  nual Report for 1932.
     Existing project. This project provides for the construction of
  9 locks and 6 dams; dredging a navigation channel with least di-
  mensions of 9 feet in depth and 300 feet in width from the mouth
  of Waterway at Grafton, Ill., to Lockport, Ill., a distance of 291.1
  miles; a navigable channel depth of not less than 9 feet of the
present width, from Lockport to the controlling works, a distance
  of 2 miles; a channel with usable depth of 9 feet and width of
225 feet, from the controlling works to its junction with the Calu-
met-Sag Channel, a distance of 10.4 miles; thence in the Calu-
met-Sag Channel to the present lock in Blue Island, Ill., a distance
of 16 miles; a channel 9 feet deep and 300 feet wide in the Calu-
met and Little Calumet Rivers, from the lock in Blue Island to
turning basin 5, a distance of 7.8 miles. Also a channel with usable
depth of 9 feet and a width of 225 feet along the general route
of the Grand Calumet River from its junction with the Little
Calumet River to and in the Indiana Harbor Canal to 141st Street,
East Chicago, Ind., a distance of 9 miles. Also from the junc-
tion of the Indiana Harbor Canal and the Grand 'Calumet River,
a channel in that river of usable depth of 9 feet and a width of
160 feet to Clark Street in Gary, Ind., with a turning basin at
Clark Street, a distance of 4.2 miles. Also, the removal of the
controlling lock at Blue Island, Ill., and construction of a control-
ling works in Calumet River near its head, and similar structures
in the proposed Grand Calumet Channel west of the Indiana Har-
bor Canal; alteration or elimination of railroad bridges across
these channels lakeward of the Chicago Sanitary and Ship Canal,
or the construction of new railroad bridges, to provide suitable
clearances, with apportionment of the costs between the bridge
owners and the United States, in general accordance with the pro-
visions of section 6 of Public Law 647, 76th Congress; and making
at the expense of the United States all fixed span bridges across
the waterway, between McDonough Street, in Joliet, and turning
basin 5, capable of conversion to lift bridges having vertical clear-
ance of not less than 40 feet. The project also provides for a
navigable channel depth of not less than 9 feet of the present
width from the Calumet-Sag Junction to Lake Street, Chicago, via
the Chicago Sanitary and Ship Canal and south branch of the
Chicago River, a distance of 22.1 miles. Provision is also made
for a small boat harbor in the vicinity of Peoria, Ill., by construc-
tion of a basin 510 by 250 feet, dredged to a depth of 7 feet and
protected by an earth embankment riprapped on the lakeside.
The total length of the project from the mouth to Lake Street,
Chicago, is 325.6 miles, to turning basin 5, is 327.3 miles, to 141st
Street, Chicago, is 325.6 miles, to turning basin 5, is 327.3 miles,
to 141st Street, is 334.7 miles, and to Clark Street in Gary, Ind.,
is 336 miles.
1132            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  The estimated cost of new work, revised in 1954, is $155,800,-
000. The latest (1954) approved estimate of cost for the operat-
ing and care of locks and dams is $1,040,000 annually, and for
channel maintenance $650,000 annually.
  The existing project was authorized by the following River and
Harbor Acts:

     Acts                         Work authorized                                     Documents


Jan. 21, 1927   Channel 9 feet deep and 200 feet wide from mouth of       Rivers and Harbors Committee
                 Illinois River to Utica, 231 miles, modification of        Doc. 4, 69th Cong., 1st sess., and
                 the 2 United States locks and dams, removal of the        S. Doc. 130, 69th Cong., 1st sess.
                 2 State dams. (Act authorized appropriation of not
                 to exceed $3,500,000 for carrying on the work.)
July 3, 1930    Channel depth of 9 feet from Utica, Ill., to the heads    S. Doc. 126, 71st Cong., 2d sess.
                 of the present Federal projects on the Chicago and
                  Calumet Rivers, distances of 94.6 miles to Lake St.
                 and 96.3 miles to turning basin 5, respectively, to be
                 secured by means of completed dams, locks, lateral
                 canals, and dredging begun by the State of Illinois
                 in general accordance with the present plans of the
                 State for that work. The act in adopting the project
                 authorized the appropriation of not to exceed
                 $7,500,000 for carrying on the work.
June 26, 19341 Operation and care of the locks and dams provided
                 for with funds from War Department appropria-
                 tions for rivers and harbors.                                                                 2
Aug. 30, 1935 Construction of modern locks and dams at La Grange          H. Doc. 184, 73d Cong., 2d sess.
                 and Peoria and for a channel 9 feet deep and 300
                 feet wide below Lockport, the exact location and
                 details of design of all structures to be left to the
                 discretion of the Chief of Engineers, and, for the
                 time being, that no change be made in the water
                 authorized for navigation of the Illinois River by
                 act of July 3, 1930.
Augi 30, 1935 3 This act also provides for 3 passing places along the     H.   Doc. 180, 73d Cong., 2d sess.
                 Sag Channel and the authorized channel in the
                  Calumet-Sag route to turning basin 5, and dredging
                 at entrance of Lake Calumet.
June 14, 1937 Realinement of portion of Calumet River and aban-           Rivers and Harbors Committee
  (Publl. Res.   donment of bypassed section of the Calumet River.          Doc. 19, 75th Cong., 1st sess.
  42>
June 20, 1938 Modifies requirements of "local cooperation" in act         Public, 685, 75th Cong., 3d sess.
                 of Aug. 30, 1935.
Oct. 23, 1943 Payment of damages to levee and drainage districts          H. Doe. 711, 77th Cong., 2d sess.
                 due to seepage and other factors, amount not to
                 exceed $303,500.
                  RIVERS AND HARBORS--CHICAGO, ILL., DISTRICT                                         1133

     Acts                          Work authorized                                    Documents

Mar. 2, 1945    Enlarge the Calumet-Sag Channel to a width of 160          H. Doe. 145, 76th Cong., 1st sess.
                   feet and to a usable depth of 9 feet. Dredge a barge
                   channel 160 feet in width with a usable depth of 9
                   feet in the Grand Calumet and Little Calumet
                   River branch of the Indiana Harbor Canal to deep
                    (lake) draft through 141st St., East Chicago, Ind.
                   Construct in the Little Calumet River a lock of
                   suitable dimensions for barge navigation. Rebuild
                   or otherwise alter at Federal expenge all obstructive
                   railroad bridges across the Calumet-Sag Channel,
                   Little Calumet River, Calumet River, Grand
                   Calumet River, and Indiana Harbor Canal, so as
                   to provide suitable clearance, except that no Federal
                  funds shall be expended for removal or alteration
                   of the Illinois Central R.R. bridge at mile 11.20 of
                   the Little Calumet River.
July 24, 1946   Substitutes the following work for that authorized by      H. Doc. 677, 79th Cong., 2d sess.
                  act of Mar. 2, 1945; Replacement of emergency dam
                  in the Chicago Sanitary and Ship Canal; enlarge-
                  emnt of that canal thence to Sag Junction and of
                   Calumet-Sag Channel to afford channels 225 feet
                  wide with usable depth of 9 feet; construction along
                  the general route of Grand Calumet River of a
                  channel with usable depth of 9 feet, 225 feet wide
                  between Little Calumet River and the junction
                  with the Indiana Harbor Canal and 160 feet wide
                  thence to Clark St., Gary, Ind., with a turning
                  basin at Clark St.; enlargement of the Indiana
                  Harbor Canal to a width of 225 feet and usable
                  depth of 9 feet between Grand Calumet River and
                  the vicinity of 141st St., inclusive; removal of
                  Blue Island lock and construction of a lock and
                  control works in Calumet River near its head, and
                  of similar structures in the proposed Grand Calu-
                 met Channel west of the Indiana Harbor Canal;
                 alteration or elimination of railroad bridges across
                 these channels lakeward of the Chicago Sanitary
                 and Ship Canal, or the construction of new railroad
                 bridges, to provide suitable clearances.
July 24, 1946   Provide for a small-boat harbor in the vicinity of         H. Doc. 698, 79th Cong.,   d:sess.
                 Peoria, Ill., by construction of a basin 510 by 250
                 feet, dredged to a depth of 7 feet.


1 Permanent Appropriations Repeal Act.
2 Contains latest published map of Illinois and Des Plaines Rivers.
3 Included, in part, in the Public Works Administration program, Oct. 31, 1934, and Feb. 28, 1935.

   The latest published map and profile :of the Illinois and Des
Plaines Rivers are contained in House Document 184, 73d Con-
gress, 2nd session, and a map of the Calumet-Sag Channel is
printed in House Document 145, 76th Congress, 1st session.
   Pertinent data for existing and proposed locks and dams are
given in the following table:
                                                                                                                                                                                                                         Lock
                                                                                                                    Location
                                                                                                                                                                                           Dimensions                                    Depth on miter sills at
                                                                                                                                                                                                      Dimensions                              low water 1

                                 Name
                                                                                                                                                                                            Available
                                                                                       Miles                                                                              Width of            length                Lift at low            Lower       Upper          b
                                                                                       above                               Nearest town                                   chamber             for full               waterI                (fee
                                                                                       mouth                                                                               (feet)              width                   (feet)                   t)      (feet)        0
                                                                                                                                                                                               (feet)

La Grange _________                                                                        80.2   7.8 miles below Beardstown, Ill...........            _    110--                                    600                   10.0              13.0           15. 5
                                                                                                                                                                                                                                                             15.5
Peoria_.._..______ __                                                                     157.7   4.1 miles below Peoria, Ill.._____________________         110                                      600                   11.0              12.0
Starved Rock..-...                                                                        231.0   Utica, Ill-....-  .          ......----------------------- 110                                      600                   18.5              14.0           16.85    0
Marseilles ...........                        ------------------                          244.6   Marseilles Ill _---------------------------------_110                                               600                   24.25             14.0           18.6
Dresden Island         -----                  ------------------                  --      271.5   Morris, Ili             ------------------------------                            110               600 I                 21. 75            12.25          16. 85
Brandon Road .....
Lockport- ..........
                                              ------------------

                                              ------------------
                                                                                          286.0
                                                                                          291.1
                                                                                                  Joliet, Ill_.......__-___.......--          ....--..__      ___
                                                                                                  Lockport, Ill.......................---------------------------------
                                                                                                                                                                        110
                                                                                                                                                                        110
                                                                                                                                                                                                      600
                                                                                                                                                                                                      600
                                                                                                                                                                                                                             34.0
                                                                                                                                                                                                                        30.5-39.5
                                                                                                                                                                                                                                              13.8
                                                                                                                                                                                                                                              15.0
                                                                                                                                                                                                                                                            17.85
                                                                                                                                                                                                                                                       11.5-22.0      C12
Calumet River 3s...                           ------------------                          326.4   Chicago, Ill...------.......---..............-----------..110                                       950   ------------...                   14.0          14.0      LOx

Grand Calumet 3_                              ------------------
                                                                                          329.5   Hammond, Ind ...---------------..................             ---     110                           950                           -I        14.0          14.0


                                                             Lock-Continued                                                                         Dam                                                                                            Estimated
                                                                                                                                                                                                                                                                      z
                                                                                                                                                                                                                         Percent-        Year of cost to United
                                                                                                                                                                                                                          age of                                      r1
                    Name                                                                                                                                                                                                                 comple- States under
                                                    Type of con-               Character of                                                                                                Character of                  complen           tion     existing
                                                                                                               Kind                           Type of construction
                                                     struction                 foundation                                                                                                  foundation                                                project

Illinois River, mouth to Utica;                   --           j~---_
                                                                        -
                                                                        ---       -----
                                                                              -----        _--
                                                                                          -----                     ---                __         -------                          .....        --.....-
                                                                                                                                                                                                   -                -           -----..                $2, 773,499
   Channel      improvement     by
   dredging in the Illinois River
   below Starved Rock, modifi-
   cation of 2 United States locks
   and dams. and for the removal
   of the 2 State darns.  -
La Grange ...               .                       Concrete                   Piles in sand      Movable (wicket type                  Concrete and timber ..........                 Piles in sand -                          100        1939       42, 744, 592
                                                                                                   and weir with A-frame
Peoria--------------_---__----____--------
                       _____________do-                                                            Movabl
                                                                                                     crest)   (wicket type)           do-------------------                            ---- do                                  100        1939       43,381,030
Starved Rock          -------------                 do...... Rock........Movable (Tainter gates) Concrete and structural steel._ Rock-...........                                                                               100        1933         4   885,315
Marseilles ...-----------                    ....----------
                                                    do---------.........do---------do......... .... do...........--------------.do-----------------......................... ..... do..........                                 100        1933       41,853,725
Dresden Island ---.     --....--...                  do..-                   do...---...               do     -.............----      do -- ______- ---...........                              do.......                       100        1933        2,503,376
Brandon Road ........        -do............                  .              ...
                                                                             do-.              '....do      .-----...---...                              --
                                                                                                                                      do ..........................--. -----        -           do.......       .               100        1933       '2,031,683
Lookport....------------------.-----do-                     ..----           do-_........Movable (sector gates) a- .... do.------                                         ..----------------....do ..........                   100        1933         4 133 608
Proposed lock in Calumet River__              Concrete          Piles in clay-.          Fixed       6.                          .                              Concrete and sheet piling .--                                              Piles in clay                    -              --------                1     4, 315, 000
                                                 and sheet
                                                 piling.
Proposed lock in Grand Calumet              ...- - do      .        . do ..        do    -
                                                                                         ....   do..............                                  ...                 do-.........                  ..        _...     .       .           ... do..._                   .   ..        ..                                 4....
                                                                                                                                                                                                                                                                                                                         4,305,000
  Channel.
Proposed replacement of emer- .                                                          (Movable                    vertical              lift                 Structural Steel--.---                                                     Rock -------                                                                  1,056, 300
  gency dam.                                                                               type.)
Lock and dam equipment -...---                                                                                                                                                                                                         -                         -                    -          -         -             1,666,700
       Total, locks and dams                                               .....                                                                                                                                                                                                               ---             i        7 , 649, 828
                                                                                                                                                                                                                                                                                                                       27-----------,
                                                                                                                                                                                                                                                                                                                                               C
                                                            ADDITIONAL FEATURES ENTERING INTO COST OF PROJECT
Dredging:
L ittle Calu m et a nd C alum et R ivers                            .--                                               -           -
                                                                                                                         ---------------
                                                                                                                                       .....                                                                                                                                                   ....----.               $2, 135, 3 68
Calumet-Sag, 3 passing places -                   -                                                                .-                                                                                                                                                                                                     813,419
                                                                                                                                                                                                                                                                                                                           8-------------------------
Starved Rock to Lockport ....---------------------------------------------------------------------------------------
  Starved Rock to Grafton ...-                                                                                                        -----------------------                                                                                  .--
                                                                                                                                                                                                                                                                                                                        4,309,308
                                                                                                                                                                                                                                                                                                                        3-
                                                                                                                                                                                                                                                                                                                        3,077, 683
                                                                                                                                                                                                                                                                                                                                               z
  Chicago Sanitary and Ship Canal.......-------------------------------------------------------------                                                                                                                          --------------------------------------- 13,423,000
  Calumet-Sag Channel....3310---------00-----------.------------0__-                               -                            -----------
                                                                                                                                  _-------.                                _--..--_-                               .           ..          ...      .      .33,531,000         00--------...
  Grand Calumet River and Indiana Harbor Canal                                                                                                                   -------------------                                                                                    6 053,000       d
  Peoria small-boat harbor -..--------------                                                                                                                                              --..                                                                                                                               2, 97-------------------------------------
                                                                                                                                                                                                                                                                                                                             24,937
Protection piers at all locks - ..........           . -     . -...                      .              .              .                  .                      .              .            .               . -       .                   .            .-                                                                  77, 633
Calumet-Sag Channel, advance planning . - -            - -     - -                  -    -      -       -        -      -        -         -            -         -    -         -         - -           -         -       -                                           --                 --                             3,000,000
Rebuilding railway bridges:                                                                                                                                                                                                                                                                                                                    0
LCalumet-Sag Channel-........................           .    .    . .                   .   .                                                                                                                                                                                                                          23,249, 000
Little Calumet and Calumet Rivers ..             .- .    ..   ..                       ..-------                                                                                                                                                    ---............                                                   17, 020, 000
  Grand Calumet River and Indiana Harbor Canal-                                                -
                                                                                           .-----                                                                                          -----------------------                                                                                                     20,153, 370
Removal of Blue Island lock _
St. Louis, Mo., district
                                              ...
                                 --------------------------
                                                                                                             -        _-         -        -                 -     -        -          -
                                                                                                                                                                       ----------------
                                                                                                                                                                                             -      -                  .           .            .      .   .  .   .  .   .118,000
                                                                                                                                                                                                                                                     --------------------------                                          1,140,684
                                                                                                                                                                                                                                                                                                                          ,                    W
Miscellaneous._ _-                                                                                       -                  -                                                                       --                                                                                                                      23,800
       Total additional features ----------------------------------                                                             ---           -             -                  ----                          ___----                                                             --                                    128,150,172
                                                                                                                                                                                                                                                                                                                                            O
       Total existing project..---             _...---......   _                        ---------------------- ------------------
                                                                                                                          ...     -----                                                                                                                                                                                 55,800,000
                                                                                                                                                                                                                                                                                                                               0----0---------------------------------
                                                                                                                                                                                                                                                                                                                       15,------------

  1 Lifts and depths on miter sills are those obtained with flat pools.                                                                            + Actual cost.                                                                                                                                                                               H

  3 Variation in lift and depth on upper miter sill at Lockport is due to fluctuation                                                               5 6 dams conpleted by Corps of Engineers; the 48-foot bear trap at Lockport completed
of water surface in the sanitary District Canal.                                                                                                  by State of Illinois.                                                                                                                                                                         H=
  3 Proposed.                                                                                                                                       6 Control works.                                                                                                                                                                           Ut
 1136      REPORT OF CHIEF OF: ENGINEERS, U. S. ARMY, 1954

      Local cooperation. The River and Harbor Act of January 21,
   1927, modified the existing project subject to the condition that the
   State of Illinois transfer to the United Sates without cost all rights
   and titles in the two State-owned dams on the Illinois River, and that
   local interests furnish the United States without cost all necessary
   areas for the disposal of materials dredged in creating and main-
   taining the channel authorized (S. Doc. 130, 69th Cong., 1st sess.).
   By deed dated March 28, 1928, the State of Illinois transferred
  these locks and dams to the United States.
      Permission has been granted by many riparian landowners for
  use of their lands for the disposal of dredged material.
      The River and Harbor Act of July 3, 1930, modified the existing
  project subject to the following provisions: That the project thus
  adopted shall be in all its parts a navigable waterway of the United
  States, forever free to the public use of all, unencumbered: by any
  tolls or restrictions of any kind whatsoever except such as may be
  imposed by Congress; that the State of Illinois shall proceed, sub-
  ject to the supervision and approval of all expenditures and obli-
  gations by the Secretary of the Army, to construct the highway
  bridges at Brandon Road and Marseilles Canal, to make the neces-
  sary alterations in other highway bridges across the Illinois Water-
way, to make the necessary arrangements and agreements for the
  alterations of the railroad bridges across said waterway, and to
  do such other work on said waterway as the Secretary of the Army
shall direct and .the available funds of the State make possible,
the bridges mentioned not to become the property of the United
States, and no obligations to be incurred by the United States to
maintain, operate, or replace them; and that no claim shall lie
against the United States because of any contractual obligations
which have been or may be entered into by the State of Illinois as
regards the construction of a waterway between Utica apd Lake
Michigan (S. Doc. 126, 71st Cong., 2d sess.).
                                                             -
     The State of Illinois appropriated $20,000,000 for the .c nstruc-
tion of a waterway providing minimum 8-foot depths in channels
not less than 150 feet wide, from the upper end of the Federal
project on the Illinois River, to Lockport. The lock and dam at
Starved Rock was about 95 percent complete, the Marseilles lock
was about 95 percent, the Marseilles Canal 98 percent, Dresden
Island lock and dam about 20 percent, Brandon Road lock and dam
about 70 percent, and the Lockport lock about 95 percent complete,
before the passage of the River and Harbor Act of July 3, 1930.
     The River and Harbor Act of August 30, 1935, as modified by
the River and Harbor Act of June 20, 1938, provides that local
interests furnish to the United States, free of cost, all necessary
land to effect the improvements recommended in House Docu-
ment 180, 73d Congress, 2d session, and install operating machin-
ery and place in operating condition the three drawbridges across
the Chicago Sanitary and Ship Canal between its junction with
the Calumet-Sag Channel and Lockport when directed by the Sec-
retary of the Army. All requirements have been met except for
the installation of operating machinery in the Atchison, Topeka
& Santa Fe Railway bridge at Lemont, Ill.
  The River and Harbor Act of July 24, 1946, superseded the pro-
           RIVERS AND HARBORS-CHICAGO, ILL., DISTRICT           1137
visions of River and Harbor Act of March 2, 1945, and provided
that local interests furnish free of cost to the United States all
lands, easements and rights-of-way, and spoil disposal areas neces-
sary for the new work and for subsequent maintenance when and
as required, including the alteration of utilities as necessary, with
the exception of such land needed for the waterway as is now oc-
cupied by abutments or railroad tracks at the approaches to rail-
road bridges; and agree to remove at their own expense, or satis-
factorily alter, the highway bridges across Des Plaines River at
McDonough and Cass Streets (Joliet) across the Chicago Sanitary
and Ship Canal at 16th Street (Lockport), Romeo Road, and Le-
mont Road, and all highway and street bridges across the chan-
nels included in the project lakeward of Sag Junction which, in
the opinion of the Secretary of the Army, constitute unreason-
able obstructions to navigation; construct all necessary new high-
way, street, or foot bridges across these channels; agree to pro-
vide near Clark Street, Gary, Ind., an adequate public barge-rail-
truck terminal open to all on equal terms;,.and that the several
sections of the proposed channel may be improved as separate units
when considered advisable by the Secretary of the Army and the
Chief of Engineers after local interests have provided, or furnished
assurances satisfactory to the Secretary of the Army that they will
provide the cooperation required for any unit.
   The city of Chicago has supplied informal assurances that it
will furnish the lands required between 130th and 138th Streets
for the Calumet River lock site and appurtenances.
   Local cooperation required for the small boat harbor at Peoria,
Illinois, authorized by the River and Harbor Act of July 24, 1946,
has been fully complied with.
   Terminal.facilities. Of the 13 principal cities and towns along
the Illinois River, about 5 own dock frontage, more or less im-
proved for boat landings; 4 own dock frontage with no improve-
ments; and 4 own no frontage except at street ends.
   At Peoria, the largest city on the river, there is a $400,000 mod-
ern river-rail municipal public terminal having an available front-
age of 1,100 feet; 205 feet are occupied by a dock house and 190
feet by an open dock. The dock house is served by a wharf boat
45 feet by 230 feet, and an escalator capable of handling 1,000
tons a day. This terminal is served by the equivalent of a belt line
railroad. Grain elevators are available at 26 points between Graf-
ton and Joliet. Private coal loading terminals are located at
Havana, Liverpool, Copperas Creek, and Kingston Lake. Coal-
unloading terminals are located at Havana, at the mouth of the
Vermilion River near La Salle, and at Joliet; and a cement load-
ing plant is located at the mouth of the Vermilion River near La
Salle, and one at Peru. Bulk-petroleum terminals are located at
Havana, Kingston Mines, Peoria, Peru, Seneca, and Joliet. Sand
and gravel plants are located at Kingston Lake, Chillicothe, Henry,
Ottawa, Morris, Joliet, and Lockport.
   A barge construction yard, launching ways, and shipyard are lo-
cated at Seneca.
  From the Chicago Sanitary and Ship Canal, sand, gravel, oil,
and gasoline are shipped from Lockport, and petroleum products
1138     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

and stone from Lemont. Bulk-petroleum terminals are located at
Argo and Forest View, Ill., and at California Avenue, Cicero Ave-
nue, and Kedzie Avenue, Chicago; and a liquid industrial-chemicals
terminal is located at Cicero Avenue in Stickney, Ill. Private coal-
unloading terminals are located at Ridgeland Avenue, Crawford
Avenue, Loomis Street, Fisk Street, and Addison Street, Chicago.
At Western Avenue, Chicago, bulk and package freight are
handled through the North Pier River barge terminal. The State
of Illinois barge terminal, including a 1,500,000-bushel grain ele-
vator, is located at Damen Avenue, Chicago, on the South Branch
of the Chicago River. Two sand and gravel distribution yards are
located on the Calumet-Sag Channel. A petroleum unloading ter-
minal is located on the Little Calumet River at Riverdale, just
upstream from the junction with the Sag Channel; and two petro-
leum terminals are located at Homan Avenue in Blue Island.
Plans for further terminals and docks between Grafton and Chi-
cago are underway.
    Operations and results during fiscal year. New work:
   Main stem modifications: Contracts for construction of spare
miter gate sections, anchorages, and structural steel sectional
bulkhead were continued at a cost of $450,863. Anchorages for
gate lifting devices were installed by hired labor at a cost of
$3,517. Miscellaneous hired labor work was accomplished at a
cost of $2,058.
   Payment was made to the Nutwood Drainage and Levee Dis-
trict, Illinois, in the amount of $107,683 for rectification of dam-
ages caused by pool No. 26 (Alton).
   Calumet-Sag modificationi: Design memorandum, plans and
specifications for dredging in Part I, plans and specifications for
the G.M. & O. Bridge, and plans and specifications for the Calumet
River lock were accomplished by hired labor at a cost of $22,733.
   Maintenance: Alton pool: Condition surveys, inspections, and
reports were accomplished by hired labor at a cost of $14,422 with
pending adjustments of $3,733.
   All pools above Alton pool: Condition and operation studies,
inspections and reports, by hired labor, were accomplished at a
cost of $165,103. Dredging was performed by contract in the
Calumet-Sag Channel and Little Calumet River between miles
315.9 and 320.2 at a cost of $60,861, with 85,943 cubic yards of
material removed. Dredging was performed by contract in La-
Grange Pool between miles 133.0 and 137.5, at a cost of $62,273,
with 202,141 cubic yards of material removed. Channel dredging
was accomplished by hired labor and Government plant at a cost
of $44,093, with 43,195 cubic yards of material removed.
   Operatingand care of locks and dams: The locks and dams were
operated as required and the necessary repairs made thereto and
to appurtenant structures at a cost of $1,719,685.
   The total cost for the fiscal year was $2,657,024 of which $586,-
854 was for new work, and $2,070,170 for operation and mainte-
nance of locks, dams, and canals.
   Condition at end of fiscal year. The existing project, exclusive
of the Calumet-Sag Modification, is 93 percent complete. The proj-
ect as a whole, including the recent Calumet-Sag Modification, is
           RIVERS AND HARBORS-CHICAGO, ILL., DISTRICT          1139
21 percent complete. Seven locks and 6 dams have been completed,
and there is a channel 300 feet wide and 9 feet deep between Graf-
ton and Lockport, Ill., with the exception of Marseilles Canal
which is 200 feet wide. The three passing places in the Calumet-
Sag Channel, and dredging to widen the channel in the Calumet and
Little Calumet Rivers, are complete. A small-boat harbor has been
provided at Peoria, Ill. A navigable channel now exists connecting
the Mississippi River at Grafton, Ill., with Lake Michigan, via the
Illinois and Des Plaines Rivers, the Chicago Sanitay and Ship
Canal, and the Chicago River, with a secondary outlet to Lake
Michigan via the Calumet-Sag Channel and the Little Calumet
and Calumet Rivers. The controlling depth of the river as it pre-
vails is 9 feet during extreme low water. The limiting bridge
clearance in the reach from Grafton to Utica, Ill., is 114 feet. The
limiting horizontal clearance which occurs at bridges between
Utica and Lockport, Ill., is 110 feet. The limiting horizontal clear-
ance which occurs between Lockport and Lake Michigan, via the
Chicago Sanitary and Ship Canal and the Chicago River, is 80
feet at the Emergency (Butterfly) Dam, mile 293.1. The limiting
horizontal clearance which occurs at bridges between Lockport
and turning basin 5 in the Calumet River, via the Chicago Sani-
tary and Ship Canal, the Calumet-Sag Channel, Little Calumet and
the Calumet River, is 50 feet. The following work remains to be
done. Preliminary surveys, planning, designs, completion of con-
struction of emergency lock and dam equipment, dredging to pro-
vide a channel 9 feet deep and 300 feet wide, with adequate
widening at critical points and bends from Grafton, Ill., to Lock-
port Lock; and improvement of the Calumet-Sag Channel as fol-
lows: (1) replacement of the emergency (Butterfly) dam in the
Chicago Sanitary and Ship Canal; (2) enlargement of that canal
to Sag Junction, and of the Calumet-Sag Channel, to afford chan-
nels 225 feet wide with usable depth of 9 feet; (3) construction
along the general route of the Grand Calumet River of a channel
with usable depth of 9 feet, 225 feet wide between Little Calumet
River and the junction with the Indiana Harbor Canal, and 160
feet wide thence to Clark Street, Gary, Ind., with a turning basin
at Clark Street; (4) enlargement of the Indiana Harbor Canal
to a width of 225 feet and usable depth of 9 feet between Grand
Calumet River and the vicinity of 141st Street, inclusive; (5)
removal of Blue Island Lock and construction of a lock and con-
trol works in Calumet River near its head and of similar struc-
tures in the proposed Grand Calumet Channel west of the In-
diana Harbor Canal; (6) alteration or elimination of railroad
bridges across these channels lakeward of the Chicago Sanitary
and Ship Canal, or the construction of new railroad bridges to
provide suitable clearances, with apportionment of the costs be-
tween the bridge owners and the United States in accordance with
the principles set forth in agreement dated February 23, 1945.
The total cost of the existing project to June 30, 1954, with regu-
lar funds was $45,210,422, of which $23,211,462 was for new
work, $8,228,502 for maintenance, and $13,770,458 for operating
and care of locks and dams. The above includes the sum of $1,-
735,890 expended between 1927 and 1936 on the operation and
1140            REPORT OF CHIEF OF ENGINEERS, U.                                       S. ARMY,        1954


care of the works of improvement under the provisions of the
permanent indefinite appropriation for such purposes. With Pub-
lic Works funds, the cost was $3,960,735 for new work. With
Emergency Relief funds, the cost was $1,858,936 for new work.
The grand total cost, all funds, was $51,030,093, of which $29,-
031,133 was for new work, $8,228,502 for maintenance and $13,-
770,458 for operating and care. The above includes the sum of
$1,735,890 expended between 1927 and 1936 on the operation and
care of the works of improvement under the provisions of the
permanent indefinite appropriation for such purposes.
                                       Cost and financial summary

                                              Fiscal year ending June 30                                    Total to June
                                                                                                           30, 1954, includ-
                                                                                                           ing fiscal years
                                1950         1951            1952               1953           1954          prior to 19501


New work:
    Appropriated            $   650,000 $    700,000     $   203,860       $    130,250    $   182,683          $31,823,959
    Cost-                       266, 196     403, 794        208, 806           535, 236       586, 854          31, 600, 234
Maintenance:
    Appropriated_            1,399,000     1,825,800      1,660, 000        1,830,623       1,896, 898           23,216,514
    Cost_   -   -            1,388,784     1,757,929      1,490,403         1,858,936       2,070,170            23,027,428


  1 Includes $2,569,102 for new work and $1,028,468 for maintenance for previous projects.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954__                 $52,993
    Appropriated for succeeding fiscal year ending June 30, 1955__....       40,000
    Unobligated balances available     for succeeding fiscal year  ending
      June 30, 1955                                                          92,993
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project_____     _                      _ ___ 126,505,100

                    8.   INACTIVE           NAVIGATION                     PROJECTS
                                                    i                 i



                                                                               Cost to June 30, 1954
                                                          For last                                             EStimated
                                                        full report                                              amount
                Name of project                         see annual                          Operations         required to
                                                        report for-       Construction         and               complete
                                                                                           maintenance


1. Lake Calumet, Ill  ______                                1952                $405,011              11,840
2. New Buffalo Harbor, Mich.'    -                        2 1885                  83,000          -    -


1 No commerce reported.
2 Abandonment recommended in 1868.

                                       9.. FARM         CREEK, ILL.
   Location. The Farm Creek watershed in Tazewell County, Ill.,
is 60 square miles in extent. The stream empties into the Illinois
Waterway at mile 162 above the mouth.
   Existing project. The project involves the construction of two
compacted-earth flood-detention dams, the Fondulac Dam on Fon-
              FLOOD CONTROL-CHICAGO., 'LL., DISTRICT          1141
dulac Creek, Tazewell County, Ill., approximately 1.5 miles east-
erly of East Peoria, Ill., and Farmdale Dam on Farm Creek, Taze-
wel County, Ill., approximately 2.5 miles easterly of East Peoria,
Ill., and improvements to Farm Creek, Cole Creek, and Kerfoot
Creek channels in East Peoria, Ill. The Fondulac Dam has a
maximum height of 67 feet above the river bed and a reservoir
capacity of 3,780 acre-feet. The Farmdale Dam has a maximum
height of 80 feet above the river bed and a reservoir capacity of
1:5,500 acre-feet. Linear feet of channel improvements are Farm
Creek, 12,000 feet; Cole Creek, 1,875 feet; Kerfoot Creek, 900 feet.
The project when completed will provide complete protection to
the residential, business, and highly developed industrial areas of
East Peoria, Ill., against design flows in Farm, Cole, kerfoot, and
Dempsey Creeks having expected frequency of occurrence of once
in about.-100 years. The current.:estimated construction cost
 (1954) rIs:$9,838,000, including lands and damages with $11,800
annually for maintenance. The existing project was authorized
by the Flood Control Act approved December 22, 1944      ;  (See H.
Doc. 802;-17th, Cong., 2d sess.)
   Local ooperation. Local interests have given assurances that
they will provide adequate maintenance of channels existing to
be constructed, prescribed and enforce such regulations as may be
necihsary to prevent encroachments, and provide the rights-of-
way and perform the highway bridge alterations required"f6r'the
proposed channel improvements. Final assurances of localFco-
operation were accepted by the Chief of Engineers on February 17,
1950.
   Operations and results during fiscal year. New work: Work on
acquisition of lands for Farmdale and for the Chiannel Improve-
ments was continued. Agreement with the T. P. & W: RR., and
construction of Farm Creek Channel Improvements were con-
tinued; both by contract, and miscellaneous work' was accom-
plished by hired labor. The total cost of new work was $1,028,733.
   Maintenance: Maintenance of remedial works at Fondulac was
conducted by hired labor at a cost of $19,360.
   Total cost for the fiscal year was $1,048,093.
   Condition at end of fiscal year. The project is 99 percent com-
plete. Construction was initiated in August 1947, with the esti-
mated date of completion in September 1954. Preliminary
studies, designs, and plans and specifications, by hired labor, are
complete. Fondulac Dam and Farmdale Dam are both 100 per-
cent complete. Construction of Farm Creek Channel Improve-
ments is 98 percent complete. The work remaining to be done
consists of completion of Channel Improvements, miscellaneous
hired labor work, and the agreement with the T. P. & W. RR.
   The total costs to June 30, 1954, were $9,890,132, of which
 $9,839,772 were for new work and $50,360 for maintenance.
1142           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                   Cost and financial summary

                                            Fiscal year ending June 30                             Total to June
                                                                                                  30,1954, includ-
                                                                                                  ing fiscal years
                           1950            1951          1952            1953           1954           to1950
                                                                                                   prior

New work:
                   -_
   Appropriated .....  $1,860,200    $     900,000    $1,500,000   $     771,500     -$275,147         $9,951,553
   Cost---------------
       ................2,962,280         1,314, 610      672,606       1,191,061      1,028,733         9,839,772
Maintenance:
   Appropriated........ ....                10,000        11,000          10,000         19,400             50,400
   Cst-...-__............... ...             8,440        11,619            ,10941       19,360             50,360


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_                    $18,593
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955-                                                                    18,593

   10 LACEY LANGELLIER, WEST MATANZAS,                                               AND KERTON
VALLEY DRAINAGE AND LEVEE DISTRICTS, ILLINOIS RIVER, ILL.
   Location. In Fulton County, Ill., on the right or west bank of
the Illinois River between miles 11.8 and 119.3 above the mouth,
and bounded by the Illinois River, Otter Creek, State Highway 10,
and the bluffs.
   Existing project. The project involves the enlargement of 1.6
miles of upper flank levee, raising and enlargement of 7.7 miles of
riverfront levee, degrading of 1.2 miles of existing riverfront
levee, raising and enlargement of 4 miles of lower flank levee, and
alterations to existing pumping stations. The project when com-
pleted will afford additional flood protection to approximately
7,800 acres of highly productive farmland and improvements.
The project was authorized by the Flood Control Act approved
June 22, 1936. (See H. Doc. 182, 72d Cong., 1st sess.) The cost
of the completed project is $1,234,024; lands and damages, $36,-
000; total $1,270,024.
   Local cooperation. Fully complied with.
   Operations and results during fiscal year. Wave wash repairs
were completed by hired labor. The total costs for the fiscal year
were $44,327, all new work.
   Condition at end of fiscal year. Construction is completed.
Construction was initiated in November 1947 and was essentially
completed in December 1949, by contracts. Wave wash repair
by H.L. was completed in 1954. The total costs to June 30, 1954,
were $1,234,024, all new work.
                           FLOOD CONTROL-CHICAGO.,                ILL., DISTRICT                   1143
                                       Cost and financial summary

                                              Fiscal year ending June 30                   Total to June
                                                                                           30, 1954, includ-
                                                                                           ing fiscal years
                                1950         1951        1952        1953       1954        prior to 1950


New work:
      Appropriated                       -- $100, 000                $25, 000                   $1, 235, 002
        ost---------....   .   $455,63         7,02      $3,861       20, 784   $44, 327          1,234,024

Other new work data:
   Unobligated balance, fiscal year ending June 30, 1954 -_                  $977
   Unobligated balances available for succeeding fiscal year ending June 30,
            1955-----------------------------------------------------------------                      977

11.     COAL         CREEK     DRAINAGE         AND LEVEE                   DISTRICT,       ILLINOIS
                                             RIVER, ILL.

    Location. In Schuyler County, Ill., on the right or west bank of
the Illinois River between miles 85 and 92 opposite the city of
Beardstown, Ill.
    Existing project. The project involves the construction of ap-
proximately 3.8 miles of setback levee; degrading of 1.9 miles of
existing riverfront levee; enlargement of 0.1 mile of upper flank
levee and construction of 130 feet of concrete wall; enlargement
of 1.9 miles of riverfront levee, 2.4 miles of lower flank levee, and
0.4 mile of bluff levee; and alterations at highway bridge and to
an existing pumping station. The project was authorized by the
Flood Control Acts approved June 22, 1936, and June 28, 1938.
The levee degrading and the construction of the setback levee are
described in House Document 182, 72d Congress, 1st session. For
description of remaining items of the project, see Upper Missis-
sippi River Basin, Chicago district. The cost of the completed
project is $1,923,145, including $10,728 contributed funds; lands
and damages, $72,000; total, $1,995,145.
   Local cooperation. Fully complied with. Local interests have
contributed the sum of $10,728 for raising a portion of Illinois
State Highway 100 in connection with construction of the author-
ized project.
    Operations and results during fiscal year. The total cost for
the fiscal year was $59.
    Condition at end of fiscal year. The project is complete. The
total costs to June 30, 1954, were $1,923,145, including $10,728
contributed funds.
.1144        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                   Cost and financial summary

                                          Fiscal year ending June 30                           Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                            1950         1951        1952           1953            1954       prior to 19501


New work:
    Appropriated ..__      $ 18, 000   -$95, 000    $46,500    1   -$4,      000   -$4, 483        $1,.912, 417
   .Cost' -                 940,650       21,066      6, 376              9, 964         59         1,91.2,417


1In addition $10,728 for new work was expended from contributed funds.

                   12. MOUTH OF SANGAMON                           RIVER, ILL.
   Location. The mouth of the Sangamon River is 98 miles above
the mouth and on the east bank of the Illinois River, 9.4 miles
above the Beardstown Highway bridge. This project extends for
several miles upstream from the mouth of the river. This portion
of the Sangamon River forms the boundary line between Mason
County on the northwest and Cass County on the southwest.
   Existing project. This project provides for the excavation of a
ntew boutlet :channel for the Sangamon River approximately 6.7
miles long and 200 feet wide extending from Hager Slough oni the
Illinois River to mile 6.7 above the mouth of the Sangamon River,
and a diversion channel and remedial works necessary for.the
maintenance of a highwater table inidjacent wild game reserves.
The cost of the completed Project is $768,273, including $7,183
contributed funds; lands and damages, $23,000; total, $791,273.
Annual cost of maintenance, estimated in 1949, is $15,000.. 'The
project was authorized by the Flood Control Act approved June
22, 1936, and described in House -Document 186, 72d Congr.esst1't
session.
   Local.cooperation. Section:2 of the FloodControl Act appr
Jine 28, 1938, ' applies. Local interests, h Aever, .provided all
rights-of-way for the project in order: thaatadditional chainel
work could be accomplished, and eop  qbuted     $7,183 for the pur-
pose.
  Operationsand results during fiscal                       yiear
                                                Maintenance. Snag-
ggg and    clearing operations    were conducted by hired labor at a
cost f' $21,287.
  :The total costs for the fiscal year were $21,287, all maintenance.
  C..ondition at end of fiscal year. Construction is completed. 'the
tOfal costs to June 30, 1954, including $7,183 contributed funds,
                     FLOOD CONTROL--CHICAGO., ILL., DISTRICT                                                   1145
were $812,260, of which $768,273 were for new work and $43,987
for maintenance.
                                   Cost and financial summary

                                          Fiscal year ending June 30                                   Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                            1950         1951            1952            1953               1954         priorto 1950

New work:
   Appropriated. --------
                       . ---------- .   -- -----------     I       -   .....----
                                                                           ---      -----    ....-            $761, 090
   Cost--                   $36, 523      $   818    -$1, 556             $15,504-1                            761, 090
Maintenance:
   Appropriated ........      5, 800       5, 000         6, 000            5,900           $21, 700             44,400
   Cost-----------------         119       4,718          9,154             8,709            21,287              43,987


1 In addition $7,183 for new work was expended from contributed funds.

                  13. BEARDSTOWN, ILLINOIS RIVER, ILL.
   Location. Beardstown is located in Cass County, Ill., on the
south bank of the Illinois River at river mile 89, about 70 miles
below Peoria, Ill.
   Existing project. The project provides for construction of a
new section of floodwall to replace that lost or damaged, and for
raising, strengthening, and extending the remaining portion of
the floodwall and adjacent levees, and the modification of existing
levees in the adjacent Lost Creek, South Beardstown, and Valley
Drainage and Levee districts. The project when completed will
afford flood protection to the city of Beardstown and adjacent
land against the maximum flood of record, having an expectancy
of once in 80 years. The project was authorized by the Flood
Control Act approved May 17, 1950 (see H. Doc. 332, 81st Cong.).
The estimated cost, revised in 1954, is $4,120,000; lands and dam-
ages, $50,000; total $4,170,000.
  :Local cooperation. Local interests have indicated that require-
ments will be met.
   Operationsand results during fiscal year. Continuation of the
Design Memorandum #1 was accomplished by H.L. at a cost of
$31,364.
   Condition at end of fiscal year. Construction has not been
started.
   The total costs to June 30, 1954, for planning were $52,882.
1146        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                    Cost and financial summary

                                               Fiscal year ending June 30                    Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                             1950         .   1951.1952               1953       1954        prior to 1950

New work:
  Appropriated        ---------         ------------ ------           $30, 000   $30, 000            $60, 000
   Cost -    -    -                 -                                  21,518     31,364              52,882


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_                   $7, 118
    Appropriated for succeeding fiscal year ending June 30, 1955 _.-...     400,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955_ --         amont-nededto-b-appopri--d-orcmp                 407, 118
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project   -                                        3,660,000

14. PEKIN-LA MARSH DRAINAGE AND LEVEE DISTRICT, ILLINOIS
                       RIVER, ILL.
    Location. On the right or west bank of the Illinois River, 149.6
to 155.2 miles above its mouth, and across the river from Pekin,
Ill., which is 153 miles above the mouth.
   Existing project. This project involves the raising and enlarg-
ing of approximately 5.6 miles of riverfront levee and 0.7 mile of
flank levee along La Marsh Creek, and the construction of a iew
flank levee along that creek. Additional flood protection will be
provided for 3,010 acres of land and 1.6 miles of concrete high-
way. Raising and strengthening the levee at three locations are
estimated to cost $30,000, and will increase the total estimated
construction cost to $172,800, plus lands and damages, $7,000.
The existing project is one of 15 projects authorized by the Flood
Control Act approved June 22, 1936, providing for levee setbacks,
improvements to floodway, and improvement of existing levees
along the Illinois River and is described in House Document 182,
72d Congress, 1st session.
    Local cooperation. Fully complied with.
    Operations and results during fiscal year. Work of raising and
strengthening the levee was accomplished by contract at a cost of
$24,385.
    Condition at end of fiscal year. Construction of work author-
ized by the Flood Control Act approved June 22, 1936, about 6.9
miles of earth levee was completed in 1940. The work of raising
and strengthening the levee is complete except for a bituminous
impregnation of the ballast under the C. & N. W. Railway tracks.
The total costs to June 30, 1954, were $168,383.
                  RIVERS AND HARBORS--CHICAGO,                               ILL., DISTRICT                 1147
                                      Cost and     financial      summary


                                                 Fiscal year ending June 30                        Total to June
                                                                                                  30, 1954, includ-
                                                                                                  ing fiscal years
                               1950         1951               1952         1953       1954         priorto 1950


New work:
   Appropriated                              -                 $30, 000 -                                    $172, 788
   cost                                                               s                  24,3s5
                                                                                       s$s----------------ii1 16s,3s3

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954          -      -   $4,405
    Unobligated balances available for succeeding fiscal year ending June 30,
          1955___-_     ____                                                                                 4,405

    15. UPPER MISSISSIPPI                        RIVER BASIN,                CHICAGO          DISTRICT
   Location. The Mississippi River Basin above the Ohio River,
exclusive of the Missouri River Basin, in the Chicago district.
   Existing project. The Flood Control Act of June 28, 1938, ap-
proved the general comprehensive plan for flood control and other
purposes in the Upper Mississippi River Basin described in Flood
Control Committee Document 1, 75th Congress, 1st session, with
such modifications thereof as in the discretion of the Secretary of
the Army and the Chief of Engineers may be advisable, and au-
thorized $6,600,000 for reservoirs and $2,700,000 for local flood
protection works on the upper Mississippi and Illinois Rivers; the
reservoirs and local proctection projects to be selected and ap-
proved by the Chief of Engineers. The act specifically provides
that the authorization shall include the enlargement and extension
of a system of levees located on the south side of the Sangamon
River east of Chandlerville, Ill., as set forth in House Document
604, 75th Congress, 3d session. The Flood Control Act approved
December 22, 1944, authorized to be appropriated the additional
sum of $10,000,000 for prosecution of the comprehensive plan ap-
proved in Act of June 28, 1938. The Flood Control Act approved
July 24, 1946, authorized an additional appropriation of $10 mil-
lion for prosecution of the comprehensive plan. The following
individual projects located in the Chicago district were considered
in the comprehensive plan:
                                      Estimated cost of reservoir
Name-------_                               _Chandlerville                                   No. 2 reservoir.1
Tributary basin_..                                                          Illinois.
State                                                                          Do.
Total estimated cost     2                                                  $45,300,000

                     Estimated or actual construction cost of levees
Illinois River:
     South Beardstown and Valley levee and drainage districts,
        Illinois River, Ill-----------------------------------                                  3220,729.43
      Crane Creek levee and drainage district, Illinois River, Ill ... _ .                         68,897.65
      Coal Creek drainage and levee district, Illinois River, Ill                  ......     4 1,923,145.00
      Iig Lake levee and drainage district, Illinois River, IlL -    _                            144,909.89
  1Recommended for abandonment in pending comprehensive flood control report for Illinois River and
tributaries.
  SRevised in 1954,
  a Completed. See table "Inactive flood-control projects" on p. 1148 for reference to previous report.
  4 See "Coal Creek drainage and levee district, Illinois River, Ill., on p. 1143 for further data.
1148            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                    16. INACTIVE            FLOOD        CONTROL            PROJECTS

                                                                       Cost to June 30, 1954
                                                        For last                                          Estimated
                   Name of project                    full report,                                         amount
                                                      see annual                   Operations            required to
                                                      report for-    Construction     and                 complete
                                                                                  maintenance

                 ILLINOIS RIVER, ILL.

1. Banner special drainage and levee district           1943           $274,822                              (1)
2. Big Lake drainage and levee district-.........       1943             144,910                            (1)7
3. Big Prairie drainage and levee district - - --        (2)            .........                           $177,000
4. Crane Creek drainage and levee district...   -       1941               68,898                            (1)
5. East Liverpool drainage and levee district .-        1941             207, 826                           (1)
6. East Peoria drainage and levee district.......       1946             279, 963                           (1)
7. Hennepin drainage and levee district-.........       1940             109,593 -(1)
8. Kelly Lake drainage and levee district--......       1947               13,153                          1,056,847
9. Liverpool drainage and levee district-.........      1943             117,731  3-----
                                                                                    1-------                  (1)
10. Lost Creek drainage and levee district 3 --                                        --------------
                                                         1938                                                (1)
                                                                                                              (1)
11. Rocky Ford drainage and levee district- .....        1941            108,797                              (1)
12. Seahorn drainage and levee district-...-------       1945             32,281                              (1)
13. South Beardstown and Valley drainage and             1943            220,729                              (1)
      levee districts.
14. South Beardstown drainage and levee district-        1942            171,839                             (1)
15. Spring Lake drainage and levee district-..----       1941            185,980                             (1)
16. Thompson Lake drainage and levee district_--         1952              9,465                            1, 040,535
           KANKAKEE RIVER, ILL. AND IND.

17. Levee between Shelby Bridge and Baum's               1938                           -                   1,130,000
      Bridge in Ind.
               SANGAMON RIVER, ILL.

18. Bell drainage district.............__ -------        1946             1,112                               168, 888
19. Clear Lake levee............._.. ____________        1940             2,680                               279,320
20. Farmers Levee and drainage district:-..........      1942            155,562             --      I       (1)
21. Levees east of Chandlerville        -.....
                                        ......-...       1946             5,606                             1,164, 394
22. Mason and Menard drainage district--_ --             1940            93,808                              (1)
23. Near Springfield on Sangamon River, Ill_ .-          1941            97, 743
24. Oakford special drainage district . - -              1940            38,417
25. Panther Creek levee         -       -                1938                                                229,000
26. Sangamon River and Salt Creek, Ill _. ----           1938                                                 51,000
27. Sangamon River, from mouth of Salt Creek to          1938                                              2,510,000
      Roby, Ill.
28. Tar Creek Levee......._...... ___________            1946              1,425                              280,575
                  SALT CREEK, ILL.

29.   Donovan Levee -.........           -     -__-____ 1945               1,821                              113,179
30.   East of Hubly Bridge____                          1945                 572                               72,428
31.   Lussenhop levee.________            _________     1945                 116                               43,884
32.   Salt Creek in vicinity of Middletown, Ill -.--.   1940                  48                              218 952
33.   Swiger, Whitney, Young-Hoblit levee _......       1945                 399                               41,601
34.   Watts levee     .......
                        __...._- _.. _.                 1945               1,031            -....-            138,969


1 Completed.
2 Never activated.
3 Reported previously by St. Louis District as completed under provisions of Sec. 6 of Flood Control
Act approved May 15, 1928.


                             17. GENERAL INVESTIGATIONS
   Examinations and surveys. The costs and expenditures for the
work during the fiscal year were $9,311 for navigation studies,
$616 for flood control studies, and $15,705 for special studies;
total, $25,632. There were no accounts receivable at the end of
the fiscal year. The unexpended balances at the end of the fiscal
year amounting to $102 for navigation studies and $3,404 for spe-
cial studies, a total of $3,506, will be applied to continuing work
on the Illinois Waterway, Illinois and Indiana, 12-foot channel re-
port, and the survey report on Great Lakes water levels. The ad-
ditional sums of $7,000 for navigation studies, $62,100 for flood
                 RIVERS AND HARBORS-CHICAGO, ILL., DISTRICT                                      1149
control studies, and $10,000 for special studies, a total of $79,100,
can be profitably expended in fiscal year 1955.
   Coalection and study of basic data.: The cost of the work during
the fiscal year was $4,993. The funds were used for hydrologic
studies in the amount of $3,554 and for flood investigations in the
amount of $1,439. The balance unexpended at the end of the
fiscal year amounting to $7 will be,applied to the continuation of
hydrologic studies. The additional sum of $5,400 can be profit-
ably expended during fiscal year 1955 for flood emergency and
hydrologic studies, $4,400, and for flood investigations, $1,000.
    18. INSPECTION           OF COMPLETED                 FLOOD CONTROL WORKS
   Purpose of inspections. Annual inspections are made with local
interests, of all projects improved or extensively repaired at Fed-
eral expense in order to determine compliance of local interests
with assurances given to the United States regarding maintenance
of the projects, to determine physical condition of the levees and
appurtenances and to receive necessary information for use in
flood emergencies.
   Operations and results during fiscal year. Inspection of 29
levees was made in the Chicago District involving approximately
177 miles of embankment. The cost of work during the year
amounted to $5,982.
                                  Cost and financial summary

                                        Fiscal year ending June 30                       Total to June
                                                                                         30, 1954, includ-
                                                                                        ing fiscal years
                           1950        1951        1952        1953           1954        priorto 1950

Maintenance
   Appropriated ......                  $6,000      $4, 900     $7, 000       $6, 300            $24, 200
   Cost_-                                4,835       6,004       7, 029        5,982              23,850



   19. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
   Snagging and Clearing of Navigable Streams and Tributaries
in the interests of Flood Control (Sec. 13 of the 1946 Flood Con-
trol Act).
   Channel straightening, removal of snags, brush, and other de-
bris, were performed by hired labor at Indian Creek at a cost of
$8,906.
                                  Cost and financial summary

                                        Fiscal year ending June 30                       Total to June
                                                                                        30,1954, includ-
                                                                                        ing fiscal years
                           1950        1951        1952        1953       1   1954        priorto 1950

New work:
   Appropriated-........   $78,000     $38,200     $20,000     $ 7,030         -$94             $193,336
   Cost.................    35,454      47,009      49,101      29,216         8,906             193,336



  Flood control emergencies-repairand flood fighting and rescue
work. (Section 210 of the 1950 Flood Control Act and supple-
mental authorizations) .
1150            REPORT           OF CHIEF OF ENGINEERS, U.                  S. ARMY,     1954


                                         Cost and financialsummary

                                               Fiscal year ending June 30                    Total to June
                                                                                            30, 1954, includ-
                                                                                           ing fiscal years
                                  1950        1951        1952        1953        1954       prior to 1950

Maintenance:
   Appropriated--------$58,300                           $182,014      -$983       -$304            $342,027
   Cost.--_ -----          --      48, 374     43,685     164,234      46,743         -5             342,027
      IMPROVEMENT OF RIVERS AND HARBORS IN THE
               DETROIT, MICH., DISTRICT

  This district comprises the eastern end of the upper, and eastern
half of the lower, or southern peninsulas of Michigan, northwest-
ern Ohio, and a small portion of northeastern Indiana, embracing
the United States waters of Lakes Huron, St. Clair, and the west-
ern end of Lake Erie with their tributary watersheds from the
head of St. Marys River and the Straits of Mackinac to Sandusky
Bay, exclusive.
                                  IMPROVEMENTS


                 Navigation                                  Flood control
                                      Page                                             Page
1.   St. Marys River, Mich ----- 1151       12. Sebewaing, Sebewaing River,
2.   St. Clair River, Mich .____.    1158         Mich--...      -     __----        1179
3.   Detroit River, Mich.---------   1161   13. Red Run,       Clinton River,
4.   Au Sable Harbor and Harbor                   Mich------------------             1180
        of Refuge at Au Sable River          14. Inactive flood control projects_     1182
         (Oscoda), Mich-----------1165       15. General investigations----      --   1182
5.   Saginaw River, Mich ---- _      1167   16. Inspection of completed flood
6.   Port Austin Harbor, Mich-.-     1169         control works------------          1182
7.   Port Sanilac Harbor, MichL..    1170   17. Flood control work under
8.   Rouge River, Mich.              1172         special authorization-------       1183
9.   Toledo Harbor, Ohio--------- 1175
10.   Inactive navigation projects_ _ 1178
11.   River and harbor work under
        special authorization------- 1178


                          1. ST. MARYS RIVER, MICH.
   Location. St. Marys River is about 63 miles long, and flows in
a southeasterly direction between the State of Michigan and the
Province of Ontario, Canada, from the eastern end of Lake Su-
perior into the northern end of Lake Huron. (See U. S. Lake Sur-
vey Charts Nos. 61, 62, and 63.)       At Sault Ste. Marie, Mich.,
about 14 miles downstream from Lake Superior, are located four
parallel locks and a hydroelectric power plant.
   Previous projects. Authorized by River and Harbor Acts of
July 8, 1856, July 11, 1870, June 14, 1880, August 2, 1882, and
August 5, 1886. For further details, see page 1955, Annual Re-
port for 1915, and page 1529, Annual Report for 1938.
   Existing project. This provides for channels through St. Marys
River, which, at low water datum, are suitable for vessels draw-
ing 20 feet when upbound and 24 feet when downbound, with a
least width of 500 feet in the upbound and 300 feet in the down-
bound routes, and for channels between Lake Superior and the
falls having minimum widths of 1,000 feet and a depth of 27 feet
below low water datum through Round Island Shoals and Middle
Ground and 26 feet through Vidal Shoals. The specific improve-
ments include dredging shoals between the mouth of the river
and Lake Munuscong; excavating channels from Lake Munuscong
                                                                             1151


       Sig 37-1151-1182
1152     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

to Lake Nicolet on either side of Neebish Island, a distance via
West Neebish of 14 miles and via Middle Neebish 15 miles, the
Middle Neebish, or upbound, route to have a least width of 500
feet, and the West Neebish, or downbound, route a least width of
300 feet; widening and deepening the west side of the channel in
Lake Nicolet to a maximum width of 1,000 feet over a length of
5,500 feet, with a depth of 26.5 feet for anchorage and maneuver;
dredging to widen and deepen the upper entrance channel into Lake
Nicolet; dredging through shoals between the lower end of the ca-
nals and the upper entrance to Lake Nicolet, including extension of
anchorage and maneuver area below the locks and the widening of
angle at black gas buoy No. 33; constructing compensating works
at the falls; constructing remedial works at the inlet of the power
canal of the Carbide Power Co.; deepening and widening the tail-
race of the United States power plant and construction of the first
step (14,000 kilowatt capacity) of a new hydroelectric power plant
of 45,000 kilowatt ultimate capacity; constructing and operating
four locks, two canals, and an emergency dam for each of the
canals at the falls; including a new lock on site of Weitzel lock
and replacement of Poe lock, removal of Bridge Island and struc-
tures therein to' secure a depth of 27 feet at low water, deepening
the approach channels and reconstruction of approach piers;
widening and deepening the channels through Vidal Shoals; wid-
ening the channel from Point Louise to Brush Point to bottom
width of 1,000 feet and Brush Point Turn to bottom width of
1,200 feet; widening the channel across Point Iroquois Sh6tdhs a
maximum width of 1,500 to 5,300 feet as measured from the cen-
ter line of Birch Point Range, with a depth of 27 feet for anchor-
age and maneuver.
  The following table shows the principal features of the locks
and emergency dams. All structures are located at Sault Ste.
Marie, Mich.
                    RIVERS AND HARBORS-DETROIT, MICH., DISTRICT                                                     1153

                                                                                     Lock
             Principal features
                                                       Poe                Davis                Sabin          MacArthur

Miles above mouth....           ..--------------- 47------- ---- 47....                    47-----------47.
Clear width of chamber            _..feet _ 95------               __  80-----------       80-----------..      80.
Leugt).ibetween miter sills_ __.do-....704                             1,350 ---------
                                                               .----------                 1,350---------       800.
Lift'      _________-------__          ..do.-.... 21.7--------....     21.7---------       21.7 .-.. . 21.7.
Depth:on upper breast wall 1 ....         do.... 21.8----...-----..    24.3.---------      24.3 ....---------   31.
Depth on lower breast wall 1'       _.. do .-- 16.6 _ -.... 23.1___---------               23.1 ...         .   31.
Foundation.....________________________           Rock                 Rock.....--------   Rock ........ Rock.
Type of construction ...     __._........_ Masonry ..... Concrete- ...                     Concrete        .--- Concrete.
Estimated cost .___....__________________ 2 $4,738,865 ... 3 $6,200,000 .                  4 $3,275,000 .___ $12,909,440.
Actual cost      ._______________________         5 $2,837,337 ... 6 $2,200,000 ...        7 $1,750,000 ..           (8)
Completed (open to commerce)-...... Aug. 3, 1896_.                     Oct. 21, 1914-_     Sept. 18, 1919_. July 11, 1943.


                                                                    Emergency dam for-
      Principal features
                                                South Canal                                    North Canal

Miles above mouth.--------- 47   --      _--                                  47.
Estimated cost .----------- (10)             -------                          $300,000.
Type- ..-...................    Steel stop-logs recessed into lock            Removable trusses, revolving wickets,
                                   masonry.                                     and steel stop-logs.
Cost, completed .      ..----------
                                (10)___                         _             $269, 224. 9
Years completed----------
                .......... 1943 and 1945.........----------------             1922.


  1 At low water, 601.1 above and 579.4 below.
  2.Includes cost of deepening and enlarging South Canal.
  3 Includes cost of North Canal.
  4 Includes canal excavations to provide necessary approaches to lock, canal walls, and piers, and emer-
gency dam.
  5Excludes cost of deepening and enlarging South Canal, $1,653,378.
  6 Excludes cost of North Canal, $2,572,611.
  7 Excludes cost of canal excavations to provide necessary approaches to lock, canal walls, and piers, and
emergency dam, $662,919.
  8 Construction about 97 percent complete. Actual costs to June 30, 1954, $12,718,806.
  9 Including engineering office, and inspection.
  10 Not separable from cost of locks.
  Note.-The limiting draft to the locks is determined by the depth over the breast walls.


   The Poe lock was operated and maintained under the perma-
nent indefinite appropriation from August 3, 1896, the Davis lock
from October 21, 1914, and the Sabin lock from September 18,
1919, to the end of the fiscal year 1935. The original State locks
were operated and maintained under the same appropriation from
June 9, 1881, to November 2, 1886, after which they were de-
stroyed by excavation for the present Poe lock.
   The Weitzel lock, destroyed in 1942 by excavation for the Mac-
Arthur lock, was operated and maintained under the same appro-
priation from September 1, 1881, to the end of the fiscal year
1935.
1154            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                              1954


   In the following table are stated other characteristic features
of the channel improvements belonging to the existing project.
                                                                                 1                 I            I
                                                        i




                                                       Dis-                                                     Project da-
                                              Length tance Used by up-                Project                  tum planes
                                                                                                       Project above
                                                of    from    or down-                                                 mean
        Name of improved channel                                                      width            depth      tide at
                                             channel mouth     bound                   (feet)          (feet) New York
                                              (feet) of river  vessels
                                                     (miles)                                                       (feet)
                                             .1   -     1-          1            1                 I

Point Iroquois Shoals anchorage-.......... 16,000            59 Both         - - 1,500-5,300            27                601.5
Round Island middle ground-.............                     57 -- do-- --                              27                601.5
Round Island Shoal 1___.......__.._._.._ 5, 000              57 --- do-------          1,000            27                601.5
Round Island Shoal 2_....... .__________9,800                54                        1,000            27                601.5
Brush Point to Point Louise-............       9,000         52 --- do------     1,000-1,200            26                601.4
Vidal Shoals __
             .............
                ___...._.__                 .  9, 100        48                  1,000-1,500            26                601.2
South Canal----........------------------                    47 -do-------
    West approach to MacArthur lock_--
    M acArthur lock......................
                                               8,235
                                                                                          I10880        27
                                                                                                        31
                                                                                                                          601.1
                                                                                                                          579.4
    West approach to Poe lock-..........                                                  1108          24                601.1
    Poe lock-----------------------                                 -B.oh__                100         216. 6             579.4
    East approach to MacArthur lock....                                                    362          27                579.4
    East approach to Poe lock......__...                                                   370          19.5              579.4
North Canal........._______...........____ 8,520             47

    West approach.................____                                                        80   24
    Davis lock-------------------------                                                       80 323. 1
    Sabin lock__--- ------ ------ -----                                                       80 323. 1                   579.4
    East approach_________                 __                                                312   24.5                   579.4
Course. 1, Bayfield Channel, anchorage         9,237              45Both             1,300-1,500   26                     579.3
  and maneuver area.
Courses 2 and 3, Little Rapids --------       24,193         40 -_do. . .                  600          25          579.2-578.9
Lake N icolet ......
                  _      ...... ...... ...... 22,000         36     ---do- -..           1,500          26                578.8
Lake Nicolet anchorage. __                     5, 500        38 --do.....                1,000          26.5              578.8
Middle Neebish (upbound route):
    Course 5, lower end of Lake Nicolet.. 17,900             33 Up .            500                     21                 578.8
    Course 6, dike_........                   16,918         30 ...---
                                                                    do....-     500                     21          578.7-578.6
    Course 7, Munuscong Channel ...... 17, 586               27 -.. do ...----  500                     21                578.6
    Course 9, Sailor Encampment Chan- 12,400                      do.......---- 500
                                                             22 ---                                     21                578.5
     nel.
West Neebish, (downbound route):
    Course 4, lower end of Lake Nicolet_. 10, 762            34 Down __.                   300          25                578.8
    Course 5, lower end of Lake Nicolet_._ 23,370            29 ..-do- ...                 300          25                578.8
    Course 6, Rock Cut..............___       14,064         27 ... do-....                300          27          578.7-578.6
    Course 7_                                 13, 270        24 _do-----                   300          25                578.5
   Course 8, Moon Island-..............       12, 600        21 -- _do-.....               300          25                578.5
Lake Munuscong, Twin Island to Lime 26,459                   12 Both ----                1,000          26                578.5
Island.
Crab Island Shoal......-----------------       1,300     ---
                                                         --..- --       do              ---- -.-- 26                      578.5

  1 2 Channels past Bridge Island, each 108 feet wide; minimum width of connecting channel, 304 feet.
  2 Refers to datum plane of 579.4; project depth at datum plane in effect at time of construction was 18 feet.
  s Refers to datum plane 579.4; project depth at datum in effect at time of construction was 24.5 feet.


   The project depths are referred to low water datum for Lakes
Superior and Huron, which are 601.6 and 578.5 feet above mean
tide at New York.
   Each year the St. Marys River rises and falls about 1 foot as
measured by the monthly mean levels. During the navigation
season the difference between the highest and lowest monthly
mean levels above the locks, since 1871, has been about 4 feet, and
below the locks, since 1903, about 4.3 feet. In addition to these
changes in level, occasionally a considerable oscillation takes place
within 2 or 3 hours, which is somewhat in the nature of a seiche;
such changes amounting to over 5 feet have been known to occur
within 3 hours.
     The estimate of cost for new work, revised in 1954, is $100,-
000,000, exclusive of amounts expended on previous projects. The
latest (1954) approved estimate for annual cost of maintenance is
$1,601,900, of which $1,262,000 is for operating and care of locks.
                  RIVERS AND HARBORS-DETROIT, MICH., DISTRICT                                          1155
  The existing project was authorized by the following River and
Harbor Acts:

     Acts                          Work authorized                                    Documents

July 11, 1870   Weitzel lock (replaced in 1943 by MacArthur lock),
                                                                 1    Report by Maj. O. M. Poe, Corps
                  widening and deepening existing State Canal.          of Engineers, not published.
Aug. 5, 1886    Poe lock 1......                                      H. Ex. Doc. 72, 49th Cong., 2d sess.
July 13, 1892   Dredging through shoals above the falls and the H. Ex. Doec. 207, 51st Cong., 2d
                  shoals below the falls between the lower end of the   sess., and Annual Report 1891,
                  canal and the upper entrance channel into Lake        p. 2810.
                  Nicolet (Hay Lake).
June 13, 1902
Mar. 2, 1905    iEnlarging  the old canal................__
                                                         _____....
                                                            .      .. H. Does. 128, 56th Cong., 2d ses.,
                                                                        and 215, 58th Cong., 3d sess.
June 13, 1902 Hay Lake and Neebish Channels work in that section      H. Doc. 128, 56th Cong., 2d sess.
                  of the river below the locks.
Mar. 3, 1907 Davis lock, second canal, and emergency dam-........     H. Doc. 333, 59th Cong., 2d sess.
                                                                        (plan 3).
Mar. 3, 1909 Lease of waterpower at the falls. Lease entered into
                  with Michigan Northern Power Co. Provided for
                  the construction of remedial and compensating
                 works.
July 25, 1912 Fourth lock (renamed "Sabin" lock in 1943).-----        H. Doec. 64, 62d Cong., 1st sess.
Mar. 4, 1915 Deepening tailrace of the power plant-...............
Sept. 22, 1922 Widening upper approach to the canals through District engineer report, Oct. 29,
                  Vidal Shoals, extension of anchorage and maneuver     1920.
                 area below the locks.
Jan. 21, 1927 Removal of Round Island middle ground, extension        H. Doc. 270, 69th Cong., 1st sess.
                 of Northwest Canal pier, and widening channels
                 middle Neebish route.
July 3, 1930 Deepening channels throughout the downbound H. Doc. 253, 70th Cong., 1st sess.
                 route.
June 26, 1934 3 Operation and care of canal and locks provided for
                 from War Department appropriations for rivers
                 and harbors.
Aug. 30, 1935 Widening Brush Point turn and the channel from River and Harbor Committee               2
                 Brush Point to Point Louise.                          Doc. 53, 74th Cong., 1st sess.
Mar. 7, 1942 Construction of new (MacArthur) lock on site of for- H. Doc. 218, 77th Cong., 1st sess.
   (Public       mer Weitzel lock deepening the approach channels
  Law 490,       to 27 feet, and reconstruction of approach piers.
  sec.    17) 4 This act named the "MacArthur"lock and changed
  June 15,       the name of "Fourth" lock to "Sabin" lock.
  1943 (Pub-
  lic Law 72,
  78th Cong.,
  1st sess.)
Mar. 2, 1945 Removal of Bridge Island and construction of a new H. Doec. 679, 78th Cong., 2d sess.
  jPublic         hydroelectric powerplant.                                 and H. Doec. 339, 77th Cong., 1st.
  Law 14,                                                                   sess.
  79th Cong.,
  1st sess.)
July 24, 1946   Replacement of Poe lock at St. Marys Falls Canal          H. Doc. 335, 80th Cong., 1st sess.
  (Public        with a new structure 800 feet long, 100 feet wide,
  Law 525,       and 32 feet deep, with necessary reconstruction of
  79th Cong.,    nose and center piers; and widening and deepening
  2d seas.)      the channel across Point Iroquois Shoals to a maxi-
                 mum width of 1,500 to 5,300 feet, with a depth of
                 27 feet, and in Lake Nicolet to a maximum width
                 of 1,000 feet, with a depth of 26.5 feet, when the
                 governing lakes are at datum, to provide wider
                 anchorage and maneuver areas in St. Marys River.

  1 Completed under previous projects.
  2 Contains latest published maps.
  3 Permanent Appropriations Repeal Act.
  4 Dimensions of lock authorized were specified in the act as "about 800 feet long, 80 feet wide, and 30 feet
deep."

   Local cooperation. Fully complied with for all features of the
project except for the removal of Bridge Island. For that fea-
ture, the owners of the International Bridge are required to pro-
vide a lift span over the South Canal upon request made by the
Secretary of the Army and in accordance with plans, specifica-
tions, and conditions approved by the Chief of Engineers, and the
United States is to participate in the cost of the bridge change by
payment to the owners of a percentage of the actual cost of the al-
teration, such percentage to be adjusted by the Chief of Engineers
1156      REPORT OF CHIEF OF: ENGINEERS, U. S. ARMY, 1954

between 77.5 percent if a span for Cooper's E-50 loading is con-
structed and 84 percent if a span for E-35 loading is constructed.
On the basis of 1954 price levels the amount of the United States
participation is estimated to be $2,201,000.
    Terminal facilities. This improvement serves the through com-
merce between Lake Superior and the lower lakes, and it has not
materially influenced the terminal facilities at the towns along its
route which consist mainly of small docks for the accommodation
of local traffic. Several coaling docks for through-traffic accom-
modations have been established at Sault Ste. Marie, Lime Island,
and Detour. A dock has been established at Drummond Island
for stone shipments.
    Operations and results during fiscal year. Regular funds:
New work: Powerhouse: A 2,500 KVA electric power transformer
was procured under contract and installed by hired labor in con-
nection with Unit No. 10 of the old hydro plant, which is now
operated by remote control from the new hydro plant. A new
2,500 KVA electric generator known as Unit No. 3A was received
and installed in the new hydro plant. This unit was placed in
commercial operation on March 5, 1954. Contract work on this
item is practically complete. Cost during the fiscal year was
 $133,926.
    Navigation features: Special studies were continued, in con-
nection with the operation of the locks and construction in con-
nection therewith to insure the continuity of operation. Cost dur-
ing the fiscal year was $21,380.
    Total costs for new work during the fiscal year were $155,306.
    Maintenance: Operation and care: Locks: The canal and four
locks were operated as required, and necessary repairs and im-
provements were made thereto and to the appurtenant structures
and equipment. The canal was opened to navigation 249 days,
from July 1, 1953, to December 15, 1953, and from April 11, 1954,
to June 30, 1954. During that period a total of 17,052 vessels ag-
gregating 106,150,429 tons of freight and 4,253 passengers,
passed through the MacArthur, Poe, Davis, and Sabin Locks in
13,132 lockages. Cost during the fiscal year was $931,455.
    Powerhouse and equipment: The new powerhouse and Unit No.
10 were operated and maintained. Cost during the fiscal year
was $73,567.
    Other operation and care items: Buildings and grounds were
maintained; security measures were carried out; condition and
operation studies, inspections, reports and statistics were made or
compiled as required. Cost during the fiscal year was $456,792.
    Total costs for operation and care during the fiscal year were
$1,461,814.
    General maintenance: Locks: Installation of a duct line and
cable on the northeast pier, by hired labor, is in progress; en-
largement and alteration of ice recesses at the east end of Mac-
Arthur Lock were completed by hired labor; a new steam line
was purchased and the contractor has begun installation from the
Emergency Dam to MacArthur Lock; the installation of new
boilers in the Emergency Dam boiler house was accomplished by
hired labor; the purchase and installation of a new friction plates
                  RIVERS AND HARBORS-DETROIT, MICH., DISTRICT                                                 1157
for 9 wire rope fenders were completed.by hired labor; and other
miscellaneous rehabilitation items were performed by hired labor.
Cost during the fiscal year was $154,938.
   Channels and canals: Repairs were made by hired labor to the
guide walls of the West Neebish Rock Cut; U. S. derrickboats, in-
cluding the Tompkins, removed a total of 32,427 cubic yards scow
measure of material from shoals in St. Marys River and Canal ap-
proaches; a contract was let for construction of a new mooring
dock, Middle Neebish Channel, the steel sheet piling being fur-
nished by the Government; and dredging in the vicinity of light
52 was completed under a continuing contract. Cost during the
fiscal year was $162,085.
    Cost of general maintenance during the fiscal year was $317,-
023.
   Total costs this fiscal year for maintenance were $1,778,837.
   Total costs for all work this fiscal year were $1,934,143, all of
which were regular funds.
    Condition at end of fiscal year. The existing project is complete
with the exception of the installation of steel guard gates at Mac-
Arthur Lock, removal of Bridge Island from South Canal, the re-
placement of the railroad bridge across South Canal with a new
lift bridge, the replacement of Poe Lock, widening the channel
across Point Iroquois Shoals, and widening channel along west
side of Lake Nicolet. No work has been performed on any of the
uncompleted items referred to above.
                                                   Project       Controlling   Project     Length of         Ye
        Name of channel or locality                depth           depth       width        channel
                                                    (feet)         (feet)       (feet)       (feet)      completed


Round Island Middle Ground          __      .              27          26.8 --------------.....              1932
Round Island Shoal No. 1___ .... ____________          27              26.8       1,000         5,000        1932
Round Island Shoal No. 2- ..-- - __                    27              26.8       1,000         9, 800       1932
Brush Point to Point Louise__-......- __               26              26.0 1,000-1,200         9,000        1937
Vidal Shoals (rock)_...----------------.               26              25.8 1,000-1,500         9,100        1933
South Canal---- ----------------------        --   -   -        --     - -----    - -           8,235    -
   West approach to MacArthur lock                     27              27.0        1 108 --- _-_-_-          1949
    West approach to Poe lock ...             .        24              23.8         1108 --- .....           1911
    MacArthur lock_--                                          30   31.0            80      --         _     (2)
    Poe lock -_3.------------ ---                  -         3 18   16. 6        4100 .----.--.             1896
    East approach of MacArthur lock _                          27   27.0           362 ......--
                                                                                              ______..      1949
    East approach to Poe lock _____ ____                       19.5 18. 1          370    ________           915
North Canal --- .. . .. . .. . . . . 24                             23 . ..          - .-       8,520    --
    West approach -----------                                  24   23.5           280 -                    1914
    Davis lock_______________-_____                    _     324.5  23.1            80 ------------         1914
    Sabin lock ________________ _______                      3 24.5 23.1            80 -------...           1919
    East approach ____-----------                              24.5 23.1           312 ....------------     1919
Course 1, Bayfield Channel, anchorage
  and maneuver area__---     __-             --                26   26.0 1,300-1,890            9,237       1949
Courses 2 and 3, Little Rapids....------------                 25   25.0          600          24, 193      1934
Lake Nicolet__-........                   .____._____-..
                                                     ___      26    24.8        1,500          22,000       1933
Middle Neebish (upbound route):
    Course 5, Lower end of Lake Nicolet__                     21    21.0          500          17,900       1929
    Course 6, dike (rock)__.._----...........   --            21    21.0          500          16,918       1930
    Course 7, Munuscong .Channel- ...--                       21    21.0          500          17, 586      1930
    Course 9, Sailors Encampment Chan-
      nel (rock)_...-.__-----------------                     21    21.0          500          12, 400      1930
West Neebish (downbound route):
    Course 4, Lower end of Lake Nicolet__                     25    25.0          300          10,762       1932
    Course 5, Lower end of Lake Nicolet..                     25    25.0          300          23, 370      1932
    Course 6 (rock cut)_-----____-__--                        27    26.2          300          14 064       1933
    Course 7___--__----_ ----------------                     25    25.0          300          13,270       1932
    Course 8, Moon Island._--------------                     25    25.0          300          12,600       1932
Lake Munuscong, Twin Island to Lime
Island-----------
         ......................-----------...--------...      26    25.0        1,000          26,459       1934
Crab Island Shoal...................------------------------  26    27.0 -----------            1,300       1933

  STwo channels past bridge island each 108 feet wide; minimum width of connecting channel, 304 feet.
  2 Opened to traffic July, 1943. Lock 97 percent complete.
  3 Depths referred to datum plane in effect at time of construction.
  4 Width reduced to 95 feet by construction of a curtain wall along south side of lock in 1943. *
  * Depth 26.0 feet, except that area northward of line from end of East Center Pier to intersection of north
channel line and international boundary line is 24.7 feet.
1158           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

    The costs of the existing project have been as follows:
      Regular funds:
          New work       --------------------------------------                  $61,991,312
          Maintenance---         -----------------             ----------------- 20,620,064

             Total-----------------------------------------                                                             82,611,376
      Public works funds:
          New work                        - ---                         _                                                     1I58,401

              Total all funds-------                    -------------------------                                       82,769,777
  In addition, the sum of $7,028,127 was expended between 1881
and June 30, 1936, on operation and care of the works of improve-
ment under the provisions of the permanent indefinite appropria-
tion for such purposes.
                                      Cost and financialsummary

                                                    Fiscal year ending June 30                                          Total to June
                                                                                                                       30, 1954, includ-
                                                                                                                       ing fiscal years
                               1950               1951           1952             1953                1954              prior to 1950


New work:
   Appropriated_. ....
   Cost_---
                          $2, 520,000
                        .___
                           3,441,127
                                            $      159, 726
                                                3,183,518
                                                              $ 987,240
                                                              1,276, 823
                                                                             $ 117,110
                                                                                  277, 201
                                                                                                $      12, 000
                                                                                                      155,306
                                                                                                                            1$65,069,976
                                                                                                                             165, 054,520
Maintenance:
   Appropriated ........ 1,379,500              1,427,000 1,633,000             1,887, 850 1,684,500                          27, 796,179
   Cost-.--------------    1,398, 593           1,460,030 1,643,112             1,777,806 1,699,145                           27, 648,191
                          I             I

  1 Includes $2,904,807 for new work for previous projects.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project --------------------- $37,834,800
                               2. ST. CLAIR RIVER,                              MICH.
  Location. This river is about 40 miles long and flows in a south-
erly direction from Lake Huron into Lake St. Clair. (See U. S.
Lake Survey Chart No. 43.)
  Existing project. This provides for channels as follows:
                                                                                                                              Project
                                                            Dis-                                                              datum
                                                  Length tance Used by up-               Project             Project          planes
                                                     of    from    or down-               wjt                Projet             above
       Name of improved channel                  eha.     m.        h...a                 width              depth            a
                                                   (feet) of river  vessels
                                                                                             (feet)           (feet)            at
                                                          (miles)                                                           New York
                                                                                                                              (feet)
                                                                    !                                     !---------



Foot of Lake Huron__ ____________                 25,000      42.0   Both......         800                            26   578.5-578.3
Port Huron Middle Ground.............              8,000      37.5   Down-.... 1,000-1,400                             25   577.7-577.3
Shoals, Port Huron to Marysville ...-- -          15,000      34,.0  Both.....       1, 000                            25   577.3-576.9
Shoals, Marysville to Stag Island-..--...          8,000      32.0   __do.. . .      1,000                             25   576.8-576.6
Stag Island-East Channel-        --               15,000      31.0   Up__- -..          800                            20   576.6-576.3
Shoals, Stag Island to St. Clair_. ----           28,000      27.0   Both......      1,000                             25   576.5-575.9
St. Clair Middle Ground.......____                 4,500      25.0   __do .... ,_       900                            25         575.8
Marine City Shoal,...........___                   5,800      1.9.0 ___do -___       1,000                             25   575.2-575.1
Shoals, Michigan Salt Works to Roberts            18,000      15.0 --_do --          1,000                             25   575.0-574.8
  Landing.
Head of Russell Island Shoal __.........           5,500      12.5 -__do -.....     1,000                              25   574.6-574.5
Grand Pointe and Squirrel Island Shoals-          15,000       7.0 __do ...     1,000-700                              25   574.4-574.2
Southeast Bend from Light 36 to St. Clair         28,000       2.7 - do .-.--          800                             26   574.0-573.6
  Flats Canal.
North Channel Outlet_......_........_              8,000                Small                       100                10          573.5
                                                                         craft.

   The project also provides for compensating works, consisting
of a number (estimated at 31) of submerged rock sills, with crests
31 feet below datum.
                 RIVERS AND HARBORS-DETROIT, MICH., DISTRICT                                         1159
   The project depths are referred to local low water datums
which correspond to low water datums for Lakes Huron and St.
Clair, which are 578.5 and 573.5 feet above mean tide at New
York. The water level of this river fluctuates with the levels of
the lakes above and below it, which during the course of each year
are subject to a consistent seasonal rise and fall, the lowest stages
prevailing during the winter months and the highest during the
summer months.
   At the head of St. Clair River, as measured by monthly mean
levels, the water may rise and fall each year during the naviga-
tion season as much as 1.3 feet. Since 1900 the difference between
the highest and lowest monthly mean level during the navigation
season has been about 4.5 feet. Occasional fluctuations due to
winds of high velocity may be as much as 3.5 feet in 6 hours.
   The River and Harbor Act, approved July 24, 1946, approved the
modification of the project to provide for widening and deepening
the Southeast Bend and improvement of the outlet of the North
Channel, St. Clair River, in general accordance with the following
descriptions: (a) That the two-way channel at Southeast Bend,
St. Clair River, from light 12 to St. Clair Flats Canal, be widened
to a width of 700 to 800 feet, with a depth of 26 feet for 24-foot
navigation; (b) that the North Channel outlet at the mouth of the
St. Clair River be widened to provide a channel 100 feet wide and
10 feet deep from lower St. Clair River to Lake St. Clair, for small
craft, apart from the regular steamboat channels.
   The estimate of cost for new work, revised in 1954, is $14,719,-
000, including $10,600,000 for construction of submerged sills.
   The latest (1954) approved estimate for annual cost of mainte-
nance of dredged channels is $64,900, including $1,500 for mainte-
nance in the outlet to North Channel. No expense or maintenance
will probably be required for submerged sills.
   The existing project was authorized by the following River and
Harbor Acts:

    Acts                             Work authorized                                  Documents

July 13, 1892   20-foot channel in the river-------------------.... ....   H. Doc. 207, 51st Cong., 2d sess.
July 3, 1930    Deepening of channel to 25 and 26 feet, and com-           H. Doc. 253, 70th Cong., 1st sess.
                 pensating works.                                            (Contains latest published map.)
Mar. 2, 1945    Widening channel at Southeast Bend to 700 feet-___-        H. Doc. 309, 77th Cong., 1st sess.
July 24, 1946   Widening and deepening the Southeast Bend and              H. Doc. 335, 80th Cong., 1st sess.
                 improvement of the outlet of the North Channel,
                  St. Clair River.




   Local cooperation. None required.
   Terminal facilities. This improvement serves the through com-
merce between the upper and lower lakes, and it has not materi-
ally influenced the terminal facilities at the towns along its route
which consist only of small docks for the accommodation of local
traffic. At Port Huron, Mich., there are 6 privately owned docks
for receiving coal, stone, petroleum products and wood pulp, and
1 public terminal for general cargo. At Marysville, Mich., there
are 2 privately owned docks for receiving coal and shipping salt.
At St. Clair, Mich., there is 1 privately owned dock for receiving
1160             REPORT                  :OF
                                 OF :CHIEF                ENGINEERS, U.           S. ARMY, 1954


coal, and at Marine City, Mich., there is 1 privately owned: dock
for receiving coal and stone.
  Operations and results during fiscal year. Surveys were made
over the channel at the foot of Lake Huron, Southeast Bend. Chan-
nel and miscellaneous areas, and repairs and replacements to the
control system were accomplished at a total cost of $30,776. The
cost of miscellaneous inspections and reports, and supervision and
administration, was $11,159. The total costs during the fiscal
year were $41,935, all for maintenance.
   Condition at end of fiscal year. The existing project, exclusive
of the compensating works, widening and deepening Southeast
Bend, and improvement of the outlet of the North Channel, was
completed in 1937. The following table gives the project depths,
and controlling depths, widths, and lengths of the several channels
covered by the project at the end of the fiscal year:

                                                                  Project     Controlling Minimum                     Length of
                      Name of channel                             depth         depth      width                       channel
                                                                   (feet)       (feet)      (feet)                      (feet)


Foot of Lake Huron ---------------------------
                        .--         ...                                  26              25.5                 800         25, 000
Port Huron Middle Ground ..--           --------------                   25              25.0               1,000          8, 000
Shoals, Port Huron to Marysville ...............---       --             25              25.0               1,000         15,000
Shoals, Marysville to Stag Island         -----------------              25              25.0               1,000          8,000
Stag Island East Channel ...--------------------                         20              21.0                  450        15,000
Shoals, Stag Island to St. Clair --- - -         --------                25              25. 0              1, 000        28, 000
St. Clair Middle Ground------------------------------                    25              25.0                  900         4,500
Marine City Shoal ------------------------                               25              25.0               1, 000         5, 800
Shoals, Michigan Salt Works to Roberts Landing_ -...                     25              25.0               1,000         18,000
Head of Russell Island Shoal --------             ----                   25              25.0               1,000          5,500
Grand Pointe and Squirrel Island Shoals_                                 25              25.0                  700        15,000
Southeast Bend from Harsens Island Rear Range Light
  to light13---------------                      -
                             ----------------------    -                 25             25.0                   700        18,000
Shoals from light 13 to St. Clair Flats Canal-......                     26             25.0               700-800        10,000
North"Channel outlet-- ------------------------------                    10 ....--------           -           100         8,000



    The costs have been as follows:
       Regular funds:
           New work--------------------------------------------                                                  $1,448,269
           Maintenance------------------------ ---------------                                                    1,485,254

             Total_------------------------------                    2,933,523
      Public works funds, new work--------- ------------------------ 1,671,660
      Emergency Relief Act funds -----------------------------------    49,419

                 Total, all funds_--------------------------------                                     -             4,654,602

                                           Cost and financial summary

                                                     Fiscal year ending June 30                                 Total to June
                                                                                                                30, 1954, includ-
                                                                                                                ing fiscal years
                                    1950           1951         1952          1953                1954           priorto 1950


New work:
   Appropriated                  ------- ------------                           --
                                                                         ---------                                    $3, 169,348
   Cost ...----------------------.                  $     9        ,0    -$943                             -           3,169,348
Maintenance:
   Appropriated .                      $81,500      $91,295    $19,800        $49,443             $44, 000             1,487,319
   Cost ___-----------        --        79,113        90,148    23,485         49, 443             41,935              1,485, 255


Other new work data: Estimated additional amount needed to be appro-
   priated for completion of existing project__---------                                   _---        -        $11, 549,700
           RIVERS AND HARBORS-DETROIT, MICH., DISTRICT           1161
                     3. DETROIT RIVER, MICH.
     Location. This river is about 31 miles long and flows in a south-
  erly direction from Lake St. Clair into Lake Erie. (See U. S.
  Lake Survey Chart No. 41.)
     Previous projects. Authorized by River and Harbor Acts of
  June 23, 1874, July 5, 1884, August 5, 1886, August 11, 1888, July
  13, 1892, and March 3, 1899. For further details, see page 1958
of Annual Report for 1915, and page 1541 of Annual Report for
  1938.
    Existing projects. This provides for a two-way channel 25 feet
deep and 800 feet wide through shoals at head of river, 26 feet
  deep and 800 feet wide through Fighting Island Channel, and 26
feet deep and 600 feet wide through Ballards Reef north of junc-
tion with Livingstone Channel; for a downbound channel, known
as Livingstone Channel, west of Bois Blanc Island, 26 feet deep
and at least 450 feet wide from its upper end to opposite Bar
Point; thence 26 feet deep and 800 feet wide to lower junction
with Amherstburg Channel, thence 26 feet deep and 1,200 feet
wide to the 26-foot contour in Lake Erie, passing to the east of
Detroit River Lighthouse, the lower section, 1,200 feet wide, being
used for both up- and down-bound traffic; for an upbound channel
known as the Amherstburg Channel, at least 600 feet wide with a
depth of 21 feet in the easterly 300-foot width and a depth of 27
feet in the westerly 300-foot width, from the lower junction with
Livingstone Channel, passing on the east side of Bois Blanc Island
to the head of Livingstone Channel; for an auxiliary downbound
channel, 22 feet deep and 800 feet wide, passing to the west of
Detroit River Light; for a dike on the west bank of the rock cut
through Livingstone Channel to ameliorate cross currents; for a
compensating waste bank between Livingstone and Amherstburg
Channel at their north junction; for improving channels to Wyan-
dotte by removing shoal at head of Grosse Ile and by dredging
through the Middle Ground opposite the head of Fighting Island;
for improving Trenton Channel (west of Grosse Ile), 21 feet deep
and 250 feet wide, extending from deep water near the head of
the island to a point 2,300 feet below the lower Grosse Ile Bridge,
ending in a turning basin of the same depth and 29 acres in area;
and for improving the American Channel passing north of Belle
Isle; from deep water near Windmill Point to a point opposite
Fairview Slip, to a depth of 21 feet and a width of 200 feet.
 1162                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

    The following table shows the characteristic features of the
existing project:

                                                                Dis-                                        Project
                                                                                                            datum
                                                      Length tance Used by up-            Project Project   planes
                                                                                                             above
                                                         of     from   or down-             wodthPdeth
        Name of improved channel                      chanelwidth
                                                      channel mouth     bound                     depth     above
                                                                                                          mean   tide
                                                       (feet) of river  vessels            (feet)  (feet)   at New
                                                              (miles)                                     York (feet)

Channel north of Belle Isle-.........-----------.....        (1)         23 Both......            200       21          573.0
Shoals at head of Detroit River
Fighting Island Channel---.........-.
                                            ----..........37,000
                                                       - 24,800
                                                                         23  ---   do_......
                                                                         11 ... do.......
                                                                                                  800
                                                                                                  800
                                                                                                            25
                                                                                                            26
                                                                                                                 573.3-572.8
                                                                                                                        571.7
Ballards Reef Channel (north of junction 13,000                            8    .. do.....        600       26          571.25
  with Livingstone Channel).
Livingstone Channel....---------------- 36,800                             1    Down.....    450-800        26 571.25-570.5
Bar Point Channel---------                   --..... 12,300...... Both...... 800-1,200                      26        570.5
Channel passing east of Detroit River 24,000 ........---- ...--                    do.......    1,200       26        570.5
  Light.
Ballards Reef Channel (south of junction                   5, 700         7 Up........            600       21 571.25-571.0
  with Livingstone Channel).
Amherstburg Channel.-           -------.                  36,000 ........---- ...----
                                                                                   do.......      600   221-27   571.0-570.5
Channel passing west of Detroit River 21, 000 ........ Down.....                                  800       22         570.5
  Light.
Wyandotte Channel--           --............          -..-2, 400         15 Local......           300       21          571.8
Grosse Ile Shoal. ......--                                - 600          13 ._do...................         20          571.8
Trenton Channel (west of Grosse Ile)-... 19, 400                          6 .. do.......          250       21   571.7-571.1

  1 Extends from deep water near Windmill Point to a point opposite Fairview Slip, approximately 3,000
feet.
  $ Project depth 21 feet in easterly 300-foot width of channel and 27 feet in westerly 300-foot width.


    The project depths are referred to local low water datum planes
which correspond to low water datum for Lakes St. Clair and
Erie and are taken at 573.5 and 570.5 feet, respectively, above
mean tide at New York.
  Each year during the navigation season the river rises and falls
about 2 feet as measured by the monthly mean levels. Since 1906
the difference between the highest and lowest monthly mean level
during the navigation season has been about 4.0 feet. Occasional
fluctuations in depths of several feet, produced by high easterly or
westerly winds, respectively, raise or lower the water level at the
west end of Lake Erie, and similarly affect the level of the lower
Detroit River; such changes have been as much as 6 feet within
8 hours.
  The estimate of cost for new work, revised in 1954, exclusive of
amounts expended on previous projects, is $47,361,000. The latest
(1954)            approved estimate for annual cost of maintenance is
$102,000.
  The existing project was authorized by the following River and
Harbor Acts:
     Acts                                   Work authorized                                        Documents

June 13, 1902
Mar. 3, 1905
June 25, 1910
                      IAmherstburg
                         Shoal.
                                        Channel and removal of Grosse Ile             H. Does. 712, 56th Cong., 1st sess.,
                                                                                        and 40, 58th Cong., 3d sess.
Mar. 4, 1913                                                          _
                       Fighting Island Channel_.........._..............__            H. Doec. 17, 62d Cong., 1st sess.
Mar. 2, 1907                                                                          H. Does. 266, 59th Cong., 2d sess.;
June 25, 1910         Livingstone Channel_............._.__        .. __      _ ...     676, 61st Cong., 2d sess.; and 322,
Mar. 2, 1919      i
                                                                                       .65th  Cong., 1st sess.
July 3, 1930    Channel depths of 26 and 25 feet_ _     ..        _                   H. Doe. 253, 70th Cong., 1st sess.t
Akug. 30,1935 2 Channel to Wyandotte 21 feet deep and 300 feet wide                   Rivers and Harbors Committee
                  through the Middle Ground opposite the head of                        Doec. 1, 72d Cong., 1st sess.'
                  Fighting Island.
  See footnotes at end of table.
                RIVERS AND HARBORS-DETROIT, MICH., DISTRICT                                         1163

     Acts                        Work authorized                                  Documents
Aug. 26, 1937   Trenton Channel and turning basin (west of Grosse      H. Doc. 205, 75th Cong., 1st sess.t
                 Ile.).
Mar. 2, 1945    American Channel north of Belle Isle between           H. Doc. 734, 79th Cong., 2d sess.
                 Windmill Point and Fairview Slip, Detroit.
July 24, 1946   Deepening the westerly 300 feet of Amherstburg         H. Doc. 335, 80th Cong., 1st sess.
                 Channel and Ballards Reef Channel below Living-
                 stone Channel to 27 feet to provide depths ade-
                 quate for 24-foot draft navigation, when the gov-
                 erning lakes are at datum, with necessary widening
                 at approaches and bends and construction of neces-
                 sary compensating works, Detroit River.
May 17, 1950    Extending turning basin in Trenton Channel 600         Sen. Doc. 30, 81st Cong., 1st sess.
                 feet, dredging through east draw of lower Grosse
                 Ile Bridge, and extending 300-foot width of channel
                 north of lower Grosse Ile Bridge.

  1Contain latest published maps.
  2Included in the Public Works Administration program, Sept. 6, 1933.

    Local cooperation. Fully complied with for completed portions
of project. For Trenton Channel modification approved May 17,
  1950, responsible local agencies are required to give assurances
satisfactory to the Secretary of the Army that they will furnish
without cost to the United States all lands, easements, rights-of-
way, and spoil disposal areas necessary for the construction and
subsequent maintenance of the project, when and as required; and
hold and save the United States free from damages due to the
construction and subsequent maintenance of the works.
    Terminal facilities. Within the limits of the port of Detroit are
more than 8.4 linear miles of docks fronting on the river, and the
appliances for handling freight are adequate. A number of docks
are owned by railroads and large manufacturing corporations over
which no freight is received except for their own use. Other docks
are owned by steamship lines, where peference is given to their
own vessels. There are, however, still other docks that are open to
the use of all vessels upon equal terms including one with terminal
warehouse. Present terminals are considered adequate for exist-
ing commerce.
    Operations and results during the fiscal year. Sounding sur-
veys prior to dredging were made over the lower Livingstone
Channel and Channel Passing East of Detroit River Light, includ-
ing the extension thereto into Lake Erie, for the 1953 and 1954
dredging seasons, and repairs and replacements were made to the
control system, at a total cost of $53,472. The cost of miscellane-
ous inspections and reports, including supervision and administra-
tion of the project, was $11,982.
    The location and removal of obstructions above 21 foot depth
in the Amherstburg Channel and above 26 foot depth in the Liv-
ingstone Channel, a total channel length of about 8 miles, were
accomplished by sweeping survey and the United States derrick-
boat Erie at a cost of $79,650. Repairs were made to about 1,000
linear feet of the Sugar Island Compensating Dike by the derrick-
boat Erie at a cost of $8,795.
    The United States hopper dredges Hoffman and Hains oper-
ated in the Channel Passing East of Detroit River Light and ex-
tension thereto during the periods August 10 to September 18,
1953, and August 10 to October 6, 1953, and removed 327,165 and
1164           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

543,734 cubic yards, bin measure, of shoal material respectively,
at a cost of $169,672. The United States hopper dredge Hains
operated in Lower Livingstone Channel and Channel Passing East
of Detroit River Light including extension thereto during the
period June 10 to June 30, 1954, and removed 119,035 cubic yards,
bin measure, of material at a cost of $36,892. The total quantity
of material removed by hopper dredging operations during the
fiscal year was 989,934 cubic yards, bin measure, and the total
cost of dredging was $206,564.
   The total costs during the fiscal year were $360,464 for main-
tenance.
   Condition at end of fiscal year. The existing project, with the
exception of the channel north of Belle Isle, deepening the westerly
300 feet of the Amherstburg Channel and the Ballards Reef Chan-
nel (south of its junction with the Livingstone Channel), and ex-
tending the turning basin in Trenton Channel, was completed in
1941. The work done consists of dredging, rock excavation, and the
costruction of dikes and compensating works. The dikes are gen-
erally in good condition. The Sugar Island compensating dike
still shows signs of erosion and weathering. The following table
gives project depths, controlling depths, widths, lengths, and date
of completion of the several channels covered by the project at the
close of the fiscal year:
                                                 Length            Minimum       Project        Controlling   Date of
            Name of channel                      channel            width        depth            depth       Date of
                                                  (feet)            (feet)        (feet)          (feet)    Completion


Channel north of Belle Isle                           (1)                200              21-
Shoals at head of Detroit River ..-....               37,000             800              25         25.0         1935
Fighting Island Channel._-.                           24,800             800              26         26.0         1933
Ballards Reef Channel (north of junc-
  tion w ith Livingstone Channel) ......              13,000             600              26         26.0     Aug. 18, 1936
Livingstone Channel. .....                            36,000             450              26         26.0     Sept. 2, 1936
Bar Point Channel _        ---                        12,300             800              26         26.0     June 26, 1936
Channel passing east of Detroit River
  Light---------------------------------              24,000           1,200              26         26.0     Aug. 14, 1937
Ballards Reef Channel (south of junc-
  tion with Livingstone Channel) ......                5,700             600          2 21-27       3 21.0      3 1914
Amherstburg Channel_-                                 36,800             600          2 21-27       321.0       31912
Channel passing west of Detroit River
P',Light        -
               -.                                     21,000             800              22         20.1        1929
Wyandotte Channel_                                     2,400             300              21         21.0        1933
G rosse Ile Shoal ------------------------                600                             20         19.5        1904
Trenton Channel_                                      19, 400            250              21         21.0       41941
  I Extends from deep water near Windmill Point to a point opposite Fairview Slip, approximately 3,000
feet.
  2 Project depth 21 feet in easterly 300 feet width of channel and 27 feet westerly 300 feet width.
  3 No work has been done in westerly half.
  4 No work has been done to extend the turning basin.




    The costs of the existing project have been as follows:
      Regular funds:
          New work     ----------                           -----------          --        -                 $--
                                                                                                              20,045,988
          Maintenance --------------                           -        -                                     2,075,039

             Total-------------------                                                                        22,121,027
      Public worksfunds---                   ----------------------
                                                 --                                                           1,530,688
               Total, all funds_---          -               -----------------
                                                                                                             23,651,715
               RIVERS AND HARBORS-DETROIT, MICH., DISTRICT                                     1165
                                   Cost and financial summary

                                         Fiscal year ending June 30                    Total to June
                                                                                       30, 1954, includ-
                                                                                       ing fiscal years
                            1950        1951         1952        1953        1954        priorto 1950


New work:
   Appropriated--..---------------- --$10, 000       -$8, 063------..    ------------     1 $23,673,930
   Cost---------
Maintenance:
                                 ------------
                        ------------             ------------    ---------- ------------ 123,673,930
   Appropriated------ _        300
                           $136,        143,
                                           275       158,000 $151,
                                                                 154            000
                                                                            $358,             2,076,583
   Cost                    157,633   122 751
                .......----------------.             159,178     167,018     360,464          2,075,039


IIncludes $2,097,254
                  fornew work forprevious projects.
Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project---------------------    $25,784,300

4. AU SABLE HARBOR AND HARBOR OF REFUGE AT AU SABLE
                 RIVER (OSCODA), MICH.
   Location. The Au Sable River, with the village of Oscoda,
Mich., situated near its mouth, is located on the westerly shore of
Lake Huron, about 8 miles north of Au Sable Point at the entrance
to Saginaw Bay. (See U. S. Lake Survey Chart No. 5.)
   Previous project. The previous project was authorized in 1866
and modified in 1879. For further details, see pages 336 and 2453
of the Annual Report for 1892.
   Existing project. This provides for riprapping at the outer 200
feet of the existing north pier at the mouth of the Au Sable River,
dredging an entrance channel 12 feet in depth and dredging the
channel between the piers and upstream to the State Highway
bridge to a depth of 10 feet.
   The project depths are referred to low water datum in Lake
Huron, which is 578.5 feet above mean tide at New York.
   The estimated cost for new work, revised in 1954, is $147,000,
excluding $16,400 to be contributed by local interests. The latest
 (1954) approved estimate of annual cost of maintenance is $2,000.
   The existing project was authorized by the River and Harbor
Act approved March 2, 1945. For latest published map, see House
Document 446, 78th Congress, 2d session.
   Local cooperation. The improvement authorized by the act of
March 2, 1945, is subject to the condition that responsible local
agencies give assurances satisfactory to the Secretary of the Army
that they will-
     (1) Contribute $16,400 in cash toward the first cost of pro-
          tective structures and dredging.
     (2) Provide and maintain, without cost to the United States,
          and in accordance with plans approved by the Chief of
          Engineers, a suitable and adequate public wharf for the
          accommodation of transient vessels.
     (3) Establish a competent and properly constituted public
          body, empowered to regulate the use, growth, and free
          development of harbor facilities, with the understanding
          that harbor facilities shall be open to all on equal and
          reasonable terms.
1166     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

      (4) Hold and save the United States free from damages due
           to construction and maintenance of the works.
      (5) Provide, without cost to the United States, all lands,
           easements, and rights-of-way necessary for the construc-
           tion of the project, including suitable spoil disposal areas
           when and as required.
   It is further provided that no work shall be done by the United
States at this harbor until the prescribed requirements for local
cooperation have also been complied with at the following addi-
tional projects in this area: Hammond Bay, Mich., and Harris-
ville, Mich.
   These assurances were furnished by the Michigan State Water-
ways Commission and were approved by the Assistant Secretary
of the Army on March 22, 1948.
   Terminal facilities. Seven small timber pile docks are used pri-
marily as fishing terminals by their owners. Ample space for
mooring small craft is available along the face of old cribbing,
and present terminials are considered adequate for all existing
or reasonably prospective commerce.
   Operations and results during the fiscal year. An adjustment
was made in the cost of the dredging by United State bucket
dredge Tompkins during May and June 1953, including after
dredging survey cost, in the amount of $10,000. Sounding survey
prior to dredging was made during April 1954, and the United
States bucket dredge Tompkins operated in the entrance channel
of Au Sable Harbor during the period May 13 to May 27, 1954,
removing 18,498 cubic yards, bucket measure, at a total cost of
$25,000. Total costs for the fiscal year were $35,000, all for main-
tenance.
   Condition at end of fiscal year. The existing project has not
been constructed but the entrance channel is being maintained
under the previous project to allow passage of the U. S. Air Force
crashboats based in the river. The existing jetties have deteri-
orated to the point where they afford little or no protection from
wave action during storms and are ineffective in intercepting lit-
toral drift from entering the channel. The controlling depth at
the present time is about 7.5 feet below low water datum, from
the State Highway Bridge through the entrance channel. The con-
trolling depth could be reduced to about 3.0 feet in a very short
period of time as a result of severe storm from either north-
easterly or southeasterly direction.
   The costs of the existing project have been as follows:
   Regular funds:
      New work (existing project)-                              $      100
       Maintenance (previous project)   - -       -                 76,367

         Total                                                      76,467
                      RIVERS AND HARBORS-DETROIT, MICH., DISTRICT                                           1167
                                               Cost and financial summary

                                                     Fiscal year ending June 30                     Total to June
                                                                                                    30, 1954, includ-
                                                                                                    ing fiscal years
                                        1950        1951           1952       1953       1954        prior to 1950


New work:
     Appropriated_
                 --------                $8,000    -$7, 900-----------------------------------            1$114,886
   Cost -----------------------------                      100   _1114,886-
Maintenance:
     Appropriated ....   ---------                   18,367           $700    $22, 300   $35, 000             76,367
     Cost--------------------------                  18,367            700     22,300     35,000              76,367

  1 Includes $114,786 for new work for previous projects.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project  _    _ _-------------------------- $146,90(

                                         5. SAGINAW RIVER, MICH.
   Location. This river is formed by the union of the Tittabawas-
see and Shiawassee Rivers, is about 22 miles long, and flows in a
northerly direction and into the south end of Saginaw Bay, Lake
Huron. (See U. S. Lake Survey Chart No. 5.)
   Previous projects. Authorized by River and Harbor Acts of
June 23, 1866, June 23, 1874, June 18, 1878, March 3, 1879, August
2, 1882, and August 5, 1886. For further details, see page 1957
of Annual Report for 1915, and page 1550 of Annual Report for
1938.
   Existing project. This provides for a channel 21 feet deep and
200 feet wide from deep water in Saginaw Bay to the Detroit &
Mackinac Railway bridge in Bay City, thence 20 feet deep to the
Sixth Street Bridge in Saginaw, Mich., thence 161/2 feet deep to
the junction with the Tittabawassee River, a distance of about
29 1/ miles; and for a turning basin 15 feet deep by 360 feet wide,
varying from 690 feet to 420 feet in length, adjacent to the east
side of the existing channel between Court Street and Bristol
Street Bridges. The project depth is referred to low water datum
for Lake Huron, which is taken at 578.5 feet above mean tide
level at New York. Due to storms, the level of the river at its
mouth rises and falls about 3 feet. Spring freshets and excessive
rains have caused an abnormal rise of as much a 14 feet at Sagi-
naw. Occasionally a considerable change takes place within few
hours, resulting from the raising or lowering of Saginaw Bay by
violent winds. •
   The cost of new work for the completed project was $2,081,580,
exclusive of amounts expended on previous projects. The latest
 (1954) approved estimate for annual cost of maintenance is:
 1168             REPORT OF CHIEF OF.ENGINEERS, U. S. ARMY, 1954

 $97,500. The existing project was adopted by the following River
and Harbor Acts:
     Acts                              Work authorized                                Documents

June 25, 1910     Channel 200 feet wide, with depths of 181 feet in the   H. Doec. 740, 61st Cong., 2d sess.
                     bay and 163/ feet in the river.
July 3, 1930       Project depth of 18% feet extended up the river to      Rivers and Harbors Committee
                    Saginaw.                                                 Doc. 30, 71st Cong., 2d sess.
Aug. 26, 1937     Turning basin_.___________-__..----------------         Rivers and Harbors Committee
                                                                             Doc. 21, 75th Cong., 1st sess.
                                                                            (Contains     latest:   published
                                                                            maps.)
June 20, 1938      Present project channel dimensions from the bay to      IH. Doc. 576, 75th Cong., 3d sess.
                     the 6th St. Bridge in Saginaw.



   Local cooperation. Fully complied with.
   Terminal facilities. The terminals are centered at Bay City and
Saginaw, Mich. At Bay City, which includes Essexville, there are
36 piers, wharves, and docks. At Saginaw, which includes Mil-
waukee and Carrollton, there are 20 such facilities. Of the total
of 56 terminals, 17 are used for receiving bulk commodities, 8 are
used for handling petroleum products, 9 are moorings or landings
for small craft, and 22 are not in use. A terminal at Carrollton,
Mich., is a public bulk handling and storage plant. These ter-
minal facilities are considered adequate for existing commerce.
   Operations and,results during the fiscal year. Condition of the
channel sounding surveys, including prior to dredging 1953 season,
and repairs and replacements to the control system were made at
a cost of $18,716. The cost of miscellaneous inspections and re-
ports, including supervision and administration of the project was
$3,772. The United States hopper dredge Hains operated in the
Saginaw Bay Channel of the project during the period July 24 to
August 9, 1953, removing 59,368 cubic yards, bin measure, of
shoal material at a cost of $26,642.   Total costs during the fiscal
year were $49,130, all for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in April 1942. The present controlling depth in the bay
section channel is 20.0 feet over the center 120 feet width. Proj-
ect depths are generally available in the river section channel
from the mouth of the river to the 6th Street Bridge in Saginaw,
Mich. Considerable shoaling has occurred in the river section
channel and the turning basin between the 6th Street and Court
Street bridges in Saginaw, Mich. The controlling depth in this
section is 15.5 feet. The portion of the project upstream of the
Court Street Bridge is not maintained.
   The costs of the existing project have been as follows:
Regular funds:
            New work_- -----------------                                                      $2,081,579
            Maintenance_                                                                       1,826,414
                 Total_                                                                        3,907,993
              RIVERS AND HARBORS-DETROIT,; MICH., DISTRICT                                1169
                                   Cost and financial summary

                                         Fiscal year ending June 30                Total to June
                                                                                  30, 1954, includ-
                                                                                  ing fiscal years
                            1950        1951           1952     1953   1954        prior to 1950


New work:
   Appropriated - -        -                                     - __--               1$3,044,136
   Cost   -------------------------------------------                    _
                                                         -------------------           13,044,136
Maintenance:
   Appropriated          $262,239    $ 90,000   -$3, 700     $37,050    $59,000          1,838,677
   Cost .....-- ----      330,841     213,600     16,.54      34,657     49,130          1,826,414

                  fornew work for previous projects.
1Includes $962,556


                        6. PORT AUSTIN             HARBOR, MICH.

   Location. This harbor is located on the west shore of Lake
Iluron at the extreme eastern limit of Saginaw Bay, about 29
miles across the bay from the mouth of the Au Sable River
 (Oscoda). (See U. S. Lake Survey Chart No. 5.)
   Existing project. This provides for a harbor of refuge at the
mouth of Bird Creek, consisting of a harbor basin dredged to a
depth of 10 feet protected by breakwater. structure and for dredg-
ing an entrance channel to the harbor basin to a depth of 12 feet.
   The project depths are referred to low-water datum for Lake
Huron, which is 578.5 feet above mean tide at New York.
   The estimated cost for new work, revised in 1954, is $1,160,000,
excluding $172,100 to be contributed by local interests. The lat-
est (1945) approved estimate of annual cost of maintenance is'
$750.
   The existing project was authorized by River and Harbor Act
approved March 2, 1945. For latest published map see House
Document No. 446, 78th Congress, second session.
   Local cooperation. The improvement authorized by the act of
March 2, 1945, is subject to the condition that responsible local
agencies give assurances satisfactory to the Secretary of the
Army that they will-
   (1) Contribute $172,100 in cash toward the first cost of pro-
tective structures and dredging.
   (2) Provide and maintain, without cost to the United States,
and in accordance with plans approved by the Chief of Engineers,
a suitable and adequate public wharf for the accommodation of
transient vessels.
   (3) Establish a competent and properly constituted public body
empowered to regulate the use, growth, and free development of
harbor facilities, with the understanding that harbor facilities-
shall be open to all on equal and reasonable terms.
   (4) Hold and save the United States free from damages due to
construction and maintenance of the works.
   (5) Provide, without cost to the United States all lands, ease-
ments, and rights-of-way necessary for the construction of the
project,. including suitable spoil disposal areas when and as re-
quired.
  It is further provided that no work shall be done by the United
States at this harbor until similar prescribed requirements for
 1170             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

local cooperation at Port Sanilac, Mich., have also been complied
with.
   These assurances were furnished by the Michigan State Water-
ways Commission and were approved by the Assistant Secretary
of the Army on March 22, 1948. The Michigan State Waterways
Commission has contributed in the amount of $28,000 for advance
planning.
   Terminal facilities. There are no terminal facilities at Port
Austin.
   Operationsand results during fiscal year. The only new work
was for preliminary engineering and design. The total costs for
the fiscal year were $267.
   Condition at the end of the fiscal year. No construction work
has been done. The total cost to date, all for advance planning
for new work, has been as follows:
      United States funds----------    --------------------------------  3,500
      Contributed by State of Michigan    ----------------------------- 15,057
          Total-------------------                         ----------------------------                      18,557
                                            Cost and financialsummary
                                                UNITED STATES FUNDS

                                                    Fiscal year ending June 30                        Total to June
                                                                                                    *30, 1954, includ-
                                                                                                     ing fiscal years
                                     1950          1951        1952         1953         1954          prior to 1950


New work:
   Appropriated--------....-----------....        --------------------------------- ------------                $3,500
   Cost-----------------               $3,013         $753       $4,497 ------------------------.
                                                                                         .3,500

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project_ ----------------------
                                                             _       $1,156,500
                                                CONTRIBUTED FUNDS


                                                     Fiscal year ending June 30                       Total to June
                                                                                                    _ 30, 1954, includ-
                                                                                                     ing fiscal years
                                    1950           1951        1952         1953         1954          prior to 1950

New work:
   Appropriated --------------..------------------------------------------------                               $28,000
   Cost-----------------    $9,288 ------------- $4, 497                $267                                   $215,057

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-__---          _---- $12,943
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955      -------------------------------------------------               12,943
    Estimated additional amount needed to be appropriated for completion
      of existing project         -------------------------------------- 144,100

                             7. PORT SANILAC HARBOR, MICH.
  Location. This harbor is located on the southwest shore of
Lake Huron, about 30 miles borth of Port Huron, Mich. (See
U. S. Lake Survey Chart' No. 5.)
  Existing project. This provides for the formation of a harbor
of refuge protected by breakwater structures extending to the 12-
                    RIVERS AND HARBORS-DETROIT, MICH., DISTRICT                                                       1171
foot depth contour in the lake; for dredging a harbor basin, 10
feet in depth, and for dredging an entrance channel 12 feet in
depth.
   The project depths are referred to low water datum for Lake
Huron, which is 578.5 feet above mean tide at New York.
   The cost of new work for the completed project was $538,650,
excluding $130,100 contributed by local interests. The latest (1954)
approved estimate of annual cost of maintenance is $5,500.
   The existing project was authorized by the River and Harbor
Act approved March 2, 1945. For latest published map, see House
Document 446, 78th Congress, 2d session.
   Local cooperation. Fully complied with.
   Terminal facilities. One small privately owned, stone-filled,
timbered-crib dock is used principally as a fishing terminal by the
owner. A municipally owned timber pier, extending about 150
feet lakeward, with a 50-foot extension on one side and a 40-foot
extension on the other side, is open to all vessels on equal terms.
Terminal facilities are considered adequate for existing commerce.
   Operations and results during the fiscal year. During May,
1954, a sounding survey was made over the dredged anchorage
areas to determine the extent of the shoaling, at a cost of $1,200.
Total cost for the fiscal year was $1,200, all for maintenance.
   Condition at end of fiscal year. Construction of the project
began April 24, 1950, and was completed May 25, 1951. Project
depths are generally available over all of the dredged anchorage
area and entrance channel, except for a strip along the west edge
at the north end of the anchorage area, 200 feet wide and 350 feet
long, where the controlling depth is about 4.0 feet. The break-
waters are in good condition except that minor cracks and holes
have formed in the blacktop covers of the individual cells as a
result of frost and wave action.
   The total costs have been as follows:
     New work:
        United States funds$----------------------------------538,650
        Contributed by the State of Michigan --------------      130,100
         Total-------------------------------------------$668,750
     Maintenance---------------------------------------------  1,475
                 Total, all funds                   ------------------------------------                             70,225
                                               Cost and financial summary

                                                               Fiscal year ending June 30                     Total to June
                                                                                                              30, 1954, includ-
                                                                                                              ing fiscal years
                                       1950              1951           1952         1953          1954         priorto 1950

New work:
   Appropriated ------..              $435,000         $228, 250      -$25, 000------------                         1 $668, 750
       ----------------
   Cost__                              197,266          414,361           3,140    $362572        .------------      1 668, 750
Maintenance:
   Appropriated---  ..--------------------------------------                                275     $1, 200              1,475
   Cost ------------------------------------------------                                    275      1, 200              1,475

1 Includes $130,100 costs for new work from contributed funds.
 1172      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                       8. ROUGE RIVER, MICH.
     Location. The river rises in Oakland and Washtenaw Counties,
  Mich., is about 30 miles long, and flows in a southeasterly direction
  through Wayne County into the Detroit River. (See U. S. Lake
  Survey Chart No. 415.)
     Previous projects. Authorized by the River and Harbor Act of
  August 11, 1888 (Annual Report for 1887, pp. 2275-2278); joint
  resolution of April 11, 1898 (H. Doc. 138, 55th Cong., 2d sess.,
  and Annual Report for 1898, p. 2605), and the River and Harbor
Act of March 2, 1907 (H. Doc. 289, 59th Cong., 1st sess.). For
further details, see page 1530 of Annual Report for 1932, and page
  1558 of Annual Report for 1938.
    Existing project. This provides for the following:
    a. A channel 21 feet deep from that depth in Detroit River
through the Short Cut Canal, 400 feet wide at the entrance, taper-
ing to 200 feet in a distance of 2,000 feet, thence 200 feet to Maples
Road, including a turning basin, 21 feet deep, near the upper end
of the project.
    b. A channel 25 feet deep from that depth in Detroit River
through the mouth of the old channel upstream for a distance of
1,300 feet, with a width of 240 feet at the mouth, tapering to 100
feet at a distance of 800 feet from the mouth, thence 18 feet deep
and 100 feet wide for a distance of 1,425 feet, thence 17 feet deep
and 100 feet wide to the Detroit, Toledo & Ironton Railroad
bridge, a distance of about 1,550 feet, thence 21 feet deep and 100
feet wide, flaring to 130 feet at the north end of the Peerless Port-
land Cement Co. wharf, thence 21 feet deep, with width flaring
from 130 feet to 150 feet at the junction of the old channel with
the Short Cut Canal, suitably widened at the bend opposite the
Detroit Sulphite Pulp & Paper Co. plant.
    The distance from Detroit River to the head of the project: at
Maples Road is about 31/ miles via the Short Cut Canal, and
about 41/2 miles via the old channel.
    The project depths are referred to local low water datum in the
Detroit River at the mouth of the Rouge River, which is 572.2
feet above mean tide at New York. The level of this river, except
during floods, changes with the level of the Detroit River, which
fluctuates to an average extent of about 1.5 feet during the navi-
gatio Pseason.
    The estimate of cost for new work, revised in 1954, is $1,249,000,
exclusive of amounts expended on previous projects. The latest
 (1954) approved estimate for annual cost of maintenance is
$90,000.
                  RIVERS AND HARBORS-DETROIT, MICH., DISTRICT                                      1173
The existing project was authorized by the following River and
Harbor Acts:
     Acts                           Work authorized                                Documents

Aug.. 11, 1888   17-foot channel 1___....----------................     Annual Report, 1887, p. 2275.     2
Aug. 8, 1917     21-foot channel via Short Cut Canal.-------------H_    H. Doc. 2063, 64th Cong., 2d sess.
Aug. 30, 1935 2 25-foot channel at mouth of old channel, the 18-foot    Senate committee
                                                                                   2     print, 73d Cong.,
                  channel, 1,425 feet in length and adjacent to the       2d sess.
                  latter, and the 21-foot channel extending from the
                  junction of the old channel and Short Cut Canal
                  into the old channel to the Detroit, Toledo & Iron-
                  ton R.R. bridge.

  1Completed under previous projects.
  2Contains latest published maps. See also        map with Rivers and Harbors Committee Doc. 19, 72d
Cong., 1st sess.
3 Including Emergency Relief Administration work authorized May 28, 1935.


   Local cooperation. The act approved August 30, 1935, pro-
vided that no Federal expenditures should be made on the im-
provements in the old channel until local interests had provided,
without cost to the United States, all necessary rights-of-way and
had furnished guaranties, satisfactory to the Secretary of the
Army, protecting the United States against all damages to adja-
cent lands and property which may result from dredging opera-
tions. Except for the guaranties protecting the United States
against damages to adjacent lands and property along the 25-foot
channel, this requirement has not been complied with. All prior
requirements fully complied with.
   Terminal facilities. There is an iron ore dock near the river's
mouth equipped with unloading machinery. The Ford Motor Co.
has an ore and coal dock near the head of the river improvement,
with improved type of unloaders. Eight docks fully equipped for
handling oil and oil products, and one dock equipped for handling
gypsum rock, have been constructed along the riverbank. These
docks have good railroad connections. In addition, there are four
docks owned by sand and gravel companies which have unloading
machinery, one pulpwood dock, and one timber dock. There are
9 docks that receive coal, 7 docks that receive stone, 1 dock that
receives coal tar, and 1 dock that ships salt. There are also a
number of smaller docks for launches. All docks along the river
are privately owned and understood to be restricted to use of the
owners. These facilities are considered adequate for existing
commerce.
   Operations and results during the fiscal year. The costs of a
prior to dredging sounding survey made over the entire project
during October and November 1953 and studies in connection with
1174       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

the illegal deposit of industrial wastes were $8,325. The cost of
miscellaneous inspections and reports including supervision and
administration of the project was $4,676.
   The United States hopper dredge Hains operated over the en-
tire project during the period November 11 to December 17, 1953,
removing 187,640 cubic yards, bin measure, of shoal material at
a cost of $63,490. These costs do not include the financial par-
ticipation of industries in the removal of illegal deposits of in-
dustrial wastes, in the amounts, Ford Motor Company $9,962;
Peerless Cement Corporation $2,759; Solvay Process Division of
the Allied Chemicals Corporation $1,299. Total financial partici-
pation by industries was $14,020.
   Total costs during the fiscal year were $76,491, all for mainte-
nance.
   Condition at end of fiscal year. The 21-foot project, which con-
sisted of dredging a 21-foot channel from the Detroit River via
the Short Cut Canal to the upper limit of improvement, and the
construction of five dolphins at the mouth of the Short Cut Canal,
wa completed in 1923. The 25-foot project at the mouth of the
old channel was started with funds from the Emergency Relief
Administration, but due to shortage of funds, dredging was re-
stricted to a distance of 1,150 feet upstream of the mouth of the
old channel. All other work provided for in the act of August
30, 1935, relative to the improvement of the old channel, is held
in abeyance until local interests have complied with the terms of
local cooperation.
   The controlling depth of the 21-foot project, via the Short Cut
Canal, is 21 feet along the center half of the channel to the turn-
ing basin which has a controlling depth of 21 feet except along
the channel banks. The controlling depth of the old channel,
from its intersection with the Short Cut Canal to the 25-foot proj-
ect, is 17 feet. The 25-foot section has a controlling depth of
25 feet, except along the channel banks.
   All bridges have been altered to comply with the requirements
of law. The dolphins at the mouth of the Short Cut Canal are in
poor condition; and as they are no longer utilized by navigation
interests, further maintenance is not justified and the dolphins
should be removed. The head of navigation is determined by a
fixed bridge about 2,600 feet above the upper limit of improve-
ment.
   The costs of the existing project have been as follows:
   Regular funds:
            N ew work .-----------------.......-                                   .-.-.-.. $561, 646
            Maintenance.....               .. ...         -1,       ..--------------         464, 434

             Total....   .................---------------------------------              2,026, 080
   New work, Emergency Relief Act funds ...           ----------------            --------  29, 563
          Total, all funds...............-----------------------------------                 2,055, 643
                   RIVERS AND HARBORS-DETROIT, MICH., DISTRICT                                                    1175
                                             Cost and financial summary

                                                         Fiscal year ending June 30                       Total to June
                                                                                                          30, 1954, includ-
                                                                                                          ing fiscal years
                                      1950             1951             1952        1953       1954        prior to 1950


New work:
   Appropriated            -----------------------------------------------------------                         $ 641,292
               ---------------------------------------------------------------
   Cost..........----                                                                                              641,292
Maintenance:
   Appropriated----....               $79, 000         $76, 500         $93, 700    $78,807    $77, 300          1,521,851
   Cost-----------------               75,179           74,136           96,326      84, 514    76,491           1,521,041


1Includes $50,082 for new work and $56,608 for maintenance for previous projects.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project--------------------------     $657,790

                                       9. TOLEDO HARBOR,                           OHIO
   Location. This harbor comprises the lower 7 miles of Maumee
River and the channel about 16.5 miles through Maumee Bay to
Lake Erie. The Maumee River has its source in northern Indi-
ana and empties into Lake Erie. The harbor is located at the
westerly end of Lake Erie, 99 miles westerly from Cleveland, Ohio.
 (See U. S. Lake Survey Chart No. 3.)
   Previous projects. Adopted by River and Harbor Acts of June
23, 1866, June 14, 1880, July 5, 1884, August 5, 1886, July 13,
1892, and August 18, 1894. For further details, see page 1959 of
Annual Report for 1915, and page 1565 of Annual Report for
1938.
   Existing project. This provides for a channel 25 feet deep and
500 feet wide from deep water in Lake Erie to the mouth of the
Maumee River, with a width of 300 feet on each side of center
dike in the bay channel; for a channel 25 feet deep in Maumee
River to the Baltimore & Ohio Railroad dock, 400 feet wide from
the mouth of the river to the Fassett Street Bridge, and 200 feet
wide above that point; for a turning basin at the upper end, 18
feet deep and 8.25 acres in area; for a triangular widening at the
bend in the channel at the mouth of the river, on the north side
of the channel opposite the Chesapeake & Ohio Railway dock,
3,055 feet in length, 460 feet maximum width and 16.2 acres in
area; and for a stone-revetted earth dike, 1,000 feet long, to form
a foundation for range lights in Maumee Bay.
   The projects depths are referred to low water datum for Lake
Erie, which is 570.5 feet above mean tide at New York. Ordinary
fluctuations of water level are from 4 feet above to 2 feet below
low water datum, and extreme fluctuations, produced by wind and
other causes, are from 9 feet above to 7.6 feet below that plane.
   The estimate of cost for new work, revised in 1954, is $5,565,-
000, exclusive of amounts expended on previous projects. The
latest (1954) approved estimate for annual cost of maintenance
is $354,000.
1176            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

The existing project was adopted by the following River and
Harbor Acts:

    Acts                             Work authorized                                         Documents


Mar. 3, 1899    Auxiliary channel above Fassett Street Bridge, and                H. Doc. 198, 55th Cong., 2d sess,
                  the dike.                                                         and Annual Report, 1898, p. 2693.
June 25, 1910   Channel 21 feet deep..............--------------...------------   H. Doc. 865, 60th Cong., 1st sess.
Aug. 30, 1935   Present project dimensions of the main channel and                Rivers and Harbors Committee
                  turning basin, and eliminated from the project the                Doc. 21, 72d Cong., Ist sess.
                  auxiliary channel above Fassett Street Bridge.                    (Contains latest published map.)
May 17, 1950    Widening at bend at mouth of river opposite Chesa-                H. Doec. 189, 81st Cong., 1st sess.
                 peake & Ohio Ry. dock.                                            (Contains latest published maps,)



   Recommended modification of project. On April 28, 1950, the
Chief of Engineers recommended modification of the existing proj-
ect for Toledo Harbor, Ohio, to provide for removal of the center
dike on which the Maumee Bay Range Lights are located, to the
project depth of 25 feet, generally in accordance with the plans of
the district engineer, and with such modifications thereof as in
the discretion of the Chief of Engineers may be advisable, at an
estimated cost to the United States of $420,000 for the removal
of the dike and a reduction of $3,000 in the cost of annual main-
tenance, subject to the provision that local interests hold and save
the United States free from damage due to the construction works.
   Local cooperation. Fully complied with for completed portions
of project. For widening at bend opposite C. & O. dock, approved
May 17, 1950, local interests are required to agree to hold and
save the United States free from damages resulting from the con-
struction works.
   Terminal facilities. There are 3 large railroad terminals :for
receipt of ore and 3 for handling coal, 1 fuel dock, 4 docks for
handling grain, 5 docks for handling petroleum products, 5 sand
and gravel docks, 1 cement dock, 3 private fish docks, and 2 pack-
age-freight terminals which are open to all vessels on all terms.
The city of Toledo has provided a lagoon, near the mouth of the
Maumee River, suitable for winter mooring of vessels. The ter-
minal facilities are regarded as adequate for existing commerce.
   Operationsand results during the fiscal year. Condition of the
channel and prior to dredging sounding surveys were made over
the entire project channel during July 1953, and May and June
1954, at a cost of $10,897. The cost of miscellaneous inspections
and reports including supervision and administration of the proj -
ect and custody of the harbor was $11,658.
   The United States hopper dredges Hoffman, Hains, and Taylor
                RIVERS AND HARBORS-DETROIT, MICH., DISTRICT                                                         1177
operated in the Maumee Bay Channel and the lower portion of the
River Section Channel during the periods September 19 to Decem-
ber 17, 1953, October 7 to November 10, 1953, and November 12
to December 17, 1953, respectively, removing 402,639, 194,176 and
141,854 cubic yards, bin measure, of shoal material, respectively.
The total quantity of material removed by hopper dredge opera-
tions was 738,669 cubic yards, bin measure, and the total lost of
dredging was $276,476. Total costs during the fiscal year were
$299,031, :all for maintenance.
   Condition at end of fiscal year. The existing project, exclusive
of Widening the channel opposite the Chesapeake and Ohio Rail-
way dock, was completed in 1936. Maintenance dredging nor-
mally performed during the late summer and fall months usually
restores project depth over a center width of 300 feet in the lake
section and over about 80 percent of the river channel. Contin-
uous and heavy shoaling usually results in a controlling depth of
about 23 feet in the bay section channel by the end of the fiscal
year. The controlling depth is 16.5 feet in the turning basin. The
center dike which forms a foundation for the range lights in
Maumee Bay is in poor condition, removal of the dike has been
recommended. The costs for the existing project have been as
follows:
   Regular funds:
       New work and maintenance prior to 1903 (not separable)  $ 1,410,262
       Maintenance since 1903--------------------------------5,381,202
            Total_                        -                                       -                -           6,791,464
        Public works funds, new work_                                                       -                  3,690,000
            Total, all funds_-                                                                               10,481,464

                                        Cost and financial summary

                                                      Fiscal year ending June 30                             Total to June
                                                                                                            30, 1954, includ-
                                                                                                            ing fiscal years
                                 1950               1951         1952             1953           1954        prior to 1950

New work:
   Appropriated                                                                                                 1 $6,724,958
   Cost-                 -----------------------
                           ---                                          ---------------                          16,724,958
Maintenance:
   Appropriated   -------
                        $421,       000            $396, 269   $220, 500        $313, 300       $303, 000          5, 386, 347
   Cost . -  _                  416,288             400, 026    222,175          312,124         299,031           5,381,202

1 Includes $1,624,695 for new work for previous projects.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project __                            $464,700
1178            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                        10. INACTIVE NAVIGATION                          PROJECTS

                                                                        Cost to June 30, 1954
                                                           For last                                  Estimated
                   Name of project                       full report,                           amount
                                                         see annual                Operations required to
                                                         report for- Construction     and      complete
                                                                                  maintenance

  1. Alpena Harbor, Mich.2 ...........      _______...           1951    $328, 451       $114,519       (1)
2. Belle River, Marine City, Mich.2 5----                       1907      24,301             857       (1)
3. Black River, Mich.6 7          .............                 1951     140, 323        392,136       $194, 526
4. Channel between Mackinac Island and                          1946     419,400           7,831       (1)
       Round Island.
5. Channels in Lake St. Clair, Mich-------.....             .   1953   4,192, 782     1,291, 221       (1)
6. Channels in Straits of Mackinac, Mich.,                      1946      29,544 ..----------          (1)
       Poe Reef Shoal.                               -         -
7. Cheboygan Harbor, Mich.           ._    ......           .   1953      242, 510       133,311       (1)
                                                                 1939
8. Clinton River, Mich.----___________________....................         60, 046        53,410       (1)
9. Hammond Bay Harbor7 ....................                     1951       19,833-                      860,567
10. Harbor of Refuge at Harbor Beach, Lake                       1953   1, 200, 598    1, 496523        (1)
       Huron, Mich.2                     - - - -           -
11. Harrisville Harbor, Mich.7 8....          ....               1952     21, 782 .. _                 1, 177, 718
12. Mackinac Harbor, Mich._'-__------.........                   1953     77, 982         31, 623       (1)
13. Maumee River, Ohio, above Toledo 2 - 5                       1873      7, 000                       (7)
14. Monroe Harbor, Mich................ ......                   1953   9987, 340      p 578, 279          90,160
15. Pine River, St. Clair City, Mich.----------                  1907     13,647            1, 031      (1)
16. Point Lookout Harbor, Mich. 7 s                              1951      2, 520 .       _._         1, 169, 980
17. Port Clinton Harbor, Ohio 2_--.                ---.....      1951     71,950          92, 591       (1)
18. Put-in-Bay, Ohio 2___________________
                       .............                         1951          51, 747          1,512       (1)
19. Rogers City Harbor, Mich.2 5s... 2                       1926           5, 666             193      (4)
20. Sebewaing Harbor and River, Mich. ........ -             1917          50, 573          8, 427      (1)

  1 Completed.
  2 Channels adequate for commerce.
  3 Abandonment recommended in H. Doc. 467, 69th Cong., 1st sess.
  4 Project 65 percent complete.
  5 No commerce reported.
  6 Incomplete.
  T Awaiting local cooperation.
  9 Work suspended for duration of defense emergency.
  9 Includes contributed funds.


11. RIVER AND HARBOR WORK UNDER SPECIAL AUTHORIZATION
-PROTECTING, CLEARING AND STRAIGHTENING CHANNELS OF
   NAVIGABLE WATERS (SECTION 3 OF THE 1945 RIVER AND
                      HARBOR ACT)
  Section 3 of the River and Harbor Act approved March 2, 1945,
authorized the allotment not to exceed $300,000 from any appro-
priations made for any one fiscal year for improvement of rivers
and harbors, for removing accumulated snags and other debris,
and for protecting, clearing, and straightening channels in navi-
gable harbors and navigable streams and tributaries thereof, when
in the opinion of the Chief of Engineers such work is advisable
in the interest of navigation or flood control.
   The operations during the fiscal year pursuant to this authoriza-
tion consisted of the following work:

                  Location                         Nature of work        Contract or hired labor         Costs

Foot of Lake Superior...-___-...... ......      Removal of boulder_ Contract----....    -        _ $12,562
                                                                                               -___
Gros Cap Reef upper St. Marys River...          Removal of shoal.... U.S. dipper dredge Tompkins- 70, 308
Foot of Lake Huron_....-----------              Removal of wreck..- U.S. derrick boat Erie....      22, 200



   The total costs for the fiscal year were $105,070, all for main-
tenance.
                           FLOOD CONTROL--DETROIT, MICH., DISTRICT                                                                1179
                                              Cost and financial summary

                                                           Fiscal year ending June 30                                      Total to June
                                                                                                                          30, 1954, includ-
                                                                                                                          ing fiscal years
                                      1950               1951               1952               1953            1954         prior to 1950


Maintenance:
    Appropriated ...                         ......
                           ---------- ------------              ------------------------                     1$187, 200           $187, 200
    Cost................                         ......................-----------------------------------    1184, 762            184, 762

  1 Includes $150,000 appropriation, and $79,692 of prior year costs which were transferred from St. Marys
River.

                    12. SEBEWAING, SEBEWAING RIVER, MICH.
   Location. Sebewaing River drains an area of about 105 square
miles in Huron and Tuscola Counties on the westerly side of the
Thumb area of the Lower Peninsula of Michigan and discharges
into Saginaw Bay, an arm of Lake IIuron, about 20 miles north-
east of the mouth of Saginaw River. (See U. S. Lake Survey
Chart No. 5.)
   Existing project. This provides for the enlarging of the pres-
ent channel of the Sebewaing River through the village of Sebe-
waing, Mich., to a capacity of 7,500 cubic feet per second from the
junction of the Columbia and State drains to a point 4,500 feet
lakeward of the railroad bridge near the mouth, for altering the
railroad bridge and three highway bridges to permit free passage
of ice, and for removal of the present dike on the south side of
the channel lakeward of the railroad bridge.
   The project is designed to provide protection for the village of
Sebewaing from floods with a frequency of occurrence of once in
15 years and with a magnitude greater than the maximum flood
of record.
   The existing project was authorized by the Flood Control Act
approved August 18, 1941. (See H. Doc. 286, 76th Cong., 1st sess.,
which contains the latest published maps.)
   The current (1951) estimated cost of construction is $380,500.
The approved estimate (1954) for annual cost of maintenance is
$5,000.
   Local cooperation. With the exception of the furnishing of
easements, and rights-of-way for the removal of the remaining
portion of the dike on the south side of the channel lakeward of
the railroad bridge, all requirements of local cooperation have
been complied with.
   Operations and results during fiscal year. The continuing
stream gaging program and sounding survey to determine the
condition of the channel and extent of the shoaling were accom-
plished at a total cost of $2,894. Minor repairs were made to the
stop logs at a cost of $63. Due to the comparatively mild winter
and early thaw, removal of ice jams was not required. The total
costs for the fiscal year were $2,957.
   Condition at end of fiscal year. The work required to construct
the project is 95 percent complete. The incomplete portion of
the project consists of the removal of the remainder of the old
earth dike on the south side of the channel lakeward of the rail-
road bridge. All items of the project are in good condition with
1180        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

exception of the Channel which has shoaled to considerable extent
throughout the entire length, and extensively at the upper end
of the project and downstream of the railroad bridge. The costs
have been as follows:
     New work_ - ---                                                                   -       $365,642
     Maintenance              ..-                                                                .15,321
       Total                                       --                                           380,963

                                 Cost and financial summary

                                       Fiscal year ending June 30                           Total to June
                                                                                           30, 1954, includ-
                                                                                           ing fiscal years
                          1950        1951        1952        1953              1954        priorto 1950

New work:
   Appropriated-----------------------$858------------
   Appropriated _ _  .    .      |    -$858                  .........                             $365,642
   C ost ..............
                      _
                     _............                               -    ------------
                                                                         - -_                      $365,642
                                                                                                    365,642
Maintenance:
   Appropriated _...._     $3, 000     2, 000      $2, 457     $3, 700          $2,000               16,157
   Cost-....._........_     3,665      2,263        2,691       2,185            2,957               15,321


Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project_          -           --   -$14,900


                   13. RED RUN, CLINTON RIVER,                       MICH.
   Location. Red Run, a tributary of South Branch of dOinton
River, drains an area of about 70 square miles in Oakland and
Macomb Counties, in the southeastern portion of the Lower Penin-
sula of Michigan.
   Existing project. This provides for enlargement of the chan-
nel of Red Run, from the intersection of Campbell and Twelve Mile
Roads to the junction with South Branch, a distance of about 12
miles, to a trapezoidal section having side slopes generally of one
vertical on two horizontal and a depth, from design-profile water
surface (elevation 621 feet above sea level at the junction of Camp-
bell and Twelve Mile Roads and 598 feet at the junction with South
Branch) to bottom, of 13 feet; with bottom widths of 40 feet up-
stream from the junction of Bear Creek, 80 feet below Bear Creek,
100 feet below Beaver Creek, and 125 feet below Plum Brook; with
necessary local modifications of side slopes and rectifications of
alinement of the channel.
   The plan of improvement will give substantially complete pro-
tection against such damage as has occurred in the past and will
result in an increase in the value of property in the areas subject
to flooding.
   The existing project was approved by the Flood Control Act ap-
proved June 30, 1948. (See H. Doc. 628, 80th Cong., 2nd sess.,
which contains the latest published maps.)
   The estimate of Federal cost for new work (1954) is $953,000.
The estimated cost to local interests is $3,474,100.
                           FLOOD CONTROL--DETROIT, MICH., DISTRICT                                                         1181
    Local cooperation. Fully complied with.
    Operations and results during fiscal year. The drainage board
contracts for underpinning and replacing bridges over Red Run
were the only work on the project remaining incomplete at the be-
ginning of the fiscal year. Federal participation in these contracts
is limited to the amount required for underpinning existing struc-
tures. The following bridges were completed during the fiscal
year.

                                                                                                                    Federal
                        Location                                             Type of work                     cosrts--fiscal yatear
                                                                                                                      1954


Ryan Road------_     -----------------------                        Replacement bridge ------------ --              $18,252
Mound Road --.--                                                .-----------------------
                                                                         do------------------------                   1, 718
Dequindre Road..............................----------------------------do ....----------------------------           4, 855
Shoenherr Road....................-------------------------         Underpinning bridge--------------                    142



   Underpinning work on Fifteen Mile Road' and Maple Lane
Bridge continued, Federal costs being $51,032 and $9,842, respec-
tively. The total costs during the fiscal year, including final ac-
counting for previously completed work, were $84,795, all for new
work.
   Condition at end of fiscal year. The existing project is com-
plete and in operation except for two bridges across the channel.
These bridges, the Fifteen Mile Road and the Maple Lane Road,
are 91 percent and 85 percent complete, respectively, and will be
completed early in fiscal year 1955. The project facilities except
for the bridges, were turned over to the drainage board on July
26, 1952, for operation and maintenance in accordance with re-
quirements of the authorizing legislation.
   The costs have been as follows:
      New work:
         United States funds_                                                                                  -$      939,712
         Contributed funds_-                                      -                                                    257,837
                 Total          ------------------------------------------                                           1,297,549

                                           Cost and financial summary
                                               UNITED STATES FUNDS


                                                      Fiscal year ending June 30                                 Total to June
                                                                                                                30, 1954, includ-
                                                                                                                ing fiscal years
                                    1950            1951              1952         1953           1954           prior to 1950

New work:
   Appropriated..   ---------      $500, 000      $430, 000       $ 40,000 ..----------         --$17, 594               $952, 406
   Cost....-----------------         48,486        401,266         186,526     $218,449            84, 985                939,712


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_-                   $1,672
    Unpbligated balances available for succeeding fiscal year ending June 30,
     .1955_-1,672
1182            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                        Cost and financial summary
                                            CONTRIBUTED FUNDS


                                                Fiscal year ending June 30                               Total to June
                                                                                                        30, 1954, inclu-
                                                                                                        ing fiscal years
                                 1950          1951           1952          1953              1954       prior to 1950


New work:
   Appropriated.    ------       484, 000                                 -$50, 000      --                     $434, 000
   Cost_     -                    10,041      $179,181       $139,904        27, 133           $1,578            357,837


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-_-----------        $75,163
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955     -------------------------------------------------               75,163
                   14. INACTIVE              FLOOD CONTROL                      PROJECTS

                                                                           Cost to June 30, 1954
                                                          For last                                         Estimated
                 Name of project                         full report,                                        amount
                                                         see annual                   Operations           required to
                                                         report for-    Construction     and                complete
                                                                                     maintenance

1. Mount Clemens, Clinton River, Mich..---------             1953       2 $1, 136,008 --------------           (1)
2. Reno Beach-Howard
                 s       Farms area, Lucas                   1953               4,467 --                       $451, 533
    County, Ohio. 4


  1Completed.
  3
  2 Includes $202,996 contributed funds.
   Awaiting local cooperation.
  4 Work suspended for duration of defense emergency.
                             15. GENERAL INVESTIGATIONS
    Examinations and surveys. The cost of work during the fiscal
year was $102,587 for navigation studies, $35,817 for flood control
studies, and $1,903 for special studies, making a total cost of
 $140,307. There were no accounts receivable at the end of the
fiscal year.
    The balance unexpended at the end of the fiscal year amounting
to $1,478 for navigation studies, $640 for flood control studies and
 $1,103 for special studies, a total of $3,221, will be applied to con-
tinuing work on the Maumee River Survey Report in the amount
of $640, and the balance of $2,581 will be expended on unliquidated
obligations for navigation studies. The additional sum of $33,500
for navigation studies and $40,600 for flood control studies, a total
of $74,100, can be profitably expended in fiscal year 1955.
    Collection and study of basic data. The cost of work during
the fiscal year was $2,000. The funds were used for Flood Emer-
gency Studies in the amount of $215 and for International Water
Studies in the amount of $1,785.
    The balance unexpended at the end of the fiscal year, amounting
to $1,000, will be expended for International Water Studies. The
additional sum of $1,000 can be profitably expended during the
fiscal year 1955 for miscellaneous flood investigations.
     16. INSPECTION OF COMPLETED FLOOD CONTROL WORKS
    Inspections of the completed local protection flood control proj-
ects were made as required at a cost of $868.
   The total costs have been $868.
                                FLOOD CONTROL--DETROIT, MICH., DISTRICT                                                                         1183
                                                     Cost and financial summary

                                                                   Fiscal year ending June 30                                           Total to June
                                                                                                                                        30, 1954, includ-
                                                                                                                                        ing fiscal years
                                             1950              1951                 1952                 1953         1954                prior to 1950

  Maintenance:
     Appropriated--...........------------ -----------------------                                        $1,000            $100                  $1,100
       Cost ---------------------------------------------------------                                                        868                      868



   17. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATIONS
    Snagging and clearing of navigable streams and tributaries in
the interests of flood control. (Section 13 of the 1946 Flood Con-
trol Act.)
    The operations during the fiscal year pursuant to this authoriza-
tion consist of preliminary engineering and planning in connection
with straightening and deepening the channel at the mouth of the
Kawkawlin River, Mich. The costs were $2,017, all for new work.
                                                    Cost and financial summary

                                                                 Fiscal year ending June 30                                         Total to June
                                                                                                                                   30, 1954, includ-
                                                                                                                                   ing fiscal years
                                            1950              1951                 1952                 1953         1954               prior to 1950


New work:
   Appropriated--------.......         ------------------                   ----------------------                  $38,000                     $38,000
      Cost--------                                         ......------------------------------------------------        2,017                    2,017


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954- ---      _ ----    $35, 965
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955.    ------------------------------------------------- 35,965

   Small flood control projects not specifically authorized by Con-
gress. (Section 212 of the 1950 Flood Control Act.)
   During the fiscal year, the construction of about 3,000 lineal feet
of earth and rock-fill protective dikes at Camp Perry, Ohio, in co-
operation with the National Guard of Ohio, was completed. The
cost of the completed project was $150,000, excluding $28,670 con-
tributed by local interests. The costs for the fiscal year were
$138,218, excluding $28,670 contributed by local interests.
                                                    Cost and financial summary
                                                     UNITED STATES FUNDS


                                                               Fiscal year ending June 30                                           Total to June
                                                                                                                                   30, 1954, includ-
                                                                                                                                   ing fiscal years
                                           1950              1951                 1952                 1953         1954.           prior to 1950

New work:
   Appropriated-------------                     ------------------------                           $150,000------------._$150,000
   Cost     ............--------------------.......------------------.--------                       11,782  $138,218        150,000
                                                          I~11-I                                                    i:             ig     ~calyear$15,0I



          Sig 38--1183-1214
1184        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                   Cost and financial summary
                                    CONTRIBUTED        FUNDS


                                         Fiscal year ending June 30                     Total to June
                                                                                       30, 1954, includ
                                                                                       ing fiscal years
                            1950        1951        1952        1953         1954       prior to 1950


New work:
   Appropriated     ------------------------------------     $125, 000----                    $125, 000
   Cost      ---------------------------------------------------             $28,670             28,670


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954------- - ----       $95, 570
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955     -------------------------------------------------               95,570
  IMPROVEMENTS OF RIVERS AND HARBORS IN THE
            BUFFALO, N. Y., DISTRICT

   The district comprises a portion of northeastern Ohio, north-
western Pennsylvania, and western and northern New York, em-
bracing the United States waters of Lake Erie, exclusive of the
western end, Lake Ontario, and the St. Lawrence River, with their
tributary drainage basins from and including Sandusky Bay, Ohio,
to the international boundary line east of Frontier, N. Y.
                                   IMPROVEMENTS



                Navigation                                  Flood control
                                     Page                                          Page
1' Sandusky Harbor, Ohio .....      1185   19. Lancaster, Cayuga Creek, N. Y.     1228
2. Huron Harbor, Ohio ........      1187   20. Batavia and vincinity, Tona-
3. Lorain Harbor, Ohio ........     1189         wanda Creek, N. Y_               1228
4. Cleveland Harbor, Ohio       ,,  1191   21. Wellsville, Genesee River, N. Y.   1229
5. Fairport Harbor, Ohio__          1195   22. Mount       Morris    reservoir,
6. Ashtabula Harbor, Ohio_          1198         Genesee River, N. Y_             1231
7. Conneaut Harbor, Ohio_           1200   23. Dansville and vicinity, Genesee
8. Erie Harbor, Pa_____
9. Dunkirk Harbor, N. Y     ------  1203
                                     1206
                                                  River, N. Y-     -    -----      1232
                                            24. Montour Falls, Oswego River
10. Buffalo Harbor, N. Y .......     1208         Basin, N. Y_________             1233
11. Black Rock Channel and Tona-            25. Syracuse, Oswego River Basin,
       wanda Harbor, N. Y    ------
12. Niagara River, N. Y ........
                                      1211        N. Y
                                      1216 26. Inactive flood control projects.
                                                                                   1234
                                                                                   1236
13. Niagara Remedial Works, N. Y. 1217 27. General investigations_.__              1236
14. Rochester (Charlotte) Harbor,           28. Inspection of completed flood
       N. Y ....-... . . .       ..-. 1219:       control works                    1236
15. Great Sodus Bay Harbor, N. Y. 1221 29. Flood control work under
16. Oswego Harbor, N. Y-              1222        special authorization            1237
17. Ogdensburg Harbor, N. Y. ..       1225
18. :Inactive navigation projects__ 1227


                       1. SANDUSKY          HARBOR, OHIO
  Location. This harbor is located in the southeasterly portion
of Sandusky Bay, 55 miles westerly from Cleveland, Ohio. : (See
U. S. Lake Survey Chart No. 365.)
  Previous projects. Adopted by River and Harbor Acts of June
11, 1844; June 23, 1866 ; March 3, 1873; July 5, 1884; August 11,
1888; and August 18, 1894. For further details, see page 1960 of
Annual Report for 1915, and page 1574 of Annual Report for 1938.
  Existing project. This provides for the following:
  a. An outer channel 400 feet wide and 21 feet deep from deep
water in Lake Erie through Sandusky Bay, a distance of about 31/2
miles, to the city waterfront docks.
   b. A channel along the waterfront about 7,800 feet long,' 300
feet wide, and 22 feet deep, ending in a turning basin generally
800 feet wide and 22 feet deep, and a dike constructed with the
excavated rock on the north side of the channel and basin.
   c. Maintaining a channel to a depth of 22 feet, from the turning
                                                                            1185
1186              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

basin northward about 3,540 feet, that portion opposite the Penn-
sylvania Railroad coal wharf to a width of 350 feet, and north
thereof to a width of 400 feet; thence 300 feet wide northeastward
through Sandusky Bay about 7,700 feet, to a junction with the
straight channel; no dredging to be done within 50 feet of the face
of the wharf.
    d. Protection works consisting of a stone jetty on the easterly
side of the channel, extending northeasterly from Cedar Point, a
distance of 6,000 feet, with suitable pierhead; a short stone spur
at Cedar Point; and revetment of the slope adjacent to the channel
in the vicinity of the inner front light with a brush-and-stone mat-
tress.
    The project depth is referred to low water datum for Lake Erie,
which is 570.5 feet above mean tide at New York. Ordinary fluc-
tuations of water level are from 3.5 feet above to 0.5 foot below
low water datum, and extreme fluctuations, produced by wind and
other causes, are from 6 feet above to 2.5 feet below that plane.
    The actual cost of new work was $2,597,258 (excluding $325,000
contributed by local interests), exclusive of amounts expended on
previous projects. The (1954) estimate of annual cost of main-
tenance is $92,000.
    The existing project was authorized by the following River and
Harbor Acts:

       Acts                          Work authorized                                   Documents

Mar. 3, 1899       Construction of channel protection works..... _.-        H. Doc. 362, 55th Cong., idsess.,
                                                                             and Annual Report, 1898, p. 2708.
June 13, 1902      Widening of straight and dock channels and deepen-       H. Doe. 120, 56th Cong., 2d sees.
                    ing to 19 feet.
Mar. 2, 1919       Extension of east jetty to total length of 6,000 feet,   H. Doe. 982, 64th Cong., 1st sess.
                  I with pierhead on outer end; deepening of the outer,
                    straight, and easterly portion of dock channels to
                     21 feet, and westerly portion of dock channel to 20
                    feet.
Jan. 21, 1927      Deepening of dock channel to 22 feet    ______..____     H. Doc. 584, 69th Cong 2d seas.
Aug. 30,19351      Enlargement of turning basin and construction of         Rivers and Harbors Committee
                    rock dike.                                               Doc. 2, 73d Cong., 1st seas.'
Mar.    2, 1945    Maintenance of bay channel to 22 feet; and elimina-      H. Doc. 328, 76th Cong., 1st sess.'
                     tion from project of portion of turning basin and
                     rock dike.

1 Included in Public Works Administration program, Nov. 15, 1933.
s Contains latest published maps.


   Local cooperation. Fully complied with.
   Terminal facilities. There is an extensive coal terminal, con-
sisting of three docks, adjacent to the turning basin at the westerly
end of the dock channel open to shippers of coal. Located on the
dock channel are 10 private terminals for the handling of sand and
gravel, fish, miscellaneous freight, and passengers. The city of
Sandusky owns a pier and two small boat basins. A yacht club
dock and several other privately owned servicing and storage docks
are for recreational and other small craft. Two docks for passen-
ger boats are located at Cedar Point. The facilities are considered
adequate for the existing commerce. (See Lake Series No. 4, re-
vised 1950, Corps of Engineers.)
  Operations and results during fiscal year. Government plant
and hired labor removed 131,641 cubic yards of material and minor
                         RIVERS AND HARBORS--BUFFALO, N. Y., DISTRICT                                                                             1187
obstructions for restoration of project depths in the channels at a
cost of $58,332, and performed miscellaneous inspection services
at the project at a cost of $9,652. The total cost for maintenance
for the year was $67,894.
    Condition at end of fiscal year. The existing project was com-
pleted in 1935 at a cost of $2,922,258 (including $325,000 contrib-
uted by local interests). The protecting works are generally in
poor condition. The east jetty has settled from its original eleva-
tion of 4.3 feet to about 1 or 2 feet above low water datum and in
some places has settled to below low water datum. The stone in
the dike has disintegrated and settled. In many places the dike is
down to low water datum. The controlling depth in the straight,
outer bar, and bay channels is 21 feet and in the dock channel and
turning basin 20 feet at low water datum.
    The total costs of the existing project were $3,932,694, of which
 $2,597,258, including $599,500 public works funds, were for new
work and $1,335,436 for maintenance. In addition, $325,000 were
expended from contributed funds for new work.

                                                         Cost and financial summary

                                                                 Fiscal year ending June 30                                              Total to June
                                                                                                                                        30, 1954, includ-
                                                                                                                                        ing fiscal years
                                              1950              1951             1952                        1953            1954        priorto 1950

New work:
     Appropriated--.             -   -   .-    -.    -   -                _.. --......-- .2                                                1... $3, 074,407
     Cost                                      .......                                          .                                           12 3,074,407
          --------------------                     -----
                                              ---------------             -------------------       ---_~.        --
                                                                                                                 --------   --   ---        12    07,    7

Maintenance:
     Appropriated.                            $65, 587          $66,000          $58,000                     $63,000         $69, 076            1,337,152
     Cost.....-----------------                65,587            63,943           58,287                      64,146          67,984             1,335,436


1Includes $477,149 for new work for previous projects.
2   In addition, $325,000 for new work was expended from contributed funds.


                                               2. HURON HARBOR, OHIO
  Location. On the south shore of Lake Erie at the mouth of the
Huron River, 47 miles westerly from Cleveland, Ohio. (See U. S.
Lake Survey Chart No. 363.)
  Previous projects. Adopted by River and Harbor Acts of May
20, 1826, and September 19, 1890. For further details, see page
1961 of Annual Report for 1915, and page 1576 of Annual Report
for 1938.
  Existing project. This provides for a pier 3,170 feet long on
the west side of the entrance channel, the shoreward 1,970 feet
consisting of timber cribs with concrete superstructure and the re-
maining 1,200 feet of rubble-mound construction, with a timber-
crib concrete superstructure pierhead at its outer end; for a rub-
ble-mound east breakwater 1,450 feet long, with a concrete light
foundation at its outer end, founded on the rubble-mound; for a
steel-sheet pile shore protection extending 200 feet westerly from
near the shoreward end of the west pier; for a channel with a
depth of 26 feet in the hard material and 25 feet in soft material
extending from deep water in the lake to the south side of Wheel-
ing & Lake Erie Railway Co.'s slip 1,' at the entrance of the river,
the channel to be 400 feet wide in the lake and 300 feet wide in-
1188            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

ward of the outer pierhead, narrowing to 250 feet at the head of
the channel; and for the enlargement but not maintenance of the
turning basin, 19 feet deep, opposite the Wheeling & Lake Erie
Railway Co.'s ore dock.
   The project depth is referred to low water datum for Lake Erie,
which is 570.5 feet above mean tide at New York. Ordinary fluc-
tuations of water level are from 3.5 feet above to 0.5 foot below
low water datum, and extreme fluctuations, produced by wind and
other causes, are from 5.5 feet above to 2.5 feet below that plane.
   The actual cost of new work was $1,034,350, exclusive of amount
expended on previous projects. The (1954) estimate for annual
cost of maintenance is $55,000. The existing project was author-
ized by the following River and Harbor Acts:

     Acts                         Work authorized                                   Documents

Mar. 3, 1905    Extension of west pier; construction of east break-      H. Doc. 122, 58th Cong., 2d sess.
                 water; removal of part of old east pier; deepening of
                 channel to 19 feet; and dredging of sheltered area.
Mar. 2, 1919    Widening of river to 200 feet; removal of remainder of   H. Doe. 5, 63d Cong., 1st sess.
                 old east pier; construction of new spur pier; en-
                 largement of sheltered area; and closure of breach
                 at shore end of west pier.
Aug. 30,19351   Extension of west pier with pierhead at its outer end;   H. Doc. 478, 72d Cong., 2d sess.
                 removal of outer end of east breakwater and con-         (Contains latest published map.)
                 structing pierhead on new outer end; widening and
                 deepening of channel to present project dimen-
                 sions; enlargement of turning basin at head of
                 channel; shore protection west of west pier; and
                 elimination from the project construction of spur
                 pier and dredging of sheltered area outside of
                 channel limits.

  1 Partially included in Public Works Administration program. Nov. 15, 1933.

  Local cooperation. Fully complied with.
  Terminal facilities. The New York, Chicago & St. Louis Rail-
road (W. & L. E. Div.) has deepened and maintained the channel
above the limits of the Federal improvement. This company has
a dock with a frontage of over 1 mile, which affords facilities for
handling iron ore and coal. The Eastern States Farmers Ex-
change, Inc., has a dock with a frontage of approximately 800 feet,
adjacent to the ore dock. Three fish docks are private. A number
of privately owned servicing and storage docks are for recreational
and other small craft. The town of Huron owns a dock at the foot
of South Street, which is open to the public. The facilities are re-
garded as adequate for the existing commerce. (See Lake Series
No. 4, revised 1950, Corps of Engineers.)
  Operations and results during the fiscal year. Government
plant and hired labor removed 223,956 cubic yards of material for
restoration of project depths in the channels at a cost of $62,718,
made repairs to the east breakwater at a cost of $50,502, and per-
formed miscellaneous inspection services at the project at a cost
of $5,973. The total cost for maintenance for the year was $119,-
193.
  Condition at end of fiscal year. The existing project was com-
pleted in 1940 at a cost of $1,034,350. A length of 250 linear feet
of the west pier timber crib and concrete superstructure conritruc-
tion has been reinforced and repaired with steel sheet piling and
                 RIVERS AND HARBORS-BUFFALO, N. Y., DISTRICT                                                1189
concrete. An additional 1,700 feet of the west pier and portions
of the east breakwater are failing. The controlling depth in the
channel is 25 feet at low water datum.
  The total costs of the existing project were $2,049,618, of which
$1,034,350, including $561,252 public works funds, were for new
work and $1,015,268 for maintenance.
                                     Cost and financial summary

                                               Fiscal year ending June 301                          Total to June
                                                                                                    30, 1954, includ-
                                                                                                    ing fiscal years
                              1950            1951                 1952      1953        1954         priorto 1950


New work:
  Appropriated     -    -                --                                                             i-----
                                                                                                         $1,304,139
   Cost.-                      -                 --------------------                                    11,304,139
                                                                                                         1--
Maintenance:
   Appropriated -            $ 61,000         $27, 600            $75, 867   .$8, 000   $117, 821          1,016, 776
   Cost--------------- --     140,920          23,725              81, 294      4,501    119, 193          1,015,268

1 Includes $269,789 for new work for previous projects.



                                3. LORAIN HARBOR, OHIO

   Laication. On the south shore of Lake Erie at the mouth of the
Black River, 28 miles westerly from Cleveland, Ohio. (See U. S.
Lake Survey Chart No. 357.)
   Previous projects. Adopted by River and Harbor Act of May
23, 1828. For further details, see page 1961 of Annual Report for
1915, and page 1580 of Annual Report for 1938.
  Existing project. This provides for the following:
   a. An outer harbor about 60 acres in area formed by converging
rubble-mound breakwaters with an aggregate length of 6,350 feet
and having an entrance 500 feet wide between pierheads of timber
cribs with concrete superstructure located at the outer ends of the
breakwaters.
   b. Two piers at the mouth of the river 300 feet apart, the west
pier of timber cribs with concrete superstructure 1,003 feet long,
and the east pier 1,875 feet long, of which 1,763 feet is of timber
cribs with concrete superstructure and 112 feet is of sheet-pile
construction.
   c. A depth of 25 feet in soft material and 26 feet in hard mate-
rial in the outer harbor and the river channel to a point 2,200 feet
upstream from the outer ends of the piers, thence 24 feet deep in
soft material and 25 feet in hard material to the upper end of the
American Shipbuilding Co. drydock 2; thence for a channel of the
same depths and generally 200 feet wide suitably widened at the
bends, to the upper end of the National Tube Co. dock, with a
turning basin 650 feet wide and 20 feet deep in the bend of the
Black River immediately upstream from the Baltimore & Ohio
Railroad coal dock, and approximately 690 feet wide and 17 feet
deep opposite the National Tube Co. dock; no project dredging
above drydock 2 to be closer than 50 feet to existing and future
docks or bulkheads.
   d. An approach channel 16 feet deep extending from the outer
harbor to the municipal pier.
1190           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   The project depth is referred to low water datum for Lake Erie,
which is 570.5 feet above mean tide at New York. Ordinarly fluc-
tuations of water level are from 3.5 feet above to 0.5 foot below
low water datum, and extreme fluctuations, produced by wind and
other causes, are from 5 feet above to 2 feet below that plane.
  The actual cost of new work was $2,748,513, including $3,000
contributed by local interests, but exclusive of amounts expended
on previous projects. The (1954) estimate for annual cost of
maintenance is $165,000.
  The existing project was authorized by the following River and
Harbor Acts:
    Acts                        Work authorized                                  Documents


Mar. 3, 1899   Breakwaters and extensions of piers to present di- H. Doc. 131, 55th Cong., 2d sess.
                mensions.                                             and Annual Report, 1898, p. 2718.
Mar. 2, 1907   Extension of 18-foot phannel from inner end of piers H. Doc. 560, 60th Cong., 1st sess.
                to Erie Ave. Bridge.
June 25, 1910  Extension of breakwaters and dredging to depth of H. Doc. 644, 61st Cong., 2d sess.
                19 feet in outer harbor.
Aug. 8, 1917   Extension of breakwaters to present project dimen- I H. Doe. 980, 64th Cong., 1st sess.
                sions.
    Do.......- Deepening of outer harbor and river channel to Erie  H. Doc. 985, 64th Cong., 1st sess.
                Ave. Bridge to a depth of 20 feet.
July 3, 1930   Extension of 20-foot channel to the American Ship- H. Doc. 587, 69th Cong., 2d sess.
                building Co. drydock 2.                                                              2
Aug. 30, 1935 Widening of 2 bends in river and enlargement of H. Doc. 469, 72d Cong., 2d sess.
                turning basin opposite National Tube Co. dock.1
    Do....... Approach channel to municipal pier................. Senate committee
                                                                            2         print, 73d Cong.
                                                                       2d sess.
        --
    Do.....    Deepening outer harbor and river channel to Ameri-    Rivers and Harbors Committee
                can Shipbuilding Co. drydock 2 to present project      Doc. 51, 74th Cong., 1st sess.*
                dimensions and extension of river channel to upper
                end of National Tube Co. dock with turning basin
                 opposite that dock. Maintenance dredging in
                 Black River from American Shipbuilding Co. dry-
                 dock 2 to upper end of the National Tube Co. dock
                 was authorized Apr. 7, 1934, by the Public Works
                 Administration.
     (3)       Enlarging turning basin opposite National Tube Co.    Specified in act.
                dock to present project dimensions.
Mar. 2, 1945   Turning basin in the bend of Black River immedi-      H. Doc. 161, 77th Cong., 1st sess.2
                ately upstream from the Baltimore & Ohio R.R.
                coal dock.

1 Authorized by Public Works Administration, Sept. 6, 1933.
2 Contains latest published maps.
3 First Supplemental National Defense Appropriation Act, 1944, approved Dec. 23, 1943.

   Local cooperation. Fully complied with.
   Terminal facilities. One iron ore terminal and one coal dock
are open to the public.              Extensive docks of the United States Steel
Corp. (National Tube Div.) handle iron ore, limestone, pig iron,
fuel oil, and sand, and are not open to the public. Two sand, one
slag, and four fish docks are privately owned. The American Ship-
building Co., has drydocks and facilities for building and repairing
the largest lake vessels. A yacht club dock and several other pri-
vately owned servicing and storage docks are for recreational and
other small craft. The city of Lorain owns two docks without rail
connections which are open to the public. The facilities are re-
garded as adequate for existing commerce. (See Lake Series No.
4, revised 1950, Corps of Engineers.)
   Operations and results during fiscal year. Government plant
and hired labor removed 130,794 cubic yards of material for res-
toration of project depths in the channels at a cost of $62,380, made
repairs to the east and west breakwaters at a cost of $13,452, and
                RIVERS AND HARBORS-BUFFALO, N. Y., DISTRICT                                              1191
performed miscellaneous inspection services at the project at a cost
of $14,329. The total cost for maintenance for the year was $90,-
163.
   Condition at end of fiscal year. The existing project was com-
pleted in 1951 at a cost of $2,748,512. An outer harbor has been
provided by constructing breakwaters and pierheads completed in
1915, except the extension of the west breakwater to shore, which
was completed in 1921. A channel through the outer harbor to the
entrance to Black River was deepened to 25 feet in 1937, also a
channel 16 feet deep to the municipal pier was provided in 1936.
Deepening the outer harbor was completed in 1946. The entrance
to the river has been improved by the construction of parallel piers
completed in 1909. Widening of two bends in the river was com-
pleted in 1934. The river channel and turning basin opposite the
National Tube Co. dock were deepened to project depth in 1937
and 1938 and the turning basin widened in 1944.
   The protection works are generally in poor condition. The shore-
ward section of the west breakwater which was completed in 1921
has disintegrated and settled and in places is below water datum.
At various locations on the lake face of the lakeward section of the
west breakwater stones have shifted leaving holes in the wall, and
in many sections of the east breakwater the stones above water
have deteriorated and shifted. The concrete superstructure of the
East Pier is badly deteriorated.
   The controlling depth is 25 feet in the channel through the outer
harbor, 24 feet in the river channel to the upper end of the Na-
tional Tube Co. dock, 16 feet in the outer harbor channel to the
municipal pier, and 17 feet in the turning basin opposite the Na-
tional Tube Co. dock, all at low water datum.
   The total costs of the existing project were $4,711,238, of which
$2,745,513, including $165,000 public works funds, for new work
and $1,965,725, including $76,300 public works funds, for main-
tenance. In addition $3,000 was expended from contributed funds
for new work.
                                            Cost and financial summary

                                                  Fiscal year ending June 30                    Total to June
                                                                                            _   30, 1954, includ-
                                                                                                ing fiscal years
                                     1950        1951        1952      1953         1954         prior to 1950


New work:
   Appropriated ------       ------------       $ 50,000    -$9, 000    -$3, 782                     $3, 037,716
   Cost --------------       ------------          2, 423     34,794 ------------    ----             3,037,716
Maintenance:
   Appropriated      - - -         $153, 000     128,600     142,000     209, 000   $88,910            1, 967, 615
   Cost---------         -          158,480      129,377     145,438     205,808     90,163            1,965,725

1 Includes $292,203 for new work for previous projects.
2In addition $3,000 for new work was expended from contributed funds.

                                4. CLEVELAND HARBOR, OHIO
  Location. On the south shore of Lake Erie, at the mouth of
Cuyahoga River, 176 miles westerly from Buffalo, N. Y. (See U. S.
Lake Survey Chart No. 354.)
  Previous projects. Adopted by acts of March 3, 1825, June 23,
1866, March 3, 1875, August 5, 1886, and August 11, 1888. For
1192              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

further details, see page 1962 of Annual Report for 1915, and page
1585 of Annual Report for 1938.
   Existing project. This provides for the following:
   a. Outer harbor 5 miles long and 1,600 to 2,400 feet wide, en-
closed by a breakwater system comprising an east breakwater
21,270 feet long, with a pierhead at its easterly end, of which 3,300
feet is of timber-crib substructure with stone superstructure and
17,970 feet of rubble-mound construction, and a west breakwater
connected with the shore, 6,048 feet long, of timber cribs with
concrete superstructure with a gap of 201 feet about 662 feet from
the shore end.
   b. A rubble-mound spur breakwater 400 feet long to protect the
gap in the west breakwater shore arm.
   c. A main entrance 700 feet wide between arrowhead rubble-
mound breakwaters extending 1,250 feet lakeward from the 850-
foot opening between the main breakwaters, with timber-concrete
pierheads at their lakeward ends.
   d. Two parallel stone-filled timber-crib piers with concrete
superstructure, 325 feet apart, at the mouth of Cuyahoga River;
the east pier 1,602 feet long and the west pier 1,440 feet long.
   e. A depth of 19 feet, with provisional dredging to 23 feet, east-
erly from a line drawn perpendicular to the east main breakwater,
beginning 800 feet easterly from the westerly end thereof, and a
depth of 25 feet westerly from that line.
   f. An entrance channel 25 feet deep, through the outer harbor
and between the piers up to the New York Central swing bridge.
   g. Improvement of the channels in Cuyahoga River to the vicin-
ity of mile 5.8 and in Old River to the head of the Sand Products
Corp. dock to a depth of 23 feet, the balance of Old River to a
depth of 21 feet, with a turning basin in Cuyahoga River to a
depth of 18 feet in the vicinity of mile 4.8.
   h. Replacement or pier reconstruction of seven railroad bridges.
   The project depths are referred to low water datum for Lake
Erie, which is 570.5 feet above mean tide at New York. Ordinary
fluctuations of water level are from 3.5 feet above to 0.5 foot below
low water datum, and extreme fluctuations produced by wind and
other causes are from 4.5 feet above to 1 foot below that plane.
   The estimated cost of new work is $26,709,000 (1954). The es-
timate for annual cost of maintenance is $7,000 (1954).
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                          Work authorized                                       Documents

Mar. 3, 1875      West breakwater    1_   ____Annual                                    Report, 1876, p. 558.
Aug. 5, 1886      Part of east breakwater _                 _                H.  Ex. Doc. 116, 48th Cong., 2d
                                                                               sess., and Annual Report, 1886,
                                                                               p. 1865.
Aug. 11, 1888     Extension of east breakwater                   _           H. Ex. Doc. 189, 50th Cong., 1st
                                                                                  sess., and Annual Report, 1888,
                                                                               p. 2005.
June    3, 1896   Reconstruction of piers___ _ _    -                  -     H. Doc. 326, 54th Cong., 1st sess.,
                                                                               and Annual Report, 1896, p. 2949.
                  Dredging of channel between piers and outer harbor         H. Doc. 156, 55th Cong., 3d sess.,
Mar. 3, 1899        to a depth of 19 feet; dredging to depth of 23 feet in        and Annual Report, 1899, pp.
June 13, 1902       any portion of harbor in the discretion of Secretary          3075 and 3078.
                    of War.
  See footnotes at end of table.
                     RIVERS AND HARBORS-BUFFALO, N. Y., DISTRICT                                             1193

       Acts                             Work authorized                                      Documents
June 13, 1902 JArrowhead breakwaters and extension of east break-                  H. Doc. 118, 56th Cong., 2d sess.
Mar. 2, 1907    water.
June 25, 1910 Removal of deflecting arm of old east breakwater and                 No printed report.
                closure of gap between old and new east break-
                waters.
July 27, 1916       Pierhead at easterly end of east breakwater--...-------.....   H. Doc. 891, 63d Cong., 2d sess.
                    Maintenance and improvement of channels in Cuya-               H. Doc. 707, 63d Cong., 2d sess.,
Aug. 8, 1917         hoga and Old Rivers to a depth of 21 feet to a point           and Rivers and Harbors Com-
Aug. 26, 1937        2,000 feet upstream from Clark Ave. viaduct and                mittee Doc. 84,2 74th Cong., 2d
                     18-foot turning basin.                                         sess.
Aug. 30,1935s       Deepening of outer harbor and channel between                  H. Doc. 477, 72d Cong., 2d sess.
                     piers to present project dimensions, construction
                     of 400-foot spur breakwater at the gap in the shore
                     arm of west breakwater; removal of easterly 150
                     feet of west main breakwater; elimination from
                     project of a 298-foot southerly extension of the west
                     pier; and abandonment of inner 932 feet of shore
                     arm of west breakwater.
Aug. 30, 1936   4   Maintenance dredging in Cuyahoga and Old Rivers                Rivers and Harbors Committee,
                     for 1 year as an emergency measure.                             Doc. 39, 74th Cong., 1st sess.
       (s)          Maintenance of the extension of the Cuyahoga River             Specified in act.
                     channel.                                                                                         2
Mar.    2, 1945     Extension, maintenance, and improvement to a depth             H. Doc. 95, 79th Cong., 1st sess
                     of 21 feet of Cuyahoga River channel to present
                      project limit.6                                                                                     2
July 24, 1946       Improvement of Cuyahoga and Old Rivers to a depth              H. Doc. 629, 79th Cong., 2d sess.
                      of 23 feet and replacement or pier construction of
                      7 railroad bridges.

  1 Completed under previous projects.
  2 Contains latest published map.
  3 Authorized by Public Works Administration, Sept. 6, 1933.
  4 Previously authorized by Public Works Administration.
  5 First Deficiency Appropriation Act approved Apr. 1, 1944.
  6 Authorized by the Defense Plant Corporation, May, 19 1942.


   Local cooperation. Assurances required for the improvements
authorized by the July 24, 1946, act were received and approved on
May 3, 1949, by the Assistant Secretary of the Army. Negotiations
for furnishing lands, easements, and rights-of-way are currently
under way by the city of Cleveland.
   All other conditions are fully complied with.
   Terminal facilities. There are approximately 48 terminals for
the handling of various types of cargoes, the most important of
which are iron ore, steel products, coal, scrap, cement, sand and
gravel, stone, grain, petroleum products, automobiles, newsprint,
paper, salt, sulfur, and fish. In general, the terminals operated by
the railroads, which include two of the iron-ore and a coal terminal,
are open to shippers of the commodities handled. The city of Cleve-
land owns three terminals, one of which is leased for a miscella-
neous freight and automobile terminal. The Corps of Engineers
owns a wharf at the foot of East Ninth Street which is private.
Several yacht club docks and numerous other privately owned
servicing and storage docks are for recreational and other small
craft. The facilities are considered adequate for the existing com-
merce. (See Lake Series No. 3, revised 1950, Corps of Engineers.)
   Operations and results during fiscal year. New work: Reloca-
tions consisting of replacement or pier reconstruction of railroad
bridges over the Cuyahoga River was carried on by continuing
contracts at a cost for the year of $1,646,195. Replacement of
Bridge No. 8 was completed during December 1953; replacements.
of Bridges Nos. 9 and 1 were continued and were 21 and 12 per-
cent completed, respectively, at end of fiscal year; replacements
of Bridges Nos. 15 and 3 were initiated during April 1954. Widen-
1194     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

ing Cuyahoga River in the vicinity of Bridges Nos. 25 and 8, by
contract, was continued at a cost of $4,522.
   Maintenance: Government plant and hired labor removed 265,-
346 cubic years of material and minor obstructions for restora-
tion of project depths in the outer harbor and entrance channel
at a cost of $115,040, made repairs to the east breakwater at a
cost of $145,451 and performed miscellaneous inspection services
at the project at a cost of $16,218. Maintenance of the Cuyahoga
and Old Rivers was continued and 614,429 cubic yards of material
were removed, by contract, at a cost of $599,929. The total cost
for the year was $2,527,355 of which $1,650,717 was for new work
and $876,638 for maintenance.
   Condition at end of fiscal year. The existing project is about 45
percent complete. The river entrance channel has been improved
by the construction of parallel piers 325 feet apart, and dredging
to a depth of 25 feet at low water datum up to the New York Cen-
tral Railroad bridge. The piers were completed in 1900 and the
dredging in 1935. An outer harbor, about 1,300 acres in extent,
has been formed by the construction of an aggregate length of
about 30,000 feet of breakwater, including converging arms, com-
pleted in 1915. The main entrance has been widened to 700 feet
and protected by converging arms extending lakewood from the
east and west breakwaters, completed in 1908. The outer harbor
was deepened, 1933 to 1935, to 25 feet at low water datum through-
out the west basin, in the entrance channel, and over a portion of
the east basin adjacent to the entrance channel; over the remaining
portion of the east basin a depth of 23 feet at low water datum has
generally been secured. Portions of the channel in Cuyahoga River
were widened each year from 1939 to 1942. Removal of 150 feet
of easterly end of west breakwater and construction of 400 feet
of spur breakwater to protect the gap in the west breakwater
shore arm were completed in 1935. A concrete base for a light
tower was constructed at east end of east breakwater in 1917 in
lieu of the east-end pierhead. Providing a 1,300-foot extension of
the Cuyahoga River channel to the present project limit was au-
thorized by the River and Harbor Act of March 2, 1945, and par-
tially completed with Defense Plant Corporation funds during
1942. Old River to the Sand Products Corp. dock was deepened
to 23 feet in 1952. Replacement of New York, Chicago & St.
Louis Railroad bridge No. 25 was completed during April 1953.
Replacement of the New York Central Railroad Bridge No. 8 was
completed December 1953. The harbor structures require exten-
sive repairs.
   Completing the remainder of the channel extension, widening
portions of the Cuyahoga River, deepening Cuyahoga River to 23
feet, and replacement or pier reconstruction of five railroad
bridges, remain to be done to complete the project.
   The controlling depth in the main entrance channel, through the
west basin and between the piers, was 25 feet, and in the channel
through the east basin, 23 feet. Depths elsewhere in the east basin
within the project area range from 10 to 30 feet. The controlling
depth in the Cuyahoga River was 21 feet; in Old River to Sand
                 RIVERS AND HARBORS-BUFFALO, N. Y., DISTRICT                                           1195
Products Corp. dock, 23 feet; in remainder of Old River, 21 feet;
and in the turning basin, 18 feet.
  The total costs of the existing project were $22,268,997, of which
$12,111,612, including $616,767 public works funds, was for new
work and $10,157,386, including $125,000 public works funds, for
maintenance. In addition, $50,000 was expended from contributed
funds for maintenance.
                                    Cost and financial summary

                                            Fiscal year ending June 30                          Total to June
                                                                                               30, 1954, includ-
                                                                                               ing fiscal years
                               1950        1951         1952          1953         1954         priorto 1950

New work:
   Appropriated .......-    $1, 500,000   $237, 000   $1,000,000   $4,720,000    $ 500,000        1$18, 011, 642
    Cost ----------------        1, 975    991,394    2,033,728       956, 844   1, 650, 717      1 13,675, 765
M aintenance:
    Appropriated--------       536, 002    637, 528     899,539       796,000      862,030         2 10, 311, 402
    Cost-- --------------      653,284     676, 403     915,771       632,743      876,638         ~ 10,157, 386


   Includes $1,564,154 for new work for previous projects.
2 In addition $50,000 for maintenance was expended from contributed funds.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_--------------$19,705
    Appropriated for succeeding fiscal year ending June 30, 1955-------....... 1,000,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955-------___   ------------------------------------                1,019,705
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project      _
                                   ---------------------------------           9,261,500

                             5. FAIRPORT HARBOR,                     OHIO
   Location. On the south shore of Lake Erie, at the mouth of the
Grand River, 33 miles easterly from Cleveland, Ohio. (See U. S.
Lake Survey Chart No. 346.)
   Previous projects. Adopted by River and Harbor Acts of
March 3, 1825, and May 20, 1826. For further details, see page
1963 of Annual Report for 1915, and page 1590 of Annual Report
for 1938.
   Existing project. This provides for the following:
   a. An outer harbor about 360 acres in area formed by a system
of breakwaters comprising a west breakwater, 3,878 feet long,
connected with the shore, consisting of 825 feet of timber-crib sub-
structure with stone superstructure and sea slope, 2,553 feet of
rubble-mound construction, and 500 feet of cellular steel sheet
piling with concrete caps; and an east breakwater 6,750 feet long,
of rubble-mound construction.
   b. A west breakwater pierhead of steel-sheet piling with con-
crete cap and an east breakwater pierhead of timber-crib sub-
structure with concrete superstructure.
   c. An east river pier 1,252 feet long, 578 feet of timber-crib sub-
structure with concrete superstructure, the inner 674 feet not
maintained.
   d. Removal of the old west pier and construction of cellular
steel-sheet pile bulkhead 500 feet long and 300 feet west of the
westerly face of the east pier.
1196              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   e. A depth of 25 feet in soft material and 26 feet in hard mate-
rial in the outer harbor.
   f. A channel in Grand River 24 feet deep and 200 feet wide ex-
tending from the outer harbor a distance of 2,000 feet upstream
from the outer end of the east river pier; thence of the same depth
with a width of 150 feet to the angle in the ore terminal, a farther
distance of 1,700 feet; and thence with a depth of 21 feet, and
with widths varying from 200 to 100 feet for a distance of 4,000
feet to the end of the stone receiving terminal of the Diamond
Alkali Co., with a turning basin 18 feet deep, 760 feet long, and 400
feet wide about midway in this section.
   g. A channel in Grand River 8 feet deep at the upper end of and
adjacent to the west side of the 21-foot project channel, no dredg-
ing to be done closer than 20 feet from the westerly dock lines.
   The project depth is referred to low water datum for Lake Erie,
which is 570.5 feet above mean tide at New York. Ordinary fluc-
tuations of water level are from 3.5 feet above to 0.5 foot below
low water datum, and extreme fluctuations, produced by wind and
other causes, are from 4 feet above to 1 foot below that plane.
  The estimated cost of new work is $2,537,000 (1954), exclusive
of amounts expended on previous projects. The estimate for an-
nual cost of maintenance is $94,000 (1954).
   The existing project was authorized by the following River and
Harbor Acts:

     Acts                           Work authorized                                      Documents


Mar. 3, 18251     Construction of piers-------          ------------------ Annual Report, 1880, pp. 2147-2153.
June 3, 1896      \Breakwaters and dredging outer harbor to a depth of       H. Doc. 347, 54th Cong., 1st sess.,
Mar. 3, 1905      1 18 feet.                                                   and Annual Reports, 1896 p.
                                                                               2956; 1903, p. 2084; 1905, p. 2349.
Mar. 2, 1919      1,400-foot extension of east breakwater, present project   H. Doc. 206, 63d Cong., 1st sess.
                    dimension of east pier; and deepening of harbor to
                 19 feet.
Jan. 21, 1927 4,000-foot extension of east breakwater at limit of cost       H. Doc. 592, 69th Cong., 2d sess.,
July 3, 1930 J to the United States of      T715,000.                          Rivers and Harbors Committee
                                                                               Doc. 13, 70th Cong., 1st sess.
Aug. 30, 1935 2   Deepening of outer barbor and entrance channel to          H. Doc. 472, 72d Cong., 2d sess.
                   present project dimensions; extending the west
                    breakwater to present project dimensions with
                    pierhead at its outer end; removal of west pier: and
                    construction of bulkhead on west side of river
                    channel.
Aug. 26, 1937     Dredging of 21- and 24-foot river channels and turn-       Rivers and Harbors Committee    3
                   ing basin in Grand River to present project dimen-          Doc. 79, 74th Cong., 2d sess,
                   sions.                                                                                        s
July 24, 1946     Dredging of 8-foot river channel_----. ------------.       H. Doc. 706, 79th Cong., 2d sess.


1 Modified 1830, 1881, and 1890. New work completed under previous projects.
2 Partly included in Public Works Administration program, Nov. 15, 1933.
3 Contains latest published maps.




  Local cooperation. The River and Harbor Act of January 21,
1927, requires local interests to contribute $304,000 toward the
cost of extending the breakwater 4,000 feet, and dredge the chan-
nel of approach to their terminal at their own expense. The River
and Harbor Act approved July 3, 1930, waived the condition re-
           RIVERS AND HARBORS-BUFFALO, N. Y., DISTRICT           1197
quiring local interests to contribute to the cost of the breakwater
extension. The condition requiring dredging has not been com-
plied with.
    The act of July 24, 1946, provides for the 8-foot channel subject
to the condition that local interests agree to hold and save the
United States free from damages resulting from the improvement.
This condition has not been complied with.
    All'other conditions have been complied with.
    Terminal facilities. One coal dock does a general public busi-
ness. Two limestone docks, 2 limestone and sand and gravel docks,
6 fish docks, a yacht club dock and 1 dock equipped with a derrick
for handling small pleasure craft, are privately owned. There are
no publicly owned terminals. The facilities are regarded as ade-
quate for the existing commerce. (See Lake Series No. 2, 1950,
Corps of Engineers.)
    Operations and results during fiscal year. Government plant
and hired labor removed 234,564 cubic yards of material and minor
obstructions from the project channels and turning basin for res-
toration of project depths at a cost of $83,650, and performed
miscellaneous inspection services at the project at a cost of $10,-
083. The total cost for maintenance for the year was $93,733.
    Condition at end of fiscal year. The existing project is about 99
percent complete. A length of 400 linear feet of the east pier was
repaired with steel sheet piling and sand filled in 1949. The river
entrance has been improved by the construction of an east pier
completed in 1904, and the removal of the old west pier and con-
struction of the bulkhead, completed in 1939. The east breakwater
was completed in 1931 and the west breakwater in 1935. The river
channel was deepened to project depths, and the turning basin was
excavated in 1939. The outer harbor was deepened and the river
channel was widened at its mouth in 1940.
    The harbor structures require repairs. The concrete cap of two
cells of the cellular section of the west breakwater requires replace-
ment. At several places along the remainder of the west break-
water and along the east breakwater, the slope stone has disinte-
grated and settled. The inner 274 feet of the east pier requires
replacement, and the outer end of the structure requires repairs.
The work remaining to be done to complete the project is the deep-
ening to 8 feet of the westerly portion of the channel in Grand
River at the upper end of the 21-foot channel.
    The controlling depth is 25 feet in the outer harbor, 24 feet in
the river channel for 3,700 feet upstream from the outer end of
the east pier, thence 21 feet in the river channel upstream to the
project limit, and 18 feet in the turning basin. All depths are re-
ferred to low water datum.
   The total costs of the existing project were $4,198,272, of which
$2,496,654, including $187,772 public works funds, was for new
work and $1,701,618 for maintenance.
1198           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                      Cost and financial summary

                                                 Fiscal year ending June 30                   Total to June
                                          ...                                                30, 1954, Includ-
                                                                                             ing fiscal years
                               1950             1951        1952        1953       1954       priorto 1950


New work:
   Appropriated -----------                 .------------              ...------
                                                                .------------          .
                                                                          -----.------------. $2, 865, 594
   Cost      ..
            -------------------                                .....
                                --------------------------------  -------            ------         2,865,594
Maintenance:
   Appropriated --_ --.       $ 89,913          $56, 000    $67,000    $140,000    $93,488          1,701, 684
   Cost . . - - -- .           147, 422          52,462      72,295     139,439     93,733          1,701,618


1Includes   $368,940 for new work for previous projects.
Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project ---------------------------   $40,300

                            6. ASHTABULA HARBOR, OHIO
   Location. On the south shore of Lake Erie, at the mouth of the
Ashtabula River, 59 miles easterly from Cleveland, Ohio. (See
U. S. Lake Survey Chart No. 342.)
   Previous projects. Adopted by River and Harbor Acts of May
20, 1826, March 3, 1829, July 3, 1832, March 2, 1867, June 10,
1872, and March 3, 1881, and modified by the Secretary of Army
July 8, 1890. For further details, see page 1963 of Annual Report
for 1915, and page 1593 of Annual Report for 1938.
   Existing project. This provides for the following:
   a. An outer harbor about 185 acres in area protected by break-
waters, the west breakwater 7,780 feet long, and the east break-
water 4,400 feet long, all of rubble-mound construction, except 430
feet of the west breakwater, which consists of timber-crib sub-
structure and stone superstructure.
   b. A west pierhead of timber-crib substructure and concrete
superstructure.
   c. An east light foundation located 600 feet easterly from the
west pierhead, consisting of a concrete superstructure founded on
the outer end of the rubble-mound east breakwater.
   d. The removal of 250 feet of the old inner east breakwater and
of such additional lengths as may be necessary.
   e. An entrance 28 feet deep between existing breakwaters 600
feet apart; thence a channel of 25-foot depth and 1,100-foot max-
imum bottom width through the outer harbor to the old inner east
breakwater; thence 24 feet deep to the mouth of Ashtabula River;
thence a channel 24 feet deep with a bottom width of 160 feet to
a point 2,000 feet upstream; thence a channel 18 feet deep (except
where ledge rock may be encountered) with a bottom width of 160
feet decreasing to 100 feet and suitably widened at the southerly
end, to the upper car-ferry slip; thence a channel 16 feet deep (ex-
cept where ledge rock may be encountered) with a bottom width
of 100 feet suitably widened at bends and in the turning basin, to
the southerly end of the turning basin; thence a channel 16 feet
deep with a bottom width of 100 feet to a point 1,550 feet upstream
of the turning basin; also an approach channel 24 feet deep, with
a minimum width of 250 feet from the 24-foot-depth section of the
outer harbor eastward to the New York Central Railroad Co.'s slip.
                   RIVERS AND HARBORS-BUFFALO, N. Y., DISTRICT                                       1199
   f. Maintenance to 21-foot depth of that portion of the outer har-
bor between the deepened channel and a meridian line through the
westerly angle of the east breakwater.
   The project depth is referred to low water datum for Lake Erie,
which is 570.5 feet above mean tide at New York. Ordinary fluc-
tuations of water level are from 3.5 feet above to 0.5 foot below
low water datum, and extreme fluctuations, produced by the winds
or other causes, are from 4 feet above to 1 foot below low water
datum.
   The estimated cost of new work is $3,114,000 (1954), exclusive
of amounts expended on previous projects. The estimate for an-
nual cost of maintenance is $101,000 (1954).
   The existing project was authorized by the following River and
Harbor Acts:
       Acts                        Work authorized                                   Documents


June      1896   }3,
                  Construction of breakwater...---------------------Annual      Report, 1895, p. 3122.
June 25, 1910    Enlargement of outer harbor by extension of west        H. Doc. 654, 61st Cong., 2d sess.
                  breakwater and construction of new east break-
                  water; pierheads on lakeward ends of breakwaters;
                  and removal of part of old east breakwater.
Mar. 2, 1919     Extension of west breakwater to shore; dredging         H. Doc. 997, 64th Cong., 1st sess.
                   outer harbor to a depth of 20 feet.
Aug. 30,19351    Removal of a portion of east breakwater, extension      H. Doc. 43, 73d Cong., 1st sess.
                  of breakwaters to present project dimensions, and
                  removal of dredging restrictions in portion of west
                  basin.
Aug. 26, 1937    Dredging of channel through the outer harbor, chan-     Rivers and Harbors Committee    2
                  nel of approach to New York Central RR. Co.'s            Doc. 78, 74th Cong., 2d sess.
                  slip, channel in Ashtabula River, to and in turning
                  basin, all to present project dimensions; removal of
                  portion of old east inner breakwater; and mainte-
                  nance to 24-foot depth of portion of outer harbor.
Mar. 2, 1945     Extension of river channel to the present project       H. Doc. 321, 77th Cong., 1st sess.
                  limit.

1 Authorized by Public Works Administration, Sept. 6, 1933.
2 Contains latest published map.


   Local cooperation. Fully complied with.
    Terminal facilities. There are 3 iron ore and 2 coal terminals
with an aggregate developed dock frontage of 18,500 feet, all open
to the public. There are 4 privately owned fish docks, 1 privately
owned limestone dock, 1 limestone and sand and gravel dock, 1 salt
dock, a large shipyard and drydock, and a car-ferry terminal. A
yacht club dock and several other privately owned servicing and
storage docks are for recreational and other small craft. The fa-
cilities are considered adequate for the existing commerce. (See
Lake Series No. 2, 1950, Corps of Engineers.)
   Operations and results during fiscal year. Government plant
and hired labor removed 106,323 cubic yards of material and minor
obstructions for restoration of project depths in the channels at
a cost of $45,692, made repairs to the east and west breakwaters
at a cost of $59,363, and performed miscellaneous inspection serv-
ices at the project at a cost of $9,594. The total cost for mainte-
nance for the year was $114,649.
   Condition at end of fiscal year. The existing project is about 96
percent complete. The west breakwater was completed in 1915
except 580 feet of the inner end which was completed in 1923, and
1200           REPORT OF CHIEF OF ENGINEERS, U, S. ARMY, 1954

600 feet of the outer end which was completed in 1935. The east
breakwater was completed in 1915; 800 feet of the westerly end
was removed, and a lakeward extension of 700 feet was completed
in 1935. The old inner east breakwater 1,200 feet long was com-
pleted in 1909, and the westerly 600 feet was removed in 1913 and
350 feet in 1935. The 18- and 16-foot sections of the river channel
and the turning basin were deepened to project depth in 1939. The
channel through the outer harbor, the approach channel to the
New York Central Railroad Co.'s slip, and the channel in Ashta-
bula River to a point 2,000 feet upstream from its mouth, were
deepened to project depths in 1940.
   The harbor structures require repairs. Portions of both the
east breakwater and the west breakwater where the slope stone
has pulled away the core stone has washed away, and the deck
stones have dropped, require major repairs.
   The work remaining to be done to complete the project consists
of deepening the upper 1,550 feet of the river channel and the con-
ditional removal of the east inner breakwater. The portion of the
outer harbor to be maintained to 21 feet has not been deepened to
that depth, shale rock being above project depth over a portion of
the area.
   The controlling depth is 25 feet in the channel through the outer
harbor lakeward of the inner breakwater, 24 feet shoreward there-
of, 20 feet in the east basin, 24 feet in the approach channel to the
New York Central Railroad Co.'s slip, and in the Ashtabula River
channel to a point 2,000 feet upstream from its mouth, 18 feet to
the upper car-ferry slip, and 16 feet up to and including the turn-
ing basin.
   The total costs of the existing project were $4,204,895, of which
$2,856,873, including $536,648 public works funds, was for new
work and $1,348,022 for maintenance.
                                      Cost and financial summary

                                                Fiscal year ending June 30                  Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                             1950              1951        1952        1953       1954       priorto 1950


New work:
   Appropriated----------        .----------   -$335    ---------------------------------       1$3, 422,066
                             $        48                                                         13,422,066
   Cost-----------------
Maintenance:
   Appropriated-- ------      52, 000          86,200      $23,800    $162,000   $121,740          1,355, 572
   Cost-----------------      51,906           82,795       24,686     164,798    114,649          1,348,022


IIncludes $565,192 for new work for previous projects.
Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project ---------------- ---------    $257,100

                            7. CONNEAUT HARBOR, OHIO
  Location. On the south shore of Lake Erie, at the mouth of the
Conneaut River, 73 miles easterly from Cleveland, Ohio. (See
U. S. Lake Survey Chart No. 33.)
Previous projects. Adopted by River and Harbor Acts of
March 2, 1829, July 13, 1892, February 24, 1893, and June 3, 1896.
                   RIVERS AND HARBORS-BUFFALO, N. Y., DISTRICT                                       1201
For further details, see page 1964 of Annual Report for 1915, and
page 1597 of Annual Report for 1938.
   Existing project. This provides for the following:
   a. An outer harbor, the deepened portion of which is about 142
acres in area formed by a system of breakwaters comprising a west
breakwater 5,965 feet long, connected with the shore, with a 100-
foot gap, 1,670 feet from shore, all of rubble-mound construction,
and an east breakwater 3,675 feet long, 2,625 feet of which is rub-
ble-mound construction and 1,050 feet of timber-cribs with con-
crete superstructure.
   b. A west breakwater pierhead of timber-crib substructure with
concrete superstructure.
   c. An east breakwater light foundation of concrete superstruc-
ture founded on the outer end of the rubble-mound.
   d. An entrance 600 feet wide between the west breakwater pier-
head and the east breakwater light foundation.
   e. An east pier, 1,008 feet long, of timber-crib substructure and
concrete superstructure.
   f. A depth of 25 feet in soft material and 26 feet in hard mate-
rial in the eastern portion of the outer harbor, and for a depth of
20 feet in the remainder of the outer harbor, consisting of a tri-
angular area with its apex about 900 feet southerly from the west
breakwater pierhead, its southeasterly angle 800 feet westerly from
the west pier, its southwesterly angle 100 feet from the west
breakwater.
   The project depth is referred to low water datum for Lake Erie,
which is 570.5 feet above mean tide at New York. Ordinary fluc-
tuations of water level are from 3.5 feet above to 0.5 foot below
low water datum, and extreme fluctuations, produced by wind and
other causes, are from 4 feet above to 1 foot below low water datum.
   The estimate of cost for new work is $4,990,000 (1954), exclu-
sive of amounts expended on previous projects. The estimate for
annual cost of maintenance is $88,000 (1954).
   The existing project was authorized by the following River and
Harbor Acts:
       Acts                         Work authorized                                  Documents


June 25, 1910     Extension of east breakwater, construction of new       H. Doc. 653, 61st Cong.,r2d sess.
                   west breakwater; removal of portion of old west
                   breakwater; and dredging of outer harbor to 19 feet.
Aug.    8, 1917   Realinement of west breakwater; removal of remain-      H. Doc. 983, 64th Cong., 1st sess.
                   der of old west breakwater, and deepening outer
                   harbor to 20 feet.
       (2)        Removal by Bessemer & Lake Erie RR. Co. of inner
                   645 feet of the west pier.                                                                1
Aug. 30, 1935 3   Removal of a portion of west breakwater; extension      H. Doc. 48, 73d Cong., 1st sess.
                   of breakwaters to present project dimensions; con-
                   struction of pierheads on outer ends of break-
                   waters; deepening outer harbor to present project
                   dimensions; removal of portions of river pier, and
                   elimination from project of a 255-foot shoreward
                   extension of the west breakwater.

  1 Contains latest published maps.
  2 Permit of the Secretary of War, Aug. 5, 1927.
  8Partially authorized by Public Works Administration, Sept. 6, 1933.
    Local cooperation. Fully complied with.
    Terminal facilities. Local interests maintain the river channel
1202     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

to provide access to terminals in the river comprising 1 coal ter-
minal which is open to shippers of coal, 1 iron ore, 1 stone, and 1
steel-products terminal, which are private. The city of Conneaut
owns a terminal and a small boat lagoon on the outer harbor which
are open to the public. The facilities are considered adequate for
the existing commerce. (See Lake Series No. 2, 1950, Corps of
Engineers.)
    Operations and results during fiscal year. Government plant
and hired labor removed 82,683 cubic yards of material from the
outer harbor for the restoration of project depths at a cost of
 $23,734, made repairs to west breakwater at a cost of $41,795, and
performed miscellaneous inspection services at the project at a
cost of $6,448. The total cost for maintenance for the year was
 $71,977.
   Condition at end of fiscal year. The existing project is about 71
percent complete. Under existing project, a length of 4,445 feet
of the new west breakwater was completed in 1916; the old east
breakwater, 1,050 feet long, was extended shoreward 800 feet
 (completed 1911) and lakeward 900 feet (completed 1923). The
1,670-foot shore arm to the west breakwater was completed in
1934. Extension of the west breakwater 830 feet lakeward, the
east breakwater 925 feet lakeward, and removal of the lake arm
of the west breakwater were completed in 1935; 642 feet of the
old west breakwater was removed in 1916, and the remaining 600
feet in 1925. Two piers have been constructed at the mouth of the
Conneaut River. Removal of west pier and 459 feet of east pier
were completed in 1934. The east pier is now 1,008 feet long. A
channel through the outer harbor was dredged to 25 and 26 feet
in 1938.
   The inner 1,200 feet of the west breakwater was rebuilt to its
original elevation during 1941 to 1952. At several places along
the remainder of the west breakwater and along the east break-
water, the slope stone along the lakeside is disintegrating and pull-
ing away and the deck stone is settling. Other harbor structures
are generally in fair condition.
   The controlling depth in the channel through the outer harbor is
25 feet below low water datum. The work remaining to be done to
complete the project is to deepen a 320-foot wide strip on the west-
erly side of the deepened channel through the outer harbor, to 25
feet in soft material and 26 feet in hard material, and to deepen
the remainder of the outer harbor to 20 feet.
   The total costs of the existing project were $4,423,509, of which
$3,270,447, including $1,010,500 public works funds, was for new
work and $1,153,062 for maintenance.
                   RIVERS AND HARBORS--BUFFALO,                                   N. Y., DISTRICT               1203
                                         Cost and financial summary

                                                  Fiscal year ending June 30                           Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                                  1950           1951           1952          1953          1954         prior to 1950'

New work:
    Appropriated---.......-------------                            ------------                 ....          4,075,719
S   Cost     ...----.........-------------------------------------                 -------------------        4,075,719
Maintenance:
    Appropriated---.._            $64, 500       $29, 450      $64, 700      $169, 500      $90, 887          1,211,869
    Cost---....- --                70,632         23,667         75,255       164,009        71,977            1,192,846

    Includes $805,272 for new work and $39,784 for maintenance for previous projects.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project-----_---- --.----       $1,719,600

                                         8. ERIE HARBOR,                   PA.
   Location. On the southerly side of the bay formed by Presque
Isle Peninsula, on the south shore of Lake Erie, 78 miles westerly
from Buffalo, N. Y. (See U. S. Lake Survey Chart No. 332.)
   Previous projects. Adopted by River and Harbor Act of May
26, 1824, and modifications were subsequently made by approval
of the report of a board of engineers in 1855 and in 1865; by the
River and Harbor Act of March 2, 1867; by approval of the report
of a board of engineers in 1870; and by River and Harbor Acts of
August 5, 1886, and September 19, 1890. For further details see
page 1965 of Annual Report for 1915, and page 1600 of Annual
Report for 1938.
   Existing project. This provides for the following:
   a. An entrance channel, 25 feet deep in soft material and 26 feet
deep in hard material, 500 feet wide lakeward of the entrance
piers, and 300 feet wide between the piers and into the harbor.
   b. A channel of the same depths and 600 feet wide from the en-
trance channel to a line 50 feet outside of the pierhead line at the
ore terminal, suitably widened at the junction with the entrance
channel.
   c. A harbor area 21 feet deep, approximately 117 acres, extend-
ing westerly from the 600-foot channel for a distance of about
2,100 feet to a line perpendicular to the harbor line 200 feet west
of the city dock, with its southerly side 50 feet from the harbor line.
   d. An approach channel, 23 feet deep and 300 feet wide, from
the 25-foot channel to and including a turning basin of the same
depth 1,200 feet long by 1,000 feet wide at the westerly docks.
   e. An additional harbor area 18 feet deep, of about 35 acres, ex-
tending westerly from the 21-foot area and northerly from the har-
bor line off the public dock, to natural deep water in the bay.
 1204            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY. 1954

    f. For harbor entrance piers 360 to 450 feet apart, of the timber-
crib type with concrete superstructure, extending to the 14-foot
contour in the lake, the north pier to have a length of about 3,248
feet and the south pier to have a length of about 2,215 feet, further
extension lakeward of the north pier to be made when required to
meet advance of said contour.
    g. A timber-crib breakwater 1,200 feet long (original length,
2,530 feet) with stone superstructure, extending from the inner
end of the south pier toward the mainland, to maintain a closure
at the eastern end of the harbor and for plant growth and emer-
gency protection work on the peninsula.
   The project depths are referred to low water datum for Lake
Erie, elevation 570.5 feet above mean tide at New York. Ordi-
nary fluctuations of water level are from 3.5 feet above to 0.5 foot
below low water datum, and extreme fluctuations, produced by
wind and other causes, are from 5.9 feet above to 2.7 feet below
that plane.
   The estimate of cost for new work is $3,428,000 (1954), exclu-
sive of amounts expended on previous projects. The estimate for
annual cost of maintenance is $73,000 (1954). The existing proj-
ect was authorized by the following River and Harbor Acts:

     Acts                         Work authorized                                    Documents

May 26, 1824     Breakwaters and piers; dredging entrance channel;       Annual Report, 1915, p. 1965.
                  and brushwood protection of beach of Presque
                  Isle Peninsula.'
Mar. 3, 1899     Deepening channel and harbor basin to 18 feet; repair   H. Doc. 70, 55th Cong., 1st sess.,
                   and extension of piers; and plant growth and emer-      and Annual Report, 1897, p. 3237.
                   gency protection work on peninsula.
June 15, 1910                                                       Rivers and Harbors Committee
                 Deepening channel and part of harbor to 20 feet......
                                                                           Doc.26, 61st Cong., 2d sess.
Nov. 28, 1922 2 Reconveyed Presque Isle Peninsula to the State of
                 Pennsylvania for park purposes.
Aug. 30, 1935    Deepening,   widening, and straightening entrance       H. Doc. 52, 73d Cong., 1st sess.
                  channel, dredging channel at easterly end of harbor      (Contains the latest published
                  basin, deepening a portion of harbor basin, all to       map.)
                  present project dimensions; elimination of north
                  breakwater from project; and limitation of south
                  breakwater to a length of 1,200 feet.
Mar. 2, 1945     Approach channel and turning basin to the westerly      H. Doc. 735, 79th Cong., 2d sess.
                  docks.
    Do-..... Protection of the peninsula south of the waterworks         Specified in act.
              settling basin.

1 Completed under    previous projects.
2 Public 366.


   Recommended modification of project. Modification of the ex-
isting project to provide for an anchorage area by widening the
25-foot approach channel to the ore dock, from 600 feet to 1,200
feet, with the western boundary of the area 1,500 feet long and
the eastern boundary about 1,900 feet long, at an estimated cost
of $154,000 for construction with no increase in the cost of annual
maintenance, has been recommended in House Document No. 345,
83d Congress, 2d session.
   Local cooperation. Providing an approach channel 23 feet deep,
including a turning basin, to the westerly docks, is subject to the
condition that local interests give assurances satisfactory to the
Secretary of the Army that they will: Provide and maintain a
coal dumper and slip so that full utilization can be made of the
           RIVERS AND HARBORS-BUFFALO,        N. Y., DISTRICT   1205
improvement; lower the waterworks intake line where necessary;
and hold and save the United States free from all claims for dam-
ages incidental to the work or maintenance thereof. These condi-
tions have not been complied with. Prior conditions have been
fully complied with.
   Terminal facilities. The developed waterfront has a length of
about 2 miles. Two groups of terminals have been established
along this harbor frontage. The westerly group consists of 3
piers, 1 of which is used for sand and stone, 1 for petroleum prod-
ucts, and 1 for sand and petroleum products. The easterly group
consists of 1 terminal for iron ore, limestone, and coal; 1 for petro-
leum; 1 for coal; 1 for pulpwood; 1 for sand, stone, and petroleum;
1 grain elevator; and 1 municipal pier used as a passenger ter-
minal. There are two smallboat basins in which there are docks
for fish, marine repair work, and small pleasure craft. The fa-
cilities are considered adequate for the existing commerce. (See
Lake Series No. 1, 1951, Corps of Engineers.)
   Operations and results during fiscal year. Government plant
and hired labor removed 163,873 cubic yards of material and minor
obstructions, for restoration of project depths in the channels and
basin area at a cost of $38,655, and performed miscellaneous in-
spection services at the project at a cost of $11,315. Rebuilding
540 linear feet of the north pier, by contract, and preparation of
plans and specifications, by hired labor, for an additional 373 linear
feet of the north pier, were completed at a cost of $211,206. The
total. cost for maintenance for the year was $261,176.
   Condition at end of fiscal year. The existing project is 41 per-
cent complete. The breakwater and piers were completed in 1915.
A 3,050-foot section of rubble-mound protection work on the pen-
insula was completed in 1921, 5,281 feet of steel sheet piling pro-
tection work with stone facing were completed in 1930, and two
experimental 300-foot stone groins and about 1,385 feet of stone
protection work at beach 2 were completed in 1943. The construc-
tion of 2,750 feet of stone protection work, just north of the Kelso
groin, was completed in 1944. The 18-foot harbor basin was deep-
ened in 1900. Widening and straightening of the entrance chan-
nel was completed in 1936. The deepening of the entrance chan-
nel and the approach channel to the easterly docks to 25 feet, except
for small triangular areas along the southeasterly and southwest-
erly limits of the approach channel, was completed in 1939. The
21-foot harbor basin was deepened in 1940.
   The harbor structures are generally in poor condition. In ap-
proximately 550 feet of the north pier, the concrete superstructure
has disintegrated, broken, and dropped. In the outer 200-foot
section of the south breakwater, the slope stone on the channel
side has pulled away and dropped. A length of 40 linear feet of
the south pier and 540 linear feet of the north pier has been rein-
forced and repaired with steel sheet piling and concrete. In ap-
proximately 1,400 linear feet of the steel sheet piling bulkhead
with stone facing adjacent to the mainland, Presque Isle protec-
tion works, constructed in 1930, the stone facing has settled, leav-
ing the piling exposed to wave action from the lake.
  The work remaining to be done to complete the project consists
1206          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

of dredging an approach channel and turning basin to the westerly
docks, deepening the remaining portion of the approach channel to
the easterly docks, and the conditional extension of the north pier.
There is a controlling depth of 25 feet at low water datum in the
entrance channel and in the approach channel to the docks at the
easterly end of the harbor, 15 feet to docks at the westerly end,
and 21 feet to the public docks, foot of State Street.
   The total costs of the existing project were $4,177,365, of which
$768,075 was for new work and $3,409,290 for maintenance. In
addition, there was a cost and expenditure of $154,500 from con-
tributed funds for maintenance.

                                       Cost and financial summary

                                                Fiscal year ending June 30                              Total to June
                                                                                                        30, 1954, includ-
                                                                                                        ing fiscal years
                              1950            1951            1952             1953          1954        prior to 1950

New work:
   Appropriated ------       ------      -----------------------------------                -----------      $1, 505, 042
   Cost ----------------------------     -----------------------------------             ------------         1,505,042
Maintenance:
   Appropriated- .......-- $59, 800           $72, 000        $95, 000         $99,500      $327, 830        23,653,770
   Cost..-----------------  60,511             71,031          91,454           31,206       261,176         23,   514,191

1Includes $736,967 for new work and $104,900 for maintenance for previous projects.
2 In addition $154,500 for maintenance was expended from contributed funds.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project ----------------------
                                                 _                   $2,659,900

                             9. DUNKIRK HARBOR,                                N. Y.

  Location. This harbor is located on the south shore of Lake
Erie, 37 miles southwesterly from Buffalo, N. Y. (See U. S. Lake
Survey Chart No. 32.)
  Previous projects. The original project was adopted by the
River and Harbor Act of March 2, 1827, and was modified by the
River and Harbor Act of March 2, 1867, by approval November 30,
1870, of the report of a board of engineers and by the River and
Harbor Act of June 3, 1896. For further details of previous proj-
ects, see page 1966 of Annual Report for 1915, and page 1604 of
Annual Report for 1938.
  Existing project. This provides for an outer entrance channel
with depths of 17 feet in earth and 18 feet in rock, with a least
width of 190 feet just inside the harbor structures, flaring to a
width of 320 feet about 600 feet lakeward thereof, and extending
to deep water; an inner entrance channel and basin to a depth of
16 feet, the west channel limit to be a prolongation landward of
the west limit of the outer entrance channel to a point about 635
feet landward of the centerline of the west pier, thence extending
to a point about 200 feet west of the west face of the city dock on
a line parallel to and 25 feet south of the face of the city dock,
thence extending eastward to a point about 420 feet east of the
east face of the city dock, thence northerly about 270 feet meeting
a line parallel to and 50 feet from the channel arm of the east
                    RIVERS AND HARBORS-BUFFALO,                              N. Y., DISTRICT                1207
breakwater; removal of a rock shoal on the west side of the inner
entrance channel to a depth of 17 feet; for a pier 1,410 feet in
length on the west side of the entrance channel, extending to shore,
1,037 feet of timber-cribs with concrete superstructure, 151/2 feet
with stone superstructure, and 3571/2 feet of the shore end not
maintained; and for a detached breakwater extending eastward
from the entrance channel, 2,814 feet in length, 987 feet of timber-
cribs with concrete superstructure, and 1,827 feet with stone super-
structure.
   The project depth is referred to low water datum for Lake Erie,
elevation 570.5 feet above mean tide at New York. Ordinary fluc-
tuations of water level are from 3.5 feet above to 0.5 foot below
low water datum, and extreme fluctuations produced by wind and
other causes are from 6 feet above to 3 feet below that plane.
   The cost of new work for the completed project was $429,174,
including $11,000 contributed by local interests and exclusive of
amounts expended under previous projects. The (1954) estimate
for annual cost of maintenance is $22,000.
   The existing project was authorized by the following River and
Harbor Acts:
       Acts                           Work authorized                                      Documents

Mar. 2, 18271                                                                  S. Ex. Doc. 42, 35th Cong., 1st sess.,
                   Construction of west pier 1 2........._________________________...........
                                                                                 and Annual Report, 1866, pt. IV,
                                                                                 p. 155.
Mar.     2, 1867   Breakwater2 and  excavation   of    entrance   channel  to  Annual         Report, 1871, p. 214.
                    13 feet.
June 3, 1896       Deepening of entrance channel and harbor basin2  to         H. Doc. 63, 54th Cong., 1st sess.
                    a depth suitable for vessels of 16-foot draft.
June 25, 1910      Removal of rock reef bordering the inner entrance           H. Doc. 720, 61st Cong., 2d sess.
                    channel.
June 30, 1948      Deepening outer entrance channel to present project         H. Doc. 632, 80th Cong., 2d sess.
                    depths; removal of rock shoal on the west side of           (Contains latest published map.)
                    the entrance channel to a depth of 17 feet, and
                    changed limits of the inner entrance channel and
                    basin to present project dimensions.

  I   Modified 1828 and 1852.
  2 Complete under previous projects.

   Local cooperation. Fully complied with.
   Terminal facilities. A dock owned by the city of Dunkirk is de-
signed for commercial use by large lake vessels. The terminal has
been leased to private parties, but is open to all on equal terms
under the terms of the lease. A yacht club dock and a privately
owned marine service dock are for recreational and other small
craft.
   The facilities are considered adequate for the existing commerce.
   Operations and results during fiscal year. Government plant
and hired labor removed minor obstructions in the project chan-
nels and performed miscellaneous inspection services at the proj-
ect, at a cost of $4,060 for the year, for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1951 at a cost of $429,174 (including $11,000 contributed
by local interests). The protecting structures are generally in
good condition. Approximately 800 feet of the lake side of the
west pier has been reinforced with stone riprap, and repairs to ad-
1208           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

ditional areas are necessary. The controlling depth in the outer
channel is 13 feet and the inner channel and turning basin are 16
feet at low water datum.
   The total costs of the existing project were $1,117,422, of which
$418,174 was for new work and $699,248 for maintenance. In ad-
dition, $11,000 was expended from contributed funds for new work.
                                       Cost and financial summary

                                              Fiscal year ending June 30                     Total to June
                                                                                             30, 1954, includ-
                                                                                             ing fiscal years
                                1950         1951        1952           1953       1954       priorto 19501

New work:
   Appropriated ......         $362,000------------------------------------ -..                  2 $1,229,424
   Costc                         92,204         796----
                                            $269,                  ..
                                                                    -   .... .....
                                                                               __.                21,229,424
Maintenance:
   Appropriated ...-----  77,000             176,100    -$5, 039        $4,500      $4,387            878,208
   Cost- --.....----
              .. --......     62             102, 817    146,845         2,388       4,060            875,769


I Includes   $811,250 for new work and $176,520 for maintenance for previous projects.
2 In addition $11,000 for new work was expended from contributed funds.

                               10. BUFFALO HARBOR, N. Y.
   Location. At the eastern end of Lake Erie, at the head of Ni-
agara River, 176 miles easterly from Cleveland, Ohio. (See U. S.
Lake Survey Charts Nos. 3 and 314).
   Previous projects. The original project was adopted by River
and Harbor Act of May 20, 1826, with modifications by River and
Harbor Acts of July 7, 1838, June 23, 1866, June 23, 1874, June
3, 1896, March 2, 1907, and June 25, 1910. For further details
see page 1967 of Annual Report for 1915, and page 1606 of An-
nual Report for 1938.
   Existing project. This provides for the following:
   a. An outer harbor about 41/ miles long and 1,600 feet wide,
formed by a breakwater system, approximately parallel to the lake
shore extending from Stony Point to the head of Niagara River,
and having a total length of 23,704 feet, with entrances near the
north and south ends, and consisting of the Stony Point breakwater
 (including the south entrance arm) 3,603 feet long; the south
breakwater 10,289 feet long; the old breakwater 7,608.5 feet long;
the north breakwater 2,203.5 feet long; a south entrance 550 feet
wide; a centrally located circulation gap about 150 feet wide and
natural depth of 20 feet; and a north entrance 1,300 feet wide.
The types of construction are as follows: 9,550 linear feet of
rubble mound, 14,154 linear feet of timber-crib substructure sur-
mounted with 9,113 linear feet of concrete, 370.5 linear feet of
stone, and 4,670.5 linear feet of stone-concrete superstructure.
    b. A south pier at the entrance to the inner harbor (Buffalo
River), 1,760 feet long, of timber cribs and piles with concrete
and stone superstructure.
    c. A depth of 25 feet in the south entrance and the portion of
the outer harbor south of a line perpendicular to and 2,000 feet
north of the southerly end of the south breakwater and a depth of
23 feet north of that line, with the westerly project limit 150 feet
from the axes of the breakwaters and the easterly project limit
50 feet from the United States harbor line; and removal, to a depth
                     RIVERS AND HARBORS-BUFFALO, N. Y., DISTRICT                                          1209
of 27 feet, of three small shoals located on the direct route of ap-
proach to the south entrance.
   d. A north entrance channel, 800 feet wide with a depth of 25
feet in earth and 26 feet in rock, from deep water in the lake to
the outer harbor; and a depth of 22 feet in earth and 23 feet in
rock in the Buffalo River entrance channel from the outer harbor
to the junction of Buffalo River and Buffalo ship canal, with the
southern project limit 5 feet from the south pier and the northern
project limit 40 feet from the dock of the Delaware, Lackawanna
& Western Railroad Co.
   e. Channels in Buffalo River and Buffalo ship canal with depths
of 22 feet in earth and 23 feet in rock to the upper Delaware, Lack-
awanna & Western Railroad Co. bridge and to the Lehigh Valley
Railroad canal, respectively, with widths generally of 150 and
125 feet, respectively, without dredging closer than 25 feet to dock
lines except at bends, and with the rock ledge just above the Ohio
Street Bridge cut back approximately 13 feet.
    The project depths are referred to low water datum for Lake
Erie, elevation 570.5 feet above mean tide at New York. Ordin-
ary fluctuations of water surface are from 3.5 feet above to 0.5
foot below low water datum, and extreme fluctuations due to wind
and other causes about 9 feet above and 3.5 feet below the plane.
   The estimate of cost for new work is $17,865,000 (1954), ex-
clusive of amounts expended on previous projects. The estimate
for annual cost of maintenance is $290,000 (1954).
The existing project was authorized by the following River and
Harbor Acts:
     Acts                             Work authorized                                    Documents

May 20, 1826       Construction of south pier (extended in 1868) 1-.......    Annual Report, 1868, pp. 222 and
                                                                                232.
June 23, 1866      Construction of old breakwater 1---..---------...........  Annual Report, 1868, pp. 232-236.
June 23, 1874      Extension of old breakwater 1_....         _ _------...    Annual Report, 1876, pt. 2, pp. 569
                                                                                and 573.
June, 3, 1896      Stony Point and south breakwater 1-.......---........ Annual Report, 1895, p. 3153.
Mar. 3, 1899       North breakwater 1_'                               .      J_--_
                                                                              H. Doc. 72, 55th Cong., 1st sess.,
Mar. 3, 1909      1-                     ---   -----              .      ..-    and Annual Report 1897, p. 3245.
June 6, 1900       Deepening entrance channel to inner harbor and re- Specified in acts
June 13, 1902        moving rock shoal therein.
Mar. .2, 1907      Dredging at entrance to canals at South Buffalo in Specified in act.
                     outer harbor.1
Mar. 2, 19072      South entrance breakwater 1----..-...---------             H. Dec. 240, 59th Cong., 1st sess.
June 25, 1910      Extension of Federal project to Commercial St. and H. Doc. 298, Rivers and Harbors
                     removal of Watson elevator site.l                          Committee Dec. 2, 61st Cong.,
                                                                                2d sess.
July 25, 1912      Deepening areas A, B, and     D  in outer harbor   to  21  H.  Doc. 550, 62d Cong., 2d sess.
Mar. 2, 1919
Jan. 21, 1927
                     feet, and area C in north entrance to 23 feet.
                   Deepening   areas F and  0in outer  harbor to 21 feet....  H.  Doc. 1139, 64th Cong., 1st sess.
                   Removal of shoal between entrance channel to Buffalo H. Doc. 481, 68th Cong., 2d sess.
                     River and Erie Basin to 21 feet.
July 3, 1930       Deepening areas H, I, and Kin outer harbor to 21 feet_ Rivers and Harbors Committee
                                                                                Doe. 1, 71st Cong., 1st sess. 4
Aug. 30, 1935 3    Extension of south entrance and south breakwaters, H. Doc. 46, 73d Cong., 1st sess.
                     deepening outer harbor to present project dimen-
                     sions, and removal of shoals on approach to south
                     entrance.
Aug. 30, 1935      Maintenance of channels in Buffalo River and Buffalo Rivers and Harbors Committee           4
                     Ship Canal to 21 feet, in cooperation with the city        Doe. 54, 74th Cong., 1st sess.
                     of Buffalo.                                                                                 4
Mar. 2, 1945       Deepening the North and Buffalo River entrance H. Doc. 352, 78th Cong., 1st sess.
                     channels, and deepening and maintaining the Buf-
                     falo River and Buffalo Ship Canal to present
                     project dimensions.

i Completed under previous projects.
SAlso Sundry Civil Act of Mar. 3, 1905.
I Authorized in part by Public Works Administration, Sept. 6, 1933.
4Contains latest published maps.
1210     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Local cooperation. Fully complied with.
   Terminal facilities. There are approximately 50 terminals for
the handling of all types of cargoes. The most important cargoes
handled are iron ore, coal, grain, limestone, sand and gravel, steel
products, scrap, petroleum products, automobiles, cement, and sul-
fur. In general, the terminals operated by the railroads and lake
transportation companies and most of the grain elevators are
open to the public. The city of Buffalo owns two wharves which
are used as automobile terminals. The American Shipbuilding
Co. has a drydock and facilities for repairing lake vessels. There
are also several privately owned marine service, mooring, and
supply docks for lake vessels and smaller boats. The facilities are
considered adequate for the existing commerce. (See Lake Series
No. 1, revised 1951, Corps of Engineers.)
   Operations and results during fiscal year. New work: Dredg-
ing and rock excavation, by contract, for removal of shoals in Lake
Erie in approach to the south entrance channel, and deepening of
the south entrance channel and southerly portion of the outer har-
bor was continued at a cost of $578,810. A cost adjustment of
$6,432 was made on contract for dredging stage III B, Buffalo
River, completed during fiscal year 1952.
   Maintenance: Government plant and hired labor removed ob-
structions and 241,176 cubic yards of material for restoration of
project depths in the Buffalo River entrance channel, north en-
trance channel and outer harbor at a cost of $59,714; performed
miscellaneous inspection services at the project at a cost of $18,-
452, and made repairs to the south breakwater at a cost of $34,627.
Maintenance of the Buffalo River and ship canal, by contract, was
continued, and 162,339 cubic yards of material was removed for
restoration of project depths at a cost of $178,789.
   The total cost for the year was $876,822, of which $585,242 was
for new work and $291,580 for maintenance.
   Condition at end of fiscal year. The existing project is about
30 percent complete. The Stony Point breakwater was completed
in 1899, a 1,000-foot extension was completed in 1914, 1,200 feet
of the shore end were sold to the Lackawanna Steel Co. in 1918,
and another 1,000-foot extension was completed in 1935. The
south breakwater was completed in 1903, and a 300-foot extension
was completed in 1935. The north breakwater was completed in
1901, the old breakwater in 1893, and the south pier in 1869.
   Removal of three shoals to 27 feet, on the direct approach to
the south entrance channel was completed in 1954. Deepening of
the 25-foot project area in the south entrance channel was com-
pleted in 1954. Deepening of the 25-foot project area in the
southerly part of the outer harbor was completed in 1954 except
for approximately 800 feet of the northern portion.
   The 23-foot project area in the outer harbor and in the north-
end entrance channel, has been deepened to project depth except
for strips 50 feet wide along the harbor line and 180 feet wide be-
tween the Superior Grain Corp.'s and the Merchants Refrigerating
Co.'s piers. Buffalo River entrance channel has been deepened to
21 feet.
  The harbor structures are generally in good condition, except
                      RIVERS AND HARBORS-BUFFALO, N. Y., DISTRICT                                         1211
at various points of the south breakwater and old breakwater
where the slope stone on the lakeside has been displaced, portions
of the stone banquette on the harbor side of the old breakwater
have dropped, and the riprap protection along the lakeside of the
northerly 1,200 feet of the old breakwater has settled.
   The controlling depth in the northerly part of the outer harbor
is 23 feet, and in the north and south entrance channels is 21 feet.
Controlling depth in the Buffalo River channel is 20 feet, and in
the southerly portion of the outer harbor is 21 feet, at low-water
datum.
   The work remaining to be done to complete the project consists
of the deepening of the north entrance channel to 25 feet in earth
and 26 feet in rock; completion of deepening the Buffalo River
entrance and Buffalo River and Ship Canal to 22 feet in earth and
23 feet in rock; and completion of deepening of the 25-foot project
area in the southerly part of the outer harbor; and the remainder
of the 23-foot outer harbor area; all to project depths.
   The total costs of the existing project were $10,087,179, of
which $5,353,034 including $655,500 public works funds, was for
new work, and $4,734,145 for maintenance. In addition, $390,000
was expended from contributed funds for maintenance.
                                            Cost and financialsummary

                                                      Fiscal year ending June 30                   Total to June
                                                                                          _ __    30, 1954, includ-
                                                                                                  ing fiscal years
                                     1950       i   1951         1952        1953      1954        prior to 19501


New work:
   Appropriated-_-
                 .....-             $550, 000           000
                                                    $900,                      ------------
                                                                 $80,000 $658,000                      $9,638,554
                 ------
    Cost....-------                  560,164        463,163      489,558     127,913   $585,243          9,630,620
Maintenance:
   Appropriated---..--.              208,800        250,000      236,000     287,000   298,040         26,630, 318
   Cost ..----.....-------.......    171,867        211, 843     319, 287    304,077   291,580          6617,792

1 Includes $4,277,586 for new work and $1,883,647 for maintenance for previous projects.
2 In addition $390,000 for maintenance was expended from contributed funds.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954--__---------             $955
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955----------------------------------------------                        955
    Estimated additional amount needed to be appropriated for com-
pletion of existing project               --------------------------------- 12,504,000

  11. BLACK ROCK CHANNEL AND TONAWANDA HARBOR, N. Y.
   Location. This improvement is essentially that of the upper
131/2 miles of the Niagara River from its head at Lake Erie, Buf-
falo, N. Y., to and including Tonawanda Harbor, N. Y. It com-
prises the improvements formerly designated by three titles; viz,
Lake Erie entrance to Black Rock Harbor and Erie Basin, N. Y.,
Black Rock Harbor and Channel, N. Y., and Tonawanda Harbor
and Niagara River, N. Y. (See U. S. Lake Survey Chart No. 312.)
   Previous projects. Lake Erie section, none. The original proj-
ect for Black Rock Harbor and Channel was adopted by the River
and Harbor Act of March 2, 1829. The original project for Tona-
wanda Harbor and Niagara River was adopted by the River and
1212     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Harbor Act of March 3, 1881. For further details, see items 5
and 7, page 1970 of Annual Report for 1915, and page 1612 of
Annual Report for 1938.
   Existing project. This provides for a channel 21 feet deep from
Buffalo Harbor, north entrance channel, to opposite Sixth Avenue,
North Tonawanda, total length 131/2 miles, as follows: From Buf-
falo north entrance channel to the foot of Maryland Street, Buffalo,
a distance of about 4,200 feet, about 1,000 to 500 feet wide, with
a short branch channel leading to Erie Basin; thence 350 feet wide,
narrowing to 200 feet wide, 500 feet northwest; thence generally
200 feet wide through Black Rock Channel to the ship lock at the
foot of Bridge Street, a distance of 3.3 miles, widening at the curve
opposite the foot of Porter Avenue and at the angle immediately
south of the International Bridge. From the lock the channel is
400 feet wide in the Niagara River to the natural deepwater pool
at the upstream end of Rattlesnake Island, a distance of 3.4 miles;
thence through natural deepwater to the downstream end of the
deepwater pool at the Tonawanda waterworks intake crib, a dis-
tance of about 4.7 miles, widened to 500 feet opposite the Colorado
Iron & Fuel Corp.'s plant, by the removal of 200 feet of the west-
erly end of Rattlesnake Island Shoal; thence 400 feet wide to the
foot of Tonawanda Island opposite Second Avenue, North Tona-
wanda, a distance of 5,000 feet, ending in a turning basin about
1,230 feet long and 1,250 feet wide extending to a point opposite
Sixth Avenue.
   The project also provides for the removal of rock shoals from
the Lake Erie entrance to the canal, and in the canal south of
Ferry Street Bridge, to a depth of 22 feet; for a channel 16 feet
deep, 6,800 feet long, and generally 400 feet wide in Tonawanda
inner harbor; for a channel 16 feet deep, 1,400 feet long, and gen-
erally 180 feet wide in Tonawanda Creek; for a ship lock at Bridge
Street, Buffalo; for a bridge over the canal at Ferry Street, Buf-
falo; for the repair and 800-foot extension of Bird Island pier; for
the improvement and extension of the guide pier; and for the re-
pair of the towpath wall.
   The project depth in the canal is referred to low water datum
in Lake Erie, evelation 570.5 feet above mean tide at New York.
The project depth in the river is referred to the river surface when
Lake Erie is at low water datum. Ordinary fluctuations of water
level above the lock are from 3.5 feet above to 0.5 foot below low
water datum, and extreme fluctuations produced by winds and
other causes, are about 9 feet above to 31/ feet below that plane.
River fluctuations gradually decrease to about 70 percent of fluc-
tuations above the lock when they reach North Tonawanda.
   The estimate of cost for new work is $11,300,000 (1954), ex-
clusive of amounts expended on previous projects. The estimate
for annual cost of maintenance is $300,000 (1954) including $200,-
000 for operation and care.
                    RIVERS AND HARBORS-BUFFALO, N. Y., DISTRICT                                                         1213
                                         Descriptionof Black Rock lock
Location: Foot of Bridge St., Buffalo, N. Y. (in city limits).
Dimensions:
   Length between miter sills-----------------------------------------.feet-                                               650
   Available length for full width-----------------------------------------............do__                                625
   Width in clear (between fenders) ------            -----------------      ---------------------
                                                                                        ......            do -              68
   Depth on miter sills at low water------------------------                     .------ ---............  do_.              21.6
   Lift------                                     --------------------------   .---------------------
                                                                                     -------------     .. do                 5
Foundation (lock): Bedrock.
Dam: Fixed.
Type of construction:
   Lock: Concrete walls; steel mitering gates.
   Dam: The dam consists of Squaw Island dike and Bird Island pier lying between the
      canal and Niagara River. The pier was built of timber cribs filled with stone in 1822-
      34, chiefly by State of New York. Cost is unknown.
Cost of lock ..       -------------------------------------------------------------                  $1, 037, 213.20
Approach walls and office storehouse___ __________                       __--___--_______________- - -526,842.53
       Total            -------------------------------------               -------------------------               1,564,055.73

The existing project was authorized by the following River and
Harbor Acts:
      Acts                              Work authorized                                                 Documents

                                                                                         H.
                                                                            Ex. Doe. 83, 50th Cong., 1st
Aug. 1    888Dredging channel through Horseshoe Reef at outlet            sess., Annual Report, 1888, p.
Aug. 11, 1896  of Lake Erie and Tonawanda Inner Harbor, to 16             2066, and Annual Report, 1897,
               feet.                                                     pp. 3116-3120.
June 13, 1902 Deepening Tonawanda Creek to 16 feet-----.... -          H. Doc. 143, 56th Cong., 1st sess.,
                                                                          and Annual Report, 1900, p. 4152.
June 13, 1902 \Dredging channel from Buffalo outer harbor to foot fH. Doc. 125, 56th Cong., 2d sess.,
Aug.: 8, 1917J of Maryland St. Buffalo, to 21 feet.                       and Annual Report, 1901, p. 3343.
Maxr, 3, 1905 Dredging channel from foot of Maryland St., Buf- H. Doc. 428, 58th Cong., 2d sess.
                   falo, to natural deep-water pool upstream from
                   Tonawanda Harbor to 21 feet; construction of ship
                   lock and bridge; and repair of Bird Island pier and
                   towpath wall.
July 27, 1916 Dredging channel :along Tonawanda Island, with H. Doc. 658, 63d Cong., 2d sess.
                   turning basin at its downstream end at the foot of
                   the Island, to 21i:feet.
Mar. 2, 1919 Dredging triangular area at junction with Buffalo         H. Doc. 1004, 65th Cong., 2d sess.,
Mar.: ;2, 1945f north entrance channel.                                   and H. Doc. 92, 79th Cong., 1st
                           '                •'sess.
Sept. 22, 1922 Widening channel at foot of Maryland St., Buffalo..__   H. Doc. 981, 66th Cong., 3d sess.
Mar. 3,:1925 'Wide ing canal south of International        Bridge  and H.  Doc. 289, 68th Cong., 1st sess.
                  rqmoval of westerly end of Rattlesnake Island
                  .Shoal.
June 26,'19341 -    eOperationand care of improvements provided for
                   with funds from War Department appropriations
                  for rivers and harbors.                                                                3
Aug. 30, 1935 2 Removal of rock shoals in Lake Erie entrance to        H. Doc. 28, 73d Cong., 1st sess.
                 -canal, and in canal south of Ferry St. Bridge, to 22
                  feet; enlargement of, North Tonawanda turning
                  basin; extension of Bird Island pier; improvement
                  of guide pier at the lock; and eliminatioin
                   150 feet of Tonawanda Creek channel from the
                                                                upper  of
                  project.
Mar. 2, 1945     Widening Lake Erie entrance to canal------------      H. Doc. 92, 79th Cong., 1st sess.3

  1Permanent Appropriations Repeal Act.
  2 Authorized May 28, 1935, by Emergency Relief Administration Act of 1935.
  3 Contains latest published map.

   Recommended modification of project. Modification of the ex-
isting project to provide for deepening of the lower 1,500 feet of
Tonawanda Inner Harbor and minor enlargement of the turning
basin, all to a depth of 21 feet below low water datum at an esti-
mated cost of $270,000 for construction and $3,000 annually for
maintenance in addition to that now required, have been recom-
mended in the report as transmitted by the Secretary of the Army
to Congress on May 28, 1954.
1214      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

    Local cooperation. Fully complied with.
    Terminal facilities. There are no freight terminals along the
channel above the Black Rock lock.
    Along the upstream end of the channel there are 2 small boat
harbors, 1 unused seaplane terminal, 1 Naval Militia dock, 2 yacht
club docks, and several other privately owned servicing and stor-
age docks for recreational and other small craft, and 2 State-
owned barge canal terminals at Erie Basin.
    Below the Black Rock lock and at Tonawanda Harbor, there are
6 terminals for petroleum products, 2 for iron ore, stone, and pig
iron, 2 for coal, 1 for molasses, 4 for sand and gravel, 1 for lumber,
and 1 for pulpwood, all of which are private. There are also two
State-owned barge canal terminals at Tonawanda, N. Y. There are
seven marine service and supply docks for recreational and other
small craft. The Corps of Engineers owns a wharf adjacent to the
Black Rock lock, which is private. The facilities are considered
adequate for the existing commerce. (See Lake Series No. 1, re-
vised 1951, Corps of Engineers.)
    Operations and results during fiscal year. Government plant
and hired labor removed 19,791 cubic yards of material for res-
toration of project depths in Black Rock Channel and Tonawanda
Harbor at a cost of $18,359, removed obstructions from the chan-
nels at a cost of $10,986, repaired 216 linear feet of the towpath
wall at a cost of $12,746 and performed miscellaneous inspection
services at the project at a cost of $11,815.
    Operating and care; Black Rock Lock: The lock was in con-
tinuous operation 266 days. The lock was closed January 4
through April 13, 1954, inclusive. The signal station located on
the canal at the foot of West Genesee Street was in continuous
operation 266 days, and was not in operation December 23, 1953,
to April 1, 1954, inclusive. The Ferry Street Bridge was in con-
tinuous operation 279 days and in operation during the day only
for 70 days. The operating and care of the Ferry Street Bridge
was assumed by the city of Buffalo beginning October 1953. The
cost for the year was $180,000. Twelve thousand square feet of
the west wall of the lock chamber were resurfaced, by contract, at
a cost of $69,127. A study by hired labor, to consider replace-
ment or modernization of Black Rock Lock and appurtenant struc-
tures was continued at a cost of $476. The total, cost for the year
was $303,509 of which $249,603 was for operating and care, in-
cluding $69,127 for improvement and reconstruction and $53,906
for maintenance.
    Condition at end of fiscal year. The existing project is about 92
percent complete. The channel from Buffalo Harbor north en-
trance to opposite Sixth Avenue, North Tonawanda, is complete.
The different sections of this channel were completed to project
depth as follows: Lake Erie section in 1909; Black Rock Canal
section in 1915; Niagara River section from lock to deepwater pool
above Tonawanda, in 1913; and Tonawanda section, including
turning basin, 1921. The channel was further widened as follows:
The triangular area at Lake Erie entrance to the canal was com-
             RIVERS AND HARBORS--BUFFALO, N. Y., DISTRICT       1215
pleted in 1922 and transferred from Buffalo Harbor project in
1945; Lake Erie section was widened at the bend opposite foot of
Georgia Street, Buffalo, in 1924; Black Rock Canal section, just
south of the International Bridge at Buffalo, in 1928, and opposite
the foot of Maryland Street, Buffalo, in 1930; and Niagara River
section in the vicinity of the westerly end of the Rattlesnake Island
shoal in 1928. Rock shoals extending above a depth of 21.4 feet
were removed from the Lake Erie entrance to the canal and in the
canal south of Ferry Street Bridge, in 1937. Rock shoals extend-
ing above a depth of 22 feet were removed from the Lake Erie en-
trance to the canal, in Black Rock Canal, and in the Niagara River
portion of the canal in 1948-1949.
    The Tonawanda Creek channel was completed in 1902. Tona-
wanda inner harbor channel was completed in 1904. The enlarge-
ment of the Tonawanda turning basin and the extension of Bird
Island pier, were completed in 1936. The lock, including wing
walls and retaining walls above the lock, was completed in 1914,
and the 100-foot east wing wall extension in 1927. The guide pier
connecting with the west lower wing wall was completed in 1916,
except for the 200-foot northerly extension and construction of
concrete platform in the angle. The upstream 100 linear feet of
the lower West Guide Pier were repaired during 1951. The bridge
at Ferry Street, operated and maintained by the City of Buffalo,
was completed in 1914, and the lock-operating houses in 1924.
    The work remaining to be done to complete the project consists
of the improvements and extension of the guide pier, as authorized
by the River and Harbor Act of August 30, 1935, and widening
the Lake Erie entrance to the canal.
    All structures are in poor condition. Both the towpath wall and
Bird Island pier are badly deteriorated and require considerable
annual maintenance. Several sections of the towpath wall fail
yearly, requiring removal of stone and debris from the channel
and repair of the structure. The operating equipment and controls
for the Black Rock lock are antiquated and inefficient. The east
channel face of the lock wall was repaired in 1953, and the west
channel face in 1954. The upper wing wall of the lock has shifted
laterally approximately 2 feet at the maximum point, and the con-
crete superstructure on the lower wing wall is badly cracked indi-
cating a possible failure of the timber-crib.
   The controlling depths at low water datum are Black Rock chan-
nel 21 feet, 20 feet in the Niagara River section of the channel
and in the Tonawanda turning basin, Tonawanda inner harbor
14 feet, and Tonawanda Creek channel, 12 feet.
    The costs of the existing project were $14,989,704, of which
$10,066,019, including $1,764,922 Emergency Relief funds was for
new work, $1,847,003 for maintenance, and $3,076,682 for oper-
ating and care. In addition, the sum of $1,356,007 was expended
between July 9, 1914, and June 30, 1935, on the operation and care
of the works of improvement under the provisions of the perma-
nent indefinite appropriation for such purposes.


     Sig 39--1215.1246
1216           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                     Cost and financial summary

                                            Fiscal year ending June 30                        Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                              1950         1951        1952            1953        1954        priorto 1950

New work:                                                         {
   Appropriated------------------        -$26, 201   i                                             10, 119, 125
                                                                                                  $__,,
   Cost .......---------------.. $ 106 -   , 0       ._   ,                        3---10          10,119,125
Maintenance:
   Appropriated-......-.      457,200      333,000    $233, 000       $315, 000   $310, 000        s 6,294, 122
   Cost ------------          367,515      375,018     255,926         346,145     303,509           6, 284,614

1 Includes $58,027 for new work for previous projects.
2 Includes $4,921.94 of emergency relief authority administrative costs transferred from new work to
maintenance upon conversion to programming and budgeting system July 1, 1953, by direction of Office,
Chief of Engineers.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project__          ____    _    $----------1,238,900

                                12. NIAGARA RIVER, N. Y.

   Location. This improvement covers that portion of the Niagara
River from Tonawanda Harbor, N. Y., to Niagara Falls, N. Y., a
distance of 71/2 miles, and compensating works near the head of
the river. The downstream limit of the improvement is about 16
miles from the mouth of the river at Lake Ontario. (See U. S.
Lake Survey Chart No. 312.)
   Previous projects. Adopted by River and Harbor Acts of July
13, 1892, August 18, 1894, and June 25, 1910. For further details,
see page 1970 of Annual Report for 1915, and page 1619 of Annual
Report for 1938.
   Existing project. This provides for a channel 12 feet deep and
300 feet wide in the east channel from the downstream end of the
existing 21-foot channel opposite Sixth Avenue, North Tonawanda,
to the upstream end of the 12.7-foot channel near the Niagara
Falls waterworks intake crib; and for a channel 12.7 feet deep and
from 300 to 400 feet wide from the Navy Island channel (natural)
to the foot of Hyde Park Boulevard (formerly called Sugar Street);
Niagara Falls; N. Y.
   The project also provides for the construction of compensating
works just above the contracted section of the river at Fort Erie,
this work forming a part of the project for deeper channels in the
connecting waters of the Great Lakes.
   The project depths are referred to the river surface when Lake
Erie is at low water datum, elevation 570.5 feet above mean tide
at New York. Ordinary fluctuations of water level are from 3
feet above to low water datum, and extreme fluctuations, produced
by wind and other causes, are from 51/2 feet above to 11/2 feet be-
low that plane.
   The estimate of cost for new work is $3,350,000 (1954) includ-
ing $2,887,000 for compensating works, but is exclusive of $27,563
contributed by local interests and amounts expended on previous
projects..
   The estimate of cost of annual maintenance is $9,000 (1954).
   The existing project was authorized by the following River and
Harbor Acts:
                    RIVERS AND HARBORS-BUFFALO, N. Y., DISTRICT                                            1217

       Acts                           Work authorized                                    Documents

July 25, 1912      Dredging channel from the Navy Island natural H. Doc. 549, 62d Cong., 2d sess.
                    channel to the Niagara Falls waterworks channel,
                    and deepening the last-named channel to the foot
                    of Hyde Park Blvd. all to depth of 12.7 feet.
July     3, 1930   Deepening channel from North Tonawanda to the H. Doc. No. 289, 71st Cong., 2d
                    Niagara Falls waterworks intake crib, to 12 feet.      sess.'                          1
      Do.....      Construction of compensating works     .-------------- . Doc. 253, 70th Cong., 1st sess.

     1 Contain latest published maps.

    Local cooperation. Fully complied with.
    Terminal facilities. There is one terminal, which is occupied
by a builder's supply company, whose facilities are open to ship-
pers of commodities for which the facilities are suited. These fa-
cilities are considered adequate for the small amount of existing
commerce. Two yacht club docks and several other privately
owned servicing and storage docks are for recreational and other
small craft.
    Operations and results during fiscal year. Government plant
and hired labor removed obstructions from the project channels
and performed miscellaneous inspection services at the project at
a cost of $8,593 for the year for maintenance.
    Condition at end of fiscal year. The existing project is about 40
percent complete. The east channel from North Tonawanda to the
Niagara Falls waterworks intake and Schlossers Channel from
Niagara Falls waterworks intake to the foot of Hyde Park Boule-
vard, were completed in 1934. The work remaining to be done is
the construction of the compensating works just above the con-
tracted section of the river at Fort Erie. The controlling depth in
the channels is 11.4 feet at low water datum.
   The total costs of the existing project were $549,894, of which
$463,387, including $94,512 public works funds, was for new work
and $86,507 for maintenance. In addition, $27,563 was expended
from contributed funds for new work.

                                        Cost and financial summary

                                                   Fiscal year ending June 30                      Total to June
                                                                                                  30, 1954, includ-
                                                                                                  ing fiscal years
                                 1950            1951           1952       1953         1954        priorto 1950

New work:
   Appropriated- ......                                         ----                                   1 2 $531, 894
     Cost .----------       -------- ---------------       --   ------------------------------          12 531,894
Maintenance:
     Appropriated------.. -      $14, 500      $72 -                        $6, 000     $9, 042             87,115
     Cost-----------------        14,572......                               5,841       8, 593             86,507

1 Includes $68,507 for new work for previous projects.
2   In addition $27,563 for new work was expended from contributed funds.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project__________________________ $2,886,600

                        13. NIAGARA REMEDIAL WORKS, N. Y.
  Location. The improvement is located in the Niagara River
adjacent to the cities of Niagara Falls, N. Y., and Niagara Falls,
1218         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Ontario, Canada. (See U. S. Lake Survey Charts Nos. 312 and 31.)
   Previous project. Authorized by Senate executive resolution
dated November 27, 1941, ratifying Executive G, 77th Congress.
For further details, see pages 2189 and 2190 of the Annual Report
for 1949.
   Existing project. The plan of improvement provides for the
following: (1) Chippawa-Grass Island Pool Control Structure ex-
tending 1,550 feet from the Canadian shore out into the Niagara
River parallel to the existing submerged weir and about 300 feet
downstream therefrom. With the exception of an approach fill
adjacent to the Canadian shore, the structure will consist entirely
of piers and 13 movable control gates; (2) excavation in the
Horseshoe Cascades lying immediately upstream from the Cana-
dian flank of the Horseshoe Falls and a crest fill on that flank
about 100 feet long; (3) excavation in the Horseshoe Cascades
lying immediately upstream from the Goat Island flank of the
Horseshoe Falls and a crest fill on that flank about 300 feet long.
Construction of the Chippawa-Grass Island Pool control structure
and excavation in the Horseshoe Cascades on the Canadian flank
will be accomplished by the government of Canada. Excavation
in the Horseshoe Cascades on the Goat Island flank will be ac-
complished by the Government of the United States.
   The estimate of cost for new work is $17,100,000 (1954), ex-
clusive of amounts expended on previous projects. In accordance
with Article II of 1950 Treaty, costs will be divided equally be-
tween the Governments of United States and Canada. The annual
cost for operation and maintenance is estimated to be $100,000
 (1952).
   The existing project was authorized by a treaty concerning the
uses of the waters of the Niagara River between the United States
and Canada as signed at Washington, D. C., on February 27, 1950,
approved by the Canadian Parliament on June 14, 1950, consented
to by  theU. S. Senate on August 9, 1950, and put into force by an
exchange of ratifications at Ottawa on October 10, 1950.
   By letter dated July 14, 1953 from the Secretary of State to the
Secretary of the Army, the Department of the Army was desig-
nated as the agency of the United States to perform its obligations
with respect to planning, supervision and construction of the
remedial works, to obtain the appropriation of funds necessary to
carry on the work connected with the whole project, and to dis-
burse such funds in connection with the performance of the work.
By letter dated July 28, 1953, the Secretary of the Army accepted
the arrangements and designated the Chief of Engineers to super-
vise the necessary planning and construction.
   Local cooperation. None required.
   Operations and results during fiscal year. (1) Canadian opera-
tions: construction of control structure was initiated during
September 1953 by the Ontario Hydro-Electric Power Commission.
Vouchers from Canada in the amount of $798,565 were received
during the year for reimbursement by the United States; (2)
United States operations: plans and specifications for the work
proposed on the United States flank of Horseshoe Falls were com-
pleted. Engineering studies in connection with the project and
                     RIVERS AND HARBORS-BUFFALO, N. Y., DISTRICT                                                               1219
review of plans and specifications for work being performed by
Canada were initiated. Construction by contract for excavation
and crest fill on United States flank of Horseshoe Falls, were in-
itiated during September 1953. Costs for the year were $115,235.
   The total cost for the year to the United States was $913,800.
   Condition at end of fiscal year. Construction of the control
structure by Canada was 10 percent complete. Construction on
United States flank of Horseshoe Falls was 10 percent complete.
   The work remaining to be done consists of completion of con-
struction work currently underway; excavation and crest fill on
the Canadian flank of Horseshoe Falls and purchase and installa-
tion of water level stage recording equipment. The total cost of the
existing project at the end of this fiscal year is $913,800, all for
new work.
                                                Cost and financial summary

                                                           Fiscal year ending June 30                               Total to June
                                                                                                                    30,1954; includ-
                                                                                                                    ing fiscal years
                                       1950              1951               1952              1953       1954         priorto 1950


New work:
   Appropriated-----.......---
     Cost------------.......... ...
                                         ------------
                                      -------
                                                              -
                                                  ---------------..--------------
                                                                                       -----------
                                                                                               ----
                                                                                                      $1, 500,000
                                                                                                         913,800
                                                                                                                        1   $1, 863,864
                                                                                                                            1 1,277, 644
Maintenance:
   Appropriated........-------------             -----------------------------------------------                               212377
    Cost---------------------                    ----------------------------------------------                                  12,377

  1 Includes $363,864 cost for Submerged Weir, Niagara River, N. Y.
  2 Costs incurred for maintenance of Submerged Weir, Niagara River, N. Y.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-_-----------      $37,204
    Appropriated for succeeding fiscal year ending June 30, 1955          2,000,000                      -------
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955       --------------------------------------- ---          2,037,204
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project---------     -----------      ---------    5,050,000

                    14. ROCHESTER (CHARLOTTE)                                               HARBOR, N. Y.
   Location. On the south shore of Lake Ontario, at the mouth of
the Genesee River, 59 miles westerly from Oswego, N. Y. (See
U. S. Lake Survey Charts Nos. 2 and 238.)
   Previous projects. Adopted by River and Harbor Acts of
March 2, 1829, August 2, 1882, and by authority of the Chief of
Engineers on July 18, 1896, and March 2, 1897. For further de-
tails, see page 1971 of Annual Report for 1915, and page 1623 of
Annual Report for 1938.
   Existing project. This provides for a channel from deep water
in the lake to New York Central Railroad bridge near the mouth
of the river on an alinement centrally located with respect to the
entrance piers, and with a width of 300 feet lakeward of the pier-
heads and 200 feet shoreward of the pierheads, and a depth of 20
feet, and for a turning basin of the same depth, 600 feet in width,
opposite the municipal terminal; thence for maintenance of a chan-
nel 20 feet deep and approximately 150 feet wide to a point 200
feet upstream from the Genesee docks, without dredging closer
than 50 feet to existing bulkheads; and for parallel piers of the
1220             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

timber-crib type with concrete superstructure, about 450 feet
apart, from the lake to the pool at the mouth of the Genesee River,
the west pier to be 3,036 feet long and the east pier 2,699 feet long.
   The project depth is referred to low water datum for Lake On-
tario, elevation 244 feet above mean tide at New York. Ordinary
fluctuations of water surface are from 4 feet above to 0.5 foot be-
low water datum, and fluctuations due to winds are small.
   The cost of new work for the completed project was $78,614, ex-
clusive of amounts expended on previous projects. The estimate
for annual cost of maintenance is $90,000 (1954).
   The existing project was authorized by the following River and
Harbor Acts:
    Acts                            Work authorized                                     Documents

Mar. 2, 1829     Construction of piers 1-..............----------..----      Annual Report, 1874, p. 247.
Aug. 2, 1882     Extension of piers to 15-foot contour in the lake 1----..... Annual Report, 1881, p. 2437.

June 25, 1910
                 Concrete superstructure on piers 1,.....--    -   --     -..Annual Report, 1905, p. 2393.
                 Deepening channel to 20 feet--------------------....H. Doc. 342, 61st Cong., 2d sess. 3
Aug. 30,1935 2   Dredging of the entrance channel and turning basin, H. Doc. 484, 72d Cong., 2d sess.
                  and the elimination of the inner ends of the east
                  and west piers, all to present project dimensions.                                              s
Mar. 2, 1945     Maintenance of the existing channel upstream of the         H. Doc. 139, 76th Cong., 1st sess.
                  New York Central RR. bridge.

1Completed under previous projects.
2 Authorized May 28, 1935, by Emergency Relief Appropriation Act of 1935.
3Contains latest published map.
   Local cooperation. Fully complied with.
   Terminal facilities. There is 1 coal terminal, 1 inactive car-
ferry terminal, and 1 municipal passenger and miscellaneous
freight terminal, all open to the public. Two yacht club docks, and
several other privately owned servicing and storage docks, are for
recreational and other small craft. These facilities are considered
adequate for the existing commerce.
   Operations and results during fiscal year. Government plant
and hired labor removed 308,549 cubic yards of material for res-
toration of project depths in the channels and turning basin at a
cost of $80,137 and performed miscellaneous inspection services at
the project at a cost of $12,371. Rebuilding of 550 linear feet of
the east pier, by contract, was commenced at a cost of $112,015.
The total cost for maintenance for the year was $204,523.
   Condition at end of fiscal year. The existing project was com-
pleted in 1935 at a cost of $78,614. A length of 1,265 linear feet
of the west pier has been reinforced and repaired with steel sheet
piling and concrete. An additional 1,080 feet of the west pier and
the lakeward 700 feet of the east pier crib and superstructure are
failing, the crib filling stone has escaped and the concrete is badly
cracked. Repairs to 550 linear feet of the east pier were com-
menced in 1954. The present channel was completed in 1935. The
channel is unstable and requires annual dredging to maintain proj-
ect depth. The controlling depth in the river channel and the turn-
ing basin is 20 feet at low water datum.
                  RIVERS AND HARBORS--BUFFALO, N. Y., DISTRICT                                         1221
  The total costs of the existing project were $1,622,760, of which
$78,614 was for new work and $1,544,146 for maintenance. These
costs include Emergency Relief funds in the amount of $57,284, of
which $56,806 was for new work and $478 for maintenance.
                                          Cost and financial summary

                                                Fiscal year ending June 30                     Total to June
                               ....                                            _     _         30, 1954, includ-
                                                                                               ing fiscal years
                                   1950        1951        1952         1953         1954      prior to 19501.2


New work:
   Appropriated..          -----------
                           .....       ------------.
                                              .      ------------ ----------------------           :-$ 326,408
   Cost------..                        --------------------------
                               .....---..                                                              326,408
Maintenance:
   Appropriated --...---          $ 69,339     $54, 000    $54, 500   $144,000     $267, 378         2,298, 657
   Cost                            114,154      56,802      61,506      72,656      204,523          2,161, 675


I Includes $247,794 for new work and $617,529 for maintenance for previous projects.
2 Includes $478 of emergency relief authority administrative costs transferred from new work to main-
tenance upon conversion to Programming and Budgeting System July 1, 1953 by direction of Office, Chief
of Engineers.

                       15. GREAT SODUS BAY HARBOR,                             N. Y.
    Location. On Sodus Bay, which is a nearly landlocked indenta-
tion of the south shore of Lake Ontario, 29 miles westerly from
Oswego, N. Y. (See U. S. Lake Survey Chart No. 234.)
    Previous projects. Adopted by River and Harbor Acts of
March 2, 1829, and June 23, 1866. For further details, see page
1972 of Annual Report for 1915, and page 1626 of Annual Report
for 1938.
    Existing project. This provides for an entrance channel paral-
lel to the entrance piers, extending from deep water in the lake to
deep water in the bay, 22 feet deep and 300 feet wide to just lake-
ward of the pierheads, thence narrowing to 200-foot width with
20-foot depth between the piers, widening to 300-foot width with
20-foot depth to deep water in Great Sodus Bay; for parallel piers,
450 feet apart, of timber-cribs with concrete superstructure, the
west pier 1,580 feet long and the east pier 1,294 feet long; for an
east breakwater, 1,653 feet long, of timber-cribs with concrete su-
perstructure, extending from the inner end of the east pier to
Charles Point; and for a west breakwater, 2,200 feet long, of stone-
filled timber-cribs, extending from the inner end of the west pier to
Sodus Point, not maintained.
    The project depth is referred to low water datum for Lake On-
tario, elevation 244 feet above mean tide at New York. Ordinary
fluctuations of water surface are from 4 feet above to 0.5 foot be-
low low water datum, and fluctuations due to wind are small.
    The cost of new work for the completed project was $249,187,
exclusive of amounts expended on previous projects. The estimate
for annual cost of maintenance is $20,000 (1954).
    The existing project was authorized by the following River and
Harbor Acts:
1222               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


       Acts                            Work authorized                                                      Documents

Mar. 2, 1829       Construction of piers and breakwater 1...------------                    Annual Report, 1876, pt. II, p. 589.
Aug. 2, 1882       Extension of piers to 15-foot contour in the lake......                  Annual Report, 1881, p. 2442.
Mar. 3,1925        Deepening and widening of channel to 18-foot depth                       H. Doc. 192, 68th Cong., 1st sess.'
                    and 150-foot width.
July     3, 1930   Widening channel lakeward of the piers to 250 feet ...                   Rivers and Harbors Committee
                                                                                              Doc. 17, 70th Cong., 1st sess.
Aug. 30 1935       Dredging channel to present project dimensions-_....                     Rivers and Harbors Committee    s
                                                                                              Doc. 23, 72d Cong., 1st sess.

  1 Completed under previous projects.
  2   Contains latest published maps.

   Local cooperation. Fully complied with.
   Terminal facilities. There is one coal terminal which is open to
shippers of coal, one fish dock which is private, and one passenger
tour boat dock. A yacht club dock and several other privately
owned servicing and storage docks are for recreational and other
small craft. These terminals are considered adequate for the ex-
isting commerce.
   Operations and results during fiscal year. Government plant
and hired labor removed 15,695 cubic yards of material for the res-
toration of project depths in the channel at a cost of $11,804 and
performed miscellaneous inspection services at the project at a
cost of $5,254. The total cost of maintenance for the year was
$17,058.
   Condition at end of fiscal year. The existing project was com-
pleted in 1940 at a cost of $249,187. The piers are generally in poor
condition. In a 450-foot section of the east pier and a 900-foot
section of the west pier, the concrete superstructure is badly dis-
integrated and cracked. The controlling depths are 22 feet in the
entrance channel, and 20 feet in the channel between the piers.
   The total costs of the existing project were $960,084, of which
$249,187 was for new work, and $710,897 for maintenance.
                                           Cost and financial summary

                                                         Fiscal year ending June 30                                   Total to June
                                                                                                                      30, 1954, includ-
                                                                                                                      ing fiscal years
                                   1950             1951             1952              1953                1954         priorto 1950

New work:
       Appropriated     _                                                   ..... -$610,-       - -.----                    '..       959
   Cost .         -           ..   .   .   .   ..    .    .   .    ..-                                                        ':-610, 959
Maintenance:
   Appropriated                    $13, 500         $10, 500 1      -$2, 500          $13, 300             $17,020             712, 037
   Cost .............   -.           10, 939          9,842            2, 205          12,245               17, 058            710, 897


      Includes $361,772 for new work for previous projects.

                                   16. OSWEGO                     HARBOR,            N. Y.
   Location. On the south shore of Lake Ontario, at the mouth of
the Oswego River, 59 miles easterly from Rochester, N. Y. (See
U. S. Lake Survey Chart No. 225.)
   Previous projects. Adopted by the River and Harbor Acts of
March 2, 1827, March 2, 1831, June 23, 1866, July 25, 1868, July
11, 1870, March 3, 1881, September 19, 1890, the Sundry Civil Act
of March 3, 1893, and River and Harbor Acts of August 18, 1894,
                RIVERS AND HARBORS-,-BUFFALO,                           N. Y., DISTRICT               1223

June 3, 1896, March 2, 1907, and March 2, 1919. For further de-
tails, see page 1973 of Annual Report for 1915, and page 163Q of
Annual Report for 1938.
    Existing project. This provides for the following:
   a. An outer harbor, about 280 acres in area, formed by a system
of breakwaters comprising an outer west breakwater 4,478 feet
long connected with the shore, consisting of 4,359 feet of stone-
filled timber cribs with concrete superstructure and 119 feet of
rubble-mound construction; a west arrowhead rubble-mound break-
water 2,700 feet long; an east arrowhead rubble-mound breakwater
about 1,180 feet long; an'd an outer east rubble-mound breakwater
about 4,900 feet long, connected with the shore.
    b. A depth of 21 feet in soft material and 22 feet in hard mate-
rial in the west outer harbor west of the east side of the Lacka-
wanna coal dock; a depth of 21 feet in the outer harbor between
the arrowhead breakwaters, in the west outer harbor east of the
Lackawanna coal dock, and between the harbor lines in the Oswego
River north of the north line of Seneca Street; no dredging to be
done within 100 feet of the breakwaters nor within 50 feet of the
established harbor lines, except in the river.
    c. A channel 250 feet wide in the east outer harbor, and an ir-
regular shaped basin at the easterly end, with depths of 18 feet in
soft material and 19 feet in hard material.
    d. Maintenance of 145 feet of the west inner breakwater.
    The project depths are referred to low water datum for Lake
Ontario, elevation 244 feet above mean tide at New York. Ordi-
nary fluctuations of water surface are from 4 feet above to 0.5 foot
below low water datum, and fluctuations due to wind are small.
    The estimate of cost for new work is $17,917,000 (1954). The
estimate for annual cost of maintenance is $62,700 (1954).
    The existing project was authorized by the following River and
Harbor Acts:
    Acts                          Work authorized                                    Documents

July 11, 1870   Construction of outer west breakwater 1....--------      Annual Report 1870, pp. 54, 220,
                                                                           and 221.
Mar. 2, 1907    Repair of outer west breakwater under plan (A) '....     H. Doc. 55, 58th Cong., 2d sees.
July 3, 1930    Construction of arrowhead breakwaters; deepening         Rivers and Harbors Committee
                 outer harbor between the arrowhead breakwaters,           Doc. 24, 71st Cong., 2d sess.
                 the west outer harbor east of Delaware, Lacka-
                 wanna & Western coal dock, and Oswego River
                 north of Seneca St., to 21 feet; and deepening west
                 outer harbor, west of Delaware, Lackawanna &
                  Western coal dock, to 16 feet.
Aug. 30, 1935   Widening of channel to harbor lines in Oswego River      Rivers and Harbors Committee
                 north of Seneca St.                                       Doc. 7, 74th Cong., 1st sess.'
Oct. 17, 1940   Closing the gap in the west breakwater; deepening        H. Doc. 96, 76th Cong., 1st sess.'
                  the west outer harbor, west of the east line of the
                  Lackawanna coal dock, to project depth.                                                     2
June 30, 1948   Construction of east outer breakwater; removal of        H. Doc. 722, 80th Cong., 2d sess.
                 inner end of east arrowhead breakwater; and
                 dredging channel and basin in east outer harbor.

  1 Completed under previous projects.
2 Contains latest published map.

   Recommended modifications of project. Modifications of the ex-
isting project to provide for a detached breakwater 850 feet long
at the harbor entrance, and the removal of shoals to a depth of 25
feet below low water datum in the approach to the entrance, all at
1224     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

an estimated cost of $1,811,000 for construction and $5,000 an-
nually for maintenance in addition to that now required, have been
recommended in House Document No. 487, 81st Congress, 2nd
session,
   Local cooperation. The act of June 30, 1948, provides for con-
struction of the east outer harbor, provided local interests give
assurances satisfactory to the Secretary of the Army that they will
provide without cost to the United States all necessary lands, ease-
ments, and rights-of-way necessary for construction of the project
and subsequent maintenance, as and when required; hold and save
the United States free from damage due to the construction and
subsequent maintenance of the project; construct a wharf about
1,300 feet long, including the necessary extension of the water in-
take line, in accordance with plans approved by the Chief of Engi-
neers, and construct handling and storage facilities of such design
and capacity as to insure expeditious handling and adequate stor-
age for the wood pulp required by paper mills in the vicinity, and
for prospective commerce in soybeans; dredge and maintain the
area between the project limit and wharf face to project depth; and
agree to receive, handle and store, at reasonable and equal terms to
all, the wood pulp requirements of paper mills in the vicinity. As-
surances of local cooperation were furnished and submitted for
approval. The assurances were returned without action because
they were not in strict accordance with the requirements. Nego-
tiations are in progress to obtain the revised assurances. All prior
conditions have been complied with.
   Terminal facilities. One coal terminal and two State-owned
terminals for grain and barge canal traffic are open to the public.
Two terminals for coal, 1 for cement, 1 for woodpulp, and 1 for
fish are private. One dock owned by the State naval militia and
one by the city of Oswego are used by recreational craft. The
facilities are considered adequate for the existing commerce.
   Operations and results during fiscal year. Government plant
and hired labor removed 65,669 cubic yards of material for res-
toration of project depths in the outer harbor at a cost of $15,536;
made repairs to the west breakwater at a cost of $40,513; and per-
formed miscellaneous inspection services at the project at a cost
of $7,167. The total cost of maintenance for the year was $63,216.
   Conditionat end of fiscal year. The existing project is about 30
percent complete. The west outer breakwater was completed in
1882, and was originally 6,032 feet long with a 119-foot gap near
the westerly end, but was reduced to 4,359 feet in 1931, and the
gap was closed in 1942. The west arrowhead breakwater was com-
pleted in 1931, and the east arrowhead breakwater in 1932. The
old lighthouse pier, a part of the west inner breakwater, and the
upper and lower islands in Oswego River, were removed in 1931.
A depth of 21 feet was obtained in Oswego River to within 50 feet
of the harbor line and in the outer harbor east of the Lackawanna
coal dock, except a strip about 200 feet wide along the harbor line
east of the mouth of the river, in 1932. The channel in Oswego
River was widened to the harbor lines in 1937. A channel, 16 feet
deep and 100 feet wide, with a turning basin at its westerly end,
was dredged in 1932 in the outer harbor west of the Lackawanna
               RIVERS AND HARBORS-BUFFALO, N. Y., DISTRICT                                                    1225
coal dock. The channel was widened to 250 feet and deepened to
21 feet below low water datum in 1948. The breakwaters are gen-
erally in fair condition except that the riprap protection along the
lake side of the old west breakwater for a length of approximately
1,000 feet has settled, and a 400-foot portion of the concrete section
has disintegrated and broken; slope stone in portions of the west
arrowhead breakwater has disintegrated and settled and the core
stone in a 1,500-foot section of the west breakwater has settled in
many places.
   A depth of 21 feet at low water datum is available in the Oswego
River to the north line of Seneca Street, and in the outer harbor
east of the Lackawanna coal dock, except in a 200-foot-wide strip
along the harbor line east of the mouth of the Oswego River which
has a controlling depth of 18 feet. The 250-foot channel in the
outer harbor west of the Lackawanna coal dock and the turning
basin have a controlling depth of 21 feet at low water datum.
   The work remaining to be done to complete the project is the
deepening of the 200-foot strip along the harbor line east of the
Oswego River, deepening the remainder of the outer harbor west
of the Lackawanna coal dock, and construction of the east outer
harbor.
   The total costs of the existing project were $5,080,060, of which
$4,260,354 was for new work and $819,706 for maintenance.
                                            Cost and financial summary

                                                    Fiscal year ending June 30                        Total to June
                                                                                                     30, 1954, includ-
                                                                                                     ing fiscal years
                                   1950          1951         1952         1953           1954        prior to 1950

New work:
   Appropriated           -             -          -$867 -           --           -                        $5,448, 332
   Cost..            --       --    -       ----------------------------      ---------                     5,448,332
Maintenance:
   Appropriated__                  $56, 000       32, 000     $6, 000      $57, 000       $62, 836     1     1, 766,461
   Cost        . .    .             55, 911       33,708       5,519        56,619         63,216          '1765,390


1 Includes $1,187,977 for new work and $945,684 for maintenance for previous projects.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project __                                                      $13, 656,600
                              17. OGDENSBURG HARBOR, N. Y.
   Location. This harbor is located on the south bank of the St.
Lawrence River, 62 miles by water from Lake Ontario. (See U. S.
Lake Survey Chart No. 13.)
   Previous projects. Adopted by River and Harbor Acts of
March 2, 1867, August 2, 1882, and September 19,1890, by author-
ity of the Chief of Engineers dated February 27, 1897; and by
River and Harbor Act of March 3, 1899. For further details of
previous projects, see page 1975 of Annual Report for 1915, and
page 1635 of Annual Report for 1938.
   Existing project. This provides for an upper entrance channel
400 feet wide, a city waterfront channel 350 feet wide, and for a
lower entrance channel 250 feet wide, all suitably widened at en-
trances to, and at angles in channels and all 19 feet deep; and for
a lower basin 2,400 to 3,500 feet wide and 21 feet deep, extending
1226            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

from deep water in the river to within 50 feet of the existing dock
lines.
   The project depths are referred to the river surface when Lake
Ontario is at low water datum, elevation 244 feet above mean tide
at New York. Ordinary seasonal fluctuations of water surface are
from 4 feet above to 0.5 foot below low water datum. Other fluc-
tuations due to wind and other causes are small.
   The estimate of cost for new work is $558,000 (1954), exclusive
of amounts expended on previous projects. The estimate for an-
nual cost of maintenance is $20,000 (1954).
   The existing project was authorized by the following River and
Harbor Acts:

    Acts                             Work authorized                                          Documents

June 25, 1910   Deepening the several channels to 19 feet----------.............   H. Doc. 920, 60th Cong., 1st sess.
Mar. 2, 1919    Widening upper entrance channel to 400 feet, and                   H. Doc. 663, 64th Cong., 1st sess.
                 city front to 350 feet.                                                                               2
Aug. 30, 1935   Enlarging and deepening lower basin to 21 feet, and                H. Doc. 266, 72d Cong., 1st sess.
                  removal of old elevator wharf.

1 Authorized by Public Works Administration, Sept. 6, 1933.
2Contains latest published map.

   Local cooperation. Fully complied with.
   Terminal facilities. Two terminals for coal, 5 for petroleum
products, 2 for pulpwood, and 1 for sand, are private. There is a
car-ferry terminal and a terminal for a passenger and automobile
ferry. The city of Ogdensburg owns a terminal which is used by
large passenger vessels, and is open to the public. The facilities are
considered adequate for the existing commerce.
   Operations and results during fiscal year. Government plant
and hired labor performed miscellaneous inspection services at the
project at a cost of $5,023 for maintenance.
   Condition at end of fiscal year. The existing project is about 95
percent complete. The channels were deepened to 19 feet in 1913.
The upper entrance channel was widened to 400 feet in 1920 and to
700 feet in 1935. Removal of the elevator wharf and deepening of
the lower basin were completed in 1935, except for the removal of
hard-material shoals, which remains to be done to complete the
project. There is a controlling depth of 17 feet in the channels,
and a depth of 20 feet in the lower basin, at low water datum.
   The total costs of the existing project were $798,504, of which
$375,086, including $174,549 Public Works funds, were for new
work and $423,418 for maintenance.
                         RIVERS AND HARBORS-BUFFALO, N. Y., DISTRICT                                                                                1227
                                                     Cost and financial summary

                                                                 Fiscal year ending June 30                                                 Total to June
                                                                                                                                           30, 1954, includ-
                                                                                                                                           ing fiscal years
                                            1950               1951              1952              1953                  1954                prior to 19501

New work:
   Appropriated ....................                                                                          -      -                             $646, 465
   Cost ............                                                                                                                                646,465
Maintenance:
   Appropriated ....-.               $11, 500                 $14, 000 -$1, 000                        $1, 500             $6, 015                  555,907
   Cost--------------..10,035                                  10,002     4,163                            816              5,023                   553,930

      1Includes   $271,380 for new work and $130,512 for maintenance for previous projects.
Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project ______________________________ $182,900

                              18.      INACTIVE                   NAVIGATION                       PROJECTS

                                                                                                  Cost to June 30, 1954
                                                                            For last        _               ____                 ___Estimated
                        Name of project                                   full report                                                            amount
                                                                          see annual                       Operations                          required to
                                                                          report for-        Construction     and                               complete
                                                                                                          maintenance

                           -------------------
1. Barcelona Harbor, N. Y......................                               1947                    $72,216 ......_------__                 1 $1,026,900
2. Big (Cunningham) Creek, Ohio 2-...........                                  (3)                4 19, 763      ........................--
3. Black River Harbor, N. Y. 6------..-.....                      .   (3)                              42, 401 .
4. Cape Vincent Harbor, N. Y................                         1951                             275,082       $36,254                        159, 200
5. Cattaraugus Creek, N. Y.    ------------------..................
                           7- - - - - - - - - - - - - - - - - - - - -
                                                                       (3)                              57, 410
6. Grand View Bay, N. Y.                                             1948                               1,524 -----                               424,600
7. Grasse River (Massena), N. Y.5,                             -...  1891                             4 9, 000
8. Little Sodus Bay Harbor, N. Y.1--                    --------1953                                   69,066       535,071
9. Morristown Harbor, N. Y___  .            -__ ------- 1949                                            6,221         9,106
10. Oak Orchard Harbor, N. Y.-----------------
                                   .................                  1947                             214,110 --------------                       624,500
                   7 Y.10-- .o..
11. Olcott Harbor, N.        - - - - - - - - - - - - - -_-------......
                                                         - - - - - - - - -1953
                                                                           - - - - - - - - - - -140,
                                                                                                 - - - 210                - - - -699
                                                                                                       - - - - - - - - - 283,     -- -- -
12.    Port Bay, N. Y. ..                                                    -                     .                                              2 737,000
13.    Port Ontario Harbor, N. Y__----------, ..                       -1949                            56,904    --------------                  3 961,100
14.    Pultneyville Harbor, N. Y4..................
                                     41934                                                              68, 219                20,087- ..
15.    Rocky River, Ohio 10         -                  .1953                                            8.3,971                59,364
16.    Sackets Harbor, N. Y....-.---......-.-.-..-- 1948                                                25,010-      ---            - .            379, 000
17.    St. Lawrence River between Ogdensburg,
         N. Y., and Lake Ontario
                             - - - -1 - - - - .....- - - - --- -- -- -  1935                       515, 978 ........------         1,962,000
18.    Sandusky River, Ohio 5...                                        1894                       458, 000
19.    Vermillion Harbor, Ohio......................                    1949                       133, 278          60, 581
20.    Waddington Harbor, N. Y.l.................                       1932                       435,500 -'                         20,000
21.    Wilson Harbor, N. Y.10.....................--------------------  1953                       387,319           44, 256 ..-----

      Local interests required to contribute $7,500 additional.
      21
      No commerce reported.
      43 Only
           information available is in index to the reports of the Chief of Engineers.
      Amount includes maintenance; not separable.
   5 Abandonment recommended in H. Doc. 467, 69th Cong., 1st sess.
   67 Abandonment recommended in Ex. Doe. 16, 35th Cong., 1st sess.
      No work proposed pending compliance with conditions of local cooperation.
    8 Local interests required to contribute $79,300 additional.
    * Channel improved by local interests.
  10 Completed.
  11 Local interests required to contribute $170,700 additional.
  "s Local interests required to contribute $200,000 additional.
  is Local interests required to contribute $211,300 additional.
  14 Abandonment recommended in H. Doc. 375, 64th Cong., 1st sess.
  t1 Channels adequate for existing commerce.
  1t No work has been done on the existing project, and none is proposed pending consideration of major
improvement of St. Lawrence River.
  ITLocal interests required to contribute $28,000 additional.
1228         REPORT OF CHIEF OF ENGINEERS. U. S.
                                              SARMY, 1954

                    19. LANCASTER, CAYUGA CREEK, N. Y.
   Location. Cayuga Creek passes through the village of Lan-
caster, N. Y., and joins Buffalo Creek about 8 miles downstream
from the village. Buffalo Creek empties into Lake Erie at Buffalo,
N. Y., about 9 miles downstream from its juncture with Cayuga
Creek.
   Existing project. The plan of improvement provides for the
protection of the village of Lancaster against flood flows of 18,000
cubic feet per second, the maximum of record, by clearing and im-
proving Cayuga Creek channel from Park Boulevafd in the village
of Lancaster downstream to Penora Street, in the village of Depew,
a distance of about 11/2 miles, and constructing drainage facilities
in the village of Lancaster. The channel improvement consists
of straightening and widening Cuyuga Creek channel, construct-
ing earth dikes, and steel sheet pile floodwalls.
   The cost of new work for the completed project was $797,300, ex-
clusive of $28,000 contributed by local interests toward the cost of
construction of drainage facilities. The local cost for lands and
damages was $311,200.
   The existing project was authorized by the Flood Control Act
approved August 18, 1941 (H. Doc. 326, 77th Cong., 1st sess.).
   Local cooperation. Fully complied with.
   Operationsand results during fiscal year. New work: Installa-
tion of a flap gate on the head wall of a 60-inch pressure culvert
in the St. Mary's dike was completed during December 1953, by
hired labor. The total cost for the year was $1,773.
   Condition at end of fiscal year. Construction of the existing
project was initiated during June 1947, and completed during July
1949, except for flap gate installed in December 1953.
   The total cost of the existing project, United States funds, was
$797,300. In addition, there were costs of $28,000 from contrib-
uted funds for new work.
                                    Cost and financialsummary

                                           Fiscal year ending June 30                          Total to June
                                                     _     _ _    _30,                           1954, includ-
                                                                                               ing   fiscal years
                             1950        1951            1952             1953      1954        priorto 1950


New work:
   Appropriated                        -- $10, 306                       -$5, 267   -$1, 727           ' $797, 300
   Cost...........          $11,753         1,224           $50     ______             1,773   "          797.300

1 In addition $28,000 for new work was expended from contributed funds.

     20. BATAVIA AND VICINITY, TONAWANDA CREEK, N. Y.
  Location. Tonawanda Creek passes through the city of Ba-
tavia, N. Y., and joins Niagara River about 68 miles downstream
of the city. The city of Batavia, N. Y., is located in Genesse
County. (See U. S. Geological Survey maps of Attica, Medina,
Albion, and Batavia, N. Y.)
  Existing project. The plan of improvement provides for the
flood protection of the city of Batavia and vicinity by improve-
ments to the channel of Tonawanda Creek consisting of: widening
                     FLOOD CONTROL--BUFFALO, N. Y., DISTRICT                                        1229

the creek channel from a point approximately three-quarters of a
mile westerly of the west city line of Batavia to the municipal dam
in Batavia; bank protection between Oak and Walnut Streets; and
minor channel clearing above the municipal dam to the Lehigh
Valley Railroad Bridge. Removal of the bridge pier of the aban-
doned Attica Branch of the New York Central Railroad is to be
done by local interests at no cost to the United States.
   The estimated Federal cost for construction is $505,000 (1954).
The estimated local cost for lands and damages is $232,500 (1954).
   The existing project was authorized by the Flood Control Act
approved June 30, 1948 (S. Doc. 46, 80th Cong., 1st sess.).
   Local cooperation. In addition to the usual requirements as
provided by law, local interests have agreed to assume responsibil-
ity for the removal of the abandoned bridge pier and the relocation
of any utilities. Local interests were requested to furnish assur-
ances of local cooperation, and have indicated that assurances
will be furnished upon receipt of plans for the proposed work
in order that a determination of their responsibility can be
made.
   Operations and results during fiscal year. New work: Prepara-
tion of detailed plans and specifications for the flood protection
work were completed, by hired labor. The total cost for the year
was $19,431.
   Condition at end of fiscal year. No construction has been
started. The work remaining to be done consists of construction,
by continuing contract, of the flood protection work.
   The total cost of the existing project was $45,431.
                                     Cost and financial summary

                                           Fiscal year ending June 30                        Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                              1950    1   1951                  1952   1953       1954        prior to 1950

New work:
   Appropriated      - ---              -----      .   ---             $26, 000   $20,000            $46, 000
    ost-------- -    --------------------------------------             26,000     19,431             45, 431


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_--------------      $569
    Appropriated for succeeding fiscal year ending June 30, 1955-------- 300,000
    Unobligated balances available for succeeding fiscal year ending June 30,
        1955_-                            -------------------                                    300,569
     Estimated additional amount needed to be appropriated for completion
       of existing project---------_  ----------------------------- 159,000
                    21. WELLSVILLE, GENESEE RIVER, N. Y._
  Location. The village of Wellsville, N. Y., is located in Alle-
gany County, and is situated at the junction of Dyke Creek with
Genesee River. (See U. S. Geological Survey map of Wellsville,
N. Y.)
  Existing project. Provides for:
  a. Improvment of Genesee River to provide a channel with a
bottom width of 100 feet from a point 2,700 feet downstream from
the Bolivar Road Bridge to Dyke Creek and 75 feet from Dyke
Creek to the water supply dam near the southern boundary of the
1230                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

village,
   b. Improvement of Dyke Creek to provide a channel with a bot-
tom width of 50 feet from the mouth of the creek to a point 4,500
feet upstream,
   c. Excavation of the banks and protection of these banks against
erosion, and
   d. Underpinning of the South Main Street highway bridge over
Dyke Creek, and the Baltimore & Ohio Railroad bridge over Gen-
esee River, with such modifications thereof as in the discretion of
the Chief of Engineers may be advisable.
   The estimated Federal cost for construction is $960,000 (1954),
exclusive of $50,000 to be contributed by local interests. The esti-
mated local cost for lands, damages, and necessary alterations to
utility crossings and bridges is $122,000 (1953).
   The existing project was authorized by the Flood Control Act
approved May 17, 1950 (H. Doc. 232, 81st Cong., 1st sess.).
   Local cooperation. In addition to the usual requirements for
local cooperation as provided by law, local interests are required
to contribute $50,000 toward the construction cost, and make any
necessary alterations to utility crossings and bridges. Local in-
terests were requested to furnish assurances of local coopera-
tion, and have indicated that assurances will be furnished by
them upon receipt of a definite project plan of the proposed work
in order that a determination of their responsibilities can be
made.
   Operationsand results during fiscal year. New work: Prepara-
tion of detailed plans and specifications for the flood protection
work was continued, by hired labor. The total cost for the year
was $11,354.
   Condition at end of fiscal year: No construction has been
started. The work remaining to be done consists of completion of
detailed plans and specifications, by hired labor, and construction,
by continuing contract, of the flood protection work.
   The total cost of the existing project was $34,645.
                                                         Cost and financial summary

                                                               Fiscal year ending June 30                   Total to June
                                                                                                           30, 1954, includ-
                                                                                                           ing fiscal years
                                                1950          1951        1952        1953       1954       prior to 1950


New work:
   Appropriated ...--------------------------
                  --                                                   ----------      38,000                       $38,000
    Cost----------------------------------------------                                 23, 291   $11,354             34, 645


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-_-----------         $3, 355
    Appropriated for succeeding fiscal year ending June 30, 1955--------- 26,000
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955---     -------------------------------------------                  29,355
    Estimated additional amount needed to be appropriated for completion
      of existing project _            -         ----                         896, 000
              FLOOD CONTROL-BUFFALO, N. Y., DISTRICT             1231
     22. MOUNT MORRIS RESERVOIR, GENESEE RIVER, N. Y.
   Location. The dam site is on the Genesee River 66.9 miles
above the mouth of the river and approximately 32 miles south-
westerly of Rochester, N. Y. The reservoir area is in Livingston
and Wyoming Counties, N. Y. (See U. S. Geological Survey maps
of Nunda and Portage, N. Y.)
   Existing project. This provides for a reservoir at Mount Mor-
ris for flood control and other purposes. Present plans provide for
the construction of a concrete gravity dam rising about 210 feet
above the riverbed with an uncontrolled overflow spillway and
gate-controlled outlet sluices through the overflow section of the
dam, and a reservoir with a storage capacity of 337,000 acre-feet
at spillway crest. Provisions for the future development of power
at the site will consist of two penstocks through the dam near the
left abutment.
   The reservoir will be operated for the protection of the city of
Rochester, the Genesee River flats from Rochester to Mount Mor-
ris, and the lower Canaseraga Valley.
   The estimated Federal cost is $23,397,000 (1954) for construc-
tion, including $379,300 for the acquisition of lands in the reservoir
area and exclusive of $5,000 contributed by local interests.
   The estimated cost of annual maintenance and operation is
$68,800 (1954).
   The existing project was authorized by the Flood Control Act
approved December 22, 1944 (H. Doc. 615, 78th Cong., 2d sess.).
   Local cooperation. None required.
   Operationsand results during fiscal year. New work: Prepara-
tion of operation and maintenance manual was completed, by hired
labor. Reservoir regulation and miscellaneous engineering studies
for the project were continued. Costs were incurred during the
year in connection with title evidence for the purchase of lands in
fee simple. Construction of the ultimate reservoir management
and recreational use facilities, exclusive of comfort station, was
completed by hired labor. Purchase and installation of permanent
operating equipment was completed by hired labor. Reimburse-
ment was made to the U. S. Geological Survey for the continuation
of cooperative stream gaging. The total cost of new work for the
year was $32,927. Operation and maintenance: Operation and
ordinary maintenance of the dam, reservoir and service facilities,
and condition and operation studies were done during the year at
a cost of $43,287.
   Condition at end of fiscal year. The existing project is about 99
percent complete. Construction of the concrete gravity-type dam
was initiated by contract on March 26, 1948, and completed on
May 16, 1952. Clearing of the reservoir area and construction of
all appurtenances have all been completed. The work remaining
to be done to complete the project consists of completion of engi-
neering studies for regulation and construction of comfort station.
1232           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY. 1954

  The total cost of existing project was $23,385,548, of which
$23,317,262 was for new work and $68,286 for maintenance. In
addition, $5,000 for new work was expended from contributed
funds.
                                      Cost and financialsummary

                                            Fiscal year ending June 30                     Total to June
                                                                                          30, 1954, includ-
                                                                                          ing fiscal years
                               1950        1951        1952         1953        1954        priorto 1950

New work:
   Appropriated      ..-    $4,836,600 $7, 500,000   $5, 000,000 -$539, 500   -$28, 000      1 $23, 369, 100
   Cost .                    7,200,755 8,136, 910
                      .---------------                1,771,734     261,722      32,927       123,   317,262
Maintenance:
   Appropriated--------------------......... --------......------ -- 25,000     53,000                78,000
   Cost-          .----------------------------------------------    25,000     43,287                68,286

1 In   addition $5,000 for new work was expended from contributed funds.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_---------                  $47,188
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955-----..----------------------------------.---------------                   47,188
    Estimated additional amount needed to be appropriated for completion
      of existing project_                              _------------------------ -- 32,550

         23. DANSVILLE AND VICINITY,                        GENESEE RIVER, N. Y.
    Location. The village of Dansville, N. Y., is located on Mill
Creek, a tributary of Canaseraga Creek, which is a tributary of
Genesee River. Mill Creek flows through the southwest corner of
Dansville and joins Canaseraga Creek about one-half mile down-
stream of Dansville. Canaseraga Creek flows generally northwest-
erly from its junction with Mill Creek, for about 19.3 miles to its
confluence with Genesee River. The village of Cummingsville is
located on Canaseraga Creek about 11/2 miles downstream of the
confluence of Mill and Canaseraga Creeks. The villages of Dans-
ville and Cummingsville are located in Livingston County. (See
U. S. Geological Survey map of Wayland, N. Y.)
    Existing project. Improvement of Canaseraga Creek at Cum-
mingsville and at the sewage disposal plant, both in the vicinity of
Dansville, N. Y., by channel work, levee or dike enlargement and
construction, and bank-protection works.
    The estimated Federal cost for construction is $250,000 (July
1954), exclusive of 70 percent of the cost of the construction of ero-
sion protection at the sewage disposal plant to be contributed by
local interests. The estimated local cost is $19,000 (1953) for lands
and damages.
    The existing project was authorized by the Flood Control Act
approved June 30, 1948 (H. Doc. 206, 80th Cong., 1st sess.).
    Local cooperation. In addition to the usual requirements for
local cooperation as provided by law, local interests are required
to contribute 70 percent of the cost of construction of erosion
protection for the Dansville municipal sewage disposal plant, and
hold and save the United States free from any future claims that
the Federal Government should participate in providing additional
protection for the sewage disposal plant or in its operation or
maintenance.            Assurances have not been received to date.
                   FLOOD CONTROL--BUFFALO, N. Y., DISTRICT                                       1233
   Operationand results during fiscal year. New work: Prepara-
tion of detailed plans and specifications for the flood protection
work was initiated by hired labor. The total cost for the year was
$11,199.
   Condition at end of fiscal year. No construction has been
started. The work remaining to be done consists of completion of
detailed plans and specifications by hired labor, and construction
by continuing contract, of the flood protection work.
   The total cost of the existing project was $11,199.
                                     Cost and financial summary

                                           Fiscal year ending June 30                     Total to June
                                                                                         30, 1954, includ-
                                                                                         ing fiscal years
                           1950           1951        1952           1953      1954        prior to 1950


New work:
   Appropriated                                                   _---------   $11,800            $11,800
   Cost--------       ------------     ------------     -     -                 11,199             11,199


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-------_-                                 $601
    Unobligated balances available for succeeding fiscal year ending June 30,
       1955_____                                 ____        _____                                   601
    Estimated additional amount needed to be appropriated for completion
       of existing project_     _-__                                                           238.200

        24. MONTOUR            FALLS, OSWEGO RIVER BASIN, N. Y.
   Location. The village of Montour Falls, N. Y., is located in
Schuyler County, and is situated 2.5 miles from the southern end
of Seneca Lake. (See U. S. Geological Survey topographical maps
of New York State.)
   Existing project. Catharine Creek flows northerly through the
center of the village of Montour Falls and discharges into Seneca
Lake. Havana Glen Creek joins Catharine Creek just south of the
village, Catlin Mill Creek flows through a diversion channel to the
east of the village and joins Catharine Creek north of the village,
and Shequaga Creek flows through a diversion channel along the
northwest edge of the village and joins Catharine Creek north of
the village. The plan of improvement for Catharine and Havana
Glen Creeks provides for the diversion of Catharine Creek to the
east of the village to join the present diversion channel of Catlin
Mill Creek, involving the excavation of a channel about 6,800 feet
long and the construction of a levee along the left bank of the chan-
nel so as to secure a channel with a capacity of 35,000 cubic feet
per second with bank protection where scour is likely to occur; con-
struction of a small gate in the levee where it crosses the present
Catharine Creek channel to provide water for sewage disposal; and
construction of two new highway bridges across the Catharine
Creek diversion channel one at Owego Street and one at Broadway
Street, the latter to be done by local interests.
   The plan of improvement for Shequaga Creek provides for in-
creasing the capacity through the village to 8,000 cubic feet per
second, to be secured by widening and deepening the channel, and
also includes construction of a wall and levee along the right bank.
1234        REPORT OF CHIEF OF ENGINEERS, U. S. ARMIY, 1954

The plan also includes construction of a stilling basin at the base
of the falls, construction of a twin barrel, reinforced concrete con-
duit, and provision of an additional span for the existing Pennsyl-
vania Railroad bridge near the lower end of the proposed improve-
ment.
   The project will provide substantial flood protection for the vil-
lage of Montour Falls.
   The existing project was authorized by the Flood Control Act
approved August 18, 1941. (H. Doc. 846, 76th Cong., 3d sess.).
   The estimated Federal cost is $1,715,000 (1953) for construc-
tion, and the estimated local cost is $526,900 (1954) for lands,
damages and relocations.
   Local cooperation. Fully complied with.
   Operations and results during fiscal year. New work: Prep-
aration of an operation and maintenance manual was completed by
hired labor and outstanding costs in connection with previously
completed construction contracts were incurred. The total° cost
for the year was $7,692.
   Condition at the end of the fiscal year. Construction of the
project is complete. Construction of the flood control improve-
ments on Catharine Creek were initiated during August 1948 and
completed during June 1953. Construction of the flood control
improvements on Shequaga Creek were initiated during April 1950,
and completed during September 1952. Adjudication of outstand-
ing contractor's claim remains to be done.
   The total cost of the existing project was $1,689,318.
                                    Cost and financial summary

                                          Fiscal year ending June 30                    Total to June
                                                                                        30, 1954, includ-
                                                                                        ing fiscal years
                             1950        1951         1952         1953      1954         priorto 1950


New work:
   Appropriated _.....    -$134,000     $ 84,000---       .....-             $17, 500        $1,697,500
   Cost----------------      507, 638    458, 467   $348,944       $70,721      7,692         1, 689, 318


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954--_--------------    $8,182
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955----------------------------_  - -     --------------------------    8,182
    Estimated additional amount needed to be appropriated for completion
       of existing project_         ---------------------------------------                    17,500

              25. SYRACUSE,             OSWEGO         RIVER BASIN,           N. Y.

   Location. Syracuse, N. Y., is located in Onondaga County at the
southern end of Onondaga Lake. (See U. S. Geological Survey
topographical map of New York State.)
   Existing project. The plan of improvement provides for in-
                    FLOOD CONTROL-BUFFALO, N. Y., DISTRICT                                   1235

creasing the capacity of Onondaga Creek Channel through the city
between Atlantic and Dorwin Avenues, 4.5 and 6.3 miles, respec-
tively, above the mouth of Onondaga Creek, from 1,000 to 6,000
cubic feet per second, by widening and realining the channel and
constructing low levees on both banks at the lower end. Two new
bridges will be required over the new channel, to be done by local
interests.
   It also provides for constructing a retention reservoir on Onon-
daga Creek about 4 miles south of Syracuse, with a capacity of
18,200 acre-feet at spillway crest, consisting of an earth dam 67
feet high, a concrete spillway channel, and an outlet conduit with
appurtenant structures. This will provide protection for the city
of Syracuse against a flood approximately 50 percent greater than
the largest on record.
   The existing project was authorized by the Flood Control Act
approved August 18, 1941 (H. Doc. 846, 76th Cong., 3d sess.).
   The estimated Federal cost is $3,407,000 (1953) for construc-
tion and the estimated local cost is $918,500 (1954) for lands,
damages and relocations.
   Local cooperation. Fully complied with.
   Operations and results during fiscal year. New- work: Reser-
voir regulation studies and preparation of regulation manual were
continued by hired labor. Reimbursement was made to the U. S.
Geological Survey for the continuation of cooperative stream gag-
ing. The total cost for the year was $4,185.
    Condition at end of fiscal year. Construction of the project is
completed. Construction of the dam was initiated during May
1947 and completed during August 1949. Improvements to the
Onondaga Creek Channel in the city of Syracuse were initiated
during July 1949 and completed during July 1951. Work remaining
to be done consists of completion of engineering studies for regula-
tion.
   The total cost of the existing project was $3,349,148.
                                   Cost and financial summary

                                         Fiscal year ending June 30                   Total to June
                                                                                     30, 1954, includ-
                                                                                     ing fiscal years
                            1950        1951        1952         1953       1954      priorto.1950


New work:
   Appropriated---------$200, 000--------$30,                         752       -         $3349, 248
   Costk-------------476,282          $205, 014     $33,687           689   $4,185         3,349,148

Other new work data:
   Unobligated balance, fiscal year ending June 30, 1954----------------                       $100
    Unobligated balances available for succeeding fiscal year ending June 30,
       1955-        -------------------------------------------------- 100
     Estimated additional amount needed to be appropriated for completion
       of existing project...----------------                 ---------------------         57,752
1236              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                       26. INACTIVE FLOOD CONTROL PROJECTS


                                                                          Cost to June 30, 1954
                                                          For last                                     Estimated
                    Name of project                      full report                                    amount
                                                        see annual                   Operation         required to
                                                        report for-    Construction     and             complete
                                                                                    maintenance

1. Caledonia, Genesee River, N. Y-..........................                                               $46, 000
2. Chittenango Creek and Tributaries, N. Y _-               1948           $12, 464-1                      633, 600
3. Hammondsport, Oswego River Basin, N. Y._                 1951            18, 691 -.......---- ...       734, 300
4. Ithaca, Oswego River Basin, N. Y...-------------         1950            20, 459 -------------          959, 600
5. Owasco Inlet and Outlet, Montville and Dry
     Creeks, State Ditch, and Crane Brook, N. Y.2           1950           281, 559 .33,500
6. Watkins Glen, Oswego River Basin, N. Y _.                1952            38, 340 --------------       1, 181, 700

     I Local interests required to contribute $25,000 additional.
     2 Assurances of local cooperation for State Ditch and Crane Brook have not been complied with. Im-
provement of Owasco Outlet, State Ditch, and Crane Brook, remains to be done to complete the project.


                                27. GENERAL INVESTIGATIONS

  Examinations and surveys. Navigation studies were continued
at a cost for the year of $21,183. The unexpended balance of $37
at the end of the fiscal year will be used to continue preparation of
the Interim Report on Cleveland Harbor. $15,000 can be profitably
expended during the next fiscal year for completion of reports on
Irondequoit Bay, N. Y., Cleveland Harbor, Ohio, and Vermilion
Harbor, Ohio.
   Cooperative beach erosion studies for New York State Parks on
the Shores of Lake Ontario were completed at a cost for the year
of $6,094. The unexpended balance of $3 will be applied to out-
standing costs for the completed studies. No work is proposed in
the next fiscal year.
  Special studies were continued at a cost for the year of $116,751,
of which $83,252 was for the New England-New York Resources
Survey. The unexpended balance of $8,704 at the end of the fiscal
year will be applied as follows: $2,895 for the New England-New
York Resources Survey and $5,809 for the Niagara Redevelopment
Remedial Works Investigation Report. $92,000 can be profitably
expended during the next fiscal year for completion of the New
England-New York Resources Survey.
  The total costs for the year for examinations and surveys was
$144,028 and the unexpended balance for the year is $8,744.
  Collection and study of basic data. The total cost for the year
was $5,537 of which: $237 was for flood emergency studies; $1,500
was for flood investigations; and, $3,800 was for International
water studies in connection with the Massena and Niagara Control
Boards.
         28. INSPECTION OF COMPLETED FLOOD CONTROL WORKS
  Inspection of the completed flood control works in the Buffalo
District was made during the year at a cost of $364.
                     FLOOD CONTROL-BUFFALO, N. Y., DISTRICT                                        1237
                                   Cost and financial summary

                                          Fiscal year ending June 30                       Total to June
                                                                                          30, 1954, includ-
                                                                                          ing fiscal years
                            1950        1951            1952        1953        1954        prior to 1950


Maintenance:
   Appropriated--------------------  $350.-----------                  $400        $400             $1, 150
   Cost--------------------------------------$75                        663         364              1,102


29. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
   Snagging and clearing of navigable streams and tributaries in
the interests of flood control. (Section 13 of the 1946 Flood Con-
trol Act.)
   Snagging and clearing by hired labor of Glen Brook, Ham-
mondsport, N. Y., was accomplished at a cost for the year of
$7,830; Smokes Creek, Lackawanna, N. Y., at a cost for the year
of $48,946; Canaseraga Creek, N. Y., at a cost for the year of
$49,404 and Cold Spring Brook, Weedsport, N. Y., at a cost for
the year of $4,020. The total cost for the year was $110,200. The
total allocation for the year was $126,500 including $8,000 to Ham-
mondsport, N. Y., from a previous appropriation. The unexpended
balance of $16,300 will be applied to outstanding commitments of
the existing snagging and clearing work.

                                   Cost and financial summary

                                          Fiscal year ending June 30                       Total to June
                                                                                          30, 1954, includ-
                                                                                          ing fiscal years
                            1950        1951            1952        1953        1954       priorto 1950

New work:
   Appropriated . - - -     $20, 000   -$2,177                      $13,792    $118,500           $365,115
   Cost _    -          -    19, 611     12, 346 -__-          --     5, 792    110,200            348,815


Other new work data: Unobligated balance, fiscal year ending June 30, 1954_ $9,365
                UNITED STATES LAKE SURVEY
   This district embraces the United States portion of the Great
Lakes-St. Lawrence River drainage basin, Lake Champlain, the
lakes and other naturally navigable waters of the New York canal
system, and the Minnesota-Ontario border lakes. In addition, con-
tiguous Canadian areas are included where essential to the integ-
rity of charting and other activities.
                             IMPROVEMENTS
                                  Navigation
                                                                          Page
1. Survey of Northern and Northwestern Lakes-----------   -------------   1239
2. General investigations---_---_   --------                              1246

    1. SURVEY OF NORTHERN AND NORTHWESTERN LAKES
   Location. The region thus covered, in which operations are
conducted for the benefit of navigation and other interests, lies
within the States of Vermont, New York, Pennsylvania, Ohio
Michigan, Indiana, Illinois, Wisconsin, and Minnesota. The Great
Lakes portion alone covers 61,000 square miles of United States
waters and 4,000 miles of United States coastline.       The Lake
Champlain portion covers 430 square miles and 560 miles of coast-
line of that lake. The additional New York State portion stretches
62 miles along the canalized waters of the State from the south
end of Lake Champlain along the Hudson River to the head of tide-
water at Albany and 333 miles westward from Troy at the conflu-
ence of the Hudson and Mohawk Rivers along the Erie Canal to
Lyons, along the Oswego Canal to Oswego, and along the Cayuga
and Seneca Canal into the Finger Lakes. The Minnesota-Ontario
border lakes portion reaches about 300 miles from Lake Superior
to and including Lake of the Woods in the Hudson Bay drainage
basin.
   Previous projects. In the region described, previous projects
of the Lake Survey have specified provision of complete navigation
charts designed to suit the needs of existing use of the waters.
These projects, in addition to hydrographic and topographic sur-
veys, contemplated the establishment of the requisite horizontal
and vertical control where not already in existence, and the meas-
urement and analysis of other factors pertaining to navigation.
The most recent comprehensive statement concerning prior proj-
ects on the Great Lakes, and formulation of "a general project cov-
ering to completion the operations of the Survey" appeared in the
Annual Report for 1907, pages 844 to 850.
   The Sundry Civil Act of March 4, 1911, extended the charting
responsibility to include the lakes and other naturally navigable
waters of the New York canals. The project extension contem-
plated compilation of navigation charts of the added waters from
all existing survey data pertaining thereto, supplemented by such
additional surveys as might be required.
                                                                  1239
1240      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   The scope of responsibility was again extended by the Sundry
Civil Act of June 23, 1913, to include Lake Champlain, and again
by the Sundry Civil Act of August 1, 1914, to include the Minneso-
ta-Ontario boundary waters from Lake Superior to Lake of the
Woods. Here, as in the extension to the New York canals, the
project extensions contemplated compilation of charts from exist-
ing surveys, supplemented by additional surveys as required.
   Responsibilities of the U. S. Lake Survey in the Great Lakes
portion of the region covered, apart from the charting and navi-
gational aspects, consist of those pertaining to lake levels, hydrol-
ogy, and hydraulics of the connecting and outflow rivers. The
1907 Annual Report, referred to above in connection with the
charting and navigational portions of the project, also discussed
prior and existing responsibilities in these respects.
   A board appointed by the division engineer, Great Lakes Di-
vision, to study and clarify U. S. Lake Survey activities in this sec-
ond category formulated a report which included definite recom-
mendations. The board report was presented to the Chief of Engi-
neers and approved on January 21, 1935, as the basic description
of such responsibilities. The report thus is the foundation for the
continuing activities of the U. S. Lake Survey relating to lake
levels, hydrology, and hydraulics. It is to be noted that these ac-
tivities do not include the waters separate from the Great Lakes,
which were added for charting only.
   Existing project. That portion of the existing project con-
cerned with charting provides for general maintenance of chart
coverage. Various classes of charts are issued, consisting essen-
tially of general charts employing small scales suitable for the
needs of open-lake navigation; coastal, river, and sectional charts
employing medium scales affording greater detail for closer navi-
gation in "the areas covered; harbor and confined locality charts
employing large scales showing details pertinent to the restricted
navigation involved; and special charts such as those of the Min-
nesota-Ontario border lakes employing scales suitable to the pur-
poses intended. The number of charts and individual chart scale
and coverage are not fixed. Changing requirements of navigation
render existing charts unnecessary, alter coverage and scale re-
quirements, and make new charts desirable. Within the region
assigned for charting, the project is flexible in permitting altera-
tions to keep abreast of changing needs.
 . Closely related to charting, but pertinent to lake levels and hy-
draulics- as well, is the portion of the project relating to horizontal
and vertical control. The original control was established under
the early projects in connection with the initial surveys by the
U. S. Lake Survey on the Great Lakes and by other Government
agencies in the other areas of the district. The original control
has been preserved wherever possible; where destroyed it has been
replaced as needed, and where necessary it has been augmented by
additional control for use in connection with later surveys and
other Corps of Engineers work. Present efforts are directed to-
ward preservation of both horizontal and vertical control by :peri-
odic recovery of monuments, replacing when found destroyed,
checking of elevations by instrumental means and water transfers,
                          U. S. LAKE SURVEY                     1241
and augmentation where required for U. S. Lake Survey and Great
Lakes Division activities. In the same connection, necessary re-
adjustments are made as indicated to correlate U. S. Lake Survey
horizontal control with nationwide horizontal control networks of
the U. S. Coast and Geodetic Survey.
   The project includes publications of information for the benefit
of navigation, additional to that provided by the charts. These
consist primarily of the Great Lakes Pilot and the Supplements
thereto. The Pilot, issued annually, supplies full descriptions of
physical conditions of the waters charted and the particulars of
constantly changing conditions not adapted to adequate or prompt
representation on the charts. The Supplement, issued monthly
during the navigation season, provides corrections and additions
to the Pilot text occasioned by constantly changing conditions in
the navigational areas. Revisory material for the annual editions
of the Pilot and material for the Supplement are collected by U. S.
Lake Survey sections operating in the field, the various Corps of
Engineers districts having jurisdiction over the waters concerned,
and by other United States and Canadian governmental organiza-
tions.
   Other data collected and disseminated to navigation, or included
in the project for future collection and dissemination, consist of
such features as lake and river bottom characteristics, water tem-
peratures, etc. This phase of activity often requires field determi-
nation, analysis of data, and publication of results.
   Since 1859, lake level gages installed and operated by the U. S.
Lake Survey have provided a continuous record of stages of the
Great Lakes and their connecting rivers. These records have in-
terest in both the navigational and hydraulic aspects of the work.
The present project provides for continued operation of sufficient
gages for these purposes and includes reduction of the records ob-
tained, tabulation and study of the data, use in other studies such
as that of movement of the earth's crust, and publication of the re-
sults in various forms.
   In the field of hydraulics, the present project provides for con-
tinuing studies of all phases relating to the connecting and outflow
rivers to affirm the fundamental laws of flow or to determine the
changed relationships resulting from changes in river regimen.
In addition to the operation of stage recorders, as discussed above,
periodic and special measurements of current velocities and river
discharges are involved. The fundamental flow relationships de-
termined and the equations derived enter into such studies as lake
level regulation, compensations for increases in river capacity
caused by channel improvement, diversions for sanitary purposes
and power, changes in river capacity resulting from marine con-
struction, wrecks, commercial sand and gravel dredging, and prob-
lems of like nature.
   The hydrology of the lakes included in the present project, in ad-
dition to factors discussed above, deals with precipitation over the
lake basins, runoff, evaporation from the lake surfaces, ice retarda-
tions and effects, and similar phenomena. The work involves com-
pilation of data, supplied primarily by other organizations, in form
to be used in studies and problems discussed above.
1242     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

    The over-all responsibility of the U. S. Lake Survey, involving
the measurement of lake and river levels, hydraulics, and hydrol-
ogy, presented as part of the present project in the foregoing para-
graphs, is concerned with the preservation of levels of the Great
Lakes, and with the establishment and maintenance of datum
planes for control of Corps of Engineers river and harbor work
and for use as planes of reference for navigation charts.
    Operations and results accomplished during the fiscal year.
Field activities continued to be operated on a curtailed basis in
keeping with the general policy of the President and the Chief of
Engineers. This policy provides for accomplishment of only those
operations of greatest importance to defense, and essential civilian
and navigation requirements.
    Emergency sweeping operations which were started during fiscal
year 1953 were completed at the southern end of Lake Huron in
the early part of fiscal year 1954, and additional emergency sweep-
ing operations were accomplished later in the vicinity of lower
Whitefish Bay in Lake Superior where groundings had been re-
ported. Offshore soundings were resumed early in September, and
the sounding of Green Bay in Lake Michigan, also started in fiscal
year 1953 was completed before the close of the field season in Oc-
tober. Sweeping operations in the vicinity of Thunder Bay Island
Shoal in Lake Huron opened the 1954 field season in June. Shoran,
an electronic device for positioning survey vessels while conducting
offshore surveys, was procured, and preliminary testing of the
equipment was begun during the latter part of June.
    Inshore soundings were conducted from July through November.
A complete hydrographic survey was made of a portion of the west
end of Lake Erie between Toledo and the mouth of the Detroit
River, and examination surveys were made of sections of the St.
Clair River to determine where dredging and dumping operations
had caused sufficient changes in charted depths to warrant resur-
veys. As a result of the examination soundings, complete hydro-
graphic surveys of selected portions of the river were made during
April.
    Revisory surveys were conducted at full scale to accomplish the
important responsibility of gathering coastline data necessary for
the triennial revision of the Great Lakes navigation charts and the
establishment and maintenance of vertical control in all of the
United States harbors on the lakes. These activities were effected
on Lake Michigan from the start of the fiscal year until the end of
the field season, and the work was continued in selected harbors on
Lake Huron and the St. Marys River during May and June 1954.
At the time revisory surveys were being made during the 1953
field season, inshore examination sounding was accomplished off
the South Chicago waterfront and in the St. Marys River.
    In the following paragraphs further details concerning the chart-
ing and related activities, consolidated according to geographical
position on the various bodies of water, are given to show total
field accomplishments in these respects during the fiscal year.
    Lake Michigan: Offshore hydrography was completed in Green
Bay covering approximately 1600 miles of sounding. Examina-
tions and revisory surveys were made along the coastline and in
                         U. S. LAKE SURVEY                     1243
all harbors from Whitehall, Mich., clockwise around the lake to the
Straits of Mackinac, including Green Bay. Depths were checked
in harbor entrances and other critical areas. Topography was re-
vised where changes were found and new features were added, such
as the new petroleum dock at Grand Haven, Mich., and the power
plants and docking facilities in Lake Charlevoix, Mich., and at Oak
Creek, Wis. Positions of prominent landmarks used by navigators
were determined, particularly along the coastline between the har-
bors. In addition, vertical control work consisting of recovery and
replacement of benchmarks where necessary and instrumental
levels between selected marks to check their stability, was accom-
plished in all harbors where revisory surveys were made. Se-
lected triangulation stations along the east coast from Sleeping
Bear Point to South Haven, Mich., and along the west coast from
Waukegan, III., to Milwaukee, Wis. were recovered where still in
existence. Of the 45 stations searched for, 36 were recovered and
redescribed.
   Lake Huron: Sweeping operations were conducted in the lower
end of Lake Huron and resulted in the discovery of two shoals
which constitute definite hazards to navigation. Revisory surveys
were made in selected harbors from the head of the St. Clair River
along the west coast to the mouth of the St. Marys River. Depths
were checked in and around entrances to harbors and other critical
areas. Benchmarks were recovered and levels were run between
selected marks. Prominent landmarks used by navigators were lo-
cated along the shoreline. Seven water gages were set in April at
selected harbors on the west side of the lake, for earth movement
study. Sweeping operations were started in the vicinity of Thun-
der Bay Island Shoal.
   Lake Superior: Sweeping operations were conducted in the
vicinity of Point Iroquois Shoal in the southeasterly end of the lake
and three uncharted shoals were found, one of which was a serious
menace to deep draft navigation.
   Lake Erie: A hydrographic survey was completed at the west
end of the lake between Toledo and the mouth of the Detroit River,
thereby extending the survey made during fiscal year 1953 off the
mouth of the river where shoaling had been encountered during
earlier examination surveys.
   St. Marys River: Investigation soundings were made of se-
lected areas in the St. Marys River to determine whether resurvey
is necessary. Revisory examinations were made along the river
for chart revision.
    St. Clair River: Preliminary investigation soundings were
taken to determine necessity of resurvey; it was indicated to be
necessary in certain sections of the river. Additional soundings
were taken to correct the navigation chart of the river and to sup-
plement the model surveys made in fiscal year 1953.
   St. Lawrence River: Precise levels were run from BM 35 at
Tibbets Point, N. Y. to BM 28, north of Clayton, N. Y.; from BM
28 to BM 2711 on Wellesly Island, and from BM 2537 at Fort
Covington, N. Y. to BM 490 at Cornwall, Ontario.
   Hydraulics and hydrology activities consisted of recording the
levels of the Great Lakes and the connecting rivers, field meas-
1244      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

urement of the flow of the St. Clair and St. Lawrence Rivers, re-
duction, tabulation, and dissemination of data relating to lake and
river levels, river flows, diversions, precipitation and other hy-
draulic and hydrologic factors, and study and preparation of num-
erous reports on hydraulic and hydrologic problems which have
been rapidly increasing in number in connection with such matters
as the survey report on Great Lakes levels, the St. Lawrence sea-
way, the redevelopment of power on the Niagara River, the pres-
ervation and enhancement of Niagara Falls, the deepening of the
connecting rivers, and the joint United States-Canadian study of
basic Great Lakes hydraulic and hydrologic data.
    Forty-six gaging sites were maintained, of which 33 were
equipped with self-registering instruments. Four of the automatic
and 5 of the non-automatic gages were operated to gather data on
short period fluctuations of the lake surfaces, and to determine
slope profiles of the St. Clair-Detroit River for the survey report.
    Field discharge measurements were made under open water
conditions in the St. Lawrence River for determination of river
flow after removal of Gut Dam in the Galop Rapids Section of the
river. Special winter measurements were conducted on the St.
Clair and St. Lawrence Rivers.
    Forecasts of the ranges in which the 1953-54 winter low levels
and the 1954 summer high levels of the Great Lakes could be ex-
pected to occur were made approximately 5 months in advance of
the estimated months of occurrence. Summer high levels of 1953
of all the lakes occurred within the range forecast during the pre-
vious winter and within 0.3 foot of the mid-point of the range. All
of the winter low levels occurred within the forecast ranges and
within 0.5 foot of the mid-point. Although the 1954 summer high
levels had not yet been established on June 30, 1954, it appeared
that none of the lakes would peak outside of the ranges predicted.
A feature length, illustrated article, describing the current Lake
Survey method of long range forecasting, was prepared and pub-
lished in the February 1954 issue of Civil Engineering.
    The program of investigating digital and analog computing ma-
chines in the interest of greater economy and efficiency in engineer-
ing computation was continued. A study of Univac for possible
use in triangulation adjustment computations and also for compu-
tation of river discharges was started. IBM equipment was used
extensively for the statistical processing of lake levels and hydro-
logic data, and was investigated for possible use in the solution
of lake regulation problems. Investigation of GEDA analog com-
puters for lake regulation studies and backwater computations was
commenced.
    Information from numerous sources including data collected by
U. S. Lake Survey field surveys was compiled for production of 39
revised chart editions and for 3 chart reprints. Manual corrections
consisting of modifications in aids-to-navigation and other critical
chart data were made on 90,497 copies of the printed chart stock to
maintain it currently accurate to the date of issue or sale. The latter
undertaking involved 806,230 separate operations consisting of
deletion of changed chart features and addition of the new features.
Vessel masters of approximately 70 ships were interviewed at var-
                          U. S. LAKE SURVEY                     1245
ious Great Lakes ports for the purpose of improving the presenta-
tion of chart information.
   Revised editions of 40 charts and 8 reprint editions were pro-
cessed and printed during the year. In addition to the charts, 705
hydrographs, 6 revised pages of the volume of New York Canals
charts, and 25,040 Chart Catalogs were printed.
   Chart sales for the year amounted to 60,321 copies, which com-
pared with 62,311 copies sold during fiscal year 1953 and the
average of 48,696 for the 5 fiscal years prior to 1953. The proceeds
of sales, amounting to $44,319.50, were deposited to the credit of
the Treasurer of the United States. An additional 7,009 charts
were issued for official use. The 1954 edition of the Great Lakes
Pilot was prepared and copy provided to the Government Printing
Office for reproduction. The publication became available late in
March 1954. Supplements Nos. 3 to 7, inclusive, to the 1953 Great
Lakes Pilot were prepared and the copy provided to the printing
contractor monthly from July through November 1953. Supple-
ments Nos. 1 and 2 to the 1954 Great Lakes Pilot were prepared in
a similar manner in May and June 1954. The U. S. Lake Survey,
as agent for the Superintendent of Documents, sold 1,630 copies of
the Great Lakes Pilot during the fiscal year. A total of $3,796.50
was collected and transmitted to that official. An additional total
of 388 copies of the publication was issued for official use. Sales of
supplements to the 1953 and 1954 Pilots amounted to 1,206 sets of
7 issues, realizing $314.30 in sales proceeds. The 388 Pilots which
were issued were complemented by 388 sets of Supplements, as the
latter were published.
   In addition to the above publications, mimeographed notices of
the monthly mean stages of the Great Lakes and tabulations of
other hydraulic and hydrologic factors were sent to individuals,
newspapers, vessel interests, industrial interests, and Government
agencies in both the United States and Canada to which the infor-
mation is of concern.
   The foregoing operations were all maintenance. The total cost
during the year was $499,149.          Reimbursable printing work
amounted to $152,534, of which $8,661 were received for reproduc-
ing project and other special maps for Corps of Engineers districts
and the remainder was received for aeronautical charts and Army
Map Service Ground Maps. In order to include the costs of re-
visory surveys and adjacent inshore soundings in the operations
and maintenance budget for each project, direct allotments are not
made to the U. S. Lake Survey for those purposes but reimburse-
ments for the work are madel by the districts concerned. Reim-
bursable work under this category amounted to $37,500 for inshore
soundings and $69,000 for revisory surveys during fiscal year 1954.
   Conditionat end of fiscal year. All new work under the various
projects had been completed. Work under the existing project is
composed solely of maintenance. The total cost of new work under
all projects since the inauguration of the survey in 1841, amounted
to $6,729,811. New work under the existing project cost $2,755,-
914 and maintenance thereunder to June 30, 1954, cost $6,465,111,
amounting to a total for the present project during its 48 years
of existence, of $9,221,026.
1246           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   At the end of the year publications available for issue to official
users and for sale to the general public consisted of 114 charts of
the Great Lakes and connecting rivers, 5 charts of Lake Champlain,
6 charts and a volume of 60 small charts of New York canals, 17
charts of the Minnesota-Ontario border lakes, the 1954 Great
Lakes Pilot and the Supplements to the Pilot. In addition, mimeo-
graphed reports of lake levels showing current elevations, compari-
sons with past levels, and forecasts of future levels are mailed
early each month to a list of 1160 official and private recipients;
and tabulations of river discharges, precipitation, and stages at
specific locations on the lakes are dispatched regularly to 61 addi-
tional receivers, the latter being primarily official. Numerous other
tabulations and compilations of data in the charting geodetic, hy-
draulic, and hydrologic fields are posted currently for use in an-
swer to the large number of inquiries for such data received each
year.
   Requests for authorized U. S. Lake Survey services from Cana-
dian and United States agencies were extremely heavy in fiscal
year 1954 and it seems evident that this situation will continue for
some time to come. Special hydraulic and hydrologic studies con-
ducted by the U. S. Lake Survey for international engineering
boards, committees and others, have far surpassed the workload
contemplated when the present long range program was estab-
lished in 1952.
                                      Cost and financial summary

                                            Fiscal year ending June 30                         Total to June
                                                                             S _              30, 1954, includ-
                                                                                              ing fiscal years
                               1950        1951        1952        1953             1954       prior to 1950

New work:
   Appropriated        ---------------------------------------------------------                   $6,729, 811
   Cost ...------         ------------ -----------------------------------------------              6, 729,811
Maintenance:
   Appropriated ...--------   $415,000    $425,000    $365,000    $489,000         $525,000        2   6,491, 340
   Cost....----------------    409,348     421,396     386,973     483,622          499,149        26, 465, 111

  1Includes $3,973,897 for new work for previous projects.
  7 Reduced by $100,000 which represents costs of prior fiscal years, which were transferred to General

Investigations in conversion to new appropriation structure.

                              2. GENERAL INVESTIGATIONS
   The cost of the work during the fiscal year was $78,319 for spe-
cial studies in connection with survey report on Great Lakes water
levels. The balance unexpended at the end of the fiscal year
amounting to $3,681 will be applied to continuation of the study.
The additional sum of $71,000 can be profitably expended in fiscal
year 1955 for dontinuation of the study.
                                          U. S. LAKE SURVEY                                          1247
                                      Cost and financial summary

                                                     Fiscal year ending June 30               Total to June
                         S_                                                                  30, 1954, includ-
                                                                                             ing fiscal years
                               1950             1951            1952        1953   1954        priorto 1950


Maintenance:
   Appropriated.              --       I-------...                                 $82,000         1$182, 000
   Cost_                                                                      ..    78,319          1 178,319


  I Includes $100,000 prior year costs which were transferred from Survey of Northern and Northwestern
Lakes, in conversion to new appropriation structure.




         Sig 40-1247-1278
      IMPROVEMENTS OF RIVERS AND HARBORS IN THE
             LOS ANGELES, CALIF., DISTRICT
   This district is comprised of the following: the drainage basins
in California tributary to the Pacific Ocean which lie north of the
Mexican boundary and south of Cape San Martin (about 265 miles
north of the entrance to Los Angeles Harbor) ; the entire drainage
basin of Colorado River, which basin lies in southeastern Califor-
nia, southeastern Nevada, southern and eastern Utah, southwest-
ern Wyoming, western Colorado, western New Mexico, and Ari-
zona; that part of the Great Basin which lies in southwestern Utah,
southern Nevada; and southeastern California; and the United
States portions of the drainage basins of certain small streams in
southern Arizona and in southwestern New Mexico west of the
Continental Divide which drain southerly into Mexico.
                                          IMPROVEMENTS

                    Navigation                                 Flood Control-Continued
                                               Page                                                Page

1.   Morro Bay Harbor, Calif .......1249        16. Brea Dam, Santa Ana River
2.   Santa Barbara Harbor, Calif... 1251              Basin, Calif ............................   1292
3.   Redondo Beach Harbor, Calif__ 1253         17. Carbon Canyon Dam and
4.   Los Angeles and Long Beach                       Channel, Santa Ana River
        Harbors, Calif .............. 1254             Basin, Calif .............. ..........      1293
5.   Newport Bay Harbor, Calif.....       1257  18. Santa Ana River Basin, Calif.
6.   San Diego Harbor, Calif ..... 1260.              (Flood Control Act of May
7.   San Diego River and Mission                      17, 1950) _.............. ...... .. ....    1293
        Bay, Calif ..........    .         1263  19. Devil, East Twin, and Warm
8.   Inactive navigation projects-..._    1265        Creeks improvements and
9.   General investigations-............. 1265        Lytle Creek levee, Santa Ana
                                                       River Basin, Calif .. .-..--..... "         1294
                  Flood Control                 20. Riverside Levees, Santa Ana
10.   Los Angeles County drainage                      River Basin, Calif ....... _.....           1295
        area, Calif-..-..    .      .      1266 21. San Diego River Basin, Califl...               1295
11.   Santa Ana River Basin (and                22. Painted Rock Reservoir, Gila
        Orange County), Calif. (Flood                 River Basin, Ariz......... .... _            1296
        Control Act of June 22, 1936,           23. Mathews Canyon Reservoir,
        as amended).........................
                                           1287        Colorado River, Basin,. Nev..               1297
12.   San Antonio Dam, Santa Ana                24. Pine Canyon Reservoir, Colo-
        River Basin, Calif _....__.   .... 1288       rado River Basin, Nev ......                 1297
13.   San Antonio and Chino Creeks              25. Inactive flood control projects..              1298
        Channel, Santa Ana River                26. General investigations.______...               1298
        Basin, Calif ......
                          . .......
                                 ..........1289 27. Inspection of completed proj-
14.   Prado Dam Santa Ana River                       ects= ....                         -         1299
        Basin, Ca if ........          _...1.29028. Emergency flood control work.-
                              .............                                                        1299
15.   Fullerton Dam, Santa Ana                  29. Scheduling of Flood Control
        River Basin, Calif. _ .._....1291             Reservoir Operation_..-..........            1299

                                   1. MORRO BAY, CALIF.
   Location. Morro Bay is on the Pacific coast, 110 miles south of
Monterey Bay, 120 miles northwest of Santa Barbara Harbor and
nearly midway between San Francisco and Los Angeles.          (See
U. S. Coast and Geodetic Survey Chart No. 5387.)
   Existing project. This plan of improvement provides:for two
random stone breakwaters, the upcoast breakwater extending 1,800
feet south by west from Morro Rock, and the downcoast break-
                                                                                        1249
 1250            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

water extending west from the sandspit, 1,399 feet, thence north-
west 433 feet, a total distance of 1,832 feet; an entrance channel
16 feet deep and 350 feet wide; the Navy channel 16 feet deep,
varying in width from 350 feet to 800 feet from the entrance chan-
nel to the town of Morro; Morro channel from the town of Morro
to the lower bay, 12 feet deep and generally 150 feet wide; a stone
dike extending from Morro Rock to the mainland, a distance of
1,600 feet; and a quarry-waste revetment levee extending along
the waterfront at Morro, a distance of 6,930 feet to retain margin-
al fills.
   The plane of reference is mean lower low water. The range be-
tween mean lower low water and mean higher high water is 4.7
feet. The extreme range is about 8.5 feet.
   The cost for new work for the completed project was $2,612,093.
The latest (1954) approved estimate for annual cost of mainten-
ance is $25,000.
   The existing project was adopted by the River and Harbor Act
of March 2, 1945 (H. Doc. 283, 77th Cong., 1st sess.) and further
harbor development as desired by the Navy Department in ac-
cordance with the plans on file in the office, Chief of Engineers.
The project document contains the latest published map.
   Local cooperation. Fully complied with. The project has been
completed under supervision of the Chief of Engineers using funds
provided by the Navy Department.
  Terminal facilities. There are 640 feet of existing piers con-
structed by the Navy; 205 feet of piers under construction by the
county of San Luis Obispo, 169 feet of privately owned docks, and
270 feet of privately owned floating docks. Facilities are adequate
for existing commerce.
   Operations and results during fiscal year. Operations with
regular funds consisted of a condition study of the harbor, and
miscellaneous inspections and reports, all with hired labor. The
costs were $980 for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1946. The south breakwater and the stone dike connect-
ing Morro Rock and the mainland were completed in 1942; the re-
taining levee, marginal fills along the waterfront and the channel
to the lower bay in 1944; and the Morro (North) breakwater in
1946. The project was in usable condition at the end of the fiscal
year. Shoaling has occurred in the entrance and interior chan-
nels and the north breakwater has suffered extensive damage. The
south breakwater is being flanked at its root by erosion.
   Controlling depths were as follows:

                                                                                             Feet   Date ascer-
                                                                                                      tained

Entrance channel                   -------------
                                             ..    -----------------
                                                 ....                  ------- -------         14   May 1953.
Navy channel- . _..--
                   ....---------                                                -              14     Do.
Morro Channel ....---------                                              -                      4     Do.
                                                                                         I
           RIVERS AND HARBORS-LOS ANGELES, CALIF., DISTRICT                                                            1251
   Total costs for the existing project to June 30, 1954, were as
follows:

                                                                                                 Costs
                                Funds
                                                                             New work          Maintenance          Total

Navy funds .. --------------------------------------                          $2,612, 093          $307, 945         $2, 920, 038
Regular funds ___                 ____---..-----------.                              -----          576, 751             576, 751

       Total, all funds__.----------------------------- --                      2,612,093           884, 696          3,496, 789



                                              Cost and financial summary

                                                           Fiscal year ending June 30                           Total to June
                                                                                                               30, 1954, includ-
                                                                                                               ing fiscal years
                                       1950               1951        1952           1953          1954         prior to 1950

New work:
                                ............
   Appropriated.....-------.-----------.-----------  -------...-----------------------............                  $2,612,093
       ................---------........----------------------------------------------
   Cost-----------                                                                                                   2,612,093
Maintenance :
     Appropriated                   ---
                             _---------                   $4, 094     $2, 252         -$162         $5, 600             889, 691
                 .......
     Cost----------------- .          271, 771             2,998        1,099          5,510             980            884,696


                            2. SANTA BARBARA                           HARBOR, CALIF.
   Location. This improvement is located on the Pacific coast, 90
miles northwest of Los Angeles Harbor and 320 miles southeast of
San Francisco Harbor.      (See U. S. Coast and Geodetic Survey
Chart No. 5261.)
   Existing project. This plan of improvement provides for main-
tenance by dredging of depths existing in 1934 in the harbor
formed by the breakwater constructed by local interests and per-
mits the maintenance of the harbor by means of a fixed sand-inter-
cepting plant to be provided and operated by and at the expense of
local interests; the United States to make available for the opera-
tion of the plant an amount not exceeding $30,000 annually, the
present approved estimated annual cost of maintenance, whenever
funds are alloted for such purpose, provided that there shall be de-
ducted from such funds the actual cost of harbor maintenance
found necessary, if and when the intercepting plant has been in-
stalled.
   The plane of reference is mean lower low water. The range of
tide between mean lower low water and mean higher high water is
5.4 feet. The extreme range is about 10 feet. The (1954) estimate
for annual cost of maintenance is $30,000.
   The existing project was authorized by the following river and
harbor acts:
1252              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


       Acts                         Work authorized                                                             Documents
                                                                                                i                                      ----




Aug. 30, 1935     Maintenance by dredging of the present depths into                                 Senate committee print, 73d Cong.
                    the harbor formed by the breakwater constructed                                    2d sess.
                    by local interests.
Mar.    2, 1945   Permits maintenance by means of a fixed sand-inter-                                H. Doc. 348, 77th Cong., 1st sess.
                    cepting plant to be provided and operated by and                                   (Contains latest published map.)
                    at the expense of local interests, the United States
                    to contribute to operating expense an amount not
                    to exceed $30,000 annually, whenever funds are
                    allotted therefor, the funds thus contributed to be
                    reduced by actual cost of harbor maintenance if
                    and when the intercepting plant has been installed.



  Prior to adoption by Congress, the work was authorized by the
Public Works Administration.
  Local cooperation. No specific local cooperation is required.
Local interests have contributed $450,322 to date to cover the ex-
cess cost of depositing dredged material on the beach, over the esti-
mated cost of similar dredging with disposal at sea, and $12,664
for dredging in vicinity of the Navy pier. The River and Harbor
Act of March 2, 1945, permits maintenance of the harbor by an
intercepting plant as described above.
  Terminal facilities. These consist of one wharf 2,200 feet long,
a Navy pier 335 feet long, and also a landing float and mooring
facilities for small craft. The wharf, which is equipped with a
warehouse, is used for general cargo and for servicing fishing
boats.         Facilities are adequate for existing commerce.
  Operations and results during fiscal year. Operations, with
regular funds, consisted of miscellaneous inspections and reports.
The costs were $1,887 for maintenance from regular funds.
   Condition at end of fiscal year.                                            Controlling depths were as
follows:

                                                                                                             Feet          Date ascertained


Entrance channel (for a width of 600 feet).----------    ----                                                       20    June 1953.
North anchorage ..       .   .   ..     .
                                     __-----_----
                                              . - ....                                                              12    June 1952.
South anchorage      ----------------------------------------------           ---                                   15        Do.
Navy channel .                                                                                                      20        Do.
Stearns wharf------- -- -- -- -- ----. -- . -. . . . . . . . .    ..---------                                       18        Do.



  Total costs for maintenance and beach restoration to June 30,
1954, were as follows:

                                                                                                             Costs
                           Funds
                                                                               New work                   Maintenance            Total


Regular funds________       _______                                   -- - - -        -                   -$638,456                $638,456
Public works funds__________________..                                           ..              .29,198                             29,198
       Total, United States funds    -..                                  .-. -----
                                                                         ---                                    667,653             667,653
Contributed funds______ __________.                                                                             462, 986            462,986
Working funds -      ._________________-..
                                      -.........------                  -             -11,000                                        11,000

       Total, all funds_______________     .................-------      ---              - -   --    -       1,141,640           1,141,640
         RIVERS AND HARBORS                   LOS ANGELES, CALIF., DISTRICT                     1253
                                      Cost and financial summary
                                           CONSOLIDATED


                                            Fiscal year ending June 30                  Total to June
                                                                                        30, 1954, includ-
                                             ....                                       ing fiscal years
                               1950        1951       1952         1953       1954        priorto 1950


Maintenance:
   Appropriated .         -   -$2, 460      $2, 600    $1, 499    $315, 350   $5, 086         $1, 144, 337
   Cost__ _______________         -- 745        488        831     308, 459    1, 887          1, 141, 640



                       3. REDONDO          BEACH HARBOR,                 CALIF.
    Location. On the Pacific coast in the southern (downcoast)
part of Santa Monica Boy, about 18 miles by sea northwest of Los
Angeles and Long Beach Harbors and about 417 miles southeast of
San Francisco Bay. (See U. S. Coast and Geodetic Survey Charts
5101 and 5144.)
    Existing project. This plan of improvement provides for re-
construction of about 1,485 linear feet of the existing stone break-
water, construction of a 2,800-foot extension of the existing break-
water, and a south breakwater 700 feet long; and for maintenance
of the entire existing breakwater as reconstructed, the breakwater
extension, and the south breakwater. The plane of reference is
mean lower low water. In Santa Monica Bay, the mean tidal range
is 3.8 feet; the diurnal range 5.6 feet; and the extreme range about
10.5 feet.
    The estimated cost of new work (1954) is $4,510,000. The esti-
mate for annual cost of maintenance (1954) is $20,000.
    The existing project was adopted by River and Harbor Act of
May 17, 1950, (H. Doc. 303, 81st Cong., 1st sess.). The project
document contains the latest published map.
    Local cooperation. Local interests are required to provide,
through a competent and duly authorized public body, all lands
and rights-of-way necessary for construction and maintenance of
the proposed improvements, including transfer of ownership of
the existing section of the breakwater to the United States; con-
struct a quay wall along the land side of the harbor between the
existing breakwater and the vicinity of Beryl Street; dredge the
harbor area a least depth of 12 feet below mean lower low water,
deposit the dredge spoil landward of the quay wall and in the
eroded area south of the wall, construct an access trestle, pier,
slips, and all other facilities necessary for adequate berthing, serv-
icing, maintaining, and supplying small craft, maintain the speci-
fied depth in the harbor area and maintain and operate the harbor
facilities, except the breakwater, with such facilities available to
all on equal terms; and hold and save the United States free from
responsibility for any effects of the improvement on adjacent shore
lines and from any damages due to construction and maintenance
of the harbor improvements.
    The 2,400 feet of breakwater already constructed at a cost of
$545,000 and the marginal land in public ownership has been of-
fered by the city of Redondo Beach as items of local cooperation.
1254     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

By resolution, dated May 11, 1949, the city of Redondo Beach indi-
cated its willingness to deed the existing breakwater to the United
States. The city of Redondo Beach proposes to provide, without
cost to the United States additional items of local cooperation.
  Terminal facilities. The only existing commercial terminal
facility is the Monstad pier. This pier is privately owned. It is
20 feet wide and extends seaward about 300 feet to a depth of 15
feet below mean lower low water. Facilities are considered ade-
quate for existing commerce.
  Operations and results during fiscal year. None.
  Condition at end of fiscal year. No work has been accomplished.
    4. LOS   ANGELES   AND LONG BEACH HARBORS,           CALIF.

   Location. These harbors are on the Pacific coast, 410 miles
southeast of San Francisco Harbor and 96 miles northwest of San
Diego Harbor. (See U. S. Coast and Geodetic Survey Chart No.
5147).
   Previous projects. Los Angeles Harbor: There was no project
for the outer harbor prior to the existing project. Original proj-
ect for the inner harbor was adopted by the River and Harbor Act
of March 3, 1871, and modified by the River and Harbor Acts of
March 3, 1881, August 2, 1882, June 3, 1896, June 13, 1902, June
25, 1910, July 18, 1918, and March 3, 1925.
   Long Beach Harbor: There was no previous project.
   For further details, see page 1977 of Annual Report for 1915,
and page 1646 of Annual Report for 1938.
   Existing project. This plan of improvement provides for a
stone breakwater 11,152 feet long (San Pedro breakwater) ex-
tending easterly from Point Fermin; for a stone and earth de-
tached breakwater 18,500 feet long (Middle breakwater); for a
stone and earth detached breakwater 13,350 feet long (Long Beach
breakwater) ; for maintenance of the original Long Beach break-
water south of the outer end of pier A (now an integral part of
pier A as extended) ; for an entrance channel 1,000 feet wide and
40 feet deep to outer Los Angeles Harbor, with a turning basin
3,500 feet long and 1,500 feet wide of the same depth opposite the
end of pier 1, and enlargement of the entrance to the inner harbor
by dredging to a depth of 35 feet, a triangular area at its junction
with this turning basin; for irregular anchorage areas (areas A
and B) 40 feet deep adjacent to the 40-foot-depth entrance chan-
nel; for an inner harbor channel (Los Angeles Channel) 35 feet
deep and 1,000 feet wide, with a turning basin at its north extrem-
ity 35 feet deep; for a channel (East Basin Channel) 35 feet deep
and 650 feet wide extending from the turning basin to United
States station 406; for a channel (Cerritos Channel) 35 feet deep
and 400 feet wide from United States station 406 to a turning
basin in Long Beach inner harbor; for a turning basin 35 feet deep
in Long Beach inner harbor; for an entrance channel to Long
Beach inner harbor 35 feet deep and 300 to 500 feet wide; for a
settling basin at the mouth of the Los Angeles River diversion
channel, the dredged material to be deposited on the beaches east-
          RIVERS AND HARBORS-LOS ANGELES, CALIF., DISTRICT                                               1255
ward therefrom to Belmont pier; for a silt diversion channel (Los
Angeles River) for the protection of Los Angeles and Long Beach
Harbors; and for maintenance of the entire project except the silt
diversion channel.
   The plane of reference is mean lower low water. The range of
tide between mean lower low water and mean higher high water is
5.5 feet. The extreme range is about 10 feet.
   The Federal cost for new work for the completed project is $30,-
360,145, exclusive of amounts expended on previous projects. This
estimate does not include cost of constructing 6,000 feet of the au-
thorized 21,000-foot section of the detached breakwater by the
Navy Department. The latest (1954) approved estimates for an-
nual cost of maintenance are $125,000 for dredging and $125,000
for repairs to breakwater.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                         Work authorized                         It          Documents


June 3, 1896      A breakwater 8,500 feet long, easterly of Point Fermin.    S. Doc. 18, 55th Cong., 1st sess.
June 25, 1910     Extension of said breakwater to shore, making a total      H. Doc. 969, 60th Cong., 1st sess.
                    length of 11,152 feet from Point Fermin.
July 25, 1912     Dredging in Los Angeles outer harbor west of the en-       Rivers and Harbors Committee
                    trance channel.                                            Doc. 8, 62d Cong., 2d sess.
Aug.    8, 1917   For the silt-diversion works___---------                   Rivers and Harbors Committee
                                                                               Doc. 9, 64th Cong., 2d sess.
Sept. 22, 1922Triangular area approach to Los Angeles inner har-             H. Doc. 1013, 66th Cong., 3d sess.
                bor entrance channel.
Mar. 3, 1925  Dredging the Los Angeles Harbor main channel and               H. Doc. 349, 68th Cong., 1st sess.
                entrance 35 feet deep and 1,000 feet wide, dredging
                the inner harbor turning basin 35 feet deep, and for
                reclamation of Reservation Point.
July 3, 1930 A detached breakwater 12,500 feet long in prolonga-             Rivers and Harbors Committee
                tion of the existing breakwater (authorized by act             Doc. 33, 71st Cong., 2d sess.
                of June 3, 1896).
    Do ...    Widening the fairway on the easterly side of the en-           S. Doc. 130, 71st Cong., 2d sess.
                trance to Los Angeles inner harbor, dredging a
                channel 35 feet deep and 650 feet wide in the east
                basin from the turning basin to United States sta-
                tion 406; dredging 35 feet deep and 400 feet wide in
                 Cerritos Channel from United States station 406 to
                the Long Beach turning basin; a turning basin 35
                feet deep at Long Beach; for the entrance channel
                to Long Beach Harbor, 35 feet deep and 500 feet
                wide and for maintenance of the Long Beach break-
                water south of the outer end pier A.
    Do ..--- This act provides that in no case shall dredging be
                done within 50 feet of established pierhead lines or
                existing piers and wharves.
Aug. 30, 1935 Dredging the 1,000-foot-wide entrance channel to Los           Senate committee       print,   74th
                Angeles outer harbor to 40-foot depth and for a                Cong., 1st sess.
                turning basin 3,500 feet long and 1,500 feet wide to
                the same depth and enlargement of the entrance to
                the inner harbor by dredging to 35-foot depth a
                triangular area at its junction with the turning
                basin.
Oct. 17, 1940 Dredging to a depth of 40 feet, areas A and B adjacent         H. Doc. 843, 76th Cong., 3d sess.
                to the 40-foot-depth entrance channel; the construc-           (Contains latest published map.)
                tion and maintenance of a rubble-mound break-
                water of the composite type about 21,000 feet long
                in an easterly direction from the northeast end of the
                existing detached breakwater; dredging about
                4,000,000 cubic yards initially for a settling basin at
                the mouth of the Los Angeles River diversion chan-
                nel, and depositing the material on the beaches east-
                ward therefrom to Belmont pier; maintenance
                dredging of areas A and B, and at the mouth of the
                Los Angeles River diversion channel; all subject to
                such modifications as in the discretion of the Chief
                of Engineers may be advisable to meet the require-
                ments of the Navy.
1256             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954                                                  :


   Local cooperation. Fully complied with. Local interests have
contributed $335,575 for new work and $87,120 for maintenance to
cover the excess cost of depositing dredged materials at desired
locations.
   Terminal facilities. In Los Angeles Harbor there are 77,662
linear feet of wharves, of which 65,206 linear feet are owned by
the city and 12,456 linear feet by private interests. In Long Beach
Harbor there are 42,325 linear feet of wharves and bulkheads, of
which there are 14,013 linear feet of finished deep water wharves
and quays and 13,515 linear feet of usable bulkheads owned by the
city, 10,700 linear feet by the Federal Government, and 4,097 linear
feet by private interests. Facilities are considered adequate for
existing commerce.
   Operations and results during fiscal year. Operations with
regular funds consisted of condition study of the harbors, and mis-
cellaneous inspections and reports, all by hired labor. A -public
hearing was held and report submitted in connection with removal
of West Basin Bridge under the Truman-Hobbs Act. The costs
from regular funds were $17,271 for maintenance.
   Condition at end of fiscal year. The existing project was; com-
pleted in 1949.
   The 11,152-foot San Pedro breakwater was completed in 1912;
the silt diversion works in 1923; the Los Angeles inner harbor
channels and turning basin in 1931; the Long Beach entrance
channel in 1932; the Los Angeles Harbor entrance channel in 1937;
and the outer harbor turning basin in 1939. The 18,500-foot (Mid-
dle) breakwater was completed in 1942. The 13,350-foot (Long
Beach) breakwater was completed in 1949. Dredging from the
settling basin at the mouth of the Los Angeles River diversion
channel was completed in 1946. Dredging of areas A and B was
completed in February 1949. The breakwaters were in good con-
dition.
   Controlling depths were as follows:

                                                                                              Feet        Date ascertained

Los Angeles Harbor:
    Entrance channel-      _ - - ...-- - -          - -              -------------------             40   July 1949.
   West anchorage area (outer harbor)                                                                40       Do.
    East anchorage area (outer harbor)___________
                                                ........................                             40       Do.
    Turning basin (outer harbor)___________......................                                    40       Do.
   Main channel --- -_ ----------------                    -------------------  ---------            35       Do.
   Turning basin (inner harbor) _.............                       __...                           35       Do.
   East basin channel and Cerritos channel from slip 5 to Los Angeles-
     L ong B each C ity boundary _                            ..
                                                _____________-_               ._..     ..
                                                                                  . ____  -          32   M ay 1953.
Long Beach Harbor:
   Entrance channel _______----------------------------------                                        36   July 1949.
   Turning basin __------ - - - - - - - -                                  - - - -                   42       Do.
    Cerritos channel from Los Angeles-Long Beach City boundary to Long
     Beach turning basin___................................                                          40      Do.
   Setting basin at mouth of Los Angeles River diversion channel.......                              25   April 1946.
               RIVERS AND HARBORS-LOS ANGELES, CALIF., DISTRICT                                                       1257
  The total costs for the existing project to June 30, 1954, were
as follows:

                                                                                               Costs
                           Funds
                                                                        New work            Maintenance            Total


Regular_______________-------.----.----              $27, 769, 686       $2, 676, 312                             $30,445,998
Public works ..                                        1,593,667 . .....              .                             1,593,667
Emergency-------------------------------------------      996, 792 ----------------                                   996, 792

     Total, United States funds-                -      - ---   --         30, 360,145          2,676, 312          33, 036, 457
Contributed   -----                                                           335, 575             87,120              422, 695

        Total, all funds....-------------------------------               30,695,720           2, 763, 432         33,459,152



                                         Cost and financial summary

                                                     Fiscal year ending June 30                               Total to June
                                                                                                             30, 1954, includ-
                                                                                                             ing fiscal years
                                  1950              1951        1952             1953           1954          prior to 195012


New    work:
      Appropriated-        _   -$100, 000     -$16, 476                                                          $32, 756,315
      Cost_--      -                3,626        12,509    ----------------------------------                     32,547,192
Maintenance:
      Appropriated______ ____________       ---------               $5, 638      $11~600        $17, 500            2,816,096
      Cost_      _  ......
                       _- _-- .. 4,500      -.----------             2,930        14,.100        17,271             2,815,660


  1 Includes $2,187,047 for new work and $139,347.45 for maintenance for previous projects.
2 In addition $335,575.40 for new work and $87,120.00 for maintenance performed with contributed funds.
This work was in addition to existing project.
  Additional note: New work includes $1,593,667 public works funds; includes credit of $33,050 from transfer
of land at Reservation Point; includes $996,792 Emergency Relief funds.

                          5. NEWPORT BAY                       HARBOR,              CALIF.
   Location. This improvement is on the Pacific coast, 24 miles
southeast of Los Angeles-Long Beach Harbors, and 72 miles north-
west of San Diego Harbor, Calif. (See U. S. Coast and Geodetic
Survey Chart No. 1508.)
  Existing project. This plan of improvement provides for rub-
ble-mound entrance jetties, 900 feet apart, 1,620 and 2,860 feet in
length on the east and west sides of the channel, respectively; an
entrance channel 20 feet deep and 500 feet wide; a main channel
20 feet deep, 700 feet wide just inside the entrance, narrowing to
a general width of 350 feet; and anchorage area 20 feet deep, ap-
proximately 3,800 feet long and varying in width up to 520 feet on
the north side of the main channel in the easterly end of the bay;
an anchorage area 20 feet deep, approximately 5,200 feet long and
varying in width up to 600 feet on the south side of the main chan-
nel in the easterly end of the bay; a yacht anchorage area 15 feet
deep, 1,200 feet wide and 1,700 feet long on the south side of the
main channel midway of the bay; the Newport Channel 15 feet
1258            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

deep, approximately 6,000 feet long and varying in width up to
330 feet; a turning basin 20 feet deep, approximately 2,000 feet
long and varying in width up to 1,000 feet at the westerly end of
the bay; and for a depth of 10 feet in the remainder of the main bay
area.
   All work described above except widening the 20-foot-deep main
channel from a general width of 200 feet to a general width of 350
feet and a width of 700 feet just inside the entrance, the deepening
of Newport Channel to 15 feet over a width varying up to 330 feet,
and for dredging two anchorages to a depth of 20 feet, which were
improvements authorized in the River and Harbor Act approved
March 2, 1945, was recommended by the Chief of Engineers to the
Secretary of War under date of September 25, 1933, and was au-
thorized by the Public Works Administration June 15, 1934, at a
total estimated cost of $1,835,400 for new work, of which amount
local interests were required to contribute one-half.
   The latest (1954) approved estimated cost of new work is
$1,857,000 which is comprised of $1,593,794, the cost of work au-
thorized by the Public Works Administration of which local inter-
ests contributed one-half; and $1,060,000 (revised 1954), the esti-
mated cost of work authorized by the River and Harbor Act of
March 2, 1945, of which $255,000 is required to be contributed by
local interests. The latest (1954) approved estimate for annual
cost of maintenance is $15,000.
   The plane of reference is mean lower low water. The range be-
tween mean lower low water and mean higher high water is 4.3
feet. The extreme range is about 10 feet.
   The existing project was authorized by the following River and
Harbor Acts:

    Acts                        Work authorized                              Documents

Aug. 26, 1937   Maintenance of the work authorized by the Public   Senate   Commerce      Committee
                 Works Administration.                              print 75th Cong.
Mar. 2, 1945    Widening the main channel, deepening the Newport   S. Doc. 138, 78th Cong., 1st sess.
                 Channel, and dredging 2 anchorage areas.            (Contains latest published map.)


   Local cooperation. The improvements authorized by the River
and Harbor Act of March 2, 1945, are subject to the conditions
that local interests contribute $255,000 to the first cost, and that
responsible local agencies agree to furnish without cost to the
United States suitable areas for the disposal of dredge spoil for the
initial work and subsequent maintenance when and as required,
and to hold and save the United States free from damages result-
ing from the improvements.
   These conditions of local cooperation have not been complied
with. Local interests state that they expect to be able to guarantee
the $255,000 as soon as Federal funds become available. All prior
conditions imposed by the Public Works Administration and by the
act of August 26, 1937, are fully complied with.
         RIVERS AND HARBORS-LOS ANGELES, CALIF., DISTRICT                                                          1259
   In addition to the Federal project requirements the city of New-
port Beach and Orange County have expended for dredging and
jetty work the sum of $2,657,645 since 1916. Private interests
have spent $683,000 for dredging and other harbor work, making
the total expenditure for harbor improvements by local interests,
$3,340,645. exclusive of the Federal project.
   Terminal facilities. A county wharf 100 feet long, 440 linear
feet of wharves maintained by local canneries for discharge of fish,
120 feet of outfitting wharves, 23 marine railways, and 3 vertical
hoists for construction and servicing of small craft.
   Operations and results during fiscal year. Operations with
regular funds consisted of miscellaneous inspections and reports
by hired labor. The costs from regular funds were $299 for main-
tenance.
   Condition at end of fiscal year. The existing project is about 76
percent complete. The units of the projects authorized by the
Public Works Administration were completed in 1936 at a cost of
 $1,593,794, half of which was contributed by local interests. The
jetties were generally in good condition.
   Controlling depths were as follows:

                                                                                             Feet        Date ascertained

Entrance channel .......------------------ --          -     -----    -                             21   March 1953.
Main channel....-----------------------------------------------------                               19   February 1950.
Northerly anchorage area-------------         ------------------------------                        12      Do.
Southerly anchorage area--------------------------------------------                                12      Do.
Yacht anchorage.........-------....--------------------------------------------                     16      Do.
Turning basin  ------...........--.....-------------------------------------------                  20      Do.
Newport channel-........------------------------------------------....                              11      Do.
Lido channel.......----..........------------------------------------------------                   10      Do.
West Lido channel.......-------------------------------------------------                           11      Do.
Balboa Island channel-........--------------------------------------------                          11      Do.
Upper bay channel-......-------....--------------------------------------------....                 11      Do.



  Areas of the main bay not specifically described have been
dredged to a depth of 10 feet. Work remaining consists of wide-
ning the main channel, dredging the anchorages on both sides of
the main channel opposite Balboa Island, and deepening Newport
Channel. Total costs for the existing project to June 30, 1954,
were as follows:

                                                                                             Costs
                               Funds
                                                                     New work          Maintenance             Total

Regular funds-...--------     ------------------- --------------------------                   $117, 254           $117, 254
Public works funds ..........
                       ----------------------------------           $796,897           ---        _796,                  897
     Total, United States funds__--.---------------                        796, 897             117, 254            914, 151
Contributed funds- .---- -------------------- ---------                    796,897 -                1-              796, 897
      Total, all funds---
                      ......---.....-----------------------...-.-.       1,593,794              117,254           1, 711,048
1260            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                           Cost and financial summary

                                                    Fiscal year ending June 30                              I Total to June
                                                                                                             30, 1954, includ-
                                                                                                            ing fiscal years
                                    1950        1951            1952                 1953      1954           prior to 19501

New work:
   Appropriated       ._-                      __      -       --   --                          --                   $796,897
   Cost       _       -         -                                              -   -796,                                  897
Maintenance:
     Appropriated - - - - - -        $8, 000        $3, 000    -$1, 501              $1, 050    $1, 000               117,966
     Cost.................            7,003            496               645           2,394          299             117,254

1   In addition $796, 897 for new work was performed with contributed funds.

Other new work data: Estimated additional amount needed to be ap-
  propriated for completion of existing project-  __         __ _ $_
                                                                   1,060,103
                                6. SAN DIEGO                  HARBOR,                CALIF.

   Location. This improvement is on the Pacific coast just north
of the United States-Mexico boundary line, about 96 and 506 miles
southeast of Los Angeles Harbor and San Francisco Bay, respec-
tively. (See U. S. Coast and Geodetic Survey Chart No. 5107.)
   Previous projects. The original project was adopted by the
River and Harbor Acts of August 30, 1852, March 3, 1875, Sep-
tember 19, 1890, and June 25, 1910. For further details, see page
1976 of Annual Report for 1915, and page 1642 of Annual Report
for 1938.
   Existing project. This plan of improvement provides for a
rubble-mound jetty 7,500 feet long on Zuniga Shoal; for an en-
trance channel 40 feet deep, 800 feet wide; for removal of Middle
Ground Shoal and widening the entrance channel to the eastward
in that vicinity to a depth of 36 feet; for a bay channel 35 feet deep
and 2,200 feet wide from the vicinity of Whalers Bight to the naval
air station; for an anchorage area northward of the bay channel
1,200 feet wide, 12,000 feet long, and 35 and 26 feet deep in the east-
erly and westerly halves, respectively; for an approach to the 35-
foot anchorage, triangular in shape, 900 feet wide and 35 feet deep;
for an approach to the 26-foot anchorage, triangular in shape, 800
feet wide and 26 feet deep; for a seaplane basin 1,500 feet wide,
12,000 feet long, and 8 feet deep, landward of the anchorage area;
for a turning basin 35 feet deep, opposite the municipal piers; for a
channel approximately 20,000 feet long, 1,500 to 2,500 feet wide,
and 30 feet deep in the southerly part of the bay; for a channel to
National City and Chula Vista 20 feet deep and 200 feet wide; for a
seaplane basin in the southerly part of the bay, 5,000 to 8,500 feet
wide, 21,000 feet long, and 10 feet deep, using a part of the dredged
material to fill an area of approximately 110 acres adjacent to the
southerly end of the basin; and for an earthen dike 7,735 feet long
to divert the San Diego River from San Diego Bay to Mission Bay.
The plane of reference is maen lower low water. The range be-
tween mean lower low water and mean higher high water is 4.7
feet. The extreme range is about 10.5 feet.
   The latest revised (1954) estimated cost of new work is $10,-
879,000 exclusive of amounts expended on previous projects and
$10,000 to be contributed by local interests. The latest (1954) ap-
         RIVERS AND HARBORS-LOS ANGELES, CALIF., DISTRICT                                             1261
proved estimate for annual cost of maintenance is $40,000, of
which $20,000 is for entrance channel dredging and $20,000 for
bay dredging.
  The existing project was authorized by the following River and
Harbor Acts:

     Acts                         Work authorized                                    Documents

Mar. 3, 1875     Diversion dike..________                                 . Annual Report 1873, p. 1142.
Sept. 19; 1890   Jetty on Zuniga Shoal .                                    H. [Ex.] Doc. 177, 50th Cong., 1st
                                                                               sess. (Annual Report 1888, p.
                                                                               2114.)
Mar. 4, 1913    Dredging channel through outer bar 570 feet wide and H. Doc. 1309, 62d Cong., 3d sess.
                  35 feet deep, and a channel through the middle
                  ground 32 feet deep.
July 27, 1916 Widening the apporach (area B) to San Diego munic- H. Doc. 648, 64th Cong., 1st sess.
                  ipal pier 2 by dredging area C (north of area B).
Aug. 8, 1917    Dredging area A (south of area B)  -                        Rivers and Harbors Committee
                                                                               Doc. 8, 64th Cong., 2d sess.
    Do- .-  -   Dredging the 35-foot channel through the Middle H. Doc. 140, 65th Cong., 1st sess.
                  Ground.
Sept. 22, 1922 Dredging areas D and E_            _-                        H. Doc. 1000, 66th Cong., 3d sess.
Mar. 3, 1925 Widening the apporach (area C) to San Diego munic- Rivers and Harbors Committee
                  ipal pier 1 by dredging a portion of area F (north of        Doc. 2, 68th Cong., lst' sss.
                  area C).
July 3, 1930    For the 40-foot channel through the outer bar; dredg-       S. Doc. 81, 71st Cong., 2d sess.
                  ing along the south and north banks of the main
                  channel; dredging the turning basin; dredging area
                  H; and dredging a channel to National City and
                  Chula Vista.
Aug. 30, 1935 1 Widening the bay channel to 2,200 feet with depth of H. Doc. 223, 73d Cong., 2d sess.
                  35 feet from the vicinity of Whalers Bight in the
                  lower bay to the naval air station opposite the
                  turning basin.
Aug. 26, 1937 Dredging areas Q, Q-1, M, N, and O_____                       Rivers and Harbors Committee
                                                                               Doc. 89, 74th Cong., 2d sess.
Oct. 17, 1940 Dredging of a seaplane basin (area S) of approxi- H. Doc. 844, 76th Cong., 3d sess.,
                  mately 3,000 acres, 10 feet deep, and the filling of an
                  area of approximately 110 acres adjacent to the
                  southerly end of the basin                                                                 2
Mar. 2, 1945    Dredging of triangular approaches to 26- and 35-foot H. Doc. 390, 77th Cong., 1st sess. .
                  anchorages, area M.

  1Included  in the Emergency Relief program, May 28, 1935.
  2 Contains latest published map.

   Local cooperation. The River and Harbor Act of July 3, 1930,
provides that before any work is undertaken on the turning basin,
local interests shall furnish necessary disposal areas and give as-
surances satisfactory to the Secretary of War and Chief of En-
gineers that they will deepen areas adjacent to the municipal piers
to depth of 35 feet, and that before any work is undertaken on the
channel to Chula Vista local interest shall contribute $10,000 in
cash. These conditions have been complied with, except in the case
of the channel to Chula Vista. The modification of the project in
act of October 17, 1940, is subject to the provision that the Chief
of Engineers may direct the disposal of dredged materials on lands
not under Federal ownership, provided that local interests reim-
burse the United States for the cost involved in excess of the cost
of disposal by the most economical method and hold and save the
United States free from claims for damages resulting from such
disposal. This requirement was accepted by resolution of the city
of Coronado, and approved by the Chief of Engineers. The River
and Harbor Act of March 2, 1945, requires no local cooperation.
   Terminal facilities. In San Diego Harbor there are 34,427
linear feet of wharves, exclusive of Government-owned wharves of
which 16,123 feet are municipally owned, and 18,304 linear feet by
1262             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

private interests. In addition, there are 2 wharves at Coronado and
1 Government-owned wharf at North Island. Facilities are being
expanded to meet increased commerce.
   Operations and results during fiscal year. Operations with
regular funds consisted of a condition study of the harbor, and
miscellaneous inspections and reports, all by hired labor. The costs
from regular funds were $3,057 for maintenance.
   Condition at end of fiscal year. The existing project is about 91
percent complete. The San Diego River dike was completed in
1876; the Zuniga Shoal jetty in 1904; the entrance channel to a
width of 800 feet and a depth of 40 feet in 1934; the bay channel
to a width of 2,200 feet and a depth of 35 feet in 1936; dredging
for the Navy at mooring No. 49 in 1941; dredging the westerly
anchorage area and seaplane basin in area M to depths of 26 and
8 feet, respectively; and areas N and 0 to a depth of 30 feet in
1942; divisions 3 and 4 of area S in 1942; division 2 in 1944; and
division 1 in 1946. Dredging in area S, to the extent desired by
the Navy, was completed in 1946.
   Controlling depths were as follows:

                                                                                           Feet            Date ascertained

Entrance channel--                                                                                 40      April 1953.
Bay channel .                                                                                      35      April 1952.
26-foot anchorage.            ------------------------------                                       26         Do.
Triangular approach to 26-foot anchorage------                                                      1         Do.
35-foot anchorage .....-------------------  ---------------------                                  35              Do.
Triangular approach to 35-foot anchorage------------                                               26              Do.
Seaplane basin (area M) ---                                                                         8              Do.
Turning basin ..--------------                                                                     35              Do.
South Bay Channel-.....        ..-------------- -----------------         -----    -               30           Do.
Seaplane basin (area S)-------------------                                                         10           Do.
Chula Vista Channel-----                                     -                                     16           Do.



   Work remaining consists of completion of dredging in area S,
the triangular approaches to the 26-foot and 35-foot anchorages in
area M, and the Chula Vista Channel. The costs for the existing
project to June 30, 1954, were as follows:

                                                                                                 Costs
                                    Funds

                                                                          New work           Maintenance                  Total


Regular funds ---------------------------              ------               $7, 949, 756           $275, 971         $8, 225, 727
Public works funds .............................--..                             86, 352     --------------               86, 352
Emergency Relief funds-...............-                              __      1, 226, 793-------------............     1, 226, 793
     Total, United States funds_                                             9, 262, 901                275, 971         9, 538, 872
Contributed funds _          _   -                                                4,441 -                                     4, 441
       Total, all funds      __--                               --           9, 267, 342                275, 971         9, 543, 313
         RIVERS AND HARBORS-LOS ANGELES, CALIF., DISTRICT                                               1263
                                       Cost and financial summary

                                                  Fiscal year ending June 30                    Total to June
                                                                                                30, 1954, includ-
                                                                    I                           ing fiscal years
                                1950         1951            1952         1953       1954       prior to 1950123


New work:
                -------------------------------
   Appropriated--..                                                     ----.                        $9,417,605
    Cost ---                                                                          - --            9,417,605
Maintenance:
    Appropriated ....- -        $10, 500      $        6     $ 5,112       $3, 200    $3, 600            336, 780
    Cost.-----------------           703          1, 915      10,432        5, 406     3,057             335,875

  1Includes $154,704 for new work and $59,904 for maintenance for previous projects.
  2 In addition $4,441 for new work was performed with contributed funds.
  a Includes $86,352 public works funds; includes $1,226,793 Emergency Relief funds.

Other new work data: Estimated additional amount needed to be ap-
  propriated for completion of existing project_ _    _----       $1,616,099

             7. SAN DIEGO RIVER AND MISSION BAY, CALIF.
   Location. San Diego River has its source on the tableland in
Cuyamaca Mountains near Santa Ysabel, Calif., and flows south-
westerly 52 miles to the Pacific Ocean at the city of San Diego.
Mission Bay Harbor is adjacent to the outlet of San Diego River,
77 miles southeast of Los Angeles-Long Beach Harbors and 8 miles
north of San Diego Harbor.
   Existing project. This plan of improvement provides for a
leveed flood channel 800 feet wide with a capacity of 87,400 cubic
feet per second, from 0.4 mile above Morena Boulevard, 3.3 miles
directly to the ocean; alteration of a railroad bridge over the
leveed river flood channel; dredging of an entrance channel 20 feet
deep into Mission Bay, and in the bay a main channel and turning
basin about 3,500 feet long and 1,000 feet wide, and two anchorage
basins, one 3,000 feet long and 800 feet wide and the other about
1,600 feet long and 800 feet wide, all to a depth of 20 feet; and
construction of three jetties at the entrance, and stone revetment
for the banks of the entrance and main channels and turning basin.
   The latest (1954) approved estimated cost of new work is $9,-
860,000 and the estimated cost of annual maintenance is $13,000
for the navigation improvement.
   The existing project was authorized by the River and Harbor
Act approved July 24, 1946. (See H. Doc. 760, 79th Cong., 2d
sess., which contains the latest published map.) This project mod-
ifies the flood control project: "San Diego River Basin, Calif."
 (See H. Doc. 635, 77th Cong., 2d sess.)
   The plane of reference is main lower low water. The diurnal
range is 4.4 feet. The extreme range is 9.5 feet.
   Local cooperation. Local interests are required to provide the
necessary bulkheading and give assurances satisfactory to the Sec-
retary of Army that they will: (1) provide without cost to the
United States all lands and rights-of-way, including spoil disposal
areas necessary for construction of the improvements; (2) make
all necessary alterations to highway bridges, utilities, and side-
drainage structures; (3) purchase and hold in the public interests
the lands between the flood control channel and Mission Bay, west
of United States Highway 101; (4) prepare project plans and con-
1264            REPORT OF CIIIEF OF ENGINEERS, U. S. ARMY, 1954

struction schedules for the improvement of the bay area for park
purposes, which shall be subject to approval by the Secretary of
Army; (5) complete the improvements of the 8-foot dredging and
park development within 5 years after completion of the project;
 (6) provide adequate facilities for storage, maintenance, and sup-
ply of small craft; (7) maintain and operate the entire project,
except maintenance of the jetties, stone revetment constructed by
the United States, and project depths in areas dredged by the
United States; (8) protect the carrying capacity of the flood con-
trol channel from future encroachments or obstructions; and (9)
hold and save the United States free from damages due to the con-
structions works.
   Local interests have furnished assurances specified by the act
which were approved by the Secretary of the Army and have ex-
pended in excess of $8 million toward fulfillment of the require-
ments of local cooperation; dredged about 8 million cubic yards in
the west and east arms of Mission Bay, all to a depth of 8 feet;
removed the Mission Boulevard Bridge; completed a temporary
bridge at Ventura Boulevard; completed new bridges at Midway
Drive, U. S. 101, Sunset Cliffs Boulevard, and Morena Boulevard.
   Controlling depths were as follows:

                                                                                Feet       Date ascertained

Entrance channel (pilot channel) ..                                                    7   May 1952.
M ain channel (pilot channel)......... _ .................      .- --       -          8   June 1951.
Turning basin (pilot channel)___     ________._                                        8       Do.
East anchorage basin (pilot channel)        -           -  -      --    -              8       Do.
West anchorage basin             _     -               __   _                          8       Do.



   Operations and results during fiscal year. Operations con-
sisted of preparation of a completion report and maintenance man-
ual for the floodway portion of the project.
   The costs from regular funds were $1,708 for new work per-
formed by hired labor.
   Condition at end of fiscal year. The existing project as a!whole
is approximately 68 percent completed. The project plan for the
entire project has been completed. Construction of the downcoast
and middle jetties by contract was completed in November 1949.
Construction of the north jetty by contract was completed in Sep-
tember 1950. Relocation of the Atchison, Topeka and Santa Fe
Railway bridge by contract was completed in February 1951. Con-
struction of the Atchison, Topeka, and Santa Fe Railway bridge
approaches by contract was completed in April 1951. Construc-
tion of unit No. 1 of the flood channel by continuing contract was
completed in August 1951. Construction of foundations for two
navigation light towers near ends of middle and north jetties was
completed in April 1952. Construction of stone revetment bank
protection by contract along east shore of main channel was com-
pleted in June 1952. Construction of unit No. 2 of the flood chan-
nel by contract was commenced in April 1951 and completed in
June 1953.
   Work remaining consists of completing dredging of an entrance
        RIVERS AND HARBORS-LOS ANGELES, CALIF., DISTRICT                                                                 1265
channel, a main channel, a turning basin, and two anchorage
basins, and revetment of slopes of resultant fills.
   The total costs for the existing project to June 30, 1954, are as
follows:

                                                                                                   Costs
                             Funds
                                                                              New work           Maintenance           Total


Regular __---            _        ..   .      .      .                            $6,503,244 ---------------           $6,503,244
Contributed __.                            - ---                                     115,689 ------------                 115,689'
     Total, all funds.       __        ___                                        6,618,933   ___--
                                                                                                 -       -    -     - -6,618,933


                                                  Cost and financial summary
                                                         CONSOLIDATED


                                                          Fiscal year ending June 30




New work:
   Appropriated     __..      $2,225,000             $1,515,499        $510,000 ...
   Cost_ --                    1,787,312              2, 983,279        628,578        $71,146


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_-___-----          $5,740
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955_________              ---------------------------              5,740
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project        ----------          ----------      3,350,810

                         8. INACTIVE                      NAVIGATION                   PROJECTS

                                                                                      Cost to June 30, 1954
                                                                     For last                                        Estimated
                                                                   full report,                                       amount
                  Name of project                                                                                   required to
                                                                   see annual                    Operation
                                                                   report for-     Construction     and              complete
                                                                                                maintenance


1. San Luis Obispo Harbor, Calif                                       1937         $568,417.13       $54, 715.08        (1)



1 Completed.

                                  9. GENERAL INVESTIGATIONS
   Examinations and surveys. The costs during the fiscal year for
navigation studies and beach erosion cooperative studies were as
follows:
     Hedionda Lagoon Harbor and Shore Protection .......                                                              $ 1,875
     Interim report on critical sites, San Diego County, Calif_                                                        11,277
   The balance unexpended at the end of the fiscal year amounting
to $3,870 plus accounts receivable of $1,471, a total of $5,341 will
be applied during fiscal year 1955 as follows:
     Interim report on critical sites, San Diego County, Calif                                                         $ 5,341

   The additional sum of $48,000 can be profitably expended during
fiscal year 1956.
1266           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                               Cost and financial summary
                                    CONSOLIDATED


                                     Fiscal year ending June 30                    Total to June
                                                                                  30, 1954, includ-
                                                                                  ing fiscal years
                        1950        1951        1952         1953   I   1954        priorto 1950


Maintenance:
   Appropriated__              --           -                           $17,997           $453,255
   Cost---                                              --               23,969               148
                                                                                           443,


    10. LOS ANGELES COUNTY DRAINAGE AREA, CALIFORNIA
   Location. The site of the improvement is along the Los An-
geles and San Gabriel Rivers, Rio Hondo and Ballona Creek, and
tributaries thereof in Los Angeles County, Calif.
   Existing project. The Flood Control Acts of June 22, 1936,
and May 15, 1937, authorized the construction of reservoirs and
channel improvements in Los Angeles and San Gabriel Rivers, Rio
Hondo, and Ballona Creek, and tributaries thereof for protection
of Los Angeles County, in accordance with plans approved by the
Chief of Engineers on recommendation of the Board of Engineers
for Rivers and Harbors at an estimated construction cost not to
exceed $70,000,000.
   The Flood Control Act approved August 18, 1941, adopted the
general comprehensive plan for flood control and other purposes in
the basins of the Los Angeles and San Gabriel Rivers, Rio Hondo
and Ballona Creek as set forth in House Document No. 838, 76th
Congress, 3d session, and in addition to previous authorizations,
the act authorized $25 million for the further accomplishment of
that plan. The Flood Control Act approved December 22, 1944,
authorized to be appropriated in addition to previous authoriza-
tions, the sum of $25 million for the prosecution of the comprehen-
sive plan approved in the Flood Control Act of August 18, 1941.
The Flood Control Act approved July 24, 1946, authorized to be
appropriated, in addition to previous authorizations, the sum of
$25 million for the further prosecution of the comprehensive plan.
The Flood Control Act approved May 17, 1950, modified the com-
prehensive plan by authorizing the construction of channel im-
provements on Rio Hondo to conduct flood-water and other releases
from Whittier Narrows flood control basin to the Los Angeles River
channel, in accordance with plans on file in the Office, Chief of
Engineers. This act also authorized to be appropriated, in addi-
tion to previous authorizations, the sum of $40 million for prose-
cution of the comprehensive plan.
   For the Los Angeles River Basin the plan provides for the Sepul-
veda, Hansen, and Lopez flood control basins, debris basins at the
mouths of 17 tributary canyons, improvement of 49.07 miles of
main channel and 53.42 miles of tributary channels, and recon-
struction of 109 bridges. For the San Gabriel River Basin the
plan provides for the Santa Fe and Whittier Narrows flood con-
trol basins, debris basins at the mouths of 7 tributary canyons,
improvement of 35.6 miles of main channel and 69.16 miles of
tributary channels and reconstruction of 142 bridges. For the Rio
         FLOOD CONTROL--LOS ANGELES, CALIF., DISTRICT          1267
Hondo Basin the plan provides for debris basins at the mouth of
7 tributary canyons, improvement of 17.51 miles of main channel
and 35.23 miles of tributary channels, and reconstruction of 65
bridges. For Ballona Creek Basin the plan provides for debris
basins at the mouths of 2 canyons, 2 jetties at the mouth of Ballona
Creek, improvement of 2.39 miles of main channel and 23.67 miles
of tributary channels, and reconstruction of 12 bridges.
   Prior to the authorization of the existing project, flood control
improvements in the Los Angeles metropolitan area were under-
taken as Emergency Relief projects at a cost of $16,726,888
Emergency Relief funds and $4,238,000 contributed funds. For
full report on these improvements see Annual Report for 1941.
   The units included in the comprehensive plan are listed in the
following table:
 1268              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


                                                                                        Latest approved estimated cost 1954
                               Project unit
                                                                                         Federal               Local            Total


                       LOS ANGELES RIVER BASIN
Blanchard channel      A.                  E.                                              $454,000        $35,000               $489,000
Blue Gum Canyon----------------.------------------------                    .               214,000         25,000                239,000
Burbank-Eastern system ._..........                                                     13,188,000          90,000            13, 278,000
Burbank-Western system (lower) 1                --------                                 1,254,800         232 000             1,486,800
Burbank-Western system (upper)_-------------_                                            6,469,700      2,200,000              8,669,700
Caballero Creek_ .......                                                    _            2,465,600         275,000             2,740,600
Compton Creek 1_.             . -.    .                                                  3,742,200        401,000              4,143,200
Dead Horse Canyon and Royal Blvd. Channel                      .    - -                     733,500        125,000                858, 500
Haines Canyon 1_I.-                              -       - - -524,700                                      -524,                       700
Hansen flood-control basin 1----------                                                  11,363, 700 -11,363,                           700
Lopez Canyon diversion _._                   .           ._.914,400                                       300,000              1,214,400
Lopez flood-control basin 1I - -----------                                                 498, 900 -498,900
Los Angeles River channel:
    Owensmouth Ave. to Lankershim Blvd.l-__                               -             17, 423,300•          3,864,000       21, 287,300
    Lankershim Blvd. to Stewart and Gray Rd.1 -                                -        60, 545,300      --                   60,545,300:
    Stewart and Gray Rd. to Santa Ana branch, Pacific Electric
      Ry. bridge 1.......                                                                6,278,200                  50,000     6,328,200
    Santa Ana branch, Pacific Electric Ry. bridge to Pacific
      Ocean '__.----                        .29,959,                                            900       12, 000,000         41,959,900
Pacoima Wash channel 1          __........ __-....                 --.... -              3,215,000         1,150,000           4,365,000
Sepulveda flood-control basin                  ._--------- .__          .. .             6,648,200 --                          6, 648, 200
Sycamore Wash . ..                                                                           23,500 -23,500
Tujunga Wash channel 1.                                                                  7, 604 300     2,027, 000             9,631,300
Verdugo Wash, Concord Street to Upper Canada bridge .                          .            752,600                              752,600
Verdugo Wash, Upper Canada bridge to debris basin -..-                                   1, 546 000              90,000        1,636,000
Wilson Canyon and Mansfield St. channel---           .-----                              3,657, 000             500,000        4,157,000
Winery Canyon ----------------------------------------                                      939,000              90,000        1,029,000

         Total                                                              -     180,415,800
                                                                          -..............                 23,454,000         203 869,800

                       SAN GABRIEL RIVER BASIN
Coyote Creek ........                                                                   11,494000             4,000,000       15, 494,000
Emerald Wash and Live Oak Wash '........                                                 3,154, 700             400,000        3,554,700
Marshall Creek-......................................                                    1,711,500              125,000        1,836, 500
Santa Fe flood-control basin 1 -.                                                       12, 636, 000 .                -       12,636,000
San Gabriel River channel:
    San Gabriel Canyon to Santa Fe flood-control basin                                   1926,300--------------1,926, 300
    Santa Fe flood-control basin to Whittier Narrows ...... .                            6,966,600      1,345,000   8,311,600
    Whittier Narrows to Pacific Ocean -.....                _                            9,214,400      1,000,000  10,214,400
Thompson Creek and San Jose Wash_                                                        5,616, 500     1,000,000   6,616,500
Walnut Creek System 1        _ ___34,358,500                                                            6,750,000  41,108,500
Walnut Creek Inlet channel_                                 _                            4,035, 700        525,000  4,560,700
Whittier Narrows flood-control basin 1I __32,400,000                                                 --
                                                                                                    -.-        ..  32,400,000

         Total__   -123,514,200         .........                                                         15,145,000         138,659,200

                           RIO HONDO BASIN
Alhambra Wash I...                                                                       1,117,100                             1,117,100
Arcadia Wash system 1_  _.....                                                           9,943,100            1,455,000       11,398,100
Eaton Wash 1 _                                                                           5, 630,200           1,350,000        6,980,200
Rio Hondo channel:
    Santa Fe Railway to Whittier Narrows flood control basin
       (upper) I....                                   .    .                           10,638,500            1,969,000      12,607,500
    Whittier Narrows flood control basin to Los Angeles River
       (lower) 1__                                                                       4,889, 200           1, 763,000       6,652,200
Rubio Canyon diversion_                                                                  1,522,200               175,000       1,697, 200
Santa Anita Wash                                                                         6,824,600            1,600,000        8,424,600
Sawpit Wash 1        -_                                                                  4,824,000            1,369, 000       6,193,000
Sierra Madre Villa channel__          _                                                    834,000               130,000         964,000
         Total          _46,                                                               222, 900           9,811,000      56,033,900
                        BALLONA CREEK BASIN
Ballona Creek channel and jetties 1_       _                   --          _             2,087, 000    -2,087,000
Benedict Canyon-----_.                                                                   9,167, 900              300,000      9,467,900
Centinela Creek 1                                                                        6,099,000            3, 225,000      9,324,000
  tHigginsand Coldwater Canyons_           -_--10,                                         519,000               300,000     10,819,000
Sawtelle-Westwood systems 1                                         -14,-324,900                                 765,000     15,089, 900
Buildings, grounds, and utilities _...............                                          71,800                    -_ -       71,800
Permanent operating equipment -......                                              _        23, 900             -                23,900
        Total ...       ....                                 .        .                 42, 293,500           4,590,000      46,883,500
        Grand total for comprehensive plan .                                           392, 446,400       53,000,000         445, 446, 400
  1   The individual units that have been selected for construction are described in the following paragraphs.
         FLOOD CONTROL-LOS ANGELES, CALIF., DISTRICT           1269
                   LOS ANGELES RIVER BASIN
   Hansen flood control basin: This unit is on Tujunga Wash ap-
proximately 9.4 miles above its junction with Los Angeles River.
It includes a rolled earthfill dam 10,475 feet long, maximum height
97 feet above stream bed, with a flood control basin of 34,100
acre-feet capacity at spillway crest; an uncontrolled spillway 284
feet in length, located near the center of the dam where bedrock
is available; and outlet works through the dam near the center of
the structure.
   The operation of the basin regulates the runoff from a tributary
area of 147.4 square miles, reducing the flow of a design flood from
64,800 to 12,000 cubic feet per second.
   Sepulveda flood control basin: This unit is on upper Los Angeles
River, approximately 43:1 miles above the mouth. It includes a
rolled earthfill dam 15,443 feet long, maximum height 57 feet
above stream bed, with a flood control basin of 16,700 acre-feet
capacity at top of spillway crest gates; a spillway 399 feet in
length, located near the center of the dam; and outlet works
through the dam near the center of the structure. The operation
of the basin regulates the runoff from a tributary area of 155.3
square miles, reducing the flow of a design flood from 69,000 to
7,100 cubic feet per second.
   Los Angeles River channel, Owensmouth Avenue to Lankershim
Boulevard: This unit comprises three sections (1) Owensmouth
Avenue to Sepulveda flood control basin; (2) Sepulveda flood con-
trol basin to Tujunga Wash; (3) Tujunga Wash to Lankershim
Boulevard.
   The plan of improvement provides for a reinforced concrete
channel for Owensmouth Avenue to Lankershim Boulevard. (A
distance of 13.2 miles.')
   The channel is designed for the probable maximum flood.
   Los Angeles River channel; Lankershim Boulevard to Niagara
Street: This improvement provides a rectangular concrete chan-
nel from Lankershim Boulevard to Niagara Street (a distance of
1.7 miles). The channel is designed for the probable maximum
flood.
   Los Angeles River channel, Niagara Street to Stewart and Gray
Road: The plan of improvement provides for channel improve-
ments along Los Angeles River as follows: A rectangular concrete
channel from Niagara Street to the Burbank Western Wash (1.7
miles)'; a trapezoidal channel with concrete slab or grouted rock
protection from the Burbank Western Wash to 1,400 feet above
Dayton Avenue (7.5 miles); a channel with concrete invert and
either sloping concrete side walls or vertical sheet steel-pile or
concrete retaining walls, depending on rights-of-way available and
the proximity of mainline railroads on each bank, from 1,400 feet
above Dayton Avenue to Soto Street (5.4 miles); a trapezoidal
channel with concrete slab or grouted rock bank protection from
Soto Street to Stewart and Gray Road (6.2 miles) ; and four high-
way bridges, four railroad bridges, and one footbridge. Additional
work consists of repairs to invert at Spring Street and Main and
Alhambra Street, paving of soft-bottom channels, Victory Blvd. to
 1270     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  Dayton Ave. and the reach Soto Street to Stewart and Gray Road.
  The unit provides protection for the city of Los Angeles. The
  channel is designed for the probable maximum flood.
     Los Angeles River channel, Stewart and Gray Road to Santa
  Ana branch Pacific Electric Railway bridge: The plan provides for
  levees with grouted cobblestone bank protection and concrete paved
  invert for this reach of the river (a distance of 2.4 miles). The
  unit provides protection for the low-lying areas of Los Angeles,
  South Gate, and Lynwood to the west and South Gate to the east.
  The channel is designed for the probable maximum flood.
     Los Angeles River channel, Pacific Electric Railway bridge to
  Pacific Ocean: The plan of improvement provides for construction
  of a trapezoidal channel from the Santa Ana branch Pacific Elec-
  tric Railway bridge to Pacific Ocean (a distance to 10.3 miles).
  The channel is designed for the probable maximum flood.
     Los Angeles River channel, Long Beach Boulevard: This im-
  provement provides channel rectification of the Los Angeles River
  at Long Beach Boulevard for a distance of about 0.4 mile, by the
  removal of about 154,000 cubic yards of material. The unit re-
moved a constriction in the river channel above the city of Long
Beach.
     Haines Canyon: This unit consists of a rectangular reinforced
concrete channel of Haines Canyon from Plainview Avenue to
mouth of Haines Canyon (a distance of 1.8 miles), thus completing
a channel 3.6 miles long from Tujunga Wash to existing debris
basin. The unit also includes reconstruction of debris basin by
construction of reinforced concrete spillway and outlet structure,
enlargement of earthfill embankment, and excavation in basin. The
debris basin and the channel between Tujunga Wash and Plainview
Avenue were constructed under Emergency Relief projects. The
project intercepts the runoff from 7 square miles of mountainous
terrain and protects the cities of Tujunga and Sunland. The unit
is designed for the probable maximum flood.
    Sycamore Wash: This unit consists of 0.07 mile of covered rein-
forced concrete conduit at the junction of Sycamore Wash with the
Los Angeles River between San Fernando Road and Southern
Pacific Railroad, to provide an outlet for the existing improved
channel through the city of Glendale. The unit, including 0.6 mile
of improved channel completed under Emergency Relief projects,
will receive the runoff from an area of 7.7 square miles in the south
portion of the city of Glendale. The channel is designed for 35
percent of the probable maximum flood. Local interests contem-
plate construction of a relief bypass channel, when required by fu-
ture development.
    Verdugo Wash, Concord Street, to Upper Canada Bridge: This
unit includes channel improvements along Verdugo Wash, consist-
ing of the following features : 5.1 miles of reinforced concrete chan-
nel connecting existing improved channels at both ends of the wash
between Concord Street and Upper Canada Boulevard Bridge, in
the city of Glendale, and the removal and replacement of 15 street
bridges, 1 railroad bridge, and 1 footbridge. The unit, including a
debris basin and improved channel, above and below the project,
          FLOOD CONTROL-LOS ANGELES, CALIF., DISTRICT           1271
completed in part under Emergency Relief projects, and in part by
the Los Angeles County flood control district, provides protection
for the city of Glendale. The channel is designed for the probable
maximum flood.
    Compton Creek, Alameda Street to Hooper Avenue storm drain:
This unit includes channel improvements along Compton Creek,
consisting of the following features: 3.5 miles of rectangular rein-
forced concrete channel from above the mouth of the Hooper Ave-
nue storm drain to below Greenleaf Avenue in the city of Compton;
0.5 mile of rock-paved trapezoidal channel below Greenleaf Ave-
nue; 12 highway bridges and 2 railway bridges. The unit, includ-
ing 2.5 miles of improvement between Alameda Street and Los
Angeles River completed under Emergency Relief projects, pro-
vides protection for a large part of the southern portion of the city
of Los Angeles and the low-lying area in and around the city of
Compton. The channel is designated for the probable maximum
flood.
    Compton Creek, Hooper Avenue storm drain to Main Street:
This improvement provides an open, rectangular concrete channel
from Main Street to the upper end of the existing concrete channel
 (a distance of 2.1 miles), and includes the construction of one rail-
road bridge. The channel is designed for the probable maximum
flood.
    Lopez flood control basin. This unit is located on Pacoima Wash
approximately 6 miles above its confluence with Tujunga Wash.
The improvement serves principally as a debris basin. The plans
provide for a rolled earthfill dam about 1,300 feet long, maximum
height about 50 feet above stream bed, with a debris and flood con-
trol basin of about 900 acre-feet capacity. The drainage area
above the dam site is 34 square miles. The partly regulated and
desilted outflows will discharge into the Pacoima Wash channel.
    Pacoima Wash channel: This unit includes channel improve-
ments consisting of the following features: 5:9 miles of trapezoidal
channel with reinforced concrete invert and grouted cobble-stone
slopes with base width ranging from 10 feet to 35 feet, and 0.6
mile of rectangular reinforced concrete channel, with base widths
of 30 feet and 55 feet, extending from Lopez flood control basin to
the confluence with Tujunga Wash channel. This unit is desig-
nated to accommodate the standard project flood.
    Tujunga Wash channel: This improvement provides an open
rectangular concrete channel extending from the existing struc-
ture at Hansen flood control basin to the Los Angeles River (a dis-
tance of 9.3 miles). This unit provides flood protection for resi-
dential areas in San Fernando Valley. The channel is designed
for the probable maximum flood.
    Burbank-Western system (lower): This unit is on Burbank
Wash, a tributary of Los Angeles River. The plan of improve-
ment provides for a rectangular reinforced concrete channel and
appurtenant structures, extending from Burbank Boulevard to
above Victory Boulevard, a distance of approximately 1.6 miles.
The channel is designed with a width of 40 to 60 feet and with wall
heights of 12 to 16 feet. The construction of 5 highway bridges
and of 5 railroad bridges, and the relocation of 5 sewer lines and
1272     REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

other public utilities are included in the plan. The channel is
designed to provide adequate protection from erosion and overflow
damage by uncontrolled floodwater of the Burbank-Western sys-
tem for the residential and industrial properties located in or ad-
jacent to the valley area between Burbank Boulevard and the Los
Angeles River.
                  SAN   GABRIEL   RIVER BASIN
  Santa Fe flood control basin: This unit is on San Gabriel River,
approximately 29 miles above its mouth.
  The improvement provides a rolled earthfill dam 23,800 feet long,
maximum height 92 feet above stream bed, with a flood control
basin of 34,300 acre-feet capacity at spillway crest; an uncon-
trolled spillway 1,200 feet in length, located near the right abut-
ment; and outlet works through the dam near the center of the
structure. The operation of the basin regulates the runoff from
a tributary area of 231 square miles, reducing the flow of a design
flood from 81,600 to 19,000 cubic feet per second.
   San Gabriel River channel, San Gabriel Canyon to Santa Fe
flood control basin: This unit includes the raising and strengthen-
ing of existing levees between the mouth of San Gabriel Canyon
and the Santa Fe flood control basin, a distance of 3.4 miles. This
unit will confine the probable maximum flood on the upper San
Gabriel River to its present course, prevent flanking of the Santa
Fe flood control basin, and will protect the builtup areas in the
vicinity of Azusa.
   Whittier Narrows flood control basin: This unit is on the main
channels of Rio Hondo and San Gabriel River 10 miles east of the
city of Los Angeles and between 3 and 4 miles downstream from
the city of El Monte, Calif.
   The plan of improvement provides for a rolled earthfill dam
with gated flood control outlets discharging into Rio Hondo chan-
nel and gated spillway outlets discharging into San Gabriel River
channel, with a flood control basin of 35,000 acre-feet at spillway
crest.
   The operation of the basin will regulate the runoff from a trib-
utary area of 554 square miles of which 231 square miles are now
controlled at Santa Fe flood control basin.
   'Emerald Wash and Like Oak Wash: This unit is in San Gabriel
River Basin about 4 miles from the San Bernardino County line.
The plan of improvement for Emerald Wash provides for construc-
tion of a debris basin on Emerald Wash of 20,000 cubic yards ca-
pacity and one on the east branch of Emerald Wash of 60,000
cubic yards capacity; and an open, rectangular concrete channel,
ranging in width from 12 to 24 feet, from the debris basin to Pud-
dingstone Reservoir, a distance of 3.1 miles. The East Bra nw
Channel from the proposed debris basin to the proposed Emerald
Wash Channel, a distance of 0.1 mile, will be an open rectangular
concrete channel with a width of 14 feet. The plan of improvement
for Live Oak Wash provides for a debris basin of 35,000 yards
capacity and an open, rectangular concrete channel, varying in
width from 18 to 20 feet, from the debris basin to Emerald Wash,
a distance of 1.8 miles.
          FLOOD CONTROL-LOS ANGELES, CALIF., DISTRICT         1273
                        RIO HONDO BASIN
    Alhambra Wash: This unit includes channel improvements along
Alhambra Wash, as follows: 7.1 miles of rectangular reinforced
  concrete channel ranging in width from 18 to 40 feet to close gaps
and extend the channel from Huntington Drive to the Rio Hondo,
and 12 bridges, 6 of which are highway, 2 railroad, 3 farm, and 1
foot-bridge. The project intercepts the runoff from 14.3 square
miles of highly developed area in the cities of Alhambra, Pasadena,
San Marino, and San Gabriel. The channel is designed for the
probable maximum flood.
    Arcadia Wash: This unit is in Rio Hondo Basin about 6 miles
upstream from Whittier Narrows flood control basin. The plan
of improvement provides for construction of an open, rectangular
concrete channel, ranging in width from 4 to 50 feet as follows:
Lima Street Branch from a debris basin in San Gabriel Mountains
downstream a distance of 2.7 miles to the confluence with Baldwin
Avenue Branch; Baldwin Avenue Branch from a debris basin in
San Gabriel Mountains downstream a distance of 2.3 miles to the
confluence with East Branch; East Branch from Orange Grove
Avenue downstream, a distance of 1.9 miles to the confluence with
the main channel; main channel from East Branch downstream,
a distance of 3.1 miles to the confluence with Rio Hondo, and 3
debris basins, Carter, Auburn, and Bailey, these units are located
on Arcadia Wash above Sierra Madre, Calif. The plan of improve-
ment provides for construction of 3 rolled earthfill debris basins
as follows: Carter Debris Basin located at the head of Baldwin
Avenue of Arcardia Wash with a design capacity of 19,000 cubic
yards; Auburn Debris Basin at the end of Auburn Avenue Branch
on Arcadia Wash with a design capacity of 35,000 cubic yards;
Bailey Debris Basin located at the head of Lima Street Branch of
Arcardia Wash with a design capacity of 124,000 cubic yards.
    Rio Hondo channel, Santa Fe Railway to Whittier Narrows flood
control basin: The plan of improvement for this unit provides for
a trapezoidal channel with grouted stone bank paving and rang-
ing in width from 50 to 100 feet from the Santa Fe Railway to
Whittier Narrows flood control basin (a distance of 9.76 miles).
The channel is designed for the probable maximum flood.
    Rio Hondo channel, Whittier Narrows flood control basin to Los
Angeles River: This unit provides for the construction of a trape-
zoidal channel with reinforced concrete invert ranging in width
from 50 to 85 feet and grouted stone bank paving from Whittier
Narrows flood control basin to Los Angeles River (a distance of
7.75 miles). The channel is designed for the probable maximum
flood.
   .Sawpit Wash: This unit is in Rio Hondo basin about 7 miles
upstream from Whittier Narrows flood control basin. The plan
of improvement provides for construction of an open, rectangular
concrete channel, ranging in width from 25 to 50 feet from the
debris basin downstream to the confluence with Rio Hondo, a dis-
tance of 3.9 miles and Sawpit Wash debris basin, this unit is lo-
cated on Sawpit Wash above Monrovia, Calif. The plan of im-
1274     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

provement provides for construction of a rolled earthfill debris
basin with a design capacity of 600,000 cubic yards.
   Rubio Canyon diversion: This plan of improvement provides
for a debris basin at the junction of Rubio and Las Flores Canyons
and a rectangular concrete channel 16 feet wide to divert the flow
from the debris basin to Eaton Wash (a distance of 1.2 miles).
The debris basin, with a tributary drainage area of 1.82 square
miles, has a debris storage capacity of 182,000 cubic yards. Cov-
ered sections are provided at street crossings over the concrete
channel in lieu of bridges, and 0.75 mile of the channel is a closed
box section.
   Eaton Wash: This plan of improvement provides for a rein-
forced concrete channel ranging in width from 25 to 60 feet from
the outlet of Eaton Dam to a junction with Rio Hondo (a distance
of 7.6 miles). The plan of improvement provides for the recon-
struction of four railroad bridges. The channel is designed for
the probable maximum flood.
                     BALLONA    CREEK BASIN
   Ballona Creek channel and jetties: This unit includes channel
improvements along Ballona Creek, consisting of parts of the fol-
lowing: 1.76 miles of rectangular reinforced concrete channel be-
tween Redondo and Washington Boulevards, 1.66 miles of rec-
tangular concrete conduit with trapezoidal high water section be-
tween Washington and La Salle Streets, 5.53 miles of trapezoidal
stone-paved section between La Salle Street and the ocean; 2 heavy
stone jetties extending into the ocean for approximately 800 feet to
insure a free channel at the outlet; 14 highway bridges, 3 rail-
road bridges, the substructure for a future highway bridge; a
temporary highway bridge and a temporary railroad bridge; and
large regulating gates at the mouth of Playa del Rey Lagoon, to
allow free tidal action within the lagoon. The unit provides drain-
age for 130 square miles of area in West Los Angeles, and when
side drainage channels are provided, will control floods in West
Los Angeles, Venice, Culver City, and Beverly Hills. The channel
is designed for the probable maximum flood.
   Centinela Creek: The plan of improvement provides for the
construction of rectangular reinforced concrete channel approx-
imately 44 feet in width from the Pacific Electric Railway Bridge
downstream to the confluence at Ballona Creek, a distance of 2.3
miles.
   Sawtelle-Westwood system: This unit is on the southerly slopes
of the Santa Monica Mountains, about 4 miles northeast of the city
of Santa Monica and extends from a debris basin north of Sunset
Boulevard to a confluence with Ballona Creek, 3.46 miles from the
Pacific Ocean.
   The plan of improvement provides for the construction of rec-
tangular reinforced concrete channels as follows: East Branch
from Pico Boulevard southerly 1.06 miles to a confluence with
Westwood Branch; from a debris basin in the Santa Monica
Mountains downstream a distance of 5.7 miles to the confluence
with Sawtelle Branch; Sawtelle Branch from Pearl Street a dis-
            FLOOD CONTROL-LOS ANGELES, CALIF., DISTRICT                      1275
tance of 1.6 miles to a confluence with Westwood Branch; and the
Sawtelle-Westwood channel from that confluence to Ballona
Creek, a distance of 2.2 miles. The plan includes construction of
four highway bridges and two covered sections in Westwood
Branch.
  Local cooperation. No local cooperation is required at the fol-
lowing locations:
Hansen flood control basin.
Sepulveda flood control basin.
Los Angeles River channel: Lankershim Boulevard to Stewart and Gray Road.
Long Beach Boulevard.
Haines Canyon.
Sycamore Wash.
Verdugo Wash, Concord Street, to Upper Canada Bridge.
Compton Creek, Alameda Street to Hooper Avenue storm drain.
Lopez flood control basin.
Santa Fe flood control basin.
San Gabriel River channel:
     San Gabriel Canyon to Santa Fe flood control basin.
     Santa Fe flood control basin to Walnut Creek. (That portion constructed within
       the $70,000,000 authorization.)
Whittier Narrows flood control basin.
Alhambra Wash.
Ballona Creek channel and jetties.

   Local interests are required to furnish all lands, easements, and
rights-of-way, bear the expense of all highway and highway bridge
modifications, hold and save the United States free from damages
due to the construction work, and maintain and operate all the
works after completion at the following locations:
Los Angeles River channel:
    Owensmouth Avenue to Lankershim Boulevard.
    Stewart and Gray Road to Santa Ana branch, Pacific Electric Railway bridge.
    Santa Ana Branch, Pacific Electric Railway bridge to Pacific Ocean.
Verdugo Wash, Upper Canada Bridge to debris basin.
Compton Creek, hooper Avenue storm drain to Main Street.
Caballero Creek.
Wilson Canyon and Mansfield Street channel.
Lopez Canyon diversion.
Pacoima Wash channel.
Blue Gum Canyon.
Tujunga Wash channel.
Burbank-Western system (lower).
Burbank-Western system (upper).
Burbank-Eastern system.
Blanchard channel.
Dead Horse Canyon and Royal Boulevard channel.
Winery Canyon.
San Gabriel River channel:
    Santa Fe flood control basin to Walnut Creek. (Only the portion required to be
       built outside of the $70,000,000 authorization.)
    Walnut Creek to Whittier Narrows flood control basin.
    Whittier Narrows flood control basin to Pacific Ocean.
Walnut Creek system.
Walnut Creek Inlet channel.
Marshall Creek.
Emerald Wash and Live Oak Wash.
Thompson Creek and San Jose Wash.
Coyote Creek.
Rio Honde channel:
    Santa Fe Railway to Whittier Narrows flood-control basin.
    Whittier Narrows flood control basin to Los Angeles River.
1276      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Sawpit Wash.
Sierra Madre Villa channel.
Santa Anita Wash.
Arcadia Wash system.
Rubio Canyon diversion.
Eaton Wash.
Higgins and Coldwater Canyons.
Benedict Canyon.
Sawtelle-Westwood (lower).
Sawtelle-Westwood (upper).
Centinela Creek.

    Hansen flood control basin: Operations consisted of maintain-
ing the dam in good operating condition, preparation of operations
and maintenance manual and recreational reports. The costs from
regular funds for new work were minus $1,040 for work performed
by contract and $866 for work performed by hired labor. The
costs from regular funds for maintenance were $28,890 for work
performed by hired labor. The total costs were $28,716.
    Two-hundred and eighty c.f.s. was the maximum inflow into
reservoir and occurred on February 14, 1954. Release from reser-
voir was for spreading only. The maximum water in storage was
2,540 acre-feet, or 8 percent of the gross storage capacity at spill-
way crest.
    Sepulveda flood control basin: Operations consisted of main-
taining the dam in good operating condition; preparation of op-
eration and maintenance manual and recreational reports. The
costs from regular funds were $3,282 for new work and $31,293
for maintenance, all performed by hired labor. The total costs
were $34,575.
    Two minor storms occurred during the year: one on January
19, 1954, which produced a peak inflow and outflow of 2,500 c.f.s.;
the other storm occurred on February 13, which produced a peak
inflow of 3,200 c.f.s. and a peak outflow of 3,100 c.f.s. Reservoir
peak storage was 34 acre-feet, or 2 percent of gross storage' at
spillway crest.
    Los Angeles River channel, Owensmouth Avenue to Lankershim
Boulevard: This section of the river comprises three parts :.(1)
Owensmouth Avenue to Sepulveda flood control basin ; (2) Sepul-
veda flood control basin to Tujunga Wash; (3) Tujunga Wash to
Lankershim Boulevard. Part (1), work consisted of completion
of the project plan and preparation of plans and specifications.
Construction by continuing contract was started in April 1954
on the reach from Sepulveda Reservoir to Reseda Boulevard, part
6, and is 18 percent complete. Plans and specifications were
started and are 45 percent complete on Reseda to Corbin Avenue,
part 7. Part (2), complete; part (3), complete. The costs from
regular funds for new work for the three units were $497,851 for
work performed by contract and $98,886 for work performed by
hired labor. The total costs were $596,737, exclusive of contrib-
uted funds.
   .Los Angeles River channel, Lankershim Boulevard to Stewart
:and Gray Road: Operations consisted of rights-of-way transac-
tions, preparation of plans and specifications for repairs to the
unreinforced section of the invert, and repairs to the soft-bottom
          FLOOD CONTROL-LOS ANGELES, CALIF., DISTRICT        1277
section of the channel, and maintaining the channel in good oper-
ating condition. Status of repairs for the unreinforced invert on
three parts of the reach, North Broadway to Aliso Street, is as
follows: Plans and specifications are complete for part 1, Spring
Street. Construction was started on Spring Street in May 1104
and is 71 percent complete. Plans and specifications for part 2,
Main Street, and for part 3, Alhambra Avenue are 98 percent
complete. Plans and specifications for paving the soft-bottom
 (emergency) section, Victory Blvd. to Dayton Ave., 90 percent
complete. The costs from regular funds for new work were
$80,312 for work performed by contract and $31,010 by hired
labor. The costs from regular funds for maintenance were $36,-
303 for work performed by hired labor. The total costs were
$147,625.
   One minor storm occurred on February 13, 1954, producing a
peak discharge of 6,400 c.f.s. at Mariposa Street, which is approx-
imately 11 percent of channel capacity. At Dayton Avenue the
peak discharge was 9,600 c.f.s., which was approximately 11 per-
cent of channel capacity, and at Firestone Boulevard the peak
discharge was 19,500 c.f.s., which was approximately 16 percent
of channel capacity.
    Los Angeles River channel, Stewart and Gray Road to Santa
Ana Branch, Pacific Electric Railway bridge: Operations con-
sisted of completion of construction by contract of the reach from
station 560+00 to station 570+00, in February 1954. The costs
from regular funds for new work were $695,249 for work per-
formed by contract and $79 by hired labor. The total costs were
$695,328, exclusive of contributed funds.
   Los Angeles River channel, Santa Ana branch, Pacific Electric
Railway bridge to Pacific Ocean: Operations consisted of the
initiation of plans and specifications on part 4, 20th St. to Wil-
low St., 85 percent complete; part 5, Willow St. to Wardlow Rd.,
5 percent complete; part 6, Wardlow Rd. to Carson S., 5 percent
complete; and part 12, Compton Blvd. to Pacific Electric Railway,
80 percent complete. Operations also included completion of con-
struction by contract of the reach from Pacific Ocean to Seventh
St., December 1953. Plans and specifications were completed and
construction by continuing contract initiated in April 1954 on the
reach from Seventh St. to 20th St. and is complete. The costs from
regular funds for new work were $1,711,357 for work performed
by contract and $213,790 for work performed by hired labor.
The total costs were $1,925,147.
   Los Angeles River channel, Long Beach Boulevard: No opera-
tions were performed during the fiscal year.
   Haines Canyon: Operations consisted of maintaining the chan-
nel and debris basin in good operating condition. The costs from
regular funds were $293 for maintenance performed by hired
labor.
   No major storms occurred in this area, and deposit of detrital
material in the basin was negligible.
   Sycamore Wash: No operations were performed. during they
fiscal year. No major storms occurred in this area during the:
fiscal year.
1278     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Verdugo Wash, Concord Street to Upper Canada bridge: No op-
erations were performed during the fiscal year.
   One minor storm occurred on February 13, 1954, producing a
peak discharge of 1,300 c.f.s., which is approximately 7 percent
of channel capacity.
   Compton Creek, Alameda Street to Main Street: Operations
consisted of maintaining the channel in good operating condition
from Hooper Avenue storm drain to Main Street and of preparing
the operation and maintenance manual for the channel from
Hooper Avenue storm drain to Main Street. The costs from regu-
lar funds were $646 for new work and $2,587 for maintenance, all
work performed by hired labor. The total costs were $3,233.
   Three minor storms occurred on November 14, 1953, January
19, and February 13, 1954, producing peak discharges of 1,360
c.f.s., 1,670 c.f.s., and 3,600 c.f.s., of which the maximum peak
was approximately 40 percent of channel capacity.
   Lopez flood control basin: Operations consisted of completion
of the project plan and preparation of contract plans and specifica-
tions. Construction of the dam, by contract was initiated in April
1954 and is 15 percent complete. The costs from regular funds
for new work were $174,837 for work performed by contract and
$47,744 for hired labor. The total costs were $222,581.
   Pacoima Wash channel: Operations consisted of completion by
contract of the reach from Tujunga Wash to Arleta Avenue in
December 1953. Construction by continuing contract on the reach
from Arleta Avenue to Lopez flood control basin was completed in
April 1954. The operational maintenance manual is being pre-
pared. The costs from regular funds for new work were $1,960,208
for work performed by contract and $11,403 by hired labor. The
total costs were $1,971,611, exclusive of contributed funds.
   Tujunga Wash channel: Operations consisted of preparation
of operations and maintenance manual. The costs from regular
funds for new work were -$981 for hired labor. The total costs
were -$981, exclusive of contributed funds.
   Burbank-Western system (lower): Completed in September
1949, no operation or maintenance work was required in fiscal
year 1954.
                   SAN GABRIEL RIVER BASIN
   Santa Fe flood control basin: Operations consisted of maintain-
ing the dam in good operating condition, installation of metering
apparatus, and preparation of operation and maintenance manual.
The costs from regular funds were $1,056 for new work and $21,-
065 for maintenance by hired labor. The total costs were $22,121.
   A maximum inflow into reservoir of 170 c.f.s. occurred on March
30, 1954. Release from reservoir was for spreading only. The
maximum water in storage was 904 acre-feet, or 3 percent of the
gross storage capacity at spillway crest.
   Whittier Narrows flood control basin: Operations were as fol-
lows: Road and utility relocations were continued. Construction
of the central embankment, the Rosemead ramp and paving and the
San Gabriel River approach channel were completed by contract
in March 1954; the first phase of the San Jose diversion channel
          FLOOD CONTROL-LOS ANGELES, CALIF., DISTRICT          1279
and the flood-flow channel were completed in April 1954. Reser-
voir clearing by contract was started in February 1954 and com-
pleted in June 1954. Construction of the west embankment, out-
let works, Rio Hondo approach channel and the final phase of the
San Jose diversion channel was initiated by continuing contract in
April 1954 and is about 8 percent complete. The costs from regu-
lar funds for new work were $3,341,153 for work performed by
contract, and $224,215 for hired labor. The total costs were
$3,565,368, exclusive of contributed funds.
   Emerald Wash and Live Oak Wash: Operations consisted of
preparation of operation and maintenance manual. The costs
from regular funds were -$2,227 for new work performed by
contract and $242 for new work performed by hired labor. The
total costs were -$1,985, exclusive of contributed funds.
                        RIO HONDO BASIN
   Alhambra Wash: Operations performed during the fiscal year
were maintaining the channel in good operating condition. The
costs from regular funds for maintenance were $3,054 for hired
labor.
   One minor storm occurred on February 13, 1954, producing a
peak discharge of 2,400 c.f.s., which is approximately 20 percent
of channel capacity.
   Arcadia Wash: Operations performed during the fiscal year on
the project, which consists of one main flood channel, three trib-
utary channels, and three debris basins, Carter, Auburn, and
Bailey, were the initiation of the project plan and the plans and
specifications. The plans and specifications on Part 1 (Rio Hondo
to Huntington Place) are 5 percent complete. Plans and specifica-
tions for the three debris basins are 80 percent complete. The
costs from regular funds for new work were $174 for work per-
formed by contract and $64,140 for work performed by hired
labor. The total costs were $64,314.
   Eaton Wash: Operations performed during the fiscal year con-
sisted of preparation of the project plan including the plan on
Sierra Madre Villa channel, and completion of plans and speci-
fications for the Pacific Electric Railway bridge. The project
plan and specifications on Part 1 (Rio Hondo to Encinita Ave.)
were started and are 18 percent complete. The costs from regu-
lar funds for new work were $59,418 for work performed by hired
labor.
   Rio Hondo Channel (Upper) Santa Fe Railway to Whittier Nar-
rows flood control basin: Operations during the fiscal year consisted
of initiation of the project plan which is 45 percent complete. The
costs from regular funds for new work were $616 for work per-
formed by contract and $46,572 for hired labor. The total costs
were $47,188.
   Rio Hondo channel (Lower) Whittier Narrows flood control
basin to Los Angeles River: Operations performed during the
fiscal year were as follows: plans and specifications for Part 3
 (Washington Blvd. to the Santa Ana Freeway) were completed.
Plans and specifications for Part 4 (Washington Blvd. to Whittier


     Sig 41-1279-1310
1280      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Narrows reservoir) were initiated and are 95 percent complete.
Construction was completed in January 1954 of Part 2 (Southern
Pacific Railroad to Santa Ana Freeway). Construction by con-
tinuing contract of the channel improvement on Part 3 (Washing-
ton Blvd. to Santa Ana Freeway) was initiated in May 1954. The
costs from regular funds for new work were $2,235,746 for work
performed by contract and $100,729 for hired labor. The total
costs were $2,336,505, exclusive of contributed funds.
   Rubio Canyon diversion: Operations performed during the fiscal
year consisted of initiation of work on the project plan. The
costs from regular funds for new work were $5,000 for work per-
formed by hired labor.
   Santa Anita Wash: Operations performed during the fiscal year
were initiation of the project plan and initiating of a contract for
instrumental surveys. The costs from regular funds for new work
were $23 for work performed by hired labor.
   Sawpit Wash: Operations performed during the fiscal year on
the project which consists of a flood channel and debris basin were
the initiation of the project plan and completion of the contract
plans and specifications for the debris basin. The costs from reg-
ular funds for new work were $44,790 for work performed by
hired labor.
                      BALLONA CREEK BASIN
   Ballona Creek Channel and Jetties. Operations consisted of
maintaining the channel and jetties in good operating conditions.
The costs from regular funds for maintenance were $4,030 for
work performed by hired labor.
   Two minor and one moderate storm occurred on November 14,
1953, and January 19, and February 13, 1954, producing the fol-
lowing peak discharges of 6,700 c.f.s., 6,400 c.f.s., and 18,900 c.f.s.
The maximum discharge was approximately 51 percent of channel
capacity.
   Centinela Creek. Operations consisted of initiation of the project
plan, which is 30 percent complete. The costs from regular funds
were $9,107 for new work performed by hired labor.
   Sawtelle-Westwood System. Operations consisted of initiation
of the project plan, for which plans are 30 percent complete. Con-
tract plans and specifications on part 4 (Charnock Road to Na-
tional Boulevard) are 20 percent complete. The costs from regu-
lar funds for new work were $18,207 for work performed by hired
labor.
   Condition at the end of fiscal year.

                    LOS ANGELES RIVER BASIN
   Hansen flood control basin. The dam was completed in 1941.
Work remaining consists of reimbursement to local interests for
rights-of-way.
   Sepulveda flood control basin. The dam was completed in 1941.
Work remaining consists of reimbursement to local interests for
rights-of-way.
          FLOOD CONTROL-LOS ANGELES, CALIF., DISTRICT         1281
   Los Angeles River channel-Owensmouth Avenue to Lanker-
shim Boulevard.
   a. Owensmouth Avenue to Sepulveda flood control basin. The
project plan and contract plans and specifications on the reach
from Sepulveda Reservoir to Reseda Boulevard were completed
and construction by contract has been initiated. Work remaining
consists of completing construction of the reach from Sepulveda
Reservoir to Reseda Boulevard and completing the contract plans
and specifications, and construction, of the reach from Owensmouth
Avenue to Reseda Boulevard.
   b. Sepulveda flood control basin to Tujunga Wash. Construc-
tion was completed in 1953. No work remains to be done.
   c. Tujunga Wash to Lankershim Boulevard.             Construction
was completed in 1949. No work remains to be done.
   Los Angeles River channel-Lankershim Boulevard to Stewart
and Gray Road. The channel from Lankershim Boulevard to
Niagara Street was completed in 1948. Channel improvement
and bridge reconstruction from Niagara Street to Dayton Avenue
Bridge, except the Burbank-Western side drainage channel were
completed in 1939. The inlet structure for Burbank-Western
channel was completed in 1940; Dayton Avenue Bridge to Arroyo
Seco in 1940; Arroyo Seco to North Broadway in 1942; North
Broadway to Aliso Street in 1943; Fourth Street to 23d Street
in 1940; 23rd Street to Downey Road in 1940; Downey Road to
Atlantic Avenue in 1940; Atlantic Avenue to Randolph Street
in 1942; Randolph Street to Stewart and Gray Road in 1942;
except reconstruction of Firestone Boulevard Bridge, which was
completed in 1949. Channel stabilizers between Stewart and
Gray Road and Randolph Street were completed in 1940; and three
additional stabilizers were constructed in 1944. Two stabilizers
were constructed by hired labor in 1949 between Los Feliz Boule-
vard and Verdugo Wash. Work remaining to be done consists
of reimbursement to local interests for rights-of-way, completion
of repairs to Spring Street, replacing unreinforced invert, North
Broadway to Aliso, completion of plans and specifications and con-
struction for paving soft-bottom sections, Victory Boulevard to
Dayton Avenue, and Soto Street to Stewart and Gray Road.
   Los Angeles River channel-Stewart and Gray Road to Santa
Ana branch, Pacific Electric Railway bridge. The project plan
and contract plans and specifications have been completed. Con-
struction by contract of the reach from Stewart and Gray Road
to Imperial Highway was completed in December 1951 and the
reach from Imperial Highway to station 570 was completed in
November 1951. Construction by continuing contract of the reach
from station 570 to station 560 was completed in February 1954.
No work remains to be done.
   Los Angeles River channel-Santa Ana branch, Pacific Electric
Railway to Pacific Ocean. Preparation of the project plan is
partially complete. Construction on the reach from Pacific Ocean
to Seventh Street was completed in February 1954. Contract
plans and specifications are partially complete on the reaches
from. 20th Street to Carson Street, and the reach from Compton
Boulevard to Pacific Electric Railway. Construction has been
1282     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

initiated on the reach from Seventh Street to 20th Street. Work
remaining consists of completion of project plan, contract plans
and specifications, and construction.
   Los Angeles River channel-Long Beach Boulevard: Removal
of a constriction caused by silt deposit at this point was completed
in 1938. No work remains to be done.
   Haines Canyon: This unit was completed in 1938. Work re-
maining consists of reimbursements to local interests for rights-
of-way.
   Sycamore Wash: This unit was completed in 1938. Work re-
maining consists of reimbursements to local interests for rights-
of-way.
   Verdugo Wash-Concord Street to Upper Canada Bridge: This
unit was completed in 1939. Work remaining consists of reim-
bursements to local interests for rights-of-way.
   Compton Creek channel-Alameda Street to Hooper Avenue
storm drain: This unit was completed in 1939. Work remaining
consists of reimbursements to local interests for rights-of-way.
   Compton Creek channel-Hooper Avenue storm drain to Main
Street: The unit was completed in 1951. Construction by continu-
ing contract of the reach from Hooper Avenue storm drain to
Lanzit Avenue was completed in January 1951. Construction by
contract of the reach from Lanzit Avenue to Main Street was
completed in November 1951. No work remains to be done.
   Lopez flood control basin: The project plan and contract plans
and specifications have been completed. Construction by continu-
ing contract of the embankment spillway, completion of outlet
works and relocation of Maclay Street was initiated in April 1954
and is 18 percent complete. Work remaining consists of comple-
tion of construction.
   Pacoima Wash channel: The project plan and contract plans
and specifications have been completed. Construction by continu-
ing contracts of the reach from Tujunga Wash to Arleta Avenue
was initiated in December 1952, and from Arleta Avenue to Lopez
flood control basin, in June 1953.
   Tujunga Wash channel: This unit was completed in 1951. Con-
struction by contract of the reach from Los Angeles River to Mag-
nolia Boulevard was completed in February 1950. Construction
by continuing contract of the. reach from Magnolia Boulevard to
Vanowen Street was completed in January 1951. Construction by
contract of the reach from Vanowen Street to Beachy Avenue was
completed in November 1951. Construction by continuing contract
of the reach from Beachy Avenue to Hansen flood control basin
was completed in February 1952. No work remains to be done.
   Burbank-Western System (lower) : This unit was completed in
1949. No work remains to be done.
                   SAN GABRIEL RIVER BASIN
  Santa Fe flood control basin: This unit was completed in 1948.
Work remaining consists of preparation of recreational planning
report and maintenance manual, and rights-of-way transactions.
   San Gabriel River channel-San Gabriel Canyon to Santa Fe
flood control basin: This unit was completed in 1947. Repair work
         FLOOD CONTROL--LOS ANGELES, CALIF., DISTRICT          1283
to the existing right bank levee to protect against flanking of Santa
Fe flood control basin was completed in 1943. No work remains to
be done.
   Whittier Narrows flood control basin: This unit is about 70 per-
cent complete. The project plan and contract plans and specifica-
tions have been completed. Constru'ction of Workman Mill Road
Bridge was completed in October 1952. Construction of Rosemead
Boulevard Bridge was completed in December 1952. Construc-
tion on the central embankment, Rosemead ramp and paving, and
the San Gabriel River approach channel were completed by con-
tract in March 1954; the first phase of the San Jose diversion
channel and the flood-flow channel were completed in April 1954.
Reservoir clearing by contract was completed in June 1954. Con-
struction of the west embankment, outlet works, Rio Hondo ap-
proach channel and the final phase of the San Jose diversion chan-
nel was initiated by continuing contract in April 1954 and is about
8 percent complete. Work remaining consists of completion of
the west embankment, outlet works, Rio Hondo approach channel,
final phase of the San Jose diversion channel, road and utility re-
locations, protection work for oil wells and an oil refinery, opera-
tor's quarters and operational buildings and installation of spill-
way gates and operating equipment.
   Emerald Wash and Live Oak Wash: This unit is about 14 per-
cent completed. The project plan and contract plans and specifica-
tions have been completed for the reach from A Street to D Street.
Construction by continuing contract of the reach from A Street
to D Street was completed in December 1950. Work remaining
consists of completing the project plan and contract plans and
specifications, and construction of the remainder of the channel.
                        RIO HONDO BASIN
   Alhambra Wash: This unit was completed in 1939. Work re-
maining consists of reimbursements to local interests for rights-
of-way.
   Rio Hondo channel-Santa Fe Railway to Whittier Narrows
flood control basin: Work has not been commenced. Work remain-
ing consists of preparation of the project plan and contract plans
and specifications, and construction.
   Rio Hondo channel-Whittier Narrows flood control basin to
Los Angeles: This unit is about 48 percent complete. Construc-
tion by contract of the reach from Union Pacific Railroad to
Southern Pacific Railway was completed in December 1951. Con-
struction by contract of the reach from Southern Pacific Railway
to Santa Ana Freeway was completed in January 1954. Contract
plans and specifications have been completed and construction by
continuing contract was initiated in May 1954 on the reach from
Washington Boulevard to Santa Ana Freeway. Work remaining
consists of completion of contract plans and specifications and
construction of the reach from Washington Boulevard to Whittier
Narrows Reservoir, and completion of construction of the reach
from Washington Boulevard to Santa Ana Freeway.
   Rubio Canyon diversion: Engineering studies in connection with
the project plan have been commenced. Work remaining consists
1284     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

of preparation of the project plan, contract plans, and specifica-
tions and construction.
   Eaton Wash: Engineering studies in connection with the project
plan have been commenced. Work remaining consists of prepara-
tion of the project plan, contract plans, and specifications and
construction.
                     BALLONA CREEK BASIN
   Ballona Creek channel and jetties: The channel was completed in
1939 and the jetties at the outlet in 1940. Work remaining con-
sists of reimbursements to local interests for rights-of-way.
   Sawtelle-Westwood system: This unit is about 22 percent com-
pleted. Construction by contract of the reach from Ballona Creek
to Braddock Drive was completed in November 1949. Construc-
tion by contract of the reach from Braddock Drive to Washington
Place was completed in January 1951. Construction by contract
of the reach from Washington Place to Charnock Road was com-
pleted in February 1951. Work remaining consists of preparation
of the project plan, contract plans and specifications, and construc-
tion of the remainder of the project, upstream from Charnock
Road.
                           PROJECT COSTS
  The total costs to June 30, 1954, for new work and maintenance
for the existing project are:
                                                                                                                                                               I_

                          Units                                   Regular                    Emergency               Total               Contributed           Total
                                                                                               Relief          United States funds         funds              all funds
                                                      -                        -   1
                                                                                   '    --    --          -1       -                 !                 1-




                  $70,000,000 project                                                                                                                                       0
                                                                                                                                                                            0
Alhambra, Wash_---                                              $506,615.04              $580,437.19            $1,087,052.23             $4,684.14                         0
                                                                                                                                                            $1,091,736.37
Ballona Creek Channel and Jetties-...............              1,235,474.25               509,118.38             1,744,592.63             72,201.49          1,816,794.12   O
Compton Creek, Alameda St. to Hooper Ave. Storm
  Drain -------                                                1,597,854.03                  745,848.82          2,343,702.85             25,408.90          2,369,111.75
Haines Canyon         _            ---                    - 1    290,330.43                  233,953.57            524,284.00                                               0
                                                                                                                                                               524,284.00   O



Hansen flood control basin_- -                                11,359,680.05                                     11,359,680.05                               11,359,680.05
Los Angeles River channel:
     Lankershim Blvd. to Stewart and Gray Rd .---                                                                                                                           0
                                                              32,299,680.18            7,638,038.67             39,937,718.85            -1,302.04          39,936,416.81
     Long Beach Blvd--------------                    - -          13,678.41              20,565.98                 34,244.39                                   34,244.39
Plant_        -----------------------------                                              217,754.88                217,754.88                                  217,754.88
San Gabriel River Channel:
                                                                                                                                                                            r
     San Gabriel Canyon to Santa Fe flood control basin        1,900,626.68                   44,686.32          1,945,313.00                                1,945,313.00
     Santa Fe flood control basin to Walnut Creek----                                                                                                                       H
                                                                  32,263.51                                         32,263.51                                   32,263.51
Santa Fe flood control basin__-    --      ----   -     ---   12,637,097.44                                     12,637,097.44                               12,637,097.44
Sepulveda flood control basin-- -----------         - -        6,651,517.63                                      6,651,517.63                                6,651,517.63
Surveys and engineering_-------- -                               353,893.14                   24,000.00            377,893.14                                  377,893.14
Sycamore, Wash_--------------------------------                     8,835.10                  14,710.43             23,545.53                                   23,545.43
Verdugo, Wash., Concord St. to Upper Canada Bridge-_             367,804.52                  362,557.41            730,361.93            155,120.89            885,482.82

      Subtotal-New work                           -            69,255,350.41           10,391,671.65            79,647,022.06            256,113.38         79,903,135.44
      Subtotal-Maintenance_. -             -   -- -       --    1,756,169.81                                     1,756,169.81                                1,756,169.81
      Subtotal-All work_-------------------_                   71,011,520.22           10,391,671.65            81,403,191.87            256,113.38         81,659,305.25
                                                                 Regular            Emergency               Total            Contributed        Total
                          Units                                                       Relief          United States funds      funds          all funds


           Projects outside $70,000,000 project
Arcadia, Wash---_-----_   - --  -                               $64,314.00                                 $64,314.00                          $64,314.00
Burbank-Western system _______________________                1,421,864.17                              1,421,864.17                         1,421,864.17    0
Centinela Creek_-                                                 9,107.05                                  9,107.05                             9,107.05
                                                                              --    --   -   --   -
Compton Creek, Hooper Ave. storm drain to Main St__           1,202,964.64                              1,202,964.64         362,937.46      1,565,902.10    o
Eaton, Wash ------------------------------------                 62,862.52                                 62,862.52                            62,862.52
Emerald, Wash. and Live Oak, Wash----------------               395,020.44                                395,020,44          50,209.86        445,230.30    Q




Lopez flood control basin__-         -________-__-__--
                                                  ____                                                                                                       O
                                                                304,425.60                                304,425.60                           304,425.60
Los Angeles River Channel:
    Owensmouth Ave. to Lankershim Blvd----------              9,918,676.56                              9,918,676.56        1,180,739.22    11,099,415.78
    Pacific Electric Ry. bridge to Pacific Ocean---...        2,699,212.95                              2,699,212.95                         2,699,212.95
    Stewart and Gray Road to Pacific Electric Ry.                                                                                                            M


                                                                                                                                                             z
      bridge-           --                  --------          5,868,677.95                              5,868,677.95                         6,181,484.01
Pacoima, Wash. channel----------------------                  3,179,169.94                              3,179,169.94                         4,082,047.00
Rio Hondo Channel:
    Whittier Narrows to Los Angeles River -....               4,316,396.57                              4,316,396.57                         4,797,163.67
Rubio Canyon Diversion__                                          5,000.00                                  5,000.00                             5,000.00
Santa Anita .........                                                22.96                                     22.96                                22.96
San Gabriel River channel: Walnut Creek to Pacific
  Ocean-                   -----------------------       -        6,108.51                                  6,108.51                             6,108.51
                                                                                                                                                             C2
Sawpit, Wash---------                                            44,789.89     --                          44,789.89                            44,789.89    oo
Sawtelle-Westwood system ___-__ _______________               2,176,273.72                              2,176,273.72          102,432.04     2,278,705.76
Tujunga, Wash. channel-                                       7,358,991.61                    _         7,358,991.61        2,286,305.13     9,645,296.74    co
Whittier Narrows flood control basin _                       22,840,410.83                             22,840,410.83           8,634.98     22,849,045.81

       Subtotal---New work --                        -       61,874,289.91 ..--------------61,874,289.91                    5,687,708.91    67,561,998.82

'-'~----- Grand total_    --------------                     132,885,810.13    10,391,671.65
                                                                                        -             1.43,277,481.78       5,943,822.29   149,221,304.07
                                                                                                                                           -- ~----~- ~~~.
       Subtotal--New work_
       Grand    total
               FLOOD CONTROL-LOS ANGELES, CALIF., DISTRICT                                              1287
                                      Cost and financialsummary
                                            CONSOLIDATED



                                              Fiscal year ending June 30                        Total to June
                                                                                                30, 1954, includ-
                                                                                                ing fiscal years
                               1950          1951         1952         1953          1954        priorto 1950


New work:
   Appropriated-_- _      $11,893,755    $14,610,325 $10, 826,585 $13,092,212 $12, 235,170         $176,049,977
   Cost ---------------      8,561,983    14,045,681   15,271, 184   8,401, 854   13, 081,150      1168, 406, 613
Maintenance:
   Appropriated --------       140,000       107,725      154,950      121,548       129,000           1, 775, 751
   Cost-----.......     --     169,791        97,959      138,119      130,056       127,516           1,756,170


SIncludes $141,227 plant cost adjustment.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954--_-------   $3,033,857
    Appropriated for succeeding fiscal year ending June 30, 1955_     12,000,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955-----------       ---------------------------- 15,033,857
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project--------     ------------------ --- 278,361,311

  11. SANTA ANA RIVER BASIN AND ORANGE COUNTY, CALIF.
    Location. These works are on the Santa Ana River and tribu-
taries and other streams in Orange, Riverside, and San Bernar-
dino Counties.
   Existing project. The Flood Control Act approved June 22,
1936, authorized the construction of reservoirs and related flood
control works for the protection of the metropolitan area of
Orange County, at an estimated construction cost not to exceed
$13,000,000.    The Flood Control Act approved June 28, 1938,
modified the project to provide for the control of floods on San
Antonio and Chino Creeks, in accordance with plans approved by
the Chief of Engineers, and authorized $6,500,000, for initiation
and partial accomplishment of the plans for those creeks. (See
H. Doc. 688, 75th Congress, 3d sess.) The Flood Control Act
approved August 18, 1941, authorized the amount of $2,500,000,
in addition to previous authorizations, for the prosecution of the
projects approved in the above-mentioned flood control acts, for
flood control in the Santa Ana River Basin, and for the protec-
tion of Orange County, Calif. The Flood Control Act approved
December 22, 1944, authorized the amount of $10,000,000 in ad-
dition to previous authorizations for the prosecution of the proj-
ects adopted in the above-mentioned flood control acts, includ-
ing the projects on Lytle and Cajon Creeks for local flood protec-
tion at San Bernardino and Colton, Calif., in accordance with
the recommendations contained in the report of the Chief of Engi-
neers dated February 11, 1944.     (See H. Doc. 534, 78th Cong.,
2d sess.)
   The individual parts considered in the general plan for this
project and their estimated Federal costs (1954) are as follows:
1288             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


                                                                                              Estimated cost

                             Project                                                           Relocations,
                                                                      Construction             lands, ease-           Total
                                                                                               ments, and
                                                                                              rights-of-way

Lytle and Cajon Creeks channel improvements 2.---...                       $6, 834, 358             $779, 000          $7, 613, 358
San Antonio Dam 1.-..--                                  --             5, 044, 700                2, 295, 300          7, 340, 000
San Antonio and Chino Creeks channel 1._'_--- ..--..                     8, 517, 500               2, 982, 500         11.600, 000
Prado Dam 2-             _ _......                                       6, 051, 944               3, 511, 456          9, 563, 400
Carbon Canyon dam and channel-_-. .....       .........                  4, 082, 000               1, 648, 000          5, 730,000
Fullerton Dam 1.                                                            373, 146                   37, 954             411,100
Brea Dam 12-                                                                968, 800                  221, 200          1, 190, 000
Villa Park Dam--_,                                                      2, 076, 000                   100, 000          2, 176, 000
Aliso Creek Dam                                                             311, 000
                                                    ...-----------------------------------             15, 000             326, 000
T rabuco D am- . . . . . .         . . ......                .          2, 073, 000                    30, 000          2, 103, 000
San Juan Dam......------------------------------------                  5, 526, 000                  200, 000           5, 726, 000


  1 For details of this project, see individual report.
  2 Completed.



   Local cooperation. See individual reports for requirements.
   Operations and results during fiscal year. All work during the
fiscal year is applicable to and described under the individual
project items.
   Condition at end of fiscal year. The progress of projects se-
lected for construction under this authorization is given in indi-
vidual reports. The total cost and expenditures for new work
not transferred to individual project items were $85,310.42 from
regular funds.
                                            Cost and financial summary

                                                      Fiscal year ending June 30                                 Total to June
                                                                                                                 30, 1954, includ-
                                                                                                                 ing fiscal years
                                     1950           1951            1952            1953             1954         priorto 1950

New work;
    Appropriated     -                                          -    --             --    -             -                 $85, 310
        ..........
    Cost-------------             ----------------------------              --......------------    ------------           85,310


12. SAN ANTONIO DAM, SANTA ANA RIVER BASIN, AND ORANGE
                     COUNTY, CALIF.
  Location. The site of the improvement is on San Antonio
Creek, in San Bernardino and Los Angeles Counties, Calif., ap-
proximately 7.5 miles north of Pomona, Calif.
  Existing project. This unit is a part of the general plan for
protection of the metropolitan areas in Orange County. The plan
provides for an earth-fill dam with a crest elevation of 2,260
feet, height above stream bed 160 feet, and length of crest 3,850
feet, with a reservoir capacity of 9,110 acre-feet at spillway crest,
at the mouth of San Antonio Canyon. The latest (1954) approved
estimate cost is $5,044,700 for construction and $2,295,300 for
lands and damages and relocations, a total of $7,340,000 for new
work. The latest (1954) approved estimated cost for mainte-
nance is $20,600. The improvement was authorized by the Flood
Control Act approved June 28, 1938. (See H. Doc. 688, 75th
Cong., 3d sess.)
  Local cooperation. None required.
                FLOOD CONTROL-LOS ANGELES, CALIF., DISTRICT                                            1289
   Operationsand results during fiscal year. Operations consisted
of completion of contract plans and specifications, continuation
of utility relocations and completion of land acquisitions. Con-
struction of the dam embankment, spillway and second (and final)
stage of the outlet works by continuing contract was initiated
in March 1954. The costs from regular funds for new work were
$1,757,764 for work performed by contract and $100,540 for hired
labor. The total costs were $1,858,304.
   Condition at end of fiscal year. This project is about 47 per-
cent completed. The project plan and contract plans and speci-
fications have been completed. Construction by contract of unit
No. 1 of the outlet works was completed in February 1953. Work
remaining consists of completion of utility and highway reloca-
tions and completion of construction of outlet works, dam em-
bankment, and spillway. The total costs from regular funds to
June 30, 1954, were $3,467,598 for new work.
                                      Cost and financial summary

                                             Fiscal year ending June 30                        Total to June
                                                                                               30, 1954, includ-
                                                                                               ing fiscal years
                               1950        1951          1952         1953          1954        prior to 1950 1


New work:
   Appropriated-..                        $525, 000   $1, 000, 000   $995, 000   $1,700, 000         $4, 500, 000
   Cost --------------
               .......         $3, 075      63, 702      550,509      776,583     1,858,304          3, 467,598


  1In addition $8,500 for new work was performed with contributed funds. Includes $5,000 working
funds.   This work is in addition to existing project.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_-----------      $515,759
    Appropriated for succeeding fiscal year ending June 30, 1955_         2,300,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955         --------------------------------------             2,815,759
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project_                        -                 540,000

       13. SAN ANTONIO AND CHINO CREEKS CHANNEL
    SANTA ANA RIVER BASIN, AND ORANGE COUNTY, CALIF.

   Location. The site of improvement is in San Bernardino and
Los Angeles Counties, Calif., about 30 miles east of the city of
Los Angeles. The channel, with its source in the San Gabriel
Mountains would extend from San Antonio Dam about 15 miles
to the existing Prado reservoir on Santa Ana River.
   Existing project. This unit is a part of the general plan for
protection of the metropolitan areas in Orange County. The plan
of improvement provides for a concrete-lined, rectangular sec-
tion about 7.1 miles in length and ranging in width from 20 to
30 feet along San Antonio Creek, and a trapezoidal section about
7.9 miles in length and ranging in width from 140 to 160 feet
with grouted stone-faced side slopes along Chino Creek below
the junction of Chino and San Antonio Creeks, 29 highway bridges,
4 railroad bridges, and one combination highway and railroad
bridge. The latest (1954) approved estimated cost of construc-
tion is $8,517,500 and $2,982,500 for lands and damages, and re-
1290              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

locations, a total of $11,500,000. The improvement was authorized
by Flood Control Act approved June 28, 1938. (See H. Doc. 688,
75th Cong., 3d sess.)
  Local cooperation. None required.
   Operations and results during fiscal year. Operations consisted
of preparation of the project plan. The costs from regular funds
for new work were $76,184 by hired labor.
   Condition at end of fiscal year. The project plan is nearly com-
pleted. Work remaining consists of completing the project plan,
contract plans and specifications and construction. The total costs
from regular funds for new work to June 30, 1954 were $141,184.
                                                  Cost and financial summary

                                                                Fiscal year ending June 30                  Total to June
                                                                                                           30, 1954, includ-
                                                                                                           ing fiscal years
                                           1950               1951        1952         1953      1954       priorto 1950

New work:
   Appropriated-------------------..------------                                       $65,000   $85,000           $150, 000
   Cost...---           ------------             --------------------            -      65,000    76,184            141,184


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954                   $8, 500
    Appropriated for succeeding fiscal year ending June 30, 1955   - -.
                                                                      -     80,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955----------------------------------------                 88,500
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project                               _
                                        ---------------------------
                                         _                        _     11,270,000

                14. PRADO DAM, SANTA ANA RIVER BASIN, AND
                           ORANGE COUNTY, CALIF.

   Location. The site of the improvement is in Riverside County,
on the Santa Ana River, approximately 30 miles above the mouth.
   Existing project. This plan of improvement is a unit of the
general plan for protection of the metropolitan area in Orange
County.
   The plan of improvement provides for a rolled earthfill dam,
2,280 feet long, maximum height 106 feet above streambed with a
total basin capacity of 223,000 acre-feet at spillway crest. The
operation of the basin regulates the runoff from a tributary area
of 2,264 square miles, reducing the flow of the design flood from
193,000 to 9,200 cubic feet per second. The latest (1954) ap-
proved estimated cost is $9,597,377. The improvement was author-
ized by the Flood Control Act approved June 22, 1936.
   Local cooperation. None required.
   Operationsand results during fiscal year. Operations consisted
of rights-of-way transactions, preparation of a recreational plan-
ning report, and maintaining the dam in good operating condition.
The costs from regular funds were $25 for new work and $24,-
587 for maintenance, a total cost of $24,612 for work performed
by hired labor.
                        FLOOD CONTROL-LOS ANGELES, CALIF., DISTRICT                                                        1291
  Condition at end of fiscal year. The dam was completed in 1941.
Work remaining consists of preparation of recreational planning
report. The costs for the existing project to June 30, 1954, were
as follows:

                                                                                                      Costs
                              Funds
                                                                                New work           Maintenance          Total

Regular funds......-----------------------------------                              $9, 473, 272       $420, 842        $9, 894, 114
Contributed funds----------------------------------                                    124, 105 ----------------            124, 105
      Total_        .     .       ..--------------------------------------           9, 597, 377        420, 842        10, 018, 219



                                               Cost and financial summary

                                                             Fiscal year ending June 30                            Total to June
                                                                                                                   30, 1954, includ-
                                                                                                                   ing fiscal years
                                        1950            1951                 1952           1953        1954        priorto 1950 1


New work:
   Appropriated -------........--....                        ------------
                                                                       $137,612       -----------------------           $9, 473 272
   Cost----------------              $13,103            $12,223               1,530          $1,348           25          9,473,272
Maintenance:
   Appropriated-.......                  30,000           33,255             23,600          28,400      25,000             421,255
   Cost. -------------                   31,016           31,392             23,526          3,0337      24, 587            420,842


1 In addition $124,105 for new work was performed with contributed funds.

           15. FULLERTON DAM, SANTA ANA RIVER BASIN, AND
                       ORANGE COUNTY, CALIF.
   Location. The site of the improvement is in Orange County, 2
miles northeast of the city of Fullerton, on East Fullerton Creek,
approximately 4 miles above its junction with Brea Creek.
   Existing project. This is a unit of the general plan for pro-
tection of the metropolitan area in Orange County. The plan of
improvement provides for a rolled earthfill dam 575 feet long,
maximum height 47 feet above streambed with basin capacity of
775 acre-feet at spillway crest. The operation of the basin regu-
lates the runoff from a tributary area of 5.05 square miles, reduc-
ing the flow of a design flood from 4,600 to 240 cubic feet per
second. The latest (1954) approved estimated cost is $373,146
for construction and $37,954 for acquisition of lands and reloca-
tion of highways. This improvement was authorized by the Flood
Control Act approved June 22, 1936.
   Local cooperation. None required.
   Operationsand results during fiscal year. Operations consisted
of maintaining the dam in good operating condition. The costs
from regular funds were $8,752 for maintenance performed by
hired labor.
   Condition at end of fiscal year. The dam was completed in 1941.
Work remaining consists of preparation of the recreational plan-
ning report. The total costs to June 30, 1954, were $411,076 for
new work, and $144,249 for maintenance, a total cost of $555,325.
1292           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                            Cost and financial summary

                                                         Fiscal year ending June 30                          Total to June
                                                                                                            30, 1954, includ-
                                                                                                            ing fiscal years
                                    1950               1951        1952        1953              1954         priorto 1950


New work:
   Appropriated    .--------------------------------                           --$1,380    __---
                                                                                           ---                      $411,076
   Cost-------------                            ------------           ---------------------                         411,076
Maintenance:
   Appropriated_                      9, 500
                                     $--------          $8, 755    $10, 300     11,416            $7, 750            145, 221
   Cost-----------------              9,484              6, 819      9, 784     11,910             8,752             144,249



            16. BREA DAM, SANTA ANA RIVER BASIN, AND
                       ORANGE COUNTY, CALIF.

   Location. The site of the improvement is in Orange County, 1.5
miles north of Fullerton on Brea Creek, approximately 8 miles
above its junction with Coyote Creek.
   Existing project. This is a unit of the general plan for protec-
tion of the metropolitan area in Orange County. The plan of im-
provement provides for a rolled earthfill dam approximately 1,765
feet long, maximum height 87 feet above streambed, with basin
capacity of 4,100 acre-feet at spillway crest. The operation of
the basin regulates the runoff from a tributary area of 23.4 square
miles, reducing the flow of a design flood from 8,300 to 1,330 cubic
feet per second. The latest (1954) approved estimated cost is
$968,800 for construction and $221,200 for acquisition of lands.
This improvement was authorized by the Flood Control Act ap-
proved June 22, 1936.
   Local cooperation. None required.
   Operationsand results during fiscal year. Operations consisted
of maintaining the dam in good operation condition. The costs
from regular funds were $15,149 for maintenance performed by
hired labor.
   Condition at end of fiscal year. The dam was completed in 1942.
Work remaining consists of preparation of the recreational plan-
ning report. The total costs from regular funds to June 30, 1954,
were $1,189,068 for new work and $202,875 for maintenance, a
total cost of $1,391,943.
                                            Cost and financial summary

                                                        Fiscal year ending June 30                          Total to June
                                                                                                            30, 1954, includ-
                                                                                                            ing fiscal years
                                   1950                1951       1952         1953              1954         priorto 1950


New work:
   Appropriated--_--------------
   Cost-----------------                 $32
                                                ---------------- ----
                                                       $96 -.......... ,
                                                                                -$844----------
                                                                                     ..
                                                                                      844--- -      .
                                                                                                                 $1,189,068
                                                                                                                   1, 189,068
Maintenance:
   Appropriated .      .--..         17, 500           11,265     $19, 250      13,336           14,250             203,101
   Cost   ------------               17,500            11,265      17,015       14,446           15, 149            202, 875
              FLOOD CONTROL--LOS ANGELES, CALIF., DISTRICT                                            1293
17. CARBON CANYON DAM AND CHANNEL, SANTA ANA RIVER
           BASIN, AND ORANGE COUNTY, CALIF.
    Location. The site of the improvement is in Orange County, on
Carbon Creek near the mouth of Carbon Creek Canyon, and about
4 miles east of Brea, California.
    Existing project. This unit is a part of the general plan for
protection of the metropolitan areas in Orange County.
    The tentative plan of improvement provides for a rolled earth-
fill dam, 1,600 feet long, maximum height 90 feet above streambed,
with basin capacity of 7,000 acre-feet. The operation of the basin
will regulate the runoff from a tributary area of 20 square miles.
    The plan includes construction below the dam of a reinforced
concrete channel approximately 3,500 feet long with a capacity of
about 4,000 cubic feet per second. The current (1954) approved
estimated cost of the dam and channel is $4,082,000 for construc-
tion and $1,648,000 for relocations, lands, easements and rights-
of-way.
    Operations and results during fiscal year. No operations were
performed during the fiscal year.
    Condition at end of fiscal year. The project plan is completed
partially. Work remaining consists of completion of the project
plan, preparation of contract plans and specifications, and con-
struction of the project. The total costs from regular funds for
new work to June 30, 1954, were $156,128.
                                          Cost and financial summary

                                                Fiscal year ending June 30                    Total to June
                                                                                          _   30, 1954, includ-
                                                         1                                    ing fiscal years
                                   1950        1951           1952          1953   1954        prior to 1950

New work:
                .. _.
   Appropriated __      -------.          .    $25,000       -$8,387    _                             $156,128
   Cost....----------------        $26,220     .15,584          1,029   .156,128

Other new work data: Estimated additional amount needed to be ap-
  propriated for completion of existing project--------_      _   $5,573,872

                     18. SANTA ANA RIVER BASIN, CALIF.
   Location. These works are on the Santa Ana River and tribu-
taries and other streams in Riverside and San Bernardino Counties.
  Existing project. The Flood Control Act approved May 17,
1950, authorized the plan of improvement for flood control in Santa
Ana River Basin, substantially in accordance with the recommen-
dations contained in the report of the Chief of Engineers, dated
September 27, 1948. (See H. Doc. 135, 81st Cong., 1st sess.)
1294             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  The individual units considered in the general plan for this proj-
ect and their estimated Federal costs (1954) are as follows:

                                                                                     Estimated cost

                            Project                                                   Relocations,
                                                                   Construction       lands, ease-     Total
                                                                                      ments, and
                                                                                     rights-of-way

Mill Creek levees.....---------------------------------               $1,590, 000 ----------------     $1, 590, 000
Devil, East Twin and Warm Creeks, improvements                        14, 780,000         $420, 000    15,200,000
and Lytle Creek levee.
Riverside levees- ........... ................. .--                    3, 040, 000 ----------------     3, 040, 000
San Jacinto River and Bautista Creek levees                            5, 280,000         ----------    5, 280, 000
     Totals ..     ..   .     ..      .   .   ......   _   ... .      24, 740, 000          420, 000   25,110, 000



  Local cooperation. See individual reports for requirements.
  Operations and results during fiscal year. No funds have been
appropriated.
  Condition at end of fiscal year. No work accomplished to date.
19. DEVIL, EAST TWIN, AND WARM CREEKS IMPROVEMENTS AND
    LYTLE CREEK LEVEE, SANTA ANA RIVER BASIN, CALIF.
    Location. The site of the improvements is in San Bernardino
County, Calif. The Devil Creek diversion and Lytle Creek levee
are north and northwest of San Bernardino; the Waterman and
East Twin Creeks levee revetments are northeast of San Bernar-
dino; and the East Twin and Warm Creeks concrete channel is
along the outskirts and just easterly of San Bernardino.
   Existing project. This plan of improvement provides for an
intersecting levee, 1.19 miles long, across Devil Creek (below the
mouth of Devil Creek Canyon and just north of San Bernardino)
and a concrete diversion channel, 1.90 miles long, extending from
the levee to Cajon Creek; a levee, 1.16 miles long, on the right side
of Lytle Creek opposite the mouth of Cajon Creek; revetment of
3.59 miles of levees, constructed or to be constructed by local
interests along Waterman and East Twin Creeks; and construction
of one continuous concrete channel, total length 4.15 miles, along
 (lower) East Twin Creek and (lower) Warm Creek. The latest
 (1954) approved estimated Federal cost is $15,200,000. The im-
provement was authorized by the Flood Control Act, approved
May 17, 1950. (See House Doc. 135, 81st Cong., 1st sess.)
   Local cooperation. Local interests are required to pay $200,000
of the construction cost in (zone 5) Devil, East Twin, and Warm
Creeks improvements, furnish free of cost to the United States all
lands, easements, and rights-of-way necessary for construction of
the improvements and bear the cost of all highway and highway
bridge construction and alteration, and utility relocation; adjust
all claims concerning water rights and hold and save the United
States free from all claims for damages due to the construction
works; prevent any future encroachments on the project channels;
perform any work made necessary by the effect of flood control on
stream regimen; and maintain and operate the improvement works
after completion in accordance with regulations prescribed by the
          FLOOD CONTROL--LOS ANGELES, CALIF., DISTRICT          1295;
Secretary of the Army. Local interests have not been notified of
requirements.
  Operationsand results during fiscal year. None.
  Condition at end of fiscal year. No work has been done as funds
have not been appropriated.
  20. RIVERSIDE    LEVEES, SANTA      ANA RIVER BASIN, CALIF.
   Location. The site of the improvement is in San Bernardino
and Riverside Counties, on Santa Ana River, immediately west of
Riverside, Calif.
   Existing project. This plan of improvement provides for con-
struction of two stone faced levees, total length 4.59 miles, along
Santa Ana River near Riverside, Calif., one on the left (east) side
of the river for protection of the northwest part of Riverside,
Calif., and the other on the right (west) side for the protection of
most of Rubidoux, Calif. The latest (1954) approved estimated
Federal cost is $3,040,000. The improvement was authorized by
the Flood Control Act approved May 17, 1950. (See H. Doc. 135,
81st Cong., 1st sess.)
   Local cooperation. Local interests are required to furnish free
of cost to the United States all lands, easements, and rights-of-way
necessary for construction of the improvements and bear the cost
of all highway and highway bridge construction and alteration, and
utility relocation; adjust all claims concerning water rights and hold
and save the United States free from all claims for damages due to
the construction works; prevent any future encroachments on the
project channels; perform any work made necessary by the effect
of flood control on stream regimen; and maintain and operate the
improvement works after completion in accordance with regula-
tions prescribed by the Secretary of the Army. Local interests have
not been notified of requirements.
   Operations and results during fiscal year. None.
   Condition at end of fiscal year. No work has been done as funds:
have not been appropriated.
              21. SAN DIEGO RIVER BASIN, CALIF.
   Location. The site of the improvement is on the San Diego
River at San Diego, Calif.
   Existing project. The plan of improvement provides for the
construction of a suitable levee as a replacement of the existing
Government dike across the old channel of the river, at the city of
San Diego, making use of the dike to the extent found practicable
at the time of construction, the levee would extend easterly from
Presidio Hill in Old Town, a distance of 6700 feet to a low hill
with a connecting cutoff levee extending southwest 1,000 feet to
high ground near Ingraham Street. The project would afford
added protection from floodwaters of San Diego River to facilities
and activities which are concentrated in the area between the
Government dike and San Diego Bay.
   The latest (1949) approved estimated cost is $350,000 for con-
struction and $20,000 for lands and damages.
   This improvement was authorized by the Flood Control Act ap-
126i           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

proved December 22, 1944. (.See H. Doec. 635, 77th Cong., 2d sess.)
  The River and Harbor Act approved July 24, 1946, authorized a
modification of this project. See navigation project entitled "San
Diego River and Mission Bay, Calif."
  Local cooperation. Local cooperation shown in navigation proj-
ect entitled "San Diego River and Mission Bay, Calif.," applies.
  Operationsand results during fiscal year. See navigation proj-
ect entitled "San Diego River and Mission Bay, Calif."
   Condition at end of fiscal year. See navigation project entitled
"San Diego River and Mission Bay, Calif."
   22. PAINTED              ROCK        RESERVOIR,                GILA     RIVER      BASIN,          ARIZ.
   Location. The site of the improvement is on Gila River, mile
126, about 20 miles below Gila Bend, Ariz.
   Existing project. The plan of improvement provides for a dam
and reservoir for flood control. The dam would be a rolled-fill earth
structure with a maximum height of 174 feet above streambed, a
crest length of 4,390 feet, and a detached broad-crested spillway
with a crest length of 1,050 feet. The reservoir at spillway crest
would have a gross capacity of 2,480,000 acre-feet including
200,000 acre-feet for sediment. The operation of the reservoir
would reduce the standard project flood of 320,000 cubic feet per
second to a maximum outflow of 22,500 cubic feet per second. The
latest (1954) approved estimate of cost is $25,302,000 for construc-
tion, $9,698,000 for relocations, lands, easements, and rights-of-
way; $40,000 annually for maintenance and operation. The project
was authorized by the Flood Control Act approved May 17, 1950.
 (See H. Doc. 331, 81st Cong., 1st sess.)
   Local cooperation. Local interests are required to adjust all
water rights claims that might result from the improvement and
to keep the flood channel of Gila River downstream from the
Painted Rock site free from encroachment.
   Operations and results during fiscal year. Permeability tests
were completed. The costs from regular funds for new work were
$14,723 for work performed by contract and $49,130 by hired labor.
The total costs were $63,853.
   Condition at end of fiscal year. No construction undertaken.
Work remaining consists of preparation of project plan, contract
plans and specifications and construction. The total costs from
regular funds to June 30, 1954, were $212,474.
                                        Cost and financial summary

                                                 Fiscal year ending June 30                      Total to June
                                                                                                 30, 1954, includ-
                                                                                                 ing fiscal years
                                 1950          1951           1952         1953       1954        prior to 1950

New work:
   Appropriated..       ------------------------------------              $164, 000   $65, 000           $229, 000
   Cost__--...............I__         -        -        _______-------
                                                                  -- _-    148,621     63,853             212,474


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954____------_                                      $139
    Appropriated for succeeding fiscal year ending June 30, 1955-----_                                 100,000
    Unobligated balances available for succeeding fiscal year ending
     : June 30, 1955, ----------------.                         ---      100,139
    Estimated additional amount needed to be appropriated for com-
       pletion of existing project..--.--         ..
                                          --.-.---------   --..     - 34,671,000
           FLOOD CONTROL-LOS ANGELES, CALIF., DISTRICT          1297
23. MATHEWS CANYON        RESERVOIR, COLORADO RIVER BASIN,
                                NEV.
   Location. The site of the improvement is about 20 miles east-
ward from Caliente, Nev., in Mathews Canyon, a tributary of
Clover Creek, and about 2 miles above the mouth of Mathews
Canyon.
   Existing project. The plan of improvement provides for a dam
and reservoir for flood control. The dam would be an earthfill
structure with a maximum height of 68 feet above streambed, and
a crest length of 717 feet. A 60-foot spillway, crest elevation 5,461,
would be constructed in a saddle to the left of the left abutment.
The reservoir would have a total capacity at spillway crest of 6,260
acre-feet, including 1,000 acre-feet for sediment. The operation of
the reservoir would regulate the runoff from a tributary area of 34
square miles, reducing the standard project flood from 8,500 cubic
feet per second to 221 cubic feet per second. The latest (1954) ap-
proved estimated cost is $755,000. This improvement was author-
ized by the Flood Control Act approved May 17, 1950. (See H. Doc.
530, 81st Cong., 2d sess.)
   Local cooperation. Local interests are required to adjust all
water rights claims resulting from operation of the improvements
and to keep the flood channels below the flood control reservoir free
from man-made encroachments.
   Operations and results during fiscal year. None.
   Condition at end of fiscal year. No construction undertaken.
Work remaining consists of preparation of the project plan, con-
tract plans and specifications, and construction.
24. PINE   CANYON RESERVOIR,       COLORADO     RIVER BASIN, NEV.
   Location. The site of the improvement is about 17 miles east-
ward from Caliente, Nev., in Pine Canyon, a tributary to Clover
Creek, and about 3 miles above the mouth of Pine Canyon.
   Existing project. The plan of improvement provides for a dam
and reservoir for flood control. The dam would be an earth-fill
structure with a maximum height of 97 feet above stream bed, and
a crest length of 2,003 feet. A 90-foot spillway, crest elevation
5,675 would be constructed along the left wall of the canyon. The
reservoir would have a total capacity at spillway crest of 7,840
acre-feet, including 1,400 acre-feet reserved for sediment. The
operation of the reservoir would regulate the runoff from a tribu-
tary area of 45 square miles, reducing the standard project flood
from 10,500 cubic feet per second to 318 cubic feet per second. The
latest (1954) approved estimate of cost is $1,600,000. The im-
provement was authorized by the Flood Control Act approved May
17, 1950. (See H. Doc., 81st Cong., 2d sess.)
   Local cooperation. Local interests are required to adjust all
water rights claims resulting from operation of the improvements
and to keep the flood channels below the flood control reservoir free
from manmade encroachments.
   Operations and results during fiscal year. No operations were
performed.
   Condition at end of fiscal year. No construction undertaken.
1298           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Work remaining consists of preparation of the project plan, con-
tract plans and specifications, and construction.
                  25.   INACTIVE           FLOOD        CONTROL           PROJECTS

                                                                   Cost and expenditures
                                                       For last       to June 30, 1954     Estimated
                 Name of project                     full report,                            amount
                                                     see annual                 Operation  required to
                                                     report for- Construction       and     complete
                                                                               maintenance

Alamo Reservoir, Bill Williams River, Colorado
  River Basin, Ariz--------------------------__    1950             $213,212 ------------     2 $8,546,800
Aliso Creek Dam, Santa Ana River Basin, Calif_ _-        _- ..---------------------------          340,000
Holbrook levee, Little Colorado River, Colorado
   River Basin, Ar es,-S----- a---v1950                              335,000 --------------         ()
Lytle and Cajon Creeks, Santa Ana River Basin,
  Calif ------------------------------------       1950           7,613,358    --------------       (1)
Mill Creek levees, Santa Ana River Basin, Calif_"  1951       -_---------------------             1,590,000
San Jacinto River and Bautista Creek levees,
  Santa Ana River Basin, Calif.----------------- 1951 ----------------------------               5,280, 000
San Juan Dam, Santa Ana River Basin, Calif....     1950               67,361 --------------       5,v892,000
Santa Clara River and its tributaries, channel
  improvements, Santa Clara River Basin, Calif_    1950     ---------------------------           6,750,000
Stewart Canyon debris basin and channel, Ven-
  tura River Basin, Calif-----------       - ---.  1950               38, 242                   2 1,328, 600
Trabuco Dam, Santa Ana River Basin, Calif...........----------- -----------------------------     2,190,000
                                           --.....
Tucson diversion channel-....-.......-- .1953                         72, 200 -------------- 27, 800
Villa Park Dam, Santa Ana River Basin, Calif._ _    __ - . ------------ --------------           2,270,000
Ventura River levee, Ventura River Basin, Calif.   1950           1, 343, 638...-----             -(1)
Whitlow Wanch Reservoir, Queen Creek, Ariz...      1950      .                                    4, 550, 000

  I Completed.
  2 Inactive, due to lack of funds.
  3 Inactive, awaiting appropriation of funds.

                            26. GENERAL INVESTIGATIONS

   Examinations and surveys. The costs during the fiscal year for
flood control studies were as follows:
                                                                        -------...
     Gila River and Tributaries, Ariz. and New Mexico_.... - -.....---.---.        $1,015
     Mojave River, Calif .......---------------------------------------            17,579
                                                                                       736
     San Dieguito River, Calif ....-------------------------------------..................

  The balance unexpended at the end of the fiscal year amounting
to $29 plus accounts receivable $0, a total of $29 will be applied
during fiscal year 1955 as follows:
     Mojave River, Calif ................................................................-
                                                                            $29

  The additional sum of $118,600 can be expended profitably dur-
ing fiscal year 1956.
  Collection and study of basic data. The costs during the fiscal
year for collection and study of basic data were $3,818. The bal-
ance unexpended at the end of fiscal year amounting to $182 plus
accounts receivable of $0, a total of $182 will be applied as needed
during the fiscal year 1955.
                    FLOOD CONTROL-LOS ANGELES, CALIF., DISTRICT                                                      1299
                       27. INSPECTION OF COMPLETED PROJECTS
     The costs during the fiscal year were $13 for maintenance.
                                                  Cost and financial summary

                                                        Fiscal year ending June 30                            Total to June
                                                                                                             30, 1954, includ-
                                                                                                             ing fiscal years
                                          1950         1951          1952         1953           1954         prior to 1950


Maintenance:
   Appropriated----.......----..------------........      $300 ------------....      $300           $300                $900
     Cost................--------------------------------------          $208            25             13                246



  28. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
  Flood control emergencies-Repair and flood fighting rescue
work. '(Section 210 of the 1950 Flood Control Act and supple-
mental authorizations.)
                                                  Cost and financial summary

                                                        Fiscal year ending June 30                           Total to June
                                                                                                             30, 1954, includ-
                                                                                                             ing fiscal years
                                           1950        1951          1952         1953          1954          priorto 1950


Maintenance:
   Appropriated....---------------- ------------                        000
                                                                     $38,         -$3, 908        -$185               $64, 907
     Cost...------------------------------------25,020                              8,225     .64,245



29. SCHEDULING OF FLOOD CONTROL RESERVOIR OPERATIONS
  Section 7 of Flood Control Act of 1944 reads as follows: "Here-
after, it shall be the duty of the Secretary of War to prescribe
regulations for the use of storage allocated for the flood control or
navigation at all reservoirs constructed wholly or in part with
Federal funds provided on the basis of such purposes, and the
operation of any such project shall be in accordance with such
regulations: ***"
  In accordance with the above authority, preparation of schedule
of flood control operations manual for Hoover Dam was carried on
during the fiscal year at a cost of $860.
                                                  Cost and financial summary

                                                        Fiscal year ending June 30                            Total to June
                                                                                                             30, 1954, includ-
                                                                                                             ing fiscal years
                                           1950        1951           1952        1953           1954         prior to 1950

Maintenance:
   Appropriated--.... -----------------------------------------------                             $1,000               $1,000
   Cost----------      ------------------------------------------------                              860                  860
IMPROVEMENT OF RIVERS AND HARBORS IN THE SAN
         FRANCISCO, CALIF., DISTRICT

   This district comprises parts of southern Oregon and northern
and western California embraced in the drainage basins tributary
to the Pacific Ocean from the Oregon-California State line on the
north to Cape San Martin, Calif. (about 150 miles south of the en-
trance to San Francisco Bay), on the south, except the waters of
Suisun Bay and the Sacramento and San Joaquin Rivers and their
tributaries. It also includes the Hawaiian, Line, Gilbert, Marshall,
Midway, Wake, and Johnston Islands, and such islands in the South
Pacific Ocean lying between the 159th meridian of east longitude
and 108th meridian of west longitude as may be under the jurisdic-
tion of the United States.
                                       IMPROVEMENTS
                  Navigation                                   Navigation-Continued
                                             Page                                               Page

1. Crescent City Harbor, Calif......         1301 17. Nawiliwili Harbor, T. H..                 1329
2. Humboldt Harbor and Bay,                       18. Port Allen Harbor, T. H...                1331
     Calif ................. .          .    1303 19. Keehi Lagoon T. H...........              1332
3. Noyo River and Harbor, Calif..            1305 20. Honolulu Harbor, T. H.....                1334
4. Bodega Bay, Calif ................        1307 21. Kaunakakai Harbor, T. H....               1336
5. San Francisco Harbor, Calif....           1308 22. Kahului Harbor, T. H_._........           1337
6. San Francisco Harbor and Bay,                  23. Kawaihae Harbor, T. H.........            1338
     Calif. (collection and re-                   24. Hilo Harbor, T. H......................   1340
     moval of drift) .....................   1311 25. Inactive Navigation projects ...          1341
7. San Rafael Creek, Calif ............      1311
8. Petaluma Creek Calif............          1312                   Flood Control
                             .........
9. Napa River, Caiif............            1314 26. Russian River, Calif.........             1341
10. San Pablo Bay and Mare                        27. Hanapepe River, T. H..............        1343
      Island Strait Calif.......             1315 28. Kawainui Swamp, T. H...........           1344
11. Richmond Harbor Calif..........          1317 29. Inactive flood control projects..         1345
12. Oakland Harbor, (alif.....               1321 30. General investigations-......             1345
13. Redwood City Harbor, Calif....           1323 31. Inspection of completed flood
14. Halfmoon Bay, Calif..................    1325       control projects.... ................   1346
15. Moss Landing Harbor, Calif.....          1326 32. Flood control work under special
16. Monterey Harbor, Calif ..........        1328       authorization_.....______...._..        1346

                       1. CRESCENT CITY HARBOR, CALIF.
   Location. This harbor is 17 miles south of the Oregon State
line, 125 miles south of Coos Bay, Oreg., 70 miles north of Hum-
boldt Bay, Calif., and midway between San Francisco Bay and the
mouth of the Columbia River. (See U. S. Coast and Geodetic Sur-
vey Chart No. 5895.)
   Existing project. This provides for a rubble-mound break-
water extending for approximately 3,700 feet on a bearing of S. 270
E. from Battery Point, thence for approximately 1,000 feet on a
bearing of S. 80 ° E.; a rubble-mound sand barrier from Whaler
Island to the easterly shore, an inner breakwater extending north-
westerly from Whaler Island, to form a protected inner harbor, for
maintaining, by dredging, a basin 1,800 feet long and 1,400 feet
wide to a depth of 20 feet at mean lower low water, except in rock,
for the removal of pinnacle rocks in the inner harbor, and for main-
                                                                                       1301
1302               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

tenance dredging of the inner harbor basin in the vicinity of the
seaward end of the sand barrier.
   The range of tide between mean lower low water and mean
higher high water is 6.9 feet; the extreme range of tide is about
12.3 feet.
  The estimate of cost for new work (1954) is $6,792,000, exclusive
of $217,116 contributed by local interests.
  The latest (1954) approved estimate for annual cost of mainte-
nance is $151,500, exclusive of the cost of maintenance of the
inner harbor.
  The existing project was authorized by the following River and
Harbor Acts:

       Acts                            Work authorized                                  Documents

July 18,1918       Breakwater__---.---                   -------------       H. Doc. 434, 64th Cong., 1st sess.
Sept. 22,1922      Conditions of local cooperation modified--.....--     _   Rivers and Harbors Committee
                                                                              Doc. 4, 67th Cong., 2d sess.
Jan.    21, 1927   Extending the breakwater to length of 3,000 feet_ ...     H. Doc. 595, 69th Cong., 2d sess.
Aug. 30, 1935      Dredging the harbor basin, 1,800 feet long, 1,400 feet    Rivers and Harbors Committee
                    wide, and 20 feet deep.                                    Doc. 40, 74th Cong., 1st sess.
Aug. 26,1937       For the sand barrier and maintenance dredging in          Senate Commerce Committee
                     the vicinity of the seaward end thereof.              print, 75th Cong., 1st sess.
Mar. 2,1945        Extending the breakwater to Round Rock (modified      H. Doc. 688, 76th Cong., 3d sess.
                     by the Chief of Engineers).                           (Contains latest published map.)
       Do.......   Inner breakwater and removal of rock in inner harbor. Report on file in Office, Chief of
                                                                               Engineers.


   Local cooperation. Fully complied with for work performed to
date. The act of March 2, 1945, requires that local interests grant to
the United States, free of cost, necessary easements and rights-of-
way and a suitable quarry or source of supply of royalty free rock
for extension of the breakwater. The required permits and assur-
ances of cooperation were provided by the Board of Supervisors
of Del Norte County, State of California, in Resolution No. 475
dated May 4, 1953.
   Terminal facilities. There are 4 piers in the harbor, 1 of which
is designated for public use; 1 boat fueling station; and a private
mooring for barges discharging petroleum products to a pipeline
located on the inner breakwater. One of the private piers was
severely damaged by winter storms and cannot be utilized until
repaired. The facilities will be adequate for existing commerce
upon completion of the repairs.
   Operations and results during fiscal year. The repair and
strengthening of the outer breakwater was initiated by contract at
a cost of $716,095, including the placement of 99,518 tons of stone,
121 salvage stones, and 288 cubic yards of concrete. Condition and
operation studies and inspections and reports were accomplished
by hired labor at a cost of $2,204. The total maintenance cost dur-
ing the fiscal year was $718,299.
   Condition at end of fiscal year. The existing project is about 73
percent complete. The work remaining to be accomplished is the
completion of the outer breakwater extension. The 3,000-foot outer
breakwater was completed in 1930, the sand barrier in 1939, the
inner breakwater in 1946, and the removal of pinnacle rock in 1951.
  The controlling depths in June 1954 were as follows: Main
harbor basin, 12 feet at the A. C. Dutton Co. wharf, 6 feet at the
      RIVERS AND HARBORS-SAN FRANCISCO, CALIF., DISTRICT                                                                                     1303
J. C. Paul wharf, and 15 feet in the outer half of the basin; inner
harbor, 12 feet, except in the extreme northeast and southeast
corners, which were 9.5 feet.
   The total costs for the existing project to the end of the fiscal
year were as follows:

                                                                                               New work           Maintenance             Total
                                                                                                   costs              costs               costs


Regular funds .......................................------------------------------------          $3, 971, 085       $1, 498, 572         $5, 469, 657
Contributed funds ................---------------------..--------------                                217, 116            27, 884             245, 000

         Total...........................--------------------------------------                     4, 188, 201        1, 526, 456          5, 714, 657


                                                         Cost and financial summary

                                                                      Fiscal year ending June 30                                     Total to June
                                                                                                                                     30, 1954, includ-
                                                                                                                                     ing fiscal years
                                                1950                1951                    1952           1953          1954         prior to 19501


New work:
   Appropriated .-..     -.                   $524, 350           $900, 000                  $4, 000 I--$---------------------            $3, 971, 085
   Cost ---------------                        800,531           1,253,138                    8,623        $152 ------------              '3,971,085
Maintenance:
   Appropriated ........                        293, 000             40,182                  28,600        909, 725       $3,700            1, 691, 572
   Cost----------- ----                         109,151             240, 223                 73,349         57,820       718,299            1, 498,572


  1 Exclusive of contributed funds of $217,116 for new work and $27,884 for maintenance.
  3 Exclusive of $2,138 surplus material from Corps of Engineers' military activities.

Other new work data:
    Appropriated for succeeding fiscal year ending June 30, 1955           500,000
                                                                         $--------
    Estimated additional amount needed to be appropriated for completion
      of existing project----_    ----------------------------------     2,318,777

                             2. HUMBOLDT                            HARBOR AND BAY, CALIF.
  Location. Humboldt Bay is a landlocked harbor on the coast of
California, 225 miles north of San Francisco Bay and 70 miles south
of Crescent City Harbor. (See U. S. Coast and Geodetic Survey
Chart No. 5832.)
  Previous projects. Adopted by the River and Harbor Acts of
March 3, 1881, September 19, 1890, July 3, 1892, March 3, 1899, and
March 2, 1907. For further details, see pages 1982-1984 of Annual
Report for 1915, page 1673 of Annual Report for 1929, and page
1689 of Annual Report for 1938.
   Existing project. This provides for two rubble-mound jetties
at the entrance-the north jetty about 4,500 feet in length and the
south jetty 5,100 feet long, not including shore revetments; for a
bar and entrance channel 40 feet deep tapered from a width of 1,600
feet at seaward mile 0.91 to 500 feet at seaward mile 0.18, thence
500 feet wide to mile 0.75, with easing of the bend at mile 0.75; for
a North Bay Channel 30 feet deep and 400 feet wide from mile 0.75
tc mile 4.29; a channel 400 feet wide and 30 feet deep from mile
4.29 to mile 5.00, thence 26 feet deep to the foot of N Street,
Eureka; a channel 30 feet deep and 300 feet wide from mile 4.29
across Indian Island Shoal to Samoa, at mile 5.84; a channel 18 feet
deep and 150 feet wide to Arcata wharf; and a channel 26 feet
deep and 300 feet wide to Fields Landing, with a turning basin 600
1304             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

feet wide and 800 feet long off the Fields Landing wharf. All
depths refer to mean lower low water. The tidal range between
mean lower low water and mean higher high water is 6.4 feet at
the south jetty and 6.7 feet at Eureka. The extreme range is 12.5
feet at the south jetty and 12 feet at Eureka.
  The estimate of cost for new work (1954) is $3,294,000, exclusive
of $95,000 contributed by local interests and of the amounts ex-
pended on previous projects. The latest (1954) approved estimate
for annual cost of maintenance is $259,500.
  The existing project was authorized by the following River and
Harbor Acts:

       Acts                         Work authorized                                      Documents
June 25, 1910    Rebuilding the jetties-.....    __...-------------------..   H. Doc. 950, 60th Cong., 1st sess.
July    3,1930   For depth of 20 feet and widths of 250 and 300 feet in       H. Doc. 755, 69th Cong., 2d sess.
                   the bay channels and for the channel to Arcata
                   wharf.
Aug. 30, 1935    For the entrance channel, 500 feet wide, 30 feet deep.       Rivers and Harbors Committee
                                                                                Doc. 14, 74th Cong., 1st sess.
Aug. 26, 1937    For widths of 400 feet in Eureka channel and 300 feet        Rivers and Harbors Committee
                  in Samoa and Fields Landing channels, and for                 Doc. 11, 75th Cong., 1st sess.
                  construction of Fields Landing turning basin, 600
                  feet wide and 800 feet long, all to a depth of 26 feet.
July 16, 19521   For deepening to 40 feet and widening bar and en-            H. Doc. 143, 82d Cong., 1st sess.
                  trance channel; deepening       Eureka and       Samoa        (Contains latest published map.)
                  channels to 30 feet; and for construction of North
                   Bay channel, 400 feet wide, 30 feet deep.

   Public Law 549, 82d Cong., 2d sess.

   Local cooperation. Fully complied with for new work. The
acts of August 26, 1937, and July 16, 1952, require that local ihter-
ests furnish, free of cost to the United States, all lands, easements,
rights-of-way, and suitable spoil disposal areas required for main-
tenance dredging.
   Terminal facilities. There are 28 wharves and piers, 2 of which
are publicly owned, 4 oil terminals, 4 boatbuilding and repair plants,
1 boat icing plant, 7 small boat fueling stations, and numerous log
booms and small landings, exclusive of facilities owned by the
United States. These facilities are considered adequate for exist-
ing commerce.
   Operations and results during fiscal year. New work dredging
was initiated by the U. S. hopper dredges Biddle and Davison
which removed 1,049,574 cubic yards of material from the Bar
and Entrance Channel and 271,226 cubic yards from the North Bay
Channel at a cost of $245,764. Preliminary engineering for the
remainder of the new work dredging was initiated by hired labor
at a cost of $108. As maintenance, condition and operation studies
and inspections and reports were accomplished by hired labor at a
cost of $5,582. The total costs during the fiscal year were $245,872
for new work and $5,582 for maintenance, a total of $251,454,.
   Conditionat end of fiscal year. The existing project is about 92
percent complete. The work remaining to be done is the completion
of dredging of the Bar and Entrance Channel and the North Bay
Channel and dredging of Eureka and Samoa Channels to depths
authorized by the Act of July 16, 1952. The north jetty was m-
pleted in 1925; the south jetty in 1927; Arcata Channel in 1981;
the entrance channel, 30 feet deep and 500 feet wide, in 1935;
     RIVERS AND HARBORS-SAN FRANCISCO, CALIF., DISTRICT                                                                                              1305
Fields Landing channel and turning basin and Eureka and Samoa
channels, to a depth of 26 feet, in 1939.
  The controlling depths over various channels in June 1954 were
as follows: Entrance channel and channel between the jetties, 31
feet; natural channel in bay north of the entrance, 26.5 feet;
Samoa channel, 27 feet; Eureka channel, 25 feet to D Street, thence
12.5 feet to head of project; and Fields Landing channel, 20 feet.
In May 1937, Arcata channel (no longer in use) was 18 feet.
  The total costs for the existing project to the end of the fiscal
year were as follows:

                                                                                                New work                 Maintenance              Total
                                                                                                     costs                    costs               costs

Regular funds....--        ---------------------------------                                       $3, 024, 760               $5, 085, 862        $8, 110, 622
Contributed funds -----------------------------------                                                      95, 000                                     95, 000
      Total.-                                                                                        3, 119, 760               5, 085, 862         8, 205, 622



                                                        Cost and financial summary

                                                                          Fiscal year ending June 30                                          Total to June
                                                                                                                                             30, 1954, nclud-
                                                                                                                                             ing fiscal years
                                              1950                     1951              1952                 1953               1954         prior to 1950 12


New work:
   Appropriated_                                                                  --.     .            .      - -    -          $250,000          $5, 290,259
   C ost-- ---------- -.i ............                         I............      ....................                    .      245, 872          5,286, 131
Maintenance:                                                                                                                          '
    Appropriated_                           $139,400                   $70, 220          $10,000             $116,850               1,300          5,185, 653
    Cost----..---......-----                  68,657                   157,482            22,197              110,999               5,582          5,184,068


  1 Includes $2,261,371 for new work and $98,206 for maintenance on previous project.
  2 Exclusive of contributed funds of $95,000 for new work on the existing project.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_--                $4,128
    Appropriated for succeeding fiscal year ending June 30, 1955--         265,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955 --                                               ---------- 269,128


                               3. NOYO RIVER AND HARBOR, CALIF.

  Location. Noyo Harbor is a cove on the California coast about
100 miles south of Humboldt Bay and 135 miles northwest of San
Francisco. Noyo River rises in the Coast Range Mountains, flows
westerly, and empties into Noyo Harbor. (See U. S. Coast and
Geodetic Survey Chart No. 5703.)
  Previous projects. Adopted by the River and Harbor Act of
September 22, 1922. For further details, see page 1680, Annual
Report for 1929, and page 1772, Annual Report for 1930.
  Existing project. This provides for a rubble-mound breakwater
extending northwesterly about 1,100 feet from the south headland
of Noyo Harbor, two entrance jetties, and for an entrance channel
into Noyo River 10 feet deep and 100 feet wide and a channel in the
river 10 feet deep and 150 feet wide extending 1.15 miles above the
mouth, to be obtained by jetty construction and dredging. All
depths refer to mean lower low water. The tidal range between
1306              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

mean lower low water and mean higher high water is 5.8 feet. The
extreme range is about 11.5 feet.
  The estimate of cost for new work (1954) is $2,378,000, exclusive
of amounts expended on the previous project. The latest (1954)
approved estimate for annual cost of maintenance is $54,500.
  The existing project was authorized by the following River and
Harbor Acts:

       Acts                         Work authorized                                  Documents

July    3, 1930   Entrance channel and channel in the river...---------   S. Doc. 156, 71st Cong., 2d sess.
Mar.    2,1945    The breakwater in Noyo Harbor------- __----------       H. Doc. 682, 76th Cong., 3d sess.
June 30, 1948     Extension of project channel one-half mile upstream_    H. Doc. 586, 80th Cong., 2d sess.
                                                                           (Contains latest published map.)


   Local cooperation. The act of July 3, 1930, requires that local
interests provide free of cost to the United States suitable areas for
the disposal of dredged materials. This requirement has been fully
complied with for new work. The act of March 2, 1945, requires
that local interests provide the necessary rights-of-way and ease-
ments for the construction and maintenance of the breakwater,
including access thereto, and a suitable royalty-free quarry in the
locality; and give assurances satisfactory to the Secretary of War
that they will provide suitable public facilities and arrangements
for the loading and unloading of vessels in Noyo Harbor. These
requirements have not been complied with. The act of June 30,
1948, requires that local interests establish a competent public body
empowered to regulate the use and development of the port facili-
ties, which shall be open to all on equal terms, and provided such
public body (1) furnishes, without cost to the United States, all
lands, easements, and rights-of-way necessary for construction of
the improvement; (2) agrees to hold and save the United States
free from damages resulting from construction and maintenance
of the project; (3) reserves for spoil disposal areas all presently
unused lands adjacent to the lower 1.6 miles of the river and lying
below an elevation of 16 feet above mean lower low water; (4)
agrees to furnish, free of cost to the United States, easements over
these areas for the deposit of spoil from the new work and main-
tenance dredging and for the construction thereon of impounding
levees and to furnish royalty-free material for the construction of
such levees, all when and as required; and (5) agrees to contribute
to the United States funds equal to the Federal cost of constructing
such levees as and when required. The Noyo Harbor District was
established by the Board of Supervisors of Mendocino County on
October 18, 1950, as an initial step in fulfilling the requirements of
local cooperation.
   Terminal facilities. There are no facilities in the harbor prop-
er. In the river above the harbor there are 2 wharves, 6 fish
receiving and shipping piers, 3 of which have boat fueling stations
thereon; 5 boat building and repair plants; 1 boat fueling and icing
terminal; and a number of mooring facilities; all privately owned.
These facilities are considered adequate, with the exception of
    RIVERS AND HARBORS---SAN                                  FRANCISCO, CALIF., DISTRICT                      1307
mooring and berthing facilities for fishing boats. Improvement of
the project as authorized will provide additional protected area for
required facilities.
   Operations and results during fiscal year. As maintenance, at
a cost of $5,109, plans and specifications were prepared by hired
labor and a contract was awarded for repair of the jetties during
fiscal year 1955. Condition and operation studies and inspections
and reports were made at a cost of $2,087. The total maintenance
cost during the fiscal year was $7,196.
   Condition at end of fiscal year. The project is about 15 percent
complete. The work remaining to be done is the construction of
the breakwater in Noyo Harbor and the extension of the channel
one-half mile upstream to mile 1.15. The jetties, rock removal, and
dredging of the entrance channel and approximately five-eighths
of a mile of the river channel were completed in 1931.
   In March 1954 the controlling depths were as follows: 11 feet
at the entrance to the channel and 6.2 feet between the jetties;
thence 9.0 feet to the green navigation light at the first curve
 (quarter-mile point) ; thence 5.0 feet through the completed portion
of the project except for a depth of 2.5 feet at the extreme end.
   The cost of the existing project to the end of the fiscal year was
$195,834 for new work and $465,500 for maintenance, a total of
$661,334.
                                                  Cost and financial summary

                                                          Fiscal year ending June 30                   Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                                           1950        1951        1952         1953        1954       prior to 19501 2


New work:
   Appropriated-..-------......----------............ -$851 .................................... $207,819
                                                                                                  207,819-
   Cost_.
   Cost--------------------------------------------------------------------2E)7,819'
Maintenance:
   Appropriated.- ---                  -    $6, 700    -5,174     $212,382      $25, 778   $153, 300           645, 508
   Cost...............----------------       2 691         863       4,346      232,008       7,196            497, 597

I Includes $11,985 for new work and $32,097 for maintenance on previous project.
2 Exclusive of contributed funds of $7,180 for new work and $820 for maintenance on previous project.

Other new work data: Estimated additional amount needed to be ap-
  propriated for completion of existing project---                 2,182,166
                                                                  $---------------

                                              4. BODEGA BAY, CALIF.
   Location. Bodega Bay is a triangular lagoon on the California
coast 85 miles south of Noyo River and 58 miles north of San
Francisco.    (See U. S. Coast and Geodetic Survey Chart No.
5603.)
   Existing project. This provides for an entrance channel 100
feet wide and 12 feet deep at mean lower low water, protected by
jetties; a channel of the same dimensions as the entrance channel
to the town of Bay, and thence southeasterly along the shore for
a distance of about 4,200 feet, with three widenings or turning
basins 12 feet deep, one, 300 feet wide, located at the inner end
of the entrance channel, the second, 400 feet wide, at the junction
of the bay and shore channels near the town of Bay, and the third,
400 feet wide, at the southern end of the shore channel; and a
1308           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

suitable bulkhead to prevent sand from the spit near the entrance
being carried into the bay channel. The tidal range between mean
lower low water and mean higher high water is 5.6 feet, and the ex-
treme tidal range is about 11 feet.
   The cost of new work under the project, completed in 1943, was
$641,800. The latest (1954) approved estimate for annual cost of
maintenance is $38,500.
   The existing project was adopted by the River and Harbor Act of
June 20, 1938 (H. Doc. 619, 75th Cong., 3d sess.). The latest
published map is in that document.
   Local cooperation. Fully complied with for new work. Local
interests are required to furnish disposal areas for maintenance
dredging and to maintain suitable grasses or shrubbery to control
the sands on the dunes west of the bay.
   Terminal facilities. There are 7 piers, 2 of which have boat
fueling stations thereon; 1 boat fueling pier; 1 boatbuilding and
repair plant; 2 small repair plants; and 7 small landings; all pri-
vately owned. These facilities are considered adequate for exist-
ing commerce.
   Operations and results during fiscal year. As maintenance, by
hired labor, condition and operation studies and inspections and
reports were made at a cost of $2,162.
   Condition at end of fiscal year. The project was completed in
1943. In March 1954 the controlling depths were as follows: 11
feet between the jetties to beacon 2, thence 8 feet to beacon 8, 10
feet to beacon 20, 10 feet to the easterly end of the middle turn-
ing basin, thence 9 feet to the innermost turning basin, and 6 feet
in the innermost turning basin.
   The cost of the existing project to the end of the fiscal year was
$641,800 for new work and $111,078 for maintenance, a total of
$752,878.
                                        Cost and financial summary

                                                 Fiscal year ending June 30                   Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                                 1950        1951         1952         1953         1954       priorto 1950


New work:
   Appropriated ------- --       .$641,800
   Cost                                          ----    ---------    -----------    ------           641, 800
Maintenance:
   Appropriated ... -             $2, 100    $     727     $2, 500      $2, 700     $2, 200            111, 127
   Cost-....        .-       I     2,726         1,664      1,630        3,559       2,162             111,078



                         5. SAN FRANCISCO HARBOR, CALIF.
  Location. The works included under this project are in San
Francisco Bay, in the vicinity of San Francisco, and in the ap-
proach channels to the Golden Gate, the bay entrance. (See U. S.
Coast and Geodetic Survey Chart No. 5532.)
  Previous projects. Adopted by the River and Harbor Acts of
July 25, 1868, June 10, 1872, June 23, 1874, March 3, 1899, June
13, 1902, June 25, 1910, and September 22, 1922. For further
details, see page 1978 of Annual Report for 1915, page 1749 of
Annual Report for 1921, page 1633 of Annual Report for 1929,
and page 1669 of Annual Report for 1938.              .
      RIVERS AND HARBORS-SAN FRANCISCO, CALIF., DISTRICT                                                                 1309
   Existing project. This provides for dredging a channel through
the San Francisco Bar on the line of the main ship channel, 50
feet deep and 2,000 feet wide; the removal of Presidio Shoal, Black
Point Shoal, Rincon Reef Rock (inner), Rincon Reef Rock
 (outer), Blossom Rock, and Alcatraz Shoal westward of a north-
and-south line 2,500 feet west of Alcatraz Light to a depth of 40
feet; the removal of Arch Rock, Shag Rocks 1 and 2, Harding
Rock, Raccoon Shoal, Point Knox Shoal westward of a north-and-
south line through Point Stuart Light, and a portion of the shoal
channelward of the pierhead line near the mouth of Islais Creek,
to a depth of 35 feet; and for dredging a channel 750 feet wide
and 10 feet deep from that depth in the bay to San Francisco Air-
port ending in a basin 10 feet deep and approximately 2,000 feet
in width.
   All depths refer to mean lower low water. The tidal range
between mean lower low water and mean higher high water is
5.7 feet at Fort Point and 7.2 feet at the San Francisco Airport.
The extreme ranges at the foregoing localities are 10.6 and 12
feet, respectively.
   The estimate of cost for new work (1954) is $1,628,000, ex-
clusive of amounts expended on previous projects and of $134,-
591 contributed by local interests. The latest (1954) approved
estimate for annual cost of maintenance is $200,000.
   The existing project was authorized by the following River and
Harbor Acts:

      Acts                                  Work authorized                                               Documents
Jan. 21, 1927  Dredging at Islais Creek-----------------------............................   H. Doc. 337, 69th Cong., 1st sass.
July 3, 1930   Removal of Presidio Shoal, Rincon Reef Rock (inner),                          H. Doc. 196, 70th Cong., 1st seas.
                 Rincon Reef Rock (outer), Blossom Rck, and
                 Alcatraz Shoal to depth of 40 feet, mean lower low
                 water; removal of Arch Rock, Shag Rocks 1 and
                 2, and Harding Rock to depth of 35 feet; removal of
                 Raccoon Shoal and Point Knox Shoal, westward of
                a north-and-south line through Point Stuart Light
                 to depth of 35 feet.
Aug. 30,1935 1 For a 50-foot depth in the bar main ship channel, 2,000                       Rivers and Harbors Committee, 2
                feet wide, removal of Black Point Shoal to a depth                            Doc. 50, 72d Cong., 2d sess.
                 of 40 feet and certain modifications of the areas to be
                 deepened on Alcatraz and Islais Creek Shoals, and
                 abandonment of the 34-foot depth area south of the
                 flared approach channel to Islais Creek.
Aug. 26,1937 For the channel to the San Francisco Airport 750 feet                           Rivers and Harbors Committee,
                 wide and 10 feet deep ending in a basin 2,000 feet                          Doc. 12, 75th Cong., 1st sess.'
                       wide.


  1Included in part in the Public Works Administration program, Sept.
   Contains latest
                                                                                               6, 1933.
  2                      published maps.


   Local cooperation. Fully complied with for new work. The act
of August 26, 1937, requires that local interests furnish, free of
cost to the United States, suitably bulkheaded spoil disposal areas
for maintenance of the channel to the San Francisco Airport.
   Terminal facilities. The State of California owns 66 piers, a
large passenger ferry terminal, 3 car ferry terminals, and a moor-
ing wharf in the harbor. In addition, there are 4 privately owned
wharves, 1 shipbuilding yard, 2 shipbuilding and repair plants,
a fishboat harbor and a yacht harbor. These facilities are exclu-
sive of those owned by the United States and are considered ade-
quate for existing commerce.
1310                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

    Operationsand results during fiscal year. As maintenance, the
U. S. hopper dredge Biddle removed 244,707 cubic yards of mate-
rial from the main ship channel at a cost of $64,063; plans and
specifications for dredging the Airport Channel by contract during
fiscal year 1955 were initiated by hired labor at a cost of $397;
and condition and operation studies and inspections and reports
were made by hired labor at a cost of $10,236. The total main-
tenance cost during the fiscal year was $74,696.
    Condition at end of fiscal year. The existing project is about 90
percent completed. The work remaining to be done is the com-
pletion of the bar channel and the removal of Raccoon Shoal.
'The dredging of Islais Creek Shoal was completed in 1930, the
deepening of Presidio Shoal in 1931, the removal of the various
rocks in 1932, the deepening of Point Knox Shoal in 1934, the
deepening of Alcatraz Shoal in 1936, the deepening of Black Point
'Shoal in 1937, and the dredging of the channel and basin at the
San Francisco Airport in 1941.
    The controlling depths over various portions of the project on
the dates indicated were as follows: Main ship channel, 44 feet,
April 1954; Presidio Shoal, 35 feet, April 1954; Black Point Shoal,
35 feet, April 1954; Rincon Reef Rock (inner), 41 feet, March
1946; Rincon Reef Rock (outer), 40 feet, July 1933; Blossom
Rock, 40 feet, October 1950; Alcatraz Shoal, 36 feet, April 1954;
Arch and Harding Rocks, 33 feet, December 1949; Shag Rocks 1
.and 2, 36 feet, December 1949; Point Knox Shoal, 37.5 feet, April
1954; Raccoon Strait Shoal, 28.5 feet, April 1954; Islais Creek
Shoal, 32 feet, April 1954; channel and basin at San Francisco
Airport, 5 feet, September 1953.
    The cost of the existing project to the end of the fiscal year
was as follows:

                                                                                          New work          Maintenance             Total
                                                                                            costs               costs               costs

Regular funds---------
              .........----------...---------------...............                          $1,167, 038         $832, 354           $1, 999, 392
Public Works funds---------------------------------                                            193, 000 ---------------                 193, 000
Contributed funds _            -......              .___...-----------                         134, 591 -----        --                 134, 591

        Total      ........ ...........-------------------------------------                 1, 494, 629          832,354             2, 326, 983


                                                         Cost andfinancial summary

                                                                       Fiscal year ending June 30                            Total to June
                                                                                                                             30, 1954, includ-

                                                                   1951
                                                                                                                             ing   fiscal years
                                                 1950                                1952           1953          1954       priorto 195012

New work:
   Appropriated...
      Aprorite                   1---------- --
                          --------
                                                     _   ...      .-
                                                               -----------
                                                                                 -- ...
                                                                                 I-
                                                                                            ...            .........
                                                                                  ----------- ------'------'------------
                                                                                                                                    $2,390,437
                                                                                                                                     2,   390,437
      Cost   -------------------------------------                                   -    ----
                                                                                    ..........----...........                        2,390,437
Maintenance:
      Appropriated.--------    $167, 500                               $4, 703       $74,000       $175,067       $76, 000            1,309, 618
      Cost-          -    "--------
                                162,880                                 7,049         80,670        175, 061       74, 696            1,307,675

  1Includes $1,030, 399 for new work and $475,321 for maintenance on previous projects.
  2   Exclusive of contributed funds of $134,591 for new work on existing project.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project- _-----------                 $267,962
    RIVERS AND HARBORS-SAN FRANCISCO, CALIF., DISTRICT                                          1311

               6. SAN FRANCISCO HARBOR AND BAY, CALIF.
                                  (Collection and removal of drift)

   Location. This project applies to San Francisco Bay, lower
San Francisco Bay, Oakland Harbor, Richmond Harbor, San Pablo
Bay and Mare Island Strait, Richardson Bay, and their tributaries.
   Existing project. This provides for the collection and removal
of drift from San Francisco Bay and its tributary waters.
   The (1954) estimate of cost for new work (initial acquisition of
plant and equipment) is $1,070,000. The latest (1954) approved
estimate for annual cost of maintenance is $203,900.
   The existing project was authorized by the River and Harbor
Act of May 17, 1950 (H. Doc. No. 286, 81st Cong., 1st sess.)
   Local cooperation. None required.
   Terminal facilities. Described in pertinent separate project
descriptions.
   Operations and results during fiscal year. As maintenance,
floating debris was collected and disposed of from the project
waterways at a cost of $70,191.
   Condition at end of fiscal year. No new work funds have been
appropriated. Operations under the existing project were com-
menced July 1, 1950. Costs for the removal of drift previous
to that time were carried as maintenance on applicable authorized
river and harbor projects in the area.
   The cost of the existing project to the end of the fiscal year, all
for maintenance, was $238,934.
                                  Cost and financial summary

                                          Fiscal year ending June 30 .                   Total to June
                                                                                        30, 1954, includ-
                                                                                        ing fiscal years
                           1950         1951         1952         1953       1954        prior to 1950

Maintenance:
   Appropriated -------------------.    $60, 000     $52, 000     $62, 500   $69, 000           $243, 500
   Cost....     .                        52, 318      59, 682      56, 742    70, 191            238,934


Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project-------------            $-$1,070,000

                        7. SAN RAFAEL CREEK, CALIF.
   Location. This is a small, mainly tidal stream about 2 miles in
length, flowing easterly and emptying into the west side of San
Francisco Bay, 14 miles north of San Francisco. (See U. S. Coast
and Geodetic Survey Chart No. 5532.)
   Existing project. This provides for a channel 8 feet deep and
100 feet wide across the flats in San Francisco Bay to the mouth
of the creek; thence 6 feet deep and 60 feet wide to Irwin Street,
San Rafael; a cutoff through Goose Neck Bend, and a turning
basin 200 feet long, 100 feet wide, and 6 feet deep at San Rafael,
near the head of the project. All depths refer to mean lower low
water. The length of the section under improvement is 3.5 miles,
of which 2 miles are in San Francisco Bay, outside the mouth of
the creek.
   The tidal range between mean lower low water and mean higher


       Sig 42-1311-1342
1312              REPORT OF CHIEF OF ENGINEERS. U: S. ARMY, 1954

high water is 5.7 feet, with an extreme range of 10.5 feet.
   The cost of new work under the project, completed in 1928, was
$32,359, exclusive of $41,094 contributed funds. The latest (1954)
approved estimate for annual cost of maintenance is $27,000.
   The existing project was authorized by the River and Harbor
Act of March 2, 1919 (H. Doc. 801, 63d Cong., 2d sess.). No map
has been published.
   Local cooperation. Fully complied with.
   Terminal facilities. There are 8 wharves, 6 of which are for
the receipt of bulk petroleum products; 2 boatbuilding and repair
plants; 4 yacht harbors and 4 boat fueling stations; and 11 moor-
ings and bulkhead landings; all privately owned. These facilities
are considered adequate for existing commerce.
   Operations and results during fiscal year. As maintenance, by
hired labor, plans and specifications were prepared and 265,941
cubic yards of material were removed by contract from the proj-
ect channels at a cost of $116,810; and condition and operation
studies and inspections and reports were made by hired labor at
a cost of $1,467; a total maintenance cost during the fiscal year of
$118,277.
   Condition at end of fiscal year. The project was completed in
1928. In February 1954 the controlling depths were as follows:
8.5 feet in the channel across the flats in San Francisco Bay to
the mouth of the creek; 8.0 feet in the creek to the municipal
yacht harbor, thence 7.5 feet to the head of the project at Irwin
Street.
The costs of the existing project to the end of the fiscal year
were as follows:

                                                                            New work              Maintenance              Total
                                                                              costs                  costs                 costs


Regular funds ......--------------------------------------                          $32, 359        $416, 465                  $448, 824
Contributed funds        .....      .....----------------------------                41, 094 ----------------                    41, 094
       Total        -      .        .             ..                                    73, 453           416, 465              489, 918
          T   tl------------------------------------------7,5                                              1,6                  8,1




                                               Cost and financial summary

                                                          Fiscal year ending June 30                                   Total to June
                                                                                                                      30, 1954, includ-
                                                                                                                      ing fiscal years
                                        1950             1951            1952            1953             1954         prior to 1950 1

New work:
   Appropriated-                                                                   --                                           $32, 359
    Cost - -            _----    =-------------------
                                             -    -   -            -    ------------                    - - - -
                                                                                                      - ------       -32,359
Maintenance:
    Appropriated                        $61,350        -$24, 158          $1,618            $2, 500      $118, 400              416, 677
    Cost6---------6,101                                   33,451           1,618             2,411        118,277               416,465

  SExclusive of contributed funds of $41,094 for new work.

                                    8. PETALUMA CREEK, CALIF.
   Location. This stream rises in the hills north of Petaluma,
flows southeasterly about 20 miles, and empties into the north-
west side of San Pablo Bay about 22 miles from San Francisco.
   RIVERS AND HARBORS-SAN FRANCISCO, CALIF., DISTRICT           1313
 (See U. S. Coast and Geodetic Survey Chart No. 5533.)
   Previous projects. Adopted by the River and Harbor Acts of
June 14, 1880, July 13, 1892, July 18, 1918, and March 3, 1925.
For further details, see page 1982 of Annual Report for 1915,
page 1665 of Annual Report for 1929, and page 1684 of Annual
Report for 1938.
   Existing project. This provides for a channel 8 feet deep and
200 feet wide in San Pablo Bay to the mouth of the creek; thence
8 feet deep and 100 feet wide in the creek to Western Avenue,
Petaluma, including a depth of 8 feet in the turning basin; thence
4 feet deep and 50 feet wide to Washington Street Bridge; thence
4 feet deep and 40 feet wide to a point 935 feet above the Wash-
ington Street Bridge. All depths refer to mean lower low water.
   The length of the section under improvement is 19.5 miles, of
which 5 miles are in San Pablo Bay downstream from the mouth
of the creek.
   The tidal range between mean lower low water and mean higher
high water is 6.1 feet at the entrance and 6.6 feet at the head of
navigation, with an extreme range of 10 feet.
   The cost of new work under the project, completed in 1933, was
$85,063, exclusive of amounts expended on previous projects. The
latest (1954) approved estimate for annual cost of maintenance is
$61,000.
   The existing project was adopted by the River and Harbor Act
of July 3, 1930 (H. Doc. 183, 70th Cong., 1st sess.). The latest
published map is in this document.
   Local cooperation. Fully complied with for new work. The act
of July 3, 1930, requires that local interests furnish satisfactory
areas with necessary levees, spillways, and drainage works for the
proper disposal of spoil from maintenance.
   Terminal facilities. There are 24 wharves and piers and 11
small landings, all privately owned. These facilities are consid-
ered adequate for existing commerce.
   Operations and results during fiscal year. As maintenance,
condition and operation studies and inspections and reports were
made by hired labor at a cost of $2,988.
   Condition at end of fiscal year. The project was completed in
1933. The controlling depths on the dates indicated were as fol-
lows: June 1953, 6.5 feet in the channel across the flats in San
Pablo Bay; March 1953, 9 feet to Haystack Landing, 8 feet to F
Street in Petaluma, 7 feet to Western Avenue, and 2.5 feet to the
head of the project.
   The cost of the existing project to the end of the fiscal year was
$85,063 for new work and $622,397 for maintenance, a total of
$707,460.
1314            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                         Cost and financial summary

                                               Fiscal year ending June 30                      Total to June
                                                                                               30, 1954, includ-
                                                                                               ing fiscal years
                                  1950        1951        1952         1953         1954       priorto 1950 I3


New work:
   Appropriated-----            ------------------------------------------------------                 $297,146
   Cost---------------------------_             ----------------- -----------    -----------            297,146
Maintenance:
   Appropriated-........         -$78, 000     $4, 535   $194, 000     $ 7,475       $5, 700            941, 112
    Cost-----------------           2,794       4, 561      8,475      191,688        2,989             937,089


  1Includes $212,083 for new work and $314,692 for maintenance of previous project.
  2 Exclusive of contributed funds of $15,559 for new work on the previous project.


                                      9. NAPA RIVER, CALIF.
   Location. This stream rises in the St. Helena Mountains, flows
in a southerly direction, and empties into Mare Island Strait. The
navigable portion is a tidal estuary. The head of navigation is at
Third Street in the city of Napa, 16.2 miles above the mouth.
 (See U. S. Coast and Geodetic Survey Chart No. 5533.)
   Previous projects. The original project was adopted by the
River and Harbor Act of August 11, 1888, and modified by the
River and Harbor Act of March 2, 1919. For further details, see
page 1756, Annual Report for 1930, and page 1683, Annual Re-
port for 1938.
   Existing project. This provides for a channel 15 feet deep and
100 feet wide between the mouth at Mare Island Strait and Asy-
lum Slough and 10 feet deep and 75 feet wide thence to Third
Street in Napa with a cutoff at Horseshoe Bend, a turning basin
300 feet wide at Jacks Bend, and additional widenings, realine-
ments, and related works in other difficult sections. The length of
the section included in the project is 16.2 miles. The range be-
tween mean lower low water and mean higher high water is 6
feet at the mouth and 7.1 feet at the head of navigation. The
extreme range is about 11 feet.
   The estimate of cost for new work (1954) is $1,167,000, exclu-
sive of amounts expended on previous projects. The latest (1954)
approved estimate for annual cost of maintenance is $37,000.
   The existing project was authorized by the following River and
Harbor Acts:

     Acts                            Work authorized                                Documents

Aug. 30,1935     Channel 8 feet deep, 100 feet wide from Mare Island     Rivers and Harbors Committee
                  Strait to Asylum Slough, thence 75 feet wide to         Doc. 6, 72d Cong., 1stsess.
                  Napa.
July 24, 1946    Channel 15 feet deep, 100 feet wide between Mare        H. Doc. 397, 79th Cong., 2d sess.
                  Island Strait and Asylum Slough, thence 10 feet          (Contains latest published map.)
                  deep, 75 feet wide to 3d St. in Napa.



  Local cooperation. The act of July 24, 1946, requires that local
interests: (1) Furnish, free of cost to the United States, all neces-
sary lands, easements, rights-of-way, and spoil disposal areas
for the new work and subsequent channel maintenance when and
as required; (2) provide all necessary spoil impounding and drain-
age works; (3) assume responsibility for maintenance of such
    RIVERS AND HARBORS-SAN FRANCISCO, CALIF., DISTRICT                                                1315
bank revetment and levees as may be constructed or reconstructed
in connection with the works; and (4) hold and save the United
States free from damages due to construction and subsequent
maintenance of the Federal improvements. These and all prior
requirements have been complied with for work performed to date.
  STerminal  facilities. There are 4 dry docks, 1 vessel outfitting
wharf, 7 wharves used in connection with oil distributing plants,
and 4 wharves for general cargoes and other miscellaneous pur-
poses. There are also numerous small yacht mooring facilities
along the river. These facilities are considered adequate for
existing commerce.
   Operations and results during fiscal year. As maintenance,
condition and operation studies and inspections and reports were
made by hired labor at a cost of $7,632.
   Condition at end of fiscal year. The existing project is 99 per-
cent complete. The remaining work consists of the construction
of dikes and revetments should they be required. The controlling
depths over various sections of the project on the dates indicated
were as follows: July 1952, 15 feet from Mare Island Causeway to
Goodluck Point; November 1953, 12.5 feet at Goodluck Point,
thence 15 feet to Dutton Landing, 11 feet to Bull Island, 14 feet to
Horseshoe Bend Cutoff, 12 feet to Asylum Slough, 11 feet to Tan-
nery Bend, and 4 feet to the head of the project.
   The cost of the existing project to the end of the fiscal year
was $1,021,274 for new work and $53,394 for maintenance, a total
of $1,074,668.
                                    Cost and financial summary


                                           Fiscal year ending June 30                          Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                             1950         1951        1952           1953        1954          prior to 1950 1


New work:
   Appropriated     .       $ 56,650      -           $18, 275                     ...-            $1,048,830
   Cost----------------      863,034      $15,604      24,751    -          --      -1,048,830
Maintenance:
   Appropriated - ---...      18,600        -311        7, 500        $6, 200       $4, 200             88, 600
   Cost.------------          17, 776         642       5,310          4,347         7,632              87,990

IIncludes $27,556 for new work and $34,596 for maintenance of previous project.
Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project-------- -----------     $145,726

     10. SAN PABLO BAY AND MARE ISLAND STRAIT, CALIF.
  Location. The channel extends from a point in the lower end of
San Pablo Bay west of Pinole Point in a general northeasterly di-
rection across Pinole Shoal in San Pablo Bay to the junction of
Carquinez Strait and Mare Island Strait, thence northwesterly in
Mare Island Strait along the frontage of the Mare Island Navy
Yard. (See U. S. Coast and Geodetic Survey Chart No. 5533.)
  Previous projects. Adopted by the River and Harbor Acts of
June 13, 1902, February 27, 1911, and August 8, 1917. For fur-
ther details; see page 1680, Annual Report for 1938.
  Existing project. This provides for dredging a channel across
1316             'REPORT        OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

Pinole Shoal in San Pablo Bay 600 feet wide and 35 feet deep;
thence through Mare Island Strait a channel 700 feet wide and 30
feet deep flaring to a turning basin generally 1,000 feet wide from
former dike 6, Mare Island, to a line 75 feet southerly from the
causeway between Vallejo and Mare Island, 30 feet deep, except
at the northerly end where the project depth is 26 feet. The proj-
ect provides also for two approach areas 20 feet deep to within
50 feet of the pierhead line adjacent to the improved water front
at Vallejo and South Vallejo and for maintenance of the two ap-
proach areas to the navy yard piers at the southern end of Mare
Island. All depths refer to mean lower low water. The tidal
range between mean lower low water and mean higher high water
is 5.8 feet at the lower end of San Pablo Bay, and 6 feet opposite
the Mare Island Navy Yard with an extreme range of about 10
feet.
   The estimate of cost for new work (1954) is $390,000, exclu-
sive of amounts expended on previous projects. The latest (1954)
approved estimate for annual cost of maintenance is $225,000.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                            Work authorized                                          Documents

Feb. 27,1911      A depth of 30 feet through Pinole Shoal-----------..............   H. Doc. 1103, 60th Cong., d sess.
Aug. 8,1917       A depth of 35 feet and the Mare Island Strait Channel              H. Doc. 140, 65th Cong., 1st eess.
                    and turning basin.
Jan. 21,1927      Increasing width of the channel to 600 feet and de-                H. Doc. 104, 69th Cong., 1st ses.
                    creasing channel and turning basin depth in Mare
                    Island Strait to 30 feet.
June 20,1938      Increasing width of the channel in Mare Island Strait              H. Doc. 644, 75th Cong., 3d sess.
                    to 700 feet and increasing length of turning basin.
Mar.    2,1945    Approach areas at Vallejo and South Vallejo and                    H. Doc. 217, 77th Cong., 1st sess.
                    maintenance of approach areas to navy yard piers                  (Contains latest published map.)
                    at south end of Mare Island.


   Local cooperation. None required.
   Terminal facilities. There are 3 wharves along the southern
shore of San Pablo Bay; in Mare Island Strait there are 6
wharves, 2 ferry slips, and 3 small boat moorings, in addition to
the Navy Yard facilities. These facilities are considered adequate
for existing commerce.
   Operations and results during fiscal year. As maintenance, the
U. S. hopper dredge Hyde removed 649,447 cubic yards of material
from Pinole Shoal Channel and U. S. hopper dredges Hyde, Biddle,
and Rossell removed 1,586,762 cubic yards of material from Mare
Island Strait, at a cost of $353,019. Condition and operation
studies and inspections and reports were made by hired labor at
a cost of $4,818. The total maintenance cost for the fiscal year
was $357,837.
   Condition at end of fiscal year. The project is about 97 percent
complete. The work remaining to be done is the dredging of the
two approach channels adjacent to Vallejo and South Vallejo.
Pinole Shoal Channel was completed in 1929. The Mare Island
Strait Channel and turning basin was completed in 1943. In
January 1954 the controlling depth throughout Pinole Shoal Chan-
nel was 34 feet, and in May 1954, the controlling depth in Mare
Island Strait was 24.5 feet.
   RIVERS AND HARBORS-SAN FRANCISCO, CALIF., DISTRICT                                                   1317
   The costs of the existing project to the end of the fiscal year
were $282,669 for new work and $3,580,168 for maintenance, a
total of $3,862,837,
                                          Cost and financial summary

                                                 Fiscal year ending June 30                     Total to June
                                                                                                30, 1954, includ-
                                                                                                ing fiscal years
                                   1950        1951         1952         1953        1954        prior to 1950 1

New work:
   Appropriated.. ------------ ------------ ------------------------ -----------                      $1,369,372
   Cost--------------_  ---------------------------------------- ------------                          1,369,372
Maintenance:
   Appropriated------...          $174, 200   $143, 700    $185, 900    $103, 634   $308, 000          4,944,937
   Cost------                      208,347     108, 066     227, 974      48, 749    357, 837          4,939,548


1Includes $1,086,703      for new work and $1,359,380 for maintenance of previous projects.
Other new work data: Estimated additional amount needed to be appropri-
ated for completion of existing project _---                           $107,331

                                 11. RICHMOND HARBOR,                     CALIF.
   Location. This harbor is on the eastern shore of San Francisco
Bay about 10 miles north of Oakland. (See U. S. Coast and
Geodetic Survey Chart No, 5532.)
   Existing project. This provides for a channel 30 feet deep from
San Francisco Bay to the Santa Fe Channel (Ellis slough), 400
feet wide between the bay and the basin at terminal No. 1;
thence 500 feet wide to Point Potrero, with an increased width
of 1,150 feet at the turn off that point; thence widening from
about 700 feet just east of Point Potrero to 850 feet at a point
575 feet northerly therefrom; thence 850 feet wide to the Santa-
Fe Channel; for widening and flaring to the basin at terminal
No. 1 and the subsequent maintenance, to a depth of 30 feet, of
the basin as thus enlarged to within 75 feet of the pierhead line;
for the maintenance to a depth of 30 feet in the Santa Fe Charinel
to within 50 feet of the established harbor lines; for approach
areas 32 feet deep to within 75 feet of the pierhead line in the
outer harbor at Point San Pablo, Point Orient, and Richmond
long wharf; for a channel 20 feet deep, 150 feet wide and about
2,000 feet long from deep water in San Pablo Bay easterly along
the north side of Point San Pablo; and for a training wall 10,000
feet long extending in a general westerly direction from Brooks
Island. All depths refer to mean lower low water. The tidal
range between mean lower low water and mean higher high water
is 5.8 feet, with an extreme range of about 11 feet.
   The estimate of cost for new work (1954) is $878,000, exclusive
of contributed funds in the amount of $524,778. The latest (1954)
appi~ed estimate for annual cost of maintenance is $128,500.
1318               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

The existing project was authorized by the following River and
Harbor Acts:

       Acts                           Work authorized                                  Documents
Aug.     8,1917    Channel 24 feet deep and 600 feet wide in the inner      H. Doc. 515, 63d Cong., 2d sess.
                    harbor and the training wall.
July     3, 1930   A 30-foot channel with lessened widths ....-----------   Rivers and Harbors Committee
                                                                              Doc. 16, 70th Cong., 1st sess.
Aug. 30,1935 1 Increasing project widths in the inner harbor, the           Rivers and Harbors Committee
                     maintenance of the Santa Fe Channel to 30 feet and       Doc. 7, 73d Cong., 1st sess., and
                     the approach areas in the outer harbor to 32 feet.       Rivers and Harbors Committee
                                                                              Doc. 10, 74th Cong., 1st sess. 2
June 20, 1938      Widening of the channel at Point Potrero and north       H. Doc. 598, 75th Cong., 3d sess.
                     thereof, and for enlarging and subsequently main-
                     taining the basin at terminal No. 1.
Mar.     2, 1945   Channel in San Pablo Bay 20 feet deep and 150 feet       H. Doc. 715, 76th Cong., 3d sess.2
                    wide.

   Included in part in the Public Works Administration program, Sept. 6, 1933.
2 Contain latest published maps.

   Recommended modification of project. Modifications to the ex-
isting project are recommended by the Chief of Engineers in
House Document 395, 83d Congress, 2d session, to provide for a
channel 35 feet deep and 600 feet wide adjacent to Southampton
Shoal from deep water to the outer harbor, enlarging the approach
area in the vicinity of Richmond Long Wharf for about 3,670
feet parallel to the pierhead line at a distance of 75 feet there-
from and deepening the enlarged area to 35 feet, deepening to
85 feet and widening to 600 feet the inner harbor entrance chan-
nel from deep water to the turning basin at Point Richmond
deepening to 35 feet the turning basin at Point Richmond and
thence the inner harbor project area to a point in Santa Fe
Channel 2,000 feet above its entrance including dredging on the
east side of the channel in the vicinity of Point Potrero to afford
the full authorized width of 850 feet and excluding a small area
in the apex of the bend at Point Potrero, tapered widening of the
channel in the westerly approach to Point Potrero bend to afford
a maximum width of about 600 feet with a depth of 35 feet, and
maintenance of a suitable approach area at the Naval Fuel Annex
Wharf to a depth of 35 feet; generally in accordance with the
plan of the district engineer and with such modifications thereof
as in the discretion of the Chief of Engineers may be advisable; at
an estimated cost to the United States of $1,866,000 for new work
and $41,400 annually for maintenance in addition to that now
required; provided that before construction of any item of work
is commenced local interests agree that insofar as applicable to
such item of work they will: (1) furnish, without cost to the
United States, all necessary easements for the improvement and
suitable spoil-disposal areas for the new work and for subsequent
maintenance when and as required; (2) hold and save the United
states free from all damages due to construction and maintenance
of the work; and (3) construct and maintain suitable wharves,
ship-loading facilities and cargo-storage and handling facilities
adjacent to the deepened portion of Santa Fe Channel, with the
provision that such wharves and other facilities, intended for pub-
lic use, shall be open to all on equal terms. It is further recom-
mended that the modification of the existing project include the
      RIVERS AND HARBORS---SAN FRANCISCO, CALIF., DISTRICT                                                         1319

rescission of the provision that no portion of the channel widen-
ing to 850 feet, north of Point Potrero, as authorized by the River
and Harbor Act of June 20, 1938, shall be undertaken until local
interests furnish satisfactory assurances that industries will avail
themselves of the improved navigation facilities.
   Local cooperation. The act of June 20, 1938, requires that local
interests furnish necessary rights-of-way and spoil disposal
areas for initial work and subsequent maintenance and that no
portion of the channel widening north of Point Potrero authorized
by that act be undertaken until assurances are received that in-
dustries will avail themselves of the improved navigation facilities.
These latter assurances have not been received. All other re-
quirements have been fully complied with.
   Terminal facilities. In the inner harbor there are 4 deep-water
terminals, 2 oil-distribution terminals, a shipyard, a rail car ferry
terminal, 4 privately owned wharves, and several small wharves
for the mooring of floating equipment. In the outer harbor there
are 2 oil distribution terminals, a passenger and auto ferry ter-
minal, a deep-water terminal, a privately owned wharf for handling
sand and cement, and about 10 fish-receiving wharves.
   Operationsand results during fiscal year. As maintenance, the
U. S. hopper dredge Davison removed 90,800 cubic yards of mate-
rial from the inner harbor at a cost of $50,716 and preliminary
engineering for dredging to be accomplished during fiscal year
1955 in Santa Fe Channel was initiated by hired labor at a cost of
$1,751. Condition and operation studies and inspections and re-
ports were made by hired labor at a cost of $6,455. The total main-
tenance cost during the fiscal year was $58,922.
   Conditionat end of fiscal year. The existing project is about 94
percent complete. Dredging was initiated in 1918 and carried on
intermittently until 1940, at which time the project was complete
except for the widening of the channel north of Point Potrero. The
training wall was completed in 1931, and the channel in San Pablo
Bay in 1945.
   The controlling depths in the project channels on the dates
indicated were as follows: March 1954, 28 feet in the channel from
San Francisco Bay to the southerly end of Santa Fe Channel, and
27 feet in Santa Fe Channel; April 1951, 10 feet in the channel
east of Point San Pablo; June 1953, 30 feet in approach to Point
San Pablo and Point Orient; April 1954, 28 feet in approach to
Richmond Long Wharf.
   The costs of the existing project to the end of the fiscal year
were as follows:

                                                                          New work        Maintenance           Total
                                                                            costs               costs           costs

Regular funds------..  ---.------                .-.                         $709,018            $1, 205, 879   $1, 914, 897
Public Works funds         _---.     -....-       -.............              105, 000    ...........               105, 000
Contributed funds ___- ___.______---
                           .         --........... -             --           524, 778                34, 800       559, 578
       Total_____ _____---..............
                    ... __        _      ---             ---          -     1, 338, 796          1,240, 679      2, 579, 475
1320           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                      Cost and financial summary

                                               Fiscal year ending June 30                          Total to June
                                                                                                   30, 1954, includ-
                                                                                                   ing fiscal years
                               1950          1951           1952          1953          1954         prior to 1950'


New work:
   Appropriated    ..------------              ------------ -----------------------------------             814, 018
   Cost.....          ...------------
                             --------------------------------------------------------
                                             .                                                              814,018
Maintenance:
   Appropriated--..---         $58,000        $46, 412     $111, 500     $114, 555      $59, 000          1, 207, 039
   Cost-- ---------             15,106         91,312       110,597       114,719        58,922           1,205,879

I Exclusive of contributed funds of $524,778 for new work and $34,800 for maintenance.
Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project -_          - - - - --- - - - -- $63, 982

                             12. OAKLAND HARBOR, CALIF.
  Location. This harbor is on the eastern side of San Francisco
Bay, opposite the city of San Francisco. The inner harbor is situ-
ated between the cities of Oakland and Alameda. (See U. S. Coast
and Geodetic Survey Chart No. 5535.)
  Previous projects. Adopted by the River and Harbor Acts of
June 23, 1874, June 13, 1902, and March 2, 1907. For further
details, see page 1979 of Annual Report for 1915, page 1755
of Annual Report for 1921, and page 1674 of Annual Report for
1938.
    Existing project. This provides for an entrance channel to Oak-
land Outer Harbor, 35 feet deep from deep water in San Francisco
Bay and 800 feet wide across the shoal southeast of Yerba Buena
Island, thence narrowing to 600 feet at Oakland Mole; thence a
channel and turning basin 35 feet deep and from 600 to 950 feet wide
in the outer harbor to the Army Base. The project also provides for
an entrance channel to Oakland Inner Harbor, 30 feet deep and 800
feet wide at the bayward end, narrowing to 600 feet wide at the
ends of the Oakland jetties; a channel from the ends of the jetties
30 feet deep and 600 feet wide to the west end of Government
Island, with additional widening to the pierhead line in front of the
Grove and Market Street (formerly municipal) piers, and widening
to within 75 feet of the pierhead line along the south side of the
channel from Harrison Street eastward to harbor-line point 119 in
Brooklyn Basin; a channel 30 feet deep and 500 feet wide through
Brooklyn Basin; for dredging to a depth of 30 feet a triangular
area about 2,700 feet long and of a maximum width of 300 feet
at the western end of Brooklyn Basin; maintenance of a channel 25
feet deep and 300 feet wide at the north end of Brooklyn Basin; a
turning basin at the east end of Brooklyn Basin 30 feet deep, 500
feet wide, and 1,200 feet long; a navigation channel in the tidal
canal 30 feet deep and 275 feet wide from Brooklyn Basin to Park
Street, thence 25 feet deep to San Leandro Bay; a total channel
length of 81/2 miles from San Francisco Bay to San Leandro Bay.
The project also includes parallel rubble-mound jetties at the en-
trance to the inner harbor, a north jetty 9,500 feet long and a south
jetty 12,000 feet long; and three highway bridges across the tidal
canal, two of which (at Park Street and High Street) have been
     RIVERS AND HARBORS-SAN FRANCISCO, CALIF., DISTRICT                                                    1321
replaced by local interests. The railroad and highway bridges at
Fruitvale Avenue are being maintained and operated by the United
States. All depths refer to mean lower low water.
  The range between mean lower low water and mean higher high
water is 6 feet in the outer harbor and 6.3 feet in the inner harbor
at the Park Street Bridge. The extreme range is about 11 feet.
  The estimate of cost for new work (1954) is $3,111,100, exclusive
of contributed funds in the amount of $83,547 and of amounts ex-
pended on previous projects. The latest (1954) approved estimate
for annual cost of maintenance is $209,000.
  The existing project was authorized by the following River and
Harbor Acts:

                 I
     Acts                               Work authorized                                  Documents


June 23,1874         Jetties ............ ...............   __-......_.....   Annual Report, Part II, 1874,
                                                                                p. 378.
June 25, 1910        North channel in Brooklyn Basin and tidal canal to       H. Doc. 647, 61st Cong., 2d sess.
                       18 feet.
Sept. 22, 1922  Channel across the shoal southeast of Yerba Buena             H. Doc. 144, 67th Cong., 2d sess.
                  Island, and thence to Webster St.; south channel
                  in Brooklyn Basin; turning basin at the east end of
                  Brooklyn Basin; and the channel in the tidal canal
                  from Brooklyn Basin to Park St.
Jan. 2, 1927 Channel from Webster St. to Brooklyn Basin, the                  H. Doc. 407, 69th Cong., Ist sess.'
                  maintenance of the area to within 75 feet of the pier-
                  head line south of the channel from Harrison St. to
                  harbor line point 119 in Brooklyn Basin; dredging of
                  a triangular strip about 2,700 feet long and maxi-
                  mum width of 300 feet and deepening to 25 feet of the
                  tidal canal above Park St. to San Leandro Bay.
Apr. 28, 1928 Local cooperation requirements modified to provide              Public Res. 28, 70th Cong.
                  that alteration or replacement of bridges by local
                  interests shall apply only to that feature of the
                 project covering the deepening of the tidal canal to
                 25 feet.
                The draw bridges across the tidal canal were required
                 by the 1882 decree of the court in the condemnation
                 proceedings whereby title was obtained to the
                 right-of-way for the tidal canal.
July 3, 1930 Entrance channel to the outer harbor, 800 feet to                Rivers and Harbors Committee
                 600 feet wide.                                                 Doe. 43, 71st Cong., 2d sess.
Mar. 2,1945 Elimination of requirement that local interests con-              H. Doec. 466, 77th Cong., lst sess.
                 tribute 10 cents per cubic yard toward deepening
                 the tidal canal.
    Do       .Deepening     channel to outer harbor to 35 feet and            Report on file in Office, Chief of
                 maintenance of channel and turning basin in outer             Engineers.
                 harbor.

1 Contain   latest published maps.


   Local cooperation. The act of January 21, 1927, as modified by
the act of March 2, 1945, requires that local interests contribute
one-half the cost of the entrance channel (400 feet wide) to the
outer harbor and that the future maintenance by the United States
of the north channel in Brooklyn Basin be contingent upon the
removal by local interests of all sewers emptying therein, or, in lieu
of such removal, upon the contribution of one-half the cost of
maintenance (H. Doc. 407, 69th Cong., 1st sess., and H. Doc. 466,
77th Cong., 1st sess.). The first of the above requirements has
been fulfilled. The others have not been fulfilled. In compliance
with a 1910 license issued by the Secretary of War pursuant to
provisions of the act of June 25, 1910, local interests have replaced
the bridges at Park Street and High Street and are operating and
 1322             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

maintaining them. They have been legally unable to continue to
maintain, operate, or replace a combined railroad and highway
bridge at Fruitvale Avenue because of a decision rendered by the
California Court of Appeals that it was illegal for them to use
appropriated funds for the sole benefit of a private corporation.
The Southern Pacific Railroad Co. operated trains over the com-
bined bridge until June 1951 when a separate railroad bridge,
constructed for its use by the Federal Government, was placed in
operation. (The railroad and highway bridges at Fruitvale Ave.
are maintained and operated by the United States.)
   Terminalfacilities. In the inner harbor there are 64 wharves of
which 36 are owned by the Port of Oakland, 7 shipyards, 2 ferry
terminals and numerous small boat moorings. In the outer harbor
there are 5 wharves, owned by the Port of Oakland, and 2 privately
owned ferry terminals. These facilities are exclusive of those
owned by the United States and are considered adequate for exist-
ing commerce.
   Operationsand results during fiscal year. As maintenance, the
following work was performed at the indicated costs:
IT . S. hopper dredges Davison and Hyde removed 509,792 cubic yards of
    material from the inner and outer harbors--.............---.----                                          -------- .. $142, 649
By contract, 481 cubic yards of material was removed from the channel
    adjacent to the Ninth Avenue Pier.,--------------------........-----------                                                  1,156
Repair of the deck swing span and superstructure of Fruitvale Avenue
    Highway Bridge was accomplished by contract-------                    ...................--------------................... 27,090
Miscellaneous rehabilitation of Fruitvale Avenue Highway Bridge was
    accomplished by hired labor--.....................----------------------................................................    4,301
Engineering and design for repair of the Fruitvale Avenue Highway Bridge
    approaches was accomplished by hired labor--------------------......................----...........................         3, 605
Condition and operation studies and inspections and reports were made
    by hired labor....----------------------------------------------7,398
The Fruitvale Highway and Railroad Bridges were operated and main-
    tained by hired labor------.........        ---------------------------------------                                        50,857
          Total maintenance during fiscal year.............................--------------------......---........        237, 056
   Condition at end of fiscal year. The existing project is about 82
percent complete. The work remaining to be done is the deepening
to 25 feet of the tidal canal above the Park Street Bridge. The
jetties were completed in 1894. Dredging of the various project
channels was completed in 1931 except for the deepening of 'the
tidal canal above Park Street Bridge. The 35-foot depth in the
channel to the outer harbor was obtained in 1942 with military
funds.
  The controlling depths in the project channels on the dates
indicated were as follows: April 1954, 30 feet in the entrance chan-
nel to the outer harbor, and 28 feet in the entrance channel to the
inner harbor; January 1953, 29 feet in. the inner harbor to Fort-
mann Basin, and 28 feet to the westerly end of Government Island;
in April 1954, 24 feet to the Park Street Bridge; June 1952, 16 feet
in the, tidal canal to Fruitvale Avenue Bridge; August 1950, 17
feet in the tidal canal to San Leandro Bay, and 18 feet in the north.
channel of BrQoklyn Basin.
    RIVERS AND HARBORS-SAN FRANCISCO, CALIF., DISTRICT                                                                   1323
  The costs of the existing project to the end of the fiscal year were
as follows:

                                                                          New work           Maintenance              Total
                                                                             costs                 costs              costs

Regular funds-------------------------------....        $2,622, 031                                $4,489,285         $7, 111, 316
Contributed funds...-----------------------------------     83, 547                                    ----                83, 547
     Total ..--_   -   ______________
                        -    -        -    ...-    -        -   ......
                                                                  -          2, 705, 578           4, 489, 285         7, 194, 863



                                          Cost and financial summary

                                                       Fiscal year ending June 30                                 Total to June
                                                                                                                 30, 1954, includ-
                                                                                                                 ing fiscal years
                                1950               1951               1952            1953            1954        prior to 1950 12


New work:
   Appropriated                   --                   --        -               -   -              ---               $5,521,263
   Cost .-----------                                                                                                   5,521,263
Maintenance:
   Appropriated----            $847,450           $ 82,275           $237, 000       $168, 250      $306, 000          5, 277, 471
   Cost_ ______________         635,360               355
                                                   531,               336,207            143,352     237,056          35,173,313

  ' Includes $2,899,232 for new work and $684,028 for maintenance of previous projects. The cost reported
in prior years included the work accomplished under authority of the River and Harbor Act of June 25,
1910. This cost being chargeable to the existing project.
  A Exclusive of contributed funds of $83,547 for new work on the existing project.

  * Includes $408,137 for operation and care of Fruitvale Ayenue Bridges.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project   _  ___ _- - - -  -- _       $489,038

                        13. REDWOOD CITY HARBOR, CALIF.
   Location. Redwood City Harbor is on Redwood Creek, a tribu-
tary of San Francisco Bay about 20 miles south of the city of San
Francisco. The project works also include a channel in San Fran-
cisco Bay east of Point San Bruno. (See U. S. Coast and Geodetic
Survey Chart No. 5531.)
   Previous projects. The original project was adopted by the
River and Harbor Act of July 5, 1884, and modified by the River
and Harbor Act of June 13, 1902. For further details, see page
1979 of Annual Report for 1915, and page 1672 of Annual Report
for 1938.
   Existing project. This provides for a channel 500 feet wide and
30 feet deep across San Bruno Shoal in San Francisco Bay; a chan-
nel 300 feet wide and 30 feet deep to the vicinity of the confluence
of West Point Slough and Redwood Creek, with a basin at that loca-
tion 2,200 feet long and from 400 to 900 feet wide; thence a
channel 400 feet wide, 30 feet deep, and approximately 1,300 feet
long flaring to a second turning basin approximately 900 feet wide,
1,700 feet long, and 30 feet deep; thence a channel 150 feet wide
and 5 feet deep extending to Steinberger Slough.
   All depths refer to mean lower low water. The tidal range be-
tween mean lower low water and mean higher high water is 6.9
feet at Point San Bruno and 7.9 feet at Redwood City. The ex-
treme ranges are estimated to be 12 feet and 13 feet at the
respective localities.' The authorized channel across San Bruno
Shoal is about 4-173 miles long. In the creek, the authorized deep-
1324             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

water channel is 3.4 miles long including the basins, and the 5-foot
channel extends to mile 4.3.
  The estimate of cost for new work (1954) is $1,670,000, exclusive
of $119,572 contributed by local interests and of the amounts ex-
pended on previous projects. The latest (1954) approved estimate
for annual cost of maintenance is $102,500.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                        Work authorized                                    Documents
June 25, 1910    A 5-foot channel to Steinberger Slough....------------    H. Doc. 307, 61st Cong., 2d sess.
July 3, 1930     A 20-foot channel to West Point Slough.....------------   H. Doc. 142, 70th Cong., 1st sess.
Aug. 30, 1935    A 27-foot channel to West Point Slough and a turn-        Rivers and Harbors Committee
                   ing basin 27 feet deep, 1,800 feet long, and 700 feet     Doc. 10, 73d Cong., 1st sess.
                   wide.
Mar.    2,1945   A 30-foot channel across San Bruno Shoal and en-          H. Doc. 94, 79th Cong., 1st sess.
                   larging and deepening the 27-foot channel and
                   turning basin in Redwood Creek to 30 feet.
May 17, 1950     Extending the 30-foot channel 1,300 feet upstream         H. Doc. 104, 81st Cong., 1st sess.
                   and providing a second turning basin 30 feet deep,        (Contains latest published map.)
                   900 feet wide and 1,700 feet long at junction of Red-
                   wood Creek and Boundary Slough.        Project name
                   changed from Redwood Creek, Calif., to Redwood
                   City Harbor, Calif.


   Local cooperation. The act of August 30, 1935, requires that
local interests furnish areas for disposal of dredged material re-
moved during maintenance; the requirements for new work have
been fully complied with for work performed to date. No local
cooperation is required by the act of March 2, 1945. The act of
May 17, 1950, requires that the port of Redwood City give assur-
ances satisfactory to the Secretary of the Army that it will (1)
provide, without cost to the United States, all necessary land,
easements, rights-of-way, and spoil disposal areas with necessary
impounding works, for the construction and subsequent mainte-
nance of the project, when and as required; (2) hold and save the
United States free from damages due to the construction and sub-
sequent maintenance of the works; (3) arrange with responsible
local interests to relocate, without cost to the United States, the
municipal yacht harbor and provide new facilities at least equal
to those now available; (4) maintain at its own expense the exist-
ing public terminal and construct and maintain, without cost to
the United States, an additional public wharf, sufficient in size to
accommodate a modern cargo vessel, located on the proposed
extension of the project, with the understanding that all public
terminals shall be open to all on equal terms. Thee board of port
commissioners of the city of Redwood City has passed a resolution
of intent to comply with these requirements.
   Terminal facilities. There are 3 municipally owned wharves, 3
privately owned wharves, a boat repair yard, a bulk salt loading
facility, and a pleasure boat mooring in Redwood City Harbor. Local
interests have definite plans for additional facilities to accommo-
date anticipated increases in commerce.
   Operations and results during fiscal year. As maintenance, the
U. S. hopper dredge Davison removed 62,938 cubic yards of mate-
rial from the entrance channel and outer turning basin at a cost of
$21,591, and condition and operation studies and inspections and
    RIVERS AND HARBORS-SAN FRANCISCO, CALIF., DISTRICT                                                          1325
reports were accomplished by hired labor at a cost of $4,528. The
total maintenance cost during the fiscal year was $26,119.
   Condition at end of fiscal year. The existing project is about 20
percent complete. The work remaining to be done is the widening
and deepening of the channel across San Bruno Shoal, and of the
channel and turning basin in Redwood Creek as authorized by the
act of March 2, 1945, and the channel and turning basin in Redwood
Creek as authorized by the act of May 17, 1950.
  The controlling depths in the various channels on the dates in-
dicated were as follows: April 1954, 27 feet in San Bruno Shoal
Channel; March 1954, 26 feet in San Francisco Bay to the outer
turning basin; May 1954, 24 feet in the turning basin, 10 feet to
the municipal yacht harbor, and 3.5 feet to Steinberger Slough,
except at extreme end of project where depth was 1.5 feet.
  The cost of the existing project to the end of the fiscal year was
as follows:

                                                                 New work            Maintenance             Total
                                                                   costs                costs                costs

Regular funds___                                        $129, 893     $592, 671          564
                                                                                   $722, 572
Contributed funds------------------------------------$119,
Oontributed funds                                             572----------------119,
                                                         119, 572 ._     __ .119,
                                                                        .____   _        572
     Total     .....   ...------------------         _
                                               .-------                  249,465             592,
                                                                                                671              842, 136



                                          Cost and financial summary

                                                   Fiscal year ending June 30                            Total to June
                                                                                                        30, 1954, includ-
                                                                                                        ing fiscal years
                                 1950             1951        1952            1953           1954       prior to 1950 12


New work:
   Appropriated                                                                                                 $161, 336
   Cost __...                                                          i
                                                                     -----           -----------                 161,336
Maintenance:
   Appropriated.                -$7, 000          $49, 800     $3, 000       $100, 725       $24, 000            593, 351
   Cost__---------------          55,147           49, 589      3,176          98,373    1    26,119             592,671


  IIncludes $31,443 for new work on previous projects.
2 Exclusive of contributed funds of $119,572 for new work on existing project.
Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project                          1,540,107
                                                                     $____________________

                                 14. HALFMOON BAY, CALIF.
   Location. Located on the coast of California about 15 miles
south of San Francisco. (See U. S. Coast and Geodetic Survey
Chart No. 5520.)
   Existing project. This provides for the construction of two
rubble-mound breakwaters each approximately 4,400 feet long.
The tidal range between mean lower low water and mean higher
high water is 5.5 feet. The extreme range is about 8 feet. The
estimate of cost for new work (1954) is $6,420,000, including
$12,100 for navigation aids, but exclusive of $100,000 to be con-
tributed by local interests. The (1954) estimate for annual cost
of maintenance is $43,800.
  The existing project was authorized by the River and Harbor
 1326            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Act approved June 30, 1948. (H. Doc. 644, 80th Cong., 2d sess.)
The latest published map is contained in that document.
    Local cooperation. The River and Harbor Act of June 30, 1948,
requires that local interests establish a competent and properly
constituted public body empowered to administer the harbor facili-
ties, and furnish assurances satisfactory to the Secretary of the
Army that they will: (1) make available to the United States the
right to obtain, free of royalty costs, the necessary stone for the
initial construction and future maintenance of the breakwaters
from a source or sources acceptable to the district engineer, when
and as required; (2) provide without cost to the United States all
necessary lands, easements, and rights-of-way for the construction
and maintenance of the project; (3) hold and save the United
States free from claims for damages due to construction and main-
tenance of the project; (4) provide and maintain without cost to
the United States necessary utilities and mooring facilities in-
cluding a public landing with suitable supply facilities open to
all on equal and reasonable terms; and (5) contribute toward the
first cost of the improvement the sum of $100,000. Local interests
have established the San Mateo County Harbor Commission which
has initiated action for the fulfillment of the requirements for
local cooperation.
    Terminal facilities. There are 3 privately owned piers, each
with boat-fueling facilities and 1 with a sardine conveyor pipeline
to a plant located on shore. These facilities are considered ade-
quate for existing commerce.
    Operations and results during fiscal year. No work was ac-
complished.
    Condition at end of fiscal year. No construction has been per-
formed on this project. Engineering and design is approximately
41 percent complete. The cost of the existing project to the end
of the fiscal year was $36,875 for new work.
                                           Cost and financial summary

                                                        Fiscal year ending June 30                 Total to June
                                                                                                  30, 1954, includ-
                                                                                                  ing fiscal years
                                    1950               1951        1952             1953   1954    priorto 1950

New work:
   Appropriated--------
   Cost       __-----------------
                                    $75,900
                                     22,812   (   --      -
                                                       $8,433
                                                                 -- $38, 125 - --836,
                                                                      5,630        -
                                                                                                               875
                                                                                                            36,875


Other new work data: Estimated additional amount needed to be appro-
  ated for completion of existing project                             6,383125
                                                                     $------------------------
                            15. MOSS LANDING HARBOR, CALIF.
   Location. This harbor is approximately 80 miles south of San
Francisco Harbor on Monterey Bay about midway between the
cities of Santa Cruz and Monterey. See U. S. Coast and Geodetic
Survey Chart No. 5403.)
   Existing project. This provides for an entrance channel 200
feet wide and 15 feet deep, protected by jetties, from Monterey
Bay into the inner lagoon at Moss Landing, thence a channel in
the lagoon, 100 feet wide, 15 feet deep, and approximately 3,200
feet long extending southerly from the entrance, with a flared
    RIVERS AND HARBORS-SAN FRANCISCO, CALIF., DISTRICT                                              1327
widening to a width of 200 feet for a length of 400 feet at the
southerly end.
   All depths refer to mean lower low water. The tidal range be-
tween mean lower water and mean higher high water is 5.3 feet
with an estimated extreme range of 10.5 feet.
   The cost of new work under the project, completed in 1947, was
$343,552. The latest (1954) approved estimate for annual cost of
maintenance is $34,000.
   The existing project was authorized by the River and Harbor
Act approved March 2, 1945. (Report on file in the Office of the
Chief of Engineers.) No map has been published.
  Local cooperation. The act of March 2, 1945, requires that local
interests furnish the necessary rights-of-way and suitably bulk-
headed spoil disposal areas for new work and subsequent main-
tenance, when and as required, and hold the United States free
from claims for damages resulting from construction work. The
requirements for new work have been fulfilled.
   Terminal facilities. There are 5 piers, 1 of which has boat fuel-
ing facilities, 1 oil receiving terminal, several fish receiving hop-
pers, and a number of mooring facilities within the protected har-
bor. Outside the harbor in Monterey Bay there is 1 privately
owned submerged petroleum pipeline and 1 pier which is used
for receipts of petroleum products. These facilities are not ade-
quate, but plans have been made for improvements to accommo-
date prospective commerce.
   Operations and results during fiscal year. As maintenance,
78,864 cubic yards of material was removed from the project by
contract at a cost of $32,748; engineering and design was initiated
by hired labor, at a cost of $1,046, for repair of the north jetty
by contract; and condition and operation studies and inspections
and reports were made by hired labor at a cost of $1,753. The
total maintenance cost during the fiscal year was $35,907.
   Condition at end of fiscal year. The project was completed in
1947, The controlling depths on the dates indicated were as fol-
lows: February 1954, 10 feet in the entrance channel, except 5
feet near the south edge of channel; August 1953, 16 feet in the
inner channel and turning basin.
   The cost of the existing project to the end of the fiscal year was
$338,215 for new work and $866,139 for maintenance, a total of
$1,204, 354, exclusive of surplus material from Corps of Engineers'
military activities.
                                     Cost and financial summary

                                             Fiscal year ending June 30                     Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                              1950         1951         1952         1953         1954       prior to 1950


New work:
   Appropriated_-----------         -- ------------ ----------------- -----------------         $338,215.50
   Cost...------------ -------------- -------------------------------------------               1338,215.50
Maintenance:
   Appropriated ..            $33,000    -$36, 800       $3, 500    $134,200    -$19, 000            866,900
   Cost..-----------------      1,163        1,911        2,886       79,145       35,907          ' 866,139

SExclusive of $5,337 surplus material from Corps of Engineers' military activities.
2 Exclusive of $8,539 surplus material from Corps of Engineers' military activities.
1328              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                             16. MONTEREY HARBOR, CALIF.
  Location. This harbor is about 90 miles south of San Francisco
Bay, at the south end of Monterey Bay, an indentation in the coast
of California. (See U. S. Coast and Geodetic Survey Chart No.
5403.)
   Previous projects. Adopted by the River and Harbor Act of
July 25, 1912. No work was done. No expenditures were made.
   Existing project. This provides for a breakwater 1,700 feet
long, with the shore connection extending about 750 feet due east
from a point about half-way between Reeside Avenue and the
Presidio boundary, and the outer section bearing about S. 70 ° E.; a
harbor depth of 8 feet adjacent to municipal wharf No. 1; and a
sand trap, 500 feet long, to prevent further encroachment of sand
into the protected portion of the harbor. The tidal range between
mean lower low water and mean higher high water is 5.5 feet. The
extreme range is about 10 feet.
   The estimate of cost for new work (1954) is $916,000. The
latest (1954) approved estimate for annual cost of maintenance is
$22,500.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                         Work authorized                                Documents

July    3, 1930   Breakwater, 1,300 feet long   ---------------------   Rivers and Harbors Committee
                                                                          Doc. 12, 71st Cong., 1st sess.
Aug. 30, 19351    Extension of breakwater to length of 1,700 feet--------
                                                                        Rivers and Harbors Committee
                                                                          Doe. 45, 72d Cone., 1st sess. 2
Mar.     2,1945   Harbor depth of 8 feet and sand trap--------------    H. Doe. 266, 76th Cong., 1st sess.


  1 Previously authorized Public Works Administration program, Sept. 6, 1933.
2  Contains latest published map.


   Local cooperation. The River and Harbor Act of March 2. 1945,
required that local interests furnish, free of cost to the United
States, necessary easements for the construction and maintenance
of the sand trap, and hold and save the United States free from
claims for damages resulting from the improvements; and pro-
vided further that local interests bear the excess cost of placing
dredged materials in disposal areas of their selection. These re-
quirements have been complied with for the work performed to
date. All prior requirements have been fulfilled.
   Terminal facilities. Within the protected harbor the existing
commercial facilities consist of 2 publicly owned wharves with a
total of about 2,600 feet of berthing space, 3 boat fueling stations,
2 net tanning plants, 2 machine shops and other facilities for serv-
icing fishing boats, exclusive of facilities owned by the United
States. Outside the protected harbor there are 1 boatbuilding and
repair plant, 35 anchored floating fish-receiving hoppers connected
by pipelines to the sardine plants ashore, 2 submarine pipelines
between tanker moorings and shore plants for handling petroleum
products, and other facilities for servicing fishing boats. The
facilities are considered adequate for existing commerce, although
a state of congestion generally exists within the protected harbor
due to a lack of sufficient protected anchor mooring space.
        RIVERS AND HARBORS-SAN FRANCISCO, CALIF., DISTRICT                                                                                1329
   Operations and results during fiscal year. As maintenance,
8,049 cubic yards of material was removed by contract from areas
adjacent to municipal wharf No. 1 at a cost of $13,036, and condi-
tion and operation studies and inspections and reports were made
by hired labor at a cost of $434. The total maintenance cost during
the fiscal year was $13,470.
   Condition at end of fiscal year. The existing project is about 78
percent complete. The breakwater was completed in 1934. The
harbor was dredged to within approximately 120 feet of the shore-
ward limits of the project in 1947. The work remaining to be done
is the completion of the dredging to project limits, and the con-
struction of the sand trap.
   The controlling depth in the completed portion of the harbor in
August 1953 was 8 feet except in the extreme southerly portion
which was 6.1 feet easterly of municipal wharf No. 1 and 6.0 feet
westerly of municipal wharf No. 1.
   The costs of the existing project to the end of the fiscal year were
as follows:

                                                                                          New work         Maintenance                Total
                                                                                              costs             costs                 costs

Regular funds-------...          .__-         ___ _____               _
                                                                  -____.....                 $490, 671                $50, 904           $541, 575
Publi works funds              ----------------------------------
                               ................                                               207, 800        ,----------------207,           800
        Total                  ...              ....      ...                                 698, 471
                                                                       ...----------------------------------------     50,904             749,375



                                                   Cost and financial summary

                                                                 Fiscal year ending June 30                                       Total to June
                                                                                                                                 30, 1954, includ-
                                                                                                                                 ing fiscal years
                                           1950                 1951              1952             1953               1954        prior to 1950


New work:
   Appropriated--            ---          $45,520 .---                                                                                   $698,471
   Cost ....----------------------------------------------------------------                                                              698, 471
Maintenance:
   Appropriated ... ---                    14, 700          -- $1,175               $2,500        $30, 925           -$3,700               51,500
   Cost --....-------------                               -
                                           15, 940- ........            .          -2, 085         13, 574             13, 470             50, 904


Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project--------------_---             $217, 529

                                        17. NAWILIWILI HARBOR, T. H.
   Location. This harbor is on the southeast coast of the island of
Kauai, and about 100 nautical miles northwest of Honolulu. (See
U. S. Coast and Geodetic Survey Chart No. 4111.)
   Existing project. This provides for a rubble-mound breakwater
about 2,150 feet in length along the reef which separates this bay
into an inner and an outer harbor; for an entrance channel 35 feet
deep with a minimum width of 600 feet and a length of about 2,400
feet; for a harbor basin 35 feet deep, 1,100 feet wide, and with an
average length of about 2,000 feet protected by a filled area in addi-
tion to the protection afforded by the breakwater.                                                                       The plane of
reference is mean lower low water. The tidal range between mean
1330      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

lower low water and mean higher high water is about 1.8 feet, the
extreme tidal range being about 4 feet.
    The cost of new work under the project, completed in 1930, was
 $1,197,178, exclusive of $200,000 contributed by local interests.
The latest (1954) approved estimate for annual cost of mainte-
nance is $28,000.
    The existing project was authorized by the River and Harbor
Act of March 2, 1919 (H. Doc. 609, 62nd Cong., 2d sess., as modified
by the Chief of Engineers). The latest published map is found in
the project document.
    Recommended modification of project. Modifications to the ex-
isting project are recommended by the Chief of Engineers in House
Document 453, 83d Cong., 2d sess., to provide for deepening the
entrance channel to 40 feet below mean lower low water; enlarge-
ment of the harbor basin by dredging along its westerly side an
additional area 440 feet wide with an average length of 1,230 feet
and a depth of 35 feet below mean lower low water; and construc-
tion of a revetted-fill area by deposition of dredge spoil between
the shore and bulkhead line west of the harbor basin; all generally
in accordance with the plans of the district engineer and with such
modifications thereof as in the discretion of the Chief of Engineers
may be advisable; at an estimated cost to the United States of
 $1,121,600 for new work and $5,000 annually for maintenance in
addition to that now required; subject to the condition that local
interests agree to: (1) furnish free of cost to the United States, all
lands, easements, rights-of-way, and quarrying rights necessary for
construction and maintenance of the improvements, and suitable
spoil disposal areas for the new work and for subsequent mainte-
nance when and as required; (2) hold and save the United States
free from damages due to the construction and maintenance of the
improvements; (3) contribute in cash a sum sufficient to pay for
the total cost of construction of the revetment of the fill area,
presently estimated at $38,500; (4) maintain the revetment; (5)
provide, maintain, and operate adequate terminal and transfer fa-
cilities open to all on equal terms; and (6) operate the improved
harbor in accordance with regulations prescribed by the Secretary
of the Army.
    Local cooperation. Fully complied with for completed work.
    Terminal facilities. The Territory of Hawaii owns a reinforced
concrete wharf with two sheds thereon. Pipelines for kerosene,
gasoline, molasses, and water are available. There is also a plant
for storing, handling, and loading bulk sugar. The plant consists
of a reinforced concrete and steel storage building with a storage
capacity of 28,000 tons, and conveying belts of various widths.
The facilities of the harbor are open to all on equal terms and are
considered adequate for existing commerce.
    Operations and results during fiscal year. As maintenance,
condition and operation studies and inspections and reports were
accomplished by hired labor at a cost of $4,153.
    Condition at end of fiscal year. The project was completed in
July 1930. The controlling depths in May 1953 were 32.6 feet in
the entrance channel and 34.5 feet in the harbor basin.
    RIVERS AND HARBORS-SAN FRANCISCO, CALIF., DISTRICT                                                        1331
  The costs for the existing project to the end of the fiscal year
were as follows:
                                                                New work           Maintenance            Total
                                                                    costs              costs               costs

Regular funds-----------------------------------                    $1, 197,178          $332,142          $1, 629,320
Contributed funds ----------------------------------                    200, 000       ----                    200,000

      Total--- ---............-----............                      1, 397, 178         332, 142           1, 729, 320



                                        Cost and financial summary

                                                   Fiscal year ending June 30                         Total to June
                                                                                                    . 30, 1954, includ-
                                                                                                     ing fiscal years
                                 1950             1951       1952           1953         1954          prior to 1950 1


New work:
                 .....
    Appropriated-------      ------- ------------ ------------ ---------- -----------                      $1, 197,178
    Cost---------       ---------------------------------    ------------ -----------                       12 197, 178
Maintenance:
    Appropriated- ------.         $3, 500         $24,956     $4, 006        $3, 450      $5, 000              338,851
    Cost-.--------------           1, 742           2, 930    31, 215         3,010        4,153             2 332,142


  SExclusive of contributed funds of $200,000 for new work.
  2 Exclusive of $4,187 expended for rock stockpile.



                             18. PORT ALLEN HARBOR, T. H.
   Location. This harbor is located in Hanapepe Bay on the south-
ern coast of the island of Kauai, about 110 nautical miles northwest
of Honolulu. (See U. S. Coast and Geodetic Survey Chart No.
4108.)
   Existing project. This provides for a rubble-mound breakwater
about 1,200 feet long on the east side of the bay; for the dredging
of a harbor basin about 1,200 feet wide, 1,500 feet long, and 35 feet
deep; and an entrance channel 500 feet wide and 35 feet deep.
   The plane of reference is mean lower low water. The range of
tide between mean lower low water and mean higher high water is
1.7 feet, and the extreme tidal range under ordinary conditions is
2.7 feet.
   The cost of new work under the project, completed in 1948, was
$752,645 exclusive of $200,000 contributed by local interests. The
latest (1954) approved estimate for annual cost of maintenance is
$13,000.
   The existing project was authorized by the following River and
Harbor Acts:
    Acts                            Work authorized                                       Documents
Aug. 30,1935 1 Construction of a breakwater 1,200 feet long; dredging          H. Doe. 30, 73d Cong., 1st ses.
                of a harbor basin about 1,000 feet wide, 1,500 feet
                long, and 35 feet deep; and an entrance channel 500
                feet wide and 35 feet deep.
Mar. 4,1945 Additional dredging of an area at the northerly side               H. Doe. 180, 77th Cong., 1st seas.
                of the existing project, 200 feet wide, 1,200 feet long,        (Contains latest published map.)
                and 35 feet4eep.

1 Ineluded in the Public Works Administration program, Sept. 6, 1933.

   Local cooperation. Fully complied with.
   Terminal facilities. The Territory of Hawaii owns a concrete
 1332            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

wharf with a concrete-steel transit shed. The wharf is operated by
the Territorial Board of Harbor Commissioners, and is open to
shipping on equal terms. Pipelines for oil and molasses and a
sugar conveyor are available. The facilities are considered ade-
quate for existing commerce.
   Operations and results during fiscal year. As maintenance,
condition and operation studies and inspections and reports were
accomplished by hired labor at a cost of $2,521.
   Condition at end of fiscal year. The existing project was com-
pleted in May 1948. The portion of the existing project authorized
prior to the modification adopted by the River and Harbor Act of
March 2, 1945, was completed in September 1935. The controlling
depth in June 1953 was 32.9 feet in the harbor basin.
  The costs for the existing project to the end of the fiscal year
were as follows:
                                                                            New work           Maintenance              Total
                                                                                costs             costs                 costs

Regular funds.......--------------------- -------_                                  72, 645       $80,865                  $153, 510
Public Works funds---------------------------------                                680,000-................                 680, 000
Oontributed funds...        ...      ...       ..   .     ...       ..             200, 000 . ..........       .            200,000
      Total .... __               . . .... . . . _ _.                              952, 645            865
                                                                                                     80so,                1,03, 510

                                           Cost and financial summary

                                                     Fiscal year ending June 30                                     Total to June
                                                                                                                   30, 1954, includ-
                                                                                                                   ing fiscal years
                                    1950            1951                 1952           1953        1954            priorto 1950 1


New work:
   Appropriated---------------------------------------------                                                               $752,645
    Cost....---------   ------------ -----------------------------------------------                                        752,645
Maintenance:
    Appropriated                     $2, 020             $485            $4, 000         $3,100      $5, 000                 84,948
         .267
    Cost-----------------                               3,718   1         2,737           2,760       2, 521                 80, 865


  1 Exclusive of contributed funds of $200,000 for new work.

                                      19. KEEHI LAGOON, T. H.
   Location. Keehi Lagoon is on the south coast of the island of
Oahu, approximately midway between the entrance to Honolulu
Harbor and the entrance to Peairl Harbor. (See U. S. Coast and
Geodetic Survey Charts Nos. 4132 and 4110.)
   Existing project. This provides for construction of a seaplane
harbor as follows:
   a. Three intersecting runways (designated A, B, and D on proj-
ect map), each 10 feet deep and 1,000 feet wide, of lengths 2.9
miles, 3 miles; and 2.25 miles, respectively.
   b. Two rock breakwaters of lengths 2,500 lineal feet and 2,000
lineal feet at the seaward ends of the runways.
   c. A mooring basin 800 feet long by 400 feet wide by 10 feet
deep at the northwesterly side and midway of runway A.
   (Note. As a wartime measure, the basin was enlarged to 3,000 feet long by 500
feet wide.)
   d. Installation of a standard seaplane lighting system.
       RIVERS AND HARBORS-SAN FRANCISCO, CALIF., DISTRICT                                                                  1333

   The plane of reference is mean lower low water. The range of
tide between mean lower low water and mean higher high water is
1.9 feet, and the extreme tidal range under ordinary conditions is
2.3 feet.
   The cost of new work under the project, completed in 1944, was
$3,348,000. The latest (1954) approved estimate for annual cost
of maintenance is $5,000.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                                 Work authorized                                              Documents
Oct. 17,1940      Construction of a seaplane harbor of 3 intersecting                         H. Doc. 329, 76th Cong., 1st sass.
                   runways (A, B, and C) each 10 feet deep and 1,000
                   feet wide, of lengths 2.9 miles, 3 miles, and 1.4 miles,
                    respectively, with 2 protecting breakwaters at the
                    seaward ends thereof; a mooring basin, and stand-
                    ard seaplane lighting system.
Mar.     2,1945   Elimination of runway C and protective breakwater                            H. Doc. 379, 77th Cong., 1st sess.
                    and construction of runway D, about 2.25 miles                              (Contains latest published map.)
                    long, 1,000 feet wide, and 10 feet deep, with pro-
                    tective breakwater at the seaward end.

   Local cooperation. Fully complied with for new work. The
Act of October 17, 1940, requires that local interests furnish, free
of cost to the United States, all lands, easements, and rights-of-way
and spoil disposal areas as and when required for maintenance.
   Terminal facilities. Shore facilities are available for servicing
of seaplanes and are considered adequate.
   Operations and results during fiscal year. As maintenance,
condition and operation studies and inspections and reports were
accomplished by hired labor at a cost of $4,873.
   Condition at end of fiscal year. The existing project was com-
pleted in September 1944, except that no work was done on the rock
breakwaters at the seaward ends of the runways. The controlling
depths in January 1954 were 9.6 feet in runway A, 10 feet in run-
way B, and 10 feet in runway D.
  The cost of the existing project to the end of the fiscal year was
$3,348,000 for new work and $41,789 for maintenance, a total of
$3,389,789. In addition, $276,674 was paid from funds of the fol-
lowing agencies for new work: $92,526, Navy funds; $177,619, Civil
Aeronautics Authority funds; and $6,529, military funds.
                                                 Cost and financialsummary

                                                                Fiscal year ending June 30                          Total to June
                                                                                                                   30, 1954, includ-
                                                                                                                   ing fiscal years
                                       1950                  1951                     1952   1953       1954        priorto 19501

New work:
   Appropriated         -----------------------------------------------------------                                     $3,348,000
                      -------
   Cost..---..-------..             ------------------------------------                               ---------          3,348, 000
Maintenance:
   Appropriated---
                 ......      $6,500      $4, 6141.-               $5, 725                                $5, 000             41,939
   Cost__                                 6,336                 4,801------------..5,702                  4,873              41,789


SExclusive of the respective funds provided by the following agencies:
   Navy------ $ 92,526
   C.A.A...-         177, 619
   Military ..-        6, 529
 ., Total..... $276,674
1334              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                20. HONOLULU HARBOR, T. H.
   Location. This harbor is on the south coast of the island of
Oahu, about 2,100 nautical miles from San Francisco. (See U. S.
Coast and Geodetic Survey Chart No. 4109.)
   Existing project. This provides for an entrance channel 40 feet
deep and 500 feet wide; easing the curve where the entrance chan-
nel joins the inner harbor; deepening the harbor basin to 35 feet
for a general width of 1,520 feet; a depth of 35 feet in the channel
connecting Honolulu Harbor with Kapalama Basin, 1,000 feet wide
through the first 1,000 feet, thence 600 feet wide for the remaining
distance of 2,400 feet; a turning basin in Kapalama Basin 35 feet
deep by 1,000 feet wide and 3,000 feet long; and a slip of like
depth, 1,000 feet long on the easterly side of pier 39.
   The plane of reference is mean lower low water. The range of
tide between mean lower low water and mean higher high water is
1.9 feet, and the extreme tidal range under ordinary conditions is
2.3 feet.
   The cost of new work under the project, completed in 1945, was
$3,952,363. The latest (1954) approved estimate of cost of annual
maintenance is $15,000.
   The existing project was authorized by the following River and
Harbor Acts:
       Acts                        Work authorized                                   Documents

Mar. 3,1905       Deepening to 35 feet the inner harbor with a general    Annual Report 1905, p. 2565.
                    width of 1,200 feet and easing the curve between
                    the entrance channel and the inner harbor.
Aug.    8, 1917   For the channel 1,000 feet long-...................-    H. Doe. 392, 64th Cong., 1st sess.
July    3,1930    Channel connecting Honolulu Harbor and Kapa-            H. Doe. 753, 69th Cong., 2d seass.
                   lama Basin.
Aug. 80,19351     Enlarging entrance channel to present project dimen-    H. Doc. 54, 73d Cong., 1st seas.
                    sions, widening of the harbor basin by 320 feet and
                    the maintenance of the improved 400-foot wide por-
                    tion of the reserved channel.                                                             5
July 24,1946      A depth of 35 feet over the full width of 600 feet      H. Doc. 705, 79th Cong., 2d sess.
                   throughout the reserved channel; a turning basin
                    in Kapalama Basin 35 feet deep by 1,000 feet wide
                   and 3,000 feet long; and a slip of like depth 1,000
                   feet long on the easterly side of pier 39.

 ' Included in the Public Works Administration program Sept. 6, 1933.
aContains latest published map.

   Recommended modification of project. Modifications to the ex-
isting project are recommended in House Document 717, 81st Con-
gress, 2d session, to provide for a second entrance channel 35 feet
deep below mean lower low water extending seaward from the west
end of Kapalama Basin, having a width of 400 feet for 5,850 feet,
thence increasing to a width of 1,000 feet in a distance of 4,150
feet; and installation of a pontoon drawbridge or other suitable
movable-type bridge across the channel having a minimum clear
horizontal draw opening of 200 feet, all generally in accordance with
the plan of the district engineer and the comments of the Board of
Engineers for Rivers and Harbors, and with such modifications
thereof as in the discretion of the Chief of Engineers may be ad-
visable; at an estimated cost to the United States of $2,380,000 for
construction and $5,000 annually for maintenance of the navigable
channel in addition to that now required; provided that local in-
terests give assurances satisfactory to the Secretary of the Army
    RIVERS AND HARBORS-SAN FRANCISCO, CALIF., DISTRICT                                                   1335

that they will (1) provide without cost to the United States all
lands, easements, rights-of-way, and spoil disposal areas necessary
for the construction and subsequent maintenance of the project,
when and as required; (2) hold and save the United States free
from damage due to the construction works; and (3) relinquish to
the United States, without royalty charge, all salvageable material
removed from the channel; and provided further that the Territory
of Hawaii take title to the proposed drawbridge after construction
and maintain and operate it in accordance with regulations pre-
scribed by the Secretary of the Army.
    Local cooperation. Fully complied with on existing project.
    Terminal facilities. There are 37 piers and 2 marginal wharves
 (a 470-foot concrete wharf and a 2,600-foot timber wharf). The
Federal Government owns 4 of the piers and the 2 marginal
wharves. Of the remaining piers, 15 are owned by the Territory
of Hawaii, administered by the Territorial Board of Harbor Com-
missioners, and 18 are privately owned. Construction of a new
freight terminal at pier 2 by the Territory of Hawaii is in progress
to accommodate two C-3-type general cargo vessels and one lum-
ber cargo vessel. All piers owned by the Territory and private con-
cerns are open to all on equal terms. However, certain piers are
reserved for certain commodities such as oil, pineapples, and bulk
cement. Pipelines for diesel oil, fuel oil, kerosene, gasoline, dis-
tillate, molasses, and water are available.
    In addition to these facilities, the United States Army started
construction of a slip in the northerly side of Kapalama Basin ad-
jacent to the storage and terminal facilities in the vicinity of the
United States owned piers 39 and 40. The slip is 151 feet wide by
544 feet long on the westerly side, 468 feet long on the easterly
side, and 30 feet deep, and is intended for mooring of barges and
small vessels only. Work was suspended on August 22, 1945. At
that time, dredging was completed, piling was driven, and 450
lineal feet of concrete curtain wall and shelf were in place.
   There is a definite need for a powder and explosive terminal since
existing facilities do not permit the proper handling of this type of
cargo. Establishment of an anchorage area in or near by Honolulu
Harbor is desired for the mooring of idle craft.
    Operations and results during fiscal year. As maintenance,
condition and operation studies and inspections and reports were
accomplished by hired labor at a cost of $12,429.
    Condition at end of fiscal year. The existing project was com-
pleted in August 1945. The controlling depths in March 1953 were
40.1 feet in the entrance channel, 33.5 feet in the harbor basin, 34
feet in the connecting channel, and 34 feet in Kapalama Basin.
   The costs for the existing project to the end of the fiscal year
were as follows:
                                                                 New work         Maintenance           Total
                                                                   costs             costs               costs


Regular funds----------------------------.....                    $3, 167, 563         $594, 784       $3, 762, 347
Public Works funds- ...-----------------------------                  784, 800 ----------------           784,800

     Total-------   --------   ---------   --------   --------     3,952363   1
                                                                                       594, 784    1   4,547,147
 1336          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954
                                        Cost and financial summary

                                                 Fiscal year ending June 30                                 Total to June

                                                                                                          Sing fiscal years
                                 1950           1951        1952        1953                 1954            prior to 1950


New work:
   Appropriated                         --.-                                         - -                        $3, 952,363
   Cost      ----                                                                                                3, 952,363
Maintenance:
   Appropriated .-...             $1,000       -$3,201       $8,000     $12, 660             $16,000                599,190
    Cost-...-------------   --    5,739          3,865       6,310       13,516                  12,429             .594,784




                            21. KAUNAKAKAI                  HARBOR, T. H.
   Location. This harbor is located centrally on the southern
coast of the island of Molokai, about 52 nautical miles southeast
of Honolulu. (See U. S. Coast and Geodetic Survey Chart No.
4121.)
   Existing project. This provides for dredging a harbor basin
about 1,500 feet long, 600 feet wide, and 23 feet deep at mean lower
low water.
   The range of tide between mean lower low water and mean
higher high water is 2 feet and the extreme tidal range for normal
conditions is about 2.5 feet.
   The cost of new work under the project, completed in 1934, was
$103,200. The latest (1954) approved estimate for annual cost of
maintenance is $5,000.
   The existing project was authorized by the Public Works Ad-
ministration, September 6, 1933, and adopted by the River and
Harbor Act of August 30, 1935 (H. Doc. 35, 73d Cong., 1st sess.).
The latest published map is in that document.
   Local cooperation. Fully complied with for new work. The
River and Harbor Act of August 30, 1935, provides that no ex-
pense shall be incurred by the United States in acquiring any lands
or easements required for maintenance of the project.
   Terminal facilities. There is one concrete wharf owned by the
Territory of Hawaii, operated by the Territorial Board of Harbor
Commissioners, and open to shipping on equal terms. The facili-
ties are considered adequate.
   Operations and results during fiscal year. As maintenance,
condition and operation studies and inspections and reports were
made by hired labor at a cost of $2,359.
   Condition at end of fiscal year. The existing project was com-
pleted in January 1934. The controlling depth in October 1953
was 22 feet in the harbor basin.
   The costs of the existing project to the end of the fiscal year
were as follows:

                                                              New work          Maintenance                    Total
                                                                costs              costs                       costs


Regular funds_----      ---------------------------------------                            $55, 381                $55, 381
Public works funds------------------
                    ........                              $103, 200
                                     ,...---------------.....                 ----   _-.----..                     143, 200
     Total.....                                      103, 200
                      ..................................                                     55, 381            :158,581
    RIVERS AND HARBORS-SAN FRANCISCO, CALIF., DISTRICT                                                                1337
                                        Cost and financial summary

                                                  Fiscal year ending June 30                                  Total to June
                                                                                                              30, 1954, includ-
                                                                                                              ing fiscal years
                                 1950           1951            1952             1953                1954       priorto 1950


New work:
   Appropriated_                                   ---------                                ------                    $103, 200
   Cost                                                                   ------------                                 103,200
Maintenance:
   A ppropriated ........         $2,188          - $356                           $2,500            $2,800             55,980
   Cost-_-----                     2,144 ------------------------                   2,342             2,359             55,381


                                 22. KAHULUI HARBOR, T. H.
   Location. This harbor is on the north coast of the island of
Maui, about 90 nautical miles southeast of Honolulu. (See U. S.
Coast and Geodetic Survey Chart No. 4105.)
   Existing project. This provides for the extension of a total
length of 2,850 feet of the privately constructed rubble-mound
breakwater on the east side of the harbor, for a rubble-mound
breakwater on the west side with an approximate length of 2,396
feet and for the dredging of a basin in the lee of the east break-
water to a depth of 35 feet, mean lower low water, and a maxi-
mum width of 1,450 feet. The range of tide between mean lower
low water and mean higher high water is 2.4 feet and the extreme
tidal range under normal conditions is 3.4 feet.
   The cost of new work under the project, completed in 1931, was
$1,778,560. The latest (1954) approved estimate for annual cost
of maintenance is $54,000.
   The existing project was authorized by the following River and
Harbor Acts:

    Acts                            Work authorized                                                  Documents

June 25,1910 Extending the east breakwater and dredging the H. Doe.593, 61st Cong., 2d sess.
                 basin.
July 27,1916   For the west breakwater .................----------------------       H. Doc. 1330, 62d Cong., 3d sess.
Jan. 21,1927   Extension of both breakwaters and enlargement of                      H. Doe. 235, 69th Cong., 1st sess.'
                the dredged basin.

1Contains latest published map.

   Local cooperation. Fully complied with.
   Terminal facilities. There are two wharves at the end of the
harbor, both owned by the Territory of Hawaii. They are oper-
ated by the Territorial Board of Harbor Commissioners, and are
open to shipping on equal terms. Pipelines for fuel oil, distillate,
kerosene, gasoline, molasses, and water are available. Facilities
available for storing and conveying sugar in bulk consist of a
30,000-ton wooden storage building and conveying belts of various
widths. Pier No. 1 is being extended to provide more adequate
berthing for 2 freighters, and upon completion the facilities will
be considered adequate for existing commerce.
   Operations and results during fiscal year. As maintenance,
condition and operation studies and inspections and reports were
made by hired labor at a cost of $6,241.
  Condition at end of fiscal year. The project was completed in
1338           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

December 1931. The controlling depth in May 1953 was 30.6 feet
in the harbor basin.
   The costs of the existing project to the end of the fiscal year
were $1,778,560 for new work and $1,022,974 for maintenance, a
total of $2,801,534.

                                       Cost and financial summary

                                                Fiscal year ending June 30                   Total to June
                                                                                             30, 1954, includ-
                                                                                             ing fiscal years
                                1950          1951         1952        1953       1954         prior to 1950


New work:
   Appropriated -----------.----.----.---------------------- ------- ------------                 $1, 778,560
   Cost-------     -----------------------------------------------------------                     1,778,560
Maintenance:
   Appropriated ......--   -- $5, 360            -$38    $105, 400   -$22, 854     $6, 200          1, 025,661
   Cost..-----------------     3,462------------.....       5,033        81,361     6,241           1,022,974




                              23. KAWAIHAE               HARBOR, T. H.
    Location. This harbor is in Kawaihae Bay, adjacent to the
town of Kawaihae, and is on the northwest coast of the island of
Hawaii, approximately 45 miles northwesterly from Hilo, island
of Hawaii. (See U. S. Coast and Geodetic Survey Chart No. 4166.)
    Existing project. This provides for an entrance channel 400
feet wide and approximately 2,900 feet long to a depth of 40 feet;
a harbor basin 1,250 feet square to a depth of 35 feet; and a pro-
tective breakwater with maximum crest elevation 13 feet above
mean lower low water and approximately 4,400 feet long, of which
3,200 feet would be protected with heavy stone revetment.
    The plane of reference is mean lower low water. The range of
tides between mean lower low water and mean higher high water
is 2.1 feet, and the extreme range under ordinary conditions is 4.5
feet.
    The estimate of cost for new work (1954) is $7,030,000. The
latest (1954) approved estimate for annual cost of maintenance
is $10,000.
    The existing project was authorized by the River and Harbor
Act of May 17, 1950 (H. Doc. 311, 81st Cong., 1st sess.). The lat-
est published map is in that document.
    Local cooperation. The River and Harbor Act of May 17, 1950,
requires that local interests give assurances satisfactory to the
Secretary of the Army that they will (1) furnish without cost to
the United States all lands, easements, rights-of-way and spoil dis-
posal areas necessary for the construction and subsequent mainte-
nance of the project, when and as required, to include specifically
properties landward of the harbor basin and breakwater from the
shoreline to the paved public highway; (2) hold and save the
United States free from damages due to the construction and sub-
sequent maintenance of the project; (3) provide and maintain at
their own expense adequate public terminal and transfer facilities
open to all on equal terms; and (4) accomplish without cost to the
   RIVERS AND HARBORS-SAN FRANCISCO, CALIF., DISTRICT           1339
United States all necessary alterations in water supply, sewerage,
drainage, and other utilities.
   Responsible local interests have expressed their willingness and
ability to cooperate in any harbor development project that may
be recommended by the Federal Government at this location. The
Territory of Hawaii, by authority of its legislature, would assume
through the Territorial Board of Harbor Commissioners full
sponsorship of the project. The Territory has offered (1) to pro-
vide all lands and rights-of-way necessary for the construction of
the project; (2) to construct all shore structures relative and ger-
mane to the improvement of the harbor; and (3) to maintain such
structures at Territorial and local expense. The legislature of the
Territory, by Act 95 session laws 1947, authorized the Territorial
Board of Harbor Commissioners to expend $1,000,000 for harbor
facilities at Kawaihae, upon approval and development of the proj-
ect by the Federal Government. The Kohala Sugar Co. would
abandon its wholly owned subsidiary, the Mahukona Terminals,
Ltd., which represents a substantial investment, and is prepared
to participate jointly with other sugar companies to finance the
installation of bulk sugar handling facilities at Kawaihae.
   By Act No. 136 of the 1953 session of the Territorial legislature,
the Board of Harbor Commissioners was authorized to provide
partial harbor improvements at Kawaihae at a cost of $500,000.
Of that amount, $300,000 will be expended for dredging a channel
and harbor basin, and $200,000 will be for terminal facilities,
lands, and rights-of-way. The dredging plan contemplates a chan-
nel 200 feet wide, 1,800 feet long, and 20 feet deep, and a turning
basin 450 feet square to the same depth. These facilities would be
built so that they could be incorporated in the Federal harbor
and would reduce the cost of the Federal project. Act No. 136
was signed by the Governor of Hawaii on May 28, 1953. Con-
struction of the Territorial project is now in progress.
   Terminal facilities. There is one pier approximately 2,200 feet
northwesterly from the location of the proposed project. It is 60
feet wide and 104 feet long, and provides 60 feet of wharf front-
age and about 1,800 square feet of storage area. An approach to
the pier extends 323 feet offshore and consists of a reinforced con-
crete substructure, 130 feet of timber decking, and 193 feet of re-
inforced concrete slab. There is a light hoist available for han-
dling freight, and a cattle chute for handling livestock. The pier
is owned and administered by the Territorial Board of Harbor
Commissioners and is open to all on equal terms.
   The existing facilities are considered unsuitable for existing
commerce and inadequate to permit year-round trans-Pacific and
interisland shipping, and to meet the increasing shipping needs of
the communities of the western half of the island of Hawaii.
   Operationsand results during fiscal year. None.
   Condition at end of fiscal year. No work has been done under
the existing project.
1340             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                      Cost and financial summary
Other new work data:
    Appropriated for succeeding fiscal year ending June 30, 1955_           $50,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 19555----------------------------------------------                 0,000
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project  --------------------------------          6,980,000


                                   24. HILO HARBOR, T. H.
   Location. This harbor is on the northeast coast of the island of
Hawaii, about 195 nautical miles southeast of Honolulu.         (See
U. S. Coast and Geodetic Survey Chart No. 4103).
   Existing project. This provides for a rubble-mound break-
water 10,170 feet long, for the removal of shoals at the entrance to
Kuhio Bay to a depth of 35 feet, and for dredging an area in Kuhio
Bay 1,400 feet wide, about 2,300 feet long, and 35 feet deep.
   The plane of reference is mean lower low water. The range of
tides between mean lower low water and mean higher high water
is 2.3 feet, and the extreme range under ordinary conditions is
3.2 feet.
   The cost of new work under the project, completed in 1930, was
$3,408,826. The latest (1954) approved estimate of annual cost
of maintenance is $20,000.
   The existing project was authorized by the following River and
Harbor Acts:

    Acts                           Work authorized                                   Documents
                                                                    ---


Mar. 2, 1907     For a rubble-mound breakwater-----------------.... ...      Doc. 407, 59th Cong.,    2dsess.
July 25, 1912    Dredging the entrance to Kuhio Bay without in-           H. Doc. 417, 62d Cong., 2d sess.
                  creasing the original limit of cost.
Mar.   3, 1925   Extension of the breakwater and dredging in the bay.     IH. Doc. 235, 68th Cong., 1st sess.'

  ' Contains latest published maps.

   Local cooperation. Fully complied with.
   Terminal facilities. There are three wharves at the head of
Kuhio Bay, owned by the Territory of Hawaii. They are operated
by the Territorial Board of Harbor Commissioners, and are open
to shipping on equal terms. Pipelines for fuel oil, Diesel oil,
distillate, kerosene, gasoline, molasses, and water are available.
Facilities available for storing and conveying sugar in bulk con-
sist of four 10,000-barrel steel storage tanks and 42-inch convey-
ing belts. The facilities are considered adequate for existing
commerce.
   Operations and results during fiscal year. As maintenance,
condition and operation studies and inspections and reports were
made by hired labor at a cost of $2,258.
   Condition at end of fiscal year. The project was completed in
     RIVERS AND HARBORS-SAN FRANCISCO, CALIF.; DISTRICT                                                                                    1341

July 1930. The controlling depth in May 1953 was 34.4 feet in
the harbor basin.
   The costs of the existing project to the end of the fiscal year
were $3,408,826 for new work and $1,635,945 for maintenance, a
total of $5,044,771.
                                                  Cost and financial summary

                                                              Fiscal year ending June 30                                            Total to June
                                                                                                                                   30, 1954, includ-
                                                                                                               Sing                     fiscal years
                                           1950           1951                 1952                1953                 1954         prior to 1950

New work:
    Appropriated ........                             -----------                                                    --------           $3,3,408,826
                                                                                                                                             408,826
   Cost----------------------------------------------------------
Maintenance:--                                               --                                                 -
    Appropriated               _           $31, 586    -$8,         446        $82, 994          -$5, 240                $6, 200          1, 640, 439
    Cost..............-----------------.    20, 305                 -1              618            80, 116                2, 258          1, 635, 945



                             25.     INACTIVE                 NAVIGATION                           PROJECTS

                                                                                                 Cost to June 30, 1954
                                                                            For last                                                   Estimated
                       Name of project                                     full report                                                  amount
                                                                          see annual                                  Operation       required to
                                                                          report for-      Construction                    and          complete
                                                                                                                     maintenance


1. Lower San Francisco Bay, Calif.l _.........                                1935       1 -......................                       2$450,000
2. Welles Harbor, Midway Island 3__            .-----                         1950              $2,488,056                 $ 2,111
3. Wake Island Harbor ...-----------------------                              1950        -              -                 4 14,493      3,442,900


  1Awaiting local cooperation.
  SExclusive of $260,000 to be contributed by local interests.
  3 Project was 99 percent complete on June 30, 1941. Remaining work will be accomplished by the
Department of the Navy.
  4 For a hydrographic survey completed in August 1948.

                                           26. RUSSIAN RIVER, CALIF.
   Location. The Russian River rises in the Coast Range in north-
western California, flows southerly for a distance of 87 miles, and
then turns westerly to flow for 23 miles to the Pacific Ocean at
Jenner, 60 miles northwest of San Francisco, Calif. (For the
general location see U. S. Geological Survey map for the State of
California.)
   Existing project. The authorized project provides for the con-
struction of the initial stage of the plan of improvement consisting
of Coyote Valley Reservoir at mile 1 on the East Fork of the Rus-
sian River, and channel stabilization works on the lower 97 miles
of the Russian River and on the lower reaches of several tribu-
taries. The dam is an earthfill type, with a total length of 4,600
feet, a crest at elevation 785, mean sea level datum, and a height
above the stream bed of 150 feet. A paved overflow spillway is to
be located adjacent to the right abutment (looking downstream),
having a fixed crest at elevation 768 and a crest length of 410 feet.
Gated outlet works, located through the dam, will provide capacity
1342     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

to empty the flood-control storage in about 4 days. The dam will
create a reservoir having a capacity at spillway crest of 122,000
acre-feet, of which 48,000 acre-feet are reserved for flood control
and the remainder for water conservation and siltation. The dam
will control runoff from 105 square miles of drainage area.
   The estimate of cost for new work (1954) is $16,600,000, ex-
clusive of $5,598,000 to be contributed by local interests. The
latest (1954) approved estimate for annual cost of maintenance
of Coyote Valley Reservoir is $18,900.
   The project was authorized by the Flood Control Act approved
May 17, 1950 (H. Doc. 585, 81st Cong., 2d sess.). The latest
published map is contained in the project document.
   Local cooperation. The improvements are subject to the condi-
tion that prior to starting construction, local interests shall con-
tribute the sum of $5,598,000 in cash in full payment of the con-
servation benefits, and shall (1) Furnish free of cost to the
United States all lands, easements, and rights-of-way necessary
for the construction of the channel stabilization works; (2) make
all necessary road and bridge revisions and utility alterations and
relocations required for the channel stabilization works; (3) ad-
just all claims concerning water arising from the construction
and operation of the improvements; (4) hold and save the United
States free from damages due to the construction works; (5)
maintain the channel stabilization works, after completion, in ac-
cordance with regulations prescribed by the Secretary of the
Army; (6) prevent any encroachment on the stream channel
which would interfere with the proper functioning of the improve-
ments or lessen their beneficial effects; and, (7) enter into an
agreement among themselves as to the method of operation of the
reservoir for conservation subject to flood control priority.
   Sonoma and Mendocino Counties have formed flood control and
water conservation districts as an initial step toward meeting the
requirements of local cooperation. In addition, they have en-
gaged consultants to make independent engineering and financial
appraisals of the authorized project and to serve as a basis for
allocating the required cash contribution between the two counties.
Present plans include a referendum in March 1955 on a bond
issue to cover the cash contribution.
   Operations and results during fiscal year. Engineering and de-
sign for the Coyote Valley Reservoir was continued by hired labor
at a cost of $200,104 for new work.
   Condition at end of fiscal year. No construction has been per-
formed on the project. Engineering and design is approximately
52 percent complete. The cost of the existing project to the end of
the fiscal year was $375,245 for new work.
            FLOOD CONTROL-SAN FRANCISCO, CALIF., DISTRICT                                  1343
                                 Cost and financial summary

                                       Fiscal year ending June 30                  Total to June
                                                                                   30, 1954, includ-
                                                                                   ing fiscal years
                          1950        1951        1952        1953       1954       priorto 1950


New work:
   Appropriated - .-                                 -       $226,000   $170,000           $396, 000
   Cost------------------------------------                   175,142    200,104            375,245


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954        __                       $3,994
    Appropriated for succeeding fiscal year ending June 30, 1955-......                  150,000
    Unobligated balances available for succeeding fiscal year ending June
       30, 1955_---------------               ______________                             153,994
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project_                                       16,054,000


                         27. HANAPEPE RIVER, T. H.
   Location. This river is on the southwest portion of the island
of Kauai, T. H., northwest of the town of Hanapepe.
   Existing project. This provides for construction, along the left
bank of the river, of a 370-foot earth levee, commencing at the
new Kauai Belt Highway Bridge about one-half mile above the
river mouth; thence a 1,720-foot reinforced concrete flood wall
extending to the cliffs at the northeast corner of the town of
Hanapepe.
   The estimate of cost for new work (1954) is $337,000.
   The existing project was authorized by the Flood Control Act
approved December 22, 1944, in accordance with the recommen-
dations of the Chief of Engineers in a report submitted to Congress
by the Secretary of War on March 15, 1944.
   Local cooperation. Local interests are required to (1) Furnish
lands, easements, and rights-of-way necessary for the construction
of the project; (2) bear the expense of all highway alterations, of
removing the existing railroad trestle near the river mouth, and
of replacing this trestle with a satisfactory structure if replace-
ment is required; (3) hold and save the United States free from
damages resulting from construction of the works; and (4) main-
tain and operate all works after completion in accordance with
regulations prescribed by the Secretary of War.
   The railroad trestle was removed in 1948. Bill No. 165, resolu-
tion No. 152, adopted October 3, 1951, by the IBoard of Supervisors,
County of Kauai, providing formal assurance of local cooperation,
was accepted by the district engineer March 10, 1952.
   Operations and results during fiscal year. As new work, engi-
neering and design was continued by hired labor at a cost of $8,859.




      Sig 43-1343-1374
1344           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  Condition at end of fiscal year. No construction has been per-
formed on the project. Engineering and design is approximately
83 percent complete. The cost of the existing project to the end
of the fiscal year was $24,455 for new work.
                                     Cost and financial summary

                                             Fiscal year ending June 30                    Total to June
                                                                                           30, 1954, includ-
                                                                                           ing fiscal years
                              1950          1951       1952I        1953      1954          priorto 1950


New work:
   Appropriated ....----      $20, 000 ------------
                                        _             -$7, 271       $8,300    $8, 600             $29,629
   Cost-_______                10,210       $2,457          63        2,867     8,859               24,455


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_                                        $4,292
    Unobligated balances available for succeeding fiscal year ending June
        30, 1955-          _ __-_       _     __      -_-_-_-                             -_       4,292
      Estimated additional amount needed to be appropriated for completion
        of existing project--                                                         -         307,371


                              28. KAWAINUI SWAMP, T. H.
   Location. This swamp is in the southeasterly portion of the
island of Oahu, in the Kailua District, 13 miles northeasterly of
Honolulu.
   Existing project. This provides for an unlined tidewater flood
channel 9,600 feet long extending from Kailua Bay to the northern
end of Kawainui Swamp, 14 to 15 feet deep, and approximately
160 feet wide except for a narrowed section under the highway
bridge at Kalaheo Avenue.
   The estimate of cost for new work (1954) is $951,000.
   The existing project was authorized by the Flood Control Act
of May 17, 1950 (H. Doc. No. 214, 81st Cong., 1st sess.). The
latest published map is in that document.
   Local cooperation. Local interests are required to: (1) Provide
without cost to the United States all lands, easements, rights-of-
way, and spoil disposal areas necessary for the construction and
subsequent maintenance of the project; (2) construct all highway
and street bridges, alterations, and other related works made
necessary by the construction of the project; (3) hold and save the
United States free from any damages resulting from the con-
struction and maintenance of the works; (4) maintain and operate
all works after completion of the project in accordance with regu-
lations prescribed by the Secretary of the Army.
   Local interests have indicated their willingness to furnish the
required items of cooperation and have initiated measures to pro-
vide them. At the 1951 session of the Territorial Legislature, the
sum of $325,000 was authorized for flood control purposes at
Kailua. The Department of Public Works has constructed a con-
crete bridge at Kalaheo Avenue at a cost of $90,000. The Depart-
ment of Public Works has acquired rights-of-way consisting of a
uniform width of 200 feet from the swamp to Kailua Bay. In ad-
                    FLOOD CONTROL-SAN FRANCISCO, CALIF., DISTRICT                                                             1345

dition to the required cooperation, local interests have constructed
a pilot channel along the alinement of the proposed Federal project
for emergency flood relief at a cost of $158,936.
   Operations and results during fiscal year. As new work, engi-
neering and design was continued by hired labor at a cost of $6,985.
   Condition at end of fiscal year. No construction has been per-
formed on the project. Engineering and design is approximately
52 percent complete.
   The cost of the existing project to the end of the fiscal year was
$27,543.
                                               Cost and financial summary

                                                           Fiscal year ending June 30                                  Total to June
                                                                                                                      30, 1954, includ-
                                                                                                                      ing fiscal years
                                        1950           1951           1952              1953                1954        priorto 1950


New work:
    Appropriated----------------------------                          $28, 000          $ 3,000             $8, 700            $39, 700
    Cost-       -         -
                        ...-.....-.........           .-    --          5,213             15,345             6,985              27,543

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954__--      -      $12,041
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955             ----------------------------------------------  12,041
    Estimated additional amount needed to be appropriated for completion
      of existing project_      ----------------------------         ---  911,300


                     29. INACTIVE                     FLOOD 'CONTROL PROJECTS

                                                                                       Cost to June 30, 1954
                                                                   For last                                              Estimated
                    Name of project                              full report                                              amount
                            projectof
                           Name                                  see annual                     Operation               required to
                                                                 report for-      Construction     and                   complete
                                                                                               maintenance



1. Eel River, Calif.1       ___________________________              1938    ----------------------------                    $865,800
2. Napa River above
                  - - -(Conn         - - - Reservoir)
                                - - Creek   - - -     ........                                                                 100,000
    Suscol, Calif. .................
3. Pajaro River, Calif.'_                   -     -                   1950
                                                             -__________________        $748, 283 --.-----                     39, 717
4. Salinas River, Calif_-__         -      -__ --             -       1952
                                                                    -__________         4 89,925                            8,000,075


1 Awaiting local cooperation.
2 Authorized by the Flood Control Act approved December 22, 1944, in accordance with H. Doc. 626, 78th
Cong., 2d sess. Local interests subsequently constructed a reservoir for domestic water supply at the same
site as that proposed by the United States for flood control. Work now contemplated by Federal Govern-
ment consists of channel clearing at a cost of $100,000, which is awaiting local cooperation.
   a Levees on Pajaro River and Corralitos Creek completed. Local interests are not in favor of constructing
the authorized Carnadero Creek levee at the present time.
   4 For engineering and design, which was approximately 32 percent complete on June 30, 1952.




                                 30. GENERAL INVESTIGATIONS
  Examinations and surveys. During the fiscal year, hired labor
costs of $42,932 were incurred in the preparation of preliminary
examinations, surveys, reviews, special studies, and cooperative
studies authorized by Congress for navigation, flood control, and
beach erosion. The expenditures were $33,192 from regular
funds and $9,818 from contributed funds, a total of $43,010.
1346             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  The balance unexpended June 30, 1954, $19,207, plus an antici-
pated allotment of $85,000 for fiscal year 1955, a total of $104,207,
will be applied as follows:
      Accounts payable June 30, 1954 ...                    .
                                                          ~$..           .....       -.                 $728
      Examinations, surveys, reviews, special studies, and cooperative studies
        for navigation, flood control, and beach erosion------...-..-........------------          103, 479
           Total.............-----------------------------------------------                       104, 207
  Collection and study of basic data. During the fiscal year, flood
investigations, flood emergency studies, and collection of rain gage
data was accomplished by hired labor at a cost of $5,363. The
expenditures were $5,363 from regular funds.
  The balance unexpended June 30, 1954, $256, plus accounts re-
ceivable of $4 and an anticipated allotment of $11,600, a total of
$11,860, will be applied to the collection and study of basic data
during fiscal year 1955.
                         31. INSPECTION OF COMPLETED PROJECTS
  Section 3 of the Flood Control Act approved June 22, 1936, as
amended and supplemented, included the requirement that local
interests maintain and operate flood control works after com-
pletion in accordance with regulations prescribed by the Secretary
of War.
  During the fiscal year ending June 30, 1954, completed flood-
control projects transferred to local interests for operation and
maintenance were inspected by hired labor at a cost of $815.
                                            Cost and financial summary

                                                  Fiscal year ending June 30                  Total to June
                                                                                             30, 1954, includ-
                                                                                             ing fiscal years
                                     1950        1951       1952         1953       1954      priorto 1950


Maintenance:
   Appropriated _----- ....          -._ --        $750    --             $1, 800     $900             $3, 450
    Cost     -.............---   .                  750         -   -      1,684       815              3,248



   32. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
  Snagging and clearing of navigable streams and tributariesin
the interests of flood control (Section 13 of the 1946 Flood Con-
trol Act).
   During the fiscal year ending June 30, 1954, as new work, snag-
ging and clearing of the channels of Alameda Creek tributaries
in Livermore Valley, Calif., was completed by contract and an
operation and maintenance manual was prepared by hired labor,
at a cost of $15,027; an operation and maintenance manual cover-
ing work performed on the Salinas River, Calif., during fiscal year
1953 was completed by hired labor at a cost of $503; and en-
gineering and design for snagging and clearing lao Stream, T. H.,
by contract, during fiscal year 1955 was completed by hired labor
at a cost of $2,522. The total new work cost during the fiscal
year was $18,052.
                  FLOOD CONTROL-SAN FRANCISCO, CALIF., DISTRICT                                                       1347
                                            Cost and financial summary

                                                      Fiscal year ending June 30                              Total to June
                                                                                                             30, 1954, includ-
                                                                                                             ing fiscal years
                                     1950           1951             1952       1953             1954         prior to 1950

New work:
   Appropriated -..--    -           $39, 000- ...                   $50, 000   $24,930          $47,186             $297, 366
   Cost ....------------              25,711       $35,420            12,779     59,485           18,052             *249,888


  *Total to June 30, 1954, includes $700 cumulative error in total cost of "dropped" accounts which were
picked up on general ledgers as of July 1, 1953. Total now reflects cumulative amount shown on Form
3099 dated July 1, 1953, plus costs for fiscal year 1954.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954------------_    $47,478
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955 ---------------------------------------------------- 47,478
   Emergency bank protection (Section 14 of the 1946 Flood Con-
trol Act).
   During fiscal year 1954, $5 was expended in payment of costs
incurred in connection with revetment, during fiscal year 1953,
of the left bank of Redwood Creek, Humboldt County, near United
States Highway 101 Bridge at Orick, Calif., which costs were not
recorded in fiscal year 1953 finance accounts.
                                            Cost and financial summary

                                                      Fiscal year ending June 30                              Total to June
                                                                                                             30, 1954, includ-
                                                                                                             ing fiscal years
                                     1950           1951             1952       1953             1954         priorto 1950


New work:
   Appropriated ..... -------------------------------------                     $23, 738 I ----------                 $23, 738
   Cost----------           ---.-------- -------------------------               23,733                 $5             23,738



   Small flood control projects not specifically authorized by Con-
gress (Sec. 212 of the 1950 Flood Control Act).
   During the fiscal year, a report determining the economic
feasibility of constructing a project at Mad River, Blue Lake,
Calif., was completed, and engineering and design therefor was
initiated, all by hired labor, at a cost of $2,569.
                                            Cost and financial summary

                                                     Fiscal year ending June 30                               Total to June
                                                                                                             30, 1954, includ-
                                                                                                             ing fiscal years
                                    1950           1951              1952       1953             1954         priorto 1950

New work:
                   -
    Appropriated --..               $98,600 -------              -$24,852       $4,000            $6, 000             $83, 748
    Cost-----------------              5,058       $67,406              792       3,003            2,569               78,828

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-------- -----
                                                                   _          $4,416
    Unobligated balances available for succeeding fiscal year ending June 30,
          1955---                                                                                            --       4,416
1348           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  Flood control emergencies--Repairand flood fighting and rescue
work (Section 210 of the 1950 Flood Control Act and supplemental
authorizations).
   During the fiscal year, emergency flood fighting operations
were conducted in connection with flooding on northern California
coastal streams, and a maintenance manual was prepared cover-
ing previously completed emergency levee repairs on Alameda
Creek, Calif., all by hired labor, at a cost of $3,150.
                                   Cost and financial summary

                                              Fiscal year ending June 30                  Total to June
                                                                                         30, 1954, includ-
                                                                                         ing fiscal years
                            1950            1951         1952        1953      1954        priorto 1950

Maintenance:
   Appropriated--..------    ....-----------. $20, 000   $62, 641   -$2, 935   $2, 506            $82, 212
   Cost_---- ______-
                  .     _                      17,641     55,360       6,061    3,150              82,212
      IMPROVEMENT OF RIVERS AND HARBORS IN THE
             SACRAMENTO, CALIF., DISTRICT

  This district comprises the basins of Suisun Bay and the San
Joaquin and Sacramento Rivers, in California, and Goose Lake
in Oregon; the basins of the Great Salt Lake and Sevier Lake, in
Utah; and the intervening portion of the Great Basin in northern
Nevada and northern California.
                                              IMPROVEMENTS

               Rivers and Harbors                                    Flood Control-Continued
                                                   Page                                                         Page
                                                          11. Lower San Joaquin River and
1. Sacramento River, Calif _.....-                1349          tributaries, including Tuo-
2. Suisun Channel, Calif .......     ......       1356         lumne and Stanislaus Rivers,
3. Suisun Bay Channel, Calif ..-...               1358                          ......................--....
                                                                Calif ..........-----                            1383
4. Old River, Calif ............                  1360   12. Merced County Stream Group,
5. San Joaquin River, Calif .........             1362         Calif .......................................... 1388
6. Stockton and Mormon Chan-                             13. Big Dry Creek Reservoir and
      nels, Calif ..............................   1368         Diversion, Calif ...................             1392
7. Inactive navigation projects....               1369   14. Kings River and Tulare Lake,
                                                                including Pine Flat Reser-
                   Flood Control                                voir, Calif ...........................          1394
                                                          15. Isabella Reservoir, Kern River,
8. Sacramento River and tribu-                                 Calif _ ___                                    - 1397
      taries, California, from Col-                       16. Inactive flood control projects_ 1400
      linsville to Shasta Dam-..........           1370   17. General investigations .......                     1400
9. Folsom Reservoir, Sacramento                          18. Inspection of completed proj-
      River Basin, Calif ..................        1374         ects_ ___                                        1402
10. Calaveras River and Littlejohn                        19. Flood control work under
      Creek and tributaries, includ-                            special authorization. -.                        1402
      ing Hogan and Farmington                            20. Scheduling of flood control
      Reservoirs, Calif....................        1377         operations __                                    1404

                              1. SACRAMENTO RIVER, CALIF.

   Location. Sacramento River rises in the Trinity Mountains in
north-central California, flows in a general southerly direction
about 374 miles and empties into Suisun Bay, an arm of San Fran-
cisco Bay, at Collinsville, Calif. (See U. S. Geological Survey
topographic map of the Sacramento Valley, Calif.
   Previous projects. The original project was adopted by the
River and Harbor Act of March 3, 1875, and provided for improve-
ment of the low-water channels in the Sacramento River and for
snagging and construction of temporary wing dams in the Feather
River, a tributary entering the Sacramento River about 16 miles
above the city of Sacramento. The project was subsequently modi-
fied by the River and Harbor Acts adopted August 2, 1882, Decem-
ber 21, 1889, July 13, 1892, and August 18, 1894. These modifica-
tions provided for dredging in the Sacramento and Feather Rivers
and for restraining barriers (for mining debris) in the Yuba,
Bear, and American Rivers, tributaries of the Sacramento River,
as an aid to navigation; for improving navigation by repairing
                                                                                                   1349
1350     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

damages caused by floods; for a snag boat above Sacramento;
removal of obstructions in the lower Sacramento River; further
treatment of the Yuba River near and above the city of Marysville
and improvement of the navigable channel of the Feather River;
and for treatment of the Bear River and construction of a cutoff
on the Feather River to avoid Shanghai Bend. For further details
see page 1985, Annual Report for 1915, and page 1708, Annual
Report for 1938.
   Existing project. The project provides for construction of the
Sacramento River Deep Water Ship Channel from deep water in
Suisun Bay to Washington Lake, 11/2 miles west of the Sacra-
mento River at the city of Sacramento, a distance of 43 miles, con-
struction of a harbor and turning basin at Washington Lake, and
a connecting canal with navigation lock from the harbor to the
Sacramento River. The project also provides for a channel ten
feet deep at mean lower low water, 150 to 200 feet bottom width,
from Suisun Bay to Sacramento, Calif., a distance of 60 miles; a
depth of 6 feet at low water between Sacramento and Colusa, a
distance of 85 miles; a depth of 5 feet at low water between Colusa
and Chico Landing, a distance of 50 miles; and such depths as
practicable between Chico Landing and Red Bluff, a distance of
52 miles.
   The deep water channel will be formed by widening and deep-
ening existing channels for the first 18 miles above Suisun Bay to
6 miles above Rio Vista and excavation of a new channel for the
remaining 25 miles to Washington Lake to a depth of 30 feet at
mean lower low water with a bottom width of 200 to 300 feet,
including related confining embankments and such works as may
be necessary to compensate for or to alleviate any possible detri-
mental effects on salinity of Delta tidal channels which might
result from the ship channel. The triangular harbor and turning
basin will be formed by deepening and widening Washington Lake
to a depth of 30 feet at mean lower low water, 2,400 feet by 2,000
feet by 3,400 feet, with provision for future enlargement. The
construction of the 11/2-mile long canal 13 feet deep and 120 feet
wide between the harbor and the Sacramento River, together with
a navigation lock 86 feet wide by 600 feet long, will provide for the
transfer of barges between the two different water surface eleva-
tions. A single leaf combination highway and railroad bascule
bridge will cross the canal at the harbor end of the navigation
lock. Local interests will construct, operate and maintain an ade-
quate public terminal with necessary utilities and rail and highway
connections at the harbor.
   Above Sacramento the results are to be obtained by removal of
snags and concentration of the channel by dredging and wing
dams, and by stream-flow regulation by the Shasta Reservoir.
The 10-foot channel below Sacramento was completed in 1931 and
the 6-foot channel between Sacramento and Colusa was completed
in 1946; these channels are to be maintained for local navigation.
             RIVERS AND HARBORS-SACRAMENTO,                                           CALIF., DISTRICT                 1351
  The following table shows the tidal and flood conditions pre-
vailing:
                                                                                            Range in feet
                                                       Miles from
                       Place                            mouth of
                                                         river
                                                                          Mean          Extreme           Ordinary    Extreme
                                                                          tidal '        tidal I           flood       flood


Collinsville--..---_                      .........--------------------------           5. 8       7. 0          8          10
Sacramento__  ------------------------------                                59        2 2. 0       3. 0         20          28
Verona (mouth of Feather River) .....                                       80  -----------      Trace          22          30
        ---------------------------------
Colusa.....                     .......                                   144                                   26          32
Chico Landing---------------------------                                  193 -------------------------         20          25
Red Bluff ..------------------------------                                246 ....------
                                                                                       _--------                24          30


  1 Mean lower low water to mean higher high water.
  2 Tide at low water season only.


   The latest approved estimate of Federal cost for new work
 (1954) is $35,300,000 (exclusive of $281,000 Federal cost (Coast
Guard) for navigation aides) for the 30-foot deep water ship
channel and 13-foot deep connecting canal, and $906,000 for
shallow-draft river channels, exclusive of amounts expended on
previous projects. The estimated (1954) cost to local interests for
new work is $2,870,000 for lands, easements, and rights-of-way,
spoil disposal areas for the initial work, and necessary utility
changes, exclusive of costs for port facilities. The latest (1953)
approved estimate for annual Federal cost of maintenance is $205,-
000 for the deep-water channel and 13-foot connecting canal, and
$250,000 for shallow-draft channels.
   The existing project was authorized by the following River and
Harbor Acts:
      Acts                               Work authorized                                                  Documents
Mar.    3,1899     A depth of 7 feet below Sacramento__________________                 H. Does. 186, 55th Cong., 2d sess.
                                                                                          and 48, 55th Cong., 3d sess.
                                                                                          (Annual Report, 1898, p. 2944,
                                                                                          and 1899, p. 3171.)           1
July 25, 1912 For work above Sacramento_____________________ ___                        H. Doc. 76, 62d Cong., 1st sess.
Jan. 21, 1927 The 10-foot channel up to Sacramento.___.__.......                        H. Doc. 123, 69th Cong., 1st sess.
Aug. 30, 1935 A depth of 6 feet between Sacramento and Colusa and                       Rivers and Harbors Committee,
                 5 feet between Colusa and Chico Landing, at a                            Doc. 35, 73d Cong., 2d sess.
                cost of $390,000 provided the flow of the river is
                increased to the minimum flow of $5,000 cubic feet
                per second after Shasta Reservoir is built.
    Do....... Authority for a special direct participation of the       Rivers and Harbors Committee
                Federal Government of $12,000,000 in the cost of          Doc. 35, 73d Cong., 2d sess.
                Shasta Reservoir.
Aug. 26, 1937 Transfer of authority for expenditure of the above
                $12,000,000 from the Secretary of War to the Secre-
                tary of the Interior.
July 24, 1946 Modification of the existing navigation project for       S. Doc. 142, 79th Cong., 2d sess.
                Sacramento River, Calif., to provide for construc-
                tion of a ship channel 30 feet deep and 200 to 300 feet
                wide from deep water in Suisun Bay to Washington
                Lake, including such works as may be necessary to
                compensate for or to alleviate any detrimental salin-
               ity conditions resulting from the ship channel; a
               triangular basin of equal depth, 2,400 feet by 2,000
               feet by 3,400 feet at Washington Lake; and connect-
               ing channel 13 feet deep and 120 feet wide, with lock
               and draw bridge, thence to Sacramento River.

  1 This document contains latest published map of the section above Sacramento. For map of the sec-
tion below Sacramento, see H. Doc. 1123, 60th Cong., 2d sess. and S. Doc. 142, 79th Cong., 2d sess.
1352     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Recommended modification of project. In House Document No.
1893, 64th Congress, 2d session, it was recommended that Chico
Landing, about 52 miles downstream from Red Bluff, be made the
head of the improvement.
    Local cooperation. The improvement for the deep-water chan-
nel is subject to the condition that responsible local interests give
assurances satisfactory to the Secretary of the Army that they
will-
    (1) Furnish without cost to the United States all lands, ease-
ments, rights-of-way, and spoil disposal areas for the initial work
and subsequent maintenance when and as required and make all
necessary utility changes necessary for the construction of the
project;
    (2) Construct, operate, and maintain at the Washington Lake
basin an adequate public terminal with necessary utilities and rail
and highway connections open to all on equal terms; and
    (3) Hold and save the United States free from any damages
which may arise from construction, operation, and maintenance
of the improvement.
    The Sacramento-Yolo Port District was formed under the laws
of the State of California in April 1947 for the purposes of carry-
ing out the required local cooperation. A total bond issue of
$3,750,000 was authorized by the voters in November 1947, and
bonds in the amount of $1,750,000 have been sold to date. The Cali-
fornia State Legislature appropriated $750,000 in June 1947 to
assist in the acquisition of rights-of-way. The required assurances
have been furnished and were approved by the Secretary of the
Army on February 3, 1948. Local interests have furnished all
lands, rights-of-way, and easements required for project construc-
tion purposes to date, and in addition have completed construction
of a 500,000-bushel grain elevator together with necessary rail-
road, highway, and appurtenant facilities. A master plan covering
development of terminal facilities has been prepared for the future
development of the port. The current (1954) estimate of cost to
local interests for terminal facilities is $5,000,000.
    The sum of $500,000 was advanced to the United States in June
1949 to accelerate construction, of which $300,000 has been re-
turned to the port authority.
    No local cooperation is required on the shallow-draft feature
of the project.
    Terminal facilities. All of the piers, wharves, and docks at the
port of Sacramento are open pile structures with timber decks,
some of which are designed to meet the extreme high waters at
flood stages. Eleven facilities are located along the east bank, or
Sacramento side, of the river, and 10 are on the west bank at
Broderick, West Sacramento, and points below. Of the 21 pier,
wharf, and dock facilities at the port, 9 are used for receipt of
petroleum products, with 955 linear feet of berthing space; 2 are
general cargo wharves, with 592 linear feet berthing space and
40,000 square feet of transit shed storage area; 2 are used for the
receipt and shipment of sacked rice with 150 linear feet of berth-
ing space; and 1 is receiving point for Diesel oil used in the gas and
electric power plant with 130 linear feet of berthing space. Four
      RIVERS AND HARBORS-SACRAMENTO, CALIF., DISTRICT           1353
facilities, providing 1,620 linear feet of berthing space and com-
prised mainly of floats, are used for mooring and servicing recrea-
tional craft; the three remaining wharves provide 1,292 linear
feet of berthing space but are not operated from the waterside,
however, the 39,885 square feet of transit sheds are occupied for
storage purposes. These facilities provide a total of 4,739 linear
feet of berthing space, with 79,885 square feet of transit sheds, of
which 40,000 square feet are available for receipt and shipment of
general cargo. All the preceding is for shallow-draft navigation.
All the main wharves at Sacramento have rail connections. Mu-
nicipal belt railroad tracks serve the shedded wharves from the
rear.
    Ten public warehouses, located within a radius of 31/2 miles
from the waterfront, provide 305,000 square feet of space for dry
cargo and approximately 3,074,000 cubic feet of space for the cold
storage of perishable foods. The amount of storage space at
Sacramento varies according to the season of the year owing to
the great amounts of rice, fruits, vegetables, and other commodi-
ties that are produced in the Sacramento Valley.
    Thirteen of the waterfront facilities are served by one or more
of the four carriers operating in the port area. Two of the carriers
are trunk line railroads and two are interurban electric lines
operated for freight service; all traverse the rich agricultural
areas and provide connections with other transcontinental and
local carriers. All waterborne movements to and from the port
are transported by shallow-draft river steamers, tank barges, and
freight barges, and will continue to be handled thus until such
time as the authorized deep-water ship channel is completed.
    Two grain elevators are located at the port. One, handling rice
exclusively, is located on the river at West Sacramento, and is
served by two wharves. The elevator, a warehouse, and storage
bins have a combined capacity of approximately one million 100-
pound sacks of rice. The other elevator, the port district grain
elevator, has a capacity of 500,000 bushels of barley, wheat, or
other grains in its 12 concrete silos. It is located near Washing-
ton Lake, on the site of the new port development to be built upon
completion of the deep water channel. The port district elevator
is served by rail and highway facilities. Construction of a new
rice plant in the port district area is currently under way by the
Farmers Rice Growers Cooperative. The first units of the plant
will be utilized for rice storage and drying facilities; these facili-
ties were completed in time for the 1953-54 crop season. The
plant will be enlarged with the addition of a mill next year. The
new plant will have a capacity of more than 400,000 one hundred-
pound bags of rice and there will be 40 storage bins.
   Between Sacramento and Chico Landing there are 47 ware-
houses and numerous small landings. Several oil companies have
recently made major capital investments for the storage of petro-
leum products in the vicinity of Colusa. Freight is also handled
on the bank. On the river channels, between Sacramento and the
mouth of the river, there are, in addition to 1,440 linear feet of
wharf with warehouse facilities at Rio Vista, 19 large wharves,
about 38 large warehouses, and many small warehouses and land-
1354           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

ings all owned and operated by private interests. The facilities
below Sacramento, except at Rio Vista, are for shallow-draft navi-
gation. They are considered adequate for existing commerce.
   The total tonnage through the port in 1952 was 1,889,466 tons.
   Operations and results during fiscal year. New work: There
were no new work operations on the shallow-draft portion of the
project. New work activities for the deep-draft channel to Sacra-
mento consisted of office engineering and design studies. Total
costs during the fiscal year for new work on the deep-draft channel
were $17,702, from funds advanced by the Sacramento-Yolo Port
District. Maintenance: Preliminary surveys, preparation of plans
and specifications, condition surveys of the channel, miscellaneous
minor spoil area maintenance and miscellaneous inspections and
reports were accomplished by hired labor during the fiscal year.
In addition, maintenance operations were performed as follows:
   a. Above Sacramento (shallow-draft).        Dredging of critical
shoals in Sacramento River at various locations from Sacramento
to Colusa, by hired labor and rented clamshell dredge, resulted in
the removal of 105,490 cubic yards of material from the channel.
Snagging and clearing of the channel at scattered locations be-
tween Sacramento and Colusa and repairs to wing dams at scat-
tered locations between Sacramento and Verona were accomplished
by hired labor and rented equipment.
   b. At and below Sacramento (shallow-draft). Construction of
a levee to provide spoil area near Sacramento, by contract, resulted
in placement of 201,865 cubic yards embankment. Hired labor
and rented clamshell dredge were utilized to remove 11,389 cubic
yards of material in Sacramento Harbor at Sacramento. Dredg-
ing of shoals in Steamboat Slough, between the mouth of Steam-
boat Slough and Walker Landing, by hired labor and rented clam-
shell dredge, resulted in the removal of 59,950 cubic yards of
material from the channel. A contract suction dredge removed
333,670 cubic yards of material from the Sacramento River at
Sacramento, from the M Street Bridge to Y Street Bend, and from
the I Street Bridge to mouth of American River. Dredging of
shoals in the Sacramento River, from Y Street to Bryte Bend, by
contract suction dredge, resulted in the removal of 20,000 cubic
yards of material.
   Total costs for maintenance during the fiscal year for both sec-
tions of shallow-draft channels were $326,839.
   Total costs for all work during the fiscal year were as follows:

                          Funds                                   New work             Maintenance     Total

United States funds.................................... ................               $326, 839         $326, 839
Advanced funds (by Sacramento-Yolo Port District)...                   $17, 702 ----------------           17, 702

      Total, all funds..................       .........---------------------------------
                                                                            17, 702         326, 839      344, 641



  Conditionat end of fiscal year. Construction of the 7-foot shal-
low-draft below Sacramento was initiated in September 1899 and
completed in 1904. The modified 10-foot shallow-draft up to
Sacramento was initiated in fiscal year 1928 and completed in
1931. The shallow-draft channel above Sacramento was initiated
           RIVERS AND HARBORS-SACRAMENTO,                                                                    CALIF., DISTRICT                            1355
in April 1946. New work on the shallow-draft channel is about 66
percent complete. The work remaining to complete the shallow-
draft portion of the project is the provision of a 5-foot depth be-
tween Colusa and Chico Landing (50 miles), subject results to be
obtained by removal of snags, construction of wing dams, concen-
tration of the channel by temporary works, and streamflow regu-
lation of 5,000 second-feet by operation of Shasta Reservoir.
   Construction of the 30-foot deep water ship channel, under the
modification authorized by the River and Harbor Act approved
July 24, 1946, was initiated in July 1949 and is about 7 percent
complete. Construction of road, railroad, and levee embankments
in the harbor area was completed by contracts in October 1949 and
February 1950. Excavation of the ship channel together with
necessary levee reconstruction, mile 14.1 to mile 17.8, by contract,
was completed in October 1951. Further new construction has
been suspended since that date in accordance with Presidential
Directive dated July 21, 1950. Preparation of plans and specifi-
cations for the project are about 25 percent complete. Work re-
maining to complete the deep-draft portion of the project is
construction of the lock with gates and operating equipment, barge
canal, bascule bridge, bank protection and levees, channel and
turning basin, and pumping plants and drainage facilities.
   The entire project as modified is about 8 percent complete.
   The controlling low water season depths were as follows: From
the mouth of the river to Sacramento, 8 feet; thence to Colusa, 5
feet; thence to Chico Landing, 2 feet; and thence to Red Bluff, head
of navigation, 1.5 feet. The channel is navigable during the entire
year; however, there is no regular navigation above Sidds Land-
ing, 178 miles above the mouth of the river.
   Annual maintenance dredging is required in both sections of the
shallow-draft channel to remove accumulated shoals caused by
settlement of flood borne sand and silt to provide the project
depths in satisfactory condition to accommodate navigation
requirements. Maintenance was performed in 1952, consisting of
bank protection along Ryer Island and Egbert Tract, along the
deep-draft channel to repair serious erosion caused by tidal action
and wave wash due to construction of the ship channel; however,
the erosion is continuing and extension of the bank protection
work on the Egbert Tract levee will ultimately be necessary.
   The total costs for the existing project to June 30, 1954, were
as follows:
                                 Funds                                                             New work           Maintenance                 Total

United States funds:
   Shallow-draft ----..........-----.....--------....-----------------                                $585, 436            $6, 138, 810               $6, 724, 246
    30-foot channel        .............           --........ __...........                          2, 308, 758               124, 496                2, 433, 254

               1 States funds---...........
     Total United                                                   __.           __..               2, 894, 194             6, 263, 306               9, 157, 500
Advanced funds:
   30-foot channel---     --......................----                        -                     - 133, 054 --..-..---.                 ---.   -       133, 054
Contributed funds (nonproject): 2
    30-foot channel-----                                                                .
                                                             ___..............................._       172, 109 ................                          172,109
      Total, all funds                     __---................................                     3, 199, 357            6, 263, 306                9, 462, 663

  SFunds advanced to the United States by the Sacramento-Yolo Port District.
  2 Miscellaneous construction (nonproject) accomplished for the Sacramento-Yolo Port District at its
expense in connection with excavation of the ship channel and necessary levee reconstruction cost.
1356            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                        Cost and financial summary
                                         UNITED STATES FUNDS


                                                     Fiscal year ending June 30                       Total to June
                                                                                                     30, 1954,1 includ-
                                                                                                      ing fiscal years
                                1950               1951       1952            1953        1954         priorto 19541


New work:
   Appropriated-_ _---- $1, 700,000        $   263,000                        $ 8,819----                2 3$3, 079,392
   Cost--                   671,280         1, 510,456        $17,760          10,000 ------------            3 3, 079,392
Maintenance:
      Appropriated       .      183, 000           172,079    330, 784        286, 972    467, 200            47,042, 708
      Cost-_
           --                   205,534            137,115    188,684         380,993     326, 839            5 6,817,026


  1 Includes $185,198 fornew work and $553,720 for maintenance for previous projects.
  2 Includes $585,436 for existing shallow-draft project and $2,308,758 for deep-draft project; these amounts
are exclusive of  funds  advanced by the Sacramento-Yolo Port District for the deep-draft channel, which
are listed on a separate summary.
  3 In addition, $172,109 was expended from contributed funds for miscellaneous construction and engineer-
ing and design services (non-project) accomplished at the expense of the Sacramento-Yolo Port District in
connection with acquisition of rights-of-way and utility alterations.
  4 Includes $6,364,492 for existing shallow-draft project and $124,496 for deep-draft project.
  5 Includes $6,138,810 for existing shallow-draft project and $124,496 for deep-draft project.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project____                                __         __        $33,311,806

                                        Cost and financial summary
                                               ADVANCE FUNDS


                                                     Fiscal year ending June 30                       Total to June
                                                                                                     30, 1954, includ-
                                                                                                     ing fiscal years
                                 1950              1951        1952            1953        1954        priorto 1954

New work:
   Appropriated-.....           $400,000       1       000
                                                   $200,                 --                -$200,                   000
      Cost--                                                  $112,305          $3,047     $17,702               133,054

  1 Refund to advanced funds.
  2   To be refunded to Sacramento-Yolo Port District from future project appropriations.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954__------------                                       $66,728
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955_______                     ___                                                                   66,728
    Estimated additional amount needed to be appropriated for comple-
          tion of existing project_                       _                                 ._            2   200,000

                               2. SUISUN              CHANNEL, CALIF.
  Location. Suisun Channel is the project channel in Suisun
Slough, a tidal inlet with its mouth on the northwest side of Suisun
Bay, about 7 miles northeast of Benicia and 36 miles northeast of
San Francisco. The head of navigation is at the town of Suisun,
about 13 miles north of the mouth. (See U. S. Coast and Geodetic
Survey Chart No. 5534.)
  Existing project. This provides for dredging a channel 8 feet
deep at mean lower low water from Suisun Bay to and in the basin
at the town of Suisun, about 13 miles in length, straightened by
four cutoffs in the upper portion; channel widths to be 200 feet in
the bar channel, 100 feet in the cutoffs, and a minimum of 125 feet
in the remaining parts of the project channel; widening four bends
located 5, 512, 7 L, and 1212 miles below Suisun; the removal of
ledge rock from the channel at a location about 312 miles below Sui-
           RIVERS AND HARBORS-SACRAMENTO, CALIF., DISTRICT                                             1357
sun; and a 1,400 by 150-foot harbor at Suisun, with an extension
for a turning basin 275 feet wide and 600 feet long. The range be-
tween mean lower low water and mean higher high water is about
5 feet during the low water season, with an extreme range of 10
feet.
  The total Federal cost of new work for the project, completed in
1947, was $217,677, and the latest (1953) approved estimate for
annual (Federal) cost of maintenance is $10,000.
  The existing project was authorized by the following River and
Harbor Acts:

    Acts                           Work authorized                                      Documents
June 25, 1910   To secure a channel up to Suisun, 6 feet deep at low         H. Doc. 1110, 60th Cong., 2d sess.
                 water, by dredging and making a cutoff just below
                 the town.
Mar. 4,1913     Pursuant to this act the project was modified by the
                  Assistant Secretary of War to provide for dredging a
                  channel 125 feet wide on the bottom and 6 feet deep,
                  mean lower low water, up to and including a harbor
                  6 feet deep, 150 feet wide, and 1,400 feet long in front
                  of the town of Suisun, and the removal of a rock
                  about 3% miles below the head of navigation.
Aug. 26,1937    Depth of 8 feet with a width of 200 feet in the bar chan-    Rivers and Harbors Committee
                 nel and 100 feet in cutoffs; widening 4 bends below           Doc. 97, 74th Cong., 2d sess.
                  Suisun; removal of ledge rock and extension of the          (Contains latest published map.)
                  harbor at Suisun to provide a turning basin.



   Local cooperation. Local interests are required to furnish free
of cost to the United States all necessary rights-of-way and suit-
able spoil disposal areas for new work and subsequent maintenance,
undertake any necessary reconstruction of the powerline crossing
over the proposed cutoff near Suisun, and provide at Suisun ade-
quate public terminal facilities subject to the approval of the Chief
of Engineers. These requirements have been fulfilled except for
the public terminals, which will be completed when materials are
available at reasonable cost.
   Terminal facilities. There are three wharves in the city of
Suisun, with a total of 600 feet of berthing space. There is also
warehouse space of 33,500 square feet, and an oil storage terminal.
These are all privately owned and operated, and will be increased
in compliance with the provisions of local cooperation, as land has
been purchased, financing arranged, and plans have been prepared
for construction when materials are available at reasonable cost.
Certain facilities are in use for military purposes.
   Operations and results during fiscal year. Maintenance: Oper-
ations during the year consisted of preliminary surveys, condition
surveys of the channel, and miscellaneous inspections and reports,
all of which were accomplished by hired labor. Total costs during
the fiscal year were $1,223 for maintenance.
   Condition at end of fiscal year. The construction of new work
was initiated in March 1912; improvement of the channel modifi-
cation authorized in 1937 was initiated in May 1946 and completed
in June 1947. The channel is navigable during the entire year;
head of navigation is in the town of Suisun, Calif., about 400 feet
above Sacramento Street. The controlling depth is 7 feet in the
channel and harbor basin at mean lower low water. Maintenance
dredging is required to remove accumulated shoals to assure ade-
1358           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

quate project depths. Total costs for the project to June 30, 1954,
were $291,184 of which $217,677 was for new work and $73,507
for maintenance.
                                       Cost and financial summary

                                                    Fiscal year ending June 30                                Total to June
                                                                                                          ....3 0 , 195 4 , in c lu d -
                                                                                                            ing fiscal years
                              1950                1951               1952             1953      1954          priorto 1954

New work:
   Appropriated_   ----------------------                  ------------------------                                      $217,677
   Cost_--------   ------------------------------------------------------------                                           217,677
Maintenance:
   Appropriated -------.        $2,000          -$3, 215            $10, 000          $4, 800   $1,000                       73,507
   Cost ------------                                                 10,000            4,577     1, 223                      73,507



                       3. SUISUN BAY CHANNEL, CALIF.
   Location. Suisun Bay is about 30 miles northeast of San Fran-
cisco, Calif., and is an integral part of the waterways which provide
access to the Pacific Ocean from inland ports of California. Sacra-
mento and San Joaquin Rivers flow to a junction and empty into
Suisun Bay near Collinsville, and New York Slough, a distributary
of San Joaquin River, leads to the head of Suisun Bay at Pittsburg,
Calif. The port of Sacramento is situated on the Sacramento River
about 60 miles north of Collinsville; the city of Stockton is on the
San Joaquin River about 40 miles above Pittsburg and access to
the city has been provided by Stockton Deep Water Channel, an
artificial cut extending from the river about 21/4 miles into the city.
 (See U. S. Coast and Geodetic Survey Chart No. 5534.)
   Previousproject. The River and Harbor Act of March 2, 1919,
provided for a channel 300 feet wide from Martinez to Antioch,
Calif., 24 feet deep across the lower shoal near Bulls Head Point,
20 feet deep across Point Edith and Middle Ground Shoals, and 18
feet deep through New York Slough; all depths refer to mean lower
low water. Local interests were required to contribute toward the
first cost of construction and to provide spoil area together with
the required impounding levees. For further details, see page 1756
of Annual Report for 1920, page 1562 of Annual Report for 1926,
and page 1714 of Annual Report for 1938.
   Existing project. This provides for a channel 300 feet wide and
30 feet deep through Bulls Head Point, Point Edith, and Middle
Ground Shoals to the mouth of New York Slough, a distance of
about 13 miles, and for a channel 250 feet wide and 20 feet deep
south of Seal Islands from the main channel at Point Edith, mile
3, to the main channel again at Bay Point, mile 6. All depths refer
to mean lower low water. The tidal range between mean lower
low water and mean higher high water is about 6 feet. The ex-
treme range is about 9.5 feet.
   The total Federal cost of new work for the existing project, com-
pleted in 1934, exclusive of work accomplished under the public
works program as part of the San Joaquin River 30-foot project,
was $142,026, and the latest (1953) approved estimate for annual
(Federal) cost of maintenance is $75,000.
          RIVERS AND HARBORS-SACRAMENTO,                                CALIF., DISTRICT              1359
  The existing project was authorized by the following River and
Harbor Acts:

     Acts                          Work authorized                                    Documents'

Jan. 21, 1927    For a 26-foot channel through the bay-.......     ..--..   H. Doc. 554, 68th Cong., 2d sess.
July 3, 1930     The 30-foot channel across Bulls Head Point Shoal          Rivers and Harbors Committee
                  and for the 20-foot channel south of Seal Islands.          Doc. 23, 71st Cong., 2d sess.
Aug. 30, 19352   A 30-foot channel through Bulls Head Point, Point          Senate committee print, 73d Cong.,
                  Edith, and Middle Ground Shoals to the mouth of             1st sess. (San Joaquin River and
                  New York Slough.                                            Stockton Channel, Calif.).


  1 The latest published map is in Rivers and Harbors Committee Doc. 4, 70th Cong., 1st sess.
  2 Included in the Public Works Administration program, Sept. 6, 1933.



    Local cooperation. Fully complied with.
    Terminal facilities. Along the channel between the western
end of the bay and mouth of New York Slough, there are 3 wharves
and 2 car-ferry slips, all privately owned and used. Also, a naval
magazine with wharves and warehouses has been constructed at
Port Chicago, on the southern shore (mile 6). These facilities are
considered adequate for existing commerce.
    Operations and results during fiscal year. Maintenance: Oper-
ations during the year accomplished by hired labor included pre-
liminary surveys, preparation of plans and specifications, miscel-
laneous inspections and reports, and condition surveys. The
Government-owned hopper dredge Hyde was utilized during Octo-
ber and November 1953 to remove 237,129 cubic yards of material
in maintenance dredging at scattered locations in Suisun Bay
Channel. Further shoal removal of 59,090 cubic yards of material
was accomplished in Carquinez Straits for Sacramento District
under the direction of San Francisco District personnel by the
dredge Hyde. Total costs for maintenance during the fiscal year
were $69,909.
    Condition at end of fiscal year. New work under the existing
project was initiated in June 1930 and completed in 1934; a por-
tion of this work was accomplished under the public works pro-
gram. The portion of the existing project authorized prior to the
public works program was completed in 1931 except for deepening
the 26-foot channel across Bulls Head Point Shoal to 30 feet; this
portion was subsequently included in the public works program.
Work under the public works program was accomplished during
1933 and 1934. The channel is navigable during the entire year
and provides access to San Francisco Bay from the navigation
channels of San Joaquin and Sacramento Rivers. The controlling
depth at mean lower low water in the main channel is 28 feet, and
in the channel south of Seal Island is 14 feet. Annual dredging
is required to maintain the project depth and width in a satis-
factory manner without undue interference to essential navigation
requirements.
   Total costs for the existing project to June 30, 1954, exclusive
of the work performed under the public works program at a cost
of $207,198 as a part of the San Joaquin River 30-foot project,
were $1,030,540, of which $142,026 was for new work and $888,-
514 for maintenance.
1360          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                      Cost and financial summary

                                            Fiscal year ending June 30                    Total to June
                                                                                          30, 1954, includ-
                                                                                          ing fiscal years
                              1950         1951        1952        1953            1954   priorto 1954 12

New work:
   Appropriated .    ----      ----                                            -                3 $200,928
   Cost---------------                                                                -          3 200, 928
Maintenance:
   Appropriated -              9 000
                             $71,           -$381     $62, 000     $66, 875    $69, 900            948, 487
   Cost                       69,023        16,310     64,180       66, 710     69,909             948,331

  1Includes $58,901  for new work and $59,817 for maintenance for previous projects.
  2 In addition $59,551 for new work and $5,449 for maintenance was expended from contributed funds for
the previous project.
  3 Exclusive of work accomplished under existing project at a cost of $207,198 from Public Works Admin-
istration funds allotted to San Joaquin River.


                                      4. OLD RIVER, CALIF.
   Location. Old River is the most westerly branch of the inter-
connecting tidal channels into which the San Joaquin River divides
in crossing its delta. It leaves the main river 21/2 miles downstream
from the Mossdale State Highway Bridge, or 131/2 miles above the
mouth of Stockton Channel, and flows westerly and northerly
32 miles to its lower confluence with the main river, 23 miles above
its mouth in Suisun Bay.
   Existing project. This project extends along Old River from
its mouth near Venice Island to its source in the San Joaquin River
near Mossdale and provides for a side channel 10 feet deep and
80 feet wide to Santa Fe wharves and Phillips cannery at Orwood;
for channels 10 feet deep and 100 feet wide in Grant Line Canal
west of Doughty Cut, 10 feet deep and 80 feet wide from the
westerly end of Doughty Cut to the Holly Sugar factory, 2 miles
north of Tracy, 8 feet deep and 80 feet wide from the southerly end
of Doughty Cut to head of Old River, and 6 feet deep and 80 feet
wide in Old River from the westerly end of Grant Line Canal to
Lammers Ferry Road; and for entrances 8 feet deep and 80 feet
wide to Fabian-Bell Canal at its westerly end and also westerly
of Grant Line Bridge. All depths are referred to mean lower low
water. The tidal range between mean lower low water and mean
higher high water at the head of Old River is about 3 feet; and at
its mouth about 5.5 feet; ordinary flood ranges are, respectively,
16 feet and 8 feet; extreme flood ranges are, respectively, 20 feet
and 11 feet.
   The latest approved estimate of Federal cost for new work
 (1954) is $86,000 and the latest (1953) approved estimate for
annual (Federal) cost of maintenance is $35,000.
   The existing project was adopted by the River and Harbor Act
of August 26, 1937 (H. Doc. 151, 75th Cong., 1st sess.). This
document contains the latest published map.
   Local cooperation. Local interests are required to furnish with-
out cost to the United States all necessary rights-of-way and suit-
able spoil disposal areas for new work and for subsequent mainte-
nance as necessary, and to agree to provide public landings satis-
factory to the Chief of Engineers on each side of the proposed
channel in the Old River near Lammers Ferry Road and on the
     RIVERS AND HARBORS-SACRAMENTO, CALIF., DISTRICT           1361
Fabian-Bell Canal west of Grant Line Bridge. Spoil disposal areas
have been provided for those channels so far completed. Comple-
tion of the project is being held in abeyance pending fulfillment of
all requirements for local cooperation.
   Terminal facilities. The Santa Fe Railroad has a warehouse
and wharf at Orwood for transfer of farm produce from boat to
rail. The Phillips cannery at Orwood has similar facilities. The
Holly Sugar Co. refinery and terminal near Tracy has a large
wharf and an unloading basin with three mechanical unloading
and conveying units connecting with a warehouse; there is also
a passing basin one-half mile downstream. There are about 100
private bank landings along the project channels; some have
sheds for storage. These are all privately owned and operated.
Public landings should be provided as set forth above under "Local
cooperation."
   Operationsand results during fiscal year. Maintenance: Oper-
ations during the year consisted of miscellaneous inspections and
reports, maintenance of gages and gage readings, and condition
surveys of the channel, all of which were accomplished by hired
labor. In addition, removal of 90,342 cubic yards of material
at scattered locations in Old River, Grant Line Canal, and con-
necting channels leading to Holly sugar factory, was accom-
plished by hired labor and hired clamshell dredges Neptune and
California.
   Total costs during the fiscal year were $33,702 for maintenance.
   Condition at end of fiscal year. The construction of new work
was initiated in fiscal year 1939; the project is about 28 percent
complete. Work remaining to complete the project includes com-
pletion of the project channels up to and at Orwood; in Fabian-
Bell Canal, in Grant Line Canal, from Grant Line Canal to the
head of Old River in San Joaquin River, and in the original chan-
nel of Old River from Grant Line Canal up to the Lammers Ferry
Road, when the remaining requirements for local cooperation, in-
cluding rights-of-way, spoil area, and public landings have been
fulfilled. However, local interests have not shown any interest
in the remaining part of the project. Existing commerce does
not indicate a need for completion of the remaining channel con-
struction. The channel is navigable during the entire year and
provides the only avenue of water transportation from the delta
islands to certain agricultural processing plants. It is necessary
to perform annual maintenance dredging to maintain full channel
dimensions in order to accommodate the using traffic. The two
heads of navigation are at the head of Old River in San Joaquin
River, and at the Holly sugar factory wharf, 2 miles north of
Tracy. The controlling depths at the end of the fiscal year were:
From the mouth of the river to Orwood, 11 miles, 10 feet; thence
to the lower end of Grant Line Canal, 10 miles, 10 feet; thence (1)
to Holly sugar factory near Tracy, 6 feet (low water season), or
 (2) to head of Old River in San Joaquin River, 5 feet (low water
season). All depths refer to mean lower low water.
   Total costs for the project to June 30, 1954 were $304,592, of
which $23,185 was for new work and $281,407 for maintenance.
1362           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                     Cost and financial summary

                                                 Fiscal year ending June 30                            Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                              1950             1951               1952      1953            1954        priorto 1954

New work:
               ---------------
   Appropriated_                         ---------------------------------------------                         $ 23,185
   Cost....--------------------       -----------------------------                ------     ------------       23,185
Maintenance:
   Appropriated-----...       $25, 000         $28, 184          -$1, 997   $21, 003        $34, 400            282, 105
   Cost------------            45,423           29,238     ------------      21,003          33,702             281,407


Other new work data: Estimated additional amount needed to be appropri-
                                                              ___
      ated for completion of existing project_----------- ------------  $62,815
                          5. SAN JOAQUIN RIVER, CALIF.
   Location. San Joaquin River rises in east Central California in
the Sierra Nevada about 25 miles southeast of the Yosemite Valley
and flows southwesterly to the town of Mendota, thence northerly
to its confluence with Sacramento River about 48 miles northeast
of San Francisco to empty into Suisun Bay near Collinsville, Cali-
fornia. Total length of the river is about 340 miles. Near the
mouth, a distributary channel, New York Slough, 3 miles long,
leads to the head of Suisun Bay at Pittsburg; thence a deep chan-
nel extends through this bay and others to San Francisco. The
city of Stockton is on the east side of San Joaquin River about
40 miles above Pittsburg and access to the city has been provided
by Stockton Ship Channel, an artificial cut extending from the
river about 21/4 miles into the city. (See U.S. Coast and Geodetic
Survey Sheet No. 5527.)
   Existing project. This improvement, as authorized by the River
and Harbor Acts through May 17, 1950 (Public Law 516, 81st
Congress), provides for a channel 30 feet deep at mean lower low
water and for channel bottom width of 400 feet below Criminal
Point (near river mile 25) and 225 feet above that point, from
the mouth of New York Slough to Mormon Channel at Stockton,
a distance of 41 miles (suitably widened at bends and at the en-
trances to New York Slough and to channels through shoals, with
levees set back 230 feet from the center of the channel) ; for a
channel 30 feet deep and 150 feet wide thence to Weber Point, 1
mile; for a 9-foot depth, thence to the head of navigation at El
dorado Street, one-half mile; for a 9-foot depth at Fremont Chan-
nel and McLeod Lake, arms of Stockton Channel; and for a chan-
nel 9 feet deep and 100 feet wide in Mormon Channel from its
mouth to Washington Street, head of navigation, about 1 mile.
It also provides for suitable passing basins and a turning basin
30 feet deep, 960 feet wide and 1,900 feet long at Stockton; for
a turning basin 30 feet deep, 600 feet wide and 1,350 feet long
adjacent to Rough and Ready Island; for a triangular shapeid
         RIVERS AND HARBORS-SACRAMENTO,                                     CALIF., DISTRICT                1363
settling basin 30 feet deep and average side length of about 1,000
feet at the San Joaquin River just above its junction with the
deep water channel (mile 42) and a second settling basin 30 feet
deep, 100 feet wide and 1,200 feet long adjoining the deep water
channel at the mouth of Calaveras River; for dredging an addi-
tional settling basin 17 feet deep, 600 feet wide and 2,000 feet long
on San Joaquin River above the head of Burns Cutoff; for a leveed
channel 30 feet deep and 225 feet wide around Rough and Ready
Island including construction of a combination railroad and high-
way bridge; for the reconstruction to grade and section of about
4,000 feet of levee along the north side of Venice Island Cut, and
the setting back of levees where required for channel improve-
ments and for other levee changes and levee protective works
below Stockton; for cutting off sharp bends and making cutoffs
in the river; for filling Mormon Channel and Mormon Slough above
Washington Street with dredge spoil insofar as is economically
feasible; for partial closing of side channels at Laird Slough and
Paradise Cut by weirs to confine the low water flow to one main
channel; and for snagging, removing overhanging trees, and con-
structing brush wing-dams from the mouth of Stockton Channel to
Hills Ferry, 86 miles, to facilitate light-draft navigation on this
part of the river during higher stages of water.
   The following table shows the tide and flood conditions pre-
vailing:

                                                                                  Range in feet
                                                   Miles from
                     Place                         mouth of
                                                        river
                                                                  Mean        Extreme           Ordinary   Extreme
                                                                  tidal 1      tidal'            flood      flood


Collinsville        ..-------------------------------         0        5. 8           7. 0             8         10
Mouth of Stockton Channel-                                   40        3. 2           4.5              9         11
Mossdale Bridge-_                                            56        1. 5           2. 5            17         22
Hills Ferry-_ -         ___         _                       126     _------------------------         12         16


t Mean lower low water to mean higher high water.

   The latest approved estimate of Federal cost for new work
(1954) is $13,000,000. Non-Federal costs required for the project
construction are estimated (1954) at $3,267,500, exclusive of the
cost of suitable terminals and related facilities, comprising the
cash contribution of $1,837,500 toward the construction cost; pro-
vision of lands, easements, and rights-of-way; provision of suit-
able spoil-disposal areas for new work; and accomplishment of
necessary utility relocations and alterations. Maintenance of the
channel to project depths after completion is the responsibility of
the Federal Government. The latest (1953) approved estimate
for annual Federal cost of maintenance is $175,000.
 1364                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  The existing project was authorized by the following River and
Harbor Acts:

     Acts                               Work authorized                                            Documents
                  I                                                            I


Aug.   14, 1876       These acts provided for cutting off sharp bends and
Mar.    3, 1881         making cutoffs in San Joaquin River below the
July    5, 1884         mouth of Stockton Channel; dredging Mormon
Aug.   11, 1888         Channel; snagging, removing obstructions, and con-
July   13, 1892         structing wing dams in San Joaquin River from
Aug.   18, 1894         Stockton Channel to Hills Ferry; and the partial
June    3, 1896         closing of side channels at Laird Slough and Para-
                        dise Cut, without adopting any specific dimensions.
June 25, 1910         A 9-foot channel up to Stockton_...............__...._            H. Doc. 1124, 60th Cong., 2d sess.
July 25, 1912         Improvement of Fremont Channel and McLeod Lake                    H. Doc. 581, 62d Cong., 2d sess.
                        at Stockton.
Jan. 21, 1927         A 26-foot channel up to Stockton_...."...............             H. Doc. 554, 68th Cong., 2d sess.'
Aug. 30, 19352        The original 30-foot channel up to Stockton-.........             Senate committee print, 73d Cong.,
                                                                                          1stsess.
Aug. 26, 1937         The widened 30-foot channel up to Stockton-..........        ']   Rivers and Harbors Committee
                                                                                         Doc. 15, 75th Cong., 1st sess.'
May 17, 1950          Modification of the navigation project to provide for             H. Doc. 752, 80th Cong., 2d sess.
                       construction of a new turning basin adjacent to
                       Rough and Ready Island; widen existing turning
                       basin at Stockton; enlargement of Stockton Channel
                       between existing turning basin and Weber Point;
                       construction of leveed channel, as necessary, around
                       Rough and Ready Island, including construction
                       of a combination railroad and highway bridge;
                       dredging a settling basin on San Joaquin River
                       above the head of Burns Cutoff; elimination of
                       dredging of a portion of Mormon Channel; filling
                       of a portion of Mormon Channel and Mormon
                       Slough; and for levee changes and levee protective
                       works below Stockton.

1 Contains latest published maps.
2 Included in the Public Works Administration program, Sept. 6,
                                                                 1933.

    Local cooperation. All requirements for work accomplished to
date under the authorization of the River and Harbor Acts through
August 26, 1937, have been complied with. In accordance with
those acts, local interests were required to furnish, free of cost
to the United States, all lands, rights-of-way, and suitable spoil
disposal areas for new work and for subsequent maintenance;
contribute $1,307,500 toward the first cost of the dredging for the
26-foot project; provide terminal facilities; and assume mainte-
nance of the levees.
   In accordance with the River and Harbor Act of May 17, 1950;
local interests are required to (1) except for the new turning
basin, furnish free of cost to the United States all necessary lands,
easements, rights-of-way, and suitable spoil disposal areas for the
new work and subsequent maintenance, when and as required; (2)
agree to accept ownership of the combined rail and highway
bridge upon completion of construction, together with mainte-
nance, operation, and future replacement or alteration as may be
required, provide and maintain any other bridges required over
the waterway, and accomplish all necessary utility relocations
and alterations and the maintenance thereof; (3) contribute pro-
gressively as the project is constructed, at such rate as is satis-
factory to the Secretary of the Army, a total of $530,000 in cash
toward the cost of new work of the improvement; (4) prior to
enlargement of Stockton Channel and construction of the channel
around Rough and Ready Island, agree to provide, maintain, and
operate suitable terminal and related facilities at the site of the
improvement under consideration; (5) agree to continue to main-
      RIVERS AND HARBORS-SACRAMENTO, CALIF., DISTRICT           1365
tain the levees along the deep water channel including those pro-
vided with bank protection by the Federal government and those
bordering the improved channel around Rough and Ready Island;
and (6) agree to hold and save the United States free from
damages resulting from construction, maintenance, and operation
of the proposed improvements. The necessary assurances for
compliance with the above requirements of the 1950 authorization
will be requested from local interests upon completion of detailed
project plans.
   Terminal facilities. The harbor facilities at the Port of Stock-
ton, Calif., consist of 55 piers, wharves and docks which are
located along the San Joaquin River and on the Stockton, Mormon,
and Fremont Channels. With the exception of four facilities on
the San Joaquin River and three on Mormon Channel, all facilities
are located on Stockton Channel or in proximity thereto. Nearly
half of the port's water terminals are bulkhead-type shore wharves
with sufficient depths of water to accommodate ordinary river
craft; the ocean terminals are concrete marginal wharves; and
the remainder are generally open pile, timber-decked piers, shore
wharves, or offshore wharves. General cargo facilities (6 in
number) and petroleum handling facilities (7 in number), are
indicative of the foremost items of waterborne commerce handled
at the port. The harbor facilities include a marine service station,
facilities for handling creosote, treated piling, fruits, vegetables,
ore and other bulk materials.
   About one-half of the waterfront facilities are owned by the
city of Stockton and are under the jurisdiction of the Stockton
Port District, governed by the board of port commissioners. The
Stockton Port District is the agency operating the Stockton Ocean
terminal, comprised of seven public wharves and a bulk-material
wharf providing 3,335 feet of berthing space in depths of 28 and
29 feet, mean lower low water, with approximately 303,400 square
feet of transit sheds, as well as 508 feet of open wharf. Eight
oceangoing vessels can be accommodated at one time at the public
ocean terminal. The transit sheds are provided with rail con-
nections by the Stockton public belt railroad. The port also owns
and operates five storage warehouses with a total of 799,420 square
feet of storage area available for public merchandise, equipped
with portable mechanized handling equipment and served by
trackage of the belt railroad, adjacent to the public ocean terminal
which includes a cotton warehouse and compress with 246,400
square feet of floor area and a grain terminal. The grain terminal
has a floor area of 185,140 square feet and a cubical capacity of
3,41.4,600 feet. It has a storage capacity of 2,500 tons of loose
barley in 15 laminated wood bins, and space for approximately
35,000 tons of sacked grain. Bulk shipments are transferred to
vessels by overhead conveyors having a maximum capacity of
250 tons of bulk grain or 50 tons of sacked grain per hour.
Approximately 1,000,000 square feet open storage space is avail-
able at Stockton Port District public wharves for commodities not
affected by weather conditions. The open storage space is readily
accessible to trucks and is served by trackage of the belt railroad.
Portable handling equipment and a 121/-ton locomotive crane
 1366     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 195.4

  serve the storage areas on the port district property. Certain
  facilities at the Stockton port terminal are in use for military
  purposes. A naval supply depot (Stockton annex) has been com-
  pleted on Rough and Ready Island, bounded by the Stockton deep
  water channel on the north side, San Joaquin River on the east
  side, and !Burns Cutoff on the south and west sides.
     Shallow-draft facilities on the upper channel include 12,500
  linear feet of wharves of which 8,620 linear feet are privately
  operated, the remainder being operated by the Stockton Port
  District. Included along these wharves are 341,600 square feet
  of transit sheds and 225,370 square feet of storage warehouses.
  There are two privately owned cold-storage warehouses located on
  Mormon Channel with a total storage capacity of 1,582,750 cubic
  feet, of which 1,124,750 cubic feet are available for public storage.
     The port owns and operates the belt-line railroad, which connects
  with three transcontinental railroads and serves all facilities in
the area; highway trucks are afforded easy access by paved streets
  and roads. An excellent system of improved highways connects
  the port with the Pacific coastal areas, as well as the surrounding
  agricultural area.
     Downstream from Stockton, the traffic is accommodated by bank
  landings and sheds, except at Antioch and near Pittsburg, where
there are wharves for shallow and deep draft vessels.
    The terminal transfer facilities at the public ocean terminal of
the port of Stockton are adequate for the present and immediate
future. The 1952 tonnage reported in and out by the port of
Stockton was nearly 2,000,000 tons. Of this amount, over 1,000,-
000 tons constitute deep draft cargo and the balance barge traffic.
There has been a sustained annual growth of traffic in and out of
the port of Stockton. The port has expanded its loading and
storage facilities to handle iron ore brought in by rail from
Nevada; it is expected that this item will reach 1,000,000 tons a
year. It is expected that construction of the facilities authorized
by the 1950 River and Harbor-Flood Control Act will be required
in the relatively near future to accommodate the additional re-
quirements of industry and commerce.
    Operations and results during fiscal year. New work: None.
Maintenance: Operations during the year included condition sur-
veys of the channel, maintenance of gages and gage readings,
preparation of plans and specifications, and miscellaneous field
reconnaissance and reports, all of which were performed by hired
labor; and the removal of 292,831 cubic yards of material at scat-
tered locations in San Joaquin River near Antioch, Calif., by the
utilization of the Government-owned hopper dredge Hyde. Total
costs during the fiscal year were $62,425 for maintenance.
    Condition at end of fiscal year. The existing project is about
32 percent complete. Construction of the project was initiated in
December 1877; further modifications were subsequently author-
ized and accomplished. The 9-foot channel up to Stockton, au-
thorized in 1910, was initiated in 1915 and completed in 1923.
Improvement of Fremont Channel and McLeod Lake, authorized
         RIVERS AND HARBORS-SACRAMENTO,                                          CALIF., DISTRICT                1367
in 1912, was accomplished in 1914. Dredging of the 26-foot chan-
nel up to Stockton, authorized in 1927, was initiated in 1930 and
completed in 1933. The original 30-foot channel up to Stockton,
which was included in the Public Works program under the
National Industrial Recovery Act and subsequently authorized in
1935, was accomplished during 1934 and 1935. Dredging of the
widened 30-foot channel, authorized in 1937, was initiated in
1938 and completed in October 1940; Mormon Channel was
dredged from the junction with Stockton deep water channel to
a point near Washington Street Bridge at Stockton in 1948. There
has been no new work accomplished since that date. All work
authorized prior to May 1950 is complete except for the dredging
above the south line of Main Street in Stockton to a depth of 9
feet; local interests have advised that dredging above the south
line of Main Street will not be required. The turning basin in
Stockton Channel is 960 feet wide and has a length of 1,900 feet
along the northerly edge, tapering to 1,100 feet along the southerly
edge.
   The controlling depth from mouth of the river in Suisun Bay to
Mormon Channel, 41 miles, is 28 feet; thence to Edison Street,
three-quarters of a mile, 22 feet; and thence to head of Eldorado
Street one-half mile, 9 feet. A 9-foot depth is available in Mormon
Channel, up to Main Street, 0.9 mile; thence 2 feet to Center Street,
head of navigation; and 9 feet in Fremont Channel and McLeod
Lake. All depths are referred to mean lower low water. The
channel is navigable during the entire year.
   The river, from its junction with Stockton Channel to the Moss-
dale Bridge (16 miles), usually has a controlling depth of 4 feet
from April to June, inclusive, and from Mossdale Bridge to Hills
Ferry (70 miles), head of navigation, the usual controlling depth
is 3 feet from April to June, inclusive. Navigation in the section
above the San Joaquin Bridge (Southern Pacific Railroad crossing)
is impracticable in the low stages after June.
   New work remaining to complete the project consists of the con-
struction authorized by the River and Harbor-Flood Control Act
of May 17, 1950, for modification of the navigation project.
   Annual maintenance dredging is required for removal of ac-
cumulated shoals caused by settlement of flood borne sand and
silt to provide the project depths in satisfactory condition to ac-
commodate general and defense navigation requirements.
   The total costs for the project to June 30, 1954, were as follows:


                            Funds                                            New work        Maintenance        Total


United States:
   Regular.--      -       ------------------             ----------------    $2, 851, 590     $3, 208, 409    $6, 059, 999
   Public works..___.---------------------  -             ------               1,158, 348       _--     -     1 1, 158,348

     Total United States funds                   - ----------                  4, 009, 938      3, 208, 409     7, 218, 347
    Contributed...........     ----            -------------------             1, 307, 500           1, 250     1, 308, 750

      Total, all funds            ....--....------------------------           5, 317, 438      3, 209,659      8, 527, 097

  1 Includes $207,198 for the 30-foot channel in Suisun Bay Channel.
1368           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                            Cost and financial summary

                                                    Fiscal year ending June 30                        Total to June
                                                                                                      30, 1954, includ-
                                                                                                      ing fiscal years
                                   1950           1951          1952          1953         1954         prior to1954 1

New work:
   Appropriated      ...            -$966     ..... .....    ...-      --- -------- ------------..        2 $4,009,938
   Cost...--------         ---------------------------------------------------------....                     4,009938
Maintenance:
    Appropriated........         $108,000        $238, 749     $299, 446     $146, 550     $51, 600         3,208, 843
    Cost  - - --     ---           62, 039        314,509       293,548       146,584       62,425          3,208,409

  I In addition $1,307, 500 for new work and $1,250 for maintenance was expended from contributed funds.
2 Includes $1,158,348 from Public Works funds, of which $207,198 was for the 30-foot channel in Suisun
Bay Channel.

Other new work data: Estimated additional amount heeded to be appro-
  priated for completion of existing project_ _-----------------  .$8,990,062

6. STOCKTON AND MORMON                                    CHANNELS              (DIVERTING             CANAL),
                                                         CALIF.
   Location. This is an artificial cut located about 3 miles east of
Stockton, Calif., which extends northwesterly about 41/2 miles
to intersect the original Calaveras River Channel near the north-
east corner of the city of Stockton. (See U. S. Geological Survey
Sheet, Stockton quadrangle.)
   Existing project. This provides for diverting the waters of
Mormon Slough before reaching Mormon and Stockton Channels
for the purpose of preventing deposits of material in the navigable
portions of Stockton and Mormon Channels. The results were
obtained by construction of a dam in the slough 3 miles east of
Stockton, and a canal 150 feet wide, with average cut of 8 feet,
thence to the north branch of the Calaveras River, 4.63 miles; by
the enlargement of the cross section of this branch to 1,550 square
feet, thence to its mouth at San Joaquin River, 5 miles; and by
the construction of a levee along the west side of the canal and
the south side of the north branch of the Calaveras River from
the material excavated. The height of the levee is limited by
necessary railway and highway crossings to about 3 feet above
the contemplated flood surface. The canal is empty during the
greater part of the year, but at times of extreme flood there is a
depth of about 12 feet, and at ordinary flood a depth of about
10 feet.
   The total Federal cost of new work for the project, completed
in 1923 was $253,151, and the latest (1953) approved estimate
for annual Federal cost of maintenance is $8,000.
   The existing project was authorized by the River and Harbor
Act of June 13, 1902 (H. Doc. 152, 55th Cong., 3d sess., and
Annual Report for 1899, p. 3188). The latest published map is
in House Document 256, 63rd Congress, 1st session.
   Local cooperation. Fully complied with.
   Terminal facilities. See report on San Joaquin River, Calif.
   Operationsand results during fiscal year. Maintenance: Oper-
ations during the year consisted of condition inspections and
studies, field reconnaissance, and miscellaneous reports, all of
which were accomplished by hired labor. In addition, clearing at
scattered locations along the banks of Calaveras River and the
         RIVERS AND HARBORS-SACRAMENTO,                                        CALIF., DISTRICT                        1369
Diverting Canal between the mouth of Calaveras River and U.S.
Highway 99 was accomplished by hired labor. Bank repairs along
the left bank of Calaveras River, near Stockton, Calif., were ac-
complished by contract. Total cost during the fiscal year was
$9,530.
   Condition at end of fiscal year. Construction of new work was
initiated in November 1908; under this initial construction phase,
work along the Calaveras River section was completed in October
1909 and the Canal section of the Diverting Canal in September
1910. The project was then considered to be about 86 percent
complete; no further new work was accomplished until fiscal year
1922. During fiscal years 1922 and 1923 additional new work was
accomplished in the Calaveras River section to complete the pro-
ject. The structures involved are in good condition. Most of the
silt formerly deposited in Stockton and Mormon Channels is
diverted therefrom by this canal, obviating serious inconveniences
to navigation and expensive annual dredging.
   Annual maintenance activities, consisting of the provision of
an adequate channel capacity for floodwaters by clearing brush
and trees and construction of bank protection at critical locations
to prevent slippage and erosion of banks caused by floodwaters,
are required to preserve the effectiveness of the project.
   Total cost for the project to June 30, 1954, was $411,423, of
which $253,151 was for new work and $158,272 for maintenance.
                                       Cost and financial summary

                                               Fiscal year ending June 30                                      Total to June
                                                                                                              30, 1954, includ-
                                                                                                              ing fiscal years
                                1950         1951             1952             1953                1954          prior to 1954

New work:
   Appropriated                  ---       -------- -----        ----- -                   ---                         $253,151
   Cost                                                         -253,151
Maintenance:
   Appropriated-_ ...           $8, 000     -$2,    072        $7, 712         $17, 500            $1, 100              158, 480
   Cost-----------      --       9,359                6         7, 712           8,862              9,530               158,272



                        7. INACTIVE NAVIGATION PROJECTS

                                                                            Cost to June 30, 1954
                                                            For last                                               Estimated
                      Project                             full report                                                amount
                                                          see annual                              Operation        required to
                                                          report for-    Construction               and             complete
                                                                                                 maintenance

Feather River, Calif__ --               _                    1951                                    1 $5, 752          (2)
Middle River and connecting channels, Calif                  1951              3$8,354                3 1, 682       (4), (5)
Mokelumne River, Calif-.......----------------- -            1951                 8, 500               67, 537       (4), (5)
Snagging and Clearing under authority of sec. 3              1951          _                            2,997           (4)
  of the River and Harbor Act approved Mar.
  2, 1945.


   1 Includes $10 for maintenance for previous project. In addition, $6,160 for previous project and $3,840
for existing project, for maintenance, was expended from contributed funds.
  2Maintenance project; channels currently adequate for commerce; latest approved estimate (1953) of
Federal cost for annual maintenance is $2,000.
  3 Includes $1,600 for new work and $790 for maintenance for previous project.
   4 Completed.
   SMaintenance not presently required as channels are adequate for commerce. Latest approved estimate
(1953) of Federal cost for annual maintenance is $2,000 for Middle River and connecting channels and $4,000
for Mokelumne River, Calif.
1370     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   8. SACRAMENTO RIVER AND TRIBUTARIES, CALIF., FROM
              COLLINSVILLE TO SHASTA DAM
   Location. The Sacramento River rises in the Trinity Mountains
in north-central California, flows in a general southerly direction
about 374 miles and empties into Suisun Bay, an arm of San
Francisco Bay at Collinsville, Calif. The works covered by this
improvement are on the Sacramento River and tributaries from
Collinsville to Shasta Dam, about mile 312. (See U.S. Geological
Survey quadrangles of the area for Sacramento River and upper
Butte Basin; Flournoy and Fruto quadrangles for Black Butte
Reservoir; and the Tuscan Buttes, Tehama, Redding, and Hooker
quadrangles for Table Mountain Reservoir.)
   Existing project. The improvement of Sacramento River and
tributaries, from Collinsville to Shasta Dam, was authorized as a
unit of a comprehensive plan for flood control and other related
purposes in the Sacramento River Basin. The project comprises
the enlargement of existing levees on Sacramento River between
vicinity of Moulton Weir and Ord Bend; the construction of new
levees from the present levee terminus to vicinity of Chico Land-
ing; construction of a weir in vicinity of Chico Landing, the ex-
tension of Moulton Weir, and construction of a bypass through
Upper Butte Basin; the construction of new levees in lower Butte
Basin; and the enlargement of existing levees in Sutter, Tisdale,
Sacramento, and Yolo bypasses. In addition to the above, the
project includes levee construction and/or channel enlarge-
ment on the following minor tributaries of the Sacramento River:
Antelope Creek; Chico and Mud Creeks and Sandy Gulch; Butte
and Little Chico Creeks; Cherokee Canal; Elder Creek; Deer Creek
 (Tehama County) ; Thomes Creek, and Willow Creek. These im-
provements are for the purpose of flood control.
   The above levee construction supplements the program of levee
improvements which are being accomplished pursuant to the Flood
Control Act of March 1, 1917, as amended by subsequent acts, in-
cluding the Flood Control Act of August 18, 1941, and which are
reported by California Debris Commission under Improvement
No. 4, "Sacramento River, Calif., Flood Control."
   Improvements on the minor tributaries will, in themselves,
provide flood protection to large agricultural areas, to the cities
of Chico and Willows, to small communities, and to transportation
systems. The improvements along the major tributaries and in
Butte Basin, in conjunction with the following authorized Table
Mountain (Iron Canyon) and Black Butte Reservoirs in the upper
Sacramento Basin, will provide flood protection to an additional
large agricultural area in Butte Basin and along the Sacramento
River, and to additional communities and transportation systems.
A total area of 218,000 acres of agricultural land will be protected
by the entire project.
   The authorization also provides for the construction of the
Black Butte Reservoir, an earthfill dam, with a maximum height
of 138 feet, to create a reservoir with a gross storage capacity
of 160,000 acre-feet for flood control and water conservation
purposes. The improvement will be located about 9 miles westerly
of Orland, Glenn County, Calif., on Stony Creek, a tributary en-
               FLOOD CONTROL-SACRAMENTO,                      CALIF., DISTRICT                   1371
tering the Sacramento River at mile 190. The reservoir will
provide flood protection for about 35,000 acres of agricultural
land lying along the lower reaches of Stony Creek and west of
Sacramento River and, in addition, will provide 60,000 acre-feet
of new water annually for irrigation. In conjunction with the
authorized Table Mountain (Iron Canyon) Reservoir on Sacra-
mento River, this reservoir will provide flood protection to about
106,000 acres of agricultural land in Butte Basin and will augment
the flood protection to lands along Sacramento River and tribu-
taries where levee and channel improvements have been provided.
   In addition, the improvement provides for construction of Table
Mountain (Iron Canyon) Reservoir, an earthfill dam, with a max-
imum height of 210 feet and an ungated saddle spillway, to create
a reservoir with a gross storage capacity of 503,000 acre-feet, for
flood control, water conservation, and power generation. Con-
struction of a power plant with an installed capacity of 54,000
kilowatts is included in the improvement. The reservoir will be
located on the Sacramento River at about mile 250, about 3 miles
north of Red Bluff, in Tehama and Shasta Counties, Calif. The
reservoir will provide flood protection to a local area of about
50,000 acres along Sacramento River. In conjunction with the
above authorized Black IButte Reservoir, this reservoir will pro-
vide flood protection to about 106,000 acres of agricultural lands in
the basin and will augment the flood protection along Sacramento
River and tributaries where levee and channel improvements have
been provided. In addition, the reservoir will make available
about 350,000 acre-feet of new water annually for irrigation and
will make possible the generation of about 300,000,000 kilowatt-
hours of electrical energy per year.
   The latest approved estimate of Federal cost for new work of
the principal features is as follows:

                                                                          Estimated cost


                       Project                                              Lands and
                                                       Construction          damages         Total


Levees, Sacramento River and tributaries, including      $32, 830, 000-    -- ___ _' _ __    $32, 830, 000
  Upper Butte Basin.
Black Butte Dam and Reservoir ----------------------      14, 809, 200          $690, 800    115, 500, 000
Table Mountain (Iron Canyon) (low-level) dam and          73, 389, 400         3, 810, 600   177, 200, 000
powerplant.

     Total                                               121, 028., 600        4, 501, 400   125, 530, 000

   (1954)


   The estimated (1954) cost to local interests for new work on
the levee and channel improvements is $7,342,000 and comprises
the provision of lands, easements, and rights-of-way and all neces-
sary highway and utility alterations required.
   Operation and maintenance of the levee and channel improve-
ments after completion will be the responsibility of local interests.
Operation and maintenance of the Black Butte Reservoir and of
Table Mountain (Iron Canyon) Reservoirs and power facilities
will be the responsibility of the Federal Government; the latest
1372     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

approved estimated (1948) annual cost is $60,000 for Black Butte
Reservoir and $567,000 for Table Mountain (Iron Canyon) Reser-
voir and power facilities. Local interests will reimburse the
United States for conservation accomplishments of the reservoirs.
   The improvement was adopted by the Flood Control Act of
December 22, 1944 (H. Doc. 649, 78th Cong., 2d sess., which con-
tains the latest published map (which authorized to be appropri-
ated for the initiation of the project the sum of $15,000,000; and
as further amended by the Flood Control Act of May 17, 1950 (H.
Doc. 367, 81st Cong., 1st sess.), to include the necessary works
of improvement for the protection of the upper Butte Basin.
   Local cooperation. With respect to conservation storage to
be provided by the Table Mountain (Iron Canyon) and Black
Butte Reservoirs, payment, as determined by the Secretary of
the Army upon the basis of continuing studies by the Bureau of
Reclamation, the Department of the Army, and local organiza-
tions, is to be made to the United States by the State or other
responsible agency for this storage when used.
   Chapter 1514 of the Statutes of 1945, State of California, ap-
proved July 19, 1945, provides for adoption of the project and for
the furnishing of the required assurances of local cooperation for
the levee and channel improvement work. These assurances
have been furnished and accepted.
   All lands and rights-of-way required to date have been furnished
by the State of California.
   Operations and results during fiscal year. a. Construction and
enlargement of levees and local improvements on Sacramento
River and major and minor tributaries: Preliminary engineering
was continued. The Federal cost of new work during the fiscal
year was $23,123.
   b. Black Butte Reservoir: There were no operations during the
fiscal year, and no costs were incurred.
   c. Table Mountain Reservoir: There were no operations during
the fiscal year, and no costs were incurred.
   Total cost of new work for the entire project during the fiscal
year was $23,123.
   Condition at end of fiscal year. a. Construction and enlarge-
ment of levees and channel improvements on Sacramento River
and major and minor tributaries: Preliminary engineering, in-
cluding field surveys and preparation of detailed plans and con-
tract plans and specifications, is being continued; design work is
about 8 percent completed. Construction of the project was initi-
ated in May 1949; items completed include most of the Deer Creek
levees and a portion of the Butte Creek channel improvements
and levees. Initiation of further construction was suspended
                   FLOOD CONTROL-SACRAMENTO,                        CALIF., DISTRICT                   1373
as a result of Presidential Directive dated July 21, 1950. The
project is about 5 percent complete.
   Levee work remaining to be done includes enlargement of exist-
ing levees on Sacramento River between Moulton Weir and Ord
Bend; and on Sutter, Tisdale, Yolo, lower Yolo, and Sacramento
bypasses; construction of new levees on Sacramento River from
Butte City to Chico Landing and in lower Butte Basin. In addi-
tion to the above, the project includes uncompleted levee con-
struction and channel enlargement on the following minor tribu-
taries of the Sacramento River: Antelope Creek; Little Chico-
Butte Creek above Highway 99E, Chico, Mud, and Sandy Gulch
Creeks; Cherokee Canal; Elder Creek; Deer Creek (Tehama
County); Thomes Creek; and Willow Creek. Construction of
bypass levees and necessary works of improvements for the pro-
tection of the upper Butte Basin, as authorized by the Flood
Control Act of May 17, 1950 (H. Doc. 367, 81st Cong.), also re-
mains to be accomplished.
   Total cost of new work to June 30, 1954, was $1,748,352.
   b. Black Butte Dam and Reservoir: Data for definite design
studies has been assembled, including general design, surveying
and mapping, and exploration and material tests. The definite
design studies are about 25 percent complete; and plans and
specifications are about 10 percent complete; construction has not
been initiated. Further engineering activities have been discon-
tinued due to lack of funds. Total cost of new work to June 30,
1954, was $101,260.
   c. Table Mountain (Iron Canyon) -Dam and Reservoir: Engi-
neering studies are about 28 percent complete. Only portions of
the definite project report have been completed; no work on the
preparation of plans and specifications is in progress. Further
investigations and engineering studies for the reservoir have been
indefinitely delayed because of lack of agreement among local
interests and State and Federal agencies concerned, with respect
to conflicting proposals for control of floods and use of water
resources in the upper Sacramento Valley. Total cost of new
work to June 30, 1954, was $637,608.
   Total cost of new work for the entire project to June 30, 1954,
was as follows:

                                             Project                                             Total cost of
                                                                                                  new work

Sacramento River and major and minor tributaries.............---------------------------             $1, 748, 352
Black Butte Dam and Reservoir..-------------------                   --------------------                101, 260
Table Mountain (Iron Canyon) Dam and Reservoir- ....................                                    637, 608

      Total..-----....----   --------------------------------------------------   ------------        2, 487, 220
1374          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY. 1954

                                   Cost and financial summary

                                         Fiscal year ending June 30                    Total to June
                                                                                      1 30, 1954, includ-
                                                                                       ing fiscal years
                            1950        1951        1952        1953        1954        prior to 1954

New work:
   Appropriated__          $695, 000   $216,108    -$2, 240                                  $2, 588,868
   Cost - -         .      618,152      594, 788    255, 438    $37, 242    $23,123           2, 487, 220

1 Includes amount of $23,000 advance for establishment of South Pacific Division Laboratory.



Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954             ------------
                                                                        $101,618
    Appropriated for succeeding fiscal year ending June 30, 1955 .             O
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955__________       ____________________________
                                      -                                  101,618
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project ____________________________ ___   122,941,132

   9. FOLSOM RESERVOIR, SACRAMENTO                             RIVER BASIN, CALIF.
   Location. The Folsom Dam site is on the American River about
21/2 miles above or northeasterly of the town of Folsom in Sacra-
mento County, Calif., about 1 mile below the confluence of the
north and south forks of this stream, and about 20 miles upstream
from the city of Sacramento. The reservoir will extend from the
dam site up the main river to this confluence and about 14 miles
farther upstream in each of the two forks. The American River
system originates on the western slope of the Sierra Nevada, and
the main river flows into the Sacramento River at the city of
Sacramento. The lower portion of the American River, 25 miles
below Folsom, is in the Sacramento Valley. The drainage area
of the river system contains 2,115 square miles of which 1,875
square miles are above the dam site. (See U. S. Geological Survey
quadrangles of the area.)
   Existing project. The authorization provided initially for the
construction of a dam, with gross storage capacity of 355,000
acre-feet, and facilities for future power generation. The project,
as modified, provides for the construction of a multiple purpose
storage reservoir with a storage capacity of 1,000,000 acre-feet
in the joint interest of flood control, irrigation, municipal water
supply, and power generation. The reservoir will be formed by
construction of earthfill wing dams and a concrete gravity dam in
the river channel with a gated spillway and with a maximum
height of approximately 340 feet and crest length of 1,400 feet.
The earthfill wing dams on each side of the river with a maximum
height of 145 feet will complete the closure; the crest length of
the right wing dam will be about 6,700 feet and the left wing dam
about 2,100 feet. An earthfill auxiliary dam is provided at Mor-
mon Island, about 21/2 miles easterly from the main dam, with a
maximum height of 110 feet and a crest length of about 4,820
feet. Eight earthfill dikes, with a total crest length of approx-
imately 11,700 feet and maximum height of 10 feet to 100 feet,
close saddles in the reservoir perimeter. Outlet facilities will be
provided for irrigation and flood control releases and for power
            FLOOD CONTROL-SACRAMENTO, CALIF., DISTRICT        1375
generation. Simultaneous construction of a hydro-electric power
plant at the damsite with power facilities of 162,000 KW capacity,
a downstream reregulatory afterbay at Nimbus Dam with power
facilities of 13,500 KW capacity, and related transmission lines
is being accomplished by the U. S. Bureau of Reclamation. Sub-
sequent maintenance and operation of the completed project
will be accomplished by that agency in conjunction with other
units of the Central Valley project. The authorization also pro-
vides for the dam to be operated for flood control in accordance
with criteria established by the Secretary of the Army.
   The project will provide flood protection to the cities of Sacra-
mento and North Sacramento and adjacent suburban areas, will
make available annually about 500,000 acre-feet of new water for
irrigation and municipal water supply and will make possible the
generation of about 500,000,000 kilowatt-hours of electrical energy
per year.
   The latest approved estimate of Federal cost for new work
 (1954) is $65,400,000, of which $2,622,500 is for lands and dam-
ages and $62,777,500 for construction, including $5,209,900 for
penstocks, trash racks, penstock face gates, and tailrace excava-
tion being constructed by the Corps of Engineers for and in co-
ordination with the facilities being built at the Folsom site by the
Bureau of Reclamation.
    The latest estimate (1953) of the cost of the Federal facilities
being constructed by the U. S. Bureau of Reclamation is $40,098,-
000. Local interests will reimburse the United States for the con-
servation accomplishments of the project.
   The existing project was adopted by the Flood Control Act of
December 22, 1944 (H. Doc. 649, 78th Cong., 2d sess., which con-
tains the latest published map), as modified by the American River
Basin Development Act (Public Law 356, October 14, 1949, 81st
Cong., 1st sess.).
   Local cooperation. None required, except payment for conser-
vation costs when used; these costs have not yet been allocated.
The State of California officially adopted the project by chapter
1514 of the Statutes of 1945, State of California, approved July
19, 1945.
    Operations and results during fiscal year. New work: Engi-
neering, including preparation of contract plans and specifications,
was continued. Preparation of operation and maintenance man-
uals, operation of construction facilities, engineering studies to
develop criteria for flood control operation of Folsom Reservoir,
and acquisition of land (including improvements, disposals, and
damages) were continued during the fiscal year.
    Construction of the Folsom Dam and appurtenant works, by
continuing contract, was continued; 46 percent of the work was
placed this period. Fabrication of the 140-ton gantry crane and
appurtenances, under continuing supply contract, was continued;
10 percent of the work was accomplished this year. Fabrication
was completed and delivery made, under continuing supply con-
tracts, of the fixed-wheel gates, frames, and anchorage for pen-
stocks, 43 percent placed this year; penstock gate hoists and
appurtenances, 18 percent this year; and tainter gates and appur-



     Sigs    1--1875-1406
1376     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

tenances, 36 percent this year. In addition, the following con-
tinuing contracts were completed with work placement as follows:
Relocation of Pacific Gas and Electric Co.'s Halsey Junction-New-
ark electric power transmission line, 10 percent this year; furnish
and install pumping plant equipment, supply contract, 30 percent
this year; and South Fork Road relocation, 26 percent this year.
    Additional work accomplished by hired labor included the pur-
chase and installation of electric tape gages, continuation of estab-
lishment of sedimentation ranges, initiation of removal of Negro
Hill telephone lines, and survey for fencing of the reservoir area.
    Relocation of Pacific Gas and Electric Co.'s power distribution
lines was continued with 31 percent accomplished during the year.
Completion of construction, by contracts, was accomplished during
the year as follows: Construction of South Fork Road, Sweetwater
Creek Section extension, 10 percent this year; Natoma Canal Re-
location and appurtenant facilities, 26 percent this year; and
reservoir clearing, Area "A," 86 percent this year.
    Foundation drilling and grouting through embankment was
initiated by continuing contract, 79 percent of the work placement
was accomplished during the year. Additional construction for
the project was initiated by contracts as follows: Relocation of
Green Valley and Mormon Island Roads, vicinity of Mormon Is-
land Auxiliary Dam, with 90 percent placed during the year;
reservoir clearing, Area "B," 32 percent this year; foundation
drilling and grouting, main concrete dam, 5 percent this year; and
relocation of cemeteries, 1 percent this year.
    Total cost of new work during the year for the project was
$19,366,796.
   Condition at end of fiscal year. Construction was initiated in
October 1948; the project is about 75 percent complete. Design
work is approximately 90 percent complete; relocations are about
79 percent complete; land acquisition is practically completed; and
the construction of the dam and its appurtenances is 75 percent
complete. Major items of work completed include construction of
5 of the 8 earthfill dikes required; the Government administration
and operations buildings; the diversion tunnel and the foundation
excavation for the main dam; Mormon Island auxiliary dam in-
cluding riprapping; relocation of North Fork Ditch Co. buildings
and utilities; relocation of Natoma Canal and appurtenant facili-
ties; reservoir clearing, area "A"; relocation of Folsom-Auburn
Road and of South Fork Road; construction of South Fork Road,
Sweetwater Creek Section extension; and fabrication of tandem
slide gates for main dam outlet works and other appurtenant op-
erating equipment.
   Design and construction programs of the Corps of Engineers
and the Bureau of Reclamation have been coordinated to provide
for orderly prosecution of the project, and construction work to be
accomplished by the Corps of Engineers in the interest of power
development is under way.
   Work remaining to complete the project includes: completion of
items now under construction, including the main dam; final test-
ing of the tandem slide gates, tainter gates, and other such operat-
ing equipment; malaria control; additional access roads, miscel-
               FLOOD CONTROL-SACRAMENTO, CALIF., DISTRICT                                                   1377
laneous road improvements and repairs; additional water supply
and sanitary facilities; and the installation of gages and communi-
cation facilities for operating purposes.
   The project construction schedule calls for closing of the diver-
sion tunnel gates on February 15, 1955, and completion of all con-
struction work by June 30, 1956.
   Total cost to June 30, 1954, for the project is $49,240,665 for
new work.
                                      Cost and financial summary

                                              Fiscal year ending June 30                            Total to June
                                                                                                    30, 1954, includ-
                                                                                                    ing fiscal years
                               1950         1951           1952          1953           1954          priorto 1954


New work:
   Appropriated       -    $3, 100,000   $4, 400, 000   $6, 870,000 $16, 917, 000   1$17, 500,000      1$50, 369, 000
   Cost  -...-.-- .....     1,372,848     2, 924, 499    8, 893, 049 151237, 722     19, 366, 796        49, 240, 665


   Includes $4,200,000 allotted on loan basis during fiscal year 1954.
2 Exclusive of $4,200,000 utilized for repayment of funds loaned in fiscal year 1954.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 ___-___        $106,156
    Appropriated for succeeding fiscal year ending June 30, 1955__-  2 10,300,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955_----------      ----------------------------- 10,406,156
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project----------------        ------         4,731,000

       10. CALAVERAS RIVER AND LITTLEJOHN CREEK AND
        TRIBUTARIES, INCLUDING HOGAN AND FARMINGTON
                       RESERVOIRS, CALIF.
   Location. The streams comprising the Calaveras River and
Littlejohn Creek groups rise in the Sierra Nevada and its foothills,
flow westerly across the flat lands of San Joaquin Valley and empty
into the San Joaquin River directly, or through various sloughs,
in the vicinity of Stockton, Calif. The Littlejohn Creek group
drains 487 square miles, of which 184 square miles are below the
base of the foothills; the watershed is located in Calaveras, Stan-
islaus, and San Joaquin Counties. The three principal stream
systems of the group are, from south to north, Lone Tree Creek,
Littlejohn Creek, and Duck Creek. This group is bounded on the
south by Stanislaus River watershed, and on the north by the
Calaveras River group. The Calaveras River group drains 173
square miles below the base of the foothills and 560 square miles
above. It is located in Calaveras and San Joaquin Counties, and
is bounded on the south by Littlejohn Creek group watershed, and
on the north by Mokelumne River watershed. The two principal
streams of the group are, from south to north, Calaveras River
and Bear Creek. The valley lands are essentially a delta area in
which the streams of both groups are more or less inter-connected
by creeks and swales. (See U. S. Geological Survey Valley Springs
quadrangle for Hogan Reservoir area and Trigo and Bachelor
Valley quadrangles for Farmington Reservoir area.)
1378     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

    Existing project. This provides for-
    a. Construction of Farmington Dam and Reservoir, with a gross
storage capacity of 52,000 acre-feet, construction of a diversion
channel from Duck Creek to Littlejohn Creek and of two dikes
across downstream channels leading from Duck Creek to Mormon
slough, and enlargement of downstream Littlejohn Creek channels
for the exclusive purpose of flood control. The reservoir is formed
by an earthfill dam with a maximum height of about 58 feet and a
length of about 7,800 feet; it is located on Littlejohn Creek 31/2
miles upstream from Farmington and about 18 miles easterly of
Stockton, Calif. The outlet works are located in the right abut-
ment and consist of two rectangular concrete conduits, each 6 feet
by 9 feet, controlled by slide gates, and a stilling basin. A concrete
broad-crested weir approximately 95 feet long, located in the right
abutment, serves as the spillway. Construction of the main dam
and spillway was completed in June 1951. The Duck Creek diver-
sion, located approximately 1 mile east of Farmington, comprises
an earth dike across Duck Creek with two pipe outlets, an overflow
concrete weir adjacent thereto, and a diversion channel approxi-
mately 5,000 feet long with a capacity of 2,000 cubic feet per sec-
ond to Littlejohn Creek. The two dikes across the downstream
channels are of earthfill construction and are located approxi-
mately 3 and 8 miles, respectively, west of Farmington. Duck
Creek channel improvements were completed in November 1951.
Enlargement of downstream Littlejohn Creek channels will con-
sist of clearing, channel excavation, and minor levee construction
west of Farmington to French Camp. These improvements will
provide flood protection for about 58,000 acres of agricultural
land, suburban areas, and industrial sites in the area immediately
southeast of Stockton.
    The latest approved estimate of Federal cost for new work
 (1954) is $3,729,000, of which $672,000 is for lands and damages
and $3,057,000 for construction.
    The latest estimate (1954) of the cost to local interests for
rights-of-way and relocations on the Duck Creek and downstream
Littlejohn Creek improvements, required by the authorization, is
$366,000.
    Maintenance and operation of the dam, reservoir and appur-
tenant gages are the responsibility of the Federal Government;
the latest (1953) approved estimate for annual Federal cost of
this maintenance and operation is $12,800. Maintenance and op-
eration of the channel improvements after completion are the
responsibility of local interests.
    b. Construction of New Hogan Reservoir, comprising an earth-
fill dam with a height of about 215 feet, together with three dikes
with a maximum height of 20 feet, and a side-channel ungated
spillway, to create a reservoir with a gross storage capacity of
325,000 acre-feet for flood control, irrigation and other water con-
servation purposes. The improvement will be located on the
Calaveras River, about 28 miles northeast of Stockton, Calif., at
           FLOOD CONTROL-SACRAMENTO, CALIF., DISTRICT             1379
or below the site of the present small Hogan Dam, which is owned
and operated by the City of Stockton for the partial flood protec-
tion of that city. The project will provide flood protection for
46,000 acres of agricultural lands in the Calaveras River area and
to the city of Stockton and suburban areas and, in addition, will
provide 62,000 acre-feet of new water annually for irrigation re-
quired for the continued agricultural growth of the area and to
provide a potential municipal water source for Stockton and its
industries.
    The latest approved estimate of Federal cost for new work
  (1954) is $15,800,000, of which $142,700 is for lands and damages
and $15,657,300 for construction.
    Operation and maintenance of the project will be the responsi-
bility of the Federal Government; the latest (1948) approved
estimate for annual Federal cost of this maintenance and operation
is $85,500. Local interests will reimburse the United States for
the conservation accomplishments of the project.
    c. Construction will consist of about 42 miles of levee, enlarge-
ment of about 16 miles of existing channel, and excavation of about
1 mile of new channel along Bear Creek, San Joaquin County,
Calif., for flood control purposes. The levee and channel improve-
ments will extend along the south channel of Bear Creek from
Jacktone Road, about 2 miles south of Lockeford, to Disappoint-
ment Slough, a delta channel which connects with San Joaquin
River. This construction will provide a channel of 4,000 cubic
feet per second capacity with 3 feet of levee freeboard. The im-
provement will provide flood protection to about 19,000 acres of
intensively developed agricultural croplands in the vicinity of Lodi
and Stockton.
    The latest approved estimate of Federal cost for new work
  (1954) is $705,000, for construction.
    The latest estimate (1954) of the cost to local interests for lands,
damages, and bridge and utility relocations is $573,000.
    Maintenance and operation of the levee and channel improve-
ments after completion are the responsibility of local interests.
    The existing project was adopted by the Flood Control Act of
December 22, 1944. (See H. Doc. 545, 78th Cong., 2d sess., which
contains the latest published map.)
    Recommended modifications of project. In House Document
No. 367, 81st Congress, 1st session, a plan of improvement was
recommended which would provide for construction of a levee on
the right bank, of the Stockton diverting canal and incidental
channel improvement, such work to extend from its source at
Mormon Slough to its confluence with the lower Calaveras River.
The recommended work would supplement the authorized Hogan
Reservoir, and would control Calaveras River floods by confining
regulated flows to leveed channels. The estimate of Federal cost
for new work (1948) is $52,000.
    Local cooperation. None is required for construction of Farm-
ington Dam and Reservoir. Payment for conservation storage in
1380     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Hogan Reservoir, when used, is to be made to the United States
by the State of California or other responsible agency. .Arrange-
ments for such repayment have not been undertaken as yet. The
State of California has officially adopted the project by chapter
1514 of the Statutes of 1945, State of California, approved July
19, 1945. The State of California or other responsible local
agencies must give assurances satisfactory to the Secretary of the
Army that for the Duck Creek diversion structures and dikes, the
enlarged downstream Littlejohn Creek channels, and Bear Creek
channel and levee improvements they will (1) provide without
cost to the United States all lands, easements, and rights-of-way
necessary for construction of the works; (2) make all necessary
bridge and utility alterations; (3) hold and save the United States
free from damages due to the construction works; and (4) main-
tain and operate all works after completion in accordance with
regulations prescribed by the Secretary of the Army. Chapter
1514, Statutes of State of California, 1945, approved by the Gov-
ernor of that State on July 19, 1945, provided for the furnishing
of the assurances for the Duck Creek diversion structures and
dikes and the Bear Creek levee and channel improvements. Senate
bill No. 26, signed by the Governor of California on April 16, 1952,
modified the 1945 Statutes of the State of California to authorize
furnishing of assurances for the enlargement of the channels of
Littlejohn Creek below Farmington Dam.
    Assurances have not been requested from local interests for the
IBear Creek channel and levee improvements pending completion
of project plans.
    Assurances were furnished and all requirements have been
complied with for the Duck Creek diversion structures and dikes.
Duck Creek diversion structures and dikes were transferred to
the State of California for maintenance by Sacramento District
letter dated June 19, 1952. This construction was accepted by the
State of California by letter dated July 3, 1952.
    Assurances for the enlargement of the downstream Littlejohn
Creek channels have been furnished; all rights-of-way have been
procured by local interests; and funds in the amount of $100,000
have been contributed by the State of California to provide pay-
ment for the required utility alterations. Acceptance of these con-
tributed funds was approved by the Secretary of Army on April
28, 1954.
    Operations and results during fiscal year. New work :
    a. Farmington Reservoir: Engineering and design, including
preparation of plans and specifications was continued and prepara-
tion of the operation and maintenance manual was completed, by
hired labor. Completion of the construction of slope protection,
relief wells, and upstream connecting channel was accomplished by
contract. A contract was awarded for channel improvement and
clearing of south Littlejohn Creek, from Farmington to French
Camp; this work will be accomplished in fiscal year 1955. The
cost of new work for Farmington Reservoir during the fiscal year
was $259,602 from United States funds and $17,827 from contrib-
uted funds, a total of $277,429.
                   FLOOD CONTROL-SACRAMENTO, CALIF., DISTRICT                                 1381
   b. Hogan Reservoir: There were no operations and no costs
were incurred.
   c. Bear Creek channel improvements: There were no operations
and no costs were incurred.
   Maintenance: Farmington Reservoir: Maintenance and opera-
tion of the dam and outlet works and service facilities was accom-
plished during the year by hired labor. In addition, periodic gage
readings and other operational functions, including repairs to
gages, were also accomplished by hired labor.
   Farmington Reservoir and the Duck Creek channel improve-
ments were operated for flood control during the 1953-1954 flood
season, by the Federal government and local interests respectively.
Only minor flood flows occurred, and no appreciable amount of
floodwater was stored in the reservoir. Total cost of maintenance
during the fiscal year was $7,480 from Federal funds.
   The costs and expenditures for the entire project during the
fiscal year were as follows:
                              Funds                        New work        Maintenance     Total
                                                             costs            costs        costs

United States funds ..  ....   _____________                   $259, 602         $7, 480     $267, 082
Contributed
       T-I_- funds (nonproject) ...................   .i         17, 827                       17, 827
       Total                                               1    277, 429          7, 480      284, 909



   Condition at end of fiscal year.
   a. Farmington Reservoir: Construction of Farmington project
was initiated in July 1949 and is about 88 percent complete. The
project construction was completed for beneficial flood control
operation in calendar year 1952. Construction is substantially
completed and all functional parts of the reservoir and the Duck
Creek channel improvements are in operation and acting to provide
the flood protection for which they were designed. Engineering
and design is substantially completed except for preparation of
plans and specifications for a stream gaging and rating station on
Duck Creek above the diversion. Acquisition of real estate lands
and/or flowage easements has been completed except for legal
proceedings. The following major features have been completed:
Construction of outlet works, including installation of slide gates
and appurtenances; main dam and spillway in June 1951; Duck
Creek channel improvement in November 1951; relocations of
necessary roads and utilities; construction of Littlejohn Creek
gaging station; installation of local and net wire transmission for
stream gaging station; removal of floatable debris from the reser-
voir area; and construction of embankment slope protection, relief
wells, and upstream connecting channel between Littlejohn Creek
and Rock Creek.
   The work remaining to complete construction of Farmington
project includes channel improvement and clearing of south Little-
john Creek, from Farmington to French Camp and the installation
of a stream gage and rating station on Duck Creek above the di-
version structures; this will be completed in fiscal year 1955.
   Total cost of new work for Farmington project to June 30, 1954,
1382           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

was $3,300,481, of which $3,275,897 was from United States funds
and $24,584 from contributed funds.
   Total cost of maintenance for Federal operation and mainte-
nance of the Farmington Reservoir and appurtenant gages was
$11,346 from United States funds between July 1952 and June 30,
1954.
   b. Hogan Reservoir: Preliminary definite design studies have
been prepared for selection of reservoir capacity and a survey and
preliminary geological investigations of the dam site have been
made. Design memoranda are about 30 percent complete; plans
and specifications are about 10 percent complete. Construction
has not been initiated. Total cost of new work for Hogan Reser-
voir to June 30, 1954, was $122,180 from Federal funds.
   c. Bear Creek channel improvements: Engineering studies are
about 25 percent complete; construction has not been initiated.
Further studies are delayed until agreement is reached with local
interests regarding the plan of improvement. Total cost of new
work for Bear Creek channel improvement to June 30, 1954, was
$17,057.
   Total costs for the entire project to June 30, 1954, were as
follows:

                        Funds                              New work            Maintenance             Total
                                                             costs                costs                costs

United States funds_-------------------------------           $3, 415, 133             $11, 346         $3, 426, 479
Contributed funds (nonproject) ..................
                               ------------------------            24, 584   ----------------                24, 584

     Total     --------------------------------------
                 _                                             3, 439,717               11,346                063
                                                                                                         3,451,



                                    Cost and financial summary
                                    UNITED STATES FUNDS


                                           Fiscal year ending June 30                              Total to June
                                                                                                  30, 1954, includ-
                                                                                                  ing fiscal years
                             1950        1951          1952             1953           1954         priorto 1954


New work:
   Appropriated   ... ._ $1,750,000 $1,420,000         $181,180 -   -              -   -$2, 943        $3,868,237
   Cost_--                  503,871  1,533,888          473,275         $277,120        259,602         3,415,133
Maintenance:
   Appropriated- .-....                                                   8, 000         3, 400             11,400
   Cost - -------------                          ---
                                                  .                       3,866          7,480              11,346


Other new work data:
     Unobligated balance, fiscal year ending June 30, 1954_                                           $148,375
     Unobligated balances available for succeeding fiscal year ending
       June 30, 1955_____ _____      __       ___________ __________                                    148,375
     Estimated additional amount needed to be appropriated for com-
       pletion of existing project _____________________ _____________ $16,365,763
                FLOOD CONTROL--SACRAMENTO,                           CALIF., DISTRICT                1383
                                       Cost and financial summary
                                        CONTRIBUTED FUNDS 1

                                                Fiscal year ending June 30                   Total to June
                                                                                             30, 1954, includ-
                                                                                             ing fiscal years
                                1950         1951         1952         1953       1954         priorto 1954


New work:
   Appropriated......-----------------------------         $7,000       2-$243   $100,000            $106,757
   Cost -------------------------------------               6, 750           7     17, 827             24,584


  1 Contributed funds for miscellaneous construction (nonproject) at expense of local interests in connec-
tion with acquisition of rights-of-way and utility alterations.
   2 Refund of trust funds.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_ ___-  -$18,019
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955     -------------------------------------------------                                    18,019

11. LOWER SAN JOAQUIN RIVER AND TRIBUTARIES, INCLUDING
        TUOLUMNE AND STANISLAUS RIVERS, CALIF.

   Location. The San Joaquin River has its sources in the Sierra
Nevada, and flows generally southwest through the mountains and
foothills to the vicinity of Friant, where it enters the flat alluvial
valley through which it flows west 60 miles to Mendota midway of
the valley floor. At Mendota the river turns northwest and flows
157 miles to Mossdale at the head of the San Joaquin Delta, an
extensive area of reclaimed tidal swamplands through which the
river flows with numerous side channels and sloughs to join the
Sacramento River at the head of Suisun Bay near Pittsburg. The
river drains an area of 17,000 square miles. The Tuolumne and
Stanislaus Rivers, two of the principal tributaries of the San
Joaquin River, likewise have their sources in the Sierra Nevada,
and flow in a generally westerly direction through the mountains
and foothills to enter the alluvial valley and join the main river
from the east in its lower reaches. Stockton, at the head of the
delta, and Fresno, just south of the San Joaquin watershed, are the
principal commercial and distributing centers serving the area un-
der consideration. (See U. S. Geological Survey quadrangles of
the area.) The lower San Joaquin River is under improvement for
navigation, the existing project providing for a 30-foot ship chan-
nel to Stockton and various minor improvements for the benefits of
light-draft navigation in the delta channels.
   Existing project. This improvement provides for-
   a. Construction of New Melones Dam and Reservoir, a 482 foot
high concrete gravity dam on the Stanislaus River, about 14 miles
above the town of Knights Ferry, Calif., to create a 1,100,000 acre-
foot reservoir for flood control, irrigation, and other water con-
servation purposes. The project will provide flood protection to
about 25,000 acres of agricultural land along the Stanislaus River
and is an integral unit of the authorized plan for flood control in
the San Joaquin River Basin. In addition, the project will make
possible the construction of a large hydroelectric plant below the
dam to supply the urgent demands of a power-deficient area. Con-
struction of the power plant has not been authorized.
1384     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   The latest approved estimate of Federal cost for new work
 (1954) is $53,200,000, of which $4,183,400 is for lands and dam-
ages and $49,016,600 for construction.
   Maintenance and operation of the dam and reservoir are the re-
sponsibility of the Federal Government; the latest (1948) approved
estimate for annual Federal cost of this maintenance and opera-
tion is $165,000. Local interests will reimburse the United States
for the conservation accomplishments of the project.
   b. An expenditure toward the first cost of Cherry Valley Reser-
voir and the New Don Pedro Reservoir in the Tuolumne River
Basin. Federal interest in the development is in the flood protec-
tion to be afforded by reservoirs constructed by local interests,
comprising the City and County of San Francisco and the Turlock
and Modesto Irrigation Districts; the Federal Government will
contribute toward the first cost of the construction an amount
commensurate with the flood control benefits to be derived. Ulti-
mately the flood protection will be derived from the operation for
flood control of at least 340,000 acre-feet of storage in the New Don
Pedro Reservoir, proposed for a total capacity in the order of 1,-
200,000 acre-feet. First phase of the development by local inter-
ests is the construction for municipal water supply, power genera-
tion, and other purposes of the Cherry Valley Reservoir, in the
upper Tuolumne River watershed, about 25 miles east of the town
of Sonora, Calif. The dam is a composite earth and rock embank-
ment 315 feet high and about 2,500 feet long, which will create a
reservoir with a capacity of 268,000 acre-feet below the spillway
crest. The local interests will operate this reservoir and the exist-
ing Hetch Hetchy and Don Pedro Reservoirs for flood control until
such time as the New Don Pedro Reservoir is constructed and
placed in operation. This improvement is an integral unit of the
authorized plan for flood control in the San Joaquin River Basin;
operation of the Tuolumne River Reservoirs will provide flood pro-
tection to about 8,000 acres of agricultural lands and several com-
munities along the Tuolumne River.
   The latest approved estimate (1954) of the Federal contribution
toward the first cost of the Cherry Valley Reservoir is $9,270,000,
including $270,000 incidental Federal costs, in return for that por-
tion of the ultimate contribution justified by the degree of flood
protection provided. The latest approved estimate (1954) of the
total Federal contribution toward the first cost of the Tuolumne
River Reservoirs is $12,000,000.
   The latest estimate (1954) of the costs to local interests are
$4,320,000 for Cherry Valley Reservoir and $67,000,000 for New
Don Pedro Reservoir, a total of $71,320,000.
   c. Construction of levee and channel improvements on the lower
San Joaquin River and tributaries consisting of the improvement
of the existing levee system along the river below the mouth of
the Merced River by raising and strengthening the existing levees;
for construction of new levees; for revetment of banks where re-
quired; for channel improvements; and for the acquisition of flow-
age rights on natural overflow lands generally downstream of
Skaggs Bridge and upstream of the Merced River where necessary
          FLOOD CONTROL--SACRAMENTO, CALIF., DISTRICT             1385
to insure continued effectiveness of channel storage. The flowage
rights are to be provided by the State of California or other respon-
sible local agency.
   This project is an integral unit of the authorized plan for flood
control and other purposes in the San Joaquin River Basin; it is
designed to supplement the reservoir units of the overall plan,
involving flood-control storage on the Tuolumne and Stanislaus
Rivers and in the existing Friant Reservoir on the upper San
Joaquin River, by providing channel capacities along the San
Joaquin River sufficient to safely pass regulated flows. The levee
and channel improvement project, together with the reservoir
units, will provide urgently needed flood protection to a rich agri-
cultural area of approximately 140,000 acres, to numerous com-
mercial and public installations, and to a suburban area adjacent to
the City of Stockton.
   The latest approved estimate of Federal cost for new work
 (1954) is $9,700,000, for construction.
   Maintenance and operation of the levee and channel improve-
ments after completion are the responsibility of local interests.
   The latest estimate (1953) of the costs to local interests are $1,-
790,000 for rights-of-way and natural valley storage flowage rights
or suitable facilities.
   The existing project was adopted by the Flood Control Act of
December 22, 1944, which authorized to be appropriated for the
initiation and partial accomplishment of the project the sum of
$8,000,000.    (See H. R. Flood Control Committee Doc. 2, 78th
Cong., 2d sess., which contains the latest published map.) Further
monetary authorization of $2,500,000 was provided for this project
by Public Law 235, 83d Congress, 1st sess., making a total mone-
tary authorization of $10,500,000 available.
   Recommended modificationsof project. In House Document No.
367, 81st Congress, 1st session, it was recommended that power-
generating facilities, not now included in the authorized project,
be constructed concurrently with and as part of New Melones Dam.
For an initial installation of 41,000 kilowatts, the first cost is esti-
mated (May 1948) at $4,727,000, and the annual cost of mainte-
nance and operation at $194,400.
   Local cooperation. a. New Melones Reservoir (Stanislaus
River) : The State of California or other responsible agency will be
required to pay for the conservation storage when used. Such pay-
ment will be based upon future cost allocation studies by the De-
partment of the Army. The State of California has officially
adopted the project by chapter 1514, Statutes of State of Cali-
fornia, 1945, approved by the Governor of that State, July 19,
1945.
   b. In Tuolumne Basin: Local interests are to construct, main-
tain, and operate the dams and reservoirs, allocate storage for flood
control, and agree to operate such storage in accordance with rules
and regulations prescribed by the Secretary of the Army. Local
interests have agreed by means of a negotiated contract to con-
struct, maintain, and operate in the interest of flood control, the
Cherry Valley Reservoir, as well as allocate flood control storage
space in their existing facilities until such time as the New Don
 1386                  REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Pedro Dam and Reservoir is constructed by local interests and flood
control storage is provided therein. Local interests have been
operating their existing reservoirs for flood control since Decem-
ber 1949 in accordance with applicable regulations and the above
cited contract.
     c. San Joaquin River: The State of California or other respon-
sible local agencies are to give assurances satisfactory to the Sec-
retary of the Army that they will: (1) furnish flowage rights to
overflow certain lands along the main San Joaquin River, and all
lands, easements, and rights-of-way necessary for construction of
levees; (2) hold and save the United States free from damages due
to the construction works in the San Joaquin River and tributary
channels, and their subsequent maintenance and operation; and
  (3) maintain all levees and channel improvements after completion
in accordance with regulations prescribed by the Secretary of the
Army. Chapter 1514, Statutes of State of California, 1945, ap-
proved by the Governor of that State on July 19, 1945, provides for
furnishing the requirements for the levee and channel improve-
ment work. These assurances will be furnished when required.
    Operations and results during fiscal year. New work:
    a. New Melones Reservoir (Stanislaus River) : There were no
operations and no costs were incurred.
    b. Cherry Valley Reservoir, Tuolumne River Basin: Prepara-
tion of the reservoir regulation manual covering flood control
operations under phase II of the project (to correlate operation of
Cherry Valley Reservoir with the continued operation of existing
facilities) was initiated; these regulations have been agreed upon
by the contractors and the Federal Government. The contractors,
the City and County of San Francisco, and the Turlock and Modesto
Irrigation Districts, operated their existing Don Pedro Reservoir
facilities for flood control (phase I of the project) during the year
in accordance with requirements of the contract.
    Construction of Cherry Valley Reservoir was continued by the
contractors; about 21 percent of the work was accomplished dur-
ing the fiscal year.
    c. Construction of levee and channel improvement works on
lower San Joaquin River and tributaries: Engineering and design
studies, including preparation of general design memorandum and
drawings, were continued during the year. These studies included
review of the economics of New Melones Reservoir and the rela-
tionship of the reservoir to the design of the levees and channel
improvements in lower San Joaquin River.
    The total cost for the entire project during the fiscal year for
new work was as follows:
                                               Project                                                Cost

New Melones Reservoir, Stanislaus River....------------------------------------------
Tuolumne River Basin Reservoirs, including Cherry Valley Reservoir --- - - -               --._.       $226, 781
                                        .........--------------------------------------.........--
Lower San Joaquin River and tributaries---                                                               27, 312
      Total-........----..---   ------------------------------------------------------------            254, 093


    Condition at end of fiscal year. New work:
    a. New Melones Reservoir, Stanislaus River:                                                  Engineering
                  FLOOD CONTROL-SACRAMENTO, CALIF., DISTRICT                                                 1387
accomplished consists of collection of data for design memoranda
including topographic surveys and hydrologic data, consideration
of its interrelationship with other units in the comprehensive plan,
revision of project costs and benefits, and the preparation of pre-
liminary plans. Design memoranda are about 5 percent complete.
Total cost for New Melones Reservoir to June 30, 1954, is $70,156.
    b. Cherry Valley Reservoir, Tuolumne River Basin: Engineer-
ing and design studies including preparation of flood control opera-
tion criteria, review and approval of plans prepared by the con-
tractor, and design analyses, have been accomplished.
    A contract was awarded in fiscal year 1950 to local interests, the
City and County of San Francisco and the Turlock and Modesto
Irrigation Districts, for modification of existing facilities as neces-
sary at Don Pedro, Hetch Hetchy, and Lake Eleanor Reservoirs
and for the operation of these facilities in accordance with regula-
tions of the Secretary of the Army to obtain immediately a degree
of control over Tuolumne River floods. The contractors have been
operating the existing reservoir facilities for flood control (phase
1 of the project) since December 1949, in accordance with the ap-
plicable regulations.
    Construction of Cherry Valley Reservoir (phase II) was initiated
in September 1950; this construction is about 35 percent complete
and is scheduled for completion by June 30, 1956. Construction of
New Don Pedro Reservoir (phase III) remains to be accomplished;
and is scheduled for completion in 1964.
    The initial Federal contribution was made in 1950 and total costs
for Cherry Valley Reservoir to June 30, 1954, were $7,419,001, con-
sisting of $7,126,920 as direct payments to local interests and
$292,081 for incidental Federal costs.
    c. Construction of levee and channel improvement works on
lower San Joaquin River and tributaries: Data for the definite de-
sign studies have been assembled, including studies of existing
channel capacities, topographic surveys, reconnaissance of existing
levees, derivation of project design flood plane, determination of
potential benefits, and general design of plan of improvement; de-
sign memoranda are about 95 percent complete and plans and
specifications are about 20 percent complete. Cooperative studies
with the State of California have been made to determine plans for
preservation of natural valley storage above Merced River. Con-
struction has not been initiated under this improvement. Total
cost for lower San Joaquin River and tributaries to June 30, 1954,
is $355,765.
   The total costs for the entire project to June 30, 1954 for new
work were as follows:

                                             Project                                                      Cost

                                                                  ---------- ------------------........
New Melones Reservoir, Stanislaus River ..--...............--------------                                    $70, 156
Tuolumne River Basin Reservoirs, including Cherry Valley Reservoir ------------------                     7, 419, 001
Lower San Joaquin River and tributaries...-------------------------------------------                        355, 765
      Total............------------------------------------------------------------------------           7, 844, 922


  1 Includes $7,000 advance toward establishment of South Pacific Division laboratory.
1388         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                    Cost and financial summary

                                             Fiscal year ending June 30                           Total to June
                                                                                                 30, 1954, includ-
                                                                                                 ing fiscal years
                             1950           1951         1952           1953             1954     prior to 1954


New work:
   Appropriated.--------    $539, 900   $   728,000   $3, 394,345    $2,274,000    $205, 000          $7, 896,245
   Cost----------------      165, 815    1,516, 725    3, 592, 309    2,189, 700    254, 093          17, 844,922

1 Includes amount of $7,000 advance for establishment of South Pacific Division Laboratory.


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_-                                           $7,384
    Appropriated for succeeding fiscal year ending June 30, 1955                           - -    $1,040,000
     Unobligated balances available for succeeding fiscal year ending
       June 30, 1955 __--                                                                         $-----$1,047,384
     Estimated additional amount needed to be appropriated for com-
       pletion of existing project                                      -          ---           $65,963,755


              12. MERCED COUNTY                       STREAM GROUP, CALIF.

    Location. The streams comprising the Merced County stream
group rise in the Sierra Nevada foothills of the Central Valley of
California and flow in a general westerly direction to join the San
Joaquin River west of the city of Merced. The streams form three
general groups; Bear Creek with its tributaries, Black Rascal,
Canal, Fahrens, and Burns Creeks; Mariposa Creek with its tribu-
taries, Miles and Owens Creeks; and Deadmans Creek with its
tributaries, Little Deadmans, Big Deadmans, and Dutchmans
Creek. The latter group crosses an area of pasture land and flood
control improvements are not provided for this group. The re-
mainder of the Merced County stream group drains an upper area
of 398 square miles, ranging from mountains to low foothills, and
a lower area of 312 square miles of broad alluvial valley. The flow
of the streams of the Merced County group is intermittent. (See
U. S. Geological Survey Haystack Mountain quadrangle for Burns
Reservoir area and Indian Gulch quadrangle for Bear, Owens, and
Mariposa Reservoirs areas.)
    Existing project. Improvement of Merced County Stream
Group is a unit in the comprehensive plan for flood control and
other purposes in the Sacramento-San Joaquin Basins. The proj-
ect provides for construction of four retarding-type reservoirs and
for channel improvements, in the vicinity of the city of Merced,
Calif., for the exclusive purpose of flood control.
    Mariposa Dam, completed in November 1948, comprises an earth-
fill main dam 1,330 feet long with a maximum height of about 88
feet and 2 auxiliary dikes aggregating 1,375 feet in length; the
reservoir has a gross storage capacity of 15,000 acre-feet; the out-
let consists of an ungated 5-foot 5-inch diameter reinforced con-
crete conduit located through the left abutment of the dam; and
the spillway is located in a saddle near the left abutment of the
main dam and consists of an ungated concrete gravity weir, with
a crest length of 260 feet, and trapezoidal approach and exit chan-
          FLOOD CONTROL--SACRAMENTO,       CALIF., DISTRICT      1389
nels. The dam is located on Mariposa Creek about 18 miles east of
Merced.
    Owens Dam, completed in October 1949, consists of an earthfill
main dam with a maximum height of 75 feet and a crest length of
790 feet and an auxiliary dike approximately 370 feet long in a
saddle near the left abutment; the gross storage capacity of the
reservoir is 3,600 acre-feet; the outlet is an ungated concrete en-
cased corrugated metal pipe 3 feet, 4 inches in diameter; the spill-
way is an ungated concrete broadcrested weir with a crest length
of 75 feet, located in a saddle near the left abutment of the aux-
iliary dike. Owens Dam is located on Owens Creek about 16 miles
east of Merced.
    Burns Dam, completed in January 1950, is an earthfill structure
with a maximum height of 55 feet and a crest length of 4,075 feet;
a low auxiliary dike about 290 feet long is located in a saddle near
the left abutment; the reservoir has a gross storage capacity of
7,000 acre-feet; the outlet works consist of an ungated double-
barrel conduit, each barrel being 4 feet, 9 inches by 6 feet; the
spillway is located near the right abutment, consisting of an un-
gated concrete weir 40 feet long with an exit channel and a jump
basin. Burns Dam is located on Burns Creek about 13 miles north-
east of Merced.
    Bear Dam, construction initiated in April 1954, a 92-foot high
earthfill structure with ungated saddle spillway and an auxiliary
dike, will provide a reservoir capacity of 7,700 acre-feet and will be
located on Bear Creek about 15 miles northeast of Merced.
    Diversion of flow from Black Rascal Creek to Bear Creek will be
accomplished by means of a 3,000 second-foot capacity canal with
a length of 1.3 miles, and diversion of flow from Owens Creek to
Mariposa Creek, by means of a 400 second-foot capacity canal with
a length of 1.6 miles. These improvements will be located east of
Merced 4 and 11 miles, respectively.
    In addition, channel enlargement of a constricted portion of
Miles Creek and restoration of impaired channel capacities of Black
Rascal, Burns, Bear, Owens, and Mariposa Creeks is to be accom-
plished by responsible local interests at their expense.
    The project will provide flood protection to about 136,000 acres
of agricultural lands, to the city of Merced, to the towns of Planada
and Le Grand and other smaller communities, and to highway and
transportation facilities.
    The latest approved estimate of Federal cost for new work
 (1954) is $2,874,000, for construction.
    The estimated (1954) cost to local interests for new work is
$1,078,000, comprising the provision of lands, easements, and
rights-of-way necessary for construction; highway and utility
modifications; and provision of channel enlargement and restora-
tion of impaired channel capacities.
    Operation and maintenance of the project and of the existing
channel improvements after completion will be the responsibility
of local interests. Operation and maintenance of the reservoirs and
appurtenant gaging facilities is the responsibility of the Federal
Government; the latest (1953) approved estimate for annual Fed-
eral cost of this operation and maintenance is $15,000.
1390     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   The existing project was adopted by the Flood Control Act of
December 22, 1944. (See H. Doc. 473, 78th Cong., 2d sess., which
contains the latest published map.)
   Local cooperation. Construction of the project is subject to the
conditions that the State of California or other responsible local
agencies give assurances satisfactory to the Secretary of the Army
that they will (1) provide without cost to the United States all
land, easements and rights-of-way necessary for the construction;
 (2) bear the expense of all necessary highway and utility changes;
 (3) complete the enlargement of the channel of Miles Creek and
restore the channel capacities of Black Rascal, Burns, Bear, Owens,
and Mariposa Creeks in accordance with the plan of the district
engineer; (4) hold and save the United States free from damages
resulting from construction of the works; and (5) except for the
reservoirs, dams, and appurtenant gages, maintain and operate the
completed project works and existing channel in accordance with
regulations prescribed by the Secretary of the Army. Chapter
1514, Statues of State of California, 1945, approved by the Gover-
nor of that State on July 19, 1945, provides for the furnishing of
the required assurances which were furnished and accepted by the
Secretary of the Army on January 22, 1948.
   All lands, easements, and rights-of-way have been furnished
without cost to the United States for the four reservoirs and the
additional lands and rights-of-way needed for the project will be
furnished by the State of California as required, in accordance with
the above assurances.
   The State of California has been requested to provide the en-
largement and restore the channel capacities of the creeks enu-
merated in (3) above. State Senate bill No. 1659, chapter 1118,
Statutes of State of California of 1953, authorized the State to
provide the enlargement and restore the channel capacities of these
creeks. The State of California Reclamation Board furnished a
copy of Senate bill No. 1659 to Sacramento District by letter dated
June 15, 1953. Enlargement and restoration of the above channel
capacities is now underway and will be completed in the near
future.
    Operations and results during fiscal year. New work: Engi-
neering and design, including preparation of contract plans and
specifications, was continued during the year for Bear Dam and
Reservoir and for the Owens Creek and Black Rascal Creek Diver-
sion Canals, by hired labor. Preparation of the operation and
maintenance manual for Bear Dam was underway by hired labor.
Construction of Bear Dam and appurtenances was initiated in
April 1954 by contract; 10 percent of the work was accomplished.
   Maintenance: Condition and operation studies, including peri-
odic gage reading and other operational functions, were accom-
plished throughout the fiscal year by hired labor. Preparation of
contract plans and specifications for repairs to the outlet works at
Mariposa Dam and to the access roads to Mariposa, Burns, and
Owens Dams was accomplished by hired labor; this maintenance
work was not initiated during the year and will be accomplished
in fiscal year 1955. Protective fencing at Owens and Burns Dams
                    FLOOD CONTROL--SACRAMENTO,                                        CALIF., DISTRICT                    1391
was completed by contract; 5 percent of this work was accom-
plished this fiscal year.
   The three completed reservoirs were in operation as units of the
project designed to protect the city of Merced and adjoining agri-
cultural areas during the fiscal year. Only minor flows occurred
and no appreciable amounts of floodwaters were stored.
   In addition, local interests have initiated the channel enlarge-
ment of Miles Creek and the restoration of channel capacities of
Black Rascal, Burns, Bear, Owens, and Mariposa Creeks at their
expense as a part of the requirements of local cooperation. These
improvements are about 20 percent complete.
   Total cost for the project during the fiscal year was $83,126, of
which $74,270 was for new work and $8,856 for maintenance, from
Federal funds.
  Condition at end of fiscal year. Construction under this im-
provement is about 65 percent complete and was initiated in March
1948 with the construction of Mariposa Dam and Reservoir, which
was completed in November 1948. Construction of Owens Dam and
Reservoir, initiated in March 1949, was completed in October
1949, and Burns Dam and Reservoir, initiated in July 1949, was
completed in January 1950. The Master Manual of Reservoir
Regulations for San Joaquin Basin, Calif., and Appendix III thereto
covering the Merced County stream group project, and the main-
tenance manuals for the Mariposa, Owens, and Burns Dams and
Reservoirs have been completed.
   Construction of Bear Dam and appurtenances is scheduled for
completion in calendar year 1954. Other work remaining to be
accomplished by the Federal Government consists of construction
of Owens Creek and Black Rascal Creek diversion canals and the
installation of gages and communication facilities for operating
purposes. The entire project is scheduled for completion in fiscal
year 1955.
   Total cost of new work for the project to June 30, 1954, was
$1,895,129, of which $1,870,759 was from United States funds and
$24,370 from contributed (nonproject) funds.
   In addition, local interests will complete the channel enlarge-
ment and restoration of channel capacities of Miles, Black Rascal,
Burns, Bear, Owens and Mariposa Creeks; 80 percent of this work
remains to be accomplished in fiscal year 1955 at their expense.
   Total cost of maintenance for Federal operation and mainte-
nance of the three completed reservoirs and appurtenances was
$24,370 from United States funds between July 1948 and June 30,
1954.
   Total costs for the project to June 30, 1954, were as follows:

                                   Funds                                          New work          Maintenance         Total
                                                                                    costs                costs          costs


United States funds-----------........... --------------------                     $1, 870, 759              $24, 370   $1, 895, 129
Contributed (nonproject) funds--...................------------------.....              37, 982 ----------------             37, 982

        Total--..            .....------------......---------------------------     1,908, 741               24, 370     1, 933, 111
1392           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                      Cost and financial summary

                                              Fiscal year ending June 30                      Total to June
                                                                                      _       30, 1954, includ-
                                                                                              ing fiscal years
                               1950          1951         1952         1953         1954       prior to 1954


New work:
    Appropriated --------     $175, 000     $60, 000    $265, 000    $199, 000    $300, 000       1$2, 554,000
    Cost ----------------      770, 249      19, 583      31,987       16, 247      74,270         11, 870, 759
Maintenance:
   Appropriated --------------------          4,000        10,000       6, 000      12, 000             35, 000
   Cost----------            1,880            2,587         2,804       7,706        8,856              24,370

   1In addition, $37,982 was expended from contributed funds for miscellaneous construction (nonproject)
accomplished at the expense of local interests in connection with acquisition of rights-of-way and relocation
of highways.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_-----------     $308,021
    Appropriated for succeeding fiscal year ending June 30, 1955-------    320,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955    ---------------------------------------------            628,021


      13. BIG DRY CREEK                   RESERVOIR              AND DIVERSION,                CALIF.

   Location. The streams comprising the Fresno County group
are Big Dry Creek, Dog Creek, Redbank Creek,and.Fancher Creek.
All of them rise in the Sierra Nevada, near the foothills, from 17
to 31 miles northeasterly from Fresno, Calif., and follow nearly
parallel courses in a southwesterly direction toward Clovis and
Fresno. Portions of the channels of these creeks, after entering
the valley floor, serve as part of large and complicated systems of
irrigation canals. The creeks eventually empty directly into the
San Joaquin River, or indirectly through Murphy Slough, at vari-
ous points northwesterly and southwesterly of Fresno, Calif. (See
U. S. Geological Survey Clovis and Friant quadrangles of the area.)
   Existing project. This improvement provides for construction
of an earthfill dam with a maximum height of 40 feet to create a
reservoir with a maximum storage capacity of 16,250 acre-feet, all
for flood control purposes, together with appurtenant diversion
facilities both upstream and downstream from the reservoir. The
improvement is located about 10 miles northeast of Fresno, and
about 4 miles northeast of Clovis, Calif. The Big Dry Creek Dam
was completed in 1948. The project controls the run-off from 86
square miles, and by diverting the flows of Dog and Big Dry Creeks
to Little Dry Creek, and subsequently to the San Joaquin River,
provides a high degree of flood protection to the cities of Fresno
and Clovis and their suburban areas.
   The latest approved estimate of cost for new work (1954) is
$1,372,000 for construction.
   The estimated (1954) cost to local interests for new work is
$300,000, comprising the provision of lands and damages and
road and utility revisions.
   Operation and maintenance of the project is the responsibility
of local interests.
          FLOOD CONTROL--SACRAMENTO,       CALIF., DISTRICT     1393
   The existing project was adopted by the Flood Control Act of
August 18, 1941. (See H. Doc. 845, 76th Cong., 3d sess., which
contains the latest published map.)
   Local cooperation. Local interests were required to give assur-
ances satisfactory to the Secretary of the Army that they would
provide without cost to the United States all lands, easements, and
rights-of-way necessary for the construction of the project; hold
and save the United States free from claims for damages due to
construction and maintenance of the project; bear the expense of
bridge construction; and maintain and operate all the works after
completion in accordance with regulations prescribed by the Secre-
tary of the Army. These requirements have been fully complied
with.
   The reservoir and diversion structures, completed in February
1948, were transferred to the State of California for maintenance
and operation by letter dated March 19, 1948, and accepted by the
State April 7, 1948. The State of California transferred responsi-
bility for the maintenance and operation of the completed works to
the county of Fresno in accordance with contract and agreement
dated August 6, 1946, between the State Reclamation Board and
the county of Fresno. The drop structures, completed in April
1953, were transferred to the State of California by letter dated
April 13, 1953, for operation and maintenance.
   Operations and results during fiscal year. Engineering was
continued; revision of the reservoir regulation manual to include
new construction was completed. Construction of side erosion con-
trol structures was accomplished by contract. These structures
were transferred to the State of California for operation and main-
tenance by letter dated October 13, 1953. In addition, seeding of
slopes, Big Dry Creek Reservoir, was accomplished by hired labor.
   Total cost of new work for the project during the year was
$24,296.
   Condition at end of fiscal year. Construction was initiated in
April 1947 and is 99 percent complete. The reservoir was com-
pleted in February 1948 and has subsequently been operating to
provide the flood protection for which it was designed. Construc-
tion of remedial work consisting of erosion control structures to
control side hill erosion was initiated in October 1952 and com-
pleted in September 1953.
   Big Dry Creek Reservoir and Diversion was operated for flood
control by local interests in accordance with regulations prescribed
by the Government. Only minor flows occurred and no appreciable
floodwater was stored. Permanent regulations were agreed upon
by the Federal Government and local interests, and will be pub-
lished in the Federal Register in the near future.
   Work remaining to complete the project consists of installation
of improved gaging facilities on the outlet channel; this installation
will be accomplished in fiscal year 1955.
   Total cost of new work for the project to June 30, 1954, was
$1,401,983, of which $1,357,975 was from United States funds and
$44,008 from contributed (nonproject) funds.
1394              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                             Cost and financial summary

                                                        Fiscal year ending June 30                   Total to June
                                                                                                     30, 1954, includ-
                                                                                                     ing fiscal years
                                      1950            1951         1952        1953       1954         priorto 1954


New work:
Appropriated.--.-.-----         $13, 876 ----------------------              $130, 000                    $1,372, 124
Cost-----------       ------------------------------------                     91, 555   $24, 296          1,357, 975


  1 In addition, $44,008 was expended from contributed funds for miscellaneous construction (nonproject)
accomplished at the expense of local interests in connection with bridge construction.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954--_                  $14,068
    Unobligated balances available for succeeding fiscal year ending June 30,
       1955    -------------------------------------------------               14,068

  14. KINGS RIVER AND TULARE LAKE, INCLUDING PINE FLAT
                     RESERVOIR, CALIF.
   Location. The area covered by this project comprises the upper
watershed of Kings River, its valley alluvial fan or delta, and the
lake bed known as Tulare Lake. The upper basin above the town
of Piedra is rugged and mountainous. Below Piedra the river
enters the relatively flat alluvial valley where the river divides,
one branch known as Fresno Slough flowing north to join the San
Joaquin River, and the second south to Tulare Lake, an area which
in its unreclaimed state varied from a completely dry condition to
a body of water some 750 square miles in extent. There is no
natural outlet from this lake as it is separated from the San Jo-
aquin Basin by a low ridge, but lake waters have escaped over this
ridge at least once since settlement of the region. Tulare Lake also
receives floodwaters of Tule, Kaweah, and Kern Rivers in some
years. The area below Piedra, including Tulare Lake, is known as
the Kings River service area. (See U. S. Geological Survey quad-
rangles of the area.)
   Existing project. The improvement is a unit in the compre-
hensive plan for flood control and other related purposes for the
Sacramento-San Joaquin Basins. The project provides for con-
struction of a 440-foot high concrete gravity dam, including a gated
overflow section with a maximum discharge capacity of 391,000
cubic feet per second, to create a reservoir with a gross storage
capacity of 1,000,000 acre-feet, for flood control, irrigation, and re-
lated purposes. Outlet provisions for future power development
are included in the dam, but Federal construction of power gen-
erating facilities is not authorized. The dam is located on Kings
River, about 25 miles east of the city of Fresno, Calif., and about 4
miles upstream from the town of Piedra; construction of the dam
was completed in June 1954. The improvement also includes a
limited amount of channel improvements on Kings River and its
distributaries on the valley floor about 25 miles south of Fresno.
The channel improvement work will enlarge channel capacities and
regulate flows in the lower branches of the Kings River.
   The improvement will provide flood protection for about 80,000
acres of rich agricultural lands in the Kings River area and, in con-
junction with the authorized projects on Kaweah, Kern, and Tule
          FLOOD CONTROL-SACRAMENTO, CALIF., DISTRICT             1395
Rivers, will provide protection against floods to 260,000 acres of
rich croplands in the Tulare Lake area. In addition, the project
will improve the irrigation water supply with an average of 165,000
acre-feet of new water annually by retention of flood flows, and
will provide a means of regulating the normal supply. The im-
provement to irrigation will benefit 460,000 acres in the Kings
River service area and 260,000 acres in the Tulare Lake area.
    The latest approved estimate of Federal cost for new work
 (1954) is $40,900,000, of which $650,100 is for lands and damages
and $40,249,900 for construction.
    Operation and maintenance of the dam and reservoir is the re-
sponsibility of the Federal Government; the latest (1953) approved
estimate for annual Federal cost of this operation and maintenance
is $112,000. Local interests will reimburse the United States for
the conservation accomplishments of the project.
    The existing project was adopted by the Flood Control Act of
December 22, 1944. (See H. Doc. 630, 76th Cong., 3d sess., which
contains the latest published map.)
    Recommended modifications of project. In House Document
No. 367, 81st Congress, 1st session, it was recommended that a
power installation be authorized for construction at such time as
it may be economically feasible. For an initial installation of
45,000 kilowatts, the first cost is estimated (May 1948) at $5,500,-
000, and the annual cost for maintenance and operation at $224,000.
    Local cooperation. The allocation to local interests for repay-
ment for use of conservation storage when used, has been estab-
lished in accordance with War Department Civil Appropriation Act,
1947, and published in House Document 136, 80th Congress, 1st
session. The exact amount is to be agreed upon between the Bu-
reau of Reclamation of the Department of the Interior and the
local agencies concerned. Negotiations with local interests are now
under way. The State of California has officially adopted the proj-
ect by chapter 1514 of the Statutes of 1945, State of California,
approved July 19, 1945.
    Operations and results during fiscal year. New work: Engi-
neering and design, including preparation of contract plans and
specifications, and preparation of the operation and maintenance
manual, by hired labor, was continued during the fiscal year. In
addition, hired labor was utilized to accomplish installation of
gaging stations, operation and maintenance of construction faci-
lities, purchase and installation of an electric tape gage, installa-
tion of hydrological telemetering facilities on Kings River, and
channel clearing and installation of a gaging station below the
dam. Land acquisition was completed except for legal proceed-
ings. Construction of Pine Flat Dam was completed; services
of the erection engineers were utilized for final testing of installed
  equipment consisting of sluice gates under continuing supply
  contract and tainter gates and elevator under supply contracts.
  Completion of continuing contracts was accomplished as follows:
River Road relocation and Sycamore Creek Gaging Station, near
Trimmer, Calif., 1 percent accomplished this year; and drilling
and grouting of the dam foundation, Pine Flat Dam, 25 percent
  accomplished this year. Maintenance of Sycamore Creek and
 1396     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

River Roads was completed this year with 91 percent of the work
placed under contract; 26 percent of the contract work was ac-
complished to complete a stream gage and rating station; and a
water supply system was constructed for Pine Flat project by
contract during the year. Further work was initiated by contract
during the fiscal year as follows: Construction of hydrologic tele-
metering system, Kings River, 5 percent placed this year; paving
access roads, parking area, crane shelter access, and resurfacing
Sycamore Creek and River Roads, 80 percent placed this year;
and construction of additional water supply and miscellaneous
improvements, 10 percent placed this year.
    Maintenance: Maintenance and operation of the dam and reser-
voir, service facilities, and public recreational facilities was ac-
complished .by hired labor. In addition, hired labor was utilized
during the year for condition and operation inspections and for
condition surveys, including maintenance of gages and gage
readings.
    Pine Flat Reservoir was operated for flood control only prior
to February 13, 1954. A maximum of 3,530 acre-feet was stored
during this period. Operation for conservation, under interim
contract with Kings River Conservation District, was initiated on
February 13, 1954. A maximum storage of 428,000 acre-feet
occurred during the fiscal year, and 353,000 acre-feet was in
storage at the end of the fiscal year. Of this, about 62,000 acre-
feet was stored under interim contract with the Pacific Gas and
Electric Company for future exchange with Kings River water
at proposed upstream reservoirs. No releases for flood control
were made subsequent to February 13, 1954. The reservoir regu-
tion manual was completed.
   Total costs during the year for the project were $865,203, of
which $813,857 was for new work and $51,346 for maintenance.
   Condition at end of fiscal year. Construction was initiated in
April 1947; the project is 93 percent complete. Construction of
the main dam was initiated in January 1950 and completed in
June 1954; final concrete pour was made in March 1953; and the
dam is operating to provide the flood protection for which it was
designed. Acquisition of lands required for the project is com-
plete, except for legal proceedings. Reservoir clearing, reloca-
tions of roads and utilities, and construction of operational build-
ings have been completed. Work remaining to be done consists
of completion of work underway, construction of bridge and rating
weir, malaria control, completion of minor public use and sanitary
facilities, the installation of gages and communication facilities
for operating purposes, and the provision of channel improve-
ments. Project completion is currently scheduled for fiscal year
1956.
   Maintenance was initiated in fiscal year 1954.
   Total costs for the project to June 30, 1954, were $38,212,290,
of which $38,160,944 was for new work and $51,346 for mainte-
nance.
                   FLOOD CONTROL-SACRAMENTO, CALIF., DISTRICT                                                                       1397
                                                     Cost and financial summary

                                                                      Fiscal year ending June 30                            Total to June
                                                                                                                            30, 1954, includ-
                                                                                                                            ing fiscal years
                                              1950               1951                   1952        1953          1954        priorto 1954


New work:
   Appropriated -- -                   $7, 100,000         $8, 365, 000 $ 8, 000, 000            $8, 707,000   -$353, 455       $38, 518, 545
   Cost   -...............                  3, 286, 739      7, 497, 576          12, 130, 727   18,948,626      813, 857       2 38,160, 944
Maintenance:
   Appropriated........------------------------------------------------                                           53,900              53,900
   Cost------                ------------            ------------------------------------                         51,346              51,346

  1Includes amount of $102,500 advance for establishment of South Pacific Division Laboratory.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954---------_ --      $164,769
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955                                                                164,769
                                                                            $----------------
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project              --------           -----      $2,381,455

               15. ISABELLA RESERVOIR, KERN RIVER, CALIF.
   Location. The area covered by this project comprises the upper
watershed of Kern River, its valley alluvial fan (which includes
the Buena Vista Lake area and a large portion of that part of the
San Joaquin Valley floor south of Tulare Lake), and the Tulare
Lake area. Kern River is the most southerly of the major streams
flowing into the San Joaquin Valley and drains an area of some
2,400 square miles in the Sierra Nevada. North Fork and South
Fork, headwaters of Kern River, have their sources in the high
Sierra Nevada, flow south 83 and 82 miles, respectively, and join
near the town of Isabella to form Kern River, which flows south-
west 72 miles past the city of Bakersfield to a point in the valley
trough just north of Buena Vista Lake. River flows at this point
are either diverted into the Buena Vista Lake Basin for temporary
storage or are carried northwest along the trough of the valley
toward Tulare Lake by improved flood and irrigation channels.
Under normal conditions of runoff the flow of Kern River below
Bakersville is gradually dissipated by irrigation diversions so that
Kern River water reaches Tulare Lake only during large floods.
 (See U. S. Geological Survey quadrangles of the area.)
   Existing project. The improvement is a unit in the compre-
hensive plan for flood control and other related purposes for the
Sacramento-San Joaquin Basins. The project provides for con-
struction of a 185 foot high earthfill structure, an ungated con-
crete spillway in the left abutment with a discharge capacity of
53,000 cubic feet per second, and a 100 foot high earthfill auxiliary
dam, to create a reservoir with a gross storage capacity of 550,000
acre-feet, for flood control, irrigation, and related purposes. Out-
let facilities for the existing Borel Power Canal are included in
the auxiliary dam. The dam is located about 50 miles northeast
of the city of Bakersfield, California, near the confluence of the
north and south forks of Kern River; the auxiliary dam is about
1398     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

one-half mile east of the main dam. Construction of the dam was
completed in April 1953.
   The improvement provides flood protection for about 350,000
acres of agricultural land and oil fields in the Kern River area
and for the city of Bakersfield. In conjunction with the author-
ized projects on Kings, Kaweah, and Tule Rivers, it will provide
flood protection to 260,000 acres of cropland in the Tulare Lake
area. The project also provides an improvement in the average
annual irrigation water supply amounting to about 56,000 acre-
feet of new water, through reduction in evaporation losses, and
provides means for regulating the present irrigation supply. No
power facilities are provided in the authorized construction, but
existing downstream plants will benefit incidentally from reser-
voir regulations.
   The latest approved estimate of Federal cost for new work
 (1954) is $21,093,000, of which $4,478,700 is for lands and dam-
ages and $16,614,300 for construction.
   Operation and maintenance of the dam and reservoir is the
responsibility of the Federal government; the latest (1953) ap-
proved estimate for annual Federal cost of this operation and
maintenance is $71,000. Local interests will reimburse the United
States for the conservation accomplishments of the project.
   The existing project was adopted by the Flood Control Act of
December 22, 1944. (See H. Doc. 513, 78th Cong., 2d sess., which
contains the latest published map.)
   Local cooperation. Payment, as determined by the Secretary
of the Army upon the basis of continuing studies by the Bureau
of Reclamation, the Department of the Army, and local organi-
zations, is to be made to the United States by the State or other
responsible agency for the conservation storage when used.
Studies to determine the amount of this payment have been initi-
ated. Local interests state they will meet these requirements.
The State of California has officially adopted the project by chapter
1514 of the Statutes of 1945, State of California, approved July
19, 1945.
   Operations and results during fiscal year. New work: Engi-
neering, including preparation of contract plans and specifications,
was continued. Land acquisition activities have been completed
except for legal proceedings. Preparation of the operation and
maintenance manual, operation and maintenance of construction
facilities, and establishment of sedimentation ranges was con-
tinued, by hired labor. In addition, hired labor was utilized in
connection with the purchase and installation of electric tape
gages and for the installation of local wire transmitter facilities
for 1 stream gage. Construction was completed under contracts
for the following items of work: Reservoir clearing, Area "B",
with 50 percent of the work accomplished this fiscal year; in-
stallation of 2 stream gages and a rating station near Bodfish and
Kernville, 26 percent this fiscal year; and relocation of Pacific
Telephone Company lines, 1 percent this fiscal year. Removal of
          FLOOD CONTROL-SACRAMENTO,       CALIF., DISTRICT      1399
Southern California Edison Company power distribution lines
and appurtenances was continued, by a continuing contract, with
40 percent of the work accomplished this fiscal year. Construc-
tion of hydrologic telemetering system, Kern River, was initiated
by contract and is 5 percent complete. Conversion of part of
the existing administration building to operators' quarters and
grouting of the outlet tower of the main dam were accomplished
by contracts. In addition, clearing, removing, and burning brush
and debris remaining from removing buildings in the reservoir
area was accomplished by hired labor and rented equipment.
   Maintenance: Maintenance and operation of the dam and reser-
voir, service facilities, and public recreational facilities was ac-
complished by hired labor. In addition, hired labor was utilized
during the fiscal year for condition and operation inspections and
for condition surveys, including maintenance of gages and gage
readings. Removal and burning of debris from the reservoir
area was accomplished by hired labor and rented equipment.
   Isabella Reservoir was operated under interim regulations
for flood control only prior to April 15, 1954. A maximum of
1,120 acre-feet was stored during this period. Operation for
conservation under interim contract with North Kern Water
Storage District, Buena Vista Water Storage District, and Tulare
Lake Basin Water Storage District was initiated on April 15,
1954. A maximum storage of 85,400 acre-feet occurred during
the fiscal year, and 69,500 acre-feet was in storage at the end of
the fiscal year. No releases for flood control were made subse-
quent to April 15, 1954.
   Total costs during the year for the project were $514,554, of
which $476,768 was for new work and $37,786 for maintenance.
   Condition at end of fiscal year. Construction was initiated in
March 1948; the project is 97 percent complete; and is operating
to provide the flood protection and conservation benefits for which
it was designed. Construction of the main dam and Borel Canal
outlet works and appurtenances and completion of the auxiliary
dam was completed in April 1953. Other major features com-
pleted include: Acquisition of lands required for the project ex-
cept for legal proceedings; relocations of roads and utilities;
construction of operational buildings; alteration of IBorel Canal
and facilities; relocation of United States Forest Service facilities;
and reservoir clearing.
   Items remaining to complete the project consist of completion
of work underway; malaria control; completion of minor reservoir
clearing; completion of minor public use and sanitary facilities;
and the installation of gages and communication facilities for
operating purposes. Project completion is currently scheduled for
fiscal year 1956.
   Maintenance and operation of the project was initiated in fiscal
year 1954. Total cost for the project to June 30, 1954, was
$20,563,957, of which $20,526,171 was for new work and $37,786
for maintenance.
1400             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                          Cost and financial summary

                                                   Fiscal year ending June 30                                     To tal to June
                                                                                                                 30, 1954, includ-
                                                                                                                 ing fiscal years
                                   1950      I   1951          1952               1953                1954          pr ior to 1954

New work:
   Appropriated          $2, 550,000 $2, 855, 000           $4,500, 000        1$6,980,000                               $20, 743,000
           __ . . .__. -
   Cost .....             1, 756,128  2, 175, 863            6, 679, 907        7, 453,309          $476,768              20, 526,171
Maintenance:
   Appropriated_..
   Cost--------------
                      ------------
                          --   -----.-----


                                             I
                                                   ---- I                  I                   I
                                                                                                       38,700
                                                                                                       37, 786
                                                                                                                                   38, 700
                                                                                                                                   37, 786

  1 Does not include reserve of $350,000 retained in OCE for the project.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_                $133,695
    Unobligated balances available for succeeding fiscal year ending June
            30, 1955___                                                                                                   133,695
       Estimated additional amount needed to be appropriated for completion
         of existing project_        -                     ---                                                            350,000


                   16.    INACTIVE               FLOOD        CONTROL                  PROJECTS

                                                                                 Cost to June 30, 1954
                                                          For last                                                    Estimated
                  Name of project                       full report                                                    amount
                                                        see annual                       Operations                  required to
                                                        report for-        Construction     and                       complete
                                                                                        maintenance

Terminus Reservoir, Kaweah River, Calif         .--- 1953                         $343,472  -----------              S?$17, 056, 528
Success Reservoir, Tule River, Calif-..........-.    1953                          401,318 --------------            1 712, 598,682
Humboldt River and tributaries, Nevada        -----1951
                                              ...
                                                                                                                          10,900,000
Jordan River, Salt Lake City, Utah -                           1951                 42, 399         ------------     1   6 1,127, 601
Little Valley Wash, Magna, Utah__-_-_ -       _                1951                                                      16 707 000
Sevier River, near Redmond, Utah-....-------------             1952               a 919, 000                              (6),     (8)
Spanish Fork River, Utah---------....   ---                 -__1953                                                       1 228,000
Emergency Flood Control Work under authority                   1951                                  $3.069.099              (8)
  of Public Laws 138 and 318, 78th Cong., Public
  Law 75, 79th Cong., and 102, 80th Cong.
Emergency Bank Protection under authority of                  1953                 3 40,013        -------------.            (8)
  Section 14 of the Flood Control Act approved
  July 24, 1946.
Emergency Flood Control Work under authority                  1953                                   S1, 919, 202            (8)
  of Section 208 of the Flood Control Act approved
  June 30, 1948.

  1 1954.
  2 In addition, $48,000 was expended from contributed project funds.
   3 In addition, $12,700 was expended from contributed funds.
  4 In addition, $184,986 was expended from contributed funds for maintenance. Fiscal year 1953 cost
adjusted to exclude $7,832 erroneously reported under this improvement in lieu of Sect. 210 of Flood Control
Act approved May 17, 1950. Actual fiscal year 1953 costs were $88,033. $7,832 was revoked in fiscal year
1954.
   5 In addition, local interests are to contribute $2,762,000 toward the cost of construction, making a total
first cost of $13,662,000.
   6 The latest estimates (1954) of costs to local interests are as follows: Humboldt River and tributaries,
Nev., $1,248,000 in addition to the above cash contribution; Jordan River, Utah, $318,000; Little Valley
Wash, Utah, $29,000; Sevier River, Utah, $70,000 in addition to cash contribution; and Spanish Fork
River, Utah, $83,000.
   7 The latest (1948) approved estimate for annual Federal cost of maintenance is as follows: Terminus
Reservoir, Calif., $114,900; Success Reservoir, Calif. $43,000; and Humboldt River and tributaries, Nev.,
$75,000.
  s Completed.

                                17. GENERAL INVESTIGATIONS

  Examinations and surveys. Work performed under this cate-
gory includes all investigations of authorized navigation and flood
control preliminary examination, survey, and review studies for
          FLOOD CONTROL-SACRAMENTO, CALIF., DISTRICT            1401
the purpose of determining the advisability of recommending proj-
ects for construction.
   Total costs and expenditures during fiscal year 1954 were
$14,428.
   The balance unexpended on June 30, 1954, amounting to $58 will
be applied to examinations and surveys. Additional funds in the
amount of $83,000 can be profitably expended in fiscal year 1955.
$63,000 would be utilized to expedite the preparation of investi-
gational reports as follows: Gleason Creek, Robinson Watershed,
vicinity of Ely, and Martin Creek, vicinity of Paradise Valley,
Humboldt County, Nev.-Initiate and complete preliminary ex-
amination reports, $6,000 each; Walnut Creek Drainage Area,
Contra Costa County, Calif.-Initiate and complete preliminary
examination and survey report, $29,000; Jordan River Basin, Utah
-Continue     interim report, $15,000; and Sacramento-San Jo-
aquin Delta, Calif.-Continue review of survey report, $7,000.
   The additional sum of $107,600 for examinations and surveys
can be profitably expended during fiscal year 1956 for preparation
of examination and survey reports.
   Collection and study of basic data. This activity includes the
collection and study of basic data pertaining to navigation, flood
control, and related programs, which cannot be assigned to au-
thorized projects or examinations and surveys, and which are
required for maintaining up-to-date information essential to the
proper evaluation of water resources of river basins.
   Total costs and expenditures during fiscal year 1954 were $5,000.
Additional funds in the amount of $20,000 would be utilized for
miscellaneous studies in connection with collection and study of
basic data consisting of stream flow and recording rain gage data;
storm studies, and economic studies. The additional funds for
miscellaneous studies are considered to be essential to provide for
the uninterrupted collection and analysis of basic data for the
river basins concerned, and particularly in view of the very lim-
ited funds which were made available for expenditure during the
prior fiscal year 1954. The additional sum of $20,000 for miscel-
laneous studies in connection with collection and study of basic
data can be profitably expended during fiscal year 1956 for mis-
cellaneous studies consisting of collection and analysis of hydro-
logic data, storm studies, sedimentation studies, flood investigation,
and general economic studies.
   Miscellaneous studies in connection with the collection and study
of basic data were conducted to the extent permitted by the very
limited funds available for fiscal year 1954. Stream flow data and
recording rain gage data were obtained from the operation of gen-
eral coverage stations in the noncooperative Corps of Engineers
stream gaging program and independent general coverage rain
gages operated by Sacramento District which could not be assigned
to authorized project or examination and survey investigations.
Analysis of flood potential on all principal streams of the Sacra-
mento District was accomplished from current runoff, snow cover,
and soil moisture data. Aerial reconnaissance surveys were con-
ducted of the snow falls in the Cascade-Sierra Nevada area for
1402               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

rain flood potential and progress of snow melt runoff. In addi-
tion, a flood reporting network was developed and maintained
throughout the district in cooperation with U. S. Forest Service,
U. S. Weather Bureau, U. S. Geological Survey, State of California,
and local interests. The above studies provided for partial assem-
bly and analysis of basic data covering the Sacramento-San Jo-
aquin River Basins and for use in developing the regulations for
Shasta and Friant Reservoirs, operated by the Bureau of Recla-
mation. The development of these operating regulations, in ac-
cordance with Section 7 of the 1944 Flood Control Act, are further
reported upon under Improvement No. 20 "Scheduling of Flood
Control Operations".
                          18. INSPECTION OF COMPLETED WORKS
   Projects authorized subject to specified conditions of local co-
operation are transferred to responsible local interests upon com-
pletion of construction for operation and maintenance in accord-
ance with the requirements of the authorizing legislation. Ap-
proved regulations for operation and maintenance of flood control
works, Part 208, Title 33, Code of Federal Regulations, provide for
semiannual inspection by the District of completed projects which
have been transferred to local interests for operation and main-
tenance to determine the status of the project and to insure com-
pliance with regulations.
   During fiscal year 1954, inspections were made of the following
projects: Sevier River, Redmond and vicinity, Utah; completed
units of the Sacramento River flood control project; various emer-
gency flood control works under authority of section 208 of the
Flood Control Act approved June 30, 1948, section 210 of the Flood
Control Act approved May 17, 1950, section 14 of the Flood Con-
trol Act approved July 24, 1946, and Public Law 371 approved
June 4, 1952; and snagging and clearing projects under authority
of section 2 of the Flood Control Act approved August 28, 1937,
as amended. Total cost for maintenance during the year was
$1,105.
   Total costs for maintenance to June 30, 1954, were $8,005.
                                                Cost and financial summary

                                                      Fiscal year ending June 30                       Total to June
                                                                                        _             30, 1954, includ-
                                                                                                      ing fiscal years
                                         1950        1951        1952        1953           1954        priorto 1954


Maintenance:
   A p p r op r iate d _ .. . . _ _- . .-.. . . .    $4 , 450                 $2, 500       $1, 100             $8 ,050
     Cost_-------------                               1,385      $1,494        4,022         1,105               8,005



  19. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
  Snagging and clearing of navigable streams and tributaries in
the interests of flood control. (Section 13 of the 1946 Flood Con-
trol Act.)
     Operations during the fiscal year included completion of the
                FLOOD CONTROL--SACRAMENTO,                         CALIF., DISTRICT                1403
snagging and clearing of the channel of Marsh Creek, Contra Costa
County, Calif. initiated in fiscal year 1953, by hired labor. See
page 1810, Annual Report, 1953, for local cooperation requirements
for this improvement; the requirements were fully complied with
prior to construction.
   Snagging and clearing the channel of Salt Creek, near Nephi,
Utah, by hired labor and rented equipment, was also accomplished
during the fiscal year. Local interests furnished assurances, prior
to initiation of construction, that they would provide all necessary
rights-of-way, hold and save the United States free from damages,
and maintain the work after completion; requirements were fully
complied with.
   Plans and specifications for equipment rental were prepared for
snagging and clearing of Cottonwood Slough and the South Fork
of Willow Slough in the vicinity of Madison, Calif. Operations
were not initiated in fiscal year 1954. Local interests were re-
quested on April 30, 1954, to furnish assurances that they will
provide all necessary rights-of-way, hold and save the United
States free from damages that may occur as a result of the work,
and maintain the work after completion. The assurance agreement
has been furnished; this work will be accomplished in fiscal year
1955.
   Total costs for new work during fiscal year 1954 were $32,758
from Federal funds.
   Total costs to June 30, 1954, for new work were $1,255,122, of
which $1,251,122 was from Federal funds and $4,000 from con-
tributed funds.
                                       Cost and financial summary

                                             Fiscal year ending June 30                    Total to June
                                                                                           30, 1954, includ-
                                                                                           ing fiscal years
                                1950        1951        1952         1953       1954        priorto 1954

New work:
   Appropriated--------.....   $191, 734   $145, 934    $56, 671    $211, 264   $38, 153       1 $1, 290098
   Cost----------------         103, 195    100, 921    141, 012     229, 031    32, 758        1 1251, 122

  1 In.addition, $4,000 was expended from contributed funds.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954---------_ -_    $31,510
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955    ---------------------------------------------- 31,510

  Flood control emergencies--Repair and flood fighting and rescue
work. (Section 210 of the 1950 Flood Control Act and supple-
mental authorizations.)
  Operations during the fiscal year under the provisions of this
act consisted of the completion of emergency levee repairs to
Bethel Island, Reclamation District No. 1619, along Piper Slough
San Joaquin River, Calif., by hired labor and rented clamshell
dredge; 10 percent of the work was accomplished this fiscal year.
  Total cost during fiscal year 1954 for the above work was $1,801
for maintenance from United States funds.
1404              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Total costs to June 30, 1954, for maintenance were $1,601,083,
of which $1,578,207 were from United States funds and $22,876
from contributed funds.
                                             Cost and financial summary

                                                     Fiscal year ending June 30                          Total to June
                                                                .. . . . .    .30,                         1954, includ-
                                                                                                        ing fiscal years
                                   1950           1951          1952          1953          1954         priorto 1954

Maintenance:
   A p p ro p ria ted _.. _   .. ............    $6 9 2, 73 4   $4 2 , 101    $3 2, 624   - $13, 40 5       1   $1, 58 3 , 70 5
   Cost-.- --                      $29, 391       377, 241      279, 165      290, 349        1, 801            11, 578, 207
   1 In addition, $22,876.09 was expended from contributed funds.
   2 Fiscal year 1953 cost of $90,349 includes adjustment of $7,832 erroneously reported as cost for emergency
flood control work under section 208 of Flood Control Act approved June 30, 1948.


  Flood control emergencies---Repairand flood fighting and rescue
work. (Section 210 of the 1950 Flood Control Act and supple-
mental authorizations.)
  Operations during the fiscal year under the provisions of this
act also consisted of the completion of emergency levee repairs
along the right bank of Sacramento River 21/2 miles above Sacra-
mento Wier, Reclamation District No. 537, Calif., by contract; 89
percent of the work was accomplished this year. All requirements
of local cooperation were fully complied with.
  Total costs during fiscal year 1954 for the above work were
$34,858 from United States funds.
  Total costs to June 30, 1954, for work under the provisions of
this act were $238,847, of which $226,347 were from United States
funds and $12,500 from contributed funds.
                                           Cost and financial summary

                                                    Fiscal year ending June 30                           Total to June
                                                                                                        30, 1954, includ-
                                                                                                        ing fiscal years
                                   1950           1951          1952          1953          1954          priorto 1954

Maintenance:
    Appropria : ted
    A pp rop riated -------    ....-------
                              !I                    .-.------- . ........    $254,471
                                                                              1 1$2
                                                                                  4       -$28, 124              I$226, 347
    Cost-_ .             -      -191,489                                                     34, 858              1226, 347

  1 In addition, $12,500 was expended from contributed project funds.



            20. SCHEDULING OF FLOOD CONTROL OPERATIONS
   Section 7 of the Flood Control Act approved December 22, 1944,
reads as follows:
   "Hereafter, it shall be the duty of the Secretary of War to pre-
scribe regulations for the use of storage allocated for flood control
or navigation at all reservoirs constructed wholly or in part with
Federal funds provided on the basis of such purposes, and the op-
eration of any such project shall be in accordance with such regu-
lations: Provided, That this section shall not apply to the Ten-
nessee Valley Authority, except that in case of danger from floods
on the lower Ohio and Mississippi Rivers the Tennessee Valley Au-
thority is directed to regulate the release of water from the Ten-
               FLOOD CONTROL---SACRAMENTO,                  CALIF., DISTRICT              1405
nessee River into the Ohio River in accordance with such
instructions as may be issued by the War Department."
   In accordance with the provision of the above authorization
continuing studies are being conducted for the purpose of devel-
oping and prescribing regulations for Friant Reservoir, operated
by the Bureau of Reclamation.
   During the fiscal year, navigation flow requirements were ana-
lyzed to determine operational criteria for Shasta Reservoir. A
draft of the reservoir regulation manual for Shasta Reservoir and
draft of flood control regulations for Friant Reservoir were pre-
pared. Data were assembled on weather, river stages and flows,
and tidal stages in the Sacramento and San Joaquin River Basins
for determination of the effect upon the operation of these reser-
voirs. In addition, charts of monthly reservoir operations were
submitted to the Chief of Engineers.
   The cost of this work during the fiscal year 1954 was $2,500.
   Total cost for this work to June 30, 1954, was $24,183.
                                 Cost and financial summary

                                       Fiscal year ending June 30                Total to lune
                                                                                 30, 1954, includ-
                                                                                 ing fiscal years
                          1950        1951        1952        1953    1954        priorto 1954

Maintenance:
   Appropriated   ..---   $12, 913     $1,997        $999              $2, 500            $24,183
   Cost   .                12, 913      1,997         999               2, 500             24,183
   IMPROVEMENT OF RIVERS AND HARBORS IN THE
           PORTLAND, OREG., DISTRICT

  This district comprises all of Oregon which lies within the
watershed of Columbia River and tributaries below Irrigon, also
the coastal drainage area, together with south central Oregon,
not including that part which drains into Klamath Lake and
River. It also includes that part of southern Washington within
said watershed and downstream from a point opposite Irrigon,
Oreg.
                                     IMPROVEMENTS

                 Navigation                                     Flood control
                                         Page                                            Page
1. Columbia River and tributaries              24. Amazon Creek, Oreg ........          1453
      above Celilo Falls to-Kenne-              25. Willamette River Basin, Port-
      wick, Wash_             _      .   1408         land District, Oreg ......         1454
2. The Dalles Dam, Columbia                    26. Hills Creek Dam, Willamette
      River, Wash. and Oreg ....         1410         River Basin, Oreg__                1458
3. The Dalles-Celilo Canal, Oreg.              27. Lookout     Point     Reservoir,
      and Wash_                          1412         Willamette     River Basin,
4. Columbia River at Bonneville,                     Oreg                               1459
      Oreg                               1414   28. Cottage     Grove     Reservoir,
5. Restoration of Indian Fishing                     Willamette River          Basin,
      Grounds, Bonneville, Oreg__        1418         Oreg--------                       1461
6. Columbia River between Van-                 29. Dorena Reservoir, Willamette
      couver, Wash. and The                           River Basin, Oreg-                 1462
      Dalles, Oreg___________            1419   30. Fern Ridge Reservoir, Willa-
7. Willamette River, above Port-                     mette River Basin, Oreg -..        1464
      land, and Yamhill River,                  31. Cougar Dam, Willamette River
      Oreg___                            1421         Basin, Oreg_                       1465
8. Willamette River at Willa-
                          -         -
                                                32. Green Peter Dam, Willamette
      mette Falls, Oreg         ___      1425         River Basin, Oreg .......          1466
9. Columbia and Lower Willa-                   33. Detroit Reservoir, Willamette
      mette Rivers below Van-                         River Basin, Oreg ........         1467
      couver, Wash., and Portland,              34. Willamette River Basin, Oreg.
      Oreg"___                           1427         (Bank Protection) ........         1470
10. Cowlitz River, Wash_ ____ __         1432   35. Lower Columbia River Basin,
11. Skipanon Channel, Oreg.. .-          1433         Oreg. and Wash____                 1472
12. Columbia River between Chi-                 36. Sandy Drainage District, Mult-
      nook, Wash. and head of                         nomah County, Oreg., Lower
      Sand Island_                       1434         Columbia River Basin Levees
13. Columbia River at Baker Bay,                      and Improvement to Exist-
      Wash                               1435         ing Projects __-                   1474
14. Columbia River at the mouth,                37. Inactive flood control projects_     1475
      Oregon and Washington.__-          1437   38. General investigations .......       1476
15. Nehalem Bay, Oreg                    1439   39. Inspection of completed flood
16. Tillamook Bay and Bar, Oreg_..       1440         control works-                     1477
17. Depoe Bay, Oreg_                     1441   40. Flood control work under
18. Yaquina Bay and Harbor, Oreg         1442         special authorization ......       1478
19. Umpqua River, Oreg __....            1445
20. Coos Bay, Oreg_                      1447
21. Coquille River, Oreg ........        1450
22. Snagging and clearing of chan-
      nels in the interest of naviga-
      tion under authority of sec-
      tion 3 of the River and
      Harbor Act approved March
      2, 1945------_---------            1452
23. Inactive navigation projects__       1452
                                                                                1407



       Sig 45-1407-1438
1408               REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

1. COLUMBIA RIVER AND TRIBUTARIES ABOVE CELILO FALLS TO
                   KENNEWICK, WASH.
  Location. This project includes improvement of the 128-mile
stretch between the head of Celilo Falls and Kennewick, Wash.
For brief description of Columbia River, see page 1427. (See U. S.
Geological Survey map of Washington.)
   Previous project. The original project was adopted by the
River and Harbor Act of June 10, 1872, and modified by the River
and Harbor Act of March 2, 1907. For further details, see page
1992 of Annual Report for 1915; page 1889, Annual Report for
1931; and page 1845, Annual Report for 1938.
  Existing project. This provides for a channel 7 feet deep and
150 feet wide at low water from Celilo Falls to Wallula, with no
specified depth or width between Wallula and the mouth of the
Snake River; for an approach channel 6 feet deep at low water
from the navigation channel in the Columbia River to the site of
port development at Arlington, Oreg.; for removal of obstructions
in the channel from the mouth of the Snake River to Kennewick,
Wash.; and for an approach channel 6 feet deep from the channel
in the Columbia River to the site of terminal developments at
Kennewick. The section included in the project is 128 miles long.
The lower end of the project is about 200 miles from the mouth of
the river. The summer freshets occur from May to August and
the ordinary freshets reach a stage of 21 feet on Umatilla gage.
The highest flood (1894) reached a stage of 341/2 feet at Umatilla.
Freshets due to rains sometimes occur in the early winter, but
rarely exceed a 9-foot stage. Ice conditions, usually occurring in
January or February, sometimes suspend navigation for 2 weeks
or more. Construction of McNary Dam has obviated the necessity
for channel work between Umatilla Rapids and Kennewick, Wash.
   The latest (1954) approved estimate of cost for new work is
$1,775,000, exclusive of amounts expended on previous projects.
The latest (1954) approved estimate for annual cost of mainte-
nance is $120,000.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts        i                       Work authorized                                   Documents'
Apr.     8, 1935       Emergency Relief Appropriation Act authorized the        Rivers and Harbors Committee
                        existing project as an Emergency Relief project.         Doc. 16, 73d Cong., 2d sess.
Aug. 30, 1935          Adopted existing project as a river and harbor project_ J       1
M ar. 2, 1945          Arlington approach channel .........    ................   S. Doc. 28, 76th Cong., 1st sess.
    Do                                                      ..
                       Kennewick approach channel __________----------            -If. Doc. 324, 77th Cong., 1st sess.


  1Contains     latest published map.


   Local cooperation. The River and Harbor Act approved March
2, 1945, provides that for each of the Arlington and Kennewick
channels local interests give assurance that they will construct a
suitable freight terminal, open to all on equal terms, and for the
Kennewick channel that they furnish, free of cost to the United
States, all lands, easements, rights-of-way, and spoil disposal areas
necessary for the improvements and their subsequent mainte-
         RIVERS AND HARBORS-PORTLAND, OREG., DISTRICT             1409
nance, when and as required, and hold and save the United States
free from claims for damages resulting from the improvements.
Assurances of cooperation for work at Arlington were approved
December 29, 1947, but a suitable freight terminal has not yet been
constructed.
   Terminal facilities. There is one public wharf on this stretch
of the river located at Pasco, Wash. (mile 127.2 above Celilo), and
owned by the port of Pasco. A bulk grain elevator of 500,000-
bushel capacity, with rail, truck, and water connections, is located
adjacent to the wharf at Pasco; a bulk grain elevator of 1,200,000-
bushel capacity, with rail, truck, and water connections is located
at Kennewick, Wash. (mile 129.6 above Celilo); and a 300,000-
bushel capacity grain elevator is located at Arlington, Oreg. Other
facilities for handling bulk grain from truck to river craft, but
without rail connections, are as follows: A bulk grain elevator of
150,000-bushel capacity at Port Kelley, Wash. (mile 110.6 above
Celilo); a 335,000-bushel elevator at Umatilla (mile 88 above
Celilo); and a 40,000-bushel elevator at Blalock (mile 32 above
Celilo). There are privately owned storage facilities for handling
petroleum products with capacities and locations as follows: At
Pasco, Wash. (mile 127.2 above Celilo), 9,000,000 gallons with rail,
truck, and water connections; and at Umatilla, Oreg. (mile 88 above
Celilo), 13,403,425 gallons of which 8,494,425 gallons have rail
connections and 4,909,000 gallons with truck and water connec-
tions only. There is a railroad located on each bank of the river,
but there is no physical connection between the railroad and the
river except as noted. At Irrigon, Oreg., there is a privately owned
wharf for the shipment of lumber and general cargo by barge.
Also, on the Oregon shore, across the river from Patterson, Wash.
 (mile 76 above Celilo), there is a privately owned dock for the
shipment of general cargo by barge.
   Located on the Snake River, a tributary of the Columbia River
 (between mouth and mile 2.7) there are privately owned storage
facilities for handling petroleum products with a capacity of 38,-
271,597 gallons with pipeline, rail, truck, and water connections
with a planned immediate installation of facilities for handling and
storage of 2,180,000 gallons of liquid ammonia and 5,000 barrels of
bulk cement.
   These facilities, with planned extensions, are considered ade-
quate for existing commerce.
   Operations and results during fiscal year. Maintenance: Hy-
drographic condition surveys were made at a cost of $2,336.26.
Inspections and reports were made at a cost of $356.69.
   Total costs for the fiscal year were $2,692.95, all for maintenance.
   Condition at end of fiscal year. The existing project is approxi-
mately 90 percent complete. The authorized 7 foot channel 150
feet wide has been completed to the foot of Umatilla Rapids but
channel rectification at Indian Rapids, Squally Hook Rapids, and
Owyhee Rapids remains to complete this stretch of the project.
The controlling depth between Celilo Falls and the foot of Umatilla
Rapids is 7 feet, survey of August 1953.
   Construction of McNary Dam at Umatilla Rapids has been un-
1410           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

derway since May 1947. The navigation lock is officially opened to
river traffic, and for that portion of the project above McNary Dam
project depths or greater are available at all times.
   Total costs have been $2,128,731, of which $1,356,584 (includ-
ing $400,000 emergency relief funds) was for new work and $772,-
147 for maintenance.
                                        Cost and financial summary

                                                 Fiscal year ending June 30                            Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                                 1950           1951           1952          1953           1954        prior to 1950 1


New work:
   Appropriated ------........------------------------- ------------------    -----...................--    $1, 851,195
   Cost -----------------------------------------------------------....................                      1, 851, 195
Maintenance:
   Appropriated--------          $73, 377       $25, 500       $9, 840        $4 000         $2, 600            873,263
   Cost---- ----------            73, 377        25, 500        9, 840         3, 621         2, 693            872, 977

1Includes $494,611 for new work and $100,830 for maintenance for previous projects.
2 In addition $25,000 for new work was expended from contributed funds, for the previous project.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project$--------------------------419,716

  2. THE DALLES DAM, COLUMBIA RIVER, WASH. AND                                                             OREG.
  Location. The site of this project is on Columbia River at the
head of the pool behind Bonneville Dam, approximately 192.5 miles
above the mouth of the river and 90 miles east of Portland, Oreg.
  Existing project. This project provides for a dam, powerplant,
navigation lock and appurtenant facilities. The improvement will
provide for navigation and hydroelectric power generation. The
dam is designed for a normal pool at elevation 160 mean sea level.
The normal pool will create a reservoir extending upstream about
31 miles, providing slackwater to the John Day Dam site. The
total length of The Dalles Dam will be approximately 8,700 feet and
will consist of a rock, gravel, and sand closure section from the
Oregon shore connecting to the powerhouse, then concrete non-
overflow sections connecting the spillway with the powerhouse and
the spillway with the navigation lock located at the right abutment
on the Washington shore. Fish passing facilities including two
ladders will be provided. The 2,150-foot powerhouse will be con-
structed for 16 units with 14 units installed initially and substruc-
ture will be constructed for 6 additional units, an ultimate total of
22 units. The rated capacity of each unit is to be 78,000 kilowatts
and the initial installation is to be 1,092,000 kilowatts. The spill-
way dam will be 1,370 feet long and located near the right abut-
ment. The overflow crest at elevation 121 mean sea level will be
surmounted with 23 radial gates 50 feet wide by 43 feet high which
will provide capacity to pass a spillway design flood of 2,290,000
cubic feet per second. The deck will be at elevation 185.0 mean
sea level and will provide a service road and track for two gantry
cranes. The navigation lock will have clear plan dimensions of 86
feet by 675 feet and a single lift of about 87.5 feet with minimum
depth over the sill 15 feet and normally 20 feet. The lock will in-
clude upstream and downstream guard and guide walls to protect
         RIVERS AND HARBORS-PORTLAND, OREG., DISTRICT            1411
boats and tows from adverse currents. The structures will be
founded on Columbia River basalt.
    The estimate of cost for new work approved in 1954 is $300,000,-
000, of which $64,949,100 is for lands and damages, including re-
locations, and $235,050,900 for construction.
   The existing project was authorized by the Flood Control Act
approved May 17, 1950, House Document 531, 81st Congress, 2d
session.
    Operations and results during fiscal year. Excavation work in
the powerhouse, spillway dam, stilling basin, tailrace, and approach
channel areas progressed satisfactorily throughout the fiscal year
except for a shutdown of operations during January 1954, occa-
sioned by unfavorable weather conditions. Construction of the
spillway dam and the powerhouse substructure for the first 14
main generating units (phase I) is in progress, each under con-
tinuing contracts. Concrete placing initiated in December 1953
is in progress in the stilling basin, the spillway, and the draft tubes
and intake structure of the powerhouse. Work under a third con-
tinuing contract for excavation and construction of the substruc-
ture for main unit bays 15 through 22, the east fishladder and east
concrete nonoverflow dam (phase III) was initiated January 1954,
and is scheduled to be complete in April 1956.
    Grading operations and construction of bridges for relocation of
the U.P.R.R. and U. S. Highway No. 30 on the Oregon shore were
in progress under several continuing contracts, all of which were
on or ahead of schedule.
    Negotiations with the S. P. &S. Railway for relocation of approxi-
mately 14 miles of main line track on the Washington shore were
in progress and a draft of the proposed agreement prepared.
    Land acquisition was continued and settlement negotiations with
the Indian tribes in connection with their fishing rights were in
progress.
    Design and fabrication of turbines for the first 14 main and the
two fishwater supply generating units, the powerhouse intake gates
and appurtenances, bridge cranes and other powerhouse equipment
were under way under various contracts.
    Contract plans and specifications for construction of the naviga-
tion lock, adjacent gravity dam, and fish ladder, were completed
and it is proposed to award a continuing contract for this work in
September 1954. Preparation of plans and specifications for con-
struction of the powerhouse superstructure was under way with a
contract scheduled to be awarded early in calendar year 1955.
    Total costs for the fiscal year were $21,890,701.19, all for new
work.
    Condition at end of fiscal year. Construction of the project
initiated in February 1952 is 13 percent complete as a whole.
Construction of the spillway dam and appurtenances is 46 percent
complete and is scheduled to be 100 percent complete December
1955. Construction of the powerhouse substructure for the first 14
main units and the substructure for units 15 through 22 is 22 per-
cent and 6 percent complete, respectively. U.P.R.R. and U. S.
Highway No. 30 grading and bridge construction currently under
contract is 44 percent complete. Engineering and design for the
1412              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

remainder of the required relocation work is well advanced. Plans
and specifications for the closure contract and procurement of
powerhouse mechanical and electrical equipment and for miscel-
laneous items of construction are being prepared and the work will
be advertised for bids as plans are completed and approved, pro-
vided necessary funds are available.
   Total costs have been $38,123,412, all for new work.
                                                Cost and financial summary

                                                            Fiscal year ending June 30                                   Total to June
                                                                                                                        30, 1954, includ-
                                                                                                                        ing fiscal years
                                        1950              1951             1952         1953             1954             priorto 1950

New work:
                ......--..----------
   Appropriated------                                   $800, 000       $4, 000,000 $19, 876,000 $32, 000, 000                 $56, 676, 000
   Cost --------------------------                       542,207         2,993,596   12,696,907 21,890, 701                     38,123,412


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954__                                                                $412, 537
    Appropriated for succeeding fiscal year ending June 30, 1955 ....                                              _     36,000,000
     Unobligated balances available for succeeding fiscal year ending
          June 30, 1955_                      ---------------------------------------                                    36,412,537
     Estimated additional amount needed to be appropriated for com-
          pletion of existing project --                                  -
                                                                 ___________---              --------                  207,324,000


             3. THE DALLES-CELILO CANAL, OREG. AND WASH.
  Location. This improvement embraces about 12 miles of the
Columbia River between The Dalles and Celilo, Oreg. (See U. S.
Geological Survey map of Oregon.)
  Previous projects. Adopted by the River and Harbor Act of
August 18, 1894. For further details see page 1993 of Annual
Report for 1915 and page 1842 of Annual Report for 1938.
   Existing project.                          This provides for open river improvement
from the foot of Threemile Rapids to the foot of The Dalles (Five-
mile) Rapids, and a continuous canal on the Oregon shore from
the foot of The Dalles (Fivemile)                                            Rapids to the head of Celilo
Falls, the canal to have a depth of 8 feet, width of 65 feet at the
bottom, and length of 81/ miles, with 4 locks, as follows:
                                               Detailed information of locks

                                                                 Dimensions                  Lift
                                                                                                         Avail-
Miles                                                        Great-                                       able
from                                                           est                                      depth         When
lower              Lock                  Foundation           length Clear           Low        High        on          com-        Cost
  en-                                                         avail- width          water       water    lower         pleted
trance                                                       able for (feet)        (feet)      (feet)     sill
                                                                full                                      (feet)
                                                              width
                                                               (feet)


   0       Big Eddy lock ___ Rock....----------                   265         45    44. 7           18      9. 2        1941     $477,   600
   1. 6    Fivemile lock-..........        do_,---------          265         45     10. 1          15      8. 7        1915      246,   700
   5. 2    Tenmile lock 2 __           ... do __-......           265         50                     6      7. 8        1915      149,   600
   8. 1    Celilo lock 2a_-.....    ..-- .do---------.........    265         45 ....... _           6      7. 9        1915      103,   200


SOriginally constructed tandem locks converted to single lift lock in 1941.
SNot used at low water.
            RIVERS AND HARBORS--PORTLAND, OREG., DISTRICT              1413
   There are no dams in the canal. The lower end of the canal is
about 4 miles and the lower end of the Threemile Rapids about
11/2 miles above The Dalles, Oreg.
   The normal pool level at the lower end of the canal has an eleva-
tion of 72.5 feet above mean sea level and the highest flood 114.2
feet above mean sea level. At the upper end of the canal the nor-
mal freshets are about 18 feet and the maximum rise 33 feet. The
canal was designed to operate to a stage of 18 feet at the upper
pool and is then "drowned out" until the river recedes to a stage
of 18 feet.
   The actual cost for new work was $4,669,092.23, exclusive of
amount expended on previous projects. The estimate of annual
cost of operation and care, made in 1952, is $172,000.
   The existing project was adopted by the River and Harbor Act
of March 3, 1905 (Annual Report, 1904, p. 3475). Operation and
care of the canal were included in the project July 1, 1935, under
the provisions of the Permanent Appropriations Repeal Act ap-
proved June 26, 1934. For latest published map see Annual Re-
port for 1915, page 3380.
   Local cooperation. Fully complied with.
   Terminal facilities. None.
   Operationsand results during fiscal year. The canal and locks
were in continuous operation throughout the fiscal year except for
the periods from 8:00 a.m., September 28, to 7:00 a.m., September
30, 1953, when the locks and canal were closed for inspection,
cleaning and repairs.
   The various items of maintenance (operation and care) and
their costs were as follows:
Operation of locks and canal .          -.............            8$80, 334.83
Ordinary maintenance and repair..............                       8, 008.52
Dredging canal and turning basin ..........              --   -     7, 364.99

       Total....         .....................-                    95, 708.34
   Two temporary pipe lines were installed during May and June
1954 for use in pumping petroleum products around Big Eddy
lock when water stages and The Dalles Dam construction make
navigation hazardous or impossible. The cost of construction of
this facility and its maintenance is chargeable to The Dalles Dam
but the facility is to be operated by navigation interests at their
expense.
   Total costs for the fiscal year were $95,708.34, all for mainte-
nance.
   Condition at end of fiscal year. - The canal and locks were com-
pleted in 1919. The originally constructed tandem locks at Big
Eddy were converted into a single lift lock in 1941.
   The available dimensions of the locks and canal are inadequate
for the existing traffic. The Dalles Dam, Columbia River, Wash.
and Oreg., a multiple purpose project now under construction will
when completed provide adequate navigation facilities and will
inundate the existing facilities of "The Dalles-Celilo Canal". The
existing facilities of The Dalles-Celilo Canal will be maintained
until navigation facilities in connection with The Dalles Dam are
completed.
1414           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  Total costs under the existing project have been $6,748,780 of
which $4,669,092 was for new work, $5,445 for maintenance and
$2,074,243 for operation and care. In addition the sum of
$525,267.16 was expended between May 5, 1915, and June 30,
1935, on operation and care of the work of improvement, under
provision of the permanent indefinite appropriation for such pur-
poses.
                                        Cost and financial summary

                                                Fiscal year ending June 30                 Total to June
                                                                                           30, 1954, includ-
                                                                                           ing fiscal years
                                 1950         1951           1952      1953       1954      prior to 19501

New work:
    Appropriated _ -----------------------            ------------ ------------ ------------     $4, 716, 205
    Cost....-------------------          -----------------------   ------------------------       4,716,205
Maintenance:
   Appropriated........         $145, 500    $151, 000   $120, 000    $ 97,000 $110, 000         2,618, 872
   Cost----------------          130, 403     132, 912    140, 126     110,693   95, 708         2,604, 956

  I Includes $47,113   for new work for previous projects.

                4. COLUMBIA RIVER AT BONNEVILLE,                                  OREG.
   Location. This project is located on Columbia River, 42 miles
east of Portland, Oreg., about 144 miles above the mouth of the
river. For description of Columbia River see page 1427.
   Existing project. This project provides for a dam, power plant,
and lock, for power and navigation. The spillway dam extends
across the main river channel from the Washington shore to Brad-
ford Island, which divides the river at this point. The overflow
crest at 24 feet above mean sea level is surmounted by 18 vertical
lift-steel gates placed between piers which extend to elevation
99 feet where a service roadway permits the operation of two
350-ton gantry cranes for regulating the gates. The powerhouse
extending across Bradford Slough to the Oregon shore has an
installation of 10 units, consisting of 2 units of 43,200 kilowatts
each and 8 units of 54,000 kilowatts each, totaling 518,400 kilo-
watts. The ordinary and extreme fluctuations of the river at the
lower lock gate are about 21 and 47 feet, respectively. The proj-
ect includes fish ladders and locks to serve both the main channel
and the Bradford Slough channel. The lock and powerhouse are
founded on andesite, and the main dam rests upon solidified sedi-
mentary rock of volcanic origin. The pool created by the dam
provides a navigable channel with a depth of 30 feet and over
between Bonneville and Big Eddy, a distance of 47 miles.
   The principal data concerning the ship lock and spillway dam
are shown in the following table:
                                               Ship lock
Dimensions:
    Clear width of chamber..................................          76 feet.
    Greatest length available for full width..........-.. 500 feet.
    Lift (vertical):
         At extreme low water and normal pool level. 66 feet.
         At normal river stage_..........-....-..---.---.....          59 feet.
         At extreme high water ....-... ............                  About 30 feet.
                                                              ......--.---
    Depth over miter sills at adopted low water.-..                  24.2 feet.
Character of foundation- --
                         _---....... ........  ...                   Andesite.
                RIVERS AND HARBORS-PORTLAND, OREG., DISTRICT                                       1415
                                                          Spillway dam
Opened to navigation.........-------------------.....................----             January 1938.
Type of construction--..---...                                -------------------     Concrete, gravity.
Completed--------.....----...---.......-------------------.....................----.. 1938.
Capacity------                 ---------------                     ----------- 1,600 000 cubic feet per second.
Elevation of gate sills on crest of spillway                                -------- 23.3 feet.
Height above lowest foundation ...-.-----------------..-                              About 170 feet.
Length of dam proper-.....-..........                    ...........................  1,090 feet.
Length of dam overall-..-..-...................................._                     1,230 feet.
Width at base..........------                                                         200 feet.
                                 ...........---....--...------..............--------........
Gate openings....-----------------------------------------                            18.
Crest overflow (above mean sea level) ...                        __-................  24 feet.
Pool elevation (normal) (above mean sea level)-~..-                                   72 feet.
                                              Power plant
Length .-........                               .....-------------   1,027 feet.
Width---............-----        ---------------------               190 feet.
Height (roof to bedrock).............---------------------           190 feet.
Generator (station unit) ...........---------------------            1 4,000-kw. 0.8 power factor.
Generators....            ......    ------------                     2 43,200-kw. 0.9 power factor.
                                                                     8 54,000-kw. 0.9 power factor.
Total rated capacity __--..........            __
                                             ..--.-         ..       518,400-kw. 0.9 power factor.
                         ..................................
Speed..... .........................                           ... . 75 revolutions per minute.
                                                             ...

   The actual cost of the dam, navigation lock, 10-power unit gen-
erating installation, fishways, and attendant buildings and grounds
is $83,210,608, of which $6,072,480 is for navigation facilities,
$39,322,037 is for power facilities, and $37,816,091 is for joint
facilities, consisting of dam, fishways, buildings, and grounds,
and the headwall section of power units 0 to 6, cost of which
 ($2,106,000) is allocated to dam and reservoir facilities. The esti-
mated annual cost approved in 1953 of operation and maintenance
exclusive of improvements, reconstruction, or contingencies, is
$1,215,000. Of this amount $55,000 is for navigation, $560,000
for power and $600,000 for joint facilities.
   The existing project was authorized by the following river and
harbor acts:
     Acts                         Work authorized                                   Documents
                 The existing project was originally authorized Sept.
                  30, 1933, by the Federal Emergency Administra-
                  tion of Public Works.
Aug. 30, 1935    Existing project authorized by Congress-............    Senate committee print, 73d Cong.,
                                                                           2d seas. (Report of Chief of
                                                                           Engineers, dated Aug. 21, 1933.)
Aug. 20,1937     This act authorized the completion, maintenance,
 (Pub. 329,       and operation of the Bonneville project under the
75th Cong.)      direction of the Secretary of War and the super-
                  vision of the Chief of Engineers, subject to certain
                  provisions contained therein relating to the powers
                  and duties of the Bonneville Power Administrator.


   Operations and results during fiscal year. The project was in
continuous operation throughout the fiscal year, with ordinary
maintenance and repairs accomplished as required. The naviga-
tion lock was in continuous operation, except from July 1 to 9:40
a.m. July 3, 1953, to complete cleaning and painting, initiated
the prior fiscal year, and from 8:22 a.m. September 28 to 11:24
a.m. September 30, 1953, for the repair of miter gate seal and
broken electrical conduit.
  Reconstruction of the north shore access road including a new
1416               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

approach connection to U. S. Highway No. 8 was completed Oc-
tober 1953.
   Overhaul of the fishways and the powerhouse fish collection
system stoplog guides and trashracks was also completed.
   A contract was awarded but work not initiated for the con-
struction of cofferdam and restoration of eroded and damaged
baffle deck on the south half of the spillway.
   A total of 432,483 persons visited the project during the fiscal
year.
   Total costs during the fiscal year were $1,539,286.13.
   Condition at end of fiscal year. Construction of the project,
initiated October 1933, was completed February 19, 1953. The
navigation lock was placed in operation in January 1938. The
spillway dam and the first two power units were completed and
placed in operation during the fiscal year 1938. The powerhouse,
with the complete installation of 10 units, was in operation in
December 1943.
   The total costs to June 30, 1954, have been $96,339,795 of
which $83,210,608 was for new work ($39,322,037.26 for power
facilities and $43,888,570.79 for other than power) and $13,129,-
186 for operation and care ($6,684,157.96 for power facilities and
$6,445,028.53 for other than power). The costs of new work
include $32,440,700 emergency funds.
   Power production and revenues. Electrical power energy gen-
erated excepting that portion required for the operation of the
project, is delivered to the transmission lines of the Bonneville
Power Administration for disposition in accordance with the
terms of the iBonneville Act. During the fiscal year 1954, a total
of 4,406,265,000 kilowatt hours was so delivered and 16,327,000
kilowatt hours used for operation of the project, a total of 4,422,-
592,000 generated.
   Total generated by years, in thousands of kilowatt hours, from
1939 through 1954, is as follows:

                                                                                                                Delivered to
                                 Fiscal year                                            Total generation      Bonneville Power
                                                                                                               Administration

1939                                                              -------------------               39, 750                34,874
1940...--- ------------- ----------------- ----                    -----------                     218,063                208,426
1941.         _-----..---------------------------------------                                      907,729                894,177
1942---------         ------------------ ---------------             -------                    1,826,048              1,807,309
1943 ....-------------------           ------------------ - -------------                       2, 815, 954            2, 801, 480
1944 .-----------------------------------------------------                                     3,502,610              3,488,874
1945 ---------------------------------------------------------..                                3. 405, 231            3,391,128
1946 ..--                                                                                       2,691,503              2,674,834
1947------- --------------------                    ----------------------                      3,711,155              3,695,255
1948..--------        -------------------                -----------------------                4,008,064              3,991,  860
1949----------        ---------        .--------------------------------                        3,885,101              3,868,558
1950------------------------------.                                                             3,708,564              3,689,309
1951---------------------------------------------------------                                   3, 811,032             3,793,276
1952-------------------------------- ----------------------                                     4, 480, 174            4, 462, 935
1953----------------------------------4,                                                           242, 522            4, 227, 463
1954---     -------------------------------------------------------                             4, 422, 592            4,406,265



   Receipts from power sales by the Bonneville Power Adminis-
tration are deposited in the United States Treasury as required
by law, but allocated to the project in accordance with memo-
randum-of-understanding with Bonneville Power Administration.
                RIVERS AND HARBORS-PORTLAND, OREG., DISTRICT                                                                   1417
Amounts so allocated are independent of the amount of power
generated and delivered and are designed to cover (1) operation
and maintenance expense applicable to power operations, (2)
interest at the rate of 2.5 percent per annum on that portion
of Government expenditures allocated to power, and (3) sched-
uled repayment of construction cost, including replacements,
allocated to power, over a 50-year period beginning July 1, 1944.
During the fiscal year 1954 the amount of $3,350,000.00 was so
deposited and $276.99 returned to U. S. Treasury by Corps of
Engineers, of which sum the amount of $907,504.23 was for re-
payment of project operating expenses applicable to power,
$1,103,060.96 for repayment of interest expense applicable to
power and $1,339,711.80 for amortization of construction costs,
including replacements applicable to power. As of June 30, 1954,
the sum of $48,825,799.84 has been deposited in the United States
Treasury to the credit of the project, of which $8,969,118.91 was
for repayment of operating expenses applicable to power, $18,-
173,806.13 for interest expense applicable to power and $21,682,-
874.80 for amortization (including replacements) of construction
costs applicable to power. Of a total of $96,339,795.00 expended
to date on the project for construction, operation and mainte-
nance and replacements, the amount of $66,408,879.19 or 69 per-
cent, has been for direct and allocated portions of power features.
   Summary of governmental investments and expenses for power
purposes as of June 30, 1954, and repayments thereon are tabu-
lated below:
                                                                Investment
Construction costs (including interest during con- $59, 618, 627.05
  struction).
Replacements (net retirements)           .........-------- 196, 339. 96
Total cost of fixed plant .-                              ..          -       --....           59, 814, 967.01
Net other assets ..-......... ... ...           .     .     .     .       .    .                    45, 468. 51
         Total capital investment .-......................................                                        $59, 860, 435.52
                                                                Expenses
      Operation and maintenance                           (excluding de-                        8, 969, 118. 91
         preciation).
      Interest-----.........--------------..                                                   18, 173, 806. 13
         Total expenses .... -.....--. ...-.          .    ..     . .         ..............            .. -.-. ........ 27, 142, 925.04

                                                                                                                   87,003,360.56

                                         Repayments
      Total expenses (currently repaid)-...---.............. $27, 142, 925.04
      Amortization of capital investment------..---................. 121, 682, 874.80
        Total repayments             ------------------------------------..--. 48, 825, 799.84
      Net remaining capital investment to be repaid.............--------------...     38, 177, 560. 72

                                                                                                                   87,003, 360.56

  1Represents 36 percent of total capital investment through only 10 years, or 20 percent, of scheduled
payment period has elapsed.
1418          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                       Cost and financial summary
                                             CONSOLIDATED


                                               Fiscal year ending June 30                          Total to June
                                                                                                   30, 1954, includ-
                                                                                                   ing fiscal years
                                1950          1951            1952       1953          1954         prior to 1950


New work:
   Appropriated -...    .   $1, 250, 000   -$412,419     ..-------     -$72, 000        -$976          $83, 210, 608
    Cost----------------       452, 848      655,028        $186,663      18,043     1-175,000          83, 210, 608
Maintenance:
   Appropriated .            1, 047, 000   1, 319, 500     1,110,000   1, 192, 000   1, 676,183          13, 492,711
   Cost----------------         961,636    1,171,291       1,255,367   1,149, 541    1, 539, 286         13,129,186


  1 Represents offset for Derrick Barge Cascade received from military surplus without expenditure, which
isnow distributed to cost.

5. RESTORATION OF INDIAN FISHING GROUNDS, BONNEVILLE,
                         OREG.
   Location. Columbia River between Bonneville and The Dalles,
Oreg., and Wash.
   Existing project. The Secretary of War was authorized, under
such terms and conditions as he may deem advisable, to acquire
lands and provide facilities in the States of Oregon and Washing-
ton to replace Indian fishing grounds submerged or destroyed as a
result of the construction of Bonneville Dam: Provided, That not
to exceed $50,000 may be expended for this purpose from funds
heretofore or hereafter appropriated for maintenance and im-
provement of existing river and harbor works: Provided further,
That such lands and facilities shall be transferred to the Secre-
tary of the Interior for the use and benefit of the Indians, and
shall be subject to the same conditions, safeguards and protec-
tions as the treaty fishing grounds submerged or destroyed.
   The existing project was authorized by the River and Harbor
Act approved March 2, 1945.
   Operationsand results during fiscal year. Completion of drill-
ing a water well at the Lone Pine camp site accomplished all
work at that location. Investigations for the purchase of addi-
tional real estate were continued.
   Total costs for the fiscal year were $1,063.01.
   Condition at end of fiscal year. The project is 72 percent com-
plete. Camp sites for Indian fishing grounds have been con-
structed at Underwood, Wash. and at Lone Pine site in the vicinity
of The Dalles, Oreg. Additional fishing camp sites to be pur-
chased and developed are contingent upon agreements with the
Indians concerned.
   Total costs have been $28,649.00.
              RIVERS AND HARBORS-PORTLAND, OREG., DISTRICT                                          1419
                                       Cost and financial summary

                                              Fiscal year ending June 30                    Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                                1950         1951        1952          1953      1954        prior to 1950

New work:
   Appropriated-----......------------....-------------------------------.....                      $39, 488
   Cost ---------------      $1, 978        $2, 844      $8, 360      $10, 477    $1, 063            28,649

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_------------        $21,064
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955     -------------------------------------------------               21,064

     6. COLUMBIA RIVER BETWEEN VANCOUVER,                                        WASH. AND
                      THE DALLES, OREG.
   Location. On Columbia River, between the Interstate Bridge at
Vancouver, Wash., 106.5 miles above the mouth and The Dalles,
Oreg., mile 191, a distance of 84.5 miles. For description of
Columbia River see page 1437.
   Existing project. This provides for a channel 27 feet deep at
low water and 300 feet wide between Vancouver, Wash., and The
Dalles, Oreg., 85 miles; a channel 10 feet deep at low water and
300 feet wide at the upstream entrance to Oregon slough, Oregon;
a suitable turning basin adjacent to the site of port development
in the vicinity of Camas and Washougal, Wash.; a boat basin at
Hood River, Oreg., 500 by 1,300 feet and 10 feet deep at normal
Bonneville pool level, with a connecting channel of the same depth
to deep water, and a protecting breakwater on the easterly side;
a barge channel to the waterfront at Bingen, Wash., 10 feet deep
at normal Bonneville pool level, 200 feet wide and approximately
1 mile long, and for an access channel 7 feet deep at normal Bonne-
ville pool level, 100 feet wide and approximately 1,000 feet long,
to a natural mooring basin for small boats near the east end of
the channel; and for the construction of The Dalles Harbor, Oreg.,
to provide a breakwater and shear boom protected basin approxi-
mately 400 feet by 800 feet in size with depth of 8 feet below a
pool elevation of 72.5 feet mean sea level.
   The tidal range between mean lower low water and mean higher
high water at Vancouver is about 21/ feet and at Bonneville about
0.2 foot at low stages of the river. Extreme tidal ranges are about
3 feet and 0.4 foot respectively. Annual freshets average about 21
feet at Vancouver, while the highest known stage reached 33 feet
above low water.
   The estimate of cost for new work, revised in 1954 is $6,759,000.
The latest (1953) approved estimate for annual cost of mainte-
nance is $480,000.
1420            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  The existing project was authorized under the following River
and Harbor Acts:

    Acts                           Work authorized                                  Documents
Aug. 26, 1937     Construction of a channel 27 feet deep by 300 feet House Committee Doc. 94, 74th
                   from Vancouver, Wash. to Bonneville, Oreg.          Cong., 2d sess.'
Mar. 2, 1945      Construction of Camas-Washougal turning basin---- H. Doc. 218, 76th Cong., 1st sess.'
July 24, 1946     Construction of a channel 27 feet deep by 300 feet H. Doc. 704, 79th Cong., 2d sess.
                   wide from Bonneville, Oreg., to The Dalles, Oreg.
    Do--.....     Construction of a channel 10 feet deep and 300 feet        Do.
                   wide at the upper entrance to Oregon Slough, Oreg.
    Do-------     Construction of a boat basin at Hood River, Oreg.,         Do.
                   10 feet deep, 500 feet wide, by 1,300 feet long.
    Do -_____     Construction of a barge channel at Bingen, Wash.,          Do.
                   10 feet deep, 200 feet wide, by 1 mile long, and an
                   access channel 7 feet deep, 100 feet wide, by 1,000
                   feet long to natural mooring basin.
    Do-------     Construction of The Dalles Harbor 8 feet deep, 400     S. Doc. 89, 79th Cong.'
                   feet wide by 800 feet long.

  1Contains     latest published maps.


   Local cooperation. The River and Harbor Act approved March
2, 1945, provides in connection with the Camas-Washougal turn-
ing basin that local interests furnish assurances that they will con-
struct a suitable freight terminal, open to all on equal terms, and
bear additional cost of disposing of dredged material behind bulk-
heads provided by them; and provides that no dredging will be
performed by the United States within 50 feet of the proposed
dock.
   The act of July 24, 1946, provides that for improvements at
Hood River, Oreg., and at Bingen, Wash., local interests furnish
free of cost to the United States all necessary rights-of-way, agree
to maintain depths in the basins, and to construct, operate, and
maintain necessary mooring facilities and public wharf available
to all on equal terms. For The Dalles, the act of July 24, 1946,
provides that local interests (1) furnish free of cost to the United
States all lands, easements, and rights-of-way required for new
work, and suitable spoil disposal areas for new work, and for
subsequent maintenance when and as required, (2) provide neces-
sary bulkheads, and (3) agree to construct, maintain, and operate
within the basin suitable moorages and a public landing with
adequate supply facilities, open to all on equal terms. Assurances
of local cooperation for The Dalles Harbor were approved by the
Secretary of the Army October 5, 1948.
   Terminal facilities. The only terminal facilities at present
available or suitable for ocean vessels on the stretch of the river
under the project are at The Dalles, Oreg. The port of Camas-
Washougal has a wharf 528 feet in length at Washougal, Wash.,
which will be available for ocean vessels when an adequate en-
trance channel is provided.
   At the port of The Dalles (mile 44 above Bonneville) there is a
municipal wharf 125 by 1,100 feet for use of both ocean vessels and
river boats. There are two one-story timber and corrugated-iron
warehouses, each 94 by 461 feet, on this wharf with rail connec-
tions. There is also a municipal oil terminal consisting of a
concrete and timber wharf, 27 by 193 feet, located about a mile
below the main wharf. There are private storage tanks with a
               RIVERS AND HARBORS-PORTLAND, OREG., DISTRICT                                         1421
total capacity of 2,300,000 gallons located near this terminal for
handling petroleum products from ocean vessels and river boats.
Storage tanks have rail and truck connections. A private elevator
with a capacity of 40,000 bushels and a public elevator of 868,000
bushels capacity for handling bulk grain to ocean or river craft
are: also located at The Dalles. The public elevator has rail and
truck connections. There is a privately owned rail connection
about three-fourth miles below the municipal wharf where certain
types of cargo may be handled between railroad cars and river
boats or barges, by means of a derrick of 22-ton capacity. The
facilities are considered adequate for present commerce.
    Operations and results during fiscal year. Hydrographic sur-
veys were made at a cost of $5,589.11. Inspections and reports
were made at a cost of $1,954.30.
    Total costs for the fiscal year were $7,543.41, all for mainte-
nance.
    Condition at end of fiscal year. The existing project is approxi-
mately 52 percent complete. Dredging of the main channel
between Vancouver and 'Bonneville was completed to project di-
mensions of 27 feet deep and 300 feet wide in 1949. This channel,
at the present time, is used for barge transportation and log
towing and is maintained to a depth of 15 feet which is adequate
for existing traffic. Depths of 20 feet or more are available be-
tween Bonneville and The Dalles. Construction of The Dalles
Harbor was completed in 1949.
   No construction work has been done on the 27 foot channel
between Bonneville and The Dalles, the channel at the upper
entrance to Oregon Slough, the Camas-Washougal turning basin,
the Hood River boat basin, the Bingen channels, or the improve-
ment of the lower entrance to Bonneville canal.
   Total costs have been $3,658,935, of which $3,074,513 was for
new work and $584,422 for maintenance.
                                  Cost and financial summary

                                         Fiscal year ending June 30                        Total to June
                                                                                           30, 1954, includ-
                                                                                           ing fiscal years
                           1950        1951            1952       1953           1954        prior to 1950


New work:
   Appropriated       .               -$304, 280 .--               -         -     -            $3,074, 513
   Cost                    $79,008                                       -                       3,074,513
Maintenance:
   Appropriated .... - .   53,314       56, 331        $48, 013   $55, 200       $8, 300           585,916
   Cost-----------------   53,314       56,331          48,013     54,462         7, 543           584,421


Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project__                                              $3,684,486

    7. WILLAMETTE RIVER, ABOVE PORTLAND, AND YAMHILL
                       RIVER, OREG.

  Location. The Willamette River rises in the Cascade Range in
southwestern Oregon, flows northerly, and empties into the Colum-
bia River about 100 miles from the sea. Its length from the source
of the Middle Fork is about 294 miles. (See U. S. Coast and Geo-
1422                    REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

detic Survey Chart No. 6155 and the U. S. Geological Survey map,
State of Oregon.)
   The Yamhill River rises in the Coast Range, flows easterly, and
empties into the Willamette River about 42 miles above Portland.
Its length from the source of the South Fork is about 52 miles.
   Previous projects. Adopted by the River and Harbor Acts of
March 3, 1871, and July 13, 1892. For further details, see page
1997 of Annual Report for 1915, and page 1754 of Annual Report
for 1938.
   Existing project. This provides for improvement of Willam-
ette River between Portland (14 miles above the mouth) and
Oregon City (26 miles above the mouth) by a channel 8 feet deep
at low water, 200 feet wide below Cedar Island and 150 feet wide
thence to Oregon City; for such channel improvement and contrac-
tion works as may be necessary to secure, with stream flow regula-
tion, controlling depths of 6 feet at low water from Oregon City
to the mouth of Santiam River (108.5 miles above the mouth), and
5 feet from that point to Albany (120 miles above the mouth) ; and
for a channel 2 to 21/2 feet deep from Corvallis to Eugene (53
miles) ; for a channel 3.0 to 3.5 feet deep at low water and of no
prescribed width from Albany to Corvallis (132 miles above the
mouth) ; and for necessary snagging between Corvallis and Harris-
burg (163 miles above the mouth). The project also provides
for a channel in the Yamhill River 4 feet deep at low water and
60 feet wide from its mouth to McMinnville (18 miles) to be
secured by means of a lock and dam near Lafayette and the re-
moval of obstructions. The section of Willamette River in the
vicinity of Willamette Falls at Oregon City is covered by a project
described on page 1425 of this report.
    The following table shows the principal features of the lock and
dam in Yamhill River:
Location..-----..............---------------...                  miles below Lafayette, Oreg., 8
                                                                                1
                                                               miles above the mouth.
Usable lock dimensions ......              .............    1 lock, 175 by 38 feet.
                                            --------------- 16 feet.
Lift of lock --------.....................---
Depth on sills at low water.......--------------.......- 4 feet on upper sill; 2 feet on lower sill.
Character of foundation .-......----------------.....       Timber piling in clay.
Kind of dam -......-..                            .   .   -------------------   Fixed.
Type of construction...........     - -..--........ Timber crib.
Date of completion ...-......................      . Sept. 21, 1900.
Cost..... .....---------------.....
                     .---------------                 72,164.83.
   For the Willamette River below the falls at Oregon City ordi-
nary fluctuation of stage of water is 15 feet and the extreme fluc-
tuation due to flood conditions 35 to 50 feet. Above Oregon City
the ordinary fluctuation is 12 to 20 feet and the extreme is 20 to 27
feet. For the Yamhill River the ordinary fluctuation is 35 feet and
the extreme 48 feet. Tidal changes vary from about 21/2 feet
at the mouth of the Willamette to zero, 26 miles above the mouth.
   The approved estimate (1954) of cost for new work is $2,485,-
000. The latest (1953) approved estimate of annual cost of main-
                  RIVERS AND HARBORS--PORTLAND, OREG., DISTRICT                                       1423
tenance is $547,000 including $15,000 for operation and care of
the lock and dam in Yamhill River. For information concerning
the comprehensive flood control plan for Willamette River Basin
see page 1454.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                         Work authorized                                   Documents


June 3,1896        Improvement of Willamette River above Oregon          H. Doc. 260, 54th Cong., 1st sess.
                     City.                                                (Annual Report, 1896, p. 3309).
   Do-.......      Improvement of Yamhbill River by lock and dam         Annual Report, 1895, p. 3602.
                    construction.
                   Project modified in 1904 by abandoning the 20-mile    Annual Report, 1904, p. 3529.
                    stretch of the river between Harrisburg and Eugene
                     as unworthy of improvement.
July    25,1912    For a 6-foot channel in the Willamette River below    H. Doc. 438, 62d Cong., 2d sess.
                    Oregon City.
July    3, 1930    For the 8-foot channel between Portland and Oregon    H.     Doc. 372, 71st Cong., 2d sess.
                     City.                                                    (Contains latest published map.)
June 26,1934 '     Operating and care of the lock and dam in Yamhill
                 River and provided for with funds from War De-
                 partment appropriations for rivers and harbors.
June 28,1938 2 Stream flow regulation with controlling depths of 6       H. Doc. 544, 75th Cong., 3d sess.
                 feet to the mouth of Santiam River and 5 feet to
                     Albany with enlargement of locks at Oregon City.

  1 Permanent Appropriations Repeal Act.
  2 Flood Control Act.




   Terminal facilities. Between Portland and Willamette Falls
the terminal facilities consist of privately owned mill wharves,
sand and gravel wharves, and oil receiving stations. Above the
falls there are privately owned landings including a facility at pulp
siding (3 miles above the falls) with rail and water connections
for shipment of clay and receipt of paper mill products, by barge.
About 5 miles downstream from Albany there is a newly con-
structed tank farm of 1,367,100-gallon capacity with truck and
water connection which receives petroleum by barge from Port-
land. At numerous locations over the entire waterway there are
log rollways with water and rail or truck connections to facilitate
the movement of logs to mills in the lower Columbia and William-
ette Rivers. These facilities are considered adequate for existing
commerce.
   Operations and results during fiscal year. Dredging by hired
plant and dredging and snag removal by Government plant and
hired labor maintained sufficient depths for the requirements of
present navigation.
   Releases of storage water from the completed Fern Ridge, Cot-
tage Grove, Detroit and Dorena Reservoirs aided materially dur-
ing low water periods in providing sufficient depths for existing
traffic. For more detailed information on reservoir releases see
pages covering those reservoirs.
   Because of lack of use by commercial traffic for which the facili-
ties were originally provided operation of Yamhill Lock was dis-
continued on February 7, 1954.
1424        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 19 4

   The various items of maintenance and their costs during the
fiscal year were as follows:
    Maintenance:
        Dredging by Government plant, a total of 743,200 cubic yards
          removed----------------.......                                        $330, 989. 17
                                         ...................... ----------------------
        Leveling and disposal of dredge material .............................
                                                         -                        13, 005.01
                                                                        .
        Snagging in Willamette and Yamhill Rivers ..........-----------------..    7, 931.82
        Inspections and reports....          --------------------------------      4,350.23
       Hydrographlc surveys by Government plant................---------------.   26, 937. 52

               Total maintenance . ... .................
                                       ..              .....    .....               383, 213. 75
    Operation and care of Yamhill Lock:
        Operation..------------------------------------------3,773.81
        Maintenance and repair of structures and grounds..............-------------      657.20

                 Total operation and care-------................-------------------   4,431.01


    Total costs for the fiscal year were $387,644.76, of which $383,-
213.75 was for maintenance and $4,431.01 for operation and care.
    Condition at end of fiscal year. The existing project is approxi-
mately 65 percent complete. The 8-foot channel between Port-
land and Oregon City and the 21/ to 31/2 -foot channel between
Oregon City and Albany were completed in 1939. The 21/2 to 31/2-
foot channel between Albany and Corvallis was completed in 1945.
The remaining work required to complete the project consists of
the construction of such contraction works and channel improve-
ments as may be necessary, with stream-flow regulation, to secure
controlling depths of 6 feet at low water from Oregon City to the
mouth of Santiam River, and 5 feet from that point to Albany.
Controlling depths at low water are 8 feet from Portland to Ore-
gon City, and 31/2 feet from Oregon City to Corvallis. In Yamhill
River, the controlling depth is 4 feet from the mouth to Yamhill
Lock.
   Traffic is confined to towboats, log rafts, launches, and dredges.
Between Oregon City and Pulp Siding (about 3 miles) and be-
tween Oregon City and Portland, barges are used in the transpor-
tation of paper and wood-pulp products.
   The Yamhill Lock and grounds are in fair condition. Operation
of the lock was discontinued February 7, 1954.
   Total costs under the existing project, from Federal funds, have
been $7,513,782, of which $615,170 was for new work, $6,754,484
for maintenance and $144,128 for operation and care. In addi-
tion, the sum of $106,433 was expended between September 24,
1900, and June 30, 1935, on operation and care of works of im-
provement under the provisions of the permanent indefinite ap-
propriations for such purposes. An additional sum of $7,500 was
expended from contributed funds for maintenance and $484,900
from Emergency Relief Administrative funds for new work.
                  RIVERS AND HARBORS-PORTLAND,                                           OREG., DISTRICT                    1425
                                               Cost and financial summary

                                                           Fiscal year ending June 30                             Total to June'
                                                                                                                  30, 1954, includ-
                                                                                                                  ing fiscal years'
                                        1950             1951            1952            1953          1954        priorto 1950

New work:
   Appropriated--------------------------------------------------                                      -                $   862,917
   Cost .--------- ------------                   ------------ -----------------------------------                          862,917
Maintenance
   Appropriated           - -         $400, 374          $357, 250     $358, 765       $357, 000      $405, 800          7,031,314
   Cost----------------                399, 712           423, 291      364,478         349, 798       387,645           7,005, 045

   1Includes $247,748 for new work for previous projects.
  .2 In addition $484,900 was expended from ERA flood control funds for bank protection for new work and

$7,500 for maintenance was expended from contributed funds.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project _                  -    $1,384,930

        8. WILLAMETTE RIVER AT WILLAMETTE                                                            FALLS, OREG.
   Location. The locks and the dam covered by this project are
located at Willamette Falls, a rocky reef in the Willamette River
at Oregon City, Oreg., about 26 miles above the mouth of the river.
   Existing project. This provides for the construction of a new
single-lift main lock and a guard lock each with clear dimensions
of 56 feet by 400 feet and minimum depth over the sills of 91/2
feet, to replace the authorized existing facilities which were pro-
vided for by the purchase, rehabilitation, and deepening to 6 feet
at low water of the existing canal and locks and the separation of
the canal from the waterpower intake by construction of a concrete
division wall. The total length of the existing canal and locks is
about 3,500 feet.
   The following table shows the principal features of the existing
canal and locks at Willamette Falls:
Usable lock dimensions------..                                  ---........Series of 4 locks, each 175 by 37 feet.'
Lift of each lock---------._...                              ----....-....Lock 1 (lower), 22.5 feet; 2 lock, 2, 8.7 feet; lock
                                                                             3, 10.9 feet; lock 4 (upper), 8.1 feet.
Depth on miter sills at low water -- Lower lock, 8.4 feet; upper lock, 6 feet.
Character of foundation-------                    ........--...            Rock.
Kind of dam- ..-......                          _..........----------Fixed.3
Type of construction .......                                               Concrete.
                                                                 ..------------
Year of completion ........----------------                                1873; purchased by United States Apr. 26, 1915.
Cost ------.......................................-----------------. Unknown; purchase price, $375,000.
  1 A guard lock 210 by 40 feet, which is used only at higher stages of water, is located at the upper end
of the canal basin.
  2 A concrete division wall. 1,227 feet long, extending from lock 4 to the guard lock, separates the upper
basin of the canal from the head race, which formerly led directly from the basin and supplied water for
the power plants operated by the Crown Willamette Paper Co. and the Portland Ry., Light & Power Co.
  3 The dam is owned by private parties.

  The ordinary fluctuation of the stage of water above the locks is
12 feet, and the extreme, due to flood conditions, 20 feet. Below
the locks the ordinary fluctuation is 15 feet and the extreme 50 feet.
  The estimated cost, revised in 1954, is $10,200,000. The latest
(1953) approved estimate of annual cost of operation and care is
$228,000.
1426             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  The existing project was authorized by the following river and
harbor acts:

       Acts                             Work authorized                                          Documents

June 25,1910      For the purchase and rehabilitation of the system                H. Doc. 202, 56th Cong., 1st sess.,
                    and the construction of the concrete division wall.              and Annual Report, 1900, p. 4374.
Aug.    8,1917    Deepening of the locks...............................            H. Doc. 1060, 62d Cong., 3d sess.'
June 26, 1934 2 Operation and care of the canal and locks provided
                 for with funds from War Department appropria-
                 tions for rivers and harbors.
Mar. 2, 1945 Construction of the New Willamette Falls lock-..... H. Doc. 544, 75th Cong., 3d sess.

   I Contains latest published maps.
  ' Permanent Appropriation Repeal Act.


   Local cooperation. Fully complied with.
   Terminal facilities. The Crown Willamette Paper Co. has a
timber wharf about 850 feet in length, extending to and supported
by the concrete division wall built in the lock canal by the United
States. This wharf is used for the receipt of mill supplies and the
shipment of paper and paper products.
   Operations and results during fiscal year. The existing canal
and locks were in continuous operation throughout the fiscal year,
except for the periods 8:00 a.m., September 22 to 8:00 a.m., Sep-
tember 25, 1953, and 8:00 a.m., to 4:30 p.m., for the eight consecu-
tive working days (exclusive of Saturday and Sunday) from
September 1 to September 11, 1953. On October 23, 1953, be-
tween 8:00 a.m. and 4:30 p.m. the locks below the basin were
closed for gate No. 3 replacement.
   The various items of operation and care and their costs were as
follows:
Operation of locks and canal ............ ................. .... $136, 957. 36
Ordinary maintenance and repair...........             .           ...........................            7, 067.03
Improvement and reconstruction ...........................................                               44, 322. 17

          Total... .....         ..................                              ...................    188, 346.56

   Total costs for the fiscal year were $188,346.56 for operation and
care.
   Condition at end of fiscal year. The existing canal and locks
were originally constructed by private interests in 1873 and pur-
chased April 26, 1915, by the United States for $375,000. The dam
is owned by private interests. The final report on the purchase
and rehabilitation of the existing locks and canal was given in the
Annual Report for 1923, when the project was reported 98 percent
complete. No further work on that existing project has been
considered necessary. The controlling depth is 6 feet at low water
on the miter sill of the upper lock. The existing locks and grounds
are in fair condition and are in continuous operation except when
flooded out by high water or undergoing repair. The facilities
are obsolete and inadequate for existing traffic.
   The original manually operated lock gates have been converted
to hydraulic opening and closing but the operation of the gate wick-
ets is still manual. During the fiscal year 1951 the height of the
                 RIVERS AND HARBORS-PORTLAND,                                           OREG., DISTRICT                       1427
easterly wall of the guard lock was raised three feet permitting
use of the lock to elevation 14.5.
   No construction work has been done on the lock and guard lock,
which was authorized to replace the existing facilities, by the
Flood Control Act of June 28, 1938, and the River and Harbor Act
of March 2, 1945. Plans and specifications for the work have been
essentially completed, but will require review and some revision.
   Total costs have been $2,652,067 of which $520,005 was for new
work ($377,122.20 for purchase and rehabilitation of existing lock
and canal and $3,882.88 for new lock from River and Harbor
funds and $139,000 for new lock from Flood Control funds) and
$2,132,063 for maintenance (operation and care) from River and
Harbor funds.
   In addition $300,000 was expended from contributed funds for
new work on existing canal and lock and $452,109.76 was expended
between April 16, 1915, and June 30, 1935, on the operation and
care of works of the improvement under the provisions of the
permanent indefinite appropriations for such purposes.
                                               Cost and financial summary

                                                         Fiscal year ending June 30                                 Total to June
                                                         _        -30,                                                 1954, includ-
                                                                                                                    ing fiscal years
                                        1950            1951              1952           1953            1954        prior to 19501


New work:
                ........----------
   Appropriated------                    -$35, 617 ........--------...........------------------------...........         $   520,005
   Cost---- --          --------------------------------------------                        ---------------                   520,005
Maintenance:
                      ------
       Appropriated--........         $182,710          144,000          $146,114      $182, 000        $192, 500          2, 614,484
       Cost--.--------------           179702           128,116           161,364        159, 483        188,347           2,584,172

   1   In addition $300,000 for new work was expended from contributed funds.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project-_.-------               $9,715,700

         9. COLUMBIA AND LOWER WILLAMETTE RIVERS BELOW
               VANCOUVER, WASH., AND PORTLAND, OREG.
  Location. This project embraces 1031/ miles of Columbia River
below Vancouver, Wash., and 14 miles of Willamette River below
Portland, Oreg. For description of Columbia River see page 1437,
and of Willamette River, page 1421.
  Previous project. Some relief dredging was done between 1866
and 1876. Projects were adopted by the River and Harbor Acts of
June 18, 1878; July 13, 1892; June 13, 1902; and March 3, 1905.
For further details see pages 1995 and 1998 of Annual Report for
1915, and page 1746 of Annual Report for 1938.
  Existing project. This provides for a channel 35 feet deep and
500 feet wide in the Columbia River from its mouth to the mouth
of the Willamette, 101.5 miles, and thence up Willamette River to
Broadway Bridge at Portland 12 miles; 30 feet deep and 300 feet
wide from Broadway Bridge to Ross Island, 14 miles above the
mouth of Willamette River to be maintained by the port of Port-
land. The existing project also provides for maintenance at not
to exceed a depth of 35 feet at low water, over such areas in the
1428               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Portland harbor and Willamette River between its mouth and
Broadway Bridge as have been or may be dredged to project depth
by the port of Portland; no dredging, however, shall be done by the
United States within 50 feet of the pierhead line. In addition, the
existing project also provides for the following: A channel 30 feet
deep and 300 feet wide in the Columbia River from the mouth of
the Willamette River to the interstate highway bridge at Van-
couver, Wash., about 5 miles, with two turning basins of the same
depth at Vancouver, 800 feet wide and approximately 2,000 and
3,000 feet long for the upper and lower basins, respectively, auxili-
ary channels 10 feet deep and 300 feet wide in the vicinity of Cath-
lamet, Wash., 30 feet deep and 300 feet wide in St. Helens (Oreg.)
Channel, and 30 feet deep and 500 feet wide connecting the upper
end of the St. Helens Channel with the main ship channel of the
Columbia; 24 feet deep and 200 feet wide along the frontage of
the town of Rainier, Oreg., extended at its upper and lower ends
to deep water in the Columbia River, 8 feet deep and 150 feet wide
from this depth in Columbia River through the old mouth of Cow-
litz River to a point approximately 3,000 feet upstream from the
present terminus of the harbor line; a channel from the Longview
Port dock downstream along the pierhead line and past the Weyer-
haeuser Timber Co.'s plant at Longview, to a connection with the
main ship channel below Mount Coffin the downstream 2,400 feet
of this channel to be 30 feet deep and 300 feet wide and the re-
mainder to be 28 feet deep and 250 feet wide; construction of a
small boat mooring basin at Astoria, Oreg., to include a sheet
pile, sand-filled breakwater about 2,400 feet long with a 30-foot
roadway along its full length, and steel-pile shore wings totaling
about 1,460 feet in length; and for the construction of stone and
pile dikes and revetments.
    The plane of reference in the estuary from the mouth to Har-
rington Point is mean lower low water; thence to Portland and
Vancouver, low water. The tidal range between mean lower low
water and mean higher high water at the mouth of the Columbia
is about 8 feet, and at Portland and Vancouver about 21/2 feet at
low stages of the rivers. Extreme tidal ranges are about 13 feet
and 3 feet, respectively. Annual freshets have but little effect on
depths at the mouth of the Columbia; at Portland and Vancouver
they average about 20 feet, while the highest known reached a
stage of 33 feet above low water at Portland.
    The actual cost for new work, exclusive of amounts expended
under previous projects and contributed funds, is $5,384,677. The
latest (1953) approved estimate for annual cost of maintenance is
 $1,845,000.
    The existing project was authorized by the following River and
Harbor Acts:
       Acts                            Work authorized                                          Documents
June: 18, 1878      Dike at St. Helens Bar ....-       _                      ....
                                                               _-.................   Annual Report, 1877, p. 1019.
July    13,1892     For the closing dike at head of Oregon Slough and                H. Does. 36 and 38, 52d Cong.
                     dikes at Deer Island and Walker Island.............              1st sess.
June    13,1902     Replacing the revetment of Coon Island.......-----------... H. Doc. 673, 56th Cong., 1st sess.
Feb.    27,1911     2 pipeline dredges and accessories..... .......
July    25, 1912    Increasing the main channel depth to 30 feet .-             H. Doc. 1278, 61st Cong., 3d sess
                                                                                H.....
July    27, 1916    Consolidating the improvements below Portland, No prior report.
                      Oreg., and between Vancouver, Wash., and the
                      mouth of the Willamette.
                  RIVERS AND HARBORS-PORTLAND,                            OREG., DISTRICT              1429

       Acts                         Work authorized                                    Documents
                                                                                                ,
                                                                                                                  1
Aug. 8,1917       For the Cathlamet Channel....--------      ----------    H. Doec. 120, 63d Cong., 1st sess.
Sept. 22, 1922    Construction of an additional dredge (dredge was         H. Doec. 1009, 66th Cong., 3d sess.
                   not built) and accessories for better maintenance,
                   and the construction of contraction works.
Mar. 4, 1923 s    Channel from deep water in Willamette Slough to          H.   Doec. 156, 67th Cong., 2d sess.
                    deep water in Columbia River.
Mar. 3, 1925      Depth of 25 feet and width of 300 feet from mouth of     H. Doe. 126, 68th Cong., 1st sess.
                   the Willamette River to Vancouver, Wash.
Mar. 3,1927       Closing of the east channel at Swan Island in the        Rivers and Harbors Committee
                   Willamette River on condition that the main chan-        Doc. 10, 69th Cong., 2d sess.
                   nel to be opened to project dimensions on the west
                   side of the island by the port of Portland.
July    3, 1930   For a 35-foot channel 500 feet wide from Portland to     H. Doec. 195, 70th Cong., 1st sess.,
                   the sea.                                                  and Rivers and Harbors Comr
                                                                             mittee
                                                                                  1  Doe. 8, 71st Cong., 1st
                                                                             sess.                           1
Sept. 6, 1933 3
              A channel 28 feet deep and 300 feet wide from the            H. Doec. 249, 72d Cong., 1st sess.
               mouth of the Willamette River to Vancouver, with
               2 turning basins, each generally 28 feet deep by 800
               feet wide by 2,000 feet long.
Aug. 30,1935 A channel in the Columbia River from mouth of the             Rivers and Harbors Committee
               Willamette to the Interstate Highway Bridge at                Doec. 1, 74th Cong., 1st sess.
               Vancouver, Wash., 30 feet deep and 300 feet wide,
               with 2 turning basins at Vancouver.
    Do....... Maintenance of not to exceed 35-foot depth at low            Rivers and Harbors Committee
               water in Portland Harbor and Willamette River                 Doec. 6, 73d Cong., 1st sess.'
               between its mouth and Broadway Bridge at Port-
               land.
    Do......  Auxiliary channels, 30 feet deep, 300 and 500 feet at        H. Doe. 235, 72d Cong., 1st sess.'
               St. Helens.
Aug. 26, 1937 Extension of the lower turning basin at Vancouver,           Rivers and Harbors Committee
               Wash., 1,000 feet downstream.                                 Doec. 81, 74th Cong., 2d sess.'
    Do .... An auxiliary channel 24 feet deep and 200 feet wide            H. Doec. 203, 75th Cong., 1st sess.'
               along the water front at Rainier, Oreg.
Mar. 2, 1945 Improvement of old mouth of the Cowlitz River ...             H. Doec. 341, 77th Cong., 1st sess.x
    Do ..... An auxiliary channel in the vicinity of Longview,             H. Doec. 630, 77th Cong., 2d sess.'
               Wash.
July 24,1946 A small-boat mooring basin at Astoria, Oreg ...---            H. Doec. 692, 79th Cong., 2d sess.'


   SContains latest published maps.
  2 Public Res. 105, 67th Cong.
    Public Works Administration.


  Local cooperation. Requirements of cooperation prior to 1945
have been fully complied with. The act of July 24, 1946, authoriz-
ing the construction of a small-boat mooring basin at Astoria,
Oreg., provides that local interests furnish assurances to the
United States that they will furnish free of cost all necessary
lands, easements, and rights-of-way for the new work and subse-
quent maintenance when and as required; provide all necessary
mooring facilities within the basin, sewers, water and electric
supply lines, and a public landing with suitable supply facilities
open to all on equal terms.
   Assurances for the small-boat basin at Astoria were approved
on November 4, 1947. Local interests have provided some moor-
ing facilities, and public landings.
  Terminal facilities. At Portland, Oreg., there are under public
ownership and open to all on equal terms, three terminals for
handling general cargo, bulk grain, coal, phosphate, lumber, oils,
and similar commodities. Extensive modernization and rehabilita-
tion of these public facilities are planned for the immediate future
as a result of the outcome of the May 1954 primary election when
a 6.5-million dollar expenditure of public funds was authorized for
this work. Under private ownership and operation there are 5
general cargo, 5 flour and grain, 6 lumber, 1 cement, 1 bulk creo-
sote, 1 salt, and 10 fuel oil and gasoline wharves and piers, besides
outfitting and repair, sand and gravel, and construction equipment
1430     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

wharves. Three of the private general cargo terminals subscribe:
to Commission of Public Docks Terminal Tariff 2A and four of the
five flour and grain facilities publish terminal tariffs and may
therefore be considered to be open to the public on equal terms.
The port of Portland Commission, a State of Oregon agency, has
recently completed at Swan Island, modern ship repair and outfit-
ting facilities complete with three dry docks, one of 2,000-ton, one
of 12,500-ton and one on long term lease from the U. S. Navy of
14,000-ton capacity. Also available at this facility and available
to the public on equal terms are five rail mounted gantry cranes
each of 45-ton capacity, and one truck mounted crane, as well as
machine shops, rail lines, staging, compressed air, steam, elec-
tricity and water. Seven berths are available at the outfitting dock
of this facility which is open to all on equal terms. Also located
within the harbor are one dry dock of 85-ton capacity, three pri-
vately owned marine railways for handling small vessels and
barges, as well as several skid-type haulouts on which launches and
other small craft can be accommodated. Heavy lift equipment at
the general cargo wharves include 10 locomotive cranes and auto
cranes with up to 35-ton capacity, one 150-ton swinging boom
derrick, one 100-ton swinging boom derrick, one 100-ton shear-leg
derrick crane, two 35-ton traveling gantry cranes and two 75-ton
floating cranes.
    At Astoria, Oreg., there is a large municipal terminal with grain
elevator and flour mill, facilities for receiving oil products by
tanker, and bunkering of vessels. There are also private wharves
used for receipt of fish, sand and gravel, and bunkering of fishing
vessels.
    At Vancouver, Wash., below Interstate Bridge, there are two
municipal terminal wharves. There are also several privately
owned wharves for the shipment of lumber, a fuel and gasoline
terminal, and a privately owned grain elevator and wharf.
    The port of Longview has a public terminal on the Columbia
River at Longview, Wash., and the Long-Bell Lumber Company
and Weyerhaeuser Timber Company have wharves in the same
vicinity for the shipment of lumber. A privately operated grain
elevator for shipment of grain is located at the port terminal; a
fuel oil and gasoline terminal is also located at the port dock for
the receipt of petroleum products. There is a heavy lift of 125-ton
capacity at the public terminal.
    At other locations on the Columbia River between Portland and
Columbia River entrance, there are sufficient private facilities to
accommodate the river vessels and fishing craft, and at seven
points there are large sawmill docks used exclusively for shipment
of lumber in ocean-going vessels.
    These facilities, with planned extensions, are considered ade-
quate for existing commerce. (For further details see Port Series
Nos. 33 and 34, Corps of Engineers, published in 1953 and 1954,
respectively.)
    Operationsand results during fiscal year. Maintenance: Dredg-
ing with Government plant and hired labor was done on all bars
and shoals in the main and side channels where condition surveys
indicated shoaling. A total of 7,450,700 cubic yards of material
                RIVERS AND HARBORS-PORTLAND,                                                  OREG., DISTRICT                    1431
was removed at a cost of $1,235,183.42, and hydrographic condi-
tion surveys were made at a cost of $69,037.80. Inspections and
reports were made at a cost of $40,023.80 and minor repairs to
dikes and engineering cost $25,046.67. Bank stabilization on
Sauvie Island was completed at a cost of $16,104.00.
   Total costs for the fiscal year were $1,385,395.69, all for main-
tenance.
   Condition at end of fiscal year. The existing project was com-
pleted on September 29, 1950. The main channel project was
completed in 1933, except that a revision at Harrington Point was
made in 1935. The dikes were completed in 1935 and the extension
of the Vancouver turning basin in 1939. The auxiliary channel in
the vicinity of Longview was completed in 1949, and the improve-
ment of the old mouth of Cowlitz River and the small boat mooring
basin at Astoria were completed in 1950.
   The controlling depth at low water in Columbia River from its
mouth to the mouth of Willamette River is 34 feet. Above the
mouth of Willamette River the Vancouver channel has a controlling
depth of 30 feet and in Willamette River from its mouth to Broad-
way bridge the controlling depth is 33 feet. Project depths are
maintained throughout the year except during short shoaling
periods following freshets which generally occur in May, June, and
July.
   In Columbia and Willamette Rivers between the mouth and
Broadway bridge at Portland a draft of 32 feet at low tide and 35
feet at high tide is practicable throughout the year. In Columbia
River between the mouth of Willamette River and Vancouver,
Wash., drafts of 26 and 28 feet at low and high tide, respectively,
are practicable throughout the year.
   Total costs under the existing project to June 30, 1954, have been
as follows:
                                                                              New work             Maintenance               Total


United States Funds:
    Regular funds--................-------- -----------------------                4, 799, 932          24, 287, 277          29, 087, 209
    Public works funds-......------------------------------                           446, 296    ..----------------              446, 296
    Emergency relief administration funds                             ._             138, 449               98, 668                  237, 117
           Total U. S. funds...------------              --------------            5, 384, 677         24, 385, 945           29, 770, 622
Contributed funds...........---------------------------------..                      223, 026               24, 320                  247, 346
           Total all funds .----------------------------..                         5, 607, 703         24, 410, 265           30, 017, 968


                                                 Cost and financial summary

                                                            Fiscal year ending June 30                                   Total to June
                                 .            ..-....                        _3                                         30, 1954, includ-
                                       1950               1951             1952           1953             1954
                                                                                                                        ing fiscal  years
                                                                                                                        prior to 1950 12


New work:
   Appropriated -.--
   Cost---_----------
                             _        $150, 000
                                     1,273,746
                                                        -$97, 000
                                                           16,060
                                                                       -$9, 578         .--   -                              $6, 914, 090
                                                                                                                              6,914,090
Maintenance:
    Appropriated    --  -            1,543, 560         1,296,297     1,162,134       $1, 623,200      $1,383, 975           25, 621,948
    Cost- ---------------            1,660, 559         1, 318, 572   1,171, 453       1,603, 954       1, 385, 396 .        25,600,810

1Includes $1,529,413 for new work and $1,214,865 for maintenance for previous projects.
SIn addition $223,026 for new work and $24,320 for maintenance was expended from contributed funds.
1432           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                               10. COWLITZ           RIVER, WASH.
   Location. This river rises in the Cascade Range in Washing-
ton, flows westerly and southerly about 120 miles, and empties in
the Columbia River about 69 miles from the mouth. (See U. S.
Coast and Geodetic Survey Chart No. 6153.)
   Previous projects. Adopted by the River and Harbor Act of
June 14, 1880. For further details see page 2000 of Annual Report
for 1915 and page 1763 of Annual Report for 1938.
  Existing project. This provides for a channel 4 feet deep at low
water and 50 feet wide from the mouth to Ostrander (9 miles),
thence 2     feet deep and 50 feet wide to Castle Rock (10 miles),
and thence 21/ feet deep at low water and not less than 40 feet wide
to Toledo (18 miles), to be secured by snagging, dredging, and
regulating works. The water level, due to tides, varies from 4 feet
at the mouth to zero at Ostrander. During ordinary freshets a
stage of 20 feet, and at extreme floods a stage of 25 feet, is reached
in the river at Kelso, Wash.
   The actual cost for new work was $32,906.62, exclusive of
amounts expended on previous projects. The latest (1953) ap-
proved estimate for annual cost of maintenance is $40,000.
   The existing project was adopted by the River and Harbor Act
of June 25, 1910 (H. Doc. 1167, 60th Cong., 2d sess., from the mouth
to Castle Rock, and H. Doc. 404, 61st Cong., 2d sess., from Castle
Rock to Toledo). For the latest published map see House Docu-
ment 1167, 60th Congress, 2d session.
   Recommended modifications of project. The Chief of Engineers
has recommended that the project be modified by the elimination
of all work above Castle Rock (H. Doc. 467, 69th Cong., 1st sess.).
   Terminal facilities. Terminal facilities consist of privately
owned and operated landing and log rollways which are considered
adequate for the existing commerce.
   Operations and results during fiscal year. Hydrographic sur-
veys were made and shore controls established.
   Total costs for the fiscal year were $3,434.
   Condition at end of fiscal year. The existing project was com-
pleted in 1913. The channel is maintained to the project depth of
4 feet between the mouth and Kelso, Wash. Above Kelso the
channel is in poor condition with a controlling depth at low water of
2 feet.
   Total costs for the existing project have been $360,518, of which
$32,908 was for new work and $327,610 for maintenance.
                                      Cost and financial summary

                                             Fiscal year ending June 30                         Total to June
                                                                                               30, 1954, includ-
                                                                                               ing fiscal years
                               1950         1951         1952         1953         1954         priorto 19501


New work:
   Appropriated.------------.....       --------------------------------------              ------- $ 37,907
   Cost......--- ---------.......---------------------------------- ---------------- ------           37,907
Maintenance:
    Aparopriated ....          $29, 093     $25,789 ------------------------         $4, 000            876, 360
    Cost ..  -------            29, 093      25,789 ------------------------          3,434             375, 794

  1Includes $4,999 for new work and $48,184 for maintenance for previous projects.
                 RIVERS AND HARBORS-PORTLAND, OREG., DISTRICT                                        1433
                            11. SKIPANON CHANNEL,                     OREG.
  Location. This channel is a tidal waterway extending south 2.7
miles from deep water in Columbia River. The channel enters the
Columbia about 10 miles above its mouth and 4 miles below
Astoria, Oreg. (See U. S. Coast and Geodetic Survey Chart No.
6151.)
   Existing project. This provides for a channel 30 feet deep and
generally 200 feet wide extending from deep water in Columbia
River to the railroad bridge at Warrenton, Oreg., a distance of
1.8 miles, for a turning basin of the same depth, a mooring basin
12 feet deep at mean lower low water at Warrenton, Oreg.; and
for a channel 6 feet deep and generally 40 feet wide, with in-
creased widths at log dumps and terminals, for a distance of
4,500 feet, via cutoff channel, above the railroad bridge. Mean
lower low water is the plane of reference. The tidal range be-
tween mean lower low water and mean higher high water is about
8 feet; the extreme tidal range is about 13 feet.
   The estimate of cost of new work revised in 1954 is $315,000.
The latest (1952) approved estimate of cost for annual mainte-
nance is $48,000.
   The existing project was authorized by the following River and
Harbor Acts:

       Acts                        Work authorized                                   Documents 1
July    3,1930    Channel from deep water in Columbia River to the        H. Doc. 278, 70th Cong., 1st sess.
                   railroad bridge.
Aug. 26, 1937     For the channel extending upstream from the rail-       H. Doc. 201, 75th Cong., 1st sess.

June 30, 1948
                   road bridge a distance of 4,500 feet.
                  For a mooring basin 12 feet deep at Warrenton....   -   S. Doc. 93, 80th Cong., 1st sess.


  'Contains latest published maps.

   Local cooperation. Requirements contained in River and Har-
bor Acts of July 3, 1930, and August 26, 1937, have been fully
complied with.
   The River and Harbor Act approved June 30, 1948, Public Law
858, provides in connection with the mooring basin that before
construction is initiated, responsible local interests give assur-
ances satisfactory to the Secretary of the Army that they will (1)
provide without cost to the United States all lands, easements, and
rights-of-way necessary for the construction of the project and
subsequent maintenance thereof, (2) hold and save the United
States free from damages due to the construction work, (3)
maintain project depth in the basin after completion, and (4) con-
struct, maintain, and operate the necessary mooring facilities
and utilities within the basin, including a public landing with
suitable supply facilities, all of which shall be open to all on
equal terms. Before adoption of the project, local interests and
the port of Astoria constructed timber bulkheads and dredged the
channel at a total cost of about $560,000.
   Terminal facilities. The city of Warrenton owns a wharf with
300-foot frontage open to the public. One privately owned lumber
mill wharf with 800-foot frontage is used for loading lumber.
   One privately owned cannery wharf with 300-foot frontage
1434        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

is used for unloading fish, loading and unloading nets. One pri-
vately owned boatyard has floats and moorage facilities for a
maximum of 80 small boats. In the channel above the railroad
bridge the facilities are the rollways used by log trucks. These
facilities are considered adequate for present commerce.
   Operations and results during fiscal year. Snagging by con-
tract during April and May removed 240 snags at a cost of $1,886.
Condition surveys were made at a cost of $565 and inspections and
reports cost $77.
   Total costs for the fiscal year were $2,528, all for maintenance.
   Condition at end of fiscal year. Dredging of the channel and
turning basin was completed in 1939. No work has been done on
the construction of the small-boat mooring basin at Warrenton.
The project is 70 percent complete. Controlling depths are 27
feet in the channel and 10 feet in the turning basin. No recent
surveys above the railroad bridge at Warrenton have been made.
   Total costs have been $410,651, of which $130,119 was for new
work and $280,532 for maintenance.
                                    Cost and financial summary

                                          Fiscal year ending June 30              Total to June
                                                                                  30, 1954, includ-
                                                                                  ing fiscal years
                             1950        1951             1952   1953   1954       prior to 1950

New work:
   Appropriated             -..                                                           $130,119
   Cost -- - -        -   -- --                                                            130,119
Maintenance:
   Appropriated       .     $27, 000            --                      $3, 000            281 ,004
   Cost ..        -          27,100 --               - ----               2,528            280,532


Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project _____________________________ $184,881

  12. COLUMBIA RIVER BETWEEN CHINOOK, WASH., AND THE
                  HEAD OF SAND ISLAND
   Location. At the easterly end of Baker Bay, which is on the
north side of Columbia River near its mouth. (See U. S. Coast
and Geodetic Survey Chart No. 6151.)
   Existing project. This provides for a channel 8 feet deep and
150 feet wide, extending from the head of Sand Island to Chinook,
Wash., a distance of about 4,000 feet, and the reinforcement of
and future maintenance of the existing pile and timber break-
water at Chinook. Mean lower low water is the plane of refer-
ence. The tidal range between mean lower low water and mean
higher high water is about 8 feet and the extreme tidal range about
13 feet.
   The actual cost of new work is $40,000. The latest (1948) ap-
proved estimate of cost of annual maintenance is $18,000.
   The existing project was authorized by the River and Harbor
Act of June 20, 1938, (R&H Comm. Doc. 50, 75th Cong., 2d Ses-
sion). The latest published map is in this document.
   Recommended modification of the project. The Chief of En-
gineers has recommended that the existing project be modified
to provide for a channel 10 feet deep and 150 feet wide, extend-
                RIVERS AND HARBORS-PORTLAND, OREG., DISTRICT                                                    1435
ing from the head of Sand Island to Chinook; a turning and moor-
ing basin at the upper end of the channel, 10 feet deep, 660 feet
long, and ranging from 275 to 500 feet wide; reconstruction of the
easterly 393 feet of existing breakwater; and extension of the
existing breakwater easterly and thence northerly to connect with
the shore in the vicinity of Portland Street; at an estimated cost
to the United States of $196,200 for construction and $8,000 an-
nually for maintenance in addition to that now required; pro-
vided local interests agree to: (1) Furnish free of cost to the
United States all lands, easements, rights-of-way, and suitable
spoil disposal areas for the initial work, and for subsequent
maintenance when and as required; (2) hold and save the United
States free from damages due to construction and maintenance
of the improvement; (3) maintain the project depth of ten feet
in the turning and mooring basin; (4) dredge and maintain the
project depth in berthing areas within 50 feet of the existing
wharf; and (5) provide and maintain without cost to the United
States adequate terminal and mooring facilities, including a
public landing with suitable supply facilities, open to all on equal
terms. (Senate Document No. 8, 83d Congress, 1st Session.)
   Terminal facilities. The only terminal is the wharf of the
Chinook Packing Co., a portion of which is used as a public land-
ing. There is no present need for additional terminals.
   Operations and results during fiscal year. A total of 19,100
cubic yards of material was removed from the channel during April
1954, by hired labor and rented plant.
   Costs during the fiscal year were $9,860.47.
   Condition at end of fiscal year. Construction of the project
was accomplished in 1940. The channel is in good condition with
project depths available, survey of June 1953.
   Total costs have been $118,106 of which $40,000 was for new
work and $78,106 for maintenance.
                                          Cost and financial summary

                                                    Fiscal year ending June 30                          Total to June
                                                         __                         -                   30, 1954, includ-
                                                                                                        ing fiscal years
                                   1950          1951           1952         1953          1954          priorto 1950


New work:
   Appropriated--........-----------------------------------------------------------                             $40,000
        ...
   Cost------------     --------               --
                                    ------............ ------------------------------------                       40,00
Maintenance:
    Appropriated..-------.... --   $10, 000------------
                                           ............ --------......   .       ...------------
                                                                                             $10, 000             78, 245
    Cost-----------------           10,000 ----------------------------------                 9,860               78,10&


                  13. COLUMBIA RIVER AT BAKER BAY, WASH.
  Location. Baker Bay is a shallow body of water about 15
square miles in extent, lying on the north side of Columbia River
near its mouth. The bay is separated from the river by Sand Island,
a low-lying sand bar only a few feet above high tide level. (See
U. S. Coast and Geodetic Survey Chart No. 6151.)
  Existing project. This provides for a main channel, 10 feet
deep and 200 feet wide extending through the easterly passage at
Sand Island to the port of Ilwaco, a distance of about 5 miles; for
1436             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

a mooring basin 10 feet and 12 feet deep, about 20 acres in extent,
located east of the port of Ilwaco dock, with protecting break-
waters; and for a west channel 10 feet deep connecting the basin
with deep water in Columbia River, with a width of 150 feet, in-
creased to 200 feet for a distance of 2,000 feet at the southerly end.
   Mean lower low water is the plane of reference. The tidal range
between mean lower low water and mean higher high water is
about 8 feet, and the extreme about 13 feet.
   The estimate of cost for new work revised in 1954 is $1,016,000.
The approved estimate of annual maintenance revised in 1950 is
$88,500.
The existing project was authorized by the following River and
Harbor Acts:

     Acts                             Work authorized                                         Documents
D ec. 11, 1933   M ain channel_._. ..........           ...-__ .. ____ -  - ....   Public W orks Adm inistration.
Aug. 30, 1935    .. do __..............................                            H. Doc. 44, 73d Cong., 1st sess.
Mar. 2,1945      West channel 8 feet deep                 ----------------------   H. Doc. 443, 76th Cong., 1st sess.
May 17, 1950     West channel 10 feet deep and mooring basin with                  S. Doc. 95, 81st Cong., 1st sess.
                   protecting breakwaters.



   Local cooperation. The River and Harbor Act approved May
17, 1950, in connection with construction of the mooring basin and
modification of the west channel provides: (1) That local interests
furnish free of cost to the United States all necessary lands, ease-
ments, rights-of-way, and spoil disposal areas for the new work
and for its subsequent maintenance, when and as required; (2)
hold and save the United States free from damages due to the
construction works and their subsequent maintenance; (3) main-
tain project depths in the mooring basin; (4) make the necessary
changes in existing sewers; and (5) provide and maintain ade-
quate terminal and mooring facilities within the basin, including
a public landing with suitable supply facilities open to all on
equal terms.
   Terminal facilities. The facilities consist of wharves, floats,
ramps and berths for fishing craft, oil and sand barges, and tow-
boats. The facilities are considered adequate for existing com-
merce.
   Operations and results during fiscal year. New work: Closure
of about 800 feet of the timber and stone dike was completed in
July 1953.
   Maintenance: Hydrographic surveys were made at a cost of
$2,802. Dredging of the west channel was accomplished with a
total of 66,817 cubic yards of material being removed at a cost of
$22,110.
   Total costs for the fiscal year were $27,645, of which $2,733
was for new work and $24,912 for maintenance.
   Condition at end of fiscal year. The existing project is 40 per-
cent complete. The channel extending through the easterly pas-
sage at Sand Island was completed in 1934. Dredging of the
west channel extending from deep water in Columbia River to
the east channel near Ilwaco was completed to a depth of 8 feet,
August 1948. Construction of three spur dikes in connection with
              RIVERS AND HARBORS--PORTLAND, OREG., DISTRICT                                               1437
the west channel was completed September 1948. Construction of
an 1,800-foot pile, timber and stone dike was completed in 1951
and additional piling needed to tighten the dike were installed
during fiscal year 1954. No work has been done on the mooring
basin authorized as a project modification by the River and Har-
bor Act approved May 17, 1950.
  Total costs have been $690,426 of which $418,731 was for new
work and $271,695 for maintenance.
                                       Cost and financial summary

                                               Fiscal year ending June 30                           Total to June
                                                                                                  30, 1954, includ-
                                                                                                  ing fiscal years
                               1950         1951             1952       1953            1954        priorto 1950


New work:
   Appropriated--..     __...------------    $5, 315- ..-           "   $5,500     --                     $419,392
   Cost....---------------      $2, 474       2,630          $74, 372   12, 906         $2,733             418,731
Maintenance:
   Appropriated...--------      30,000       26,377           34, 301   -7,300          30,000             276, 827
   Cost-----------------        25,731       29, 947           1,281     26, 374        24, 912            271,695


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_       _--                                        $661
    Estimated additional amount needed to be appropriated for completion
        of existing project                     ----------                               --------       596,608


         14. COLUMBIA RIVER AT THE MOUTH, OREGON AND
                                            WASHINGTON
   Location. This river rises in British Columbia, through which
it flows for 425 miles. It enters the United States in northeastern
Washington, flows southerly to the mouth of Snake River, thence
westerly between Oregon and Washington, and empties into the
Pacific Ocean 645 miles north of San Francisco Bay and 160 miles
south of the Straits of Juan de Fuca. The total length of the river
is 1,210 miles. (See U. S. Coast and Geodetic Survey Charts Nos.
5902, 6151, 6152, 6153, 6154, 6155, and 6156; also Geological Sur-
vey map of Washington.)
   Previous project. Adopted by the River and Harbor Act of
July 5, 1884. For further details see page 1999 of Annual Report
for 1915 and page 1740 of Annual Report for 1938.
   Existing project. This provides for a channel across the bar 40
feet deep at mean lower low water and of suitable width (not less
than one-half mile), to be secured by dredging and by converging
rubble-mound jetties, the south jetty being about 7 miles and the
north jetty about 21/ miles long, terminating 2 miles north of the
end of the south jetty. Mean lower low water is the plane of refer-
ence. The tidal range on the bar between mean lower low water
and mean higher high water is about 8 feet, and the extreme tidal
range is about 13 feet.
   The actual cost for new work was $11,357,506.35 exclusive of
amount expended under previous projects. The latest (1953) ap-
proved: estimate for annual cost of maintenance is $336,000 except
forthe repairs to jetties. Jetty maintenance is done only at inter-
vals of several years and is covered by special allotments.
   The existing project was authorized by the River and Harbor
1438           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Act of March 3, 1905, making final provision for the south jetty,
the construction of the north jetty, and dredging (H. Doc. 94, 56th
Cong., 1st sess., and Annual Report for 1903, p. 2275). The con-
struction of the north jetty was approved July 29, 1910, and a
modification of its alignment December 27, 1913. The latest pub-
lished map is in the Annual Report for 1921 opposite page 1868.
   Recommended modification of the project. The Chief of Engi-
neers has recommended that the existing project be modified to
provide for a channel of suitable alinement with depth of 48 feet
at mean lower low water for a width of one-half mile, to be se-
cured by dredging and the construction of a spur jetty on the north
shore at an estimated cost to the United States of $8,555,000 for
new work and $195,000 annually for maintenance, in addition to
that now required. (H. Doc. No. 249, 83d Congress, 2nd Session.)
   Local cooperation. The existing project contains no conditions
requiring local cooperation. However, during 1914 the Port of
Portland contributed $475,000 and the Port of Astoria $25,000 to
the improvement. These amounts for the greater part were ap-
plied to the purchase of stone for the north jetty.
   Terminal facilities. For terminal and transfer facilities see
report on Columbia and Lower Willamette Rivers, page 1427.
   Operationsand results during fiscal year. Maintenance: Land
management costs were $183, condition surveys $6,590, inspec-
tions and reports $5,823 and dike repairs on Sand Island were
$605.
   A total of 2,141,736 cubic yards of material was removed from
the entrance channel by the Corps of Engineers hopper dredge
at a cost of $295,270.
   Total costs for the fiscal year were $308,471, all for maintenance.
  Condition at end of fiscal year. The existing project was com-
pleted in 1918. The jetties are in fair condition. A gap in the
narrow portion of Sand Island about 2 miles from the east end
continues to cause shoaling at Clatsop Spit and Baker Bay chan-
nels. A survey made in April 1954 showed a controlling depth in
the entrance channel of 43 feet at mean lower low water except at
Clatsop Spit where the controlling depth for the left quarter of the
channel was 40 feet after dredging in August 1953.
   Total costs under the existing project from Federal funds have
been $23,553,609, of which $11,357,506 was for new work and
$12,196,103 for maintenance.
   In addition, $475,000 and $25,000 were contributed by the ports
of Portland and Astoria respectively and expended for new work.
                                     Cost and financial summary

                                             Fiscal year ending June 30                             Total to June
                                                                                                    30, 1954, includ-
                                                                                                    ing fiscal years
                              1950         1951             1952               1953       1954       prior to 195012


New work:
   A ppropriated .-- ---. ---- ----.---                                                                 $13,343,759
   Cost--.  ----------- -------------------           ---------------------------                        13,343,759
Maintenance:
   Appropriated_ .-.         $315, 113    $203, 800       $208, 297          $385, 300   $327,100         12, 217, 715
   Cost--.-                   117, 720     310,717         222,974            458,116     308,471         12,196,103

1 Includes $1,986,253 for new work for previous projects.
2 In addition $500,000 for new work was expended from contributed funds.
                  RIVERS AND HARBORS--PORTLAND,                                  OREG., DISTRICT           1439
                                         15. NEHALEM BAY, OREG.
    Location. Nehalem Bay is an indentation of the Oregon Coast
45 miles south of mouth of Columbia River (See U. S. Coast and
Geodetic Survey Chart No. 5902).
    Previous project. Adopted by act of September 9, 1890. For
details see page 1991 of Annual Report for 1915.
    Existing project. This provides for two high-tide rubblestone
jetties at the entrance to the bay designed to secure a permanent
depth of at least 8 feet at mean lower low water. The south jetty
to be extended to a total length of 4,950 feet from the 2,385 foot
long jetty constructed by the port of Nehalem. The north jetty to
be 3,850 feet long and based on the north spit. The jetties are
slightly converging with their outer ends 700 feet apart and about
on the 6-foot contour.
    The mean of the higher high waters above the plane of reference
and the extreme tidal ranges at the entrance are 7.4 feet and 11
feet, respectively.
    The actual cost of new work from Federal funds, exclusive of
amount expended on previous project is $302,006.03. In addition,
 $304,825.61 was expended from contributed funds.
    The existing project was authorized by the River and Harbor
Act of July 25, 1912, (H. Doc. No. 623, 62d Congress, 2d session).
For latest published map, see page 3206, Annual Report for 1916.
    Local cooperation. Complied with.
    Terminal facilities. Wheeler, Oreg., has 600 feet of private
wharf frontage plus 60 feet which is open to the public. Nehalem,
Oreg., has 280 feet of privately owned wharves of which 80 feet
has always been free to all. Existing terminals are considered
adequate for present commerce.
    Operations and results during fiscal year. Preliminary work
in connection with hydrographic surveys was accomplished.
    Total cost for the fiscal year was $42.03.
    Condition at end of fiscal year. The south jetty was completed
in 1915 and the north jetty in 1918. The outer end of the north
jetty has subsided below low tide level for a distance of about 200
feet and the south jetty about 600 feet. There are also several
breaks in both jetties. The channels across the ocean bar at the
entrance and between the jetties are of project depth and better.
    Total costs under the existing project have been $312,614, of
which $302,006 was for new work and $10,608 for maintenance.
    In addition, $304,825.61 was expended from contributed funds
for new work.
                                                Cost and financial summary

                                                      Fiscal year ending June 30                   Total to June
                                                                                                  30, 1954, includ-
                                                                                                  ing fiscal years
                                       1950          1951         1952          1953    1954       prior to 1950 1


New work:
   Appropriated ................          _                                                               $302,692
   Cost       _               ---------------                 ---------                                    302, 692
Maintenance:
   Appropriated            -                                                            $2, 000             13,337
     ApprCost                                                   ...       ---            42.03              11379

  1 Includes $686 for new work and for previous projects.
  2In addition $304,826 for new work was expended from contributed funds.


         Sig 46--1439-1470
1440            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                      16. TILLAMOOK BAY AND BAR, OREG.
   Location. This bay is located on the Oregon coast about 50
miles south of the mouth of Columbia River. (See U. S. Coast and
Geodetic Survey Charts Nos. 5902 and 6112.)
   Previous project. Adopted by River and Harbor Acts of August
11, 1888, and July 13, 1892. For further details, see pages 1989 of
Annual Report for 1915, and page 1474 of Annual Report for 1936.
   Existing project. This provides for a jetty about 5,700 feet
long on the north side of the entrance; for a channel through the
bar 18 feet deep and of such width as can be practically and eco-
nomically obtained; for a channel 200 feet wide and 18 feet deep
from deep water in the bay to Miami Cove; for initial dredging
of a small boat basin and an approach thereto at Garibaldi, Oreg.,
to a depth of 12 feet; for a channel to Hobsonville, 200 feet wide
and 16 feet deep, with a turning basin 500 feet wide at Hobson-
ville, and regulating works as needed.
   The mean of the higher high waters above the plane of reference
and the extreme tidal range at the entrance are 7.4 feet and about
13 feet, respectively.
   The estimate of cost for new work revised in 1953 is $784,000,
exclusive of contributed funds. The latest (1953) approved esti-
mate for annual cost of maintenance is $28,000 for entrance and
bay channels.
   The existing project was authorized by the following River and
Harbor Acts:

     Acts                         Work authorized                                    Documents
Aug. 11, 1888    Improvement of Dry Stocking bar and Hoquarton            H. Ex. Doc. 185, 50th Cong., 1st
                   Slough.                                                  sess.
July 13,1892   Dredging channel 200 feet wide and 6 feet deep be-         H. Ex. Doc. 35, 52d Cong., 1st sess.
                tween north and middle channels above Bay City
                and construction of various control dikes.
July 25, 1912 \Construction of north jetty, 5,700 feet long and dredg-    H. Doc. 349, 62d Cong., 2d sess.
Mar. 4, 1913 f    ing channel 16 feet deep, 200 feet wide, to Bay City.                       ng,
Mar. 2,1919      Abandonment of that portion of project above Bay         H. Doc. 730, 65th Cong., 2d sess.
                   City.
Mar. 3, 1925     Abandonment of Bay City channel and for present          H. Doc. 562, 68th Cong., 2d sess.
                  project dimensions of the channels and turning
                  basins with regulating works as needed.
June 30, 1948    Dredging small-boat basin and approach at Gari-          H. Doc. 650, 80th Cong., 1st sess.
                  baldi, Oreg., to a depth of 12 feet.



   Local cooperation. The River and Harbor Act approved June
30, 1948, in connection with the authorization of small boat basin
at Garibaldi provides, (1) that local interests furnish all necessary
easements, rights-of-way, and spoil disposal areas, both for new
work and maintenance, and (2) agree to maintain necessary
depths in the mooring basin proper, to construct, maintain, and
operate necessary mooring facilities and utilities within the basin,
including a public landing with suitable supply facilities, open to
all on equal and equitable terms, and (3) to hold and save the
United States free from any claim for damages which might result
from execution of the work.
   The River and Harbor Act of March 3, 1925, provides that no
work is to be done in the Hobsonville Channel until assurance is
given that a mill of substantial capacity will be erected in the
            RIVERS AND HARBORS-PORTLAND,                              OREG., DISTRICT             1441
vicinity of Hobsonville. This condition has not been complied
with. All other prescribed conditions of local cooperation have
been fully complied with except for requirements for Garibaldi
Channel.
   Terminal facilities. At Garibaldi there is a privately owned
wharf for the shipment of lumber; a public wharf suitable for
fishing vessels, towboats and other craft, and a privately owned
fixed derrick for loading logs to oceangoing barges. These facili-
ties are considered adequate for existing commerce.
   Operationsand results during fiscal year. None.
   Condition at end of fiscal year. The existing project is 74 per-
cent complete. The jetty was completed in 1933 and is in poor
condition, with the outer 800 feet below low-water level. The
remaining work required to complete the project consists of dredg-
ing the Hobsonville Channel and turning basin, which work will
not be done until navigation requires deeper water, and dredging
a small-boat basin and connecting channel at Garibaldi. A survey
made in May 1953 shows a controlling depth of 171/2 feet on the
bar, 12 feet in the channel to Miami Cove, and 10 feet in the turn-
ing basin, at lower low water.
   Total costs have been $1,528,751, of which $574,447 was for new
work and $954,304 for maintenance. In addition, $398,832.70 was
expended for new work and $6,450.00 for maintenance from con-
tributed funds.
                                    Cost and financial summary

                                              Fiscal year ending June 30                   Total to June
                                                         _          .__      -             30, 1954, includ-
                                                        1151    -   1953         15 I      ing fiscal years
                             1950         1951           1952         1953       1954       prior to 1950 12


New work:
                      _----
   Appropriated .......              -5----                -            3-                      $ 651,656
        ............. ---------------------------------------------------
   Cost-----------------                                                  651,656
Maintenance:
   Appropriated------.... $55, 030 $1,022 ....        3,355    $4,1,025,803
   Cost-----------------      55, 030         1,022 ------------       3,355------------         1,025,803

1Includes $77,209 for new work and $71,498 for maintenance for previous projects.
8 In addition $398,833 for new work and $6,450 for maintenance was expended from contributed funds.

Other new work data: Estimated additional amount needed to be appropri-
                                                                        $209, 553
  ated for completion of existing project..........................................
                                    17. DEPOE BAY, OREG.
   Location. This harbor is located on the Oregon coast, 100 miles
south of the mouth of Columbia River. (See U. S. Coast and
Geodetic Survey Chart No. 5902.)
  Existing project. This provides for a breakwater north of the
entrance, for an entrance channel 8 feet deep and 30 feet wide, and
for an inner basin 750 feet long by an average of 390 feet wide, 8
feet deep, with retaining wall along the easterly side.
  Mean lower low water is the plane of reference. The mean of the
higher high water and the extreme rise at the entrance above the
plane of reference are 7.8 feet and about 11.5 feet respectively.
The actual cost for new work was $367,364.46. The latest (1953)
approved estimate for annual cost of maintenance is $15,000.
   The River and Harbor Act of August 26, 1937 (H. Doc. 202, 75th
1442           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Cong., 1st sess.), authorized construction of an inner basin 375 feet
long, 125 feet wide, and 5 feet deep, with entrance channel of same
depth and 30 feet in width. The River and Harbor Act of March
2, 1945 (H. Doc. 350, 77th Cong., 1st sess.), modified the project
to provide for the existing project as described. The latest pub-
lished map is in this document.
   Local cooperation. Provisions of the River and Harbor Act ap-
proved August 26, 1937, have been fully complied with except for
the construction of a public terminal. Under the provisions of the
River and Harbor Act approved March 2, 1945, local interests are
required to furnish free of cost to the United States all lands,
easements, rights-of-way, and spoil disposal areas necessary for
the improvements and their subsequent maintenance, when and as
required, hold and save the United States free from claims for dam-
ages resulting from the improvements, and save and hold free for
use of the public as a roadway, promenade, or landing, a strip at
least 60 feet wide along the easterly side of the retaining wall for
its full length.
   Terminal facilities. Terminal facilities, all in the inner basin,
consist of landings and floats, privately owned, to accommodate
operators of excursion and commercial fishing boats. The present
facilities are considered adequate for existing commerce.
   Operationsand results during fiscal year. A hydrographic con-
dition survey of the entrance channel and inner basin was made
June 1954.
   Total costs for the fiscal year were $811.54.
   Condition at end of fiscal year. Dredging of the basin and en-
trance channel to a depth of 5 feet as originally authorized was
completed in 1939. Enlarging and deepening the basin and en-
trance channel to 8 foot depth and construction of a retaining wall
and breakwater at the entrance authorized by the River and Har-
bor Act of 1945 was completed in June 1952.
   Project depths of 8 feet prevail in the entrance channel and inner
basin except for the south half of the basin which has shoaled to
such an extent that depths at lower low water vary to less than one
foot. Shoaling has also occurred to a lesser extent in the northeast
portion of the basin.
   Total costs have been $458,017, of which $367,364 was for new
work and $90,653.00 for maintenance.
                                  Cost and financial summary

                                         Fiscal year ending June 30                        Total to June
                                                                                          30, 1954, includ-
                                                                                          ing fiscal years
                           1950         1951        1952           1953         1954        prior to 1950


New work:
   Appropriated ._----    $400,000    -$62, 315               -   -$2, 282 -$367,                      364
   Cost- -------------      47,862      261,066     $26,876            195 -----------.            367,364
Maintenance:
   Appropriated -------      2,302                                              $1, 000             90, 841
   Cost .--------------      2,302                                                  812             90, 653


                   18. YAQUINA         BAY AND             HARBOR,         OREG.
   Location.         This bay is located on the Oregon coast, 115 miles
                RIVERS AND HARBORS-PORTLAND, OREG., DISTRICT                                          1443
south of the mouth of the Columbia River. (See U. S. Coast and
Geodetic Survey Charts Nos. 5802 and 6058.)
   Previous projects. The River and Harbor Act of June 14, 1880,
provided for the improvement of the entrance. Subsequent proj-
ects were adopted by River and Harbor Acts of June 3, 1896, June
6, 1900, and March 3, 1905. For further details, see the Annual
Report for 1893, part 4, page 3314, House Document 68, 54th Con-
gress, 1st session, and the Annual Report for 1938, page 1736.
   Existing project. This provides for two high tide rubble-mound
jetties at the entrance, 1,000 feet apart at their outer ends; the
north jetty to be 4,700 feet and the south jetty to be 5,800 feet in
length; for a spur jetty on the channel side of the south jetty 4,700
feet from its sea end, 800 feet in length; for five groins channel-
ward from the south jetty; insofar as the rock bottom will allow
for a channel 26 feet deep and of suitable width across the entrance
bar for a channel 20 feet deep and 300 feet wide from the outer end
of the jetties upstream and along the south side of the bay a dis-
tance of about 2 miles to McLean Point with a turning basin at the
upstream end 22 feet deep, 1,000 feet wide and 1,200 feet long; for
a channel 18 feet deep and 200 feet wide from the 20-foot channel
at about mile 1, along the city docks at Newport, thence upstream
to the abandoned railroad terminus at Yaquina, a distance of
about 41/2 miles; and for a small boat mooring basin at Newport,
Oreg., by construction of a breakwater about 2,650 feet long and
a shore wing about 400 feet long, and initial dredging in the moor-
ing basin to a depth of 10 feet.
   Mean lower low water is the plane of reference. The mean of
the higher waters above the plane of reference and the extreme
tidal range at the entrance and at the head of the bay are 8.1 feet
and 12 feet, respectively.
   The actual cost for new work is $2,181,745.79. The latest (1953)
approved estimate for annual cost of maintenance dredging in the
bay and entrance is $87,500. The latest (1937) approved estimate
of cost for maintenance of the north jetty is $12,000 annually to
be applied at intervals of several years. There is no approved
estimate for maintenance of the south jetty.
   The existing project was authorized by the following River and
Harbor Acts:
     Acts                          Work authorized                                   Documents
June 14, 1880   For improvement of the entrance----------------Annual Report, 1881, p. 2589.
June 6, 1900    Rock removal at the entrance....------------------ H. Doc. 110, 56th Cong., 1st sess.
Mar. 3, 1905    This act repealed previous acts relating to improve-
                  ment of the entrance, but provided for 2 years'
                 maintenance.
Mar. 2, 1919 Restoration and extension of the jetties constructed        H. Doc. 109, 65th Cong., 1st sess.
                  under previous projects; rock removal at the en-
                  trance; and dredging in the bay up to the railroad
                  terminus at Yaquina.
Aug. 26, 1937   Extension of the north jetty seaward 1,000 feet .....    Senate committee print, 75th Cong.
                                                                           1st sess.'
Mar. 2, 1945    26-foot channel of suitable width across entrance bar,   S. Doc. 119, 77th Cong., 1st sess.x
                  insofar as rock bottom will allow, a 20-foot channel
                  300 feet wide along south side of bay to and includ-
                  ing a turning basin 22 feet deep, 1,000 feet wide,
                  and 1,200 feet long.
July 24, 1946   Construction of a small-boat mooring basin at New-       S. Doec. 246, 79th Cong., 2d sess.
                 port, Oreg.


  1Contains latest published maps.
1444          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Local cooperation. Fully complied with.
   Terminal facilities. At McLean Point, on the north side of the
bay, about 2 miles from the entrance, the Yaquina Bay Dock &
Dredge Co., Inc., wharf has a frontage of about 900 feet, which
provides loading berths for two vessels. This facility has a lum-
ber planing mill, necessary lumber carriers and lift trucks, and
is open to all on equal terms. On the south side of the bay imme-
diately above the highway bridge, about a mile and a quarter above
the entrance, the C. D. Johnson Lumber Company maintains pri-
vate dolphins with a frontage of 700 feet for loading ocean-going
vessels from barges. The port of Newport has a public wharf with
400 feet of frontage for handling of fishing boats. In addition, the
port of Newport maintains about 500 feet of protected float land-
ings for use by seagoing fishing vessels.
   Operationsand results during fiscal year. Maintenance: Dredg-
ing entrance bar and channel restored project depths. A total of
223,933 cubic yards of material was removed at a cost of $88,904.
Hydrographic surveys were made at a cost of $2,928. Inspections
and reports were made at a cost of $460 and preliminary engineer-
ing costs were $1,873.
   Total costs for the fiscal year were $94,165.32, all for mainte-
nance.
   Condition at end of fiscal year. The existing project was com-
plete in May 1952. Restoration of the jetties was completed in
1934 and the extension to the north jetty in 1940. Both jetties are
in fair condition. The main channel from the outer ends of the
jetties to McLean Point with turning basins at the upstream end
was completed in May 1952, and the channel 18 feet deep and 200
feet wide from the 20-foot channel at mile 1 along the city dock
at Newport, thence upstream to the abandoned railroad terminus
at Yaquina and the small boat mooring basin at Newport were
completed during the fiscal year 1949. The controlling depth on
the bar is 171/2 feet for a width of 300 feet and 161/2 feet between
the jetties, 16 feet in the turning basin, 9 feet in the small boat
basin, by survey of April 1954. Dredging is in progress.
   Total costs under the existing project from Federal funds have
been $3,448,419, of which $2,181,746 was for new work and $1,-
266,673 for maintenance. In addition, $729,168.48 was expended
for new work from contributed funds.
                                   Cost and financial summary

                                          Fiscal year ending June 30                       Total to June
                                                                                           30, 1954, includ-
                                                                                           ing fiscal years
                            1950         1951         1952       1953           1954        prior to 1950 1s

New work:
   Appropriated --------
                 .....     $35, 000    -$79, 000 ..         .           -              .               059
                                                                                                $2, 889,
                                                                                                $-$744-...
   Cost_         _------ -13,296          40,464       $7,248           21--    - -        -     2,889,059
Maintenance:
   Appropriated_             83, 650     29, 639      117, 000    53,900       $109, 680         1,288,797
   Cost----------------j     79,152      34,138       117,000     53,316         94,165          1,272,699

1 Includes $707,313 for new work and $6,026 for maintenance for previous projects.
   In addition $729,168 for new work was expended from contributed funds.
                RIVERS AND HARBORS-PORTLAND, OREG., DISTRICT                                           1445
                                 19. UMPQUA RIVER, OREG.
   Location. This river rises in the Cascade Range, flows westerly
about 120 miles, and empties into the Pacific Ocean 180 miles
south of the mouth of the Columbia River and 465 miles north of
San Francisco Bay. (See U. S. Coast and Geodetic Survey Charts
No. 5802 and 6004.)
   Previousprojects. Adopted by River and Harbor Act of March
3, 1871, and modified in 1886. For further details, see page 2967
of Annual Report for 1898, and page 1732 of Annual Report for
1938.
   Existing project. This provides for a jetty on the north side of
the entrance approximately 8,000 feet in length, westerly from the
highwater line to the sea; for a south jetty extending to a point
1,800 feet south of the outer end of the north jetty; for dredging
to provide a usable entrance channel 26 feet deep, and a river
channel 22 feet deep and 200 feet wide, from the mouth to Reeds-
port, a distance of about 11 miles, with a turning basin at Reeds-
port 1,000 feet long, 600 feet wide, and 22 feet deep; for a channel
12 feet deep and 100 feet wide from deep water in the river to
the vicinity of the docks in Winchester Bay with a mooring and
turning basin 12 feet deep, 175 feet wide and 300 feet long at
the inner end; and for a channel 22 feet deep and 200 feet wide
from the main river channel near mile 8 to Gardiner, Oreg., and
a turning basin of the same depth, 500 feet wide and 800 feet long,
opposite Gardiner.
   Mean lower low water is the plane of reference. The tidal range
between mean lower low water and mean higher high Water at
the river mouth is 6.9 feet, and the extreme range is about 11
feet. The latest 1954 approved estimate of cost of new work is
$2,709,000, exclusive of amounts expended on previous projects
and $276,500 contributed by local interests. The latest 1953 ap-
proved estimate for annual cost of maintenance is $174,500, ex-
cluding jetty maintenance.
   The existing project was authorized by the following River and
Harbor Acts:
     Acts                         Work authorized                                     Documents

Sept. 22,1922   North jetty, 7,500 feet long___--------------------- H. Doc. 913, 65th Cong., 2d sess.
Jan. 21, 1927   Present project dimensions of north jetty and for         H. Doc. 320, 69th Cong., 1st sess.
                  dredging the ocean bar.                                                                      1
July 3, 1930    For a short south jetty-----.._.. . ..--- -------------   H. Doc. 317,    70th Cong., 1st sess.
Aug. 30, 1935   For a full length south jetty and maintenance dredg-      Rivers and      Harbors Committee
                  ing to a 26-foot depth.                                   Doc. 9, 72d   Cong., 1st sess.'
June 20, 1938   Channel 22 feet deep and 200 feet wide from mouth         S. Doc. 158,    75th Cong., 3d sess.'
                 to Reedsport.
Mar. 2, 1945    Channel 22 feet deep and 200 feet wide from river         S. Doe. 86, 76th Cong., 1st sess.l
                  channel to Gardiner and turning basin 22 feet deep,
                  500 feet wide and 800 feet long.
Do...--------   Channel 10 feet deep and 100 feet wide from river         S. Doc. 191, 77th Cong., 2d sess.'
                 channel to dock in Winchester Bay with mooring
                 and turning basin 10 feet deep, 175 feet wide and
                 300 feet long at inner end.
June 30, 1948   Channel 12 feet deep and 100 feet wide from river         S. Doc. 154, 80th Cong., 2d sess.'
                  channel to dock in Winchester Bay with mooring
                  and turning basin 12 feet deep, 175 feet wide and
                  300 feet long at inner end.

  1Contains latest published maps.

    Recommended modification of the project.                                     Senate Document
1446     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

133, Eighty-first Congress, second session, recommends that the
existing project for Umpqua River, Oreg., be modified to provide
for a channel in Scholfield Creek, 12 feet deep at mean lower low
water, generally 100 feet wide from its confluence with Umpqua
River to a point 0.5 mile below the first railroad bridge, a dis-
tance of 2 miles, the entrance to be widened to 300 feet in a dis-
tance of 500 feet, at an estimated cost to the United States of
 $41,000 for new work and $7,000 annually for maintenance in
addition to that now required; provided, that local interests con-
tribute in cash $10,000 toward the cost of the new work; agree to
furnish, free of cost to the United States, suitable spoil disposal
areas for initial work and subsequent maintenance when and as
required; and hold and save the United States free from damages
due to the construction and maintenance when and as required.
    Local cooperation. Requirements of local cooperation for all
work authorized prior to 1945 have been fully complied with and
approved.
    Under the provisions of River and Harbor Act approved March
2, 1945, state or other local interests are required, for the Win-
chester Bay channel, to furnish free of cost to the United States
suitable areas for spoil disposal for initial work and subsequent
maintenance, when and as required, and hold and save the United
States free from claims for damages resulting from the improve-
ments; construct, maintain, and operate suitable public terminal
and mooring facilities with essential utilities and supply services
at the basin, open to all on equal terms, and at their own expense
maintain project depths within the mooring and turning basin
after its construction has been accomplished. For the Gardiner
Channel local interests are to furnish assurances that the Gardi-
ner mill will be operated to produce an average daily output of
100,000 feet board measure for 300 days per year; that the mill
wharf or other suitable wharf will be open to all on equal and
reasonable terms; and that local interests furnish free of cost
to the United States, when and as required, all lands, easements,
and rights-of-way and spoil disposal areas for the initial work and
for subsequent maintenance, and hold and save the United States
free from claims for damages resulting from the improvement.
Assurances in connection with Gardiner Channel were approved
December 26, 1947. Assurances in connection with Winchester
Bay channel have not yet been requested.
    Terminal facilities. At Gardiner there is approximately 650
feet of wharf frontage, of which 60 feet is publicly owned. At
Reedsport there is about 750 feet of usable wharf frontage, all
privately owned. The port of Umpqua owns one wharf with 456
feet of water frontage and another with about 75 feet of water
frontage which has not been used generally for commercial ship-
ping. On Bolon Island across the river from Reedsport a wharf
has been constructed which has about 5 acres of open storage for
lumber and is available to all on equal terms. At Winchester
Bay, there is a public landing float with a wooden pile and timber
shore approach, and a privately owned wharf used by excursion
and commercial fishing vessels.     The facilities are considered
adequate for present commerce.
               RIVERS AND HARBORS-PORTLAND, OREG., DISTRICT                                       1447
   Operations and results during fiscal year. Maintenance: Re-
pairs of shore end of training jetty were made at a cost of
$208,532. Condition surveys were made at a cost of $4,256 and
the cost of inspections and reports was $903. A total of 183,756
cubic yards of material was removed from the entrance bar and
inner channel at a cost of $51,721.
   Total costs for the fiscal year were $265,412.
   Condition at end of fiscal year. The existing project is 97 per-
cent complete. The north jetty was completed in 1940. The ex-
tension to the original south jetty was completed in 1938 and
construction of a new training jetty on the south side of the
entrance to replace the original south jetty which was partially
destroyed by storms was completed in 1951. Dredging of a 22-
foot channel from the mouth of the river to Reedsport was com-
pleted in 1941.
   The controlling depth at the close of the fiscal year was 25 feet
on the bar, survey of September 1953, and 17 feet from the mouth
to Reedsport and 21 feet in Gardiner channel and turning basin,
survey of June 1953. No work has been done on the Winchester
Bay channel and mooring basin.
   Total costs under the existing project from Federal funds have
been $6,433,712, of which $2,605,811 was for new work and
$3,827,901 for maintenance. In addition, $276,500 was expended
from contributed funds for new work.
                                    Cost and financial summary

                                            Fiscal year ending June 30                    Total to June
                                                                                          30, 1954, includ-
                                                                                          ing fiscal years
                             1950         1951         1952        1953        1954       prior to 1950 1 2

New work:
   Appropriated                         -- $10, 395                       -   -$2,645,053
   Cost -----  ---    -                     14,605                                               2, 645, 053
Maintenance:
   Appropriated             $704, 086     977, 460     $37, 000   $220,300    $215, 300          3, 831, 896
   Cost ____..               576, 770   1,108,487       32,787     172,647     265,412           3,827,901

1 Includes $39,242 for new work for previous projects.
2 In addition $276,500 for new work was expended from contributed funds.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project________    ______________ $103,189
                                    20. COOS BAY, OREG.
   Location. On the Oregon coast 200 miles south of the mouth of
Columbia River and 445 miles north of San Francisco Bay. It is
about 13 miles long and 1 mile wide, with an area at high tide of
about 15 square miles. (See U. S. Coast and Geodetic Survey
Charts Nos. 5802 and 5984.)
   Previous projects. Adopted by River and Harbor Acts of
March 3, 1879, September 19, 1890, and August 18, 1894. For
further details, see page 1987 of Annual Report for 1915, and
page 1728 of Annual Report for 1938.
   Existing project. This provides for two rubble-mound, high-
tide jetties at the entrance; a channel across the outer bar 40
feet deep at mean lower low water, and of suitable width with
dimensions reduced gradually to Guano Rock; a channel 30 feet
1448               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

deep at mean lower low water and generally 300 feet wide thence
to the mouth of Isthmus slough; turning basins of the same depth
and 1,000 feet long and 600 feet wide opposite Coalbank slough
and at the city of North Bend; anchorage basins 600 feet wide by
2,000 feet long at mile 3.5 and near mile 7; a channel 22 feet deep
and 150 feet wide from Smith's Mill (mouth of Isthmus Slough)
to Millington, a mooring basin, about 500 feet by 900 feet, for
small boats at Charleston, with a connecting channel, 10 feet deep
and 150 feet wide, to deep water in Coos Bay, and the construction
of a protecting breakwater and a bulkhead.
   The plane of reference is mean lower low water. The mean of
the higher high water above the plane of reference and the ex-
treme tidal range at the entrance are 7 feet and about 11 feet,
respectively, and at Coos Bay 7.3 feet and 11 feet respectively.
   The estimate of cost for new work, revised in 1954, is $8,271,200,
exclusive of amounts expended on previous projects. The latest
 (1953) approved estimate for annual cost of maintenance is
$654,500, not including repairs to jetties.
   The existing project was authorized by the following River and
Harbor Acts:

        Acts                         Work authorized                                  Documents
Sept.   19, 1890   For 2 jetties_-....       ._--------------------_       Annual Report, 1890, p. 2936.
June    15,1910    Dredging the ocean bar channel--------......      --    H. Doc. 958, 60th Cong., 1st sees.
Mar.     2,1919    A channel  22 feet  deep to           -------------
                                               Smith's mill                H. Doc. 325, 65th Cong., 1st sess.
Sept.   22,1922    Restoration of the north jetty, 9,600 feet long; con-   H. Doe. 150, 67th Cong., 2d sess.
                     struction of a south jetty about 3,900 feet long;
                     extension of the 22-foot bay channel from Smith's
                     mill to Millington.
Jan. 21,1927       Extension of the jetties to such lengths as may be
                    practicable within the estimate of total cost of the
                    jetties, $3,250,000, as given in the former document
                     (H. Doe. 150, 67th Cong.).
July     3,1930    A channel 24 feet deep and 300 feet wide through        H. Doc. 110, 70th Cong., 1st sess.'
                    Pigeon Point Reef, following a location along the
                    westerly side of the bay.
Aug. 30, 1935      For the 24-foot channel from Pigeon Point Reef to       Senate committee
                                                                                      t     print, 73d Cong.,
                    Smith's mill and a turning basin above Marshfield.       2d sess.
July 24, 1946      For increased dimensions of channel across the bar      S. Doc. 253, 79th Cong., 2d sess.
                     and to Isthmus slough and turning basin opposite
                     Coalbank slough and at city of North Bend; an-
                    chorage basins at mile 3.5 and near mile 7.
June 30,1948       For a mooring basin and connecting channel at           H. Doc. 646, 80th Cong., 1st sess.
                    Charleston.

  ' Contains latest published maps.

   Local cooperation. The River and Harbor Act of July 24, 1946,
provided that the local interests give assurances satisfactory to
the Secretary of War that they will: (1) Furnish free of cost
to the United States necessary spoil disposal areas for new work
and subsequent maintenance as and when required; and (2) con-
struct and maintain any additional terminal facilities necessary
to the full use of the port, such facilities to be open to all on equal
terms. Assurances of local cooperation approved by the Secre-
tary of the Army on November 4, 1947, have been fully complied
with.
   The River and Harbor Act of June 30, 1948, in connection with
Charleston Channel, provides that local interests (1) furnish,
free of cost to the United States, all lands, easements, rights-of-
way, and spoil disposal areas required for both new work and
         RIVERS AND HARBORS-PORTLAND, OREG., DISTRICT           1449
subsequent maintenance; (2) agree to construct, maintain, and
operate adequate mooring facilities within the basin, and a public
landing with suitable utility and supply facilities, without profit
and open to all on equal and equitable terms; (3) maintain the
bulkhead and maintain project depths within the mooring basin;
  (4) agree to hold and save the United States free from any claims
for damages which might result from execution of this improve-
ment; (5) contribute $40,800 to defray one-half of the estimated
cost of constructing the bulkhead; and (6) hold for the free use
of the public as a roadway, promenade, or landing, a strip at least
100 feet wide, adjacent to and landward of the bulkhead along
the northerly, easterly, and southerly sides of the filled area. As-
surances have not been requested.
    Terminal facilities. At North Bend there is a municipal wharf
649 feet long fronting on the channel and about 1,400 feet of
privately owned mill wharves, and 3 oil docks in the vicinity. At
Coos Bay there is a privately owned wharf with a frontage of 1,310
feet, 500 feet of which was constructed in 1952, open to the public
on equal terms; several small landings for fishing boats and har-
bor craft; and 2 lumber docks with 1,300-foot and 596-foot front-
ages, respectively. At Eastside, on Isthmus Slough, there is a
200-foot wharf to accommodate coastal lumber schooners and
about 4      miles above Eastside on Isthmus Slough, there is a
newly constructed mill wharf served by oceangoing barges. At
Empire there is a privately owned lumber wharf with a frontage
of 545 feet. About 11/ miles below Empire there is a privately
owned lumber and pulp mill wharf with a frontage of 410 feet.
These facilities are considered adequate for existing commerce.
    At Charleston there are 2 wharves, 1 public and 1 private, with
usable area of 1,200 square feet and 2,400 square feet, respectively,
each equipped with facilities for servicing fishing craft. A float
landing extends some 200 feet north of the private wharf. Pres-
ent facilities are congested and inadequate to accommodate the
boats operating in the vicinity.
    A privately owned floating moorage located on Joe Ney Slough
has facilities for mooring approximately 50 fishing vessels. Dur-
ing stormy season, vessels from Charleston seek shelter at these
moorings, which are entirely inadequate during these periods.
    Operations and results during fiscal year. Condition surveys of
the entrance and bay channel were made at a cost of $13,307.
Land management and inspections and reports cost $2,986.
Dredging on the bar and inner channel to project depths by Gov-
ernment plant and hired labor and by contract was accomplished
at a cost of $456,740. A total of 2,082,143 cubic yards of material
was removed.
    Total costs for the fiscal year were $473,033 for maintenance.
    Condition at end of fiscal year. The existing project is 91 per-
cent complete. All work authorized prior to 1946 was completed
in 1937. The south jetty was completed in 1928, the north jetty
in 1929 and the 24-foot channel in 1937. Excavation of the chan-
nel to a depth of 30 feet and generally 300 feet wide from the en-
trance to Isthmus slough was completed January 15, 1951. Dredg-
ing a channel on the outer bar to a depth of 40 feet decreasing to
1450              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

30 feet at Guano Rock was completed in 1952. No work has been
done on construction of the Charleston Channel and small boat
basin. The controlling depth on the bar is 26 feet and from the
entrance to Coos Bay, 23 feet, survey of April 1954. Dredging
is now in progress.
   Total costs under the existing project have been $14,917,700,
of which $7,595,107 was for new work and $7,322,593 for mainte-
nance.
   In addition, $2,713.14 was expended for new work and $8,386.86
for maintenance from contributed funds.
                                              Cost and financial summary

                                                    Fiscal year ending June 30                     Total to June
                                                                                                   30, 1954, includ-
                                                                                                   ing fiscal years
                                       1950        1951          1952       1953        1954       priorto 1950 12


New work:
   Appropriated--------........       $850, 000   $622, 800 _------------   -$2, 457        ----        $8, 397,203
     Cost.....---___________      _    486,628     681,186       $20,465                                  8,397,203
Maintenance:
     Appropriated --------             140,000     134,235       11, 286    465, 000   $494, 800          7, 535, 103
     Cost----------------              115, 149     58, 570      211, 802   453, 058    473033            7, 501, 394


  1 Includes $802,096 for new work and $178,801 for maintenance for previous projects.
  2 In addition $2,713 for new work and $8,387 for maintenance was expended from contributed funds.


Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project_ -------------------------                                    744, 293

                                      21. COQUILLE            RIVER, OREG.
   Location. This river rises in the Coast Range, flows in a gen-
eral westerly direction for about 100 miles, and empties into the
Pacific Ocean at Bandon, Oreg., 225 miles south of the mouth of
the Columbia River and 420 miles north of San Francisco Bay.
 (See U. S. Coast and Geodetic Survey Charts Nos. 5802 and 5971.)
   Previous projects. Adopted by River and Harbor Acts of June
14, 1880, and July 13, 1892. For further details, see page 1986 of
the Annual Report for 1915, and page 1727 of the Annual Report
for 1938.
   Existing project. This provides for two rubble-mound high tide
jetties at the river mouth, the south jetty 2,700 feet long and the
north 3,450 feet; and for a channel 13 feet at mean lower low
water and of suitable width from the sea to a point 1 mile above the
old Coquille River Lighthouse, and for snagging to the State
highway bridge at the city of Coquille. Mean lower low water is
the plane of reference. The tidal range between mean lower low
water and mean higher high water at the mouth is 6.8 feet and the
extreme range about 10 feet.
   The actual cost for new work, is $316,640.21, exclusive of
amounts expended on previous projects. The latest (1953) ap-
proved estimate for annual cost of maintenance is $50,000 for
dredging and snagging. There is no approved estimate for
maintenance of jetties.
                RIVERS AND HARBORS-PORTLAND, OREG., DISTRICT                                                       1451
The existing project was authorized by the following River and
Harbor Acts:
    Acts                                   Work authorized                                       Documents
                                                                                                                          1
June 14, 1880   Jetties_ _-------------_       ----           --------------    -.. S. Ex. Doc. 14, 45th Cong., 3d sess. ;
                                                                                       Annual Report 1879, p. 1806.
June 25, 1910   Dredging shoals between the mouth and Riverton,                      H. Doc. 673, 61st Cong., 2d sess.
                 and removing obstructions between the mouth of
                 the North Fork and Bandon.
Mar. 2,1919     For a 13-foot channel from the ocean to Bandon-......                H. Doc. 207, 65th Cong., 1st sess. 1
July 3, 1930    Deepening the channel to 16 feet between the sea and                 H. Doc. 186, 70th Cong., 1st sess.
                  the eastern end of the north jetty.
Aug. 30,1935    Present project depth between the sea and the east-                  Senate committee print. 74th Cong.,
                  ern end of the north jetty.                                          1st sess.                       1
Mar. 2,1945      For 13-foot depth from sea to a point 1 mile above                  H. Doe. 672, 76th Cong., 3d sess.
                  Coquille River Lighthouse and snagging to State
                  highway bridge.

   Contains latest published maps.

   Local cooperation. None required.
   Terminal facilities. At Bandon there is one privately owned
lumber wharf suitable for handling coastwise vessels. There is a
publicly owned wharf open to all on equal terms. These facilities
are adequate for the present commerce. Above Bandon, there
are numerous log booms and rollways on the navigable waterway.
   Operations and results during fiscal year. Condition surveys
were made as required at a cost of $1,803. Inspections and reports
cost $333.
   A total of 15,593 cubic yards of material was removed from the
entrance at a cost of $13,520. Engineering for repairs to the
south jetty was made at a cost of $3,464. A contract for repair
of south jetty was awarded in May 1954, but operations not
initiated.
   Total costs for the fiscal year were $19,120, all for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1933. The jetties were completed in 1908 and the en-
trance channel in 1933. The north jetty was reconstructed in
1942 and a 750 foot extension to the easterly end was constructed
in 1951. The jetties are in fair condition. The controlling depth
on the bar is 111/2 feet and in the entrance channel, 11 feet, survey
of June 1954.
   Total costs from Federal funds under the existing project have
been $1,222,193, of which $316,640 was for new work and $905,-
553 for maintenance. In addition, $72,891.20 was expended for
new work from contributed funds.
                                             Cost and financial summary

                                                        Fiscal year ending June 30                        Total to June
                                                                                                          30, 1954, includ-
                                                                                                          ing fiscal years
                                   1950                1951           1952      1953           1954       prior to 1950 1

New work:
   Appropriated-----------........ --      ----------------                                                    $   657,366
   Cost.........--------------......------------------ -----------------------------------                         657,366
Maintenance:
   Appropriated ......------      $138, 000           $ 53,909         -$617    $20, 300      $153, 700          1,082,916
   Cost ----------------            31, 636            157, 991         2,101    20,937         19 120             947, 020

1 Includes $340,726 for new work and $41,467 for maintenance for previous projects.
  SIn addition $72,891 for new work was expended from contributed funds.
1452               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

22. SNAGGING AND CLEARING OF CHANNELS IN THE INTEREST
OF NAVIGATION UNDER AUTHORITY OF SECTION 3 OF THE
      RIVER AND HARBOR ACT APPROVED MARCH 2, 1945
  The River and Harbor Act approved March 2, 1945, authorized
the allotment of not to exceed $300,000 from any appropriation
heretofore or hereafter made for any one fiscal year for the im-
provement of rivers and harbors, for removing accumulated snags
and other debris, and for protecting, clearing, and straightening
channels in navigable harbors and navigable streams and tribu-
taries thereof; when, in the opinion of the Chief of Engineers, such
work is advisable in the interest of navigation or flood control.
   Funds in the amount of $118,338.93 have been allotted the Port-
land District to June 30, 1954, for work under this authority.
   Operations during the fiscal year 1954 consisted of the removal
of 5,026 cubic yards of material, by hired labor and rented equip-
ment, from Marshfield Channel, Coos Bay, Oreg.
  Costs during the fiscal year were $4,041.54.
  Total costs to June 30, 1954, have been $110,379.
                                                 Cost and financial summary

                                                             Fiscal year ending June 30                                  Total to June
                                                                                                                        30, 1954, includ-
                                                                                                                        ing fiscal years
                                          1950             1951              1952        1953             1954           prior to 1950
                                                     -I               I                   I                         I
                                                                                                                    i



Maintenance:
   Appropriated .___ _                   $20,000          -$1, 700 ..........            $8,400          $12,000                $118, 339
   Cost.--- ._ -----                      10, 407            7, 893-8,                      39 8           4,042                 110,379



                              23. INACTIVE                    NAVIGATION                PROJECTS

                                                                                       Cost and expenditures
                                                                                          to June 30, 1954
                                                                                                                           Estimated
                       Name of project                                                                                       amount
                                                                                                   Operation               required to
                                                                                      onstruction     and                    complete
                                                                                                  maintenance

1. John Day Dam, Columbia River, Wash. and                                  1950                   1-            .----.. $400,000,000      -------------
      Oreg.
2. The Cascades Canal, Columbia River, Oreg.L_                              1939   $3,903 780.30        $559,857.78        Completed.
3. Bridges across the Columbia at Cascade Lock                              1944    1,081,805.96                             Do.
      and Hood River, Oreg.
4. Oregon 2 Slough (North                 Portland            Harbor,       1936     416,881.30           12,576.42            Do.
      Oreg.) 3
5. Columbia Slough, Oreg-......---.....      2                 -------      1953   .---..--.-..-                  $1,150, 000
6. Multnomah Channel,       2     Oreg. _.                    __ ....       1949       18,112.28          61.33 Completed.
7. Lake River, Wash.2 ......................                                1948        2,700.00      4,000.00       Do.
8. Lewis River, Wash. _..................___
                                      2
                                                                             1950       35,880.44     74,929.36       Do.
9. Clatskanie River, Oreg. 2                         _        ---   ._      1949        3,703.34     79, 833.27      Do.
10. Skamokawa Creek, Wash.                                                   1950        2,400.00     35, 343.57      Do.
11. Skamokawa (Steamboat Slough, Wash.)                         2  2__...___ 1932                                   540,000.00
12. Youngs Bay and Youngs2 River, Oreg. -_- ...                              1949        9, 347.51        258.85  Completed.
13. Elokomin Slough, Wash.                    . ..................1943                  18,641.25         437.49  Completed.
14 . W e stpo rt S lou g h , O re
                               2  g -  .....    .   ..  .--- .
                                      -- - --- -- - -- --- - -      ....--
                                                                     - -     1953       16,276.19     68, 111.07      Do.
15. Grays River, Wash.2                                                      1951        2,500.00      6,002.29       Do.
16. Deep River, Wash. __________________________                             1950       15, 384.40    12, 435.66      Do.
17. Salmon River, Oreg ........ .............
18. Bayocean Peninsula, Oreg_-                               ---
                                                                    ....     1949
                                                                             1945           -----------..-.
                                                                                         2,145.23
                                                                                    ----- ---.                        Do.
                                                                                                                    280,000.00
19. Yaquina River, Oreg.
                                 2      - - -- - -- - - - - - - - - - -
                                                          .......            1950     6 28,800.00        776,
                                                                                                          631. 28 Completed.
20. Siuslaw River, Oreg ..............---------------..---                   1953    8 526,589.00     42,551.00       Do.
21. Smith River, Oreg-             ..            ..------.-------------      1950   --------    ------- ----        147,000.00
                                                                                                                 ---..

22. Chetco River, Oreg_                  ------------------                  1950             6.19 ....---- .----- 600,000.00
23. Coos and Millicoma Rivers, Oreg                                          1950        8,000.00     85,154.00     487,000.00
                FLOOD CONTROL--PORTLAND, OREG., DISTRICT                                    1453
  1Project abandoned due to flooding by Bonneville pool.
  2 Channel adequate for present commerce.
  s Abandonment of the project was recommended in 1916 (HD 580, 64th Cong., 1st session).
4In addition $24,556.30 was expended from contributed funds, $17,556.30 for new work and $7,000 for
maintenance.
S Local interests are to contribute two-thirds of the costs or not to exceed $20,000.

6 In addition, $43,200 was expended from contributed funds.
 * In addition, $3,000 was expended from contributed funds.
8 In addition, $322,531.59 was expended from contributed funds.

                              24. AMAZON CREEK, OREG.
   Location. On Amazon Creek, a tributary of Willamette River
in the vicinity of and below the city of Eugene, Oreg.
   Existing project. This provides for channel improvement from
a point above the south limits of the city of Eugene through the city
to the diversion point; a diversion canal 3.5 miles in length from
Amazon Creek at the diversion point to Fern Ridge Reservoir; and
an improved channel from the diversion point to Clear Lake and
from Clear Lake to Long Tom River, with 3 lateral drainage canals,
one 13,000 feet, one 15,000 feet, and one 5,000 feet in length. The
project will control the entire Amazon Creek drainage area of 62
square miles and care for a flood of 1,000 second-feet through the
city of Eugene and 1,840 second-feet at the point of diversion.
   The estimated Federal cost approved in 1954 is $1,040,000. The
estimated non-Federal cost is $688,000.
   The existing project was authorized by the Flood Control Act of
1946, Senate Document 138, 79th Congress, 2d session, and modi-
fied by the Flood Control Act of 1950, House Document 531, 81st
Congress, 2d session.
   Local cooperation. The Flood Control Act approved July 24,
1946, provided that local interests furnish assurances satisfactory
to the Secretary of War that they will (1) provide, without cost to
the United States, all lands, easements, and rights-of-way neces-
sary for the construction of the project; (2) hold and save the
United States free from damages due to the construction works;
 (3) bear the cost of fences and bridge construction and revision;
 (4) maintain and operate all the works after completion in ac-
cordance with regulations prescribed by the Secretary of War.
Local interests have furnished assurances of local cooperation.
   These assurances were approved August 2, 1951.
   Operations and results during fiscal year. Construction of the
channel improvement 5.6 miles in length from a point in the city of
Eugene, Ore. (Sta. 513/76) to the completed diversion canal lead-
ing to Fern Ridge Reservoir was initiated September 1953, by con-
tract. Operations were 75 percent complete when a stop order was
issued December 14, 1953, due to wet ground and unfavorable
working conditions. Work was resumed May 24, 1954, and the job
90 percent complete at the end of the fiscal year.
   Total costs for the fiscal year were $180,109.72, all for new work.
   Condition at end of fiscal year. Construction of the project was
initiated August 1951. The diversion channel from Amazon Creek
to Fern Ridge Reservoir including the diversion works, and a por-
tion of the channel improvement of Amazon Creek in the vicinity
of the west city limits of Eugene, Oregon have been completed and
were turned over to local interests for operation and maintenance
November 26, 1952. Construction of another section of the project
1454        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

5.6 miles in length is 90 percent complete and is scheduled to be 100
percent complete July 1954. This construction will complete a
flood control unit of the authorized plan.
   Total costs for new work have been $563,333.
                                Cost and financial summary

                                      Fiscal year ending June 30                 Total to June
                                                                                30, 1954, includ-
                                                                                ing fiscal years
                         1950        1951        1952        1953    1954        prior to 1950


New work:
   Appropriated . -----------------------------------------------    245, 000           $617, 000
   Cost ----------------  $2,713     $5,695   $297,578    $26,277   $180,110             563,333

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954__              $14,274
    Estimated additional amount needed to be appropriated for completion
      of existing project _______________________________ 423,000

  25. WILLAMETTE RIVER BASIN, PORTLAND DISTRICT, OREG.

   Location. The Willamette River is formed by the Coast and
Middle Forks which join a few miles above Eugene, Oreg., flows
north 189 miles, and enters the Columbia River 101.5 miles above
its mouth. The basin has an area of 11,200 square miles and lies
between the Cascade Range on the east and the Coast Range on the
west. The major tributaries of the Willamette River rise in the
Cascade Mountains and consist of the Coast and Middle Forks and
the McKenzie, Calapooya, Santiam, Molalla, and Clackamas Rivers.
The important tributaries that head in the Coast Range are the
Luckiamute, Yamhill, and Tualatin Rivers. Minor tributaries, all
of which enter the main stream from the west, are Marys River,
Rickreall Creek, and Long Tom River.
   Existing project. The Flood Control Act of June 28, 1938, ap-
proved the general comprehensive plan for flood control, naviga-
tion, and other purposes in the Willamette River Basin, as set forth
in House Document No. 544, 75th Congress, 3d session, and author-
ized $11,300,000 for the initiation and partial accomplishment of
the plan recommended for initial development; the reservoirs and
related works to be selected and approved by the Chief of En-
gineers.
   Subsequent Flood Control Acts authorized additional flood con-
trol works and increased the monetary authority as follows: Act of
August 18, 1941, $11 million; act of December 22, 1944, $20 mil-
lion; act of July 24, 1946, $35 million; and act of May 17, 1950, $40
million; a total authorization of $117,300,000. In addition, the act
of May 17, 1950, as amended by Public Law 75 approved June 22,
1953, contains an authorization of $150 million for the Columbia
River Basin, including the Willamette River Basin. The 1950 Act
was further amended by Public Law 363, 83d Congress, 2d session,
approved May 17, 1954, which substitutes $166,000,000 in lieu of
the $150,000,000 authorized.
   The dams and reservoirs and other improvements included in the
plan as modified by the Flood Control Act of 1950 are as follows:
                  FLOOD CONTROL-PORTLAND, OREG., DISTRICT                                                      1455

                                                                                        Estimated            Date of
               Projects and streams                          Authorizing act               cost             estimate
                                                                                                       I



Amazon Creek, Oreg.l ___                                July 24, 1946 S.D. 138, 79      $1,040,000         1954.
                                                           Cong., 2d Sess. and May
                                                           17, 1950 H.D. 531 81st
                                                           Cong. 2d Sess.
Cottage Grove Reservoir Coast Fork 1-........           June 28, 1938, H.D. 544,         2,373,294         Actual cost.
                                                           75th Cong., 3d Sess.
Dorena Res. Row R.1     ----                            ---- do_---__------.------      13, 517,101        Actual cost.
Lookout Point Res., including Dexter Rereg.             June 28, 1938, H.D. 544,        88, 600, 000       1954.
Dam.1                                                     75th Cong., 3d Sess. and
                                                           May 17, 1950, H.D. 531,
                                                           81st Cong., 2d Sess.
Hills Cr. Dam, Middle Fork 1____- __-                   ---- do-------------------
                                                                ....... ...  - -.-...   32,300,000
                                                                                             -do           1954.
Fall Creek Dam, Middle Fork 2__
Cougar Dam, South Fork McKenzie River 1         I....
                                         -__________-
                                                        June 28, 1938, H.D. 544,
                                                            75th Cong., 3d Sess.
                                                                                        18,800,000
                                                                                        31,000,000
                                                                                                           1954.
                                                                                                           1954.

Blue River Dam, McKenzie Basin 2 3--_-_.             .    --- do .____-------------.    13, 674,000        1954.
Gate Creek Dam, McKenzie Basin 2 3_ .....     _.        Not authorized- __------        13,800, 000        1954.
Cascadia Dam, South Santiam River 24____    ....   2    Not authorized _-------
                                                                              ...       25, 200, 000       1954.
Wiley Creek Dam, South Santiam River Basin 4. Not authorized....--------..               8,070,000         1954.
Green Peter Dam, Middle Santiam River 4 ..              June 28, 1938, H.D. 544,        37,100,000         1954.
                                                           75th Cong., 3d Sess.
Fern Ridge Reservoir, Long Tom River .-..- I           --- do_-__-------------
Detroit Res., including Big Cliff, North Santiam 1 _..-do...         .__.. . .. .        4,495,780         Actual cost.
                                                                                                           1954.
                                                                                        63,345,000
                                                        Power authorized by Pub-
                                                           lic Law 858, 1948.
Holley Dam, Calapooya River 2. -                        May 17, 1950, H.D. 531          12, 500, 000       1954.
                                                           81st Cong., 2d Sess.
Waldo L. Tunnel and Rereg. wks., N. Fork, May 17, 1950, H.D. 531,                          922, 000        1954.
  M. Fork, Will. R.2                                       81st Cong., 2d Sess.
Channel improvements for flood control and .....do-_-----------------                   14,800,000         1954.
  major drainage on 16 streams tributary to
  Will. R.2
Pudding River, Oreg.                                    Aug. 18, '41, S.D. 185,          6,640,000         1954.
                                                           76th Cong., 3d Sess. and
                                                           May 17, '50, H. D. 531,
                                                           81st Cong., 2d Sess.
Johnson Creek, Oreg.l_                                  May 17, '50, H.D. 531,             519, 000        1954.
                                                           81st Cong., 2d Sess.
Flood wall and levees at Portland, Oreg. 2_ ......                                      18, 900,000    1954.
                                                                                             -_---do....------------------
Willamette R. Bank protection (including bank June 28, 1938, H.D. 544,                  11,000,000     1954.
  protection on 77 additional locations on Will. R.        75th Cong., 3d Sess. and
  and 94 locations on major tributaries).1                  May 17, 1950, H.D. 531,
                                                           81st Cong., 2d Sess.
Channel clearing and2   snagging  on Will.   R.  and    May      17, 1950, H.D. 531,     2,190, 000        1954.
  major tributaries.                                       81st Cong., 2d Sess.
Will. Falls fish ladder 2________                       May 17, 1950, H.D. 531,            214,000         1954.
                                                           81st Cong., 2d Sess.
New Will. Falls 2 5 navigation lock, Will. R. at        June 28, 1938 and Mar. 2,
  Oregon City.                                              1945, H.D. 544, 75th
                                                            Cong., 3d Sess.
Open river navigation improvement, Will. R.26_          June 28, 1938, H.D. 544,
                                                            75th Cong., 3d Sess.


  1 See individual report for details of this project.
  2 Not yet selected for construction. See House Document 531, 81st Congress, 2nd session for details.
  3 Proposed in lieu of Quartz Creek Reservoir.
  4 Proposed in lieu of Sweet Home Reservoir.
  5 Re-authorized as a river and harbor project by River and Harbor Act of 1945.
  6 Included under river and harbor project "Willamette River above Portland and Yamhill River, Ore."




   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies to reservoir and dam projects. Local coop-
eration for other projects is shown in individual reports for those
projects.
   Operations and results during fiscal year. The progress of pre-
liminary work and status of operations on projects selected for
construction are given in individual reports for those projects. No
costs were incurred other than those shown under the individual
reports.
   Condition at end of fiscal year. The following projects have
been completed and are in continuous operation: Fern Ridge Res-
ervoir was completed in August 1951; Cottage Grove Reservoir,
March 1952; and Dorena Reservoir, October 1952. The Detroit
1456     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Reservoir project is essentially complete and power is being pro-
duced with all three generators.
   The Lookout Point Reservoir project is 89 percent complete.
The scheduled "in service" dates for the three generating units at
Lookout Point Dam powerhouse are December 1954, and April and
June 1955. The power unit at Dexter Reregulating Dam is sched-
uled to go on the line April 1955.
   Advance planning for construction of Hills Creek and Cougar
Dam projects was in progress during the fiscal year.
   Details of operation and construction and the financial status of
the above projects are given in the individual reports for those
projects.
   During the low-water season, July-September, supplemental
water releases are made from the Willamette River Basin reser-
voirs for conservation purposes. Interests which benefit from the
increased downstream flows include irrigation, navigation, power,
pollution abatement, and recreation. Although optimum regula-
tion cannot be provided for every conservation interest, water re-
leased from the reservoirs during the low-water season for a par-
ticular purpose will usually provide benefits to other conservation
uses as well. The basic policy is to provide the most beneficial over-
all regulation, consistent with established water-use priorities.
   The following table summarizes the status of projects author-
ized, under "Willamette River Basin, Portland, Oregon District".
                                                                      Approved                  Total new                   Cost to June 30, 1954
                                                                                                                                                        -Percent
                            Project                                      1954                 work appro-                                                 com-
                                                                      estimated                priations to                                                                                                Date construction initiated and completed
                                                                         cost                 June 30, 1954              New work            Maintenance pleted
                                                                                                                   .                                                                         1
                                                                  i
                                                                  I                                                i                                                  i
                                                                                                                                                                      I



Cottage Grove Reservoir_                  ... .      ..                $2,373,294               $2,373,294               $2,373,294                    $284,079                       100        Started in August 1940. Dam completed and in operation
                                                                                                                                                                                                   in September 1942. Project completed March 28, 1952.
Dorena Reservoir. __.......-............-.....                         13,517, 101              13,517, 101                13, 517, 101                  159, 275                     100        Relocations started in June 1941. Dam and reservoir com-      0
                                                                                                                                                                                                   pleted and in operation in October 1949. Project complete   0O
                                                                                                                                                                                                   October 1952.                                                O
Lookout Point Reservoir, including Dexter Re-                          88, 600, 000             85,176,320 79, 765,839                                                                 89        Construction of project initiated May 1947. Construction
regulating Dam.                                                                                                                                                                                   of Dexter Reregulating Dam initiated April 1953. Project    H
                                                                                                                                           -- - - -- - -
Hills Creek Dam........                                                  32, 300, 000                 462,500                   441,584
                                                                                                                                                                                                   scheduled for completion fiscal year 1957.
                                                                                                                                                                                                 Planning initiated fiscal year 1952.
                                                                                                                                                                                                                                                               O
                                                                                                                                                                                                                                                               0
Fall Creek Dam....________ __---------------                              18, 800000      _       ---
                                                                                              ----;, -
Cougar Dam....                                                           31, 000,000              S115, 500                     115,500    ----..........                                        Planning initiated fiscal year 1953.
Blue River Dam_........._____                     .____________._ 13,674,000                       196, 000                     96,000
Gate Creek Dam_......_......__ ___..._     ..........                     13,800,000                  195,000                   95, 000
Cascadia Dam ...............................                              25,200,000               1 112,000                   112,000                                                                                                                         0
Wiley Creek Dam_..................___.___....                              8,070,000               1112,000                    112,000
Green Peter Dam................................                          37,100,000                3 115, 371                  115,371
Fern Ridge Reservoir_......               .           __................. 4,495,780               4, 495,
                                                                                                        780                 4, 495, 780                  430, 613                                Construction started in April 1940. Dam and reservoir in      H
                                                                                                                                                                                      100         operation in 1942. Project completed August 1951.
Holley Dam .................. ............ ... .                       12 500n 000
                                                                       63,345,000
Detroit Reservior and Big Cliff Re-regulating                          63,   345,   000
                                                                                                63,345,000
                                                                                                63,   345,   000           61, 719,793                                                 97        Construction of project initiated May 1947. Construction
  Dam.                                                                                                                                     ...............                                        of Detroit Dam started March 1949 and completed June
                                                                                                                                                                                                  1953. Construction of Big Cliff Dam started September
                                                                                                                                                                                                  1951. Project completion date June 1955.                     z
Waldo Lake tunnel and re-regulating wks. .....                              922,000 ----------------------
Willamette Falls fish ladder_...__   ____                                   214,000 ------------
Amazon Creek, Oreg...........____________ .                              1, 040, 000      617,000        563,333                                                                       54-       Construction was initiated August 14, 1951.
                                                                                                                                                                                                                                                               rr




Pudding River, Oreg_____                                                 6, 640,000         5,000          5,000                                                                                 Costs were for advance planning.
Johnson Cr. at Ptld .........                                               519,000                                                                --- 956, -238-                                                                                              C-.
Flood wall and levees at Portland................                       18,900,000         .--------...-----....
Will. R. Basin, Bank Protection_....                                                                                                                                    ........                                                                               0
                                                                        11,000,000                5,402, 424                 5,389,985                                                 49.       Construction was initiated in 1938.
Channel Imp. for flood control and major drain-                         14,800,000        -.........---                --..........
  age on 16 tribs. to Will. R.
Channel clearing and snagging on Will. R. and                            2,190, 000        -------------                   --------                                                                                                                             1
  major tribs.
                                                                                                                                          1-------                I            ----
        Total ------..........--................                      $421,000,175            $176,040,290              $168,917, 580              $2, 008, 903                        40

   i Pro-rata cost of site selection studies.
                                                                ~
                                                          1~~~~~~~~~~~~~~~           ~ ~ ~~                                        coto ieslcinsuis
                                                                                                                             Pr-rt Icue   13,0 r-aasaeo                                                    ieslcinsuis
                                                                                                                                      3   Includes           $113,000       pro-rata         share   of   site   selection   studies.
   2 Includes $96,000 pro-rata share of site selection studies.
1458     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   26. HILLS CREEK DAM, WILLAMETTE RIVER BASIN, OREG.
    Location. On the Middle Fork Willamette River, 47.8 miles
from the mouth and 26.5 miles upstream from the Lookout Point
Dam. The Middle Fork Willamette River rises on the west slope
of the Cascade Range and flows northwesterly to its junction with
the Coast Fork Willamette River 4 miles southeast of Eugene,
Oreg., to form the main Willamette River. The location of the dam
is about 45 miles southeast from Eugene, Oreg. The drainage area
above the dam site is 389 square miles.
    Existing project. The plan of improvement provides for the
construction of an earth and gravel-fill dam about 2,215 feet long
at the crest and 304 feet high above the streambed. An ungated
spillway of the straight chute type will be located in the right abut-
ment. The dam will form a reservoir 7.5 miles long, with a usable
storage capacity of 291,000 acre-feet at normal pool level. A diver-
sion and outlet tunnel will be located in the right abutment. Power
facilities consisting of a power tunnel, surge tank, penstock, and
powerplant will be located at the right abutment. The power instal-
lation will consist of two 15,000 kilowatt units.
    The Hills Creek Dam project is an integral unit of the compre-
hensive plan for development of the water resources of the Willa-
mette River Basin. The Hills Creek and Lookout Point reservoirs
will be operated as a unit for control of floods and generation of
power on the Middle Fork Willamette River. These reservoirs, in
conjunction with the Dexter reregulating dam and the Fall Creek
flood control reservoir, will effectively control floods on the Middle
Fork and provide maximum efficient generation of hydroelectric
power.
    The Hills Creek Dam project was authorized by Public Law 516,
81st Congress, 2d session, approved May 17, 1950. The estimated
cost, revised in 1954, including power facilities, $26,863,600 for
construction and $5,436,400 for lands and damages including re-
locations, a total of $32,300,000.
    Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
    Operations and results during fiscal year. Foundation investi-
gations and design studies for preparation of the general design
memorandum were in progress.
    In May 1954 digging of a test pit for the purpose of subsurface
exploration was initiated by contract.
    Total costs for the fiscal year were $141,877.02 all for planning.
    Condition at end of fiscal year. No construction has been ac-
complished. Engineering, including field surveys and foundation
investigations, is in progress. A general design memorandum is
85 percent complete.
    Total costs have been $441,584.
                 FLOOD CONTROL--PORTLAND, OREG., DISTRICT                                                 1459
                                           Cost and financial summary

                                                    Fiscal year ending June 30                    Total to June
                                                                                                  30, 1954, includ-
                                                                                                  ing fiscal years
                                    1950          1951         1952        1953        1954        priorto 1950


New work:
   Appropriated ----------------------               -----......
                                                            $165, 000     $155, 000   $142, 500           $462, 500
   Cost-----------------...--            ----   ------------   46, 971     252, 736    141,877             441,584


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954__.- - -    $14,980.37
    Appropriated for succeeding fiscal year ending June 30, 1955_ __ 125,000.00
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955-_ --------------                  ----------     139,980.37
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project    -------------------------- 32,160,020.00

27. LOOKOUT POINT RESERVOIR (MERIDIAN SITE), WILLAMETTE
                   RIVER BASIN, OREG.
   Location. On the Middle Fork Willamette River at Meridian
site, 21.3 miles from the mouth. The Middle Fork Willamette
River rises in Lane County on the western slope of the Cascade
Range and flows northwesterly to its junction with the Coast Fork,
which is the head of the main stem Willamette River. The dam
site is approximately 22 miles southeast from Eugene, Oreg. The
drainage area tributary to the reservoir is 991 square miles.
   Existing project. The plan of improvement provides for the
construction of a main dam at the Meridian site and a reregulating
dam 3 miles downstream at the Dexter site. Both dams will be
earth and gravel fills with concrete gravity spillways and power
generating facilities. The main dam will have a height of 250 feet
above the stream bed and will be 3,175 feet long at the crest, form-
ing a reservoir 14.2 miles long and providing total storage of 456,-
000 acre-feet at normal pool level. The spillway, 274 feet long,
will be a gate-controlled overflow type, forming the right abutment.
Outlet works, consisting of slide-gate-controlled conduits, will pass
through the spillway section. The powerhouse will have 3 main
generating units totaling 120,000-kilowatt capacity. The reregu-
lating dam will have a maximum height of 80 feet above the foun-
dation and will be 2,835 feet long at the crest, forming a pool ex-
tending upstream to the main dam and providing pondage to re-
regulate Lookout Point power water releases to a uniform dis-
charge. The spillway will be a gate-controlled overflow section 476
feet long forming the right abutment. Flow regulation will be
accomplished by use of the spillway gates plus releases through
the powerhouse, which will contain one 15,000-kilowatt unit.
   Lookout Point and Dexter Dams will be operated as a single unit
of a coordinated system of dams to protect Willamette River Val-
1460      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

ley against floods, to provide needed hydroelectric power, and to
increase low water flows for navigation, irrigation, and other pur-
poses.
    The existing project, authorized as a unit of the comprehensive
plan for flood control and other purposes in the Willamette River
Basin, was authorized by the Flood Control Act of June 28, 1938,
House Document 544, 75th Congress, 3d session. The Flood Con-
trol Acts of December 22, 1944, and July 24, 1946, modified the
project to provide for recreational facilities and the Flood Control
Act of May 17, 1950, House Document 531, 81st Congress, 2d ses-
sion, modified the project to provide for power generating facilities.
    The estimated cost revised in 1954, including the Dexter re-regu-
lating dam, is $38,253,300 for lands and damages, including relo-
cations and $50,346,700 for construction, a total of $88,600,000.
    The latest (1953) approved estimate of annual cost of operation
and maintenance is $218,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
    Operationsand results during fiscal year. Lookout Point Dam:
Relocation of County Road No. 360 was accomplished November
1953, except for a short section upon which the high line track is
situated.
    Construction of the earth dam and concrete gravity spillway
was essentially complete except for installation of the spillway
crest gates and operating machinery. The powerhouse structure
progressed to 82 percent completion and installation of the me-
chanical and electrical equipment was initiated.
    Functional regulation of Lookout Point Reservoir was on an in-
terim basis during the fiscal year. The reservoir was maintained
slightly below the interim minimum pool elevation of 760 during
the summer and fall months. A flood November 22-24, 1953, had
a peak inflow of 64,400 second-feet, which was reduced to a max-
imum outflow of 21,000 second-feet. Approximately 100,000 acre-
feet of water was stored in Lookout Point Reservoir in regulating
this flood. Several lesser freshets occurred during the winter
months, all of which were fully controlled, in Middle Fork Wil-
lamette River.
    Construction activities delayed the start of conservation filling
of the reservoir until mid-April. The reservoir was filled steadily
the next two months and attained a maximum elevation of 880 on
June 21, 1954.
   Dexter Re-regulating Dam: Construction of the Dexter re-
regulating dam and powerhouse was 85 percent complete at the
end of the fiscal year with placing of concrete under way in both
structures. A contract was awarded for installation of equip-
ment in the powerhouse but work not initiated.
   Highway relocation work and reservoir clearing were completed.
   Total costs for the fiscal year were $16,325,234.96, all for new
work.
   Condition at end of fiscal year. Construction of the project
initiated May 1947 is 89 percent complete. All highway and rail-
road relocation work is complete except for a small amount of
road grading and surfacing. The Lookout Point dam is essentially
                    FLOOD CONTROL--PORTLAND, OREG., DISTRICT                                          1461
complete and the powerhouse structure is scheduled to be complete
in November 1954. The "in-service" date for generating unit No.
1 is scheduled for December 1954, Unit No. 2 for April 1955, and
the third unit is scheduled to be placed on the line in June 1955.
   Construction of Dexter re-regulating dam and powerhouse struc-
ture is scheduled for completion in December 1954.
   Re-regulation of the fluctuating flows from Lookout Point dam
will be in effect December 1954, and power on the line from the
Dexter unit is planned for April 1955.
   Fish facilities consisting of a salmon hatchery at Oakridge,
Oregon and a game fish hatchery at Leaburg, are complete and in
operation. At Dexter Dam construction of a salmon egg collect-
ing station is in progress.
   Total costs have been $79,765,839 all for new work.
                                     Cost and financial summary

                                             Fiscal year ending June 30                       Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                              1950         1951          1952         1953          1954       prior to 1950


New work:
   Appropriated-__...      $9, 500,000 $13,617, 700 $16, 000,000 $17,166,620 $18,000,000          $85, 176,320
   Cost--------.........    6,835,494   16, 347, 322 20,264,238   13, 390, 027 16, 325, 235        79, 765,839


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954------ ----        $1,049,676
    Appropriated for succeeding fiscal year ending June 30, 1955-----...... 3,000,000
    Unobligated balances available for succeeding fiscal year ending June
       30, 1955_------------------------------------------4,049,676
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project-------------------------------     ---                              423,680

28. COTTAGE GROVE RESERVOIR, WILLAMETTE RIVER BASIN,
                         OREG.
   Location. On the Coast Fork of Willamette River, 29 miles
from the mouth. The Coast Fork rises in Douglas County, Oreg.,
on the western slope of the Cascade Range and the northern slope
of the Calapooya Range, flows north for 49 miles, and unites with
the Middle Fork to form the main Willamette River. The drainage
area tributary to this reservoir is 104 square miles.
   Existing project. The plan of improvement provides for con-
struction of an earthfill dam, 1,650 feet long at the crest, rising
95 feet above the stream bed, with a reservoir providing for usable
storage of 30,000 acre-feet. The spillway, 264 feet long, is a con-
crete, gravity, overflow type forming the right abutment. Outlet
works, consisting of three gate-controlled conduits, pass through
the spillway section. The reservoir is operated as a unit of the
coordinated reservoir system to protect the Willamette River Val-
ley and to increase low water flow for navigation.
   The existing project was selected for construction under the
general authorization for the Willamette River Basin, contained
in the Flood Control Act approved June 28, 1938. The Flood Con-
trol Acts of December 22, 1944, and July 24, 1946, modified the
project to provide for recreational facilities.
1462         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   The actual cost for new work is $1,821,793.94 for construction
and $551,500 for lands and damages, a total of $2,373,293.94
   The latest (1953) approved estimate for annual cost of opera-
tion and maintenance is $35,700.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. The dam, reservoir,
and public use facilities were in continuous operation throughout
the fiscal year. A total of 56,799 persons visited the reservoir area
for recreational purposes.
   Functioning of Cottage Grove Reservoir was normal during the
fiscal year. Several freshets and minor floods, and one moderate
flood, occurred, all of which were completely controlled on Coast
Fork Willamette River.
   The largest flood occurred November 22-23, 1953, and had a
peak inflow of 10,800 second-feet, at which time the outflow was
maintained at 100 second-feet. Volume of water stored during
this flood was 20,000 acre-feet, or 67 percent of the total flood
control space in the reservoir.
   Cottage Grove Reservoir was drawn down to minimum conser-
vation pool during the months of August-October. The low natu-
ral flows in both Coast Fork and the main stem of Willamette
Rivers were supplemented by the releases from Cottage Grove and
other reservoirs during this season.
   Conservation filling was initiated on February 1, and the sched-
uled filling rate was maintained until about May 1, 1954. After
that date the reservoir inflow was inadequate to maintain the fill-
ing rate and the maximum storage attained was 27,000 acre-feet,
4,000 acre-feet below maximum conservation pool.
   Total costs for the fiscal year were $31,990 all for maintenance.
   Condition at end of fiscal year. Construction of the project
initiated August 1940 was completed April 1952.
   The dam and reservoir have been in continous operation since
September 1942.
   Total costs have been $2,657,373 of which $2,373,294 was for
new work and $284,079 for maintenance.
                                  Cost and financial summary

                                         Fiscal year ending June 30                     Total to June
                                                                                       30, 1954, includ-
                                                                                       ing fiscal years
                           1950        1951            1952       1953      1954        priorto 1950

New work:
   Appropriated .. ____   $140, 000   -$20,000    .-              $3, 206                   $2,373, 294
   Cost     ____ ___        56,809      33,735         $26, 249       995                     2,373,294
Maintenance:
   Appropriated-            31, 200     27, 200         28, 250   28,000    $36, 400            2907 250
   Cost         -31,           088      25,835          25,253    30, 714    311990             284,079


   29. DORENA RESERVOIR, WILLAMETTE                               RIVER BASIN, OREG.

  Location. Dorena Reservoir is located on Row River, Oreg., 7
miles from the mouth. Row River rises in Lane County on the
western slope of the Cascade Range, flows northwest for 19 miles,
          FLOOD CONTROL-PORTLAND, OREG., DISTRICT              1463
and enters the Coast Fork of Willamette River 191/2 miles above
the mouth. The drainage area, tributary to this reservoir, is 265
square miles.
    Existing project. The plan of improvement provides for con-
struction of an earthfill dam, 3,297 feet long at the crest, rising
145 feet above the streambed, with a reservoir providing usable
storage capacity at normal pool level of 70,000 acre-feet. The
spillway, 200 feet long, is a concrete gravity, overflow type, form-
ing the right abutment. Outlet works consisting of five slide
gate-controlled conduits pass through the spillway section. The
reservoir, controlling practically the entire drainage area of Row
River, will be operated as a unit of the coordinated reservoir sys-
tem to protect the Willamette River Valley and to increase low
water flows for navigation, and for other purposes.
    The existing project was selected for construction under the
general authorization for the Willamette River Basin contained in
the Flood Control Act approved June 28, 1938.
    The Flood Control Acts of December 22, 1944, and July 24, 1946,
modified the project to provide for recreational facilities.
    The actual cost of new work is $13,517,101.
    The approved (1953) estimate of the annual cost of operation
and maintenance is $40,300.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
    Operations and results during fiscal year. Maintenance: The
dam and reservoir were in continuous operation throughout the
fiscal year. At total of 27,687 persons visited the reservoir area
for recreational purposes.
    Functional regulation of Dorena Reservoir was normal during
the fiscal year. Several freshets and minor floods, and one mod-
erate flood, occurred all of which were completely controlled on
Coast Fork Willamette River.
    The largest flood occurred November 22-23, 1953, and had a
peak inflow of 20,400 second-feet, at which time the outflow was
maintained at 100 second-feet. Volume of water stored in Dorena
Reservoir to control this flood was 56,500 acre-feet, or 80 percent
of the total flood control space in the reservoir.
    Dorena Reservoir was drawn down to minimum conservation
pool during the months of August-October. The low natural flows
in both Coast Fork and the main stem of Willamette River were
supplemented by the releases from Dorena and other reservoirs
during this season.
    Conservation filling was initiated on February 1, 1954, but be-
cause of inadequate inflow during the latter part of the filling
season the maximum storage attained was 69,000 acre-feet, 3,000
acre-feet below maximum conservation pool.
   Total costs for the fiscal year were $32,659.23 all for mainte-
nance.
   Condition at end of fiscal year. Construction of the project
initiated in June 1941 was completed October 1952. The dam and
appurtenant works were placed in operation November 1949.
   Total costs have been $13,676,376, of which $13,517,101 was for
new work, and $159,275 for maintenance.
1464          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


                                   Cost and financial summary

                                           Fiscal year ending June 30                     Total to June
                                                                                          30, 1954, includ-

                            1950         1951         1952        1953         1954        prior to 1950


New work:
   Appropriated- .   .   $2, 500,000    $170,600    $100,000    -$132,060 ------------        $13, 517,101
   Cost.... ----          1, 777, 286    217, 671    366,034        48,846 ------------        13,517,101
Maintenance:
   Appropriated      -
                  ----       21,000       35,100      38, 520      33,500     $37, 900             166,020
   Cost.-----------------    20,172       33,955      37,446       35,042      32 659              159,275



30. FERN RIDGE RESERVOIR, WILLAMETTE RIVER BASIN, OREG.
   Location. On the Long Tom River, 23.6 miles from the mouth.
The Long Tom River rises in Lane County, Oreg., on the eastern
slope of the Coast Range, flows north for 50 miles, and enters the
Willamette River 147 miles above its mouth. The drainage area
tributary to this reservoir is 252 square miles.
   Existing project. The plan of improvement provides for con-
struction of an earthfill dam, 6,360 feet long at the crest, and two
auxiliary dikes, 850 feet and 3,680 feet long, along the north-
easterly boundary of the reservoir. The main dam has a maximum
height of 44 feet above the streambed. The spillway, located near
the left abutment, consists of a gravity section concrete overflow
structure controlled by six automatic radial gates. Outlet works
are located in the spillway structure. The project includes recti-
fication of the channel of Long Tom River downstream from the
dam. The reservoir, having a usable storage capacity of 95,000
acre-feet, protects the Long Tom River Valley and will be operated
as a unit of the coordinated reservoir system to protect the Wil-
lamette River Valley generally and to increase low water flows
for navigation.
   The existing project was selected for construction under the gen-
eral authorization for the Willamette River Basin contained in the
Flood Control Act approved June 28, 1938. The Flood Control
Acts of December 22, 1944, and July 24, 1946, modified the proj-
ect to provide for recreational facilities.
   The actual cost of new work is $3,683,145 for construction and
$812,635 for lands and damages, a total of $4,495,780.
   The latest (1953) estimate of the annual cost of operation and
maintenance is $48,400.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
  Operations and results during fiscal year. The dam, reservoir
and public use facilities were in continuous operation. A total of
113,826 persons visited the reservoir area for recreational pur-
poses.
   Several minor floods and one major flood occurred during the
winter high water season. Flood waters were stored in Fern
Ridge Reservoir so as to control the floods completely in Long Tom
River and, in conjunction with other reservoirs in Willamette
Basin, to effect substantial reductions on the main stem of the
Willamette River.
                  FLOOD CONTROL--PORTLAND, OREG., DISTRICT                                           1465
   The largest flood, which was of major flood proportions, on
Long Tom River occurred during January 27-30, 1954. Peak in-
flow into Fern Ridge Reservoir was 19,400 second-feet, which is
the greatest inflow since Fern Ridge Project has been in operation.
Flood volume was not as great as that of some previous floods,
however, and the entire inflow, except for a minimum release
of about 50 second-feet, was stored in the reservoir during the
flood. The volume of water stored was 80,000 acre-feet, or about
85 percent of the total flood control space in the reservoir.
   The reservoir was drawn down to minimum conservation pool
during the months of August-October. Natural flows in Willam-
ette River were low during this season and were augmented by
the releases from Fern Ridge and other reservoirs in the interests
of irrigation, navigation, pollution abatement, and fish life.
   Conservation filling of Fern Ridge Reservoir began February
1, as scheduled, and the reservoir was nearly full on the scheduled
date of May 1, 1954.
   Total costs for the fiscal year were $42,165.79 all for mainte-
nance.
   Condition at end of fiscal year. Construction of the project
initiated April 1940 was completed August 1951. The dam and
reservoir have been in continuous operation since December 1941.
   Total costs have been $4,926,393, of which $4,495,780 was for
new work and $430,613 for maintenance.
                                   Cost and financial summary

                                         Fiscal year ending June 30                          Total to June
                                                                                             30, 1954, includ-
                                                                                             ing fiscal years
                            1950        1951       1952            1953           1954        prior to 1950


New work:
   Appropriated    _   .   $190,000     $50, 000   -$4, 000    -$7, 945------------               $4,495,780
   Cost .....      .        192, 778     80,760     95,134    ..          ----   ----              4,495,780
Maintenance:
   Appropriated        -    45, 800      35, 700    46, 230         46, 500       $45, 400            436,030
   Cost            -----
          .----------       45,311       35,236     43,823          47,677         42,166             430,613



       31. COUGAR DAM, WILLAMETTE RIVER BASIN, OREG.
   Location. On South Fork McKenzie River 4.4 miles from the
mouth. South Fork McKenzie River flows northwesterly from its
source and joins McKenzie River about 56.5 miles above its con-
fluence with Willamette River.
   Existing project.- The plan of improvement provides for the
construction of an earth- and gravel-filled dam about 1,630 feet
long at the crest and 430 feet high above the stream bed. The dam
will form a reservoir about 6 miles long with a usable capacity at
normal pool of 182,000 acre-feet. The spillway, 288 feet long, will
be an overflow combination chute and tunnel section located in the
left abutment. The outlet tunnel and power tunnel will pass
through the right abutment. The powerhouse, when authorized,
will include one unit rated at 25,000 kilowatts and will be located
near the toe of the dam along the right abutment. The improve-
ment will function as a unit in the coordinated system of reservoirs
for multiple-purpose development of the water resources in the
1466          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Willamette River Basin.
   The project is one of three reservoirs to replace the Quartz Creek
Reservoir which was authorized by the Flood Control Act ap-
proved June 28, 1938. Authorization for Cougar Reservoir, ex-
clusive of complete power features, is contained in the Flood Con-
trol Act approved May 17, 1950. The estimated cost approved in
1954, exclusive of power, is $29,216,200 for construction and
$1,783,800 for lands and damages including relocations, a total of
$31,000,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. A topographic sur-
vey of the dam site was completed and a memorandum report
prepared recommending that inclusion of power generating facili-
ties in the project be authorized.
   Costs for the fiscal year were $7,407.52:
   Condition at end of fiscal year. No construction has been ac-
complished. Engineering studies and preliminary planning are
in progress.
   Total costs have been $115,500.
                                      Cost and financial summary

                                             Fiscal year ending June 30                         Total to June
                                                                                                30, 1954, includ-
                                                                                                ing fiscal years
                               1950         1951         1952          1953         1954         prior to 1950'

New work:
   Appropriated              - ---          --------                  $15, 000       $4, 500            $115, 500
   Cost---                                                             12,092          7,408             115,500


1 Includes $96,000 prorated share of site selection costs in lieu of Quartz Creek Reservoir.
Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project_- -                     $30,884,500

  32. GREEN PETER DAM, WILLAMETTE                                      RIVER BASIN, OREG.
   Location. On Middle Fork Santiam River, 4 miles from the
mouth and 56.8 miles from the mouth of Santiam River.
   Existing project. The plan of improvement provides for the
construction of an earth- and rock-fill dam about 1,180 feet long at
the crest and 350 feet high above the stream bed. The dam will
form a reservoir about 11 miles long with a usable capacity at
normal pool of 322,000 acre-feet. The spillway to be located in the
left abutment will consist of a free overflow chute section about
300 feet long at the crest. Outlet works will be incorporated in a
tunnel through the left abutment. The powerhouse, when author-
ized, will include two units rated at 40,500 kilowatts each and will
be located near the toe of the dam along the left abutment. The
improvement will function as a unit in the coordinated system of
reservoirs for multiple purpose development of the water resources
in Willamette River Basin.
   The project is one of the three reservoirs to replace the Sweet
Home Reservoir which was authorized by the Flood Control Act
approved June 28, 1938. Authorization for Green Peter Dam ex-
                    FLOOD CONTROL-PORTLAND, OREG., DISTRICT                                        1467
clusive of complete power features is contained in the Flood Con-
trol Act of May 17, 1950. The estimated cost approved in 1954
exclusive of power is $32,330,000 for construction and $4,770,000
for land and damages including relocations, a total of $37,100,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. Advance planning
costs were $2,371.34.
   Condition at end of fiscal year. A site selection report has been
completed and preliminary advance planning initiated for Green
Peter Dam, which is one of three dams proposed to be constructed
in lieu of Sweet Home Reservoir project, originally authorized.
   Total costs have been $115,371.
                                       Cost and financial summary

                                                    Fiscal year ending June 30             Total to June
                                                                                           30, 1954, includ-
                                                                                           ing fiscal years
                                1950            1951               1952   1953   1954      priorto 19501


New work:
   Appropriated-------_                -------------------------------           $2, 371           $115,371
   Cost                                -----                                      2,371             115,371


1 Includes $113,000 pro-rata share of site selection costs.

Other new work data: Estimated additional amount needed to be appro-
  priated for completion of existing project------ ------------  --                         36,984,629
  33. DETROIT RESERVOIR, WILLAMETTE                                        RIVER BASIN, OREG.
   Location. On North Santiam River, with dam site 60 miles
from the mouth and 45 miles southeast of Salem, Oreg. North
Santiam River flows north and west for 85 miles, and unites with
South Santiam River to form Santiam River, which 10 miles down-
stream enters the Williamette River 108 miles above its mouth.
   Existing project. The plan of improvement provides for the
construction of one main dam and a re-regulating dam, both with
power generating facilities. Detroit Dam is a concrete-gravity
structure approximately 1,580 feet in length and 379 feet in height
above riverbed. The spillway is a gate-controlled overflow section,
and the outlet works are gate-controlled conduits through the
dam. The powerhouse with two units having a capacity of 50,000
kilowatts each is located in the right abutment immediately
below the dam. The reservoir has a usable storage capacity of
340,000 acre-feet. It is being operated as a unit in the coor-
dinated reservoir system to protect the Williamette Valley from
floods, to increase low water flows in the interest of navigation
and irrigation, to generate power, and for other purposes. The
re-regulating dam located 3 miles downstream-at the Big Cliff
site will be of the concrete-gravity type, approximately 128 feet
in height above riverbed. The power installation proposed will
be one unit with a capacity of 18,000 kilowatts. The reservoir
created by the dam will have a usable storage capacity of 3,000
acre-feet.
  The project is a unit of comprehensive plan for flood control and
other purposes in the Williamette Basin. The existing project
1468     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

was selected for construction under the general authorization for
the Willamette River Basin contained in Flood Control Act ap-
proved June 28, 1938. The Flood Control Acts of December 22,
1944, and July 24, 1946, modified the project to provide for recrea-
tional facilities, and the Flood Control Act of June 30, 1948,
modified the existing project to provide for the installation of
hydroelectric power generating facilities, including the construc-
tion of a re-regulating dam.
   The estimated cost (1954) is $55,376,200 for construction and
$7,968,800 for lands and damages including relocations, a total of
$63,345,000.
   The 1953 estimate of annual cost of operation and maintenance
is $218,000.
   Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year. Detroit Dam: The
concrete gravity dam, and the powerhouse and appurtenances,
were completed. Generating unit No. 1 was in commercial opera-
tion the entire fiscal year and unit No. 2 was placed on the line
October 19, 1953.
   Grading of a short section of Kinney Creek forest access road
at the dam axis and miscellaneous minor items of modification
and cleanup were accomplished.
   Big Cliff Reregulating Dam: The dam and powerhouse were
essentially complete and installation of electrical and mechanical
equipment necessary for generator operation was accomplished.
The generating unit was placed on the line June 11, 1954. Use
of Big Cliff dam for regulating the flow from the Detroit units
was effected in October 1953.
   Routine operation and maintenance of Detroit dam and power-
house and appurtenant facilities were continued throughout the
fiscal year.
   During the fiscal year a total of 434,397,000 KWH of electrical
power energy was generated by the Detroit and Big Cliff power-
houses, of which 432,162,000 KWH was delivered to Bonneville
Power Administration.
   Functional regulation of Detroit Reservoir was normal during
the fiscal year. A number of freshets and minor floods occurred,
all of which were completely controlled in North Santiam River.
Substantial stage reductions on lower Santiam and Willamette
Rivers were effected by Detroit Reservoir during the high water
periods.
   The reservoir was drawn down from interim maximum conser-
           FLOOD CONTROL--PORTLAND, OREG., DISTRICT            1469
vation pool, elevation 1525, during the months of September-
November 1953.         Low natural flows in lower Santiam and
Willamette Rivers were supplemented by the releases from De-
troit Reservoir in the interests of conservation uses. Water was
stored for control of floods several times during the high water
season of late November through February.
   Conservation filling of the reservoir was accomplished Febru-
ary-April 1954. The reservoir was nearly at the maximum con-
servation pool elevation of 1563.5 on the scheduled date of May
5 and reached that elevation soon thereafter.
   A total of 78,346 persons visited the reservoir area for recrea-
tional purposes during the fiscal year.
   Total costs for the fiscal year were $3,159,605.19 of which
$2,980,907.37 was for new work and $178,697.82 for operation and
maintenance.
   Condition at end of fiscal year. Construction of the project
initiated in June 1947 is essentially complete.
   Remaining to complete are accomplishment of minor mechanical
and architectural features in the Big Cliff powerhouse, some road
surfacing and oiling, and miscellaneous items of modification and
cleanup.
   The three generating units are in commercial production and
the project is being operated as a unit in the coordinated reservoir
system of Willamette Valley for flood control.
   A salmon egg collecting station at Minto Pool below Big Cliff
dam and a salmon hatchery at Marion Forks have been con-
structed and are in operation.
   Total costs have been $61,898,491 of which $61,719,793 is for
new work and $178,698 for operation and maintenance.
   Powerproduction and revenues. During the first year of opera-
tion: a total of 434,397,000 kilowatt hours were generated of which
2,235,000 kilowatt hours were used for operation of the project
and 432,162,000 kilowatt hours were delivered to the Bonneville
Power Administration, the Marketing Agency, for disposition.
Revenues allocated to the project for the year amounted to $1,590,-
000.00 of which $130,651.68 was for repayment of operating
expenses applicable to power, $685,365.72 for repayment of inter-
est expense applicable to power and $773,982.60 for amortization
of construction costs, including replacement applicable to power.
Of a total of $61,898,491.18 expended to date on the project for
construction, operation and maintenance and replacements, the
amount of $39,828,186.23, or 64 percent, has been for direct and
allocated portions of power features.
1470           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Summary of governmental investments and expenses for power
purposes as of June 30, 1954, and repayments thereon are tabu-
lated below:
                                                    Investment
Construction costs (including interest during con-                               $42,480,005.04
  struction).
Replacements (net retirements) .....    _.....-.........                                         89.72

Total cost of fixed plant...~.........
Net other assets (credit balance) ....................
                                                                 ----..
                                                                 .       .
                                                                             .
                                                                                  42,480,094.76
                                                                                         151.67

        Total capital investment......                 .    .        .           ............................. $42, 479, 943.09
                                         Expenses
Operation and maintenance (excluding depreci-                                          130, 651. 68
  ation).
Interest..... .. .. .. .. .. .. ... .. .. .. .. .. ..                                  685, 365.72

        Total expenses ..........................                                      816, 017.40               816, 017.40
                                                                                                             43, 295, 960.49

                                        Repayments
Total expenses (currently repaid) .....-...... .....                                   816, 017.40
Amortization of capital investment ..             __.                                  773, 982.60
       Total repayments - -.... .        .... ....                                      ......... .           1, 590, 000.00
Net remaining capital investment to be repaid....                                     - .. ...    -          41,705,960.49

                                                                                                             43, 295, 960.49

                                       Cost and financial summary

                                                    Fiscal year ending June 30                                   Total to June
                                                                                                                30, 1954, includ-
                                                                                                                ing fiscal years
                                1950           1951             1952                 1953             1954        prior to 1950


New work:
   Appropriated_             $9,600,000 $15,862,100$16,978,000$10,299,
                                                                     000 -$366,200                                  $63, 345,000
   Cost_. _                   6,930,049  14,940, 662 20,378,703 9,337,239 2,980,907                                  61,719, 793
Maintenance:
   Appropriated_                                                                                      184,200            184,200
   Cost.   _                                                                                             698
                                                                                                      178,               178,698


Other new work data: Unobligated balance, fiscal year ending June
  30, 1954_                                                   _   $1,026,665.39

  34. WILLAMETTE                  RIVER BASIN, OREG. (BANK PROTECTION)
   Location. On Willamette River and tributaries, between the
Cascade Range and the Coast Range, from a point south of Eugene
to Portland, Oreg.
   Existing project. The plan of improvement provides for clear-
ing, sloping, and revetting of river banks; construction of pile
and timber bulkheads and drift barriers; minor channel improve-
ments; and maintenance of existing works for control of floods
and prevention of erosion at various locations along Willamette
River and its tributaries.
   The existing project was authorized by the Flood Control Act of
June 22, 1936, and June 28, 1938. The Flood Control Act of May
                       FLOOD CONTROL-PORTLAND, OREG., DISTRICT                                                           1471
17, 1950, authorized similar work at 77 additional locations.
  The estimated cost of new work revised in 1954 is $11,000,000.
  The latest approved annual cost of maintenance (1953) is
$100,000.
  Local cooperation. Section 204 of the Flood Control Act of May
17, 1950, applies.
  Operations and results during fiscal year. New work: A total
of 20,195 linear feet of bank protection works was completed
during the fiscal year at the following listed locations on Wil-
lamette River and tributaries:

                               Location                                                                              Quantity
                                                                                        Nature of work              (linear feet)

                        WILLAMETTE RIVER

Hathaway, R/B, Middle Channel opposite Mile 139.....                         Dumped stone revetment .-..                    1, 503
* Stallbush Island, R/B, Mile 135.2-------------------....................        do
                                                                              --.....  .............                        2, 673
                       SOUTH SANTIAM RIVER

* Cox, L/B & R/B, Mile 18.8.................----------------------           Dumped stone revetment and                    11, 827
                                                                              channel rectification.
  Crenshaw, L/B, Mile 16.2......-----------------------                      Dumped stone revetment .....                   1, 226
* Blakeley, R/B, Mile 14.9------------------------Dumped stone revetment and                                                1, 195
                                                                                  channel rectification.
                         CALAPOOYA RIVER

* Henshaw, R/B, Mile 38-------------------------                             Dumped stone revetment and                     1, 771
                                                                                  channel rectification.
       Total linear feet_.             ....................          .. .    ..           .     ...   ...   .....          20, 195

  * Minor additional work will be accomplished at these locations in fiscal year 1955.


   Contracts were awarded for construction, and work initiated
at Morriss Location on McKenzie River and at Eagle Location on
South Santiam River. Plans and specifications were completed,
but advertisement of the work at the following locations was in
abeyance pending receipts of rights-of-way from local interests:
Laird and Wilson Locations on Middle Fork and Half Moon Bend
Location on main stem of Willamette River.
   Maintenance: Repair of existing bank protection works at
various locations on Willamette River and tributaries was com-
pleted by contract and by hired labor.
   Total costs for the fiscal year were $515,298.86 of which $464,-
946.00 was for new work and $50,352.86 for maintenance.
   Condition at end of fiscal year. Construction of the project
initiated in 1938 is 49 percent complete. A total of 257,918 linear
feet of bank protection works, consisting of the revetment of
river banks, pile and timber bulkheads, drift barriers and channel
improvement, having been completed on Willamette River and
tributaries. The Annual Reports for the fiscal years 1949-1953
itemized 237,723 linear feet of this total by streams and locations.
   Total costs to June 30, 1954, from Federal funds have been
$6,346,223 of which $956,238 has been for maintenance and
$5,389,985 for new work as follows:



         Sig 47-1471-1502
1472           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954


                    Stream                           Regular funds           Emergency                   Total
                                                                             relief funds

Willamette River                                 $3,450,412.00         $131,767.89                 $3,582,179.89
McKenzie River_                                     455,130.87               21.66                    455,152.53
Clackamas River                                      23,019.21           21,600.00                     44,619.21
Molalla River                                       152,240.79          122,477.91                    274,718.70
Santiam River---                        ..          882,207.59               72.54                    882,280.13
Tualatin River                                       68,941.97                                         68,941.97
Marys River and Muddy Creek_ _ _                         9,271.82                                          9,271.82
Calapooya River .........                                72,820.74      --            _                  72,820.74
         Total, all funds                            5,114,044.99            275,940.00               5,389,984.99

  In addition $43,969.05 has been expended for new work on Willamette River from contributed funds.


                                         Cost and financial summary


                                               Fiscal year ending June 30                              Total to June
                                                                                                      30, 1954, includ-
                                                                                                       ing fiscal years
                                 1950         1951          1952        1953                1954        prior to 1950 '


New work:
   Appropriated .-          .   $450,000     $450,000      $400,000    $398,000        $310,000             $5, 402424
   Cost ...----------------      376, 155     357, 120      515, 071    285, 682        464,946              5,389985
Maintenance:
    Appropriated ..          61,000            66,000        66,000      43,800              21,500              963 300
    Cost----------------176,806                58,853        23,535     123,007              50,353              956,238


  1In addition $43,969 for new work was expended from contributed funds.
Other new work data:
    Appropriated for succeeding fiscal year ending June 30, 1955________  $300,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955------------ -------------------------------------- 300,000
    Estimated additional amount needed to be appropriated for comple-
         tion of existing project_----------------                                                       5,297,576


       35. LOWER COLUMBIA RIVER BASIN, OREG. AND WASH.

  Location. On Columbia River and minor tributaries, channels,
and sloughs, between Sandy River, Oreg., approximately 15 miles
east of Vancouver, Wash., and the mouth of Columbia River.
  Existing project. The plan of improvement for bank protection,
construction of flood control works, and improvements to existing
projects, in the lower Columbia River Basin was authorized by
the Flood Control Act approved May 17, 1950, House Document
531, 81st Congress, 2d session.
  The plan provides for new construction and for supplementing
and extending projects authorized by the Flood Control Act of
June 22, 1936, in the Columbia, Lewis, and Cowlitz River Basins,
as follows:
    a. Lower Columbia River Basin levees at new locations, Oregon
and Washington. This provides for flood control works at five
                       FLOOD CONTROL-PORTLAND, OREG., DISTRICT                                                                              1473
     Washougal area, Clark County, Wash., approximately 5% miles of levee and
       other appurtenant works at an estimated cost of $670,000 from Federal funds.
     Hayden Island, Oreg., approximately 4 miles of levee and other appurtenant
       works at an estimated cost of $546,200 from Federal funds.
     Vancouver Lake area, in vicinity of Vancouver, Wash., approximately 11 miles
       of levee and other appurtenant works at an estimated cost of $3,374,000 from
       Federal funds.
     Kalama River (south area) Cowlitz County, Wash., approximately 3 miles of
       levee and other appurtenant works at an estimated cost of $754,700 from
       Federal funds.
     Clatskanie River area, Oreg., approximately 2,000 feet of bulkhead and levee
       and other appurtenant work at an estimated cost of $156,000 from Federal
       funds.

   The estimated total Federal cost approved in 1954 is $5,500,000.
   The estimated non-Federal cost is $1,349,100.
   b. Lower Columbia River Basin bank protection works, Oregon
and Washington. This improvement provides for bank protection
works at 66 locations on Columbia River and tributaries between
Sandy River and mouth of Columbia River, totaling approximately
123,800 linear feet.
   The estimated total cost approved in 1954 is $6,880,000.
   c. Lower Columbia River Basin levees and improvement to ex-
isting projects. This provides for improvements to existing
projects as delineated below:
                                                                                                                                Estimated cost of
Location                                                                                                           work approved in 1964
    Sandy drainage district, Multnomah County, Oreg............................                                                                $15, 400*
    Multnomah drainage district No. 1, Multnomah County, Oreg-                                                                           .. 1, 550,000
    Peninsula drainage district No. 2, Multnomah County, Oreg--..... .. 1,000, 000
    Peninsula drainage district No. 1, Multnomah County, Oreg.............                                                                     790,000
    Sauvie Island (areas A and B) ....                                          ------------------------------                                 574, 000
    Columbia drainage district No. 1                                              ------------------------...------..                       1, 197, 000
    Bachelor Island, Clark County, Wash...........-.......... .........-............. 2, 132, 000
    Scappoose drainage district, Columbia County, Oreg..--...................                                                                  817, 000
    Lewis River area.......................................................---------------------------..................-------.....           859, 000
    Cowlitz diking and improvement district Nos. 5 and 11...................... 1,255,000
    Deer Island drainage district....................................................................                                          382,000
    Cowlitz County diking and improvement districts Nos. 2 and 13_.....                                                                        389, 000
    Consolidated diking and improvement district No. 1, Cowlitz County,
      Wash.........--......-------------------.................................................................---------------.......       1,400,000
    Cowlitz County diking improvement district No. 15..................--------------                                                          212,000
    Rainier drainage district, Columbia County, Oreg-............--.................                                                           520, 000
    John drainage district.........------------..-----------------..................................--------...................                 87, 000
    Beaver drainage district, Columbia County, Oreg---------.....------....................                                                    186, 000
    Clatskanie drainage district......................................................--------------------                                     162,000
    Magruder drainage district, Columbia County, Oreg......-----------..-....-.                                                           .     62,000
    Midland drainage district, Columbia County, Oreg-------..-.-..-............                                              ...               108, 000
    Woodson drainage district, Columbia County, Oreg-----------.....-__......__.                                                                81,000
    Puget Island Area, Wahkiakum diking districts Nos. 1 and 3... _____.. 1, 100, 000
    Tenasillahee Island diking district No. 6....__.......__--.................__                                                        ..     46, 000
    Wahkiakum diking district No. 4.---..............._......._..............                                                           ..     324,000
    Clatsop County diking district No. 4.........._............ ...............                                                  .      ..      31, 000
    Clatsop County drainage district No. 1. __................                                                                        ....
                                                                                                                     __............._....       20,600
   Construction was accomplished by local interests at no cost to the Government.

   The estimated total cost from Federal funds approved in 1954
is $15,300,000.
1474     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  The estimated non-Federal cost is $725,200.
  The approved 1954 Federal cost of all work under the lower
Columbia River Basin, Oregon and Washington, as authorized by
the Flood Control Act of May 17, 1950, is $27,680,000.
  Local cooperation. The Flood Control Act of May 17, 1950, pro-
vides that local interests: (1) Provide without cost to the United
States all lands, easements, and rights-of-way; (2) make all
necessary highway, highway bridge, and utility alterations; (3)
hold and save the United States free from all damages due to the
construction works; and (4) maintain and operate the works after
completion in accordance with regulations prescribed by the
Secretary of the Army.
  Operations and results during fiscal year. The progress of en-
gineering and construction accomplished is given under individual
report for Sandy Drainage District, Improvement to Existing
Projects.
  Condition at end of fiscal year. Construction of the improve-
ment to the existing project in Sandy Drainage District has been
completed, at no cost to the Government, by local interests.

36. SANDY DRAINAGE DISTRICT, MULTNOMAH COUNTY, OREG.,
LOWER COLUMBIA RIVER BASIN LEVEES AND IMPROVEMENT
                 TO EXISTING PROJECTS
   Location. This district is located in Multnomah County, Oreg.,
near the town of Troutdale about 13 miles east of Vancouver,
Wash., and 119 miles and 121.5 miles above the mouth of Columbia
River at lower and upper ends respectively.
   Existing project. The plan of improvement provides for
strengthening existing levee on the landward side by the addition
of pervious material between stations 0+00 and 145+00 and the
installation of type 2 toe drains along the levee at various locations
as needed.
   The estimated cost: Construction of the project as authorized
has been completed by the Sandy Drainage District at no cost to
the Federal Government.
   Local cooperation. Requirements of the Flood Control Act of
May 17, 1950 applied.
   Operations and results during fiscal year. A "General Design
Memorandum" covering the authorized improvement was com-
pleted. Construction of the project as authorized was accom-
plished by local interests at no cost to the Government.
   Total costs for the fiscal year from Federal funds were $5,277.97
for advance engineering and design.
   Condition at end of fiscal year. All authorized construction
work has been completed by local interests.
   Total costs from Federal funds have been $15,049 all for ad-
vance engineering and design.
                             FLOOD CONTROL--PORTLAND, OREG., DISTRICT                                                                             1475
                                                         Cost andfinancial summary

                                                                        Fiscal year ending June 30                                        Total to June
                                                                                                                                         30, 1954, includ-
                                                                                                                                         ing fiscal years
                                                 1950               1951                1952               1953            1954            prior to 1950


New work:
    Appropriated- ..----                                                                                   $15,355          -$306                     $15,049
    Cost                                                    -       -     --                                 9, 771          5, 278                    15,049

                             37. INACTIVE                         FLOOD CONTROL                                PROJECTS
                             37.      INACTIVE                    FL~OOD              CONTROL                  PROJECTS




                                                                                                         Cost and expenditures
                                                                                                           to June 30, 1954
                                                                                     For last                                                Estimated
                           Name of project                                         full report,                                               amount
                                                                                   see annual                    Operation                  required to
                                                                                   report for-     Construction     and                      complete
                                                                                                                maintenance
                                                                          --   i                  1-11
                      COLUMBIA RIVER BASIN
  1. Diking and improvement district 5, Cowlitz
      County, Wash.                                ---                --              1940          $161,380.07 .---------                       (1)
2. Beaver drainage district, Columbia County,
      Oreg.---------                                                                  1940               274, 578.03   -----------               (1)
  3. Magruder drainage                          district,       Columbia
      County, Oreg-....-----                                         .----------      1940                61,186.49 --.........                  ()
4. Midland drainage district, Columbia County,
      Oreg.......                                                                     1939                77,743.64    .--- -                    (1)
  5. Marshland drainage district, Columbia
      County, Oreg....---------------------                                           1940                39,474.74    ----------                (1)
  6. Webb-District Improvement Co., Columbia
      County, Oreg-------------------.......--                                        1940                84,591.68 ._------                     (1)
  7. Woodson drainage district, Columbia County,
      Oreg---------........                -------------------                        1940                22,796.86 ........ __                  (1)
8. Westland District Improvement Co., Colum-
      bia County, Oreg..--------------------------.                                   1940               205, 531.21 --------------             (1)
9. Tenasillabe Island, Clatsop County, Oreg ...                                      1939               133,778.47                             (1)
                                                                                                                       -------------

10. Blind slough diking district, Clatsop County,
      Oreg................................--------                                    1939           163,396.66        --------------           (1)
11. Drainage district 1, Clatsop County, Oreg -_.                                     1939           240, 939.43       --------------           (1)
12. Diking district 2, Clatsop County, Oreg                                 -         1940            43,149, 78       --------------           (1)
13. Diking district 5, Clatsop County, Oreg .. ..                                     1940            25,608.49        --------------           (1)
14. Warrenton diking district 1, Clatsop County,
      Oreg ..............                .......--     .           ..------- -        1940               69, 503.03 --------------              (1)
15. Warrenton diking district 2, Clatsop County,
      Oreg......----------                 ------------------                         1940               117,142.92 --------------               (1)
16. Warrenton diking district 3, Clatsop County,
      Oreg......----------------------------.                                         1940                74, 596.11 --------------             (1)
17. Consolidated diking and improvement dis-
      trict 1, Cowlitz County, Wash .............                                     1941               163, 290.97 --------------              (1)
18. Diking districts 1 and 3 (Puget Island) and
      Little Island, Wahkiakum County, Wash..                                         1941               258, 795.11 --------------
19. Diking improvement district 1, Pacific                                                                                                      (1)
      County, Wash-------.--                             ------------                 1941               26,810.33
20. Karlson Island, Clatsop County, Oreg ._-                              --          1941
                                                                                                                       --------------

                                                                                                         25,773.40 --------------               (1)
                                                                                                                                                (1)
21. Deep River area, Wahkiakum County, Wash_                                          1942               69,723.84 --------------
22. Sandy drainage district, Multnomah County,                                                                                                  (1)
      Oreg...__.----------                       .-------------------                 1942           138, 955.89 --------------
23. Peninsula drainage district 1, Multnomah                                                                                                    (1)
      County, Oreg..........................                                          1942           211,250.51        --------------
24. Peninsula drainage district 2, Multnomah                                                                                                    (1)
      County, Oreg- ............................                                      1942           241,148.60 --------------                  (L)
25. Seappoose drainage district, Columbia
      County, Oreg .................                           --...                  1942           424,309.56 --------------                  (')
26. Rainier drainage district, Columbia County,
      Oreg...............................----------------------------                 1942            47,661.88 --------------                  (1)
27. Knappa area, Clatsop County, Oreg-....___..                                       1942            18, 788.70 --------------                 (1)
28. John Day River area, Clatsop County, Oreg_                                        1942            33,080.38 --------------                  (1)
29. Walluski River, Clatsop County, Oreg......                                        1942            66,932.39 --------------                  (1)
30. Youngs River Dikes, Clatsop County, Oreg_                                         1942           248,802.48 --------------                  (1)
31. Lewis and Clark River area, Clatsop County
      Oreg........--...........................                                       1942           158, 418.51 --------------                 (1)
32. Deer Island area, Columbia County, Oreg_ .                                        1943           574,122.85 --------------                  (1)
33. Westport district, Columbia and Clatsop
      Counties, Oreg....                       ---------.................             1943               40,657.64                              (1)
34. Skamokawa Creek area, Wahkiakum County,
         W ash-.............. ..........
                                     --                         .--
                                                                -- -- --              1946           178,884.82._
                                                                                                                -                               (1)
35. Upper Grays River area, Wash ..............                                       1947            61,263.40                 30,000          (1)
36. Multnomah diking district 1, Oreg.......                                          1951           610,652.28                                 (1)
  See footnotes at end of table.
 1476              REPORT OF CHIEF OF ENGINEERS,                                      U.     S. ARMY,      1954


                                                                                     Cost and expenditures
                                                                                       to June 30, 1954
                                                                      For last                                    Estimated
                                                                    full report,                                    amount
                       Name of project                                        1
                                                                    see annual I
                                                                    report for- Construction
                                                                              -I
                                                                                                     Operations
                                                                                                        and
                                                                                                                  required to
                                                                                                                   complete
                                                                                                    maintenance


37. Sauvie Island areas A and B, Multnomah
      C ounty, Oreg _._.........................                       1951        1,623,505.42                       (1)
38. Diking and improvement district 4, Wahkia-
      kum County, Wash--------                                         1951         169,542.29--------------          (1)
39. Prescott area, Columbia County, Oreg_ .....                        1941            124.88                          2 37, 875
40. Diking district 3, Clatsop County, Oreg.......                     1938            258.28                           2 4, 740
41. Local protection projects......---------------                     1950                                           (4)

        Total Columbia River Basin --------------                                  7,188,152.02          30,000            42,615
                    LEWIS RIVER BASIN

42. Diking and improvement district 11, Cow-
     litz County, Wash........------------------                       1943        $172,521.40                        (1)

                   COWLITZ RIVER BASIN

43. Cowlitz County drainage improvement dis-
     trict 1, Wash ....                                                1939          42,078.11 -- -- -__ -----        (1)
44. Diking improvement district 2, Cowlitz
     County, Wash__                                                    1940         120,728.84-                       (1)
45. Diking improvement district 13, Cowlitz
     County, Wash _           -                                        1939          26,262.78                       (1)

            Total Cowlitz River Basin--------------                                 189,069.73                       (I)

46. Castle Rock, Cowlitz River, Wash .-.-------                       1949            3,499.90 ------------          $143, 500
47. Mill Four drainage district, Yaquina River,
      Oreg-    Alkali............................                      1949         118,432.84                        (1)
48. Arlington, Alkali Canyon, Oreg -..    .-.   -                      1950          20,111.51                       3 492, 689
49. Pudding River, Oreg_----- ....    __ __    ...                     1950           3,933.62                      6,640,000
50. Johnson Creek at Portland and vicinity, Oreg_                      1953                                           519,000
51. Coquille River, Oreg-....                                          1948                908.15                    2 353, 092
52. Umpqua River and tributaries, Oreg .........                       1952         428,880.60                       (1)
53. Vicinity of Nehalem, Nehalem River, Oreg___                        1952          45,677.12                       (1)
               WILLAMETTE RIVER BASIN

Blue River Dam----------------------..   ..        .          ---                                                  13,674,000
Cascadia Dam .................---------------.                                                                     25, 200, 000
H olley Dam ----.....         ....... ...... ....... .....                                                         12,500,000
G ate Creek D am ---.........            .......... .........                                                      13, 800, 000
W aldo Lake Tunnel----------------------------_                                                                       922,000
W iley Creek Dam----... ...... .....                 ...... ....                                                    8,070,000
Flood wall and levees at Portland, Oreg --.....                                                                    18,900,000
Willamette River Basin Channel clearing and
  snagging----..........................                                                                            2,190,000
Willamette Falls fish ladder---- -----------------                                                                    214,000
Channel improvement for flood control and ma-
  jor drainage on 16 tributaries to Willamette
  River----------------------------------                                                                          14,800,000

   1 Completed.
   3 Awaiting local cooperation.

  3 Construction of John Day Dam will inundate the site of authorized work.
   ' The Flood Control Act approved May 17, 1950, approved a general comprehensive plan for the Columbia
River Basin for flood control and other purposes as set forth in House Document 531, 81st Congress, 2d
session, and authorized the sum of $75 million to be appropriated for the partial accomplishment of certain
projects. Of this authorization, an amount not to exceed $15 million was authorized for the construction
of local flood protection works throughout the Columbia River Basin, subject to the conditions that all
work undertaken pursuant to this authority shall be economically justified prior to construction, and
local cooperation specified in the 1936 Flood Control Act, as amended, shall be required.


                                    38. GENERAL INVESTIGATIONS
  Examinations and surveys. Navigation studies: The total cost
of work during the fiscal year was $8,535.18. Total costs to June
30, 1954, have been $3,843,015.
  The funds unexpended June 30, 1954, amounting to $5,045,06
           FLOOD CONTROL-PORTLAND, OREG., DISTRICT              1477
plus an allotment of $10,400, a total of $15,445.06, will be expended
during fiscal year 1955 for completion of the following reports:
Chetco Cove, Oregon; Siuslaw River and Bar, Oregon; Winchester
Bay, Oregon; and Yaquina Bay and Harbor, Oregon.
    Flood control studies. The total cost of work during the fiscal
year was $15,516.62. Total costs to June 30, 1954, have been
$2,577,297.
   An allotment of $10,000 will be expended during fiscal year
1955 to continue preparation of the report on Silvies River and
Tributaries, Oregon. Expenditure of this amount will bring the
report to approximately 80 percent completion.
   Collection and study of basic data. The principal items of work
included under miscellaneous studies are as follows:
   a. Hydrologic studies, consisting of preparing hydrologic data,
in answer to various inquiries, for areas not associated with proj-
ects for which funds are available.
    b. Derivation of flood forecasting procedures, which consists of
compiling and analyzing stream-flow, temperature and precipita-
tion data in order to forecast and disseminate information on flood
volume and peak discharges for Columbia River and major trib-
utaries.
    c. Investigation of the general behavior of snow, which consists
of work in coordination with North Pacific Division to establish
basic data to be used in flood and run-off volume forecasting.
   d. Compiling and distributing weather and river stage data,
which consists of daily compilation and distribution to those con-
cerned within the office of data obtained from the U. S. Weather
Bureau and Corps of Engineer field offices as a basis for normal
functioning of the organization.
   Total costs for the fiscal year were $2,779.92.
   Total costs to June 30, 1954, have been $378,622.
    39. INSPECTION OF COMPLETED FLOOD CONTROL WORKS
   Funds in the amount of $19,450.00 have been allotted to June 30,
1954, to cover costs of inspections of completed local flood control
protection projects. The purposes of the inspection are to deter-
mine the condition of the completed works and to ascertain
whether those works are being properly maintained by local
interests.
   A total of 32 diking districts (9 in Washington and 23 in
Oregon) along Columbia River were inspected. In most cases
a representative of the diking districts accompanied the Portland
District Inspector in making the inspections of their districts.
Deficiencies in maintenance and the need for repairs were pointed
out to the diking districts' representatives on the ground and a
report was made for each district inspected on the conditions
found with recommendations for correction of deficiencies. Copies
of these reports were furnished the diking districts concerned.
   Costs for the fiscal year were $4,568.41.
   Total costs to June 30, 1954, have been $12,410.
1478           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                      Cost andfinancial summary

                                            Fiscal year ending June 30                       Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                               1950        1951           1952       1953        1954         priorto 1950

Maintenance:
   Appropriated........      .....          $5,750    ------------   $13,700 .......-                   $19,450
   Cost................. _..........--.-                   $4,618      3,224       $4,568                12,410


40. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
   Emergency bank protection (Section 14 of the 1946 Flood Con-
trol Act).
   In addition to funds in the amount of $413,302 previously
allotted, funds in the amount of $50,000 were allotted during the
fiscal year for emergency work at Pierce Riffle Location, Rogue
River, Oreg., to protect the main gravity canal of Grants Pass
Irrigation District from destruction by erosion of the river bank
during flood stages of Rogue River. For accomplishment of the
work the Grants Pass Irrigation District must make a cash con-
tribution of $75,000.
   Operations during the fiscal year consisted of the preparation
of contract plans and specifications for emergency bank protection
on Clackamas River near Gladstone, Oreg., and for the work at
Pierce Riffle on Rogue River. A contract was awarded for the
work on Clackamas River, but operations were not initiated.
   Costs from Federal funds during the fiscal year were $5,497.
   Total costs from Federal funds have been $407,799.
   In addition, costs from contributed funds have been $65,190.
                                      Cost andfinancial summary

                                            Fiscal year ending June 30                       Total to June
                                                                                            30, 1954, includ-
                                                                                            ing   fiscal years
                               1950        1951           1952       1953        1954        prior to 19501


New work:
   Appropriated----.          -$3 516      $50, 000       $46, 000    -$677      $50, 000             $463, 302
    Cost....        .            4,792      50,000         2,475     31,848         5,497              407, 799


1 In addition $65,190 for new work was expended from contributed funds.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954__----------- -                             46,479
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955------------------             ----------------------------                                46,479

  Small flood control projects not specifically authorized by Con-
gress. (Section 212 of the 1950 Flood Control Act.)
  To June 30, 1954, a total of $167,914 has been allotted from
Federal funds for the preparation of project reports and for con-
                  FLOOD CONTROL-PORTLAND, OREG., DISTRICT                                          1479
struction. In addition, the amount of $4,120 has been contributed
by local interests.
   During the fiscal year the preparation of project reports was in
progress to determine if construction of protective works would
be economically feasible at Catching Inlet Drainage District,
Coos River, Oregon, and in the vicinity of Cushman on Siuslaw
and North Fork Siuslaw Rivers, Oreg. Contract plans and specifi-
cations were prepared for proposed construction on Molalla River
at Milk Creek, Oreg., but advertisement for bids was in abeyance
pending receipt of grant of right-of-way, provision of which was
assured by local interests.
   Costs for the fiscal year from Federal funds were $10,173.
   Total costs to June 30, 1954 from Federal funds have been
$96,338.
   In addition, costs from contributed funds have been $2,520.
                                       Cost and financial summary

                                              Fiscal year ending June 30                    Total to June
                                                         ......       ..                   30, 1954, includ-
                                                                                           ing fiscal years
                                1950        1951        1952         1953       1954        prior to 1950 1

New work:
    Appropriated -------------------        $88, 340    $ 2,300       $8, 274   $69, 000           $167, 914
    Cost..--------------------------          7, 337     78,777            51    10,173              96, 338

  1In addition $2,520   for new work was expended from contributed funds.
Other new work data: Unobligated balance, fiscal year ending June 30, 1954_                      $64, 519

  Flood control emergencies--repair, flood fighting and rescue
work. (Section 210 of the 1950 Flood Control Act and supple-
mental authorizations.)
  Funds in the amount of $7,060,845.86 have been allotted the
Portland District to June 30, 1954, for work under this and prior
authorities.
  Total costs during the fiscal year were $30,679.51 for emergency
repair work at Columbia Drainage District No. 1, Oregon and for
engineering and revision of flood manuals.
   Total costs to June 30, 1954, have been $7,026,371.
   In addition, $145,000 has been expended from contributed funds.
                                       Cost and financial summary

                                             Fiscal year ending June 30                    Total to June
                                                                                           30, 1954, includ-
                                                                                           ing fiscal years
                                1950        1951        1952         1953       1954        prior to 19501


Maintenance:
   Appropriated --------       $ 80,659    $131, 729    $28, 760     $12,342    $42, 651        $7, 060, 846
   Cost ----------------       605, 688     177, 024     22,353       88,576    30, 680           7, 026,371

  1In addition $145,000 for maintenance was expended from contributed funds.
     IMPROVEMENT OF RIVERS AND HARBORS IN THE
              SEATTLE, WASH., DISTRICT
   This district comprises all of Washington except the southern
and southeastern portions, northern Idaho, and northwestern
Montana embraced in the drainage basins tributary to the Pacific
Ocean south of the international boundary to Cape Disappoint-
ment, and to the Columbia River above the Yakima River, in-
clusive.
                                                IMPROVEMENTS

                      Navigation                                             Navigation-Continued
                                                      Page                                                                Page
1. Puget Sound and its tributary                         16. Willapa River and Harbor,
      waters, Wash..........._ ..........            1481        Wash----------------...................................... 1511
2. Bellingham Harbor, Wash ------ _                 1482 17. Inactive navigation projects .... 1514
3. Anacortes Harbor, Wash.........                  1485
4. Swinomish Slough, Wash..-.                       1486                    Flood Control
5. Neah Bay, Wash-.....................             1487 18. Libby Dam, Kootenai River,
6. Lake Crockett, Wash..............                1488        Mont ..................................... 1514
7. Waterway        connecting Port                       19. Albeni Falls Reservoir, Pend
      Townsend Bay and Oak Bay,                                  Oreille River, Idaho.............                          1516
      Wash.......................................    1489 20. Stillaguamish River, Wash.......                              1518
8. Everett Harbor, Wash....-....                    1490 21. Eagle Gorge Reservoir, Green
9. Chief Joseph Dam, Columbia                                  River, W ash .......................                        1519
      River, Wash............................        1492 22. Tacoma, Puyallup River, Wash.. 1520
10. Quillayute River, Wash............               1495 23. Mud        Mountain                   Reservoir,
11. Lake Washington Ship Canal,                                 White River, Wash ..........                 -              1521
      Wash........................................   1497 24. Inactive flood control projects.. 1523
12. Seattle Harbor, Wash................             1499 25. General investigations...............                         1523
13. Tacoma Harbor, Wash ...........                  1501 26. Inspection of completed works,
14. Olympia Harbor, Wash ..........                  1504       local protection projects....... 1524
15. Grays Harbor and Chehalis                             27. Flood control work under special
      River, Wash .......................            1506       authorization..-.. ......_....... 1524

1. PUGET SOUND AND ITS TRIBUTARY WATERS, WASHINGTON
   Location. Puget Sound is located in the western part of the
State of Washington. (See U. S. Coast and Geodetic Survey Charts
Nos. 6300, 6450, and 6460.)
   Previous projects. Project adopted by the River and Harbor
Act of August 2, 1882, contemplated clearing and maintaining the
navigable portions of the Skagit, Stillaguamish, Nooksack, Sno-
homish, and Snoqualmie Rivers, Wash., free from snags, debris,
and drift, by means of a shallow-draft stern wheel snag boat con-
structed for this purpose. For further details, see page 2003 of
Annual Report for 1915 and page 1869 of Annual Report for 1938.
   Existing project. This provides for maintenance of Puget
Sound and its tributary waters by snagging and dredging. The
actual cost for new work was $43,336.92. The latest (1953) ap-
proved estimate for annual cost of maintenance is $165,000. The
existing project was adopted by the River and Harbor Act of
July 13, 1892 (Annual Report for 1893, p. 3425).       The latest
published map is in the Annual Report for 1913, page 3127.
   Local cooperation. None required.
                                                                                                           1481
1482              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

    Terminal facilities.                        The terminal facilities at the numerous
localities on Puget Sound and its tributary waters are, in general,
considered adequate for existing commerce.
    Operations and results during fiscal year.                                                    Floating obstruc-
tions to navigation were removed from ship lanes in the Seattle
area by two small United States tugs during the fiscal year, at a
cost of $1,663.87.                   The United States snagboat W. T. Preston was
operated a total of 101/2 months at a cost of $98,217.48, accom-
plishing the following work:

                                                        Obstructions
                                          Dredging       removed
             Waterway                      (cubic                                              Miscellaneous
                                           yards)
                                                        Snags     Piles


Agate Pass..-----------------------------                    2----
Duwamish Waterway .......               7                  220    1          Disposed of 376 cords of floating debris, and
                                                                              1 rowboat.
Everett Harbor and Snohomish        ....------...        467           72    Removed 189 cubic yards of dike rock from
  River.                                                                      channel.
Lake Washington- --.         ....--             -..... 1, 171          14    Disposed of miscellaneous floating debris, in-
                                                                              cluding 8 rafts, 12 bundles of lumber, 1
                                                                              houseboat, and 1 rowboat.
Lake Washington Ship Canal_ ... __....                    842     .          Burned debris at lock site, including 8 rafts,
                                                                              6 floats, 1 launch, 3 rowboats, 73 cords of
                                                                              wood, and 1 dolphin.
Olympia Harbor.....-----------------------......            11 .......
Shelton Harbor   ... o   or...
        SetnHro---------------_--------.....       8     5 42, ----
Skagit River and North Fork..                27, 718     511        141
Tacoma Harbor          .        ........           5-- 3------
                                                         246         .--     Removed 1 scow.
      Total.__--.- --..        .             27, 725 3, 274         228



  Condition surveys were made at a cost of $1,750.75. The cost
of miscellaneous inspections and reports was $1,241.49.
  Total costs were $102,873.59, all for maintenance.
  Condition at end of fiscal year. The work has consisted chiefly
of snagging and dredging in the principal tributaries of Puget
Sound. No permanent results are obtainable, but the maintenance
of existing channels requires practically continuous operation of
the snag boat. The controlling depths range from 1 to 40 feet
at mean lower low water.
  The total costs of the existing project to June 30, 1954, have
been $43,336.92 for new work and $1,959,050.13 for maintenance,
a total of $2,002,387.05.
                                            Cost and financial summary
                                                                                                                   I
                                                       Fiscal year ending June 30                                       Total to June
                                                                                                                       30, 1954, includ-
                                                                                                                       ing fiscal years
                                     1950             1951            1952           1953             1954              prior to 1950 1


New work:
                    ------
   Appropriated.......-                                                                                                         $43,337
   Cost-- ---------------                        -    81,--47
                                                            /
                                                                               ----- -..8,0----- -----------.
                                                                             ----
                                                                        5,11---                   - 102-
                                                                                                       - ..-..
                                                                                                          -..8--
                                                                                                              7-                 43,337
Maintenance:
   Appropriated- ....-----          $175,000         $137,247         $50,648        $78,
                                                                                        029          $109,582                2,033, 254
   Cost-- --------------             147, 737         181,147          55,119           029
                                                                                      78,             102874                 2,026, 546


  SIncludes $67,496 for maintenance for previous projects.

                               2. BELLINGHAM                     HARBOR,                WASH.
    Location.             This harbor is a part of Bellingham Bay, an arm of
                RIVERS AND HARBORS-SEATTLE, WASH., DISTRICT                                               1483
Puget Sound, about 18 miles south of the international boundary
and about 100 miles north of Seattle.        (See U. S. Coast and
Geodetic Survey Chart No. 6378.)
   Previous projects. The original project adopted by the River
and Harbor Act of June 13, 1902, contemplated dredging Whatcom
Creek waterway to a depth of 12 feet and 200 feet wide from deep
water to the railroad bridge, a distance of 1200 feet, and to its full
width (363.2 feet) above the bridge, an additional distance of
1,950 feet. For further details see page 2006 of Annual Report
for 1915 and page 1888 of Annual Report for 1938.
   Existing project. This provides for (1) dredging a channel
known as Whatcom Creek waterway from deep water to the head
of the harbor, 363.2 feet wide, 26 feet deep at mean lower low
water for the outer 3,800 feet, and 18 feet deep for the inner
1,300 feet; (2) for Squalicum Creek waterway, including dredging
an entrance channel 200 feet wide and 26 feet deep from deep
water in the bay to the main pierhead line, maintenance of the
southerly half and westerly end of the Squalicum Creek basin to
a depth of 26 feet at mean lower low water, and maintenance of
the breakwater constructed by the port of Bellingham in 1934, to
a crest height of 14 feet, provided that no dredging be done within
75 feet of wharves, piers, or similar structures. The extreme tidal
range is about 16 feet. The range between mean lower low water
and mean higher high water is 8.6 feet.
   The actual cost for new work was $112,013, exclusive of amount
expended on previous project. The latest (1953) approved esti-
mate for annual cost of maintenance is $5,000 for Whatcom Creek
waterway, and $2,500 for Squalicum Creek waterway.
   The existing project was authorized by the following river and
harbor acts:

      Act                           Work authorized                                Documents and reports

June 25, 1910   For the Whatcom Creek Waterway-------------..............-.   H. Doc. 1161, 60th Cong., 2d sess.'
July 3,1930     Entrance channel in Squalicum Creek Waterway.---              H. Doc. 187, 70th Cong., 1st sess.
Aug. 26, 1937   Maintenance of the southerly half and westerly end            Rivers and Harbors Committee
                 of Squalicum Creek Basin and maintenance of the                Doc. 70, 74th Cong., 1st sess.'
                 breakwater constructed by the port commission
                  in 1934.



1Contains latest published    map of Whatcom Creek Waterway.
2   Contains latest published map of Squalicum Creek Waterway.

   Recommended modifications of project. Under date of March
20, 1951, the Chief of Engineers recommended modification of the
existing project to provide for a small-boat basin by removal of
existing breakwater southeasterly of Squalicum Creek waterway
and construction of a new breakwater seaward of the existing
one and in two sections totaling 3,920 feet in length, at an esti-
mated cost to the United States of $1,224,300 with $13,500 an-
nually for maintenance in addition to that now required; subject
to certain conditions of local cooperation (H. Doc. 558, 82d Cong.,
2d sess.)
   Local cooperation. Fully complied with. In addition, the port
of Bellingham, since November 1945, has improved the small-boat
1484           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

basin behind the Squalicum Creek breakwater constructed in
1934, by constructing breakwaters, bulkheads, and floats, and by
dredging at a cost of $507,586. Further improvements, con-
sisting of relocation and extension of the breakwater, are planned.
   Terminal facilities. There are 23 wharves and piers in Belling-
ham Harbor; 8 are located on Whatcom Creek waterway, 4 on
Squalicum Creek waterway, and 11 on Bellingham Bay. Three
wharves on Whatcom Creek waterway serve general cargo termi-
nals. One of these, which is publicly owned and operated, is suit-
able for use by oceangoing vessels; the other two are privately
owned and operated and serve vessels in the Puget Sound trade.
The four wharves on Squalicum Creek waterway are publicly
owned; one oil-handling wharf is publicly operated; the other
three are privately operated. The latter 3 wharves and the other
15 are used for various industrial purposes. These terminal facili-
ties are considered adequate for existing commerce.
   Operations and results during fiscal year. Maintenance dredg-
ing of Whatcom Creek Waterway by contract, commenced June
29, 1953, was completed in July 1953 with 82,857 cubic yards of
material being removed at a cost of $45,968.09. Condition surveys
were made at a cost of $1,929.45. Miscellaneous inspections and
reports were made at a cost of $623.94. Total costs were $48,-
521.48, all for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1931. The dredging of Whatcom Creek Waterway was
completed in 1913. The dredging of the entrance channel in
Squalicum Creek Waterway was completed in 1931 and local in-
terests have since dredged the southerly half and westerly end of
Squalicum Creek basin, and in 1934 constructed a detached rubble
breakwater 1,500 feet long south of the basin. This structure was
raised and extended in 1945 (see "Local cooperation").
   In February 1954 the inner 1,200 feet of Whatcom Creek Water-
way had a controlling depth of 17.4 feet over a width of 150 feet,
except at the head of the waterway, and a depth of 25.2 feet over
a width of 150 feet in the outer 4,400 feet of the waterway. In
June 1952, the Squalicum Creek Waterway entrance channel was
23.1 feet deep over a width of 200 feet, and the basin was 20.3 feet
deep except near the edges and at the head of the waterway.
   The costs under the existing project to June 30, 1954, have been
$112,013.16 for new work and $143,073.41 for maintenance, a
total of $255,086.57.
                                    Cost and financial summary

                                           Fiscal year ending June 30                       Total to June
                                                                                           _30, 1954, includ-
                                                                                           ing fiscal years
                             1950         1951         1952         1953        1954         priorto 1950 1


New work:
   Appropriated                ------ ------------------------     ------                           $168,595
   Cost ...-                                     ---                          --------               168,595
Maintenance:
   Appropriated.---....         $549       -$216        $1 500      $49,000     $ 1, 414             144,165
   Cost                          849          131        1,308        2,085      48,521              144,165


1Includes $56,581.93 for new work and $1,092 for maintenance for previous projects.
        RIVERS AND HARBORS-SEATTLE,       WASH., DISTRICT     1485
                 3. ANACORTES HARBOR,       WASH.
   Location. Anacortes Harbor is on the northern point of Fidalgo
Island in Puget Sound, 17 miles south of Bellingham, Wash., and
64 miles north of Seattle. The main harbor is on Guemes Channel.
 (See U. S. Coast and Geodetic Survey Chart No. 6377.)
   Existing project. This provides for a channel in Cap Sante
Waterway, 12 feet deep at mean lower low water and 150 to 250
feet wide, between the east side of Q Avenue and deep water in
Fidalgo Bay, a distance of 2,850 feet. The tidal range between
mean lower low water and mean higher high water is 8.2 feet. The
extreme range is about 15.5 feet.
   The actual cost for new work was $46,377, exclusive of $23,188
contributed funds. The latest (1953) approved estimate for an-
nual maintenance is $3,000.
   The existing project was adopted by the River and Harbor Act
of March 2, 1919 (H. Doc. 1117, 64th Cong., 1st sess.). This
document contains the latest published map of the locality.
   Recommended modifications of project. Under date of June 26,
1953, the Chief of Engineers recommended modification of the ex-
isting project to provide for a mooring basin 570 feet wide, and
960 feet long, adjacent to the north side of Cap Sante Waterway,
protected by a breakwater, at an estimated cost to the United
States of $150,000 with $3,500 annually for maintenance in addi-
tion to that now required, subject to certain conditions of local
cooperation. (S. Doc. 102, 83d Cong.,. 2d sess.)
   Local cooperation. Fully complied with.
    Terminal facilities. There are 21 terminals in the port of Ana-
cortes, 16 on Guemes Channel, 1 on Cap Sante Waterway, and 4
on Fidalgo Bay. Three terminals on Guemes Channel are open
for public use; of these, 1 is publicly owned and operated and used
for handling general cargo in foreign and domestic trade; and 2,
1 publicly and 1 privately owned and operated, are used by ferries
plying to the San Juan Islands. The terminal on Cap Sante Water-
way is publicly owned and operated and is used for the receipt of
petroleum products, and by small craft in the fishing trade. All of
the other terminals are used for general industrial purposes.
    Operations and results during fiscal year. A condition survey
was made at a cost of $606.06; inspections and reports were made
as required at a cost of $174.67. Total costs were $780.73, all for
maintenance.
    Condition at end of fiscal year. The existing project was com-
pleted in 1930, except that portion of Cap Sante Waterway west of
R Avenue, which was omitted at the request of local interests. A
survey made in February 1954 shows a controlling depth of 7.2
feet in the completed portion of the waterway. The costs from
Federal funds have been $46,376.90 for new work and $7,969.15
for maintenance, a total of $54,346.05. In addition, $23,188.45 has
been expended from contributed funds for new work.
1486                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY. 1954

                                            Cost and financial summary

                                                          Fiscal year ending June 30                            Total to June
                                                      _30,                                                         1954, Includ-
                                                                                                                ing fiscal years
                                     1950             1951               1952      1953            1954          prior to 19501

New work:
   Appropriated --                                                                                                       $------------46,377
   Cost-------------------------------                                                      -                             46,377
Maintenance:
    Appropriated--------------...           ------------------------------------                          781              7,969
    Cost ...--------------------------------------------------                            ----..          781              7,969

Other new work data: Estimated additional amount needed to be appropriated for
completion of existing project-__      --                                     2
1In addition $23,188 for new work was expended from contributed funds.
2 Project completed to extent contemplated; portion of Cap Sante Waterway west of R Avenue has been
omitted at request of local interests.

                                    4. SWINOMISH SLOUGH, WASH.
   Location. This is an inland passage, 11 miles long, between
Saratoga Passage and Padilla Bay, in the northwestern part of the
State of Washington, about 60 miles north of Seattle. (See U. S.
Coast and Geodetic Survey Charts Nos. 6300, 6376, and 6380.)
  Existing project. This provides for a channel 100 feet wide and
12 feet deep at mean lower low water from deep water in Saratoga
Passage to deep water in Padilla Bay, a distance of 11 miles, by
dredging and dike construction where necessary. The extreme
tidal range is about 19 feet at the south end of the slough and about
16 feet at the north end. The range between mean lower low
water and mean higher high water is 11.5 feet at the south end of
the slough, 8.5 feet at the north end, and 6.5 feet at La Conner.
   The actual cost for new work was $409,030. The latest (1953)
approved estimate for annual cost of maintenance is $100,000.
   The existing project was authorized by the following river and
harbor acts:

      Act                                Work authorized                                     Documents and reports
July 13,1892           Channel 4 feet deep and 100 feet wide, and dike con-           H. Doc. 31, 52d Cong., 1st sess.,
                        struction.                                                      and annual report, 1892, p. 2752.
Aug. 30, 1935          Enlargement of the channel to present project di-              Senate committee print, 73d Cong.,
                        mensions.                                                       1st sess.

   1 For latest published map, see H. Doc. 860, 63d Cong., 2d sess.

   Local cooperation. Under the provisions of the River and Har-
bor Act of August 30, 1935, adopting the project for the 12-foot
channel, local interests were required to furnish free of cost to the
United States suitable areas for the disposal of dredged material
during initial construction and for future maintenance as and when
needed. Compliance with these conditions has not yet been re-
quired, as suitable areas for disposal of dredged material have been
found without invoking the requirements of local cooperation.
   Terminal facilities. There are nine wharves on Swinomish
slough, all of which are privately owned and operated for industrial
purposes and not open for general public use. These facilities are
considered adequate for existing commerce.
   Operationsand results during fiscal year. Maintenance dredg-
              RIVERS AND HARBORS-SEATTLE, WASH., DISTRICT                                               1487
ing commenced June 15, 1953, was completed July 15, 1953, and
114,601 cubic yards of material were removed from the channel
during the fiscal year at a cost of $53,105.71. Another mainte-
nance dredging contract was awarded June 29, 1954, with pre-
liminary costs of $720.11. Condition surveys and miscellaneous
inspections and reports were made at costs of $5,737.63 and
$559.03, respectively.   Total costs during the fiscal year were
$60,122.48, all for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1937. The dikes are in good condition except for one
timber dike. In April 1954 the controlling depth in the channel
was 6.2 feet at mean lower low water. The costs to June 30, 1954,
have been $409,029.51 for new work and $897,079.55 for main-
tenance, a total of $1,306,109.06.
                                      Cost and financial summary

                                                 Fiscal year ending June 30                      Total to June
                                                                                                30, 1954, includ-
                                                                                                ing fiscal years
                               1950          1951         1952         1953          1954         priorto 1950


New work:
   Appropriated        ...                                             ------        -------             409,030
   Cost              -----------         -----------         -        --------    ---------              409,030
Maintenance:                                                                                             4
   Appropriated   .          $101,450         $2,463       $3,120     $105,300      $107, 600          1,000,812
   Cost----------------        102,387         2, 535       3,120       49, 045       60,122             897, 080



                                      5. NEAH BAY, WASH.
  Location. On the south side of the Strait of Juan de Fuca, 5
miles east of Cape Flattery, at the entrance to the strait from the
Pacific Ocean, and about 60 miles west of Port Angeles, Wash.
(See U. S. Coast and Geodetic Survey Charts Nos. 6102, 6265, and
6266.)
   Existing project. This provides for a rubblestone breakwater
approximately 8,000 feet long between Waadah Island and the
westerly shore of the bay. The tidal range between mean lower
low water and mean higher high water is 8.2 feet. The extreme
range is 15.5 feet.
   The actual cost for new work was $1,934,483. The latest (1953)
approved estimate of cost for annual maintenance is $35,000.
   The existing project was adopted by the River and Harbor Act
of June 20, 1938 (Rivers and Harbors Committee Doc. 51, 75th
Cong., 2d sess.). This document contains the latest published map.
   Recommended modifications of project. Under date of June 26,
1953, the Chief of Engineers recommended modification of the ex-
isting project to provide for reinforcement of the existing rock
revetment extending 1,800 feet west from Baada Point and an im-
mediate 200-foot extension of the revetment westward, then suc-
cessive 200-foot extensions at intervals of 2 years, or as needed,
for a total of 1,200 feet, at an estimated cost of $118,650, consisting
of $40,000 for initial work and $15,730 for each of five successive
extensions with $2,000 annually for maintenance in addition to
that now required; subject to certain requirements of local co-
operation. (H. Doc. 404, 83d Cong., 2d sess.)
  Local cooperation. Fully complied with.
1488           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Terminal facilities. There are 6 wharves at Neah Bay, includ-
ing 2 owned by the United States which are used by the Coast
Guard, and 4 privately owned wharves, 3 of which are open to
general public use to accommodate small commercial fishing ves-
sels. In addition to the wharves, there is a facility for dumping
and rafting logs. These facilities are considered adequate for
existing commerce.
   Operations and results during fiscal year. Miscellaneous in-
spections and reports were made at a cost of $305.53, all for
maintenance.
   Condition at end of fiscal year. The project was completed in
February 1944. In April 1954, the breakwater showed consider-
able loss of rock from the inner half of the crest. The costs to
June 30, 1954, have been $1,934,482.70 for new work and $174,-
883.15 for maintenance, a total of $2,109,365.85.
                                      Cost and financial summary

                                            Fiscal year ending June 30             Total to June
                                                                                   30, 1954, includ-
                                                                                   ing fiscal years
                               1950        1951           1952     1953   1954       priorto 1950

New work:
   Appropriated                                                                         $1, 934,483
   Cost     -      ....-                                                  -$             1,934, 483
Maintenance:
   Appropriated                           -$1, 440    .   . I               $306            174, 883
   Cost --------------   ---   $2,050         1,077                          306            174,883



                               6. LAKE CROCKETT, WASH.
   Location. The harbor 'islocated on the west side of Whidbey
Island, about 35 nautical miles north of Seattle, Wash. The lake
lies parallel to Admiralty Bay and is separated from it by a narrow
strip of gravel beach. (See U. S. Coast and Geodetic Survey Chart
No. 6450.)
   Existing project. This provides for a basin in Lake Crockett
with an area of about 6 acres and a depth of 18 feet at mean lower
low water, connected with Admiralty Bay by a channel of the
same depth and 150 feet wide protected by a breakwater. The
diurnal tidal range in Admiralty Bay is 8.8 feet and the extreme
range is about 16.5 feet.
   The actual cost for new work was $260,240.
   The latest (1953) estimate of cost for annual maintenance is
$20,000.
   The existing project was adopted by the River and Harbor Act
of March 2, 1945. (See H. Doc. 303, 77th Cong., 1st sess., which
contains the latest published map.)
   Local cooperation. None required.
   Terminal facilities. There is one publicly owned and privately
operated passenger and automobile ferry landing within the
dredged basin which is open for public use. The United States
Army has a wharf just outside of the basin. The public terminal
is adequate for existing commercial traffic.
  Operations and results during fiscal year. A condition survey
was made at a cost of $626.83. The shore end of the breakwater
            RIVERS AND HARBORS--SEATTLE, WASH., DISTRICT                                                              1489
was repaired in February 1954 by placing 700 tons of rock
under contract at a cost of $4,689.73. Miscellaneous inspections
and reports were made at a cost of $178.33. Total costs were
$5,494.89, all for maintenance.
   Condition at end of fiscal year. The project was completed in
January 1948. A survey made in September 1953 showed con-
siderable shoaling in the entrance channel. The breakwater was
in good condition following completion of repairs in February
1954.
   The costs to June 30, 1954, have been $260,239.67 for new work
and $26,829.29 for maintenance, a total of $287,068.96.
                                       Cost and financial summary

                                                   Fiscal year ending June 30                                  Total to June
                                                                                                              30, 1954, includ-
                                                                                                              ing fiscal years
                              1950               1951               1952                  1953      1954       prior to 1950

New work:
   Appropriated.   .....------------   ------------------------------------------------                               $260,240
   Cost-------------------- ------------------------------------------------                                           260,240
Maintenance:
   Appropriated               $ 1,200 ------------------------                            $1, 000   $4, 596             26,829
   Cost-_                      20,478 ------------------------                                101    5,495              26,829



     7. WATERWAY               CONNECTING PORT TOWNSEND BAY AND
                                   OAK BAY, WASH.
   Location. The canal connects two bays which are arms of Ad-
miralty Inlet onthe west side of Puget Sound, in the northwestern
part of the State of Washington, about 40 miles north of Seattle.
 (See U. S. Coast and Geodetic Survey Chart No. 6405.)
   Existing project. This provides for a canal 15 feet deep at
mean lower low water, 75 feet wide on the bottom and about 4,800
feet long, and for the construction of jetties to protect the chan-
nel at the southern or Oak Bay end, and a bulkhead for the re-
tention of dredged material. The extreme tidal range is 16 feet.
The range between mean lower low water and mean higher high
water is 8.3 feet in Port Townsend Bay and 9.4 feet in Oak Bay.
   The actual cost for new work was $73,322. The latest (1953)
approved estimate for annual cost of maintenance is $5,000.
   The existing project was adopted by the River and Harbor Act
of March 4, 1913 (H. Doc. 625, 62d Cong., 2d sess.). The latest
published map is in the Annual Report for 1915, page 3441.
   Local cooperation. Fully complied with.
   Terminal facilities. There are no terminal facilities directly
served by the canal.
   Operations and results during fiscal year. A condition survey
was made at a cost of $802.57, and the cost of inspections and re-
ports was $189.87, a total of $992.44, all for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1915. A controlling depth of 14.1 feet obtained in the
project channel in January 1954 and the bulkhead and jetties
were in good condition. The costs under the existing project have
been $73,322.35 for new work and $66,768.34 for maintenance, a
total of $140,090.69.
1490             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                             Cost and financial summary

                                                        Fiscal year ending June 30                                   Total to June
                                                                                                                     30,1954, includ-
                                                                                                                     ing fiscal years
                                      1950            1951             1952             1953            1954           priorto 1950


New work:
   Appropriated-------........    ---------------------........................ ----------- ----------- -----------          $73, 322
   Cost----....----------------                          ......------------.......------------------------------------...     73, 322
Maintenance:
   Appropriated             ------------------
                         .----------                     - -----------.                                     $992              66,768
   Cost------------- ----------------------- -----------      ---------                                      992              66,768


                                     8. EVERETT HARBOR, WASH.
   Location. On Port Gardner Bay, at the northern end of Pos-
session Sound, an arm of Puget Sound, 30 miles north of Seattle
and 45 miles south of Bellingham. (See U. S. Coast and Geodetic
Survey Chart No. 6448.)
   Previous projects. The original project adopted by the River
and Harbor Act of August 18, 1894, provided for a basin in front
of the Everett Peninsula, for a channel from the end of the basin
around the peninsula to the head of Old River, and for a dike from
the lower end of Smith Island to the south end of the basin. By
authority of joint resolution of Congress approved April 23, 1902,
the work in Old River was discontinued. The project was further
modified by the River and Harbor Act of March 3, 1905, to pro-
vide for survey of Everett Harbor with a view to the extension of
the dike and of the dredged area. For further details, see page
704 of Annual Report of 1905, page 2005 of Annual Report for
1915, and page 1883 of Annual Report for 1938.
   Existing project. This provides for a training dike in the up-
per harbor extending from Smith Island to a point opposite 23d
Street, with a gap of suitable width at the outlet of Snohomish
River channel and spur dikes to regulate the flow through the
gap; for a channel shoreward of the training dike, between the
outlet of the main river channel and deep water in the lower har-
bor, 100 feet wide and 8 feet deep at mean lower low water; for
a settling basin with a capacity of about 200,000 cubic yards,
1,200 feet long, 700 feet wide, and 12 feet deep at mean lower low
water, in the upper harbor in the vicinity of the 14th Street dock;
and for a channel throughout that portion of the lower harbor
known as East Waterway, 30 feet deep at mean lower low water
and generally 900 feet wide.
   The length of channel improvement under this project is 2.5
miles. The extreme tidal range is about 19 feet. The range be-
tween mean lower low water and mean higher high water is 11.1
feet.
   The actual cost for new work was $325,968, exclusive of
amounts expended under previous projects. The latest (1953)
approved estimate of annual cost of maintenance of the entire
project is $35,000.
   The existing project was authorized by the following River and
Harbor Acts:
                 RIVERS AND HARBORS-SEATTLE, WASH., DISTRICT                                           1491

       Act                         Work authorized                              Documents and reports

June 25,1910      Training dike 10,500 feet long extending across the      H. Doc. 1108, 60th Cong., 2d sess.
                   bar at the outlet of Old River Channel.
July    3,1930   Raising 6,000 feet of the training dike, extending spur   H. Doc. 377, 71st Cong., 2d sess.
                  dike, widening gap in dike as required, maintain-
                  ing East Waterway and the channel to the gap.
June 20, 1938    Abandoned the project for Snohomish River, and            H. Doc. 546, 75th Cong., 3d sess.
                  provided for the settling basin.                          (Contains latest published map.)


   Recommended modifications of project. Under date of March
8, 1950, the Chief of Engineers recommended modification of the
existing project to provide for realining and enlarging to a depth
of 15 feet and widths of 150 to 425 feet that portion of the exist-
ing channel extending from deep water in Port Gardner Bay to
the settling basin opposite 14th Street, deepening the existing
settling basin to 20 feet, constructing a spur dike extending west-
ward from Preston Point a distance of 1,410 feet, and removing
the section of the existing training dike north of the gap; all at
an estimated cost to the United States of $325,970, with $10,000
annually for maintenance in addition to that now required; sub-
ject to certain conditions of local cooperation (H. Doc. 569, 81st
Cong., 2d sess.).
   Local cooperation. None required.
   Terminal facilities. There are 24 wharves and piers on Everett
Harbor and Snohomish River-12 are located on Port Gardner
Bay, 5 on the channel to the gap, and 7 on Snohomish River.
Seven wharves are suitable for use by oceangoing vessels; all of
these are located on Port Gardner 'Bay and East Waterway chan-
nel and one serves a publicly owned and operated general cargo
terminal that is open for public use. The remaining wharves are
used by barges and light-draft vessels and serve various indus-
trial purposes. These facilities are considered adequate for exist-
ing commerce.
   Operations and results during fiscal year. A condition survey
was made at a cost of $2,655.27. Miscellaneous inspections and
reports were made at a cost of $1,214.70. Total costs were
$3,869.97, all for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1940. Dike work was commenced in September 1911
and terminated in September 1912, and 6,000 feet of dike were
raised to an elevation of 14 feet above mean lower low water in
1931. The channel between the river outlet and the lower habor
was dredged to 8 feet in 1931 and the settling basin was com-
pleted in 1940. Dredging of East Waterway has been completed
by local interests.
   Controlling depths in January 1954 were 8.1 feet in in the
channel from the lower harbor to the settling basin, 8.4 feet in
the settling basin, 8.0 feet from the settling basin upstream for
4,200 feet, and thence 3.9 feet to the gap in the dike. Controlling
depth in East Waterway in January 1954 was 26.9 feet. The
dike was in good condition except for the southerly end.
   The costs under the existing project to June 30, 1954, have been
1492             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

$325,968.16 for new work and $352,243.31 for maintenance, a
total of $678,211.47.
                                           Cost and financial summary

                                                     Fiscal year ending June 30                         Total to June
                                                                                                       30,1954, includ-
                                                                                                       ing fiscal years
                                    1950           1951         1952               1953      1954        priorto 19501

New work:
   Appropriated--------------------------------------                                                         $744,177
   Cost----...                             ------------                   ------------                         744,177
Maintenance:
    Appropriated ..                               -- $1,001     $2, 500           $76, 472   $3, 800           358,150
     Cost-----------------           $1,355          1,828       2,177              76,686    3,870            358,112

  1Includes $418,209 for new work and $5,868 for maintenance for previous projects.

             9. CHIEF JOSEPH DAM, COLUMBIA RIVER, WASH.
   Location. The Columbia River rises in Columbia Lake, British
Columbia, at elevation 2,650, flows northwesterly for nearly 200
miles, then southerly through Upper and Lower Arrow Lakes to
enter the United States near the northeast corner of the State of
Washington. From the international boundary the river flows
south 112 miles to a point below the mouth of the Spokane River,
then west 100 miles to the mouth of the Okanogan River, passing
Grand Coulee Dam and the Chief Joseph Dam site en route.
Swinging south, the river follows the eastern foothills of the
Cascade Mountains for 209 miles to its confluence with Snake
River. A few miles below the Snake, it turns sharply westward
and flows for 324 miles, forming the Washington-Oregon bound-
ary, to the Pacific Ocean. The works covered by this project
are on the Columbia River just upstream from the mouth of
Foster Creek, 11/2 miles upstream from the town of Bridgeport,
Wash., and 51 miles downstream from Grand Coulee Dam. (U. S.
Geological Survey topographic sheet "Okanogan, Wash.," shows
the general locality.)
   Existing project. The project provides for a straight concrete
gravity overflow dam on the Columbia River, 220 feet high, for a
powerhouse, and an intake of sufficient capacity to utilize future
upstream storage. The powerhouse will have 16 units installed
initially and a substructure for 4 additional units. The ultimate
installed capacity will be dependent upon the rate and amount of
future development of upstream storage. Present plans provide
for future expansion to a maximum development of 27 units. All
units are to be 64,000 kilowatts capacity.
   The estimate of cost for new work (1954) is $169,000,000 (16
units). The latest (1953) approved estimate for annual cost of
operation and maintenance ranges from $940,000 for the first 4
units to $1,853,000 for 16 units.
   The existing project was authorized by the River and Harbor
Act of July 24, 1946.     (.See H. Doc. 693, 79th Cong., 2d sess.,
which contains the latest published map.)
  Local cooperation. None required.
   Operations and results during fiscal year. Hired labor opera-
tions were carried on as follows: Acquisition of reservoir lands was
         RIVERS AND HARBORS-SEATTLE, WASH., DISTRICT           1493
in progress. Engineering and design were completed for the fol-
lowing items: Main generators (two units), station service trans-
former, 230-kilovolt equipment, machine shop equipment, wire and
control cable (second group), and installation of powerhouse equip-
ment. Preparation of construction drawings to supplement con-
tract drawings for construction of the powerhouse and intake
structure and installation of powerhouse equipment was continued.
Engineering and design for powerhouse equipment items not yet
advertised was also continued.
   Procurement contracts substantially completed during the fiscal
year include sluice gates, 19 tainter gates, tainter gate operating
machinery, two 165-ton bridge cranes, 50-ton intake gantry crane,
18-ton draft tube gantry crane, draft tube stop-logs, 4160-volt
switchgear, station service substation, station service control
switchboards, 480-volt motor control centers, wire and cable (first
contract), intake gates and latch assemblies, and intake gate oper-
ating machinery.
   Procurement contracts under way but not completed during the
fiscal year include 100,000-horsepower turbines (16 units), 64,000-
kilowatt generators (8 units), main unit governors (10 units),
103,300-kilovolt-ampere transformers (12 units), 3500-horsepower
station service turbines and governors (2 units), 3,000-kilovolt-
ampere station service generators (2 units), 3,000-kilovolt-ampere
station service transformer, machine shop equipment, intake trash
racks, wire and cable (second group), main control boards and
appurtenant equipment (8 units), main unit substation (12 units),
15-kilovolt breakers and grounding equipment (12 units), 15-kilo-
volt bus (12 units), batteries, 480-volt intake structure substation,
station service grounding equipment, and main dam switchgear.
Of these contracts, the following were awarded during the fiscal
year: 3,000-kilovolt-ampere station service transformer, machine
shop equipment, intake trash racks, draft tube stop-logs, station
batteries, 480-volt motor control centers, station service grounding
equipment, and main dam switchgear.
   Work was under way on the following construction contracts:
Second-stage construction (main dam) contract was continued,
including placing right-bank abutment fill, left-bank fill, placing
concrete in main dam monoliths, and partial installation of tainter
gates and hoisting machinery. Construction of powerhouse and
intake structure was continued, including placing concrete in in-
take monoliths, service deck piers and slabs, station service and
assembly bays, generator bays, including embedded turbine parts,
and penstock erection and encasement. Contract for installation
of powerhouse equipment and completion of powerhouse and ap-
purtenances was awarded, and work accomplished includes com-
pletion of installation of intake and draft tube gantry cranes; par-
tial installation of turbine rotating parts, station service switch-
boards and switchgear, cable tray supports, conduit and piping;
receiving and storing of generator parts and other items of elec-
trical equipment for installation. Contracts were awarded for in-
stallation of piezometers in the right abutment and for adjustment
of the water supply system at Elmer City. Contract for reservoir
clearing was awarded and work was completed.
   Costs for the fiscal year were $32,092,598.24, all for new work.
1494     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Condition at end of fiscal year. The existing project is about 48
percent complete. Engineering and design (including construction
drawings) are about 85 percent complete. Construction contracts
completed include construction of first cofferdam, right bank
blanket and foundation excavation, commenced in July 1950 and
completed in August 1951; excavation of intake canal and reloca-
tion of State Highway 10B, completed in June 1951; access high-
way, completed in October 1950; Okanogan River bridge on the
access highway, completed in November 1950; Columbia River
bridge, completed in August 1951; housing, administration, and
maintenance facilities, completed in September 1950; and lawn
seeding and landscaping of housing and administration areas, com-
pleted in July 1951.
   Construction of the main dam and excavation for the power-
house and intake structure, commenced in February 1951, is 95
percent complete. Construction of powerhouse and intake struc-
ture, commenced in April 1952, is 77 percent complete. Installa-
tion of powerhouse equipment, started in October 1953, is 13 per-
cent complete. Reservoir clearing has been completed. Right-
bank piezometer installation is 98 percent complete. Relocation of
the Elmer City water system is 5 percent complete. Acquisition
of project lands is 53 percent complete.
   Procurement contracts completed include sluice gates, 19 tainter
gates, tainter gate operating machinery, two 165-ton bridge cranes,
50-ton intake gantry crane, 18-ton draft tube gantry crane, draft
tube stop-logs, 4,160-volt switchgear, station service substation,
station service control switchboards, 480-volt motor control cen-
ters, wire and cable (first group), intake gates and latch assem-
blies, intake gate operating machinery, truck cranes, and copper
bus bar and shapes. Work is continuing on procurement contracts
in force but not completed.
   The work remaining to be done to complete the project consists
of completion of engineering and design of powerhouse equipment
to be procured under supply contracts; completion of engineering
and design for miscellaneous minor features; completion of con-
struction drawings for powerhouse and intake structure and for
installation of powerhouse equipment; awarding supply contracts
for equipment and materials for the project; completion of con-
struction features now in progress; completion of installation of
powerhouse equipment and miscellaneous minor features; and
completion of land acquisition.
   The total costs to June 30, 1954, have been $88,119,291.03, all for
new work.
                  RIVERS AND HARBORS--SEATTLE, WASH., DISTRICT                                                1495
                                        Cost and financial summary


                                                Fiscal year ending June 30                            Total to June
                                                                                                      30, 1954, includ-
                                                                                                      ing fiscal years
                                 1950         1951          1952           1953          1954          prior to 1950

New work:
   Appropriated. -..          $5, 000, 000 $18, 529,000 $16,892, 000 $14, 903,000    1$29,750,000         $88,245, 760
   Cost ---------------        3,187, 697   12, 550, 090 15,008,561 224,600,174        32, 092, 598        88, 119, 291


Other new work data:
    Appropriated for succeeding fiscal year ending June 30, 1955-____.  $20,600,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955---_______----   .------.- ____     ___
                                                         -     .__       20,600,000
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project.-_ .  ---...----- __ -----       ____--- 60,154,240
1 Includes $6,400,000 of funds borrowed to meet fiscal year 1954 obligations.
2 Erroneously reported in fiscal year 1953 Annual Report as $24,591,317.53.




                              10. QUILLAYUTE RIVER, WASH.
   Location. This river is formed by the junction of the Soleduck
and Bogachiel Rivers, and flows westerly 5 miles to the Pacific
Ocean at La Push, Wash., about 30 miles south of Cape Flattery.
 (See U. S. Coast and Geodetic Survey Chart No. 6102.)
   Existing project. This provides for a jetty on the easterly side
of the mouth, and a dike, with groins, on the westerly side, with a
view of stabilizing the entrance, and for maintenance dredging to
afford a channel 6 feet deep and of suitable width from the ocean
to within the river mouth. The length of the section included in
the project is 1,500 feet. The range between mean lower low water
and mean higher high water at La Push is 8.3 feet. The extreme
range is about 15 feet.
   The actual cost for new work was $68,000. The latest (1953)
approved estimate for annual cost of maintenance is $13,000.
   The existing project was authorized by the following River and
Harbor Acts:

       Act                          Work authorized                                 Documents and reports

July    3, 1930   Jetty on easterly side of mouth, and a dike, with          H. Doc. 125, 71st Cong., 1st sess.
                    groins, on the westerly side, to stabilize entrance.
Mar. 2,1945       Maintenance dredging to provide a channel 6 feet           H. Doc. 218, 78th Cong., 1st sess.
                    deep and of suitable width from ocean to within           (Contains latest published map.)
                    river mouth.
1496           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Recommended modifications of project. Under date of March 8,
1950, the Chief of Engineers recommended modification of the
existing project to provide a channel 10 feet deep and 100 feet wide
extending 2,000 feet upstream from deep water; a basin 10 feet
deep, 300 to 425 feet wide, and 2,400 feet long at the upper end of
the channel; and raising the easterly jetty to a height of 15 feet
above mean lower low water, all at an estimated cost to the United
States of $375,000 for construction and annual maintenance of
$65,750 in addition to that now required; subject to certain con-
ditions of local cooperation, including a cash contribution of $20,000
toward the cost of the improvement (H. Doc. 579, 81st Cong., 2d
sess.).
   Local cooperation. Fully complied with, including agreement
to repair any breach in the sand spit north of James Island. In
1953 the Port of Port Angeles expended $1,680 for protective work
on the spit.
   A channel 6 feet deep, 50 feet wide, and about 2,500 feet long,
extending upstream from the Coast Guard ways, was dredged in
1948 and 1949 with Coast Guard funds.
   Terminal facilities. There are four terminals at La Push; of
these, three privately owned are open to public use to accommodate
small commercial fishing vessels, and one owned by the United
States is used as a Coast Guard station. These facilities are con-
sidered adequate for existing commerce.
   Operations and results during fiscal year. Dike repairs were
completed in October 1953 by placing 4,092 cubic yards of rock
under contract at a cost of $18,030.52. A condition survey was
made in April 1954 at a cost of $1,683.92. The cost of miscellaneous
inspections and reports was $695.24. Total costs were $20,409.68,
all for maintenance.
   Condition at end of fiscal year. The existing project was sub-
stantially completed in 1931, omitting the groins, which do not
appear necessary or desirable. In April 1954 the dike, which had
been repaired in October 1953, showed a maximum subsidence of
2 feet, and the jetty showed considerable deterioration. The con-
trolling depth in the entrance channel was 5 feet over a width of 80
feet.
   The costs to June 30, 1954, have been $68,000 for new work and
$161,731.72 for maintenance, a total of $229,731.72.
                                     Cost and ,financial summary

                                            Fiscal year ending June 30                         Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                              1950         1951         1952          1953          1954        prior to 1950


New work:
   Appropriated       ...------------     --- ------      -       ------ ------------                 $ 68,000
   Cost                 - ------------ ------------ ------------ ------------                           68,000
Maintenance:
   Appropriated ... _.        $15,000    -$30, 554       $1,091       $52,000     -$29, 166            161, 732
   Cost -      .-------------- 35,373            1        1,091         2,424        20,410            161,732


Other new work data: Estimated additional amount needed to be appropriated for
  completion of existing project
1Project completed   to extent contemplated.
                        RIVERS AND HARBORS-SEATTLE, WASH., DISTRICT                                                                                   1497
                           11. LAKE WASHINGTON SHIP CANAL, WASH.
   Location. This improvement lies entirely within the city of
Seattle and extends from Puget Sound through Shilshole Bay, Sal-
mon Bay, Lake Union, Portage Bay, and Union Bay to deep water
in Lake Washington. (See U. S. Coast and Geodetic Survey Chart
No. 6447.)
   Previous projects. The original project adopted by the River
and Harbor Act of August 18, 1894, provided for dredging Salmon
Bay and the improvement of the waterway connecting the waters
of Puget Sound, at Salmon Bay, with Lakes Union and Washington,
by enlarging the said waterway into a ship canal, with necessary
locks and appliances. The project as modified by the River and
Harbor Act of June 13, 1902, provided for dredging a low-water
channel 10 feet in depth from Shilshole Bay through Salmon Bay
to the wharves at Ballard; and for the appointment of a board of
engineers to make investigations for constructing a canal, over
alternate routes, with necessary locks and dams.
   For further details see page 2003, Annual Report for 1915, and
page 1880, Annual Report for 1938.
   Existing project. This provides for a double lock and fixed dam
with movable crest and necessary accessory works at the Narrows
at the entrance to Salmon Bay, approximately 11/4 miles from
deep water in Puget Sound; for a channel 34 feet deep at mean
lower low water and 300 feet wide from Puget Sound to the Great
Northern Railway bridge, about 5,500 feet, with a passing basin
34 feet deep and log basin 8 feet deep at the turn below the railway
bridge; thence 34 feet deep and 150 to 200 feet wide to the locks,
about 900 feet; and a guide pier 600 feet long; for the revetment
of the canal banks between the locks and Lake Union and between
Lakes Union and Washington; and for a channel 30 feet deep with
a width of 100 feet from the locks to Lake Union, 200 feet thence
to Portage Cut, 100 feet through Portage Cut, and thence 200 feet
wide through Union Bay to Lake Washington.
  The following table shows the principal features of the double
lock and dam. (The structures are located at Seattle, Wash.)

                                                                                                                                Large lock        Small lock

Miles above mouth------.......---------------------------------------------1..........                                                   1                  1
Clear width of chamber ...........                          ....... .......---------------------...
                                               ....-------------                       feet..                                             80                 30
Maximum available length....--                --------------------------....
                                                                     ..........        do...                                             760                123
Lift.........-------------.. ............       ...    ........-----
                                          -----------------------------.........                                       do                 26                 26
Depth on upper miter sill 1...__---.....__                                                                                                36                 16
Depth on intermediate miter sill 2 ...........                ..... __---------.....                                   do_..              29 ..
Depth on lower miter sill ..-------..............                   ---...................                             do..               29                 16
Character of foundation...--------------.........................---------------------..............---------                      (3)               (3)
Kind of dam----......................------------------............-----------------------------
                                                                                    .......                                        (4)               (4)
Type of construction .....--..----.....----------------................-----------------.......----                                (5)               (5)
Year completed-----------.....---------------------------------------------                                                              1916              1916
Cost......................................------------------------..----------------------------------.......................      (6)               (6)
  1
      Low water in upper pool.
  2 Mean lower low water in Puget Sound.
  s Clay.
  4 Fixed dam with movable crest.
  6 Concrete.
  6 The cost of double lock and dam was $2,224,712 and the emergency gates, completed in 1923, $174,698.31.
1498             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  The length of section included in this project is about 8 miles.
The extreme tidal range is 19.3 feet. The range between mean
lower low water and mean higher high water is 11.3 feet, and be-
tween mean lower low water and extreme low water is 4.5 feet.
The ordinary fluctuation in the upper pool is approximately 16
inches and the extreme fluctuation is 2 feet.
  The actual cost for new work was $3,539,295, exclusive of
amounts expended on previous projects. The latest (1953) ap-
proved estimate of annual cost of maintenance is $385,000, of
which $345,000 is for operating and care of locks and dam.
  The existing project was authorized by the following River and
Harbor Acts:

       Act                        Work authorized                             Documents and reports

                 (For a double lock and fixed dam with movable crest
                 I and necessary accessory works at the entrance to
June 25, 1910       Salmon Bay; dredging a channel from the locks to     H. Doc. 953, 60th Cong., 1st sess.
Mar. 4, 1913        deep water in Puget Sound, and excavation by
                   Lake Washington.
Aug.    8,1917   Dredging below the locks and revetting canal banks_..   H. Doc. 800, 64th Cong., 1st sess.
Sept. 22,1922   Increased dimensions of the channel between Puget        H. Doc. 324, 67th Cong., 2d sess.
                   Sound and the locks and a 600-foot extension of the
                  lower guide pier.
June 26, 1934 1 Operating and care of the locks and dam provided
                  for with funds from War Department appropria-
                  tions for rivers and harbors.                                                               s
Aug. 30, 1935 2 Enlargement of the channel between the locks and         H. Doc. 140, 72d Cong., 1st sess.
                   Lake Washington.

  1Permanent Appropriations Repeal Act.
  3Included in the Public Works Administration program, Sept. 6, 1933.
  s Contains the latest published maps.

   Local cooperation. Fully complied with.
   Terminal facilities. There are 112 wharves, piers, and land-
ings on Lake Washington Ship Canal and adjacent inland waters,
including Shilshole Bay, Salmon Bay, Lake Union, Portage Bay,
and Lake Washington. Fifteen wharves are used for moorage and
servicing of commercial fishing vessels; of these, four are publicly
owned. Other publicly operated wharves include 6 used by agen-
cies of the United States Government, and 3 by the city of Seattle.
The other wharves include 15 used for the building, outfitting, or
repair of vessels, 16 for handling petroleum products, 28 for various
industrial purposes, 27 for mooring and servicing pleasure craft,
and 2 are not in use. These facilities are considered adequate for
existing commerce.
   Operations and results during fiscal year. The locks were op-
erated and maintained throughout the year. Reconstruction of
the greenhouse, repairs to the emergency dam wharf, filling of the
northwest corner of the reservation, installation of a lawn sprinkler
system, overhaul of two spillway gates, replacement of the locks
scow, and other minor improvements were completed. Bids were
opened for repair of the southwest section of the Montlake revet-
ments, correction of the slide area at the west boundary of the lock
site, overhaul of the pumping plant, and overhaul of miters and
sills on the large lock service gates. The costs were $358,182.79,
all for operation and care.
                 RIVERS AND HARBORS-SEATTLE, WASH., DISTRICT                                                  1499
   Condition at end of fiscal year. The existing project was com-
pleted in 1934. The water between the locks and Lake Washington
is nontidal and is maintained between elevations 20 feet and 22 feet
above mean lower low water in Puget Sound. The controlling
depths in midchannel when last ascertained were as follows: From
Puget Sound to the locks, 28.2 feet in October 1953; the locks to
Lake Union, 29.7 feet in October 1953; Lake Union to Lake Wash-
ington, 29.2 feet in November 1953.
   The costs under the existing project to June 30, 1954, have been
$3,539,294.87 for new work, including $192,516.44 Public Works
funds, $108,379.38 for maintenance, and $4,571,027.35 for opera-
tion and care, a total of $8,218,701.60.
   In addition, the sum of $1,631,195.33 was expended between
1916 and 1936 on the operation and care of the works of improve-
ment, under the provisions of the permanent indefinite appropria-
tion for such purposes.
   In addition there was expended by the State of Washington
$246,567.07, and by King County, $742,070.51 in the excavation of
the channel above the locks and in construction of concrete revet-
ment at the portage.
                                           Cost and financial summary

                                                     Fiscal year ending June 30                       Total to June
                                                                                                      30, 1954, includ-
                                                                                                      ing fiscal years
                                    1950           1951            1952        1953        1954        prior to 1950 1

New work:
   Appropriated---......----..------- ----------------------                     --... ...... $4,024,297
                                                                              --.-.
   Cost---.--_--      .           ...-------------...........-..----                                         4,024,297
Maintenance:
   Appropriated -              $500,000        $268, 500           $328,817   $371, 500   $467, 800          6,461,820
     Cost----------------           442,335        341,324        392 089      335,208     358,183           6,310,602

  1 Includes $485,002 for new work for previous projects.


                                   12. SEATTLE HARBOR, WASH.
   Location. This harbor includes all waterways within the city
limits of Seattle. The chief anchorage basin is Elliott Bay, an arm
of Puget Sound, 30 miles north of Tacoma. (See U. S. Coast and
Geodetic Survey Chart No. 6449.)
   Existing project. This provides for maintenance of the east
and west waterways to a depth of 34 feet at mean lower low water,
with a width of 750 feet for distances of 6,500 and 5,200 feet, re-
spectively, from the pierhead line in Elliott Bay; for the mainte-
nance of east waterway between the upper end of the 750-foot
section and Spokane Street, 34 feet deep, 700 feet long, and 400 feet
wide, and of a turning basin, including the head of the east water-
way at the junction of the waterways south of the Chicago, Mil-
waukee, St. Paul & Pacific Railroad bridge, to a depth of 30 feet,
after these sections of the waterway have been dredged by local
interests to full project dimensions; and for dredging the Duwam-
ish Waterway 200 feet wide and 30 feet deep at mean lower low
water between the west waterway and 1st Avenue South, 150 by
20 feet between 1st and 8th Avenues South, thence 150 by 15 feet
to a point about 1.4 miles above 14th Avenue South Bridge, with a
 1500             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

turning basin 600 by 350 feet and 20 feet deep just south of the 1st
Avenue South Bridge, and a turning basin 500 by 250 feet and 15
feet deep and settling basin with a capacity of about 100,000 cubic
yards at the upper end of the waterway, a distance of 27,060 feet,
or 5.12 miles.
  The total length of waterways included under the project is
about 71/2 miles. The range between mean lower low water and
mean higher high water is 11.3 feet. The extreme tidal range is
19.3 feet.
  The estimate of cost for new work (1954) is $193,000 exclusive
of $97,833 to be contributed by local interests. The latest (1953)
approved estimates for annual cost of maintenance are $4,750 for
the east waterway, $6,000 for the west waterway, and $48,000
for the Duwamish Waterway.
  The existing project was authorized by the following River and
Harbor Acts:
       Act                         Work authorized                             Documents and reports

Mar.    2, 1919   Maintenance of the east and west waterways 750 feet     S. Doc. 313, 65th Cong., 3d sess.
                   wide and 34 feet deep, and of the Duwamish Water-
                   way 20 feet deep and 150 feet wide as far south as
               the 8th Ave. South Bridge.
Mar.   3, 1925                                                           (H. Doc. 108, 68th Cong., 1st sess.'
July 31930Enlargement yof the Duwamish Waterway-----------...........       and H. Doc. 126, 71st Cong., 2d
                                                                           sess.
Aug. 30,1935 Maintenance of the east waterway between the 750-           H. Doc. 211, 72d Cong., 1st sess.'
               foot section and Spokane St. and of the turning ba-
                   sin at the junction of the east and west waterways.

  1Contains latest published map.
   Local cooperation. Fully complied with, including agreement
to pay half of the cost of dredging the settling basin at such time
as in the judgment of the United States seems necessary.
   Terminal facilities. There are 122 wharves and piers on Seattle
Harbor, exclusive of those given in the report for Lake Washington
Ship Canal. Fifty are located on Elliott Bay, 19 on east waterway,
15 on west waterway, 35 on Duwamish Waterway, and 3 on Puget
Sound near the northern limits of the port. Of these, 20 general
cargo terminals and 1 grain terminal are open for public use.
Eleven of the general cargo terminals are publicly owned, and 7
of these are publicly operated. The grain terminal is publicly owned
and privately operated. The remaining 84 serve various industrial
purposes, with the exception of 10 that are either owned or leased
by the United States and are restricted to Government use. These
facilities are considered adequate for existing commerce.
   Operations and results during fiscal year. Condition surveys
were made at a cost of $2,560.84, and the cost of miscellaneous in-
spections and reports was $5,920.98. A contract for maintenance
dredging was awarded June 2, 1954, with preliminary costs of
$475.49. Total costs were $8,957.31, all for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1931, except the settling basin. Controlling depths in the
several waterways when last surveyed were as follows: West wa-
terway, 34 feet except along the edges and the extreme inner por-
tion in April 1953; East waterway, 34 feet except along the edges
and except over one small shoal where the least depth is 27.7 feet,
                 RIVERS AND HARBORS-SEATTLE, WASH., DISTRICT                                                      1501
from Elliott Bay to the Spokane Street terminal, and 26.9 feet
over a width of 150 feet in the southerly 600 feet of the waterway
in September 1953; Duwamish waterway, 27.2 feet except along
the edges from the head of West waterway to 1st Avenue South
in May 1953, 16.7 feet except along the edges from 1st Avenue
South to 8th Avenue South and 13.5 feet except along the edges
from 8th Avenue South to 14th Avenue South in March 1953; 9.4
by 100 feet from 14th Avenue South upstream for 3,100 feet, +0.4
by 150 feet to the settling basin, and a least depth in the settling
basin of +0.6 foot above the datum plane, in March 1954. All
depths refer to the plane of mean lower low water. Local interests
have practically completed dredging of East waterway above the
750-foot section and of the turning basin at the junction of the
waterways to 30 feet.
   The costs from Federal funds to June 30, 1954, have been $170,-
334.74 for new work and $742,145.83 for maintenance, a total of
$912,480.57. In addition, $69,332.64 has been expended from con-
tributed funds for new work.
                                           Cost and financial summary

                                                     Fiscal year ending June 30                           Total to June
                                                                                                          30, 1954, includ-
                                                                                                          ing fiscal years
                                    1950            1951           1952          1953          1954         prior to 19501

New work:
                        --------
   Appropriated--------........         --------------------                    ------------   -----------        $170,335
   Cost-------------                  ---------------------------------------                                      170,335
Maintenance:
   Appropriated -...--       $ 70,000       $143, 700           -$5, 834         $88, 875      $88, 800            901, 230
   Cost-_                     135,394         142,125                  776         9,858         8,957             742,146

  1In addition    $69,332.64 for new work was expended from contributed funds.
Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project$--------------------------23,000
                                  13. TACOMA HARBOR, WASH.
   Location. This harbor is 30 miles south of Seattle and em-
braces Commencement Bay and tributary waterways. (See U. S.
Coast and Geodetic Survey Chart No. 6407.)
   Previous projects. The project for the Puyallup Waterway,
providing for a channel 500 feet wide, 32 feet deep, and 3,650 feet
long, was adopted by the River and Harbor Act of March 3, 1905 ;
suspended by the act of June 25, 1910; and abandoned by the River
and Harbor Act of August 30, 1935. For further details, see pages
1372 to 1376 of Annual Report for 1934, and page 1875 of Annual
Report for 1938.
  The project providing for maintenance of a channel in Wapato
Waterway, 700 feet wide and 34 feet deep over such length as shall
have been dredged by local interests to dimensions stated, was
adopted by the River and Harbor Act of August 30, 1935, and
superseded by the existing project for that waterway adopted
March 2, 1945. For further details, see page 1702 of Annual Re-
port for 1944.
  Existing project. This provides for (1) city waterway, having
a channel 500 feet wide and 29 feet deep at mean lower low water
from deep water in Commencement Bay to the 11th Street Bridge,
 1502           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

500 feet wide and 22 feet deep to the 14th Street Bridge, and
varying from 500 to 250 feet wide and 19 feet deep from the 14th
Street Bridge to the end of this waterway, a total length of 8,500
feet; (2) for a channel in Hylebos Waterway 200 feet wide and 30
feet deep from Commencement Bay to the bend below Lincoln
Avenue, thence 150 feet wide and 30 feet deep to a turning basin
of the same depth, 410 feet wide and 900 feet average length; (3)
construction of two training walls, each about 700 feet long, at the
mouth of Puyallup River; and (4) dredging to a depth of 30 feet,
an area in the Wapato Waterway (renamed Port-Industrial Water-
way in 1949), not nearer than 50 feet from established pierhead
lines or lateral limits of the waterway, nor 100 feet from the north-
erly line of East 11th Street.
   The extreme tidal range is about 20 feet. The range between
mean lower low water and mean higher high water is 11.8 feet.
   The estimate of cost for new work (1954) is $448,000, exclusive
of amounts expended on previous projects, and exclusive of $40,-
000 to be contributed by local interests for dredging Wapato (Port-
Industrial) Waterway.
   The latest (1953) approved estimates for annual cost of mainte-
nance are as follows: City Waterway, $10,000; Hylebos Waterway,
$16,000; Wapato Waterway, $1,000; Puyallup River training walls,
$2,500.
The existing project was authorized by the following River and
Harbor Acts:

       Act                        Work authorized                              Documents and reports

June 13,1902    City Waterway-.......---.--------                 ..     H
                                                                         H.  Doc. 76, 56th Cong., 2d sess.
                                                                         H-------
                                                                         Rivers and Harbors Committee
July    3,1930 1Hylebos Waterway- -_ ---     _--_-----------                Doe. 25, 71st Cong., 2d seass., and
Aug. 26, 1937   Hyl           erway.......................                 Rivers and Harbors Committee
                                                                           Doec. 91, 74th Cong., 2d seas.'
Aug. 30,1935    Training walls at the mouth of Puyallup River.           Rivers and Harbors Committee
                  (Training   walls   previously   authorized   by the     Doc. 55, 72d Cong., 2d sess.
                 Public Works Administration Sept. 6, 1933.)
Mar. 2,1945     Wapato Waterway----------------.....--.-----..           H. Doc. 124, 76th Cong., 1st sess.'

 ' Contains latest published maps of Hylebos Waterway.
3 Contains latest published map of Wapato Waterway.



   Local cooperation. Fully complied with, except for Wapato
Waterway, the improvement of which is subject to the provisions
that local interests furnish, free of cost to the United States, suit-
able spoil disposal areas for new work and for subsequent main-
tenance as required, and contribute $40,000 toward the initial cost.
The port of Tacoma was advised of the foregoing requirements on
December 30, 1946; and in reply of December 31, 1946, stated it
would provide disposal areas, but did not feel justified in con-
tributing $40,000 toward the initial cost.
   Terminal facilities. There are 75 wharves and piers on Ta-
coma Harbor. Eighteen are located on Commencement Bay, 28
on City Waterway, 4 on Middle Waterway, 5 on Milwaukee Water-
way, 8 on Wapato Waterway, and 12 on Hylebos Waterway.
            RIVERS AND HARBORS-SEATTLE, WASH., DISTRICT        1503
Twenty-eight of the wharves are suitable for use by oceangoing
vessels; of these five serving general cargo terminals and one
serving a grain elevator are open for public use; two of the former
and the latter are publicly owned. These facilities are considered
adequate for existing commerce.
   Operations and results during fiscal year. A condition survey
of City Waterway was made in March 1954 at a cost of $1,468.49.
A contract was awarded June 8, 1954, for reconstruction of the
east training wall at the mouth of Puyallup Waterway by means
of contact piling, with preliminary costs of $2,463.78. The cost of
miscellaneous inspections and reports was $2,055.41. Total costs
were $5,987.68, all for maintenance.
   Condition at end of fiscal year. The existing project is 74 per-
cent complete. City waterway was completed in 1905. The costs
have been $150,018.58 for new work and $205,643.50 for mainte-
nance, a total of $355,662.08, not including $5,000 expended for
maintenance from contributed funds. The depths available in
March 1954 were as follows: 29 feet over a width of 500 feet, from
Commencement Bay to South 11th Street; 21.8 feet over a width
of 400 feet, from South 11th Street to South 14th Street; and 15.8
feet over a width of 130 feet, from South 14th Street to the head of
the waterway.
   Hylebos Waterway was completed in 1939. The costs have been
$212,501.60 for new work and $73,842.15 for maintenance, a total
of $286,343.75. Depths available in March 1953 were as follows:
30 feet over a width of 160 feet from deep water in Commencement
Bay to East 11th Street; 28.8 feet over a width of 150 feet from
East 11th Street to bend below Lincoln Avenue; and 28.8 feet over
a width of 150 feet above Lincoln Avenue, with a least depth of 30
feet in the turning basin, except in the upper 100 feet and along
the edges.
   The two rubble-mound training walls at the mouth of Puyallup
River were completed in 1934 at a cost of $51,609.12, all for new
work. Maintenance costs have been $7,834.18. Total costs to date
have been $59,443.30. On April 4, 1943, a slide destroyed the east
training wall. Approximately 550 feet of this wall will be replaced
by a contact pile structure during July 1954. The west wall is in
good condition.
   No work has been done by the Corps of Engineers on the existing
project for Wapato Waterway. Available information indicates a
controlling depth of about 30 feet in the outer half of the waterway
and about 28 feet in the eastern two-thirds of the inner portion.
  Miscellaneous inspections and reports have been made at a cost
of $2,164.51, all for maintenance.
  The work remaining to be done to complete the project is to
dredge all of Wapato Waterway to a depth of 30 feet.
   The total costs under the existing project to June 30, 1954, have
been $414,129.30 for new work, including $51,609.12 Public Works
funds, and $289,484.34 for maintenance, a total of $703,613.64, not
including $5,000 contributed funds for maintenance.




     Sig 48-1503.1534
1504           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                        Cost and financial summary

                                               Fiscal year ending June 30                      Total to June
                                                                                              30, 1954. includ-
                                                                                              ing fiscal years
                                 1950        1951        1952         1953         1954        prior to 1950 12

New work:
   Appropriated--.. ---------------------------------------------------------                         $573,714
   Cost--- -----------------------
Maintenance:
                                         --          ---                    -- ----------              573,714
   Appropriated- - ----------------          $48, 499     -$870        $2, 600     $17, 500            306, 598
   Cost-----------------.......... $1 095     45, 892      1,893        2,453        5,988             294, 831

1 Includes $159,584.46 for new work and $5,347 for maintenance for previous projects.
2 In addition $5,000 for maintenance was expended from contributed funds.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project_ _-------------________
                                                           _          - $33,870

                               14. OLYMPIA HARBOR, WASH.
   Location. This harbor is near the southern end of Puget Sound
at the head of Budd Inlet, about 45 miles southwest of Tacoma.
 (See U. S. Coast and Geodetic Survey Chart No. 6462.)
   Previous projects. The original project adopted by the River
and Harbor Act of July 13, 1892, provided for a channel on the
east side of the harbor 250 feet wide and 12 feet deep from vicinity
of Fourth Street Bridge to deep water in Budd Inlet, with a turn-
ing basin 500 feet wide at the inner end. The River and Harbor
Act of June 25, 1910, modified and extended the project to pro-
vide for a channel on the west side of the harbor 200 feet wide and
12 feet deep from deep water to a point 1,900 feet south of the west
side waterway, with a turning basin at its inner end 800 feet long
and a maximum width of 400 feet. For further details see page
1369 of Annual Report for 1934 and page 1873 of Annual Report
for 1938.
   Existing project. This provides for a channel between deep
water in iBudd Inlet and the port terminal, 30 feet deep at mean
lower low water and 500 feet wide, with suitable additional width
at the bend, and a turning basin adjacent to the port terminal 30
feet deep, 3,350 feet long, and 500 to 960 feet wide. The extreme
tidal range is 22.5 feet. The range between mean lower low water
and mean higher high water is 14.4 feet.
   The (1954) estimate of cost for new work is $608,000 exclusive
of amounts expended on previous projects. The latest (1953)
approved estimate for annual cost of maintenance is $10,000.
   The existing project was authorized by the following river and
harbor acts:
                 RIVERS AND HARBORS--SEATTLE,                        WASH., DISTRICT                 1505

       Act                         Work authorized                             Documents and reports

Jan. 21,1927    Channel 22 feet deep and 150 feet wide__ ------------
                                                              _          H. Doc. 244, 69th Cong., 1st sess.
July 3, 1930    Channels of 26-foot depth on the east side of the harbor Rivers and Harbors Committee
                                                                           Doc. 5, 71st Cong., 1st sess.
Aug. 30, 1935 1 Elimination from the project of the 12-foot channels Rivers and Harbors Committee
                  on the east and west sides of the harbor and for a       Doc. 21, 73d Cong., 2d sess.
                  channel 30 feet deep and 300 feet wide between Budd
                  Inlet and the port terminal, with turning basin of
                   same depth.
Aug. 26, 1937     Widen outer portion of channel to 500 feet, and widen   Rivers and Harbors Committee
                   entrance to turning basin.                               Doc. 75, 74th Cong., 2d sess.   2
Mar.    2,1945    Entrance channel 500 feet wide to and including a       H. Doc. 699, 76th Cong., 3d sess.
                   turning basin 3,350 feet long and generally 960 feet
                   wide, all at a depth of 30 feet at mean lower low
                   water.

1   Included in Public Works Administration program.
2   Contains latest published map.


   Local cooperation. Local interests are required to furnish, free
of cost to the United States, suitably bulkheaded areas for the
retention of dredged materials, when and as required. The port
of Olympia advised January 25, 1949, that it could not comply
with the requirements at that time but would do so on the earliest
possible date.
   Terminal facilities. There are 17 wharves and piers on Olym-
pia Harbor. Two serve general cargo terminals that are open
for public use; one of these, which is publicly owned and operated,
is located on the improved channel and has sufficient depths along-
side to accommodate oceangoing vessels; the other, privately
owned and operated, is used by vessels in the Puget Sound trade.
The remainder are suitable for barges and scows and are used
for various industrial purposes. These facilities are considered
adequate for existing commerce.
   Operations and results during fiscal year. A condition survey
was made in December 1953 at a cost of $1,245.24. Miscellaneous
inspections and reports were made at a cost of $695.57. Total
costs were $1,940.81, all for maintenance.
   Condition at end of fiscal year. The existing project is 83 per-
cent complete. The channel and basin were completed to present
dimensions in 1939. In December 1953 controlling depths in
the completed section were as follows: 30.4 feet in the outer chan-
nel, 30.8 feet in the entrance channel, and 30 feet in the turning
basin. The work remaining to be done to complete the project
is to widen the entrance channel and enlarge the turning basin
as authorized by the Act of March 2, 1945. The costs under the
existing project to June 30, 1954, have been $262,825.33 for new
work, including $105,467 Public Works funds, and $79,750.78
for maintenance, a total of $342,576.11.
1506           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                        Cost and financial summary

                                               Fiscal year ending June 30                    Total to June
                                                                                            30, 1954, includ-
                                                                                            ing fiscal years
                               1950           1951                1952   1953    1954        prior to 1950 1

New work:
   Appropriated -------    ----------    - -$184,094     ....--                                     $446,082
   Cost_ ---       _- -_              $32 -446,082
Maintenance:
   Appropriated    -                          -8,999                              $1, 941             94, 169
   Cost-      -                  2,007 -             -            ...              1,941              94,169

1 Includes $183,257 for new work and $14,418 for maintenance for previous projects.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project----------_ _       -------    $_
                                                                        $345,175

           15. GRAYS HARBOR AND CHEHALIS RIVER, WASH.
   Location. Grays Harbor lies at the mouth of Chehalis River,
in the southwestern part of the State of Washington, 45 miles
north of the entrance to Columbia River. The inner portion
comprises two main channels, the south and the north, connecting
the harbor proper with the Chehalis River at Aberdeen. Chehalis
River rises in the southwestern part of the State of Washington,
about 40 miles east of the Pacific Ocean, flows in a general north-
westerly direction and empties into the eastern part of Grays
Harbor. (See U. S. Coast and Geodetic Survey Chart No. 6195.)
   Previous projects. The original project for the Chehalis River,
adopted by the River and Harbor Act of August 2, 1882, provided
for removal of log jams and for annual snagging. The original
project for the inner harbor, adopted by the River and Harbor
Act of July 13, 1892, provided for improvement of North channel,
by constructing a dike across middle channel and head of South
channel; and improving Chehalis River from Grays Harbor to
Montesano by dredging a channel 16 feet deep and 200 feet wide
and by diking across five sloughs. For further details, see pages
2002-2003 of Annual Report for 1915, and page 1863 of Annual
Report for 1938.
   Existing project. This provides for an entrance channel across
the bar 600 feet wide and 30 feet deep, to be secured by a south
jetty 13,734 feet long and a north jetty 16,000 feet long, both at
an elevation of 16 feet above mean lower low water and by dredg-
ing; for maintenance of a channel 30 feet deep at mean lower low
water and 350 feet wide from deep water in Grays Harbor to
the Port of Grays Harbor Commission terminal, a distance of
131/4 miles; thence 26 feet deep and 200 to 350 feet wide to the
Union Pacific Railroad bridge at Aberdeen, a distance of 21/4
miles; thence 18 feet deep and 200 feet wide to Cosmopolis, a
distance of 3 miles; for a channel 16 feet deep at mean lower low
water and 150 feet wide from Cosmopolis to Montesano, a dis-
tance of 103/4 miles, with a turning basin at Montesano of the
same depth, 1,500 feet long, and 200 to 500 feet wide; for a channel
14 feet deep at mean lower low water and 100 feet wide in South
Bay to Bay City; for a breakwater at and maintenance of an
entrance channel to Westhaven Cove; and for protection of Point
Chehalis for an exposed length of about 7,500 feet.
                   RIVERS AND HARBORS-SEATTLE, WASH., DISTRICT                                                    1507
   The tidal range between mean lower low water and mean higher
high water is 9 feet at Point Chehalis, 9.9 feet at Aberdeen, and
8.1 feet at Montesano. The extreme range is 15 feet at Point
Chehalis, 18.1 feet at Aberdeen, and 23.8 feet at Montesano (river
flood of 1935).
   The estimate of cost for new work (1954) is $4,766,000. This
cost does not include amounts expended on previous projects and
Navy funds expended on deepening from 26 feet to 30 feet the
channel from deep water in Grays Harbor to the Port of Grays
Harbor Commission terminal, nor does it include $239,500 to be
contributed by local interests. The latest (1953) approved esti-
mate for annual cost of maintenance dredging in the section below
Aberdeen is $373,700. Local interests are to maintain the work
above Aberdeen; enlarge and maintain Westhaven base.
   The existing project was authorized by the following River and
Harbor Acts:

       Act                            Work authorized                                   Documents and reports


June 3, 1896  South jetty                                               --------- Annual Report,1895, pp. 3517-3533.
Mar. 2,1907   A north jetty, 9,000 feet long-------------------- Rivers and Harbors Committee
                                                                                          Doc. 2, 59th Cong., 2d sess.
    Do....... The 18-foot channel...........................---------------------------. H. Doc. 507, 59th Cong., 1st sess.
June 25, 1910 Extension of the north jetty 7,000 feet; length of the         Rivers and Harbors Committee
               south jetty fixed at 13,734 feet.                               Doe. 29, 61st Cong., 2d sess.
    Do-...... A 6-foot channel above Cosmopolis_ ,            - .  -..........H. Doc. 1125, 60th Cong. 2d seas.
Aug. 8,1917 lDredging in the bar channel-------------------H.                    Doc. 1729, 64th Cong., 2d sess.;
Jan. 21, 1927        ng                                                        H. Doc. 582, 69th Cong., 2d seas.
July 3, 1930 The 16-foot channel above Cosmopolis, with turning              H. Doe. 315, 70th Cong., 1st sess.
                    basin at Montesano.
Aug. 30, 1935      Reconstruction of the north and south jetties to an            Rivers and Harbors Committee
                    elevation of 16 feet above mean lower low water.                Doc. 2, 74th Cong., 1st sess.
    Do.......      Maintenance of the 26-foot channel below Aberdeen              H. Doc. 53, 73d Cong. 1st sess.;
                    (as authorized by the Public Works Administration               Rivers and Harbors Committee
                    Dec. 11, 1933) and for combining the projects                   Doec. 2, 74th Cong., 1st sess.
                    for Grays Harbor and bar entrance, and Grays
                    Harbor, inner portion, and Chehalis River, under
                    a modified project for Grays Harbor and Chehalis
                    River.
Mar.    2, 1.945   Maintenance of a 30-foot depth in the channel from             Report on file in Office, Chief of
                    deep water in Grays Harbor to the Port of Grays                Engineers.
                    Harbor Commission terminal, which was deepened
                    from 26 to 30 feet with Navy funds.
June 30, 1948      The 14-foot channel to Bay City; breakwater at                 H. Doc. 635, 80th Cong., 2d sess.
                    Westhaven; protection of Point Chehalis; and                    (Contains latest published map.)
                    maintenance of Westhaven entrance channel.



   Recommended modifications of project. Under date of August
28, 1953, the Chief of Engineers recommended modification of the
existing project to provide essentially for a channel 30 feet deep
and 200 to 350 feet wide from the upstream end of the authorized
30-foot channel to a point approximately 2.6 miles upstream from
the Union Pacific Railroad bridge at Aberdeen, and a turning
basin 30 feet deep at the upstream end of the channel, with
Federal maintenance dredging of the channel above the railroad
bridge, and the turning basin. The estimated Federal cost for
construction is $403,400, and for maintenance, $12,500 annually
in addition to that now required; subject to certain conditions of
local cooperation.
   Local cooperation. The River and Harbor Act of July 3, 1930,
adopting the 16-foot channel, provides that local interests con-
tribute one-half the first cost, estimated at $239,500, and give
1508     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

assurances satisfactory to the Secretary of War and Chief of En-
gineers that they will assume the entire cost of maintenance of
same and provide a suitable public terminal at Montesano. These
assurances have been given and $35,834.27 contributed, which was
expended in 1931 with an equal amount of Government funds in
securing a 12-foot channel to Montesano, the remaining con-
tribution necessary to complete the project being deferred until
a later date, as approved by the Secretary of War, March 18, 1931.
   The River and Harbor Act of August 30, 1935, continues the
requirement that local interests shall pay one-half of the first
cost of enlarging the channel between Cosmopolis and Montesano,
and further provides that the Grays Harbor Port Commission
shall continue to remove all snags and deadheads from the chan-
nels, shall furnish free of cost to the United States suitable areas
for the disposal of dredged material as and when needed, and
shall assist in the work of maintenance by loaning to the United
States, when not required on the work of the Commission, its pipe-
line dredge without charge other than reimbursement to the Port
of Grays Harbor Commission for the operating costs of the dredge
on a basis approved by the Chief of Engineers, and maintain the
channel above the Union Pacific Railroad bridge at Aberdeen.
These conditions have been met as required to cover current needs.
   With Navy funds, the 26-foot channel was deepened to 30 feet,
and widened to 350 feet in the narrow section, from the port
terminal to deep water, at a cost of $162,000.
   The Act of June 30, 1948, authorizing the Bay City channel and
improvements at Westhaven and Point Chehalis, provides that
local interests furnish assurances satisfactory to the Secretary of
the Army that they will furnish lands and rights-of-way required
for construction and suitable spoil disposal areas for initial dredg-
ing and subsequent maintenancey,when and as required; maintain
depths at the IBay City wharf commensurate with those of the
channel; lend to the United States the Port of Grays Harbor
dredge for dredging the Bay City and Westhaven channels, with-
out charge other than reimbursement for the operating cost of
the dredge on a basis approved by the Chief of Engineers; hold
and save the United States free from damages due to construction
and maintenance of improvements; enlarge and maintain the
Westhaven base by dredging; and construct, in accordance with
plans approved by the Secretary of the Army, maintain, and
operate, adequate mooring facilities within the basin, utilities, and
a public landing with suitable service and supply facilities, open
to all on equal terms. The necessary assurances of local co-
operation were furnished by the Port Commission of the Port of
Grays Harbor on October 7, 1949, and were approved by the
Secretary of the Army on November 23, 1949. The Port Com-
mission furnished necessary rights-of-way on May 1, 1950; and
dredged the existing base to a depth of 16 feet and constructed
bulkheads, wharf and float facilities, utilities, service and supply
features in 1952, thus completing requirements for local co-
operation, except for enlargement of the base.
   Terminal facilities. There are 33 wharves and piers on Grays
Harbor and adjacent inland waters, including 1 general cargo
        RIVERS AND HARBORS-SEATTLE, WASH., DISTRICT         1509
terminal, 13 sawmill wharves, 1 pulp- and paper-mill wharf, 8
fish wharves; 8 miscellaneous industrial wharves, and 2 are not
in use. One general cargo wharf and two fish wharves are
publicly owned and open to public use. These facilities are con-
sidered adequate for existing commerce.
   Operations and results during fiscal year. New work, hired
labor: Operations during the fiscal year included work on prepara-
tion of a model study report by the Waterways Experiment Sta-
tion at Vicksburg, and preliminary engineering studies and
investigations for protection of Point Chehalis.
   Contract: A contract for reinforcement of breakwater A and
groin 4 and repair of revetment at Westhaven Cove was awarded
in August 1953 and completed in October 1953, using 5,780 tons
of rock, 516 cubic yards of gravel, and 3,840 feet (board measure)
of lumber. A contract for plank reinforcement of breakwater A
at Westhaven Cove was awarded in February 1954 and completed
in March 1954, using 3,840 feet (board measure) of lumber.
   Total costs were $76,634.58, all for new work.
   Maintenance: Surveys were made by the U. S. survey boat Ma-
mala at a cost of $21,547.66. The United States hopper dredge
Pacific, during the period November 1953 to February 1954, re-
moved 7,000 cubic yards of material from the Chehalis River
above Cow Point, 286,224 cubic yards from Cross-Over Channel,
128,551 cubic yards from Sand Island Shoal, and 16,814 cubic
yards from Westhaven Cove outer channel, a total of 438,589
cubic yards, at a cost of $154,589.77. The pipeline dredge Robert
Gray, leased from the Port of Grays Harbor Commission, removed
267,771 cubic yards of material from the North Channel at a cost
of $49,773.22. Miscellaneous inspections and reports were made
at a cost of $2,647.29.
   Costs for the fiscal year were $76,634.58 for new work and
 $228,557.94 for maintenance, a total of $305,192.52.
   Condition at end of fiscal year. The existing project was 82
percent complete. The south jetty was completed in 1902 with
a groin 11,952 feet from the high-water line. A 12,656-foot sec-
tion of the jetty was reconstructed to an elevation of 20 feet
above mean lower low water during the period 1936-40. In July
1953, the inner 100 feet of the reconstructed jetty had been
partially removed, the next 4,500 feet were at or near grade, the
next 2,400 feet showed subsidence to a maximum depth of 15 feet
below grade, and the outer 5,456 feet varied from elevations 4
feet above to elevations below mean lower low water. Serious
erosion of the shore line immediately north of the jetty was oc-
curring. The north jetty was completed to midtide elevation in
December 1913. It was later restored and raised to or above
ordinary high water, this work being completed in January 1916.
During 1941 and 1942, an 8,288-foot section was reconstructed
westward from the high-water line, the inner 7,760 feet being
raised to a crest elevation of + 20 feet and the remainder to an
elevation of + 30 feet. The remainder of the north jetty has not
been restored. The 412-foot section seaward of the reconstructed
jetty is at the elevation of mean lower low water, and the 7,300-
foot section shoreward of the reconstructed jetty has sanded in.
1510             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

An examination of the reconstructed jetty, made in July 1953,
showed that sea action had leveled the outer 325 feet; had breached
the sand spit at the shore end, exposing old jetty rock to the east;
and a 1,000-foot section about 1,000 feet from the outer end showed
a maximum settlement of 10 feet. The Westhaven Cove break-
water was completed in 1950, and local interests completed initial
dredging of an entrance channel in 1952. Construction of three
rock groins for protection of Point Chehalis was completed in
1951. In 1952, the groins were reinforced, and a revetment was
constructed along the north shore of Point Chehalis from groin
4 to groin 5, using rock from the east end of the south jetty. In
August to October 1953 and March 1954, breakwater A and
groin No. 4 were reinforced.
   The 26-foot channel previously dredged by the Port of Grays
Harbor below Aberdeen was deepened to 30 feet from the port
terminal to deep water in the lower harbor in 1945. The 18-foot
channel below Cosmopolis and 6-foot channel between Cosmopolis
and Montesano were completed in 1910, and the latter was deep-
ened to 12 feet in 1931. The Bay City Channel was completed in
July 1950.
   The controlling depths, when last ascertained, were as follows:
Bar channel, 35 feet over a width of 600 feet (July 1953) ; deep
water in lower harbor to port terminal, 26.9 feet over a width of
250 feet (May 1954); port terminal to Union Pacific Railroad
bridge at Aberdeen, 26 feet over a width of 200 feet (May 1954) ;
Union Pacific Railroad bridge at Aberdeen to Cosmopolis, 22.6
feet over a width of 200 feet (January to March 1950); Cos-
mopolis to Montesano, 8.9 feet (April 1943); Bay City Channel,
14 feet over a width of 100 feet (November 1953). Project
dimensions were available in Westhaven Cove entrance channel
in February 1954.
   The work remaining to be done to complete the project is to
construct further protective works on the west shore of Point
Chehalis as required, and increase the channel depth from Cos-
mopolis to Montesano to 16 feet.
   The total costs of the existing project to June 30, 1954, have
been as follows:

                                                                     New work        Maintenance       Total

Reg-lar ._        -----------------------------                   $3, 793, 808       $13, 148, 641     $16, 942, 449
Public works....---------------------------------------                -------------       57, 000           57, 000
Emergency relief.......------------------------------------- ---------------              409, 660          409, 660

     Total, United States funds ---------------------                  3, 793, 808      13, 615, 301    17, 409, 109
Contributed funds .-----------------------------------                     35, 834           47, 889         83, 724

      Total, all funds......-------------------------------.......     3, 829, 642      13, 663, 190    17, 492, 833
               RIVERS AND HARBORS-SEATTLE, WASH., DISTRICT                                            1511
                                    Cost and financial summary

                                          Fiscal year ending June 30                          Total to June
                                                                                              30, 1954, includ-
                                                                                              ing fiscal years
                             1950        1951            1952        1953          1954       prior to 1950 2


New work:
   Appropriated- .......    $650, 000   $500. 000   -                 (3)       -$135, 400        $ 3, 969,189
   Cost----------------..    112, 664    436,593        $245,168    $ 81,294        76, 635         3, 906, 943
Maintenance:
    Appropriated.- .-        365, 770    340, 000        109, 665    233, 000      233, 405         13, 661, 431
    Cost----------------     398, 991    329,894         111,718     238,186       228,558          13,652,716


  1Includes $113,134 for new work and $37,415 for maintenance for previous projects.
  2 In addition $35,834 for new work and $47,889 for maintenance was expended from contributed funds;
and $162,000 was expended from Navy funds for new work.
  8 Funds in amount of $137,781 previously reported as revoked. However, revocation of allotment in
amount of $135,400 was not made until October 15, 1953.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954                - -- - $ 62,247
    Appropriated for succeeding fiscal year ending June 30, 1955-------_          93,300
    Unobligated balances available for succeeding fiscal year ending June 30,
       1955 -- ----------------------------------------------                   155,547
    Estimated additional amount needed to be appropriated for completion
      of existing project---_ ---------------         ----                   -  703,511

                     16. WILLAPA RIVER AND HARBOR, WASH.
   Location. Willapa Harbor consists of the lower reaches of
Willapa River and Willapa Bay, an inlet of the Pacific Ocean located
about 30 miles north of the mouth of Columbia River. Willapa
River rises in the State of Washington, about 30 miles east of the
harbor, flows in a general westerly direction, and empties into the
bay. (See U. S. Coast and Geodetic Survey Chart No. 6185.)
   Previous projects. The original project adopted by the River
and Harbor Act of July 13, 1892, provided for a channel 100 feet
wide and 8 feet deep from deep water in Willapa Bay to Willapa
City, by dredging and construction of dikes across the head of
Mailboat and Lauderbach Sloughs, and for snagging the Nasel
River. The act of August 18, 1894, appropriated funds for the
work underway and for improving North River by removal of a
log jam. The act of March 3, 1899, authorized additional work in
clearing a channel through the log jam on North River and ap-
propriated funds for work on the 8-foot channel to Willapa City.
The act of June 13, 1902, authorized the expenditure of funds for
the improvement of Willapa River and Harbor, North and Nasel
Rivers, by snagging or otherwise. The act of March 2, 1907, con-
templated a channel 150 feet wide and 12 feet deep between South
Bend and Raymond. The act of June 25, 1910, provided for a chan-
nel 200 feet wide and 18 feet deep from deep water in Willapa Bay
to the junction of the north and south forks of the river at Ray-
mond, and for a channel 18 feet deep and 150 feet wide up the south
fork for a distance of 3,100 feet. For further details, see page 2001
1512               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

of Annual Report for 1915; page 968 of Annual Report for 1910;
and page 1861 of Annual Report for 1938.
  Existing project. This provides for a channel over the bar at
the mouth of Willapa Bay, 26 feet deep at mean lower low water,
with a minimum width of 500 feet; for straightening the river
channel at the Narrows about a mile downstream from Raymond
by a cutoff channel 200 feet wide, 24 feet deep, and about 3,100
feet long; for a channel 24 feet deep and 200 feet wide from deep
water in Willapa Bay to the forks of the river at Raymond, 24 feet
deep and 150 feet wide up the south fork as far as the deep basin
above the Cram lumber mill, and up the north fork to a point op-
posite Twelfth Street, with a turning basin 250 feet wide, 350 feet
long, and 24 feet deep at the latter point, and a closing dike at Mail-
boat slough; and for a channel from deep water in Palix River to
Bay Center Dock, with a depth of 10 feet at mean lower low water
over a bottom width of 40 feet, widened at the shoreward end to
provide a small mooring basin. The length of the section included
in the project is 26 miles for the main channels, and about 2,800
feet for the Palix River-Bay Center channel. The tidal range be-
tween mean lower low water and mean higher high water is 8.9 feet
at Toke Point; 9.9 feet at Raymond; and 9.2 feet at Bay Center.
The extreme range is 18 feet at Toke Point; 19.3 feet at Raymond;
and 16 feet at Bay Center.
  The actual cost for new work was $772,637, exclusive of amounts
expended on previous projects and exclusive of $71,775 contributed
by local interests. The latest (1953) approved estimate for annual
cost of maintenance is $277,500.
  The existing project was authorized by the following River and
Harbor Acts:

                                                                                                        1
       Act                          Work authorized                             Documents and reports

July 27,1916       Present project dimensions of the river channels __ _   H. Doc. 706, 63d Cong., 2d sess.
Aug. 30, 1935 2 Maintenance of the channel over the bar to a depth of      Rivers and Harbors Committee
                     26 feet and minimum width of 500 feet.                  Doc. 41, 72d Cong., 1st sess.
      Do s......   For the cutoff channel at the Narrows------------       Rivers and Harbors Committee
                                                                            Doc. 37, 73d Cong., 2d sess.
Mar.     2,1945    Channel from deep water in Palix River to Bay Cen-      H. Doc. 481, 76th Cong., 2d sess.
                     ter dock.

  ' Contain latest published maps.
  2 Included in the Public Works Administration program, Dec. 11, 1933.
  =   Included in the Emergency Relief program May 28, 1935.

  Recommended modifications of project. Under date of March
22, 1954, the Chief of Engineers recommended modification of the
existing project to provide for a mooring basin adjacent to the
port wharf at Tokeland; an entrance channel at Nahcotta, a moor-
ing basin, and a rubble-mound breakwater; widening the existing
project channel in Willapa River in the section upstream from the
foot of Ferry Street, South Bend, to the westerly end of the Nar-
rows cutoff channel, through the Narrows upstream to the forks
of the river at Raymond; and removal of snags, piles, and other
obstructions in the navigable channel of the Naselle River between
                RIVERS AND HARBORS-SEATTLE, WASH., DISTRICT                                                       1513
Naselle and the mouth, at an estimated cost to the United States of
$817,710 for construction and $9,450 annually for maintenance in
addition to that now required; subject to certain conditions of local
cooperation.
   Local cooperation. Fully complied with.
  Terminal facilities. There are 33 wharves on Willapa River
and Harbor, including 7 in Willapa Bay, 7 in Bay Center, 17 in
Raymond and South Bend, and 2 in Tokeland. Three of the wharves
at Raymond and South Bend are suitable for use of oceangoing
vessels; one of these, which is publicly owned and operated, is open
for use as a general cargo terminal, and 2 are located at sawmills.
All of the other wharves, including three that are publicly owned
and operated, are used by light-draft vessels in local trade. These
facilities are considered adequate for existing commerce.
   Operations and results during fiscal year. Maintenance dredg-
ing by the United States hopper dredge Davison during Septem-
ber and October 1953, and May and June 1954, totaled 30,277
cubic yards removed from the bar channel and 164,792 cubic
yards from Willapa River at a cost of $173,915.78. Hydrographic
surveys were made by the United States survey boat Mamala at
a cost of $18,051.19. The cost of miscellaneous inspections and
reports was $1,415.52. Total costs were $193,328.49, all for
maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1936 'except for the channel from Palix River to Bay Cen-
ter, which was completed in 1949. The dike at the head of Mailboat
slough is in good condition. A survey completed June 8, 1954,
showed a controlling depth of 26 feet over a width of 1,500 feet
across the bar. The controlling depths in the inner channels in
June and July 1954 were as follows: Below forks at Raymond, 23.6
feet over width of 140 feet; lower 2,200 feet of North Fork, 24 feet
over width of 80 feet; and lower 1,500 feet of South Fork, 20 feet
over width of 100 feet. The controlling depth in Bay Center Chan-
nel in July 1953 was 6.4 feet with a least depth of 3.2 feet in the
turning basin. There has been no navigation in the upper portions
of the forks, and no soundings have been taken in recent years.
   The total costs of the existing project to June 30, 1954, have been
as follows:

                                                                        New work          Maintenance          Total


Regular          ..      ..     ..     ..     ..   ..            ..       $580,322.47
                                                          . .-_____-______..               $2, 580,015.73     $3,160,338.20
Public works ..----------------             ---                     ----------------.           78,533.00         78,533.00
Emergency relief-..           ._ _......--- --------------------             192,314.06                          192,314.06

     Total, United States funds....-------------------                    772, 636. 53       2, 658, 548.73   3,431,185.26
Contributed funds -----------        -----------                           71, 775.00     ---------------        71, 775.00

       Total, all funds .               ----- ----------
                                  ..---------                .            844,411.53        2,658,548.73      3,502,960.26



  The total costs have been $3,431,185.26, of which $3,160,338.20
were regular funds, $78,533 public works funds, and $192,314.06
emergency relief funds. In addition, $71,775 was expended from
contributed funds.
1514             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                         Cost and financial summary

                                                   Fiscal year ending June 30                                     Total to June
                                                                                                              30, 1954, includ-
                                                                                                              ing fiscal years
                                  1950           1951             1952              1953           1954        prior to 1950 1 s

New work:
      Appropriated- --- _.      -$14, 783 -----------.              -$852     ----                                    $1, 000, 720
      Cost....-----------------    29, 027      $3, 794                     6 ------------------------                 1, 000, 720
Maintenance:
      Appropriated- ......        292, 848       196, 752         131, 259      -$19, 635         $198, 250            2, 673, 783
      Cost. -------------         329,651        186, 901          85, 217         38,610          193,382             2,665, 725

  I Includes $228,084 for new work and $7,177 for maintenance for previous projects.
  s In addition $71,775 for new work was expended from contributed funds for existing project and $6,596.92
contributed funds for previous project.


                        17. INACTIVE                NAVIGATION                     PROJECTS

                                                                                   Cost to June 30, 1954
                                                              For last                                              Estimated
                    Name of project                         full report                                               amount
                                                            see annual                            Operation         required to
                                                            report for-       Construction          and              complete
                                                                                                 maintenance

1. Kootenal River, Idaho and Mont. ............ 1933                            $9, 254.54         $5, 642. 60         (2)
2. Columbia River, Wenatchee to Kettle Falls,   1923                           274, 390. 53         7,692.58           (3)
      Wash.'
3. Skagit River, Wash...----------------------1950                                99, 829.80       36, 257.81          $348,200
4. Stillaguamish River, Wash.      -----        1946                        ...                                         189,000
5. Flathead River, Mont. --------------------   1901                              9,810.77(6)
6. Port Angeles Harbor, Wash. 7 ____________    1950                                                                     44,000
7. Port Gamble Harbor, Wash..                                    1953
                                         ..........-----------------           1 11i911.08          13, 336.65            56,000
8. Polson Bay, Flathead Lake, Mont.8 .........   1918                              4,491. 14     258.86                (2)
9. Port Orchard Bay, Wash. -_-    _ -- -     - -1928                              42, 803.58 1.......                  (2)
10. Hammersley Inlet, Wash.'---- -- __-------..                 1950                9, 000.00       10, 682.67            30,000
11. Hoquiam River, Wash                             1950
                                 ____......................     51, 293.64                          5, 316.35            (2)
12. Removing accumulated snags and debris un-       1953    .............                          69, 320.69           ( o)
     der authority of section 3 of River and Har-
     bor Act approved March 2, 1945.

  1No commerce reported.
    Completed.
8 All work now contemplated has been completed. River closed by Grand Coulee Dam.

  A
 ' Local cooperation cannot be expected.
    No longer economically justified.
E All work now contemplated has been completed.

 'Proposed for construction in 1957. Modification recommended May 23, 1951, in H. Doc. 155, 82d
Cong., 1st sess.
9' No maintenance required at present.

  ' Deepening of shoal not required for present traffic.
  10All work now contemplated has been completed. Revoked, $567.32.
It In addition $21,260.09 was expended from contributed funds.


                      18. LIBBY DAM, KOOTENAI RIVER, MONT.

      Location.          The Kootenai River rises in British Columbia, flows
southerly about 40 miles into Montana and thence northwesterly
across western Montana and the northwestern corner of Idaho to
re-enter British Columbia, where it empties into Columbia River
after passing through Kootenay Lake. Libby Dam will be located
on the Kootenai River, 15 miles upstream from Libby, Montana,
and 217.0 miles upstream from its confluence with the Columbia
River.         (See U. S. Geological Survey topographic sheet, "Thomp-
son Lakes, Mont.")
      Existing project.               The project provides for a straight concrete
gravity overflow flood control and power dam on Kootenai River
about 400 feet high; for a powerhouse; and for a reservoir back-
                 FLOOD CONTROL---SEATTLE, WASH., DISTRICT                                            1515
ing water into Canada with a usable storage capacity of 5,010,000
acre-feet. The initial power installation will consist of six units,
each unit with a capacity of 100,000 kilowatts. Construction of
the dam will depend on an order to be issued by the International
Joint Commission.
   The estimate of cost for new work (1954) is $268,000,000 (six
units). The latest approved estimate for average annual operation
and maintenance for a 50-year project life is $876,000 (six units).
   The existing project was authorized by the Flood Control Act
of May 17, 1950. (See H. Doc. 531, 81st Cong., 2d sess., which con-
tains the latest published map.)
   Local cooperation. None required.
   Operations and results during fiscal year. Preliminary engi-
neering studies were continued on final location of axis, type and
layout of dam, construction materials investigation, preliminary
locations of alternate routes for railroad relocation, and studies for
relocation of public and Forest Service roads. A report on "Import
of the Proposed Libby Dam upon the Forest Economy of Lincoln
County, Montana," was prepared by the Forest Service for the
Corps of Engineers, using Corps planning funds. This report
was given wide distribution to all pertinent local, state and Federal
interests. Field work included mapping alternate railroad relo-
cations, topography for alternate dam axes, explorations for con-
crete aggregate, and preliminary exploration by drilling at two
axes. Costs were $98,097.05, all for new work.
   Condition at end of fiscal year. No construction work has been
done. Preliminary engineering is about 25 percent complete. The
general location of the dam has been fixed near Dunn Creek above
the Fisher River. Additional studies of dam layouts, and founda-
tion exploration are under way. Discussions have been held with
Great Northern Railway, United States Forest Service, Montana
State Highway Department, J. Neils Lumber Company, and Zono-
lite Mine Company on relocation problems. The project as a whole
is about 2 percent complete. Costs to June 30, 1954, have been
$439,976.13, all for new work.
                                      Cost and financial summary

                                               Fiscal year ending June 30                    Total to June
                                                                                             30, 1954, includ-
                                                                                             ing fiscal years
                               1950          1951         1952        1953        1954        priorto 1950

New work:
   Appropriated........ ....      .. _ __. __... .....   $285,000    $ 85,500    $150,000            $520, 500
   Cost--               _98,                                  466     243, 413     98, 097            439, 976


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954                   ------------
                                                                          $57,555
    Appropriated for succeeding fiscal year ending June 30, 1955-.....     46,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955---------------------------------------------               103,555
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project_-_____ __-_______--___ __ - 267,433,500
1516    REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

19. ALBENI FALLS RESERVOIR, PEND OREILLE RIVER, IDAHO
   Location. Pend Oreille River has its source in Pend Oreille
Lake in northern Idaho, which receives most of its inflow from
Clark Fork. The lake has an area of about 83,500 acres. Pend
Oreille River leaves the lake near Sandpoint, Idaho, and flows
westerly 25 miles to Albeni Falls, where the channel is divided
by an island and the low water fall is about 7 feet. About 2 miles
downstream from the falls, the stream enters the State of Wash-
ington, in which its course is northwesterly for 72 miles to the
Canadian border. In Canada, Pend Oreille River flows westerly
for 16 miles and joints the Columbia River. Just downstream from
this junction, Columbia River enters the United States, where it
flows generally southward across Washington and westerly along
the Washington-Oregon line to the Pacific Ocean, a total distance
of about 748 miles. (See U. S. Geological Survey topographic
sheets "Sandpoint, Idaho," and "Newport, Wash.")
   Existing project. The project provides for a low concrete
gravity dam at Albeni Falls on Pend Oreille River for power gen-
eration, flood control, and related water uses. The dam will con-
sist of a gated, open channel spillway in the left channel and a
powerhouse having an installation of 42,600 kilowatts in the right
channel, creating a reservoir with a usable storage capacity of
1,153,000 acre-feet. The dam site is 838 and 90 miles upstream
from the mouths of Columbia and Pend Oreille Rivers, respec-
tively, and is 50 miles northeast of Spokane, Wash.
   The estimate of cost for new work (1954) is $31,100,000. The
latest (1953) approved estimate for annual cost of maintenance
is $345,000.
   The existing project was authorized by the Flood Control Act
of May 17, 1950. (See S. Doc. 9, 81st Cong., 1st sess., which con-
tains the latest published map.)
   Local cooperation. None required.
   Operations and results during fiscal year. Operation and main-
tenance, hired labor: The reservoir was operated through its sec-
ond annual cycle of storage and release during the year. The
highest pool level attained was elevation 2062.62, approximately
normal, on August 18, 1953; the lowest was elevation 2048.17 on
January 21, 1954. Maximum storage used was 1,295,000 acre-
feet. There was no flood surcharge during the year. The log
chute was operated to pass 40 rafts constituting 168 tons of cut
timber through the dam for processing by mills downstream. Rou-
tine structural, mechanical and electrical maintenance was per-
formed on the spillway dam and equipment, and on those fea-
tures of the powerhouse that are completed and operating.
   New work, hired labor: Planning was continued for protective
            FLOOD CONTROL--SEATTLE, WASH., DISTRICT          1517
and restoration works required by reservoir effects on railroads,
highways, municipal, and utility properties. Engineering and
design was completed and contract awarded for construction of
drift-removal sites in the reservoir. Shop inspections of manu-
factured equipment and laboratory tests of construction materials
were continued. Contract for installation of powerhouse equip-
ment and completion of powerhouse was awarded in July 1953.
Acquisition of land rights for the reservoir was continued.
   New work, contract: Supply contracts were completed for pow-
erhouse bridge crane, elevator, draft tube gantry crane, trash
raking equipment, switchgear, and miscellaneous electrical equip-
ment; and were continued for hydraulic turbines and generators,
turbine governors, main transformers, machine shop equipment,
and miscellaneous electrical equipment. Construction of the pow-
erhouse and intake structure was continued, and is about 99 per-
cent complete. Construction of drift-removal sites is about 80
percent complete. Installation of powerhouse equipment is about
50 percent complete. Operations were continued on protective
works for county roads which are vulnerable to direct damage by
the reservoir.
   The costs during the fiscal year were $8,165,232.99 for new work
and $17,987.05 for maintenance, a total of $8,183,220.04.
   Condition at end of fiscal year. Construction of the existing
project was started in January 1951 and the project is about 86
percent complete. Engineering and design are about 98.5 percent
complete. Construction of the spillway dam and powerhouse cof-
ferdams was completed in June 1952. The project started opera-
tions in June 1952 impounding storage which was used to in-
crease minimum flows through downstream power plants during
the extremely low water supply period of the fall. Construction
of the powerhouse and intake structure was started in March 1952
and is about 99 percent complete. Installation of powerhouse
equipment was started in July 1953 and is about 50 percent com-
plete. Engineering and design of powerhouse operating equip-
ment and machinery are complete. Evaluation of reservoir effects
on vulnerable public and utility property is complete for most
items and is continuing on the remainder. Negotiations with own-
ing agencies are proceeding with a view to restoring or protecting
the properties so far as legally required.
   Work remaining to be done to complete the project is installa-
tion of powerhouse equipment; design and construction of a few
minor features; delivery of remaining powerhouse operating
equipment and machinery; and limited development of public ac-
cess and reservoir utilization facilities.
   The costs to June 30, 1954, have been $26,875,417.87 for new
work and $17,987.05 for maintenance, a total of $26,893,404.92.
1518              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                              Cost and financial summary

                                                         Fiscal year ending June 30                                Total to June
                                                                                                                  30, 1954, includ-
                                                                                                                  ing fiscal years
                                       1950            1951             1952            19553          1954        prior to 1950


New work:
  Appropriated.-------. ---
   Cost---------       ----------------
                                         -         $2,900,000 $10,000,000 $ 6,966,000
                                                     1,408,715              6,384,973 210,916,496
                                                                                                    $7,344,185
                                                                                                     8,165,233
                                                                                                                      $27, 210,185
                                                                                                                        26,875,418
Maintenance:
  Appropriated.......--....                                  -----------             --- -              19,900              19 900
  Apo      rte-----------
   Cost............         .    ........-----------------------------------------                      17,987
                                                                                                        17, 987             17,987
                                                                                                                            17 987

  1 Includes $504,185 borrowed funds.
  2 Erroneously reported in fiscal year 1953 Annual Report as $10,913,173.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_-----------      $153,372
    Appropriated for succeeding fiscal year ending June 30, 1955-         3,295,815
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955-----------          ----------------------------- 3,449,187
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project_---                                          594,000

                               20. STILLAGUAMISH RIVER, WASH.
   Location. Stillaguamish River is formed by the confluence of
its North and South Forks at Arlington, Wash., and flows westerly
a distance of 22 miles to Puget Sound, entering Port Susan through
Hat Slough and South Pass, and Skagit Bay through West Pass.
 (See U. S. Coast and Geodetic Survey Chart No. 6450, and U. S.
Geological Survey quadrangles Stanwood, Marysville, and Stilla-
guamish, Wash.)
   Existing project. The plan of improvement provides for works
to reduce bank erosion and channel changes on Stillaguamish River
between Arlington and the head of Hat Slough, a distance of 15
miles, and on Cook Slough, 3 miles long, as follows: Revetment at
26 places on the river and Cook Slough; a concrete control weir
275 feet long between steel sheet pile piers at the head of Cook
Slough to limit flow through the slough; and 2 cutoff channels,
each about 900 feet long, to eliminate sharp bends in Cook Slough.
   Tidal influence extends about 3 miles into the improved section.
Flood stages of 16 feet above low water at the Cook Slough weir
have been observed.
   The actual cost for new work was $220,594. The latest (1953)
approved estimate for annual cost of maintenance is $15,000.
   The project was authorized by the Flood Control Act approved
June 22, 1936 (H. Doc. 657, 71st Cong., 3d sess.). This document
contains the latest published map of the locality.
   Local cooperation. Fully complied with.
   Operations and results during fiscal year. Revetment repairs
were completed under contract in November 1953 at a cost of
$32,001.68. The cost of condition surveys was $2,111.67. Total
costs were $34,113.35, all for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1939. Progressive deterioration of brush mat revet-
ments necessitates annual repair at critical points. Other features
are in good condition. The costs to June 30, 1954, have been
                     FLOOD CONTROL-SEATTLE, WASH., DISTRICT                                                        1519
$134,594.98 from regular funds and $85,999 from emergency relief
funds, a total of $220,593.98, for new work; and $145,712.56 for
maintenance, a total of $366,306.54.
                                           Cost and financial summary

                                                        Fiscal year ending June 30                          Total to June
                                                                                                           30, 1954, includ-
                                                                                                           ing fiscal years
                                   1950               1951               1952       1953        1954        prior to 1950

New work:
   Appropriated .             ..............-                                                          -           $220,594
   Cost....-------    ------------------------------------------------                         -------------        220,594
Maintenance:
   Appropriated- ..-----          $15, 000-- ........                    $15, 000   $57, 000    $21, 266            173, 266
   Cost ...-----------------       17,442         $11,126                 11,334     20,265      34,113             145,713



         21. EAGLE GORGE RESERVOIR, GREEN RIVER, WASH.
   Location. Green River lies wholly in King County, Wash.
From its source at the crest of the Cascade Mountains in the vi-
cinity of Stampede Pass, the river flows westerly for 40 miles to
Auburn, thence northerly 32 miles to its mouth in Elliott Bay,
which forms the principal part of Seattle's salt-water harbor.
Eagle Gorge dam site is on the upper Green River, 6 miles south-
east of Kanaskat, Wash., and 1 mile downstream from the mouth
of North Fork. (See U. S. Geological Survey topographic sheet,
"Cedar Lake quadrangle, Wash.")
   Existing project. The project provides for a rockfill dam about
230 feet high, with a side channel spillway with a concrete weir
at elevation 1206 feet above mean sea level, to create a reservoir
with a capacity of 106,000 acre-feet. The length along the top
of the dam is approximately 700 feet; at the bottom, 100 feet.
The improvement is designed to control flooding in the Green
River Valley to prevent existing agricultural and urban flood dam-
age, and to make possible further expansion of the Seattle indus-
trial area.
   The estimate of cost for new work (1954) is $20,500,000, ex-
clusive of $2,000,000 to be contributed by local interests. The lat-
est approved estimate for average annual cost of maintenance and
operation for a 50-year project life, is $80,000.
   The existing project was authorized by the Flood Control Act
of May 17, 1950. (See H. Doc. 271, 81st Cong., 1st sess., which
contains the latest published map.)
   Local cooperation. Local interests are required to contribute
$2,000,000 in cash toward the cost of the project. The Washing-
ton State legislature, by acts approved 1949, 1951, and 1953, ap-
propriated $1,500,000 for participation in the Eagle Gorge proj-
ect, contingent upon contribution by King County, Wash., of
$500,000, authorization of the project by Congress, and appropri-
ations of funds therefor.
   The King County Board of County Commissioners, by resolu-
tion dated March 7, 1949, agreed to furnish $500,000 as their con-
tribution.
   Operations and results during fiscal year. Preliminary engi-
1520          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

neering studies, initiated in June 1952, were continued on loca-
tion of axis, type and layout of dam, construction materials investi-
gation, and relocations. Field work included surveys for railroad
relocation routes, bridge sites, topography for dam site and res-
ervoir area, exploration for construction materials, and founda-
tion explorations for the dam, bridge sites, and railway relocation.
Costs were $152,889.37, all for new work.
   Condition at end of fiscal year. No construction work has been
done. Preliminary engineering is about 65 percent complete.
Studies on type and layout of dam, construction materials inves-
tigations, and relocations are under way. Studies and design
memoranda have been completed on spillway design flood and hy-
droelectric power potential. The project as a whole is about 2
percent complete. The costs to June 30, 1954, have been $337,-
889.89, all for new work.
                                    Cost and financial summary

                                            Fiscal year ending June 30                  Total to June
                                                  I                                    30, 1954, includ-
                                                                                       ing fiscal years
                             1950        1951         1952        1953       1954       prior to 1950


New work:
   Appropriated .--    ------------------------------------      $216,200   $127,000           $343, 200
   Cost----                   ----        -----                   185,001    152,889            337,890


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954__                      $110
    Appropriated for succeeding fiscal year ending June 30, 1955             ,170,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955---------------------------------------------------            170,110
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project --------------------------------------
                                    _                                     19,986,800

                      22. TACOMA, PUYALLUP RIVER, WASH.

   Location. The Puyallup River has its source in the glaciers on
the western slopes of Mount Rainier in the State of Washington,
flows northwesterly 50 miles, and empties into Commencement Bay,
an arm of Puget Sound, at Tacoma. Wash. The work covered by
this project is on Puyallup River, within the city limits of Tacoma.
 (See U. S. Coast and Geodetic Survey Chart No. 6407.)
   Existing project. The plan of improvement provides for a
channel with a capacity of 50,000 second-feet between the East
Eleventh Street Bridge and the lower end of the intercounty im-
provement, a distance of about 2.2 miles, by straightening the
channel, building levees, revetting the channel and levees, and
making all necessary bridge changes. The 11th Street Bridge at
the lower end of the project is 0.75 mile above the mouth of the
Puyallup River. The diurnal tidal range at the mouth of the river
is 11.8 feet and the extreme range is 20 feet. The improvement
was planned in conjunction with Mud Mountain Dam and affords
protection against floods about 50 percent greater than the maxi-
mum discharge of record.
  The actual cost for new work to June 30, 1954, was $3,947,493.
The latest (1953) approved estimate for annual cost of mainte-
                       FLOOD CONTROL-SEATTLE, WASH., DISTRICT                                                          1521
nance is $40,000. The project was authorized by the Flood Con-
trol Act approved June 22, 1936. (See Senate committee print,
"Puyallup River, Wash.," 74th Cong., 2d sess.)
   Local cooperation. None required. Section 2 of the Flood Con-
trol Act approved June 28, 1938, applies.
   Operations and results during fiscal year. Revetment repairs
were completed by contract in July 1953 at a cost of $3,247.08,
and trees were cleared from the revetments by hired labor in June
1954 at a cost of $2,156.33. The cost of condition studies was
$1,198.81. Total costs were $6,602.22, all for maintenance.
   Condition at end of fiscal year. The existing project was com-
pleted in 1950. Reconstruction of six bridges, channel improve-
ment, and levee construction were completed in 1949. Placing of
additional riprap was completed in May 1950. In June 1954 all
features were in good condition, except for several minor revet-
ment sloughs.
   The costs to June 30, 1954, have been $3,947,492.81 for new
work and $8,785.34 for maintenance, a total of $3,956,278.15.
                                               Cost and financial summary

                                                            Fiscal year ending June 30                          Total to June
                                                                                                               30. 1954, includ-
                                                                                                               ing fiscal years
                                        1950            1951            1952          1953        1954           priorto 1950


New work:
   Appropriated        .-   - __       $359, 740 ------------ -.........-           -$11,022    ---       -        1 $3, 948,718
   Cost            -                    516, 049    -$3, 893              $1, 064         987         -               3, 947, 493
Maintenance:
    Appropriated       .-----      I------------ ------------            20, 000     -13,600       $2, 700                9,100
    Cost....-------------------------------------                         1, 203          980         6, 602              8, 785

  1 Funds in the amount of $1,225 have been transferred to "Minor Completion Items" account, and are
available for real estate costs.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_-------------       1 $1,225
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955       _                -                  _-_                __--_ 1--1,225

       23. MUD MOUNTAIN                               RESERVOIR, WHITE                          RIVER, WASH.
   Location. The White River rises on the northeastern slope of
Mount Rainier, in the State of Washington, and flows in a general
northwesterly direction for 57 miles to its confluence with the Puy-
allup River. The White River is the principal tributary of the
Puyallup River and enters the latter 10 miles above its mouth in
Puget Sound at Tacoma, Wash. The works covered by this proj-
ect are on White River near Mud Mountain, 6 miles southeast of
Enumclaw, Wash. (See U. S. Geological Survey topographic
sheet "Cedar Lake quadrangle, Washington.")
   Existing project. The plan of improvement provides for the
construction of a rockfill dam, 700 feet long at crest elevation and
rising 425 feet above bedrock. The dam is located 28 miles above
the confluence of the White and Puyallup Rivers and 38 miles
above the mouth of the Puyallup River. The reservoir has a stor-
age capacity of approximately 106,000-acre feet. Outlet works are
located in the right abutment and permit controlled discharge of
 1522           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

17,700 cubic feet per second through two concrete-lined tunnels,
with uncontrolled discharge over a spillway having a maximum
capacity of 139,000 cubic feet per second. The improvement af-
fords flood protection to the White and Puyallup River Valleys
and protects the Tacoma industrial district in conjunction with the
authorized project at that locality against floods about 50 percent
greater than the maximum discharge of record.
    The existing project was authorized by the Flood Control Act
approved June 22, 1936. (See Senate committee print, "Puyallup
River, Wash.," 74th Cong., 2d sess.)
    The actual cost for new work was $13,208,063.49. The latest
  (1953) approved estimate for annual cost of maintenance and op-
eration is $115,000.
    Local cooperation. None required. Section 2 of the Flood Con-
trol Act approved June 28, 1938, applies.
    Operationsand results during fiscal year. Operation and main-
tenance of the dam and appurtenances, gages, radio network,
roads, buildings, grounds, and utilities were continued; and drift
removal, fish haul, and miscellaneous studies were accomplished.
A total of 14,146 migratory fish was transported around the dam
in tank trucks. There were no severe floods during the year, the
highest pool level attained attributable to floods being elevation
1040 in December 1953, equivalent to a head of 145 feet and stor-
age of 9,682 acre-feet. In June 1954 the pool was raised to ele-
vation 1079 to facilitate debris-removal operations.
    Costs for the fiscal year were $102,586.32, of which $406.26 was
for new work accomplished the previous year, and $102,180.06 for
maintenance.
    Condition at end of fiscal year. The existing project was com-
pleted in June 1953.
    The costs to June 30, 1954, have been $13,182,063.49 from regu-
lar funds and $26,000 from Emergency Relief funds, a total of
$13,208,063.49, for new work; and $922,925.53 for maintenance,
a combined total of $14,130,989.02.

                                        Cost and financial summary

                                               Fiscal year ending June 30                      Total to June
                                                                                               30, 1954, includ-
                                                                                               ing fiscal years
                                 1950        1951           1952        1953        1954        prior to 1950


New work:
   Appropriated   --------      $400, 000   $191, 700 ---.-----......   -$5, 103    -$9, 473       $13, 208, 063
   Cost------- ---------         187,921     301, 259      $341, 933     190, 721        406       1 13, 208,063
Maintenance:
   Appropriated     ...-----      96,000      63,000         85,000       80,000     87, 500            924,380
   Cost__----- ------------       89,058      72, 236        80,687     2 73,295    102,180             922,926


12 Includes $914 for surplus military stock used
    Erroneously reported
                                                  without reimbursement from project funds.
                           infiscal year 1953 Annual Report as $73,716.
                    FLOOD CONTROL-SEATTLE, WASH., DISTRICT                                              1523
                   24. INACTIVE             FLOOD         CONTROL PROJECTS

                                                                        Cost to June 30, 1954
                                                         For last                                   Estimated
                  Name of project                     full report                                     amount
                                                      see annual                  Operation         required to
                                                      report for-   Construction     and             complete
                                                                                 maintenance

1. Columbia River Basin, Local Protection                1953                                          (8)
      Projects.
2. Skagit River, Wash.1----------------
                          _.      ___                     1938      -$8,320,000
3. Coeur d'Alene, Spokane River, Idaho
                                     3    .......         1942        $152, 872.16-_       ----          (2)
4. Spokane, Spokane River, Wash.         -       __      1939           2,944.45 _-------------          78,056
5. St. Maries, St. Joe River, Idaho-_ -  - - -           1942         357, 697.93 ..-----....---        (2)
6. Upper Puyallup River, Wash.__---- - -- - - -___-
                                                -    -    1938      -------- -      ----------- _       (4)
7. Raymond, Willapa River, Wash. 5 __                    1950          23, 742.60 -------------         330, 258
8. Priest Rapids Dam, Columbia River, Wash..             1953                                      371, 000, 000
9. Yakima, Yakima River, Wash ....-..      ____...       1948        381, 000.00----------             (2)
10. Snagging and clearing under authority of Sec.         1952        126, 032.25   -    -              (6)
      2 of the Flood Control Act approved Aug.
     28, 1937, as amended.
11. Emergency bank-protection works, under                1952       7 429, 039.98     50, 000.00       (6)
     authority of Sec. 14 of Public Law 526, 79th
     Congress.

   1 Awaiting local cooperation.
   S Completed and transferred to local interests for maintenance.
   3 Project indefinitely deferred because of unsatisfactory foundation conditions.
   4 The work has been completed as a Works Progress Administration project, at no cost to the Corps
of Engineers.
    5 Work deferred as not essential to the defense program. Completion of design for care of interior
drainage awaits formulation of plans by city of Raymond for sewage handling facilities.
    6 All work now contemplated has been completed.
    7 In addition, total funds contributed to date have been $29,637.65, all for new work.
    S The Flood Control Act approved May 17,1950, approved a general comprehensive plan for the Columbia
River Basin for flood control and other purposes as set forth in H. Doc. 531, 81st Cong., 2d sess., and author-
ized the sum of $75,000,000 to be appropriated for the partial accomplishment of certain projects. Of this
authorization, an amount not to exceed $15,000,000 was authorized for the construction of local flood pro-
tection works throughout the Columbia River Basin, subject to the conditions that all work undertaken
pursuant to this authority shall be economically justified prior to construction, and local cooperation
specified in the 1936 Flood Control Act, as amended, shall be required.

                             25. GENERAL INVESTIGATIONS

   Examinations and surveys. Funds in the amount of $26,350
were allotted during the fiscal year for general investigations.
Costs and expenditures for examinations and surveys accom-
plished during the year amounted to $19,878.01.
   The balance unexpended June 30, 1954, $3,243.06 together with
any new funds to be allotted for fiscal year 1955 will be applied as
needed during fiscal year 1955 to payment of expenses to be in-
curred under this heading.
   Collection and study of basic data. The work programmed for
the collection and study of basic data consists of storm studies,
sediment studies, hydrologic studies, flood investigations, and in-
ternational waters studies. Costs of these studies were $4,102.13,
leaving a balance of $1,997.87 which will be applied to studies
planned for fiscal year 1955. In general, a larger expenditure
was made for flood investigations than initially planned, and re-
duced expenditures were made for sediment studies and hydro-
logic studies, because of requirements for completing more ur-
gent civil works project studies.
1524         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

     26. INSPECTION OF COMPLETED FLOOD CONTROL WORKS
   Annual inspections are made of local flood protection projects,
and agencies responsible for their operation and maintenance are
advised of any needed repairs. During fiscal year 1954, inspec-
tions were made of works on the Nooksack, Skagit, Stillaguamish,
Puyallup, Elwha, Dungeness, Nisqually, Hoquiam, Chehalis, Hump-
tulips, Wynoochee, Satsop, Willapa, Entiat, Methow, Okanogan,
Wenatchee, Yakima, Naches, Pend Oreille, Spokane, St. Joe, Koo-
tenai, and Flathead Rivers, and on Lake Coeur d'Alene. The costs
were $2,871.03, all for maintenance.
   Costs to date have been $8,633.53, all for maintenance.
                                Cost and financial summary

                                      Fiscal year ending June 30                Total to June
                                                                                30, 1954, includ-
                                                                                ing fiscal years
                         1950        1951        1952        1953      1954      priorto 1950


Maintenance:
   Appropriated_           .$3,          500                  $3,600   $1,534             $8, 634
   Cost_         -                     1,270     $2,230        2,263    2,871              8, 634



  27. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
  Flood control emergencies--repairand flood fighting and rescue
work. (Section 210 of the 1950 Flood Control Act and supple-
mental authorizations.)
  Funds were allotted during fiscal year 1954 for work as follows:
  Kootenai Flats Area, District No. 4, Kootenai River, Idaho:
$28,800 (March 25, 1954).
  Kootenai River, Vicinity of Bonners Ferry, Idaho: $165,000
(June 3, 1954).
  Funds were revoked during fiscal year 1954 as follows:
Jeffries Levee Yakima River below Ellensburg, Wash_........................... $643.43
                                                                          .. ._-
                                                                          . ,7,120. 55
North Fork, Stillaguamish River near Oso, Wash -....-......................
Pollin Levee, along Kalispel Creek, Cusick, Wash____-__---------._---....
                                                                  .         --
                                                                           _482.     10

  Total allotments to June 30, 1954 amounted to $4,986,582.12
Federal Funds.
  Operations during the fiscal year included:
  Kootenai Flats Area, District No. 4, Kootenai River, Idaho:
Costs were $980.49 for preliminary engineering work on project
providing for repair to damaged levee.
  Kootenai River, Vicinity of Bonners Ferry, Idaho: Flood fight-
ing and rescue work were carried on during the spring flood in
1954. Costs were $92,959.52.
Yakima River at Yakima, Wash. final costs ________.____....
                                                         ....                $334. 22
                                                                      .__.____.
North Fork Stillaguamish River near Oso, Wash.:
    Adjustment of Federal costs -.........................
                                                        _ .    .  ...     -1, 379:45
    Increase in contributed funds_____------...-.. _____.___                1, 379. 45
    Emergency flood control at various locations ._.............
                                                           .....
                                                               ....
                                                                 ...........   760. 51
                    FLOOD CONTROL-SEATTLE, WASH., DISTRICT                                              1525
   Total costs during the fiscal year, all for maintenance, amounted
to $93,655.29 for Federal funds and $1,379.45 from contributed
funds, a total of $95,037.74.
  Total costs to June 30, 1954, all for maintenance, have been
$4,967,745.80, including $4,855,777.29 Federal funds and $111,-
968.51 contributed funds.
                                       Cost and financial summary
                                           UNITED STATES FUNDS


                                               Fiscal year ending June 30                        Total to June
                                                              _30,                                 1954, includ-
                                                                                                ing fiscal years
                                1950          1951        1952          1953         1954        priorto 19501

Maintenance:
    Appropriated....          --$88,910      $719, 814   $ 91, 705   2 -$13,030     $185, 554         $4, 986, 582
    Cost_   _     -           1,069,717       681,212     162,492         42,251      93,655           4,855,777

  I Inaddition $62,986 for maintenance was expended from contributed funds.
2 Amount of -$49, 723 reported in fiscal year 1953 Annual Report in anticipation of revocation of $21,693.
Actual revocation was $7,602.65.

                                       Cost and financial summary
                                           CONTRIBUTED FUNDS

                                               Fiscal year ending June 30                        Total to June
                                                                                                30, 1954, includ-
                                                                                                ing fiscal years
                                1950          1951         1952         1953         1954         prior to 1950


Maintenance:
    Contributed   .- -          $17, 350     $121, 745   -$40, 506     t $20, 500   -$7, 121            $111, 987
    Cost_ -         -------      10,394        74,020       13,155        13,000       1,379             111,987

  1 Amount of $12,000 reported in fiscal year 1953 Annual Report in anticipation of return of $8,500 to the
State of Washington.     Funds in the amount of $7,121 were returned to the State of Washington on January
14, 1954, from the project, Stillaguamish River near Oso Wash.


   Small flood control projects not specifically authorized by Con-
gress. (Section 212 of the 1950 Flood Control Act.)
   In addition to funds in the amount of $10,850 previously allotted,
funds were allotted during fiscal year 1954 as follows:
   Mission Creek at Cashmere, Wash., $425 (November 1, 1953).
   Hot Springs Creek, Hot Springs, Mont., $165 (November 1,
1953).
   Total allotments to June 30, 1954, have been $11,440.
   Operations during the fiscal year included:
   Mission Creek at Cashmere, Wash.: Project report studies were
revised, and report with favorable recommendations was sub-
mitted by the District Engineer March 1, 1954, and concurred in
by the Division Engineer on May 19, 1954. Local interests have
assured required local cooperation. Costs were $468.51.
   Costs during the fiscal year were $633.51, including $165 for
Hot Springs Creek, Mont., for work completed during the previous
fiscal year.
   Total costs to June 30, 1954, have been $11,440, all for new work.
1526   REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                       Cost and financial summary

                             Fiscal year ending June 30                 T(
                                                           15 1 1 99    p30,

                1950        1951       1952         1913         1954   pi
   IMPROVEMENT OF RIVERS AND HARBORS IN THE
       WALLA WALLA, WASHINGTON DISTRICT
   This district comprises southeastern Washington, exclusive of
the watershed of the Columbia River and tributaries above and in-
cluding the Yakima River, Wash.; all of Idaho, except the north-
ern part and a small southeastern portion; a portion of western
Wyoming; a small part of Northwestern Utah; part of northeast-
ern Nevada; and a part of eastern Oregon.
                                IMPROVEMENTS

              Navigation                          Flood control-Continued
                                    Page                                      Page
1. Snake River, Oregon, Wash-           7. Lucky Peak Reservoir, Boise
      ington, and Idaho------_     1527       River, Idaho-------------1535
2. McNary Lock and Dam,                 8. Grande Ronde Valley, Colum-
      Columbia River, Oregon ..    1529       bia River Basin, Oregon_...     1536
3. Inactive navigation projects   1531  9. Milton-Freewater, Walla Walla
                                              River, Oregon_________          1537
               Flood control            10. Mill Creek, Washington------ 1538
                                        11. Inactive flood control projects_ 1540
4. Columbia River Basin, Local         12. General investigations--          1540
      Flood protection projects___ 1532 13. Inspection of completed flood
5. Heise-Roberts    Area, Snake              control works---------_        -1540
      River, Idaho-------------1533 14. Flood control work under
6. Portneuf River and Marsh                  special authorization -____ 1541
      Creek,    Columbia     River
      Basin, Idaho____________     1534

            1. SNAKE RIVER, OREG., WASH., AND IDAHO
   Location. The Snake River, which is the largest tributary of
Columbia River, rises in Yellowstone National Park, in the west-
ern part of Wyoming, flows in a general westerly direction for
about 1,000 miles and empties into Columbia River near Pasco,
Wash., 324 miles from the Pacific Ocean. (See U. S. Geological
Survey maps of Oregon, Washington and Idaho.)
   Previous projects. No formal project for the improvement of
Snake River was adopted by Congress prior to the act of June
13, 1902. Subsequent projects were adopted by River and Harbor
Acts of June 13, 1902, June 25, 1910 and August 30, 1935. For
further details see page 1991 of Annual Report for 1915, page
1849 of Annual Report for 1938 and page 2676 of Annual Report
for 1948.
   Existing project. This provides for the construction of such
dams as are necessary and open-channel improvement for pur-
poses of providing slack water navigation and irrigation between
the mouth of Snake River and Lewiston, Idaho. The pool formed
by McNary Dam will provide slack water from the mouth of
Snake River to mile 9.7. For maintenance purposes the project
also provides for any necessary work on the River between Lewis-
ton and Johnson's Bar, Idaho, as authorized under previous proj-
ects. No channel dimensions are specified above Lewiston. A
                                                                      1527
 1528          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

system of four dams between the mouth of Snake River and
Lewiston has been approved. The estimated total cost, revised
in 1954 including the installation of three power units at each
dam is as follows:
      Dam                                                            .
             1, Ice Harbor, river mile 9.7-..------------...----...--...                 ----- $142, 000, 000
      Dam    2, Lower Monumental, river mile 44.7..-.........------------------                 123, 000, 000
      Dam                                                           ....... .....--------- 139, 000, 000
             3, Little Goose, river mile 72.2----.. ------.... ----......
      Dam    4, Lower Granite, river mile 113.1. . ......................---------------------  116,000,000
         Total ..........---------------...
                             .................---------------------------.                    520, 000, 000
  The existing project was authorized by the River and Harbor
Act approved March 2, 1945. (See H. Doc. 704, 75th Cong., 3d
Sess.)
    Local cooperation. No conditions were imposed by law.
    Terminal facilities. From the mouth of Snake River to Riparia,
67 miles, there-are no wharves or warehouses on the river banks.
From Riparia to Lewiston, Idaho, 73 miles, there are no wharves,
but there are public and privately owned warehouses and grain
elevators located at Penawawa, mile 91.5, Lewiston, mile 140,
Asotin. mile 146 and between Asotin and 11 miles above. Just
above Lewiston, mile 140.5, there is a privately owned 40 by 60
foot wharf. On the left bank between Riparia and Lewiston there
are several wheat warehouses formerly used for storage of wheat
to be transferred to the railroad on the right bank.
    Operationsand results during fiscal year. Limited preliminary
design and cost estimate studies of project features for Ice Harbor
as presented in Design Memorandum No. 1, General Plan and De-
tailed Cost Estimate, were continued in accordance with recom-
mendations contained in OCE approval of this report, dated 25
March 1953, and supplemental authority granted 16 January 1953.
This work is approximately 20 percent complete and will be in-
corporated in revisions to the Design Memorandum when complete.
   Costs for the fiscal year were $9,778 for new work.
   Condition at end of fiscal year. Construction has not been
initiated at any of the four dam sites. Engineering and design of
Ice Harbor Dam is approximately 18 percent complete. Hydraulic
design and model studies have been initiated and the preliminary
stage of an architect engineer powerhouse design contract has
been completed. Plans and Specifications for the first step coffer-
dam are 75 percent complete. Engineering and design studies
for dams 2, 3, and 4 are in a preliminary stage only. Preliminary
plans on real estate, flowage, and relocations covering the four
dams have been completed and submitted to higher authority.
   Total costs under the existing project have been as follows:

                           Description of work                               New work         Maintenance

Site Selection, lands and damages (all dams)--                                   $587, 500
Ice Harbor Dam (dam 1)                                     --                     855, 837
Lower Monumental Dam (dam 2)                                    -   _43,               166             _-
Maintenance of channel between Lewiston and Johnson's Bar                                            $9, 825
      Total costs ..........................
                                    _.-             _                           1, 486, 503           9,825
             FLOOD CONTROL-WALLA WALLA, WASH., DISTRICT                                                 1529
                                    Cost and financialsummary

                                           Fiscal year ending June 30                           Total to June
                                                                                                30, 1954, includ-
                                                                                                ing fiscal years
                             1950        1951           1952            1953          1954      prior to 1950      2

New work:
   Appropriated ...-...     $225, 000    $87,611      -$240, 438       $140,000       $50,000        $1,971,936
   Cost----------------      109,792      34,895              93        131,152         9,778         1,921,266
Maintenance:
   Appropriated ..
   Cost-    - -4,602
                       _       6, 000      5, 000        -5, 000 ...             ------------            214,947
                                                235            336             433                       214,553

I Includes $434,763 for new work and $204,728 for maintenance on previous projects.
2 In addition $85,000 for new work was expended on previous projects from contributed funds.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-_---------_ -     $49,070
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955_                 -------------        -----------        49,070
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project_                                         518,028,064

           2. McNARY       LOCK AND DAM, COLUMBIA RIVER, OREG.
   Location. The site of this project is on the Columbia River, 292
miles above the mouth, near Umatilla, Oreg., and 3 miles above the
mouth of the Umatilla River.
   Existing project. This project includes a dam, power plant,
navigation lock, and appurtenant facilities for purposes of naviga-
tion, power development, and incidental irrigation. The proposed
improvement provides principally for the improvement of naviga-
tion, creation of pool extending approximately 64 miles upstream
to a point about 27 miles above Pasco, Wash. The dam, which will
raise the normal water surface approximately 85 feet to elevation
340 mean sea level, will be approximately 7,600 feet long and will
consist of an earth dam at the Oregon (south) abutment, a power-
house, a spillway dam, a navigation lock, and an earth dam at the
Washington (north) abutment. Suitable facilities for migrating
fish, including fish ladders, will be provided.
   The powerhouse installation will comprise 14 units of 70,000
kilowatts each, making a total installed capacity of 980,000 kilo-
watts.
   The spillway dam will be 1,310 feet long and will be located
in the north channel of the river. The overflow crest at 291 feet
above sea level will be surmounted by 22 spillway gates canablo of
releasing the design flood of 2,200,000 cubic feet per second. The
deck will be at elevation 361 and will provide a service roadway
and tracks for the operation of two gantry cranes.
   The navigation lock will be a single type and will operate at
all flows less than 800,000 cubic feet per second.
   The pool created by the spillway dam will provide navigable
channel with depths of 12 feet and over, between McNary Dam and
the confluence of the Yakima River, a distance of approximately
48 miles. A controlling depth of 9 feet will be provided on Snake
River from its mouth to a point approximately 10.2 miles above.
  All structures will be founded on a massive basalt flow that
reaches a maximum thickness of 130 feet and directly overlies a
1530          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

sedimentary interbed. The principal data concerning the naviga-
tion lock and spillway dam are shown in the following table:

                                         Navigation lock
Type.         -----------............-----------------------                      Single lift.
Dimensions:
      Net clear width of chamber................___            _____________ 86 feet.
      Net clear length------------------
                              ...................................-----            675 feet.
Lift (vertical):
      At extreme low water and normal pool-.....---.._-92 feet.
      At mean annual flow (190,000 cubic feet per
        second) -------............------..-----.........................         84.4 feet.
      At average maximum flow (550,000 cubic feet
        per second) .... -------------------------                                72.3 feet.
Depth over miter sill at adopted low water (43,000
   cubic feet per second)-..                           ------------...-..      _   12 feet.
Depth over upper sill at normal pool (elevation 340) 20 feet.
Character of foundation......._...........................--------------------    Basalt flow.
                                                         Spillway dam
Overall length of spillway dam section---.-.-.-.-...                              1,310 feet.
Type of construction-----------------------...                                    Concrete gravity.
Elevation spillway crest--..__...-......----....-...         ..                   291 feet above mean sea level.
Elevation deck______________......................        ........... 361 feet above mean sea level.
Height, maximum (foundation to deck)_ -........                                   158 feet.
                                                                             ___......
Type of control---....            --..............
                                                __
                                                 __.                 ....         Fixed wheel segmental lift gates.
Number of gates............                 ...........-------------------------- 22.
Size of gates-----.......    ---------...
                                .. ..                                             50 by 53 feet.
                                                       ---------------...............
Stilling basin type..._____......-....      ..............              __        Concrete apron with baffles.
Normal pool elevation-...                 --.-.-  __
                                             __......_           --...            340 feet above mean sea level.
Maximum pool elevation--            _--.-.-----...............                    356.5 feet above mean sea level.
Maximum spillway capacity at normal pool ele-
  vation ....--............................------------------------------....     1,480,000 cubic feet per second.
Maximum spillway capacity at maximum pool ele-
   vation ..              ................................... .....               2,200,000 cubic feet per second.

  The estimated cost of the dam, navigation lock, 14-power unit
generating installation, flshways, and attendant buildings and
grounds, revised in 1954 is $287,300,000.
  The existing project was authorized by the River and Harbor
Act approved March 2, 1945. (See H. Doc. 704, 75th Cong., 3d
sess.)
   Operations and results during fiscal year.                         New work: Placing
of concrete in powerhouse structure, nonoverflow dam, spillway
dam and navigation lock upstream miter sill is complete except
the embedding of turbine parts. Installation of second pumping
units in fishway pumphouse was completed and work is progress-
ing on the third unit.
   Installation of turbines, generators, electrical eauipment, fish-
way pump, piping, and fish collection system control equipment is
in progress by several contractors.
   Contract work in connection with Kennewick levees and pump-
ing plants was completed.
  Maintenance: The pool was raised to minimum operating level
of elevation 335 on November 4, 1953. The project was placed
on a permanent operation basis on December 1, 1953, and has been
in continuous operation throughout the balance of the fiscal year.
Counting of fish, using the two ladders at the dam, was initiated
in March 1954. The first four power units were placed in com-
             FLOOD CONTROL--WALLA WALLA, WASH., DISTRICT                                                       1531
mercial operation on the following dates: November 6, 1953, De-
cember 26, 1953, April 10, 1954, and June 16, 1954.
   Total costs during the fiscal year were $41,157,966 for new work
and $468,146 for maintenance.
   Condition at end of fiscal year. Construction of existing proj-
ect which was started May 5, 1947, is now approximately 86 per-
cent complete.
  Work on the Washington shore including the navigation lock is
99 percent complete. Fish facilities are complete except for in-
stallation of operating and control equipment. The following
structures have been completed: north and south embankments,
spillway structure, powerhouse and intake structure and fishway
pumphouse building. The following relocations have been com-
pleted: 80.8 miles of railroad, 42.5 miles of State highway and
County roads, and 57 miles of power and communication lines.
Construction of levees is complete.
   The project was placed on a permanent operation basis on De-
cember 1, 1953. The pool was raised to elevation 340 on Decem-
ber 6, 1953. The first four power units were in commercial oper-
ation June 16, 1954.
   Total costs have been $246,351,186 for new work and $468,146
for maintenance.
                                       Cost and financial summary

                                                   Fiscal year ending June 30                           Total to June
                                                                                                       30, 1954, includ-
                                                                                                       ing fiscal years
                                1950             1951            1952         1953          1954        priorto 1950


New work:
   Appropriated-_ __-$35, 000,000 $39,610,000 $42, 900,000 $62, 604,000                 1$26,350,000     1$244,039,000
   Cost -     -       - 36,791,573 40,305, 923 55,o813,617 50,696,511                     41,157,966       246,351,186
Maintenance:
   Appropriated .....    .     .    ..                    .  .      .                        479,000           479,000
   Cost-.. _            . - ---------- ---------
                               -..........                                                   468,146           468,146

1 Excludes $4,573,000 allotted on a loan basis, and includes $1,924,000 revoked for Bureau of the Budget
Reserve.
  2 Includes repayment of $3,700,000 advanced funds.            Balance of $873,000 to be repaid from fiscal year 1956
funds.

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_      -                                             $3,636
    Appropriated for succeeding fiscal year ending June 30, 1955 _ _                                   2 24,000,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955______________________________ -______                                               24,003,636
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project   _____________________________                                       19,261,000

                       3. INACTIVE NAVIGATION PROJECTS

                                                                            Cost to June 30, 1954
                                                               For last                -                I Estimated
                Name of project                              full report                                   amount
                                                             seeannual i                 Operation       required to
                                                             report for-- Construction      and           complete
                                                                                         maintenance

Umatilla Harbor.       .......----------------------------     1952----------------------------               $575,000

1No funds appropriated    for work.
1532             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

       4. COLUMBIA RIVER BASIN, LOCAL FLOOD PROTECTION
                           PROJECTS
   Location. The improvements included in this project are lo-
cated along the Columbia River and its tributaries.
   Existing project. The Flood Control Act approved May 17,
1950, approved a general comprehensive plan for the Columbia
River basin for flood control and other purposes as set forth in
House Document 531, 81st Congress, 2d session, and authorized
the sum of $75,000,000 to be appropriated for the partial accom-
plishment of certain projects. Of this authorization, an amount
not to exceed $15,000,000 was authorized for the construction of
local flood protection works throughout the Columbia River Basin,
subject to the conditions that all work undertaken pursuant to this
authority shall be economically justified prior to construction, and
local cooperation specified in the 1936 Flood Control Act, as
amended, shall- be required. Protection to the following areas,
located in the Walla Walla District, is being considered under this
latter authorization:

                                                  Project                                                            Federal cost

Grande Ronde Valley, Oreg. -                                                                                              $4, 630, 000
Portneuf River and Marsh Creek, Idaho                                                                                      1, 193, 000
Umatilla River, Oregon ___               --
                                    ___-____--___________               ------
                                                                     _____                  -----
                                                                                        ________________                    1, 105, 000
Touchet River, Wash_                                                                                                          492, 000
Heise-Roberts Extension, Idaho                                                                                             4, 623, 000
Boise Valley, Idaho ..__----------------------------                                                                       5, 541, 000
Lower Walla Walla River, Wash                                                                                                 372, 000
Blackfoot Area, Snake River, Idaho _           .        .            . ________
                                                            .__________         ..  ___ __                                     74, 000
Blackfoot River, Idaho _________-...
                                ...          __........           ___________________
                                                                            .....                                             451, 000
Shelley Area, Idaho......------------------------------------------------------------                                          51, 000
Little Wood River, Idaho__ .................                    .
                                                      __________.............. ....        .                                  186, 000
Kendrick, Potlatch River, Idaho-........................                    ....-.-----....                                     76, 000
Mill Creek, Wash ....       .. .. . ..-----------------------.-------------------------- -                                    113, 000
Payette Valley, Idaho              ...-----------------------------------                  -------------- ----              1, 103, 000
Teton River, Idaho-----      ------------------------------------------------------                                           687, 000
Malheur River, Oregon             --------------------------------------------------------                                    432, 000
South Fork, Clearwater River, Idaho_____ ________ __                      .____________  . . . .                              102, 000
Palouse River, Wash     ----------------------------------------------------------                                            515, 000
Mud Lake Area, Idaho ....                                                  -------------                                      676, 000
Weiser River, Idaho            ----------------------------------------------------------                                     788, 000
Whitebird Creek, Idaho_ ._____               ._____            - ------------------------
                                                                   _.--
                                                          ._____..__                                         __                 64, 000
Camas Creek, Idaho                                                                                                             688, 000
                                                                ...............----------------------------------------------------.....

  1 The economic justification of work proposed for this area has been established in compliance with con-
ditions set forth in the Flood Control Act of 1950. See individual report for details of this project.


   Local cooperation. Section 3 of the Flood Control Act approved
June 22, 1936, as amended, applies to all the flood control projects.
   Operations and results during fiscal year. Plans and specifica-
tions were initiated during the fiscal year on the Portneuf River
and Marsh Creek Location, Idaho. Design memorandum was ini-
tiated during the fiscal year on the Grande Ronde Valley, Oreg.
Justification Reports were initiated on the following locations,
Teton River, Idaho, Weiser River, Idaho, Mill Creek, Wash., and
Lower Walla Walla River, Wash. Total costs for the fiscal year
were $37,352.
   Conditions at end of fiscal year. Plans and specifications have
been initiated on the Portneuf River and Marsh Creek Location,
            FLOOD CONTROL--WALLA                   WALLA, WASH., DISTRICT                      1533
Idaho. Design memorandum has been initiated on the Grande
Ronde Valley, Oreg. Justification reports are in progress on the
following projects, Teton River, Idaho, Weiser River, Idaho,
Mill Creek, Wash., and Lower Walla Walla River, Wash. Total
costs have been $37,352.

                                 Cost and financial summary

                                         Fiscal year ending June 30                    Total to June
                                                                                       30, 1954, includ-
                                                                                       ing fiscal years
                          1950         1951           1952            1953   1954       priorto 1950


New work:
   Appropriated   ------------------------------------------------           $60,000            $60,000
   Cost----------------           --------    ---------------------           37,352             37,352


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954__                $21,973
    Appropriated for succeeding fiscal year ending June 30, 1955 _ - -      80,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955                                  - -                   101,973
Estimated additional amount needed to be appropriated for completion            b
      of existing project                                              $-------------------

           5. HEISE-ROBERTS              AREA, SNAKE                  RIVER, IDAHO
   Location. This project is located on both banks of the Snake
River between the towns of Heise and Roberts in eastern portion
of Idaho, approximately 20 miles northeast of Idaho Falls, Idaho.
   Existing project. This provides for channel improvement of
the Snake River at selected points between Heise and Roberts,
Idaho, by channel clearing, alinement changes, levee construction
and bank protection works. This work is a part of a multipurpose
project on the Snake River, Idaho, which also includes the con-
struction of the Palisades Dam by the Bureau of Reclamation for
operation in the combined interest of flood control, irrigation, and
power.
   The existing project was authorized by Flood Control Act ap-
proved December 22, 1944 (H. Doc. 452, 77th Cong., 1st sess.).
The estimate of cost revised in 1953 is $1,575,905 for construction.
The cost of lands and damages is to be paid by local interests.
   Local cooperation. Assurances of local cooperation have been
furnished.
   Operations and results during fiscal year. Special report on
project adequacy is approximately 98 percent complete. Construc-
tion on emergency controls on outlets through flood walls were
completed.
   Total costs for the fiscal year were $4,821.
   Conditions at end of fiscal year. Construction of the project as
described in Definite Project Report entitled "Heise-Roberts and
Weiser Areas, Snake River, Idaho" January 29, 1948, is 100 per-
cent complete. Construction on emergency controls on outlets
through flood walls, being done by hired labor, was completed.
   Total costs have been $1,575,481.
1534             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                               Cost and financial summary

                                                              Fiscal year ending June 30                      Total to June
                                                                                                             30, 1954, includ-
                                                                                                             ing fiscal years
                                     1950                   1951         1952        1953         1954        priorto 1950

New works:
   Appropriated -__                $340,300               $     9,000    $78,000    -$1,095    ------------        $1,575, 905
   Cost----------------              207, 792               177,416       54,468      32,384       $4, 821          1,575,481

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_--------------      $424
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955--------       -------------------------------------------           424

   6. PORTNEUF RIVER AND MARSH CREEK, COLUMBIA RIVER
                       BASIN, IDAHO
   Location. This project is located at three areas along the Port-
neuf River and along the entire length of its main tributary, Marsh
Creek, all in Southeastern Idaho.
   Existing project. The plan of improvement provides for chan-
nel straightening and improvement, removal of obstructions and
construction of new levees and revetments or improvements to
existing levees in the Blackrock area, in and adjacent to the city
of Pocatello, Idaho, and in the vicinity of Inkom, Idaho, all of the
Portneuf River, and channel improvement along the entire length
of Marsh Creek.
   The existing project was authorized under the Columbia River
Basin Plan by the Flood Control Act approved May 17, 1950, (Pub-
lic Law 516, 81st Cong., 2 sess.) subject to economic justification.
Justification was provided by a survey report completed in fiscal
year 1953. The estimated cost revised in 1954 is $1,193,000 for
construction.
   Local cooperation. Section 3 of the Flood Control Act approved
June 22, 1936, as amended, applies.
   Operations and results during fiscal year. Plans and specifica-
tions were initiated during the fiscal year. Total costs during the
fiscal year were $17,766.
   Condition at end of fiscal year. Plans and specifications have
been initiated. Total costs have been $17,766.
                                               Cost and financial summary

                                                              Fiscal year ending June 30                      Total to June
                                                                __    _ _ _ _0,                                 1954, includ-
                                                                                                             ing fiscal years
                                     1950                   1951         1952        1953         1954        prior to 1950

New works:
   Appropriated...------------------------------------ ----------- $20, 000                                           $20, 000
   Cost-------        ------------------------------------------------                             17,766              17, 766


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_------------                                              $1,559
    Appropriated for succeeding fiscal year ending June 30, 1955------__                                            25,000
    Unobligated balances available for succeeding fiscal year ending June
       30, 1955---------------  __                                 --                                               26,559
     Estimated additional amount needed to be appropriated for comple-
        tion of existing project_                                                                               1, 148,000
          FLOOD CONTROL-WALLA WALLA, WASH., DISTRICT            1535
        7. LUCKY PEAK RESERVOIR, BOISE RIVER, IDAHO
    Location. On the Boise River in southwestern Idaho approxi-
mately 9 miles southeast of the city of Boise, and approximately
  12 miles downstream from Arrowrock Reservoir.
    Existing project. The plan of improvement provides for con-
struction of a rolled earth-fill dam approximately 250 feet high
and 1,700 feet long at the crest, with a reservoir providing a total
storage, at normal pool level, of 306,000 acre-feet. The spillway
will be located on the left abutment and will be designed to pass
  123,000 cubic feet per second at maximum pool. Its discharge will
be controlled by automatically operated tainter gates. The outlet
works are to be located on the left abutment and consists of a
tunnel controlled by Howell-Bunger valves.
    The plan contemplates the joint use of storage in Lucky Peak,
Arrowrock, and Anderson Ranch Reservoirs. Operations of the
dam as a flood control facility will be by the Department of the
Army under the direction of the Secretary of the Army with the
understanding that complete or partial joint use of the storage
in the three reservoirs may be undertaken at such time as may be
agreed upon by the Secretary of the Army, Secretary of the In-
terior, and local interests concerned with flood control and use of
irrigation water. The existing project was authorized by the
Flood Control Act approved July 24, 1946. The latest (1954)
approved estimate project cost is $19,400,000.
    Local cooperation. Section 2 of the Flood Control Act approved
June 28, 1938, applies.
    Operationsand results during fiscal year. The contract for the
completion of the diversion channel, cofferdams, main dam, and
excavation of the spillway was completed in December 1953. The
contract for the construction of the manifold, penstock, intake
tower, bridge, spillway, and completion of the intake tower has
advanced from 14 percent to 65 percent complete. Delivery of
slide gates and materials to be furnished under contract for hoist-
ing machinery and appurtenances was initiated in June. Con-
struction work on relocation of Highway 21 was completed, except
for final surfacing, and opened to traffic. Mores Creek Bridge was
completed and opened to traffic. Relocation of Arrowrock County
Roads was completed and opened to traffic. A contract for the
relocation of Robie Creek Road was awarded and completed during
the fiscal year. The major work to be accomplished by the Bureau
of Reclamation has been accomplished. Total costs for the fiscal
year were $3,670,796.
    Conditions at end of fiscal year. Construction of the existing
project, which was initiated in November 1949, is now 83 percent
complete. The following construction work at the project has
been completed: Control and diversion tunnel, March 1951; Lower
portion of intake tower, July 1952; Diversion channel, cofferdams,
main dam, and excavation of spillway, December 1953; Relocated
Highway 21 was opened to traffic in October; all work with excep-
tion of final surfacing and final painting on Mores Creek Bridge
was completed; Arrowrock Road relocation and Robie Creek Roads
were completed. The contract for the completion of outlet works,
     Sig 49-1535-1566
 1536                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

intake tower, penstock, manifold, intake bridge, and spillway ad-
vanced from 14 percent to 65 percent complete. Status of supply
contracts for furnishing gates and appurtenances are as follows:
Emergency gates, delivery complete, slide gate and control equip-
ment, delivery initiated in June; hoisting machinery for emergency
gate, delivery of first items made in June. Work being accom-
plished by Bureau of Reclamation at Arrowrock Dam 90 percent
complete. Total cost has been $16,035,586.
                                                   Cost and financial summary

                                                               Fiscal year ending June 30                                       Total to June
                                                                                                                               30, 1954, includ-
                                                                                                                                ing fiscal years
                                           1950              1951              1952              1953              1954          prior to 1950

New work:
   Appropriated-.......  $3,000,000                     $2, 400,000       $3,800,000        $4,975,000 1$1, 500,000                 s $16,455,000
   Cost,---------------,    099375                       3 499,736         2,784,969         4,482,800   3,670,796                     16,035,586

1 Includes $152,853 repayment of funds advanced on a loan basis and $347,147 revoked for Bureau of the
Budget reserve.
5Excludes $500,000 allotted on a loan basis.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954----......-------------                                                            $314, 553
    Appropriated for succeeding fiscal year ending June 30, 1955......-....... 1,750,000
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955------.......................---------------................................................-----------.................     2,064, 553
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project................................--------------------------------............................................ 1,195,000
  8. GRANDE RONDE VALLEY, COLUMBIA RIVER BASIN,                                                                                      OREG.
   Location. This project is located along Grande Ronde River;
Catherine, Willow and Ladd Creeks; and lower reaches of several
small tributaries, all in the eastern part of Oregon.
   Existing project. This project provides for channel improve-
ment and construction of levees on both banks of Grande Ronde
River between LaGrande and Elgin; on Catherine Creek through
Union downstream, including the old channel of Grande Ronde
River; on Willow and Ladd Creeks; and on the lower reaches of
several small tributaries.
   The existing project was authorized under the Columbia River
Basin Plan by the Flood Control Act approved May 17, 1950 (Pub-
lic Law 516, 81st Congress, 2d Sess.) subject to economic justifica-
tion. The economic justification of this work has recently been
established. The estimated cost revised in 1954 is $4,630,000 for
construction. The costs of rights-of-way and highway and utility
revisions will be paid by local interests.
   Local cooperation. Section 3 of the Flood Control Act approved
June 22, 1936, as amended, applies. In addition to the usual re-
quirements local interests are required to accomplish, at their own
expense, any highway and utility revision.
   Operations and results during fiscal year. Design memoran-
dum was initiated during the fiscal year. Total costs during the
fiscal year were $967.
   Condition at end of fiscal year. Design memorandum has been
initiated. Total costs have been $967.
             FLOOD CONTROL-WALLA WALLA, WASH., DISTRICT                                         1537
                                    Cost and financial summary

                                           Fiscal year ending June 30                    Total to June
                                                                                        30, 1954, includ-
                                                                                        ing fiscal years
                             1950        1951         1952        1953        1954       priorto 1950

New work:
   Appropriated_
     Apopria         ----     .
                 - ---------------------------------------------
   Cost------------------- ----------------------------------------------
                                                                          _   $10
                                                                              $10,000
                                                                                  967
                                                                                                 $10,000
                                                                                                     967

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954__                   $9,033
    Appropriated for succeeding fiscal year ending June 30, 1955------        20,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955--------_    --------------            ----------------    29,033
    Estimated additional amount needed to be appropriated for comple-
      tion of existing project --------        ------------------------   $4,600,000

      9. MILTON-FREEWATER,                      WALLA WALLA RIVER, OREG.
   Location. On both banks of the Walla Walla River between Joe
West and McCoy Bridges in the vicinity of Freewater and Milton,
Oreg., 8 miles south of Walla Walla, Wash.
   Existing project. The plan of improvement provides for chan-
nel rectification and improvement of approximately 7 miles of
Walla Walla River in the vicinity of the towns of Milton and
Freewater, Oreg. The lower 5.3 miles, between McCoy Bridge and
the Milton power plant, will be protected by levees with necessary
revetment and channel improvement designed for a flood of 18,600
cubic feet per second. The upper 1.7 miles, extending from the
Milton power plant upstream to Joe West Bridge, will be improved
by some channel clearing and rectification. The existing project
was authorized by the Flood Control Act approved August 18,
1941, House Document 719, Seventy-sixth Congress, Third Session.
The latest (1953) approved estimate of cost is $890,000 for con-
struction, and $59,600 for lands and damages to be paid by local
interests. The project will provide protection for the towns of
Milton and Freewater and for other lower-lying areas in the Walla
Walla River Valley from Milton, Oreg., to McCoy bridge against
floods with a discharge about two times as great as that of the
maximum flood of record, which occurred in 1931.
   Local cooperation. Assurances of local cooperation have been
furnished. Local interests have contributed $6,300 to cover the
cost of their portion of diversion structures.
   Operations and results during fiscal year. No work was ac-
complished during the fiscal year.
   Total costs for the fiscal year were $14, all for new work.
   Conditions at end of fiscal year. Construction of levee and
channel improvement has been completed throughout sections 1 to
6 inclusive. This includes all levees and revetments on the project.
   Remaining work consists of channel improvement form the up-
stream limit of the project to station 108. This work is indefi-
nitely postponed pending reopening by sponsors.
1538         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Total costs have been $884,704 for new work. In addition costs
for new work from contributed funds amounted to $6,300.
                                   Cost and financial summary

                                           Fiscal year ending June 30                     Total to June
                                                                                         30, 1954, includ-
                                                                                         ing fiscal years
                            1950         1951        1952       1953          1954        prior to 19501

New work:
   Appropriated........     640,000- _.                        -$125, 000 ------------          $890,000
   Cost-----------------    388,853     $273,981    $123,106          148         $14            884, 704

1In addition $6,300 for new work was expended from contributed funds.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-_-- --------        $3,896
    Unobligated balances available for succeeding fiscal year ending June 30,
      1955----------------------------------------------------                 3,896

                               10. MILL CREEK, WASH.
   Location. Near Walla Walla, Wash., on Mill Creek, a tributary
of the Walla Walla River.
  Existing project. The plan of improvement provides for con-
struction of flood control works consisting of a storage dam, out-
let works, diversion works, division structures and improvement
of a stretch of Mill Creek Channel, including the reconstruction of
the Otis and Merriam Street Bridges across Mill Creek in the city
of Walla Walla, Wash.
   The storage dam, which forms a reservoir of 6,000 acre-feet
capacity, is a rolled earth fill structure 145 feet high, 3,200 feet
long at the crest, and 800 feet wide at the base. Flood water is
diverted storage by means of diversion work on Mill Creek con-
sisting of a rolled earth fill dam 1,700 feet long and 20 feet high,
with a concrete spillway section and headworks at the left abut-
ment, and a concrete-lined canal leading from the headworks to
the storage reservoir. Stored water is subsequently released
through outlet works consisting of a steel-lined concrete conduit
through the base of the storage dam and a canal 5,900 feet in
length from the dam to Mill Creek. The normal flow of water past
the diversion works is apportioned, by means of two concrete divi-
sion structures, to the three delta streams, Yellowhawk, Garrison,
and Mill Creek. The project will control the entire Mill Creek
drainage area of 85 square miles and care for a flood of 11.400
second-feet. The existing project was authorized by the Flood
Control Act approved June 28, 1938. The Flood Control Act ap-
proved August 18, 1941, modified the project in accordance with
the recommendations of the Chief of Engineers in House Docu-
               FLOOD CONTROL-WALLA WALLA, WASH., DISTRICT                                            1539
ment 719, Seventy-sixth Congress, third session. Cost of the com-
pleted project was $2,162,155.
   Local cooperation. For the project, except for Mill Creek
through the city of Walla Walla, section 2 of the Flood Control
Act approved June 28, 1938, applies. For the section of Mill Creek
through the city of Walla Walla, Wash., local interests will provide
without cost to the United States all lands, easements, and rights-
of-way necessary for construction of the project, and hold and
save the United States free from claims for damages resulting
from improvement. Assurances of compliance with these require-
ments received from local interests were approved by the Division
Engineer, March 2, 1948. Local interests have contributed
$80,000 toward the cost of channel improvement through the city
of Walla Walla.
   Operations and results during fiscal year. Maintenance: Piez-
ometer and seepage studies were conducted. Ordinary maintenance
and repairs were continued. Reservoir regulation was routine ex-
cept for diversion for bed sealing. Stream flow was normal. Res-
ervoir regulation manual was resubmitted for approval in March
1954.
  Total cost for the fiscal year was $17,459, all for maintenance.
   Conditions at end of fiscal year. Construction of the dam and
appurtenant works was completed in 1942. An auxiliary outlet
canal from the dam to Russell Creek and construction of additional
drainage at the toe of the dam were completed in 1944. Paving
of the channel through City of Walla Walla was completed in 1948.
Compaction of reservoir area, installation of seepage relief wells,
grouting of interior drains, and installation of a new sluice gate
were completed in 1949 and 1950. Diversion of water for bed seal-
ing operations carried out during 1952.
   Total cost has been $2,559,879, of which $2,162,155 was for new
work and $397,724 for maintenance. In addition, costs for new
work from contributed funds amounted to $80,000.

                                     Cost and financial summary

                                            Fiscal year ending June 30                       Total'to June
                                                                                             30, 1954, includ-
                                                                                             ingrfiscalyears
                              1950         1951        1952        1953           1954        priorto 1950 1

New work:
   Appropriated ____         $ 58,800    -$95, 439                                                $2, 162, 155
   Cost----.-_____-            36,433       4,011         .        .          _ _2,162,155
Maintenance:
   Appropriated   --------
                    _          18,000      -7, 000    $15, 000     $17, 200      $13,500              399,600
   Cost---.-------------      196,696      23,245      14,899       17,290        17,459              397,724

1 In addition $80,000 was expended for new work from contributed funds.
1540               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                          11. INACTIVE FLOOD CONTROL PROJECTS

                                                                                        Cost to June 30, 1954
                                                                      For last                                    Estimated
                                                                    full report                                     amount
                      Name of project                               see annual                     Operation      required to
                                                                    report for-      Construction     and          complete
                                                                                                  maintenance

Jackson Hole, Wyoming-----------------------                              1953     ---------------------------     $2, 000, 000
Pullman, Palouse River, Washington ..---------                  -         1953           $49, 267 -----------       1, 460,733
Colfax, Palouse River, Washington--------------...............            1953            73,851                   22,386, 149
Pendleton, Umatilla River, Oregon...                       _...........   1939           143,263 -.....               (1)
Dayton, Touchet River, Washington.............                            1953            16,064                    2 548,936
Malheur Improvement District near Weiser,
  Snake River, Idaho....._____------------1949                                                319--------------         51,681
Pilot Rock, Birch Creek, Oregon.___,           -- _ -   -                 1949             3,700 _                     147,300
Pendleton, Umatilla River, Oregon.......              _                   1950    --------------------------          633, 000
Lewiston-Clarkston Levees .._____________ .... ___.                       1950-                                    23,910,000


  1 Completed.
  2 No funds appropriated for work.


                                    12. GENERAL INVESTIGATIONS
   Examinations and surveys. Total costs of work during the fis-
cal year for examinations and surveys were $161,464 and expendi-
tures were $161,464.
   Total funds unexpended as of June 30, 1954, amounting to $183
plus an allotment of $60,400, or a total of $60,583, will be applied
during the fiscal year to examinations and surveys.
   Collection and study of basic data. Total costs of work during
the fiscal year for the collection and study of basic data were $1,923
and expenditures were $1,923.
   A total of five reconnaissance trips were made during the fiscal
year to define the snow line at various times during the snow-melt
period. Pictures were taken at representative locations for com-
parison of snow field condition at various times. The extent of the
snow field was plotted on sectional aeronautical charts and a draw-
ing was prepared to preserve information on snow line locations
and elevations. It is anticipated that the data obtained on these
trips will be utilized in hydrograph reconstitutions and in future
years as a basis for forecasting runoff and stream flows.
   Total funds unexpended as of June 30, 1954, amounting to $77,
plus an allotment of $2,100, or a total of $2,177 will be applied
during the fiscal year 1955 to the collection and study of basic
data.
       13. INSPECTION OF COMPLETED FLOOD CONTROL WORKS
   Allotments totaling $2,500 have been received previously for in-
spection of various completed flood control works to insure that
projects are being maintained by local interests.
   Operations during the fiscal year 1954 consisted of inspections of
flood control works at the following locations: Touchet River,
Wash., Milton-Freewater, Walla Walla River, Oreg., and Mill
Creek, Wash.
   Total cost during the fiscal year 1954 was $324.
                   FLOOD CONTROL---WALLA WALLA, WASH., DISTRICT                                                  1541
                                                     Cost and financial summary

                                                           Fiscal year ending June 30                    Total to June
                                                                                                         30, 1954, includ-
                                                                                                         ing fiscal years
                                            1950          1951          1952        1953      1954        priorto 1950


Maintenance:
   Appropriated-------....------------                     $1, 500 ------------..   $1, 000                        $2, 500
    Cost--------.... .......-----------------   --            175          $579         652      $324               1,730



   14. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION
  Snagging and clearing of navigable streams and tributaries in
the interests of flood control. (Sec. 13 of the 1946 Flood Control
Act.)
   In addition to funds previously allotted amounting to $212,422,
funds in the amount of $33,400 were allotted during fiscal year
1954, making a total of $245,822, all for new work. In addition,
local interests at Waitsburg, Wash., have contributed $20,000 to
cover cost of their portion of Touchet River project.
   Channel clearing and snagging was completed at Owyhee River,
Oreg. Plans and specifications were completed for Phil Ford and
Salubria Cove Locations, Weiser River, Idaho as well as prepara-
tory work by local interests.
   Total costs from Federal funds during the fiscal year have been
$51,086. Total costs to June 30, 1954, have been $214,794, all for
new work.
                                                     Cost and financial summary

                                                           Fiscal year ending June 30                    Total to June
                                                                                                         30, 1954, includ-
                                                                                                         ing fiscal years
                                            1950          1951          1952        1953      1954        priorto 1950

New work:
   Appropriated .------------------                       $70,000   ------------    35, 561   $33, 400          1$245, 822
    Cost ...--------------------------                     39,090       $16, 471     1,286     51,086            1214,794
1 In addition $20,000 was expended from contributed funds by local interests for Touchet River at
Waitsburg, Wash.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-_-----------        $30,883
    Unobligated balances available for succeeding fiscal year ending June 30,
       1955__-------------------------------------------------                 30,883
    Small flood control projects not specifically authorized by Con-
gress.           (Section 212 of the 1950 Flood Control Act.)
   A revocation in the amount of $4,400 was made during fiscal
year 1954 from a total previously allotted of $166,969, plus a new
allotment of $274,050, making a total of $436,619 for work under
this authorization for fiscal year 1954.
   Operations during the fiscal year. Plans and specifications
were completed for Tomanovich-Salmon City Location, Salmon
River, Idaho; Gooding-Shoshone, Big and Little Wood Rivers,
Idaho. Project reports were partially completed for Dry Creek
Location, Tributary of the Walla Walla River, Wash.; Deep Creek
Location, Potlatch, Idaho; Bancroft Location, Portneuf River,
Idaho.
1542           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Total costs during the fiscal year have been $69,859. Total costs
to June 30, 1954, have been $191,411, all for new work.

                                    Cost and financial summary

                                            Fiscal year ending June 30                    Total to June
                                                      .     ..   . ...                   30, 1954, includ-
                                                                                         ing fiscal years
                             1950        1951        1952           1953       1954        priorto 1950


New work:
    Appropriated --------   $100, 000    $14,000    $120, 093     -$67, 124   $269,650           $436,619
    Cost-----------------     12,759      71,352      22,888        14,553     69,859              191,411

Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_-------------- $245,207
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955   ---------------------------------------------            245,207
   Flood control emergencies---Repairand flood fighting and rescue
work. (Section 210 of the 1950 Flood Control Act and supple-
mental authorizations.)
   In addition to funds previously allotted in the amount of $2,527,-
179, funds in the amount of $33,205 were allotted during the fiscal
year, making a total of $2,560,384, all for maintenance.
   Plans and specifications were completed on Ford Smith and
Galloway Locations, Weiser River, Idaho. Design and construc-
tion were completed for placement of revetment stone at Jackson
Hole Area, Snake River, Wyoming and Fullmer Location, Heise
Roberts Area, Snake River, Idaho. Emergency flood fights were
carried on at Wilson Area and Jackson-Wilson Bridge, Jackson
Hole, Wyoming and on Payette River, Idaho.
   Total costs during the fiscal year have been $80,234. Total costs
to June 30, 1954, have been $2,534,245.

                                    Cost and financial summary

                                           Fiscal year ending June 30                     Total to June
                                                                                         30, 1954, includ-
                                                                                         ing fiscal years
                             1950        1951        1952          1953       1954        priorto 1950


Maintenance:
   Appropriated .......     $136,513    $ 84,247     $46, 219     $134, 659   $33, 205         $2, 560,384
   Cost ----------------
              _              214, 164    155,891      80,654       132,114     80, 234        12,534,245
  1 In addition $64,000
                      formaintenance was expended from contributed funds-$44,000 for Touchet River
at Dayton, Washington and $20,000 for Boise River, Silver Bridge, Idaho.
    IMPROVEMENT OF RIVERS AND HARBORS IN THE
                ALASKA DISTRICT
   This District consists of the Territory of Alaska.
                                    IMPROVEMENTS

                 Navigation                                           Flood Control
                                         Page                                                           Page

1. Nome Harbor, Alaska_.....-.-.......   1543 4. Salmon River, Alaska..-----...---.....                 1547
2. Harbor of refuge, Seward, Alaska      1545 5. Inactive flood control projects....                    1549
3. Inactive navigation projects-..       1547 6. General investigations................                 1549
                                              7. Inspection of completed proj-
                                                   ects..............................................   1550
                           1. NOME HARBOR, AASKA
  Location. Nome Harbor is situated at the mouth of Snake
River on the northerly shore of Norton Sound, an arm of Bering
Sea. It is a shallow, open roadstead, 581 nautical miles north of
Dutch Harbor and 2,288 nautical miles northwest of Seattle, Wash.
(See U. S. Coast & Geodetic Survey Charts Nos. 9302, 9380 and
9381.)
   Existing project. This provides for two jetties, the easterly,
951 feet long and the westerly, not exceeding 676 feet long, at the
mouth of the Snake River; a channel 8 feet deep at mean lower low
water and 75 feet wide from Norton Sound through Snake River to
the mouths of Bourbon and Dry Creeks, in the City of Nome, termi-
nating in a basin of similar depth 250 feet wide and 600 feet long,
revetting the banks of the river; and protecting all existing water
front improvements on the easterly beach by means of a rock-
mound seawall 3,350 feet long extending easterly from the east
jetty. The extreme tidal range is 2.8 feet and the range between
mean lower low water and mean higher high water is 1.15 feet, but
water levels are influenced more by wind than tide. Levels of 7
feet below mean lower low water have been observed during off-
shore winds, and a level of 14 feet above mean lower low water has
been observed during a southerly storm.
  The latest (1954) approved estimate of cost for new work is
$2,200,000. The latest (1952) approved estimate for annual cost
of maintenance, exclusive of the seawall, which is to be maintained
by local interests, is $67,500, including $20,000 for annual mainte-
nance of the authorized extensions to the jetties, but excluding
$2,500 to be contributed by the City of Nome.
  The existing project was authorized by the following river and
harbor acts:
                                                                                            1543
 1544             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                                                                                          1
       Acts                         Work authorized                                Documents and reports


Aug.    8, 1917   For 2 jetties, the easterly 335 feet and the westerly        H. Doc. 1932, 64th Cong., 2d sess.
                   460 feet long; revetment, channel, and basin 200
                   feet wide and 250 feet long.
Aug. 30,1935      Extension of the jetties and basin__----------------         H. Doc. 404, 71st Cong., 2d sess.,
                                                                                and Rivers and Harbors Com-
                                                                                mittee, Doc. 38, 73d Cong., 2d
                                                                                sess.
June 16, 1948     Seawall____________ _____________    ________....... .....   Report of the Chief of Engineers
                                                                                dated Mar. 8, 1948.

   Contains latest published maps.

     Local cooperation. In accordance with the provisions of the
  River and Harbor Act of August 8, 1917, which authorized the
  initial improvement, the city of Nome furnished evidence, accepted
  by the Secretary of War on December 22, 1917, that it would con-
  tribute $2,500 annually toward the maintenance of the improve-
  ments and furnish all lands or easements necessary to the proper
  execution of the work. These conditions have been met annually
as required.
     In accordance with the provisions of the River and Harbor Act
of June 16, 1948, which authorized the seawall, local interests are
required to furnish without cost to the United States, the neces-
sary lands, easements, rights-of-way, and quarry rights; accom-
plish without expense to the United States, alterations as may be
required to utility facilites; agree to hold and save the United Sates
free from any claims for damages that may result from construc-
tion of the project; and agree to maintain the works after com-
pletion. These conditions have been met.
    Terminal facilities. Cargoes and passengers from ocean vessels
are lightered to and from shore a distance of about 2 miles. Traf-
fic enters the dredged channel and is handled over the revetment,
where transfer facilities that are open to public use have been in-
stalled by a lighterage company. These facilities are considered
adequate for existing commerce.
    Operations and results during fiscal year. There was no new
work during the fiscal year.
    Maintenance was performed by Government plant and hired
labor, July through November 5, 1953 and April through June
1954, and consisted of dredging 18,800 cu. yds., at a cost of $39,143
and continuing revetment repairs and patching the east jetty at a
cost of $6,871. Total maintenance costs for the fiscal year, which in-
cluded $6,953 for operations and ordinary maintenance were $55,-
472, of which $52,972 was from Federal funds and $2,500 from
contributed funds.
    Condition at end of fiscal year. The project is 62 percent com-
plete. Construction of the original 335- and 460-foot jetties and
the revetments was commenced in 1919 and completed in 1923.
Reconstruction of the jetties with concrete to modified lengths of
240 feet and 400 feet was completed in 1940. Dredging of the
channel and the original 200- by 250-foot basin was commenced
in 1919 and completed in 1922. Construction of the seawall was
commenced in 1949 and completed in June 1951.
  Dredging of the 400-foot extension of the basin was commenced
                          FLOOD CONTROL-ALASKA DISTRICT                                            1545
in 1949 and is complete with the exception of small areas in the
northerly portion of the small boat harbor extension and around
the Corps of Engineers marine ways.
  Timber revetments have shown progressive deterioration and
have been refaced with sheet steel piling. The east jetty was re-
paired in 1954 with a concrete fill. The work remaining to be done
to complete the project is to dredge two small areas in the 400-foot
extension of the basin in the northerly portion of the small boat
harbor extension and around the Corps of Engineers marine ways
and to extend the jetties to their authorized lengths.
   The costs from Federal funds to June 30, 1954 have been $1,348,-
240 for new work and $1,291,916 for maintenance, a total of $2,-
640,156. The costs from contributed funds have been $125 for new
work and $80,000 for maintenance, a total of $80,125.

                                     Cost and financial summary
                                         UNITED STATES FUNDS


                                             Fiscal year ending June 30                    Total to June
                                                                                           30, 1954, includ-
                                                                                           ing fiscal years
                              1950          1951        1952        1953        1954         prior to 1950


New work:
   Appropriated _......      $701, 000     $464, 000   -$89, 710------------------------       I $1, 348,240
   Cost-   -          -       333,689       738,839        2,763 ------------------------         1,348,240
Maintenance:
   Appropriated    -ost
                      .        40, 000      45,000       23,000     $31, 850    $52, 379        2 1, 298, 426
   Cost   __________           57,593       43,473       51,480      33,725      52,972          1, 291, 916

1In addition $125,00 of contributed funds was expended on new work.
2   In addition $80,000.00 of contributed funds was expended on maintenance.

Other new work data: Estimated additional amount needed to be appropri-
  ated for completion of existing project_________    ____-_____-       $851,760

                   2. HARBOR OF REFUGE, SEWARD, ALASKA
  Location. This harbor is located at Seward, Alaska, on the west
side of the north end of Resurrection Bay. The harbor is about 130
miles west of Cordova, Alaska. (See U. S. Coast and Geodetic
Survey Charts Nos. 8529 and 8552.)
  Existing project. This provides for a south breakwater 580
feet long and a north breakwater 950 feet long, and dredging a
basin about 207,000 square feet in area between the breakwaters to
a depth of 121/2 feet at mean lower low water. The range between
1546           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

mean lower low water and mean higher high water is 8.3 feet with
an extreme range of 18.9 feet.
  The actual cost for new work was $154,154. The approved esti-
mate of annual cost of maintenance, made in 1952, is $4,000.
  The existing project was authorized by the following river and
harbor acts:

    Acts                         Work authorized                         Documents and reports   1

July 3,1930    South breakwater and dredged basin--------------...   H. Doc. 109, 70th Cong., 1st sess.
Aug. 30,1935   North breakwater____
                                  .......     ...................    Rivers and Harbors Committee
                                                                       Doc. 3, 74th Cong., 1st sess.

1 Contain latest published maps.


   Recommended modification of project. Under date of July 29,
1952, the Chief of Engineers recommended modification of the ex-
isting project so as to provide a pile breakwater to close partially
the east (entrance) side of the existing basin and to raise the south
breakwater by constructing a 3-foot high concrete wall on top of
the rock, all at a total estimated first cost of $68,200 with annual
maintenance of $1,075; subject to certain conditions of local co-
operation. (H. Doc. 182, 83d Cong., 1st Sess.).
   Local cooperation. None required.
   Terminal facilities. Docking facilities at Seward include a float
constructed by local interests which will accommodate about 50
boats, one commercial wharf, owned by the Alaska Railroad, which
is available to the use of the public on payment of the usual wharf-
age charges, one wharf owned by the Standard Oil Company, one
wharf owned by the United States Government and operated by
the Alaska Railroad as a general cargo terminal, and two wharves
which are privately owned and used for industrial purposes. These
facilities are considered adequate for existing commerce.
   Operations and results during fiscal year. Maintenance was
performed by contract labor during March and April 1954, and
consisted of placing 1,482 cubic yards of rock on the north break-
water at a cost of $24,084. Total maintenance cost for the fiscal
year, which included $5,658 for operations and ordinary mainte-
nance, was $29,742.
   Condition at end of fiscal year. The existing project was com-
pleted in 1937. Maintenance dredging to restore project depth
over all navigable portions of the basin was completed in fiscal year
1952 and the north breakwater was restored to project dimensions
in fiscal year 1953. The costs to June 30, 1954, have been $154,154
for new work and $73,909 for maintenance, a total of $228,063.
                                FLOOD CONTROL-ALASKA DISTRICT                                                                      1547
                                                  Cost and financialsummary

                                                            Fiscal year ending June 30                                    Total to June
                                                                                                                      30, 1954, includ-
                                                                                                                      ing fiscal years
                                          1950         1951             1952            1953              1954          priorto 1950

New work:
   Appropriated              -----------------------------------------------------------                                           $154,154
   Cost....-----------------                       ------------------------------------------------                                 154,154
Maintenance:
   Appropriated--------                  $55, 000 .........----------- -- $23, 927 ------------          $37, 500                        81,667
   Cost-----------------                    4,290                 $44             ------------
                                                                                 26,739                   29,742                         73,909



                             3. INACTIVE NAVIGATION PROJECTS

                                                                                        Cost to June 30, 1954
                                                                     For last                                                  Estimated
                      Name of project                              full report                                                   amount
                                                                   see annual                          Operations              required to
                                                                   report for-     Construction           and                   complete
                                                                                                      maintenance



1. Apoon Mouth of Yukon River, Alaska                  2......        1920         $128,896.04           $2,153.83                 (1)
2. Cordova Harbor, Alaska ---------------------                       1952          253,534.14           92,999.79                (1)
3. Craig Harbor, Alaska-                      .--.--.--..
                                         ---........                   1945                               $341,000
                                                                                  .......-...............---
4. Dry Pass, Alaska                       --------                    1949            58, 665.32             536.79                (1)
5. Egegik River, Alaska            -_                             -1941                4,441.10 -.--            -         -        (1)
6. Elfin Cove, Alaska_________ -____--               -__              1945--   -----------_------------                           - 162,000
7. Gastineau Channel, Alaska___                                       1952 -
                                                                        1-.---. -    ---   -1,                                       010,000
8. Iliuliuk Harbor, Alaska- --- __--_---                   ----       1941            66, 036. 59 -.. .             ..            (1)
9.   Juneau Harbor, Alaska ...---------------------                   1952           150, 715.81         28, 464.40               (1)
10.   Ketchikan Harbor, Alaska ....-----------------                   1953           224, 945.84         33, 438.50               (1)
11.   Kodiak Harbor, Alaska--------.......------------                 1949            12,144.64           3,458.47                 109,900
12.   Metlakatla Harbor, Alaska__------------------                    1952                                                         383,000
13. Meyers Chuck Harbor, Alaska- ---------..                       - 1945                                                           123 000
14. Petersburg Harbor, Alaska             ------                       1950             88, 386.84         412.78                   226,600
15. Port Alexander, Alaska ... _____----------                         1949             17,000.00          593.83                    97, 000
16. St. Michael Canal, Alaska -          --                            1916            377, 061.95         559.76                  (1)
17. Seldovia Harbor,Alaska. _-__-_--_                                  1949        .....         ....                               258,000
18. Sitka Harbor, Alaska __----------------------                      1952             64, 797.04      4, 605.98                   891, 200
19. Skagway Harbor, Alaska_           ___---
20. Skagway River, Alaska (O&M Special) ...
                                                 ----
                                                        5-
                                                                       1953
                                                                       1953
                                                                                        62, 172.99    -11, 667.00
                                                                                                                     -               46,000
                                                                                                                                   (1)
21. Stikine River, Alaska a-------                                     1949 ------                .     4, 757.10                  (7)
22. Valdez Harbor, Alaska ......-------------------                    1952             52, 361.08     42,728.96                   (1)
23. Wrangell Harbor, Alaska_                                           1953             91, 020.98      7,349.87                    507,700
24. Wrangell Narrows, Alaska....------------------                     1953        6 3,195,502.08     242, 923.24                   854,500


  1 Completed.
  2 Abandonment recommended in House Document 467, 79th Congress, 1st Session.
  a No maintenance required at present.
  4 In addition, $8,000 was expended from contributed funds.
  5 This amount was used to partly fund a joint civil works and maintenance project for emergency work
on Skagway River.
  6 Refunded during fiscal year $779.51.
  7 Authorized for maintenance only.


                                          4. SALMON RIVER, ALASKA
  Location. Salmon River rises in Canada and empties into Port-
land Canal at the Town of Hyder. (See U. S. Coast and Geodetic
Survey Chart No. 8054.)
      Existing project.                        The plan of improvement provides for a rock-
faced earth dike on the left limit of the river near its mouth, 4,334
1548             REPORT OF CHIEF OF ENGINEERS, U. S. AI MY, 1954

feet in length with an average height of 5 feet. The project pro-
tects the townsite of Hyder, Alaska, from floods in Salmon River
and deflects the silt deposit away from the harbor area.
   The estimated cost, made in 1931, was $53,000 (including $7,000
contributed by local interests) for new work and $1,000 (including
$200 to be contributed by local interests) annually for maintenance.
The project was authorized by the act approved June 18, 1934,
P.L. 388, Seventy-third Congress (H. Doc. 228, 72d Cong., 1st
Sess.). The latest published map is in the project document.
   Local cooperation. In accordance with the provisions of the act
of June 18, 1934, local interests were required to contribute $7,000
toward the first cost of the work and $200 annually for mainte-
nance. An appropriation of $7,000 was made by the Territorial
Legislature in 1933 for this purpose. Annual contributions have
been made as required. Prior to the adoption of the existing proj-
ect, approximately $8,000 was expended by the United States Bu-
reau of Public Roads for a rock dike, and $26,350 by Territorial
and local interests for dikes, revetment and dredging with a view
to flood protection.
   Operations and results during fiscal year. The costs in the
amount of $11,475.55 were incurred under operations and ordinary
maintenance activities including an inspection of completed work.
   Condition at end of fiscal year. The existing project was com-
pleted in 1935. The dike was generally in good condition in May
1954. The costs from Federal funds have been $34,231 for new
work and $21,246 for maintenance, a total of $55,477. In addition,
$7,000 has been expended from contributed funds for new work
and $2,400 for maintenance.
                                              Cost and financial summary

                                                        Fiscal year ending June 30                                Total;to June
                                                                                                                  30, 1954, includ-
                                                                                                                  ing fiscal years
                                       1950            1951           1952            1953            1954         prior to 1950

New work:
               -------------------------------------------------
   Appropriated..                                                                                   ------------         1$34, 231
   Cost----------------------                                                                                               32-----------------------
                                                                                                                           134,231
Maintenance:
    Appropriated---........ -----------------------------------                 ----------------------                      21, 246
    Cost...............------------------------------------......... ------------        447           $11, 475             21,246


  1 In addition $7,000.00 of contributed funds was expended on new work.
  2 In addition $2,400.00 of contributed funds was expended on maintenance.
                             FLOOD CONTROL-ALASKA DISTRICT                                                      1549
                     5.   INACTIVE            FLOOD         CONTROL             PROJECTS

                                                                            Cost to June 30, 1954
                                                            For last                                         Estimated
                   Name of project                        full report                                      amount
                                                          see annual                   Operations        required to
                                                          report for-    Construction     and             complete
                                                                                      maintenance

1. Fairbanks, Tanana River and Chena Slough,
     Alaska_-------
2. Lowell               ----------------------
            Creek, Alaska-                                 1945       $557, 000.00                              (1)
                            _----_---------------          1945       2 416,382.29           $30, 771.35        (1)
3. Skagway, Skagway River, Alaska.............             1953           21,384.93 --------------              $768, 000
4. Emergency Bank Protection Work Under Au-
     thority of Section 14 of the Flood Control Act
     Approved July 24, 1946.. ----.        .--.---...  - 1952            24, 898.00--------------               ()
5. Emergency Flood Control Work Under Au-
     thority of Section 5 of the Flood Control Act
     Approved August 18, 1941, as Amended 4....            1950   ---------------             46, 831.20        (1)
6. Emergency Flood Control Work Under Au-
     thority of Public Law 138, 78th Congress, and
     Public Laws 102 and 858, 80th Congress.....           1953 --------------                72, 360.91..     ...
7. Emergency Flood Control Work Under Au-
     thority of Section 208 of the 1948 Flood Con-
     trol Act, 80th Congress, 2d Session, and Pub-
    lic Law 371 Approved June 4, 1952, 82d Con-
     gress, 2d Session-                                    1953    .............--------------
                                                 .-------------------------                '151, 719.81

    Completed and transferred to local interests for maintenance.
   2In addition, $25,000 has been expended from contributed funds.
  3 Emergency bank protection of Talkeetna River at Talkeetna, Alaska. Completed.
  4 Emergency flood control work, Gold Creek, Juneau, Alaska.
  b Consists of emergency dike repair Skagway River $47,360.91 and channel revetment repairs Gold
Creek, Juneau $25,000.
  a Consists of emergency repairs Skagway River $44,299.43 and emergency flood control work Gold
Creek, Juneau $107,421.23.
  ' Does not include $11,667 which was used to partly fund a joint Civil Works-Military project for emer-
gency work on Skagway River. Included in inactive navigation projects table.

                                6. GENERAL INVESTIGATIONS
  Examinations and surveys. The cost of work during the fiscal
year amounted to $60,583, the expenditures were $60,583. This
amount includes $6,108 for examination and surveys, flood control
studies, and $54,475 for navigation studies.
   The funds unexpended June 30, 1954, $13,303 together with an
anticipated allotment of $37,000, $20,000 for flood control and
$17,000 for navigation, will be applied as needed during fiscal year
1955 for further study in connection with Interim Report No. 6--
Seward Peninsula and Arctic Shelf and Interim Report No. 7-
Yukon and Kuskokwim Rivers, and to unliquidated obligations in
the amount of $1,200 for navigation studies which were conducted
in 1953.
   Collection and study of basic data. The cost of work during the
fiscal year amounted to $12,000.
1550    REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   7. INSPECTION   OF COMPLETED    FLOOD CONTROL WORKS

  Inspections were made of Salmon River, Lowell Creek and Fair-
banks, Tanana River and Chena Slough projects during fiscal year
1954. The inspections made of Lowell Creek and Fairbanks,
Tanana River and Chena Slough projects were made in conjunction
with other civil works activities in the area at no costs to the
projects.
   ANNUAL REPORT OF THE BOARD OF ENGINEERS FOR
              RIVERS AND HARBORS
   The Board of Engineers for Rivers and Harbors was authorized
by section 3 of the River and Harbor Act approved June 13, 1902.
The enabling act provided for the organization in the Office of the
Chief of Engineers by detail from time to time from the Corps of
Engineers of a Board of five engineer officers (later increased by
legislation to seven members), a majority of whom shall be of
rank not less than lieutenant colonel.
   The act with subsequent amendments directs that all reports on
authorized preliminary examinations and surveys of river and
harbor and flood control projects be reviewed by the Board prior
to submission of the reports by the Chief of Engineers with his
recommendation to Congress. The review is for the purpose of de-
termining the economic and engineering justification of the proj-
ects reported upon. The Board is also required upon request by
the appropriate committees of Congress to review and report
through the Chief of Engineers upon any authorized project or
desired improvement previously reported upon with a view to
recommending the initiation of a project or modification of an ex-
isting project. The Chief of Engineers may refer to the Board
for consideration and recommendation all special reports ordered
by Congress and may prescribe such other duties as he desires.
   Additional duties were assigned to the Board under the terms
of section 8 of the Merchant Marine Act of 1920, and of various
River and Harbor Acts, notably those of February 1891 and Sep-
tember 1922. In compliance with the Merchant Marine Act, the
Board is responsible, in cooperation with the Maritime Administra-
tion, for collecting, compiling, and publishing information on more
than 100 sea and Great Lakes ports. Under the River and Harbor
Acts, the Board compiles and publishes data on the water transpor-
tation lines of the United States, and other publications containing
information on the water-borne commerce of the United States,
and on the port and terminal charges at United States ports. It
provides technical supervision over the compilation and publication
of the National Summary Tables and the Regional Statistical Re-
ports containing the statistics pertaining to the water-borne com-
merce in the United States.
    In addition to the duties prescribed by law, the Board performs
such other duties as may be assigned by the Chief of Engineers.
During the fiscal year ending June 30, 1954, the Board performed
the following assigned duties: Reviewed and submitted recommen-
dations on certain Corps of Engineers policies and procedures as
directed; reviewed and commented on reports of other Federal
agencies pertaining to water resource development; conducted in-
vestigations and studies of the economics of ports and waterways;
provided guidance to the field offices of the Corps of Engineers in
the field of waterways economics including distribution of the
Waterways Economic Series of publications; prepared Engineer
                                                           1551
1552     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Intelligence Reports and special planning studies on Foreign Ports;
and prepared vulnerability reports on certain ports of the United
States.
   On June 30, 1954, the Board was composed of the following Mem-
bers: Major General Bernard L. Robinson, Deputy Chief of En-
gineers for Construction (Chairman); Brigadier General William
E. Potter, Division Engineer, Missouri River Division; Brigadier
General Herbert D. Vogel, Division Engineer, Southwestern Di-
vision; Colonel Wendell P. Trower, Division Engineer, Great Lakes
Division; Colonel Benjamin B. Talley, Division Engineer, North
Atlantic Division; Colonel Paul D. Berrigan, Division Engineer,
South Pacific Division; and Colonel Francis H. Falkner, Resident
Member, Board of Engineers for Rivers and Harbors.
   In addition to the foregoing, the following named officers have
also been detailed for various periods during the year to Member-
ship on the Board: Brigadier General Emerson C. Itschner, Divi-
sion Engineer, North Pacific Division; Brigadier General Charles
G. Holle, Division Engineer, South Atlantic Division; and Colonel
Leland H. Hewitt, Division Engineer, New England Division.
   A summary of the Congressional investigations authorized from establishment of the Board in 1902 to the
close of the fiscal year 1954, authorizations completed, and the number of authorizations remaining to be
reported upon is given in the following table:


                                                                          Number of investiga-    Number of investiga-        Total number           Number completed           Numb er
                     Authority for investigations                          tions ordered prior    tions ordered during       completed prior         during year ending       remainin g to
                                                                              to July 1, 1953        fiscal year 1954         to July 1, 1953           June 30, 1954         be compl eted
                                                                                                                                                                                               O
                                                                       SI.                                               I                       I                        I
River and Harbor and Flood Control acts-----------------------------                     4,987                                          4,556                       41                   391
Congressional resolutions.- --                                                           2, 786                     56                  2,048                       87                   707
     Total-----------------.
          _                                                                                                         56                   6,604                     128                 1,098
                                                                                         7, 774
                                                                                                                                                                                               z


                                                                                                                                                                                               O




                                                                                                                                                                                               v7j




                                                                                                                                                                                               O




                                                                                                                                                                                               01
                                                                                                                                                                                               c1
1554              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   The Board held three hearings during the year and made one
field inspection trip pertaining to projects in California, with par-
ticular reference to San Francisco Bay and Monterey Bay. It held
eight meetings of from one to three days duration and considered
91 reports, acting favorably on 58 and unfavorably on seven re-
ports of survey; reporting unfavorably on 10 preliminary examina-
tions; recommending seven surveys be made; recommending one
project for construction under the River and Harbor Act of 1909;
and returning eight reports to the field for reconsideration. In
addition the Resident Member returned 26 obsolete reports to the
Office, Chief of Engineers with the recommendation that they be
sent back to the reporting officers for revisions to reflect changed
conditions and to bring the costs and benefits up-to-date. The
board recommended favorably on projects totaling $913.545.000 of
which $864,547,000 was the cost to United States and $48,998,000
cost to local interests; and unfavorably on projects totaling $44,-
181,100 during the year.
   Commencing with its meeting in October 1953, the Board opened
its meetings to the public. Since that time all deliberations and
discussions of the Board have been conducted in open session in
order that interested parties can be fully informed on the bases in
which the Board's decisions are made. This practice will be con-
tinued. As a result of having its meetings open to the public in-
terested parties were present during the consideration of about 90
percent of the reports and on about 50 percent of the reports in-
formal statements were made by interested parties.
   In addition to its review of preliminary examination and surveys,
the Board submitted reports or comments on reports to the Chief
of Engineers as follows:
     39 Reports of other Federal agencies on water resource de-
         velopment;
     16 Special Civil Works reports to the Chief of Engineers;
       4 Reports on Corps of Engineers policies and procedures;
       2 Waterways Economic Series Reports;
     27 Engineer Intelligence Studies covering 38 foreign ports;
       2 Reports on vulnerability of United States Ports, covering
         9 ports; and
     27 Special planning studies on foreign ports.
   Studies prescribed by various River and Harbor Acts, and by
section 8 of the Merchant Marine Act of 1920, were continued and
the results published in three series of reports under the titles of:
     Port Series Reports
     Lake Series Reports
     Transportation Series Reports
   The following reports were published during the year:
                                  Port Series Reports
No.   33.   The   Ports of Astoria, Oregon, and Longview and Vancouver, Washington.
No.   34.   The   Port of Portland, Oregon.
No.   35.   The   Ports of Tacoma, Grays Harbor, and Olympia, Washington.
No.   36.   The   Port of Seattle, Washington.
No. 37. The Ports of Everett, Bellingham, and Port Angeles, Washington.
           BOARD OF ENGINEERS FOR RIVERS AND HARBORS                           1555
                             Lake Series Reports
No. 7. The Ports of Chicago, Illinois, Indiana Harbor, Indiana, and Muskegon,
         Michigan.
No. 8. The Ports of Milwaukee, Manitowoc, and Green Bay, Wisconsin, and Escanaba,
         Michigan.
                      Transportation Series Reports
No. 3. Transportation Lines on the Great Lakes System, 1954.
No. 4. Transportation Lines on the Mississippi River System and the Gulf Intra-
         coastal Waterway, 1954.
   At the close of the year the following report was in progress:
                              Port Series Reports
No. 5. Parts 1 and 3, The Port of New York, N. Y. and N. J.

  The following reports were completed during the year and at
the close of the year were in the process of printing:
                             Port Series Reports
No. 1. The Ports of Portland and Searsport, Maine, and Portsmouth, N. H.
No. 4. The Ports of Southern New England.

                       TransportationSeries Reports
No. 5. Transportation Lines on the Atlantic, Gulf, and Pacific Coasts, 1954.

   The Annual Report of the Chief of Engineers, Part 2, 1953 con-
taining the waterborne commerce statistics of the United States
for the calendar year 1952 was prepared and sent to the printer.
This will be the last Annual Report of the Chief of Engineers, Part
2, which will be assembled by the Board and printed as a separate
volume. During the year the Board recommended discontinuance
of this practice in favor of publication of the national statistical
summaries in the volume containing Part 1 of the Annual Report
and the publication of detailed waterborne commerce statistics in
four regional volumes to be published by the Regional Statistical
Offices. This procedure will be used for the current report for
1954. The new procedure will reduce staffing requirements and
cut the time of publication from 18 months after the close of the
calendar year to 9 months.
   The waterborne commerce statistics pamphlet containing the
calendar year 1952 basic national tables including the tabulation of
domestic deepsea tonnages on an area to area basis was published.
In addition, area to area movements reports for 24 basic commodi-
ties or groups of commodities in domestic inland waterborne com-
merce were compiled, published, and distributed. These area to
area movement reports were established during the year as a
permanent part of the waterborne commerce statistics service of
the Board.
   The waterways economics research works of the Board was
placed on a firmer basis during the year through adoption of a long-
range program of study and the establishment of more specific ob-
jectives. The Board's economic studies were given a broader field
of usefulness by establishing The Waterways Economics Series of
reports designed for distribution to all Corps of Engineers offices
1556     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

for the purpose of disseminating throughout the organization, the
data compiled. Two economics reports were distributed during the
year and four additional reports were nearing completion.
   In addition to the dissemination of waterways economics re-
search data to the field offices, the Board's staff rendered assistance
to 15 divisions and districts by preparation of reports, field surveys,
and providing staff supervision on the analysis of waterways eco-
nomics for specific projects.
   During the year, the Board maintained close contact with the
field offices of the Corps of Engineers, gave wide distribution to its
studies and reports, gave thorough and independent analysis to all
reports of investigations, and opened all its actions and delibera-
tions to public scrutiny.
                               BEACH EROSION BOARD

   .The Beach Erosion Board was organized under authority of sec-
tion 2 of the River and Harbor Act approved July 3, 1930 (Public
Law 520, 71st Cong.) which authorized and directed the Chief of
Engineers under the direction of the Secretary of the Army to
cause investigations and studies to be made, in cooperation with
public agencies of the various States, to devise effective means of
preventing erosion of the coastal and Great Lakes shores by waves
and currents. To furnish the technical advice and assistance re-
quired in this program, the Chief of Engineers was directed to
form a board of seven members to assist in the conduct of studies,
review the reports on such investigations and submit recommenda-
tions. By executive ruling the agency applying for a cooperative
study under this act is required to contribute 50 percent of the
estimated cost of the investigation. Each study results in a report
containing plans and specific recommendations as to methods or
means to improve or remedy a condition at a particular localtiy. A
summary of such cooperative studies follows:
Number    of applications for studies approved prior to July 1, 1953............................ 81
Number    of applications for studies approved during fiscal year 1954........................ 4
Number    of reports completed prior to July 1, 1953 . ......................................87
Number                                                            -
          of reports completed during fiscal year 1954-,....-....-........                              6
Number    of studies remaining to be completed 1.................          ...._ ..................... 10
1 These studies involve 15 localities and will result in 15 reports.


   This basic law was supplemented by section 5 of the River and
Harbor Act approved August 30, 1935 (Public Law 409, 74th
Cong.) which provided that every report submitted to Congress
looking to the improvement of the entrance at the mouth of any
river or at any inlet for navigation contain information concerning
the configuration of the shoreline and the probable effect of the
proposed improvement on the coast line for a distance of not less
than 10 miles on either side of the entrance. Another supplemen-
tary law was the act approved July 31, 1945 (Public Law 166, 79th
Cong.) which made it the duty of the Chief of Engineers, through
the Beach Erosion Board, in addition to participating in cooperative
investigations under the basic law, to make general investigations
with a view to preventing erosion of the shores of the United States
by waves and currents and determining the most suitable methods
for the protection, restoration and development of beaches; and
to publish from time to time such useful data and information con-
cerning the erosion and protection of beaches and shore lines as
the Board may deem to be of value to the people of the United
States.
   Federal participation in the cost of protecting the shores of
publicly owned property was established in the act approved
August 13, 1946 (Public Law 727, 79th Cong.) which declared it
to be the policy of the United States to assist in the construction,
                                                                                         1557
1558             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

but not the maintenance, of works for the improvement and protec-
tion against erosion by waves and currents of the shores of the
United States that are owned by States, municipalities and other
political divisions; provided that the Federal contribution toward
the construction of protective works shall not in any case exceed
one-third of the total costs and that the plan of protection shall
have been specifically adopted and authorized by Congress after
investigation and study by the Beach Erosion Board. The word
 "shores" as used in the act includes all the shore lines of the At-
lantic and Pacific Oceans, the Gulf of Mexico, the Great Lakes,
estuaries and bays directly connected therewith.
    At the end of fiscal year 1954 the Board was composed of the
following members: Colonel Wendell P. Trower, U.S. Army, Presi-
dent; Colonel Richard W. Pearson, U.S. Army, Division Engineer,
New England Division, Boston, Mass.; Colonel Herman W. Schull,
Jr., U.S. Army, District Engineer, Jacksonville, Fla.; Colonel John
U. Allen, Resident Member; Mr. Thorndike Saville of New York,
Dean of the College of Engineering, New York University; Mr.
Morrough P. O'Brien of California, Dean of the College of Engi-
neering, University of California; Dr. Lorenz G. Straub, Engineer-
ing Consultant, Division of Waterways, Department of Conserva-
tion, State of Minnesota.
   In addition to the foregoing, Colonel Leland H. Hewitt, U.S.
Army was President of the Board and Major Peter Somers, U.S.
Army was detailed as Acting Resident Member of the Board, for
a part of the year.
   During the fiscal year 1954, the Board carried out studies and
investigations in cooperation with appropriate agencies of various
states and territories and with the field offices of the Corps of En-
gineers to develop effective works for the protection and stabiliza-
tion of the shores and beaches of coastal and lake waters. The
Board completed the review of cooperative beach erosion control
reports on Hampton Beach, N. H.; Selkirk Shores and Fair Haven
Beach State Parks on Lake Ontario in the State of New York; the
Atlantic shore from Sandy Hook to Barnegat Inlet in the State of
New Jersey; Perdido Pass, Alabama; and Grand Isle, La.
   The Board also completed 10 reports on the beach erosion aspects
of navigation improvements as provided in section 5 of the River
and Harbor Act approved August 30, 1935.
   The following cooperative studies were in progress on June
30, 1954:
                                                Date approved by                    Division         District
                 Locality                       Chief of Engineers                  Engineer         Engineer


California, State of (continuing study).      September 12, 1946_...            South Pacific    San Francisco and
                                                                                                   Los Angeles
Carolina Beach, N. C _-._--_.---------        April 24, 1952.........           South Atlantic   Wilmington..
Connecticut, State of (continuing             August 28, 1947-......            New England
  study).
Delaware, State of__-----------------         May 26, 1954-........             North Atlantic   Philadelphia.
Fire Island Inlet, N. Y------------..........--...    December 24, 1953..... North Atlantic New York.
Kenosha, Wis,_..------------                       .. February 2, 1950....__ Great Lakes    Milwaukee.
Lake Ontario State Parks, N. Y. April 1, 1953-..........-......do........... Buffalo.
  (Hamlin Beach & Braddock Bay.)
Massachusetts,     Commonwealth         of,   July 20, 1950...---------......   New England
Pemberton Pt. to Gurnet Pt.
Manitowoe-Two Rivers, Wis-........ October 13, 1953.......                      Great Lakes      Milwaukee.
Waimea and Hanapepe, T. H.......... April 19, 1950.........                     South Pacific    San Francisco.
                        BEACH EROSION BOARD                      1559
    The Board has continued general investigations of means of
protecting shores and beaches against erosion in accordance with
the authorization contained in the act approved July 31, 1945 (Pub-
lic Law 166, 79th Congress). Publication of the Quarterly bulletin
to disseminate rapidly pertinent information to the public was
continued. Six technical papers prepared by the staff were pub-
lished in the technical press. Fourteen technical research papers
were published by the Board. Two papers reporting results of re-
search were prepared but not yet published and sixteen others
were in preparation. In addition fourteen reports were prepared
and issued to other governmental agencies on projects carried out
for them. Review of the comprehensive report on shore protection,
planning and design was carried out, appropriate revision made,
and publication as a Technical Report of the Board is under way.
Additional equipment for the Coast Model Test Basin was installed.
Additional contracts were advertised for construction of wave gen-
erating equipment for the large outdoor wave tank adjacent to the
Board offiice building. Seven contracts with universities for re-
search to supplement the staff activities were continued and two
new contracts were negotiated. Two projects were prosecuted by
the Waterways Experiment Station at Vicksburg for the Board.
During the year a 3-week course on wave phenomena was con-
ducted at the Board's offices for interested District and Division
personnel and technical representatives of State and the Canadian
Government agencies.
    At the end of the year, studies were in progress on: the charac-
teristics of ocean waves by actual measurement at nine locations;
the relationship between wave dimensions, angularity of approach,
and the resulting littoral current velocity; the improvement of
wave forecasting procedures for both inland and ocean waters;
methods of bypassing sand at inlets; sources of beach material; an
analysis of Mission Bay field data; wave runup and overtopping on
shore structures; effects of tidal inlets on adjacent beaches; effect
of tidal fluctuations on wave produced beach profiles; available in-
formation on transport of sand by wind; statistical wave data for
United States coasts obtained by hindcast methods; reforming of
waves after breaking: effect of groin fields on rate of littoral trans-
port; case history of Moriches Inlet, Long Island; and a reexamina-
tion of data on artificially nourished and constructed beaches.
Regional studies consisting of compilation of basic data pertinent
to shore processes were substantially completed for two regions
and partly completed for three additional regions. In addition the
staff has worked on eight research projects for various defense
agencies of which four are still active, two research projects for
other government agencies and ten miscellaneous projects for
other Government agencies.
                 CALIFORNIA DEBRIS COMMISSION

   This Commission, consisting of three officers of the Corps of En-
gineers appointed by the President with the consent of the Senate,
created by the act of Congress approved March 1, 1893 (27 Stat. L.,
p. 507), was organized in San Francisco, Calif., on June 8, 1893,
and has jurisdiction and duties extending over the drainage area
of the Sacramento and San Joaquin Rivers, comprising the great
central valley of California and extending from the crest of the
Sierra Nevada on the east to that of the Coast Range on the west,
and from Mount Shasta and the Pitt River Basin on the north to
the Tehachapi Mountains on the south. These rivers empty into
the head of Suisun Bay, ultimately discharging into the Pacific
Ocean through the connecting bays and straits and the Golden
Gate.
   The duties prescribed by the act creating the Commission are:
First: To regulate hydraulic mining in such a way as to permit its
resumption and continuance under such restrictions as to prevent
the resulting debris from being carried into navigable waters or
otherwise causing damage. Second: To study and report upon
general hydraulic and hydraulic-mining conditions and matters af-
fecting or affected by them and to make surveys, mature and adopt
plans for the purpose of improving the navigability, deepening the
channels, and protecting the banks of the rivers, and affording re-
lief from flood damages.
   While the Commission was to "adopt" plans as a result of its
study, the act creating it did not provide means for directly carry-
ing them out. Congress, however, has from time to time adopted
certain of the plans formulated by the Commission charged it with
their execution, under the direction of the Secretary of the Army
and the supervision of the Chief of Engineers.
                                  IMPROVEMENTS

               Navigation                             Navigation-Continued
                                     Page                                           Page
1. Regulation of hydraulic mining           3. Sacramento River and tribu-
     and preparation of plans-..._   1561        taries, Calif. (debris control)_   1565
2. Treatment of the Yuba River
     debris situation-restraining                        Flood control
                  -------------
     barriers, Calif                 1563   4. Sacramento River, Calif .-------..   1568

  1. REGULATION OF HYDRAULIC MINING AND PREPARATION
                       OF PLANS
   Location. Operations are largely limited to the territory be-
tween Mount Lassen on the north and the Yosemite Valley on the
south, on the western watershed of the Sierra Nevada. (See U. S.
Geological Survey sheets for the area, 25 in number.)
   Existing project. This improvement provides for regulating
hydraulic mining operations, planning the improvement of condi-
tions upon the Sacramento and San Joaquin Rivers and their tribu-
                                                                            1561
 1562          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

taries affected by such operations, and the preparation of plans to
enable hydraulic mining to be resumed in their drainage areas. In
addition, the Secretary of the Army is authorized to enter into
contracts to supply storage for water and use of outlet facilities
from debris storage reservoirs for domestic and irrigation purposes
and power development, upon such conditions of delivery, use, and
payment as he may approve.
   Applications of prospective miners are fully investigated by the
California Debris Commission and permits to operate are issued
to those who provide satisfactory debris-restraining basins by con-
struction of suitable dams where necessary or agree to make pay-
ment for storage in Government-constructed, debris-restraining
reservoirs constructed under the act of June 19, 1934, as set forth
below. For location and description of Government-constructed de-
bris-restraining reservoirs for general hydraulic mining see Im-
provement No. 3, "Sacramento River and tributaries (debris con-
trol), Calif."
    The latest (1953) approved estimate for annual Federal cost of
this work is $15,000.
    The existing project was authorized by the following acts:

     Acts                         Work authorized                                    Documents

Mar. 1, 1893    Created California Debris Commission and author-          Ex. Doc. 267, 51st Cong., 2d sess.
                 ized (a) hydraulic mining under its regulation in the     Ex. Doc. 98, 47th Cong., 1st sess.
                 drainage areas of the Sacramento and San Joaquin
                 Rivers, if possible without injury to the naviga-
                 bility of these river systems or to lands adjacent
                 thereto; and (b) preparation of plans by the Com-
                 mission for improvement of the navigability of these
                 river systems, and flood and debris control therein.
Feb. 27, 1907 1 Authorized California Debris Commission to permit         (Amendment of sec. 13 of act ap-
                 hydraulic mining without construction of impound-         proved Mar. 1, 1893.)
                 ing works, provided there is no injury to the naviga-
                 bility of the above river systems or the lands ad-
                 jacent thereto.
June 19, 1934 2 Amended act of Mar. 1, 1893, which provides for con-      (Amendment of secs. 18 and 23 of
                 struction of debris dams or other restraining works        act approved Mar. 1, 1893.)
                 by the California Debris Commission and collection
                 of a 3-percent tax on the gross proceeds of each mine
                 using such facilities, so as to eliminate this tax and
                 substitute an annual tax per cubic yard mined,
                 obtained by dividing the total'capital cost of each
                 dam, reservoir, and rights-of-way, by the total
                 capacity of the reservoir for restraint of debris; and
                 authorized revocation of commission orders permit-
                 ting such mining, for failure to pay this annual tax
                 within 30 days after its due date; and also authorized
                 receipt of money advances from mineowners to aid
                 such construction, to be refunded later from the an-
                 nual payments of yardage taxes on material mined.
June 25, 1938 J Added at the end of sec. 23 of above act, a provision     (Further amendment of sec. 23 of
                 that the Secretary of the Army is authorized to enter      act approved Mar. 1, 1893.)
                 into contracts to supply storage for water and use of
                 outlet facilities from debris storage reservoirs for
                 domestic and irrigation purposes and power devel-
                 opment, upon such conditions of delivery, use, and
                 payment as he may approve, these payments are
                 to be deposited to the credit of such reservoir proj-
                 ect, reducing its capital cost to be repaid by tax on
                 mining operations.

1Public No. 137 (H. R. 13367).
2 Public No. 425, 73d Cong. (H. R. 1503).
8 Public No. 716, 75th Cong., 3d sess. (H. R. 9881).




    For latest published map, see Annual Report for 1913, page 3170,
and Rivers and Harbors Committee Doc. 50, 74th Congress, 1st ses-
sion.
     RIVERS AND HARBORS-CALIFORNIA DEBRIS COMMISSION                                          1563
   Local cooperation. Mine owners are required to bear all ex-
penses incurred in complying with the orders of the Commission
for regulation ot mining and restraint of debris.
   Operations and resutts aurng fiscal year. Inspections of hy-
draulic mines were accomplished to determine the rate of debris
movement into the debris-restraining basins and/or reservoirs
and compliance of the mine owners with the requirements of the
licenses issued. Cost of these inspections, regulation of hydraulic
mining, issuance of licenses, and other administrative work was
$7,116 for the fiscal year for maintenance. Administrative work
overlaps that of improvements 2, 3, and 4, hereunder and that of
the Sacramento Engineer District.
   Condition at end of fiscal year. The Commission has received
1,284 applications for hydraulic mining licenses; 22 mines are
licensed, of which 6 use storage behind Government debris dams.
Surveys have been made of those portions of Yuba, Feather, Bear,
and American Rivers containing large deposits of mining debris;
of active mines, except those on the North Fork of Yuba River
above Bullards Bar Reservoir; and of Bullards Bar and Combie
Reservoirs, to determine the rate of debris movement into the
several reservoirs.
   Work remaining to be done is, in general, the continuation of
the above or similar operations. The total cost of all work to June
30, 1954, was $748,501, for maintenance.
                                  Cost and financial summary

                                         Fiscal year ending June 30                    Total to June
                                                                                      30, 1954, includ-
                                                                                      ing fiscal years
                           1950         1951        1952        1953       1954        prior to 1950


Maintenance:
   Appropriated --------   $15,000 ..                $5, 500     $6, 500    $8, 000           $749, 479
   Cost-----------------    14,061       $4, 927      6,585       7, 814     7,116             748,501



   2. TREATMENT OF THE YUBA RIVER DEBRIS SITUATION-
              RESTRAINING BARRIERS, CALIF.
   Location. The works are on the Yuba River between Marys-
ville and where the river emerges from the foothills, near Ham-
monton, some 10 miles easterly from Marysville, or about 9 miles
below the Narrows. (See U. S. Geological Survey topographic map
of the Sacramento Valley, California.)
   Existing project. This provides for storage of mining debris
within the bed of the Yuba River by means of construction of
Daguerre Point Dam, a debris barrier, and by the restraint of flow
channel to narrow limits by means of training walls and other reg-
ulation works. The object of storing this debris in the Yuba River
-a    nonnavigable stream-is to keep it from passing into the
Sacramento and Feather Rivers to the detriment of navigation
therein. The variation in water levels due to floods is about 12
feet. The total cost of new work, completed in 1935, was $723,259,
of which $361,482 was from United States funds and $361,777 from
funds contributed by the State of California. The latest (1953)
approved estimate for annual cost of maintenance is $30,000, of
1564     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

which $15,000 is from local interests. (For details of this project
in its original form, see Annual Report, 1917, p. 1810, "Previous
projects.")
    The existing project was adopted in a rather indefinite form by
the River and Harbor Act of June 3, 1896, and in its more definite
form by the River and Harbor Act of June 13, 1902 (H. Doc. 431,
56th Cong., 1st sess.). (For the latest published map, see U. S.
Geological Survey topographic map of the Sacramento Valley,
Calif.)
    Local cooperation. Requirements of local cooperation are be-
ing complied with, progressively with the work. The State of
California contributes annually an amount equal to the Federal
allotment.
    Operations and results during fiscal .year. Maintenance: Op-
erations during the year included condition and operation inspec-
tions and surveys, including maintenance of gages and gage read-
ings; preparation of plans and specifications, and repairs to deck-
ing on Daguerre Point Dam, all of which were accomplished by
hired labor. Clearing and snagging of Yuba River was accom-
plished by hired labor and rented equipment. In addition, bank
protection was accomplished along Yuba River, at mile 5.6 on the
left bank, and above Simpson Lane Bridge on the right bank, by
contract. Total cost of maintenance during the fiscal year was
 $61,059, of which $30,529 was United States funds and $30,530
contributed funds.
    Condition at end of fiscal year. Construction of the project was
initiated in November 1902 and completed in 1935. Three train-
ing walls, having a total length of 85,100 feet and providing two
500-foot-wide channels, were built, partly by gold-dredging com-
panies and partly by the United States. A cut was made through
Daguerre Point and a concrete spillway constructed therein. The
channel between Marysville and the training walls were cleared of
obstructions. Dikes were built to block off old sand channels. The
project has been maintained in a satisfactory condition suitable to
the purpose intended and the result has been to hold in the Yuba
River millions of cubic yards of mining debris which would other-
wise have passed into the channels of Feather and Sacramento
Rivers to the detriment of navigation. Regulation of the river
necessitates annual clearing in the channel to provide adequate
capacity for flood flows, and the construction of bank revetment
or current deflection works to prevent erosion. The State of Cali-
fornia annually contributes an amount equal to the Federal funds
for maintenance work.
   The Yuba Consolidated Gold Fields was issued a Department of
the Army permit in 1944 for dredging a 600-foot channel which
would replace the two 500-foot channels above Daguerre Point
Dam. The new channel will give almost a 90 ° approach for flows
toward the crest of the dam. Work under the permit is approxi-
mately 35 percent complete.
     RIVERS AND HARBORS-CALIFORNIA DEBRIS COMMISSION                                                              1565
   The total cost of the project to June 30, 1954, was as follows:

                         Funds                                    New work            Maintenance              Total

United States------   -------------------------------                    $361, 482           $413,323             $774, 805
Contributed-----....----------------------------------                    361, 777            413, 271             775, 048
      Total...----------------------------------------                    723, 259            826, 594           1,549, 853


                                         Cost and financial summary
                                          UNITED STATES FUNDS


                                                Fiscal year ending June 30                                Total to June
                                                                                                          30, 1954, includ-
                                                                                                          ing fiscal years
                                 1950          1951           1952             1953            1954        prior to 1950


New work:
   Appropriated--------     --      .-        ----------------------.
                                                     .    .     ...-                                              $361,482
   Cost -------------      -----------                     ----------- -----------
                                                      .------------                      ----------                361, 482
Maintenance:
   Appropriated.-.......         $15, 000       $9, 207       $52, 554        $30, 000        $15, 000             415,518
   Cost---------------            16, 466        -646          58,158          19, 408          30, 529            413 322



                                         Cost and financial summary
                                            CONTRIBUTED FUNDS

                                                Fiscal year ending June 30                                Total to June
                                                                                                          30, 1954, includ-
                                                                                                          ing fiscal years
                                 1950          1951           1952            1953            1954         prior to 1950


New work:
   Appropriated......-----------------------------------------------------------    $361, 777
                  --------------------------- ----------
   Cost----------..............                   ............------------....       361,777
                                                                    .......------------
Maintenance:
   Appropriated-.......          $15,000       $15,000        $45, 000        $30, 000        $15, 000             415, 223
   Cost-----------------          24,137         5,760         58,158          19,464          30, 530             413,271



            3. SACRAMENTO                 RIVER AND TRIBUTARIES,                                      CALIF.
                                         (DEBRIS CONTROL)
   Location. The project reservoirs are to be constructed in the
watersheds of the Yuba, Bear, and American Rivers, Calif. (See
U. S. Geological Survey sheets for the basin areas, seven in num-
ber.)
   Existing project. The project was designed to permit the re-
sumption of hydraulic mining on a substantial scale and provides
for the construction of four reservoirs at the following sites: (1)
The Harry L. Englebright (Upper Narrows) Dam on Yuba River
 (completed in 1941) ; (2) the North Fork Dam on the North Fork
of American River (completed in 1939) ; (3) a site on the Middle
Fork of American River; and (4) a site on Bear River. The esti-
mate of cost for new work (1935 price index) is $6,945,000. The
latest (1953) approved estimate for annual cost of maintenance is
$25,000.
1566     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

    The existing project was adopted by the River and Harbor Act
of August 30, 1935 (Rivers and Harbors Committee Doc. 50, 74th
Cong., 1st sess.). For latest published map, see the project docu-
ment.
   The act approved November 6, 1945, provided that the dam con-
structed at the Upper Narrows site on the Yuba River, in the
State of California, should thereafter be known and designated as
the Harry L. Englebright Dam.
    Local cooperation. Satisfactory assurances were to be fur-
nished the Secretary of the Army for repayment of the capital cost
of the reservoirs from taxes on material hydraulically mined, under
licenses, and impounded in these reservoirs. These have been fur-
nished and accepted for sites (1), (2), and (3) above. Litigation
involving mining interests prevented local interests from furnish-
ing the necessary guarantees for reimbursement of the cost of a
dam at the Dog Bar site on Bear River, site number (4) above.
    Operations and results during fiscal year. Maintenance: Op-
erations during the year included maintenance and operation of the
Harry L. Englebright and North Fork Dams and appurtenant serv-
ice facilities; preparation of plans and specifications; and condition
and operation inspections and studies, all of which were accom-
plished by hired labor. In addition, construction of new care-
taker's quarters, garage, and water supply system at Englebright
Dam was accomplished by contract. Total cost for maintenance
during the fiscal year was $39,392, of which $10,000 was from
regular funds and $29,392 from Hydraulic Mining in California
funds.
   Condition at end of fiscal year. The existing project is 76 per-
cent complete. Construction of the North Fork Dam and Reservoir
was initiated in 1937 and completed and in use at the end of the
fiscal year 1939; additional work of excavation and reinforcement
of the left abutment of the dam was done in the fiscal year 1941.
The reservoir is located on the North Fork of the American River
about 5 miles northeast of the city of Auburn and 40 miles north-
east of Sacramento. The dam is 155 feet high, 620 feet long, and
the reservoir has a debris storage capacity of 26,000,000 cubic
yards. Construction of the Harry L. Englebright Dam was ini-
tiated in 1937 and completed in January 1941; the reservoir has
been in use for storage of hydraulic mining debris. Minor finish-
ing work was completed under supplementary agreement; repairs
to footings and abutments and improvement of grounds were com-
pleted in 1944. The reservoir is on the Yuba River about 20 miles
northeast of the city of Marysville. The dam is 260 feet high,
1,142 feet long, and the reservoir has a debris storage capacity of
118,000,000 cubic yards. Construction of the Ruck-A-Chucky Dam
site on the Middle Fork of American River was initiated in 1939
but was abandoned in 1940 due to construction difficulties; settle-
ment of the contract was completed; and field investigations were
made and report rendered with a view to the selection of another
site. Work was postponed on the Dog Bar site on Bear River due
to litigation involving mining interests which prevented local in-
       RIVERS AND HARBORS-CALIFORNIA DEBRIS COMMISSION                                                                           1567
terests from furnishing the necessary guarantees for reimburse-
ment of the cost of the dam, and a review of the report in the
project document was made, giving consideration to alternative lo-
cations of the proposed dam. This review has been reassigned.
    The primary purpose of the project was to make possible the
resumption of hydraulic mining in the tributary watershed for
which local interests are required to reimburse the United States
according to the volume of debris contributed. However, hydraulic
mining activity has practically ceased during recent years. Annual
maintenance activities are required to protect the Federal invest-
nient and, in addition, maintenance of the project benefits the
downstream navigation projects, primarily the Sacramento River
Project, in that it prevents debris deposits in these channels and
thus reduces the annual maintenance costs for the Sacramento
River navigation channel.
    Maintenance of this project also helps to maintain flood-channel
capacities in the downstream river reaches. In the case of Harry
L. Englebright Dam and Reservoir an additional benefit is realized
through the use of the head created for the generation of hydro-
electric power. An existing contract with the Pacific Gas and
Electric Company calls for payment to the Federal Government
of $18,000 per year for the first 30 years and $48,000 per year after
that in return for the use of head at Englebright Dam for genera-
tion of hydroelectric power. Total payment through December 31,
1952, amounts to about $180,000; these funds are paid directly to
the Secretary of the Treasury of the United States for deposit in
a lfiind known as the "Debris Fund."
    The total cost of the project to June 30, 1954, was as follows:
                                  Funds                                        New work                 Maintenance           Total


United States:
Regular funds................                                                 $5, 291, 375
                                          .............----------------------------------                   $284, 992         $5, 576, 367
Hydraulic mining in California ........--------------------- _              __    __     ___                101, 897             101, 807
       Total_----____           -------------.-      _-    ...                        5, 291, 375            386, 799           5, 678, 174



                                                  Cost and financial summary

                                                                 Fiscal year ending June 30                              Total to June
                                                                                -..      ..   . . ..           _         30, 1954. includ-
                                          1950.1951                        19520-             195351934                  ing fiscal years
                                            5               1951           1                                 1954          priorto 1950


New work:                                                                                                                          291
   -Appropriated-------              --------- ------------------------                             -       ----------        $5, 291 375
   Cost
Maintenance:
                                                                                                                              I5, 291   375
                            .
    Appropriated .. _                     $62, 153        -$21, 311        $ 6,000            $51,760        $32,548            2 396,142
    Cost       ...                         16,010            13,044 i       15,333             40,045         39,392            8 386, 799

 ' Regular funds.
s Includes $284,992 from regular funds and $111,150 from hydraulic mining in California funds.
a Includes $284,992 from regular funds and $101,807 from hydraulic mining in California funds.
4 Based on 1935 price index.

Other new work data: Estimated additional amount needed to be ap-
  propriated for completion of existing project---  __---------   4 $1, 653,625




         Sig 50--1567.1598
1568     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

        4. SACRAMENTO RIVER, CALIF., FLOOD CONTROL
   Location. The works covered by this improvement are on the
Sacramento River and tributaries in north central California from
Collinsville to Ord Bend, a distance of 184 miles.
   Previous project. Improvement of the original project for
Sacramento River was previously performed under the title of
"Alleviation of Debris Conditions in the Sacramento and Feather
Rivers, California." Debris resulting from hydraulic mining opera-
tions and natural erosion had obstructed the channels of these
rivers by raising the river beds and reducing the capacity to such
an extent that the streams broke through their banks and over-
flowed large areas during high floods, increasing the shoaling in the
channels themselves. The large deposits of debris in the river
channels and its variable movement downstream had impaired
their navigability. The construction and operation of hydraulic
dredges was authorized with the object of removing deposits from
the Sacramento River to improve navigation, with no definite limits
in depth, width, or location of the work being prescribed. Work
was accomplished from the mouth of the Sacramento River, in
Suisun Bay at Collinsville, to Rio Vista, 14 miles above, and con-
sisted of channel enlargement and levee construction. Local in-
terests were required to contribute an equal amount toward the
cost of the work and, in addition, to provide all rights-of-way for
levees and spoil banks free of cost to the United States. These
requirements were fully complied with. In addition, the State of
California constructed a retaining embankment for spoil deposit.
This minor project was absorbed in the existing project. The orig-
inal project was adopted by the River and Harbor Act of June 25,
1910 (in accordance with report of California Debris Commission
dated June 30, 1907, and printed in Annual Report for 1907, page
2262). For further details, see Annual Report for 1917, page 1815,
and Annual Report for 1938, page 1995.
   Existing project. The Sacramento River Flood Control Proj-
ect is a comprehensive plan of flood control for the Sacramento
River and the lower reaches of its principal tributaries. The im-
provement extends along the Sacramento River from Ord Bend in
Glenn County, Calif., downstream to its mouth at Collinsville at
the upper end of Suisun Bay, a distance of 184 miles, and comprises
a system of levees, overflow weirs, drainage pumping plants and
flood bypass channels or floodways designed to carry the surplus
floodwaters without inundation of valley lands. The project pro-
vides for the enlargement of the Sacramento River below the
mouth of Cache Slough to carry the entire flood discharge of the
river basin; for making two cutoffs between the mouth of the
Feather River and Colusa; for the construction of four bypass
weirs, and reconstruction of Tisdale Weir; for construction of
drainage outfall gates at Butte Slough and at Knights Landing; for
the construction of levees along certain reaches of the main river
and tributaries; for construction of three drainage pumping plants
on the east side of Sutter Bypass; for construction of bank protec-
tion works and levee setbacks on the main river and tributaries
from Ord Bend to Collinsville; for maintenance, during the con-
struction period, of the enlarged river channel below Cache Slough,
         FLOOD CONTROL-CALIFORNIA DEBRIS COMMISSION             1569
including revetment of the banks of the enlarged channel, and for
operation and maintenance of gaging stations during the same
period on navigable rivers and streams. The project also includes
channel clearing, rectification, snagging, and bank protection along
the Sacramento River and tributaries in Tehama County from Red
Bluff southerly.
    Approximately 980 miles of levee construction are involved in
the project. When completed, the project will provide adequate
flood protection to about 800,000 acres of highly productive agricul-
tural lands and to the cities of Colusa, Marysville, Sacramento and
North Sacramento and numerous smaller communities. It will
make possible the reclamation of swamps and other land which can
be developed to a high degree when protection against flood hazard
is assured.
    The above levee improvements were supplemented by works au-
thorized by the Flood Control Acts of December 22, 1944, and May
17, 1950 (H. Doc. 649, 78th Cong., 2d sess., and H. Doc. 367, 81st
Cong., 1st sess.). The levee construction and reconstruction pro-
vided for in these authorizations, including levee protection of
Upper Butte Basin and multipurpose reservoirs, are reported upon
by the Sacramento District under Improvement No. 8, "Sacra-
mento River and tributaries, from Collinsville to Shasta Dam,
Calif.", page 1370.
    The latest approved estimate (July 1954) of Federal cost for the
existing project (exclusive of the improvements authorized by the
Flood Control Acts of December 22, 1944, and May 17, 1950), in-
cluding new work and maintenance, is $64.400,000, for construc-
tion. In addition, local interests have contributed for project work
a total of $4,949,438 for levee construction, bank protection works,
and levee setbacks, of which $4,939,752 was for new work and
$9,686 for maintenance.
    Overation and maintenance of the project after completion will
be the responsibility of local interests; as units of the project are
completed they are transferred to agencies of the State of Cali-
fornia for operation and maintenance.
    The estimated cost (1954) to local interests for new work is
$104,000,000, which includes the costs of levees built by local in-
terests, lands, easements, rights-of-way, and highway, railroad,
and bridge alterations.
    The existing project was adopted by the Flood Control Act of
March 1, 1917 (H. Doc. 81, 62d Cong., 1st sess., as modified by
Rivers and Harbors Committee Doc. 5, 63d Cong., 1st sess.), and
modified by the Flood Control Act of May 15, 1928 (S. Doc. 23, 69th
Cong., 1st sess.), the River and Harbor Act of August 26, 1937
 (Senate committee print, 75th Cong., 1st sess.), and the Flood Con-
trol Act of August 18, 1941 (H. Doc. 205, 77th Cong., 1st sess.).
    Local cooperation. The Flood Control Act of May 15. 1928,
provided that local interests were to contribute one-half the cost
of construction of project levees, estimated at $3,191,500, and fur-
nish the lands, rights-of-way, and easements therefor.
    The modified project which was adopted in the River and Har-
bor Act of August 26, 1937, provided that the State of California,
should execute and maintain the remainder of the general flood
1570     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

control project, now being done or to be done by the United States,
and make illegal any levee, ditches, or other works in the bypasses
or on the lands reserved for overflow that might reduce or impede
the flood runoff, unless approved by the California Debris Com-
mission; should hold and save the United States free from dam-
ages due to construction works: And provided further, That the
bank revetment for protection of levees above Cache Slough, and
the levee reconstruction recommended in the project document
 (Senate committee print, 75th Cong., 1st sess.), should not be
undertaken until the State of California, political subdivisions
thereof, or responsible local agencies have agreed to provide with-
out cost to the United States all lands, easements, the rights-of-
way for said works, including the cost of all alterations to high-
ways, road crossings, and drainage and irrigation facilities inci-
dent to the work, and shall have contributed one-third of the cost
of bank revetment and levee reconstruction, with the understand-
ing that the contribution of funds will be made as required by the
progress of the work; and the State of California was to undertake
the operation of the movable top of Sacramento Weir in accordance
with the schedules established by the California Debris Commis-
sion.
   The modification of the project authorized in the Flood Control
Act of August 18, 1941, relieves local interests of all future con-
struction costs under the existing project, but requires them to
give assurances satisfactory to the Secretary of the Army that
they will (1) provide all needed lands, easements, and rights-of-
way free of cost to the United States, (2) bear the expense of
necessary highway,. railroad, and bridge alterations, (3) hold and
save the United States free from claims for damages resulting
from construction of the works, and (4) maintain and operate all
flood control works after completion, in accordance with regula-
tions prescribed by the Secretary of the Army.
   The requirements are being complied with as needed.
   Operations and results durng fiscat year. New work: A con-
tinuing contract was completed under which levee construction,
bank protection, and road surfacing was accomplished along the
left bank, Sacramento River, near Freeport. The channel of lower
Butte Creek was straightened, by hired labor, and work was ac-
complished at the following locations during the fiscal year, by
contract: (1) Bank protection at 5 sites along left bank Sacramento
River, between Isleton and Walnut Grove; (2) Fish ladder con-
struction at Howard Slough diversion structure along lower Butte
Creek, approximately 6 miles east of Butte City; and (3) Sutter
Bypass drainage ditch fill between Nelson Slough and Feather
River, approximately 3 miles west of Nicolaus, Calif.
   In addition, levee construction and bank protection work was
initiated during the fiscal year as follows: (1) Stockpiling of
dredged material for enlarging existing levee on Hastings Tract,
approximately 7 miles north of Rio Vista, by hired labor and rented
clamshell dredge; (2) Levee construction, bank protection and
road surfacing at 7 sites along Sacramento River, between Colusa
and Knights Landing, by contract; (3) Levee enlargement and
bank protection, right bank, Sacramento River, and Sutter Slough
          FLOOD CONTROL-CALIFORNIA       DEBRIS COMMISSION        1571
on Merritt Island, by contract; (4) Levee strengthening and bank
protection, right bank, Sacramento River, Grand Island, between
Steamboat Slough and Junction Point, by continuing contract; (5)
Construction of west levee, Sacramento River, Reclamation Dis-
tricts No. 307 and No. 765, Yolo County, Clarksburg to Y Street,
by contract; (6) Levee construction, west levee Feather River at
Cox Ranch upstream to opposite Rio Bonito Station, Butte County,
by continuing contract; (7) Levee construction along left bank of
Sacramento River from Junction Point to Mayberry Slough and
along both levees of Three Mile Slough (Sherman Island), by con-
tract; and (8) Levee strengthening and bank protection, Sacra-
mento River, along Sutter Island near Courtland, by contract.
    Contracts were awarded for work to be accomplished at the fol-
lowing locations: (1) Levee construction and bank protection, east
levee, Sacramento River, Georgiana Slough to Freeport, by con-
tinuing contract; (2) Emergency bank protection, Sacramento
River, mile 92.7 to 99.9, right and left banks, in vicinity of Knights
Landing, Sutter and Yolo Counties, by continuing contract; and
 (3) Normal bank protection at 6 sites along right and left banks
Sacramento River, between mile 103.8 and 129.5, Sutter and Yolo
Counties, by continuing contract. Construction was not initiated
during the fiscal year under the above contracts.
    Miscellaneous work, including surveys, explorations and prepar-
ation of contract plans and specifications, was accomplished by
hired labor during the year. Hired labor was also utilized in the
preparation of operation and maintenance manuals and as-built
drawings for completed portions of the project.
    A total of 2,105,674 cubic yards embankment was placed in
levees along the project waterways during the fiscal year.
    There was no maintenance work accomplished during the year.
    Total Federal cost of all new work during the year was $1,826,-
601.
    Miscellaneous construction (nonproject) accomplished for the
State of California at its expense in connection with acquisition of
rights-of-way for levees cost $163,493, for new work.
    Total cost of all work during the fiscal year was $1,990,094, of
which $1,826,601 was from United States funds (regular approprie
ations) and $163,493 from contributed (nonproject) funds.
    Condition at end of fiscal year. Construction of the existing
project, initiated in fiscal year 1918, is approximately 71 percent
complete. The channel improvement accomplished to date has
produced a channel with a capacity of 579,000 cubic feet per second
in the Sacramento River below Cache Slough. In addition, dis-
charges up to 21,000 cubic feet per second can be diverted from
the Sacramento River through Georgiana Slough. Completed ma-
jor project items include approximately 690 miles of levees; 5 weirs
with a combined discharge capacity of 602,000 cubic feet per sec-
ond; 2 cutoff channels; 2 sets of outfall gates; channel improve-
ment and clearing in the Sacramento River, Butte Creek, Putah
Creek, and Sutter and Tisdale Bypasses; construction of two main
bypasses or floodways and secondary bypasses at Tisdale and Sac-
ramento Weirs and at Wadsworth Canal; construction of Knights
Landing Ridge Cut and of Cache Creek Settling Basin; a consider-
1572            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

able amount of river levee bank protection, installation of gaging
stations; and enlargement of Sacramento River below Cache
Slough.
   A total of 85,445,870 cubic yards embankment has been placed
in levees along the project waterways. The cutoffs at Collins Eddy
and between Wild Irishman and Kinneys Bends were made in 1918
and 1919, respectively. Sacramento Weir was completed in 1917,
Fremont Weir in 1924, Tisdale and Moulton Weirs in 1932, and
Colusa Weir in 1933. Outfall gates at Knights Landing were con-
structed in 1930 and at the mouth of Butte Slough in 1936. Pump-
ing plants on Sutter Bypass were completed in 1944. Work items
with reference to the clearing, snagging, rectification of channels,
and bank protection on Sacramento River and tributaries in Te-
hama County and from Red Bluff southerly, provided for by Flood
Control Act of August 18, 1941, were accomplished in fiscal years
1947, 1948, 1949, and 1951. The total cost of this work was $126,-
355 of which $30,144 was by contract and $96,212 by hired labor.
   Work remaining to be accomplished includes completion of levees
 (along Sacramento, American, Feather, and Yuba Rivers, and the
adjoining bypasses and tributaries), bank protection, and clearing
overflow channels and bypasses; clearing, snagging, and rectifica-
tion of channels on Sacramento River and tributaries in Tehama
County and from Red Bluff southerly; and dredging of the enlarged
flood channel below Cache Slough, with continued maintenance
dredging until that part of the project below Cache Slough is com-
pleted.
   The total cost of the existing project to June 30, 1954, is as
follows :

                            Funds                                              New work         Maintenance           Total

United States funds:
  R egular appropriations_............         ....   . .....              .    $42,068, 620         $1, 979, 104    1$44, 047, 724
  Public works funds_-..........___ __      ... -.
                                         ___---         ....-                     1, 486, 469                           1, 486, 469
      Total United States funds- .----...-                  ......-.            43, 555, 089           1, 979, 104     45, 534, 193
C ontributed funds, project work     .....            ..... _... _ . .           4, 939, 752                9, 686      4,949, 438

      Total funds, project work ..               - -..............-.....        48, 494, 841           1, 988, 790     50, 483, 631
Contributed funds (nonproject)_-.... ---......                    ..------        2, 732, 369                   ,
                                                                                                ..............----      2, 732, 369
      Total, all funds------....................----                 .           51, 227, 210          1, 988, 790     53, 216, 000

   1 Does not include $429,671, representing book value of plant purchased with previous project funds and
transferred to the existing project without reimbursement.
                FLOOD CONTROL--CALIFORNIA                               DEBRIS COMMISSION                             1573
                                       Cost and financial summary
                                        UNITED STATES FUNDS

                                                Fiscal year ending June 30                                  Total to June
                                                                                                            30, 1954, includ-
                                                                                                            ing fiscal years
                                1950           1951              1952          1953              1954        prior  to1950

New work:
   Appropriated-         $3,260,000
                     -----.               $2,016, 500         $ 990,000     $1, 000,000       $3, 806,066          $46, 312,394
   Cost-------------      2,377,991        2,341,171           1,839,652     1,553,518         1,826,601            44,235,089
Maintenance:
              _
    Appropriated     -.         340,000   .....-     .        -10,000         _
                                                                              -   -2_            -6,066              1, 979,104
    Cost_____________ __        327,707        14,901              6,106              42 __         _____            1,979,104

  1a. Includes appropriation and cost of $680,000 for new work for previous project.
    b. Includes $1,486,469 public works funds for new work for existing project.
  s Based on latest approved estimate (1954).
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954_
    Appropriated for succeeding fiscal year ending June 30, 1955 ....
                                                                                              -                  $31,171
                                                                                                               3,000,000
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955_- --------     -------------------------                                                   3,031,171
    Estimated additional amount needed to be appropriated for com-
      pletion of existing project    ________________                                                       213,788,502


                                       Cost and financial summary
                                        CONTRIBUTED FUNDS

                                                Fiscal year ending June 30                                   Total to June
                                                                                                            30, 1951, includ-
                                                                                                            ing fiscal years
                                1950           1951              1952          1953              1954        prior to 1950 1


New work:
   Appropriated_              $899, 576                   -     $300, 000                       $700,000           $9,094,571
   Cost _........              299, 881        $99, 216          525,326      $164,132           163,493            8,352,121
Maintenance:
   Appropriated                            .                     .-                     ---             .-------         9,686
    Oost _-_
          - -                                                                                                            9,686


   1a. Includes $680,000 for new work for previous project.
    b. Includes $310,801 voluntary contribution for bank protection for existing project.
    c. Includes a total of $4,949,438 for existing project work for levee construction, bank protection works,
and levee setbacks, of which $4,939,752 was for new work and $9,686 for maintenance.
    d. Includes the following amounts for voluntary contribution for other appurtenant work desired by
local interests for the existing project: Appropriation, $3,164,018 and cost, $2,421,568.
Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954-_----------     $441,041
    Unobligated balances available for succeeding fiscal year ending June
      30, 1955------------------------------------------------441,041
ANNUAL REPORT OF THE PRESIDENT, MISSISSIPPI
RIVER COMMISSION, FOR THE FISCAL YEAR ENDING
JUNE 30, 1954

    Commission headouarters. Mississippi River Commission
Building, Vicksburg, Miss., post office box 80.
    Commissioners. The commissioners during the fiscal year were
Brig. Gen. John R. Hardin, United States Army, president; Rear
Adm. Leo O. Colbert, United States Coast and Geodetic Survey,
retired; Albert L. Culbertson, DeWitt L. Pyburn, civil engineer;
Eugene F. Salisbury, civil engineer; and Brig. Gen. Herbert D.
Vogel, United States Army.
    Jurisdiction. The Mississippi River Commission, created by
act of Congress approved June 28, 1879, is charged, under the di-
rection of the Secretary of the Army and supervision of the Chief
of Engineers, with prosecution of improvements for flood control
of the Mississippi River and of its tributaries and outlets in its
alluvial valley, so far as they are affected by Mississippi River
backwater, between Head of Passes, La. (mile 0), and Cape Girar-
deau, Mo. (mile 1,016), and with prosecution of improvements in
the interest of navigation between Cairo, Ill. (mile 964), and Baton
Rouge, La. (mile 232). It also is charged with prosecution of
certain flood control works on the Mississippi River and on tribu-
taries so far as they are affected by backwater, between Cape
Girardeau and Rock Island, Ill. (mile 1,446); more specifically
chargedr with control of headwater floods of the St. Francis and
Yazoo Basins including L'Anguille River and Yazoo tributaries,
respectively; West Tennessee tributaries; protection of the Cache
Basin, Mo. and Ark.; the Grand Prairie Region and Bayou Meto
Basin, Ark., including water supply improvements therein; por-
tions -of the backwater areas near the mouths of the St. Francis,
theWhite, the Yazoo, and the Red Rivers, and with improvements
of Bayous Rapides, Boeuf, and Cocodrie, La., Boeuf and Tensas
Rivers, Bayou Macon and Bayou Lafourche, La. and Ark., and
Lake Pontchartrain Jefferson Parish, La. Backwater limits on
tributary streams are considered to be located where backwater
curves from the maximum Mississippi River flood intersect maxi-
mum flood flow lines of tributaries. Flood outlets from the Missis-
sippi River connection of the Gulf of Mexico consist of the Mor-
ganza-Atchafalaya Basin and Bonnet Carre floodways.
   Location and description. The Mississippi River rises in Lake
Itasca, Minn., flows in a general southerly direction for 2,350 miles,
and empties into the Gulf of Mexico. Its drainage area, about
1,245,000 square miles, embraces all or part of 31 States between
the Rocky and Appalachian Mountains and parts of two Canadian
Provinces. There are approximately 35,000 square miles in the
alluvial valley below Cape Girardeau, Mo., which were originally
subject to overflow, including former overflow areas designated as
the St. Francis, White Tensas, Atchafalaya, and Lafourche Basins
                                                           1575
1576     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

west of the river and the Yazoo and Pontchartrain Basins east of
the river. Observations made by the Mississippi River Commis-
sion to June 30 show approximate maximum and minimum dis-
charges between the levees as follows: Cairo to White River, 2,-
000,000 and 70,000 cubic feet per second; thence to Red River,
2,150,000 and 90,000 cubic feet per second; thence to the Gulf of
Mexico, 1,500,000 and 80,000 cubic feet per second in this Missis-
sippi River and about 650,000 and 12,000 cubic feet per second in
the Atchafalaya River. As the 1927 flood flow was not confined
between the levees, maximum discharges recorded do not include
the entire flow of the 1927 flood, the maximum of record below
White River. Low water stages, generally, obtain from August to
December. High water and flood stages usually occur in the late
winter or early spring, but great floods such as that of 1937 have
occurred as early as January in .the upper reaches of the lower
river. Extreme ranges in stages recorded at representative gages
are about 60 feet at Cairo; 53 feet at Memphis; 57 feet at Red
River Landing; and 23 feet at Carrollton. The river is nontidal
above the mouth of Red River, where amplitude of the tide rarely
exceeds 0.1 foot during extreme low water.

                          ORGANIZATION

   Office of the president. The president of the Mississippi River
Commission is its executive officer. One officer has been assigned
for duty in the office of the president as secretary of the commis-
sion.
   Authorized operations of the commission below Cape Girardeau
within the following limits are conducted by three Corps of Engi-
neers districts in accordance with approved directives and pro-
grams and congressional appropriations therefor.
   New Orleans district: Mississippi River project levees and river
channel stabilization as required from Head of Passes, mile 0,to mile
320, including south bank levee of Red River to Hotwells, La.; Bon-
net Carre and Morganza floodways; maintenance and improvement
of the Mississippi River navigation channel from Baton Rouge, La.
 (mile 232) up to mile 320; and the Baton Rouge Harbor extension
 (Devils Swamp Channel); Lake Pontchartrain, Jefferson Parish,
La., protection levees; Atchafalaya Basin floodway; and flood con-
trol and drainage improvements in Bayous Rapides, Boeuf, and
Cocodrie, in Bayou des Glaises, and Red River backwater area
within district limits.
   Vicksburg district: Mississippi River project levees and river
channel stabilization as required from the upper limits of the New
Orleans district's operations in the vicinity of Black Hawk, La., to
the Coahoma-Bolivar County line, Mississippi, on the left bank and
to the mouth of the Arkansas River, Ark., on the right bank in-
cluding the Arkansas River south bank levee to the vicinity of Pine
Bluff, Ark., and its north bank levee to the mouth of Plum Bayou,
Ark.; maintenance and improvement of the Mississippi River navi-
gation channel between miles 320 and 593, and the Vicksburg-
                    MISSISSIPPI RIVER COMMISSION                  1577
Yazoo area; flood control and drainage improvements in the Red
River backwater area including the leveed portion east of Black
River within district limits; Jonesville, La., Boeuf and Tensas
River and Bayou Macon Basins, Ark. and La., and Bayou La-
fourche, La.; Yazoo River Basin, Miss., including the backwater
area; Big and Little Sunflower Rivers, Deer Creek, and Steele
Bayou, Miss., and the Grand Prairie Region, and Bayou Meto Basin,
Ark., including provision for agricultural water supply.
   Memphis district: Mississippi River project levees and river
channel stabilization as required, from the upper limits of the
Vicksburg district's operations in the vicinity of the mouth of
White River to the north bank of Little River diversion channel,
Missouri (mile 1015), a few miles below Cape Girardeau, Mo., on
the right bank and to the Cache River diversion above Cairo, Ill.
 (mile 999), on the left bank including levees on the right bank of
the Ohio River up to the previous mouth of Cache River, Ill. (mile
7), with operations above Cairo, Ill., restricted to levee work. Main-
tenance and improvement of the Mississippi River navigation chan-
nel between miles 593 and 964 and the Memphis Harbor, Tenn.;
levees in the White River backwater area up to the vicinity of
Augusta, Ark.; levees and pumping plants at DeValls Bluff and
Des Arc, Ark.; channel improvements in Cache River Basin, Ark.;
improvement works in the St. Francis River Basin, Mo. and Ark.,
including backwater area, Little River diversion channel, Missouri,
L'Anguille River, Ark., and Obion and Forked Deer River Basins,
Tenn.
   Field operations of the commission above Cape Girardeau, re-
stricted to levee construction under section 6 of the 1928 Flood
Control Act (local interests contributing one-third of costs and
furnishing rights-of-way), are conducted within the following
limits by two Corps of Engineers districts of the Upper Mississippi
Valley Division which report direct to the commission on matters
within its jurisdiction:
   St. Louis district: Mississippi River (sec. 6) levees from the
upper limits of the Memphis district's operations to Clemons Sta-
tion, Mo. (mile 1266), on the right bank and Hamburg Bay, Ill.
 (mile 1227), on the left bank including the Illinois River to mile
120, near Havana, Ill., and the Missouri River to St. Charles, Mo.
 (backwater limits).
   Rock Island district: Mississippi River (sec. 6) levees from upper
limits of the St. Louis district's operations to Rock Island, Ill. (mile
1448).
                        PREVIOUS PROJECTS

  The project outlined in a report by the commission dated Febru-
ary 17, 1880, contemplated improvement of the channel to secure a
least depth of 10 feet at extreme low water by contraction of the
low water channel, protection of banks against caving, and control
of floodwater by levees. For further details, see page 1944, Annual
Report for 1932, and page 1682, Annual Report for 1937.
1578            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  Flood control general projects previously authorized which have
been incorporated as features of the project are listed below:

                                                                              For last full report see
    Acts                            Description                               Annual Report of the
                                                                               Chief of Engineers

June 22.1936    Bayou des Glaises diversion ditch, Louisiana_ _ ....    Page 1029, fiscal year 1946.
                Jonesville, La., levee retaining wall and drainage      Page 1007, fiscal year 1949.
                  structure.
                Clarendon to Laconia Circle on White River in           Page 892, fiscal year 1937.
                  Arkansas (portion below Big Creek).
                From North Little Rock, Ark. to Gillett, Ark. on the    Page 1053, fiscal year 1946.
                  north bank of Arkansas River (portion below
                  Plum Bayou).
Aug. 18, 1941   White River levees Augusta to Clarendon and De-         Page 1083, fiscal year 1946.
                                                           ----
                  Valls Bluff, Arkansas_- .............. -__     ....   Page 1084, fiscal year 1946.



                                     EXISTING PROJECT
   This provides for protection of the alluvial valley of the Missis-
sippi, lead of Passes to Cape Girardeau, from floods by means of
levees, floodwalls, floodways, reservoirs (in the St. Francis and
Yazoo Basins), bank stabilization and channel improvements in and
along the river and its tributaries and outlets insofar as affected
by backwater of the Mississippi River and for levee work between
Cape Girardeau and Rock Island. The project also provides for
bank protection, channel improvement, contraction works and
dredging to secure a navigable channel 12 feet deep and 300 feet
wide from Baton Rouge to Cairo. Improvements completed under
previous project and incorporated in the project are maintained in
accordance therewith. The total authorized cost, including the modi-
fications authorized by the act of May 17, 1950, is $1,292,748,500,
including maintenance charges through August 18, 1941. The es-
timated cost of annual maintenance is $15,000,000.
   Table A lists major Mississippi River improvements included in
the existing project; table B lists those on tributaries and outlets;
and table C contains data pertinent to dams and reservoirs.
                                MISSISSIPPI RIVER COMMISSION                                                1579
                            TABLE A.         Mississippi River improvements

                   Location

                                                             Improvement                          Remarks
  Mileage
above Head                 Locality
of Passes


    230-966   Baton Rouge-Cairo-............. Dredging where required- ...
     10-966   Venice, La.-Cairo-----------
                                 ............--         Revetment, contraction work__
      11-25   BaptisteColletteBayou-Ostrica,            Main line levee setback, left
               La.                                         bank.
      44-91   Bohemia, La.-New Orleans .--Main line levee and floodwall,
                                                           left bank.
     91-104   New Orleans .     ........------------------- do            -                 Authorized   by Pub-
                                                                                             lie Law     515, 81st
                                                                                             Cong.
    104-230   New Orleans-Baton Rouge ....               do.------------
        234   Baton Rouge Harbor........----------. Devils Swamp barge channel-...          Authorized   by Pub-
                                                                                             lie Law     858, 80th
                                                                                             Cong.
    432-718   Vicksburg-Lake View, Miss- ... Main line levee, left bank --..-
    718-731   Memphis Harbor-------_------       Closure,    Tennessee             Chute;
                                                                                        .

                                                                                           Authorized by Pub-
                                                   levee; harbor channels, etc.             lie Law 526, 79th
                                                                                            Cong.
     807-878 Tiptonville-Obion River_ ..-- Main line levee, left bank, levee                   Do.
                                                   extension and diversion of
                                                   Obion River.
     906-931 Slough Bend-Hickman, Ky-.... Main line levee, left bank .....
        10-81 The Jump-New Orleans--          . Main line, levee, right bank -.-
        81-96 New Orleans -------                     do .    .--
                                                               --------------.            Authorized by Pub-
                                                                                            lic Law 516, 81st
                                                                                            Cong.
      96-277 New Orleans-Morganza      -----. . .do_
                                                                                          Extends     up    South
     285301 Morganza-Old River_                           ......
                                                             _do             .......
                                                                                            bank. of Old River
                                                                                            to Barbre Landing.
     304-564 Old River-Cypress Creek, Ark_ ----.      _do                                 Joins Arkansas River
                                                                                            South bank levee.
     600-660 Henrico-Helena, Ark--------------        do -.--....
   671-1, 001 St.FrancisRiver-Commerce, Mo       .-...do .     ....------------------
1, 008-1, 446 Thebes, Ill.-Rock Island-.......Levees, both banks.---------....            Intermittent.
     127-129  Bonnet Carre, La., floodway.... Regulating spillway, left bank .
     277-285 Morganza, La., floodway-......      Regulating spillway, right bank.
          895 St, Johns Bayou, Mo ........-------Drainage floodgate ________-
          932 Hickman, Ky. .---..__...    .F_    Floodwall, left bank_.
     895-964 New Madrid-Birds Point, Mo .- Floodway, right bank_
          966 Cairo, Cairo drainage district ___ Floodwalls and levees ..........
          480 Lake Providence, La----------
                                      . ...      Filling Grant's Canal ..........Authorized by Pub -
                                                                                            lic Law 516, 81st
                                                                                            Cong.
          432 Vicksburg-Yazoo area.-             Levee, left bank ___----------           Authorized by Pub-
                                                                                            lic Law 391, 70th
                                                                                            Cong., as modified
                                                                                            by     Public    Law
                                                                                            526, 79th Cong.
                                                                                              __
1580              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

            TABLE B. Mississippi River tributary and outlet improvements

                         Location                                1




                                                                               Improvement                       Remarks
  Mileage
  above                           Locali ity
  mouth

                ATCHAFALAYA RIVER AND BASIN, LA.

            6    Below Morgan City__.                                Channel relocation_             _---   Bypass route for In-
                                                                                                              tracoastal Water-
                                                                                                              way traffic.
       6-18 -..-- do--------.                         ..    .        Levees, floodwall east of lower        Protection of land
                                                                      Atchafalaya River.                      east of Morgan
                                                                                                              City.
       6-18     -.. d o ............................                 Levees,    floodwall, drainage         Protection of inclosed
                                                                       structures,   and   pumping            areas west of Ber-
                                                                       plants.                                wick.
         18      Morgan City .....................                   Lock in Bayou Boeuf 1..........        Intracoastal Water-
                                                                                                              way.
     18-115      Morgan City-Morganza_               Levee, east protection, includ-
                                                     .........                                              Including lower Mor-
                                                       ing Morgan City floodwall.                             ganza guide levee.
    108-116      Lacour-Red Cross__                  Levee, upper Morganza guide.
     81-138      Alabama Bayou-Barbre Landing__      Levee, east bank Atchafalaya
                                                        River.
        133      Simmesport-Hamburg ............     Levee, fuse plug, west Atchafa-
                                                       laya floodway.
                 Coulee des Grues ___                Levee enlargement and culvert
                                                       extension.
                 Mansura to Wax Lake Outlet and      West Atchafalaya Basin protec-
                   Wax Lake (Outlet to Berwick).       tion levee.
    107-108      M elville -..... _ ................ Levee, ring.....
        133      Simmesport._ _-                     Levee, ring and drainage struc-
                                                       ture.
         32      Atchafalaya Bay-Six Mile Lake___ Outlet, Wax Lake_.-
     63-133      Bayou Garofler-Simmesport --..      Levee, west bank Atchafalaya
                                                        River.
         54      Bayou Sorrel 1-                     Lock, Bayou Sorrel ----                                Plaquemine-Morgan
                                                                                                              City alternate
                                                                                                              route, Gulf Intra-
                                                                                                              coastal Waterway.
        109      Bayou Latenache ....                                Drainage structure, Pointe Cou-        Through upper Mor-
                                                                      pee.                                    ganza guide levee.
         20      Berwick     1                                       Lock __         -                      Lower Atchafalaya
                                                                                                              River.
         26      Patterson_ __                                       Water system_                          Adjustment to pro-
                                                                                                              vide fresh water.
         32      Calumet                                             Floodgates -....                       2 floodgates, Bayou
                                                                                                              Teche-Wax Lake
                                                                                                              Outlet.
         50     I Charenton -                                        Floodgate and navigation chan-         Bayou Teche to
                                                                                                              Grand        Lake
                                                                      nel.
                                                                                                              through West
                                                                                                              Atchafalaya pro-
                                                                                                              tection levee.
         96      Bayou Courtableau_                                  Drainage control structuresD....
         97      Bayou Darbonne___                                   Drainage structure    _._....          Through West Atch-
                                                                                                              afalaya protection
                                                                                                             levee.
      18-81      Morgan City-Alabama Bayou .-                        Floodway, Atchafalaya Basin-..
     81-115      Alabama Bayou-Mississippi River_                    Floodway, Morganza-...........
     81-138      Alabama Bayou-Red River ......                      Floodway, West Atchafalaya --.
         50      Jaws-Lake Fausse Pointe .........                   Outlet, Charenton Drainage and         Restoration of drain-
                                                                       Navigation Canal protection           age west of West
                                                                       levee.                                Atchafalaya Basin
                                                                                                             protection levee.
      18-54     1Morgan      City-Bayou Sorrel Lock.                 Alternate channel, Plaquemine-         Channel east of East
                                                                       Morgan City alternate route           Atchafalaya pro-
                                                                       Gulf Intracoastal Waterway.           tection levee.
         32 Wax Lake Outlet_                                         Bridges, railway and highway_
         95  West Atchafalaya floodway .....                              do..do-
         95  Morganza floodway_                                  ----- do
        107 ....do ----                                               -   do---------------------------
                                                                          do
        115 ..--- do-..-------------------------
        128 Bayou des Glaises, West Atchafa-                                              I
                                                                     Diversion channel -------- -
                laya protection levee borrow pit.

  1 General data concerning the Bayou Boeuf, Bayou Sorrel, and Berwick locks where the Atchafalaya
Basin protection levees cross the Gulf Intracoastal Waterway, the alternate route to Plaquemine, La.,
and the lower Atchafalaya River (extension of Bayou Teche Waterway) respectively, are given in the
report on improvement of Rivers and Harbors in the New Orleans district.
                                     MISSISSIPPI RIVER COMMISSION                                                 1581
TABLE B. Mississippi River tributary and outlet improvements-Continued

                      Location


Mileage                                                                 Improvement                      Remarks
above                         Locality
mouth


                   BAYOUS RAPIDES, BOEUF                                                            Authorized by Pub-
                     AND COCODRIE, LA.                                                               lic Law 228, 77th
                                                                                                     Cong.
                  Bayou Courtableau-Bayou
                  Rapides Diversion Channel
     0-17   Bayou Cocodrie          -------------- Enlargement and realinement_..
    17-40   Bayous Cocodrie-Boeuf diversion_ New channel-__
    40-51   Bayou Boeuf.----.....--     --------   Enlargement and realinement_
    51-60   Bayous Boeuf-Rapides diversion_ New channel_.                 -

                          Bayou Cocodrie

    17-42   Upper Cocodrie-.....___------                      Enlargement, clearing and snag-
                                                                ging.
                            Bayou Boeu f

   87-107 Bayou Lamourie to Kincaid-._-_                       Enlargement, realinement, clear-
                                                                ing and snagging.
                              Structures

       40   Lecompte control structure, __... Fixed elevation structure..-....
       60   Bayou Rapides control structure - Gated structure_-----------
       87   Bayou Lamourie control structure- -. _ do----------
            Various..............-------------------- Railway, highway, and local
                                                       road bridges and pipeline
                                                       crossings.
                          RED RIVER, LA.

   82-145   Moncla-Hotwells ..............---                  Levee, south bank- ..........

                    RED RIVER BACKWATER

            Tensas-Cocodrie area..........---                  Levees, drainage channels, and
                                                                structures.
                        AMITE RIVER, LA.

            Amite River, La-..--..-----              ------.   Bank protection.____            .-   Authorized by Pub-
                                                                                                     lic Law 516, 81st
                                                                                                      Cong.
                  LAKE PONCHARTRAIN, LA.

            Lake   Ponchartrain,                  Jefferson    Flood protection-..............          Do.
             Parish, La.
                   ARKANSAS RIVER BASIN

            Grand Prairie Region and Bayou                     Water supply and drainage im-            Do.
             Meto Basin, Ark.                                   provements.

                     OUACHITA RIVER, LA.

       56   Jonesville, La ....................                Levees,    floodwall  pumping        Portion of levee built
                                                                 plant, and interior drainage         under sec. 6, Pub-
                                                                 structures.                          lic Law 391, 70th
                                                                                                      Cong., F. C. G.
                                                                                                      project authorized
                                                                                                      by Public Law
                                                                                                      738, 74th Cong.,
                                                                                                      Public Law 516
                                                                                                      81st Cong., places
                                                                                                      project under F.
                                                                                                      C. M. R. & T.
                                                                                                      (Sen. Doc. 117, 81st
                                                                                                      Cong., 1st sess).
  99-178    Monroe-Sandy Bayou__.............Levees, left bank.._________                           Intermittent, author-
                                                                                                      ized by sec. 6 of
                                                                                                      May 15, 1928 act.
     177    Bawcomville, La--....                               Levees, culverts, floodgates, and
                                                        ..-----------                               Work being accom-
                                                                   and pumping stations and           plished under sec.
                                                                   temporary flapgates.               6 of May 15, 1928
                                                                                                      act.
1582               REPORT OF CHIEF OF ENGINEERS.                                                       T. S. ARMY, 1954

TABLE B. Mississippi River tributary and outlet improvements-Continued

                                 Location

                                                                                         Improvement                              Remarks
Mileage
above                                          Locality
mouth



                     BOEUF AND TENSAS BASINS, LA.                                                                            Authorized by Pub-
                              AND ARK.                                                                                        lic Law 534, 78th
                                                                                                                              Cong., and Public
                                                                                                                              Law     526  79th
                                                                                                                              Cong.
                                           BOEUF RIVER

         0-32    .....................................                   Clearing.              ----    -   -..        ---   Public Law 516, 81st
                                                                                                                              Cong., modifies re-
                                                                                                                              quirements of local
                                                                                                                              cooperation.
   151-233        Above Bayou Lafourche ..........                       Enlargement and realinement,_
                  Canals 19, 43, ahd 81 and Big                          Channel improvement .-------- _
                   Bayou.

                                 Bayou Lafourche, La.
         0-63     Boeuf River (mile 32) to and                           Channel improvement and re-                            Do.
                   through Bayou Lafourche to                             alinement.
                   Boeuf River (mile 151).
                                 Big and Colewa Creek
         0-26     - ----- ------ ------ ----. - ------                   Clearing, snagging, and realine-
                                                                          ment.
                                                                         Enlargement, realinement_-.

                    Tensas River
    61-160 ..........
                    --                                                   Channel improvement_                                Public Law 516, 81st
                                                                                                                              Cong., modifies re-
                                           Bayou Macon                                                                        quirements of local
                                                                                                                              cooperation.
     0-170        To mouth of Ditch Bayou                                  Clearing and snagging__------
          123      Upper end Sandy Lake..                               I Levee ....-
                                                                                   -     - ---
          120      Small outlet, right bank ..-....                        Closure
          127     .... do ....  ...  .-                                   ---. do.
                                              Structures
                  Various                    . . - . . ___. .            Railway and highway bridges
                                                                          and pipeline crossings.
                      YAZOO RIVER AND BASIN,                    MISS.

     0-381        Yazoo River, below Arkabutla                           Channel improvement ..                         .    Including Tallahat-
                   Dam.                                                                                                        chie and Coldwa.
                                                                                                                               ter Rivers.
         0--64    Yalobusha River, below Grenada                        ----
                                                                          do-.............
                                                                                        ............
                   Dam.
         0-13     Yocona River, below Enid Dam_                           --- d o -----     -               -         - -    Above Panola-Quit-
                                                                                                                              man floodway.
         0-26     Little Tallahatchie River, below                       -..     do...                                          Do.
                    Sardis Dam.
         0-88     Cassidy Bayou, below Old Cold-                                      -
                                                                               ..d o ...-       - -     -               -    Including Moores
                    water River.                                                                                               Bayou,      Cutoff
                                                                                                                               Bayou, Whiting
                                                                                                                               Lake and outlet.
    75-366        Yazoo River below Prichard,                            Levee, right bank..                    ...          Intermittent.
                    Miss.
    75 345        Yazoo River, between Yazoo City                        Levees, left bank....                                  Do.
                    and Askew.
         0-24     Tallahatchie River-Little Talla-                       Levees, Panola-Quitman flood-
                    hatchie River.                                         way.
         0-75     Lower Yazoo River .-. ___-...                          Levees and pumping plants.--.                       Backwater and flood
                                                                                                                              control.
    75-381        Arae betweenYazoo-Tallahatchie-                        Levees and channel improve-                         Authorized by Pub-
                   Coldwater River system and                              ment.                                              lic Law 526, 79th
                   the hills, including Bobo Bayou.                                                                            Cong.
                  McKinney Bayou, _..........                            Channel improvement or en-                              Do.
                                                                          largement of pumping plant.
                                                    MISSISSIPPI RIVER COMMISSION                                                    1583
TABLE B.        Mississippi River tributary and outlet improvements-Continued

                             Location

Mileage                                                                       Improvement                               Remarks
above                                       Locality
mouth


                     BIG SUNFLOWER RIVER, ETC.
                                                                Channel improvement .                                Authorized by Pub-
    0-212     Big Sunflower River............
     0-11     Hull Brake-Mill Creek Canal-...                   .... do                   __-_-------  lic Law 526, 79th
    14-27     Hushpuckena River.............                    -----doC-------------------          - Cong. Public Law
    S'-66     Quiver River....................
     6-20
    30-461    Bogue Phalia.....................
                                                                --,do--------------------------i516,
                                                                             do
                                                                                                                       modifies require-
                                                                                                             81st Cong.,
                                                                                                       ments of local co-
                                                                                                                j      operation.
      0-4     Ditchlow Bayou-................                       .--do----------   -----   -   -         -

     0-27     Little Sunflower River...........                  _do_--      ---            --
                                                                                      _-----------
                                                               ----do--------------------------
                                                                                               - --     -


  154-160     Deer Creek......................                         -----
                                                                     do--------------------
     0-70     Steele Bayou........... .... __
                           ARKANSAS RIVER, ARK.

    23-98     Yancopin-Pine Bluff.............. Levee, south bank ........
    35-98     Fletcher Bend, Ark., to Pine Bluff. Revetment.....--         --------
   48-102     North Little Rock to Gillett        Lev ee , n o rth b an k ..- -   .....
                (below Plum Bayou).
                  WHITE RIVER AND BASIN, ARK.

     18-50    Laconia Circle-Old Town Lake....       Levee, backwater including out-                                Mile 600-740 Missis-
                                                        let structures.                                              sippi River.
   100-220    Augusta to Clarendon. .            .. Levees, outlet structures_.
       125    DeValls Bluff............. ___._ . .. Levee, outlet structure anl
                                                         pumping station.
       147    D es A rc, A rk ......... .. . . ..   ..--- do-...----------------- - --                              Authorized by Pub
                                                                                                                      lic Law 516, 81st
                                                                                                                      Cong.
    0-196     Cache River, Ark...                               Channel improvement                   and                Do.
                                                                 structures.
     0-90     Bayou DeView, Ark ..... __.__.__                    ,do-.....-- -----------
                                                                ....--                            ...                   Do.


                   ST. FRANCIS RIVER AND BASIN,
                           ARK. AND MO.

    0-305     Mouth of St. Francis River- Floodway, levees, drainage
                Wappapello Dam.                             channels and structures.
    0-105     Little River Basin __         ..
                                   ..... ______          ... do........----------------.
    15-36     Tyronza River........_._._._..           Channel improvement .                   ..
       155    Marked Tree, Ark.        ____            Marked Tree Siphon-.........
     0-29     Big Slough Ditch ....... __ ___. Channel improvement-..........
     0-17     Mayo Ditch .............          ..    .....   do....................-------------------
     0-12     Cross County Ditch_              ___.........
                                                      .....                              -----
                                                              do..--......-....-----------.
                            L'Anguille River, Ark.
     9-60    ....................................                   .do_                                            Authorized by Pub-
                                                                                                                     lie Law 858, 80th
                                                                                                                     Cong.
                  WEST TENNESSEE TRIBUTARIES

     0-81     Obion River and tributary North,                      .do_                                                Do.
                South, Middle, and Rutherford
                Forks.
     0-75     Forked Deer River and tributary
                North, Middle, and South Forks.                                                                         Do.

                            ST. JOHNS BAYOU, MO.

     0-11                               -
              New Madrid-Sikeston Ridge....                     Levee and floodgate...                              Mile 895, Mississipp
                                                                                                                     River.
              LITTLE RIVER DIVERSION CHANNEL

              Delta to Ancell, Mo-......___                     Levees ...                                          Mile 50 above Cairo.
 1584                  REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954
TABLE B. Mississippi River tributary and outlet improvements-Continued

                               Location

                                                                                     Improvement                 i            Remarks
    Mileage
    above                               Locality
    mouth


                               MISSOURI RIVER, MO.

           0-28 Mouth to St. Charles, Mo_ _                                  _
                                                                    __......do      -..


                                ILLINOIS RIVER, ILL.

          0-120      Mouth to Havana, IIll...              -             I Levees   -_                               Intermittent. (Sec.6.)

                            OHIO RIVER, ILL. AND KY.

            0-5      Cairo to Cache River .............                   Floodwall,levee, andrevetment.



                   TABLE C. Mississippi River tributary dams and reservoirs

                                                                                                  Sardis
Name 1__--------- -------                        --        Grenada            Enid             Little Tal-   Arkabutla   Wappapello  2
River ....----------------                  -------       Yalobusha          Yocona            lahatchie I   Coldwater 2 St. Francis


Nearest town to dam site------------............. Grenada                           Enid            Sardis    Arkabutla         Wappapello
Drainage area- ........         square miles_.       1, 320                          560             1,545        1,000              1,310
Conservation pool:
    Area........---------...thousand acres_.             10                                 6           10                5                 5
    Volume......thousand acre-feet..                     86                                58           92               31                39
    Elevation...feet, mean sea level..                  193                               230          235              210               355
Flood-control pool:
    Area ---------............
                             thousand acres.-            65                            28               58               33                23
    Volume......thousand acre-feet__                1,252                             602            1,478              494               586
    Runoff--- ........--.....-------- inches_         17.8                           20.2             18.0              9.3               8.4
Outlet gates:
    Number....------------------------                    3                              2                4             3                 3
      Size .--....---........-----..-------- feet              7.5 x 14             8 x 16           6 x 12      8. 5x 19           10 x 20
    Capacity,
      thousand cubic feet per second__                            10.0                    9.4         10.0             10.0              18.0
Spillway:
    Type, uncontrolled-----     ...         _.....              Chute               Chute           Chute            Chute         Gravity
    Length-----............----------......feet                   200                 200             400              300             740
    Elevation, crest,
      feet, mean sea level------------..........-                  231                    268          282             239                395
    Discharge capacity,
      thousand cubic feet per second.                               52                     50          132               89               156
Surcharge pool:
    Area---------............thousand acres__                       106                41               90              63                 32
    Volume-......thousand acre-feet_                             1, 385               554            1,447             858                521
             ...........--...
    Runoff----------                      inches_.                19.7               18.5             17.6             16.1               7.5
    Elevation...feet, mean sea level_.                           247. 5             284.0            301.6           257.0              414.0
Dam:
    Type, earthfill-------------------..................       Rolled            Rolled         Hydraulic            Rolled         Rolled
    Length ..- ......         thousand feet_                     13.9               8.4              15.3             10.0              2.7
Elevation, crest,
                      feet, mean sea level_                      256.0              293.0            312.0           265.0              420.0


  1 Grenada, Enid, Sardis, and Arkabutla Reservoirs are in Yazoo River Basin, Miss.; Wappapello Reser-
voir is in St. Francis River Basin, Mo.
  S Subtract 0.6 from elevations for Sardis, 0.3 for Wappapello, and 0.7 for Arkahutla to correct for 1941 and
1944 adjustments.
                                  MISSISSIPPI RIVER COMMISSION                                            1585
   The existing project was authorized by the following acts:
    Acts                              Work authorized                                     Documents

May    15,   1928   Flood protection in the alluvial valley of the Missis-    H. Doc. 90, 70th Cong., 1st sess.
June   19,   1930     sippi River; revetment and contraction works and
Feb.   15,   1933     dredging to provide least channel depth of 9 feet
Apr.   23,   1934     and width of 300 feet below Cairo.
June   15,   1936   Morganza floodway, outlet west of Berwick, Atcha-         House Committee on Flood Con-
Aug.   28,   1937     falaya Basin; control of headwater floods, St. Fran-     trol Doc. 1, 74th Cong., 1st sess.;
June   28,   1938     cis and Yazoo Basins; flood control works along          House Committee on Flood Con-
                       Cache River, Ill., roads on levees and drainage ad-     trol Doe. 1, 75th Cong., 1st sess.
                      justments incident to floodway levees.
Aug. 18, 1941       Enlargement of main line levees to offset abandon-        H. Doc. 359, 77th Cong., 2d sess.
                      ment of floodways between Arkansas and Red
                      Rivers, flood control works in backwater areas of
                      Yazoo and Red Rivers, and in Bayous Rapides,
                      Boeuf and Cocodrie, La.
Dec. 22, 1944       Navigation channel 12 feet deep and 300 feet wide be-     H. Doc. 509, 78th Cong., 2d sess.
                      tween Baton Rouge and Cairo; execution of chan-
                      nel improvement and stabilization program; flood
                      control improvement of Yazoo River (lower tribu-
                      taries), and protection of Yazoo River backwater
                      area in vicinity of Satartia.
July 24, 1946       Improvement of Boeuf and Tensas Rivers and                S. Doc. 151, 78th Cong., 2d sess.;
                      Bayou Macon; Bayou Lafourche; Yazoo River                 S. Doc. 191, 79th Cong., 2d sess.;
                      tributaries; Bayou des Glaises; levee on north bank       H. Doc. 516, 78th Cong., 2d sess.;
                      Arkansas River (below Plum Bayou), levees on              H. Doc. 602, 79th Cong., 2d sess.;
                      White River; Tiptonville-Obion levee and drain-           H. Doc. 757, 79th Cong., 2d sess.
                      age improvements (west Tennessee tributaries);          H. Doc. 98, 76th Cong., 1st sess.
                      St. Johns Bayou Mo.; Memphis Harbor, Tenn.              H. Doc. 138, 80th Cong., 1st sess.
                      (Tennessee chute); levee protection for Vicksburg-
                      Yazoo area.
                    Tennessee Chute (Memphis Harbor)....... _-....-           S. Doc. 51, 80th Cong., 1st sess.
June 30, 1948       Improvement of the Mississippi River below Cape           H. Doc. 627, 80th Cong., 2d sess.
                      Girardeau, Mo., with respect to west Tennessee
                      tributaries.
                    Improvement of L'Anguille River, Ark..............        H. Doe. 651, 80th Cong., 2d sess.
                    Barge channel 12 feet deep and 300 feet wide from         H. Doc. 321, 80th Cong., 1st sess.
                     Mississippi River mile 234.5 through
                      Swamp, La.
                                                                  bevils
May 17, 1950        Flood protection at Des Arc, Ark_...       ............   H. Doe. 485, 81st Cong., 2d sess.
                    Improvement of St. Francis River and Basin, Ark.          H. Doc. 132, 81st Cong., 1st sess.
                     and Mo.
                    Imljrovement of Cache River and Bayou DeView,             S. Doc. 88, 81st Cong., 1st sess.
                      Ark. and Mo.
                    Improvement of Grand Prairie region and Bayou             H. Doc. 255, 81st Cong., 1st sess.
                      Meto Basin, Ark.
                    Flood protection, Lake Pontchartrain, Jefferson           S. Doc. 139, 81st Cong., 2d sess.
                     Parish, La.
                    Filling Grant's Canal, Lake Providence, La.; addi-
                      tional protection to Red River backwater area;
                     extending Federal jurisdiction to cover levees in
                      Orleans Parish, La.; and bank protection, Amite,
                      La.
Oct. 30, 1951       Modification of requirements for local cooperation in     Pub. Law 237, 82d Cong., 1st sess.
                     the White River backwater area, Arkansas.



    Recommended modification of project. The Mississippi River
Commission has submitted reports to the Chief of Engineers recom-
mending the following modifications of the project, as amended:
    a. Report dated September 20, 1950 (S. Doc. 53, 82d Cong., 1st
sess.), recommending navigation improvement on Atchafalaya' and
Old Rivers between Morgan City, La., and the Mississippi River by
providing a 12-by 125-foot channel through shoal areas in Grand
and Six Mile Lakes at an estimated additional first cost of $440,000
and an estimated annual cost of $150,000 for maintenance. This
plan was concurred in by the Chief of Engineers on May 1, 1951.
    b. Report dated February 11, 1952 (H. Doc. 85, 83d Cong.. 1st
sess.), recommending construction of an industrial fill, harbor chan-
nel, and appurtenant approach navigation channel and approach
fills near Vicksburg, Miss., substantially in accordance with a
described plan with such modifications thereto as the Chief of En-
1586     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

gineers may deem advisable, at estimated costs to the United
States of $3,220,000 for construction and $21,000 for annual main-
tenance, subject to the conditions that these improvements are in
lieu of those for the Vicksburg-Yazoo area, Miss., authorized in
Public Law 526 of the 79th Congress, and that local interests
furnish specified cooperation.
    c. Report dated December 20, 1951 (H. Doc. 183, 83d Cong., 1st
sess.), recommending the construction of improvements in the New
Madrid floodway, Missouri, substantially in accordance with an
outlined plan at an estimated additional cost to the United States of
 $1,556,000 subject to the condition that local interests furnish re-
quired cooperation.
    d. Report dated February 2, 1954 (H. Doc. 478, 83d Cong., 2d
sess.), recommending provision for the control of flows from the
Mississippi River into the Atchafalaya River and Basin via Old
River by the construction and operation of control structures on
the right bank of the Mississippi River at additional estimated
costs to the United States (exclusive of navigation lock which will
be reported on at a later time) of $46,741,000 for construction and
$231,000 annually for operation and maintenance.
    e. Report dated April 29, 1954 (S. Doc. 160. 83d Con r., 2d
sess.), recommending provision for the construction of additional
channel improvements in the Reelfoot Lake area, Tennessee and
Kentucky in accordance with an outlined plan at an estimated addi-
tional cost to the United States of $748,100 subject to the condition
that local interest furnish the required cooperation.
    References to published articles not previously reported. Paper
entitled "Mississippi-Atchafalaya Diversion Problem" by Brig.
Gen. John R. Hardin, United States Army, president, Mississippi
River Commission printed in "The Military Engineer" for March-
April 1954.
    Local cooveration. Section 2 of the Flood Control Act approved
May 15, 1928 stated that, in view of the great expenditure, esti-
mated at approximately $292,000,000, heretofore made by the local
interests in the alluvial valley of the Mississippi for protection
against the floods of that river; in view of the extent of National
concern in the control of these floods in the interest of National
prosperity, the flow of interstate commerce, and the movement of
the United States mails and in view of the gigantic scale of the
project involving flood waters of a volume and flowing from a
drainage area largely outside the states most affected and far ex-
ceeding those of any other river in the United States, no local
contribution to the project is required. Requirements of local
cooperation however are stipulated in section 3 of the act of May 15,
1928, as amended. Such requirements have in general been com-
plied with by local interests as construction of the project has
advanced.
    Terminal facilities. See volume 1 of the four-volume report of
the Board of Engineers for Rivers and Harbors, entitled "Survey
of Terminals and Landings on the Inland Waterways of the United
States" and Port Series for New Orleans, La., No. 20, 1947, and
Lake Charles, La. No. 21, 1947, also folio of Flood Control and
                    MISSISSIPPI RIVER COMMISSION                1587
Navigation Maps of the Mississippi River, Cairo, Ill., to the Gulf
of Mexico (21st edition), 1953.
       OPERATIONS AND RESULTS DURING FISCAL YEAR

     Commission activities. The 242d session of the commission
  was held on board the U. S. steamer Mississippi en route on Mis-
  sissippi River from Cairo, Ill. to mouth of Old River, La., the Old
River and Atchafalaya River from the mouth of Old River to
  Simmesport, La., and the Mississippi River from Old River to
Baton Rouge, La., from October 17 to 23, 1953. The 243d session
was held on board the same steamer en route on the Mississippi
River from Cairo, Ill. to the mouth of Old River to Simmesport,
thence on board the U. S. steamer General John Newton on the
Atchafalaya River to Morgan City, La., and the Mississippi River
from New Orleans, La. to the mouth of Southwest Pass, from May
4 to 11, 1954. On the river trips, major features of the project
were inspected and public hearings were held at which representa-
tives of local government agencies, navigation, levee, commercial,
and other interests presented problems pertaining to flood control
and navigation.
     In addition to the inspection trips via steamer, members of the
commission inspected major flood control and navigation improve-
ments under the jurisdiction of the commission and reviewed and
acted on two reports, namely:
     1. Review Report on Mississippi River and Tributaries with re-
spect to Old River Control dated February 2, 1954, which was
submitted to Congress. Studies and design of structures recom-
mended in this report are under way.
    2. Review of Reports, Lower Mississippi River for Flood Control
and Major Drainage in Reelfoot Lake Area, Tenn. and Ky. dated
April 29, 1954.
    A report was-submitted to the Chief of Engineers recommending
approval, under the provisions of section 6 of the Flood Control
Act approved June 15, 1936, for the construction of additional
drainage 6titlet. iriprovements for the completion of the Atchafa-
laya Basin floodway to afford flood benefits in the Bayou Courta-
bleau Basin and outlets.
    A resolution by the Committee on Public Works of the United
States Senate, adopted June 12, 1954, authorizes a review of the
project for flood control of the Mississippi River in its alluvial
valley and for its improvement from the Head of the Passes to Cape
Girardeau, Mo., as one comprehensive whole and in its entirety and
submission of recommendations for any modifications that are ad-
visable with 'iespect to the project or any feature of the project.
Preliminary studies under this authority have been initiated.
    The president, Mississippi River Commission, and his engineer-
ing assistants made periodic inspections of flood control, navigation,
and related works under the existing project along the Mississippi
River acid triblitaries in the alluvial valley from Cape Girardeau,
Mo to the Gdlfbf Mexico.
    No major floods. occurred during the fiscal year but through the
combined effortiibof local authorities and Fderal personnel, close
1588      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  contact with minor and local flood situations was maintained and
  operations were carried out efficiently.
    Surveys, gages, and observations. Routine hydrographic sur-
veys of the river between Head of Passes and Cairo, construction
and special surveys and inspections were made as required. Gages
were maintained and discharge observations made. Results thereof
are presented in detail in annual pamphlets issued by the Missis-
sippi River Commission.
    Alluvial valley mapping. Preparation and publication of con-
toured maps of the alluvial valley (scale 1:62,500) and quadrangle
maps were continued. On the new total 16-sheet, scale 1:250,000
map of the alluvial valley of the lower Mississippi, the initial com-
pilation has been completed on four sheets preparatory to review
and printing, and other sheets are in various stages of compilation.
    Work accomplished in the districts follows:
    Memphis district: New editions of the DeWitt quadrangle and
the new Holly Springs quadrangle were published. Eight remapped
quadrangles were completedThebes, Cairo, Charleston, Bayou-
ville, Hickman, Malden, Pascola, and Hayti; 23 new and remapped
quadrangles are in the process of reproduction-Indian Bay, Hen-
rico, Mellwood, Farrell, Latour, Park Place, Edmondson, Decker-
ville, Marked Tree, Manila, Evadale, Memphis, Horseshoe Lake,
Clayton, Blytheville, Mason, Caruthersville, Portageville, New
Madrid, Charleston, Thebes, Cairo, and Reelfoot Lake; and a con-
tract for the compilation of new planimetry on 12 quadrangles
located in the White River and St. Francis River Basins, awarded
fiscal year 1951, is under way. Four additional quadrangles are
about 50 percent complete, and preparation has been started on the
compilation of five others.
    Vicksburg district: The Sardis, Pittsboro, Duck Hill, and Gren-
ada quadrangle maps were published. Drafting was continued on
the McCarley, Oakland, Water Valley, and Coffeeville quadrangle
maps.
    New Orleans district: Work was completed on revising the
Artonish quadrangle map. The map was redrafted to the scale
1:20,000 and will be published to scale 1:62,500. Color separation
drawings were completed for the Napoleonville quadrangle and the
map 'was published to the scale of 1:62,500. Color separation
drawings were also completed for the Belle Isle and Jeanerette
maps. Work is in progress on the color separation drawings for
Batchelor, Fordoche, Morgan City, and Osca Bayou quadrangle
maps.
    Costs incurred for surveys, gages, and observations and for
alluvial valley mapping during the fiscal year, not including cost of
surveys incident and chargeable to construction features, are given
in table G.
    MississippiRiver dredging: A toal of 46,403,493 cubic yards of
material was dredged in the Mississippi River channel in the three
districts, whereby minimum depth of 9 feet was maintained except
for two days, September 19 and 20, 1953, and 11/2days, October
5 and 6, 1953, at Overton Crossing, mile 737 AHP where 8 2, feet
existed. In addition to dredging, channel patrols and surveys were
made as required; navigation notices issued; navigation aids main-
                   MISSISSIPPI RIVER COMMISSION                 1589
tained; snags, wrecks, and obstructions removed; liaison contact
pilot service with commercial navigation was maintained; channel
conditions were broadcast by radio; and velocity data were fur-
nished at troublesome reaches.
   Dredging by districts was as follows:
   New Orleans district: Channel maintenance: The U. S. dredge
Jadwin operated on the Mississippi River at mile 297.1 AHP,
moving 373,852 cubic yards.
   Vicksburg district:a. Channel maintenance. One Government-
owned dredge was operated 32 times at 21 locations on the Missis-
sippi River between mile 320 AHP and mile 593 AHP, moving
5,566,588 cubic yards of material. One leased dredge was operated
in Greenville Harbor moving 550,544 cubic yards of material.
   b. Miscellaneous dredging. One Government-owned dredge
was operated at one privately owned oil dock moving 43,458 cubic
yards of material, and at one Government-owned dock moving
38,889 cubic yards of material.
   Memphis district: a. Channel maintenance. On the Mississippi
River, between mile 593 AHP and 964 AHP, dredges were operated
99 times at 54 locations. Four Government-owned dredges re-
moved 28,654,525 cubic yards of material and two leased dredges
removed 7,934,451 cubic yards of material.
   b. Channel improvement. One leased cutterhead dredge at
Sunrise Towhead Chute, mile 775, removed 3,241,186 cubic yards
of material thereby developing a new channel to prevent bank
erosion into the controlling levee.
   Costs for dredging during the fiscal year are given in table G.
   Authorized Mississippi River harbors:
   New Orleans district: Baton Rouge Harbor extension (Devils
Swamp Canal)-No work done.
   Vicksburg district: Vicksburg-Yazoo industrial area (harbor
extension) -No work done.
   Memphis district: Tennessee Chute (Memphis Harbor)-Work
on the industrial embankment was continued with 9,186,523 cubic
yards (including 642,177 cubic yards placed in fiscal year 1953)
being placed during the fiscal year, which gives a total of 30,409,500
cubic yards placed to date. Work on the Nonconnah Creek sewer
extension is approximately 80 percent complete. Approximately
617 acres of the proposed 960-acre industrial fill is completed to
grade. The project as a whole is approximately 58 percent com-
plete.
   Wolf River (Memphis Harbor)-See report on the improvement
of Rivers and Harbors in the Memphis district.
   Costs for project work are given in table G.
   Bank protection. A total of 130,655 linear feet of new revet-
ment work was accomplished on the Mississippi, Red, Arkansas,
and Ohio Rivers, of which 19,780 linear feet were in the New
Orleans district, 27,035 linear feet in the Vicksburg district, and
84,340 linear feet in the Memphis district. Data concerning the
work are shown by district in tables D-      through D-3. Repairs
were made where required.
   Costs for this work are given in table G.
   Mainline Mississippi Rwer Levee,. Work in the New Orleans,
1590     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Vicksburg, and Memphis districts included restoration and enlarge-
ment of levees to project grade and cross section. A total of
6,139.000 cubic yards of levee construction was accomplished. In
the Vicksburg and Memphis districts, roadway embankments of
15 to 20. feet in width were placed adjacent to the crown of the
levees. (See tables E-1 through E-3). The Rock Island district
accomplished 62,000 cubic yards of levee construction on the
Mississippi River under section 6 of the Flood Control Act of May
15, 1928, as amended. (See table E-4).. No work of this type
was undertaken in the St. Louis district.
   New Orleans district: Additional work in connection with levees
includes installation of levee wavewash protection works, consist-
ing of concrete slope paving, stone slope paving and toe protection,
and maintenance of timber structures locally known as wooden
revetments. Status of this work is given in table E-6. Two
gravel roadways totaling 1.5 miles, and a 0.2-mile section of
bituminous surfaced highway were constructed where levees are
being set back. Construction of 2,500 linear feet of floodwall at
Dumaine Street in New Orleans was completed July 7, 1953; placing
of shell fills for the closure section was accomplished under separate
contract between March 6 and September 15, 1953.
   Vicksburg district. Levee work included restoration and en-
largement of approximately 6.3 miles of levees to project grade
and cross section. A total of 4,338 linear feet of floodwall at Vicks-
burg, Miss., has been constructed of which 1,988 linear feet were
accomplished during the fiscal year.
   Memphis district: Additional work in connection with levees
includes the placing of clay gravel on roadway embankment of ap-
proximately 7 miles in the White River levee district and 8 miles
in the upper St. Francis levee district.
   Costs for levee work during the fiscal year are given in table.G.
   Floodways and outlets. New Orleans district: a. Atchafalaya
floodway, La. Construction of the high-level railroad crossing
over the West Atchafalaya floodway from Krotz Springs to Courta-
bleau was continued under a reimbursable contract with the New
Orleans, Texas & Mexico Railway Company, and is about 92 percent
complete. Approximately 737,300 cubic yards were placed in the
embankment, making the final phase embankment 94 percent
complete. Construction of the steel spans for raising the bridge
over the Atchafalaya River was commenced on July 8 and com-
pleted December 31, 1953. Construction of the trestle sections
continued and is now about 98 percent complete.
   Negotiations are being conducted with the State of Louisiana,
Department of Highways, for an agreement covering the design
and construction of a high-level crossing for U. S. Highway No. 190
between Courtableau and Krotz Springs. A draft of the agreement
for preparation of plans and specifications has been forwarded to
the Department of Highways for approval.
   At Bayou Boeuf lock the following work was accomplished:
33,700 cubic yards were excavated, 75,650 cubic yards of fill and
backfill were placed in the embankment, and 9,350 square feet of
sheet piling were driven: the timber guide walls, concrete work,
stone protection, and concrete mattress were completed in Febru-
                    MISSISSIPPI RIVER COMMISSION                1591
ary; and installation of sector gates and operating machinery was
completed in June. The contract for construction of the lock was
completed on June 14, 1954. Excavating and stockpiling material
for Bayou Boeuf closure and dredging of minimum approach chan-
nels were accomplished under separate contracts. Partial excava-
tion of the approach channels was commenced March 21 and
395,900 cubic yards had been excavated and stockpiled for Bayou
Boeuf closure by May 30, 1954, when the contract was completed.
Dredging of the east and west minimum approach channels was
initiated on May 15 and completed on June 28, 1954, with a total of
346,252 cubic yards dredged.
   All work under contract for construction of Tiger Island levee
and floodwall was completed on April 14, 1954. A total of 72,270
cubic yards was placed in the embankment, a reinforced concrete
floodwall 1.990 feet in length and a drainage structure were con-
structed, 2,500 linear feet of railroad was relocated and 3,500 linear
feet raised.
   At Coulee des Grues 0.2 mile of levee was enlarged and 70 feet of
culvert extension, with stilling basin and sluice gates, was con-
structed.
   Levee enlargement on the east and west protection levee systems
was continued, and first lift closure of gaps in the east protection
levee below Morgan City at Bayou Penchant and Sword Bayou was
effected. In the Atchafalaya Basin and floodway 0.45 mile of levees
was constructed and 7.8 miles enlarged or topped.
   Advance planning and surveys are in progress. A letter report
was prepared and submitted April 7, 1954, on "Mississippi River
and Tributaries, Atchafalaya Basin Floodway, West Protection
Levee Intercepted Drainage." Field surveys were initiated for the
proposed control structure at Bayou Courtableau in the West
Atchafalaya Basin protection levee and for the inlet and outlet
channels.
   Work in connection with interior drainage west of Berwick was
accomplished as follows: A total of 344,900 cubic yards was moved
in excavating a drainage channel south of Bayou Teche, Calumet to
Wax Lake east levee borrow pit, along the east side of the Wax
Lake Outlet east spoil bank. Construction of Wax Lake West
drainage structure was initiated July 31, 1953, and completed June
18, 1954. Construction of Wax Lake East drainage structure was
started January 4, 1954; 15,600 cubic yards were excavated for the
structure and 23,000 cubic yards for the channel, 33 percent of the
concrete has been placed in the base slab and keys, and 71 percent
has been placed in the stabilization slab; the drainage structure is
approximately 29 percent complete. Two supply contracts were
awarded for purchase of pumps and pumping equipment for Bayou
Yokely pumping station; delivery has been made of two vacuum
pumps with electrical equipment covered by one contract, and
manufacture of the main pumps and equipment under the other
contract is approximately 50 percent complete. A contract was
awarded on June 8, 1954, for construction of Bayou Yokely pump-
ing station but work has not started. Plans and specifications for
North Bend and Morgan City-Bayou Boeuf pumping stations have
been completed.
1592     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   The acquisition of flowage easements in the West Atchafalaya
floodway (including extension of the floodway) is complete, except
for processing Department of Justice requirements in connection
with condemnation cases, which is about 99 percent complete. In
the Atchafalaya floodway below the latitude of Krotz Springs,
acquisition of flowage easements for the project, "Bayou Chene and
vicinity," is complete, except for making of final payments by the
Department of Justice for seven tracts in condemnation, or the
equivalent of 88 percent complete. Acquisition of flowage ease-
ments in connection with the project "Lands below the latitude of
Krotz Springs," is approximately 25 percent complete. (Approxi-
mately 95 percent of the tracts in this project on which claims have
been filed by property owners have been appraised. Negotiations
to secure options during fiscal year have failed since landowners
have refused to sign due to easement values presently assigned
these tracts.) Acquisition of all lands for the construction of
Bayou Boeuf lock has been completed, except for final payment on
one tract in condemnation.
    b. Morganza floodway, Louisiana. All work on the high-level
crossing for U.S. Highway No. 190 was completed when placing of
riprap protection at the ends of the embankment was completed on
September 12, 1953.
    Construction of the combined high-level crossing for State
Highway No. 30, the Texas & Pacific Port Allen branch line, and a
control structure was continued, with the following work accom-
plished:
   Phases IV and V (final) embankment, which was commenced
November 3, 1952, was completed on March 8, 1954, with a total
of 1,105,247 cubic yards of semicompacted and 106,566 cubic yards
of compacted fill placed.
   The Texas & Pacific Railway Company completed relocation of
their Port Allen branch line under a reimbursable contract on April
21, 1953, except for adjustment of the Lacour spur which was com-
pleted April 7, 1954.
    Under a reimbursable contract with the State of Louisiana, De-
partment of Highways, for the relocation of State Highway No. 30,
the Department of Highways awarded a contract for the completion
of approach embankments and temporary surfacing. Construction
under this contract was initiated September 1, 1953, and is now
approximately 78 percent complete making the highway relocation
approximately 41 percent complete.
    Alterations to the gantry cranes and control structure, initiated
February 11, 1953, by hired labor forces, were completed November
7, 1953.
    The overall status of completion of the combined high-level
crossing and control structure is 95 percent.
    Relocation of a rural electric power line was initiated on Novem-
ber 3, 1953, and completed on January 28, 1954.
    Acquisition of the new cemetery sites is complete, and title to
these lands has been conveyed by the contractor to the church
organizations involved. Activities in connection with processing
final papers on cemetery relocations are 95 percent complete.
   Preparation of necessary exchange agreements and conveyances
                    MISSISSIPPI RIVER COMMISSION                1593
for the consummation of the various obligations under relocation
agreements involving highways, railroads, telephone and telegraph
lines and other utilities is now underway and 90 percent of these
instruments have been prepared and forwarded to the utility
companies for review and approval.
    Acquisition of comprehensive easements over lands in the proj-
ect is complete, except for payment of one tract in condemnation.
    An "Interim Review of Reports on Mississippi River and Tribu-
taries, to determine the Crop Damage resulting from the Use of
Herbicide 2,4-D, at Morganza Floodway, Pointe Coupee Parish, La.,
25 May to 9 June 1953" was prepared and submitted June 15, 1954.
   .c.Wax Lake Outlet and Charenton drainage and navigation
canal, Louisiana. No construction work was done during the fiscal
year. Acquisition of comprehensive easements over all lands
required in connection with these features of the project is com-
plete.
    d. Bonnet Carre spillway, Louisiana. (See pp. 2089-2091, An-
nual Report for 1938.) Flood stages did not necessitate operation
of the spillway. Maintenance of the guide levees and the spillway
structure was continued. Other maintenance work, by hired labor
forces, consisted of French clearing of 1,132 acres and spraying
stumps, weeds, and new growth to improve flowage.
    Basin improvements. Work accomplished in tributary basins
located within the Mississippi River alluvial valley follows by dis-
tricts. Bank protection work on lower Red, Arkansas, and Ohio
Rivers are given in tables D-1 through D-3. Summaries of levee
and channel improvement work in these tributary basins are given
in tables E-1 through E-3, E-5, and F-1 through F-3, respectively.
    Costs for work accomplished are given in table G.
    New Orleans district, a. Atchafalaya River, Louisiana. Main-
tenance of the levee system continued.
    b. Bayous Rapides, Boeuf, and Cocodrie, Louisiana. No Con-
struction was accomplished during the fiscal year. A "Review of
Reports, Mississippi River and Tributaries, Bayous Rapides, Boeuf,
Cocodrie and Courtableau, and Outlets, La.," was prepared and
submitted May 28, 1954.
    c. Lake Pontchartrain, Jefferson Parish, La. A total of 918,448
cubic yards of fill was placed in the levee system. The slope and
toe of the levee were protected as follows: By contract, 3,700 linear
feet of toe protection was accomplished by placing 11,387 tons of
broken concrete; and by hired labor, 3,110 linear feet of levee slope
and toe protection, by placing clam shell, stone, broken concrete,
and mass asphalt. A contract was awarded for placing 14,700 tons
of broken concrete for an additional 5,000 linear feet of toe protec-
tion; preparatory work consisting of grading roadway was initi-
ated on June 18, 1954, and hauling and placing broken concrete
commenced June 30.
    d. South bank Red River levees, Louisiana. The levee system
was maintained. At mile 90.9, 700 linear feet of standard board
revetment were constructed. At Scott Home levee, in the vicinity
of Boyce, La., a concrete paved ramp was constructed by the State
of Louisiana, Department of Highways, between April 12 and June
2, 1954, under a lump-sum agreement.
1594     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

   Vicksburg district-Yazoo Basin headwater, Miss.: (1) Sardis
Reservoir. (See table C.) The facility was operated, necessary
repairs to the dam and appurtenant structures were made, and
malaria control operations in the reservoir area were continued.
Contract for asphalt surfacing of roads in the vicinity of the dam
was awarded June 7, 1954.
   A total of 500,000 pine seedlings was planted by hired labor.
   There were 509,500 visitor days for recreation.
   On July 1, 1953, 958,000 acre-feet of water remained in storage
from the 1953 flood season, and by November 10, 1953, the flood
pool was emptied. Flood runoff and reservoir stages during the
normal high water season were the lowest since 1941. Maximum
water elevation in the reservoir during the storm period was 274.8
feet mean sea level, on June 9, 1954, when flood control storage
was 198,000 acre-feet. Peak inflow was about 20,000 cubic feet per
second on January 23, 1954. Average daily releases, varied to
accord with inflow and downstream river stages, ranged from 0 to
a maximum of 2,000 cubic feet per second. On June 30, 1954,
173,100 acre-feet remained in the flood control pool, which it is
planned to release by October 15, 1954.
   (2) Arkabutla Reservoir.       (See table C.) The facility was
operated, necessary repairs to the dam and appurtenant structures
were made, and malaria control operations in the reservoir area
were carried out.
   A total of 510,000 pine seedlings was planted by hired labor.
   There were 82,000 visitor days for recreation.
   On July 1, 1953, 217,000 acre-feet of water remained in storage
from the 1953 flood season, and by October 23, 1953 the flood pool
was emptied. Flood runoff and reservoir stages during the normal
high water season were the lowest since the reservoir has been in
operation. Maximum water elevation in the reservoir, 220.8 feet
mean sea level, was reached January 29, 1954, when flood control
storage was 100,500 acre-feet. Peak inflow was about 17,000 cubic
feet per second on February 20, 1954. Average daily reservoir
releases, varied to accord with inflow and downstream river stages,
ranged from 0 to a maximum of 3,000 cubic feet per second. On
June 30, 1954, 30,100 acre-feet remained in the flood control pool,
which it is planned to release by October 1, 1954.
   (3) Enid Reservoir. (See table C.) The facility was operated
and necessary repairs to the dam and appurtenant structures were
made.
   A total of 589,000 pine seedlings was planted by hired labor.
   There were 116,700 visitor days for recreation.
   On July 1, 1953, 266,000 acre-feet of water remained in storage
from the 1953 flood season, and by November 7, 1953, the flood pool
was emptied. Flood runoff and reservoir stages during the normal
high water season were the lowest since the reservoir has been in
operation. Maximum water elevation in the reservoir was 237.4
feet mean sea level on January 25, 1954, when flood control storage
was 57,000 acre-feet. Peak inflow was about 13,000 cubic feet per
second on January 21, 1954. Average daily reservoir releases,
varied to accord with inflow and downstream river stages, ranged
from 0 to a maximum of 1,000 cubic feet per second. On June 80,
                   MISSISSIPPI RIVER COMMISSION                1595
1954, 56,800 acre-feet remained in the flood control pool, which it
is planned to release by October 15, 1954.
   there are 44,133 acres of land authorized for acquisition in the
dam and reservoir areas. Acquisition is complete except for four
tracts in condemnation now pending before Federal courts.
   (4) Grenada Reservoir. (See table C.) Contract for construc-
tion of outlet works, closure section and appurtenant works was
completed January 12, 1954. Total quantities involved in the
completion of major items of excavation under the contract, in-
cluding those for the fiscal year were as follows: Stripping for
embankment, 116,351 cubic yards; borrow, 1,738,667 cubic yards;
outlet structure, 47,663 cubic yards; and outlet channel, 381,014
cubic yards. Total quantities placed in the embankment, including
those for the fiscal year, were as follows: Compacted fill, 1,542,181
cubic yards; pervious fill. 64.008 cubic yards; and backfill, 47,953
cubic yards. A total of 12,168 cubic yards of concrete was placed
in the outlet works.
   Contract for clearing of a portion of the reservoir area, Items
I and III, was completed October 26, 1953.
   Construction of the south access road was completed, except for
seeding, by hired labor.
   Construction of access road and boat channel at Grenada Land-
ing, near the south end of the dam, was completed by hired labor
September 30, 1953.
   Reimbursable contract for the relocation of State Highway No. 7
was completed September 17, 1953. Reimbursable contract for the
relocation of the facilities of the Illinois Central Railroad across
the reservoir was completed in April, 1954. Reimbursable contract
for the relocation of the facilities of the Mississippi and Skuna
Valley Railroad was completed March 2, 1954. Maintenance of the
embankment under the contract is continuing. Reimbursable con-
tract for relocation of State Highway No. 330 (Skuna Valley Road)
was completed October 27, 1953. Reinbursable contriact for
abandonment of a' power line in the reservoir area was completed
December 31, 1953. Reimbursable contract for relocation of a
Rural Electric Association power line in Yalobusha County was
completed in December 1953. Reimbursable contract for relocation
of a telephone line in the reservoir area was completed December
31, 1953.
   County roads: Construction of closure sections of Graysport and
Gums Crossings was completed October 7, 1953, and April 20,
1954, respectively. Relocation of Clear Springs and Jones School
to Horton Church Road was completed October 30, 1953. Reloca-
tion of Big Creek to Gore Springs Road was completed December 5,
1953. Reimbursable contract for relocation of roads in Grenada
County was completed October 30, 1953. Under a continuing
reimbursable contract for relocation of roads in Yalobusha County,
Twisted Tree Road was completed.
   A total of 404,000 pine seedlings was planted by hired labor.
   Normal operation began. January 20, 1954, when outlet gates
were closed to impound water in the conservation pool. Maximum
water elevation in the reservoir was 205.6 feet mean sea level on
May 29, 1954, when flood control storage was 191,000 acre-feet.
1596     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

Peak inflow was about 13,000 cubic feet per second on May 3, 1954.
Average daily reservoir releases, varied to accord with inflow and
downstream river stages, ranged from 0 to a maximum of 3,500
cubic feet per second. On June 30, 1954, 39,100 acre-feet remained
in the flood control pool, which it is planned to release by July 15,
1954.
   There are 89,181 acres of land authorized for acquisition in the
dam and reservoir areas. Acquisition is complete except for 69
tracts in condemnation now pending before Federal courts.
   (5) Greenwood protection works. Contract for construction of
Lee and Wilson Streets pumping stations was completed September
18, 1953. Payment was made to the City of Greenwood for reloca-
tion of a power line. Reimbursable contract for alteration of tele-
phone lines was completed October 1, 1953. Maintenance of the
completed levees and operation and maintenance of floodgates and
pumping station were continued.
   (6) Yazoo City protection works. Contract for construction of
Jonestown Cutoff and adjacent levees was completed September
17, 1953. Contract for the relocation of telephone line was com-
pleted August 1, 1953.
   (7) Channel improvements.        Yalobusha River. Intermittent
channel clearing and snagging, and installation of tree retards in
bendways, between miles 24.3 and 45.0 were initiated by hired
labor August 24, 1953, and completed March 12, 1954. Alterations
to highway bridge over channel cutoff near Avalon were initiated
by hired labor October 12, 1953, and completed November 25, 1953.
Contract for clearing and snagging and channel enlargement and
realinement between the mouth and mile 11.3 was completed
January 2, 1954. Operations during the fiscal year comprised 7.45
miles clearing and snagging and the excavation of 1,192,838 cubic
yards of material.
   (8) Channel maintenance. The following operations were ac-
complished as maintenance:
   (a) Coldwater River: Ammate spraying, 40.7 miles and ran-
dom drift removal.
   (b) Little Tallahatchie River and Panola-Quitman floodway:
Clearing and snagging, 5.6 miles, in Panola-Quitman floodway.
   (c) Yocona River: No work was done.
   (d) Cassidy Bayou: Clearing, 32.7 miles and Ammate spraying,
14.2 miles.
   (e) Bobo Bayou: No work was done.
   (f) Tallahatchie River: Clearing and snagging, 6.4 miles.
   (g) Yalobusha River: Snagging, 1.8 miles and random drift
removal.
   (h) Yazoo River : Clearing and snagging, 6.3 miles.
   (9) Bank stabilization. Bank protection in the Yalobusha River
at the U. S. Highway No. 51 bridge at Grenada was initiated by
hired labor November 3, 1953, and completed December 22, 1953.
A total of 2,315 linear feet of treated piles was driven, 2,307 cubic
yards of material were moved in grading the banks, and 3,261 tons
of riprap stone and 1,519 tons of gravel were placed.
  (10) Yazoo Basin levees: Contract for construction of levee set-
                   MISSISSIPPI RIVER COMMISSION               1597
back on the right bank of Panola-Quitman floodway (Little Talla-
hatchie River) was awarded June 14, 1954. The Coldwater River
levees were maintained and the floodgates were operated.
   Biq Sunflower River, etc., Mississippi: Preparation of plans and
specifications, surveys and studies are continuing. Contract for
1.49 miles of channel clean out and construction of Poindexter
Cutoff, in Steele Bayou between miles 41.7 and 48.1, was initiated
Atgust 11, 1953, and completed February 5, 1954. Operations dur-
ing the fiscal year comprised 1,758,584 cubic yards of excavation
in 4.9 miles of channel cutoff. Reimbursable contract for relocation
of one 8-inch oil pipeline was initiated and completed in October
1953.
    Yazoo Basin backwater, Mississippi: (See table E-2.) No work
was done.
   Boeuf and Tensas Basins, La. and Ark.: Preparation of plans
and specifications, surveys, and studies are continuing. Channel
improvement continued as follows:
    (1) Bayou Lafourche, La. Contract for Channel enlargement,
realinement, and clearing and grubbing between miles 34.1 and the
upper limit of Bayou Lafourche at mile 56.8 (mile 150.9 on Boeuf
River) was completed July 31, 1953. Operations during the fiscal
year comprised 197,668 cubic yards of excavation. Contract for
widening the pilot ditch between miles 33.6 and 35.7 to full channel
width was initiated October 15, 1953, and completed April 24, 1954.
Operations comprised 956,513 cubic yards of excavation. Repairs
to the Irwin Lake weir and low water dam at mile 40.9 were initi-
ated by hired labor October 1, 1953, and completed November 9,
1953.
   Reimbursable contract for reconstruction of State Highway No.
15 bridge was completed September 14, 1953. Under reimbursable
contract, construction of new United States Highway No. 80 bridge
was in progress. Under reimbursable contract, reconstruction of
Illinois Central Railroad bridge was completed except for observa-
tion of scour around the piers. Reimbursable contract of relocation
of Richland and Morehouse Parish bridge at mile 56.0 was com-
pleted August 18, 1953. Reimbursable contract for alteration of
one power transmission line at mile 35.2 was completed March 2,
1954. Rearrangement and alteration of one telephone line at mile
34.5, was in progress.
    (2) Boeuf River, La. and Ark. Work under contract for channel
enlargement and realinement in Reach 1, mile 155.6 to mile 165.3,
was initiated August 17, 1953 and is 72 percent complete. Opera-
tions during the fiscal year comprised 2,604,487 cubic yards of
excavation. Contract for channel enlargement and realinement in
Reach 2, mile 165.3 to mile 174.0, was initiated July 17, 1953, and
completed February 24, 1954. Operations during the fiscal year
comprised 3,767,154 cubic yards of excavation.. Work under one
contract for channel enlargement in Reach 3, mile 174.0 to mile
183.0 and in Reach 4, mile 183.0 to mile 196.1, was initiated March
8, 1954, and is 15 percent complete. Operations during the fiscal
year comprised 1,341,068 cubic yards of excavation. Reimbursable
contract for alteration of State Highway No. 11 bridge in Reach 2
1598     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

was completed February 12, 1954. Relocation of a pipe line-in
Reach 4 was completed by the owner without cost to the United
States.
    (3) Big Bayou, Ark. Contract for channel enlargement and
channel cleanout between miles 0.0 and 8.0 was completed August
26, 1953. Operations during the fiscal year consisted of the con-
struction of a ramp at mile 7.24 and low water weirs at miles 0.24
and 4.34. Repairs to these weirs were initiated and completed by
hired labor in November 1953.
    Red River backwater levees, La.: Work under contract for con-
struction of 19.6 miles of new levee, between Dunbarton and the
main line Mississippi River levees near Lake St. John, involving the
placement of 706,000 cubic yards of embankment, 6 drainage struc-
tures, culverts, ditch excavation, and 1,270 linear feet of road
relocation and gravel surfacing, was initiated September 28, 1953,
and is 87 percent complete. A total of 642,456 cuLbic yards of em-
bankment was placed. Enlargement of previously constructed
levees to adopted grade and section was completed exceut for reaches
totalling approximately 4,300 linear feet in the vicinity of the
Bayou Cocodrie drainage structure. A total of 4,405,285 cubic
yards of embankment was placed. Plans and specifications for the
construction of 450 linear feet of levee wall over the Bayou Cocodrie
drainage structure are being prepared in the Mississippi River
Commission office. Preparation of plans and specifications for the
Buckner Bayou diversion is in progress. Reimbursable contract
for Woringer Bayou bridge and drainage alterations is complete.
Reimbursable contract for construction of a drainage ditch in the
vicinity of Acme, La., was essentialjr completed. The Bayou
Cocodrie drainage structure is being operated.
    Bawcomville, La.: Plans and specifications for construction of
two pumping stations and modifications of floodgates were com-
pleted.
    Arkansas River levees: Enlargement of 4.5 miles of levees on
the north bank was completed and 11.3 -miles of south banik-levees
were restored.
    Memphis district: a. St. FrancisBasin, Ark. and Mo., Wappapel-
lo Reservoir. (See table C.) The facility was maintained in oper-
ating condition and malaria control operations were continued.
Leasing of reservoir lands was continued, and a patrol of the leased
property was maintained. The fish and wildlife conservation pro-
gram conducted jointly with the Missouri Conservation Commis-
sion was continued. It is estimated that there were 164,000
visitor days of use of recreational facilities in the Wappapello
Reservoir area. The reservoir was nominally empty of flood
storage at the begining and end of the fiscal year, and the water
level was controlled insofar as possible in accordance with the
malaria control program. Maximum water surface elevation dur-
ing the year was 363.87 feet on June 11, with a net flood storage of
71,400 acre-feet. Peak inflow into the reservoir was 20,700 cubic
feet per second on June 9. Maximum outflow during the year was
7,000 cubic feet per second, occurring on June 11, 1954.
  Levees: Levee construction was continued in the basin with the
placing of 6,844,000 cubic yards of earthwork.
                        MISSISSIPPI RIVER COMMISSION            1599
    Dredging: Dredging operations began February 5, 1954, for
channel excavation of 24,000,000 cubic yards in the Madison-
Marianna, Arkansas, floodway. One contract dredge removed
2,865,265 cubic yards of material.
    West Memphis drainage:A total of 341,177 cubic yards of mate-
rial was excavated during the fiscal year. A contract for the
enlargement of approximately one mile of Ffteen Mile Bayou and
2.5 miles of new diversion ditch of Ten Mile Bayou in Crittenden
County, Ark., was completed December 19, 1953.
    b. White River Basin. The construction of a levee and pumping
station at Des Arc, Ark., was completed February 25, 1954.
    Floods-Memphis district: Rains occurring over the upper
reaches of the Mississippi River and Ohio River Basins during
January 1954 resulted in a Mississippi River crest stage of 31.25
feet on the Cairo gage on January 27, 1954, with a corresponding
maximum discharge of about 600,000 cubic feet per second. Con-
fined floods occurred in the St. Francis River Basin during May and
June 1954 with a maximum stage of 17.25 at St. Francis Town,
Ark., on June 19, 1954. On the White River a maximum stage of
26.1 feet occurred at Clarendon, Ark., on May 11, 1954.
    Vicksburg district: Crest stages on the Mississippi River were
the lowest of record, ranging from about 24 feet below flood stage
at Arkansas City to about 20 feet below flood stage at Natchez.
These crest stages were 8 feet below the previous lowest crest stage
of record (1941) at Arkansas City and 5 feet below the 1941 crest
stage at Natchez. Crest stages on the upper Ouachita River ranged
from 2 feet to 6 feet above flood stages and were below flood stages
in the lower reaches of the Ouachita River. Minor flooding oc-
curred in the upper reaches in May. Operation of flood control
works effected estimated stage reductions of 2 feet to 5 feet on the
upper Ouachita River. Crest stages on the Coldwater-Talla-
hatchie-Yazoo Rivers occurred in January. The crest stages of
23.8 feet at Swan Lake and 24.0 feet at Greenwood were the second
and third lowest of record, respectively.
    New Orleans district: No flooding of consequence occurred in the
New Orleans district. Unusually low stages prevailed throughout
the year. On the main stem Mississippi River, Carrollton gage
 (flood stage 17.0) recorded a maximum stage of 7.7 on May 16
through 18 and on May 21. On the Red River, Alexandria gage
 (flood stage 32.0) recorded a maximum stage of 26.66 on May 17.

               CONDITION AT END OF FISCAL YEAR

   Survey of the entire river below Cario, Ill., was completed in 1952
and resurvey is now under way. Contoured quadrangles, general
maps of the valley, and pamphlets tabulating river stages, dis-
charge measurements, etc., have been published and are available
for departmental use and public distribution under prescribed regu-
lations. Navigation and flood control improvements under the
existing project comprise levees, bank protection works, channel
improvements (including cutoffs), floodways, outlets, and tributary
basin improvements, summarized as follows:
   There are 1597.9 miles of project Mississippi River levees, with
     Sig 51-1599-1630
1600     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

earthwork aggregating about 1,000,349,000 cubic yards, below
Cape Girardeau as listed in tables E-1 through E-3. Construction
of project levees above Cape Girardeau under the provisions of
section 6 as shown on table E-4 has been supplemented with addi-
tional work authorized by the Congress under the provisions of the
Flood Control Act of 1936 and subsequent acts. Roads have been
constructed on 73.6 miles of levees in the New Orleans district of
which 27 miles were constructed by local agencies, on 102 miles in
the Vicksburg district, including 38 miles which constitute a por-
tion of Louisiana State Highway No. 49, and 29 miles in the Mem-
phis district. These figures represent graveled or hard-surfaced
roads on levees; roadway embankments have been constructed for
possible future surfacing on 451.3 miles in the Vicksburg district
and 442 miles in the Memphis district. In the New Orleans district,
about 36 miles of levees on the right bank and 13 miles on the left
bank are protected against wave wash by timber structures, and
about 50 miles of levees on the right bank and 32 miles on the left
bank are protected by pavement on the riverside levee slope.
    There are in place 281.56 miles of operative bank revetments on
the Mississippi and Ohio Rivers and about 24.46 miles on the
Arkansas and Red Rivers as listed in tables D-1 through D-3.
    A channel 9 feet by 300 feet is maintained by dredging as re-
quired during the low water season. During the high water season,
which usually prevails from the 1st of January to the 1st of June,
greater navigation depths are available between Cairo, Ill., and
Baton Rouge, La. Below Baton Rouge, La., a channel 35 by 500
feet is maintained by dredging as required during the low water
season under the river and harbor project, "Mississippi River,
Baton Rouge to the Gulf of Mexico, La."
    Since 1928 annual maintenance and premaintenance dredging
have averaged about 30 million cubic yards. In years of extreme
low water of long duration, as much as 75 million cubic yards may
be removed in the maintenance of the 9- by 300-foot channel be-
tween Cairo, Ill., and Baton Rouge, La. Channel improvements
accomplished by improvement dredging to increase the flood-carry-
ing capacity of the river now form part of the main river channel.
These improvements, which include 16 completed cutoffs, have
reduced the distance from Baton Rouge to Cairo to about 737 miles
from about 860 miles in 1929. The effect of channel improvement
works on carrying capacity of the river is given on page 1811,
Annual Report of Chief of Engineers for 1943.
    Levees have been built to approved grade and section on the west
side of the Atchafalaya Basin from Mansura Hills to Hamburg to
confine floodwaters within the West Atchafalaya floodway and the
Atchafalaya River, and along Bayou des Glaises from Hamburg to
Simmesport. Continuous levee systems, except at certain railroad
and highway crossings, extend along the east and west limits of the
floodway. The east protection levee starts 3.3 miles below Lottie
and extends southward to Morgan City; 73.1 miles of the 91.9 miles
in this levee system have been built to grade and section. On the
extension south of Morgan City to Cut-off Bayou, levees are being
constructed on Tiger Island and Avoca Island, with 8.9 miles of the
16.2-mile total completed to grade and section at Avoca Island.
                   MISSISSIPPI RIVER COMMISSION                1601
  The west protection levees extend from Hamburg to Wax Lake
  Outlet and thence to Berwick, with 121.5 miles built to grade and
  section. A system of levees is partially complete west of Berwick
  and the lower Atchafalaya River from the Berwick drainage canal
to Wax Lake Outlet and thence to the Charenton drainage canal,
including Bayou Sale and Teche Ridge levees of the 60.9 miles in
this system, 53.5 have been built, and 38.1 are to approved grade
and section. For status of these levees, see table E-1.
     Floodway and basin improvements, other than levees, completed
prior to 1943 are as described on pages 1884 and 1885 of the Annual
Report of the Chief of Engineers for 1943. Improvements com-
pleted since then include:
     Atchafalaya floodway: A drainage structure at Brushy Bayou in
the Simmesport ring levee; two drainage structures in the Melville
ring levee; floodwalls at Morgan City, Berwick, and Tiger Island,
1,891, 5,219, and 1,990 feet in length, respectively; pumping plant
in Morgan City; locks at Berwick, Bayou Sorrel, and Bayou Boeuf,
except for approach channels to Bayou Boeuf lock and closure of
Bayou Boeuf; a floodgate at Charenton drainage canal and at
Calumet on the east and west sides of Wax Lake outlet; a channel
9 by 100 feet from Bayou Boeuf to Bayou Long, which acts as a
drainage outlet for the floodway and forms a part of the alternate
route for the Gulf Intracoastal Waterway; enlargement of the
Charenton drainage and navigation canal to a 75-foot bottom width
at -30 feet mean sea level; construction of a bridge at Charenton
floodgate which provides access to the West Atchafalaya protection
levee in the vicinity; improvement of interior drainage west of
Berwick by construction of Ellerslie pumping station, Wax Lake
West drainage structure, and excavation of a channel from Calumet
to Wax Lake east levee borrow pit; modification of the Melville
Bridge by the Texas & Pacific Railway Company; and construction
of the Ville Platte-Opelousas and Ville Platte-Bunkie connections
by the Texas & Pacific Railway Company.
    Improvements, other than levees, now in progress are as follows:
In the drainage area west of Berwick, construction of Wax Lake
East drainage structure is approximately 29 percent complete, and
contracts have been awarded for delivery of pumps and construc-
tion of a pumping station at Bayou Yokely.
    Between Courtableau and Krotz Springs, over the West Atchafa-
laya floodway, construction of the New Orleans, Texas & Mexico
Railway Company's high-level crossing is about 92 percent com-
plete. Surveys and borings have been completed along the aline-
ment for the proposed high-level crossing of U. S. Highway No. 190,
and negotiations are being conducted with the State of Louisiana,
Department of Highways, for an agreement covering the design
and construction of the crossing; a draft of the agreement has been
forwarded to the Department of Highways for approval.
    The Atchafalaya Basin floodway, as a whole, is approximately 77
percent complete.
    At the upper end of the Morganza floodway, the combined high-
level crossing for State Highway No. 30, the Texas & Pacific Rail-
way's Port Allen branch line, and the Morganza control structure
has been in condition to be placed in operation, if needed, since
1602     REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

completion of the superstructure on February 9, 1953. Principle
features comprising the combined crossing which have been com-
pleted include the superstructure, railway relocation, embankment,
riprap and derrick stone protection, relocation of telephone and
power lines, and clearing of the forebay and structure area. Under
a reimbursable contract with the Highway Department work is in
progress on temporary surfacing of the approach embankments
with the contract being approximately 41 percent complete. The
combined high-level crossing and control structure is approxi-
mately 95 percent complete with work remaining to complete
consisting of completion of temporary surfacing of approaches,
permanent paving for State Highway No. 30, closure of levee gaps,
alteration of reservation facilities, degrading the Mississippi River
frontline levee, and deferred construction as provided under the
reimbursable contracts.
   The Morganza floodway is approximately 92 percent complete.
   Levees extend along both banks of the Atchafalaya River. Ap-
proximately 47.8 miles of the 50.8 miles in the east bank system
and 59.0 miles of the 61.3 miles in the west bank system have been
built to approved grade and section.
   A total of 16,482,158 cubic yards has been excavated and 2.2
miles cleared and snagged for channel improvement and diversion
in Bayous Boeuf, Cocodrie, and Clear. An improved and continuous
channel is complete from mile 0.0 to the Bayou Rapides drainage
structure, a distance of 59.8 miles. Drainage structures have been
completed on the south bank of Bayou Rapides and in Bayou Boeuf
at Lecompte, and the Lamourie control structure has been com-
pleted on Bayou Lamourie. Twenty-one highway, 4 railroad, and 2
footbridges have been constructed or reconstructed. The overall
percentage of completion is 79 percent for the Bayous Rapides,
Boeuf, and Cocodrie improvements.
   Channel improvement in the Boeuf and Tensas Basin has been
completed as follows: 89 miles in Big and Colewa Creek; 85 miles in
Tensas River; 14 miles in Tensas Bayou; 45.1 miles in Bayou La-
fourche; 8.7 miles in Boeuf River, and 8 miles in Big Bayou. The
improvement of these streams involved clearing and snagging, and
49,885,973 cubic yards of excavation. Reconstruction of four
parish bridges and of three State Highway bridges over Big and
Colewa Creek is complete. Over Bayou Lafourche construction of
State Highway No. 64 bridge, reconstruction of State Highway No.
15 bridge realinement and alteration of existing United States
Highway No. 80 bridge are complete, and reconstruction of Illinois
Central Railroad bridge is complete except for observation of scour
around the piers. Construction of new United States Highway No.
80 bridge is in progress. Relocation of Richland-Morehouse Parish
bridge is complete.
   Rearrangement of one 8-inch gas pipe line over Bayou Lafourche
at mile 18.1 is complete. Alteration of one 16-inch and four 13-inch
gas pipe lines and appurtenances over Bayou Lafourche at mile
35.7 is complete. Alteration of two coaxial cables over Bayou La-
fourche at mile 35.3 is complete. Reimbursement was made for
relocation of a private telephone line and power line over Bayou
Lafourche between miles 25 and 30. In addition, over Bayou La-
                    MISSISSIPPI RIVER COMMISSION                1603
fourche, alteration of one power transmission line at mile 35.2 is
complete and rearrangement and alteration of one telephone line
at mile 34.5, is in progress, and rearrangement of 6 power lines and
alteration of a multiple gas pipe line are complete.
    Over Boeuf River, State Highway No. 11 bridge is complete.
    In the Red River backwater levee project, construction of 72.0
miles of levee has been completed to final grade and section except
for reaches totaling approximately 4,300 linear feet in the vicinity
of the Bayou Cocodrie drainage structure (See table E-2). The
Woringer Bayou bridge and drainage alterations are complete.
Construction of a drainage ditch in the vicinity of Acme, La., is
essentially complete.
    The Jonesville, La., project is complete.
    In the Bawcomville, La., project, construction of the new levee,
culverts, temporary flap gates, concrete splash aprons and closure
gaps is complete. Plans and specifications for construction of two
pumping stations and modification of floodgates are complete. The
work is being accomplished under section 6 of the Flood Control
Act of May 15, 1928.
    In the Yazoo Basin, the Sardis, Arkabutla, Enid, and Grenada
Reservoirs are in operation and necessary repairs are being made
to the dams and appurtenant structures. Minimum basic public
use facilities have been provided in the Sardis, Arkabutla, and Enid
reservoir areas. The master plan for public use facilities for
Grenada Reservoir has been approved by the Office, Chief of Engi-
neers. The 4-H Club of North Mississippi, sponsored by Missis-
sippi State College, Starkville, Miss., has constructed the following
facilities at Sardis Reservoir in the Black Jack Point area. pump
house; crafts building; warehouse; caretaker's house and garage;
staff quarters building; administration building and dining hall; 12
bunk houses and two bath houses. The Mississippi State Park
Board has constructed the following facilities at Sardis Reservoir
in the Chestnut Ridge area: lodge and dining hall; 10 duplex cot-
tages; superintendent's residence; well and pump house; and a
floating boat dock. The Future Farmers of America, sponsored by
the State of Mississippi Department of Vocational Education, have
constructed the following facilities at Grenada Reservoir in the
Grenada Landing area: two bunk houses; combination recreation
and dining hall; sewage disposal field; a two-acre swimming and
fishing lake: a pier; and a gravel surfaced access road half mile
in length. Yalobusha, Grenada, and Calhoun Counties have con-
structed a public swimming beach in the same area. In the Cedar
Point area in Grenada Reservoir, the Girl Scout Campers of Missis-
sippi, Inc., have constructed a dirt road 11/4 mile in length. Channel
improvement in the basin has been completed in the Yazoo, Talla-
hatchie, and Coldwater Rivers and Cassidy and Bobo Bayous except
for the construction of two cutoffs in the Tallahatchie River and
one cutoff in the Yazoo River and the removal of plug in the upper
end of Cassidy Bayou. Construction of Jonestown cutoff, in the
Yazoo River, is complete. Improvement of Little Tallahatchie
River and Panola-Quitman floodway is complete except for addi-
tional work that will be required in the floodway. Improvement of
Yalobusha River is essentially complete. Improvement of these
1604     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

streams involved clearing and snagging, and 29,224,422 cubic yards
of excavation. Construction of Greenwood protection works is com-
plete except for the Pelucia Bayou diversion and extension of
levees.
   Channel improvement in the Big Sunflower River, etc., Miss.,
project has been completed as follows: 19.22 miles in Big Sunflower
River; 16.15 miles in Quiver River; 7 miles in Deer Creek; and 44.7
miles in Steele Bayou. Improvement of these streams involved
clearing and snagging, and 3,524,584 cubic yards of excavation.
   Enlargement of 17.4 miles of the north bank Arkansas River
levees and 76.0 miles of its south bank levees has been completed to
approved grade and section. (See table E-2.)
   In the St. Francis Basin, the Wappapello Reservoir is complete
and available for use as required. On the west bank of the St.
Francis River, 73 miles of levee are to project grade and section.
On the east bank of the St. Francis River, 80 miles of levee are to
project grade and section. In the Elk Chute drainage district, 17
miles of levee are to project grade and section. The levees along
Little River are complete. Work on levees and drainage improve-
ments is in progress. Work was continued on West Memphis
drainage project.
   Work on the Memphis Harbor project was started on May 24,
1948 and is about 58 percent complete. The features of work that
have been completed are as follows: The closure dam, batture em-
bankment, pile dikes, wavewash protection, approach fill and road-
way, and revetment. Work on the access channels is about 63 per-
cent complete, the industrial fill is about 63 percent complete, and
the Nonconnah Creek sewer extension is about 80 percent complete.
   In the White River Basin area of the Memphis district, on the
Augusta to Clarendon levee project, 40 miles of levee have been
completed to project grade and section. The Clarendon levee is
complete.
   The Des Arc project has been completed.
   Surveys and reports prescribed under the existing project and
called for by congressional or departmental directives are made as
required. Reports on tributary streams authorized pursuant to the
act of January 21, 1927, when presented to the Mississippi River
Commission in compliance with section 10 of the act of May 15,
1928, are considered and the conclusions and recommendations of
the commission thereon are submitted to the Chief of Engineers.
   Total costs under the existing project, incurred from United
States and contributed funds to June 30, 1954, were $1,019,175,-
091.96 for new work and maintenance (see table H-1), and $14,410,-
493.57 for emergency repairs. Similarly, total costs for construc-
tion and maintenance of levees under the existing project and
expenditures incurred therefor by non-Federal agencies are given
in table H-2.
                                                                         TABLE          D-1.      New Orleans district
                                           (Bank protection works built during fiscal year and operative protection in place June 30, 1954)

                                                                                                                          Maintenance                 Lost, de-
                                                      Year            Above                                                                          stroyed or       Opera-
                  Location                          initiated         Head of          Bank        New work                                          nonopera-      tive 1 on                  Type
                                                   (calendar)         Passes                                                                         tive since      June 30,
                                                                                                                  Extensions     Repairs              June 30,         1954
                                                                                                                                                        1953
                                               I                I*
                                                                1--      ---    I-       --       I- --     -I-           -                     -I                                I

              MISSISSIPPI RIVER
                                                                      Miles                        Linear feetI Linear feet      Squares2 I Linear feet           I Linear feet
                                                                                                                                                                                                                   H




Buras, La...--------------------                      1953                25.1   Right --      2,900                                                                     2,900        AB.
Port Sulphur, La _---                                 1952                39.0   .__do......                                                                             1,820        FW.
Third District Reach, La               -              1890               91-95 Left.......         -----------    -------                                               20,542        A, AC, FW, MA.           a,
Algiers Point, La ...-                                1899               94-95 Right-_--.                                                564                             7,728        A, FW, MA, CB, AB.       03
                                                      1885               95-96 --.do....                                                                                 4,960        A, AC, FW, AB.
                                                                                                                                                                                                                   H


Gouldsboro Bend, La                 --
Gretna Bend, La__----------                           1911               96-97                                                                                           4,127        FW, AB, CB.
Greenville Bend, La_                                  1890              99-102  ---   do------_
                                                                                 -.do.....                                             752                              19,870        A, AC, FW, MA, AB, CB.
Carrollton Bend, La_                                  1884             103-105 Left__..-                                             1,233                              15,015        A, FW, CB, AB, AC, MA.   0
Avondale Bend, La - -                                 1914             106-108 Right ....                                                80                             15,098        A, FW, AB, MA.
Kenner, La ---................                        1936             113-114 Left.... -                                               100                              9,089        A, FW, AB.               C
Reserve, La__                                         1938             138-139 --_do _..                                               458                               6,032        A, AB.
White Castle, La _--                                  1935             193-194 Right ....                                            1,632                               7, 282       A, AC, AB, MA.           U,
Plaquemine Bend, La _                                 1912                            - . .-
                                                                       208-216 -- _do ..                                             4,994                              14,761        A, AC, FW, CB, AB, MA.   U,
Port Allen, La- .....-------------                    1953               229.5 --- do      -.  2,320              .. I.                                                  2, 320       AB.
Arbroth, La- --- _--------------------                1950             248-250 _--do ._..                                               1,680                           13,190        AC, AB.                  0



Grand Bay, La         ----         ---                1917             255-257 --_do ...--                                                                               7, 090       A, AC, FW, CB, AB.
Morganza, La..                                        1951             277-278  l---do-------                                           1,011                           13,310        AC, AB, MA.
Carr Point, La-----------------                       1949             301-302 _--do ...--                                                907                            8,600        AC, MA, AB.
Above Old River, La.__                                1950               302.5 _--do ..---                                                 95                            4,800        AC, AB.
                                                                                                                                                                                                               Mai




Coochie, La              __-                          1953               315.0                14, 560                                                                   14,560        AC.
                                                                                                                                                                                                               z
                                                                                                                                                                                                               0
                                                              TABLE D-1.            New Orleans district-Continued
                                                                                                                                                                                                            C)
                                               (Bank protection works built during fiscal year and operative protection in place"June 30, 1954)

                                                                                                                             Maintenance                   Lost, de-
                                                        Year        Above                                                                                  stroyed or          Opera-                       C
                      Location                        initiated    mouth of            Bank            New work                                            nonopera-          tive 1 on
                                                                                                                                                           tive since         June 30,               Type
                                                     (calendar)    Lower
                                                                     River                                            Extensions         Repairs            June 30,            1954
                                                                                                                                                              1953                                          0
                                                                                                                                                                                                            h




                     RED RIVER                                        AMiles                           Linear feet     Linear feet       Squares 2         Linear feet       Linear feet                    H
Choctaw Bayou Bend, La_                                  1948             71.6      Right .                            --.                                                      3-------
                                                                                                                                                                                3 1, 563   PD.
Egg Bend, La_ __                                         1950             89.6      __do                            . . -. . . . . .
                                                                                                                    -.                 . . - -..
                                                                                                                                             . . ... . . . . . . . . . . .      4 1, 1 2 7 PD.
(Mile 90) Egg Bend, La ....                              1946                  90     do--- --
                                                                                    ---               _------ _ -                    ------------                                 1, 350   SD.
(Mile 90.9) Egg Bend, La_                                1954             90.9      __do__                                   700                                                     700 BR.
(Mile 91) Egg Bend, La ....                              1948               91      __do___                                                                        350          5 1,464 PR.                 0
Cologne Bend, La___                                      1950             92.1      __do                                                                                        6 1,635    PD.
Echo, La ...................                             1950             93.9      -do
                                                                                    __-do-------------------
                                                                                         -----   ------------ I
                                                                                                                  -------- :- -- -- _--    :____---- _--      -------             1,849 PD.
                                                                                                                                                                                7 1,5549
Richardson, La ............                              1951             94.5                                                                                                  8 1,556 PD.
Roxana, La__                                                                         -d o - --- - - - - -
                                                         1952             99.0                                                                                                    2, 200 BR.
Ryland. La ................                              1952            104.0      -d o . - -- - -- - - -                        -                                               2, 600 BR.
Hudson, La_
Alexandria Front, La_
                                                         1950            115.3      -do                                                                                           1,458 BR.                 z
                                                         1945              122                                                                                                    5,550 BR, A, RG.
Bertrand, La ....                                                                   -do
                                                         1946        139-139.5
                                                                                    -do                                                                                         - 5,014 PD.                 zCq
Boyce,_La_          ---------------                      1950              143        do             -                                                 i                       10 1, 069   PD.
       Total -       -                                                                                                          110          13,506                120         13 198, 644
                                                                                                   i




                                                                                                                                                                                                            C:
   1 This conforms with the definition of an operative revetment which is as follows. The                      8 Includes 324 linear feet of root dike.
classification "operative" is intended to include all revetments which are along the banks                     9 Includes 162 linear feet of root dike.
of the river channel and are, or conceivably would be, subject to maintenance charges                          10 Includes 691 linear feet of root dike.
if subjected to direct current impingement.                                                                    11Does not include 700 linear feet of board revetment.
   2 Squares = 100 square feet.                                                                                12Does not include 350 linear feet of pile revetment.
   3 Includes 222 linear feet of root and 99 linear feet of baffle dikes.                                      13Does not include 23,585 linear feet of dikes, groins, board and pile revetments.
                                                                                                                                                                                                            ci
   4 Includes 192 linear feet of root and 935 feet of spur dikes.                                              A = asphalt; AC = articulated concrete; FW = frame willow; CB = concrete blocks;
   5 Includes 132 linear feet of root, 60 linear feet of baffle, and 360 linear feet of spur dikes.           AB = asphalt blocks; MA = mass asphalt; SD = triangular steel dikes; PD = pile dikes;
   6 Includes 168 linear feet of root dike.                                                                   RG = rock groins; PR = pile revetment; BR = board revetment.
   7 Includes 240 linear feet of root and 193 feet baffle dikes.
                                                                                                                                                                                                            ©y
                                                                                          TABLE D-2. Vicksburg district
                                                         (Bank protection works built during fiscal year and operative protection in place June 30, 1954.)


                                                                                                                                             Maintenance                               Lost, de-
                                                                 Year           Above                                                                                                 stroyed or          Opera-
                        Location                               initiated        Head of       Bank                  New work                                                          nonopera-           tive on                   Type
                                                               (calendar)        passes                                                Extensions                Repairs              tive since         June 30,
                                                                                                                                                                                       June 30,             1954
                                                                                                                                        or repl.                  epairs                  1953
                                                                            i                                                     I-                                              I                 I
                                                                                 Miles                              Linear feet        Linear feet               Squares              Linear feet   ( Linear feet
                   MISSISSIPPI RIVER
                                                                                                                                                                 A   170
Bougere Bend, La __               -                              1950            326.5      Right_                                                               AC 175                                     18,150    AC, A, R.
                                                                                                                                                                 R    20
                                                                 1948            352                                                                             AC 3,700                                    5,650    AC, A, MA, R.
Morville, La_                                                                               __do ...                                                             A    76                                                                   00
                                                                 1949            354        __do ....                                                                                                   1    1,852    Pile dikes.
Natchez Island, La___                                                                        _do -.                                                                  --------                                1,318    Retards.             U1
                                                                                                                                                                                                                                           00
                                                                                                                                                                                                                                           H




                                                                 1949            354        __do ---                                                                                                         4, 565   AC, A, MA.
Natchez Front, Miss _-                --                         1908            360        Left__ __                                                                                                        6,045    AC, W, R.            00
                                                                                                                                                                 A        297                                6,940    AC, A, R.
Gibson, La-__    --------                            -           1952            368        Right___                        40                   100             AC       558
L'Argent, La.......                         ..   .               1948            372.5       do ....                                                              - -- --                                    1,920    Asphalt groins.
                                                                 1900            379                                                                             AC       101                               14,805    AC, A, MA, W, R.     H
Kempe Bend, La ..........................                                                   ___do....                    2,055
                                                                  1930                                                                                           AC       706                               22,530    AC, A, MA, R.
Hardscrabble, La__                                                               394.6      __.do-.                                                              A         70
                                                                  1947                                                                                           AC        95                                6,840    AC, A, CB, R, MA.
Reid-Bedford, La _-                                                              425            ....
                                                                                            ___do                                                                                                                                              00
Barge Line Terminal, Miss_                                        1928           432-433    Left ....                                                                                                        3,040    W, CB, AC, R.
Vicksburg Harbor, Miss__                                          1917           432        ___do                                                                                                            7,350    AC.                  C2



Opposite Delta Point, La         - -                              1952           432        __do..                                                               A        130                                5,680    AC, A, R.
Delta Point, La-        ----------                                1879           432        Right___                                                                                                         3,450    W.
                                                                  1933                                                                                           AC 4,378                                   12,390    AC, A, R.
False Point, La ---
                _-                                                                436       ___do__                                                              A    658
                                                                                                                                                                                                                                               H




                                                                  1952                                                                                           AC 6,716                                   15,950    AC, A.
Marshall-Brown's Point, Miss _                                                    441       Left ....                     1,690                   700            A  1,870
                                                                                                                                                                                                                                                   H




Milliken Bend, La_____                                            1923            447-451
                                                                                            Left ..
                                                                                            Right__                                                          1R
                                                                                                                                                                 AC    273
                                                                                                                                                                             30
                                                                                                                                                                                                            30,770    AC, A, W, CB, R.
                                                                                                                                                                                                                                           O


                                                                                                                                                                                                                                               z
                                                                                                        --     i---
                                                                                                                                                                 A        199
Belle Island, La.-Miss_                                           1953            453.4     Left ---                     11,440                 .--..                    -                                  11,440    AC, A, R.
                                                                  1925                                                                                  +        AC     2,104         .                     23,175    AC, A, CB, W, R.
Goodrich, La__________________                                                    460       Right -                                ----------------------        A           215
Cottonwood, Miss_                                                 1917            465       Left __-                                                                                                         2,000    W.
                                                                                                                                                                                                            13,470    AC, W, A, R.
Fitler Bend, Miss____                                             1908            470       __do__
                                                                                                             ----
                                                                                                                      ----------------------                ;1   AC          33


Hagaman, La__________________                                     1926            478       Right                                                                                                           12,000    AC, W.


                                                           N
                                                                  1904

                                                           --
Lake Providence, La___                                                            482       ___do..                                                                                                         11,600    W.
                                                                  1948            489       Left ...                                                                                                        18,825    AC , A.R.
Mayersville, Miss -----------                                                               _.do ..-                             i-
                                                                                                                                 ,5
                                                                                                                                  . ..... ........
                                                                                                                                      ------  --
                                                                                                                                           ....... A..... 1521
                                                                                                                                                     --.. .... ....                                     1    2, 684   Retards.
                                                                  1948            490                                                                                                                                 Pile dikes.
                                                                                                                                                                                                             1,386

   See footnotes at end of table.
                                                                        TABLE D-2. Vicksburg district-Continued
                                                (Bank protection works built during fiscal year and operative protection in place June 30, 1954.)

                                                                                                                                  Maintenance                           Lost, de-
                                                                                                                                                                        stroyed or                  Opera-
                                                              Year       Above                                                                                          nonopera-                   tive on
                     Location                              initiated     Head of         Bank                                                                                                                                Type
                                                                                                                                 Extensionstive                              since                 June 30,
                                                           (calendar)    passes
                                                                                                                                  l.
                                                                                                                            Extensions    Repairs                        June 30,                    1954
                                                                                                                            or repl.                                       1953
                                                  1   i1

                                                                          Miles                                             Linearfeet           Squares                Lineal feet               Linear feet                                    O
        MISSISSIPPI RIVER (Continued)
                                                                                                                                                 AC 6,679
Cracraft, Ark ........
                   ____-          ---   ----.                 1943         501        Right ____                  6,850             200          A 1,686                           1,150               9,300    AC, A, CB.
                                                                                                                                                 R     111
                                                                                                                                    565          A 1,755
                                                                                                                                                 AC    504                         --                 0
                                                                                                                                                                                                      10,115    AC, CS, CB, A.
Kentucky Bend, Miss -----------------                         1944         509         Left-....                                    565
                         . . . . . .                          1933         517        ,__do._.                                                                                     2,280               5,000    AC.
Am erican C utoff, M iss__________                                                                                                                                  2
                                                                                                                                                 AC             8                     .               11,305    AC, CS, A, CB, R, W, SC.         M
Sunnyside, Ark---------------------                           1923         523         Right_____                          ------------  IA         2
                                                                                                                                                    28
Vancluse, A rk__ ........................                     1909         525        __do___      l-                                                                                                  4,300    W.                               p
Island 84, Ark ...................                            1949         526         Left -- ___                         ------------------------------------                                        4,685    AC, A.
Warfield Point, Miss- ------------                            1934         529         Left,..-                                                                                                        3,200    CS, A, AC, T, R.
La Grange Towhead, Miss_                                      1934         530        ___do.---... .                                                                                                   2,950    AC, T.
                                                                                                                                                                                                       3,660    AC, A.
Spanish Moss, Ark _-----------------.                         1952         531         Right -...                 1,660             150          A 2,913--_____
                                                                                                                                                 AC '249
                                                                                                                           ------------ I                   1


Leland Cutoff, Ark ----------------                           1934         532         Left ..__- -                                                                                                    1,300    AC.
Tarpley Island, Miss ..----------                             1949         534         Right .----                         ------------ . . ..--
                                                                                                                                            --------                    . . . . . . . ..-              2 ,0 00 AC, A.
                                                              1928         537         Left ... ..                                       .A       64                                                   4,550 AC, A, CB, FCM, R.
                                                                                                                                                                                                      2------------
Miller Bend, Miss __-------------------                                                                                                    R      10
                                                                                                                                          -AC 1,390                                                    2,620 AC, A, R.
Ashbrook Island, Miss --------                                1949         541.5       Right .--.                                        AC---6
                                                                                                                                              30                                                      11-5A
                                                              1921         545-549     _do --                              ....          A
                                                                                                                                   .....--    35 --.
                                                                                                                                                   ... ... ..-                                        25,100 AC, CB, A, R, W.
Arkansas City and Yellow Bend, Ark_ _
Huntington Point, Miss --                                     1949         550         Left .......
                                                                                                  ...                                         15                                                          8A AC, A, R.
                                                                                                                                                                                                      9,625
Mounds, Miss -------------------------                        1946         556           do-                                                                    0   ------------              !        2,62
                                                                                                                                                                                                             FCM, AC, A, CB.                     0
Riverton, M iss ........................                      1920         578        __do ..-
                                                                                            -       -     -   -
                                                                                                                                                                                                        ,12,
                                                                                                                                                                                                          00 AC, W.
                                                                                                                                                                                                             AC, A, R.
Dennis, Miss....------------------------                      1947         504         --------         --                                       R          55
Cessions, Miss ... _--------    -----------                   1944         610        ___do.......                                         - AC -_
                                                                                                                                                 146                -11,350                                     AC, A, R.
                                                                                                                                             -A           405
                                                                                                                                                                                                       3,2080
                                                                        Miles above                     Lixnear feet        Linear feet          Squares                Linear feet               Linear feet
                 ARKANSAS RIVER
                                                                         mouth

                                                              1945          36        Right-........                                 ----                           -                                  2,187    Pile dikes.
Fletcher Bend     _____--------------.----.


                                                                                                                  :il
                                                                                                                  ...
Davis Lake, Ark-.__------------            .                  1950          38        -..do-....                                      -- - -- - -- --
                                                                                                                                  -- --                                 -- -       ---                 3 ,208   Pile dikes.
                                                                            44. 5      __do..-- ---                                                             -                                      2,900    AC, Board mat.
Pendleton, Ark .         .__------------ .                  S 1920
                                                              1928          44.5                  --
                                                                                       __do-......-
                                                                                                                     -__
                                                                                                                                                                                                                Spur levee dike, revetted end.
Big Bayou Meto, Ark--------- ----                             1944          53        Left....-         ---                               - --       - -9, ---::-                       ---               650
                                                                                                                                                                                                         9--    Board mat and riprap.
Hannaberry Lake, Ark ......          - ---.                   1947          60        __.do..... -- -                             S-- --                                                100            5,685    Pile dikes.
Cummins Bend, Ark.._- -------------.                          1946          63        Right... -- I---                            -  -.                             :          i                       9,938    Pile dikes.

  See footnotes at end of table.
                                                                            TABLE D-2. Vicksburg district-Continued
                                                      (Bank protection works built during fiscal year and operative protection in place June 30, 1954.)


                                                                                                                                 Maintenance                      Lost, de-
                                                                  Year       Above                                                                               stroyed or       Opera-
                                                                                                                                                                 nonopera-        tive on
                     Location                                   initiated    Head of       Bank             New work                                                                                             Type
                                                                                                                                           Repairs                Jvesince       June 30,
                                                               (calendar)     passes                                       Extensions                                               1954
                                                                                                                            or repl.       Repars                 J19530
                                                                                                                                                                                               i



        ARKANSAS RIVER (Continued)                                          Miles above                     Linear feet     Linear feet     Squares              Linearfeet      Linear feet
                                                                              mouth
                                                            1949                66      Left-......                                                                                   3,465        Board mat and riprap.
Little Bayou Meto, Ark-_ .               -...-... -         1947                67      _do...._-                                                                                     3,480        Pile dikes.                 00
Kimbrough, Ark..... . __           - ---                    1953                 68      Right -...                                                                                  33, 000       Board mat and riprap.       00
King's Bayou, Ark-----------------               --         1951                 75      Left_______                                                                                  2, 150       Pile dikes.
Rob Roy, Ark__----------------------                        1946                 89      Right -                                                                                      1, 790       Board mat and rock dikes.   i-4

Pine Bluff, Ark ...                                         1946
                                          _..--------------------
                                                    --
                                                                                 96       _do_-                                                                                       6,627        Pile dikes.
                                                            1943                 97      .. do                                                                                        5,400        W, R.
                                                                                                                                                                                                                               1--
                     R. &H.2
                                                                                                                                                                                                                               01-4
M edford Bend, Ark--_.-.....     --    .- ....-.---                1952         38      -- do--                                                                                       4,190        Board mat     and riprap.
Richland Bend, Ark _--                                         St  1952
                                                                   1952
                                                                                77
                                                                                77
                                                                                         _do...-
                                                                                        -_odo   -
                                                                                                                                                                                      1,455
                                                                                                                                                                                      1,997
                                                                                                                                                                                                   Board mat
                                                                                                                                                                                                   Pile dikes.
                                                                                                                                                                                                                 and riprap.

Brunson's Crossing, Ark _-
New Gascony, Ark.....
                                                          -I   {   1952
                                                                   1952
                                                                   1952
                                                                                79
                                                                                79
                                                                                81
                                                                                         Left ----
                                                                                         -- do ---
                                                                                          __do- -----
                                                                                                                                                                                      4,260
                                                                                                                                                                                        282
                                                                                                                                                                                      1,705
                                                                                                                                                                                                   Board mat
                                                                                                                                                                                                   Pile dikes.
                                                                                                                                                                                                   Pile dikes.
                                                                                                                                                                                                                 and riprap.


                                                                   1953         83       Right -- __                                                                                  2,975        Pile dikes.
New Gascony, Ark. (Trulock)-
                                                        ---    {   1954         83      -__do-......         2,827 ----------
                                                                                                             ........
                                                                                                                : ---------
                                                                                                                   :::-:.:::::::::: :.::::::::::                                      2,400        Board mat     and riprap.   r

                                                          :11  {   1953         83. 7     Left   -____                                                                                2,827        Pile dikes.
New Gascony, Ark. (Madding).                                       1953         83.7     __do____- _        -'-------     -----------
                                                                                                               9--------483.        -
                                                                                                                                          ----------             -----
                                                                                                                                                       ..---------
                                                                                                                                             --------------                             900        Board mat     and riprap.
Below Rob Roy, Ark_-- -                                            1953         87        Right ___-                                                                                  1,134        Pile dikes.                 0
                                                                                                                                                                                                                               1--1
Rob Roy, Ark_..                                                    1952
                                                                   1952
                                                                                88
                                                                                89
                                                                                        -__do ------
                                                                                          Left-_____   --------- j-- --------- ----
                                                                                                      ---- --  --   -   --   -- -----            -- -                ---------
                                                                                                                                                                                      6,955
                                                                                                                                                                                        284
                                                                                                                                                                                                   Board mat
                                                                                                                                                                                                   Pile dikes.
                                                                                                                                                                                                                 and riprap.   z
                                                                                                                                                                                                                               O-4
Plum Bayou-Rob Roy, Ark___
                                                                   1952         90       __do-----                                                                                    8,520        Board mat     and riprap.
Above Plum Bayou, Ark_
                                                                   1952         91      -__do-------                                                                                  1,990        Board mat     and riprap.
                                                                   1952         91      -__do-------                 _____, _____/_____
                                                                                                                               __------------__j                                      2,447        Pile dikes.
                                                                                                        i                                                    i




       Total_        __                                                                                       s 27, 035           1,715         39,096                  3,705     4 468, 315

  1 Operative length according to latest surveys.                                                                   5 Does not include 3,790 linear feet of pile dikes.
  2 Constructed.under appropriations for Rivers and Harbors. Report thereon included                                A = asphalt; AC = articulated concrete; CB = concrete blocks; CS = concrete slabs;
in annual report for work under the Little Rock district, Corps of Engineers.                                      FCM = flexible roll type concrete mats; MA = mass asphalt; T = tetrahedrons;
  3 Constructed under sec. 9, F.C.A. approved June 15, 1936.                                                       W = willow mattress; SC = sacked sand cement.
  4 Does not include 50,164 linear feet of pile dikes; 4,002 linear feet of triangular frame
retards; 1,920 linear feet of asphalt groins; and 650 linear feet of spur levee dike, revetted
end.                                                                                                                                                                                                                           0
                                                                                TABLE D-3. Memphis district
                                                 (Bank protection works built during fiscal year and operative protection in place June 30, 1954)
                                                                                                                                                                                                                                             0
                                                                                                                                    Maintenance                                    Lost, de-
                                                         Year         Above                                                                                                       stroyed or                  Opera-
                                                                                                                                                                                  nonopera-                   tive onT
                    Location                           initiated      Head of       Bank         New work                                                                         tive since                 June 30,                   7Y
                                                       (calendar)     Passes                                             E:xtensions                                                                            1954
                                                                                                                                                       Repairs                     June 30,
                                                                                                                                                                                     1953                                                    0
                                                    i------
                                                                                                                                                                                                                                             H
                                                                                                                                                                                                      2
                MISSISSIPPI RIVER                                      Miles                      Linear ft.               L inearft.                 Squares 1                   Linearft.                  Linearft.

Henrico, Ark .      .         -----                           1947    598-601     Right___                 7 760 ___               . .
                                                                                                                                ....         A,    AC, R            9, 132                      430             14, 950   AC.                O
Knowlton, Ark_         _       -       .                      1923    613-616     _do____                                                    A,    R                   107                                      16, 915   AC.                t4
Fair Landing, Ark                   --- -.                    1928    628-630       do _____                                                 A                          62                                      11,080    AC, A.
Burke Landing, Miss       ------                              1949    630-634     Left_____     -----------....-
                                                                                                                                             A,    AC               1,738                                       16,630    AC.
Oldtown Bend, Ark             ___                             1907    639-642     Right___            9......535.....                        A,    R                    21                                      16,260    AC, W.
                                                                                                -----------....-
Horseshoe, Miss- __-.                                         1949    642-645     Left______                                                 A                          32                                      16,845    AC.
Westover, Ark ___ --                                          1947    646-648     Right-__                                                   A,    AC, R               812                                      12,820    AC.
                                                              1915                                                                                                                                                                           0
Delta-Friars Point, Miss_                                             648-654     Left-_-_                                                   A,    C, R                127                                      30,120    AC, W.
Helena, Ark--------
                                                              1922
                                                              1880
                                                                      655-660 Right____                                                      A, R                         45
                                                                                                                                                                                              .....
                                                                                                                                                                                                                25, 475   AC, W.
                                                                                                                                                                                                                                             z
                                                              1913
Trotters Landing, Miss _---
Harbert Point, Miss_
                                                              1912    659-665
                                                                      672-674
                                                                              Left -- __
                                                                                do_
                                                                                                                                             A, C, R                      20
                                                                                                                                                                                                 70
                                                                                                                                                                                                                32,905    AC,
                                                                                                                                                                                                                          AC.
                                                                                                                                                                                                                                 V.          z
                                                              1953                                         6, 530                                                                                                6,460
Walnut Bend, Ark __---                                        1907    676-680 Right --                     7, 225                            A, C, R                   68                       200             24, 175   AC,   W.
Mhoon Bend, Miss_                                             1932    680-686 Left----                                                       A, AC, R               3,776                        40             36,228    AC,   W.           L
Peters, Ark _- Miss------                                     1952    688-691 Right ____                   8, 255                            A                        101                       215             20,790    AC.
Polks Landing, Miss _       -                                 1924      696   Left-- --                                                                                                                         11,094    W.
Porter Lake, Ark -----                                        1911    695-702 Right---                                                       A, R                        22                       80            32,585    AC,   W.
                                                              1914
Norfolk-Star, Miss        -----
                                                              1917    703-709 Left---  --                                                    A, AC, C, R                638                                     29,722    AC,   W.
                                                                                                                                                                                                                                             FP




Cow Island Bend, Ark -_..                                     1925     710-713    Right---                                                   A,     C, R                 91                                     19,534    AC,   W.
Ensley, Tenn----------                                        1952     720-722    Left -- -              3 935 --                            A,     R                    22                     310             13,425    AC.
Bauxippi-Wyanoke, Ark___                                      1919     724-728                                                               C,     R                    62                                     23,300    AC,   S.           C.3
                                                                                  Right_____ - - - - - - - - --..
                                                                                                               .  -

Tennessee Chute, Tenn___                                      1913     728-730    Left_____ - - - - - - - - --..                             C,     R                   105                                      8,850    AC.   W.           C9
                                                                                                               .  -
                                                              1944
Presidents Island, Tenn--....                                 1948     728-730     .do                       .
                                                                                             - - - - - - - - --.. -                          R                           44                                     12,435    AC,   W.
Memphis Harbor, Tenn_-__                                      1878     731-733    -do -- -       . . . . . . . . . . .   - -                 C                           50                                     14,800    AC,   W.
Bullerton Bar, Ark ......                                     1881     786-790    Right_____                                                                                                    475             13,975    AC,   S, W.
Osceola, Ark _         _ --                                   1934       790      Right___                                                                                                                       1,350    G.
Osceola, Ark _-      -                                        1881       791        do_                                                                                                                          5,823    W.
Keyes Point, Tenn__-                                          1931     793-795    Left --____                                                                                                                   10,634    AC,   L, S.
Kate Aubrey, Tenn_....                                        1931     796-797    Right -_               14,465 --                                                                                               2,500    S.
Bend of Island 25, Tenn _............                          1953    806-808    Left --                12, -220
                                                                                                         --
                                                                                                                                                                    -_-_                .. 185                  14 280    AC.
Barfield, Ark ....                                             1916    809-815    Right --                    - -
                                                                                                         12,220                              AC, C, R                8,382                      160             36,030    AC,   S, W.
Huffman-Hickman, Ark-Tenn .             - - -.                 1927    825-830    Ldo-----               -9, 535 --_
                                                                                                       . ..9,                                AC, C, R                2,572        ---.........                  26,304    AC,   S.
Heloise, Tenn      --    -                                     1953    832-834    Left   -                                              --   . .   . .. . . . . .   . . . . . .   . . . . . . . . . -. ..-       9,535    AC.
Island No. 18, Mo __                                           1931    834-838    Right                                                      AC, C, R                1,637 /----.......                         21 260    AC.
Linwood Bend, Tenn__----                                       1931    840-843    Left                                                       AC, C, R               15.368 .________.i                          14,850    AC.
  See footnotes at end of table.
                                                                            TABLE D-3. Memphis district-Continued
                                                      (Bank protection works built during fiscal year and operative protection in place June 30, 1954)

                                                                                                                                  Maintenance                    Lost, de-
                                                                                                                                                                stroyed or                  Opera-
                                                             Year           Above                                                                                                           tive on
                                                           initiated        Head of                Bank    New work                                             nonopera-                                            Type
                     Location                                                                                                                                                              June 30,
                                                           (calendar)       Passes                                       Extensions          Repairs             June 30,                     1954
                                                                                                                                                                   1953


        MISSISSIPPI RIVER (Continued)                                        Miles                         Linear ft.    Linear ft.       Squares 1             Linear ft.             Linearft.

Bells Point, Mo__-------------                                 1931          845-847  Right_                                                                                                       5, 420   AC.
Gayoso-Caruthersville, Mo__                --                  1898          848-853 _do___                                           C, R               147              --.    _                25,600    AC, W.          a




Hathaway Landing, Tenn_                                        1932            856    Left___                                                                                                      1,000    AC.             H




Bend of Island No. 14, Tenn _                                  1946          862-863    do___                                                                                                     12,080    AC.             z0
Merriwethwe Bend, Tenn_       _---                             1932          874-877  Left___                                         R                   59                                      18,995    AC.
                                                               1950
Linda, Mo.__----------------------                             1951          880-882  Right_                                          R                                                           11,950    AC.
Below Toney's Towhead, Tenn__-                                 1946          884-886  Left__.                   4,675                 C, R               131               220                    17,595    AC.
New Madrid Bend, Mo__                                          1930          888-893  Right_                                          AC, C, R         3, 378              _----
                                                                                                                                                                               -                  30 285    AC, S, G.       00
New Madrid, Mo ___--..--------                                 1893          894-895 ___do___                                                                                                      5, 559   AC, W.          00
Slough Landing Neck, Tenn-                                     1913          902-906  Left__.                                         AC, C, R         3,815                                      22,100    AC, S, W.
Island No. 9, Ky -_...................                         1944          912-914 ___do__                                                                        (4)                     (3)    7,010
Chute of Island No. 8, Ky _                                    1935          917-921 ___do__                                          C, R                52                                      12,620    AC, L.
Bend of Island No. 8, Mo__                                     1927          922-924  Right                                                                                                        9,800    S.              00
                                                                                                                                                                                                                            C


Hickman-Reelfoot, Ky_                                          188928        926-933  Left__                                          C, R               107                         _ _          33,569    AC, S, W.
                                                               1929          933-936  Right                                           C, R               264                    55            14,688        AC, S.
Beckwith Bend, Mo_
                                                                                                                                                                                                                                H




Colum bus, K y _--------------------                           1953          946-947  Left__                    3,850                                                                        3,850          AC.
B elm ont, M o _---------------------                          1953          948-949 Right                      5,890                                                                          5,890        AC.
Pritchard, Mo ----------------------.                          1951          956-959 ___do__                                                               87                   25            12, 765       AC.
                                                               1923          962-963  Left__.                                         R                     6                                  6,270        AC.
W ickliffe, K y ------------------------                       1950                                                                                                                                                             H




                                                                                                                                                                                                                            C

                   OHIO RIVER                                             Miles above
                                                                          Cairo Gage                                                  R
Cairo Front, Ill-----------------------                        1928            1       Right.                                                              17                                      5,005    AC, W.
                                                               1918           2-4     ___do_                                          C, R                 68                                      9,527    AC.
Below Cache River, IllI1___-_
                                                           .    .       . ------------      ----     -.-       81, 340                             53,168 i           2,465            (5) 868,507
      Totals   _______------------------
                                                ---                          ..----------


  1 Square = 10 x 10 feet (100 sq ft).                                                                               A -    asphalt
  2 Includes existing revetment reinforced with new work.                                                           AC =    articulated concrete
  3 Lin. ft. triangular frame retards and pile dikes.                                                                C=     concrete
  4 Submerged dike; status unknown.                                                                                  G=     groins
  5 Does not include Island No. 9 Dikes.                                                                             L -    lumber mattress
                                                                                                                     R=     riprap
                                                                                                                      S=    slab concrete
                                                                                                                     W =     willow fascine mattress
                                                                                  TABLE E-1. New Orleans district
                (Present condition of project levees, from Cape Girardeau, Mo., to Head of Passes, La., and levee operations for fiscal year 1954, as provided for in
                                                                    sec. 1 of the act of May 15, 1928, as amended.)


                                                                                                                                                            Operations fiscal year 1954
                                                 In system              Built             Built to           Contents                                                                                        Required            Estimated         Percent
             Location of levee                     when           June 30,               approved             June30,                                                           Lost or       Contents          to                 final            cmplete       0
                                                 completed1
                                                 completed          1954
                                                                  J1954                 ggradeand
                                                                                          section             June30,
                                                                                                                1953                   New work                 Mainte-         aban-or
                                                                                                                                                                                Lost          June 30,
                                                                                                                                                                                              Contents       complete            contents 2        complet
                                                                                                                                                                nance           doned           1954
                                                                                      . ...              .         ......                                                                                                                             ._
                                                                                                                                                                                                                                                                  0
                                                   Miles            Miles                     Miles             1,000       1,000                                1,000       1,000               1,000       1,000                  1,000
                                                                                                             cubic yards cubic yards                          cubic yards cubic yards         cubic yards cubic yards            cubic yards
             MISSISSIPPI RIVER

Lower Tensas....-.....................                 13.0                 13.0                 13.0              3,780                                                                           3,780                              3,780                100    -
Atchafalaya...........................                117.9                117.9                113.0             61,614                                               914 i
                                                                                                                                                                       914--------       15
                                                                                                                                                             -----------------------------------------
                                                                                                                                                                                                    62,013             306           62, 319                99
Lafourche _._.........................                 82.0                 82.0                 66.4             19,400                                                                          19, 400              800           20,200                 96
Barataria                              ....            71.9                 71.9                 52.4              9 594                                                  169     -   _ -          9,763               610           10,373                 94    O
Pontchartrain, including 2.1 miles Baton              125.7                125.7                119.6             45, 757                                                 313         172         45,898               207           46,105                  99
  Rouge Front levee.
Lake Borgne.........................                   48.3                    48.3              26.4                  7,484                          14                  141           64          7, 575              462           8,037                  94   W
Grand Prairie__________......._......_ ..   ..         15.0                    15.0               6.0                    711                                                                           711               49             760                  94   Z
Orleans Parish_______________________...               26.8                    26.8               9.9                  3,982                           5                   27          62           4,052               378           4,430                  91   Q
                                                                          ..                             III!..
                                                                                                            .      .           .       ..... .                                                                                             ... .

      Total Mississippi River.......-...              500.6                500.6                406.7             152,322                             19              1, 664          813        153,192           2,812             156,004                 98   Z
                                                              t------                                    i                         i
    LAKE PONTCHARTRAIN, JEFFERSON
             PARISH, LA.

Lake Pontchartrain protection levees ...               17.4                    17.4               2.8                  5,159                          161                 758                      6,078           2,690              8,768                  69
         BONNET CARRE SPILLWAY
Upper and lower guide levees............               11.7                    11.7              11.7             12,001                                                        --. ------.        12,001                             12,001               100
          SOUTH BANK RED RIVER

Hotwells to Moncla, La__-...       _________           60.0                    60.0              60.0             20,814 I----------                                        5                      20,819        ---------           20,819                100
  ATCHAFALAYA BASIN AND FLOODWAY

East bank Atchafalaya River- -----------               50.8                    50.8              47. 8            21,205------------..........                            385         282          21,308        156                  21,464                99    c
Bayou Des Glaises..--...................                8.1                     8.1               8.1              1.217                                                                            1,217 -..-------.                  1.217               100
West bank Atchafalaya River- .........                 61.3                    61.3              59.0              10,867                        --         -----------
                                                                                                                                                           ---                                     10,867               133           11,000                99
Simmesport Ring-__-_____--  -------------               1.6                     1.6               1.6                    990 ... .. .. ..                                                             990 ....    .......                990               100
Melville Ring_.  _______   ________......               4.1                     4.1               4.1                  2,381------------------------------------                                   2,381                               2,381               100
Mansura Hills to Hamburg..............                 20.3                    20.3              20.3                  4,943 ------------------------ ------------                                 4,943                -........-     4,943               100

See footnotes at end of table.
                                                             TABLE E-1. New Orleans district-Continued
               (Present condition of project levees, from Cape Girardea Mo., to Head of Passes, La., and levee operations for fiscal year 1954, as provided for in
                                                                 sec. 1 of the act of May 15, 1928, as amended.)

                                                                                                                  Operations fiscal year 1954
                                                                          Built to                                                                                                Estimated
                                               In system      Built                   Contents                                                                        Required
            Location of levee                                            approved                                                                                                    final       Percent
                                                  w~hen      June 30,                  June 30,i                                        Lost or         Contents         to
                                                               1954      grade and                                                                                                contents 2    complete
                                               completed I                               1953       New work        Mainte-             aban-           June 3        complete
                                                                           section
                                                                                                                     nance              doned             1954
                                           I



                                                 Miles        Miles        Miles         1,000         1,000          1,000               1,000           1,000        1,000       1,000
  ATCHAFALAYA BASIN AND FLOODWAY                                                      cubic yards   cubic yards    cubic yards         cubic yards      cubic yards cubic yards cubic yards
             (Continued)


West protection levee, Hamburg to Ber-              128.2        128.2       121.5        73,288            56                                             73,344           494       73, 838          99   U)
  wick drainage canal via Calumet, in-
  cluding 1.0 mile Berwick floodwall.
Levees west of Berwick and the lower                 60.9         53.5        38.1        10,944              ------------
                                                                                                                I------------                 -----         10,944          486       11,430           96   4d
  Atchafalaya River, Berwick drainage
  canal to Charenton drainage canal.
East protection levee, Morganza to Mor-              91.9         91.9        73.1        40,439           524           -         -      -                40,963           645       41,608           98
  gan City (S.P.R.R.), including 19.6
  miles Morganza lower guide levee and
  1.3 miles Morgan City floodwall.
Morganza upper guide levee --                        11.9         11.8        11.8         7, 422                                                            7, 422          10        7,432           99
Levees south and east of Morgan City                 16.2         16.0         8.9         6,357           104 -                                             6,461        3,932       10,393           62   0
  (S.P.R.R. to Cut-off Bayou), including
  0.4 mile Tiger Island floodwall.
     Total Atchafalaya Basin and flood-             455.3        447.6       394. 3      180,053           684               385                 282       180,840        5,856      186,696           97
      way.
                                                                                                                                                                                                            r
     Combined total----__   ------.   --          1,045.0      1,037.3       875.5       370,349           864           2,812                 1, 095      372,930       11,358      384,288           97   O
                                                                                                                                                                                                            z
1 Area protected from Mississippi River project flood-adopted project complete-is 23,621 square miles for entire project.
2 Excluding yardage to be abandoned.
                                                                          TABLE E-2. Vicksburg district
                   (Present condition of project levees, from Cape Girardeau, Mo., to Head of Passes, La., and levee operations for fiscal year 1954 as provided for in
                                                             sec. 1 of the act of May 15, 1928, as amended.)


                                                                                                                    Operations fiscal year 1954
                                               In system      Built        Built to    Contents                                                                Required
             Location of levee                    when       June 30,     approved     June 30,                                                                   to                           it     M
                                                                          grade and    June 30,                                   Lost or         Contents        to                           te
                                               completed 1     1954        section       1953         New work        Mainte-     aban-           June 30,     complete                               O
                                                                                                                             ance doned             1954


                                                                                          1,000       1,000             1,000       1,000       1,000       1,000              1,000
                                                                                                                                                                                                      O
            MISSISSIPPI RIVER 1                  Miles        Ailes         Miles      cubic yards cubic yards       cubic yards cubic yards cubic yards cubic yards        cubic yards
Lower Yazoo ...       _................            2 178.1      2 178.1       160.3       189, 500           836              27            0       190,363       5,618        195,981         97
Upper Tensas ...                                     148.2        148.2       112.4       137, 532             0              13            0       137,545       8,968        146,513         94      -
Lower Tensas                -                        131.0        131.0       116.1       111,466          1,277               0            0       112,743       5,723        118,466         95

         YAZOO RIVER AND BASIN
Headwater__-                                       3 581.0       449.0        5 19.0        1,546              0               0            0         1,546      .53,454        55,000          3
Backwater . ----------------------                  7 98.0        7 1.0          1.0         160               0               0            0           160       24,840        25,000          1
          ARKANSAS RIVER, ARK.
                                                                                                                                                                                                     40
North bank ...-.----- ---_ __---                     67.5         45.6          17.4        9,555          1, 218              0            0        10,773       16, 213       26,986         40      Z
South bank ..   _-------- ___--
                          -- -- --                   85.6         85.6          76.0       48, 898              0              0            0        48,898        2,366        51,264          95
RED RIVER BACKWATER LEVEE__                          95.3         92.5          91.8       11,454          5,047               8            0        16, 509         1.02       16, 611         99

      Total -----    ------..                     1, 384.7       731.0        594.0       510,111         8,378               48            0       518,537         284
                                                                                                                                                                 117,          635,821          81

  1 Area protected for Mississippi River project flood-adopted project complete-is                    4 Includes 30 miles built to in terim grade and section.
23,621 square miles for entire project.                                                               s Includes 17 miles Greenwood protection works.
  2 Includes 0.8 mile of concrete levee wall and 0.9 mile earth levee on Vicksburg City               6 Does not include approximately 900,000 cubic yards hydraulic         fill placed in Smith-
front.                                                                                              land Landing river crossing.
  3 Includes 29.0 miles, Greenwood protection works, but does not include 2.5 miles of                7 Includes 1 mile of highway embankment.
highway and railroad embankment to be utilized in project.
                                                                                             TABLE E-3. Memphis district

                                                                                                                                                     Operations fiscal year 1954
                                                             In system    Built               Built to               Contents        I-                                                                    Required         Estimated Percent
                 Location of levee                              when    June 30,             approv ed               June 30,                                                                                 to               final
                                                            completed 1   1954               grade and                 1953          New work          Mainte-
                                                                                                                                                                          Lost or       Contents
                                                                                                                                                                                                           complete         contents 2
                                                                                                                                                                                                                                       complete
                                                                                              sectio n                                                 nance
                                                                                                                                                                          aban-         June 30,
                                                                                                                                                                          doned           1954
                                                                                                                                                                     -!             I      -   -~      I                I--




                                                                                                                       1,000             1,000       1,000       1,000       1,000       1,000       1,000
                 MISSISSIPPI RIVER                            Miles        MIiles                 Miless            cubic yards       cubic yards cubic yards cubic yards cubic yards cubic yards cubic yards

Upper Yazoo _--                                                     94           94                     63             100,445                 915               0              0         101,360              3,887          105,247            96
Tiptonville-Obion River__                                           44           24                     13               7, 559                  0               0              0           7, 559             9, 713          17,272            44
Slough Landing Neck Dike --------------                             10           10                     10               1, 329                  0               0              0           1,329                   0           1,329           100
Reelfoot_--                                                       3 23           23                     23              13,903                   0               0              0          13,903                   0          13,903           100
White River Backwater Levee ---------                              440           40                      8              24,199               487               0                0          24,686              7,314           32,000            77       -
White River -----        ..--------------------                   5 74           74                     38              64,426               758               0                0I         65,184              6,880           72,064            90
Lower St. Francis-                                               6 212          212                    198             129,399             1,573               0                0         130, 972             3,275          134, 247           98   t
Upper St. Francis_                                               7 134          134                    110              47, 640              248             518                0          48,406              3,248           51,654            94
Thebes to Cairo, Ill ___                 ---                      8 10           10                      2               6,463                  0                0              0              6,463              400           6,863            94   .
Ohio River_.    -                                                 9 14           14                     14               4,863                 26                0              0              4,889              214           5,103            96       -
Cacha River.                                                      10 5              5                     5              1,755                  0                0              0              1,755                0           1,755           100

        ST. FRANCIS RIVER AND BASIN
                                                                                                                                                                                                                                                 44
E ast Bank - ...........             _------ ------------          201          144                    80                 19, 846         6,844                  0            850          25,840             32, 668          58,508
W est B ank .............................                          146          136                    73                 17,955                0                0              0          17, 955             7, 623          25, 578           70
East Bank, Little River, Ark_ ..........                            41           41                    41                  5,853                0                0              0           5,853                   0           5, 853          100   C
West Bank, Little River, Ark__--                                      35            35                 35                  4,099                0                0              0           4,099                   0           4,099           100   O
Elk Chute___------------                                              40            40                 17                  4,550                0/               0              0              4,550              720           5,270            86
LITTLE RIVER, MO., DIVERSION CHANNEL__-                           1120              20                     20                9,943             820               0              0          10,763                  0           10,763           100   4
                   WHITE RIVER

Augusta to Clarendon_                    _   -                        47            40
                                                                                         i i...
                                                                                                           40
                                                                                                                .      ...
                                                                                                                             8,886
                                                                                                                                          i.
                                                                                                                                               681               0              0I  I
                                                                                                                                                                                               9,567
                                                                                                                                                                                                       !
                                                                                                                                                                                                       I
                                                                                                                                                                                                               1,833
                                                                                                                                                                                                                        !
                                                                                                                                                                                                                        I
                                                                                                                                                                                                                                11,400
                                                                                                                                                                                                                                          Ii.
                                                                                                                                                                                                                                                 84   z
        Total -- - -              . ..       -.- - - - -         1,190        1, 096     1             790      1      473,113            12, 352             518             850         485,133             77, 775          562, 908          86
   1 Area protected from Mississippi River project flood-adopted project complete-                                               miles of Birds Point-New Madrid setback levee; and 14 miles of New Madrid-Sikeston
23,621 square miles for entire project.                                                                                          Ridge (St. Johns Bayou) levee.
  2 Excluding yardage to be abandoned.                                                                                             8 Includes 6.3 miles of Cairo Drainage District (Mississippi River) levee and 3.4 miles
  3 Includes 1.4 miles of Hickman City levee and 21.2 miles of Mississippi River front                                           of Cairo City (Mississippi River) levee.
line levee, Hickman, Ky., to Bessie, Tenn.                                                                                         9 Includes 5.3 miles of levee from Cache River to lower end of floodwall at Cairo, Ill.,
  4 Extends from Old Town Lake, Ark., to Laconia Circle levee, Ark.                                                              and 8.7 miles of Mounds and Mound City levee.
   5 Includes 67 miles of front line levee from Helena, Ark., to Mouth of White River,                                             io Connects Mississippi River and Ohio River levees.
Ark., and 6.6 miles of Laconia Back Circle levee.
  6 From New Madrid, Mo., to Mouth of St. Francis River, Ark.
                                                                                                                                     It
                                                                                                                                      Includes 13.9 miles of main line diversion channel levee; 2.7 miles of Ramsey Creek
                                                                                                                                 levee; and 2.9 miles of Sals Creek levee.
   7 Includes 84.3 miles of front line levee from Commerce to New Madrid, Mo.; 35.3
                                                                                                           TABLE E-4.
              Yardage placed in levees and levee operations for fiscal year 1954, as provided for in sec. 6 of the Flood Control Act approved May 15, 1928, as amended.

                                                                                                                                               Operations fiscal year 1954
                                                                                          Built to           Contents
                                                   In system           Built
                                                                                         approved            June 30,
                                                                                                                                                                                              Estimated       Percent   Approi xi-     M
              Location of levee                      when             June 30,
                                                                                         grade and           June 30,               Built by         Lost or       Contents       Required
                                                                                                                                                                                     to
                                                                                                                                                                                                 final
                                                                                                                                                                                               contents
                                                                                                                                                                                                               com-     mate area      M
                                                   completed            1954
                                                                                          section              1953                 United           aban-         June 30,                                   pleted    protect(ed     O
                                                                                                                                     States          doned           1954         complete
                                                                                     i                 i                     1
                                               i                  I

                                                                                                                                                                                                                                       O
St. Louis district                                                                                             1,000                1,000       1,000                 1,000         1,000       1,000                    Square
                                                     Miles             Miles               Miles            cubic yards          cubic yards cubic yards           cubic yards   cubic yards cubic yards                  miles
              MISSISSIPPI RIVER

Clemens Station, Mo., to mouth of                            28                28                  0                25.6                   0                   0         25.6                                                     4
  Missouri River.                                                                                                                                                                         ------------
                                                                                                                                                                                 ------------
Mouth of Illinois River to Prairie du                        20                20                  0                27.1                   0                   0         27.1                                                     3
  Pont, Ill.                                                                                                                                                                                                                           o
Prairie du Pont, Ill., to Grand Tower, Ill_.                  0                  0                 0                    0                                                    0                                                     0
Mouth of Missouri River to Cape Gi-                           4                  4                 0                57.2                   0                   0         57.2 ------------
                                                                                                                                                                                  . .. . . ... . ------------                      2
  rardeau, Mo.
Grand Tower, Ill., to Thebes, Ill   -...-.                   46                 46                 3             1, 252.4                  0                   0      1,252.4                                                      8   Z
                                                                                                                                                                                                        _._
               ILLINOIS RIVER
                                                                                                                                                                                 ------------ j------------                            z
Havana, Ill., to Beardstown, Ill.........                 25                    25               8                1,610.0                  0                   0      1,610.0                                                     24
Beardstown, Ill., to mouth of Illinois                   166                   166             127               15,940.0                  0,                  0     15,940.0    ------------ i------------
                                                                                                                                                                                                                               172
River.
                                                                          I          i                     i-~


       Total_--------.--------                           289                   289             138 I             18,912.3                                            18,912.3                                                  213
                                                                                                                   j------'------
                                                                                                                                                __
Rock Island district
                                                                                                                                                                                                                                       r>
              MISSISSIPPI RIVER

Mouth of Iowa River to Burlington, Iowa        1        34.7                  34.7            34.7                23,644                   62                  0      3,706.0       --
                                                                                                                                                                                  ......-         3,706.0         100   __

  1 Includes 6.8 miles of levee along Iowa River, right bank, from mouth to bluffs, in                                        2Does not include 5,474 cubic yards placed in filling crevasses in Keithsburg drainage
Iowa River-Flint Creek levee district No. 16.                                                                               district, Ill. in 1929 but is adjusted to include 111,000 cubic yards placed in 1950 and not
                                                                                                                            previously reported.
                                                MISSISSIPPI RIVER COMMISSION                                                      1617
                                                                    TABLE E-5.
Yardage placed in repairing levees on tributaries of the Mississippi River threatened or destroyed by flood
as provided for in sec. 9 of the act of June 15, 1936.


                                                              District                                                        Built since
                                                                                                                             July 1, 1953


                                                                                                                             Thousands of
                                                         NEW ORLEANS                                                          cubic yards
Red River:
   Lombard levee setback, R-67.1-R--------- -------------------------------------                                        _        24
                                                            VICKSBURG

Yazoo River and tributaries:
   Pelucia drainage ......                                .....---------------------------------------------------------         (*)
    Big Sand drainage..      -------------------------------------------------------                                             (*)
     Abiaca drainage                                                  -------------------                                        (*)
     Ascalmore drainage                         -----------------------------------------------------                            (*)

  * Random repairs.                    Quantities are not available.

                                                                    TABLE E-6.
                         BARATARIA                     LEVEE DISTRICT                               (RIGHT BANK)
                   Levee wave-wash protection structures in place June 30, 1954,New Orleans district


    Mileage upper end of structure                          Linear feet                 Mileage upper end of structure        Linear feet

Slope paving:                                                            Slope paving-Continued
    24.2       ...................                             A 5,646       75.3-         -           - -                        C  4,032
    24.4.... ................                                    C 900       76.1---                                              A  1,532
    25.0 -..................                                   A 3,000       77.2--------------------------.                      A  3,166
    26.3 ...................                                   C 2,135       77.6-------------------------_                       C  2,354
    27.7....................                                   A 5,238       80.1_-------------------------                       SA 5,105
    29.1..................                                     A 5,171
    29.4__.._.....-              -..                           C 1,232          Total--_--------------------                       159.578
    32.8_._                                                    A 6,193
    34.7-__                                                    A 1,928 I
    38.9 _........ ........                                   A 18,010   Wooden revetment:
    39 .8 ...................                                  A 3,743       18.8-----.                                                42,689
     43.4.......--          --        --    .              C & A 2,825       21.0.---                                                     536
     43.6 .......... .........                                   A 741       21.4....                                                   1,800
     44.9....- - --..              ....                        C 6,889       23.1---....                                               10,550
     45.1-..................                                   A 1,271       26.7-----                                                 7,342
     45.8___                                                   C 3,641       28.4---             _                                      3,446
     48.7 ...................                                  A 1,542       29.2.---                                                      216
     49.7 ......-------------                                  C 5,666       29.5--------------------------                                528
     50.4___                                                   C 3,424       31.6-....                                                 11,600
     52.3 --......            ........                        C 11,735       39.2-        -   -        -   -                            1,277
     53.6 ...................                                  A 6,473       42.8----                                                  15,475
     54.4.......-...- - - -                                    C 4,109       48.2---.                                                  13,782
     58 .0 ..... . . .. . . . . .. .. . .                      A 5,728       56.8----                                                  13,622
     59.3 ...................                                  A 1,950       58.9-        -   -        -   -                            1,725
     59.7 ...-       -.... ..           . .
                                     ----                      C 2,950       62.5----                                                   4,463
     59.9 ...................                                  A 1,193       64.5----                                                   4,779
     60.0.-- -.......        .......                             C 798       65.6----                                                   2,719
     60.2_         ----                                        A 1,056       65.9--- ....                                                  612
     60.5-.................                                      A 908       68.7.---                                                   3,550
     61.5 -.................                                   C 4,891       68.9.__-       -                                           1,000
     63.4 ___--                                                C 4,828       69.0----                                                      300
     63.7 ...................                                  A 1,780       69.1---------------------------                               280
     65.1 ...................                                  C 2,672       71.5..........-----------_-__                             13,523
     6 5.8 ..... . . . . .. . . . . . . . .                      C 898       74.6...----------------------                              4,918
     66.1k -............ .....                                   C 839       75.8-...-                                                  2,341
     6 8 .9 .... . . . . . . . . . .. . . . .                    A 350       76.6----                                                   2,562
     69.0 .........----------                                    A 520       78.8-----     ---------------------                           720
     69.2 ....                                                   A 347
     73.0 ............-------                                  A 7,868          Total ---------------.-.---                        166,355
     73.5 ...............----                                  C 2,301
                                                                               _ __
1618                   REPORT OF CHIEF OF ENGINEERS,                                                          U.     S. ARMY, 1954


                                                                 TABLE         E-6.-Continued.
                              LAFOURCHE LEVEE DISTRICT (RIGHT BANK)

    Mileage upper end of structure                                    Linear feet          Mileage upper end of structure                              Linear feet


Slope paving:                                                                           Slope paving-Continued
    96.2                __            -                    -              A 3, 961          115.5_-----------     ---                                       C 9, 500
    96.8__                                                                C 3, 000          137.0                     ----------                            C 3, 000
    96.9_J_                                                       f         C 348
                                                                            A  513          137.4 -           -
                                                                                            138.6-----------------
                                                                                                                  ----------                                C 1, 873
                                                                                                                                                            A 6,100
    97.1--                                                                  A 317           139.7----------------                                           A 1, 400
    97.2--------------------------                                          C 771           148.1      _ _----------                                       A 18, 700
    98.3_                  -                                              A 5, 227          175.6       ------------                                        C 1, 748
    99.8__                                                                A 8, 714
    101.7___                                                              A 3, 893               Total-------                          --------                95, 501
    107.0       _               -                                         A 6, 239
    107.2       __                                                          C 818       Wooden revetment:
    108.4__                                                               A 2, 727         97.0     ----------------------                                         417
    108.8_                                                                C 1, 722        97.4_   _                              -----------                    1, 058
    110.3                                                                A 10, 600
    113.5_--                                                              A 4, 330               Total __-------                       --------                 1, 475


                         GRAND PRAIRIE LEVEE DISTRICT (LEFT BANK)

    Mileage upper end of structure                                    Linear feet          Mileage upper end of structure                              Linear feet


Slope paving:                                                                           Wooden revetment:
    12.5_                                                                 A 1, 400         12.2             -      ----------                                   1, 600
    14.1--------------------------                                       SC 2, 700         12.9 -_----------------                                              2, 200
    14.2--------------------------                                         A 600           14.4                                                                    900
    15.6--------------------------                                        A 5, 700         17.4 -------            ----------                                  10, 800
    17.7_            -                                                   SC 1, 300         18.1       --- -       -      -                                      1, 100
    17.9_                                                                 C 1, 500         18.6--------            ----------                                      800
    18.4-------------------                                               A 1, 600         19.5_ ___------------------                                             940
    18.8_                                                                 C 1, 100        20.2                                                                  I, 700
    18.9_    ---                                                           A 600          22.6                                                                  2, 100
    19.4         _     -                                                  C 3, 280        23.6                      ----------                                  1, 000
    19.7---------------            -                                      C 1, 154        24.1 __         .   ------                                               600
    19.9 .--                   -                                          C 1, 000        24.7 __----------       -----------                                   1, 883
    21.1                                                                  C 1, 665
    21.6           -       -------                                         C 700                 Total _---------                     --------                 25, 623
    22.0_                                                                  C 400
    23.4--------------------------                                         C 600
    23.7--------------------------                                         C 500
    24.1_                ---                                              SC 500

       Total_--                   -                                          26, 299


                    LAKE BORGNE LEVEE DISTRICT                                                                     (LEFT BANK)

   Mileage upper end of structure                                     Linear feet         Mileage upper end of structure                               Linear feet


Slope paving:                                                                          Slope paving-Continued
    44.8...     ...        --                                            A 4,005           73.5 ....................--
                                                                                                           ----                                            A 6,975
    49.6.-                                .                              A 3,184            73.9       -----------                                         C 1,325
    50.4...                                                              A 2,755            74.7--------------                                             A 1,981
    51.8 ...                --                                           C 7,710            75.2_ ........................                                 C 2,882
    51.9.      --------------------                                      C 1,040            76.0 -------------------------                                 A 4,487
    53.0_      _ ...                                                     C 5,894            76.8 -----------------                                         C 4,092
    54.2_._           -------------------                                A 6,336            78 .9 -------------------------                                C 3,007
    54.3-_.         _                                                      C 527            79 .5 -----          ---- ------
                                                                                                       -----------                                         A 2,689
    54.6__..... . .                                                      A 1,669            85.9 ------------                                              C 1,510
    54.9               _-------------                                    C 1,648            86.1..          --------------------                             C 964
    55.1_           _------------------                                  A 1,056            9 0 .5.. . . . . . . . . . . . . . . . . . . . . . . . .       C 5,230
    56.2     .           .--------------------                           C 5,688            90.9 -----             -----------                             C 1 218
    57.7......_ . ...................                                    A 1,078            91.0 -------------                                              A 723
    58.2 ...        _                                                    C 2,450            9 1.3 -------------------------                                 A 812
    58.4-.         _    - -               --                             A 1,056            9 1.5 --------------------------                                 C 217
    58.9.........._    ..................                                C 2,162
    59.2_..........                                                      A 2,025                 To tal ......................                              113,965
    60.1 ..      __   --                  --                             A 2,728
    65.4 ..    ._                                                        A 2,330
    66.5.      --------------------                                      A 1,370       Wooden revetment:
    66.7   _...............-- -                ..- ..     .. .           C 1,471          49.0 -- - - - - - - - - -                                            11,610
    67.7 -_. ..............-                   ..        -.--            C 5,108          4 9 .8 _ -__--
                                                                                                      ------------------                                          885
    70.0 __-                                            -                C 6,328          60 .4 _-----------------------                                       1, 288
    72.2L-.-.-.                                    .                     C 6,235          62.5_ __-----------                                                  7,375
                             MISSISSIPPI RIVER COMMISSION                                                       1619
                    TABLE E-6.-Continued.
     LAKE BORGNE LEVEE DISTRICT (LEFT BANK)-Continued

   Mileage upper end of structure       Linear feet      Mileage upper end of structure                    Linear feet


Wooden revetment:-Continued                            Wooden revetment-Continued
   66.1.... - - - - - - - _                    1,881      84.7...----------------------------                       654
   70.8.....---------------------              3,900     85.2-----------------------------                          560
   71.1....-----------------------------         890      89.5...---------....--------------------                  547
   73.6._...
           --                                    700     91.2_----------------------------                          765
   79.9-----------------------------           2,899     91.5 .........--- ---------------                          933
   83.7     --------------------               5,809
   83.8_                                         467          Total-------------------------                     41,444
   84.4.- -- - --                                281


                 PONTCHARTRAIN LEVEE DISTRICT (LEFT BANK)

   Mileage upper end of structure       Linear feet       Mileage upper end of structure                   Linear feet


Slope Paving:                                          Slope paving-Continued:
    104.0               _                    0-----
                                             C 880         22.0---------     ----------------                   A1, 450
    104.9 -------------------------
                       _                   C 6, 127                _
                                                           222.8------------       ------                         A 780
    109.5-_                                A 2, 413        227.3-------       ----------                        A 2, 988
    120.6 -------------------------        A 4, 890
                        _
    166.9 -------------------------        A 1, 874           Total __--------              --------             21, 402


                       ORLEANS LEVEE DISTRICT (LEFT BANK)

Slope paving:                                          Wooden revetment:
    92.2-_                                 C 2, 667       91.6 ----------     ----------                          1, 000
    92.6__                      -            R 587        92.6-------------------------                           1, 800
    92.7                                   R 3, 156       93.9 --------------      ---                 -             600

     Total_                                   6, 410          Total_---------
                                                                     ___                    --------              3, 400


                   ORLEANS LEVEE DISTRICT (RIGHT BANK)

Slope paving:                                          Wooden revetment:
    84.5- __-                              C 4, 085       84.1                                                      596
    93.9 --------------------------        C 1, 540       91.6 -------------------------                         15,700
    94.0 --------------------------         C600          93.8--- -------            -----                        1,100
                                                         94.1 ------------------------                              498
     Total ---     -    -      -6,225                    95.5 -------------------------                           2,200

                                                             Total ----------------------                        20,094


A=asphalt; C =- concrete; R = riprap.
1 Bulkhead and wooden revetment.
                                                                             TABLE F-1. New Orleans district
                           (New channel improvement work accomplished during fiscal year and operative portion of project feature in place June 30,1954)                                                          It

                                                                                In project when complete                Completed June 30, 1954            Operations during fiscal year
                                                                   Year                                                                                                                         Percent
               Location of improvement                           initiated                                                                                                                     complete
                                                                               Excavation        Clean out          Excavation          Clean out           Excavation        Clean out

                                                                                                                                                                                                                  0
                                                                               Cubic yards         Miles            Cubic yards           Miles             Cubic   yards       Miles


Bayou des Glaises diversion channel_-       - -                    1938           2,222, 845 ___-----                      2, 222, 845 ---- _------                                                        100.
                                                                                                                                                                                                                  0
                                                                                                                                                                                                                  M
Bayous Rapides, Boeuf, and Cocodrie ................               1946          19,482,158             23.3              16,482,158            13.3                                                        79
Charenton drainage and navigation canal .___._...                  1939          10,800,105---------------                10,800,105 ---------------                                                       100
Wax Lake outlet....___________                                     1938          57,546,196 ....--- -------               57,546,196      -                                                                100
1 Atchafalaya Basin floodway.-        -     -        - -   -----------                                         ................-..                                                             - -- -----
1 Morganza floodway....                                                                                                                  ___-..........   --------------------------------
                                                                                                                                                          -------------------------------_   ...........
Devils Swamp barge channel-.-_ -------                       -     -     -       17,000,000                                                                                 ----------------


1 Information not available at this time.

                                                                                                                                                                                                                  z
                                                                                                                                                                                                                  T1
                                                                                              TABLE F-2. Vicksburg district
                                  (New channel improvement work accomplished during fiscal year and operative portion of project feature in place June 30, 1954)

                                                                                                   In project when complete             Completed June 30, 1954         Operations during fiscal year
                                                                                Year                                                                                                                        Percent
                   Location of improvement                                    initiated                                                                                                                    complete
                                                                                                   Excavation         Clean out        Excavation        Clean out      Excavation        Clean out


                                                                                                   Cubic yards         Miles           Cubic yards        Miles         Cubic yards         Miles
               YAZOOBASIN HEADWATER, MISS.

Coldwater River.._ ---------------------------                        1941                            9,896,662             46.70         9,896,662            46.70                0               0             100
Arkabutla Canal._________-------------------                          1948                                80,600             0               80,600             0                   0               0             100
Tallahatchie River__ ------            _---------_---------           1940                            7, 361,401           110.00         3,476,401           110.00                0               0              55
Little TallahatchieRiver & Panola-Quitman floodway                    1939                            1,170, 428            33. 19        1,170, 428           33. 19               0               0             100   a
Yocona River--------     _-_----------.
                                      ...------                     _ 1952                               606,181             0              606,181             0                   0               0             100
Bobo Bayou-......______________----  ----------                       1944                               423,000             4.00           423,000             4.00                0               0             100   m
Cassidy Bayou .              ...---------------------------------     1943                           10,537, 793            47.60         3,032, 793           47.60                0               0              33
Yalobusha River. -------------------------------                      1939                            6, 336, 584           42.05         6,336,584            42.05        1,192,838               0             100   44
Pelucia Creek...-------------------------------                       1953                            1,299,000              2.90                  0            2.90                0               0               1
Yazoo River..           ...------- .......-------------------------   1941                            5,105,773              0            4,201,773             0                   0               0              82   H
Lower auxiliary channel- -----              -----------------------------                            14,500, 000             0                     0            0                   0               0               0
Tchula Lake-.._.-        ..............------------------------                                          244,700            31.50                  0            0                   0               0               0   .

             BIG SUNFLOWER RIVER, ETC., MISS.
Big Sunflower River_____                            ----           __--------------
                                                                            1947                      5,100,000            199.70                 0            19.22                0               0               2
Quiver River____________ __--      ---------------                          1947                      1,507, 000            55.50                 0            16.15                0               0               8   0
Deer Creek __________________________-------.                               1947                         73,120              2.04            73,120             2.04                0               0             100   O
Steele Bayou ______________________________--                               1947                      3,451,464             45.40         3,451,464            31.94        1,758,584               1.49           97
Big Sunflower River tributaries ._____----------------_                       ......                  2,348,000            215.500                              0                   0               0               0   R
Quiver River tributaries_....-               _----------..--------                   ----.......               0            18.4                     0          0                   0               0               0
Steele Bayou tributaries--.......-------------------------                                                                  43.6                     0          0                   0               0               0

         BOEUF AND TENSAS BASINS, ARK. AND LA.                                                                                                                                                                          O
Bayou Lafourche, La _ __------ ----------.........                       1949                        35,815,784              1.10        35,815,784             1. 10       1,154,181               0             100
Big & Colewa Creeks, La._....-.------------------                   - 1947                            4,375,025             34.01         4,375,025            34.01                  0             0             100
Tensas River, La--- -----             - ----      -     -      --        1947                         1,091,965             86.16         1,091,965            86.16                  0             0             100
Boeuf River, Ark. & La-......____               --.................     1953                         17, 790, 000           28.00         7, 712,709            0           7, 712, 709             0              36
Big Bayou, Ark --------------------------------------                   1952                          1, 930, 490           15.60            890, 490           0                     0             0              30
Bayou M acon, Ark. & La._.......----.----------.---.----                                                          0        170.00                   0           0                     0             0               0
Canal 19, Ark...........
                   ----------------------------------------------------                              14,500,000              0                      0           0                     0             0               0
C an al 4 3 , A rk .. . . . ..      -                                . . . . . . . . . .6                 00 , 00 0         24 . 5 0                0           0                     0             0               0
Canal 81, Ark-...................-                                                                    1, 735, 000           15.90                   0           0                     0             0               0
                                                        TABLE F-2. Vicksburg district-Continued
                      (New channel improvement work accomplished during fiscal year and operative portion of project feature in place June 30, 1954)


                                                                     In project when complete             Completed June 30, 1954                       Operations during fiscal year
            Location of improvement                   Year                                           i
                                                                                                                                                                                                    Percent
                                                    initiated                                        I
                                                                                                                                            I
                                                                                                                                                                                                   complete
                                                                    Excavation         Clean out         Excavation            Clean out                Excavation                Clean out
                                                                1                  i                 I                     I                    I   -     -   -   -   -       I                I


																Cubic yards         Miles            Cubic yards            Miles                   Cubic yards                Miles
            BAYOU METO BASIN, ARK.                                                                                                                                                                            O
Bayou Meto __---                                                       9,940,000             19.90                     0                0                                 0                0                  0©
Little Bayou Meto and Salt Bayou      ---                              5,650,000             10.92                     0                0                                 0                0
Wabbaseka Bayou---- ---                                                  353,000             20.10                     0                0                                 0                0                  ©
Bradley Slough_                                                          470,000              0                        0                0                                 0                0



                                                                                                                                                                                                              ©

                                                                                                                                                                                                              tt0r
                                                                                                                                                                                                              z
                                                                                                                                                                                                              e




                                                                                                                                                                                                              oo
                                                                         TABLE F-3. Memphis district
                          (New channel improvement work accomplished during fiscal year and operative portion of project feature in place June 30, 1954)

                                                                          In project when complete            Completed June 30, 1954         Operations during fiscal year
               Location of improvement                         Year                                      I                                I
                                                                                                                                                                               Percent
                                                             initiated                                                                                                        complete
                                                                         Excavation       Clean out          Excavation      Clean out        Excavation        Clean out

                                                                         Cubic yards       Miles             Cubic yards      Miles           Cubic yards        Miles

West Memphis drainage project, Ark.......----------------.     1951         1,726, 912             2.5          1,596,912             0             341,177              0            80
Mississippi County DD #17, Ark                          _      1947         1,068, 302             0            1,068,302             0                   0              0           100
Cross County project ditch, Ark_____________________ _         1942         7, 710,454             0            7, 710,454            0                   0              0           100
Tyronza River, Ark __________________________________          1939         2,795,160              0            2,795,160             0                   0              0           100
Birds Point-New Madrid intercepting ditch enlarge-             1952            284,989             0               284,989            0                   0              0           100
  ment, Samos, Mo.                                                                                                                                                                           It
Miss. River, West Tenn. tribs. (backwater area)....            1952         4,890,000           25.0              161,653             0                     0            0               1
Cache River, Ark..____________________________          _       (1)        97, 000,000           0                      0             0                     0            0               0
L'Anguille River, Ark_____________________________              (1)        16, 000,000          23.5                    0             0                     0            0               0   00
Miss. River below Cape Girardeau (West Tenn.                    (1)        15,900,000          160.0                    0             0                     0            0               0   O

  tributaries).
St. Francis River, Mo. and Ark ________________-_              1953        75, 557, 000         16.0            2,865,265             0           2,865, 265             0               4

  1 Authorized but no work started.




                                                                                                                                                                                             O
                                                                                                                                                                                             z
1624                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

                                    TABLE G. Costs during iscal year 1954

                                                                                                                                                      Costs
                                  UNITED STATES FUNDS
                                                                                                                   New work                                   Maintenance


Flood Control, Mississippi River and tributaries except for emer-
  gencies:
Mississippi River levees:
    Memphis district-------------------                                                                         1,615,953.74                     363,492.56
    Vicksburg district -------                                                                                     913,403.38                    121,183.44
    New Orleans district ...____________________.                         .      .          .                      119,024.24               2, 211,879.39
Levees under section 6 of Flood Control Act approved May 15, 1928:
    Rock Island district____________.._________....                         .      .           .       .            32, 806.43
    Vicksburg district.....-------                                                                                  30,734.33
White River backwater levees, Ark. (Memphis district) ...........                                                  114,575.22
South bank Red River levees, La. (New Orleans district) ........                                                     14,234.89                    66,279.10
Red River backwater levees, La. (Vicksburg district) -...... .........                                          1,094,770.76                      45,699.19
St. Francis Basin project (Memphis district)-.......................                                            1, 574, 550.97                   192,917.19
Augusta to Clarendon, Ark. (Memphis district)--                                                                    172, 517.79
Memphis Harbor (Memphis district)                     ____                                                     2,121, 800.42
Des Are, Ark. (Memphis district) ..                         --------------------------                             158,429.38 - - -- - - - - - -
Arkansas River levees, Ark. (Vicksburg district)....----------                                                     400,904.99                     41, 250.13
Big Sunflower River, etc., Miss. (Vicksburg district).                                    _ __                     260,037.73
Boeuf and Tensas Basin (Vicksburg district)-........................                                           1,523,676.18
Yazoo Basin headwater, Miss. (Vicksburg district)                                        __                    4,438,016.43                     708,118.31
Rights-of-way and flowage, Bayou des Glaises setback (New Orleans                                                     1,516.11
  district).
Lake Pontchartrain, La. (New Orleans district):
    Appropriation 21X3112_................._______ _...             ._         .........                           358, 301.85                  404,532.95
    Appropriation 21X3122-.............----------                                                                       783.78
Atchafalaya Basin floodway, La. (New Orleans district) ....                                   .........        5,620,843.98                    383,971.96
Morganza floodway, La. (New Orleans district)....---------------                                               1,162,960.79                      38,340.54
Bonnet Carre Spillway, La. (New Orleans district) -------------                                                                                 111,861.20
Bayous Rapides, Boeuf and Cocodrie, La. (New Orleans district) ..                                                    2,194.99
Revetments:
    Memphis district                    ......---....--                                                       10, 396, 425.82             2,125,022.91
    Vicksburg district ...............                               ....        ......------------ ---        3,681,676.08                1,631,802.26
    New Orleans district                           ..--------.......------------------------------------ 2,148, 010.72                          497, 213.95
Dredging:
    Memphis district .-----------------------------                                                                                       3,039, 755.62
    Vicksburg district -----------------.                                      . .               .       . ---------------                1,056,587.98
    New Orleans district ....--------------------------                                                                                          67,780.45
Mapping:
    Memphis district -----..---.                                                          .                         73,597.70  .................
    Vicksburg district          ------------------------.......---------                                            48,634.90 ------------------
                                                                                                                                 - -- - - - - - -
    New Orleans district ......----....-------                ----------------                                      57, 309.09
Surveys, Gages and Observations:
    Memphis district ---------                                                                                                                 154,669.82
    Vicksburg district..----------------------                       ----------------                -   -   - -    -     -       - -   -    -
                                                                                                                                               172,809.77
                                                                                                                                                      -



    New Orleans district                                                      -----------
                                                         ...------------------------                 ----                ----
                                                                                                                            --          --
                                                                                                                                               343,513.23
                                                                                                                                                 --




                       -----------------
        Subtotal -------                                                          ---------------                  38,137,692.69                               13,778,681.95
                                                                                                    ----           ---        -     -   -    -        -

Flood Control Emergencies:
    Memphis district ....    .----------------------------------                                     ..................                                            16,518.42
    Vicksburg district.-----------      -    ---------------------                                   ..................                                            47, 439.01
    New Orleans district                        -     ---------------
                                   ...-----------------                                              ..................                                            50,428.03
        Subtotal_
                --------                   -.                                                                                                                     114,385.46

        Total United States Funds                       -----------------------     -----                          38,137, 692.69                              13,893,067.41
                                   CONTRIBUTED FUNDS

Iowa River-Flint Creek levees (Rock Island district) -- __                                                                    16,403.25
South bank Red River levees, La. (New Orleans district) - ---...                                                               4,200.00
Lake Pontchartrain, La. (New Orleans district).....-----------                                                                50, 066.00
        Total contributed funds...____...................
                                   _____                                              ...   _                                 70, 669.25
        Grand total, United States and Contributed Funds.........                                                  38,208, 361.94                              13,893, 067.41
                                MISSISSIPPI RIVER COMMISSION                                                    1625
                             TABLE H-1. Costs to June 30, 1954

                                                                                                 Costs
                            Existing project 1
                                                                                  New work               Maintenance


                         UNITED STATES FUNDS

Flood control, Mississippi River and tributaries except for emer-             $769,433,783.47         2 $214,790,479.24
  gencies.
Flood control emergencies_.    ____.._.__   . ___..                                                       14, 407, 626.79
Additional appropriations not under Flood Control Act authoriza-                  26,763,728.32            5,305,180.18
  tions.
      Total United States funds .......   .......    ..    ......   ...         796,197, 511. 79         234,503,286.21

                          CONTRIBUTED FUNDS

Flood control except for emergencies _________________                               2, 527, 972.90          353,947.85
Flood control emergencies-........___________ ___  . ..                   ................                     2,866.78

      Total Contributed Funds_._------.---.-.---.---                                2,527,972.90             356, 814.63

      Grand total United States and contributed funds ..........               798,725,484.69            234,860, 100.84

  1 For data covering costs under previous project, see p. 1808, Annual Report for 1944, and p. 1682, Annual
Report for 1937.
  2 Includes maintenance expenditures since August 18, 1941, not chargeable against Flood Control Act
authorizations, amounting to $169,669,108.74.
                                                                                             TABLE H-2.
Statement of the costs to June 30, 1954, incurred for the construction and repair of levees by the United States Government on existing projects under supervision of the President,
Mississippi River Commission (including all costs under sections 6 and 7 of Flood Control approved May 15, 1928, and under section 9 of Flood Control Act approved June 15, 1936;
and expenditures from the beginning of earliest records through December 31, 1953, for similar purposes by States, local levee districts, and communities interested, covering yardage
placed; rights-of-way, engineering expenses, repair work, crevasse closing, high-water expenses, interest, etc.)
                                                                                                 I Costs incurred by United States under existing projects through
                                                                                                   Costs incurred by United States under existing projects through Expended by                                                                                      4
                                                                                                                           June 30, 1954                           State and local                                                                                  4
                                                                                                                                                                                                                                     organizations                  0
                                                                                                                                                                                                                                      from begin-                   4
                                                                                                                     From Government funds                                    From contributed funds                                ning of earliest                4
                                                                                                                                                                                                                                     available rec-
                                                                                                                                                                                                                                     ords through                   O
                                                                                                                   New work                 Maintenance                    New work                     Maintenance                  Dec. 31, 1953
                                                                                                               I                       I     $1034870           i-


Northern (section 6)-        -         -                                                                               $19,287.55                                                 $9,643.78 -                -            -                       (2)
Omaha (sections 7 and 9) ------------------ --------- --------                -- --                                                           $101, 487. 50                                                                                       (3)
Kansas City (section 7)...--              ---------------------------------                                                                     25,000.00                                                                                         (3)
Rock Island:
    Section 6 --            ..------------------------------                  --                                       753,780.41 ---------------                               373,937.16 ---                -                          4 $5, 523, 287, 60         O


    Section 7 ........-----------------------                                                                                         166,785.64                                     --- . -                  -$2,079.22
St. Louis:                                                                                                                                                                                                                                                          z
    Section 6..-------------- ----------------                                              ----------------        1,950,614.41                                     979,506.84                                                          4 23, 212, 929.12
    Section 7----. . . . . . . . . . . . . . . . . . . . . . . . . .                        -----------------                                   29,787. 22                                            ---------------


C incinnati (section 9) --------------- -----------           ----------                    ----------------                                     9,688.77                                                                                         (3)
Louisville (section 9) --                                                                   ----------------                                    17, 860.80                                                                                        (3)
Tulsa (sections 7 and 9) - ---.-....... ...... ...... ....... .                             ----------------                                   395,806.34                                                            167.     04                  (3)
Little Rock (sections 7 and 9) ---.............. ................                      .    ----------------                                 2,129,108.73 ...............                                   - - -- - - -
                                                                                                                                                                                                            --                                    (3)               zz
Memphis:
    S ection 6 -------  -- ----- ----- ----- -- ----- ----- --                                                         108,651.24                6,800.00                          54,397.64               ----- -       -- --           4 93, 885, 803.97
    Sections 7 and 9--- .. ... ... ... ....           ... ... ... .... ... ..                                                                3,451,491, 02
    All other:
         Levees, White River, Woodruff and Monroe Counties, Ark___                                                      25,000.00
         Mississippi River levees - - .. . .. . .. .. . .. . .. . ... ...                                          75,552,856.41       11,016,573.97                              22,024.82
         White River backwater levee, Ark --.......................                                                 6,856,758.52             385,391.53              ................
         Augusta to Clarendon, Ark. (part for levees)                      ......                                   1,986,458.05 ................                   .................
         Des Arc, Ark. (part for levees) .--....................            --... ..                                   177, 001.12 ................
         DeValls Bluff, White River, Ark. (part for levees)- .....                    - -                                   241.84                                   ................
         New Madrid floodway (part for levees)              ------------------    ...                               3, 144,130.59                   972,48
         St. Francis Basin project (part for levees).---------                                                      9,096,465.61              288,478.94            !. . . . . . . . . . . . . . .                                 - -    -   -   - -   -   -   -


         Roads on levees .............----------                                                                        12,426.11 . . . . . . . . . . . . . .
         Levees, White River, Clarendon, Ark ....................                                                      227,363.59
                                                                                                                                       i                        I
          Subtotal (MemlIhis district) -----------------------------                                               97,187,353.08
                                                                                                                               15,149,707.94                                      76,422.46            _
Vicksburg:                                                                                                                 ---------   I-   --------            I                                    I--------I-------
   Jonesville, La--..-.............--------.......
    Section 6 ------- -- ----- ----- ----- -- ----- ----- --
                                                                                                                       509, 399.54                                              100,000.00                                               462, 220, 424.66
                                                                                                                       498, 903.91             124,373.63                       182,738.44                        27, 603.21
    Sections 7 and 9----...........................                                                                                          6,359,209.19                      ............                           620,52
  See footnotes]at end of table.
                                                                                               TABLE H-2-Continued

                                                                                                                             Costs incurred by United States under existing projects through                                                Expended by
                                                                                                                                                     June 30, 1954                                                                         State and local
                                                                                                                                                                                                                                            organizations
                                                                                                                                                                                                                                             from begin-
                                                                                                                                From Government funds                             From contributed funds                                   ning of earliest
                                                                                                                                                                                                              .
                                                                                                                                                                                                                                            available rec-
                                                                                                                                                                                                                                            ords through
                                                                                                                               New work                Maintenance               New work                           Maintenance             Dec. 31, 1953
                                                                                                                         i                         iI----------           iII                             i                              i----               -




Vicksburg=(Continued)
   All other:
       Mississippi River levees .......--  - ... .......      .  . .                      --   -   -   -                     62, 234, 712.12 10,694,496.27               14, 761.98                                                                                          00
       Arkansas River levees, Ark -.......         _...........  ....-                    -------------------------          17,108,745.38 ----------------
                                                                                                                                              2,645,098.52 ---------------- ----- - - - - -
       R oads on levees __ . . . . . . . . . ....... --.. .. .                            -------------------------              179,783.49                 ................
       Yazoo Basin headwater, Miss. (part for levees) .....-....                          -------------------------           2, 749,272.28      265,098.78                         ----------------
       Vicksburg Yazoo area, Miss. (part for levees) .-........                           -------------------------               17,804.99                 ................        ----- - - - - -
       Yazoo Basin backwater, Miss. (part for levees) --------                            -------------------------               63,715.33
       Red River backwater levees, La                          - --                       -------------------------           7, 205,956.66       55,636.75
                                                                                                                                                                          I                               i---------


           Subtotal (Vicksburg district) .-------------------------                                                           90, 568,293.70                  913.14
                                                                                                                                                        20,143,                   297, 500. 42                               28,223.73
New Orleans:
   Section 6 .                                                 -
                                       --------------------------------    -                                                                                160, 951.69                33,719.08                             23,354.14     4 119, 000, 320. 48
                                                                                                                                     100, 596.44                                                                                                                             r
   Sections 7 and 9 -........ ........ ........ ......---                    -                                                .---       -- --            1,719,200.88                       -        -
   All other:
       B oeuf Basin levees ...........        ..........---... .. ... .                            ----------------------  2,649,295.24         163,313.97         -                    -----                         -- -----                                               C)
       M ississippi R iver levees .-.............................                                  ---------------------- 41,221,063.75      19,759,429.49                             40,000.00                         271,600.00                    119320 4
                                                                                                                                                                                                                                                     r000                    00
       South bank Red River levees -..........-                                 .                  I --------------------- 8,127, 947.98      2,270,133.93                              4,200.00                  ----------------
       R oads on levees_ -_. ... ... ... ... ....                   ... ... ... .                  ----------------------    540,838.07 ..                                                                                                                                   00
       Rights-of-way and flowage, Bayou des Glaises setback _-                                     ----------------------    387, 565, 11 --          ------------                                   ----------------                                                        0
       Atchafalaya Basin floodway, La. (part for levees):
           Atchafalaya River levees ___...... ......... ........
           Atchafalaya Basin protection levees_ ------------
                                                                                                                               3,360,484.83
                                                                                                                              46,377, 867.62
                                                                                                                                              1,478,932.62 -
                                                                                                                                              1,798, 374.89   -                                  -        -
                                                                                                                                                                                                                                           . . . . . . . . . . . . . . . .
                                                                                                                                                                                                                                           . . . . . . . . . . . . . . .-
                                                                                                                                                                                                                                                                             z
           West Atchafalaya floodway levees ...............                                                                    4,251,017.13 -
       Morganza floodway, La. (part for levees) .---------------                                                               2,258,981.26      61,331.75  -
       Bonnet Carre Spillway, La. (part for levees) ............                                                               3,329,173.38
       Lake Pontchartrain, La _-- -                       ..............
                                                  _.__.____                                                                    1,798,301.85 1,053,   892.95                        676,666.00                             ----

           Subtotal (New Orleans district)                   -
                                                          __-_____-.
                                                          -_                                                                 114,403,132.66             28,465, 562.17             754,585.08                               294,954.14
                                                                                                                                                   I                      I --     -     -            -           1- --          -       I--
                                                                                                                                                                                                                                          I--
                                                                                                                                                                                                                                           -     -


               T ota l . . . . . .. . . . . . . .. . . . . . . .. . . . . . . . ..   ..                                      304,882,461.81             66,634,708.25            2,491,595.74                               325,424.13 303,842,765.83
                                                                                                                                I                  I                                                          I

  'For net expenditu res on previous projects by the United States Government for same                                 2 Included in amounts reported by the Rock Island and St. Louis districts.
purpose (U. S. funds, $81,857,583.68; and contributed funds, $16,177,994.67), see p. 1738,                             3 Reports not obtained.
Annual Report for 1937.                                                                                                4 Not segregated under class of funds or project titles.
1628               REPORT OF CHIEF OF ENGINEERS,                                               U.     S.   ARMY, 1954


                                                  Cost and financial summary
                                                                                                 1
                                                    UNITED STATES FUNDS


                                                       Fiscal year ending June 30                                            Total to June
                                                                                                                            30, 1954, includ-
                                                                                                                            ing fiscal years
                                    1950               1951                1952                1953            19542          prior to 1950

New work:
   Allotted........ $51,914,846.11 $48,227,925.17 $45,330,106.48 $43,384,676.75 $12,130,094.87 $799,069. 599.88
   Cost----------............ 54,757,729.16 48,566,783.68 42,789,118.13 58,207,484.00 50,581,608.51 796,197, 511. 79
Maintenance:
   Allotted-......... 15,730,153.89 13,171,544.83 15,169,893.52 16,635,323.25 13,858,444.78 220, 427, 360.57
          ...........
   Cost----------             16,302,102.76 13,123,166.19 15,216,552.13 16,654,459.81 13,778,681.95 220,095, 659.42
Flood control emer-
gencies (mainte-
  nance):
   Allotted......-...             464,000.00          145,000.00          800,000.00         297,382.00:                       14,879, 304.02
   Cost...........------------    430,127.53          159,970.31          238,756.57         489,054.96        114,385.46      14,407, 626.79


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954    ..--------     719,736.60
    Appropriated for succeeding fiscal year ending June 30, 1955__       46,450,000.00
    Unobligated balances available for succeeding fiscal year end-
      ing June 30, 1955---___-----_                                      47,169,736.60
                                                                    .---------------
    Estimated additional amount needed to be appropriated for
      completion of existing project-___________ -- __---             3 406,606,484.74

  1 Appropriations were as follows:
    Appropriations chargeable against Flood Control Act Authorizations:
        Flood Control, Mississippi River and Tributaries except for
          Flood Control Emergencies (excludes maintenance expendi-
          tures August 18, 1941 through June 30, 1954, $169,669,108.74):
              Net total allotted for works under Mississippi River
                Commission---------.....  ----------------                  $817, 758, 943.21
              Allotted for surveys under section 10 of Flood Control Act
                approved May 15, 1928 (not under Mississippi River
                Commission)_-------------................----                  4,995,214.54
              Transferred to Revolving Fund-------------------------          24, 944, 460.35
              Impounded Savings...........--------------------------------1,593,097.16
              Unallotted balance June 30, 1954......-----------------------       500, 000.00
                                                                                                                            $849, 791, 715. 26
          Flood Control Emergencies:
              Net total allotted-----.............------------------------------                           14,879,304.02
             Impounded savings-------...........................-----------------------------..........        14, 377.98
              Unallotted balance June 30, 1954.............----------------                                     6,618.00
                                                                                                                              14, 900,300.00

             Total appropriations chargeable against Flood Control authorizations
               through June 30, 1954.....-------- ---------------------------------                           864, 692, 015.26
  Additional funds not chargeable against Flood Control Act authorizations:
     Maintenance expenditures August 18, 1941 through June 30, 1954,                from   appropria-
       tions for Flood Control, Mississippi River and Tributaries except for Flood
     Control Emergencies                                    .------------------------------------------------ 169,669,108.74
     Appropriations in addition to appropriations for Flood Control, Mississippi River
       and Tributaries...           ---------------------------------------------------                        32,068,908.50

                Total additional funds not chargeable against Flood Control Act authoriza-
                 tions through June 30, 1954-----------------------------......................................- -------     201,738, 017.24

                Grand total appropriations for Mississippi River Commission works through
                 June 30, 1954 ...---------------------------------------------------------- 1,066,430,032.50

    Reconciliation of appropriations and allotments:
       Allotted for new work to June 30, 1954 ---------- --------------------------                                          799, 069, 599.88
       Allotted for maintenance to June 30, 1954:
           Flood Control Emergencies                                                               $ 14,879,304.02
                                                                    .....-------------------------------
           All other ......----------------------------------------                                  220, 427, 360.57
                                                                                                                             235,306,664.59
         Surveys under section 10 of Flood Control Act approved May 15, 1928---------...                                       4,995, 214.54
         Transferred to Revolving Fund-------------------------------------------------                                       24,944,460.35
         Impounded savings...-------------------------------------------------                                                 1, 607, 475.14
         Unallotted balance as of June 30, 1954...----------------------------------------                                        506, 618.00

                  Total appropriated to June 30, 1954- ..----..---........-------------------- 1,066,430,032.50
                                      MISSISSIPPI RIVER COMMISSION                                                                   1629
    Appropriations 21X3112 for five fiscal years covering new work and maintenance were as follows:
       Fiscal year 1950 _ - - . - . .....        ....            .....
                                                                  _ _.._..-------
                                                                               -----------                    -       $67,000,000
       Fiscal year 1951-       _                         ----          _-----                          _61,                400,400
       Fiscal year 1952                    ..                                    .. _     ..------------------------- 60,500,000
                                                                    -------------------------
       Fiscal year 1953 ..-----            ...
                                         _----        .                   ...-----------.
                                                                 - -----------------------------..                     60,020,000
                                                                                                .....
       Fiscal year 1954.................---------------------------------........--------------------                  51,433, 000
   2 Amounts stated in this column represent the differences between totals through June 30, 1953, and June
30, 1954. The total allotted in Fiscal Year 1954 ($50,933,000.00) is reduced $24,944,460.35 due to transfer
of such amount from the plant allotment to the revolving fund. The total cost for Fiscal Year 1954
 ($52,030,760.10) is increased $12,443,915.82 due to converting permanent work cost as stated in item 1, Form
38, to the total-to-date cost stated in item 12, Form 38. The changes made result from introduction of a
new accounting system effective July 1, 1953.
   3 Amount unappropriated is computed as follows:
   Appropriations authorized except for Flood Control Emergencies (see footnote (3),
     pages 2069 and 2070 of Annual Report for Fiscal Year 1953 for breakdown)--------.... $1, 292, 748, 500.00
   Appropriations authorized for Flood Control Emergencies (see page 2071 of Annual
     Report for Fiscal Year 1953) __.______-...__.--------------__.                                                    25,000,000.00
              T o t a l au th or izat ion s . . . . . . . . . _ ._.. . . ..          _
                                                                            ..---- - -.                .
                                                                                        . ..-- - - - - --.. ..--- $1, 3 17, 74 8 , 5 00 . 00

   Appropriations for Flood Control, Mississippi River and Tributaries (includes appro-
    priations for Fiscal Year 1955) chargeable against Flood Control Act authorizations:
        Appropriations except for Flood Control Emergencies (excludes maintenance
           expenditures August 18, 1941 through June 30, 1954, amounting to $169,669,108.74,
                                                                                 ---
           which are not chargeable against Flood Control Act authorizations) ...-           $896,241,715.26
        Appropriations for Flood Control Emergencies (includes appropriations made
           prior to July 1, 1953, and allotments thereafter)....--------- -----------------     14,900, 300.00

                   Total appropriations chargeable against Flood Control Act authorizations -                                $911,142,015.26

   Amount unappropriated:
     For all works except Flood Control Emergencies ..........................                                          -    $396,506,784.74
     For Flood Control Emergencies............-----------------                                                     -          10,099,700.00

                      Total.                                                                                                 $406,606,484.74

                                                Cost and financial summary
                                                  CONTRIBUTED FUNDS

                                                    Fiscal year ending June 30                                                Total to June
                                                                                                                            30, 1954, includ-
                                                                                                                             ing fiscal years
                                   1950             1951              1952              1953             1954                 priorto 1950

New work:
   Contributed ....    $161,177.75             -$11,666.08 ------------             $49,114.38        $46,293.56               $2, 527, 972.90
   Cost....-----------619,150.32                  58, 788.47     $29,334.60          36,353.86        1 71,118.05               2, 527, 972.90
Maintenance:
   Contributed _...                               28,000.00        -4,683.94        271,600.00 -_--..----                        2 356, 814.63
   Cost_ _                                         7, 245.68        16, 070.38      271,600.00 -------------                     2 356, 814.63

  1 Includes accounts payable in amount of $448.80, which was excluded from 1953 cost.
  2 Amount reported as of June 30, 1953, increased $2,866.78 to include amount applicable to flood control
emergencies. See footnote (1), p. 2072 of 1953 annual report.

                                               Cost and financial summary
                                                        CONSOLIDATED


                                                    Fiscal year ending June 30                                              Total to June
                                                                                                                            30, 1954, includ-
                                                                                                                            ing fiscal years
                                   1950             1951              1952             1953              1954                 priorto 1950

New work:
   Allotted and
     contributed_           $52,076,023.86 $48,216,259.09 $45,330,106.48 $43,433,791.13 $12,176,388.43 $801,597,572.78
   Cost ..      ....         55,376,879.48 48,625,572.15 42,818,452.73 58,243,837.86 50,652,726.56 798,725,484.69
Maintenance:
   Allotted and
     contributed _             16,194,153.89   13,344,544.83     15,965,209.58     17,204,305.25 13,858,444.78               235,663,479.22
    Cost .....     .....       16,732,230.29   13,290,382.18     15,471,379.08     17,415,114.77 13,893,067.41               234,860,100.84


Other new work data:
    Unobligated balance, fiscal year ending June 30, 1954 --------     $719,736.60
    Appropriated for succeeding fiscal year ending June 30, 1955___ 46,450,000.00
    Unobligated balances available for succeeding fiscal year ending
      June 30, 1955_                                                 47,169,736.60
    Estimated additional amount needed to be appropriated for
      completion of existing project___________________________ 406,606,484.74
            WATERWAYS EXPERIMENT STATION

                   ORGANIZATIONS     AND FUNCTIONS
     The Chief of Engineers, by letter dated June 18, 1929, to the
  President of the Mississippi River Commission, directed the estab-
  lishment of a hydraulic laboratory in the alluvial valley of the Mis-
  sissippi. This institution is the Waterways Experiment Station
  with installations at Vicksburg, Miss., and Jackson, Miss. It was
  initially established in 1929, under the jurisdiction of the President,
  Mississippi River Commission. By General Order No. 9, Office,
  Chief of Engineers, July 29, 1949, the Station was transferred to
  the direct jurisdiction of the Chief of Engineers, effective August
  10, 1949.
     The organization comprises the Hydraulics, Soils, Concrete,
  Technical Services and Construction Services Divisions, and the
necessary administrative and service facilities for the conduct of
experimental research and development and field exploration work.
The Flexible Pavement Branch of the Soils Division conducts
airfield, landing mat and trafficability studies for the Office, Chief
of Engineers. The Concrete and Soils Laboratories also serve as
Division Laboratories for the Lower Mississippi Valley Division.
The Mississippi River Commission Field Printing Plant is located
and operated by the station.
     The experiment station has as its functions the experimental in-
vestigation of problems in hydraulics, soil mechanics, concrete, and
flexible pavements presented to the Station for study, as well as
research and development work in those fields; technical super-
vision of hydraulic model testing at other Corps of Engineers
hydraulic laboratories, including the Bonneville Hydraulic Labora-
tory, St. Anthony Falls Hydraulic Laboratory (St. Paul District),
and the hydraulic laboratory of the Los Angeles District; proto-
type testing in fields of hydraulics, soils and concrete; and technical
supervision over hydraulic testing performed under contract with
universities or other outside agencies for the Corps of Engineers.
Work is performed on a reimbursable basis primarily for other
Corps of Engineers offices and also, with authority of the Chief of
Engineers, for other Government agencies, private concerns, and
foreign Governments. The experiment station maintains close con-
tact with the field in all experimental work, both by station person-
nel visiting the field and by engineers from the field visiting the
Station while model studies or other testing are in progress.
    The Waterways Experiment Station is also charged with the as-
sembling of experimental engineering data from all sources, do-
mestic and foreign, in the technical fields assigned to it; the trans-
lation and interpretation of these data; and the dissemination
thereof to other Corps of Engineers offices through its Research
Center and technical reference library. During Fiscal Year 1954,
one annual summary, 109 reports of individual studies conducted at
the waterways experiment station and 10 translations of foreign
articles were distributed to Corps of Engineers offices and inter-
                                                             1631




      Sig 52-1631-1662
1632     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

ested outside agencies. In addition, the editing and printing units
of the Technical Services Division completed 77 publication assign-
ments for other offices.
       OPERATIONS AND RESULTS DURING FISCAL YEAR
  All work accomplished at the Waterways Experiment Station is
initially financed by the revolving fund, reimbursement therefor
being obtained directly from agencies for whom the work is per-
formed. The cost for operation of the station for the 12 months
ending June 30, 1954 amounted to $4,479,372, of which $3,893,055
was charged to establishments served for practical research in-
vestigations and related services, and $586,317 for permanent'im-
provements and miscellaneous operating expenses. Of the reim-
bursable work, $2,258,965 was charged to civil funds, $1,596,585
to military funds, and $37,505 to non-Governmental agencies. The
total cost incurred for operation of the Waterways Experiment
Station to June 30, 1954, amounted to $46,871,892 of which $37,-
549,203 was for reimbursable operations and $9,322,689 for the
cost of permanent improvements and miscellaneous operating ex-
penses.
 PERMANENT INTERNATIONAL ASSOCIATION OF THE
         CONGRESSES OF NAVIGATION
   By an act approved June 28, 1902, Congress appropriated the
sum of $3,000 per year for the support and maintenance of the
Permanent International Commission of the Congresses of Navi-
gation and for the payment of the actual expenses of the properly
accredited national delegates of the United States to the meetings
of the congresses and of the Commission. An increase in this ap-
propriation to $5,000 per year was authorized by the River and
Harbor Act approved June 30, 1948. Beginning with the fiscal
year 1936, such expenses were paid by allotment from the general
appropriation for the improvement and maintenance of river and
harbor works. In fiscal year 1954 the allotment of funds for
these purposes was included under General Expenses, Corps of
Engineers, a single year appropriation.
   The object of the association is the promotion of inland and
maritime navigation by means of organized congresses, and the
publication of pertinent information. Its headquarters are in
Brussels, Belgium, but the congresses are held in various coun-
tries upon invitation. The association is supported principally
by member nations, but the privileges of membership are also ex-
tended to corporations, libraries, and individuals. Governments are
represented by delegates, the number of delegates being based on
the amounts received annually from such governments and their
nationals for the expenses of the Commission. Corporate member-
ship may or may not include the privilege of representation by
delegate. Two classes of corporate membership are available, the
class paying the higher annual subscription having the privilege
of representation by delegate. Life individual membership may
be secured upon the payment of a single fee or ordinary individual
membership upon the payment annually of a fixed fee.
   The general affairs of the association are managed by a Per-
manent Commission with the assistance of a Permanent Council.
The Commission is composed of delegates from the supporting
governments, and the Council is chosen from the members of the
Permanent Commission, the representation in each case being
according to the amount of the annual contribution.
   Due to the large number of American members of the Interna-
tional Association, an informal national organization known as
the American section was authorized by the Chief of Engineers.
The American section conducts all correspondence and handles
all administrative matters between the American members and
the International Association. The American members of the
International Commission act informally as the governing body
of the American section and the resident member of the Board
of Engineers for Rivers and Harbors is ex-officio a member of the
Commission and Secretary of the American section. The Secre-
tary is assisted in administering the affairs of the American Sec-
tion by the two members of the Permanent Council.
                                                         1633
1634     REPORT OF CHIEF OF ENGINEERS. U. S. ARMY, 1954

    During the fiscal year 1954 the United States was represented
as follows:
    On the American section of the Permanent Commission by Maj.
Gen. Philip B. Fleming, United States Army, retired, chairman;
Brig. Gen. Gordon R. Young, United States Army, retired; Mr.
J. Spencer Smith, of the State of New Jersey; Col. Spencer Cosby,
United States Army, retired; Maj. Gen. Glen E. Edgerton, United
States Army, retired; Rear Adm. Wm. H. Smith, United States
Navy, retired; Col. C. L. Hall, United States Army, retired; Maj.
Gen. Lewis A. Pick, United States Army, retired; Maj, Gen. John
S. Bragdon, United States Army, retired; and Col. Francis H.
Falkner, Corps of Engineers, United States Army. Colonel Falk-
ner served as secretary of the American section. During the
year a vacancy was created on the Commission due to the death
of Mr. J. Spencer Smith.
   On the American section of the Permanent Council by General
Fleming and Colonel Hall.
   During the year the United States participated in the XVIIIth
International Navigation Congress held in Rome, Italy, Septem-
ber 13-21, 1953, and in the annual meeting of the Permanent In-
ternational Commission held in Brussels, Belgium, June 1-3, 1954.
   The United States was represented at the Rome Congress by
eight official delegates, namely: Col. C. L. Hall, United States
Army, Retired, Chairman, and principal delegate from the United
States; Colonel Francis H. Falkner, Corps of Engineers, U. S.
Army; Col. Earl E. Gesler, U. S. Army, Retired; Dr. Serge G.
Koushnareff, Department of Commerce; Col. John L. Person, Corps
of Engineers, U. S. Army; Dr. Robert S. Rowe, Princeton Univer-
sity; Col. James Gordon Steese, U. S. Army, Retired; and Brig.
Gen. Paschal N. Strong, Corps of Engineers, U. S. Army. At the
annual meeting in Brussels Maj. Gen. Philip B. Fleming, Chair-
man, Col. Francis H. Falkner, Secretary, and Mr. James W. Davis,
Director, Port of Baltimore Commission, represented the United
States.
   At the Rome Congress the United States was one of the prin-
cipal contributors to the technical discussions. American mem-
bers of PIANC contributed technical papers on 12 of the 13 sub-
jects. American technical views were sought by representatives
of the 37 participating nations and the American delegates parti-
cipated extensively in the discussions. Over 200 technical papers
submitted by other nations provided a great volume of informa-
tion on foreign practices and plans for the benefit of the American
members of the Association.'
   At the annual meeting in Brussels the Permanent International
Commission accepted the invitation of Great Britain to hold the
XIXth International Congress in either London or Edinburgh' in
1957. The Commission also adopted rules proposed by the Ameri-
can Delegation for the processing of technical papers to assure
distribution to delegates prior to the Congress.
   Federal agencies concerned with maritime matters and all cor-
porate and individual members of the American section received
copies of all technical papers presented at the Rome Congress,
PERMANENT INTERNATIONAL ASSOCIATION OF CONGRESSES                                              1635
and copies of Bulletin No. 38 of the Association. In addition the
Secretary of the American section issued Newsletters at irregu-
lar intervals to all corporate and individual members informing
them of the activities of the Association and citing matters of
technical interest.
   The membership of the American section on June 30, 1954
totaled 571 consisting of 21 corporate members and 550 individ-
uals. During the year individual memberships declined by 40
while corporate memberships increased by 5. The Association is
encouraging a trend toward more corporate affiliations and fewer
individual members.
   The balance of Federal appropriations at the beginning of the
year on June 30, 1953 amounted to $13,878.40. This sum was
accumulated by curtailing expenditures from the annual $5,000
allotments of prior years. On June 30, 1954 the unobligated bal-
ance was reduced to zero due to Congressional action requiring
that unobligated General Expense funds not continue into the next
fiscal year.
   Federal funds were expended as follows:
   Annual U. S. contribution to the Association..................                 .       $1, 500.00
   Expenses of delegates to XVIIIth Congress..            ...........--------------------  1,536.32
   Expenses of delegates to annual meeting-_                      ......-....              3, 164.76
   Postage and Administrative Expenses.........--------------------------335.40
           Total expenditures..........---------------------------------.......6,536.48
           Funds revoked     ---------------------...... ...... ....               7, 341. 92
                                                                      .....---------------.
                   Total...........------------------   ..                .... ......-------------------
                                                                                             13,878.40

   The past year, being an International Commission Congress year,
occurring once every four years, was an active one in PIANC
affairs. There was a considerable international exchange of mari-
time and inland waterway information and the American section
achieved closer coordination between the various United States
agencies concerned with maritime matters as well as between them
and the agencies of other nations.
             INTEROCEANIC CANAL SURVEYS

   The proposed canal route across Nicaragua extends from Brito
on the Pacific via the Rio Grande Lake Nicaragua, the Rio San
Juan, and the Rio Deseado to Greytown on the Atlantic, and is
173 miles long.
   A survey of the Nicaragua route was made in 1901, and Public
Resolution 99, 70th Congress, approved March 2, 1929, authorized
a further survey to bring the data up to date, as well as an in-
vestigation of additional facilities needed at the Panama Canal,
to be made under the direction of the Secretary of War and super-
vision of the Chief of Engineers, with the aid of such civilian engi-
neers as the President deemed advisable. The President appointed
the Interoceanic Canal Board to assist the Chief of Engineers.
The Governor of the Panama Canal made the investigation at Pan-
ama, and a provisional battalion of United States engineer troops
made the survey in Nicaragua.
   The report of the Chief of Engineers, together with the reports
of the Interoceanic Canal Board, of the Governor of the Panama
Canal, and of the officer in charge of the survey, was submitted
on December 5, 1931, and published in House Document 139, 72d
Congress, 1st session.
   Appropriation for the investigation and survey was $150,000,
all of which had been expended by the end of the fiscal year 1943.
The River and Harbor Act, approved June 20, 1938, authorized
the Secretary of War to continue the gathering of hydrological
data in Nicaragua under the supervision of the Chief of Engi-
neers as recommended in House Document 139, 72d Congress, 1st
session, and such incidental expenses as may be necessary in con-
nection therewith are to be paid from appropriations hereafter
made for examinations, surveys, and contingencies of rivers and
harbors.
   Collection and compilation of hydrological and meterological
data was continued by the Inter-American Geodetic Survey, under
the supervision of the Chief of Engineers, in conjunction with
its other activities.
   During the past fiscal year the collection of these data has in-
volved the operation within the watershed of Lake Nicaragua of
a number of rainfall stations, also stations for collection of evap-
oration data, recording lake levels, recording barometic pressure
and humidity, and for gaging wind velocity and temperature.
   The expenditures for the fiscal year ending June 30, 1954, were
$8,507.37, from appropriations made for general investigations,
collection and study of basic data.
   It is estimated that $7,000 will be expended in continuing the
operations during the fiscal year ending June 30, 1955.
                                                           1637
      INVESTIGATIONS AND SUPERVISION OF PROJECTS.
         UNDER THE FEDERAL WATER POWER ACT

   The Federal Water Power Act of June 10, 1920, created the
Federal Power Commission, composed of the Secretary of War,
Secretary of the Interior, and Secretary of Agriculture, with
authority to grant permits and licenses for hydroelectric develop-
ments in all waters over which Congress has jurisdiction. The
act further required that the work of the Commission be performed
by and through the Departments of War, Interior, and Agriculture,
and their engineering, technical, and other personnel, except as
may be otherwise provided by law.
   By the act of June 23, 1930, entitled "An act to reorganize the
Federal Power Commission," sections 1 and 2 of the Federal Water
Power Act of June 10, 1920, were amended. A commission was
provided for to be composed of five commissioners to be appointed
by the President, by and with the advice and consent of the Senate.
The necessity of performing the work through the Departments
of War, Interior, and Agriculture was also removed and the Com-
mission authorized to appoint such officers and employees as are
necessary in the execution of its functions.
   By title II of the Public Utility Act of 1935, approved August
26, 1935, the original Federal Water Power Act was made part I
of the Federal Power Act, and parts II and III added to that act.
   The law also provides that no waterpower license affecting the
navigable capacity of any navigable waters of the United States
shall be issued until the plans of the dam or other structures af-
fecting navigation have been approved by the Chief of Engineers
and the Secretary of the Army. There is further provision where-
by any person or corporation intending to construct project works
in any stream over which Congress has jurisdiction, other than
navigable waters, shall file a declaration of intention for the pur-
pose of ascertaining whether or not the jurisdiction of the Federal
Power Commission will attach.
   During the past fiscal year work of an engineering nature has
been assigned and accomplished as follows:
Plans approved by Chief of Engineers and Secretary of the Army in accordance
  with sec. 4 (e) of Federal Water Power Act----..-----------------------............................................................ 15
Reports submitted on applications for preliminary permits or licenses or amend-
  ments thereto....................---................--------------------------............................................................................. 39
Licenses and permits under supervision....-------------.....------------------....................................................... 10

   The necessary expenses of transportation and subsistence of
personnel engaged in investigations and the cost of supervision
under the provisions of the Federal Power Act are paid from ap-
propriations made for the Federal Power Commission. All other
costs of administration of the laws in question are paid from
funds available for maintenance and improvement of existing
river and harbor work.
  During the fiscal year funds were expended as follows for the
                                                                                                                                         1639
1640         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

investigation of waterpower projects in cooperation with the
Federal Power Commission and the supervision of operations
under waterpower permits and licenses:
From appropriations for the Commission................................................ $38. 71
From appropriations for works of river and harbor improvements................ 6, 139.13

                                                                                    6,177. 84
                                   MISCELLANEOUS CIVIL WORKS

        In addition to the work of improving rivers and harbors, civil
works of a miscellaneous character as indicated below have been
committed to the Corps of Engineers. Reports on international
boundary waters are found at the pages listed.
         Kootenay Lake Board of Control (p. 1645).
         Lake Champlain Board of Control (p. 1641).
         Lake of the Woods Board of Control (p. 1644).
         Lake Superior Board of Control (p. 1643).
         Massena Board of Control (p. 1643).
         Niagara Board of Control (p. 1642).
         Osoyoos Lake Board of Control (p. 1646).
         Prairie Portage Board of Control (p. 1645).
         Rainy Lake Board of Control (p. 1645).
         St. Croix River Board of Control (p. 1640).
        Work accomplished.                                   The work of the fiscal year is summarized
as follows:
Anchorage areas, special, established or modified under the provisions of sec. 1
  of the act of Congress of Apr. 22, 1940................................................................                                  2
Anchorages established or modified under the provisions of sec. 7 of the River
  and Harbor Act of Mar. 4, 1915......................................................................                                     2
Bridge plans approved by the Chief of Engineers and the Secretary of the Army
  under the provisions of sec. 9 of the River and Harbor Act of Mar. 3, 1899, the
  General Bridge Act of Mar. 23, 1906, and the General Bridge Act of 1946...... 1 178
Bridge rules and regulations established or modified under the provisions of sec.
  5 of the River and Harbor Act of Aug. 18, 1894...............................................                                           24
Dams, other than water-power structures ,plans, approved by Chief of Engineers
  and the Secretary of the Army under the provisions of sec. 9 of the River and
  Harbor Act of Mar. 3, 1899---.................................................----------------.......------....................--------  1
Danger zone regulations established or modified under the provisions of ch. XIX
  of the Army Act of July 9, 1918, or sec. 7 of the River and Harbor Act of Aug.
   8,    1917 ._...--..........................................................................................-------------------...................   16
Fishing regulations established or modified under the provisions of sec. 10 of the
  River and Harbor Act of Mar. 3, 1899-------.....................................................----                         2
Harbor lines established or modified under the provisions of sec. 11 of the River
  and Harbor Act of Mar. 3, 1899-------- ...................................................................------------       7
Navigation regulations established or modified under the provisions of sec. 7 of
  the River and Harbor Act of Aug. 8, 1917.                   ........       .................................... ......      11
Permits issued for work or structures in navigable waters under the provisions of
  sec. 10 of the River and Harbor Act of Mar. 3, 1899............................ ............... 5, 779
Restricted area regulations established or modified under the provisions of sec.
  7 of the River and Harbor Act of Aug. 8, 1917 ......................................................                         3
Sunken vessels removed under the provisions of secs. 19 and 20 of the River
  and Harbor Act of Mar. 3, 1899.....--------...------............................................--------------------..... 2 63
  ' In addition, 88 extensions of time on bridge plans were approved.
  2 In addition, 124 sunken vessels investigated but not removed.




                                                               J   +%                                                                         1641
1642               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

     Appropriations. The funds with which the miscellaneous civil
works were prosecuted during the year totaled $1,290,461.87 and
were derived as follows:
For investigations, inspections, hearings, reports, service of notice or
  other action incidental to examination of plans or sites of bridges or
Mother structures built or proposed to be built in or over navigable
  waters or to examinations into alleged violations of law for the pro-
  tection and preservation of navigable waters of the United States
  or to the establishment or marking of harbor lines or establishment
  of anchorages: Allotted during year..........................................................                      $559, 759. 70
   (These funds were allotted from river and harbor appropriations in accordance with the provisions of
sec. 6 of the River and Harbor Act of Mar. 3, 1905.)
For the investigation and removal of sunken vessels:
    Balance on hand July 1, 1953----..----.....-----..............................--------.......................     123, 144.60
    Allotted during year....           ------------------------------------                                           606,908.54
    Received from sales and reimbursements.................----------------------..........................                649. 03
  (These funds were allotted from the appropriation "Operation and Maintenance, General, Corps of
Engineers, Civil".)
                  Total ....................                                             ........    ............. 1, 290, 461. 87

     Expenditures. The total expenditures for the fiscal year, ex-
clusive of :outstanding liabilities, amounting to $42,068.26, were
$978,471.01 expended as follows:
For investigations, inspections, hearings, and other action incidental to
  administration of Federal laws                               _....
                                            -------------------..---                                       ------- $559, 759. 70
For the removal of sunken vessels .............-----------------------------........................................... 418, 711.31
          Total.....................................---------------------------------------------                     978, 471.01
Total funds available--------------..............-----------------------.............................................. 1, 290, 461.87
Total expenditures-.........................                        ...       ........................ $978, 471.01
Outstanding liabilities-------......................................---------------------                42, 068.26
Revoked.....................................................-------------------------------------.       28, 379.78

                                                                                                                    1,048, 919.05
          Balance available June 30, 1954........................................-------------------------.           241, 542.82



                    INTERNATIONAL BOUNDARY WATERS
   THE INTERNATIONAL ST. CROIX RIVER BOARD OF CONTROL
   Constitution and duties. The Board was organized pursuant to
conditions in the orders of the International Joint Commission
approving the maintenance and operation of the dam built by the
St. Croix Water Power Company and the Sprague Falls Manu-
facturing Company, Ltd., across the St. Croix River at Grand
Falls in the State of Maine, and subsequent agreements reached
between the Governments of the United States and the Dominion
of Canada.
   The Board is charged with the duty of formulating and admin-
istering rules under which the power plant and accessories are
to be operated to prevent as nearly as possible a level of water at
the dam higher than 203.5 (mean sea-level datum), and to secure
to the users of water below Grand Falls the flow of water to which
                    MISCELLANEOUS CIVIL WORKS                1643
they are entitled. The Board is also charged with the supervision
of the operation of all fishways on the portion of the St. Croix
River that forms the international boundary.
   On October 2, 1934, the International Joint Commission issued
an order approving the reconstruction of the dam, owned by Cana-
dian Cottons, Ltd., extending across the St. Croix River from
Milltown in the province of New Brunswick, Canada, to Milltown
in the State of Maine, United States of America, which contained
the following conditions:
   1. That the reconstructed dam be so operated as to ensure
that the forebay levels rise to no higher elevation than that which
has heretofore obtained in the operation of the dam now being
replaced.
   2. That during times of flood the sluiceways of the dam shall
be sufficiently open to ensure passage of the river flow.
   3. That the operation of the dam, insofar as is necessary to
ensure the observance of the provisions of this order, be under
the supervision of the International St. Croix River Board of
Control.
   Members of the Board. The members of the Board for the fiscal
year 1954 were Mr. T. M. Patterson, Water Resources Division,
Department of Northern Affairs and National Resources, serving
as Canadian Member, and Col. L. W. Hewitt, Corps of Engineers,
serving as United States Member, succeeded by Col. R. W. Pearson,
Corps of Engineers, on May 22, 1954.
   Operations during the fiscal year. Supervision was maintained
and inspections by the Canadian and United States members were
made to ensure that the regulations of the International Joint
Commission were carried out. A representative of the United
States member made an inspection of the Vanceboro and Forest
City Reservoir dams at the request of the International Joint Com-
mission and a detailed report on the findings will be made.
THE INTERNATIONAL LAKE CHAMPLAIN BOARD OF CONTROL
   Constitution and duties. The Board was organized pursuant to
the provisions of the orders, dated June 10, 1937, of the Interna-
tional Joint Commission, approving the construction and operation
of certain remedial works in the Richelieu River at Fryers Island
in the Province of Quebec, Dominion of Canada. The Board is
charged with the responsibility of ensuring compliance with the
provisions of the order of approval insofar as they relate to the
regulation of the levels of Lake Champlain.
   Members of the Board. The members of the Board for fiscal
year 1954 were Mr. T. M. Patterson of the Water Resources Di-
vision, Department of Northern Affiairs and National Resources,
for Canada, and Col. A. H. Davidson, Corps of Engineers, for the
United States.
   Operations and results during fiscal year. None. The con-
struction of the Fryers Island Control Dam was completed in De-
cember 1938. Gates have been installed but have not been oper-
ated, pending excavation of the natural river control upstream
from the dam.
1644     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

        INTERNATIONAL NIAGARA BOARD OF CONTROL
   Constitution and duties. The Board was established on August
19, 1953, by directive of the International Joint Commission and
is charged with the duties of reviewing and approving design and
procedures for installation of remedial works, recommended by
the Commission in its report of May 5, 1953, and exercising gen-
eral direction of construction of such works; exercising control
over the maintenance and operation of such remedial works (and
more particularly over the Chippawa-Grass Island Pool Control
Structure) in such manner as to meet the scenic-beauty require-
ments of Article IV of the Treaty of February 27, 1950, by en-
suring a dependable and adequate flow over the falls; ascertain-
ing, determining and recording the amounts of water available
for the purposes of the Treaty of 1950, including diversions for
power and other purposes; and submitting written reports to the
Commission for its meetings or as otherwise directed.
   Members of the Board. The present membership of the Board
consists of Mr. T. M. Patterson, Chief, Water Resources Division,
Department of Northern Affairs and National Resources, and Mr.
A. A. Anderson, Chief Engineer, Department of Public Works, for
Canada, and Col. W. P. Trower, Corps of Engineers, and Mr.
Francis L. Adams, Chief, Bureau of Power, Federal Power Com-
mission, for the United States.
   Operations and results during fiscal year. Assisted by a Work-
ing Committee appointed by the Board in October 1953, consist-
ing of two members each from technical agencies in the United
States and Canada, the Board has reviewed and approved the de-
signs and procedures submitted so far by the construction entities
for the installation of remedial works recommended by the Inter-
national Joint Commission in its report "Preservation and En-
hancement of Niagara Falls", 1953.
   During the fiscal year the construction entity for Canada, the
Hydro-Electric Power Commission of Ontario, awarded a contract
in the amount of $1,785,567 to Canadian Vickers Ltd., Montreal,
Province of Quebec, for the design and manufacture of the gates
and operating machinery of the Chippawa-Grass Island Pool Con-
trol Structure. The construction entity for the United States, the
Buffalo District, Corps of Engineers, awarded a contract in the
amount of $595,741 to the McLain Construction Corporation of
Buffalo, New York, for excavation and fill on the Goat Island flank
of Horseshoe Falls. In each case the Board reviewed and ap-
proved the plans and specifications.
   The Board adopted a publicity program in cooperation with the
construction entities to minimize unguided speculation in the
minds of the public concerning the nature and purposes of the
remedial works. On June 2, 1954, a ground-breaking ceremony
was held at Niagara Falls, sponsored jointly by the Buffalo Dis-
trict, Corps of Engineers and the Hydro-Electric Power Commis-
sion of Ontario on behalf of the International Joint Commission,
to commemorate initiation of construction of the remedial works
for the preservation and enhancement of the scenic beauty of
Niagara Falls.
                   MISCELLANEOUS CIVIL WORKS                 1645
  The Board submitted semiannual progress reports to the Inter-
national Joint Commission in October 1953 and April 1954.
       INTERNATIONAL MASSENA BOARD OF CONTROL
   Constitution and duties. An order of the International Joint
Commission issued after a hearing on the application of the St.
Lawrence River Power Company for permission to continue to
maintain the submerged rock weir constructed by the company
in the south Sault Channel of the St. Lawrence River, authorized
the maintenance of the weir and, among other things, provided for
a board of engineers to pass upon and control the new and old
works involved.
   Members of the Board. The Canadian member of the Board
for the fiscal year was Mr. T. M. Patterson, Chief, Water Re-
sources Division, Department of Northern Affairs and National
Resources, Ottawa. The United States member was Col. Philip
R. Garges, Corps of Engineers, District Engineer, Buffalo, N. Y.
   Operationsduring the fiscal year. The Board kept in touch with
conditions by means of inspections and with respect to the diver-
sion by means of monthly reports of the power company, showing
the amount of water diverted and powerhouse performance from
day to day. The weir was inspected by the district engineer's rep-
resentative on June 28, 1954.
   "INTERNATIONAL LAKE SUPERIOR BOARD OF CONTROL
   Constitution and duties. The Board, organized in pursuance
of orders issued by the International Joint Commission, May 26,
1914, is charged with supervision of the operation of all compen-
sating works and all power canals and appurtenances from the
point of view of controlling the outflow from Lake Superior so as
to maintain its level as near as possible between elevations 602.1
and 603.6 feet above mean tide at New York, and controlling the
outflow so as to prevent the level of the St. Marys River below the
locks from exceeding elevation 584.5
   Members of the Board. The present members of the Board are
Mr. T. M. Patterson, Department of Northern Affairs and Na-
tional Resources, for Canada, and Col. Wendell P. Trower, Divi-
sion Engineer, Great Lakes Division, Corps of Engineers, for the
United States who succeeded Col. Arthur C. Nauman, District
Engineer, Detroit District Corps of Engineers, on October 7, 1953.
   Operationsduring the fiscal year. The Board was kept advised
of conditions pertaining to the regulation of Lake Superior,
through representatives of Canadian and United States technical
agencies, and by means of regular systematic reports of the water
levels in Lake Superior, in channels of the St. Marys River above
and below the Sault Locks, and in Lake Huron. Records of dis-
charge at Sault Ste. Marie through the rapids, navigation canals
and power plants were also systematically reported to the Board.
    A joint inspection of the compensating works was made by the
Board on September 3, 1953, at which time the structure and the
operating parts were found to be in more or less satisfactory con-
dition. The Canadian gates needed painting and the grease cups
1646     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

on the operating parts required attention. Some painting of the
United States gates was required. These conditions are being
corrected.
   Changes in the rate of outflow from Lake Superior are directed
by the Board as indicated by the current operating rule. Supplies
to Lake Superior during the past year have been slightly above
average with appreciable increase over normal supply noted dur-
ing late spring.
   Lake Superior levels at the beginning of fiscal year 1955 corres-
pond closely with those occurring during the same period of fiscal
year 1954. It appears that the maximum seasonal crest during
fiscal year 1955 will approximate the peake level which occurred
in fiscal year 1954.
   On March 30, 1954, the United States member of the Board sub-
mitted copies of the Board's annual report, for calendar year 1953,
to the United States Section, International Joint Commission,
through the Office, Chief of Engineers.
               LAKE OF THE WOODS WATERSHED
   The members for Canada of the International Lake of the
Woods Control Board, the International Rainy Lake Board of Con-
trol and the International Prairie Portage Board of Control for
the fiscal year were Mr. I. R. Strome, Mr. R. M. Watt, and Mr. J.
D. McLeod, in turn. Colonel Aldo H. Bagnulo, Corps of Engi-
neers, was the member for the United States.
   INTERNATIONAL LAKE OF THE WOODS CONTROL BOARD
   The convention between the United States and Great Britain
proclaimed July 17, 1925, provides for the regulation of the level
of the Lake of the Woods in order to secure to the inhabitants of
the United States and Canada the most advantageous use of the
waters thereof, and of the waters flowing into and from the lake
on each side of the boundary between the two countries.
   The convention also provides for the establishment and main-
tenance of a Canadian Lake of the Woods Control Board to regu-
late and control the outflow of the waters of the lake, and for the
establishment and maintenance of an International Lake of the
Woods Control Board, composed of two engineers, one represent-
ing the United States and the other representing Canada, to whose
approval the rate of total discharge shall be subject whenever the
elevation rises above elevation 1061 or falls below elevation 1056,
sea-level datum.
   Operationsduring the fiscal year. Supervision was maintained
and inspections were made to ensure that every effort was being
made to comply with the provisions of the Convention.
                          MISCELLANEOUS CIVIL WORKS                              1647
        INTERNATIONAL RAINY LAKE BOARD OF CONTROL
  The convention between the United States and Canada, ratified
by the United States Senate August 30, 1940, provides in part
that:

   The International Joint Commission * * * is hereby clothed with power to de-
termine when emergency conditions exist in the Rainy Lake watershed, whether by
reason of high or low water, and the Commission is hereby empowered to adopt such
measures of control as to it may seem proper with respect to existing dams at Kettle
Falls-and International Falls, as well as with respect to any existing or future dams or
works in boundary waters of the Rainy Lake watershed, in the event the Commission
shall determine that such emergency conditions exist.

   On June 8, 1949, the Commission issued an order to the owners
of the dams at the outlet of Namakan Lake and Rainy Lake, which
provided for a method of regulation as recommended by the In-
ternational Rainy Lake Board of Control. The order provides for
certain levels during the various seasons of the year as well as
control of outflows, with the view to securing the most advan-
tageous use of the water in total to the various interests.
   Operationsduring the fiscal year. Inspections were made, basin
data compiled, and engineering reports were submitted to the
Commission.
     INTERNATIONAL PRAIRIE PORTAGE BOARD OF CONTROL
   The Prairie Portage Board of Control was formed by the In-
ternational Joint Commission for the purpose of furnishing it
with technical advice regarding the suitability of the dam struc-
ture at Prairie Portage, Lake County, Minn. After approval of
the plans by the Department of the Army, and the International
Joint Commission, the Board has been retained to advise the Com-
mission further regarding progress of construction and regarding
any other matters which might arise concerning this project.
   The United States Forest Service, which is constructing the
dam, postponed work on this project during the war and at this
time is merely maintaining the cofferdam, which was completed
in 1941.
      INTERNATIONAL KOOTENAY LAKE BOARD OF CONTROL
   Constitution and duties. The Board was organized to secure
compliance with the provisions of the orders of the International
Joint Commission dated November 11, 1938, and August 5, 1949,
relating to the construction and operation of control works by the
Consolidated Mining and Smelting Company of Canada, Ltd.,
through the West Kootenay Power and Light Company, in and
adjacent to the channel of the Kootenay River, and the regulation
of the levels of Kootenay Lake in the Province of British Columbia.
1648     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1954

  Members of the Board. The members of the Board for the fiscal
year were Mr. W. C. Warren and Mr. H. T. Ramsden, Water Re-
sources Division, Department of Northern Affairs and National
Resources, Vancouver, British Columbia, for Canada, and Col.
N. A. Matthias, Corps of Engineers, and Mr. T. R. Newell, U. S.
Geological Survey, Boise, Idaho, for the United States.
  Operations during the fiscal year. No formal meetings of the
Board were held during the fiscal year. Investigations and visits
to the area were made by individual members of the Board. The
annual report was submitted to the Commission.
    INTERNATIONAL      OSOYOOS LAKE BOARD       OF CONTROL
   Constitution and duties. A special board of engineers was
constituted to ensure compliance with the provisions of the order
of the International Joint Commission dated July 12, 1943, di-
recting investigation of high water conditions on the Okanogan
River and studies of the relationships between certain obstruc-
tions, complained of in an application by the State of Washington,
and the levels of Osoyoos Lake. The Board was enlarged from two
to four members by an order of the Commission dated September
12, 1946, to carry out the provisions of the order relative to the
operations of the Zosel Dam.
   Members of the Board. The members of the Board for the fiscal
year were Mr. W. C. Warren, Water Resources Division, Depart-
ment of Northern Affairs and National Resources, Vancouver,
British Columbia, and Mr. C. F. P. Faulkner, Department of Pub-
lic works, Canada, New Westminster, British Columbia, for
Canada, and Mr. F. M. Veatch, United States Geological Survey,
Tacoma, Washington, and Col. N. A. Matthias, Corps of Engi-
neers, for the United States.
   Operations during the fiscal year. No formal meetings of the
Board were held during the fiscal year. Supervision was main-
tained to ensure compliance with the provisions of the Interna-
tional Joint Commission. The annual report was submitted to
the Commission.
                                                   INDEX

                                                             A
                                                                                                                       Pagl
Abbapoola Creek, S. C........................................------------------                          326
Aberdeen, Ohio..........................  .................................................              978
                                                              ..........................................
Abiquin Dam, N. M ex ...................................................                                 634
Abraham Creek, Pa.................................: ......................................
                                                                               ......................    234
Abseson Creek, N. J...............................              ..  ..    190
                                     ................................................
Absecon Inlet, N. J...............................................----.......................---....                           180
Academy Creek, Brunswick Harbor, Ga., improvement. .......................                                                     340
Accotink Creek, Va .................................................                      ....................258
Adams Bayou, Tex.............................................................                        .       ............      552
Adams, Hoosic River Basin, Mass...................................                                             .............. 151
Adams levee unit, Indiana ....................................................         . ...         .... .............        944
Addicks Reservoir, Tex .. ..................................................           .      ......      .................    599
Addison, N. Y ................ .................................................. ...    .      ......      ..........         225
                        .................................
Adena, Ohio................                                                         .....
                                                                                       ..... ........          .......... 1024
Adger, Ala................................................................................... 438
Agate Bay (Two Harbors) Minn...................................................                                               1033
Ahnapee River, Wis......................................................................1068
Aitkin, Minn., Mississippi River near................................................                                          784
Akron, Ala........................                      . . .....           ..
                                         ...................................... ...                              .      438
Alabama-Coosa Rivers, Ala. and Ga......................................                                             ...........          432
Alafia River, Fla.. ... .....                         .... .. . ....................
                                                                       .            .....................                   .... 391
Alameda Creek, Calif ..... .....                    ...................................                . .................
                                                                                                                      ... .            1346
Alamo Reservoir, Bill Williams River, Ariz.............                          ..........................                             1298
Alaska engineering district.............                    .       ................
                                                                             ............................                               1543
Albermarle and Chesapeake Canal, N. C. and Va., improvement ...............                                                         .. 285
Albeni Falls, Idaho........................................................................ 1516
Albuquerque, N. Mex., engineering district.....................................                                                          629
Alexandria, Va., improvement of Potomac River at...............................                                                          258
Algiers Lock, La......................................................................                                                   461
Algoma Harbor, Wis             .............................................                                                            1068
Alhambra, Wash., Los Angeles, Calif ...............................                                 _                         ..        1268
Aliso Creek Dam, Calif .............                       .......................................                            1288, 1298
Allatoona Reservoir, Coosa River Basin, Ga-...........-.................                                                                 449
Allegany on Allegheny River, N. Y......................................................                                                1024
Allegheny River, Pa. and N. Y.....                                            ................
                                                                                        .....                                  ..        983
      Construction of locks and dams .............................                                         ............ 983,985
       Flood control reservoirs .........................................................                                              1025
      Improvement by open channel work .......................................... 996
Allentown, Lehigh River, Pa.                    .......................................................                                  191
Alligator River, N. C.            . . ............
                                             ....... .......             ...      .. . ..................           .. ......            299
Alloway Creek, N. J..                .................................................                                                   190
Allyns Point, Thames River, Conn.......                                    ......................   ..........                             43
Alma, Wis., harbor.........................................................                                                              737
A l m on d R e se rvo ir, N . Y .. . . . . . . . ..     . .. . .. ...... . . . . . . . . ... . . . ... .... . . ...               .22 1, 2 2 7
Aloha-Rigolette area, Louisiana.                         ...............................                          ........       .497,509
Alpena Harbor, M ich... ......................................                                          ........................         478
Altamaha River and Sound, Ga.............                          .....     .................................                           340
Alton, Ind ............ .       . . . ......                      ....... .. .......
                                                                 .........                      ......................                   944
Amazon Creek, Oreg ....            ...............          ..................................              . ................ 1453
Ambrose Channels, New York Harbor, N. Y., improvement .........................                                                          125
Am erican Channel, M ich.......................................................                                                        1163
American River, Calif .........................................................                                                        1349
Amherstburg Channel, Detroit River, Mich., improvement.............................                                                    1162
Am ite River, La .         . ..........
                                      ... ..................................................                               ........ 49
                                                                                                           1649
 1650                                                                         INDEX

                                                                                                                                                                    Page
Amsterdam, Ohio                         ------.... -------------------------------------                                                                                 1030
Anacortes Harbor, Wash--...... -----------------------..............................-------.                                                                             1485
Anacostia River, D. C.:................................................---------------------------------------..........................................243,259
     Reclamation and development of the flats..................---------...--...--.......                                                                                  258
Anahuac Channel, Tex...                              -------.. -------------------------------------------                                                                 576
Anchorage Channel, New York Harbor, N. Y..........................................................                                                                         125
Anclote River, Fla .......................-----------------..----.....................................-----.......................................--------           384, 401
Anderson, Ind ...........................................                                                                                                                  9--------------------
Andover Reservoir, Conn ............................................................................................ 65, 83
Angelina River, Tex----.......................----------------------------------------............................................................................         604
Annapolis Harbor, Md.................-------------------------------------................................................................................                 218
Annisquam River, Mass-----........--------------------------------------......................................................................................               17
Anthony Shoals Reservoir, Ga-----......-.............--.................----...............----............................... 3------                                    341
Apalachicola Bay, Fla., to Mexican border.......----......................................................                                                                 414
Apalachicola Bay, Fla ..                                                   ------------------------------------------- 448
Apalachicola, Chattahoochee, and Flint Rivers, Ga. and Fla................................                                                                                 417
Aplin, Ark----------------------------------------------------                                                                                                             667
Apoon Mouth of Yukon River, Alaska......................................................................                                                                 1547
Appomattox River, Va..................................................................................................                                                     274
Appoquinimink River, Del----------------------------------------..........................................................................................                 190
Aqueduct, Washington, D. C., maintenance and repair of .................................. .                                                                               252
Aquia Creek, Va---------..............................................................................................--------...                                         258
Aransas Bay and Pass., Tex ....---------------------------------------....................................................................................                558
Arcadia Harbor, Mich-------------------------------------------..................................................................................................        1113
Arcadia Wash system, Calif ........................-.........--...............................................                                                          1268
Arecibo Harbor, P. R.......................................... ..... ...............................................                                                       401
Arkabutla Reservoir, Miss...... ........................                                      .....----............................................---.                 1584
Arkansas River and Tributaries, Ark. and Okla.:
     Tulsa District................................................................................................                                             671,695, 700
     Little Rock District----------------  ...................................--........................................... 643,645, 663
     Vicksburg District.....                                         ----------------------....-----------------. 523,645
Arkansas, White and Red River Basins, Ark., La., Okla., Tex., N. Mex., Colo.,
  Kans., and Mo..-------------------------------------........................................................................................................             519------519
     Flood control, Pueblo, Colo..............--...............----............--                   -........-------------..---..---------..........................      629
     John Martin Reservoir, Colo ....................................................................--------------------------------........                              630
Arkport Reservoir, N. Y....---------------------..................................................................---------------..........-----........                  221
Arlington, Oreg ..............................................................................................-------------------------------.........                   1476
Arlington Reservoir, Mo----....-........................----------------------------------................................................................                 820
Arnaudville, La .....                                                                                                     .....................................            486
                                                                                                                                                                          48................
Arthur Kill, N. Y. and N. J........................................................................................                                                        131
Ash Creek, Conn---..----------------..........................................................................................................                              53
Ashepoo River, S. C., improvement of waterway via..............................................                                                                           316
Ashland Harbor, Wis..                                                ------------------------------------------......                                                   1040
Ashland, Ky............................................................................................................972,---------------------------------972,978
Ashland City, Tennn .......................................-----                                                                                                           881
                                                                                                                                                                          881.......................
Ashley River, S. C------........................-------------------------------------.....................................................................                322
Ashtabula Harbor and River, Ohio-----.. ----........                                            --...............................................................       1198
Ashuelot River, N. H---------      ............---..................................................................................                                        85
Aspinwall, Pa .................................................................................................................                                           9985
Association of Congresses of Navigation, Permanent International...................... 1631
Astoria, Oreg ..........-------------------------------------------------                                                                                                1429-----------------
                                                                                                                                                                        1429.......................
Asylum Slough, Calif ----------..           .....................           ...................................... ......... ..................                          1314
                                      ..................................................................................................
Atchafalaya River, La----------------------------                                                                                                                         495
Athalia, Ohio ...-------------..............................................--......................................................                                      978
Atlantic-Gulf Ship Canal, Fla.....................................................................................                                                        401
Atlantic Intracoastal Waterway:
  Between Norfolk, Va., and the St. Johns River, Fla.:
     Norfolk District ....                          ----------------------------.........................................                                                 284
     Wilmington District ...............................---------------------................................................                                             297
     Charleston District .................................................                                                         .............. ..............
                                                                                                                      ----.....---.....                                   315
     Savannah District................. ..............................................................-..................                                                 329
     Jacksonville District .............................-----------------------------------------..............................................................           347
Atwood Reservoir, Ohio....................................................-----------------------------.....................................                              960
Augusta, Ga..----.------.                  . -           . -            .-            . --... .                    .                                                345
Augusta, Kans ....... ..                                                   .....................................................                                    700
Augusta, K y .................................................................................................................                                      944
                                                                               INDEX                                                                              1651
                                                                                                                                                                         Page
Augusta, Me...                               ----------------------------------                                                         --        -------------..       8, 9
Aunt Betty Rodgersditch, Ark.........------------------------------------549
Aurora, Colo.......................................................................................................-----------------------------------------.....       846
Aurora, Ind ...................................................................................................---------------------------------------------........... 944
Au Sable Harbor, and Harbor of Refuge, Mich.-..-.....-.......................................... 1165
Autauga Creek, Ala                       -------------.        .--------                                                           --------------------                 452
Avery Point, Tex ..---------------........................----------------------------..........................................................................--      589
Avoca, N. Y........................--------------------------------------------......................................................................................   225
                                                                                      B
Bachelor Island, Clark County, Wash.......................................................................                                  1473
Back Bay, Miss-----..------------------------------------------                                                                              442
Back Cove, Me------..........-----------------------------..................... 10, 11
Back Creek, Md.........-----------------------------------------171,206,218
Back River Brunswick Harbor, Ga., improvement................................................                                                340
Back Sound, N. C....---------..........................................................................................                      313
Bagaduce River, Maine               ---------......................-----...................................................................   53
Baker Bay,
Baldhill       Wash----------------------------------------------1435
          Reservoir,   N. Dak     ......................................................................................... 771,780
Baldhill Reservoir, N. Dak.....                                                              -.........                                                      771, 780
Ball Mountain Reservoir, Vt                                        ------...--------....................................                                                 69, 73
Ballona Creek Calif.......----------------------..............................................1266, 1268
Baltimore, Md.:
     Engineering district-----------------
                                        ......................................................................------------------.                      .................   195
     Harbor and channels-....................----------------------------------------.......................................................................               195
     Harbor, removal of drift-----------            ................----..----------......................---........................................                      200
Banana River, Fla., navigation............................................................................-----------------------                                          363
Bangor, Maine, navigation                                   ---------...----------                                       ----------------------.                              6
Bank stabilization and channel rectification, Arkansas River, Ark. and
  Okla -------------....-----------                                                                                                                              646,647,649
Banner, Ill., special drainage and levee district---..
                                                                                                  ---------------------
                                                                                                                 --------.-------.
Barataria Bay and Bayou, La---..-----........------------------495....................................................................
                                                                                                                                             _____                        1148
                                                                                                                                                                           495
Barbourville, Ky ...................................................-----------------------------------------------.....................................................   897
Barcelona Harbor, N. Y ....---..---------------------...........................................................................                                          1227
Bar Harbor, Maine-----.............------------------------------------..........................................................................................            53
Barker Reservoir, Tex..                                                    -------------------------------------------                                                     599
Barkman Creek, La-----------------------------------------                                                                                                                 517
Barnegat Bay, N. J.............................---------------------------------------------187.......................................................................     17
Barnegat Inlet, N. J-------------------------------------------.....................................................................................................       183
Barnett Creek, Ky....                                                      ----------------------------------------- 934,944
Barre Falls Reservoir, Connecticut River Basin, Mass...............................--                                                                       ......... 69, 83
Barren Island Gap, Md....------------------------------------------                                                                                                       205
Barren River, Ky. and Tenn-----.----------------------.-.........................................................----------.............................                   914
Barroom Bay, Tex----------------------------------------------........................................................................................................    560
Bartholomew Bayou, La. and Ark                              ----------------.......---------.. 528,529, 536, 573
Bartley, Republican River, Nebr.....--------------                               .....................................................                                    820
Bass Harbor Bar, Maine---------------..---..........................................................................................                                        53
Bastrop, La........------------------------------------------------530, 537
Bastrop Bayou, Tex....--------------------------------------------.......                                                                                                 601
Batavia and vicinity, Tonawanda Creek, N. Y........................................................ 1228
Bath, Me.....--------------------------------------------......................                                                                                           8, 9
Bath, N. Y.................--------------------------------------------------                                                                                             225
Baton Rouge to Gulf of Mexico, La--------------------------------
                                                       ..........................................................................                                         473
Baudette Harbor and River, Minn_................................                                                                                                          763
Bautista Creek, Calif..----------...............................................................................................                                         1294
Bawcomville, La....            .-------......--------------------------------------------..........                                                                  :529,538
Bay Creek, Ill             -------------------..                                           ------------------------------                                                 941
Bayfield Harbor, Wis..--------------------------------------............................................................................................                 1050
Bay Ocean Peninsula, Oreg----.........................-----------------------------------...............................................................                 1452
Bayou Bonfouca, La--------------------------------------.....................................................................................................             495
Bayou Boeuf Lock, La................................... ............................-------------------........................                                           463
Bayou Coden, Ala __....... .............................................................................................                                                  448
Bayou Galere, Miss---------------------------------------------
                     ......................................................................................................                                               448
Bayou LaBatre, Ala.. ..................................................................................................                                                   448
Bayou Lafourche, La......................................................................................................                                              483
Bayou Sorrel Lock, La462..................................................................................................                                             462
1652                                                            INDEX
                                                                                                                                              Pa
Bayous La Loutre, St. Malo and Yscloskey, La.....~_.......                                                                                     495
Bayous Nezpique to Des Cannes, La..............................--------------------------------                                               488
Bayou Portage, La-.-----..---.---..-........................................
                              -----                                                              .
                                                                                             --....        ..---...                            471
Bayou Teche, La..............................................................-----------------------------------------------483
Bay Ridge Channel, New York Harbor, N. Y-----... ---------..........                                                     -----------           103
Bay River, N. C-----------------------------------------------                                                                                313
Bayside-Gedney Channel, New York Harbor, N. Y---.---....-------_____                                                            -              125
                                                                                                                                              3----__
Beach City Reservoir, Ohio .....................................----------------------------------------..                                    960
Beach Erosion Board---.... ............................----------------------------------------                                             1557
Beals Harbor Maine                ..           ---------------                           --------------.................--   -----....          53
Bear Creek, Calif...............-------------------............1381
Bear Creek, Colo .........         .               .........................------------------------------------------------                  845
Bear Creek, Ky...........                  .................--------------------------------... ---------------                               914
Bear Creek, Miss ..................................................                                                -------------.....         5-------------------
                                                                                                                                              528
Bear Creek Reservoir, Lehigh River, Pa.............-------------------------..-----.........                                                   190
Bear Dam and Reservoir, Calif .------..........                           ............                                               .---- 1389
Beards Brook Reservoir, N. H .....--------......... .........----------------------------                                                  57, 83
Beardstown, Ill ..........                       ...........
                                   ------------------........                 .........-----------------------------                        1145
Bear River, Calif ..........................----------------------------------------------                                                  1349
Bearse Shoals, Nantucket Sound, Mass .-..........-                                                                                              32
Beaufort Harbor and River, N. C.:
     Improvement of harbor-----..............                             ----------------------------                                        313
     Improvement of waterway to Pamlico Sound via Core Sound to Beaufort
                 .......................................................... .....
        Harbor---------------------------------                                                       ...        ..                           313
Beaufort Inlet, N. C............................................... ....................                                                      2--------------------
                                                 ..
Beaumont, Tex ..................................------------    .............                                                                 552
                                                                                                                 ...------------------------------------
Beaver Bay Harbor, Minn ...-----------........                  ............--------------------------                                      1050
Beaver drainage district, Columbia County, Oreg..---....... -------------- 1473, 1475
Beaver Island, Mich.................                            .--------------
                                                        ------------------------------.....                                                 1113
Beaver and Mahoning Rivers, Pa., and Ohio..........-----------------------996,                                                              1025
Belfast Harbor, Maine                .      ....         ..--------------------------------------------..                                        7
Belhaven Harbor, N. C........------------------------------------------                                                                       313
Bellaire, Ohio          --------------------..--....
                                .-------..-----....-----....                                                                                  024
                                                                                                                                            1----------
Bellamy River N. H .......                      ........---------------------------------------------                                           53
Bell drainage district, Sangamon River, Ill.................------------------..................................1148
Belle Fourche, Cheyenne River, S. Dak .8. - __                                                 --....-.....
                                                                                              ..........---------------------.                845
Belle Glade, Fla ....----------------------------...
                                 ..........                                                                    ------------------             404
Belle Pass, La ..-- .................                                                                                                           83
                                                                                                                                              4-------------------
Belle Plains, Kan ............           ....--------------------------------.......                                      .....               700
Belle River, Marine City, Mich-                          -.....------------------------                                                      1178
Bellevue, Ky ............----------...........-------------------------------------                                                           944
Bell Foley Reservoir, Ark................... ..-----------------------------------------                                                      651
Bellingham Bay and Harbor, Wash____--___-                                                                                  -
                                                                                                                       -___-                1482
Belpre, Ohio...........                     --------------------------------------------------                                                978
Belt Creek, Mont..               ........ ----------------------------------------------- 866
Belton Reservoir, Leon River, Tex.....                                        ----------------------------------                              620
Benbrook Reservoir, Tex. See Trinity River-----.............---------..--                                                                     616
Benedict Canyon, Ballona Creek Basin-------                              ...................         ----------------------- ....          1.1268
Bennetts Creek, Va ........                        ..........                      ..                                                         274
                                                                                                       ...........---------------------------------------------
Bennett Creek, N. Y                  -------....
                                              -------                                  ------------------------------                         226
Bennington, Hoosic River Basin, Vt--..........                                             -----------------------...                         153
Bennington Reservoir, N. H---------------------------------.--57,                                                                          59, 83
Benton Harbor Canal, Mich                                           --------------------------------------                                  1088
Benwood, W. Va......---------------------------------------------                                                                           1022
Beresford Creek, S. C                         ----------------------------                                                                    326
Berlin Reservoir, Ohio ----------------                                                                                                     1017
Berwick Lock, La......----------------------------------------------                                                                          486
Bethlehem, Lehigh River, Pa..............................                                                                                     192
Beverly Harbor, Mass ...--------------------------------------------------------------                                                          53
Bickfords Island, Me..-------------------------------------------_~. -                                                                   -- 12
Big Bay Harbor, Mich...... ------------------------------------------                                                                       1050
Big Bend Reservoir, S. Dak.....------------------------------------                                                                     832,845
Big Bend Reservoir, W. Va                     ...                   ---------------------------------------                                   980
Big Black River, Miss- ---         ----........................                                                                  528,539
Big Blue River, Kans. and Nebr...........-.-.-.-...........---.--------. .                                                .          814
Big Cliff Reregulating Dam, Oreg..                              --.....                                                                1468
                                                                             INDEX                                                                                1653
                                                                                                                                                                   Page
Big     Creek, Ark- ..                           -..-
                                                  --...
                                          -------..                            ---...................... .......................................                          ....  548
Big     (Cunningham) Creek, Ohio......................------------------------------------................................................                                    1227
Big     Darby Creek Reservoir, Ohio ...............................-----------------------......................................                                               980
Big     Dry Creek Reservoir and diversion, California .......----..........--------------........................                                                             1392
Big     HornRiver, Mont ..........................................................................................----------------------------------....                       864
Big     Lake, Ill--------...........-------.........................................--------------------------------........................................................  1148
Big     Marco Pass, Fla., to Naples, Fla-----.............----------------------------........................................................                                 401
Big     Pigeon Bayou, La-----................................--------------------------------...........................................................                       495
Big     Prairie, Ill.......................................................................... ...........................--------------------------------                    1148
Big     Sandy River, including Levisa and Tug Forks, Va., W. Va., and Ky........956, 971
         Flood control reservoirs...................--------                                                 ..----.......                                                      980
Big      Sioux River, S. Dak. and Iowa ..........-------------..............................................................-- 829
Big      Slough to Belle Plains, Kan-----................-----------------------------...........................................................                               700
Big      Suamico River, Wis................................-----------......................................................                                                   1113
Big      Sunflower River, Miss--...--.......--...........--..---------------................------................................                                              528
Big Thoroughfare River, Md-2.................-.............................---..............................                                                       210
Big TimberCreek, N. J..............                                          --....................        ..........................................               190
Biles Creek, Pa .......--........---.....                      --........                                   ...........................................             158..................
                                                                                                                                                                    158
Billings, Mont---.. ---------------..                                                ..........................................................                    863
Biloxi Harbor and Bay, Miss .....-----------------..........................................----------...................................                          442
Binghamton, N. Y........-------...----------------------------------.........................................................................................      222
Birch Hill Reservoir, Connecticut River Basin, Mass....................-------------................... 69, 75
Birch Reservoir, W . Va ...............................................................................................                                            980
Biscayne Bay, Fla.................................................................-------............................                                              374
Bisteneau Lake, La----......................................................................................................----------                             495
Black Bayou Reservoir, La-------....-----                                --------------                           .............................-----          497, 519
Black Butte Dam and Reservoir, Calif                                                  ------------------------..
                                                                                          ..........                                                              1371
Blackfish Bayou, Ark.. ......... ......                            ......................................................................-------                   545
BlackfootArea, Idaho.......----------------.........................................................................................                              1532
Blackfoot River, Idaho                       --.. . . . . . . . . . . . . . . . . . . .---------------..----------------.. . . . . . . . . . . . . . . ----
Black Rascal Creek, Calif ...........................................................................................
                                                                                                                                                                 1532
                                                                                                                                                                  1389
Black River, Ark., Mo., and La....----------------......................................523,650,668
Black River Harbor, Mich                          ................                           ................------------------------------------.               1050
Black River Harbor, N. Y ...--------------------..........................................------------------....................................                  1227
Black River, Mich................................--------------------.......................................................1089, 1178
Black River, N. C............................................---------------------------------------------...................................................      313
Black River, Wis..............                 ----------------.....--......                                                                                       788
                                                                                                                                                              770,----------------------
Black Rock Channel, N. Y..--                                  ..             - --------------                   ..................................               1211
Blackstone River Basin, Mass. and R I .......................................----......................                                                              62
Black Walnut Harbor, Md-----..................-----------------.................................................................                                   218
Black Warrior Warrior and Tombigbee Rivers, Ala .....................--.....................                                                                       436
         Locks and dams-----......                                ............---.....................................--------------------.....................    438
Blackwater Reservoir, Merrimack River Basin, N. H.............................................                                                               57, 60
BlackwaterRiver, Fla.............------------------------------------------.................................................................................   448
Blackwater River, N. H .........-                                  ---...                                                                                           6.....................
                                                                                                                                                                    60
Blackwater River, Va...............------------------------.........................................................................-----------------........            288
Blackwell, Okla...........-----............-------..................................................--.............................                                      700
Blakely Mountain Reservoir, Ark......---.......................................................---------------............                                               530
Blanchard Channel, Los Angeles, Calif ......................................................................                                                            1268
Blind slough diking district, Clatsop County, Oreg ................................................                                                                     1475
Block Island, R. I.:
     Harbor of refuge-----..........................----.................                         . ...............................................                       53
     Great Salt Pond .........---.--------------............--------------...............................................                                                 53
Blood River, La .......................---.......-----...............................................................------....------.....--                             495
Blue Gum Canyon, Los Angeles, Calif ....................................................................                                                                1268
Blue Mountain Reservoir, Ark--                 .............................................................---......................-------------------------------     664
Blue River Dam, McKenzie Basin, Oreg ...........................................................                                                                1455,1476
Bluestone Reservoir, New River, W. Va..................................................................                                                              967,980
Bluewater Floodway, N. Mex.....----.............--..---.-----......................................................                                                      638
Bluff Creek, Miss......----.................-----.......---------............-----                                         ---....                                       448...............
                                                                                                                                                                         448
Boards:
     Beach Erosion ......................-----------................................................................. 1557
    Engineers for Rivers and Harbors-... ..................................                         --.                                                 ..........      1551
         International:
                 Kootenay Lake Board of Control ...................-.....................................                                                         1645
                 Lake Champlain Board of Control ...............................................                                                                  1641
1654                                                            INDEX

                                                                                                                                         Page
International :-Continued
          Lake of the Woods Board of Control--                                       ................--.....           .---------------------1644
          Lake Superior Board of Control.............................. ______1643
          Massena Board of Control....................                          ...               ............                               1643
          Niagara Board of Control------------------------------.......................................                                      1642
          Osoyoos Lake Board of Control................................-----------------------------                                         1646
          Prairie Portage Board of Control............................____                                                                   1645
          Rainy Lake Board of Control ...-------------.....................                             ..-----------------                  1645
          St. Croix River, Maine, and New Brunswick, Board of Control........-..                                                             1640
Bodcau Bayou, Red Chute, and Loggy Bayou, La-......-------... ---------..-...                                                  -- 497, 519
Bodcau Bayou Reservoir, La ......                                ........-----------------------------------                             497 ,503
Bodega Bay, Calif.....---------------------------------------------                                                                          1307
Boeuf and Tensas Rivers and Bayou Macon, Ark., and La_.......                                                      -..-.-..............      1582
Boeuf River, Ark., and La ............-.........................                                                               528, 530, 537
Bogalusa, La                                  --------------------------------------------------                                               446
Boggy Creek, Okla................----------------------------------------------                                                                701
Bogue Falia, La.................------------------------------------------------                                                               495
         Bay, Va-----------------
Bogues Bay,
Bogues         Va........................ ---------------------------                                       ----------------- 214              214
Bois de Sioux and Red Rivers, Minn. and N. Dak                                                          ................--------------------.......
                                                                                                                                         772, 782
Bois de Sioux River, S. Dak.....................                                                                                   ....-----------------------------
                                                                                                                                               771
Boise River, and Valley, Idaho..-__ --____---             ..                .
                                                                    . __1532,        .        .       .....          -           .           1535
Bolivar Peninsula, Tex------------------------------..-------------570
Bolivar Reservoir, Ohio ......                                                             .....------------------------------------------     960
Bonfouca Bayou, La...........               .........         ..--------------------------------------------                                   495
Bonnet Carre Spillway, La .                  ....      .....---------------------------------------..                                        1593
Bonneville, Oreg.:
     Construction of dam at                               ...
                                                ----.....---....               ------------------                       --------             1414
     Restoration of Indian Fishing Grounds_--                      ......... ___............_____                                            1418
Bonpas Creek, Ill-----------------------------------------------.                                                                              944
Bonum Creek, Va.................                   ----------------------------------------------                                              266
Bonneville Reservoir, Ky..-----------------------------------------                                                                            946
Boothbay Harbor, Maine.........                            .. .           .                 .       .
                                                                                    . .....................  ...........                         53
Boston Harbor, Mass....----------------------------                                                                                              19
Boswell Reservoir, Boggy Creek, Okla                                          --------------------------------                                 701
Bottle Run, Pa .....-----------------------------------------------                                                                            235
Boulder, Colo........................--------------------------------------------------                                                        845
Bowlers Wharf, Va......                     --------------------------------....------------- 258
                                                          -------..
Boyer River, east fork of, Iowa .........-----------------------------                                                                         845
Brackenridge, Pa ..............                   ----------------------------------------------                                             1024
Bradford, Pa ...-----------...........------------------------------------                                                                     998
Brady, Tex----........                            -----------------------------------------------
                                         ............                                                                                          625
Brandywine River, Wilmington Harbor, Del_..._______.--...............____                                                   .           .      168
Branford Harbor, Conn                  .-------------------------------------------                                                              53
Bransons Cove, Va ... ......                        ----------------------------------------------                                             258
Brazos Island Harbor, Tex.... .......                          ----------------------------------------                                        594
Brazos River, Tex.......-------------------------------------------                                                                      558, 601
     Whitney Reservoir                ..                 ------------------------------------------                                            618
Brea Dam, Calif                           -----------------------------                                 ------------- 1288, 1292
Breton Bay, Md                                  -----------------------------------------------                                               258
Brevoort levee, Indiana .........                                                 ----.--- ------------------...                              936
                   ------
Brewer, Me ................------------------------------------------------------------                                                            6
Bridgeport Harbor, Conn._____.__                                                                                                                  53
Bridges:
     Construction across navigable waters..----------------------------....                                                                  1639
     Rules governing opening of draws                                                                                                        1639
Brilliant, Ohio----...............           .... --------------------------------------------                                                1024
Broad Creek, Md----._...-------------------------......----------                                                                              218
Broad Creek River, Del....------------------------------------------                                                                           218
Broad Creek, Va............                       -----------------------------------------------                                              258
Broadkill River, Del........---------------------------------------------                                                                       190
Broad Sound Boston Harbor, Mass..............................                                  .....-----------------------------------    20, 21
Broadwater reek, Md ...........................-------------------------------------------                                                     218
Brockway, Pa .. -----------------........- -...---.......-.                                                                                 1024
                                                            INDEX                                                             1655
                                                                                                                                      Page
Brockway Reservoir, Connecticut River Basin, Vt ..                                                 .. ...                          69, 83
                                                                                                                       ....---------------------...
Bromley, Ky...--................-------------------------.....                                                                        944
Bronx River, N. Y...........                                                           .......                        ......------------------------------
                                                                                                                                      146
Brooklyn, W. Va................                                                                                         .....------------------------------
                                                                                                                                      978
Brookport, Ill..........---------------------                                     ... -------------------------                 944,947
Brookville Reservoir, Ind                                        ....-------------------------....--                                  946
Browns Creek, N. Y ..---------------------------------------------                                                                    146
Browns Landing, N. C                                              -------------------------------------------                         308
Brownsville, Ky..                           ------------------------------..                             ------------------           916
Brownsville, Tex.........-----------------------------------------------                                                              595
Brunswick Harbor, Ga                           .                   ------------------------------------------- 340
Brush Bayou, La-----.........------------------------------------------..                                                             511
Buchannan River, W. Va-----.....------------------------------------..                                                                996
Buckhorn Reservoir, Ky.....                                         ------------------------------------------..                      946
Bucksport Harbor, Maine ....                                            ---------------------------------------- 6, 53
Budd Inlet, Olympia Harbor, Wash ......... ---------------------------------                                                         1504
                  a , O h i o .... . _____. _ __.._ _. ____ __.
B u e n a V istBuena--Vista,-Ohio----------------------------------------------97    .__ .       .     .       ..            .        9 78
Buffalo Bayou, Tex...--------------------------------------------                                                                     599
Buffalo Creek, N. Dak                                             -------------------------------------------                         847
Buffalo Creek, W. Va., and Pa....------------------------------------                                                                1030
Buffalo, N. Y.:
       Engineer district .........---------------------------------------                                                           1185
       Improvement of Black Rock Channel and Tonawanda Harbor .......---------- 1211
        Improvement of harbor..............-------------------                                                 .                  - 1208
Buffalo River, Miss                   ........              .........---------------------------------------------                    541
Buffalo, Wyo......                  ................-------------------------------                                                   865
Buffumville Reservoir, Mass----------------------------------.....--...                                                            65, 83
Buford Dam, Ga....--------------------------------------------419,421
Buggs Island Reservoir, Va.*and N. C., flood control. See John H. Kerr Reservoir
Bull Shoals Reservoir, Ark--..------..----------------..........................-------------651,                                     655
Burbank eastern system, Los Angeles, Calif ..------------...----------..-----.......                                                 1268
Burbank western system (lower) Los Angeles, Calif                                                                                    1268
                                                                                                                      .......---------------------
Burbank western system (upper), Los Angeles, Calif ........ ....--------------------------.......                                    1268
Burgettstown Raccoon Creek, Pa                                    -..............                       ......
                                                                                             . -----------------------------------  1029
Burial Hill Reach, Conn..........                                     -----------------------------------------.                        53
Burlington Harbor, Vt-------------------------------..........------------123
        ng
B u rl iB  t o n , O  hi o  .   __.          __...
                                          .....     ..       ..
                                                       ........                             .
         rigo ,O i ---------------------------------------------------------------------------   .    .                    .9          77 8
Burns Dam and Reservoir, Calif..........                                      -----------------------------------                   1389
Burnsville Reservoir, W. Va..........---------------------------------------980
Burr Oak Reservoir, Ohio. See Tom Jenkins Reservoir
Butte Creek, Calif .................................---------------------------------------------                                    1570
Buttermilk Bay, Channel to Buzzards Bay, Mass--... .-.----------------.........                                                --- 53
Buttermilk Channel, N. Y                                ........    -------------------------------------.. ... 103,146
Butternut Creek, N. Y.....                              ...           ....                 .....                                      220
                                                                                                                     .......------------------------------
Buzzards Bay, Mass---------......                  ...                 ...                 .....                                        29
                                                                                                                     .....-------------------------------

                                                                  C
Caballero Creek, Los Angeles, Calif.......                                    .............             ..--------------
                                                                                                               ----            1268
Cache River, Ill......                                                                                                     546, 941
                                                                                                                   ..---------------------------------
Cache River Diversion, Ill ....                                                    .....
                                                                         -----------------                        ........        730
Cache Slough, Calif-----..........                                           ......                                 ....----------.
                                                                                             .....-----------------------------1568
Caddo River, Ark--..---.........                                      ......           .........                                532
                                                                                                                 ........-----------------------------
Caddoa (John Martin) Reservoir, Colo---........-------..                           .............                                630
                                                                                                                 ........---------------------
Cadle Creek, Md.....         .........                               ...                                                        218
                                                                                   ...........................-------------------------------------
Caesar Creek Reservoir, Ohio....                      .........--------........................
                                                                       ------------------------------.                           946
Cagles Mill Reservoir, Ind .....---                   .......--------------.......
                                                            -.-..-..-........-----------------------.                    -937,946
Cahaba River, Ala...................                                                                    ...........---------------------------------
                                                                                                                                448
Cajon Creek, Santa Ana River Basin, Calif .....................-------------                                                   1288
Calapooya River, Oreg-                                                                                                 1455, 1472
Calaveras River, Calif ..............................                                                                          1377
Calcasieu Pass and River, La ...............                                                                      ......------------------------------
                                                                                                                                490
    Lock-----    ...................                                                                ............ 4--------------------
1656                                                    INDEX
                                                                                                                  Page
Caledonia, N. Y...........................................................----
California Debris Commission----.......................................---.....                                                     1561
California, Ohio-----
                ...............................................................                                                      944
Calion Lake Dam, Ark................................................----------                                               5, 529, 535
Caloosahatchee River Fla-__....................................................                           ...............       378, 384
Calumet Harbor and River, Ill. and Ind., improvement of harbor (South
  Chicago Harbor) .......-------...............................................                                                     1122
Calumet Lake, 111------.......---------------------------------                                                                     1140
Calum et Sag Channel Ill ....................................................              .....-...          ...  ...... 1132
                                                                                                                             ....
Camas Creek Area, Idaho-------....                                                   -----------............
                                             -------....-----...........................                        ----------          1532
Camas-Washougal Turning Basin, Wash----.....                           ---------......
                                                                                     .......                                        1420
                                                                                                              ..........----------------
Cambridge Creek, Md....-------------------------------------------                                                                   203
Cambridge Harbor, Md --......................---------..................          ..---------..                                      203
Cambridgeport Reservoir, Connecticut River Basin, Vt--...................--                                ------------- 69, 83
Camden Harbor, Maine.......................-------------------------------------------                                                 53
Canacadea Creek, N. Y-----.. .           ...          ----------------------------------                                        221, 227
Canadian River, N. Mex., Tex., and Okla......--------------------------                                                         632,700
Canal Point, Fla....-----------------------------------------------                                                                  404
Canapitsit Channel, Mass..-----..-----------------------------------                                                                   53
Canasawacta Creek, N. Y-...----------.                      --.---------------------                                                 240
Canaveral Harbor, Fla......------------------------------------------                                                                363
Cane River, La......-----.....................................----------------                                          495, 517, 520
Caney Creek, Okla. and Kans .----.                       --------------------------------------                                      700
Caney River, Okla.....----------------------------------------------                                                                 686
Caney Fork River, Tenn--.......       .              ..................------------------------------                ---..... 894,   904
Canisteo River, N. Y..............................-------------------------------------                                 221,225,     226
Cannelton, Ind.....----------------..............................     ---------------------... 932, 944
Canton, Mo., Mississippi River ......                       -------------------------------------                                    756
Canton Reservoir, Okla....------------------------------------------677
Canyon Reservoir, Guadalupe River, Tex ....... -----------------------------                                                         624
Cape Charles City Harbor, Va                     --------------------.                              -----------------                288
Cape Cod Bay and Canal, Mass-----------------------------------..                                                                -- 28
Cape Fear River, N. C.....                       ------------------------------------------- 299
     Improvement above Wilmington                                  ----------------------------.----.                                308
Cape Girardeau, Ill. and Mo.....---------------------------------------                                                              710
Cape Lookout, N. C., harbor of refuge..---------------..-------.                                                                  .313
Cape May Canal, N. J---_--- -                                 --.- -----..-..--.--....... 187
Cape May Harbor, Cold Spring Inlet, N. J                                  -----------------------...-----.                           178
Cape Porpoise Harbor, M aine ..-............................                    ___.                                            .      12
Cape Vincent Harbor, N. Y.....                     .. ------------------------------------- 1227
Carbon Canyon Dam and Channel, Santa Ana River Basin, Calif.............                                                     1288, 1293
Cardens Bottom drainage district No. 2, Arkansas River, Ark......-----------------.                                .                 668
Carlin Bayou, La ..                  ....        .............--------------------                                495
Carlyle Reservoir, Ill----------
                           ...................          --------........--------------------------                            27
Carpenter Dam, Ark-----..........................              .....               ..----------------------....               30
Carpenters Creek, Pa------...............................              ......---------------------------------              234
Carrabelle Bar, Harbor, and River, Fla........ ....---------------------------                                        415,448
Carroll County levee and Drainage District No. 1, I11l---------_....-- ------------                                  ..     756
Carrollton, Ky.............................................---------------------------------------------913,944
Carters Creek, Va.----------------------------------------------                                                            258
Carthage, Mo ....-------------------------------------------------.                                                         688
Carthage Dam and Reservoir, Tenn...                                ---.-----.......
                                                                       ..--------.....                                      883
Carvers Harbor, Maine-------------------------------------------                                                             53
Cascadia Dam, South Santiam River, Oreg-------..........----------------                                            1455, 1476
Cascades Canal, Oreg....-------------------------------------------                                                        1452
Casco Bay, Me.....------------....-...                                                     ---------------------              10
Caseys Pass, Fla....----------------------------------------------                                                          384
Caseyville, Ky-----------------------------------------.--------                                                            944
Cashie River, N. C.........................................--------------------                                             313
Casselton, N. D........................................................--------
Castle Rock, Cowlitz River, Wash-------...-.......            ------.....-....          ...---------------------..
                                                                                                  ..-                      1476
Castlewood Reservoir, Colo.....................................                  ..                                         845
                                                                                               ..----------------------------------------
Cat River, Va.................................................................                                              214
Catfish Point, La ......................................       ...............    ......      ...                  .... 515
                                                                                                               ......
                                                                           INDEX                                                                            1657
                                                                                                                                                                Page
Cathance River, Maine-----...--------------------------------....................................................................................                           53
Catharine Creek, N. Y .-------.........................................---------------------------.........................................--                            1233
Cathlamet Channel, Oreg                     ......................................................................-----------------------------------..............      1429
Catlettsburg, Ky.....................................................................................------------------------------------------                            978
Cattaraugus Creek, N. Y ....................................................................----------------------------------------                                     1227
Cavallo Pass, Tex., improvement of channel to Port Lavaca_. ............... ___                                                                                      -.. 587
Cave-in-Rock, Ill.............---------------.......................................................--------------------------------                                       944
Cave Run Reservoir, Ky-----            ....................................                                                 ...... ....             ..                     946
                                                                                                                                                                ..------------------------------
Cayuga Creek, and Island, N. Y.............------------.........                                                                .........           ..                   1228
                                                                                                                                                                ..---------------------
Cedar Bayou, Tex., improvement........                                                       -----------------------------------                                           579
Cedar Bay to Thoroughfare Bay, N. C., improvement... ...-..........-..-..                                                                                                  313
Cedar Hill, Mo.................               ..          ......................                                         ...........                                       729
                                                                                                                                                   ..-------------------------------------
Cedar Island, Me., N. H------..                           ........ ............ ................----------------------------------                                      14,  15
Cedar Keys Harbor, Fla                            . .....                      ............                       ... ..........------------------------------------------ 401
Cedar Point Reservoir, h'ans---......--------............                                                         ... ..........---------------------------                700
Cedar River Harbor, Mich................                                                                          ... ........
                                                                                ---------------------------------------                                                   1113
Celilo Falls, Oreg...................                                                                                                                                    1408
                                                                                                                  ... ..........----------------------------------------------
Celina Dam and Reservoir, Tenn....-----------------------------------.....                                        ................                                         883
Center Hill Reservoir, Tenn                                                                __.
                                                                                             ...            .........__-.__.__--                             ------ 904
                                                                                                                                                       ---.......-
Centinela Creek, Los Angeles, Calif....                                                     .....                       ................
                                                                                              ---------------------------------                                          1268
Central and Southern, Fla...                                            .                            .....                                                                 402
                                                                                                                        ................----------------------------------------
Central City Reservoir, Iowa .....                                                                      .                  .......                                         756
                                                                                                                                           ...--------------------------------------
Ceredo-Kenova, W. Va....................---------------------------------------                                                                                     978,981
Chain of Rocks, Ill                   -------...........................-----------------------------------                                                         708, 730
Chanbersburg, Ohio                 ..                  .............                        ..................--------------------------------------------                 978
Chamita Dam and Reservoir, Rio Chama, N. Mex- -........                                                               __... __     ..... __.__.... ..                      633
Champlain Lake, N. Y. and Vt., channel between North and South Hero
  Islands, navigation                   ----------------------.........................                 ---.......        ...........        ...                           146
                                                                                                                                                                ..----------------------
     International Board of Control__-.....                                       ... .. __---__                     ......-        .................... 1641
Chandlerville, Ill., east of ...................--------------------.......          ........                              ..................                            1148
                                                                                                                                                                ..--------------------
Channel between North and South Hero Islands, Lake Champlain, Vt...--------....                                                                                            146
Channel from Buzzards Bay to Buttermilk Bay, Mass                                                                           ...............                                 29
                                                                                                                                                         ...---------------------
Channel from Pamlico Sound to Avon, N. C                                                                                        .......
                                                                                                                 ..................                           ......       305
Channel from Pass Cavallo to Port Lavaca __--. ___.__--                                                     __..--........ _____..       .               ...               587
Channel to Port Bolivar, Tex.......--------------------------------------.....                                                                                             570
Chariton River, Iowa and Mo...........                                                                                                                                     817
                                                                                                                                                         ...---------------------------------
Charles Mill Reservoir, Ohio--                                        -                    .......-.-..-----....
                                                                                                          ..____...                -.-...         .........-               960
Charleston, Oreg-....---------..-............ .                   . . . ..---------------------                                .-....-- ---.. --.......       -----... 1448
Charleston, S. C.:
     Engineering district                                                            .........------------------------------------------                                   315
     Improvement of harbor                                      .....                    ........                                                                          319
                                                                                                                           ...........---------------------------------------
Charlevoix Harbor, Mich----------...............................------------------------------                                                                           1111
Charlin Bayou, La................................................----------------------------------------------495
Charlotte Creek, N. Y...-------------------------------------------                                                                                                        220
Charlotte Harbor, Fla-----.............--------------------------------------                                                                                              387
Charlotte (Rochester) Harbor, N. Y---- ---................................. ..                                                                                           1219
Chatfield Reservoir, Colo....____.......-..                                              ..... .....................                           .841,845
Chatham (Stage) Harbor, Mass----                     ....                    .....                 .................--------------------------                              53
Chattahoochee River, Ga. and Ala                                                          ............----------------------------------                                   419
Chattanooga, Tenn., and Rossville, Ga                                                           ................------------------..                                       908
Chatooga Reservoir, Ga. and S. C_-----                                                       -
                                                                                         ..............--.....                                                             341
Chauncey Run, N. Y                    ----------------...---------------------------- 241
Cheat River, W. Va                   ------------------......--------------------------- 996
Cheatham Lock and Dam, Tenn .............................------------------------------------                                                                              881
Cheboygan Harbor and River, Mich........                                                                                                                                 1178
                                                                                                                             .................--------------------------------
Cheesequake Creek, N. J ...............................----------------------------------------                                                                            146
Chefuncte River, La                                                                  -------------------                                                        495
Chehalis River, Wash...                                                                                                     1506
                                                                                          .........-------------------------------------------
Chelsea Creek (Boston Harbor), Mass .....                               ...............--------------------------------       21
Chelsea River (Boston Harbor), Mass                             ..................------------------------------           20,21
Chemung River, N. Y.....-------------...  ........            --------------......                     -----........    ..   223
Chena Slough, Alaska                        ------------------------------------------.                                     1549
Chenango River, N. Y....-- ..............................--------------------------------------                         221,241
Chequamegon Bay, Wisconsin          ...........                  ...........................         ... .. 1040
Cherry Creek Dam and Reservoir, Colo ....               ........       ............................       840,845
Cherry Valley Reservoir, Calif ...-..-..................................................            .1384
1658                                                                 INDEX
                                                                                                                        Page
Chesapeake and Delaware Canal----.....................................................................-----
Chesapeake, Ohio-----.......------------------------.................................................
Cheshire, Ohio.............................. ............................................................................----------------------
Chester, Ill........................----------------------------------............................................
Chester River, MdPa ........................................................                                           19-------------------
Chester River, Pa             ..................................... ................................... --------------------
Cheswick, Pa----------------            -   ----------------------

Chetco River, Oreg.....--------.........................................................................---------
Cheyenne River, S. Dak. and Wyo---             - .. --.......----..-......----.. ... ...------------------
Chicago Harbor and River:
    Improvement of harbor.................-----------------------....----....------................... .....
      Improvement of river                     .................. ............... ............ ......... ... ...                   1120
Chicago, Ill., engineering district-..........-------------.... .......... ---------................ ... ...
Chicago Sanitary and Ship Canal_ ......................... __............. ........ .... ... 1133
Chickamauga, Tenn....................................................................------------------------------
Chickasawhay River, Miss .....-------------.....---.........................................----------------
Chickasaw Creek, Ala ..............................................                      ...-                                   428
Chico Landing, Calif                               --------------------------------------------                      1350
Chicopee, Connecticut River Basin, Mass--------- .                                  -------..........----.. .. -------------- 7
Chicopee River, Mass.....--------------------------------------------                                                                  8
Chief Joseph Dam, Wash--........... ............. ......----........-------------------------------
Chillicothe Reservoir, Mo                 -------...----------------------------------                                       797
Chilo, Ohio........................---------------------------............ .. .. ...... ...-----------------------
Chincoteague Inlet and Bay, Va............                                ......         ...-------------------------------        213,21
     Waterway to Delaware Bay, navigation-....................                        ... .       ..---------------------------
Chino Creek, Calif ------------------------------------------------------------------ 1287, 1288
Chinook, Wash., and the Head of Sand Island_ ....... __-.......-...__ .                                         ... 1434
Chippewa Harbor, Isle Royale, Mich                                   .. --------------------------------            1050
Chippewa River, Wis. and Minn....                                        ------------------------------------            786
Chisholm Creek, Kans .................................. . ..............-------------------------------------------
Chittenango Creek and tributaries, New York .......--------.-..............                                   -........ ___ 1236
Chitto Bogue, La ......              ..............................-----------------------------------------------
Chocolate Bayou, Tex.............-----------------....................-------------------------- 583
Choctawahatchee Bay and River, Fla. and Ala --.................... .--                                    4-- --------- 4..- 14, 426,
Choptank River, Md...............--------------------......----------..                          .............. ...-----------.. 203
Choteau, Mont-----..... ..------------....-----------------------....                                                                  86
Choupique Bayou, La .........................................----------------------------------------
Chouteau, Nameoki, and Venice drainage and levee district, Illinois-.................. 725
                     V a . a n d N . C _ . . . . . . . . .......... ....
C h owa n Rive r , Chowan--River,-Va.--and-N.-C--------------------------------------1                                3 13
Christiansted Harbor, St. Croix, V. I..........------------------------------401
Christina River, Del.........................---------------------------------------------                            168
Cincinnati, Ohio ..........................-------------------------------------------- 922,944
City Waterway, Tacoma Harbor, Wash ....-.-                                        --.------.            . ...          1502
Clackamas River, Oreg                                                 --       -------------------------            1472
Claiborne Harbor, Md               ...........................-------------------------------------------
                                  reg



Claiborne Lock and Dam, Ala.....------------........-------------------------                                              433
Clam Creek, N. J              ........................ ..----------------------------------------------- 180
Claremont Reservoir, Connecticut River Basin, N. H                                                                    6.__..........__
Clarendon to Laconia Circle, Ark ....                   ................................--------------------------------
Clarington, Ohio....         ....------------------..--.................. ......-------------------------- 97
Clarion River Reservoir, Pa.                                       . -------------------------------------- 1000
Clark Creek, S. C-_...-..
Clark Hill Reservoir, Ga. and S. C .-...-......................                                                   341,343
Clarksville, Ark ................-----------------------........... ...... ...... ---------------------                                 668
Clarksville, Ind...     .         .   --.------------------------------------                                                             926
Clatskanie Drainage Dist., Oreg---....----------...-----.... ... ------- ---------- 1473
Clatskanie River, Oreg .....---.................--------------------------------------- 1452
Clatsop County Diking Dists. Nos. 1 and 4, Oreg .....                     -----------------------...  1473
Clear Creek Drainage District, Ill....................................709,                           712
Clear Creek and Lake, Tex............-                                              --.....................                  581
Clear Lake, Ill.......................................................----------------------------------
Clearwater Reservoir, Mo.............................................            .....------------------------------
Clearwater River, Idaho, South Fork of ........             ------------------------------        1532
Clearwater River, Minn--------------------------------...                          .-.        771,775
Clendening Reservoir, Ohio- ........-..........              __ ................. ... ......... 960
Cleveland Harbor, Ohio.........                 ............. ......       ...     ....... 1191, 1236
                                                                  INDEX                                                                 1659
                                                                                                                                            Page
Cleves, Ohio................................................................................                                                        944----------------
                                                                                                                                                    944
Clewiston, Fla ......                                 ----------------------------------------------...                                       380,404
Clifton, W. Va-----   ...--------------------------------------------                                                                               978
Clinch River, Tenn. and Va...........................................---------------------------.......................--------                     894
Clinton Harbor, Conn................................................
                                                                   --------------------------            ....    -------------....
                                                                                                                    ...                              53
Clinton, Ind....--------------------------------------------------                                                                                  944
Clinton, Iowa, Pool No. 14                                 ---------------------.......---              -------...-----------                       737
Clinton, Pa---------------------------------------------...................................................................985..                    985
Clinton River, Mich..............................----------------------------..-------................1178, 1180
Clintwood Reservoir, Va------...... --------........              ............-----...........---                   ------------------              980
Clooney Island, La..----------------------------------------------                                                                                  490
Cloverport, Ky .......................----------------------------------...........-------------                                                    944
Clyde Pawtucket River Basin, R. I                                        -------....---------------------------.                                     83
Coal Creek Drainage and Levee District, Ill-----------------~~.~.-----.......                                              .           . .         1143
Coal Grove, Ohio ..-----------------------------------------------                                                                                  978
Coan River, Va--------------------------------------------..-                                                                                       258
Coasters Harbor Island, R. I....---------------------------------------                                                                              53
Cobscook Bay, Maine                                                 --------------------------------------------                                     53
Cocheco River, N. H ... -------..---..........................-----------------------------------                                                    53
Cochrane, Wis.                             .             -------------------------------------------------                                          736
Cockfield Levee, La                          ..                 ---------------------------------------------                                       520
Cockrell Creek, Va258----------------------------------------------258
Coden Bayou, Ala                                              ----------------------------------------------                                        448
Codorus Creek, Pa                                               ----------------------------------------------                                      238
Coeur D'Alene, Idaho-----..                              --                 --------------------------------------                                 1523
Cohansey River, N. J .                              .---...--.---..-----------------------                                                          190
Cohasset Harbor, Mass....--------. -----.---                                                               -      -------------------                53
Cohocton River, N. Y-.......------------------------------                                                                                          224
Cold Brook Reservoir, S. Dak.......................-------------------------------------                                                            830
Cold Spring Inlet, N. J .-------------------------------------------                                                                                178
Coldwater River, Miss ..........------------------------.................-------------------                                                        528
Colfax, La........                              ...........................------------------------------------------------ 497,519
Colfax, Wash--------------------...                  ............---------------------------                                                      1540
College Hill, Ky..                  ..                      ------------------------------------------------ 913
                                                     .............
Collinsville, Ala                      .......                    ........------------------------------------------------                          452
Collinsville to Shasta Dam, Calif .--..                                          --...--....-.-........... __                                      1370
Colonial Beach, Va .................                              ........-------------------------------------                                     258
Colorado River, Tex. and Ariz. and Colorado.-.                                                        -..-.--............ __
                                                                                                    ___..                                           560
Colorado Springs, Fountaine que Bouille River, Colo ............----------------------                                                              638
Columbia Drainage Dist. No. 1, Oreg-----------...---_____......______.                                                                             1473
Columbia drainage and levee district No. 3, Illinois ___................._____                                                             ___.. 722
Columbia, La.......................                              ...---------------------------------...                                       530, 538
Columbia Lock and Dam, Ala-----........                                          -----------------------.....                                       419
Columbia River, Oreg. and Wash.:
     At Baker Bay, Wash.....                                      ---------------------------------                                                1435
     Below Vancouver, Wash. and Portland, Oreg                                                                                                     1427
     Between Chinook, Wash, and the Head of Sand Island....__._____.____..                                                  ..          .          1434
     Bonneville, Oreg., construction of dam at..............                                                                                       1414
     Bridges at Cascade locks ......----..--.-..-.                      .          .            .             .          .         .       -       1452
     C ascades C anal .......... ... . ......................................... .                                        _--            .         1452
     Celilo Falls to Kennewick, Wash                                                                                                              1408
     Chief Joseph Dam, Wash .............--                                                                                                        1492
     Dalles Dam..............---------------------------                                                              --             -------      1410
     Local flood protection                          -               -.........            ....                                - -          1523, 1532
     M cN ary D am ......-..... . .. . .. . .. . .. . .. . .------                                                                                1529
     Mouth improvement--------------------....                                                                  ---                               1437
     Vancouver to The Dalles, Oreg ..........                                               -            -             -          -               1419
     Wenatchee to Kettle Falls, Wash...............                                              -------------------                              1514
Columbia Slough, Oreg.....-----------------------------------------. 1452
Colusa, Calif....                                                                                                                                 1350
Commercial Point, Dorchester Bay and Neponset River, Mass ...-...............                                                                        23
Compo Beach, Westport, Conn ..-----------.......                              __........                                                     _       53
Compton Creek, Los Angeles River Basin-..-.--.- -                                                         .1268
                                                                                                          -------....
Compton Creek, N. J...................................-----------------.........146
Conchas Dam and Reservoir, N. Mex..-..........................______         .. _ 632
                                                                           .__..
 1660                                                           INDEX

                                                                                                                                        Page
Concordia, Ky ... .......................                                                                               . ...              944
Conecuh River, Ala ..............---------------------------------------------                                                             448
Conejos River, Colo ...............---------------------------------------------- 639
Conemaugh River Reservoir, Pa                               .......... ------------------------------- 1010,1025
Coney Island Channel, N. Y                                .......---------------------------------------                                    102
Coney Island Creek, N. Y.....----------------------------------------                                                                      146
Congaree River, S. C-----------.          -.            . ---------
                                                       ~._..   .....-.-....                                                         -      326
Congresses of Navigation, Permanent International Association of                                                                         1.631
Conneaut Harbor, Ohio----.....                    ....-----------------------..                                                          1200
Connecticut River Basin, Vt., N. H., Mass., Conn.....................                                                                        67
Connecticut River, Mass. and Conn............----------------------------------.....                                                         81
     Above Hartford, Conn .......-------      ---                                            ------                                          53
     Below Hartford, Conn-----------------------------------------                                                                           44
Consolidated diking and improvement district No. 1, Cowlitz County,
   Wash...................................                                                                                               1475
                                                                                                                                  1-----------------------------
Contentnea Creek, N. C......                                ---------------------------------...--------                                   313
Contoocook River, N. H............                                   ------------------------------------                                    59
Conway County levee district No. 6, Arkansas River, Ark..........----------------------                                                    668
Conway County levee districts Nos. 1, 2, and 8, Arkansas River, Ark __..______                                                             668
Cooper River, N. J...........................----------------------------------------------                                                176
Cooper River, S. C..-----...                  ---------------...---------.-..                                                       319,324
Coosa River, Ga. and Ala--....------------------------------------432
Coosaw River, S. C..                     ---------------------............---------------------                                            316
Coosawatte River, Ga............                             -------------------------------------------                                   448
Coos Bay, Harbor, and River, Oreg.:
     Improvement of entrance to bay and harbor ..........-----------------------                                                         1447
     Improvement of river............---------------------------1452
Copes Corner Reservoir, N. Y .-..........------                                                          --------------------              220
                                     -------------------...
Coquille River, Oreg. .........-------....                                              -.
                                                                                         .        ...---------------------... 1450, 1476
Coralville Reservoir, Iowa-----------------.....-....                                                                    __........        754
Coraopolis, Pa.........................             ------------------------------------------------ 1024
Cordova Harbor, Alaska-----...----------------------..--------------1547
Corea Harbor, Maine, navigation..........
Corney, La ...........          -......
                                                                        -.. . .                                                               4
                                                                                                                             ....-------------------------------
                                                                                                                                           528
Corning, N. Y------........--------------------------..
                                            ....---------------                                                                            224
Cornucopia Harbor, Wis......................... ........                                                                                 1038
Corpus Christi, Tex.:
     Channel to Encinal Peninsula naval seaplane base.....-......                                             ..          ..               601
     Improvement of channel to Aransas Pass                                        -------------..----.
                                                                                         ..            .         ........                  589
Corsica River, Md--------------..........                       ---------.........
                                                                                 ........---------------                                   218
Cosmopolis, Wash..............                      ...........                                                                  ----- 1507
                                                                                .........-----------------------------------------
Cottage Grove Reservoir, Oreg...-------..                                      .......-----------------------
                                                                           ------......                                                  1461
Cottonwood Springs Reservoir, S. Dak.....                                       .........------------------------------                    829
Cougar Dam, Oreg-.........                              .-----------                               -------------------                   1465
Council Bluffs, Iowa-. .-..---------.                                                       ---------------------                   843, 845
Council Grove Reservoir, Kans....--------......................-----------------------------                                               700
Courtenay, Fla., channel improvement-----..                               ............--------------------------                           401
Covington, Ky....----------------------------------------------                                                                       20, 944
Cow Bayou, Tex..                   ---------------------...-----------------------                                                         552
Cow Creek, Kans-.....672
Cowlitz County drainage improvement districts Nos. 1, 2, 5, 11, 13 and 15
   Washington ...------------------------------------                                                                            1473, 1476
Cowlitz, River, Wash-.....-----...-.....-------------------1429,                                                                         1432
Coyote Creek, Calif ...........                                      ............................                                        1268
Coyote Valley Reservoir, Calif ...........                               ..............------------------------------------..            1341
Craig Harbor, Alaska....                   ..              -------------------------------------------                                   1547
Crane Brook, N. Y                      --------....
                                             ............              -------------------------------------                             1236
Crane Creek, Ill.....-----------------------------------------------1148
Cranes Creek, Va.......------------..---------------------------------                                                                     258
Craven Shoal, New York Harbor, N. Y., improvement..............                                                                            125
Crawford County levee district, Arkansas River, Ark ......                                                                                 6.......---------------
                                                                                                                                           660
Creede, Willow Creek, Colo                       ...........----------------------------------------                                       638
Crescent City Harbor, Calif..                                   ....                                                                       301
                                                                                                                                         1---------------------
C riehaven H arbor, M aine...... .... ... .... .... ... .... .... ... .... .                                                                 53
Crisfield Harbor, Md-...... -    --.- --.-....-................                                                                        218
Crooked Creek Reservoir, Pa ........ ............--...-.                                     .........--..-.                          1007
                                                                  INDEX                                                                    1661
                                                                                                                                              Page
Crooked Creek, Tenn--...                          ......                  ................------------------------------------------                548
Crosby Creek, N. Y....---------------------------------------------                                                                                 227
Crosbys Narrows, Me............................................................................................                                        6----------------
Cross-Florida, Waterway, Fla-------------------...................................---...............................                                401
                                                                                                                                       ....------------------------------
Cross Rip Shoals, Mass--------------------------
                                           ................................................................---..------------..                       33
Crow River, Minn .....-----.--------------------------------......................................................................                  789
Crystal River, Fla ......................----...........-------------------------------...........................---------...                      401
Cubits Gap, La..---------------------------------..-----..---------                                                                                 475
Cuivre River, Mo ....-----------------------------------------------                                                                                709
Cumberland, Ky.........----------..---------------------................................          .............         ... ..            ...       908
Cumberland, Md.. -------------................................                  ----............................. .....-----------------            260
Cumberland City, Tenn.....--------------------- ----------------------- 881
Cumberland River, Ky., and Tenn.........................                                               ..---------------------------          879, 895
    Locks....................................................................----------------------------------------------             ------ 880
Cunningham Creek, Ohio.............................................---------------------------------------                                        1227
Current River, Ark., and Mo....................................                      --------------------------------------                         650
Curtis Creek, Md-----......-................-........................-.----------------------------------------                                     195
Cutler Dam, N. Y.....----------------------------------------------                                                                                 222
Cuttyhunk Harbor, Mass ..----------.....................................                                         ..--------------------              33
Cuyahoga River, Ohio.................................................                                                                             1194
                                                                                                               ..------------------------------------------
Cypress Bayou and waterway between Shreveport, La., and Jefferson, Tex ... 495, 503
Cypress Creek, Md......                                                        .....
                                                                              ------------------------------------------                            218

                                                                        D

Dalecarlia Reservoir, Washington, D. C .............                                                                                 252
Dale Hollow Reservoir, Tenn, and Ky.-.                                ___-------
                                                                   -.....                       --------...- _                       901
Dallas Floodway, Tex....................................------------------------------------------                                   614
Dalles-Celilo Canal, Oregon and Wash., improvement- ..... .. ............                                                           1412
Dalles Dam, Oregon------................................--------------------------------------                                      1410
Dam A Reservoir, Neches River, Tex_- .........__-__--______--                                                          ----..        607
Dam B Reservoir, Neches River, Tex.......__.                                       ___            _  ----------------------          606
Damariscotta River, Maine-----.............                     ------------------------.....-----------                              53
Dansville and vicinity, Genesee River, N. Y ..........---------------------------                                                   1232
Danville, Ark-----------------------------------..---------------665
D'Arbonne Bayou, La----------.................                 ----.....-----------------------                                      528
Dardanelle, Ark-----...................................---------------------------------------                                       668
Dardanelle Dam and Reservoir, Ark .. ___....-...............___...                                                                   645
Darien River and Harbor, Ga........-------------------------------------340
Dark Head Creek, Md..-------------------------------------------.                                                                    218
Dauphin Island Bay, Ala .....                                 ----------------------------------------- 448
Davenport Center Reservoir, N. Y......                                  ----------------------------------                           220
Davenport, Iowa, Harbor ...                     ------------------------ _______..                     -         -...                737
Davis Creek, Va....              .............------------------------------------                                                   288
Davis Lock, St. Marys River, Mich....................                                 .         .        .             .            1153
Day Creek, Tex. andArk..---------------------------------                                                                        516,517
Dayton, Ky.....-----------------------------------------------                                                                       944
Dayton, Touchet River, Wash.----.._                          -      __- .-     --.......
                                                                                 ...           ..                         -         1540
Dayton, Wyo ......................... ...........                                                                                    865
Dead Horse Canyon and Royal Boulevard Channel, Los Angeles, Calif                                                                   1268
Deadman's Creek, Calif_....                       .                ....... .........                  ....                ..        1388
Deal Island, Md.:
     Lower Thoroughfare __..           .                                                                        ......        ....   218
     Upper Thoroughfare........                            ------------------------------                                            218
Debris control, Sacramento, Calif-......                                                                                            1565
Debs Inlet, N. Y             -----------------------..........-.                 .................-------------------------           98
Deep Bayou, Ark. and La..----------------------------------------                                                                    529
Deep Creek, Va..-----------.....           --............
                                      ........................                                                               . 285,288
                                                                                                           ....---------------------
Deep River, Wash ...........----------...               ...          ---------------                    ----                1452, 1475
Deer Creek Prairie levee unit, Indiana. -------                     ___-------._         ~.....                                      944
Deer Creek Reservoir, Ohio...................                                              ..-...........-                           980
Deer Island area, Columbia County, Oreg............-----------------.                                            1428, 1473, 1475
Deer Island Thoroughfare; Maine.................. .-...-....-------------------------------                                           53
                                                                       ..
Degognia and Fountain Bluff Levee and Drainage District, Ill-...-.-...-..                                                             ..      716
De Gray Reservoir, Ark.-...5................2........                                                                                 529, 532
 1662                                                                          INDEX

                                                                                                                                                        Page
Delaware Bay and River, Pa., N. J., and Del.:
    At Camden----......--------------      ---------------------------------------------------                 164
    Delaware River at Delaware City, Del ....__________.                  __ _____..             ..........    171
    At or near mouth of Neversink River- ___________________________......
                                                                      -                            ..
                                                                                                 ___           190
    Philadelphia to sea                   ----------------------------------...------..--------                160
    Philadelphia to Trenton-......                         -      -        -      -       -    -      -        157
Delaware Reservoir, Ohio....                  ..........------------------------------------------        974, 980
Delaware River, Kansas, Mouth of .__. ___._._.                  ._______.               ._                     821
Delphi, Ind ............... ..        -944,                                                                    947
Demopolis Lock and Dam, Ala                                    -...........           .        .                  ...                                438,439
Denison, Iowa---........-------------                                                                                                                    845
Denison Reservoir, Tex. and Okla --...-----------                                                                                                       696
         C reek, N . J_. _._.._._..... . .        .    ..               .      .
D enn is Dennis---Creek,---N.-J-------------------------------------------------_---                                                                    19 0
                                                                                                                                                        19
Denton Creek, Tex......-                                    -     -       -    -                                                                        612
Denver, Colo ..........                ..        ..-..-..                                                                                                846
De Peve, Wis ...-.-----                                                         -------------------                                                     1060
De Poe Bay, Oreg ------                                                                                                                                 1441
Derby, Ind---.........                                                                                                                                   944
des Cyprairres Bayou, La ...    ____..______516,                                                                                                        517
Des Moines River, Iowa...........                                                                                                                       756
                                      - - --
                           -.- __-________-
Des Plaines River, Ill_ ____._____-                                                                                           -           -     -      1130
Detroit, Mich., engineering district ......-.-.                                           .               ..      -      .- __--- .   -   ..-   -.     1151
Detroit Reservoir, Oreg --...-.........                                                                                                                 1467
Detroit River, Mich.....--------------------------------------------------                                                                              1161
Devil Creek, Calif- ..__-___--..-.. .        .
                                             __    .                                          ...                                                     1294
Dewey Reservoir, Ky.---.            ---......-------------                                                                                      - 971, 980
Dexter Reregulating Dam, Oreg..                 .   .        .         .              ..           .       .                                           1459
Dickinson Bayou, Tex                                                ..........                 ........                                                 582
Diking and improvement district No. 4, Wahkiakum County, Wash .....                                 ----------                                         1475
Diking and improvement district No. 5, Cowlitz County, Wash ...........                      --------------                                            1475
Diking district No. 2, Clatsop County, Oreg ...... ................-...                                                                                1475
Diking district No. 3, Clatsop County, Oregw...... ..........- ....                                                                                    1476
Diking district No. 5, Clatsop County, Oreg--         .................--.._______......__ -                     -.                                    1475
Diking districts Nos. 1 and 3 (Puget Island) and Little Island Wahkiakum
  County, W ash- .. . -. . . -. . . -. . . . - . . .- . . . . . . . . . .                                                                              1475
Diking improvement district No. 2, Cowlitz County, Wash . .-----------------....                                                                       1476
Diking improvement district No. 13, Cowlitz County, Wash...... _______..                                .                                              1476
Diking improvement district No. 1, Pacific County, Wash------..-------......                                                                           1475
Diking improvement district No. 11, Cowlitz County, Wash...___.._..                                                                                    1476
Dillon Reservoir, Ohio .__..__-____-___-          .
                                        . . .__962,        ... --...                                                                                    980
Dillonvale, Ohio ...........     ......... . ..                     ...... .. ...... ..                                                                1024
Dismal Swamp Canal, Va ..............                                                                                                                   284
District of Columbia:
     Anacostia Park ..       .........                                    ....----------------------------------                                        258
     Anacostia River, reclamation of flats .               ....
                                                             ---------------------------
                                                                      ......                                                                            258
     Aqueduct, increasing water supply.                       -----------------------------------                                                       252
       Improvement of Potomac River .....-.                                                    _...                                                     243
Doboy Sound, Ga..----------------------------------------------------330
Dock Hill Brook, N. Y
Dodge Creek, N. Y------
                    .........
                              -.-----------------....                  155
                                                                       996..........----------
                                                                       996
Dog River, Miss .----.......-----------------                          448
Donovan levee, Illinois .                              -............------------                                                                       1148
Don Pedro Reservoir, New Calif                                ....                                   1384
Dorcheat Bayou, La.--------------------------------------------------                                 495
Dorchester Bay and Neponset River, Mass .....                       ..-----------..---------------..   23
Dorena Reservoir, Oreg.----.-..-..................                                                   1462
Double Bayou, Tex..-           -           -       --..--...-      . -         .         .-.          575
Double Creek, N. J          -----------------------------------------                     ---------- 190
Dover Creek, Ga                                                                                                -------------------                       31
Dover, Ky.........                                                                                                                                      944
Dover, Ohio Reservoir ........                                                                                   .....
                                                                                                    ---------------                                     960
Dover Lock & Dam, Tenn         .....   ---------------------------------------------                                                                    881
Drainage district No. 1, Clatsop County, Oreg          ..   ,.                                                                                         1475
Drum Inlet, N. C-            -------------------------------------                                                                                      313
Dry Creek, N.         Y ............    --------------------                                                                                           1236
Dry Pass, Alaska                ..-    ,C-----                                --..-                 -------------------------------                    1547
                                                          INDEX                                                                           1663
                                                                                                                                            Page
Dry Run, Iowa ................- - - - - - - - - - - -                --    - - - -                                                           788
Duck Island Harbor, Conn              -----------------------------------                                                                     53
Duck Point Cove, Md-......---                                                                                                                218
Duck River, Tenn-.        .     .  .  .    .    .    .    .    .    .    .    . .                                                            894
Dudley Creek, N. Y                                             ---...                                                       -.....-          221
D u Lac B ayo u, L a------- -- -- ----- ---- -- ------ ----- -- -- -- -- -- ----- -- -- ------ --- -- -- ---- -- --  495
Duluth, Minn.:
    Engineering district -.-..-                                       -       -       -       -      -      -       1031
    Improvement of Duluth-Superior Harbor....-                                                                      1034
D unkirk H arbor, N . Y -- -- -- -- -- -- - -- -- -- -- -- -- - -- -- -- -- -- -- - 1206
Dunns Creek, and Crescent Lake, Fla .401
Dupre Bayou, La........-                       -      -   -      -      -       - -         -    -      -     -      495
Duwamish Waterway, Wash-...............                                                                             1500C
Duxbury Harbor, Mass-..-                                                                                -             53
Dyberry Reservoir, Dyberry Creek, Pa....----------------                                                             192
D yke C reek, N. Y - - -- - - -- - - -- - - =- - - -- - - -- - - -- - - -- - - -- - - 1229
Dymers Creek, Va...               -----------------------------------                                                258
                                                                 E
Eagle Creek Reservoir, Ohio ......-                          - - - - - - - - -                  --------. 1025
Eagle Gorge Reservoir, Wash                        ------------------------------------------             1519
Eagle Harbor, Mich        -----------......--------------------------------------- 1050
East Barre, Winooski River Basin, Vt.....                      ------------------------------------.. 153
East Bay Bayou, Tex .-...        .              .             .          .        .        .               601
East Boothbay, Harbor, Maine ..... .-.--                           ---       - --    - --    - -            53
East Branch, Clarion River Reservoir, Ohio River Basin, Pa.........----------------- 1000
East Brimfield Reservoir, M ass...............................                                         65, 83
East Cape Girardeau and Clear Creek Drainage District, Ill..-.................--------                     709
East Chester Creek, N. Y-.-..    .       .       .      .        .     .   .    .   .    .   .             146
East Fork Reservoir, Ohio                -------------------------------------                             946
East Hartford, Conn                                                  ------------------                                                   70, 83
Eastland, Leon River, Tex..---------------------------------------------                                                                    625
East Liverpool, Ill -..... ..             -------------.-                                                                                  1148
East Lynn, W. Va ..---..                   .              .                   -. ------------------                                         980
East   Norwalk Channel, Norwalk Harbor, Conn........------------------..----                                                                 50
East   of Hubly Bridge, Ill..---------------------------------------------                                                                 1148
East   Pass Channel, Fla., from Gulf of Mexico into Choctawhatchee Bay.......                                                               426
East   Pearl River, Miss ..........                                                                                                         448
East   Peoria, Ill ..------...  ...    ....------------------------------------------------                                                1148
East Poplar Bluff and Poplar Bluff, Mo ....--------------                                       -----------------                           668
East   River, Brunswick Harbor, Ga., improvement..-...                                   340
East                                                                    ...
       River, N. Y. improvement, including Coenties Reef.........-----------------.. 107,109
East                                 . - - - -
       River Turning Basin, Wis ..--...              --   - - - -......                 1060
East   Rockaway (Debs) Inlet, N. Y-......   . . . ..        . . . ..        . . .         98
East   St. Louis and vicinity, Ill         ------------------------------------------    724
East Sidney Reservoir, N. Y .-.-                  - --        - - --           - - --                  - - - - - -      - ---         .     220
East Twin Creek, Calif                                -----------------------------------------------                                      1294
E aton W ash, C alif .......................... ...................... .                  --........       -...                            1268
E au G allie, F la                                   ... . . . . . . .. . . .      ..... ..............  401
Echo Bay Harbor, N. Y -....    .    .    .     .     .       .    .     .    .      .        ...         146
Edenton H arbor, N . C-- -- -- -- -- -- - -- -- -- -- -- -- - -- -- -- -- -- -- -                        313
Edgartown Harbor, Mass..               .         .         .        .        .            .               53
Edisto River, S. C .......                                                                               326
Edward M acDowell Reservoir, N. H--------------------------------------- 57, 59
Edwardsville, Pa-.....---------------------------------                                                  240
Eel River, Calif.........                                    ---------------------------                1345
Eel River, M ass..-----------------------------                                                           27
Egegik River, Alaska ...........--                 -      -        - -     -     -       -        -     1547
Eightmile River, Conn .-.-.-.                 .          ..                                            .            .                         44
Elfin Cove, Alaska.....-                                      -        -      -          -         1547
Elizabeth River, N. J......----------------------------------                                       146
Elizabeth River, Va.:
     Improvement of Norfolk Harbor,             including    Eastern,    Southern, and      West-
       ern Branches------                -.--.--.-              - . .-- .     --.    ......     280,284
Elizabethtown, Ill-      -      --..- --- .        .--- .     . --.. -.       . ..........-         944

         Sig 53-1663-1694
1664                                                                    INDEX

                                                                                                                                                           Page
                                            ..-....
Elk City (Table Mound) Reservoir, Kans --..-...                                                               -----                 _ .. 696, 700
Elkhorn River Basin, Nebr...-                                                                        -...........                             845
Elkins, W. Va ..............                                                                                                    --.. 1014, 1024
Elkport, Iowa ....... ..-...                                                                                                            .... 756
Elk River, Ala. and Tenn ..............                                                                          .                       ... 894
Elk River, Md ............---------------........                                                                              -.-----------
                                                                                                                                         171, 218
Elk River, W . Va ....... .............                                            .......                       .......       .---- --- 956, 969
Elmira, N. Y ..-.....-                  .                                         -... -.                                                                   223
Elokomin slough, Washington..... .................-------------- -.............                                                                            1452
Emerald Wash and Live Oak Wash, Calif ............                                                                                                         1268
Empire, La., improvement of waterway to the Gulf of Mexico ...-...                                                                          --              482
Empire, Ohio ...............                  ----------------                                                                                             1024
England Pond levee unit, Illinois .........                      .          .                                                                    --         944
Enid Reservoir, Miss..................................                                                                                                   1584
Erie, Colo.............----------------..
                                   ...                                   .                                                                                 845
Erie Canal, N. Y......                                                                                                                           - --.- - --119
Erie Harbor, Pa .........---------------------------                                                                                                     1203
Escambia River, Fla......             .   .          .      .        ..       .                                                     .-.--             -     448
Esopus Creek and Tributaries, N. Y.....................................                                                                     --              155
Espanola, N. Mex ....     . .. .    .      .                            .
                                                    ..-----------------...                                   .             .
Essex River, M ass..-....  .......         .......
                                       ..--..                                                                                               --               53
Etowah, River, Ga ................-- -..................                                                                                                  449
Eufaula Reservoir, Okla......................                                                                 ........          .-........            696,700
Eutaw, Ala.......        . .        .        .        .      .                                   .              .                                ----       438
Evansville, Ind. ....                                                                                                                       .......944,947
Everett Harbor, Wash .......................................                                                                                    -. 1490
Everglades, Fla-... ....   .          .         .         .                                  .                .            .                --              402
Exeter River, N. H .-......                                         -                        -         --.                                                   53

                                                                              F
Fabius River, Mo .                            --------------------------                                                                                    756
Fairbanks, Alaska                                 -...-------------------------..-
                                                   ...-                                                                                                    1549
Fairfield, N. C...                          ................---------------                                                                                 299
Fairhaven and New Bedford Harbors, Mass ....---.                                                        ._ .
                                                                                                     -----.                    ..                         33,54
Fairmount Dam, Pa..............                                                             ------------------------------                                  165
Fairport Harbor, Ohio........                 ..........------------------------------------------           1195
Fajardo Harbor, P. R .........                ..........--------------------------                            401
Fall-Austin Reservoir, Ill.......               ...........                        ----------------------     753
Fall Creek Dam, Willamette River Basin, Oreg-------...                      ...      .                       1455
                                                                                              .-----------------..
Falling Spring Dam, Va.....-----------------------------------293
Fall River Basin, S. Dak ...          -------------------------.                                         829,846
Fall River Harbor, Mass ..          - .___ ._____.....---------------------------- 34
Fall River, Reservoir, Kans......-------------------------....                                                683
Falmouth Harbor, Mass-......-                                                       - -      -    -   -        53
Falmouth Reservoir, Ky ......                                                                                 946
Fancy Bluff Creek, Ga-..-         -         -                -                  --                            340
Far Creek, N. C       -------------------...                            ----------------------------          313
Fargo-Moorhead, Minn. and N. Dak .........--.....                                                                                                           772
Farm Creek, Ill......----------------------------------------------                                                                                 1140
Farmdale Dam, Ill-.. . ---------------------------------                                                                                            1141
Farmers levee and drainage district, Illinois .-...----...... ______.____                                                                      .1148
Farmington Reservoir, Calif_ ...........         -                  .__-........
                                                                    -             - ....-                                                           1377
Faulkner Count, Ark.......                                                   ............-------------------------------------------                  668
Feather River, Calif-----------.......                --.......         .................-----------------------------                    1349, 1369
Federalsburg, Md..............                                              .......                                                                   240
                                                                                               .............------------------------------------------...
Federal Water Power Act, investigation and supervision of projects                                                                                  1637
                                                                                                                                           ..............
Felsenthal Lock and Dam, Ark .......----------...............................--------------------------                                              525
Ferguson Brook, N. H ..                           ...             ...........................--------------------------------------------              59
Fernandina Harbor, Fla..                         ....--------------------------....................----------------                                  340
Fern Ridge Reservoir, Oreg                    ..................---------------------------------..
                                                                        .....------                                                                1464
Ferrels Bridge Reservoir, Tex ..                                 ---             -----------------.....-                                    497, 500
                                                                                                                                 --.--...........
Fighting Island Channel, Detroit River, Mich....................-------------------------..1162
Fire Island Inlet N. Y ............                          ............-------------------------------------------.                                  93
Fishing Bay, Md..            ...........                     ..........-----------------------------------                                           218
Fishing Creek, Md              ---------...........                  ---------------------------------
                                                                            .......                                                          206,217
                                                       INDEX                                                  1665
                                                                                                                   Page
Fishing Creek, N. C ..-.......... .                      .      .                                                  313
Fishtrap Reservoir, Ky-.............----------                                                                     980
Fivemile River Harbor, Conn...........---------------------....                                                     53
Flat Rock Dam, Schuylkill River, Pa__ ______-______..____                                                          165
Flathead Lake, Mont., improvement of Polson Bay__               __...___.
Flathead River, Mont .......-..........-                                                                          1514
Fletcher and Sunshine Gardens levee unit, Indiana .___________.______.________.______                              944
Flint River, Ga. and Fla -.........                                                                                417
Float Road Slough, Ark........--                                                                                   548
Florence, Kans.........--------------.......                                                                       700
Florida Barge Canal........ . . . .                  . . . .       . . . .                                         401
Florida Central and Southern .----------.                                                                          402
Flushing Bay, Harbor and Creek, N. Y.:                   __
Fly Creek, Ala_.................                                                                                   448
Follansbee, W. Va_________.
                         ___________.                                                                             1024
Folsom Reservoir, Calif................                                                                           1374
Fondulac Dam, Ill---...-............
                                 .                            .        .         .        .         .             1141
Fon du Lac H arbor, W is -..-......................
                                                  ---------                       1062
Ford, Ky ..............-                                 ".....-                    913
Fore River, Me-....                                                                  11
Forked Deer River, Tenn -545,                                                       548
Forsyth, Mont.............-----------------------                                   865
Fort Benning, Ga., lock and dam....... . . ---------------------------- ......
                                                                            ..      417
Fort Chartres and Ivy Landing Drainage Dist. No. 5, 111Ill____.__________......     720
Fort Gaines Lock and Dam, Ga .............                                     419, 423
Fort Gibson Reservoir, Okla-........---------------....
                                                  -                                 690
Fort Loudoun, Tenn _-.                                                              891
Fort Madison, Iowa, harbor........----------------------                            737
Fort Myers, Fla......-                                               -   -          380
Fort Peck Dam, Mont              -...
                                 ________..._.-...
                                    ..                                              857
Fort Peck, Mont., engineering district_..........______
                                                   __ ..                                                           857
Fort Pierce Harbor, Fla --...
                         _.....                                                                                    367
Fort Point Channel, Mass-........             ...             ...           ...      20, 21
Fort Randall Reservoir, S. Dak............                                             834
ort Smith, Arkansas River, Ark-........... .                       .          .       668
Fort Supply Reservoir, Okla-........       --                       -            -     676
Fort Worth floodway, Texas-.....           .        ...                            .   617
Fort Worth, Tex., engineering district-        .-- - --.-.-.-..............            603
                                                                                       6..
                                                                       _____ ______........
Forty Fort, Pa          --------------------------------.....-------------------       234
Fountain Bluff, Ill-. .--.. .            .         ..                   ..............-716
Fountain Que Bouille River, Colo-..-.b...                                              638
Fourche Island, Ark              ------   _____   __           ........-                                           662
Fourche La Fave River, Ark ...........-...                                                                         666
Fox River, Ill. and Wis -.................                                                                        1061
    L ocks and D ams ----------------------- ---------------------------------------                              1063
Francois Bayou, La .. .... . . . . . . . . . . . ..-----------------------.......                                  517
Frankfort Flats, Me---------------                --------               6
Frankfort Harbor, Mich__.........        .       ..             .     1107
Frankfort, Ky......                                               913, 944
Franklin to the Mermentau River, La...-....         _______.__.        471
Franklin Falls Reservoir, N. H .....-.....-                -    -   57, 58
Frazeyburg Reservoir, Ohio-............                                980
Freeport Creek, N. Y       ________.....                                96
Freeport H arbor, Tex ...-............................-... ....        584
Freeport on Pecatonica River, Ill............
                                          _______.
                                               .    .      ..          756
Freeport, Pa .__---______.--___------____-..___                                                          985, 1024
Fremont Channel, Calif....--------------------------------------1364
French Broad and Little Pigeon Rivers, Tenn.....                        ____........________       ___......       894
French Creek Reservoir, Pa _ ___.....                 ...                                                         1025
Friendly, W. Va.......-....                                ----------------------------                            978
Fullerton Dam, Calif ..-------------.......................------------------------------- 1288,                  1291
Fullerton, Ky     --------........                   ..........------------------------------------------------    978
Fulton, Ark ..       ..............-------------------------------                                                 672
 1666                                                   INDEX

                                                              G
                                                                                                                          Page
Galax, Va .--.....................-------------------------                                   -                        978
Galena River, Ill.......----------------------------------------752, 756, 981
Galion Bayou, La............----------------------------------------------.                                            517
Galere Bayou, Miss                                        ..........---------------------------------------------      448
Gallipolis, Ohio ...
         GlioiOi----    _...         .
                                     __________...
                                                .              .            ...
                                        ---------------------------------------------------------- 95497           954, 978
Galveston Bay and Harbor, Tex......                             ---------------------------------..              558, 565
Galveston, Tex., engineering district _...                        ...      ....       ...
                                                                          ________........                         .    551
                                   .
Gardiner, M e ...... . ...... ........      .           .           .           .          .       .      .            8, 9
Garrison, N. Dak., engineering district .. __..__.. ......                             ______-_--.            ..       849
Garrison Reservoir, N. Dak....                               ---------------------------------------..                 850
Garrows Bend, Mobile River, Ala--             ......... _____-__-._______.-                             ---            429
Garza-LittleGarza-Lit-e-Elm-Dm,-Te------------
              E lm Dam , Tex......_____ ____.           .. __._____                ----------------------
                                                                                         .        ..                    610
                                                                                                                        610
Gasconade River, Mo...........                  --------------------------------------                                 820
Gastineau Channel, Alaska_....___.__......___.___..              __-                                 . ..            1547
Gaston Reservoir, Va. and N. C ............-                                            ----------------                  289
Gate Creek Dam, McKenzie Basin, Oreg ...............-------------------------. 1455, 1476
Gathright Reservoir and Falling Spring Reregulating Dam, James River Basin,
  Va--------...........------------------------------------------------293
Gauley River, W. Va .........                       .---------------------------------. 956
                                                                     ------------------
Gavins Point, S. Dak. and Nebr ................------------------.......              .         837
Gaysville Reservoir, Connecticut River Basin, Vt .------              ___..._____..
                                                        __-______.__.____..      __..__..... 69, 83
Genegantslet Reservoir, Genegantslet Creek, N. Y .. __ _____-___...
                                                                ---.     ___..___... . 219, 232
                               - -. --
General Joe Wheeler, Tenn . __-___-..-_____._______-                             ---.           891
Generals Cut, Ga ........          ----------------------------------------------- 331
Genesee River, Pa. and N. Y--------------------------------------                             1219
Georges River, Maine ..-------------.                                                                                       53
Georgetown Harbor, S. C                                 -----------------------------------------                         317
Gest, Ky................------------------------------------                                                              913
Gila River, Ariz. and N. Mex..                           ---------------------------------        1296,                  1298
Gill Township levee unit, Indiana.-.-...............__-----.-                                                             947
Gillett, Ark., N. Little Rock to-......------------------------------                                                     661
Gladstone Harbor, Mich..-----------------------------------------                                                        1113
Glasgow, Mont .....--.......--------
                              -                                            -----------------------                        865
Glen Cove Creek, N. Y.....-------------------------------------------                                                     146
Glen Cove Harbor, N. Y ....                ___....    _____        --------------                                          146
Glenmore, Ky-......      ______________                                                                             916
Gloucester Harbor, and Annisquam River, Mass                 .  ...
                                                        ______...                                                    17
                                                                                                    ._______._____-__.
Goat Island Reservoir, Ga. and S. C..-----------------------                                                --..    341
Golconda, Ill      -      -.-.......---.----------.---                                                         944, 947
Goldsboro, Neuse River, N. C-......-.                  .         .            .           .        .                314
                     __....______.                               . . . . . . . . . . .
                                               ...
Goose Creek,
        rek S.. C.-------------------------------------------------------
                             .
       Gos                                                                                                          319
                                                                                                                   31
Gordon Landing, Lake Champlain, Vt............__.......__.._____....                                                146
Goshen Creek, N. J....... -----------                                                                               190
Gosport Harbor, N. H ..--....-                                                                                       14
Governors Run, Md                            -.-.-.-..                                                              218
Gowanus Creek Channel, New             York        Harbor,   N.   Y .....................     .__                   105
Grand Bayou Pass, La........-...                                                                                    495
Grand Caillou Bayou, La                                                                                   -         495
Grand Forks-East Grand         Forks,         Minn.,     and N.    Dak.................           ....              772
Grand Haven Harbor and River, Mich..--------------------           __________..                                    1095
Grand Marais, Mich., improvement of harbor of refuge...........                 _...             __..              1048
Grand Marais Harbor, Minn...............                                                                           1031
Grand (Neosho) River Pasin, Kans ........                     ---------------------.. 687,700
Grand Prairie region, Arkansas ... ...-- - - --..-                              - -         -  -       ---..-----
Grand River, Ohio----- --------------------------............                                                     1196
Grand River, Mich ._____...____..___.__                                                                            1095
Grand Tower Drainage and Levee, Ill ...                         --------------------------------. 715
Grand Traverse Bay Harbor, Mich.___________________...                                                             1045
Grand View Bay, N. Y .. _________.._________-                               ----------                                   1227
Grandview, Ind ...............- ----------------                                                                          944
Grande Ronde River and Valley, Oregon         ..
                                          ____________.....1532,                                                         1536
Grant Parish below olfax, La----------------------------------497,                                                        519
Grapevine Reservoir, Tex- - - - - - --........................                                                            612
Grasse River (Massena), N. Y--                                                                                           1227
                                                                                                                         1--.-----...............
Grays Harbor and River, Wash....:..............                                                                  1452,1506
                                                      INDEX                                                     1667
                                                                                                                   Page
Grays Reef Passage, Mich .........                                                                              -       1113
Gret Bridge, Va----------...............
                               .....                                                                                     285
Great Chazy River, N. Y .......................................                                                           146
Great Kills, Staten Island, N. Y......--------------------------.....                                                     137
Great Lakes:
     Waterway to Hudson River ...................                                                                         119
Great M iam i River, Ind.....................................                                                             946
Great Pee Dee River, S. C...............-----------------------                                                           326
Great Salt Plains Reservoir, Okla ....-------... ...                                      .............. 680
Great Salt Pond, Block Island, R. I .........---------------.---.          _.....                                           53
Great Sodus Bay Harbor, N. Y ....     ..             .                   .       .        .                             1221
Great South Bay, N. Y ....  ...
                              .......    . . . .                       .. . . . .                                           94
Green, Barren and Nolin Rivers and Bear Creek, Ky ...............                                                        914
Green Bay Harbor, Wis. ...-...................  ......                                                                  1059
Green Bay levee to Drainage District No. 2, Iowa.....                                                           - --   - 756
Greencastle, Ky........ ... .... ... ....                                  ....---------------------------------------916
Greenfield Bayou levee unit, Indiana ._________ ___._.__._____.__                  ___.____
                                                                                          . __._
                                                                                               .                         944
Green Island levee and Drainage District No. 1, Iowa............................                                         756
Green Peter Dam, Oreg ..--______-__.         ---                                                                       1466
Greenport Harbor, N. Y .......------------....-                      -           -                                       146

Green River, Ky ....         .            .               ...                                                            946

G reen R iver, W ash ............... .............. ..............                                                     1519
Greensboro, Ala ................................                                                                         438
Greenup, Ky .... ....--------------------------                                                                          978

Greenwich Bay, and Cove, R. I........                             ...                ...                                   53
Greenwich Harbor, Conn-...------------------.-.
                              .-                                                                                           53
Greers Ferry Reservoir, Ark ......                  ..                                 .            --. --               651
Gregory drainage district, Missouri ....                   ....................                                          756
G renada Reservoir, M iss ...............
                                      ..........      .....     ....... ...........                                    1584
Greybull, Wyo .............                                                                                              864
Grosse Tete Bayou, La...........-------------------------.                                                               495
Guadalupe River, Tex .........---------------------------                                           --.---.-.--    558, 624
Guayanes Harbor, P. R.......      .       . .             . .                  ..       . .                              401
Guemes Channel, Wash ...........------------                                                                           1485
Guilford Harbor, Conn ..              .................................                                                    53
Gulf Intracoastal Waterway between Apalachee Bay, Fla., and the Mexican
  border:
     Galveston District .....--------------------------                                                                  557
     Mobile District-----                                     .-------------------------                                 413

     New Orleans D istrict .. .................... .......                                                               458
Gulfport H arbor, M iss ..................... ........... ..........                                                     444
Gull Lake Reservoir, Minn ........       ...-----------------------.                                                     764
Guntersville, Tenn............ .. . .. .. . ....                  ..........                                            891
Guyandot River, W. Va ..........-------------.....
                                           ..                                      .                                     956
Guyandot Reservoir, W . Va --.---------------------- ............                                                        980


Hackensack River, N. J .....                                                                                  133

Hadley Creek, Ill..........         _...                                                       .              753

Hager Slough, Special Drainage District, Ill ........-----------...      .                                  1144
Hagermans Run, Pa............................. ......                                                         236
Haines Canyon, Los Angeles River Basin.......                      .          .            .          .     1268
Hales Bar, Tenn ......            ..------------------------..                                                891
Halfmoon Bay, Calif .. . . .                   ..-------------------------.                                 1325
Half Moon Shoal, Mass ..........         ------------------------------..                                      33
Hallowell, Me-.....-...------.. -------------......----------------                                       --     9
Hamburg, Ill., boat harbor opposite............---------------........        .                  .            737
Hamburg, Iowa................                                                                                 845
Hammersley Inlet, Wash-... ...------------- .                ..         . . . . . . .___---- 1514
Hammond Bay Harbor, Mich .....-.-.-..                                                                        1178
Hammondsport, Oswego River Basin, N. Y.......                      .       .       .        .       .   .    1236
Hampton Creek, Va...................------------------------------                        -.......            288
Hampton Roads, Va.:
     Improvement of approaches to Norfolk Harbor . ...........................                                280

     Removal of drift.........       ............. ..............------------------------------------         283
1668                                                       INDEX
                                                                                                                                         Page
Hanapepe River, T. H ................                   .....              .....------------------------------------------    1343
Hanging Rock, Ohio..................... ....                   .............---------------------------------                   978
Hanna Reef, Tex...........................         ...         ............---------------------------------------              601
Hannibal, Mo., harbor ....-----.... ----------------..----....
                                               ...                     ......            --------                               737
Hansen flood control basin..             --------......
                                                   ...              -------------------------------                           1268
Hanson Lock and Canal, La---........               ...        ------------------------------------                              471
Harbor Beach, Mich., harbor of refuge .___________...........                 ___.....                                        1178
Harbor Island Basin, Tex..----------...--------.......
                                                   ...-----------------------                                                   589
Harbor of Refuge, Aussable River, Mich------....                  --..----...                                                 1165
Harbor of Refuge, Delaware Bay, Del_.--..--...-.-....___                                          -                             190
Harbor of Refuge, Nantucket, Mass .......                                         _...___..                                      54
Harbor of Refuge, Seward, Alaska----...                        --------------------..--...                                    1545
Harbor of Refuge at Block Island, R. I_........ __-.-------__--._______._
                                                                       ..                                                        53
Harbor of Refuge at Point Judith, and Point Judith Pond, R. I.                                                                   54
Harlan County Reservoir, Nebr.....-                                                                                        810, 861
Harlem, Mont..-------------------------------------------------                                                                 865
Harlem River, N. Y------..---------------------------------                                                                     109
Harlingen, Tex                     ------------------------------------------                                                   560
Harpers Ferry, W. Va...........------------------------------------....                                                         266
Harraseeket River, Maine..........                  -----------------------------------------.. 53
Harrisburg, Ill-.....---.                        .__--________-                                            -       ----- 944, 947
Harrison County, Miss______....                                                                                                 448
Harrisonburg, La.________                                                                                                       525
Harrisonville and Ivy Landing drainage and levee district No. 2, Illinois
Harrisville Harbor, Mich....                  -----------------------------------
                                                                                                                         --..   721
                                                                                                                              1178
Harry L. Englebright (Upper Narrows) Reservoir, Calif...                                              .           .           1565
Hartford, Conn            .......        -----------                   -----------------------------                         70, 83
Hartford, W. Va                          -----------------------------------------------                                        978
Hartwell Reservoir, Ga., and S. C ...                          -----------------------------------                              341
Harvey Lock, La.......              ---------------------------------------                                                     461
Hastings, Minn., harbor..                  --------------------------------                                                     737
Hatchie River, Miss----------------------------------------                                                                     548
Havre, Mont             .....-                                                  -----------------------....--                            862
Hawesville, Ky.........                       -------------------------------------------..                                        931, 944
Haysi Reservoir, Va. ..-.............----------------                                                                                    980
Hay, (West) Harbor, N. Y-.......-----------------.----.                                                           53
Head of Passes, La......        __..._____                                                                       474
Heart River, N. Dak----..------..-.-.-------.-.-                              -    ---..                         853
Heather Island, Fla       ................----------------------                                                 355
Heidelberg, Ky...------------------------------------                                                  ---       913
Heise-Roberts area, Snake River, Idaho ........-                                                          1532, 1533
Hellen Creek, Md ...........                         -----------------...-                 -     -.              258
Hempstead County levee district No. 1, Arkansas.........--------------------..                              497,519
Hempstead Harbor, N. Y                                 -----------------------------------------                 146
Henderson County Drainage District No. 3, Ill11----- -                               ------------                756          .----

Henderson River, Ill             -           -         -          --..-...........                               756
Henderson, W. Va......----------------------------------------------978
Hendricks Harbor, Maine                                  .......------------------------------                    53
Hennepin, Ill ......... .             .         ....... . .                ..      . . . . ..                   1148
Henry T. Rainey Dam (Lock and Dam 26), Ill........                                              ......
                                                                                   __._ .____._______            735
Herreid, S. Dak                                                         ----------                                                       847
Herring Bay, Md ..................                                                                                                       218
Heyburn Reservoir and Channel Improvements, Okla                                           __ ...          __________..._______.         682
Htiggins and Coldwater Canyons, Ballona Creek Basin................                                                                     1268
Higginsport, Ohio- - - ------...                                                                                                         944
High Bridge, Ky ...........      ........ ...  .                                                                                         913
Highwood Creek, Mont-- --------...        --  - -- ---------------                                                                      866
Hildebrand Lock and Dam, Monongahela Rivergginsport,------------------------                                                            994
Hillsboro Bay, Canal, River, and Inlet, Fla .-. ______ -     -~...........___.                                                          389
Hills Creek, Dam, Oreg..................                    ..........-..                                                               1458
Hilo Harbor, T. H.- ...  ....................-.....-..                                                                                  1340
Hingham Harbor and Bay, Mass---___--................ .-...-                                                                         -     25
Hiwassee River, Tenn....                               ...........-------------------------------------------                            894
Hockingport, Ohio                              ....................         ........ ...                                                978
Hocking River, Ohio .........                   ... ..              .       ......... .....          ...                                965
                                                                                                                                        980
                                                           INDEX                                                         1669
                                                                                                                             Page
Hodges Village Reservoir, Mass ......----------                                                                               65, 83
Hodgman Creek, N. Y......---------------------------------..--------..                                                          224
          e se rv o ir, C ali f _..... .... . ..... ..
H o g an RHogan--Reservoir,---Calif-----------------------------------                                       -- -- -- --- 17   13 7 7
Holbrook Levee, Little Colorado River, Ariz-.............................                                                      1298
Holland Harbor, Mich-                                           ---------------------------------                              1092
Holley Dam, Oreg.......-----------------------------------------                                                        1455, 1476
Holmes River, Fla.....---------------------------------------------                                                             448
Holsten River, Tenn----------------------------------                                                                            894
Holyoke and Springfield, Mass _------------------_...........                                                              . 70, 83
Homme Reservoir and Dam, N. Dak ..............----------------..                                                          771, 778
Homochitto River, Miss-                                                                                                   528, 539
Homosassa River, Fla ...__.                                                  .___._________._____                               401
Honey Creek levee unit, Indiana --------- -                             .--........----------------------------.
                                                                                                       .......                  944
Honey Hill Reservoir, Connecticut River Basin, N. H                                                                           69, 83
Honga River, Md--------------..-..------------.--------                                                                      - 205
Honolulu Harbor, Hawaii........----------------------------------------                                                        1334
Hood River, Oreg....----------------------------------------------1420
Hoosic River Basin, N. Y....------------------------------....                                                                   148
Hoosick Falls, N. Y................                                                                                              148
Hopkinton-Everett Reservoir, N. H .........--------------------------------                                                       83
Hoquiam River, Wash-.....--                            -          -
                                                      --------------------.--                                                  1514
Hords Creek Reservoir, Tex.........--------------------------..                                                                 621
Horger, Tex ..._.-..                                       ..                                                                   604
Hornell, N. Y...............------------------------                                                                            226
Horn Harbor, Va.........                                                                                                        288
Horseshoe Cove, Fla......-                                                                      -         -         -           401
Horton and Dutch Creeks, The Sny Basin, Ill ...............-                                                                    753
Hoskins Creek, Va --.... ..                  ......... --------------------------------------------                             258
Hot Springs, Fall River Basin, S. Dak-........----------------------                                                            829
Housatonic River, Conn............................-------------------------------------------                                     53
Houston to Galveston Ship Channel, Tex....--------------------------                                                      572, 599
Howard Farms-Reno Beach Area, Ohio ....-.....                                 __....                                           1182
Howards Bay Channel---------......                ..          ---------------------...                 ----                    1036
Howell Mill Shoals Dam, Ala .....             _____....______.                                          .         .       433, 435
Hubly Bridge, Sangamon River, Ill........                              . ____. .                .              .               1.148
Hudson Harbor, Wis.....                      ..          ..         ..          ..         ..         ..              .         768
Hudson River, Fla ... _______..._._                                                                                             401
Hudson, Mohawk and Waterford Rivers, N. Y .__.________.                                        .__________-_..                  153
Hudson River, N. Y....                           -----------------------------------                     109, 111, 114, 115
      Locks and Dams, N. Y...................................----------------------------------                           118, 121
      Waterway to Great Lakes-enlargement of New York State Barge Canal ...                                                     119
Hugo Reservoir, Kiamichi River, Okla-...... ___..____.....                                        ._______                      701
Hulah Reservoir, Okla............------------------------------------686
Humbolt Bay, River, and Harbor, Calif                                                                                          1303
                                                                                                          .............------------------------------
Humboldt River, Nev...........                                                                                                 1400
Huntington Harbor, N. Y ......----------------------                                                                            146
Huntington, W. Va.:
      Engineering district .                    -..-                  - - - - - - - - - - -                                     949
      Flood control ---                   ---                 ---------                                               970, 978
Huron Harbor, Ohio .                            -.- - - - - - - - - -              - - - -                                 1187
Hurricane Ditch, Ark..                          _________ ------------------------------------                              549
Hussey Sd., Me ................----                   -------------                                                       10, 11
Hutchinson, Kans                                                           -.--...---------                                  672
Hutchinson River (East Chester Creek), N. Y_ -..--------.--.....        ---------  146
Hyannis Harbor, Mass.......--------------------------------------------53
Hydraulic Mining, regulation of...   -----------------------....------------      1561
Hylebos Waterway, Tacoma Harbor, Wash............                                 1502

                                                                 I
Ice Harbor at Marcus Hook, Pa ..-.....--.-                                  - -                                             190
Ice Harbor at New Castle, Del           -----------------------...-. ------                                                 190
Ice Harbor Dam, Snake River                ------------------------------...---                                            1528
Illuliuk Harbor, Alaska-..........................
                               - - - -                                                                                     1547
Illinois and Mississippi Canal, Ill-............-                     -      -                                               747
      Locks ............... . ... ....                                                                                       749
1670                                                               INDEX

                                                                                                                                                   Page
Illinois River, Ill-----..--.....-------...............         ..........                      -------------------               729
Illinois Waterway, Illinois and Indiana ....................---------------------------                                    709, 1130
      Locks and Dams .....................................                .........                                              1---------------------
                                                                                                                                 1134
Indiana Harbor, Ind., improvement-----..........----------------------------1125
Indianapolis, Indiana                     ...........--------------------------------------------                                 947
Indian Creek, Ill.........-----------------------------------------------1149
Indian Ford Dam, Wis.......----------------------------------756
Indian Harbor, Maine-               --------......................                                                                   4
Indian River, Fla ....                ...                 .......           ...-----------------------------------------------    379
Indian River Inlet and Bay, Del .                       ...............------------------------------------                       174
Indian River Inlet to Rehoboth Bay, Del., Waterway _..___-..........______                                            _..._       190
Indian Rock Dam, Pa., flood control ................-------------------------------..--                                           238
Indianola, Republican River, Nebr.. .______...._.........                .............                                            820
Industrial Canal, New Orleans, La..                          ..          -----------------------------                       429, 589
Industry, Pa .........----------------------..                                                                                                    1024
Inland Waterway, from:
     Chincoteague Bay to Delaware Bay, Del-                            --..
                                                                       . ____...--..
                                                                -. --..-           .      .     .                                                  190
     Between Jefferson, Tex., and Shreveport, La-----..                   --------------..........-----                                            495
     Between Rehoboth Bay and Delaware Bay, Del _____.--.........._______..._____                                                                  190
     Delaware River to Chesapeake Bay.................__________                     ----------------                                              171
     From Empire, La., to Gulf of Mexico_               -..........
                                                  _____..__.______                .      ______                                                    482
     Franklin to Mermentau River, La .............. ------------------------------                                                                 471
     Intracoastal Waterway to Bayou Dulac, La                   -           ........                                                               495
     Port Aransas-Corpus Christi, Tex__-...__. . -___---..-. ..                   ......                                                           589
     Sabine-Neches, Tex..------------------------------------------                                                                                551
     White Lake to Pecan Island, La....     .....---------------------------------                                                                 496
Inner Harbor Navigation Canal Lock, La ----.......
                                                __---____-__..........                                                                             461
International Boundary Waters      .    .........------------------------------------                                                             1640
Interoceanic Canal surveys ....--                           ..............                                              ..                        1635
Intracoastal Waterway:
     Between Apalachee Bay, Fla., and the Mexican Border.......---------...... 413, 458, 557
     Between Norfolk, Va., and the St. Johns River, Fla-....                          284, 297, 315, 329, 347
     Caloosahatchee River to Anclote River, Fla                     -..--------..
                                                                        ___-__.....---                ---         384
     Cross-Florida Barge Canal--           ----               -----------------............-                      401
     Gulf Intracoastal Waterway_- ........--.- .......-......                                  -             413, 458
     Jacksonville to Miami, Fla ---------.... .                    ...----------------------------                357
     Miami to Key West, Fla.......                   ......--------------------------------------                 401
     Mississippi River to Bayou Teche, La .. __-__-____- --............__                               ..        469
     New Jersey- .....-------....
                             ..........-.........-.....                                                           187
     Okeechobee Waterway..--------...     ---.--..... ...          .--------                                      378
     Port Townsend Bay and Oak Bay, Wash. ..-___-_______--      ..                 -------....                   1489
     Between Pamlico Sound and Beaufort Harbor, N. C..----..-                                     .
                                                                                  __----...--..--.-.-...          313
     Tombigbee-Tennessee Rivers Waterway .......... ---------------------------                                   448
Iola, Kans----..        ...            ------------------------------------------------                           700
Iowa River, Minn. and Iowa...              ...                 ...---------------------------------------         752
Ipswich River, M ass .____. __. ______.____......                                                          ..      53
Iron Canyon (Table Mountain) Dam Sacramento River __.....-..-...-..                                            '1371
Ironton, Ohio                              ..-------------..-...
                                     ----....                                              ..                                                 978,981
Irvington Harbor, N. Y .....-----------...-                                                    - -. 146
Isabella Reservoir, Calif         ----------------------------------------                          1397
Island Creek, Md            ...               ----------------------------------------- 218,258
Island levee unit, Indiana-----...------------------------------------                               944
Isle au Haut Thoroughfare, Maine_-             --__.......__
                                                     --......
                                                          -.-.--.-.-.-----
                                                           ...........     .. ...-- _ _.......        53
Isles of Shoals Harbor, Maine and N. H------------------------...                                     14
Ithaca, Oswego River Basin, N. Y.-..                                .              .       .         .           .           .      .     .       1236
Ivy L anding, Ill . . .            . . .         .      ..-..        ..       ..       .. ..    ..       ...    .. ..        ..   .. ..             719
                                                                          J
Jackson Creek, Va....          --. .            .              ...                                                                                 258
Jackson Hole, Wyo---------------------------------------------                                                                                    1540
Jackson, Ky                                                                                                                                   92------------------------
Jackson Lock and Dam, Ala....-..             ..-----------------------                                                                             439
Jackson, Miss., Pearl River at.....------------------------9.-.                                                                                    452
Jacksonville, Fla.:
       Engineering district ...-.---.--...                                                                     ---------------------- 347
       Harbor- ....                                                                                                                 349-----------------------
                                                                            INDEX                                                              1671
                                                                                                                                                   Page
Jacksonville to Miami Intracoastal Waterway .......--------------------------                                        357
Jamaica Bay, N. Y...         .        .          ---------
                                                 ..-------------...-----                                             101
James River, Va                     -------------------------------------------                                      272
James River Basin, Va-----..........................                  .....--------------------------------------    293
Jamestown Reservoir, N. Dak----    .............     .......       ..----------------------------------              853
Janesville, and Indian Ford Dams, Wis----.........                      -----------------------.                     756
Jasper, Tex                    ----------------------------------------------                                        604
Jefferson-Shreveport Waterway, La. and Tex ........                        ---------------------------.              495
Jeffersonville-Clarksville, Ind-...---........--....------------------                                          926, 944
Jemez Canyon Dam and Reservoir, N. Mex.......                                 ---------                  --          635
Jenks, Okla                     -----------------------------------------------                                      700
Jennings Beach, Conn---.....               ....-----------------------------------                                    53
Jessamine Creek Reservoir, Ky                                -------------------------------------                   946
Jim Woodruff Lock and Dam, Ga .                              --------------------------------                   419, 424
Joanna Reservoir, Mo ......... ------------------------------.                                                       729
John Day Dam, Oreg. and Wash ..-----------------------------------                                                  1452
John Day River Area Clatsop County, Oreg ........                                                                   1475
John Drainage Dist., Oreg .........                  ----------------------------------------                       1473
John H. Kerr Reservoir, Va. and N. C.........-----------------..-                                                    290
John Martin Reservoir, Arkansas River, Colo...........----------------........                                       630
Johns Creek, Ky                      ...        .............        ....                                 .....-----------------                    971
Johnsonburg, Pa                            .........            .... .              .
                                                                            -------------------   .           .             .           1003, 1024
Johnson Creek, Oreg..------------------------------------                                                                           -              1476
Johnsons Bayou, La             ------------------------------------------                                                                  ---      601
Johnsons River, Conn....                 ------------------------------------                                                                        53
Johnstown, Pa .. ......-                                                                              -----....------------.....         1008, 1024
Jones Bluff Lock and Dam, Ala........     ---------------------------.                                                                              433
Jones Inlet, N. Y   ........------------------------------------------------                                                                         96
Jordan River, Miss ..-........                                                              --------------        .....-.       .                    448
Jordan River, Utah ...        ---------------------------------                                                                                    1400
Josias River, Maine----------------...........                                                                                                       53
Juneau Harbor, Alaska...........                                                                                                                   1547
                                                                                    K

Kahului Harbor, T. H.-.                   -......       ....                                                                .       .        -1337
Kalamazoo River, Mich ..............                                                                               ..                                1091
K anawha River, W . V a.. ..................................                                                                                           952
    Locks and D am s....................................                                                                             ....--------      954
    Flood control reservoirs ..................................                                                                  ........ 980
Kanopolis Reservoir, Missouri River, Kans ......... ---.......                                                                               .... 812
Kansas City, Mo., engineering district ---.. --------                                                                                     ..... 793
Kansas Cities, Mo. and Kans......--.-..........                                                                                              .... 802
K ansas River, K ans...-........................................                                                                                       816
Kapalama Basin, T. H ---...                                                                                                                          1334
Karlson Island, Clatsop County, Oreg -...-.............                                                                            - -. -            1475
Kaskaskia Island, Ill .-.....              ..
                                       -----.                                        ............. --- -----        ---- --- -          .. . 7 2 9 , 7 3 0
Kaskaskia River, Ill                      -.....                                                     ------
                                                                                              --------       -- -- - -- -- -- - -- -- - 7 0 9 , 7 2 9
Kaunakakai Harbor, T. H....-.-......                            .          .                                                                         1336
Kaw, Okla ........-. . . . . . . . . . . .                                                                                                      -      700
Kawaihae Harbor, Hawaii                                  -.                                                                                          1338
Kawainui Swamp, Island of Oahu, T. H........                                                                            --     -.          -         1344
Kaweah River, Calif -. ..                       ..       ..         ..      . -- - - -----                                                        .  1400
Kawkawlin River, Mich ..........                 -       -        -      -                                                                           1183
Keehi Lagoon, T. H...........                                                                                                         . - -          1332
Keene, N . H ..-... .. .. .. .. .. .. .. .. .. .. .. .                                                           --                                      85
Kegotauk Bay, Va -........                                                    --------------------------------------------------.                        14
                                                                                                                                                       2214
Keithsburg, Ill          -..-.--...-                                                                                          --      -. - -            756
Kelly Lake, Ill -....             ...                                                                                                                1148
Kendrick, Idaho .-                 -         -                -        -                                                   - -- ---.                 1532
Kennebec River, Maine..- .........                         .               .
Kennebunk River, Me -..-..-.                           -....                                 -------- ----- ---- --- -- --- -- --         ----      12 , 13
Kennebunkport, Me..-..-.--.........                                           --------- ------- .--------------------------------.                       1
                                                                                                                                                         144
Kennewick, Wash ....-. .              .            .         .         .                                                                             1408
Kenosha Harbor, Wis                      ---....-------                                                                                          .. 1085
1672                                                         INDEX
                                                                                                                      Page
Kent Island Narrows, Md ...                 ...........----------------------------------------                201
Kentucky River, Ky.............-----------------------------------------...                              911,946
    Locks and Dams-----------------------------------------..---'913
Kentucky Lock and Dam, Gilville, Ky .........................          _____.                             . 891
Kern River, Calif..----------------------------------------------                                             1397
Kerton Valley, Ill ....                                                    ....----------------------------------------------
                                                                                                              1142
          Harbor, Alaska ..._____..____.
KetchikanKetchikan---Harbor,--Alaska-----------------------------------------14     ........                  1547
Kewaunee Harbor, Wis-......-------------------------------------...                                           1070
Keweenaw Waterway, Mich
Keyport Harbor, N. J
Keystone Lock and Dam, La
                                       _________                         ----------------
                                                   --------------------------------------
                                                 --------------------------------------
                                                                                           146
                                                                                           485
                                                                                                                     1042


KeystoneKeystone     Okla...___....____.__                             .....
          Reservoir, Okla------------------------------------------------68 .      .       681
Key West, Fla., improvement of harbor ...        ___...............__________..            401
Key West, Fla., Intracoastal Waterway from Miami- __.__--.-____-_______-.-___
                                                                    --                ____ 401
                                                                                      ---.
Kiamichi River, Okla ..--------------------------------------------                        701
King Bluff, N. C    ..-----------------------------------------------                      308
Kings Brook, N. Y               ------------------                                                                    997
Kings Creek, Va.....-----------------------------------------------                                                   288
Kingsley Creek, Fla                         ...---------------------------------------------                          348
Kings River, Calif...               ---------------------------------------------                                    1394
Kingston Harbor, Mass. (North Plymouth Harbor)....--____-----___.......____                                            53
Kingston, Pa....... .....-                                   - - - - - - -                                            240
Kiser Creek, Ill__.....
                    . .__.____-.-.-
                       .                                                                                              753
Kissimmee River, Fla ________.                       ___________---------------                                       401
Kittanning, Pa .______________.....
      KtannP--                                              .             ..
                         ---------------------------------------------------------------             1024
                                                                                                985, 102
                                                                                              985,
Knappa area, Clatsop County, Oreg .-----------.                            --------------------- 1475
Knapps Narrows, Md .......                     --------------------------------------------           218
Knife River and Harbor, Minn. and N. Dak- ----__ __ --- ------------             _______-._.        1050
Knightsville Reservoir, Mass....                     -------------------------------------.. 69, 78
Knobbs Creek, Va..----------------------------------------------                                      288
Knobel, Ark-----------------------------------------                                                  668
Kodiak Harbor, Alaska..------------------------------------------                                   1547
Kootenai River, Idaho and Mont......................-------------------              -- -- .1514, 1524
Kootenay Lake Board of control....                         ----------------------------------- 1645
                                ....----------------------------------------....
Kuhio Bay, T. H................-----                                                                1340
Kuttawa Lock and Dam, Ky-..... . . . . . . .                                          ..      .       881

                                                                 L
Lacey, Langellier, West Matanzas, and Kerton Valley, Ill________. _________.__. 1142
Lackawaxen R. Pa ............----------------------------------------------                    192
Lackawanna River, Pa __.......- -        -----------------------.
                                                           .                              240, 241
Lac La Belle Harbor, Mich.......                  ---------------------------------------    1050
            B ay ou , L a .__.._._.........
La c om b e Lacombe--Bayou,--La---------------------------------------------495
                                          ..... .. ...  ....4                                   95
Lac qui Parle Reservoir, Minn...-------------------------------------                          785
Lafayette River, Va........-----------------------....               ----------------------    288
Lafourche Bayou, La              -.................-                      -..                                         483
La Grange Bayou, Fla......-------------------------------------------                                                            448
Laguna Madre Bay, La. and Tex                            -----------------------------------                                     560
Lake Ashtabula and Baldhill Dam, N. Dak .... ----------------------- . 771, 780
Lake Betsie, Mich-------.......------------------------------1108
Lake Bisteneau, La.....---------------------------------------------                                                             495
Lake Borgne, La-....----------.---------.-................                                                                  .    495
Lake Brownwood Reservoir, Tex- ...... ___________-                                                                               625
                                                                                                                      ...... 6........
Lake Calumet, Ill-------                        ~_..            ------------------------                                   --   1140
Lake Champlain, N. Y. and Vt------------------------------------.                                                               1239
Lake Champlain Board of Control .........             . ...................                ..---------------------------------- 1641
Lake Charles Deep Water Channel, La.....-----------.----------------- 491,496
Lake Chautauqua, N. Y....-----------------------------------------1025
Lake City, Minn., harbor ----------...---------------         - -.------------------..-------------                              737
Lake Crescent, Fla----------..------------------------------------                                                               401
Lake Crockett, Wash--------...................................             .............-----------------------------------.    1488
Lake Drummond Canal .....------------------- ---------..................------------------------------------------               285
Lake Greeson, Ark........2.-.--.-                                                                                 ----... 533
                           - .............
Lake Griffin, Fla.. --- .....    --......... . . . . . . ..                                                           354
Lake Hamilton, Ark- ..      - - --- -         ---.--...--...                                                          530
                                                     INDEX                                             1673
                                                                                                          Page
Lake Harbor, Fla ...................     ..........   ...-----------------------------------------------    404
Lake Harney, Fla------..                        ...-----------------------------
                          ----...................                                                           401
Lake Macatawa, Mich-----...........----------------------------------                                     1093
Lake Michigan Ship Canal, Wis....            ---------------------------------..                          1066
Lake Montauk Harbor, N. Y.........---------------------------------------                                    90
Lake Ogleton, Md         -------...------------------------...------------.                                 218
Lake Okeechobee, Fla....  __.. _____........-378
                                   .     .     ..                    . . . ..                             , 402
Lake of the Woods Minn ..........       ...............
        Lake----of--the--------------------------------                               ------- 7123   761, 1239
    International Control Board                                                                           1644
Lake Pontchartrain, La          ---------..------------------------------                                   458
Lake River, Wash...........-------------------------                                                       1452
Lake Series Reports             ..............-------------                                              1555
Lakes, Great. See Great Lakes.
Lake Superior Board of Control_.................                                                          1643
Lake Survey, U. S............-------------------------------------                                        1239
Lake Texoma, Red River, Tex. and Okla................____...                                               696
Lake Traverse, Minn. and S. Dak-......                         -------------------------              770, 782
Lake Traverse and Bois de Sioux River, S. Dak...........                                                   771
Lake Washington, Miss............................-----------------------------------..                     528
Lake Washington Ship Canal, Wash., improvement _.______.                               _______________
                                                                                         .                1497
Lake Winnebago, Wis ..........          ------------------------                                          1062
Lake Winnepesaukee, N. H ..                               ----------------------------------------          53
Lake Loutre Bayou, La------                                  ------------------------------------          495
La M arsh, Ill-..........------------------------                                                         1146
Lam oille River, Vt ....-.............................-                                                    153
Lamprey River, N. H-....                                                                                    53
Lancaster, Cayuga Creek, N. Y.......__..____________...                                         . ..      1228
Langellier, Ill...........------------------------1142
L'Anguille River, Ark-...                    .            .         .          .           .          545, 548
Lansing, Iowa, harbor ..... .. . . .. . . .. . .. . . .. . . .. . .                                        737
Larchmont Harbor, N. Y........-.                                                                           146
La Trappe River, M d-----.---------------------                ...........                                 218
Latrobe, Pa- .........-...           .----------------...-.                                               1025
Lavaca Bay, Tex., improvement of channel from Pass Cavallo to Port Lavaca.                                 587
Lavon Reservoir, Tex ...........----------------------------------------                                   609
Lawrence, Kans., Kansas River at_..........._____.____............                                         821
Lawrence, Mass ............------------------------                                                     57, 83
Lawrenceburg, Ind....                        -------------------------------------.                   944, 947
Lawrenceburg, Ky                                ----------------------------------------------             913
Lawrence Cove, Me....                          ----------------------------------------..                    6
Leaf River, Miss.....           ..          -------------------------------------------..                  448
L'eau Bleu Bayou,         La-------------------------------------------                                    517
Leavenworth, Ind --.....----------------------............                                           .     944
Le Carpe Bayou, La...........--------------------------------                                              495
Le Claire Lock (Cana), Iowa...                             --------------------------------------          734
Leech Lake Reservoir, Minn ____-......---...............                                            .      764
Leech River, Minn ........              .       .       .     .      .      .           ..       .         770
Leesville, Ohio, Reservoir-----.....------------------------------------                                   960
Leesville Reservoir, Va..---------------....--------                                                       289
Leetsdale, Pa ......                                                                                      1025
Lehigh River, Pa ...---------------------------                                                     190,191
Leipsic   River, Del ...----------                                                                       190
Leland    Harbor, Mich..-------------------------------------------                                     1109
Lemon     Bay, Fla...------------------------------------------                                          385
Lemon     Creek, Staten Island, N. Y-.......            ------------------------......                   146
Leon River, Tex ......-------------------------...                                                        620
Letart Falls, Ohio----------------------------------------------                             978
Letart, W. Va                               BK.K.naei..d.......... 978
Levees between Shelby Bridge and Baum's Bridge, Kankakee River, Ind ........                1148
Levees between New Athens and Carlyle, Ill_ _......................___             .      . 729
Levee unit 1, Little Wabash River, Ill_____.......__....       .____..._                     945
Levee unit 2, Little Wabash River, Ind.-....-.-.....-..           .......                    945
Levee unit 1, Eel River, Ind......................--------------------------
                                                                         --                  944
Levee unit 2, Eel River, Ind_...__....................                                       945
Levee unit 3, East Fork of White River, Ind ....             - ___....         ..
                                                                 . .........-.....
                                                                            --.. . .___ ...-
                                                                                         -   947
Levee unit No. 1, Wabash River, Ill-.....----__ _~..................
                                                             --.                             947
 1674                                                               INDEX

                                                                                                                                                Page
Levee unit No. 2, Wabash River, Ind...........                      ............--------------------------------                                947
Levee units 3 and 4, Wabash River, Ill. and Ind......                        ....     .....................--------                             947
Levee unit 5, Wabash River, Ind               -------------                ---          -------------....           -                           947
Levee unit 6, Wabash River, Ill              .........------------------------------------                                                      945
Levee unit 7, White River, Ind.....-------------------------------------                                                                        945
Levee unit 1, White River, Ind ....-------------------------------------                                                                        945
Levee unit 2, White River, Ind.....-------------------------------------                                                                        945
Levee unit 8, White River, Ind...-------------------------------------                                                                          947
Levee unit 9, White River, Ind...-------------------------------------                                                                          947
Levee unit 10, White River, Ind.................. ............................------------------------------------                              947
Levee unit 17, Wabash River, Ind             ........................ ..........-----------------------------------                             945
Levering Creek, Md---------------------------------------------                                                                                 211
Levisa Fork, W.               Va --........-----.-...                                          -------------                                    956
Lewis and Clark River area, Clatsop County, Oreg .---------------------------------------    1475
Lewisport, Ky., flood control .-----------              ------..----------------              945
Lewis River, Wash_____ ................ _______
         Lewis--River,--Wash------------------------------------------1452147          1452, 1473
Lewiston-Clarkston Levees                       ---------------------------------------      1540
Liberty (Bedloe) Island, New York Harbor, N. Y..-------------------------------.--            125
Libby Dam, Mont ...---------------------------------------------                             1514
Licking River, Ky                        -------------------------------------------      919,946
Lieutenant Run, Va---------------------------------------------                               275
Lisle, N. Y.........-----------------------------                                                                                              221
Little Bay (Aransas Bay at Fulton), Tex--------------------------------                                                                         601
Little Caillou Bayou, La .--------------------------------                                                                                     495
Little Choptank River to Choptank River, Md., waterway- -. __________-.-                                                   ---          _____  __ _-- 218
Little Cypress River, Tex----------                          ------                    -----                     --------------------                   517
Little Egg Harbor, N. J-------                 -------..........-.............                                                                          190
Little Elk River, Md.....                                       ......................--------------------------------------------                      218
Little Elm Reservoir, Tex. See Garza-Little Elm reservoirs-----------------                                                    -----------------        610
Little Harbor, N. H ..                ...                   ..-----------
                                                                 -------.-...-...-.......                                                                53
Little Harbor, Woods Hole, Mass ---.------.-------...........---------                                                 ------------------ 53
Little Hickman, Ky            ........                     .....................---------------------------------------------                           913
Littlejohn Creek, Calif ..........                       ............. ......-----------------------------------------                                 1377
Little Juaniata River, Pa ......                         .........................                                                                      240
                                                                                                                                ......------------------------------------
Little Kanawha River, W. Va                                  ...           ..--...               .......                                                956
                                                                                                                       ...........--------------------...
      Flood control reservoirs                           .....             ...........................---------------------------------------           980
Little Lake Harbor, Mich.....                            ...... .............------------------------------...............                             1050
Little Machipongo River, Va..                            ...... ...........................--------------------------------------                       288
Little Manatee River, Fla.......                                           ...                    .....                                                 401
                                                                                                                      ...........---------------------------------------
Little Miami River, Ohio, flood control reservoirs-----.....................------------------                                                          946
Little Missouri River, Ark..................----------------------------------                                                             528, 530, 532
Little Missouri River, Mont. and N. Dak ..................-----------------------------                                                                 853
Little Narragansett Bay, R. I-----.......................---------------------------------                                                               39
Little Pee Dee River, S. C ...........................----------------------------------------                                                          326
Little Pigeon Bayou, La..--                       ---------------------------                                              ---------------              495
Little Pigeon River, Tenn                                      -----------------------------------------                                                894
Little River, Ark. and La..               ........------------------------------------..............                                               528, 699
Little River, Del ...........................-----------------------------------------------                                                            190
Little River, Va........................----------------------------------------------                                                              -- 288
Little Rock, Ark.:
     Engineering district                                  ------------------------------------------                                                   643
     Arkansas River------------------              ---------------------------------------------                                                        668
Little Silver Creek, N. J-...-----..------ -----------------------                                                                                      141
Little Sioux River, Iowa                                   ------------------------------------------                                                   845
Little Sodus Bay, N. Y                                  ------------------------------------------                                                     1227
Little Tallahatchie River, Miss                    ....-----------           ---...                                      --------------- 528
                                                                                                -------...................
Little Tennessee River, Tenn.------..                   ..           .          ..                                                                      894
                                                                                             ... ...............................--------------------------------
Little Valley Wash., Utah.....----------------------------------------                                                                                 1400
Little Wicomico River, Va .--------------------------------------                                                                                       249
Little Willow and Wakefield Creeks, Minn...                                                  .....................................-------               784
Little Wood River, Idaho                     .........---------....--------------            .......---......--.----...................-----------.    1532
Liverpool drainage and levee district ............................................--------------------------------... 1148
Livingston Manor, N. Y., Vol. 2---------...            --------------------------------------                                                           193
Livingstone Channel, Detroit River, Mich ... ___.. ...                                                  .......... ............ .... 1161
Lobdell Canal, Del ..---------------------------------                                                                                168
Lobster Cove, Annisquam River, Mass------   ...               ...
                                                    -----...-.....                                          ..................         17
                                                                  INDEX                                                                                                 1675
                                                                                                                                                                          Pag
Lock and Dam No. 1, Tennessee River, Florence, Ala................                                                                                                       891
Lockport, Ky ...............................---------------------------------------------------                                                                          913
Locklies Creek, Va                   ...........................----------------------------------------------------                                                     258
Lockwoods Folly River, N. C .........................--------------------------------------                                                                              313
Logan Reservoir, Ohio .. . .... .. ............. .....                                                                                                                   980
Logansport, Ind --.                     ....            ..........
                                                            ---------------                                                                                               947
Loggy Bayou, La .....                      ..------------------------------------------..                     495
London, W. Va         ........---------------------------------------------------                             954
Lone Rock Reservoir, Ark .          .                            ------------
                                            ..----------------------                                           651
Long Beach, Mass..       .        .      .          .          .          .                                    27
                                                                                      ..-----------------------------
Long Beach Harbor, Calif ..-   .                                                                                                                                        1254
Long Creek, N. Y ..................-----------------                                                  --                                                                  96
Long Island intercoastal waterway, New York ...--------------                                                                                                             92
Long Island Sound, N. Y-....-                                 -                                                                                                           48
Long Tom R iver, Oreg ... . .. . . .. . . . .. . . .. . . . .. . .. . -                                                                                                 1464
Lookout Bight, N. C---------------------------------------------                                                                                                         313
Lookout Point Reservoir, Oreg..............                                             _. .-         . .       . ...----------                                         1459
Loosahatchie River, Tenn....                             ---------------------------------                                                                               548
Lopez Canyon Diversion, Calif ----------                             --.- -     -         -       -            --            -     -             -    -      -    -     1268
Lopez Flood Control Basin, Calif -.......                                                                                                                               1268
Lo rain H arb o r, O h io-... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                                                                           118 9
Los Angeles, Calif.:
       Engineering district            -...     -   -      -      -          -       -         -            -   -         -                  --        ----              1249
      Flood control on river ---- ---------------------                                                                        1266
      Improvement of harbor-...----                                                                                            1254
Los Angeles County drainage area, California .............                                                                    1266
Lost C reek, Ill -_---------------------------------                                                                          1148
Louisville and Portland Canal, Kentucky                                                                                         869
Louisville, K y..... . . . . . . . . . . . . . . . . . . . .                                                                    927
     Engineering district.              -           -           -           -           .               .         .             911
     Local protection..-                                                                                                        945
Lowell Creek, Alaska ....-------------                                                                                        1549
Lowell, Mass                                                                                                                 57,  83
Lower Cedar Point, Md.....-                                                        ---                    ---                   258
Lower Columbia River Basin, Oreg., Bank Protection Works.................... 1472
Lower M achodoc Creek, Va............                -         -         -      ............... ......                          258
Lower Monumental Dam, Snake River-.....-                                                                                      1528
L o we r M ud L ake , La ... . . .. . . . .. . . .. . . . .. . . .. . . . .. . . . .. . . .. . . . .. . . .. . . . .. . . .     4 88
Lower Rio Grande Valley, Tex.                                                                                                   602
Lower San Francisco Bay, Calif-.....                                                                                          1341
Lower San Joaquin River, Calif-........-                                                                           -          1383
Lower Thoroughfare, Deal Island, Md...-                                                                                         218
Lower Walla Walla River, Wash-.....                                                                                           1532
Lower Willam ette River, Oreg .......--------------------------                                                               1427
Loyalhanna Reservoir, Pa ....---                                                                  -            -              1012
Lubec Channel, Maine-..------------------------------                                                                            53
Lucky Peak Reservoir, Idaho-........                    .          .          .           .          .          .             1535
Ludington Harbor, Mich...............--------------------                                                                     1102
Ludlow, Ky                                                                                                                      945
Ludlow Reservoir, Connecticut River Basin, Vt....................                                                           69, 83
Lugert R eservoir, Okla ..-------------------------  -----                                                                                                               701
Lum ber River, N. C., and S. C                 -..---------------------                                                           ------------                           326
Lussenhop levee, Illinois ..................... --- -- -- -                                                                                                             1148
Lutsen Harbor, M inn ..             --------         --- - ---                                         - --          --           - ---                           - -   1050
Lycoming Creek, Pa ..-                                                                                                              --..                                 236
Lyford levee, Indiana --....-.-.-                                                                                                                      --                947
Lynche River, S. C                                                -..                                                                                                    326
Lynn Harbor, Mass .-..-...                                                                                                                                                53
Lytle Creek, Calif-..... . . . .                    . . . . .                    . . . . .                      . . . . .                             1288, 1294, 1298
                                                                         M

MacArthur Lock, St. Marys River, Mich..-..                                                                                              --             ---         .-   1153
M acataw a Lake, M ich . . ....                                         .
                                                        .........---------..                                                                                            1093
M achias R iver, M aine..... .......................                     .                                                              --             .
                                                                                                                                                      -53
M ackay Creek, N . C .....................                                                                                                                               313
1676                                                                    INDEX

                                                                                                                                                                                             Page
Mackinac Harbor, Mich., improvement ...... .................                             .                                                                                                  1178
Mackinac Island, Mich., to Round Island, Mich., channel improvement .---.......                                                                                                             1178
Mackinac Straits, Mich., improvement of Poe Reef Shoal....-..............                                                                                                                   1178
Macon Bayou, Ark. and La.............            ___-                -           -                                                                                                           528
Macon, Ga-................--------------------                                                                                                                                               344
Madison, Ind., flood control.............                                                                                                                                                    945
Mad R., Conn_                                                                                                                                                                                 82
Magna, Little Valley Wash., Utah                          ................                                                                                                                  1400
Magruder drainage district, Columbia County, Oreg ........................-...       . 1473,                                                                                                1475
Mahoning Creek Reservoir, Pa ..-.-.......                                              1004,                                                                                                1005
Mahoning River, Ohio .....-.....-.--.....-..   .    ..-                                                                                                                                      996
Main Ship Channel, New York Harbor, N. Y.-.......             .           .        .                                                                                                          53
Maintenance, Operation and Capital Outlay, Washington Aqueduct_             ....     _____                                                                                                   252
Malaga Island, Me., N. H ...........-                                                                                           -15
M alden R iver, M ass ....-....... ........................ ..............                                   ..-.....                       .                         .                       53
Malheur improvement district, Idaho ........                                                                 ____               .                       .                     .             1540
Malheur River, Oreg ...----    -- .                                                                                                                                                         1532
Mamaroneck Harbor, N. Y ______..-
                          .-....                                                      ____                                                                                                    146
Manasquan-Bayhead Canal, N. J...                                __..-..                    ___._____                                                                                          187
Manasquan Inlet and River, N. J                                         ---           --....                                                                  .                          185, 186
                                                                                                                                                                                        4...
Manatee River, Fla .....-.---...-                                                                                                                                                            401
M anchac Bayou, La ________.
                         _____.__________                                                                                                                                                    495
Manchester Harbor, Mass .-______-.______._...                                                                                                                 .                               53
Manchester, Ohio _-------------.-----                                                                                                                                                        978
M andan, N . D ak----- --------------   ------------------                                                                                                                                   853
Manhasset Bay, N. Y.______________..                                                                                                                                                         146
                                             __.____.__...
Manistee Harbor and River, Mich_..... ___.__.--.. ....                                                                                                                                      1104
Manistique Harbor, Mich                      .....                  .             .            .         .              .....       -   .                   ..--                            1053
                          _......-.
Manitowoc Harbor, Wis ......                                             .                         ...                                                                .                     1074
Mannford Reservoir, Okla...                                     --                                                                              -                                            644
Manokin River, Md. --...                                                                                                                                                                     218
Mansfield Hollow Reservoir, Conn                                          .                    .         ._________________..........
                                                                                                             -.-.                     65, 66
Mansfield Reservoir, Ind -....-.                                                                            --..-.....--                946
Manteo (Shallowbag) Bay, N. C __________....                                                                                                    .                                            303
Mantua Creek, N. J......                 .           .___..     .             .           ..                                                        .             .           .          163,177
Maple River, N. Dak ..........                                                                                                                                                               772
Mapleshade, Ohio ........                                                                                                                                                                    978
Marblehead Harbor, Mass ____.____..___.                                  ____                                     .                         ..                                                53
Marcus HIook, Pa .-...                                                                                                                                                            -.          163
Mare Island Strait, Calif                                                                                                                                                 .            1314, 1315
Marietta, Ohio                  -..-... __
                              ___.___                                                                                                                                                        978
Marion Reservoir, Kans.....                                            700
Mariposa Dam, Calif - ---------........                               1388
M arkham Ferry Reservoir, Okla ...............     ......... . -   696,700
M arm arth, N. D ak-------- --------------- ------- -------            853
Marmet, W. Va ..-............                                          954
Marquette Bay Harbor, Mich., improvement of harbor. See Presque Isle
  Harbor.
Marquette Harbor, Mich_____.____________                              1047
Marshall, Minn.....---                                                 790
M arshall C reek, Calif ....            . .           .   . .           . .           .        .     . .     . .          . .           .                   ..-               ----------     1268
Marsh Creek, Idaho______________.____________1532, 1534
M a rsh field, O re g . . . . . . . . . . . . . .-... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 4 8
Marsh Lake Reservoir, Minn., flood control ._..............                                __..
Marsh River, Minn...--                                            - - - - - --                     - - - - -                    772
Marshland drainage district, Columbia County, Oreg                                      - .    _______.__. ______..      __    1475
M arshyhope Creek, M d .-... . . . . . . . . . . . . . . . . . . . .                                                            240
M arthas Vineyard, M ass ................. ............-                                   - - - - - - - - -                     31
M artins Ferry, Ohio ___. . ____._______.__.....  .        .         ..                                                        1025
M arys R iver, O reg . -               .-....
                                           .................................                                                   1472
M ason and M enard, Ill ... __. ____..          .. -. __..                          .        .       .       .        .        1148
Masonboro Inlet, N. C .-------------- ------------                            --                                           299, 313
Mason J. Niblack levee unit, Indiana                                      -      .   ..
                                                                              _____..__..__.                                                                                                 945
Mason, W. Va.......                                                                                                                                                                           978
Massena Board of Control, operations of International                                                                     ...                               .........                        1643
                                                                 INDEX                                                                  1677
                                                                                                                                           Page
                     ..-
M assillon, Ohio ...--      -- - - - -------------                 ---        -956,                                                        978
Matagorda Bay, Tex                                                             .....     -
                                              --------------------------------------------..                                               558
Matanzas Bay, Fla..--------._                       -     -                                                                                362
Matawan Creek, N. J...----------------------------------.                                                                                  146
Mathews Canyon Reservoir, Nev.....-                             -    --      --      --                                                   1297
Matinicus, Maine-----------------.-...........--                                                                                            53
Mattapoisett Harbor, Mass .__.______.             ___~_                    ...                                                              53
Mattaponi River, Va..----------------------------------.                                                                                   288
M attituck Harbor, N. Y..................................                                                                                   89
Mauckport, Ind_.....      ____._____________                                                                                               945
Maumee Bay and River, Ind., Ohio.........-                                              1175,                                             1178
Maurice River, N. J _.______________________________                                                                                        190
M ayaguez H arbor, P. R..........................            --........                                                                        401
Mayfield Creek, Ky .....                                                                                                                       548
Maysville, Ky .......        ---.--.                                                                                                975, 978
McCook, Nebr., near Republican River                                                                                                  .        821
McCraney, Hadley, Kaiser, Six Mile, and Bay Creeks, Pike County, Ill                                                               -.......... 753

McGee Bend Dam, Texas -...-                                                 -         -            -             -          -       604,605
McGee Creek, Ill ...--..-                                                 -.
                                                                          ...                                                                  730
M cGinnis levee unit, Indiana-......................................                                                      .   -                945
McHenry Valley Creek, N. Y..........                       .                 ..                                                -               227
M cKees Rock, Pa               . . . . . . . . . . . . . . . . . . -.......1025
McKenzie River, Oreg. ... .              .             .           .             .             .                ..---------------------1472
McLean Bottom levee district No. 3, Arkansas River, Ark-............                                                                           668
M cLeod Lake, C alif.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                                                        1364
McNary Lock and Dam, Oreg-......                                                                                                              1529
M edom ak River, M aine ...--- __--                            ..-------------
                                                                 _                             ....-                                  _         53
Meherrin River, N. C.........                                                                                                                  313
Melbourne Harbor, Fla ---....--------..                                                                                                        401
Melones Reservoir (New), Calif_                                                                                                               1383
M elrose Reservoir, Va.........       .. .         . .           .               ... ..... .               .......                  __ 289
Memphis Harbor, Tenn                                                                            "                                              543
Memphis, Tenn.:
     Engineering district-.....               .            .                 ..                                        .            543, 545
M enem sha Creek, M arthas Vineyard, M ass... ............... ..................................                                                53
Menominee Harbor and River, Mich. and Wis .....................                                                                1055, 1081
M eramec Res., M o-...... .. .. .. .. .. .. .. .                                                                                               729
Merced County stream group, California ...........-...                                                                                        1388
Meredosia Lake and Willow Creek, Ill                                 --............-                                          -729,1... 730
Mermentau River, La.              .        .         .         .           .          .               .          .          .       488, 513
Merrimack River, Mass .............                                                                     ..            ...         16, 54, 56
Metlakatla Harbor, Alaska                                        ......                                                             -..... 1547

M etam ora Reservoir, Ind -------------------------------------                ....... .......                      ..-                        946
Metropolis, Ill .......                                                                                                                        945
M eyers C hu ck H arb or, A la sk a--------------------------------------------- .------------ ...........................                    1547
Miami Harbor and River, Fla.:
     Improvement of harbor.......................                                                                                              373
Miami to Key West, Fla., Intracoastal Waterway ....                                        ---------..                                         401
M ianus River, Conn ..------    ----------------..... ...                                                                                       54
Michigan City Harbor, Ind .....                                                                 .....                          __-. 1128
M iddleport, O hio ...... ... . . . . . . . . . . . . . . . . . . ..-....                                                                      978
Middle River, and connecting channels, Calif ........                                                                                         1369
Middle River, Md ....-..-.... ...---                                                                                                           218
Middlesboro, Ky ...             .          .             .              .               ...                                         895, 907
M iddleton Shoals Reservoir, Ga. and S. C                                                        ..--.-............................. 341
Midland drainage district, Columbia County, Oreg                                                                               1473, 1475
Milan, Ill                                                                                                                  -   -- ..          751
Miles City, Mont __________.        _____                                                                                        _. -.. 865
M ilford H arbor, Conn ...........................                                                                                              46
M ilford H aven, Va ... .                      --     --     - --       --    - --       -    --     --     - --      -        ------
                                                                                                                            ---.-          258
M ilford Reservoir- - - ------------------------------------------- -------                  798
Milk River, Mont ___ __________________-_.                                              862, 865
Mill Creek and South Slough, Illinois                           .............-      -        751
M ill C reek, Ind --- - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - -
Mill Creek Levees, Santa Ana River Basin, Calif                          .......---   1294, 1298
1678                                                          INDEX

                                                                                                                                    Page
Mill Creek, Md .....                                                                                                             218
Mill Creek, N. C .....                                                                                                           304
Mill Creek, Va ....                                                                                                              258
Mill Creek, Wash .-                                                                                                 ______1532, 1538
Mill Creek, W est Fork, Ohio .....................................                                                  .....924, 946
Miller, Ohio .....
              _                                                                                                                  978
Miller Pond, Drainage District, Ill_                                                                                             713
Millers R., Mass .. .            .    .   . .          .    .      . .        ..    .                                             75
Millersburg Reservoir, Ohio.....                                                                                                 980
M illers Ferry Lock and Dam, Ala .................. ..................................                                           433
Millers Run, Pa ..      .      .    .      ......               ......                                                           236
Mill Four drainage district, Yaquina River, Oreg                        _                                                       1476
Millicoma River, Oreg ......                 .            .              .       .                                              1452
Mill River, Conn ....................................                                                                             54
Millwood   Reservoir,     in Red   River    Basin,       Ark..____...........____..                                              699
M illwood, W . Va ............. ......................                                                                           978
Milton-Freewater, \ alla Walla River, Oreg                                                                                      1537
Milton, Ky ..............-                                             -                                                         945
M ilton, M ass ..- -......         .. ..                                                                                          23
Milwaukee, V     is :
       Engineering district .-..                                     --                                                                   1053
     Improvement of harbor..-                                                                                -                            1080
Mingo Creek, S. C....                                                                                                                      326
M ingo Junction, Ohio...... ................. .... . . . . . . ..                                                    .                    1025
Minum Creek, S. C                       --.......................             -...               ..                                        316
Mining City Reservoir, Ky ..........                                                     .                                                 946
M innesota River, M inn .......             .          .................                        .. .................        ........ 7, 7 785
Miscellaneous civil works ...-                       -.....                                                                               1639
Mispillion River, Del ...                --                                                          -                                     190
Mission Bay,Calif ....              . ..                ........                                          .                               1263
Mississippi River:
                                                                                                                                           756
     At Canton, M o ..............-
     Baton Rouge to Gulf of Mexico, La
     Between Ohio and Missouri Rivers___.._...
                                                                 -          --- -- ---..   .......
                                                                                  _.______.__.._____
                                                                                     _____._______                 .
                                                                                                                                           473
                                                                                                                                           706
     Brainerd and Grand Rapids, Minn                                                                             __                        770
     M issouri River to M inneapolis ...                                               .
                                                                         _______________._______.      ..         _. _     .... 709, 733
          Locks and dam s... ...............                                                                                               734
     Near Aitkin, Minn...............                                                                                                      784
     Reservoirs at headwaters . -...........................                                                                               764
Mississippi River Commission:
     Report of the President ....................
                                                --                        .........        .                                              1575
          Flood control on lower Mississippi River:
               Alluvial valley flood protection and mapping_______                                                                 _1585, 1588
               Arkabutla Dam and Reservoir, Miss ._______________________..                                        .                      1584
               Arkansas River levees --..-..                                                                                              1598
               Atchafalaya floodway, Louisiana_                                                                                    1590,1601
               Atchafalaya River and Basin, improvements                                            ..........                        . 1580
               Bank protection, works                     ..........      ...      _....                                            -     1605
               Bayous Rapides, Boeuf and Cocodrie, La .......                                                                      1585, 1581
               Boeuf and Tensas Basins, La. and Ark_                                                                                      1582
               Bonnet Carre spillway, I ouisiana _____-.___                                                                               1593
               Cairo to Baton Rouge, navigation channel __..                                                        ..                    1585
               Channel, improvements ........                                                 .....                   .                   1619
               Enid Dam and Reservoir, Miss .                                       .         ..                                          1584
               Existing Project .......                                                                                                   1578
               Grenada Dam and Reservoir, Miss .. ....                                                         __                   . . ..1584
               Lake Pontchartrain, La                                                                 __________                          1593
                                                                                                                                   1....585,
               Le ve e s ... .. .. ... .. ..------......  --....
                                                            -.-                -.-.....
                                                                                .. ... .. .. ...... . .. . .                      ... _ 1612
               Mississippi River Improvements ............                                                                                1579
               Mississippi River Tributary and outlet improvements_                                                                       1580
               Morganza floodway, Louisiana .. ____________                                  .__._                                 1585, 1592
               Organization .-----------------------------                                                 .            .                 1576
               Previous Projects -.....-.. __- --...........                                                                              1577
               Sardis Dam and Reservoir, Miss...                                                                                          1584
               St. Francis R iver Basin..                               ........... .-..... ......... ... ____                              ..
                                                                                                                                          1584
                     M emphis Harbor Project-..................... ...                                                  __         1.585, 1604
                                                           INDEX                                                                                    1679
                                                                                                                                                     Page
Mississippi River Commission :-Continued
              Surveys, gages and observations ..........................                                                                             1588
              Tributary Dams and Reservoirs ............................              -- ---                                                         1584
              Wappapello Dam and Reservoir, Mo ........                  .-.-    ---.  - -                                                           1584
              Yalobusha River, Miss ...........                                                                                                      1584
              Y azoo R iver B asin ..................................       --------- 1584,                                                          1594
              Mississippi and Leech Rivers, Minn .....................                                                                                770
Mississippi Sound, Ala. and Miss ...                                                                                                                  442
Missouri River:
    Agricultural levees
      Kenslers Bend, Nebr., to Sioux City                                                   -..                               839
                                                                                                      .................---........
      K ansas City D istrict - -...................                                         .......                           797
      Omaha District -.. ------                                                                                               8;31
    Garrison D istrict --....................                         .      ....                                             849
    Fort Peck D istrict                                ..............              ................... .............. 861      .......
    A t Fort Peck, M ont ....................--                                   ................                            857
    Kansas City to mouth                                                -....-..                                              793
    Kansas City to Sioux City ._---------- .---------                           ---- --           _                           825
    Sioux City to m outh .......-- . . .. . . . .                                   .........         -- ~.-....--- --- -- - ...79 9 , 8 4
    Sioux City, Iowa to Fort Benton, M ont ...............................                                                    829
M obile, Ala., engineering district ..-....................                                                                   413
Mobile Bay, Harbor, and River, Ala .......                                                    -.--.-.. . . . -----414 , 4 27
M ohawk R eservoir, O hio --...............................                                                                   960
Mohawk, Hudson and Waterford Rivers, N. Y ..........................                                                          153
Mohicanville Reservoir, Ohio ........                                                                                         960
M ojave River, Calif                                                                            -....   . . ....... . - 1298 - ---
M okelumme River, Calif ..............                          .... .. . . . . . . . .                                      1369
M olalla River, Oreg ..................................                                                                      1472
Monarch, Wyo ......                                                                       ---..                               865
Monett, Mo               --------.........                                                                                    7C0
Monongahela River, W. Va. and Pa ..........                                                                                   989
    L ocks and D am s._ .................................                                                                     992
    Flood control reservoirs ..................                              ...........                                     1025
Monroe Bay and Creek, Va ...                                                                          -...----------------- 258, 266
Monroe Harbor, Mich -.... .                     .       .         .              ..            .                             1178
M onroe, La.....-- .... . . . . . . . . . . .. .. . . . . . .                                              -------- 525, 529, 538
M onterey Bay and Harbor, Calif ......                        .---------......... . .                                       1328
M on tezuma, G a...........................................                                                                   453
M ontour Falls, Oswego River Basin, N. Y .....................-.-...........                                                 1233
Montville Creek, N. Y                                                                                            -.....-..           ..         -    1236
M oorefield, W . Va .....-- ..... .. .. .. .. .. ... .. .. .. .. .. ..                                                                               266
Moore Haven Lock, Fla .......              ..                    .                                                                                   379
Moores Ferry Reservoir, Va -...                                                                                                                      980
Mooringsport Reservoir, La ...............                     -. __.-.--------.                                                              . 497 , 519
M oosabec Bar, M aine .                .        ......                      .              - -..         ....     . . . .                             54
M oose R iver, Vt-.............. ...................                                       ........                                             ... 71
M orehead City         Harbor, N. C                      -..-..--.......................                                                         . . 306
                                                                                                                                          ... . ...
M organ C ity, L a ....-.. .. .. .. .. ....             ...------...............                                                               .... 495
Morgantown Lock and Dam, W. Va -.......                     ... .        .        .                                                            ... 992
Mormon Channel, Calif ...... .             .          .          ..             .        -- --- 1364, 1368
Morrilton West of, Arkansas, flood control ..................                                              668
Morrison, Colo -....-.                              . .           .        .         .           .... 845
Morristown Harbor, N. Y....................                                            .         ---     1227
Morro Bay, Calif.- - -                         .. .....        .             .                           1249
Moscow, Ohio ..... ......... ..                                                                            945
M osquito Creek Reservoir, Ohio              .......       ... . ................ ..........             1019
M oss Bluff Lock and Dam, Ila ........................                            ..                       355
M oss Landing, Calif ...-                       - .. .... ................                               1326
M oundville, Ala-......                                        -----------------                           438
Mounds and Mound City, Ohio River Basin, 111.........................                                      546
M oundsville, W . V a -      --..  ....-................            .............                        1025
Mountain Brook Reservoir, Merrimack River Basin, N. H ...... -....................                   . 5 7 ,83
Mount Clemens, Clinton River, Mich .................                                                     1182
Mount Holly, Rancocas Creek, N. J..                                                                  . 192
Mount Hope Bay, Mass ......         ..... ...                                                               34
Mount Morris Reservoir, Genesee River, N. Y ............                                                 1231
1680                                                  INDEX

                                                                                                                  Page
M ount Vernon, Va...............................     ..................                                           258
M outh of Sangamon River, Ill ....................... ........                                                   1144
Mouth of Trinity River, Tex ...       -.      .    .       ..................                                     601
Mud Lake area, Idaho .........      .            .          ...                                                  1532
Mud Mountain Dam, W ash .. . . . . . .                     .......................                               1521
Mulberry Creek, Va....-.......                                  ...                                               258
M ultnomah Channel, Oreg :__    _____------------------------   .                                                1452
Multnomah drainage district No. 1, Multnomah County, Oreg                                              ._1473, 1475
M uncie, Ind .....-- - - - - - - - - - - -                 - - -        --       -----------                      947
Murderkill River, Del........-----------..
                                     ..                                                                           173
Murfreesboro Reservoir, Ark -..................                                                      --------529, 535
Muscatine, Iowa, harbor -.-.-..         .         .      .                                .                       737
Muskegon Harbor, Mich --... .            .      .   . .    .                          .        .                 1097
Muskingum River, Ohio -...............................---                                                         949
      Locks and dams-----
                     ...-------                                        --    ---                                  951
    Flood control reservoirs ..............................                  --........              _958, 960, 980
M ustang Creek, La ............................                                                                   517
M ustinka River, M inn ...-...............................-.                                                      772
Myrtle Beach, S. C ...
                     ___                ---                                                                       316
Mystic River, Conn .....           .        ..          .    . .             .         .        .                  54
Mystic River, Mass                                                                                                 54



Nameoki Drainage and Levee Dist., Ill..-                                                      -                 725
Nandua Creek, Va-...----------------.-                                            -   -        -                288
Nansemond River, Va.................................                                                            288
Nantasket Roads, Mass-.                  .           .         .           ..           .                 20, 21
Nanticoke, Pa ..-..-                                                               --     --                    240
Nanticoke River (including Northwest Fork), Del. and Md                                                         218
Nantucket Harbor, Mass.:
    Harbor of refuge-...                                                                                         54
Nantucket Sound, Pollock Rip Shoals, Mass                                                     .-...              31
Napa River, Calif-.-- - - - - -               - -    -  -   -    -  -  -   -                     1314,        1345
Naples, Fla., to Big Marco Pass., Fla.:
    Channel improvement .......                 ....        ....       ....--                                   401
Narragansett Bay, R. I .                                                                                         36
Narraguagus River, Maine -...                            --                                           -......... 54

Narrows Channel, M ass-.................... .-...-.-                                             .--             20
Narrows of Lake Champlain, N. Y. and Vt -..-.-.             ..--......                                          122
Narrows Reservoir, Ark               . . . . . . . . . . . . . . . . . . .---
                                    -..                                                                         533
Naselle River, Wash ..................... ...          ----------------------------                           1511
Nashua, Merrimack River Basin, N. H-....-----------------------.---..----                                 57, 83
Nashville, Tenn., engineering district.....-                                                -                   879
Natalbany River, La..                                                                                4......----------------------
                                                                                                                517
Natchaug River, Conn                                                     ...-...
                                                             ---------------------..                                66
Natchitoches Parish, La...---------------------------.                                                      497, 507
Natrona, Pa ...      --------------------------------                 --                                          985
Navidad River, Tex.---------------------------------------------587
Nawiliwili Harbor, T. H ..-                                       ---      ---     ---        --.----------      1329
Neabsco Creek, Va..... -------------------                                                                         258
Neah Bay, Wash-...-                                               -            -              -                  1487
Neale Sound, Md---------------------------------------------                                                      258
Near Dardanelle, Arkansas River, Ark ..-------------------------------------..                                     668
Near Springfield on Sangamon River, Ill..------------------              -                                       1148
                                                                               .........-----------------------------
Neches River, Tex......................------------------------------------------551,604
Neenah Channel, Fox River, Wis.......----------------------------------                                          1062
Nehalem Bay and River, Oreg                --------.........------------------                                   1439
Nehalem, Oreg ....--------------------------------------------------                                             1476
Neodesha Reservoir, Kans....---..........-----------------------------------696, 700
Neosho (Grand) River Basin, Kans .                  .....---------------------------------- 687
Neponset River, Mass.---------...........-----------------------------------...                                     23
Neuse River, N. C..       .................----------------------------------------------                         313
Neversink River, Pa                         --------------------------------------------                           190
Neville Island, Pa........                 --------------------------------------------                          1025
New Albany, Ind.....                                                                                        930, 945
                                                                                                        ....----------------------------
                                                                          INDEX                                                                        1681
                                                                                                                                                            Page
New Amsterdam, Ind .........                        ..........                                                                                                         945
Newark Bay, N. J ....................               ....                   .......                                                                            .        133
Newark, Ohio ....................---------------------------------------------                                                                                    62,978
New Bedford and Fairhaven Harbor, Mass                                                     ............................... 33,54
Newbegun Creek, N. C...                                                                                                                                                313
N ew B oston, O hio............................................                                                                .............                           973
New Buffalo Harbor, Mich .............                                                                                                   .                           1140
Newburyport Harbor, Mass ..........                               .                      .........................                                                      15
New Cumberland, W. Va... ... . ..--------------.........................                                                                            . .              1025
New Don Pedro Reservoir, Calif-..........------------------------                                                                                                    1384
New England Division.................---------------                                                                                                                      3
New England-New York Inter-Agency Committee .........                                                                                                                1236
New Harbor, Maine................-----------------                                                                                                                      54
New Harmony Bridge, Ind                                                                                                                                         93------------------.------
                                                                                                                                                                  38,945
New H armony, Ind. .............-------------- -- ------...........                                                    ..........                                      945
New Haven Conn., breakwater ..........----.............                                                                                                                 54
New Haven Harbor, Conn ......                       .              .             .                   .                      ..                            .             54
New Haven, Mo........-------------------------------                                                                                                                   822
New Jersey and New York Channels, improvement ...............                                                                                                          129
New Jersey Intracoastal Waterway .............................                                                                                                         187
New Kensington, Pa-........---------------------------                                                                                                               1025
New London Harbor, Conn .......-------------......            ..                                                                                                        41
New M artinsville, W . V a - -....................                                           ............                           ...........                        978
New Matamoras, Ohio                             .                    .                       ...- -..                                                                  978
New Melones Reservoir, Calif .......                                 ...                                                                        .                    1383
New Orleans, La.:
    Engineering district .....                                                                                                                                         455
    Improvement of Intracoastal Waterway to Apalachee Bay, Fla..................                                                                                       414
    Harbor ..---......-------------------------------------                                                                                                            477
Newport, Ark ...-------...                                                                                                                                             668
Newport Bay Harbor, Calif ......... ..--------------.--.                                                                                                             1257
Newport Harbor, R. I.....-                                                                                   --                                                         54
Newport, Ky............                                                                                                                                                919
Newport News Creek, Va ......--......                                                                                                  .                               288
Newport News, Va., improvement of channel to .....                                                                                                                     277
Newport, Ky-...      .--.. .                             .          .         .           .            .             .               . .                    .          945
Newport, Oreg .........                    .........                          .........                                   .....                      ...             1443
Newport, Ohio . ..          ..        . . ..--.....                                                                                                                    978
New Richmond, Ohio ...                                                                                                                                                 945
New River, Fla .....                                                                                                                                                   401
New River, La ..... .                                                                                                                                                  517
New River, N. C .......                                                                                                                                           )9, 314
                                                                                                                                                                29...----------------...29
New River, Va. and W. Va ... . . . . . . . . . . . .                                                                           .. . . . .                             956
New Rochelle Harbor, N. Y ......-----------...             ..                 .                  .                 .               .                   .               146
Newry-Old Pickens Reservoir, S. C                                  .        .         .            .             . -.... .
                                                                                                                 -.                  .            .         .          341
New Savannah Bluff Lock and Dam .................-------------------                                                                                                   338
Newton Creek, N. Y ...........................-----------------------------------------                                                                                241
Newtown Creek, N. Y.......                        .                .                .                     .                    .                      .                146
New York and New Jersey Channels ..........                                         ..                      ..                  ..                    ..               129
New York Bay and Harbor, N. Y ............                                                                         ......                                              111
    Barge Canal ...            ...      .....................---------------------------------------
                                         .                                                                                           .             ---                 119
    Drift, collection and removal-----.......                                          ------------------------...                                                     128
    Entrance Channels and Anchorage Areas ............                                                                   ....                ..                        125
    Supervision- ._.... .. . . . . . . . . . .                                            ...............--                            . .-------------------------    143
New York engineering district-----           .......---------------------                                                                                               87
New York (Southern) Flood Control Project ...-......-                                                                                                                  219
Nezpique Bayou, La......                 ......-----------------                   -- .                  --.                                                           488
Niagara Falls, supervision of power ......-........                                                                                                                  1217
Remedial works.................------------------
Niagara River, N. Y .................. ...                     ....             ....------------------   --...........                                               1216
Niagara Special International Board ..............--------------......                                                                                               1642
Nicaraguan Canal survey ......----------.-. .                                    .                   .                 .             .                    .          1635
Nicholasville, Ky...............------------------.                                                                                                                   913
Nimrod Reservoir, Ark ....                                                                                                                                            666
Niobrara, Nebr .....           .           .              .              .                 .                   .                           .            .             845
1682                                                   INDEX

                                                                                                                     Page
Nishnabotna River, Iowa.............------------------------                                                           845
Nixes Mate Shoal, Mass ...............                 ----------------------------------------                     20, 21
Nolin Reservoir, Ky.......-....-...----------------------------946
Nolin River, Ky---....      --........-.....----------------------                                                     914
Nome Harbor, Alaska..............                   -------------------------------------------                       1543
Nomini Bay and Creek, Va..........                         --------------------------------------                      258
Nonconnah Creek, Tenn ............                      ------------------------------------------                     545
Nooksack River Basin, Wash ..-----------------                                                           -      -     1481
Norfolk Harbor, Va.:
     General improvement, including main channel of Elizabeth River and
       portions of southern, eastern and western branches .___... ..                                   . ______.       278
Norfolk, Va., engineering district...________________.........._____                                                   269
Norfolk, Va., to Beaufort Inlet ...                            ---------------------------                        285, 299
Norfolk, Va., to the sounds of N. C., waterway..-.................                                          ---        313
Norfolk Reservoir, Ark ...............................                                                            651, 656
Normal, Ky----....-----..-.                   ..--------------------                                                   978
North Adams, Hoosic River Basin, Mass-- -....                      _________________. ._____       ..                  146
North Alexander Drainage and Levee District, Ill                       111..-...............                  _        711
Northhampton, Mass----...................--------------------------70, 83
North Andover, Merrimack River Basin, Mass-.._______._________________-___....57, 83
North Canadian River, Okla ....                     -------------------------                                     676, 700
North Canal, Tex. See Buffalo Bayou, Tex                                                                               599
North Concho River, Tex-                         -               -           ---                                       622
North Cove, Old Saybrook, Conn......                                                                                    44
N ortheast H arbor, M aine- . .....--------------.- -------------------.................................                  4
Northeast River, Md..--------------------------------------------                                                      218
Northeast River, N. C..----.._                           ----------------                      -----              311, 313
N orth Fork of R ed River... .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . ..                                      701
North Fork of American River, Calif ..-..-..               ....--
                                                             .                                                        1349
North Hartland Reservoir, Connecticut River Basin, Vt..................................- 69, 83
North Landing River, Va...-----------------------------------                                                          284
North Little Rock, Ark-........            ----------------------------..                                              668
North Little Rock to Gillett, Ark. (below Plum Bayou)-------------------         .......---                            661
N orthport, Ala. ........ . . . . . . . . . . . . . . . . . . . . . . . .                                              438
Northport Harbor, N. Y------....--------------------------.-                                                -          146
North Portland Harbor, Oreg .-...                        .            .            .         .          .             1452
North River, Ga....-----------------------------------------------                                                     340
North Springfield Reservoir, Connecticut River Basin, Vt..-.-..                                                     69, 83
Norwalk, Conn ......---  .                                                                                              83
Norwalk Harbor, Conn..                   .           .           .         .            .            .    .             49
Norwich, Conn                     -----------------------------------                                               65, 83
Noxubee River, Ala. and Miss .---------------------------------                                                        448
Noyo River and Harbor, Calif ......                            --------------------------..-                          1305
               NubnuitBrokN.H---------------
N ubanusit B rook, N . H ..._____._____.
                                   ..                                                --------------------------
                                                                             ._______..              .       .          559
Nubble channel, Mass..... ----------------------------..                                                            20, 21

                                                            0
Oahe Reservoir, S. Dak. and N. Dak                        .
                                                   -------....            -------------------------             832
Oak Bay to Port Townsend Bay, Wash., waterway improvement-................                                    1489
Oak Creek, Md., channel to Plain Dealing Creek .........                         .      .      .      .___ 218
Oakford, Ill ......                                          .....-----------------------------------         1148
Oakland Harbor, Calif..........--....-                                   -. --------------------              1320
Oak Orchard Harbor, N. Y                                                            .1227
                                                                  .__.__________._______.____
                                                               ...._
Obey River, Tenn ..........------------------....                                                         894,901
Obion River, Tenn-                                                  -     --------------------            545....-..-----
                                                                                                         545,548
Occohannock Creek, Va.            ..--- -----------------..------         ----                                  288
Occoquan Creek, Va ..----------------------------------                                               -         258
Ocean City Harbor and Inlet, Mdv...----------------------------                                          5- 215
Ocklockonee River, Ga. and Fla -....                        ----..----------------                        416, 448
Ocmulgee River, Ga            ...         -----------------------------------------                       340,344
Oconee River, Ga              ......-------------------------------------                        ---------      340
Oconto Harbor, Wis ......              ------------------------------.--                                      1057
Ogdensburg Harbor, N. Y.---------------------------------                                                     1225
Ogleton L ake, M d...           . .      . .      . .      . .      . .      . .      . .      .    .    .           218
                                                                 INDEX                                                                   1683
                                                                                                                                          Page
Ohio River:
     Flood control in basin:
         Huntington district--                 ------                 --........-------------------                                             977
         Louisville district ---..............-------...                                    ....                                 ....-------------------...
                                                                                                                                                 943
          Nashville district            .........               .....................----------------------------------------                   906
          Pittsburgh district-----.........                     .......................----------------------------------                      1023
     Improvements:
          Locks and dams, construction .....................                                                                      869, 871, 872
                                                                                                                ..------------------------...
          Open channel work .---------------------------------------                                                                            875
Okeechobee-Everglades area ---------.---.-----                                                     ...-------------------- 402
Okeechobee Waterway, Fla ............------------...                      --------..--------------------.......                                 378
Oklahoma City, floodway, North Canadian River, Okla __.-- -____..............                                                     ______        679
Oklawaha River, Fla-----.                 --.............----------------------                                                                 354
Olcott Harbor, N. Y-                    ----.-
                                   ..--..--                                                       ---------------------    .....               1227
Old Hickory Dam and Reservoir, Tenn _--..............................
                                                                _____-                                                                     _-_____________
                                                                                                                                                883
Oldmans Creek, N. J ......--------------------------------------------...                                                                        190
Old Pass Lagoon, Fla                                                                            -----------------------     .----......-..- 427
Old River, Calif                                                 .------------..                                                .......-----------------------------
                                                                                                                                               1360
Old River, La..........-------------------------------------------------                                                                        456
Old River, Ohio...                                                                                                                   ....----------------------------
                                                                                                                                               1193
Old River Channel, Everett Harbor, Wash                                                                -------------------          .....---------.....
                                                                                                                              .........        1491
Old Town Creek, Miss ..--                     -------........                                      ---------------------                        448
Olean on Allegheny River, N. Y...--------------------------------..                                                                     997, 1025
Olentangy River, Ohio.._____ _________-----------------------------                                                                             974
Olympia Harbor, Wash.........------------------------------------------                                                                        1504
Omaha,   Nebr.:
     Engineering district-----.........-------------------------------------                                                                    825
     Missouri River Basin......-----------------------------------------...                                                                     844
Ompompanoosuc River, Vt                                                                                                                           71
                                                                                                                          ........--------------------------------
Onancock River, Va....--........---------------------------------------------                                                                   288
Onondago Creek, N. Y..                                                                                                    .........-------------------------------
                                                                                                                                               1235
Onset Bay, Mass-.........--   ---     ------...-...                                                                                  ..-----------------------
                                                                                                                                                  29
Ontonagon Harbor, Mich .....                            ----------------------------------------                    .............              1041
Oologah Reservoir, Okla                                                                                     ..        ..............------------------------------
                                                                                                                                                685
Oostanaula and Coosawatte Rivers, Ga....                                 ... -------------------------------
                                                                                       .                    ..        ....... ... ..            448
Operation Snowbound:
     Omaha District-----........                                                                                      .......------------------------------...---
                                                                                                                                                845
Optima Reservoir, Okla ----...............----------------------                                                                                700
Orange County, Calif                                          .                                                .....................------------------------------
                                                                                                                                               1287
Orange River, Fla....--.....................------------------------..                                                                          401
Orange, Tex....-                           --------------------------------------------------                                                   553
Oregon Inlet, N. C....---------------------                                                                      ---------------....................
                                                                                                                                                304
Oregon slough, Oregon                                                ....---------------------------------- 1420, 1428, 1452
Orleans, Ind....-------------------------------------------------                                                                               947
Orowoc Creek, N. Y ..............................---------------------------------------------                                                  146
Ortona Lock, Fla..-----------------------------------------------                                                                               379
Orwell Reservoir (Otter Tail River), Minn                                          ------              ....... ....................             772
Osage River, Kans. and Mo .......-----...................----------------------------------                                                     820
Osceola Reservoir, Mo.....------------...................-----------------......                                                                820
Osoyoos Lake Board of Control.........................------------------------------------                                                     1646
Oswego Canal, N. Y.............................---------------------------------------------                                                    120
Oswego Harbor and River, N. Y.........................................--------------------------- 1222, 1233, 1236
Otego Creek, N. Y .....                   -- ---------------------------------------------- 220
Otselic River, N. Y------......                                                                                         ...........----------------------...
                                                                                                                                                221
Ott Bayou, Miss....----...                                                               ......        ...              ..............-----------------------------
                                                                                                                                                443
Otter Creek, Vt.........                                                                        ......        ..          ...........--------------
                                                                                                                                                146
                                                                                                                        ..-----------------------------
Otter Tail River, Minn                                                        ... ......               ..                                       772
                                                                                                                       ...............-----------------------------
Ouachita River and river system, Arkansas and Louisiana---------.....                                              . -----..... 523, 529
     Locks and dams ..-----                                                                                                                     525
                                                                                                                                .--------------------------
Ouleout Creek, N. Y .....                                                                                              ...............-----------------------------
                                                                                                                                                220
Overflow Creek, Ark. and La.....                                                                                                                529
                                                                                                                       ...............-----------------------------
Overton-Red River Waterway, La                             ...                                                         ...............-----------------------------
                                                                                                                                                495
Owensboro, Ky.............                           -------------------------------------------....                                            945
Owens Dam and Reservoir, Calif ..........................                                                                 .........       1389
Owls Head Harbor, Maine --     ----------.......                                                       ...      .......      .........      54
1684                                                        INDEX
                                                                                                                          Page
O xford, N. Y .-.. .....................
                                   .. ... .... ..... .... ..... .... ..... .... ....                                       221
Oyster Channel, Va .__..................                                                                                   288
Oyster Creek Channel, N. J..............         .      .      .    .     .      .                                         183
Ozan Creek, Ark....-----------------------------------------------                                                         533
Ozark Dam and Reservoir, Ark .............                   .        .     .----------                                    6....
                                                                                                                           645
Ozona Channel, Fla...... . . . . . . . . . . . . . . . . . . . ..                                                          401

                                                              P
Pacoima Wash Channel, Los Angeles, Calif .................. __........._                                       1268
Paducah, Ky.....----------------------------------------940,                                                     945
Pagan River, Va..............         ---------------------------------------                                    288
Paint Creek Reservoir, Ohio -------------                                                                        980
Painted Post, N. Y ..............      . . . . . . .                 . .           . ..          . .             224
Painted Rock Reservoir, Ariz...__.......                                                                       1296
Pajaro River, Calif ....-.--.-----.--.....                                                                     1345
Palatka, Fla ...........  - - - - - - - - - - - - - - - - - - -                                                  401
Palm Beach, Fla.:
     Beach Erosion Control---------------------------                                                            401
     Harbor                            ---------------------------------------------------                       401
     Channel.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                                       401
Palouse River, Idaho, Wash., Oreg .............................----                                            1532
Pamlico and Tar Rivers, N. C ---...--..--------                                                                  313
Pamlico Sound, N. C.:
     Improvement of waterway to Avon, N. C. ...                              .
                                                                         ________...      ___________            305
     Improvement of waterway to Beaufort Harbor _.........-...                                      _            313
     Improvement of waterway to Rodanthe, N. C_                         _____-_.........
                                                                                     ____..                      313
Pamunkey River, Va ..........---------------...-                                                   -             288
Panama City Harbor, Fla ---........---------                                                                     448
Pantego Creek, N. C ...............................                                        . -        --         313
Panther  Creek Levee,
       PaterCek            Ill .....___                    . . . . . .
                    eeel------------------------------------------------------14   ..          . . . .
                                                                                           . __._____..        1148
Parish Creek, M d-.........                                                                                      218
                                                                                                  . --- .....................................
Park River, N. Dak                                                       --                              7..............--------------
                                                                                                         771,778
Parkersburg, W. Va--..-.........                                                                         964,978
Pascagoula Harbor and River, Miss....---------------------------------
Pasquotank River, N. C., waterway from Norfolk to The St. Johns River
Passaic River, N. J........---------------------------------------------
                                                                                                           -.. .
                                                                                                         284, 314
                                                                                                                 448
                                                                                                                 133
Passamaquoddy tidal power project, Maine                                       ....-.-...                          54
Pass Cavallo, Tex-.....-----          ---------------.....                                               558, 561
Pass Christian Harbor, Miss                                      ....................-.-.-------                 448
Patapsco River, Md -__--                                     __
                                                              -           --                     --                        195
Patchogue River, Conn .......... . . . . . . . . . . . . . . .                                                    95
Patriot, Ind                            ---------------------------------------------------                     945
Patuxent River, Md ........---------------------------------------------                                        258
Pawcatuck River, R. I., and Conn-.---------------------------------                                               39
Paw Paw River, Mich...                             --------------------------------                            1087
Pawtucket, Blackstone River Basin, R. I _______..____.____.
                                                        -.                     _________.._ .                     83
Pawtucket (Seekonk) River, R. I. .......                ...................                              38, 39, 63
Payette River and Valley, Idaho_.                -______----                                                   1532
Peace River, Fla ---   .............---         --                                                              387
Pea Patch Island Dike, Delaware River, Pa..--........                        .    .           .            ...   163
Pearl River, Miss. and La_____.________            _______                                          445,448,452
     Locks...--------.------..                                   . . . . . ..                       ......      446
Pecan Bayou, Tex                                            ---....-------      -   ---------------         621,625
Peconic River, N.         Y .............................                                                 ....-----------------------
                                                                                                                            146
Peekskill H arbor, N. Y---- -- -- -- -- - -- -- -- -- -- -- - -- -- - - -- -- -- -                                        146
Pekin and La Marsh drainage and levee district, Illinois -                                                               1146
Pembina River Reservoir, N. Dak                  . _...        . ...--.-
                                                                       . .   .     .771,                                  788
Pembroke Creek, N. C -...-                                                                                                313
Pemigewasset R., N. H-...........--------------.
                                               -                                                                           58
Pendleton Umatilla River, Oreg ..           ..                                                                          1540
Pend Oreille River and Lake, Idaho .....            -----------------------------                                       1516
Peninsula drainage district Nos. 1 and 2, Multnomah County, Oreg-.........-...1473,                                     1475
Pennington, Ala.      --....                                                                                              438
Pennington Bayou, Ark                     .       .       .....-...-..
                                                           ...                   .                                        662
                                                                  INDEX                                                                1685
                                                                                                                                           Page
Penny Slough, Rock River, Ill--..--..                 ....-.. . . . . . . . . . . . .                                                              756
Penobscot River, Maine---         .              ._______.....
                                                            -                                                                                         5
Pensacola Bay and Harbor, Fla ...                                 .       .       .          .          .       .        .       .          414, 448
                                                                                                                                           A..
Pensacola Reservoir, Okla                            . . .. . . . .. .......                . . .. . . . .. . . .                                  689
Pensaukee Harbor, W is....... ..                          . .. . .. . .. .. . .. . .. . .. .                                                      1113
Pentwater Harbor, Mich ...                                                                                                                        1100
           Pepperells---Cove,-Maine-------------------------------------------5
Pepperells Cove, M aine_ _....__.._______._____________.                                  ... ...                                                    54
Permanent International Association of the Congress of Navigation .----------------                                                               1631
Perquimans River, N. C...------------------------------------------313
Perry County Drainage and Levee Districts Nos. 1, 2 and 3, Mo _______-...----------                                                                717
Perry Reservoir, Kans...-------------------------------------------                                                                                798
Perth Amboy Anchorage, N. J..-------------------------------------                                                                                 131
Peru Indiana ----------------------------------------------                                                                                        947
Petaluma Creek, Calif...-------------------------------------------                                                                               1312
Petersburg Harbor, Alaska....                                       ---------------------------------------                                       1547
Peterson, Ala............----------------------------------------                                                                                  438
          se B ay ou , L a. _____.....           ____.___
                                                      .           _. .
P etit A nPetit---Anse--Bayou,---La----------------------------------------------495 ...                                             .             495
Petoskey Harbor, Mich                                           ------------------------------------------                                        1113
Phelps Creek, N. Y---------------------------------------------                                                                                    222
Philadelphia, Pa., engineering district .______-_____________________.                                                                             157
Philpott Reservoir, Va..                         ...            -------------------------------------------                                        292
Phoebus, Va., improvement of channel to Hampton Roads.... _____.--_.--_------------ 288
Pickwick Landing, Tenn-.....                            -       -         -             -           -                 --------------- 891
Piedm ont    Reservoir,
          Piedmont
             Reservoir, Ohio_   Ohio-------------------------------------------6
                                            ____________._     __._..
                                                               _.._.......          ....                                       . .. .              960
Pierre Bayou, La                                   --------------------------------------------                                            497,506
Pigeon Creek, Ill. and Ind                                                                                                                         753
                                                                                                                                        ..-----------------------------
Pigeon Point Reef, Oreg....-----------------------------------------                                                                              1448
Pilot Rock, Birch Creek, Oreg                                                                   ..-------------------------------------..         1540
Pine Bluff,    Ark...____________________.
         PnBlfAk--                  --------------------------------------------------------- _--52,-                                       529,536  3
Pine Canyon Reservoir, Nev                                            --------------------------------------                                      1297
Pine Flat Reservoir, Calif ......                                   ----------------------------------------                                      1394
Pine River Reservoir, Minn....---------------------------------------                                                                              764
Pine River, St. Clair City, Mich                                            -----------------------------------                                   1178
Pineville, Ky...--------------------------------------------------896
Pineville, Red River, La..... ...................................--------------------------------------                                   - 497,519
Pinole Shoal, Calif ....---------------------------------------------                                                                             1316
Pioneer Reservoir, Arikaree River, Colo. and Kans ..........----------------------                                                                 820
Pithlachascotee River, Fla..----------------------------------------                                                                               401
Pittsburgh Harbor, Pa......                                     -------------------------------------------                                        996
Pittsburgh, Pa., engineering district                                          ---------------------------------                                   983
P ittsb urg h , P a . ..... .. __.......
     Pittsburgh,---------------------Pa---------------------------------------------------1025                                         .. . . . 10 25
Plain Dealing Creek, Md., channel to Oak Creek ---_____----______-.-.                                                                              218
Plaquemine Brule, Bayou, La ....--------------------------------------                                                                             496
Plaquemine Lock, La..... __-__-___-           .             .
                                                       ___--____-       .            ..                  -      --                 --              462
Platoro Reservoir, Conejos River, Colo                                                      __________..                                           639
                                                                                                                                               ....................
Platte River, Colo., Nebr. and Wyo .__.........______._______.                               ____
                                                                                                .. ____    .. .____. .. _____-_____-.. 845
Plattsburg Harbor, N. Y..........                                  -----------------------------------------                                        146
Pleasant Hill Reservoir, Ohio.....                                     --------------------------------------                                      960
                                                    ...
Pleasant River, Maine ....... -----------------------------                                                                                          54
Pleasanton, Tex .             .        .        ..---------------------------------.------                                                         626
Plentywood, Mont-----                                               -----------------------------------------                                      867
Plum Bayou, Ark ..-----------------------------------------------                                                                                  661
Plum Island, Mass                ...........................
                                                          -....
                                                           -----------------------------------------------                                   .       16
Plunkett Dam, Hoosic River, M ass., Vol. 2 __-......................__________                                             ..                      151
Plymouth Dam, Schuylkill R., Pa., Vol. 2-........................               -                _____             .. ___                 ..       165
Plymouth Harbor, Mass....------------------------------------------                                                                                  26
Plymouth, Pa-..... ------                ----.-------------------------------------------------                                                    240
Poca Reservoir, W. Va ....------------------------------------------- 980
Pocomoke River, Md ......                         .........--------------------------------------------...                                         208
Poe Lock, St. Mary's River, Mich..........----------------------------------                                                                      1153
Poes Run, Va., Vol. 2.....--------------------------------------------                                                                             275
Point Judith, and Point Judith Pond, R. I., harbor of refuge-__- ---                                                 ______.___           -1___ 18   54
Point Lookout Harbor, Mich                                                                     .                                                  1178
Point Pleasant, W. Va........................                                                                        ............. 978, 981
Pokegama Reservoir, Minn._-.......                                                              ...........           ..............    764
1686                                                                 INDEX

                                                                                                                                                                                       Page
Polecat Creek, Okla-...--. . . . . . . . . . . . . . .                                                               . .                   . .              . .           .           682
Pollock Rip Shoals, Nantucket Sound, Mass...-.-.-.-.-.........                                                                                                                         31
Poison Bay, Flathead Lake, Mont....                                                                                                                                                  1514
Pomeroy, Ohio............. . ... .......-                                                                                                                                             978
Pomme de Terre Reservoir, Mo ....
                              -...                                        ...              ...              ...                      ...                           ..-                     819
Pompton River, Passaic River Watershed, N. J----------------------------------                                                                                                             155
Ponce Harbor, P. R .......                                                                                                                                                                 401
Ponchatoula Creek and River, La-..   ..................                                                                                                                                    517
Pontchartrain Lake, La ....-                                                                                                                                -                              458
Pontiac diversion, Pawtuxet River Basin, R. I......-                                                                                                                                        83
Popasquash Neck, R.               I ...-----------------------------                                                                                                                        37
Poplar Bluff, Mo .........---------------------------------------                                                                                                                          668
Poquonock River, Conn                                       .       .-. . . .                                                    .         .                 ..-                 .     53
P orpoise C ove, M e                  --...-----..................-----   --                                                                                                           12
Portage Lake harbor of refuge, Mich -                     .                -
                                                                          --.                                           -                  -             -                -          1106
Port Alexander, Alaska .                   -    -..-         -       -        -        -         -             --             -            -                                         1547
Port Allen Harbor, T. H .....                    .     . .       .      . .       . .      . .          . ..            .            . .            .           ..-              .   1331
Port    Angeles H arbor, Wash ..................................  -                                                                                                                  1514
Port    Aransas-Corpus Christi Waterway . ---------------                    .......                                                                                                  589
Port    Arthur Canal, Tex         -..-------------------                                                                                                                              552
Port    Austin Harbor, Mich         -.....-                                                                                                                                          11.69
Port    Bay, N. Y -----                                                                                                                                                              1227
Port    Boca Grande, Fla ...    . .            . . .     . . .   . . .     . . .                                                                                                      388
P ort   B olivar, T ex- --- - - -- - - -- - -- - - -- - - -- - -- - - --     - - -- - -                                                                                               570
Port    Chester Harbor, N. Y -.-.-                                       -       -                                                                                                     146
Port    Clinton Harbor, Ohio-...-------------------------------                                                                                                                      1178
Port    Everglades Harbor, Fla .....-                                                                                                                                                 369
Port    Gamble Harbor, W ash., improvement - ................... .. .. . .. .. .                                                                                                     1514
Port    Henry Harbor, N. Y ...---                                                                                                                                                      146
Port Inglis, Fla --.--....-                                                                                                                                                                396
Port Isabel Channel, Texas..------                                                                                                                                                         595
Port Jefferson H arbor, N. Y .. .............                                                          .............-                                                            .          87
Portland Harbor, Maine...-            -   --                        -           10
Portland, Ohio-------------------------------------------------------978
Portland, Oreg., engineering district   ------------------------------------- 1407
Portland, Oreg ..-         .
                           ....                  .                      ...-------------                                                                                 1429, 1455
Port Lavaca, Tex., channel from Pass Cavallo ..----------------------                                                                                                     ....  587
Port Mansfield, Tex .-...............                                                                                                                                           559
Portneuf River and Marsh Creek, Idaho........................                                                                                                            1532, 1534
Port    Ontario Harbor, N. Y -....-                                                                                                                                -              1227
                                                                                                                                                                         --..-----------

Port    Orchard Bay, Wash -..--          - -                                      -         -          -                                                           --             1514
Port    Richmond Anchorage, Pennsylvania                                      -.....                                                                                          162, 163
Port    Royal Sound, S. C           ----                                                                                                                                       . 329
Port St. Joe Harbor, Fla...... . .. . . .. . . .. . .. . . .. . . .. . .. . . .. . .                                                                                                   448
Port Sanilac Harbor, Mich .......         .         .         .        .--------.                                                                                                     1170
Port Series Reports .              .....       ..-                                -             ----                                                                                  1554
Portsm outh Harbor, N. H-...............................                                54
Portsmouth Harbor, Va., channel to Nansemond Ordnance Depot ---------------------      288
Portsmouth, New Boston, Ohio -.....                                      956,     973, 978
                                                                                      1489
Portville on Allegheny River, N. Y.--
Port Washington Harbor, Wis-......-
                                                      -  - --                  996, 1025
                                                                                      1078
                                                                                                                                               -
Port W ing Harbor, W is .-----------                     ---.-.--....                                                                  -                                              1037
Posten Bayou, La. and Ark .......-..---- - - - --                                                .--                .                . .            . .                                    517
Poteau River, Okla ---                                                                                                                                                                     694
Potomac River:
        Improvement at Alexandria, Va                                         --.-......-                                                                                                  258
        Improvement       at Lower Cedar Point, Md                                                                                                                                         258
        Improvement       at Mount Vernon, Va --..............                                                                                                                             258
        Improvement       at Washington, D. C ......       ..                                                                                                                              243
        Improvement       below Washington, D. C........... ........                                                    ------------                                                       258
        W aterchestnut elim ination ...............                       .. ...                                    ......................--------.                                        248
Potowomut River, R. I.....           .            .       .                                                                  .                          .                        54
Powhatan Point, Ohio         ..                         . . .
                                ........... . . . ----...                                                                   .                  ..           .....               978
Prado Dam, Calif ...........                                                                                                                                             1288, 1290
Prairie du Chien, Wis., harbors .          ... .. .. .. .. .....--.
                                                                ..                                                                   . ............                             737
                                                         INDEX                                                               1687
                                                                                                                              Page
Prairie du Pont drainage and levee district                                                                                    723
Prairie du Rocher and vicinity, Illinois ..--------------------------....                            .                         718
Prairie Portage Board of Control......... ...........                  ........------------------
                                                                            ...---------------     .                          1645
Prattville, Autauga Creek, Ala ................. . ..........                                  . -                             452
Prescott area, Columbia County, Oreg                       ....................-------............                            1476
President Roads, Mass------................-----------------------------------                      20, 21
Presque Isle Harbor, Marquette, Mich..........            .....------------------------------------ 1046
Presque Isle Peninsula, Erie, Pa .....-...................                                            _...
                                                                                                .....------------. __.--      1204
Preston drainage and levee district, Illinois .                               -......-.-..........                             714
Prestonville, Ky -...-...........-------------------                                                                          945
Price Landing, Mo ...............------------------                                                                           730
Priest Rapids Dam, Wash____.                       __-____...-...                                                             1523
Princess Point Cut-off Channel---------------------------------                                                               1043
Proctor, Otter Creek, Vt..............                                                                                         153
Proctor, W.       Va      -....-   -   --. ---..                                                              -.              978
Proctorville, Ohio                                                                                                   .         978
Prompton Reservoir, Lackawaxen River, Pa........                                ...                      ..              .     192
Providence Harbor and River, R. I ..............                      __...                          -        _...              36
Provincetown Harbor, Mass ....-.. -------------------------                           31, 54
Pudding River, Oreg ...-.....     .       .         .       ..... -             1455, 1476
Pueblo, Colo ........         -     -    -       --              -  -       -..          629
Puget Island area, Wahkiakum Diking districts Nos. 1 and 3----...---....... .--------- 1473
Puget Sound and its tributary waters, Wash., improvement of ....- ___-...-.........._ 1481
Pullman, Wash------------------------------------------------------1540
Putneyville Harbor, N. Y -.--.--.----                                                                                         1227
Pungo River, N. C..........      ---------------------------------------------------.. 299
Punxsutawney, Pa               ----------------------------------------------     1004,1025
Purdy Creek, N. Y---------------------------------------------------                     226
Purgatoire River, Colo              -------------------------------------------------    638
Put-in-Bay Harbor, Ohio ..- ___        ----------------
                              __ ____-----                                              1178
Puyallup River, Wash., improvement of Tacoma Harbor_ ....---...-... .__.._..            1520

                                                             Q
                             ---
Queenstown Harbor, Md ..........---------------.......
                                                   ....                                             218
Queque de Tortue Bayou, La.....-------------------------------------------496
Quillayute River, Wash ....- __-____ ____--__-  -- ___.__.--...                -....            .. 1495
Quinby Creek, Va..------------------..--...........-------------------------------288
Quincy, Ill    --------.....  .................                    ...   ..          .............
                                          --------------------------------------------------        752
Quindaro Bend, Missouri River -...._____-......_____....----........                                794
Quinnipiac River, Conn                                          .----------------------------------- 54
                                                            R
Raccoon Creek, N. J........-----------------------------------------                              190
Raccoon (Little) Creek, Ind                     ------------------------------------              946
                                 _._._
           C re ek , Pa .. .. . .__.
R ac co on Raccoon-Creek,-Pa-------------------------------------------1028--_-
                                   .    .      .
                                              __.     .     .     .     .      .     ..          10 2 8
Raccoon levee unit, Indiana......____                           -------------------------------- 945
Rachel, W. Va .............--------------------...                                               1030
Racine Harbor, Wis ......--------------.-                                                                                    1083
Racine, Ohio ....-----------------------------                                                                                978
Rahway River, N. J------..-.       -------------.---------------.                                           146
Ranier drainage district, Columbia County, Oreg ................---------------------....            1473, 1475
Rainy Lake Board of Control..                           ------------------------------------------         1645
Rancocas Creek or River, N. J                               ------------------------------------------      190
                               --..--. -
Randolph, Me------... -----..........                    --                        -        -        -        9
Randolph Reservoir, Va.-             ---.-                       -.-------.---------                        289
Rapidan River, Va..           ------.....--------------------------------------------                       264
Rapides Parish, La--------------------------------------..------------497
Rappahannock River, Va..                        ---------------------------------------. 250,258,264
Raritan Bay and River, N. J....                       .....-------------------------------------------      138
    Improvement of channel to Authur Kill_-___-_____-------...-...          .....             __       .    146
Rathburn Reservoir, Iowa...........-                                    . . . --.....
                                                            ... . --.....-           .797
Ravenna, Ky---....    -----.-----............-.....-...-.                                                   913
Ravenswood, W. Va..--------..                 ....          ...------------------------------------------. 978
Raymond, Wash-                  .- . -. .
                        - ............                    .                       .........                1523
 1688                                                                  INDEX
                                                                                                                                              Page
Red Chute Bayou, La-------....                         ......................-----------------------------------                                              497
Red Fish Bay and Landing, Tex .........................................-........                                                                              560
Red Hook Channel, New York Harbor, N. Y_.... ___-___.___-. - ..--                                                                ---....__              .     103
Red Lake and Red Lake River, Minn.....                                    -------------------------                                         770, 771, 775
Redmond, Utah................                                        ...........................-----------------------------------------------             1400
R edondo B each  Harbor,
            Redondo                                                                              ...
                               C alif __.....__................. .... . ...---------------------------
                     Beach-Harbor,-Calif----------                                                                                                          1253
                                                                                                                                                            15
Red River, La., Ark., Tex., and Okla.:
     Below Denison Dam:
         New Orleans district .........-----.......-----------------------------                                                                      496, 501
         Tulsa district------...............      ...............----------------------                                                               698,701
    Below Fulton, Ark ....-.-..--...                                                                                                                          456
                                                                                                                                              .--------------------
    From Fulton, Ark. to mouth of Washita River, Okla..-....._______.-.......__..... . 672
    Vicinity of Shreveport, La.....                               ---------------------------------                                                      97, 519
Red River of the North Drainage Basin, Minn., S. Dak., and N. Dak.....                                                                                770, 772
Red River Parish, La                        -----------------------------                                                                             497,519
Red River, Tenn....---.               ..--                                                          -           --------------------                          894
Red Rock Reservoir, Iowa ....                  .....               ........                  ..........----------------------------------------              756
Red Run, Clinton River, Mich ....................                                                     ........------------------------------------          1180
Redstone Creek,         ..... . __.
                  Pa_____                       . .             .        .
           Redstone-Creek,-Pa----------------------------------------------101      . .                 .         .              ..       . .               1015
Red Willow Reservoir, Nebr.................                                                                                                                   797
                                                                                                              ..........---------------------------------------
Red Wing, Minn., harbor.....______---                   - __ -                 -          -                     -. ..                                         736
Redwood City Harbor, Calif.....                        ..                                                                                                   1323
Redwood Creek, Calif....-----------------------------------------                                                                                           1323
Redwood River, Minn ---                                ------------------------------------------                                                            790
Reevesville, Ill....---------------------------------------                                                                                -          941,945
Regulation of hydraulic mining and preparation of plans ..-...___.                                                             .___....___.._____    .. 1561
Rehoboth Bay to Delaware Bay, Del., navigation.....__--___-_______.                                                                                          190
Reno Beach, Lucas County, Ohio.....                                     ----------------------------------                                                  1182
Republican River, Kans., Colo. and Nebr ._........____...........                                                                     .            ....      821
Reserved Channel, Boston Harbor, Mass__--                                     _____..__.............                                                  .....20, 21
Reservoirs at Headwaters of Mississippi River-....----.-----                                                       ..           ..
                                                                                                                __-..-____.........           ___..          764
Restoration of Indian Fishing Grounds, Bonneville, Oreg ..................................                                                                  1418
Richland Reservoir, Mo ....------------------------------------------                                                                                        820
Richmond, Ky....-----------------------------------------                                                                                                    913
Richmond Harbor, Calif.......------------------------------------                                                                                           1317
Richmond Harbor, Maine__....--.-----.                          -_ -                ---..                                          ..---.-.-.                   54
Richmond Harbor, Va ..                                                                          -----------------                             272
Richmond, Me                                                                                              99----------------
Richmonds Island Harbor, Maine -... _...--.-..-                           -        -        -            54
Ridgeley, W. Va..-----------------------------------------------                                        260
Ridgeway, Pa         ..------------------------------------------------- 1025
Rigolets, Gulf Intracoastal               ......---------------------------------....                   458
Rigolette Bayou, La __..- __      --....       -         -
                                                       --.-           ---------
                                                                   .____                                509
Rimerton, Pa..---....                                     ---------------------------------------       985
Rio Chama, N. Mex.....                    ------------------------------..                              633
Rio Grande Floodway, N. Mex .....-----------------------------                                         636
Rio Hondo, Calif          ...        ------------------------------------                             1266
Rio Hondo Channel: Santa Fe Ry. to Whittier Narrows flood control basin....                           1268
Ripley, Ohio _..---------------..-                                                                     945
Rising Sun, Ind ......              ---------------------------------------                            945
Riverdale, Connecticut River Basin, Mass _..............._..                            .      .     70, 83
Riverland levee district, Missouri .___.........--.--               -      --.-       --.-       ---   730
Riverside levees, Calif                            -------------------------------------------        1294
                       -       -        -
Riverton, La-.---..-.----------------------                                                            525
Riverview, W. Va.........                                      ...----------------------------         979
Roanoke Rapids Reservoir, N. C ....                                  --.-.-.-.-............                                                  289
Roanoke River Basin, N. C. and Va .....        ----------------------------                                                            288, 301
    John H. Kerr, Reservoir ....     ....------------------------                                                                           290
    Dams and Reservoirs....                      and..-----..--------------------------------                                               289
Roaring       Branch,       Bennington,            Vt--------------------------------------------------------------------------------


Rochester, Ky....-.. ..-........                      -----------------------------                                                          916
Rochester and McCleary's Bluff levee unit, Illinois-...-.--.-.                                                      .---.... .     .         945
Rochester (Charlotte) Harbor, N. Y .-.... __--..............-                                                                              1219
Rochester, Pa-....- - ....- - ....- - ....
                                       - - -....                                                   ....  ..                                1025
Rochester Reservoir, Iowa- - -             .-. . ..                                               . . . ..           ...........            756
                                                             INDEX                                                               1689
                                                                                                                                     Page
Rock Hall Harbor, Md......----------------........                                 .......------------------------             218
Rockhold Creek, Md----....-......................-...............---------------------------------------218
Rock Island, Ill., engineering district .-......... ___                            --..........                                747
Rock Island, Ill., harbor............                               ......------------------------------------------           737
Rockland Harbor, Maine-----                                  -------------------------------------                              54
Rockland Reservoir, Neches River, Texas.--........                             .___._..------- --                       604, 607
            H arb or, M
R ock p ortRockport
            Harbor,      ain e ..................               ..
                      Maine--------------------------------------------5                         ..                             54
Rockport Harbor, Mass......                       -------------------------------------------                                   54
Rockport Harbor, Tex                            -------------------------------------------                                    560
Rockport, Ind.......            ...     -------------------------------------------------                                      945
Rock River Ill. and Wis.....                  -----------------------------------                               747, 752, 756
Rocky Ford drainage and levee district, Illinois .........................                              .              ... 1148
Rocky Fork Reservoir, Ohio ......                       ---------------------------------------                                980
Rocky River, Ohio                 ---------------------------                                ------------------              1227
Rodanthe, N. C., channel from Pamlico Sound to......--...                                ---..-.............____ .             313
Rogers City Harbor, Mich ....              -------------------------.....................--------------                      1178
Roland drainage district Arkansas River, Ark.---.__.__--......                                                                 668
                              ---
Rollinson Channel, N. C ....-.-.-............                                                                            .     313
Rome, Ga ...--------------------------------------------...                                                                    451
Rome, Ind ...... -----------------------------                                                                                 945
Rondout Harbor, N. Y.............-------------------------------------------114
Root River, Wis., improvement of Racine Harbor_ ...-------.-----.-.-..-...-...   -                                           1083
Roscoe-Rockland Area, N. Y-----....           ------..........                         -----------                             193
                      --       ---.-
Roseville, Ohio- ..-............ ......--                                                                        -963..963,979
Rosiclare, Ill-----.....-----------------------------------------                                                              939
Rossview Reservoir, Tenn. and Ky........                          ...               ...-------------------------
                                                                                                          -.-------.......     907
Rossville, Ga                                            -----------------------                                                      908
Rouge River, Mich....---------------------------------------------.    1172
Rough River, Ky ------------------                                  919,945
    Reservoir ...----------
                     ---------------------------------              933, 946
Round Lake, Mich................-----------------------------.......1112
Rouses Point, Lake Champlain, N. Y--------------------------------       146
Row River, Oreg                                                              -------   --------------                               1462
Royal River, Maine                      -.............                                                             54
                                                                                                   ..---------------------------------
Rubio Canyon, Diverson, Calif -.                           .    . .      .    . .................          . 1268
Rumsey, Ky..........-------------------------------------------------                                            916
Rush River, N. Dak......                              ----------------------------------------                   772
Russell and Allison levee unit, Illinois.-............__.__.--.-----                                             945
Russell Creek, S. C...............----------------------------                                                   326
Russell, Ky         ------------------....                   --------------         --------------         979,981
           iv e r, C a l if __. . ._... _..     . .. . . . .
                                         . . . _.._                   . . .
Ru ssi an RRussian-iver,-Cli--------------------------------------__--_1341        . . .        . . .           13 41
Rutland, Otter Creek, Vt                    ......... -           - -       -   -............                    153



Sabin Lock, St. Mary's River, Mich ....................                                                                             1153
Sabine-Neches Waterway, Tex...--------------------------------..                                                                     551
Sabula,      Iowa --....-----          - -----------------                                                                           756
Sackets Harbor, N. Y                                  --..--.           - -..- -                                                    1227
Saco, Mont .............--------------------------                                                                                   865
Saco River, Maine-------------------..------.---                      .....-....                                                      54
Sacramento, Calif., engineering district......     .    .     .     .         .  .                                                  1349
Sacramento River, Calif..-                                                                                            -.....-.      1349
     Collinsville to Shasta Dam, Calif--...............-.............                                                               1370
     D ebris control  ... ________________.________...
             Debris---control------------------------------------------1565---_                                                     1565
     Flood control _________________________                                                                                        1568
Sag Harbor, N.          Y ........       -           -           -                      -......--------------------                   146
Saginaw Bay and River, Mich_----.........            ...                   .    1167
St. Albans Harbor, Lake Champlain, Vt........------------------------------      146
St. Andrews Bay and Sound, Fla                 -------------------------..
                                                ...-------                   331,414
St. Anthony Falls Upper Lock, Minn., improvement of Mississippi River from
   Missouri River to Minneapolis__.__..--.--.-.-....-~...      .......           734
     Lower Lock and Dam---------
                           .......-      ---... ...-       ... ...-.-..-.        734
St. Augustine Harbor and Inlet, Fla ...---                                                       ...... ---.......--........           401
St. Catherine Sound, Md---        --       -                               --          --          ---            --....................258
1690                                                   INDEX

                                                                                                                      Page
St. Clair Flats Canal, Lake and River, Mich-                               ----------------------..-........               1158
     Improvement of channels in Lake St. Clair.____________.........                        ...------------------------    1178
St. Croix River, Minn. and Wis.........................                      .........                                      768
                                                                                            ...------------------------------------
St. Croix River, Maine-----.........................................      .........                                           54
                                                                                            ...---------------------------------------
St. Croix River, Maine and New Brunswick, operations of International Board
  of Control................--------------------------------------------------                                             1640
St. Francis Bay and River, Ark ......                                           ------------------
                                                                 ____......____...........___                           545,548
St. Genevieve Levee Dist. No. 1, Mo.                      ................----------------------------                       730
St. George Island, Md.--                  .....................-----------------------                                      258
St. James Harbor, Beaver Island, Mich .................-------------------------                                           1113
St. Jeromes Creek, Md...........----------                ....       .... ----------------                                   258
St. Johns River, Fla.:
     At Jacksonville ............................---------------------------------                                           349
     Between Norfolk, Va., and St. Johns Riv., Fla...-.. ..- ----------------------                                          284
     Jacksonville to Lake Harney............._....__.............-----                                                       401
St. Jones, River, Del-----..........     .........................---------------------------------------                    190
St. Joseph Harbor and River, Mich., and Ind...................---------------------                                 1087, 1113
St. Lawrence River, improvement between Ogdensburg, N. Y., and Lake
  Ontario      ......----------------------------------------------- 1225, 1227
St. Louis County, Mo.....-------------------------------------------                                                        730
St. Louis, Mo., engineering district ..                  .......          .        .........         ........         705
St. Lucie Canal and River, Fla .                      ... . .......--
                                                                   _-----------------------    378, 380, 401, 407
St. Malo Bayou, La ............-                ---------------------------------------------
                                              -...          ............                                            495
St. Marks River, Fla.....                    -----------------------------------------                        414, 448
St. Martinsville, La..---------------------------------------------                                                 486
St. Marys, Pa ..------------.                                            ----------------------------- 1025
St. Marys River, Ga. and Fla..........                    --------------------------------------                    340
St. Marys River, Mich ........------------------------------------------                                           1151
St. Marys, W. Va ......----------------------------------------------                                               979
St. Michael Canal, Alaska ..----------------------------------------                                               1547
St. Patricks Creek, Md                             ------------------------------------------                       258
St. Paul Harbor, Minn...-------------------------------------                                                       736
St. Paul, Minn., engineering district_- ....----.--..     -        ---                             ---------        761
St. Petersburg Harbor, Fla                             ----------------------------------------. 401
St. Simon Sound, Ga .--------------------------------------------                                                   340
St. Thomas Harbor, V. I--...                              __.                 .-------------------------            401
Sakonnet Harbor and River, R. I-.......-------------                     -----------                             34, 54
Salem Church Reservoir, Va ....--                        ---------------------------------------                    264
Salem Harbor, Mass                             ---------------------------------------------                          54
Salem River, N. J ----------                                       ---------------------..---                       190
Salinas River, Calif----------------------------------------                                                       1345
Saline Point, La                -------------------------------------------- 497, 519
Saline River, Ark....-----------------------------------------                                                      528
Salitpa, Ala---------------------------------------------------                                                     438
Salkahatchie River, S. C-----------------------------------------                                                   326
Salmon River, Alaska-----.. . . . . . ..--------------------------                                                 1547
Salmon River, SalonRivrOre-----------------
                 Oreg---------
                          .....                                                -------------------------- 145      1452
Salt Creek, Fla. See St. Petersburg Harbor.
Salt Creek,  Ill.....           --------------------------------                                                   1148
Salt Creek and Fork of Arkansas River, Okla.........-----------------------                                  680,700
Salt Lake City, Jordan River, Utah                                ---------------------------------                1400
Sampit River, S. C....----------------------------------------317
San Angelo Reservoir, Tex- .... ----------------------------------..-----------------------------------------.. 6..22
San Antonio Channel, P. R-...---                                          ----------                                401
San Antonio Creek, Calif                         ------------------------------------                      1288, 1289
San Antonio Dam, Calif ....------------------------------------ -1288
San Bernard River, Tex....                       ..------------------------------------------.. 558
San Bruno Shoal, Redwood City Harbor, Calif                                                                        1323
                                                                                              .........-------------------------...
San Diego Creek, Texas-----                                -------------------------------------.                   626
San Diego Harbor and River, Calif _...-............. .----------------------------..     ....   .          1260, 1295
                                                                                                                1..

San Diego River and Mission Bay, Calif_.....                           ---------------------------.               1263
Sand Hill River, Minn-----------------------------------------..                                                    772
Sandusky River and Harbor, Ohio..............------------------------------1185, 1227
Sandy Bay, Cape Ann, Mass ...--- ------         - -          -------..........         .     54
Sandy drainage district, Multnomah County, Oreg-..-. --.-............          1473, 1474, 1475
Sandy Hook Bay, N. J-----           --------
                                     .       . ... .            .               .       141,146
                                                           INDEX                                                  1691
                                                                                                                    Page
Sandy Lake Reservoir, Minn .......                ........-------------------------------------                        764
San Francisco Bay and Harbor, Calif_.----__                         ________....
                                                                        --                .           -_1308,         1311
San Francisco, Calif., engineering district . ..............-                                                        1301
                                                                                            ......-----------------------------
San Gabriel River, Calif...                       -------------------------------------                      1266, 1268
Sangamon River, Ill                              ---------------------------------------- 1144, 1148
San Jacinto, Calif....----------------------------------------------1294
San Joaquin R   iver,
               San    C
                   Joaqin     ...______ ._____
                        alif River
                       Calif-----------------        .___ .__
                                                   .__                               . . . . . . . . 16
                                                               _.___. . . .--------------------                       1362
San Juan Dam, Santa Ana River Basin, Calif.                                   .                              1288, 1298
                                                                                         .---------------------
San Juan Harbor, P. R...-------------------------------------------401
San Luis Obispo Harbor, Calif
San Pablo Bay, Calif-----------
San   Rafl aelCre,
                                              _________._____- _ -------

San Rafael Creek, Calif____________ ___._____-.........
                                                             - -...--------------------
                   Calif------------------------------------------------------------------33
Santa Ana River, Calif..--------------------------------------1287, 1293
                                                                                                            331311
                                                                                                            .....-    1265
                                                                                                            .1313, 1315
                                                                                                                      1311

Santa Anita Wash, Calif..-----------------------------------------                                                   1268
Santa Barbara Harbor, Calif_ .----...-------      __-___--_____.._                                           -        1251
Santa Clara River, Calif                              -----------------------------------------                       1298
Santa Fe Channel, Calif..-----------------------------------------                                                    1318
Santa Monica Bay, Calif ..-..--..--                                                  -------------------- 1253
Santee River, N. C. and S. C...____.. ___________                          ---------------------------                 326
Santiam River, Oreg----------..   ..----------------------------------                                               1472
Sapelo Harbor, Ga ....-------------------------------------------                                                      340
Sardis, Ohio----- --...-------------.--. .. .. . .. . .. .. . ...                                                      979
Sardis Reservoir, Miss                         ---------------------------------------                                1584
Sasanoa River, Maine           ..-------------------------------------------..                                          54
Sasco Hill Beach, Conn ................------------------             _------                                           54
Satilla River, Ga..........                 -----------------------------------------------.. 340
Saugatuck Harbor, Mich...               _________..-----------------------------------1091
Saugatuck River, Conn .....- ---------------------------
                                            -...                                      --                                54
            Harbor,Mich
Saugerties Marie,     N. Y.........                                               ----------------------- 152          146
Saugetie.             N     ----
Sault Ste. Marie, Mich ___...______...
                                          ---------------------------------------------------------------
                                                         ..........
                                                     ___._                                                            1152
Sauvie Island (areas A and B), Multnomah County, Oreg .........-------------..... 1473, 1476
Savage River Dam, Md----     .................. -------------------------------------
                                                                 ....                                                  263
Savannah, Ga., engineering district _...__-___--           __-____- ---....                                        -- 329
Savannah Harbor and River, Ga.:
      Improvement of harbor_ _________-__..--........         ......                                      .            332
      Improvement of river above Augusta ..............               ___--__-__                       -.              340
      Improvement of river at Augusta ......                                         --------------------              340
      Improvement of river below Augusta ...... ..                           _- --       -        -. .                 337
Savannah River Basin, Ga., and S. C ._________.___.....         ...                                                    341
Sawpit Wash., Rio Hondo Basin ...                              -----------------------------------                   1268
Sawtelle-Westwood, Calif......                         -------------------------------------...--.. 1268
Sawyersville, Ala ......----------------------------                                                                438
Saylersville, Ky .--------------..-------------------------                           -       947
Scappoose drainage district, Columbia County, Oreg......----------------..              1473,1475
Scarboro River, Maine, between Prouts Neck and Pine Point _...............____.____..          54
Schell Run, Pa....                       ...
                                         -------------------------------------------------    240
Schoolfield Reservoir, Va. and N. C_ . -                                  _______..
                                                        -.......................              289
Schooner Bayou, La                                                 -------------------                              515
Schuyler, Nebr                                 ---------------------                          845
Schuylkill River, Pa ...-.. ......------------------------                                    166
     Above
Scioto River,Fairmont         ...
                        Dam------
               Ohio-------                            -----             - ------               165
                                                                                          9564---------------------
     Flood control reservoirs
                        Dam-.---------------------------------------                          980
Sciotoville, Ohio----------                                  ----------------------------     979
Scituate Harbor, Mass.......            --------------------------.                             54
Scranton, N. Dak         --------------------          --.-----                               847
Scuppernong River, N. C ...----------------....                                               313
Seaford, Del .....         .      ..---------------------------.                                                    218
Seahorn drainage and levee district, Illinois..... __...............______. . 1148
Seattle Harbor, Wash., improvement of Duwamish River and east and west
  waterways      ..-------------------------------------------------              1499
Seattle, Wash., engineering district      __----___---______--                    1481
                                                                             ..........
Sebastian, Fla .-------------------------------------------------                   357
Sebewaing River and Harbor, Mich-.. ---------------                                                                1178
Sebewaing, Sebewaing River, Mich-.. ---------------                                                                1179
Seekonk (Pawtucket) River, R. I ..........---.--.-                                       --   --   .   .
                                                                                                       -.   ...      38
1692                                                        INDEX

                                                                                                                            Page
Seldovia Harbor, Alaska_......................   _____.. ..                                                                  1547
         SelsersCreekLa-----------
Selsers Creek,  La __                  __ __.........____.
                              _.........                       ----------------------                                          517-----------
                                                                                                                               517
Senecaville Reservoir, Ohio-...........                             -             -                -             -             960
Sepulveda flood control basin..-.--.                      ---...       ---..-.- -       --..-------                           1268
Sevier River, Utah and Nevada......                                 ------------------------------------                     1400
Seward Alaska, Harbor of Refuge..                                     ----------------------------------                     1545
Seward, Nebr., Big Blue River..                       .....................                                                    821
Shad Landing, Md             ------............               ----------------------------------------                         208
Shallotte River, N. C ...-----------------                                                                                     313
Shallowbag (Manteo) Bay, N. C-.......                                    ..                               .                    303
Shamokin Creek, Pa-----...........              --------------------..                                                         240
Shark River, N. J-........           -               --              -         -                                                146
Shasta Dam to Collinsville, Calif ...._____-.___-_________                                                                   1370
Shaw Cove, New London Harbor, Conn........                                          __.                                          41
Shawneetown, Ill                ........ .......
                           . .....                                                                                 .           945
Sheboygan Harbor, Wis.........                        ..-----------------------                                              1076
Sheepshead Bay, N. Y................------------------.....                                                                    146
Shell Creek, Ala.......-                          - - - - - - - -                    -- - - - - - - - -                        428
Shelley Area, Idaho       .......                             ---------------------------                                    1532
                              .
Shem Creek, S. C ...____._..____._.              _.319,
                                                 ___.                                                                          325
Shenango Reservoir, Pa. and Ohio ___............................                                                             1025
Sherwood Island State Park, Conn--...--.-.........                              __...........                                    54
Sheridan, Wyo               ---------------------------...
                                                _...                -                                                          864
           River, Conn.... ...._____..___            ..       .....
ShetucketShetucket----River,--Conn-----------------------------------------   .        .          .       .          .           64
                                                                                                                                 64
Sheyenne River, N. Dak .........                        --------------------------------------...                        772, 780
Shields River, Mont ........                        --------------------------------------------..                             866
Ship Island Pass, Miss., improvement of pass and channel to Gulfport                                                 ______. 444
Shipyard River, S. C_                                                                                                  _-----323
Shoal Harbor, N. J....----------------------------------------------                                                           146
Shoals, east fork of White River, Ind..-....                                     - __. -
                                                                            -. -___--.......   --.-                            947
Shonkin Creek, Mont....               -.... ________                                             ....                          866
                                                                                                        ..------------------------------------
Shore Protection Board. See Beach Erosion Board.
Short Cut Canal, Mich ...............................-------------------------..                                             1173
Short Mountain Dam and Reservoir, Okla ......... __                                       ......                               644
Shreveport, La., to Jefferson, Tex., improvement of waterway                                          -.........               495
Shrewsbury River, N. J ...................................------------------------------------                                 141
Shufflebarger levee unit, Indiana .....                    -          --.....-..................                               945
Sierra Madre Villa Channel, Rio Hondo Basin....-.                                 __.......................                  1268
Silver Creek, Pa .......                ..--------------------------------                                                   1003
Silver Lake Harbor, N. C....                     ---------------------------.-..                                               313
Silver Springs Run, Fla                 ..------------------------------                                                       354
Sinepuxent Bay, Md.........-------------------------------                                                                     215
Sink Run, Pa.................                                                                                               240
Sioux City, Iowa------------                                                                  7--------------------794,8
Sistersville, W. Va...---------------------------------..                                           979
Sitka Harbor, Alaska..                  --------------------------------                          1547
Siuslaw River, Oreg ......... .            .     .    .   .   .    .   .   .   .   .     .        1452
Six Mile Creek, Ill..........       ----------------------------                        ........ 753
Skaggs Ferry, Black River, Ark-......-                                        -       -             668
Skagit Bay and River, Wash..                       ----------------------------------      1514, 1523
Skagway Harbor and River, Alaska..........-----------------------------1547,                      1549
Skamokawa Creek area, Wahkiakum County, Wash ....................---------------------            1475
             a C re e k, Wa sh .. ... .............. . .      .     . .
Sk amo kawSka-noka-a-Creek,-Wash-----------------------------------_--    . . .       . --- 15    14 52
Skamokawa Slough, Washington . -                                    .--.--.-   .           .       .   --..-..             1452
Skipanon Channel and River, Oreg., improvement of channel                                      ....................... 1433
Slaughter Creek, Md...............----------------------------                                                          218
Slidell, La             --..- -     -        -                --
                                                     ------------                          -----                      -     495
Slovan, Raccoon Creek, Pa---------------                             -- ---------------------                              1028
Smith Creek, Md       -.                                                                                                    258
Smith Creek, N. C--       --      -.--.--.....-------------------                                                           313
Smithland, Ky                                     ---------------------                                                     945
Smith Mountain Reservoir, Va.........                     ------------------------------------
                                                       ..........                                                           289
Smith River, Oreg .---------------------------------------------                                                           1452
Smiths Ferry, Pa       ..-...---------------------------------------                                                       1025
Smoky Hill River, Kans......                 ------------------------------------......--..
                                                        .......                                                             821
Smuttynose Island, Me., N. H......                                                                                        14, 15
                                                             INDEX                                                                        1693
                                                                                                                                            Page
Smyrna River, Del -_. --..-                                                                                                         190
Snagging and clearing in the interest of flood control and of navigation. See
  districts.
Snake Creek, N. Dak.....................--------------------------------------------                                                851
Snake River, Idaho, Oreg., and Wash ....---------------------------                                                        1527, 1533
Snohomish River, Wash                                     -----------------------------------------                               1491
Fort Peck District---------------------------------------                                                                          857
Snow Hill, Md             -----------------...--------------------------------                                                     208
Sny Basin Ill ....                             --------------------------------------------------                                  753
Sny Island levee drainage district, Ill..-                            ---..-.-.-.-.-.........      _____..                         756
Soldier Ledge Channel, Hussy Sd., Maine.____                      ................ --                   ____           .      . 10,  11
Solomon, Kans., south of, Smoky Hill River_                                       -             . ___-.........
                                                                                             -___  -_____---                       821
South Bank Arkansas River, (Head of Fourche Island to Pennington Bayou)
  Ark ..... - ...... ................                                      ................                                   662, 668
South Beardstown drainage and levee district, Ill-__- --.-.----.--.--..                       .      .     .      .      .       1148
South Beloit, Ill ..........------------------------------------------------.....                                                  756
South Bristol      Harbor,      Maine.            ------.....---------------------------------                                       54
South Coventry Reservoir, Conn                             ---------------------......-------------                             65, 83
Southern and Central Florida.............                          --------------------------------------                          402
Southern New York Flood Control Project..-.--.........___..                                    __........                          219
     Dams and Reservoirs....................... -----------------------------------------                                          228
     Local flood protection works.........                               -----------------------------------                       229
South Fork of Cumberland River, Ky                                  ...         --------------------------------.                  894
South Grand Reservoir, Mo................                                ...------------------------------------                   797
South Haven Harbor, Mich., improvement-------                           .                 - __.......
                                                                                                 ----..-        _                1089
South Mills, N. C.                    ---------................. ...-----------------------------------                            285
South Milwaukee Harbor, Wis..                                 -----------------------------..-----
                                                                         ...                                                     1113
South Pass, La...........................                 ...             ...-------------------------------------------------     479
South Platte River Basin, Colo_ ............        - ........ - .......                                        __....__           841
South Plymouth Reservoir, Canasawacta Creek, N. Y....                                            --------------------..- 240
South Point, Ohio----------------------------------------..------                                                                  979
Southport Beach, Conn.....                    ..              --------------------------------------                                 54
Southport Harbor, Conn.........---------------------------                                                                           48
South Portsmouth, Ky..........----------------------------..--------------- 979
South Quincy, Ill                                     ----------------------------------------                                     756
South River, Mo .....                      ..          ..               .         ...------------------------------------
                                                                                                   --.--.........       -          756
                                                                                                                                    -

South River, N. C.................                             ....------------------.........---------------------.               313
South River, N. J.........                                                                                                                  146
South Santiam River, Oreg ...........--
                                     ...                              ------------                                                         1455
South Slough, Ill---.............................  ........ .    . .         ...... . ..........------------------------------------
                                                                                                              751
South Tunbridge Reservoir, Connecticut River Basin, Vt __                             .__.._..____         69, 83
Southwest Pass, La -...---.. .                 .    .      .    ..-                -.                         474
Sowashee Creek, Meridian, Miss..........................                                                      453
Spanish Fork River, Utah------       .........           ------------------------                            1400
Sparkman Channel, Fla                                 ------------------------------------------              391
Spokane River, Wash. and Idaho.......-------------------                                                     1523
Spottsville, Ky-----..--------------------------------------------916
Spring Creek, S. Dak-..............                                                                           847
Springdale, Connecticut River Basin, Mass _______.._______                                    _________...70, 83
Springfield, Connecticut River Basin, Mass-...........-------------------------......-                     70, 83
Spring Lake, Ill        ------------.................                    ..----------                        1148
Spring Point, Me....................                                                                            10
Spring River, Mo                                                                                 .            688
Spuyten Duyvil Creek, N. Y-                        ---------                                                                            109,111
Squalicum Creek, Wash-....                            ----------------------------...                                                      1483
Stamford Harbor, Conn..                                                                                                                      51
Stislaus River, Calif           ------------------------..                                       ------------------                        1383
Star Island, Me., N. H_ _ __--__________--_~~_-
                             --...                                                                                                        14, 15
                             .
Starlings Creek, Va----------...--. .      .     .                         .         .       .      .               .           .           211
State Barge Canal, N. Y-.-.-             .
                                      ------.--. .                             .         ,              .                   .               115
State Ditch, N. Y ...-......-                               --------------------------------                                               1236
Stearn's Mill, Me.............-------------------------------------------                                                                     6
Steele Bayou, Miss...............--------------------------------                                                                           528
Steer Creek, W. Va---------------------------------------------                                                                             980
Steinhatchee River, Fla.............------------------------------------------                                                              401
            Reach, La
Sterlington uMis.                                  .525
1694                                                         INDEX
                                                                                                                                   Page
Stewart Canyon Debris Basin, Ventura River Basin, Calif-......-.-..                                                   .          .         1298
Stewarts Ferry Reservoir, Tenn....-------------------..-..                                                                                  907
Stikine River, Alaska ..                    ...--------------------...                                                                     1547
Stillaguamish River, Wash .......----                                                                                               1514, 1518
Stillwater Harbor, Minn .--                                                                                                                 768
Stillwater Reservoir, Pa... . . . . . . . . . . . . . . . . . . . . 232, 240
Stockton Channel, San Joaquin River, Calif., improvement                                     ............                           1364, 1368
Stockton Harbor, Maine-............ . . ..                          . .. . ..               . ...             . ..         . . .             54
Stone Horse Shoals, Mass .....                    .          .                                                      ..........               32
Stonehouse Creek, Jefferson Co., Kans                                                                                                       798
Stones River, T enn-- - - - - - - - - - - -- - - - - - - - - - - -- - - - - - - - - - -                                                     907
Stonington Harbor, Conn......---                         ------------------------..-                                                         54
Stony Creek, Pa -.....-...           - -           -       -         -           -     -                - -            -          -        1008
Strattonville, Ohio .....                                                      -                          -.                               1025
Strawn Reservoir, Kans..................................                                                                              .     687
Stringtown-Fort Chartres and Ivy Landing, Ill ..._.......                                             ...                    ..........     719
Stuart Reservoir, Va ............................. ............                                             .                               289
Stumpy Pt. Bay, N. C-..... . . . . . . . . . . . . . . . .                                                                                  313
Sturgeon Bay and Lake Michigan Ship Canal, Wis __ ____                                       -                   --.----.
                                                                                                      --__----_____.__-._____-             1066
Sturgis, Ky....                             ....
                                         --....................         ......-------------------------------------...                      945
Success Reservoir, Calif .. .......... ..................                                                                                  1400
Sugar Creek levee unit, Indiana ......                                ________.
                                                                      .... ...                              ....           .          .     945
Sugar Hill Reservoir, Connecticut River Basin, N. H......                                              __......___                       69, 83
Suisun Bay Channel, Calif .....                 ------------------------                                                           1350, 1358
Suisun Channel, Calif ...........................-------------------------------------------                                              1356
Sullivan Falls Harbor, Maine............                        -------------------------------------...                                     54
Sulphur River, Tex. and Ark ........-------------------------------- 495, 517, 520
Summersville Reservoir, W. Va ..                                --------------------------------...                                         980
Sumpawanus (Babylon Creek) Inlet, N. Y__.....__........._____                                                   _         ___........       146
Sunbury, Pa-........-----..-.....-----------------------                                                                                    240
Sunday Creek, Ohio                 ---------------------..-.     ...                                                                        965
Sun River, Mont-----..........------------------------------------------                                                                    865
Superior Harbor, Wis----------------------------------------                                                                              1034
Supervision of the Harbor of New York __..__-........                              -_...       ______-.--.                         _.     ..143
Surry Mountain Reservoir, N. H ..........                                                                                                69, 74
Surveys, Interoceanic Canal___________....____...____---------------------------                                                          1635
     Of Northern and Northwestern Lakes                                                        ....-------------------------.... 1239
Susquehanna River, Pa., Md., and N. Y. Above and below Havre de Grace, Md__                                                                 234
Sutton Reservoir, W. Va-.. ....                  ..........                                                                            969,980
                                                                                                        .......-------------------------------...-...
Suwanee River, Fla. and Ga........-----------------------------                                                                             401
Swan Creek, N. Dak ...-.                                                                                                                    789
Swan Creek Inlet, Md............                                                                                                            218
Swan Island, Me.......             .      .           .          .          .        .       .                   ..            .              8
Sw an L ake, A rk- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -- -                                                   517
Swan Quarter Bay, N. C., to Deep Bay, N. C., waterway...............--.                                                                     313
Swansboro Harbor and Bogue Inlet, N. C...............................                                                                       299
Swanton Harbor, Vt .              --------------------                                                                                      146
Swift Creek, N. C                            .....                                                                                          313
Swiger, Whitney, Young-Hoblit levee, Illinois ...                                                                                         1148
Swinomish Slough, Wash.......----------------------------.                                                                                1486
Swoyersville, Pa --....... - - -               -- - -                                                                                       234
Sycamore, Wash., Los Angeles River Basin -..                                          ___...
                                                                                       -- .
                                                                                     __-.....       .             .          .            1268
Syracuse, O hio . . . . . . . . . . . . . . .- . .---. . . . . . . . . ..--                                                        979
Syracuse, Oswego River Basin, N. Y-..................                                                                            1234
                                           T
Taber Reservoir, Va                                                   -------------------                                          289
Table Mound Reservoir, Kans ..-------------------------------------.                               96
Table Mountain Reservoir, (Iron Canyon), Calif ...-......                                        1371
Table Rock Reservoir, Mo..-------------------------------------                              651,653
Tacoma Harbor, Wash           -. -     --..-.-.-----------.---..                           1501, 1520
Tallahatchie River, Miss-       --             ---------------------------------.. 528
                       ..--
Tallapoosa River, Ala .s.                                        --------------------...--         2448
Tallow Hill Reservoir, Ga......    .     ..---------------------------.                           341
Tampa Bay and Harbor, Fla-       --.-- ----                           -        -.-.               389
Tanana River, Alaska ..... . ..                        . . ..       . . ..          . ..    . . ..        . . ..        . .      1549
                                                                        INDEX                                                    1695
                                                                                                                            Page
                                     --------------------..
Tangier Channel, Va-........ .............................-----------------                                                  212
Tangipahoa River, La .                 ---------------                        ..----------------------                    -495
Tappan Reservoir, Ohio                ---------------- -------.-                       ------- ---------------....           960
Tar Bay, Md.....           ..-------------           ......................-------------------------------------             205
Tar  Creek, Ill    -.-.........
Tar Creek, Ill---------------- -----        ---------------                                                                 1148
                                                                                   --------------------- 1148
Tar River and Creek, N. C                   -----                       ---------------......-------------             313, 314
Tarrytown Harbor, N. Y----.....              - -----------                         ------------------ ----------------       146
Taunton River, Mass                    ----------------------...---.-.
                                             ....                  . .              ........ ..-------------------.       34,54
Taylor Creek, Fla..-------------------------------------------..                                                             .378
Taylor Falls, Minn-----.......-------------------------------..                                                              768
Taylors Bayou, Tex....................-------------.......                                                                   552
Taylorsville, Ky .................................                                                                     945,947
Tchula Lake, Miss................----------------------------------                                            -             528
Teche Bayou, La..-...                                                                                                   .--- 510
                                                                                                                       485,
     Tell
     City, md---------~--           -------------------------                                                            4,4
Tell City, Ind. ......  _
                    __...     ......
                                   . . . . . . . . . . .                                                               .....
                                                                                                                       945, 947
                 - - . -. -. .- . -.. . . .-95..
Templeton, Pa9.. ..                           . .. .. . . . . . ... . . .. .                                                           985
Tenants Harbor, Maine -------......................------------------------------                        --         54
Tenasillahe Island, Clatsop County, Oreg ...........
T      s        h      l          ,               o       u      .................
                                                               t1473,                                           1475
Tenkiller Ferry Reservoir, Okla ............                  .......                                             692
Tennessee River, Tenn., Ala., and Ky....                                                                          889
      Locks and dams...... ..............---
                                          ..... .        ......------. -.... -... _.....................          891
Tensas River, Ark. and La......              .        ..............................        __ . .. ..            528
Terminus Reservoir, Calif .....         ..........
                                               .      ..............................                  ....... 1400
Terrebonne Bayou, La--...-..---                   ------------------
                                           ..............                           -----------------             495
Terre Haute, Ind..                  ----------------------------------..-     ....--                              947
Terre Noire Creek, Ark... ........                     .. .... .. .....                                           533
Teton River, Idaho---                            __                                                             1532
T eton R iver, M ont -.. ---. .         . ..............................                                          866
Texarkana Reservoir, Tex.....-......                - ....-.-
                                                           --
                                                          ____-__-___-__-_-:                                497, 498
T e xas C ity C h annel, T ex............      . ..............
                                           ......--             ..............................                    5 68
Thames River Basin, Conn., R. I. and Mass......_                                      _-----------------            64
Thames River, Conn-----------------------....
                                           .           .                                                            42
The Island Reservoir, Vt..--               .......                                                             69, 83
Thief River Falls, Minn ....... ...                       .....                                        -          771
Thimble Shoal Channel and Norfolk Harbor, Va--                               .                                    270
Thomaston Reservoir, Housatonic River Basin, Conn. ....                                                             83
Thompson Creek and San Jose, Wash.....................-                      _     ..                           1268
Thompson Lake Drainage and Levee District, Ill...........                                                       1148
Thoroughfare Bay with Cedar Bay, N. C., channel connecting..                                                      313
Three Forks Mont....................                                                .                             866
Three Islands Reservoir, Tenn............                                                                         907
Three Mile Creek, Mobile River, Ala.............-.-.....
Tickfaw River, La., improvement of, including tributaries.....
                                                                             .                      .        -
                                                                                                            ....429
                                                                                                                  _.

                                                                                               ....               495
Ticonderoga River, N. Y ..........-.....-......                                                                    146
Tigre Bayou, La. _~..-............                            .... .. ... .                                       495
Tilghman Island Harbor, Md .                   ~........                                                                _.218
Tillamook Bay, bar, and entrance, Oregon-__.                                     .........                       1440
Tionesta Reservoir, Pa-----........ ~999
Tioughnioga River, N. Y-..................                                                                        222
Tolars Landing, N. C...                                                                                           308
Toledo Harbor, Ohio..---------.........                                                                          1175
Tolu Ky.............                                                                                               945
Tombigbee River, Ala. and Miss ...                                      -...------
                                                                        --                     .             4..
                                                                                                             _36, 452
                                                                                                           __..

Tombigbee and Tennessee Waterway...................                                                                448
Tom Jenkins Reservoir (Burr Oak), Ohio ....................
Toms River, N. J-...-....--.-.........-.-.-...
                                                                           '- ..          . . .   -          q- 980
                                                                                                            965,
                                                     ...                                                           190
Tonawanda Creek, N. Y ...                                                                                     :1228
            Tonawanda:Creek,
               n  a  H


Tobnianda Harbor, N. Y .
                          r    o       ,N
                                       N    .


                                          ...
                                                  Y ._.--------
                                                Y~------   -------
                                                               --
                                                    ...--- .....
                                                                -------------    ~-------------------------
                                                                                                 .. 1211
Tongue River Reservoir, N. Dak              ..                                  ...                                             771,
Topeka, Kans.-----------... --------------------                       ---       ---                                                   816
Tophet Brook, Hoosic River, Mass                                ------------...
                                                                              _.........-.                                             151
Toronto Reservoir, Kans .......       -----------------------------------------                                                        684
Totuskey Creek, Va..~..               -------------                                           -                                        258
Touchet River, Wash..... ....---------.......-.                                                                                    1532
Town Bluff, Tex . -------.... ..
Town Creek, M d ...-----------------                          ------------------------------------------------
                                                                                  -------------------.....
                                                                                                                                     04
                                                                                                                                ... 218
1696                                                       INDEX

                                                                                                                                                   Page
Tow n Creek, S. C.-.-......       .......... ....                         ....      .......     ..-     ..-.. ........-.-.-. ...... .                           319
Town River, Mass            .....................                                                                            21, 24
Townshend Reservoir, Vt ....................................................--------------                                                                 - 69,      83
Trabuco Dam, Calif --..... .... ...................                          - ...   ........ . .                       .__ ----------------                  1298
Tradewater River, Ky-
Tranquitas Creek, Tex .-.......
                                                --.
                                     ---...... --..-.. .. ................                                                                          919
Transportation Series Report .........                    ..-.............                                            ...........---------------------. 1555
Traverse City Harbor, Mich..........................--------------------------------...               1110
Treatment of Yuba River Debris Situation ..............--...... ................. 1563
Tred Avon River, M d ....-....                                  .-- ...--                ......................... 21
Trent River, N. C-.........                                             --.... .    ---         313,314
Trenton Channel, M ich ...-......-.......                     ....... ..... ...-.-...-..                . .............
Trinidad, Purgatoire River, Colo-                                  ......................            638
Trinity River and Tributaries, Tex ..................... --...... ---............. 577, 601, 607
Tri Pond levee unit, Illinois.................-                                                                 945
Troy, Ind                               -......-..                                                 . ... .............
Tualatin River, Oreg ...........................----------------------------------------                1472
Tuckahoe River, Md.................         .................                                        218
Tucker Bayou, Miss ..--------------                                                                                           -        --............              542
Tucker Lake, Ark             -..--..............
Tuckerton Creek, N. J ...                                     ...-.........   ......... ......... ...
Tucum cari, N. M ex -....     ..........                   ......-..-.. ...........-.... .......--..
Tug Fork, W. Va ...-..........-.....
Tujunga Wash channel, Los Angeles River Basin ........----------..... -..-..------------... -. 1268
Tule Lake, Tex                                             ------------                                                       ------                    589
Tule River, Calif .........       ..............................                          -------------------------                                 1400
Tulare Lake, Calif .............-----------------.                                                                                                1394
Tully Reservoir, Mass................................                                69, 77
Tully River, Mass .-                                                                     77
Tulsa and West Tulsa, Arkansas River, Okla .................... ------------------- 675
Tulsa, Okla., engineering district ...... ............. ........................ ....... 671
Tunungwant Creek, Pa............------------------------------------------998
Tuolumne River, Calif ...-      __ ---              ---      ---                            ----.....--.
Turners Cut, N. C ...-                                                                                  -   -     -    ----                                   --...        .
Turtle Creek Reservoir, Pa .....---------------------------------------                                 1025
Turtle River, Brunswick Harbor, Ga., improvement ....................----------------------..               340
Tuscaloosa, Ala ..........           ........-----------------------                                   438
Tuscarora Creek, N. Y..                ----------------------..--------.....----------- 225
Tuttle Creek Reservoir, Kans..---------.....                        ---------------------------- 814
Twelve Pole Creek, W. Va.,        flood   control reservoir .                  .....    .......... ___ 980
Twin Rivers, Wis ...............------------------------------.                                                 1072
Twitch Cove, Md ................-----------------------------------------------
Two Harbors (Agate Bay), Minn ....               ______............      .....                         1033
Two Rivers Harbor, Wis. -------------..... .....-------                          ....                             1072
Tyaskin Creek, M d .....               - - - - - - - - -.. . . . . . . . . .                           218
Tygart River Dam, W. Va...----------------------------------------.987
Tyrone, Ky                 ..................              ----------------------                                                                                          912
Tyrone, Pa........                     .........................                                                                                    240



U matilla I    rrb o r, O reg.... .. . . .................................................................
Umatilla River, Oreg....-------------------------------------------                                                     1532
UmpquHarbor and River, Oreg................                                                  ------------------------------ 144
Union Reservoir, Mo--------... .........------------------------------------
Union River, Maine............................                                                                        54
Uniontown, Ky          ....................--------------------------------------------- 945, 947
Uniontown, Pa-----          -------------------                                                                .............  .. ------
Union Township Drainage District Levee, Mo                           -------------------------.... 756
Union Village Reservoir, Vt...........            ..-------------------------------------                        69, 71
Upper Butte Basin, Calif----------------------------.......------------ 1371
Upper Chipola River, Fla----------..... ......................                                             ...-------------------------
Upper Grays River Area, Wash             ..................------------------------------------ 1475
Upper Machodoc Creek, Va .               ...........................--------------------------------------- 258
                                                                     INDEX                                                                      1697
                                                                                                                                                   Page
Upper Mississippi River Basin:
     Rock Island Dist.....--------------- .....         . .............--                       ----- ... ..........                755
     St. Louis Dist-------..... -   .. ..... ---....
                                    ------...                             ...... ........                            ..        727, 728
     Chicago Dist..-........ ......-.                                                                                   .....      1147
     St. Paul Dist........-----------............---------------------------                                                        788
Upper Narrows (Harry L. Englebright) Reservoir.............--------------------                                                    1565
Upper New York Bay, N. Y...-------------.....-------..------..-----                                                  -------        107
Upper Puyallup River, Wash-.......----------.............----------                                ..........------------.---... 1523
Upper Thoroughfare, Deal Island, Md ........................-------------------------------                                         218
U pper W hite R iver, A rk ..... ....... ... ......-..                   .-............         .................           ..      650
Urbanna Creek, Va                             ------
                                     ---------....-....
                                             ............ .     ..... .                  ......   ..........                        258
U. S. Lake Survey.........                 .............         -----------                                                       1239
                               .... --.. ........-.......------------ - .........
U tica, Ind. -----------........----..                                         -.........              ... ...       ......         945


Valdez H arbor, Alaska............. .........                                   ............... . .............. .....                       ........     1547
Valley Center and Wichita, Kans.................                                 -..........                ........             ....       .........      673
Valley V iew Ky ..                  .....            .        ........ ........ ......... .                     ... ......         .                       9.
                                                                                                                                                           9.........1..
                                                                                                                                                           913
Van Buren, Arkansas River, -Ark.....__......                                  ........................................                                     668
Vanceburg, K y.......                                                                . . .............                 . . .........            ...        979
Vancouver, Wash., Columbia River....... .............                                    .........._ .            .......                .........        1429
Venice Drainage and Levee District, Ill-...................~..... . ......                                                    .... ......                  725
Venice Inlet, I~la-...... --- -.................................                                                                                           384
                                                                                                                                          . ...------------------------
Ventura, Ventura River Basin, Calif..-.....-.................-..-.............-               -.....                                                      1298
Verdigris River, Kans., and Okla...........                               ... ............ .......-..............                           644, 684, 700
Verdugo W ash., flood control................... ............. ............                                              .............                    1268
Vermilion Bay and River, La............--.                                                                                                                 510
V erm ilion B ayou, La.......... ....... ___--........ ..........-                       ......... ___...............                      ...             495
V erm ilion Lock, La-................................                        _      -
                                                                         ....-. ...... ........... ..--.---..       .         .......-...
                                                                                                                                        ....          ..   462
Vermilion Harbor, Ohio......__..............                          ...-..........                                  ... .             .........         1227
Verney M ills Dam, N. H.......                     ........        ...... ...                  ..._........                                        .         59
Vero Beach, Fla........... ............................                                                                                                    358
V erona, C alif...--........ ........        ......... ........... .............. ...               ....... .......           .. . . .                    1349
Versailles, Ky....                                                                                                                                         913
V evay, Ind-.......................................                                             -..........--                                              945
Vicksburg, Miss., engineering district                                                                                                                     5...
                                                                                                                                                           523
Victory Reservoir, Connecticut River Basin, Vt..                                                            .....                  .....                 69, 71
Villa Park Dam, Calif ..................................                                                                           ....            1288, 1298
Village Creek, White River and Mayberry districts, Arkansas..........                                                                                       668
Vincennes, Ind.................------------.-..                                     ....................        ....               ...        .... 935,945
Vineyard Haven Harbor, Mass...                                 .......                                                                                       54
Vinton Waterway, La...                    .................                                                                                                 496
Virginia Channel...........                             .........                                                                                           244
Virginia Key, Fla..                     .            ..............                                                                                         375
                                                                           W
W abash, Ind...... .                                             . .......-........... .....                                                         947
Wabash River, Ind. and Ill                   .........                 ....                                                                     936, 946
W abasha, M inn., harbor............. ...- ...... ......                ..... ..                                                                     737
Waccamaw River, N. C. and S. C                                                                                                                       326
Waddington Harbor, N. Y......            __         ......                                                                                         1227
Wahkiakum Diking District No. 4, Oreg                                                                                                               1473
W ahpeton-Breckenridge-...........                            .........
                                                                    ......................                                    -:                     772
W ake Island H arbor............. . ......... ... ..... .. .....                ___..                                   _                           1341
Waldo Lake, Oreg .........-.......                                                                                                            1455, 1476
Waker Island Oreg...-                                                                                                                               1428
Wa     - Lake Canal, M iss------------------                    .- . .......                 ...                                                     542
Walla Walla, Wash. Engineering District-.....................         --            _-    -_--                                                   . 1527
Walla W alla River, Wash ............ -..........          .....       ..          ___                      -__.   -               .                1537
Wallabout Channel, N. Y....................                                                                                                     107, 146
Wallace Bayou, La                    .....                                                                                                           517
W allace Channel, Pamlico Sound, N. C ... ... __._..__-..............                                                                  ....          313
Wallace Lake Reservoir, La-.............. ................. ............                                                                       497, 505
Wallace, W . V a........... ...             . ........ .... .... ....                                                 ....        ........         1030
Walluski River, Clatsop County, Oreg.............................                                                                                  1475
1698                                                    INDEX

                                                                                                                  Page
Walnut Creek drainage area, Calif ...---.........                                                                1268
Wapato Waterway, Tacoma Harbor, Wash ..........__..
Wappinger Creek, N. Y....
                                                                                     .................           1502
                                                                                                                  146
Wareham Harbor, Mass -...                                                                                           54
Warm Creek, Calif-.........-..--                                                                                 1294
.Warren River, R.
               R. I .             ...
Warren River,     I---------------------------------------------------------------    --------------               544
Warrenton diking district No. 1, Clatsop County, Greg...                                               __._...   1475
Warrenton diking district No. 2, Clatsop County, Oreg.:. _ _                                     1475
Warrenton diking district No. 3, Clatsop County, Oreg....................                  .     1475
Warrenton, Oreg. mooring basin .........      ....---------------------                          1433
Warrior Lock and Dam, Ala-....                                            _                       439
Warrior River, Ala ..................--                                                           436
Warroad Harbor and River, Minn.                                                                   761
Warwick River, Md -218
Warwood, W. Va..-.-.................                                          ..      .          1025
Washington Bayou and Lake, Miss _----..                                     ...                   528
Washington Canal and South River, N. J .                                                          146
Washington, D. C.:
     Aqueduct .......      .
                    -----------                                                                   252
     Engineering district.                                                                        243
     Potomac River...........                                                        ... .        258
     Harbor at--..............       -                                                       243, 266
Washington Island Harbors, Wis.....                                                              1113
Washita River, Okla_.......-----------.-.----                        .                            672
Waterbury, Winooski River Basin, Vt....-..-----------                                             153
Waterbury Reservoir, Winooski River Basin, Vt..                                                   153
Waterchestnut elimination, Washington, D. C.. ..                                                  248
W ateree River, S. C .... ... . . . . . . .. . . ..                              . . .            326
Waterford, Hudson and Mohawk Rivers, N. Y                                           _~....        153
Water hyacinths, removal of, from Florida, Alabama, Mississippi, Louisiana,
  and Texas waters .. __... ._ .                    ....-........                        399,431, 493
Water Valley Reservoir, Ark__                                           ..                        651
Waterway on Coast of Virginia                             -........                               213
'WaterwayConnecting Tombigbee and Tennessee Rivers, Ala. and Miss....                             448
Waterways Experiment Station, Vicksburg, Miss ....................                               1629
Watkins Glen, Oswego River Basin, N. Y_....                              .....                   1236
Watts Bar, Tenn---.                                                                ...            891
Watts levee, Illinois                                                         ............       1148
Waukegan Harbor, Ill...                                                                          1115
Waverly, W. Va................                                                                    979
Way Cake Creek, N. J...__             .                                   .    .........          146
Waynesboro, Va., flood control ._..                    .               .-----                --_       i           266
Webb District Improvement Co., Columbia County, Oreg....          .         1475
Webbers Falls Dam and Reservoir, Okla ...                                    644
Weehawken-Edgewater Channel, N. Y. Harbor, N. Y .......
                                                   __      ........   .      113
Weiser River, Idaho ..........-                                             1532
Welles Harbor, Midway Island                                                1341
Wellfleet Harbor, Mass........                                                54
Wellsburg, W. Va....                                                        1025
Wells Cove, Md -                                                             201
Wells Harbor, Maine                                                 .....     54
Wellsville, N. Y..1229
Wellsville, Ohio .                                           .      . 1021, 1025
Wenatchee River, Wash ............                                          1514
Wenkel Drainage and Levy Dist., Ill -.                                       723
West Bridgewater, Pa............._____ ___ ..             ............ 1025
West Brookfield Reservoir Connecticut River Basin, Mass..                 69, 83
West Canaan Reservoir, donnecticut River Basin, N. H .            ....... 69,83
W estchester Creek, N. Y.......................................
                                                      ... ......             146
Westcott Cove, Conn.....                                                      54
Westerly Creek, Colo_ -_...                                                  847
Westfield River, Mass            ...-      .........                   .- 78, 81
West Fork of Mill Creek Reservoir, Ohio ...        ..............            924
West Fork River, W. Va....                                                                                       1025
West Hill Reservoir, Blackstone River Basin, Mass..........                                                     63, 83
Westland District Improvement Co., Columbia County, Oreg... .                                                    1475
                                                                        INDEX                                                                  1699
                                                                                                                                                   Page
West Matanzas, Ill.....                                                                                                                           1142
West Monroe, La..~.....                                                           .....                                                             537
West of Benedict, Kans.                             ..                                                                                              700
West of Elk City, Kans ..........                                                                                                                   700
West of Fredonia, Kans.......                                                                                                                       700
W est of M orrilton, Ark--_.... .                     -           .............................                                                     668
West Oneonta Reservoir, N. Y __---..                                     -...........................--.....
                                                            ---..............                                                                      220
West Peterborough Reservoir (now Edward MacDowell), N. H._                                                                                          59
W est Pittston, Pa .. . ..... .....                                     ........ ..... ...... ........
                                                                   -...........                                                                    240
West Point, Ga-..-...                                                                                                                              448
West Point, Ky-......-                                                                                                                             945
Westport District, Oreg..                                                                                                                         1475
Westport Harbor, Conn....                                                                                                                             54

Westport, Ky......                                          ....                     ...                 ......                               945
Westport River, Mass......                                                                                                                      54
Westport Slough, Oreg....--                                                                                                                  1452
West River, Conn ....                                                                                                                           54
West Springfield, Mass ....                                                                                                                 70, 80
West Terre Haute, Ind..                   -                       ..                                              .                           945
Westville Reservoir, Mass.........                                                                                              .....
                                                                                                                               .....      . 65,83
WTeymouth Back River, Mass....                                                                                                                  54
Weymouth Fore River, Mass ..                                                                                                                21, 54
Whatcom Creek Waterway, Wash_                                                                                                                1483
Wheeling-Benwood, W. Va...._..                                                                          ......                        -1022, 1025
White Dam, N. Y.--------.......-.....                                                                                                          148
Whitefish Point Harbor, Mich...                                                                                                              1050
Whitebird Creek, Idaho .........        __                                                                                                   1532
White Lake Harbor, Mich.....                            .......                                                                              1099
White Oak Levees, Cape Fear River, N. C..........-.._._..                                                    .                                314
White River, Ark., (below Peach Orchard Bluff) navigation.......                                                                              545
White River, Ark. and Mo...................................-                                                                                  650
White River, Ind.......            ...                                                                                                        919
White River, Wash.....-                                                                                                                      1521
Whitfield, Ala...........                                                                                                                      438
W hitings Creek, Va                            ...
                                               ....               ..            -...... ..--   -..
                                                                                            -.......        .                                  258
Whitlow Ranch Reservoir, Queen Creek, Ariz                                               .           .....                                   1298
Whitney Point, N. Y.................                         ..            .                                                                   222
Whitney Point Reservoir, N. Y._...........                                                                                                     221
Whitney Reservoir, Brazos River, Tex.... .-.                                                 ..          ___._..                               618
Whittier Narrows flood control basin, Calif .....                                                                                            1268
W ichita and Valley Center, Kans__.._ ........... .....                                            ... ___.....                                      673
W ickford Harbor, R. I........                                                         ...................                                 54
Wicomico River, Md .....                  .                 ..                .               . ..                    .                   206
Wiedmer Chemicals drainage and levee district, Missouri                                                               ....                730
Wilcox, Pa ...-... .       .-.. ..........          .._...
                                                         ...... ........           .............              .... . .              ... 1.....
                                                                                                                                 ....     025
Wilder, Ky ................          .                                                                                                    945
Wild Rice River, Minn ....                                                                                                                772
                                                                                                                                      -....
Wiley Creek Dam, Oreg                                                  .....................                                       1455, 1476
                                                                                                                               .........
Wilkes-Barre--Hanover Township, Pa ........................                                                           ..                        . 242
                                                                                                                                           . 240,
Willapa Harbor and River, Wash.....                                                                                            ... .. ... . . .   15 11
Willamette River, Oreg.:
     Bank protection.....                   ..                                                                                                         1470
     Flood control in basin...__......._______.......___                                                                                               1454
     Improvement above Portland, and Yamhill River......... .                                                                                    . 1421
     Improvement at Willamette Falls-.                               .           ...                 ~~.......-..  .....     _....
                                                                                                                                 _... . 1425, 1455
     Improvement below Portland..                                            ............                        ..                                    1427
Williamsport, Pa............................                    .       .. .               .                                                            235
W illiamstown, W. Va ........................                        ..........                        ........                                         979
Williamsville Reservoir, Connecticut River Basin, Vt........ ......                                                           -.......................67,83
W illiston, N. Dak....--------------   =------                         . -.................                                                             851
Willoughby Channel, Va......                                                                                                                            288
Willow, Ky-.................                                                                                                                            913
Willow Creek, Colo-.....-                                                                                                                               638
Willow Run, Ky......                                .....................                                                                            921
Wills Creek Reservoir, Ohio.......................                                                                                                   960
Wills Creek, W. Va.....                                                                                   ........                                   261
1700                                                                INDEX

                                                                                                                                                  Page
Wilmington Harbor, Del. .............                                                                                                             168
Wilmington Harbor, N. C ......                                    ...........                                     -..                             2
Wilmington, N. C., engineering district .....                                   ----------------------------                                      297
Wilson and Wenkel and Prairie Du Pont drainage and levee districts, Illinois ...                                                                  723
Wilson Canyon and Mansfield St. channel, Calif----........                                            -------------------. 1268
Wilson Harbor, N. Y                     ....--------------------------------
                                    --------.........                                                                                          1227
Wilson Point Harbor, Conn .................                                   .          ------------------------------------------                 54
Wilson, Ala     ---------------..-----------------..-----.......-------....------                                                                 891
Winchester Bay, Oreg -----.--.                             -            --------                 .---         ---..---------- 1445
Winery Canyon, Calif           -------------               -------                                                                             1268
Winfield, Kans......---                                                               --------------------------.                                 700
Winfield, W. Va------------------------------------------------......                                                                             954
Wings Neck, Mass    ........   ----...............                       .....................-----------------------------------------------       29
Winnebago, Lake, harbors on .......................                                                                                            1062
                                                                                                              ............-------------------------------------.
Winnibigoshish Reservoir, Minn...........                       ------------------------------------...                           ... ..          764
Winona, Minn., basin                                                                                         ....           ---           736,737
                                                                                                                                         736,....
Winooski River, Vt-------------------------------........--------------...                                                                        153
Winsted, Connecticut River Basin, Conn ........... ......................----------------------------. _ 70, 82
Winter Harbor, Va............------------------ ----                                                --             -----                          288
Winterport, Me .. .,~...........................                                                                                                     66
Winthrop Beach, Mass., beach erosion control ......................---------------------------                                                      54
Winthrop Cove, New London Harbor, Conn                                  .....................                                                       41
Winthrop Harbor Mass .....                  ------......----------                                                                                  54
Winyah Bay, S. C ------.........................................                                                                          299, 316
Wisconsin River, Wis-.....                                                                                                                        770
W ister Reservoir, Okla  _............... . .                            .......................
                                                                              -     _...... -               --                   - - - -
                                                                                                                       - - - -.................   694
Withlacoochee River, Fla                                                        -..................----------.......                              396
W olf Creek Reservoir, Ky-         ......            ..............        ......... . ............                ............... - 899, 907
Wolf Creek, Okla -------------....-------....
                                .............................--------------------------- 676
Wolf River, Tenn. and Miss .....                            --
                                                             --.......             ..................---------...........                    448,545
Wolf River (Memphis Harbor), Tenn..................                        __                    ...         .        ......      .........        543
Wolf River, Wis .........                                                                                               ......                    1.....
                                                                                                                                                 1062
W oodbridge Creek, N. J                   __ -..........           ......... ...... .......
                                                                                        -......          ...          -...... . . 146
W oodbury, K y ..... ............ ....               --
                                                   .......... ..... .. ........ ...... ..........                                    ...........   916
                                                                                                                                                   190
Woodbury Creek, N. J-....
Wood Island Harbor, Maine, and the Pool at Biddeford............-------...-..----                                                       --           54
Woodlands, W. Va............--------------------....                                    ---------------------                                      979
Wood River drainage and levee district, Illinois.............------------------------- 726
Woods Brook N. Y ....................... ---------------------------------------------                                                             148
Woods Hole Channel, Mass                   -------------....-----------..--..                                    ------...-----..............---. 54
Woodson drainage district, Columbia County, Oreg..............................                                                            1473, 1475
Woonsocket, Blackstone River Basin, R. I
Worcester diversion, Blackstone River Basin, Mass ..........
                                                                          - -.           .............
                                                                                          ~..                  ..................             . 63, 83
                                                                                                                 .....-.................. 63, 83
Wrangell Harbor, Alaska, navigation.........-
Wrangell Narrows, Alaska, navigation .
Wrightsville, Winooski River Basin, Vt...
                                                                    -      -...
                                                                     ............
                                                                          ................................
                                                                                                                ....................
                                                                                                           -.....
                                                                                                     . ... .........
                                                                                              ..........                            .....
                                                                                                                               ..............
                                                                                                                                                  1547
                                                                                                                                                  1547
                                                                                                                                                   153

                                                                          Y
Yadkin River, N. C...           ................                             .........            ............           ................ .        326
Y ak ima R iver, W ash..............................................                                                                              1523
Y alobusha River, M iss..................... .            .... .......................                         ..                                  528
Yamhill River, Oreg                                                       .....                                                                   1421
Yaquina Bay, Harbor, and River, Oreg .... ..........                                .......-.... .         .... ..... ..........         1442,    1452
Yazoo River, M iss ............                                                                ............ .. ......
                                                                                      _...-.......__..                                             528
Ybor Channel, Fla -............                                                        ........................                                    390
Yellow Creek, Ky-.........-........................                                                                   . .             .            895
Yellowstone River Basin, Mont. and Wyo---------------.~_...                               ............................----------            -      863
Yellow Water River, La ....------------------------------------------                                                                              517
York Harbor, Maine ...____.......                                           _---
                                                                     ..--.----                   ...-.                                              54
York, Pa .---.---.-.         --        --....-....                                               -------------------------                         238
York River, Va ........------....--                 .....................                                                                          288
                                             INDEX                                              1701
                                                                                                 Page
York Roller Mill Dam, Pa..         ............     ....................             239
York Spit Channel, Va          ---------------------..----...            ------- 199,269
Youghiogheny River, Pa-------------------------------.......----------- 996
    Flood control reservoir-..                                                      1015
Youngs Bay and River, Oreg           ....-- -----------------------------------.    1452
Youngs River Dikes, Clatsop County, Oreg..........---------------------------.. 1475
Yuba River, Calif., treatment of debris situation, construction of restraining
  dams     .........---------------------------...------.................. 1349, 1563
                                                    z
Zanesville, O hio................................                                                979
Zippel Bay Harbor, Minn., improvement..                                 ..........-----------    770
